LEVEL 2
OBRAS PROVISIONALES
Q006
LEVEL 3
Bill Quantity=75.00 ml
L008V
Operario
20.93/hh________________*1.00
2.62
196.50
L012V
Peon
15.71/hh________________*2.00
3.93
294.75
APPLIED FACTOR
6.55
491.25
260.00/ml_______________*1.00ml*50%amortiz
130.00
9,750.00
13.90/m2________________*2.40m2
61.83
4,637.25
576.00/rll______________/200ml
5.34
400.50
________________________*139/[LC]
APPLIED FACTOR
Net Rate
L= 5.82
Q001
M= 197.34
67.16
5,037.00
203.71
15,278.27
S= 0.55
Bill Quantity=60 m
01.01.02 acondicionado)
[OFI1]=60 m2
[MC]=5.00 meses de contenedor
?[GGP]=1.0000000
1) CONTENEDOR
================================================
#
T880/005 Contenedor Oficina
700.00/mes______________*2und
116.67
7,000.20
SB024
11120.00/glb____________/[MC]
185.33
11,119.80
APPLIED FACTOR
________________________*[MC]/[OFI1]
302.00
18,120.00
Oficina
83.40/m2________________*60m2
83.40
5,004.00
SB014
Armado y desarmado
695.00/vez______________*2veces
23.17
1,390.20
APPLIED FACTOR
________________________/[OFI1]
106.57
6,394.20
37.07
2,224.20
27.34
1,640.40
4) DESMONTAJE DE OBRA
SB066
5)
Desmontaje de obra-Acarreo-Transport
1640.20/glb_____________*1of/[OFI1]
ALQUILER OFICINA
SB023
Alquiler oficina
111.20/m2_______________*[M]/[OFI1]*0
=
Net Rate
S= 356.30
M
19:39
26/02/14
0.00
472.97
28,378.20
E= 116.67
1.
AI
MEP2013
Q001a
Bill Quantity=45 m
[OFI2]=45 m2
[MC]=5.00 meses de contenedor
?[GGP]=1.0000000
1) CONTENEDOR- ETAPA DE EXCAVACIONES
================================================
#
T880/005 Contenedor Oficina
700.00/mes______________*1und
77.78
3,500.10
SB024
11120.00/glb____________/[MC]
247.11
11,119.95
APPLIED FACTOR
________________________*[MC]/[OFI2]
324.89
14,620.05
Oficina
83.40/m2________________*45m2
83.40
3,753.00
SB014
Armado y desarmado
695.00/vez______________*2veces
30.89
1,390.05
APPLIED FACTOR
________________________/[OFI2]
114.29
5,143.05
37.07
1,668.15
4) DESMONTAJE DE OBRA
SB066
Desmontaje de obra-Acarreo-Transport
1640.20/glb_____________*1of/[OFI2]
=
Net Rate
S= 434.92
Q001b
36.45
1,640.25
512.69
23,071.20
556.00
8,340.00
556.00
8,340.00
E= 77.78
Sala de reuniones
Bill Quantity=15 m
01.01.04
[OFI2]=15 m2
[MC]=5.00 meses de alquiler
?[GGP]=1.0000000
1) CONTENEDOR
================================================
#
SB023
Alquiler oficina
111.20/m2_______________*1und
APPLIED FACTOR
________________________*[MC]
Oficina
83.40/m2________________*15m2
83.40
1,251.00
SB014
Armado y desarmado
695.00/vez______________*2veces
92.67
1,390.05
APPLIED FACTOR
________________________/[OFI2]
176.07
2,641.05
74.13
1,111.95
109.35
1,640.25
915.55
13,733.20
4) DESMONTAJE DE OBRA
SB066
Desmontaje de obra-Acarreo-Transport
1640.20/glb_____________*1of/[OFI2]
Net Rate
S= 915.55
19:39
26/02/14
2.
AI
MEP2013
Q005
340.00/mes______________*1.00
APPLIED FACTOR
________________________*1
340.00
5,440.00
340.00
5,440.00
340.00
5,440.00
233.33
3,499.95
233.33
3,499.95
83.40
1,251.00
83.40
1,251.00
92.67
1,390.05
92.67
1,390.05
37.07
556.05
109.35
1,640.25
555.81
8,337.20
Net Rate
S= 340.00
Q003a
Bill Quantity=15 m
01.01.06
[MC]=5
?[GGP]=1.0000000
[A]=15 m2
1) DEPOSITO
================================================
#
T880/005 Contenedor Oficina
700.00/mes______________*1und
________________________*[MC]/[A]
APPLIED FACTOR
1) MODULO DE MADERA
================================================
#
SB006
Comedor personal
83.40/m2________________*1und
APPLIED FACTOR
________________________*1
SB014
Armado y desarmado
695.00/vez______________*1und
APPLIED FACTOR
________________________*2veces/[A]
#
=
5) DESMONTAJE DE OBRA
SB066
Desmontaje de obra-Acarreo-Transport
1640.20/glb_____________*1come/[A]
Net Rate
S= 322.48
19:39
26/02/14
E= 233.33
3.
AI
MEP2013
Q002
Bill Quantity=15 m
01.01.07
[ALM]=15 m2
[MC]=5.00
1) DEPOSITO
================================================
#
T880/005 Contenedor Oficina
700.00/mes______________*1und
233.33
3,499.95
SB024
11120.00/glb____________/[MC]
741.33
11,119.95
APPLIED FACTOR
________________________*[MC]/[ALM]
974.67
14,620.05
55.60
834.00
55.60
834.00
92.67
1,390.05
92.67
1,390.05
111.20
1,668.00
Almacen
55.60/m2________________*1und
APPLIED FACTOR
________________________*1
3) ARMADO Y DESARMADO
#
SB014
Armado y desarmado
695.00/vez______________*1und
APPLIED FACTOR
________________________*2veces/[ALM]
5) MOBILIARIO ALMACEN
======================
#
M830007
0.50/und________________*4und
1.33
19.95
M830008
12.00/und_______________*4und
32.00
480.00
M830009
8.00
120.00
APPLIED FACTOR
41.33
619.95
________________________*5altox6*2*/[ALM]
6) DESMONTAJE DE OBRA
SB066
Desmontaje de obra-Acarreo-Transport
1640.20/glb_____________*1almc*/[ALM]
=
Net Rate
M= 41.33
Q002a
S= 1,110.15
109.35
1,640.25
1,384.81
20,772.20
55.60
1,390.00
55.60
1,390.00
27.80
695.00
27.80
695.00
E= 233.33
Bill Quantity=25 m
01.01.08
[ALM2]=25
Almacen
55.60/m2________________*1und
APPLIED FACTOR
________________________*1
3) ARMADO Y DESARMADO
#
SB014
Armado y desarmado
695.00/vez______________*1und
APPLIED FACTOR
________________________*1veces/[ALM2]
6) DESMONTAJE DE OBRA
SB066
Desmontaje de obra-Acarreo-Transport
1640.20/glb_____________*1almc*/[ALM2]*0.5
Net Rate
32.80
820.00
116.20
2,905.10
S= 116.20
19:39
26/02/14
4.
AI
MEP2013
Q00012
Bill Quantity=15 m
01.01.09
SB023
Alquiler oficina
111.20/m2_______________*5meses
=
Net Rate
556.00
8,340.00
556.00
8,340.00
6,800.00
108,800.00
6,800.00
108,800.00
52.13
834.08
S= 556.00
Q009b
01.01.10
1) GUARDIANIA
==============
#
L014
6800.00/mes_____________*1und
APPLIED FACTOR
________________________*1
#
3) CASETA DE MADERA TRIPLAY
SB018
139.00/m2_______________*6
APPLIED FACTOR
________________________/[M]
=
Net Rate
L= 6,800.00
M
Q011
52.13
834.08
6,852.12
109,633.99
S= 52.13
01.01.11
?[M]=16.0000000 meses
1) CONSUMO DE AGUA PARA LA CONSTRUCCION
M3900003 Consumo de Agua para Construccin
556.00/MES______________*[M]
8,896.00
8,896.00
232.81
2) INSTALACIONES PROVISIONAL
#
Ss00001
33.26/UND_______________*1und
232.81
Ss00002
79.48/UND_______________*1und
556.35
556.35
Ss00003
13.90/ML________________*15metros
1,459.50
1,459.50
M80o9020 Manguera
1.50/ml_________________*25
APPLIED FACTOR
________________________*14pisos*0.5
Ss00004
Bomba de agua
800.00/und______________*3und
Ss00005
Cisterna 1000lt
550.00/und______________*3und
APPLIED FACTOR
________________________*1
de
1 1/4
262.50
262.50
2,511.16
2,511.16
2,400.00
2,400.00
1,650.00
1,650.00
Net Rate
M= 9,158.50
M
19:39
26/02/14
4,050.00
4,050.00
15,457.16
15,457.16
S= 6,298.66
5.
AI
MEP2013
Q013a
?[M]=16.0000000
1) CONSUMO DE ENERGIA ELECTRICA
M3900004 Consumo de energia electrica p/construcc 2780.00/MES_____________*[M]
44,480.00
44,480.00
2) INSTALACIONES PROVISIONAL
#
Se00001
90.00/und_______________*3und
1,215.00
1,215.00
Se00002
30.00/ml________________*12ml*3
4,860.00
4,860.00
Se00003
8.00/ml_________________*15ml*3
1,620.00
1,620.00
APPLIED FACTOR
________________________*15niveles*0.3
7,695.00
7,695.00
Se00004
Tablero
973.00/und______________*3und
1,459.50
1,459.50
Se00005
Tablero general
5004.00/und_____________*1und
2,502.00
2,502.00
APPLIED FACTOR
________________________*0.5
3,961.50
3,961.50
3) AMPLIACION DE CARGA
Se050
5000.00/glb_____________*1und
=
Net Rate
M= 44,480.00
M
Q004A
5,000.00
5,000.00
61,136.50
61,136.50
233.33
3,499.95
233.33
3,499.95
S= 16,656.50
Bill Quantity=15 m
01.01.13 obreros
[A]=15.00
[MC]=5.00 meses de contenedor
1) CONTENEDOR
================================================
#
T880/005 Contenedor Oficina
700.00/mes______________*1und
________________________*[MC]/[A]
APPLIED FACTOR
2) MODULO DE MADERA
================================================
#
SB005
Vestidores
55.60/m2________________*30 m2
111.20
1,668.00
SB014
Armado y desarmado
695.00/vez______________*2und
92.67
1,390.05
APPLIED FACTOR
________________________/[A]
203.87
3,058.05
SB065
37.07
556.05
SB066
Desmontaje de obra-Acarreo-Transport
109.35
1,640.25
583.61
8,754.20
1640.20/glb_____________*1vest/[A]
Net Rate
S= 350.28
19:39
26/02/14
E= 233.33
6.
AI
MEP2013
Q004B
para obreros
01.01.14
Bao portatil
290.00/mes______________*4.00und
APPLIED FACTOR
________________________*1
Net Rate
1,160.00
18,560.00
1,160.00
18,560.00
1,160.00
18,560.00
S= 1,160.00
Q010
Carteles de Obra
01.01.16
1) MANO DE OBRA
============
#
9
L008V
Operario
20.93/hh________________*1.00
167.47
167.47
L012V
Peon
15.71/hh________________*1.00
125.72
125.72
APPLIED FACTOR
________________________*8horas
293.19
293.19
2) MATERIALES
==========
M0940007 Pernos de Anclaje
13.90/und_______________*8
111.20
111.20
4.30/p2_________________*50.00*30% amort
64.48
64.48
22.00/pln_______________*3.00*30% amort
19.80
19.80
M3032081 Gigantografia
28.83/m2________________*9.00
259.47
259.47
454.95
454.95
748.14
748.14
18,070.00
18,070.00
18,070.00
18,070.00
=
1 unidad de Cartel de Obra
Net Rate
L= 261.68
Q012
M= 462.47
S= 23.99
01.01.17
SO110
18070.00/glb____________*1.00
=
Net Rate
S= 18,070.00
TRABAJOS PRELIMINARES
P000
LEVEL 3
Movilizacin y desmovilizacin de
1) MOVILIZACION Y DESMOVILIZACION
#
SM004
1500.00/und_____________*3und
9,000.00
SM002
Equipos menores
778.40/und______________*4und
6,227.20
6,227.20
APPLIED FACTOR
________________________*2veces*[GGP]
15,227.20
15,227.20
15,227.20
15,227.20
Net Rate
9,000.00
S= 15,227.20
GGP
19:39
26/02/14
7.
AI
MEP2013
P005e
Demoliciones
01.02.02
SO104
Demoliciones
22361.11/glb____________*1
=
Net Rate
22,361.11
22,361.11
22,361.11
22,361.11
S= 22,361.11
P008
Topografa Permanente
01.02.07
[CUA]=2
[TOPO]=15
[NIVE]=5
1) MANO DE OBRA
============
#
9
L008V
Operario
20.93/hh________________*1.00
5,722.06
85,830.90
L012V
Peon
15.71/hh________________*2.00
8,590.70
128,860.50
APPLIED FACTOR
_________________*205horas*[CUA]*10/[TOPO]
14,312.76
214,691.40
2) EQUIPOS
=======
#
T023/003 Teodolito
9.73/hm_________________*1und
2,659.53
39,892.95
1.39/hm_________________*1und
379.93
5,698.95
T023/005 Jalon
0.14/hm_________________*2und
76.53
1,147.95
_________________*205horas*[CUA]*10/[TOPO]
3,116.00
46,740.00
APPLIED FACTOR
3) MATERIALES
==========
#
M0205003 Clavos p/Madera Tamao Promedio 2" a 4"
3.48/kg_________________*2.75
19.14
287.10
M3032030 Yeso
1.81/kg_________________*5.00
18.10
271.50
4.30/p2_________________*3.75/5usos
6.45
96.75
45.00/gln_______________*0.5
45.00
675.00
________________________*[CUA]
88.69
1,330.35
APPLIED FACTOR
4) NIVELACION PERMANENTE
#
9
L008V
Operario
20.93/hh________________*1.00
1,430.52
21,457.80
L012V
Peon
15.71/hh________________*1.00
1,073.84
16,107.60
T023/015 Nivel
4.17/hm_________________*1und
284.95
4,274.25
1.39/hm_________________*1und
94.98
1,424.70
___________________*205horas*[NIVE]/[TOPO]
2,884.29
43,264.35
20,401.73
306,025.95
APPLIED FACTOR
Net Rate
L= 14,956.12
P001
M= 538.32
S= 1,411.36
E= 3,495.93
01.02.10 gra
[TGRUA]=5.00 meses
[ENR]=0 meses de grupo electrogeno (luego energia del medidor)
[TMAN]=0 meses
1) TRANSPORTE VERTICAL
ALQUILER MENSUAL
===================
#
19:39
10300.00/mes____________*1
10,300.00
51,500.00
SV020
Convertidor de corriente
950.00/mes______________*1
950.00
4,750.00
SV018
600.00/mes______________*1
600.00
3,000.00
SV019
360.00
1,800.00
SV016a
Mantenimiento
1,750.00
8,750.00
26/02/14
1750.00/mes_____________*1
8.
AI
MEP2013
P001
APPLIED FACTOR
________________________*1
13,960.00
69,800.00
OPERACION DE GRUA
====================
#
9
L017V
5813.46/mes_____________*1
5,813.46
29,067.30
L015V
3605.37/mes_____________*2
7,210.75
36,053.75
APPLIED FACTOR
________________________*1
13,024.21
65,121.05
7500.00/glb_____________*2
3,000.00
15,000.00
SM062
7500.00/und_____________*2
3,000.00
15,000.00
SV022a
9700.00/und_____________*2
3,880.00
19,400.00
SV024a
9800.00/und_____________*1
1,960.00
9,800.00
APPLIED FACTOR
________________________*1/[TGRUA]
11,840.00
59,200.00
ALIMENTACION ELECTRICA
========================
#
8
75.97/hm________________*1und*205horas
APPLIED FACTOR
________________________*[ENR]/[TGRUA]
0.00
SV014
2502.00/und_____________/[TGRUA]
500.40
2,502.00
0.00
2) BASE DE CONCRETO
#
MANO DE OBRA
============
9
L008V
Operario
20.93/hh________________*3.00
93.79
468.95
L011V
Oficial
17.31/hh________________*1.00
25.84
129.20
L012V
Peon
15.71/hh________________*4.00
93.87
469.35
APPLIED FACTOR
__________________/(30/8)m3/h*28m3/[TGRUA]
213.50
1,067.50
5,944.70
MATERIALES
==========
#
M2120003 Conc. premzcl fc=140K Tp.1 P#57 Sl 3-4" 202.20/m3_______________*1.00+5%waste
1,188.94
SO050
35.00/m3________________*0.50
98.00
490.00
APPLIED FACTOR
________________________*28m3/[TGRUA]
1,286.94
6,434.70
3) MANLIFT
#
T046/025 Manlift
4800.00/mes_____________*1
________________________*[TMAN]/[TGRUA]
APPLIED FACTOR
0.00
0.00
19:39
26/02/14
M= 1,483.61
S= 16,751.30
40,825.05
204,125.25
E= 10,300.00
9.
AI
MEP2013
P002
01.02.13 elevadora
[TMONTA]=12
[ENR]=0 meses de grupo electrogeno (luego energia del medidor)
1) MONTACARGA
ALQUILER MENSUAL
===================
#
T046/022 Montacarga Alba MC-1500 21mts
8400.00/mes_____________*1
8,400.00
SV016
1,680.00
92,400.00
18,480.00
APPLIED FACTOR
________________________*1
10,080.00
110,880.00
2,776.53
30,541.83
2,776.53
30,541.83
OPERACION
====================
#
9
L016V
2776.53/mes_____________*1
APPLIED FACTOR
________________________*1
11200.00/glb____________*1
933.33
10,266.63
SV010a
11200.00/glb____________*1
933.33
10,266.63
SM061
7600.00/und_____________*1
633.33
6,966.63
SV022
0.00
APPLIED FACTOR
________________________/[TMONTA]
2,500.00
27,500.00
ALIMENTACION ELECTRICA
========================
#
8
28.02/hm________________*1und*[HM]horas
APPLIED FACTOR
________________________*[ENR]/[TMONTA]
SV014a
2502.00/und_____________/[TMONTA] *1
0.00
=
Net Rate
L= 2,775.00
HM
P001a
M= 0.47
S= 4,389.56
0.00
208.50
2,293.50
15,565.03
171,215.31
6,443.02
103,088.32
6,443.02
103,088.32
6,443.02
103,088.35
1,668.00
1,668.00
1,668.00
1,668.00
E= 8,400.00
01.02.14
L012V
Peon
15.71/hh________________*2.00
APPLIED FACTOR
________________________*205horas
=
Net Rate
L= 5,670.30
P0030
M= 192.70
S= 580.02
SR040
Traslado de ascensor
1668.00/glb_____________*1.00
=
Net Rate
S= 1,668.00
19:39
26/02/14
10.
AI
MEP2013
P00037
Reubicacin de rboles
01.02.16
SR043
Reubicacin de arboles
2780.00/glb_____________*1.00
=
Net Rate
2,780.00
2,780.00
2,780.00
2,780.00
556.00
556.00
556.00
556.00
S= 2,780.00
P0031
01.02.17 proyecto
SR044
556.00/glb______________*1.00
=
Net Rate
S= 556.00
LEVEL 3
01.03.08 escombros)
[LIM]=11 mes
[ARQ]=7 mes
1) LIMPIEZA PERMANENTE
=====================
#
9
L012V
Peon
15.71/hh________________*1*2personas
APPLIED FACTOR
________________________*205h/mes*25%
1,610.76
17,718.36
1,610.76
17,718.36
3,054.55
33,600.05
3,054.55
33,600.05
4,665.30
51,318.31
4,170.00
4,170.00
4,170.00
4,170.00
**Se considera solo el 25% del tiempo de 2peones para la limpieza permanente**
2) ELIMINACION POR TRABAJOS DE ACABADOS
===========================================
#
SO060
600.00/vez______________*2*4
APPLIED FACTOR
________________________/[LIM]*[ARQ]
P0020
M= 48.18
S= 3,199.55
01.03.09 la construccin
SO222
Ventilacion Forzada
4170.00/glb_____________*1
=
Net Rate
S= 4,170.00
19:39
26/02/14
11.
AI
MEP2013
P003b
[LIM]=11 mes
[ARQ]=0 mes
1) LIMPIEZA PERMANENTE
=====================
#
9
L012V
Peon
15.71/hh________________*1 personas
APPLIED FACTOR
________________________*205h/mes*50%
1,610.76
25,772.16
1,610.76
25,772.16
**Se considera solo el 25% del tiempo de 2peones para la limpieza permanente**
2) ELIMINACION POR TRABAJOS DE ACABADOS
===========================================
#
SO060
600.00/vez______________*2*4
APPLIED FACTOR
________________________/[LIM]*[ARQ]
0.00
0.00
P0021
M= 48.18
1,610.76
25,772.09
16,680.00
16,680.00
16,680.00
16,680.00
15,086.10
15,086.10
15,086.10
15,086.10
1,200.00
1,200.00
S= 145.01
Iluminacin de obra
01.03.11
SR045
Reflectores
834.00/glb______________*20
=
Net Rate
S= 16,680.00
P003a
1) LIMPIEZA FINAL
=================
#
9
L012V
Peon
15.71/hh______________*1*8horas*10personas
APPLIED FACTOR
________________________*12dias
600.00/vez______________*2veces
APPLIED FACTOR
________________________*1
=
Net Rate
L= 13,276.80
M= 451.20
19:39
26/02/14
1,200.00
16,286.10
16,286.10
S= 2,558.10
1,200.00
LEVEL 3
12.
AI
MEP2013
Q021a
[BP]=1240 ml
L008V
Operario
20.93/hh________________*2.00
324.48
5,191.68
L012V
Peon
15.71/hh________________*1.00
121.79
1,948.64
APPLIED FACTOR
________________________/10ml/hr*[BP]/[M]
446.27
7,140.32
20,683.20
MATERIALES
============
#
M3026004 Barandas provisionales (madera)
16.68/ml________________*1ml
1,292.70
32.00/und_______________/50m/2usos+3%waste
25.54
408.64
________________________*[BP]/[M]
1,318.24
21,091.84
5.36
85.76
5.36
85.76
APPLIED FACTOR
L012V
Peon
15.71/hh________________*1
APPLIED FACTOR
_______________________/22ml/hr*[MEXC]/[M]
#
M3026007 Malla Plastificada color nranja (50m)
32.00/und_______________/50m/2usos+3%waste
2.47
39.52
13.90/und_______________*0.5
52.13
834.08
________________________*[MEXC]/[M]
54.60
873.60
APPLIED FACTOR
3) MALLA ANTICAIDAS
#
SC050
592.92
9,486.72
166.80/ml_______________*1ml*[PCTJ]+5%
2,846.03
45,536.48
2,561.42
40,982.72
APPLIED FACTOR
________________________*[MC]/[M]
Net Rate
L= 404.54
M
Q022
M= 6,791.38
6,000.37
96,005.92
7,824.84
125,197.43
S= 628.93
01.04.04
1) MATERIALES
============
#
M3026006 Stiker Autodesivo - Seal de seguridad
5.00/und________________*10und*15pisos
46.87
749.92
25.42/und_______________*32und
50.84
813.44
32.00/und_______________*20und
40.00
640.00
25.00/und_______________*10und
15.62
249.92
50.00/und_______________*7und*5sotanos
109.37
1,749.92
50.00/und_______________*3und*10pisos
________________________/[M]
APPLIED FACTOR
Net Rate
93.75
1,500.00
356.47
5,703.52
356.47
5,703.47
M= 356.47
M
19:39
26/02/14
13.
AI
MEP2013
Q026
01.04.07
L012V
Peon
15.71/hh________________*205
=
Net Rate
L= 2,835.15
M= 96.35
16,107.55
3,221.51
16,107.56
S= 290.01
OTROS
Q028
3,221.51
LEVEL 3
SR042
2224.00/glb_____________*1.00
=
Net Rate
2,224.00
2,224.00
2,224.00
2,224.00
S= 2,224.00
PARTIDAS COMPLEMENTARIAS
Q027
LEVEL 3
01.07
1) MANO DE OBRA
#
9
L008V
Operario
20.93/hh________________*1
418.69
L012V
Peon
15.71/hh________________*2
628.59
418.69
628.59
APPLIED FACTOR
________________*1frente*4horas/dia*5veces
1,047.27
1,047.27
2) MATERIALES
#
M3026012 Cachacos Portacintas
25.00/und_______________*0und
0.00
125.00/und______________*10und
1,250.00
1,250.00
________________________*1
1,250.00
1,250.00
2,297.27
2,297.27
6,950.00
6,950.00
6,950.00
6,950.00
APPLIED FACTOR
Net Rate
L= 930.80
O210
M= 1,278.20
S= 88.27
Reparacion de veredas
01.08
SO220
Reparacion de veredas
2.78/glb________________*2500
=
Net Rate
S= 6,950.00
ARQUITECTURA
LEVEL 2
n
MUROS Y TABIQUES
LEVEL 3
n
LEVEL 4
19:39
26/02/14
14.
AI
MEP2013
a003002
Bill Quantity=963.46 m
1) Mano de obra
#
9
L008V
Operario
20.93/hh________________*1.00
22.33
L012V
Peon
15.71/hh________________*0.50
8.38
21,514.06
8,073.79
APPLIED FACTOR
30.71
29,587.86
2) Materiales
#
M1700032 Ladrillo de concreto (9x13x22cm)
0.57/und________________*42.000
25.14
24,221.38
14.93/bls_______________*0.2340 +5%waste
3.67
3,535.90
34.00/m3________________*0.0310 +5%waste
1.11
1,069.44
6.00/m3_________________*0.0070 +5%waste
0.04
38.54
4.30/p2_________________*0.5800
2.49
2,399.02
3.48/kg_________________*0.0220
________________________/ 1
APPLIED FACTOR
+5%waste
Net Rate
L= 27.51
19:39
26/02/14
M= 33.28
0.08
77.08
32.53
31,341.35
63.24
60,925.71
S= 2.44
15.
AI
MEP2013
a003002
Bill Quantity=273.97 m
1) Mano de obra
#
9
L008V
Operario
20.93/hh________________*1.00
22.33
6,117.75
L012V
Peon
15.71/hh________________*0.50
8.38
2,295.87
APPLIED FACTOR
30.71
8,413.62
2) Materiales
#
M1700032 Ladrillo de concreto (9x13x22cm)
0.57/und________________*42.000
25.14
6,887.61
14.93/bls_______________*0.2340 +5%waste
3.67
1,005.47
34.00/m3________________*0.0310 +5%waste
1.11
304.11
6.00/m3_________________*0.0070 +5%waste
0.04
10.96
4.30/p2_________________*0.5800
2.49
682.19
3.48/kg_________________*0.0220
________________________/ 1
APPLIED FACTOR
+5%waste
Net Rate
L= 27.51
a001002
M= 33.28
0.08
21.92
32.53
8,912.24
63.24
17,324.87
S= 2.44
Bill Quantity=1,910.44 m
1) Mano de obra
#
9
L008V
Operario
20.93/hh________________*1.00
20.93
39,985.51
L012V
Peon
15.71/hh________________*0.50
7.86
15,016.06
APPLIED FACTOR
28.79
55,001.57
2) Materiales
#
M1700020 Ladrillo Pandereta acanalado 9x10.5x23cm 0.44/und________________*39.000 +5%waste
18.02
34,426.13
14.93/bls_______________*0.1790 +5%waste
2.81
5,368.34
34.00/m3________________*0.0230 +5%waste
0.82
1,566.56
6.00/m3_________________*0.0070 +5%waste
0.04
76.42
4.30/p2_________________*0.5800
2.49
4,757.00
3.48/kg_________________*0.0220
________________________/ 1
APPLIED FACTOR
Net Rate
L= 25.80
19:39
26/02/14
M= 24.96
0.08
152.84
24.26
46,347.27
53.05
101,349.06
S= 2.29
16.
AI
MEP2013
a001004
Bill Quantity=159.74 m
L008V
Operario
20.93/hh________________*1.00
20.93
3,343.36
L012V
Peon
15.71/hh________________*0.50
7.86
1,255.56
APPLIED FACTOR
28.79
4,598.91
2) Materiales
#
M1700020 Ladrillo Pandereta acanalado 9x10.5x23cm 0.44/und________________*39.000 +5%waste
18.02
2,878.51
14.93/bls_______________*0.1790 +5%waste
2.81
448.87
34.00/m3________________*0.0230 +5%waste
0.82
130.99
6.00/m3_________________*0.0070 +5%waste
0.04
6.39
4.30/p2_________________*0.5800
2.49
397.75
3.48/kg_________________*0.0220
________________________/ 1
APPLIED FACTOR
0.08
12.78
24.26
3,875.29
115.31
18,419.62
168.36
26,894.00
7,860.68
TABIQUE DE DRYWALL
==================
Sbb00001 Tabiques de drywall y FCR
0.95SA__________________*121.38
=
Net Rate
L= 25.80
a001002
M= 24.96
S= 117.60
Bill Quantity=375.57 m
1) Mano de obra
#
9
L008V
Operario
20.93/hh________________*1.00
20.93
L012V
Peon
15.71/hh________________*0.50
7.86
2,951.98
APPLIED FACTOR
28.79
10,812.66
2) Materiales
#
M1700020 Ladrillo Pandereta acanalado 9x10.5x23cm 0.44/und________________*39.000 +5%waste
18.02
6,767.77
14.93/bls_______________*0.1790 +5%waste
2.81
1,055.35
34.00/m3________________*0.0230 +5%waste
0.82
307.97
6.00/m3_________________*0.0070 +5%waste
0.04
15.02
4.30/p2_________________*0.5800
2.49
935.17
3.48/kg_________________*0.0220
________________________/ 1
APPLIED FACTOR
Net Rate
L= 25.80
19:39
26/02/14
M= 24.96
0.08
30.05
24.26
9,111.33
53.05
19,924.03
S= 2.29
17.
AI
MEP2013
a000003
Muro de ladrillo KK
9x12.5x23
T09 A
Bill Quantity=460.43 m
02.01.01
1) Mano de obra
#
9
L008V
Operario
20.93/hh________________*1.00
20.93
L012V
Peon
15.71/hh________________*0.50
7.86
9,636.80
3,618.98
APPLIED FACTOR
28.79
13,255.78
2) Materiales
#
M1700010 Ladrillo KK 18H (9x13x24) tipo IV
0.55/und________________*42.000 +5%waste
24.26
11,170.03
14.93/bls_______________*0.2490 +5%waste
3.90
1,795.68
34.00/m3________________*0.0730 +5%waste
2.61
1,201.72
6.00/m3_________________*0.0070 +5%waste
0.04
18.42
4.30/p2_________________*0.5800
2.49
1,146.47
3.48/kg_________________*0.0220
________________________/ 1
APPLIED FACTOR
Net Rate
L= 25.80
a000003
M= 34.08
Muro de ladrillo KK
0.08
36.83
33.38
15,369.15
62.17
28,624.69
S= 2.29
9x12.5x23
T09 A
Bill Quantity=1,279.49 m
02.01.01
1) Mano de obra
#
9
L008V
Operario
20.93/hh________________*1.00
20.93
26,779.73
L012V
Peon
15.71/hh________________*0.50
7.86
10,056.79
APPLIED FACTOR
28.79
36,836.52
2) Materiales
#
M1700010 Ladrillo KK 18H (9x13x24) tipo IV
0.55/und________________*42.000 +5%waste
24.26
31,040.43
14.93/bls_______________*0.2490 +5%waste
3.90
4,990.01
34.00/m3________________*0.0730 +5%waste
2.61
3,339.47
6.00/m3_________________*0.0070 +5%waste
0.04
51.18
4.30/p2_________________*0.5800
2.49
3,185.93
3.48/kg_________________*0.0220
________________________/ 1
APPLIED FACTOR
Net Rate
L= 25.80
19:39
26/02/14
M= 34.08
0.08
102.36
33.38
42,709.38
62.17
79,545.22
S= 2.29
18.
AI
MEP2013
a000003
Muro de ladrillo KK
9x12.5x23
T09 A
Bill Quantity=2.80 m
02.01.01
1) Mano de obra
#
9
L008V
Operario
20.93/hh________________*1.00
20.93
58.60
L012V
Peon
15.71/hh________________*0.50
7.86
22.01
APPLIED FACTOR
28.79
80.61
2) Materiales
#
M1700010 Ladrillo KK 18H (9x13x24) tipo IV
0.55/und________________*42.000 +5%waste
24.26
67.93
14.93/bls_______________*0.2490 +5%waste
3.90
10.92
34.00/m3________________*0.0730 +5%waste
2.61
7.31
6.00/m3_________________*0.0070 +5%waste
0.04
0.11
4.30/p2_________________*0.5800
2.49
6.97
3.48/kg_________________*0.0220
0.08
0.22
________________________/ 1
33.38
93.46
62.17
174.07
APPLIED FACTOR
Net Rate
L= 25.80
M= 34.08
S= 2.29
LEVEL 4
Bill Quantity=2,388.35 m
02.01.02
0.95SA__________________*119.17
=
Net Rate
113.21
270,385.10
113.21
270,388.69
100.44
139,976.20
100.44
139,981.07
97.54
22,564.90
97.54
22,564.09
117.51
42,548.02
117.51
42,546.39
94.87
39,632.89
94.87
39,631.64
S= 113.21
Bill Quantity=1,393.63 m
02.01.02
0.95SA__________________*105.73
=
Net Rate
S= 100.44
Bill Quantity=231.34 m
02.01.02
0.95SA__________________*102.67
=
Net Rate
S= 97.54
Bill Quantity=362.08 m
02.01.02
0.95SA__________________*123.69
=
Net Rate
S= 117.51
Bill Quantity=417.76 m
02.01.02
0.95SA__________________*99.86
=
Net Rate
S= 94.87
TABIQUES DRYWALL +
a000004
TABIQUES DE ........
LEVEL 4
Bill Quantity=912.88 m
MURO DE LADRILLO
================
1) Mano de obra
#
9
L008V
Operario
20.93/hh________________*1.00
27.91
L012V
Peon
15.71/hh________________*0.50
10.48
25,478.48
9,566.98
APPLIED FACTOR
38.39
35,045.46
2) Materiales
#
M1700010 Ladrillo KK 18H (9x13x24) tipo IV
0.55/und________________*42.000 +5%waste
24.26
22,146.47
14.93/bls_______________*0.2490 +5%waste
3.90
3,560.23
34.00/m3________________*0.0730 +5%waste
2.61
2,382.62
70.27
64,148.08
10.00
9,128.80
97.30/m2________________*1.0000 +5%waste
102.17
93,268.95
19.46/und_______________*1.0000
19.46
17,764.64
6.00/m3_________________*0.0070 +5%waste
0.04
36.52
4.30/p2_________________*0.5800
2.49
2,273.07
3.48/kg_________________*0.0220
________________________/ 1
APPLIED FACTOR
0.08
73.03
235.27
214,773.28
5.58
5,093.87
5.58
5,093.87
16.75
15,290.74
16.75
15,290.74
PINTURA HIDROFUGA
=================
1) Mano de obra
#
9
L008V
Operario
20.93/hh________________*1.00
APPLIED FACTOR
2) Materiales
M3010006 Pintura hidrofuga
58.00/gal_______________*0.275 +5%waste
=
TABIQUE DE DRYWALL
==================
Sbb00001 Tabiques de drywall y FCR
0.95SA__________________*100.09
=
Net Rate
L= 39.43
19:39
26/02/14
M= 253.09
95.09
86,805.76
391.08
357,008.33
S= 98.56
20.
AI
MEP2013
a000004
Bill Quantity=570.76 m
MURO DE LADRILLO
================
1) Mano de obra
#
9
L008V
Operario
20.93/hh________________*1.00
27.91
L012V
Peon
15.71/hh________________*0.50
10.48
15,929.91
5,981.56
APPLIED FACTOR
38.39
21,911.48
2) Materiales
#
M1700010 Ladrillo KK 18H (9x13x24) tipo IV
0.55/und________________*42.000 +5%waste
24.26
13,846.64
14.93/bls_______________*0.2490 +5%waste
3.90
2,225.96
34.00/m3________________*0.0730 +5%waste
2.61
1,489.68
70.27
40,107.31
10.00
5,707.60
97.30/m2________________*1.0000 +5%waste
102.17
58,314.55
19.46/und_______________*1.0000
19.46
11,106.99
6.00/m3_________________*0.0070 +5%waste
0.04
22.83
4.30/p2_________________*0.5800
2.49
1,421.19
3.48/kg_________________*0.0220
________________________/ 1
APPLIED FACTOR
0.08
45.66
235.27
134,282.71
5.58
3,184.84
5.58
3,184.84
16.75
9,560.23
16.75
9,560.23
PINTURA HIDROFUGA
=================
1) Mano de obra
#
9
L008V
Operario
20.93/hh________________*1.00
APPLIED FACTOR
2) Materiales
M3010006 Pintura hidrofuga
58.00/gal_______________*0.275 +5%waste
=
TABIQUE DE DRYWALL
==================
Sbb00001 Tabiques de drywall y FCR
0.95SA__________________*100.09
=
Net Rate
L= 39.43
19:39
26/02/14
M= 253.09
95.09
54,273.57
391.08
223,212.33
S= 98.56
21.
AI
MEP2013
a000005
Bill Quantity=506.25 m
MURO DE LADRILLO
================
1) Mano de obra
#
9
L008V
Operario
20.93/hh________________*1.00
27.91
L012V
Peon
15.71/hh________________*0.50
10.48
14,129.44
5,305.50
APPLIED FACTOR
38.39
19,434.94
2) Materiales
#
M1700010 Ladrillo KK 18H (9x13x24) tipo IV
0.55/und________________*42.000 +5%waste
24.26
12,281.63
14.93/bls_______________*0.2490 +5%waste
3.90
1,974.38
34.00/m3________________*0.0730 +5%waste
2.61
1,321.31
87.84
44,469.00
12.50
6,328.13
6.00/m3_________________*0.0070 +5%waste
0.04
20.25
4.30/p2_________________*0.5800
2.49
1,260.56
3.48/kg_________________*0.0220
________________________/ 1
APPLIED FACTOR
0.08
40.50
133.72
67,695.75
5.58
2,824.88
5.58
2,824.88
16.75
8,479.69
137.38
69,548.63
331.82
167,981.91
PINTURA HIDROFUGA
=================
1) Mano de obra
#
9
L008V
Operario
20.93/hh________________*1.00
APPLIED FACTOR
2) Materiales
M3010006 Pintura hidrofuga
58.00/gal_______________*0.275 +5%waste
TABIQUE DE DRYWALL
==================
Sbb00001 Tabiques de drywall y FCR
0.95SA__________________*144.61
Net Rate
L= 39.43
19:39
26/02/14
M= 151.53
S= 140.86
22.
AI
MEP2013
a001003
Bill Quantity=156.25 m
MURO DE LADRILLO
================
1) Mano de obra
#
9
L008V
Operario
20.93/hh________________*1.00
20.93
3,270.31
L012V
Peon
15.71/hh________________*0.50
7.86
1,228.13
APPLIED FACTOR
28.79
4,498.44
2) Materiales
#
M1700020 Ladrillo Pandereta acanalado 9x10.5x23cm 0.44/und________________*39.000 +5%waste
18.02
2,815.63
14.93/bls_______________*0.1790 +5%waste
2.81
439.06
34.00/m3________________*0.0230 +5%waste
0.82
128.13
6.00/m3_________________*0.0070 +5%waste
0.04
6.25
4.30/p2_________________*0.5800
2.49
389.06
3.48/kg_________________*0.0220
________________________/ 1
APPLIED FACTOR
0.08
12.50
24.26
3,790.63
91.31
14,267.19
144.36
22,556.89
TABIQUE DE DRYWALL
==================
Sbb00001 Tabiques de drywall y FCR
0.95SA__________________*96.12
=
Net Rate
L= 25.80
M= 24.96
S= 93.61
OTROS
LEVEL 4
Bill Quantity=267.28 m
02.01.04
0.95SA__________________*105.73
=
Net Rate
100.44
26,845.60
100.44
26,846.54
102.76
65,580.40
102.76
65,581.36
122.27
24,693.65
122.27
24,692.64
S= 100.44
Bill Quantity=638.19 m
02.01.04
0.95SA__________________*108.17
=
Net Rate
S= 102.76
Bill Quantity=201.96 m
02.01.04
0.95SA__________________*128.70
=
Net Rate
S= 122.27
REVOQUES Y REVESTIMIENTOS
n
19:39
LEVEL 3
TARRAJEOS
26/02/14
LEVEL 4
23.
AI
MEP2013
a030001
Bill Quantity=2,251.94 m
1) Mano de obra
#
9
L008V
Operario
20.93/hh________________*1.00
16.75
L012V
Peon
15.71/hh________________*0.33
4.15
37,720.00
9,345.55
APPLIED FACTOR
20.90
47,065.55
2) Materiales
#
M2100001 Cemento Portland Tipo I bls 42.5 Kg
14.93/bls_______________*0.1390 +5%waste
2.18
4,909.23
35.00/m3________________*0.0380 +5%waste
1.40
3,152.72
6.00/m3_________________*0.0080 +5%waste
0.05
112.60
19.00/m2mes_____________*570*2mes/2252
9.62
21,663.66
4.50/p2_________________*2.00/(4.00*20)
________________________/ 1
p2/(m2*usos)
APPLIED FACTOR
=
Net Rate
L= 18.76
a031001
M= 4.24
S= 1.64
0.11
247.71
13.36
30,085.92
34.25
77,135.07
33,015.42
E= 9.62
Bill Quantity=1,971.07 m
1) Mano de obra
#
9
L008V
Operario
20.93/hh________________*1.00
16.75
L012V
Peon
15.71/hh________________*0.33
4.15
8,179.94
APPLIED FACTOR
20.90
41,195.36
2) Materiales
#
M2100001 Cemento Portland Tipo I bls 42.5 Kg
14.93/bls_______________*0.1390 +5%waste
2.18
4,296.93
35.00/m3________________*0.0380 +5%waste
1.40
2,759.50
6.00/m3_________________*0.0080 +5%waste
0.05
98.55
3.48/kg_________________*0.0260
0.09
177.40
4.30/p2_________________*62.20/(7.20*12)
3.09
6,090.61
4.50/p2_________________*2.00/(4.00*20)
0.11
216.82
________________________/ 1
6.92
13,639.80
27.82
54,832.97
p2/(m2*usos)
APPLIED FACTOR
Net Rate
L= 18.76
19:39
26/02/14
M= 7.42
S= 1.64
24.
AI
MEP2013
a032001
Bill Quantity=2,263.50 m
1) Mano de obra
#
9
L008V
Operario
20.93/hh________________*1.00
14.56
L012V
Peon
15.71/hh________________*0.33
3.61
32,956.56
8,171.24
APPLIED FACTOR
18.17
41,127.80
2) Materiales
#
M2100001 Cemento Portland Tipo I bls 42.5 Kg
14.93/bls_______________*0.0970 +5%waste
1.52
3,440.52
35.00/m3________________*0.0210 +5%waste
0.77
1,742.90
6.00/m3_________________*0.0080 +5%waste
0.05
113.18
3.48/kg_________________*0.0260
0.09
203.72
4.30/p2_________________*62.20/(7.20*12)
3.09
6,994.22
4.50/p2_________________*2.00/(4.00*20)
0.11
248.99
________________________/ 1
5.64
12,766.14
23.81
53,894.25
120,697.32
APPLIED FACTOR
Net Rate
L= 16.31
a031001
M= 6.07
S= 1.43
Bill Quantity=7,205.81 m
1) Mano de obra
#
9
L008V
Operario
20.93/hh________________*1.00
16.75
L012V
Peon
15.71/hh________________*0.33
4.15
29,904.11
APPLIED FACTOR
20.90
150,601.43
2) Materiales
#
M2100001 Cemento Portland Tipo I bls 42.5 Kg
14.93/bls_______________*0.1390 +5%waste
2.18
15,708.67
35.00/m3________________*0.0380 +5%waste
1.40
10,088.13
6.00/m3_________________*0.0080 +5%waste
0.05
360.29
3.48/kg_________________*0.0260
0.09
648.52
22,265.95
p2/(m2*usos)
M4300005 Madera Tornillo (Andamiaje)
4.30/p2_________________*62.20/(7.20*12)
3.09
4.50/p2_________________*2.00/(4.00*20)
0.11
792.64
________________________/ 1
6.92
49,864.21
27.82
200,457.62
APPLIED FACTOR
Net Rate
L= 18.76
19:39
26/02/14
M= 7.42
S= 1.64
25.
AI
MEP2013
a037001
Bill Quantity=2,823.12 m
1) Mano de obra
#
9
L008V
Operario
20.93/hh________________*1.00
20.93
59,087.90
L012V
Peon
15.71/hh________________*0.33
5.19
14,651.99
APPLIED FACTOR
26.12
73,739.89
3) Materiales
#
M2100001 Cemento Portland Tipo I bls 42.5 Kg
14.93/bls_______________*0.1390 +5%waste
2.18
6,154.40
35.00/m3________________*0.0380 +5%waste
1.40
3,952.37
6.00/m3_________________*0.0080 +5%waste
0.05
141.16
3.48/kg_________________*0.0777
0.27
762.24
18,745.52
p2/(m2*usos)
M4300005 Madera Tornillo (Andamiaje)
4.30/p2_________________*116.80/(3.60*21)
6.64
4.50/p2_________________*2.67/(10*10)
0.12
338.77
________________________/ 1
10.66
30,094.46
36.78
103,823.68
APPLIED FACTOR
Net Rate
L= 23.44
a031201
M= 11.28
S= 2.05
Bill Quantity=222.43 m
L008V
Operario
20.93/hh________________*1.00
20.93
4,655.46
L012V
Peon
15.71/hh________________*0.33
5.19
1,154.41
APPLIED FACTOR
26.12
5,809.87
809.65
2) Materiales
#
M2100001 Cemento Portland Tipo I bls 42.5 Kg
14.93/bls_______________*0.2320 +5%waste
3.64
35.00/m3________________*0.0066 +5%waste
0.24
53.38
3.06/kg_________________*0.2320 +5%waste
0.75
166.82
6.00/m3_________________*0.0029 +5%waste
0.02
4.45
4.30/p2_________________*0.8100
3.48
774.06
4.50/p2_________________*0.0300
0.14
31.14
3.48/kg_________________*0.0445
0.15
33.36
________________________/ 1
8.41
1,870.64
APPLIED FACTOR
L008V
Operario
20.93/hh________________*1.00
20.93
4,655.46
L012V
Peon
15.71/hh________________*0.33
5.19
1,154.41
APPLIED FACTOR
26.12
5,809.87
#
M2100001 Cemento Portland Tipo I bls 42.5 Kg
14.93/bls_______________*0.2240 +5%waste
3.51
780.73
35.00/m3________________*0.0192 +5%waste
0.71
157.93
3.06/kg_________________*0.2240 +5%waste
0.72
160.15
6.00/m3_________________*0.0054 +5%waste
0.03
6.67
________________________/ 1
4.97
1,105.48
65.63
14,597.16
APPLIED FACTOR
Net Rate
L= 46.89
19:39
26/02/14
M= 14.64
S= 4.10
26.
AI
MEP2013
a037201
Bill Quantity=272.54 m
L008V
Operario
20.93/hh________________*1.00
20.93
5,704.26
L012V
Peon
15.71/hh________________*0.33
5.19
1,414.48
APPLIED FACTOR
26.12
7,118.74
992.05
2) Materiales
#
M2100001 Cemento Portland Tipo I bls 42.5 Kg
14.93/bls_______________*0.2320 +5%waste
3.64
35.00/m3________________*0.0066 +5%waste
0.24
65.41
3.06/kg_________________*0.2320 +5%waste
0.75
204.41
6.00/m3_________________*0.0029 +5%waste
0.02
5.45
4.30/p2_________________*116.80/(3.60*29)
4.81
1,310.92
4.50/p2_________________*2.67/(10*15)
0.08
21.80
3.48/kg_________________*0.0760
0.26
70.86
L008V
Operario
20.93/hh________________*1.00
23.92
6,519.16
L012V
Peon
15.71/hh________________*0.33
5.93
1,616.16
APPLIED FACTOR
29.85
8,135.32
2) Materiales
#
M2100001 Cemento Portland Tipo I bls 42.5 Kg
14.93/bls_______________*0.2240 +5%waste
3.51
956.62
35.00/m3________________*0.0192 +5%waste
0.71
193.50
3.06/kg_________________*0.2240 +5%waste
0.72
196.23
6.00/m3_________________*0.0054 +5%waste
0.03
8.18
________________________/ 1
4.97
1,354.52
70.74
19,279.21
199.25
APPLIED FACTOR
Net Rate
L= 50.24
a060001
M= 16.11
S= 4.40
Bill Quantity=25.00 ml
02.02.02 Escaleras
L008V
Operario
20.93/hh________________*1.00
7.97
L012V
Peon
15.71/hh________________*0.33
1.98
49.50
APPLIED FACTOR
9.95
248.75
2) Materiales
#
M2100001 Cemento Portland Tipo I bls 42.5 Kg
14.93/bls_______________*0.1770 +5%waste
2.77
69.25
35.00/m3________________*0.0190 +5%waste
0.70
17.50
6.00/m3_________________*0.0049 +5%waste
0.03
0.75
4.50/p2_________________*0.0360
0.16
4.00
________________________/ 1
3.67
91.75
13.62
340.41
APPLIED FACTOR
Net Rate
L= 8.93
19:39
26/02/14
M= 3.90
S= 0.78
27.
AI
MEP2013
a060002
Forjado en descansos
Bill Quantity=3.58 m
02.02.02
1) Mano de obra
#
9
L008V
Operario
20.93/hh________________*1.00
18.61
66.62
L012V
Peon
15.71/hh________________*0.50
6.98
24.99
APPLIED FACTOR
25.59
91.61
2) Materiales
#
M2100001 Cemento Portland Tipo I bls 42.5 Kg
14.93/bls_______________*0.3880 +5%waste
6.08
21.77
35.00/m3________________*0.0590 +5%waste
2.17
7.77
6.00/m3_________________*0.0300 +5%waste
0.19
0.68
4.50/p2_________________*0.0560
0.25
0.90
________________________/ 1
8.69
31.11
34.28
122.74
7.61
121.76
7.61
121.76
45.00
720.00
45.00
720.00
52.61
841.80
APPLIED FACTOR
Net Rate
L= 22.93
M= 9.32
S= 2.04
02.02.02
1) Mano de obra
#
9
L008V
Operario
20.93/hh________________*1
APPLIED FACTOR
2) Materiales
M1030601 Tapas para cajas de valvulas en MDF
45.00/und_______________*1
=
Net Rate
L= 6.87
M= 45.17
S= 0.58
VESTIDURA DE DERRAMES
a040001
LEVEL 4
Bill Quantity=4,148.01 ml
1) Mano de obra
#
9
L008V
Operario
20.93/hh________________*1.00
11.96
49,610.20
L012V
Peon
15.71/hh________________*0.33
2.96
12,278.11
APPLIED FACTOR
14.93
61,929.79
2) Materiales
#
M2100001 Cemento Portland Tipo I bls 42.5 Kg
14.93/bls_______________*0.0170 +5%waste
0.27
1,119.96
35.00/m3________________*0.0024 +5%waste
0.09
373.32
6.00/m3_________________*0.0006 +5%waste
0.00
4.30/p2_________________*35.75/(5*37)
0.83
3.48/kg_________________*0.0300
0.10
414.80
________________________/ 1
1.29
5,350.93
16.22
67,277.32
APPLIED FACTOR
Net Rate
L= 13.40
M= 1.65
S= 1.17
BRUAS
19:39
26/02/14
3,442.85
LEVEL 4
28.
AI
MEP2013
a0500001 Brua e = 10 mm
Bill Quantity=55.00 ml
02.02.04
BRUA DE 1.00CM
===============
1) Mano de obra
#
9
L008V
Operario
20.93/hh________________*1.00
APPLIED FACTOR
=
Net Rate
L= 2.52
M= 0.06
153.45
2.79
153.45
2.79
153.52
S= 0.21
EMPASTES
a700001
2.79
LEVEL 4
Bill Quantity=993.30 m
02.02.05
1) Mano de obra
#
9
L008V
Operario
20.93/hh________________*1.00
APPLIED FACTOR
4.93
4,896.97
4.93
4,896.97
3.93
3,903.67
3.93
3,903.67
8.85
8,794.52
2) Materiales
#
M5405000 Pasta mural a base de latex
31.20/gln_______________*0.1199 +5%waste
________________________/ 1
APPLIED FACTOR
=
Net Rate
L= 4.44
M= 4.04
S= 0.37
REVESTIMIENTOS
a600001
LEVEL 4
Bill Quantity=5.93 ml
=
Net Rate
371.88
2,205.25
371.88
2,205.25
S= 371.88
LEVEL 3
LEVEL 4
Bill Quantity=3,900.44 m
02.03.01
0.95SA__________________*106.78
=
Net Rate
101.44
395,660.63
101.44
395,664.53
112.14
59,407.29
112.14
59,406.23
S= 101.44
Bill Quantity=529.76 m
0.95SA__________________*118.04
=
Net Rate
S= 112.14
19:39
26/02/14
29.
AI
MEP2013
Clean Room FL y VL
Bill Quantity=77.81 m
0.95SA__________________*114.64
=
Net Rate
108.91
8,474.29
108.91
8,474.13
S= 108.91
OTROS
LEVEL 4
0.95SA__________________*99.61
=
Net Rate
94.63
44,192.21
94.63
44,191.98
S= 94.63
PISOS Y PAVIMENTOS
n
LEVEL 3
CONTRAPISOS
LEVEL 4
Bill Quantity=7,142.66 m
#
1) Mano de obra
9
L008V
Operario
20.93/hh________________*3.00
9.13
65,212.49
L011V
Oficial
17.31/hh________________*1.00
2.52
17,999.50
L012V
Peon
15.71/hh________________*6.00
13.71
97,925.87
26.65/hm________________*1.00
2) Equipos
8
APPLIED FACTOR
3.88
27,713.52
29.24
208,851.38
3) Materiales
#
M2100001 Cemento Portland Tipo I bls 42.5 Kg
14.93/bls_______________*0.3980 +5%waste
6.24
44,570.20
35.00/m3________________*0.0890 +5%waste
3.27
23,356.50
6.00/m3_________________*0.0336 +5%waste
0.21
1,499.96
4.50/p2_________________*0.1800
0.81
5,785.55
________________________/ 1
10.53
75,212.21
39.78
284,099.41
APPLIED FACTOR
Net Rate
D= 1.69
19:39
26/02/14
L= 22.54
M= 11.22
S= 2.14
E= 2.18
30.
AI
MEP2013
Bill Quantity=414.64 m
#
1) Mano de obra
9
L008V
Operario
20.93/hh________________*3.00
11.16
4,627.38
L011V
Oficial
17.31/hh________________*1.00
3.08
1,277.09
L012V
Peon
15.71/hh________________*6.00
16.76
6,949.37
26.65/hm________________*1.00
2) Equipos
8
APPLIED FACTOR
4.74
1,965.39
35.74
14,819.23
3) Materiales
#
M2100001 Cemento Portland Tipo I bls 42.5 Kg
14.93/bls_______________*0.5140 +5%waste
8.06
3,342.00
35.00/m3________________*0.0890 +5%waste
3.27
1,355.87
3.06/kg_________________*0.5140 +5%waste
1.65
684.16
6.00/m3_________________*0.0336 +5%waste
0.21
87.07
4.50/p2_________________*0.1800
0.81
335.86
________________________/ 1
APPLIED FACTOR
Net Rate
D= 2.07
L= 27.55
M= 14.84
S= 2.61
14.00
5,804.96
49.74
20,625.90
E= 2.67
PISOS
LEVEL 4
Bill Quantity=245.20 m
02.04.02
=
Net Rate
507.52
124,443.90
507.52
124,443.12
S= 507.52
19:39
26/02/14
31.
AI
MEP2013
Bill Quantity=201.43 m
02.04.02
L008V
Operario
20.93/hh________________*3.00
12.56
L011V
Oficial
17.31/hh________________*1.00
3.46
2,529.96
696.95
L012V
Peon
15.71/hh________________*6.00
18.86
3,798.97
26.65/hm________________*1.00
2) Equipos
APPLIED FACTOR
5.33
1,073.62
40.21
8,099.50
3) Materiales
#
M2100001 Cemento Portland Tipo I bls 42.5 Kg
14.93/bls_______________*0.5140 +5%waste
8.06
1,623.53
35.00/m3________________*0.0890 +5%waste
3.27
658.68
3.06/kg_________________*0.5140 +5%waste
1.65
332.36
6.00/m3_________________*0.0336 +5%waste
0.21
42.30
4.50/p2_________________*0.6400
2.88
580.12
________________________/ 1
16.07
3,236.98
APPLIED FACTOR
ACABADO PULIDO
==============
1) Acabado con alisadora
#
9
L008V
20.93/hh________________*1.00
4.19
843.99
Operario
42.22/hm________________*1.00
8.44
1,700.07
12.63
2,544.06
APPLIED FACTOR
2) Materiales
M2100001 Cemento Portland Tipo I bls 42.5 Kg
14.93/bls_______________/42.50
=
Net Rate
D= 4.66
19:39
26/02/14
L= 34.77
M= 17.46
S= 3.26
0.35
70.50
69.26
13,951.86
E= 9.12
32.
AI
MEP2013
Bill Quantity=522.39 m
02.04.02 En rampas
L008V
Operario
20.93/hh________________*3.00
9.13
4,769.42
L011V
Oficial
17.31/hh________________*1.00
2.52
1,316.42
L012V
Peon
15.71/hh________________*6.00
13.71
7,161.97
26.65/hm________________*1.00
2) Equipos
8
APPLIED FACTOR
3.88
2,026.87
29.24
15,274.68
3) Materiales
#
M2100001 Cemento Portland Tipo I bls 42.5 Kg
14.93/bls_______________*0.3980 +5%waste
6.24
3,259.71
35.00/m3________________*0.0890 +5%waste
3.27
1,708.22
6.00/m3_________________*0.0336 +5%waste
0.21
109.70
4.50/p2_________________*0.1800
0.81
423.14
________________________/ 1
10.53
5,500.77
APPLIED FACTOR
PULIDO
======
1) Mano de obra
#
9
L008V
20.93/hh________________*1.00
4.19
2,188.81
Operario
42.22/hm________________*1.00
8.44
4,408.97
12.63
6,597.79
APPLIED FACTOR
14.93/bls_______________/42.50
0.35
182.84
BRUADO @10CM
=============
1) Mano de obra
#
9
L008V
Operario
20.93/hh________________*1.00
0.42
219.40
L012V
Peon
15.71/hh________________*1.00
0.31
161.94
APPLIED FACTOR
D= 4.02
L= 26.97
M= 11.68
S= 2.52
0.73
381.34
53.49
27,942.76
E= 8.30
Bill Quantity=52.40 m
1) Mano de obra
#
9
L008V
Operario
20.93/hh________________*1.00
15.22
797.53
L012V
Peon
15.71/hh________________*0.33
3.77
197.55
APPLIED FACTOR
19.00
995.60
2) Materiales
#
M80a0503 Ceram. EMILCERAMICA PT White bark
151.44
7,935.46
24.64/bls_______________*0.200 +5%waste
5.17
270.91
3.94/kg_________________*0.600 +5%waste
2.48
129.95
M80z0920 Crucetas
0.03/und________________*9.000
0.27
14.15
6.00/m3_________________*0.065
0.39
20.44
________________________/ 1
159.75
8,370.90
178.75
9,366.56
APPLIED FACTOR
Net Rate
L= 17.05
19:39
26/02/14
M= 160.21
S= 1.49
33.
AI
MEP2013
Bill Quantity=25.00 ml
1) Mano de obra
#
9
L008V
Operario
20.93/hh________________*1.00
15.22
L012V
Peon
15.71/hh________________*0.33
3.77
380.50
94.25
APPLIED FACTOR
19.00
475.00
2) Materiales
#
M80a0504 Ceram. EMILCERAMICA Grey panther
287.73/m2_______________*0.450 +5%waste
135.95
3,398.75
9.40/bls________________*0.090 +5%waste
0.89
22.25
3.38/kg_________________*0.270 +5%waste
0.96
24.00
M80z0920 Crucetas
0.03/und________________*9.000
0.27
6.75
6.00/m3_________________*0.065
0.39
9.75
________________________/ 1
138.46
3,461.50
157.45
3,936.34
APPLIED FACTOR
Net Rate
L= 17.05
M= 138.91
S= 1.49
Bill Quantity=4,556.02 m
02.04.02 7mm
1) Mano de obra
#
9
L008V
Operario
20.93/hh________________*1.00
4.91
22,370.06
L012V
Peon
15.71/hh________________*1.00
3.69
16,811.71
APPLIED FACTOR
8.60
39,181.77
8.60
39,172.75
Net Rate
L= 7.67
M= 0.22
S= 0.70
Bill Quantity=347.43 m
1) Mano de obra
#
9
L008V
Operario
20.93/hh________________*1.00
15.22
5,287.88
L012V
Peon
15.71/hh________________*0.33
3.77
1,309.81
APPLIED FACTOR
19.00
6,601.17
2) Materiales
#
M80a0501 Ceram. EMILCERAMICA Lappato 44x89 PTCWL
180.79/m2_______________*1.000 +5%waste
189.83
65,952.64
24.64/bls_______________*0.200 +3%waste
5.08
1,764.94
3.94/kg_________________*0.600 +3%waste
2.44
847.73
M80z0920 Crucetas
0.03/und________________*9.000
0.27
93.81
6.00/m3_________________*0.065 +3%waste
0.40
138.97
________________________/ 1
198.02
68,798.09
217.01
75,396.56
APPLIED FACTOR
Net Rate
L= 17.05
19:39
26/02/14
M= 198.47
S= 1.49
34.
AI
MEP2013
Bill Quantity=732.55 m
L008V
Operario
20.93/hh________________*3.00
8.37
6,131.44
L011V
Oficial
17.31/hh________________*1.00
2.31
1,692.19
L012V
Peon
15.71/hh________________*6.00
12.57
9,208.15
26.65/hm________________*1.00
2) Equipos
8
APPLIED FACTOR
3.55
2,600.55
26.81
19,639.67
3) Materiales
#
M2100001 Cemento Portland Tipo I bls 42.5 Kg
14.93/bls_______________*0.5140 +5%waste
8.06
5,904.35
35.00/m3________________*0.0890 +5%waste
3.27
2,395.44
6.00/m3_________________*0.5140 +5%waste
3.24
2,373.46
4.50/p2_________________*0.0750
0.34
249.07
________________________/ 1
14.90
10,915.00
APPLIED FACTOR
L008V
Operario
20.93/hh________________*1.00
1.40
1,025.57
42.22/hm________________*1.00
2.81
2,058.47
4.21
3,084.04
0.35
256.39
2) Equipos
8
APPLIED FACTOR
3) Materiales
#
M2100001 Cemento Portland Tipo I bls 42.5 Kg
14.93/bls_______________/42.50
________________________/ 1
APPLIED FACTOR
=
Net Rate
D= 2.33
19:39
26/02/14
L= 21.92
M= 15.91
S= 2.07
0.35
256.39
46.27
33,896.68
E= 4.04
35.
AI
MEP2013
Bill Quantity=18.14 m
23.68
===========================
#
1) Mano de obra
9
L008V
Operario
20.93/hh________________*3.00
9.13
L011V
Oficial
17.31/hh________________*1.00
2.52
165.62
45.71
L012V
Peon
15.71/hh________________*6.00
13.71
248.70
26.65/hm________________*1.00
2) Equipos
8
APPLIED FACTOR
3.88
70.38
29.24
530.41
3) Materiales
#
M2100001 Cemento Portland Tipo I bls 42.5 Kg
14.93/bls_______________*0.3980 +5%waste
6.24
113.19
35.00/m3________________*0.0890 +5%waste
3.27
59.32
6.00/m3_________________*0.0336 +5%waste
0.21
3.81
4.50/p2_________________*0.1800
0.81
14.69
________________________/ 1
10.53
191.01
5.58
101.22
5.58
101.22
APPLIED FACTOR
PINTURA ANTIBACTERIAL
=====================
#
1) Mano de obra
9
L008V
Operario
20.93/hh________________*1.00
APPLIED FACTOR
2) Materiales
M5490001 Pintura antibacterial
45.00/gln_______________*0.415
=
Net Rate
D= 1.69
19:39
26/02/14
L= 27.58
M= 30.02
S= 2.56
18.67
338.67
64.03
1,161.55
E= 2.18
36.
AI
MEP2013
Bill Quantity=15.61 m
L008V
Operario
20.93/hh________________*3.00
8.37
L011V
Oficial
17.31/hh________________*1.00
2.31
130.66
36.06
L012V
Peon
15.71/hh________________*6.00
12.57
196.22
26.65/hm________________*1.00
2) Equipos
8
APPLIED FACTOR
3.55
55.42
26.81
418.50
3) Materiales
#
M2100001 Cemento Portland Tipo I bls 42.5 Kg
14.93/bls_______________*0.5140 +5%waste
8.06
125.82
35.00/m3________________*0.0890 +5%waste
3.27
51.04
6.00/m3_________________*0.5140 +5%waste
3.24
50.58
4.50/p2_________________*0.0750
0.34
5.31
________________________/ 1
14.90
232.59
APPLIED FACTOR
ACABADO PULIDO
==============
1) Mano de obra + Alisadora
#
9
L008V
20.93/hh________________*1
1.40
21.85
Operario
42.22/hm________________*1
2.81
43.86
4.21
65.72
0.35
5.46
0.35
5.46
8.37
130.66
8.37
130.66
57.11
891.49
APPLIED FACTOR
2) Materiales
#
M2100001 Cemento Portland Tipo I bls 42.5 Kg
14.93/bls_______________/42.50
________________________/ 1
APPLIED FACTOR
L008V
Operario
20.93/hh________________*1.00
APPLIED FACTOR
2) Materiales
#
M3012502 Agregado de polvo de cuarzo
3.40/kg_________________*16.00 +5%waste
________________________/ 1
APPLIED FACTOR
=
Net Rate
D= 2.33
19:39
26/02/14
L= 29.48
M= 73.21
S= 2.70
57.11
891.49
111.75
1,744.48
E= 4.04
37.
AI
MEP2013
Bill Quantity=197.54 m
1) Mano de obra
#
9
L008V
Operario
20.93/hh________________*1.00
15.22
L012V
Peon
15.71/hh________________*0.33
3.77
3,006.56
744.73
APPLIED FACTOR
19.00
3,753.26
2) Materiales
#
M80a0601 Ceram.ROSSELLO Gress Sanit. Habano 30x30 75.33/m2________________*1.00 +5%waste
79.10
15,625.41
24.64/bls_______________*0.33 +3%waste
8.38
1,655.39
29.84/bls_______________*0.08 +3%waste
2.46
485.95
M80z0920 Crucetas
0.03/und________________*9.00
0.27
53.34
6.00/m3_________________*0.075 5%waste
0.45
88.89
________________________/ 1
90.65
17,907.00
109.65
21,659.83
1,219.12
APPLIED FACTOR
Net Rate
L= 17.05
M= 91.11
S= 1.49
Bill Quantity=80.10 m
1) Mano de obra
#
9
L008V
Operario
20.93/hh________________*1.00
15.22
L012V
Peon
15.71/hh________________*0.33
3.77
301.98
APPLIED FACTOR
19.00
1,521.90
2) Materiales
#
M80a0501 Ceram. EMILCERAMICA Lappato 44x89 PTCWL
180.79/m2_______________*1.000 +5%waste
189.83
15,205.38
24.64/bls_______________*0.200 +3%waste
5.08
406.91
3.94/kg_________________*0.600 +3%waste
2.44
195.44
M80z0920 Crucetas
0.03/und________________*9.000
0.27
21.63
6.00/m3_________________*0.065 +3%waste
0.40
32.04
________________________/ 1
198.02
15,861.40
217.01
17,382.68
APPLIED FACTOR
Net Rate
L= 17.05
19:39
26/02/14
M= 198.47
S= 1.49
38.
AI
MEP2013
Bill Quantity=44.60 m
1) Mano de obra
#
9
L008V
Operario
20.93/hh________________*1.00
15.22
678.81
L012V
Peon
15.71/hh________________*0.33
3.77
168.14
APPLIED FACTOR
19.00
847.40
680.15
2) Materiales
#
M80a0021 Ceram. CELIMA Granilla Nevada 30x30cm
14.53/m2________________*1.000 +5%waste
15.25
9.40/bls________________*0.170 +3%waste
1.65
73.59
3.38/kg_________________*0.700 +3%waste
2.43
108.38
M80z0920 Crucetas
0.03/und________________*9.000
0.27
12.04
6.00/m3_________________*0.070 +3%waste
0.43
19.18
________________________/ 1
20.03
893.34
39.03
1,740.74
APPLIED FACTOR
Net Rate
L= 17.05
19:39
26/02/14
M= 20.49
S= 1.49
39.
AI
MEP2013
Bill Quantity=25.50 m2
L008V
Operario
20.93/hh________________*3.00
8.37
L011V
Oficial
17.31/hh________________*1.00
2.31
213.44
58.91
L012V
Peon
15.71/hh________________*6.00
12.57
320.54
26.65/hm________________*1.00
2) Equipos
8
APPLIED FACTOR
3.55
90.53
26.81
683.66
3) Materiales
#
M2100001 Cemento Portland Tipo I bls 42.5 Kg
14.93/bls_______________*0.5140 +5%waste
8.06
205.53
35.00/m3________________*0.0890 +5%waste
3.27
83.39
6.00/m3_________________*0.5140 +5%waste
3.24
82.62
4.50/p2_________________*0.0750
0.34
8.67
________________________/ 1
14.90
379.95
35.70
APPLIED FACTOR
ACABADO PULIDO
==============
1) Acabado con alisadora
#
9
L008V
20.93/hh________________*1.00
1.40
Operario
42.22/hm________________*1.00
2.81
71.66
4.21
107.36
0.35
8.93
0.35
8.93
5.77
147.14
5.77
147.14
582.42
APPLIED FACTOR
2) Materiales
M2100001 Cemento Portland Tipo I bls 42.5 Kg
14.93/bls_______________/42.50
=
PINTURA EPOXICA (JET POX 2000)
==============================
1) Mano de obra
#
9
L011V
Oficial
17.31/hh________________*1.00
APPLIED FACTOR
2) Materiales
#
M5460002 Epoxico Jet Pox 2000 CPPQ(1gln-R+1gln-C) 248.81/kit______________*0.0918
22.84
45.04/gln_______________*0.0285
1.28
32.64
________________________/ 1
24.12
615.06
76.17
1,942.22
114.54
9,419.77
114.54
9,419.44
APPLIED FACTOR
Net Rate
D= 2.33
L= 27.05
M= 40.19
S= 2.56
E= 4.04
Bill Quantity=82.24 m
Sbfa3001 Alfombra
2.78____________________*41.20
=
Net Rate
S= 114.54
19:39
26/02/14
40.
AI
MEP2013
Bill Quantity=38.50 m
02.04.02 60x60cm
1) Mano de obra
#
9
L008V
Operario
20.93/hh________________*1.00
15.22
585.97
L012V
Peon
15.71/hh________________*0.33
3.77
145.15
APPLIED FACTOR
19.00
731.50
2) Materiales
#
M80a0901 Ceram. Balsat Lappato 60x60
28.63/m2________________*1.00 +5%waste
30.06
1,157.31
9.40/bls________________*0.20 +3%waste
1.94
74.69
3.38/kg_________________*0.60 +3%waste
2.09
80.47
M80z0920 Crucetas
0.03/und________________*9.00
0.27
10.40
6.00/m3_________________*0.065 +3%waste
0.40
15.40
________________________/ 1
34.75
1,337.88
53.75
2,069.37
17,576.92
APPLIED FACTOR
Net Rate
L= 17.05
M= 35.21
S= 1.49
Bill Quantity=2,099.99 m
L008V
Operario
20.93/hh________________*3.00
8.37
L011V
Oficial
17.31/hh________________*1.00
2.31
4,850.98
L012V
Peon
15.71/hh________________*6.00
12.57
26,396.87
26.65/hm________________*1.00
2) Equipos
8
APPLIED FACTOR
3.55
7,454.96
26.81
56,300.73
3) Materiales
#
M2100001 Cemento Portland Tipo I bls 42.5 Kg
14.93/bls_______________*0.5140 +5%waste
8.06
16,925.92
35.00/m3________________*0.0890 +5%waste
3.27
6,866.97
6.00/m3_________________*0.5140 +5%waste
3.24
6,803.97
4.50/p2_________________*0.0750
0.34
714.00
________________________/ 1
14.90
31,289.85
2.02
4,241.98
APPLIED FACTOR
ACABADO FROTACHADO
==================
1) Mano de obra
#
9
L008V
Operario
20.93/hh________________*1.00
APPLIED FACTOR
=
Net Rate
D= 1.55
19:39
26/02/14
L= 22.49
M= 15.58
S= 2.11
2.02
4,241.98
43.73
91,829.07
E= 2.00
41.
AI
MEP2013
Bill Quantity=11.52 m
1.00____________________*185.00
=
Net Rate
185.00
2,131.20
185.00
2,131.20
1,745.84
S= 185.00
Bill Quantity=222.40 m
02.04.02
L008V
Operario
20.93/hh________________*3.00
7.85
L011V
Oficial
17.31/hh________________*1.00
2.16
480.38
L012V
Peon
15.71/hh________________*6.00
11.79
2,622.10
26.65/hm________________*1.00
2) Equipos
8
APPLIED FACTOR
3.33
740.59
25.13
5,588.91
3) Materiales
M3018095 Membrana asfaltica autoadhesiva
23.00/m2________________*1.05
24.15
5,370.96
70.00/m2________________*1.05
73.50
16,346.40
14.93/bls_______________*0.3700 +5%waste
5.80
1,289.92
35.00/m3________________*0.0530 +5%waste
1.95
433.68
6.00/m3_________________*0.0136 +5%waste
0.09
20.02
4.50/p2_________________*0.0600
0.27
60.05
105.75
23,518.80
696.11
=
ACERO
=====
1) Mano de obra
#
9
L008Vb
Operario Acero
20.93/hh________________*1.00
3.13
L011Vb
Oficial Acero
17.31/hh________________*1.00
2.58
573.79
APPLIED FACTOR
5.71
1,269.90
2) Materiales
M0300002 Acero corrugado fy= 4200 kg/cm2 grado 60 2.22/kg_________________*5.6 +5%waste
13.05
2,902.32
3.48/Kg_________________*0.04 *5.6
0.78
173.47
0.20/und________________*0.08 *5.6
0.09
20.02
13.92
3,095.81
150.52
33,475.36
=
Net Rate
D= 1.46
19:39
26/02/14
L= 24.49
M= 120.40
S= 2.29
E= 1.88
42.
AI
MEP2013
Bill Quantity=1,101.65 m
1) Mano de obra
#
9
L008V
Operario
20.93/hh________________*1.00
15.22
L012V
Peon
15.71/hh________________*0.33
3.77
16,767.11
4,153.22
APPLIED FACTOR
19.00
20,931.35
2) Materiales
#
M80a0701 Cer. PORCELANOSA Arizona Stone 44.3x44.3 89.42/m2________________*1.00 +5%waste
93.90
103,444.94
24.64/bls_______________*0.20 +3%waste
5.08
5,596.38
3.94/kg_________________*0.60 +3%waste
2.44
2,688.03
M80z0920 Crucetas
0.03/und________________*9.00
0.27
297.45
6.00/m3_________________*0.065 +3%waste
0.40
440.66
________________________/ 1
102.08
112,456.43
121.08
133,383.19
APPLIED FACTOR
Net Rate
L= 17.05
M= 102.53
S= 1.49
Bill Quantity=408.70 m
1) Mano de obra
#
9
L008V
Operario
20.93/hh________________*1.00
15.22
6,220.41
L012V
Peon
15.71/hh________________*0.33
3.77
1,540.80
APPLIED FACTOR
19.00
7,765.30
2) Materiales
#
M80a0702 Cer.PORCELANOSA Arizona StoneT 44.3x44.3 89.42/m2________________*1.00 +5%waste
93.90
38,376.93
24.64/bls_______________*0.20 +3%waste
5.08
2,076.20
3.94/kg_________________*0.60 +3%waste
2.44
997.23
M80z0920 Crucetas
0.03/und________________*9.00
0.27
110.35
6.00/m3_________________*0.065 +3%waste
0.40
163.48
________________________/ 1
102.08
41,720.10
121.08
49,483.69
116.73
17,976.42
116.73
17,976.76
APPLIED FACTOR
Net Rate
L= 17.05
M= 102.53
S= 1.49
Bill Quantity=154.00 ml
=
Net Rate
S= 116.73
19:39
26/02/14
43.
AI
MEP2013
Bill Quantity=727.30 ml
L008V
Operario
20.93/hh________________*3.00
9.04
6,574.79
L011V
Oficial
17.31/hh________________*1.00
2.49
1,810.98
L012V
Peon
15.71/hh________________*6.00
13.58
9,876.73
26.65/hm________________*1.00
2) Equipos
8
APPLIED FACTOR
3.84
2,792.83
28.95
21,055.34
3) Materiales
#
M2100001 Cemento Portland Tipo I bls 42.5 Kg
14.93/bls_______________*0.5140 +5%waste
4.35
3,163.76
35.00/m3________________*0.0890 +5%waste
1.77
1,287.32
6.00/m3_________________*0.5140 +5%waste
1.75
1,272.78
4.50/p2_________________*0.0780
0.19
138.19
________________________/ 1 *0.54
8.06
5,862.04
6.44
4,683.81
6.44
4,683.81
0.19
138.19
APPLIED FACTOR
L008V
Operario
20.93/hh________________*1.00
APPLIED FACTOR
2) Materiales
M2100001 Cemento Portland Tipo I bls 42.5 Kg
14.93/bls_______________/42.50
*0.54
=
Net Rate
D= 1.68
L= 28.13
M= 9.07
S= 2.61
31,737.55
LEVEL 4
Sardinel h=0.30 m
Bill Quantity=3.00 ml
02.04.03
138.19
43.64
E= 2.16
SARDINELES DE CONCRETO
6a0061
0.19
Price Qty 1
D023
M2
0.30
9.34
2.80
8.40
SARDINEL
2
C300
M3
0.045
428.78
19.30
57.89
m2
0.30
16.19
4.86
14.57
m2
0.30
4.54
1.36
4.08
Net Rate
28.31
6a0059
M= 18.84
S= 0.75
Sardinel h=0.10 m
Bill Quantity=9.70 ml
02.04.03
84.94
E= 0.35
Price Qty 1
D023
M2
0.30
9.34
2.80
27.16
SARDINEL
2
C300
M3
0.045
428.78
19.30
187.16
m2
0.30
16.19
4.86
47.10
Net Rate
26.95
L= 7.24
19:39
26/02/14
M= 18.70
S= 0.65
261.43
E= 0.35
44.
AI
MEP2013
6a0059
Sardinel h=0.10 m
Bill Quantity=61.00 ml
02.04.03
Price Qty 1
D023
M2
0.30
9.34
2.80
170.83
SARDINEL
2
C300
M3
0.045
428.78
19.30
1,177.01
m2
0.30
16.19
4.86
296.22
Net Rate
26.95
L= 7.24
M= 18.70
S= 0.65
ZOCALOS Y CONTRAZOCALOS
n
1,644.06
E= 0.35
LEVEL 3
ZOCALOS
LEVEL 4
Bill Quantity=316.37 m
1) Mano de obra
#
9
L008V
Operario
20.93/hh________________*1.00
12.88
4,074.85
L012V
Peon
15.71/hh________________*0.33
3.19
1,009.22
APPLIED FACTOR
16.07
5,084.07
2) Materiales
#
M80a0007 Ceram. CELIMA America Blanco 30x30cm
14.27/m2________________*1.00 +4%waste
14.84
4,694.93
9.40/bls________________*0.17 +5%waste
1.68
531.50
3.38/kg_________________*0.70 +5%waste
2.48
784.60
M80z0920 Crucetas
0.03/und________________*9.00
0.27
85.42
6.00/m3_________________*0.008
0.05
15.82
________________________/ 1
19.31
6,109.10
35.39
11,194.88
APPLIED FACTOR
Net Rate
L= 14.43
M= 19.70
S= 1.26
Bill Quantity=46.28 m
1) Mano de obra
#
9
L008V
Operario
20.93/hh________________*1.00
12.88
596.09
L012V
Peon
15.71/hh________________*0.33
3.19
147.63
APPLIED FACTOR
16.07
743.72
6,392.66
2) Materiales
#
M80a0502 Ceram. EMILCERAMICA Natural 30x60 PTCWL
132.81/m2_______________*1.00 +4%waste
138.13
9.40/bls________________*0.20 +5%waste
1.97
91.17
3.38/kg_________________*0.79 +5%waste
2.80
129.58
M80z0920 Crucetas
0.03/und________________*9.00
0.27
12.50
6.00/m3_________________*0.08 +5%waste
0.50
23.14
________________________/ 1
143.67
6,649.05
159.75
7,393.06
APPLIED FACTOR
Net Rate
L= 14.43
19:39
26/02/14
M= 144.06
S= 1.26
45.
AI
MEP2013
Bill Quantity=91.28 m
1) Mano de obra
#
9
L008V
Operario
20.93/hh________________*1.00
12.88
L012V
Peon
15.71/hh________________*0.33
3.19
1,175.69
291.18
APPLIED FACTOR
16.07
1,466.87
2) Materiales
#
M80a0801 Ceram. SAN LORENZO Satinado 30x60cm
17.37/m2________________*1.00 +4%waste
18.06
1,648.52
9.40/bls________________*0.20 +5%waste
1.97
179.82
3.38/kg_________________*0.62 +5%waste
2.20
200.82
M80z0920 Crucetas
0.03/und________________*9.00
0.27
24.65
6.00/m3_________________*0.02
0.12
10.95
________________________/ 1
22.63
2,065.67
38.70
3,532.45
APPLIED FACTOR
Net Rate
L= 14.43
M= 23.01
S= 1.26
Bill Quantity=29.00 m
1) Mano de obra
#
9
L008V
Operario
20.93/hh________________*1.00
13.96
404.84
L012V
Peon
15.71/hh________________*0.33
3.46
100.34
APPLIED FACTOR
17.41
504.89
2) Materiales
#
M80d1008 Piedra Volcan color arena 40x20cm SPAZIO 37.31/m2________________*1.00 +5%waste
39.17
1,135.93
25.08/bls_______________*0.28 +5%waste
7.37
213.73
3.94/kg_________________*0.60 +5%waste
2.48
71.92
M80z0920 Crucetas
0.03/und________________*4.00
0.12
3.48
6.00/m3_________________*0.065 +5%waste
0.41
11.89
80.00/gln_______________*0.072
________________________/ 1
APPLIED FACTOR
Net Rate
L= 15.63
M= 55.73
19:39
26/02/14
167.04
1,604.28
72.73
2,109.20
S= 1.37
CONTRAZOCALOS
5.76
55.32
LEVEL 4
46.
AI
MEP2013
Bill Quantity=138.67 ml
1) Mano de obra
#
9
L008V
Operario
20.93/hh________________*1.00
8.81
L012V
Peon
15.71/hh________________*0.33
2.18
1,221.68
302.30
APPLIED FACTOR
11.00
1,525.37
2) Materiales
#
M80a0501 Ceram. EMILCERAMICA Lappato 44x89 PTCWL
180.79/m2_______________*0.10 +6%waste
19.16
2,656.92
9.40/bls________________*0.02 +5%waste
0.20
27.73
3.38/kg_________________*0.07 +5%waste
0.25
34.67
M80z0920 Crucetas
0.03/und________________*2.00
0.06
8.32
6.00/m3_________________*0.008 +5%waste
0.05
6.93
________________________/ 1
19.72
2,734.57
30.72
4,259.63
224.04
APPLIED FACTOR
Net Rate
L= 9.87
M= 19.98
S= 0.86
Bill Quantity=25.43 ml
1) Mano de obra
#
9
L008V
Operario
20.93/hh________________*1.00
8.81
L012V
Peon
15.71/hh________________*0.33
2.18
55.44
APPLIED FACTOR
11.00
279.73
2) Materiales
#
M80c1010 Porc. CELIMA Mate Beige Esmaltado 60x60
27.47/m2________________*0.1000 +10%waste
3.02
76.80
24.64/bls_______________*0.0200 +5%waste
0.52
13.22
3.94/kg_________________*0.0700 +5%waste
0.29
7.37
M80z0920 Crucetas
0.03/und________________*2.0000
0.06
1.53
6.00/m3_________________*0.0170 +5%waste
0.11
2.80
________________________/ 1
4.00
101.72
14.99
381.29
APPLIED FACTOR
Net Rate
L= 9.87
19:39
26/02/14
M= 4.26
S= 0.86
47.
AI
MEP2013
Bill Quantity=749.96 ml
02.05.02
CONTRAZOCALO DE CEMENTO
=======================
1) Mano de obra
#
9
L008V
Operario
20.93/hh________________*1.00
5.58
4,184.78
L012V
Peon
15.71/hh________________*0.33
1.38
1,034.94
APPLIED FACTOR
6.97
5,227.22
2) Materiales
#
M2100001 Cemento Portland Tipo I bls 42.5 Kg
14.93/bls_______________*0.0111 +5%waste
0.17
127.49
35.00/m3________________*0.0016 +5%waste
0.06
45.00
6.00/m3_________________*0.0004 +5%waste
0.00
4.50/p2_________________*0.1417
0.64
479.97
________________________/ 1
0.87
652.47
3.42
2,564.86
3.42
2,564.86
0.04
30.00
APPLIED FACTOR
ACABADO PULIDO
==============
1) Mano de obra
#
9
L008V
Operario
20.93/hh________________*1.00
APPLIED FACTOR
2) Materiales
#
M2100001 Cemento Portland Tipo I bls 42.5 Kg
14.93/bls_______________/42.50 *0.10
________________________/ 1
APPLIED FACTOR
=
Net Rate
L= 9.33
M= 1.15
0.04
30.00
11.29
8,468.06
S= 0.81
LEVEL 4
02.05.03
822.25/und______________*2
1,644.50
271,342.50
822.25/und______________*1
822.25
135,671.25
80.00/und_______________*1
80.00
13,200.00
0.00/und________________*1
0.00
1.00____________________*1800.00
=
Sbmn2001 Carp. Madera - Puertas
Net Rate
M= 2,546.76
2,546.76
420,215.40
1,800.00
297,000.00
4,346.76
717,214.58
324.83
88,720.82
324.83
88,720.82
S= 1,800.00
c0000001 P2
02.05.03
1.00____________________*324.83
=
Net Rate
S= 324.83
19:39
26/02/14
48.
AI
MEP2013
c0000002 P3
02.05.03
1.00____________________*324.83
=
Net Rate
324.83
4,482.65
324.83
4,482.65
324.83
14,120.36
324.83
14,120.36
S= 324.83
c0000003 P4
02.05.03
1.00____________________*324.83
=
Net Rate
S= 324.83
k1500001 P5
02.05.03
2.64____________________*530.00
1,399.73
25,195.14
158.46/und______________*1
158.46
2,852.28
198.08/und______________*1
198.08
3,565.44
21.13/und_______________*3
63.38
1,140.84
73.95/und
73.95
1,331.10
264.10/und
264.10
4,753.80
110.92/und
110.92
1,996.56
2,268.62
40,835.16
2,268.62
40,835.14
=
Net Rate
S= 2,268.62
n2000004 P6
02.05.03
1.00____________________*918.75
918.75
4,593.75
601.50/und______________*1
601.50
3,007.50
60.00/und_______________*1
60.00
300.00
1,580.25
7,901.25
1,580.25
7,901.25
981.75
981.75
105.65
105.65
67.17
67.17
1,154.57
1,154.57
1,154.57
1,154.57
=
Net Rate
M= 661.50
S= 918.75
n2000003 P7
02.05.03
1.00____________________*981.75
22.39/und_______________*3
=
Net Rate
M= 172.82
19:39
26/02/14
S= 981.75
49.
AI
MEP2013
k1000020 P8
02.05.03
0.95____________________*2300.00
2,185.00
2,185.00
333.60/m2_______________*0.654*0.887
193.52
193.52
22.39/und_______________*3.00
67.17
67.17
105.65
105.65
M80b123
M80b124
105.65/und______________*1
=
Net Rate
M= 471.99
105.65
105.65
2,656.99
2,656.99
2,656.99
2,656.99
2,808.75
2,808.75
S= 2,185.00
n2000005 P9
02.05.03
1.00____________________*2808.75
22.39/und_______________*3
67.17
67.17
105.65/und______________*1
105.65
105.65
2,981.57
2,981.57
2,981.57
2,981.57
981.75
2,945.25
=
Net Rate
M= 172.82
S= 2,808.75
n2000006 P10
02.05.03
1.00____________________*981.75
22.39/und_______________*3
67.17
201.51
105.65/und______________*1
105.65
316.95
333.60/m2_______________*0.68*0.85
192.82
578.46
1,347.39
4,042.17
1,347.39
4,042.16
=
Net Rate
M= 365.64
S= 981.75
k1000001 P11
02.05.03
0.95____________________*3200.00
3,040.00
3,040.00
556.00/m2_______________*0.30*0.485
80.90
80.90
22.39/und_______________*3.00
67.17
67.17
105.65
105.65
M80b123
M80b124
105.65/und______________*1
=
Net Rate
M= 359.37
19:39
26/02/14
105.65
105.65
3,399.37
3,399.37
3,399.37
3,399.37
S= 3,040.00
50.
AI
MEP2013
02.05.03
1.00____________________*1233.75
1,233.75
3,701.25
4,933.51
14,800.53
847.69/m2_______________*0.923*0.20*2
312.97
938.91
847.69/m2_______________*1.89*0.20*2
640.86
1,922.58
200.00/und______________*2
400.00
1,200.00
7,521.09
22,563.27
7,521.09
22,563.26
3,570.00
10,710.00
1,129.88
3,389.64
108.09
324.27
3,306.00
9,918.00
8,113.96
24,341.88
8,113.96
24,341.89
3,570.00
14,280.00
1,129.88
4,519.52
108.09
432.36
3,306.00
13,224.00
8,113.96
32,455.84
8,113.96
32,455.85
1,086.75
2,173.50
564.94
1,129.88
128.43/und______________*1
128.43
256.86
847.69/m2_______________*0.20*0.60
101.72
203.44
847.69/m2_______________*0.94*0.20
159.37
318.74
2,041.21
4,082.42
2,041.21
4,082.42
=
Net Rate
M= 5,333.51
S= 2,187.58
02.05.03
1.00____________________*3570.00
333.60/m2_______________*0.54*0.30*2
S= 6,876.00
02.05.03
1.00____________________*3570.00
333.60/m2_______________*0.54*0.30*2
S= 6,876.00
n2000010 P15
02.05.03
1.00____________________*1086.75
=
Net Rate
M= 693.37
S= 1,347.84
n2000013 P16
02.05.03
1.00____________________*2415.00
2,415.00
9,660.00
105.65/und______________*1
105.65
422.60
22.39/und_______________*3
67.17
268.68
2,587.82
10,351.28
2,587.82
10,351.27
=
Net Rate
M= 172.82
19:39
26/02/14
S= 2,415.00
51.
AI
MEP2013
n2000011 P17
02.05.03
1.00____________________*813.75
813.75
3,255.00
822.25/und______________*3
2,466.76
9,867.04
105.65
422.60
3,386.16
13,544.64
3,386.16
13,544.62
334.68
3,386.96
334.68
3,386.96
2,232.50
2,232.50
=
Net Rate
M= 2,572.41
S= 813.75
c0000004 P18
02.05.03
1.00____________________*334.68
=
Net Rate
S= 334.68
k1000002 P19
02.05.03
0.95____________________*2350.00
22.39/und_______________*3.00
67.17
67.17
M80b125
150.00/und______________*2.00
300.00
300.00
2,599.67
2,599.67
2,599.67
2,599.67
Barra de acero
=
Net Rate
M= 367.17
S= 2,232.50
k1500002 P20
02.05.03
2.64____________________*500.00
1,320.50
2,641.00
158.46/und______________*1
158.46
316.92
198.08/und______________*1
198.08
396.16
21.13/und_______________*3
63.38
126.76
39.62
79.24
Sbk01007 Cerradura
132.05/und______________*1
132.05
264.10
110.92/und______________*1
110.92
221.84
556.00/und______________*2
1,112.00
2,224.00
3,135.01
6,270.02
3,135.01
6,270.01
2,280.00
38,760.00
=
Net Rate
S= 3,135.01
k1000003 P22
02.05.03
0.95____________________*2400.00
22.39/und_______________*3
67.17
1,141.89
M80b123
105.65
1,796.05
M80b124
105.65
1,796.05
2,558.47
43,493.99
2,558.47
43,493.95
105.65/und______________*1
=
Net Rate
M= 278.47
19:39
26/02/14
S= 2,280.00
52.
AI
MEP2013
k1000004 P23
02.05.03
0.95____________________*2500.00
2,375.00
21,375.00
22.39/und_______________*3
67.17
604.53
M80b123
105.65
950.85
M80b124
105.65
950.85
2,653.47
23,881.23
2,653.47
23,881.21
2,185.00
2,185.00
105.65/und______________*1
=
Net Rate
M= 278.47
S= 2,375.00
k1000005 P24
02.05.03
0.95____________________*2300.00
22.39/und_______________*3
67.17
67.17
M80b123
105.65
105.65
M80b124
105.65/und______________*1
=
Net Rate
M= 278.47
105.65
105.65
2,463.47
2,463.47
2,463.47
2,463.47
S= 2,185.00
k1500003 P25
02.05.03
2.64____________________*530.00
1,399.73
13,997.30
158.46/und______________*1
158.46
1,584.60
198.08/und______________*1
198.08
1,980.80
21.13/und_______________*3
63.38
633.80
73.95/und_______________*1
73.95
739.50
110.92/und______________*1
110.92
1,109.20
Sbk01007 Cerradura
132.05/und______________*1
132.05
1,320.50
264.10/und______________*1
264.10
2,641.00
2,400.67
24,006.70
2,400.67
24,006.69
2,441.25
=
Net Rate
S= 2,400.67
n2000012 P26
02.05.03
1.00____________________*813.75
813.75
128.43/und______________*1
128.43
385.29
564.94
1,694.82
847.69/m2_______________*2.25*0.20
=
Net Rate
M= 693.37
19:39
26/02/14
381.46
1,144.38
1,888.58
5,665.74
1,888.58
5,665.75
S= 1,195.21
53.
AI
MEP2013
k1000006 P27
02.05.03
0.95____________________*2600.00
2,470.00
4,940.00
22.39/und_______________*3
67.17
134.34
M80b123
105.65
211.30
M80b124
105.65
211.30
2,748.47
5,496.94
2,748.47
5,496.94
2,802.50
2,802.50
105.65/und______________*1
=
Net Rate
M= 278.47
S= 2,470.00
k1000007 P27
02.05.03
0.95____________________*2950.00
22.39/und_______________*3
67.17
67.17
M80b123
105.65
105.65
M80b124
105.65/und______________*1
=
Net Rate
M= 278.47
19:39
26/02/14
105.65
105.65
3,080.97
3,080.97
3,080.97
3,080.97
S= 2,802.50
54.
AI
MEP2013
k1500004 P28
02.05.03
2.64____________________*455.00
1,201.66
158.46/und______________*1
158.46
950.76
198.08/und______________*1
198.08
1,188.48
21.13/und_______________*3
63.38
380.28
39.62
237.72
73.95/und_______________*1
73.95
443.70
110.92/und______________*1
110.92
665.52
Sbk01007 Cerradura
132.05/und______________*1
132.05
792.30
1,978.11
11,868.66
1,978.11
11,868.65
3,895.00
3,895.00
=
Net Rate
7,209.96
S= 1,978.11
k1000008 P29
02.05.03
0.95____________________*4100.00
22.39/und_______________*3
67.17
67.17
M80b123
105.65
105.65
M80b124
105.65/und______________*1
=
Net Rate
M= 278.47
105.65
105.65
4,173.47
4,173.47
4,173.47
4,173.47
S= 3,895.00
k1500005 P30
02.05.03
2.64____________________*455.00
1,201.66
1,201.66
158.46/und______________*1
158.46
158.46
198.08/und______________*1
198.08
198.08
21.13/und_______________*3
63.38
63.38
73.95/und_______________*1
73.95
73.95
110.92/und______________*1
110.92
110.92
Sbk01007 Cerradura
132.05/und______________*1
=
Net Rate
132.05
132.05
1,938.49
1,938.49
1,938.49
1,938.49
2,808.75
8,426.25
201.51
S= 1,938.49
n2000016 P31
02.05.03
1.00____________________*2808.75
22.39/und_______________*3
67.17
105.65
316.95
2,981.57
8,944.71
2,981.57
8,944.70
=
Net Rate
M= 172.82
19:39
26/02/14
S= 2,808.75
55.
AI
MEP2013
02.05.03
1.00____________________*4278.75
4,278.75
4,278.75
601.50/und______________*8
4,812.00
4,812.00
69.50/und_______________*1
69.50
69.50
69.50/und_______________*1
69.50
69.50
9,229.75
9,229.75
9,229.75
9,229.75
=
Net Rate
M= 4,951.00
S= 4,278.75
k1000009 PE4
02.05.03
0.95____________________*2300.00
2,185.00
2,185.00
333.60/m2_______________*0.70*1.25
291.90
291.90
22.39/und_______________*3.00
67.17
67.17
105.65
105.65
M80b123
M80b124
105.65/und______________*1
=
Net Rate
M= 570.37
105.65
105.65
2,755.37
2,755.37
2,755.37
2,755.37
S= 2,185.00
02.05.03
1.00____________________*1391.25
1,391.25
1,391.25
601.50/und______________*10
6,015.00
6,015.00
69.50/und_______________*1
69.50
69.50
69.50/und_______________*1
69.50
69.50
7,545.25
7,545.25
7,545.25
7,545.25
340.48
7,204.56
340.48
7,204.56
294.23
1,073.94
294.23
1,073.94
277.97
3,983.31
277.97
3,983.31
=
Net Rate
M= 6,154.00
S= 1,391.25
c0000005 PV 1
02.05.03
1.00____________________*340.48
=
Net Rate
S= 340.48
c0000006 PV 2
02.05.03
1.00____________________*294.23
=
Net Rate
S= 294.23
c0000007 PV 4
02.05.03
1.00____________________*277.97
=
Net Rate
S= 277.97
19:39
26/02/14
56.
AI
MEP2013
n3000001 L1
02.05.03
2.71____________________*331.85
=
Net Rate
900.13
10,801.56
900.13
10,801.50
744.97
15,644.37
744.97
15,644.44
900.13
24,303.51
900.13
24,303.38
744.97
19,369.22
744.97
19,369.31
801.12
7,210.08
801.12
7,210.09
468.30
8,429.40
468.30
8,429.47
744.97
6,704.73
744.97
6,704.76
983.13
8,848.17
983.13
8,848.13
S= 900.13
n3000002 L2
02.05.03
2.71____________________*274.65
=
Net Rate
S= 744.97
n3000003 L3
02.05.03
2.71____________________*331.85
=
Net Rate
S= 900.13
n3000004 L4
02.05.03
2.71____________________*274.65
=
Net Rate
S= 744.97
n3000005 L5
02.05.03
2.71____________________*295.35
=
Net Rate
S= 801.12
n3000006 L6
02.05.03
2.71____________________*172.65
=
Net Rate
S= 468.30
n3000007 L7
02.05.03
2.71____________________*274.65
=
Net Rate
S= 744.97
n3000008 L8
02.05.03
2.71____________________*362.45
=
Net Rate
S= 983.13
19:39
26/02/14
57.
AI
MEP2013
n3000009 L9
02.05.03
2.71____________________*238.70
=
Net Rate
647.46
5,827.14
647.46
5,827.15
468.30
5,619.60
468.30
5,619.65
192.85
1,735.65
192.85
1,735.69
606.23
4,849.84
606.23
4,849.85
900.13
8,101.17
900.13
8,101.13
744.97
1,489.94
744.97
1,489.95
647.46
647.46
647.46
647.46
1,993.11
1,993.11
1,993.11
1,993.11
S= 647.46
n3000010 L10
02.05.03
2.71____________________*172.65
=
Net Rate
S= 468.30
n3000011 L11
02.05.03
2.71____________________*71.10
=
Net Rate
S= 192.85
n3000012 L12
02.05.03
2.71____________________*223.50
=
Net Rate
S= 606.23
n3000013 L13
02.05.03
2.71____________________*331.85
=
Net Rate
S= 900.13
n3000014 L14
02.05.03
2.71____________________*274.65
=
Net Rate
S= 744.97
n3000015 L15
02.05.03
2.71____________________*238.70
=
Net Rate
S= 647.46
n3000016 L16
02.05.03
2.71____________________*734.80
=
Net Rate
S= 1,993.11
19:39
26/02/14
58.
AI
MEP2013
n3000017 L17
02.05.03
2.71____________________*238.70
=
Net Rate
647.46
647.46
647.46
647.46
551.17
551.17
551.17
551.17
744.97
744.97
744.97
744.97
900.13
5,400.78
900.13
5,400.75
744.97
4,469.82
744.97
4,469.84
468.30
1,404.90
468.30
1,404.91
633.36
1,900.08
633.36
1,900.07
15,146.14
30,292.28
15,146.14
30,292.27
S= 647.46
n3000018 L18
02.05.03
2.71____________________*203.20
=
Net Rate
S= 551.17
n3000019 L19
02.05.03
2.71____________________*274.65
=
Net Rate
S= 744.97
n3000020 L20
02.05.03
2.71____________________*331.85
=
Net Rate
S= 900.13
n3000021 L21
02.05.03
2.71____________________*274.65
=
Net Rate
S= 744.97
n3000022 L22
02.05.03
2.71____________________*172.65
=
Net Rate
S= 468.30
n3000023 L23
02.05.03
2.71____________________*233.50
=
Net Rate
S= 633.36
k0000001 PER1
02.05.03
2.64____________________*5735.00
=
Net Rate
S= 15,146.14
19:39
26/02/14
59.
AI
MEP2013
k1000010 PER2
02.05.03
0.95____________________*4400.00
=
Net Rate
4,180.00
8,360.00
4,180.00
8,360.00
256.80
12,423.98
256.80
12,423.98
282.75
6,868.00
282.75
6,868.00
283.37
7,954.20
283.37
7,954.20
287.63
8,283.74
287.63
8,283.74
S= 4,180.00
c1000001 FV01
02.05.03
1.00____________________*256.80
=
Net Rate
S= 256.80
c1000002 FV02
02.05.03
1.00____________________*282.75
=
Net Rate
S= 282.75
c1000003 FV03
02.05.03
1.00____________________*283.37
=
Net Rate
S= 283.37
c1000004 FV04
02.05.03
1.00____________________*287.63
=
Net Rate
S= 287.63
BARANDAS
n
LEVEL 3
BARANDAS DE MADERA
LEVEL 4
Bill Quantity=4.05 ml
02.06.01
1.00____________________*150
=
Net Rate
150.00
607.50
150.00
607.50
S= 150.00
CARPINTERIA METALICA
n
k400001
LEVEL 3
BARANDAS METALICAS
LEVEL 4
Bill Quantity=202.65 ml
2.64____________________*165.00
=
Net Rate
435.77
88,308.79
435.77
88,307.78
S= 435.77
19:39
26/02/14
60.
AI
MEP2013
k300001
2"
Bill Quantity=332.48 ml
2.64____________________*60.00
=
Net Rate
158.46
52,684.78
158.46
52,684.78
616.02
3,308.03
616.02
3,308.03
585.45
3,419.03
585.45
3,419.03
S= 158.46
Bill Quantity=5.37 ml
02.07.01
1.00____________________*616.02
=
Net Rate
S= 616.02
Bill Quantity=5.84 ml
02.07.01
1.00____________________*585.45
=
Net Rate
S= 585.45
REJILLAS
LEVEL 4
02.07.02
2.64____________________*70.00
=
Net Rate
184.87
3,327.66
184.87
3,327.66
S= 184.87
ESCALERAS
k500001
LEVEL 4
2.64____________________*450.00
=
Net Rate
1,188.45
4,753.80
1,188.45
4,753.80
1,188.45
1,188.45
1,188.45
1,188.45
1,452.55
1,452.55
1,452.55
1,452.55
S= 1,188.45
k500002
2.64____________________*450.00
=
Net Rate
S= 1,188.45
k500003
2.64____________________*550.00
=
Net Rate
S= 1,452.55
OTROS
19:39
26/02/14
LEVEL 4
61.
AI
MEP2013
a0100001 Topellantas
02.07.04
1) Mano de obra
#
9
L008V
Operario
20.93/hh________________*1.00
5.23
203.97
L012V
Peon
15.71/hh________________*1.00
3.93
153.27
APPLIED FACTOR
9.16
357.24
50.51
1,969.89
50.51
1,969.89
59.67
2,327.25
27.80
3,502.80
44.90
5,657.40
72.70
9,160.20
2) Materiales
M79a0001 Topellantas de concreto, l= 1.80m
50.51/und_______________*1.00
=
Net Rate
L= 8.18
M= 50.75
S= 0.75
1) Mano de obra
M80z3002 Instalacion esquineros caucho e=1/4-1/2
27.80/und_______________*1
2) Material
M80z3001 Esquineros en caucho reflectivo
44.90/und_______________*1
Net Rate
M= 72.70
SELLOS CORTAFUEGO
LEVEL 4
02.08.01
1.00____________________*173129.73
Net Rate
= 173,129.71
173,129.71
173,129.71
173,129.71
S= 173,129.71
19:39
26/02/14
62.
AI
MEP2013
n
LEVEL 3
LEVEL 4
Bill Quantity=3,367.64 m
02.09.01 (VENCEDOR)
Sbpa7001 Pintura
0.95____________________*11.51
=
Net Rate
10.93
36,808.31
10.93
36,823.46
S= 10.93
PINTURA MUROS
LEVEL 4
Bill Quantity=2,043.90 m
Sbpa7001 Pintura
0.95____________________*11.51
=
Net Rate
10.93
22,339.83
10.93
22,349.02
12.03
23,539.34
12.03
23,533.47
12.03
139,015.67
12.03
138,981.01
17.48
39,363.91
17.48
39,363.91
S= 10.93
Bill Quantity=1,956.72 m
Sbpa7001 Pintura
0.95____________________*12.66
=
Net Rate
S= 12.03
Bill Quantity=11,555.75 m
Sbpa7001 Pintura
0.95____________________*12.66
=
Net Rate
S= 12.03
Bill Quantity=2,251.94 m
02.09.02
Sbpa7001 Pintura
0.95____________________*18.40
=
Net Rate
S= 17.48
PINTURA TRAFICO
LEVEL 4
Bill Quantity=153.00 ml
Sbpa7001 Pintura
0.95____________________*9.21
=
Net Rate
8.75
1,338.75
8.75
1,338.67
S= 8.75
19:39
26/02/14
63.
AI
MEP2013
0.95____________________*8.06
=
Net Rate
7.66
275.76
7.66
275.65
7.66
22.98
7.66
22.97
8.75
26.25
8.75
26.25
7.66
490.24
7.66
490.05
7.66
275.76
7.66
275.65
7.66
275.76
7.66
275.65
7.66
3,906.60
7.66
3,905.07
7.66
68.94
7.66
68.91
S= 7.66
0.95____________________*8.06
=
Net Rate
S= 7.66
Bill Quantity=3.00 ml
Sbpa7001 Pintura
0.95____________________*9.21
=
Net Rate
S= 8.75
0.95____________________*8.06
=
Net Rate
S= 7.66
02.09.03
Sbpa7001 Pintura
0.95____________________*8.06
=
Net Rate
S= 7.66
02.09.03
Sbpa7001 Pintura
0.95____________________*8.06
=
Net Rate
S= 7.66
02.09.03
Sbpa7001 Pintura
0.95____________________*8.06
=
Net Rate
S= 7.66
02.09.03
Sbpa7001 Pintura
0.95____________________*8.06
=
Net Rate
S= 7.66
19:39
26/02/14
64.
AI
MEP2013
Bill Quantity=72.00 ml
02.09.03
Sbpa7001 Pintura
0.95____________________*9.21
=
Net Rate
8.75
630.00
8.75
629.96
S= 8.75
LEVEL 3
APARATOS SANITARIOS
LEVEL 4
2) Materiales
M1000301 Inodoro KOHLER Santa Rosa Blanco
718.07/und______________*1
718.07
110,582.78
3.88
597.52
5.45/und________________*1
5.45
839.30
1.31
201.74
15.01
2,311.54
743.72
114,532.88
743.72
114,533.50
15,163.96
15.01/und_______________*1
=
Net Rate
M= 743.72
02.10.01
2) Materiales
M1000302 Inodoro KOHLER Wall-Hung Blanco
1083.14/und_____________*1
1,083.14
468.23/und______________*1
468.23
6,555.22
1,551.37
21,719.18
1,551.37
21,719.12
=
Net Rate
M= 1,551.37
02.10.01
2) Materiales
M1000014 Inodoro TREBOL Taza Atlantic Flux
232.74/und______________*1
232.74
1,396.44
2.13/und________________*1
2.13
12.78
8.86
53.16
243.73
1,462.38
243.73
1,462.37
=
Net Rate
M= 243.73
19:39
26/02/14
65.
AI
MEP2013
2) Materiales
M1015301 Lavatorio KOHLER Verticyl 20x16"
230.83/und______________*1
230.83
38,548.61
24.52
4,094.84
15.01/und_______________*1
15.01
2,506.67
99.50/und_______________*1
99.50
16,616.50
369.86
61,766.62
369.86
61,767.29
=
Net Rate
M= 369.86
2) Materiales
M1015102 Ovalin VAINSA Ocean c/rebose cromado
87.53/und_______________*1
87.53
525.18
9.84
59.04
15.03
90.18
17.08
102.48
129.47
776.82
129.47
776.84
87.53
262.59
87.53
262.58
87.53
262.59
87.53
262.58
=
Net Rate
M= 129.47
02.10.01 Blanco
2) Materiales
M1005301 Urinario KOHLER High Efficiency Blanco
87.53/und_______________*1
=
Net Rate
M= 87.53
02.10.01
2) Materiales
M1005001 Urinario TREBOL Cadet Blanco
87.53/und_______________*1
=
Net Rate
M= 87.53
19:39
26/02/14
66.
AI
MEP2013
02.10.01 K-1835-XH2G
2) Materiales
M1020301 Tina KOHLER Bubble massage WhirlpoolBath 15292.58/und____________*1
15,292.58
251.06
1,255.30
15,543.63
77,718.15
15,543.63
77,718.15
251.06/und______________*1
=
Net Rate
76,462.90
M= 15,543.63
GRIFERIAS
LEVEL 4
2) Materiales
M1052301 Shower head KOHLER Purist
72.61/und_______________*1
72.61
30.70/und_______________*1
30.70
4,574.30
103.31
15,393.19
103.31
15,393.34
=
Net Rate
10,818.89
M= 103.31
2) Materiales
M1052302 Mezcladora ducha KOHLER Singulier + valv 205.49/und______________*1
205.49
30,618.01
169.69
25,283.81
375.17
55,900.33
375.17
55,900.93
334.82
49,888.18
334.82
49,887.88
169.69/und______________*1
=
Net Rate
M= 375.17
=
Net Rate
M= 334.82
885.71
7,085.68
299.19
2,393.52
388.29/und______________*1
=
Net Rate
388.29
3,106.32
1,573.18
12,585.44
1,573.18
12,585.46
M= 1,573.18
19:39
26/02/14
67.
AI
MEP2013
02.10.02
=
Net Rate
185.92
2,602.88
185.92
2,602.91
1,381.20
4,143.60
1,381.20
4,143.61
240.17
720.51
240.17
720.50
240.17
720.51
240.17
720.50
108.51
651.06
108.51
651.08
123.96
991.68
123.96
991.66
M= 185.92
1381.20/und_____________*1
=
Net Rate
M= 1,381.20
02.10.02 TRE-0000HA1503
=
Net Rate
M= 240.17
02.10.02 COD.TRE-A4020C-NEO
240.17/und______________*1
=
Net Rate
M= 240.17
=
Net Rate
M= 108.51
123.96/und______________*1
=
Net Rate
M= 123.96
ACCESORIOS
19:39
26/02/14
LEVEL 4
68.
AI
MEP2013
1) Mano de obra
#
9
L008V
Operario
20.93/hh________________*1
APPLIED FACTOR
10.47
1,528.62
10.47
1,528.62
418.01
61,029.46
428.47
62,556.94
10.47
1,612.38
10.47
1,612.38
177.97
27,407.38
188.43
29,018.71
10.47
1,528.62
10.47
1,528.62
165.06
24,098.76
165.06
24,098.76
175.53
25,626.97
10.47
1,528.62
10.47
1,528.62
165.06
24,098.76
175.53
25,626.97
2) Materiales
M1035001 Barra de toalla doble 24" LOURE
418.01/und______________*1
=
Net Rate
L= 9.44
M= 418.24
S= 0.79
#
1) Mano de obra
9
L008V
Operario
20.93/hh________________*1
APPLIED FACTOR
2) Materiales
M1033201 Porta papel higienico LOURE
177.97/und______________*1
=
Net Rate
L= 9.44
M= 178.20
S= 0.79
#
1) Mano de obra
9
L008V
Operario
20.93/hh________________*1
APPLIED FACTOR
2) Materiales
M1037001 Gancho simple stillness KOHLER
165.06/und______________*!
=
Net Rate
L= 9.44
M= 165.30
S= 0.79
#
1) Mano de obra
9
L008V
Operario
20.93/hh________________*1
APPLIED FACTOR
2) Materiales
M1035002 Barra de toalla 18" LOURE
165.06/und______________*1
=
Net Rate
L= 9.44
19:39
26/02/14
M= 165.30
S= 0.79
69.
AI
MEP2013
#
1) Mano de obra
9
L008V
Operario
20.93/hh________________*1
APPLIED FACTOR
10.47
62.82
10.47
62.82
25.65
153.90
25.65
153.90
36.12
216.70
10.47
20.94
10.47
20.94
738.59
1,477.18
738.59
1,477.18
749.06
1,498.12
2) Materiales
M1030007 Dispens. jabon adosado 500ml KIMB CLARK
25.65/und_______________*1
=
Net Rate
L= 9.44
M= 25.89
S= 0.79
#
1) Mano de obra
9
L008V
Operario
20.93/hh________________*1
APPLIED FACTOR
2) Materiales
M1030301 Secador manos c/sensor WORLD DRYER DXA54 738.59/und______________*1
=
Net Rate
L= 9.44
19:39
26/02/14
M= 738.83
S= 0.79
70.
AI
MEP2013
02.10.03 2"
#
1) Mano de obra
9
L008V
Operario
20.93/hh________________*1
APPLIED FACTOR
20.93
104.65
20.93
104.65
850.55
2) Materiales
M1030507 Barra A.Inox. c/bisagras
170.11/und______________*1
170.11
80.99/und_______________*1
80.99
404.95
251.10
1,255.50
272.03
1,360.17
10.47
83.76
10.47
83.76
6.12
48.96
=
Net Rate
L= 18.88
M= 251.57
S= 1.58
02.10.03
#
1) Mano de obra
9
L008V
Operario
20.93/hh________________*1
APPLIED FACTOR
2) Materiales
M1031000 Jabonera TREBOL Losa vitrificada Blanco
6.12/und________________*1
=
Net Rate
L= 9.44
M= 6.36
6.12
48.96
16.59
132.70
10.47
20.94
10.47
20.94
41.41
82.82
S= 0.79
KIMBERLY-CLARK
#
1) Mano de obra
9
L008V
Operario
20.93/hh________________*1
APPLIED FACTOR
2) Materiales
M1030212 Disp. papel hig. KIMB. CLARK JRT Windows 41.41/und_______________*1
=
Net Rate
L= 9.44
M= 41.64
41.41
82.82
51.88
103.75
S= 0.79
DIVISIONES DE BAO
LEVEL 4
Bill Quantity=259.89 m
2.78____________________*147.00
=
Net Rate
408.66
106,206.65
408.66
106,206.65
S= 408.66
19:39
26/02/14
71.
AI
MEP2013
2.78____________________*582.84
=
Net Rate
1,620.30
11,342.10
1,620.30
11,342.07
523.45
1,570.35
523.45
1,570.34
1,620.30
8,101.50
1,620.30
8,101.48
S= 1,620.30
02.10.04
2.78____________________*188.29
=
Net Rate
S= 523.45
02.10.04
2.78____________________*582.84
=
Net Rate
S= 1,620.30
MOBILIARIO FIJO
LEVEL 3
02.11.02
1.00____________________*349.95
=
Net Rate
349.95
34,645.05
349.95
34,645.05
578.82
28,941.00
578.82
28,941.00
857.93
169,870.14
857.93
169,870.14
857.93
42,896.50
857.93
42,896.50
S= 349.95
02.11.03
1.00____________________*578.82
=
Net Rate
S= 578.82
02.11.04
1.00____________________*857.93
=
Net Rate
S= 857.93
02.11.05
1.00____________________*857.93
=
Net Rate
S= 857.93
19:39
26/02/14
72.
AI
MEP2013
02.11.06
1.00____________________*957.25
=
Net Rate
957.25
142,630.25
957.25
142,630.25
957.25
142,630.25
957.25
142,630.25
1,443.48
215,078.52
1,443.48
215,078.52
2,461.50
366,763.50
2,461.50
366,763.50
1,792.95
267,149.55
1,792.95
267,149.55
343.67
51,206.83
343.67
51,206.83
2,681.87
399,598.63
2,681.87
399,598.63
5,754.73
28,773.65
5,754.73
28,773.65
S= 957.25
02.11.07 Doble)
1.00____________________*957.25
=
Net Rate
S= 957.25
02.11.08
1.00____________________*1443.48
=
Net Rate
S= 1,443.48
1.00____________________*2461.50
=
Net Rate
S= 2,461.50
1.00____________________*1792.95
=
Net Rate
S= 1,792.95
1.00____________________*343.67
=
Net Rate
S= 343.67
1.00____________________*2681.87
=
Net Rate
S= 2,681.87
1.00____________________*5754.73
=
Net Rate
S= 5,754.73
19:39
26/02/14
73.
AI
MEP2013
02.11.15
1.00____________________*4976.69
=
Net Rate
4,976.69
4,976.69
4,976.69
4,976.69
28,613.41
28,613.41
28,613.41
28,613.41
12,314.59
12,314.59
12,314.59
12,314.59
1,368.29
2,736.58
1,368.29
2,736.58
38,743.07
38,743.07
38,743.07
38,743.07
36,516.87
109,550.61
36,516.87
109,550.61
9,121.92
9,121.92
9,121.92
9,121.92
S= 4,976.69
1.00____________________*28613.41
=
Net Rate
S= 28,613.41
1.00____________________*12314.59
=
Net Rate
S= 12,314.59
1.00____________________*1368.29
=
Net Rate
S= 1,368.29
02.11.20
1.00____________________*38743.07
=
Net Rate
S= 38,743.07
1.00____________________*36516.87
=
Net Rate
S= 36,516.87
1.00____________________*9121.92
=
Net Rate
S= 9,121.92
19:39
26/02/14
LEVEL 3
74.
AI
MEP2013
Bill Quantity=25.54 m
02.12.01
2.78____________________*110.00
=
Net Rate
305.80
7,810.13
305.80
7,810.13
305.80
18,289.90
305.80
18,289.90
305.80
13,378.75
305.80
13,378.75
21,088.60
S= 305.80
Bill Quantity=59.81 m
02.12.02
2.78____________________*110.00
=
Net Rate
S= 305.80
Bill Quantity=43.75 m
02.12.04
2.78____________________*110.00
=
Net Rate
S= 305.80
Bill Quantity=326.55 m
1) Suministro
Sba90001 Sum, Vinil p/pared VESCOM Albert
58.71/m2________________*1 +10%waste
64.58
17.80/m2________________*1
17.80
5,812.59
82.38
26,901.19
82.38
26,902.22
2) Instalacion
Sba90000 Inst. Standard de revestimiento vinil
=
Net Rate
S= 82.38
Bill Quantity=616.50 m
1) Suministro
Sba90001 Sum, Vinil p/pared VESCOM Albert
58.71/m2________________*1 +10%waste
64.58
39,813.57
17.80/m2________________*1
17.80
10,973.70
82.38
50,787.27
82.38
50,789.22
2) Instalacion
Sba90000 Inst. Standard de revestimiento vinil
=
Net Rate
S= 82.38
19:39
26/02/14
75.
AI
MEP2013
Bill Quantity=50.25 m
1) Suministro
Sba90002 Sum, Vinil p/pared VESCOM Tessera
65.07/m2________________*1 +10%waste
71.58
3,596.90
17.80/m2________________*1
17.80
894.45
89.38
4,491.35
89.38
4,491.18
2) Instalacion
Sba90000 Inst. Standard de revestimiento vinil
=
Net Rate
S= 89.38
OTROS
LEVEL 3
02.13.01
#
1) Mano de obra
9
L008V
Operario
20.93/hh________________*1
APPLIED FACTOR
10.47
1,612.38
10.47
1,612.38
45.00
6,930.00
55.47
8,541.95
504.00
5,544.00
504.00
5,544.00
2) Materiales
M80z1001 Numeros en acrilico
15.00/und_______________*3.00
=
Net Rate
L= 9.44
M= 45.23
S= 0.79
02.13.02
504.00/jgo______________*1
=
Net Rate
S= 504.00
ESPEJOS
LEVEL 3
Sbcc9001 Espejos
0.98____________________*129.70
=
Net Rate
127.11
762.66
127.11
762.64
127.11
18,558.06
127.11
18,557.48
S= 127.11
02.15.02 en habitaciones
Sbcc9001 Espejos
0.98____________________*129.70
=
Net Rate
S= 127.11
19:39
26/02/14
76.
AI
MEP2013
Sbcc9001 Espejos
0.98____________________*163.22
=
Net Rate
159.96
799.80
159.96
799.78
578.03
2,890.15
578.03
2,890.17
1,314.70
1,314.70
1,314.70
1,314.70
99.66
3,511.02
99.66
3,510.89
S= 159.96
02.15.04
Sbcc9001 Espejos
0.98____________________*589.83
=
Net Rate
S= 578.03
02.15.05
Sbcc9001 Espejos
0.98____________________*1341.53
=
Net Rate
S= 1,314.70
Bill Quantity=35.23 m2
02.15.06
Sbcc9001 Espejos
0.98____________________*101.69
=
Net Rate
S= 99.66
VIDRIOS Y CRISTALES
n
LEVEL 3
MURO CORTINA
LEVEL 4
Bill Quantity=273.60 m2
1.00____________________*935.26
=
Net Rate
935.26
255,887.14
935.26
255,887.14
1,649.15
167,718.56
1,649.15
167,718.56
S= 935.26
02.16.01
1649.15/ml______________*1
=
Net Rate
S= 1,649.15
VENTANAS-MAMPARAS
LEVEL 4
c2000001 V-01(1.60x1.60)
Bill Quantity=276.48 m
02.16.02
1.00____________________*576.04
=
Net Rate
576.04
159,263.54
576.04
159,263.54
S= 576.04
19:39
26/02/14
77.
AI
MEP2013
Bill Quantity=69.60 m
02.16.02
1.00____________________*559.13
=
Net Rate
559.13
38,915.45
559.13
38,915.45
545.33
45,862.25
545.33
45,862.25
748.49
5,321.76
748.49
5,321.76
270.87
541.74
270.87
541.74
536.65
6,616.89
536.65
6,616.89
608.37
5,292.82
608.37
5,292.82
564.80
3,931.01
564.80
3,931.01
276.13
5,025.57
276.13
5,025.57
S= 559.13
c2000004 V-05(29.0x2.90)
Bill Quantity=84.10 m
02.16.02
1.00____________________*545.33
=
Net Rate
S= 545.33
c2000005 V-06(2.45x2.90)
Bill Quantity=7.11 m
02.16.02
1.00____________________*748.49
=
Net Rate
S= 748.49
c2000006 V-07(1.38x1.45)
Bill Quantity=2.00 m
02.16.02
1.00____________________*270.87
=
Net Rate
S= 270.87
c2000007 V-08(4.25x2.90)
Bill Quantity=12.33 m
02.16.02
1.00____________________*536.65
=
Net Rate
S= 536.65
c2000008 V-09(1.50x2.90)
Bill Quantity=8.70 m
02.16.02
1.00____________________*608.37
=
Net Rate
S= 608.37
c2000009 V-10(2.40x2.90)
Bill Quantity=6.96 m
02.16.02
1.00____________________*564.80
=
Net Rate
S= 564.80
Bill Quantity=18.20 m
02.16.02
1.00____________________*276.13
=
Net Rate
S= 276.13
19:39
26/02/14
78.
AI
MEP2013
Bill Quantity=19.98 m
02.16.02
1.00____________________*549.42
=
Net Rate
549.42
10,977.41
549.42
10,977.41
716.59
4,887.14
716.59
4,887.14
540.96
2,353.18
540.96
2,353.18
283.89
701.21
283.89
701.21
586.33
71,239.10
586.33
71,239.10
S= 549.42
Bill Quantity=6.82 m
02.16.02
1.00____________________*716.59
=
Net Rate
S= 716.59
Bill Quantity=4.35 m
02.16.02
1.00____________________*540.96
=
Net Rate
S= 540.96
Bill Quantity=2.47 m
02.16.02
1.00____________________*283.89
=
Net Rate
S= 283.89
Bill Quantity=121.50 m
02.16.02
1.00____________________*586.33
=
Net Rate
S= 586.33
REVESTIMIENTO
LEVEL 4
Bill Quantity=1.00 m
02.16.03
16680.00/m2_____________*1
=
Net Rate
16,680.00
16,680.00
16,680.00
16,680.00
S= 16,680.00
COBERTURAS
LEVEL 3
Bill Quantity=17.31 m
1.00____________________*360.80
=
Net Rate
360.80
6,245.45
360.80
6,245.45
S= 360.80
SEGURIDAD
n
19:39
LEVEL 3
SEALETICA De 20x30
26/02/14
LEVEL 4
79.
AI
MEP2013
iluminado de 40
lmenes
Z001
Sealizacion
1.00/vg_________________*354.54
=
Net Rate
354.54
7,090.80
354.54
7,090.80
354.54
10,281.66
354.54
10,281.66
354.54
17,372.46
354.54
17,372.46
354.54
1,772.70
354.54
1,772.70
354.54
2,836.32
354.54
2,836.32
354.54
1,772.70
354.54
1,772.70
95.00
2,850.00
95.00
2,850.00
95.00
665.00
95.00
665.00
S= 354.54
Sealizacion
1.00/vg_________________*354.54
=
Net Rate
S= 354.54
Sealizacion
1.00/vg_________________*354.54
=
Net Rate
S= 354.54
Sealizacion
1.00/vg_________________*354.54
=
Net Rate
S= 354.54
Sealizacion
1.00/vg_________________*354.54
=
Net Rate
S= 354.54
Sealizacion
1.00/vg_________________*354.54
=
Net Rate
S= 354.54
Z001
Sealizacion
1.00/vg_________________*95.00
=
Net Rate
S= 95.00
02.19.01
Z001
Sealizacion
1.00/vg_________________*95.00
=
Net Rate
S= 95.00
19:39
26/02/14
80.
AI
MEP2013
Z001
Sealizacion
1.00/vg_________________*95.00
=
Net Rate
95.00
3,515.00
95.00
3,515.00
95.00
3,325.00
95.00
3,325.00
289.99
7,249.75
289.99
7,249.75
S= 95.00
02.19.01
Z001
Sealizacion
1.00/vg_________________*95.00
=
Net Rate
S= 95.00
Bill Quantity=25.00 un
Z001
Sealizacion
1.00/vg_________________*289.99
=
Net Rate
S= 289.99
19:39
26/02/14
81.
AI
MEP2013
Sealizacion
1.00/vg_________________*342.55
=
Net Rate
342.55
90,090.65
342.55
90,090.64
95.00
950.00
95.00
950.00
95.00
2,090.00
95.00
2,090.00
95.00
190.00
95.00
190.00
95.00
2,565.00
95.00
2,565.00
S= 342.55
02.19.01 de 10 Kg
Z001
Sealizacion
1.00/vg_________________*95.00
=
Net Rate
S= 95.00
02.19.01
Z001
Sealizacion
1.00/vg_________________*95.00
=
Net Rate
S= 95.00
02.19.01
Z001
Sealizacion
1.00/vg_________________*95.00
=
Net Rate
S= 95.00
Sealizacion
1.00/vg_________________*95.00
=
Net Rate
S= 95.00
OTROS
n
LEVEL 3
h00458
LEVEL 4
02.20.01
Z002
30000.00/un
=
Net Rate
30,000.00
30,000.00
30,000.00
30,000.00
35,000.00
35,000.00
35,000.00
35,000.00
S= 30,000.00
h00461
02.20.01
Z003
35000.00/un
=
Net Rate
S= 35,000.00
19:39
26/02/14
82.
AI
MEP2013
h00464
02.20.01
Z004
179999.98/un
= 179,999.98
179,999.98
179,999.98
179,999.98
Net Rate
S= 179,999.98
LEVEL 4
Spare Parts
LEVEL 5
582.30/und______________*1
=
Net Rate
582.30
1,746.90
582.30
1,746.90
M= 582.30
LEVEL 5
( 2 % del Total -
02.20.02 mnimo de 2 )
109.51/und______________*1
=
Net Rate
109.51
328.53
109.51
328.54
M= 109.51
PARTIDAS COMPLEMENTARIAS
n
LEVEL 3
TARRAJEOS
a037003
LEVEL 4
Bill Quantity=228.15 m2
1) Mano de obra
#
9
L008V
Operario
20.93/hh________________*1.00
16.75
L012V
Peon
15.71/hh________________*0.33
4.15
3,821.51
946.82
APPLIED FACTOR
20.90
4,768.34
2) Materiales
#
M2100001 Cemento Portland Tipo I bls 42.5 Kg
14.93/bls_______________*0.1280 +5%waste
2.01
458.58
35.00/m3________________*0.0173 +5%waste
0.64
146.02
6.00/m3_________________*0.0040 +5%waste
0.03
6.84
4.30/p2_________________*1.0800
4.64
1,058.62
4.50/p2_________________*0.0350
0.16
36.50
3.48/kg_________________*0.0040
0.01
2.28
________________________/ 1
7.48
1,706.56
28.38
6,474.09
APPLIED FACTOR
Net Rate
L= 18.76
19:39
26/02/14
M= 7.98
S= 1.64
83.
AI
MEP2013
a031002
Bill Quantity=41.83 m2
#
1) Mano de obra
9
L008V
Operario
20.93/hh________________*1.00
18.61
778.46
L012V
Peon
15.71/hh________________*0.33
4.61
192.84
APPLIED FACTOR
23.22
971.29
2) Materiales
#
M2100001 Cemento Portland Tipo I bls 42.5 Kg
14.93/bls_______________*0.1490 +6%waste
2.36
98.72
35.00/m3________________*0.0288 +6%waste
1.07
44.76
6.00/m3_________________*0.0080 +6%waste
0.05
2.09
4.50/p2_________________*2.33/(0.40*15)
1.75
73.20
________________________/ 1
APPLIED FACTOR
Net Rate
L= 20.84
a033001
M= 5.78
5.22
218.35
28.44
1,189.77
8,378.78
S= 1.82
Bill Quantity=450.23 m2
02.21.01 - Columnas
1) Mano de obra
#
9
L008V
Operario
20.93/hh________________*1.00
18.61
L012V
Peon
15.71/hh________________*0.33
4.61
2,075.56
APPLIED FACTOR
23.22
10,454.34
2) Materiales
#
M2100001 Cemento Portland Tipo I bls 42.5 Kg
14.93/bls_______________*0.1280 +5%waste
2.01
904.96
35.00/m3________________*0.0173 +5%waste
0.64
288.15
6.00/m3_________________*0.0060 +5%waste
0.04
18.01
4.30/p2_________________*62.20/(7.20*17)
2.18
981.50
4.50/p2_________________*0.0350
0.16
72.04
3.48/kg_________________*0.0220
0.08
36.02
________________________/ 1
5.10
2,296.17
28.32
12,748.74
APPLIED FACTOR
Net Rate
L= 20.84
M= 5.65
S= 1.82
PINTURA
LEVEL 4
Bill Quantity=41.83 m2
02.21.02 (Vencelatex)
Sbpa7001 Pintura
0.95____________________*11.51
=
Net Rate
10.93
457.20
10.93
457.39
10.93
22,339.83
10.93
22,349.02
S= 10.93
Bill Quantity=2,043.90 m2
02.21.02 (Vencelatex)
Sbpa7001 Pintura
0.95____________________*11.51
=
Net Rate
S= 10.93
19:39
26/02/14
84.
AI
MEP2013
Bill Quantity=3,900.44 m2
Sbpa7001 Pintura
0.95____________________*11.51
=
Net Rate
10.93
42,631.81
10.93
42,649.36
S= 10.93
VIDRIOS Y CRISTALES
LEVEL 4
c1000005 FV05
02.21.03
1.00____________________*282.88
=
Net Rate
282.88
1,357.82
282.88
1,357.82
285.26
1,178.12
285.26
1,178.12
291.69
1,064.67
291.69
1,064.67
283.28
9,968.62
283.28
9,968.62
S= 282.88
c1000006 FV06
02.21.03
1.00____________________*285.26
=
Net Rate
S= 285.26
c1000007 FV07
Bill Quantity=3.65 m2
02.21.03
1.00____________________*291.69
=
Net Rate
S= 291.69
c1000008 FV08
Bill Quantity=35.19 m2
02.21.03
1.00____________________*283.28
=
Net Rate
S= 283.28
CARPINTERIA DE MADERA
LEVEL 4
02.21.01 Doble)
1.00____________________*413.83
=
Net Rate
413.83
61,660.67
413.83
61,660.67
348.05
1,740.25
348.05
1,740.25
S= 413.83
02.21.01 (Suites)
1.00____________________*348.05
=
Net Rate
S= 348.05
19:39
26/02/14
85.
AI
MEP2013
02.21.01
1.00____________________*1791.45
=
Net Rate
1,791.45
8,957.25
1,791.45
8,957.25
2,142.51
10,712.55
2,142.51
10,712.55
1,109.45
11,094.50
1,109.45
11,094.50
386.24
1,931.20
386.24
1,931.20
561.71
2,808.55
561.71
2,808.55
40,820.59
40,820.59
40,820.59
40,820.59
S= 1,791.45
1.00____________________*2142.51
=
Net Rate
S= 2,142.51
02.21.01
1.00____________________*1109.45
=
Net Rate
S= 1,109.45
02.21.01 (Suites)
1.00____________________*386.24
=
Net Rate
S= 386.24
02.21.01 (Suites)
1.00____________________*561.71
=
Net Rate
S= 561.71
02.21.01
1.00____________________*40820.59
=
Net Rate
S= 40,820.59
02.21.01
822.25/und______________*2
1,644.50
1,644.50
822.25/und______________*1
822.25
822.25
105.65/und______________*1
105.65
105.65
2,572.41
2,572.41
1,800.00
1,800.00
4,372.41
4,372.41
=
Sbmn2001 Carp. Madera - Puertas
1.00____________________*1800.00
=
Net Rate
M= 2,572.41
19:39
26/02/14
S= 1,800.00
86.
AI
MEP2013
02.21.01
1.00____________________*670.00
670.00
1,340.00
105.65
211.30
22.39/und_______________*3
67.17
134.34
847.69/m2_______________*0.90*0.20
152.59
305.18
995.40
1,990.80
995.40
1,990.80
=
Net Rate
M= 172.82
S= 822.58
02.21.11 Puerta P2
1.00____________________*660.00
660.00
82,500.00
601.50/und______________*1
601.50
75,187.50
60.00/und_______________*1
60.00
7,500.00
1,321.50
165,187.50
1,321.50
165,187.48
660.00
1,980.00
201.51
=
Net Rate
M= 661.50
S= 660.00
02.21.12 Puerta P3
1.00____________________*660.00
22.39/und_______________*3
67.17
105.65
316.95
832.82
2,498.46
832.82
2,498.45
660.00
13,860.00
1,410.57
=
Net Rate
M= 172.82
S= 660.00
02.21.13 Puerta P4
1.00____________________*660.00
22.39/und_______________*3
67.17
105.65
2,218.65
832.82
17,489.22
832.82
17,489.15
=
Net Rate
M= 172.82
S= 660.00
REVESTIMIENTOS
LEVEL 4
Sbg9989
Granito, Marmol,cuarzo
1.00____________________*909.39
=
Net Rate
909.39
284,820.95
909.39
284,820.95
S= 909.39
19:39
26/02/14
87.
AI
MEP2013
Sbg9989
Granito, Marmol,cuarzo
1.00____________________*912.35
=
Net Rate
912.35
37,771.29
912.35
37,771.29
912.63
35,044.99
912.63
35,044.99
1,012.39
8,099.12
1,012.39
8,099.12
2,427.59
12,137.95
2,427.59
12,137.95
6,394.00
6,394.00
6,394.00
6,394.00
13,132.32
13,132.32
13,132.32
13,132.32
912.63
4,563.15
912.63
4,563.15
S= 912.35
Sbg9989
Granito, Marmol,cuarzo
1.00____________________*912.63
=
Net Rate
S= 912.63
Sbg9989
Granito, Marmol,cuarzo
1.00____________________*1012.39
=
Net Rate
S= 1,012.39
Sbg9989
Granito, Marmol,cuarzo
1.00____________________*2427.59
=
Net Rate
S= 2,427.59
6394.00/glb_____________*1
=
Net Rate
S= 6,394.00
02.21.08
13132.32/glb____________*1
=
Net Rate
S= 13,132.32
Bill Quantity=5.00 ml
02.21.09
Sbg9989
Granito, Marmol,cuarzo
1.00____________________*912.63
=
Net Rate
S= 912.63
19:39
26/02/14
88.
AI
MEP2013
Bill Quantity=3.00 ml
02.21.10
Sbg9989
Granito, Marmol,cuarzo
1.00____________________*1012.39
=
Net Rate
1,012.39
3,037.17
1,012.39
3,037.17
S= 1,012.39
LEVEL 4
Bill Quantity=77.00 m
02.21.01 -1)
0.95SA__________________*95.77
=
Net Rate
90.98
7,005.46
90.98
7,005.58
90.98
8,188.20
90.98
8,188.34
68.18
5,931.66
68.18
5,931.79
68.18
14,051.90
68.18
14,052.21
22.16
2,775.32
22.16
2,775.76
4,524.82
4,524.82
4,524.82
4,524.82
S= 90.98
Bill Quantity=90.00 m
02.21.01 -1)
0.95SA__________________*95.77
=
Net Rate
S= 90.98
Bill Quantity=87.00 m
02.21.01
0.95SA__________________*71.77
=
Net Rate
S= 68.18
Bill Quantity=206.10 m
02.21.01
0.95SA__________________*71.77
=
Net Rate
S= 68.18
Bill Quantity=125.24 m2
02.21.01 paredes
0.95SA__________________*23.33
=
Net Rate
S= 22.16
02.21.01
0.95SA__________________*4762.97
=
Net Rate
S= 4,524.82
19:39
26/02/14
LEVEL 4
89.
AI
MEP2013
Bill Quantity=179.68 m
0.95SA__________________*120.67
=
Net Rate
114.64
20,598.52
114.64
20,597.89
22.16
103.04
22.16
103.06
25.34
430.78
25.34
430.72
S= 114.64
Bill Quantity=4.65 m2
02.21.01
0.95SA__________________*23.33
=
Net Rate
S= 22.16
02.21.01 (1.00x1.00m)
0.95SA__________________*26.67
=
Net Rate
S= 25.34
CARPINTERIA METALICA
LEVEL 4
2.64____________________*800.00
=
Net Rate
2,112.80
4,225.60
2,112.80
4,225.60
5,225.01
5,225.01
5,225.01
5,225.01
5,510.00
5,510.00
5,510.00
5,510.00
2,517.50
5,035.00
179.10
S= 2,112.80
02.21.03 (3.65x5.44m)
2.64____________________*1978.42
=
Net Rate
S= 5,225.01
02.21.04 (5.77x5.44m)
2.64____________________*2086.33
=
Net Rate
S= 5,510.00
02.21.04
0.95____________________*2650.00
22.39/und_______________*4
89.55
105.65
211.30
2,712.71
5,425.42
2,712.71
5,425.41
M80b123
=
Net Rate
M= 195.21
19:39
26/02/14
S= 2,517.50
90.
AI
MEP2013
02.21.05
2.64____________________*450.00
1,188.45
1,188.45
158.46/und______________*1
158.46
158.46
198.08/und______________*1
198.08
198.08
21.13/und_______________*3
63.38
63.38
39.62
39.62
73.95/und_______________*1
73.95
73.95
110.92/und______________*1
110.92
110.92
Sbk01007 Cerradura
132.05/und______________*1
132.05
132.05
422.56/und______________*1
422.56
422.56
2,387.46
2,387.46
2,387.46
2,387.46
=
Net Rate
S= 2,387.46
02.21.06
0.95____________________*4400.00
4,180.00
8,360.00
22.39/und_______________*8
179.11
358.22
M80b126
105.65/und______________*1
105.65
211.30
M80b127
Pestillo
50.00/und_______________*1
50.00
100.00
4,514.76
9,029.52
4,514.76
9,029.52
=
Net Rate
M= 334.76
S= 4,180.00
02.21.07
0.95____________________*4400.00
4,180.00
4,180.00
22.39/und_______________*8
179.11
179.11
M80b126
105.65/und______________*1
105.65
105.65
M80b127
Pestillo
50.00/und_______________*1
50.00
50.00
4,514.76
4,514.76
4,514.76
4,514.76
2,185.00
6,555.00
268.65
=
Net Rate
M= 334.76
S= 4,180.00
02.21.08
0.95____________________*2300.00
22.39/und_______________*4
89.55
105.65
316.95
2,380.21
7,140.63
2,380.21
7,140.62
M80b123
=
Net Rate
M= 195.21
19:39
26/02/14
S= 2,185.00
91.
AI
MEP2013
02.21.09
0.95____________________*2350.00
22.39/und_______________*4
89.55
89.55
M80b126
105.65/und______________*1
105.65
105.65
333.60/m2_______________*0.75*0.30
Net Rate
M= 270.27
2,232.50
2,232.50
75.06
75.06
2,502.77
2,502.77
2,502.77
2,502.77
S= 2,232.50
02.21.10
2.64____________________*600.00
1,584.60
3,169.20
158.46/und______________*1
158.46
316.92
198.08/und______________*1
198.08
396.16
21.13/und_______________*3
63.38
126.76
73.95/und_______________*1
73.95
147.90
110.92/und______________*1
110.92
221.84
Sbk01007 Cerradura
132.05/und______________*1
132.05
264.10
2,321.44
4,642.88
2,321.44
4,642.88
=
Net Rate
S= 2,321.44
02.21.11
2.64____________________*600.00
1,584.60
4,753.80
158.46/und______________*1
158.46
475.38
198.08/und______________*1
198.08
594.24
21.13/und_______________*3
63.38
190.14
73.95/und_______________*1
73.95
221.85
110.92/und______________*1
110.92
332.76
Sbk01007 Cerradura
132.05/und______________*1
132.05
396.15
422.56/und______________*1
422.56
1,267.68
2,744.00
8,232.00
2,744.00
8,232.00
2,327.50
4,655.00
=
Net Rate
S= 2,744.00
02.21.12
0.95____________________*2450.00
77.84/und_______________*1
77.84
155.68
M80b128
278.00/und______________*1
278.00
556.00
22.39/und_______________*4
89.55
179.10
2,772.89
5,545.78
2,772.89
5,545.79
Barra antipanico
Net Rate
M= 445.39
19:39
26/02/14
S= 2,327.50
92.
AI
MEP2013
02.21.13
2.64____________________*550.00
1,452.55
1,452.55
158.46/und______________*1
158.46
158.46
198.08/und______________*1
198.08
198.08
21.13/und_______________*3
63.38
63.38
73.95/und_______________*1
73.95
73.95
110.92/und______________*1
110.92
110.92
Sbk01007 Cerradura
132.05/und______________*1
=
Net Rate
132.05
132.05
2,189.39
2,189.39
2,189.39
2,189.39
S= 2,189.39
02.21.14
2.64____________________*500.00
1,320.50
3,961.50
158.46/und______________*1
158.46
475.38
198.08/und______________*1
198.08
594.24
21.13/und_______________*3
63.38
190.14
39.62
118.86
73.95/und_______________*1
73.95
221.85
110.92/und______________*1
110.92
332.76
Sbk01007 Cerradura
132.05/und______________*1
132.05
396.15
422.56/und______________*2
845.12
2,535.36
2,942.07
8,826.21
2,942.07
8,826.22
=
Net Rate
S= 2,942.07
02.21.15
2.64____________________*500.00
1,320.50
5,282.00
158.46/und______________*1
158.46
633.84
198.08/und______________*1
198.08
792.32
21.13/und_______________*3
63.38
253.52
73.95/und_______________*1
73.95
295.80
110.92/und______________*1
110.92
443.68
Sbk01007 Cerradura
132.05/und______________*1
132.05
528.20
2,057.34
8,229.36
2,057.34
8,229.36
=
Net Rate
S= 2,057.34
19:39
26/02/14
93.
AI
MEP2013
02.21.16
2.64____________________*560.00
1,478.96
1,478.96
158.46/und______________*1
158.46
158.46
198.08/und______________*1
198.08
198.08
21.13/und_______________*3
63.38
63.38
73.95/und_______________*1
73.95
73.95
110.92/und______________*1
110.92
110.92
Sbk01007 Cerradura
132.05/und______________*1
132.05
132.05
422.56/und______________*1
422.56
422.56
2,638.36
2,638.36
2,638.36
2,638.36
=
Net Rate
S= 2,638.36
02.21.17
2.64____________________*510.00
1,346.91
1,346.91
158.46/und______________*1
158.46
158.46
198.08/und______________*1
198.08
198.08
21.13/und_______________*3
63.38
63.38
73.95/und_______________*1
73.95
73.95
110.92/und______________*1
110.92
110.92
Sbk01007 Cerradura
132.05/und______________*1
=
Net Rate
132.05
132.05
2,083.75
2,083.75
2,083.75
2,083.75
6,650.00
13,300.00
S= 2,083.75
02.21.18
0.95____________________*7000.00
22.39/und_______________*8
179.11
358.22
1,129.88
2,259.76
333.60/m2_______________*0.54*0.30*2
=
Net Rate
M= 1,417.07
108.09
216.18
8,067.07
16,134.14
8,067.07
16,134.14
2,517.50
2,517.50
S= 6,650.00
02.21.19
0.95____________________*2650.00
22.39/und_______________*4
89.55
89.55
M80b126
105.65/und______________*1
105.65
105.65
333.60/m2_______________*0.605*0.30
Net Rate
M= 255.75
19:39
26/02/14
60.55
60.55
2,773.25
2,773.25
2,773.25
2,773.25
S= 2,517.50
94.
AI
MEP2013
02.21.20
0.95____________________*2300.00
22.39/und_______________*4
M80b126
105.65/und______________*1
2,185.00
4,370.00
89.55
179.10
105.65
211.30
2,380.21
4,760.42
2,380.21
4,760.41
=
Net Rate
M= 195.21
S= 2,185.00
02.21.21
2.64____________________*600.00
1,584.60
3,169.20
158.46/und______________*1
158.46
316.92
198.08/und______________*1
198.08
396.16
21.13/und_______________*3
63.38
126.76
110.92/und______________*1
110.92
221.84
Sbk01007 Cerradura
132.05/und______________*1
132.05
264.10
1390.00/und_____________*1
1,390.00
2,780.00
3,637.49
7,274.98
3,637.49
7,274.98
=
Net Rate
S= 3,637.49
PISOS
19:39
26/02/14
LEVEL 4
95.
AI
MEP2013
Bill Quantity=130.00 m2
L008V
Operario
20.93/hh________________*3.00
9.13
L011V
Oficial
17.31/hh________________*1.00
2.52
1,186.90
327.60
L012V
Peon
15.71/hh________________*6.00
13.71
1,782.30
26.65/hm________________*1.00
2) Equipos
8
APPLIED FACTOR
3.88
504.40
29.24
3,801.20
3) Materiales
#
M2100001 Cemento Portland Tipo I bls 42.5 Kg
14.93/bls_______________*0.5190 +5%waste
8.14
1,058.20
35.00/m3________________*0.0890 +5%waste
3.27
425.10
6.00/m3_________________*0.5190 +5%waste
3.27
425.10
4.50/p2_________________*0.0910
0.41
53.30
________________________/ 1
15.09
1,961.70
7.28
946.40
7.28
946.40
0.35
45.50
APPLIED FACTOR
L008V
Operario
20.93/hh________________*1.00
APPLIED FACTOR
2) Materiales
#
M2100001 Cemento Portland Tipo I bls 42.5 Kg
14.93/bls_______________/42.50
________________________/ 1
APPLIED FACTOR
=
Net Rate
D= 1.69
19:39
26/02/14
L= 29.11
M= 16.28
S= 2.69
0.35
45.50
51.96
6,755.09
E= 2.18
96.
AI
MEP2013
Bill Quantity=472.29 m2
L008V
Operario
20.93/hh________________*3.00
8.37
3,953.07
L011V
Oficial
17.31/hh________________*1.00
2.31
1,090.99
L012V
Peon
15.71/hh________________*6.00
12.57
5,936.69
26.65/hm________________*1.00
2) Equipos
8
APPLIED FACTOR
3.55
1,676.63
26.81
12,662.09
3) Materiales
#
M2100001 Cemento Portland Tipo I bls 42.5 Kg
14.93/bls_______________*0.5140 +5%waste
8.06
3,806.66
35.00/m3________________*0.0890 +5%waste
3.27
1,544.39
6.00/m3_________________*0.5140 +5%waste
3.24
1,530.22
4.50/p2_________________*0.0750
0.34
160.58
________________________/ 1
14.90
7,037.12
APPLIED FACTOR
ACABADO PULIDO
==============
1) Acabado con alisadora
#
9
L008V
20.93/hh________________*1.00
1.40
661.21
Operario
42.22/hm________________*1.00
2.81
1,327.13
4.21
1,988.34
0.35
165.30
0.35
165.30
5.77
2,725.11
5.77
2,725.11
10,787.10
APPLIED FACTOR
2) Materiales
M2100001 Cemento Portland Tipo I bls 42.5 Kg
14.93/bls_______________/42.50
=
PINTURA EPOXICA (JET POX 2000)
==============================
1) Mano de obra
#
9
L011V
Oficial
17.31/hh________________*1.00
APPLIED FACTOR
2) Materiales
#
M5460002 Epoxico Jet Pox 2000 CPPQ(1gln-R+1gln-C) 248.81/kit______________*0.0918
22.84
45.04/gln_______________*0.0285
1.28
604.53
________________________/ 1
24.12
11,391.63
76.17
35,972.15
APPLIED FACTOR
Net Rate
D= 2.33
19:39
26/02/14
L= 27.05
M= 40.19
S= 2.56
E= 4.04
97.
AI
MEP2013
Bill Quantity=33.90 m2
1) Mano de obra
#
9
L008V
Operario
20.93/hh________________*1.00
15.22
515.96
L012V
Peon
15.71/hh________________*0.33
3.77
127.80
APPLIED FACTOR
19.00
644.10
2) Materiales
#
M80c1010 Porc. CELIMA Mate Beige Esmaltado 60x60
27.47/m2________________*1.00 +5%waste
28.84
977.68
24.64/bls_______________*0.25 +5%waste
6.47
219.33
3.38/kg_________________*0.35 +5%waste
1.24
42.04
M80z0920 Crucetas
0.03/und________________*4.00
0.12
4.07
6.00/m3_________________*0.03 +5%waste
0.19
6.44
________________________/ 1
36.86
1,249.55
55.86
1,893.51
106.00
8,952.76
106.00
8,952.76
APPLIED FACTOR
Net Rate
L= 17.05
M= 37.31
S= 1.49
Bill Quantity=84.46 m2
similar
106.00__________________*1
=
Net Rate
S= 106.00
19:39
26/02/14
98.
AI
MEP2013
Bill Quantity=250.73 m2
02.21.06 impermeabilizado
CONTRAPISO
==========
#
1) Mano de obra
9
L008V
Operario
20.93/hh________________*3.00
8.37
L011V
Oficial
17.31/hh________________*1.00
2.31
2,098.61
579.19
L012V
Peon
15.71/hh________________*6.00
12.57
3,151.68
26.65/hm________________*1.00
2) Equipos
8
APPLIED FACTOR
3.55
890.09
26.81
6,722.07
3) Materiales
#
M2100001 Cemento Portland Tipo I bls 42.5 Kg
14.93/bls_______________*0.5140 +5%waste
8.06
2,020.88
3.06/kg_________________*0.5140 +5%waste
1.65
413.70
35.00/m3________________*0.0890 +5%waste
3.27
819.89
6.00/m3_________________*0.0336 +5%waste
0.21
52.65
4.50/p2_________________*0.0640
0.29
72.71
________________________/ 1
13.48
3,379.84
36.24
9,086.46
APPLIED FACTOR
ESTAMPADO DE PISO
=================
#
Sbf30001 INCRETE - Estampado natural de pisos
36.24/m2________________*1
________________________/ 1
APPLIED FACTOR
=
Net Rate
D= 1.55
L= 20.67
M= 14.11
S= 38.20
36.24
9,086.46
76.53
19,187.78
55.00
5,172.20
55.00
5,172.20
55.00
5,172.20
E= 2.00
Bill Quantity=94.04 m2
02.21.07
1) Suministro e Instalacion
Sbf29001 Grass artificial
55.00/m2________________*1.00
=
Net Rate
S= 55.00
19:39
26/02/14
99.
AI
MEP2013
Bill Quantity=1.85 m
1) Mano de obra
#
9
L008V
Operario
20.93/hh________________*1.00
15.22
L012V
Peon
15.71/hh________________*0.33
3.77
28.16
6.97
APPLIED FACTOR
19.00
35.15
2) Materiales
#
M80a0021 Ceram. CELIMA Granilla Nevada 30x30cm
14.53/m2________________*1.000 +5%waste
15.25
28.21
9.40/bls________________*0.170 +3%waste
1.65
3.05
3.38/kg_________________*0.700 +3%waste
2.43
4.50
M80z0920 Crucetas
0.03/und________________*9.000
0.27
0.50
6.00/m3_________________*0.070 +3%waste
0.43
0.80
________________________/ 1
20.03
37.06
39.03
72.21
20.58
493.51
20.58
493.51
APPLIED FACTOR
Net Rate
L= 17.05
M= 20.49
S= 1.49
Bill Quantity=23.98 m2
56.00/pln_______________*0.35 +5%waste
=
Net Rate
M= 20.58
Bill Quantity=3.58 m2
1) Mano de obra
#
9
L008V
Operario
20.93/hh________________*1.00
15.22
54.49
L012V
Peon
15.71/hh________________*0.33
3.77
13.50
APPLIED FACTOR
19.00
68.02
2) Materiales
#
M80a0505 Ceram. EMILCERAMICA PT White bark 15x90
144.23/m2_______________*1.00 +5%waste
151.44
542.16
24.64/bls_______________*0.20 +5%waste
5.17
18.51
3.94/kg_________________*0.60 +5%waste
2.48
8.88
M80z0920 Crucetas
0.03/und________________*9.00
0.27
0.97
6.00/m3_________________*0.06 +5%waste
0.38
1.36
________________________/ 1
159.74
571.87
178.74
639.89
APPLIED FACTOR
Net Rate
L= 17.05
M= 160.20
S= 1.49
ZOCALOS
19:39
26/02/14
LEVEL 4
100.
AI
MEP2013
Bill Quantity=1,344.49 m2
1) Mano de obra
#
9
L008V
Operario
20.93/hh________________*1.00
12.88
L012V
Peon
15.71/hh________________*0.33
3.19
17,317.03
4,288.92
APPLIED FACTOR
16.07
21,605.95
2) Materiales
#
M80a0701 Cer. PORCELANOSA Arizona Stone 44.3x44.3 89.42/m2________________*1.00 +4%waste
93.00
125,037.57
24.64/bls_______________*0.20 +3%waste
5.08
6,830.01
3.94/kg_________________*0.60 +3%waste
2.44
3,280.56
M80z0920 Crucetas
0.03/und________________*5.00
0.15
201.67
6.00/m3_________________*0.02
0.12
161.34
________________________/ 1
100.78
135,497.70
116.86
157,113.53
APPLIED FACTOR
Net Rate
L= 14.43
M= 101.17
S= 1.26
CONTRAZOCALOS
LEVEL 4
Bill Quantity=1,663.02 ml
1) Mano de obra
#
9
L008V
Operario
20.93/hh________________*1.00
8.37
L012V
Peon
15.71/hh________________*0.33
2.07
13,919.48
3,442.45
APPLIED FACTOR
10.45
17,378.56
2) Materiales
#
M80a0750 Cer.ZC PORCELANOSA Arizona Stone 10x44.3 9.32/pza________________*2.250 +3%waste
21.59
35,904.60
24.64/bls_______________*0.026 +5%waste
0.67
1,114.22
3.94/kg_________________*0.065 +5%waste
0.27
449.02
M80z0920 Crucetas
0.03/und________________*2.000
0.06
99.78
6.00/m3_________________*0.002 +5%waste
0.01
16.63
________________________/ 1
22.60
37,584.25
33.05
54,962.76
APPLIED FACTOR
Net Rate
L= 9.38
19:39
26/02/14
M= 22.85
S= 0.82
101.
AI
MEP2013
Bill Quantity=116.59 ml
1) Mano de obra
#
9
L008V
Operario
20.93/hh________________*1.00
8.81
L012V
Peon
15.71/hh________________*0.33
2.18
1,027.16
254.17
APPLIED FACTOR
11.00
1,282.49
2) Materiales
#
M80a0505 Ceram. EMILCERAMICA PT White bark 15x90
144.23/m2_______________*0.150 +10%waste
23.80
2,774.84
24.64/bls_______________*0.029 +5%waste
0.75
87.44
3.94/kg_________________*0.068 +5%waste
0.28
32.65
M80z0920 Crucetas
0.03/und________________*2.00
0.06
7.00
6.00/m3_________________*0.002 +5%waste
0.01
1.17
________________________/ 1
24.90
2,903.09
35.90
4,185.52
257.29
APPLIED FACTOR
Net Rate
L= 9.87
M= 25.16
S= 0.86
Bill Quantity=33.81 ml
1) Mano de obra
#
9
L008V
Operario
20.93/hh________________*1.00
7.61
L012V
Peon
15.71/hh________________*0.33
1.89
63.90
APPLIED FACTOR
9.50
321.20
2) Materiales
#
M80a0506 Cer.ZC EMILCERAMICA Natural 7.5x60 PTCWL 29.89/pza_______________*1.600 +3%waste
49.26
1,665.48
24.64/bls_______________*0.029 +5%waste
0.75
25.36
3.94/kg_________________*0.068 +5%waste
0.28
9.47
M80z0920 Crucetas
0.03/und________________*2.000
0.06
2.03
6.00/m3_________________*0.002
0.01
0.34
________________________/ 1
50.36
1,702.67
59.86
2,023.84
5.80
22,493.73
5.80
22,488.15
APPLIED FACTOR
Net Rate
L= 8.53
M= 50.59
S= 0.75
Bill Quantity=3,878.23 ml
5.80/ml_________________*1
=
Net Rate
S= 5.80
19:39
26/02/14
102.
AI
MEP2013
Bill Quantity=200.59 ml
1) Mano de obra
#
9
L008V
Operario
20.93/hh________________*1.00
8.81
L012V
Peon
15.71/hh________________*0.33
2.18
1,767.20
437.29
APPLIED FACTOR
11.00
2,206.49
2) Materiales
#
M80a0602 Ceram.ROSSELLO Gress Sanit. Habano 15x15 17.06/m2________________*0.150 +5%waste
2.69
539.59
24.64/bls_______________*0.029 +5%waste
0.75
150.44
3.94/kg_________________*0.068 +5%waste
0.28
56.17
M80z0920 Crucetas
0.03/und________________*6.00
0.18
36.11
6.00/m3_________________*0.002
0.01
2.01
________________________/ 1
3.91
784.31
14.91
2,990.39
APPLIED FACTOR
Net Rate
L= 9.87
M= 4.17
S= 0.86
Bill Quantity=4.74 ml
1) Mano de obra
#
9
L008V
Operario
20.93/hh________________*1.00
8.81
41.76
L012V
Peon
15.71/hh________________*0.33
2.18
10.33
APPLIED FACTOR
11.00
52.14
2) Materiales
#
M80a0021 Ceram. CELIMA Granilla Nevada 30x30cm
14.53/m2________________*0.1500 +5%waste
2.29
10.85
9.40/bls________________*0.0528 +5%waste
0.52
2.46
3.38/kg_________________*0.0967 +5%waste
0.34
1.61
M80z0920 Crucetas
0.03/und________________*3.0000
0.09
0.43
6.00/m3_________________*0.0045 +5%waste
0.03
0.14
________________________/ 1
3.27
15.50
14.27
67.63
APPLIED FACTOR
Net Rate
L= 9.87
19:39
26/02/14
M= 3.53
S= 0.86
103.
AI
MEP2013
Bill Quantity=6.70 ml
1) Mano de obra
#
9
L008V
Operario
20.93/hh________________*1.00
11.16
74.77
L012V
Peon
15.71/hh________________*0.33
2.77
18.56
APPLIED FACTOR
13.93
93.33
2) Materiales
#
M80a0801 Ceram. SAN LORENZO Satinado 30x60cm
17.37/m2________________*0.4500 +7%waste
8.36
56.01
9.40/bls________________*0.0750 +4%waste
0.73
4.89
3.38/kg_________________*0.3150 +4%waste
1.11
7.44
M80z0920 Crucetas
0.03/und________________*9.0000
0.27
1.81
6.00/m3_________________*0.0135 +4%waste
0.08
0.54
________________________/ 1
10.56
70.75
24.49
164.06
1,672.19
APPLIED FACTOR
Net Rate
L= 12.50
M= 10.89
S= 1.09
Bill Quantity=279.63 ml
CONTRAZOCALO DE CEMENTO
=======================
1) Mano de obra
#
9
L008V
Operario
20.93/hh________________*1.00
5.98
L012V
Peon
15.71/hh________________*0.33
1.48
413.85
APPLIED FACTOR
7.46
2,086.04
2) Materiales
#
M2100001 Cemento Portland Tipo I bls 42.5 Kg
14.93/bls_______________*0.0119 +5%waste
0.19
53.13
35.00/m3________________*0.0016 +5%waste
0.06
16.78
6.00/m3_________________*0.0004 +5%waste
0.00
4.50/p2_________________*0.1417
0.64
178.96
________________________/ 1
0.89
248.87
2.89
808.13
2.89
808.13
0.05
13.98
APPLIED FACTOR
ACABADO SEMIPULIDO
==================
1) Mano de obra
#
9
L008V
Operario
20.93/hh________________*1.00
APPLIED FACTOR
2) Materiales
#
M2100001 Cemento Portland Tipo I bls 42.5 Kg
14.93/bls_______________/42.50 *0.15
________________________/ 1
APPLIED FACTOR
=
Net Rate
L= 9.30
19:39
26/02/14
M= 1.18
0.05
13.98
11.29
3,156.64
S= 0.80
104.
AI
MEP2013
Bill Quantity=1,590.00 ml
5.80/ml_________________*1
=
Net Rate
5.80
9,222.00
5.80
9,219.71
S= 5.80
Bill Quantity=80.00 ml
CONTRAZOCALO DE CEMENTO
=======================
1) Mano de obra
#
9
L008V
Operario
20.93/hh________________*1.00
6.98
558.40
L012V
Peon
15.71/hh________________*0.33
1.73
138.40
APPLIED FACTOR
8.71
696.80
2) Materiales
M2100001 Cemento Portland Tipo I bls 42.5 Kg
14.93/bls_______________*0.0222 +5%waste
0.35
28.00
3.06/kg_________________*0.0222 +5%waste
0.07
5.60
35.00/m3________________*0.0032 +5%waste
0.12
9.60
6.00/m3_________________*0.0008 +5%waste
0.01
0.80
4.50/p2_________________*0.1417
0.64
51.20
1.18
94.40
5.23
418.40
5.23
418.40
=
ACABADO PULIDO
==============
1) Mano de obra
#
9
L008V
Operario
20.93/hh________________*1.00
APPLIED FACTOR
2) Materiales
M2100001 Cemento Portland Tipo I bls 42.5 Kg
14.93/bls_______________/42.50 *0.20
0.07
5.60
1.00____________________*25.74
25.74
2,059.20
40.93
3,274.42
17.10
2,616.81
17.10
2,616.81
Net Rate
L= 12.53
M= 1.58
S= 26.82
Bill Quantity=153.03 ml
02.21.12
1.00____________________*17.10
=
Net Rate
S= 17.10
SARDINELES DE CONCRETO
6a0067a
LEVEL 4
Bill Quantity=3.15 ml
02.21.02
Price Qty 1
D023
M2
0.15
9.34
1.40
4.41
M3
0.023
428.78
9.86
31.07
m2
0.30
4.54
1.36
4.29
Net Rate
12.62
SARDINEL
2
C300
L= 2.82
19:39
26/02/14
M= 9.37
S= 0.25
39.76
E= 0.18
105.
AI
MEP2013
6a0059
Sardinel h=0.10 m
Bill Quantity=1,709.47 ml
02.21.03
Price Qty 1
D023
M2
0.30
9.34
2.80
4,787.39
SARDINEL
2
C300
M3
0.045
428.78
19.30
32,984.65
m2
0.30
16.19
4.86
8,301.19
Net Rate
26.95
L= 7.24
M= 18.70
S= 0.65
46,073.23
E= 0.35
APARATOS SANITARIOS
LEVEL 4
02.21.02
2) Materiales
M1015201 Lavatorio ITALGRIF Aruba
20.67/und_______________*1
20.67
9.84
9.84
15.03
15.03
17.08
17.08
62.62
62.62
62.62
62.62
407.70
5,300.10
407.70
5,300.10
=
Net Rate
20.67
M= 62.62
407.70/und______________*1
=
Net Rate
M= 407.70
02.21.04 Kohler
821.74/und______________*1
821.74
10,682.62
1,056.87
13,739.31
1,878.61
24,421.93
1,878.61
24,421.88
1,088.62
19,105.28
1,088.62
19,105.28
=
Net Rate
M= 1,878.61
02.21.05
Sbg9989
Granito, Marmol,cuarzo
1.00____________________*1088.62
=
Net Rate
S= 1,088.62
19:39
26/02/14
106.
AI
MEP2013
1,295.98
6,479.90
334.82
1,674.10
24.52
122.60
99.50
497.50
1,754.82
8,774.10
1,754.82
8,774.10
99.50/und_______________*1
=
Net Rate
M= 1,754.82
GRIFERIAS
LEVEL 4
19.38/und_______________*1
=
Net Rate
19.38
19.38
19.38
19.38
M= 19.38
ACCESORIOS SANITARIOS
LEVEL 4
1) Mano de obra
#
9
L008V
Operario
20.93/hh________________*1
APPLIED FACTOR
10.47
1,580.97
10.47
1,580.97
109.51
16,536.01
119.98
18,116.86
54.00
8,046.00
54.00
8,046.00
2) Materiales
M1039001 Unlighted cosmetic mirror 200mm ALISEO
109.51/und______________*1
=
Net Rate
L= 9.44
M= 109.75
S= 0.79
02.21.03
M1031201 Jabonera
54.00/und_______________*1
=
Net Rate
M= 54.00
ESPEJOS
LEVEL 4
0.98____________________*89.48
=
Net Rate
87.69
1,139.97
87.69
1,139.98
S= 87.69
ESTRUCTURAS
LEVEL 2
n
LEVEL 3
n
EXCAVACION MASIVA
LEVEL 4
19:39
26/02/14
107.
AI
MEP2013
B006b
Bill Quantity=17,550.99 m
03.01.01
L012V
15.71/hh________________*2.00
0.32
5,616.32
Peon
272.07/hm_______________*1.00
2.78
48,791.75
________________________/98 M3/H
3.10
54,408.07
27.30
479,142.03
30.40
533,496.59
APPLIED FACTOR
SR030a
21.00/m3______________*1+30% esponjamiento
Net Rate
D= 0.89
L= 0.47
M= 0.01
S= 27.34
E= 1.68
EXCAVACION LOCALIZADA
B001
LEVEL 4
Bill Quantity=117.16 m
L012V
Peon
15.71/hh________________*1.0
APPLIED FACTOR
=
Net Rate
L= 39.51
B020
M= 1.34
44.90
5,260.48
44.90
5,260.48
44.90
5,260.38
4,372.47
S= 4.04
Perfilado de taludes
Bill Quantity=2,301.30 m
03.01.02
1) MANO DE OBRA
=============
#
9
L008V
Operario
20.93/hh________________*1.00
1.90
L012V
Peon
15.71/hh________________*2.00
2.86
6,581.72
APPLIED FACTOR
________________________/11 M2/H
4.76
10,954.19
6.00/m3_________________*2.2*1%
=
Net Rate
L= 4.23
19:39
26/02/14
M= 0.26
0.13
299.17
4.89
11,258.74
S= 0.40
108.
AI
MEP2013
O048
Paeteo de taludes
Bill Quantity=2,301.30 m
03.01.02
L008V
Operario
20.93/hh________________*1.0
1.55
3,567.02
L012V
Peon
15.71/hh________________*0.50
0.58
1,334.75
APPLIED FACTOR
2.13
4,901.77
3,428.94
2) MATERIALES
M2100001 Cemento Portland Tipo I bls 42.5 Kg
14.93/bls_______________*(1/10)
1.49
34.00/m3________________*0.035
1.19
2,738.55
4.82
11,082.42
Net Rate
L= 1.91
M= 2.74
S= 0.17
LEVEL 4
1) SUBCONTRATO
===============
SCH051g
Anclaje de 4 cabos
398.00/m________________*98
39,004.00
39,004.00
SCH051h
Anclaje de 5 cabos
403.33/m________________*297
= 119,789.01
119,789.01
SCH051i
Anclaje de 6 cabos
408.80/m________________*129
52,735.20
52,735.20
SCH051j
Anclaje de 7 cabos
414.12/m________________*598.5
= 247,850.82
247,850.82
SCH052
18,014.40
18,014.40
477,393.43
477,393.43
477,393.43
477,393.43
9,730.00
9,730.00
9,730.00
9,730.00
O015
Movilizacin y desmovilizacin de
SCH050
=
Net Rate
S= 9,730.00
19:39
26/02/14
LEVEL 4
109.
AI
MEP2013
C053c
Bill Quantity=912.00 m
03.01.04 pantalla
1) MANO DE OBRA
============
#
9
L008Vc
Operario Concreto
20.93/hh________________*1.00
9.05
8,253.60
L011Vc
Oficial Concreto
17.31/hh________________*2.00
14.97
13,652.64
L012Vc
Peon Concreto
15.71/hh________________*4.00
27.18
24,788.16
5.41/hm_________________*2.00
2) EQUIPOS
=======
8
APPLIED FACTOR
4.68
4,268.16
55.88
50,962.56
342,182.40
3) MATERIALES
==========
M2120013 Conc. premzcl fc=350K Tp.1 P#67 Sl 4-6" 268.00/m3_______________*1.00+40%WASTE
375.20
SO050
35.00
31,920.00
466.08
425,066.36
70,702.49
35.00/m3________________*1.00
Net Rate
D= 2.52
D058c
L= 45.38
M= 376.62
S= 39.40
E= 2.16
Bill Quantity=2,279.99 m
03.01.04 pantalla
1) MANO DE OBRA
============
#
9
L008Va
Operario Encofrado
20.93/hh________________*2.00
31.01
L011Va
Oficial Encofrado
17.31/hh________________*2.00
25.64
58,458.94
APPLIED FACTOR
56.65
129,161.43
2) MATERIALES
==========
T001/020 Encof. Metlico p/Muros (1 Cara) h <=3m
42.48/m2mes_____________/6rotaciones
7.08
16,142.33
22.24/undme_____________/16rotaciones
1.39
3,169.19
SC021
2.92/m2_________________*1
2.92
6,657.57
0.75/und________________*1
0.75
1,709.99
0.26
592.80
1.23/m2_________________*1.00
1.23
2,804.39
3.48/Kg_________________*0.20
0.70
1,595.99
4.30/p2_________________*0.7
3.01
6,862.77
3.48/kg_________________*0.20
0.70
1,595.99
30.58/Ton______*0.095ton/m2*2viajes/12rota
0.48
1,094.40
75.16
171,370.85
4) FLETE
======
SR010
19:39
26/02/14
M= 7.75
S= 7.95
E= 8.47
110.
AI
MEP2013
X002c
Bill Quantity=89,827.92 kg
03.01.04
L008Vb
Operario Acero
20.93/hh________________*1.00
0.52
46,710.52
L011Vb
Oficial Acero
17.31/hh________________*1.00
0.43
38,626.01
APPLIED FACTOR
________________________/(320/8) Kg/Hr
0.96
86,234.80
2) MATERIALES
==============
M0300001 Acero Corrugado fy= 4200 Kg/cm2 Dimensio 2.50/Kg_________________*1.00+1%waste
2.53
227,264.64
3.48/Kg_________________*0.04
0.14
12,575.91
0.20/und________________*0.08
0.02
1,796.56
3.64
326,698.85
Net Rate
L= 0.86
C053d
M= 2.70
S= 0.08
Bill Quantity=168.83 m
03.01.04 pantalla
1) MANO DE OBRA
============
#
9
L008Vc
Operario Concreto
20.93/hh________________*1.00
9.85
1,662.98
L011Vc
Oficial Concreto
17.31/hh________________*2.00
16.29
2,750.24
L012Vc
Peon Concreto
15.71/hh________________*4.00
29.58
4,993.99
5.41/hm_________________*2.00
2) EQUIPOS
=======
8
APPLIED FACTOR
5.09
859.34
60.81
10,266.55
45,128.26
3) MATERIALES
==========
M2120011 Conc. premzcl fc=280K Tp.1 P#67 Sl 4-6" 243.00/m3_______________*1.00+10%waste
267.30
SO050
35.00
5,909.05
363.11
61,304.24
35.00/m3________________*1.00
Net Rate
D= 2.74
19:39
26/02/14
L= 49.38
M= 268.85
S= 39.79
E= 2.35
111.
AI
MEP2013
D001
Bill Quantity=358.48 m
1) MANO DE OBRA
============
#
9
L008Va
Operario Encofrado
20.93/hh________________*1.00
33.49
L011Va
Oficial Encofrado
17.31/hh________________*1.00
27.69
12,005.50
9,926.31
APPLIED FACTOR
61.19
21,935.39
2) MATERIALES
==========
4.30/p2_________________*4.03/4usos
4.33
1,552.22
3.48/kg_________________*0.15
0.52
186.41
3.48/Kg_________________*0.30
1.04
372.82
0.34/m2_________________*1.00
0.34
121.88
340.00/gln______________*(1/15)*(1/5)
4.53
1,623.91
170.00/gln_____________*(1/15)*(1/5)*(1/3)
0.76
272.44
72.71
26,065.20
X002c
M= 12.76
S= 4.91
Bill Quantity=3,847.34 kg
03.01.04
L008Vb
Operario Acero
20.93/hh________________*1.00
0.52
2,000.62
L011Vb
Oficial Acero
17.31/hh________________*1.00
0.43
1,654.36
APPLIED FACTOR
________________________/(320/8) Kg/Hr
0.96
3,693.45
2) MATERIALES
==============
M0300001 Acero Corrugado fy= 4200 Kg/cm2 Dimensio 2.50/Kg_________________*1.00+1%waste
2.53
9,733.77
3.48/Kg_________________*0.04
0.14
538.63
0.20/und________________*0.08
0.02
76.95
3.64
13,992.55
Net Rate
L= 0.86
M= 2.70
S= 0.08
ESTRUCTURAS - SOTANOS
n
LEVEL 3
MOVIMIENTO DE TIERRAS
B001
LEVEL 4
Bill Quantity=99.72 m
L012V
Peon
15.71/hh________________*1.0
APPLIED FACTOR
=
Net Rate
L= 39.51
19:39
26/02/14
M= 1.34
44.90
4,477.43
44.90
4,477.43
44.90
4,477.34
S= 4.04
112.
AI
MEP2013
B001
Bill Quantity=2,046.46 m
L012V
Peon
15.71/hh________________*1.0
APPLIED FACTOR
=
Net Rate
L= 39.51
B060
M= 1.34
44.90
91,886.05
44.90
91,886.05
44.90
91,884.23
S= 4.04
Relleno y compactacin
Bill Quantity=380.33 m
03.02.01
L008V
Operario
20.93/hh________________*1.00
9.30
3,537.07
L012V
Peon
15.71/hh________________*3.00
20.95
7,967.91
14.03/hm________________*1.00
________________________/(18/8) M2/HR
2) EQUIPOS
=======
8
APPLIED FACTOR
Net Rate
D= 1.29
T003
L= 26.83
M= 0.84
S= 2.59
6.24
2,373.26
36.49
13,878.24
36.49
13,879.26
32.89
47,428.70
32.89
47,425.99
E= 4.94
Bill Quantity=1,442.04 m
03.02.01
25.30/m3____________*1.00+30%esponjamiento
Net Rate
S= 32.89
B074
Bill Quantity=1,153.57 m
1) MANO DE OBRA
============
#
9
L011V
Oficial
17.31/hh________________*1.00
1.21
1,395.82
L012V
Peon
15.71/hh________________*1.00
1.10
1,268.93
39.44/hm________________*1
2.77
3,195.39
________________________/(114/8) M2/HR
5.09
5,871.67
5.09
5,865.92
2) EQUIPOS
=======
8
APPLIED FACTOR
Net Rate
D= 0.82
L= 2.05
M= 0.07
S= 0.20
E= 1.95
19:39
26/02/14
LEVEL 4
113.
AI
MEP2013
C195
Solado
Bill Quantity=525.66 m
03.02.02
1) MANO DE OBRA
============
#
9
L008Vc
Operario Concreto
20.93/hh________________*3.00
5.29
L011Vc
Oficial Concreto
17.31/hh________________*1.00
1.46
2,780.74
767.46
L012Vc
Peon Concreto
15.71/hh________________*8.00
10.59
5,566.74
26.65/hm________________*1.00
2) EQUIPOS
=======
8
APPLIED FACTOR
2.24
1,177.48
19.58
10,292.42
#
3) MATERIALES
==========
M2100001 Cemento Portland Tipo I bls 42.5 Kg
14.93/bls_______________*0.190
2.84
1,492.87
M0500007 Hormigon
34.00/m3________________*0.065
2.21
1,161.71
________________________*1
APPLIED FACTOR
Net Rate
D= 0.98
C223
L= 15.38
M= 5.52
S= 1.48
5.05
2,654.58
24.62
12,943.71
1,319.93
E= 1.26
Bill Quantity=59.11 m
1) MANO DE OBRA
============
#
9
L008Vc
Operario Concreto
20.93/hh________________*3.00
22.33
L011Vc
Oficial Concreto
17.31/hh________________*1.00
6.15
363.53
L012Vc
Peon Concreto
15.71/hh________________*8.00
44.70
2,642.22
26.65/hm________________*1.00
________________________/ (22.5/8)M3/HR
2) EQUIPOS
=======
8
APPLIED FACTOR
9.48
560.36
82.66
4,886.03
3) MATERIALES
==========
#
M0505005 Piedra Grande 25cm max
50.00/m3________________*0.52
26.00
1,536.86
M0500007 Hormigon
34.00/m3________________*0.78
26.52
1,567.60
14.93/bls_______________*2.90
43.30
2,559.46
________________________*1
APPLIED FACTOR
Net Rate
D= 4.14
19:39
26/02/14
L= 64.94
M= 97.82
S= 6.24
95.82
5,663.92
178.48
10,549.69
E= 5.34
114.
AI
MEP2013
C062a
Bill Quantity=8.0 m
03.02.02
1) MANO DE OBRA
============
#
9
L008Vc
Operario Concreto
20.93/hh________________*1.00
6.32
L011Vc
Oficial Concreto
17.31/hh________________*2.00
10.45
50.56
83.60
L012Vc
Peon Concreto
15.71/hh________________*4.00
18.98
151.84
5.41/hm_________________*2.00
2) EQUIPOS
=======
8
APPLIED FACTOR
3.27
26.16
39.01
312.08
1,713.92
3) MATERIALES
==========
M2120006 Conc. premzcl fc=210K Tp.1 P#57 Sl 3-4" 208.00/m3_______________*1.00+3%WASTE
214.24
SO050
35.00
280.00
288.25
2,306.01
35.00/m3________________*1.00
Net Rate
D= 1.76
B060
L= 31.68
M= 215.23
S= 38.07
E= 1.51
Relleno y compactacin
Bill Quantity=150.77 m
03.02.02
L008V
Operario
20.93/hh________________*1.00
9.30
1,402.16
L012V
Peon
15.71/hh________________*3.00
20.95
3,158.63
14.03/hm________________*1.00
________________________/(18/8) M2/HR
2) EQUIPOS
=======
8
APPLIED FACTOR
Net Rate
D= 1.29
L= 26.83
M= 0.84
S= 2.59
B060a
36.49
5,502.00
LEVEL 4
Bill Quantity=615.23 m
940.80
5,501.60
E= 4.94
6.24
36.49
M3
0.15
64.54
9.68
Net Rate
9.68
5,956.50
4.0HP-MAT.PRESTAMO,
D= 0.11
19:39
26/02/14
L= 2.30
M= 6.63
S= 0.22
5,956.50
E= 0.42
115.
AI
MEP2013
C026
Bill Quantity=92.28 m
03.02.03
1) MANO DE OBRA
============
#
9
L008Vc
Operario Concreto
20.93/hh________________*1.00
5.40
L011Vc
Oficial Concreto
17.31/hh________________*2.00
8.93
498.31
824.06
L012Vc
Peon Concreto
15.71/hh________________*4.00
16.22
1,496.78
5.41/hm_________________*2.00
2) EQUIPOS
=======
8
APPLIED FACTOR
2.79
257.46
33.35
3,077.54
20,153.95
3) MATERIALES
==========
M2120006 Conc. premzcl fc=210K Tp.1 P#57 Sl 3-4" 208.00/m3_______________*1.00+5%waste
218.40
SO050
35.00
3,229.80
253.40
23,383.75
286.75
26,461.17
35.00/m3________________*1.00
=
Net Rate
D= 1.50
9D006
L= 27.08
M= 219.25
S= 37.63
E= 1.29
Bill Quantity=302.35 ml
03.02.03
D006
M2
0.15
46.33
6.95
Net Rate
6.95
2,101.06
DE PISO
L= 3.95
M= 2.65
VEREDAS EN STANOS
D006
2,101.06
S= 0.35
LEVEL 4
Bill Quantity=6 M2
03.02.04 DE PISO
1) MANO DE OBRA
============
#
9
L008Va
Operario Encofrado
20.93/hh________________*1.00
15.95
L011Va
Oficial Encofrado
17.31/hh________________*1.00
13.19
95.70
79.14
APPLIED FACTOR
29.14
174.84
2) MATERIALES
==========
M0200001 Alambre Negro N8
3.48/Kg_________________*0.30
1.04
6.24
4.30/p2_________________*2.18
9.37
56.22
3.48/kg_________________*0.33
6.90
69.36
0.34/m2_________________*1.00
0.34
2.04
340.00/gln______________*(1/15)*(1/5)
4.53
27.18
170.00/gln_____________*(1/15)*(1/5)*(1/3)
Net Rate
L= 26.34
19:39
1.15
11.56
26/02/14
M= 17.64
0.76
4.56
46.33
277.96
S= 2.35
116.
AI
MEP2013
C026
Bill Quantity=7.2 m
03.02.04
1) MANO DE OBRA
============
#
9
L008Vc
Operario Concreto
20.93/hh________________*1.00
5.40
L011Vc
Oficial Concreto
17.31/hh________________*2.00
8.93
38.88
64.30
L012Vc
Peon Concreto
15.71/hh________________*4.00
16.22
116.78
5.41/hm_________________*2.00
2) EQUIPOS
=======
8
APPLIED FACTOR
2.79
20.09
33.35
240.12
1,572.48
3) MATERIALES
==========
M2120006 Conc. premzcl fc=210K Tp.1 P#57 Sl 3-4" 208.00/m3_______________*1.00+5%waste
218.40
SO050
35.00
252.00
253.40
1,824.48
286.75
2,064.59
35.00/m3________________*1.00
=
Net Rate
D= 1.50
L= 27.08
M= 219.25
S= 37.63
E= 1.29
CONCRETO ARMADO
n
LEVEL 4
Zapatas
C004
LEVEL 5
Bill Quantity=328.84 m
03.02.05
1) MANO DE OBRA
============
#
9
L008Vc
Operario Concreto
20.93/hh________________*1.00
4.78
1,571.86
L011Vc
Oficial Concreto
17.31/hh________________*2.00
7.91
2,601.12
L012Vc
Peon Concreto
15.71/hh________________*4.00
14.37
4,725.43
5.41/hm_________________*2.00
2) EQUIPOS
=======
8
APPLIED FACTOR
2.47
812.23
29.54
9,713.93
3) MATERIALES
==========
M2120010 Conc. premzcl fc=280K Tp.1 P#57 Sl 3-4" 236.00/m3_______________*1.00+7%WASTE
252.52
83,038.68
SO050
35.00
11,509.40
35.00/m3________________*1.0
=
Net Rate
D= 1.33
19:39
26/02/14
L= 23.99
M= 253.27
S= 37.33
287.52
94,548.08
317.06
104,261.15
E= 1.14
117.
AI
MEP2013
D001
Bill Quantity=278.04 m
1) MANO DE OBRA
============
#
9
L008Va
Operario Encofrado
20.93/hh________________*1.00
33.49
L011Va
Oficial Encofrado
17.31/hh________________*1.00
27.69
9,311.56
7,698.93
APPLIED FACTOR
61.19
17,013.27
2) MATERIALES
==========
4.30/p2_________________*4.03/4usos
4.33
1,203.91
3.48/kg_________________*0.15
0.52
144.58
3.48/Kg_________________*0.30
1.04
289.16
0.34/m2_________________*1.00
0.34
94.53
340.00/gln______________*(1/15)*(1/5)
4.53
1,259.52
170.00/gln_____________*(1/15)*(1/5)*(1/3)
0.76
211.31
72.71
20,216.38
6,505.58
X002c
M= 12.76
S= 4.91
Bill Quantity=12,510.73 kg
03.02.05
L008Vb
Operario Acero
20.93/hh________________*1.00
0.52
L011Vb
Oficial Acero
17.31/hh________________*1.00
0.43
5,379.61
APPLIED FACTOR
________________________/(320/8) Kg/Hr
0.96
12,010.30
2) MATERIALES
==============
M0300001 Acero Corrugado fy= 4200 Kg/cm2 Dimensio 2.50/Kg_________________*1.00+1%waste
2.53
31,652.15
3.48/Kg_________________*0.04
0.14
1,751.50
0.20/und________________*0.08
0.02
250.21
3.64
45,500.79
Net Rate
L= 0.86
M= 2.70
S= 0.08
Vigas de Cimentacin
19:39
26/02/14
LEVEL 5
118.
AI
MEP2013
C022
Bill Quantity=36.80 m
1) MANO DE OBRA
============
#
9
L008Vc
Operario Concreto
20.93/hh________________*1.00
3.81
140.21
L011Vc
Oficial Concreto
17.31/hh________________*2.00
6.29
231.47
L012Vc
Peon Concreto
15.71/hh________________*4.00
11.43
420.62
5.41/hm_________________*2.00
2) EQUIPOS
=======
8
APPLIED FACTOR
1.97
72.50
23.50
864.80
8,945.34
3) MATERIALES
==========
M2120010 Conc. premzcl fc=280K Tp.1 P#57 Sl 3-4" 236.00/m3_______________*1.00+3%WASTE
243.08
SO050
35.00
1,288.00
278.08
10,233.34
301.58
11,097.98
35.00/m3________________*1.0
=
Net Rate
D= 1.06
D004
L= 19.08
M= 243.68
Encofrado y Desencofrado de
S= 36.85
E= 0.91
Vigas de
Bill Quantity=164.11 m
03.02.05 cimentacin
1) MANO DE OBRA
============
#
9
L008Va
Operario Encofrado
20.93/hh________________*1.00
15.95
2,617.55
L011Va
Oficial Encofrado
17.31/hh________________*1.00
13.19
2,164.61
APPLIED FACTOR
29.14
4,782.17
2) MATERIALES
==========
4.30/p2_________________*2.18/5usos
1.87
306.89
3.48/Kg_________________*0.30
1.04
170.67
3.48/kg_________________*0.33
1.15
188.73
0.34/m2_________________*1.00
0.34
55.80
340.00/gln______________*(1/15)*(1/5)
4.53
743.42
170.00/gln_____________*(1/15)*(1/5)*(1/3)
0.76
124.72
38.83
6,372.50
19:39
26/02/14
M= 10.14
S= 2.35
119.
AI
MEP2013
X002c
Bill Quantity=4,480.07 kg
03.02.05
L008Vb
Operario Acero
20.93/hh________________*1.00
0.52
2,329.64
L011Vb
Oficial Acero
17.31/hh________________*1.00
0.43
1,926.43
APPLIED FACTOR
________________________/(320/8) Kg/Hr
0.96
4,300.87
2) MATERIALES
==============
M0300001 Acero Corrugado fy= 4200 Kg/cm2 Dimensio 2.50/Kg_________________*1.00+1%waste
2.53
11,334.58
3.48/Kg_________________*0.04
0.14
627.21
0.20/und________________*0.08
0.02
89.60
3.64
16,293.75
Net Rate
L= 0.86
M= 2.70
S= 0.08
Reservorios
n
LEVEL 5
Cisterna
C041
LEVEL 6
Concreto
Bill Quantity=237.27 m
03.02.05
1) MANO DE OBRA
============
#
9
L008Vc
Operario Concreto
20.93/hh________________*1.00
4.29
1,017.89
L011Vc
Oficial Concreto
17.31/hh________________*2.00
7.10
1,684.62
L012Vc
Peon Concreto
15.71/hh________________*4.00
12.89
3,058.41
5.41/hm_________________*2.00
2) EQUIPOS
=======
8
APPLIED FACTOR
2.22
526.74
26.51
6,290.03
3) MATERIALES
==========
M2120013 Conc. premzcl fc=350K Tp.1 P#67 Sl 4-6" 268.00/m3_______________*1+30%waste
348.40
82,664.87
SO050
35.00
8,304.45
409.91
97,258.85
35.00/m3________________*1.00
19:39
26/02/14
L= 21.53
M= 349.07
S= 37.09
E= 1.03
120.
AI
MEP2013
D008
Encofrado y Desencofrado
Bill Quantity=1,414.60 m
03.02.05
1) MANO DE OBRA
============
#
9
L008Va
Operario Encofrado
20.93/hh________________*1.00
23.92
33,837.23
L011Va
Oficial Encofrado
17.31/hh________________*1.00
19.78
27,980.79
APPLIED FACTOR
43.70
61,818.02
5,021.83
2) MATERIALES
==========
M4300002 Madera Tornillo (Encofrado)
4.30/p2_________________*3.30/4usos
3.55
3.48/Kg_________________*0.10
0.35
495.11
3.48/kg_________________*0.30
1.04
1,471.18
4.94
6,988.12
=*1
8
1.23/m2_________________*1.00
1.23
1,739.96
340.00/gln______________*(1/15)*(1/5)
4.53
6,408.14
170.00/gln_____________*(1/15)*(1/5)*(1/3)
0.76
1,075.10
55.16
78,027.23
X002c
M= 12.25
S= 3.51
Bill Quantity=34,851.96 kg
03.02.05
L008Vb
Operario Acero
20.93/hh________________*1.00
0.52
18,123.02
L011Vb
Oficial Acero
17.31/hh________________*1.00
0.43
14,986.34
APPLIED FACTOR
________________________/(320/8) Kg/Hr
0.96
33,457.88
2) MATERIALES
==============
M0300001 Acero Corrugado fy= 4200 Kg/cm2 Dimensio 2.50/Kg_________________*1.00+1%waste
2.53
88,175.46
3.48/Kg_________________*0.04
0.14
4,879.27
0.20/und________________*0.08
0.02
697.04
3.64
126,754.53
Net Rate
L= 0.86
M= 2.70
S= 0.08
Camaras de Bombeo
19:39
26/02/14
LEVEL 6
121.
AI
MEP2013
C041
Concreto
Bill Quantity=7.35 m
03.02.05
1) MANO DE OBRA
============
#
9
L008Vc
Operario Concreto
20.93/hh________________*1.00
4.29
31.53
L011Vc
Oficial Concreto
17.31/hh________________*2.00
7.10
52.19
L012Vc
Peon Concreto
15.71/hh________________*4.00
12.89
94.74
5.41/hm_________________*2.00
2) EQUIPOS
=======
8
APPLIED FACTOR
2.22
16.32
26.51
194.85
3) MATERIALES
==========
M2120013 Conc. premzcl fc=350K Tp.1 P#67 Sl 4-6" 268.00/m3_______________*1+30%waste
348.40
2,560.74
SO050
35.00
257.25
409.91
3,012.82
35.00/m3________________*1.00
D008
L= 21.53
M= 349.07
S= 37.09
E= 1.03
Encofrado y Desencofrado
Bill Quantity=60.97 m
03.02.05
1) MANO DE OBRA
============
#
9
L008Va
Operario Encofrado
20.93/hh________________*1.00
23.92
1,458.40
L011Va
Oficial Encofrado
17.31/hh________________*1.00
19.78
1,205.99
APPLIED FACTOR
43.70
2,664.39
2) MATERIALES
==========
M4300002 Madera Tornillo (Encofrado)
4.30/p2_________________*3.30/4usos
3.55
216.44
3.48/Kg_________________*0.10
0.35
21.34
3.48/kg_________________*0.30
1.04
63.41
4.94
301.19
=*1
8
1.23/m2_________________*1.00
1.23
74.99
340.00/gln______________*(1/15)*(1/5)
4.53
276.19
170.00/gln_____________*(1/15)*(1/5)*(1/3)
0.76
46.34
55.16
3,363.01
19:39
26/02/14
M= 12.25
S= 3.51
122.
AI
MEP2013
X002c
Bill Quantity=486.49 kg
03.02.05
L008Vb
Operario Acero
20.93/hh________________*1.00
0.52
252.97
L011Vb
Oficial Acero
17.31/hh________________*1.00
0.43
209.19
APPLIED FACTOR
________________________/(320/8) Kg/Hr
0.96
467.03
2) MATERIALES
==============
M0300001 Acero Corrugado fy= 4200 Kg/cm2 Dimensio 2.50/Kg_________________*1.00+1%waste
2.53
1,230.82
3.48/Kg_________________*0.04
0.14
68.11
0.20/und________________*0.08
0.02
9.73
3.64
1,769.34
Net Rate
L= 0.86
M= 2.70
S= 0.08
Trampa de Grasa
C040
LEVEL 6
Concreto
Bill Quantity=5.31 m
03.02.05
1) MANO DE OBRA
============
#
9
L008Vc
Operario Concreto
20.93/hh________________*1.00
4.29
22.78
L011Vc
Oficial Concreto
17.31/hh________________*2.00
7.10
37.70
L012Vc
Peon Concreto
15.71/hh________________*4.00
12.89
68.45
5.41/hm_________________*2.00
2) EQUIPOS
=======
8
APPLIED FACTOR
2.22
11.79
26.51
140.77
3) MATERIALES
==========
M2120011 Conc. premzcl fc=280K Tp.1 P#67 Sl 4-6" 243.00/m3_______________*1.00+30%waste
315.90
1,677.43
SO050
35.00
185.85
377.41
2,004.04
35.00/m3________________*1.00
19:39
26/02/14
L= 21.53
M= 316.57
S= 37.09
E= 1.03
123.
AI
MEP2013
D008
Encofrado y Desencofrado
Bill Quantity=45.85 m
03.02.05
1) MANO DE OBRA
============
#
9
L008Va
Operario Encofrado
20.93/hh________________*1.00
23.92
L011Va
Oficial Encofrado
17.31/hh________________*1.00
19.78
1,096.73
906.91
APPLIED FACTOR
43.70
2,003.65
2) MATERIALES
==========
M4300002 Madera Tornillo (Encofrado)
4.30/p2_________________*3.30/4usos
3.55
162.77
3.48/Kg_________________*0.10
0.35
16.05
3.48/kg_________________*0.30
1.04
47.68
4.94
226.50
=*1
8
1.23/m2_________________*1.00
1.23
56.40
340.00/gln______________*(1/15)*(1/5)
4.53
207.70
170.00/gln_____________*(1/15)*(1/5)*(1/3)
0.76
34.85
55.16
2,529.02
114.66
X002c
M= 12.25
S= 3.51
Bill Quantity=220.5 kg
03.02.05
L008Vb
Operario Acero
20.93/hh________________*1.00
0.52
L011Vb
Oficial Acero
17.31/hh________________*1.00
0.43
94.82
APPLIED FACTOR
________________________/(320/8) Kg/Hr
0.96
211.68
2) MATERIALES
==============
M0300001 Acero Corrugado fy= 4200 Kg/cm2 Dimensio 2.50/Kg_________________*1.00+1%waste
2.53
557.87
3.48/Kg_________________*0.04
0.14
30.87
0.20/und________________*0.08
0.02
4.41
3.64
801.95
Net Rate
L= 0.86
M= 2.70
S= 0.08
Columnas
19:39
26/02/14
LEVEL 5
124.
AI
MEP2013
C047c
Concreto
f'c=350 kg/cm
Bill Quantity=141.21 m
03.02.05
1) MANO DE OBRA
============
#
9
L008Vc
Operario Concreto
20.93/hh________________*1.00
10.47
1,478.47
L011Vc
Oficial Concreto
17.31/hh________________*2.00
17.31
2,444.35
L012Vc
Peon Concreto
15.71/hh________________*3.00
23.57
3,328.32
5.41/hm_________________*2.00
2) EQUIPOS
=======
8
APPLIED FACTOR
5.41
763.95
56.76
8,015.08
38,979.61
3) MATERIALES
==========
M2120013 Conc. premzcl fc=350K Tp.1 P#67 Sl 4-6" 268.00/m3_______________*1.00+3%WASTE
276.04
SO050
35.00
4,942.35
367.80
51,936.43
35.00/m3________________*1.00
Net Rate
D= 2.91
D069a
L= 45.56
M= 277.45
S= 39.38
E= 2.50
Encofrado y Desencofrado
Bill Quantity=1,029.17 m
03.02.05
1) MANO DE OBRA
============
#
9
L008Va
Operario Encofrado
20.93/hh________________*1.00
12.41
12,772.00
L011Va
Oficial Encofrado
17.31/hh________________*1.00
10.26
10,559.28
APPLIED FACTOR
22.66
23,320.99
2) MATERIALES
==========
T001/030 Encof. Metlico p/Columas h <=3.6m
50.04/m2mes_____________/5 rotaciones
10.01
10,301.99
19.00/m2mes_____________/5rota
3.80
3,910.85
SC021
2.92/m2_________________*1
2.92
3,005.18
0.75/und________________*1
0.75
771.88
0.26
267.58
1.23/m2_________________*1.00
1.23
1,265.88
3.48/Kg_________________*0.20
0.70
720.42
4.30/p2_________________*0.7*0
0.00
3.48/kg_________________*0.20
0.70
720.42
30.58/Ton_________*0.048Kg/m2*2viaje/10rot
0.29
298.46
43.31
44,572.89
4) FLETE
========
SR010
19:39
26/02/14
M= 3.91
S= 5.05
E= 13.81
125.
AI
MEP2013
X002c
Bill Quantity=40,989.42 kg
03.02.05
L008Vb
Operario Acero
20.93/hh________________*1.00
0.52
21,314.50
L011Vb
Oficial Acero
17.31/hh________________*1.00
0.43
17,625.45
APPLIED FACTOR
________________________/(320/8) Kg/Hr
0.96
39,349.84
2) MATERIALES
==============
M0300001 Acero Corrugado fy= 4200 Kg/cm2 Dimensio 2.50/Kg_________________*1.00+1%waste
2.53
103,703.23
3.48/Kg_________________*0.04
0.14
5,738.52
0.20/und________________*0.08
0.02
819.79
3.64
149,076.11
Net Rate
L= 0.86
M= 2.70
S= 0.08
Placas
C059c
Concreto
LEVEL 5
f'c=350 kg/cm
Bill Quantity=190.50 m
03.02.05
1) MANO DE OBRA
============
#
9
L008Vc
Operario Concreto
20.93/hh________________*1.00
10.47
1,994.54
L011Vc
Oficial Concreto
17.31/hh________________*2.00
17.31
3,297.56
L012Vc
Peon Concreto
15.71/hh________________*3.00
23.57
4,490.09
5.41/hm_________________*2.00
2) EQUIPOS
=======
8
APPLIED FACTOR
5.41
1,030.61
56.76
10,812.78
52,585.62
3) MATERIALES
==========
M2120013 Conc. premzcl fc=350K Tp.1 P#67 Sl 4-6" 268.00/m3_______________*1.00+3%WASTE
276.04
SO050
35.00
6,667.50
367.80
70,065.08
35.00/m3________________*1.00
Net Rate
D= 2.91
19:39
26/02/14
L= 45.56
M= 277.45
S= 39.38
E= 2.50
126.
AI
MEP2013
D059a
Encofrado y Desencofrado
Bill Quantity=1,239.47 m
03.02.05
1) MANO DE OBRA
============
#
9
L008Va
Operario Encofrado
20.93/hh________________*1.00
12.41
15,381.82
L011Va
Oficial Encofrado
17.31/hh________________*1.00
10.26
12,716.96
APPLIED FACTOR
22.66
28,086.39
2) MATERIALES
==========
T001/005 Encof. Metlico p/Placas h <=4.20m
33.36/m2mes_____________/5 rotaciones
6.67
8,267.26
22.24/undme_____________/9rota
2.47
3,061.49
SC021
2.92/m2_________________*1
2.92
3,619.25
0.75/und________________*1
0.75
929.60
0.26
322.26
1.23/m2_________________*1.00
1.23
1,524.55
3.48/Kg_________________*0.20
0.70
867.63
4.30/p2_________________*0.7*0
0.00
3.48/kg_________________*0.20
0.70
867.63
30.58/Ton_______*0.050Kg/m2*2viajes/10rota
0.31
384.24
38.66
47,914.07
4) FLETE
======
SR010
X002c
M= 3.91
S= 5.06
E= 9.14
Bill Quantity=28,035.01 kg
03.02.05
L008Vb
Operario Acero
20.93/hh________________*1.00
0.52
14,578.21
L011Vb
Oficial Acero
17.31/hh________________*1.00
0.43
12,055.05
APPLIED FACTOR
________________________/(320/8) Kg/Hr
0.96
26,913.61
2) MATERIALES
==============
M0300001 Acero Corrugado fy= 4200 Kg/cm2 Dimensio 2.50/Kg_________________*1.00+1%waste
2.53
70,928.58
3.48/Kg_________________*0.04
0.14
3,924.90
0.20/und________________*0.08
0.02
560.70
3.64
101,961.68
Net Rate
L= 0.86
M= 2.70
S= 0.08
Vigas
19:39
26/02/14
LEVEL 5
127.
AI
MEP2013
C081c
Concreto
f'c=280 kg/cm
Bill Quantity=190.01 m
03.02.05
1) MANO DE OBRA
============
#
9
L008Vc
Operario Concreto
20.93/hh________________*1.00
6.57
1,248.37
L011Vc
Oficial Concreto
17.31/hh________________*2.00
10.86
2,063.51
L012Vc
Peon Concreto
15.71/hh________________*4.00
19.72
3,747.00
5.41/hm_________________*2.00
2) EQUIPOS
=======
8
APPLIED FACTOR
3.39
644.13
40.54
7,703.01
46,187.63
3) MATERIALES
==========
M2120010 Conc. premzcl fc=280K Tp.1 P#57 Sl 3-4" 236.00/m3_______________*1.00+3%WASTE
243.08
SO050
35.00
6,650.35
318.62
60,541.27
35.00/m3________________*1.00
Net Rate
D= 1.83
D065a
L= 32.92
M= 244.11
S= 38.19
E= 1.57
Encofrado y Desencofrado
Bill Quantity=1,472.61 m
03.02.05
1) MANO DE OBRA
============
#
9
L008Va
Operario Encofrado
20.93/hh________________*1.00
8.81
12,973.69
L011Va
Oficial Encofrado
17.31/hh________________*1.00
7.29
10,735.33
APPLIED FACTOR
16.10
23,709.02
2) MATERIALES
==========
T001/090 Encof. Metlico p/Vigas Fondo Viga
30.58/m2mes_____________/2.0 rotaciones
15.29
22,516.21
26.69/mlmes_____________/0.90/1.9rota
15.61
22,987.44
36.14/m2mes_____________/8rotaciones
4.52
6,656.20
19.00/m2mes_____________/10rotaciones
1.90
2,797.96
SC021
2.92/m2_________________*1
2.92
4,300.02
0.75/und________________*1
0.75
1,104.46
0.26
382.88
0.34/m2_________________*1.00
0.34
500.69
3.48/Kg_________________*0.20
0.70
1,030.83
4.30/p2_________________*0.50*0
0.00
3.48/kg_________________*0.20
0.70
1,030.83
30.58/Ton_________*0.095Kg/m2*2viaje/6rota
0.97
1,428.43
60.04
88,421.47
4) FLETE
=======
SR010
19:39
26/02/14
M= 2.86
S= 5.20
E= 37.32
128.
AI
MEP2013
X002c
Bill Quantity=36,136.73 kg
03.02.05
L008Vb
Operario Acero
20.93/hh________________*1.00
0.52
18,791.10
L011Vb
Oficial Acero
17.31/hh________________*1.00
0.43
15,538.79
APPLIED FACTOR
________________________/(320/8) Kg/Hr
0.96
34,691.26
2) MATERIALES
==============
M0300001 Acero Corrugado fy= 4200 Kg/cm2 Dimensio 2.50/Kg_________________*1.00+1%waste
2.53
91,425.93
3.48/Kg_________________*0.04
0.14
5,059.14
0.20/und________________*0.08
0.02
722.73
3.64
131,427.16
Net Rate
L= 0.86
M= 2.70
S= 0.08
Cortes
C081c
Concreto
LEVEL 5
f'c=280 kg/cm
Bill Quantity=68.27 m
03.02.05
1) MANO DE OBRA
============
#
9
L008Vc
Operario Concreto
20.93/hh________________*1.00
6.57
L011Vc
Oficial Concreto
17.31/hh________________*2.00
10.86
448.53
741.41
L012Vc
Peon Concreto
15.71/hh________________*4.00
19.72
1,346.28
5.41/hm_________________*2.00
2) EQUIPOS
=======
8
APPLIED FACTOR
3.39
231.44
40.54
2,767.67
16,595.07
3) MATERIALES
==========
M2120010 Conc. premzcl fc=280K Tp.1 P#57 Sl 3-4" 236.00/m3_______________*1.00+3%WASTE
243.08
SO050
35.00
2,389.45
318.62
21,752.29
35.00/m3________________*1.00
Net Rate
D= 1.83
19:39
26/02/14
L= 32.92
M= 244.11
S= 38.19
E= 1.57
129.
AI
MEP2013
D065a
Encofrado y Desencofrado
Bill Quantity=549.59 m
03.02.05
1) MANO DE OBRA
============
#
9
L008Va
Operario Encofrado
20.93/hh________________*1.00
8.81
4,841.89
L011Va
Oficial Encofrado
17.31/hh________________*1.00
7.29
4,006.51
APPLIED FACTOR
16.10
8,848.40
2) MATERIALES
==========
T001/090 Encof. Metlico p/Vigas Fondo Viga
30.58/m2mes_____________/2.0 rotaciones
15.29
8,403.23
26.69/mlmes_____________/0.90/1.9rota
15.61
8,579.10
36.14/m2mes_____________/8rotaciones
4.52
2,484.15
19.00/m2mes_____________/10rotaciones
1.90
1,044.22
SC021
2.92/m2_________________*1
2.92
1,604.80
0.75/und________________*1
0.75
412.19
0.26
142.89
0.34/m2_________________*1.00
0.34
186.86
3.48/Kg_________________*0.20
0.70
384.71
4.30/p2_________________*0.50*0
0.00
3.48/kg_________________*0.20
0.70
384.71
30.58/Ton_________*0.095Kg/m2*2viaje/6rota
0.97
533.10
60.04
32,999.61
4) FLETE
=======
SR010
X002c
M= 2.86
S= 5.20
E= 37.32
Bill Quantity=5,668.25 kg
03.02.05
L008Vb
Operario Acero
20.93/hh________________*1.00
0.52
2,947.49
L011Vb
Oficial Acero
17.31/hh________________*1.00
0.43
2,437.35
APPLIED FACTOR
________________________/(320/8) Kg/Hr
0.96
5,441.52
2) MATERIALES
==============
M0300001 Acero Corrugado fy= 4200 Kg/cm2 Dimensio 2.50/Kg_________________*1.00+1%waste
2.53
14,340.67
3.48/Kg_________________*0.04
0.14
793.56
0.20/und________________*0.08
0.02
113.37
3.64
20,615.09
Net Rate
L= 0.86
M= 2.70
S= 0.08
19:39
26/02/14
LEVEL 5
130.
AI
MEP2013
C064c
Bill Quantity=730.96 m
03.02.05
1) MANO DE OBRA
============
#
9
L008Vc
Operario Concreto
20.93/hh________________*4.00
11.96
L011Vc
Oficial Concreto
17.31/hh________________*4.00
9.89
8,742.28
7,229.19
L012Vc
Peon Concreto
15.71/hh________________*8.00
17.96
13,128.04
5.41/hm_________________*2.00
2) EQUIPOS
=======
8
APPLIED FACTOR
1.55
1,132.99
41.36
30,232.51
177,681.76
3) MATERIALES
==========
M2120010 Conc. premzcl fc=280K Tp.1 P#57 Sl 3-4" 236.00/m3_______________*1.00+3%WASTE
243.08
SO050
35.00
25,583.60
319.44
233,495.85
35.00/m3________________*1.00
Net Rate
D= 0.83
D061a
L= 35.38
M= 244.15
S= 38.36
E= 0.71
Encofrado y Desencofrado
Bill Quantity=3,659.57 m
03.02.05
1) MANO DE OBRA
============
#
9
L008Va
Operario Encofrado
20.93/hh________________*1.00
9.57
35,022.08
L011Va
Oficial Encofrado
17.31/hh________________*1.00
7.91
28,947.20
APPLIED FACTOR
17.48
63,969.28
2) MATERIALES
==========
T001/055 Encof. Metlico p/Losa Maciza
13.90/m2mes_____________/1.3 rotaciones
10.69
39,120.80
32.30/m2________________*1.00m2/8 usos
4.04
14,784.66
19.00/m2mes_____________/8rotaciones
2.37
8,673.18
SC021
2.92/m2_________________*1
2.92
10,685.94
0.75/und________________*1
2,744.68
0.75
0.26
951.49
0.34/m2_________________*1.00
0.34
1,244.25
3.48/Kg_________________*0.20
0.70
2,561.70
4.30/p2_________________*0.25*0
0.00
3.48/kg_________________*0.20
0.70
2,561.70
30.58/Ton_________*0.035Kg/m2*2viaje/4rota
0.54
1,976.17
40.78
149,236.86
4) FLETE
=======
SR010
19:39
26/02/14
M= 6.93
S= 4.87
E= 13.07
131.
AI
MEP2013
X002c
Bill Quantity=73,445.20 kg
03.02.05
L008Vb
Operario Acero
20.93/hh________________*1.00
0.52
38,191.50
L011Vb
Oficial Acero
17.31/hh________________*1.00
0.43
31,581.44
APPLIED FACTOR
________________________/(320/8) Kg/Hr
0.96
70,507.39
2) MATERIALES
==============
M0300001 Acero Corrugado fy= 4200 Kg/cm2 Dimensio 2.50/Kg_________________*1.00+1%waste
2.53
185,816.36
3.48/Kg_________________*0.04
0.14
10,282.33
0.20/und________________*0.08
0.02
1,468.90
3.64
267,115.87
Net Rate
L= 0.86
M= 2.70
S= 0.08
Losa Macizas de 22 cm
C064c
LEVEL 5
Bill Quantity=17.74 m
03.02.05
1) MANO DE OBRA
============
#
9
L008Vc
Operario Concreto
20.93/hh________________*4.00
11.96
212.17
L011Vc
Oficial Concreto
17.31/hh________________*4.00
9.89
175.45
L012Vc
Peon Concreto
15.71/hh________________*8.00
17.96
318.61
5.41/hm_________________*2.00
2) EQUIPOS
=======
8
APPLIED FACTOR
1.55
27.50
41.36
733.73
4,312.24
3) MATERIALES
==========
M2120010 Conc. premzcl fc=280K Tp.1 P#57 Sl 3-4" 236.00/m3_______________*1.00+3%WASTE
243.08
SO050
35.00
620.90
319.44
5,666.82
35.00/m3________________*1.00
Net Rate
D= 0.83
19:39
26/02/14
L= 35.38
M= 244.15
S= 38.36
E= 0.71
132.
AI
MEP2013
D061a
Encofrado y Desencofrado
Bill Quantity=80.66 m
03.02.05
1) MANO DE OBRA
============
#
9
L008Va
Operario Encofrado
20.93/hh________________*1.00
9.57
L011Va
Oficial Encofrado
17.31/hh________________*1.00
7.91
771.92
638.02
APPLIED FACTOR
17.48
1,409.94
2) MATERIALES
==========
T001/055 Encof. Metlico p/Losa Maciza
13.90/m2mes_____________/1.3 rotaciones
10.69
862.26
32.30/m2________________*1.00m2/8 usos
4.04
325.87
19.00/m2mes_____________/8rotaciones
2.37
191.16
SC021
2.92/m2_________________*1
2.92
235.53
0.75/und________________*1
0.75
60.50
0.26
20.97
0.34/m2_________________*1.00
0.34
27.42
3.48/Kg_________________*0.20
0.70
56.46
4.30/p2_________________*0.25*0
0.00
3.48/kg_________________*0.20
0.70
56.46
30.58/Ton_________*0.035Kg/m2*2viaje/4rota
0.54
43.56
40.78
3,289.31
4) FLETE
=======
SR010
X002c
M= 6.93
S= 4.87
E= 13.07
Bill Quantity=2,809.58 kg
03.02.05
L008Vb
Operario Acero
20.93/hh________________*1.00
0.52
1,460.98
L011Vb
Oficial Acero
17.31/hh________________*1.00
0.43
1,208.12
APPLIED FACTOR
________________________/(320/8) Kg/Hr
0.96
2,697.20
2) MATERIALES
==============
M0300001 Acero Corrugado fy= 4200 Kg/cm2 Dimensio 2.50/Kg_________________*1.00+1%waste
2.53
7,108.24
3.48/Kg_________________*0.04
0.14
393.34
0.20/und________________*0.08
0.02
56.19
3.64
10,218.28
Net Rate
L= 0.86
M= 2.70
S= 0.08
Rampas
19:39
26/02/14
LEVEL 5
133.
AI
MEP2013
C105c
Concreto
f'c=280 kg/cm
Bill Quantity=83.13 m
03.02.04
1) MANO DE OBRA
============
#
9
L008Vc
Operario Concreto
20.93/hh________________*3.00
18.96
L011Vc
Oficial Concreto
17.31/hh________________*1.00
5.22
1,576.14
433.94
L012Vc
Peon Concreto
15.71/hh________________*4.00
18.98
1,577.81
5.41/hm_________________*1.00
2) EQUIPOS
=======
8
APPLIED FACTOR
1.63
135.50
44.79
3,723.39
20,599.61
3) MATERIALES
==========
M2120010 Conc. premzcl fc=280K Tp.1 P#57 Sl 3-4" 236.00/m3_______________*1.00+5%WASTE
247.80
SO050
35.00
2,909.55
327.59
27,232.84
35.00/m3________________*1.00
Net Rate
D= 0.88
D021
L= 38.44
M= 248.94
S= 38.59
E= 0.75
Encofrado y Desencofrado
Bill Quantity=354.59 m
03.02.04
#
1) Mano de obra
9
L008Va
Operario Encofrado
20.93/hh________________*1.00
13.40
4,751.51
L011Va
Oficial Encofrado
17.31/hh________________*1.00
11.08
3,928.86
APPLIED FACTOR
24.47
8,676.82
248.21
2) Materiales
M0205003 Clavos p/Madera Tamao Promedio 2" a 4"
3.48/kg_________________*0.20
0.70
3.48/Kg_________________*0.10
0.35
124.11
4.30/p2_________________*2.12
9.11
3,230.31
10.16
3,602.63
=
8
0.34/m2_________________*1.00
0.34
120.56
340.00/gln______________*(1/15)*(1/5)
4.53
1,606.29
170.00/gln_____________*(1/15)*(1/5)*(1/3)
0.76
269.49
40.26
14,275.55
19:39
26/02/14
M= 16.12
S= 1.98
134.
AI
MEP2013
X002c
Bill Quantity=8,352.91 kg
03.02.04
L008Vb
Operario Acero
20.93/hh________________*1.00
0.52
4,343.51
L011Vb
Oficial Acero
17.31/hh________________*1.00
0.43
3,591.75
APPLIED FACTOR
________________________/(320/8) Kg/Hr
0.96
8,018.79
2) MATERIALES
==============
M0300001 Acero Corrugado fy= 4200 Kg/cm2 Dimensio 2.50/Kg_________________*1.00+1%waste
2.53
21,132.86
3.48/Kg_________________*0.04
0.14
1,169.41
0.20/und________________*0.08
0.02
167.06
3.64
30,379.04
Net Rate
L= 0.86
M= 2.70
S= 0.08
Escalera
C088
Concreto
LEVEL 5
f'c=280 kg/cm
Bill Quantity=32.57 m
03.02.05
1) MANO DE OBRA
============
#
9
L008Vc
Operario Concreto
20.93/hh________________*1.00
9.05
294.76
L011Vc
Oficial Concreto
17.31/hh________________*2.00
14.97
487.57
L012Vc
Peon Concreto
15.71/hh________________*4.00
27.18
885.25
5.41/hm_________________*2.00
2) EQUIPOS
=======
8
APPLIED FACTOR
4.68
152.43
55.88
1,820.01
8,070.85
3) MATERIALES
==========
M2120010 Conc. premzcl fc=280K Tp.1 P#57 Sl 3-4" 236.00/m3_______________*1.00+5%WASTE
247.80
SO050
35.00
1,139.95
338.68
11,030.86
35.00/m3________________*1.00
Net Rate
D= 2.52
19:39
26/02/14
L= 45.38
M= 249.22
S= 39.40
E= 2.16
135.
AI
MEP2013
D017
Encofrado y Desencofrado
Bill Quantity=223.61 m
03.02.05
1) MANO DE OBRA
============
#
9
L008Va
Operario Encofrado
20.93/hh________________*1.00
33.49
L011Va
Oficial Encofrado
17.31/hh________________*1.00
27.69
7,488.70
6,191.76
APPLIED FACTOR
61.19
13,682.70
1,829.13
2) MATERIALES
==========
M4300002 Madera Tornillo (Encofrado)
4.30/p2_________________*5.71/3 usos
8.18
3.48/Kg_________________*0.10
0.35
78.26
3.48/kg_________________*0.20
0.70
156.53
9.23
2,063.92
=*1
8
0.34/m2_________________*1.00
0.34
76.03
340.00/gln______________*(1/15)*(1/5)
4.53
1,012.95
170.00/gln_____________*(1/15)*(1/5)*(1/3)
0.76
169.94
76.04
17,003.11
X002c
M= 16.09
S= 4.91
Bill Quantity=3,121.27 kg
03.02.05
L008Vb
Operario Acero
20.93/hh________________*1.00
0.52
1,623.06
L011Vb
Oficial Acero
17.31/hh________________*1.00
0.43
1,342.15
APPLIED FACTOR
________________________/(320/8) Kg/Hr
0.96
2,996.42
2) MATERIALES
==============
M0300001 Acero Corrugado fy= 4200 Kg/cm2 Dimensio 2.50/Kg_________________*1.00+1%waste
2.53
7,896.81
3.48/Kg_________________*0.04
0.14
436.98
0.20/und________________*0.08
0.02
62.43
3.64
11,351.88
Net Rate
L= 0.86
M= 2.70
S= 0.08
LEVEL 3
n
CONCRETO ARMADO
LEVEL 4
n
LEVEL 5
19:39
26/02/14
136.
AI
MEP2013
C047c
Concreto
f'c=350 kg/cm
Bill Quantity=91.86 m
03.03.01
1) MANO DE OBRA
============
#
9
L008Vc
Operario Concreto
20.93/hh________________*1.00
10.47
961.77
L011Vc
Oficial Concreto
17.31/hh________________*2.00
17.31
1,590.10
L012Vc
Peon Concreto
15.71/hh________________*3.00
23.57
2,165.14
5.41/hm_________________*2.00
2) EQUIPOS
=======
8
APPLIED FACTOR
5.41
496.96
56.76
5,213.97
25,357.03
3) MATERIALES
==========
M2120013 Conc. premzcl fc=350K Tp.1 P#67 Sl 4-6" 268.00/m3_______________*1.00+3%WASTE
276.04
SO050
35.00
3,215.10
367.80
33,785.71
8,881.34
35.00/m3________________*1.00
Net Rate
D= 2.91
D069
L= 45.56
M= 277.45
S= 39.38
E= 2.50
Encofrado y Desencofrado
Bill Quantity=715.66 m
03.03.01
1) MANO DE OBRA
============
#
9
L008Va
Operario Encofrado
20.93/hh________________*1.00
12.41
L011Va
Oficial Encofrado
17.31/hh________________*1.00
10.26
7,342.67
APPLIED FACTOR
22.66
16,216.86
2) MATERIALES
==========
T001/030 Encof. Metlico p/Columas h <=3.6m
50.04/m2mes_____________/8rotaciones
6.26
4,480.03
19.00/m2mes_____________/5rota
3.80
2,719.51
SC021
2.92/m2_________________*1
2.92
2,089.73
0.75/und________________*1
0.75
536.75
0.26
186.07
1.23/m2_________________*1.00
1.23
880.26
3.48/Kg_________________*0.20
0.70
500.96
4.30/p2_________________*0.7*0
0.00
3.48/kg_________________*0.20
0.70
500.96
30.58/Ton_______*0.048ton/m2*2viaje/16rota
0.18
128.82
39.45
28,230.26
4) FLETE
========
SR010
19:39
26/02/14
M= 3.91
S= 4.94
E= 10.05
137.
AI
MEP2013
X002c
Bill Quantity=24,260.81 kg
03.03.01
L008Vb
Operario Acero
20.93/hh________________*1.00
0.52
12,615.62
L011Vb
Oficial Acero
17.31/hh________________*1.00
0.43
10,432.15
APPLIED FACTOR
________________________/(320/8) Kg/Hr
0.96
23,290.38
2) MATERIALES
==============
M0300001 Acero Corrugado fy= 4200 Kg/cm2 Dimensio 2.50/Kg_________________*1.00+1%waste
2.53
61,379.85
3.48/Kg_________________*0.04
0.14
3,396.51
0.20/und________________*0.08
0.02
485.22
3.64
88,235.14
Net Rate
L= 0.86
M= 2.70
S= 0.08
Concreto
LEVEL 5
f'c=280 kg/cm
Bill Quantity=196.68 m
03.03.01
1) MANO DE OBRA
============
#
9
L008Vc
Operario Concreto
20.93/hh________________*1.00
10.47
2,059.24
L011Vc
Oficial Concreto
17.31/hh________________*2.00
17.31
3,404.53
L012Vc
Peon Concreto
15.71/hh________________*3.00
23.57
4,635.75
5.41/hm_________________*2.00
2) EQUIPOS
=======
8
APPLIED FACTOR
5.41
1,064.04
56.76
11,163.56
49,227.04
3) MATERIALES
==========
M2120011 Conc. premzcl fc=280K Tp.1 P#67 Sl 4-6" 243.00/m3_______________*1.00+3%WASTE
250.29
SO050
35.00
6,883.80
342.05
67,273.55
35.00/m3________________*1.00
Net Rate
D= 2.91
19:39
26/02/14
L= 45.56
M= 251.70
S= 39.38
E= 2.50
138.
AI
MEP2013
D069
Encofrado y Desencofrado
Bill Quantity=1,562.31 m
03.03.01
1) MANO DE OBRA
============
#
9
L008Va
Operario Encofrado
20.93/hh________________*1.00
12.41
19,388.27
L011Va
Oficial Encofrado
17.31/hh________________*1.00
10.26
16,029.30
APPLIED FACTOR
22.66
35,401.94
2) MATERIALES
==========
T001/030 Encof. Metlico p/Columas h <=3.6m
50.04/m2mes_____________/8rotaciones
6.26
9,780.06
19.00/m2mes_____________/5rota
3.80
5,936.78
SC021
2.92/m2_________________*1
2.92
4,561.95
0.75/und________________*1
0.75
1,171.73
0.26
406.20
1.23/m2_________________*1.00
1.23
1,921.64
3.48/Kg_________________*0.20
0.70
1,093.62
4.30/p2_________________*0.7*0
0.00
3.48/kg_________________*0.20
0.70
1,093.62
30.58/Ton_______*0.048ton/m2*2viaje/16rota
0.18
281.22
39.45
61,627.61
4) FLETE
========
SR010
X002c
M= 3.91
S= 4.94
E= 10.05
Bill Quantity=40,351.44 kg
03.03.01
L008Vb
Operario Acero
20.93/hh________________*1.00
0.52
20,982.75
L011Vb
Oficial Acero
17.31/hh________________*1.00
0.43
17,351.12
APPLIED FACTOR
________________________/(320/8) Kg/Hr
0.96
38,737.38
2) MATERIALES
==============
M0300001 Acero Corrugado fy= 4200 Kg/cm2 Dimensio 2.50/Kg_________________*1.00+1%waste
2.53
102,089.14
3.48/Kg_________________*0.04
0.14
5,649.20
0.20/und________________*0.08
0.02
807.03
3.64
146,755.81
Net Rate
L= 0.86
M= 2.70
S= 0.08
19:39
26/02/14
LEVEL 5
139.
AI
MEP2013
C059c
Concreto
f'c=350 kg/cm
Bill Quantity=190.16 m
03.03.01
1) MANO DE OBRA
============
#
9
L008Vc
Operario Concreto
20.93/hh________________*1.00
10.47
1,990.98
L011Vc
Oficial Concreto
17.31/hh________________*2.00
17.31
3,291.67
L012Vc
Peon Concreto
15.71/hh________________*3.00
23.57
4,482.07
5.41/hm_________________*2.00
2) EQUIPOS
=======
8
APPLIED FACTOR
5.41
1,028.77
56.76
10,793.48
52,491.77
3) MATERIALES
==========
M2120013 Conc. premzcl fc=350K Tp.1 P#67 Sl 4-6" 268.00/m3_______________*1.00+3%WASTE
276.04
SO050
35.00
6,655.60
367.80
69,940.03
35.00/m3________________*1.00
Net Rate
D= 2.91
D059
L= 45.56
M= 277.45
S= 39.38
E= 2.50
Encofrado y Desencofrado
Bill Quantity=1,373.25 m
03.03.01
1) MANO DE OBRA
============
#
9
L008Va
Operario Encofrado
20.93/hh________________*1.00
12.41
17,042.03
L011Va
Oficial Encofrado
17.31/hh________________*1.00
10.26
14,089.55
APPLIED FACTOR
22.66
31,117.85
2) MATERIALES
==========
T001/005 Encof. Metlico p/Placas h <=4.20m
33.36/m2mes_____________/8rotaciones
4.17
5,726.45
22.24/undme_____________/9rota
2.47
3,391.93
SC021
2.92/m2_________________*1
2.92
4,009.89
0.75/und________________*1
0.75
1,029.94
0.26
357.05
1.23/m2_________________*1.00
1.23
1,689.10
3.48/Kg_________________*0.20
0.70
961.28
4.30/p2_________________*0.7*0
0.00
3.48/kg_________________*0.20
0.70
961.28
30.58/Ton_______*0.05ton/m2*2viajes/16rota
0.19
260.92
36.04
49,492.24
4) FLETE
======
SR010
19:39
26/02/14
M= 3.91
S= 4.94
E= 6.64
140.
AI
MEP2013
X002c
Bill Quantity=29,241.66 kg
03.03.01
L008Vb
Operario Acero
20.93/hh________________*1.00
0.52
15,205.66
L011Vb
Oficial Acero
17.31/hh________________*1.00
0.43
12,573.91
APPLIED FACTOR
________________________/(320/8) Kg/Hr
0.96
28,071.99
2) MATERIALES
==============
M0300001 Acero Corrugado fy= 4200 Kg/cm2 Dimensio 2.50/Kg_________________*1.00+1%waste
2.53
73,981.40
3.48/Kg_________________*0.04
0.14
4,093.83
0.20/und________________*0.08
0.02
584.83
3.64
106,350.20
Net Rate
L= 0.86
M= 2.70
S= 0.08
Concreto
LEVEL 5
f'c=280 kg/cm
Bill Quantity=464.59 m
03.03.01
1) MANO DE OBRA
============
#
9
L008Vc
Operario Concreto
20.93/hh________________*1.00
11.55
L011Vc
Oficial Concreto
17.31/hh________________*2.00
19.10
5,366.01
8,873.67
L012Vc
Peon Concreto
15.71/hh________________*3.00
26.01
12,083.99
5.41/hm_________________*2.00
2) EQUIPOS
=======
8
APPLIED FACTOR
5.97
2,773.60
62.63
29,097.27
116,282.23
3) MATERIALES
==========
M2120011 Conc. premzcl fc=280K Tp.1 P#67 Sl 4-6" 243.00/m3_______________*1.00+3%WASTE
250.29
SO050
35.00
16,260.65
347.92
161,638.75
35.00/m3________________*1.00
Net Rate
D= 3.21
19:39
26/02/14
L= 50.27
M= 251.85
S= 39.83
E= 2.76
141.
AI
MEP2013
D059
Encofrado y Desencofrado
Bill Quantity=3,363.38 m
03.03.01
1) MANO DE OBRA
============
#
9
L008Va
Operario Encofrado
20.93/hh________________*1.00
12.41
41,739.55
L011Va
Oficial Encofrado
17.31/hh________________*1.00
10.26
34,508.28
APPLIED FACTOR
22.66
76,214.19
2) MATERIALES
==========
T001/005 Encof. Metlico p/Placas h <=4.20m
33.36/m2mes_____________/8rotaciones
4.17
14,025.29
22.24/undme_____________/9rota
2.47
8,307.55
SC021
2.92/m2_________________*1
2.92
9,821.07
0.75/und________________*1
0.75
2,522.54
0.26
874.48
1.23/m2_________________*1.00
1.23
4,136.96
3.48/Kg_________________*0.20
0.70
2,354.37
4.30/p2_________________*0.7*0
0.00
3.48/kg_________________*0.20
0.70
2,354.37
30.58/Ton_______*0.05ton/m2*2viajes/16rota
0.19
639.04
36.04
121,216.96
4) FLETE
======
SR010
X002c
M= 3.91
S= 4.94
E= 6.64
Bill Quantity=44,769.74 kg
03.03.01
L008Vb
Operario Acero
20.93/hh________________*1.00
0.52
23,280.26
L011Vb
Oficial Acero
17.31/hh________________*1.00
0.43
19,250.99
APPLIED FACTOR
________________________/(320/8) Kg/Hr
0.96
42,978.95
2) MATERIALES
==============
M0300001 Acero Corrugado fy= 4200 Kg/cm2 Dimensio 2.50/Kg_________________*1.00+1%waste
2.53
113,267.44
3.48/Kg_________________*0.04
0.14
6,267.76
0.20/und________________*0.08
0.02
895.39
3.64
162,824.91
Net Rate
L= 0.86
M= 2.70
S= 0.08
Vigas
19:39
26/02/14
LEVEL 5
142.
AI
MEP2013
C081c
Concreto
f'c=280 kg/cm
Bill Quantity=519.71 m
03.03.01
1) MANO DE OBRA
============
#
9
L008Vc
Operario Concreto
20.93/hh________________*1.00
6.57
L011Vc
Oficial Concreto
17.31/hh________________*2.00
10.86
3,414.49
5,644.05
L012Vc
Peon Concreto
15.71/hh________________*4.00
19.72
10,248.68
5.41/hm_________________*2.00
2) EQUIPOS
=======
8
APPLIED FACTOR
3.39
1,761.82
40.54
21,069.04
126,331.11
3) MATERIALES
==========
M2120010 Conc. premzcl fc=280K Tp.1 P#57 Sl 3-4" 236.00/m3_______________*1.00+3%WASTE
243.08
SO050
35.00
18,189.85
318.62
165,590.78
35.00/m3________________*1.00
Net Rate
D= 1.83
D065
L= 32.92
M= 244.11
S= 38.19
E= 1.57
Encofrado y Desencofrado
Bill Quantity=3,986.37 m
03.03.01
1) MANO DE OBRA
============
#
9
L008Va
Operario Encofrado
20.93/hh________________*1.00
8.81
35,119.92
L011Va
Oficial Encofrado
17.31/hh________________*1.00
7.29
29,060.64
APPLIED FACTOR
16.10
64,180.56
2) MATERIALES
==========
T001/090 Encof. Metlico p/Vigas Fondo Viga
30.58/m2mes_____________/2.0rotaciones
15.29
60,951.60
26.69/mlmes_____________/0.90/1.9 rot
15.61
62,227.24
36.14/m2mes_____________/8rotaciones
4.52
18,018.39
19.00/m2mes_____________/10rotaciones
1.90
7,574.10
SC021
2.92/m2_________________*1
2.92
11,640.20
0.75/und________________*1
0.75
2,989.78
0.26
1,036.46
0.34/m2_________________*1.00
0.34
1,355.37
3.48/Kg_________________*0.20
0.70
2,790.46
4.30/p2_________________*0.50*0
0.00
3.48/kg_________________*0.20
0.70
2,790.46
30.58/Ton________*0.095ton/m2*2viaje/4rota
1.45
5,780.24
60.53
241,287.92
4) FLETE
=======
SR010
19:39
26/02/14
M= 2.86
S= 5.68
E= 37.32
143.
AI
MEP2013
X002c
Bill Quantity=113,640.39 kg
03.03.01
L008Vb
Operario Acero
20.93/hh________________*1.00
0.52
L011Vb
Oficial Acero
17.31/hh________________*1.00
0.43
59,093.00
48,865.37
APPLIED FACTOR
________________________/(320/8) Kg/Hr
0.96
109,094.77
2) MATERIALES
==============
M0300001 Acero Corrugado fy= 4200 Kg/cm2 Dimensio 2.50/Kg_________________*1.00+1%waste
2.53
287,510.19
3.48/Kg_________________*0.04
0.14
15,909.65
0.20/und________________*0.08
0.02
2,272.81
3.64
413,303.41
Net Rate
L= 0.86
M= 2.70
S= 0.08
Vigas Postensadas
D065
LEVEL 5
Encofrado y Desencofrado
Bill Quantity=143.87 m
03.03.01
1) MANO DE OBRA
============
#
9
L008Va
Operario Encofrado
20.93/hh________________*1.00
8.81
1,267.49
L011Va
Oficial Encofrado
17.31/hh________________*1.00
7.29
1,048.81
APPLIED FACTOR
16.10
2,316.31
2) MATERIALES
==========
T001/090 Encof. Metlico p/Vigas Fondo Viga
30.58/m2mes_____________/2.0rotaciones
15.29
2,199.77
26.69/mlmes_____________/0.90/1.9 rot
15.61
2,245.81
36.14/m2mes_____________/8rotaciones
4.52
650.29
19.00/m2mes_____________/10rotaciones
1.90
273.35
SC021
2.92/m2_________________*1
2.92
420.10
0.75/und________________*1
0.75
107.90
0.26
37.41
0.34/m2_________________*1.00
0.34
48.92
3.48/Kg_________________*0.20
0.70
100.71
4.30/p2_________________*0.50*0
0.00
3.48/kg_________________*0.20
0.70
100.71
30.58/Ton________*0.095ton/m2*2viaje/4rota
1.45
208.61
60.53
8,708.20
4) FLETE
=======
SR010
19:39
26/02/14
M= 2.86
S= 5.68
E= 37.32
144.
AI
MEP2013
X002c
Bill Quantity=4,466.82 kg
03.03.01
L008Vb
Operario Acero
20.93/hh________________*1.00
0.52
2,322.75
L011Vb
Oficial Acero
17.31/hh________________*1.00
0.43
1,920.73
APPLIED FACTOR
________________________/(320/8) Kg/Hr
0.96
4,288.15
2) MATERIALES
==============
M0300001 Acero Corrugado fy= 4200 Kg/cm2 Dimensio 2.50/Kg_________________*1.00+1%waste
2.53
11,301.05
3.48/Kg_________________*0.04
0.14
625.35
0.20/und________________*0.08
0.02
89.34
3.64
16,245.56
Net Rate
L= 0.86
M= 2.70
S= 0.08
Cortes
C081c
Concreto
LEVEL 5
f'c=280 kg/cm
Bill Quantity=171.33 m
03.03.01
1) MANO DE OBRA
============
#
9
L008Vc
Operario Concreto
20.93/hh________________*1.00
6.57
1,125.64
L011Vc
Oficial Concreto
17.31/hh________________*2.00
10.86
1,860.64
L012Vc
Peon Concreto
15.71/hh________________*4.00
19.72
3,378.63
5.41/hm_________________*2.00
2) EQUIPOS
=======
8
APPLIED FACTOR
3.39
580.81
40.54
6,945.72
41,646.90
3) MATERIALES
==========
M2120010 Conc. premzcl fc=280K Tp.1 P#57 Sl 3-4" 236.00/m3_______________*1.00+3%WASTE
243.08
SO050
35.00
5,996.55
318.62
54,589.42
35.00/m3________________*1.00
Net Rate
D= 1.83
19:39
26/02/14
L= 32.92
M= 244.11
S= 38.19
E= 1.57
145.
AI
MEP2013
D065
Encofrado y Desencofrado
Bill Quantity=1,736.31 m
03.03.01
1) MANO DE OBRA
============
#
9
L008Va
Operario Encofrado
20.93/hh________________*1.00
8.81
15,296.89
L011Va
Oficial Encofrado
17.31/hh________________*1.00
7.29
12,657.70
APPLIED FACTOR
16.10
27,954.59
2) MATERIALES
==========
T001/090 Encof. Metlico p/Vigas Fondo Viga
30.58/m2mes_____________/2.0rotaciones
15.29
26,548.18
26.69/mlmes_____________/0.90/1.9 rot
15.61
27,103.80
36.14/m2mes_____________/8rotaciones
4.52
7,848.12
19.00/m2mes_____________/10rotaciones
1.90
3,298.99
SC021
2.92/m2_________________*1
2.92
5,070.03
0.75/und________________*1
0.75
1,302.23
0.26
451.44
0.34/m2_________________*1.00
0.34
590.35
3.48/Kg_________________*0.20
0.70
1,215.42
4.30/p2_________________*0.50*0
0.00
3.48/kg_________________*0.20
0.70
1,215.42
30.58/Ton________*0.095ton/m2*2viaje/4rota
1.45
2,517.65
60.53
105,095.77
6,380.77
4) FLETE
=======
SR010
X002c
M= 2.86
S= 5.68
E= 37.32
Bill Quantity=12,270.71 kg
03.03.01
L008Vb
Operario Acero
20.93/hh________________*1.00
0.52
L011Vb
Oficial Acero
17.31/hh________________*1.00
0.43
5,276.41
APPLIED FACTOR
________________________/(320/8) Kg/Hr
0.96
11,779.88
2) MATERIALES
==============
M0300001 Acero Corrugado fy= 4200 Kg/cm2 Dimensio 2.50/Kg_________________*1.00+1%waste
2.53
31,044.90
3.48/Kg_________________*0.04
0.14
1,717.90
0.20/und________________*0.08
0.02
245.41
3.64
44,627.85
Net Rate
L= 0.86
M= 2.70
S= 0.08
19:39
26/02/14
LEVEL 5
146.
AI
MEP2013
C064c
Bill Quantity=11.98 m
03.03.01
1) MANO DE OBRA
============
#
9
L008Vc
Operario Concreto
20.93/hh________________*4.00
11.96
143.28
L011Vc
Oficial Concreto
17.31/hh________________*4.00
9.89
118.48
L012Vc
Peon Concreto
15.71/hh________________*8.00
17.96
215.16
5.41/hm_________________*2.00
2) EQUIPOS
=======
8
APPLIED FACTOR
1.55
18.57
41.36
495.49
2,912.10
3) MATERIALES
==========
M2120010 Conc. premzcl fc=280K Tp.1 P#57 Sl 3-4" 236.00/m3_______________*1.00+3%WASTE
243.08
SO050
35.00
419.30
319.44
3,826.86
835.92
35.00/m3________________*1.00
Net Rate
D= 0.83
D061
L= 35.38
M= 244.15
S= 38.36
E= 0.71
Encofrado y Desencofrado
Bill Quantity=79.84 m
03.03.01
1) MANO DE OBRA
============
#
9
L008Va
Operario Encofrado
20.93/hh________________*1.00
10.47
L011Va
Oficial Encofrado
17.31/hh________________*1.00
8.65
690.62
APPLIED FACTOR
19.12
1,526.54
2) MATERIALES
==========
T001/055 Encof. Metlico p/Losa Maciza
13.90/m2mes_____________/1.6rotaciones
8.69
693.81
32.30/m2________________*1.00m2/8 usos
4.04
322.55
19.00/m2mes_____________/8rotaciones
2.37
189.22
SC021
2.92/m2_________________*1
2.92
233.13
0.75/und________________*1
0.75
59.88
0.26
20.76
0.34/m2_________________*1.00
0.34
27.15
3.48/Kg_________________*0.20
0.70
55.89
4.30/p2_________________*0.25*0
0.00
3.48/kg_________________*0.20
0.70
55.89
30.58/Ton________*0.035ton/m2*2viaje/4rota
0.54
43.11
40.41
3,226.65
4) FLETE
=======
SR010
19:39
26/02/14
M= 6.97
S= 5.01
E= 11.06
147.
AI
MEP2013
X002c
Bill Quantity=1,344.48 kg
03.03.01
L008Vb
Operario Acero
20.93/hh________________*1.00
0.52
L011Vb
Oficial Acero
17.31/hh________________*1.00
0.43
699.13
578.13
APPLIED FACTOR
________________________/(320/8) Kg/Hr
0.96
1,290.70
2) MATERIALES
==============
M0300001 Acero Corrugado fy= 4200 Kg/cm2 Dimensio 2.50/Kg_________________*1.00+1%waste
2.53
3,401.53
3.48/Kg_________________*0.04
0.14
188.23
0.20/und________________*0.08
0.02
26.89
3.64
4,889.79
Net Rate
L= 0.86
M= 2.70
S= 0.08
LEVEL 5
Bill Quantity=950.13 m
03.03.01
1) MANO DE OBRA
============
#
9
L008Vc
Operario Concreto
20.93/hh________________*4.00
11.96
L011Vc
Oficial Concreto
17.31/hh________________*4.00
9.89
11,363.55
9,396.79
L012Vc
Peon Concreto
15.71/hh________________*8.00
17.96
17,064.33
5.41/hm_________________*2.00
2) EQUIPOS
=======
8
APPLIED FACTOR
1.55
1,472.70
41.36
39,297.38
230,957.60
3) MATERIALES
==========
M2120010 Conc. premzcl fc=280K Tp.1 P#57 Sl 3-4" 236.00/m3_______________*1.00+3%WASTE
243.08
SO050
35.00
33,254.55
319.44
303,506.91
35.00/m3________________*1.00
Net Rate
D= 0.83
19:39
26/02/14
L= 35.38
M= 244.15
S= 38.36
E= 0.71
148.
AI
MEP2013
D061
Encofrado y Desencofrado
Bill Quantity=4,750.62 m
03.03.01
1) MANO DE OBRA
============
#
9
L008Va
Operario Encofrado
20.93/hh________________*1.00
10.47
49,738.99
L011Va
Oficial Encofrado
17.31/hh________________*1.00
8.65
41,092.86
APPLIED FACTOR
19.12
90,831.85
2) MATERIALES
==========
T001/055 Encof. Metlico p/Losa Maciza
13.90/m2mes_____________/1.6rotaciones
8.69
41,282.89
32.30/m2________________*1.00m2/8 usos
4.04
19,192.50
19.00/m2mes_____________/8rotaciones
2.37
11,258.97
SC021
2.92/m2_________________*1
2.92
13,871.81
0.75/und________________*1
0.75
3,562.97
0.26
1,235.16
0.34/m2_________________*1.00
0.34
1,615.21
3.48/Kg_________________*0.20
0.70
3,325.43
4.30/p2_________________*0.25*0
0.00
3.48/kg_________________*0.20
0.70
3,325.43
30.58/Ton________*0.035ton/m2*2viaje/4rota
0.54
2,565.33
40.41
191,991.43
55,099.54
4) FLETE
=======
SR010
X002c
M= 6.97
S= 5.01
E= 11.06
Bill Quantity=105,960.66 kg
03.03.01
L008Vb
Operario Acero
20.93/hh________________*1.00
0.52
L011Vb
Oficial Acero
17.31/hh________________*1.00
0.43
45,563.08
APPLIED FACTOR
________________________/(320/8) Kg/Hr
0.96
101,722.23
2) MATERIALES
==============
M0300001 Acero Corrugado fy= 4200 Kg/cm2 Dimensio 2.50/Kg_________________*1.00+1%waste
2.53
268,080.47
3.48/Kg_________________*0.04
0.14
14,834.49
0.20/und________________*0.08
0.02
2,119.21
3.64
385,372.68
Net Rate
L= 0.86
M= 2.70
S= 0.08
19:39
26/02/14
LEVEL 5
149.
AI
MEP2013
C064c
Bill Quantity=700.02 m
03.03.01
1) MANO DE OBRA
============
#
9
L008Vc
Operario Concreto
20.93/hh________________*4.00
11.96
L011Vc
Oficial Concreto
17.31/hh________________*4.00
9.89
8,372.24
6,923.20
L012Vc
Peon Concreto
15.71/hh________________*8.00
17.96
12,572.36
5.41/hm_________________*2.00
2) EQUIPOS
=======
8
APPLIED FACTOR
1.55
1,085.03
41.36
28,952.83
170,160.86
3) MATERIALES
==========
M2120010 Conc. premzcl fc=280K Tp.1 P#57 Sl 3-4" 236.00/m3_______________*1.00+3%WASTE
243.08
SO050
35.00
24,500.70
319.44
223,612.46
35.00/m3________________*1.00
Net Rate
D= 0.83
D061
L= 35.38
M= 244.15
S= 38.36
E= 0.71
Encofrado y Desencofrado
Bill Quantity=2,333.41 m
03.03.01
1) MANO DE OBRA
============
#
9
L008Va
Operario Encofrado
20.93/hh________________*1.00
10.47
24,430.80
L011Va
Oficial Encofrado
17.31/hh________________*1.00
8.65
20,184.00
APPLIED FACTOR
19.12
44,614.80
2) MATERIALES
==========
T001/055 Encof. Metlico p/Losa Maciza
13.90/m2mes_____________/1.6rotaciones
8.69
20,277.33
32.30/m2________________*1.00m2/8 usos
4.04
9,426.98
19.00/m2mes_____________/8rotaciones
2.37
5,530.18
SC021
2.92/m2_________________*1
2.92
6,813.56
0.75/und________________*1
0.75
1,750.06
0.26
606.69
0.34/m2_________________*1.00
0.34
793.36
3.48/Kg_________________*0.20
0.70
1,633.39
4.30/p2_________________*0.25*0
0.00
3.48/kg_________________*0.20
0.70
1,633.39
30.58/Ton________*0.035ton/m2*2viaje/4rota
0.54
1,260.04
40.41
94,302.37
4) FLETE
=======
SR010
19:39
26/02/14
M= 6.97
S= 5.01
E= 11.06
150.
AI
MEP2013
X002c
Bill Quantity=70,907.31 kg
03.03.01
L008Vb
Operario Acero
20.93/hh________________*1.00
0.52
36,871.80
L011Vb
Oficial Acero
17.31/hh________________*1.00
0.43
30,490.14
APPLIED FACTOR
________________________/(320/8) Kg/Hr
0.96
68,071.02
2) MATERIALES
==============
M0300001 Acero Corrugado fy= 4200 Kg/cm2 Dimensio 2.50/Kg_________________*1.00+1%waste
2.53
179,395.49
3.48/Kg_________________*0.04
0.14
9,927.02
0.20/und________________*0.08
0.02
1,418.15
3.64
257,885.71
Net Rate
L= 0.86
M= 2.70
S= 0.08
LEVEL 5
Bill Quantity=5.29 m
03.03.01
1) MANO DE OBRA
============
#
9
L008Vc
Operario Concreto
20.93/hh________________*4.00
11.96
63.27
L011Vc
Oficial Concreto
17.31/hh________________*4.00
9.89
52.32
L012Vc
Peon Concreto
15.71/hh________________*8.00
17.96
95.01
5.41/hm_________________*2.00
2) EQUIPOS
=======
8
APPLIED FACTOR
1.55
8.20
41.36
218.79
1,285.89
3) MATERIALES
==========
M2120010 Conc. premzcl fc=280K Tp.1 P#57 Sl 3-4" 236.00/m3_______________*1.00+3%WASTE
243.08
SO050
35.00
185.15
319.44
1,689.82
35.00/m3________________*1.00
Net Rate
D= 0.83
19:39
26/02/14
L= 35.38
M= 244.15
S= 38.36
E= 0.71
151.
AI
MEP2013
D061
Encofrado y Desencofrado
Bill Quantity=15.10 m
03.03.01
1) MANO DE OBRA
============
#
9
L008Va
Operario Encofrado
20.93/hh________________*1.00
10.47
158.10
L011Va
Oficial Encofrado
17.31/hh________________*1.00
8.65
130.62
APPLIED FACTOR
19.12
288.71
2) MATERIALES
==========
T001/055 Encof. Metlico p/Losa Maciza
13.90/m2mes_____________/1.6rotaciones
8.69
131.22
32.30/m2________________*1.00m2/8 usos
4.04
61.00
19.00/m2mes_____________/8rotaciones
2.37
35.79
SC021
2.92/m2_________________*1
2.92
44.09
0.75/und________________*1
0.75
11.33
0.26
3.93
0.34/m2_________________*1.00
0.34
5.13
3.48/Kg_________________*0.20
0.70
10.57
4.30/p2_________________*0.25*0
0.00
3.48/kg_________________*0.20
0.70
10.57
30.58/Ton________*0.035ton/m2*2viaje/4rota
0.54
8.15
40.41
610.25
4) FLETE
=======
SR010
X002c
M= 6.97
S= 5.01
E= 11.06
Bill Quantity=520.40 kg
03.03.01
L008Vb
Operario Acero
20.93/hh________________*1.00
0.52
270.61
L011Vb
Oficial Acero
17.31/hh________________*1.00
0.43
223.77
APPLIED FACTOR
________________________/(320/8) Kg/Hr
0.96
499.58
2) MATERIALES
==============
M0300001 Acero Corrugado fy= 4200 Kg/cm2 Dimensio 2.50/Kg_________________*1.00+1%waste
2.53
1,316.61
3.48/Kg_________________*0.04
0.14
72.86
0.20/und________________*0.08
0.02
10.41
3.64
1,892.66
Net Rate
L= 0.86
M= 2.70
S= 0.08
19:39
26/02/14
LEVEL 5
152.
AI
MEP2013
C064c
Bill Quantity=4.23 m
03.03.01
1) MANO DE OBRA
============
#
9
L008Vc
Operario Concreto
20.93/hh________________*4.00
11.96
50.59
L011Vc
Oficial Concreto
17.31/hh________________*4.00
9.89
41.83
L012Vc
Peon Concreto
15.71/hh________________*8.00
17.96
75.97
5.41/hm_________________*2.00
2) EQUIPOS
=======
8
APPLIED FACTOR
1.55
6.56
41.36
174.95
1,028.23
3) MATERIALES
==========
M2120010 Conc. premzcl fc=280K Tp.1 P#57 Sl 3-4" 236.00/m3_______________*1.00+3%WASTE
243.08
SO050
35.00
148.05
319.44
1,351.22
35.00/m3________________*1.00
Net Rate
D= 0.83
D006
L= 35.38
M= 244.15
S= 38.36
E= 0.71
Bill Quantity=32.96 M2
03.03.01 DE PISO
1) MANO DE OBRA
============
#
9
L008Va
Operario Encofrado
20.93/hh________________*1.00
15.95
525.71
L011Va
Oficial Encofrado
17.31/hh________________*1.00
13.19
434.74
APPLIED FACTOR
29.14
960.45
2) MATERIALES
==========
M0200001 Alambre Negro N8
3.48/Kg_________________*0.30
1.04
34.28
4.30/p2_________________*2.18
9.37
308.84
3.48/kg_________________*0.33
37.90
381.02
0.34/m2_________________*1.00
0.34
11.21
340.00/gln______________*(1/15)*(1/5)
4.53
149.31
170.00/gln_____________*(1/15)*(1/5)*(1/3)
Net Rate
L= 26.34
19:39
1.15
11.56
26/02/14
M= 17.64
0.76
25.05
46.33
1,526.95
S= 2.35
153.
AI
MEP2013
X002c
Bill Quantity=294.38 kg
03.03.01
L008Vb
Operario Acero
20.93/hh________________*1.00
0.52
153.08
L011Vb
Oficial Acero
17.31/hh________________*1.00
0.43
126.58
APPLIED FACTOR
________________________/(320/8) Kg/Hr
0.96
282.60
2) MATERIALES
==============
M0300001 Acero Corrugado fy= 4200 Kg/cm2 Dimensio 2.50/Kg_________________*1.00+1%waste
2.53
744.78
3.48/Kg_________________*0.04
0.14
41.21
0.20/und________________*0.08
0.02
5.89
3.64
1,070.64
9,000.00
9,000.00
9,000.00
9,000.00
Net Rate
L= 0.86
O113
M= 2.70
S= 0.08
sistema antivibracion
03.03.01
SO203
Sistema antivibracion
9000.00/glb_____________*1.00
=
Net Rate
S= 9,000.00
Escalera
C088
Concreto
LEVEL 5
f'c=280 kg/cm
Bill Quantity=50.89 m
03.03.01
1) MANO DE OBRA
============
#
9
L008Vc
Operario Concreto
20.93/hh________________*1.00
9.05
L011Vc
Oficial Concreto
17.31/hh________________*2.00
14.97
460.55
761.82
L012Vc
Peon Concreto
15.71/hh________________*4.00
27.18
1,383.19
5.41/hm_________________*2.00
2) EQUIPOS
=======
8
APPLIED FACTOR
4.68
238.17
55.88
2,843.73
12,610.54
3) MATERIALES
==========
M2120010 Conc. premzcl fc=280K Tp.1 P#57 Sl 3-4" 236.00/m3_______________*1.00+5%WASTE
247.80
SO050
35.00
1,781.15
338.68
17,235.50
35.00/m3________________*1.00
Net Rate
D= 2.52
19:39
26/02/14
L= 45.38
M= 249.22
S= 39.40
E= 2.16
154.
AI
MEP2013
D017
Encofrado y Desencofrado
Bill Quantity=352.98 m
03.03.01
1) MANO DE OBRA
============
#
9
L008Va
Operario Encofrado
20.93/hh________________*1.00
33.49
L011Va
Oficial Encofrado
17.31/hh________________*1.00
27.69
11,821.30
9,774.02
APPLIED FACTOR
61.19
21,598.85
2) MATERIALES
==========
M4300002 Madera Tornillo (Encofrado)
4.30/p2_________________*5.71/3 usos
8.18
2,887.38
3.48/Kg_________________*0.10
0.35
123.54
3.48/kg_________________*0.20
0.70
247.09
9.23
3,258.01
=*1
8
0.34/m2_________________*1.00
0.34
120.01
340.00/gln______________*(1/15)*(1/5)
4.53
1,599.00
170.00/gln_____________*(1/15)*(1/5)*(1/3)
0.76
268.26
76.04
26,840.29
X002c
M= 16.09
S= 4.91
Bill Quantity=6,302.04 kg
03.03.01
L008Vb
Operario Acero
20.93/hh________________*1.00
0.52
3,277.06
L011Vb
Oficial Acero
17.31/hh________________*1.00
0.43
2,709.88
APPLIED FACTOR
________________________/(320/8) Kg/Hr
0.96
6,049.96
2) MATERIALES
==============
M0300001 Acero Corrugado fy= 4200 Kg/cm2 Dimensio 2.50/Kg_________________*1.00+1%waste
2.53
15,944.16
3.48/Kg_________________*0.04
0.14
882.29
0.20/und________________*0.08
0.02
126.04
3.64
22,920.15
Net Rate
L= 0.86
M= 2.70
S= 0.08
19:39
26/02/14
LEVEL 5
155.
AI
MEP2013
C096a
Concreto
Bill Quantity=83.26 m
03.03.01
1) MANO DE OBRA
============
#
9
L008Vc
Operario Concreto
20.93/hh________________*1.00
6.32
L011Vc
Oficial Concreto
17.31/hh________________*2.00
10.45
526.20
870.07
L012Vc
Peon Concreto
15.71/hh________________*4.00
18.98
1,580.27
5.41/hm_________________*2.00
________________________/ (26.5/8)M3/HR
2) EQUIPOS
=======
8
APPLIED FACTOR
3.27
272.26
39.01
3,247.97
18,437.93
3) MATERIALES
==========
M2120007 Conc. premzcl fc=210K Tp.1 P#67 Sl 4-6" 215.00/m3_______________*1+3%WASTE
221.45
SO050
35.00
2,914.10
295.46
24,600.14
35.00/m3________________*1.00
Net Rate
D= 1.76
D019
L= 31.68
M= 222.44
S= 38.07
E= 1.51
Encofrado y Desencofrado
Bill Quantity=1,189.42 m
03.03.01
#
1) Mano de obra
9
L008Va
Operario Encofrado
20.93/hh________________*1.00
16.75
19,922.79
L011Va
Oficial Encofrado
17.31/hh________________*1.00
13.85
16,473.47
APPLIED FACTOR
30.59
36,384.36
2) Materiales
M4300002 Madera Tornillo (Encofrado)
4.30/p2_________________*2.12/5usos
1.82
2,164.74
3.48/kg_________________*0.20
0.70
832.59
3.48/Kg_________________*0.10
0.35
416.30
2.87
3,413.64
=
8
1.23/m2_________________*1.00
1.23
1,462.99
340.00/gln______________*(1/15)*(1/5)
4.53
5,388.07
170.00/gln_____________*(1/15)*(1/5)*(1/3)
0.76
903.96
39.98
47,547.85
19:39
26/02/14
M= 9.86
S= 2.47
156.
AI
MEP2013
X002c
Bill Quantity=7,945.33 kg
03.03.01
L008Vb
Operario Acero
20.93/hh________________*1.00
0.52
4,131.57
L011Vb
Oficial Acero
17.31/hh________________*1.00
0.43
3,416.49
APPLIED FACTOR
________________________/(320/8) Kg/Hr
0.96
7,627.52
2) MATERIALES
==============
M0300001 Acero Corrugado fy= 4200 Kg/cm2 Dimensio 2.50/Kg_________________*1.00+1%waste
2.53
20,101.68
3.48/Kg_________________*0.04
0.14
1,112.35
0.20/und________________*0.08
0.02
158.91
3.64
28,896.70
Net Rate
L= 0.86
M= 2.70
S= 0.08
LEVEL 5
Concreto
Bill Quantity=41.63 m
03.03.01
1) MANO DE OBRA
============
#
9
L008Vc
Operario Concreto
20.93/hh________________*1.00
6.32
263.10
L011Vc
Oficial Concreto
17.31/hh________________*2.00
10.45
435.03
L012Vc
Peon Concreto
15.71/hh________________*4.00
18.98
790.14
5.41/hm_________________*2.00
________________________/ (26.5/8)M3/HR
2) EQUIPOS
=======
8
APPLIED FACTOR
3.27
136.13
39.01
1,623.99
9,218.96
3) MATERIALES
==========
M2120007 Conc. premzcl fc=210K Tp.1 P#67 Sl 4-6" 215.00/m3_______________*1+3%WASTE
221.45
SO050
35.00
1,457.05
295.46
12,300.07
35.00/m3________________*1.00
Net Rate
D= 1.76
19:39
26/02/14
L= 31.68
M= 222.44
S= 38.07
E= 1.51
157.
AI
MEP2013
D019
Encofrado y Desencofrado
Bill Quantity=594.71 m
03.03.01
#
1) Mano de obra
9
L008Va
Operario Encofrado
20.93/hh________________*1.00
16.75
L011Va
Oficial Encofrado
17.31/hh________________*1.00
13.85
9,961.39
8,236.73
APPLIED FACTOR
30.59
18,192.18
2) Materiales
M4300002 Madera Tornillo (Encofrado)
4.30/p2_________________*2.12/5usos
1.82
1,082.37
3.48/kg_________________*0.20
0.70
416.30
3.48/Kg_________________*0.10
0.35
208.15
2.87
1,706.82
=
8
1.23/m2_________________*1.00
1.23
731.49
340.00/gln______________*(1/15)*(1/5)
4.53
2,694.04
170.00/gln_____________*(1/15)*(1/5)*(1/3)
0.76
451.98
39.98
23,773.92
X002c
M= 9.86
S= 2.47
Bill Quantity=3,972.66 kg
03.03.01
L008Vb
Operario Acero
20.93/hh________________*1.00
0.52
2,065.78
L011Vb
Oficial Acero
17.31/hh________________*1.00
0.43
1,708.24
APPLIED FACTOR
________________________/(320/8) Kg/Hr
0.96
3,813.75
2) MATERIALES
==============
M0300001 Acero Corrugado fy= 4200 Kg/cm2 Dimensio 2.50/Kg_________________*1.00+1%waste
2.53
10,050.83
3.48/Kg_________________*0.04
0.14
556.17
0.20/und________________*0.08
0.02
79.45
3.64
14,448.33
Net Rate
L= 0.86
M= 2.70
S= 0.08
Conectores Mecnicos
O110
LEVEL 5
03.03.01 empalmes
L008Vb
Operario Acero
20.93/hh________________*3.00
APPLIED FACTOR
________________________/(158/8) und/Hr
SO200
172.55/und______________*1.00
=
Net Rate
L= 2.87
19:39
26/02/14
M= 0.07
3.18
1,329.24
3.18
1,329.24
172.55
72,125.90
175.73
73,455.10
S= 172.79
158.
AI
MEP2013
O111
03.03.01
L008Vb
Operario Acero
20.93/hh________________*3.0
APPLIED FACTOR
________________________/(175/8) und/Hr
SO201
55.34/und_______________*1.00
=
Net Rate
L= 2.59
O112
M= 0.06
2.87
1,119.30
2.87
1,119.30
55.34
21,582.60
58.21
22,702.29
2.87
746.20
2.87
746.20
101.93
26,501.80
104.80
27,248.26
S= 55.56
03.03.01 dobleces
L008Vb
Operario Acero
20.93/hh________________*3.00
APPLIED FACTOR
________________________/(175/8) und/Hr
SO202
101.93/und______________*1.00
=
Net Rate
L= 2.59
M= 0.06
S= 102.15
ESTRUCTURAS METALICAS
n
LEVEL 4
s00670
LEVEL 5
Bill Quantity=360 kg
03.03.02
E0001
Estructura metalica
2.78/glb________________*3.00
=
Net Rate
8.34
3,002.40
8.34
3,002.40
8.34
750.60
8.34
750.60
8.34
8,106.48
8.34
8,106.48
S= 8.34
s00671
Plancha Base
Bill Quantity=90 kg
03.03.02
E0001
Estructura metalica
2.78/glb________________*3.00
=
Net Rate
S= 8.34
s00672
Bill Quantity=972 kg
03.03.02
E0001
Estructura metalica
2.78/glb________________*3.00
=
Net Rate
S= 8.34
19:39
26/02/14
159.
AI
MEP2013
s00673
Perfiles C8"x3"3mm
Bill Quantity=340 kg
03.03.02
E0001
Estructura metalica
2.78/glb________________*3.00
=
Net Rate
8.34
2,835.60
8.34
2,835.60
8.34
218.59
8.34
218.59
8.34
208.50
8.34
208.50
S= 8.34
s00674
Bill Quantity=26.21 kg
03.03.02
E0001
Estructura metalica
2.78/glb________________*3.00
=
Net Rate
S= 8.34
s00675
Bill Quantity=25 kg
03.03.02
E0001
Estructura metalica
2.78/glb________________*3.00
=
Net Rate
S= 8.34
7C100
Grouting
Bill Quantity=2.7 l
03.03.02
Price Qty 1
C101
lt
1.0
9.26
9.26
9D100
m2
0.012
69.73
0.84
2.26
C101b
lt
0.5
29.04
14.52
39.20
Net Rate
24.62
L= 5.92
M= 18.13
66.46
S= 0.56
Cobertura Liviana
s00678
25.00
LEVEL 5
Bill Quantity=25.25 m
03.03.02
E0001
Estructura metalica
2.78/glb________________*58.00
=
Net Rate
161.24
4,071.31
161.24
4,071.31
S= 161.24
19:39
26/02/14
160.
AI
MEP2013
s00679
Bill Quantity=25.25 m
03.03.02
L008V
Operario
20.93/hh________________*3.00
7.85
L011V
Oficial
17.31/hh________________*1.00
2.16
198.21
54.54
L012V
Peon
15.71/hh________________*6.00
11.79
297.70
26.65/hm________________*1.00
2) Equipos
8
APPLIED FACTOR
3.33
84.08
25.13
634.53
3) Materiales
M3018095 Membrana asfaltica autoadhesiva
23.00/m2________________*1.05
24.15
609.79
70.00/m2________________*1.05
73.50
1,855.88
14.93/bls_______________*0.3700 +5%waste
5.80
146.45
35.00/m3________________*0.0530 +5%waste
1.95
49.24
6.00/m3_________________*0.0136 +5%waste
0.09
2.27
4.50/p2_________________*0.0600
0.27
6.82
105.75
2,670.19
79.03
=
ACERO
=====
1) Mano de obra
#
9
L008Vb
Operario Acero
20.93/hh________________*1.00
3.13
L011Vb
Oficial Acero
17.31/hh________________*1.00
2.58
65.15
APPLIED FACTOR
5.71
144.18
2) Materiales
M0300002 Acero corrugado fy= 4200 kg/cm2 grado 60 2.22/kg_________________*5.6 +5%waste
13.05
329.51
3.48/Kg_________________*0.04 *5.6
0.78
19.70
0.20/und________________*0.08 *5.6
0.09
2.27
13.92
351.48
150.52
3,800.60
=
Net Rate
D= 1.46
L= 24.49
M= 120.40
S= 2.29
E= 1.88
LEVEL 5
Bill Quantity=1,900 kg
03.03.02
E0001
Estructura metalica
2.78/glb________________*3.00
=
Net Rate
8.34
15,846.00
8.34
15,846.00
8.34
166.80
8.34
166.80
S= 8.34
s00675
Bill Quantity=20 kg
03.03.02
E0001
Estructura metalica
2.78/glb________________*3.00
=
Net Rate
S= 8.34
19:39
26/02/14
LEVEL 4
161.
AI
MEP2013
C026
Bill Quantity=3 m
03.04.01
1) MANO DE OBRA
============
#
9
L008Vc
Operario Concreto
20.93/hh________________*1.00
5.40
16.20
L011Vc
Oficial Concreto
17.31/hh________________*2.00
8.93
26.79
L012Vc
Peon Concreto
15.71/hh________________*4.00
16.22
48.66
5.41/hm_________________*2.00
2) EQUIPOS
=======
8
APPLIED FACTOR
2.79
8.37
33.35
100.05
3) MATERIALES
==========
M2120006 Conc. premzcl fc=210K Tp.1 P#57 Sl 3-4" 208.00/m3_______________*1.00+5%waste
218.40
655.20
SO050
35.00
105.00
253.40
760.20
286.75
860.25
35.00/m3________________*1.00
=
Net Rate
D= 1.50
D006
L= 27.08
M= 219.25
S= 37.63
E= 1.29
Bill Quantity=12 M2
03.04.02 DE PISO
1) MANO DE OBRA
============
#
9
L008Va
Operario Encofrado
20.93/hh________________*1.00
15.95
191.40
L011Va
Oficial Encofrado
17.31/hh________________*1.00
13.19
158.28
APPLIED FACTOR
29.14
349.68
2) MATERIALES
==========
M0200001 Alambre Negro N8
3.48/Kg_________________*0.30
1.04
12.48
4.30/p2_________________*2.18
9.37
112.44
3.48/kg_________________*0.33
13.80
138.72
0.34/m2_________________*1.00
0.34
4.08
340.00/gln______________*(1/15)*(1/5)
4.53
54.36
170.00/gln_____________*(1/15)*(1/5)*(1/3)
Net Rate
L= 26.34
19:39
1.15
11.56
26/02/14
M= 17.64
0.76
9.12
46.33
555.93
S= 2.35
162.
AI
MEP2013
X002c
Bill Quantity=155 kg
03.04.03
L008Vb
Operario Acero
20.93/hh________________*1.00
0.52
L011Vb
Oficial Acero
17.31/hh________________*1.00
0.43
80.60
66.65
APPLIED FACTOR
________________________/(320/8) Kg/Hr
0.96
148.80
2) MATERIALES
==============
M0300001 Acero Corrugado fy= 4200 Kg/cm2 Dimensio 2.50/Kg_________________*1.00+1%waste
2.53
392.15
3.48/Kg_________________*0.04
0.14
21.70
0.20/und________________*0.08
0.02
3.10
3.64
563.73
Net Rate
L= 0.86
M= 2.70
S= 0.08
ACELEROMETRO
s00690
LEVEL 4
Tecnoport
03.05.01
SO205
Acelerometro
60826.01/und____________*1.00
=
Net Rate
60,826.01
60,826.01
60,826.01
60,826.01
S= 60,826.01
PARTIDAS COMPLEMENTARIAS
n
LEVEL 3
EXCAVACION LOCALIZADA
O001
LEVEL 4
03.06.01
SV031
17500.00/glb____________*1
=
Net Rate
17,500.00
17,500.00
17,500.00
17,500.00
S= 17,500.00
CONCRETO ARMADO
n
19:39
LEVEL 4
Vigas Postensadas
26/02/14
LEVEL 5
163.
AI
MEP2013
C081c
Concreto
f'c=280 kg/cm
Bill Quantity=40.66 m
03.06.02
1) MANO DE OBRA
============
#
9
L008Vc
Operario Concreto
20.93/hh________________*1.00
6.57
267.14
L011Vc
Oficial Concreto
17.31/hh________________*2.00
10.86
441.57
L012Vc
Peon Concreto
15.71/hh________________*4.00
19.72
801.82
5.41/hm_________________*2.00
2) EQUIPOS
=======
8
APPLIED FACTOR
3.39
137.84
40.54
1,648.36
9,883.63
3) MATERIALES
==========
M2120010 Conc. premzcl fc=280K Tp.1 P#57 Sl 3-4" 236.00/m3_______________*1.00+3%WASTE
243.08
SO050
35.00
1,423.10
318.62
12,955.15
35.00/m3________________*1.00
Net Rate
D= 1.83
O200
L= 32.92
M= 244.11
S= 38.19
E= 1.57
Postensado de vigas
03.06.02
[F]=21081.6
1) INSTALACION
SO210
Postensado de vigas
4.25/ton________________*1.00
4.25
89,596.80
0.24
5,059.58
14.93/bls_______________*250
0.18
3,794.69
3.48/Kg_________________*100
0.02
421.63
________________________/[F]
0.43
9,065.09
4.68
98,716.41
2) MATERIALES
#
APPLIED FACTOR
Net Rate
M= 0.43
S= 4.25
Reservorios
O211
LEVEL 5
Tapas de concreto
03.06.02
SO221
tapas de cocreto
270.00/glb______________*1.00
=
Net Rate
270.00
1,620.00
270.00
1,620.00
S= 270.00
VARIOS
19:39
26/02/14
LEVEL 4
164.
AI
MEP2013
O005
Bill Quantity=184.76 ML
03.06.03
1) JUNTA
#
Mano de Obra
============
9
L008V
Operario
20.93/hh________________*1.0
2.09
386.15
L012V
Peon
15.71/hh________________*1.0
1.57
290.07
APPLIED FACTOR
________________________/ 10 ml/hr
3.66
676.22
395.00/cja______________/30
13.17
2,433.29
45.20/hm________________*1.00
4.52
835.12
________________________/10 m/hr
4.52
835.12
2) CORTE DE LOSA
#
Mano de obra
============
8
APPLIED FACTOR
1390.00/und_____________*0.001
=
Net Rate
D= 0.35
O004a
L= 5.11
M= 14.70
S= 0.42
1.39
256.82
22.74
4,201.77
E= 2.17
Bill Quantity=244.79 ML
03.06.03
Junta de Dilatacin
===================
#
Mano de Obra
============
9
L008V
Operario
20.93/hh________________*1.0
2.09
511.61
L012V
Peon
15.71/hh________________*1.0
1.57
384.32
APPLIED FACTOR
________________________/ 10 ml/hr
3.66
895.93
26.90/pln_______________*0.15/(2.4*1.2)
=
Net Rate
L= 3.27
O004b
M= 1.50
1.40
342.71
5.07
1,240.08
S= 0.30
Bill Quantity=244.79 ML
03.06.03
Junta de Dilatacin
===================
#
Mano de Obra
============
9
L008V
Operario
20.93/hh________________*1.0
2.09
511.61
L012V
Peon
15.71/hh________________*1.0
1.57
384.32
APPLIED FACTOR
________________________/ 10 ml/hr
3.66
895.93
13.17
3,223.88
16.83
4,120.20
395.00/cja______________/30
=
Net Rate
L= 3.27
19:39
26/02/14
M= 13.26
S= 0.30
165.
AI
MEP2013
O047
Bill Quantity=717.29 ml
03.06.03
#
1) MANO DE OBRA
============
9
L008V
Operario
20.93/hh________________*1.00
5.40
3,873.37
L012V
Peon
15.71/hh________________*1.00
4.06
2,912.20
APPLIED FACTOR
9.46
6,785.56
9.46
6,784.00
Net Rate
L= 8.44
19:39
26/02/14
M= 0.24
S= 0.77
166.
AI