Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Abstract. Cracking deterioration was observed on a motorway after only few years
after construction. The motorway pavement was semi-rigid with a relatively thin
thickness: 4 cm wearing layer, 11 cm asphalt base course, 20 cm lean concrete base
course, 20 cm cement stabilized base course, 20 cm drainage layer, subgrade. lean
concrete base course was cut in spacing 2,5 m to reduce the reflective cracking in
asphalt layers. Testing program included: coring and materials composition testing,
FWD testing to evaluate pavement layers stiffness modulus, radar testing to
measure layer thickness, and to detect water presence in pavement layers,
evaluation of cracks type and spacing, interlayer bond testing, low temperature
resistance of asphalt wearing course. Testing results led to following conclusions:
extremely low winter temperature in combination with relatively thin pavements
thickness and semi-rigid pavement type was the reason of transverse cracking,
longitudinal cracking observed on one of the sections were evaluated as top-down
fatigue type cracking, low interlayer bond between asphalt base layers was one of
the main reason of lower fatigue resistance of the pavement, lack of drainage in
motorway median caused the presence of water in the pavement layers, and
increased the danger of premature pavement deterioration, unpredicted increase in
road traffic caused longitudinal top-down fatigue cracking.
Introduction
Three motorway sections of total length of 150 km were constructed in the period
of 2002-2004 years. Section 1 was a semi-rigid pavement with use of old pavement
constructed in late 1970-ties. Sections 2 and 3 were new constructions:
The notches were transversely cut in the upper cement bound base course in both
Sections with frequency 2-3 m and filled with bitumen to minimise the risk of
reflective cracking in the semi rigid pavements (according to experience [1, 2]). At
this frequency of notches, the width of crack opening is as small that neighbouring
rigid plates co-work providing the load transfer. Hence, the pavement bearing
capacity and fatigue distress is not reduced.
Pavement strengthening was foreseen for all sections after the traffic of 10 million
115kN axel loading. In reality, the traffic density increase was far faster and
pavements have been strengthened with two asphalt layers in years 2007 (section
1), 2008 (section 2), 2009 (section 3).
Pavement deterioration
Transverse cracking on section 2 and block (transverse and longitudinal) cracking
on section 3 appeared in January 2006 r..Cracks appeared also on section 1 but in a
very low number. Further cracking intensity was observed in 2008, especially
longitudinal cracking on section 3. Cracks were not significantly dangerous for
road users (do not create danger or driving comfort). Cracks were systematically
and effectively sealed with polymer-bitumen. Sealing reduced also the risk of
water penetration through cracking into the lower layers. However, the increasing
cracking frequency leads to distress intensification, especially during the winter
time due to water penetration and freezing as well as brine penetration (distress of
hydraulically bound subbase),
Testing programme
In June 2008 an extensive pavement testing programme have been performed on
sections 2 and 3. Previous tests results performed in 2006 have been used in the
final analysis. Testing programme included: FWD layers deflection and moduli,
georadar tests to measure layers thickness and moisture, cracking inventory,
cracking origin analysis, laboratory testing of pavement layers samples, properties
of bituminous binders of section 3, low temperature resistance of wearing course
asphalt mixture.
Dielectric constant
<9
9-12
12-16
> 16
It was determined that the dielectric constants obtained for the wearing course of
Section 3 averaged at 7 while those of Section 2 averaged at 6. The wearing course
in both sections was dry. On the other hand, the asphalt base course was found to
be moist the dielectric constant for Section 3 was 13 (max. 16) and that for
Section 2 ranged between 10 and 14.
Layer modulus calculation based on FWD measurements of pavement
deflections
The total equivalent modulus of elasticity for all the carriageway pavement layers
was as follows:
2,722 MPa
3,016 MPa
2,802 MPa
2,899 MPa.
Ebase [MPa]
Esubgrade [MPa]
9,0765,853
9,7525,515
444100
463100
14,1577,156
173089,475
38680
40387
Specimen no.
right carriageway JPPA
1
2
3
23
25
22
68
64,2
69,0
-8
-9
-14
67,5
74,5
63,5
22,0
16,5
15,8
Property
Softening point R&B, C
Fraass breaking point, C
Elastic recovery at 25 C, %
Specimen no.
right carriageway JPPA
67,8
66,8
71
-10
-4
-10
69
65
62,5
Properties of polymer modified bitumen PMB 25/55-60 from the wearing course
are shown in Table IV. Rheological properties evaluated by DSR didnt show any
significant differences between bitumen samples, apart from specimen number 2,
that had the highest shear modulus G* (Fig. 5).
Fourier Transform Infrared (FTIR) Spectroscopy was performed in KTH,
Stockholm, according to the method described in [5]. FTIR spectra are shown in
Figures 6 and 7. Peaks at 966 and 699 cm-1 are characteristic of SBS polymer
modified bitumen (Figure 6). To evaluate polymer content, IR absorbance at these
specific wave numbers was calculated and compared with SBS calibration curves.
The approximate polymer content was determined in the range from 3,5% to 5,1%.
The tested binders reveals properties showing their aging. The hardest binder (4)
shows the lowest penetration, the highest softening point and the lowest elastic
recovery. It indicates the lowest effectiveness of polymer modification.
Average Force
max [N]
8598
Average Stress
max [kPa]
3573
Average Cracking
Temperature [C]
-20,0
7933
3233
-19,6
Conclusions
Transverse cracking on all three pavement sections are of thermal origin due to
very low temperature, about -28C, during winter 2006. It was confirmed by the
analysis with use of MEPDG system. Cracks in semi-rigid pavement are of the
dual origin thermal in combination with reflective cracking effect (copy of
dilatation notches) [6]. Relatively thin thickness of asphalt layers (15 cm) resulting
from the stage construction of the pavement contributed to creation of thermal
cracking. Low harmfulness of transverse cracks does not weaken the pavement
bearing capacity, thanks to the pavement slabs load transfer.
Longitudinal cracks are limited to wearing course depth. Their origin is of topdown fatigue cracking. It may be presumed that the reason was the lower
effectiveness of PMB binder.
Transverse and block cracking on sections 3 may have three origins. Firstly:
significant growth of road traffic, exceeding 5-ve times prediction in the pavement
design). Secondly: moisture in pavement asphalt subbase due to lack of drainage in
motorway median (which is a known appearance eg. [7]). Thirdly: weakening of
pavement bearing capacity due to dividing asphalt subbase layer into two sublayers, which resulted in weaker compaction and interlayer bonding with the
final effect of lower pavement fatigue resistance.
After strengthening and drainage construction in motorway median, the pavement
is in a good condition under a heavier traffic loading. It may be expecting that the
semi rigid asphalt pavement may fulfil requirements of long life pavement,
requiring only the wearing course renewal [8].
References
[1]
Prevention of Reflective Cracking in Pavements. State-of-the-Art Report
of RILEM Technical Committee 157 PRC. RILEM Report 18, E&FN Spon, 1997
[2]
Conception et dimensionnement des strucutres de chausse. Guide
technique. Setra-LCPC 1994
[3]
Road Doctor Users Guide, Roadscanners Oy, Rovaniemi, Finland 2001