Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
14
14.1
INTRODUCTION
14-2
14.2
ENGINEERING APPROACH
The format of engineering information, including the content of drawings, has developed over many years. Changes
and improvements have occurred very slowly, and in some
shipyards and design ofces, not at all. Traditionally, shipyards were craft-organized and only required the minimum
number of drawings for which accuracy was not essential.
The loft prepared the templates and made everyday decisions on structural details. The pipetters worked from diagrammatics and developed their own pipe templates from
the ship being built. This system was also true for the other
shipyard crafts.
The changeover from a traditional craft-organized shipyard to one of advanced technology has obviously had a
tremendous effect on all shipyard departments. It should
have had its second greatest impact on the engineering department. However, many engineering departments did not
rise to this challenge and, therefore, lost what might have
been a lead position for directing and controlling change.
Engineering simply ignored the needed changes and left
them to be incorporated into the shipbuilding process after
their work was completed in the traditional manner. Shipyards responded to this problem by getting the necessary
production information from other sources, usually new
groups that may have been called industrial or production
engineering or perhaps from an existing planning group.
Some shipyards even accepted the fact that engineering information was inadequate for production and left it to production workers to perform as best they could. This situation
often resulted in the same work being done many times before it was reluctantly accepted by the inspectors.
Production performance depends largely on the quality,
quantity, and suitability of technical information supplied
by engineering. By organizing for integrated engineering
and preparing design and engineering for zone construction,
engineering can take its proper place and play an essential
role in the improvement of shipbuilding performance. This
section discusses how this can be done, but rst considers
what is production-compatible engineering (integrated engineering) by comparing it with traditional engineering.
14-3
14-4
of the drawings marked up with production data by the planning/production control groups for incorporation into the
original drawings before formal issue. Others provide the
required production information on unique additional documents to the traditional engineering drawings.
The traditional engineering practice of referencing drawings, ship specication, standard specications, and other
data on the drawing, instead of including the information,
is a serious problem to production. To expect production
workers or even their supervisors to have access and knowledge of the references is impractical. Because of this situation, items are often ignored and the work is not done to
spec.
Traditional engineering is not suitable for high productivity, short-build cycle shipbuilding, and therefore has no
14-5
14-6
Figure 14.4 Traditional Detailed Design and Construction Appoach Time Cycle
14-8
For burning plate: Nest tape sketches and CNC information (Figure 14.6),
For cutting shapes: Process sheets, CNC information,
and sketches (Figure 14.7),
For processing plate or shapes: Process sheets and templates,
For subassembly: Subassembly drawing and parts list,
For assembly: Assembly drawing and parts list,
For block construction: Block assembly sketches and
parts list,
For on-block outtting: Block outtting sketches and
parts list, and
For block erection: Hull block erection drawing and
moving and lifting instructions.
Figures 14.8, and 14.9 show the workstation information packages for typical subassembly, and block, respectively. Note that for the assembly and module, the parts lists
are separate from the drawings. The parts list should be sequenced in the way the product is to be constructed. Again,
the product/phase chart can be used to develop the sequencing.
It is important to remember that all the information required by the workers to perform a work package should
be included in the package. The worker should not have to
obtain or look at any other drawing, work package, standard, etc., to complete the task.
14.2.5.2 Outt workstation/zone information
The workstation/zone information will be provided for
shops, assemblies, modules, and zones. The product/stage
chart is helpful in deciding the work packages. Workstation
information for shops for both processing and assembly
will be required for hull ttings, pipe, sheet metal, foundation structure, joiner, paint, and electrical work. It is suggested that zone be used instead of the term workstation for
all the logical breakdown of the total machinery space design and engineering, and the provision of workstation/zone
information packages in place of traditional working drawings. The machinery arrangement becomes a series of major
pieces of machinery, units, and connecting system corridor/oor plate units. However, the quantity of information
provided to production is vastly increased in scope compared
to traditional engineering, plus all systems are given equal
depth of consideration and are shown to the same detail. Figure 14.10 shows a typical work station/zone instruction
sketch for outt.
Workstation information for shops for both processing and
14-10
14.3
14-13
14-14
Figure 14.13 Potential Cost Inuence as Design and Build Phase Progresses
14-15
Simplicity in Design
minimum number of parts,
minimum number of parts to be formed,
reduction of part variability,
reduction in joint weld length,
part standardization,
minimum tting/fairing of erection joints,
14-16
design than one which is designed to make best use of a shipyards facilities. Obvious shipyard imposed requirements are:
Next Page
14-17
sembly to erection, shop door sizes and the shipyards maximum plate size. The panel maximum size will depend on
panel line limits as well as any access limits. It will also be
impacted by whether the panels need to be turned and/or
rotated. A panel line with no rotation capability can achieve
the same results by vertical plate straking of shell and bulkheads when the ship is transversely framed and the bulkheads vertically stiffened.
Not so obvious and often ignored requirements are:
maximum berth loading,
spread of launchways, and
maximum launch pressure on the hull.
The maximum berth loading could affect the extent of
outtting before launch and thus the productivity achieved