Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
foundations
A. S. Hoback and K. Z. Truman
Department of Civil Engineering, Washington University, St. Louis, Missouri
63130, USA
(Received 15 July 1992; revised version accepted October 1992)
The layouts of steel piles under slab foundations are optimized to find
the least weigtlt systems. The pile inertias and batters are varied using
an optimality criteria approach. A Gauss-Seidel procedure is used to
evaluate the Lagrange multipliers. The types of design limits controlled
by the optimization are the pile stresses, displacements, sizes and
orientations. Three examples are given, two of them are dam structures,
and the other is a control tower foundation. The first dam structure
demonstrates that a feasible design can be reached even though the
initial design is highly infeasible. The control tower foundation demonstrates that significant weigtlt reductions can be achieved given an
understressed initial design.
Keywords:
criteria
Notation
A
ci
d~
hj
Ixx
Iyy
m
Mi
n
N
Pi
r
v
Vi
Wr
0
2j
p
~b
Pile layouts
The cross-sectional properties and the orientations of the
piles will be variables. All of the pile tips are at the same
depth within a design regardless of batter. The initial coordinates of the head of the piles will be fixed, and the pile
spacing will not change.
The batter of the piles is the ratio of the depth of the
pile to the horizontal distance between the pile head and
tip as shown in Figure l(a). Phi (4) is the angle of
rotation of the pile about the vertical axis from the global
X-axis as shown in Figure 1 (b), measures the pile flange
alignment as shown in Figure 1 (c). The batter is the only
topological parameter that is variable in the examples
shown. The angle ~b is not a variable in the examples
because symmetry exists in each example; it is a variable
when out-of-plane loads are applied.
Initially the cross-sections are not restricted to discrete
HP-14 steel pile sizes which are available from fabri-
0141-0296/93/050379-07
1993 Butterworth-Heinemann ktd
Pile Cap
The maximum size of HP-14 section available is 1,., -1220 in 4 (50780 cm4), and the minimum is Ix~ = 729 in ~
(30343 cm4). Similar equations can be developed for
regular and irregular cross-sections 5.
Pile
Batter
a
1.0
Pile
b
X
Y
HP
Sections
x
Y
0 -- O. d e g r e e s
0 - 90. d e g r e e s
(1)
(2)
cx = 1.2110
(3)
10 -3
380
(4)
Thick concrete monolith foundations are analysed assuming that the pile cap is rigid in the manner of Basic
Pile Group Behaviour 6. The structural foundation is
assumed to rigidly connect all the piles. Therefore the pile
cap has only six degrees-of-freedom, three translations
and the three rotations.
The pile group stiffness coefficients are calculated in
the manner of Saul 7. A beam on an elastic foundation
theory is used to find the lateral pile stiffness. The pile
and soil interaction is represented at the head of the pile
by a linearly elastic pile stiffness. The global stiffness
matrix is calculated by summing the coefficients from all
the piles. The displacements in the stiffness method are
found by inverting the stiffness matrix and multiplying it
by the applied loads.
Stress interaction equations are used to evaluate the
feasibility of the piles 6. The top portion of the piles are
subject to axial load and bending. The point of maximum
moment is a function of the soil characteristics and the
pile connection fixity. The bending moments dissipate in
the top portions of the piles, therefore, only the axial
forces are carried through the lower regions. An increased factor of safety is used in the lower regions
because the pile tips are subject to damage during
driving. The axial load at the tip must be less than the
damaged cross-section capacity and the soil bearing
capacity.
Pile structures are subject to a variety of design limits
or constraints. Some of the constraints are:
(1) Member stress constraints. The most highly stressed
member in any group is prevented from becoming
over-stressed
(2) Size constraints. The cross-sections are prevented
from advancing beyond the maximum or minimum
section sizes available
(3) Interference constraints. Piles cannot pass through
one another. In two-dimensional problems and the
less complicated three-dimensional problems this
constraint can be established by preventing the pile
tips from meeting
(4) Minimum batter constraints. The piles may not be
battered with a slope beyond a specified angle
(5) Displacement constraints. Each displacement component may be limited to a specified value
The constraints are represented by the value hj wherej
is the constraint number. Constraint j is satisfied when
hj < 0, exactly satisfied (active) when hj = 0, and violated
when hj > 0. A design is feasible when all the constraints
are satisfied. A computer program O P T P I L E was
created for the analysis and optimization 8. All of the
above constraints may be controlled by user specified
values.
(5)
wT = T, p, v,
/Ohjdh,\
I c3dl c3di I
i=l
- ~ 2j
j =a
ew,
Ohj
C~dl
-i
i = 1 .... ,n
s=l
i=I
Ohj
i=1 ~//
j = 1..... m
(12)
/OhjOh,~
- - - c~dil
--n I -c3dl
(6)
".2. Ohj
Od~
\
j = l ..... m
(7)
hj<_O j = 1..... m
(8)
j = 1..... m
~ - - ~ d,
Examples
The design process consists of estimating an initial design
and then performing an optimization. The first example
is a dam structure, it demonstrates that given a highly
infeasible initial design the optimality criteria algorithm
can find a feasible design and then find the optimal
design. The second example is a control tower foundation. The third example is an existing dam structure.
The piles are placed in groups which maintain the
same sizes and batters in each group. This grouping is
also called linking. The individual piles in a group are not
allowed to independently vary in size or batter. Placing
piles into groups provides the consistency that is desired
when installing the piles.
c~di
(10)
Ohj
Ahj=h~ +1 - h ~ = i=lWJ-Ad
iuui
j = l ..... m
(13)
Od~
(9)
/-
j = 1..... m
i=1 OWr
2jhj=O
c3di /
)lq=
Example 1
This example is a dam with 29 piles. The piles are
arranged in three rows. The piles in each row are linked.
Linking causes the piles to maintain the same orientation
and cross-section as the other piles in the same row. The
loading is shown in Table 1. The initial pile layouts are
(11)
Tab~ 1.
Load
case
Px
(kips)
P
(~ips)
Pz
(kips)
M
(~-k)
-1300
1500
-10000
1580
M
(~V-k)
M
(~-k)
/ xx
(in 4)
Batter
~
(degrees)
729
100
90
2
3
1
2
3
729
729
729
729
729
100
100
3.96
2.35
4.14
90
90
270
90
270
0
0
0
0
0
Spacing 5'
LJ~ 2
~p,
Ir
~3
-q-
(degrees)
Ir
~
[~
10
.~Y
A r r o w s indicate
batter direction.
--T
"~3
.J
N*
N"
N'19
Spacing 5'
~'~ 11
Groups:
29 I r
N-~19
~ _ 10
2~
3m
Arrows indicate
batter direction.
N*
N*
N"
Groups:
2 9 "~
2[]
3
Cap
Cap
Spacing
15'
i
I Depth" z'
Pile group 3
II
D e p t h = 70'
Figure 2
382
Figure 3
the final design is absolutely the best design. The KuhnTucker conditions guarantee that this is the locally
optimum design. Multiple starting points could be used
to search for the absolute best design.
3E5Weight
Obs.)
SiDeD ~
2E5.
~D
1 E5
Figure 4
D~D~D
I
1
Iteration
Example 2
This example is a control tower with 18 piles arranged in
two rings. The initial design is a design example which is
analysed in the CPGA User's Guide 9. This design will
now be optimized with the optimality criteria method.
The only alterations to the design are that the depth of
piles 1-12 is held at 65 ft (19.81 m), and the depth of piles
13-18 is held at 74 ft (22.56 m). The loading is given in
Table 3, and the initial layouts are given in Figure 5 and
Table 4. Piles 1-12 were originally vertical. The piles in
each ring will maintain the same size and slope as the
1E5r
Group
Weight ? \
L 6 piles
@ 60 de 9,
<k
2,
9E4f
1S piles
\
0.____~0 ....
.-
0 ~ 0
3
4
Iteration
30 de 9
8E4
I
1
-X
I
2
..._0/0_.____0_~0~0Limit 0,35"
Displ.
Camp. 1
(inches)
"=0- - - (
I "'"
+
0.000
Figure 5 Initial pile layouts for example 2. (a), plan view; (b),
elevation view
3
4
Iteration
Load
P
(kips)
Pv
(kips)
Pz
(kips)
Mx
(ft-k)
My
(ft-k)
M,
(ft-k)
- 142.8
1272
5600
0
7
Pile
/xx
group
(in 4)
1
2
1
2
904
729
729
729
Batter
4.
100.
8.80
14.81
(degrees)
(degrees)
See Figure 5
See Figure 5
Unchanged
Unchanged
0
0
0
0
383
Example 3
This example is a dam with 240 piles arranged in three
groups. This example is a design which is analysed in the
CPGA User's Guide 9, it will now be optimized. The only
alteration to the design is that all pile tips reach a depth
i 57-:26-i
EL -13 --
-20
Group
Group
Group
_~- 3,5'
61
95'
_I
--
00000
[]
O00OO
[]
[]
[]
[]
[]
00000
eeeeeeeeeee
00000
eeeeeeeeeee
00000
eeeeeeeeeee
[]
[]
O00OO
[]
[]
[]
[]
[]
[]
[]
[]
[]
[]
Group
[]
[]
[]
i0@9':90'
eeeeeeeeee
[]
00000
[]
eeeeeeeeee
[]
OOOOO
[]
eeeeeeeeee
61~
0
11@9'=99'
8'
llseeeeeeeeeee
[]
eeeeeeeeeee
[]
[]
[]
00000
eeeeeeeeeee
O00OO
eeeeeeeeeee
O00OO
eeeeeeeeee
0000~0
eeeeeeeeeee
[]
[]
0
O
[]
[]
[]
0
O
[]
0
....
[]
[]
[]
0112
240
35' ]
b
Figure 8
384
Inital pile layouts for example 3. (a) elevation view; (b), plan view. (1 ft = 0.3048 m)
106'
[]
1~ 58 pites
60 piles
128 piles
Pile o p t i m i z a t i o n : A. S. H o b a c k a n d K. Z. Truman
Tab~ 5.
Loading forexample 3
Load
case
P
(dips)
P
(kips)
Pz
(kips)
M
(~-k)
M
(~-k)
Mz
(~-k)
-12000
20000
-1.E6
Tab~ ~
Iteration
0
7
Pile
group
~x
(in 4)
Batter
1
2
3
1
2
3
729
729
729
729
729
729
100
2
2
6.58
3.96
3.92
2.00E6Weight
Obs.)
1.50E6
P-'--~-O~o------'O- - - - - 0 ~ 0
1.00E6
0
I
1
I
2
0
I
3
4
Iteration
I
5
I
6
Conclusions
Concrete monolith foundations supported by steel H P 14 piles were optimized. An optimality criteria method
was selected because it is suitable for large optimization
problems.
The pile cross-sections and pile batters were allowed to
vary. Initially the variables were not held to discrete
values but were allowed to change in a continuous
manner.
The examples included dams and a control tower. The
first example demonstrated that a feasible design can be
obtained even though an initial design is highly infeasible. The second example demonstrated that constraints
~
(degrees)
90
90
270
270
90
270
0
0
0
0
0
0
(degrees)
Acknowledgment
The authors wish to thank the US Army Corps of
Engineers for partially funding this work under contract
D A C W 3989M3044.
References
1 Hill,J. L. 'User's guide: computer program for optimal design and
analysis of pile foundations (PILEOPT), Instruction Rep. K-81-5
US Army Crops of Engineers, 1981
2 Gellatly, R. A. and Berke, L. Optimal structural design 1971, USAF
AFFDL-TR-70-165
3 Venkayya, V. B. 'Design of optimum structures', Comput. Struct.
1971, 1, 265-309
4 Manual of Steel Construction (8th edn), American Institute of Steel
Construction, Chicago, IL, 1980
5 Cheng, F. Y. and Truman, K. Z. 'Optimization algorithm of 3-D
building systemsfor static and seismicloading, In Ames, W. F. and
Vichnevetsky, R. (Eds) Modeling and Simulation in Engineering Vol
3. North-Holland, Amsterdam, 1983, pp 315-326
6 'Basic pile group behavior', Tech. Rep. K-83-1 CASE Task Group
on Pile Foundations, US Army Corps of Engineers, 1983
7 Saul, W. E. 'Static and dynamic analysis of pile foundations', J.
Struct. Div., ASCE 1968, 94, (ST5), Prec. Paper 5936
8 Hoback, A. S. and Truman, K. Z. 'Optimization of steel pile
foundations using optimality criteria', Contract Rep. ITL-92-1, US
Army Corps of Engineers 1992
9 'User's Guide: Pile Group Analysis (CPGA) Computer Program',
Tech. Rep. 1TL-88 CASE Task Group on Pile Structures and
Substructures, US Army Corps of Engineers, 1988
385