Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
May 2010
0051706
www.erm.com
FINAL REPORT
Country Energy
Lismore to Mullumbimby
Electricity Network
Upgrade
Traffic Management Sub-Plan
May 2010
Date
Description
Final Traffic Management
Sub-Plan
1.0
By
Review
Approved
DirectorGeneral, DoP
Country Energy
Country Energy
10 February
2010
4 May 2010
Country Energy
24 May 2010
Country Energy
28 May 2010
Country Energy
ERM Australia
ERM Australia
ERM Australia
ERM Australia
Murray Curtis
Murray Curtis
Murray Curtis
Murray Curtis
This Sub Plan is considered a dynamic document and will be reviewed as part of the annual review process (see Section 8 of
CEMP Framework). The Sub-Plan and any subsequent revisions must be approved by the Country Energy Project Manager.
Initial approval of the Sub-Plan must also be obtained from the Director-General (or delegate), NSW Department of Planning in
accordance with the Ministers Conditions of Approval. Subsequent Sub-Plan revisions do not require Director-General (or
delegate) approval; however, a copy of the revised Sub-Plan will be submitted for information.
CONTENTS
ABBREVIATIONS
1
BACKGROUND
2.1
2.2
PURPOSE
OBJECTIVES
3.1
3.2
3.3
3.4
3.5
ENVIRONMENTAL IMPACTS
LEGISLATION AND POLICIES
MINISTERS CONDITIONS OF APPROVAL
RELATED MANAGEMENT PLANS
GUIDELINES AND STANDARDS
5.1
5.2
5.3
5.4
5.4.1
5.4.2
5.5
5.5.1
5.5.2
5.5.3
5.6
5.7
5.8
5.8.1
5.9
5.10
5.11
5.12
5.13
CONSTRUCTION PHASE
TRAFFIC GENERATED BY THE PROJECT ACTIVITIES
CONSTRUCTION VEHICLE TYPE
HEAVY VEHICLE ROUTES
MOBILE WORKS CONVOY FOR LOW LOADERS
TRAFFIC VOLUMES ASSOCIATED
WITH TRANSMISSION LINE INSTALLATION
PROJECT WORKS AT SUBSTATION LOCATIONS
REDEVELOPMENT OF EXISTING SUBSTATIONS
CONSTRUCTION OF NEW SUBSTATIONS
UPGRADE OF SKINNERS SHOOT ROAD AND YAGERS LANE
TRANSMISSION LINE CROSSING A ROADWAY
TRANSMISSION LINE INSTALLATION IN A ROAD RESERVE
TRANSMISSION LINE INSTALLATION ON PRIVATE LAND
ACCESS WAYS
DETOURS
PUBLIC TRANSPORT SERVICES
EFFECT ON TRAFFIC MOVEMENTS IN ADJOINING STREETS
PACIFIC HIGHWAY UPGRADE
ALSTONVILLE BYPASS
6.1
6.1.1
6.1.2
3
3
4
4
5
6
6
13
42
42
43
44
46
47
47
48
49
50
51
52
52
52
55
56
57
57
74
74
75
CONTENTS
6.1.3
6.1.4
6.2
6.3
6.4
LOCAL ROADS
ACCESS ROADS
TRANSMISSION LINE INSTALLATION IN A ROAD RESERVE
TRANSMISSION LINE INSTALLATION ON PRIVATE LAND
STAKEHOLDER CONSULTATION
8.1
8.2
8.3
8.4
8.4.1
8.4.2
SITE INSPECTIONS
ROAD DILAPIDATION REPORTS
CONSTRUCTION VEHICLE CODE OF CONDUCT
REPORTING
TRAFFIC CONTROL PLANS
REPORTING
75
76
76
77
77
81
81
83
84
84
84
ANNEXES
ANNEX A
ANNEX B
ANNEX C
LIST OF TABLES
TABLE 3.1
TABLE 3.3
TABLE 3.4
TABLE 3.5
TABLE 4.1
TABLE 5.1
13
TABLE 5.2
44
TABLE 6.1
59
TABLE 3.2
TABLE 6.2
STAKEHOLDER CONSULTATION
76
TABLE 8.1
81
LIST OF FIGURES
FIGURE 1.1
FIGURE 4.1
12
36
37
38
39
40
41
62
FIGURE 5.1
FIGURE 5.2
FIGURE 5.3
FIGURE 5.4
FIGURE 5.5
FIGURE 5.6
FIGURE 6.1
ABBREVIATIONS
Term
AS
BSP
CE
CECG
CEM
CEMP
CoA
dBA
EAR
EMP
EMS
EPA
ERM
KPI
kV
LALC
LRS
OHS
Definition
Australian Standard
Bulk Supply Point
Country Energy
Country Energy Construction Guidelines
Country Energy Manual
Construction Environmental Management Plan
Conditions of Approval
Decibel (A-weighted)
Environmental Assessment Report
Environmental Management Plan
Environmental Management System
Environment Protection Authority
Environmental Resources Management
Key Performance Indicator
Kilovolts
Local Aboriginal Land Council
Line Route Selection
Occupational Health and Safety
PADs
BACKGROUND
In order to cater for long term demands, Country Energy (CE) has identified
the need for augmentation of its electricity supply network in the Far North
Coast of New South Wales from Lismore to Mullumbimby which includes the
areas of Lismore, Ballina, Ewingsdale and Mullumbimby. As outlined in the
framework CEMP the Project has undergone a number of investigations
across the Project Study Area as part of detailed Environmental Assessment
(EA) in order to evaluate the extent of impact of the proposed electricity
network upgrade on the local traffic and transport network.
The location of the proposed works is illustrated on Figure 1.1.
It is estimated that in the order 20 vehicles per day (maximum), including
cars, rigid truck and cranes, would travel in and out of the substation sites
during the upgrade/construction. Semi trailers and low loaders would be
required to deliver large plant items such as transformers on several occasions
per substation site (i.e. <10 movements per site over the construction period)
and would be expected to be accounted for in the maximum daily movements
as outlined above.
!
Q
DU
!
Q
0890 &
0891
850
1
H2
!
Q
8502
HWY
0897
BRUXNE
R
!
Q Lismore East ZS
H1!
QLismore Uni ZS
LISMORE
Lismore South ZS
Lismore BSP
NIMBIN RD
RD
NO
O
EL
TH
AM
!
QAlstonville ZS
RD
85
05
8507
85
03
Q
!
SUFFOLK PARK
BYRON BAY
!
Q
BALLINA
Ballina ZS
LENNOX HEAD
!
Q Lennox Head ZS
85
08
Suffolk Park ZS
Ewingsdale ZS
!
Q
Q Brunswick Heads ZS
!
BANGALOW
!
Q Mullumbimby ZS
ALSTONVILLE
D
WR
LO
A
NG
BA
MULLUMBIMBY
BRUNSWICK HEADS
OCEAN SHORES
4
85
0
8508
PACIFIC HWY
Proposed Substation
Pacific Highway Upgrade
Casino-Murwillumbah Railway
Main Roads
Highway
Existing 132kV
Existing 66kV
SEPP14 Areas
LGA boundaries
Project Area
Built-up Areas
National Parks
Existing Substation
8 km
Environmental Resources Management Australia Pty Ltd
Building C, 33 Saunders St, Pyrmont, NSW 2009
Telephone +61 2 8584 8888
[
N
Department of Lands
Source:
Reviewed by: WW
TH
Drawn by:
A0
Drawing size: A4
29/07/08
Date:
Suffix No:
Country Energy
Client:
Figure 1.1
Project Area
!
Q
Q
!
Legend
2.1
PURPOSE
The primary purpose of this Traffic Management Sub-Plan (TM Sub-Plan) is to
provide a reference document to maximise safety of all road users and project
personnel by implementing best management practices. In addition, the SubPlan:
describes how Country Energy will manage and control risks associated
with traffic management during construction activities of the project;
address the requirements of applicable legislation;
meet the Project Conditions of Approval (CoA); and
address the requirements of the Project Environmental Assessment Report
(EAR) (ERM, 2009).
This Sub-Plan was produced in accordance with the recommendations
provided within Roads and Traffic Authority (RTA) (2003) Traffic Control at
Work Sites and Country Energys Policy Guideline CEPG 2328 Traffic Control
Safety. Reference was also made to the RTA (2000) Road Design Guide.
2.2
OBJECTIVES
The traffic management objectives established for the construction works
described in this Sub-Plan include the following:
to identify relevant obligations and legislative requirements to be
addressed during the construction phase of the Project;
to describe the specific traffic management requirements and identify the
best practice methods to be implemented;
to outline record keeping and management plan monitoring requirements;
and
to define key roles and responsibilities.
3.1
ENVIRONMENTAL IMPACTS
The Project activities that are most likely to have the potential to result in
impacts to the local traffic and transport network are the delivery of
infrastructure and equipment to various locations along the transmission line
corridor, and construction personnel travelling to and from construction
locations during the construction phase of the project. Table 3.1 summarises
the activities and potential impacts, and provides a risk analysis.
Table 3.1
Aspect
Impact
Risk
T1
Low
Low
Low
T2
T3
Note:
3.2
Risk Rankings
Table 3.2
The road upgrade construction works in the road reserves of Skinners Shoot
Road and Yagers Lane do not require a Section 138 permit from the Byron
Shire Council.
3.3
i)
ii)
iii)
iv)
v)
vi)
vii)
3.4
Table 3.3
3.5
Environmental Sub-Plan
Three Chain Road
Construction Pollution Prevention
Construction Noise and Vibration
Construction Aboriginal Cultural Heritage
Construction Flora and Fauna
Electric and Magnetic Field
Soil and Water Management
Landscape/Revegetation Plan
Table 3.5
Table 4.1
TM.EC.02
TM.EC.03
TM.EC.04
TM.EC.05
TM.EC.06
TM.EC.07
Action
Ensuring that the MCoA, Project Commitments,
CEMP and ACHM Sub-plan are being implemented.
Provide the DoP, RTA, Local Councils and
emergency services with the opportunity to
contribute to the development of the TM Sub-plan.
Ensuring all staff and contractors are provided with
induction regarding the importance traffic
management and ensuring that they know of agreed
management and mitigation strategies.
Ensuring those personnel who operate within close
proximity to roadways, access ways and private
access are fully briefed on the relevant requirements
of any approval conditions.
Respond to any complaints from the public in regard
to traffic related impacts.
Provide copies of road dilapidation reports to the
relevant road authority(ies).
construction
schedule
and
hours
of
construction;
Timing
At all times
Prior to
commencement of
construction
Prior to
commencement of
construction
Prior to
commencement of
construction
During
Construction.
Prior to
commencement and
after completion of
construction
Project Manager
Action No.
TM.PM.01
TM.PM.02
Management Procedure
Ensure that MCoA and Project Commitments are
adhered to when working in designated Project areas
to the satisfaction of the Project Environmental
Coordinator.
Notifying the Project Environmental Coordinator
before commencing any new phase of clearing or
construction works.
Timing
At all times.
Prior to works
TM.WC.02
TM.WC.03
TM.WC.04
TM.WC.05
TM.WC.06
Management Procedure
Ensure that MCoA and Project Commitments are
adhered to when working in designated Project areas
to the satisfaction of the Project Environmental
Coordinator.
Directions associated with the CEMP, the TM Subplan are adhered when working in designated Project
areas.
Notify RTA and complete Road Occupancy Form
prior to commencing any works affecting a road
which is part of the State Road Network
Notify in writing, the Ambulance Service of NSW of
any road closures that may impede ambulance access.
Notify NSW Fire Brigade stations affected by any
proposed road closures
Notify local residents prior to undertaking
construction works in their areas, where works may
affect access to particular residences.
Timing
At all times.
At all times
At least 10 days
prior to
commencing works
Prior to any road
closures
Fax one week prior
to any road closures
Prior to works
TM.SS.02
TM.SS.03
TM.SS.04
TM.SS.05
Management Procedure
Ensure approval has been given by the Project
Environmental Coordinator prior to undertaking any
works within known areas of concern with regard to
traffic and access.
Ensure that, unless otherwise approved by the DoP,
all works including construction, maintenance and
repair activities, and operational stage truck
movements that would generate an audible noise at
any sensitive receiver during the following hours:
a) 7:00 am to 6:00 pm, Mondays to Fridays, inclusive;
b) 8:00 am to 1:00 pm on Saturdays; and
c) at no time on Sundays or public holidays.
Minimise idling and queuing in local residential
streets and town centres.
Minimise the use of local roads (though residential
streets and town centres) to gain access to
construction sites.
Adhere to any nominated haulage routes identified in
the TM Sub-plan.
Timing
Prior to
commencement of
works
Prior to
commencement of
works
During
Construction.
During
Construction.
During
Construction.
TM.SS.06
TM.SS.07
TM.SS.08
TM.SS.09
TM.SS.10
TM.SS.11
TM.SS.12
TM.SS.13
PPM.SS.14
During
Construction.
Prior to
commencement and
after completion of
construction
Prior to
commencement of
works at Suffolk
Park Substation
As soon as
practicable
following
completion of
works
Prior to
commencement of
works
Prior to
commencement of
works
During
Construction.
At all times.
At all times
Management Procedure
Identify all work sites requiring a TCP in accordance
with the requirements TM Sup-plan.
TM.TC.02
TM.TC.03
TM.TC.04
TM.TC.05
TM.TC.06
Timing
Prior to
commencement of
works
Prior to
commencement of
works
At all times.
At all times.
At all times.
Prior to
commencement of
10
works
Construction Personnel
Action No.
TM.CP.01
TM.CP.02
TM.CP.03
Management Procedure
Personnel must take reasonable steps to manage and
control impact to roadways, road users and private
access.
Ensure approval has been given by the Project
Environmental Coordinator prior to undertaking any
works within known areas of concern with regard to
roadways and private access.
Being aware of the TMP and site specific TCP
requirements relevant to their work.
Timing
At all times
Prior to
commencement of
works
At all times
11
DoP
Country
Energy
Project
Manager
Country
Energy
ER
GHD
Construction
Work
Coordinator
Country
Energy
Construction
Site Supervisor
Project
Environmental
Coordinator
Country Energy
Traffic
Control Site
Supervisor
Consultants
Construction
Personnel
Figure 4.1
12
5.1
CONSTRUCTION PHASE
The EA (ERM 2009) identified potential environmental impacts associated
with the construction activities for the Project. These are summarised in Table
5.1 below.
Table 5.1
Potential Impact
Site establishment
and access
Installation of
overhead and
underground
transmission lines
(includes digging
and excavation of
trenches using
backhoe, import of
sand and cabling
and spoil spread,
removal and
reestablishment of
poles)
Road upgrades
Substation
upgrades and new
Substations
13
Table 5.2
Affected Roadway
Nearest Town
Significant
Infrastructure
Type of Work
to be
Conducted
Mullumbimby
Power station
existing
aboveground
easement
upgrade
Notification
Traffic Control
Method Required
Detour
possibilities
Traffic Impact
on Adjacent
Streets
Public
Transport
Route1
Pedestrian/cyclist
Route1
Mullumbimby to Ewingsdale
Adjacent to
Mullumbimby
Power Station
Access (off Wilsons
Creek Road)
Mullumbimby
14
Mullumbimby
Mullumbimby
Power station
Wilsons Creek
Road
Mullumbimby
Mullumbimby
Power station
Mullumbimby
residential
dwelling
existing
aboveground
easement
upgrade
existing
aboveground
easement
upgrade
existing
aboveground
easement
upgrade
resident
minimal - private
access ways
resident
minimal - private
access ways
access way to
the south may
be negotiated
for use if
required
access way for
house appears
to travel to both
Alidenes and
Wilsons Creek
Road
residents
along roadway
crossing of road
(partial/total closure)
resident
minimal - private
access ways
no
no
no
no
no
no
no
yes, Wilsons
Road is a
Connector
Road
no
no
no
no
no
no
Affected Roadway
Crossing of
Coolamon Scenic
Dr
Nearest Town
Significant
Infrastructure
15
Mullumbimby
residential
dwellings
Residential access
way
Mullumbimby
residential
dwelling
Myocum
residential
dwelling
Crossing of Dingo
Lane
Myocum
residential
dwellings
Myocum
residential
dwelling
Type of Work
to be
Conducted
existing
aboveground
easement
upgrade
existing
aboveground
easement
upgrade
existing
aboveground
easement
upgrade
existing
aboveground
easement
upgrade
existing
aboveground
easement
upgrade
Notification
Traffic Control
Method Required
Detour
possibilities
Traffic Impact
on Adjacent
Streets
Public
Transport
Route1
Pedestrian/cyclist
Route1
residents
along roadway
crossing of road
(partial/total closure)
no
Coolamon
Scenic Drive is
a connector
road so other
adjacent
streets will be
affected
resident
minimal - private
access ways
no
no
no
no
resident
minimal - private
access ways
no
no
no
residents
crossing of road
(partial/total closure)
no
no
Crossing will
affect a few
residents to
the south west
of Dingo lane
crossing
no
no
resident/land
owner
minimal - private
access ways
no
no
no
no
yes low
level
impact
Affected Roadway
Myocum Ridge
Road
Mullumbimby
Ewingsdale Road
16
Crossing of
Mullumbimby
Ewingsdale Road
Crossing of
Possum Shoot
Road
Nearest Town
Significant
Infrastructure
Type of Work
to be
Conducted
Notification
Traffic Control
Method Required
Detour
possibilities
Myocum
residential
dwelling
Myocum
residential
dwellings
existing
aboveground
easement
upgrade
existing
aboveground
easement
upgrade
residential
dwellings
existing
aboveground
easement
upgrade
residents
crossing of road
(partial/total closure)
no
residential
dwellings
existing
aboveground
easement
upgrade
residents
crossing of road
(partial/total closure)
no
Ewingsdale
Ewingsdale
residents
crossing of road
(partial/total closure)
residents
crossing of road
(partial/total closure)
no
no
Traffic Impact
on Adjacent
Streets
no
yes - Myocum
Road is a
connector road
yes, connector
road, residents
and road users
to the west
need to e
informed of
works and
possible
delays
yes, connector
road, residents
and road users
to the west
need to e
informed of
works and
possible
delays
Public
Transport
Route1
Pedestrian/cyclist
Route1
no
no
no
no
no
no
no
no
Affected Roadway
17
Within road
reserve of
Mullumbimby
Ewingsdale Road
Approximately 10
access ways within
Mullumbimby
Ewingsdale Road
reserve
Adjacent to Pacific
Highway
Crossing Pacific
Highway
Nearest Town
Ewingsdale
Significant
Infrastructure
residential
dwellings
Type of Work
to be
Conducted
existing
aboveground
easement
upgrade
Ewingsdale
residential
dwellings
Ewingsdale
Pacific
Highway
existing
aboveground
easement
upgrade
existing
aboveground
easement
upgrade
Pacific
Highway
existing
aboveground
easement
upgrade
Ewingsdale
Notification
residents
especially
where
crossing access
ways
residents
especially
where
crossing access
ways
RTA/Local
Council
RTA/Local
Council/local
and
widespread
road users
Traffic Control
Method Required
Detour
possibilities
Traffic Impact
on Adjacent
Streets
Public
Transport
Route1
Pedestrian/cyclist
Route1
working adjacent to
roadway/in road
reserve/crossing
access ways
no
yes, connector
road, residents
and road users
to the west
need to e
informed of
works and
possible
delays
minimal - private
access ways
no
no
no
no
no
no
yes low
level
impact
no
no
adjacent
streets may
have increased
traffic/delays
yes low
level
impact
no
working adjacent to
roadway/in road
reserve
crossing of road
(partial/total closure)
no
no
Affected Roadway
Crossing of
Ewingsdale off
ramp
18
Crossing of
Ewingsdale Road
Crossing of
William Flick Drive
Nearest Town
Ewingsdale
Ewingsdale
Ewingsdale
Significant
Infrastructure
Type of Work
to be
Conducted
near Pacific
Highway
existing
aboveground
easement
upgrade
existing above
ground
easement
upgrade
near Pacific
Highway
existing
aboveground
easement
upgrade
Pacific
Highway
Notification
RTA/Local
Council/local
and
widespread
road users
road users
RTA/Local
Council/local
and
widespread
road users
Traffic Control
Method Required
crossing of road
(partial/total closure)
crossing of road
(partial/total closure)
crossing of road
(partial/total closure)
Detour
possibilities
Traffic Impact
on Adjacent
Streets
no
more
intermittent,
highly
concentrated
flows of traffic
on Ewingsdale
Road due to
traffic controls
yes
Ewingsdale
Road is a
connector road
no
potential
delays on
Pacific
Highway
no
Public
Transport
Route1
Pedestrian/cyclist
Route1
yes low
level
impact
no
yes low
level
impact
no
yes low
level
impact
no
Affected Roadway
Working in road
reserve of Parkway
Drive
19
Crossing of
McGettigans Lane
Road reserve of
McGettigans Lane
(between Parkway
Drive and
Citriadora Drive)
Nearest Town
Ewingsdale
Ewingsdale
Ewingsdale
Significant
Infrastructure
residential
dwellings
residential
dwellings
residential
dwellings
Type of Work
to be
Conducted
Notification
underground
new easement
residents
underground
new easement
residents on
and to the
south of
McGettigans
Lane
underground
new easement
residents on
and to the
south of
McGettigans
Lane
Traffic Control
Method Required
Detour
possibilities
working adjacent to
road/in road reserve
yes - Parkway
Drive forms a
loop with
McGettigans
Lane
crossing of road
(partial/total closure)
yes - Parkway
Drive forms a
loop with
McGettigans
Lane
working adjacent to
road/in road reserve
yes - Parkway
Drive forms a
loop with
McGettigans
Lane
Traffic Impact
on Adjacent
Streets
traffic using
adjacent
streets to
avoid the
project works
may cause
minor increase
in traffic
numbers
traffic using
Parkway
Drive to avoid
the project
works may
cause minor
increase in
traffic
numbers
traffic using
Parkway
Drive to avoid
the project
works may
cause minor
increase in
traffic
numbers
Public
Transport
Route1
Pedestrian/cyclist
Route1
yes no
significant
impact
predicted
yes
yes low
level
impact
yes
yes no
significant
impact
predicted
yes
Affected Roadway
Working in Road
Reserve of
Citriadora Drive
20
Crossing of
Citriadora Drive
Crossing of Vista
Drive
Nearest Town
Ewingsdale
Significant
Infrastructure
residential
dwellings
Ewingsdale
dwellings
Ewingsdale
Byron Bay
dwellings
quarry nearby
but access
should be
unaffected
Byron Bay
residential
dwellings
Type of Work
to be
Conducted
underground
new easement
underground
new easement
underground
new easement
existing
aboveground
easement
upgrade
existing
aboveground
easement
upgrade
Notification
Traffic Control
Method Required
Detour
possibilities
Traffic Impact
on Adjacent
Streets
Public
Transport
Route1
Pedestrian/cyclist
Route1
no
no
no
Vista Drive
and Ivory Curl
Circuit traffic
will also be
affected by the
proposed
works
Vista Drive
and Ivory Curl
Circuit traffic
will also be
affected by the
proposed
works
no
no
no
no
no
no
minimal - private
access ways
no
no
no
no
working adjacent to
road/in road reserve
no
no
no
no
residents on
Citriadora
Drive, Ivory
Curl Circuit
and Vista
Drive
working adjacent to
road/in road reserve
residents on
Citriadora
Drive, Ivory
Curl Circuit
and Vista
Drive
residents on
Vista Drive
crossing of road
(partial/total closure)
crossing of road
(partial/total closure)
residents
residents
along skinners
shoot road
no
Affected Roadway
Crossing of Skinner
Shoot Road
21
Adjacent to Yagers
Lane
Skinners Shoot
Road
Yagers Lane
Nearest Town
Significant
Infrastructure
Byron Bay
residential
dwellings
Byron Bay
residential
dwellings/arti
st retreat
Byron Bay
Byron Bay
Type of Work
to be
Conducted
existing
aboveground
easement
upgrade
existing
aboveground
easement
upgrade and
in southern
section new
underground
easement
Public
Transport
Route1
Notification
residents
along skinners
shoot road
crossing of road
(partial/total closure)
no
no
no
no
residents
along Yagers
Lane
working adjacent to
road/in road reserve
no
no
no
no
no
yes Yagers
Lane
no
no
no
no
no
no
residential
dwellings
road upgrade
construction
activities
residents
along Skinners
Shoot Road
and Yagers
Lane and
Local Council
residential
dwellings
road upgrade
construction
activities
residents
along Yagers
Lane and
Local Council
Detour
possibilities
Traffic Impact
on Adjacent
Streets
Traffic Control
Method Required
Pedestrian/cyclist
Route1
Affected Roadway
Nearest Town
Significant
Infrastructure
Type of Work
to be
Conducted
Railway Line
existing
aboveground
easement
upgrade
Notification
Traffic Control
Method Required
Detour
possibilities
Traffic Impact
on Adjacent
Streets
Public
Transport
Route1
Pedestrian/cyclist
Route1
Byron Bay
22
Crossing of
Bangalow Road
Byron Bay
residential
dwellings
Crossing of
Coopers Shoot
Road
Suffolk Park
residential
dwellings
Crossing of Broken
Head Road
Suffolk Park
residential
dwellings
existing
aboveground
easement
upgrade
existing
aboveground
easement
upgrade
existing
aboveground
easement
upgrade
Australian
Rail Track
Corporation
crossing a railway
line
residents
along roadway
crossing of road
(partial/total closure)
no
residents
along roadway
crossing of road
(partial/total closure)
no
residents
along roadway
crossing of road
(partial/total closure)
no
no
no
yes Bangalow
Road is a
connector
road, many
residences
may be
effected by the
traffic
management
measures
roadways to
the east of
Coopers Shoot
Road
yes - Broken
Head Road is
a rural
collector road
currently
disused
no
yes low
level
impact
yes
no
no
no
no
Affected Roadway
Adjacent to Broken
Head Road to the
west
Adjacent to access
way off Broken
Head Lane
23
Crossing of access
way east of
Armstrong Lane
Nearest Town
Suffolk Park
Suffolk Park
Significant
Infrastructure
Type of Work
to be
Conducted
residential
dwellings
existing
aboveground
easement
upgrade
dwelling
existing
aboveground
easement
upgrade
Suffolk Park
dwelling
7km adjacent to
Newrybar Swamp
Road
Lennox Head
Dwellings,
Lennox Head
substation
Crossing Martins
Lane
Lennox Head
dwellings
existing
aboveground
easement
upgrade
existing
aboveground
easement
upgrade
existing
aboveground
easement
upgrade
Notification
Traffic Control
Method Required
Detour
possibilities
Traffic Impact
on Adjacent
Streets
Public
Transport
Route1
Pedestrian/cyclist
Route1
working adjacent to
road/in road reserve
no
yes - Broken
Head Road is
a rural
collector road
minimal - private
access ways
no
no
no
resident
crossing of road
(partial/total closure)
no
no
no
residents
working adjacent to
road/in road reserve
no
minimal
no
no
residents
crossing of road
(partial/total closure)
no
minimal
no
no
residents
along roadway
resident
no
no
Affected Roadway
Adjacent to Ross
Lane
24
Crossing of Ross
Lane
Nearest Town
Lennox Head
Lennox Head
Significant
Infrastructure
dwellings
residential
dwellings.
Ballina Shire
Council has
indicated that
the roadway is
a distributor
between
Lennox Head
and Lismore.
As such road
closure is
discouraged
and changed
conditions
would require
extensive
message sign
notification.
Type of Work
to be
Conducted
Notification
Traffic Control
Method Required
Detour
possibilities
Traffic Impact
on Adjacent
Streets
Public
Transport
Route1
Pedestrian/cyclist
Route1
existing
aboveground
easement
upgrade
residents
working adjacent to
road/in road reserve
no
minimal
no
no
existing
aboveground
easement
upgrade
residents
crossing of road
(partial/total closure)
no
minimal
no
no
Affected Roadway
Nearest Town
Significant
Infrastructure
Type of Work
to be
Conducted
existing
aboveground
easement
upgrade
existing
aboveground
easement
upgrade
25
Crossing of
Dufficys Lane
Lennox Head
Crossing of access
way twice
Ballina
residential
dwellings
Pacific
Highway
upgrade
location
Ballina
Pacific
Highway/loca
tion of the
Pacific
Highway
upgrade
existing
aboveground
easement
upgrade
near Pacific
Highway
existing
aboveground
easement
upgrade
Cross Pacific
Highway
Cross Old
Bangalow Road in
road reserve of
Pacific Highway
Ballina
Notification
Traffic Control
Method Required
Detour
possibilities
Traffic Impact
on Adjacent
Streets
Public
Transport
Route1
Pedestrian/cyclist
Route1
residents
crossing of road
(partial/total closure)
no
minimal
no
no
resident
minimal - private
access ways
no
no
no
no
RTA/Local
council RTA
and road users
crossing of road
(partial/total closure)
no
yes low
level
impact
no
residents
crossing of road
(partial/total closure)
no
yes low
level
impact
no
no
no
Affected Roadway
Nearest Town
Significant
Infrastructure
Type of Work
to be
Conducted
Adjacent to
Cumbalum Road
Ballina
dwellings
Crossing
Cumbalum Road
twice
Ballina
dwellings
existing
aboveground
easement
upgrade
existing
aboveground
easement
upgrade
26
Adjacent to Pacific
Highway
Ballina
Ballina
Ballina
Notification
Traffic Control
Method Required
Detour
possibilities
Traffic Impact
on Adjacent
Streets
Public
Transport
Route1
Pedestrian/cyclist
Route1
residents
working adjacent to
road/in road reserve
no
no
no
no
residents
crossing of road
(partial/total closure)
no
no
no
Pacific
Highway
existing
aboveground
easement
upgrade
RTA/Local
council and
road users
crossing of road
(partial/total closure)
yes low
level
impact
yes
Pacific
Highway
existing
aboveground
easement
upgrade
RTA/Local
council and
road users
working adjacent to
road/in road reserve
no
yes - could
cause delays
on highway
and adjoining
streets
yes - could
cause delays
on highway
and adjoining
streets
yes no
significant
impact
predicted
yes
Pacific
Highway
existing
aboveground
easement
upgrade
RTA/Local
council and
road users
crossing of road
(partial/total closure)
yes low
level
impact
yes
yes
yes
yes
yes
Affected Roadway
Crossing Gallans
Road
27
Adjacent to Pacific
Highway
Significant
Infrastructure
Type of Work
to be
Conducted
Dwellings
existing
aboveground
easement
upgrade
residential
dwellings
crossing of road
(partial/total closure)
Ballina
Pacific
Highway
existing
aboveground
easement
upgrade
RTA/Local
council and
road users
crossing of road
(partial/total closure)
Ballina
Pacific
Highway
RTA/Local
council and
road users
working adjacent to
road/in road reserve
crossing of road
(partial/total closure)
no
local council
crossing of road
(partial/total closure)
residents
working adjacent to
road/in road reserve
Nearest Town
Ballina
Crossing Canal
Road
Ballina
Crossing Fishery
Creek Road
Ballina
Ballina
Substation
sewage works
at end of
Fishery Creek
Road
Adjacent to
Barlows Road
Ballina
dwellings
new
aboveground
easement
existing
aboveground
easement
upgrade
existing
aboveground
easement
upgrade
new above
ground
easement
Notification
Traffic Control
Method Required
Detour
possibilities
no
Traffic Impact
on Adjacent
Streets
traffic may
bypass the
works by
using the loop
road network
yes - could
cause delays
on highway
and adjoining
streets
yes - could
cause delays
on highway
and adjoining
streets
Public
Transport
Route1
Pedestrian/cyclist
Route1
no
no
yes low
level
impact
no
yes low
level
impact
no
no
yes
no
no
no
no
no
minimal
no
no
yes
yes
Affected Roadway
Crossing Barlows
Road
Crossing Teven
Road
Crossing access
way off the Pacific
Highway
Nearest Town
Ballina
West Ballina
West Ballina
28
Adjacent Pacific
Highway
West Ballina
Crossing of access
way off Bruxner
Highway
West Ballina
Crossing
Westbridge Lane
Alstonville
Significant
Infrastructure
dwellings
dwellings
dwelling?
Pacific and
Bruxner
highways - no
dwellings are
apparent in
this section
Bruxner
Highway
Bruxner
Highway and
a few
dwellings
Type of Work
to be
Conducted
new above
ground
easement
existing
aboveground
easement
upgrade
existing
aboveground
easement
upgrade
existing
aboveground
easement
upgrade
existing
aboveground
easement
upgrade
new above
ground
easement
Notification
Traffic Control
Method Required
residents
crossing of road
(partial/total closure)
residents
crossing of road
(partial/total closure)
crossing of road
(partial/total closure)
Detour
possibilities
Public
Transport
Route1
Pedestrian/cyclist
Route1
no
no
no
no
yes
yes low
level
impact
no
no
no
no
no
working adjacent to
road/in road reserve
no
yes, delays
may cause
backlog on
Bruxner
Highway
no
no
resident
minimal - private
access ways
no
no
no
no
residents
along
Roadway
crossing of road
(partial/total closure)
no
minimal
no
no
resident
road users
(doesn't
appear to be
any dwellings
along this
section)
no
Traffic Impact
on Adjacent
Streets
Nearest Town
Significant
Infrastructure
Alstonville
Bruxner
Highway and
a few
dwellings
Crossing
Teakwood Drive
Alstonville
Near Bruxner
Highway
Affected Roadway
29
Crossing of
Bruxner Highway
In the road reserve
adjacent to the
Bruxner Highway
Crossing residents
access ways
Crossing Wardell
Road (in two
locations)
Alstonville
Bruxner
Highway
Alstonville
Bruxner
Highway
Alstonville
near Bruxner
Highway
Alstonville
Alstonville
substation
Type of Work
to be
Conducted
existing
aboveground
easement
upgrade
existing
aboveground
easement
upgrade
existing
aboveground
easement
upgrade
existing
aboveground
easement
upgrade
existing
aboveground
easement
upgrade
new above
ground
easements
Detour
possibilities
Traffic Impact
on Adjacent
Streets
Public
Transport
Route1
Notification
Traffic Control
Method Required
residents
along roadway
crossing of road
(partial/total closure)
no
minimal
no
no
residents
along roadway
crossing of road
(partial/total closure)
no
minimal
may cause
delays along
the Bruxner
Highway
no
no
RTA/Local
council and
road users
crossing of road
(partial/total closure)
RTA/Local
council and
road users
working adjacent to
road/in road reserve
resident
minimal - private
access ways
no
possible to
reroute traffic
through
adjacent
paddocks
road users
crossing of road
(partial/total closure)
no
no
no
no
yes Wardell
road is a
connector road
yes low
level
impact
yes no
significant
impact
predicted
Pedestrian/cyclist
Route1
no
no
no
no
no
no
Affected Roadway
Nearest Town
Significant
Infrastructure
Type of Work
to be
Conducted
30
Adjacent to Grays
Lane
Alstonville
Alstonville
substation
Crossing of Grays
Lane
Alstonville
Alstonville
substation
existing
aboveground
easement
upgrade
existing
aboveground
easement
upgrade
dwellings
existing
aboveground
easement
upgrade
Notification
Traffic Control
Method Required
Detour
possibilities
Traffic Impact
on Adjacent
Streets
Public
Transport
Route1
Pedestrian/cyclist
Route1
resident
working adjacent to
road/in road reserve
no
no
no
no
resident
crossing of road
(partial/total closure)
no
no
no
no
residents
working adjacent to
road/in road reserve
no
no
no
yes, use of
loop roads
may cause
minor increase
in traffic
no
no
no
no
no
Adjacent to Ellis
Road
Alstonville
Crossing of Red
Lane
Alstonville
dwellings
Crossing of Access
way off Ellis Road
Alstonville
dwelling
existing
aboveground
easement
upgrade
existing
aboveground
easement
upgrade
residents
crossing of road
(partial/total closure)
no
yes, loop road is
formed with
Rous Lynwood
Road, Beesons
Road and Ellis
Road
residents
minimal - private
access ways
no
Affected Roadway
Nearest Town
Significant
Infrastructure
Crossing of
Beesons Road
Alstonville
dwellings
Crossing of Access
way off Ellis Road
Alstonville
dwelling
Type of Work
to be
Conducted
existing
aboveground
easement
upgrade
existing
aboveground
easement
upgrade
31
Crossing of
Dalwood Road
Alstonville
dwellings
Crossing of Mollys
Grass Road
Lismore
dwellings
existing
aboveground
easement
upgrade
existing
aboveground
easement
upgrade
dwellings
existing
aboveground
easement
upgrade
Crossing of
Tregeagle Road
Lismore
Traffic Control
Method Required
Detour
possibilities
Traffic Impact
on Adjacent
Streets
residents
crossing of road
(partial/total closure)
yes, use of
loop roads
may cause
minor increase
in traffic
resident
minimal - private
access ways
no
may cause
minor increase
in traffic
volume using
surrounding
network
no
yes, Tregeagle
Road is
connected to
several roads
to the south
Notification
resident
crossing of road
(partial/total closure)
no
yes, loop road is
formed with
Rous Lynwood
Road, Beesons
Road and Ellis
Road
residents
along roadway
crossing of road
(partial/total closure)
no
residents
along roadway
and network
to the south
crossing of road
(partial/total closure)
no
Public
Transport
Route1
Pedestrian/cyclist
Route1
no
no
no
no
no
no
no
no
no
no
Affected Roadway
Nearest Town
Significant
Infrastructure
Crossing of Connor
Road
Lismore
dwellings
Crossing of Muller
Road
Lismore
dwellings
Type of Work
to be
Conducted
existing
aboveground
easement
upgrade
existing
aboveground
easement
upgrade
Detour
possibilities
Traffic Impact
on Adjacent
Streets
Public
Transport
Route1
32
Notification
Traffic Control
Method Required
Pedestrian/cyclist
Route1
residents
along roadway
crossing of road
(partial/total closure)
no
no
no
no
residents
along roadway
crossing of road
(partial/total closure)
no
no
no
no
residents
along roadway
crossing of road
(partial/total closure)
no
no
no
no
resident
crossing of road
(partial/total closure)
no
no
no
no
residents
crossing of road
(partial/total closure)
no
yes Wyrallah
Road is a
connector road
no
no
Lismore
dwellings
Crossing of Donlon
Road
Lismore
dwelling
dwellings,
south of the
Lismore
Landfill and
sewage
treatment
plant
Crossing of
Wyrallah Road
Lismore
existing
aboveground
easement
upgrade
existing
aboveground
easement
upgrade
existing
aboveground
easement
upgrade
Affected Roadway
Nearest Town
Significant
Infrastructure
Type of Work
to be
Conducted
33
Adjacent to
Monaltrie Drive
Lismore
dwelling
crossing of access
way off Monaltrie
Drive
Lismore
dwelling
Crossing of East
Gundurimba Drive
Lismore
dwellings
existing
aboveground
easement
upgrade
existing
aboveground
easement
upgrade
existing
aboveground
easement
upgrade
Crossing of
Bruxner Highway
Crossing access
way west of the
Bruxner Highway
Notification
Traffic Control
Method Required
Detour
possibilities
Traffic Impact
on Adjacent
Streets
Public
Transport
Route1
Pedestrian/cyclist
Route1
residents
working adjacent to
road/in road reserve
no
minimal
no
no
resident
crossing of road
(partial/total closure)
no
no
no
residents
along roadway
crossing of road
(partial/total closure)
no
no
no
Lismore
Bruxner
Highway
existing
aboveground
easement
upgrade
RTA/Local
council and
road users
crossing of road
(partial/total closure)
no
yes East
Gundurimba
Road is a
connector road
yes may cause
delays along
the Bruxner
Highway
causing delays
on adjacent
streets
yes low
level
impact
no
Lismore
Bruxner
Highway/Dw
elling
existing
aboveground
easement
upgrade
resident
minimal - private
access way
no
no
no
residents may
be able to travel
through
paddocks to
avoid works
locations
no
Affected Roadway
Nearest Town
Significant
Infrastructure
Adjacent to the
access way to the
west of the Bruxner
Highway
Lismore
Bruxner
Highway/Dw
elling
Crossing Muldoon
Road
Lismore
dwellings
34
Crossing Caniaba
Road
Lismore
dwellings
Type of Work
to be
Conducted
existing
aboveground
easement
upgrade
existing
aboveground
easement
upgrade
existing
aboveground
easement
upgrade
Notification
Traffic Control
Method Required
Detour
possibilities
Traffic Impact
on Adjacent
Streets
Public
Transport
Route1
Pedestrian/cyclist
Route1
resident
minimal - private
access way
residents may
be able to travel
through
paddocks to
avoid works
locations
residents
along roadway
crossing of road
(partial/total closure)
no
no
no
no
residents
along roadway
crossing of road
(partial/total closure)
no
yes, Caniaba
Road is a
connector road
no
no
no
no
no
no
no
no
Adjacent to East
Gundurimba Road
Lismore
dwellings
Crossing of East
Gundurimba Road
Lismore
dwellings
existing
aboveground
easement
upgrade
existing
aboveground
easement
upgrade
residents
along roadway
working adjacent to
road/in road reserve
no
residents
along roadway
crossing of road
(partial/total closure)
no
yes East
Gundurimba
Road is a
connector road
yes East
Gundurimba
Road is a
connector road
Affected Roadway
Crossing of
Wyrallah Road
35
Crossing of
Wyrallah Road
Type of Work
to be
Conducted
Nearest Town
Significant
Infrastructure
Lismore
dwellings/se
wage
treatment
plant/Lismore
Landfill
new
underground
easement
Local Council
and road users
crossing of road
(partial/total closure)
no
Lismore
dwellings/se
wage
treatment
plant/Lismore
Landfill
existing line
realignment
Local Council
and road users
crossing of road
(partial/total closure)
no
Notification
Traffic Control
Method Required
Detour
possibilities
Traffic Impact
on Adjacent
Streets
yes, several
roads
connected to
Wyrallah
Road to the
south
yes, several
roads
connected to
Wyrallah
Road to the
south
Public
Transport
Route1
Pedestrian/cyclist
Route1
no
no
no
no
1.
Clarification of whether the road is used for public transport and/or has a high cyclist and pedestrian traffic rate will be determined on-site and appropriate TCPs implemented upon
determination
2.
Should total road closure be necessary, the duration of the road closure will be less than fifteen minutes. This is sufficient time for the construction team to locate the line in the
necessary location and allow the roadway to reopen, with works continuing in the road reserve.
AN
K
TO
RL
R
NS
NE
W
ES
N
S CE
RD
ON
LAM
COO
K RD
PA
ST
R
LA G OON D
A N K RD
TH
F
LO
RD
TS
MYOC U
DG
RI
DINGO L
L BI L I
PO
SS
U
SE RD
C OO
LA
MO
M SHOO T RD
AN
N RD
T HE M
MC A ULE Y S
L
ES
MYOCU
M ST
C UM DOW NS DR
M YO
R
IC D
L EFT B
AZAL
RD
HA
S CR E E
KR
N
WILS O
O LLUM R
D
ERR
Y
B AN
NI
C
DR
RD
OLD
FIC
RA
YS L
Ewingsdale ZS
BAYSID
YS L
NG SDA
PA
CI
T AND
MU LLU
MB I MBY EW
I
NN ED
H
G AR A
TY A
L E RD
Brunswick Heads ZS
FRIDAY HU
Map section reproduced with permission of UBD. Universal Publishers Pty Ltd 06/07
DEPARTMENT OF LANDS www.lands.nsw.gov.au
GOO NENG
NTEC
Mullumbimby ZS
MO
FT
RD
LE
MULLUMBIMBY
AN ST
D
SR
MA
NN
TIN COG
DR
WY
D
AN G
KO
CR
RD
E
EE
K
EE
ST
PL
G
AR
E
YL
RA
NB
A
H
PACIFIC
JA
WY
KE
Y
SA
EA
TH
E
E
RSID
RIVE
PATH
SC
T RD
Lismore to Mullumbimby
Electricty Network Upgrade
Project:
1,300
1,950m
Reviewed by: MC
Drawing size: A4
Maps and figures contained within this document may be based on third
party data, may not be to scale and is intended for use as a guide only.
ERM does not warrant the accuracy of any such maps or figures.
650
Scale:
TH
Drawn by:
[
N
20/12/2009
Date:
Country Energy
Client:
Figure 5.1
Project Interaction with Road Network
- Mullumbimby to Ewingsdale
Substation Lot
Built Up Area
Drainage
Casino-Murwillumbah Railway
NSW Roadways
Legend
PACIFIC HWY
ST
HE
AR
DR
LE N
IO N
AY
DR
RI
SE
BAY
R
V I S TA D
A
L RA
IT H L
SU
N
CITRIADORA DR
Map section reproduced with permission of UBD. Universal Publishers Pty Ltd 06/07
DEPARTMENT OF LANDS www.lands.nsw.gov.au
A NTAT
RR
YL
TAHRA C
ST
H EL
ENA
RD
RE DR
EWINGSDALE RD
G RE V I L L E
BAYSH
O
CA DR
MELA
LEU
QU
A
NS L
IGA
CG
ET
T
ST
A
N RIS
NE
EB
VD
RAYWARDS L
SK
I
SU
RS
SH
SL
YAGE
R
ST
B O RD E
EY S
T
I A BA C
SUFFOLK PARK
R
A K CC
W
LO
GA
N
BA
W
LO
RD
RD
BYRON BAY
SHIR
L
TI TR EE
RD
Suffolk Park ZS
IL
DE
ST
DO
N
BANKSIA
CH
OL
D
KEN
DAL
L ST
R
PA
AN
G
AN
RR Y L
TE
Q UA
ST
O
O
R
T
Lismore to Mullumbimby
Electricty Network Upgrade
Project:
700
1,050m
Reviewed by: MC
Drawing size: A4
Maps and figures contained within this document may be based on third
party data, may not be to scale and is intended for use as a guide only.
ERM does not warrant the accuracy of any such maps or figures.
350
Scale:
TH
Drawn by:
[
N
20/12/2009
Date:
Country Energy
Client:
Figure 5.2
Project Interaction with Road Network
- Ewingsdale to Suffolk Park
Substation Lot
Built Up Area
Drainage
Cadastral Boundaries
Casino-Murwillumbah Railway
NSW Roadways
Legend
RD
L EI
R
FE
GH
RD
BR
LER
LAW
SR
EN
ROSS L
T I NS
AR
PHI
LLIP
SR
D
OOT
RD
N HEAD R
SH
BRO K
E
CO
OP
ER
S
Lennox Head ZS
OL
WATSO
NS
OK
BR
RD
AD
HE
IGH R
FE
LE
HU
T
B ANG
OW
AL
KL
E
DUDG E
O NS L
RN
BANGALOW
PA C I F
IC H WY
D
CE
LE
VA
AR
RD
RO
G
BA N
O
AL
W RD
DR
T
A RMS
CLIFFOR
PAT
H
D ST
SUFFOLK PARK
NATURA
LL
LENNOX HEAD
C H DR
PAT
H
H
PAT
BYRON BAY
Suffolk Park ZS
BEE
RD
PL
CA
RN
E
AMP RD
YBAR S
W
BAY
FR
A
ID
B YRO
N
L
ON
G
RD
RD
A
IN
LL
BA
N EWR
RD
FIG TREE HI
LL
R
PRIO
Substation Lot
Built Up Area
Drainage
Casino-Murwillumbah Railway
NSW Roadways
Lismore to Mullumbimby
Electricty Network Upgrade
Project:
820
1,640
2,460m
Reviewed by: MC
Drawing size: A4
Maps and figures contained within this document may be based on third
party data, may not be to scale and is intended for use as a guide only.
ERM does not warrant the accuracy of any such maps or figures.
[
N
TH
Drawn by:
Scale:
20/12/2009
Date:
Country Energy
Client:
Figure 5.3
Project Interaction with Road Network
- Suffolk Park to Lennox Head
Legend
HU M
RD
XN
ER
H
R IF L E
M RD
N GA DR
HA
DA
VE
Y
BA
RD
TERS L
U R AL
LEADBE
AT
RD
GAP RD
NG
E
WE
E LT
HL
A
IN
NS R
BR
UX
NE R WY
H
TUC KOM
BIL L
TE V
HA
D
TI
MAJORS L
E
W
O
R
TH
N IX
OE
E RNL
PACIFIC
RD
SL
KER
STO
ER
LL
F
EIG
H
RD
LD
PA
C IF
I
G A L OW R
K O ELLNE
BA
N
EAST ST
HWY ITH DR
SM
IM
LIC O
DOU JE
A RD
Alstonville ZS
GRAYS L
RA
ALSTONVILLE
PATH
WY ALBERT ST
ELLIS R
D
BR
U
WOLLONGBAR
S
TH
Y
PT
SN
EA
C
BA
RD
CR E
EK
ES
PEAR C
ES L
BYR
N
RD
TEVEN
RD
CROSBY L
RD
RD
D ELL
D
RR
ND
G
S
RIVE
E DR
ROSS L
FO
X
SL
ST
Lismore to Mullumbimby
Electricty Network Upgrade
Project:
770
1,540
2,310m
Reviewed by: MC
Drawing size: A4
Maps and figures contained within this document may be based on third
party data, may not be to scale and is intended for use as a guide only.
ERM does not warrant the accuracy of any such maps or figures.
Scale:
[
N
TH
20/12/2009
Drawn by:
Date:
Country Energy
Client:
Figure 5.4
Project Interaction with Road Network
- Lennox Head to Alstonville
Built Up Area
Substation Lot
Drainage
Casino-Murwillumbah Railway
NSW Roadways
Legend
RSID
SL
Ballina ZS
EAST BALLINA
ZO
W
Y SAN DY FL A T
DUFFICY
Lennox Head ZS
RD
W AR
RD
TEVE
N
SHAWS
NT
EN
D
R
R
BA
R
PH
GE L
UG
EN
V
TE
TEVEN
R
DR
WESTBR
ID
H
HOR I
C
AL
N
LA
CO
RK
R
PE
PI
RD
LA
HIL
LC
R
SS RD
"
)
BURGESS ST
W IL
AP
NO
RD
PL
ER
D
Map section reproduced with permission of UBD. Universal Publishers Pty Ltd 06/07
DEPARTMENT OF LANDS www.lands.nsw.gov.au
LIS R D
GOONELLABAH
AV
OLIVER
O N D H IL L
KAR
STAR AV ISSA DR
P I ND
LISMORE
RA
ES
TA
V
NG
RD
JUBIL
EE AV
SK
YLINE
RD
ON R
HENS
KAD INA
ST
ST
CL
HIL
LTO
P
CONN O
R RD C
O
HM
AL
HOLLA
ND
RIDGEL
A ND CL
PH AD
A LE
RI
C
TR
ROUS RD
K
UC
NO NS R D
IVER A
V
OL
ER
D
EG
EA
G
M C KI N
L I ND
EN
LO
DA
LE
W
CO
BALLINA
R
RD
RD
RO
RD
RD
NG
LE
ELLIS R
D
AN
OD
US
HUMPTY
BR
U
BAC K RD
CONVE
RYS L
C H ES W
WEIS L
O
Y N W O D RD
SL
R OU
HS
D
R
PA
AV
GRAYS L
ALSTONVILLE
RD
SPROULE DR
URALBA RD
)
Alstonville ZS "
WHITES
L
RD
E
AN G
LE R
RIF
SN E A T
WOLLONGBAR
O RTHS L
S RD
R
D
BEESO
N
OW
AL
NG
A
B
RED L
A YS L
RI CR
T AYLO RS
M
WO
AL
ELL R
TRACK
WAR D
SR
ME
JA
EEK
R
N
Y
S CR
PI
R
GE S
HW
PEAR
CE
G
RID
XN
ER
RD
Lismore to Mullumbimby
Electricty Network Upgrade
Project:
1,380
2,070m
Reviewed by: MC
Drawing size: A4
Maps and figures contained within this document may be based on third
party data, may not be to scale and is intended for use as a guide only.
ERM does not warrant the accuracy of any such maps or figures.
690
Scale:
TH
Drawn by:
[
N
20/12/2009
Date:
Country Energy
Client:
Figure 5.5
Project Interaction with Road Network
- Alstonville to East Lismore
Substation
Built Up Area
Drainage
Casino-Murwillumbah Railway
NSW Roadways
Legend
N RD
AB
C A NI
SNOW ST
HAIN R
D
S RD
TT
O
C
BAR
KE
SO
U
ST
YP
OIN
STA
LL
S
TH
TU
N
RS
T
SA
ND
ST
TREVANS R
TR
WO
O
DL
AR
K
ST
WILSON ST
T DR
ON
MONALT
R
CIT
Y
FL O
R AL ST
MAGEL
LAN
ST
T
ROTA
N
VIE TE
S
W
DR T
ST
IE L
SKYLINE
R
ER
RIV
BAN
KR
DONLO
N RD
RC
ER
KELLAS S
T
DURHEIM
RD
TULKS
R
Lismore Uni ZS
"
)
FO
AIR
DALLEY
LISMORE
ST
SS
RY DR
WANDA DR
BE AUM
PATH
EDEN S
T
EW
IN
URALBA
ORION
S
GS
T
ST
BALLIN
A ST
JA
T
ME
SPRING
S S E S YT H S
JOHN S
BRIGHT ST
T
T
ST
O
NI
Lismore South ZS
"
)
COOK S
T
RHODES ST
CANIAB
A RD
THR EE
C
KYOGLE ST
LISMORE
ST
SNOW S
T
JOHNSO
N RD
H
O RT
CASINO
C
IL
Map section reproduced with permission of UBD. Universal Publishers Pty Ltd 06/07
DEPARTMENT OF LANDS www.lands.nsw.gov.au
N O RTO
Lismore BSP
AR
MULDOON RD
BA RD
CANIA
T
TAYLO
RS
H
PAT
H
TT
C
O
NE
R
RD
BRU
X
DIBBS
ST
HU
RL
EY
ST
NIELS
ON ST
C LLE
O
GE ST
PAUN E
LLE AV
O
R
PA
TH
WILSO
N ST
KI ST
BA
CORA
M
O
LE
SW
O
R
K
TH
E
EN
ST
ST
DA
W
SO
N
ST
G
ST
EA
R IM
DU
UN
WY
BRUXNER HWY
ST
BAR H
AM
E DR
RE
E R ST
CH
FIS
AR
Y DR
BAL
LIN
TRINIT
ER
CA
UL
D
R
D
CLIFF
ORD S
T
ER ST
HUNT
CO
A R ST
HABIB DR
T
WYRA
LLAH R
D
G
FI
CED
ST
INV
Y
W
AH
LL
RA
DS
ST
ET D
SKYLIN
ER
GH
HI
S
SUN
ST
Lismore to Mullumbimby
Electricty Network Upgrade
Project:
920
1,380m
Reviewed by: MC
Drawing size: A4
Maps and figures contained within this document may be based on third
party data, may not be to scale and is intended for use as a guide only.
ERM does not warrant the accuracy of any such maps or figures.
460
Scale:
TH
Drawn by:
[
N
20/12/2009
Date:
Country Energy
Client:
Figure 5.6
Project Interaction with Road Network
- East Lismore to Lismore
Drainage
Built Up Area
Substation
Casino-Murwillumbah Railway
NSW Roadways
Legend
5.2
5.3
42
5.4
43
Table 5.3
Location
Alstonville
Ballina
Ballina
Ballina
Ballina
Ballina
Lennox Head
Lennox Head
Suffolk Park
Suffolk Park
Suffolk Park
Suffolk Park
Suffolk Park
Ewingsdale
Mullumbimby
Mullumbimby
Mullumbimby
Mullumbimby
Mullumbimby
44
work vehicles;
shadow vehicles;
tail vehicles; and
advance warning vehicles.
Lead vehicles
The lead vehicle travels in front of the work vehicle for the following
purposes:
to warn oncoming traffic of the work/heavy vehicle; and
the driver is able to alert the remaining convoy and workers of any
potential hazards posed by on-coming traffic.
The lead vehicle is not required on very low volume rural roads where speeds
are less than 80km/hr and sight distance is less than 2D*m or on urban
residential, collector or commercial streets where speeds are generally lower
than 60km/hr.
* D is the speed of traffic approaching the work site measured in km/hr or the speed limit applying to the
road, whichever is greater. The symbol D is used with an appropriate factor to indicate the distance
between two objects.
Work Vehicle
A work vehicle is the vehicle that is undertaking the work. In this project this
refers to the low loader transporting the transformer.
Shadow Vehicle
The shadow vehicle follows slowly behind the work vehicle as it progresses.
Its main purpose is to protect workers that may be outside of the work vehicle
from passing traffic. This vehicle usually travels approximately 20m to 40m
behind the work vehicle.
Tail Vehicle
The tail vehicle travels some distance behind the work vehicle for the purpose
of:
45
46
required to deliver the personnel to the project sites each day, concentrated in
the early morning and late afternoon. Depending on location of the
transmission line upgrades and vicinity to local towns, there may occasionally
be an additional 1 -2 trips for refreshments, lunches or collection of any
required equipment.
The concrete trucks will originate from local suppliers. The tipper trucks will
be similarly sourced from local suppliers and will deliver sand to partially
backfill trenches in locations where underground line is to be installed.
During the trenching activities, approximately five tipper trucks will be
required per day to supply sand.
The larger vehicles and earthmoving equipment have the potential to become
a hazard due to their slow acceleration and deceleration rates, so caution must
be exercised in planning these larger vehicles movements. Heavy vehicles are
only to travel on roads deemed appropriate to accommodate their mass and
dimensions.
5.5
5.5.1
47
The installation of the transformers may require the total or partial closure of
roadways adjoining the substation access ways which will require suitably
qualified traffic controllers, and adherence to the traffic management
principles for stopping and/or merging traffic. The protocols for heavy
vehicle movements stated above are to be followed during the transport of the
transformers. The operation of installing the transformers may require the
total or partial closure of the roadways directly adjacent to the substations.
These roadways are listed below:
Ewingsdale Road;
Newrybar Swamp Road;
Grays Lane; and
Temple Street.
The rural location of the Ewingsdale Road, Newrybar Swamp Road and Grays
Lane will mean that only minor volumes of traffic are likely to be impacted by
the partial/total road closures. Temple Street is located in a built up area of
Ballina, however the connectivity of the road network provides numerous
detour opportunities. Detours are discussed in Table 6.1.
Following completion of construction activities, the substation would generate
very little traffic. Access to the facility would be at irregular intervals and
generally be light vehicle traffic during day time hours. Such traffic
movements would not have a significant impact on the level of service or
capacity of the local road systems.
5.5.2
48
49
5.6
50
Several locations along the project area route require transmission line to be
traversed across roadways. This is the operation that will cause the most
significant traffic management procedures to be implemented should the
closure of the roadway and the stopping of traffic be required to complete the
installation. The stopping or merging of traffic has specific management
requirements that are related to the type of vehicles utilising the roadway and
the level of service of the roadway that is to be traversed and is described
further in Section 6.1.
The most significant of the roadway crossings are those of the Bruxner and
Pacific Highway. Ballina Shire Council identified that there is currently no
option for detours along the Bruxner Highway and the Highway conveys 15
000 vehicles/day. The Pacific Highway conveys 18 000 to 23 000 vehicles/day
and has two detour points in the vicinity of the project. Ross Lane/The Coast
Road and Teven Road Tintenbar Road provide a possible detour should total
road closure of the Pacific Highway be required. Ballina Shire Council is
reluctant to implement lane changes on either highway without a
comprehensive vehicle management plan being prepared and approved. Any
alteration to traffic movements on the Highways proposed by the project
requires the concurrence of the NSW RTA.
Where trenches for underground line installations are to be constructed,
partial road closures will be implemented to allow for continued road use,
allowing vehicle movements from both directions. Roadways where partial
road closures will be required due to underground transmission line
installation are:
McGettigans Lane;
Citriadora Drive;
Vista Drive; and
Yagers Lane.
5.7
51
5.8
5.8.1
Access Ways
There are to be several transmission line installations across property access
ways throughout the length of the project. The line crossings are considered
to cause minimal traffic disturbance as only the resident will be affected.
Despite the minimal traffic impact predicted for these locations, planning and
consultation will be undertaken with affected landholders to maximise safety.
Consultation with affected residents will be undertaken prior to the
commencement of any construction works on property access ways.
Consultation with landholders may identify alternative access ways that can
be utilised to eliminate vehicles from approaching/entering the worksite and
as a consequence, minimise the likelihood for impacts.
Project works requiring transmission line to cross access ways do not affect a
large area and consequently can be completed in a short period of time.
Establishment of overhead transmission line and trenching activities to install
underground transmission line along any residential access ways are
predicted to take approximately one day to complete.
5.9
DETOURS
Limited opportunities for the use of detours were identified across the project
area. Potential detour locations were assessed on the design of the road
network being of appropriate layout to simply redirect traffic without adding
a significant distance or time to vehicle trips and accommodate the increase in
vehicle numbers.
52
5.10
ROAD CLOSURES
Any operations that may involve road closure will require a Traffic Control
Plan (TCP) which will be prepared in consultation with the affected Council
and the RTA. The contents of the TCP are described further in Table 6.1
Traffic Management Measures. Consultation requirements prior to any road
closures are included in Table 4.1 Roles and Responsibilities.
53
54
5.11
55
5.12
56
5.13
5.14
ALSTONVILLE BYPASS
The Alstonville Bypass is 6.2km of roadway between Alstonville and
Wollongbar. The bypass will commence at Sneaths Road Wollongbar and will
rejoin the Bruxner Highway at the Tropical Fruit Research Station at Perrys
Hill, east of Alstonville. Construction activities commenced in mid 2009 and
are continuing at present. The construction activities have the potential to
interact with the electricity upgrade project in the areas between Wardell
Road and Teven Road (See Figure 5.7). On-going consultation with the RTA
and relevant contractors prior to and throughout the project construction
works is recommended.
57
A
M
E DR
OP
LE
TA
ES
A DEL
PATH
BR OWN
AV
D E E G AN A V
PATH
DR
PATH
M ELL
AV
IS C
CT
A LS
TO N
R TSO N S
P AR KLA
BE
ND
ROP
DR
AT
ALSTONVILLE
H
Y ST
R
RA D
M
NA
MER A
KE
N
AI
M
PA
TH
O
SM
LI
RE
Map section reproduced with permission of UBD. Universal Publishers Pty Ltd 06/07
DEPARTMENT OF LANDS www.lands.nsw.gov.au
ELLIS R
D
PL
KYLA ST
ST
ST
DA
SOUTH
S
T
TANA
O
CO
AV
AD A P D E
TEVEN
RD
O C E AN V I E W
URALBA R
O
N TE
SCENIC
WY
DA R CT
DR
LLE
YD
R
BRU
XN
ER
H
VA
GAP R D
P A N O R A M A DR
N
RA
G
PATH
G R A YS L
CA
ASHLAN
D
COR AL
CL
ST
GREEN
W LE Y
AL
CR
WARD
ELL R
D
GO
A DR
MAN TU
LA PL
E
PD
OR
V
EN A
AN
D
BUG
IPPS AV
P
WH
CT
RD
TH
PA
Lismore to Mullumbimby
Electricty Network Upgrade
Project:
400
600m
Reviewed by: MC
Drawing size: A4
Maps and figures contained within this document may be based on third
party data, may not be to scale and is intended for use as a guide only.
ERM does not warrant the accuracy of any such maps or figures.
200
Scale:
TH
Drawn by:
[
N
29/03/2010
Date:
Country Energy
Client:
Figure 5.7
Project Interaction with Alstonville
Bypass
Source:
Alstonville Bypass Concept Plan - NSW RTA
Built Up Area
Drainage
Casino-Murwillumbah Railway
NSW Roadways
Substation Lot
Legend
59
Table 6.1
Environmental Issue
Management Strategy
60
Delays to traffic
To ensure minimum disruption and inconvenience to road users close only the
minimum length and width of a road that is absolutely necessary to undertake
the works in a safe manner at each stage of construction;
Minimise the use of local roads (through residential streets and town centres)
to gain access to construction sites;
Busy roads and central business districts will be avoided where possible to
minimise idling and queuing in local residential streets and town centres;
Adhere to haulage routes and road networks listed in Section 5.4.
In locations where a transmission line is to cross roadways, make all possible
attempts to safely install the line without closing the roadway.
Audible work at the nearest sensitive receiver is to be undertaken during the
approved construction times and programmed where necessary to ensure
minimum disruption to traffic especially during the following times:
peak times;
Saturdays;
school holidays; and
special events.
Road closures will only be short term up to a maximum of 15 minutes to allow
delivery of large plant items. In the case of Skinners Shoot Road and Yagars
Lane, road works will ensure a single lane is open for traffic movement under
traffic control. Access for emergency vehicles during short term road closure
will be established between Yagars Lane and Bangalow Road via an existing
private property access track in consultation with the relevant landowner.
Responsibility
Works Coordinator
Sub Plan/CE
Procedure
CEM2328 Traffic
Control: Safety
Environmental Issue
Management Strategy
61
Specific Traffic Control Plans (TCPs) will be prepared for all work which involves any
form of traffic control or restriction. TCPs will be prepared in accordance with the
requirements of the RTA (2003) Traffic Control at Work Sites. All necessary approvals
will be obtained from Council, RTA, emergency services and other relevant authorities
prior to implementing TCPs. Annex A provides an example of the TCPs that may be
required for the construction activities.
Responsibility
Works Coordinator
Sub Plan/CE
Procedure
CEM2328 Traffic
Control: Safety
Environmental Issue
Management Strategy
Responsibility
Sub Plan/CE
Procedure
62
Where the AADT is unavailable the following formula has been developed to provide
an estimate of the ADT. Over the course of five minutes, all vehicles travelling in both
directions are counted. The number of vehicles counted after the five minutes is then
multiplied by 12 (to provide the estimated number of vehicles/hour). This number is
then multiplied by 16 to provide the estimated ADT. The reasoning behind the
multiplication factor of 16 is that, in practice, most traffic is generated within the 16
hour period between 6.00am and 10.00pm.
Number of
vehicles
counted in 5
minutes
(travelling in
both directions)
192
(conversion factor
of 12 to get vehicles
per hour multiplied
by 16 hours for
vehicles per day)
Works Coordinator
CEM2328 Traffic
Control: Safety
Environmental Issue
Management Strategy
Responsibility
Sub Plan/CE
Procedure
63
If the entire work area, including all vehicles and plant, are 3m or more from the nearest
edge of the traffic carrying lane and no parking lanes, road shoulder or lane is required
to be closed, then the only signage required is a Worker (symbolic) (T1-5) forewarning
road users and vehicle mounted warning devices on all plant and vehicles on the work
site.
Works Coordinator
CEM2328 Traffic
Control: Safety
Environmental Issue
Management Strategy
Responsibility
Sub Plan/CE
Procedure
64
If there is clearance within 1.2 and 3m of traffic and no physical barriers the following
are required when the workers are on-site:
Works Coordinator
Signage and delineation (Worker (symbolic) (T1-5) and cones, bollards or
similar);
Containment fence around the edge of work area; and
Reduction of traffic speed to 60km/hr or less.
Working less than 1.2 metres from the nearest edge of the lane carrying traffic, the
following measures are to be undertaken:
CEM2328 Traffic
Control: Safety
Environmental Issue
Management Strategy
Responsibility
Sub Plan/CE
Procedure
65
Works Coordinator
CEM2328 Traffic
Control: Safety
Environmental Issue
Management Strategy
Responsibility
Sub Plan/CE
Procedure
66
An increased risk of rear end collisions arises in any location where road traffic is
stopped for a period of time. Ensuring that there is sufficient warning to road users
before encountering the queue is essential. Depending on the situation this may require
extending the length of a sign posted roadwork speed zone in the development of the
TCP, using oversized signs, flashing light signs and variable message signs.
Works Coordinator
CEM2328 Traffic
Control: Safety
Environmental Issue
Management Strategy
Responsibility
Sub Plan/CE
Procedure
Detours
Should detours be considered the best course of action in the locations mentioned in
Section 5.9, the following principles are to be considered:
67
All the roadways to be involved in the proposed detours are to be inspected to confirm
they are of sufficient structural strength, alignment and width to carry the vehicle types,
loads and volumes expected. Following the completion of the project works in locations
where detours have been used, Project Staff are to remove all local detours and reinstate
the pre-existing road network and access arrangement to the satisfaction of relevant
road authorities.
Works Coordinator
CEM2328 Traffic
Control: Safety
68
Environmental Issue
Management Strategy
Responsibility
Sub Plan/CE
Procedure
Signs
The type of signs that will be used for traffic management during the proposed line
upgrade activities will include:
Guide signs to show road users the correct path to follow (DETOUR,
PEDESTRIANS);
Regulatory signs indicating the laws that shall be obeyed (approval is required
for the erection of such a sign); and
Works Coordinator
CEM2328 Traffic
Control: Safety
Environmental Issue
Management Strategy
Responsibility
Sub Plan/CE
Procedure
Sign Sizing
The size of the sign to be used is dependant on the traffic volume and the approach
speed. The A-D classification is used to describe sign size with A being the smallest and
D being the largest. The final design of sign size is to be determined by the works
supervisor after assessment of the road conditions, approach speeds and traffic volume.
The following is a guide for use:
69
Size A signs designed for roads with low traffic volumes and low approach
speeds;
Size B signs- designed for use on roads with high traffic volumes and/or high
approach speeds;
Size C signs designed for use on freeways and other roads with approach
speeds greater than 100km/hr; and
Size D signs to be considered on roads where approach speeds are greater
than 100km/hr and the information to be communicated needs to be
emphasised or there is excessive lateral displacement of the sign.
Site conditions and constraints can influence the placement of signs around a proposed
works location. Hence, judgement will be required from on-site personnel to ensure the
signs are placed as close as possible to the spacing indicated on the TCP. Changes in
locations are to be documented with the details of the person making the changes.
Works Coordinator
CEM2328 Traffic
Control: Safety
70
Environmental Issue
Acoustic and
Amenity Impacts
Management Strategy
Responsibility
Sub Plan/CE
Procedure
The progressive nature of the transmission line upgrades will limit any acoustic and
amenity impacts in any one location. The maintenance of amenity will be a high
priority during the construction activities and have been considered in the design of this
traffic management plan.
In accordance with Condition 2.1 of the Project Approval, the Proponent shall only
undertake construction, maintenance and repair activities, and operational stage truck
movements that would generate an audible noise at any sensitive receiver during the
following hours:
Works Coordinator
CEM2328 Traffic
Control: Safety and
CEM7022.05 Noise
and Vibration
Protocols.
Environmental Issue
71
Provisions for
Emergency Vehicles,
Heavy Vehicles,
Cyclists and
Pedestrians
Management Strategy
Emergency Incidents
As per recommendations in RTA (2003), in the event of an emergency incident the
following general procedures will be adopted:
The works crew is to stop work and activate all flashing lights;
Immediately begin warning other road users in the safest means possible;
Use an appropriate TCP and use traffic controllers and signage where
necessary; and
Responsibility
Works Coordinator
Sub Plan/CE
Procedure
CEM2328 Traffic
Control: Safety
Environmental Issue
Management Strategy
Responsibility
Sub Plan/CE
Procedure
Heavy Vehicles
The following provisions are to be applied to the movement of heavy vehicles across the
site:
72
Provisions for
Emergency Vehicles,
Heavy Vehicles,
Cyclists and
Pedestrians
Heavy vehicle movements are to occur outside of peak traffic conditions where
possible;
Heavy vehicle drivers are to abide by the construction vehicle code of conduct
(see Section 8.3);
Heavy vehicles will use local roads only when absolutely necessary;
Heavy vehicle movements will be restricted to roadways of sufficient design
and capacity to accommodate the vehicles movements and weight (a haulage
route comprised of the major roads to most likely to be used for construction
traffic is Shown in Figures 5.1 to 5.6) unless absolutely necessary; and
The RTA, local council and local police will be notified before the
commencement of heavy vehicle movements.
Works Coordinator
CEM2328 Traffic
Control: Safety
Environmental Issue
73
Provisions for
Emergency Vehicles,
Heavy Vehicles,
Cyclists and
Pedestrians
Management Strategy
Responsibility
Works Coordinator
Sub Plan/CE
Procedure
CEM2328 Traffic
Control: Safety
6.1
6.1.1
Highways
Highways are arterial roads that carry predominately through traffic from one
region to another. They provide the principal avenue for traffic movements
and are at the top of the road hierarchy (RTA, 2000).
The traversing of transmission lines across the Pacific and Bruxner Highway is
the project activity that has the potential to delay a significant amount of road
users. Extensive consultation must be undertaken with the RTA, local council,
local police and surrounding businesses and residents (as necessary) to
formulate an effective TCP. Following consultation with aforementioned
parties, a process of notification must be engaged to warn road users of the
project works and potential delays. The notification method must be
widespread and include several different media in order to inform not only
ENVIRONMENTAL RESOURCES MANAGEMENT AUSTRALIA
74
the local road users but also road users originating from outside the local area.
This may include radio broadcasts, newspaper articles in regional
newspapers, notification on the RTA website and variable message road signs.
Traffic on Highways consists of a mix of vehicle types ranging from small
vehicles through to heavy vehicles and oversize load carrying vehicles. This
mix of traffic must be considered in the development of the TCP to ensure that
warning signage is sufficient to meet the expected queue lengths of stopped
vehicles. An additional queue length of 10% is recommended by RTA (2003)
to cater for extra vehicles.
An increased risk of rear end collisions arises in any location where road
traffic is stopped for a period of time. Ensuring that there is sufficient
warning to road users before encountering the queue is essential.
6.1.2
Collector/Sub-arterial Roads
Sub-arterial roads are roads connecting to arterial roads to areas of
development and carrying traffic directly from one part of a region to another
(RTA 2000). Collector roads collect and distribute traffic in an area in addition
to serving abutting properties (RTA 2000). Transmission line traversing sub
arterial and collector roads has the potential to not only effect local road users
but also road users from outside the immediate vicinity of the roadway.
Consultation will be undertaken with the local council and surrounding
businesses and residents (as necessary) to formulate an effective TCP. The
notification process will be similar to that for a highway but with a more
concentrated focus on notifying the surrounding region. As a courtesy, local
police may also be notified on particularly busy roadways.
A mix of traffic can be expected on sub-arterial roads but to lesser extent and
with less larger vehicles than on highways, and lesser again on collector roads.
This will be considered in the development of the TCP.
An increased risk of rear end collisions arises in any location where road
traffic is stopped for a period of time. Ensuring that there is sufficient
warning to road users before encountering the queue is essential.
6.1.3
Local Roads
Local roads are used primarily for access to abutting properties (RTA 2000).
Local roads are predominately serviced by small vehicles and depending on
the length of the roadway and number of residential dwellings attached,
usually have a low volume of traffic.
75
Access Roads
Several accessways are to be traversed by the transmission line in both rural
and residential localities. Access roads are characterised by very low traffic
volumes, with vehicle types dominated by smaller vehicles. Notification is
limited to the resident/landholder of the property and is best achieved by
verbal communications to determine the most suitable method of traffic
control. Verbal communications may identify alternative options for access
for vehicles, thus eliminating vehicles from approaching the project area.
Assessing the level and times of service (assumed to peak at business hours
when residents are travelling to and from work) for accessways with
landholders may identify timeframes most suitable to carry out the project
works without causing delay to residents.
Trenching activities along Parkway Drive access ways are predicted to only
take approximately one day per accessway to complete.
6.2
76
prepared in accordance with the requirements of the RTA (2003) Traffic Control
at Work Sites. All necessary approvals will be obtained from Council, RTA,
emergency services and other relevant authorities prior to implementing
TCPs. Annex A provides example TCPs relevant to the closing of traffic lanes
to be undertaken.
6.3
6.4
STAKEHOLDER CONSULTATION
Consultation with relevant Local Councils, NSW RTA and emergency service
providers has been undertaken throughout the planning process of the project
and the development of this Sub-plan. Copies of the main framework CEMP
and this Traffic Management Sub-plan were distributed to the aforementioned
parties for comment. The relevant parties that were consulted and the status
of response received are listed in Table 6.2.
Table 6.2
Stakeholder Consultation
Group
City
Contact
Ambulance Service
of New South
Wales
Glenn Eady
Lismore
NSW Police
Service
Rob Clarke
Lismore
NSW Police
Service
Sergeant Johnson
Ballina
NSW Police
Service
Doug Connors
Byron Bay
Documents
Sent
Traffic
Management
Sub-Plan and
framework
CEMP
Traffic
Management
Sub-Plan and
framework
CEMP
Traffic
Management
Sub-Plan and
framework
CEMP
Traffic
Management
Sub-Plan and
framework
Response
Comments
received
Comments
received
Comments
received
Comments yet to
be received
77
Group
City
Contact
Fraser Hindrie
Lismore
To Whom it may
concern
Sydney South
Lismore City
Council
Darren Patch
Lismore
Ballina Shire
Council
Damon Jones
Ballina
Byron Shire
Council
Phil Holoway
Mullumbimby
RTA Grafton
Tammy Tribe
Grafton
Documents
Sent
CEMP
Traffic
Management
Sub-Plan and
framework
CEMP
Traffic
Management
Sub-Plan and
framework
CEMP
Traffic
Management
Sub-Plan and
framework
CEMP
Traffic
Management
Sub-Plan and
framework
CEMP
Traffic
Management
Sub-Plan and
framework
CEMP
Traffic
Management
Sub-Plan and
framework
CEMP
Response
Comments
received
Comments yet to
be received
No edits
recommended
Comments
received
Comments
received
Comments
received
Note: Following distribution of the reports ERM contacted the parties in the form of emails and
telephone calls, where available, to receive progress updates on the review by each group.
Responses received from these parties have been incorporated into the
preparation of this Traffic Management Sub-Plan as outlined in Consultation
Response Matrix in Annex C. Should responses be received following the
approval of this Sub-plan, all reasonable and feasible comments will be
incorporated into a revised Sub-plan.
In relation to those responses received from emergency services, all generally
requested that site specific management plans, including any road closures, be
provided prior to undertaking works to ensure alternative accesses are
confirmed.
78
79
80
8.1
SITE INSPECTIONS
As required by the CEMP, weekly inspections of construction work areas will
be conducted by the Project Environmental Coordinator or their
representative and Environmental Representative (when on-site) to monitor
work practices and identify non-conforming areas and activities or work
practices which could lead to potential impact to road users. It is noted that as
the Project is to be constructed in stages there are expected periods of minimal
to no construction activity where the regularity of inspections may need to be
revised down accordingly.
Where a non-compliance with nominated performance goals is detected
TotalSafe Notice will be raised by the Project Environmental Coordinator as
outlined in the CEMP.
8.2
81
Location
Alstonville
Ballina
Ballina
Ballina
Ballina
Lennox Head
Lennox Head
Suffolk Park
Suffolk Park
Suffolk Park
Suffolk Park
Suffolk Park
Suffolk Park
Ewingsdale
Ewingsdale
Ewingsdale
Ewingsdale
Mullumbimby
Mullumbimby
Mullumbimby
Mullumbimby
Mullumbimby
These reports are then to be supplied to the relevant road authority(ies). Any
damage caused to the road or footpaths, aside form that of normal wear and
tear shall be repaired by Country Energy. The damaged infrastructure is to be
repaired to a standard at least equivalent to that existing prior to the damage
and to the satisfaction of the relevant road authority(ies). Photographs are a
useful form of evidence that assist in comparison of the road conditions before
and after the project activities.
82
8.3
83
8.4
REPORTING
8.4.1
8.4.2
Reporting
Environmental monitoring will be reported quarterly in accordance with the
Project CEMP, Country Energys CEM7022 Environmental Operations Manual
and Country Energys Procedures.
Records shall be kept during the implementation and review of this Sub-Plan
with a copy kept at the Project site or in a suitable location and subsequently
for five years after the completion of the Project.
Country Energy procedure CEPG1060 Records Management will be
implemented during the implementation of this Sub-Plan.
84
Annex A
CE-IN-CONFIDENCE
Procedural Guideline:
Guideline (Internal)
Traffic Control: Safety
CEPG2328
In Plain English
CHECK that this printed document is the most recent version before you use it.
Accredited Service Providers: comply with Country Energy policies, state acts and
regulations.
23 JUNE 2008
ORIGINAL ISSUE
CE-IN-CONFIDENCE
UNCONTROLLED COPY IF PRINTED
CE-IN-CONFIDENCE
CEPG2328
Summary
This document provides information for Country Energy employees regarding their responsibilities and
requirements for traffic control on worksites. Traffic control is required where road conditions are different
because of work being done by Country Energy including lane closures, roadwork speed zones, detours, and
shoulder closures.
Responsibilities
RGM
GGM
GM
Contacts
Position
Extension number
8853
8178
CE-IN-CONFIDENCE
CE-IN-CONFIDENCE
CEPG2328
CONTENTS PAGE
1
INTRODUCTION ...................................................................................................................................... 4
CHALLENGES ......................................................................................................................................... 5
THE PROCEDURES................................................................................................................................. 5
4.1
4.2
Methods ................................................................................................................................................7
4.3
Unplanned work....................................................................................................................................8
4.4
4.5
Surveying ..............................................................................................................................................9
4.6
4.7
Pedestrians........................................................................................................................................ 10
4.8
4.9
Traffic controllers............................................................................................................................... 11
4.10
Notification ........................................................................................................................................ 11
4.11
4.12
4.13
4.14
4.15
4.16
Training .............................................................................................................................................. 15
4.17
4.18
4.19
4.20
4.21
Auditing .............................................................................................................................................. 15
4.22
Record keeping.................................................................................................................................. 15
4.23
4.24
4.25
TCP 2: Working a Minimum 3 Metres or More from the Nearest Traffic Lane.............................. 18
4.26
4.27
4.28
TCP 5: Work Impending on the Nearest Traffic Lane but Maintaining a Minimum 3.2 Metres to Centre Line 60
KM/HR or Less .................................................................................................................................. 21
4.29
TCP 6: Worksite not Maintaining a Minimum 3.2 Metres to Centre Line 60 KM/HR or Less... 22
4.30
4.31
4.32
TCP 9: 2 Lane / 2 Way Close One Using One Traffic Controller 60 KM/HR or Less .............. 25
4.33
TCP 10: 2 Lane/2 Way - Close One Using Two Traffic Controller 60 KM/HR or Less................ 26
4.34
REFERENCES .......................................................................................................................................28
REVISIONS ...........................................................................................................................................28
CE-IN-CONFIDENCE
CE-IN-CONFIDENCE
1
CEPG2328
INTRODUCTION
The RTA manual Traffic Control at Worksites Manual (www.rta.nsw.gov.au), outlines the processes
and responsibilities for traffic control at work sites and must be used in conjunction with this
procedure when working on RTA roads..
The AS 1742.3 Manual of uniform traffic devices Traffic Control devices for works on roads,
outlines the minimum processes and responsibilities for traffic control.
This procedure is to be used in conjunction with AS 1742.3 for non RTA roads and refers to work
conducted within the boundaries of all roads.
compliance with the regulatory requirements for traffic control at our worksites
The RTA, Traffic Control at Work Sites Manual makes reference to specific levels of authority and
uses specific terms for these positions. Where this position is stated in the Traffic Control at Work
Sites Manual, the following will apply to Country Energy.
BE responsible for compliance with the traffic control plans adopted for the work site
ENSURE that any employee appointed to the role of nominated traffic control site supervisor
has the appropriate RTA qualification for traffic control management
PERFORM inspections before work starts, during the works and pre-closedown of the site
CHECK periodically that all signs and devices are satisfactory and in their correct position
CONSULT with any contractors that maybe conducting traffic control at our worksite on our
behalf.
CE-IN-CONFIDENCE
CE-IN-CONFIDENCE
CEPG2328
ENSURE all personnel required for traffic control are trained and authorised
ENSURE that any incident that occurs and corrective action specified is taken and is recorded
via the WIN system.
ENSURE that a traffic control safety audit is carried out on a regular basis, on a selected shortterm work site via an approved checklist and that the date, time and deficiencies or non
conformances are raised via the WIN system
ENSURE that any corrective action specified is taken and recorded via the WIN system.
RGM, GGM, GM
Are responsible for ensuring that adequate resources are available to maintain appropriate traffic
control measures on all worksites. Where this is not realistic; management must ensure that
suitable contractual arrangements are made with contractors to perform this task.
CHALLENGES
To ensure that the implementation of traffic control, and traffic control measures are adequate for
each work site.
THE PROCEDURES
Traffic control may be required when conducting any trade related work within the confines of the
road reserve; the road reserve is defined as the area from a boundary fence to the opposing
boundary fence.
Signs and devices will be used to warn, inform and guide road users safely around, past or through
work areas, including providing a safe and convenient path for pedestrians through or past the work
site.
When setting up traffic control measures at Country Energy work sites the following broad principles
shall be complied with:
1
BEFORE setting up any traffic control or starting work, a risk assessment of the worksite will be
undertaken to determine what degree of traffic control is required. The selected TCP must be
included in the space provided and any additional hazards identified and documented on the
HIRAC form.
ENSURE all personnel responsible for Traffic Control are qualified in RTA approved training
courses. Traffic controllers will be used where required.
ARRANGE traffic control so that workers are able to work safely and the workers and road
users are effectively separated wherever possible.
ALWAYS have an escape route in mind in case of an emergency, such as an out of control
vehicle.
CLOSE the minimum length and width of a road at each stage to ensure minimum disruption
and inconvenience to road users, ensuring road users do not unnecessarily break the law.
CE-IN-CONFIDENCE
CE-IN-CONFIDENCE
CEPG2328
ENSURE signage is placed at the correct distance as per the TCP, preferably by the use of a
measuring wheel.
PLACE signs and devices before work begins, making sure the signs are not a hazard to
workers, pedestrians and road users and are set up at least 1 metre from the fog line. Ensure
they are clearly visible and are not obscured by vegetation, vehicles, plant or other signs and
devices and are displayed in the correct sequence.
ALWAYS set up traffic control signage in the order of the most distant sign from the worksite
first, making your way back to the worksite and always remove signs in the reverse direction.
ENSURE signage is secure and can not be knocked or blown over, sand bags may be needed
on the stand of the signs to secure them.
10
11
DO NOT park plant or vehicles on both sides of the road unless absolutely necessary.
12
ALWAYS confine the work to inside the traffic controlled area, especially when operating an
EWP, the booms must stay inside the delineated area and not encroach over the road way or
in the path of traffic.
13
STAGE work to ensure minimum disruption to traffic especially at peak times, nights,
weekends, and holidays and during special events.
14
ENSURE all employees who are conducting work on the road reserve wear a high visibility
yellow shirt or where high visibility yellow blends in with the environment (eg: canola fields)
then high visibility orange vests are required.
15
INFORM the team leader of any unexpected events that result in excessive lengths of queues
or delays.
16
COMPLETE a WIN for any incident that may occur on the worksite.
When working on or near roads or traffic it is imperative that a safe work place is consistently
maintained.
4.1
CALCULATIONS
ESTIMATED ADT
> 1500
> 1000 but 1500
> 1000 but 1500
> 300 but 1000
> 300 but 1000
> 300 but 1000
> 300 but 1000
< 300
CE-IN-CONFIDENCE
CE-IN-CONFIDENCE
4.2
Methods
4.2.1
CEPG2328
When working within the road reserve, the location may make it necessary to control traffic flow at
that worksite. Conduct a risk assessment to assist in determining the level of traffic control that is
required.
4.2.2
Approaching traffic can see the vehicle mounted warning device for at least 150 metres in a
60 km/h or less speed zone or 250 metres if the speed limit is greater than 60 km/h
Traffic can pass the worksite safely without crossing double lines or impeding on the work area
Signage or vehicle mounted warning devices are not obstructed in any way by a raised truck
body or overhanging vegetation etc
The worksites width allows a safe passage for two way traffic around it.
You must post a spotter on the ground to warn other workers of the approach of pedestrians and any
vehicle whose size or speed might be a threat to their safety.
4.2.3
ENSURE approaching traffic can see the vehicle mounted warning device for at least 150
metres in a 60 km/h or less speed zone or 250 metres if the speed limit is greater than 60
km/h
CONSIDER the need for a spotter to warn workers conducting work of the approaching traffic
In the direction of traffic flow to the work site the signs NEXT 2 KM and a worker (symbolic) or
power line works in progress sign shall be placed.
If the above requirements can not be met then the site shall be set up requiring full traffic control
with advance signs and devices.
4.2.4
CE-IN-CONFIDENCE
CE-IN-CONFIDENCE
4.2.5
CEPG2328
4.2.6
NOTE: Some worksites may require additional traffic control signage; refer to the appropriate TCP, in
the RTA manual Traffic Control at Worksites.
4.3
Unplanned work
For unplanned work such as - removing a fallen service off the road, no traffic control maybe
required, however the following shall apply:
x
A spotter shall stay within sight and hearing distance to the workers, and there is no
approaching traffic for at least a minimum distance equal to 10 seconds travelling time or
6Dm
Workers undertaking unplanned intermittent work are able to substantiate that the work was
unplanned and was required urgently
CE-IN-CONFIDENCE
CE-IN-CONFIDENCE
CEPG2328
WITH A SPOTTER
WITHOUT A SPOTTER
60
90
120
150
180
210
240
270
300
330
120
180
240
300
360
420
480
540
600
660
APPROACH SPEED
Up to 100 km/hr
4.4
Where poles, plant or equipment that may be a hazard are left on site, a suitable barrier shall
be erected around the item to prevent any unauthorised access to the item by non Country
Energy employees
ENSURE the site is safe for pedestrian and vehicle movement around the site
Note: Meshing or barriers used where required should have a Country Energy logo on them.
4.5
Surveying
For surveying work on the roadside, between the reverse boundary and the nearest road shoulder,
and all survey employees are wearing high visibility clothing, then traffic control signage will not
generally be required for such work, but if requiring movement from one side of the road to the other
then extreme caution should be taken.
If the above conditions can not be met than full traffic control is required.
CE-IN-CONFIDENCE
CE-IN-CONFIDENCE
4.6
CEPG2328
4.7
Pedestrians
When working on a worksite that requires temporary provisions for pedestrians the following is
considered:
x
The needs of older pedestrians, pedestrians with disabilities and school children
When undertaking work that requires the closure of pedestrian footpaths, you must provide a safe
and convenient path for pedestrians through or past your worksite. When doing this the path should:
x
Where it is not appropriate or allowable to have any alternate / temporary pedestrian footpath, then
a spotter must be used to inform workers on the approach of pedestrians to cease work, while the
spotter escorts the pedestrian/s through or around the worksite.
When diverting pedestrians near or onto the roadway close to traffic, a mesh fence may be used, if:
x
The path is at least 1.2 metres away from the traffic lane and the speed limit is less then
60km/h or
If the above conditions are not met then fully certified traffic safety barriers must be used.
4.8
Working at Night
When working at night and traffic control is required the following must be met:
x
WEAR high visibility clothing (not just traffic controllers), preferably retro-reflective
ENSURE when setting up cones and bollards, decrease their spacing, and make sure they
have retro reflective bands
LIGHT the work site with flood lighting, if this is not practicable, consider lighting up the
position of the traffic controller/s
BEWARE of the road users behaviour (speed, fatigue, vision, substance abuse).
CE-IN-CONFIDENCE
CE-IN-CONFIDENCE
4.9
CEPG2328
Traffic controllers
Traffic Controllers are required on both short and long term work where traffic needs to be
periodically stopped at the approach to a work site. In addition they maybe required to:
x
Slow down or stop traffic that may need to travel through or around the work site
Each entry to the work site is visible from the other end, and
Ensure traffic controllers are certified and correctly dressed in high visibility clothing, and are
informed of any special requirements relating to the worksite. Traffic controllers should be relieved
after no more than 2 hrs and given a break from traffic control for no less than 15 minutes.
4.10
Notification
When conducting a task on the worksite that requires traffic control, (that will significantly disrupt the
flow of traffic or speed limit changes are required), notification to and authorisation must be
obtained from the RTA or the local council before work can commence. Consultation with the local
council will be required as not all councils follow the same process.
4.11
4.12
CE-IN-CONFIDENCE
CE-IN-CONFIDENCE
4.13
CEPG2328
Use either fluorescent traffic cones that are at least 450 mm high for most low speed urban
and rural roads and 700mm high for freeways and high speed applications or fluorescent
plastic bollards at least 700 mm high and 100mm in diameter
RECOMMENDED MAXIMUM
APPROACH SPEED
< 60 km/hr
60 80 km/hr
15
>80 km/hr
24
60 80 km/hr
12
>80 km/hr
15
60 - 80 km/hr
12
>80 km/hr
15
60 80 km/hr
15
>80 km/hr
24
On centreline in advance of
taper with traffic control
All
Merge tapers
60-80 km/hr
>80 km/hr
12
SPACING, M
Depending on traffic flow and conditions, cone and bollard spacings may need to be reduced and
taper lengths may need to be increased to maintain a safe worksite.
CE-IN-CONFIDENCE
CE-IN-CONFIDENCE
CEPG2328
TRAFFIC CONTROL AT
LATERAL SHIFT
MERGE TAPER
BEGINNING OF TAPER
TAPER
Less than 45
30
30
65
45 - 54
30
30
80
55 - 64
30
60
95
65 - 74
30 ( at signals )
70
115
75 - 84
30 ( at signals )
80
130
85 - 94
N/A
90
145
95 105
N/A
100
160
N/A
110
180
NOTE: Always place the cones or bollards in smooth lines so that they look like the edge of a traffic
path. Be prepared to replace any that are knocked out of line.
4.14
All Country Energy work vehicles should have a vehicle mounted warning device
The device should be either a rotating amber light or an illuminated flashing arrow sign.
Always use them when the vehicle is parked at the work site and ensure that the vehicle is in the
best place to highlight the work site. You must lower or remove the vehicle mounted signs or switch
off rotating amber light etc, before driving away from the job and into the traffic stream.
4.15
Additional signs
You may need additional signs as per the TCP which may include, but not limited to:
x
Pedestrian sign
CE-IN-CONFIDENCE
CE-IN-CONFIDENCE
CEPG2328
Always make sure that the signs are placed the full required distance in advance of the work site.
When setting up a work site with traffic control always refer to the table below to determine the
spacings of signs.
Recommended Maximum Spacing of Cones and Bollards
RECOMMENDED MAXIMUM
APPROACH SPEED
< 60 km/hr
60 80 km/hr
15
>80 km/hr
24
60 80 km/hr
12
>80 km/hr
15
60 - 80 km/hr
12
>80 km/hr
15
60 80 km/hr
15
>80 km/hr
24
All
60-80 km/hr
>80 km/hr
12
On centreline in advance of
taper with traffic control
Merge tapers
SPACING, M
CE-IN-CONFIDENCE
CE-IN-CONFIDENCE
4.16
CEPG2328
Training
Traffic control and the selection or design of TCPs must only be undertaken by persons who are
qualified, authorised and have passed RTA approved training courses. The training of personnel will
be an integral part of the implementation of this document.
4.17
4.18
4.19
4.20
This course is for employees required to set up and work with TCP issued to them by
Supervisors, Line Managers or others as qualified
This course instructs participants in how to set out and remove TCPs and control any on-site
hazards
This course is for employees required to select and make minor modifications to standard
TCPs to suit the work locations, i.e. Works Supervisors, Team Leaders and others etc
It does NOT allow the person to design a new TCP or to Audit Traffic Control Plans on a road
construction site.
4.21
This course is for employees required to control traffic at a work site, by using STOP/SLOW
(R6-8/T7-1) bats in accordance with an approved TCP.
This course is for staff required to design new Traffic Control Plans or produce major upgrades
of standard plans and/or staff that will be required to Audit TCPs on any worksite.
Auditing
A traffic control safety audit is a structured procedure whereby an independent and suitably qualified
person uses a checklist to review and report on the selection, design and implementation of TCPs.
Traffic control auditing will be conducted by members of the Safety Team, who are qualified under
section 4 of this procedure. The audit process will be completed by using an approved inspection
checklist on a regular basis.
All work sites may be subject to traffic control safety audits including sites where traffic control is
undertaken by contractors.
4.22
Record keeping
It is a requirement to maintain and store HIRAC and auditing information relating to traffic control.
All records are to be kept in accordance with CEPG1060 Records Management. All records shall
be kept for 1 year at FSC then archived for 2 years. If there has been an incident then records shall
be kept for 7 years, as per CECG1000 Safety Health and Environmental Management.
NOTE: In the case of incidents either witnessed or reported or involving the public or from which
legal proceedings might arise, the actual type, size and location of signs, and devices in use at the
time of the incident should be recorded and the sign arrangement photographed for subsequent
reporting via the WIN system.
CE-IN-CONFIDENCE
CE-IN-CONFIDENCE
4.23
CEPG2328
DIAGRAM
NUMBER
NAME
T1-5
Worker symbolic
T1-1
Roadwork Ahead
T2-16
End of Roadwork
T1-200
T1-28
Next 2KM
T1-18
Prepare to Stop
T2-6-1
Lane Closed
T5-5 R
T5-5 L
R4-212
R4-225
R4-1
Speed Zone
Flashing Arrows
Worksite
CE-IN-CONFIDENCE
CE-IN-CONFIDENCE
TCP 1: Working on Shoulder No Interruption to Traffic Flow 60 KM/HR or less
Shoulder
2DM
30
30
4.24
CEPG2328
TCP 1
CREATED BY:
JOHN
OREILLY
CE-IN-CONFIDENCE
CE-IN-CONFIDENCE
TCP 2: Working a Minimum 3 Metres or More from the Nearest Traffic Lane
Shoulder
2 DM
4.25
CEPG2328
TCP 2
CREATED BY:
JOHN
OREILLLY
CE-IN-CONFIDENCE
CE-IN-CONFIDENCE
4.26
CEPG2328
Shoulder
SPOTTER
UNPLANNED WORK
THE SPOTTER MUST MAINTAIN MINIMUM SIGHT DISTANCES AS PER TABLE 2
ATTACHMENT B ROTATING LIGHTS REQUIRED
TCP 3
CREATED BY:
JOHN
0REILLY
CE-IN-CONFIDENCE
CE-IN-CONFIDENCE
TCP 4: Frequently Changing Work Areas
Shoulder
MAX 2KM
4.27
CEPG2328
TCP 4
CREATED BY:
JOHN
OREILLLY
CE-IN-CONFIDENCE
CE-IN-CONFIDENCE
TCP 5: Work Impending on the Nearest Traffic Lane but Maintaining a Minimum 3.2
Metres to Centre Line 60 KM/HR or Less
DM
4.28
CEPG2328
Shoulder
2 DM
30
30
3.2
WORK IMPEDING ON THE NEAREST TRAFFIC LANE BUT MAINTAINING A MINIMUM 3.2
METRES TO CENTRE LINE 60KM/HR or LESS
A RISK ASSESSMENT IS TO BE CONDUCTED TO DETERMINE TRAFFIC CONTROL
REQUIREMENTS ROTATING LIGHTS REQUIRED
TCP 5
CREATED BY:
JOHN
OREILLY
CE-IN-CONFIDENCE
CE-IN-CONFIDENCE
4.29
CEPG2328
TCP 6: Worksite not Maintaining a Minimum 3.2 Metres to Centre Line 60 KM/HR or
Less
30 M
DM
2 DM
Shoulder
2 DM
DM
TCP 6
CREATED BY:
JOHN
OREILLY
CE-IN-CONFIDENCE
CE-IN-CONFIDENCE
4.30
CEPG2328
FOOTPATH
Min 6.5 or
3.2 MTR
TCP 7
CREATED BY:
JOHN
OREILLY
CE-IN-CONFIDENCE
CE-IN-CONFIDENCE
4.31
CEPG2328
0.5
Shoulder
10 m
20
95
0.5 DM
TCP 8
CREATED BY:
JOHN
OREILLY
CE-IN-CONFIDENCE
CE-IN-CONFIDENCE
4.32
CEPG2328
TCP 9: 2 Lane / 2 Way Close One Using One Traffic Controller 60 KM/HR or Less
2 DM
Shoulder
0.5
0.5
2 DM
30 M
30 M
DM
2 LANE / 2 WAY - CLOSE ONE USING ONE TRAFFIC CONTROLLER 60KM/HR or LESS
FOR USE WHERE ADT IS LESS THAN 1500 VEHICLES PER DAY AND MINIMUM SIGHT
DISTANCE ON UNOBSTUCTED LANE AS PER TABLE 3 IN ATTACHMENT B --ROTATING LIGHTS
REQUIRED
TCP 9
CREATED BY:
JOHN
OREILLY
CE-IN-CONFIDENCE
CE-IN-CONFIDENCE
4.33
CEPG2328
TCP 10: 2 Lane/2 Way - Close One Using Two Traffic Controller 60 KM/HR or Less
0.5 DM
0.5 DM
2 DM
Shoulder
0.5 DM
0.5 DM
2 DM
30 M
30 M
30M
2 LANE / 2 WAY - CLOSE ONE USING TWO TRAFFIC CONTROLLER 60KM/HR or LESS
FOR USE WHERE THE ADT IS LESS THAN 6OOO VEHICLES PER DAY
ROTATING LIGHTS REQUIRED
TCP 10
CREATED BY:
JOHN
OREILLLY
CE-IN-CONFIDENCE
CE-IN-CONFIDENCE
TCP 11: 4 Lane/2 Way - Closing One Lane 60 KM/HR or Less
Shoulder
0.5
2 DM
MERGE
TAPER
30 M
DM
4.34
CEPG2328
TCP 11
CREATED BY:
JOHN
OREILLY
CE-IN-CONFIDENCE
CE-IN-CONFIDENCE
5
CEPG2328
REFERENCES
CECG1000 Safety, health and Environment Management
CEFD6281 Safety and Environment Field Audit Report
CEPG1060 Record Management
RTA Traffic control at work sites - current edition
Standards Australia Field guide for Traffic control at works on roads - Current edition
Roads (General) Regulations
Dm Approach speed in metres eg: 60km/hr approach speed equals a Dm of 60 metres, or 2Dm
will equal 120 metres.
FOG LINE Outer line or edge of the lane nearest the shoulder of the road.
HIRAC Country Energys method for documenting and recording Hazard Identification, Risk
Assessment and Control measures.
Long-term work Is work requiring traffic control or pedestrian control but taking more than one
work shift where some form of control must remain in place when the site is unattended.
Road Reserve - The area from a boundary fence to the opposing boundary fence in any direction RTA
Roads and Traffic Authority.
Site Supervisor - A person, who has taken responsibility to ensure adequate traffic control on the
work site, has been implemented.
Short-term work - Is work requiring traffic control or pedestrian control but taking less than or equal
to one shift.
TCP Traffic Control Plan.
TRADE RELATED All work and visitations associated with the trades of Lineworker, Electrical
Technician, Cable Jointer, Vegetation Management, Survey Work, Metal Fabrication, Mechanical
Repairs/Maintenance, Building, Spray Painting, Gas Technicians, Gas fitters, Storeman and Water
Technicians and Water / Sewer Workers.
UNPLANNED WORK Unscheduled work or emergency work.
Worksite - The specific area within the road reserve where construction or maintenance work is to be
conducted, this also include the areas where plant and vehicles are positioned.
REVISIONS
Issue Number
Section
CE-IN-CONFIDENCE
Annex B
1
Pre
Start
2
Pre
Close
Pre
Start
3
Pre
Close
Pre
Close
4
Pre
Start
Pre
Close
Pre
Start
Signs and
devices:
Traffic Signals
time operational
Appr No
Temp Speed
time operational
Appr No
Speed (km/h)
Supervisors
Initials:
To
To
To
To
To
To
To
To
SITE 1
SITE 2
SITE 3
SITE 4
September 2003
Issue 1
E-5
Pre
Start
Pre
Close
Pre
Start
Pre
Close
Pre
Close
Pre
Start
Pre
Close
Pre
Start
Traffic Signals
time operational
To
To
To
To
To
To
To
To
Appr No
Temp Speed
time operational
Appr No
Speed (km/h)
Supervisors
Initials:
COMMENTS:
E-6
September 2003
Issue 1
Annex C
Stakeholder Consultation
Correspondence
Concern/Comment
Response
Group/Agency
Correspondence
Concern/Comment
Response
Lismore Shire
Council
Ballina Shire
Council
Group/Agency
Correspondence
Concern/Comment
Response
Group/Agency
Correspondence
Concern/Comment
detour route for the Pacific Highway.
As Ross Lane has elevated hierarchical status any road closure
would be strongly discouraged and any change of traffic
conditions to Ross Lane requires extensive variable message
sign notification.
Pacific Highway
The Pacific Highway within Ballina Shire has very little option
for detour should total closure be applied. I seek to advise you
that both Council and the RTA are reticent to implement any
lane or full closures of the Pacific Highway without a
comprehensive vehicle management plan being submitted for
consideration. Please note that submission of such a plan does
not predicate an approval.
The Pacific Highway has only two detour points. The first is
Ross Lane Coast Road and the second is Teven Tintebar
Road. The latter has a right turn ban for south bound vehicles
at the Teven Road/Pacific Highway intersection and has load
limits on two existing bridges.
Please note that the Pacific Highway is predominantly one
lane (each way) with(in) the Shire and it conveys 18,000
23,000 vehicles per day. Any change in traffic lanes quickly
results in substantial queuing.
Response
relevant Council and the RTA. Refer Sections 5.6, 5.10 and 6.1
and Annex A.
The upgrade works include the existing powerline that crosses
Ross Lane. As detailed in the TMP road closures can be
avoided where the new conductors can be fed over the road
using existing conductors, which is likely in this case. Any
requirement for partial or total closure (in the unlikely event t
is required) will be undertaken in accordance with the
measures detailed in the TMP including Country Energys
procedures provided at Annex A that include consultation
with and approval off the relevant road authority.
The RTA has provided a response regarding potential for road
closures of highways. Refer Sections 5.6, 5.10 and 6.1
Transmission Line Crossing a Roadway and Table 6.1
Stopping or merging traffic includes all concerns described.
Group/Agency
Correspondence
Concern/Comment
Bruxner Highway
It is noted in your report that at certain locations along the
Bruxner Highway that lane or total road closures may apply.
The Bruxner Highway has no option for detour and conveys
15,000 vehicles per day. As with the Pacific Highway, any
change to traffic conditions results in instantaneous queuing.
Both the Bruxner and Pacific Highways require RTA
concurrence for any change of traffic movement.
Traffic Control Plans
A review of the traffic control plans revels additional signage
is required. For example there is no speed reduction signage,
no speed re-establishment, no advisory signage stating
shoulder closed and the presence of an unprotected spotter is
not supported.
Byron Shire
Council
Letter received
Michael King dated
25 May 2010
Response
Refer Section 5.6 Transmission Line Crossing a Roadway and
Table 6.1 Stopping or merging traffic includes all concerns
described.
Group/Agency
Correspondence
Ambulance
Service of NSW
NSW Police
Force Ballina
and Lismore
(Richmond
Local Area
Command)
NSW Police
Force Byron
Nil comments
received despite
numerous
approaches
Concern/Comment
immediately after damage ore removal and as works
progress;
4. Any damage to road infrastructure is repaired and at the
cost of Country Energy and/or their contractors and subcontractors
The plan provided addresses traffic management issues that
may relate to emergency vehicle access during the upgrade.
The plan is consistent and provides assistance for Ambulance
as required. Should there be any road closures that would
impede ambulance access to areas of the community it would
be appreciated if prior written advice could be supplied about
such closures so that alternate routes can be identified. This
information would also be placed in the Ambulance Control
Centre database to identify such areas.
The traffic control information is detailed and appears to
comply with all guidelines. I have no issues with what is
proposed at this point in time.
My only request is that on the day of each operation where
traffic control will be implemented a site supervisor be
appointed to make contact with the nearest Police Station and
advise of the area the traffic control will be in effect and the
time period expected. If they are unable to contact the nearest
Police Station I would request that they attempt to make
contact with me. This exchange of information can at times be
quite valuable in organising other activities where Police area
required (i.e.: wide load escorts/etc).
As no response has been received, management response will
incorporate actions arising from Richmond Local Area
Command comments.
Response
Group/Agency
NSW Fire
Brigade
Regional North
2
Correspondence
Email received form
Greg Lewis dated 25
March 2010
Concern/Comment
From your info supplied I would assume that Country
Energy's work in upgrading the electrical network on the Far
North Coast will involve road disruptions in areas that the
NSWFB Stations below, operate in.
Response
Refer Table 4.1 Roles and Responsibilities (TM.WC.05) which
includes notification by fax to impacted Fire Brigade Station
one week prior to commencement of road disruptions
Department of
Planning
Group/Agency
Correspondence
Concern/Comment
Response
Page 1 of 1
William Weir
From:
Sent:
To:
William Weir
Hi Will,
Re: Traffic control for the network upgrades for from Lismore to Mullumbimby.
The traffic control information is detailed and appears to comply with all guidelines. I have no issues with what
is proposed at this point in time.
My only request is that on the day of each operation where traffic control will be implemented a site supervisor
be appointed to make contact with the nearest Police Station and advise of the area the traffic control will be
in effect and the time period expected. If they are unable to contact the nearest Police Station i would request
that they attempt to make contact with me. This exchange of information can at times be quite valuable in
organising other activities where Police area required (ie: wide load escorts/etc).
Regards
Rob
_________________________________________
The information contained in this email is intended for the named recipient(s)
only. It may contain private, confidential, copyright or legally privileged
information. If you are not the intended recipient or you have received this
email by mistake, please reply to the author and delete this email immediately.
You must not copy, print, forward or distribute this email, nor place reliance
on its contents. This email and any attachment have been virus scanned. However,
you are requested to conduct a virus scan as well. No liability is accepted
for any loss or damage resulting from a computer virus, or resulting from a delay
or defect in transmission of this email or any attached file. This email does not
constitute a representation by the NSW Police Force unless the author is legally
entitled to do so.
5/25/2010
Page 1 of 1
William Weir
From:
Sent:
To:
William Weir
Hey Will,
Yes it covers both Lismore and Ballina Shire. Unfortunately i can't comment on Byron as it is outside of my
Local Area Command boundary.
Regards
Rob
_________________________________________
The information contained in this email is intended for the named recipient(s)
only. It may contain private, confidential, copyright or legally privileged
information. If you are not the intended recipient or you have received this
email by mistake, please reply to the author and delete this email immediately.
You must not copy, print, forward or distribute this email, nor place reliance
on its contents. This email and any attachment have been virus scanned. However,
you are requested to conduct a virus scan as well. No liability is accepted
for any loss or damage resulting from a computer virus, or resulting from a delay
or defect in transmission of this email or any attached file. This email does not
constitute a representation by the NSW Police Force unless the author is legally
entitled to do so.
5/25/2010
Page 1 of 1
William Weir
From:
Sent:
To:
William Weir
Cc:
Darren Patch
Irefertoletterdated24February2010toCounciladvisingoftheupgradefortheelectricitynetworkfromLismoreto
Mullumbimby.
IapologiseforthedelayinCouncil'sreply.
Councilnotesthecontextofyourrecentcorrespondenceandhasnocommentstomakeregardingyourproposalatthis
stage.
Thankyou
Regards
Carolyn Moynihan, Technical Officer
Works
Lismore City Council
WyrallahRoadDepot,WyrallahRd,LISMORE NSW 2480
Ph: (02) 6620 1659 | Fax: (02) 6620 1699
email: Carolyn.Moynihan@lismore.nsw.gov.au
This email and any files transmitted with it are confidential and intended solely for the use of the
individual or entity to whom they are addressed. If you have received this email in error please notify
the sender immediately and delete this email. Please note that any views or opinions presented in this
email are solely those of the author and do not necessarily represent those of Lismore City Council.
Finally, the recipient should check this email and any attachments for the presence of viruses.
Lismore City Council accepts no liability for any damage caused by any virus transmitted by this
email. Lismore City Council, 43 Oliver Avenue, Goonellabah NSW Australia 2480
www.lismore.nsw.gov.au
5/25/2010
Page 1 of 1
William Weir
From:
Sent:
To:
William Weir
5/25/2010
Page 1 of 2
William Weir
From:
Sent:
To:
William Weir
Cc:
David Ferguson; Andrew Hill; Brett Lowden; Christian Fabri; Dennis Henry; Douglas Dickie;
Fraser Hindry; Ian Grimwood; Jeffrey Snow; Joshua Rushton; Warren Simmons
Subject: Re: Lismore to Mullumbimby Electricity Network Upgrade Project -Traffic Management Plan
William
From your info supplied I would assume that Country Energy's work in upgrading the electrical network on
the Far North Coast will involve road disruptions in areas that the NSWFB Stations below, operate in.
I have supplied fax numbers to those stations that may be impacted upon.
Bangalow 02 66872359
Mullumbimby 02 66843786
Byron Bay 02 66808289
Alstonville 02 66283826
Lismore 02 66215481
Goonellabah 02 66252390
Can you provide a fax to the respective station that might be impacted upon 1 week prior to the work along
those roads commencing.
This will give the respective Captains ample warning to inform the drivers of the traffic changes.
I would also expect and hope that the local on site traffic controllers will work to assist NSWFB appliances
responding to emergencies around these roadworks if and when required.
I hope this helps.
Regards
Regard
Inspector Greg Lewis
Duty Commander
NSWFB Regional North 2
Ph: 6624 5384
Mob: 0419 694 256
Email: greg.lewis@fire.nsw.gov.au
s
>>> William Weir <William.Weir@erm.com> 24/03/10 14:30 >>>
Greg,
As discussed, ERM is seeking comments on the Traffic Management Plan (refer attached) for the above
referenced project to be undertaken in the Lismore, Ballina and Byron LGAs.
Dont hesitate to call and discuss.
Kind regards,
Will Weir
Senior Environmental Engineer
5/25/2010
Page 2 of 2
ERM - Environmental Advisor of the Year, 2005, 2006, 2008 & 2009 - Acquisitions Monthly
Ranked No. 1 All-Environmental Firm - ENR Magazine, 2004 - 2007
This electronic mail message may contain information which is (a) LEGALLY PRIVILEGED, PROPRIETARY IN NATURE, OR OTHERWISE
PROTECTED BY LAW FROM DISCLOSURE, and (b) intended only for the use of the Addressee (s) names herein. If you are not the Addressee
(s), or the person responsible for delivering this to the Addressee (s), you are hereby notified that reading, copying, or distributing this message
is prohibited. If you have received this electronic mail message in error, please contact us immediately and take the steps necessary to delete
the message completely from your computer system. Environmental Resources Management Australia Pty Ltd (ERM) has systems in place to
encourage a virus free software environment, however we cannot be liable for any loss or damage, corruption or distortion of electronically
transmitted information, or for any changes made to this information during transferral or after receipt by the client.
This electronic mail message may contain information which is (a) LEGALLY PRIVILEGED, PROPRIETARY IN NATURE, OR OTHERWISE
PROTECTED BY LAW FROM DISCLOSURE, and (b) intended only for the use of the Addressee (s) names herein. If you are not the
Addressee (s), or the person responsible for delivering this to the Addressee (s), you are hereby notified that reading, copying, or distributing
this message is prohibited. If you have received this electronic mail message in error, please contact us immediately and take the steps
necessary to delete the message completely from your computer system. Environmental Resources Management Australia Pty Ltd (ERM) has
systems in place to encourage a virus free software environment, however we cannot be liable for any loss or damage, corruption or distortion
of electronically transmitted information, or for any changes made to this information during transferral or after receipt by the client.
Please visit ERM's web site: http://www.erm.com
This message, and any files transmitted with it, is intended only for the addressee named and may contain
confidential and/or legally professional privileged material. If you are not the intended recipient, please
delete it and notify the sender immediately. Any retransmission, dissemination, reliance on or other use of
this communication by persons other than the intended recipient is prohibited. Views expressed in the
message are those of the individual sender, and are not necessarily the views of the NSW Fire Brigades.
Usage of Electronic mail is subject to NSWFB policy and guidelines. The NSWFB reserves the
right to filter, inspect, copy, store and disclose the contents of electronic mail messages, as
authorised by law.
5/25/2010
Murray
As discussed earlier today, we received the Lismore to Mullumbimby Electricity
Network Upgrade Traffic Management Sub-Plan (TMP) on Friday afternoon. Our
apologies in the delay in responding to you.
It should be noted that any works outlined in the attached TMP that may impact on
the Pacific Highway should be brought to the attention of the Pacific Highway
Office. The appropriate contact within that office is Tony Smith, Traffic Impact
Coordinator on 02 66 401 077.
As you are aware, the proposed works outlined in the attached plan that impact upon
the State Road Network will require Road Occupancy Licenses (ROLs).
Applications for ROLs (apart from the Pacific Highway - see Tony Smith) are to be
made using the appropriate form located on RTAs website www.rta.nsw.gov.au;
Publications, statistics & forms;
RTA forms
Road Occupancy
Road Occupancy License applications must be received 10 working days prior to
proposed commencement dates.
No late road occupancies will be considered excepting genuine emergency
maintenance or other emergency work.
Forward the appropriate completed forms, and any other applicable information to:
Northern Region Traffic Commanders
A copy of the Road Occupancy Licence must be kept on site at all times.
Completed Temporary Speed Zone Authorisation (SZA) form(s) must be completed
on site and copies returned to the Traffic Operations Unit after completion of the
work.
If you have any further queries, do not hesitate to contact me.
Regards
Todd Heyman
A/g Traffic Operations Manager
RTA Northern Region
31 Victoria St, Grafton
T: 02 6640 1384
M: 0448 725 060
F: 02 6640 1304
E: Todd_Heyman@rta.nsw.gov.au
Partner
ERM Australia and New Zealand
3-146-150 Gordon Street Port Macquarie NSW 2444
PO Box 5711 Port Macquarie NSW 2444
p + 61 (0)2 6584 7155
m +61 (0)427 423 383
http://www.erm.com
This electronic mail message may contain information which is (a) LEGALLY PRIVILEGED, PROPRIETARY IN
NATURE, OR OTHERWISE PROTECTED BY LAW FROM DISCLOSURE, and (b) intended only for the use of
the Addressee (s) names herein. If you are not the Addressee (s), or the person responsible for delivering this to
the Addressee (s), you are hereby notified that reading, copying, or distributing this message is prohibited. If you
have received this electronic mail message in error, please contact us immediately and take the steps necessary
to delete the message completely from your computer system. Environmental Resources Management Australia
Pty Ltd (ERM) has systems in place to encourage a virus free software environment, however we cannot be liable
for any loss or damage, corruption or distortion of electronically transmitted information, or for any changes made
to this information during transferral or after receipt by the client.
Please visit ERM's web site: http://www.erm.com
Before printing, please consider the environment. IMPORTANT NOTICE: This email and any attachment to it are intended only to be read or used by the named
addressee. It is confidential and may contain legally privileged information. No
confidentiality or privilege is waived or lost by any mistaken transmission to you. The
RTA is not responsible for any unauthorised alterations to this e-mail or attachment to
it. Views expressed in this message are those of the individual sender, and are not
necessarily the views of the RTA. If you receive this e-mail in error, please
immediately delete it from your system and notify the sender. You must not disclose,
copy or use any part of this e-mail if you are not the intended recipient.
New Zealand
Netherlands
Peru
Poland
Portugal
Puerto Rico
Singapore
Spain
Sri Lanka
Sweden
Taiwan
Thailand
UK
USA
Venezuela
Vietnam