Sei sulla pagina 1di 963

code and index for work items of standard data

Item Code

Item of the work


PREAMBLE & GUIDELINES

PART-1

Page No.
i-xiv

IRRIGATION
Abstract of Items - Irrigation

XV-LIII

IRR-DAW

Dam And Allied Works

IRR-DAW-1

EXCAVATION & FOUNDATION TREATMENT WORKS:

1-10

IRR-DAW-2
IRR-DAW-3
IRR-DAW-4
IRR-DAW-5
IRR-DAW-6

REINFORCEMENT & CEMENT CONCRETE WORKS :


MASONRY & GUNITING WORKS :
CONTRACTION JOINT WORKS:
EARTH / ROCKFILL EMBANKMENT WORKS :
FILTER & PITCHING WORKS :

10-23
23-29
30-32
32-38
39-46

IRR-TAW
IRR-TAW-1
IRR-TAW-2
IRR-TAW-3
IRR-TAW-4
IRR-TAW-5
IRR-TAW-6

Tunnel & Allied Works


EXCAVATION :
DEWATERING & GUNITING WORKS :
TEMPORARY & PERMANENT SUPPORTS :
MASONRY WORKS :
REINFORCEMENT & CONCRETE WORKS :
DRILLING & GROUTING WORKS :

50-57
58-59
59-64
65-66
66-69
71-72

IRR-CAW
IRR-CAW-1
IRR-CAW-2
IRR-CAW-3
IRR-CAW-4
IRR-CAW-5
IRR-CAW-6
IRR-CAW-7
IRR-CAW-8

Canal And Allied Works


EXCAVATION WORKS :
EMBANKMENT WORKS USING BORROW AREA SOIL :
EMBANKMENT WORKS USING DUMP AREA SOIL :
EMBANKMENT WORKS USING EXCAVATED SOIL :
FOUNDATION FILLING WORKS :
ROCK FILL WORKS :
CANAL LINING WORKS :
ROCK PITCHING:

74-85
86-90
91-94
95-98
99-105
106-107
107-140
141-150

IRR-CCDW
IRR-CCDW-1
IRR-CCDW-2
IRR-CCDW-3
IRR-CCDW-4
IRR-CCDW-5
IRR-CCDW-6
IRR-CCDW-7

Canal & Cross Drainage Works


EXCAVATION & FOUNDATION TREATMENT WORKS :
STEEL AND CEMENT CONCRETE WORKS :
FOUNDATION WELL SINKING WORKS :
MASONRY WORKS :
COPING & RAILING WORKS :
HUME PIPE LAYING & JOINTING WORKS :
BACK FILLING & OTHER WORKS :

152-155
155-175
176-176
177-182
183-185
185-190
190-192

IRR_GAW
IRR_GAW-1
IRR_GAW-2
IRR_GAW-3
IRR_GAW-4

Gates/Hoists And Allied Works


NOTES ON GATES/HOISTS AND ALLIED WORKS
RADIAL GATES
VERTICAL LIFT GATES
SAND BLASTING AND PAINTING:
PAINTING WITHOUT SAND BLASTING:

194-194
195-198
199-210
211-213
213-215

IRR-PMW
IRR-PMW-1
IRR-PMW-2
IRR-PMW-3

Preliminary And Maintenance Works


JUNGLE CLEARANCE :
PRELIMINARY WORKS :
MAINTENANCE WORKS :

216-223
223-228
228-240

COMMON ITEMS TO ALL DEPARTMENTS (unless specified)


COM-MWRK
COM-LDLFT

COM-LDLFT

A. Manual Works
B. Lead/Lift/Loading & Unloading Charges
(to follow MORTH standardsfor the items not covered ,as
applicable to roads and bridge works)
Notes on Lead and Lift

241-241

242-242

Item Code
COM-LDLFT-1

Item of the work


(Lead) Conveyance Charges for materials by head load
( Lead) Conveyance charges for machinery per kilometer for
transporting materials by tippers and trucks, excluding
loading, unloading and hire charges of machinery.

COM-LDLFT-2
COM-LDLFT-3
COM-LDLFT-4

Page No.
242-242

242-243
LOADING AND UNLOADING CHARGES BY MANUAL
MEANS (Idle hire charges of trucks are not added)
LOADING AND UNLOADING CHARGES BY MANUAL
MEANS (including idle hire charges of trucks )
LOADING AND UNLOADING CHARGES BY MECHANICAL
MEANS (including idle hire charges of trucks )

243-243
243-243

COM-LDLFT-5
LIFT CHARGES FOR MATERIALS BY HEAD LOAD
COM-LDLFT-6
COM-DTL-LDLFT-1 (Lead) Conveyance Charges for materials by head load
( Lead) Conveyance charges for machinery per kilometer for
transporting materials by tippers and trucks, excluding
loading, unloading and hire charges of machinery.

243-243
243-243
244-245

COM-DTL-LDLFT-2

245-250

LOADING AND UNLOADING CHARGES BY MANUAL


COM-DTL-LDLFT-3 MEANS (idle hire charges of trucks are not added)
LOADING AND UNLOADING CHARGES BY MANUAL
COM-DTL-LDLFT-4 MEANS (including idle hire charges of trucks )
LOADING AND UNLOADING CHARGES BY MECHANICAL
MEANS (including idle hire charges of trucks )
COM-DTL-LDLFT-5
COM-DTL-LDLFT-6 LIFT CHARGES FOR MATERIALS BY HEAD LOAD

250-251
251-253

253-254
254-255

PART-2

ROADS&BRIDGES

RBR

Basic Approach and General Conditions - Roads and Bridges

257-262

RBR-LUCC

Loading, Unloading, Carriage and Crushing Of Materials

263-276

RBR-STCL
RBR-EECD
RBR-SBBS

Site Clearance
Earthwork,Erosion Control And Drainage
Granular Sub-Bases, Bases (Non-Bituminous) And
Shoulders

277-292
293-313
314-348

RBR-BASC
RBR-CCPV
RBR-CWSB
RBR-HLRD
RBR-PCVT
RBR-TSRA
RBR-FNDN
RBR-SBST
RBR-SPST
RBR-PTWK
RBR-MTRD
RBR-GSRE
RBR-HRTC
RBR-RPRH

Bases And Surface Courses(Bituminous)


Cement Concrete Pavement
Causeway and Submersible Bridges
Hill Roads
Pipe Culverts
Traffic Signs, Markings and Other Road Appurtenances
Foundation
Substructure
Superstructure
Protection Works
Maintenance of Roads
Geosynthetics and Reinforced Earth
Horticulture
Repair and Rehabilitation

349-411
412-421
422-423
424-433
434-438
439-481
482-547
548-570
571-606
607-619
620-631
632-636
637-645
646-655

PART-3

BUILDINGS

BLD-CSTN

Basic Approach & General Conditions-Buildings

656-658

BLD-CSTN-1
BLD-CSTN-2
BLD-CSTN-3

Mortars
Concrete, Grouting, Damp Proof Course
Brick Work & Honey Comb Work

659-660
660-669
670-674

BLD-CSTN-5
BLD-CSTN-6
BLD-CSTN-7
BLD-CSTN-8
BLD-CSTN-9
BLD-CSTN-10
BLD-CSTN-11
BLD-CSTN-12
BLD-CSTN-13
BLD-CSTN-14
BLD-CSTN-15

Item of the work


Stone Masonry, Damp Proof Course, Dry Stone Packing, Quarry
Rubbish, Gravel Backing
Pointing
Plastering
Flooring
Roofing and Ceiling
White Washing, Colour Washing & Distempering
Painting, Varnishing
Wood Work, Aluminum Doors, Windows, ventilators etc.,
Dismantling & Demolishing
Miscellaneous
Anti Termite Treatment
Centering, Form Work

BLD-ELEC

Electrical Items for Buildings

750-753

BLD-ELEC-1
BLD-ELEC-2
BLD-ELEC-3
BLD-ELEC-4
BLD-ELEC-5
BLD-ELEC-6
BLD-ELEC-7
BLD-ELEC-8
BLD-ELEC-9
BLD-ELEC-10
BLD-ELEC-11
BLD-ELEC-12
BLD-ELEC-13
BLD-ELEC-14
BLD-ELEC-15
BLD-ELEC-16
BLD-ELEC-17
BLD-ELEC-18

Conduit Laying
Wiring
Run Of Mains
Switch Gear & MCB Distribution Board
Earthing
Service Mains & LTOH Lines
Street Light Luminaries
Internal Luminaire
AC and Refrigeration
Water Heaters
Water Pumps
Bus Bars
Swaged Poles
Control Panel & Metering Equipment
Cables / Cable Glands / Lugs
Temporary Illumination
Generators and Transformers
Repairs to Motors & Rewinding

754-761
761-764
765-767
767-779
779-783
783-790
790-795
796-800
800-807
807-808
809-824
825-825
825-832
832-835
835-844
845-845
845-855
856-860

PART-4

PUBLIC HEALTH ENGINEERING

PHE

Basic approach and General conditions Public Health


Engineering Works

861-863

PHE-LCIS-1

Lowering C.I. / D.I. Pipes (all classes) and specials (fittings)


with s/s ends

864-866

PHE-LCIF-2

Lowering C.I. / D.I. Pipes (all classes) and specials (fittings)


with flanged ends

866-867

PHE-JCIS-3

Jointing CI /DI pipes & fittings with s/s ends

868-873

PHE-JCIR-4

Jointing C.I., D.I. pipes and fittings with rubber gasket (push- 873-879
on-joint)

PHE-JCIF-5

Jointing CI pipes , fittings and valves with flanged ends

879-884

PHE-LRCS-6

Lowering the RCC S/S pipes

884-888

PHE-LJGI-7

Lowering and Jointing G.I. pipes and specials / fittings

889-892

PHE-GIDM-8

Making connection of G.I . distribution branch with G.I. main


by providing and fixing tee

892-892

PHE-LACP-9

Lowering and laying AC pressure pipes (class 5 & 10) in


ready made trenches true to alignment and gradient

893-895

Item Code
BLD-CSTN-4

Page No.
675-679
679-679
680-685
686-697
697-710
710-713
713-719
719-736
737-738
738-741
742-742
742-749

Item Code
PHE-JACP-10

Item of the work


Jointing A.C. pressure pipes with A.C. coupling or C.I.
detachable joints complete with rubber rings

Page No.
895-899

PHE-LJUP-11

Lowering, laying, jointing and testing to hydralic test pressure


of UPVC pressure pipes

899-900

PHE-LJHE-12

Laying and jointing of HDPE pipes by butt fusion welding

900-905

PHE-LJSW-13

Lowering and laying in ready made trench true to alignment


and gradient, jointing, and testing of Stone Ware pipes

905-908

PHE-CISP-14

Labour charges for laying in position S&S or flanged C.I.


specials such as tees, bends, collars tapers and caps etc

PHE-CISV-15

Lowering, keeping in position and fixing C.I. sluice valves


(with cap / with hand wheel & reflex valves)

908-910

PHE-DAAV-16

Providing and fixing double acting air valves

910-910

PHE-SFHD-17

Providing and fixing spindle fire hydrant with 65 mm outlet.

910-910

PHE-DSFH-18

Dismantling of spindle fire hydrant

910-910

PHE-URCI-19

Uprooting of C.I. pipes by melting lead, loosening the joints

911-913

PHE-URRC-20

Uprooting of R.C.C. Pipes including breaking the collars

913-913

PHE-URSW-21

Uprooting of old S.W. pipes including breaking of joints

914-915

PHE-URGI-22

Removing old G.I.pipes and specials / fittings

915-915

PHE-CCIP-23

Cutting C.I. / D.I. pipes without water in mains

915-916

PHE-DTCI-24

Drilling and tapping C.I./D.I. main and fixing brass screw


down ferrule and C.I.mouth cover.(Labour charges only)

916-916

PHE-SHST-25

Shoring and strutting of trenches for water and sewer lines

PHE-BHLW-26

Barricading, hoarding, lighting and watching etc.,

PHE-RCVS-27

Providing RCC spun vent shaft with cowl 140 mm and 200
918-918
mm internal and external dia respectively at top, 300 and 450
mm internal and external dia respectively at bottom and
9.10m overall length

PHE-WSNP-28

Well sinking in sandy and other loose soils under water


either by manual labour, divers or dredgers-NON
PERENNIAL RIVERS

918-919

PHE-WSOW-29

Sinking of RCC 12 m dia well in sandy soils, soft


disintegrated rock, loamy and clayey soils etc; -OPEN WELL
EXCAVATION

919-920

908-908

917-917

917-918

Item Code
PHE-WSPR-30

Item of the work


Well sinking in sandy and other loose soils under water
either by manual labour, divers or dredgers weightingPERENNIAL RIVERS

Page No.
920-921

PHE-CCCP-31

Curing of CC pavement for 21 days

922-922

PHE-CSHR-32

Cutting sheet rock including stocking of excavated material.

922-922

PHE-EXRW-33

Excavation for roadway in hard rock (blasting prohibited) with


rock breakers

922-923

PHE-LUSS-34

Loading or Unloading materials such as C.I / D.I Pipes,


R.C.C. Pipes, P.V.C. pipes, A.C. Pressure pipes and
Specials less than 300 mm upto 4 mts in length including
stacking.

923-923

PHE-LUMS-35

Loading or unloading materials such as C.I / D.I. Pipes,


stone ware pipes, R.C.C. pipes, A.C. Pressure pipes and
specials from 300 mm to 600 mm dia upto 4 mts in length
including stacking.

924-924

PHE-LUGS-36

Loading or unloading materials such as CI / DI Pipes, A.C.


pressure pipes less than 300 mm dia above 4.00 M in length
including stacking

924-924

PHE-LUBS-37

Loading or Unloading materials such as C.I / D.I. Pipes, A.C.


Pressure pipes from 300 to 600mm dia above 4.00 m
including stacking

924-925

PHE-CSRC-38

Centering and scaffolding charges for R.C.C. members


including all materials and labour charges for forming and
dismantling

925-926

PHE-HSSG-39

Hoisting of S.S. Girders in pump house etc.

926-926

PHE-LCVS-40

Labour charges for fixing ventilating shafts in sewerage


scheme complete with all accessories

926-926

PREAMBLE
1.

The existing AP Standard data for various constructions items are


based on observations made several decades back, mostly utilising
manpower and deployment of machinery was at the barest minimum. The
Board of Chief engineers have been adopting almost the same data, duly
modifying the rates of labour; materials, hire charges of limited machinery,
every year.

The advent of construction machinery and its usage in construction


industry has changed the structure and methodology of data formulation &
rate structure and hence, the present estimation of work item rates are not
reflecting ground reality.

The CWC(Ministry of Irrigation) has also recommended that where


standard or schedule of rates are revised or where is necessary to do so, the
primary guiding principle should be escalation in labour and material cost
and not on trend of rates quoted by contractors. But the above
recommended principle is not being followed by the Board of Chief
engineers in Andhra Pradesh.
2.

Government, in GO 7326 (GAD-GPM& AR) Dated 26-10-05, has


observed that the age old Standard data requires revision and updation
with reference to the latest machinery and contemporary practices and has
constituted a High Level Committee to advise on updating and revision of
standard data and schedule of rates. The work has been taken up by CGG
and SPIU-irrigation. The secretary (Irrigation ) is the member- convener of
the committee

Accordingly the data has been revised adopting the procedures and
guidelines given by CWC, Report on committee on cost control of river

valley Projects, BIS specifications, NHAI, MORTH, MORD, CPWD and


Government of Karnataka and revised data and formulated schedule of rates
for all infrastructure Departments (I&CAD, R&B, PR and PH). The team of
senior engineers interacted with the S.R Committee of Karnataka on
implementation and improvements needed. For irrigation works the data
pattern as adopted by Karnataka has been considered and for other
Departments the data adopted by MORTH,MORD and NHAI etc. is adopted

3.

Sequence followed in revision of standard data is,


(a) The first step is the revision and formulation of standard data for each
work component
(b) The second step is to work out the details of inputs. This enables to
generate the unit work item rates, by incorporating the use rates of
machinery, materials, labour charges and other supplementary parameters
(c) The third step is to develop software tool to generate unit rate using
the software (completed for irrigation works by the SPI Unit of Irrigation)

4.

The Detailed draft data was communicated to all the HODs and
interacted through many seminars and discussions and incorporated the
relevant features.The Board of chief engineers in their meetings have
recommended for acceptance to the data formulated and schedule of rates.
It was proposed to examine the recommendations on important parameters,
to refer to high level committee, for their specific recommendations for
adoption, as they are common to all departments.

The committee made in depth study on the methodology and systems


followed by the reputed National organizations and other States and made
detailed deliberations with HODs and representatives of Builders
Association of India and made recommendations to the Government, on
adoption of such parameters in A.P.

ii

5.

The Chief Secretary held a detailed discussions on 04-07-2007,with


the Secretaries of the Departments and Heads of Departments.

B. GUIDELINES

1)

The Revised Standard Data is formulated under four Parts which are

applicable to all the Engineering Departments and other Organisations.


PART -1: Irrigation& CAD (Dam and Allied Works, Canals And Allied Works,
Canal C.D. Works, Tunnels and Allied Works, Preliminary and
Maintenance Works, Hydraulic Gates and allied works and Leads and
Lifts applicable to all Departments

PART -2: Roads and Bridges

PART -3: Buildings including Electrical Works

PART -4: Drinking Water Supply and Public Health (ONLY FOR WORKS
DONE BY MANUAL MEANS)

2) Brief description of item of work. :


Brief description of the item of work to cover all important aspects of
the work included in the in the Data . On reading the item description, the user
should be in a position to assess the various cost components involved in the
work.
3) Data for assessing quantities :
The data reflects various assessments / assumptions made in arriving
at the quantities of materials, machinery, labour and other in-puts. In case of
plants and equipment the output of main plant is worked out and the requirement
of all other inputs and assessed to match the output of the main plant. Cycle time
of operations is the criteria for assessing the output of equipment. Generally the
equipment manufacturers furnish the output of machinery under ideal conditions
iii

of working. Suitable job and management efficiency factors are considered while
working out the average output of machinery under field conditions. In case of
combination of machinery and manpower the assessment of manpower shall
match the output of machinery.

Though cycle time of operations is the criteria for hourly / daily out-put
of machinery work-force ,the actual progress of work depends on several other
factors such as power interruptions, minor break-downs, time for meals and other
needs of work-force, stray rains etc. Therefore, it is the general practice to
consider 50 minutes as the actual working time per hour for working out the
hourly / daily out-put of machinery / work-force.CWC / BIS guide-lines stipulate
the actual working hours for the purpose of equipment planning and utilisation.
The daily out-put is computed duly considering the actual available working time
and feed back from the field.

For gate and hoist works it is the general practice to specify the
quantity of work in terms of number of sets of embedded parts / gates.
The requirement of machinery and work-force for cutting, bending,
fabrication, erection, painting etc., is assessed to commensurate with
the task involved.

The data for gates and E.M. Parts is arrived per Ton quantity.

The data for Hoists and Gantry Cranes is worked out on the basis of
capacity in tonnage

4) The lead and lift charges provided in PART-I (B) are generally applicable
and common to all Departments. Any item is not covered in this part, the
rates as provided in the data of the relevant works may be adopted in
preparation of estimates.

5) The basic material inputs needed for all works are listed and incorporated in
the data. The requirements are analyzed and the specifications adopted shall

iv

confirm to Standards published by the BIS.

The labour and material rates will be communicated by the Board of


Chief engineers.

Unless otherwise specified, all material rates shall be inclusive of all


taxes, duties, levies, royalty/seigniorage, transportation and handling
costs up to project area.

For sand, gravel , murum, stones , course aggregates etc, the rates
are to be fixed for delivery at Quarry, adding seigniorage ( royality)
charges, loading charges by machinery / manual means and idle hire
charges of machinery (as per table under chapter conveyance or lead
and lift charges), as applicable.

For earth/ soil for embankment works from borrow areas, which is not
included in the material list of schedule of rates, seigniorage charges
are to be added separately,if applicable.

For steel, Cement, AC sheets, GI sheets, Hume pipes, wood and stone
slabs, the rates are to be taken prevailing at major commercial centre
near project area. The lead charges, as applicable are to be added in
preparing estimates.

The specifications of the aggregates for sizes and gradation and its
adoption shall be as per IS 383.

6) The labour component in the data is mentioned for unit work.

No allowance towards labour importation and labour amenities added


extra as they are included in the recommended overheads.

On Labour Component: Certain additional allowances are added extra


to the wages of labour (,i.e. only on labour component in the work
item)

in

the

form

of

percentage,

as

recommended

by

the

Government/Board of chief engineers,due to statutory and other


provisions.

However, If more than one area allowances, such as those for (1)
Municipalities (2) Agency / Tribal areas (3) Industrial areas are
applicable for a particular situation, only the maximum out of the
allowable percentages is to be allowed.

7) HIRE CHARGES OF MACHINERY : The machinery and /or group of machinery

for items of works and their output has been worked based on the
availability of machinery generally in the market and working in the the
field successfully, duly considering cycle time, idle time, operator
efficiency, type of work etc. T

The hire charge of a machinery / equipment is worked out based on the


guidelines published by CWC and BIS codes.

For the other machinery not covered by the list, the R&B and other
users may adopt hire charges as recommended by the MORTH.

8) Lead Charges

The high level committee has recommended to adopt, for conveyance


by head load, a minimum lead of 50 meters and additional lead up to
150 meters in the intervals of 50 meters. Beyond 150 meters lead ,only
machinery rates are to be adopted.

The basic item rates provided in the schedule of rates include 50 m or 1


km as initial lead and no lead charges shall be allowed where the
source of material is within the initial lead specified in item rate.
Additional lead charges shall be allowed for the lead exceeding initial
lead specified in the item rate.

The lead charges per unit quantity for conveyance of the materials are
worked out,and included in the schedule of rates in increment of 50 m
for head load and in increment of 1 km for mechanical mode.

vi

The rates for lead charges by head load upto 150 meters and by
machinery up to 5 km, shall be cumulative and inclusive of lead charges
for preceding lead. For lead beyond 5 km the lead charges shall be
worked out on per km basis.

9) Loading and Unloading charges for Materials


The following features are considered:
1. Loading and unloading charges are not payable for conveyance by head load.
2. Loading and unloading charges are not payable for conveyance by mechanical
means, for disposal of excavated material unless specified.
3. The rates for unloading of materials except earth, sand, gravel, coarse
aggregate, rubble, size stone and cut stone, are inclusive of stacking
wherever applicable.
10) LIFT CHARGES :

The data includes initial lift charges of

3 meters ,for materials

conveyance by head load, Additional leads in the interval of 1.0 meters


are worked out, as additional labour input and incorporated in the
chapter on Lead and lifts .

Where the conveyance / lifting of material is done by mechanical


means, lift charges shall not be considered, as the cycle time of
operation of the machine includes lifts involved.

The data and rates for lift charges is cumulative and are inclusive of
rates for preceding lifts also .

11) Wastage of Materials


I) Cement : No wastage allowance is recommended towards the quantity of

cement used in works, as the wastage is already included in the input


and in major works bulk quantities are used.

vii

II) steel : The wastage of steel @ 2.5% is allowed for gates and allied
structures. For RCC works the wastage is @2.5% for the
reinforcement rods above 36mm did and @ 5% for rods below 36mm
dia. Including overlaps, if they are not welded.
If welding is adopted for the reinforcement rods even for below 36mm
dia, 2.5% of wastage is only recommended.

12) Provision for rate for water:The Committee has recommended not to consider the water charges in
the Irrigation Project works. But, it may be considered in specific cases as
per the site conditions.

13)

In respect of RCC works the rate for cement concrete for 1 cum
is worked separately for all grades based on Indian Standards. The
rate for ton is calculated separately and to be added separately in the
estimates of RCC works as a separate item.

14) Soil classification: The Committee recommended to allow uniform


classification of soils for all Departments and data is worked out accordingly.
1. all soils
2. Marshy soil
3. ordinary rock ( not requiring blasting),
4. hard rock
a. hard rock (requiring blasting)
b. hard rock (controlled blasting)
c. removable by chiseling(blasting prohibited)

15) Use of Super Plasticizers and Admixtures:

Concrete admixtures such as Air-Entraining Agent ( AEA ) / Water reducing


agent can be used advantageously for better quality concrete. The high level

viii

committee has recommended to adopt for super plasticizers and admixtures at


0.4% on cement for concrete work as per MORTH standards for batching plants.

16) Contractors overheads, profit and other provisions :

High Level Committee has recommended to add 14% plus 4% towards VAT
or as applicable on item rate towards overheads labour including importation
and

amenities

&

contractor

profits,

which

includes

various

items

recommended in MORTH .

This also includes 4% of VAT and should be exhibited separately. In the


agreements, it should be mentioned that it will be reimbursed as per actuals.
The provisions allowed in Go Ms. No. 94, I & CAD, Dt. 1-7-03, need not be
added separately.

The overhead charges include the following elements:

Site accommodation, setting up plant, access road, water supply, electricity


and general site arrangements.

Office furniture, equipment and communications

Expenditure on:

Corporate office of contractor

site supervision

Documentation and as built drawings

Mobilisation/ de-mobilisation of resources

Labour camps with minimum amenities and transportation to work sites.

Light vehicles for site supervision including administrative and managerial


requirements.

Laboratory equipment and quality control including field and laboratory


testing.

Minor T & P and survey instruments and setting outworks, including


verification of line, dimensions, trial pits and bore holes, where required.

Watch and ward

Traffic management during construction

ix

Expenditure on safeguarding environment

Sundries

Financing Expenditure

Sales/ Turn overtax

Work Insurance/ compensation

17) EXCISE DUTY ON SUPPLIES :


In respect of gates, hoists and allied works excise duty is applicable on
the value of fabricated components supplied to site. Excise duty is not applicable
on erection charges. Further, the excise duty shall not be considered in the rate
analysis on material component, as basic material rates are inclusive of excise
duty.
Therefore, excise duty is considered in the rate analysis only on
machinery and labour components required for fabrication of gates and hoists at
the central fabrication yard. It is difficult to determine the machinery and labour
components separately for fabrication and erection.
For the purpose of computation of excise duty to be included in the rate analysis
the machinery and labour components may apportioned at 75 % for central
fabrication yard and 25 % for field erection and commissioning. Therefore, 75 %
of the machinery and labour components may be considered for assessing the
extent of excise duty to be added in the rate analysis.
18) DEWATERING & DESILTING:
The High level committee considering the local conditions of rainfall / seepage
has recommended towards de-watering and de-silting at

3 percent

on the

relevant work component for which dewatering is required.


It is also proposed as per CWC guidelines, to keep a condition in the
agreements shall be incorporated, to fix a ceiling of 5% in extreme cases,with the
specific approval of chief engineer/Government.
19) Computerization Of Data :

A software program is developed by the SPI Unit(Irrigation), which


facilitates automatic changes and generation of unit rates, based on
basic input rates of Labour, materials and capital cost of machinery.

A soft ware tool is also developed for auto preparation of estimates


based on in put quantities.

Other Departments are also advised to develop such program.

20) For each chapter separate additional details are incorporated for clarity.

USER GUIDELINES OF REVISED STANDARD DATA


1. Please select the item of work, as given in Index Code, and
view the relevant data.

2. The common data items like, lead, lift, conveyance and manual
excavation (without involving contracting agencies) is applicable
to all Departments (volume-1)

3. The departments have to adopt the relevant data from other


Departments, if such works are executed by them.

4. The unit rate /hire charges, of machinery not covered in the


Irrigation data, the MORTH data may be taken with the approval
of Board of Chief Engineers.

5. For Drinking water Supply works(PART-IV), the data


incorporated is generally applicable only for manual means of
execution. The rates deploying machinery have to be worked out
by the Board of Chief engineers and approved for adoption.

xi

ROLE OF CENTRAL COMPETENT AGENCY FOR SCHEDULE OF RATES


( BOARD OF CHIEF ENGINEERS)

a)

The Board Of Chief Engineers under the chairman ship of Engineer-inchief, (administration) I&CAD Department is the competent authority to
finalise and recommend the Schedule of Rates applicable for all engineering
Departments. The board has to assess and incorporate only the three basic
inputs required to generate unit work item rates as below.

Basic rates of labour:


Wages of labour commonly required in execution of works has to be
arrived and incorporated in the schedule of rates ( Basic Input Of Labour
Wages), without adding extra towards area allowances ( like municipality
allowance, tribal area and ghat road allowances etc, which shall be added to
the rates where applicable in the form of separate percentage as explained
in the preceeding paras. The rates shall be the prevailing daily rates in the
State and shall not be less than the minimum wages fixed by the
Government from time to time.

Materials rates:
The basic input material rates common to all departmental works are
listed out and incorporated (in the chapter Basic inputs) The material
specifications adopted shall confirm to Standards published by the BIS.
The Prevailing market rates for all basic input materials shall be
obtained from the major commercial centers near the project areas. Average
of the rates, ignoring freak rates, shall be reckoned as the prevailing market
rate.
Unless otherwise specified, all material rates shall be inclusive of
all taxes, duties, levies, royalty, transportation and handling costs up to
project area.
For sand, gravel , murrum, stones , aggregates etc, the rates are

xii

for delivery at Quarry including seigniorage, loading charges and idle hire
charges. For steel, Cement, AC sheets, GI sheets, Hume pipes, wood and
stone slabs, the rates prevailing at major commercial centre near project area
has to be adopted.
Use rate of machinery:
The third parameter for incorporation in the Basic Inputs, is the use rate
of machinery. To arrive at the use rate of machinery, the inputs to be
incorporated are

The list and capital cost of machinery required to be used in the


construction activity, The rate has to be obtained from major
manufacturers and outlet sources and the rate shall be the current
market price inclusive of all taxes, duties and freight charges.

The prevailing fuel charges of petrol and diesel are ascertained and
average rate adopted

Borrow rate of interest as fixed by the Government/competent authority


be indicated.

For the other machinery not covered by the list, the R&B and other
users may adopt hire charges as recommended by the MORTH

b)

The Chairman, Board of Chief Engineers or competent authority


appointed by the Government, based on the approved basic inputs, load
the above three basic parameters in the software program. The unit rate
of all works including hire charges of all machinery will be generated
automatically for adoption.

He shall communicate the uniform Schedule of rates arrived from


Standard Data, to all users for uniform and direct adoption in all
infrastructure Departments, as applicable

xiii

BASIC APPROACH AND GENERAL CONDITIONS ROADS AND BRIDGES

BASIC APPROACH AND GENERAL CONDITIONS AND ASSUMPTIONS FOR THE


PREPARATION OF STANDARD DATA ON ROADS AND BRIDGES
The basic approach for the preparation of Standard Data for Roads and Bridges is indicated as under:
1.

Description of Items
The description of items is given briefly and linked with the relevant Sections and Clauses of the
Ministry of Rural Development (MORD) Specifications for Rural Roads 2004 / MORTH
Specifications (Fourth Revision 2001) referred as Technical Specifications in the description
of items, wherever feasible, which may be referred for detailed description, provisions and
interpretation.

2.

Use of Machinery
2.1. Due to mechanization of construction work inputs for various items have been indicated
using mechanical means. However, manual means have also been provided for certain
cases, where areas may be inaccessible for machines or quantum of work may not be large
enough to justify use of machines. Medium in put of Machinery is also proposed, where
ever required.
2.2. For rolling, use of static roller / vibratory / pneumatic tyre roller has been considered
wherever required as per provisions of Specifications. However alternatively vibratory
roller also proposed.

3.

Working Conditions
3.1. The inputs for the Data have been analysed for average working conditions prevailing in
the state.
3.2. Average achievable outputs of machinery and labour have been considered taking into
account the job and management factors.
3.3. Since, the outputs of machinery and labour reduces substantially in hilly areas as the altitude
increases, reduced outputs have been considered for hilly areas as indicated in the Preamble
of Chapter 8.

4.

Overheads
This is assumed to include interalia the following elements:
i.

Site accommodation, setting up plant, access road, water supply, electricity and general site
arrangements

ii. Office furniture, equipment and communications


iii. Provision towards expenditure on:
(a)
(b)
(c)

Corporate office of contractor


Site supervision
Documentation and "as built" drawings

iv. Mobilisation / de-mobilisation of resources

v. Labour camps with minimum amenities required as per labour laws and transportation to
work sites
vi. Light vehicles for site supervision including administrative and managerial requirements
vii. Setting up of Laboratories for quality control, field and laboratory testing for control of
quality of various items of work and documentation of test results as per requirement of the
MORTH / MORD Specifications.

257

BASIC APPROACH AND GENERAL CONDITIONS ROADS AND BRIDGES

viii. Minor T&P including vibrators for concrete work and survey instruments and setting
outworks, including verification of line, dimensions, taking trial pits and bore holes, where
required.
ix. Watch and ward
x. Arrangement for Traffic and Traffic Management during construction.
xi. Provision towards safeguarding environment
xii. Sundries
xiii. Financing expenditure of the Contractor
xiv. Sales/Turnover Tax / VAT at 4%
xv. Work Insurance / compensation.
5.

Contractor's Profit
It is considered to allow 18% towards overheads (Item No. 4) & contractor profits put together
which includes various items recommended in Item 4 above. This includes 4% VAT which
should be exhibited separately. In agreements it should be mentioned that it will be reimbursed
as per actuals.

6.

General
6.1.

The Section and Clause numbers refer to the MORD Specifications for Rural Roads 2004
/ MORTH as the case may be.

6.2. Additional assumptions made for analysing different items have been indicated in respective
Chapters in the form of Preamble and notes/footnotes wherever required.
6.3. For some of the items, certain size/specifications have been assumed. If size/specifications
other than the same are adopted, corresponding modifications may be made in the inputs of
analysis.
6.4. While presenting the Data some items, the quantities of sub-items involved in that analysis,
like, excavation for foundation, foundation concrete, masonry work, painting, lettering, etc.
have been given. For required inputs of such sub-items, reference may be made to relevant
Chapters dealing with the sub-items.
6.5. The sources of all materials and samples of materials are required to be approved by the
Engineer before start of any work.
6.6.

For reinforcing steel both HYSD and TMT bars conforming to IS: 1786 have been
considered.

6.7. For pipe culverts both NP3 and NP4 pipes have been considered.
6.8. The Data include inputs for testing of soil, materials and works.
6.9. The use of surface by construction vehicles shall be governed by Clause 117 of MORD / 119
of MORTH Specifications.
6.10. The contractor shall arrange to provide and maintain an adequate equipped field laboratory as
per Clause 119 of MORD / 121 of MORTH.
6.11. Quality control of works shall be governed by the relevant MORD / MORTH Specifications.
6.12. Sundries to cater for unforeseen contingency and miscellaneous items have been added in the
overhead charges.
6.13. Arrangement for traffic during construction shall be as per Clause 112 of MORTH / 111 of
MORD specifications for Road & Bridge Works.

258

BASIC APPROACH AND GENERAL CONDITIONS ROADS AND BRIDGES


6.14. The various activities of works shall also be documented photographs and video cassettes as
per Clauses 125 & 126 of MORTH / 118 MORD Specifications.
6.15. The classification of Soil shall be as per preamble in Chapter 3 (Earth Work).
6.16. The earth excavated from foundations has been considered to be backfilled and balance
utilized locally for road work except in the case of marshy soil.
6.17. The Data for removal of unsuitable soil does not provide for replacement by suitable soil
which will have to be paid separately.
6.18. Items for hilly terrain have been analysed separately.
6.19. The rates for rigid, semi-rigid and flexible crash barriers have been analysed in Chapter 10.
6.20. The coarse and fine aggregates shall conform to IS : 383.
6.21. Work in Urban Roads
The inputs for earth work in urban roads inhabited area will be comparatively higher due to
following reasons:
a)

There is mixed traffic on urban roads like slow moving hand and animal driven carts,
rickshaws, cycles, two/ three wheeler apart from the usual vehicular traffic resulting
into traffic jams. This causes loss of working time which may be in the range of 10 15 per cent

b)

There is considerable disruption of traffic adversely affecting the efficiency of the


working parties including machines due to congestion caused by pedestrian traffic,
local road side venders, parking of vehicles by the road side, encroachments by the
shopkeepers and local shops who make use of the berms of the road in front of these
shops and unauthorised conversion of road berms into mini local market The output
of manpower and machines is substantially reduced due to factors mentioned above.

c)

Cost of living in urban areas is comparatively more resulting into higher wages.

d)

At times, work is executed during night time due to heavy traffic during day time.
This involves extra expenditure by way of making arrangement for lighting and
special transport for working parties due to odd hour
In the light of above, the authorities engaged in preparing the Data cost estimates may
exercise their judgment and cater for the additional cost to the extent of 2 to 3 per
cent, keeping in view the severity of factors mentioned above. Supporting details for
the extra cost based on the actual conditions in specific cases will have to give in
justification.

7.

Basic Inputs
7.1. The Standard Data Book is based on the requirements of basic inputs of materials, labour and
machineries for various items.
7.2. The rates for labour, material and usage charges of machinery for the area where the project is
located are to be ascertained from local authorities/enquiries to prepare Schedule of Rates
for the area.
7.3. The basic rates of materials, such as, stone boulders, stone for masonry, stone ballast,
stone dust, moorum, gravel, lime, manure, sludge, quarry sweep, kankar, bricks, brick
ballast, crushed slag, etc. at quarry / crusher sites shall be fixed by the Board of Chief
Engineers yearly (effective from 1st June to 31st May). However, the basic rate of
materials hand broken / machine broken, crushed aggregates shall be based on
Analysis in Chapter 1 of Roads and Bridges.
7.4.

The cost of materials should include the cost at source and the cost of their carriage (as per
Schedule of rates arrived in Chapter 1 for conveyance, loading and unloading charges) upto
the work site.

259

BASIC APPROACH AND GENERAL CONDITIONS ROADS AND BRIDGES

8.

Plants and Equipment


8.1. Keeping in view the job and managerial factors and the age factor of machines, the output
of plant and equipment is taken approximately 70 per cent of the rated capacity given by
manufacturer under ideal conditions.
8.2. A dozer is proposed for excavation where cutting and filling for the roadways is within
100m. For longer leads, a combination of hydrolic excavator and tipper is proposed.
8.3. The requirement of machinery has been worked out assuming working period of 6 hours per
shift of 8 hours.
8.4. Certain equipment, like, road rollers, are required to be available at site for complete
period of the shift, though from the consideration of their output, they may be required only
for 3 to 4 hours. This is necessitated to match with the output of other associated machines,
like, HMP, Pavers, etc. In such cases, the hire charges of road rollers have been multiplied
with a factor of 0.65 to account for the idle period wherever considered appropriate.
8.5. Though electrically operated equipment, like, concrete mixers and vibrators have been
provided, diesel operated equipment can be used where electricity is not available.
8.6. Wherever electric generator has not been provided to run a plant or equipment, it is assumed
that it is fitted with a diesel engine.
8.7. For small jobs where loading and unloading is required to be done manually, tractortrolley has been considered for carriage instead of tipper.
8.8. Output of plant/equipment is considered for the compacted quantities.
8.9. A water tanker of 6 kl capacity which is commonly used at construction sites has been
considered.
8.10. The usage charges for machines include ownership charges, cost of repair and
maintenance including replacement of tyres and running and operating charges which
includes crew, fuel and lubricants. The hire charges shall be worked out based on the
Guidelines issued CWC for machinery covered in CWC Guidelines. For other machinery,
MORTH Guidelines shall be followed.

9.

Labour
9.1 The labour wages should be as per rates fixed by the Board of Chief Engineers keeping the
minimum wages fixed as per Minimum Wages Act.
9.2 Skilled labour include mason, carpenter, blacksmith, mechanics and other trades.

10.

Materials
10.1. Quantities of materials considered in the rate analysis are approximate for the purpose of
estimation and include normal wastages. Actual consumption would depend on mix design.
10.2. The rates of material should include basic cost at locations of stone crushers/factory/rail head
and cost of its carriage to the site of work/plant including loading, unloading and stacking.
10.3. The supply of materials will be taken either at the location of mixing plant or at the
work site as per requirement of use.
10.4. Contractor will make his own arrangements for borrowing earth. However, compensation
for earth taken from private land has to be included in the rate analysis for construction of
embankment / sub-grade with borrowed earth.
10.5. Credit for Dismantled Material: The dismantled materials should be examined and a realistic
assessment made for credit for such materials, which can be utilized for works or auctioned.
10.6. The basic rates should include all octroi charges, toll tax, sale tax, VAT, municipal taxes and
other local taxes, etc.
10.7. The specifications of materials shall be governed by section 1000 of MORTH specifications

260

BASIC APPROACH AND GENERAL CONDITIONS ROADS AND BRIDGES


for Roads and Bridge works / relevant Specifications for rural Roads (MORD).
11. Carriage of Materials
11.1 The unit for vehicle for carriage has been taken as under :
a) In hours where lead is defined including time required for loading and unloading.
b) In tonne km where lead is variable. The loading and unloading for such cases have been
provided separately.
11.2 Where the quantity of material to be transported is small such as dismantled materials and the
same are required to be loaded manually, provision of tractor trolley has been made instead of
tipper.
12. Items of Culverts
Items in Chapters 11, 12 & 13 on Foundation, Substructure and Superstructure cover both minor
bridge works as well as slab culverts as per Section 1200 of MORD Specifications. Items of Pipe
Culverts are, however, covered separately in Chapter 9.
13. Bridges
Items in Chapters 11, 12 & 13 on Foundation, Substructure and Superstructure cover both minor
and major bridge works including well sinking, protection bunds and PSC Structures as per
relevant sections 1500 to 2700 of MORTH Specifications.
(i) Bridge bearing and expansion joints are readymade items commercially produced by specialized
firms and in certain cases using imported technology and parts. The rates of these, items are to be
obtained directly from different manufacturers approved by the Ministry (MORTH) and shall be
adopted after comparison.
(ii) Normal method of curing has been covered in the schedule. Analysis for steam curing has been
included in the analysis of pre-cast concrete PSC beams.
(iii) The testing of materials and finished items of work is covered under overhead charges.
(iv) Traffic arrangements during construction are covered under overhead charges.
(v) In the items for well foundation, provision for nominal island/temporary protection, deep
islands/cofferdams with wooden ballies and sheet piles has been made.
(vi) For innovative type of structures like cable stayed bridges, suspension bridges, arch bridges, bow
string girder bridges, erected by innovative techniques where errection stage is as important as the
construction of bridge components in terms of input of machinery, manpower and materials,
special analysis is called for.
(vii) For some of the items, certain size/specifications have been assumed. If size/specifications other than
the same are adopted, corresponding modifications may be made in the inputs of analysis.
(viii) The items do not cover all components of bridge projects for all situations. There may be
specialized items for specific cases, which need to be analysed keeping in view the basic approach.
Guide Bund
(ix) The items for the guide bund are excavation, embankment and protection works. The required inputs
for these items may be taken from the respective chapters.
(x)

In case bridge construction works are to be done on wide and deep water channels in major
rivers or in sea creeks etc., provision of floating barrages etc. for taking the construction materials
and equipments inside water shall also be made separately.

(xi) Analysis for sinking of wells cover diameters from 6 m to 12 and Twin D Type of size 12 m x 6
m. For other shapes like rectangular or any other size, the inputs of sinking may be worked out on
pro-rata basis.
(xii) The lift for casting of concrete in well steining may be 2 to 2.5 m restricting the free fall of concrete to

261

BASIC APPROACH AND GENERAL CONDITIONS ROADS AND BRIDGES


1.5 m and concreting layer to 450 mm.
14. Concrete Items
14.1. For concrete work, the grades of concrete covered by the Data Book in accordance
with MORD / MORTH Specifications are:
i) PCC M15 grade to M25 for structures
(For lean concrete under foundation, M10 can be used).
ii) RCC grade M20, M25 and M30 for structures.
iii) Design mix concrete - M25 and M30 for concrete pavement.
14.2. The Data accounts for input of materials by weight and use of ordinary mixer and as well
as using Batching Plant, Transit Mixer and Concrete Pump.
14.3. Use of vibrators for all concreting work has been included in the items.
14.4. Ten per cent extra cement may be provided for concreting under water, where required.
14.5. Quantities of cement in various grades of cement concrete are to be as per nominal mix/design
mix. Grade of cement may also be adopted as per mix design.
14.6. Quantities of cement in various grades of cement concrete for structures have been
taken as per IRC:21:2000&IRC:78:2000.
14.7. Steel reinforcement for cement concrete work is required to be provided separately unless
otherwise specified in the item. The Data for the same has been indicated separately.
14.8. As per the MORD Specifications, the type of superstructure envisaged for rural roads are
RCC slabs and box culverts not exceeding 15 m span as well brick/stone masonry arches
and composite girder type of superstructure. RCC arches provided for in IRC:SP:20 have
also been analysed.
15.

Measurement and Rates


15.1. Measurement of various items and their units shall be as defined in the respective Clauses
of MORD / MORTH Specifications.
15.2. The rates for various items of work shall include all sub items defined in the respective
Clauses of MORD / MORTH Specifications.

16.

Privileged Document
The Standard Data Book is for Department use only. It should not be produced in any court of law as
reference/ authority and to that extent it is a privileged document.

262

RBR-LUCC

Andhra Pradesh Standard Data


I. Roads and Bridges
PREAMBLE
CHAPTER-1
LOADING, UNLOADING, CARRIAGE, CRUSHING OF MATERIALS AND SETTING OUT
1. The Data for loading and unloading of various items includes stacking.
2. The Data for loading and unloading has been given both by manual and mechanical means. Means
of loading/unloading appropriate to the work and site is to be adopted.
3. The Data for haulage of materials has been made in terms of tonne - kilometre (t.km) for ease of
adoption depending upon the lead in km and load in tonnes.
4. The cost of carriage will vary depending upon the riding surface of the road. Provision has been
made accordingly considering surfaced roads, unsurfaced gravel roads and katcha tracks.
5. Analysis for carriage of materials is exclusive of the loading, unloading and stacking and this has to
be added as applicable.
6. Carriage of materials if done by boats shall be paid at the same rates as given for carriage of materials
by road.
7. The provision of tipper has been made in hours where lead is known like disposal of the materials
upto1000 m. In case where lead is variable like carriage of hot mix or concrete mix from plants or earth
from borrow areas, provision has been made in terms of tonne-kilometer (t-km), which can be adopted as
per actual conditions.
8. Provision has been made for a tractor trolley instead of tipper where dismantled materials of sorts or
material having more volume as compared with weight are required to be transported. This arrangement will
be economical.
9. The cost of carriage will vary depending upon the riding surface of the road. Provision has accordingly
been made considering surface roads, unsurfaced graveled roads and katcha tracks.
10. Analysis for loading has been done both for manual and mechanical means for adoption as per actual
situations.
11. Where loading is done by mechanical plant like HMP or batching plant and there is automatic loading
in tippers, provision of loading and un-loading has been made at rate of 10 per cent of cost of carriage to
account for time taken by the tipper for getting loaded at the plant and un-loading in the paver or
otherwise at site.
12. Although the market rates for supply of aggregates at site are generally taken for estimation purpose,
rate for crushing of aggregate have also been analysed as most of the contractors prefer to crush their own
aggregates in case of large projects exceeding Rs.50 crores in value.
13. The cost of material shall be evaluated considering the cost at crushing plants and cost of carriage
including loading and unloading or the rates for supply at site depending upon system being followed at
particular locations. These rates should be compared with the rates for own crushing and carriage by the
construction agency.

263

RBR-STCL

Andhra Pradesh Standard Data


I. Roads and Bridges
PREAMBLE
CHAPTER - 2
SITE CLEARANCE
1. Unless otherwise stated, the Data for sorting and disposal of unserviceable material and stacking of
serviceable material with all lifts and upto a lead of 1000 m.
2. The Data include Specification and utilization of Tools & Plants (T&P) and scaffolding required
for items of dismantling.
3. Carriage of dismantled materials, bushes, branches of tree, etc. has been catered with a tractor-trolley
of 3 tonnes capacity with manual loading and unloading @ 2 trips per hour within a lead of 1000 m. This
will be economical for such works as compared with a tipper.
4. For cutting of trees above 1800 mm girth, 4 mazdoors have been considered to cater for large size
trees, which will fall in this category.
5. Where only grass wild growth is met with, rate of item No.2.1, i.e., clearing grass and removal of
rubbish can be applied.
6. The dismantling of structures has been catered both by manual and mechanical means. The
Engineer can use his discretion depending upon quantum of work and particular site conditions.
7. Data for removing of stumps and roots has also been provided separately.
8. Dismantling of Hume pipes has been catered manually as pipes can be easily rolled by men to a
suitable stacking place within the right-of-way.
9. For dismantling of structures, which remain submerged in water, the inputs may be enhanced by 50
per cent. If site conditions warrant lowering of water level to facilitate dismantling, the inputs may be
enhanced by additional 25 per cent.
10. Dismantling of utilities, like, water supply lines, electric and telephone lines is required to be done
under the supervision of concerned departments with prior information to the user public.
11. In certain items of dismantling, like, pipe culverts, utilities, etc. excavation in earth and
dismantling of masonry works is not included in this analysis for which suitable notes have been inserted
in respective Chapters. These items are required to be estimated based on actual quantities at site and
nature of work.
12. The dismantled materials should be examined and a realistic assessment and provision should be made
after due process for the salvage value for such materials, which can be utilized for works or auctioned.
13. In case where lead for disposal is more than 1000 m, extra provision for carriage is required to be added
based on tonne-kilometerage as per Chapter 1.
14. All minor Tools & Plants (T&P) items required for dismantling have been considered to have been
included in overhead charges.
15. For dismantling of utility services like water pipe lines, electric and telephone lines, prior intimation
should be given to users.

277

RBR-EECD

Andhra Pradesh Standard Data


I. Roads and Bridges
PREAMBLE
CHAPTER - 3
EARTHWORK, EROSION CONTROL AND DRAINAGE
1. The Data is given using mechanical means. Manual means for certain items have also been provided
which can be used for areas inaccessible to machines and also for small jobs.
2. While indicating the Data for earthwork, compacted volume of earth has been considered.
3. Cutting of earth by dozer has been proposed where the cut earth can be utilized for filling for
embankment within a lead upto 100 m.
4. Where lead for transporting of earth is more than 100 m, excavator and tipper have been provided.
5. The Data caters for disposal of unsuitable soil only upto a distance of 1 km. Necessary provision
for transportation beyond the initial lead of 1 km will be made separately based on tonne kilometerage.
6. The replacement of unsuitable soil by suitable soil shall be provided separately in the estimate. The
Data for removal of unsuitable soil does not provide for replacement by suitable soil.
7. In cases where embankment is constructed with earth taken from roadway, the cost of depositing
the earth at the site of embankment is already included in the disposal of excavated earth and, therefore, the
input of dozer for spreading earth can be deleted.
8. For narrow and restricted areas, plate compactor has been proposed for compaction to achieve
the desired density.
9. In case excavated rock is found suitable for incorporation in works, suitable credit for the available
rock shall be given.
10. For excavation of structures refer to Chapter 11 dealing with items of Foundation.
11. The possibility of using the blasted rock fragments for backfilling behind structures or
backfilling of foundation pits or filling in medians/separators or use in service road shall be examined
before proposing disposal of excavated rock.
12. For inhabited areas, controlled blasting with limited provision of explosives has been made. This
involves smaller drill holes and additional requirement of electric detonators. Provision has been made
accordingly.
13. Any work involved for crossing of water courses for irrigation purpose, etc. will be assessed under
respective items, like, excavation, grubbing, clearing, etc. for which rate analysis have separately been
made.
14. Earth excavated from drains can be used in roadway berms. Hence carriage for disposal of same is
not provided.
15. In case of rock fill embankment, it is assumed that material is available at site from rock cutting.
16. For widening of existing pavement less than 1.8 m, the rates for all items of this Chapter may be
increased by 30 per cent.
17. For small jobs where loading and unloading is required to be done manually, tractor- trolley has been
proposed for carriage instead of a tipper.
18. For small jobs where loading and unloading is required to be done manually, tractor- trolley has been
proposed for carriage instead of a tipper.
19. 'L' represents lead in km one way. This will vary from project-to-project and is required to be ascertained
at site at the time of estimation.
293

RBR-EECD

20. In the rate analyses of some items, the quantities of sub-items involved in that analyses, like, excavation
for foundation, foundation concrete, painting, lettering, etc. have been given. The rates for such items shall
be taken from relevant chapters where the same have already been analysed.
21. The item of preparation and surface treatment of formation (Clause 310) is required to be added in the
cost estimate only if there is substantial time lag between completion of sub-grade and laying of sub-base.
As this item is incidental to works, it is not required to be included in BOQ.
22. The items filling behind abutments and wing wall and provision of filter media has been included
in Chapter-15.
CLASSIFICATION OF EXCAVATED MATERIAL
CLASSIFICATION : All materials involved in excavation shall be classified by the Engineer as per
Specification No 302.2.1 of MORD /
MORTH , as under :
(a) Soil
(b) Ordinary Rock (not requiring blasting)
(c) Hard Rock
i.

requiring blasting

ii. controlled blasting


iii. removable for chiseling etc., (blasting prohibited)
(d) Marshy Soil
Further details pertaining to the above Classification are provided below :
(a) Soil
This shall comprise topsoil, turf, sand, silt, clay, mud, peat, black cotton soil, soft shale or loose
moorum, a mixture of these and similar material which yields to the ordinary application of pick,
shade and / or shovel, rake or other ordinary digging implement. Removal of gravel or any other
nodular material having dimension in any one direction not exceeding 75 mm occurring in such
strata shall be deemed to be covered under this category.
(b) Ordinary Rock (not requiring blasting)
This shall include :

294

(i)

rock types such as laterites, shales and conglomerates, varieties of limestone and sandstone,
etc., which may be quarry or split with crow bars, also including any rock which in dry state
may be hard, requiring blasting but which, when wet, becomes soft and manageable by
means other than blasting.

(ii)

macadam surfaces such as water bound and bitumen / tar bound; soiling of roads, paths, etc.,
and hard core; compact moorum or stabilized soil requiring grafting tool or pick or both and
shovel, closely applied; gravel and cobble stone having maximum dimension in any one
direction between 75 mm and 300 mm;

(iii)

lime concrete, stone masonry in lime mortar and brick in lime / cement mortar below
ground level, reinforced cement concrete which may be broken up with crow bars or picks
and stone masonry in cement mortar below ground level; and

(iv)

boulders which do not require blasting having maximum dimension in any direction of more
than 300 mm, found lying loose on the surface or embedded in river bed, soil, talus, slope
wash and terrace material of dissimilar origin.

RBR-EECD

(c) Hard Rock


i & ii. Requiring Blasting & Controlled Blasting :
This shall comprise :

any rock or cement concrete for the excavation of which the use of mechanical plant and /
or blasting is required;

reinforced cement concrete (reinforcement cut through but not separated from the
concrete) below ground level; and

boulders requiring blasting.

iii. Removable for Chiseling etc., (blasting prohibited)


Hard Rock requiring blasting as described under (c) but where blasting is prohibited for any reason
and excavation has to be carried out by chiseling, wedging or any other agreed method.
(d) Marshy Soil
This shall include soils like soft clays and peats excavated below the original ground level of
marshes and swamps and soils excavated from other areas requiring continuous pumping or
bailing out of water.
General : The classification of excavated material shall be decided by the Engineer and his decision shall
be final and binding on the Contractor. Merely the use of explosives in excavation will not be considered
as a reason for higher classification until blasting is clearly necessary in the opinion of the Engineer.

295

RBR-SBBS

Andhra Pradesh Standard Data


I. Roads and Bridges
PREAMBLE
CHAPTER - 4
GRANULAR SUB-BASES, BASES (NON-BITUMINOUS) AND SHOULDERS
1. Quantities of materials provided are approximate and are meant for the purpose of estimating only.
Actual quantities shallbe as per mix design.
2. For construction of sub-base, two alternatives as under have been provided.
a.

Mix in place method

b.

Plant mix method

3. Construction of shoulders: - Earthen, Hard and Paved shoulders have been considered, the rates
applicable are for subgrade, sub-base and different layers of pavement respectively.
4. In the case of improvement of subgrade with lime stabilization, soil is assumed to be available at the
site and has not been provided for. Only lime has been catered. In the case of lime stabilization of subbase, soil has been provided to form the sub-base.
5. While providing for the rate of materials, SS Rates shall be applied in RMR keeping in view the
location of crushing plants / quarries and lead involved.
6. The quantities considered in the output are the compacted quantities. The quantities of aggregates
provided in the rate analysis under the head material are the uncompacted quantities.
7. In the case of medians, separators and footpaths, plate compactor has been catered for compaction
due to restricted space
8. It has been assumed in the case of crushed cement concrete sub-base/base that during the process of
dismantling, 25 per cent of aggregates will get segregated and only the remaining will have to be broken
/ crushed from dismantled concrete slab portions. Transportation of materials has been catered from place of
dismantling to work site. In case, site is the same, transportation cost can be deleted.
9. Separate rate for penetration coat over top layer of crushed cement concrete base has been provided, as
this item is optional

314

RBR-BASC

Andhra Pradesh Standard Data


I. Roads and Bridges
PREAMBLE
CHAPTER - 5
BASES AND SURFACE COURSES (BITUMINOUS)
1. Various alternatives for machines and materials have been provided. The one that suits a
particular situation and design may be adopted.
2. The outputs considered for construction equipment are for compacted quantities of relevant items
and not for loose quantities.
3. In case of prime coat and tack coat, average quantities of binder indicated in specifications have
been taken in MORD Specification items.
In case of prime coat and tack coat, minimum quantities of binder indicated in specifications
have been taken in MORTH Specification Items. Adjustment, plus or minus, can be made for the
variation between this quantity and the actual quantity approved by the Engineer after the preliminary
trials.
4. Tack coat and prime coat, wherever provided, are required to be measured and paid separately.
5. Cleaning of surface is a part of the item of prime coat and tack coat. As such cleaning of surface has
not been provided for bituminous courses as the same is already catered in prime/tack coat. However,
for those cases where such coats are not required to be done, cleaning of surface shall be included and
paid.
6. It is presumed that tack coat, where required, will be provided immediately preceding the
bituminous layer.
7. Rolling of bituminous courses is required to be done as per Clause 504.3.6 of MORD / MORTH
Specifications. Provision in the analysis has been made accordingly. It has been observed during actual
practice at work sites, that the availability of road roller is generally inadequate. As compaction is
the key to good construction, this point is being specifically highlighted to ensure that adequate number
of road rollers as per provision in the rate analysis are deployed at site.
8. Spreading of bituminous materials shall be done by mechanical means except in areas where a
mechanical paver cannot have access.
9. Hot Mazdoor is the one who work for Bitumen heating/spreading or spreading of hot bituminous mix.
He will be paid the same wages. However, he will be provided safety kits containing normally
gumboots, hand gloves, dark goggles, barnol, country soap, coconut oil, tarring outfits, etc. For this purpose,
additional 0.5 per cent sundries have to be provided in the analysis of rates in addition to the normal
sundries covered by overheads.
10. Where the proposed aggregates fail to pass the stripping value test, an approved adhesion agent shall
be added to the binder as per Technical Specification Clause 507.2.4, with the approval of the Engineer and
cost of the adhesion agent shall be added under the subhead of materials.
11. The Factor for usage of rollers has been taken as 0.65 in case of Bituminous Macadam only.
12. Rate analysis has been given separately using various types of bitumen, i.e., penetrations grade
S90,
S65, Polymer Modified Bitumen and Natural Rubber Modified Bitumen to facilitate preparation of Standard
Schedule of Rates.
13. The source of ail materials to be used on the project must be tested and expressly approved by the
Engineer, Road Works : 5-Bases and Surface Course (Bituminous).
14. Quantities of materials taken in the analyses are for the purpose of cost estimate only. The actual
349

RBR-BASC

quantity shall be as per job mix formula.


15. Choice of grade of bitumen shall be made as per the guidelines given in Appendix-4 of MoRT&H
Specifications.
16. The specification and requirements for modified binder with various type of modifiers have been laid
down in Clause 521 of MoRT&H Specifications and IRC: SP:53-2002 which shall be followed.
17. The guidelines given vide Annexure - A to Clause 501 of MoRT&H Specifications in regard to
protection of environment shall be followed for a particular situation.
18. The quantities taken as output of the item in the rate analysis are the compacted quantities and the
quantities of aggregates taken under the head 'material' are the un-compacted quantities for the
procurement purposes.
19. The approximate proportions by weight of different aggregates and bitumen (or by volume in unavoidable
cases) necessary to produce the intended mix satisfying the job requirements and meeting the
designated specifications are for estimating purpose only. The actual quantities should be worked out on
the basis of job mix formula adopted for the job after working out the same in the laboratory for
particular aggregates and bitumen approved by the Engineer.

350

RBR-CCPV

Andhra Pradesh Standard Data


I. Roads and Bridges
PREAMBLE
CHAPTER - 6
CEMENT CONCRETE PAVEMENT
1. Use of cement concrete pavement for rural roads is likely to be limited to small stretches. These
will, therefore, have to be constructed without use of heavy equipment, like, high capacity batching /
mixing plant and slip form pavers. Accordingly, the rate analysis is based on concrete mixer of suitable
capacity with weigh batcher, fixed side forms and screed plate and needle vibrators. High capacity
batch mix plants of 75 cum/hour (effective output) has been considered in the rate analysis of cement
concrete pavement works for MORTH Specification Items.
2. While tippers have been provided for transportation of dry lean cement concrete and rolled cement
concrete, transit truck mixers have been considered for the cement concrete pavement.
3. Cement 43 grade has been catered for the cement concrete pavement i.e., for pavement quality
concrete to get higher strength. However, for dry lean concrete, cement of 33 grade may be preferred.
4. While a slip form paver has been catered for the top layer of concrete pavement, a mechanical paver
has been provided for dry lean and rolled cement concrete.
5. The letter 'L' represents lead in km one way. This will vary from project to project and is required to
be ascertained at site to provide for the cost of carriage of the mix to the work site.
6. Provision of Plasticizer admixture to improve workability with reduced water cement ratio has been
made.
7. The rates of materials to be taken in the analysis are at site. The concrete mixer placement is also
assured close to the site of work so that transporting and placement of concrete can be done by labour
alone.
8. Quantities of materials provided in the rate analysis are for the estimate purpose. Exact
quantity of materials will be determined from the job mix formula.
9. The rates of earthwork, subgrade and sub-base may be adopted from Chapters 3 and 4 as
appropriate.

412

RBR-CWSB

Andhra Pradesh Standard Data


I. Roads and Bridges
PREAMBLE
CHAPTER - 7
CAUSEWAY AND SUBMERSIBLE BRIDGES
1. The quantities of various items may be worked out from the design and drawings.
2. Rate analysis of various items involved in the construction of concrete causeway may be taken
from relevant Chapters.
3. RCC Hume Pipes of NP-3 and NP-4 (non-pressure types) have been considered in the analysis.
4. Rate analysis for items of submersible bridges may be based on the respective items of Chapters 11, 12
and 13 dealing with bridges. Rates for guide posts may be taken from Chapter 8.
5. Rate analysis of item of river training and protection works may be based on the respective items in
Chapter 14 (Protection Works).

422

RBR-HLRD

Andhra Pradesh Standard Data


I. Roads and Bridges
PREAMBLE
CHAPTER - 8
HILL ROADS
1. The Chapter covers only the analysis of rates for items which are peculiar to hill roads. For other
items, reference may be made to relevant Chapters and analysis modified as suggested in note 2 below.
2. Extra Provision for High Altitude Areas.
Considering the loss of output of men and machines above 2100 m altitude, the following
percentage addition to cost of manpower and usage rates of machines may be considered in the analysis
of rates given in various Chapters.

Altitude in m

% of the value in
Manpower to be added to
rates

% of the value in Machine


to be added to rates

2100 to 2400

7%

3%

2401 to 2700

15%

6%

2701 to 3000

25%

9%

3001 to 3300

32%

12%

3301 to 3600

48%

15%

3601 to 3900

66%

18%

3901 to 4200

86%

21%

4201 to 4500

108%

24%

4501 to 4800

132%

27%

4801 to 5100

186%

30%

The above provisions are based on the report of Defence Institute of Physiology and Allied Sciences /
Delhi Cantt. regarding quantitative reduction in the physical work capacity of individuals working in high
altitude areas and the recommendation of the Committee on Cost of Construction set-up by Border
Roads Development Board for reduction in output of machines while working in high altitudes. The
figures are adopted from 'Standard Schedule of Rates' of BRO as applicable to high altitude areas,
3. The above addition is also to be applied on the analysis of rates for items provided in this Chapter.
4. In case of hill roads, the cut earth can be pushed down the valley in case there is no objection. In that
case, cost of disposal is not required to be provided.
5. In case of high altitudes areas above 2100 m, the percentage addition to the cost of manpower and
usage rates of machines are required to be made as per the Table given on next page.

424

RBR-PCVT

Andhra Pradesh Standard Data


I. Roads and Bridges
PREAMBLE
CHAPTER - 9
PIPE CULVERTS
1. Pipe culverts of sizes 750 mm, 1000 mm and 1200 mm dia in single row and double row which
are generally used on roads, have been included. Providing and laying of pipe has been included in the rate
analysis. Items of auxiliary works such as excavation, bedding, backfilling, concrete and masonry be
analysed, as provided under the respective sections and paid for separately.
2. Analysis has been given separately for NP3 and NP4 pipes for ease of adoption.
3. In case of RCC culverts, rates for various items of work involved such as excavation, backfilling,
masonry, cement concrete etc. have been provided under respective clauses in the chapters on
foundations, sub-structures, super-structures and river training and protection works in bridge section
of this book.
4. The choice between first class bedding and cement cradle bedding will depend on particular
situations and the approved design.
5. Cost of any river training and protection work like stone pitching, apron, curtain wall etc. may be
analysed under the respective item included in Chapter 14.
6. The joining of pipes is proposed by collar joints.
7. Chain & pulley for lifting the pipes is considered part of overheads.
8. The thickness of first class bedding has been taken as 150 mm. The height of bedding has been taken as
1/10th of overall height of pipe in the analysis. This may be modified as per thickness indicated into
approved drawing.
9. Backfilling upto 300 mm above top of the pipe shall be carefully done and the soil thoroughly
rammed, tamped or vibrated in layers not exceeding 150 mm.
10. Head walls and other ancillary works shall be costed under respective clauses.
11. The height of filling above the top of pipe shall not be less than 600 mm

434

RBR-TSRA

Andhra Pradesh Standard Data


I. Roads and Bridges
PREAMBLE
CHAPTER - 10
TRAFFIC SIGNS, MARKINGS AND OTHER APPURTENANCES
1. Rate analysis for fencing provides for Barbed wire fencing with R.C.C. M 15 grade concrete post.
2. Rate analysis for fencing has been done for two different heights, i.e., 1.20m and 1.80m. Any of these
two can be adopted depending upon a particular situation and design.
3. Rate analysis for fencing provides for three types as under :
a. Barbed wire fencing
b. Welded steel wire fabric with mesh size of 75 x 25 mm
c.

Welded steel wire fabric with mesh size of 75 x 50 mm

4. Kerbstone laying and road marking has been provided for laying by mechanical means
5. Backfilling of foundation of boundary pillars has been proposed with stone spalls, tightly packed
and compacted.
6. The item pertaining to road traffic signals has not been analysed as this is a specialized work and
rates can be obtained from firms having specialisation for design and installation of this work.
7. Two supports have been provided for direction and place identification signs where size is more
than 0.9 square metres. Only one support is provided for size upto 0.9 square metres.
8. The traffic signs proposed are of retro- reflectorised types made of encapsulated lens type
reflective sheeting fixed over aluminum sheeting and semi-reflective type on M.S. sheet
9. The size and location of traffic signs shall be as per IRC:67.
10. Separate rate analysis has been made for tubular steel railing with RCC posts and MS steel posts.
11. For metal beam crash barrier, a W shaped beam of size 311 x 83 mm flange width made with
structural steel corrugated plate 3 mm thick and having a length of 4.5 m has been provided, over a
channel post of 150 x 75 x 5 mm with a spacer of channel section 150 x 75 x 5 mm, 330 mm long.
12. Printing of letters and signs on item Nos. 18 to 21 is required to be measured and paid separately. A
separate rate analysis for lettering has been prepared and included in this chapter for this purpose.
13. The analysis for rigid, semi-rigid and flexible crash barriers have been included.
14. Provision has been made for a crane for installation of overhead signs.
15. Separate rate analysis have been made for Tubular steel railing with RCC posts and MS steel posts.
16. The organization and financial aspects are required to be finalized in consultation with administrative
and traffic authorities
17. The rate for the message display board for gantry mounted variable message sign is required to be
ascertained from the market, this being a commercially produced item by specialised firms.
18. The rate analysis for traffic impact attenuators at abutments and piers have been included.
19. In the case of road signs and direction boards, the depth of foundation and quantity of cement
concrete provided in the rate analysis are indicative. These may be suitably increased in areas of
higher wind velocities, like, coastal areas.

439

RBR-TSRA

20. Ducts for Utility Services Along and Across the Expressway/Highway
The running metre cost of duct along the road including inspection chambers (where applicable) or
across the road will depend upon the approved design. The various items involved are earthen work,
plain cement concrete, brick stone masonry, reinforcement cement concrete, form work, steel
reinforcement, laying of pipe line (where duct is of pipe) and cast iron/RCC cover for the inspection
chamber. The rate for these items are available under respective clauses which can be applied and
running metre cost of duct worked out as per the approved design and drawing for particular situations. In
case cast iron cover for the inspection chamber, the rate can be ascertained from the market for the size
provided in the design and approved drawings.
21. Noise Barriers
Noise barrier can be provided in the form of a brick wall of a suitable height as per the site requirement and
approved design. The items involved for the construction of this barrier like earthwork, brick masonry, plain
cement concrete, etc. are available in the Data Book, which can be applied to arrive at the cost of noise
barrier based on the design adopted.
Alternatively, wherever space permits, cluster of trees, shrubs and plants can be grown by the road side 6
m away from the edge of the roadway. This will intercept the annoying sound waves and fumes from road
vehicles

440

RBR-FNDN

Andhra Pradesh Standard Data


I. Roads and Bridges
PREAMBLE
CHAPTER-11
FOUNDATION
1. Excavation for structures has been provided both by manual and mechanical means. The
rate relevant to a particular situation may be adopted.
2. The earth excavated from foundation has been proposed to be backfilled and balance quantity
utilized for road work locally except for marshy soil where disposal has been provided
3. For excavation in marshy soil, extra provision of labour for filling with carted earth has been
provided in a separate item. Cost of carted earth may be worked out separately if the same is not
available from the adjoining area.
4. The rock surface for foundations is to be prepared which has been analysed accordingly.
5. In case of rock, excavation has been considered upto a depth of 1500 mm for rock of ultimate
crushing strength of 10 Mpa or more, which shall be reckoned as hard rock.
6. Dewatering has been provided in excavation for foundation on percentage basis. In case less
dewatering is required or is not required at all for a particular site condition, the same may be
reduced/omitted.
7. Mixing of cement concrete has been considered by using concrete mixer with weigh batching
facility fitted with water measuring device and batching plant. Alternatively mixing of concrete with
Batch Mixing Plant 30/40 cum per hour is proposed. The rate can be adopted depending upon
availability of equipment and as approved by the Engineer.
8. Concrete batching plant is generally placed within one km of the bridge site. In case of longer lead,
transportation cost may be worked out based on tonne km.
9. The coarse and fine aggregate for cement concrete shall be as per IS:383.
10. Description of items has been given very briefly. Relevant clauses of MORT&H / MORD
Specifications may be referred for detailed specification.
11. The Data for well foundation has been included for diameter varying from 6 m to 12 m. Well for
twin D type has also been included.
12. Pneumatic sinking is a specialised job. All safety precaution as per 1S:4138 are required to be taken
Medical supervision for such works is considered very essential. Depth of pneumatic sinking has been
restricted to 30 m below normal water level.
13. Rate analysis for various type of piles like bored cast-in-situ, driven precast RCC pile and driven
steel piles of H section have been included. If the steel casing in case of driven pile is required to be
retained the same is required to be priced separately.
14. Pile driving rigs including vibratory hammers are assumed to be self contained with power units
and necessary accessories required for driving.
15. The quantity of concrete which is required to be stripped off upto a minimum height of 600 mm
above the designed top level of the pile has been taken into account in the rate analysis.
16.

The amount required for testing of piles shall be depending upon market situation.

17.

The levelling course below the pile cap is proposed with M 15 grade concrete.

18. Steel reinforcement for cement concrete works are required to be provided separately. The rate for
the same has been analysed.
482

RBR-FNDN

19. Appendix-4 of IRC: 78-2000 may be referred regarding precautions to be taken during sinking of
wells.
20. In case of blasting during sinking of wells the inner face of the curb is required to be protected with
the steel plates of thickness not less than 10 mm upto top level of well curb. For height above top of
curb, the thickness of steel plate may be reduced to 6 mm. This extra height of steel lining should be
limited to 3 m.
21. The concrete mix used in bottom plug shall have a minimum cement content of 330 kg/cum and a
slump of about 150 mm to permit easy flow of concrete through tremie to fill-up all cavities.
22. Necessary safety precautions shall be taken for excavation on open foundations for which guidance
may be taken from IS:3764.
23. A levelling course of 100 mm thickness in M 10 (1:3:6) shall be provided before laying open
foundations.
24. In the case of open foundation, dewatering shall not be permitted from the time of placing of concrete
upto 24 hours after placement.
25. In case of open foundations in rock, the trenches around the footing shall be filled-up with
concrete of M 15 grade upto a level of 0.6 m for hard rock and 1.5 m for soft rock above the foundation
level. The portion above this may be filled by boulders grouted with cement.
26. When there are two or more compartments in a well, the lower edge of the cutting edge of the
middle stems of such wells shall be kept about 300 mm above that of outer stems to prevent rocking.
27. The well curb shall be in RCC of mix not leaner than M 25 grade with minimum steel
reinforcement of 72 kg/cum excluding bond rods.
28.

No dewatering shall be carried out within 7 days of casting of bottom plug.

29. In case of cement concrete piles, the minimum grade of concrete shall be M 35 with minimum
cement content of 420 kg/cum.
30. The top of the pile shall project 50 mm into the pile cap and reinforcement of pile shall be fully
anchored in pile cap.
31. The minimum thickness of pile cap should be atleast 0.6 m or 1.5 times the diameter of the
pile whichever is more.
32.

Guidance for piles is to be obtained from IS.2911.

33. Concrete in driven cast-in-situ piles shall be cast upto a minimum height of 600 mm above the
designed top level of pile, which shall be stripped off to obtain sound concrete either before final set or after
3 days.
34. The top of the bottom plug shall be atleast 300 mm above top of curb
35. In remote areas, for isolated slab culvert/box culvert upto 2 m span, concrete can be hand mixed
in accordance with Clause 806 of MORD Specifications. Therefore, in the analysis, for items of
concrete, the alternative of hand mixing has also been considered.
36. Steel reinforcement for cement concrete work is required to be provided separately. The rate for
the same has been analysed using HYSD, TMT and MS bars.
37. Necessary safety precautions shall be taken for excavation for open foundation for which
guidance may be taken from IS:3764. Cost of shoring and shuttering has been provided on
percentage basis, which may be adjusted according to site condition.
38. For brick masonry work, clay fly ash bricks of approved type can be used in accordance with
Section 600 of MORD Specifications and rate may be adopted accordingly.
39. Rates of all materials used in the analysis are at site and should include cartage from crusher.

483

RBR-SBST

Andhra Pradesh Standard Data


I. Roads and Bridges
PREAMBLE
CHAPTER - 12
SUBSTRUCTURE
1. Although, Substructures are generally constructed in cement concrete, the rate analysis for brick and
stone masonry in CM 1:3 have also been included which can be adopted if permitted by design.
2. The cost of formwork will vary with the height and cross-section of the substructure. Provision has
been made accordingly.
3. As the higher grade of concrete is costlier, the provision made for formwork on percentage basis
has been suitably adjusted to make it compatible with other grades.
4. Filter media and backfilling behind abutment are required to be provided as per guidelines in
IRC:78-2000.
5. Bearing shall be set truly level so as to have full and even seating.
6. The bearing should be procured only from those manufacturers who have been pre-qualified by
MORTH.
7. For spans in gradient, the soffit shall be made horizontal specially at the supports and the bearing, where
provided, shall be placed horizontally.
8. Weep holes shall be provided as per specifications.
9. For electrometric bearings, the concrete surface shall be leveled such that the variation is not more than
1.5 mm from a straight edge placed in any direction across the area.
10. Bridge bearing, being commercial items produced by specialized firms with imported technology and
parts, the rates for the same are required to be ascertained from the market for the approved design and
technical specifications.
11. The bottoms of girders resting on the bearing shall be plane and truly horizontal.
12. For spans in grade, the bearing shall be placed horizontal by using sole plates for suitably designed
RCC pedestals.
Note: Nos. 7 to 18 of Chapter 11 will hold good for this Chapter also

548

RBR-SPST

Andhra Pradesh Standard Data


I. Roads and Bridges
PREAMBLE
CHAPTER - 13
SUPERSTRUCTURE
1. The rate for wearing coat has been analysed as under in accordance with the provisions of
MORD / MORTH Specifications:
a)

Cement concrete wearing coat

b)

Ashphaltic concrete wearing coat

c)

Bitumen mastic wearing coat

The item may be selected as per approved design. In case the thickness of wearing coat is different
from that analysed, the rate for the desired thickness may be worked out on pro-rata basis.
2. The rate analysis has been done for the following types of railings & parapet, which can be
adopted as per approved design:
(i)

R.C.C. railing

(ii)

M.S. railing

(iii)

Pipe railing (suitable for submersible bridges)

(iv)

Brick masonry parapet

(v)

Stone masonry parapet

(vi)

P.C.C. parapet

3. As per the MORD Specifications, the type of superstructure envisaged for minor bridges and
culverts for rural roads are R.C.C. slabs and box culverts not exceeding 15 m span, rates for which
have been analysed. Stone/Brick masonry arches can be adopted where hard strata is available at
shallow depth. R.C.C. arches can also be adopted as per IRC:SP:20. Hence rates for these types of
arches for span length upto 15 m have been analysed.
4. For composite type of superstructure, comprising of steel beams/built-up sections & R.C.C. deck
slab, analysis has been done for steel section separately.
5. For slab culverts and minor bridges of spans not more than 10 m, buried joint/filler joint may be
adequate. For relatively longer spans and for highly seismic intensity areas, electrometric slab
seal/compression seal joint may be provided as per the MORD Specifications. Rates have to be
analysed accordingly.
6. In remote areas, for slab culverts and box culverts upto 2 m span, concrete used in superstructure
can be hand mixed with 10 per cent extra cement at contractor's cost in accordance with Clause 806
of MORD Specifications. Hand mixing shall not be otherwise permitted.
7. Slab seal/compression seal expansion joints are specialized items commercially produced by a
number of firms. The rates for such items must be ascertained from firms pre-qualified by MORTH.
8. The length of drainage spout has been provided in such a way that it is connected to the drainage
system on the ground in case of flyovers and there is no splashing of water on the structure in case of
bridges.
9. The rate for anti-corrosive treatment is required to be ascertained from firms specialised in this work. In
this connection Circular No. RW/NH-34041/44/91-S&R dated 21.3.2000 of Ministry of Road Transport and
Highways may be referred for further details.

571

RBR-SPST

10. Expansion joints involving movements exceeding 40 mm are specialised readymade items commercially
produced by reputed firms with imported technology and parts. The rates for such joints are required to be
ascertained from the firms pre-qualified by the Ministry.
11. The rate analysis for pre-cast and pre-tensioned girders has also been included.
12. The rate analysis for prestressed cement concrete of M 60 grade has also been included which can be
adopted for bridges with innovative design/construction.
13. MORT&H letter No. RW/NH-34059/1/96 S&R dated 30.11.2000 and subsequent corrigendum dated
25.1.2001 may be referred for detailed specifications and provisions for various types of expansion joints.
14. Supply of new type of expansion joint may be obtained on the basis of competitive bidding from
amongst the suppliers pre-qualified by the Ministry of Road Transport and Highways. Further, a
warranty of 10 years of trouble free performance may be insisted from the suppliers.
15. For bridges having wide deck/span length of more than 120 m or/and involving complex movements /
rotations in different directions/planes, provision of special type of modular expansion joints such as swivel
joists joints are required for which firms specialised in this field may be consulted. Such cases will require
prior approval of Ministry
16. Note 7 to 18 of Chapter 11.

572

RBR-PTWK

Andhra Pradesh Standard Data


I. Roads and Bridges
PREAMBLE
CHAPTER-14
PROTECTION WORKS
1. Three types of aprons as under have been catered for:
(a) Boulder apron laid dry
(b) Boulder apron laid in wire crates
(c) Apron laid in cement concrete blocks of M 15 grade
2. Pitching proposed is of the following types:
(a) Brick pitching
(b) Boulder pitching
(c) CC Block pitching
3. A toe wall for toe protection of pitching can be either in random rubble masonry or in nominal mix
cement concrete M 10 / M 15, or in brick masonry. Depending upon the design, the rates may be
adopted.
4. Flooring has been proposed in dry rubble stone, rubble stone laid in cement mortar 1:3, cement
concrete blocks M 15 and brick on edge laid in cement mortar (CM) 1:3.
5. Curtain walls proposed are of the following types:
(a) Brick masonry in CM 1:4
(b) Coursed rubble stone masonry (1sl sort) is CM 1:3
(c) Cement concrete M 10 / M 15 grade
6. The rate analysis also include protection works using timber/bamboo as per details provided by
Assam PWD and may be used for guidance.
7. The rate analysis for gabion structures comprising of stone boulders laid in wire crates have been
included. Such structures are suited as retaining structures and for erosion control in river training
works especially for situations where some settlement of foundation in anticipated. These structures
can adjust in minor settlements, being flexible structures, without losing their functional requirement.

607

RBR-MTRD

Andhra Pradesh Standard Data


I. Roads and Bridges
PREAMBLE
CHAPTER - 15
MAINTENANCE
1. In the case of rain cuts, it has been assumed that some material cut by rain, approximately 25 per
cent will be available at site which can be retrieved and re-used and the balance 75 per cent is required to
be provided as fresh material.
2. For making up earthen shoulders, it has been assumed that on an average 150 mm filling will be
required. Similarly, for stripping of excess soil from shoulder, an average depth of 75 mm has been
assumed.
3. In the case of chocking of drain, it has been assumed that half the depth of drain has been filled with
earth/debris, which requires clearance.
4. Pothole repairs and patchwork are provided to be done by using Mix all 6/10 M.T.
5. In case of maintenance of Gravel and W.B.M. surfaces, it has been assumed that 25 per cent
material will be available at site, which can be retrieved and re-used and the balance 75 per cent is
required to be provided as fresh material.
6. The items of periodical renewal by premix carpet and surface coating have also been included in the
rate analysis for guidance of field Engineers. The detailed analysis of various items of bituminous
works is given in Chapter 5 and rates can be taken from there as appropriate. Additional provision of
patch repair and profile correction varying from 10 per cent to 30 per cent of the material of premix
carpet/surface dressing may be made in the estimate of periodical renewal.
7. During the process of landslide clearance on hill roads, it has been assumed that earth will be
disposed off by the dozer on the valley side. In case there is any objection to this arrangement due to
particular site conditions, resources like loader and tipper will have to be provided for disposal of
earth/debris for the lead involved.
8. The items like slurry seal, fog spray, crack prevention courses, surface dressing for maintenance
works have already been included in Chapter-5 and are not being repeated in this chapter.
9. The cost of other items like repair of ruts and undulation maintenance of earthen shoulders, cross
drainage works, minor and major bridges and miscellaneous items like turfing and arboriculture, painting
and lettering on km stones, repair to signage, repair to footpath, street lighting, railing, dividers, separators
and under passes for pedestrians has been given in the "Report of the Committee on Norms for
Maintenance of Roads in India" published by IRC in January 2001 which may be referred for guidance.
10. The repair items related to bridges have been given in Chapter-18.

620

RBR-GSRE

Andhra Pradesh Standard Data


I. Roads and Bridges
PREAMBLE
CHAPTER - 16
GEOSYNTHETICS AND REINFORCED EARTH
1. The specifications for geosynthetics which includes geotextiles, geogrids, geonets, geomembranes
and geocomposites shall be as per section 700 of MoRTH Specifications.
2. The geotextile proposed for sub-surface drain shall satisfy the requirements given in Clause 702.2.3.
3. Care shall be taken to ensure that the geotextile or core material is not exposed to dry light for more
than a cumulative total of 50 hours. Bitumen overlay shall follow on the same day where paving fabric is
laid.
4. The size of mesh opening for gabions and mattresses laid with geogrids and geonets shall be between
35 mm and 100 mm.
5. The size of the boulders shall be at least 100 mm or double the size of the aperture whichever is larger.
6. The boulders shall be laid in crates as per the methodology given in Clause 2503.3.
The usual size of gabions in aprons is 1 m x 5 m with a height of 600 mm and baffles at 1 m centers

632

RBR-HRTC

Andhra Pradesh Standard Data


I. Roads and Bridges
PREAMBLE
CHAPTER - 17
HORTICULTURE

1.
The items of turfing with sods and seeding and mulching have been included in the chapter of
earthwork.
2.
The analysis of rates for grassing of lawns and hedges has been included, as the same may be
needed for resting places on highways.
3.

Five types of tree guards as under have been provided:


a) Half brick circular type
b) Tree guards made from empty bitumen drums 1.30 m high
c) Tree guards made from empty bitumen drums 2.00 m high
d) Tree guards with MS flat iron
e) Tree guards with MS angle and 3 mm steel wire welded on MS flat and bolted to angle iron
posts

Selection from above may be made as per actual situation and design.
4.
Analysis of rates for wrought iron and mild steel welded work has been included to cater for
any miscellaneous work in connection with horticulture, fencing and traffic sign.
5.
Though the estimate for compensatory afforestation is made by the forest department, the rate for
this item has been analysed and included for the purpose of estimation.
6.
In the rate analysis of some items, the quantities of sub-items involved in that analysis, like,
excavation for foundation, foundation concrete, painting, lettering, etc. have been given. The rates for such
items may be taken from relevant chapters where the same have already been analysed.
7.
As grass and plantation need more care, one mate has been provided for every 10 mazdoors in
case of horticulture.

637

RBR-RPRH

Andhra Pradesh Standard Data


I. Roads and Bridges
PREAMBLE
CHAPTER - 18
REPAIR AND REHABILITATION
1. Removal of cement concrete wearing coat and asphaltic wearing coat has been proposed with
pneumatic breakers.
2. The rate for external prestressing has been analysed for three different spans of 25, 50 and 100 m.
3. Sealing of cracks has been proposed with cement grout, cement mortar (1:1) grout and epoxy grout
by injecting with grout pump through nipples.
4. Bonding of new concrete with old concrete is proposed with epoxy resin.
5. The repair and replacement of following structures has been included:
a. Bridge bearings
b. Expansion Joints
c. Concrete Railing
d. Mild steel railing
6. Crash barrier

646

A.P. REVISED STANDARD DATA

PART-II

ROADS AND BRIDGES

Rate Analysis as per Observations made by Engineering Staff Collage of India for Crushing of Stone Aggregate using
Primary, Secondary - Crushers & Conveyors
Data: Sizes of coarse aggregate considered for data rate analysis.
80 mm size
40 mm size
20 mm size
10 to 4.75 mm size range
Dust (powder)
1 No. primary jaw crusher of 120 tons / hour rated capacity each and 2 Nos. secondary jaw crushers are used
Single shift working for aggregate crushing
Daily output of crushing system with 70% efficiency and 50 minutes per hour working
Daily out turn = 1 x 120 x 0.70 x 8.00 x 50/60 = 560 tons or 350 cum
2 Nos secondary jaw crusher are used for recrushing over size aggregate
Capital cost of Crusher system : Rs. 72,82,167.00
Requirement of electric power : energy consumption per hour in kw.hr. = 190
Capital cost of Conveyer System (Excluding cost of belts) : Rs. 23,67,416.00

RATE ANALYSIS
Unit 343 cum

A. MATERIALS:

Sl.
Particulars
No
1. Cost of Rubble

(560 tonns/350 cum including 2% wastage)

Unit

Quantity

Rate in
Rs.

cum

350

175

hour

77.35

hour

42.97

788.72

2. Use Rate of Jaw plates 36x24


Reconditioning charges @ 10%
3. Use Rate Jaw plates 42x12
Reconditioning charges @ 10%

Amount in
Rs.
61250

C) LABOUR:

Sl.No.

Particulars

Unit

Quantity

Rate in Rs.

165

Amount in
Rs.
1320

1.

Crew for Crusher system

hour

618.8

2.

Crew for conveyor system

hour

83

664

61.88

3.

Mazdoor

day

5 Nos.

101

505

343.76

Total cost of labour

34.38

4. Use Rate of Screens

hour

98.59

5. Use Rate of Conveyer belt 1000 mm

hour

24.9

199.2

6. Use Rate of Conveyer belt 600 mm

hour

12.46

99.68

a.

Cost of materials

63,722.00

7. Use Rate of Conveyer belt 500 mm

hour

8.3

66.4

b.

Hire Charges of Machinery

24,960.00

99.68

c.

cost of labour

2,489.00

159.44

d.

Cost of civil wokrs @ 5%

4,559.00

Total cost of materials

63,721.94

e.

Total cost of 343 cum

Say

63,722.00

8. Use Rate of Conveyer belt 750 mm

hour

12.46

9. Use Rate of Conveyer belt 400 mm

hour

19.93

ABSTRACT

Rs. 95,730.00

Rates for coarse aggregates

B. MACHINERY:

Sl.
No.

2,489.00

Particulars

1. Crusher system Hire Charges


Fuel/ Energy charges
2. Conveyor System Hire Charges
Fuel/ Energy charges

Unit

Quantity

Rate in
Rs.

Amount in
Rs.

hour

1500

12000

hour

1004

hour

353

hour

263

Total cost of machinery

Crushing pattern %

Production in
cum / shift

% Cost
distribution

Amount

80 mm size

24

82.3

15

14360

Rs.174.00

8032

40 mm size

32

109.8

34

32548

Rs.296.00

2824

20 mm Size

22

75.5

33

31591

Rs.418.00

2104

10 - 4.75
mm
Dust

12

41.1

15

14360

Rs.349.00

10

34.3

2871

Rs. 84.00

100%

343.0 cum

100%

95730

Rs.279.00

24960

Size

Cost per
cum

RBR-LUCC

Andhra Pradesh Standard Data


I. Roads and Bridges
Chapter -1
LOADING, UNLOADING, CARRIAGE and CRUSHING OF MATERIALS
Index-code

S. No

Description

Unit

Quantity

day
day

0.520

hour

0.500

Rate Amount
Rs.
Rs.
5

Remarks
7

Loading and Unloading of Lime, Aggregate, Stone Boulder,


Brick Aggregate, Kankar, Building Rubbish, Crushed Slag,
Stone for Masonry Work by Manual Means including
hirecharges of truck 10t for waiting period

RBR-LUCC-1
i

Loading of Lime, Aggregate, Stone Boulder, Brick Aggregate,


Kankar, Building Rubbish, Crushed Slag, Stone for Masonry
Work by manual means including a lead upto 30 m

Unit = cum
Taking output = 5.5 cum
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Truck 10t
c&d) Overheads & Contractors Profit
Cost for 5.5 cum = a+b+c+d
Rate per cum = (a+b+c+d)/5.5
ii

Loading of Earth, Sand, Moorum, Manure, Flyash by manual


means including a lead upto 30 m

Unit = cum
Taking output = 5.5 cum
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Truck 10t
c&d) Overheads & Contractors Profit
Cost for 5.5 cum = a+b+c+d
Rate per cum = (a+b+c+d)/5.5
iii

RBR-LUCC-2

day

0.260

hour

0.250

Unloading of Lime, Aggregate, Stone Boulder, Brick Aggregate,


Kankar, Building Rubbish, Crushed Slag, Stone for Masonry
Work by manual means including a lead upto 30 m

Unit = cum
Taking output = 5.5 cum
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Truck 10t
c&d) Overheads & Contractors Profit
Cost for 5.5 cum = a+b+c+d
Rate per cum = (a+b+c+d)/5.5
iv

day

day

day

0.260

hour

0.250

Unloading of Earth, Sand, Moorum, Manure, Flyash by manual


means including a lead upto 30 m

Unit = cum
Taking output = 5.5 cum
a) Labour
day
Mate
day
Mazdoor (Unskilled)
b) Machinery
hour
Truck 10t
c&d) Overheads & Contractors Profit
Cost for 5.5 cum = a+b+c+d
Rate per cum = (a+b+c+d)/5.5
Loading and Unloading Lime, Aggregate, Stone
Boulder, Brick Aggregate, Kankar, Building Rubbish,
Crushed Slag, Stone for Masonry Work by Mechanical
Means including hire charges of Tipper 10t for waiting
period and Front end loader 1cum capacity for loading
period.
Loading of Lime, Aggregate, Stone Boulder, Brick
Aggregate, Kankar, Building Rubbish, Crushed Slag,
Stone for Masonry Work by mechanical means
including a lead upto 30 m
Placing tipper at loading point, loading with front end loader
excluding time for haulage and return trip.
Unit = cum
Taking output = 5.5 cum
Time required for
Min
i) Positioning of tipper at loading point
ii) Loading by front end loader 1 cum bucket capacity @ 45 Min
cum per hour
Min
iii) Maneuvering, reversing, dumping and turning for return

0.130
0.166

1.000
7.330
-

264

RBR-LUCC

Index-code

S. No

Description

Unit

Quantity

3
Min

4
2.000

Min

10.330

iv) Waiting time, unforeseen contingencies, etc.


Total
a) Machinery
Tipper 10 t capacity
Front end-loader 1 cum bucket capacity @ 45 cum per hour

ii

iii

hour

0.172

hour

0.122

Min

1.000

Min

3.300

Min

2.000

Min
Total
a) Machinery
hour
Tipper 10 t capacity
Front end-loader 1 cum bucket capacity @ 100 cum per hour
hour
c&d) Overheads & Contractors Profit
Cost for 5.5 cum = a+b+c
Rate per cum = (a+b+c)/5.5

6.300

c&d) Overheads & Contractors Profit


Cost for 5.5 cum = a+b+c
Rate per cum = (a+b+c)/5.5
Loading of Earth, Sand, Moorum, Manure, Flyash by
mechanical means including a lead upto 30 m.
Placing tipper at loading point, loading with front end loader
excluding time for haulage and return trip.
Unit = cum
Taking output = 5.5 cum
Time required for
i) Positioning of tipper at loading point
ii) Loading by front end loader 1 cum bucket capacity @
100 cum per hour
iii) Waiting time, unforeseen contingencies, etc.

Rate Amount
Rs.
Rs.
5

Remarks
7

0.105
0.055

Unloading of Earth, Sand, Lime, Moorum, Aggregate, Stone


Boulder, Brick Aggregate, Kankar, Building Rubbish, Manure,
Crushed Slag, Flyash, Stone for Masonry Work by mechanical
means (unloading by tipping).

Unit = cum
Taking output = 5.5 cum
Placing tipper at unloading point excluding time for haulage
and return trip
Time required for
i) Positioning of tipper at unloading point
ii) Manoeuvering, reversing, dumping and turning for return

Min

1.000

Min

2.000

265

RBR-LUCC

Index-code

S. No

Description

Unit

Quantity

3
Min

4
2.000

Min

5.000

hour

0.080

iii) Waiting time, unforeseen contingencies, etc.


a) Machinery
Tipper 10 t capacity
c&d) Overheads & Contractors Profit
Cost for 5.5 cum = a+b+c
Rate per cum = (a+b+c)/5.5
iv

RBR-LUCC-3
i

ii

Remarks
7

Loading and Unloading of Stone Boulder/Stone cum


aggregates/Sand/Kanker/Moorum.
Placing tipper at loading point, loading with front end
loader, dumping, turning for return trip, excluding time for
haulage and return trip
Unit = cum
Taking output = 5.5 cum
Time required for
i) Positioning of tipper at loading point
ii) Loading by front end loader 1 cum bucket capacity @
25 cum per hour

Rate Amount
Rs.
Rs.

Min
Min

1.000
13.000

iii)
Maneuvering, reversing, dumping and turning for Min
return
Min
iv) Waiting time, unforeseen contingencies etc
Min
Total
a) Machinery
Tipper 5.5 tonnes capacity
hour
Front end-loader 1 cum bucket capacity @ 25 cum/hour
hour
c&d) Overheads & Contractors Profit
Cost for 5.5 cum = a+b+c
Rate per cum = (a+b+c)/ 5.5
Note : Unloading will be by tipping.

2.000

Loading and Unloading of Boulders by Manual Means


Unit = cum
Taking output = 5.5 cum
a) Labour
Mate
day
Mazdoor for loading and unloading
day
b)
Machinery
Tipper 5.5 tonne capacity
hour
c&d) Overheads & Contractors Profit
Cost for5.5 cum = a+b+c+d
Rate per cum = (a+b+c+d)/5.5
Note : Unloading will be by tipping.
Loading, Unloading and Stacking of Bricks by Manual
Means including hire charges of Truck 10t for waiting
period.
Loading of Bricks by manual means including a lead
upto 30 m
Unit = 1000 Nos.
Taking output = 2000 Nos.
a) Labour
day
Mate
day
Mazdoor (Unskilled)
b) Machinery
hour
Truck 10t
c&d) Overheads & Contractors Profit
Cost for 2000 Nos. = a+b+c+d
Rate for 1000 bricks = (a+b+c+d)/2
Unloading and Stacking of Bricks by manual means
including a lead upto 30 m
Unit = 1000 Nos.
Taking output = 2000 Nos.
a) Labour
day
Mate
day
Mazdoor (Unskilled)

4.000
20.000
0.330
0.330

0.110
0.750
0.750

0.260
0.330

0.260

266

RBR-LUCC

Index-code

S. No

Description

Unit

Quantity

hour

0.330

b) Machinery
Truck 10t
c&d) Overheads & Contractors Profit
Cost for 2000 Nos. = a+b+c+d
Rate for 1000 bricks = (a+b+c+d)/2
4

Rate Amount
Rs.
Rs.
5

Remarks
7

Loading, Unloading and Stacking of Cement by Manual Means


including hire charges of Truck 10t for waiting period.

RBR-LUCC-4
i

Loading of Cement by manual means including a lead upto 30


m

Unit = t
Taking output = 10 t
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Truck 10t
c&d) Overheads & Contractors Profit
Cost for 10 t = a+b+c+d
Rate per tonnes = (a+b+c+d)/10
ii

RBR-LUCC-5
i

day

1.560

hour

1.000

Unloading, stacking of Cement by manual means including a


lead upto 30 m

Unit = t
Taking output = 10 t
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Truck 10t
c&d) Overheads & Contractors Profit
Cost for 10 t = a+b+c+d
Rate per tonnes = (a+b+c+d)/10
iii

day

day

day

1.560

hour

1.000

Loading & unloading of Cement including stacking by manual


means including a lead upto 30 m.

Unit = t
Taking output = 10 t
a) Labour
day
Mate
day
Mazdoor (Unskilled)
b) Machinery
hour
Truck 10t
c&d) Overheads & Contractors Profit
Cost for 10 t = a+b+c+d
Rate per tonnes = (a+b+c+d)/10
Loading, Unloading and Sticking of Structural Steel and
Steel Bars by manual means including hire charges of
Truck 10t for waiting period.
Loading of Structural Steel, Steel Bars by manual
means including a lead upto 30 m
Unit = t
Taking output = 10 t
a) Labour
day
Mate
day
Mazdoor (Unskilled)
b) Machinery
hour
Truck 10t
c&d) Overheads & Contractors Profit
Cost for 10 t = a+b+c+d
Rate per tonnes = (a+b+c+d)/10

2.080
2.000

1.870
1.000

267

RBR-LUCC

Index-code

S. No

Description

Unit

Quantity

ii

iii

RBR-LUCC-6
i

ii

RBR-LUCC-7

Unloading of Structural Steel, Steel Bars by manual


means including a lead upto 30 m
Unit = t
Taking output = 10 t
a) Labour
day
Mate
day
Mazdoor (Unskilled)
b) Machinery
hour
Truck 10t
c&d) Overheads & Contractors Profit
Cost for 10 t = a+b+c+d
Rate per tonne = (a+b+c+d)/10

Rate Amount
Rs.
Rs.
5

Remarks
7

1.870
1.000

Loading, unloading and Stacking of Structural Steel, Steel Bars


by manual means including a lead upto 30 m

Unit = t
Taking output = 10 t
a) Labour
day
Mate
day
Mazdoor (Unskilled)
b) Machinery
hour
Truck 10t
c&d) Overheads & Contractors Profit
Cost for 10 t = a+b+c+d
Rate per tonnes = (a+b+c+d)/10
Loading and Unloading of Bitumen Drums by Manual
Means including hirecharges of truck 10t for waiting
period
Loading of Bitumen Drums by manual means including
a lead upto 30 m
Unit = t
Taking output = 10 t
a) Labour
day
Mate
day
Mazdoor (Unskilled)
b) Machinery
hour
Truck 10t
c&d) Overheads & Contractors Profit
Cost for 10 t = a+b+c+d
Rate per tonnes = (a+b+c+d)/10
Unloading of Bitumen Drums by Manual Means
including a lead upto 30 m
Unit = t
Taking output = 10 t
a) Labour
day
Mate
day
Mazdoor (Unskilled)
b) Machinery
hour
Truck 10t
c&d) Overheads & Contractors Profit
Cost for 10 t = a+b+c+d
Rate per tonnes = (a+b+c+d)/10
Note : The weight is inclusive of the self weight of drum
Loading and Unloading of Timber by Manual Means
including hirecharges of truck 10t for waiting period

2.080
2.000

1.660
1.250

1.250
1.250

(i) Loading of Timber by manual means including a lead upto 30 m

Unit = t
Taking output = 5 t
a) Labour
Mate
Mazdoor (Unskilled)

day

day

1.040

268

RBR-LUCC

Index-code

S. No

Description

Unit

Quantity

hour

1.000

b) Machinery
Truck 10t
c&d) Overheads & Contractors Profit
Cost for 5 t = a+b+c+d
Rate per t = (a+b+c+d)/5
ii

Rate Amount
Rs.
Rs.
5

Remarks
7

Unloading of Timber by manual means including a lead upto 30


m

Unit = t
Taking output = 5 t
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Truck 10t
c&d) Overheads & Contractors Profit
Cost for 5 t = a+b+c+d
Rate per t = (a+b+c+d)/5

day

day

1.040

hour

1.000

Note : Density of wood has been assumed as 900 kg per cum. If the
density is less the output may be reduced proportionately.

RBR-LUCC-8

Loading and Unloading of C.C. Blocks, Kerb, etc.


including hirecharges of truck 10t for waiting period
i

RBR-LUCC-9

Loading with care C.C. Blocks, km Stone, 200 m Stone,


Boundary Pillar, Kerb, Channel, Bond Stone, etc. by manual
means including a lead upto 30 m

Unit = cum
Taking output = 5.5 cum
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Truck 10t
c&d) Overheads & Contractors Profit
Cost for 5.5 cum = a+b+c+d
Rate per cum = (a+b+c+d)/5.5
ii Unloading with care C.C. Blocks, km Stone, 200 m
Stone, Boundary Pillar, Kerb, Channel, Bond Stone, etc.
by manual means including a lead upto 30 m
Unit = cum
Taking output = 5.5 cum
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Truck 10t
c&d) Overheads & Contractors Profit
Cost for 5.5 cum = a+b+c+d
Rate per cum = (a+b+c+d)/5.5
Loading and Unloading of RCC Hume Pipes including
hirecharges of truck 10 t for waiting period and Crane
3t capacity including all labour charges.
i Loading of RCC Hume pipes by mechanical means
including a lead upto 30 m
A 1000 / 1200 mm dia RCC Hume pipe
Unit = per pipe
Taking output = 9 pipes
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Truck 10t
Crane (3 T)
c&d) Overheads & Contractors Profit
Cost for 9 pipes = a+b+c+d
Rate per pipe = (a+b+c+d)/9

day
day

2.080

hour

1.500

day

day

2.080

hour

1.500

day

day

0.520

hour

0.330

hour

0.330

269

RBR-LUCC

Index-code

S. No

Description

Unit

Quantity

750 mm dia RCC Hume pipe


Unit = per pipe
Taking output = 15 pipes
a) Labour
Mate

day

day
Mazdoor (Unskilled)
b) Machinery
hour
Truck 10t
hour
Crane
c&d) Overheads & Contractors Profit
Cost for 15 pipes = a+b+c+d
Rate per pipe = (a+b+c+d)/15
C 600/450 mm dia RCC Hume pipe
Unit = per pipe
Taking output = 21 pipes
a) Labour
day
Mate
day
Mazdoor (Unskilled)
b) Machinery
hour
Truck 10t
hour
Crane
c&d) Overheads & Contractors Profit
Cost for 21 pipes = a+b+c+d
Rate per pipe = (a+b+c+d)/21
ii Unloading of RCC Hume pipe by manual means
including a lead upto 30 m
A 1000/1200 mm dia RCC Hume pipes
Unit = per pipe
Taking output = 5 pipes
a) Labour
day
Mate
day
Mazdoor (Unskilled)
b) Machinery
hour
Truck 10t
c) Material
Wooden sleepers 250mm x 250mm x125mm hire charges 3 nos
sleeper
Crow bars 2 nos not less than 40 mm dia (hire-charges)

c&d) Overheads & Contractors Profit


Cost for 5 pipes = a+b+c+d+e
Rate per pipe = (a+b+c+d+e)/5
750 mm dia RCC Hume pipe
Unit = per pipe
Taking output = 6 pipes
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Truck 10t
c) Material
Wooden sleepers 250mm x 250mm x125mm hire charges 3 nos
sleeper
Crow bars 2 nos not less than 40 mm dia (hire-charges)

Rate Amount
Rs.
Rs.
5

Remarks
7

0.520
0.330
0.330

0.520
0.330
0.330

1.040
2.000

hour

2.000

hour

2.000

day

day

1.040

hour

2.000

hour

2.000

hour

2.000

c&d) Overheads & Contractors Profit


Cost for 6 pipes = a+b+c+d+e
Rate per pipe = (a+b+c+d+e)/6

270

RBR-LUCC

Index-code

S. No

Description

Unit

Quantity

600/450 mm dia RCC Hume pipe


Unit = per pipe
Taking output = 8 pipes
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Truck 10t
c) Material
Wooden sleepers 250mm x 250mm x125mm hire charges 3 nos
sleeper
Crow bars 2 nos not less than 40 mm dia (hire-charges)

day

day

1.040

hour

2.000

hour

2.000

hour

2.000

Rate Amount
Rs.
Rs.
5

Remarks
7

c&d) Overheads & Contractors Profit


Cost for 8 pipes = a+b+c+d+e
Rate per pipe = (a+b+c+d+e)/8
iii

Unloading of RCC Hume pipes by mechanical means including


a lead upto 30 m

1000/1200 mm dia RCC Hume pipe


Unit = per pipe
Taking output = 9 pipes
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Truck 10t
Crane
c&d) Overheads & Contractors Profit
Cost for 9 pipes = a+b+c+d
Rate per pipe = (a+b+c+d+e)/9
750 mm dia RCC Hume pipe
Unit = per pipe
Taking output = 15 pipes
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Truck 10t
Crane
c&d) Overheads & Contractors Profit
Cost for 15 pipes = a+b+c+d

Rate per pipe = (a+b+c+d+e)/15


600/450 mm dia RCC Hume pipe
Unit = per pipe
Taking output = 21 pipes
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Truck 10t
Crane
c&d) Overheads & Contractors Profit
Cost for 21 pipes = a+b+c+d
Rate per pipe = (a+b+c+d+e)/21

day

day

0.520

hour
hour

0.200
0.200

day

day

0.520

hour

0.200

hour

0.200

day
day

0.520

hour

0.200

hour

0.200

271

RBR-LUCC

Index-code

RBR-LUCC-10

S. No

Description

Unit

Quantity

hour

0.400

hour

0.290

10

Rate Amount
Rs.
Rs.
5

Remarks
7

Conveyance of Materials
Haulage of materials by tipper 10t capacity excluding cost of
Loading, Unloading & Stacking, but including hirecharges of
Machinery.

Haulage of materials by tipper excluding cost of loading,


unloading and stacking.
Unit = t.km
Taking output 10 t load and lead 10 km = 100 t.km(5.5 cum)
i

Surfaced Road
Speed with load: 25 km per hour
Speed while returning empty: 35 km per hour
a) Machinery
Tipper 10 t capacity
Haulage with load
Empty return trip
c&d) Overheads & Contractors Profit
Cost for 100 t.km = a+b+c
Rate per t.km = (a+b+c)/100

Note : In case of carriage of Hume pipes, output of Truck be taken as 8 t


and the rate for t is to be divided by number of pipes of different diameters
as indicated in item 9 to get the rate per pipe.
ii

Unsurfaced Gravel Road


Speed with load: 20 km/hour
Speed for empty return trip: 30 km/hour
a) Machinery
Tipper 10 t capacity
Haulage with load
Empty return trip
c&d) Overheads & Contractors Profit
Cost for 100 t.km = a+b+c
Rate per t.km = (a+b+c)/100

hour

0.500

hour

0.330

Note : In case of carriage of Hume pipes, output of Truck be taken as 8 t


and the rate per t is to be divided by number of pipes of different diameters
as indicated in item 9 to get the rate per pipe.
iii

Katcha Track and Track in River Bed/Nallah Bed and


Choe Bed
Speed with load: 10 km per hour
Speed while returning empty: 15 km per hour
a) Machinery
Tipper 10 t capacity
hour
Haulage with load
hour
Empty return trip
c&d) Overheads & Contractors Profit
Cost for 100 t.km = a+b+c
Rate per t.km = (a+b+c)/100

1.000
0.670

Note : In case of carriage of Hume pipes, output of Truck be taken as 8 t


and the cost for 8 t is to be divided by number of pipes of different
diameters as indicated in item 9 to get the rate per pipe.

RBR-LUCC-11

11

Supply of Quarried stone and hand breaking


i

Supply of quarried stone and hand breaking into coarse


aggregate to Grading 1 (90 mm to 45 mm) as per Table 400.8 of
Technical Specifications of MORD / 400-7 of MORTH.

Unit = cum
Taking output = 1 cum
a) Labour
Mate
Mazdoor (Unskilled)
b) Material
Supply of quarried stone 150-200 mm size
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d

day

day

1.248

cum

1.100

272

RBR-LUCC

Index-code

S. No
1

Description

2
i A Hand Broken Stone aggregate 75 mm nominal size
Supply of quarried stone and hand breaking into coarse aggregate
75 mm nominal size (106-63 mm) as per Table 500-17MORD &
stacking as directed.

Unit = cum
Taking output = 1 cum
a) Labour
Mate
Mazdoor (Unskilled)
b) Material
Supply of quarried stone 150-200 mm size
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
ii

Unit

Quantity

day

day

1.248

cum

1.100

Rate Amount
Rs.
Rs.
5

Remarks
7

Supply of quarried stone and hand breaking into coarse


aggregate to Grading 2 (63 mm to 45 mm) as per Table 400.8 of
Technical Specifications of MORD / 400-7 of MORTH.

Unit = cum
Taking output = 1 cum
a) Labour
Mate
Mazdoor (Unskilled)
b) Material
Supply of quarried stone 150-200 mm size
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d

day

day

1.560

cum

1.100

ii A Hand Broken Stone aggregate 63 mm nominal size


Supply of quarried stone and hand breaking into coarse aggregate
to 63 mm to nominal size (passing 80 mm and retained on 50 mm
sieve) & stacking as directed.

Unit = cum
Taking output = 1 cum
a) Labour
Mate
Mazdoor (Unskilled)
b) Material
Supply of quarried stone 150-200 mm size
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
iii

day

day

1.560

cum

1.100

Supply of quarried stone and hand breaking into coarse


aggregate to Grading 3 (53 mm to 22.4 mm)as per Table 400-8
MORTH /400.7 MORD of Technical Specifications.

Unit = cum
Taking output = 1 cum
a) Labour
Mate
Mazdoor (Unskilled)
b) Material
Supply of quarried stone 150-200 mm size
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d

day
day

1.872

cum

1.100

iii A Hand Broken Stone aggregate 40 mm nominal size

Supply of quarried stone and hand breaking into coarse


aggregate to 40 mm nominal size (passing 63 mm retained
20mm sieve) & stacking as directed.
Unit = cum
Taking output = 1 cum

a) Labour
Mate
Mazdoor (Unskilled)
b) Material
Supply of quarried stone 150-200 mm size
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d

day
day

1.872

cum

1.100

273

RBR-LUCC

Index-code

S. No

Description

Unit

Quantity

2
Crushing of Stone Aggregates 100 per cent passing through 53
mm sieve as per Table 500.6 of Technical Specifications of
MORD / 500-7 of MORTH, and 45, 40, 37.5 mm, including
hirecharges of integrated stone crusher of 200 t/h including belt
conveyor and vibrating screens, tipper 5.5 cum (10t) capacity &
Frontend Loader and all labour charges complete.
Crushing of stone boulders of 150 mm size in an integrated stone
crushing unit of 200 t/h capacity comprising of primary and
secondary crushing units, belt conveyor and vibrating screens to
obtain stone aggregates 100 per cent passing through 53 mm sieve
as per Table 500.6 of Technical Specifications of MORD / 500-7 of
MORTH including the cost of stone.

12

RBR-LUCC-12

Unit = cum
Taking output = 750 cum at crusher location
a) Labour
day
Mate
day
Mazdoor (Skilled)
day
Mazdoor (Unskilled)
b) Material
cum
Stone Boulder of size 150 mm and below
c) Machinery
Integrated stone crusher of 200 t/h including belt conveyor hour
and vibrating screens
hour
Front end loader 1 cum bucket capacity
Tipper 5.5 cum capacity
d&e) Overheads & Contractors Profit
Total (a+b+c+d+e)
Cost for 750 cum = (a+b+c+d+e) x 0.85
Rate per cum =[ (a+b+c+d+e) x 0.85]/ 750

13

RBR-LUCC-13

Rate Amount
Rs.
Rs.
5

Remarks
7

2.760
17.000
800.000
6.000
20.000

hour

20.000

Note : 1) 800 cum of stone boulders are needed to get 750 cum of stone aggregates.
2) 85 per cent of above cost will be attributed to the production of 750 cum of stone aggregates of 40 mm
size and balance 15 per cent will be for smaller size aggregates and stone dust which comes out as a byproduct.
3) The integrated stone crusher includes primary and secondary crushing units.
Crushing of Stone Aggregates 100 per cent passing through
22.4 mm sieve as per Table 500.6 of Technical Specifications
(MORD) & 20mm, 19mm, including hirecharges of integrated
stone crusher of 200 t/h including belt conveyor and vibrating
screens, tipper 5.5 cum (10t) capacity & Frontend Loader and
all labour charges complete.
Crushing of stone boulders of 150 mm size in an integrated stone
crushing unit of 200 t/h capacity comprising of primary and
secondary crushing units, belt conveyor and vibrating screens to
obtain stone aggregates 100 per cent passing through 22.4 mm
sieve as per Table 500.6 of Technical Specifications & 20 mm and
19 mm including the cost of stone.

Unit = cum
Taking output = 670 cum at crusher location
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b) Material
Stone Boulder of size 150 mm and below
c) Machinery

day

day
day

2.760
17.000

cum

800.000

Integrated stone crusher of 200 t/h including belt conveyor and


vibrating screens

hour

6.000

Front end loader 1 cum bucket capacity


Tipper 5.5 cum capacity
d&e) Overheads & Contractors Profit
Total (a+b+c+d+e)
Cost for 670 cum = (a+b+c+d+e) x 0.90
Rate per cum =[ (a+b+c+d+e) x 0.90]/ 670

hour
hour

20.000
20.000

Note : 1) 800 cum of stone boulders are needed to get 670 cum of stone aggregates.
2) 90 per cent of above cost will be attributed to the production of 670 cum of stone aggregate and
balance 10 per cent will be for smaller size aggregates and stone dust which comes out as a by-product.

14

RBR-LUCC-14

3) The integrated stone crusher includes primary and secondary crushing units.
Crushing of Stone Aggregates Nominal Size 13.2 mm as per
Table 500.9 of Technical Specifications (MORD) and Table 50021 MORTH and 14 mm, including hirecharges of integrated
stone crusher of 200 t/h including belt conveyor and vibrating
screens, tipper 5.5 cum (10t) capacity & Frontend Loader and
all labour charges complete.
Crushing of stone boulders of 150 mm size in an integrated stone
crushing unit of 200 t/h capacity comprising of primary and
secondary crushing units, belt conveyor and vibrating screens to
obtain stone aggregates of 13.2 mm nominal size as per Table
500.9 of Technical Specifications & 14 mm including the cost of
stone.

Unit = cum
Taking output = 600 cum at crusher location
a) Labour
Mate

day

274

RBR-LUCC

Index-code

S. No

Description

Unit

Quantity

3
day

4
2.760

Mazdoor (Skilled)
day
Mazdoor (Unskilled)
b) Material
cum
Stone Boulder of size 150 mm and below
c) Machinery
Integrated stone crusher of 200 t/h including belt conveyor hour
and vibrating screens
hour
Front end loader 1 cum bucket capacity
hour
Tipper 5.5 cum capacity
d&e) Overheads & Contractors Profit
Total (a+b+c+d+e)
Cost for 600 cum = (a+b+c+d+e) x 0.95
Rate per cum = [(a+b+c+d+e) x 0.95]/ 600

Rate Amount
Rs.
Rs.
5

Remarks
7

17.000
800.000
6.000
20.000
20.000

Note : 1) 800 cum of stone boulders are needed to get 600 cum of stone chips of size 13.2 mm and 125
cum stone dust.
2) 95 per cent of above cost will be attributed to the production of 600 cum of stone chips of 13.2 mm
size and balance 5 per cent to the production of stone dust which comes out as a by-product.
3) The analysis for crushing of stone chips of size 11.2 mm will be same as for 13.2 mm
A

15

RBR-LUCC-15

Crushing of Stone Aggregates Nominal Size 11.2 mm


as per Table 500.9 of Technical Specifications (MORD)
and Table 500-21 MORTH.
Same analysis as in 13.2 mm
Rate per cum
Crushing of Stone Aggregates 9.5 and 10 mm Nominal
Size as per Table 500.9 of Technical Specifications
(MORD) and Table 500-21 MORTH, including
hirecharges of integrated stone crusher of 200 t/h
including belt conveyor and vibrating screens, tipper
5.5 cum (10t) capacity & Frontend Loader and all labour
charges complete.
Crushing of stone boulders of 150 mm size in an integrated
stone crushing unit of 200 t/h capacity comprising of
primary and secondary crushing units, belt conveyor and
vibrating screens to obtain stone aggregates of 9.5 mm
nominal size as per Table 500.9 of Technical Specifications
and 10 mm including the cost of stone.
Unit = cum
Taking output = 600 cum at crusher location
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)

day

day

2.760

day

17.000

275

RBR-LUCC

Index-code

S. No

Description

Unit

Quantity

b) Material
cum
Stone Boulder of size 150 mm and below
c) Machinery
Integrated stone crusher of 200 t/h including belt conveyor hour
and vibrating screens
hour
Front end loader 1 cum bucket capacity
hour
Tipper 5.5 cum capacity
d&e) Overheads & Contractors Profit
Total (a+b+c+d+e)
Cost for 600 cum = (a+b+c+d+e) x 0.95
Rate per cum = [(a+b+c+d+e) x 0.95]/ 600

Rate Amount
Rs.
Rs.
5

Remarks
7

800.000
6.000
20.000
20.000

Note :- 1) 800 cum of stone boulders are needed to get 600 cum of stone chips of size 9.5 mm and 125
cum stone dust.
2) 95 per cent of above cost will be attributed to the production of 600 cum of stone chips of 9.5 mm size
and balance 5 per cent to the production of stone dust which comes out as a by-product.
3) The integrated stone crusher includes primary and secondary crushing units.
4) Cost of crushing of stone chips of size 6.7 mm will be 10 per cent extra over that of 9.5 mm size.
A

Crushing of Stone Aggregates 6.7, 6.3, 6 and 5 mm Nominal


Size as per Table 500.9 of Technical Specifications (MORD) and
Table 500-21 MORTH, including hirecharges of integrated stone
crusher of 200 t/h including belt conveyor and vibrating
screens, tipper 5.5 cum (10t) capacity & Frontend Loader and
all labour charges complete.
Crushing of stone boulders of 150 mm size in an integrated stone
crushing unit of 200 t/h capacity comprising of primary and
secondary crushing units, belt conveyor and vibrating screens to
obtain stone aggregates of 6.3 mm nominal size as per Table 500.9
of Technical Specifications including the cost of stone.

Unit = cum
a) Rate per cum for Crushing of Stone Aggregates 9.5 mm
as in S.No. 15
b) Add : 10% extra over that of 9.5 mm size
c) Total (a+b)
d) Overheads & Contractors Profit on (c)
Grand Total (c+d)

General Note
1. When materials are used for a finished item of work, overheads and Contractors
profit need not be included in cost of material data. Basic rates only to be carried out
as material cost.
2. Rates are for net quantities after deduction of voids.
Percentage reduction in volume of aggregates
As per Table 500 - 28 MORTH & Table 500 - 18 MORD

Standard Size of Aggregates

i.

75 mm and 63 mm

Percentage reduction in
volume computed by
stack measurements to
arrive at the volume to
be paid for

12.5

ii. 45 or 40 mm, 37.5 mm and upto 26.5 mm

10

iii. 25 mm to 13.2 mm, 11.2 mm and 6.3 or 6.7 mm


iv. Fine aggregate (sand)

5
5

v. Rough Stone for apron & revetment (as per APSS)

40

vi. Rough Stone for Soling (Proposed as in v)

40

3. Part of km beyond 1 km will be payable for the full km.


4. The provision towards Mate (1 Mate provided for 25 labour) is included in the
provision towards unskilled Mazdoor in data.
5. The rate analysis of Loading & unloading of various items includes stacking.

276

RBR-STCL

Andhra Pradesh Standard Data


I. Roads and Bridges

Chapter -2
SITE CLEARANCE
Index-code

RBR-STCL-1

S. No

Description

Unit

Quantity

Amount
Rs.
6

Remarks
7

Clearing Grass and Removal of Rubbish


Clearing grass and removal of rubbish up to a distance of
30 m outside the periphery of the area as per Technical
Specification Clause 201 MORD
By Manual Means
Unit = 10 sqm
Taking output = 1 hectare
a) Labour
Mate
Mazdoor (Unskilled)

RBR-STCL-2

Rate
Rs.
5

day

day

41.600

c&d) Overheads & Contractors Profit


Rate per hectare = a+b+c
Rate per 10 Sqm = (a+b+c)/1000
Clearing Grass and Removal of Rubbish
Clearing grass and removal of rubbish up to a distance of
50 m outside the periphery of the area as per Technical
Specification Clause 201 MORTH.
By Manual Means
Unit = 10 sqm
Taking output = 1 hectare
a) Labour
day
Mate
day
Mazdoor (Unskilled)

52.000

c&d) Overheads & Contractors Profit


Rate per hectare = a+b+c
Rate per 10 Sqm = (a+b+c)/1000
Clearing and Grubbing Road Land

Clearing and grubbing road land including uprooting wild


vegetation, grass, bushes, shrubs, saplings and trees of girth
upto 300 mm, removal of stumps of such trees cut earlier and
disposal of unserviceable materials and stacking of serviceable
material to be used or auctioned, upto a lead of 1000 m including
removal and disposal of top organic soil not exceeding 150 mm in
thickness as per Technical Specification Clause 201 MORD /
MORTH.

I
A

Unit = 10 sqm
Taking output = 1 hectare
By Manual Means
In area of non-thorny jungle (light jungle)
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Rate per hectare = a+b+c+d
Rate per 10 Sqm = (a+b+c+d)/1000
In area of thorny jungle
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Rate per hectare = a+b+c+d
Rate per 10 Sqm = (a+b+c+d)/1000

day

day

156.000

hour

1.000

day
day

208.000

hour

2.000

278

RBR-STCL
Index-code

S. No

Description

Unit

Quantity

II
A

By Mechanical Means
In area of non-thorny jungle (light jungle)
a) Labour
Day
Mate
Day
Mazdoor (Unskilled)
b) Machinery
Dozer D 50 with attachment or suitable machinery for hour
removal of trees & stumps
hour
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Rate per hectare = a+b+c+d
Rate per 10 Sqm = (a+b+c+d)/1000
In area of thorny jungle
a) labour
day
Mate
day
Mazdoor (Unskilled)
b) Machinery

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

4.160
10.00
1.00

6.240

Dozer D 50 with attachment for removal of trees & stumps

hour

12.00

Tractor with trolley 3t


c&d) Overheads & Contractors Profit
Rate per hectare = a+b+c+d
Rate per 10 Sqm = (a+b+c+d)/1000

hour

1.50

Note : The top soil removed during clearing and grubbing of site, if
suitable for re-use shall be transported, conserved and stacked as
directed by the Engineer and shall be incidental to the work.

RBR-STCL-3

A
i

ii

iii

Cutting of Trees including Cutting of Trunks, Branches


and Removal of Stumps
Cutting of trees, including cutting of trunks, branches and
removal of stumps & roots, refilling, compaction of
backfilling and stacking of serviceable material by manual
means with all lifts as per Technical Specification Clause
201MORD / MORTH
Lead upto 100 m
Unit = each
Girth above 300 mm to 600 mm
a) labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Rate for each tree = a+b+c+d
Girth above 600 mm to 900 mm
a) labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Rate for each tree = a+b+c+d
Girth above 900 mm to 1800 mm
a) labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Rate for each tree = a+b+c+d

day

day

0.624

hour

0.070

day

day

0.936

hour

0.210

day

day

2.080

hour

0.280

279

RBR-STCL
Index-code

S. No

Description

Unit

Quantity

iv

vi

B
i

ii

iii

iv

Girth above 1800 mm to 2700 mm


a) labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Rate for each tree = a+b+c+d
Girth above 2700 mm to 4500 mm
a) labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Rate for each tree = a+b+c+d
Girth above 4500 mm
a) labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Rate for each tree = a+b+c+d
Lead upto 1000 m
Unit = each
Girth above 300 mm to 600 mm
a) labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Rate for each tree = a+b+c+d
Girth above 600 mm to 900 mm
a) labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Rate for each tree = a+b+c+d
Girth above 900 mm to 1800 mm
a) labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Rate for each tree = a+b+c+d
Girth above 1800 mm to 2700 mm
a) labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Rate for each tree = a+b+c+d

day

day

4.160

hour

0.420

day

day

8.320

hour

1.000

day

day

26.000

hour

2.000

day

day

0.620

hour

0.100

day

day

0.936

hour

0.300

day
day

2.080

hour

0.400

day

day

4.160

hour

0.600

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

280

RBR-STCL
Index-code

S. No

Description

Unit

Quantity

vi

RBR-STCL-4

Girth above 2700 mm to 4500 mm


a) labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Rate for each tree = a+b+c+d
Girth above 4500 mm
a) labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Rate for each tree = a+b+c+d
Uprooting and Removing Stumps & Roots

day

day

8.320

hour

1.200

day
day

26.000

hour

2.500

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

Uprooting and Removing Stumps & roots, compaction of


backfilling and stacking of servicable material by manual means
as per Technical Specification Clause 201.
A
i

ii

iii

iv

Lead upto 100 m


Unit = each
Girth above 300 mm to 600 mm
a) labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Rate for each stump with roots = a+b+c+d
Girth above 600 mm to 900 mm
a) labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Rate for each stump with roots = a+b+c+d
Girth above 900 mm to 1800 mm
a) labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Rate for each stump with roots = a+b+c+d
Girth above 1800 mm to 2700 mm
a) labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Rate for each stump with roots = a+b+c+d
Girth above 2700 mm to 4500 mm
a) labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Rate for each stump with roots = a+b+c+d

day

day

0.416

hour

0.018

day

day

0.624

hour

0.050

day

day

1.383

hour

0.070

day

day

2.770

hour

0.110

day

day

5.540

hour

0.250

281

RBR-STCL
Index-code

S. No

Description

Unit

Quantity

vi

B
i

ii

iii

iv

Girth above 4500 mm


a) labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Rate for each stump with roots = a+b+c+d
Lead upto 1000 m
Unit = each
Girth above 300 mm to 600 mm
a) labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Rate for each stump with roots = a+b+c+d
Girth above 600 mm to 900 mm
a) labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Rate for each stump with roots = a+b+c+d
Girth above 900 mm to 1800 mm
a) labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Rate for each stump with roots = a+b+c+d
Girth above 1800 mm to 2700 mm
a) labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Rate for each stump with roots = a+b+c+d
Girth above 2700 mm to 4500 mm
a) labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Rate for each stump with roots = a+b+c+d

day

day

15.600

hour

0.750

day

day

0.416

hour

0.025

day

day

0.624

hour

0.075

day

day

1.383

hour

0.100

day

day

2.770

hour

0.150

day

day

5.540

hour

0.300

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

282

RBR-STCL
Index-code

S. No

Description

Unit

Quantity

vi

RBR-STCL-5

Girth above 4500 mm


a) labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Rate for each stump with roots = a+b+c+d
Dismantling of Structures

day

day

15.600

hour

1.000

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

Dismantling of existing structures like culverts, bridges, retaining


walls and other structure comprising of masonry, cement
concrete, wood work, steel work, including T&P and scaffolding
wherever necessary, sorting the dismantled material, disposal of
unserviceable material and stacking the serviceable material with
all lifts and lead of 1000 m as per Technical Specification Clause
202 MORD / MORTH

Unit = cum
Taking output = 1.25 cum
I
A

By Manual Means
Lime Concrete & CC upto M10
a) labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Cost for 1.25 cum = a+b+c+d
Rate per cum = (a+b+c+d)/1.25

Cement Concrete M15 & M20


a) labour
Mate
Mazdoor (Unskilled)
b) Machinery
c&d) Overheads & Contractors Profit
Cost for 1.25 cum = a+b+c+d
Rate per cum = (a+b+c+d)/1.25
Reinforced Cement Concrete and
Concrete
a) labour
Mate
Blacksmith
Mazdoor (Unskilled)
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Cost for 1.25 cum = a+b+c+d
Rate per cum = (a+b+c+d)/1.25

II

By Mechanical Means

Cement Concrete

day

day

1.040

hour

0.27

day

day

1.300

prestressed

day

day

0.400

day

3.500

hour

0.270

a) labour
day
Mate
day
Mazdoor (Unskilled)
b) Machinery
Air compressor 210 / 250 cfm with 2 leads of pneumatic hour
breaker @1.5 cum per hour
hour
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Cost for 1.25 cum = a+b+c+d
Rate per cum = (a+b+c+d)/1.25

0.520
0.83
0.27

283

RBR-STCL
Index-code

S. No
1
B

Description
2
Reinforced Cement Concrete and prestressed Concrete

Unit

Quantity

a) labour
day
Mate
day
Mazdoor (Unskilled)
day
Blacksmith
b) Machinery
Air compressor 170-210 / 250 cfm working with 2 Jack hour
Hammers simultaneously @1.00 cum per hour
hour
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Cost for 1.25 cum = a+b+c+d
Rate per cum = (a+b+c+d)/1.25

RBR-STCL-6

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

0.960
0.25
1.25
0.27

Dismantling Brick/Tile Work


Dismantling of existing structures like culverts, bridges, retaining
walls and other structures comprising of brick masonry, including
disposal of unserviceable material and stacking the serviceable
material with all lifts and lead of 1000 m as per Technical
Specification Clause 202 MORD / MORTH

Unit = cum
Taking output = 1.25 cum
A

Lime mortar
a) labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Cost for 1.25 cum = a+b+c+d
Rate per cum = (a+b+c+d)/1.25

Cement mortar
a) labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Cost for 1.25 cum = a+b+c+d
Rate per cum = (a+b+c+d)/1.25
Mud Mortar
a) labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Cost for 1.25 cum = a+b+c+d
Rate per cum = (a+b+c+d)/1.25
Dry Brick Pitching or Brick Solling
a) labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Cost for 1.25 cum = a+b+c+d
Rate per cum = (a+b+c+d)/1.25

day

day

0.520

hour

0.270

day

day

0.780

hour

0.270

day

day

0.416

hour

0.270

day

day

0.364

hour

0.270

284

RBR-STCL
Index-code

RBR-STCL-7

S. No

Description

Unit

Quantity

Dismantling Stone Masonry


Specification Clause 202.

as

per

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

Technical

Dismantling of existing structures like culverts, bridges, retaining


walls and other structure comprising of stone masonry, including
disposal of unserviceable material and stacking the serviceable
material with all lifts and lead of 1000 m as per Technical
Specification Clause 202 MORD / MORTH

Unit = cum
Taking ouput = 1.25 cum
Rubble Stone Masonry in Lime Mortar
a) labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Cost for 1.25 cum = a+b+c+d
Rate per cum = (a+b+c+d)/1.25
Rubble Stone Masonry in Cement Mortar
a) labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Cost for 1.25 cum = a+b+c+d
Rate per cum = (a+b+c+d)/1.25
Rubble Stone Masonry in Mud Mortar
a) labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Cost for 1.25 cum = a+b+c+d
Rate per cum = (a+b+c+d)/1.25
Dry Rubble Masonry
a) labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Cost for 1.25 cum = a+b+c+d
Rate per cum = (a+b+c+d)/1.25
Dismantling Stone Pitching / Dry Stone Spalls
a) labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Cost for 1.25 cum = a+b+c+d
Rate per cum = (a+b+c+d)/1.25

day

day

0.620

hour

0.270

day

day

0.780

hour

0.270

day

day

0.520

hour

0.270

day

day

0.468

hour

0.270

day

day

0.416

hour

0.270

Dismantling boulders laid in wire crates including opening of


crates and stacking dismantled materials

a) labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Cost for 1.25 cum = a+b+c+d
Rate per cum = (a+b+c+d)/1.25

day

day

0.520

hour

0.270

285

RBR-STCL
Index-code

S. No

Description

Unit

Quantity

Dismantling Wood Work Wrought and Planed Fixed in


Frames of Trusses upto a height of 5 m above Plinth
Level as per Technical Specification Clause 202 MORD
/ MORTH including stacking of dismantled material
with all lifts and lead upto 1000 m.
Unit = cum
Taking output = 1.25 cum
a) labour
Mate
Carpenter 1st Class
Mazdoor (Unskilled)
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Cost for 1.25 cum = a+b+c+d
Rate per cum = (a+b+c+d)/1.25

day

day

0.500

day

1.060

hour

0.270

RBR-STCL-8

RBR-STCL-9

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

2.9

Dismantling Steel Work in all Types of Sections upto a


height of 5 m above Plinth Level excluding Cutting of
rivet as per Technical Specification Clause 202 MORD
/ MORTH including stacking of dismantled material
with all lifts and lead upto 1000 m.
202 Unit = t
Taking output = 1 t
A Including dismembering
a) labour
Mate
Blacksmith
Mazdoor (Unskilled)
Add 2.5 per cent of cost of labour for gas cutting, ropes,
pulleys, etc.
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Rate per t = a+b+c+d
B Excluding dismembering
a) labour
Mate
Mazdoor (Unskilled)
Blacksmith
Add 2.5 per cent of cost of labour for gas cutting, ropes,
pulleys, etc.
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Rate per t = a+b+c+d
C Extra over Items (A) and (B) for cutting rivets
Unit = each
Taking output = 10 rivets
a) labour
Mate
Blacksmith
Mazdoor (Unskilled)
b&c) Overheads & Contractors Profit
Cost for 10 rivets = a+b+c
Rate for each rivet = (a+b+c) /10

day

day

1.000

day

2.640
2.50%

hour

0.170

day

day

2.100

day

0.500
2.50%

hour

0.170

day
day

0.013

day

0.014

286

RBR-STCL
Index-code

S. No

Description

Unit

Quantity

10

RBR-STCL-10

11

RBR-STCL-11

Scraping of bricks dismantled from brick work


including stacking as per Technical Specification
Clause 202 MORD / MORTH.
Unit = Nos.
Taking output = 1000 Nos.
In Lime/ Cement Mortar
a) labour
Mate
Mazdoor (Unskilled)
b&c) Overheads & Contractors Profit
Cost for 1000 Nos. = a+b+c
Rate per each = (a+b+c)/1000
Mud Mortar
a) labour
Mate
Mazdoor (Unskilled)
b&c) Overheads & Contractors Profit
Cost for 1000 Nos. = a+b+c
Rate per each = (a+b+c)/1000
Scraping of Stone from Dismantled Stone Masonry as
per Technical Specification Clause 202 MORD /
MORTH.
Unit = cum
Taking output = 1 cum
In Cement or Lime Mortar
a) labour
Mate
Mazdoor (Unskilled)
b&c) Overheads & Contractors Profit
Rate per cum = a+b+c
Mud Mortar
a) labour
Mate
Mazdoor (Unskilled)
b&c) Overheads & Contractors Profit
Rate per cum = a+b+c
Scraping Plaster in Lime or Cement Mortar from Brick
/ Stone Masonry as per Technical Specification Clause
202 MORD / MORTH, including transportation of
unserviceable Material with all lifts upto a lead of 1000
M.
Unit = sqm
Taking ouput = 100 sqm
a) labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Cost for 100 sqm = a+b+c+d
Rate per sqm = (a+b+c+d)/100

12

RBR-STCL-12

13

RBR-STCL-13

day

day

3.640

day

day

1.300

day

day

1.460

day

day

0.310

day
day

4.160

hour

0.320

Removing all types of Hume pipes and stacking within


a lead of 1000 m including Earthwork and Dismantling
of Masonry Works as per Technical Specification
Clause 202 MORD / MORTH.
Unit = m
Taking output = 1m
Upto 600 mm dia Hume pipe
a) labour
day
Mate
day
Mazdoor (Unskilled)
b&c) Overheads & Contractors Profit
Rate per m = a+b+c

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

0.540

287

RBR-STCL
Index-code

S. No

Description

Unit

Quantity

RBR-STCL-14

14

I
A

Above 600 mm to 900 mm dia Hume pipe


a) labour
day
Mate
day
Mazdoor (Unskilled)
b&c) Overheads & Contractors Profit
Rate per m = a+b+c
Above 900 mm dia Hume pipe
a) labour
day
Mate
day
Mazdoor (Unskilled)
b&c) Overheads & Contractors Profit
Rate per m = a+b+c
Note : 1. The excavation of earth, dismantling of stone masonry
work in head walls and protection works is not included which is
to be measured and paid separately.
2. Credit for retrieved stone from masonry work may be taken as
per actual availability.
Dismantling of flexible pavements
Dismantling of flexible pavements and disposal of
dismantled materials upto a lead of 1000 m, stacking
serviceable and unserviceable materials separately as
per Technical Specification Clause 202 MORD /
MORTH
Unit = cum
Taking output = 1 cum
By Manual Means
Bituminous Courses
a) labour
day
Mate
day
Mazdoor (Unskilled)
b) Machinery
hour
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d

Amount
Rs.
6

Remarks
7

0.730

1.250

1.560
0.380

Granular Courses
a) labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d

II

Rate
Rs.
5

day

day

1.040

hour

0.330

By Mechanical Means
Bituminous Courses
a) labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with trolley 3t
Tractor with ripper @ 60 cum per hour
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d

day

day

0.310

hour

0.380

hour

0.017

288

RBR-STCL
Index-code

RBR-STCL-15

S. No

Description

Unit

Quantity

15

Tractor with trolley 3t


Joint Cutting Machine with 2-3 blades
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d

16

Amount
Rs.
6

Remarks
7

Dismantling of Cement Concrete Pavements as per


Technical Specification Clause 202 MORD / MORTH.
Dismantling of cement concrete pavements by mechanical
means using pneumatic tools breaking to pieces not
exceeding 0.02 cum in volume and stock piling at
designated locations and disposal of dismantled materials
upto a lead of 1000 m, stacking serviceable and
unserviceable materials separately.
Unit = cum
Taking output = 1 cum
a) labour
Mate
Mazdoor (Semi-skilled)
Mazdoor (Unskilled)
b) Machinery
Air compressor 210 / 250 cfm with two leads for
pneumatic cutters / hammers @ 1 cum per hour

RBR-STCL-16

Rate
Rs.
5

day

day

0.500

day

0.530

hour

1.000

hour

0.400

hour

1.000

Note : The above analysis is for removal of complete pavement.


In case full depth repair work is required to be done after
dismantling, provision of a concrete saw cutter may be added
for 0.25h.
Dismantling Guard Rails
Dismantling guard rails by manual means and disposal of
dismantled material with all lifts and upto a lead of 1000
m, stacking serviceable materials and unserviceable
materials separately as per Technical Specification Clause
202 MORD / MORTH.
Unit = running m
Taking Output = 1 m
a) labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Rate per m = a+b+c+d

RBR-STCL-17

17

day

day

0.156

hour

0.050

Dismantling Kerb Stones


Dismantling kerb stones by manual means and disposal of
dismantled material with all lifts and upto a lead of 1000 m
as per Technical Specification Clause 202 MORD /
MORTH.
Unit = running m
Taking output = 10 m
a) labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Cost of 10 m = a+b+c+d
Rate per m = (a+b+c+d)/10

day

day

0.156

hour

0.200

289

RBR-STCL
Index-code

RBR-STCL-18

RBR-STCL-19

S. No

Description

Unit

Quantity

18

Dismantling Kerb Stone Channels


Dismantling kerb stone channels by manual means and
disposal of dismantled material with all lifts and upto a
lead of 1000 m as per Technical Specification Clause 202
MORD / MORTH.
Unit = running m
Taking output = 10 m
a) labour
day
Mate
day
Mazdoor (Unskilled)
b) Machinery
hour
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Cost of 10 m = a+b+c+d
Rate per m = (a+b+c+d)/10
Dismantling Kilometre Stones
Dismantling of kilometre stones including cutting of earth,
foundation and disposal of dismantled material with all lifts
and lead upto 1000 m and backfilling of pit as per
Technical Specification Clause 202 MORD / MORTH.

19

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

0.240
0.300

Unit = each
Taking output = 1 km stone
A

5th km Stone

Quantity of cement concrete = 0.392 cum


a) labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Rate for one 5th km stone = a+b+c+d
Ordinary km Stones

Quantity of cement concrete = 0.269 cum


a) labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Rate for one ordinary km stone = a+b+c+d
200 m Stones (Hecta Metre Stones)
Quantity of cement concrete = 0.048 cum
a) labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Rate for one 200 m stone = a+b+c+d

day
day

0.780

hour

0.150

day

day

0.520

hour

0.075

day

day

0.104

hour

0.020

Note : Rate for boundary pillar will be same as that of 200 m


stone

290

RBR-STCL
Index-code

RBR-STCL-20

S. No

Description

Unit

Quantity

20

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

Dismantling of Fencing
Dismantling of barbed wire fencing / wire mesh fencing
including posts, foundation concrete, backfilling of pit by
manual means including disposal of dismantled material
with all lifts and upto a lead of 1000 m, stacking
serviceable
material
and
unserviceable
material
separately as per Technical Specification Clause 202
MORD / MORTH.
Unit = running m
Taking output = 30 m
a) labour
Mate
Mazdoor (Unskilled)
Blacksmith
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Cost of 30 m = a+b+c+d
Rate per m = (a+b+c+d)/30

RBR-STCL-21

21

day

day

3.150

day

0.750

hour

0.150

Dismantling of CI Water Pipe Line


Dismantling of CI water pipe line 600 mm dia including
disposal with all lifts and lead upto 1000 m and stacking of
serviceable
material
and
unserviceable
material
separately under supervision of concerned department as
per Technical Specification Clause 202 MORD / MORTH.
Unit = running m
Taking output = 10 m
a) labour
Mate
Mazdoor (Unskilled)
Plumber
b) Machinery
Tractor with trolley 3t
Crane upto 8 t capacity
c&d) Overheads & Contractors Profit
Cost for 10 m = a+b+c+d
Rate per m = (a+b+c+d)/10

day
day

2.090

day

0.250

hour

0.250

hour

0.500

Note : The rate analysis does not include any excavation in earth or
dismantling of masonry works which are to be measured and paid
separately.

RBR-STCL-22

22

Removal of Cement Concrete Pipe of Sewer Gutter


Removal of cement concrete pipe of sewer gutter 1500 mm dia
under the supervision of concerned department including
disposal with all lifts and upto a lead of 1000 m and stacking of
serviceable and unserviceable material separately but excluding
earth excavation and dismantling of masonry works as per
Technical Specification Clause 202 MORD / MORTH.

RBR-STCL-23

23

Unit = running m
Taking output = 10 m
a) labour
day
Mate
day
Mazdoor (Unskilled)
b) Machinery
hour
Crane upto 8 t capacity
hour
Truck flat body 10 t
c&d) Overheads & Contractors Profit
Cost for 10 m = a+b+c+d
Rate per m = (a+b+c+d)/10
Note : The rate analysis does not include any excavation in
earth or dismantling of masonry works which are to be
measured and paid separately.
Removal of Telephone/Electric Poles and Lines

2.600
0.300
1.000

Removal of telephone/electric poles with wires including


excavation and dismantling of foundation concrete and
lines under the supervision of concerned department,
disposal with all lifts and upto a lead of 1000 m and
stacking the serviceable and unserviceable material
separately as per Technical Specification Clause 202
MORD / MORTH.
Unit = each
Taking output = 30 Nos.

291

RBR-STCL
Index-code

S. No

Description

Unit

Quantity

a) labour
Mate
Mazdoor (Unskilled)
Electrician / Lineman
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Cost for 30 poles = a+b+c+d
Rate per pole = (a+b+c+d)/30

day

day

10.480

day

2.000

hour

1.500

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

General Note : The provision towards Mate is included in the provision


towards unskilled Mazdoor.

292

RBR-EECD

Andhra Pradesh Standard Data


I. Roads and Bridges

Chapter - 3
EARTHWORK, EROSION CONTROL AND DRAINAGE
Index-code

RBR-EECD-1

S. No

Description

Unit Quantity
3

Rate Amount
Rs.
Rs.
5

Remarks
7

Preparation of Foundation for Embankment


Scarifying Existing Granular Surface to a Depth of 50
mm by Manual Means
Scarifying existing granular surface to a depth of 50 mm and
disposal of scarified material with a lift upto 3 m and leads
upto 1000 m as per Technical Specification Clause 301.4.
MORD
Unit = sqm
Taking output = 100 sqm
a) Labour

ii

day
Mate
day
Mazdoor (Unskilled)
b) Machinery
hour
Tractor with trolley
c&d) Overheads & Contractors Profit
Cost for 100 sqm = a+b+c+d
Rate per sqm = (a+b+c+d)/100
Note : In case material is to be reused at site, transportation cost
catered above (Sub-item b) for disposal shall be deleted.
Scarifying existing granular surface to a depth of 50 mm and
disposal of scarified material with all lifts and leads upto
1000 m as per Technical Specification Clause 305.4.3
MORTH

4.160
1.500

Unit = sqm
Taking output = 100 sqm
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with trolley
c&d) Overheads & Contractors Profit
Cost for 100 sqm = a+b+c+d
Rate per sqm = (a+b+c+d)/100

day

day

5.200

hour

1.670

Note : In case material is to be reused at site, transportation cost catered


above (Sub-item b) for disposal shall be deleted.

RBR-EECD-2

2
i

Preparation of Foundation for Embankment


Scarifying Existing Bituminous Surface to a Depth of 150
mm by Mechanical Means
Scarifying the existing bituminous road surface to a depth of 150
mm and disposal of scarified material with a lift upto 3 m and lead
upto 1000 m as per Technical Specification Clause 301.4. MORD

Unit = sqm
Taking output = 100 sqm
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with ripper attachment @ 60 cum per hour
Front end loader 1 cum bucket capacity @ 50 cum per hour

Tipper 5.5 cum capacity, 4 trips per hour


c&d) Overheads & Contractors Profit
Cost for 100 sqm = a+b+c+d
Rate per sqm = (a+b+c+d)/100

day

day

0.260

hour

0.250

hour

0.300

hour

0.680

296

RBR-EECD
Index-code

S. No

Description

2
ii

RBR-EECD-3

Rate Amount
Unit Quantity
Rs.
Rs.
3

Scarifying Existing Bituminous Surface to a Depth of 50


mm by Mechanical Means
Scarifying the existing bituminous road surface to a depth of
50 mm and disposal of scarified material with all lifts and
lead upto 1000 m as per Technical Specification Clause
305.4.3 MORTH
Unit = sqm
Taking output = 100 sqm
a) Labour
day
Mate
day
Mazdoor (Unskilled)
b) Machinery
hour
Tractor with ripper attachment @ 60 cum per hour

Remarks
7

0.260
0.080

Front end loader 1 cum bucket capacity @ 50 cum per hour

hour

0.200

Tipper 5.5 cum capacity, 4 trips per hour


c&d) Overheads & Contractors Profit
Cost for 100 sqm = a+b+c+d
Rate per sqm = (a+b+c+d)/100

hour

0.230

Construction of Embankment with Material Obtained from


Roadway Cutting
Construction of embankment with approved materials deposited at
site from roadway cutting and excavation from drain (not exceeding
0.6 m depth) and foundation of other structures graded and
compacted to meet requirement of Tables 300.1 and 300.2 as per
Technical Specification Clause 301.5 MORD / 305 MORTH

Unit = cum
Taking output = 100 cum
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Dozer D-50 for spreading @ 200 cum per hour
Motor grader for grading @ 200 cum per hour
Water tanker 6 kl capacity
Three wheel 80-100 kN Static Roller
(or)
Vibratory Roller 80 - 100 kN @ 100 cum per hour
c) Material
Water
d&e) Overheads & Contractors Profit
Cost for 100 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/100
Cost for 100 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/100

day

day

0.520

hour

0.500

hour
hour

0.500
2.000

hour

1.250

hour

1.000

kl

12.000

Note : In case the earth cutting is done by dozer and pushed for filling in
the embankment, the input of dozer in the cost of embankment shall be
deleted as the same is already provided in the cost of excavation.
However, if the earth is dumped by tippers from roadway cutting, the input
of dozer for spreading is required to be provided.

RBR-EECD-4

Construction of Embankment with Material Obtained


from Borrow Pits
i

Construction of embankment with approved material obtained from


borrow pits with all lifts, transporting to site, spreading, grading to
required slope and compacting to meet requirement of Tables 300.1
and 300.2 with a lead upto 1000 m as per Technical Specification
Clause 301.5 MORD / 305 MORTH

Unit = cum
Taking output = 100 cum
a) Labour
Mate
Mazdoor (Unskilled)

day

day

1.040

hour
hour
hour

1.670
4.500
0.500

b) Machinery
Hydraulic Excavator 0.9 cum bucket capacity @ 60 cum per hour

Tipper 5.5 cum with 10 t capacity


Dozer D-50 for spreading @ 200 cum per hour

297

RBR-EECD
Index-code

S. No

Description

Motor grader for grading @ 200 cum per hour


Water tanker 6 kl capacity
Three wheel 80-100 kN Static Roller @ 80 cum per hour

Rate Amount
Unit Quantity
Rs.
Rs.
3
hour

4
0.500

hour

2.000

hour

1.250

hour

1.000

Remarks
7

or
Vibratory Roller 80 - 100 kN @ 100 cum per hour

c) Material
kl
12.000
Water
cum 100.000
Compensation for earth taken from private land
d&e) Overheads & Contractors Profit
Cost for 100 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/100
Cost for 100 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/100
Note : 1. Compensation for earth will vary from place to place and
will have to be assessed realistically as per particular ground
situation. In case earth is available from Govt. land, compensation
for earth will not be required. The position is required to be clearly
stated in the cost estimate.
2. Loading & Unloading shall not be allowed since excavation
proposed with hydraulic excavator and unloading by tipping.
ii

Forming embankment with borrowed useful earth from outside road


boundary by mechanical means with all leads and lifts including prewatering of soil at borrow area, removal of top soil, excavation of
soils at borrowed area, conveyance of soil, depositing the soils on
the embankment, spreading soils, breaking clods, sectioning and
consolidation with Vibratory Road Roller @ OMC to meet
requirement of table 300-2 of MoRT&H, including all hire and
operational charges of T&P and seigniorage charges, complete for
finished item of work as per MoRT&H specification 305 (4th
revision) - with a lead beyond 1000m. (Payment will be made based
on level for finished item of work).

Unit = cum
Taking output = 10 cum
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery

day

day

0.104

Hydraulic Excavator 0.9 cum bucket capacity @ 60 cum/ hour

hour

0.167

Tipper 5.5 cum with 10 t capacity (L = Actual Lead)


Dozer D-50 for spreading @ 200 cum per hour
Motor grader for grading @ 100 cum per hour
Water tanker 6 kl capacity
Vibratory Roller 80 - 100 kN @ 100 cum per hour

t.km

16 x L

hour

0.050

hour

0.100

hour

0.400

hour

0.100

c) Material
Water
Compensation for earth taken from private land
d&e) Overheads & Contractors Profit
Cost for 10 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/10

kl

0.240

cum

10.000

Note : Compensation for earth will vary from place to place and will have
to be assessed realistically as per particular ground situation. In case earth
is available from Govt. land, compensation for earth will not be required.
The position is required to be clearly stated in the cost estimate.

298

RBR-EECD
Index-code

S. No

Description

2
Forming embankment with Side earth by mechanical means
including pre-watering of soil, removal of top soil, excavation of
soils, depositing the soils on the embankment, spreading soils,
breaking clods, sectioning and consolidation with Vibratory
Road Roller @ OMC to meet requirement of table 300-2 of
MoRT&H, including all hire and operational charges of T&P
and seigniorage charges, complete for finished item of work as
per MoRT&H specification 305 (4th revision) (Payment will be
made based on level for finished item of work).

iii

Unit = cum
Taking output = 100 cum
a) Labour
Mate
Mazdoor (Unskilled)

Rate Amount
Unit Quantity
Rs.
Rs.
3

day

day

0.520

Remarks
7

b) Machinery

RBR-EECD-5

1.670
Hydraulic Excavator 0.9 cum bucket capacity @ 60 cum hr
per hour
hour
1.00
Motor grader for grading @ 200 cum per hour
hour
4.00
Water tanker 6 kl capacity
hour
1.00
Vibratory Roller 80 - 100 kN
kl
24.000
C) Water
cum 100.000
d) Seigniorage Charge
Total
e) Overheads & Contractors Profit
Cost for 100 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/100
Rate per cum
a) Excavation in Cutting in Soil by manual means with
lead upto 50 m
Excavation for roadway in soil using manual means for
carrying of cut earth to embankment site with initial lift of 3
mts and lead upto 50 m as per Technical Specification
Clause 302.3 MORD
Unit = cum
Taking output = 120 cum
a) Labour
day
Mate
day
46.800
Mazdoor (Unskilled)
b&c) Overheads & Contractors Profit
Cost of 120 cum = a+b+c
Rate per cum = (a+b+c)/120

b) Excavation in Cutting in Soil by manual means with


lead beyond 50 m & upto 1000 m
Excavation for roadway in soil using manual means for
carrying of cut earth to embankment site with initial lift of 3
mts and lead beyond 50 m & upto 1000 m as per
Technical Specification Clause 301 MORTH
Unit = cum
Taking output = 120 cum
a) Labour
day
Mate
day
Mazdoor (Unskilled)
b) Machinery
hour
Truck 5.5 cum capacity
c&d) Overheads & Contractors Profit
Cost of 120 cum = a+b+c+d
Rate per cum = (a+b+c+d)/120

46.800
10.000

Note : In case there is a situation where the cross-section is of cut and fill
and cut earth is required to be used in embankment in the immediate
vicinity, the item of carriage in the truck shall be omitted.

299

RBR-EECD
Index-code

S. No
1
ii

Rate Amount
Unit Quantity
Rs.
Rs.

Description
2
Excavation in Soil with Dozer with lead upto 100m

Remarks
7

Excavation for roadway in soil by mechanical means


including cutting and pushing the earth to site of
embankment upto a distance of 100 m, including trimming
bottom and side slopes in accordance with requirements of
lines, grades and cross-sections as per Technical
Specification Clause 302.3 MORD / 301 MORTH.
Unit = cum
Taking output = 180 cum
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Dozer D-50 @ 50 cum per hour (cutting with pushing)

iii

c&d) Overheads & Contractors Profit


Cost for 180 cum = a+b+c+d
Rate per cum = (a+b+c+d)/180
Excavation in Soil using Hydraulic Excavator
Tippers with disposal upto 1000 m

day

day

2.080

hour

3.600

and

Excavation for roadwork in soil with hydraulic excavator of 0.9 cum


bucket capacity including cutting and loading in tippers, trimming
bottom and side slopes, in accordance with requirements of lines,
grades and cross-sections, and transporting to the embankment
location with all lifts and lead upto 1000 m as per Technical
Specification Clause 302.3 MORD / 301 MORTH

Unit = cum
Taking output = 360 cum
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Hydraulic excavator 0.9 cum bucket capacity @ 100 cum/ hour

Tipper 5.5 cum capacity, 4 trips per hour

RBR-EECD-6

day

day

2.080

hour
hour

3.60
15.00

c&d) Overheads & Contractors Profit


Cost for 360 cum = a+b+c+d
Rate per cum = (a+b+c+d)/360
3.6 Excavation in Marshy Soil
302 Excavation for roadway in marshy soil with hydraulic excavator 0.9
cum bucket capacity including cutting and loading in tippers and
disposal with all lifts and lead upto 1000 m, trimming of bottom and
side slopes in accordance with requirements of lines, grades and
cross- sections as per Technical Specification Clause 302.3.6
MORD / 301 MORTH

Unit = cum
Taking output = 300 cum
a) Labour
day
Mate
day
Mazdoor (Unskilled)
b) Machinery
Hydraulic excavator 0.90 cum bucket capacity @ 50 cum per hour
hour
hour
Tipper 5.5 cum capacity, 4 trips per hour.
c&d) Overheads & Contractors Profit
Cost for 300 cum = a+b+c+d
Rate per cum = (a+b+c+d)/300

2.080
6.00
12.50

300

RBR-EECD
Index-code

S. No
1

RBR-EECD-7

Description
2

Rate Amount
Unit Quantity
Rs.
Rs.
3

Remarks
7

Removal of Unsuitable / Unserviceable Soil with


Disposal upto 1000 m
Removal of unsuitable / Unserviceable soil including excavation,
loading and disposal upto 1000 m lead but excluding compaction
ground supporting embankment subgrade replacement by suitable
soil, which shall be paid separately as per Clause 303.5.2 as per
Technical Specification Clause 302.3.11 MORD / 301 MORTH

Unit = cum
Taking output = 360 cum
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Excavator 0.90 cum bucket capacity @ 100 cum per hour
Tipper 5.5 cum capacity, 4 trips per hour
c&d) Overheads & Contractors Profit
Cost for 360 cum = a+b+c+d
Rate per cum = (a+b+c+d)/360

day

day

2.080

hour
hour

3.60
15.00

Note : This item does not include replacement of unsuitable soil by


suitable soil. Replacement, where required, is to be provided and paid
separately under Clause 303.5.2.

RBR-EECD-8

i
a

Excavation in ordinary Rock by manual means


Excavation in ordinary rock using manual means including
loading in a truck and carrying of excavated material to
embankment site with initial lift of 3 mts and lead upto 50
m as per Technical Specification Clause 302.3.5 MORD /
301 MORTH
Unit = cum
Taking output = 120 cum
a) Labour
day
Mate
day
Mazdoor (Unskilled)
b&c) Overheads & Contractors Profit
Cost for 120 cum = a+b+c
Rate per cum = (a+b+c)/120
Excavation in ordinary rock using manual means including
loading in a truck and carrying of excavated material to
embankment site with initial lift of 3 mts and lead beyond
50 m & upto 1000 m as per Technical Specification Clause
301 MORTH
Unit = cum
Taking output = 120 cum
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Truck 5.5 cum capacity
c&d) Overheads & Contractors Profit
Cost for 120 cum = a+b+c+d
Rate per cum = (a+b+c+d)/120

72.800

day

day

72.800

hour

10.000

301

RBR-EECD
Index-code

S. No

Description

2
c

Rate Amount
Unit Quantity
Rs.
Rs.
3

Remarks
7

Earthwork excavation for road way in soil by mechanical


means including cutting and pushing the earth to side of
embankment upto a lead of 100 metres including
trimming bottom and side slopes in accordance with
requirements of lines, grades and cross sections etc.,
complete for finished item of work for trench cutting as
per MOR&H specification No.301 and as directed by the
Engineer-in-Charge
Unit = 1 cum
Taking output = 180 cum
a) Labour
Mate

day

Mazdoor (Unskilled)

day

2.080

Hydraulic Excavator 0.9 cum bucket capacity @ 60 cum hour


per hour

3.000

b) Machinery

c) Seigniorage Charges
d) Overheads & Contractors Profit
Cost for 180 cum = a+b+c+d

cum

180.000

Rate per cum a+b+c+d / 180


ii

iii

Excavation in Ordinary Rock with Dozer with lead upto


100m
Excavation for roadway in ordinary rock by deploying a dozer
D-50 including cutting and pushing the cut earth to site of
embankment upto a distance of 100 m (average lead 50 m),
trimming bottom and side slopes in accordance with the
requirements of lines, grades and cross-sections with lift
upto 3 m as per Technical Specification Clause 301
MORTH / 302 MORD.
Unit = cum
Taking output = 108 cum
a) Labour
day
Mate
day
Mazdoor (Unskilled)
b) Machinery
hour
Dozer D-50 @ 50% of 100 cum per hour
c&d) Overheads & Contractors Profit
Cost for 108 cum = a+b+c+d
Rate per cum = (a+b+c+d)/108

3.120
2.160

Excavation in Ordinary Rock using Hydraulic Excavator


and Tippers with disposal lead beyond 100 m & upto
1000 m
Excavation for roadway in ordinary rock with hydraulic
excavator of 0.9 cum bucket capacity including cutting and
loading in tippers, transporting to embankment site with all
lifts and lead beyond 100 m & upto 1000 m, trimming
bottom and side slopes in accordance with requirements of
lines, grades and cross-sections as per Technical
Specification Clause 302.3.5 MORD / 301 MORTH
Unit = cum
Taking output = 240 cum
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Hydraulic Excavator 0.90 cum bucket capacity @ 40 cum / hour

Tipper 5.5 cum capacity, 4 trips per hour.


c&d) Overheads & Contractors Profit
Cost for 240 cum = a+b+c+d
Rate per cum = (a+b+c+d)/240

day

day

2.080

hour
hour

6.00
11.00

302

RBR-EECD
Index-code

S. No
1

Description
2

iv

Rate Amount
Unit Quantity
Rs.
Rs.
3

Earthwork excavation for road way in soil by mechanical


means including cutting and loading in tippers trimming
bottom and side slopes in accordance with
requirements of lines, grades and cross sections and
transporting to the embankment location or disposal of
unserviceable soil with all leads and lifts etc., complete
for finished item of work for trench cutting as per
MORT&H specification No.301 and as directed by the
Engineer-in-Charge
Unit = 1 cum
Taking output = 360 cum
a) Labour
day
Mate
day
Mazdoor (Unskilled)
b) Machinery
Hydraulic Excavator 0.9 cum bucket capacity @ 60 cum hour
per hour
hour
Tipper 5.5 cum capacity, 4 trips per hour

RBR-EECD-9

Remarks

2.080
6.0000
16.00

cum
c) Seigniorage Charges
d) Overheads & Contractors Profit
Cost for 360 cum = a+b+c+d
Rate per cum a+b+c+d / 360 (OR)
Excavation in Hard Rock (requiring blasting) with
disposal upto 1000 m
Excavation for roadway in hard rock (requiring blasting) by
drilling, blasting and breaking, trimming of bottom and side
slopes in accordance with requirements of lines, grades and
cross-sections, loading and disposal of cut rock with all lifts
and leads upto 1000 m as per Technical Specification
Clause 302.3.5 MORD / 301 MORTH

Unit = cum
Taking output = 180 cum
a) Labour
Mate
Mazdoor (Unskilled)
Driller
Blaster
b) Machinery
Dozer D-50 @ 30 cum per hour
Air compressor, 210 cfm with 2 jack hammers
Front end loader 1 cum bucket capacity @ 30 cum / hour
Tipper 5.5 cum capacity, 2 trips per hour
c) Materials
Gelatine 80 per cent
Electric Detonators @ 1 detonator for 2 gelatine sticks of
285 gm each
Credit for excavated rock found suitable for use @ 50 per
cent quantity blasted
d&e) Overheads & Contractors Profit
Cost for 180 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/180

day

day

3.220

day

2.00

day

0.25

hour

6.00

hour

6.00

hour
hour

6.00
16.00

kg

70.00

each

252.00

cum

90.00

Note : 1. The quality and availability of rock shall be checked before


affording credit.
2. In case some rock is issued to the contractor at site, the item of carriage
shall be reduced/restricted to that extent.
3. Credit for useful material received as per site conditions shall be taken
into account. This has been assumed to be 50 per cent for the purpose of
analysis.

303

RBR-EECD
Index-code

S. No

Description

2
ii

Rate Amount
Unit Quantity
Rs.
Rs.
3

Remarks
7

Excavation in Hard Rock (blasting prohibited)


Excavation for roadway in hard rock (blasting prohibited) with rock
breakers including breaking rock, loading in tippers and disposal
with initial lift of 3 mts and lead upto 1000 metres, trimming
bottom and side slopes in accordance with requirements of lines,
grades and cross- sections as per Technical Specification Clause
302.3.5 MORD / 301 MORTH

(A) Manual Means


Unit = cum
Taking output = 16 cum
a) Labour
Mate
Mazdoor (Unskilled)
Chiseller (Hammer Man)
Blacksmith
b) Machinery
Tipper 5.5 cum capacity, 1 trip per hour

day

day

17.640

day

24.00

day

1.00

hour

2.90

Credit for excavated rock found suitable for use @ 50 per cent of cum
excavated quantity

8.00

c&d) Overheads & Contractors Profit


Cost for 16 cum = a+b+c+d
Rate per cum = (a+b+c+d)/16
Note : 1. Credit is considered for 50 per cent of quantity of work.
2. Loading for disposal will be done manually, being small quantity.
3. In case some rock is issued to contractor at site, the item of carriage
shall be omitted to the extent of quantity issued to the Contractor.

(B) Mechanical Means (with all lifts)


Unit = cum
Taking output = 36 cum
a) Labour
day
Mate
day
Mazdoor (Unskilled)
b) Machinery
Hydraulic excavator 0.9 cum with rock breaker attachment hour
@ 6 cum per hour
hour
Tipper 5.5 cum capacity tipper, 1 trip per hour
Credit for excavated rock found suitable for use @ 50 per cent of cum
excavated quantity

10.400
6.000
6.50
18.00

c&d) Overheads & Contractors Profit


Cost for 36 cum = a+b+c+d
Rate per cum = (a+b+c+d)/36
Note : 1. The quality and availability of rock shall be checked before
affording credit.
2. In case some rock is issued to the contractor at site, the item of carriage
shall be restricted/reduced to that extent.
3. Being small quantity, manual loading will be economical in this case and
has been provided accordingly.
iii

Excavation in Hard Rock (controlled blasting) with


disposal upto 1000 m
Excavation for roadway in hard rock with controlled blasting by
drilling, blasting and breaking, trimming of bottom and side slopes in
accordance with requirements of lines, grades and cross-sections,
loading and disposal of cut rock with all lifts and leads upto 1000
m as per Technical Specification Clause 302.3.5 MORD / 301
MORTH

Unit = cum
Taking output = 180 cum
a) Labour
Mate
Mazdoor (Unskilled)
Driller
Blaster

day

day

3.220

day

2.00

day

0.50

304

RBR-EECD
Index-code

S. No

Description

b) Machinery
Dozer D-50 @ 30 cum per hour
Air compressor, 210 cfm with 2 jack hammers
Front end loader 1 cum bucket capacity
Tipper 5.5 cum capacity, 4 trips per hour
c) Materials
Gelatine 80 per cent
Electric detonators @ 1 detonator for 2 gelatine stick of 285
gm each

10

RBR-EECD-10

Rate Amount
Unit Quantity
Rs.
Rs.
3

hour

6.00

hour

6.00

hour

6.00

hour

8.20

kg

70.00

each

1008.00

Credit for excavated rock found suitable for use @ 50 per cum
cent quantity blasted
d&e) Overheads & Contractors Profit
Cost for 180 cum =a+b+c+d+e
Rate per cum = (a+b+c+d+e)/180
Note : 1. Credit is considered for 50 per cent of quantity of blasted
rock, if found suitable for construction.
2. In case some rock is issued to the Contractor at site, the item of
carriage shall be reduced to that extent.
Extra for every additional lift of 1.5 m or part thereof over
initial lift of 3 m in all kinds of soils & rock, when
executed manually
For every additional lift of 1.5 m

Remarks
7

90.00

Unit 40 cum
Labour

day
Mazdoor (Unskilled)
Overheads & Contractors Profit
Cost for 40 cum
Rate per 1 cum
Extra for every additional lead of 50 m or part thereof
over initial lead of 50 m in all kinds of soils & rock, when
executed manually
For every additional lead of 50 m

1.00

Unit 7 cum
Labour
day
Mazdoor (Unskilled)
Overheads & Contractors Profit
Cost for 7 cum
Rate per 1 cum
Note : Head Leads limited to 150 m. Beyond 150 m only
conveyance by machinery

RBR-EECD-11

11

Stripping, Storing and Relaying Top Soil from Right-ofWay (R.O.W)


Stripping, storing and preservation of top soil by keeping it
damp in stock piles and keep wet till it is used by road side
at 15 m internal and re-application on embankment slopes,
cut slopes and other areas in localities where the available
embankment material is not conducive to plant growth as
per Technical Specification Clause 302.3.2 MORD / 305
MORTH
Unit = cum
Taking output = 10 cum
a) Labour
day
Mate
day
Mazdoor (Unskilled)
b) Machinery
hour
Dozer D-50 @ 100 cum per hour
c&d) Overheads & Contractors Profit
Cost for 10 cum = (a+b+c+d)
Rate per cum = (a+b+c+d)/10

1.00

5.200
0.100

305

RBR-EECD
Index-code

S. No

Description

RBR-EECD-12

RBR-EECD-13

12

13

14

Remarks
7

Stripping, Storing and Relaying Top Soil from Borrow


Areas in Agricultural Fields
Stripping of top soil from borrow areas located in agriculture
fields, storing at a suitable place, spreading and relaying
after taking the borrow earth to maintain fertility of the
agricultural field, finishing it to the required levels to the
satisfaction of the farmer/land owner as per Technical
Specification Clause 302.3.2 MORD / 305 MORTH
Unit = cum
Taking output = 300 cum
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Dozer D-50 with 100 cum per hour output (Initially stacking
and relaying)
c&d) Overheads & Contractors Profit
Cost for 300 cum = a+b+c+d
Rate per cum = (a+b+c+d)/300
Turfing with Sods
Furnishing and laying of the live sods of perennial turf
forming grass on embankment slope, verges or other
locations shown on the drawing or as directed by the
Engineer including preparation of ground, fetching of sods
and watering as per Technical Specification Clause 309
MORD / 307 MORTH.
Unit = sqm
Talking output = 100 sqm
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Water tanker including watering for 3 months
Tractor with Trolley
c) Material
Farmyard manure @ 0.18 cum per 100 sqm at site of work

RBR-EECD-14

Rate Amount
Unit Quantity
Rs.
Rs.

Water
d&e) Overheads & Contractors Profit
Cost for 100 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/100
Seeding and Mulching

day

day

2.080

hour

6.000

day

day

3.120

hour

2.00

hour

1.00

cum
kl

0.18
12.00

Preparation of seed bed on previously laid top soil, furnishing and


placing of seeds, fertilizer, mulching material, applying bituminous
emulsion @ 0.23 litre per sqm and laying and fixing jute netting,
including watering for 3 months all as per Technical Specification
Clause 310 MORD / 308 MORTH.

Unit = sqm
Taking output = 240 sqm
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery

day

day

10.400

Water tanker 6 kl capacity including watering for 3 months

hour

14.00

Tractor with Trolley


c) Material
Seeds
Sludge/Farmyard manure @ 0.18 cum per 100 sqm
Bitumen Emulsion
Jute netting, open weave, 25 mm square opening
Water for 3 months
d&e) Overheads & Contractors Profit
Cost for 240 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/240

hour

2.40

kg

3.60

cum

0.43

litere

55.20

sqm

264.00

kl

84.00

306

RBR-EECD
Index-code

S. No

Description

RBR-EECD-15

15

Rate Amount
Unit Quantity
Rs.
Rs.
3

Remarks
7

Construction of Subgrade and Earthen Shoulders


Construction of subgrade and earthen shoulders with approved
material obtained from borrow pits with all lifts and leads,
transporting to site, spreading, grading to required slope and
compacted to meet requirement of Table 300.2 with lead upto 1000
m as per Technical Specification Clause 303 MORD / 305 MORTH,
by using machinery.

Unit = cum
Taking output = 100 cum
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery

day

day

1.040

Hydraulic excavator 0.9 cum bucket capacity @ 100 cum/hour

hour

1.00

Tipper 5.5 cum capacity, 4 trips per hour


Add rate for loading as per item 1.1 (ii)
Add rate for unloading as per item 1.1 (iv)
Dozer D-50 for spreading @ 200 cum per hour
Motor grader for grading @ 200 cum per hour
Water tanker with 6 kl capacity
Three wheel 80-100 kN Static Roller @ 70 cum per hour

hour

4.50

cum

100.00

cum

100.00

hour

0.50

hour

0.50

hour

2.00

hour

1.43

hour

1.25

OR
Vibratory road roller 8-10 tonnes @ 80 cum per hour
c) Material
Water
Compensation for earth taken from private land
d&e) Overheads & Contractors Profit
Cost for 100 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/100
Cost for 100 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/100

RBR-EECD-16

16

kl

12.000

cum

100.000

Compacting Original Ground


i

Compacting original ground supporting embankment

Loosening, Leveling and Compacting original ground


supporting embankment to facilitate placement of first layer
of embankment, scarified to a depth of 150 mm, mixed with
water at OMC and then compacted by rolling so as to
achieve minimum dry density as given in Tables 300.1 and
300.2 for embankment construction as per Technical
Specification Clause 301.4.1 MORD / 305 MORTH.
Unit = cum
Taking output = 600 cum
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with ripper attachment
Three wheel 80-100 kN Static Roller
OR
Vibratory road roller 8-10 tonnes @ 80 cum per hour
Water tanker 6 kl capacity
c) Material
Water
d&e) Overheads & Contractors Profit
Cost for 600 cum = a+b+c+d+e (3 Wheel Roller)

day

day

2.080

hour

6.000

hour

7.500

hour

7.500

hour

4.000

kl

24.000

Rate per cum = (a+b+c+d+e)/600


Cost for 600 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/600

307

RBR-EECD
Index-code

S. No
1

Description
2

ii

Rate Amount
Unit Quantity
Rs.
Rs.
3

Remarks
7

Compacting original ground supporting subgrade


Loosening of the ground upto a level of 300 mm below the subgrade
level, watered, graded and compacted in layers to meet requirement
of Tables 300.1 and 300.2 for subgrade construction as per
Technical Specification Clause 303.5.2 MORD / 305 MORTH.

Unit = cum
Taking output = 600 cum
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with ripper attachment
Motor grader for grading
Water tanker 6 kl capacity
Three wheel 80-100 kN Static Roller @70 cum per hour
OR
Vibratory road roller 8-10 tonnes @ 80 cum per hour
c) Material
Water
d&e) Overheads & Contractors Profit
Cost for 600 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/600
Cost for 600 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/600

RBR-EECD-17

17

day

day

3.120

hour

9.000

hour

6.000

hour

4.000

hour

8.600

hour

7.500

kl

24.000

Repairs of damages caused by rain/spillage of water


Preparation and surface treatment of formation by removing mud
and slurry, watering to the extent needed to maintain the desired
moisture content, trimming to the required line, grade, profile and
rolling with three wheel 80-100 kN static roller, complete as per
Technical Specification Clause 301.5.5.1 MORD

RBR-EECD-18

18

Unit = sqm
Taking output = 3500 sqm
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor skilled
b) Machinery
Three wheel static roller 80-100 kN
Water tanker 6 kl, one trip per hour
c) Material
Water
d&e) Overheads & Contractors Profit
Cost for 3500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/3500
Presplitting Rock Excavation Slopes

day

day

6.280

day

1.00

hour

3.00

hour

2.00

kl

12.00

Carrying out excavation in hard rock to achieve a specified slope of


the rock face by controlled use of explosives and blasting
accessories in properly aligned and spaced drill holes, collection of
the excavated rock by a D-50 dozer, loading in tipper by a front end
loader and disposing of the material with all lifts and lead upto
1000 m as per Technical Specification Clause 304.3 MORD / 303
MORTH

Unit = sqm
Taking output = 400 sqm (120 cum considering 300 mm
average depth of excavation over the existing rock face)
a) Labour
day
Mate
day
Mazdoor (Unskilled)
b) Machinery
Air compressor 250/210 cfm with 2 leads @ 20 cum per hour
hour
hour
Dozer D-50
hour
Front end loader 1 cum bucket capacity
hour
Tipper 5.5 cum capacity 2 trip per hour
c) Material
kg
Gelatine 80 per cent
Electric detonators @ 1 detonator for 2 gelatine sticks of 285 each
gm each

15.600
6.00
6.00
6.00
11.00
42.00
672.00

d&e) Overheads & Contractors Profit


Cost for 400 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/400
Note : In case blasted rock is issued to the Contractor against payment for
construction work, the cost of carriage shall be reduced to that extent.

308

RBR-EECD
Index-code

S. No

Description

19

Rate Amount
Unit Quantity
Rs.
Rs.
3

Remarks
7

Construction of Embankment with Flyash/Pond ash


available from Coal or Lignite Burning Thermal Plants as
Waste Material

RBR-EECD-19

Construction of embankment with flyash conforming to Table 1 of


IRC:SP:58 obtained from coal or lignite burning thermal power
stations as waste material, spread and compacted in layer of 200
mm thickness each at OMC, all as specified in IRC:SP:58 and as
per approved plans with lead upto 1000 m as per Technical
Specification Clause 306 MORD

Unit = cum
Taking output = 360 cum
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery

day

day

4.160

Hydraulic excavator 0.9 cum bucket capacity @ 60 cum/ hour

hour

6.00

Tipper 5.5 cum capacity, flyash 360 x 1.2 = 432 t


Loading as per item 1.1 (ii)
Unloading as per item 1.1 (iv)
Dozer D-50 for spreading @ 200 cum per hour
Motor grader for grading @ 100/200 cum per hour
Water tanker 6 kl capacity
Three wheel 80-100 kN Static Roller

hour

16.00

cum

360.00

cum

360.00

hour

1.80

hour

1.80

hour

9.00

hour

4.50

hour

3.60

kl

54.00

OR

Vibratory road roller 8-10 tonnes @ 100 cum per hour


c) Material
Water
d&e) Overheads & Contractors Profit
Cost for 360 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/360
Cost for 360 cum = a+b+c+d+e (Smooth Roller)
Rate per cum = (a+b+c+d+e)/360

Note : 1. As flyash is available free of cost as waste material from Thermal


Plants, cost of material has not been added.
2. If transportation of Flyash beyond 1000 m, conveyance may be
allowed as per Chapter 1.
3. The earthcover on sides and intermediate layers of earth
sandwiching the flyash have not been included in this analysis. The same
are required to be provided as per approved design and priced separately
as embankment construction.

RBR-EECD-20

20

Surface Drains in Soil


Construction of unlined surface drains of average cross-sectional
area 0.40 sqm in soil to specified lines, grades, levels and
dimensions. Excavated material to be used in embankment with a
lift upto 3m and lead of 50 m (average lead 25 m) as per Technical
Specification Clause 307 MORD / 309 MORTH

Unit = m
Taking output = 10 m
(A) Manual Means
a) Labour
Mate
Mazdoor (Unskilled)
b&c) Overheads & Contractors Profit
Cost for 10 m = a+b+c
Rate per m = (a+b+c)/10

day

day

2.080

309

RBR-EECD
Index-code

S. No

Description

Rate Amount
Unit Quantity
Rs.
Rs.
3

Remarks
7

Note : Where lining of drain is provided, quantity shall be worked


out based on approved design and drawing and priced on rate of
cement concrete of approved grade or stone/brick masonry as the
case may be.
(B) Mechanical Means
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Hydraulic excavator 0.9 cum bucket capacity @ 100 cum/hour

ii

day
day

0.260

hour

0.040

c&d) Overheads & Contractors Profit


Cost for 10 m = a+b+c+d
Rate per m = (a+b+c+d)/10
Surface Drains in Ordinary Rock
Construction of unlined surface drain of average crosssectional area 0.4 sqm in ordinary rock to specified lines,
grades, levels and dimensions as per approved design and
Technical Specification Clause 307MORD / 309 MORTH.
Excavated material to be used in embankment at site.
Unit = m
Taking output = 10 m
(A) Manual Means
a) Labour
Mate
Mazdoor (Unskilled)
b&c) Overheads & Contractors Profit
Cost for 10 m = a+b+c
Rate per m = (a+b+c)/10
(B) Mechanical Means
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Hydraulic excavator 0.9 cum bucket capacity @ 40 cum /hour

day

day

3.120

day

day

0.520

hour

0.100

c&d) Overheads & Contractors Profit


Cost for 10 m = a+b+c+d
Rate per m = (a+b+c+d)/10
(iii) Surface Drains in Hard Rock

RBR-EECD-21

21
A

Rate per m may be worked out based on quantity of hard


rock as per design.
For rate of hard rock cutting, refer relevant item in this
ChapterDrains
Chute
Providing chute drains across embankment slopes in
approaches of bridges and on horizontal curves as per
drawings as per Specification 307 MORD.
Unit = 1 m
(a) Earthwork in excavation for foundations of structures as per
drawings and technical specifications Clause 307 including setting
out construction of shoring and bracing deleterious matter,
dressings of sides and bottom and backfilling with approved
material (By manual means).

Rate as per item No.1 of Chapter 11.

cum

(b) Providing and laying plain cement concrete M15 grade.

Rate as per item No.5 of Chapter 12.


(c) Brick Masonry in cement mortar 1:5.
Rate as per item No. 1 (III) of Chapter 12.
(d) Plastering with cement mortar 1:4.
Rate as per item No. 3 (A) of Chapter 12.

cum
cum

sqm

(e) Providing P.C.C. M.20 coping on the top of chute walls.

As per item No. 13 of Chapter 12.


B

Rate per m = a+b+c+d+e


Providing chute drains across embankment slopes in
approaches of bridges and on horizontal curves as per
drawings as per Specification 307 MORD.
Unit = 1 m
(a) Earthwork in excavation for foundations of structures as per
drawings and technical specifications Clause 307 including setting
out construction of shoring and bracing deleterious matter,
dressings of sides and bottom and backfilling with approved
material (By manual means).

Rate as per item No. 1 of Chapter 11.

cum

(b) Providing and laying plain cement concrete M15 grade.

310

RBR-EECD
Index-code

S. No
1

Description
2

Rate Amount
Unit Quantity
Rs.
Rs.
3

Remarks
7

cum
Rate as per item No.5 of Chapter 12.
(c) Coursed rubble stone masonry (2nd Sort) in cement
mortar 1:4
cum
Rate as per item No. 4 (II) (ii) of Chapter 12.

(d) Plastering with cement mortar 1:4.


Rate as per item No. 3 (A) of Chapter 12.

sqm

(e) Providing P.C.C. M.20 coping on the top of chute walls.

As per item No. 13 of Chapter 12.


Rate per m = a+b+c+d+e

Note : Quantities are to be taken as per the designs and drawings.

RBR-EECD-22

22

Sub Surface drains with Perforated Pipe


Construction of subsurface drain with perforated pipe of 100 mm
internal diameter of metal / asbestos cement / cement concrete /
PVC, closely jointed, perforations ranging from 3 mm to 6 mm
depending upon size of material surrounding the pipe, with 150 mm
bedding below the pipe and 300 mm cushion above the pipe, cross
section of excavation 450 x 550 mm. Excavated material to be
utilized in roadway at site as per Specification 309 MORTH

RBR-EECD-23

23

Unit = m
Taking output = 10 m
a) Labour
day
Mate
day
2.040
Mazdoor for excavation and back filling
c) Material
m
10.000
Perforated pipe of cement concrete, internal dia 100mm
cum
2.400
Crushed stone as per table 300-3
d&e) Overheads & Contractors Profit
Cost for 10 m = a+b+c+d+e
Rate per m = (a+b+c+d+e) /10
Note : Type of pipe may be modified depending upon provision in
design.
Aggregate Sub-Surface Drains
Construction of aggregate sub surface drain 300 mm x 450 mm with
aggregates conforming to table 300-4, excavated material to be
utilised in roadway as per Specification 309 MORTH

Unit = metre
Taking output = 10 metres
a) Labour
day
Mate
Mazdoor for excavation and back filling with aggregates day
b)
Material
cum
Crushed stone as per table 300-3 MORTH
c&d) Overheads & Contractors Profit
Cost for 10 metres = a+b+c+d
Rate per metre = (a+b+c+d)/10
Note : Provide suitable grading as per table 300-3 MORTH,
keeping classification of soils met.

1.520
1.350

311

RBR-EECD
Index-code

S. No
1

RBR-EECD-24

24

Description
2

Rate Amount
Unit Quantity
Rs.
Rs.
3

Remarks
7

Underground Drain at Edge of Pavement


Construction of an underground drain 1 m x 1 m (inside dimensions)
lined with RCC-20 cm thick and covered with RCC slab10 cm in
thickness on urban roads as per Specification 309 MORTH.

Unit = Running metre


Taking output = one metre
cum
a) Earthwork in soil
cum
b) RCC work M-20
Rate per metre = (a+b)
Rates for these items may be taken from chapters on earth
work and substructures respectively.

RBR-EECD-25

25

1.500
0.495

Preparation and Surface Treatment of Formation.


Preparation and surface treatment of formation by removing mud
and slurry, watering to the extent needed to maintain the desired
moisture content, trimming to the required line, grade, profile and
rolling with 8-10 tonne smooth wheeled roller, complete as per
clause 310 MORTH

RBR-EECD-26

24

Unit = sqm
Taking output = 3500sqm
a) Labour
Mate
Mazdoor
Mazdoor skilled
b)
Machinery
Smooth 3 wheeled steel roller 8-10 tonnes
Water tanker 6 KL, one trip per hour
c)
Material
Cost of water
d&e) Overheads & Contractors Profit
Cost for 3500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/3500
Construction of Rock fill Embankment
Construction of rock fill embankment with broken hard rock
fragments of size not exceeding 300 mm laid in layers not
exceeding 500 mm thick including filling of surface voids with
stone spalls, blinding top layer with granular material, rolled
with vibratory road roller, all complete as per clause 313
MORTH.
Unit = cum
Taking output = 100 cum
a) Labour
Mate
Mazdoor for excavation and back filling
b) Machinery
Dozer 80 HP for spreading @ 200 cum per hour
Vibratory road roller 8-10 tonnes @ 100 cum per hour
Water tanker 6 kl, one trip per hour
c) Material
Cost of Water
c&d) Overheads & Contractors Profit
Cost for 100 cum = a+b+c+d
Rate per cum = (a+b+c+d) / 100

day
day
day

6.280
1.000

hour
hour

3.000
3.000

KL

18.000

day

day

1.540

Hour

0.50

Hour

1.00

Hour

2.00

Kl

12.00

Note : It is assumed that rock is available at site from roadway cutting. In


case, portion of the rock requires breaking to acceptable size of 300 mm,
breaking charges will have to be added.

General Note : The provisions towards Mate is included in the


provision towards unskilled Mazdoor.

312

RBR-EECD
Index-code

S. No

Description

RBR-EECD-27

27

Rate Amount
Unit Quantity
Rs.
Rs.
3

Remarks
7

Work in Urban Roads


The cost of earth work in urban roads inhabited area will be comparatively higher due to
following reasons:
a)

There is mixed traffic on urban roads like slow moving hand and animal driven carts,
rickshaws, cycles, two/ three wheeler apart from the usual vehicular traffic resulting into
traffic jams. This causes loss of working time which may be in the range of 10 -15 per cent

b)

There is considerable disruption of traffic adversely affecting the efficiency of the working
parties including machines due to congestion caused by pedestrian traffic, local road side
venders, parking of vehicles by the road side, encroachments by the shopkeepers and local
shops who make use of the berms of the road in front of these shops and unauthorised
conversion of road berms into mini local market The output of manpower and machines is
substantially reduced due to factors mentioned above.

c)

Cost of living in urban areas is comparatively more resulting into higher wages.

d)

At times, work is executed during night time due to heavy traffic during day time. This
involves extra expenditure by way of making arrangement for lighting and special transport
for working parties due to odd hour
In the light of above, the authorities engaged in preparing the cost estimates may exercise
their judgment and cater for the additional cost to the extent of 2 to 3 per cent, keeping in
view the severity of factors mentioned above. Supporting details for the extra cost based on
the actual conditions in specific cases will have to give in justification.

313

RBR-SBBS

Andhra Pradesh Standard Data


I. Roads and Bridges

Chapter - 4
GRANULAR SUB-BASES, BASES (NON-BITUMINOUS) AND SHOULDERS
Index-code

RBR-SBBS-1

S. No

Description

Unit

Quantity

day
day
day

2.48
10.00

hour
hour

6.00
30.00

hour
hour

6.00
12.00

hour

3.00

cum
cum
cum
kl

192.00
77.00
115.00
18.00

day
day
day

2.48
10.00

hour
hour

6.00
30.00

hour
hour
hour

6.00
12.00
3.00

cum
cum
cum
kl

134.00
96.00
153.00
18.00

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

Granular Sub-base with Well Graded Material / Close


Graded Material (Table 400.1)
A By Mix in Place Method
Construction of granular sub-base by providing well graded
material / Close graded material, spreading in uniform layers
with motor grader on prepared surface, mixing by mix in place
method with rotavator at OMC, and compacting with smooth
wheel roller 80-100 kN / Vibratory Roller to achieve the
desired density, complete as per Technical Specification Clause
401 MORD / MORTH.
i

For Grading I Material ( CBR Value minimum 30)


Unit = cum
Taking output = 300 cum
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b) Machinery
Motor Grader 110 HP @ 50 cum per hour
Three wheel 80-100 kN static roller @ 10 cum per hour
OR

vibratory roller 80-100 kN


Tractor with Rotavator 25 cum per hour
Water tanker 6 kl capacity
c) Material
Well graded / Close Graded granular sub-base material as per
Table 400.1

ii

53 mm to 9.5 mm @ 50 per cent


9.5 mm to 2.36 mm @ 20 per cent
2.36 mm below @ 30 per cent
Water
d&e) Overheads & Contractors Profit
Cost for 300cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/300
Cost for 300 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/300
For Grading II Material (CBR Value minimum 25)
Unit = cum
Taking output = 300 cum
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b) Machinery
Motor Grader 110 HP @ 50 cum per hour

Three wheel 80-100 kN static roller @ 10 cum per hour


OR

vibratory roller 80-100 kN


Tractor with Rotavator 25 cum per hour
Water tanker 6 kl capacity
c) Material
Well graded/ Close Graded granular sub-base material as per
Table 400.1

26.5 mm to 9.5 mm @ 35 per cent


9.5 mm to 2.36 mm @ 25 per cent
2.36 mm below @ 40 per cent
Water
d&e) Overheads & Contractors Profit
Cost for 300cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/300
Cost for 300 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/300

315

RBR-SBBS
Index-code

S. No
1
iii

Description

Unit

Quantity

day
day
day

2.40
8.00

hour
hour

6.00
30.00

hour
hour
hour

6.00
12.00
3.00

cum
cum

255.00
129.00

cum
cum
cum
kl

134.40
48.00
201.60
18.00

day
day
day

2.40
8.00

hour
hour

7.50
4.00

Front end loader 0.9 cum / 1 cum bucket capacity 37.5 cum per
hour

hour

6.00

Tipper 5.5 cum @ 3 trips per hour


Motor grader 110 HP @ 50 cum per hour
Three wheel 80-100 kN static roller 10 cum per hour

hour
hour
hour

13.60
4.50
22.50

OR
vibratory roller 80-100 kN

hour

6.00

cum
cum
cum
kl

144.00
57.00
86.40
24.00

2
For Grading III Material (CBR Value minimum 20)

Unit = cum
Taking output = 300 cum
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b) Machinery
Motor Grader 110 HP @ 50 cum per hour
Three wheel 80-100 kN static roller @ 10 cum per hour

OR
vibratory roller 80-100 kN
Tractor with Rotavator 25 cum per hour
Water tanker 6 kl capacity
c) Material
Well graded/ Close Graded granular sub-base material as per
Table 400.1

9.5 mm to 4.75 mm @ 66 per cent


2.36 mm below @ 34 per cent
Or
9.5 mm to 4.75 mm @ 35 per cent
4.75 mm to 2.36 mm @ 12.5 per cent
2.36 mm below @ 52.5 per cent
Water

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

Total
d&e) Overheads & Contractors Profit
Cost for 300cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/300
Cost for 300 cum = a+b+c+d+e (Vibratory Roller)
B

Rate per cum = (a+b+c+d+e)/300


Plant Mix Method
(i) Construction of granular sub-base by providing well graded /
Close Graded material, mixing in a mechanical mix plant at
OMC, carriage of mixed material to work site upto lead of 1000
m spreading in uniform layers with motor grader on prepared
surface and compacting with smooth wheel roller 80-100 kN to
achieve the desired density, complete as per Technical
Specification Clause 401

For Grading I Material ( CBR Value minimum 30)


Unit = cum
Taking output = 225 cum (450 t)
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b) Machinery
Wet mix plant @ 60 /75 t capacity per hour
Water tanker 6 kl capacity 5 km lead with one trip per hour

c) Material
Well graded/ Close Graded granular sub-base material
as per Table 400.1
53 mm to 9.5 mm @ 50 per cent
9.5 mm to 2.36 mm @ 20 per cent
2.36 mm below @ 30 per cent
Water
d&e) Overheads & Contractors Profit
Cost for 225 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/225
Cost for 225 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/225

316

RBR-SBBS
Index-code

S. No
1
ii

Description
2
For Grading II Material (CBR Value minimum 25)

Unit = cum
Taking output = 225 cum (450 t)
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b) Machinery
Wet mix plant @ 75 t capacity per hour
Water tanker 6 kl capacity 5 km lead with one trip per hour
Front end loader 0.9 cum bucket capacity 37.5 cum per hour

Tipper 5.5 cum, 3 trips per hour


Motor grader 110 HP @ 50 cum per hour
Three wheel 80-100 kN static roller 10 cum output
OR
vibratory roller 80-100 kN
c) Material
Well graded / Close Graded granular sub-base material
as per Table 400.1
26.5 mm to 9.5 mm @ 35 per cent
9.5 mm to 2.36 mm @ 25 per cent
2.36 mm below @ 40 per cent
Water
d&e) Overheads & Contractors Profit

iii

Unit

Quantity

day
day
day

2.40
8.00

hour
hour

7.50
4.00

hour
hour
hour
hour

6.00
13.60
4.50
22.50

hour

6.00

cum
cum
cum
kl

100.80
72.00
115.20
24.00

day
day
day

2.40
8.00

hour
hour

7.50
4.00

hour
hour
hour
hour

6.00
13.60
4.50
22.50

hour

6.00

cum
cum
cum
kl

100.80
36.00
151.20
24.00

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

Cost for 225 cum = a+b+c+d+e (3 Wheel Roller)


Rate per cum = (a+b+c+d+e)/225
Cost for 225 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/225
For Grading III Material (CBR Value minimum 20)

Unit = cum
Taking output = 225 cum (450 t)
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b) Machinery
Wet mix plant @ 60 t capacity per hour
Water tanker 6 kl capacity 5 km lead with one trip per hour
Front end loader 0.9 cum bucket capacity 37.5 cum per hour

Tipper 5.5 cum, 3 trips per hour


Motor grader 110 HP @ 50 cum per hour
Three wheel 80-100 kN static roller 10 cum output
OR
vibratory roller 80-100 kN
c) Material
Well graded / Close Graded granular sub-base material
as per Table 400.1
9.5 mm to 4.75 mm @ 35 per cent
4.75 mm to 2.36 mm @ 12.5 per cent
2.36 mm below @ 52.5 per cent
Water
d&e) Overheads & Contractors Profit
Cost for 225 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/225
Cost for 225 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/225

317

RBR-SBBS
Index-code

RBR-SBBS-2

S. No

Description

Unit

Quantity

day
day
day

2.40
8.00

hour
hour
hour

6.00
6.00
3.00

cum
cum
cum
KL

134.40
172.80
76.80
18.00

cum
cum
KL

288.00
96.00
18.00

cum
cum
KL

255.00
129.00
18.00

day
day
day

2.40
8.00

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

Granular Sub-Base with Coarse Graded Material


(Table:- 400- 2)
Construction of granular sub-base by providing coarse graded
material, spreading in uniform layers with motor grader on
prepared surface, mixing by mix in place method with rotavator
at OMC, and compacting with vibratory roller to achieve the
desired density, complete as per clause 401 MORTH.

Unit = cum
Taking output = 300 cum
a) Labour
Mate
Mazdoor skilled
Mazdoor
b)
Machinery
Mortar Grader 110 HP @ 50 cum per hour
Vibratory roller 8 -10 tonne
Water tanker 6 KL capacity
c)
Material
For coarse graded Granular sub-base Materials per table
400-2
For grading-I Material (CBR Value minimum 30)
53 mm to 26.5 mm @ 35 per cent
26.5 mm to 4.75 mm @ 45 per cent
2.36 mm below @ 20 per cent (Coarse Sand)

Cost of water
OR
For Grading-II Material (CBR Value minimum 25)
26.5 mm to 4.75 mm @ 75 per cent
2.36 mm below @ 25 per cent (Dust)
Cost of water
OR
For Grading-III Material (CBR Value minimum 20)
9.5 mm to 4.75 mm @ 66 per cent
2.36 mm below @ 34 per cent (Dust)
Cost of water
(i) Rate per cum for grading-I Material
d&e) Overheads & Contractors Profit
Cost for 300 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/300
(ii) Rate per cum for grading-II Material
d&e) Overheads & Contractors Profit
Cost for 300 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/300
(iii) Rate per cum for grading-III Material
d&e) Overheads & Contractors Profit
Cost for 300 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/300
Note : Any one of the grading for material may be
adopted as per design
B (i) Gravel / Soil - Aggregate Base (Table 400.2) Grading A
a) Construction of gravel / soil - aggregate base by providing
well graded material, spreading in uniform layers with motor
grader on prepared surface, mixing by mix in place method with
rotavator at OMC, and compacting with three wheel 80-100 kN
static roller / Vibratory Roller 80-100 kN to achieve the desired
density, complete as per Technical Specifications Clause 402
MORD.

Unit = cum
Taking output = 300 cum
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)

318

RBR-SBBS
Index-code

S. No

Description

Unit

Quantity

hour
hour

6.00
30.00

hour
hour
hour

6.00
5.00
12.00

cum
cum
cum
kl

134.40
172.80
76.80
30.00

day
day
day

2.40
8.00

hour
hour

6.00
30.00

hour
hour
hour

6.00
5.00
12.00

cum
cum
kl

288.00
96.00
30.00

b) Machinery
Motor grader 110 HP @ 50 cum per hour
Three wheel 80-100 kN static roller @ 10 cum per hour

OR
Vibratory Roller 80-100 kN
Water tanker 6 kl capacity
Tractor with Rotavator 25 cum per hour
c) Material
For well graded granular sub-base materials as per Table
400.2
For Grading A Material
53 mm to 26.5 mm @ 35 per cent
26.5 mm to 4.75 mm @ 45 per cent
2.36 mm below @ 20 per cent
Water
d&e) Overheads & Contractors Profit
Cost for 300 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/300
Cost for 300 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/300
ii

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

Gravel / Soil - Aggregate Base (Table 400.2) Grading B

a) Construction of granular sub-base by providing well


graded material, spreading in uniform layers with motor
grader on prepared surface, mixing by mix in place
method with rotavator at OMC, and compacting with
three wheel 80-100 kN static roller / Vibratory Roller 80capacity to achieve the desired density,
100 kN
complete as per Technical Specification Clause 402
Unit = cum
Taking output = 300 cum
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b) Machinery
Motor grader 110 HP @ 50 cum per hour
Three wheel 80-100 kN static roller @ 10 cum per hour

OR
Vibratory Roller 80-100 kN
Water tanker 6 kl capacity
Tractor with Rotavator 25 cum per hour
c) Material
For well graded granular sub-base materials as per Table
400.2
For Grading B Material
26.5 mm to 4.75 mm @ 75 per cent
2.36 mm below @ 25 per cent
Water
d&e) Overheads & Contractors Profit
Cost for 300 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/300
Cost for 300 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/300

319

RBR-SBBS
Index-code

S. No

Description

Unit

Quantity

2
Gravel / Soil - Aggregate Base (Table 400.2) Grading C
a) Construction of granular sub-base by providing well graded
material, spreading in uniform layers with motor grader on
prepared surface, mixing by mix in place method with rotavator
at OMC, and compacting with three wheel 80-100 kN static
roller / Vibratory Roller 80-100 kN capacity to achieve the
desired density, complete as per Technical Specification Clause
402 MORD

day
day
day

2.40
8.00

iii

Unit = cum
Taking output = 300 cum
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b) Machinery
Motor grader 110 HP @ 50 cum per hour

hour

6.00

Three wheel 80-100 kN static roller @ 10 cum per hour

hour

30.00

hour
hour
hour

6.00
5.00
12.00

cum
cum
kl

255.00
129.00
30.00

day
day
day

2.40
8.00

hour
hour

6.00
30.00

hour
hour
hour

6.00
5.00
12.00

cum
cum
kl

153.60
210.40
30.00

OR
Vibratory Roller 80-100 kN
Water tanker 6 kl capacity
Tractor with Rotavator 25 cum per hour
c) Material
For well graded granular sub-base materials as per Table
400.2
For Grading C Material
9.5 mm to 4.75 mm @ 66 per cent
2.36 mm below @ 34 per cent
Water
d&e) Overheads & Contractors Profit
Cost for 300 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/300
Cost for 300 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/300
C
i

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

Gravel/Soil-Aggregate Surface Course (Table 400.3)


Construction of granular surface course by providing well
graded material, spreading in uniform layers with motor grader
on prepared surface, mixing by mix in place method with
rotavator at OMC, and compacting with three wheel 80-100 kN
static roller / Vibratory Roller 80-100 kN capacity to achieve the
desired density, complete as per Technical Specification Clause
402 MORD

Unit = cum
Taking output = 300 cum
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b) Machinery
Motor grader 110 HP @ 50 cum per hour
Three wheel 80-100 kN static roller @ 10 cum per hour

OR
Vibratory Roller 80-100 kN
Water tanker 6 kl capacity
Tractor with Rotavator 25 cum per hour
c) Material
For well graded granular sub-base materials as per Table 400.3

4.75 to 2.36 mm 40 per cent


2.36 mm below @ 60 per cent
Water
d&e) Overheads & Contractors Profit
Cost for 300 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/300
Cost for 300 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/300

320

RBR-SBBS
Index-code

RBR-SBBS-3

S. No

Description

Unit

Quantity

day
day
day

2.44
35.00

hour

2.15

hour

3.00

t
kl

5.26
18.00

day
day
day

1.36
8.00

Tractor with ripper and rotavator attachments @ 60 cum per


hour for ripping and 25 cum per hour for mixing

hour

12.00

Motor grader 110 HP @ 50 cum per hour


Three wheel 80-100 kN Static roller @ 70 cum/hour
Water tanker 6 kl capacity
c) Material
Lime
Water
d&e) Overheads & Contractors Profit
Cost for 300 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/300

hour
hour

6.00
4.30

hour

5.00

t
kl

10.50
30.00

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

Lime Stabilisation for Improving Subgrade


Laying and spreading available soil in the subgrade on a
prepared surface, pulverising, mixing the spread soil in place
with rotavator with 2 per cent slaked lime having minimum 70
per cent of contents of CaO, grading with motor grader and
compacting with the smooth wheel road roller at 80-100 kN
OMC to the desired density to form a layer of improved Subgrade as per Technical Specification Clause 403 MORD.

(A) By Manual Means


Unit = cum
Taking output = 150 cum (263 t)
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b) Machinery
Three wheel 80-100 kN Static roller @ 70 cum/hour
Water tanker 6 kl capacity
c) Material
Lime
Water
d&e) Overheads & Contractors Profit
Cost for 150 cum = a+b+c+d+e
Rate per cum = ( a+b+c+d+e)/150
(B) By Mechanical Means
Unit = cum
Taking output = 300 cum (525 t)
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b) Machinery

Note : The exact quantity of lime shall be as per design.


B

Lime Stabilisation for Improving Sub-grade


Laying and spreading available soil in the sub-grade on a
prepared surface, pulverising, mixing the spread soil in
place with rotavator with 3 per cent slaked lime having
minimum content of 70 per cent of weight by quick
lime (CaO), grading with motor grader and compacting
with the Vibratory road roller at OMC to the desired
density to form a layer of improved sub grade as per
Technical Specification 402 MORTH
Unit = cum
Taking output = 300 cum (525 tonne)
i. By Mechanical Means
a) Labour
Mate
Skilled mazdoor for alignment and geometrics
Mazdoor for spraying lime

day

day

1.36

day

8.00

321

RBR-SBBS
Index-code

S. No

Description

Unit

Quantity

b)
Machinery
Tractor with ripper and rotavator attachments @ 60 cum
per hour for ripping and 25 cum per hour for mixing

hour

12.00

hour
Motor Grader 110 HP @ 50 cum per hour
hour
Vibratory roller 8 - 10 tonne capacity
hour
Water tanker 6 KL capacity
c)
Material
tonne
Lime at site
KL
Cost of water
d&e) Overheads & Contractors Profit
Cost for 300 cum= a+b+c+d+e
Rate per cum =( a+b+c+d+e)/300
Note : Though vibratory roller is required only for 3 hours as per
norms, but the same has to be available at site for 6 hours as
other machines for spreading and mixing will take 6 hours. The
usage rates of roller have been multiplied with a factor of 0.65.

ii. By Manual Means


Unit = cum
Taking output = 150 cum (263 tonnes)
a) Labour
Mate
Mazdoor skilled
Mazdoor
b)
Machinery
Vibratory roller 8 - 10 tonne @ 60 cum per hour
Water tanker 6 KL capacity
c)
Material
Lime at site
Cost of water
d&e) Overheads & Contractors Profit
Cost for 150 cum= a+b+c+d+e
Rate per cum =( a+b+c+d+e)/150

RBR-SBBS-4

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

6.00
3.90
12.00
15.75
72.00

day

day

2.44

day

35.00

hour

2.50

hour

6.00

tonne

8.00

KL

36.00

day
day
day

2.48
10.00

Lime Treated Soil for Sub-Base


A

Providing, laying and spreading soil on a prepared sub-grade,


pulverising, mixing the spread soil in place with rotavator with 4
per cent slaked lime with minimum content of 70 per cent of
CaO, grading with motor grader and compacting with the road
roller at OMC to achieve atleast 98 per cent of the max dry
density to form a layer of sub-base as per Technical
Specification Clause 403 MORD.

Unit = cum
Taking output = 300 cum (525 t)
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b) Machinery
Hydraulic Excavator 0.90 cum bucket capacity

hour

5.00

Tipper 5.5 cum 4 trips per hour


Motor grader 110 HP @ 50 cum per hour
Three wheel 80-100 kN Static roller @ 70 cum /hour

hour
hour
hour

14.00
6.00
4.30

Tractor with rotavator and blade @ 25 cum per hour

hour
hour

12.00
5.00

t
kl

21.00
30.00

Water tanker 6 kl capacity


c) Material
Lime
Water
d&e) Overheads & Contractors Profit
Cost for 300 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/300
Note :The exact quantity of lime shall be as per design.

322

RBR-SBBS
Index-code

S. No

Description

Unit

Quantity

2
Providing, laying and spreading soil on a prepared sub
grade, pulverising, mixing the spread soil in place with
rotavator with 3 per cent slaked lime with minimum
content of 70 per cent of CaO, grading with motor grader
and compacting with the road roller at OMC to achieve at
least 98 per cent of the max dry density to form a layer of
sub base as per Technical Specification 402 MORTH.

day
day
day

2.480
10.000

hour

6.000

Unit = cum
Taking output = 300 cum (525 tonnes)
a) Labour
Mate
Mazdoor skilled
Mazdoor
b)
Machinery
Excavator 0.90 cum bucket capacity
Tipper for carriage of soil
Tipper 5.5 cum 4 trips per hour
Motor Grader 110 HP @ 50 cum per hour
Vibratory roller 8 - 10 tonne
Tractor with Rotavator and blade @ 25 cum per hour

Water tanker 6 KL capacity


Material
Lime at site
Cost of water
d&e) Overheads & Contractors Profit
Cost for 300 cum = a+b+c+d+e
Rate per cum= (a+b+c+d+e)/300

t.km

hour
hour
hour
hour
hour

14.00
6.000
6.000
12.000
12.000

tonne
KL

15.750
72.000

day
day

1.100
0.700

cum
hour

0.100
0.016

cum

1.100

cum
cum
kl

0.270
0.220
0.1

day
day
day

2.48
10.00

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

c)

RBR-SBBS-5

Soling with 150 mm cubes hard stone including 25% of


Metal of 40 to 80 mm. size for packing and 20% Gravel for
filling interstices and compacting with 80 - 100 kN Power
Roller including hire charges of Power Roller, watering etc.
complete.

Unit = cum
Taking output = 1 cum
a) Labour
Men Mazdoor for conveyance & packing
Women Mazdoor
b) Machinery

RBR-SBBS-6

Consolidating soling with static Power Roller80-100kN


Water Tanker 6Kl capacity
c) Material
Hard stone 150 mm size (Granite) (Soling Stone)
40 mm - 80 mm size metal (Hand broken)
Gravel
Water
d&e) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e)
A Cement Treated Soil Sub-Base/Base
Providing, laying and spreading soil on a prepared sub-grade,
pulverising, adding the designed quantity of cement to the
spread soil, mixing in place with rotavator, grading with the
motor grader and compacting with the smooth wheel road roller
/ Vibratory Roller 80-100 kN at OMC to achieve the desired
unconfined compressive strength and to form a layer of subbase/base as per Technical Specification Clause 404 MORD.

Unit = cum
Taking output = 300 cum (525 t)
For 4 per cent quantity of cement by weight of soil
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)

323

RBR-SBBS
Index-code

S. No

Description

Unit

Quantity

b) Machinery
Hydraulic Excavator 0.90 cum bucket capacity
Tipper 5.5 cum
Motor grader 110 HP @ 50 cum per hour

hour
hour
hour

5.00
14.00
6.00

Three wheel 80-100 kN static roller @ 70 cum per hour

hour

4.30

hour
hour

6.00
12.00
5.00

21.00

kl
Water
d&e) Overheads & Contractors Profit
Cost for 300 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/300
Cost for 300 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/300
Note : The exact quantity of cement shall be as per design.

30.00

OR
vibratory roller 80-100 kN @ 60 cum per hour
Tractor with rotavator and blade @ 25 cum per hour

Water tanker 6 kl capacity


c) Material
Cement at site @ 4% (of 525 t)

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

Cement Treated Crushed Rock or combination as per clause


403.2 and table 400.4in Sub base/ Base
Providing, laying and spreading Material on a prepared sub
grade, adding the designed quantity of cement to the spread
Material, mixing in place with rotavator, grading with the motor
grader and compacting with the road roller at OMC to achieve
the desired unconfined compressive strength and to form a layer
of sub-base/base as per Technical Specification 403 MORTH.

Unit = cum
Taking output = 300 cum (600 tonnes)
Quantity of cement assumed as 4 per cent of
quantity of crushed rock by weight.
a) Labour
day
Mate
day
Mazdoor skilled
day
Mazdoor
b)
Machinery
hour
Motor Grader 110 HP @ 50 cum per hour
hour
Vibratory roller 8 - 10 tonne
Tractor with Rotavator and blade @ 25 cum per hour hour
hour
Water tanker 6 KL capacity
c)
Material
tonne
Cement at site @ 4 per cent by weight of crushed
aggregate (600 tonne)
Grading of material for sub-base course
37.5 mm to 9.5 mm @ 55 per cent
9.5 mm to 4.75 mm @ 20 per cent
4.75 mm to 75 micron @ 25 per cent
Cost of water

2.48
10.00
6.00
6.00
12.00
10.00
24.00

cum
cum
cum
KL

211.20
76.80
96.00
60.00

cum
cum
cum
KL

124.80
19.20
240.00
60.00

or
Grading of material for Base course
37.5 mm to 9.5 mm @ 32.5 per cent
9.5 mm to 4.75 mm @ 5 per cent
4.75 mm to 75 micron @ 62.5 per cent
Cost of water
(i) For Sub-Base course
d&e) Overheads & Contractors Profit
Cost for 300 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/300
(ii) For Base course
d&e) Overheads & Contractors Profit
Cost for 300 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/300
Note : Quantities of aggregates provided under 'c' above are
uncompacted quantities.

324

RBR-SBBS
Index-code

RBR-SBBS-7

S. No

Description

Unit

Quantity

day
day

2.08

hour

0.20

day
day

4.16

hour

0.40

day
day
day

2.92
21.00

hour
hour
hour

6.00
6.00
18.00

cum

720.00

KL

108.00

day

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

Making 50 mm x 50 mm Furrows
Making 50 mm x 50 mm furrows, 25mm/ 50mm deep, 450 to the
center line of the road and at one metre interval in the existing
thin bituminous wearing coarse including sweeping and disposal
of excavated material within 1000 metres lead as per Technical
Specification 404.3.1 MORTH.

Unit = sqm
Taking output = 30 m x 7 m = 210 sqm
(i) 25mm deep furrow cutting
a)

Labour
Mate
Mazdoor
b)
Machinery
Tractor-trolley
c&d) Overheads & Contractors Profit
Cost for 210 sqm= a+b+c+d
Rate per sqm =(a+b+c+d)/210
(ii) 50mm deep furrow cutting
a) Labour
Mate
Mazdoor
b)
Machinery
Tractor-trolley
c&d) Overheads & Contractors Profit
Cost for 210 sqm= a+b+c+d
Rate per sqm =(a+b+c+d)/210

RBR-SBBS-8

Inverted Choke
Construction of inverted choke by providing, laying, spreading
and compacting screening B type/ coarse sand of specified
grade in uniform layer on a prepared surface with motor grader
and compacting with power roller etc as per Technical
Specification 404.3.2 MORTH.

RBR-SBBS-9

Unit = cum
Taking output = 600 cum
a) Labour
Mate
Mazdoor skilled
Mazdoor
b)
Machinery
Motor Grader 110 HP
Vibratory roller 8-10 tonnes @ 60 cum per hour
Water tanker 6 KL capacity
c)
Material
Screening type 'B' or coarse sand
Cost of water
d&e) Overheads & Contractors Profit
Cost for 600 cum = a+b+c+d+e
Rate per cum = ( a+b+c+d+e)/600
Water Bound Macadam Sub-base/base
A With stone screening / binding materials
I WBM Grading 1
(i) Providing, laying, spreading and compacting stone
aggregates of specific sizes to water bound macadam
specification including spreading in uniform thickness, hand
packing, rolling with three wheel 80 -100 kN static roller in
stages to proper grade and camber, applying and brooming,
stone screening/binding materials to fill-up the interstices of
coarse aggregate, watering and compacting to the required
density Grading 1 as per Technical Specification Clause 404
MORTH & 405 MORD. For compacted thickness of 100 mm.

By Manual Means (Common for rural & urban works)


Unit = cum
Taking output = 360 cum
a) Labour
Mate

325

RBR-SBBS
Index-code

S. No

Description

Unit

Quantity

3
day
day

4
12.08
250.00

Three wheel 80-100 kN static roller @ 10 cum per hour for Rural
Area works
(OR)
Three wheel 80-100 kN static roller @ 30 cum per hour for R&B
& Urban Works
(OR)

hour

36.00

hour

12.00

Vibratory roller 8-10 tonnes @ 60 cum per hour


Water tanker 6 kl capacity

hour

6.00

hour

24.00

cum

435.60

cum

97.20

cum

28.80

kl

144.00

day
day
day

2.68
15.00

Mazdoor (Skilled)
Mazdoor (Unskilled)
b) Machinery

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

c) Material (Refer Tables 400.7, 8, 9 and 10)

Aggregate
Grading 1 90 mm to 45 mm @ 1.21 cum per 10 sqm for
compacted thickness of 100 mm

Stone Screenings
Type A 13.2 mm for Grading-1 @ 0.27 cum per 10sqm

Binding Material
Binding Material @ 0.08 cum per 10 sqm for grading 1 material

Water
d&e) Overheads & Contractors Profit
Cost for 360 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/360
Cost for 360 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/360
By Mechanical Means
Unit = cum
Taking output = 360 cum
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b) Machinery
Motor grader 110 HP @ 50 cum per hour for spreading

hour

7.20

Three wheel 80-100 kN static roller @ 10 cum per hour for Rural
Area works
(OR)
Three wheel 80-100 kN static roller @ 30 cum per hour for R&B
& Urban Works
(OR)

hour

36.00

hour

12.00

Vibratory roller 8-10 tonnes @ 60 cum per hour


Water tanker 6 kl capacity
c) Material (Refer Tables 400.7, 8, 9 and 10)
Aggregate
Grading 1 90 mm to 45 mm @ 1.21 cum per 10 sqm
for compacted thickness of 100 mm
Stone Screening
Type A 13.2 mm for Grading-1 @ 0.27 cum per 10sqm

hour
hour

6.00
24.00

cum

435.60

cum

97.20

cum

28.80

kl

144.00

Binding Material
Binding Material @ 0.08 cum per 10 sqm for Grading 2 material

Water
d&e) Overheads & Contractors Profit
Cost for 360 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/360
Cost for 360 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/360

326

RBR-SBBS
Index-code

S. No

Description

Unit

Quantity

day
day
day

12.08
250.00

Three wheel 80-100 kN static roller @ 10 cum per hour for Rural
Area works
(OR)

hour

36.00

Three wheel 80-100 kN static roller @ 30 cum per hour for R&B
& Urban Works

hour

12.00

II

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

WBM Grading 2

(i) Providing, laying, spreading and compacting stone aggregates


of specific sizes to water bound macadam specification including
spreading in uniform thickness, hand packing, rolling with
smooth wheel roller 80-100 kN in stages to proper grade and
camber, applying and brooming, stone screening/binding
materials to fill-up the interstices of coarse aggregate, watering
and compacting to the required density grading 2 as per
Technical Specification Clause 405 MORD / 404 MORTH. For
compacted thickness of 75 mm.

By Manual Means
Unit = cum
Taking output = 360 cum
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b) Machinery

(OR)
Vibratory roller 8-10 tonnes @ 60 cum per hour
Water tanker 6 kl capacity
c) Material (Refer Tables 400.7, 8, 9 and 10 MORD/
400.6, 7, 8 & 9 MORTH)
Aggregate
Grading 2 63 mm to 45 mm @ 0.91 cum per 10 sqm for
compacted thickness of 75 mm
Stone Screening
Type B 11.2 mm for Grading 2 @ 0.18 / 0.20 cum/10sqm

(OR)
Type B 13.2 mm for Grading 2 @ 0.12 cum per 10sqm
Binding Material
Binding Material @ 0.06 cum per 10 sqm for Grading 2
material
Water
d&e) Overheads & Contractors Profit
Using 11.2 mm for Grading 2 :
Cost for 360 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/360
Cost for 360 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/360
Using 13.2 mm for Grading 2
Cost for 360 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/360
Cost for 360 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/360
By Mechanical Means
Unit = cum
Taking output = 360 cum
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)

hour

6.00

hour

24.00

cum

435.60

cum

86.40

cum

57.60

cum

28.80

kl

144.00

day
day
day

2.68
15.00

327

RBR-SBBS
Index-code

S. No

Description

Unit

Quantity

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

b) Machinery
Motor grader 110 HP @ 50 cum per hour for spreading

hour

7.20

Three wheel 80-100 kN static roller @ 10 cum per hour for Rural
Area works
(OR)
Three wheel 80-100 kN static roller @ 30 cum per hour for R&B
& Urban Works

hour

36.00

hour

12.00

(OR)
Vibratory roller 8-10 tonnes @ 60 cum per hour
Water tanker 6 kl capacity
c) Material (Refer Tables 400.7, 8, 9 & 10 MORD/
400.6, 7, 8 & 9 MORTH)
Aggregate
Grading 2 63 mm to 45 mm @ 0.91 cum per 10 sqm for
compacted thickness of 75 mm
Stone Screening
Type B 11.2 mm for Grading 2 @ 0.20 cum per 10sqm
(OR)
Type B 13.2 mm for Grading 2 @ 0.12 cum per 10sqm
Binding Material
Binding Material @ 0.06 cum per 10 sqm for Grading 2
material
Water
d&e) Overheads & Contractors Profit
Using 11.2 mm for Grading 2 :
Cost for 360 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/360

hour

6.00

hour

24.00

cum

435.60

cum

86.40

cum

57.60

cum

28.80

kl

144.00

day
day
day

12.08
250.00

hour

36.00

hour

12.00

hour
hour

6.00
24.00

Cost for 360 cum = a+b+c+d+e (Vibratory Roller)


Rate per cum = (a+b+c+d+e)/360
Using 13.2 mm for Grading 2
Cost for 360 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/360
Cost for 360 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/360
III

Note : Type A Screening can be used in Grading 2


WBM Grading 3
(i) Providing, laying, spreading and compacting stone
aggregates of specific sizes to water bound macadam
specification including spreading in uniform thickness, hand
packing, rolling with smooth wheel roller 80-100 kN in stages to
proper grade and camber, applying and brooming, stone
screening to fill-up the interstices of coarse aggregate, watering
and compacting to the required density Grading 3 as per
Technical Specification Clause 405 MORD/ 404 MORTH. For
compacted thickness of 75 mm.

By Manual Means
Unit = cum
Taking output = 360 cum
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b) Machinery
Three wheel 80-100 kN static roller @ 10 cum per hour for Rural
Area works
(OR)
Three wheel 80-100 kN static roller @ 30 cum per hour for R&B
& Urban Works

(OR)
Vibratory roller 8-10 tonnes @ 60 cum per hour
Water tanker 6 kl capacity

328

RBR-SBBS
Index-code

S. No

Description

Unit

Quantity

cum

435.60

cum

86.40

cum

28.80

kl

144.00

c) Material (Refer Tables 400.7, 8, 9 & 10 MORD/


400.6, 7, 8 & 9 MORTH)
Aggregate
Grading 3 53 mm to 22.4 mm @ 0.91 cum per 10 sqm
for compacted thickness of 75 mm
Stone Screening
Type B 11.2 mm for Grading 3 @ 0.18 cum per 10sqm
Binding Material
Binding Material @ 0.06 cum per 10 sqm for Grading 2
material
Water
d&e) Overheads & Contractors Profit
Cost for 360 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/360
Cost for 360 cum = a+b+c+d+e (Vibratory Roller)

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

Rate per cum = (a+b+c+d+e)/360


Note : When BT is taken up, simultaneously, avoid Binding material
By Mechanical Means
Unit = cum
Taking output = 360 cum
a) Labour
day
Mate
day
2.68
Mazdoor (Skilled)
day
15.00
Mazdoor (Unskilled)
b) Machinery
hour
7.20
Motor grader 110 HP @ 50 cum per hour for spreading
Three wheel 80-100 kN static roller @ 10 cum per hour for Rural
Area works
(OR)

hour

36.00

Three wheel 80-100 kN static roller @ 30 cum per hour for R&B
& Urban Works

hour

12.00

(OR)
Vibratory roller 8-10 tonnes @ 60 cum per hour
Water tanker 6 kl capacity
c) Material (Refer Tables 400.7, 8, 9 & 10 MORD/
400.6, 7, 8 & 9 MORTH)
Aggregate
Grading 3 53 mm to 22.4 mm @ 0.91 cum per 10 sqm
for compacted thickness of 75 mm
Stone Screening
Type B 11.2 mm for Grading 3 @ 0.18 cum per 10sqm
Binding Material
Binding Material @ 0.06 cum per 10 sqm for Grading 2
material
Water
d&e) Overheads & Contractors Profit
Cost for 360 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/360
Cost for 360 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/360

hour

6.00

hour

24.00

cum

435.60

cum

86.40

cum

28.80

kl

144.00

Note : When BT is taken up, simultaneously, avoid Binding material

329

RBR-SBBS
Index-code

RBR-SBBS-10

S. No

Description

Unit

Quantity

day
day
day

12.08
250.00

hour

36.00

hour

12.00

hour
hour

6.00
24.00

cum

435.60

cum

108.00

cum

28.80

kl

144.00

day
day
day

2.68
15.00

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

Water Bound Macadam with Crushable Screenings


such as Gravel or Morrum
WBM Grading 1 (Using Graded Metal)

I
(i) Providing, laying, spreading and compacting stone aggregates
of specific sizes to water bound macadam specification including
spreading in uniform thickness, hand packing, rolling with three
wheel 80-100 kN static roller / Vibratory Roller 80-100 kN in
stages to proper grade and camber, applying and brooming,
crushable screening to fill-up the interstices of coarse aggregate,
watering and compacting to the required density Grading 1 as
per Technical Specification Clause 405 MORD / 404 MORTH.

(A) By Manual Means


Unit = cum
Taking output = 360 cum
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b) Machinery
Three wheel 80-100 kN static roller @ 10 cum per hour for Rural
Area works
(OR)
Three wheel 80-100 kN static roller @ 30 cum per hour for R&B
& Urban Works

(OR)
vibratory roller 80-100 kN @ 60 cum per hour
Water tanker 6 kl capacity
c) Material (Refer Tables 400.7, 8, 9 & 10 MORD/
400.6, 7, 8 & 9 MORTH)
Aggregate
Grading 1 90 mm to 45 mm @ 1.21 cum per 10 sqm
for compacted thickness of 100 mm
Crushable type such as moorum or Gravel for grading 1
@ 0.30 cum per 10 sqm
Binding Material
Binding Material @ 0.06 cum per 10 sqm for Grading 1
material (for R&B & Urban Works Only)
Water
d&e) Overheads & Contractors Profit
Cost for 360 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/360
Cost for 360 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/360
(B) By Mechanical Means
Unit = cum
Taking output = 360 cum
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b) Machinery
Motor grader 110 HP @ 50 cum per hour for spreading
Three wheel 80-100 kN static roller @ 10 cum per hour for Rural
Area works
(OR)
Three wheel 80-100 kN static roller @ 30 cum per hour for R&B
& Urban Works

(OR)
vibratory roller 80-100 kN @ 60 cum per hour
Water tanker 6 kl capacity

hour

7.20

hour

36.00

hour

12.00

hour
hour

6.00
24.00

330

RBR-SBBS
Index-code

S. No

Description

Unit

Quantity

cum

435.60

cum

108.00

cum

28.80

kl

144.00

day
day
day

12.08
250.00

hour

36.00

hour
hour

6.00
24.00

cum

435.60

cum

108.00

kl

144.00

day
day
day

2.68
15.00

c) Material (Refer Tables 400.7, 8, 9 & 10 MORD/


400.6, 7, 8 & 9 MORTH)
Aggregate
Grading 1 90 mm to 45 mm @ 1.21 cum per 10 sqm
for compacted thickness of 100 mm
Crushable type such as Moorum or gravel for Grading 1
@ 0.30 cum per 10 sqm
Binding Material
Binding Material @ 0.06 cum per 10 sqm for Grading 1
material (for R&B & Urban Works Only)
Water
d&e) Overheads & Contractors Profit
Cost for 360 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/360
Cost for 360 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/360
(ii) WBM Grading 1 (Using Single Grade Metal)

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

Providing, laying, spreading and compacting stone aggregates


of 75 mm single Grade to water bound macadam specification
including spreading in uniform thickness, hand packing, rolling
with three wheel 80-100 kN static roller / Vibratory Roller 80100 kN in stages to proper grade and camber, applying and
brooming, crushable screening to fill-up the interstices of coarse
aggregate, watering and compacting to the required density
Grading 1 as per Technical Specification Clause 405 MORD.

(A) By Manual Means


Unit = cum
Taking output = 360 cum
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b) Machinery
Three wheel 80-100 kN static roller @ 10 cum per hour
(or)
vibratory roller 80-100 kN @ 60 cum per hour
Water tanker 6 kl capacity
Material (Refer Tables 400.7, 8, 9 and 10 MORD)
Aggregate
Grading 1 Hand broken stone aggregate 75 mm
nominal size @ 1.21 cum per 10 sqm for compacted
thickness of 100 mm
Crushable type such as moorum or Gravel for grading 1
@ 0.30 cum per 10 sqm
Water
d&e) Overheads & Contractors Profit
Cost for 360 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/360
Cost for 360 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/360
(B) By Mechanical Means
Unit = cum
Taking output = 360 cum
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b) Machinery
Motor grader 110 HP @ 50 cum per hour for spreading
Three wheel 80-100 kN static roller @ 10 cum per hour
(or)
vibratory roller 80-100 kN @ 60 cum per hour
Water tanker 6 kl capacity

hour

7.20

hour

36.00

hour
hour

6.00
24.00

331

RBR-SBBS
Index-code

S. No

Description

Unit

Quantity

cum

435.60

cum

108.00

kl

144.00

day
day
day

12.08
250.00

hour

36.00

hour

12.00

hour
hour

6.00
24.00

cum

435.60

cum

105.59

cum

28.80

kl

144.00

day
day
day

2.68
15.00

Material (Refer Tables 400.7, 8, 9 and 10 MORD)


Aggregate
Grading 1 Hand broken stone aggregate 75 mm
nominal size @ 1.21cum per 10 sqm for compacted
thickness of 100 mm
Crushable type such as Moorum or gravel for Grading 1
@ 0.30 cum per 10 sqm
Water
d&e) Overheads & Contractors Profit
Cost for 360 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/360
Cost for 360 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/360
II WBM Grading 2 (using Graded Metal)
(i) Providing, laying, spreading and compacting stone
aggregates of specific sizes to water bound macadam
specification including spreading in uniform thickness,
hand packing, rolling with three wheel 80-100 kN static
roller/ Vibratory Roller 80-100 kN in stages to proper
grade and camber, applying and brooming, crushable
screening to fill-up the interstices of coarse aggregate,
watering and compacting to the required density Grading
2 as per Technical Specification Clause 405 MORD / 404
MORTH.
(A) By Manual Means
Unit = cum
Taking output = 360 cum
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b) Machinery
Three wheel 80-100 kN static roller @ 10 cum per hour for Rural
Area works
(OR)
Three wheel 80-100 kN static roller @ 30 cum per hour for R&B
& Urban Works

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

(OR)

vibratory roller 80-100 kN @ 60 cum per hour


Water tanker 6 kl capacity
c) Material (Refer Tables 400.7, 8, 9 & 10 MORD/
400.6, 7, 8 & 9 MORTH)
Aggregate
Grading 2 63 mm to 45 mm @ 0.91 cum per 10 sqm for
compacted thickness of 75 mm
Crushable type such as Moorum or gravel for Grading 2
@ 0.22 cum per 10 sqm
Binding Material
Binding Material @ 0.06 cum per 10 sqm for Grading 2
material (for R&B & Urban Works Only)
Water
d&e) Overheads & Contractors Profit
Cost for 360 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/360
Cost for 360 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/360
(B) By Mechanical Means
Unit = cum
Taking output = 360 cum
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)

332

RBR-SBBS
Index-code

S. No

Description

Unit

Quantity

b) Machinery
Motor grader 110 HP @ 50 cum per hour for spreading

hour

7.20

Three wheel 80-100 kN static roller @ 10 cum per hour for Rural
Area works
(OR)

hour

36.00

Three wheel 80-100 kN static roller @ 30 cum per hour for R&B
& Urban Works
(OR)

hour

12.00

vibratory roller 80-100 kN @ 60 cum per hour


Water tanker 6 kl capacity
c) Material (Refer Tables 400.7, 8, 9 & 10 MORD/
400.6, 7, 8 & 9 MORTH)
Aggregate
Grading 2 63 mm to 45 mm @ 0.91 cum per 10 sqm for
compacted thickness of 75 mm
Crushable type such as Moorum or gravel for Grading 2
@ 0.22 cum per 10 sqm
Binding Material
Binding Material @ 0.06 cum per 10 sqm for Grading 2
material (for R&B & Urban Works Only)

hour
hour

6.00
24.00

cum

435.60

cum

105.59

cum

28.80

kl

144.00

day
day
day

12.08
250.00

Three wheel 80-100 kN static roller @ 10 cum per hour for Rural
Area works
(OR)
Three wheel 80-100 kN static roller @ 30 cum per hour for R&B
& Urban Works
(OR)

hour

36.00

hour

12.00

vibratory roller 80-100 kN @ 60 cum per hour


Water tanker 6 kl capacity
c) Material (Refer Tables 400.7, 8, 9 and 10)
Aggregate

hour
hour

6.00
24.00

Grading 2 Hand broken stone aggregate 63 mm nominal


size (passing 80 mm & retained on 50 mm sieve) @ 0.91 cum
per 10 sqm for compacted thickness of 75 mm

cum

435.60

Crushable type such as Moorum or gravel for Grading 2 @

cum

105.59

kl

144.00

Water
d&e) Overheads & Contractors Profit
Cost for 360 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/360
Cost for 360 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/360

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

(ii) WBM Grading 2 (using single grade metal)


Providing, laying, spreading and compacting stone aggregates
of 63 mm nominal single size to water bound macadam
specification including spreading in uniform thickness, hand
packing, rolling with three wheel 80-100 kN static roller/
Vibratory Roller 80-100 kN in stages to proper grade and
camber, applying and brooming, crushable screening to fill-up
the interstices of coarse aggregate, watering and compacting to
the required density Grading 2 as per Technical Specification
Clause 405 MORD.

(A) By Manual Means


Unit = cum
Taking output = 360 cum
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b) Machinery

0.22 cum per 10 sqm


Water
d&e) Overheads & Contractors Profit
Cost for 360 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/360
Cost for 360 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/360

333

RBR-SBBS
Index-code

S. No

Description

Unit

Quantity

day
day
day

2.68
15.00

(B) By Mechanical Means


Unit = cum
Taking output = 360 cum
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b) Machinery
Motor grader 110 HP @ 50 cum per hour for spreading

III

hour

7.20

Three wheel 80-100 kN static roller @ 10 cum per hour for Rural
Area works
(OR)

hour

36.00

Three wheel 80-100 kN static roller @ 30 cum per hour for R&B
& Urban Works
(OR)

hour

12.00

vibratory roller 80-100 kN @ 60 cum per hour


Water tanker 6 kl capacity
c) Material (Refer Tables 400.7, 8, 9 and 10)
Aggregate
Grading 2 Hand broken stone aggregate 63 mm
nominal size (passing 80 mm & retained on 50 mm
sieve) @ 0.91 cum per 10 sqm for compacted thickness
of 75 mm
Crushable type such as Moorum or gravel for Grading 2
@ 0.22 cum per 10 sqm
Water
d&e) Overheads & Contractors Profit
Cost for 360 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/360
Cost for 360 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/360

hour
hour

6.00
24.00

cum

435.60

cum

105.59

kl

144.00

day
day
day

12.08
250.00

Three wheel 80-100 kN static roller @ 10 cum per hour for Rural
Area works
(OR)

hour

36.00

Three wheel 80-100 kN static roller @ 30 cum per hour for R&B
& Urban Works

hour

12.00

hour
hour

6.00
24.00

cum

435.60

cum

105.59

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

WBM Grading 3 (using Graded Metal)

(i) Providing, laying, spreading and compacting stone aggregates


of specific sizes to water bound macadam specification including
spreading in uniform thickness, hand packing, rolling with three
wheel 80-100 kN static roller/ Vibratory Roller 80-100 kN in
stages to proper grade and camber, applying and brooming,
crushable screening to fill-up the interstices of coarse aggregate,
watering and compacting to the required density Grading 3 as
per Technical Specification Clause 405 MORD / 404 MORTH.

(A) By Manual Means


Unit = cum
Taking output = 360 cum
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b) Machinery

(OR)

vibratory roller 80-100 kN @ 60 cum per hour


Water tanker 6 kl capacity
c) Material (Refer Tables 400.7, 8, 9 & 10 MORD/
400.6, 7, 8 & 9 MORTH)
Aggregate
Grading 3 53 mm to 22.4 mm @ 0.91 cum per 10 sqm
for compacted thickness of 75 mm
Crushable type such as Moorum or gravel for Grading 3
@ 0.22 cum per 10 sqm

334

RBR-SBBS
Index-code

S. No

Description

Unit

Quantity

Binding Material
Binding Material @ 0.06 cum per 10 sqm for Grading 2
material (for R&B & Urban Works Only)

cum

28.80

kl

144.00

day
day
day

2.68
15.00

Water
d&e) Overheads & Contractors Profit
Cost for 360 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/360
Cost for 360 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/360
(B) By Mechanical Means
Unit = cum
Taking output = 360 cum
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b) Machinery
Motor grader 110 HP @ 50 cum per hour for spreading
Three wheel 80-100 kN static roller @ 10 cum per hour
for Rural Area works

hour

7.20

hour

36.00

hour

12.00

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

(OR)

Three wheel 80-100 kN static roller @ 30 cum per hour


for R&B & Urban Works
(OR)

hour
vibratory roller 80-100 kN @ 60 cum per hour
hour
Water tanker 6 kl capacity
c) Material (Refer Tables 400.7, 8, 9 & 10 MORD/
400.6, 7, 8 & 9 MORTH)
Aggregate
cum
Grading 3 53 mm to 22.4 mm @ 0.91 cum per 10 sqm
for compacted thickness of 75 mm
cum
Crushable type such as Moorum or gravel for Grading 3
@ 0.22 cum per 10 sqm
Binding Material
Binding Material @ 0.06 cum per 10 sqm for Grading 2 cum
material (for R&B & Urban Works Only)
kl
Water
d&e) Overheads & Contractors Profit
Cost for 360 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/360
Cost for 360 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/360
Note : Whenever BT is taken up simultaneously binding material
can be deleted
(ii) WBM Grading 3 (using Single Grade Metal)

6.00
24.00

435.60
105.59

28.80
144.00

Providing, laying, spreading and compacting stone aggregates


of 40 mm Single nominal size to water bound macadam
specification including spreading in uniform thickness, hand
packing, rolling with three wheel 80-100 kN static roller/
Vibratory Roller 80-100 kN in stages to proper grade and
camber, applying and brooming, crushable screening to fill-up
the interstices of coarse aggregate, watering and compacting to
the required density Grading 3 as per Technical Specification
Clause 405 MORD.

(A) By Manual Means


Unit = cum
Taking output = 360 cum
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)

day
day
day

12.08
250.00

335

RBR-SBBS
Index-code

S. No

Description

Unit

Quantity

hour

36.00

hour
hour

6.00
24.00

cum

435.60

cum

105.59

kl

144.00

day
day
day

2.68
15.00

b) Machinery
Three wheel 80-100 kN static roller @ 10 cum/ hour
or
vibratory roller 80-100 kN @ 60 cum per hour
Water tanker 6 kl capacity
c) Material (Refer Tables 400.7, 8, 9 and 10)
Aggregate
Grading 3 Hand broken stone aggregate 40 mm
nominal size @ 0.91 cum per 10 sqm for compacted
thickness of 75 mm
Crushable type such as Moorum or gravel for Grading 3 @ 0.22
cum per 10 sqm

Water
d&e) Overheads & Contractors Profit
Cost for 360 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/360
Cost for 360 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/360
(B) By Mechanical Means
Unit = cum
Taking output = 360 cum
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b) Machinery

RBR-SBBS-11

Motor grader 110 HP @ 50 cum per hour for spreading

hour

7.20

Three wheel 80-100 kN @ Static roller


or
vibratory roller 80-100 kN @ 60 cum per hour
Water tanker 6 kl capacity
c) Material (Refer Tables 400.7, 8, 9 and 10)
Aggregate

hour

36.00

hour
hour

6.00
24.00

Grading 3 Hand broken stone aggregate 40 mm nominal


size @ 0.91 cum per 10 sqm for compacted thickness of 75 mm

cum

435.60

Crushable type such as Moorum or gravel for Grading 3 @ 0.22


cum per 10 sqm

cum

105.59

kl

144.00

day
day
day

8.00
2.40

Water
d&e) Overheads & Contractors Profit
Cost for 360 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/360
Cost for 360 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/360
Wet Mix Macadam

10

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

Providing, laying, spreading and compacting graded stone


aggregate to wet mix macadam specification including premixing
the material with water at OMC in mechanical mixer (Pug Mill),
carriage of mixed material by tipper to site, laying in uniform
layers in sub-base/base course on a well prepared sub-base and
compacting with smooth wheel roller of 80 to 100kN / Vibratory
Roller 80-100 kN weight to achieve the desired density including
lighting, barricading and maintenance of diversion, etc as per
Tables 400.11 & 400.12 and Technical Specification Clause 406
MORD / MORTH.

By Mechanical Means with 1 km lead


Rural Works
Unit = cum
Taking output = 100 cum
a) Labour
Mate
Dresser (Skilled) for alignment
Mazdoor (Skilled)

336

RBR-SBBS
Index-code

S. No

Description

Unit

Quantity

b) Machinery
Front end loader 1 cum capacity
Wet mix plant (Pug Mill)
Tipper/Dumper (10-t) capacity / 5-6 t capacity
Motor Grader @ 50 cum per hour
Water tanker 6 kl capacity
Three wheel 80-100 kN static roller @ 16cum per hour
(or)

hour
hour
hour
hour
hour
hour

4.00
4.00
5.00
2.00
1.33
6.25

vibratory roller 80-100 kN @ 60 cum per hour


c) Material
Coarse aggregate 45 mm to 22.4 mm @ 30 per cent
Aggregates 22.4 mm to 2.36 mm @ 40 per cent
Fine aggregate / Crushed sand 2.36 mm to 75 micron @
30 per cent

hour

1.67

cum
cum
cum

39.90
53.20
39.90

Fine aggregate 10 mm

cum

Coarse Sand
Borrow area sand
Water
d&e) Overheads & Contractors Profit
Cost for 100 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/100
Cost for 100 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/100
B R&B and Urban Area Works :
Unit = cum
Taking output = 225 cum (495 tonnes)
a) Labour
Mate
Mazdoor skilled
Mazdoor
b)
Machinery
Wet mix plant of 75 tonne hourly capacity
Electric generator 125 KVA
Front end loader 1 cum capacity
Paver finisher
Vibratory roller 8 - 10 tonne
or
Smooth 3 wheeled steel roller @ 8-10 tonnes.
Water tanker 6 KL capacity
Tipper 10t
c)
Material ( Table 400-11)
45 mm to 22.4 mm@ 30 per cent
22.4 mm to 2.36 mm @ 40 per cent
2.36 mm to 75 micron@ 30 per cent
Cost of water
d&e) Overheads & Contractors Profit
Cost for 225 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/225
Cost for 225 cum = a+b+c+d+e (Smooth Roller)
Rate per cum = (a+b+c+d+e)/225

cum
cum
kl

8.00

day
day
day

2.48
10.00

hour
hour
hour
hour
hour

9.00
6.00
6.00
6.00
3.90

hour
hour
t.km

22.50
3.00
495 x L

cum

89.10

cum
cum
KL

118.80
89.10
18.00

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

Note : 1. Though vibratory roller is required only for 3 hours as per


norms, the same is required to be available at site for 6 hours to match
with other machines. The usage rates of vibratory roller may be multiplied
with a factor of 0.65
2. As three wheeled smooth steel rollers are commonly in use, the same
has been provided as an alternative which can be used if the thickness of
individual layer does not exceed 100 mm.

337

RBR-SBBS
Index-code

S. No

Description

Unit

Quantity

2
Granular sub-base/base/surface course with local materials
(Table 400.13) by mix in place method normal Construction
of granular sub-base by providing local material spreading
in uniform layers with motor grader on prepared surface,
mixing by mix in place method with rotavator at once and
compacting with smooth wheel roller to achieve the
desired density complete as per Clause 401.4 as per
Technical Specification Clause 408 MORD.

day
day
day

2.48
10.00

hour
hour
hour
hour

6.00
30.00
12.00
5.00

Naturally occurring gravel (Local materials as per Table 400.13)

cum

384.00

Water
d&e) Overheads & Contractors Profit
Cost for 300 cum = a+b+c+d+e
Rate per cum = a+b+c+d+e/300
Using Gravel mix soil using Soil Gravel Mixture /
quarry waste
Unit = cum
Taking output = 300 cum
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b) Machinery
Motor grader 110 HP 50 cum per hour

kl

30.00

day
day
day

2.40
8.00

hour
hour
hour
hour

6.00
30.00
5.00
12.00

cum

384.00

kl

30.00

11

RBR-SBBS-12

Using naturally occurring gravel


Unit = cum
Taking output = 300 cum
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b) Machinery
Motor grader 110 HP 50 cum per hour
Three wheel 80-100 kN static roller @10 cum per hour

Tractor with rotavator 25 cum per hour


Water tanker 6 kl capacity
c) Material

ii

Three wheel 80-100 kN static roller @10 cum per hour

Water tanker 6 kl capacity


Tractor with Rotavator 25 cum per hour
c) Material
Soil gravel mixture/quarry waste (Local material as per
Table400.13) (Gravel)
Water
d&e) Overheads & Contractors Profit
Cost for 300 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/300

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

338

RBR-SBBS
Index-code

RBR-SBBS-13

S. No

Description

Unit

Quantity

day
day
day

2.68
15.00

hour
hour
hour

7.20
36.00
24.00

cum

435.60

kl

144.00

day
day
day

12.08
250.00

Three wheel 80-100 kN static roller @ 8 cum per hour

hour

36.00

Water tanker 6 kl capacity


c) Material

hour

24.00

Low Grade Aggregate such as Kankar, Literate, Dhandla and


naturally occurring gravels, quarry waste as per Table 400.13 @
1.21 cum per 10 sqm compacted thickness 100 mm

cum

435.60

kl

144.00

12

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

Construction of Water Bound Macadam using locally


available material (Table 400.13)
Providing, laying spreading and compacting local material in
block or large discrete particles, such as kankar, Literate,
Dhandla etc. as per Table 400.13 to water bound macadam
specification including spreading in uniform thickness, hand
packing, rolling with three wheel 80-100 kN static roller in stages
to proper grade and camber, applying and brooming requisite
type of screening /binding materials to fill-up the interstices of
laid material watering and compacting to the required density as
per Clause 405.3 and Technical Specification Clause 408
MORD.
A

By Mechanical Means
Unit = cum
Taking output = 360 cum
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b) Machinery
Motor grader 110 H.P @ 50 cum/hr for spreading
Three wheel 80-100 kN @ static roller 8 cum per hour

Water tanker 6 kl capacity


c) Material
Low Grade Aggregate such as Kankar, Literate, Dhandla and
naturally occurring gravels, quarry waste as per Table 400.13 @
1.21 cum per 10 sqm compacted thickness 100 mm

Water
d&e) Overheads & Contractors Profit
Cost for 360 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/360
B By Manual Means
Unit = cum
Taking output = 360 cum
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b) Machinery

Water
d&e) Overheads & Contractors Profit
Cost for 360 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/360

RBR-SBBS-14

13

Lime-Flyash Stablised Soil Sub-base


Construction of sub-base using lime-flyash admixture with
granular soil, free from organic matter/deleterious material or
clayey silts and low plasticity clays having PI between 5 and 20
and liquid limit less than 25 and commercial dry lime, slaked at
site or pre-slaked with CaO content not less than 50 per cent,
flyash to conform to gradation as per Clause 4.3 of IRC:SP:20,
lime+flyash content ranging between 10 to 30 per cent, the
minimum un-confined compressive strength and CBR value after
28-days curing and 4-days soaking to be 0.75 MPa and 25 per
cent respectively, all as specified in IRC:88 including a lead upto
1000 m as per Technical Specification Clause 409 MORD.

Unit = cum
Taking output = 480 cum (720 t, density 1.50 t/cum)

339

RBR-SBBS
Index-code

S. No

Description

Unit

Quantity

day
day
day

1.24
6.00

hour

6.00

hour
hour
hour

16.00
5.50
3.80

cum
cum

480.00
480.00
-

hour
hour

6.00
3.20

hour
hour
hour

12.00
6.00
12.00

t
cum
kl

29.00
360.00
72.00

Assumptions made
Total mass taken for analysis = 720 t
Lime+Flyash admixture
@ 20% = 0.2 x 720=144 t
Soil = 720-144 = 576 t
(578/1.6 = 360 cum)
Lime + Flyash = 144 t
Ratio Lime 4 : Flyash 16
Lime = 29 t
Flyash = 115 t
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b) Machinery
Hydraulic Excavator 0.90 cum bucket capacity @ 60 cum
per hour for 360 cum soil
Tipper 10 t capacity for carriage of soil 578 t
Tipper 10 t capacity for carriage of 115 t flyash
Tipper 10 t capacity for carriage of 29 t of lime from
store to work site
Loading as per item 1.1 (ii)
Unloading as per item 1.1 (iv)
Add 10 per cent of cost of carriage to cover cost of
loading and unloading
Tractor with disc harrows for pulverisation
Motor Grader 110 HP @ 75 per cent 200 cum per hour
for mixing in-place and grading
Three wheel 80-100 kN static roller (or)
vibratory roller 80-100 kN @ 60 cum per hour
Water tanker 6 kl capacity
c) Material
Lime (Slaked)
Compensation for earth taken from private source
Water
d&e) Overheads & Contractors Profit
Cost for 480 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/480
Cost for 480 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/480

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

Note : 1. Compensation for earth will vary from place to place and will
have to be assessed realistically as per particular ground situation. In
case earth is available from Govt. land, compensation for earth will not be
required. The position is required to be clearly stated in the cost
estimate.
2. Cost of flyash has not been considered as same will be available free
of cost. Only carriage of flyash has been provided.
3. Lime + Flyash has been taken as 20 per cent of total mass and ratio of
lime and flyash as 1:4 for estimating purposes. Total quantities will be as
per approved design.

RBR-SBBS-15

14

Construction of Sub-base/Course Using Crushed


Slag as per Table 400.19
Construction of Sub-base by providing crushed slag
spreading in uniform layer with motor grader on prepared
surface mixing by mix-in-place method with Rotavator @
OMC, and compacting with three wheel 80-100 kN static
roller to achieve the desired density complete as per
Technical Specifications Clause 402.4 and 410.3.2
MORD
Unit = cum
Taking output = 300 cum
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)

day
day
day

2.48
10.00

340

RBR-SBBS
Index-code

S. No

Description

Unit

Quantity

hour
hour

6.00
30.00

hour
hour

12.00
5.00

cum
kl

384.00
30.00

day
day
day

12.08
250.00

hour

36.00

hour

24.00

cum
cum
kl

435.60
108.00
144.00

day
day
day

2.48
10.00

hour

15.00

Motor grader 110 HP @ 50 cum per hour


Three wheel 80-100 kN static roller @70 cum /hour

hour
hour

6.00
4.30

Tractor with rotavator and blade @ 25 cum per hour


Water tanker 6 kl capacity

hour

12.00

hour

7.00

b) Machinery
Motor Grader 110 HP @ 50 cum per hour
Three wheel 80-100 kN static roller @ 10 cum /hour
Tractor with Rotavator 25 cum per hour
Water tanker 6 kl capacity
c) Material
Crushed slag as per Clause 410.4.2 (i)
As per Item No.4.2 of Chapter 4
Water
d&e) Overheads & Contractors Profit
Cost for 300 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/300

RBR-SBBS-16

15

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

Water Bound Macadam using crushed slag


Providing, laying, spreading and compacting crushed slag to
water Bound Macadam specification including spreading in
uniform thickness, hand packing rolling with smooth wheel roller
80-100 kN in stages to proper grade and camber, applying and
brooming requisite type of screening/binding materials to fill up
the interstees of crushed slag watering and compacting to the
required density as per Clause 405.3 and Technical
Specification Clause 410.3.2 MORD

Unit = cum
Taking output = 360 cum
Manual Means

RBR-SBBS-17

16

a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b) Machinery
Three wheel 80-100 kN static roller @ 10 cum/ hour
Water tanker 6 kl capacity
c) Material
As per Item No.4.7 (1)(A) of Chapter 4
Crushed slag as per Clause 410.4.2 (ii)
Crushable screening (Murram / Gravel)
Water
d&e) Overheads & Contractors Profit
Cost for 360 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/360
Cement Bound Granular Material sub-base/base
Providing laying and spreading granulated blast furnace slag on
a prepared sub-grade pulverising adding the designed quantity
of cement to the spread granulated blast furnace slag mixing in
place with rotavator grading with the mortar grader and
compacting with smooth wheel roller 80-100 kN at OMC to
achieve the desired unconfined compressive strength and to
form a layer of sub-base/base as per Technical Specification
Clauses 404.3 and 410.4.2 MORD

Unit = cum
Taking output = 300 cum (525 t)
For 4 per cent quantity of cement by wt of granulated
blast furnace slag
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b) Machinery
5.50 cum Tipper for carriage of GBFS add 10 per cent of
cost of carriage of cover cost of loading and unloading

341

RBR-SBBS
Index-code

RBR-SBBS-18

S. No

Description

Unit

Quantity

c) Material
t
Cement (4%)
kl
Water
d&e) Overheads & Contractors Profit
Cost for 300 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/300
Note : 1. The exact quantity of cement shall be as per design
2. Granulated ballast slag will be available free of cost
Crusher Run Macadam Base

17

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

21.00
42.00

Providing crushed run stone aggregate grading conforming to


table 400.20 depositing on a prepared surface by hauling
vehicles, spreading and mixing with a motor grader, watering
and compacting with a three wheel 80-100 kN static roller as per
Technical Specification Clause 411MORD/ 410 MORTH to form
a layer of sub-base/base
A
ii

By mix-in-place method
With 53 mm maximum size of aggregates
Unit = cum
Taking output = 360 cum
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b) Machinery
Tractor attached with rotavator @ 25 cum / 30 cum per hour

Motor-Grader 110 H.P


Three wheel 80-100 kN static roller @ 10 cum /hour
OR
vibratory roller 80-100 kN @ 60 cum per hour
Water tanker 6 kl capacity
c) Material
Aggregate at site
For 53 mm maximum size
63 mm to 45 mm @ 33 per cent
22.5 mm to 5.6 mm @ 32 per cent
Below 5.6 mm @ 35 per cent
Water
d&e) Overheads & Contractors Profit

day
day
day

2.48
10.00

hour
hour
hour

12.00
6.00
36.00

hour

6.00

hour

6.00

cum
cum
cum
kl

157.46
151.06
116.68
36.00

day
day
day

2.48
10.00

hour
hour
hour
hour

12.00
6.00
36.00
6.00

cum
cum
cum
kl

24.12
237.60
213.48
36.00

Cost for 360 cum = a+b+c+d+e (3 Wheel Roller)


Rate per cum = (a+b+c+d+e)/360
Cost for 360 cum = a+b+c+d+e (Vibratory Roller)
ii

Rate per cum = (a+b+c+d+e)/360


With 37.5 mm maximum size
(MORDonly)
Unit = cum
Taking output = 360 cum
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b) Machinery

of

aggregates

Tractor attached with rotavator @ 25 cum / 30 cum per hour

Motor-Grader 110 H.P


Three wheel 80-100 kN static roller @ 10 cum / hour
Water tanker 6 kl capacity
c) Material
Aggregate at site
For 37.5 mm maximum size
45 mm to 22.5 mm @ 5 per cent
22.4 mm to 5.6 mm @ 50 per cent
Below 5.6 mm @ 45 per cent
Water
d&e) Overheads & Contractors Profit
Cost for 360 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/360

342

RBR-SBBS
Index-code

S. No

Description

Unit

Quantity

day
day
day

2.48
10.00

hour
hour
hour
hour

12.00
6.00
6.00
6.00

cum
cum
cum
KL

24.12
237.60
213.48
36.00

day
day
day

1.28
6.00

hour
hour
hour
hour
hour

6.00
6.00
6.00
6.00
22.50

hour
hour
hour

6.00
3.00
10.00
-

cum
cum
cum
kl

98.40
94.41
104.18
18.00

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

Or
iii For 45 mm maximum size of aggregate (MORTH only)
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b) Machinery
Tractor attached with rotavator @ 30 cum per hour
Motor-Grader 110 H.P
vibratory roller 80-100 kN @ 60 cum per hour
Water tanker 6 kl capacity
c) Material
Aggregate at site
45 mm to 22.5 mm@ 5 per cent
22.4 mm to 5.6 mm@ 50 per cent
Below 5.6 mm@ 45 per cent
Cost of water
d&e) Overheads & Contractors Profit
Cost for 360 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/360
B
i

Or
By mixing plant method
With 53 mm maximum size of aggregates
Unit = cum
Taking output = 225 cum (450 t)
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b) Machinery
Wet mix plant @ 75 t per hour
Electric generator set, 125 KVA
Front end loader 1 cum bucket capacity
Motor grader 110 HP
Three wheel roller 80-100 kN @ 8 cum /10 cum /hour
OR
vibratory roller 80-100 kN @ 60 cum per hour
Water tanker
Tipper
Add 10 per cent of cost of carriage to cover cost of
loading and unloading
c) Material
Aggregate at site
For 53 mm maximum size
63 mm to 45 mm @ 33 per cent
22.4 mm to 5.6 mm @ 32 per cent
Below 5.6 mm @ 35 per cent
Water
d&e) Overheads & Contractors Profit
Cost for 225 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/225
Cost for 225 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/225

343

RBR-SBBS
Index-code

S. No

Description

Unit

Quantity

day
day
day

1.28
6.00

hour
hour
hour
hour
hour
hour
hour

6.00
6.00
6.00
6.00
22.50
3.00
10.00

cum
cum
cum
kl

15.06
148.50
133.00
18.00

day
day
day

1.28
6.00

hour
hour
hour
hour
hour

6.00
6.00
6.00
6.00
22.50

hour
hour
t.km

6.00
3.00
-

hour

10.00

cum
cum
cum
KL

15.06
148.50
133.43
18.00

ii

iii

With 37.5 mm maximum size of aggregates (MORD


only)
Unit = cum
Taking output = 225 cum (450 t)
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b) Machinery
Wet mix plant @ 75 t per hour
Electric generator set, 125 KVA
Front end loader 1 cum bucket capacity
Mortar grader 110 HP
Three wheel roller 80-100 kN @ 8 cum / 10 cum/ hour
Water tanker
Tipper
c) Material
Aggregate at site
For 37.5 mm maximum size
45 mm to 22.5 mm @ 5 per cent
22.4 mm to 5.6 mm @ 50 per cent
Below 5.6 mm @ 45 per cent
Water
d&e) Overheads & Contractors Profit
Cost for 225 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/225

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

For 45 mm maximum size of aggregate (MORTH only)


Unit = cum
Taking output = 225 cum (450 t)
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b) Machinery
Wet mix plant @ 75 t per hour
Electric generator set, 125 KVA
Front end loader 1 cum bucket capacity
Motor grader 110 HP
Three wheel roller 80-100 kN @ 10 cum/ hour
OR
vibratory roller 80-100 kN @ 60 cum per hour
Water tanker
Tipper
Tipper
Add 10 per cent of cost of carriage to cover cost of
loading and unloading
c) Material
Aggregate at site
45 mm to 22.5 mm@ 5 per cent
22.4 mm to 5.6 mm@ 50 per cent
Below 5.6 mm@ 45 per cent
Cost of water
d&e) Overheads & Contractors Profit
Cost for 225 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/225
Cost for 225 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/225

344

RBR-SBBS
Index-code

RBR-SBBS-19

S. No

Description

Unit

Quantity

day
day
day

10.52
3.00

hour
hour

1.00
1.00

No.
No.
cum
kl

8160.00
1100.00
5.66
6.00

day
day

53.16
13.00

hour
hour

2.00
1.00

cum

0.174

cum

15.437

Nos

5,168.00

Nos
kl

464.00
6.00

18

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

Brick Soling
Laying brick soling layer on prepared sub-grade with brick on
end edging according to lines, graded and cross-section shown
on the drawing filling joints with sand and earth, spreading 25
mm thick layer of earth over brick soling, watering and rolling the
same with three wheel road roller 80-100 kN as per Technical
Specification Clause 412 MORD

RBR-SBBS-20

19

Unit = sqm
Taking output = 150 sqm
a) Labour
Mate
Mazdoor (Unskilled)
Mason 1st Class
b) Machinery
Three wheel 80-100 kN static roller
Water tanker
c) Material
Brick 1st Class
Brick 1st Class on edging
Fine Sand
Water
d&e) Overheads & Contractors Profit
Cost for 150 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/150
Stone Set Pavement
Providing and laying stone set pavement on prepared surface
with sub-base 100 mm thick compacted Granular Sub-base as
per Clause 401.4 and base 75 mm thick compacted water bound
macadam grading 2 as per Clause 405.3. The 150 mm thick
hammer desired stones are laid in the herring one or stretched
bond pattern. The stones are compacted into the bedding sand
of 40 mm over the WBM base bounded by edge stone using
suitable compacting device. The gaps are filled with fine sand
stone dust as per Technical Specification Clause 413.4 MORD.

Unit = sqm
Taking output = 360 sqm
a) Labour
Mate
Mazdoor (Unskilled)
Mason 2nd class for laying set stone and edge stone
b) Machinery
Three wheel 80-100 kN static roller
Water tanker 6 kl capacity
c) Material
(1) Collection of fine sand
3.4x0.285x0.150x1.20 = 0.174
(2) Coarse sand
96x3.35x0.04x1.20 = 15.437 cum
(3) Collection of stone set stone
300 mmx200 mmx150 mm ; 17x304 = 5168 nos.
(4) Collection of edge stone
450 mmx200 mmx350 mm ; 2x232 = 464 nos.
(5) Water
d&e) Overheads & Contractors Profit
Cost of 360 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/360

345

RBR-SBBS
Index-code

RBR-SBBS-21

S. No

Description

Unit

Quantity

20

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

Crushed Cement Concrete Sub-base / Base


Breaking and crushing of material obtained by breaking
damaged cement concrete slabs to size range not exceeding 75
mm as specified in table 400.7 transporting the aggregates
obtained from breaking of cement concrete slabs at a lead of L
km., laying and compacting the same as sub base/ base course,
constructed as WBM to clause 404 except the use of screening
or binding Material (405 MORTH).

Unit = cum
Taking output =360 cum
a) Labour
Mate

day

Mazdoor skilled

day

6.16

Mazdoor for crushing broken cement concrete pavement


/ slabs into aggregate

day

102.00

Motor Grader,110 HP @ 50 cum/hr.


Vibratory roller 8 - 10 tonne@ 60 cum per hour
or
Smooth 3 wheeled steel roller @ 30cum/hr.
Front end loader 1 cum bucket capacity
Tipper 10 tonne capacity
Loading Charges
Unloading Charges

hour
hour

6.00
6.00

hour
hour
t.km

12.00
6.00
720 x L

Water tanker 6 KL capacity with 5 km lead @ 1 trip per hour

hour

12.00

KL

72.00

b)

Machinery

cum
cum

c)
Material
Material available from dismantled concrete slab after
crushing / breaking and only carriage is required to be
provided
Cost of water
d&e) Overheads & Contractors Profit
Cost for 360 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/360
Cost for 360 cum = a+b+c+d+e (Smooth Roller)
Rate per cum = (a+b+c+d+e)/360

Note : 1. It is assumed that dismantling of concrete slab/pavement has


been considered separately. Hence same is not added in this analysis.
Only labour for crushing the dismantled slab into aggregate has been
added. Carriage from stock pile to work site has been provided with a
lead of L km. Loading & unloading charges for actual quantity to be
allowed.
2. In case of breaking of slabs is done locally without involvement of
transportation, the provision of tipper, front end loader and
loading/unloading charges may be deleted.
3. As three wheeled smooth steel rollers are commonly in use, the same
has been provided as an alternative.

RBR-SBBS-21

21

Penetration Coat Over Top Layer of Crushed Cement


Concrete Base
Spraying of bitumen over cleaned dry surface of crushed cement
concrete base at the rate of 25 kg per 10 sqm by a bitumen
pressure distributor, spreading of key aggregates at the rate of
0.13 cum per 10 sqm by a mechanical grittier and rolling the
surface as per clause 506.3.8 MORTH

Unit = sqm
Taking output = 7500 sqm
a) Labour
Mate
Mazdoor skilled
Mazdoor (Unskilled)
b)
Machinery
Mechanical broom hydraulic @ 1250 sqm per hour
Hydraulic self propelled chips spreader
Front end loader 1 cum bucket capacity
Tipper 10 tonne capacity

day
day
day

2.56
12.00

hour
hour
hour
hour

6.00
6.00
6.00
6.00

346

RBR-SBBS
Index-code

S. No

Description

Unit

Quantity

3
hour
hour

4
3.9
4.28

cum
tonne

97.50
0.25

Vibratory roller 8 -10 tonnes @ 30 cum per hour


Bitumen pressure distributor @ 1750 sqm per hour

Material
Crushed stone aggregate 11.2 mm size
Bitumen (60-70 grade)
d&e) Overheads & Contractors Profit
Cost for 7500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/7500

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

c)

Note : Though vibratory roller is required only for 3 hours as per norms,
the same is required to be available at site for 6 hours to match with other
machines. The usage rates of vibratory roller may be multiplied with a
factor of 0.65.

RBR-SBBS-22

22

Construction of Median and Island with Soil Taken


from Roadway Cutting
Construction of Median and Island above road level with
approved material deposited at site from roadway cutting and
excavation for drain and foundation of other structures, spread,
graded and compacted as per clause 407 MORTH

Unit = cum
Taking output =21 cum
a) Labour
Mate
Mazdoor
b)
Machinery

day
day

6.24

Water tanker 6 KL with 5 km lead and 1 trip per hour

hour

1.00

Plate compactor @ 3.5 cum per hour


c)
Material
Cost of water
d&e) Overheads & Contractors Profit
Cost for 21 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/21

hour

6.00

KL

6.00

Note : This analysis provides for median and island with earthen top. In case the surface is required to
be turfed or planted with shrubs, the same is required to be provided separately as per analysis given in
the chapter on horticulture. In case granular fill is required to be paved, quantities of paving are required
to be calculated as per approved design and paid separately.

RBR-SBBS-23

23

Construction of Median and Island with Soil Taken


from Borrow Areas
Construction of median and Island above road level with
approved material brought from borrow pits, spread, sloped and
compacted as per clause 407 MORTH

Unit = cum
Taking output = 21 cum
a) Labour
Mate
Mazdoor
b)
Machinery
Water tanker with 5 km lead
Plate Compactor @ 3.5 cum per hour
Hydraulic Excavator1.0 cum bucket capacity @60 cum
per hour
Tipper 10 tonne capacity
Loading Charges
Unloading Charges
c)
Material
Cost of water
d&e) Overheads & Contractors Profit
Cost for 21 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/ 21

day
day

4.16

hour
hour
hour

1.00
6.00
0.50

t.km

52.5 x L

cum

cum

KL

6.00

Note : This analysis provides for median and island with earthen top. In case the surface is required to
be turfed or planted with shrubs, the same is required to be provided separately as per analysis given in
the chapter on horticulture. In case surface finish is of hard type, the same may be provided separately
as per approved design.
Loading & unloading charges for actual quantity to be allowed.

347

RBR-SBBS
Index-code

S. No

Description

Unit

Quantity

day
day
day

4.00
31.36

hour
hour
hour

0.75
2.00
6.00

cum

20.79

cum
cum

26.73
11.88

cum

6.75

cum
tonne

3.38
1.88

cum
tonne

3.84
1.83

each

3300.00

metre

22.50

KL

12.00

RBR-SBBS-24

24

RBR-SBBS-25

25

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

Construction of Shoulders
A. Earthen Shoulders
The rate as applicable for sub-grade construction may be
adopted.
B. Hard Shoulders
Rate as applicable for sub-base and or base may be
adopted as per approved design.
C. Paved shoulders
The rate may be adopted as applicable for different
layers of pavement depending upon approved design of
paved shoulders.
Footpaths and Separators
Construction of footpath/separator by providing a 150 mm
compacted granular sub base as per clause 401 and 25 mm
thick cement concrete grade M15, over laid with pre-cast
concrete tiles in cement mortar 1:3 including provision of all
drainage arrangements but excluding kerb channel (MORTH)

Unit = sqm
Taking output = 300 sqm
a) Labour
Mate
Mason
Mazdoor (Unskilled)
b)
Machinery
Vibratory road roller 8 -10 tonnes @60 cum per hour

Water tanker 6 KL capacity @ 1 trip per hour


Concrete mixer 0.4/0.28 cum per hour
c) Material
i) For Granular sub base material
53 mm to 26.5 mm @ 35 per cent
26.5 mm to 4.75 mm @ 45 per cent
2.36 mm below @ 20 per cent
ii) For cement concrete grade M 15, 7.5 cum
Aggregate 12 mm crushed @ 0.9 cum of concrete
Sand @ 0.45 cum/cum of concrete
Cement
iii) For cement plaster 1:3
Sand
Cement
iv) Pre-cast cement concrete tiles
Tiles size 300 x 300 mm and 25 mm thick
v) RCC pipes
Pipes 200 mm dia,2.5 m long for drainage
vi) Cost of water
d&e) Overheads & Contractors Profit
Cost for 300 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/300

General Note : The provisions towards Mate is included in the provision towards
unskilled Mazdoor.

348

RBR-BASC

Andhra Pradesh Standard Data


I. Roads and Bridges

Chapter - 5
BASES AND SURFACE COURSES (BITUMINOUS)
Index-code

RBR-BASC-1

S. No

Description

1
i
a

Unit Quantity
3

Rate
Rs.

Amount
Rs.

Remarks

Prime Coat
Low porosity
Providing and applying primer coat with bitumen emulsion
(SS-1) on prepared surface of granular base including
cleaning of road surface and spraying primer at the rate of
0.70-1.0 kg/sqm using mechanical means as per Technical
Specification Clause 502 MORD (for use on Wet mix
macadam & WBM)
Unit = sqm
Taking output = 1750 sqm
a) Labour
day
Mate
day
1.040
Mazdoor (Unskilled)
b) Machinery
hour
1.400
Hydraulic broom @ 1250 sqm per hour
hour
1.400
Air compressor 210 cfm
hour
1.000
Bitumen emulsion pressure distributor @ 1750 sqm/hour
hour
0.500
Water tanker 6 kl capacity 1 trip per hour
c) Material
t
1.480
Bitumen emulsion (SS-1) @ 0.85 kg per sqm
kl
3.000
Water
d&e) Overheads & Contractors Profit
Cost of 1750 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/1750
Providing and applying primer coat with bitumen
emulsion (medium setting) on prepared surface of
granular Base including clearing of road surface and
spraying primer at the rate of 0.60 kg/sqm using
mechanical means as per Tech. specification No 502
MORTH.
Unit = sqm
Taking output = 3500 sqm
a) Labour
day
Mate
day
2.080
Mazdoor (Unskilled)
b) Machinery
hour
2.800
Mechanical broom @ 1250 sqm per hour
hour
2.800
Air compressor 250 cfm
hour
2.000
Bitumen pressure distributor @ 1750 sqm per hour
hour
1.000
Water tanker 6 KL capacity @ 1 trip per hour
c) Material
t
2.100
Bitumen emulsion @ 0.6 kg per sqm
KL
6.000
Requirement of Water
d&e) Overheads & Contractors Profit
Cost for 3500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/3500
Note : Bitumen primer has been provided @ 0.60 kg per sqm as per clause 502.8. Payment
shall be made with adjustment, plus or minus, for the variation between this quantity and the
actual quantity approved by the Engineer after the preliminary trials referred to in clause No.
502.4.3.

351

RBR-BASC
Index-code

S. No

Description

2
ii

Unit Quantity
3

Rate
Rs.

Amount
Rs.

Remarks

Medium porosity
Providing and applying primer coat with Bitumen emulsion (SS-1)
(slow setting) on prepared surface of granular base including
cleaning of road surface and spraying primer at the rate of 0.90- 1.2
kg/sqm using mechanical means as per Technical Specification
Clause 502 MORD. (for use on Cement Stebilized Soil.)

Unit = sqm
Taking output = 1750 sqm
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Hydraulic broom @ 1250 sqm per hour
Air compressor 210 cfm
Bitumen emulsion pressure distributor @ 1750 sqm per hour

Water tanker 6 kl capacity 1 trip per hour


c) Material
Bitumen emulsion (SS-1) @ 1.05 kg per sqm
Water
d&e) Overheads & Contractors Profit
Cost of 1750 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/1750
iii High porosity

day

day

2.100

hour

1.400

hour

1.400

hour

1.000

hour

0.500

t
kl

1.830
3.000

Providing and applying primer coat with Bitumen emulsion (SS-1) on


prepared surface of granular base including cleaning of road surface
and spraying primer at the rate of 1.2-1.5 kg/sqm using mechanical
means as per Technical Specification Clause 502 MORD. (for use
on Gravel base)

Unit = sqm
Taking output = 1750 sqm
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Hydraulic broom @ 1250 sqm per hour
Air compressor 210 cfm
Bitumen emulsion pressure distributor @ 1750 sqm per hour

RBR-BASC-2

Water tanker 6 kl capacity 1 trip per hour


c) Material
Bitumen emulsion (SS-1) @ 1.35 kg per sqm
Water
d&e) Overheads & Contractors Profit
Cost of 1750 sqm = (a+b+c+d+e)
Rate per sqm = a+b+c+d+e/1750
Tack Coat

2
i

day

day

3.120

hour

1.400

hour

1.400

hour
hour

1.000
0.500

2.360

kl

3.000

day
day

1.040

hour

1.400

hour
hour

1.400
1.000

0.390

Providing and applying tack coat with Bitumen emulsion (RS-1)


(Rapid Setting) using emulsion distributor at the rate of 0.20 to 0.25
kg per sqm on the prepared bituminous surface cleaned with
Hydraulic broom as per Technical Specification Clause 503 MORD.

Unit = sqm
Taking output = 1750 sqm
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Hydraulic broom @ 1250 sqm per hour
Air compressor 210 cfm
Emulsion pressure distributor @1750 sqm per hour
c) Material
Bitumen emulsion (RS-1) @ 0.225 kg per sqm
d&e) Overheads & Contractors Profit
Cost of 1750 sqm = (a+b+c+d+e)
Rate per sqm = a+b+c+d+e/1750

352

RBR-BASC
Index-code

S. No

Description

Providing and applying tack coat with Bitumen emulsion (RS1) using emulsion distributor at the rate of 0.25 to 0.30 kg
per sqm on the prepared dry and hungry bituminous surface
cleaned with Hydraulic broom as per Technical Specification
Clause 503 MORD.
Unit = sqm
Taking output = 1750 sqm
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Hydraulic broom @ 1250 sqm per hour
Air compressor 210 cfm
Emulsion pressure distributor @1750 sqm per hour
c) Material
Bitumen emulsion (RS-1) @ 0.275 kg per sqm
d&e) Overheads & Contractors Profit
Cost of 1750 sqm = (a+b+c+d+e)
Rate per sqm = a+b+c+d+e/1750
iii Providing and applying tack coat with Bitumen emulsion (RS1) using emulsion distributor at the rate of 0.25 to 0.30 kg
per sqm on the prepared granular surfaces treated with
primer & cleaned with Hydraulic broom as per Technical
Specification Clause 503 MORD.
Unit = sqm
Taking output = 1750 sqm
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Hydraulic broom @ 1250 sqm per hour
Air compressor 210 cfm
Emulsion pressure distributor @1750 sqm per hour
c) Material
Bitumen emulsion (RS-1) @ 0.275 kg per sqm
d&e) Overheads & Contractors Profit
Cost of 1750 sqm = (a+b+c+d+e)
Rate per sqm = a+b+c+d+e/1750
iv Providing and applying tack coat with Bitumen emulsion (RS1) using emulsion pressure distributor at the rate of 0.30 to
0.35 kg per sqm on the prepared non-bituminous surfaces
(cement concrete pavement) cleaned with Hydraulic broom
as per Technical Speciation 503 MORD.

Unit Quantity
3

Rate
Rs.

Amount
Rs.

Remarks

ii

Unit = sqm
Taking output = 1750 sqm
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Hydraulic broom @ 1250 sqm per hour
Air compressor 210 cfm
Emulsion pressure distributor @1750 sqm per hour
c) Material
Bitumen emulsion (RS-1) @ 0.325 kg per sqm
d&e) Overheads & Contractors Profit
Cost of 1750 sqm = (a+b+c+d+e)
Rate per sqm = a+b+c+d+e/1750

day

day

1.040

hour

1.400

hour
hour

1.400
1.000

0.480

day

day

1.040

hour

1.400

hour

1.400

hour

1.000

0.480

day

day

1.040

hour

1.400

hour
hour

1.400
1.000

0.570

Note : 1. An output of 1750 sqm has been considered in case of tack coat
which can be covered by bituminous courses on the same day.
2. The use of cutback bitumen (Medium Curing grade) as per IS:217 shall
be restricted only for sites at sub-zero temperature or for emergency
applications as directed by the Engineer.

353

RBR-BASC
Index-code

S. No

Description

2
Providing and applying tack coat with bitumen emulsion using
emulsion pressure distributor at the rate of 0.20 kg per sqm on
the prepared bituminous/granular surface cleaned with
mechanical broom as per Tech. specification No 503 MORTH

RBR-BASC-3

3
i

Unit Quantity
3

Rate
Rs.

Amount
Rs.

Remarks

Unit = sqm
Taking output = 3500 sqm
a) Labour
day
Mate
day
2.080
Mazdoor (Unskilled)
b) Machinery
hour
2.800
Mechanical broom @ 1250 sqm per hour
hour
2.800
Air compressor 250 cfm
hour
2.000
Emulsion pressure distributor @ 1750 sqm per hour
c) Material
t
0.700
Bitumen emulsion @ 0.2 kg per sqm
d&e) Overheads & Contractors Profit
Cost for 3500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/3500
Note : 1. Bitumen emulsion has been provided @ 0.20 kg per sqm as per clause 503.8.
Payment shall be made with adjustment, plus or minus, for the variation between this quantity
and actual quantity approved by the Engineer after preliminary trials referred to in clause No.
503.4.3
2. An output of 3500 sqm has been considered in case of prime coat and tack coat which can
be covered by bituminous courses on the same day.
Bituminous Macadam
Providing and laying bituminous macadam with 40-60 TPH
hot mix plant using crushed aggregates of grading as per
Table 500.4 premixed with bituminous binder, transported to
site upto a lead of 1000 m laid over a previously prepared
surface with paver finisher to the required grade, level and
alignment and rolled to achieved the desired compaction as
per Technical Specification Clause 504 MORD (using
vibratory Roller 80-100 KN for intermediate rolling and 3
wheel roller 80-100 KN for initial and final rolling).
Unit = cum
Taking output = 102.5 cum (225 t)
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Skilled)
b) Machinery
Batch mix HMP 40-60 THP @ 40 t per hour actual output
Hydraulic broom @ 1250 sqm per hour
Air compressor 210 cfm
Paver finisher
Generator 125 KVA
Front end loader 1 cum bucket capacity
Tipper 5.5 cum, 10 t / 5-6 t capacity
Three wheel 80-100 kN static roller for initial break down
rolling, final and finishing rolling
Vibratory roller 80-100 kN for intermediate rolling
c) Material
(i) Bitumen @ 3.3 per cent of mix
(Weight of mix = 102.5 x 2.2 = 225 t)
(ii) Aggregate
Total weight of mix = 225 t
Weight of bitumen = 7.425 t
Weight of aggregate = 225 7.425 = 217.575 t
Taking density of aggregate = 1.5 t/cum
Volume of aggregate = 145.05 cum

day

day

10.000

day

3.520

hour
hour

6.000
1.100

hour

1.100

hour

6.000

hour

6.000

hour

6.000

hour

6.210

hour

12.000

hour

6.000

7.425

354

RBR-BASC
Index-code

S. No
1

Description
2

Grading (19 mm nominal size) :


25 -10 mm - 40 per cent
10 5 mm - 40 per cent
5 mm and below - 20 per cent
d&e) Overheads & Contractors Profit
Cost for 102.5 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/102.5

Unit Quantity
3

cum

58.020

cum

58.020

cum

29.010

Rate
Rs.

Amount
Rs.

Remarks

Note : 1. Although the rollers are required only for 3 hours as per norms of output, but the same have to
be available at site for six hours as the hot mix plant and paver will take six hours for mixing and paving
the output of 225 t considered in these analysis.
2. Quantity of bitumen has been taken for analysis purpose. The actual quantity will depend upon job mix
formula.
3. Labour for traffic control, watch and ward and other miscellaneous duties at site, including sundries
have been included in administrative overheads of the contractor.
4. In case BM is laid over freshly laid tack coat, provision of Hydraulic broom and 2 mazdoor for the same
shall be deleted as the same has been included in the cost of tack coat.
5. Analysis is based on 1000 m lead of mixed material. Cost of additional cartage may be added as per
site requirements.
ii

Providing and laying bituminous macadam with 100-120


TPH / 40-60 TPH hot mix plant producing an average
output of 75 tonnes/ 37.50 t per hour using crushed
aggregates of specified grading premixed with
bituminous binder, transported to site, laid over a
previously prepared surface with paver finisher to the
required grade, level and alignment and rolled as per
clauses 501.6 and 501.7 to achieve the desired
compaction as per Tech. specification No. 504 MORTH.
Unit = cum
Taking output = 205 cum (450 tonnes)
a) Labour
day
Mate
Mazdoor working with HMP, mechanical broom, paver, roller, day
asphalt cutter and assistance for setting out lines, levels and
layout of construction

14.000

Skilled mazdoor for checking line & levels


b) Machinery

day

5.840

Batch mix HMP 100-120 TPH @ 75 tonne per hour actual output

hour

6.000

hour
hour
hour
hour
hour
hour
hour
hour

12.000
2.200
6.000
6.000
6.000
3.900
3.900
3.900

14.850

cum
cum
cum
cum

43.510
130.550
72.530
43.510

OR
HMP 40-60 TPH @ 17 cum (37.5 Tonnes) / hour
Air compressor 250 cfm
Paver finisher 100 TPH
Generator 250 KVA
Front end loader 1 cum bucket capacity
Smooth wheeled roller 8-10 tonnes for initial break down rolling.

Vibratory roller 8 tonnes for intermediate rolling.


Finish rolling with 6-8 tonnes smooth wheeled tandem roller.

c) Material
i) Bitumen@ 3.3 per cent of mix
weight of mix = 205 x 2.2 = 450 tonne
ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 14.85 tonnes
Weight of aggregate = 450 -14.85 = 435.15 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 290.1 cum
Grading I ( 40 mm nominal size )
37.5 - 25 mm 15 per cent
25 - 10 mm 45 per cent
10 - 5 mm 25 per cent
5 mm and below15 per cent
or

355

RBR-BASC
Index-code

RBR-BASC-4

S. No

Description

Unit Quantity
3

Rate
Rs.

Amount
Rs.

Remarks

Grading II (19 mm nominal size)


116.04 Cum of 25-10mm @ 40%
cum 29.010
25 to 27mm IRC HBGM/C metal @ 40%
cum 29.010
19 to 22mm IRC HBGM/C metal @ 10%
cum 29.010
12 to 14mm IRC HBGM/C metal @ 10%
cum 29.010
9.5 to 11.2mm IRC HBGM/C metal @ 10%
116.04 Cum of 10-5mm @ 40%
cum 58.020
9.5 to 11.2mm IRC HBGM/C metal @ 20%
cum 58.020
5 to 7mm IRC HBGM/C metal @ 20%
58.02 Cum of 5mm below @ 20%
cum 29.010
5 to 7mm IRC HBGM/C metal @ 10%
cum 29.010
2.36mm & below @ 10%
* Any one of the alternative may be adopted as per approved
design
(i) for Grading I ( 40 mm nominal size )
d&e) Overheads & Contractors Profit
Cost for 205 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/205
(ii) for Grading II (19 mm nominal size)
d&e) Overheads & Contractors Profit
Cost for 205 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/205
Note in MORTH : 1. Although the rollers are required only for 3 hours as per norms of
output, but the same have to be available at site for six hours as the hot mix plant and paver
will take six hours for mixing and paving the output of 450 tonnes considered in this analysis.
To cater for the idle period of these rollers, their usage rates have been multiplied by a factor
of 0.65.
2. Quantity of Bitumen has been taken for analysis purpose. The actual quantity will depend
upon job mix formula.
3. Labour for traffic control, watch and ward and other miscellaneous duties at site including
sundries have been included in administrative overheads of the contractor.
4. In case BM is laid over freshly laid tack coat, provision of Mechanical broom and 2
mazdoors for the same shall be deleted as the same has been included in the cost of tack
coat.
Built-Up Spray Grout
i Providing, laying and rolling of built-up spray grout layer over
prepared base consisting of a two layer composite
construction of crushed coarse aggregates using motor
grader for aggregates. Key stone chips spreader may be
used with application of bituminous binder after each layer,
and with key aggregates placed on top of the second layer to
serve as a base, conforming to the line, grades and crosssection specified, the compacted layer thickness being 75
mm as per Technical Specification Clause 505 MORD.
(using Three wheel 80-100 KN static Roller/ Vibratory
Roller 80-100 kN).
A By Manual Means
Unit = sqm
Taking output = 800 sqm (60 cum)
(I) Bitumen (S-90)
a) Labour
day
Mate
day 106.000
Mazdoor (Unskilled)
day
10.000
Chips spreader (Stone Packer)
day
2.500
Bitumen Sprayer
day
25.500
Mazdoor (Semi-Skilled)
b) Machinery
6.000
Bitumen boiler oil fired, capacity 1000 litre fitted with spray hour
set
hour
6.000
Three wheel 80-100 kN static Roller

356

RBR-BASC
Index-code

S. No

Description

c) Material
Bitumen 30 kg per 10 sqm @ 15 kg per 10 sqm for each
layer (80 / 100 Grade)
Crushed stone coarse aggregate passing 53 mm and
retained on 2.8 mm sieve @ 0.5 cum per 10 sqm for each
layer
Key aggregates passing 22.4 mm and retained on 2.8 mm
sieve @ 0.13 cum per 10 sqm
d&e) Overheads & Contractors Profit
Cost of 800 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/800
(II) Bitumen (S-65)
a) Labour
Mate
Mazdoor (Unskilled)
Chips spreader (Stone Paker)
Bitumen Sprayer
Mazdoor (Semi-Skilled)
b) Machinery
Bitumen boiler oil fired, capacity 1000 litre fitted with spray set

Unit Quantity
3

2.400

cum

80.000

cum

10.400

day

day

106.000

day

10.000

day

2.500

day

25.500

hour

6.000
6.000

hour
Three wheel 80-100 kN static Roller
c) Material
Bitumen 30 kg per 10 sqm @ 15 kg per 10 sqm for each t
layer (60 / 70 Grade)
Crushed stone coarse aggregate passing 53 mm and retained on 2.8 cum
mm sieve @ 0.5 cum per 10 sqm for each layer
Key aggregates passing 22.4 mm and retained on 2.8 mm cum

sieve @ 0.13 cum per 10 sqm


d&e) Overheads & Contractors Profit
Cost of 800 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/800
By Mechanical Means
Unit = sqm
Taking output = 3000 sqm (225 cum)
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Skilled)
b) Machinery
Hydraulic self propelled chip spreader both for aggregates
and key aggregates @ 1500 sqm per hour for 3000 x 3 sqm
Bitumen pressure distributor for 3000x 2 sqm @ 1750 sqm/hour

Tipper 5.5 cum capacity


Three wheel 80-100 kN Static Roller @ 10 cum per hour
OR
vibratory roller 80 - 100 kN
Front end loader 1 cum bucket capacity
c) Material
Bitumen 30 kg per 10 sqm @ 15 kg per 10 sqm for each
layer (80 / 100 Grade)

Amount
Rs.

Remarks

2.400
80.000
10.400

day

day

8.000

day

2.400

hour

6.000

hour
hour

3.430
10.000

hour

22.500

hour

6.000

hour

5.000

9.000

Crushed stone coarse aggregate passing 53 mm and retained on 2.8 cum


mm sieve @ 0.5 cum per 10 sqm for each layer
Key aggregates passing 22.4 mm and retained on 2.8 mm cum

Rate
Rs.

300.000
39.000

sieve @ 0.13 cum per 10 sqm


d&e) Overheads & Contractors Profit
Cost for 3000 sqm = a+b+c+d+e (3 Wheel Roller)
Rate per sqm = (a+b+c+d+e)/3000
Cost for 3000 sqm = a+b+c+d+e (Vibratory Roller)
Rate per sqm = (a+b+c+d+e)/3000
Note : 2 tippers will be needed to match the capacity of hydraulic
chip spreader and front end loader.

357

RBR-BASC
Index-code

RBR-BASC-5

S. No

Description

Modified Penetration Macadam


Construction of penetration macadam over prepared base by
providing a layer of compacted crushed coarse aggregate
using chips spreader with alternate applications of
bituminous binder and key aggregates and rolling with a
three wheel 80-100 kN static roller as per Tech. Specification
No 506 MORD.
A 50 mm thick
Unit = sqm
Taking output = 4500 sqm (225 cum)
(I) Bitumen (S-90)
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Skilled)
b) Machinery
Hydraulic self propelled chip spreader both for aggregates
and key aggregates @ 1500 sqm per hour for 4500 x 2 sqm
= 9000 sqm
Bitumen pressure distributor for @ 1750 sqm per hour

Tipper 5.5 cum capacity for carriage of aggregates from


stockpile to chip spreader
Three wheel 80-100 kN Static Roller
Front end loader 1 cum bucked capacity
c) Material
Bitumen @ 1.75 kg per sqm
40 mm size hand broken metal @ 0.06 cum per sqm
12 mm size stone chips @ 0.018 cum per sqm
d&e) Overheads & Contractors Profit
Cost of 4500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/4500
B 75 mm thick
Unit = sqm
Taking output = 4500 sqm (337.5 cum)
(I) Bitumen (S-90)
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Skilled)
b) Machinery
Hydraulic self propelled chip spreader both for aggregates
and key aggregates @ 1500 sqm per hour for 4500 x 2 sqm
= 9000 sqm
Bitumen pressure distributor for @ 1750 sqm per hour
Tipper 5.5 cum capacity for carriage of aggregates from
stockpile to chip spreader
Three wheel 80-100 kN Static Roller
Front end loader 1 cum bucked capacity
c) Material
Bitumen @ 2 kg per sqm
40 mm size hand broken metal @ 0.09 cum per sqm
12 mm size stone chips @ 0.018 cum per sqm
d&e) Overheads & Contractors Profit
Cost of 4500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/4500

Unit Quantity
3

day

day

6.000

day

2.320

hour

6.000

hour

2.570

hour

10.000

hour

22.500

hour

6.000

7.870

cum

270.000

cum

81.000

day

day

8.000

day

2.400

hour

6.000

hour

2.570

hour

10.000

hour

33.750

hour

6.000

9.000

cum

405.000

cum

81.000

Rate
Rs.

Amount
Rs.

Remarks

358

RBR-BASC
Index-code

S. No

Description

Unit Quantity
3

Rate
Rs.

Amount
Rs.

Remarks

(II) Bitumen (S-65)

RBR-BASC-6

a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Skilled)
b) Machinery
Hydraulic self propelled chip spreader both for aggregates
and key aggregates @ 1500 sqm per hour for 4500 x 2 sqm
= 9000 sqm
Bitumen pressure distributor for @ 1750 sqm per hour
Tipper 5.5 cum capacity for carriage of aggregates from
stockpile to chip spreader
Three wheel 80-100 kN Static Roller
Front end loader 1 cum bucked capacity
c) Material
Bitumen @ 2 kg per sqm
40 mm size hand broken metal @ 0.09 cum per sqm
12 mm size stone chips @ 0.018 cum per sqm
d&e) Overheads & Contractors Profit
Cost of 4500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/4500
Bituminous Penetration Macadam
Construction of penetration macadam over prepared Base by
providing a layer of compacted crushed coarse aggregate
using chips spreader with alternate applications of
bituminous binder and key aggregates and rolling with a
smooth wheeled steel roller 8-10 tonne capacity to achieve
the desired degree of compaction as per Tech. Specification
No 505 MORTH.
A 50 mm thick

day

day

8.000

day

2.400

hour

6.000

hour

2.570

hour

10.000

hour

33.750

hour

6.000

9.000

cum

405.000

cum

81.000

day
day

6.000

day
Mazdoor skilled
b) Machinery
Hydraulic self propelled chip spreader both for aggregates hour
and key aggregates@ 1500 sqm per hour for 4500 x 2 sqm =
9000 sqm

2.320

Unit = sqm
Taking output = 4500 sqm (225 cum)
a) Labour
Mate
Mazdoor (Unskilled) including for brooming of key aggregates

6.000

Bitumen pressure distributor for @ 1750 sqm per hour

hour

2.570

Tipper 5.5 cum capacity for carriage of aggregates from


stockpile to chip spreader
Vibratory roller 8 tonnes
Front end loader 1 cum bucket capacity
c) Material
Bitumen@ 5 kg per sqm
Crushed stone coarse aggregate passing 45 mm and
retained on 2.8 mm sieve @ 0.06 cum per sqm
Key aggregates passing 22.4 mm and retained on 2.8 mm
sieve @ 0.015 cum per sqm
d&e) Overheads & Contractors Profit
Cost for 4500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/4500
Note : 2 tippers will be needed to match the capacity of
spreader and front end loader.

hour

10.000

hour
hour

6.000
6.000

t
cum

22.500
270.000

cum

67.500

chip

359

RBR-BASC
Index-code

S. No
1

Description
2

75 mm thick
Unit = sqm
Taking output = 4500 sqm (337.5 cum compacted).
a) Labour
Mate
Mazdoor (Unskilled) including for brooming of key aggregates

Mazdoor skilled
b) Machinery
Hydraulic self propelled chip spreader both for aggregates
and key aggregates@ 1500 sqm per hour for 4500 x 2 sqm
Bitumen pressure distributor for@ 1750 sqm per hour
Tipper 5.5 cum capacity for carriage of aggregates from
stockpile to chip spreader
Vibratory roller 8 tonnes
Front end loader 1 cum bucket capacity
c) Material
Bitumen@ 6.8 kg per sqm
Crushed stone coarse aggregate (loose passing 63 mm and
retained on 2.8 mm sieve @ 0.09 cum per sqm

RBR-BASC-7

Unit Quantity
3

day
day

8.000

day

2.400

hour

6.000

hour

2.570

hour

10.000

hour

6.000

hour

6.000

t
cum

30.600
405.000

Key aggregates passing 26.5 mm and retained on 2.8 mm cum


sieve @ 0.018 cum per sqm

81.000

Rate
Rs.

Amount
Rs.

Remarks

d&e) Overheads & Contractors Profit


Cost for 4500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/4500
Note : 2 tippers and 2 rollers will be needed to match the capacity
of chip spreader and front end loader.
Dense Graded Bituminous Macadam
Providing and laying dense graded bituminous macadam with 100120 TPH batch type HMP producing an average output of 75 tonnes
per hour using crushed aggregates of specified grading, premixed
with bituminous binder @ 4.0 to 4.5 per cent by weight of total mix
and filler, transporting the hot mix to work site, laying with a
hydrostatic paver finisher with sensor control to the required grade,
level and alignment, rolling with smooth wheeled, vibratory and
tandem rollers to achieve the desired compaction as per MoRTH
specification clause No. 507 complete in all respects.

Unit = cum
Taking output = 195 cum (450 tonnes)
a) Labour
Mate
Mazdoor (Unskilled) working with HMP, mechanical broom,
paver, roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction
Skilled mazdoor for checking line & levels
b) Machinery
Batch mix HMP @ 75 tonne per hour
Paver finisher hydrostatic with sensor control @ 75 cum per hour

Generator 250 KVA


Front end loader 1 cum bucket capacity
Tipper 10 tonne capacity
Add 10 per cent of cost of carriage to cover cost of loading
and unloading
smooth wheeled roller 8-10 tonnes for initial break down
rolling.
Vibratory roller 8 tonnes for intermediate rolling.
Finish rolling with 6-8 tonnes smooth wheeled tandem roller.

day

day

16.000

day

5.840

hour

6.000

hour
hour

6.000
6.000

hour

6.000

t.km

450 x L

hour

3.900

hour

3.900

hour

3.900

360

RBR-BASC
Index-code

S. No
1

Description
2

c) Materials
Bitumen @ 4.25 per cent of weight of mix
Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 19.13 tonnes
Weight of aggregate = 450 -19.13 = 430.87 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 287.25 cum
Grading - I 40 mm (Nominal Size)
37.5 - 25 mm 22 per cent
25 - 10 mm 13 per cent
10 -4.75 mm 19 per cent
4.75 mm and below 44 per cent
Filler @ 2 per cent of weight of aggregates (Cement)
or
Grading - II 19 mm (Nominal Size)
25 - 10 mm 30 per cent
10 - 5 mm 28 per cent
5 mm and below 40 per cent
Filler @ 2 per cent of weight of aggregates (Cement).
Any one of the alternative may be adopted as per approved
design
(i) For Grading I ( 40 mm nominal size )
d&e) Overheads & Contractors Profit
Cost for 195 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/195
(ii) For GradingII(19 mm nominal size)
d&e) Overheads & Contractors Profit
Cost for 195 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/195

Unit Quantity
3

19.130

cum

63.190

cum

37.340

cum

54.580

cum

126.390

8.620

cum

86.160

cum

80.430

cum

114.900

8.620

Rate
Rs.

Amount
Rs.

Remarks

Note : 1. Although the roller are required only for 3 hours as per norms of output, but the same have to be
available at site for six hours as the hot mix plant and paver will take six hours for mixing and paving the
output of 450 tonnes considered in this analysis. To cater for the idle period of these rollers, their usage
rates have been multiplied by a factor of 0.65.
2. Quantity of Bitumen has been taken for analysis purpose. The actual quantity will depend upon job mix
formula.
3. Labour for traffic control, watch and ward and other miscellaneous duties at site including sundries have
been included in administrative overheads of the contractor.
4. In case DBM is laid over freshly laid tack coat, provision of mechanical broom and 2 mazdoors shall be
deleted as the same has been included in the cost of tack coat.
5. The individual density for each size of aggregates to be used for construction I.e. 37.5-25 mm, 25-10
mm etc. should be found in the laboratory and accordingly the quantities should be amended for use in
field. The average density of 1.5 tonne/cum is only a reference density in this Data Book.
6. The individual percentage of aggregates should be calculated from the total weight of dry aggregates
i.e.. excluding the weight of bitumen. The weight of filler will also be 2 per cent by weight of dry
aggregates.

RBR-BASC-8

Semi-Dense Bituminous Concrete


Providing and laying semi dense bituminous concrete with 40-60 TPH
batch type HMP producing an average output of 37.5 tonnes per hour
using crushed aggregates of specified grading, premixed with
bituminous binder @ 4.5 to 5 per cent of mix and filler, transporting
the hot mix to work site, laying with a hydrostatic paver finisher with
sensor control to the required grade, level and alignment, rolling with
smooth wheeled, vibratory and tandem rollers to achieve the desired
compaction as per MoRTH specification clause No. 508 complete in
all respects

Unit = cum
Taking output = 195 cum (450 tonnes)
a) Labour
day
Mate
Mazdoor (Unskilled) working with HMP, mechanical broom, day
paver, roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction
Skilled mazdoor for checking line & levels
b) Machinery
HMP 40-60 TPH
Paver finisher hydrostatic with sensor control @ 75 cum per
hour
Generator 250 KVA
Front end loader 1 cum bucket capacity
Smooth wheeled roller 8-10 tonnes for initial break rolling. (6
x 0.65)
Vibratory roller 8 tonnes for intermediate rolling.
Finish rolling with 6-8 tonnes smooth wheeled tandem roller
c) Material
Grading I: 13 mm (Nominal Size)
i) Bitumen@ 4.5 per cent of weight of mix
ii) Aggregate

14.000

day

5.840

hour

11.000

hour

6.000

hour

6.000

hour

6.000

hour

3.900

hour

3.900

hour

3.900

20.250

361

RBR-BASC
Index-code

S. No
1

Description
2

Total weight of mix = 450 tonnes


Weight of bitumen = 20.25 tonnes
Weight of aggregate = 450-20.25 = 429.75 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 286.5 cum
13.2 - 10 mm20 per cent
10 - 5 mm 38 per cent
5 mm and below 40 per cent
Filler @ 2 per cent of weight of aggregates.(Cement)
or
Grading II: 10 mm (Nominal Size)

Unit Quantity
3

cum

57.300

cum

108.870

cum

114.600

8.620

Bitumen 80/100 Grade @ 5 per cent of weight of mix

22.500

OR
Bitumen 60/70 Grade @ 5 per cent of weight of mix

22.500

cum

81.225

cum

81.225

cum

58.425

cum

58.425

cum

5.700

weight of mix = 450 tonne


Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 22.5 tonnes
Weight of aggregate = 450 -22.50 = 427.50 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 285 cum
9.5 - 11.2 mm IRC HBG M/C Chips
5 - 7 mm IRC HBG M/C Chips
5 - 7 mm IRC HBG M/C Chips
Below 2.36 mm
Filler @ 2 per cent of weight of aggregates.
*Any one of the alternative may be adopted as per
approved design
(i) For Grading I ( 13 mm nominal size )
d&e) Overheads & Contractors Profit
Cost for 195 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/195

Rate
Rs.

Amount
Rs.

Remarks

362

RBR-BASC
Index-code

S. No
1

Description
2

Unit Quantity
3

Rate
Rs.

Amount
Rs.

Remarks

(ii) For Grading II (10 mm nominal size)


d&e) Overheads & Contractors Profit
Cost for 195 cum = a+b+c+d+e (80 / 100 Grade BT)
Rate per cum = (a+b+c+d+e)/195
Cost for 195 cum = a+b+c+d+e (60 / 70 Grade BT)
Rate per cum = (a+b+c+d+e)/195
Note : 1. Although the rollers are required only for 3 hours as per norms of output, but the same have to
be available at site for six hours as the hot mix plant and paver will take six hours for mixing and paving
the output of 450 tonnes considered in this analysis. To cater for the idle period of these rollers, their
usage rates have been multiplied by a factor of 0.65
2. Quantity of Bitumen has been taken for analysis purpose. The actual quantity will depend upon job mix
formula.
3. Labour for traffic control, watch and ward and other miscellaneous duties at site including sundries have
been included in administrative overheads of the contractor.
4. In case SDBC is laid over freshly laid tack coat, provision of broom and 2 mazdoor shall be deleted as
the same has been included in the cost of tack coat.
5. The quantity of Bitumen to be adjusted as per job mix formula.

RBR-BASC-9

Bituminous Concrete
Providing and laying bituminous concrete with 100-120 TPH
batch type hot mix plant producing an average output of 75
tonnes per hour using crushed aggregates of specified
grading, premixed with bituminous binder @ 5.4 to 5.6 per
cent of mix and filler, transporting the hot mix to work site,
laying with a hydrostatic paver finisher with sensor control to
the required grade, level and alignment, rolling with smooth
wheeled, vibratory and tandem rollers to achieve the desired
compaction as per MORTH specification clause No. 509
complete in all respects
Unit = cum
Taking output = 191 cum (450 tonnes)
a) Labour
Mate
Mazdoor (Unskilled) working with HMP, mechanical broom,
paver, roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction
Skilled mazdoor for checking line & levels
b) Machinery
Batch mix HMP @ 75 tonne per hour
Paver finisher hydrostatic with sensor control @ 75 cum per hour

day
day

16.000

day

5.840

hour

6.000

hour
hour

6.000
6.000

Generator 250 KVA


hour
Front end loader 1 cum bucket capacity
t.km
Tipper 10 tonne capacity
Add 10 per cent of cost of carriage to cover cost of loading
and unloading
Smooth wheeled roller 8-10 tonnes for initial break down rolling.

6.000
450 x L

Vibratory roller 8 tonnes for intermediate rolling.

hour
hour

3.900
3.900

Finish rolling with 6-8 tonnes smooth wheeled tandem roller.

hour

3.900

22.500

cum

99.750

c) Material
i) Bitumen@ 5 per cent of weight of mix
ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 22.5 tonnes
Weight of aggregate = 450 -22.50 = 427.50 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 285 cum
* Grading - I-19 mm (Nominal Size)
20 - 10 mm 35 per cent
10 - 5 mm 23 per cent
5 mm and below 40 per cent
Filler @ 2 per cent of weight of aggregates.(Cement)

cum

65.550

cum

114.000

8.620

363

RBR-BASC
Index-code

S. No
1

Description
2

Unit Quantity
3

or
Grading - II-13 mm (Nominal Size)
cum
13.2 - 10 mm 30 per cent
cum
10 - 5 mm 25 per cent
cum
5 mm and below43 per cent
t
Filler @ 2 per cent of weight of aggregates.(Cement)
Any one of the alternative may be adopted as per
approved design
(i) for Grading-I ( 19 mm nominal size )
d&e) Overheads & Contractors Profit
Cost for 191 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/191
(ii) For Grading-II(13 mm nominal size)
d&e) Overheads & Contractors Profit
Cost for 191 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/191

Rate
Rs.

Amount
Rs.

Remarks

85.500
71.250
122.550
8.620

Note : 1. Although the rollers are required only for 3 hours as per norms of output, but the same have to
be available at site for six hours as the hot mix plant and paver will take six hours for mixing and paving
the output of 450 tonnes considered in this analysis. To cater for the idle period of these rollers, their
usage rates have been multiplied by a factor of 0.65
2.Quantity of Bitumen has been taken for analysis purpose. The actual quantity will depend upon job mix
formula.
3. Labour for traffic control, watch and ward and other miscellaneous duties at site including sundries have
been included in administrative overheads of the contractor.
4. In case BC is laid over freshly laid tack coat, provision of mechanical broom and 2 mazdoors shall be
deleted as the same has been included in the cost of tack coat.
5. The individual density for each size of aggregates to be used for construction i.e. 37.5-25 mm, 25-10
mm etc. should be found in the laboratory and accordingly the quantities should be amended for use in
field. The average density of 1.5 tonne/cum is only a reference density in this Data Book.
6. The individual percentage of aggregates should be calculated from the total weight of dry aggregates
i.e.. excluding the weight of bitumen. The weight of filler will also be 2 per cent by weight of dry
aggregates.

RBR-BASC-10

10

Surface Dressing using Bituminous (Penetrations grade /


modified bitumen) Binder
Providing and laying surface dressing as wearing course consisting of
a layer of bituminous binder laid on the prepared surface, followed by
a cover of crushed stone aggregates of specified size and rolling with
three wheel 80-100 kN static roller including cleaning the road surface
as per Technical Specification Clause 507 MORD.
A

By Manual Means
Case I: Using Nominal chipping size 13.2 mm
(I) Bitumen (S-90)
Unit = sqm
Taking output = 900 sqm
a) Labour
Mate
Bitumen Sprayer
Mazdoor (Unskilled)
Mazdoor (Semi-Skilled)
b) Machinery

day

day

1.000

day

58.000

day

8.600

hour

2.250

hour
Three wheel 80-100 kN static roller
L.S.
Add: 0.5 per cent of (a) Labour for sundries
c) Material
t
Bitumen (S-90) @ 1.00 kg per sqm
Crushed stone chipping, 13.2 mm nominal size @ 0.010 cum cum
per sqm
d&e) Overheads & Contractors Profit
Cost of 900 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/900

2.250

Bitumen boiler oil fired, capacity 1000 litre fitted with spray set

0.900
9.000

364

RBR-BASC
Index-code

S. No

Description

Unit Quantity
3

Rate
Rs.

Amount
Rs.

Remarks

(II) Bitumen (S-65)

Unit = sqm
Taking output = 900 sqm
a) Labour
Mate
Bitumen Sprayer
Mazdoor (Unskilled)
Mazdoor (Semi-Skilled)
b) Machinery
Bitumen boiler oil fired, capacity 1000 litre fitted with spray
set
Three wheel 80-100 kN static roller
Add: 0.5 per cent of (a) Labour for sundries
c) Material
Bitumen (S-65) @ 1.00 kg per sqm
Crushed stone chipping, 13.2 mm nominal size @ 0.010 cum
per sqm
d&e) Overheads & Contractors Profit
Cost of 900 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/900
(III) Polymer Modified Bitumen
Unit = sqm
Taking output = 900 sqm
a) Labour
Mate
Bitumen Sprayer
Mazdoor (Unskilled)
Mazdoor (Semi-Skilled)
b) Machinery
Bitumen boiler oil fired, capacity 1000 litre fitted with spray set

Three wheel 80-100 kN static roller


Add: 0.5 per cent of (a) Labour for sundries
c) Material
Polymer Modified Bitumen @ 1.00 kg per sqm
Crushed stone chipping, 13.2 mm nominal size @ 0.010 cum
per sqm
d&e) Overheads & Contractors Profit
Cost of 900 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/900
(IV) Crumb Rubber Modified Bitumen
Unit = sqm
Taking output = 900 sqm
a) Labour
Mate
Bitumen Sprayer
Mazdoor (Unskilled)
Mazdoor (Semi-Skilled)
b) Machinery
Bitumen boiler oil fired, capacity 1000 litre fitted with spray
set
Three wheel 80-100 kN static roller
Add: 0.5 per cent of (a) Labour for sundries
c) Material
Crumb Rubber Modified Bitumen @ 1.00 kg per sqm
Crushed stone chipping, 13.2 mm nominal size @ 0.010 cum
per sqm
d&e) Overheads & Contractors Profit
Cost of 900 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/900

day

day

1.000

day

58.000

day

8.600

hour

2.250

hour

2.250

L.S.
t

0.900

cum

9.000

day

day

1.000

day

58.000

day

8.600

hour

2.250

hour
L.S.

2.250

0.900

cum

9.000

day

day

1.000

day

58.000

day

8.600

hour

2.250

hour

2.250

L.S.
t
cum

0.900
9.000

365

RBR-BASC
Index-code

S. No
1

Description

2
(V) Natural Rubber Modified Bitumen

Unit = sqm
Taking output = 900 sqm
a) Labour
Mate
Bitumen Sprayer
Mazdoor (Unskilled)
Mazdoor (Semi-Skilled)
b) Machinery
Bitumen boiler oil fired, capacity 1000 litre fitted with spray
set
Three wheel 80-100 kN static roller
Add: 0.5 per cent of (a) Labour for sundries
c) Material
Natural Rubber Modified Bitumen @ 1.00 kg per sqm
Crushed stone chipping, 13.2 mm nominal size @ 0.010 cum
per sqm
d&e) Overheads & Contractors Profit
Cost of 900 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/900
Case II: Using Nominal chipping size 9.5 mm
Manual Means
(I) Bitumen (S-90)
Unit = sqm
Taking output = 1000 sqm
a) Labour
Mate
Bitumen Sprayer
Mazdoor (Unskilled)
Mazdoor (Semi-Skilled)
b) Machinery
Bitumen boiler oil fired, capacity 1000 litre fitted with spray
set
Three wheel 80-100 kN static roller
c) Material
Bitumen (S-90) @ 0.90 kg per sqm
Crushed stone chipping, 9.5 mm nominal size @ 0.008 cum
per sqm
d&e) Overheads & Contractors Profit
Cost of 1000 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/1000
(II) Bitumen (S-65)
Unit = sqm
Taking output = 1000 sqm
a) Labour
Mate
Bitumen Sprayer
Mazdoor (Unskilled)
Mazdoor (Semi-Skilled)
b) Machinery
Bitumen boiler oil fired, capacity 1000 litre fitted with spray
set
Three wheel 80-100 kN static roller
c) Material
Bitumen (S-65) @ 0.90 kg per sqm
Crushed stone chipping, 9.5 mm nominal size @ 0.008 cum
per sqm
d&e) Overheads & Contractors Profit
Cost of 1000 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/1000

Unit Quantity
3

day

day

1.000

day

58.000

day

8.600

hour

2.250

hour
L.S.

2.250

0.900

cum

9.000

day

day

1.000

day

58.000

day

8.600

hour

2.000

hour

2.000

0.900

cum

8.000

day

day

1.000

day

58.000

day

8.600

hour

2.000

hour

2.000

0.900

cum

8.000

Rate
Rs.

Amount
Rs.

Remarks

366

RBR-BASC
Index-code

S. No

Description

Unit Quantity
3

Rate
Rs.

Amount
Rs.

Remarks

(III) Polymer Modified Bitumen

Unit = sqm
Taking output = 1000 sqm
a) Labour
Mate
Bitumen Sprayer
Mazdoor (Unskilled)
Mazdoor (Semi-Skilled)
b) Machinery
Bitumen boiler oil fired, capacity 1000 litre fitted with spray
set
Three wheel 80-100 kN static roller
c) Material
Polymer Modified Bitumen @ 0.90 kg per sqm
Crushed stone chipping, 9.5 mm nominal size @ 0.008 cum
per sqm
d&e) Overheads & Contractors Profit
Cost of 1000 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/1000

day

day

1.000

day

58.000

day

8.600

hour

2.000

hour

2.000

0.900

cum

8.000

(IV) Crumb Rubber Modified Bitumen

Unit = sqm
Taking output = 1000 sqm
a) Labour
Mate
Bitumen Sprayer
Mazdoor (Unskilled)
Mazdoor (Semi-Skilled)
b) Machinery
Bitumen boiler oil fired, capacity 1000 litre fitted with spray
set
Three wheel 80-100 kN static roller
c) Material
Crumb Rubber Modified Bitumen @ 0.90 kg per sqm
Crushed stone chipping, 9.5 mm nominal size @ 0.008 cum
per sqm
d&e) Overheads & Contractors Profit
Cost of 1000 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/1000

day

day

1.000

day

58.000

day

8.600

hour

2.000

hour

2.000

0.900

cum

8.000

(V) Natural Rubber Modified Bitumen

Unit = sqm
Taking output = 1000 sqm
a) Labour
Mate
Bitumen Sprayer
Mazdoor (Unskilled)
Mazdoor (Semi-Skilled)
b) Machinery

day

day

1.000

day

58.000

day

8.600

hour

2.000

hour
Three wheel 80-100 kN static roller
c) Material
t
Natural Rubber Modified Bitumen @ 0.90 kg per sqm
Crushed stone chipping, 9.5 mm nominal size @ 0.008 cum cum
per sqm
d&e) Overheads & Contractors Profit
Cost of 1000 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/1000

2.000

Bitumen boiler oil fired, capacity 1000 lt fitted with spray set

0.900
8.000

367

RBR-BASC
Index-code

S. No

Description

Unit Quantity
3

Rate
Rs.

Amount
Rs.

Remarks

By Mechanical Means
Case I: Using Nominal chipping size 13.2 mm
(I) Bitumen (S-90)
Unit = sqm
Taking output = 7500 sqm
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Skilled)
b) Machinery
Hydraulic broom @ 1250 sqm per hour
Air compressor 210 cfm

day

day

9.000

day

2.440

hour
hour

6.000
6.000

hour

6.000

Tipper 5.5 cum - 10 t capacity for carriage of stone chips from hour
stockpile on road side to chip spreader
hour
Front end loader 1 cum bucket capacity
hour
Bitumen pressure distributor
hour
Three wheel 80-100 kN static roller weight

6.000

Hydraulic self propelled chip spreader @ 1500 sqm per hour

c) Material
t
Bitumen (S-90) @ 1.00 kg per sqm
Crushed stone chipping, 13.2 mm nominal size @ 0.010 cum cum
per sqm
d&e) Overheads & Contractors Profit
Cost of 7500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/7500
(II) Bitumen (S-65)
Unit = sqm
Taking output = 7500 sqm
a) Labour
day
Mate
day
Mazdoor (Unskilled)
day
Mazdoor (Skilled)
b) Machinery
hour
Hydraulic broom @ 1250 sqm per hour
hour
Air compressor 210 cfm
Hydraulic self propelled chip spreader @ 1500 sqm per hour

hour
Tipper 5.5 cum - 10 t capacity for carriage of stone chips hour

from stockpile on road side to chip spreader


Front end loader 1 cum bucket capacity
Bitumen pressure distributor
Three wheel 80-100 kN static roller weight
c) Material
Bitumen (S-65) @ 1.00 kg per sqm
Crushed stone chipping, 13.2 mm nominal size @ 0.010 cum
per sqm
d&e) Overheads & Contractors Profit
Cost of 7500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/7500
(III) Polymer Modified Bitumen
Unit = sqm
Taking output = 7500 sqm
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Skilled)
b) Machinery
Hydraulic broom @ 1250 sqm per hour
Air compressor 210 cfm
Hydraulic self propelled chip spreader @ 1500 sqm per hour

hour

6.000
6.000
18.750
7.500
75.000

9.000
2.440
6.000
6.000
6.000
6.000
6.000

hour

6.000

hour

18.750

7.500

cum

75.000

day

day

9.000

day

2.440

hour

6.000

hour

6.000

hour

6.000

Tipper 5.5 cum - 10 t capacity for carriage of stone chips hour


from stockpile on road side to chip spreader

6.000

368

RBR-BASC
Index-code

S. No

Description

Front end loader 1 cum bucket capacity


Bitumen pressure distributor
Three wheel 80-100 kN static roller weight
c) Material
Polymer Modified Bitumen @ 1.00 kg per sqm
Crushed stone chipping, 13.2 mm nominal size @ 0.010 cum
per sqm
d&e) Overheads & Contractors Profit
Cost of 7500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/7500
(IV) Crumb Rubber Modified Bitumen
Unit = sqm
Taking output = 7500 sqm
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Skilled)
b) Machinery
Hydraulic broom @ 1250 sqm per hour
Air compressor 210 cfm
Hydraulic self propelled chip spreader @ 1500 sqm /hour
Tipper 5.5 cum - 10 t capacity for carriage of stone chips
from stockpile on road side to chip spreader
Front end loader 1 cum bucket capacity
Bitumen pressure distributor
Three wheel 80-100 kN static roller weight
c) Material
Crumb Rubber Modified Bitumen @ 1.00 kg per sqm
Crushed stone chipping, 13.2 mm nominal size @ 0.010 cum
per sqm
d&e) Overheads & Contractors Profit
Cost of 7500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/7500
(V) Natural Rubber Modified Bitumen
Unit = sqm
Taking output = 7500 sqm
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Skilled)
b) Machinery
Hydraulic broom @ 1250 sqm per hour
Air compressor 210 cfm

Unit Quantity
3
hour

4
6.000

hour

6.000

hour

18.750

7.500

cum

75.000

day

day

9.000

day

2.440

hour

6.000

hour

6.000

hour

6.000

hour

6.000

hour

6.000

hour

6.000

hour

18.750

7.500

cum

75.000

day

day

9.000

day

2.440

hour

6.000

hour

6.000

hour
Tipper 5.5 cum - 10 t capacity for carriage of stone chips hour

6.000
6.000

Hydraulic self propelled chip spreader @ 1500 sqm per hour

from stockpile on road side to chip spreader


Front end loader 1 cum bucket capacity
Bitumen pressure distributor
Three wheel 80-100 kN static roller weight
c) Material
Natural Rubber Modified Bitumen @ 1.00 kg per sqm

hour

6.000

hour

18.750

Amount
Rs.

Remarks

6.000

hour

Crushed stone chipping, 13.2 mm nominal size @ 0.010 cum cum


per sqm
d&e) Overheads & Contractors Profit
Cost of 7500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/7500

Rate
Rs.

7.500
75.000

369

RBR-BASC
Index-code

S. No

Description

Case II: Using Nominal chipping size 9.5 mm


Mechanical Means
(I) Bitumen (S-90)
Unit = sqm
Taking output = 7500 sqm
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Skilled)
b) Machinery
Hydraulic broom @ 1250 sqm per hour
Air compressor 210 cfm

Unit Quantity
3

day

day

9.000

day

2.440

hour

6.000

hour

6.000

hour
Tipper 5.5 cum - 10 t capacity for carriage of stone chips hour

6.000
6.000

Hydraulic self propelled chips spreader @ 1500 sqm / hour

from stockpile on road side to chips spreader


hour
Front end loader 1 cum bucket capacity
hour
Bitumen pressure distributor @ 1750 sqm per hour
hour
Three wheel 80-100 kN static roller weight
c) Material
t
Bitumen (S-90) @ 0.90 kg per sqm
Crushed stone chipping, 9.5 mm nominal size @ 0.008 cum cum
per sqm
d&e) Overheads & Contractors Profit
Cost of 7500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/7500
(II) Bitumen (S-65)
Unit = sqm
Taking output = 7500 sqm
a) Labour
day
Mate
day
Mazdoor (Unskilled)
day
Mazdoor (Skilled)
b) Machinery
hour
Hydraulic broom @ 1250 sqm per hour
hour
Air compressor 210 cfm
Hydraulic self propelled chips spreader @1500 sqm per hour

hour
Tipper 5.5 cum - 10 t capacity for carriage of stone chips hour

from stockpile on road side to chips spreader


hour
Front end loader 1 cum bucket capacity
hour
Bitumen pressure distributor @ 1750 sqm per hour
hour
Three wheel 80-100 kN static roller weight
c) Material
t
Bitumen (S-65) @ 0.90 kg per sqm
Crushed stone chipping, 9.5 mm nominal size @ 0.008 cum cum
per sqm
d&e) Overheads & Contractors Profit
Cost of 7500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/7500
(III) Polymer Modified Bitumen
Unit = sqm
Taking output = 7500 sqm
a) Labour
day
Mate
day
Mazdoor (Unskilled)
day
Mazdoor (Skilled)
b) Machinery
hour
Hydraulic broom @ 1250 sqm per hour
hour
Air compressor 210 cfm
Hydraulic self propelled chips spreader @ 1500 sqm per hour

hour
Tipper 5.5 cum - 10 t capacity for carriage of stone chips hour

Rate
Rs.

Amount
Rs.

Remarks

6.000
6.000
15.000
6.750
60.000

9.000
2.440
6.000
6.000
6.000
6.000
6.000
6.000
15.000
6.750
60.000

9.000
2.440
6.000
6.000
6.000
6.000

from stockpile on road side to chips spreader

370

RBR-BASC
Index-code

S. No

Description

Unit Quantity
3

hour
Front end loader 1 cum bucket capacity
hour
Bitumen pressure distributor @ 1750 sqm per hour
hour
Three wheel 80-100 kN static roller weight
c) Material
t
Polymer Modified Bitumen @ 0.90 kg per sqm
Crushed stone chipping, 9.5 mm nominal size @ 0.008 cum cum
per sqm
d&e) Overheads & Contractors Profit
Cost of 7500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/7500
(IV) Crumb Rubber Modified Bitumen
Unit = sqm
Taking output = 7500 sqm
a) Labour
day
Mate
day
Mazdoor (Unskilled)
day
Mazdoor (Skilled)
b) Machinery
hour
Hydraulic broom @ 1250 sqm per hour
hour
Air compressor 210 cfm
Hydraulic self propelled chips spreader @ 1500 sqm per hour

hour
Tipper 5.5 cum - 10 t capacity for carriage of stone chips hour

from stockpile on road side to chips spreader


Front end loader 1 cum bucket capacity
Bitumen pressure distributor @ 1750 sqm per hour
Three wheel 80-100 kN static roller weight
c) Material
Crumb Rubber Modified Bitumen @ 0.90 kg per sqm

hour

hour

2.440
6.000
6.000
6.000
6.000
6.000

6.750
60.000

9.000
2.440
6.000
6.000
6.000
6.000
6.000
6.000

hour

15.000

9.000

hour

Crushed stone chipping, 9.5 mm nominal size @ 0.008 cum cum


per sqm
d&e) Overheads & Contractors Profit
Cost of 7500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/7500

6.750

6.000

hour
Tipper 5.5 cum - 10 t capacity for carriage of stone chips hour

60.000

15.000

Hydraulic self propelled chips spreader @ 1500 sqm per hour

Remarks

6.000

hour
t

Amount
Rs.

15.000

hour

Crushed stone chipping, 9.5 mm nominal size @ 0.008 cum cum


per sqm
d&e) Overheads & Contractors Profit
Cost of 7500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/7500
(V) Natural Rubber Modified Bitumen
Unit = sqm
Taking output = 7500 sqm
a) Labour
day
Mate
day
Mazdoor (Unskilled)
day
Mazdoor (Skilled)
b) Machinery
hour
Hydraulic broom @ 1250 sqm per hour
hour
Air compressor 210 cfm

from stockpile on road side to chips spreader


Front end loader 1 cum bucket capacity
Bitumen pressure distributor @ 1750 sqm per hour
Three wheel 80-100 kN static roller weight
c) Material
Natural Rubber Modified Bitumen @ 0.90 kg per sqm

4
6.000

Rate
Rs.

6.750
60.000

371

RBR-BASC
Index-code

S. No

Description

1
11

RBR-BASC-11

Unit Quantity
3

Rate
Rs.

Amount
Rs.

Remarks

Providing and laying surface dressing as wearing course in


single coat using crushed stone aggregates of specified size
on a layer of bituminous binder laid on prepared surface and
rolling with 8-10 tonne smooth wheeled steel roller as per
Tech Specification No 509 & 510 MORTH
Mechanical Means
Unit = sqm
Taking output = 9000 sqm
Case 1 :-19 mm nominal chipping size
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor skilled
b) Machinery
Mechanical broom @ 1250 sqm per hour
Air compressor 250 cfm
Hydraulic self propelled chip spreader @ 1500 sqm/hour
Tipper 10 tonne capacity for carriage of stone chips from
stockpile on road side to chip spreader
Front end loader 1 cum bucket capacity
Bitumen pressure distributor
Smooth wheeled roller 8-10 tonne weight
c) Material
Bitumen@ 1.20 kg per sqm
Crushed stone chipping, 19 mm nominal size @ 0.015 cum
per sqm
d&e) Overheads & Contractors Profit
Cost for 9000 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/9000
Case 2 : 13 mm nominal size chipping
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor skilled
b) Machinery
Mechanical broom @ 1250 sqm per hour
Air compressor 250 cfm

day

day

9.000

day

2.440

hour

7.200

hour

7.200

hour

6.000

hour

6.000

hour

6.000

hour

6.000

hour

6.000

10.800

cum

135.000

day

day

9.000

day

2.440

hour

7.200

hour

7.200

Hydraulic self propelled chip spreader @ 1500 sqm per hour

hour

6.000

Tipper 10 tonne capacity for carriage of stone chips from


stockpile on road side to chip spreader
Front end loader 1 cum bucket capacity
Bitumen pressure distributor @ 1750 sqm per hour
Vibratory roller 8-10 tonne weight
c) Material
Bitumen@ 1.00 kg per sqm
Crushed stone chipping,13 mm nominal size @ 0.01 cum per
sqm
d&e) Overheads & Contractors Profit
Cost for 9000 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/9000

hour

6.000

hour

6.000

hour

6.000

hour

6.000

9.000

cum

90.000

Note : 1. Where the proposed aggregate fails to pass the stripping test, an approved adhesion agent may
be added to the binder as per clause 510.2.4. Alternatively, chips may be pre-coated as per clause
510.2.5
2. Input for the second coat, where required, will be the same as per the Ist coat mentioned above

372

RBR-BASC
Index-code

S. No
1

Description
2

ii

12

Rate
Rs.

Amount
Rs.

Remarks

Case 3 : Using 6 mm nominal size chipping


Providing and laying surface dressing in single coat
using 6 mm nominal size IRC HBG machine crushed
stone aggregates @ 0.004 cum / sqm on a layer of
bitumen binder of 80/100 grade @ 0.75 kg / sqm laid on
prepared surface and rolling with 8-10 T Power Road
Roller etc., complete for finished item of work as per
MoRT&H Specification 510 (4th Revision) and as directed
by the Engineer-in-charge.
Unit = sqm
Taking output = 9000 sqm
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor skilled
b) Machinery
Mechanical broom @ 1250 sqm/hr.
Air compressor 250 cfm

RBR-BASC-12

Unit Quantity

day

day

9.000

day

2.440

hour

7.200

hour

7.200

Hydraulic self propelled chip spreader @ 1500 sqm/hr.

hour

6.000

Tipper 10Tonne capacity for carriage of stone chips from


stock pile on road side to chip spreader
Front end loader 1 cum bucket capacity
Bitumen pressure distributor @1750 sqm/hr
Smooth wheeled roller 8 Ton
c) Material
Bitumen 80/100 @0.75 Kg/sqm
or
Bitumen 60/70 @0.75 Kg/sqm
Crushed stone chippings 6 mm nominal size @0.004
cum/sqm
d&e) Overheads & Contractors Profit
Cost for 9000 sqm = a+b+c+d (80/100 BT)
Rate per sqm = (a+b+c+d)/9000
Cost for 9000 sqm = a+b+c+d (60/70 BT)
Rate per sqm = (a+b+c+d)/9000
Surface Dressing using Bitumen Emulsion

hour

6.000

hour

6.000

hour

6.000

hour

6.000

MT

6.750

Providing and laying surface dressing as wearing course


consisting of a layer of bitumen emulsion laid on the
prepared surface, followed by a cover of crushed stone
chippings of specified size and rolling with 80-100 kN roller
including cleaning the road surface as per Technical
Specification Clause 507 MORD.
A By Manual Means
Case I: Nominal aggregate size 13.2 mm
Unit = sqm
Taking output = 900 sqm
a) Labour
Mate
Bitumen Emulsion Sprayer
Mazdoor (Unskilled)
b) Machinery
Emulsion sprayer, capacity 1000 litre fitted with spray set
Three wheel 80-100 kN static roller
Add: 0.5 per cent of (a) Labour for sundries
c) Material
Bitumen Emulsion (RS-1) @ 1.50 kg per sqm
Crushed stone chipping, 13.2 mm nominal size @ 0.010 cum
per sqm
d&e) Overheads & Contractors Profit
Cost of 900 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/900

MT

6.750

cum

36.000

day

day

1.000

day

60.360

hour

2.250

hour
L.S.

2.250

1.350

cum

9.000

373

RBR-BASC
Index-code

S. No
1

Description
2

Case II: Nominal chipping size 9.5 mm


Unit = sqm
Taking output = 1000 sqm
a) Labour
Mate
Bitumen Sprayer
Mazdoor (Unskilled)
b) Machinery
Emulsion sprayer, capacity 1000 litre fitted with spray set

Three wheel 80-100 kN static roller


c) Material
Bitumen Emulsion (RS-1) @ 1.40 kg per sqm

day
day
day

1.000
60.360

hour
hour

2.000
2.000

1.400

cum

8.000

day
day
day

9.000
2.440

hour
hour
Hydraulic self propelled chip spreader @ 1500 sqm / hour
hour
Tipper 5.5 cum - 10 t capacity for carriage of stone chips hour

6.000
6.000
6.000
6.000

Crushed stone chipping, 9.5 mm nominal size @ 0.008 cum/ sqm

Unit Quantity

d&e) Overheads & Contractors Profit


Cost of 1000 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/1000
By Mechanical Means
Case I: Nominal chipping size 13.2 mm
Unit = sqm
Taking output = 7500 sqm
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Skilled)
b) Machinery
Hydraulic broom @ 1250 sqm per hour
Air compressor 210 cfm

from stockpile on road side to chip spreader


Front end loader 1 cum bucket capacity
Bitumen Emulsion pressure distributor
Three wheel 80-100 kN static roller
c) Material
Bitumen Emulsion (RS-1) @ 1.50 kg per sqm
Crushed stone chipping, 13.2 mm nominal size @ 0.010 cum/sqm

d&e) Overheads & Contractors Profit


Cost of 7500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/7500
Case II: Nominal chipping size 9.5 mm
Unit = sqm
Taking output = 7500 sqm
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Skilled)
b) Machinery
Hydraulic broom @ 1250 sqm per hour
Air compressor 210 cfm

hour
hour
hour

6.000
6.000
18.750

11.250

cum

75.000

day

day

9.000

day

2.440

hour

6.000

hour

6.000

hour
Tipper 5.5 cum - 10 t capacity for carriage of stone chips hour

6.000
6.000

Hydraulic self propelled chip spreader @1500 sqm per hour

from stockpile on road side to chip spreader


Front end loader 1 cum bucket capacity
Bitumen Emulsion pressure distributor
Three wheel 80-100 kN static roller
c) Material
Bitumen Emulsion (RS-1) @ 1.40 kg per sqm
Crushed stone chipping, 9.5 mm nominal size @ 0.008 cum/sqm

hour

Rate
Rs.

Amount
Rs.

Remarks

6.000

hour

6.000

hour

15.000

10.500

cum

60.000

d&e) Overheads & Contractors Profit


Cost of 7500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/7500
Note : Where the proposed aggregate fails to pass the stripping value test, an approved adhesion agent
may be added to the binder as per Clause 507.24. Alternatively, chips may be pre-coated as per Clause
507.25.

374

RBR-BASC
Index-code

S. No
1

RBR-BASC-13

13

14

RBR-BASC-14

Description

Unit Quantity
3

Rate
Rs.

Amount
Rs.

Remarks

Pre-coating Chips
Pre-coating of chips with 1 per cent of paving bitumen by
weight of chips in a suitable mixer duly heated to 160 degree
C as per Technical Specification Clause 507.2.5 MORD
Unit = cum
Taking output = 30 cum
(I) Bitumen (S-90)
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Bitumen boiler oil fired, capacity 1000 litre tire
Mixall 6-10 t capacity
c) Material
Bitumen @1 per cent by weight of chips (30x1.6)/100
d&e) Overheads & Contractors Profit
Cost of 30 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/30
(II) Bitumen (S-65)
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Bitumen boiler oil fired, capacity 1000 litre tire
Mixall 6-10 t capacity
c) Material
Bitumen @1 per cent by weight of chips (30x1.6)/100
d&e) Overheads & Contractors Profit
Cost of 30 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/30
i 20mm thick Open-Graded Premix Carpet using
Bituminous (penetration grade/modified bitumen) Binder

day

day

15.600

hour

6.000

hour

6.000

0.480

day

day

15.600

hour

6.000

hour

6.000

0.480

Providing, laying and rolling of open-graded premix carpet of 20 mm


thickness composed of 13.2 mm to 5.6 mm aggregates either using
penetration grade bitumen or emulsion to required line, grade and
level to serve as wearing course on a previously prepared base,
including mixing a suitable plant, laying and rolling with a three wheel
0-100 kN static roller capacity, finished to required level and grades to
be followed by seal coat of either type A or Type B or Type C as per
Technical Specification Clause 508 MORD.

(I)

Case - I By Manual Means


Bitumen (S-90)
Unit = sqm
Taking output = 500 sqm (10 cum)
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Semi-Skilled)
Labour & Hire charges
b) Machinery
Mixall 6/10 t capacity
Bitumen boiler oil fired 1000 litre capacity fitted with spray set

day

day

21.000

day

7.080

sqm
hour

4.000

hour
hour

4.000
2.000

Three wheel 80-100 kN static roller


c) Material
t
Bitumen (S-90) @ 14.60 kg per 10 sqm
Crushed stone chipping, 13.2 mm to 5.6 mm @ 0.27 cum per cum
10 sqm
d&e) Overheads & Contractors Profit
Cost of 500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/500

0.730
13.500

375

RBR-BASC
Index-code

S. No

Description

Unit Quantity
3

Rate
Rs.

Amount
Rs.

Remarks

(II) Bitumen (S-65)

Unit = sqm
Taking output = 500 sqm (10 cum)
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Semi-Skilled)
b) Machinery
Mixall 6/10 t capacity
Bitumen boiler oil fired 1000 litre capacity fitted with spray set

day

day

21.000

day

7.080

hour

4.000

hour
hour

4.000
2.000

Three wheel 80-100 kN static roller


c) Material
t
Bitumen (S-65) @ 14.60 kg per 10 sqm
Crushed stone chipping, 13.2 mm to 5.6 mm @ 0.27 cum per cum
10 sqm
d&e) Overheads & Contractors Profit
Cost of 500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/500
(III) Polymer Modified Bitumen
Unit = sqm
Taking output = 500 sqm (10 cum)
a) Labour
day
Mate
day
Mazdoor (Unskilled)
day
Mazdoor (Semi-Skilled)
b) Machinery
hour
Mixall 6/10 t capacity
Bitumen boiler oil fired 1000 litre capacity fitted with spray set

hour
hour

Three wheel 80-100 kN static roller


c) Material
t
Polymer Modified Bitumen @ 14.60 kg per 10 sqm
Crushed stone chipping, 13.2 mm to 5.6 mm @ 0.27 cum per cum
10 sqm
d&e) Overheads & Contractors Profit
Cost of 500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/500
(IV) Crumb Rubber Modified Bitumen
Unit = sqm
Taking output = 500 sqm (10 cum)
a) Labour
day
Mate
day
Mazdoor (Unskilled)
day
Mazdoor (Semi-Skilled)
b) Machinery
hour
Mixall 6/10 t capacity
Bitumen boiler oil fired 1000 litre capacity fitted with spray set

Three wheel 80-100 kN static roller


c) Material
Crumb Rubber Modified Bitumen @ 14.60 kg per 10 sqm

hour
hour
t

Crushed stone chipping, 13.2 mm to 5.6 mm @ 0.27 cum per cum


10 sqm
d&e) Overheads & Contractors Profit
Cost of 500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/500
(V) Natural Rubber Modified Bitumen
Unit = sqm
Taking output = 500 sqm (10 cum)
a) Labour
day
Mate
day
Mazdoor (Unskilled)
day
Mazdoor (Semi-Skilled)

0.730
13.500

21.000
7.080
4.000
4.000
2.000
0.730
13.500

21.000
7.080
4.000
4.000
2.000
0.730
13.500

21.000
7.080

376

RBR-BASC
Index-code

S. No

Description

b) Machinery
Mixall 6/10 t capacity
Bitumen boiler oil fired 1000 litre capacity fitted with spray set

Three wheel 80-100 kN static roller


c) Material
Natural Rubber Modified Bitumen @ 14.60 kg per 10 sqm

Unit Quantity
3

hour

4.000

hour
hour

4.000
2.000

Crushed stone chipping, 13.2 mm to 5.6 mm @ 0.27 cum per cum


10 sqm
d&e) Overheads & Contractors Profit
Cost of 500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/500
Case - II By Mechanical Means
(I) Bitumen (S-90)
Unit = sqm
Taking output = 4000 sqm (80 cum)
a) Labour
day
Mate
day
Mazdoor (Unskilled)
day
Mazdoor (Skilled)
b) Machinery
hour
HMP 30/40 t per hour
hour
Electric generator set 125 KVA
hour
Front end loader 1 cum bucket capacity
hour
Tipper 5.5 cum - 10 t/ 5-6t capacity
hour
Paver finisher
hour
Three wheel 80-100 kN static roller
c) Material
t
Bitumen (S-90) @ 14.60 kg per 10 sqm
Crushed stone chipping, 13.2 mm to 5.6 mm @ 0.27 cum per cum
10 sqm
d&e) Overheads & Contractors Profit
Cost of 4000 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/4000
(II) Bitumen (S-65)
Unit = sqm
Taking output = 4000 sqm (80 cum)
a) Labour
day
Mate
day
Mazdoor (Unskilled)
day
Mazdoor (Skilled)
b) Machinery
hour
HMP 30/40 t per hour
hour
Electric generator set 125 KVA
hour
Front end loader 1 cum bucket capacity
hour
Tipper 5.5 cum - 10 t capacity
hour
Paver finisher
hour
Three wheel 80-100 kN static roller
c) Material
t
Bitumen (S-65) @ 14.60 kg per 10 sqm
Crushed stone chipping, 13.2 mm to 5.6 mm @ 0.27 cum per cum
10 sqm
d&e) Overheads & Contractors Profit
Cost of 4000 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/4000

Rate
Rs.

Amount
Rs.

Remarks

0.730
13.500

10.000
3.520
6.000
6.000
6.000
3.640
6.000
16.000
5.840
108.000

10.000
3.520
6.000
6.000
6.000
3.640
6.000
16.000
5.840
108.000

377

RBR-BASC
Index-code

S. No

Description

Unit Quantity
3

Rate
Rs.

Amount
Rs.

Remarks

(III) Polymer Modified Bitumen

Unit = sqm
Taking output = 4000 sqm (80 cum)
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Skilled)
b) Machinery
HMP 30/40 t per hour
Electric generator set 125 KVA
Front end loader 1 cum bucket capacity
Tipper 5.5 cum - 10 t capacity
Paver finisher
Three wheel 80-100 kN static roller
c) Material
Polymer Modified Bitumen @ 14.60 kg per 10 sqm

5.840

Crushed stone chipping, 13.2 mm to 5.6 mm @ 0.27 cum/ 10 sqm

cum

108.000

d&e) Overheads & Contractors Profit


Cost of 4000 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/4000
(IV) Crumb Rubber Modified Bitumen
Unit = sqm
Taking output = 4000 sqm (80 cum)
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Skilled)
b) Machinery
HMP 30/40 t per hour
Electric generator set 125 KVA
Front end loader 1 cum bucket capacity
Tipper 5.5 cum - 10 t / 5-6 t capacity
Paver finisher
Three wheel 80-100 kN static roller
c) Material
Crumb Rubber Modified Bitumen @ 14.60 kg per 10 sqm
Crushed stone chipping, 13.2 mm to 5.6 mm @ 0.27 cum/ 10 sqm

d&e) Overheads & Contractors Profit


Cost of 4000 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/4000
(V) Natural Rubber Modified Bitumen
Unit = sqm
Taking output = 4000 sqm (80 cum)
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Skilled)
b) Machinery
HMP 30/40 t per hour
Electric generator set 125 KVA
Front end loader 1 cum bucket capacity
Tipper 5.5 cum - 10 t capacity
Paver finisher
Three wheel 80-100 kN static roller
c) Material
Natural Rubber Modified Bitumen @ 14.60 kg per 10 sqm
Crushed stone chipping, 13.2 mm to 5.6 mm @ 0.27 cum/ 10 sqm

day

day

10.000

day

3.520

hour

6.000

hour

6.000

hour

6.000

hour

3.640

hour

6.000

hour

16.000

day

day

10.000

day

3.520

hour

6.000

hour

6.000

hour

6.000

hour

3.640

hour

6.000

hour

16.000

5.840

cum

108.000

day

day

10.000

day

3.520

hour

6.000

hour

6.000

hour

6.000

hour

3.640

hour

6.000

hour

16.000

5.840

cum

108.000

d&e) Overheads & Contractors Profit


Cost of 4000 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/4000

378

RBR-BASC
Index-code

S. No
1

Description
2

ii

20 mm thick Open Graded Premix Carpet using Bitumen


Emulsion as per Technical Specification Clause 508.2
MORTH
Unit = sqm
Taking output = 900 sqm (24.3 cum)
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Skilled)
b) Machinery
Concrete mixer 0.4/0.28 cum capacity
Three wheel 80-100 kN static roller
c) Material
Bitumen emulsion (RS-1) @ 21.50 kg per 10 sqm
Crushed stone chipping, 13.2 mm to 5.6 mm @ 0.27 cum/ 10 sqm

RBR-BASC-15

Unit Quantity
3

day

day

18.000

day

2.800

hour

6.000

hour

3.600

1.940

cum

24.300

Rate
Rs.

Amount
Rs.

Remarks

d&e) Overheads & Contractors Profit


Cost of 900 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/900
Open - Graded Premix Surfacing
Providing, laying and rolling of open - graded premix
surfacing of 20 mm thickness composed of 13.2 mm to 5.6
mm aggregates either using penetration grade bitumen or cutback or emulsion to required line, grade and level to serve as
wearing course on a previously prepared base, including
mixing in a suitable plant, laying and rolling with a smooth
wheeled roller 8-10 tonne capacity, finished to required level
and grades as per Tech. Specification No. 511 MORTH.

15

Unit = sqm
Taking output = 10250 sqm (205 cum)
Case - I: Mechanical method using Penetration grade
Bitumen and HMP of appropriate capacity not less than
75 tonnes/hour .
a) Labour
day
Mate
Mazdoor (Unskilled) working with HMP, road sweeper, paver and day
roller
day
Skilled mazdoor for checking line & levels

b) Machinery
hour
i) Batch type HMP 75 tonne per hour
hour
ii) Electric Generator Set 250 KVA
hour
iii) Front end loader 1 cum bucket capacity
t.km
iv) Tipper 10 tonne capacity
Add 10 per cent of cost of carriage to cover cost of loading
and unloading
hour
v) Paver finisher hydrostatic with sensor attachment
hour
iv) Smooth wheeled/tandom roller 8-10 tonnes weight
c) Material
Bitumen@ 14.60 kg per 10 sqm
Crushed stone chipping, 13.2 mm to 5.6 mm @ 0.27 cum/ 10 sqm

16.000
5.840
6.000
6.000
6.000
450 x L

6.000
6.000

14.970

cum

276.750

d&e) Overheads & Contractors Profit


Cost for 10250 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/10250
Note : If a premix sand seal coat of 'B' type is proposed, the same is required to be provided over the
open graded premix carpet immediately on the same day. As the same HMP and other machines will be
used for laying of premix sand seal coat, out of 6 effective working hours, 4.00 hours may be utilised for
laying of premix carpet and balance 2.00 hours for the seal coat. The rate for the premix sand seal coat
under clause 513 (case II) has been worked out accordingly by utilising the HMP for 2.00 hours for the
purpose of seal coat. In case type 'A' seal coat is proposed, HMP can be worked for six hours for the
premix carpet as type 'A' seal coat does not require the use of HMP.

379

RBR-BASC
Index-code

S. No
1

Description
2

ii

Unit Quantity
3

Case - II: Open-Graded Premix Surfacing using cationic


Bitumen Emulsion
Unit = sqm
Taking output = 900 sqm (24.3 cum)
a) Labour
day
Mate
day
Mazdoor (Unskilled)
day
Mazdoor skilled
b) Machinery
hour
Concrete mixer 0.4/0.28 cum capacity
hour
Smooth wheeled steel roller 8-10 tonne
c) Material
t
Cationic Bitumen Emulsion @ 21.50 kg per 10 sqm

18.000

Crushed stone chipping, 13.2 mm to 5.6 mm @ 0.27 cum/ 10 sqm

24.300

cum

Rate
Rs.

Amount
Rs.

Remarks

2.800
6.000
6.000
1.940

d&e) Overheads & Contractors Profit


Cost for 900 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/900

RBR-BASC-16

16

Mix Seal Surfacing


Providing, laying and rolling of close-graded premix surfacing
material of 20 mm thickness composed of 11.2 mm to 0.9
mm (Type-A) or 13.2 mm to 0.9 mm (Type-B) aggregates
using penetration grade bitumen to required line, grade and
level to serve as wearing course on a previously prepared
base, including mixing in a suitable plant, laying and rolling
with a three wheel 8-10 kN static roller and finishing to
required level and grades as per Technical Specification
Clause 509 MORD
By Manual Means
Type A
(I) Bitumen (S-90)
Unit = sqm
Taking output = 500 sqm
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Skilled)
b) Machinery
Mixall 6-10 t capacity
i

Oil fired bitumen boiler 1000 litre capacity fitted with spray set

day

day

21.000

day

8.400

hour

6.000

hour
hour

6.000
6.000

Three wheel 80-100 kN static roller


c) Material
t
Bitumen (S-90) @ 22 kg per 10 sqm
Stone crushed aggregates 11.2 mm to 0.09 mm @ 0.27 cum cum
per 10 sqm
d&e) Overheads & Contractors Profit
Cost of 500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/500
(II) Bitumen (S-65)
Unit = sqm
Taking output = 500 sqm
a) Labour
day
Mate
day
Mazdoor (Unskilled)
day
Mazdoor (Skilled)
b) Machinery
hour
Mixall 6-10 t capacity
Oil fired bitumen boiler 1000 litre capacity fitted with spray set

Three wheel 80-100 kN static roller

hour
hour

1.100
13.500

21.000
8.400
6.000
6.000
6.000

380

RBR-BASC
Index-code

S. No

Description

Unit Quantity
3

c) Material
t
Bitumen (S-65) @ 22 kg per 10 sqm
Stone crushed aggregates 11.2 mm to 0.09 mm @ 0.27 cum cum
per 10 sqm
d&e) Overheads & Contractors Profit
Cost of 500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/500
(III) Polymer Modified Bitumen
Unit = sqm
Taking output = 500 sqm
a) Labour
day
Mate
day
Mazdoor (Unskilled)
day
Mazdoor (Skilled)
b) Machinery
hour
Mixall 6-10 t capacity
Oil fired bitumen boiler 1000 litre capacity fitted with spray set

hour
hour

Three wheel 80-100 kN static roller


c) Material
t
Polymer Modified Bitumen @ 22 kg per 10 sqm
Stone crushed aggregates 11.2 mm to 0.09 mm @ 0.27 cum cum
per 10 sqm
d&e) Overheads & Contractors Profit
Cost of 500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/500
(IV) Crumb Rubber Modified Bitumen
Unit = sqm
Taking output = 500 sqm
a) Labour
day
Mate
day
Mazdoor (Unskilled)
day
Mazdoor (Skilled)
b) Machinery
hour
Mixall 6-10 t capacity
Oil fired bitumen boiler 1000 litre capacity fitted with spray set

hour
hour

Three wheel 80-100 kN static roller


c) Material
t
Crumb Rubber Modified Bitumen @ 22 kg per 10 sqm
Stone crushed aggregates 11.2 mm to 0.09 mm @ 0.27 cum cum
per 10 sqm
d&e) Overheads & Contractors Profit
Cost of 500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/500
(V) Natural Rubber Modified Bitumen
Unit = sqm
Taking output = 500 sqm
a) Labour
day
Mate
day
Mazdoor (Unskilled)
day
Mazdoor (Skilled)
b) Machinery
hour
Mixall 6-10 t capacity
Oil fired bitumen boiler 1000 lt capacity fitted with spray set

hour
hour

Three wheel 80-100 kN static roller


c) Material
t
Natural Rubber Modified Bitumen @ 22 kg per 10 sqm
Stone crushed aggregates 11.2 mm to 0.09 mm @ 0.27 cum cum
per 10 sqm
d&e) Overheads & Contractors Profit
Cost of 500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/500

Rate
Rs.

Amount
Rs.

Remarks

1.100
13.500

21.000
8.400
6.000
6.000
6.000
1.100
13.500

21.000
8.400
6.000
6.000
6.000
1.100
13.500

21.000
8.400
6.000
6.000
6.000
1.100
13.500

381

RBR-BASC
Index-code

S. No

Description

Type B
(I) Bitumen (S-90)
Unit = sqm
Taking output = 500 sqm
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Skilled)
b) Machinery
Mixall 6-10 t capacity

Unit Quantity
3

day

day

21.000

day

8.400

hour

6.000

hour

6.000

hour
Three wheel 80-100 kN static roller
c) Material
t
Bitumen (S-90) @ 19 kg per 10 sqm
Stone crushed aggregates 13.2 mm to 0.09 mm @ 0.27cum cum
per 10 sqm
d&e) Overheads & Contractors Profit
Cost of 500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/500
(II) Bitumen (S-65)

6.000

Oil fired bitumen boiler 1000 lt capacity fitted with spray set

Unit = sqm
Taking output = 500 sqm
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Skilled)
b) Machinery
Mixall 6-10 t capacity
Oil fired bitumen boiler 1000 lt capacity fitted with spray set

d&e) Overheads & Contractors Profit


Cost of 500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/500
(III) Polymer Modified Bitumen
Unit = sqm
Taking output = 500 sqm
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Skilled)
b) Machinery
Mixall 6-10 t capacity

Remarks

0.950

day

21.000

day

8.400

hour

6.000

hour
hour

6.000
6.000
0.950
13.500

day

day

21.000

day

8.400

hour

6.000

hour

6.000

hour
Three wheel 80-100 kN static roller
c) Material
t
Polymer Modified Bitumen @ 19 kg per 10 sqm
Stone crushed aggregates 13.2 mm to 0.09 mm @ 0.27cum cum
per 10 sqm
d&e) Overheads & Contractors Profit
Cost of 500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/500

6.000

Oil fired bitumen boiler 1000 lt capacity fitted with spray set

Amount
Rs.

13.500

day

Three wheel 80-100 kN static roller


c) Material
t
Bitumen (S-65) @ 19 kg per 10 sqm
Stone crushed aggregates 13.2 mm to 0.09 mm @ 0.27cum cum
per 10 sqm

Rate
Rs.

0.950
13.500

382

RBR-BASC
Index-code

S. No

Description

1
2
(IV) Crumb Rubber Modified Bitumen

Unit = sqm
Taking output = 500 sqm
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Skilled)
b) Machinery
Mixall 6-10 t capacity
Oil fired bitumen boiler 1000 lt capacity fitted with spray set

Three wheel 80-100 kN static roller


c) Material
Crumb Rubber Modified Bitumen @ 19 kg per 10 sqm
Stone crushed aggregates 13.2 mm to 0.09 mm @ 0.27cum
per 10 sqm
d&e) Overheads & Contractors Profit
Cost of 500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/500
(V) Natural Rubber Modified Bitumen
Unit = sqm
Taking output = 500 sqm
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Skilled)
b) Machinery
Mixall 6-10 t capacity

Unit Quantity
3

day

day

21.000

day

8.400

hour

6.000

hour
hour

6.000
6.000

0.950

cum

13.500

day

day

21.000

day

8.400

hour

6.000

Oil fired bitumen boiler 1000 lt capacity fitted with spray set

hour

6.000

Three wheel 80-100 kN static roller


c) Material

hour

6.000

Natural Rubber Modified Bitumen @ 19 kg per 10 sqm

Stone crushed aggregates 13.2 mm to 0.09 mm @ 0.27cum


per 10 sqm
d&e) Overheads & Contractors Profit
Cost of 500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/500
By Mechanical Means
Type A
(I) Bitumen (S-90)
Unit = sqm
Taking output = 4000 sqm (80 cum)
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Skilled)
b) Machinery
HMP of appropriate capacity
Electric generator set 125 KVA
Front end loader 1 cum bucket capacity
Tipper 5.5 cum - 10 t capacity
Paver finisher
Three wheel 80-100 kN static roller
c) Material
Bitumen (S-90) @ 22 kg per 10 sqm
Stone crushed aggregates 11.2 mm to 0.09 mm @ 0.27 cum
per 10 sqm
d&e) Overheads & Contractors Profit
Cost of 4000 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/4000

0.950

cum

13.500

day

day

10.000

day

3.520

hour

6.000

hour

6.000

hour

6.000

hour

3.600

hour

6.000

hour

18.000

8.800

cum

108.000

Rate
Rs.

Amount
Rs.

Remarks

383

RBR-BASC
Index-code

S. No

Description

Unit Quantity
3

Rate
Rs.

Amount
Rs.

Remarks

(II) Bitumen (S-65)

Unit = sqm
Taking output = 4000 sqm (80 cum)
a) Labour
day
Mate
day
Mazdoor (Unskilled)
day
Mazdoor (Skilled)
b) Machinery
hour
HMP of appropriate capacity
hour
Electric generator set 125 KVA
hour
Front end loader 1 cum bucket capacity
hour
Tipper 5.5 cum - 10 t capacity
hour
Paver finisher
hour
Three wheel 80-100 kN static roller
c) Material
t
Bitumen (S-65) @ 22 kg per 10 sqm
Stone crushed aggregates 11.2 mm to 0.09 mm @ 0.27 cum cum
per 10 sqm
d&e) Overheads & Contractors Profit
Cost of 4000 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/4000
(III) Polymer Modified Bitumen
Unit = sqm
Taking output = 4000 sqm (80 cum)
a) Labour
day
Mate
day
Mazdoor (Unskilled)
day
Mazdoor (Skilled)
b) Machinery
hour
HMP of appropriate capacity
hour
Electric generator set 125 KVA
hour
Front end loader 1 cum bucket capacity
hour
Tipper 5.5 cum - 10 t capacity
hour
Paver finisher
hour
Three wheel 80-100 kN static roller
c) Material
t
Polymer Modified Bitumen @ 22 kg per 10 sqm
Stone crushed aggregates 11.2 mm to 0.09 mm @ 0.27 cum cum
per 10 sqm
d&e) Overheads & Contractors Profit
Cost of 4000 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/4000
(IV) Crumb Rubber Modified Bitumen
Unit = sqm
Taking output = 4000 sqm (80 cum)
a) Labour
day
Mate
day
Mazdoor (Unskilled)
day
Mazdoor (Skilled)
b) Machinery
hour
HMP of appropriate capacity
hour
Electric generator set 125 KVA
hour
Front end loader 1 cum bucket capacity
hour
Tipper 5.5 cum - 10 t capacity
hour
Paver finisher
hour
Three wheel 80-100 kN static roller
c) Material
t
Crumb Rubber Modified Bitumen @ 22 kg per 10 sqm
Stone crushed aggregates 11.2 mm to 0.09 mm @ 0.27 cum cum
per 10 sqm
d&e) Overheads & Contractors Profit
Cost of 4000 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/4000

10.000
3.520
6.000
6.000
6.000
3.600
6.000
18.000
8.800
108.000

10.000
3.520
6.000
6.000
6.000
3.600
6.000
18.000
8.800
108.000

10.000
3.520
6.000
6.000
6.000
3.600
6.000
18.000
8.800
108.000

384

RBR-BASC
Index-code

S. No
1

Description

2
(V) Natural Rubber Modified Bitumen

Unit = sqm
Taking output = 4000 sqm (80 cum)
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Skilled)
b) Machinery
HMP of appropriate capacity
Electric generator set 125 KVA
Front end loader 1 cum bucket capacity
Tipper 5.5 cum - 10 t capacity
Paver finisher
Three wheel 80-100 kN static roller
c) Material
Natural Rubber Modified Bitumen @ 22 kg per 10 sqm
Stone crushed aggregates 11.2 mm to 0.09 mm @ 0.27 cum
per 10 sqm
d&e) Overheads & Contractors Profit
Cost of 4000 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/4000
Type B
(I) Bitumen (S-90)
Unit = sqm
Taking output = 4000 sqm (80 cum)
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Skilled)
b) Machinery
HMP of appropriate capacity
Electric generator set 125 KVA
Front end loader 1 cum bucket capacity
Tipper 5.5 cum - 10 t / 5-6 t capacity
Add 10 per cent of cost of carriage to cover cost of loading
and unloading
Paver finisher
Three wheel 80-100 kN static roller
c) Material
Bitumen (S-90) @ 19 kg per 10 sqm
Stone crushed aggregates 13.2 mm to 0.09 mm @ 0.27 cum
per 10 sqm
d&e) Overheads & Contractors Profit
Cost of 4000 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/4000
(II) Bitumen (S-65)
Unit = sqm
Taking output = 4000 sqm (80 cum)
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Skilled)
b) Machinery
HMP of appropriate capacity
Electric generator set 125 KVA
Tipper 5.5 cum - 10 t capacity
Paver finisher
Three wheel 80-100 kN static roller

Unit Quantity
3

day

day

10.000

day

3.520

hour

6.000

hour

6.000

hour

6.000

hour

3.600

hour

6.000

hour

18.000

8.800

cum

108.000

day

day

10.000

day

3.520

hour

6.000

hour

6.000

hour

6.000

hour

3.600

hour

6.000

hour

18.000

7.600

cum

108.000

day

day

10.000

day

3.520

hour

6.000

hour

6.000

hour

3.600

hour

6.000

hour

18.000

Rate
Rs.

Amount
Rs.

Remarks

385

RBR-BASC
Index-code

S. No

Description

Unit Quantity
3

c) Material
t
Bitumen (S-65) @ 19 kg per 10 sqm
Stone crushed aggregates 13.2 mm to 0.09 mm @ 0.27 cum cum
per 10 sqm
d&e) Overheads & Contractors Profit
Cost of 4000 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/4000
(III) Polymer Modified Bitumen
Unit = sqm
Taking output = 4000 sqm (80 cum)
a) Labour
day
Mate
day
Mazdoor (Unskilled)
day
Mazdoor (Skilled)
b) Machinery
hour
HMP of appropriate capacity
hour
Electric generator set 125 KVA
hour
Tipper 5.5 cum - 10 t capacity
hour
Paver finisher
hour
Three wheel 80-100 kN static roller
c) Material
t
Polymer Modified Bitumen @ 19 kg per 10 sqm
Stone crushed aggregates 13.2 mm to 0.09 mm @ 0.27 cum cum
/10 sqm
d&e) Overheads & Contractors Profit
Cost of 4000 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/4000
(IV) Crumb Rubber Modified Bitumen
Unit = sqm
Taking output = 4000 sqm (80 cum)
a) Labour
day
Mate
day
Mazdoor (Unskilled)
day
Mazdoor (Skilled)
b) Machinery
hour
HMP of appropriate capacity
hour
Electric generator set 125 KVA
hour
Tipper 5.5 cum - 10 t capacity
hour
Paver finisher
hour
Three wheel 80-100 kN static roller
c) Material
t
Crumb Rubber Modified Bitumen @ 19 kg per 10 sqm
Stone crushed aggregates 13.2 mm to 0.09 mm @ 0.27 cum cum
/10 sqm
d&e) Overheads & Contractors Profit
Cost of 4000 sqm = a+b+c+d+e

Rate
Rs.

Amount
Rs.

Remarks

7.600
108.000

10.000
3.520
6.000
6.000
3.600
6.000
18.000
7.600
108.000

10.000
3.520
6.000
6.000
3.600
6.000
18.000
7.600
108.000

Rate per sqm = (a+b+c+d+e)/4000


(V) Natural Rubber Modified Bitumen

Unit = sqm
Taking output = 4000 sqm (80 cum)
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Skilled)
b) Machinery
HMP of appropriate capacity
Electric generator set 125 KVA
Tipper 5.5 cum - 10 t capacity
Paver finisher
Three wheel 80-100 kN static roller

day

day

10.000

day

3.520

hour

6.000

hour

6.000

hour

3.600

hour

6.000

hour

18.000

386

RBR-BASC
Index-code

S. No

Description

Unit Quantity
3

c) Material
t
Natural Rubber Modified Bitumen @ 19 kg per 10 sqm
Stone crushed aggregates 13.2 mm to 0.09 mm @ 0.27 cum cum
/10 sqm
d&e) Overheads & Contractors Profit
Cost of 4000 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/4000
ii

Rate
Rs.

Amount
Rs.

Remarks

7.600
108.000

Close Graded Premix Surfacing/Mixed Seal Surfacing


Case 1 : Mechanical means using HMP of appropriate capacity not
less than 75 tonnes/hour.
Providing, laying and rolling of close-graded premix surfacing material
of 20 mm thickness composed of 11.2 mm to 0.09 mm (Type-a) or
13.2 mm to 0.09 mm (Type-b) aggregates using penetration grade
bitumen to the required line, grade and level to serve as wearing
course on a previously prepared base, including mixing in a suitable
plant, laying and rolling with a Smooth wheeled roller 8-10 tonne
capacity, and finishing to required level and grade as per Tech.
Specification No 512 MORTH.

Type - A
Unit = sqm
Taking output = 10250 sqm (205 cum)
a) Labour
Mate

day

Mazdoor (Unskilled) working with HMP, road sweeper, paver and day
roller
day
Skilled mazdoor for checking line & levels

b) Machinery
i) HMP of appropriate capacity.
ii) Electric Generator Set 250 KVA
iii) Front end loader 1 cum bucket capacity
iv) Tipper 10 tonne capacity
Add 10 per cent of cost of carriage to cover cost of loading
and unloading
v) Paver finisher hydrostatic with sensor attachment
iv) Smooth wheeled8-10 tonnes weight
c) Material
Type - A
* Bitumen@ 22 kg per 10 sqm
Stone crushed aggregates 11.2 mm to 0.09 @ 0.27 cum per
10 sqm
d&e) Overheads & Contractors Profit
Cost for 10250 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/10250
Type - B
Unit = sqm
Taking output = 10250 sqm (205 cum)
a) Labour
Mate

5.840

hour

6.000

hour

6.000

hour

6.000

t.km

450 x L

hour

6.000

hour

6.000

22.500

cum

276.750

day

Mazdoor (Unskilled) working with HMP, road sweeper, paver and day
roller
day
Skilled mazdoor for checking line & levels

b)

16.000

16.000
5.840

Machinery

i) HMP of appropriate capacity. Not less than 75 t / hour

hour

hour
ii) Electric Generator Set 250 KVA
hour
iii) Front end loader 1 cum bucket capacity
tkm
iv) Tipper 10 tonne capacity
Add 10 per cent of cost of carriage to cover cost of loading
and unloading
hour
v) Paver finisher hydrostatic with sensor attachment
hour
iv) Smooth wheeled8-10 tonnes weight

6.000
6.000
6.000
450 x L

6.000
6.000

387

RBR-BASC
Index-code

RBR-BASC-17

S. No

Description

17

c) Material
Type - B
Bitumen @ 19 kg per 10 sqm
Stone crushed aggregates 13.2 mm to 0.09 mm @ 0.27 cum
per 10 sqm
d&e) Overheads & Contractors Profit
Cost for 10250 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/10250
Seal Coat
i Providing and laying seal coat sealing the voids in a
bituminous surface laid to the specified levels, grade and
cross fall using Type A, Type B and Type C as per Technical
Specification Clause 510 MORD. (using Three wheel 80100 kN static roller)
A By Manual Means
Case - I : Type A
(I) Bitumen (S-90)
Unit = sqm
Taking output = 1100 sqm
a) Labour
Mate
Bitumen Sprayer
Mazdoor (Unskilled)
Mazdoor (Semi-Skilled)
b) Machinery
Bitumen boiler oil fired, capacity 1000 litre fitted with spray
set
Three wheel 80-100 kN static roller
c) Material
Bitumen (S-90) @ 9.80 kg per 10 sqm
Crushed stone chipping of 6.7 mm size 100 per cent passing
11.2 mm sieve and retained on 2.36 mm sieve applied @
0.09 cum per 10 sqm
d&e) Overheads & Contractors Profit
Cost of 1100 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/1100
(II) Bitumen (S-65)
Unit = sqm
Taking output = 1100 sqm
a) Labour
Mate
Bitumen Sprayer
Mazdoor (Unskilled)
Mazdoor (Semi-Skilled)
b) Machinery
Bitumen boiler oil fired, capacity 1000 litre fitted with spray
set
Three wheel 80-100 kN static roller
c) Material
Bitumen (S-65) @ 9.80 kg per 10 sqm
Crushed stone chipping of 6.7 mm size 100 per cent passing
11.2 mm sieve and retained on 2.36 mm sieve applied @
0.09 cum per 10 sqm
d&e) Overheads & Contractors Profit
Cost of 1100 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/1100

Unit Quantity
3

19.480

cum

276.750

day

day

1.000

day

22.000

day

7.150

hour

2.200

hour

2.200

1.078

cum

9.900

day

day

1.000

day

22.000

day

7.150

hour

2.200

hour

2.200

1.078

cum

9.900

Rate
Rs.

Amount
Rs.

Remarks

388

RBR-BASC
Index-code

S. No

Description

Unit Quantity
3

Rate
Rs.

Amount
Rs.

Remarks

(III) Polymer Modified Bitumen

Unit = sqm
Taking output = 1100 sqm
a) Labour
Mate
Bitumen Sprayer
Mazdoor (Unskilled)
Mazdoor (Semi-Skilled)
b) Machinery
Bitumen boiler oil fired, capacity 1000 litre fitted with spray
set
Three wheel 80-100 kN static roller
c) Material
Polymer Modified Bitumen @ 9.80 kg per 10 sqm
Crushed stone chipping of 6.7 mm size 100 per cent passing
11.2 mm sieve and retained on 2.36 mm sieve applied @
0.09 cum per 10 sqm
d&e) Overheads & Contractors Profit
Cost of 1100 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/1100
(IV) Crumb Rubber Modified Bitumen
Unit = sqm
Taking output = 1100 sqm
a) Labour
Mate
Bitumen Sprayer
Mazdoor (Unskilled)
Mazdoor (Semi-Skilled)
b) Machinery
Bitumen boiler oil fired, capacity 1000 litre / 245 kg fitted with
spray set
Three wheel 80-100 kN static roller
c) Material
Crumb Rubber Modified Bitumen @ 9.80 kg per 10 sqm
Crushed stone chipping of 6.7 mm size 100 per cent passing
11.2 mm sieve and retained on 2.36 mm sieve applied @
0.09 cum per 10 sqm
d&e) Overheads & Contractors Profit
Cost of 1100 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/1100
(V) Natural Rubber Modified Bitumen
Unit = sqm
Taking output = 1100 sqm
a) Labour
Mate
Bitumen Sprayer
Mazdoor (Unskilled)
Mazdoor (Semi-Skilled)
b) Machinery
Bitumen boiler oil fired, capacity 1000 litre fitted with spray
set
Three wheel 80-100 kN static roller
c) Material
Natural Rubber Modified Bitumen @ 9.80 kg per 10 sqm
Crushed stone chipping of 6.7 mm size 100 per cent passing
11.2 mm sieve and retained on 2.36 mm sieve applied @
0.09 cum per 10 sqm
d&e) Overheads & Contractors Profit
Cost of 1100 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/1100

day

day

1.000

day

22.000

day

7.150

hour

2.200

hour

2.200

1.078

cum

9.900

day

day

1.000

day

22.000

day

7.150

hour

2.200

hour

2.200

t
cum

1.078
9.900

day

day

1.000

day

22.000

day

7.150

hour

2.200

hour

2.200

1.078

cum

9.900

389

RBR-BASC
Index-code

S. No

Description

Case - II : Type B (510 - MORD)


(I) Bitumen (S-90)
Unit = sqm
Taking output = 1250 sqm
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Semi-Skilled)
b) Machinery
Mixall 6/10 t capacity
Three wheel 80-100 kN static roller
Bitumen boiler oil fired 1000 litre capacity fitted with spray set

c) Material
Bitumen (S-90) @ 6.80 kg per 10 sqm

Unit Quantity
3

day

day

15.000

day

2.850

hour

2.500

hour

2.500

hour

2.500

0.850

Crushed sand or grit as passing 2.36 mm sieve and retained on 180 cum
micron sieve applied @ 0.06 cum per 10 sqm

d&e) Overheads & Contractors Profit


Cost of 1250 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/1250
(II) Bitumen (S-65)
Unit = sqm
Taking output = 1250 sqm
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Semi-Skilled)
b) Machinery
Mixall 6/10 t capacity
Three wheel 80-100 kN static roller
Bitumen boiler oil fired 1000 litre capacity fitted with spray set

c) Material
Bitumen (S-65) @ 6.80 kg per 10 sqm

Bitumen boiler oil fired 1000 litre capacity fitted with spray set

day

15.000

day

2.850

hour

2.500

hour

2.500

hour

2.500

0.850

Remarks

7.500

day

day

15.000

day

2.850

hour

2.500

hour

2.500

hour

2.500

c) Material
t
Polymer Modified Bitumen @ 6.80 kg per 10 sqm
Crushed sand or grit as passing 2.36 mm sieve and retained cum
on 180 micron sieve applied @ 0.06 cum/10 sqm

Amount
Rs.

7.500

day

Crushed sand or grit as passing 2.36 mm sieve and retained on 180 cum
micron sieve applied @ 0.06 cum/10 sqm

d&e) Overheads & Contractors Profit


Cost of 1250 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/1250
(III) Polymer Modified Bitumen
Unit = sqm
Taking output = 1250 sqm
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Semi-Skilled)
b) Machinery
Mixall 6/10 t capacity
Three wheel 80-100 kN static roller

Rate
Rs.

0.850
7.500

d&e) Overheads & Contractors Profit


Cost of 1250 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/1250

390

RBR-BASC
Index-code

S. No

Description

1
2
(IV) Crumb Rubber Modified Bitumen

Unit = sqm
Taking output = 1250 sqm
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Semi-Skilled)
b) Machinery
Mixall 6/10 t capacity
Three wheel 80-100 kN static roller
Bitumen boiler oil fired 1000 litre capacity fitted with spray set

c) Material
Crumb Rubber Modified Bitumen @ 6.80 kg per 10 sqm
Crushed sand or grit as passing 2.36 mm sieve and retained
on 180 micron sieve applied @ 0.06 cum /10 sqm
d&e) Overheads & Contractors Profit
Cost of 1250 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/1250
(V) Natural Rubber Modified Bitumen
Unit = sqm
Taking output = 1250 sqm
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Semi-Skilled)
b) Machinery
Mixall 6/10 t capacity
Three wheel 80-100 kN static roller
Bitumen boiler oil fired 1000 litre capacity fitted with spray set
c) Material
Natural Rubber Modified Bitumen @ 6.80 kg per 10 sqm
Crushed sand or grit as passing 2.36 mm sieve and retained
on 180 micron sieve applied @ 0.06 cum /10 sqm
d&e) Overheads & Contractors Profit
Cost of 1250 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/1250
Case - III : Type C (510 - MORD)
(I) Bitumen (S-90)
Unit = sqm
Taking output = 1100 sqm
a) Labour
Mate
Bitumen Sprayer
Mazdoor (Unskilled) for carrying of chips & spraying
Mazdoor (Semi-Skilled)
b) Machinery
Bitumen boiler oil fired 1000 litre capacity fitted with spray set

Unit Quantity
3

day

day

15.000

day

2.850

hour

2.500

hour

2.500

hour

2.500

0.850

cum

7.500

day

day

15.000

day

2.850

hour

2.500

hour

2.500

hour

2.500

0.850

cum

7.500

day

day

1.000

day

22.000

day

6.150

hour

2.200
2.200

hour
Three wheel 80-100 kN static roller
c) Material
t
Bitumen (S-90) @ 6.50 kg per 10 sqm
Crushed stone chipping of 6.7 mm size defined as 100% cum
passing 9.5 mm sieve and retained on 2.36 mm sieve
applied @ 0.09 cum.
d&e) Overheads & Contractors Profit
Cost of 1100 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/1100

Rate
Rs.

Amount
Rs.

Remarks

0.715
9.900

391

RBR-BASC
Index-code

S. No

Description

Unit Quantity
3

Rate
Rs.

Amount
Rs.

Remarks

(II) Bitumen (S-65)

Unit = sqm
Taking output = 1100 sqm
a) Labour
Mate
Bitumen Sprayer
Mazdoor (Unskilled)
Mazdoor (Semi-Skilled)
b) Machinery
Bitumen boiler oil fired 1000 litre capacity fitted with spray set

Three wheel 80-100 kN static roller


c) Material
Bitumen (S-65) @ 6.50 kg per 10 sqm

day

day

1.000

day

22.000

day

6.150

hour
hour

2.200
2.200

0.715

Crushed stone chipping of 6.7 mm size defined as 100% passing 9.5 cum
mm sieve and retained on 2.36 mm sieve applied @ 0.09 cum.

d&e) Overheads & Contractors Profit


Cost of 1100 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/1100
(III) Polymer Modified Bitumen
Unit = sqm
Taking output = 1100 sqm
a) Labour
Mate
Bitumen Sprayer
Mazdoor (Unskilled)
Mazdoor (Semi-Skilled)
b) Machinery
Bitumen boiler oil fired 1000 litre capacity fitted with spray set

day

day

1.000

day

22.000

day

6.150

hour

2.200
2.200

hour
Three wheel 80-100 kN static roller
c) Material
t
Polymer Modified Bitumen @ 6.50 kg per 10 sqm
Crushed stone chipping of 6.7 mm size defined as 100% cum
passing 9.5 mm sieve and retained on 2.36 mm sieve
applied @ 0.09 cum.
d&e) Overheads & Contractors Profit
Cost of 1100 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/1100
(IV) Crumb Rubber Modified Bitumen
Unit = sqm
Taking output = 1100 sqm
a) Labour
day
Mate
day
Bitumen Sprayer
day
Mazdoor (Unskilled)
day
Mazdoor (Semi-Skilled)
b) Machinery
Bitumen boiler oil fired 1000 litre capacity fitted with spray set

9.900

hour

hour
Three wheel 80-100 kN static roller
c) Material
t
Crumb Rubber Modified Bitumen @ 6.50 kg per 10 sqm
Crushed stone chipping of 6.7 mm size defined as 100% cum
passing 9.5 mm sieve and retained on 2.36 mm sieve
applied @ 0.09 cum.
d&e) Overheads & Contractors Profit
Cost of 1100 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/1100

0.715
9.900

1.000
22.000
6.150
2.200
2.200
0.715
9.900

392

RBR-BASC
Index-code

S. No
1

Description

2
(V) Natural Rubber Modified Bitumen

Unit = sqm
Taking output = 1100 sqm
a) Labour
Mate
Bitumen Sprayer
Mazdoor (Unskilled)
Mazdoor (Semi-Skilled)
b) Machinery
Bitumen boiler oil fired 1000 litre capacity fitted with spray set

Three wheel 80-100 kN static roller


c) Material
Natural Rubber Modified Bitumen @ 6.50 kg per 10 sqm

Unit Quantity
3

day

day

1.000

day

22.000

day

6.150

hour
hour

2.200
2.200

0.715

Crushed stone chipping of 6.7 mm size defined as 100% passing 9.5 cum
mm sieve and retained on 2.36 mm sieve applied @ 0.09 cum.

Rate
Rs.

Amount
Rs.

Remarks

9.900

d&e) Overheads & Contractors Profit


Cost of 1100 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/1100
Note : Since seal coat is provided immediately over the bituminous layers,
hydraulic broom for cleaning has not been catered.
B
(I)

By Mechanical Means
Case - I : Type A
Bitumen (S-90)
Unit = sqm
Taking output = 7500 sqm (67.5 cum)
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Hydraulic self propelled chips spreader
Tipper 5.5 cum capacity
Front end loader 1 cum bucket capacity
Bitumen pressure distributor
Three wheel 80-100 kN static roller
c) Material
Bitumen (S-90) @ 9.80 kg per 10 sqm

day

day

6.240

hour

6.000

hour

6.000

hour

6.000

hour

6.000

hour

15.000

Crushed stone chipping of 6.7 mm size 100 per cent passing 11.2 cum
mm sieve and retained on 2.36 mm sieve applied @ 0.09 cum/10
sqm

d&e) Overheads & Contractors Profit


Cost of 7500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/7500
(II) Bitumen (S-65)
Unit = sqm
Taking output = 7500 sqm (67.5 cum)
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Hydraulic self propelled chips spreader
Tipper 5.5 cum capacity
Front end loader 1 cum bucket capacity
Bitumen pressure distributor
Three wheel 80-100 kN static roller
c) Material
Bitumen (S-65) @ 9.80 kg per 10 sqm

7.350
67.500

day

day

6.240

hour

6.000

hour

6.000

hour

6.000

hour

6.000

hour

15.000

Crushed stone chipping of 6.7 mm size 100 per cent passing 11.2 cum
mm sieve and retained on 2.36 mm sieve applied @ 0.09 cum per 10
sqm

7.350
67.500

d&e) Overheads & Contractors Profit


Cost of 7500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/7500

393

RBR-BASC
Index-code

S. No

Description

Unit Quantity
3

Rate
Rs.

Amount
Rs.

Remarks

(III) Polymer Modified Bitumen

Unit = sqm
Taking output = 7500 sqm (67.5 cum)
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Hydraulic self propelled chips spreader
Tipper 5.5 cum capacity
Front end loader 1 cum bucket capacity
Bitumen pressure distributor
Three wheel 80-100 kN static roller
c) Material
Polymer Modified Bitumen @ 9.80 kg per 10 sqm

day

day

6.240

hour

6.000

hour

6.000

hour

6.000

hour

6.000

hour

15.000

Crushed stone chipping of 6.7 mm size 100 per cent passing 11.2 cum
mm sieve and retained on 2.36 mm sieve applied @ 0.09 cum per 10
sqm

d&e) Overheads & Contractors Profit


Cost of 7500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/7500
(IV) Crumb Rubber Modified Bitumen
Unit = sqm
Taking output = 7500 sqm (67.5 cum)
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Hydraulic self propelled chips spreader
Tipper 5.5 cum capacity
Front end loader 1 cum bucket capacity
Bitumen pressure distributor
Three wheel 80-100 kN static roller
c) Material
Crumb Rubber Modified Bitumen @ 9.80 kg per 10 sqm

7.350
67.500

day

day

6.240

hour

6.000

hour

6.000

hour

6.000

hour

6.000

hour

15.000

Crushed stone chipping of 6.7 mm size 100 per cent passing cum
11.2 mm sieve and retained on 2.36 mm sieve applied @
0.09 cum/10 sqm

7.350
67.500

d&e) Overheads & Contractors Profit


Cost of 7500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/7500
(V) Natural Rubber Modified Bitumen

Unit = sqm
Taking output = 7500 sqm (67.5 cum)
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Hydraulic self propelled chips spreader
Tipper 5.5 cum capacity
Front end loader 1 cum bucket capacity
Bitumen pressure distributor
Three wheel 80-100 kN static roller
c) Material

day

day

6.240

hour

6.000

hour

6.000

hour

6.000

hour

6.000

hour

15.000

Natural Rubber Modified Bitumen @ 9.80 kg per 10 sqm


t
Crushed stone chipping of 6.7 mm size 100 per cent passing 11.2 cum
mm sieve and retained on 2.36 mm sieve applied @ 0.09 cum per 10
sqm
d&e) Overheads & Contractors Profit

7.350
67.500

Cost of 7500 sqm = a+b+c+d+e


Rate per sqm = (a+b+c+d+e)/7500
Note : Since seal coat is provided immediately over the bituminous layers,
Hydraulic broom for cleaning has not been catered.

394

RBR-BASC
Index-code

S. No

Description

Unit Quantity
3

Rate
Rs.

Amount
Rs.

Remarks

Case - II : Type B
(I) Bitumen (S-90)
Unit = sqm
Taking output = 5000 sqm (30 cum)
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
HMP of 30/40 t per hour
Electric generator set 125 KVA
Front end loader 1 cum bucket capacity
Tipper 5.5 cum - 10 t capacity
Paver finisher
Three wheel 80-100 kN static roller
c) Material
Bitumen (S-90) @ 6.80 kg per 10 sqm

day

day

4.160

hour

2.000

hour

2.000

hour

2.000

hour

1.360

hour

2.000

hour

10.000

Crushed sand defined as passing 2.36 mm sieve and retained on 180 cum
micron sieve applied @ 0.06 cum per 10 sqm

d&e) Overheads & Contractors Profit


Cost of 5000 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/5000
(II) Bitumen (S-65)
Unit = sqm
Taking output = 5000 sqm (30 cum)
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
HMP of 30/40 t per hour
Electric generator set 125 KVA
Front end loader 1 cum bucket capacity
Tipper 5.5 cum - 10 t capacity
Paver finisher
Three wheel 80-100 kN static roller
c) Material
Bitumen (S-65) @ 6.80 kg per 10 sqm

day

day

4.160

hour

2.000

hour

2.000

hour

2.000

hour

1.360

hour

2.000

hour

10.000

Crushed sand defined as passing 2.36 mm sieve and retained on 180 cum
micron sieve applied @ 0.06 cum /10 sqm

d&e) Overheads & Contractors Profit


Cost of 5000 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/5000
(III) Polymer Modified Bitumen
Unit = sqm
Taking output = 5000 sqm (30 cum)
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
HMP of 30/40 t per hour
Electric generator set 125 KVA
Front end loader 1 cum bucket capacity
Tipper 5.5 cum - 10 t capacity
Paver finisher
Three wheel 80-100 kN static roller
c) Material
Polymer Modified Bitumen @ 6.80 kg per 10 sqm

3.400
30.000

3.400
30.000

day

day

4.160

hour

2.000

hour

2.000

hour

2.000

hour

1.360

hour

2.000

hour

10.000

Crushed sand defined as passing 2.36 mm sieve and retained on 180 cum
micron sieve applied @ 0.06 cum per 10 sqm

3.400
30.000

d&e) Overheads & Contractors Profit


Cost of 5000 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/5000

395

RBR-BASC
Index-code

S. No

Description

1
2
(IV) Crumb Rubber Modified Bitumen

Unit = sqm
Taking output = 5000 sqm (30 cum)
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
HMP of 30/40 t per hour
Electric generator set 125 KVA
Front end loader 1 cum bucket capacity
Tipper 5.5 cum - 10 t capacity
Paver finisher
Three wheel 80-100 kN static roller
c) Material
Crumb Rubber Modified Bitumen @ 6.80 kg per 10 sqm

Unit Quantity
3

day

day

4.160

hour

2.000

hour

2.000

hour

2.000

hour
hour

1.360
2.000

hour

10.000

Crushed sand defined as passing 2.36 mm sieve and retained on 180 cum
micron sieve applied @ 0.06 cum per 10 sqm

d&e) Overheads & Contractors Profit


Cost of 5000 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/5000
(V) Natural Rubber Modified Bitumen
Unit = sqm
Taking output = 5000 sqm (30 cum)
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
HMP of 30/40 t per hour
Electric generator set 125 KVA
Front end loader 1 cum bucket capacity
Tipper 5.5 cum - 10 t capacity
Paver finisher
Three wheel 80-100 kN static roller
c) Material
Natural Rubber Modified Bitumen @ 6.80 kg per 10 sqm

Remarks

3.400

day

4.160

hour

2.000

hour

2.000

hour

2.000

hour

1.360

hour

2.000

hour

10.000

Amount
Rs.

30.000

day

Crushed sand defined as passing 2.36 mm sieve and retained on 180 cum
micron sieve applied @ 0.06 cum per 10 sqm

Rate
Rs.

3.400
30.000

d&e) Overheads & Contractors Profit


Cost of 5000 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/5000
Note : Since seal coat is required to be provided over the premix carpet on
the same day, out of the 6 working hours of the HMP, 4.00 hours are
proposed to be utilised for the premix carpet and the balance 2.00 hours
have been considered for this case.

Case - III : Type C


(I) Bitumen (S-90)
Unit = sqm
Taking output = 7500 sqm (67.5 cum)
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Hydraulic self propelled chips spreader
Tipper 5.5 cum capacity
Front end loader 1 cum bucket capacity
Bitumen pressure distributor
Three wheel 80-100 kN static roller
c) Material
Bitumen (S-90) @ 6.50 kg per 10 sqm

day

day

5.200

hour
hour
hour
hour

6.000
6.000
6.000
6.000

hour

15.000

t
Crushed stone chipping of 6.7 mm size 100 per cent passing 9.5 mm cum
sieve and retained on 2.36 mm sieve applied @ 0.09 cum per 10 sqm

4.880
67.500

d&e) Overheads & Contractors Profit


Cost of 7500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/7500

396

RBR-BASC
Index-code

S. No

Description

Unit Quantity
3

Rate
Rs.

Amount
Rs.

Remarks

(II) Bitumen (S-65)

Unit = sqm
Taking output = 7500 sqm (67.5 cum)
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Hydraulic self propelled chips spreader
Tipper 5.5 cum capacity
Front end loader 1 cum bucket capacity
Bitumen pressure distributor
Three wheel 80-100 kN static roller
c) Material
Bitumen (S-65) @ 6.50 kg per 10 sqm
Crushed stone chipping of 6.7 mm size 100 per cent passing
9.5 mm sieve and retained on 2.36 mm sieve applied @ 0.09
cum per 10 sqm
d&e) Overheads & Contractors Profit
Cost of 7500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/7500
(III) Polymer Modified Bitumen
Unit = sqm
Taking output = 7500 sqm (67.5 cum)
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Hydraulic self propelled chips spreader
Tipper 5.5 cum capacity
Front end loader 1 cum bucket capacity
Bitumen pressure distributor
Three wheel 80-100 kN static roller
c) Material
Polymer Modified Bitumen @ 6.50 kg per 10 sqm
Crushed stone chipping of 6.7 mm size 100 per cent passing
9.5 mm sieve and retained on 2.36 mm sieve applied @ 0.09
cum per 10 sqm
d&e) Overheads & Contractors Profit
Cost of 7500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/7500
(IV) Crumb Rubber Modified Bitumen
Unit = sqm
Taking output = 7500 sqm (67.5 cum)
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Hydraulic self propelled chips spreader
Tipper 5.5 cum capacity
Front end loader 1 cum bucket capacity
Bitumen pressure distributor
Three wheel 80-100 kN static roller
c) Material
Crumb Rubber Modified Bitumen @ 6.50 kg per 10 sqm
Crushed stone chipping of 6.7 mm size 100 per cent passing
9.5 mm sieve and retained on 2.36 mm sieve applied @ 0.09
cum per 10 sqm
d&e) Overheads & Contractors Profit
Cost of 7500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/7500

day

day

5.200

hour

6.000

hour

6.000

hour

6.000

hour

6.000

hour

15.000

4.880

cum

67.500

day

day

5.200

hour

6.000

hour

6.000

hour

6.000

hour

6.000

hour

15.000

4.880

cum

67.500

day

day

5.200

hour

6.000

hour

6.000

hour

6.000

hour

6.000

hour

15.000

t
cum

4.880
67.500

397

RBR-BASC
Index-code

S. No
1

Description

2
(V) Natural Rubber Modified Bitumen

Unit = sqm
Taking output = 7500 sqm (67.5 cum)
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Hydraulic self propelled chips spreader
Tipper 5.5 cum capacity
Front end loader 1 cum bucket capacity
Bitumen pressure distributor
Three wheel 80-100 kN static roller
c) Material
Natural Rubber Modified Bitumen @ 6.50 kg per 10 sqm
Crushed stone chipping of 6.7 mm size 100 per cent passing
9.5 mm sieve and retained on 2.36 mm sieve applied @ 0.09
cum per 10 sqm
d&e) Overheads & Contractors Profit
Cost of 7500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/7500

Unit Quantity
3

day

day

5.200

hour

6.000

hour

6.000

hour

6.000

hour

6.000

hour

15.000

4.880

cum

67.500

Rate
Rs.

Amount
Rs.

Remarks

Note : Since seal coat is provided immediately over the bituminous layers,
Hydraulic broom for cleaning has not been catered.
ii

Providing and laying seal coat sealing the voids in a


bituminous surface laid to the specified levels, grade and
cross fall using Type A and B seal coats as per Tech.
specification No. 513 MORTH
Unit = sqm
Taking output = 10250 sqm (92.25 cum)
Case - I : Type A
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Hydraulic self propelled chip spreader
Tipper 5.5 cum capacity
Front end loader 1 cum bucket capacity
Bitumen pressure distributor @ 1750 sqm per hour
Smooth wheeled roller 8 -10 tonne weight
c) Material
Bitumen@ 9.80 kg per 10 sqm

day

day

6.240

hour

6.000

hour

6.000

hour

6.000

hour

6.000

hour

6.000

t
Crushed stone chipping of 6.7 mm size defined as 100 per cent cum
passing 11.2 mm sieve and retained on 2.36 mm sieve applied @
0.09 cum per 10 sqm

10.050
92.250

d&e) Overheads & Contractors Profit


Cost for 10250 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/10250
Note : Since seal coat is provided immediately over the bituminous layers,
mechanical broom for clearing has not been catered.

398

RBR-BASC
Index-code

S. No

Description

Unit Quantity
3

Rate
Rs.

Amount
Rs.

Remarks

Case - II : Type B
Providing and laying of premix sand seal coat with HMP of
appropriate capacity not less than 75 tonnes/ hours using crushed
stone chipping 6.7 mm size and penetration bitumen of suitable
grade.

Unit = sqm
Taking output = 7858 sqm (47.16 cum)
a)

Labour

Mate

day

Mazdoor (Unskilled)
b) Machinery
HMP of 75 tonnes/hour.

day

4.160

hour

2.000

Electric Generator Set 250 KVA

hour

2.000

Front end loader 1 cum bucket capacity


Tipper 10 tonne capacity

hour
t.km

2.000
104 x 'L'

Paver finisher hydrostatic with sensor attachment

hour

2.000

Smooth wheeled 8-10 tonnes capacity


c) Material
Bitumen@ 6.80 kg per 10 sqm

hour

2.000

Add 10 per cent of cost of carriage to cover cost of loading and


unloading

Crushed stone chipping of 6.7 mm size defined as passing 11.2 mm sieve


and retained on 2.36 mm sieve applied @ 0.06 cum per 10 sqm

5.340
47.160

d&e) Overheads & Contractors Profit


Cost for 7858 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/7858
Note : Since seal coat is required to be provided over the premix carpet on
the same day, out of the 6 working hours of the HMP, 4.00 hours are
proposed to be utilised for the premix carpet and the balance 2.00 hours for
the seal coat. Hence 2.00 hours have been considered for this case. This
may be linked to rate analysis worked out under clause 511.

RBR-BASC-18

18

5.1 Supply of Stone Aggregates for Pavement Courses

Supply of stone aggregates from approved sources


conforming to the physical requirement, specified in the
respective clauses, including royalties, fees, rents, collection,
transportation, stacking and testing and measured in cum as
per Clause 511.5 MORD / 514.5 MORTH

RBR-BASC-19

19

Note : Rates for stone crushing given in Chapter 1 may be


adopted. In case for supply of aggregates at site are not
available, nearest crusher site may be ascertained. Loading
and unloading charges and cost of carriage may be added to
these rates to arrive at the cost at site.
Mastic Asphalt
Providing and laying 25 mm thick mastic asphalt wearing
course with paving grade bitumen meeting the requirements
given in table 500-29, prepared by using mastic cooker and
laid to required level and slope after cleaning the surface,
including providing antiskid surface with bitumen precoated
finegrained hard stone chipping of 13.2 mm nominal size at
the rate of 0.005cum per 10 sqm and at an approximate
spacing of 10 cm center to center in both directions, pressed
into surface when the temperature of surfaces is not less
than 1000C, protruding 1 mm to 4 mm over mastic surface,
all complete as per clause 515 MORTH.
Unit = sqm
Taking output = 35.00 sqm (0.87 cum ) assuming a
density of 2.3 tonnes/cum.-2 tonnes
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor skilled

day

day

10.000

day

1.440

399

RBR-BASC
Index-code

S. No
1

Description
2

b) Machinery
Mechanical broom @ 1250 sqm per hour
Air compressor 250 cfm
Mastic cooker 1 tonne capacity
Bitumen boiler 1500 litres capacity
Tractor for towing and positioning of mastic cooker and
bitumen boiler
c) Material
Base mastic (without coarse aggregates) = 60 per cent
Coarse aggregate (6.3mm to 13.2 mm) = 40 per cent

Unit Quantity
3

hour

0.060

hour

0.060

hour

6.000

hour

6.000

hour

1.000

Proportion of material required for mastic asphalt with coarse


aggregates (based on mix design done by CRRI for a specific
case)
I) Bitumen 80 / 100 or 30/40 @ 10.2 per cent by weight of t
mix. 2 x 10.2/100 = 0.204
ii) Fine aggregate passing 2.36mm and retained on 0.075mm cum
sieve @ 31.9 per cent by weight of mix = 2 x 31.9/100 =
0.638 tonnes = 0.638/1.625 = 0.39
iii) Lime stone dust filler with calcium content not less than 80 t
per cent by weight @ 17.92 per cent by weight of mix = 2 x
17.92/100 = 0.36
iv) Coarse aggregates 6.3 mm to 13.2 mm @ 40 per cent by cum
weight of mix = 2 x 40/100 = 0.8 MT = 0.8/1.456 = 0.55
v) Pre-coated stone chips of 13.2 mm nominal size for skid cum
resistance = 35 x 0.005/10 = 0.018
vi) Bitumen for coating of chips @ 2 per cent by weight = kg
0.018 x 1.456 x 2/100 = 0.0005 MT = 0.5kg
d&e) Overheads & Contractors Profit
Cost for 35.00 sqm = a+b+c+d+e

Rate
Rs.

Amount
Rs.

Remarks

0.204
0.390

0.360

0.550
0.018
0.500

Rate per sqm = (a+b+c+d+e)/35


Note : 1.The rates for 50 mm & 40 mm thick layers may be worked out on pro-rata basis.
2. Where tack coat is required to be provided before laying mastic asphalt, the same is

required to be measured and paid separately.


3. The quantities of binder, filler and aggregates are for estimating purpose. Exact quantities
shall be as per mix design.
4. This rate analysis is based on design made by CRRI for a specific case and is meant for
estimating purposes only. Actual design is required to be done for each case.

RBR-BASC-20

20

Slurry Seal
Providing and laying slurry seal consisting of a mixture of fine
aggregates, portland cement filler, bituminous emulsion and
water on a road surface including cleaning of surface, mixing
of slurry seal in a suitable mobile plant, laying and
compacting to provide even riding surface as per Tech.
Specification 516 MORTH
(i) 5 mm thickness
Unit = sqm
Taking output = 16000 sqm (80 cum)
Taking density of 2.2 tonnes per cum
weight of mix = 176 tonnes
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Mechanical broom
Air compressor 250 cfm
Mobile slurry seal equipment
Front end loader 1 cum bucket capacity
Tipper 5.5 cum capacity for carriage of aggregate from
stockpile on road side to slurry equipment, bitumen emulsion
and filler.

day

day

6.240

hour

6.000

hour

6.000

hour

6.000

hour

6.000

hour

6.000

400

RBR-BASC
Index-code

S. No
1

Description

Unit Quantity

2
3
Pneumatic tyred roller with individual wheel load not exceeding 1.5 hour
tonnes
hour
Water tanker6 KL capacity

c) Material
Residual Binder (BT Emulsion - medium setting) @ 11 t
per cent of mix 80 x 2.2 x 0.11
Fine aggregate 4.75 mm and below 87 per cent of total cum
mix,80 x 2.2 x 0.87 = 153.12 tonnes. Taking density1.5, =
153.12/1.5 = 102.08 cum
t
Filler @ 2 per cent of total mix = 80 x 2.2 x 0.02 (Cement)
Cost of water
d&e) Overheads & Contractors Profit
Cost for 16000 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/16000
(ii) 3 mm thickness
Unit = sqm
Taking output = 20000 sqm (60 cum)
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Mechanical broom
Air compressor 250 cfm
Mobile slurry seal equipment
Front end loader 1 cum bucket capacity

KL

4
6.000

6.000

hour

6.000

hour

6.000

hour

6.000

Tipper 5.5 cum capacity for carriage of aggregate from stockpile on hour
road side to slurry equipment, bitumen emulsion and filler
hour
Water tanker6 KL capacity

6.000
2.000

17.160

cum

74.800

2.640

KL

12.000

day

day

5.200

hour

6.000

hour

6.000

hour

6.000

hour
Tipper 5.5 cum capacity for carriage of aggregate from stockpile on hour
road side to slurry equipment, bitumen emulsion and filler.
hour
Water tanker6 KL capacity

6.000
6.000

KL

12.000

hour

Cost of water
d&e) Overheads & Contractors Profit
Cost for 24000 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/24000

3.520

Fine aggregate 2.36 mm and below,82 per cent of total mix,36x 2.2 x cum
0.82 = 64.94 tonnes. Taking density 1.5
t
Filler @ 2 per cent of total mix = 36x 2.2 x 0.02

102.080

5.200

Remarks

19.360

day

c) Material
Residual Binder (BT Emulsion -Medium setting) @ 16 per
cent of mix, 36 x 2.2 x 0.16

Amount
Rs.

2.000

day

c) Material
Residual Binder (BT Emulsion - medium setting) @ 13 per
cent of mix = 60 x 2.2 x 0.13
Fine aggregate 3 mm and below 85 per cent of total mix,
60x 2.2 x 0.85 = 112.2 tonnes. Taking density 1.5,
Filler @ 2 per cent of total mix = 60x 2.2 x 0.02
Cost of water
d&e) Overheads & Contractors Profit
Cost for 20000 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/20000
(iii) 1.5 mm thickness
Unit = sqm
Taking output = 24000 sqm (36 cum)
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Mechanical broom
Air compressor 250 cfm
Mobile slurry seal equipment
Front end loader 1 cum bucket capacity

Rate
Rs.

2.000
12.670
43.300
1.580
12.000

Note : 1.Tack coat, if required to be provided, before laying slurry seal may be measured and paid
separately

401

RBR-BASC
Index-code

S. No
1

RBR-BASC-21

21

Description

Unit Quantity

Recycling of Bituminous
Recycling Plant

Pavement

with

Rate
Rs.

Amount
Rs.

Remarks

Central

Recycling pavement by cold milling of existing bituminous layers,


planning the surface after cold milling, reclaiming excavated material
to the extent of 30 per cent of the required quantity, hauling and
stock piling the reclaimed material near the central recycling plant
after carrying out necessary checks and evaluation, adding fresh
material including rejuvenators as required, mixing in a hot mix plant,
transporting and laying at site and compacting to the required grade,
level and thickness, all as specified in clause 517 MORTH.

Unit = cum
Taking output = 120 cum (276 tonnes)
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor skilled
b) Machinery
Cold milling machine @ 20 cum per hour
Mechanical broom @ 1250 sqm per hour
Air compressor 250 cfm
Bitumen pressure distributor @ 1750 sqm per hour

day

day

10.000

day

2.480

hour

6.000

hour

1.280

hour

1.280

hour

0.910

Hot mix plant 100-120 TPH producing an average of 75 tonnes per hour
hour
hour
Electric generator set 250 KVA

3.000

Front end loader 1.00 cum bucket capacity


Tipper 5.5 cum capacity
Smooth wheeled roller 8-10 tonnes
Vibratory roller 8 tonnes
Smooth wheeled tandem roller 6-8 tonnes
c) Material
i) Bitumen

3.000

hour

3.000

hour

18.000

hour

1.950

hour

1.950

hour

1.950

1.987

7.728

A bitumen content is 4.5 per cent bitumen weight of mix. For


reclaimed material, fresh bitumen will be required to the extent of 60
per cent of normal requirement.
In a mix of 276 tonnes, 82.8 tonne is reclaimed and balance 193.2
tonne is fresh mix.

Bitumen required for reclaimed mix of 82.8 tonne @ 60 per


cent = 82.8 x 0.60 x0.04 = 1.99
Bitumen required for fresh mix of 193.2 tonnes = 193.2 x 0.04
= 7.73
ii) Aggregates
Percentage of mix requiring fresh aggregates - 70 per cent

Weight of fresh mix = 276 x 0.70 = 193.2 tonne


Weight of fresh aggregate in the mix = 193.2 x 0.96 = 185.47 tonne

Taking average density of 1.5 tonnes/cum, total volume


of aggregate = 123.65 cum.
Size wise requirement of fresh aggregates
cum
37.5 - 25 mm @ 23 per cent
cum
25 - 10 mm @ 15 per cent
cum
10- 5 mm @ 20 per cent
cum
Below 5 mm @40 per cent
t
Filler (cement) @ 2 % of 276 tonne = 5.52 tonnes
d&e) Overheads & Contractors Profit
Cost for 120 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/120

28.440
18.550
24.730
49.460
5.520

Note : Although the total rolling time is only 4 hours as per norms, all the
three rollers have to be available at site for 3 hours each to match with the
output of re-cycling plant. To cater for their idling time, these have been
multiplied with a factor of 0.65.

402

RBR-BASC
Index-code

S. No

Description

RBR-BASC-22

22

Unit Quantity
3

Rate
Rs.

Amount
Rs.

Remarks

Fog Spray
Providing and applying low viscosity bitumen emulsion for sealing
cracks less than 3 mm wide or incipient fretting or disintegration in an
existing bituminous surfacing as per Tech. Specification 518 MORTH.

Unit = sqm
Taking output = 10500 sqm
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Mechanical broom @ 1250 sqm per hour
Air compressor 250 cfm
Bitumen emulsion pressure distributor @ 1750 sqm per hour

day

day

3.120

hour

6.000

hour

6.000

hour

6.000

c) Material
t
Bitumen emulsion (Medium setting) @ 0.75 kg/sqm
d&e) Overheads & Contractors Profit
Cost for 10500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/10500
1.In case it is decided by the engineer to blind the fog spray,
the following may be added
a) Labour
day
Mate
day
Mazdoor (Unskilled) for precoating of grit
b) Material
cum
Crushed stone grit 3 mm size @ 3.75 kg per sqm
Bitumen emulsion for precoating grit @ 2 per cent of t
grit,39.38 x 0.02

7.880

0.160
4.000
26.250
0.790

d&e) Overheads & Contractors Profit


Cost for 10500 sqm = a+b
Rate per sqm = (a+b)/10500

RBR-BASC-23

23

Bituminous Cold Mix ( Including Gravel Emulsion)


Providing, laying and rolling of bituminous cold mix on prepared base
consisting of a mixture of unheated mineral aggregate and emulsified
or cutback bitumen, including mixing in a plant of suitable type and
capacity, transporting, laying, compacting and finishing to specified
grades and levels as per Tech. Specification 519 MORTH.

Unit = cum
Taking output = 205 cum (450 tonne)
(i) Using bitumen emulsion and 9.5 mm or 13.2 mm size
aggregate
Composition of mix (450 tonne) is assumed to be as under:-

Bitumen Emulsion 8 per cent by weight of Total Mixture


Filler2 per cent
Total aggregates 90 per cent
Proportion of aggregates
19 mm to 9.5 mm25 per cent
9.5 mm to 6 mm29 per cent
6 mm to 0.075 mm 36 per cent
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor skilled
b) Machinery
Drum mix plant for cold mixes of appropriate capacity but not
less than 75 tonnes/hour.
Electric generator 125 KVA
Front end loader 1 cum bucket capacity
Tipper 10 tonne capacity
Add 10 per cent of cost of carriage to cover cost of loading
and unloading
Paver finisher
Pneumatic tyred roller 12-15 tonnes
Smooth wheeled steel tandem roller 6-8 tonnes
c) Material
Bitumen emulsion (Medium setting) @ 8 per cent
Filler (lime)@ 2 per cent
Aggregates size 19 to 9.5 mm - 450 x 0.25 x 1/1.5
Aggregates size 9.5 to 6 mm - 450 x 0.29 x 1/1.5

day

day

16.000

day

5.840

hour

6.000

hour

6.000

hour

6.000

t.km

450 x L

hour

6.000

hour

3.900

hour

3.900

36.000

9.000

cum

75.000

cum

87.000

cum
Aggregates size 6 to 0.075 mm - 450 x 0.36 x 1/1.5
d&e) Overheads & Contractors Profit
Cost for 205 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/205
(Applicable to cases I to IV)
Note : 1. Density of aggregates has been assumed 1.5 gms/cc

108.000

2. Tack coat where provided will be measured and paid separately.

403

RBR-BASC
Index-code

S. No
1

Description
2

Unit Quantity
3

Rate
Rs.

Amount
Rs.

Remarks

3. Though the rollers are required only for 3.5 hours each as per norms of output, but these are required
to be available at site for 6 hours as the drum mix plant and the paver would take 6 hours for mixing and
paving. To cater for the idle period, their usage rates have been multiplied by a factor of 0.65
(ii) Using bitumen emulsion and 19 mm or 26.5 mm nominal

size aggregate
Composition of mix (450 tonne) is assumed to be as under:Bitumen Emulsion 8 per cent
Filler2 per cent
Total aggregates 90 per cent
Proportion of aggregates
37.5 mm to 19 mm25 per cent
19 mm to 6 mm 30 per cent
6 mm to 0.075 mm 35 per cent
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor skilled
b) Machinery
Drum mix plant for cold mixes 60-90 tonne per hour
producing average output of 75 tonnes per hour
Electric generator 125 KVA
Front end loader 1 cum bucket capacity
Tipper 10 tonne capacity

day

day

16.000

day

5.840

hour

6.000

hour

6.000

hour

6.000

t.km

450 x L

Add 10 per cent of cost of carriage to cover cost of loading


and unloading
hour
Paver finisher
hour
Pneumatic tyred roller 12-15 tonnes
hour
Smooth wheeled steel tandom roller 6-8 tonnes
c) Material
t
Bitumen emulsion (Medium setting) @ 8 per cent
t
Filler (lime)@ 2 per cent
cum
Aggregates size 37.5 to 19 mm - 450 x 0.25 x 1/1.5
cum
Aggregates size 19 to 6 mm - 450 x 0.3 x 1/1.5
cum
Aggregates size 6 to 0.075 mm - 450 x 0.35 x 1/1.5
d&e) Overheads & Contractors Profit
Cost for 205 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/205
Note : 1. Density of aggregates has been assumed 1.5 gms/cc

6.000
3.900
3.900
36.000
9.000
75.000
90.000
105.000

2. Tack coat where provided will be measured and paid separately.


3. Though the rollers are required only for 3.5 hours each as per norms of output, but these
are required to be available at site for 6 hours as the drum mix plant and the paver would
take 6 hours for mixing and paving. To cater for the idle period, their usage rates have been
multiplied by a factor of 0.65

404

RBR-BASC
Index-code

S. No

Description

1
2
(iii) Using cutback bitumen and 9.5 mm or 13.2 mm nominal

Unit Quantity
3

Rate
Rs.

Amount
Rs.

Remarks

size aggregate
Composition of mix (450 tonne) is assumed to be as under:Cutback bitumen 5 per cent
Filler (lime) 2 per cent
Total aggregates 93 per cent
Proportion of aggregates
19 mm to 9.5 mm26 per cent
9.5 mm to 6 mm31 per cent
6 mm to 0.075 mm 36 per cent
a) Labour
day
Mate
day
Mazdoor (Unskilled)
day
Mazdoor skilled
b) Machinery
Drum mix plant for cold mixes 60-90 tonne per hour hour
producing average output of 75 tonnes per hour
hour
Electric generator 125 KVA
hour
Front end loader 1 cum bucket capacity
t.km
Tipper 10 tonne capacity

16.000
5.840
6.000
6.000
6.000
450 x L

Add 10 per cent of cost of carriage to cover cost of loading


and unloading
hour
6.000
Paver finisher
hour
3.900
Pneumatic tyred roller 12-15 tonnes
hour
3.900
Smooth wheeled steel tandem roller 6-8 tonnes
c) Material
t
22.500
Cutback bitumen @ 5 per cent
t
9.000
Filler (lime)@ 2 per cent
cum 78.000
Aggregates size 19 to 9.5 mm - 450 x 0.26 x 1/1.5
cum 93.000
Aggregates size 9.5 to 6 mm - 450 x 0..31 x 1/1.5
cum 108.000
Aggregates size 6 to 0.075 mm - 450 x 0.36 x 1/1.5
d&e) Overheads & Contractors Profit
Cost for 205 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/205
Note : 1. Density of aggregates has been assumed 1.5 gms/cc
2. Tack coat where provided will be measured and paid separately.
3. Though the rollers are required only for 3.5 hours each as per norms of output, but these are required
to be available at site for 6 hours as the drum mix plant and the paver would take 6 hours for mixing and
paving. To cater for the idle period, their usage rates have been multiplied by a factor of 0.65
(iv) Using cutback bitumen and 19 mm or 26.5 mm nominal

size aggregate
Composition of mix (450 tonne) is assumed to be as under:Cutback bitumen 5 per cent
Filler2 per cent
Total aggregates 93 per cent
Proportion of aggregates
37.5 mm to 19 mm25 per cent
19 mm to 6 mm 30 per cent
6 mm to 0.075 mm 38 per cent
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor skilled
b) Machinery
Drum mix plant for cold mixes 60-90 tonne per hour
producing output of 75 tonnes per hour
Electric generator 125 KVA
Front end loader 1 cum bucket capacity
Tipper 10 tonne capacity
Paver finisher
Pneumatic tyred roller 12-15 tonnes.
Smooth wheeled steel tandem roller 6-8 tonnes
c) Material
Cutback bitumen on @ 5 per cent
Filler (lime)@ 2 per cent
Aggregates size 37.5 to 19 mm - 450 x 0.25 x 1/1.5
Aggregates size 19 to 6 mm - 450 x 0.3 x 1/1.5
Aggregates size 6 to 0.075 mm - 450 x0.38 x 1/1.5
d&e) Overheads & Contractors Profit
Cost for 205 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/205

day

day

16.000

day

5.840

hour

6.000

hour

6.000

hour

6.000

t.km

450 x L

hour

6.000

hour

3.900

hour

3.900

22.500

9.000

cum

75.000

cum

90.000

cum

114.000

Note : 1. Density of aggregates has been assumed 1.5 gms/cc


2. Tack coat where provided will be measured and paid separately.
3. Though the rollers are required only for 3.5 hours each as per norms of output, but these are required to
be available at site for 6 hours as the drum mix plant and the paver would take 6 hours for mixing and
paving. To cater for the idle period, their usage rates have been multiplied by a factor of 0.65

RBR-BASC-24

24

Sand Asphalt Base Course

405

RBR-BASC
Index-code

S. No

Description

2
Providing, laying and rolling sand-asphalt base course composed of
sand, mineral filler and bituminous binder on a prepared sub-grade or
sub-base to the lines, levels, grades and cross sections as per the
drawings including mixing in a plant of suitable type and capacity,
transporting, laying, compacting and finishing as per Tech.
specification 520 MORTH.

Unit = cum
Taking output = 205 cum (450 tonne)
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor skilled
b) Machinery

Unit Quantity
3

day

day

16.000

day

5.840

Hot Mix Plant of appropriate capacity but not less than 75 tonnes/hour hour

6.000

Electric generator set 250 KVA


Front end loader 1 cum bucket capacity
Tipper 10 tonne capacity
Add 10 per cent of cost of carriage to cover cost of loading
and unloading
Paver finisher
smooth wheeled roller 8-10 tonnes for initial break down
rolling.
Vibratory roller 8 tonnes for intermediate rolling.

hour

6.000

Finish rolling with 6-8 tonnes smooth wheeled tandom rollers.

hour

6.000

t.km

450 x L

hour

6.000

hour

3.900

hour

3.900

hour

3.900

c) Material
Composition of mix (450 tonne) is assumed to be as
under:Density 2.20 tonne per cum
Weight450 tonne
Bitumen5 per cent
Filler2 per cent
Sand of size 4.75 to 0.075 mm 93 per cent
t
Bitumen@ 5 per cent
t
Filler (lime)@ 2 per cent
cum
Sand of size 4.75 to 0.075 mm - 450 x 0.93 x 1/1.5
d&e) Overheads & Contractors Profit
Cost for 205 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/205

Rate
Rs.

Amount
Rs.

Remarks

22.500
9.000
288.620

Note : 1. Tack coat will be measured and paid separately


2. Although the rollers are required only for 3 hours as per norms of output, but the same have to be
available at site for six hours as the hot mix plant and paver will take six hours for mixing and paving the
output of 450 tonnes considered in this analysis. To cater for the idle period of this roller, their usage rates
has been multiplied by a factor of 0.65

406

RBR-BASC
Index-code

S. No
1

RBR-BASC-25

Description
2

25

Unit Quantity
3

Rate
Rs.

Amount
Rs.

Remarks

Modified Binder
Supply of modified binder produced by mixing bitumen with modifier such as natural rubber
or crumb rubber or any other polymer found compatible with bitumen and which allows
properties given in clause 521.3 and IRC:SP: 53 blending of modifier with bitumen to be done
either at the refinery or at central unit with all facilities by proper industrial process, is
essential. See Tech. specification 521 MORTH.
Unit = tonne
The use of modified binder is expected to result in an extended service life of bituminous
pavements subject to heavy traffic loads in extreme climatic conditions, thus justifying the
entire cost of adding modifiers/fibers. Other advantages include lower temperature
susceptibility, higher resistance to aging, higher fatigue life, higher resistance to cracking and
better adhesion between aggregates and binder.
Detailed information and inductive dose level on the use of polymer modified binder is
available in IRC : SP-53 / 2002. A number of proprietary products are now available in the
market. For such proprietary products, test reports and cost effectiveness should be the
basis for their selection in road works.
The modifier, in the required quantity shall be blended at the refinery or at central unit with all
facilities by proper industrial process, is essential. If supplied in drums it shall be agitated in
melted condition with suitable device for achieving homogeneity
Proposals to use glass fiber, polypropylene fibers or any other similar material in a
bituminous mixture should be substantiated, complete with all details including test results,
manufacturer's recommendations for addition or means of incorporating the fibers,
homogeneously, without segregation, into the mixture.
Before agreeing to the use of a fiber, it should have been proved to be satisfactory in use
under circumstances, similar to the work, elsewhere or it would have under gone appropriate
performance trials. Documented evidence of use and trials of the fiber, in any country having
conditions similar to Indian will be acceptable.
where information on use of trials is inadequate or lacking, trials may be required to be under
taken before agreeing to the use of the fiber.
Note : 1. The modified binder is usually manufactured by specialised firms as a proprietary product. The
rate for this product is required to be as certained from the market.
2.The specifications for various item of road works using polymer/rubber modified bitumens are same as
those for penetration grade bitumen except those for any special conditions which the manufacturer may
indicate
3.The other controls during mixing, laying shall be same as specified in IRC - 14, 29, 94 and 95 for open
graded premix carpet, bituminous concrete, DBM and SDBC respectively
4.The temperature of mixing and rolling will be slightly higher than conventional bituminous mixes as
indicated in Table 8 of IRC: SP: 53 - 2002

RBR-BASC-26

26
i

Crack Prevention Courses


Stress absorbing membrane (SAM) crack width less than
6 mm
Providing and laying of a stress absorbing membrane over a cracked
road surface, with crack width below 6 mm after cleaning with a
mechanical broom, using modified binder complying with clause 521,
sprayed at the rate of 9 kg per 10 sqm and spreading 5.6 mm crushed
stone aggregates @ 0.11 cum per 10 sqm with hydraulic chip
spreader, sweeping the surface for uniform spread of aggregates and
surface finished to conform to clause 902. Tech. Specification 522
MORTH.

Unit = sqm
Taking output = 10500 sqm
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Mechanical broom @ 1250 sqm per hour
Air compressor 250 cfm
Bitumen pressure distributor @ 1750 sqm per hour
Hydraulic Chip spreader
Smooth wheeled road roller 8-10 tonne
c) Material
Modified binder
Crushed stone aggregates 5.6 mm size
d&e) Overheads & Contractors Profit
Cost for 10500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/10500
(ii) Stress absorbing membrane (SAM) with crack width 6
mm to 9 mm

day
day

6.240

hour

6.000

hour

6.000

hour
hour
hour

6.000
6.000
6.000

t
cum

9.450
105.000

day
day

6.240

hour

6.000

hour

6.000

hour

6.000

Providing and laying of a stress absorbing membrane over a cracked


road surface, with crack width 6 to 9 mm after cleaning with a
mechanical broom, using modified binder complying with clause 521,
sprayed at the rate of 11 kg per 10 sqm and spreading 11.2 mm
crushed stone aggregates @ 0.12 cum per 10 sqm, sweeping the
surface for uniform spread of aggregates and surface finished to
conform to clause 902, Tech. Specification 522 MORTH.

Unit = sqm
Taking output = 10500 sqm
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Mechanical broom @ 1250 sqm per hour
Air compressor 250 cfm capacity
Bitumen pressure distributor @ 1750 sqm per hour

407

RBR-BASC
Index-code

S. No

Description

Unit Quantity
3

hour
Hydraulic Chip spreader
hour
Smooth wheeled road roller 8-10 tonne
c) Material
t
Modified binder
cum
Crushed stone chipping 11.2 mm size
d&e) Overheads & Contractors Profit
Cost for 10500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/10500
(iii) Stress absorbing membrane (SAM) crack width above 9
mm and cracked area above 50 per cent

4
6.000

Rate
Rs.

Amount
Rs.

Remarks

6.000
11.550
105.000

Providing and laying a single coat of a stress absorbing membrane


over a cracked road surface, with crack width above 9 mm and
cracked area above 50 per cent after cleaning with a mechanical
broom, using modified binder complying with clause 521, sprayed at
the rate of 15 kg per 10 sqm and spreading 11.2 mm crushed stone
aggregates @ 0.12 cum per 10 sqm, sweeping the surface for
uniform spread of aggregates and surface finished to conform to
clause 902, Tech. Specification 522 MORTH.

Unit = sqm
Taking output = 10500 sqm
a) Labour
day
Mate
day
6.000
Mazdoor (Unskilled)
day
2.240
Mazdoor skilled
b) Machinery
hour
6.000
Mechanical broom @ 1250 sqm per hour
hour
6.000
Air compressor 250 cfm capacity
hour
6.000
Bitumen pressure distributor @ 1750 sqm per hour
hour
6.000
Hydraulic Chip spreader
hour
6.000
Smooth wheeled road roller 8-10 tonne
c) Material
t
15.750
Modified binder
cum 126.000
Crushed stone aggregates 11.2 mm size
d&e) Overheads & Contractors Profit
Cost for 10500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/10500
Note : In case 2nd coat is also required to be provided, material provided for the 2nd coat
shall be as per table 500-47.

408

RBR-BASC
Index-code

S. No
1

Description

2
(iv) Case-IV : Bitumen impregnated geotextile

Providing and laying a bitumen impregnated geotextile layer


after cleaning the road surface, geotextile conforming to
requirements of clause 703.3, laid over a tack coat with 1.05
kg per sqm of paving grade bitumen 80 - 100 penetration and
constructed to the requirement of clause 703.4.5, Tech.
Specification 522 MORTH.
Unit = sqm
Taking output = 3500 sqm
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor skilled
b) Machinery
Mechanical broom @ 1250 sqm per hour
Air compressor 250 cfm capacity
Bitumen pressure distributor @ 1750 sqm per hour
Pneumatic roller
c) Material
Paving grade bitumen of 80 - 100 penetration @ 1.05 kg per sqm

Geotextile including 10 per cent for overlaps


d&e) Overheads & Contractors Profit
Cost for 3500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/3500

Unit Quantity
3

day

day

12.000

day

2.560

hour

2.800

hour

2.800

2.000

hour

2.000

Rate
Rs.

Amount
Rs.

Remarks

t
3.680
sqm 3850.000

Note : As bitumen overlay construction shall follow closely the fabric


placement on the same day, an output of 3500 sqm only has been
considered for the analysis which will cover a length of 500 m, of 7 m wide
carriageway. This can be conveniently overlaid by a bituminous course in a
day

RBR-BASC-27

27

Recipe Cold Mix


Providing and laying of premix of crushed stone aggregates and
emulsion binder, mixed in a batch type cold mixing plant, laid over
prepared surface, by paver finisher, rolled with a pneumatic tyred
roller initially and finished with a smooth steel wheel roller, all as per
clause 519.3 MORTH

Unit = cum
Taking output = 205 sqm (450 tonnes)
(i) 75 mm thickness
a) Labour
day
Mate
day
Mazdoor (Unskilled)
day
Mazdoor skilled
b) Machinery
Drum mix plant for cold mixes 40 / 60 tonne per hour hour
producing output of 50 tonnes per hour
hour
Electric generator 125 KVA
hour
Front end loader 1 cum capacity
Paver finisher hydrostatic with sensor control @ 75 cum/ hour

hour
t.km

Tipper 10 tonne capacity


Add 10 per cent of cost of carriage to cover cost of loading
and unloading
hour
Pneumatic tyred roller12-15 tonnes.
Smooth wheeled steel roller6-8 tonnes.
Water tanker6 KL capacity
c) Material
Bitumen emulsion (MS) @ 45 litres per tonne
Crushed stone aggregates 40 mm nominal size
Cost of water
d&e) Overheads & Contractors Profit
Cost for 205 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/205

hour
hour

12.000
6.000
9.000
6.000
6.000
6.000
450 x L

3.900
3.900
1.000

20.250

cum

297.000

KL

6.000

409

RBR-BASC
Index-code

S. No

Description

2
ii

40 mm thickness
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor skilled
b) Machinery

Unit Quantity
3

day

day

12.000

day

6.000

Batch type cold mixing plant100-120 TPH capacity producing an hour


average output of 75 tonne per hour
Drum mix plant for cold mixes 40 / 60 tonne per hour hour

9.000

producing output of 50 tonnes per hour


hour
Electric generator 125 KVA
hour
Front end loader 1 cum capacity
Paver finisher hydrostatic with sensor control @ 75 cum per hour
hour
t.km
Tipper 10 tonne capacity

Rate
Rs.

Amount
Rs.

Remarks

6.000
6.000
6.000
450 x L

Add 10 per cent of cost of carriage to cover cost of loading and


unloading

Pneumatic tyred roller 12-15 tonnes.


Smooth wheeled steel roller 6-8 tonnes.
Water tanker6 KL capacity
c) Material
Bitumen emulsion (MS) @ 70 litres per tonne
Crushed stone aggregates 14 mm nominal size
Cost of water
d&e) Overheads & Contractors Profit
Cost for 205 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/205
iii 25 mm thickness
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor skilled
b) Machinery
Batch type cold mixing plant 100-120 TPH capacity producing
an average output of 75 tonne per hour
Drum mix plant for cold mixes 40 / 60 tonne per hour
producing output of 50 tonnes per hour
Electric generator 125 KVA
Front end loader 1 cum capacity
Paver finisher hydrostatic with sensor control @ 75 cum per
hour
Tipper 10 tonne capacity
Add 10 per cent of cost of carriage to cover cost of loading
and unloading
Pneumatic tyred roller
Smooth wheeled steel roller
Water tanker6 KL capacity
c) Material
Bitumen emulsion (MS) @ 85 litres per tonne
Crushed stone aggregates 6 mm nominal size
Cost of water
d&e) Overheads & Contractors Profit
Cost for 205 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/205

hour

3.900

hour

3.900

hour

1.000

31.500

cum

287.000

KL

6.000

day

day

12.000

day

6.000

hour

hour

9.000

hour

6.000

hour

6.000

hour

6.000

t.km

450 x L

hour
hour

3.900
3.900

hour

1.000

38.250

cum

270.000

KL

6.000

410

RBR-BASC
Index-code

S. No

Description

Unit Quantity
3

Rate
Rs.

Amount
Rs.

Remarks

Note : (Case I to III)


1. These mixes are considered suitable for minor repair work and temporary road surface
improvement.
2. In case concrete mixtures are required to be used for mixing, a number of these will be
needed to match the capacity of road rollers.
3. Tack coat, where provided, will be measured and paid separately.
4. Both the rollers have to be available at site to match with the output of batch mixing plant
and paver finisher. A multiplying factor of 0.65 has been adopted to cater for the idling period
of road rollers.
General Note :

1. The provisions towards Mate is included in the provision towards unskilled


Mazdoor upto item 2.
2. The provisions towards Mate is included in the provision towards skilled Mazdoor
from item 3.

411

RBR-CCPV

Andhra Pradesh Standard Data


I. Roads and Bridges

Chapter - 6
CEMENT CONCRETE PAVEMENT
Index-code

S. No
1

RBR-CCPV-1

RBR-CCPV-2

RBR-CCPV-3

RBR-CCPV-4

Description
2

Unit Quantity
3

Rate
Rs.

Amount
Rs.

Remarks

Granual Sub-base
Rate as per item No. 1 or 2 of Chapter 4
Lime Treated Soil
Rate as per item No. 3 or 4 of Chapter 4
Water Bound Macadam (WBM) - Sub-base
(A) By Manual Means
As per item No.9 of Chapter 4
(B) By Mechanical Means
As per item No.9 of Chapter 4
Dry Lean Cement Concrete Sub- base
Construction of dry lean cement concrete Sub- base over a prepared
sub-grade with coarse and fine aggregate conforming to IS: 383, the
size of coarse aggregate not exceeding 25 mm, aggregate cement
ratio not to exceed 15:1, aggregate gradation after blending to be as
per table 600-1, cement content not to be less than 150 kg/ cum,
optimum moisture content to be determined during trial length
construction, concrete strength not to be less than 10 Mpa at 7 days,
mixed in a batching plant, transported to site, laid with a paver with
electronic sensor, compacting with 8-10 tonnes vibratory roller,
finishing and curing etc. complete as per Technical Specification 601
MORTH.

Unit = cum
Taking output = 450 cum (990 tonne)
a) Labour
Mate
Mazdoor skilled
Mazdoor (Unskilled)
b)
Machinery
Front end loader 1 cum bucket capacity
Cement concrete batch mix plant @ 75 cum per hour
Electric generator 100 KVA
Paver with electronic sensor
Vibratory roller 8-10 t capacity
Water tanker 6 KL capacity
Tipper
c)
Material
Crushed stone coarse aggregate of 25 mm and 12.5 mm
nominal sizes graded as per table 600-1 @ 0.90 cum/cum of
concrete conforming to clause 602.2.4.
Coarse Sand as per IS: 383 @ 0.45 cum/cum of concrete
Cement @ 150 kg/cum of concrete
Cost of water
d&e) Overheads & Contractors Profit
Cost for 450 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/450

day

day

7.12

day

22.00

hour

6.00

hour

6.00

hour

6.00

hour

6.00

hour

8.00

hour

8.00

t.km

990 x L

cum

405.00

cum

203.00

tonne

67.50

KL

48.00

Note : Quantity provided for aggregate is for estimating purpose.


Exact quantity shall be as per mix design.

413

RBR-CCPV
Index-code

RBR-CCPV-5

S. No

Description

Unit Quantity
3

Rate
Rs.

Amount
Rs.

Remarks

Cement Concrete Pavement


Construction of un-reinforced, dowel jointed at expansion and
construction joint only, plain cement concrete pavement, thickness
as per design, over a prepared sub base, with 43 grade cement or
any other type as per Clause 1501.2.2 M30 (Grade), coarse and
fine aggregates conforming to IS : 383, maximum in a concrete
mixer of not less than 0.2 cum capacity and appropeiate weigh
batcher using approved mix design, laid in approved fixed side
formwork (steel channel, laying and fixing of 125 mictron thick
polythene film, wedges, steel plates including levelling the
formwork as per drawing), spreading the concrete with sholvels,
rakes, compacted using needle, scareed and plate vibrators and
finished in continuous operation including provision of contraction
and expansion, construction joints, applying debonding strips,
primer, sealant, dowel bars, near approaches to bridge / culvert
and construction joints, admixtures as approved, curing of
concrete slabs for 14- days, curing compound (where specified)
and water finishing to lines and grade as per drawing and
Technical Specification Clause 1501 MORD.
Unit = cum
Taking output = 75 cum (172.50 t)
(100 x 3.75 x 0.200)
a) Labour
Mate
Mason (1st class)
Mason (2nd class)
Mazdoor (Unskilled)
Mazdoor (Skilled)
Surveyor
Mazdoor (Semi-Skilled)
Blacksmith for cutting of dowel bars including removal of
burrs, fabrications & fixing of dowel bars.
b) Machinery
Concrete mixer 0.28 / 0.4 cum capacity (6 mixers) with weigh
batcher and suitable capacity calibrated water tank
Needle vibrator
Screed vibrator
Plate vibrator
Concrete joint cutting machine for initial & final cuts
Water tanker 6 kl capacity
Air Compressor (1 hour initial + 1 hour final)
c) Material
Crushed stone coarse aggregates, grading will be as per
Clause 1501.2.4.1 (Table 1500.1) of specifications @ 0.90
cum/cum of concrete (25 mm & 12.5 mm blending)
Sand as per IS:383 and conforming to Clause 1500.2.4.2 @
0.45 cum/cum of concrete
Cement @ 310 kg/cum of concrete

day

day

5.00

day

5.00

day

150.00

day

6.00

day

2.00

day

6.00

day

1.00

hour

36.00

hour

9.00

hour

9.00

hour

9.00

hour

4.00

hour

5.00

hour

2.00

cum

67.50

cum

33.75

26.25

sqm
Polythene sheet 125 micron
Mild steel dowel bar 25 mm dia of grade S 240. 500 mm long
20 Nos. at culvert/bridge slab and at construction joint
including 5 per cent wastage.
(4 x 20 x 0.500) + 5 per cent wastage = 42 m @ 2.80 kg per t
m = 117.6 kg.
kg
Bitumen primer @ 200 ml per joint for 23 joints
litre
Bituminous sealant 800 ml per joint for 23 joints
m
Jute rope 12 mm dia including 5 per cent wastage
Debonding strips 3.75 m (length) x 10 mm (width) x 5 mm m
(thick) cut-out of rubber filler board or similar material
including 5 per cent wastage

412.50

Polythene sheathing, covering 2/3rd dowel bars (20x23) and No.


tight fit including 5 per cent wastage

483.00

litre

122.00

litre

131.25

kl

18.00

sqm

3.00

Plasticizer 0.5 per cent by weight of cement


Curing compound (if used) @ 0.33 litre per sqm
Water for curing
Joint filler board 20 mm thick as per IS:1838
(4 x 3.75 x 0.200 = 3 sqm)
d) Formwork @ 3% of (a+b+c)

0.118
5.00
19.00
90.00
90.00

e&f) Overheads & Contractors Profit


Cost for 75 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/75

414

RBR-CCPV
Index-code

S. No

Description

2
Construction of un-reinforced, dowel jointed, plain cement concrete
pavement over a prepared sub base with 43 grade cement @ 400 kg
per cum, coarse and fine aggregate conforming to IS 383, maximum
size of coarse aggregate not exceeding 25 mm, mixed in a batching
and mixing plant as per approved mix design, transported to site, laid
with a fixed form or slip form paver, spread, compacted and finished
in a continuous operation including provision of contraction,
expansion, construction and longitudinal joints, joint filler, separation
membrane, sealant primer, joint sealant, debonding strip, dowel bar,
tie rod, admixtures as approved, curing compound, finishing to lines
and grades as per drawing and Technical Specification 602 MORTH.

RBR-CCPV-6

Unit = cum
Taking output = 1050 cum (2415 tonne)
a) Labour
Mate
Mazdoor skilled
Mazdoor (Unskilled)
b)
Machinery
Road Sweeper @ 1250 sqm per hour
Front end loader 1 cum bucket capacity
Cement concrete batch mix plant @ 175 cum per hour
(effective
output) 250 KVA
Electric generator
Slip form paver with electronic sensor
Water tanker6 KL capacity
Transit truck agitator 5 cum capacity.
Concrete joint cutting machine
Texturing machine
c)
Material
Crushed stone coarse aggregates of 25mm and 12.5mm
nominal size @ 0.90 cum/cum of concrete conforming to
clause 602.2.4.
Sand as per IS: 383 and conforming to clause 602.2.4 @
0.45 cum/cum of concrete
Cement 43 grade @ 400 kg/cum of concrete
32 mm mild steel dowel bars of grade S 240
16 mm deformed steel tie bars of grade S 415
Separation Membrane of impermeable plastic sheeting 125
micron thick
Pre moulded Joint filler, 25 mm thick for expansion joint.
Joint sealant

Unit Quantity
3

day

day

15.00

day

37.00

hour

2.80

hour

18.00

hour

6.00

hour

6.00

hour

6.00

hour

36.00

Rate
Rs.

Amount
Rs.

Remarks

tonne 2415xL
.km
hour
12.00
hour

12.00

cum

945.00

cum

473.00

tonne

414.00

tonne

9.45

tonne

1.17

sqm

3675.00

sqm

16.33

kg

875.00

415

RBR-CCPV
Index-code

RBR-CCPV-7

S. No

Description

Unit Quantity
3
kg

4
116.67

Rate
Rs.

Amount
Rs.

Remarks

Sealant primer
sqm
46.67
Plastic sheath,1.25 mm thick for dowel bars
liter 1850.00
Curing compound
Super plastisizer admixture IS marked as per 9103-1999 @ kg 2070.00
0.5 per cent by weight of cement
KL
216.00
Cost of water
Add 1 per cent of material for cost of miscellaneous
materials like tarpaulin, Hessian cloth, metal cap, cotton /
compressible sponge and cradle for dowel bars, work
bridges for men to approach concrete surface without
walking over it, cutting blades and bites, minor equipments
like scrabbling machine, threads, ropes, guide wires and any
other unforeseen items.
d&e) Overheads & Contractors Profit
Cost for 1050 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/1050
Note : The quantities for cement, coarse aggregate and fine
aggregates are for estimating only .The exact quantities will be as
per mix design.
Roller Compacted Concrete Pavement
Construction of Roller Compacted Concrete Pavement (RCCP) with
coarse and fine aggregates conforming to IS:383, the size of coarse
aggregate not exceeding 25 mm with minimum aggregate cement
ratio of 5:1 and with minimum cement content of 310 kg per cum,
aggregate gradation to be as per Table 602.2 after blending, mixing in
concrete mixer at optimum moisture content, transporting to site,
laying with wheel barrows or steel pans or with mechanical paver,
compacting with 80-100 kN smooth wheel, tendem, vibratory roller, to
achieve, the designed flexural strength, finishing and curing as per
drawings and Technical Specification Clause 1502 MORD.

Unit = cum
Taking output = 75 cum
a) Labour
Mate
Mazdoor (Unskilled)
Mason (1st class)
Mason (2nd class)
Surveyor
b) Machinery
Concrete mixer 0.28 / 0.4 cum capacity (6 mixers) with weigh
batcher and suitable capacity calibrated water tank
Three wheel 80-100 kN static roller
OR
Vibratory roller 80-100 kN
Concrete joint cutting machine for days end work and
regulartanker
joint cutting.
Water
6 kl capacity
Air compressor (1 hour initial + 1 hour final)
c) Material
Crushed stone coarse aggregates grading as per Clause
1501.2.4.1 (Table 1500.3) @ 0.90 cum/cum of concrete
conforming to Clause 600.4.4 (25 mm & 12.5 mm blending)

day

day

152.00

day

4.00

day

4.00

day

2.00

hour

36.00

hour

7.50

hour

6.00

hour

6.00

hour

6.00

hour

2.00

cum

67.50

Sand as per IS:383 and conforming to Clause 1501.2.4.2 @ cum


0.45 cum/cum of concrete

33.75

416

RBR-CCPV
Index-code

S. No

Description

Unit Quantity
3
t

Cement @ 310 kg/cum of concrete


Bituminous primer @ 200 ml per joint for 21 joints
Jute rope 10 mm dia including 5 per cent wastage
Bituminous sealant @ 800 ml per joint for 21 joints
Curing compound @ 0.33 litre per sqm
Water for mixing and curing for 14-days
d) Formwork @ 3% of (a+b+c)
e&f) Overheads & Contractors Profit
Cost for 75 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/75
Cost for 75 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/75

4
23.25

kg

4.00

90.00

kg

16.80

131.25

kl

18.00

Rate
Rs.

Amount
Rs.

Remarks

Note : When curing compound is used 4-days water curing will be done

RBR-CCPV-8

Rolled Cement Concrete Base


Construction of rolled cement concrete base course with coarse and
fine aggregate conforming to IS:383, the size of coarse aggregate not
exceeding 25 mm with minimum, aggregate cement ratio15:1 and
minimum cement content of 200 kg/cum, aggregate gradation to be
as per table 600-4 after blending, mixing in batching plant at optimum
moisture content, transporting to site, laying with a paver with
electronic sensor, compacting with 8-10 tonnes smooth wheeled
vibratory roller to achieve, the designed flexural strength, finishing
and curing as per Technical Specification 603 MORTH.

Unit = cum
Taking output = 450 cum (990 tonne)
a) Labour
Mate
Mazdoor skilled
Mazdoor (Unskilled)
b)
Machinery
Front end loader 1 cum bucket capacity
Cement concrete batch mix plant @ 75 cum per hour
Electric generator 100 KVA
Paver with electronic sensor @ 75 cum/hr.
Vibratory roller 8-10 t capacity
Water tanker with 5 km lead 6 KL capacity
Tipper

day

day

7.00

day

24.20

hour

6.00

hour

6.00

hour

6.00

hour

6.00

hour

8.00

hour

tonne
Add 10 per cent of cost of carriage to cover cost of loading and .km
unloading

c)

8.00
990xL

Material

Crushed stone coarse aggregates of 25mm and 12.5mm nominal cum


size @ 0.90 cum/cum of concrete conforming to clause 602.2.3.
Sand as per IS: 383 and conforming to clause 602.2.3 @ 0.45 cum
cum/cum of concrete
tonne
Cement @ 200 kg/cum of concrete
KL
Cost of water

405.00
203.00
90.00
48.00

d&e) Overheads & Contractors Profit


Cost for 450cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/450
Note : The quantities for cement, coarse aggregate and fine aggregates are
for estimating only .The exact quantities will be as per mix design.

417

RBR-CCPV
Index-code

RBR-CCPV-9

S. No

Description

Unit Quantity
3

Rate
Rs.

Amount
Rs.

Remarks

Transition Section between Rigid and Flexible Pavement


Due to change in the properties of materials and type of construction,
a gradual changeover from rigid pavement to flexible pavement is
desirable to avoid any damage at the butting joint. After provision of
an expansion joint in the cement concrete slab, the thickness of slab
should be tapered to 10 cm over a length of 3 m towards the flexible
pavement. The deficiency of thickness caused due to tapering of the
slab should be made up by the asphaltic layers.
The quantities of items should be worked out based on the approved
design and drawings and priced as per rates given under respective
clauses for cement concrete and asphaltic work.

RBR-CCPV-10

10

Construction of Base/Sub-Base of Pavement with Lean


Concrete - Flyash.
Construction of Base/sub-base using cement, sand, fly ash and
coarse aggregates proportioned as per table 4 of IRC: 74/1979 and
with water content ratio, slump and compressive strength as defined
in the said table, mix prepared in a batching and mixing plant and
compacted with a vibratory roller 8-10 tonnes capacity within the time
limit laid down vide clause 7.6.3 of IRC: 74-1979, construction joints
properly formed at the end of day's work, cured for 14 days, all as
specified in IRC: 74-1979 and as per approved plans MORTH.
(Suggestive MORTH)

Unit = cum
Taking output = 450 cum (990 tonne)
a)

Labour

Mate

day

Mazdoor skilled

day

6.00

Mazdoor (Unskilled)

day

23.12

Front end loader 1 cum bucket capacity

hour

6.00

Cement concrete batch mix plant @ 75 cum per hour

hour

6.00

Electric generator 100 KVA

hour

6.00

Paver finisher with electronic sensor

hour

6.00

Vibratory roller 8-10 t capacity

hour

8.00

Water tanker6 KL capacity

hour

8.00

Tipper 10 T Capacity

t.km

990 x L

b)

Machinery

Add 10 per cent of cost of carriage to cover cost of loading


and unloading
c)
Material

Crushed stone coarse aggregate of 40 mm nominal size @ 0.90 cum


cum/cum of concrete conforming to table 2 of IRC: 74-1979.
cum
Coarse Sand as per IS: 383 - 1970

405.00
110.96

Cement @ 150 kg/cum of concrete

tonne

67.50

Fly ash conforming to IS: 3812 ( Part II )

cum

91.54

( Total fine aggregates = 450 x 0.45 = 202.50 cum To be divided in


ratio of 2 sand : 1.65 flyash. Refer table 4 of IRC: 74-1979).

d&e) Overheads & Contractors Profit


Cost for 450cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/450
Note : 1. Depending upon approved designs, crushed stone aggregates of
nominal size 20mm can also be used as per gradation given in table 2 of
IRC: 74-1979.
2. The ratio of specific gravities of fly ash and sand has been assumed to be
0.827.
3. The quantities of materials given in the analyses are for estimating
purposes. Actual quantities shall be as per job mix formula.
4. Construction procedure as laid down in clause, of IRC: 74-1979 shall be
followed.

418

RBR-CCPV
Index-code

RBR-CCPV-11

S. No

Description

11

Unit Quantity
3

Rate
Rs.

Amount
Rs.

Remarks

Cement - Flyash Concrete Pavement.


Construction reinforced-reinforced, dowel jointed, plain cement
concrete pavement over a prepared sub base with 43 grade cement,
coarse and fine aggregate conforming to IS 383, maximum size of
coarse aggregate not exceeding 25 mm, replacing cement by fly ash
to the extent of 15 per cent and sand by 10 per cent, mixed in a
batching and mixing plant as per approved mix design, transported to
site, laid with a fixed form or slip form paver, spread, compacted and
finished in a continuous operation including provision of contraction,
expansion, construction and longitudinal joints, joint filler, separation
membrane, sealant primer, joint sealant, debonding strip, dowel bar,
tie rod, admixtures as approved, curing compound, finishing to lines
and grades as per drawing. (Suggestive MORTH)

Unit = cum
Taking output = 1050 cum (2415 tonne)
a)

Labour

Mate

day

Mazdoor skilled

day

15.00

Mazdoor (Unskilled)

day

37.00

b)

Machinery

Road Sweeper @ 1250 sqm per hour

hour

2.80

Front end loader 1 cum bucket capacity

hour

18.00

Cement concrete batch mix plant @ 175 cum per hour hour
(effective output)
hour
Electric generator 250 KVA

6.00
6.00

Slip form paver with electronic sensor

hour

6.00

Water tanker6 KL capacity

hour

36.00

Transit truck agitator 5 cum capacity.

tonne 2415xL

Add 10 per cent of cost of carriage to cover cost of loading .km


and unloading

Concrete joint cutting machine .

hour

12.00

Texturing machine .

hour

12.00

Crushed stone coarse aggregates of 25mm and 12.5mm cum


nominal size @ 0.90 cum/cum of concrete conforming to
clause 602.2.4.

945.00

Sand as per IS: 383 and conforming to clause 602.2.4

cum

425.00

Cement 43 grade

tonne

357.00

Fly ash conforming to IS: 3812-1966 (Part-I)

tonne

109.00

32 mm mild steel dowel bars of grade S 240

tonne

9.45

16 mm deformed steel tie bars of grade S 415

tonne

c)

Material

1.17

Separation Membrane of impermeable plastic sheeting 125 sqm


micron thick

3675.00

Pre moulded Joint filler, 25 mm thick for expansion joint ('SILFLEX' sqm
CAPCELL HD -100)
kg
Joint sealant

16.33

Sealant primer

kg

875.00
116.67

Plastic sheath,1.25 mm thick for dowel bars

sqm

46.67

Curing compound

liter

1850.00

Super plastisizer admixture IS marked as per 9103-1999 @ kg


0.5 per cent by weight of cement

2070.00

KL

216.00

Cost of water

419

RBR-CCPV
Index-code

S. No

Description

2
Add 1 per cent of material for cost of miscellaneous materials like
tarpaulin, Hessian cloth, metal cap, cotton / compressible sponge and
cradle for dowel bars, work bridges for men to approach concrete
surface without walking over it, cutting blades and bites, minor
equipments like scabbling machine, threads, ropes, guide wires and
any other unforeseen items.

Unit Quantity
3

Rate
Rs.

Amount
Rs.

Remarks

d&e) Overheads & Contractors Profit


Cost for 1050cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/1050
Note : 1. The quantities for cement, coarse aggregate and fine aggregates are for estimating only. The
exact quantities will be as per mix design.
2. IRC: 68-1976 may be referred for guidelines on the design of cement-fly ash concrete for rigid
pavement construction.
*Calculation of cement, sand and fly ash.
Cement @ 400 kg/cum = 1050 x 400 = 420 tonnes. 15 per cent of cement to be replaced by fly ash
= 63 tonnes. Balance cement = 357 tonnes. Quantity of fly ash = 63 x specific gravity of fly ash
/specific gravity of cement = 63 x 2.25/3.15 = 45 tonnes.
Sand @ 0.45 cum / cum of concrete = 1050 x 0.45 = 472.50 x 1.6 = 756 tonnes.10 per cent to be
replaced by flyash. Balance sand = 756 x 0.9 = 680.4 tonnes = 680.4 / 1.6 = 425 cum. Quantity of
flyash = (756-680.4) x specific gravity of fly ash/specific gravity of sand = 76.4 x 2.25 / 2.687 = 63.97
tonnes (say 64 tonnes)
Fly ash Total fly ash = 45 + 64 = 109 tonnes.

RBR-CCPV-12

12

Rectangular Concrete Block Pavement


Manufacturing, laying of cement concrete blocks of size 0.450 m x
0.300 m x 0.15 m of Cement Concrete (C.C.) M30 grade and
spreading 25 mm thick sand under neath and filling joints with sand
on existing W.B.M. base as per Technical Specification Clause 1503
MORD.

Unit = sqm
Taking output = 112.5 sqm
Concrete M30 grade for block, 400 x (0.450 x 0.300 x 0.150) cum
= 8.10
Concrete M30 for edge block, 2 x 50 x (0.300 x 0.300 x 0.150) = 1.35 cum
cum
cum
TOTAL

a) Labour
Labour for Manufacturing the Cement Concrete Block :
Mate
Mazdoor (Unskilled)
Mason (2nd class)
Bhisti
b) Machinery
Concrete mixer 0.28 / 0.4 cum
Plate vibrator
Water tanker 6 kl capacity
c) Material
For CC Blocks M 30
Coarse aggregates (9.45 x 0.90)
Sand (9.450 x 0.45)
Cement
Sand as per Table 1500.5
Bed = 60*0.025 = 1.5 cum
Joints = 1.5*0.15 = 0.225 cum
Cost of water
d) Formwork @ 3% of (a+b+c)
e&f) Overheads & Contractors Profit
Cost for 112.5 sqm = a+b+c+d+e+f
Rate per sqm = (a+b+c+d+e+f)/112.5

day

day

44.10

day

6.00

day

hour

6.00

hour

12.00

hour

2.00

cum

8.505

cum

4.25

3.80

cum

1.73

kl

6.00

Note : 1. In case curing compound is used in places where there is scarcity of water, the water curing will
be used for 4-days and rate analysis will be amended accordingly
2. Carriage of C.C. block to site of is payable separately as per Chapter of carriage of material from
manufacturing site to the site of work.

420

RBR-CCPV
Index-code

RBR-CCPV-13

S. No

Description

13
i

ii

Unit Quantity
3

Rate
Rs.

Amount
Rs.

Remarks

Interlocking Concrete Block Pavement


Providing and Laying of Interlocking Concrete Block
Pavements using CC M30 having thickness 80 mm as per
drawings and Technical Specification Clause 1504 MORD.
Unit = sqm
Taking output = 225 sqm
a) Labour
Mate
Mazdoor (Unskilled)
Mason (2nd class)
b) Machinery
Water tanker 6 kl capacity
c) Material
(i) Providing inter-locking blocks of approved shape,
thickness and size.
(ii) Edge blocks 60 mx2
(iii) Sand as per Table 1500.5
Bed = 603x75x 0.03 = 6.75 cum
Joints = 60x0.08
= 0.48 cum
(iv) Water for wetting of bedding sand
d&e) Overheads & Contractors Profit
Cost for 225 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/225
Providing and Laying of Interlocking Concrete Block
Pavements using CC M30 having thickness 60 mm as per
drawing and Technical Specification Clause 1504 MORD

day

day

18.00

day

8.00

hour

2.00

sqm

225.00

120.00

cum

7.23

kl

3.00

Unit = sqm
Taking output = 225 sqm
a) Labour
day
Mate
day
Mazdoor (Unskilled)
day
Mason (2nd class)
b) Machinery
hour
Water tanker 6 kl capacity
c) Material
(i) Providing inter-locking blocks of approved shape, sqm
thickness and size.
m
(ii) Edge blocks 60 mx2
cum
(iii) Sand as per Table 1500.5
kl
(iv) Water
d&e) Overheads & Contractors Profit
Cost for 225 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/225
Note : 1. Carriage of interlocking blocks is payable separately as
per Chapter of carriage of material from manufacturing site to the
site of work.
2. Edge blocks may be cast-in-situ. Brick masonry toe wall or CC
block 300 mm x 300 mm x 150 mm or any other shape can also be
used and their cost shall be analysed/included accordingly
3. The rates for sub-grade, sub-base and base course can be
taken from Chapters 3 and 4

15.90
7.00
2.00
225.00
120.00
5.42
3.00

General Note :

The provisions towards Mate is included in the provision towards unskilled Mazdoor

421

RBR-CWSB

Andhra Pradesh Standard Data


I. Roads and Bridges

Chapter - 7
CAUSEWAY AND SUBMERSIBLE BRIDGES
Index-Code

RBR-CWSB-1

S. No

Description

1
i

ii

Unit Quantity
3

Rate
Rs.

Amount
Rs.

Remarks

Construction of Cut-off Walls/Head Walls


Earthwork in excavation for structures as per drawing and
technical specification Clause 305.
cum
Rate as per item No. 1 of Chapter 11
Plain cement concrete M15 grade
cum
Rate as per item No. 4 (A) (iii) / 4 (A) (iv) of Chapter 11

Brick masonry in cement mortar 1:4


Rate as per item No. 5 (ii) of Chapter 11
iv Stone masonry in cement mortar 1:4
Rate as per item No. 6 (ii) of Chapter 11
v Providing P.C.C M20 architectural coping on top of wall
Rate as per item No. 13 of Chapter 12
iii

RBR-CWSB-2

RBR-CWSB-3

RBR-CWSB-4

RBR-CWSB-5

5
6

RBR-CWSB-6

RBR-CWSB-7

RBR-CWSB-8

Note : Rate as appropriate for the type of soil/rock are to be


taken in (i)
Preparation of Subgrade
Rate as per item No. 15 of Chapter 3
Granular Sub-base
Rate as per item No. 1 or 2 of Chapter 4
W.B.M. Base Course
Rate as per item No. 9 of Chapter 4
Cement Concrete Slab
Rate as per item No. 4 of Chapter 6
i Providing and Laying Apron with Stone Boulders as per
Drawings & Technical Specification Clause 1301
Rate as per item No. 1 of Chapter 14
ii Providing and Laying of Boulder Apron Laid in Wire
Crates as per Drawing and Technnical Specification
Clause 1301
Rate as per item No. 2 of Chapter 14
iii Providing and Laying of Apron with Cement Concrete
Blocks as per Drawing and Technical Specification
Clause 1301
Rate as per item No.3 of Chapter 14
Note : Any one of the items appropriate may be taken

Rate as per item No. 8 of Chapter 8


Bedding for Causeway

ii
9

10

RBR-CWSB-10

cum
m

cum
cum
cum
cum

cum

cum

cum

Guide Posts
Construction of R.C.C. guide posts of 250 mm dia, M25
grade as per drawing and technical specification Clause
1401.6

RBR-CWSB-9

cum

cum

Type A (concrete cradle) Bedding Clause 1402.5


cum
As per item No.2 (i) of Chapter 9
Type B (first class) Bedding Clause 1402.5
cum
As per item No.2 (ii) of Chapter 9
Laying Reinforced Cement Concrete Pipe NP3 as per
drawing and technical specification Clause 1402.6
m
As per item No. 3 of Chapter 9
Laying Reinforced Cement Concrete Pipe NP4 as per
technical specification Clause 1402.6
m
As per item No. 4 of Chapter 9

423

RBR-HLRD

Andhra Pradesh Standard Data


I. Roads and Bridges

Chapter - 8
HILL ROADS
Index-code

S. No

Description

RBR-HLRD-1

RBR-HLRD-2

Unit Quantity
3

Rate Amount
Rs.
Rs.
5

Remarks
7

Site Clearance
As per Chapter 2
Setting Out
Unit = 1km
The analysis of rate per km shall account for the following:
(1) Construction of reference pillars (burjee) @ 20 m on both
sides as per Fig. 1600.1 (b) and @ 8.33 m interval on curves

(2) Construction of back pillars in front of each reference


pillar as per Fig. 1600.1 (c )
(3) Construction of job pillars as per Fig. 1600.1 (d)
(1) Construction of reference pillars as per Fig. 1600.1 (b)
as per drawing and Technical Specification Clause 1602.1
(a) Earthwork in excavation for foundation as per drawing
and technical specifications.
cum
Rate as per item No.1 of Chapter 11

1.20

(b) Stone masonry work in cement mortar 1:4 in


foundation complete as per drawing and technical
specifications
cum
Rate as per item No. 6 (I) (ii) or 6 (II) (ii) of Chapter 11

1.20

(c) Plaster with cement mortar 1:4 as per technical


specifications
sqm
Rate as per item No. 3 (A) or (B) or (C) of Chapter 12

4.00

Add 5% of (a+b+c) for white washing, lettering and painting, etc.

Total Cost for each Reference Pillar


(2) Construction of back piller as per Fig. 1600.1( c) as per
drawing and Technical Specification Clause 1602.3

(a) Earthwork in excavation for foundation as per drawing


and technical specifications.
cum
Rate as per item No.1 of Chapter 11
(b) Stone masonry work in cement mortar 1:4 in
foundation complete as per drawing and technical
specifications
cum
Rate as per item No. 6 (I) (ii) or 6 (II) (ii) of Chapter 11
(c) Plaster with cement mortar 1:4 as per technical
specifications
sqm
Rate as per item No. 3 (A) or (B) or (C) of Chapter 12

3.60

3.60

45.00

Add 5% of (a+b+c) for white washing, lettering and painting, etc.

Total Cost for each Reference Pillar


(3) Construction of Job pillers as per Fig. 1600.1 (d) and
Technical Specification Clause 1602.4

(a) Earthwork in excavation for foundation as per drawing


and technical specifications.
cum

0.10

cum

0.10

(c) Plaster with cement mortar 1:4 as per technical


specifications
sqm
Rate as per item No. 3 (A) or (B) or (C) of Chapter 12

0.96

Rate as per item No.1 of Chapter 11


(b) Stone masonry work in cement mortar 1:4 in foundation
complete as per drawing and technical specifications

Rate as per item No. 6 (I) (ii) or 6 (II) (ii) of Chapter 11

Add 5% of (a+b+c) for white washing, lettering and painting, etc.

Total Cost for each Reference Pillar

425

RBR-HLRD
Index-code

S. No
1

RBR-HLRD-3

Description

Unit Quantity

2
3
Note : 1. The dimensions of reference pillars, back pillars and job pillars
are as per figure/site conditions. The above items are covered under
different Chapters of MORD Specifications for payment.
2. The marking of centre line, setting out, curves, recording of levels,
etc. by the surveyor will be incidental to work and no extra payment shall
be made for the same.

3
i
A

ii
A

Earthwork in Hill Road


Excavation in Hilly Areas in Soil by manual means.
Excavation in soil in Hilly Area by manual means
including cutting and trimming of side slopes and
disposing of excavated earth with a lift upto 1.5 m and
a lead upto 20 m as per drawing and Technical
Specification Clause 1603.1
Unit = cum
Taking output = 120 cum
a) Labour
Mate
Mazdoor (Unskilled)
b&c) Overheads & Contractors Profit
Cost for 120 cum = (a+b+c)
Rate per cum = (a+b+c)/120
Extra for Every Additional Lift of 1.5 m or Part thereof
Excavation in Soil
Unit = cum
Taking output = 10 cum
a) Labour
Mazdoor (Unskilled)
b&c) Overheads & Contractors Profit
Cost for 10 cum = (a+b+c)
Rate per cum = (a+b+c)/10
Excavation in Hilly Areas in Soil by mechanical means
Excavation in soil in Hilly Area by mechanical means
including cutting and trimming of side slopes and
disposing of excavated earth with a lift upto 1.5 m and
a lead upto 20 m as per Technical Specification Clause
1603.1
Unit = cum
Taking output = 260 cum
a) Labour
Mate
Mazdoor (Unskilled) for trimming slopes and helping in
excavation, etc.
b) Machinery
Dozer D-50 @ 43.28 cum per hour
Front end loader
c&d) Overheads & Contractors Profit
Cost for 260 cum = a+b+c+d
Rate per cum = (a+b+c+d)/260
Extra for Every Additional Lift of 1.5 m or Part thereof
Excavation in Soil
Unit = cum
Taking output = 10 cum
a) Labour
Mazdoor (Unskilled)
b&c) Overheads & Contractors Profit
Cost for 10 cum = (a+b+c)
Rate per cum = (a+b+c)/10

Rate Amount
Rs.
Rs.
5

Remarks
7

day
day

62.40

day

0.55

day
day

20.80

hour

6.00

hour

6.00

day

0.55

Note : 1. In case the land on the valley side is barren and there is no
objection for disposing of excavated earth on the valley side, the
provision of front end loader and tipper shall be deleted as excavated
earth shall be disposed off on the valley side.

2. For disposal of excavated surplus earth beyond 20 m, the relevant


items of carriage be followed
3. In case, alternative machine like hydraulic excavator 0.9 cum bucket
capacity is necessitude because of site conditions, the same can be
used.
Excavation in soil in hilly area by mechanical means
including cutting and trimming of side slopes and disposing
of excavated earth with all lifts and lead upto 1000 metres as
per Tech Specification 301 MORTH

426

RBR-HLRD
Index-code

S. No

Description

Unit Quantity
3

Unit = cum
Taking output = 260 cum
a) Labour
day
Mate
Mazdoor (Unskilled) for trimming slopes and helping in day
excavation
etc.
b)
Machinery
Dozer 80 HP (D-80 A 12)@ 43.28 cum per hour
Front end loader
Tipper 5.5cum capacity, 4 trips per hour.
c&d) Overheads & Contractors Profit
Cost for 260 cum = a+b+c+d
Rate per cum = (a+b+c+d)/260

hour

Rate Amount
Rs.
Rs.
5

Remarks
7

6.24
6.00

hour

6.00

hour

12.00

Note : In case the land on the valley side is barren and there is no
objection for disposing of excavated earth on the valley side, the
provision of front end loader and tipper shall be deleted as excavated
earth shall be disposed off on the valley side.
iii

Excavation in Hilly Area in Ordinary Rock by manual


means

Excavation in ordinary rock using manual means including


loading in a truck and carrying of excavated material to
embankment site with a lift upto 1.5 m and lead upto 20 m as
per Clause 1603.2.

Unit = cum
Taking output = 120 cum
a) Labour
Mate
Mazdoor (Unskilled)
b&c) Overheads & Contractors Profit
Cost for 120 cum = (a+b+c)
Rate per cum = (a+b+c)/120
Extra for Every Additional Lift of 1.5 m or Part thereof
For Ordinary Rock
Unit = cum
Taking output = 10 cum
a) Labour
Mazdoor (Unskilled)
b&c) Overheads & Contractors Profit
Cost for 10 cum = (a+b+c)
Rate per cum = (a+b+c)/10

day

5.28

day

132.00

day

0.86

427

RBR-HLRD
Index-code

S. No

Description

2
iv
A

Unit Quantity
3

Rate Amount
Rs.
Rs.
5

Remarks
7

Excavation in Hilly Areas in Ordinary Rock by


mechanical means not requiring blasting
Excavation in hilly area in ordinary rock not requiring
blasting by mechanical means including cutting and
trimming of slopes and disposal of cut material with a lift
upto 1.5 m and lead upto 20 m as per Clause 1603.2.
Unit = cum
Taking output = 170 cum
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor for disposing of earth upto 20 m
b) Machinery
Dozer D-50 @ 28.32 cum per hour
Hydraulic Excavator 0.9 cum bucket capacity @ 40 cum
per hour
c&d) Overheads & Contractors Profit
Cost for 170 cum = a+b+c+d
Rate per cum = (a+b+c+d)/170

day
day

17.68

day

9.00

hour

6.00

hour

4.25

Note : 1. In case the land on the valley side is barren and there is no
objection for disposing of excavated earth on the valley side, the
provision of front end loader and tipper shall be deleted as excavated
earth shall be disposed off on the valley side.
2. In case, alternative machine like hydraulic excavator 0.9 cum bucket
capacity is necessitude because of site conditions, the same can be
used.
B

Excavation in hilly area in ordinary rock not requiring


blasting by mechanical means including cutting and
trimming of slopes and disposal of cut material with all
lift and lead upto 1000 metres as per Tech
Specification 301 MORTH.
Unit = cum
Taking output = 170 cum
a) Labour
day
Mate
day
Mazdoor (Unskilled)
b)
Machinery
Dozer 80 HP (D-80 A 12)@ 28.32 cum per hour
Front end loader
Tipper 5.5cum capacity, 4 trips per hour.

8.32

hour

6.00

hour

7.00

hour

7.00

c&d) Overheads & Contractors Profit


Cost for 170 cum = a+b+c+d
Rate per cum = (a+b+c+d)/170
Note : In case the land on the valley side is barren and there is no
objection for disposing of excavated earth on the valley side, the
provision of front end loader and tipper shall be deleted as excavated
earth can be disposed off on the valley side.
v
A

Excavation in Hilly Areas in Hard Rock requiring


blasting
Excavation in hilly areas in hard rock requiring
blasting, by mechanical means, lift upto 1.5 m and
disposal of excavated rock upto a lead of 20 m as per
Clause 1603.2.
Unit = cum
Taking output = 170 cum
a) Labour
day
Mate
day
Mazdoor (Unskilled)

23.36

428

RBR-HLRD
Index-code

S. No

Description

Unit Quantity
3
day

4
2.00

Driller
Blaster
b) Machinery
Dozer D-50 @ 56.67 cum per hour (blasted rock)

day

10.00

hour

3.00

Hydraulic Excavator 0.9 cum bucket capacity @ 34 cum/hour

hour

5.00

Air compressor 210 cfm with two jack hammer @ 6 cum/ hour

hour

28.00

c) Material
Gelatin 80 per cent
Electric detonators @ 1 detonator for 1 Gelatin stick of 285
gm each
d&e) Overheads & Contractors Profit
Cost for 170 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/170
Extra for Every Additional Lift of 1.5 m or Part thereof
For Hard Rock
Unit = cum
Taking output = 10 cum
a) Labour
Mazdoor (Unskilled)
b&c) Overheads & Contractors Profit
Cost for 10 cum = (a+b+c)
Rate per cum = (a+b+c)/10
Excavation in hilly areas in hard rock requiring
blasting, by mechanical means including trimming of
slopes and disposal of cut material with all lifts and
lead upto 1000 metres as per Tech Specification 301
MORTH
Unit = cum
Taking output = 170 cum
a) Labour
Mate
Mazdoor (Unskilled)
Driller
Blaster
b)
Machinery
Dozer 80 HP (D-80 A 12)@ 28.32 cum per hour

kg

67.00

nos

235.00

day

1.08

day

day

10.49

day

2.00

day

0.25

hour

6.00

Air compressor 250 cfm with two jack hammer @ 20 cum per hour
hour
hour
Front end loader

5.00

hour

7.00

Tipper 5.5cum capacity, 4 trips per hour.


c)
Materials
Gelatin 80 per cent

kg

Electric Detonators @ 1 Detonator for 2 Gelatin sticks of 125 gms each


each

Rate Amount
Rs.
Rs.
5

Remarks
7

7.00

35.00
140.00

d&e) Overheads & Contractors Profit


Cost for 170 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/170
Note : 1. In case the land on the valley side is barren and there is no
objection for disposing of excavated earth on the valley side, the
provision of front end loader and tipper shall be deleted as excavated
earth shall be disposed off on the valley side.
2. In case of hill roads, the altitude effect comes into play. The output of
men and machines decreases progressively after 2100 m elevation
leading to increase in cost. High altitude effect has been explained in the
basic approach.
3. The arrangement for igniting the detonator is covered under
overheads

429

RBR-HLRD
Index-code

RBR-HLRD-4

S. No

Description

Retaining Walls / Breast Walls


Construction of retaining walls/breast walls in cement
mortar 1:5 as per drawing and technical specifications
Clause 1604
(i) Earthwork in excavation for structures
Rate as per item No. 1 of Chapter 11
(ii) Plain cement concrete M 10 grade
Rate as per item No. 4 (A) (i) or (ii) of Chapter 11
(iii) Stone masonry in cement mortar 1:5
Rate as per item No. 4 (I) (iii) or 4 (II) (iii) of Chapter 12
(iv) Pointing with cement mortar 1:3
Rate as per item No 2 of Chapter 12
(v) Providing P.C.C. M 20 architectural coping on top of
retaining wall/breast wall
Rate as per item No. 13 of Chapter 12
(vi) Filter material behind retaining wall / breast wall as
per Specification 1204.3.8 in a width of 600 m
Rate as per item No. 11 of Chapter 12
(vii) Back filling behind retaining wall/breast wall
Rate as per item No. 10 of Chapter 12

Unit Quantity
3

Rate Amount
Rs.
Rs.
5

Remarks
7

cum
cum
cum
sqm

cum
cum

Note : 1. Quantities of material/work shall be as per design and


drawings
2. Earth work in excavation may be taken as per site conditions.
It may comprise of a number of sub-items depending upon the
type of soil/rock encountered.

RBR-HLRD-5

Construction of Hill Side Drain


Construction of hill side drain in accordance with the
requirement of specifications true to lines and grades.
Dimensions and other particulars as per drawing and
Technical Specification Clause 1606.1
Unit = 1 m
(i) Earthwork in excavation for structures as per
drawing and technical specification
cum
Rate as per item No. 1 of Chapter 11
(ii) Plain cement concrete M10 grade
cum
Rate as per item No. 4 (A) (i) or (ii) of Chapter 11
(iii) Stone masonry in cement mortar 1:5
cum
Rate as per item No. 4 (I) (iii) or 4 (II) (iii) of Chapter 12
(iv) Plain cement concrete M15 grade
Rate as per item No. 4 (A) (iii) or (iv) of Chapter 11
(v) Cement plaster 15 mm thick 1:4 on stone masonry

cum

cum
Rate as per item No. 3 (A) or (B) or (C) of Chapter 12
(vi) Providing P.C.C. M20 architectural coping on top of
wall
m
Rate as per item No. 13 of Chapter 12
Rate per m length (i+ii+iii+iv+v+vi)
Note : 1. Quantities of material/work shall be as per design
and drawings
2. Earth work in excavation may be taken as per site
conditions. It may comprise of a number of sub-items
depending upon the type of soil/rock encountered.

430

RBR-HLRD
Index-code

RBR-HLRD-6

S. No

Description

Unit Quantity
3

Rate Amount
Rs.
Rs.
5

Remarks
7

Construction of Catch Water / Intercepting Drain


Construction of catch water/intercepting drain in random
rubble masonry in 1:5 cement mortar true to the specified
lines grades levels and dimensions as per the requirement
of the specifications Clause 1606.2
Unit = 1 m
(i) Earthwork in excavation for structures as per
drawing and technical specification
Rate as per item No. 1 of Chapter 11
(ii) Plain cement concrete M10 grade
Rate as per item No. 4 (A) (i) or (ii) of Chapter 11
(iii) Stone masonry in cement mortar 1:5
Rate as per item No. 4 (I) (iii) or 4 (II) (iii) of Chapter 12
(iv) Plain cement concrete M15 grade
Rate as per item No. 4 (A) (iii) or (iv) of Chapter 11
(v) Cement plaster 15 mm thick 1:4 on stone masonry

cum
cum
cum
cum

cum
Rate as per item No. 3 (A) or (B) or (C) of Chapter 12
(vi) Providing P.C.C. M20 architectural coping on top of
wall
m
Rate as per item No. 13 of Chapter 12
Rate per m length (i+ii+iii+iv+v+vi)
Note : 1. Quantities of material/work shall be as per design
and drawings
2. Earth work in excavation may be taken as per site
conditions. It may comprise of a number of sub-items
depending upon the type of soil/rock encountered.

RBR-HLRD-7

Construction of Scupper
Construction of scupper with dry stone masonry as per
drawing and technical specifications as per Clause 1606.5.

Unit = 1 m
Taking output = 6 m
Earthwork in excavation for structures as per drawing
and technical specifications
Quantity for 6 m formation width of hill side rock cutting and
foundation as per plate No. 7.27 of Rural Road Manual

ii

Rate as per item No. 1 of Chapter 11


Rate per m = a/6
Random rubble dry stone masonry
Quantity for 6 m formation width = 38 cum
a) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
b) Material
Stone for RR masonry
Bond stone
c&d) Overheads & Contractors Profit
Cost for 6 m = a+b+c+d
Rate per m = (a+b+c+d)/6

cum

115.00

day

day

38.00

day

60.80

cum
nos

35.72
6.08

431

RBR-HLRD
Index-code

S. No

Description

2
iii

iv

ii

iii

iv

RBR-HLRD-9

day

day

6.00

day

12.72

nos

1335.00

day

day

3.12

cum

12.00

Rate Amount
Rs.
Rs.
5

Remarks
7

Construction of RCC guide posts of 250 mm dia M 20 grade


cast-in-situ with 20 mm nominal size aggregate, true to line
and grade, tolerance of vertical RCC posts not to exceed 1 in
500 as per drawing and Technical Specification Clause
1608.2

RBR-HLRD-8

Random course rubble dry stone masonry in


corbelling
Quantity for 6 m formation width = 9 cum
a) Labour
Mate
Mason (2nd class)
Mazdoor (Unskilled)
b) Material
Corbelling Stones size 300 mm x 150 mm x 150 mm
including wastage
c&d) Overheads & Contractors Profit
Cost for 6 m = a+b+c+d
Rate per m = (a+b+c+d)/6
Stone filling in foundation trenches as per drawing and
technical specification
Quantity for 6 m formation width = 10 cum
a) Labour
Mate
Mazdoor (Unskilled)
b) Material
Loose stone
c&d) Overheads & Contractors Profit
Cost for 6 m = a+b+c+d
Rate per m = (a+b+c+d)/6
Rate per m length= (i + ii + iii + iv)
Note : 1. Quantities of parapet are not included in the
quantities of scupper.
2. The above analysis is based on plate No.7.27 of Rural
Roads Manual.
3. Rates for earth work are to be taken appropriate to the
type of soil/rock

Unit Quantity

Earth work in excavation for structures


Unit = cum
Rates as per item No. 1 of Chapter 11
RCC M20 grade
Unit = cum
Rate as per item No. 4 (C) (i) of Chapter 11
HYSD steel bars
Unit = t
Rate as per item No. 7 of Chapter 11
Painting two coats including prime coat on new
concrete surface
Unit = sqm
Rate as per item No. 5 of Chapter 10
Note : Quantities are to be taken as per drawing
Providing edge stones on valley side of formation as
per drawing and Technical Specification Clause
1608.2.6
Unit = 1 m
Taking Output = 45 m (100 no of edge stones of size 450
mm x 300 mm x 100 mm)
a) Labour
Mate
Mazdoor (Unskilled)

cum

cum

sqm

day

day

3.18

432

RBR-HLRD
Index-code

RBR-HLRD-10

S. No

Description

10

Unit Quantity
3
day

Mason (2nd class)


b) Material
nos
Stones of size 450 mmx300 mmx100 mm
c) Painting two coats including priming coat on new
concrete/stone surfaces
45 x 0.500 = 22.50
sqm
Rate as per item No. 5 of Chapter 10
d&e) Overheads & Contractors Profit
Cost for 45 m = a+b+c+d+e
Rate per m = (a+b+c+d+e)/45
Turfing with Sods

4
1.50

Rate Amount
Rs.
Rs.
5

Remarks
7

100.00

22.50

Furnishing and laying of the live sods of perennial turf forming


grass on embankment slope, verges or other locations shown on
the drawing or as directed by the Engineer including preparation
of ground, stacking the sods and watering as per Clause 309

Unit = sqm
Taking output = 100 sqm
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Water tanker including watering for 3 months
Tractor with Trolley
c) Material
Farmyard manure @ 0.18 cum per 100 sqm at site of work

RBR-HLRD-11

11

Water
d&e) Overheads & Contractors Profit
Cost for 100 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/100
Seeding and Mulching
Preparation of seed bed on previously laid top soil,
furnishing and placing of seeds, fertilizer, multching
material, applying bituminous emulsion at the rate of 0.23 l
per sqm and laying and fixing jute netting, including
watering for 3 months as per clause 310 & 1600 MORD.

day

day

4.16

hour

4.00

hour

1.00

cum

0.18

kl

24.00

Unit = sqm
Taking output = 240 sqm
a) Labour
day
Mate
day
Mazdoor (Unskilled)
b) Machinery
Water tanker 6 kl capacity including watering for 3 months hour
(for one hour per week)
Tractor with Trolley
c) Material
Seeds
Sludge / Farm yard manure @ 0.18 cum per 100 sqm
Bitumen Emulsion
Jute netting, open weave, 25 mm square opening
Water for 3 months
d&e) Overheads & Contractors Profit
Cost for 240 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/240

15.60
13.00

hour

2.40

kg

3.60

cum
t

0.43
0.06

sqm

264.00

kl

84.00

General Note :
The provisions towards Mate is included in the provision towards unskilled Mazdoor.

433

RBR-PCVT

Andhra Pradesh Standard Data


I. Roads and Bridges

Chapter - 9
PIPE CULVERTS
Index-code

RBR-PCVT-1

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

9.1 Excavation for Structures

Earthwork in excavation for foundation of structures upto 3


m depth as per drawing and technical specification Clause
300 / 1104 MORD including setting out, construction of
shoring and bracing, removal of stumps and other
deleterious matter, dressing of sides and bottom and
backfilling with approved material.
Unit = cum
Rate as per item No. 1 of Chapter 11
Rate as applicable for the type of soil/rock are to be taken

RBR-PCVT-2

RBR-PCVT-3

Bedding for Pipe


(i) Type A (Concrete Cradle) Bedding
Laying concrete cradle bedding with M15 Grade Cement
Concrete as per Clause 1105 (i)
Unit = cum
cum
Rate as per Item No. 4 (A) (iii) or (iv) of Chapter 11
(ii) Type B (First Class) Bedding
Laying (First Class) bedding on well compacted sand,
moorum or approved granular material as per Clause 1105
(ii)
Unit = cum
cum
Rate as per Item No. 2 of Chapter 11
Providing and Laying Reinforced Cement Concrete
Pipe NP3 as per design.

1.00

1.00

Providing and laying reinforced cement concrete pipe NP3 for


culverts on first class bedding of granular material including fixing
collar with cement mortar 1:2 but excluding excavation, protection
works, backfilling, concrete and masonry works in head wall and
parapets. Tech Specification Clause 1106 MORD.

Unit = m
Taking output = 7.5 m
(3 pipes of 2.5 m length each)
A 1200 mm dia
a) Labour
day
Mate
day
Mason (1st Class)
day
Mazdoor (Unskilled)
Laying & fixing of Pipes with colors in position including rm
lifting, aligning etc.,
b) Material
cum
Sand at site
t
Cement at site
m
RCC pipe NP3 pipe including collar at site
Handling loading and unloading on (b)
c&d) Overheads & Contractors Profit
Cost for 7.5 m = a+b+c+d
Rate per m = (a+b+c+d)/7.5

0.50
3.14

0.05
0.07
7.50

435

RBR-PCVT
Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

RBR-PCVT-4

1000 mm dia
a) Labour
day
Mate
day
Mason (1st Class)
day
Mazdoor (Unskilled)
Laying & fixing of Pipes with colors in position including rm
lifting, aligning etc.,
b) Material
cum
Sand at site
t
Cement at site
m
RCC pipe NP3 pipe including collar at site
c&d) Overheads & Contractors Profit
Cost for 7.5 m = a+b+c+d
Rate per m = (a+b+c+d)/7.5
750 mm dia
a) Labour
day
Mate
day
Mason (1st Class)
day
Mazdoor (Unskilled)
Laying & fixing of Pipes with colors in position including rm
lifting, aligning etc.,
b) Material
cum
Sand at site
t
Cement at site
m
RCC pipe NP3 pipe including collar at site
c&d) Overheads & Contractors Profit
Cost for 7.5 m = a+b+c+d
Rate per m = (a+b+c+d)/7.5
Note : The labour rate for 600 mm dia Hume pipe may be
derived from the rates for 750 dia by decreasing 20 per cent
Providing and Laying Reinforced Cement Concrete
Pipe NP4 as per design.
Providing and laying reinforced cement concrete pipe NP4
for culverts on first class bedding of granular material
including fixing collar with cement mortar 1:2 but
excluding excavation, protection works, backfilling,
concrete and masonry works in head walls and parapets
as per Clause 1106 MORD / 2900 MORTH
Unit = m
Taking output = 7.5 m
(3 pipes of 2.5 m length each)
(A) 1200 mm dia
a) Labour
day
Mate
day
Mason (1st Class)
day
Mazdoor (Unskilled)
b) Material
cum
Sand at site
t
Cement at site
m
RCC pipe NP4 pipe including collar at site
cum
Granular material passing 5.6 mm sieve for bedding
c&d) Overheads & Contractors Profit
Cost for 7.5 m = a+b+c+d
Rate per m = (a+b+c+d)/7.5

0.25
2.09

0.04
0.03
7.50

0.15
1.25

0.024
0.018
7.50

0.50
3.14
0.05
0.07
7.50
5.00

436

RBR-PCVT
Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

(B) 1000 mm dia


a) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
b) Material
Sand at site
Cement at site
RCC pipe NP4 pipe including collar at site
Granular material passing 5.6 mm sieve for bedding
c&d) Overheads & Contractors Profit
Cost for 7.5 m = a+b+c+d
Rate per m = (a+b+c+d)/7.5

day

day

0.25

day

2.09

cum

0.04

0.03

7.50

cum

4.50

Note : 1. In case of cement cradle bedding, quantity of PCC M15 is to be calculated as per design and
priced separately and added .
2. The rate analysis does not include excavation, cement /masonry works in head walls, backfilling,
protection works and parapet walls. The same are to be calculated as per approved design and drawings
and priced separately on rates available under respective sections.

(C) 750 mm dia


a) Labour
day
Mate
day
Mason (1st Class)
day
Mazdoor (Unskilled)
b) Material
cum
Sand at site
t
Cement at site
m
RCC pipe NP4 pipe including collar at site
c&d) Overheads & Contractors Profit
Cost for 7.5 m = a+b+c+d
Rate per m = (a+b+c+d)/7.5
Note : The labour rate for 600 mm dia Hume pipe may be derived
by decreasing 20 per cent
5

RBR-PCVT-5

Laying Cement Concrete Pipe NP3 on first class


bedding of granular material including fixing collar
with cement sand mortar 1:2 but excluding excavation,
protection works, backfilling, concrete and masonry
work in head wall and parapet as per Tech
Specification No. 1100 MORTH
Unit = m
Taking output = 7.5 m
(3 pipes of 2.5 m length each)
500 mm dia
a) Labour
day
Mate
day
Mason (1st Class)
day
Mazdoor (Unskilled)
b) Material
cum
Sand at site
t
Cement at site
m
RCC pipe NP3 concrete pipe including collar at site
c&d) Overheads & Contractors Profit
Cost for 7.5 m = a+b+c+d
Rate per m = (a+b+c+d)/7.5
Note : The labour rate for 300 mm dia shall be decreased by 20%

0.15
1.25
0.024
0.018
7.50

from the rates for 750 dia

0.30
2.51
0.04
0.036
15.00

437

RBR-PCVT
Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

RBR-PCVT-6

RBR-PCVT-7

RBR-PCVT-8

Laying Cement Concrete Pipe NP4 on first class


bedding of granular material including fixing collar
with cement sand mortar 1:2 but excluding excavation,
protection works, backfilling, concrete and masonry
work in head wall and parapet as per Tech
Specification No. 1100 MORTH
Unit = m
Taking output = 7.5 m
(3 pipes of 2.5 m length each)
500 mm dia
a) Labour
day
Mate
day
Mason (1st Class)
day
Mazdoor (Unskilled)
b) Material
cum
Sand at site
t
Cement at site
m
RCC pipe NP4 concrete pipe including collar at site
c&d) Overheads & Contractors Profit
Cost for 7.5 m = a+b+c+d
Rate per m = (a+b+c+d)/7.5
Note : The labour rate for 300 mm dia shall be decreased by 20%
Plain Cement Concrete M10 (1:3:6 nominal mix) in
leveling course below open foundation of Head walls
as per drawings & Technical Specification Clause 1109

RBR-PCVT-9

0.02
0.01
7.50

cum
cum

Stone Masonry Work in cement mortar in foundation of


Head walls complete as per drawing and technical
specification Clause 1109
A. In 1:4 cement mortar
cum
Rate as per item No. 6 (I) (ii) or (II) (ii) Chapter 11
B. In cement-lime mortar (1:0.5:4.5)
Rate as per item No. 6 (I) (iii) or (II) (iii) Chapter 11

RBR-PCVT-10

0.94

cum
Rate as per item No. 4 (A) (i) or (ii) of Chapter 11
Brick Masonry Work in cement mortar in foundation of
Head walls complete excluding pointing and plastering
as per drawing and technical specification Clause 1109

A. Brick Masonry in 1:4 cement mortar


Rate as per item No. 5 (ii) Chapter 11
B. Brick Masonry in cement-lime mortar (1:0.5:4.5)
Rate as per item No. 5 (iii) Chapter 11
9

0.11

cum

10

Pointing with Cement Mortar (1:3) on brickwork as per


technical specification Clause 613.3
10
Rate as per item No. 2 of Chapter 12

11

Plastering with Cement Mortar (1:4), 15 mm thick on


brickwork
in
substructure
as
per
technical
specification
10
Rate as per item No. 3 (A) of Chapter 12

12

Backfilling in Foundation Trenches as per drawing and


technical specification Clause 1108
cum
Rate as per Item No. 2 of Chapter 11

13

Providing PCC M20 Architectural Coping on the top of


wing wall, return wall etc. complete as per drawing and
technical specification Clause 615

sqm

RBR-PCVT-11

sqm

RBR-PCVT-12

RBR-PCVT-13

Rate as per Item No. 13 of Chapter 12

General Note :
The provisions towards Mate is included in the provision towards unskilled Mazdoor.

438

RBR-TSRA

Andhra Pradesh Standard Data


I. Roads and Bridges

Chapter - 10
TRAFFIC SIGNS, MARKINGS AND OTHER ROAD APPURTENANCES
Index-code

S. No
1

RBR-TSRA-1

Description

Unit

Quantity

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

Printing New Letters and Figures of any Shade


Printing new letter and figures of any shade with synthetic
enamel paint black or any other approved colour to give an
even shade as per drawings and Technical Specification
Clause 1701 MORD / 801 MORTH
(i) Hindi (Matras commas and the like not to be measured

and paid for. Half letters shall be counted as half only)


Details for 100 letters of 160 mm height, i.e., 1600 cm
Unit = per cm height per letter
a)Labour
Mate
Painter 1st Class
Painter Assistant
Mazdoor (Unskilled)
b) Material
Paint
c&d) Overheads & Contractors Profit
Cost for 1600 cm = a+b+c+d
Rate per cm height per letter = (a+b+c+d)/1600
(ii) English and Roman

day

day

2.00

day
day

1.12

litre

0.70

day
day
day
day

1.25

litre

0.50

cum

0.126

cum

0.126

Hyphens, commas and the like not to be measured and paid for.

Detail for 100 letters of 160 mm height, i.e. 1600 cm


Unit = per cm height per letter
a)Labour
Mate
Painter 1st Class
Painter Assistant
Mazdoor (Unskilled)
b) Material
Paint
c&d) Overheads & Contractors Profit
Cost for 1600 cm = a+b+c+d
Rate per cm height per letter = (a+b+c+d)/1600
RBR-TSRA-2

0.57

Traffic Signs
A Retro-reflectorised Traffic Signs
i

Providing and fixing of retro-reflectorised cautionary,


mandatory and informatory sign as per IRC:67 made of
encapsulated lens type reflective sheeting vide Clause 1701.2.3
MORD / 801.3 MORTH fixed over aluminum sheeting, 1.5 mm
thick supported on a mild steel angle iron pron post 75 mm x 75
mm x 6 mm firmly fixed to the ground by means of properly
designed foundation with M15 grade cement concrete 450 mm x
450 mm x 600 mm, 600 mm below ground level as per drawings
and Technical Specification Clause 801 MORTH / 1701 MORD.

Unit = each
Taking output = one traffic sign
(i) Excavation for foundation
As per item No. 1 of Chapter 11
(ii) Cement concrete M15 grade
As per item No. 4 (A) (iii) or (iv) of Chapter 11

441

RBR-TSRA
Index-code

S. No
1

Description

Unit

Quantity

sqm
sqm

0.887
0.43

day
day

0.26

kg

19.00

sqm

0.35

sqm

0.156

sqm

0.283

sqm

0.48

sqm

0.27

sqm

0.36

sqm

0.672

hour

0.01

cum

0.126

cum

0.126

day
day

0.26

3.00

(iii) Painting Angle Iron Post with Primer and two coats
of Epoxy Paint as per specifications
As per item No. 9 of this Chapter (or)
Painting Angle Iron Post with Primer and two coats item
6 of this chapter
(a) labour (For fixing at site)
Mate
Mazdoor (Unskilled)
b) Material
Mild steel angle iron 75 x 75 x 6 mm
Add 3 per cent of cost of angle iron towards cost of
fabrication, drilling holes, nuts, bolts etc.
Aluminum sheeting fixed with encapsulated lens type
reflective sheeting of size including lettering and signs as
applicable background with epoxy paint
(i) 900 mm equilateral triangle
OR
(ii) 600 mm equilateral triangle
OR
(iii) 600 mm circular
OR
(iv) 800 mm x 600 mm rectangular
OR
(v) 600 mm x 450 mm rectangular
OR
(vi) 600 mm x 600 mm square
OR
(vii) 900 mm side octagon
(c) Machinery
Tractor with trolley
d&e) Overheads & Contractors Profit
Rate per traffic sign = (i+ii+iii+a+b+c+d+e) (with Epoxy
Paint)
Rate per traffic sign = (i+ii+iii+a+b+c+d+e) (with Enamel
Paint)
ii

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

Providing and fixing of retro-reflectorised cautionary,


mandatory and informatory sign as per IRC:67 made of
encapsulated lens type reflective sheeting vide Clause 1701.2.3,
fixed over aluminum sheeting, 1.5 mm thick supported on GI
pipe 50 mm dia firmly fixed to the ground by means of properly
designed foundation with M15 grade cement concrete 450 mm x
450 mm x 600 mm, 600 mm below ground level as per drawings
and Technical Specification Clause 1701 MORD

Unit = each
Taking output = one traffic sign
(i) Excavation for foundation
As per item No. 1 of Chapter 11
(ii) Cement concrete M15 grade
As per item No. 4 (A) (iii) or (iv) of Chapter 11
(a) labour (For fixing at site)
Mate
Mazdoor (Unskilled)
b) Material
50 mm dia GI Pipe 2.85 m long including 5% wastage
Add 3 per cent of cost of GI Pipe towards cost of fabrication,
drilling holes, nuts, bolts etc.
Aluminum sheeting fixed with encapsulated lens type reflective
sheeting of size including lettering and signs as applicable
background with epoxy paint

442

RBR-TSRA
Index-code

S. No
1

Description

Unit

Quantity

3
sqm

4
0.35

sqm

0.156

sqm

0.283

sqm

0.48

sqm

0.27

sqm

0.36

sqm

0.672

hour

0.08

cum

0.126

cum

0.126

(i) 900 mm equilateral triangle


OR
(ii) 600 mm equilateral triangle
OR
(iii) 600 mm circular
OR
(iv) 800 mm x 600 mm rectangular
OR
(v) 600 mm x 450 mm rectangular
OR
(vi) 600 mm x 600 mm square
OR
(vii) 900 mm side octagon
(c) Machinery
Tractor with trolley
d&e) Overheads & Contractors Profit
Rate per traffic sign = (i+ii+iii+a+b+c+d+e)

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

iii Providing and fixing of retro-reflectorised cautionary,


mandatory and informatory sign as per IRC:67 made of
encapsulated lens type reflective sheeting vide Clause 1701.2.3,
fixed over aluminum sheeting, 1.5 mm thick supported on RCC
Post 100 mm x 100 mm firmly fixed to the ground by means of
properly designed foundation with M15 grade cement concrete
450 mm x 450 mm x 600 mm, 600 mm below ground level as per
drawing and Technical Specification Clause 1701 MORD.

Unit = each
Taking output = one traffic sign
(i) Excavation for foundation
As per item No. 1 of Chapter 11
(ii) Cement concrete M15 grade
As per item No. 4 (A) (iii) or (iv) of Chapter 11
(iii) Painting two coats including prime coat on concrete surface
with Epoxy Paint as per specifications

As per item No. 9 of this Chapter


(a) labour (For fixing at site)
Mate
Mazdoor
b) Material
RCC M15 Grade in Sub-structure
As per item No. 5 (i) or (ii) of Chapter 12
Steel reinforcement HYSD bars
As per item No. 6 of Chapter 12
Add 3 per cent of cost of RCC Post towards cost of drilling
holes, nuts, bolts, etc.
Aluminum sheeting fixed with encapsulated lens type
reflective sheeting of size including lettering and signs as
applicable background with epoxy paint
(i) 900 mm equilateral triangle
OR
(ii) 600 mm equilateral triangle
OR
(iii) 600 mm circular
OR
(iv) 800 mm x 600 mm rectangular
OR
(v) 600 mm x 450 mm rectangular
OR
(vi) 600 mm x 600 mm square
OR
(vii) 900 mm side octagon
(c) Machinery
Tractor with trolley
d&e) Overheads & Contractors Profit
Rate per traffic sign = (i+ii+iii+a+b+c+d+e)

0.90
day
day

0.26

cum

0.0285

0.0077

sqm

0.35

sqm

0.156

sqm

0.283

sqm

0.48

sqm

0.27

sqm

0.36

sqm

0.672

hour

0.08

443

RBR-TSRA
Index-code

S. No
1

Rate Amount
Rs.
Rs.
2
3
4
5
6
Note : 1. Any one area of aluminum sheeting given at (i) to (vii) may be adopted as per site requirement
and in accordance with IRC:67.
Description

Unit

Quantity

Remarks
7

2. The rate for excavation, cement concrete M-15, RCC M-15 in Sub-structure, steel re-enforcement
and painting may be taken from respective Chapters.
3. The depth of foundation and quantity of cement concrete in the foundation are indicative. These
may be increased for areas having higher wind velocities like in coastal areas. This is applicable to
all road signs and directions boards.
B Semi Reflective Traffic Signs

Providing and fixing of semi reflective cautionary, mandatory


and informatory sign board as per IRC:67 made of 1.5 mm
thick MS Sheet duly stove white colour in front and gray
colour on back with red reflective border of 65 mm width
and required letters and figures with reflective tape
engineering grade as per Clause 1701.3.9 of MORD for
Rural Roads of required shade and colour supported and
welded on 47 mm x 47 mm 12 SWG sheet tube firmly fixed
to the ground by means of properly designed foundation
with M15 grade cement concrete 450 mm x 450 mm x 600
mm, 600 mm below ground level as per drawings and
Technical Specification Clause 1701 MORD
Unit = Each
Taking output = one traffic sign
(i) Excavation for foundation
As per item No. 1 of Chapter 11
(ii) Cement concrete M15 grade
As per item No. 4 (A) (iii) or (iv) of Chapter 11

cum

0.126

cum

0.126

sqm

0.46

day
day

0.26

kg
kg

12.40
1.06

sqm

0.35

sqm

0.156

sqm

0.283

sqm

0.48

sqm

0.27

sqm

0.36

sqm

0.672

hour

0.08

(iii) Painting two coats including prime coat on concrete surface


with Epoxy Paint as per specifications

As per item No. 9 of this Chapter


(a) labour (For fixing at site)
Mate
Mazdoor (Unskilled)
b) Material
Support of M.S. Sheet tube
(I) 47 mm x 47 mm x 12 SWG Sheet 3050 mm long
(II) Angle iron 50 x 50 x 6 mm for hold fast including 5% wastage
Add 3% cost of MS Sheet tube 12 SWG and angle irons towards the
cost of fabrication, drilling holes, nuts and bolts etc.
(III) 1.5 mm thick M.S. Sheet duly painted with stove enameled paint
including lettering, signs, border, message with reflective tape of
engineering grade required size, shade and colour as per Technical
Specifications

(i) 900 mm equilateral triangle


OR
(ii) 600 mm equilateral triangle
OR
(iii) 600 mm circular
OR
(iv) 800 mm x 600 mm rectangular
OR
(v) 600 mm x 450 mm rectangular
OR
(vi) 600 mm x 600 mm square
OR
(vii) 900 mm side octagon
(c) Machinery
Tractor with trolley
d&e) Overheads & Contractors Profit
Rate per traffic sign = (i+ii+iii+a+b+c+d+e)

Note : 1. Any one area of M.S. Sheet given at (i) to (viii) may be adopted as per site requirement and in
accordance with IRC-67.

444

RBR-TSRA
Index-code

S. No
1

RBR-TSRA-3

Rate Amount
Rs.
Rs.
2
3
4
5
6
2. The rate for excavation, cement concrete M-15, and painting may be taken from respective
Chapters.
3. The depth of foundation and quantity of cement in the foundation are indicative. These may be
increased for areas having higher wind velocities like in coastal area. This is applicable to all road
signs and direction boards.
Description

Unit

Quantity

Remarks
7

Direction and Place Identification signs upto 0.9 sqm size board
A Retro-reflectorised Traffic Signs
i

Providing and erecting direction and place identification retroreflectorised sign as per IRC:67 made of encapsulated lens type
reflective sheeting vide Clause 1701.2.3 MORD / 801.3 MORTH,
fixed over aluminum sheeting, 2 mm thick with area not
exceeding 0.9 sqm supported on a mild steel single angle iron
post 75 x 75 x 6 mm firmly fixed to the ground by means of
properly designed foundation with M15 grade cement concrete
450 mm x 450 mm x 600 mm, 600 mm below ground level as per
drawings and Technical Specification Clause 1701 MORD / 801
MORTH

Unit = sqm
Taking output = 0.9 sqm
(i) Excavation for foundation
As per item No. 1 of Chapter 11
(ii) Cement concrete M15 grade
As per item No. 4 (A) (iii) or (iv) of Chapter 11
(iii) Painting Angle Iron Post with Primer and two coats
of Epoxy Paint as per specifications
As per item No. 9 of this Chapter OR
Painting Angle Iron Post with Primer and two coats as
per item 6 of this chapter.
(a) labour (For fixing at site)
Mate
Mazdoor (Unskilled)
b) Material
Mild steel angle iron 75 x 75 x 6 mm

cum

0.126

cum

0.12

sqm

0.887
0.43

day
day

0.21

kg
Aluminum sheeting fixed with encapsulated lens type reflective sqm
sheeting of size 0.90 sqm including lettering and signs as applicable
background with epoxy paint
Add 3 per cent of cost of angle iron towards cost of fabrication,
drilling holes, nuts, bolts, etc.

19
0.9

(c) Machinery
Tractor with trolley
d&e) Overheads & Contractors Profit

hour

0.02

cum

0.126

cum

0.126

Cost for 0.9 sqm = (i+ii+iii+a+b+c+d+e) (with epoxy paint)


Rate per sqm (for sign having area upto 0.9 sqm) =
(i+ii+iii+a+b+c+d+e)/0.90
Cost for 0.9 sqm = (i+ii+iii+a+b+c+d+e) (with enamel paint)
Rate per sqm (for sign having area upto 0.9 sqm) =
(i+ii+iii+a+b+c+d+e)/0.90
(ii) Providing and erecting direction and place identification retroreflectorised sign as per IRC:67 made of encapsulated lens type
reflective sheeting vide Clause 1701.2.3, fixed over aluminum
sheeting, 2 mm thick with area not exceeding 0.9 sqm
supported on 2 inch dia GI Pipe firmly fixed to the ground by
means of properly designed foundation with M15 grade cement
concrete 450 mm x 450 mm x 600 mm, 600 mm below ground
level as per drawings and Technical Specification Clause 1701
MORD.

Unit = sqm
Taking output = 0.9 sqm
(i) Excavation for foundation
As per item No. 1 of Chapter 11
(ii) Cement concrete M15 grade
As per item No. 4 (A) (iii) or (iv) of Chapter 11

445

RBR-TSRA
Index-code

S. No
1

Description

Unit

Quantity

day
day

0.26

3.00
0.90

(a) labour (For fixing at site)


Mate
Mazdoor (Unskilled)
b) Material
50 mm dia GI Pipe 2.85 m long including 5 per cent wastage

Aluminum sheeting fixed with encapsulated lens type sqm


reflective sheeting of size including lettering and signs as
applicable background with epoxy paint
Add 3 per cent of cost of GI Pipe towards cost of fabrication,
drilling holes, nuts, bolts etc.
(c) Machinery
hour
Tractor with trolley
d&e) Overheads & Contractors Profit
Cost for 0.9 sqm = (i+ii+iii+a+b+c+d+e)
Rate per sqm (for sign having area upto 0.9 sqm) =
(i+ii+iii+a+b+c+d+e)/0.90

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

0.08

(iii) Providing and erecting direction and place identification retroreflectorised sign as per IRC:67 made of encapsulated lens type
reflective sheeting vide Clause 1701.2.3, fixed over aluminum
sheeting, 2 mm thick with area not exceeding 0.9 sqm
supported on RCC Post 100 mm x 100 mm firmly fixed to the
ground by means of properly designed foundation with M15
grade cement concrete 450 mm x 450 mm x 600 mm, 600 mm
below ground level as per drawings and Technical Specification
Clause 1701 MORD.

Unit = sqm
Taking output = 0.9 sqm
(i) Excavation for foundation
As per item No. 1 of Chapter 11
(ii) Cement concrete M15 grade
As per item No. 4 (A) (iii) or (iv) of Chapter 11

cum

0.126

cum

0.126

(iii) Painting two coats including prime coat on concrete


surface with Epoxy Paint as per specifications
As per item No. 9 of this Chapter
(a) labour (For fixing at site)
Mate
Mazdoor (Unskilled)
b) Material
RCC M15 Grade in Sub-structure
As per item No. 5 (i) or (ii) of Chapter 12
Steel reinforcement HYSD bars
As per item No. 6 of Chapter 12
Aluminum sheeting fixed with encapsulated lens type
reflective sheeting of size including lettering and signs as
applicable background with epoxy paint
Add 3 per cent of cost of RCC Post towards cost of drilling
holes, nuts, bolts, etc.
(c) Machinery
Tractor with trolley
d&e) Overheads & Contractors Profit
Cost for 0.9 sqm = (i+ii+iii+a+b+c+d+e)
Rate per sqm (for sign having area upto 0.9 sqm) =
(i+ii+iii+a+b+c+d+e)/0.90

0.90
day
day

0.26

cum

0.0285

0.0077

sqm

0.90

hour

0.08

Note : 1. Lettering and arrow markings on sign board to be provided separately as per actual
requirement. Rates for these items have been analysed separately.
2. The rate for excavation, cement concrete M15, RCC M15 in Sub-structure, steel re-enforcement
and painting may be taken from respective Chapters.
3. The depth of foundation and quantity of cement concrete in the foundation are indicative. These
may be increased for areas having higher wind velocities like in coastal areas. This is applicable to
all road signs and directions boards.

446

RBR-TSRA
Index-code

S. No
1

Description

2
B Semi-Reflective Traffic signs

Unit

Quantity

cum

0.126

cum

0.126

sqm

0.59

day
day

0.26

kg
kg

12.40
1.06

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

Direction and place identification signs up to 0.9 sqm


size board
Providing and erecting direction and place identifications of semi
reflective sign boards as per IRC:67 made of 2 mm thick M.S. Sheet
duly stove enameled paint in white colour in front and grey colour on
back with red reflective border of 70 mm width and required
message, letters, figures with reflective engineering grade tape as
per MORD specifications of required shade and colour. supported
and welded on 47 mm x 47 mm of 12 SWG Square tube of 3050
mm height duly strengthened by 25 mm x 5 mm M/s flat iron on
edges on back firmly fixed to the ground by means of properly
designed foundation with M15 grade cement concrete 450 mm x 450
mm x 600 mm, 600 mm below ground level as per drawings and
Technical Specification Clause 1701 MORD.

Unit = each
Take Output = 0.9 sqm
(i) Excavation for foundation
As per item No. 1 of Chapter 11
(ii) Cement concrete M15 grade
As per item No. 4 (A) (iii) or (iv) of Chapter 11
(iii) Painting on M.S. tube post with primer and two coat
of epoxy paint as per specifications
As per item No.9 of Chapter 10
(a) labour (For fixing at site)
Mate
Mazdoor (Unskilled)
b) Material
(i) Support of MS sheet tube
47 mm x 47 mm of 12 SWG sheet 3050 mm long
(ii) Angle iron 50 x 50 x 6 mm for lugs including 5% wastage

(iii) 2 mm thick MS sheet strengthened by 25 mm x 5 mm MS flat sqm


iron & painted with stove enameled paint including lettering, signs,
message, border with reflective tape of engineering grade of
required shade and colour as per Technical Specifications.

Add 3% cost of MS sheet angle iron towards the cost of


fabrications, drilling, holes, nuts, bolts etc.
(c) Machinery
hour
Tractor with trolley
d&e) Overheads & Contractors Profit
Cost for 0.9 sqm = (i+ii+iii+a+b+c+d+e)
Rate per sqm (for sign having area upto 0.9 sqm) =
(i+ii+iii+a+b+c+d+e)/0.90

0.90

0.08

Note : Rate for excavation, cement concrete M15 and painting may be taken from respective
Chapters.

RBR-TSRA-4

Direction and Place Identification signs with size more


than 0.9 sqm size board
A Retro-reflectorised Traffic Signs
i

Providing and erecting direction and place identification retro\reflectorised sign as per IRC:67 made of encapsulated lens
type reflective sheeting vide Clause 1701.2.3 MORD / 801.3
MORTH, fixed over aluminum sheeting, 2 mm thick with area
exceeding 0.9 sqm supported on mild steel angle iron posts 75
mm x 75 mm x 6 mm, 2 Nos. firmly fixed to the ground by
means of properly designed foundation with M15 grade cement
concrete 450 mm x 450 mm x 600 mm, 600 mm below ground
level as per drawings and Technical Specification Clause 1701
MORD / 801 MORTH

Unit = sqm
Taking output = 1.50 sqm
(i) Excavation for foundation
As per item No. 1 of Chapter 11
(ii) Cement concrete M15 grade
As per item No. 4 (A) (iii) or (iv) of Chapter 11

cum

0.252

cum

0.252

447

RBR-TSRA
Index-code

S. No
1

Description

Unit

Quantity

sqm
sqm

1.774
0.86

day
day

0.31

kg

38.00

sqm

1.50

(iii) Painting Angle Iron Post with Primer and two coats
of Epoxy Paint as per specifications
As per item No. 9 of this Chapter (or)
Painting Angle Iron Post with Primer and two coats (item 6
of this chapter)
(a) labour (For fixing at site)
Mate
Mazdoor (Unskilled)
b) Material
Mild steel angle iron 75 mm x 75 mm x 6 mm, 2.85 m long,
2 nos. with 5 per cent wastage
Aluminum sheeting fixed with encapsulated lens type
reflective sheeting of size including lettering and signs as
applicable background with epoxy paint
Add 2 per cent of cost of angle iron towards cost of
fabrication, drilling holes, nuts, bolts, etc.
(c) Machinery
Tractor with trolley
d&e) Overheads & Contractors Profit
Cost for 1.5 sqm = i+ii+iii+a+b+c+d+e (with epoxy paint)
Rate per sqm (for sign having area more than 0.9 sqm) =
(i+ii+iii+a+b+c+d+e)/1.50

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

2.00%

hour

0.02

cum

0.252

cum

0.252

day
day

0.52

6.00
1.50

Cost for 1.5 sqm = i+ii+iii+a+b+c+d+e (with enamel paint)

Rate per sqm (for sign having area more than 0.9 sqm) =
(i+ii+iii+a+b+c+d+e)/1.50
(ii) Providing and erecting direction and place identification retroreflectorised sign as per IRC:67 made of encapsulated lens type
reflective sheeting vide Clause 1701.2.3, fixed over aluminum
sheeting, 2 mm thick with area exceeding 0.9 sqm supported on
dia GI Pipe firmly fixed to the ground by means of properly
designed foundation with M15 grade cement concrete 450 mm x
450 mm x 600 mm, 600 mm below ground level as per drawings
and Technical Specification Clause 1701 MORD.

Unit = sqm
Taking output = 1.50 sqm
(i) Excavation for foundation
As per item No. 1 of Chapter 11
(ii) Cement concrete M15 grade
As per item No. 4 (A) (iii) or (iv) of Chapter 11
(a) labour (For fixing at site)
Mate
Mazdoor (Unskilled)
b) Material
50 mm dia GI Pipe 2.85 m long including 5 per cent wastage

Aluminum sheeting fixed with encapsulated lens type sqm


reflective sheeting of size including lettering and signs as
applicable background with epoxy paint
Add 3 per cent of cost of GI Pipe towards cost of fabrication,
drilling holes, nuts, bolts, etc.
(c) Machinery
hour
Tractor with trolley
d&e) Overheads & Contractors Profit
Cost for 1.5 sqm = i+ii+iii+a+b+c+d+e
Rate per sqm (for sign having area more than 0.9 sqm) =
(i+ii+iii+a+b+c+d+e)/1.50

0.12

448

RBR-TSRA
Index-code

S. No
1

Description

2
(iii) Providing and erecting direction and place identification retroreflectorised sign as per IRC:67 made of encapsulated lens type
reflective sheeting vide Clause 1701.2.3, fixed over aluminum
sheeting, 2 mm thick with area exceeding 0.9 sqm supported on
RCC Posts 100 mm x 100 mm firmly fixed to the ground by
means of properly designed foundation with M15 grade cement
concrete 450 mm x 450 mm x 600 mm, 600 mm below ground
level as per drawings and Technical Specification Clause 1701
MORD.

Unit = sqm
Taking output = 1.50 sqm
(i) Excavation for foundation
As per item No. 1 of Chapter 11
(ii) Cement concrete M15 grade
As per item No. 4 (A) (iii) or (iv) of Chapter 11
(iii) Painting two coats including prime coat on concrete
surface with Epoxy Paint as per specifications
As per item No. 9 of this Chapter
(a) labour (For fixing at site)
Mate
Mazdoor (Unskilled)
b) Material
RCC M15 Grade in Sub-structure
As per item No.12.5 of Chapter 12
Steel reinforcement HYSD bars
As per item No.12.6 of Chapter 12
Aluminum sheeting fixed with encapsulated lens type
reflective sheeting of size including lettering and signs as
applicable background with epoxy paint

Unit

Quantity

cum

0.252

cum

0.252

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

1.00
day
day

0.52

cum

0.057

t
sqm

0.0154
1.50

Add 3 per cent of cost of RCC Post towards cost of drilling


holes, nuts, bolts, etc.
(c) Machinery
hour
Tractor with trolley
d&e) Overheads & Contractors Profit
Cost for 1.5 sqm = a+b+c+d+e
Rate per sqm (for sign having area more than 0.9 sqm) =
(a+b+c+d+e)/1.50

0.12

Note : 1. Lettering and arrow markings on sign boards to be provided separately as per actual
requirement. Rates for these items have been analysed separately.
2. The rate for excavation, cement concrete M15, RCC M15 in Sub-structure, steel re-enforcement and
painting may be taken from respective Chapters.
3. The depth of foundation and quantity of cement concrete in the foundation are indicative. These may be
increased for areas having higher wind velocities like in coastal areas. This is applicable to all road signs
and directions boards.

449

RBR-TSRA
Index-code

S. No
1

Description

2
B Semi-Reflective Traffic signs

Unit

Quantity

cum

0.252

cum

0.252

sqm

0.92

day
day

0.52

kg

24.80

kg

2.12

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

Direction and place identification signs more than 0.90


sqm sign board
Providing and erecting direction and place identification of semi
reflective sign boards as per IRC-67 made of 2 mm thick M.S. Sheet
duly stove enameled paint white colour in front and grey colour on
back with reflective border of 70 mm width and required message,
letters, figures with reflective tape of engineering grade as per
MORD specifications of required shade and colour. Supported and
welded on two nos. 47 mm x 47 mm of 12 SWG square tube of 3050
mm height duly strengthened by 25 mm x 5 mm MS flat iron on
edges on back firmly fixed to the ground by means of properly
designed foundation with M15 grade cement concrete 450 mm x 450
mm x 600 mm, 600 mm below ground level as per drawings and
Technical Specification Clause 1701 MORD.

Unit = each
Taking output = 1.5 sqm
(i) Excavation for foundation
As per item No. 1 of Chapter 11
(ii) Cement concrete M15 grade
As per item No. 4 (A) (iii) or (iv) of Chapter 11
(iii) Painting M.S. tube posts with primer and two coats
of epoxy paint as per specification
As per item No. 9 of chapter 10
(a) labour (For fixing at site)
Mate
Mazdoor (Unskilled)
b) Material
(i) Support of MS Sheet tubes 47 mm x 47 mm x 12 SWG
sheet 3050 mm long
(ii) Angle iron 50 mm x 50 mm x 6 mm for lugs

(iii) 2 mm thick MS Sheet strengthened by 25 mm x 5 mm M.S. flat sqm


iron and painted with stove enameled paint including lettering, signs,
messages, border with reflective tape of engineering grade of
required size, shade and colour as per MORD specifications

Add 3% cost of MS sheet and angle iron towards the cost of


fabrications, drilling, holes, nuts, bolts etc.
(c) Machinery
hour
Tractor with trolley
d&e) Overheads & Contractors Profit
Cost for 1.5 sqm = a+b+c+d+e
Rate per sqm (for sign having area more than 0.9 sqm) =
(a+b+c+d+e)/1.50

1.50

0.16

Note : Rate for excavation cement concrete M15 and painting may be taken
from respective chapter

RBR-TSRA-5

Overhead Signs
Providing and erecting overhead signs with a corrosion resistant
2mm thick aluminum alloy sheet reflectorised with high intensity retroreflective sheeting of encapsulated lense type with vertical and
lateral clearance given in clause 802.2 and 802.3 and installed as
per clause 802.7 over a designed support system of aluminum alloy
or galvanised steel trestles and trusses of sections and type as per
structural design requirements and approved plans as per clause
802 MORTH
A Truss and Vertical Support

Unit = tonne
Taking output = 1 tonne
a) Labour
Mate

day

Blacksmith

day

2.00

Mazdoor including for handling & fixing at site.

day

4.24

450

RBR-TSRA
Index-code

S. No
1

Description

Unit

Quantity

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

b) Material
tonne
Aluminum alloy / galvanised steel including 5% wastage
Add 1 per cent on cost of material for nuts, bolts and drilling
and welding consumables

1.05

Add 15 per cent on cost of material for fabrication of trusses


as per approved design
c) Machinery
Crane 3 tonne capacity

hour

3.00

Truck

hour

0.50

d&e) Overheads & Contractors Profit


Rate per tonne = (a+b+c+d+e)
B Aluminum Alloy Plate for Over Head Sign

Unit = sqm
Taking output = 1 sqm
a) Labour
Mate

day

Blacksmith

day

0.10

Mazdoor

day

0.17

Aluminum alloy plate, 2 mm thick, fixed with high intensity sqm


grade sheeting vide clause 801.3

1.00

b) Material

Miscellaneous
Add 1 per cent of cost of labour for lifting arrangement, like
ladders, pulleys, ropes etc
c&d) Overheads & Contractors Profit
Rate per sqm = (a+b+c+d)
Note : 1. The cost of excavation and foundation concrete for fixing of vertical support system to be
worked out separately as per the approved drawing/design and to be included in the estimate.
2. Lettering and arrow marks on sign board to be provided separately as per actual requirement. Rates for
these items have been included separately in this chapter.

RBR-TSRA-6

6
i

Painting Two Coats on New Concrete Surfaces


Painting two coats including primer coat after filling the
surface with synthetic enamel paint in all shades on new,
plastered / concrete surfaces as per drawing and Technical
Specification Clause 1701MORD.
Unit = sqm
Taking output = 40 sqm
a)Labour
Mate
Painter (1st Class)
Painter Assistant
Mazdoor (Unskilled)
b) Material
Cement Primer as per specifications
Paint conforming to requirement of Clause 1701.3.8

day
day
day
day

3.00

litre
litre

3.00
6.00

Filling Material on Paint Cost


c&d) Overheads & Contractors Profit
Cost for 40 sqm = a+b+c+d
Rate per sqm = (a+b+c+d)/40
ii Painting two coats after filling the surface with synthetic
enamel paint in all shades on new plastered concrete
surfaces (excluding Primary Coat) as per Speciufication
803 MORTH
Unit = sqm
Taking output = 40 sqm
a) Labour
day
Mate
day
Painter
day
Mazdoor

2.000
1.120

2.20

Add for scaffolding @ 1 per cent of labour cost where required

451

RBR-TSRA
Index-code

S. No
1

b)

Description

Unit

Quantity

Litre

6.000

7
i

day
day
day

0.25
0.60
0.40

litre
litre

0.60
1.25

day
day
day

0.45
0.28

Litre

1.25

day
day
day

0.60
0.65

litre
litre

0.60
1.25

Amount
Rs.
6

Remarks
7

Material

Paint conforming to requirement of clause 803.3 MORTH

RBR-TSRA-7

Rate
Rs.
5

Add for scaffolding @ 1% of labour cost where required


c&d) Overheads & Contractors Profit
Cost for 40 sqm = a+b+c+d
Rate per sqm = (a+b+c+d)/40
Painting on Steel Surfaces
Providing and applying two coats of ready mix Enamel paint
including primer coat of approved brand on steel surface
after through cleaning of surface to give an even shade as
per drawing and Technical Specification Clause 1701MORD
Unit = sqm
Taking output = 10 sqm
a)Labour
Mate
Painter (1st Class)
Mazdoor (Unskilled)
b) Material
Red-oxide Primer as per specifications
Paint ready mixed approved brand
Add @ 1% on cost of material for scaffolding wherever required

c&d) Overheads & Contractors Profit


Cost for 10 sqm = a+b+c+d
Rate per sqm = (a+b+c+d)/10
ii Providing and applying two coats of ready mix Enamel paint
of approved brand on steel surface after through cleaning of
surface to give an even shade (excluding Primary Coat)
as per specification 803 MORTH.
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate
Painter
Mazdoor
b)
Material
Paint ready mixed approved brand.
Add @ 1 per cent on cost of material for scaffolding
c&d) Overheads & Contractors Profit
Cost for 10 sqm = a+b+c+d
Rate per sqm= (a+b+c+d)/10
iii Painting on Steel Surfaces
Providing and applying two coats of ready mix Aluminum paint
including primer coat of approved brand on steel surface after
through cleaning of surface to give an even shade as per drawing
and Technical Specification Clause 1701MORD

Unit = sqm
Taking output = 10 sqm
a)Labour
Mate
Painter (1st Class)
Mazdoor (Unskilled)
b) Material
Red-oxide Primer as per specifications
Paint ready mixed approved brand
Add @ 1 per cent on cost of material for scaffolding
wherever required
c&d) Overheads & Contractors Profit
Cost for 10 sqm = a+b+c+d
Rate per sqm = (a+b+c+d)/10

452

RBR-TSRA
Index-code

S. No
1

Description

2
iv Providing and applying two coats of ready mix paint

Unit

Quantity

day
day
day

0.45
0.28

Litre

1.25

day
day
day

0.50
0.23

litre
litre

0.60
1.5
1.00%

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

Aluminum of approved brand on steel surface after through


cleaning of surface to give an even shade (excluding
Primary Coat) as per Specification 803 MORTH

RBR-TSRA-8

8
i

Unit = sqm
Taking output = 10 sqm
a) Labour
Mate
Painter
Mazdoor
b)
Material
Paint ready mixed approved brand.
Add @ 1 per cent on cost of material for scaffolding
c&d) Overheads & Contractors Profit
Cost for 10 sqm = a+b+c+d
Rate per sqm= (a+b+c+d)/10
Painting on Wood Surfaces
Providing and applying two coats of ready mix paint
including primer coat of approved brand on wood surface
after through cleaning of surface to give an even shade as
per drawing and Technical Specification Clause 803
MORTH
Unit = sqm
Taking output = 10 sqm
a)Labour
Mate
Painter (1st Class)
Mazdoor (Unskilled)
b) Material
Red-oxide Primer as per specifications
Paint ready mixed approved brand
Add @ 1 per cent on cost of material for scaffolding
wherever required
Add @ 5 per cent on cost of labour & materials to prepare the
surface by filling minutes roughness on the surface and priming the
surface before laying 2 coats of painting.

5.00%

c&d) Overheads & Contractors Profit


Cost for 10 sqm = a+b+c+d
Rate per sqm = (a+b+c+d)/10
ii

Providing and applying two coats of ready mix paint


excluding primer coat of approved brand on wood surface
after through cleaning of surface to give an even shade as
per drawing and Technical Specification Clause 803
MORTH
Unit = sqm
Taking output = 10 sqm
a)Labour
Mate
Painter (1st Class)
Mazdoor (Unskilled)
b) Material
Paint ready mixed approved brand
Add @ 1 per cent on cost of material for scaffolding
wherever required
c&d) Overheads & Contractors Profit
Cost for 10 sqm = a+b+c+d
Rate per sqm = (a+b+c+d)/10

day
day
day
litre

0.50
0.23
1.5
1.00%

453

RBR-TSRA
Index-code

S. No
1

RBR-TSRA-9

Description

Unit

Quantity

day
day
day

0.60
0.65

litre
litre

0.60
1.25

day
day
day
day
day

0.35

litre

1.48

day
day
day
day
day

0.55

litre

1.48

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

Painting on Concrete/Steel Surfaces with Epoxy


Painting two coats including prime coat with epoxy paint of
approved brand on concrete/steel surfaces after through
cleaning of surface to give an even shade as per drawing
and Technical Specification Clause 1701 MORD
Unit = sqm
Taking output = 10 sqm
a)Labour
Mate
Painter (1st Class)
Mazdoor (Unskilled)
b) Material
Epoxy primer / Red-oxide
Epoxy paint
Add @ 1 per cent on cost of material for scaffolding
wherever required
c&d) Overheads & Contractors Profit
Cost for 10 sqm = a+b+c+d
Rate per sqm = (a+b+c+d)/10

RBR-TSRA-10

10

Painting lines, Dashes, Arrows, etc. on Road in Two


Coats on New Work
Painting lines, dashes, arrows, etc. on roads in two coats on
new work with ready mixed road marking paint conforming
to IS:164 on bituminous/concrete surface, including cleaning
the surface of all dirt, dust and other foreign matter,
demarcation at site and traffic control as per drawing and
Technical Specification Clause 1702 MORD / 803 MORTH
i

Upto 100 mm width


Unit = sqm
Taking output = 10 sqm
a)Labour
Mate
Painter (1st Class)
Painter (2nd Class)
Painter Assistant
Mazdoor (Unskilled)
b) Material
Road marking paint as per IS:164
c&d) Overheads & Contractors Profit
Cost for 10 sqm = a+b+c+d
Rate per sqm = (a+b+c+d)/10
ii Over 100 mm width (MORTH)
Unit = sqm
Taking output = 10 sqm
a)Labour
Mate
Painter (1st Class)
Painter (2nd Class)
Painter Assistant
Mazdoor (Unskilled)
b) Material
Road marking paint as per IS:164
c&d) Overheads & Contractors Profit
Cost for 10 sqm = a+b+c+d
Rate per sqm = (a+b+c+d)/10

1.42

1.64

454

RBR-TSRA
Index-code

S. No
1

RBR-TSRA-11

11

Description

Unit

Quantity

day
day
day

0.30
1.31

litre

0.90

day
day
day

0.35
1.42

litre

0.90

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

Painting lines, Dashes, Arrows, etc. on Roads in Two


Coats on Old Work
Painting lines, dashes, arrows, etc. on roads in two coats on
old work with ready mixed road marking paint conforming to
IS:164 on bituminous/concrete surface, including cleaning
the surface of all dirt, dust and other foreign matter,
demarcation at site and traffic control as per drawing and
Technical Specification Clause 1702 MORD / 803 MORTH.
i

Upto 100 mm width


Unit = sqm
Taking output = 10 sqm
a)Labour
Mate
Painter (1st Class)
Mazdoor (Unskilled)
b) Material
Road marking paint
c&d) Overheads & Contractors Profit
Cost for 10 sqm = a+b+c+d
Rate per sqm = (a+b+c+d)/10
ii Over 100 mm width
Unit = sqm
Taking output = 10 sqm
a)Labour
Mate
Painter (1st Class)
Mazdoor (Unskilled)
b) Material
Road marking paint
c&d) Overheads & Contractors Profit
Cost for 10 sqm = a+b+c+d
Rate per sqm = (a+b+c+d)/10
12

RBR-TSRA-12

Road Marking with Hot Applied Thermoplastic


Compound with Reflectorising Glass Beads on
Bituminous Surface
Providing and laying of hot applied thermoplastic compound 2.5 mm
thick including reflectorising glass beads @ 250 gms per sqm area,
thickness of 2.5 mm is exclusive of surface applied glass beads as
per IRC:35 .The finished surface to be level, uniform and free from
streaks and holes as per Specification 803 MORTH

Unit = sqm
Taking output = 600 sqm
a) Labour
day
Mate
day
0.78
Mazdoor
b) Machinery
hour
10.00
Road marking machine @ 60 sqm per hour
hour
0.50
Tractor-trolley
c) Material
Litre 1500.00
Hot applied thermoplastic compound
kg
150.00
Reflectorising glass beads
d&e) Overheads & Contractors Profit
Cost for 600 sqm = a+b+c+d+e
Rate per sqm = a+b+c+d+e)/600
Note : 1. A sealing primer may be applied in advance on cement concrete pavement to
ensure proper bonding. Any laitance and/or curing compound to be removed where paint is
required to be applied on concrete surface.
2. Cost of painter is already included in hire charges of road marking machine.

455

RBR-TSRA
Index-code

RBR-TSRA-13

S. No

Description

Unit

Quantity

13

Kilometre Stone
Reinforced cement concrete M15 grade kilometre
stone/local stone of standard design as per IRC:8 fixing in
position including painting and printing, etc as per drawing
and Technical Specification Clause 1703 MORD / 804
MORTH
(i) 5th Kilometre Stone (precast)
Unit = each
Taking output = 6 Nos.
a) M-15 grade of concrete
cum
As per item No. 5 (i) or (ii) of Chapter 12
b) Steel reinforcement @ 5 kg per sqm
kg
As per item No. 6 of Chapter 12
c) Excavation in soil for foundation
cum
As per item No. 1 of Chapter 11
d) Painting two coats on concrete surface
sqm
As per item No.5 of Chapter 10

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

2.35
22.08
1.68
9.85

e) lettering on km post (average 30 letters of 10 cm height each)

As per item No. 1 of Chapter 10

Transportation and fixing


f)Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
g) Machinery
50 HP Tractor with trolley
h&i) Overheads & Contractors Profit
j )Cost for 6 Nos. 5th km stone = a+b+c+d+e+f+g+h+i
Rate for each 5th km stone = j/6
(ii) Ordinary Kilometer Stone (Precast)
Unit = each
Taking output = 14 Nos.
a) M-15 grade of concrete
As per item No. 5 (i) or (ii) of Chapter 12
b) Steel reinforcement @ 5 kg per sqm
As per item No. 6 of Chapter 12
c) Excavation in soil for foundation
As per item No. 1 of Chapter 11
d) Painting two coats on concrete surface
As per item No.5 of Chapter 10

per
cm
high
per
letter

1800.00

day
day
day

0.60
6.26

hour

6.00

cum

3.77

kg

26.32

cum

2.77

sqm

11.41

per
cm
high
per
letter

1680.00

day
day
day

1.00
7.32

hour

6.00

e) lettering on km post (average 12 letters of 10 cm height each)

As per item No. 1 of Chapter 10

Transportation and fixing


f)Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
g) Machinery
50 HP Tractor with trolley
h&i) Overheads & Contractors Profit
j) Cost for 14 Nos. ordinary km stone = (a+b+c+d+e+f+g+h+i)
Rate for each ordinary km stone = j/ 14

456

RBR-TSRA
Index-code

S. No
1

Description

2
(iii) 200 m / Hectometer stone (precast)

Unit = each
Taking output = 33 Nos.
a) M-15 grade of concrete
As per item No. 5 (i) or (ii) of Chapter 12
b) Steel reinforcement @ 5 kg per sqm
As per item No. 6 of Chapter 12
c) Excavation in soil for foundation
As per item No. 1 of Chapter 11
d) Painting two coats on concrete surface
As per item No.5 of Chapter 10

Unit

Quantity

cum

1.58

kg

66.00

cum

1.39

sqm

6.27

per
cm
high
per
letter

330.00

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

e) lettering on km post (average 1 letter of 10 cm height each)

As per item No. 1 of Chapter 10

RBR-TSRA-14

14

Transportation and fixing


f)Labour
day
Mate
day
1.50
Mason (1st Class)
day
7.34
Mazdoor (Unskilled)
g) Machinery
hour
6.00
50 HP Tractor with trolley
h&i) Overheads & Contractors Profit
j) Cost for 33 Nos. 200 m stone = (a+b+c+d+e+f+g+h+i)
Rate for each 200 m stone = j / 33
Note : 1. The rate for excavation, cement concrete, steel reinforcement, painting and
lettering may be taken from respective Chapters.
2. In case local stone is to be used in place of precast RCC stones, then rate of cement
concrete and steel reinforcement may be deleted.
Road Delineators
Supplying and installation of delineators (road way indicators, hazard
markers, object markers), 80-100 cm high above ground level,
painted black and white in 15 cm wide strips, fitted with 80 x 100 mm
rectangular or 75 mm dia circular reflectorised panels at the top,
buried or pressed into the ground and conforming toIRC-79 and the
drawings as per Specification 805 MORTH.

Unit = Each
Taking output= 30 Nos.
a) Labour
day
Mate
day
Mazdoor for fixing
b) Material
Cost of approved type of delineators from ISI certified firm each
as per the standard drawing given in IRC - 79
Add 10 per cent cost of material for installation
c&d) Overheads & Contractors Profit
Cost for 30 Nos. delineators = (a+b+ c+d)
Rate per delineators = (a+b+c+d) /30

RBR-TSRA-15

15

1.04
30.00

Note : In case of soft ground, a proper foundation may be provided as per approved
design. In case foundation is required to be provided, the items of excavation and
foundation concrete are required to be measured and paid separately.
Boundary Pillar
Reinforced cement concrete M15 grade boundary pillars/local stone
of standard design as per IRC:25, fixed in position including finishing
and lettering but excluding painting as per drawing and Technical
Specification Clause 1704 MORD / 806 MORTH

Unit = each
Taking output = 57 Nos.
a) M-15 grade of concrete
As per item No. 5 (i) or (ii) of Chapter 12

cum

1.25

457

RBR-TSRA
Index-code

S. No
1

Description

Unit

Quantity

kg

79.80

cum

10.72

per
letter
per
cm
high

2280.00

day
day

14.82

hour

6.00

cum

11.97

b) Steel reinforcement @ 5 kg per sqm


As per item No. 6 of Chapter 12
c) Excavation in soil for foundation
As per item No. 1 of Chapter 11
d) lettering, each 10 cm high
As per Item No. 1 of Chapter 10

Transportation and fixing


f)Labour
Mate
Mazdoor (Unskilled)
g)Machinery
Tractor with trolley
h) Material
Stone spall
i&j) Overheads & Contractors Profit
k) Cost for 57 Nos. boundary pillar = a+b+c+d+e+f+g+h+i+j

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

Rate for each boundary pillar = k/57


Note : 1. In case of soft ground, a proper foundation may be provided as per approved
design. In case foundation is required to be provided, the items of excavation and
foundation concrete are required to be measured and paid separately.

RBR-TSRA-16

16
i

2. In case local stone is to be used in place of precast RCC stones, then rate of cement
concrete and steel reinforcement may be deleted.
G.I Barbed Wire Fencing 1.2 m high
Providing and fixing 1.2 m high GI barbed wire fencing with
1.8 m RCC posts 150 mm x 150 mm placed every 3 m
centre-to-centre founded in M15 grade cement concrete, 0.6
m below ground level, every 15th post, last but one end post
and corner post shall be strutted on both sides and end post
on one side only and provided with 9 horizontal lines and 2
diagonals interwoven with horizontal wires, fixed with GI
staples, turn buckles etc., complete as per Clause 1705
MORD.
Unit = per running m
Taking output = 30 m
a)Labour
day
Mate
day
0.25
Blacksmith
day
2.09
Mazdoor (Unskilled)
b) Machinery
kg
31.42
Barbed wire 335 m length @ 9.38 kg per 100 m
R.C.C. Post 150 mm x 150 mm x 1.80 m M15 Grade
concrete 13 x 150 mm x 150 mm x 1.8 m
cum
0.526
As per item No. 5 (i) or (ii) of Chapter 12
Add 5 per cent extra cost for formwork of M-15
Supply of HYSD Bars including cutting, bending, tying &
placing in position.
10 mm dia HYSD bars for posts
13 x 4 x 1.8 = 93.6 m @ 0.62 kg/mt = 43.60 kg
8 mm dia HYSD bars for rings
13 x 10 x 0.6 = 78 m @ 0.39 kg/mt = 30.42 kg
Total = 74.02 Kgs
As per item No. 6 of Chapter 12
Add for GI staple binding wire, drilling holes, etc. @ 2 per
cent of the cost of material

0.074

458

RBR-TSRA
Index-code

S. No
1

Description

Unit

Quantity

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

c) Painting
Applying two coats of painting including primer coat on
exposed surface of RCC posts
sqm
8.14
As per item No. 6 of this Chapter
d&e) Overheads & Contractors Profit
Cost for 30 m fencing = a+b+c+d+e
Rate per m = (a+b+c+d+e)/30
Note : Cost of excavation for foundation and foundation concrete to be added separately in
the cost estimate as per approved design. The rate for these items may be taken from
respective Chapters.
ii G.I Barbed Wire Fencing 1.8 m high
Providing and fixing 1.8 m high GI barbed wire fencing with
2.4 m RCC M15 grade 150 mm x 150 mm concrete post
placed every 3 m centre-to-centre founded in M15 grade
cement concrete, 0.6 m below ground level, every 15th
post, last but one end post and corner post shall be strutted
on both sides and end post on one side only and provided
with 9 horizontal lines and 2 diagonals interwoven with
horizontal wires, fixed with GI staples, turn buckles etc.
complete as per Clause 1705 MORD.
Unit = per running m
Taking output = 30 m
a)Labour
day
Mate
day
0.40
Blacksmith
day
2.62
Mazdoor (Unskilled)
b) Machinery
kg
40.15
Barbed wire 428 m length @ 9.38 kg per 100 m
R.C.C. Post 150 mm x 150 mm x 2.4 m High M-15 Grade
13 x 150 mm x 150 mm x 2.4 m
cum
0.702
As per item No. 5 (i) or (ii) of Chapter 12
Add 5 per cent extra cost of C.C. for formwork of M-15
Supply of HYSD Bars including cutting, bending, tying &
placing in position.
10 mm dia HYSD bars for posts 13 x 4 x 2.4 = 124.80 m
@ 0.62 kg/mt =
77.38 kg
8 mm dia HYSD bars for rings
13 x 11 x 0.6 =
85.80 m
@ 0.39 kg/m =
33.46 kg
Total = 110.84 Kgs
t
0.111
As per item No. 6 of Chapter 12
Add for GI staple, binding wire, drilling holes etc. @ 2 per
cent of the cost of material
c) Painting
Applying two coats of painting including primer coat on
exposed surface of RCC posts
sqm
12.10
As per item No. 6 of this Chapter
d&e) Overheads & Contractors Profit
Cost for 30 m fencing = a+b+c+d+e
Rate per m fencing = (a+b+c+d+e)/30
Note : Cost of excavation for foundation and foundation concrete to be added separately in
the cost estimate as per approved design. The rate for these items may be taken from
respective Chapters.

459

RBR-TSRA
Index-code

S. No
1

Description

2
iii G.I Barbed Wire Fencing 1.2 Metre High

Unit

Quantity

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

Providing and fixing 1.2 metres high GI barbed wire fencing


with 1.8 m angle iron posts 40 mm x 40 mm x 6 mm placed
every 3 metres center to center founded in M15 grade
cement concrete, 0.6 metre below ground level, every 15th
post, last but one end post and corner post shall be strutted
on both sides and end post on one side only and provided
with 9 horizontal lines and 2 diagonals interwoven with
horizontal wires, fixed with GI staples, turn buckles etc
complete as per clause 807 MORTH
Unit = per running metre
Taking output = 30 metres
a) Labour
day
Mate
day
0.25
Blacksmith
day
2.09
Mazdoor
b)
Material
kg
31.42
Barbed wire 335 metres length @ 9.38 kg / 100 metres
80.50
MS angle iron 40 mm x 40mm x 6 mm, 23 metres in length kg
@ 3.5 kg per metre
Add for GI staple binding wire, drilling holes etc. @ 2 per
cent of the cost of material
c)
Painting
2.11
Applying two coats of painting on exposed surface of angle sqm
iron posts ( Rate as per item no. 7)
d&e) Overheads & Contractors Profit
Cost for 30 metres fencing = a+b+c+d+e
Rate per metre = (a+b+c+d+e)/30
Note : Cost of excavation for foundation and foundation concrete to be added separately in
the cost estimate as per approved design. The rate for these items may be taken from
respective chapters.
iv G.I Barbed Wire Fencing 1.8 Metre High
Providing and fixing 1.8 metres high GI barbed wire fencing with 2.4
m angle iron posts 50 mm x 50 mm x 6 mm placed every 3 metres
center to center founded in M15 grade cement concrete, 0.6 metre
below ground level, every 15th post, last but one end post and
corner post shall be strutted on both sides and end post on one side
only and provided with 12 horizontal lines and 2 diagonals
interwoven with horizontal wires, fixed with GI staples, turn buckles
etc complete as per clause 807 MORTH.

Unit = per running metre


Taking output = 30 metres
a) Labour
Mate
Blacksmith
Mazdoor
b)
Material
Barbed wire 428 metres length @ 9.38 kg / 100 metres
MS angle iron 50 mm x 50 mm x 6 mm, 33.8 metres in
length @ 4.5 kg per metre
Add for GI staple, binding wire, drilling holes etc. @ 2 per
cent of the cost of material
c)
Painting
Applying two coats of painting on exposed surface of angle
iron posts

day

day

0.40

day

2.62

kg

40.15

kg

152.00

sqm

3.96

d&e) Overheads & Contractors Profit


Cost for 30 metres fencing = a+b+c+d+e
Rate per metre fencing = (a+b+c +d+e)/30
Note : Cost of excavation for foundation and foundation concrete to be added separately in
the cost estimate as per approved design. The rate for these items may be taken from
respective chapters.

460

RBR-TSRA
Index-code

S. No
1

RBR-TSRA-17

17

Description

Unit

Quantity

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

Fencing With Welded Steel Wire Fabric 75 mmx50 mm


Providing 1.20 metre high fencing with angle iron posts 50
mm x 50 mm x 6 mm at 3 metre center to center with 0.40
metre embedded in M15 grade cement concrete, corner,
end and every 10th post to be strutted, provided with
welded steel wire fabric of 75 mm x 50 mm mesh or 75 mm
x 25 mm mesh and fixed to iron posts by flat iron 50 x 5 mm
and bolts etc. complete in all respects. (MORTH
Suggestive )

RBR-TSRA-18

18

Unit = Running metre


Taking output = 30 m
a) Labour
day
Mate
day
1.00
Welder
day
2.12
Mazdoor
b)
Material
kg
106.00
i) Angle iron for posts 50 x 50 x 6 mm
kg
26.00
ii) Runner flat 50 x 5 mm
151.00
iii) Welded steel wire fabric 75x50 mm mesh @ 4 kg/sqm, 4 kg
x 30 x 1.2 + 5 per cent wastage
OR
293.00
Welded steel wire fabric 75 x 25 mm mesh @ 7.75 kg/sqm, kg
7.75 x 30 x 1.2 + 5 per cent wastage
Add 2.5 per cent of cost of material for drilling holes in
angles, flats, splitting angle at bottom, nuts and bolts and
welded consumables
c)
Machinery
hour
0.10
Tractor-trolley
d)
Painting
sqm
8.00
Painting two coats including priming
e&f) Overheads & Contractors Profit
Cost for 30 metre = a+b+c+d+e+f
Rate per metre = (a+b+c+d+e+f)/30
Note : i) Adopt any one type of welded steel wire fabric 75 x 50 mm or 75 x 25 mm as per
approved design.
Note : ii) The item of excavation and cement concrete in foundation shall be measured and
paid separately
Tubular Steel Railing on Medium Weight Steel Channel
(ISMC series) 100 mm x 50 mm
Providing, fixing and erecting 50 mm dia steel pipe railing in
3 rows duly painted on medium weight steel channels
(ISMC series) 100 mm x 50 mm, 1.2 m high above ground,
2 m centre-to-centre, complete as per approved drawings
Clause 1706 MORD
Unit = Running m
Taking output = 10 m
i) Excavation for foundation (6 Nos.) 6 x 0.6 x 0.6 x 0.6
As per item No. 1 of Chapter 11

cum

1.296

cum

0.648

sqm

4.71

sqm

2.16

day
day
day

0.26
0.01

ii) Foundation concrete M-15 grade PCC 6 x 0.6 x 0.6 x 0.3

As per item No. 4 (A) (iii) or (iv) of Chapter 11


iii) Painting of pipe
As per item No. 6 of this Chapter
iv) Painting of channel section (6 nos.)
1.8 m each 0.2 x 1.8 x 1.6 = 2.16
As per item No.6 of this Chapter
a) labour (For fixing at site)
Mate
Mazdoor (Unskilled)
Plumber

461

RBR-TSRA
Index-code

S. No
1

RBR-TSRA-19

19

Description

Unit

Quantity

b) Material
m
Steel pipe 50 mm external dia as per IS:1239
Medium weight steel channel (ISMC series) 100 mm x 50 kg
mm, 10.8 m length @ 9.2 kg per m
Add for drilling holes @ 3 per cent of cost of channels
c) Machinery
hour
50 HP Tractor with trolley
d&e) Overheads & Contractors Profit
Cost for 10 m = a+b+c+d+e
Rate per m = (a+b+c+d+e)/10
Tubular Steel Railing on Precast RCC posts, 1.2 m high
above Ground Level

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

30.00
99.36

0.04

Providing, fencing and erecting 50 mm dia painted steel pipe railing


in 3 rows on precast M-20 grade RCC vertical posts 175 mm x 175
mm x 1.8 m high (1.2 m above Gl) with 3 holes 50 mm dia for pipe,
fixed 2 m centre-to- centre complete as per approved drawings
Clause 1706 MORD

Unit = Running m
Taking output = 10 m
i) Excavation for foundation (6 Nos.) 6 x 0.6 x 0.6 x 0.6
As per item No. 1 of Chapter 11

cum

1.296

cum

0.648

cum

0.32

sqm

4.71

day
day
day

0.364
0.01

m
t

30.00
0.032

hour

0.25

cum

0.252

cum

0.252

ii) Foundation concrete M-15 grade PCC 6 x 0.6 x 0.6 x 0.3

As per item No. 4 (A) (iii) or (iv) of Chapter 11


iii) RCC M20 for precast posts (6 nos.) of 1.8 m each
As per item No. 5 (A) (i) of Chapter 12
iv) Painting of pipe
As per item No.10.6 of this Chapter
a) labour (For fixing at site)
Mate
Mazdoor (Unskilled)
Plumber
b) Material
Steel pipe 50 mm external dia as per IS:1239
HYSD steel bars as per item No. 6 of Chapter 12
c) Machinery
50 HP Tractor with trolley
d&e) Overheads & Contractors Profit
Cost for 10 m = a+b+c+d+e
Rate per m = (a+b+c+d+e)/10
RBR-TSRA-20

20

Providing and Fixing 'Logo' of PMGSY Project


Providing and fixing of typical PMGSY informatory sign board with
Logo as per MORD specifications and drawing. Three MS Plates of
1.6 mm thick, top and middle plate duly welded with MS flat iron
25mm x 5m size on back on edges. The lower plate will be we
welded with MS angle irone frame of 25 mm x 25 mm x 5 mm. The
angle iron frame of the lower most plate and flat iron frame of middle
plate will be welded to 2 nos. 75 mm x 75 mm of 12 SWG sheet
tubes posts duly embedded in cement concrete M-15 grade blocks
of 450 mm x 450 mm x 600 mm, 600 mm below ground level. The
top most diamond plate will be welded to middle plate by 47 mm x
47mm of 12 SWG sheet tube. All M.s. will be stove enameled on
both sides. Lettering and printing arrows, border etc., will be pointed
with ready mixed synthetic enamel paint of superior quality in
required shade and colour. All sections of framed posts and steel
tube will be painted with primer and two coats of epoxy paint as per
drawing clause 1701 MORD

Unit = Each
Taking out put = one typical board
i) Excavation for foundation
As per item No. 1 of Chapter 11
(ii) Cement Concrete M15 grade
As per item No. 4 (A) (iii) or (iv) of Chapter 11

462

RBR-TSRA
Index-code

S. No

Description

Unit

Quantity

2
(iii) Painting on MS Steel tubes with primer and two coats of
epoxy paint

sqm

1.80

2x2.05x.30 = 1.23
1x1.10x188 = 0.21
As per item no. 9 of Chapter 10

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

(iv) Printing new letters and figures of any shade with synthetic
enamel paint black or any other approved colour to give an
even shade.

Logo Border 60x4x5 = 1200 per cm height per letter


Figure 60x10 = 600 per cm height per letter
Middle plate words 28x5 = 140 per cm height per letter
Bottom plate border 150x2x5 = 1500 per cm height per letter

Bottom plate border 60x2x5 = 600 per cm height per letter


Words 101x2.5 = 252.5
Words 80x3 = 240.00
Total (4532.5 per cm height per letter)
As per item No. 1 of Chapter 10

a) Labour (for fixing at site)


Mate
Mazdoor (Unskilled)
b) Material
2 nos. MS tubes 75mx75mm of 12 SWG sheet 2650 mm long

1 No. MS tube 47mm x 47mm of 12 SWG 1100 mm long


Angle iron 50mm x 50mm x 5 mm for lugs

per
4532.50
cm
height
/
letter
day
day

0.78

kg
kg
kg

63.15
4.47
2.12

1.6 mm thick MS sheet strengthened by 25mm x 5 MS flat iron on sqm


logo and middle plate angle iron 25mm x 25mm x 5mm on bottom
plate painting with stove enameled paint on both sides as per MORD
specifications
Add 3% cost of MS tube and angle iron towards the cost of
fabrications, drilling holes, nuts, bolts, etc.

1.44

c) Machinery
hour
0.24
Tractor with trolley
d&e) Overheads & Contractors Profit
Cost for one Board= (i+ii+iii+iv+a+b+c+d+e)
Printing and lettering for blank spaces on the lower plate will be written as required and paid
separately.
Items Suggested by MORTH
RBR-TSRA-21

21

Traffic Cone
Provision of red fluorescent with white reflective sleeve
traffic cone made of Low Density Polyethylene (LDPE)
material with a square base of 390 x 390 x 35 mm and a
height of 770 mm, 4 kg in weight, placed at 1.5 m interval,
all as per BS:873
Unit = Each
Taking output = 68 Nos.
a) Labour
Mate
Mazdoor (Unskilled)
b) Material
Traffic cones with 150 mm reflective sleeve
c) Machinery
50 HP Tractor with trolley
d&e) Overheads & Contractors Profit
Cost for 68 Nos. = a+b+c+d+e
Rate for each cone = (a+b+c+d+e)/68

day
day

0.52

Nos.

68.00

Hour

0.10

463

RBR-TSRA
Index-code

S. No

Description

Unit

Quantity

cum
cum
cum
cum
sqm

2.50

day
day
day
day

1.09
1.00
0.25

metre
metre
kg

3.50
10.00
8.00

hour

0.50

RBR-TSRA-22

22

RBR-TSRA-23

23

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

Rumble Strips (MORD)


Provision of 15 nos. rumble strips covered with premix
bituminous carpet, 15-20 mm high at centre, 250 mm wide
placed at 1 m centre-to-centre at approved locations to
control speed, marked with white strips of road marking
paint.
Unit = sqm
Taking output = 100 sqm (including gaps)
The rate per sqm of premix carpet and road marking may be
adopted from Chapters 5 & 10 respectively for the quantities
calculated from approved drawings.
A

Roadside Amenities
Rest areas
Providing plainly furnished accommodation for rest rooms,
dormitories, restaurants, stalls, shops, petrol pump, telephone booth,
first aid room, traffic aid post, police assistance booth, including
electricity, toilet and sewerage system
Pricing may be done based on current plinth area rates approved by
PWD/CPWD/MES for a particular zone. Area is required to be
assessed for specific location as per actual site conditions

B Parking areas and bus laybyes for trucks, buses and

light vehicles
Pricing of parking areas may be done for the quantities of various
items based on the approved dimensions and pavement design for a
particular terrain and soil. Rates for items may be from respective
chapters.
C Lawn

Providing a lawn planted with grass and its maintenance


Pricing of lawn may be done as per rates given in the
chapter on horticulture for the quantities as per approved
dimensions in the drawings
RBR-TSRA-24

24

Policeman Umbrella
Provision of a 2 m high (floor to roof) umbrella for traffic policeman at
road crossings, where necessary, installed on a raised platform, built
on a central support of a steel pipe 100 mm dia, roof made of 25 mm
dia steel pipe to provide covered area of 3 sqm, roofed with CGI
sheets, all steel parts to be given 2 coats of paint

Unit = each
Taking output = one number
Quantities of these items to be

Earthwork
calculated as per approved design
Cement Concrete
and cost added as per rates of
these items given in chapter 3 and
brick masonry or
13
stone masonry
Painting
a) Labour
Mate
Mazdoor
Blacksmith
Welder
b)
Material
Steel pipe 100 mm dia
Steel pipe 25 mm dia
CGI sheets
Add 25 per cent of cost of material for fabrication
Add 2 percent of cost of material for welding consumables,
J-hooks, washers etc.
c)
Machinery
Tractor-trolley
d&e) Overheads & Contractors Profit
Rate per policeman umbrella = a+b+c+d+e

464

RBR-TSRA
Index-code

S. No

Description

Unit

Quantity

RBR-TSRA-25

25

High Mast Pole Lighting at Interchanges and Flyovers


Providing and erecting a high mast pole lighting with 30 m
high hot dip galvanised mast designed to withstand forces
exerted with wind speeds of 180 km per hour with 3
seconds gust, as per IS:875 (Part 3) - 1978, fitted with a
base flange, door at the base of mast with heavy duty
internal lock, lantern carriage, suitable winching
arrangement for safe working load of 750 kg and high
powered electrically driven power tools for raising and
lowering of lantern carriage, flexible 8 core electric cable,
lightening conductor, earthing terminal, and fixing 2 nos
aviation obstruction lights on top of the mast, all complete
as per approved design and drawings
This is a specialised work and is generally done by firms
who specialise in such jobs. The detailed designs and
estimates are submitted by the firms along with their tender
for checks by the Department. The cost of this work is
required to be worked out based on approved design,
drawings and estimate of the lowest tender. A separate
contract for this work is concluded as the contractors for
road and bridge works generally donot undertake such jobs.

RBR-TSRA-26

26

Toll Plaza
The construction, operation and maintenance of Toll Plaza
can be broken into separate items of work as under based
on the approved design and drawings:-

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

a)
Provision of toll collection service lane to separate
different categories of vehicles for purpose of toll collection.
This involves considerable increase in carriage way width
b)
Provision of 2.5 m wide separators for different toll
collection service lanes for safety
c)
Toll booths with integrated roof cover
d)
Barrier gates for individual lanes
e)
Provision of building to provide facility to toll plaza
personnel
f)
Toll plaza office equipment and furniture
g)
Water supply, electricity, sanitation, septic-tank
system and drainage
h)
Telephone, intercomes, wireless communication
system
i)
High mast lighting
j) Pavement marking
k) Overhead signs
l) Fixed message signs (Advance)
m) Variable message signs
n) Traffic cones and pylons
o) First aid post
p) Traffic aid post and security
The quantities for the above mentioned items may be
calculated from the approved design and drawings and their
rates adopted from respective chapters of the Standard
Data Book

465

RBR-TSRA
Index-code

S. No
1

RBR-TSRA-27

27

Description

Unit

Quantity

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

Safety Devices and Signs in Construction Zones


Provision and fixing of traffic signs for limited period at
suitable locations in construction zone comprising of
warning zone, approach transition zone, working zone and
terminal transition zone with a minimum distance of 2-3 m
from the edge of the carriageway. the bottom edge of the
lowest sign plate to be not less than 2 m above the road
level, fixed on 600 mm x 600 mm x 6 mm angle iron post,
founded and installed as per approved design and
drawings, removed and disposed of adter completion of
construction work, all as per IRC : SP : 55-2001.
Unit = each
Taking output = one sign post
Following types of signs are required to be fixed in
construction zones for safety of traffic:
a) Diversion one km ahead
b) Traffic sign ahead
c) Road ahead closed
d) Men at work
e) Road narrow
f) Un-even road
g) Slippery road
h) Loose chippings
i) Diversion
j) Do not enter
k) Road closed
l) Stop
m) Slow
n) Speed limit
o) Single file traffic
p) Right Lane Diverted
q) Left Lane Diverted
r) Right Lane Closed
s) Left Lane Closed
t) Median closed
u) Diversion to other carriageway
v) Traffic signal ahead
w) Two way Traffic
x) Dual Carriageway ends
y) One way
z) Give way
aa) Over taking prohibited
bb) Wight limit
cc) Height & Length limit
dd) No Stopping or Standing
ee) Any other warning or regulatory safety signs as per site
requirement and consistent with IRC : SP:55-2001 & IRC:
Note
67 : The rate for traffic signs are already worked out and given
elsewhere in this Chapter. The same may be adopted.

RBR-TSRA-28

28

Road Markers/Road Stud with Lens Reflector


Providing and fixing of road stud 100 x 100 mm die cast in
aluminum, resistant to corrosive effect of salt and grit, fitted
with lense reflectors, installed in concrete or asphaltic
surface by drilling holes 30 mm upto a depth of 600 mm and
bedded in a suitable bituminous grout or epoxy mortar, all
as per BS:873 (Part 4) 1973.
Unit = each
Taking output = 50 Nos.
a) Labour
day
Mate
day
Mazdoor (Unskilled)

1.04

466

RBR-TSRA
Index-code

S. No

Description

Unit

Quantity

RBR-TSRA-29

29

b) Material
Nos.
Aluminum studs 100x100 mm fitted with lense reflectors
Add 10 per cent of cost of material for fixing and installation.
c&d) Overheads & Contractors Profit
Cost for 50 studs = a+b+c+d
Rate per stud = (a+b+c+d)/50
Cast in Situ Cement Concrete M20 Kerb

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

50.00

Construction of cement concrete kerb with top and bottom


width 115 and 165 mm respectively, 250 mm high in M 20
grade PCC on M-10 grade foundation 150 mm thick,
foundation having 50 mm projection beyond kerb stone,
kerb stone laid with kerb laying machine, foundation
concrete laid manually, all complete as per clause 408
MORTH
Unit = Running metre
Taking output = 360 metre
A Using Concrete Mixer

Cement Concrete
Cement concrete of grade M20 = 12.60 cum
Cement concrete of grade M10 for base= 11.61 cum
Total Concrete = 24.21 cu.m
a)

Labour

Mate

day

Mason

day

2.00

Mazdoor

day

16.72

b)

Machinery

Kerb casting machine @ 60 metres/hour

hour

6.00

Concrete mixer 0.48/0.28 cum capacity

hour

12.00

Water tanker 6 KL capacity

hour

5.00

cum

21.79

cum

10.90

c)

Material

Crushed stone aggregate 20 mm nominal size 59 %


Coarse sand 30 per cent
Cement 11 per cent
Cost of water

5.70

KL

30.00

d&e) Overheads & Contractors Profit


Cost for 360 meter = a+b+c+d+e
Rate per metre = (a+b+c+d+e)/360
B Using Concrete Batching and Mixing Plant

Cement Concrete
Cement concrete of grade M20 = 12.60 cum
Cement concrete of grade M10 for base = 11.61 cum
Total Concrete = 24.21 cu.m
a)

Labour

Mate

day

Mason

day

1.00

Mazdoor

day

2.12

Kerb casting machine @ 60 metres/hour

hour

6.00

Concrete batching and mixing plant @ 15 cum/hr.

hour

1.60

Water tanker 6 KL capacity

hour

5.00

Tipper 5.5 cum capacity

hour

6.00

cum
cum
t

21.79
10.90
5.70

b)

c)

Machinery

Material

Crushed stone aggregate 20 mm nominal size 59 %


Coarse sand 30 per cent
Cement 11 per cent

467

RBR-TSRA
Index-code

S. No

Description

Unit

Quantity

3
KL

4
30.00

Cost of water

RBR-TSRA-30

30

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

d&e) Overheads & Contractors Profit


Cost for 360 meter = a+b+c+d+e
Rate per metre = (a+b+c+d+e)/360
Cast in Situ Cement Concrete M 20 Kerb with Channel
Construction of cement concrete kerb with channel with top
and bottom width 115 and 165 mm respectively, 250 mm
high in M 20 grade PCC on M10 grade foundation 150 mm
thick, kerb channel 300 mm wide, 50 mm thick in PCCM20
grade, sloped towards the kerb, kerb stone with channel laid
with kerb laying machine, foundation concrete laid manually,
all complete as per clause 408 MORTH
A Using Concrete Mixer

Unit = Running metre


Taking output = 300 metre length
Cement Concrete
Cement concrete of grade M20= 17.48 cum
Cement concrete of grade M10 for base = 23.18 cum
Total Concrete = 40.66 cum
a)

Labour

Mate

day

Mason

day

2.00

Mazdoor

day

16.72

Kerb casting machine @ 50 metres/hour for laying kerb and hour


channel
hour
Concrete mixer 0.48/0.28
hour
Water tanker6 KL capacity
c)
Material
cum
Crushed stone aggregate 20 mm nominal size 60%
cum
Coarse sand 30 per cent

6.00

b)

Machinery

Cement 10 per cent


Cost of water

t
KL

16.00
6.00
36.59
18.30
9.01
36.00

d&e) Overheads & Contractors Profit


Cost for 360 meter = a+b+c+d+e
Rate per metre = (a+b+c+d+e)/300
B Using Concrete Batching and Mixing Plant

Unit = Running metre


Taking output = 300 metre length
Cement Concrete
Cement concrete of grade M20= 17.48 cum
Cement concrete of grade M10 for base = 23.18 cum
Total Concrete = 40.66 cum
a)

Labour

Mate

day

Mason

day

1.00

Mazdoor

day

2.12

Kerb casting machine @ 50 metres/hour for laying kerb and hour


channel
hour
Concrete batching and mixing plant @ 15 cum/hr.

6.00

Water tanker6 KL capacity

hour

6.00

Tipper of 5.5 cum capacity

hour

6.00

Crushed stone aggregate 20 mm nominal size 60 %

cum

36.59

Coarse sand 30 per cent

cum

18.30

b)

c)

Machinery

2.70

Material

468

RBR-TSRA
Index-code

S. No

Description

Unit

Quantity

3
t

4
9.01

KL

36.00

cum

3.00

Cement 10 per cent


Cost of water

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

d&e) Overheads & Contractors Profit


Cost for 300 meter = a+b+c+d+e
Rate per metre = (a+b+c+d+e)/300
RBR-TSRA-31

31

Reinforced Cement Concrete Crash Barrier


Provision of an Reinforced cement concrete crash barrier at
the edges of the road, approaches to bridge structures and
medians, constructed with M-20 grade concrete with HYSD
reinforcement conforming to IRC:21 and dowel bars 25 mm
dia, 450 mm long at expansion joints filled with pre-moulded
asphalt filler board, keyed to the structure on which it is built
and installed as per design given in the enclosure to MOST
circular No. RW/NH - 33022/1/94-DO III dated 24 June 1994
as per dimensions in the approved drawing and at locations
directed by the Engineer, all as specified 809 MORTH
Unit = Linear metre
Taking output = 10 m
(i) a) M 20 grade concrete
M 20 grade concrete
b)

Labour

Mate

day

Mazdoor

day

1.04

0.28

sqm

0.32

c)

Material

HYSD steel reinforcement including dowel bars


Pre-moulded asphalt filler board
d&e) Overheads & Contractors Profit
Cost for 10 metre = a+b+c+d+e
Rate per metre = (a+b+c+d+e)/10

RBR-TSRA-32

32

Note : i) Excavation and backfilling are incidental to work and not to be measured
separately.
ii) Rate for RCC M 20 may be taken from chapter on super structure.
Metal Beam Crash Barrier
A Type - A, "W" : Metal Beam Crash Barrier

Providing and erecting a "W" metal beam crash barrier


comprising of 3 mm thick corrugated sheet metal beam rail,
70 cm above road/ground level, fixed on ISMC series
channel vertical post, 150 x 75 x 5 mm spaced 2 m centre to
centre, 1.8 m high, 1.1 m below ground/road level, all steel
parts and fitments to be galvanised by hot dip process, all
fittings to conform to IS:1367 and IS:1364, metal beam rail
to be fixed on the vertical post with a spacer of channel
section 150 x 75 x 5 mm, 330 mm long complete as per
clause 810 MORTH
Unit = Running metre
Taking output = 4.5 metre length
a)

Labour

Mate

day

Blacksmith

day

0.50

Mazdoor

day

1.06

hour

0.10

kg

41.21

kg

88.56

kg

16.24

kg

20.00

b)

Machinery

Tractor-trolley
c)

Material

Corrugated sheet,3 mm thick, "W" beam section railing,4.5


m in length
Channel post 150 x 75 x 5 mm,1.8 m long,3 Nos @ 16.4 kg
per metre
Spacer 150 x 75 x 5 mm channel 0.33 m long, 3 Nos @
16.4 kg per metre
Nuts and bolts
Add 25 per cent of the cost of material for fabrication, nuts,
bolts and washers etc.)
d&e) Overheads & Contractors Profit
Cost for 4.5 metre = a+b+c+d+e
Rate per metre = (a+b+c+d+e)/4.5
B Type - B, "THRIE" : Metal Beam Crash Barrier
Providing and erecting a "Thrie" metal beam crash barrier
comprising of 3 mm thick corrugated sheet metal beam rail, 85 cm
above road/ground level, fixed on ISMC series channel vertical post,
150 x 75 x 5 mm spaced 2 m centre to centre, 2 m high with 1.15 m
below ground level, all steel parts and fitments to be galvanised by
hot dip process, all fittings to conform to IS:1367 and IS:1364, metal
beam rail to be fixed on the vertical post with a space of channel
section 150 x 75 x 5 mm, 546 mm long complete as per clause 810
MORTH

Unit = Running metre

469

RBR-TSRA
Index-code

S. No

Description

Unit

Quantity

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

Taking output = 4.5 metre length


a)

Labour

Mate

day

Blacksmith

day

0.50

Mazdoor

day

1.06

hour

0.10

kg

72.94

kg

98.40

kg
kg

26.86
30.00

b)

Machinery

Tractor-trolley
c)

Material

Corrugated sheet,3 mm thick, "Thrie" beam section


railing,4.5 m in length
Channel post 150 x 75 x 5 mm, 2 m long,3 Nos @ 16.4 kg
per metre
Spacer 150 x 75 x 5 mm channel 0.546 m long,3 Nos
Nuts and bolts
Add 15 per cent of the cost of material for fabrication, nuts,
bolts and washers etc.)
d&e) Overheads & Contractors Profit
Cost for 4.5 metre = a+b+c+d+e
Rate per metre= (a+b+c+d+e)/4.5

Note : In the case of median crash barrier, 'W' metal beam or thrie beam section should be provided on
both sides of the vertical posts fixed in the median. Extra provision for metal beam railing and spacer is
required to be made when fixed in the median depending on approved design.

RBR-TSRA-33

33

Road Traffic Signals electrically operated


Note : Since it is a ready made item commercially produced and erected by specialised firm in the
electrical and electronic field, rate may be taken based on market enquiry from firms specialised in this
field and ISI certified for the approved design and drawing.

RBR-TSRA-34

34

Flexible Crash Barrier, Wire Rope Safety Barrier (Suggestive)


Providing and erecting a wire rope safety barrier with vertical posts of medium weight RS Joist (ISMB
series) 100 mm x 75 mm (11.50 kg/m), 1.50 m long 0.85 m above ground and 0.65 m below ground level,
split at the bottom for better grip, embedded in M 15 grade cement concrete 450 x 450 x 450 mm, 1.50 m
center to center and with 4 horizontal steel wire rope 40 mm dia and anchored at terminal posts 15 m
apart. Terminal post to be embedded in M 15 grade cement concrete foundation 2400 x 450 x 900 mm
(depth), strengthened by a strut of RS joist 100 x 75 mm, 2 m long at 450 inclination and a tie 100 x 8
mm, 1.50 m long at the bottom, all embedded in foundation concrete as per approved design and
drawing, rate excluding excavation and cement concrete.

Unit = Running metre


Taking output = 15 metre
a) Labour
Mate
Mazdoor

day
day

2.12

470

RBR-TSRA
Index-code

S. No

Description

Unit

Quantity

3
day

4
1.00

kg

190.00

kg
kg

46.00

Blacksmith
b) Material
i) RS Joist 100 x 75 mm - 16.5 m @ 11.5 kg per metre
ii) Struts - 2 Nos. for terminal posts,2 m long each 2 x 2 x 11.50

RBR-TSRA-35

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

188.40
iii) Tie 2 Nos. of 8 mm steel plate,1.5 sqm each for terminal
posts @ 62.80 kg/sqm (2 x 1.5)
65.00
iv) Steel wire rope 40 mm, including 7.50 per cent extra for kg
fixing at ends 15 x 4 x 1.075 @ 1 kg per m
Add 5 per cent of cost of material for drilling, gripping,
fixing, fabrication and welding consumables
c)
Painting
sqm
16.50
Applying 2 coats of painting on exposed surface
d)
Machinery
hour
0.25
Tractor-trolley
e&f) Overheads & Contractors Profit
Cost for 15 m = a+b+c+d+e+f
Rate per m = (a+b+c+d+e+f)/15
Note : The items of excavations and cement concrete works will
be measured and included separately as per the approved designs
and drawings.
35 8.3 Anti-Glare Devices in Median
A Plantation
Plantation of shrubs and plants of approved species in the median.
apart from cutting off glare from vehicle coming from opposite
direction, these plants provide a pleasant environment and are ecofriendly. The rate for this item is available in the chapter 11 on
horticulture.
B Anti-glare screen with 25 mm steel pipe framework fixed with
circular and rectangular vans
Providing and erecting an anti - glare screen with 25 mm dia
vertical pipes fabricated and framed in the form of panels of one
metre length and 1.75 metre height fixed with circular vane 250
mm dia at top and rectangular vane 600 x 300 mm at the middle,
made out of steel sheet of 3 mm thickness, end vertical pipes of
the panel made larger for embedding in foundation concrete,
applying 2 coats of paint on all exposed surfaces, all as per
approved design and drawings.

Unit = Running metre


Taking output = one metre
a)

Labour

Mate

day

Mazdoor

day

0.104

metre

16.00

kg

4.32

kg

4.80

sqm

1.83

b)

Material

i) 25 mm steel pipe
ii) MS sheet for 600 x 300 x 3 mm rectangular vane, one
number @ 24kg/sqm
iii) MS sheet for 250 mm dia circular vane 3 mm thick, 4
numbers @ 24 kg/sqm
Add 5 per cent cost of material for fabrication, welding,
bending, nuts, bolts etc
c)
Painting
Applying 2 coats of painting on exposed surface
d&e) Overheads & Contractors Profit
Rate per metre = a+b+c+d+e

Note : The items of excavation and cement concrete as per


approved design to be measured and paid separately

471

RBR-TSRA
Index-code

S. No
1

Description

2
C Anti-glare screen with rectangular vane of MS sheet

Unit

Quantity

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

Providing and erecting anti - glare screen with rectangular vanes of


size 750 x 500 mm made from MS sheet, 3 mm thick and fixed on
MS angle 50 x 50 x 6 mm at an angle of 450 to the direction of flow
of traffic, 1.5 m center to center, top edge of the screen 1.75 m
above ground level, vertical post firmly embedded in M-15 cement
concrete foundation 0.60 m below ground level, applying 2 coats of
paint on exposed faces, all complete as per approved design and
drawings

Unit = Running metre


Taking output = 1.50 metre
a)

Labour

Mate

day

Mazdoor

day

0.104

kg
kg

10.58
9.00

hour

0.10

sqm

0.85

b)

Material

i) Angle iron post,50 x 50 x 6 mm, length 2.35 m


ii) MS sheet 3 mm thick @ 24 kg/sqm
Add 5 % of cost of material for fabrication, nuts, bolts etc

c)

Machinery

Tractor-trolley
d)

Painting

Applying 2 coats of painting


e&f) Overheads & Contractors Profit
Cost for 1.5 m = a+b+c+d+e+f
Rate per metre = (a+b+c+d+e+f)/1.50

Note : The items of excavation and cement concrete as per approved


design to be measured and paid separately. Rate of painting has been
analaysed separately in this chapter.

RBR-TSRA-36

36

Street Lighting
Providing and erecting street light mounted on a steel circular hollow
pole of standard specifications for street lighting, 9 m high spaced 40
m apart, 1.8 m overhang on both sides if fixed in the median and on
one side if fixed on the footpath, fitted with sodium vapour lamp and
fixed firmly in concrete foundation.

Unit = Each
Taking output = one light
a) Labour
Mate
Mazdoor
Electrician

day
day
day

0.53
0.25

i) Steel circular hollow pole of standard specification for street each


lighting to mount light at 9 m height above road level
each
ii) Sodium vapour lamp

1.00

b)

Material

1.00

Add 5 per cent of cost of material for holder, electric cable,


insulation, ladder, scaffolding etc
c)
Painting
For Fixing in Median
Providing two coats of aluminum paint over steel circular sqm
hollow pipe with overhang on both sides
For fixing in Footpath

5.75

Providing two coats of aluminum paint over steel circular sqm


hollow pipe with overhang on one side
(i) For Fixing in Median

4.63

d&e) Overheads & Contractors Profit


Rate per light for fixing in Median= a+b+c+d+e
(ii) For fixing in Footpath
Rate per light for Fixing in Footpath = a+b+c+d+e
Note : The items of excavation and cement concrete foundation will be measured and included
separately in the estimate as per approved design and drawing. The rate for painting has been analysed
in this chapter.

472

RBR-TSRA
Index-code

S. No

Description

Unit

Quantity

RBR-TSRA-37

37

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

Lighting on Bridges
Providing and fixing lighting on bridges, mounted on steel
hollow circular poles of standard specifications, 5 m high
fixed on parapets with cement concrete, 20 m apart and
fitted with sodium vapour lamp
Unit = Each
Taking output = one light
a)

Labour

Mate

day

Mazdoor

day

0.42

Electrician

day

0.20

i) Steel circular hollow pole of standard specification for each


street lighting to mount light at 5 m above deck level
each
ii) Sodium vapour lamp 70 watt

1.00

b)

Material

1.00

Add 1 per cent of cost of material for holder, electric cable,


insulation, ladder, scaffolding etc
c)
Painting
Providing two coats of aluminum paint over steel circular sqm
hollow pipe
d&e) Overheads & Contractors Profit
Rate per light = a+b+c+d+e

RBR-TSRA-38

2.76

Note : The items of cement concrete to be measured and paid


separately as per approved design. The rate for painting has
already been analysed in this chapter.
Cable Duct Across the Road

38

Providing and laying of a reinforced cement concrete pipe duct, 300


mm dia, across the road (new construction), extending from drain to
drain in cuts and toe of slope to toe of slope in fills, constructing
head walls at both ends, providing a minimum fill of granular material
over top and sides of RCC pipe as per IRC:98-1997, bedded on a
0.3 m thick layer of granular material free of rock pieces, outer to
outer distance of pipe at least half dia of pipe subject to minimum
450 mm in case of double and triple row ducts, joints to be made
leak proof, invert level of duct to be above higher than ground level
to prevent entry of water and dirt, all as per IRC: 98 - 1997 and
approved drawings.
i

Single row for one utility service


Unit = Running metre
Taking output = 20metres
a) Random Rubble masonry/Brick masonry in cement cum
mortar 1:6 for head wall both side (11.6 in Chapter 11)
b)

2.36

Labour

Mate

day

Mazdoor

day

1.00

Mazdoor skilled

day

0.30

metre

20.00

c)

Material

Reinforced Cement Concrete pipe 300 mm dia NP2

Granular soil with PI less than 6 for bedding and sides of cum
pipe (0.6 x 0.6 x 20 m)

7.20

Collar for joints 300 mm dia

each

9.00

Cement mortar 1:2 for joints (Rate as in Sub analysis)

cum

0.02

hour

0.50

d)

Machinery

Tractor-trolley
e&f) Overheads & Contractors Profit
Cost for 20 metre = a+b+c+d+e+f
Rate per metre = (a+b+c+d+e+f)/20

473

RBR-TSRA
Index-code

S. No

Description

Unit

Quantity

1
ii

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

Double row for two utility services


Unit = Running metre
Taking output = 20metres
a) Random Rubble brick/Brick masonry in cement cum
mortar 1:6 for head wall both sides.
b)

3.37

Labour

Mate

day

Mazdoor

day

2.00

Mazdoor skilled

day

0.30

metre

40.00

c)

Material

Reinforced Cement Concrete pipe 300 mm dia

Granular soil with PI less than 6 for bedding and sides of cum
pipe (0.6 x 0.6 x 40 m)

14.40

Collar for joints 300 mm dia

each

18.00

Cement mortar 1:2 for joints (Rate as in Sub analysis)

cum

0.04

hour

1.00

a) Random Rubble brick/Brick masonry in cement cum


mortar 1:6 for head wall both sides.

4.38

d)

Machinery

Tractor-trolley
e&f) Overheads & Contractors Profit
Cost for 20 metre = a+b+c+d+e+f
Rate per metre = (a+b+c+d+e+f)/20
iii Triple Row for three utility services

Unit = Running metre


Taking output = 20metres

b)

Labour

Mate

day

Mazdoor

day

3.00

Mazdoor skilled

day

1.16

metre

60.00

c)

Material

Reinforced Cement Concrete pipe 300 mm dia

Granular soil with PI less than 6 for bedding and sides of cum
pipe (0.6 x 0.6 x 60 m)

21.60

Collar for joints 300 mm dia

each

27.00

Cement mortar 1:2 for joints (Rate as in Sub analysis)

cum

0.06

hour

1.50

d)

Machinery

Tractor-trolley
e&f) Overheads & Contractors Profit
Cost for 20 metre = a+b+c+d+e+f
Rate per metre = (a+b+c+d+e+f)/20

Note : 1. Inspection chamber at both ends is the responsibility of the agency who is laying
the duct. Hence not included.
2. The rates for stone masonry / brick masonry and cement mortar to be adopted from
respective clauses.
Sub Analysis :
Cement Mortar 1:2
Unit = cum
(a) Material
t
0.72
Cement
cum
1.05
Sand
(b) Labour
day
Mate
day
0.2
Mazdoor (Unskilled)
day
Bhisti
Total material and labour = (a+b)

474

RBR-TSRA
Index-code

S. No

Description

Unit

Quantity

day
day
day

2.12
1.00

Aluminum alloy/galvanised steel including 5 % wastage


Add 15 % of cost of material for fabrication and erection.
Add 1% of cost of material for nuts, bolts and welding
c)
Machinery

tonne

1.05

Truck 10 tonne

hour

1.00

RBR-TSRA-39

39

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

Highway Patrolling and Traffic Aid Post


It is proposed to locate one Traffic Aid Post every 50-60 km
of the highway.
The organisation and financial aspect are required to be
finalised in consultation with administrative and traffic
authorities .

40

Items Related to Underpass/ Subway/ Overhead Bridge/


Overhead Foot Bridge

RBR-TSRA-40

The items involved for underpass/ subway/ overhead bridge/


overhead foot bridge are earthwork, plain cement concrete,
plastering, painting, information sign etc. The rates for these
items are available in respective chapters which can be
adopted for the quantities derived from the approved
designs and drawings
RBR-TSRA-41

41

Traffic Control System and Communication System


Providing a traffic control centre and communication system
including
telecommunication
facilities
and
related
accessories, CCTV, radar, vehicle detection camera, central
computer system
These are specialised item of telecommunication system and are the
commercial products. The designer is required to contact the
manufacturers to ascertain market prices. In case of civil works
required to be executed for these installations, pricing may be done
as per rates in relevant chapters for quantities derived as per
approved design and drawing.
As regards the locations where such devices are required to be
installed, the traffic control authority should be consulted to finalise
the location

42

Gantry Mounted Variable Message Sign Board

iii

RBR-TSRA-42

Providing and erecting gantry mounted variable message


sign board electronically operated capable of flashing the
desired message over a designed support system of
aluminum alloy or galvanised steel, erected as per approved
design and drawings and with lateral clearance as per
clause 802.3
Gantry Support System
Unit = tonne
Taking output=1 tonne
a) Labour
Mate
Mazdoor
Blacksmith
b)
Material

d&e) Overheads & Contractors Profit


Rate per tonne = a+b+c+d+e
iii Message Display
Message display board 6 sqm electronically operated with complete
electronic fitments for flashing the pre-determined messages.
This is a specilised commercial product and the lumpsum rate
including erection at site is required to be as certained from the
market and including in the rate analysis. The size of the board will
vary depending upon specific location.
The rate for the gantry mounted variable sign would be the addition
of cost of gantry support system as per approved design determined
at (i) above and the cost of message display board as certained from
the market at (ii) above

475

RBR-TSRA
Index-code

S. No

Description

Unit

Quantity

RBR-TSRA-43

43

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

Traffic Impact Attenuators at Abutments and Piers


A With Scrap Tyres

Provision and installation of traffic attenuators at


abutment/pier of flyovers bridges using scrap tyres of size
100 x 20 retrieved from trucks laid in 2 rows and 4 tiers, one
above the other and tied with 20 mm wire rope as per
approved design and drawings.
Unit = sqm
Taking output = 20sqm
a)

Labour

Mate

day

Mazdoor

day

1.58

Blacksmith

day

0.25

b)

Material

Scrap tyres of size 900 x 20


20 mm steel wire rope

each

80.00

kg

150.00

hour

3.00

day
day
day

3.13
0.25

each

50.00

each
cum
kg

50.00
8.00
15.00

hour

2.00

day
day

2.60

each
KL
kg

40.00
12.00
100.00

Add 1 per cent of cost of wire rope for clamps etc.


c)

Machinery

Tractor-trolley
d&e) Overheads & Contractors Profit
Cost for 20 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/20
B Using Plastic/Steel Barrel, Filled with Sand
Provision and installation of traffic impact attenuator at abutment/pier
of flyovers bridges using plastic/steel barrels 0.60 m dia and 1.0 m in
height, filled with sand in three rows and tied with20 mm steel wire
rope as per approved design and drawings

Unit = sqm
Taking output = 20sqm
a) Labour
Mate
Mazdoor
Blacksmith
b)
Material
Plastic barrels
or
Steel barrels
Sand
20 mm steel wire rope
Add 1 per cent of cost of wire rope for clamps etc.
c)
Machinery
Tractor-trolley
d&e) Overheads & Contractors Profit
Cost for 20 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/20
C With HI - DRO cell Sandwich (Patented)
(In this patented HI - DRO cell system, water gets discharged from
plastic tubes on impact over a pre-determined time, thus absorbing
the energy)
Providing and installing a patentend HI - DRO cell system as a traffic
impact attenuators, using plastic tubes 50 cm dia, 1.2 m in height, 25
mm opening at the top, placed in three rows, filled with water and
tied with a 20 mm steel wire rope

Unit = sqm
Taking output = 10sqm
a) Labour
Mate
Mazdoor
b)

Material

Plastic tubes 50 cm dia,1.2 m high


Cost of water
20 mm steel wire rope

476

RBR-TSRA
Index-code

S. No
1

RBR-TSRA-44

Description

Unit

Quantity

hour
hour

2.00
2.00

day
day
day
day

0.02
0.25
0.50
0.25

kg
kg
litre

25.00
15.00
0.50

Add 1 per cent of cost of wire rope for clamps etc.


c)
Machinery
Tractor-trolley
Water tanker6 KL capacity
d&e) Overheads & Contractors Profit
Cost for 10 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/10
Portable Barricade in Construction Zone

44

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

Installation of a steel portable barricade with horizontal rail


300 mm wide, 2.5 m in length fitted on a 'A' frame made
with 45 x 45 x 5 mm angle iron section, 1.5 m in height,
horizontal rail painted (2 coats) with yellow and white
stripes, 150 mm in width at an angle of 450, 'A' frame
painted with 2 coats of yellow paint, complete as per
IRC:SP:55-2001
Unit = each
Taking output = one steel portable barricade
a)

Labour

Mate
Mazdoor
Painter
Welder
b)
Material
Angle iron 45 x 45 x 5 mm
MS sheet 300 mm wide,2.5 m long and 2.6 mm thick
Paint
Add 2 per cent of cost of steel for welding consumables,
nuts & bolts and drilling holes
c&d) Overheads & Contractors Profit
Rate per barricade = a+b+c+d
RBR-TSRA-45

45

Permanent Type Barricade in Construction Zone


A

With steel components+C1454


Construction of a permanent type barricade made of steel
components, 1.5 m high from road level, fitted with 3
horizontal rails 200 mm wide and 4 m long on 50 x 50 x 5
mm angle iron vertical support, painted with yellow and
white strips, 150 mm in width at an angle of 450, complete
as per IRC:SP:55-2001
Unit = each
Taking output = one barricade
a)

Labour

Mate

day

Mazdoor

day

0.35

Painter

day

0.60

Welder

day

0.30

kg
kg
litre

15.00
50.00
1.00

b)

Material

Angle iron 50 x 50 x 5 mm, 2 m long, 2 Nos.


MS sheet of 12 SWG,3 Nos of 200 mm width and 4 m length

Paint
Add 1 per cent of cost of steel for welding consumables,
nuts & bolts and drilling holes
c&d) Overheads & Contractors Profit
Rate per barricade = a+b+c+d

477

RBR-TSRA
Index-code

S. No

Description

Unit

Quantity

day
day
day
day

0.35
0.60
0.60

cum

0.18
1.00%

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

B With wooden components


Construction of a permanent type barricade made of wooden
components, 1.5 m high from road level, fitted with 3 horizontal
planks 200 mm wide and 3.66 m long on 100 x 100mm wooden
vertical post, painted with yellow and white strips, 150 mm in width
at an angle of 450, complete as per IRC:SP:55-2001

Unit = each
Taking output = one barricade
a) Labour
Mate
Mazdoor
Painter
Carpenter
b)
Material
Timber
Add 1percent of cost of timber for nuts & bolts, nails, etc.
c&d) Overheads & Contractors Profit
Rate per barricade = a+b+c+d
C With bricks
Construction of a permanent type barricade made with brick
work in mud mortar, 1.5 m high, 4 m long, 600 mm thick,
plastered with cement mortar 1:6, painted with yellow and
white strips
Unit = each
Taking output = one barricade
a)

Labour

Mate

day

Mazdoor

day

3.24

Painter

day

1.00

Mason

day

2.00

each

1800.00

kg

22.00

Sand

cum

0.09

Paint

litre

1.25

b)

Material

Brick
Cement

c&d) Overheads & Contractors Profit


Rate per barricade = a+b+c+d
RBR-TSRA-46

46

Drum Delineator in Construction Zone


Provision of metal drum/empty bitumen drum delineator,
300 mm in diameter, 800 mm high, filled with earth for
stability, painted in circumferential strips of alternate black
and white 100 mm wide fitted with reflectors 3 Nos of 7.5 cm
dia, all as per IRC:SP:55-2001
Unit = each
Taking output = one drum delineator
a)

Labour

Mate

day

Mazdoor

day

0.27

Painter

day

0.25

Steel drum 300 mm dia 1.2 m high/empty bitumen drum

each

1.00

Paint

litre

0.50

b)

Material

c&d) Overheads & Contractors Profit


Rate per drum delineator = a+b+c+d

478

RBR-TSRA
Index-code

S. No

Description

Unit

Quantity

day
day

1.04

each
each

1.00
1.00

RBR-TSRA-47

47

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

Flagman
Positioning of a smart flagman with a yellow vest and a yellow cap
and a red flag 600 x 600 mm securely fastened to a staff 1 m in
length for guiding the traffic

Unit = each
Taking output = one flagman
a) Labour
Mate
Mazdoor
b)
Material
Flag of red color cloth 600 x 600 mm
Wooden staff for fastening of flag 25 mm dia, one m long

c&d) Overheads & Contractors Profit


Rate per flagman = a+b+c+d

BARRICADING ARRANGEMENTS - MADE BY R&B DEPT


48

RBR-TSRA-48

Providing barricading arrangements with casuria posts for vertical to


be fixed at 3 mts (10'.0") intervals duly excavating a pitt fixing the
vertical post firmly in the pit with excavated earth and metal for
additional gap, tying two horizontal casuarinas posts to the verticals
with coconut rope firmly. Dismantling the barricading after the
programmed including conveyance of all material, all labour charges,
hire charges of casurina posts, cost of coconut rope and all other
incidental charges etc., complete for finished item of work and as
directed by the Engineer-in- Charge.

2 TIER FOR 2 DAYS :


Labour charges for digging pits fixing vertical post in the
excavated earth using crow bars for additional grip, tying
horizontal posts two rows with coconut ropes firmly as
directed by the departmental officer and dismantling the
entire work after the programme is over.
day
Mazdoor (Unskilled)
Hire charges of vertical posts (2M long) Rs. 1.00 per day
I.E., 2daysX1.00
Hire charges of horizontal post of 4M long 100/4=25X2=50
Nos Rs. 2.50 per day I.e., 2X2.50
Cost of coconut rope (55X2X2.00M=220RM)
Conveyance of vertical posts and horizontal posts including
loading and unloading at site and vice versa for two
operations.(55+50)
Mazdoor's (Unskilled) (NMR) for maintenance of
barricading such as refixing fallen posts if any in position
including watch and ward-3 shifts at 3 Nos. for each shift (1
no. for 600RM) 9/1800X2daysX100M=1No

9.000

Each

34.000

Each

50.000

RM
Each

220.000
84.000

1.000

Rate per 100 RM


Rate per 1RM

49

RBR-TSRA-49

Total
Providing barricading arrangements with casuria posts for vertical to
be fixed at 3 mts (10'.0") intervals duly excavating a pit fixing the
vertical post firmly in the pit with excavated earth and metal for
additional gap, tying three horizontal casuarina posts to the verticals
with coconut rope firmly. Dismantling the barricading after the
programme including conveyance of all material, all labour charges,
hire charges of casurina posts, cost of coconut rope and all other
incidental charges etc., complete for finished item of work and as
directed by the Engineer -in- Charge.

3 TIER FOR 2 DAYS :


Labour charges for digging pits fixing vertical post in the excavated
earth using crow bars for additional grip, tying horizontal posts two
rows with coconut ropes firmly as directed by the departmental
officer and dismantling the entire work after the programme is over.

Mazdoor (Unskilled)
For tying third horizontal row
Mazdoor (Unskilled)

day

9.000

day

1.000

479

RBR-TSRA
Index-code

S. No
1

Description

Unit

Quantity

4
34.000

Hire charges of vertical posts (2M long) Rs. 1.00 per day
I.E., 2daysX1.00
Hire charges of horizontal post of 4M long 100/4=25X3=75
Nos Rs. 2.50 per day I.e., 2X2.50
RM
Cost of coconut rope (55X3X2.00M=330RM)
Conveyance of vertical posts and horizontal posts including Each
loading and unloading at site and vice versa for two
operations.(55+75)
Mazdoor's (Unskilled) (NMR) for maintenance of
barricading such as refixing fallen posts if any in position
including watch and ward-3 shifts at 3 Nos. for each shift (1
no. for 600RM) 9/1800X2daysX100M=1No
Rate per 100 RM
Rate per 1RM
50

RBR-TSRA-50

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

75.000
330.000
130.000

1.000

Providing barricading arrangements with casuria posts for vertical to


be fixed at 3 mts (10'.0") intervals duly excavating a pitt fixing the
vertical post firmly in the pit with excavated earth and metal for
additional gap, tying two horizontal casuarina posts to the verticals
with coconut rope firmly. Dismantling the barricading after the
programme including conveyance of all material, all labour charges,
hire charges of casurina posts, cost of coconut rope and all other
incidental charges etc., complete for finished item of work and as
directed by the Engineer -in- Charge.

2 TIER FOR 15 DAYS :


Labour charges for digging pits fixing vertical post in the
excavated earth using crow bars for additional grip, tying
horizontal posts two rows with coconut ropes firmly as
directed by the departmental officer and dismantling the
entire work after the programme is over.
Mazdoor (Unskilled)
Hire charges of vertical posts (2M long) for 15 days at Rs.
1.00 per day
Hire charges of horizontal post of 4M long for 15 days at
Rs.2.50 per day 100/4=25X2=50 Nos
Cost of coconut rope (55X2X2.00M=220RM)
Conveyance of vertical posts and horizontal posts including
loading and unloading at site and vice versa for two
operations.(55+50)

day
Each

9.000
55.000

Each

50.000

RM
Each

220.000
105.000

Mazdoor's (Unskilled) (NMR) for maintenance of barricading such


as refixing fallen posts if any in position including watch and ward-3
shifts at 3 Nos. for each shift (1 no. for 600RM)
2X9/1800X15daysX100M=15 Nos

15.000

Compensation for damaged posts


Rate per 100 RM
Rate per 1RM
51

RBR-TSRA-51

Providing barricading arrangements with casuria posts for vertical to


be fixed at 3 mts (10'.0") intervals duly excavating a pitt fixing the
vertical post firmly in the pit with excavated earth and metal for
additional gap, tying two horizontal casuarina posts to the verticals
with coconut rope firmly. Dismantling the barricading after the
programme including conveyance of all material, all labour charges,
hire charges of casurina posts, cost of coconut rope and all other
incidental charges etc., complete for finished item of work and as
directed by the Engineer -in- Charge.

3 TIER FOR 15 DAYS :


Labour charges for digging pits fixing vertical post in the excavated
earth using crow bars for additional grip, tying horizontal posts two
rows with coconut ropes firmly as directed by the departmental
officer and dismantling the entire work after the programme is over.
day
Mazdoor (Unskilled)
For tying third horizontal row
day
Mazdoor (Unskilled)
Hire charges of vertical posts (2M long) Rs. 1.00 per day Each
I.E., 15daysX1.00
Hire charges of horizontal post of 4M long 15 days at Rs. Each
2.50 per day 100/4=25X3=75 Nos
RM
Cost of coconut rope (55X3X2.00M=330RM)
Conveyance of vertical posts and horizontal posts including loading Each
and unloading at site and vice versa for two operations.(55+75)
Mazdoor's (Unskilled) (NMR) for maintenance of barricading such
as refixing fallen posts if any in position including watch and ward-3
shifts at 3 Nos. for each shift (1 no. for 600RM)
2X9/1800X15daysX100M=15 Nos

9.000
1.000
55.000
75.000
330.000
130.000

15.000

Compensation for damaged posts


Rate per 100 RM
Rate per 1RM

480

RBR-TSRA
Index-code

S. No
1
52

RBR-TSRA-52

Description

Unit

2
3
Providing barricading arrangements with iron posts (Departmental
Material) for vertical to be fixed at 3 mts (10'.0") intervals duly
excavating a pit fixing the vertical post firmly in the pit with excavated
earth and metal for additional gap, fixing three horizontal iron posts to
the verticals with bolts & nuts firmly. Dismantling the barricading after
the programme including conveyance of all material, all labour
charges, cost of bolts and nuts and all other incidental charges etc.,
complete for finished item of work and as directed by the Engineer -inCharge.

Quantity
4

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

3 TIER FOR 2 DAYS :

Labour charges for digging pits fixing vertical post in the excavated
earth using crow bars for additional grip, tying horizontal posts two
rows with bolts & nuts firmly as directed by the departmental officer
and dismantling the entire work after the programme is over.
day
Mazdoor (Unskilled)
Cost of bolts and nuts for fixing horizontal posts to vertical Each
posts.(55X3=165 Nos)
Mazdoor's (Unskilled) (NMR) for maintenance of barricading such
as refixing fallen posts if any in position including watch and ward-3
shifts at 3 Nos. for each shift (1 no. for 600RM)
9/1800X2daysX100M=1No

Conveyance of iron posts from stock place to various points


of barricading
Rate per 100 RM
Rate per 1RM

53

RBR-TSRA-53

8.000
165.000
1.000

LS

Providing barricading arrangements with iron posts (Departmental


Material) for vertical to be fixed at 3 mts (10'.0") intervals duly
excavating a pit fixing the vertical post firmly in the pit with excavated
earth and metal for additional gap, fixing three horizontal iron posts to
the verticals with bolts & nuts firmly. Dismantling the barricading after
the programme including conveyance of all material, all labour
charges, cost of bolts and nuts and all other incidental charges etc.,
complete for finished item of work and as directed by the Engineer -inCharge.

3 TIER FOR 15 DAYS :


Labour charges for digging pits fixing vertical post in the excavated
earth using crow bars for additional grip, tying horizontal posts three
rows with bolts & nuts firmly as directed by the departmental officer
and dismantling the entire work after the programme is over.
day
Mazdoor (Unskilled)
Cost of bolts and nuts for fixing horizontal posts to vertical Each
posts.(55X3=165 Nos)
Mazdoor's (Unskilled) (NMR) for maintenance of barricading such
as refixing fallen posts if any in position including watch and ward-3
shifts at 3 Nos. for each shift (1 no. for 600 RM)
9/1800X15daysX100M=7.5 No
Conveyance of iron posts from stock place to various points of
barricading

8.000
165.000
7.500

LS

Rate per 100 RM


Rate per 1RM
General Note :
The provisions towards Mate is included in the provision towards unskilled Mazdoor.

481

RBR_FNDN

Andhra Pradesh Standard Data


I. Roads and Bridges

Chapter - 11
FOUNDATION
Index-code

RBR-FNDN-1

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

Excavation for Structures


Earthwork in excavation for structures as per drawing and
technical specifications Clause 305.1 including setting out,
construction of shoring and bracing, removal of stumps and
other deleterious material and disposal upto a lead of 50 m,
dressing of sides and bottom and backfilling in trenches with
excavated suitable material as per Technical Specification
305 MORD / 304 MORTH
Note : Classifications of Earth Work Specification are as
per 302.2.1(a) of MORD and 301.2.1 of MORT&H
(I) Ordinary soil
(A) Manual Means
(i) Upto 3 m depth
Unit = cum
Taking output = 10 cum
a) Labour
day
Mate
day
Mazdoor (Unskilled)
b&c) Overheads & Contractors Profit
Cost for 10 cum = a+b+c
Rate per cum = (a+b+c)/10

3.64

Note : 1. Cost of dewatering may be added, where required, up to 5 per cent of labour cost. Assessment
for dewatering shall be made as per site conditions.
2. The cost of shoring and shuttering, where needed, may be added on cost of excavation for open
foundation.
3. The excavated earth if found suitable, can be used partly for backfilling in trenches & partly for road work.
Hence cost of disposal has not been added except for marshy soil. This note is common to all cases of
item 11.1 excluding 11.1 V
(B) Mechanical Means
i

Upto 3 m depth
Unit = cum
Taking output = 240 cum
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Hydraulic Excavator 1 cum bucket capacity
c&d) Overheads & Contractors Profit
Cost for 240 cum = a+b+c+d
Rate per cum = (a+b+c+d)/240

day

day

8.32

hour

6.00

Note : 1. Cost of dewatering upto 5% of a+b may be added, where required, up to 10 per cent of labour
cost. Assessment for dewatering shall be made as per site conditions.
ii

3 m to 6 m depth
Unit = cum
(A) Manual Means
a) Labour
Mate / Supervisor
Mazdoor (Unskilled)
b&c) Overheads & Contractors Profit
Cost for 10 cum = a+b+c
Rate per cum = (a+b+c)/10

day

day

4.68

Note : 1. Cost of dewatering may be added, when needed, up to 5 per cent of labour cost.
2. Cost of shoring and shuttering, where needed, may be taken @ 10 per cent on cost of excavation for
open foundation.

484

RBR_FNDN

Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

1
B

Mechanical Means
Unit = cum
Taking output = 210 cum
a) Labour
Mate

day

Mazdoor (Unskilled)

day

8.32

b)
Machinery
Hydraulic excavator 1.0 cum bucket capacity

hour

6.00

c&d) Overheads & Contractors Profit


Cost for 210 cum = a+b+c+d
Rate per cum = (a+b+c+d)/210
Note : Cost of dewatering upto 5 per cent of (a+b) may be added, where required. Assessment for
dewatering shall be made as per site conditions.
iii Depth above 6 m
(A) Manual Means

Unit = cum
Taking output = 10 cum
a) Labour
Mate/Supervisor
Mazdoor (Unskilled)

day

day

6.24

b&c) Overheads & Contractors Profit


Cost for 10 cum = a+b+c
Rate per cum = (a+b+c)/10
Note : 1. Cost of dewatering may be added where required upto 5 per cent of labour cost.
B

Assessment for dewatering shall be made as per site conditions..


Mechanical Means
Unit = cum
Taking output = 180 cum
a) Labour
Mate

day

Mazdoor (Unskilled)

day

10.40

b)
Machinery
Hydraulic excavator 1.0 cum bucket capacity

hour

6.00

c&d) Overheads & Contractors Profit


Cost for 180 cum = a+b+c+d
Rate per cum = (a+b+c+d)/180
Note : 1. Cost of dewatering upto 5 per cent of (a+b) may be added, where required.

Assessment for dewatering shall be made as per site conditions..


2. Labour provided for excavation by mechanical means includes that required for trimming of
bottom and side slopes.
(II) Ordinary rock (not requiring blasting)
(A) Manual Means
Upto 3 m depth
Unit = cum
Taking output = 10 cum
a) Labour
day
Mate
day
5.20
Mazdoor (Unskilled)
b&c) Overheads & Contractors Profit
Cost for 10 cum = a+b+c
Rate per cum = (a+b+c)/10
Note : Cost of dewatering upto 5 per cent of labour cost may be added, where required as
per site condition.

485

RBR_FNDN

Index-code

S. No
1

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

(B) Mechanical Means


Upto 3 m depth
Unit = cum
Taking output = 180 cum
a) Labour
Mate

day

Mazdoor (Unskilled)

day

6.24

b) Machinery
Hydraulic Excavator 1 cum bucket capacity

hour

6.00

c&d) Overheads & Contractors Profit


Cost for 180 cum = a+b+c+d
Rate per cum = (a+b+c+d)/180
Note : 1. Cost of dewatering upto 5% of a+b may be added, where
required, up to 10 per cent of labour cost. Assessment for dewatering
shall be made as per site conditions.

2. in case of rock foundation beyond 3 m is not dug and


hence not included.
(III) Hard rock (requiring blasting)
Upto 3 m depth including 1.5 m depth in hard rock
Unit = cum
Taking output = 10 cum
a) Labour
Mate
Driller
Blaster
Mazdoor (Unskilled)
b) Machinery
Air compressor 210 cfm / 250 cfm with 2 jack hammers for
drilling at 15 cum per hour
c) Material
Gelatin 80%
Detonator electric
d&e) Overheads & Contractors Profit
Cost for 10 cum = a+b+c+d+e
Rate per cum = a+b+c+d+e)/10
Note : 1. Cost of dewatering @ 5 per cent of (a+b) may be
added, where required as per site condition.
2. No limitation of depth in MORTH

day

day

0.50

day

0.25

day

8.35

hour

kg

3.50

Nos.

14.00

(IV) Hard rock (blasting prohibited)

Upto 3 m depth including 1.5 m depth in hard rock


Unit = cum
Taking output = 10 cum
a) Labour
day
Mate
day
Mazdoor (Unskilled)
b) Machinery
Air compressor 210 cfm / 250 cfm with 2 jack hammers of hour
pneumatic breaker at 1 cum per hour
c&d) Overheads & Contractors Profit
Cost for 10 cum = a+b+c+d
Rate per cum = a+b+c+d)/10

5.20
6.00

Note : Cost of dewatering up to 5 per cent of (a+b) may be added,


where required as per site conditions.
2. in case of rock foundation beyond 3 m is not dug and hence
not included. (MORTH)

486

RBR_FNDN

Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

(V) Marshy soil

Unit = cum
Taking output = 10 cum
a) Labour
Mate
Mazdoor (Unskilled)
b&c) Overheads & Contractors Profit
Cost for 10 cum = a+b+c
Rate per cum = a+b+c)/10

day

day

15.60

Note : Cost of dewatering @ 5 per cent of (a) may be added.


Shoring and shuttering @ 15 per cent of (a) may be added where required.
Since marshy soil cannot be used in filling in trenches, it shall be removed and replaced by approved quality
of soil. The labour cost includes labour input for disposal of marshy soil from excavated pit with a lead upto
50 m lead.
Marshy soil is generally available upto 3 m depth. The rate has, therefore, been done upto 3 m depth of
excavation. For deeper excavation refer analysis in item (i) to (iv) of ordinary soil.
(a) Marshy soil

Including Refilling with selected earth conveyed from


1000 M lead through Tractor Trally.
Unit = cum
Taking output = 10 cum
(A) Manual Means (upto 3 m depth)
a) Labour
Mate / Supervisor

day

Mazdoor (Unskilled)

day

10.40

b) Machinery
Tractor - Trally

hour

2.67

c) Material
Selected earth for refilling with conveyance from 1000m

cum

5.00

d&e) Overheads & Contractors Profit


Cost for 10 cum = a+b+c+d+e
Rate per cum = a+b+c+d+e)/10
Note : 1. Cost of dewatering @ 5 per cent of (a) may be added. Assessment for dewatering
shall be made as per site conditions.
2. Shoring and shuttering @ 15 per cent of (a) may be added where required.
3. It is assumed, that Marshy soil will be available upto 3 m depth only. For deeper
excavation below 3m depth, refer analysis in item (i) to (iv) for ordinary soil.
(B) Mechanical Means
a) Labour
Mate

day

Mazdoor for dressing sides, bottom and back filling day


(Unskilled)

2.08

b) Machinery
Hydraulic Excavator 1 cum bucket capacity @ 60 cum / hour

hour

0.17

Tipper 5.5 cum capacity, 4 trips per hour

hour

0.45

c) Material
Selected earth for refilling

cum

5.00

d&e) Overheads & Contractors Profit


Cost for 10 cum = a+b+c+d+e
Rate per cum = a+b+c+d+e)/10
Note :1. Cost of dewatering @ 5 per cent of (a+b) may be added where required. Assessment for
dewatering shall be made as per site conditions.

2. Shoring and shuttering @ 10 per cent of (a+b) may be added where required.
3. It is assumed, that Marshy soil will be available upto 3 m depth only. For deeper
excavation below 3m depth, refer analysis in item (i) to (iv) for ordinary soil.

487

RBR_FNDN

Index-code

S. No
1

Description

2
VI Back Filling in Marshy Foundation Pits

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

Unit : Cum
Taking Output : 6 cum
a) Labour
day
Mate
Mazdoor (Unskilled) for dressing sides, bottom and day
backfilling
b)
Machinery
hour
Tractor-trolley for transportation
c&d) Overheads & Contractors Profit
Cost for 6 cum = a+b+c+d
Rate per cum = (a+b+c+d)/6
Filling in foundation trenches as per drawing and
technical specification Clause 305.3.9 MORD & 304
MORTH

RBR-FNDN-2

3.12
2.00

Sand filling
Unit = cum
a) Labour
day
Mate
day
0.31
Mazdoor (Unskilled)
b) Material
cum
1.00
Sand
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
II Earth filling (For marshy soil)
Unit = cum
Taking output = 6 cum
a) Labour
day
Mate
day
3.12
Mazdoor (Unskilled)
b&c) Overheads & Contractors Profit
Cost for 6 cum = a+b+c
Rate per cum = (a+b+c)/6
Note : Cost of transportation of good quality earth has not been included. Only labour for carrying carted
earth with a lead of 50 m to the foundation pits has been taken in the rate. The cost of carted earth may be
worked out separately if the same is not available from the adjoining area.

RBR-FNDN-3

Backfilling of foundation trenches shall normally be done with excavated earth. The cost of
this operation is included in item 11.1. Only in case the excavated earth is not of suitable
quality, sand filling or backfilling with carted earth may be resort to.
Filling annular space around footing in rock as per
technical specification Clause 1203.4.3. MORD
Unit = cum
P.C.C grade M 15
Nominal mix 1:2.5:5 (Hand mixing)
Unit = cum
(a) Material
t
0.275
Cement
cum
0.48
Coarse sand
cum
0.54
40 mm aggregate
cum
0.27
20 mm aggregate
cum
0.09
10 mm aggregate
(b) Labour
day
Mate
day
0.10
Mason (1st Class)
day
2.36
Mazdoor (Unskilled)
4.00%
(c) Formwork @ 4% on (a+b)
d&e) Overheads & Contractors Profit
Rate per cum = a+b+c+d+e

488

RBR_FNDN

Index-code

S. No
1

Description

2
(a) Filling Annular Space Around Footing in Rock with CC 1:3:6
nominal mix using 40mm nominal size stone aggregate as pre
Tech. Specification 304 & 2100 MORTH

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

Unit = cum
Taking out put = 1 cum
Lean cement concrete 1:3:6 nominal mix. Rate may be taken
as per item 11.4.
4

RBR-FNDN-4

Providing concrete for plain/reinforced concrete in open


foundations using 40 mm nominal size Graded hard stone
aggregate, mechanically mixed, placed in foundation and
compacted by vibration including curing for 14 days complete as
per drawings and technical specifications Clause 802, 803, 1202
& 1203 MORD and 1500, 1700 & 2100 MORTH.
I P.C.C grade M 10
(i) Nominal mix 1:3:6

Unit = cum
(a) Material
Cement

0.22

cum

0.45

cum

0.9

kl

1.2

day
day
day

0.1
1.39

Mechanical concrete mixer 0.4/0.28 cum capacity fitted with water hour
measuring device and preferably also with load cell.
hour
Water tanker 6 kl capacity

0.40

Coarse sand
40 mm aggregate
Water
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
(c) Machinery

(d) Formwork @ 4% on cost of material, labour and


machinery (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = a+b+c+d+e+f
(ii) Nominal mix 1:3:6 (Hand mixing) (MORD)
Unit = cum
(a) Material
t
Cement
cum
Coarse sand
cum
40 mm aggregate
cum
20 mm aggregate
cum
10 mm aggregate
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)

0.220
0.45
0.570
0.280
0.050

day

day
day

0.10
2.36

(c) Formwork@4% on cost of material (a) and labour (b)

d&e) Overheads & Contractors Profit


Rate per cum = a+b+c+d+e
II P.C.C grade M 15 (MORD)
iii Nominal mix (1:2.5:5) (Mechanical Mixer)
Unit = cum
(a) Material
Cement
Coarse sand
40 mm aggregate
20 mm aggregate
10 mm aggregate
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)

0.13
4.00%

4.00%

t
cum
cum

0.275
0.48
0.48

cum

0.24

cum

0.08

day
day

0.10

day

1.39

489

RBR_FNDN

Index-code

S. No
1

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

(c) Machinery
hour
Concrete mixer 0.4/0.28 cum capacity
d) Formwork @ 4% on cost of material, labour and
machinery (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = a+b+c+d+e+f

0.40
4.00%

Note : Needle Vibrator is an item of minor T & P which is already included in overhead charges. Hence not
added in rate analysis of cement concrete works.
iv Nominal mix 1:2.5:5 (Hand mixing) (MORD)

Unit = cum
(a) Material
Cement
Coarse sand
40 mm aggregate
20 mm aggregate
10 mm aggregate
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
(c) Formwork @ 4% on (a+b)
d&e) Overheads & Contractors Profit
Rate per cum = a+b+c+d+e
V P.C.C. grade M 20 (MORD)
(i) Nominal mix (1:2:4) (Mechanical Mixer)
Unit = cum
(a) Material
Cement
Sand
40 mm aggregate
20 mm aggregate
10 mm aggregate
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
Bhisti
(c) Machinery
Concrete mixer 0.4/0.28 cum capacity
(d) Formwork @ 4% on (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = a+b+c+d+e+f
(ii) Nominal mix 1:2:4 (Hand mixed) (MORD)
Unit = cum
(a) Material
Cement
Sand
40 mm aggregate
20 mm aggregate
10 mm aggregate
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
(c) Formwork @ 4% out of material and labour (a+b)
d&e) Overheads & Contractors Profit
Rate per cum = a+b+c+d+e

0.275

cum

0.48

cum

0.54

cum
cum

0.27
0.09

day
day
day

0.10
2.36
4.00%

0.33

cum

0.45

cum

0.36

cum

0.36

cum

0.18

day

day

0.1

day

1.39

day
hour

0.4
4.00%

t
cum

0.33
0.45

cum

0.36

cum

0.36

cum

0.18

day

day

0.1

day

2.36
4.00%

490

RBR_FNDN

Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

B
i

P.C.C grade M 15 (Design Mix) MORTH 12.8 A using 40


mm Graded Metal
Unit = cum
(a) Material
Cement
Coarse sand
40 mm aggregate
20 mm aggregate
10 mm aggregate
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
(c) Machinery
Concrete mixer 0.4/0.28 cum capacity
Generator 33 KVA
d) Formwork @ 4% on cost of material, labour and
machinery (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = a+b+c+d+e+f
ii P.C.C. grade M 20 (Design Mix) MORTH 12.8 B using 40
mm Graded Metal
Unit = cum
(a) Material
Cement
Sand
40 mm aggregate
20 mm aggregate
10 mm aggregate
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
(c) Machinery
Concrete mixer 0.4/0.28 cum capacity
Generator 33 KVA
(d) Formwork @ 4% on (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = a+b+c+d+e+f
C i R.C.C grade M 20 using Concrete mixer (Nominal Mix)
using 20 mm Graded Metal (MORD)
Unit = cum
(a) Material
Cement
Coarse sand
20 mm aggregate
10 mm aggregate
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
(c) Machinery
Concrete mixer 0.4/0.28 cum capacity
(d) Formwork @ 4% on (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = a+b+c+d+e+f

0.275

cum

0.45

cum

0.54

cum

0.27

cum

0.09

day

day

0.10

day

1.39

hour

0.40

hour

0.40
4.00%

0.343

cum

0.45

cum

0.36

cum

0.36

cum

0.18

day

day

0.1

day

1.39

hour

0.4

hour

0.4
4.00%

0.33

cum

0.45

cum

0.54

cum

0.36

day

day

0.1

day

1.39

hr /
cum

0.4
4.00%

491

RBR_FNDN

Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

1
ii

R.C.C grade M 20 (Design Mix) using 20 mm Graded


Metal (MORTH)
CASE I : Using Concrete Mixer
Unit = cum
(a) Material
t
Cement
cum
Coarse sand
cum
20 mm aggregate
cum
10 mm aggregate
(b) Labour
day
Mate
day
Mason (1st Class)
day
Mazdoor (Unskilled)
(c) Machinery
hr /
Concrete mixer 0.4/0.28 cum capacity
Generator 33 KVA
(d) Formwork @ 4% on (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = a+b+c+d+e+f
Case II : With Batching Plant, Transit Mixer and Concrete
Pump (RCC M20) (Design Mix) (MORTH 12.8 C)
Unit : cum
Taking Output = 120 cum
a) Material
Cement
Coarse Sand
20 mm Aggregate
10 mm Aggregate
b)
Labour
Mate
Mason
Mazdoor (Unskilled)
c)
Machinery
Batching Plant @ 20 cum/ hour
Generator 100 KVA
Loader 1 cum capacity
Transit Mixer 4 cum capacity for lead upto 1 km.
Lead beyond 1 km, L-lead in km
Concrete Pump
d)
Formwork @ 4 per cent on cost of concrete i.e. cost of
material, labour and machinery
e&f) Overheads & Contractors Profit
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = ( a+b+c+d+e+f )/120

cum
hour

0.347
0.45
0.54
0.36
0.1
1.39
0.4
0.4
4.00%

tonne

41.66

cum

54.00

cum
cum

64.80
43.20

day

0.84

day

3.00

day

18.00

hour

6.00

hour
hour

6.00
6.00

hour
t.km

15.00
300L

hour

6.00
4.00%

PCC Grade M25 using 40 mm Graded Metal (Design Mix)


(MORTH 12.8 D)
CASE I : Using Concrete Mixer
Unit = cum
Taking output = cum
a) Material
tonne
Cement
cum
Coarse sand
cum
40 mm Aggregate
cum
20 mm Aggregate
cum
10 mm Aggregate
b)
Labour
day
Mate
day
Mason
day
Mazdoor (Unskilled)

0.40
0.45
0.36
0.36
0.18
0.1
1.39

492

RBR_FNDN

Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

hr /
cum
hour

0.40

c)
Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
d)
Formwork @ 3.75 per cent of (a+b+c)
e&f) Overheads & Contractors Profit
Rate for cum = a+b+c+d+e+f
CASE II : With Batching Plant, Transit Mixer and Concrete
Pump (M 25) (MORTH 12.8 D)
Unit : cum
Taking Output = 120 cum
a) Material
Cement
Coarse sand
40 mm Aggregate
20 mm Aggregate
10 mm Aggregate
b)
Labour
Mate
Mason
Mazdoor (Unskilled)
c)
Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader 1 cum capacity
Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity lead beyond 1 Km, L - lead in
Kilometer
Concrete Pump

0.40
4.00%

tonne
cum
cum
cum
cum

47.95
54.00
43.20
43.20
21.60

day
day
day

3.00
18.84

hour
hour
hour
hour
tonne
.km
hour

6.00
6.00
6.00
15.00
300L

d)
Formwork @ 3.75 per cent of cost of concrete i.e. cost of
material, labour and machinery

6.00
3.75%

e&f) Overheads & Contractors Profit


cost of 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120
E

R.C.C. grade M 25 (Design Mix) using 20 mm Graded Metal


(MORD & MORTH 12.8 E)

Case 1 : Using Concrete Mixer


Unit = cum
(a) Material
Cement
Coarse sand
20 mm aggregate
10 mm aggregate
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
Bhisti
(c) Machinery
Concrete mixer 0.4/0.28 cum capacity

0.403

cum

0.45

cum

0.54

cum

0.36

day

day

0.1

day

1.39

day
hr /
cum

0.4
3.75%

(d) Formwork @ 3.75% on (a+b+c)


e&f) Overheads & Contractors Profit
Rate per cum = a+b+c+d+e+f
Case 2 : With Batching Plant, Transit Mixer and Concrete Pump
(RCC M 25) (MORTH 12.8 E)

Unit: cum
Taking Output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate

tonne
cum
cum

48.38
54.00
64.80

cum

43.20

493

RBR_FNDN

Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

b)
Labour
Mate
Mason
Mazdoor (Unskilled)
c)
Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader 1 cum capacity 1 cum
Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity lead beyond 1 Km, L - lead in
Kilometer
Concrete Pump
d)
Formwork @ 3.75 per cent on cost of concrete i.e.
cost of material, labour and machinery
e&f) Overheads & Contractors Profit
cost of 120 cum = a+b+c+d+e+f
Rate per cum (a+b+c+d+e+f )/120
F PCC Grade M 30 (MORTH 12.8 F) Design Mix using 40
mm Graded Metal
CASE I : Using Concrete Mixer
Unit = cum
Taking output = cum
a) Material
Cement
Coarse sand
40 mm Aggregate
20 mm Aggregate
10 mm Aggregate
b)
Labour
Mate
Mason
Mazdoor (Unskilled)
c)
Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
d)
Formwork @ 3.5 per cent of (a+b+c)
e&f) Overheads & Contractors Profit
Rate for 1 cum = a+b+c+d+e+f
CASE II : With Batching Plant, Transit Mixer and Concrete
Pump (PCC M 30) Design Mix
Unit : cum
Taking Output = 120 cum
a) Material
Cement
Coarse sand
40 mm Aggregate
20 mm Aggregate
10 mm Aggregate

day

day

3.00

day

18.84

hour

6.00

hour

6.00

hour

6.00

hour

15.00

tonne
.km

300L

hour

6.00
3.75%

tonne
cum

0.405
0.45

cum

0.36

cum

0.36

cum

0.18

day

day

0.1

day

1.39

hour

0.4

hour

0.4
3.50%

tonne
cum
cum

48.60
54.00
43.20

cum
cum

43.20
21.60

b)
Labour
day
Mate
day
Mason
day
Mazdoor (Unskilled)
c)
Machinery
hour
Batching Plant @ 20 cum/hour
hour
Generator 100 KVA
hour
Loader 1 cum capacity
hour
Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity lead beyond 1 Km, L - lead in tonne
.km
Kilometer
hour
Concrete Pump

3.00
18.84
6.00
6.00
6.00
15.00
300L
6.00

494

RBR_FNDN

Index-code

S. No
1

Description

Unit

Quantity

4
3.50%

t
cum

0.407
0.45

cum

0.54

cum

0.36

d)
Formwork @ 3.5 per cent of cost of concrete i.e. cost
of material, labour and machinery
e&f) Overheads & Contractors Profit
cost of 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120
G

Amount
Rs.

Remarks

R.C.C. grade M 30 Design Mix, using 20 mm Graded


Metal (MORTH 12.8 G)
Case 1 : Using Concrete Mixer
Unit = cum
(a) Material
Cement
Coarse sand
20 mm aggregate
10 mm aggregate
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
(c) Machinery
Concrete mixer 0.4/0.28 cum capacity
Generator 33 KVA
(d) Formwork @ 3.5% on (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = a+b+c+d+e+f
Case 2 : With Batching Plant, Transit Mixer and Concrete
Pump (RCC M 30) Design Mix
Unit: cum
Taking Output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
b)
Labour
Mate
Mason
Mazdoor (Unskilled)
c)
Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader 1 cum capacity 1 cum
Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity lead beyond 1 Km, L - lead in
Kilometer
Concrete Pump
d)
Formwork @ 3.5 per cent on cost of concrete i.e. cost
of material, labour and machinery
e&f) Overheads & Contractors Profit
cost of 120 cum = a+b+c+d+e+f
Rate per cum (a+b+c+d+e+f )/120

Rate
Rs.

day

day

0.1

day

1.39

hour

0.40

hour

0.40
3.50%

tonne
cum

48.80
54.00

cum

64.80

cum

43.20

day

day

3.00

day

18.84

hour

6.00

hour

6.00

hour

6.00

hour

15.00

tonne
.km

300L

hour

R.C.C. grade M 35 Design Mix using 20 mm Graded Metal


(MORTH 12.8.H)
Case 1 : Using Concrete Mixer
Unit = cum
(a) Material
t
Cement
cum
Coarse sand
cum
20 mm aggregate
cum
10 mm aggregate

6.00
3.50%

0.422
0.45
0.54
0.36

495

RBR_FNDN

Index-code

S. No
1

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

(b) Labour
day
Mate
day
Mason (1st Class)
day
Mazdoor (Unskilled)
(c) Machinery
hour
Concrete mixer 0.4/0.28 cum capacity
hour
Generator 33 KVA
(d) Formwork @ 3% on (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = a+b+c+d+e+f
Case 2 : With Batching Plant, Transit Mixer and Concrete
Pump (RCC M35) Design Mix
Unit: cum
Taking Output = 120 cum
a) Material
tonne
Cement
cum
Coarse sand
cum
20 mm Aggregate
cum
10 mm Aggregate
b)
Labour
day
Mate
day
Mason
day
Mazdoor (Unskilled)
c)
Machinery
hour
Batching Plant @ 20 cum/hour
hour
Generator 100 KVA
hour
Loader 1 cum capacity 1 cum
hour
Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity lead beyond 1 Km, L - lead in Kilometer

t.km

hour
Concrete Pump
Vibrator
d)
Formwork @ 3 per cent on cost of concrete i.e. cost of
material, labour and machinery
e&f) Overheads & Contractors Profit
cost of 120 cum = a+b+c+d+e+f
Rate per cum (a+b+c+d+e+f )/120

0.1
1.39
0.40
0.40
3.00%

50.64
54.00
64.80
43.20
3.00
18.84
6.00
6.00
6.00
15.00
300L
6.00
3.00%

Note : Where ever concrete is carried out using batching plant, transit mixer, concrete pump, Admixtures @
0.4 per cent of weight of cement may be added for achieving desired slump of concrete.
NOTE : Concrete used in any component or structure shall be specified by designation along with
prescribed method of design of mix i.e., "Design Mix" or "Nominal Mix". For all items of concrete, only
"Design Mix" shall be used, except where "Nominal Mix" concrete is permitted as per drawing or by the
Engineer. "Nominal Mix" may be permitted only for minor bridges and culverts or other incidental
construction where strength requirements are upto M 20 only. "Nominal Mix" may also be permitted for nonstructural concrete or for screed below open foundations.
Note : Water : A provision for cost of water may be added at 1.2 kl / 1 cum (including curing

purpose) keeping the site conditions


Coarse Aggregate : Single grade nominal size can also be used instead of graded metal,

keeping the site conditions in view


5

Brick masonry work in cement mortar in foundation complete


excluding pointing and plastering as per drawing and technical
specifications Clauses 600, 1202 & 1203 MORD / 1300 MORTH
with Second Class Bricks & Moulded Bricks

RBR-FNDN-5

Unit = cum
Brick masonry in 1:3 cement mortar
(a) Material
Bricks
Cement mortar 1:3 (Rate as per Sub-analysis)
(b) Labour
Mate
Mason (1st Class)

Nos.

512

cum

0.2

day

day

0.89

496

RBR_FNDN

Index-code

S. No

Description

Unit

Quantity

3
day

4
1.8

t
cum

0.48
1.05

Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
Sub-analysis
Cement mortar 1:3 (1 cement : 3 sand)
Unit = cum
(a) Material
Cement
Sand
(b) Labour
Mate
Mazdoor (Unskilled)
Total material and labour = (a+b)
II Brick masonry in 1:4 cement mortar
Unit = cum
(a) Material
Bricks
Cement mortar 1:4
Rates as per sub-analysis
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
Sub-analysis
Cement mortar 1:4 (1 cement : 4 sand)
Unit = cum
(a) Material
Cement
Sand
(b) Labour
Mate
Mazdoor (Unskilled)
Total material and labour = (a+b)
III Brick masonry in cement-lime-mortar (1:0.5:4.5)
Unit = cum
(a) Material
Bricks
Cement lime mortar rates as per sub-analysis
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
Sub-analysis

day

day

0.2

Nos.

512

cum

0.2

Rate
Rs.

Amount
Rs.

Remarks

day
day

0.89

day

1.8

0.36

cum

1.05

day

day

0.2

Nos.

512

cum

0.20

day

day

0.89

day

1.80

Cement-lime-mortar 1:0.5:4.5 (1 cement: 0.5 lime putty : 4.5 sand)

Unit = cum
(a) Material
t
0.38
Cement
t
0.175
Lime putty
cum
1.05
Sand
(b) Labour
day
Mate
day
3.05
Mazdoor (Unskilled)
Total material and labour = (a+b)
Note : i. To provide 512 Nos Bricks Traditional size 23 x 11 x 7 cms and 520 Nos Modular
Bricks 19 x 9 x 9 cms
ii. Compressive strength of individual Brick shall not be less than 70 kg / cm 2
6

Stone masonry work in cement mortar in foundation complete as


per drawing and technical specifications Clauses 702, 704, 1202
& 1203 MORD and 1405 MORTH.

RBR-FNDN-6

Unit = cum
Coursed rubble masonry (1st sort)
(i) CRS 1st Sort in 1:3 cement mortar
Unit = cum
(a) Material
Stone for C.R. masonry 1st sort
Through bond stone (7 nos 0.24 x 0.24 x 0.39 = 0.16 cum)
I

Cement mortar (1:3) (Rate as in item 11.5 I)


(b) Labour
Mate
Mason 1st Class
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d

cum

0.94

Nos.

0.16

cum

0.28

day

day

2.5

day

2.32

497

RBR_FNDN

Index-code

S. No
1

Description

2
(ii) CRS 1st Sort in 1:4 cement mortar

Unit = cum
(a) Material
Stone for C.R. masonry 1st sort
Through bond stone (7 nos 0.24 x 0.24 x 0.39 = 0.16 cum)
Cement mortar 1:4 (Rate as in item 11.5 II)
(b) Labour
Mate
Mason 1st Class
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
(iii) CRS First Sort in cement-lime-sand mortar (1:0.5:4.5)
Unit = cum
(a) Material
Stone for C.R. masonry 1st sort
Through bond stone (7 nos 0.24 x 0.24 x 0.39 = 0.16 cum)
Cement lime mortar (Rate as in item 11.5 III)
(b) Labour
Mate
Mason 1st Class
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

cum

0.94

Nos.

0.16

cum

0.28

day

day

2.5

day

2.32

cum

0.94

Nos.

0.16

cum

0.28

day

day

2.5

day

2.32

cum

0.94

Nos.
cum

0.16
0.32

Note : Quantity of required chips has not been provided for separately
as it is assumed that the same will be available from dressing of
stones.
II

Coursed rubble masonry (2nd sort)

(i) In 1:3 cement mortar

Unit = cum
(a) Material
Stone for C.R. masonry 2nd sort
Through bond stone (7 nos 0.24 x 0.24 x 0.39 = 0.16 cum)
Cement mortar (Rate as in item 11.5 I.)
Water
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d

day

day

1.5

day

2.22

498

RBR_FNDN

Index-code

S. No
1

Description

2
(ii) CRS 2nd Sort in 1:4 cement mortar

Unit = cum
(a) Material
Stone for C.R. masonry 2nd sort
Through bond stone (7 nos 0.24 x 0.24 x 0.39 = 0.16 cum)
Cement mortar (Rate as in item 11.5 II)
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
(iii) CRS 2nd Sort in cement-lime-mortar (1:0.5:4.5)
Unit = cum
(a) Material
Stone for C.R. masonry 2nd sort

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

cum

0.94

Nos.

0.16

cum

0.32

day

day

1.5

day

2.22

cum

0.94

Through bond stone (7 nos 0.24 x 0.24 x 0.39 = 0.16 cum)

Nos.

0.16

cement-lime-mortar (1:0.5:4.5) (Rate as in item 11.5 III)

cum

0.32

(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
III Random Rubble Masonry
(i) In 1:3 cement mortar
Unit = cum
(a) Material
CR Stone
Stone for R.R. masonry
Through bond stone (7 nos 0.24 x 0.24 x 0.39 = 0.16 cum)
Cement mortar (1:3) (Rate as in item 11.5 I)
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
(ii) RR Masonry in cement mortar 1:4
Unit = cum
(a) Material
CR Stone
Stone for R.R. masonry
Through bond stone (7 nos 0.24 x 0.24 x 0.39 = 0.16 cum)
Cement mortar (1:4) (Rate as in item 11.5 II)
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d

day

day

1.50

day

2.22

cum

0.44

cum

0.5

Nos.

0.16

cum

0.33

day

day

1.2

day

cum

0.44

cum

0.5

Nos.

0.16

cum

0.33

day

day

1.2

day

499

RBR_FNDN

Index-code

S. No
1

RBR-FNDN-7

Description

2
(iii) RR Masonry in cement mortar 1:6

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

Unit = cum
(a) Material
cum
CR Stone
cum
Stone for R.R. masonry
Nos.
Through bond stone (7 nos 0.24 x 0.24 x 0.39 = 0.16 cum)
cum
Cement mortar (1:6) (Rate as in Sub Analysis)
(b) Labour
day
Mate
day
Mason (1st Class)
day
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
Sub Analysis :
Cement Mortar 1:6
Unit = cum
(a) Material
t
Cement
cum
Sand
(b) Labour
day
Mate
day
Mazdoor (Unskilled)
Total material and labour = (a+b)
(iv) RR Masonry in cement lime mortar (1:0.5:4.5)
Unit = cum
(a) Material
cum
CR Stone
cum
Stone for R.R. masonry
Nos.
Through bond stone (7 nos 0.24 x 0.24 x 0.39 = 0.16 cum)
cum
Cement lime mortar (Rate as in item 11.5 III)
(b) Labour
day
Mate
day
Mason (1st Class)
day
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
Note : Quantity of required chips has not been provided for
separately as it is assumed that the same will be available from
dressing of stones
Supplying, fitting and placing HYSD bar reinforcement in
foundation complete as per drawings and technical
specifications Clauses 1000 and 1202 MORD & 1100,
1600 MORTH for Bars below 36 mm dia including over
laps and wastage, where they are not welded.
Unit = t
(a) Material
HYSD bars including 5 per cent for overlaps and wastage

kg
Binding wire
(b) Labour for cutting, bending, shifting to site, tying and
placing in position
day
Mate
day
Blacksmith
day
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per t = a+b+c+d

0.44
0.5
0.16
0.33
1.2
2

0.24
1.05
0.2

0.44
0.5
0.16
0.33
1.20
2.00

1.05
6.00

2.00
6.40

500

RBR_FNDN

Index-code

S. No
1

RBR-FNDN-8

Description

2
A Supplying, fitting and placing HYSD bar reinforcement in

foundation complete including wastage, as per drawings


and technical specifications Clauses 1000 and 1202
MORD & 1100, 1600 MORTH for Bars 36 mm dia and
above, where welding required to be done compulsorily.
Unit = t
(a) Material
HYSD bars including 2.5 per cent for wastage
Welding Electrodes @ 5 per joint (14 joints / ton)
Welding Charges (Hire charges of Welding Machine)
Binding wire
(b) Labour for cutting, bending, shifting to site, tying and
placing in position
Welder
Blacksmith
Mazdoor (Unskilled)
(c) Overheads on (a+b)
(d) Contractors profit on (a+b+c)
c&d) Overheads & Contractors Profit
Rate per t = a+b+c+d
Supplying, fitting and placing TMT bar reinforcement in
foundation complete as per drawings and technical
specifications Clauses 1000 and 1202 MORD & 1100,
1600 MORTH for Bars below 36 mm dia including over
laps and wastage, where they are not welded.
Unit = t
(a) Material
TMT bars including 5 per cent for overlaps and wastage
Binding wire
(b) Labour for cutting, bending, shifting to site, tying and
placing in position
Mate
Blacksmith
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per t = a+b+c+d
A Supplying, fitting and placing TMT bar reinforcement in
foundation complete including wastage, as per drawings
and technical specifications Clauses 1000 and 1202
MORD & 1100, 1600 MORTH for Bars 36 mm dia and
above, where welding required to be done compulsorily.
Unit = t
(a) Material
TMT bars including 2.5 per cent for wastage

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

1.025

each

70.000

Hr

10.00

kg

6.00

day

2.50

day

2.00

day

6.40

1.05

kg

6.00

day

day

2.00

day

6.40

each
Welding Electrodes @ 5 per joint (14 joints / ton)
Hr
Welding Charges (Hire charges of Welding Machine)
kg
Binding wire
(b) Labour for cutting, bending, shifting to site, tying and
placing in position
day
Welder
day
Blacksmith
day
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per t = a+b+c+d

1.025
70.000
10.00
6.00

2.50
2.00
6.40

501

RBR_FNDN

Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

RBR-FNDN-9

10

RBR-FNDN-10

Supplying, fitting and placing MS bar reinforcement in


foundation complete as per drawings and technical
specifications Clauses 1000 and 1202 MORD & 1100,
1600 MORTH for Bars below 36 mm dia including over
laps and wastage, where they are not welded.
Unit = t
(a) Material
t
1.05
MS bars including 5 per cent for overlaps and wastage
kg
6.00
Binding wire
(b) Labour for cutting, bending, shifting to site, tying and
placing in position
day
Mate
day
2.00
Blacksmith
day
6.40
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per t = a+b+c+d
WELL FOUNDATION
Providing and Constructing Temporary Island 16 m
diameter for Construction of Well Foundation for 8m dia.
Well as per Tech. Specification 1203 MORTH.
A Assuming depth of water 1.0 m and height of island to be
1.25 m.
Unit = 1 No
Taking output = 1 No.
a) Material
cum
251.20
Earth (compacted)
each
750.00
Sand bags
b)
Labour
day
Mate
day
15.40
Mazdoor for filling sand bags, stitching and placing
c)
Machinery
hour
20.00
Crane with grab 1 cum capacity
Consumables @ 2.5 per cent of (c) above
d&e) Overheads & Contractors Profit
Rate per No. (a+b+c+d+e)
Note : It is assumed that earth will be available within the working space of crane with grab
bucket.
B Assuming depth of water 4.0 m and height of island 4.5 m.

Unit = 1No
Taking output = 1 No
a) Material
cum
904.32
Earth (compacted)
each 6000.00
Sand bags
each
95.00
Wooden ballies 8" Dia and 9 m long
m
190.00
Wooden ballies 2" Dia for bracing
b)
Labour
day
Mate
day
23.60
Mazdoor for piling 8" dia ballies for piling 8" dia ballies
day
12.00
Mazdoor for bracing with 2" dia ballies
day
110.00
Mazdoor for filling sand bags, stitching and placing
c)
Machinery
hour
50.00
Crane with grab 1 cum capacity
Consumables and other arrangements for piling ballies @ 2.5
per cent of (a+b+c).
d&e) Overheads & Contractors Profit
Rate per No. (a+b+c+d+e)
Note : For other well diameters rate can be worked out on the basis of cross-sectional area of
well. The diameter of the island shall be in the conformity with clause 1203.2 of MoRTH
specifications.
C Providing and constructing one span service road to
reach island location from one pier location to another
pier location as per Tech. Specification 1203 MORTH.
Assuming span length 30 m, width of service road 10m and
depth of water 1m
Unit = 1 meter
Taking output = 30 metre
a) Material
cum
Earth
each
Sand bags

450.00
300.00

b)
Labour
Mate

day

Mazdoor (Unskilled) for filling sand bags, stitching and placing

day

6.24

hour

27.00

hour

28.00

c)
Machinery
Front end Loader 1 cum capacity
Tipper 5.5 cum capacity
d&e) Overheads & Contractors Profit

502

RBR_FNDN

Index-code

S. No
1

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

1.05

Kg

20.00

Cost for 30 m = (a+b+c+d+e)


Rate per m = (a+b+c+d+e)/30
11

Providing and Laying Cutting Edge of Mild Steel weighing 40 kg


per metre for Well Foundation complete as per Drawing and
Technical Specification 1204, 1900 MORTH.

RBR-FNDN-11

Unit = 1 MT
Taking output = 1 MT
a) Material
Structural steel in plates, angles, etc including 5 per cent wastage

Nuts & bolts


b)
Labour
(for cutting, bending, making holes, joining, welding and erecting in
position)

Mate
Fitter
Blacksmith
Welder
Mazdoor (Unskilled)

day

day

5.50

day

5.50

day

5.50

day

17.82

cum

1.00
20.00%

Electrodes, cutting gas and other consumables @ 10 per cent of cost


of (a) above

Handling loading and unloading on (a)


Hire charges of Welding machine on (a)
c&d) Overheads & Contractors Profit
Rate per MT (a+b+c+d)
Plain/Reinforced Cement Concrete, in Well Foundation
complete as per Drawing and Technical Specification
1200, 1500 & 1700 MORTH.
Unit = 1 cum
Taking output = 1 cum

12

RBR-FNDN-12

Well Curb

(i) RCC M20 Grade


Same as per 4.C.(ii) Case I, except for formwork which shall be@ 20
per cent of the cost of concrete instead of 4 per cent.

Case 1 : Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

d) formwork @ 20 per cent of the cost of concrete


e&f) Overheads & Contractors Profit
Rate per m (a+b+c+d+e+f)

503

RBR_FNDN

Index-code

S. No
1

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

Case II : With Batching Plant, Transit Mixer and Concrete


Pump as per 4.C.(ii) Case II
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) cum
d) formwork @ 20 per cent of the cost of concrete
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)

1.00
20.00%

(ii) RCC M25 Grade

Same as per 4.E except for formwork which shall be@ 20 per
cent of the cost of concrete instead of 3.75 per cent.
Case 1 : Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) cum
d) formwork @ 20 per cent of the cost of concrete
Water
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)
Case II : With Batching Plant, Transit Mixer and Concrete
Pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) as in 4.E cum

d) formwork @ 20 per cent of the cost of concrete


e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)
(iii) RCC M35 Grade
Same as for 4(H) except for formwork which shall be@ 20
per cent of the cost of concrete instead of 3.0 per cent.
Case 1 : Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) cum
d) formwork @ 20 per cent of the cost of concrete
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)
Case II : With Batching Plant, Transit Mixer and Concrete
Pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) as in 4H

cum

d) formwork @ 20 per cent of the cost of concrete


e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)

1.00
20.00%

1.00
20.00%

1.00
20.00%

1.00
20.00%

Note : If curb concrete is carried out within steel liner, cost of formwork
shall be excluded.
(B)

Well staining

PCC M15 Grade (Design Mix) using 40 mm Graded Metal


Same as per 4 B(i) except for formwork which shall be @ 10
per cent of the cost of concrete instead of 4 per cent.
Case 1 : Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) cum
d) formwork @ 10 per cent of the cost of concrete
e&f) Overheads & Contractors Profit
Rate per m (a+b+c+d+e+f)
II PCC M20 Grade (Design Mix) using 40 mm Graded Metal
Same as per 4 B(ii) except for formwork which shall be @ 10
per cent of the cost of concrete instead of 4 per cent.
Case 1 : Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) cum
d) formwork @ 10 per cent of the cost of concrete
e&f) Overheads & Contractors Profit
Rate per m (a+b+c+d+e+f)

1.00
10.00%

1.00
10.00%

504

RBR_FNDN

Index-code

S. No
1

Description

2
III RCC M20 Grade (Design Mix) using 20 mm Graded Metal

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

Same as per 4C (ii) except for formwork which shall be @ 10


per cent of the cost of concrete instead of 4 per cent.
Case 1 : Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) cum
d) formwork @ 10 per cent of the cost of concrete
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)
Case II : With Batching Plant, Transit Mixer and Concrete
Pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) cum
as per 4C (ii)
d) formwork @ 10 per cent of the cost of concrete
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)
IV PCC M25 Grade Design Mix
Same as per 4D except for formwork which shall be @ 10 per
cent of the cost of concrete instead of 3.75%
Case 1 : Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

cum

10.00%

1.00

cum

1.00
10.00%

cum

1.00
10.00%

d) formwork @ 10 per cent of the cost of concrete


Water
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)
V RCC M25 Grade Design Mix
Same as per 4 E except for formwork which shall be @ 10
per cent of the cost of concrete instead of 3.75 %
Case 1 : Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

1.00

10.00%

d) formwork @ 10 per cent of the cost of concrete


e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)
Case II : With Batching Plant, Transit Mixer and Concrete
Pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

1.00
10.00%

d) formwork @ 10 per cent of the cost of concrete


Water
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)
Case II : With Batching Plant, Transit Mixer and Concrete
Pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) cum
as in 4 E
d) formwork @ 10 per cent of the cost of concrete
Water
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)
VI PCC M30 Grade Design Mix
Same as for 4 (F) except for formwork which shall be @ 10
per cent of the cost of concrete instead of 3.5 per cent.

1.00
10.00%

Case 1 : Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

d) formwork @ 10 per cent of the cost of concrete


Water
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)

cum

1.00
10.00%

505

RBR_FNDN

Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

Case II : With Batching Plant, Transit Mixer and Concrete


Pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) cum
as in 4 F
d) formwork @ 10 per cent of the cost of concrete
Water
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)
VII RCC M30 Grade Design Mix
Same as for 4(G) except for formwork which shall be @ 10
per cent of the cost of concrete instead of 3.5 per cent.
Case 1 : Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

cum

1.00
10.00%

1.00
10.00%

d) formwork @ 10 per cent of the cost of concrete


Water
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)
Case II : With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) cum
as in 4G
d) formwork @ 10 per cent of the cost of concrete
e)
Overhead charges @ input on (a+b+c+d)
f)
Contractor's profit @ input on (a+b+c+d+e)
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)
VIII RCC M35 Grade
Same as for 4 (H) except for formwork which shall be @ 10
per cent of the cost of concrete instead of 3 per cent.
Case 1 : Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

cum

d) formwork @ 10 per cent of the cost of concrete


Water
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)
Case II : With Batching Plant, Transit Mixer and Concrete
Pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) cum
as in 4 H
d) formwork @ 10 per cent of the cost of concrete
Water
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)
IX RCC M40 Grade (Design Mix) using 20 mm Graded Metal

1.00
10.00%

1.00
10.00%

1.00
10.00%

Using Batching Plant, Transit Mixer and Concrete Pump

Unit = cum
Taking output = 120 cum
a) Material
Cement
Coarse Sand
20 mm Aggregate
10 mm Aggregate
Admixture
b)
Labour
Mate
Meson
Mazdoor (Unskilled)
c)
Machinery
Batching Plant
Generator 100 KVA

tonne

51.60

cum

54.00

cum

64.80

cum

43.20

kg

206.00

day

day

3.00

day

18.84

hour

6.00

hour

6.00

506

RBR_FNDN

Index-code

S. No

Description

Unit

Quantity

3
hour

4
6.00

Loader 1 cum capacity


Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity for lead beyond 1 km.
Concrete Pump
d)
Formwork @ 10 per cent on cost of concrete i.e. cost
of material, labour and machinery
e&f) Overheads & Contractors Profit
cost of 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120
(C) Bottom Plug
Concrete to be placed using tremie pipe
Note : 10% extra cement to be added where under water
concreting is involved
(i) PCC Grade M20 Design Mix
Case 1 : Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement
Coarse sand
40 mm Aggregate
20 mm Aggregate
10 mm Aggregate
Admixture
b)
Labour
Mate
Mason
Mazdoor (Unskilled)
c)
Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
Light Crane 3 tonnes capacity for handling tremie pipe

hour

15.00

t.km

300xL

hour

Rate
Rs.

Amount
Rs.

Remarks

6.00
10.00%

tonne
cum

5.55
6.75

cum

5.40

cum

5.40

cum

2.70

Kg

18.60

day

day

1.50

day

20.90

hour

6.00

hour

6.00

hour

6.00

Add 5 per cent of cost of material and labour towards cost of forming
sump, protective bunds, chiselling and making arrangements for under
water concreting with tremie pipe.

d&e) Overheads & Contractors Profit


cost of 15 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/15
Case II : Using Batching Plant, Transit Mixer and
Crane/concrete pump (PCC M20)
Unit ; cum
Taking Output = 120 cum
a) Material
tonne
Cement
cum
Coarse sand
cum
20 mm Aggregate
cum
10 mm Aggregate
Kg
Admixture
b)
Labour
day
Mate
day
Mason
day
Mazdoor (Unskilled)
c)
Machinery
hour
Batching Plant @ 20 cum/hour
hour
Generator 100 KVA
hour
Loader 1 cum capacity
hour
Transit Mixer 4 cum capacity for lead upto 1 km.

44.40
54.00
64.80
43.20
148.80
3.00
18.88
6.00
6.00
6.00
15.00

507

RBR_FNDN

Index-code

S. No

Description

Unit

Quantity

3
t.km

4
300L

hour

6.00

tonne

5.99

cum

6.75

cum

5.40

cum

5.40

Transit Mixer 4 cum capacity, lead beyond 1 Km, L - lead in


Kilometer
Concrete Pump
Add 5 per cent of cost of material and labour towards cost of
forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe.
d&e) Overheads & Contractors Profit
cost of 120 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/120
(ii) PCC Grade M25 Design Mix
Case 1 : Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement
Coarse sand
40 mm Aggregate
20 mm Aggregate
10 mm Aggregate
Admixture
b)
Labour
Mate
Mason
Mazdoor (Unskilled)
c)
Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
Light Crane of 3 tonnes capacity for handling tremie pipe

cum

2.70

Kg

21.60

day

day

1.50

day

20.90

hour

6.00

hour

6.00

hour

6.00

tonne
cum

47.88
54.00

Rate
Rs.

Amount
Rs.

Remarks

Add 5 per cent of cost of material and labour towards cost of forming
sump, protective bunds, chiselling and making arrangements for under
water concreting with tremie pipe.

d&e) Overheads & Contractors Profit


cost of 15 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/15
Case II : Using Batching Plant, Transit Mixer and
Crane/concrete pump (PCC M25)
Unit = cum
Taking output = 120 cum
a) Material
Cement
Coarse sand
40 mm Aggregate
20 mm Aggregate
10 mm Aggregate
Admixture
b)
Labour
Mate
Mason
Mazdoor (Unskilled)
c)
Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader 1 cum capacity
Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - lead in
Kilometer
Concrete Pump

cum

cum

64.80

cum

43.20

Kg

172.80

day

day

3.00

day

18.88

hour

6.00

hour

6.00

hour

6.00

hour

15.00

tonne
.km

300L

hour

6.00

508

RBR_FNDN

Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

2
Add 5 per cent of cost of material and labour towards cost of forming
sump, protective bunds, chiselling and making arrangements for under
water concreting with tremie pipe.

d&e) Overheads & Contractors Profit


cost of 120 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/120
(iii) PCC Grade M30 Design Mix
Case I : Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement
Coarse sand
40 mm Aggregate
20 mm Aggregate
10 mm Aggregate
Admixture
b)
Labour
Mate
Mason
Mazdoor (Unskilled)
c)
Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
Light Crane of 3 tonnes capacity for handling tremie pipe

6.08

cum

6.75

cum

5.40

cum

5.40

cum

2.70

Kg

21.60

day

day

1.50

day

20.90

hour

6.00

hour

6.00

hour

6.00

Add 5 per cent of cost of material and labour towards cost of forming
sump, protective bunds, chiselling and making arrangements for under
water concreting with tremie pipe.

d&e) Overheads & Contractors Profit


cost of 15 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/15
Case II : Using Batching Plant, Transit Mixer and
Crane/concrete pump (PCC M30)
Unit = cum
Taking output = 120 cum
a) Material
t
Cement
cum
Coarse sand
cum
20 mm Aggregate
cum
10 mm Aggregate
Kg
Admixture
b)
Labour
day
Mate
day
Mason
day
Mazdoor (Unskilled)
c)
Machinery
hour
Batching Plant @ 20 cum/hour
hour
Generator 100 KVA
hour
Loader 1 cum capacity
hour
Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - lead in Kilometer

Concrete Pump

tonne
.km
hour

48.64
54.00
64.80
43.20
172.80
3.00
18.88
6.00
6.00
6.00
15.00
300L
6.00

Add 5 per cent of cost of material and labour towards cost of forming
sump, protective bunds, chiselling and making arrangements for under
water concreting with tremie pipe.

d&e) Overheads & Contractors Profit


cost of 120 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/120

509

RBR_FNDN

Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

(iv) PCC Grade M35 Design Mix

Case 1 : Using Concrete Mixer


Unit = 1 cum
Taking output = 15 cum
a) Material
Cement
Coarse sand
40 mm Aggregate
20 mm Aggregate
10 mm Aggregate
Admixture
b)
Labour
Mate
Mason
Mazdoor (Unskilled)
c)
Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
Light Crane of 3 tonnes capacity for handling tremie pipe

6.29

cum

6.75

cum

5.40

cum

5.40

cum

2.70

Kg

21.60

day

day

1.50

day

20.90

hour

6.00

hour
hour

6.00
6.00

Add 5 per cent of cost of material and labour towards cost of forming
sump, protective bunds, chiselling and making arrangements for under
water concreting with tremie pipe.

d&e) Overheads & Contractors Profit


cost of 15 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/15
Case II : Using Batching Plant, Transit Mixer and
Crane/concrete pump (PCC M35)
Unit = cum
Taking output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
Admixture
b)
Labour
Mate
Mason
Mazdoor (Unskilled)
c)
Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader 1 cum capacity
Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - lead in
Kilometer
Concrete Pump

50.28

cum

54.00

cum

64.80

cum

43.20

Kg

172.80

day
day

3.00

day

18.88

hour

6.00

hour

6.00

hour

6.00

hour

15.00

tonne
.km

300L

hour

6.00

Add 5 per cent of cost of material and labour towards cost of forming
sump, protective bunds, chiselling and making arrangements for under
water concreting with tremie pipe.

d&e) Overheads & Contractors Profit


cost of 120 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/120

510

RBR_FNDN

Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

cum

1.00

cum

1.00

(D) Intermediate plug


(i) Grade M20 PCC Design Mix

Same as in bottom plug concrete, excluding cost of forming


sump, protective bunds, chiseling etc.
Case 1 : Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

d&e) Overheads & Contractors Profit


Rate per cum = (a+b+c+d+e)
Case II : Using Batching Plant, Transit Mixer and
Crane/concrete pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

d&e) Overheads & Contractors Profit


Rate per cum = (a+b+c+d+e)
(ii) Grade M25 PCC Design Mix
Same as in bottom plug concrete, excluding cost of forming
sump, protective bunds, chiseling etc.
Case 1 : Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) cum
d&e) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e)
Case II : Using Batching Plant, Transit Mixer and
Crane/concrete pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

1.00

cum

1.00

cum

1.00

cum

1.00

cum

1.00

cum

1.00

cum

1.00

d&e) Overheads & Contractors Profit


Rate per cum = (a+b+c+d+e)
(iii) Grade M30 PCC Design Mix
Same as in bottom plug concrete, excluding cost of forming
sump, protective bunds, chiseling etc.
Case 1 : Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

d&e) Overheads & Contractors Profit


Rate per cum = (a+b+c+d+e)
Case II : Using Batching Plant, Transit Mixer and
Crane/concrete pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

d&e) Overheads & Contractors Profit


Rate per cum = (a+b+c+d+e)
(E) Top plug
(i) Grade M15 PCC Design Mix
Same as Item 4.B(i) excluding formwork
Case 1 : Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

d&e) Overheads & Contractors Profit


Rate per cum = (a+b+c+d+e)
(ii) Grade M20 PCC Design Mix
Same as Item 4.B(ii) excluding formwork
Case 1 : Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

d&e) Overheads & Contractors Profit


Rate per cum = (a+b+c+d+e)
(iii) Grade M25 PCC Design Mix
Same as Item 4(D) excluding formwork
Case 1 : Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

d&e) Overheads & Contractors Profit


Rate per cum = (a+b+c+d+e)

511

RBR_FNDN

Index-code

S. No
1

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

cum

1.00

cum

1.00

cum

1.00

t
cum

5.12
6.75

cum

8.10

cum

5.40

Case II : Using Batching Plant, Transit Mixer and


Crane/concrete pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

d&e) Overheads & Contractors Profit


Rate per cum = (a+b+c+d+e)
(iv) Grade M30 PCC Design Mix
Same as Item 4(F) excluding formwork
Case 1 : Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

d&e) Overheads & Contractors Profit


Rate per cum = (a+b+c+d+e)
Case II : Using Batching Plant, Transit Mixer and
Crane/concrete pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

d&e) Overheads & Contractors Profit


Rate per cum = (a+b+c+d+e)
(F) Well cap
(i) RCC Grade M20 (Design Mix)
Case 1 : Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
b)
Labour
Mate
Mason
Mazdoor (Unskilled)
c)
Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
Form Work @ 4 per cent of a+b+c
d&e) Overheads & Contractors Profit
cost of 15 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/15

day

day

1.50

day

20.86

hour

6.00

hour

6.00
4.00%

Case II : Using Batching Plant, Transit Mixer and Concrete Pump


(RCC M 20)

Unit = cum
Taking output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
b)
Labour
Mate
Mason
Mazdoor (Unskilled)
c)
Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader (capacity 1 cum)
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity for lead upto 1 km.
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump

40.92

cum

54.00

cum

64.80

cum

43.20

day

day

3.00

day

18.84

hour

6.00

hour

6.00

hour

6.00

hour

15.00

t.km

300L

hour

6.00

512

RBR_FNDN

Index-code

S. No

Description

Unit

Quantity

3
cum

4
4.00%

t
cum

6.05
6.75

cum

8.10

cum

5.40

Formwork @ 4 per cent of (a+b+c)


d&e) Overheads & Contractors Profit
cost of 120 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/120
(ii) RCC Grade M25 (Design Mix)
Case I : Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
b)
Labour
Mate
Mason
Mazdoor (Unskilled)
c)
Machinery
Concrete mixer (cap. 0.40/0.28 cum)

day

day

1.50

day

20.86

hour/
cum
hour

6.00

Generator 33 KVA
Form Work of a+b+c
cum
Centering Charges
Water
d&e) Overheads & Contractors Profit
cost of 15 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/15
Case II : Using Batching Plant, Transit Mixer and
Concrete Pump (RCC M 25)
Unit = cum
Taking output = 120 cum
a) Material
t
Cement
cum
Coarse sand
cum
20 mm Aggregate
cum
10 mm Aggregate
b)
Labour
day
Mate
day
Mason
day
Mazdoor (Unskilled)
c)
Machinery
hour
Batching Plant @ 20 cum/hour
hour
Generator 100 KVA
hour
Loader (capacity 1 cum)
Transit Mixer ( capacity 4.0 cu.m )
hour
Transit Mixer 4 cum capacity for lead upto 1 km.
t.km
Lead beyond 1 Km, L - lead in Kilometer
hour
Concrete Pump
cum
Formwork @ 3.75 per cent of ( a+b+c)
d&e) Overheads & Contractors Profit
cost of 120 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/120

Rate
Rs.

Amount
Rs.

Remarks

6.00
3.75%

48.40
54.00
64.80
43.20
3.00
18.84
6.00
6.00
6.00
15.00
300L
6.00
3.75%

513

RBR_FNDN

Index-code

S. No
1

Description

2
(iii) RCC Grade M30 (Design Mix)

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

Case 1 : Using Concrete Mixer


Unit = cum
Taking output = 15 cum
a) Material
t
Cement
cum
Coarse sand
cum
20 mm Aggregate
cum
10 mm Aggregate
b)
Labour
day
Mate
day
Mason
day
Mazdoor (Unskilled)
c)
Machinery
hour
Concrete mixer (cap. 0.40/0.28 cum)
hour
Generator 33 KVA
cum
Formwork @ 3.5 per cent of (a+b+c)
d&e) Overheads & Contractors Profit
cost of 15 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/15
Case II : Using Batching Plant, Transit Mixer and
Concrete Pump (RCC M 30)
Unit = cum
Taking output = 120 cum
a) Material
t
Cement
cum
Coarse sand
cum
20 mm Aggregate
cum
10 mm Aggregate
b)
Labour
day
Mate
day
Mason
day
Mazdoor (Unskilled)
c)
Machinery
hour
Batching Plant @ 20 cum/hour
hour
Generator 100 KVA
hour
Loader (capacity 1 cum)
Transit Mixer ( capacity 4.0 cu.m )
hour
Transit Mixer 4 cum capacity for lead upto 1 km.
t.km
Lead beyond 1 Km, L - lead in Kilometer
hour
Concrete Pump
cum
Formwork @ 3.5 per cent of (a+b+c)
d&e) Overheads & Contractors Profit
cost of 120 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/120
(iv) RCC Grade M35 (Design Mix)
Case 1 : Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
t
Cement
cum
Coarse sand
cum
40 mm Aggregate
cum
20 mm Aggregate
b)
Labour
day
Mate
day
Mason

6.10
6.75
8.10
5.40
1.50
20.86
6.00
6.00
3.50%

48.79
54.00
64.80
43.20
3.00
18.84
6.00
6.00
6.00
15.00
300L
6.00
3.50%

6.33
6.75
8.10
5.40
1.50

514

RBR_FNDN

Index-code

S. No

Description

Unit

Quantity

3
day

4
20.86

hour

6.00

Mazdoor (Unskilled)
c)
Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
Formwork @ 3 per cent of (a+b+c)
d&e) Overheads & Contractors Profit
cost of 15 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/15
Case II : Using Batching Plant, Transit Mixer and
Concrete Pump (RCC M 35)
Unit = cum
Taking output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
b)
Labour
Mate
Mason
Mazdoor (Unskilled)
c)
Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader (capacity 1 cum)
Transit Mixer ( capacity 4.0 cu.m ) :
Transit Mixer 4 cum capacity for lead upto 1 km.
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump
Formwork of (a+b+c)
d&e) Overheads & Contractors Profit
cost of 120 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/120
Note : Where ever concrete is carried out using batching
plant, transit mixer, concrete pump, Admixtures @ 0.4 per
cent of weight of cement may be added for achieving desired
slump of concrete.
(v) RCC M40 Grade (Design Mix)
Using Batching Plant, Transit Mixer and Concrete Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement
Coarse Sand
20 mm Aggregate
10 mm Aggregate
Admixture
b)
Labour
Mate
Mason
Mazdoor (Unskilled)
c)
Machinery
Batching Plant
Generator 100 KVA
Loader 1 cum capacity
Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity for lead beyond 1 km.

hour

6.00

cum

3.00%

t
cum

50.64
54.00

cum

64.80

cum

43.20

day

day

3.00

day

18.84

hour

6.00

hour

6.00

hour

6.00

hour

15.00

t.km

300L

hour

6.00

cum

3.00%

52.20

cum

54.00

cum

64.80

cum

43.20

kg

206.00

day

day

3.00

day

18.84

hour

6.00

hour

6.00

hour

6.00

hour

15.00

t.km

300.L

Rate
Rs.

Amount
Rs.

Remarks

515

RBR_FNDN

Index-code

S. No
1

Description

Unit

Quantity

4
6.00

hour
Concrete Pump
Formwork on cost of concrete i.e. cost of material, labour and cum
machinery
d)
Overhead charges @ input on (a+b+c)
e)
Contractor's profit @ input on (a+b+c+d)
d&e) Overheads & Contractors Profit
cost of 120 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/120
13

RBR-FNDN-13

(A)
(i)

(ii)

(iii)

(iv)

Sinking of 6 m external diameter well (other than


pneumatic method of sinking) through all types of strata
namely sandy soil, clayey soil and rock as shown against
each case, complete as per drawing and technical
specifications 1207 MORTH. Depth of sinking is reckoned
from bed level.
Note : To arrive proportionate quantities keeping the
cross sectional area & depth (22/7xd2xh) for lesser
diametre wells than 6m
Unit = Running Meter.
Taking output = 1 m
Diameter of well - 6 m.
Sandy Soil
Depth below bed level upto 3.0 M
Rate of sinking = 0.50 m per hour.
a) Labour
Mate
Sinker ( skilled )
Sinking helper ( semi-skilled )
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum
capacity and accessories.
Consumables in sinking @10 per cent of (b)
c&d) Overheads & Contractors Profit
Rate per metre = (a+b+c+d)
Beyond 3m upto 10m depth
Rate of sinking = 0.33 m per hour.
a) Labour
Mate
Sinker
Sinking helper ( semi-skilled )
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum
capacity and accessories
Consumables in sinking @10 per cent of (b)
c&d) Overheads & Contractors Profit
Rate per metre = (a+b+c+d)
Beyond 10m upto 20m
a. Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Beyond 20m upto 30 m
a. Add 7.5 per cent for every additional meter depth of
sinking over the rate of sinking for the previous meter

Rate
Rs.

Amount
Rs.

Remarks

3.00%

day

day

1.00

day

2.12

hour

2.00
10.00%

day

day

1.25

day

2.65

hour

3.00
10.00%

b. Add 20 per cent of cost for Kentledge including supports,


loading arrangement and Labour.
(v) Beyond 30m upto 40 m
a. Add 10 per cent for every additional meter depth of
sinking over the rate of sinking for the previous meter
b. Add 20 per cent of cost for Kentledge including supports,
loading arrangement and Labour.

516

RBR_FNDN

Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

(B) Clayey Soil ( 6m dia. Well )

(i)

(ii)

(iii)

(iv)

Unit = Running Meter.


Taking output = 1 meter
Depth below bed level upto 3.0 M
Rate of sinking = 0.33 m per hour.
a) Labour
Mate
Sinker ( skilled )
Sinking helper ( semi-skilled )
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum
capacity and accessories
Consumables in sinking @ 10 per cent of (b)
c&d) Overheads & Contractors Profit
Rate per metre = (a+b+c+d)
Beyond 3m upto 10m depth
Rate of sinking = 0.17 m per hour.
a) Labour
Mate
Sinker
Sinking helper ( semi-skilled )
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum
capacity and accessories.
Air compressor with pneumatic chisel attachment for cutting
hard clay.
Consumables in sinking @ 10 per cent of (b)
c&d) Overheads & Contractors Profit
Rate per metre = (a+b+c+d)
Beyond 10 m upto 20 m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add for dewatering @ 5 per cent of cost, if required.
Beyond 20m upto 30 m
Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter

day

day

1.50

day

2.40

hour

3.00
10.00%

day

day

3.00

day

4.80

hour

6.00

hour

2.00
10.00%

Add 5 per cent of cost for dewatering of the cost, if required

Add 25 per cent of cost for Kentledge including supports,


loading arrangement and Labour ).
(v) Beyond 30m upto 40 m
Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering, if required
Add 20 per cent of cost for Kentledge including supports,
loading arrangement and Labour).
(C) Soft Rock (6m dia well )
Unit = Running Meter.
Taking output = 1 m
Depth in Soft rock strata up to 3m
Rate of sinking = 0.25 m per hour.
a) Labour
Mate
Sinker ( skilled )
Sinking helper ( semi-skilled )
Diver

day

day

3.00

day

20.92

day

0.50

517

RBR_FNDN

Index-code

S. No
1

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum hour
capacity and accessories.
hour
Air compressor with pneumatic breakers
Consumables in sinking @ 10 per cent of (b)
Add for dewatering @ of 5 per cent of (a+b), if required

14

RBR-FNDN-14

c&d) Overheads & Contractors Profit


Rate per metre = (a+b+c+d)
(D) Hard Rock (6m dia well )
Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking = 0.17 m per hour.
a) Material
Gelatine 80 per cent
Electric Detonators
b)
Labour
Mate
Driller
Blaster
Mazdoor (Unskilled)
Mazdoor (Skilled)
c)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum
capacity and accessories.
Hire & running charges of compressor with pneumatic
breaker/Jack hammer for drilling.
Dewatering @ 5 per cent of cost of (b+c), if required.
Consumables in sinking @ 10 per cent of cost of (b).
d&e) Overheads & Contractors Profit
Rate per metre = (a+b+c+d+e)
Sinking of 7 m external diameter well (other than
pneumatic method of sinking) through all types of strata
namely sandy soil, clayey soil and rock as shown against
each case, complete as per drawing and technical
specifications 1207 MORTH. Depth of sinking is reckoned
from bed level.
Unit = Running Meter.
Taking output = 1 m
Diameter of well - 7 m.
(A) Sandy Soil
(i) Depth below bed level upto 3.0 M
Rate of sinking = 0.30 m per hour.
a) Labour
Mate
Sinker ( skilled )
Sinking helper ( semi-skilled )
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum
capacity and accessories.
Consumables in sinking @10 per cent of (b)
c&d) Overheads & Contractors Profit
Rate per metre = (a+b+c+d)

4.00
3.50
10.00%

Kg

4.00

each

18.00

day

day

2.00

day

0.25

day

13.56

day

4.00

hour

6.00

hour

2.00

10.00%

day

day

1.25

day

2.65

hour

3.25
10.00%

518

RBR_FNDN

Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

(ii) Beyond 3m upto 10m depth

Rate of sinking = 0.22 m per hour.


a) Labour
Mate
Sinker
Sinking helper ( semi-skilled )
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum
capacity and accessories.
Consumables in sinking @10 per cent of (b)
c&d) Overheads & Contractors Profit
Rate per metre = (a+b+c+d)
(iii) Beyond 10m upto 20m

day

day

1.50

day

3.18

hour

4.50
10.00%

a. Add 5 per cent for every additional meter depth of sinking over the
rate of sinking for the previous meter
(iv) Beyond 20m upto 30 m
a. Add 7.5 per cent for every additional meter depth of sinking over
the rate of sinking for the previous meter
b. Add 20 per cent of cost for Kentledge including supports, loading
arrangement and Labour).
(v) Beyond 30m upto 40 m
a. Add 10 per cent for every additional meter depth of sinking over the
rate of sinking for the previous meter
b. Add 20 per cent of cost for Kentledge including supports, loading
arrangement, and Labour etc.
(B) Clayey Soil ( 7m dia. Well )

Unit = Running Meter.


Taking output = 1 cum
(i) Depth below bed level upto 3.0 M
Rate of sinking = 0.22 m per hour.
a) Labour
Mate
Sinker ( skilled )
Sinking helper ( semi-skilled )
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum
capacity and accessories.
Consumables in sinking @ 10 per cent of (b)
d&e) Overheads & Contractors Profit
Rate per metre = (a+b+c+d)
(ii) Beyond 3m upto 10m depth
Rate of sinking = 0.17 m per hour.
a) Labour
Mate
Sinker
Sinking helper ( semi-skilled )
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum
capacity and accessories.
Air compressor with pneumatic chisel attachment for cutting
hard clay.
Consumables in sinking @ 10 per cent of (b)
c&d) Overheads & Contractors Profit
Rate per metre = (a+b+c+d)
(iii) Beyond 10 m upto 20 m
a. Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b. Add for dewatering @ 5 per cent of cost, if required.

day

day

1.50

day

3.18

hour

4.50
10.00%

day

day

2.00

day

4.26

hour

6.00

hour

3.25
10.00%

519

RBR_FNDN

Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

(iv) Beyond 20m upto 30 m

a. Add 7.5 per cent for every additional meter depth of


sinking over the rate of sinking for the previous meter
b. Add 5 per cent of cost for dewatering on the cost, if
required
c. Add 25 per cent of cost for Kentledge including supports,
loading arrangement and Labour ).
(v) Beyond 30m upto 40 m
a. Add 10 per cent for every additional meter depth of
sinking over the rate of sinking for the previous meter
b. Add 5 per cent of cost for dewatering, if required
c. Add 20 per cent of cost for Kentledge including supports,
loading arrangement and Labour).
(C) Soft Rock ( 7m dia well )
Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking = 0.22 m per hour.
a) Labour
Mate
Sinker ( skilled )
Sinking helper ( semi-skilled )
Diver
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum
capacity and accessories.
Air compressor with pneumatic breakers
Consumables in sinking @ 10 per cent of (b)
Add for dewatering @ of 5 per cent of (a+b), if required
c)
Overhead charges @ input on (a+b)
d)
Contractor's profit @ input on (a+b+c)
c&d) Overheads & Contractors Profit
Rate per metre = (a+b+c+d)
(D) Hard Rock ( 7m dia well )
Unit = Running Meter
Taking output = 1 m
Depth in Hard rock strata up to 3 m
Rate of sinking = 0.17 m per hour.
a) Material
Gelatine 80 per cent
Electric Detonators
b)
Labour
Mate
Driller
Blaster
Mazdoor (Unskilled)
Mazdoor (Skilled)
Diver
c)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum
capacity and accessories.
Hire & running charges of compressor with pneumatic
breaker/Jack hammer for drilling.
Dewatering @ 5 per cent of cost of (b+c), if required.
Consumables in sinking @ 10 per cent of cost of (b).
d&e) Overheads & Contractors Profit
Rate per metre = (a+b+c+d+e)

day

day

4.00

day

10.58

day

0.75

hour

4.50

hour

3.75
10.00%

Kg

7.00

each

30.00

day

day

2.00

day

0.25

day

19.60

day

4.00

day

0.50

hour

6.00

hour

2.00

10.00%

520

RBR_FNDN

Index-code

S. No
1
15

RBR-FNDN-15

A
(i)

(ii)

(iii)

(iv)

(v)

(i)

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

Sinking of 8 m external diameter well (other than


pneumatic method of sinking ) through all types of strata
namely sandy soil, clayey soil and rock as shown against
each case, complete as per drawing and technical
specifications 1207 MORTH. Depth of sinking is reckoned
from bed level.
Unit = Running Meter.
Taking output = 1 m
Diameter of well - 8 m.
Sandy Soil
Depth below bed level upto 3.0 M
Rate of sinking @ 0.25 m/hour
a) Labour
Mate
Sinker ( skilled )
Sinking helper ( semi-skilled )
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum
capacity and accessories.
Consumables in sinking @10 per cent of (b)
c&d) Overheads & Contractors Profit
Rate per metre = (a+b+c+d)
Beyond 3m upto 10m depth
Rate of sinking @ 0.20 m/hour
a) Labour
Mate
Sinker
Sinking helper ( semi-skilled )
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum
capacity and accessories.
Consumables in sinking @10 per cent of (b)
c&d) Overheads & Contractors Profit
Rate per metre = (a+b+c+d)
Beyond 10m upto 20m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Beyond 20m upto 30 m
a. Add 7.5 per cent for every additional meter depth of
sinking over the rate of sinking for the previous meter
b. Add 20 per cent of cost for Kentledge including supports,
loading arrangement and Labour.
Beyond 30m upto 40 m
a. Add 10 per cent for every additional meter depth of
sinking over the rate of sinking for the previous meter
b. Add 20 per cent of cost for Kentledge including supports,
loading arrangement, and Labour etc.
Clayey Soil ( 8m dia. Well )
Unit = Running Meter.
Taking output = 1 meter
Depth from bed level upto 3.0 M
Rate of sinking @ 0.18 m/hour
a) Labour
Mate
Sinker ( skilled )
Sinking helper ( semi-skilled )

day

day

1.50

day

3.18

hour

4.00
10.00%

day

day

1.75

day

3.75

hour

5.00
10.00%

day

day

2.00

hour

3.72

521

RBR_FNDN

Index-code

S. No
1

(ii)

(iii)

(iv)

(v)

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

hour

5.50

b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum
capacity and accessories.
Consumables in sinking @ 10 per cent of (b)
c&d) Overheads & Contractors Profit
Rate per metre = (a+b+c+d)
Beyond 3m upto 10m depth
Rate of sinking @ 0.17 m/hour
a) Labour
Mate
Sinker
Sinking helper ( semi-skilled )
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum
capacity and accessories.
Air compressor with pneumatic chisel attachment for cutting
hard clay.
Consumables in sinking @ 10 per cent of (b)
c&d) Overheads & Contractors Profit
Rate per metre = (a+b+c+d)
Beyond 10 m upto 20 m
a. Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b. Add for dewatering @ 5 per cent of cost, if required.
Beyond 20m upto 30 m
a. Add 7.5 per cent for every additional meter depth of
sinking over the rate of sinking for the previous meter
b. Add 5 per cent of cost for dewatering on the cost, if
c. Add 25 per cent of cost for Kentledge including supports,
loading arrangement and Labour ).
Beyond 30m upto 40 m
a. Add 10 per cent for every additional meter depth of
sinking over the rate of sinking for the previous meter
b. Add 5 per cent of cost for dewatering, if required
c. Add 20 per cent of cost for Kentledge including supports,
loading arrangement and Labour).
Soft Rock ( 8m dia well )
Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.20 m/hour
a) Labour
Mate
Sinker ( skilled )
Sinking helper ( semi-skilled )
Diver
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum
capacity and accessories.
Air compressor with pneumatic breakers
Consumables in sinking @ 10 per cent of (b)
Add for dewatering @ of 5 per cent of (a+b), if required

10.00%

day

day

2.50

day

4.82

hour

6.00

hour

3.50
10.00%

day

day

4.00

day

12.68

day

1.00

hour

5.00

hour

3.75
10.00%

c&d) Overheads & Contractors Profit


Rate per metre = (a+b+c+d)

522

RBR_FNDN

Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

16

RBR-FNDN-16

Hard Rock ( 8m dia well )


Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking @ 0.17 m/hour
a) Material
Gelatine 80 per cent
Electric Detonators
b)
Labour
Mate
Driller
Blaster
Mazdoor (Unskilled)
Mazdoor (Skilled)
c)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum
capacity and accessories.
Hire & running charges of compressor with pneumatic
breaker/Jack hammer for drilling.
Dewatering @ 5 per cent of cost of (b+c), if required.
Consumables in sinking @ 10 per cent of cost of (b).
d&e) Overheads & Contractors Profit
Rate per metre = (a+b+c+d+e)
Sinking of 9 m external diameter well ( other than
pneumatic method of sinking ) through all types of strata
namely sandy soil, clayey soil and rock as shown against
each case, complete as per drawing and technical
specifications 1207 MORTH. Depth of sinking is reckoned
from bed level.
Unit = Running Meter.
Taking output = 1 m
Diameter of well - 9 m.
A Sandy Soil
(i) Depth below bed level upto 3.0 M
Rate of sinking @ 0.25 m/hour
a) Labour
Mate
Sinker ( skilled )
Sinking helper ( semi-skilled )
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum
capacity and accessories.
Consumables in sinking @10 per cent of (b)
c&d) Overheads & Contractors Profit
Rate per metre = (a+b+c+d)
(ii) Beyond 3m upto 10m depth
Rate of sinking @ 0.18 m/hour
a) Labour
Mate
Sinker
Sinking helper ( semi-skilled )
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum
capacity and accessories.
Consumables in sinking @10 per cent of (b)
c&d) Overheads & Contractors Profit
Rate per metre = (a+b+c+d)

Kg

8.00

each

32.00

day

day

2.00

day

0.25

day

21.09

day

4.00

hour

6.00

hour

2.00

10.00%

day

day

1.50

day

3.44

hour

4.00
10.00%

day

day

1.75

day

4.27

hour

5.50
10.00%

523

RBR_FNDN

Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

(iii) Beyond 10m upto 20m

(iv)

(v)

(i)

(ii)

(iii)

(iv)

(v)

a. Add 5 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter
Beyond 20m upto 30 m
a. Add 7.5 per cent for every additional meter depth of
sinking over the rate of sinking for the previous meter
b. Add 20 per cent of cost for Kentledge including supports,
loading arrangement and Labour.
Beyond 30m upto 40 m
a. Add 10 per cent for every additional meter depth of
sinking over the rate of sinking for the previous meter
b. Add 20 per cent of cost for Kentledge including supports,
loading arrangement, and Labour etc.
Clayey Soil ( 9m dia. Well )
Unit = Running Meter.
Taking output = 1 cum
Depth below bed level upto 3.0 M
Rate of sinking 0.17 m / hour
a) Labour
Mate
Sinker ( skilled )
Sinking helper ( semi-skilled )
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum
capacity and accessories.
Consumables in sinking @ 10 per cent of (b)
c&d) Overheads & Contractors Profit
Rate per metre = (a+b+c+d)
Beyond 3m upto 10m depth
Rate of sinking 0.15 m / hour
a) Labour
Mate
Sinker
Sinking helper ( semi-skilled )
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum
capacity and accessories.
Air compressor with pneumatic chisel attachment for cutting
hard clay.
Consumables in sinking @ 10 per cent of (b)
c&d) Overheads & Contractors Profit
Rate per metre = (a+b+c+d)
Beyond 10 m upto 20 m
a. Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b. Add for dewatering @ 5 per cent of cost, if required.
Beyond 20m upto 30 m
a. Add 7.5 per cent for every additional meter depth of
sinking over the rate of sinking for the previous meter
b. Add 5 per cent of cost for dewatering on the cost, if
required
c. Add 25 per cent of cost for Kentledge including supports,
loading arrangement and Labour ).
Beyond 30m upto 40 m
a. Add 10 per cent for every additional meter depth of
sinking over the rate of sinking for the previous meter
b. Add 5 per cent of cost for dewatering, if required
c. Add 20 per cent of cost for Kentledge including supports,
loading arrangement and Labour).

day

day

2.25

day

3.99

hour

5.75
10.00%

day

day

2.50

day

5.34

hour

6.50

hour

3.75
10.00%

524

RBR_FNDN

Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

Soft Rock ( 9m dia well )


Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata up to 3m
Rate of sinking 0.15 m / hour
a) Labour
Mate
Sinker ( skilled )
Sinking helper ( semi-skilled )
Diver
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum
capacity and accessories.
Air compressor with pneumatic breakers
Consumables in sinking @ 10 per cent of (b)
Add for dewatering @ of 5 per cent of (a+b), if required
c&d) Overheads & Contractors Profit
Rate per metre = (a+b+c+d)
D Hard Rock ( 9m dia well )
Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking 0.15 m / hour
a) Material
Gelatine 80 per cent
Electric Detonators
b)
Labour
Mate
Driller
Blaster
Mazdoor (Unskilled)
Mazdoor (Skilled)
Diver
c)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum
capacity and accessories.
Hire & running charges of compressor with pneumatic
breaker/Jack hammer for drilling.
Dewatering @ 5 per cent of cost of (b+c), if required.
Consumables in sinking @ 10 per cent of cost of (c).
d&e) Overheads & Contractors Profit
Rate per metre = (a+b+c+d+e)
17

RBR-FNDN-17

day

day

4.00

day

14.76

day

1.20

hour

6.50

hour

4.00
10.00%

Kg

10.00

each

40.00

day

day

2.00

day

0.25

day

23.17

day

4.00

day

1.00

hour

7.00

hour

2.50

10.00%

Sinking of 10 m external diameter well (other than pneumatic


method of sinking) through all types of strata namely sandy soil,
clayey soil and rock as shown against each case, complete as
per drawing and technical specifications 1207 MORTH. Depth of
sinking is reckoned from bed level.

Unit = Running Meter


Taking output = 1 m
Diameter of well - 10 m.
A Sandy Soil
(i) Depth below bed level upto 3.0 M
Rate of sinking 0.20 m / hour
a) Labour
Mate
Sinker ( skilled )
Sinking helper ( semi-skilled )

day

day

1.50

day

3.70

525

RBR_FNDN

Index-code

S. No
1

(ii)

(iii)

(iv)

(v)

(i)

(ii)

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

hour

5.00

b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum
capacity and accessories.
Consumables in sinking @10 per cent of (b)
c&d) Overheads & Contractors Profit
Rate per metre = (a+b+c+d)
Beyond 3m upto 10m depth
Rate of sinking 0.17 m / hour
a) Labour
Mate
Sinker
Sinking helper ( semi-skilled )
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum
capacity and accessories.
Consumables in sinking @10 per cent of (b)
c&d) Overheads & Contractors Profit
Rate per metre = (a+b+c+d)
Beyond 10m upto 20m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Beyond 20m upto 30 m
a. Add 7.5 per cent for every additional meter depth of
sinking over the rate of sinking for the previous meter
b. Add 20 per cent of cost for Kentledge including supports,
loading arrangement and Labour.
Beyond 30m upto 40 m
a. Add 10 per cent for every additional meter depth of
sinking over the rate of sinking for the previous meter
b. Add 20 per cent of cost for Kentledge including supports,
loading arrangement, and Labour etc.
Clayey Soil (10m dia. Well )
Unit = Running Meter
Taking output = 1 cum
Depth below bed level upto 3.0 M
Rate of sinking 0.18m/hour.
a) Labour
Mate
Sinker ( skilled )
Sinking helper ( semi-skilled )
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum
capacity and accessories.
Consumables in sinking @ 10 per cent of (b)
c&d) Overheads & Contractors Profit
Rate per metre = (a+b+c+d)
Beyond 3m upto 10m depth
Rate of sinking 0.15m/hour.
a) Labour
Mate
Sinker
Sinking helper ( semi-skilled )
b)
Machinery

10.00%

day

day

2.00

day

4.56

hour

5.75
10.00%

day

day

2.50

day

5.75

hour

6.00
10.00%

day

day

3.00

day

5.90

a. Hire & running charges of crane with grab bucket of 0.75 cum hour
capacity and accessories.
b. Air compressor with pneumatic chisel attachment for cutting hard hour
clay

6.00

c. Consumables in sinking @ 10 per cent of (b)


c&d) Overheads & Contractors Profit
Rate per metre = (a+b+c+d)

4.00
10.00%

526

RBR_FNDN

Index-code

S. No
1

Description

2
(iii) Beyond 10 m upto 20 m
a. Add 5 per cent for every additional meter depth of sinking over the
rate of sinking for the previous meter

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

day
day

4.00

day

16.86

day

1.40

hour

7.00

b. Add for dewatering @ 5 per cent of cost, if required.


(iv) Beyond 20m upto 30 m
a. Add 7.5 per cent for every additional meter depth of sinking over
the rate of sinking for the previous meter
b. Add 5 per cent of cost for dewatering on the cost, if required
c. Add 25 per cent of cost for Kentledge including supports, loading
arrangement and Labour ).
(iv) Beyond 30m upto 40 m
a. Add 10 per cent for every additional meter depth of sinking over the
rate of sinking for the previous meter
b. Add 5 per cent of cost for dewatering, if required
c. Add 20 per cent of cost for Kentledge including supports, loading
arrangement and Labour).
C

Soft Rock (10m dia well )


Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking 0.14m/hour.
a) Labour
Mate
Sinker ( skilled )
Sinking helper ( semi-skilled )
Diver
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum
capacity and accessories.
Air compressor with pneumatic breakers
Consumables in sinking @ 10 per cent of (b)
Add for dewatering @ 5 per cent of cost, if required
c&d) Overheads & Contractors Profit
Rate per metre = (a+b+c+d)
D Hard Rock (10m dia well )
Unit = Running Meter.
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking 0.12 m/ hour.
a) Material
Gelatine 80 per cent
Electric Detonators
b)
Labour
Mate
Driller
Blaster
Mazdoor (Unskilled)
Mazdoor (Skilled)
c)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum
capacity and accessories.
Hire & running charges of compressor with pneumatic
breaker/Jack hammer or drill
Dewatering @ 5 per cent of cost (c), if required.
Consumables in sinking @ 10 per cent of cost of (c).
d&e) Overheads & Contractors Profit
Rate per metre = (a+b+c+d+e)

hour

4.25
10.00%

Kg

11.00

each

44.00

day

day

2.00

day

0.25

day

25.27

day

4.00

hour

8.50

hour

3.00

10.00%

527

RBR_FNDN

Index-code

S. No
1
18

RBR-FNDN-18

A
(i)

(ii)

(iii)

(iv)

(v)

(i)

(ii)

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

Sinking of 11 m external diameter well ( other than


pneumatic method of sinking ) through all types of strata
namely sandy soil, clayey soil and rock as shown against
each case, complete as per drawing and technical
specifications 1207 MORTH. Depth of sinking is reckoned
from bed level.
Unit = Running Meter
Taking output = 0.50 m
Diameter of well - 11 m.
Sandy Soil
Depth from bed level upto 3.0 M
Rate of sinking @ 0.15 m/hour
a) Labour
Mate
Sinker ( skilled )
Sinking helper (semi-skilled)
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum
capacity and accessories.
Consumables in sinking @10 per cent of (b)
d&e) Overheads & Contractors Profit
Cost for 0.5m = a+b+c+d
Rate per metre = (a+b+c+d)/0.50
Beyond 3m upto 10m depth
Rate of sinking @ 0.13 m/hour
a) Labour
Mate
Sinker
Sinking helper (semi-skilled)
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum
capacity and accessories.
Consumables in sinking @10 per cent of (b)
c&d) Overheads & Contractors Profit
Cost for 0.5m = a+b+c+d
Rate per metre = (a+b+c+d)/0.50
Beyond 10m upto 20m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Beyond 20m upto 30 m
a. Add 7.5 per cent for every additional meter depth of
sinking over the rate of sinking for the previous meter
b. Add 20 per cent of cost for Kentledge including supports,
loading arrangement and Labour.
Beyond 30m upto 40 m
a. Add 10 per cent for every additional meter depth of
sinking over the rate of sinking for the previous meter
b. Add 20 per cent of cost for Kentledge including supports,
loading arrangement, and Labour etc.
Clayey Soil (11 m dia. Well )
Unit = Running Meter
Taking output = 0.50 meter
Depth from bed level upto 3.0 M
Rate of sinking @ 0.10 m/hour
a) Labour
Mate
Sinker ( skilled )
Sinking helper (semi-skilled)
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum
capacity and accessories.
Consumables in sinking @ 10 per cent of (b)
c&d) Overheads & Contractors Profit
Cost for 0.5m = a+b+c+d
Rate per metre = (a+b+c+d)/0.50
Beyond 3m upto 10m depth
Rate of sinking @ 0.08 m/hour
a) Labour
Mate
Sinker
Sinking helper (semi-skilled)
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum
capacity and accessories.
Air compressor with pneumatic chisel attachment for cutting
hard clay
Consumables in sinking @ 10 per cent of (b)

day

day

1.50

day

3.51

hour

6.00
10.00%

day

day

2.00

day

4.82

hour

4.00
10.00%

day

day

2.50

day

4.26

hour

5.00
10.00%

day

day

3.50

day

6.18

hour

6.00

hour

4.25
10.00%

528

RBR_FNDN

Index-code

S. No
1

(iii)

(iv)

(v)

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

c&d) Overheads & Contractors Profit


Cost for 0.5m = a+b+c+d
Rate per metre = (a+b+c+d)/0.50
Beyond 10 m upto 20 m
a. Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b. Add for dewatering @ 5 per cent of cost, if required.
Beyond 20m upto 30 m
a. Add 7.5 per cent for every additional meter depth of
sinking over the rate of sinking for the previous meter
b. Add 5 per cent of cost for dewatering on the cost, if
required
c. Add 25 per cent of cost for Kentledge including supports,
loading arrangement and Labour ).
Beyond 30m upto 40 m
a. Add 10 per cent for every additional meter depth of
sinking over the rate of sinking for the previous meter
b. Add 5 per cent of cost for dewatering, if required
c. Add 20 per cent of cost for Kentledge including supports,
loading arrangement and Labour).
Soft Rock (11m dia well )
Unit = Running Meter.
Taking output = 0.50 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.06 m/hour
a) Labour
Mate
Sinker ( skilled )
Sinking helper (semi-skilled)
Diver
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum
capacity and accessories.
Air compressor with pneumatic breakers
Consumables in sinking @ 10 per cent of (b)
Add for dewatering @ 5 per cent of cost, if required
c&d) Overheads & Contractors Profit
Cost for 0.5m = a+b+c+d
Rate per metre = (a+b+c+d)/0.50

day

day

4.25

day

18.95

day

1.50

hour

8.00

hour

4.50
10.00%

529

RBR_FNDN

Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

Kg

12.00

each

48.00

19

RBR-FNDN-19

Hard Rock (11m dia well )


Unit = Running Meter.
Taking output = 0.50 m
Depth in hard rock upto 3 m
Rate of sinking @ 0.05 m/hour
a) Material
Gelatine 80 per cent
Electric Detonators
b)
Labour
Mate
Driller
Blaster
Mazdoor (Unskilled)
Mazdoor (Skilled)
c)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum
capacity and accessories.
Hire & running charges of compressor with pneumatic
breaker/Jack hammer or drill
Dewatering @ 5 per cent of cost (c), if required.
Consumables in sinking @ 10 per cent of cost of (c).
d&e) Overheads & Contractors Profit
Cost for 0.5m = a+b+c+d
Rate per metre = (a+b+c+d)/0.50
Sinking of 12 m external diameter well ( other than
pneumatic method of sinking ) through all types of strata
namely sandy soil, clayey soil and rock as shown against
each case, complete as per drawing and technical
specifications 1207 MORTH. Depth of sinking is reckoned
from bed level.
Unit = Running Meter
Taking output = 0.25 m
Diameter of well - 12 m.
A Sandy Soil
(i) Depth below bed level upto 3.0 M
Rate of sinking @ 0.05 m/hour
a) Labour
Mate
Sinker ( skilled )
Sinking helper (semi-skilled)
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum
capacity and accessories.
Consumables in sinking @10 per cent of (b)
c&d) Overheads & Contractors Profit
Cost for 0.25m = a+b+c+d
Rate per metre = (a+b+c+d)/0.25
(ii) Beyond 3m upto 10m depth
Rate of sinking @ 0.038 m/hour
a) Labour
Mate
Sinker
Sinking helper (semi-skilled)
b)
Machinery

day

day

2.00

day

0.25

day

27.35

day

4.00

hour

10.00

hour

3.50

10.00%

day
day

1.75

day

4.22

hour

6.00
10.00%

day

day

2.50

day

5.12

Hire & running charges of crane with grab bucket of 0.75 cum capacity hour
and accessories.

6.50

Consumables in sinking @10 per cent of (b)


c&d) Overheads & Contractors Profit
Cost for 0.25m = a+b+c+d
Rate per metre = (a+b+c+d)/0.25

10.00%

530

RBR_FNDN

Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

(iii) Beyond 10m upto 20m

(iv)

(v)

(i)

(ii)

(iii)

(iv)

a. Add 5 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter
Beyond 20m upto 30 m
a. Add 7.5 per cent for every additional meter depth of
sinking over the rate of sinking for the previous meter
b. Add 20 per cent of cost for Kentledge including supports,
loading arrangement and Labour.
Beyond 30m upto 40 m
a. Add 10 per cent for every additional meter depth of
sinking over the rate of sinking for the previous meter
b. Add 20 per cent of cost for Kentledge including supports,
loading arrangement, and Labour etc.
Clayey Soil (12 m dia. Well )
Unit = Running Meter.
Taking output = 0.25 meter.
Depth below bed level upto 3.0 M
Rate of sinking @ 0.04 m/hour
a) Labour
Mate
Sinker ( skilled )
Sinking helper (semi-skilled)
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum
capacity and accessories.
Consumables in sinking @ 10 per cent of (b)
c&d) Overheads & Contractors Profit
Cost for 0.25m = a+b+c+d
Rate per metre = (a+b+c+d)/0.25
Beyond 3m upto 10m depth
Rate of sinking @ 0.03 m/hour
a) Labour
Mate
Sinker
Sinking helper (semi-skilled)
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum
capacity and accessories.
Air compressor with pneumatic chisel attachment for cutting
hard clay.
Consumables in sinking @ 10 per cent of (b)
c&d) Overheads & Contractors Profit
Cost for 0.25m = a+b+c+d
Rate per metre = (a+b+c+d)/0.25
Beyond 10 m upto 20 m
a. Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b. Add for dewatering @ 5 per cent of cost, if required.
Beyond 20m upto 30 m
a. Add 7.5 per cent for every additional meter depth of
sinking over the rate of sinking for the previous meter
b. Add 5 per cent of cost for dewatering on the cost, if
required
c. Add 25 per cent of cost for Kentledge including supports,
loading arrangement and Labour ).

day

day

3.00

day

4.80

hour

6.25
10.00%

day

day

3.75

day

6.48

hour

8.33

hour

4.50
10.00%

531

RBR_FNDN

Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

(v) Beyond 30m upto 40 m

a. Add 10 per cent for every additional meter depth of


sinking over the rate of sinking for the previous meter
b. Add 5 per cent of cost for dewatering, if required
c. Add 20 per cent of cost for Kentledge including supports,
loading arrangement and Labour).
C Soft Rock (12m dia well )
Unit = Running Meter
Taking output = 0.25 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.025 m/hour
a) Labour
Mate
Sinker ( skilled )
Sinking helper (semi-skilled)
Diver
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum
capacity and accessories.
Air compressor with pneumatic chisel attachment for cutting
hard clay.
Consumables in sinking @ 10 per cent of (b)
Add for dewatering @ 5 per cent, if required
c&d) Overheads & Contractors Profit
Cost for 0.25m = a+b+c+d
Rate per metre = (a+b+c+d)/0.25
D Hard Rock (12m dia well )
Unit = Running Meter
Taking output = 0.25 m
Depth in hard rock strata upto 3 m
Rate of sinking @ 0.020 m/hour
a) Material
Gelatine80 per cent
Electric detonator
b)
Labour
Mate
Driller
Blaster
Mazdoor (Unskilled)
Mazdoor (Skilled)
c)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum
capacity and accessories.
Hire & running charges of compressor with pneumatic
breaker / Jack hammer or drill
Dewatering @ 5 per cent, if required.
Consumables in sinking @ 10 per cent of (c).
c&d) Overheads & Contractors Profit
Cost for 0.25m = a+b+c+d+e
Rate per metre = (a+b+c+d+e)/0.25

day

day

4.50

day

21.06

day

1.75

hour

10.00

hour

4.75
10.00%

Kg

14.00

each

56.00

day

day

2.00

day

0.25

day

29.44

day

4.50

hour

12.50

hour

4.00

10.00%

532

RBR_FNDN

Index-code

S. No
1
20

RBR-FNDN-20

A
(i)

(ii)

(iii)

(iv)

(v)

(i)

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

day
day
day

1.25
3.95

hour

5.50

Sinking of Twin D Type well (other than pneumatic


method of sinking) through all types of strata namely
sandy soil, clayey soil and rock as shown against each
case, complete as per drawing and technical
specifications 1207 MORTH. Depth of sinking is reckoned
from bed level.
Unit = Running Meter
Taking output = 1 m
Dimensions of well.
Overall length = 12 m
Overall width = 6 m
Sandy Soil
Depth from bed level upto 3.0 M
Rate of sinking @ 0.18 m/hour
a) Labour
Mate
Sinker ( skilled )
Sinking helper (semi-skilled)
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum
capacity and accessories.
Consumables in sinking @10 per cent of (b)
c&d) Overheads & Contractors Profit
Rate per metre = (a+b+c+d)
Beyond 3m upto 10m depth
Rate of sinking @ 0.17 m/hour
a) Labour
Mate
Sinker
Sinking helper (semi-skilled)
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum
capacity and accessories.
Consumables in sinking @10 per cent of (b)
c&d) Overheads & Contractors Profit
Rate per metre = (a+b+c+d)
Beyond 10m upto 20m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Beyond 20m upto 30 m
a. Add 7.5 per cent for every additional meter depth of
sinking over the rate of sinking for the previous meter
b. Add 20 per cent of cost for Kentledge including supports,
loading arrangement and Labour.
Beyond 30m upto 40 m
a. Add 10 per cent for every additional meter depth of
sinking over the rate of sinking for the previous meter
b. Add 20 per cent of cost for Kentledge including supports,
loading arrangement, and Labour etc.
Clayey Soil (Twin D Type Well )
Unit = Running Meter
Taking output = 1 meter
Depth below bed level upto 3.0 M
Rate of sinking @ 0.16 m/hour
a) Labour
Mate
Sinker ( skilled )
Sinking helper (semi-skilled)
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum
capacity and accessories.
Consumables in sinking @ 10 per cent of (b)
c&d) Overheads & Contractors Profit
Rate per metre = (a+b+c+d)

10.00%

day
day
day

1.50
4.30

hour

5.88
10.00%

day

day
day

2.50
4.26

hour

6.25
10.00%

533

RBR_FNDN

Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

(ii) Beyond 3m upto 10m depth

Rate of sinking @ 0.15 m/hour


a) Labour
Mate
Sinker
Sinking helper (semi-skilled)
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum
capacity and accessories.
Air compressor with pneumatic chisel attachment for cutting
hard clay.
Consumables in sinking @ 10 per cent of (b)
c&d) Overheads & Contractors Profit
Rate per metre = (a+b+c+d)
(iii) Beyond 10 m upto 20 m
a. Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b. Add for dewatering @ 5 per cent of cost, if required.
(iv) Beyond 20m upto 30 m
a. Add 7.5 per cent for every additional meter depth of
sinking over the rate of sinking for the previous meter
b. Add 5 per cent of cost for dewatering on the cost, if
c. Add 25 per cent of cost for Kentledge including supports,
loading arrangement and Labour ).
(v) Beyond 30m upto 40 m

day

day

3.25

day

6.45

hour

6.67

hour

4.50
10.00%

a. Add 10 per cent for every additional meter depth of sinking over the
rate of sinking for the previous meter

b. Add 5 per cent of cost for dewatering, if required


c. Add 20 per cent of cost for Kentledge including supports, loading
arrangement and Labour).
C

Soft Rock (Twin D Type Well )


Unit = Running Meter
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.12 m/hour
a) Labour
Mate
Sinker ( skilled )
Sinking helper (semi-skilled)
Diver
b)
Machinery

day

day

4.50

day

15.86

day

1.50

Hire & running charges of crane with grab bucket of 0.75 cum capacity hour
and accessories.
hour
Air compressor with pneumatic breakers

8.33

Consumables in sinking @ 10 per cent of (b)


Add for dewatering @ 5 per cent, if required
c&d) Overheads & Contractors Profit
Rate per metre = (a+b+c+d)
D Hard Rock (Twin D Type Well )
Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking @ 0.10 m/hour
a) Material
Geletine80 per cent
Electric detonators
b)
Labour
Mate
Driller
Blaster
Mazdoor (Unskilled)
Mazdoor (Skilled)

6.00
10.00%

Kg

10.00

each

40.00

day

day
day
day

2.00
0.25
26.34

day

4.25

534

RBR_FNDN

Index-code

S. No
1

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

c)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum hour
capacity and accessories.
Hire & running charges of compressor with pneumatic hour
breaker/Jack hammer or drill
Dewatering @ 5 per cent of cost of (b+c), if required.
Consumables in sinking @ 10 per cent of (b).
d&e) Overheads & Contractors Profit
Rate per metre = (a+b+c+d+e)
21

RBR-FNDN-21

10.00
3.00

10.00%

Pneumatic sinking of wells with equipment of approved design,


drawing and specifications worked by competent and trained
personnel and comprising of compression and decompression
chambers, reducers, two air locks separately for men and plant &
materials, arrangement for supply of fresh air to working
chambers, check valves, exhaust valves, shafts made from steel
plates of riveted construction not less than 6 mm thick to
withstand an air pressure of 0.50 MPa, controlled blasting of hard
rock where required, staircases and 1 m wide landing platforms
with railing, arrangement for compression and decompression,
electric lighting of 50 V maximum, proper rooms for rest and
medical examinations and compliance with safety precautions as
per IS:4138, all as per clause1207.6 of MoRTH Specifications.

Unit - 1 cum
Taking output = 5 cum
a) Material
M35 grade RCC corbel provided for supporting of equipment
(Dimensions as per ground conditions). Rate may be adopted
vide Item 4 (H)
HYSD bar reinforcement in corbel
Blasting material
Gelatine 80 per cent
Electric detonators
b)
Labour
Medical Officer
Para medical personnel
Mate
Driller
Blaster
Mazdoor unskilled (for cutting, blasting, cleaning, removal of
Material etc.)

Cum

8.00

0.48

Kg

1.50

each

6.00

day
day
day
day
day
day

0.50
1.00
1.00
0.50
31.86

Mazdoor (Skilled) (for fixation and removal of adopter for air lock, day
carrying out mechanical and electrical operations and repairs and other
skilled jobs.)
day
Diver

10.00

c)
Machinery
(i) Induction, denudation and erection of plant and
equipment including all components and accessories for
pneumatic method of well sinking.
Induction and denudation
Erection at site and commissioning
Usage of plant and equipment for pneumatic method of well
sinking
Air compressor 250 cfm, 2 nos.
Hire and running charges of crane of 15 tonne capacity
Motorised barge of 20 tonne capacity
Boat to carry at least 20 persons
Electric generating set 33 KVA
Tipper 10 tonne capacity
d&e) Overheads & Contractors Profit
Cost for 5 cum = a+b+c+d+e (see notes below)
Rate per cum = (a+b+c+d+e)/5

hour

4.00
6.00

L.S
L.S
hour

6.00

hour

12.00

hour

6.00

hour

6.00

hour

6.00

hour

6.00

hour

6.00

535

RBR_FNDN

Index-code

S. No
1

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

2
3
4
5
6
Note : 1. The cost of induction, denudation and erection of equipment shall be divided by the total quantity
of pneumatic sinking for all the wells of a particular bridge to arrive at the per cum rate on account of this
item.
2. Cost of pneumatic sinking per cum of individual wells will be added to the cost indicated at (1) above to
arrive at the final rate of pneumatic sinking per cum.
3. The cost of induction and denudation will depend upon the distance involved for shifting of equipment
which may be assessed in individual cases as per actual ground conditions at the time of making of cost
estimates.
4. In case pneumatic sinking is involved on a dry bed, the provision of barge and boat may be omitted.

Remarks
7

5. The necessity and dimensions of the corbel will be as per actual ground conditions.

RBR-FNDN-22

22

6. Small equipments like welding sets, pumps, vibrators, pneumatic tools, portable lamps, fire extinguishers,
hose pipes etc., have not been included as the same are covered as items of minor T&P under overhead
charges.
7. Depth of sinking shall be restricted to 30 m.
Sand Filling in Wells complete as per Drawing and Technical
Specifications 1207 MORTH.

Unit = 1 cum
Taking output = 1 cum
a) Material
Sand (assuming 20 per cent voids )
b)
Labour
Mate
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per cum (a+b+c+d)
23

RBR-FNDN-23

cum

1.00

day
day

0.31

1.05

Providing Steel Liner 10 mm thick for Curbs and 6 mm thick for


Staining of Wells including Fabricating and Setting out as per
Detailed Drawing as per Tech. Specifications 1200 & 1900
MORTH.

Unit = 1 MT
Taking output = 1 MT
a) Material
i) Structural steel including 5 per cent wastage
b)
Labour
Mate
Fitter
Blacksmith
Welder
Mazdoor (Unskilled)

day

day

6.00

day

5.00

day

5.00

day

11.24

Pile diameter-750 mm
Unit = meter
Taking output = 15 m
a) Materials
cum
PCC Grade M35
Rate for concrete may be adopted same as for bottom plug
vide item no. 12( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia.
b)
Machinery( for boring and construction )

6.62

Electrodes, cutting gas and other consumables @ 5 per cent on cost a


(a) above.

c&d) Overheads & Contractors Profit


Rate for per MT (a+b+c+d)
24

RBR-FNDN-24

Bored cast-in-situ M35 grade R.C.C. Pile excluding


Reinforcement complete as per Drawing and Technical
Specifications in Section 1100 & 1700 MORTH and removal of
excavated earth with all lifts and lead upto 1000 m.

Hire and running charges of hydraulic piling rig with power unit and hour
complete accessories including shifting from one bore location to
another.
hour
Hire and running charges of Bentonite pump

6.00

Hire and running charges of light crane for lowering reinforcement hour
cage
hour
Loader I cum bucket capacity.

0.50

Tipper 5.5 cum capacity for disposal of muck from pile bore hole

0.30

hour

6.00

0.30

536

RBR_FNDN

Index-code

S. No
1

Description

Unit

Quantity

3
kg

4
300.00

Bentonite
c)
Labour
Mate/Supervisor
Mazdoor (Unskilled)
d&e) Overheads & Contractors Profit
Cost for 15 m = a+b+c+d+d+e
Rate per metre (a+b+c+d+e)/15
25

RBR-FNDN-25

day

day

3.64

Pile diameter-1000 mm
Unit = meter
Taking output = 10 m
a) Materials
cum
PCC Grade M35
Rate for concrete may be adopted same as for bottom
plug vide item no. 12 ( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia.
b)
Machinery( for boring and construction )

7.85

Hire and running charges of hydraulic piling rig with power unit and hour
complete accessories including shifting from one bore location to
another.
hour
Hire and running charges of Bentonite pump

6.00

Hire and running charges of light crane for lowering hour


reinforcement cage
hour
Loader I cum bucket capacity.

0.50

Bentonite
c)
Labour
Mate/Supervisor
Mazdoor (Unskilled)
d&e) Overheads & Contractors Profit
Cost for 10 m = a+b+c+d+d+e
Rate per metre (a+b+c+d+e)/10
26

Amount
Rs.

Remarks

Bored cast-in-situ M35 grade R.C.C. Pile excluding


Reinforcement complete as per Drawing and Technical
Specifications in Section 1100, 1600 & 1700 MORTH and removal
of excavated earth with all lifts and lead upto 1000 m.

Tipper 5.5 cum capacity for disposal of muck from pile bore hole

RBR-FNDN-26

Rate
Rs.

hour
kg

6.00

0.40
0.40
350.00

day

day

4.16

Pile diameter-1200 mm
Unit = meter
Taking output = 9 m
a) Materials
cum
PCC Grade M35
Rate for concrete may be adopted same as for bottom plug
vide item no. 12( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia.
b)
Machinery( for boring and construction )

10.17

Bored cast-in-situ M35 grade R.C.C. Pile excluding


Reinforcement complete as per Drawing and Technical
Specifications in Section 1100 & 1700 MORTH and removal of
excavated earth with all lifts and lead upto 1000 m.

Hire and running charges of hydraulic piling rig with power unit and hour
complete accessories including shifting from one bore location to
another.
hour
Hire and running charges of Bentonite pump

6.00

Hire and running charges of light crane for lowering hour


reinforcement cage
hour
Loader I cum bucket capacity.

0.50

Tipper 5.5 cum capacity for disposal of muck from pile bore hole

Bentonite
c)
Labour
Mate/Supervisor
Mazdoor (Unskilled)
d&e) Overheads & Contractors Profit
Cost for 9 m = a+b+c+d+d+e
Rate per metre (a+b+c+d+e)/9

6.00

0.50

hour

0.50

kg

385.00

day

day

4.68

537

RBR_FNDN

Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

2
Driven cast-in-place vertical M35 grade R.C.C. Pile excluding
Reinforcement complete as per Drawing and & Technical
Specification in Section 1100 & 1700 MORTH

cum

17.66

Kg

160.00

Kg

70.00

Kg

50.00

hour

6.00

hour

0.50

27

RBR-FNDN-27

Pile diameter - 750 mm


Unit = Running meter
Taking output = 40 metre
a) Materials
PCC Grade M35
Rate for concrete may be adopted same as for bottom plug
vide item no. 12( C ) (IV)
b)
Materials Pile shoes
i) C.I. shoes for the pile
ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m
iii) Steel helmet and cushion block on top of casing head
during driving
c)
Machinery
Hire and running charges of piling rig Including double acting
pile driving hammer complete with power unit and
accessories.
Hiring and running charges for light crane 5 tonnes lifting
capacity for lowering reinforcement and handling steel
casing.
d)
Labour
Mate/Supervisor
Mazdoor (Unskilled)
e&f) Overheads & Contractors Profit
Cost for 40 m = a+b+c+d+e
Rate per metre (a+b+c+d+e)/40

day

day

3.12

Note : 1.The quantity of concrete required to be removed above the designed top level of concrete, if any,
will be provided for in the rate analysis.
2. In case steel lining is included in the design for driven cast-in-situ pile and is planned to be retained, the
same may be included in the rate analysis. In case the temporary steel casing used during casting is
planned to be removed, an additional cost @ 0.50 per cent of cost of concrete may be provided to cover its
usage.
28

RBR-FNDN-28

Driven cast-in-place vertical M35 grade R.C.C. Pile


excluding Reinforcement complete as per Drawing and &
Technical Specification in Section 1100 & 1700 MORTH
Pile diameter - 1000 mm
Unit = Running meter
Taking output = 30 metre
a) Materials
PCC Grade M35
Rate for concrete may be adopted same as for bottom
plug vide item no. 12 ( C ) (IV)
b) Materials Pile shoes
i) C.I. shoes for the pile
ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m
iii) Steel helmet and cushion block on top of casing head
during driving
c)
Machinery
Hire and running charges of piling rig Including double acting
pile driving hammer complete with power unit and
accessories.

cum

23.55

Kg

160.00

Kg

70.00

Kg

50.00

hour

6.00

Hiring and running charges for light crane 5 tonnes lifting capacity for hour
lowering reinforcement and handling steel casing.

0.50

Hire and running charges for light crane for lowering hour
reinforcement cage.
d)
Labour
day
Mate/Supervisor
day
Mazdoor (Unskilled)
e&f) Overheads & Contractors Profit
Cost for 30 m = a+b+c+d+e
Rate per metre (a+b+c+d+e)/30

0.50

4.16

538

RBR_FNDN

Index-code

S. No
1

29

RBR-FNDN-29

Description

Unit

Amount
Rs.

Remarks
7

Driven cast-in-place vertical M35 grade R.C.C. Pile


excluding Reinforcement complete as per Drawing and &
Technical Specification in Section 1100 & 1700 MORTH

Hire and running charges of piling rig Including double acting pile hour
driving hammer complete with power unit and accessories.
Hiring and running charges for light crane 5 tonnes lifting capacity for hour
lowering reinforcement and handling steel casing.

d)
Labour
Mate/Supervisor
Mazdoor (Unskilled)
e&f) Overheads & Contractors Profit
Cost for 20 m = a+b+c+d+e
Rate per metre (a+b+c+d+e)/20

30

Rate
Rs.

2
3
4
5
6
Note : 1.The quantity of concrete required to be removed above the designed top level of concrete, if any,
will be provided for in the rate analysis.
2. In case steel lining is included in the design for driven cast-in-situ pile and is planned to be retained, the
same may be included in the rate analysis. In case the temporary steel casing used during casting is
planned to be removed, an additional cost @ 0.50 per cent of cost of concrete may be provided to cover its
usage.

Pile diameter - 1200 mm


Unit = Running meter
Taking output = 20 metre
a) Materials
cum
PCC Grade M35
Rate for concrete may be adopted same as for bottom
plug vide item no. 12( C ) (IV)
b)
Materials Pile shoes
Kg
i) C.I. shoes for the pile
Kg
ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m
Kg
iii) Steel helmet on top of casing head during driving
c)
Machinery

RBR-FNDN-30

Quantity

22.61

160.00
70.00
50.00
6.00
0.50

day

day

4.68

Note : 1. The quantity of concrete required to be removed above the designed top level of concrete, if any,
will be provided for in the rate analysis.
2. In case steel lining is included in the design for driven cast-in-situ pile and is planned to be retained, the
same may be included in the rate analysis. In case the temporary steel casing used during casting is
planned to be removed, an additional cost @ 0.50 per cent of cost of concrete may be provided to cover its
usage.
Driven precast vertical M35 grade R.C.C. Piles excluding
Reinforcement complete as per Drawing and & Technical
Specification in Section 1100 & 1700 MORTH

Pile Diameter = 500 mm


Unit = Running Meter
Taking output = 60 m
a) Materials
cum
RCC Grade M35
Rate for concrete may be adopted same as for bottom plug
vide item no. 12( F ) (IV)
b ) Material Pile shoes
Kg
a) C.I Shoes
Kg
b) M.S. shoes
c) Steel helmet and cushion block on top of pile head during driving.

11.78

240.00
105.00

Kg

30.00

hour

6.00

Vibrating Pile driving hammer complete with power unit and hour
accessories.

6.00

c)
Machinery
Crane20 t capacity

d)
Labour
Mate/Supervisor
Mazdoor (Unskilled)

day

day

3.12

Add 1 per cent of (a+b+c)


for carriage of piles from casting yard to
work site and stacking, and other imponderables during installation.

e&f) Overheads & Contractors Profit


Cost for 60 m = a+b+c+d+e+f
Rate per metre (a+b+c+d+e+f)/60
31

RBR-FNDN-31

Note : The quantity of concrete required to be removed above the designed top level of concrete, if any, will
be provided for in the rate analysis.
Driven precast vertical M35 grade R.C.C. Piles excluding
Reinforcement complete as per Drawing and & Technical
Specification in Section 1100 & 1700 MORTH

Pile Diameter = 750 mm


Unit = Running Meter
Taking output = 50 m
a) Materials
cum
RCC Grade M35
Rate for concrete may be adopted same as for bottom plug
vide item no. 12( F ) (IV)
b ) Material Pile shoes
Kg
a) C.I. shoes
Kg
b) M.S. shoes
c) Steel helmet and cushion block on top of pile head during driving.

c)

Kg

22.08

160.00
70.00
40.00

Machinery

539

RBR_FNDN

Index-code

S. No

Description

Unit

Quantity

3
hour

4
6.00

Vibrating Pile driving hammer complete with power unit and hour
accessories.

6.00

Crane 40 T capacity

d)
Labour
Mate/Supervisor
Mazdoor (Unskilled)

day

day

4.16

Rate
Rs.

Amount
Rs.

Remarks

Add 1 per cent of (a+b+c)


for carriage of piles from casting yard to
work site and stacking, and other imponderables during installation.

e&f) Overheads & Contractors Profit


Cost for 50 m = a+b+c+d+e+f
Rate per metre (a+b+c+d+e+f)/50
Note : The quantity of concrete required to be removed above the designed top level of
concrete, if any, will be provided for in the rate analysis.
32

RBR-FNDN-32

Driven precast vertical M35 grade R.C.C. Piles excluding


Reinforcement complete as per Drawing and & Technical
Specification in Section 1100 & 1700 MORTH

Pile Diameter = 1000 mm


Unit = Running Meter
Taking output = 40 m
a) Materials
RCC Grade M35

cum

31.40

b ) Material Pile shoes


a) C.I. shoes for the pile
b) M.S. shoes @ 35 Kg per pile of 15 m

Kg

160.00

Kg

70.00

c) Steel helmet and cushion block on top of pile head during driving.

Kg

50.00

hour

6.00

Vibrating Pile driving hammer complete with power unit and hour
accessories.

6.00

Rate for concrete may be adopted same as for bottom plug vide item
no. 12( F ) (IV)

c)
Machinery
Crane 50 t capacity.

d)
Labour
Mate/Supervisor
Mazdoor (Unskilled)

day

day

5.20

Add 1 per cent of (a+b+c)


for carriage of piles from casting yard to
work site and stacking, and other imponderables during installation.

e)
Overhead charges @ input on (b+c+d)
f)
Contractor's profit @ input on (b+c+d+e)
e&f) Overheads & Contractors Profit
Cost for 40 m = a+b+c+d+e+f
Rate per metre (a+b+c+d+e+f)/40
Note : The quantity of concrete required to be removed above the designed top level of
concrete, if any, will be provided for in the rate analysis.

540

RBR_FNDN

Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

2
Driven precast vertical M35 grade R.C.C. Piles excluding
Reinforcement complete as per Drawing and & Technical
Specification in Section 1100 & 1700 MORTH

33

RBR-FNDN-33

Size of pile - 300 mm x 300 mm


Unit = Running Meter
Taking output = 60 m
a) Materials
RCC Grade M-35
Rate for concrete may be adopted same as for bottom plug cum
vide item no. 12( F ) (IV)
b ) Material Pile shoes
kg
a) C I shoes
kg
b) M. S shoes
c) Steel helmet and cushion block on top of pile head during Kg
driving.
c)
Machinery
hour
Crane 10 tonne capacity
Vibrating Pile driving hammer complete with power unit and hour
accessories.

d ) Labour
Mate/Supervisor
Mazdoor (Unskilled)

5.40

240.00
105.00
30.00

6.00
6.00

day

day

3.12

Add 1 per cent of (a+b+c) for carriage of piles from casting yard to
work site and stacking, and other imponderables during installation.

e)
Overhead charges @ input on (b+c+d)
f)
Contractor's profit @ input on (b+c+d+e)
e&f) Overheads & Contractors Profit
Cost for 60 m = a+b+c+d+e+f
Rate per metre (a+b+c+d+e+f)/60
Note : The quantity of concrete required to be removed above the designed top level of
concrete, if any, will be provided for in the rate analysis.
34

RBR-FNDN-34

Driven precast vertical M35 grade R.C.C. Piles excluding


Reinforcement complete as per Drawing and & Technical
Specification in Section 1100 & 1700 MORTH

Size of pile - 500 mm x 500 mm


Unit = Running Meter
Taking output = 50 m
a) Materials
RCC Grade M-35
Rate for concrete may be adopted same as for bottom plug vide item cum
no. 12( F ) (IV)

b ) Material Pile shoes


kg
a) C I shoes
kg
b) M. S shoes
c) Steel helmet and cushion block on top of pile head during Kg
driving.
c)
Machinery
hour
Crane 20 tonne capacity

Vibrating Pile driving hammer complete with power unit and hour
accessories.

d ) Labour
Mate/Supervisor
Mazdoor (Unskilled)

12.50

160.00
70.00
30.00

6.00
6.00

day

day

4.16

Add 1 per cent of (a+b+c)


for carriage of piles from casting yard to
work site and stacking, and other imponderables during installation.

e&f) Overheads & Contractors Profit


Cost for 50 m = a+b+c+d+e+f
Rate per metre (a+b+c+d+e+f)/50
Note : The quantity of concrete required to be removed above the designed top level of
concrete, if any, will be provided for in the rate analysis.

541

RBR_FNDN

Index-code

S. No
1
35

RBR-FNDN-35

RBR-FNDN-36

36

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

Driven precast vertical M35 grade R.C.C. Piles excluding


Reinforcement complete as per Drawing and & Technical
Specification in Section 1100 & 1700 MORTH
Size of pile - 750 mm x 750 mm
Unit = Running Meter
Taking output = 40 m
a) Materials
RCC Grade M-35
22.50
Rate for concrete may be adopted same as for bottom plug cum
vide item no. 12( F ) (IV)
b ) Material
Pile shoes
kg
160.00
a) C I shoes
kg
70.00
b) M. S shoes
30.00
c) Steel helmet and cushion block on top of pile head during Kg
driving.
c)
Machinery
hour
6.00
Crane 20 tonne capacity
6.00
Vibrating Pile driving hammer complete with power unit and hour
accessories.
d ) Labour
day
0.18
Mate/Supervisor
day
4.50
Mazdoor (Unskilled)
1.00%
Add 1 per cent of (a+b+c)
for carriage of piles from
casting yard to work site and stacking, and other
imponderables during installation.
e&f) Overheads & Contractors Profit
Cost for 40 m = a+b+c+d+e+f
Rate per metre (a+b+c+d+e+f)/40
Note : The quantity of concrete required to be removed above the designed top level of
concrete, if any, will be provided for in the rate analysis.
Driven Vertical Steel Piles complete as per Drawing and
& Technical Specification in Section 1100 & 1900 MORTH
Section of the pile - H Section steel column 400 x 250 mm
(ISHB Series)
Unit = Running Meter
Taking output = 70 m
a) Materials
t
6.04
Structural steel including 5 per cent wastage @ 82.20 kg/m
b)
Machinery
Crane 10 T capacity
Vibrating Pile driving hammer complete with power unit and
other accessories.
c)
Labour
Mate/Supervisor
Mazdoor (Unskilled)
Add 0.5 per cent of (a+b+c)
for providing steel helmet on
top of pile head during driving, stacking of piles at site,
providing anti-corrosion treatment and other imponderables
during installation.
d&e) Overheads & Contractors Profit
Cost for 70 m = a+b+c+d+e
Rate per metre (a+b+c+d+e)/70

hour

6.00

hour

6.00

day

day

3.12
0.50%

542

RBR_FNDN

Index-code

S. No
1
37

RBR-FNDN-37

38

RBR-FNDN-38

39

RBR-FNDN-39

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

tonne
s

5.83

hour

6.00

hour

6.00

Driven Vertical Steel Piles complete as per Drawing and


& Technical Specification 1108 & Section 1100 & 1900
MORTH
Section of the pile - H Section steel column 450 x 250 mm
(ISHB Series)
Unit = Running Meter
Taking output = 60 m
a) Materials
Structural steel including 5 per cent wastage @92.50 kg/m
b)
Machinery
Crane 10 T capacity
Vibrating Pile driving hammer complete with power unit and
accessories.
c)
Labour
Mate/Supervisor
Mazdoor (Unskilled)
Add 0.5 per cent of (a+b+c)
for providing steel helmet and
cushion block on top of pile head during driving, stacking of
piles at site, providing anti-corrosive treatment and other
imponderables during installation.

day

day

3.64
0.50%

d&e) Overheads & Contractors Profit


Cost for 60 m = a+b+c+d+e
Rate per metre (a+b+c+d+e)/60
Pile Load Test on single Vertical Pile in accordance with
IS:2911(Part-IV) and as per Tech Specification 1113
MORTH
Unit = 1 MT
Taking output = 1 MT
t
1.00
a) Initial and routine load test
t
1.00
b) Lateral load test
Note : Although, this item is incidental to work and is not required to be included in BOQ of
contract, the same is required to be added in the estimate to assess cost of work.
Cement Concrete for Reinforced Concrete in Pile Cap
complete as per Drawing and Technical Specifications in
Section 1100, 1500 & 1700 MORTH
A. RCC Grade M20 (Design Mix)
Unit = cum
Taking output = 15 cum
(i) Using Concrete Mixer
a) Material
t
5.12
Cement
cum
6.75
Coarse sand
cum
8.10
20 mm Aggregate
cum
5.40
10 mm Aggregate
b)
Labour
day
Mate
day
1.50
Mason
day
20.90
Mazdoor (Unskilled) for concreting
1.00
Mazdoor (Unskilled) for breaking pile head, bending bars, day
cleaning etc.
c)
Machinery
hour
6.00
Concrete mixer (cap. 0.40/0.28 cum)
hour
6.00
Generator (capacity 33 KVA)
Formwork @ 4 per cent on cost of concrete i.e. cost of a) cum
Material,
b)
Labour
and c)
Machinery
d&e) Overheads & Contractors Profit
Cost for 15 cum = a+b+c+d+e
Rate per metre (a+b+c+d+e)/15

543

RBR_FNDN

Index-code

S. No
1

Description

2
(ii) RCC M 20 Design Mix Using Batching Plant, Transit Mixer

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

and Concrete Pump


a) Material
t
Cement
cum
Coarse sand
cum
20 mm Aggregate
cum
10 mm Aggregate
b)
Labour
day
Mate
day
Mason
day
Mazdoor (Unskilled) for concreting
Mazdoor (Unskilled) for breaking pile head, bending bars, day
cleaning etc.
c)
Machinery
hour
Batching Plant @ 20 cum/hour
hour
Generator 100 KVA
hour
Loader (capacity 1 cum)
Transit Mixer ( capacity 4.0 cu.m )
hour
Lead upto 1 Km
t.km
Lead beyond 1 Km, L - lead in Kilometer
hour
Concrete Pump
Formwork @ 4 per cent on cost of concrete i.e. cost of a) cum
Material,
b)
Labour
and c)
Machinery
d&e) Overheads & Contractors Profit
Cost for 15 cum = a+b+c+d+e
Rate per metre (a+b+c+d+e)/15
Note : The value of a, b and c may be taken as applicable i.e. either
batching plant.
B RCC Grade M25 Design Mix
Unit = cum
Taking output = 15 cum
(i) Using Concrete Mixer
a) Material
t
Cement
cum
Coarse sand
cum
20 mm Aggregate
cum
10 mm Aggregate
b)
Labour
day
Mate
day
Mason
day
Mazdoor (Unskilled) for concreting
Mazdoor (Unskilled) for breaking pile head, bending bars, day
cleaning etc.
c)
Machinery
hour
Concrete mixer (cap. 0.40/0.28 cum)
hour
Generator (capacity 33 KVA)
Formwork @ 4 per cent on cost of concrete i.e. cost of
a) cum
Material, b)
Labour
and
c)
Machinery
d&e) Overheads & Contractors Profit
Cost for 15 cum = a+b+c+d+e
Rate per metre (a+b+c+d+e)/15

5.12
6.75
8.10
5.40
0.38
2.66
1.00

0.75
0.75
0.75
2.00
37.5L
0.75
4.00%

using concrete mixer or

5.99
6.75
8.10
5.40
1.50
20.90
1.00

6.00
6.00
4.00%

544

RBR_FNDN

Index-code

S. No
1

Description

2
(ii) RCC M 25 Design Mix Using Batching Plant, Transit Mixer

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

and Concrete Pump


a) Material
t
Cement
cum
Coarse sand
cum
20 mm Aggregate
cum
10 mm Aggregate
b)
Labour
day
Mate
day
Mason
day
Mazdoor (Unskilled) for concreting
Mazdoor (Unskilled) for breaking pile head, bending bars, day
cleaning etc.
c)
Machinery
hour
Batching Plant @ 20 cum/hour
hour
Generator 125 KVA
hour
Loader (capacity 1 cum)
Transit Mixer ( capacity 4.0 cu.m )
hour
Lead upto 1 Km
t.km
Lead beyond 1 Km, L - lead in Kilometer
hour
Concrete Pump
Formwork @ 4 per cent on cost of concrete i.e. cost of cum
a) Material,
b)
Labour
and
c)
Machinery
d&e) Overheads & Contractors Profit
Cost for 15 cum = a+b+c+d+e
Rate per metre (a+b+c+d+e)/15
Note : The value of a, b and c may be taken as applicable i.e. either
batching plant.
C RCC Grade M30 Design Mix
Unit = cum
Taking output = 15 cum
(i) Using Concrete Mixer
a) Material
t
Cement
cum
Coarse sand
cum
20 mm Aggregate
cum
10 mm Aggregate
b)
Labour
day
Mate
day
Mason
day
Mazdoor (Unskilled) for concreting
Mazdoor (Unskilled) for breaking pile head, bending bars, day
cleaning etc.
c)
Machinery
hour
Concrete mixer (cap. 0.40/0.28 cum)
hour
Generator (capacity 33 KVA)
Formwork @ 4 per cent on cost of concrete i.e. cost of
a) cum
Material,
b)
Labour and c)
Machinery
d)
Overhead charges @ input on (a+b+c)
e)
Contractor's profit @ input on (a+b+c+d)
d&e) Overheads & Contractors Profit
Cost for 15 cum = a+b+c+d+e
Rate per metre (a+b+c+d+e)/15

5.99
6.75
8.10
5.40
0.38
2.66
1.00

0.75
0.75
0.75
2.00
37.5L
0.75
4.00%

using concrete mixer or

6.10
6.75
8.10
5.40
1.50
20.90
1.00

6.00
6.00
4.00%

545

RBR_FNDN

Index-code

S. No
1

Description

2
(ii) RCC M 30 Design Mix Using Batching Plant, Transit Mixer

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

and Concrete Pump


a) Material
t
Cement
cum
Coarse sand
cum
20 mm Aggregate
cum
10 mm Aggregate
b)
Labour
day
Mate
day
Mason
day
Mazdoor (Unskilled) for concreting
Mazdoor (Unskilled) for breaking pile head, bending bars, day
cleaning etc.
c)
Machinery
hour
Batching Plant @ 20 cum/hour
hour
Generator 100 KVA
hour
Loader (capacity 1 cum)
Transit Mixer ( capacity 4.0 cu.m )
hour
Lead upto 1 Km
tonne
Lead beyond 1 Km, L - lead in Kilometer
.km
hour
Concrete Pump
cum
Formwork @ 4 per cent on cost of concrete i.e. cost of
a)
Material,
b)
Labour and c)
Machinery
d&e) Overheads & Contractors Profit
Cost for 15 cum = a+b+c+d+e
Rate per metre (a+b+c+d+e)/15
Note : The value of a, b and c may be taken as applicable i.e. either
batching plant.
D RCC Grade M35 Design Mix
Unit = cum
Taking output = 15 cum
(i) Using Concrete Mixer
a) Material
t
Cement
cum
Coarse sand
cum
20 mm Aggregate
cum
10 mm Aggregate
b)
Labour
day
Mate
day
Mason
day
Mazdoor (Unskilled)
Mazdoor (Unskilled) for breaking pile head, bending bars, day
cleaning etc.
c)
Machinery
hour
Concrete mixer (cap. 0.40/0.28 cum)
hour
Generator (capacity 33 KVA)
Formwork @ 4 per cent on cost of concrete i.e. cost of
a) cum
Material,
b)
Labour and c)
Machinery
d&e) Overheads & Contractors Profit
Cost for 15 cum = a+b+c+d+e
Rate per metre (a+b+c+d+e)/15
(ii) RCC M 35 Design Mix Using Batching Plant, Transit Mixer
and Concrete Pump
a) Material
t
Cement
cum
Coarse sand
cum
20 mm Aggregate
cum
10 mm Aggregate
b)
Labour
day
Mate
day
Mason

6.10
6.75
8.10
5.40
0.38
2.66
1.00

0.75
0.75
0.75
2.00
37.5L
0.75
4.00%

using concrete mixer or

6.33
6.75
8.10
5.40
1.50
2.90
1.00

6.00
6.00
4.00%

6.33
6.75
8.10
5.40
0.38

546

RBR_FNDN

Index-code

S. No
1

RBR-FNDN-40

40

Description

Unit

Quantity

3
day

4
2.66

day

1.00

hour

0.75

hour

0.75

hour

0.75

Mazdoor (Unskilled) for concreting


Mazdoor (Unskilled) for breaking pile head, bending bars,
cleaning etc.
c)
Machinery
Batching Plant @ 20 cum/hour
Generator 125 KVA
Loader (capacity 1 cum)
Transit Mixer ( capacity 4.0 cu.m )
Lead upto 1 Km
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump
Formwork @ 4 per cent on cost of concrete i.e. cost of
a)
Material,
b)
Labour and c)
Machinery
d&e) Overheads & Contractors Profit
Cost for 15 cum = a+b+c+d+e
Rate per metre (a+b+c+d+e)/15
Leveling Course for Pile cap
Providing and laying of PCC M15 (Design Mix) leveling
course 100mm thick below the pile cap.
Unit = cum
Taking output = 15 cum
a) Material
Cement
Coarse sand
40 mm aggregate
20 mm Aggregate
10 mm Aggregate
b)
Labour
Mate
Mason
Mazdoor (Unskilled)
c)
Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
d&e) Overheads & Contractors Profit
Cost for 15 cum = a+b+c+d+e
Rate per metre (a+b+c+d+e)/15

hour

2.00

t.km

37.5L

hour

0.75

cum

4.00%

t
cum

4.13
6.75

cum

8.10

cum

4.05

cum

1.35

day

day

1.50

day

20.86

hour

6.00

hour

6.00

Rate
Rs.

Amount
Rs.

Remarks

General Note :
The provisions towards Mate is included in the provision towards unskilled Mazdoor.

547

RBR-SBST

Andhra Pradesh Standard Data


I. Roads and Bridges

Chapter - 12
SUBSTRUCTURE
Index-code

S. No
1
1

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

Brick masonry work in cement mortar in substructure


complete excepting pointing and plastering, as per
drawing and technical specification Clauses 602, 603,
604, 1202 & 1204 MORD and 1300 & 2200 MORTH

RBR-SBST-1

In 1:3 cement mortar


Unit = cum
(a) Material
Nos.
Bricks 1st class traditional size 23 x 11 x 7 cm
cum
Cement mortar (Rate as in item 11.5 I)
(b) Labour
day
Mate
day
Mason 1st Class
day
Mason 2nd Class
day
Mazdoor (Unskilled)
Add for scaffolding @ 5 per cent of cost of materials and
labour (a+b)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
II In 1:4 Cement mortar
Unit = cum
(a) Material
Nos.
Bricks 1st class traditional size 23 x 11 x 7 cm
cum
Cement mortar (Rate as in item 11.5 II)
(b) Labour
day
Mate
day
Mason 1st Class
day
Mason 2nd Class
day
Mazdoor (Unskilled)
Add for scaffolding @ 5 per cent of cost of materials and
labour (a+b)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
III In 1:5 cement mortar
Unit = cum
(a) Material
Nos.
Bricks 1st class traditional size 23 x 11 x 7 cm
cum
Cement mortar
(b) Labour
day
Mate
day
Mason 1st Class
day
Mason 2nd Class
day
Mazdoor (Unskilled)
Add for scaffolding @ 5 per cent of cost of materials and
labour (a+b)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
Sub-analysis
Cement mortar 1:5 (1 cement, 5 sand)
(a) Material
t
Cement
cum
Sand
(b) Labour
day
Mate
day
Mazdoor (Unskilled)
Total material and labour = (a+b)

512
0.200
0.270
0.620
1.800

512
0.200

0.270
0.620
1.800

512
0.200

0.270
0.620
1.800

0.288
1.050

0.200

549

RBR-SBST
Index-code

S. No
1

Description

2
IV In cement lime mortar (1:0.5:4.5)

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

Unit = cum
(a) Material
Nos.
Bricks 1st class traditional size 23 x 11 x 7 cm
cum
Cement lime mortar (Rate as in item 11.5 III)
(b) Labour
day
Mate
day
Mason 1st Class
day
Mazdoor (Unskilled)
Add for scaffolding @ 5 per cent of cost of materials and
labour (a+b)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
V In 1:5 cement mortar (with Modular Bricks)
Unit = cum
(a) Material
Nos.
Bricks 1st class Modular size 19 x 9 x 9 cm
cum
Cement mortar
(b) Labour
day
Mate
day
Mason 1st Class
day
Mason 2nd Class
day
Mazdoor (Unskilled)
Add for scaffolding @ 5 per cent of cost of materials and
labour (a+b)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d

512
0.200
0.620
1.800

520
0.200
0.270
0.620
1.800

Note : 1. The compressive strength of any individual Brick shall not be less than 70 Kg/cm2
2. When Mortar mix is changed as CM 1:3 & 1:4 proportionate quantity of cement has to be substituted. No
change in other data.
2

Pointing with cement mortar (1:3) on brickwork as per


drawing and technical specification Clauses 613.3 and
1204 MORD and 1300 & 2200 MORTH
Unit = 10 sqm
Taking output = 10 sqm
(a) Material
cum
Cement mortar 1.3 (Rate as in item 11.5. I)
(b) Labour
day
Mate
day
Mason 1st Class
day
Mason 2nd Class
day
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per 10 sqm = (a+b+c+d)
Note : Scaffolding is already included in item 12.1

RBR-SBST-2

RBR-SBST-3

0.030
0.500
0.740

Plastering with cement mortar (1:4), 15 mm thick on brickwork


in substructure as per technical specification Clauses 613.4 &
1204 MORD

Unit = 10 sqm
Taking output = 10 sqm
(a) Material
cum
0.190
Cement mortar 1:4 (Rate as in item 11.5 II )
(b) Labour
day
Mate
day
0.600
Mason 1st Class
day
0.960
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per 10 sqm = (a+b+c+d)
Note : 1. Scaffolding is already included in item 12.1
2. Though cement mortar of leaner mix has been included in item 12.1, for cement plaster mix of 1:4 has
been proposed for better finishing

3. If cement plaster 12 mm or 18 mm thick is required elsewhere only the quantity of cement mortar may be
changed on prorata basis without any change in the labour.

550

RBR-SBST
Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

2
Plastering with cement mortar (1:3), on brickwork in
substructure as per technical specification Section 1300 &
2200 MORTH

cum

0.144

Unit = 10 sqm
Taking output = 10 sqm
(a) Material
Cement mortar 1:3 (Rate as in item 11.5 II )
(b) Labour
Mate
Mason 1st Class
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per 10 sqm = (a+b+c+d)
Note : 1. Scaffolding is already included in item 12.1
C

day

0.500

day

0.540

cum

0.144

Plastering with cement mortar (1:5), on brickwork in


substructure as per technical specification 1300 & 2200
MORTH

Unit = 10 sqm
Taking output = 10 sqm
(a) Material
Cement mortar 1:5 (Rate as in item 11.5 II )
(b) Labour
Mate
Mason 1st Class
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per 10 sqm = (a+b+c+d)
Note : 1. Scaffolding is already included in item 12.1

RBR-SBST-4

day

day

day

0.500

day

0.540

cum
Nos.

0.940
0.160

cum

0.280

Stone masonry in cement mortar for substructure complete as


per drawing & technical specification Clauses 702, 704, 1202 &
1204 MORD and 1400 & 2200 MORTH
I Coursed rubble masonry (1st sort)
(i) In 1:3 cement mortar

Unit = cum
(a) Material
Stone for CR masonry 1st sort
Through and bond stone
(7 no x 0.24 x 0.24 m x 0.39 m = 0.16 cum)
Cement mortar (Rate as in item 11.5. I)
(b) Labour
Mate
Mason 1st Class
Mason 2nd Class
Mazdoor (Unskilled)

day
day
day
day

2.500
2.320

Add for scaffolding @ 5 per cent of cost of material (a) and labour
(b) (a+b)

c&d) Overheads & Contractors Profit


Rate per cum = a+b+c+d
(ii) In 1:4 cement mortar
Unit = cum
(a) Material
Stone for CR masonry 1st sort
Through and bond stone
(7 no x 0.24 x 0.24 m x 0.39 m = 0.16 cum)
Cement mortar (Rate as in item 11.5.II)
(b) Labour
Mate
Mason 1st Class
Mazdoor (Unskilled)

cum
Nos.

0.940
0.160

cum

0.280

day
day
day

2.500
2.320

Add for scaffolding @ 5 per cent of cost of material (a) and labour
(b) 5% on (a+b)

c&d) Overheads & Contractors Profit


Rate per cum = a+b+c+d

551

RBR-SBST
Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

cum
Nos.

0.940
0.160

cum
cum

0.280

day
day
day

2.500
2.320

cum
Nos.

0.940
0.160

cum

0.280

day
day
day

2.500
2.320

cum
Nos.

0.940
0.160

cum
cum

0.320

day
day
day
day

1.500
2.220

cum
Nos.

0.940
0.160

cum
cum

0.320

day
day
day
day

1.500
2.220

(iii) In cement mortar (1:5)

Unit = cum
(a) Material
Stone for CR masonry 1st sort
Through and bond stone
(7 no x 0.24 x 0.24 m x 0.39 m = 0.16 cum)
Spalls / blasted rubbles
Cement mortar (Rate same as in item 12.1 III)
(b) Labour
Mate
Mason 1st Class
Mazdoor (Unskilled)
As for scaffolding @ 5% on (a+b)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
(iv) In cement lime mortar (1:0.5:4.5)
Unit = cum
(a) Material
Stone for CR masonry 1st sort
Through and bond stone
(7 no x 0.24 x 0.24 m x 0.39 m = 0.16 cum)
Cement lime mortar (Rate as in item 11.5. III)
(b) Labour
Mate
Mason 1st Class
Mazdoor (Unskilled)
Add for scaffolding @ 5% of (a) and (b)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
II Coursed Rubble masonry (2nd sort)
(i) In cement mortar (1:3)
Unit = cum
(a) Material
Stone for CR masonry 2nd sort
Through and bond stone
(7 no x 0.24 x 0.24 m x 0.39 m = 0.16 cum)
Spalls/blasted rubbles
Cement mortar (Rate as in item 11.5 I)
(b) Labour
Mate
Mason 1st Class
Mason 2nd Class
Mazdoor (Unskilled)
Add for scaffolding @ 5 per cent of cost of material (a) and labour
(b)

c&d) Overheads & Contractors Profit


Rate per cum = a+b+c+d
(ii) In 1:4 cement mortar
Unit = cum
(a) Material
Stone for CR masonry 2nd sort
Through and bond stone
(7 no x 0.24 x 0.24 m x 0.39 m = 0.16 cum)
Spalls/blasted rubbles
Cement mortar (Rate same as in item 11.5 II)
(b) Labour
Mate
Mason 1st Class
Mason 2nd Class
Mazdoor (Unskilled)
Add for scaffolding @ 5 per cent of cost of material (a) and labour
(b)

c&d) Overheads & Contractors Profit


Rate per cum = a+b+c+d

552

RBR-SBST
Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

cum
Nos.

0.940
0.160

cum
cum

0.320

day
day
day
day

1.500
2.220

cum
Nos.

0.940
0.160

cum
cum

0.320

day
day
day

1.500
2.220

cum
cum
Nos.

0.440
0.500
0.160

cum

0.330

day
day
day
day

1.200
2.000

cum
cum
Nos.

0.440
0.500
0.160

cum

0.330

day
day
day
day

1.200
2.000

(iii) In cement mortar (1:5)

Unit = cum
(a) Material
Stone for CR masonry 2nd sort
Through and bond stone
(7 no x 0.24 x 0.24 m x 0.39 m = 0.16 cum)
Spalls/blasted rubbles
Cement mortar (Rate same as in item 12.1 III)
(b) Labour
Mate
Mason 1st Class
Mason 2nd Class
Mazdoor (Unskilled)
Add for scaffolding @ 5 per cent on (a+b)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
(iv) In cement lime mortar (1:0.5:4.5)
Unit = cum
(a) Material
Stone for CR masonry 2nd sort
Through and bond stone
(7 no x 0.24 x 0.24 m x 0.39 m = 0.16 cum)
Spalls/blasted rubbles
Cement lime mortar (Rate as in item 11.5 III)
(b) Labour
Mate
Mason 1st Class
Mazdoor (Unskilled)
Add for scaffolding @ 5 per cent on (a+b)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
III Random rubble masonry
(i) In cement mortar (1:3)
Unit = cum
(a) Material
Coursed Rubble Stone
Stone for RR masonry
Through and bond stone
(7 no x 0.24 x 0.24 m x 0.39 m = 0.16 cum)
Cement mortar (Rate as in item 11.5 I)
(b) Labour
Mate
Mason 1st Class
Mason 2nd Class
Mazdoor (Unskilled)
Add for scaffolding @ 5 per cent of cost of material (a) and labour
(b)

c&d) Overheads & Contractors Profit


Rate per cum = a+b+c+d
(ii) In 1:4 cement mortar
Unit = cum
(a) Material
Coursed Rubble Stone
Stone for RR masonry
Through and bond stone
(7 no x 0.24 x 0.24 m x 0.39 m = 0.16 cum)
Cement mortar (Rate same as in item 11.5 II)
(b) Labour
Mate
Mason 1st Class
Mason 2nd Class
Mazdoor (Unskilled)
Add for scaffolding @ 5 per cent of cost of material (a) and labour
(b) 5% on (a+b)

c&d) Overheads & Contractors Profit


Rate per cum = a+b+c+d

553

RBR-SBST
Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

cum
cum
Nos.

0.440
0.500
0.160

cum

0.330

day
day
day
day

1.200
2.000

cum

1.110

each

7.000

cum

0.280

(iii) In cement mortar (1:5)

Unit = cum
(a) Material
Coursed Rubble Stone
Stone for RR masonry
Through and bond stone
(7 no x 0.24 x 0.24 m x 0.39 m = 0.16 cum)
Cement mortar (Rate same as in item 12.1 III)
(b) Labour
Mate
Mason 1st Class
Mason 2nd Class
Mazdoor (Unskilled)
Add for scaffolding @ 5 per cent on (a+b)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
IV Ashlar masonry ( first sort ) Tech. Specification 1405.5
MORTH
Plain ashlar
Unit = cum
Taking output = 1 cum
a) Material
Stone
Through and bond stone
(7no.x0.24mx0.24mx0.39m = 0.16 cu.m)
Cement mortar 1:3 (Rate as in Item 11.5 I)
b) Labour for masonry work
Mate
Mason
Mazdoor (Unskilled)
Add for scaffolding @ 5 per cent of cost of a)
Labour

day

day

2.500

day

2.700

Material and b)

c&d) Overheads & Contractors Profit


Rate per cum (a+b+c+d)
Note : The labour already considered in the cement mortar have been taken into account while providing
these categories in the stone masonry works.
Plain/reinforced cement concrete in substructure complete as
per drawings and technical specification Clauses 802, 804, 805,
806, 807, 1202 and 1204 MORD and 1500, 1700 & 2200 MORTH
Note : Water for concrete : A provision for cost of water may be
added at 1.2 kl / 1 cum (including curing purpose) keeping the site
conditions
Coarse Aggregate : Single grade nominal size can also be used
instead of graded metal, keeping the site conditions in view

RBR-SBST-5

I
i

For height upto 5 m


Unit = cum
P.C.C grade M 15
Nominal mix (1:2.5:5) using CC Mixer (MORD)
Unit = cum
(a) Material
Cement
Coarse sand
40 mm aggregate
20 mm aggregate
10 mm aggregate
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
(c) Machinery
Concrete mixer 0.4/0.28 cum capacity

0.275

cum

0.480

cum

0.480

cum

0.240

cum

0.080

day
day
day

0.100
1.390

hour

(d) Formwork @ 10% on cost of material, labour and machinery


(a+b+c)

e&f) Overheads & Contractors Profit


Rate per cum = a+b+c+d+e+f
(ii) Nominal mix 1:2.5:5 (Hand mixing) (MORD)
Unit = cum
(a) Material
Cement
Coarse sand
40 mm aggregate
20 mm aggregate
10 mm aggregate
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
(c) Formwork @ 10% on (a+b)
d&e) Overheads & Contractors Profit
Rate per cum = a+b+c+d+e
II P.C.C. grade M 20 - Height upto 5m
(i) Nominal mix (1:2:4) using CC Mixer (MORD)
Unit = cum

0.400
10.00%

t
cum

0.275
0.480

cum
cum

0.540
0.270

cum

0.090

day

day

0.100

day

2.360
10.00%

554

RBR-SBST
Index-code

S. No
1

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

t
cum
cum
cum
cum

0.330
0.450
0.360
0.360
0.180

day
day
day
day

0.100
1.390

hour
hour

0.400
0.400

(a) Material
Cement
Coarse sand
40 mm aggregate
20 mm aggregate
10 mm aggregate
(b) Labour
Mate
Mason (1st Class)
Mason 2nd Class
Mazdoor (Unskilled)
(c) Machinery
Concrete mixer 0.4/0.28 cum capacity
Generator 63 KVA
Vibrator
(d) Formwork @ 10% on cost of material, labour and machinery
(a+b+c)

10.00%

e&f) Overheads & Contractors Profit


Rate per cum = a+b+c+d+e+f
(a) Height 5m to 10m
Case I : Using concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) cum
of above Item (excluding Form Work)

1.000

d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork
Add
on cost of material, Labour and machinery excluding formwork
to cater for extra lift

e&f) Overheads & Contractors Profit


Rate perm (a+b+c+d+e+f)
(ii) Nominal mix 1:2:4 (Hand mixed) (MORD)
(a) Height upto 5m
Unit = cum
(a) Material
Cement
Sand
40 mm aggregate
20 mm aggregate
10 mm aggregate
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
(c) Formwork @ 10% out of material and labour (a+b)

10.00%
2.00%

t
cum
cum
cum
cum

0.330
0.450
0.360
0.360
0.180

day
day
day

0.100
2.360
10.00%

d&e) Overheads & Contractors Profit


Rate per cum = a+b+c+d+e

555

RBR-SBST
Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

(b) Height 5m to 10m


Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) cum
of item (a) above (excluding Form Work)

1.000

d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork
Add on cost of material, Labour and machinery excluding formwork
to cater for extra lift

10.00%
2.00%

e&f) Overheads & Contractors Profit


Rate perm (a+b+c+d+e+f)
III PCC Grade M15 (Design Mix) (MORTH):
(C)
(i) For height upto 5 m

Case I : Using Concrete mixer :


Rate per Cum
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) cum
of Chapter 11. 4(B)(i) of Chapter 11, excluding formwork.

d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)
III PCC Grade M20 (Design Mix) (MORTH) :
(C)
(ii) For height upto 5 m
Case I : Using Concrete mixer :
Rate per Cum
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) cum
of Chapter 11.4(B)(ii) of Chapter 11, excluding formwork.

d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)
III PCC Grade M25 (Design Mix) (MORTH):
(C) (i) For height upto 5 m
(iii)
i Case I : Using Concrete mixer :
Rate per Cum
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) cum
of Chapter 11.4 (D) Case I excluding formwork.

1.000

10.00%

1.000

10.00%

1.000

d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork

10.00%

e&f) Overheads & Contractors Profit


Rate perm (a+b+c+d+e+f)

Case II : With Batching Plant, Transit Mixer and Concrete Pump


Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) cum
of Chapter 11.4 (D) Case II excluding formwork.

1.000

d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork

10.00%

e&f) Overheads & Contractors Profit


Rate perm (a+b+c+d+e+f)
(ii) Height 5m to 10m
Case I : Using concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) cum
of Chapter 11.4 (D) Case I excluding formwork.

1.000

d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork
Add
on cost of material, Labour and machinery excluding formwork
to cater for extra lift

12.00%
2.00%

e&f) Overheads & Contractors Profit


Rate perm (a+b+c+d+e+f)

556

RBR-SBST
Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

Case II : With Batching Plant, Transit Mixer and


Concrete Pump
Per Cum Basic Cost of Labour, Material & Machinery cum
(a+b+c) of Chapter 11. 4 (D) Case II excluding
formwork.
d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork
Add on cost of material, Labour and machinery excluding
formwork to cater for extra lift
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)
(iii) Height above 10m
Case I : Using concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery cum
(a+b+c) of Chapter 11. 4(D) Case I excluding
formwork.
d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork
Add on cost of material, Labour and machinery excluding
formwork to cater for extra lift
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)
Case II : With Batching Plant, Transit Mixer and
Concrete Pump
Per Cum Basic Cost of Labour, Material & Machinery cum
(a+b+c) of Item 4 (D) Case II excluding formwork.
d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork
Add on cost of material, Labour and machinery excluding
formwork to cater for extra lift
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)
IV D PCC Grade M30 (Design Mix) (MORTH):

1.000

12.00%
2.00%

1.000

15.00%
4.00%

1.000

15.00%
4.00%

(i) Height upto 5m

Case I : Using concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery cum
(a+b+c) of Chapter 11.4 (F) Case I excluding formwork.
d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)
Case II : With Batching Plant, Transit Mixer and
Concrete Pump
Per Cum Basic Cost of Labour, Material & Machinery cum
(a+b+c) of Chapter 11.4 (F) Case II excluding formwork.
d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)

1.00

10.00%

1.00

10.00%

557

RBR-SBST
Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

(ii) Height 5m to 10m

Case I : Using concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) cum
of Chapter 11.4 (F) Case I excluding formwork.

d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork
Add on cost of material, Labour and machinery excluding
formwork to cater for extra lift
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)

1.00

12.00%
2.00%

Case II : With Batching Plant, Transit Mixer and Concrete Pump


Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) cum
of Chapter 11.4 (F) Case II excluding formwork.

d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork
Add on cost of material, Labour and machinery excluding
formwork to cater for extra lift
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)
(iii) Height above 10m
Case I : Using concrete Mixer

1.00

12.00%
2.00%

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) cum
of Chapter 11.4 (F) Case I excluding formwork.

1.00

d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork
Add
on cost of material, Labour and machinery excluding formwork
to cater for extra lift

15.00%
4.00%

e&f) Overheads & Contractors Profit


Rate perm (a+b+c+d+e+f)
Case II : With Batching Plant, Transit Mixer and Concrete Pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) cum
of Chapter 11. 4 (F) Case II excluding formwork.

1.00

d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork
Add on cost of material, Labour and machinery excluding formwork
to cater for extra lift

e&f) Overheads & Contractors Profit


Rate perm (a+b+c+d+e+f)
V R.C.C grade M 20 (Nominal Mix) (MORD):
(A) Unit = cum
(i) Height upto 5m
Case I : Using concrete Mixer
(a) Material
Cement
Coarse sand
20 mm aggregate
10 mm aggregate
(b) Labour
Mate
Mason (1st Class)
Mason 2nd Class
Mazdoor (Unskilled)
(c) Machinery
Concrete mixer 0.4/0.28 cum capacity
Generator 33 KVA
(d) Formwork @ 10% on (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = a+b+c+d+e+f

15.00%
4.00%

t
cum

0.330
0.450

cum
cum

0.540
0.360

day
day
day
day

0.100
1.390

hour
hour

0.400
0.400
10.00%

558

RBR-SBST
Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

(ii) Height 5m to 10m

Case I : Using concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) cum
of Item V(A)(i) above excluding formwork.

1.00

d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork
Add on cost of material, Labour and machinery excluding formwork
to cater for extra lift

12.00%
2.00%

e&f) Overheads & Contractors Profit


Rate perm (a+b+c+d+e+f)
(iii) Height above 10m
Case I : Using concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) cum
of Item V(A)(i) above excluding formwork.

1.00

d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork
Add
on cost of material, Labour and machinery excluding formwork
to cater for extra lift

15.00%
4.00%

e&f) Overheads & Contractors Profit


Rate perm (a+b+c+d+e+f)
V R.C.C grade M 20 (Design Mix) (MORTH):
(B) Unit = cum
(i) Height upto 5m
Case I : Using concrete Mixer
(a) Material
Cement
Coarse sand
20 mm aggregate
10 mm aggregate
(b) Labour
Mate
Mason (1st Class)
Mason 2nd Class
Mazdoor (Unskilled)
(c) Machinery
Concrete mixer 0.4/0.28 cum capacity
Generator 33 KVA
(d) Formwork @ 10% on (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = a+b+c+d+e+f

t
cum

0.347
0.45

cum
cum

0.54
0.36

day
day
day
day

0.06
0.10

hour
hour

0.40
0.40

1.33

10.00%

Case II : With Batching Plant, Transit Mixer and Concrete Pump


Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) cum
of Chapter 11.4 (c)(ii) Case II excluding formwork.

1.00

d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork

10.00%

e&f) Overheads & Contractors Profit


Rate perm (a+b+c+d+e+f)
(ii) Height 5m to 10m
Case I : Using concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) cum
of Item V(B)(i) Case I excluding formwork.

1.00

d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork
Add
on cost of material, Labour and machinery excluding formwork
to cater for extra lift

12.00%
2.00%

e&f) Overheads & Contractors Profit


Rate perm (a+b+c+d+e+f)

559

RBR-SBST
Index-code

S. No
1

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

Case II : With Batching Plant, Transit Mixer and


Concrete Pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) cum
of Chapter 11.4 (C) (ii) Case II excluding formwork.

1.00

d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork
Add
on cost of material, Labour and machinery excluding formwork
to cater for extra lift

12.00%
2.00%

e&f) Overheads & Contractors Profit


Rate perm (a+b+c+d+e+f)
(iii) Height above 10m
Case I : Using concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) cum
of Item V (B) (i) Case I excluding formwork.

1.00

d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork
Add
on cost of material, Labour and machinery excluding formwork
to cater for extra lift

15.00%
4.00%

e&f) Overheads & Contractors Profit


Rate perm (a+b+c+d+e+f)
Case II : With Batching Plant, Transit Mixer and Concrete Pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) cum
of Chapter 11.4 (C) (ii) Case II excluding formwork.

1.00

d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork
Add on cost of material, Labour and machinery excluding formwork
to cater for extra lift

e&f) Overheads & Contractors Profit


Rate perm (a+b+c+d+e+f)
VI R.C.C. grade M 25 (Design Mix)
Unit = cum
(i) Height upto 5m
Case I : Using concrete Mixer
(a) Material
Cement
Coarse sand
20 mm aggregate
10 mm aggregate
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
(c) Machinery
Concrete mixer 0.4/0.28 cum capacity
Generator 33 KVA
Vibrator
(d) Formwork @ 10% on (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = a+b+c+d+e+f
Case II : With Batching Plant, Transit Mixer and
Concrete Pump

15.00%
4.00%

t
cum
cum
cum

0.403
0.450
0.540
0.360

day
day
day

0.10
1.39

hour
hour
hour

0.40
0.40

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) cum
of Chapter 11.4 (E) Case II excluding of Formwork

d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)

10.00%

10.00%

560

RBR-SBST
Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

(ii) Height 5m to 10m

Case I : Using concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery cum
(a+b+c) of Item VI (i) Case I excluding of Formwork
d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork
Add on cost of material, Labour and machinery excluding
formwork to cater for extra lift
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)
Case II : With Batching Plant, Transit Mixer and
Concrete Pump
Per Cum Basic Cost of Labour, Material & Machinery cum
(a+b+c) of Chapter 11.4 (E) Case II excluding of
Formwork
d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork
Add on cost of material, Labour and machinery excluding
formwork to cater for extra lift
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)

11.80%
1.80%

11.80%
1.80%

(iii) Height above 10m

Case I : Using concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery cum
(a+b+c) of Item VI (i) Case I excluding of Formwork

d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork
Add on cost of material, Labour and machinery excluding
formwork to cater for extra lift
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)

15.00%
4.00%

Note in MORD : 1. The cost of form work has been increased,


for more height, to account for cost of side support to form work.
2. Extra expenditure on structures which are more than 5m height
is to cater for cost involve for approaching the work spot by
providing ramp for use by labour.
Case II : With Batching Plant, Transit Mixer and
Concrete Pump
Per Cum Basic Cost of Labour, Material & Machinery cum
(a+b+c) of Chapter 11.4 (E) Case II excluding of
Formwork
d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork
Add on cost of material, Labour and machinery excluding
formwork to cater for extra lift
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)

15.00%
4.00%

561

RBR-SBST
Index-code

S. No
1

Description

2
VII RCC Grade M30 (Design Mix)
(i) Height upto 5m

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

Case I : Using concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery cum
(a+b+c) of Chapter 11.4(G) Case I excluding of
d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)

10.00%

Case II : With Batching Plant, Transit Mixer and Concrete Pump


Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) cum
of Chapter 11.4(G) Case II excluding of Formwork

d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork

10.00%

e&f) Overheads & Contractors Profit


Rate perm (a+b+c+d+e+f)
(ii) Height 5m to 10m
Case I : Using concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) cum
of Chapter 11.4(G) Case I excluding of Formwork

d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork
Add on cost of material, Labour and machinery excluding formwork
to cater for extra lift

11.50%
1.60%

e&f) Overheads & Contractors Profit


Rate perm (a+b+c+d+e+f)
Case II : With Batching Plant, Transit Mixer and Concrete Pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) cum
of Chapter 11.4(G) Case II

d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork
Add on cost of material, Labour and machinery excluding formwork
to cater for extra lift

11.50%
1.60%

e&f) Overheads & Contractors Profit


Rate perm (a+b+c+d+e+f)
(iii) Height above 10m
Case I : Using concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) cum
of Chapter 11.4 (G) Case I excluding of Formwork

d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork
Add
on cost of material, Labour and machinery excluding formwork
to cater for extra lift

14.00%
3.50%

e&f) Overheads & Contractors Profit


Rate perm (a+b+c+d+e+f)
Case II : With Batching Plant, Transit Mixer and
Concrete Pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) cum
of Chapter 11.4(G) Case II excluding of Formwork

d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork
Add
on cost of material, Labour and machinery excluding formwork
to cater for extra lift

14.00%
3.50%

e&f) Overheads & Contractors Profit


Rate perm (a+b+c+d+e+f)

562

RBR-SBST
Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

VIII RCC Grade M35


(i) Height upto 5m

Case I : Using concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery cum
(a+b+c) of Chapter 11.4(H) Case I excluding of
Formwork
d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)
Case II : With Batching Plant, Transit Mixer and
Concrete Pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) cum
of Chapter 11.4(H) Case II excluding of Formwork

10.00%

1.000

d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork

e&f) Overheads & Contractors Profit


Rate perm (a+b+c+d+e+f)
(ii) Height 5m to 10m
Case I : Using concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery cum
(a+b+c) of Chapter 11.4(H) Case I excluding of
Formwork
d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork
Add on cost of material, Labour and machinery excluding formwork
to cater for extra lift

10.00%

11.00%
1.40%

e&f) Overheads & Contractors Profit


Rate perm (a+b+c+d+e+f)
Case II : With Batching Plant, Transit Mixer and Concrete Pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) cum
of Chapter 11.4(H) Case II excluding of Formwork

1.000

d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork
Add on cost of material, Labour and machinery excluding formwork
to cater for extra lift

e&f) Overheads & Contractors Profit


Rate perm (a+b+c+d+e+f)
(iii) Height above 10m
Case I : Using concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery cum
(a+b+c) of Chapter 11.4(H) Case I excluding of
d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork
Add on cost of material, Labour and machinery excluding formwork
to cater for extra lift

11.00%
1.40%

13.00%
3.00%

e&f) Overheads & Contractors Profit


Rate perm (a+b+c+d+e+f)
Case II : With Batching Plant, Transit Mixer and
Concrete Pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) cum
of Chapter 11.4(H) Case II excluding of Formwork

1.000

d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork
Add on cost of material, Labour and machinery excluding formwork
to cater for extra lift

13.00%
3.00%

e&f) Overheads & Contractors Profit


Rate perm (a+b+c+d+e+f)

563

RBR-SBST
Index-code

S. No
1

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

2
3
4
5
6
Note in MORTH : The basic components of this analysis are the same as those of items 13.8 (A to H). The
only changes are as under:
a) Ramps/Stairs: Extra expenditure on structures which are more than 5 m high @ 2 per cent of cost for
height upto 10 m and 4 per cent for heights above 10 m will be involved for approaching the work spot by
providing higher ramp/stair case for use by the working parties.

Remarks
7

The above mentioned percentages have been suitably modified for different categories as cost for
b)
various categories varies, whereas effort for access for same height will be similar. As the cost of richer
concrete is comparatively more, the percentage to be added has been reduced to maintain the same cost
for extra efforts.
6

Supplying, fitting and placing HYSD bar reinforcement


(Fe 415) in substructure complete as per drawings and
technical specification Clauses 1002, 1005, 1010 &
1202 MORD / Sections 1600 & 2200 MORTH for Bars
below 36 mm dia including over laps and wastage,
where they are not welded.
Unit = t
(a) Material

RBR-SBST-6

HYSD bars including 5 per cent overlaps and wastage

kg
Binding wire
(b) Labour for cutting, bending, shifting to site, tying,
and placing in position
day
Mate
day
Blacksmith
day
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per t = a+b+c+d
A

RBR-SBST-7

6.000

2.000
6.840

Supplying, fitting and placing HYSD bar reinforcement (Fe 415)


in substructure complete including wastage, as per drawings
and technical specification Clauses 1002, 1005, 1010 & 1202
MORD / Sections 1600 & 2200 MORTH for Bars 36 mm dia and
above, where welding required to be done compulsorily.

Unit = t
(a) Material
HYSD bars including 2.5 per cent for wastage
Welding Electrodes @ 5 per joint (14 joints / ton)
Welding Charges (Hire charges of Welding Machine)
Binding wire
(b) Labour for cutting, bending, shifting to site, tying,
and placing in position
Welder
Blacksmith/Bar Bender
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per t = a+b+c+d
7

1.050

t
each

1.025
70.000

Hr

10.00

kg

6.00

day

2.50

day
day

2.000
6.840

Supplying, fitting and placing TMT bar reinforcement (Fe 415)


in substructure complete as per drawings and technical
specification Clauses 1002, 1005, 1010 & 1202 MORD /
Sections 1600 & 2200 MORTH for Bars below 36 mm dia
including over laps and wastage, where they are not welded.

Unit = t
(a) Material
t
TMT bars including 5 per cent overlaps and wastage
kg
Binding wire
(b) Labour for cutting, bending, shifting to site, tying,
and placing in position
day
Mate
day
Blacksmith/Bar Bender
day
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per t = a+b+c+d

1.050
6.000

2.000
6.840

564

RBR-SBST
Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

2
Supplying, fitting and placing TMT bar reinforcement (Fe 415)
in substructure complete including wastage, as per drawings
and technical specification Clauses 1002, 1005, 1010 & 1202
MORD / Sections 1600 & 2200 MORTH for Bars 36 mm dia and
above, where welding required to be done compulsorily.

Unit = t
(a) Material
TMT bars including 2.5 per cent for wastage
Welding Electrodes @ 5 per joint (14 joints / ton)
Welding Charges (Hire charges of Welding Machine)
Binding wire
(b) Labour for cutting, bending, shifting to site, tying,
and placing in position
Welder
Blacksmith/Bar Bender
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per t = a+b+c+d
8

RBR-SBST-8

1.025

each

70.000

Hr

10.00

kg

6.00

day

2.50

day
day

2.000
6.840

Supplying, fitting and placing with MS bar reinforcement in


substructure complete as per drawings and technical
specification Clauses 1002, 1005, 1010 & 1202 MORD /
Sections 1600 & 2200 MORTH for Bars below 36 mm dia
including over laps and wastage, where they are not welded.

Unit = t
(a) Material
t
MS bars including 5 per cent overlaps and wastage
kg
Binding wire
(b) Labour for cutting, bending, shifting to site, tying,
and placing in position
day
Mate
day
Blacksmith
day
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per t = a+b+c+d
9

RBR-SBST-9

1.050
6.000

1.500
5.780

Providing weep holes in brick masonry/stone masonry,


plain/reinforced concrete abutment, wing wall, return wall with
100 mm dia AC pipe extending through the full width of the
structures with slope of 1(V):20(H) towards drawing face
complete as per drawing and technical specification Clauses
614, 709, 1204.3.7 MORD / 2706 & 2200 MORTH.

Unit = Nos
Taking output = 30 Nos
(a) Material
AC pipe 100 mm dia including wastage @ 5 per cent. Average
m
length of weep hole is taken as one metre for the purpose of
estimating
Nos.
MS clamps

31.500

Collar for AC pipe (average taking 10% of above pipe rate)

10.00%

Cement mortar 1:3 (For rate refer to item 11.5 I)


(b) Labour
Mate
Mason 1st Class
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Cost for 30 Nos = (a+b+c+d)
Rate per No = (a+b+c+d)/30

30.000

cum

0.050

day
day
day

0.500
0.280

Note in MORTH : 1. In case of stone masonry, the size of the weep hole shall be 150 mm x 80 mm or
circular with 150 mm diameter.
2. For structure in stone masonry, the weep holes shall be deemed to be included in the item of stone
masonry work and shall not be paid separately.

565

RBR-SBST
Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

cum

12.000

day
day

7.280

hour
hour

2.500
0.050

cum

12.000

day
day

7.280

hour
hour

2.500
0.060

10

RBR-SBST-10

11

RBR-SBST-11

Backfilling behind abutment, wing wall and return wall


complete as per drawings & technical specification
Clause 1204.3.8 MORD / 710.14 of IRC, 78 & 2200
MORTH
Unit = cum
Taking output = 10 cum
I Granular material
(a) Material
Granular material
(b) Labour
Mate
Mazdoor (Unskilled)
(c) Machinery
Plate compactor / power rammer
Water Tanker
d&e) Overheads & Contractors Profit
Cost for 10 cum of granular backfill = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/10
II Sandy material
Unit = cum
Taking output = 10 cum
(a) Material
Sand
(b) Labour
Mate
Mazdoor (Unskilled)
(c) Machinery
Plate compactor/power rammer
Water Tanker
d&e) Overheads & Contractors Profit
Cost for 10 cum of granular backfill = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/10
Providing and laying filter media with granular crushed
aggregates as per specification to a thickness of not less than
600 mm with smaller size towards the soil and bigger size
towards the wall and providing over the entire surface behind
abutment, wing wall, return wall to the full height, compacted
to firm condition complete as per drawing and technical
specification Clause 1204.3.8 MORD / 710.14 of IRC, 78 & 2200
MORTH

Unit = cum
Taking output = 10 cum
(a) Material
cum
Filter media as per specification
(b) Labour
day
Mate
day
Mazdoor (Unskilled)
day
Mazdoor (Skilled)
c)
Machinery
hour
Water Tanker of 6 KL capacity
d&e) Overheads & Contractors Profit
Cost for 10 cum of granular backfill = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/10
Note : Suitable Grade of Filter media shall be proposed as per
Specification in said IRC.

12.000
7.320
1.000
0.060

566

RBR-SBST
Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

2
Supplying, fitting and fixing in position true to line and level
electrometric bearing conforming to IRC:83 (Part-II) Section IX
complete, including all accessories as per drawings and
technical specification Clause 1207.1 MORD

day
day
day

1.060
0.500

12

RBR-SBST-12

Unit = cubic centimeter


Considering an electrometric bearing of size 500 x 400 x 96 mm for
this analysis,

Overall volume = 19200 cu.cm


Volume of 6 Nos 488x388x4 mm size reinforcing steel
plates = 4545cu.cm.
Hence volume of elastomer = 14655 cu. cm.
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor Skilled
b) Material

Electrometric bearing assembly consisting of 7 internal layers of Nos.


elastomer bonded to 6 nos. internal reinforcing steel laminates by
the process of vulcanisation, complete with all components as per
drawing and technical specification
Add for anchorage bolts if required and consumables @ 1 per cent
on (a+b)

1.000

1.00%

c&d) Overheads & Contractors Profit


Cost for 19200 cu.cm. of elastomeric bearing = a+b+c+d
Rate

per

cu.cm

of

elastomeric

bearing

(a+b+c+d)/19200
Note
: For such type of manufactured item, the overhead cost is taken as
30 per cent instead of 20 per cent
i

Supplying, fitting and fixing in position true to line and


level cast steel rocker bearing conforming to IRC:
83(Pt.-1) section IX and clause 2003 of MoRTH
specifications complete including all accessories as
per drawing and Technical Specifications 2000, 1000 &
2200 MORTH.
Unit: one tonne capacity
Considering a 250 tonne capacity bearing for this analysis

a) Labour
Mate

day

Mazdoor (Skilled)

day

0.500

Mazdoor (Unskilled)

day

1.060

b)

Material

Cast steel rocker bearing assembly of 250 tonne design each.


load capacity duly painted complete with all its components
as per drawing and specifications
Add 1 per cent of cost of bearing assembly for foundation
anchorage bolts, lifting arrangements, grease and other
consumables.
c&d) Overheads & Contractors Profit
cost for 250 tonnes capacity bearing = a+b+c+d
Rate per tonne capacity = (a+b+c+d)/250
ii Supplying, fitting and fixing in position true to line and
level forged steel roller bearing conforming to IRC:
83(Pt.-1) section IX and clause 2003 of MoRTH
specifications complete including all accessories as
per drawing and Technical Specifications 2000, 1000 &
2200 MORTH.
Unit: one tonne capacity

1.000

Considering a 250 tonne capacity bearing for this analysis

a)

Labour

Mate

day

Mazdoor (Unskilled)

day

1.060

Mazdoor (Skilled)

day

0.500

567

RBR-SBST
Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

b)

Material

Forged steel roller bearing of 250 tonne design load each.


capacity duly painted complete with all its components as
per drawing and specifications

1.000

Add 1 per cent of cost of bearing assembly for foundation


anchorage bolts, lifting arrangements, grease and other
consumables.
c&d) Overheads & Contractors Profit
cost for 250 tonnes capacity bearing = a+b+c+d
Rate per tonne capacity = (a+b+c+d)/250
iii Supplying, fitting and fixing in position true to line and
level sliding plate bearing with PTFE surface sliding on
stainless steel complete including all accessories as
per drawing and Technical Specifications and BS:
5400, section 9.1 & 9.2 (for PTFE) and clause 2004 of
MoRTH Specifications & Sections 2000 & 2200 MORTH
Unit: one tonne capacity
Considering a 80 tonne capacity bearing for this analysis

a)

Labour

Mate

day

Mazdoor (Unskilled)

day

1.060

Mazdoor (Skilled)

day

0.500

b)

Material

PTFE sliding plate bearing assembly of 80 tonnes design load each.


capacity duly painted complete with all its components as per
drawing and Technical Specifications
Add 1% for foundation anchorage bolts and consumables.

1.000

c&d) Overheads & Contractors Profit


cost for 80 tonnes capacity bearing = a+b+c+d
Rate per tonne capacity = (a+b+c+d)/80
iv Supplying, fitting and fixing in position true to line and

level elastomeric bearing conforming to IRC: 83 (PartII) section IX and clause 2005 of MoRTH specifications
complete including all accessories as per drawing and
Technical Specifications 2000 & 2200 MORTH.
Unit: one cubic centimeter
Considering an elastomeric bearing of size 500 x 400 x 96
mm for this analysis.
Overall volume - 19200 cu.cm
Volume of 6 nos. 488 x 388 x 4 mm size reinforcing steel
plates = 4545 cu.cm.
Hence volume of elastometer = 14655 cu.cm.
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Skilled)
b)
Material

day
day
day

Elastomeric bearing assembly consisting of 7 layers of elastomer each.


bonded to 6 nos. internal reinforcing steel laminates by the process
of vulcanisation, complete with all components as per drawing and
Technical Specifications.

1.06
0.50
1.00

Add 1 per cent of cost of bearing assembly for foundation


anchorage bolts and consumables.
c&d) Overheads & Contractors Profit
cost for 19200cc of elastomeric bearing = a+b+c+d
Rate per cc of elastomeric bearing = (a+b+c+d)/19200

568

RBR-SBST
Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

2
Supplying, fitting and fixing in position true to line and level
sliding plate bearing with stainless steel plate sliding on
stainless steel plate with mild steel matrix complete including
all accessories as per drawing and Technical Specifications
2000, & 2200 MORTH.

day
day
day

0.790
0.350

Unit: one tonne capacity


Considering the sliding bearing of 80 tonnes design capacity for this
analysis.

a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Skilled)
b)
Material

Supply of sliding plate bearing of 80 tonne design capacity each.


complete as per drawings and Technical Specifications.
Add 1 per cent of cost of bearing assembly for foundation
anchorage bolts and consumables.

1.000

c&d) Overheads & Contractors Profit


cost for 80 tonnes of capacity bearing = a+b+c+d
Rate per tonne capacity = (a+b+c+d)/80
vi Supplying, fitting and fixing in position true to line and level
POT-PTFE bearing consisting of a metal piston supported by a
disc or unreinforced elastomer confined within a metal
cylinder, sealing rings, dust seals, PTFE surface sliding
against stainless steel mating surface, complete assembly to
be of cast steel/fabricated structural steel, metal and elastomer
elements to be as per IRC: 83 part-I & II respectively and other
parts conforming to BS: 5400, section 9.1 & 9.2 and clause
2006 of MoRTH Specifications complete as per drawing and
approved Technical Specifications 2000, & 2200 MORTH.

Unit: one tonne capacity


Considering a Pot bearing assembly of 250 tonne capacity for this
analysis.

a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Skilled)
b)
Material

day
day
day

Pot type bearing assembly consisting of a metal piston supported each.


by a disc, PTFE pads providing sliding surfaces against stainless
steel mating together with cast steel assemblies/fabricated
structural steel assemblies duly painted with all components as per
clause 2006 and complete as per drawings and Technical
Specifications.

1.580
0.500
1.000

Add 1 per cent of cost of bearing assembly for foundation


anchorage bolts and consumables.

c&d) Overheads & Contractors Profit


cost for 250 tonnes capacity bearing = a+b+c+d
Rate per tonne capacity = (a+b+c+d)/250
13

RBR-SBST-13

Providing PCC M-20 architectural coping on the top of wing


wall, return wall etc. complete as per drawing and technical
specification Clauses 615, 710 and 1204.3.11 MORD

Unit = Running m
Taking output = 1 m
Assume wall thickness = 345 mm
Projection of the coping will be 25 mm wide on both side of
the wall = 345 + 50 = 395 mm
Quantity = 1 x 0.395 x 0.150 = 0.059
PCC M-20 Grade (1:2:4) Nominal Mix
As per item No. 12.5 (II)(i) including Overheads & Contractor's cum
Profit

0.059

Add 10% extra of cost of (a) being architectural coping


Cost of 1 m = a
Rate per m = a
14

RBR-SBST-14

Providing pressure relief pipes 100 mm dia in bottom slab of


box cell on a filter media base of 500 mm x 500 mm as per
drawing and technical specification Clause 1205.5.7 MORD

Unit = Nos
(a) Material
AC pipe 100 mm dia i/c wastage of 5 per cent 600 mm long upto
m
the bottom of leveling course
Filter media base with stone aggregate as per specifications 0.5 m cum
x 0.5 m area 1 m deep

(b) Labour
Mate
Mason 1st Class
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per No = (a+b+c+d)

0.630
0.250

day
day

0.016

day

0.831

General Note :
The provisions towards Mate is included in the provision towards unskilled Mazdoor.

569

RBR-SPST

Andhra Pradesh Standard Data


I. Roads and Bridges

Chapter - 13
SUPERSTRUCTURE
Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

t
cum

0.33
0.45

cum

0.54

cum

0.36

day
day

0.10

day

1.39

hr /
cum

0.40

RBR-SPST-1

Providing and laying reinforced cement concrete in


superstructure as per drawing and technical
specifications Clauses 800, 1205.4 and 1205.5 MORD /
Sections 1500, 1600 & 1700 MORTH
Note : 1. Water for CC works : A provision for cost of
water may be added at 1.2 kl / 1 cum (including curing
purpose) keeping the site conditions
2. Coarse aggregate : Single grade nominal size can also
be used instead of graded metal, keeping the site
conditions in view.
I (A) R.C.C grade M 20 (MORD)
(i) For nominal mix 1:2:4 (Using Concrete Mixture)
Height upto 5m
Unit = cum
(a) Material
Cement
Coarse sand
20 mm aggregate
10 mm aggregate
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
c) Machinery
Concrete mixer 0.4/0.28 cum capacity

d) Add for formwork and staging


Height upto 5 m @ 20% of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = a+b+c+d+e+f
ii Height 5m to 10m
Per Cum Basic Cost of Labour, Material & Machinery cum
(a+b+c) of Item 1(A)(i), excluding of Formwork
d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork

25.00%

e&f) Overheads & Contractors Profit


Rate perm (a+b+c+d+e+f)
iii Height above10m
Per Cum Basic Cost of Labour, Material & Machinery cum
(a+b+c) of Item 1(A)(i), excluding of Formwork
d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork

e&f) Overheads & Contractors Profit


Rate perm (a+b+c+d+e+f)
(B) For design mix RCC M 20 Using Concrete Mixer
(a) Material
Cement
Coarse sand
20 mm aggregate
10 mm aggregate

20.00%

30.00%

t
cum

0.341
0.45

cum

0.54

cum

0.36

573

RBR-SPST
Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
c) Machinery
Concrete mixer 0.4/0.28 cum capacity

I
(i)

Generator 33 KVA
Total (a+b+c)
d) For formwork and staging add the following
percentage of (a+b+c):
Height upto 5 m @ 20 per cent
e&f) Overheads & Contractors Profit
Rate per cum = a+b+c+d+e+f
Note : 1. Height from 5 m to 10 m @ 25 %(MORD)
2. Height above 10 m @ 30 per cent (MORD)
RCC M 20 Design Mix (Using Concrete Mixture)
(MORTH)
Case I : (I) For solid slab super-structure (MORTH)
For formwork and staging add the following:

day

day

0.10

day

1.39

hr /
cum
hour

0.40
0.40

20.00%

(i) Height upto 5m


Basic Cost of Labour, Material & Machinery (a+b+c) for cum

cum

1.00
20.00%

d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
(ii) Height 5m to 10m

(iii)

II
(i)

(ii)

(iii)

Basic Cost of Labour, Material & Machinery


cum Formwork and staging of (a+b+c)
d)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
Height above 10m
Basic Cost of Labour, Material & Machinery
cum Formwork and staging of (a+b+c)
d)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
For T-beam & slab
Height upto 5m
Basic Cost of Labour, Material & Machinery
cum
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
Height 5m to 10m
Basic Cost of Labour, Material & Machinery
cum Formwork and staging of (a+b+c)
d)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
Height above 10m
Basic Cost of Labour, Material & Machinery
cum Formwork and staging of (a+b+c)
d)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
Case II : Using Batching Plant, Transit
Concrete Pump (RCC M20) Design Mix
Unit = cum
Taking output = 1 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate

(a+b+c) for cum

1.00
25.00%

(a+b+c) for cum

1.00
30.00%

(a+b+c) for cum

1.00
25.00%

(a+b+c) for cum

1.00
30.00%

(a+b+c) for cum

1.00
35.00%

Mixer and

t.km

0.341

cum

0.45

cum

0.54

cum

0.36

574

RBR-SPST
Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

day
day

0.024

day

0.157

hour

0.05

hour

0.05

hour

0.05

hour

0.125

t.km

2.5 L

hour

0.05

cum

1.00

cum

1.00
20.00%

b)
Labour
Mate
Mason
Mazdoor (Unskilled)
c)
Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader
Transit Mixer ( capacity 4.0 cu.m ) :
Transit Mixer 4 cum capacity lead upto1 Km
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump

I
(i)

(ii)

(iii)

II
(i)

(ii)

(iii)

II
A

Basic Cost of Labour, Material & Machinery (a+b+c)


For formwork and staging add the following:
For solid slab super-structure
Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
Height above 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
For T-beam & slab
Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
Height above 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
R.C.C M 25 Grade (Design Mix)
Unit =cum
Case I : Using Concrete Mixer.
(a) Material
Cement
Coarse sand
20 mm aggregate
10 mm aggregate
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
c) Machinery
Concrete mixer 0.4/0.28 cum capacity

cum

1.00
25.00%

cum

1.00
30.00%

cum

cum

1.00
25.00%

1.00
30.00%

cum

1.00
35.00%

t
cum
cum
cum

0.40
0.45
0.54
0.36

day
day
day

0.10
1.39

hour/
cum

0.40

575

RBR-SPST
Index-code

S. No

Description

Unit

Quantity

3
hour

4
0.40

Generator 33 KVA

Rate
Rs.

Amount
Rs.

Remarks

d) For formwork and staging refer to sub-item I (B) case I above

(I) For solid slab super-structure


(II) For T-beam & slab
e&f) Overheads & Contractors Profit
Rate per cum = a+b+c+d+e+f
Note : This analysis will hold good for concrete of nominal mix 1:1:3 also
B Case II : Using Batching Plant, Transit Mixer and
Concrete Pump (RCC M25) Design Mix (MORTH)
Unit = cum
Taking output = 1 cum
a) Material
t
0.400
Cement
cum
0.450
Coarse sand
cum
0.540
20 mm Aggregate
cum
0.360
10 mm Aggregate
b)
Labour
day
Mate
day
0.024
Mason
day
0.157
Mazdoor (Unskilled)
c)
Machinery
hour
0.05
Batching Plant @ 20 cum/hour
hour
0.05
Generator 100 KVA
hour
0.05
Loader
Transit Mixer ( capacity 4.0 cu.m )
hour
0.125
Transit Mixer 4 cum capacity lead upto1 Km
t.km
2.5 L
Lead beyond 1 Km, L - lead in Kilometer
hour
0.05
Concrete Pump
Basic Cost of Labour, Material & Machinery (a+b+c)
(I) For solid slab super-structure

cum

1.00

cum

1.00
20.00%

(i) Height upto 5m

Basic Cost of Labour, Material & Machinery (a+b+c)


d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
(ii) Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
(iii) Height above 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)

cum

1.00
25.00%

cum

1.00
30.00%

(II) For T-beam & slab


(i) Height upto 5m

Basic Cost of Labour, Material & Machinery (a+b+c)


d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
(ii) Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
(iii) Height above 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)

cum

1.00
25.00%

cum

1.00
30.00%

cum

1.00
35.00%

576

RBR-SPST
Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

t
cum
cum
cum

0.407
0.45
0.54
0.36

day
day
day

0.10
1.39

hour
hour

0.40
0.40

cum

1.00
20.00%

III R.C.C. Grade M 30 Design Mix

Unit =cum
Case 1: Using Concrete Mixer
(a) Material
Cement
Coarse sand
20 mm aggregate
10 mm aggregate
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
c) Machinery
Concrete mixer 0.4/0.28 cum capacity
Generator 33 KVA
d) For formwork and stagings refer to sub-item (d) of I
(II) above
(I) For solid slab super-structure
(i) Height upto 5m

Basic Cost of Labour, Material & Machinery (a+b+c)


d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
(ii) Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
(iii) Height above 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
(II) For T-beam & slab

cum

1.00
25.00%

cum

1.00
30.00%

(i) Height upto 5m


cum
Basic Cost of Labour, Material & Machinery (a+b+c)
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
(ii) Height 5m to 10m
cum
Basic Cost of Labour, Material & Machinery (a+b+c)
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
(iii) Height above 10m
cum
Basic Cost of Labour, Material & Machinery (a+b+c)
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
C Case II : Using Batching Plant, Transit Mixer and
Concrete Pump (RCC M30) Design Mix (MORTH)
Unit = cum
Taking output = 120 cum
a) Material
t
Cement
cum
Coarse sand
cum
20 mm Aggregate
cum
10 mm Aggregate
b)
Labour
day
Mate
day
Mason
day
Mazdoor (Unskilled)
c)
Machinery
hour
Batching Plant @ 20 cum/hour
hour
Generator 100 KVA
hour
Loader
Transit Mixer ( capacity 4.0 cu.m )
hour
Transit Mixer 4 cum capacity lead upto1 Km
t.km
Lead beyond 1 Km, L - lead in Kilometer
hour
Concrete Pump

1.00
25.00%

1.00
30.00%

1.00
35.00%

0.407
0.46
0.54
0.36
0.024
0.157
0.05
0.05
0.05
0.125
300L
0.05

Basic Cost of Labour, Material & Machinery (a+b+c)

Rate per cum = (a+b+c)


(I) For solid slab super-structure
(i) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)

cum

1.00
20.00%

577

RBR-SPST
Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

(ii) Height 5m to 10m

(iii)

II
(i)

(ii)

(iii)

cum
1.00
Basic Cost of Labour, Material & Machinery (a+b+c)
25.00%
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
Height above 10m
cum
1.00
Basic Cost of Labour, Material & Machinery (a+b+c)
30.00%
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
For T-beam & slab
Height upto 5m
cum
1.00
Basic Cost of Labour, Material & Machinery (a+b+c)
25.00%
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
Height 5m to 10m
cum
1.00
Basic Cost of Labour, Material & Machinery (a+b+c)
30.00%
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
Height above 10m
cum
1.00
Basic Cost of Labour, Material & Machinery (a+b+c)
35.00%
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
Note : Quantity of cement provided for various components of the superstructure is for
estimating purpose only. Actual quantity of cement will be as per approved mix design.
Similarly quantity for coarse and fine aggregates is for estimating purpose and the exact
quantity shall be as per the mix design.
Use of Design mix in place of nominal mix of concrete of M20 and higher grades shall be
preferred. Nominal mix of grades M20 is to be used with adequate supervision and quality
control requirements. Technical Specification Clause 803 MORD.
RCC/PSC Grade M35 Design Mix (MORTH)
Case I : Using Concrete Mixer.
Unit = 1 cum
Taking output = 1 cum
a) Material
tonne
0.422
Cement
cum
0.45
Coarse sand
cum
0.54
20 mm Aggregate
cum
0.36
10 mm Aggregate

578

RBR-SPST
Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

b)
Labour
Mate
Mason
Mazdoor (Unskilled)
c)
Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA

day

day

0.10

day

1.39

hour

0.40

hour

0.40

Basic Cost of Labour, Material & Machinery (a+b+c)

For formwork and staging add the following :


For solid slab super-structure
(i) Height upto 5m
I

Basic Cost of Labour, Material & Machinery (a+b+c)

cum

d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
(ii) Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)

cum
23.00%

d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
(iii) Height above 10m
Basic Cost of Labour, Material & Machinery (a+b+c)

cum
28.00%

d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
II For T-beam & slab
(i) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)

cum
23.00%

d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
(ii) Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)

cum
28.00%

d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
(iii) Height above 10m
Basic Cost of Labour, Material & Machinery (a+b+c)

cum
33.00%

d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
III For box girder and balanced cantilever
(i) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)

cum
38.00%

d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
(ii) Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)

cum
48.00%

d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
(iii) Height above 10m
Basic Cost of Labour, Material & Machinery (a+b+c)

d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)

cum
58.00%

579

RBR-SPST
Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

t
cum
cum
cum

0.422
0.45
0.54
0.36

day
day
day

0.024
0.157

hour
hour
hour

0.05
0.05
0.05

hour
tkm
hour

0.125
2.5 L
0.05

Case II : Using Batching Plant, Transit Mixer and


Concrete Pump (RCC/PSC M35)

I
(i)

(ii)

(iii)

II
(i)

(ii)

(iii)

III
(i)

Unit = cum
Taking output = 1 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
b)
Labour
Mate
Mason
Mazdoor (Unskilled)
c)
Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump
Basic Cost of Labour, Material & Machinery (a+b+c)
For formwork and staging add the following :
For solid slab super-structure
Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
Height above 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
For T-beam & slab
Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
Height above 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
For box girder and balanced cantilever
Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)

cum

cum
23.00%

cum
28.00%

cum
23.00%

cum
28.00%

cum
33.00%

cum
38.00%

580

RBR-SPST
Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

(ii) Height 5m to 10m

(iii)

I
(i)

(ii)

(iii)

II

Basic Cost of Labour, Material & Machinery (a+b+c)


d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
Height above 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
PSC Grade M-40 Design Mix (MORTH)
Case I : Using concrete mixer.
Unit = 1 cum
Taking output = 1 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
Admixture @ 0.4 per cent of cement
b)
Labour
Mate
Mason
Mazdoor (Unskilled)
c)
Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
Basic Cost of Labour, Material & Machinery (a+b+c)
For formwork and staging add the following :
For solid slab super-structure
Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
Height above 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
For T-beam & slab

cum
48.00%

cum
58.00%

t
cum
cum
cum
kg

0.43
0.45
0.54
0.36
1.72

day
day
day

0.133
1.53

hour
hour

0.40
0.40

cum
20.00%

cum
25.00%

cum
30.00%

(i) Height upto 5m

Basic Cost of Labour, Material & Machinery (a+b+c)


d)
Formwork and staging of (a+b+c)

cum
25.00%

e&f) Overheads & Contractors Profit


Rate per cum = (a+b+c+d+e+f)
(ii) Height 5m to 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)

cum
30.00%

(iii) Height above 10m


cum
Basic Cost of Labour, Material & Machinery (a+b+c)
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
Case II : Using Batching Plant, Transit Mixer and
Concrete Pump (PSC Grade M-40) (Design Mix)
Unit = cum

35.00%

Taking output = 1 cum


a) Material
Cement

0.430

Coarse sand

cum

0.45

20 mm Aggregate

cum

0.54

10 mm Aggregate
Admixture @ 0.4 per cent of cement
b)
Labour
Mate
Mason
Mazdoor (Unskilled)
c)
Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA

cum

0.36

kg

1.72

day

day

0.029

day

0.175

hour

0.05

hour

0.05

581

RBR-SPST
Index-code

S. No

Description

Unit

Quantity

3
hour

4
0.05

hour

0.125

tkm

2.5L

hour

0.05

I
(i)

(ii)

(iii)

II
(i)

(ii)

(iii)

Loader
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump
Basic Cost of Labour, Material & Machinery (a+b+c)
For formwork and staging add the following :
For solid / voided slab super-structure
Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
Height above 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
For T-beam & slab
Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
Height above 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)

Rate
Rs.

Amount
Rs.

Remarks

cum

cum
23.00%

cum
28.00%

cum
23.00%

cum
28.00%

cum
33.00%

582

RBR-SPST
Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

III For cast-in-situ box girder, segment construction and

balanced cantilever
(i) Height upto 5m

Basic Cost of Labour, Material & Machinery (a+b+c)


d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
(ii) Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
(iii) Height above 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
F PSC Grade M-45 (Design Mix)

cum
38.00%

cum
48.00%

cum
58.00%

Using Batching Plant, Transit Mixer and Concrete Pump

Unit = 1 cum
Taking output = 1 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
Admixture @ 0.4 per cent of cement
b)
Labour
Mate
Mason
Mazdoor (Unskilled)
c)
Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump
Basic Cost of Labour, Material & Machinery (a+b+c)
For formwork and staging add the following :
For solid / voided slab super-structure

0.465

cum

0.450

cum

0.540

cum

0.360

kg

1.860

day

day

0.029

day

0.174

hour

0.050

hour

0.050

hour

0.050

hour

0.125

tkm

2.5 L

hour

0.050

(i) Height upto 5m

Basic Cost of Labour, Material & Machinery (a+b+c)


d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
(ii) Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
(iii) Height above 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)

16.00%

21.00%

26.00%

583

RBR-SPST
Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

II
(i)

(ii)

(iii)

III
(i)

(ii)

(iii)

For T-beam & slab including launching of precast


girders by launching truss upto 40 m span
Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
Height above 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
For cast-in-situ box girder, segmental construction and
balanced cantilever
Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
Height above 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
PSC Grade M-50 Design Mix (MORTH)
Using Batching Plant, Transit Mixer and Concrete
Pump
Unit = 1 cum
Taking output = 1 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
Admixture @ 0.4 per cent of cement
b)
Labour
Mate
Mason
Mazdoor (Unskilled)
c)
Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump
Basic Cost of Labour, Material & Machinery (a+b+c)

21.00%

26.00%

31.00%

36.00%

46.00%

56.00%

0.49

cum

0.45

cum

0.54

cum

0.36

kg

1.96

day
day

0.029

day

0.174

hour

0.05

hour

0.05

hour

0.05

hour

0.125

tkm

2.5 L

hour

0.05

584

RBR-SPST
Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

III
(i)

(ii)

(iii)

For formwork and staging add the following:


For cast-in-situ box girder, segmental construction
balanced cantilever
Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
Height above 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
PSC Grade M- 55 MORTH
Using Batching Plant, Transit Mixer and Concrete
Pump
Unit = 1 cum
Taking output = 1 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
Admixture @ 0.4 per cent of cement
b)
Labour
Mate
Mason
Mazdoor (Unskilled)
c)
Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump
Basic Cost of Labour, Material & Machinery (a+b+c)

cum
35.00%

cum
45.00%

cum
55.00%

0.529

cum

0.450

cum

0.540

cum

0.360

kg

2.120

day
day

0.029

day

0.174

hour

0.05

hour

0.05

hour

0.05

hour

0.125

tkm

2.5 L

hour

0.05

For formwork and staging add the following:


III For cast-in-situ box girder, segmental construction and

balanced cantilever
(i) Height upto 5m

Basic Cost of Labour, Material & Machinery (a+b+c)


d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
(ii) Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
(iii) Height above 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)

cum
35.00%

cum
45.00%

cum
55.00%

585

RBR-SPST
Index-code

S. No
1

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

2
3
4
5
6
Note in MORTH : 1. Where ever concrete is carried out using batching plant, transit mixer, concrete
pump, admixers conforming IS: 9103 @ 0.4 per cent of weight of cement may be added for achieving
desired slump of concrete.
2. Cement provided for various components of the super structure is for estimating purpose only. Actual
quantity of cement will be as per approved mix design. Similarly, the provision for coarse and fine
aggregates is for estimating purpose and the exact quantity shall be as per the mix design.

Remarks
7

3. The items like needle and surface vibrators are part of minor T & P which is already covered under the
overhead charges. As such these items have not been added separately in the rate analysis.
2

in superstructure complete as per drawing and


technical specifications Clauses 1002, 1010 and 1202
MORD / 1600 MORTH, for Bars below 36 mm dia
including over laps and wastage, where they are not
welded.
Unit = t

RBR-SPST-2

RBR-SPST-3

(i) Supplying, fitting, and placing HYSD bar reinforcement

(a) Material
HYSD bars including 5 per cent for laps and wastage
Binding wire
(b) Labour for cutting, bending, tying and placing in
position
Mate
Blacksmith/ Rod Binder
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per t = a+b+c+d
(ii) Supplying, fitting, and placing HYSD bar reinforcement
in superstructure complete including wastage, as per
drawing and technical specifications Clauses 1002,
1010 and 1202 MORD / 1600 MORTH, for Bars 36 mm
dia and above, where welding required to be done
compulsorily.
Unit = t
(a) Material
HYSD bars including 2.5 per cent for wastage
Welding Electrodes @ 5 per joint (14 joints / ton)
Welding Charges (Hire charges of Welding Machine)
Binding wire
(b) Labour for cutting, bending, tying and placing in
position
Welder
Blacksmith/ Rod Binder
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per t = a+b+c+d
(i) Supplying, fitting, and placing TMT bar reinforcement in
superstructure complete as per drawing and technical
specifications Clauses 1002, 1010 and 1202 MORD /
1600 MORTH for Bars below 36 mm dia including over
laps and wastage, where they are not welded.

t
kg

1.05
8.00

day

day

3.00

day

8.44

1.025

each

70.000

Hr

10.00

kg

8.00

day

2.50

day

3.00

day

8.44

Unit = t
(a) Material
t
TMT bars including 5 per cent for laps and wastage
kg
Binding wire
(b) Labour for cutting, bending, tying and placing in
day
position
Mate
day
Blacksmith/ Rod Binder
day
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per t = a+b+c+d

1.05
8.00

3.00
8.44

586

RBR-SPST
Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

(ii) Supplying, fitting, and placing TMT bar reinforcement in


A superstructure complete including wastage, as per

RBR-SPST-4

RBR-SPST-5

drawing and technical specifications Clauses 1002,


1010 and 1202 MORD / 1600 MORTH for Bars 36 mm dia
and above, where welding required to be done
compulsorily.
Unit = t
(a) Material
TMT bars including 2.5 per cent for wastage
Welding Electrodes @ 5 per joint (14 joints / ton)
Welding Charges (Hire charges of Welding Machine)
Binding wire
(b) Labour for cutting, bending, tying and placing in
position
Welder
Blacksmith/ Rod Binder
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per t = a+b+c+d
i Supplying, fitting, and placing MS bar reinforcement in
superstructure complete as per drawing and technical
specifications Clauses 1002, 1010 and 1202, for Bars
below 36 mm dia including over laps and wastage,
where they are not welded.
Unit = t
(a) Material
MS bars including 5 per cent for laps and wastage
Binding wire
(b) Labour for cutting, bending, tying and placing in
position
Mate
Blacksmith/ Rod Binder
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per t = a+b+c+d
ii High
tensile steel wires/strands including all
accessories for stressing, stressing operations and
grouting complete as per drawing and Technical
Specifications in section 1800 MORTH
Unit = 1 MT
Taking output = 0.377 MT
Details of cost for 12T13 strand 40 m long cable (weight =
0.377
MT)
a) Material

1.025

each

70.000

Hr

10.00

kg

8.00

day

2.50

day

3.00

day

8.44

1.05

kg

8.00

day
day

3.00

day

8.44

H.T. Strand @ 9.42 kg/m including 2 per cent for wastage t


and extra length for jacking
Sheathing duct ID 66 mm along with 5 per cent extra m
length 40 x 1.05 = 42 m.
Tube anchorage set complete with bearing plate, each
permanent wedges etc
Cement for grouting including 3 per cent wastage @ 3.00 t
kg/m = 3 x 1.03 x 40 = 123.60 kg (say, = 125 kg)
Add 0.50 per cent cost of material for Spacers, Insulation
tape and miscellaneous items
b)
Labour
i) For making and fixing cables, anchorages
day
Mate
day
Blacksmith
day
Mazdoor (Unskilled)
ii) For prestressing
day
Mate/Supervisor
day
Prestressing operator / Fitter
day
Mazdoor (Unskilled)
iii) For grouting
day
Mate/Supervisor
day
Mason
day
Mazdoor (Unskilled)
c)
Machinery
hour
Stressing jack with pump
hour
Grouting pump with agitator
hour
Generator 33 KVA.
d&e) Overheads & Contractors Profit
Cost for 0.377 MT (a+b+c+d+e)
Rate per MT = (a+b+c+d+e)/0.377
Note : Cost of HT steel shall be taken for delivery at site. Hence
carriage has not been considered.
(i) Providing and laying cement concrete wearing course
M 30 grade including reinforcement complete as per
drawing and technical specifications Clauses 800 and
1206.3 MORD and 2702 MORTH

0.39
42.00
2.00
0.125

1.00
3.16
0.25
1.05
0.25
1.05
2.50
1.00
3.50

587

RBR-SPST
Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

Unit = cum
(a) Material
Cement
Sand
20 mm aggregate
10 mm aggregate
HYSD bar reinforcement including binding wire (Rate as
per item 13.2) except OH & CP
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
Mazdoor (Unskilled) for cleaning deck slab concrete
surface
c) Machinery
Concrete mixer 0.4/0.28 cum capacity
Generator 33 KVA.
(d) Formwork @ 3% of cost of concrete
e&f) Overheads & Contractors Profit
Rate per cum = a+b+c+d+e+f
(ii) Providing and laying cement concrete wearing course
M 25 grade including reinforcement complete as per
drawing and technical specifications Clauses 800 and
1206.3 MORD
Unit = cum
(a) Material
Cement
Sand
20 mm aggregate
10 mm aggregate
HYSD bar reinforcement including binding wire (Rate as
per item 13.2) except OH & CP
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
Mazdoor (Unskilled) for cleaning deck slab concrete
surface
c) Machinery
Concrete mixer 0.4/0.28 cum capacity
Generator 33 KVA.
(d) Formwork @ 3% of cost of concrete
e&f) Overheads & Contractors Profit
Rate per cum = a+b+c+d+e+f

0.407

cum

0.45

cum

0.54

cum

0.36

0.075

day

day

0.10

day

1.39

day

0.15

hour

0.40

hour

0.40
3.00%

0.400

cum

0.45

cum

0.54

cum

0.36

0.075

day

day

0.10

day

1.39

day

0.15

hour

0.40

hour

0.40
3.00%

588

RBR-SPST
Index-code
RBR-SPST-6

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

Mastic Asphalt
Providing and laying 12 mm thick mastic asphalt wearing
course on top of deck slab excluding prime coat with paving
grade bitumen meeting the requirements given in table 500-29,
prepared by using mastic cooker and laid to required level and
slope after cleaning the surface, including providing antiskid
surface with bitumen precoated fine grained hard stone
chipping of 9.5 mm nominal size at the rate of 0.005cum per 10
sqm and at an approximate spacing of 10 cm center to center
in both directions, pressed into surface when the temperature
of surfaces not less than 100 deg. C, protruding 1 mm to 4 mm
over mastic surface, all complete as per clause 515 & 2702
MORTH.

Unit = sqm
Taking output = 72.46 sqm (2 tonnes)(0.869 cum)
assuming a density of 2.3 tonnes/cum.
a) Labour
day
Mate
day
Mazdoor (Unskilled)
day
Mazdoor (Skilled)
b) Machinery
hour
Mechanical broom @ 1250 sqm per hour
Air compressor 250 cfm
Mastic cooker 1 tonne capacity
Bitumen boiler 1500 litres capacity
Tractor for towing and positioning of mastic cooker and
bitumen boiler
c) Material
Base mastic (without coarse aggregates) = 60 per cent
Coarse aggregate(3.35mm to 9.5 mm size) = 40 %

11.49
1.25
0.06

hour
hour
hour

0.06
6.00
6.00

hour

1.00

Proportion of material required for mastic asphalt with


coarse aggregates (based on mix design done by CRRI for
a specific case)
i) Bitumen 80/100 or 60/70 or 30/40 @ 10.2 per cent by t
weight of mix. 2 x 10.2/100 = 0.204
ii) Crusher stone dust @ 31.9 per cent by weight of mix = 2 cum
x 31.9/100 = 0.638 tonnes = 0.638/1.625 = 0.39
iii) Lime stone dust filler with calcium carbonate content not t
less than 80 per cent by weight @ 17.92 per cent by
weight of mix = 2 x 17.92/100 = 0.36
iv) Coarse aggregates 9.5 mm to 3.35 mm size @ 40 per cum
cent by weight of mix = 2 x 40/100 = 0.8 MT = 0.8/1.456 =
0.55
v) Pre-coated stone chips of 9.5 mm nominal size for skid cum
resistance = 72.46x0.005/10 = 0.036
vi) Bitumen for coating of chips @ 2 per cent by weight = kg
0.036 x 1.456 x 2/100 = 0.001048MT = 1.05kg
d&e) Overheads & Contractors Profit
Cost for 72.46 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/72.46

0.204
0.39
0.36

0.55

0.036
1.05

Note : 1.The rates for 6 mm or any other thickness may be worked out on pro-rata basis.

2. Where tack coat is required to be provided before laying mastic asphalt, the same is
required to be measured and paid separately.
3.The quantities of binder, filler and aggregates are for estimating purpose. Exact quantities
shall be as per mix design.
4.This rate analysis is based on design made by CRRI for a specific case and is meant for
estimating purposes only. Actual design is required to be done for each case.
5.The quantity of bitumen works out 17 per cent of the mastic asphalt blocks without
aggregates and falls within the standards laid down by MoRTH Specifications.

589

RBR-SPST
Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

RBR-SPST-7

Construction of R.C.C. railing of M 25 grade in cast-insitu with 20 mm nominal size aggregate, true to line
and grade, tolerance of vertical railing post not to
exceed 1 in 500, centre-to-centre spacing between
vertical posts not to exceed 2000 mm as per drawing
and technical specifications Clauses 800, 900 and
1208.3 MORD.
Unit = Running m
Taking output = 4x12 m
Span = 48 m
(a) M 25 grade R.C.C.
No. of vertical posts = (6+1) 4 = 28 nos
Cross-sectional area of vertical post = 0.25x0.275 = 0.069 sqm

Concrete in vertical posts = 0.069x28x1.00 = 1.932 cum


Hand rail in 3 tiers = 3x48 = 144 m
Cross-sectional area = 0.17x0.175 = 0.03 sqm
Concrete in hand rails = 0.03 x 144 = 4.32 cum
cum
6.252
Total concrete = 1.932+4.32 = 6.252 cum
t
1.36
(b) HYSD bar reinforcement (Rate as per item 13.2)
c&d) Overheads & Contractors Profit
Cost for 48 m = (a+b+c+d)
Rate per m = (a+b+c+d)/48
Sub Analysis for Rate of Concrete
(a) Material
t
0.40
Cement
cum
0.45
Coarse sand
cum
0.54
20 mm aggregate
cum
0.36
10 mm aggregate
(b) Labour
day
Mate
day
0.12
Mason (1st Class)
day
2.09
Mazdoor (Unskilled)
c) Machinery
hour
0.40
Concrete mixer 0.4/0.28 cum capacity
12.00%
Formwork @ 12%
Total (a+b+c+d)
Note : 1. 48 m length is the total linear length adding both sides
of 2x12 m span
2. Quantities of material have been adopted from standard plans
of MORTH vide drawing No SD/202
ii Construction of precast RCC railing of M30 Grade,
aggregate size not exceeding 12 mm, true to line and
grade, tolerance of vertical RCC post not to exceed 1 in
500, centre to centre spacing between vertical post not
to exceed 2000 mm, leaving adequate space between
vertical post for expansion, complete as per approved
drawings and technical specifications, in sections
1500, 1600, 1700 & 2703 MORTH.
Unit = 1 RM
Taking output = 2 x 24 m span = 48 m
a) Material
4.092
Cement concrete M30 Grade Refer relevant item of cum
concrete in Item 14.1(C) by using batching plant, excluding
formwork i.e. per cum basic cost (a+b+c)
No. of vertical posts = (12 + 2)2 = 28 Nos., External area of vertical
post 0.25x0.275 = 0.069sqm, Concrete in Vertical posts = 0.069 x
28 = 1.932 cum, Hand rail in 3 tiers = 3 x 24 = 72 m, External area =
0.170 x 0.175 = 0.03 sqm, Concrete in hand rails = 0.03 x 72 = 2.16
cum, Total Concrete = 1.932 + 2.16 = 4.092 cum. (Refer MoRTH SD
/ 202).

Add 5 per cent of above cost for form work for casting in cum
casting yard.

5.00%

590

RBR-SPST
Index-code

S. No

Description

Unit

Quantity

3
t

4
0.865

Rate
Rs.

Amount
Rs.

Remarks

HYSD bar reinforcement Rate as per item No 14.2


(Excluding OH & CP)
Refer MoRTH SD / 202.
5.00%
Add 5 per cent of (a) for handling and fixing of precast
panels in position
b&c) Overheads & Contractors Profit
Rate for 48 m (a+b+c)
Rate per metre (a+b+c)/48
Note : 1. Quantities of material have been adopted from standard plans of MoRTH vide
drawing no. SD/202.
2. 48 m length is the total linear length adding both sides of 24 m span.
iii Construction of RCC railing of M30 Grade in-situ with 20 mm
nominal size aggregate, true to line and grade, tolerance of
vertical RCC post not to exceed 1 in 500, centre to centre
spacing between vertical post not to exceed 2000 mm, leaving
adequate space between vertical post for expansion, complete
as per approved drawings and technical specifications in
sections 1500, 1600, 1700 & 2703 MORTH.

Unit = 1 RM
Taking output = 2 x 24 m span = 48 m.
a) Material
Cement concrete M30 Grade Refer relevant item of concrete in Item cum
14.1(C) by using batching plant, excluding formwork i.e. per cum
basic cost (a+b+c)
No. of vertical posts = (12 + 2)2 = 28 Nos., External area of vertical
post 0.25x0.275 = 0.069sqm, Concrete in vehicle posts = 0.069 x 28
= 1.932 cum, Hand rail in 3 tiers = 3 x 24 = 72 m, External area =
0.170 x 0.175 = 0.03 sqm, Concrete in hand rails = 0.03 x 72 = 2.16
cum, Total Concrete = 1.932 + 2.16 = 4.092 cum. (Refer MoRTH SD
/ 202).
cum
Add 12 per cent of above cost for form work.
HYSD bar reinforcement Rate as per item No 14.2 (Excluding OH &
t
CP)

4.092

10.00%
0.865

refer MoRTH SD / 202.


b&c) Overheads & Contractors Profit
Cost for 48 m (a+b+c)
Rate per metre (a+b+c)/48
Note : 1. Quantities of material have been adopted from standard
plans of MoRTH vide drawing no. SD/202.

RBR-SPST-8

2. 48 m length is the total linear length adding both sides of


span.
Providing fitting and fixing mild steel railing complete
as per drawing and technical specifications Clause
1208.2 MORD / 1900 & 2703 MORTH.
Unit = Running m
Taking output = 100 m (2 x 50 m span)
(a) Material
IS MC 100=2.806x1.05=2.946 t
MS Flats = 0.964x1.05 =1.012 t
MS bars = 0.17x1.05=0.18 t
MS bolts, nuts and washers
(b) Labour
Mate
Blacksmith
Mazdoor (Unskilled)
(c) Add 5 per cent of (a) for painting one shop coat with
red oxide primer and three coats of synthetic enamel
paint and consumables to safeguard against
weathering and corrosion.
(d) Add for cost of concrete for fixing vertical post in
the preformed recess @ 1 per cent of (a)

24 m

2.946

t
t
kg

1.01
0.18
150.00

day

day

30.00

day

42.80
5.00%

1.00%

591

RBR-SPST
Index-code

S. No

Description

Unit

Quantity

4
1.00%

RBR-SPST-9

RBR-SPST-10

11

RBR-SPST-11

Amount
Rs.

Remarks

(e) Add for electricity charges, welding and drilling


equipment, electrodes and other consumables @ 1 per
cent of (a)
f&g) Overheads & Contractors Profit
Cost for 100 m = (a+b+c+d+e+f+g)
Rate per m = (a+b+c+d+e+f+g)/100
Note : A typical drawing for MS railing has been followed for estimate purpose. Rate may
be worked out as per design to be followed
Providing and fixing in position pipe railing consisting
of IS Rolled steel joist posts designation IS MB 100
(100x75) at 2.5 m interval and three rows of 50 mm dia
steel pipes (light) including fixing in position on bridge
deck complete as per drawing and Technical
Specifications Clause 1208.2 MORD
Unit = Running m
Taking output = 2 x 10 m = 20 m
(a) Material
t
0.13
Steel posts IS MB 100 (100 x 75)
5 x 2 x 11.5 x 1.1 x 1.05 = 130 kg
m
60.00
50 mm dia steel pipes light quality with ISI mark
20 x 3 = 60 m
kg
50.00
M.S Bolts, nuts and washers
5.00%
Add @ 5 per cent of (a) for painting one shop coat with red
oxide primer and three coats of synthetic enamel paint and
consumables
Add for electricity charges, welding and drilling equipment,
electrodes and other consumables @ 1% of (a)

10

Rate
Rs.

(b) Labour
Mate
Blacksmith
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Cost for 20 m steel railing = a+b+c+d
Rate per metre = (a+b+c+d)/20
Brick masonry work in cement mortar 1:3 in parapet
excluding pointing and plastering as per drawing and
technical specifications Clauses 600, 900 and 1208.4
MORD
Unit = cum
(a) Material
Bricks (Modular Bricks 19 x 9 x 9 cms)
Cement mortar (Rate as in item 11.5 I)
(b) Labour
Mate
Mason 1st Class
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
Drainage spouts complete as per drawing and
technical specifications Clause 1209 MORD & 2705
MORTH
Unit = 1 No
(a) Material
Corrosion resistant structural steel grating including 5 per
cent wastage
G I pipe 100 mm dia
GI bolt 10 mm Dia
Galvanised MS flat clamp

1.00%

day

day

6.00

day

8.56

Nos.

520.00

cum

0.20

day

day

0.89

day

1.80

kg

4.00

6.00

each

6.00

each

2.00

592

RBR-SPST
Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

(b) Labour
For fabrication
Mate
Blacksmith, Welder etc. (Skilled)
Mazdoor (Unskilled)
For fixing in position
Mate
Mason (1st Class)
Mazdoor (Unskilled)
Add @ 5 per cent of cost of material and labour (a+b) for
electrodes, gas cutting, sealant, anti-corrosive bituminous
paint, mild steel grating etc.
c&d) Overheads & Contractors Profit
Rate per m = a+b+c+d

day

day

0.02

day

0.04

day

day

0.01

day

0.21
5.00%

Note in MORTH : 1. In case of viaducts in urban areas, the drainage spouts should be connected with
suitably located pipelines to discharge the surface run-off to drains provided at ground level.
2. In case of bridges, sufficient length of G.I Pipe shall be provided to ensure that there is no splashing of
water from the drainage spout on the structure.
12

RBR-SPST-12

P.C.C. M 15 ordinary grade (1:2.5:5) leveling course


below approach slab complete as per drawing and
technical specifications Clauses 800 and 1211 MORD &
2700 MORTH
(i) Nominal mix (1:2.5:5) / PCC M 15 using Concrete
Mixture
Unit = cum
(a) Material
Cement
Coarse sand
40 mm aggregate
20 mm aggregate
10 mm aggregate
(b) Labour
Mate
Mason (1st Class0
Mazdoor (Unskilled)
c) Machinery
Concrete mixer 0.4/0.28 cum capacity
Generator 33 KVA.
d&e) Overheads & Contractors Profit
Rate per cum = a+b+c+d+e+f
(ii) Nominal mix 1:2.5:5 (Hand mixing) MORD
Unit = cum
(a) Material
Cement
Coarse sand
40 mm aggregate
20 mm aggregate
10 mm aggregate
(b) Labour
Mate
Mason (1st Class0
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d

0.275

cum

0.48

cum

0.54

cum

0.27

cum

0.09

day

day

0.10

day

1.39

hour

0.40

hour

0.40

0.275

cum

0.48

cum

0.54

cum

0.27

cum

0.09

day

day

0.10

day

2.36

593

RBR-SPST
Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

2
Reinforced Cement Concrete M 25 grade approach slab
including reinforcement and formwork complete as per
drawing and technical specifications Clauses 800 and 1211
MORD / 1500, 1600, 1700 & 2704 MORTH

13

RBR-SPST-13

Unit = cum
(a) Material
Reinforced cement concrete M 25 grade
cum
Rate as per Item 11 (i)
HYSD reinforcement
t
Rate per item 2
Rate per cum = (a)
ii Reinforced cement concrete approach slab including
reinforcement and formwork complete as per drawing
and Technical specification 1500, 1600, 1700 & 2704
MORTH
Unit = 1 cum
Taking output = 1 cum
a) Material
Cement concrete M30 Grade Refer relevant item of concrete in item cum
1(III) by using batching plant, excluding formwork i.e. per cum basic
cost (a+b+c) (Excluding OH & CP)
Form Work : Refer relevant item of concrete in item No. cum

1(III) except that form work may be added at the rate of 2


per cent of cost against 3.5 per cent provided in the
foundation concrete.
HYSD bar reinforcement Rate as per item No 2 (Excluding

1.00
0.05

1.00

2.00%

0.05

OH&CP)

RBR-SPST-14

b&c) Overheads & Contractors Profit


Rate per cum (a+b+c)
Note : The grade of reinforced cement concrete may be adopted as M30 for severe
conditions and M25 for moderate conditions.
14
Providing and laying of an electrometric slab seal
expansion joint complete as per approved drawing and
approved
specifications
to
be
installed
by
manufacturer/supplier
or
their
authorised
representative
ensuring
compliance
to
the
manufacturers instruction for installation and as per
Technical Specification Clause1207.2.5 MORD / 2606
MORTH
(i) Unit = Running m
Taking output = 12.00 m
(a) Material
12.00
Supply of electrometric slab seal expansion joint assembly m
manufactured by using chloroprene elastomer for
elastomeric slab unit conforming to Clause 915.1 of IRC:83
(Part II) complete as per approved drawings and
specifications.
(b) Labour
day
Mate
day
1.00
Mazdoor (Unskilled)
day
0.56
Mazdoor (skilled)
5.00%
Add 5 per cent of cost of material for anchorage
reinforcement, welding and other incidentals.
c&d) Overheads & Contractors Profit
Rate per m = (a+b+c+d)/ 12
(ii) Unit = Running m
Taking output = 7.5 m
(a) Material
7.50
Supply of elastomeric slab seal expansion joint assembly m
manufactured by using chloroprene elastomer for
elastomeric slab unit conforming to Clause 915.1 of IRC:83
(Part II) complete as per approved drawings and
specifications.
(b) Labour
day
Mate
day
0.74
Mazdoor (Unskilled)
day
0.40
Mazdoor (skilled)
5.00%
Add 5 per cent of cost of material for anchorage
reinforcement, welding and other incidentals.
c&d) Overheads & Contractors Profit
Rate per m =(a+b+c+d)/7.5
15

RBR-SPST-15

Providing and laying of compression seal joint consisting of


steel armoured nosing at two edges of the joint gap suitably
anchored to the deck concrete and a preformed chloroprene
elastomer or closed cell foam joint sealer compressed and
formed into the joint gap with special adhesive binder to cater
for a horizental movement upto 40mm and vertical movement of 3
mm as per drawing and Technical Specification Clause
1207.2.4 / 2600 MORTH

594

RBR-SPST
Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

Galvanised angle section 100 mm x 100 mm of 12 mm thickness


weldable structural steel as per IS:2062, 2 Nos. of 12m length each
@ 17.7 kg/m and 5% wastage.

kg

446.00

(a) Unit = Running m

Taking output = 12m


(a) Material

Add 5 per cent of cost of above for structural steel for


welding and other incidentals.
Preformed continuous chloroprene elastomer or closed cell foam
sealing element with high tear strength, vulcanised in a single
operation for the full length of a joint to ensure water tightness.

5.00%
m

12.00

Add 1 per cent of cost of sealing element for lubricant-cumadhesive and other consumables.
(b) Labour
day
Mate
day
Mazdoor (Skilled)
day
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Cost for 12 m = a+b+c+d
Rate per m = (a+b+c+d)/ 12
(b) Unit = Running m
Taking output = 7.5 m
(a) Material

1.00%

Galvanised angle section 100 mm x 100 mm of 12 mm thickness


weldable structural steel as per IS:2062, 2 Nos. of 7.5 m length each
@ 17.7 kg/m and 5 per cent wastage.
Add 5 per cent of cost of above for structural steel for welding and
other incidentals.
Preformed continuous chloroprene elastomer or closed cell foam
sealing element with high tear strength, vulcanised in a single
operation for the full length of a joint to ensure water tightness.

293.00

kg

0.30

5.00%
m

Add 1 per cent of cost of sealing element for lubricant-cum-adhesive


and other consumables.

(b) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Cost for 7.5 m = a+b+c+d
Rate per m = (a+b+c+d)/7.5

0.64

7.50

1.00%

day
day

0.224

day

0.40

Note : 1. The installation shall be done by the manufacturer or his authorised representative to the
satisfaction of the Engineer.
2. The concreting for joining the expansion joint assembly with the deck has not been included in this
analysis as the same is catered for in the quantities of R.C.C deck
3. The anchoring bars of the expansion joint assembly shall be welded to the main reinforcement of the
deck.

595

RBR-SPST
Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

Buried Joint
Providing and laying a buried expansion joint, covered
with 12 mm thick, 200 mm wide galvanised weldable
structural steel plate as per IS:2062, placed
symmetrical to centre line of the joint, resting freely
over the top surface of the deck concrete, welding of 8
mm dia, 100 mm long galvanised nails spaced 300 mm
c/c along the centre line of the plate, as per Technical
Specification Clause 1207.2.3 MORD / 2604 MORTH.

16

RBR-SPST-16

Unit = Running m
Taking output = 12 m
(a) Material
Galvanised M.S. plate 200 mm wide 12 mm thick @ 94.20 kg
kg/sqm including 5 per cent wastage.
Add 1 per cent of cost of steel plate for cutting, welding,
consumables and galvanised nails.
(b) Labour
day
Mate
day
Mazdoor (Skilled)
day
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Cost for 12 m = a+b+c+d
Rate per m = (a+b+c+d)/ 12

17

1.00%

0.22
0.40

Unit = Running m
Taking output = 7.5 m
(a) Material
Galvanised M.S. plate 200 mm wide 12 mm thick @ 94.20
kg/sqm including 5 per cent wastage.
Add 1 per cent of cost of steel plate for cutting, welding,
consumables and galvanised nails.
(b) Labour

RBR-SPST-17

237.50

kg

150.00
1.00%

day
Mate
day
0.16
Mazdoor (Skilled)
day
0.25
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Cost for 7.5 m = a+b+c+d
Rate per m = (a+b+c+d)/ 7.5
NOTE : Guidelines laid down vide the MoRTH circular No. RW/NH-34059/1/96-S&R dated
30.11.2000 and subsequent corrigendum dated 25.01.2001 may be referred for expansion
joints.
Filler Joint
(I) Providing and fixing 2 mm thick corrugated copper
(A) plate in expansion joint as per drawing and technical

specifications Clause 1207.2.2 MORD


Unit = Running m
Taking output = 7.5 m
(a) Material
Copper plate - 7.5 m long x 250 mm wide
Area = 7.5 x 0.25 = 1.875 sqm
Weight = 1.875 x 0.002 x 8900 = 33.4 kg.
Wastage @ 2.5% = 0.83 kg.
Total weight = 34 kg
(b) Labour
For cutting, bending, carrying and fixing etc.
Mate
Mazdoor (Unskilled)
Mazdoor (Skilled)
c&d) Overheads & Contractors Profit
Cost for 7.5 m = a+b+c+d
Rate per m = (a+b+c+d)/7.5
(B) Providing & fixing 2 mm thick corrugated copper plate
in expansion joint complete as per drawing & Technical
Specification 2605 MORTH.
Unit = Running m
Taking output = 12 m
(a) Material
Copper plate - 12 m long x 250 mm wide
Area = 12 x 0.25 = 1.875 sqm
Weight = 3 x 0.002 x 8900 = 53.4 kg
Wastage @ 2.5% = 1.33 kg/54.73 kg say = 55 kg.
Total weight = 108.4 kg
(b) Labour
For cutting, bending, carrying and fixing etc.
Mate
Mazdoor (Unskilled)
Mazdoor (Skilled)
c&d) Overheads & Contractors Profit

kg

34.00

day

day

0.35

day

0.37

kg

55.00

day

day

0.54

day

0.50

596

RBR-SPST
Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

sqm

1.875

(II)
(A)

(B)

(III)
(A)

Cost for 12 m = a+b+c+d


Rate per m =(a+b+c+d)/ 12
Providing and fixing 20 mm thick compressible fiber
board in expansion joint complete as per drawing and
technical specifications MORD
Unit = Running m
Taking output = 7.5 m
(a) Material
20 mm thick compressible fiber board 250 mm deep
Area = 7.5 x 0.25 = 1.875 sqm
(b) Labour
For carrying, placing and fixing
Mate
Mazdoor (Unskilled)
Mazdoor (Skilled)
c&d) Overheads & Contractors Profit
Cost for 7.5 m = a+b+c+d
Rate per m = (a+b+c+d)/7.5
Providing and fixing 20 mm thick compressible fiber
board in expansion joint complete as per drawing and
technical specifications 2605 MORTH
Unit = Running m
Taking output = 12 m
(a) Material
20 mm thick compressible fiber board 250 mm deep
Area = 12 x 0.25 = 3.00 sqm
(b) Labour
For carrying, placing and fixing
Mate
Mazdoor (Unskilled)
Mazdoor (Skilled)
c&d) Overheads & Contractors Profit
Cost for 12 m = a+b+c+d
Rate per m =(a+b+c+d)/ 12
Providing and fixing in position 20 mm thick
premoulded joint filler in expansion joint for fixed ends
of simply supported spans, covered with sealant
complete as per drawing and technical specifications
MORD
Unit = Running m
Taking output = 7.5 m
(a) Material
Premoulded joint filler 20 mm thick and 300 mm deep

day

day

0.11

day

0.1

sqm

3.00

day
day

0.1

day

0.108

sqm

2.25

597

RBR-SPST
Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

(b) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Skilled)
c&d) Overheads & Contractors Profit
Cost for 7.5 m = a+b+c+d
Rate per m = (a+b+c+d)/7.5

day

day

0.14

day

0.07

(B) Providing and fixing in position 20 mm thick premoulded joint


filler in expansion joint for fixed ends of simply supported
spans not exceeding 10 m to cater for a horizontal movement
upto 20 mm, covered with sealant complete as per drawing and
technical specifications MORTH

Unit = Running m
Taking output = 12 m
(a) Material
sqm
3.6
Premoulded joint filler 20 mm thick and 300 mm deep
(b) Labour
day
Mate
day
0.21
Mazdoor (Unskilled)
day
0.1
Mazdoor (Skilled)
c&d) Overheads & Contractors Profit
Cost for 12 m = a+b+c+d
Rate per m = (a+b+c+d)/ 12
(IV) Providing and filling joint sealing compound as per
(A) drawings and technical specifications with coarse sand
and 6 per cent bitumen by weight MORD
Unit = Running m
Taking output = 7.5 m
00 mm wide x 10 mm deep recess
(a) Material
cum
0.008
Sand
Volume = 7.5 x 0.1 x 0.01 = 0.008 cum
Weight = 0.008 x 1400 = 11.2 kg
t
0.0007
Bitumen-11.2 x 0.06 = 0.672 kg
(b) Labour
day
Mate
day
0.52
Mazdoor (Skilled)
day
0.10
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Cost for 7.5 m = a+b+c+d
Rate per m = ((a+b+c+d)/7.5) or ((a+b+c+d)/ 12)
(B) Providing and filling joint sealing compound as per
drawings and technical specifications with coarse sand
and 6 per cent bitumen by weight MORTH
Unit = Running m
Taking output = 12 m
00 mm wide x 10 mm deep recess
(a) Material
cum
0.012
Sand
Volume = 12 x 0.1 x 0.01 = 0.012 cum
Weight = 0.012 x 1400 = 16.8 kg
t
0.001
Bitumen-16.8 x 0.06 = 1.008 kg
(b) Labour
day
Mate
day
0.12
Mazdoor (Skilled)
day
0.5
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Cost for 12 m = a+b+c+d
Rate per m = (a+b+c+d)/ 12
Note : For arriving at the final rate for filler joints per m length and per cm depth of joint
filling compound, the rates of Sr. Nos (i), (ii), (iii) and (iv) shall be added.

598

RBR-SPST
Index-code
RBR-SPST-18

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

18

Asphaltic Plug joint


Providing and laying of asphaltic plug joint to provide
for horizontal movement of 25 mm and vertical
movement of 25 mm, depth of joint varying from 75 mm
to 100 mm, width varying from 500 mm to 750 mm (in
traffic direction), covered with a closure plate of 200mm
x 6mm of weldable structural steel conforming to IS:
2062, asphaltic plug to consist of polymer modified
bitumen binder, carefully selected single size
aggregate of 12.5 mm nominal size and a heat resistant
foam caulking / backer rod, all as per approved
drawings and specifications 2600 MORTH.
Unit = Running meter
Taking output = 12 m
a) Labour
Mate
Mazdoor (unskilled)
Mazdoor (Skilled) / Mason
b) Material
Crushed stone aggregate 12.5 mm nominal size
Polymer modified bitumen
Galvanised structural steel plate 200 mm wide,6 mm thick,
12 m long (2.4 sqm) @ 47.10 kg/sqm including 5 per cent
wastage
Add
1 per cent for welding and foam caulking/backer rod
and other incidentals.
c)
Machinery
Mastic cooker 1 tonne capacity
Smooth 3-wheeled steel roller 8-10 capacity
d&e) Overheads & Contractors Profit
Cost for 12 m asphalt plug joint = (a+b+c+d+e)
Rate per m = (a+b+c+d+e)/12

RBR-SPST-19

19

day
day

1.052

day

0.30

cum

0.75

kg

77.50

kg

113.00
1.00%

hour

1.00

hour

0.50

Note : The nominal size of aggregates shall be 12.5 mm for


depth of joint upto 75 mm and 20 mm for joints of depth more
Strip Seal Expansion Joint
Providing and laying of a strip seal expansion joint catering to
maximum horizontal movement upto 70 mm, complete as per
approved drawings and standard specifications 2607 MORTH
to be installed by the manufacturer / supplier or their
authorised representative ensuring compliance to the
manufacturer's instructions for installation.

Unit = Running meter


Taking output = 12 m
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Skilled)
b) Material
Supply of complete assembly of strip seal expansion joint comprising
of edge beams, anchorage, strip seal element and complete
accessories as per approved specifications and drawings.

day

day

1.00

day

0.30

12.00

5.00%
Add 5 per cent of cost of material for anchorage
reinforcement, welding and other incidentals.
c&d) Overheads & Contractors Profit
Cost for 12 m = (a+b+c+d)
Rate per m = (a+b+c+d)/12
Note : 1. The installation shall be done by the manufacturer or his authorised representative
to the satisfaction of the Engineer.
2. The concreting for joining the expansion joint assembly with the deck has not been
included in this analysis as the same is catered in the quantities of RCC deck.

599

RBR-SPST
Index-code
RBR-SPST-20

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

20

Modular Strip / Box Seal Joint


Providing and laying of a modular strip Box seal
expansion joint including anchorage catering to a
horizontal movement beyond 70 mm and upto 140mm,
complete as per approved drawings and standard
specifications 2600 MORTH to be installed by the
manufacturer
/
supplier
or
their
authorised
representative
ensuring
compliance
to
the
manufacturer's instructions for installation.
Unit = Running meter
Taking output = 12 m
a) Labour
day
Mate
day
Mazdoor (Unskilled)
day
Mazdoor (Skilled)
b) Material
Supply of a modular strip/box seal joint assembly comprising of edge
beams, central beam, 2 modules chloroprene seal, anchorage
elements, support and control system, all steel sections protected
against corrosion and installed by the manufacturer or his authorised
representative.

RBR-SPST-21

21

Supply of a modular box/box seal joint assembly containing 3


modules/cells and comprising of edge beams, two central beams,
chloroprene seal, anchorage elements, support and control system,
all steel sections protected against corrosion and installed by the
manufacturer or his authorised representative.

22

RBR-SPST-23

23

0.46
12.00

c&d) Overheads & Contractors Profit


Cost for 12 m Modular strip/box seal joint = (a+b+c+d)
Rate per m = (a+b+c+d)/12
Note : 1. The installation shall be done by the manufacturer or his authorised representative
to the satisfaction of the Engineer.
2. The concreting for joining the expansion joint assembly with the deck has not been
included in this analysis as the same is catered in the quantities of RCC deck.
3. The anchoring bars of the expansion joint assembly shall be welded to the main
reinforcement of the deck.
Modular Strip / Box Seal Joint
Providing and laying of a modular strip box seal
expansion joint catering to a horizontal movement
beyond 140mm and upto 210mm, complete as per
approved drawings and standard specifications 2600
MORTH to be installed by the manufacturer / supplier
or their authorised representative ensuring compliance
to the manufacturer's instructions for installation.
Unit = Running meter
Taking output = 12 m
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Skilled)
b) Material

RBR-SPST-22

1.00

day

day

1.25

day

0.57

12.00

c&d) Overheads & Contractors Profit


Cost for 12 m Modular strip/box seal joint = (a+b+c+d)
Rate per m = (a+b+c+d)/12
Note : 1. The installation shall be done by the manufacturer or his authorised representative
to the satisfaction of the Engineer.
2. The concreting for joining the expansion joint assembly with the deck has not been
included in this analysis as the same is catered in the quantities of RCC deck.
3. The anchoring bars of the expansion joint assembly shall be welded to the main
reinforcement of the deck.
Providing
anti-corrosive
treatment
to
HYSD
reinforcement with Fusion Bonded Epoxy Coating
(FBEC)
Unit = 1 MT
Taking output = 1 MT
To be taken as per the prevailing market rates.
Note : Contractors generally do not have expertise for this item . The job is therefore, got
done from specialised firms who have the expertise in the field of construction chemicals.
The prevailing rate in the market is required to be ascertained from the market and added in
the cost estimate. Detailed guidelines in this regard have been issued by MoRTH vide their
circular no. RW/NH-34041/44/91-S&R dated 21.3.2000.
Precast - pretensioned Girders
Providing, precasting, transportation and placing in
position precast pretensioned concrete girders as per
drawing and technical specifications in sections 1800 &
2300 MORTH
Unit = 1 cum

600

RBR-SPST
Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

Taking output = 1 cum


Grade of concrete - M40
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
Admixture @ 0.4 per cent of cement
HYSD steel .
HT strand with 5 per cent as wastage and extra length for
anchoring
LDO for steam curing
Add consumables such as binding wire, foam, packing
tape, shuttering oil, HDPE pipe for unbonding of strand, bolt
& nuts etc @ 1 per cent of material cost
b)
Labour
(i) Cutting, bending, making reinforcement cage,
placing in position, binding etc. complete
Taking quantity of steel 100 Kg/cum of concrete
including laps and wastage
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
(ii) Cable cutting and threading in position including
binding by insulation tape with HDPE pipes etc.,
prestessing and cutting of extra length of HT strand
after de-stressing.
Taking quantity of HT strand 60 Kg/cum
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
(iii) Erection and dismantling of shuttering
Taking shuttering area 10 sqm/cum of concrete
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
(iv) Concreting by Batching plant and stationary
concrete pump
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)

0.47

cum

0.45

cum

0.54

cum

0.36

Kg

1.88

0.10

0.06

Litre

37.00
1.00%

day

day

0.41

day

1.40

day

day

0.16

day

0.50

day

day

1.12

day

2.00

day

day

0.08

day

0.60

601

RBR-SPST
Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

(v) Steam curing and manual curing


Mate
Mazdoor (Unskilled)
(vi) Handling of precast girder, stacking in stockyard
and again loading in trailer
Mate
Mazdoor (Unskilled)
(vii) Placement of girders in position over pier caps
including placement of sand jacks, channel, leveling
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
c)
Machinery
i) At casting yard
Generator 100 KVA
Batching Plant @ 20 cum/hour
Transit Mixer 4 cum capacity
Concrete Pump stationary
Crane 35 tonne capacity
Trailer 30 tonne capacity
Loader
ii) For transportation and placement at site
Crane 35 tonne capacity
Trailer 30 tonne capacity for transporting to site.
(L - Lead in Kilometer)
Trailer 30 tonne capacity during placement.
Cost of formwork, steam curing arrangement, pretensioning
arrangement etc @ 5 per cent of cost material, labour and
machinery
d&e) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e)
24

RBR-SPST-24

day

day

0.36

day

day

0.26

day

day

0.07

day

0.24

hour

0.05

hour

0.05

hour

0.10

hour

0.05

hour

0.10

hour

0.10

hour

0.05

hour

0.15

t.km

2.5xL

hour

Providing and fixing Helical pipes in voided concrete


slabs as per Tech Specification in Section 1700 & 1800
MORTH.
Unit = 1 RM
Taking output = 1 RM
a) Material
metre
Helical pipes 600mm diameter
each
Tie rods 20mm diameter

0.15
5.00%

1.00
1.00

Consumables for sealing joints etc.@ 5%of cost of material

RBR-SPST-25

25

b)
Labour
day
Mate
day
Fitter
day
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per cum (a+b+c+d)
Crash Barriers
The rate analysis for rigid crash barrier in reinforced
cement concrete, semi-rigid crash barrier with metal beam
and flexible crash barrier with wire ropes have been made
and included in chapter-8 on Traffic and Transportation as
per Specification 800 MORTH.

0.05
0.21

602

RBR-SPST
Index-code
RBR-SPST-26

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

26

Painting on concrete surface


Providing and applying 2 coats of water based cement paint to
unplastered concrete surface after cleaning the surface of dirt,
dust, oil, grease, efflorescence and applying paint @ of 1 litre
for 2 sqm as per Tech Specification 800 MORTH.

27

RBR-SPST-27

28

RBR-SPST-28

29

RBR-SPST-29

30

RBR-SPST-30

31

RBR-SPST-31

32

RBR-SPST-32

Unit = sqm
Taking output = 10 sqm
a) Labour
Mate
Painter
Mazdoor (Skilled)
b) Material
Water based paint of approved quality for cement concrete
surface
c&d) Overheads & Contractors Profit
Cost for 10 sqm (a+b+c+d)
Rate per sqm (a+b+c+d)/10
Stone masonry in cement mortar 1:3 for parapet
complete as per drawing and technical specifications
Clauses 700 and 1208.4 MORD
I. Random rubble masonry
Rate same as in Chapter 12.4 III (i)
II. Coursed rubble masonry (1st sort)
Rate same as in Chapter 12.4 I (i)
Pointing with cement mortar (1:3) on brickwork in
parapet as per technical specifications Clauses 613.3
and 1208.4 MORD
Rate same as in Chapter 12.2
Plastering with cement mortar (1:3) 15 mm thick on
brickwork in parapet as per technical specifications
Clauses 613.4 and 1208.4 MORD
Rate same as in Chapter 12.3
Providing and laying parapet with PCC M 15 as per
drawing & technical specifications Clauses 800 and
1208.4 MORD
I. Nominal mix 1:2.5:5 (Hand mixing)
Rate same as in item 12.5 I (ii)
II. Nominal mix (1:2.5:5)
Rate same as in item 12.5 I (i)
Providing bituminous wearing coat comprising of 20
mm thick premix carpet with 5 mm thick seal coat Type
B for culverts as per drawing and technical
specifications Clauses 1206.2 and 500 MORD
i.Rate for wearing coat as per item No. 5.9 of Chapter 5
ii.Rate for seal coat Type B as per item No. 5.12 of Chapter
5

day

day

0.25

day

0.26

5.00

cum
cum

sqm

sqm

cum
cum

Note : This type of wearing coat may be adopted where a


cushion is provided over the culvert and the adjoining road
pavement is continued over it.
Providing bituminous wearing coat comprising of 50
mm thick bituminous macadam overlaid by 20 mm thick
premix carpet with 5 mm thick seal coat Type B as per
Tech Specification 1200 MORD
i. Rate for BM layer may be analysed as per item No 5.3 of cum
Chapter 5
ii. Rate of 20 mm premix carpet wearing course as per sqm
item No.5.9 of Chapter 5
iii. Rate of seal coat Type B as per item No. 5.12 of Chapter sqm
5

603

RBR-SPST
Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

33

Brickwork in arches in cement mortar 1:4 complete


including centering and shuttering excluding pointing
and plastering as per drawing and technical
specifications Clauses 606 and 1205.1 MORD
Unit = cum
(a) Material
Nos. 512.00
Brick 1st class (23 x 11 x 7 cms Traditional Bricks)
cum
0.20
Cement mortar (1:4) (Rate same as for item 11.5 II)
(b) Labour
day
Mate
day
1.80
Mazdoor (Unskilled)
day
0.89
Mason (1st Class)
(c) Add for centering and shuttering @ 110% of (a+b)
d&e) Overheads & Contractors Profit
Rate per cum = a+b+c+d+e
Note : 1. In case cement mortar 1:3 is used, rate as in item 11.5 I. will hold good.
2. Quantity of bricks for arches will be about 10 per cent more than that for ordinary
brickwork .
3. In case special arch bricks are used, the quantity of bricks per cum shall be taken as 580
Nos.
4. Rates for spandrel walls shall be taken same as for brickwork in substructure.
5. Rate for spandrel filling will depend on the filling material adopted

RBR-SPST-33

6. Compressive strength of Bricks shall be not less than 72 kg /cm 2


34

Coursed rubble stone masonry arch (Ist sort) in cement


mortar (1:4) complete including centering etc. complete
as per drawing and technical specifications Clauses
706 and 1205.1 MORD
Unit = cum
(a) Material
Stone for CR masonry 1st sort
Through and bond stone (7 Nos 0.24x0.24x0.39 =
0.16cum)mortar (Rate as in item 11.5 II)
Cement
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
(c) Add for centering and shuttering @ 100 % of (a+b)
d&e) Overheads & Contractors Profit
Rate per cum = a+b+c+d+e

RBR-SPST-34

cum

0.94

Nos.

0.16

cum

0.30

day

day

1.50

day

1.62

Note : 1. In case cement mortar 1:3 is used, rate for the same shall be as per item 11.5 I.

2. The addition for centering and sluttering at (c) above is for arch above 6 m span. For
lesser span length the addition shall be 80 per cent for span above 4 m length and 50 per
cent for spans less than 4 m.
Providing & Laying reinforced cement concrete arch
complete including centering and shuttering excluding
reinforcement as per drawings and technical
specifications Clauses 800, 900 and 1205.1 MORD

35

RBR-SPST-35

Unit = cum
RCC grade M20 (1:2.4) nominal mix
(a) Material
Cement
Coarse sand
20 mm aggregate
10 mm aggregate
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
Bhisti
(c) Machinery
Concrete mixer 0.4/0.28 cum capacity
(d) Add for cost of centering and shuttering @ 50 per
cent of (a+b) per sqm of surface of arch soffit

e&f) Overheads & Contractors Profit


Rate per cum = a+b+c+d+e+f
II RCC Grade M 25 (Design Mix)
(a) Material
Cement
Coarse sand
20 mm aggregate
10 mm aggregate
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
Bhisti

0.33

cum

0.45

cum

0.54

cum

0.36

day

day

0.20

day

2.15

day

hour

0.40

0.40

cum

0.45

cum

0.54

cum

0.36

day

day

0.20

day

2.15

day

604

RBR-SPST
Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

(c) Machinery
hour
Concrete mixer 0.4/0.28 cum capacity
(d) Add for cost of centering and shuttering @ 45 % of
cost of (a+b) per sqm of surface of arch soffit
e&f) Overheads & Contractors Profit
Rate per cum = a+b+c+d+e+f

0.40

Note : The additional cost of centering and shuttering @ 50 / 45 per cent of cost of material and labour
shall hold good for arch spans of 6 m and above. For lesser length of spans, the corresponding additional
cost can be taken as 40 per cent for spans above 4 m length and 30 per cent for spans less than 4m.
36

RBR-SPST-36

Providing steel R.S.Js/built-up steel sections including


cutting, welding/riveting, hoisting, fixing in position for
composite girders with shear connectors complete with
painting as per drawing and technical specifications
Clause 1205.6 MORD
A Steel section
Unit = quintal
Taking output for a typical 6 m long built up section comprising of of
R.S.Js, with connecting plates with shear connectors

(a) Material
R.S.Js 350 m x 200 mm @ 56.9 kg/m
6.0 m x 56.9 kg = 341.4 kg
Add 5 per cent for wastage = 17.87 kg
Total = 358.47 kg
25 cm wide x 12 mm thick plate
4x6x8.25 = 565.25 kg
Wastage 5 per cent = 28.3 kg
Total = 593.54 kg
Add shear connectors @ 10% = 59 kg
Total = 358.47 +593.5+59 = 1011 kg
Steel fabricated section
Rivets 22 mm dia = 240 Nos
Wastage @ 5 per cent = 12 Nos
Total = 252 Nos
Quantity of riveting @ 1.8 kg per 10 rivets = 45.35 kg

Add 5% of cost of material for painting one shop coat with red oxide
primer and three coats of synthetic enamel and consumables

10.11

0.454
5.00%

(b) Labour
day
6.00
Fitter
day
6.00
Blacksmith
day
12.00
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Cost for 10.11 q = a+b+c+d
Rate per quintal = (a+b+c+d)/10.11
Note : 1. In case of welded section, welding charges per cm length of welding shall
substitute cost of riveting
2. Shear connectors should always be welded to the top flange
3. The analysis of R.C.C. deck slab for the composite girder to be adopted from the item
13.1 of concrete superstructure
4. In the analysis of deck slab for composite girder superstructure, the component of
formwork for the same shall be 20 per cent of cost of materials, labour and machinery for
deck slab.
5. For spans upto 6 m with height above 5 m extra labour of mazdoor @ 3.0 days per
quintal may be added
6. For higher span lengths of different heights following additional labour for erection of steel
girders on pier/abutment caps may be provided:
Labour
day
Mate
day
0.06
Mazdoor (Skilled)
day
0.25
Mazdoor (Unskilled)
However, it is preferable to analyse the cost of erection of composite girder type of
superstructure for required span range and height range with a project - specific
methodology.
7. The provision of 10 per cent for shear connectors in the typical case is tentative. The
quantity shall be worked out as per design.
8. The cost of painting can also be analysed in detail in accordance with item 10.6 of
Chapter 10

General Note :
The provisions towards Mate is included in the provision towards unskilled Mazdoor.

605

RBR-PTWK

Andhra Pradesh Standard Data


I. Roads and Bridges

Chapter - 14
PROTECTION WORKS
Index-code

S. No

Description

RBR-PTWK-1

Unit Quantity
3

Mazdoor (Unskilled)
Overheads & Contractors Profit
Rate per cum

RBR-PTWK-2

Remarks
7

Providing and laying boulder apron for bed protection with stone
boulders of minimum size and weight as per Table 1300.1, no
fragment weighing less than 25 / 40 kg laid dry complete as per
drawing and technical specifications Clause 1301 MORD / 2503
MORTH

Unit = cum
(a) Material
cum
Stone boulder (25 kg / 40 Kg minimum)
cum
Stone spalls
(b) Labour
day
Mate
day
Mason 1st Class
day
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
Note : 1. Nominal excavation required for preparation of bed has
been taken into account while making provisions for labour.
2. Same data is hold good for stone boulders 25 kg / 40 kg only rate
may be substituted.
(i) Jeddy Stone Dry Packing for Aprons and Revetments
Section 1300 MORD
Unit = cum
(a) Material
cum
Jeddy Stone (Including small stone for wedging)
(b) Labour
day
Mason 1st Class
day
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
(ii) Removing old revetment and repacking with old stones
Unit = cum
cum
Rate as per Item 1(i) above for labour component only
Extra labour for removing old revetment including stacking

Rate Amount
Rs.
Rs.

1.00
0.20

0.35
0.79

1.20
0.35
1.05

1.00

day

0.20

cum
cum
kg

5.63
1.13
64.00

sqm

22.00

day
day
day

1.50
3.18

Providing and laying of boulder apron laid in wire crates with 4 mm


dia GI wire conforming to IS:280 and IS:4826 in 100 mm x 100 mm
mesh (woven diagonally) including 10 per cent extra for laps and
joints laid with stone boulders weighing not less than 25 / 40 kg
each as per drawing and technical specifications Clause 1301
MORD / 2503 MORTH

Unit = cum
Taking output = 3 m x 1.5 m x 1.25 m = 5.63 cum
(a) Material
Stone boulder (25 kg minimum) (MORTH - 40 kg)
Stone spalls
GI wires 4 mm dia @ 32 kg/10 sqm
(or)
4mm GI wire crates woven in mesh size of 100 mm x 100 mm.

(b) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)

608

RBR-PTWK
Index-code

S. No

Description

Unit Quantity
3

Rate Amount
Rs.
Rs.
5

Remarks
7

Add for labour for weaving the wire crates @ 2 per cent of cost
of GI wire
c&d) Overheads & Contractors Profit
Cost for 5.63 cum = a+b+c+d
Rate per cum = (a+b+c+d)/5.63
Note : 1. Nominal cost of trimming for preparation of bed has been included in the cost of
labour
2. The analysis will by & large hold good for gabions
3. Readymade woven wire crate rolls have been considered in the rate analysis. In case
readymade rolls are not available, GI wire 4mm dia. @ 32 kg per 10 sqm may be provided. In
that case 2 per cent of the cost of GI wire may be added for weaving the wire crates.
3

RBR-PTWK-3

Providing and laying of apron with cement concrete blocks


of size as per Table 1300.1 cast-in-situ and made with
nominal mix of M-15 grade cement concrete with a
minimum 250 kgs of cement per cum, as per IRC 21-2000,
as per drawing and technical specifications Clause 1301
MORD / 2503 MORTH
Unit = cum
(a) Concrete grade M 15
cum
(Rate as per item No 11.4 II (i)
kg
Deduct cost of cement
Add 2 per cent of cost to account for excavation for preparation
of bed, nominal surface reinforcement and filling of granular
material in recesses between blocks.
Rate per cum = (a)

1.00
25.00
2.00%

Note : The weight of CC Blocks shall be equivalent to the weight of stone


required to mean design velocity as per specifications.
4

RBR-PTWK-4

Single bamboo palasiding / walling of whole 2nd class


bamboo (Jati or Bethua) 75mm dia and closely packed &
driven including fitting fixing with half bamboo kamis
horizontally in three rows with cane or tying with wire
complete and struts 1.5 m apart longitudinally and
providing brush wood as per drawing and technical
specifications Clause 1302.5 MORD
A Driven at least 900 mm below ground and 1200 mm above
ground
Unit = Running metre
Taking Output = 3.00 metre
(a) Material
2nd Class Bamboo 65mm to 75mm dia, (1.2m to 3.0m)
Binding Wire
Brush Wood (LS Rs.10.00)
(b) Labour
Mate
Mazdoor (Unskilled)
(c) Sundries (LS Rs.5.00)
d&e) Overheads & Contractors Profit
Cost for 3 metre = a+b+c+d+e
Rate per metre = (a+b+c+d+e) / 3.00

nos.

15.00

kg

0.15

LS
day

day

1.04

LS

B Driven at least 900 mm below ground and 900 mm above ground on


average

(a) Material
2nd Class Bamboo 65 mm to 75 mm dia, (1.8 m-2.5 m) long

Binding Wire
Brush Wood (LS Rs.10.00)
(b) Labour
Mate
Mazdoor (Unskilled)
(c) Sundries
d&e) Overheads & Contractors Profit
Cost for 3 metre = a+b+c+d+e
Rate per metre = (a+b+c+d+e) / 3.00

nos.
kg

14.00
0.15

LS
day

day

1.04

LS

609

RBR-PTWK
Index-code

S. No

Description

RBR-PTWK-5

RBR-PTWK-6

RBR-PTWK-7

Providing and laying pitching on slopes laid over prepared


filter media as per drawing and technical specifications
Clause 1302 MORD / 2504 MORTH
I Stone/Boulder
Unit = cum
(a) Material
Stone boulder (25 kg minimum) /(MORTH - 40 kg)
Stone spalls of minimum 25 mm size
(b) Labour
Mate
Mason 1st Class
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per cum = (a+b+c+d)
II Cement concrete blocks of size as per Table 1300.2 cast in
cement concrete of grade M 15
(a) Concrete grade M 15
(Rate as per item No. 11.4 II (I) except that the size of
aggregate shall be 20 mm & down
Add 2 per cent of cost to account for surface reinforcement and
filling of granular material in recesses between blocks
Rate per cum = (a)
III Brick pitching set in cement mortar 1:4 (MORD)
Unit = cum
(a) Material
Bricks
Cement mortar 1:4 (Rate as in item 11.5 II)
(b) Labour
Mate
Mason 1st Class
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per cum = (a+b+c+d)

Unit Quantity
3

cum

1.00

cum

0.20

day

day

0.35

day

0.79

cum

1.00

Rate Amount
Rs.
Rs.
5

Remarks
7

2.00%

Nos.

500.00

cum

0.20

day

day

0.80

day

1.90

Providing and laying filter material underneath pitching in


slopes complete as per drawing and technical
specifications Clause 1302 MORD / 2504 MORTH
Unit = cum
(a) Material
Graded stone aggregate of required size - passing through cum
22.4 mm Sieve
(b) Labour
day
Mate
day
Mazdoor (Skilled)
day
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per cum = (a+b+c+d)
Note : Labour cost includes labour required for trimming of slope to
proper profile and preparation of bed.
(i) Quarry Rubbish Backing for Revetments as per APSS
Unit = cum
(a) Material
Quarry Rubbish
(b) Labour
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per cum = (a+b+c+d)

1.20

0.25
1.05

cum

1.1

day

0.7

610

RBR-PTWK
Index-code

S. No
1

RBR-PTWK-8

Description

2
(ii) Gravel Backing for Revetments as per APSS

Unit Quantity
3

Unit = cum
(a) Material
cum
Gravel
(b) Labour
day
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per cum = (a+b+c+d)
I Providing and laying flooring laid over cement concrete
bedding with M 10 grade complete as per drawing and
technical specification Clause 1303 MORD
i Rubble stone laid in cement mortar 1:3
Unit = cum
(a) Material
(i) Cement mortar (1:3) (For rate refer to item 6 (III) (i) of cum
Chapter 11
(ii) Add for cement concrete bedding (M 10) nominal mix) (For cum
rate refer to item 4 (I) (i) or (ii) of Chapter 11
Quantity shall be adopted as per design.
Add 1 per cent of cost to account for excavation for preparation
of bed
cum
(iii) Stone for rubble flooring 150 mm thick
cum
(iv) Stone spalls
(b) Labour
day
Mate
day
Mason 1st Class
day
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per cum = (a+b+c+d)
Note : Quantity of cement mortar is inclusive of mortar for laying and
filling of joints.
ii Providing and laying flooring laid over cement concrete
bedding with M 15 grade complete as per drawing and
technical specification Clause 2505 MORTH
Rubble stone laid in cement mortar 1:3
Unit = cum
(a) Material
(i) Cement mortar (1:3) (For rate refer to item 6 (III) (i) of cum
Chapter 11
b)
Add for cement concrete bedding (M15 Nominal mix) cum
vide 5 (I) (i) of Chapter 12 excluding OH & CP . Quantity
shall be adopted as per design (Assume Rubble stone
Flooring thickness 300mm and cement concrete bedding
thickness 100mm)
Add 1 per cent of cost to account for excavation for preparation
of bed
cum
(iii) Stone for rubble flooring 150 mm thick
cum
(iv) Stone spalls
(b) Labour
day
Mate
day
Mason 1st Class
day
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per cum = (a+b+c+d)
Note : Quantity of cement mortar is inclusive of mortar for laying and
filling of joints.

Rate Amount
Rs.
Rs.
5

Remarks
7

1.16
1.1

0.33

1.00
0.20
0.50
1.58

0.33
0.33

1.00
0.20
0.50
1.58

611

RBR-PTWK
Index-code

S. No

Description

1
2
II (i) Cement concrete blocks grade M 15 as per Specification

RBR-PTWK-9

RBR-PTWK-10

1300 MORD
Cement concrete blocks grade M 15 with 20 mm Graded metal
as per sizes in Table 1300.2
Add for Cement Concrete bedding (Quantity shall be as per
design)
Add 1 per cent of cost to account for excavation for preparation
of bed
Rate per cum
ii Cement concrete blocks grade M 15 as per Specification
2505 MORTH
Cement concrete blocks grade M 15 with 20 mm Graded metal
as per sizes in Table 1300.2
b)
Add for cement concrete bedding (M15 Nominal mix)
vide 5 (I) (i) of Chapter 12 excluding OH & CP. Quantity
shall be adopted as per design (Assume Cement Concrete
Blocks thickness 300mm and cement concrete bedding
thickness 100mm)
Add 1 per cent of cost to account for excavation for preparation
of bed
Rate per cum
III Brick on edge laid in cement mortar (1:3) for Flooring on
road sides 150 mm thick and each layer shall be bedded on
25 mm thick CM 1:5 & Joints filled with CM 1:3 as per
Technical Specifications Clause 1303 - MORD
Unit=cum
(a) Material
Bricks
Cement mortar (1:3)
Cement mortar bedding (1:5)
(b) Labour
Mate
Mason 1st Class
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per cum = (a+b+c+d)
Providing and laying of dry rubble flooring complete as per
drawings and technical specifications Clause 1303.3
MORD / 2506 MORTH
Unit = cum
(a) Material
Stone for rubble flooring 150 mm thick
Stone spalls
(b) Labour
Mate
Mason 1st Class
Mazdoor (Unskilled)
Add 1 per cent of (b) for trimming and preparation of base
c&d) Overheads & Contractors Profit
Rate per cum = (a+b+c+d)
Providing and laying curtain walls complete as per drawing
and technical specification Clause 1304 MORD / 2507
MORTH
Unit = cum
I Brick masonry in cement mortar (1:4)
(Rate same as in chapter 11
II (i) Coursed rubble masonry (2nd sort) in cement mortar (1:4)

Unit Quantity
3

cum

1.00

Rate Amount
Rs.
Rs.
5

Remarks
7

1.00%
1.00%

cum

1.00

cum

0.33

1.00%

Nos

500.00

cum

0.15

cum

0.25

day

day

0.80

day

1.90

cum

1.00

cum

0.20

day

day

0.50

day

1.60

cum

1.00

cum
(Rate same as in chapter 12
(ii) Coursed rubble masonry (1st sort) in cement mortar (1:3) cum
(Rate same as in chapter 12)

1.00
1.00

612

RBR-PTWK
Index-code

S. No
1

Description

2
III (i) Cement concrete grade M 10

Unit Quantity
3

cum
(Rate same as in chapter 11)
(ii) Cement concrete grade M 15
cum
(Rate same as in chapter 11)
Note : Other items like excavation for foundation, filling behind wall,
filter media, weep holes, etc. shall be added separately as per
approved design.
Construction of flexible apron 1 m thick comprising of
loose stone boulders weighing not less then 25 kg / 40 Kg
as per requirement beyond curtain wall as per Tech
Specification in Section 1300 MORD / 2507 MORTH.
Unit = cum
(a) Material
cum
Stone boulder (MORTH - 40 kg)
cum
Stone spalls
(b) Labour
day
Mate
day
Mason 1st Class
day
Mazdoor (Unskilled)

10

RBR-PTWK-11

Rate Amount
Rs.
Rs.
5

Remarks
7

1.00
1.00

1.00
0.20
0.25
1.05

Add: 1 per cent of cost of (a+b) for trimming and preparation of


bed
c&d) Overheads & Contractors Profit
Rate per cum = (a+b+c+d)
Construction of toe walls for protection of slopes as per
drawing and technical specifications Clause 1302.5 MORD

11

RBR-PTWK-12
I

Random rubble masonry in case of stone pitching laid with


cement mortar (1:5)
Unit = cum
(a) Material
cum
Stone for RR masonry
Nos.
Through and bond stone
(7 no x 0.24 x 0.24 m x 0.39 m = 0.16 cum)
cum
Cement mortar (Rate same as in item 12.1 III)
(b) Labour
day
Mate
day
Mason 1st Class
day
Mazdoor (Unskilled)
Add for scaffolding @ 5 per cent on (a+b)
c&d) Overheads & Contractors Profit
Rate per cum = (a+b+c+d)
Note : For height less than 3 m, dry rubble masonry can also be
used. In that case, the sub-item of cement mortar may be omitted in
the analysis.
II Brick masonry in cement mortar 1:4 in case of brick
pitching
Unit = cum
(a) Material
Nos.
Traditional Bricks (23 x 11 x 7 cms)
cum
Cement mortar 1:4 (Rate as per Sub analysis)
(b) Labour
day
Mate
day
Mason (1st Class)
day
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per cum = (a+b+c+d)

0.94
0.16
0.33
1.20
2.00

512.00
0.20
0.80
1.89

613

RBR-PTWK
Index-code

S. No

Description

Sub-analysis
Cement mortar 1:4 (1 cement : 4 sand)
Unit = cum
(a) Material
Cement
Sand
(b) Labour
Mate
Mazdoor (Unskilled)
Total material and labour = (a+b)

Unit Quantity
3

t
cum

0.36
1.05

Rate Amount
Rs.
Rs.
5

Remarks
7

day
day

0.20

0.220

III Cement concrete grade M 10 in case of concrete block pitching

Unit = cum
(i) P.C.C grade M 10 - Machine Mixed

Nominal mix 1:3:6


Unit = cum
(a) Material
Cement
Coarse sand
40 mm aggregate
20 mm aggregate
10 mm aggregate
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
(c) Machinery

RBR-PTWK-13

cum

0.45

cum

0.570

cum

0.280

cum

0.050

day

day

0.10

day

1.39

Mechanical concrete mixer 0.4/0.28 cum capacity fitted with water hour
measuring device and preferably also with load cell.

0.40

(d) Formwork @ 4% on cost of material, labour and


machinery (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = a+b+c+d+e+f
Toe protection Tech Specification 2504.4 MORTH

12

A toe wall for toe protection can either be in dry rubble masonry in case
of dry rubble pitching or pitching with stones in wire crates or it can be in
PCC M15 nominal mix if cement concrete block have been used for
pitching. Rates for toe wall can be adopted from respective clauses
depending upon approved design. The rate for excavation for
foundation, dry rubble masonry and PCC M15 have been analysed and
given in respective chapters.
13

Single bamboo spur and palisading of whole 2nd class bamboo


(jati or Bethua) 65 mm to 75 mm dia and closely packed & driven,
including fitting, fixing with half bamboo kamis horizontally in three
rows with cane or tying wire complete and struts 1500 mm apart
longitudinally and providing brush wood as per drawing and
technical specifications Clause 1302.5 MORD

RBR-PTWK-14

Driven at least 900 mm below ground and 1800 mm above ground on


average

Unit = Running metre


Taking output = 3.00 metre
(a) Material
2nd class bamboo (65 mm to 75 mm dia 3 m long)
Binding wire
Brush Wood (LS Rs.10.00)
(b) Labour
Mate
Mazdoor (Unskilled)
(c) Sundries
e&f) Overheads & Contractors Profit
Cost for 3 metre = a+b+c+d+e
Rate per metre = (a+b+c+d+e)/3

Nos
Kg.

18.00
0.15

LS

LS

day
day

1.04

LS

614

RBR-PTWK
Index-code

S. No
1

Description

2
ii Driven at least 900 mm below ground and 900 mm above ground on
average

Unit = Running metre


Taking output = 3.00 metre
(a) Material
2nd class bamboo (65 mm to 75 mm dia 2 m long)
Binding wire
Brush Wood (LS Rs.10.00)
(b) Labour
Mate
Mazdoor (Unskilled)
(c) Sundries
e&f) Overheads & Contractors Profit
Cost for 3 metre = a+b+c+d+e
Rate per metre = (a+b+c+d+e)/3
Single bamboo spur and palisading of whole 1st class
bamboo (Bholuka or Barua) 85 mm to 100 mm dia. Closely
packed & driven including fitting, fixing with half 2nd class
bamboo (jati or Bethua) horizontally in three rows with
cane or tying wire complete and struts 1500 mm apart
longitudinally and providing brush wood in the spur as per
drawings and technical specifications (MORD Suggestive)

14

RBR-PTWK-15

Unit Quantity
3

Nos

14.00

Kg.

0.15

LS

LS

Rate Amount
Rs.
Rs.
5

Remarks
7

day
day

1.04

LS

Driven at least 900 mm below ground and 1800 mm above


ground
Unit = Running metre
Taking output = 3.00 metre
(a) Material
Nos
1st class bamboo (85 mm - 100 mm dia) 3.0 long
Nos
2nd class bamboo (85-100 mm dia 3.0 long)
Kg.
Binding wire
LS
Brush Wood (LS Rs.10.00)
(b) Labour
day
Mate
day
Mazdoor (Unskilled)
LS
(c) Sundries
e&f) Overheads & Contractors Profit
Cost for 3 metre = a+b+c+d+e
Rate per metre = (a+b+c+d+e)/3
ii Driven at least 900 mm below ground and 900 mm above
ground on average
Unit = Running metre
Taking output = 3.00 metre
(a) Material
Nos
1st class bamboo (85-100 m dia, 2.0m long)
Nos
2nd class bamboo (85-100 mm dia, 2.0 m long)
Kg.
Binding wire
LS
Brush Wood (LS Rs.10.00)
(b) Labour
day
Mate
day
Mazdoor (Unskilled)
LS
(c) Sundries
e&f) Overheads & Contractors Profit
Cost for 3 metre = a+b+c+d+e
Rate per metre = (a+b+c+d+e)/3

15.00
2.00
0.15

1.25

10.00
1.50
0.15
LS
1.04

615

RBR-PTWK
Index-code

S. No
1

Description

2
iii Driven at least 600 mm below ground and 1200 mm above

ground on average.
Unit = Running metre
Taking output = 3.00 metre
(a) Material
1st class bamboo (85-100 m dia, 2.0m long)
2nd class bamboo (85-100 mm dia, 2 m long)
Binding wire
Brush Wood (LS Rs.10.00)
(b) Labour
Mate
Mazdoor (Unskilled)
(c) Sundries
e&f) Overheads & Contractors Profit
Cost for 3 metre = a+b+c+d+e
Rate per metre = (a+b+c+d+e)/3
Bamboo spur 'A' type with whole bamboo 85mm-100mm
dia, placed 230 mm centre to centre driven 900 mm below
ground and 1200 mm to 1500 mm above ground tied with
2nd class bamboo (jati or Bethua) on either side at 450 mm
apart horizontally with galvanised wire etc. complete as per
drawings and technical specifications (MORD Suggestive)

15

RBR-PTWK-16

Unit Quantity
3

Nos

9.00

Nos

1.50

Kg.

0.15

LS

LS

day

day

1.04

Rate Amount
Rs.
Rs.
5

Remarks
7

LS

2nd class bamboo (jati or Bethua) 65mm-75mm dia


Unit= Running metre
Taking output = 3.00 metre
(a) Material
2nd class bamboo ( 65mm-75mm dia, 2.5 m long)
2nd class bamboo ( 65mm-75mm dia, 3 m long)
Binding wire
(b) Labour
Mate
Mazdoor (Unskilled)
(c) Sundries
e&f) Overheads & Contractors Profit
Cost for 3 metre = a+b+c+d+e
Rate per metre = (a+b+c+d+e)/3

Nos

14.00

Nos

4.00

Kg.

0.75

day

day

1.04

LS

ii 1st class bamboo (Bholuka or Barua ) 85 mm to 100 mm dia

Unit = Running metre


Taking output = 3.00 metre
(a) Material
1st class bamboo (85-100 mm dia, 2.5 m long)
2nd class bamboo (85-100 mm dia, 2.5 m long)
Binding wire
Brush Wood (LS Rs.10.00)
(b) Labour
Mate
Mazdoor (Unskilled)
(c) Sundries
e&f) Overheads & Contractors Profit
Cost for 3 metre = a+b+c+d+e
Rate per metre = (a+b+c+d+e)/3

Nos

7.00

Nos

4.00

Kg.

1.00

LS
day

day

1.46

LS

616

RBR-PTWK
Index-code

S. No

Description

2
Providing 'A' type single spur with 1st class bamboo (Bholuka or
Barua) 85 mm to 100 mm dia. Driven closely placed 3m to 4m
above ground and 1200 mm to 1500 mm below ground tied with
cane or coir string, half 2nd class bamboo (jati or Bethua)
horizontally on both face placed not more than one metre apart
including whole bamboo struts inside one metre apart and 2 nos. of
purling at top and bottom fitted with vertical struts at 1500 mm
apart and filling with brushwood or jungle wood inside the spur
complete as per drawing and technical specifications (MORD
Suggestive)

16

RBR-PTWK-17

17

RBR-PTWK-18

18

RBR-PTWK-19

Unit= Running metre


Taking output = 3.00 metre
(a) Material
1st class bamboo (85-100 mm dia, 4.5-5.5 m long)
2nd class bamboo (85-100 mm dia, 3.0 m long)
Binding wire
Brush wood (LS Rs.10.00)
(b) Labour
Mate
Mazdoor (Unskilled)
(c) Sundries
e&f) Overheads & Contractors Profit
Cost for 3 metre = a+b+c+d+e
Rate per metre = (a+b+c+d+e)/3
Providing close bamboo toe walling consisting of 65mm to
75mm dia bamboos of length ranging from 1.2 m to 3m
driven at 150 mm centre to centre and provided with three
horizontal split bamboo runner fixed with nails. All
bamboos to be duly protected by coal tar painting.
Unit = Running Metre
Taking output = 10.00 running metre
(a) Material

Unit Quantity
3

Nos
Nos

15.00
6.00

Kg.

2.00

Rate Amount
Rs.
Rs.
5

Remarks
7

LS
day

day

1.56

LS

2nd class bamboo (65mm-75mm dia and average 2.1 m length)

Nos

2nd class bamboo (65mm-75mm dia and 3 m length)


Coal tar
(b) Labour
Mate
Mazdoor (Unskilled)
(c) Sundries
e&f) Overheads & Contractors Profit
Cost for 3 metre = a+b+c+d+e
Rate per metre = (a+b+c+d+e)/3
Double timber spur with two rows at 800 mm c/c apart of
1st
class
local
wood
piles
with
timber
of
Azar/Nahar/Nageswar / Zarul wood 150 mm to 200 mm dia
driven 2000 mm minimum below ground and 3600 mm
above ground average placed at 800 mm belts, bracings
etc. of 100 mm x 75 mm size 1st class local wood
longitudinally & crosswise at ends fitted with 10 mm dia
bolts and nuts etc. including coal tarring of timber
members and cost of necessary bamboo staging etc. as
directed by the Engineer as per drawing and technical
specifications (MORD Suggestive)
Unit =RM
Taking output = 4.00 RM
(a) Material
1st class local wood piles 150-200 mm dia, 6m long
1st class local wood (100 mm x 75 mm) for collar, bracing and
belt
Nuts and Bolts

Nos

67.00
6.00

kg

10.00

day

day

1.56

LS

Nos

68.00

cum

0.404

Kg

10.00

617

RBR-PTWK
Index-code

S. No

Description

19

RBR-PTWK-20

1st Class Bamboo


2nd class bamboo
Coir rope
Coal tar
(b) Labour
Carpenter 1st Class
Mate
Mazdoor (Unskilled)
(c) Sundries
e&f) Overheads & Contractors Profit
Cost for 4 Rm = a+b+c+d+e
Rate per metre = (a+b+c+d+e)/4
Supplying and filling up hollows of the timber spur to an
average height of 3600 mm above ground with jungle wood
branches as per drawing and technical specifications as
directed by the Engineer. (MORD Suggestive)
Unit = RM
Taking output = 20.00 RM
(a) Labour
Mazdoor (Unskilled)
(b) Sundries
c&d) Overheads & Contractors Profit
Cost for 20 RM = (a+b+c+d)
Rate per metre = (a+b+c+d)/20

RBR-PTWK-21

20

Unit Quantity
3
Nos

4
5.00

Nos

5.00

Rate Amount
Rs.
Rs.
5

Remarks
7

LS
LS
Nos

1.20

Nos

Nos

31.20

LS

day

5.00

LS

Geotextile Filter
Laying of a geotextile filter between pitching and embankment slopes on
which pitching is laid to prevent escape of the embankment material
through the voids of the stone pitching/cement concrete blocks as well
as to allow free movement of water without creating any uplift head on
the pitching as per Tech Specifications in Section 700 & 2504 MORTH

RBR-PTWK-21

21

Unit = sqm
Taking output = 10 sqm.
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Skilled)
b)
Material
Permeable synthetic geotextile including 5 per cent for overlap
and wastage
c&d) Overheads & Contractors Profit
Cost for 10 sqm = a+b+c+d
Rate per sqm = (a+b+c+d)/10
Gabian Structure for Retaining Earth

day

day

0.30

day

0.12

sqm

11.00

Providing and construction of a gabian structure for retaining earth with


segments of wire crates of size 7 m x 3 m x 0.6 m each divided into 1.5
m compartments by cross netting, made from 4 mm galvanised steel
wire @ 32 kg per 10 sqm having minimum tensile strength of 300 Mpa
conforming to IS:280 and galvanizing coating conforming to IS:4826,
woven into mesh with double twist, mesh size not exceeding 100 x 100
mm, filled with boulders with least dimension of 200 mm, all loose ends
to be tied with 4 mm galvanised steel wire as per Tech Specifications
2503.3 MORTH

Unit = cum
Taking output = 7 x 3 x 0.6 = 12.60 cum
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Skilled)

day

day

5.00

day

2.28

618

RBR-PTWK
Index-code

S. No

Description

b)

Unit Quantity
3

Rate Amount
Rs.
Rs.
5

Remarks
7

Material

Galvanised steel wire crates of mesh size 100 mm x 100 mm woven sqm
with 4mm dia. GI wire in rolls of required size.

61.00

cum

12.60

cum

2.52

Stone boulders with least dimension of 200 mm


Stone spalls of minimum size 25 mm
c&d) Overheads & Contractors Profit
Cost for 12.60 cum (a+b+c+d)
Rate per cum (a+b+c+d)/12.60

Note : Readymade woven wire crate rolls have been considered in the rate
analysis. In case readymade rolls are not available, GI wire 4mm dia. @ 32 kg
per 10 sqm may be provided. In that case 2 per cent of the cost of GI wire
may be added for weaving the wire crates.

RBR-PTWK-22

22

Gabian Structure for Erosion Control, River Training Works


and Protection works
Providing and constructing gabian structures for erosion
control, river training works and protection works with wire
crates of size 2 m x 1 m x 0.3 m each divided into 1m
compartments by cross netting, made from 4 mm galvanised
steel wire @ 32 kg per 10 sqm having minimum tensile
strength of 300 Mpa conforming to IS:280 and galvanizing
coating conforming to IS:4826, woven into mesh with double
twist, mesh size not exceeding 100 mm x 100 mm, filled with
boulders with least dimension of 200 mm, all loose ends to be
securely tied with 4 mm galvanised steel wire as per Tech
Specifications 2503.3 MORTH.
Unit = cum
Taking output = 2 x 1 x 0.3 x 10 Nos. = 6.00 cum
a) Labour
day
Mate
day
2.50
Mazdoor (Unskilled)
day
1.14
Mazdoor (Skilled)
b)
Material
65.00
Galvanised steel wire crates of mesh size 100 mm x 100 mm sqm
woven with 4mm dia. GI wire in rolls of required size to cover
6.00 cum.
cum
6.00
Stone boulders with least dimension of 200 mm
cum
1.20
Stone spalls of minimum size 25 mm
c&d) Overheads & Contractors Profit
Cost for 6.00 cum (a+b+c+d)
Rate per cum (a+b+c+d)/6.00
Note : Readymade woven wire crate rolls have been considered in the rate analysis. In case
readymade rolls are not available, GI wire 4mm dia. @ 32 kg per 10 sqm may be provided. In
that case 2 per cent of the cost of GI wire may be added for weaving the wire crates.

General Note :
The provisions towards Mate is included in the provision towards unskilled Mazdoor.

619

RBR-MTRD

Andhra Pradesh Standard Data


I. Roads and Bridges

Chapter - 15
MAINTENANCE OF ROADS

Index-code

RBR-MTRD-1

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

Restoration of Rain Cuts


Restoration of rain cuts with soil, moorum gravel or a mixture
of these, clearing the loose soil, benching for 300mm width
laying fresh material in layers not exceeding 250 mm and
compaction with plate compactor or power rammer to restore
the original alignment, level and slopes as per drawings and
technical specifications Clause 1902 MORD / 3002 MORTH
A Manual Means

Unit = cum
Taking output = 10 cum
(a) Labour
day
Mate
day
Mazdoor (Unskilled)
(b) Machinery
hour
Plate compactor
(c) Materials
cum
Compensation for earth Taken from private land
d&e) Overheads & Contractors Profit
Cost for 10 cum = a+b+c+d
Rate per cum = a+b+c+d/10
B Mechanical Means including conveyance of earth from
1000 M load
Unit = cum
Taking output = 50 cum
(a) Labour
day
Mate
day
Mazdoor (Unskilled)
(b) Machinery
hour
Hydraulic Excavator 0.9 cum bucket capacity @ 60 cum/h

RBR-MTRD-2

OR
hour
Hydraulic Excavator 1 cum bucket capacity @ 60 cum/h
hour
Tipper 5.5 cum, 10 t capacity
hour
Plate compactor 3.5 cum / hour capacity
(c) Materials
cum
Compensation for earth Taken from private land
d&e) Overheads & Contractors Profit
Cost for 50 cum = a+b+c+d+e
Rate per cum a+b+c+d+e/50
Note : Only 75% of fresh material has been provided as 25% can be
retrieved from site from earth i.e. flown down the slop in the form of
slurry and deposited at the foot of rain cuts.
Maintenance of Earthen shoulder (filling with fresh
selected soil)
(I) Making up loss of material/irregularities on shoulders to the
design level by adding fresh approved selected soil and
compacting it with appropriate equipment at OMC upto a lead
of 1000 m as per technical specification Clause 1903 MORD /
3003 MORTH
Unit = sqm
Taking output = 100 sqm
Assuming average thickness of filling to be 150 mm
Quality of fresh material = 15 cum
(a) Labour
day
Mate
day
Mazdoor (Unskilled)

6.240
3.000
7.500

10.400
0.830
0.650
2.270
15.000
37.500

4.680

621

RBR-MTRD
Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

hour

0.250

hour
hour

0.680
4.000

cum

15.000

day
day

2.600

hour

4.000

(b) Machinery
Hydraulic Excavator 0.9 cum / 1.00 cum bucket capacity @
60 cum/h
Tipper 5.5 cum
Plate compactor @ 25 sqm per hour
(c) Materials
Compensation of earth
d&e) Overheads & Contractors Profit
Cost for 100 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/100
(II) Maintenance of Earthen shoulder (stripping of excess
soil)
Stripping excess soil from the shoulder surface to achieve the
approved level and compacting with plate compactor at OMC
as per drawings and Technical Specification Clause 1903
MORD / 3003 MORTH
Unit = sqm
Taking output = 100 sqm
Assuming height of stripping as 75 mm
Quantity of earth cutting involved = 7.5 cum
(a) Labour
Mate
Mazdoor (Unskilled)
(b) Machinery
Plate compactor @ 25 sqm per hour
c&d) Overheads & Contractors Profit
Cost for 100 sqm = a+b+c+d
Rate per sqm = a+b+c+d/100

RBR-MTRD-3

Amount
Rs.

Remarks

Note : Earth stripped from earthen shoulders to be used as


shoulders or dumped on the side slopes locally for disposal.
Maintenance of bituminous surface road
(i) Repair to pot holes by removal of failed material, trimming the
sides to vertical and leveling the bottom, cleaning the same with
compressed air or any appropriate method filled with 75mm B.M,
applying bitumen emulsion prime coat at the bottom and
bitumen emulsion tack coat on sides and on bottom as per
technical specifications Clauses 502 and 503 and 1904 MORD.

Unit = cum
Taking output = 187.5x0.075 = 14.06 cum = (30.94 Tonne)
(5% area of one km)
(a) Labour
day
Mate
day
Mazdoor (Unskilled)
(b) Machinery
hour
Jack hammer 25 kg with tractor
hour
Compressor 210 cfm with tractor
hour
Emulsion pressure distributor
hour
Mixall 6/10 t capacity
hour
Three wheeled 80-100 kN Static Roller
(c) Materials
Primer with bitumen emulsion @ 9 kg/10 sqm 187.5x9 = Tonne
168.75 kg.
Tack coat with bitumen emulsion @ 3.0 kg/ 10 sqm
Bottom = 187.5
Tonne
Sides = 28.27
Total = 215.77
Bitumen for BM @ 3.5% by weight of mix = 30.94 x 3.5 / 100 = 1.082

Weight of mix (BM) 14.06 cum = (30.94 tonne)


Weight of Bitumen = 1.082
Weight of aggregate 30.94 -1.082 = 29.86
Taking density of aggregate 1.5 t per cum
Volume of aggregate 29.86 / 1.5 = 19.90 cum
Grading (1) (40 mm nominal size)
37.5 - 25 mm 15%
25 - 10 mm 45%
10 - 5 mm 25%
5 mm and below 15%
d&e) Overheads & Contractors Profit
Cost of 14.06 cum = a+b+c+d+e
Rate per cum = a+b+c+d+e/14.06

20.800
4.000
2.000
4.000
4.000
4.000
0.168

0.064

Tonne

1.082

cum
cum
cum
cum

2.985
8.955
4.975
2.985

(ii) Patch repair on already filled pot holes with 75 mm BM

with 20 mm premix carpet and seal coat Type B as per


drawings and technical specification Clause 1904.2
MORD
Unit = sqm

622

RBR-MTRD
Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

day
day

16.640

hour
hour
hour

2.000
2.000
4.000

tonne

0.292

tonne

0.040

tonne

0.136

cum

5.400

cum

1.200

day
day

20.800

hour
hour
hour
hour

2.000
2.000
2.000
4.000

t
t

0.064
0.292

0.136

cum

5.400

cum

1.200

day
day

16.640

hour
hour
hour
hour

2.500
2.000
2.000
4.000

tonne

0.060

tonn

0.430

tonn
Emulsion for seal coat @ 10 kg per 10 sqm
= 200 x 10 / 10 = 200 kg
Crushed stone aggregate 13.2 mm to 5.6 mm @ 0.27 cum per cum
10 sqm= 200x0.27/10=5.4cum

0.200

Taking output = 200 sqm


(a) Labour
Mate
Mazdoor (Unskilled)
(b) Machinery
Mixall 6/10 tonne
Bitumen pressure distributor
Three wheeled 80-100 kN Static Roller
(c) Materials
Bitumen for pre-mix carpet @ 14.60 kg/10 sqm 200x14.60/10
=292 kg
Bitumen for tack coat @2kg per 10sqm 200 x 2 / 10 =40kg
Bitumen for seal coat @ 6.8 kg per 10 sqm
200 x 6.8stone
/ 10 =aggregate
136 kg 13.2 mm to 5.6 mm @ 0.27 cum per
Crushed
10 sqm= 200x0.27/10=5.4cum
Crushed sand passing 2.36 mm sieve and retained on 180
micron sieve @ 0.06 cum per 10 sqm
200 x 0.06 / 10 = 1.20 cum
d&e) Overheads & Contractors Profit
Cost of 200 sqm = a+b+c+d+e
Rate/sqm = a+b+c+d+e/200
(iii) Repair to pot holes and removal of loose material,
trimming of sides, cleaning of surface by providing tack
coat, 20 mm thick pre-mix carpet and seal coat type B
specification Clause 1904.2 MORD
Unit = sqm
Taking output = 200 sqm
(a) Labour
Mate
Mazdoor (Unskilled)
(b) Machinery
Air compressor 210 cfm with tractor
Bitumen pressure distributor
Mixall 6/10t capacity
Three wheeled 80-100 kN Static Roller
(c) Materials
Bitumen for tack coat @ 3kg per 10 sqm 200 x 3 / 10 = 60 kg

Bitumen for pre-mix carpet @ 14.60 kg per 10 sqm = 200 x


14.6 / 10 = 292 kg
Bitumen for seal coat @ 6.8 kg per 10 sqm
= 200 x 6.8 / 10 = 136 kg
Crushed stone aggregate 13.2 mm to 5.6 mm @ 0.27 cum per
10 sqm= 200x0.27/10=5.4cum
Crushed sand passing 2.36 mm sieve and retained on 180
micron sieve @ 0.06 cum per 10 sqm
200 x 0.06 / 10 = 1.20 cum
d&e) Overheads & Contractors Profit
Cost for 200 sqm = a+b+c+d+e
Rate per sqm = a+b+c+d+e/200
(iv) Repair to pot holes and removal of loose material, trimming of
sides, cleaning of surface by providing tack coat with bitumen
emulsion, 20 mm thick pre-mix carpet using cationic bitumen
emulsion and seal coat type B with bitumen emulsion as per
Technical Specification Clauses 1904.2, 503 and 508.2
MORD
Unit = sqm
Taking output = 200 sqm
(a) Labour
Mate
Mazdoor (Unskilled)
(b) Machinery
Concrete mixer 0.4 / 0.28 cum capacity
Air compressor 210 CFM with tractor
Emulsion pressure distributor
Three wheeled 80-100 kN Static Roller
(c) Materials
Emulsion for tack coat @ 3 kg per 10 sqm
200 x 3 / 10 = 60 kg
Emulsion for premix carpet @ 21.50 kg per 10 sqm
200 x 21.50 / 10 = 430 kg

Amount
Rs.

Remarks

5.400

623

RBR-MTRD
Index-code

S. No
1

Description

Unit

Quantity

4
1.200

Crushed sand passing 2.36 mm sieve and retained on 180 cum


micron sieve @ 0.06 cum per 10 sqm = 200 x 0.06 / 10 = 1.20

Rate
Rs.

Amount
Rs.

Remarks

d&e) Overheads & Contractors Profit


Cost for 200 sqm = a+b+c+d+e
Rate per sqm = a+b+c+d+e/200
RBR-MTRD-4

RBR-MTRD-5

Filling Pot-holes and Patch Repairs with open-Graded


Premix surfacing, 20mm.
Removal of all failed material, trimming of completed
excavation to provide firm vertical faces, cleaning of surface,
painting of tack coat on the sides and base of excavation as
per clause 503, back filling the pot holes with hot bituminous
material as per clause 511, compacting, trimming and
finishing the surface to form a smooth continuous surface, all
as per clause 3004.2 MORTH
Unit = Sqm
Taking out put = 10250 sqm (205 cum)(405 tonne)
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor skilled
b)
Machinery
Air compressor 250 cfm
HMP 100-110 TPH Capacity
Tipper 10 tonnes capacity
Smooth wheeled roller 8-10 tonnes
c)
Material
Crushed stone aggregates nominal size 13.2mm
Crushed stone aggregates nominal size 11.2mm
Bitumen 80/100
Bitumen emulsion for tack coat including vertical sides of pot
hole.
d&e) Overheads & Contractors Profit
Cost for 10250 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/10250
Filling Pot-holes and Patch Repairs with Bituminous
concrete, 40mm.

Day
Day
Day

90.000
7.760

hour
hour
hour
hour

6.000
6.000
45.000
12.000

cum
cum
tonne

184.500
92.250
14.970

tonne

2.460

Day
Day
Day

70.000
5.920

hour
hour
hour
hour

6.000
6.000
45.000
12.000

tonne

22.500

tonne

1.180

cum
cum
cum

99.750
65.550
114.000

cum
cum
cum
tonne

85.500
71.250
122.550
9.000

Removal of all failed material, trimming of completed excavation to


provide firm vertical faces, cleaning of surface, painting of tack coat
on the sides and base of excavation as per clause 503, back filling
the pot holes with hot bituminous material as per clause 504,
compacting, trimming and finishing the surface to form a smooth
continuous surface, all as per clause 3004.2 MORTH

Unit = Sqm
Taking out put = 4900 sqm (196 cum)(450 Tonnes)
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor skilled
b)
Machinery
Air compressor 250 cfm
HMP 100-110 TPH Capacity
Tipper 10 tonnes capacity
Smooth wheeled roller 8-10 tonnes
c)
Material
I) Bitumen
ii) Bitumen emulsion for tack coat .
iii) Aggregates
Grading I - 19mm(Nominal size)
20-10mm 35 per cent
10-5 mm 23 per cent
5mm and below40 per cent
Add 5 per cent for wastage
or
Grading-II 13mm (Nominal size)
13.2-10 mm 30 per cent
10-5 mm 25 per cent
5 mm and Below43 per cent
Filler 2 per cent (Cement)
Add 5 per cent for wastage
Any one of the above alternatives of aggregate i.e. 19mm or 13mm
nominal size may be adopted as per approved design.
(i)

for grading I Material


d&e) Overheads & Contractors Profit
Cost for 4900 sqm = a+b+c+d+e

624

RBR-MTRD
Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

Rate per sqm = (a+b+c+d+e)/4900


(ii) for grading II Material
d&e) Overheads & Contractors Profit
Cost for 4900 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/4900

RBR-MTRD-6

RBR-MTRD-7

RBR-MTRD-8

Note : For detailed working of quantities of aggregates, refer item 5.8


of chapter 5
Crack Filling
Filling of crack using slow - curing bitumen emulsion and
applying crusher dust in case cracks are wider than 3mm as
per Tech. specification 3004.3.3 MORTH
Unit = Running Meter
Taking out put = 500m
a) Labour
day
Mate
day
Mazdoor (Unskilled)
b)
Material
Kg
Slow-curing bitumen emulsion
cum
Stone crusher dust
c&d) Overheads & Contractors Profit
Cost for 500sqm = a+b+c+d
Rate per meter = (a+b+c+d+e)/500
Dusting

A
B

(C)

(D)

Applying crusher dust to areas of road where bleeding of


excess bitumen has occurred as per Tech. specification
3004.4 MORTH.
Unit = Sqm
Taking output = 3500 sqm
a) Labour
Mate
Mazdoor (Unskilled)
b)
Material
Stone crusher dust finer than 3mm with not more than 10
per cent passing 0.075 sieve.
c&d) Overheads & Contractors Profit
Cost for 3500sqm = a+b+c+d
Rate per meter = (a+b+c+d)/3500
Fog Seal as per Specification 3004.3.2 MORTH
Data as in Chapter 5
Crack Prevention courses as per Specification 3004.3.4
MORTH
(i) Stress Absorbing Membrane (SAM) crack width less than 6
mm
(ii) Stress Absorbing Membrane (SAM) with crack width 6 mm
to 9 mm
(iii) Stress Absorbing Membrane (SAM) crack width above 9
mm and cracked area above 50 per cent
(iv) Bitumen Impregnated Geotextile
Data as in Chapter 5
Slurry Seal
(i) 5 mm thickness
(ii) 3 mm thickness
(iii) 1.5 mm thickness
Data as in Chapter 5
Surface Dressing for maintenance works.
(i) 19 mm nominal chipping size
(ii) 13 mm nominal size chipping
Data as in Chapter 5

RBR-MTRD-9

Repair of Joint Grooves with Epoxy Mortar


Repair of spalled joint grooves of contraction joints,
longitudinal joints and expansion joints in concrete pavements
using epoxy mortar or epoxy concrete as per Tech.
specification 3005.1 MORTH
Unit = running metre
Taking output = 10 metres
a) Labour
Mate
Mazdoor (Unskilled)
Chiseller
b)
Material
Epoxy primer
Epoxy compound with accessories for preparing epoxy mortar
c)
Machinery
Air compressor 250 cfm for cleaning

1.040
33.000
0.020

day
day

2.080

cum

6.250

sqm

sqm
sqm
sqm
sqm

sqm
sqm
sqm

sqm
sqm

day
day
day

0.540
0.500

kg
kg

2.500
10.000

hour

0.050

625

RBR-MTRD
Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

Amount
Rs.

Remarks

d&e) Overheads & Contractors Profit


Cost for 10 metres = a+b+c+d+e
Rate per metre = (a+b+c+d+e)/10
RBR-MTRD-10

RBR-MTRD-11

10

11

Repair of old Joints Sealant


Removal of existing sealant and re sealing of contraction,
longitudinal or expansion joints in concrete pavement with
fresh sealant material as per Tech. specification 3005.2
MORTH
Unit = running metre
Taking output = 10 metres
a) Labour
day
Mate
day
Mazdoor (Unskilled)
b)
Material
kg
Primer
kg
Sealant
c)
Machinery
hour
Air compressor 250 cfm for cleaning
d&e) Overheads & Contractors Profit
Cost for 10 metres = a+b+c+d+e
Rate per metre = (a+b+c+d+e)/10
Hill Side Drain Clearance as per Specification 3000
MORTH
Removal of earth from the choked hill side drain and
disposing it on the valley side manually
Unit = running metre
Taking output = 10 metres
Assuming muck causing choking of drain to be 0.2 cum per
metre, quantity of earth to be removed for 10 metres = 2 cum
a) Labour
Mate
Mazdoor (Unskilled)
b&c) Overheads & Contractors Profit
Cost for 10 metres = a+b+c
Rate per metre = (a+b+c)/10

RBR-MTRD-12

12

0.540
0.250
1.000
0.050

day
day

1.080

day
day

1.040

hour

1.670

Land Slide Clearance in soil


Clearance of land slides in soil and ordinary rock by a bulldozer D 80 A-12, 180 HP and disposal of the same on the
valley side as per Tech. specification 3000 MORTH
Unit = cum
Taking output = 100 cum
a) Labour
Mate
Mazdoor (Unskilled)
b)
Machinery
Dozer 180 HP @ 60 cum per hour
c&d) Overheads & Contractors Profit
Cost for 100 cum = a+b+c+d
Rate per cum = (a+b+c+d)/100

Note : Land Slide clearance involves pushing of loose earth slided on the road surface from hill face on the
valley side. Since no cutting of original ground is involved, the output of dozer has been taken as 60 cum
per hour for soil, ordinary rock and blasted hard rock. However, if there are objection to disposing of earth
on valley side, additional resources for its disposal shall be considered as per site conditions.

RBR-MTRD-13

13

Landslide Clearance in Hard Rock Requiring Blasting


Clearing of land slide in hard rock requiring blasting for 50 per
cent of the boulders and disposal of the same on the valley
side as per Tech. specification 3000 MORTH.
Unit = cum
Taking output = 100 cum
a) Labour
Mate
Mazdoor (Unskilled)
Driller

day
day
day

1.590
0.750

626

RBR-MTRD
Index-code

S. No
1

RBR-MTRD-14

14

Description

Unit

Quantity

4
0.070

day
Blaster
b)
Machinery
hour
Dozer D 80 A-12,180 HP @ 60 cum per hour
hour
Air compressor 250 cfm with two jack hammer
c)
Materials
kg
Gelatine 80 per cent @ 35 kg per 100 cum
Electric Detonators @ 1 Detonator for 2 Gelatine sticks of 125 each
gms each
c&d) Overheads & Contractors Profit
Cost for 100 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/100
Note : Credit for the rock if found acceptable as construction material
shall be afforded
Maintenance of Gravel Road
Maintenance of gravel road including making up the loss of
profile, rectifying corrugated surface, filling up of depressions,
pot holes and erosion gullies by adding fresh material and
compacting it with appropriate equipment or to strip excess
of material from the road surface as per drawings and
technical specification Clause 1905 MORD

For grading I Material compacting with Smooth Wheel


Roller 80-100 kN
Unit = sqm
Taking out put @ 5% of the area in one km. as affected:
= 1000 x 3.75x0.05 / 100 = 187.5 Sqm
Quantity = 187.5 x 0.15 = 28.12 cum
cum
a) Rate as per item 4.1 of Chapter 4
b) Add 50% for extra efforts involved as maintenance is to be
done in small reaches

RBR-MTRD-15

15

16

Amount
Rs.

Remarks

1.670
2.500
17.500
70.000

28.120
50%

Cost of 187.5 Sqm = a+b


Rate per sqm = a+b/187.5
Note : The cost of 25% retrieved material may be deducted from
rates.
Maintenance of WBM Road
Maintenance of WBM road including filling up of pot holes,
ruts and rectifying corrugated surface, damaged edges and
raveling as per technical specification Clause 1906 MORD.
For grading III Material compacting with Smooth Wheel
Roller 80-100 kN
Unit = Sqm
Output - Taking affected area @ 5% in 1 km
= 1000 x 187.5
3.75 xx0.05
= 187.5
sqm
Quantity
0.075
= 14.06
cum
cum
a) Rate as per item 4.7(3) of Chapter 4
b) Add 50% for extra efforts involved as maintenance is to be
done in small reaches

RBR-MTRD-16

Rate
Rs.

14.060
50%

Cost of 187.5 Sqm = a+b


Rate of per sqm a+b/187.5
Note : The cost of 25% retrieved material may be deducted from rates.
Maintenance of Drains
The maintenance of drains include erosion, repair, clearing,
cleaning, reshaping, regarding, deepening of side drains as
well as catch water drains as per technical specification
Clause 1907 MORD.
Unit - Per Metre
Taking output one km = 1000 metre
a) Labour
day
Mate
day
8.320
Mazdoor (Unskilled)
b&c) Overheads & Contractors Profit
Cost for 1000 metre = a+b+c
Rate per Metre = a+b+c/1000

627

RBR-MTRD
Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

day
day
day

1.100
1.400

L.S

LS

day
day
day

4.200
1.000

L.S

LS

day
day
day

2.400
4.000

LS

LS

day
day
day

2.090
0.125

LS

LS

RBR-MTRD-17

17

Amount
Rs.

Remarks

Maintenance of Culverts
(I) Maintenance of Hume pipe Culvert by way of Clearing, Cleaning,
Erosion repair, repairs to cracks, parapet wall and protection work as
per drawing and technical specification Clause 1908 MORD.

Unit = One No. Hume pipe (1000 mm dia)


Taking output = One No.H.P. Culvert
a) Labour
Mate
Mazdoor (Unskilled)
Mason 2nd Class
b)
Material
Cement, Sand, Brick, Boulder etc.
c&d) Overheads & Contractors Profit
Cost for one No. Hume pipe culvert = a+b+c+d
Rate per hume pipe Culvert = a+b+c+d
(II) Maintenance of Culverts Slab type
Maintenance of Slab type Culverts by way of clearing, Cleaning,
Erosion repair, repairs to cracks, parapet walls and Protection works
as per drawing and technical specification Clause 1908 MORD

RBR-MTRD-18

18

Unit = One No. Culvert (2 m span)


Taking output = one No. Slab Culvert
a) Labour
Mate
Mazdoor (Unskilled)
Mason 2nd Class
b)
Material
Cement, Sand, Brick, Boulder etc.
c&d) Overheads & Contractors Profit
Cost for One Slab Culverts =a+b+c+d
Rate per Culvert = a+b+c+d
Maintenance of Causeway
Maintenance of Causeway by way of minor Surface repairs, replacing
Guide Posts, repair of flood gauges, removal of debris, providing
boulders and protection work and painting as per technical
specification Clause 1909 MORD

RBR-MTRD-19

19

Unit = One metre


Taking output = 50 metre causeway
a) Labour
Mate
Mazdoor (Unskilled)
Mason 1st Class/Painter 1st Class
b)
Material
Supply of cement, paint, sand, aggregate, boulder etc.
(LS Rs.350.00)
c&d) Overheads & Contractors Profit
Cost for 50 metre = a+b+c+d
Rate per metre = a+b+c+d/50
Maintenance of Road Signs
Maintenance of road signs by way of cleaning and repainting of
mandatory / regulatory / cautionary / informatory and place
identifications sign board as per drawings and technical specification
Clause 1910 MORD

Unit = 1 km
All types of signs in one Km
a) Labour
Mate
Mazdoor (Unskilled)
Painter 1st Class
b) Material
Synthetic Enamel Paint, Engineering grade tape, welding
machine etc. (LS Rs.300)
c&d) Overheads & Contractors Profit
Cost for one Km = a+b+c+d
Rate per km = a+b+c+d

628

RBR-MTRD
Index-code

S. No
1

RBR-MTRD-20

20
i

Description

Unit

Quantity

Rate
Rs.

21

Remarks

Maintenance of steel and RCC Railing


Repair of steel railing to bring it to original shape cleaning and
repainting as per drawing and technical specification Clause
1911MORD

Steel Railing
Unit = Running metre
Taking output = 10 metre
It is assumed that damage is to the extent of 10%
a) Labour
day
Mate
day
Mazdoor (Unskilled)
day
Painter 1st Class
day
Blacksmith
b)
Material
t
Mild steel (structural steel)
ISMC = 0.029T
MS plate = 0.01
t
Nuts and bolts
c) Machinery
LS
Welding set (LS Rs.100.00)
d&e) Overheads & Contractors Profit
Cost for 10 metre = a+b+c+d+e
Rate per metre = a+b+c+d+e/10
ii Repair of RCC railing to bring it to the original shape, cleaning
and repainting as per drawings and technical specification
Clause 1911 MORD
RCC Railing
Unit = running metre
Taking output = 1 metre
It is assumed that damage is to the extent of 10%
a) Labour
day
Mate
day
Mazdoor (Unskilled)
day
Mason 1st Class
b)
Material
M 30 grade cement concrete
cum
Rate as per item no. 13.1 (III) of Chapter 13
Steel bars reinforcement
t
Rate as per item no.13.2 of Chapter 13
c&d) Overheads & Contractors Profit
Rate per metre = a+b+c+d+e
RBR-MTRD-21

Amount
Rs.

0.324
0.100
0.200
0.039

0.001
LS

0.212
0.100

0.100
0.013

Maintenance of 200 metre and km stones


Maintenance of 200 metre and km stone by way of refitting of tilted
stones repairing with cement mortar, cleaning, repairing and lettering
on 200 metre km stone and 5th km stone as per drawing and
technical specification Clause 1912 MORD

Unit = 1 km
Assuming 1 km stone, 4 nos 200 metre stone and 1/5th 5km
stone
Painting two coats with synthetic enamel paint
200 m stone 4 nos = 0.760 sqm.
One km stone = 0.815 sqm.
5th km stone 1x1/5 = 0.320 sqm.
Total = 1.895 sqm.
sqm
As per item No. 10.5 of chapter 10

1.895

ii Printing letters and figures of any shade with synthetic enamel


paint of any approved colour to give an even shade

200 m stone 4 Nos. = 40 per cm height per letter


One no km stone = 120 per cm height per letter
5th km stones 1/5th = 60 per cm height per letter
Total = 220 per cm height per letter
Rate as per item no 10.1 of chapter 10

per cm
height

220.000

629

RBR-MTRD
Index-code

S. No
1

RBR-MTRD-22

Description

Unit

Quantity

Rate
Rs.

day
day
day

0.524
0.100

LS

LS

day
day
day

1.120
2.000

day
day

2.080

day
day

10.400

day
day
day

0.153
0.143

quintal
kg
kg

0.045
0.100
0.013

a) Labour
Mate
Mazdoor (Unskilled)
Mason 1st Class
b)
Material
Cement, sand, aggregates etc.
(LS = Rs.100.00)
c&d) Overheads & Contractors Profit
Rate per/km = (i+ii+a+b+c+d)
Cutting of branches of trees shrubs and trimming of
grass and weeds

22
i

23

Remarks

Cutting of branches of trees and shrubs from the road way or


with in R.O.W including disposal of wood and leaves to suitable
location as per technical specification Clause 1914 MORD

Unit = one tree


Taking output = 10 trees of 900 mm average girth
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b&c) Overheads & Contractors Profit
Cost for 10 trees = (a+b+c)
Rate per tree = (a+b+c)/10
ii Cutting of shrubs from the road way or with in R.O.W and
disposal of shrubs to suitable locations as per technical
specifications Clause 1914 MORD
Unit=Each
Taking output = 100 nos shrubs
a) Labour
Mate
Mazdoor (Unskilled)
b&c) Overheads & Contractors Profit
Cost for 100 shrubs = a+b+c
Rate per shrub = a+b+c/100
iii Trimming of grass and weeds from the shoulders/berms
and disposing off the same to suitable locations as per
technical specifications Clause 1914 MORD

RBR-MTRD-23

Amount
Rs.

Unit = sqm
Taking output = 1500 sqm
a) Labour
Mate
Mazdoor (Unskilled)
b&c) Overheads & Contractors Profit
Cost for 1500 sqm = a+b+c
Rate per sqm = a+b+c/1500
White washing of parapet walls of CD work and tree
truncks
White washing two coats on parapet walls and tree trunks including
preparation of surface by cleaning scraping etc. as per technical
specifications Clause 1915 MORD

RBR-MTRD-24

24

Unit = sqm
Taking output = 9 sqm
a) Labour
Mate
Mazdoor (Unskilled)
White washer
b)
Material
Lime
Fevicol adhesive
Indigo
c&d) Overheads & Contractors Profit
Cost for 9 sqm = a+b+c+d
Rate per sqm = a+b+c+d/9
Periodical Renewal to existing bituminous surface
I Open graded Premix carpet 20 mm thick
Unit = sqm
(i) Tack coat
With bituminous Emulsion (RS-1)
Rates as in Chapter 5

sqm

(ii) Pre-mix carpet using bituminous (penetration grade modified


bitumen) binder

Rates as in Chapter 5
as relevant
Or
(iii) Premix carpet using bitumen Emulsion
Rates as in Chapter 5

sqm

sqm

630

RBR-MTRD
Index-code

S. No

Description

Unit

Quantity

Rate
Rs.

(iv) Seal coat Type A, B or C


Rates as in Chapter 5
II Surface dressing single coat/first coat or 2nd coat
Rates as in Chapter 5

Amount
Rs.

Remarks

sqm

General Note :
The provisions towards Mate is included in the provision towards unskilled Mazdoor.

631

RBR-GSRE

Andhra Pradesh Standard Data


I. Roads and Bridges
CHAPTER - 16
GEOSYNTHETICS AND REINFORCED EARTH
Index-code

RBR-GSRE-1

RBR-GSRE-2

S. No

Description

Unit

Quantity

2
Sub-Surface Drain with Geotextiles
Construction of sub surface drain 200 mm dia using geotextiles
treated with carbon black with physical properties as given in
clause 702.2.3 formed in to a stable network and a planar
geocomposite structure, joints wrapped with geotextile to prevent
ingress of soil, all as per clause 702 MORTH and approved
drawings including excavation and backfilling

Unit = Running metre


Taking output = one metre
a) Labour
Mate
day
Mazdoor skilled
day
Mazdoor (Unskilled)
day
b)
Material
Geonets, geomembrane and geotextile to make planar
geocomposite stable network for sub surface drain including
wrapping of joints with 160 mm over lapping with geotextile .
Geonets
sqm
Geomembrane
sqm
Geotextile
sqm
Add 2 per cent cost of material for miscellaneous items like
synthetic cord
c&d) Overheads & Contractors Profit
Rate per metre = a+b+c+d
Note : Surplus excavated material to be used at site. Hence separate
cost for disposal not added.
Narrow Filter Sub-Surface Drain as per Specification 702.4
Construction of a narrow filter sub- surface drain consisting of
porous or perforated pipe laid in narrow trench surrounded by a
geotextile filter fabric, with a minimum of 450 mm overlap of
fabric and installed as per clause 702.3 and 309.3.5 including
excavation and backfilling
Unit = Running metre length
Taking output = one metre
a) Labour
Mate
day
Mazdoor skilled
day
Mazdoor (Unskilled)
day
b)
Material
Perforated geosynthetic pipe 150 mm dia
M
Geotextile filter fabric
sqm
Add 2 per cent cost of material for miscellaneous item like
synthetic cord
c&d) Overheads & Contractors Profit
Rate per metre = a+b+c+d
Note : Surplus excavated material to be used at site. Hence separate
cost for disposal not added.

Rate Amount
(Rs.)
(Rs.)
5

0.250
0.540

1.000
1.000
2.000

0.250
0.540
1.000
1.250

633

RBR-GSRE
Index-code

RBR-GSRE-3

S. No

Description

Unit

Quantity

2
Laying Paving Fabric Beneath a Pavement Overlay as per
Specification 703
Providing and laying paving fabric with physical requirements as
per table 704-2 over a tack coat of paving grade Bitumen 80-100
penetration, laid at the rate of 1 kg per sqm over thoroughly
cleaned and repaired surface to provide a water resistant
membrane and crack retarding layer. Paving fabric to be free of
wrinkling and folding and to be laid before cooling of tack coat,
brooming and rolling of surface with pneumatic roller to maximize
paving fabric contact with pavement surface

day
day

20.800

hour
hour
hour

2.240
1.400
1.680

sqm
tonne

2940.000
2.800

day
day
day

0.500
1.560

sqm
each
M
cum
cum

21.000
50.000
20.000
3.450
0.450

Unit = sqm
Taking output = 2800 sqm
a) Labour
Mate
Mazdoor (Unskilled)
b)
Machinery
Road sweeper 1250 sqm per hour
Pneumatic roller 14 tonnes 2000 sqm per hour
Bitumen pressure distributor 1750 sqm per hour
c)
Material
Paving Fabric
Paving Bitumen 80-100

RBR-GSRE-4

Rate Amount
(Rs.)
(Rs.)
5

d&e) Overheads & Contractors Profit


Cost for 2800 sqm = a+b+c+d+e
Rate per sqm =(a+b+c+d+e)/2800
Laying Boulder Apron in Crates of Synthetic Geogrids as per
Specification 704
Providing, preparing and laying of geogrid crated apron 1 m x 5
m, 600 mm thick including excavation and backfilling with baffles
at 1 metre interval, made with geogrids having characteristics as
per clause 704.2 MORTH, joining sides with connectors/ring
staples, top corners to be tie tensioned, placing of suitable cross
interval ties in layers of 300 mm connecting opposite side with
lateral braces and tied with polymer braids to avoid bulging,
constructed as per clause 704.3. filled with stone with minimum
size of 200 mm and specific gravity not less than 2.65, packed
with stone spalls, keyed to the foundation recess in case of
sloping ground and laid over a layer of geotextile to prevent
migration of fines, all as per clause 704 and laid as per clause
2503.3 and approved design.
Unit = cum
Taking output = 3.00 cum
a) Labour
Mate
Mazdoor skilled
Mazdoor (Unskilled)
b)
Material
Geo grids
Connectors/ Staples
Polymer braids
Stones with minimum size of 200 mm
Stones spall for filling voids
c&d) Overheads & Contractors Profit
Cost for 3 cum = a+b+c+d
Rate per cum = (a+b+c+d)/ 3

634

RBR-GSRE
Index-code

RBR-GSRE-5

RBR-GSRE-6

S. No

Description

Unit

Quantity

2
Reinforced Earth Structures as per Specification 3100
MORTH
Reinforced earth Structures have four main components as
under:
a) Excavation for foundation, foundation concrete and cement
concrete grooved seating in the foundation for facing elements
(facia material).

b)
Facia material and its placement.
c)
Assembling, joining with facing elements and laying of the
reinforcing elements.
d)
Earth fill with granular material which is to be retained by
the wall.
Each component is analysed separately as under:
considering Average height of wall = 8 m.
(i) Assembling, joining and laying of reinforcing elements as
per Specification 3102 MORTH
A
With reinforcing element of steel / Aluminum strips /
polymeric strips.
Unit = Running Metre
Taking Output = 450 m
a) Labour
Mate
day
Mazdoor (Unskilled)
day
Mazdoor skilled
day
b)
Material
@ Reinforcement strips 60 mm wide 5 mm thick as per clause
3102.
1.Galvanised carbon steel strips
M
or
2.Copper Strips
M
or
3.Aluminium Strips
M
or
4.Stainless steel strips
M
or
5.Glass reinforced polymer/fiber reinforced polymer/polymeric M
strips

Rate Amount
(Rs.)
(Rs.)
5

6.360
3.000

450
450
450
450
450

@ Any one of the above alternative may be adopted as per approved


design.
Add
10 per cent of the cost of reinforcing strip towards accessories like
tie-strips, nuts and bolts and loops/lugs for joining reinforcing elements
with the facia panels, overlaps, heat bonding or extension.

II

III

IV

Galvanised carbon steel strips


c&d) Overheads & Contractors Profit
Cost of 450 m = a+b+c+d
Rate per metre =(a+b+c+d)/450
Copper Strips
c&d) Overheads & Contractors Profit
Cost of 450 m = a+b+c+d
Rate per metre =(a+b+c+d)/450
Aluminum Strips
c&d) Overheads & Contractors Profit
Cost of 450 m = a+b+c+d
Rate per metre =(a+b+c+d)/450
Stainless steel strips
c&d) Overheads & Contractors Profit
Cost of 450 m = a+b+c+d
Rate per metre =(a+b+c+d)/450
Glass reinforced polymer/fiber reinforced polymer/polymeric
strips
c&d) Overheads & Contractors Profit
Cost of 450 m = a+b+c+d
Rate per metre =(a+b+c+d)/450
With reinforcing elements of synthetic geogrids
Unit = sqm
Taking output = 300 sqm
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor skilled
b)
Material
Synthetic Geogrids as per clause 3102.8 and approved design
and specifications.

day
day
day

6.360
3.000

sqm

300.000

635

RBR-GSRE
Index-code

S. No

Description

Unit

Quantity

2
Add 10 per cent of the cost of reinforcing elements (synthetic
geogrids) for accessories like tie-strips, nuts and bolts and
loops/lugs for joining reinforcing elements with the facia panels,
overlaps and other protective elements for synthetic geogrids.

day
day
day

3.180
1.500

hour

6.000

cu.m

13.500

0.380

Rate Amount
(Rs.)
(Rs.)
5

c&d) Overheads & Contractors Profit


Cost of 300 sqm of Synthetic geogrids = a+b+c+d
Rate per sqm = (a+b+c+d)/ 300
(ii) Facing elements of RCC as per Specification 3104 MORTH
Unit = sqm
Taking output = 75 sqm
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor skilled
b)
Machinery
Light crane with lifting capacity upto 3 tonne
c)
Material
Pre-cast RCC M-35 facing elements of size as per design and 18
cm thick for 75 sqm. (Refer Chapter 12)
HYSD steel @ 5 kg / sqm (Refer Chapter 12)
Add 2 per cent of cost of facia panels, for all necessary
temporary form work, scaffolding and provision of loops/lugs for
lifting of panels and joining the reinforcing elements.
d&e) Overheads & Contractors Profit
Cost for 75 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/ 75

Note : 1.The specification and construction details to be adopted shall be as per section 3100 of
MoRTH Specification.
2. Drainage arrangement shall be made as per approved design and drawings.
3. The quantity of filler media shall be calculated as per approved design and specifications and shall
be priced separately. The rate for same to be adopted from chapter 15.
4. Excavation for foundation including foundation concrete and groove in the foundation for seating of
bottom most facia panel and capping beam to be calculated as per design and priced separately. The
rates for excavation and foundation concrete shall be taken from the chapter 12 & 13 in bridge section.
5. The earth fill to be retained is not included in this analysis. The same is to be worked out and
provided separately complete as per clause 305.
6. For compaction of Earthwork, attention is invited to clause 3105.5 of MoRTH Specification.
7. Length of reinforcing strips will vary with the height of wall and will be as per approved design and
drawings.
8. The type of reinforcing elements to be adopted shall be as per approved design and specifications.
9. The market rate for supply of reinforcing elements and their accessories are to be ascertained from
reputed firms in the field of earth reinforcement.
10. The earth fill material shall be clean, free draining, granular with high friction and low cohesion, noncorrosive, coarse grained with not 10 per cent of particles passing 75 micron sieve, free of any
deleterious matter, chlorides, salts, acids, alkalies, mineral oil, fungus and microbes and shall be of
specified PH value.
11. Capping beam is to be priced separately as per approved design. The rate for cement concrete
shall be taken from the chapter of sub-structure in bridge section.
12. The cost of reinforced earth retaining wall shall include following:
(I) Excavation for foundation including backfilling.
(ii) Foundation concrete as per approved design.
(iii) Cost of facial panels and their erection .
(iv) Cost of reinforcing elements including their fixing and joining with the facial panels.
(v) Drainage arrangement including filter media as per approved design and drawings.
13. The compacted earth filling to be retained shall form part of embankment.
General Note :
The provisions towards Mate is included in the provision towards unskilled Mazdoor.

636

RBR-HRTC

Andhra Pradesh Standard Data


I. Roads and Bridges
CHAPTER - 17
HORTICULTURE

Index-code

RBR-HRTC-1

S. No

Description

2
Spreading of Sludge Farm Yard Manure or/and good Earth as
per Specification 307 MORTH

Unit Quantity
3

Rate
(Rs.)

Amount
(Rs.)

Spreading of sludge farm yard manure or/ and good earth in required
thickness (cost of sludge, farm yard manure or/and good earth to be
paid for separately)

RBR-HRTC-2

Unit = cum
Taking output = 15 cum
a) Labour
Mate
day
Mazdoor (Unskilled)
day
b&c) Overheads & Contractors Profit
Cost for 15 cum= a+b+c
Rate per cum = (a+b+c)/15
Grassing with ' Doobs' Grass as per Specification 307 MORTH
Grassing with 'Doobs' grass including watering and maintenance of
the lawn for 30 days or more till the grass forms a thick lawn free
from weeds and fit for moving including supplying good earth if
needed
Unit = sqm
Taking output = 100 sqm
(i) In rows 15 cm apart in either direction
a) Labour
Mate
Mazdoor (Unskilled) for grassing
Mazdoor (Unskilled) for maintenance for 30 days
b)
Machinery
Water tanker6 KL capacity
c)
Material
Doob grass
d&e) Overheads & Contractors Profit
Cost for 100 sqm = a+b+c+d+e
Rate per sqm= (a+b+c+d+e)/100
(ii) In rows 7.5 cm apart in either direction
a) Labour
Mate
Mazdoor (Unskilled) for grassing.
Mazdoor (Unskilled) for maintenance for 30 days
b)
Machinery
Water tanker6 KL capacity
c)
Material
Doob grass
d&e) Overheads & Contractors Profit
Cost for 100 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/100
NOTE : In the case of horticulture one mate has been provided for
every 10 mazdoors as maintenance of grass and plants require more
care.

1.040

day
day
day

0.170
0.920
1.000

hour

0.500

kg

100.000

day
day
day

1.470
1.000

hour

0.750

kg

200.000

638

RBR-HRTC
Index-code

RBR-HRTC-3

RBR-HRTC-4

S. No

Description

2
Making Lawns including Ploughing and Dragging with 'Swagha'
Breaking of Clod as per Specification 307 MORTH
Making lawns including ploughing and breaking of clod, removal of
rubbish, dressing and supplying doobs grass roots and planting at 15
cm apart, including supplying and spreading of farm yard manure at
rate of 0.18 cum per 100 sqm
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate
Mazdoor (Unskilled) for preparation of ground
Mali for fetching doobs grass roots and grassing at 15 cm apart
b)
Machinery
Water tanker6 KL capacity
Tractor with tiller
c)
Material
Supply of farm yard manure at site of work
Fine grass
d&e) Overheads & Contractors Profit
Cost for 100 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/100
Maintenance of Lawns or Turfing of Slopes as per Specification
307 MORTH
Maintenance of lawns or Turfing of slopes (rough grassing)
for a
period of one year including watering etc

Unit = sqm
Taking output = 100 sqm
a) Labour
Mali
b)
Machinery
Water tanker6 KL capacity
c)
Material
Cost of water
d&e) Overheads & Contractors Profit
Cost for 100 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/100

RBR-HRTC-5

Unit Quantity
3

day
day
day

0.650
1.000

hour
hour

0.500
0.010

cum
kg

0.180
100.000

day

10.000

hour

15.000

KL

90.000

Rate
(Rs.)

Amount
(Rs.)

Turfing Lawns with Fine Grassing including Ploughing, Dressing


as per Specification 307 MORTH
Turfing lawns with fine grassing including ploughing, dressing
including breaking of clods, removal of rubbish, dressing and
supplying doobs grass roots at 10 cm apart, including supplying and
spreading of farm yard manure at rate of 0.6 cum per 100 sqm
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate
day
Mazdoor (Unskilled) for preparation of ground
day
Mali for fetching doobs grass roots hedges and grassing at 10 cm day
apart
b)
Machinery
Water tanker6 KL capacity
hour
Tractor with tiller
hour
c)
Material
Supply of farm yard manure at site of work @ 0.6 cum per 100sqm
cum
Fine grass
kg
d&e) Overheads & Contractors Profit
Cost for 100 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/100

1.250
1.500

0.500
0.010
0.600
100.000

639

RBR-HRTC
Index-code

RBR-HRTC-6

S. No

Description

2
Maintenance of Lawns with Fine Grassing for the First Year as
per Specification 307 MORTH
Maintenance of lawns with fine grassing for the first year including
watering etc

Unit = sqm
Taking output = 100 sqm
a) Labour
Mali
b)
Machinery
Water tanker6 KL capacity
c)
Material
Cost of water
d&e) Overheads & Contractors Profit
Cost for 100 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/100

RBR-HRTC-7

Unit Quantity
3

day

10.000

hour

20.000

KL

60.000

Rate
(Rs.)

Amount
(Rs.)

Planting and Maintaining of Permanent Hedges as per


Specification 307 MORTH
(a) Planting permanent hedges including digging of trenches
Planting permanent hedges including digging of trenches, 60 cm
wide and 45 cm deep, refilling the excavated earth mixed with
farmyard manure, supplied at the rate of 4.65 cum per 100 metres
and supplying and planting hedge plants at 30 cm apart
Unit = Running metre
Taking output = 100metre
a) Labour
Mate

day
day
Mazdoor (Unskilled) for refilling the excavated earth mixed with cow day
dung, preparation of ground and digging of plant, from the nursery
carriage to site and planting in position
b)
Machinery
Water tanker6 KL capacity
hour
c)
Material
Cost of hedge plants 2 rows at 30 cm apart
each
Supply of farm yard manure at site of work
cum
Pesticide
kg
Cost of water
KL
d&e) Overheads & Contractors Profit
Cost for 100 metres = a+b+c+d+e
Rate per metre = a+b+c+d+e)/100
(b) Maintenance of hedge for one year
Unit = Running metre
Taking output = 100 m
a) Labour
Mate
day
Mazdoor (Unskilled)
day
b)
Machinery
Water tanker6 KL capacity
hour
c)
Material
Manure sludge/Farm yard manure
cum
Pesticide
kg
Cost of water
KL
Cost of hedge plants @ 10 per cent casualty
each
d&e) Overheads & Contractors Profit
Cost for 100 metres = a+b+c+d+e
Rate per metre = a+b+c+d+e)/100
Mazdoor (Unskilled) for digging of trench 60 cm wide and 45 cm deep

10.000
5.400

0.500
2x340
4.670
0.250
3.000

33.000
5.000
2.000
0.500
30.000
68.000

640

RBR-HRTC
Index-code

S. No
1

RBR-HRTC-8

Description

2
Planting and Maintaining of Flowering Plants and Shrubs as per
Specification 307 MORTH
(a) Planting flowering plants and shrubs in central verge
Unit = Running metres 200 plants and 800 shrubs in two rows in
one km length of road where width of verge is 3m and above.

Unit Quantity
3

Taking output = 1000 metres


a) Labour
Mate
day
Mazdoor (Unskilled)
day
b)
Machinery
Water tanker6 KL capacity
hour
c)
Material
Plants
each
Shrubs
each
Manure sludge/Farm yard manure
cum
Pesticide
kg
Cost of water
KL
d&e) Overheads & Contractors Profit
Rate per Km = (a+b+c+d+e)
(b) Maintenance of flowering plants and shrubs in central verge for
one year
Unit = km
Taking output = one km
a) Labour
Mate
day
Mazdoor (Unskilled)
day
b)
Machinery
Water tanker6 KL capacity
hour
c)
Material
Manure Sludge / farm yard manure at site
cum
Cost of water
KL
Replacement of casualties @ 10 per cent
Plants
each
Shrubs
each
d&e) Overheads & Contractors Profit
Rate per Km for one year = (a+b+c+d+e)

RBR-HRTC-9

Rate
(Rs.)

Amount
(Rs.)

13.200
6.000
200.000
800.000
63.640
0.500
36.000

401.000
90.000
10.000
180.000
20.000
80.000

Planting of Trees and their Maintenance for one Year as per


Specification 307 MORTH
Planting of trees by the road side (Avenue trees) in 0.60 m dia holes,
1 m deep dug in the ground, mixing the soil with decayed farm
yard/sludge manure, planting the saplings, backfilling the trench,
watering, fixing the tree guard and maintaining the plants for one
year
Unit = Each
Taking output = 10 trees
a) Labour
Mate
Mazdoor (Unskilled) for planting
Mazdoor (Unskilled) for maintenance for one year
b)
Machinery
Water tanker6 KL capacity
c)
Material
Sapling 2 m high 25 mm dia
Farm yard manure
Pesticide
Cost of water
d&e) Overheads & Contractors Profit
Cost for 10 trees = a+b+c+d+e
Rate per trees = (a+b+c+d+e)/10

day
day
day

3.700
15.000

hour

2.000

each
cum
kg
KL

10.000
0.940
0.500
12.000

641

RBR-HRTC
Index-code

S. No

Description

2
Renovation Lawns including, Weeding, Forking the Ground, Top
Dressing with Forked Soil as per Specification 308 MORTH

10

RBR-HRTC-10

RBR-HRTC-11

RBR-HRTC-12

11

12

RBR-HRTC-13 13

Unit Quantity
3

Renovation lawns including, weeding, forking the ground, top


dressing with forked soil, watering and maintenance the lawns, for 30
days or more, till the grass forms a thick lawn, free from weeds, and
fit for moving and disposal of rubbish as directed, including supplying
good earth, if needed but excluding the cost of well decayed farm
yard manure
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate
day
Mazdoor (Unskilled)
day
b)
Machinery
Water tanker6 KL capacity
hour
c)
Material
Cost of water
KL
d&e) Overheads & Contractors Profit
Cost for 100 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)
Supply at Site Well Decayed Farm Yard Manure as per
Specification 308.2 MORTH
Supply at site of work well decayed farm yard manure, from any
available source, approved by the engineer in charge including
screening and stacking
Unit = cum
Taking output = one cum
a) Material
a) Cost of well decayed farm yard manure duly screened, cum
loading, carriage, unloading and stacking at site
b&c) Overheads & Contractors Profit
Rate per cum = (a+b+c)
Supply at Site of Work/ Store-Deoiled Neem Cake as per
Specification 308.2 MORTH
Supply at site of work/ store-deoiled neem cake duly packed in used
gunny bags
Unit = quintal
Taking output = one quintal
a) Cost, carriage, loading, unloading and stacking in store/site quint
al
b&c) Overheads & Contractors Profit
Rate per quintal = a+b+c
Supplying Sludge as per Specification 308.2 MORTH
Supplying sludge duly stacked at site/ store
Unit = cum
Taking output = one cum
a)
Cost of sludge including carriage, loading, unloading and cum
stacking at site
b&c) Overheads & Contractors Profit
Rate per cum = a+b+c

Rate
(Rs.)

Amount
(Rs.)

3.120
0.500
3.000

1.000

1.000

1.000

642

RBR-HRTC
Index-code

S. No

Description

2
Half Brick Circular Tree Guard, in 2nd Class Brick, internal
diameter 1.25 metres, and height 1.2 metres, above ground and
0.20 metre below ground
Half brick circular tree guard, in 2nd class brick, internal diametre
1.25 metres, and height 1.2 metres, above ground and 0.20 metre
below ground, bottom two courses laid dry, and top three courses in
cement mortar 1:6 (1 cement 6 sand) and the intermediate courses
being in dry honey comb masonry, as per design complete

14

RBR-HRTC-14

Unit = Each
Taking output = one tree guard
a) Labour
Mate
Mason
Mazdoor (Unskilled)
b)
Material
Brick 2nd class including carriage
Cement mortar 1:6
c&d) Overheads & Contractors Profit
Rate per tree Guard = a+b+c+d

RBR-HRTC-15 15

RBR-HRTC-16

16

Edging with 2nd Class Bricks, Laid Dry Lengthwise


Edging with 2nd class bricks, laid dry lengthwise, including
excavation, refilling, consolidation, with a hand packing and
spreading nearly surplus earth within a lead of 50 metres
Unit = Metre
Taking output= 10 metres
a) Labour
Mate
Mason
Mazdoor (Unskilled)
b)
Material
Brick 2nd class including carriage
c&d) Overheads & Contractors Profit
Cost for 10 metre = a+b+c+d
Rate per metre = (a+b+c+d)/10

Unit Quantity
3

day
day
day

0.250
0.300

Rate
(Rs.)

Amount
(Rs.)

each 230.000
cum
0.025

day
day
day

0.050
0.052

each

50.000

day
day
day

0.150
0.090

each
kg
each

1.000
0.650
22.000

Making Tree Guard 53 cm dia and 1.3 m High as per Design from
Empty Bitumen Drums
Making tree guard 53 cm dia and 1.3 m high as per design from
empty bitumen drum, slit suitably to permit sun and air, (supplied by
the department at stock issue rate) including providing and fixing 2
nos MS sheet rings 50 x 0.5 mm with rivets, complete in all respect
Unit = Each
Taking output = one tree guard
a) Labour
Mate
Blacksmith
Mazdoor (Unskilled)
b)
Material
Empty bitumen drum
MS sheet 50 x 0.5 mm
Rivets 6 mm dia and 10 mm in length
d&e) Overheads & Contractors Profit
Rate for each tree guard = a+b+c+d

643

RBR-HRTC
Index-code

RBR-HRTC-17

S. No

Description

2
Making Tree Guard 53 cm dia and 2 Metre High as per Design
from Empty Bitumen Drums

17

Unit Quantity
3

day

0.200
0.240

each
kg
each

1.500
0.650
50.000

day
day
day

2.000
2.950

quint
al
quint
al

1.050
0.050

day
day
day

0.250
0.300

kg
kg

19.200
9.600

hour

0.040

sqm

1.770

Rate
(Rs.)

Amount
(Rs.)

Making tree guard 53 cm dia and 2 metres high as per design from empty
bitumen drums, slit suitably to permit sun and air, ( supplied by the department
at stock issue rate)
including providing and fixing four legs 40 cm long of 30
x 3 mm MS riveted to tree guard and providing and fixing 2 nos MS sheet rings
50 x 0.5 mm with rivets complete in all respects

RBR-HRTC-18 18

Unit = Each
Taking output = one tree guard
a) Labour
Mate
Blacksmith
Mazdoor (Unskilled)
b)
Material
Empty bitumen drum
MS sheet 50 x 0.5 mm
Rivets 6 mm dia and 10 mm in length
c&d) Overheads & Contractors Profit
Rate for each tree guard = a+b+c+d
Wrought Iron and Mild Steel Welded Work
Wrought iron and mild steel welded work (using angles, square bars, tees and
channel grills, grating frames, gates and tree guards of any size and design etc.
including cost of screens and welding rods or bolts and nuts complete fixed in
position but without the cost of excavation and concrete for fixing which will be
paid separately

RBR-HRTC-19 19

Unit = quintal
Taking output = one quintal
a) Labour
Mate
Blacksmith/ welder for cutting to design and shape and jointing
Mazdoor (Unskilled) for fixing and helper for Blacksmith/welder
b)
Material
Angle, tees, channels etc
Deduct the cost of scrap
Add 5 per cent of cost of material for welding rods and other welding
accessories
c&d) Overheads & Contractors Profit
Rate per quintal = a+b+c+d
Tree Guard with MS Iron
Providing and fixing MS iron tree guard 60 cm dia and 2 metre high above
ground level formed of 4 Nos (25 x 6 mm) and 8 Nos (25 x 3 mm) vertical MS
riveted to 3 Nos (25 x 6 mm) iron rings in two halves, bolted together with 8 mm
dia and 30 mm long bolts including painting two coats with paint of approved
brand over a coat of priming, complete in all respects.

Unit = Each
Taking output = one tree guard
a) Labour
Mate
Blacksmith
Mazdoor (Unskilled)
b)
Material
MS iron 25 x 6 mm
MS iron 25 x 3 mm
Add 5 per cent of cost of material for riveting, bolting and welding accessories

c)
Machinery
Tractor-trolley
d)
Painting
Painting two coats including priming
e&f) Overheads & Contractors Profit
Rate per tree guard =a+b+c+d+e+f

1 The items of excavation and concreting to be measured and paid separately as per design .
2 . Rate of painting may be adopted from the chapter as Traffic signs.

RBR-HRTC-20 20

Tree Guard with MS Angle Iron and Steel Wire


Providing and fixing tree guard 0.60 metre square, 2.00 metre high
fabricated with MS angle iron 30 x 30 x 3 mm, MS iron 25 x 3 mm
and steel wire3 mm dia welded and fabricated as per design in two
halves bolted together
Unit = Each
Taking output = one
a) Labour
Mate
Blacksmith
Welder
Mazdoor (Unskilled)
b)
Material
MS angle 30 x 30 x 3 mm
MS iron 25 x 3 mm
Steel wire 3 mm dia

day
day
day
day

0.250
0.250
0.300

kg
kg
kg

13.500
18.000
6.000

644

RBR-HRTC
Index-code

S. No
1

RBR-HRTC-21 21

Description

Unit Quantity

2
3
Add 5 per cent of cost of material for riveting, bolting and welding
accessories
c)
Machinery
Tractor-trolley
hour
d)
Painting
Painting two coats including priming
sqm
e&f) Overheads & Contractors Profit
Rate per tree guard = a+b+c+d+e+f
Compensatory Afforestation
Planting trees as compensatory afforestation at the rate of 290 trees
per hectare at a spacing of 6 m by grubbing and leveling the ground
upto a depth of 150 mm, digging holes 0.9 m dia, 1 m deep, mixing
farm yard/sludge manure with soil, planting of sapling 2 m high with
25 cm dia stem, backfilling the hole and watering

Rate
(Rs.)

Amount
(Rs.)

0.040
1.500

Unit = Hectare
Taking output = one hectare
a) Labour
i) Planting
Mate
day
Mazdoor (Unskilled)
day
27.500
ii) For Maintenance for one year
Mate
day
Mazdoor (Unskilled)
day
50.500
b)
Machinery
Dozer 80 HP @ 1000 sqm/hour
hour 10.000
Water tanker6 KL capacity (for planting)
hour
3.000
Water tanker6 KL capacity (for maintenance)
hour 25.000
c)
Material
Sapling 1 to 1.5 m high 2 cm dia stem
each 290.000
Add 10 per cent of sapling
each 29.000
Decayed farm yard/sludge manure (planting)
cum 60.900
Decayed farm yard/sludge manure (maintenance)
cum
4.000
Pesticides for planting
kg
0.500
Pesticides for maintenance
kg
1.500
Cost of water
KL
18.000
d&e) Overheads & Contractors Profit
Rate per hectare = a+b+c+d+e
Cost of fencing to be provided as per size of plot and approved
design, measured and paid separately
General Note :
The provisions towards Mate is included in the provision towards unskilled Mazdoor.

645

RBR-RPRH

Andhra Pradesh Standard Data


I. Roads and Bridges
CHAPTER - 18
REPAIR AND REHABILITATION

Index-code

S. No

Description

Unit

Quantity

Rate
(Rs.)

Amount
(Rs.)

2
Removal of existing cement concrete wearing coat including its
disposal complete as per Technical Specification 2809 MORTH
without causing any detrimental effect to any part of the bridge
structure and removal of dismantled material with all lifts and
lead upto 1000 m
Unit = Sq m ( Thickness 75 mm)
Taking output = 10 sqm
a) Labour
Mate
Mazdoor (Unskilled)
b)
Machinery
Air Compressor 250 cfm with pneumatic breaker/jack hammer along
with accessories.
Tractor-trolley.
c&d) Overheads & Contractors Profit
Cost for 10 sqm = (a+d+c+d)
Rate per sqm = (a+b+c+d)/10
Removal of existing asphaltic wearing coat comprising of 50 mm
thick asphaltic concert laid over 12 mm thick mastic asphalt
including disposal with all lift and lead upto 1000 m as per
Technical Specification 2809 MORTH.
Unit = Sq m
Taking output = 10 sqm
a) Labour
Mate
Mazdoor (Unskilled)
b)
Machinery
Air Compressor 250 cfm with pneumatic breaker.
Tractor-trolley.
c&d) Overheads & Contractors Profit
Cost for 10 sqm = (a+d+c+d)
Rate per sqm = (a+b+c+d)/10
Guniting concrete surface with cement mortar applied with
compressor after cleaning surface and spraying with epoxy
complete as per Technical Specification 2807 MORTH
Unit = Sq m
Taking output = 1 sqm
Assuming thickness 25 mm
a) Material
Cement
Graded sand
Wire mesh 50mm x 50mm size of 3mm wire
Epoxy
Accelerator compound for guniting @ 4 % of weight of cement
Add 2 per cent of cost of material for miscellaneous consumables like
nozzles, wire brush, cotton waste etc.
b)
Labour
Mate
Mason
Mazdoor (Unskilled)
c)
Machinery
Compressor with guniting equipment along with accessories
d&e) Overheads & Contractors Profit
Rate per sqm = (a+b+c+d+e)

day
day

1.06

hour

1.00

hour

0.50

day
day

0.78

hour
hour

0.75
0.40

kg
cum
kg
kg
kg

16.00
0.04
2.00
0.67
0.64

day
day
day

0.04
0.15

hour

0.10

RBR-RPRH-1

RBR-RPRH-2

RBR-RPRH-3

647

RBR-RPRH
Index-code

S. No
1

RBR-RPRH-4

Description

Unit

2
3
Providing and inserting nipples with approved fixing compound
after drilling holes for grouting as per Technical Specifications
2800 MORTH including subsequent cutting/removal and sealing
of the hole as necessary of nipples after completion of grouting
with Cement/Epoxy
Unit = Number
Taking output = 1 No.
a) Material
Nipples
each

Quantity

Rate
(Rs.)

Amount
(Rs.)

1.00

Cement, fixing compound and consumables @ 15% of cost of nipple

RBR-RPRH-5

RBR-RPRH-6

b)
Labour
Mate
Mazdoor (Skilled) labour for drilling
Mazdoor (Skilled) labour for fixing nipple and sealing inlets
Mazdoor (Unskilled) for cutting and removing of nipples
Add 10 per cent of labour cost for drilling holes etc
c&d) Overheads & Contractors Profit
Rate per No. = (a+b+c+d)
5
Sealing of cracks/porous concrete by injection process through
nipples/Grouting complete as per Technical Specification 2806
MORTH.
A Cement Grout
Unit = kg
Taking output = 1 kg
a) Material
Cement including 10 per cent wastage
Admixtures (anti shrinkage compound) @ 20 % of cost of cement
b)
Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
c)
Machinery
Grout pump with agitator and accessories
d&e) Overheads & Contractors Profit
Rate per kg = (a+b+c+d+e)
B Cement Mortar (1:1) Grouting
Unit = kg
Taking output = 1 kg
a) Material
Cement including 10 per cent wastage
Sand including 10 per cent wastage
Admixtures (anti shrinkage compound) @ 20 % of cost of cement
b)
Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
c)
Machinery
Grout pump with agitator and accessories
d&e) Overheads & Contractors Profit
Rate per kg = (a+b+c+d+e)
6
Patching of damaged concrete surface with polymer concrete
and curing compounds, initiator and promoter, available in
present formulations, to be applied as per instructions of
manufacturer and as approved by the Engineer as per Technical
Specification 2800 MORTH.
Unit = sqm
Taking output = 10 sqm for an average thickness of 25mm.
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b)
Material
Pre-packed polymer concrete based on epoxy system complete with
curing compound, initiator and promoter including 5 per cent wastage.

day
day
day
day

0.08
0.08
0.05

kg

1.10

day
day
day

0.10
0.18

hour

0.10

kg
kg

0.55
0.55

day
day
day

0.10
0.18

hour

0.10

day
day
day

0.75
0.81

kg

315.00

c)
Machinery
Grout pump with agitator and accessories
hour
d&e) Overheads & Contractors Profit
Cost for 10 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/10
Note : This item is a proprietary item available in market as pre-packed
polymer concrete and is required to be applied as per instructions of the
manufacturer.

2.00

648

RBR-RPRH
Index-code

S. No

Description

Unit

Quantity

Rate
(Rs.)

Amount
(Rs.)

2
Sealing of crack / porous concrete with Epoxy Grout by injection
through nipples complete as per clause 2803.1 MORTH

kg

1.10

day
day
day

0.10
0.18

hour

0.10

kg
kg
kg

2.50
2.20
2.00

day
day
day

0.50
0.54

day
day
day

0.54
0.50

hour
hour
hour

1.00
1.00
0.02

kg
cum
cum
kg
KL

120.00
0.15
0.15
2.50
0.10

Litre
kg

1.40
12.00

day
day

0.50

RBR-RPRH-7

Unit = kg
Taking output = 1 kg
a) Material
Epoxy including 10 per cent wastage
b)
Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
c)
Machinery
Epoxy Injection gun
d&e) Overheads & Contractors Profit
Rate per kg = (a+b+c+d+e)
8

RBR-RPRH-8

RBR-RPRH-9

RBR-RPRH-10

10

Applying epoxy mortar over leached, honey combed and spalled


concrete surface and exposed steel reinforcement complete as
per Technical Specification 2804 MORTH.
Unit = sqm
Taking output = 10 sqm
Assume average 10mm thickness of epoxy mortar
a) Material
Epoxy resin-hardener mix for prime coat
Epoxy mortar
Epoxy resin -hardener mix for seal coat.
Add 3 per cent cost of material for other consumables like acetone
etc and to cover wastage.
b)
Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Cost for 10 sqm = a+b+c+d
Rate per sqm = (a+b+c+d)/10
Removal of defective concrete, cleaning the surface thoroughly,
applying the shot Crete mixture mechanically with compressed
air under pressure, comprising of cement, sand, coarse
aggregates, water and quick setting compound in the proportion
as per clause 2807.1., sand and coarse aggregates conforming to
IS: 383 and table 1 of IS: 9012 respectively, water cement ratio
ranging from 0.35 to 0.50, density of gunite not less than 2000
kg/cum, strength not less than 25 Mpa and workmanship
conforming to clause 2807.6 MORTH.
unit: sqm
Taking output = 10 sqm, 40 mm average thickness.
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Skilled)
b) Machinery
Air compressor 250 cfm
Shotcreteing equipment
water tanker 6 KL capacity
c) Material
Cement
Sand
Coarse aggregate of size 4.75mm
Quick setting compound
Water
d&e) Overheads & Contractors Profit
Cost for 10 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/10
Applying pre-packed cement based polymer mortar of strength
45 Mpa at 28 days for replacement of spalled concrete as per
Unit = sqm
Taking output = 10 sqm
Assumed thickness - 10 mm
a) Material
Acrylic polymer bonding coat
pre-packed cement based polymer mortar of strength 45 Mpa at 28
days
Add 3 per cent of (a ) above for wastage.
b)
Labour
Mate
Mazdoor (Skilled)

649

RBR-RPRH
Index-code

RBR-RPRH-11

S. No

Description

Unit

Quantity

2
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Cost for 10 sqm = a+b+c+d
Rate per sqm = (a+b+c+d)/10
Epoxy bonding of new concrete to old concrete as per Technical
Specification 2805 MORTH.
Unit = sqm
Taking output = 10 sqm
a) Material
Epoxy resin with pot life not less than 60-90 minutes and satisfying
testing as per clause 2803.9
Add 3 per cent of (a ) above for wastage.
b)
Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Cost for 10 sqm = a+b+c+d
Rate per sqm = (a+b+c+d)/10
Providing external prestressing with high tensile steel
wires/strands including drilling for passage of prestessing steel,
all accessories for stressing and stressing operation and
grouting complete as per drawing and Technical Specification
2810 MORTH.
Span assumed: 25 m
No. of cables: 4 no.
No. of anchorages : 8 no.
Unit = MT
Taking output = 1 MT
Assume 12.7mm dia. Strand in 12T13 system. Weight-9.42 kg/m of
cable.
a) Material

3
day

4
0.54

kg

8.00

day
day
day

0.50
0.54

HTS strand including 5 per cent wastage and extra length for jacking

t
m
kg

1.05
112.00
400.00

11

12

RBR-RPRH-12

HDPE pipes 75mm dia including 5 per cent wastage


Cement for grouting

Rate
(Rs.)

Amount
(Rs.)

650

RBR-RPRH
Index-code

S. No

Description

Unit

Quantity

2
Tube anchorage set complete with bearing plate, permanent wedges
etc
Epoxy
MS plates for deviator (where deviator blocks are not provided)
Add 20 per cent cost of material for other materials like lead sheet,
sleeves, deviator fixtures etc.
b)
Labour
i) For making holes in the structure .
Mate
Mazdoor (Semi-skilled)
Mazdoor (Unskilled)
ii) For making and fixing anchorages for cables and placement of
cables .
Mate
Blacksmith
Mazdoor (Unskilled)
iii) For prestressing
Mate/Supervisor
Fitter
Mazdoor (Unskilled)
iv) For grouting
Mate/Supervisor
Mason
Mazdoor (Unskilled)
c)
Machinery
Stressing jack with pump
Grouting pump with agitator
d&e) Overheads & Contractors Profit
Rate per MT = (a+b+c+d+e)
Providing external prestressing with high tensile steel
wires/strands including drilling for passage of prestessing steel,
all accessories for stressing and stressing operation and
grouting complete as per drawing and Technical Specification
2810 MORTH.
Span assumed: 50 m
No. of cables: 4 no.
No. of anchorages : 8 no.
Unit = MT
Taking output = 3.10 MT
Assume 12.7mm dia. Strand in 19T13 system. Weight-14.73 kg/m of
cable.
a) Material

3
each

4
8.00

kg
t

6.00
2.10

day
day
day

3.00
3.24

day
day
day

3.00
8.44

day
day
day

0.70
2.78

day
day
day

0.70
2.78

hour
hour

4.00
1.35

HTS strand including 5 per cent wastage and extra length for jacking

t
m
t
each

3.10
224.00
1.01
8.00

kg
t

10.00
7.00

day
day
day

8.00
8.08

day
day
day

7.00
26.28

day
day
day

1.00
4.20

day
day
day

1.50
5.26

hour
hour

7.00
3.00

13

RBR-RPRH-13

HDPE pipes 90mm dia including 5 per cent wastage


Cement for grouting
Tube anchorage set complete with bearing plate, permanent wedges
etc
Epoxy
MS plates for deviator (where deviator blocks are not provided)
Add 20 per cent cost of material for other materials like lead sheet,
sleeves, deviator fixtures etc.
b)
Labour
i) For making holes in the structure .
Mate
Mazdoor (Semi-skilled)
Mazdoor (Unskilled)
ii) For making and fixing anchorages for cables and placement of
cables .
Mate
Blacksmith
Mazdoor (Unskilled)
iii) For prestressing
Mate/Supervisor
Fitter
Mazdoor (Unskilled)
iv) For grouting
Mate/Supervisor
Mason
Mazdoor (Unskilled)
c)
Machinery
Stressing jack with pump
Grouting pump with agitator
d&e) Overheads & Contractors Profit
Cost for 3.10 MT = a+b+c+d+e
Rate per MT = (a+b+c+d+e)/3.10

Rate
(Rs.)

Amount
(Rs.)

651

RBR-RPRH
Index-code

S. No

Description

Unit

Quantity

Rate
(Rs.)

Amount
(Rs.)

2
Providing external prestressing with high tensile steel
wires/strands including drilling for passage of prestessing steel,
all accessories for stressing and stressing operation and
grouting complete as per drawing and Technical Specification
2810 MORTH.
Span assumed: 100 m
No. of cables: 6 no.
No. of anchorages : 12 no.
Unit = MT
Taking output = 9.28 MT
Assume 12.7mm dia. Strand in 19T13 system. Weight-14.73 kg/m of
cable.
a) Material

t
m
t
each

9.28
672.00
3.04
12.00

kg
t

14.00
20.00

day
day
day

18.00
26.72

day
day
day

20.00
84.00

day
day
day

1.50
6.30

day
day
day

5.00
21.00

hour
hour

10.00
10.00

14

RBR-RPRH-14

HTS strand including 5 per cent wastage and extra length for jacking

HDPE pipes 90 mm dia including 5 per cent wastage


Cement for grouting
Tube anchorage set complete with bearing plate, permanent wedges
etc
Epoxy
MS plates for deviator (where deviator blocks are not provided)
Add 20 per cent cost of material for other materials like lead sheet,
sleeves, deviator fixtures etc.
b)
Labour
i) For making holes in the structure .
Mate
Mazdoor (Semi-skilled)
Mazdoor (Unskilled)
ii) For making and fixing anchorages for cables and placement of
cables .
Mate
Blacksmith
Mazdoor (Unskilled)
iii) For prestressing
Mate/Supervisor
Fitter
Mazdoor (Unskilled)
iv) For grouting
Mate/Supervisor
Mason
Mazdoor (Unskilled)
c)
Machinery
Stressing jack with pump
Grouting pump with agitator
d&e) Overheads & Contractors Profit
Cost for 9.28 MT = a+b+c+d+e
Rate per MT = (a+b+c+d+e)/9.28

652

RBR-RPRH
Index-code

RBR-RPRH-15

S. No

Description

Unit

Quantity

Rate
(Rs.)

Amount
(Rs.)

2
Replacement of Bearings complete as per Technical Specification
2808 MORTH
Unit = No
Taking output = 3 No.
Lifting of superstructure span by jacking up from below i.e. by placing
the jacks on pier/abutment caps for span length of 30m.

15

a) Lifting of span
i) Hire charges for jack of 40 tonne lifting capacity.
Day
Mate
day
Mazdoor (Skilled)
day
Mazdoor (Unskilled)
day
v) Wooden packing
cum
b)
Replacement of bearing
Cost of bearing.
each
c&d) Overheads & Contractors Profit
Cost of repair of 3 bearings = a+b+c+d
Rate of repair per bearing = (a+b+c+d)/3
Note : The work entails replacement of all the bearings on one side of the span.

RBR-RPRH-16

RBR-RPRH-17

16

17

Rectification of Bearings as per Technical Specifications 2808


MORTH
Unit = 1 No
Taking output = 3 No.
a) Lifting of superstructure span by jacking up from below i.e.
by placing the jacks on pier/abutment caps for span length of
30m.
i) Hire charges for jack of 40 tonne lifting capacity.
each
ii) Mate
day
iii) Mazdoor (Skilled)
day
iv) Mazdoor (Unskilled)
day
v) Wooden packing
cum
each
b) Cost of parts to be replaced for 3 bearings.
c&d) Overheads & Contractors Profit
Cost of repair of 3 bearings = a+b+c+d
Rate of repair per bearing = (a+b+c+d)/3
Note : The rectification of 3 bearings included in this analysis are on the
same side of the span.
Replacement of Expansion Joints complete as per drawings
Unit -1 RM
Taking output = 12 RM
a) Material
Epoxy for bonding new concrete to old concrete @ 0.8 kg/sqm
kg
M-30 grade cement concrete excluding OH & CP (Rate as per Chapter cum
14
b)
Labour
Removal of old expansion joint including breaking of concrete, cutting
of lugs and shifting of broken material etc.
Mate
day
Mazdoor (Unskilled)
day
Mazdoor (Skilled)
day
c&d) Overheads & Contractors Profit
Cost for replacement of 12 RM = a+b+c+d
Rate per RM = (a+b+c+d)/12
Note : The rate for the installation of new expansion joints may be taken from
the chapter on superstructure. Broken concrete will have to be replaced which
has been included in this analysis.

3.00
4.00
12.64
0.15
3.00

3.00
4.00
12.64
0.15
3.00

9.60
3.60

6.26
0.50

653

RBR-RPRH
Index-code

S. No
1

RBR-RPRH-18

18

Description
2
Replacement of Damaged Concrete Railing.
Unit = RM
Taking output = 10 RM
a) Labour

Unit

Quantity

Rate
(Rs.)

Amount
(Rs.)

Labour for dismantling old railing and disposal of dismantled material.

RBR-RPRH-19

19

Mate
day
Mazdoor (Unskilled)
day
b)
Machinery
Tractor-trolley for disposal of dismantled material
hour
c&d) Overheads & Contractors Profit
Cost for 10 m = a+b+c+d
Rate per metre = (a+b+c+d)/10
Note : The rate for the provision of new railing may be adopted from the
chapter on superstructure.
Replacement of Crash Barrier.
Unit = RM
Taking output = 10 M
a) Labour

5.20
1.00

Labour for dismantling old railing and disposal of dismantled material.

RBR-RPRH-20

20

Mate
day
Mazdoor (Unskilled)
day
b)
Machinery
Tractor-trolley for disposal of dismantled material
hour
c&d) Overheads & Contractors Profit
Cost for 10 m = a+b+c+d
Rate per metre = (a+b+c+d)/10
Note : The rate for the construction of new crash barrier may be adopted from
chapter 8 on Traffic and Transportation.
Replacement of Damaged Mild Steel Railing
Unit = RM
Taking output = 10 M
a) Labour

10.40
1.00

Labour for dismantling old railing and disposal of dismantled material.

Mate
Mazdoor (Unskilled)
b)
Machinery
Tractor-trolley for disposal of dismantled material
c&d) Overheads & Contractors Profit
Cost for 10 m = a+b+c+d
Rate per metre = (a+b+c+d)/10

RBR-RPRH-21

21

day
day

4.16

hour

1.00

Repair of Crash Barrier


Repair of concrete crash barrier with cement concert of M-30 grade by cutting
and trimming the damaged portion to a regular shape, cleaning the area to be
repaired thoroughly, applying cement concert after erection of proper form
work.

Unit = Running meter.


Taking output = 10 M.
It is assumed that damage is to the extent of 10 per cent of the
volume of concrete .This will require 0.30 cum of concrete.
a) Manpower
Mate
day
Mazdoor (Unskilled)
day
For dismantling and trimming the surface to a regular shape and
removal of damaged material.
b)
Material
M-30 grade cement concrete excluding OH & CP (Rate as per Chapter cum
14)
This may be priced based on the rate given the chapter of
superstructure.
c&d) Overheads & Contractors Profit
Cost for 10 m = a+b+c+d
Rate per m = (a+b+c+d)/10

1.04

0.30

654

RBR-RPRH
Index-code

S. No
1

RBR-RPRH-22

22

Description

Unit

Quantity

Rate
(Rs.)

Amount
(Rs.)

Repair of RCC Railing


Carrying out repair of RCC M30 railing to bring it to the original shape.

RBR-RPRH-23

23

Unit = Running meter.


Taking output = 10 M.
It is assumed that damage is to the extent of 10 per cent .
a) Material
M-30 grade cement concrete excluding OH & CP (Rate as per Chapter cum
14
HYSD bar reinforcement Rate as per Chapter 14 (Excluding OH & CP)
t
b)
Labour
Mate
day
Mazdoor (Unskilled)
day
For dismantling and trimming the surface to a regular shape and
removal of damaged material.
c&d) Overheads & Contractors Profit
Cost for 10 m = a+b+c+d
Rate per m = (a+b+c+d)/10
Repair of Steel Railing
Repair of steel railing to bring it to the original shape. It is assumed
that the damage to the steel railing is to the extent of 10 %.
Unit = Running meter.
Taking output = 10 M.
a) Material
Mild steel ISMC series
Flat iron
MS Bolt and nuts
Add 5 per cent of cost of material for painting.
b)
Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Cost of repair for10m = a+b+c+d
Rate of meter = (a+b+c+d)/10

0.10
0.01
0.216

kg
kg
kg

29.00
10.00
1.00

day
day
day

0.20
0.216

General Note :
The provisions towards Mate is included in the provision towards unskilled Mazdoor.

655

BLD-CSTN

Andhra Pradesh Standard Data


Buildings
Index-code

S No

Description

Unit

Quantity

BLD-CSTN-1
BLD-CSTN-1-1

BLD-CSTN-1-3

BLD-CSTN-1-4

BLD-CSTN-1-5

Amount
Rs.
6

MORTARS
1

Cement Mortar (1 : 1)
Unit : 1cum
A. MATERIALS:
Cement
Sand (including 5% wastage)
Seigniorage charges for sand
B. MACHINERY
- Nil C. LABOUR:
Man mazdoor for mixing mortar
Grand Total

BLD-CSTN-1-2

Rate
Rs.
5

kg.

1440.00

cum

1.05

cum

1.05

day

0.20

Cement Mortar (1 : 1.5)


Unit : 1cum
A. MATERIALS:
Cement
Sand (including 5% wastage)
Seigniorage charges for sand
B. MACHINERY
- Nil C. LABOUR:
Man mazdoor for mixing mortar
Grand Total
Cement Mortar (1 : 2)
Unit : 1cum
A. MATERIALS:
Cement
Sand (including 5% wastage)
Seigniorage charges for sand
B. MACHINERY
- Nil C. LABOUR:
Man mazdoor for mixing mortar
Grand Total
Cement Mortar (1 : 3)
Unit : 1cum
A. MATERIALS:
Cement
Sand (including 5% wastage)
Seigniorage charges for sand
B. MACHINERY
- Nil C. LABOUR:
Man mazdoor for mixing mortar
Grand Total
Cement Mortar (1 : 4)
Unit : 1cum
A. MATERIALS:
Cement
Sand (including 5% wastage)
Seigniorage charges for sand
B. MACHINERY
- Nil C. LABOUR:
Man mazdoor for mixing mortar

kg.

960.00

cum

1.05

cum

1.05

day

0.20

kg.

720.00

cum

1.05

cum
day

0.20

kg.

480.00

cum

1.05

cum

1.05

day

0.20

kg.

360.00

cum

1.05

cum

1.05

day

0.20

Grand Total

659

Remarks
7

BLD-CSTN
Index-code

S No

BLD-CSTN-1-6

1
6

BLD-CSTN-1-7

BLD-CSTN-1-8

Unit

Quantity

Cement Mortar (1 : 5)
Unit : 1cum
A. MATERIALS:
Cement
Sand (including 5% wastage)
Seigniorage charges for sand
B. MACHINERY
- Nil C. LABOUR:
Man mazdoor for mixing mortar
Grand Total
Cement Mortar (1 : 6)
Unit : 1cum
A. MATERIALS:
Cement
Sand (including 5% wastage)
Seigniorage charges for sand
B. MACHINERY
- Nil C. LABOUR:
Man mazdoor for mixing mortar
Grand Total
Cement Mortar (1 : 8)
Unit : 1cum
A. MATERIALS:
Cement
Sand (including 5% wastage)
Seigniorage charges for sand
B. MACHINERY
- Nil C. LABOUR:
Man mazdoor for mixing mortar
Grand Total

kg.

288.00

cum

1.05

cum

1.05

Rate
Rs.
5

Amount
Rs.
6

day

0.20

kg.

240.00

cum

1.05

cum

1.05

day

0.20

kg.

180.00

cum

1.05

cum

1.05

day

0.20

Kg
cum
cum

400.00
0.90
0.45

cum

0.90

cum

0.45

CONCRETE, DAMP PROOF COURSE &


REINFORCEMENT

BLD-CSTN-2
BLD-CSTN-2-1

Description

Plain Cement concrete Grade M20 - Nominal Mix


using 20mm metal with hand mixing
Unit : 1cum
A. MATERIALS:
Cement
Coarse aggregate 20mm
Fine aggregate (Sand)
Seigniorage charges for C.A
Seigniorage charges for F.A
B. LABOUR:

day
Mason 1st class
day
Mazdoor (unskilled)
kl
Water (including for curing)
Grand Total
Note : For Nominal Mix : Considering table 9 IS 456 : 2000,
the quantity of cement needed is 405 kgs / cum. Hence
proposed 400 kgs of cement for cum of CC M20

0.10
2.36
1.20

660

Remarks
7

BLD-CSTN
Index-code

BLD-CSTN-2-2

S No
1
10

Description

Unit

Quantity

Plain Cement concrete Grade M10 - Nominal Mix


upto Plinth level
using 40mm metal using concrete mixer
Unit : 1cum
A. MATERIALS:
Cement
Coarse aggregate 40mm
Fine aggregate (Sand)
Seigniorage charges for C.A
Seigniorage charges for F.A
Water (including for curing)
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity

Kg

220.00

cum
cum
cum

0.90
0.45
0.90

cum
kl

0.45
1.20

hour

1.00

day

0.10

day

1.39

Rate
Rs.
5

Amount
Rs.
6

C. LABOUR:
Mason 1st class
Mazdoor (unskilled)
Grand Total

BLD-CSTN-2-3

BLD-CSTN-2-4

11

12

13

BLD-CSTN-2-5

PCC Grade M15 - Nominal mix 1:2.5:5 (Hand


mixing)
Unit = 1cum
A) Material
Cement
Coarse sand
40 mm aggregate
20 mm aggregate
10 mm aggregate
Water (including for curing)
B) Labour
Mason (1st Class)
Mazdoor (Unskilled)
Grand Total
Plain Cement concrete (1:4:8) using 40 mm
metal with hand mixing upto Plinth level
Unit = 1cum
A. MATERIALS:
Cement
Coarse aggregate 40 mm
Fine aggregate (Sand)
Seigniorage charges for C.A
Seigniorage charges for F.A
Water (including for curing)
B. LABOUR:
Mason 1st class
Mazdoor (unskilled)
Grand Total
Plain Cement concrete (1:4:8) using 40 mm
metal with concrete mixture.
All work upto
plinth level.
Unit = 1cum
A. MATERIALS:
Cement
Coarse aggregate 40 mm
Fine aggregate (Sand)
Seigniorage charges for C.A
Seigniorage charges for F.A
Water (including for curing)
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity

kg

275.00

cum

0.48

cum

0.54

cum

0.27

cum

0.09

kl

1.20

day

0.10

day

2.36

kg

162.00

cum

0.90

cum

0.45

cum

0.90

cum

0.45

kl

1.20

day

0.10

day

2.36

kg

162.00

cum

0.90

cum

0.45

cum

0.90

cum

0.45

kl

1.20

hour

1.00

661

Remarks
7

BLD-CSTN
Index-code

S No
1

Description

Unit

Quantity

day

0.10

day

1.39
-

kg
cum

129.60
0.90

cum

0.45

cum

0.90

cum

0.45

kl

1.20

day

0.10

day

2.36

C. LABOUR:
Mason 1st class
Mazdoor (unskilled)
Water Charges 1%
Grand Total

BLD-CSTN-2-6

14

15

BLD-CSTN-2-7

Plain Cement concrete (1:5:10) using 40 mm


metal with hand mixing upto Plinth level
Unit = 1cum
A. MATERIALS:
Cement
Coarse aggregate 40 mm
Fine aggregate (Sand)
Seigniorage charges for C.A
Seigniorage charges for F.A
Water (including for curing)
B. LABOUR:
Mason 1st class
Mazdoor (unskilled)
Grand Total
Plain Cement concrete (1:5:10) using 40 mm
metal with Concrete mixture. All work upto

Rate
Rs.
5

Amount
Rs.
6

plinth level.
Unit = 1cum
A. MATERIALS:
Cement
Coarse aggregate 40 mm
Fine aggregate (Sand)
Seigniorage charges for C.A
Seigniorage charges for F.A
Water (including for curing)
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity
C. LABOUR:

BLD-CSTN-2-8

BLD-CSTN-2-9

16

17

Mason 1st class


Mazdoor (unskilled)
Grand Total
Plain Cement concrete (1:6:10) using 40 mm
metal with hand mixing upto Plinth level
Unit = 1cum
A. MATERIALS:
Cement
Coarse aggregate 40 mm
Fine aggregate (Sand)
Seigniorage charges for C.A
Seigniorage charges for F.A
Water (including for curing)
B. LABOUR:
Mason 1st class
Mazdoor (unskilled)
Grand Total
Plain Cement concrete (1:6:10) using 40 mm
metal with Concrete mixture upto Plinth level
Unit = 1cum
A. MATERIALS:
Cement
Coarse aggregate 40 mm
Fine aggregate (Sand)
Seigniorage charges for C.A
Seigniorage charges for F.A
Water (including for curing)

kg

129.60

cum

0.90

cum

0.45

cum

0.90

cum

0.45

kl

1.20

hour

1.00

day

0.10

day

1.39

kg

129.60

cum

0.90

cum

0.54

cum

0.90

cum

0.54

kl

1.20

day

0.10

day

2.36

kg

129.60

cum

0.90

cum

0.54

cum

0.90

cum

0.54

kl

1.20

662

Remarks
7

BLD-CSTN
Index-code

S No
1

Description

Unit

Quantity

hour

1.00

day

0.10

day

1.39

B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity
C. LABOUR:

BLD-CSTN-2-10

BLD-CSTN-2-11

BLD-CSTN-2-12

18

19

20

Mason 1st class


Mazdoor (unskilled)
Grand Total
Plain Cement concrete - Nominal Mix (1:3:6)
using 40mm metal with hand mixing
Unit : 1cum
A. MATERIALS:
Cement
Coarse aggregate 40mm
Fine aggregate (Sand)
Seigniorage charges for C.A
Seigniorage charges for F.A
Water (including for curing)
B. LABOUR:
Mason 1st class
Mazdoor (unskilled)
Grand Total
Plain Cement concrete (M 20) Nominal Mix using
40mm metal using concrete mixer
Unit : 1cum
A. MATERIALS:
Cement
Coarse aggregate 40mm graded
Fine aggregate (Sand)
Seigniorage charges for C.A
Seigniorage charges for F.A
Water (including for curing)
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity
C. LABOUR:
Mason 1st class
Mazdoor (unskilled)
Grand Total
Plain Cement concrete (M 15) Nominal Mix
1:2.5:5
using 40mm metal using concrete mixer
Unit : 1cum
A. MATERIALS:
Cement
Coarse aggregate 40mm
Coarse aggregate 20mm
Coarse aggregate 10mm
Fine aggregate (Sand)
Seigniorage charges for C.A
Seigniorage charges for F.A
Water (including for curing)
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity
C. LABOUR:
Mason 1st class
Mazdoor (unskilled)
Grand Total

Kg

220.00

cum

0.90

cum

0.45

cum

0.90

cum

0.45

kl

1.20

day

0.10

day

2.36

Kg

330.00

cum

0.90

cum

0.45

cum

0.90

cum

0.45

kl

1.20

hour

1.00

day

0.10

day

1.39

Kg

275.000

cum

0.540

cum

0.270

cum

0.090

cum

0.480

cum

0.900

cum

0.480

kl

1.20

hour

1.000

day

0.100

day

1.390

Rate
Rs.
5

Amount
Rs.
6

663

Remarks
7

BLD-CSTN
Index-code

BLD-CSTN-2-13

S No

Description

1
2
21 R.C.C. M-20 Nominal Mix
NEW RCC M- 20 Nominal mix (Cement:fine aggregate:

Unit

Quantity

cum
cum
Kgs

0.900
0.450
400.000

day
day
day

0.133
0.267
3.600

hour
Liters
Liters
kl

1.000
0.133
0.667
1.200

cum
cum
Kgs

0.900
0.450
400.000

day
day
day

0.167
0.167
4.700

hour
kl

1.000
1.200

cum
cum
Kgs

0.900
0.450
400.000

day
day
day

0.067
0.133
2.500

hour
kl

0.267
1.200

Rate
Rs.
5

Amount
Rs.
6

coarse aggregate) corresponding to Table 9 of IS


456 using 20mm size graded machine crushed hard
granite metal (coarse aggregate) from approved
quarry including cost and conveyance of all
materials like cement, fine aggregate (sand) coarse
aggregate, water etc., to site and including
Seigniorage charges, sales & other taxes on all
materials including all operational, incidental and
labour charges such as machine mixing, laying
concrete, curing etc.,complete but excluding cost of
steel and its fabrication charges for finished item of
work, but excluding centering, shuttering.

FOUNDATIONS, PLINTH, PEDESTALS (Below Plinth)

A. MATERIALS:
20mm HBG graded metal
Sand
Cement
B. LABOUR:
1st Class Mason
2nd Class Mason
Mazdoor (Both Men and Women)
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity
Cost of Diesel for Miller
Cost of Petrol for Vibrator
Water (including for curing)
BASIC COST per 1 cum
B

COLUMNS, LINTELS, WATER TANKS, RCC WALLS IN


BUILDINGS

A. MATERIALS:
20mm HBG graded metal
Sand
Cement
B. LABOUR:
1st Class Mason
2nd Class Mason
Mazdoor (Both Men and Women)

B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity
Water (including for curing)
BASIC COST per 1 cum
C

RCC SLABS, BEAMS

A. MATERIALS:
20mm HBG graded metal
Sand
Cement
B. LABOUR:
1st Class Mason
2nd Class Mason
Mazdoor (Both Men and Women)
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity
Water (including for curing)
BASIC COST per 1 cum

664

Remarks
7

BLD-CSTN
Index-code

S No

Description

Unit

Quantity

22

DESIGN MIX CONCRETE (WEIGH BATCH at


SITE) and placing of the Design Mix Concrete
Supply

Rate
Rs.
5

Amount
Rs.
6

corresponding to IS 456 using WEIGH BATCHER / MIXER


with 20mm size graded machine crushed hard granite
metal (coarse aggregate) from approved quarry including
cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site and
including Seigniorage charges, sales & other taxes on all
materials including all operational, incidental and labour
charges such as weigh batching, machine mixing, laying
concrete, curing etc.,complete but excluding cost of steel
and its fabrication charges for finished item of work (APSS
No. 402)with minimum cement content as per IS code from
standard suppliers approved by the department including
pumping, centering, shuttering, laying concrete, vibrating,
curing etc. complete but excluding cost of steel and its
fabrication charges for finished item of work.

BLD-CSTN-2-14

FOUNDATIONS, PLINTH, PEDESTALS (Below


Plinth)
ANY GRADE OF MIX
20mm HBG graded metal
Sand
1st Class Mason
2nd Class Mason
Mazdoor (Both Men & Women)
Weigh Batcher Hire charges (Machine mixing)
charges
Water (including for curing)
BASIC COST per 1 cum
COLUMNS, LINTELS, WATER TANKS, RCC
WALLS IN BUILDINGS
ANY GRADE OF MIX
20mm HBG graded metal
Sand
1st Class Mason
2nd Class Mason
Mazdoor (Both Men & Women)
Weigh Batcher Hire charges (Machine mixing)
Water (including for curing)
BASIC COST per 1 cum
RCC SLABS, BEAMS
ANY GRADE OF MIX
20mm HBG graded metal
Sand
1st Class Mason
2nd Class Mason
Mazdoor (Both Men & Women)
Weigh Batcher Hire charges (Machine mixing)
Water (including for curing)
BASIC COST per 1 cum

Excluding Cement cost

cum
cum
day
day
day
h

0.80
0.40
0.133
0.267
4.600
1.333

kl

1.200

cum
cum
day
day
day
H
kl

0.80
0.40
0.167
0.167
5.600
1.333
1.200

cum
cum
day
day
day
h
kl

0.80
0.40
0.067
0.133
3.077
0.308
1.200

Note : Quantity of cement proposed for various design mixes is for


estimating purpose only. Actual quantity of cement will be as per
approved mix design. Similarly quantity for coarse and fine
aggregates is for estimating purpose and the exact quantity shall be
as per the mix design. Nominal mix of grades M20 is to be used with
adequate supervision and quality control requirements.
For Design mix concrete, allow Cement as follows (for
estimate purpose only) :

Grade

Kgs

M 20

350

M 25
M 30
M 35
M 40

380
400
420
430

665

Remarks
7

BLD-CSTN
Index-code

S No
1
23

BLD-CSTN-2-15

Description

Unit

Quantity

Supply and placing of the Ready Mix (RMC)


Standard Design Mix Concrete grade as per IS
4926-2003 with minimum cement content as per
IS code 456-2000 using 20 mm graded metal,
from standard suppliers approved by the
department including pumping, laying concrete,
vibrating, curing etc. complete but excluding
cots of steel and its fabrication charges,
centering, shuttering for finished item of work.

Rate
Rs.
5

Amount
Rs.
6

Excluding Cement any


Grade.

FOUNDATIONS, PLINTH, PEDESTALS (Below Plinth)

Unit : 1cum
A. MATERIALS:
Coarse aggregate 20mm graded
Fine aggregate (Sand)
Seigniorage charges for C.A
Seigniorage charges for F.A
Water (including for curing)
B. MACHINERY
Batching plant at 20 cum per hour
Transit mixer 4cum capacity for lead upto 1km
Concrete Pump
C. LABOUR:
Mason 1st class
Mason 2nd class
Mazdoor (unskilled)
Grand Total
Note : Wherever concrete is carried out using
batching plant, transit mixer, concrete pump, then
Admixtures @ 0.4% of weight of cement may be
added for achieving desired slump of concrete. If
concentrated Admixture is proposed, only 0.04% of
weight of Cement shall be used.
B

cum

0.80

cum

0.40

cum

0.80

cum

0.40

kl

1.20

hour

0.222

hour

0.222

day

0.222

day

0.056

day

0.056

day

0.917

cum

0.80

cum

0.40

cum

0.80

cum

0.40

COLUMNS, LINTELS, WATER TANKS, RCC WALLS IN


BUILDINGS

Unit : 1cum

A. MATERIALS:
Coarse aggregate 20mm graded
Fine aggregate (Sand)
Seigniorage charges for C.A
Seigniorage charges for F.A
Water (including for curing)
B. MACHINERY
Batching plant at 20 cum per hour

kl

1.20

hour

0.444

Transit mixer 4cum capacity for lead upto 1km

hour

0.444

Concrete Pump
C. LABOUR:

day

0.444

Mason 1st class


Mason 2nd class
Mazdoor (unskilled)
Grand Total
RCC SLABS, BEAMS
Unit : 1cum

day

0.111

day

0.222

day

1.556

cum

0.80

cum

0.40

cum

0.80

cum

0.40

kl

1.20

A. MATERIALS:
Coarse aggregate 20mm graded
Fine aggregate (Sand)
Seigniorage charges for C.A
Seigniorage charges for F.A
Water (including for curing)

666

Remarks
7

BLD-CSTN
Index-code

S No

Description

Unit

Quantity

hour

0.133

hour
day

0.133
0.133

day

0.033

day

0.067

day

0.433

B. MACHINERY
Batching plant at 20 cum per hour
Transit mixer 4cum capacity for lead upto 1km
Concrete Pump
C. LABOUR:
Mason 1st class
Mason 2nd class
Mazdoor (unskilled)
Grand Total
For Design mix concrete, allow Cement as follows (for
estimate purpose only) :

Rate
Rs.
5

Grade

Kgs

M 20
M 25
M 30
M 35
M 40

350

Amount
Rs.
6

380
400
420
430

Note: LIFT CHARGES - for all RCC Items


1. For Lift Charges of Labour, increase @ 10% on labour charges for each upper
floor on Ground Floor Rate
2. For Lift Charges of Materials only, for lifting Concrete above 6.1 M (2nd floor
onwards)
Winch/ Lift hire charges may be allowed at following rates:

24

BLD-CSTN-2-16

Description of Structure

Basic Rate for 2nd


Floor (6.1 M)

a. FOUNDATIONS, PLINTH, PEDESTALS (Below Plinth)

Nil

for each
additional floor
(3.05 M) over
and above 2nd
floorNil
(6.1 M)

b. COLUMNS, LINTELS, WATER TANKS, RCC WALLS

1.333

Hrs

10%

c. RCC SLABS, BEAMS

0.267

Hrs

10%

kgs
cum

320.00
0.90

cum
cum
cum
L.S.

0.45
0.90
0.45

hour

1.00

Damp proof course 40mm thick with cement concrete


(1:2:4 Nominal mix), using 12mm hard broken stone
aggregate including cost of all materials, seigniorage
charges, excluding conveyance charges of materials,
including the cost of machinery, labour charges,
mixing, placing in position, leveling, vibrating, curing
etc. complete for finished item of work. (Using
concrete mixer)

Unit = 25 sqm
A. MATERIALS:
Cement
Coarse aggregate 12mm
Fine aggregate (sand)
Seigniorage charges of coarse aggregate

Seigniorage charges of sand


Form work
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity
C. LABOUR:
Mason 1st class
Mazdoor (unskilled)
D. Grand Total for 25 sqm
Rate per Sqm = D/25

day

0.1

day

1.98

667

Remarks
7

BLD-CSTN
Index-code

BLD-CSTN-2-17

S No

Description

Unit

Quantity

1
25

2
Damp proof course 50mm thick with 1:2:4 cement
concrete Nominal mix, using 12mm hard broken stone
aggregate including cost of all materials, seigniorage
charges, excluding conveyance charges of materials
including the cost of machinery, labour charges,
mixing, placing in position, leveling, vibrating, curing
etc. complete for finished item of work. (Using
concrete mixer)

kgs
cum
cum
cum
cum
L.S.

320.00
0.90
0.45
0.90
0.45

hour

1.00

day
day

0.1
1.98

1.05

kg

6.00

day
day

2.00

1.025

each

70.000

Hr

10.00

kg

6.00

Unit = 20 sqm
A. MATERIALS:
Cement
Coarse aggregate 12mm
Fine aggregate (sand)
Seigniorage charges of coarse aggregate

Seigniorage charges of sand


Form work
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity
C. LABOUR:
Mason 1st class
Mazdoor (unskilled)
D. Grand Total for 20 sqm
Rate per Sqm = D/20
26 Supplying, fitting and placing HYSD bar
11.7 reinforcement in foundation complete as per
drawings and technical specifications for Bars
BLD-CSTN-2-18
below 36 mm dia including over laps and
wastage, where they are not welded
1000 Unit = t
& (a) Material
1200
HYSD bars including 5 per cent for overlaps and
wastage
Binding wire
(b) Labour for cutting, bending, shifting to site,
tying and placing in position
Blacksmith / Bar bender
Mazdoor (Unskilled)
Sundries on Material
(c) Overheads on (a+b)
(d) Contractors profit on (a+b+c)
Rate per t = a+b+c+d
A Supplying, fitting and placing HYSD bar
reinforcement in foundation complete including
wastage, as per drawings and technical
specifications Clauses 1000 and 1202 MORD &
1100, 1600 MORTH for Bars 36 mm dia and
above, where welding required to be done
compulsorily.
1000 Unit = t
& (a) Material
1200

HYSD bars including 2.5 per cent for wastage


Welding Electrodes @ 5 per joint (14 joints / ton)
Welding Charges (Hire charges of Welding
Machine)
Binding wire

Rate
Rs.
5

Amount
Rs.
6

6.40

668

Remarks
7

BLD-CSTN
Index-code

S No

Description

Unit

Quantity

day

2.50

day

2.00

day

6.40

1.05

kg

6.00

day
day

2.00

27
11.8

BLD-CSTN-2-19

1000
&
1200

28
11.9

BLD-CSTN-2-20

1000
&
1200

(b) Labour for cutting, bending, shifting to site,


tying and placing in position
Welder
Blacksmith
Mazdoor (Unskilled)
(c) Overheads on (a+b)
(d) Contractors profit on (a+b+c)
Rate per t = a+b+c+d
Supplying,
fitting
and
placingTMT
bar
reinforcement in foundation complete as per
drawings and technical specifications for Bars
below 36 mm dia including over laps and
wastage, where they are not welded.
Unit = t
(a) Material
TMT bars including 5 per cent for overlaps and
wastage
Binding wire
(b) Labour for cutting, bending, shifting to site,
tying and placing in position
Blacksmith / Bar bender
Mazdoor (Unskilled)
(c) Overheads on (a+b)
(d) Contractors profit on (a+b+c)
Rate per t = a+b+c+d
Supplying,
fitting
and
placingTMT
bar
reinforcement in foundation complete including
wastage, as per drawings and technical
specifications Clauses 1000 and 1202 MORD &
1100, 1600 MORTH for Bars 36 mm dia and
above, where welding required to be done
compulsorily.
Unit = t
(a) Material
TMT bars including 2.5 per cent for wastage
Welding Electrodes @ 5 per joint (14 joints / ton)
Welding Charges (Hire charges of Welding
Machine)
Binding wire
(b) Labour for cutting, bending, shifting to site,
tying and placing in position
Welder
Blacksmith
Mazdoor (Unskilled)
(c) Overheads on (a+b)
(d) Contractors profit on (a+b+c)
Rate per t = a+b+c+d
Supplying, fitting and placing MS bar
reinforcement in foundation complete as per
drawings and technical specifications for Bars
below 36 mm dia including over laps and
wastage, where they are not welded
Unit = t
(a) Material
MS bars including 5 per cent for overlaps and
wastage
Binding wire

Rate
Rs.
5

Amount
Rs.
6

6.40

1.025

each

70.000

Hr

10.00

kg

6.00

day

2.50

day

2.00

day

6.40

1.05

kg

6.00

day
day

2.00

(b) Labour for cutting, bending, shifting to site, tying


and placing in position

Blacksmith / Bar bender


Mazdoor (Unskilled)

6.40

669

Remarks
7

BLD-CSTN
Index-code

S No
1

Description

Unit

Quantity

Rate
Rs.
5

Amount
Rs.
6

(c) Overheads on (a+b)


(d) Contractors profit on (a+b+c)
Rate per t = a+b+c+d

BLD-CSTN-3
BLD-CSTN-3-1

BRICK WORK, HONEY - COMBWORK


29
a
i

Brick Masonry in CM (1:3) with Bricks with


traditional size 23 x 11 x 7 cms 2nd class
Unit = 1cum
A. MATERIALS:
Cement
Bricks traditional size 23 x 11 x 7 cms 2nd class
Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:
Mason 1st class
nd

Mason 2 class
Mazdoor (unskilled)
Grand Total
Note : For Bricks 2.4 % wastage taken.
ii

Brick Masonry in CM (1:4) with Bricks traditional


size 23 x 11 x 7 cms 2nd class
Unit = 1cum
A. MATERIALS:
Cement
Bricks traditional size 23 x 11 x 7 cms 2nd class
Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:
Mason 1st class
nd

iii

Mason 2 class
Mazdoor (unskilled)
Grand Total
Brick Masonry in CM (1:5) with Bricks traditional
size 23 x 11 x 7 cms 2nd class
Unit = 1cum
A. MATERIALS:
Cement
Bricks traditional size 23 x 11 x 7 cms 2nd class
Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:
Mason 1st class
nd

Mason 2 class
Mazdoor (unskilled)
Grand Total

kg

96.00

Nos
cum

512.00
0.20

cum

0.20

day

0.24

day

0.56

day

1.89

kg

72.00

Nos

512.00

cum

0.20

cum

0.20

day

0.24

day

0.56

day

1.89

kg

57.60

Nos
cum

512.00
0.20

cum

0.20

day

0.24

day

0.56

day

1.89

670

Remarks
7

BLD-CSTN
Index-code

S No
1
iv

Description

Unit

Quantity

Brick Masonry in CM (1:6) with 2nd class Bricks


traditional size 23 x 11 x 7 cms
Unit = 1cum
A. MATERIALS:
Cement
Bricks traditional size 23 x 11 x 7 cms 2nd class
Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:
Mason 1st class
Mason 2nd class
Mazdoor (unskilled)
Grand Total
Brick Masonry in CM (1:8) with Bricks traditional
size 23 x 11 x 7 cms 2nd Class
Unit = 1cum
A. MATERIALS:
Cement
Bricks traditional size 23 x 11 x 7 cms 2nd class
Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:

kg

48.00

Nos
cum

512.00
0.20

cum

0.20

day

0.24

day

0.56

day

1.89

kg

36.00

Nos

512.00

cum

0.20

cum

0.20

Mason 1st class

day

0.24

Mason 2nd class


Mazdoor (unskilled)
Grand Total
Brick Masonry in CM (1:3) with Bricks
traditional size 23 x 11 x 7 cms 1st Class
Unit = 1cum
A. MATERIALS:
Cement
Bricks1st Class traditional size 23 x 11 x 7 cms
Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:

day

0.56

day

1.89

Mason 1st class


nd

kg

96.00

Nos

512.00

cum

0.20

cum

0.20

day

0.24

day

0.56

Mason 2 class
day
Mazdoor (unskilled)
Grand Total
Note : 1. When Mortar mix is changed as CM 1:4, 1:5, 1:6
and 1:8, proportionate quantity of cement has to be
substituted. No change in other data.

Rate
Rs.
5

Amount
Rs.
6

1.89

2. When First class Modular Bricks are used provide 570


nos bricks of size 19 x 9 x 9 cms.

671

Remarks
7

BLD-CSTN
Index-code

BLD-CSTN-3-2

S No
1
30
i

Description

Unit

Quantity

Brick Masonry in CM (1:3) with Modular Bricks


19 x 9 x 9 cms 2nd class
Unit = 1cum
A. MATERIALS:
Cement
Bricks modular size 19 x 9 x 9 cms 2nd class
Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:
Mason 1st class
nd

ii

Mason 2 class
Mazdoor (unskilled)
Grand Total
Brick Masonry in CM (1:4) with Modular Bricks
19 x 9 x 9 cms 2nd class
Unit = 1cum
A. MATERIALS:
Cement
Bricks modular size 19 x 9 x 9 cms 2nd class
Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:
Mason 1st class
nd

iii

Mason 2 class
Mazdoor (unskilled)
Grand Total
Brick Masonry in CM (1:5) with Modular Bricks
19 x 9 x 9 cms 2nd class
Unit = 1cum
A. MATERIALS:
Cement
Bricks modular size 19 x 9 x 9 cms 2nd class
Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:

iv

100.60
520.00
0.21

cum

0.21

day

0.24

day

0.56

day

1.89

kg

75.60

Nos
cum

520.00
0.21

cum

0.21

day

0.24

day

0.56

day

1.89

kg

60.48

Nos
cum

520.00
0.21

cum

0.21

Mason 1st class

day

0.24

Mason 2nd class


Mazdoor (unskilled)
Grand Total
Brick Masonry in CM (1:6) with Modular Bricks
19 x 9 x 9 cms 2nd class
Unit = 1cum
A. MATERIALS:
Cement
Bricks modular size 19 x 9 x 9 cms 2nd class
Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:

day

0.56

day

1.89

kg

50.40

Nos
cum

520.00
0.21

cum

0.21

day

0.24

Mason 2 class
Mazdoor (unskilled)
Grand Total
Brick Masonry in CM (1:8) with Modular Bricks
19 x 9 x 9 cms 2nd class
Unit = 1cum
A. MATERIALS:
Cement

day

0.56

day

1.89

kg

37.80

Bricks modular size 19 x 9 x 9 cms 2nd class

Nos
cum

520.00
0.21

cum

0.21

Mason 1st class


nd

iv

kg
Nos
cum

Fine aggregate (Sand)


Seigniorage charges for F.A
B. LABOUR:

Rate
Rs.
5

Amount
Rs.
6

672

Remarks
7

BLD-CSTN
Index-code

S No

Description

Unit

Quantity

3
day

4
0.24

day

0.56

day

1.89

nos

565.000

31

BLD-CSTN-3-3

Mason 1st class


Mason 2nd class
Mazdoor (unskilled)
Grand Total
11.5 cm wide Brick masonry for super-structure
on ground floor in cm (1:3) using second class
traditional size bricks including cost of all
materials, seigniorage charges, labour and all
operations for constructing half brick masonry,
mixing cement mortar, curing etc., complete for
finished item of work, but excluding conveyance
charges of materials.
unit:10sqm
A. MATERIALS:
Country bricks, second class traditional size
23x11x7cm
Cement
Sand
Seigniorage charges for sand
B. LABOUR:
Mason 1st class
Mason 2nd class
Mazdoor (unskilled)
Add water charges 1%
Grand Total

32

BLD-CSTN-3-4

BLD-CSTN-3-5

106.000
0.220

cum

0.220

day

0.600

day

0.600

day

Amount
Rs.
6

2.750
1.00%

Reinforced Brick Masonary walls of 11.5cm in CM(1:6)


using FlyAsh bricks having a crushing strength of not less
than 35.00kg/cm2 and using two mild steel bars of 6m dia
in every third layer of brick masory, with free joints of the
main block work including cost and seignorage charges
and conveyance of all materials and water from approved
sources to work site and all operational, incidental, labour
charges such as scaffolding mixing mortor constructing
masonary lift charges, curing etc. complete but excluding
the cost of steel and its fabrication charges for finished
item of work as per SS 509

Ground Floor :
A. MATERIALS:
II Class Bricks
C.M.(1:6)
B. LABOUR:

33

kg.
cum

Rate
Rs.
5

Mason 1st class


Mason 2nd class
Mazdoor (unskilled)
Grand Total
Exposed brick masonry for super structure on
ground floor in cm (1:6) using wire cut bricks or
moulded bricks including making horizontal and
vertical grooves 10mm Wide 12mm deep, cost of
all materials, seigniorage charges, labour and all
operations, mixing cement mortar, curing etc.,
complete for finished item of work, but
excluding conveyance charges of materials
unit:1cum
A. MATERIALS:
Wire cut bricks or moulded bricks size 19x9x9cm
Cement

cum

512.000

cum

0.200

day

0.600

day

0.600

day

2.750

nos
kg.

520.000
48.00

673

Remarks
7

BLD-CSTN
Index-code

S No

Description

Unit

Quantity

3
cum

4
0.20

cum

0.20

Sand
Seigniorage charges for sand
B. LABOUR:

34

BLD-CSTN-3-6

35

BLD-CSTN-3-7

36

BLD-CSTN-3-8

Rate
Rs.
5

Amount
Rs.
6

day
0.57
Mason 1st class
nd
day
0.57
Mason 2 class
day
2.54
Mazdoor (unskilled)
1.00%
Add water charges 1%
Grand Total
Note : Compressive strength of individual Brick
shall not be less than 70 kg / cm2
Brickwork in arches in cement mortar 1:4
complete including centering and shuttering
excluding pointing and plastering as per
drawing and technical specifications Clauses
606 and 1205.1 MORD
Unit = cum
a) Material
Nos.
525.00
Brick 1st class
cum
0.24
Cement mortar (1:4)
b) Labour
day
1.88
Mazdoor (Unskilled)
day
2.00
Mason (1st Class)
c) Add for centering and shuttering @ 110% of
(a+b)
Grand Total
Note : 1 ) In case cement mortar 1:3 is used, proportionate rate is to be adopted.

2) Quantity of bricks for arches will be about 10 per cent more than that for ordinary
brickwork .
3) In case special arch bricks are used, the quantity of bricks per cum shall be taken as
580 Nos.
4) Rates for spandrel walls shall be taken same as for brickwork in substructure.
5) Rate for spandrel filling will depend on the filling material adopted
6) Compressive strength of individual Brick shall not be less than 70 kg / cm2
Honey Comb work with Bricks of traditional Size
and Plastered One Coat 10 mm. thick Cement
Mortar 1:5 including White Washing 2 Coats
Unit = cum
a) Material
Brick 2nd class 23 x 11 x 7
Cement mortar (1:5)
b) Labour
Mazdoor (Unskilled)
Mason (1st Class)
Mason (2nd Class)
White Washing 2 Coats
Grand Total
Honey Comb work with Bricks of Modular Size
and Plastered One Coat 10 mm. thick Cement
Mortar 1:5 including White Washing 2 Coats
Unit = cum
a) Material
Brick 2nd class 19 x 9 x 9
Cement mortar (1:5)
b) Labour
Mazdoor (Unskilled)
Mason (1st Class)
Mason (2nd Class)
White Washing 2 Coats
Grand Total

Nos.

750.00

cum

0.67

day
day
day
LS

6.60
2.41
6.21
LS

Nos.

790.00

cum

0.67

day

6.60

day

2.41

day

6.21

LS

LS

674

Remarks
7

BLD-CSTN
Index-code

S No
1

Unit

Quantity

Rate
Rs.
5

Amount
Rs.
6

STONE MASONRY, DAMP PROOF COURSE,


DRY STONE PACKING, QUARRY RUBBISH &
GRAVEL BACKING

BLD-CSTN-4
BLD-CSTN-4-1

Description

37

Cut Stone Masonry in CM 1:2


Unit = 1cum
A. MATERIALS:
Cement
Cut Stone Roughly dressed to shape at quarry
Bond Stones
Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:
Mason 1st class
Mason 2nd class
Man mazdoor
Woman mazdoor
Grand Total

kg

115.20

cum

0.89

cum

0.16

cum

0.16

cum

0.16

day
day

1.05
2.45

day

3.50

day

2.80

Note : When Mortar mix is changed as CM 1:3, 1:4, 1:5, 1:6


and 1:8, proportionate quantity of cement has to be
substituted. No change in other data.

BLD-CSTN-4-2

38
i

ii

iii

CRS Masonry in CM (1:2) 1st Sort

Unit = 1cum
A. MATERIALS:
Cement
Coursed Rubble Stone
Bond Stones 7Nos 0.24 x 0.24 x 0.39 = 0.16cum
Fine aggregate (Sand)
Seigniorage charges for F.A
Seigniorage charges for Stone
B. LABOUR:
Mason 1st class
Mazdoor (unskilled)
Grand Total
CRS Masonry in CM (1:3) 1st Sort
Unit = 1cum
A. MATERIALS:
Cement
Coursed Rubble Stone
Bond Stones 7Nos 0.24 x 0.24 x 0.39 = 0.16cum
Fine aggregate (Sand)
Seigniorage charges for F.A
Seigniorage charges for Stone
B. LABOUR:
Mason 1st class
Mazdoor (unskilled)
Grand Total
CRS Masonry in CM (1:4) 1st Sort
Unit = 1cum
A. MATERIALS:
Cement
Coursed Rubble Stone
Bond Stones 7Nos 0.24 x 0.24 x 0.39 = 0.16cum
Fine aggregate (Sand)
Seigniorage charges for F.A
Seigniorage charges for Stone
B. LABOUR:
Mason 1st class
Mazdoor (unskilled)
Grand Total

kg

201.60

cum

0.94

7Nos.

0.16

cum

0.28

cum
cum

0.28
1.10

day
day

2.50
2.32

kg

134.40

cum

0.94

7Nos.

0.16

cum

0.28

cum
cum

0.28
1.10

day
day

2.50
2.32

kg

100.80

cum

0.94

7Nos.
cum

0.16
0.28

cum
cum

0.28
1.10

day
day

2.50
2.32

675

Remarks
7

BLD-CSTN
Index-code

S No
1
iv

BLD-CSTN-4-3

39

Description

Unit

Quantity

CRS Masonry in CM (1:6) 1st Sort


Unit = 1cum
A. MATERIALS:
Cement
Coursed Rubble Stone
Bond Stones 7Nos 0.24 x 0.24 x 0.39 = 0.16cum
Fine aggregate (Sand)
Seigniorage charges for F.A
Seigniorage charges for Stone
B. LABOUR:
Mason 1st class
Mazdoor (unskilled)
Grand Total

kg

67.20

cum

0.94

7Nos.
cum

0.16
0.28

cum
cum

0.28
1.10

day
day

2.50
2.32

kg

76.80

cum

0.94

cum

0.16

cum

0.32

cum

0.32

cum

1.10

day
Mason 1st class
day
Mazdoor (unskilled)
Grand Total
Note : When Mortar mix is changed proportionate quantity of
cement has to be substituted. No change in other data.

BLD-CSTN-4-4

Amount
Rs.
6

CRS Masonry in CM (1:6) 2nd Sort

Unit = 1cum
A. MATERIALS:
Cement
Coursed Rubble Stone
Bond Stones 7Nos 0.24 x 0.24 x 0.39 = 0.16cum
Fine aggregate (Sand)
Seigniorage charges for F.A
Seigniorage charges for Stone
B. LABOUR:

40

Rate
Rs.
5

1.50
2.32

Coursed rubble stone masonry arch (Ist sort) in


cement mortar (1:4) complete including
centering etc. complete as per drawing and
technical specifications Clauses 706 and 1205.1
Unit = cum
A. Material
Stone for CR masonry 1st sort
Through and bond stone (7 Nos 0.24x0.24x0.39 =
0.16 cum)
Cement mortar (Rate as in item 11.5 II)
B. Labour
Mason (1st Class)
Mazdoor (Unskilled)
C. Add for centering and shuttering @ 100 % of
(a+b)
Grand Total

cum

0.94

Nos.

0.16

cum

0.30

day

3.00

day

2.43

Note : 1) In case cement mortar 1:3 is used,


proportionate rate is to be adopted.
2) The addition for centering and sluttering at (c) above is for arch
above 6 m span. For lesser span length the addition shall be 80 per
cent for span above 4 m length and 50 per cent for spans less than
4 m.

BLD-CSTN-4-5

41

Ashlar Arch Work in Cement Mortar (1:4)

Unit = 1cum
A. MATERIALS:
Cement

kg

57.60

Cut Stone Roughly dressed to shape at quarry

cum

0.89

Bond Stones of Cutstone quality


Fine aggregate (Sand)
Seigniorage charges for F.A

cum

0.16
0.16

cum

0.16

676

Remarks
7

BLD-CSTN
Index-code

S No

Description

Unit

Quantity

Mason 1st class


Mason 2nd class
Mazdoor (unskilled)
Centering Charges
Grand Total
Rubble Arch Work in Cement Mortar (1:4)
Unit = 1cum
A. MATERIALS:
Cement
Seleted Stone of sizes as per specification
(including Bond Stones)
Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:
Mason 1st class
Mason 2nd class
Mazdoor (unskilled)
Centering Charges
Grand Total
Providing & Laying reinforced cement concrete
arch complete including centering and
shuttering excluding reinforcement as per
drawings and technical specifications Clauses
800, 900 and 1205.1
Unit = cum
RCC grade M20 nominal mix
a) Material
Cement
Coarse sand
20 mm aggregate
10 mm aggregate
b) Labour
Mason (1st Class)
Mazdoor (Unskilled)
c) Machinery
Concrete mixer 0.4/0.28 cum capacity

day

5.05

day

2.45

day

6.30

Rate
Rs.
5

Amount
Rs.
6

B. LABOUR:

BLD-CSTN-4-6

42

43

BLD-CSTN-4-7

LS

kg
cum

100.80
1.15

cum
cum

0.28
0.28

day

0.90

day
day

2.10
2.43

LS

0.40

cum

0.45

cum

0.54

cum

0.36

day

0.20

day

2.15

hour

0.40

d) Add for cost of centering and shuttering @ 50 per


cent of (a+b) per sqm of surface of arch soffit

II

Grand Total
RCC Grade M 25 (Design mix)
a) Material
Cement
Coarse sand
20 mm aggregate
10 mm aggregate
b) Labour
Mason (1st Class)
Mazdoor (Unskilled)
c) Machinery
Concrete mixer 0.4/0.28 cum capacity

0.38

cum

0.45

cum

0.54

cum

0.36

day

0.20

day

2.15

hour

0.40

d) Add for cost of centering and shuttering @ 50 per


cent of (a+b) per sqm of surface of arch soffit

Grand Total
Note : The additional cost of centering and shuttering @ 50 per cent
of cost of material and labour shall hold good for arch spans of 6 m
and above. For lesser length of spans, the corresponding additional
cost can be taken as 40 per cent for spans above 4 m length and 30
per cent for spans less than 4 m.

677

Remarks
7

BLD-CSTN
Index-code

S No

BLD-CSTN-4-8

1
44

BLD-CSTN-4-9

45

Description

Unit

Quantity

RR Masonry in CM (1:6)
Unit = 1cum
A. MATERIALS:
Cement
CR Stone
Rough Stone
Bond Stones 7Nos 0.24 x 0.24 x 0.39 = 0.16cum
Fine aggregate (Sand)
Seigniorage charges for F.A
Seigniorage charges for Stone
B. LABOUR:
Mason 1st class
Mazdoor (unskilled)
Grand Total
RR Masonry in CM (1:8)
Unit = 1cum
A. MATERIALS:
Cement
CR Stone
Rough Stone
Bond Stones 7Nos 0.24 x 0.24 x 0.39 = 0.16cum
Fine aggregate (Sand)
Seigniorage charges for F.A
Seigniorage charges for Stone
B. LABOUR:

kg

79.20

cum

0.44

cum

0.50

cum
cum

0.16
0.33

cum
cum

0.33
1.10

day

1.20

day

2.00

kg

59.40

cum

0.44

cum

0.50

cum
cum

0.16
0.33

cum
cum

0.33
1.10

day
Mason 1st class
day
Mazdoor (unskilled)
Grand Total
Note : When Mortar mix is changed proportionate quantity
of cement has to be substituted. No change in other data

BLD-CSTN-4-10

BLD-CSTN-4-11

46

47

Dry Stone Masonry for Retaining Walls


Unit = 1cum
A. MATERIALS:
Rough Stone
Bond Stones 7Nos 0.24 x 0.24 x 0.39 = 0.16cum
Seigniorage charges for Stone
B. LABOUR:
Mason 1st class
Mason 2nd class
Mazdoor (unskilled)
Grand Total
Dry Stone Masonry for Well steining
Unit = 1cum
A. MATERIALS:
Rough Stone
Bond Stones
Seigniorage charges for Stone
B. LABOUR:
Mason 1st class
Mason 2nd class
Mazdoor (unskilled)
Grand Total

Rate
Rs.
5

Amount
Rs.
6

Remarks
7

1.20
2.00

cum
cum

1.04
0.16

cum

1.20

day

0.33

day

0.77

day

1.10

cum
cum

1.04
0.16

cum

1.20

day

0.45

day

1.05

day

1.10

678

BLD-CSTN
Index-code

S No
1
48

BLD-CSTN-4-12

Description

Unit

Quantity

Damp Proof, Course Damp Proof (or anti Proof)


Course with Cuddapah / Shabad slabs 50 mm.
thick in CM (1:3)
(Unit - 10 sqm)
A. MATERIALS:
Cuddapah / Shabad slabs 50 mm. thick
Cement Mortar 1:3
Seigniorage charges for Stone
B. LABOUR:

sqm

10.50

cum

0.15

day

0.90

day

2.10

day

2.00

Mason 1st class


Mason 2nd class
Mazdoor (unskilled)
Grand Total

BLD-CSTN-5-2

49

50

Flush Pointing with CM (1:3) to Brick / CRS


Masonry
Unit = 10 sqm
A. MATERIALS:
Cement
Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:
Mason 2nd class
Mazdoor (unskilled)
Grand Total
Flush Pointing with CM (1:3) to RR Masonry
Unit = 10 sqm
A. MATERIALS:
Cement
Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:

BLD-CSTN-5-3

51

Mason 2nd class


Mazdoor (unskilled)
Grand Total
Raised Pointing with CM (1:3) to RR Masonry
Unit = 10 sqm
A. MATERIALS:
Cement
Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:
Mason 2nd class
Mazdoor (unskilled)
Grand Total

52

BLD-CSTN-5-4

Amount
Rs.
6

POINTING

BLD-CSTN-5
BLD-CSTN-5-1

Rate
Rs.
5

kg

14.40

cum

0.03

cum

0.03

day

0.50

day

0.74

kg

14.40

cum

0.03

cum

0.03

day

0.50

day

0.74

kg

28.80

cum

0.06

cum

0.06

day

0.50

day

0.74

cum

0.038

day
day

1.460
2.260

Raised and cut pointing on coursed or Ashlar stone


masonry or concrete block walling in white cement mortar
1 : 3 (1 white cement : 3 marble dust).

Details of cost for 10 sq.m


Materials :Cement mortar 1 :4
Labour :
Mason llnd class
Mazdoor (unskilled)
Add for water charges @ 1 %
Add for contractor's profit and overheads @ 10%
Cost for 10 sq.m.
Cost per sq.m

Note : When Mortar mix is changed as CM 1:4


proportionate quantity of cement has to be substituted. No
change in other data.

679

Remarks
7

BLD-CSTN
Index-code

S No
1

BLD-CSTN-6
BLD-CSTN-6-1

Description

Unit

Quantity

cum

0.15

cum

0.15

day

0.60

day

0.96

cum

0.15

cum

0.15

day

0.60

day

0.96

BLD-CSTN-6-3

cum

0.150

cum

0.150

day

0.60

day

0.96

BLD-CSTN-6-4

cum

0.15

cum

0.15

day

0.60

day

0.96

BLD-CSTN-6-5

cum

0.15

cum

0.15

day

0.60

day

0.96

Amount
Rs.
6

PLASTERING
53

Plastering with CM (1:3), 12 mm thick


Unit = 10 sqm
A. MATERIALS:
Cement Mortar (1:3)
Seigniorage charges for F.A
B. LABOUR:

BLD-CSTN-6-2

Rate
Rs.
5

54

55

56

57

Mason 1st class


Mazdoor (unskilled)
Grand Total
Plastering with CM (1:4), 12 mm thick
Unit = 10 sqm
A. MATERIALS:
Cement Mortar (1:4)
Seigniorage charges for F.A
B. LABOUR:
Mason 1st class
Mazdoor (unskilled)
Grand Total
Plastering with CM (1:5), 12 mm thick
Unit = 10 sqm
A. MATERIALS:
Cement Mortor (1:5)
Seigniorage charges for F.A
B. LABOUR:
Mason 1st class
Mazdoor (unskilled)
Grand Total
Plastering with CM (1:6), 12 mm thick
Unit = 10 sqm
A. MATERIALS:
Cement Mortor (1:6)
Seigniorage charges for F.A
B. LABOUR:
Mason 1st class
Mazdoor (unskilled)
Grand Total
Plastering with CM (1:8), 12 mm thick
Unit = 10 sqm
A. MATERIALS:
Cement Mortor (1:5)
Seigniorage charges for F.A
B. LABOUR:
Mason 1st class
Mazdoor (unskilled)
Grand Total

680

Remarks
7

BLD-CSTN
Index-code

S No

BLD-CSTN-6-6

1
58

Description

Unit

Quantity

cum

0.19

cum

0.19

day

0.60

day

0.96

BLD-CSTN-6-8

59

cum

0.210

cum

0.21

day

0.94

day

1.60

60

cum

0.210

cum

0.21

61

BLD-CSTN-6-9

Mason 2nd class


Mazdoor (unskilled)
Grand Total
Plastering with CM (1:4), 20 mm thick
Unit = 10 sqm
A. MATERIALS:
Cement Mortar (1:4)
Seigniorage charges for F.A
B. LABOUR:
Mason 2nd class
Mazdoor (unskilled)
Grand Total
Plastering with CM (1:3), 20 mm thick
Unit = 10 sqm
A. MATERIALS:
Cement Mortar (1:3)
Seigniorage charges for F.A
B. LABOUR:

day
Mason 2nd class
day
Mazdoor (unskilled)
Grand Total
Note : When Mortar mix is changed proportionate quantity of
cement has to be substituted
Plastering with CM 2 coats, 20 mm thick, base
coat in CM (1:6), 16mm thick and top coat in CM
(1:4), 4mm thick with Dubara sponze finishing.

Unit = 10 sqm
A. MATERIALS:
Base Coat in CM(1:6), 16 mm thick
Cement
Fine aggregate (Sand)
Top Coat in CM(1:4), 4 mm thick
Cement
Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:

BLD-CSTN-6-10

Remarks
7

Plastering with CM 2 coats, 12 mm thick, base


coat in CM (1:5), 8mm thick and top coat in CM
(1:3), 4mm thick with sponze finishing.
Unit = 10 sqm
A. MATERIALS:
Base Coat in CM(1:5), 8 mm thick
Cement
Fine aggregate (Sand)
Top Coat in CM(1:3), 4 mm thick
Cement
Fine aggregate (Sand)

0.94
1.60

kg

43.00

cum

0.18

kg

14.50

cum

0.04

cum

0.22

day
Mason 1st class
nd
day
Mason 2 class
day
Mazdoor (unskilled)
Grand Total
Note : When Mortar mix is changed proportionate quantity of
cement has to be substituted
62

Amount
Rs.
6

Plastering with CM (1:4), 15 mm thick


Unit = 10 sqm
A. MATERIALS:
Cement Mortar (1:4)
Seigniorage charges for F.A
B. LABOUR:

BLD-CSTN-6-7

Rate
Rs.
5

0.63
1.47
3.90

kg

31.70

cum

0.11

kg

19.20

cum

0.04

681

BLD-CSTN
Index-code

S No
1

Description

Unit

Quantity

3
cum

4
0.15

Seigniorage charges for F.A


B. LABOUR:

63

BLD-CSTN-6-11

day
Mason 1st class
nd
day
Mason 2 class
day
Mazdoor (unskilled)
Grand Total
Note : When Mortar mix is changed proportionate quantity of
cement has to be substituted
RCM FACIA WORKS
RCM facia 5cm thick in CM (1:3) for drop walls, fins with
rabbit wire mesh & nominal reinforcement as directed by
Engineer-in-charge with dubara sponge finishing, including
cost & conveyance of all materials to site, seigniorage
charges, sales & other taxes on all materials, operational &
incidental, cost and conveyance of cement, wire mesh, water
to work site, centering, scaffolding and form work, lift
charges etc., complete for finished items of work but
excluding cost of steel & its fabrication charges, for finished
item of work. (APSS No.403 & 903)

Unit - 10 sqm
A) MATERIALS
Rabbit wire mesh (1.0 M panna for 0.6 M drop)
Cement Mortar 1:3 for 25 mm thick
Dry Cement for making Lumps
12 mm Plastering 2 coats in 1:4 & 1:2 cm both sides
Excluding HYSD Steel/ Mild steel & Binding wire
B) LABOUR CHARGES
1st Class Mason
Miller Operator
Mazdoor (unskilled)
c) Machinery
Machine Mixing Mortar with Miller - Hire charges
BASIC COST per 10 sqm
64

BLD-CSTN-6-12

sqm

Rate
Rs.
5

Amount
Rs.
6

0.63
1.47
3.90

13.30

cum

0.25

kg

50.00

sqm

21.80

day

8.00

day

1.00

day

10.00
32.00

Hrs

2.00

cum

0.110

20 mm thick rough cast exterior cement plaster on walls


upto height of 10 metres above ground level consisting of
10 mm thick backing coat of 1 : 3 cement mortar (1
cement : 3 sand) and 10 mm thick finishing coat of 1 : 3
cement mortar (1 cement : 3 coarse aggregate of size 6
mm to 10 mm) including arrises, chamfers and/or rounded
angles not exceeding 80 mm in girth.

Details of cost for 10 sq.m


Materials :Cement mortar 1:3 (1 cement: 3 sand)
Cement mortar 1:3(1 cement: 3 coarse aggregate of
size 6 mm to 10 mm)
Cement
Coarse aggregate of size 6 mm -10 mm
Mazdoo (unskilled) for mixing mortar with coarse
aggreagate 6 - 10 mm
Labour for backing coat and finishing coat Plaster work :
Mason, llnd class
Mazdoo (unskilled)
Extra labour for scooping :
Mason, llnd class
Mazdoor (male)
Add for water charges @ 1 %
Cost for 10 sq.m.
Cost per sq.m

kg

52.800

cum

0.110

day

0.020

day
day

1.710
3.270

day
day

0.250
0.250

682

Remarks
7

BLD-CSTN
Index-code

S No
1
65

BLD-CSTN-6-13

Description

Unit

Quantity

cum

0.224

cum

0.100

kg

9.280

day
day

1.710
3.270

day
day

0.500
1.000

kg

6.000

kg

6.000

Rate
Rs.
5

Amount
Rs.
6

Rough cast exterior cement plaster on walls upto a


height of 10 metres above ground level with a
mixture of sand and gravel or crushed stone graded
from 6 mm to 10 mm nominal size dashed over and
including fresh plaster in two coats, backing coat 10
mm cement plaster 1 : 3 (1 cemen" : 3 sand) and
finishing coat 10 mm cement plaster with cement
mortar 1:3 (1 cement: 3 sand) mixed with 10% finely
grounded hydrated lime by volume of cement
including arrises, chamfers and/or rounded angles
not exceeding 80 mm in girth.

(a) Natural cement finish using ordinary cement.


Details of cost for 10 sq.m.
Materials :
Cement mortar 1:3 (1 cement: 3 sand)
Sand and gravel or crushed stone graded from 6
mm to 10 mm nominal size
Coarse aggregate of size 6 mm -10 mm
Carriage
Grounded hydrated lime
Carriage
Labour for backing coat and finishing coat Plaster work :
Mason, llnd class
Mazdoo (unskilled)
Add labour for dashing crushed stone
Mason 1st class
Mazdoo (unskilled)
Add for water charges @ 1 %
Cost for 10 sq.m.
Cost per sq.m
(b) Dark coloured finish using ordinary cement
and pigment
Details of cost for 10 sq.m.
Same rate as per (a) above item ()
Add cost of colour
Add for water charges @ 1 %
Add for contractor's profit and overheads
Cost for 10 sq.m.
Cost per sq.m
(c) Light coloured finish using white cement
and pigment
Details of cost for 10 sq.m.
Same rate as per (a) above item ()
Add cost of light colour
Add for water charges on cost of colour @ 1 %
Add for contractor's profit and overheads on cost of
colour and water charges
Cost for 10 sq.m.
Cost per sq.m

683

Remarks
7

BLD-CSTN
Index-code

S No

Description

Unit

Quantity

1
66

2
Pebble dash exterior plaster on walls upto a height of 10
metres above ground level with a mixture of washed
pebble or crushed stone graded from 6 mm to 12 mm
nominal size dashed over and including fresh cement
plaster in two coats, backing coat 10 mm cement plaster 1
: 3 (1 cement : 3 sand) and finishing coat 10 mm cement
plaster 1 : 3 (1 cement : 3 sand) mixed with 10% finely
grounded hydrated lime by volume of cement including
arrises, chamfers and/or rounded angles not exceeding 80
mm in girth

Details of cost for 10 sq.m


Materials :
Cement mortar 1:3
Grounded hydrated lime
Pebbles or crushed stone graded from 6 mm to 12
mm nominal size

cum
kg

0.224
9.280

Crushed stone / Pebble of size 6 mm -12 mm

cum

0.100

day
day

1.710
3.270

day
day

0.500
0.610

cum

0.023

day
day

0.300
0.350

cum

0.023

day
day

0.300
0.350

cum

0.023

day
day

0.380
0.430

BLD-CSTN-6-14

Labour for backing coat and finishing coat :Mason llnd class
Mazdoor (unskilled)
Labour for pebble dashing
Mason llnd class
Mazdoor (unskilled)
Add for water charges @ 1 %
Cost for 10 sq.m.
Cost per sq.m
Plain Cement Mortar Bands :
67

BLD-CSTN-6-15

20 mm thick plain cement mortar bands in cement


mortar 1 : 4 (1cement : 4 sand) upto 300 mm in
width
(a) Flush Band :Details of cost for 10 metres long and 10 cm wide
band
Materials :Cement mortar 1 :4
Labour :
Mason llnd class
Mazdoor (unskilled)
Add for water charges @ 1 %

Rate
Rs.
5

Amount
Rs.
6

Cost for 10 metres long and 10 cm wide band


Cost per cm width x metre long
b) Sunk band :Details of cost for 10 metres long and 10 cm wide
band
Materials :Cement mortar 1 :4
Labour :
Mason llnd class
Mazdoor (unskilled)
Add for water charges @ 1 %
Cost for 10 metres long and 10 cm wide band
Cost per cm width x metre long
C) Raised Band :Materials :Cement mortar 1 :4
Labour :
Mason llnd class
Mazdoor (unskilled)
Add for water charges @ 1 %
Cost for 10 metres long and 10 cm wide band
Cost per cm width x metre long

684

Remarks
7

BLD-CSTN
Index-code

BLD-CSTN-6-16

S No

Description

Unit

Quantity

1
68

cum

0.224

day
day

2.200
2.700

cum

0.224

day
day

2.500
3.000

cum

0.224

day
day

3.000
3.500

cum

0.023

day
day

0.870
0.920

20 mm thick plain cement mortar bands in cement


mortar 1:4(1 cement: 4 sand) above 300 mm in
width
(A) Flush Band :Details of cost for 10 sq.m
Materials :Cement mortar 1 :4
Labour :
Mason llnd class
Mazdoor (unskilled)
Add for water charges @ 1 %
Cost for 10 sq.m.
Cost per sq.m
(B) Sunk band :Details of cost for 10 sq.m
Materials :Cement mortar 1 :4
Labour :
Mason llnd class
Mazdoor (unskilled)
Add for water charges @ 1 %
Cost for 10 sq.m.
Cost per sq.m
(C) Raised band
Details of cost for 10 sq.m
Materials :Cement mortar 1 :4
Labour :
Mason llnd class
Mazdoor (unskilled)
Add for water charges @ 1 %
Cost for 10 sq.m.
Cost per sq.m
Moulded Cement Mortar Bands 15 mm

BLD-CSTN-6-17

69

Rate
Rs.
5

Amount
Rs.
6

15 mm thick moulded cement mortar band in


cement mortar 1 : 4 (1cement: 4 sand)
Details of cost for 10 metres long and 10 cm wide
band
Materials :Cement mortar 1 :4
Labour :
Mason llnd class
Mazdoor (unskilled)
Add for water charges @ 1 %
Cost for 10 metres long and 10 cm wide band
Cost per cm width x metre long

70

BLD-CSTN-6-18

Masonry work in CM (1:8) prop with Flyash


Cement solid blocks of size 290 x 225 x 140 mm
for manufacturing of flyash solid blocks using
flyash of 80 kgs, cement of 15 kgs. Gypsum of 5
kgs. and stone dust including cost and
conveyance of all materials, labour charges,
seiniorage charges, scaffolding and curing etc.,
cpomplete with a compresive streangth not
lessthan 50 kg/sqm for walls for Superstructure
Walls.
Ground Floor
Unit = 1 cum
A. MATERIALS:
No of blocks required for one cum of Masonry
Cost of Cement Mortar (1:6)

day

110.000

cum

0.100

B. LABOUR
Mason 1st class

day

0.420

685

Remarks
7

BLD-CSTN
Index-code

S No

Description

Unit

Quantity

3
day

4
0.920

day
day

0.700
2.100

Polished Shabad Stone (White) (0.457 x 0.457m)


SSR item No. (36)

sqm

11.00

Cement for CM (1:8) proportion for base coat

kg.

21.60

Cement for slurry


Cement for jointing
Sand for CM (1:8) proportion
Seigniorage charges of sand
B. LABOUR:

kg.

33.00

kg.

20.00

cum

0.12

cum

0.12

day

3.10

day

1.10

day

0.86

sqm

10.50

Cement for CM (1:8) proportion for base coat

kg.

21.60

Cement for CM 1:3 proportion for pointing


Sand for CM (1:8) proportion
Sand for CM (1:3) proportion
Seigniorage charges of sand
B. LABOUR:

kg.

9.60

cum

0.12

cum

0.02

cum

0.14

day

0.960

day

2.240

day

3.30

Mason 2nd class


Man Mazdoor
Woman Mazdoor
Total

Rate
Rs.
5

Amount
Rs.
6

FLOORING

BLD-CSTN-7
71

BLD-CSTN-7-1

Flooring with 25mm thick polished shabad


stones set over base coat of CM (1:8) over
already laid CC bed / RCC Roof Slab, including
neat cement slurry of honey like consistency
spread @ 3.3 kgs per sqm. & Jointed with neat
cement to full depth including cost of all
materials like cement, sand, and water and
flooring stones etc., complete, including
seigniorage charges, labour charges for
dressing of flooring stones etc., complete for
finished item of work, but excluding the cost of
conveyance of all materials.
Unit = 10 sqm
A. MATERIALS:

72

BLD-CSTN-7-2

Mason 1st class


Mason 2nd class
Mazdoor (unskilled)
Add water charges 1%
Grand Total
Flooring
with
40
mm
thick
Rough
Cuddapah/Shabad stones, set over base coat of
cement mortar (1 : 8) 12 mm thick over CC bed
already laid or RCC roof slab, including pointing
with cement mortar 1:3 duly filling joints nearly,
including cost of all materials like flooring
stone, cement, sand, and water etc., complete,
including seigniorage charges, labour charges
for dressing of flooring stones etc., complete for
finished item of work, but excluding the cost of
conveyance of all materials.
Unit = 10 sqm
A. MATERIALS:
Rough Cuddapah/Shabad stones (40 mm thick)
(0.457 x 0.457 m)

Mason 1st class


Mason 2nd class
Mazdoor (unskilled)
Add water charges 1%
Grand Total

686

Remarks
7

BLD-CSTN
Index-code

S No
1
73

BLD-CSTN-7-3

Description

Unit

Quantity

sqm

10.10

kg.

48.00

kg.

33.00

kg.
cum

5.00
0.20

cum

0.20

day

1.00

day

2.10

day

3.00

day

5.00

sqm

10.05

Cement for CM (1:6) proportion for base coat

kg.

28.80

Cement for slurry


Cement for jointing & pointing
Pigment
Sand for CM (1:6) proportion
Seigniorage charges of sand
B. MACHINERY
Nill
C. LABOUR

kg.

33.00

kg.

6.00

Mason 1st class


Mason 2nd class
Mazdoor (unskilled)
Add water charges 1%
Grand Total

BLD-CSTN-7-4

Amount
Rs.
6

Flooring with polished marble slab 20 mm thick


set over base coat of cement mortar (1:6) 20 mm
thick (joints of stone must be flushed) over CC
bed already laid or RCC roof slab, including near
cement slurry of honey like consistency spread
@ 3.30 kgs per sqm. Jointed with neat cement to
full depth mixed with pigment of matching
shade, including cost of all materials like
flooring slab, cement, sand, and water etc.,
complete, including seigniorage charges, labour
charges for dressing, rubbing and polishing of
flooring stones etc., complete for finished item
of work, but excluding the cost of conveyance
of all materials.
Unit = 10 sqm
A. MATERIALS:
Marble slab of size 0.305 M x 0.305 M
Cement for CM (1:6) proportion for base coat
Cement for slurry for bedding
White Cement for pointing
Sand for CM (1:6)
Seigniorage charges of sand
B. Machinery
Machine for rubbing of floor
C. LABOUR:

74

Rate
Rs.
5

Flooring with chequrred terrazzo tiles of 22 mm thick


(medium shade) set over base coat of cement mortar
(1:6) 12 mm thick over CC bed already laid or RCC roof
slab, including near cement slurry of honey like
consistency spread @ 3.3.kgs per sqm & jointed with
neat cement to full depth mixed with pigment of
matching shade including cost of all materials like
cement, sand water and tiles etc., complete, including
seigniorage charges, complete for finished item of
work, but excluding the cost of conveyance of all
materials.

Unit = 10 sqm
A. MATERIALS:
Chequerred terrazzo tiles of 22 mm thick (medium
shade)

Mason 2nd class


Man mazdoor
Mazdoor (unskiled)
Add water charges 1%
Grand Total

kg.
cum

0.12

cum

0.12

day

0.960

day

2.240

day

3.30

687

Remarks
7

BLD-CSTN
Index-code

S No
1
75

BLD-CSTN-7-5

76

BLD-CSTN-7-6

Description

Unit

Quantity

Vitrified tiles of 1st quality of size


Cement for CM (1:8) for base coat
Cement for slurry
Cement for Pointing with CM (1:3)
Sand for CM (1:8)
Sand for pointing
Seigniorage charges of sand
B. LABOUR

sqm

10.10

kg.

21.60

kg.

33.00

kg.

6.000

Mason 1st class


Mason 2nd class
Mazdoor (unskiled)
Add water charges 1%
Grand Total
Flooring with ceramic tiles, set over base coat of
cement mortar (1:8), 12 mm thick over CC bed
already laid or RCC roof slab, including neat
cement slurry of honey like consistency spread
@ 3.3.kgs per sqm & jointed neatly with white
cement paste to full depth mixed with pigment
of matching shade, including cost of all
materials like cement, sand water and tiles etc.,
complete, including seigniorage charges, etc.,
complete for finished item of work, but
excluding the cost of conveyance of all
materials.
Unit = 10 sqm
A. MATERIALS:
Ceramic tiles
Cement for CM (1:8) for base coat
Cement for slurry
White cement
Sand for CM (1:8)
Seigniorage charges of sand
B. LABOUR

Rate
Rs.
5

Amount
Rs.
6

Flooring with vitrified tiles of 1st quality, set over


base coat of cement mortar (1:8), 12 mm thick
over CC bed already laid or RCC roof slab,
including neat cement slurry of honey like
consistency spread @ 3.3.kgs per sqm & jointed
neatly with white cement paste to full depth
mixed with pigment of matching shade,
including cost of all materials like cement, sand
water and tiles etc., complete, including
seigniorage charges, etc., complete for finished
item of work, but excluding the cost of
conveyance of all materials.
Unit = 10 sqm
A. MATERIALS:

Mason 1st class


Mason 2nd class
Mazdoor (unskiled)
Add water charges 1%
Grand Total

cum

0.12

cum

0.020

cum

0.140

day

0.96

day

2.24

day

3.30
1.00%

sqm

10.10

kg.

21.60

kg.

33.00

kg.

2.00

cum

0.12

cum

0.12

day

0.96

day

2.24

day

3.30
1.00%

688

Remarks
7

BLD-CSTN
Index-code

S No
1
77

BLD-CSTN-7-7

Description

Unit

Quantity

sqm

10.10

kg.

36.00

kg.

33.00

kg.

6.00

Flooring with high polished granite 16 to 18 mm


mm thick slabs other than black set over base
coat of cement mortar (1:8), 20 mm thick over
CC bed already laid or RCC roof slab, including
neat cement slurry of honey like consistency
spread @ 3.3.kgs per sqm & jointed neatly with
white cement paste mixed with pigment of
matching shade to full depth, including cost of
all materials like cement, sand water and
tilesetc., complete, including seigniorage
charges, labour charges for dressing of tilesetc.,
complete for finished item of work, but
excluding the cost of conveyance of all
materials
Unit = 10 sqm
A. MATERIALS:
High polished granite 16 to 18 mm thick slab other
than black
Cement for CM (1:8) for base coat
Cement for slurry
White cement for jointing & pointing
Cement for jointing
Sand for CM (1:8)
Seigniorage charges of sand
B. LABOUR
Mason 1st class
Mason 2nd class
Mazdoor (unskiled)
Add water charges 1%
Grand Total

78

BLD-CSTN-7-8

Rate
Rs.
5

Amount
Rs.
6

kg.
cum

0.20

cum

0.20

day

3.00

day

1.00

day

8.00
1.00%

Flooring with marble tiles polished 8 mm thick set


over base coat of cement mortar (1:8), 12 mm thick
over CC bed already laid or RCC roof slab, including
neat cement slurry of honey like consistency spread @
3.3.kgs per sqm & jointed neatly with white cement
paste mixed with pigment of matching shade to full
depth, including cost of all materials like cement, sand
water and tiles etc., complete, including seigniorage
charges, etc., complete for finished item of work, but
excluding the cost of conveyance of all materials

Unit = 10 sqm
A. MATERIALS:
Marble tiles polished 8 mm thick
Cement for CM (1:8) for base coat
Cement for slurry
White cement for jointing & pointing
Sand for CM (1:8)
Seigniorage charges of sand
B. LABOUR (including for polishing & rubbing)
Mason 1st class
Mazdoor (unskiled)
Add water charges 1%
Grand Total

sqm

10.10

kg.

36.00

kg.

33.00

kg.

5.00

cum

0.20

cum

0.20

day

4.00

day

8.00
1.00%

689

Remarks
7

BLD-CSTN
Index-code

S No
1
79

BLD-CSTN-7-9

80

BLD-CSTN-7-10

Description

Unit

Quantity

sqm

10.10

Flooring with granite stone tiles 8 mm thick


(mirror polished of all shades) set over base
coat of cement mortar (1:6), 12 mm thick over
CC bed already laid or RCC roof slab, including
neat cement slurry of honey like consistency
spread @ 3.3.kgs per sqm & jointed neatly with
white cement paste mixed with pigment of
matching shade to full depth, including cost of
all materials like cement, sand water and tiles
etc., complete, including seigniorage charges,
etc., complete for finished item of work, but
excluding the cost of conveyance of all
materials.
Unit = 10 sqm
A. MATERIALS:
Granite stone tiles 8 mm thick (mirror polished of all
shades)
Cement for CM (1:6) for base coat
Sand for CM (1:6)
Seigniorage charges of sand
B. LABOUR
Mason 1st class
Mazdoor (unskiled)
Add water charges 1%
Grand Total
Flooring with decorated white back ground
glazed tiles, set over base coat of cement mortar
(1:6), 12 mm thick over CC bed already laid or
RCC roof slab, including neat cement slurry of
honey like consistency spread @ 3.3.kgs per
sqm & jointed neatly with white cement paste
mixed with pigment of matching shade to full
depth, including cost of all materials like
cement, sand water and tiles etc., complete,
including seigniorage charges, etc., complete
for finished item of work, but excluding the cost
of conveyance of all materials

kg.

48.00

cum

0.20

cum

0.20

day

4.00

day

Rate
Rs.
5

Amount
Rs.
6

8.00
1.00%

Unit = 10 sqm
A. MATERIALS:
Decorated white back ground glazed tiles

Cement for CM (1:6) for base coat


Cement for slurry
White cement for jointing & pointing
Sand for CM (1:6)
Seigniorage charges of sand
B. LABOUR
Mason 1st class
Mason 2nd class
Mazdoor (unskiled)
Add water charges 1%
Grand Total

sqm
kg.

10.10
28.80

kg.

33.00

kg.

6.00

cum

0.12

cum

0.12

day

0.96

day

2.24

day

3.30
1.00%

690

Remarks
7

BLD-CSTN
Index-code

S No
1
81

BLD-CSTN-7-11

Description

Unit

Quantity

1000
Nos
kg.

0.255
21.600

kg.

6.000

10sqm

1.000

Flooring with pressed clay flooring tiles, set


over base coat of cement mortar (1:8) 12 mm
thick over CC bed already laid or RCC roof slab,
including neat cement slurry of honey like
consistency spread @ 3.3.kgs per sqm & jointed
neatly with cement mixed with pigment of
matching shade to full depth, including cost of
all materials like cement, sand water and tiles
etc., complete, including seigniorage charges,
etc., complete for finished item of work, but
excluding the cost of conveyance of all
materials
Unit = 10 sqm
A. MATERIALS:
20 X 20 cm pressed clay flooring tiles
Cement for CM (1:8) for base coat
Cement for jointing & pointing
Pointing with CM (1:3)
Deduct CM (1:3)

82

BLD-CSTN-7-12

cum

0.040

Sand for CM (1:8)


Seigniorage charges of sand
B. LABOUR

cum

0.120

cum

0.120

Mason 1st class


Mason 2nd class
Mazdoor (unskiled)
Add water charges 1%
Grand Total
Flooring with Plain Cement tiles, set over base
coat of cement mortar (1:8) 12 mm thick over
CC bed already laid or RCC roof slab, including
neat cement slurry of honey like consistency
spread @ 3.3.kgs per sqm & jointed neatly with
cement paste mixed with pigment of matching
shade to full depth, including cost of all
materials like cement, sand water and tiles etc.,
complete, including seigniorage charges, etc.,
complete for finished item of work, but
excluding the cost of conveyance of all
materials
Unit = 10 sqm

day

0.960

day

2.240

A. MATERIALS:
Plain cement Tiles 20 x 20 cms

day

Amount
Rs.
6

4.30
1.00%

1000
Nos

0.255

kg.

21.600

kg.

6.000

10sqm

1.000

cum

0.040

Sand for CM (1:8)


Seigniorage charges of sand
B. LABOUR

cum

0.120

cum

0.120

Mason 1st class


Mason 2nd class
Mazdoor (unskiled)
Add water charges 1%
Grand Total

day

0.960

day

2.240

Cement for CM (1:8) for base coat


Cement for jointing & pointing
Pointing with CM (1:3)
Deduct CM (1:3)

Rate
Rs.
5

day

3.30
1.00%

691

Remarks
7

BLD-CSTN
Index-code

S No

Description

Unit

Quantity

Rate
Rs.
5

Amount
Rs.
6

Note : When Mortar mix is changed proportionate quantity


of cement has to be substituted for all above Flooring Items.
The same data holds good for stones with all colours. Adopt
same data for polished Kadapa Stones and Bethamcherla
stones.
83

BLD-CSTN-7-13

Gronolithie Concrete Flooring 20 mm thick with


(1:1:2), using 6mm to 12 mm size hard granite
machine crushed metal laid over CC bed already
laid or RCC roof slab, in alternate panels of size
not exceeding 1.50 m x 1.50 m and finishing the
top surface to required smoothness and slopes
and thread lining including cost of all materials
like cement, metal, sand and water etc.,
complete, including seigniorage charges, etc.,
complete for finished item of work, but
excluding the cost of conveyance of all
materials
Unit = 10 sqm
A. MATERIALS:
6mm to 12 mm H.G. Metal (Machine crushed)
Cement
Sand
Seigniorage charges of sand
B. LABOUR
Mason 1st class
Mason 2nd class
Mazdoor (unskiled)
Add water charges 1%
Grand Total

84

BLD-CSTN-7-14

85

86

BLD-CSTN-7-16

0.17

kg

120.00

cum

0.085

cum

0.085

day

1.25

day

0.06

day

3.00
1.00%

Flooring with 100mm thick Cement Concrete 1:6:10,


using 40mm metal, 100mm thick and 20 mm Cement
Concrete surface (Ellis Pattern, 1st Sort)

Unit = 10 sqm
A. MATERIALS:
Cement Concrete 1:6:10 using concrete mixer
Stone Chippings 3.34 mm - 10 mm
Cement
B. LABOUR

BLD-CSTN-7-15

cum

cum

1.000

cum

0.250

kg

120.000

day
Mason 1st class
nd
day
Mason 2 class
day
Mazdoor (unskiled)
Add water charges 1%
Grand Total
Flooring with Cement Concrete 1:6:10, using
40mm metal, 100mm thick and plastered over
with 12 mm thick in CM(1:3)
Unit = 10 sqm
A. MATERIALS:
cum
Cement Concrete 1:6:10 using concrete mixer
10 sqm
Plastering with CM (1:3), 12 mm thick
Grand Total
Flooring with Cement Concrete 1:6:10, using
40mm metal, 100mm thick and plastered over
with 12 mm thick in CM(1:3) using Red oxid,
with polished surface
Unit = 10 sqm
A. MATERIALS:
cum
Cement Concrete 1:6:10 using concrete mixer
10 sqm
Plastering with CM (1:3), 12 mm thick
kg
Red oxid

0.150
0.350
5.40
1.00%

1.00
1.00

1.00
1.00
10.00

692

Remarks
7

BLD-CSTN
Index-code

S No
1

87

BLD-CSTN-7-17

Description

Unit

Quantity

Nos

1.10

kg

17.000

B. LABOUR
Masons for polishing
Grand Total
6 mm thick terrazzo flooring in situ with white,
black, chocolate, gray, yellow or green superior
marble chips, over 20 mm thick base coat of CM
(1:3) laid over CC bed already laid or RCC roof
slab, including cost of all materials like cement
marble powder, marble chips, sand & water etc.,
complete including polishing to get high smooth
finishing, seigniorage charges, etc., complete
for finished item of work, but excluding the cost
of conveyance of all materials
Unit = 10 sqm
A. MATERIALS:
Marble Powder
Marble Chips
Cement for top layer
Cement for base coat in CM (1:3)
Sand for base coat
Seigniorage charges of sand
B. MACHINERY
Polishing Charges
C. LABOUR

88

BLD-CSTN-7-18

Mason 1st class


Mason 2nd class
Mazdoor (unskiled)
Grand Total
Providing skirting to internal walls to 15 cm
height/risers of steps with ceramic tiles 7.30 mm
thick length equal to flooring stones, set over
base coat of CM (1:3) 12 mm thick with cement
slurry of honey like consistency spread at the
rate of 3.30 kgs per sqm and jointed with white
cement paste mixed with pigment of matching
shade to full depth, including cost of all
materials like tiles, cement, sand and water etc.,
complete including seigniorage charges, etc.,
complete for finished item of work, but
excluding the cost of conveyance of all
materials
Unit = 10 sqm
A. MATERIALS:
Ceramic tiles 7.30 mm thick
Sand for cm 1:3 base coat
Cement for cm 1:3 base coat
Cement for slurry
White cement for jointing & pointing
Seigniorage charges of sand
B. LABOUR
Mason 1st class
Mazdoor (unskiled)
Grand Total

cum

0.060

kg.

50.000

kg.

96.000

cum

0.200

cum

0.200

sqm

10.000

day

0.960

day

2.240

day

3.30

sqm

10.00

cum

0.12

kgs

57.60

kgs

33.00

kgs

6.00

cum

0.12

day

0.77

day

0.80

Rate
Rs.
5

Amount
Rs.
6

693

Remarks
7

BLD-CSTN
Index-code

S No
1
89

BLD-CSTN-7-19

Description

Unit

Quantity

sqm

10.10

BLD-CSTN-7-20

Amount
Rs.
6

Providing skirting to internal walls to 15 cm


height/risers of steps with marble slab..mm
thickness, length equal to flooring stones, set
over base coat of CM (1:3) 12 mm thick with
cement slurry of honey like consistency spread
at the rate of 3.30 kgs per sqm and jointed with
white cement paste mixed with pigment of
matching shade to full depth, including cost of
all materials like marble slab, cement, sand and
water etc., complete including seigniorage
charges, etc., complete for finished item of
work, but excluding the cost of conveyance of
all materials
Unit = 10 sqm
A. MATERIALS:
Marble slabmm thickness
Sand for base coat
Cement for base coat
Cement for slurry
White cement for jointing & pointing
Flate nosing charges
Machine cutting charges
Seigniorage charges of sand
B. LABOUR
Mason Ist class
Man mazdoor (Beldar)
Man mazdoor (Beldar) for polishing & rubbing
Woman mazdoor
Grand Total

90

Rate
Rs.
5

cum

0.12

kg

57.60

kg

33.00

kg

5.00

RM

66.67

RM

67.67

cum

0.12

day

2.10

day

4.90

day

4.00

day

4.00

sqm
cum
kgs
kgs
kgs
cum

10.10
0.12
34.56
33.00
2.00
0.12

day
day
day

0.96
2.24
3.30
1.00%

Providing skirting to internal walls to 15 cm


height/risers of steps with vitrified tiles length
equal to flooring stones, set over base coat of
CM (1:5) 12 mm thick with cement slurry of
honey like consistency spread at the rate of 3.30
kgs per sqm and jointed with white cement
paste mixed with pigment of matching shade to
full depth, including cost of all materials like
tiles, cement, sand and water etc., complete
including seigniorage charges, etc., complete
for finished item of work, but excluding the cost
of conveyance of all materials
Unit = 10 sqm
A. MATERIALS:
Vitrified tiles polished 1st quality
Sand for cm 1:5 base coat
Cement for cm 1:5 base coat
Cement for slurry
White cement for jointing & pointing
Seigniorage charges of sand
B. LABOUR
Mason Ist class
nd

Mason 2 class
Mazdoor (unskilled)
Add water charges 1%
Grand Total

694

Remarks
7

BLD-CSTN
Index-code

S No
1
91

BLD-CSTN-7-21

Description

Unit

Quantity

sqm

10.10

cum
kgs
kgs
kgs
cum

0.12
57.60
33.00
5.00
0.12

day
day

2.10
0.80
4.90
1.00%

sqm

10.10

cum
kgs
kgs
cum

0.12
57.60
33.00
0.12

day
day
day

0.96
2.24
3.10
1.00%

Rate
Rs.
5

Amount
Rs.
6

Providing skirting to internal walls to 15 cm


height/risers of steps with 8 mm thick mirror
polished granite tiles length equal to flooring
stones, set over base coat of CM (1:3) 12 mm
thick with cement slurry of honey like
consistency spread at the rate of 3.30 kgs per
sqm and jointed with white cement paste mixed
with pigment of matching shade to full depth,
including cost of all materials like tiles, cement,
sand and water etc., complete including
seigniorage charges, etc., complete for finished
item of work, but excluding the cost of

conveyance of all materials


Unit = 10 sqm
A. MATERIALS:
8 mm thick mirror polished granite tiles
Sand for cm 1:3 base coat
Cement for cm 1:3 base coat
Cement for slurry
White cement for jointing & pointing
Seigniorage charges of sand
B. LABOUR
Mason Ist class
Mazdoor (unskiled)

92

BLD-CSTN-7-22

Mason 2nd class


Add water charges 1%
Grand Total
Providing skirting to internal walls to 15 cm
height/risers of steps with 25 mm thick polished
Cuddapah stone length equal to flooring stones,
set over base coat of CM (1:3) 12 mm thick with
cement slurry of honey like consistency spread
at the rate of 3.30 kgs per sqm and jointed with
white cement paste mixed with pigment of
matching shade to full depth, including cost of
all materials like Cuddapah stone, cement, sand
and water etc., complete including seigniorage
charges, etc., complete for finished item of
work, but excluding the cost of conveyance of all

materials
Unit = 10 sqm
A. MATERIALS:
25 mm thick polished Cuddapah stone
Sand for cm 1:3 base coat
Cement for cm 1:3 base coat
Cement for slurry
Seigniorage charges of sand
B. LABOUR
Mason Ist class
Mason 2nd class
Mazdoor (unskiled)
Add water charges 1%
Grand Total

695

Remarks
7

BLD-CSTN
Index-code

S No
1
93

BLD-CSTN-7-23

Description

Unit

Quantity

Rate
Rs.
5

Amount
Rs.
6

Providing skirting to internal walls to 15 cm


height/risers of steps with 25 mm thick polished
Shahabad stone length equal to flooring stones,
set over base coat of CM (1:3) 12 mm thick with
cement slurry of honey like consistency spread
at the rate of 3.30 kgs per sqm and jointed with
white cement paste mixed with pigment of
matching shade to full depth, including cost of
all materials like Shahabad stone, cement, sand
and water etc., complete including seigniorage
charges, etc., complete for finished item of
work, but excluding the cost of conveyance of all

materials
Unit = 10 sqm
A. MATERIALS:
sqm
25 mm thick polished Shahabad stone (White)
cum
Sand for cm 1:3 base coat
kgs
Cement for cm 1:3 base coat
kgs
Cement for slurry
cum
Seigniorage charges of sand
B. LABOUR
day
Mason Ist class
Mason 2nd class
day
Mazdoor (unskiled)
Add water charges 1%
Grand Total
Note : When Mortar mix is changed proportionate quantity of
cement has to be substituted for all Skirting Items.
94

BLD-CSTN-7-24

Teak Wood Flooring 40mm. Thick Tongued and


Grooved Planks, including cost of all materials,
labour etc., complete
Unit = 10 sqm
A. MATERIALS:
cum
Teak Wood Planks 40mm thick
100 Nos
75 mm Long Screws
B. LABOUR
day
Carpenters 1st Class
day
Carpenters 2nd Class
day
Man mazdoor
Note : Deduct 4.3 Nos Carpenters if plank rate is for tongued
and grooved ready planned.
Grand Total

10.10
0.12
57.60
33.00
0.12
0.96
2.24
3.10
1.00%

0.44
3.00

1.95
4.55
5.40

696

Remarks
7

BLD-CSTN
Index-code

S No
1
95

BLD-CSTN-7-25

Unit

Quantity

cum

1.53

day

1.10

day

0.50

kgs

103.09

nos

47.91

Flooring with Gravel 150 mm thick including


cost of all materials, labour, watering etc.,
complete
Unit = 10 sqm
A. MATERIALS:
Gravel (including 2% wastage)
B. LABOUR
Man mazdoor
Woman mazdoor
Grand Total

Rate
Rs.
5

Amount
Rs.
6

ROOFING & CEILING

BLD-CSTN-8
96

BLD-CSTN-8-1

Description

Roofing with corrugated G.I sheets 0.80mm


thick fixed with G.I J bolts & nuts 8 mm dia
with bitumen & G.I limpet washers filled with
white lead & including a coat of approved steel
primer and two coats of approved paint on over
lapping of sheets complete (up to a pitch of 600 )
and seigniorage charges, etc., complete,
excluding the cost of purlins, rafters, trusses &
cost of conveyance of all materials
Unit = 184.518 sqm
A. MATERIALS:
G.I corrugated 0.80 mm thick sheets
G.I scam bolts & nuts 2 x 27 (laps) x 17 = 884
G.I bolts & nuts 20 x 6

nos

G.I J bolts 8 mm dia 2 x 5 x 27 sheets x 3 nos =


810 nos. with washers or srews, if wooden battens
used.
Limpet washers (for scam & J bolts)
884 +
810 = 1694
Bitumen washers
Zinc cromate yellow paint
Ready mixed paint
B. LABOUR
For roofing
Carpenter II class
Man mazdoor (beldar)
For premier painting one coat
Painter
Mazdoor (coolie)
For two coats of painting to over laps
Painter
Mazdor (coolie)

nos

43.90

nos

91.82

nos

91.82

litre

0.14

litre

0.20

day

0.84

day

0.91

day

0.06

day

0.06

day

0.14

day

0.14

Sundries including 50 x 6 mm iron wind ties white lead etc.

LS

Add for Standard specification 1mm. Thick ridging and


1.25 mm thick sheet vallyes when such are required for a
particular work. Average allowance for 10 sqm roofing.

LS

Grand Total
Rate per 10 sqm = Grand Total/10

697

Remarks
7

BLD-CSTN
Index-code

S No
1
97

BLD-CSTN-8-2

98

BLD-CSTN-8-3

Description

Unit

Quantity

Rate
Rs.
5

Amount
Rs.
6

Roofing with corrugated G.I sheets 1.00mm


thick fixed with G.I J bolts & nuts 8 mm dia
with bitumen & G.I limpet washers filled with
white lead & including a coat of approved steel
primer and two coats of approved paint on over
lapping of sheets complete (upto a pitch of 600 )
and seigniorage charges, turnover tax etc.,
complete, excluding the cost of purlins, rafters,
trusses & cost of conveyance of all materials
Unit = 184.518 sqm
A. MATERIALS:
G.I corrugated 1.00 mm thick sheets
G.I scam bolts & nuts 2 x 27 (laps) x 17 = 884
G.I J bolts 8 mm dia 2 x 5 x 27 sheets x 3 nos =
810 nos.
Limpet washers (for scam & J bolts)
884 +
810 = 1694
Bitumen washers
Zinc cromate yellow paint
Ready mixed paint
B. LABOUR
For roofing
Carpenter II class
Man mazdoor (beldar)
For premier painting one coat
Painter
Mazdoor (coolie)
For two coats of painting to over laps
Painter
Mazdor (coolie)
Grand Total
Rate per 10 sqm = Grand Total/10
Roofing with corrugated G.I sheets 1.25mm
thick fixed with G.I J bolts & nuts 8 mm dia
with bitumen & G.I limpet washers filled with
white lead & including a coat of approved steel
primer and two coats of approved paint on over
lapping of sheets complete (upto a pitch of 600 )
and seigniorage charges, turnover tax etc., complete,
excluding the cost of purlins, rafters, trusses & cost of
conveyance of all materials
Unit = 184.518 sqm
A. MATERIALS:
G.I corrugated 1.25 mm thick sheets
G.I scam bolts & nuts 2 x 27 (laps) x 17 = 884
G.I J bolts 8 mm dia 2 x 5 x 27 sheets x 3 nos =
810 nos.
Limpet washers (for scam & J bolts)
884 + 810
= 1694
Bitumen washers
Zinc cromate yellow paint
Ready mixed paint
B. LABOUR
For roofing
Carpenter II class
Man mazdoor (beldar)
For premier painting one coat
Painter
Mazdoor (coolie)

kgs

126.07

nos

47.91

nos

43.90

nos

91.82

nos

91.82

litre

0.14

litre

0.20

day

0.84

day

0.91

day

0.06

day

0.06

day

0.14

day

0.14

kgs

154.80

nos

47.91

nos

43.90

nos

91.82

nos

91.82

litre

0.14

litre

0.20

day

0.84

day

0.91

day

0.06

day

0.06

698

Remarks
7

BLD-CSTN
Index-code

BLD-CSTN-8-4

BLD-CSTN-8-5

S No

Description

Unit

Quantity

For two coats of painting to over laps


day
Painter
day
Mazdor (coolie)
Grand Total
Rate per 10 sqm = Grand Total/10
99 Roofing with 6 mm thick corrugated asbestos
cement sheets, fixing with G.I J bolts & nuts 8
mm dia G.I plain washers complete including
seigniorage charges etc., complete for finished
item of work, but excluding the cost of purlins,
rafters, trusses & cost of conveyance of all
materials upto 600 pitch.
Unit = 216.14 sqm
A. MATERIALS:
T /sqm
6 mm thick corrugated AC sheets
nos
8 mm dia G.I J bolts & nuts
nos
G.I washers
nos
Bitumen washers
B. LABOUR
day
Carpenter II class
day
Man mazdoor
LS
Sundries including 50 x 6 mm iron wind ties white
lead etc.
LS
Add for Standard specification 1mm. Thick ridging
and 1.25 mm thick sheet vallyes when such are
required for a particular work. Average allowance
for 10 sqm roofing.
Grand Total
Rate per 10 sqm = Grand Total/10
100 Best Tiled Roofing with Pan tiles over Flat Tiles
196 and Lime mortar Borders including Teak
Reapers.

Amount
Rs.
6

0.14
0.14

0.15
22.03
22.03
22.03
0.43
0.54

Unit = 10 sqm
A. MATERIALS:
Pan Tiles 230 x (140 + 130)/2, 12 mm thick

1000 No

1560

Flat Tiles 150 x 150 x 15 mm

1000 No

470

10RM
Teak Reepers 50 x 12 mm
kgs
Wire Nails 40 mm long
cum
Lime
cum
Lime Mortar
B. LABOUR
day
Carpenter
day
Bricklayers
day
Man mazdoor
day
Woman mazdoor
LS
Sundries including tarring reepers, extra labour / for
pointing the underside of flat tiles and white
washing the same.
Grand Total
Sub Analysis :
Lime Moratar 1:2
cum
lime
cum
Sand
cum
Grinding Lime Mortar
Total

Rate
Rs.
5

75.000
0.500
0.008
0.300
0.800
2.200
1.100
5.400
LS

0.500
1.000
1.000

699

Remarks
7

BLD-CSTN
Index-code

BLD-CSTN-8-6

S No

Description

Unit

Quantity

1000 No

1560

10RM
kgs
cum

107.000
0.700
0.120

day
day
day
day

1.100
1.400
1.100
3.200

Mats, including Lime mortar Borders


Unit = 10 sqm
A. MATERIALS:
Pan Tiles 230 x (140 + 130)/2, 12 mm thick

1000 No

1560

Bamboo rafters (450 mm apart) 75 to 100 mm dia

RM

25

Bamboo reepers, Split 25 mm dia

100 No

150

Bamboo mats

10 sqm

10.500

cum

0.120

day
day
day
day

1.100
1.400
1.100
3.200

Mangalore tiles (vide Stadard Specification)

1000 No

160

Flat Tiles 150 x 150 x 15 mm

1000 No

470

1
2
101 Best Tiled Roofing with Pan tiles and Lime
197 mortar Borders including Teak Reapers at 100

mm. centres
Unit = 10 sqm
A. MATERIALS:
Pan Tiles 230 x (140 + 130)/2, 12 mm thick
Teak Reepers 50 x 12 mm
Wire Nails 40 mm long
Lime Moratar
B. LABOUR
Carpenter
Bricklayers
Man mazdoor
Woman mazdoor
Grand Total

BLD-CSTN-8-7

BLD-CSTN-8-8

Rate
Rs.
5

Amount
Rs.
6

102 Best Tiled Roofing with Pan tiles laid on


198 Bamboo Rafters, Bamboo Reepers and Bamboo

Lime Moratar for Borders


B. LABOUR
Carpenter
Bricklayers
Man mazdoor
Woman mazdoor
Sundries including nails
Grand Total
103 Best Tiled Roofing with Mangalore tiles set in
199 Lime mortar over Flat Tiles and including Teak
Reepers
Unit = 10 sqm
A. MATERIALS:

10RM
Teak Reepers 50 x 12 mm
kgs
Wire Nails 40 mm long
cum
Lime
cum
Lime Moratar
B. LABOUR
day
Carpenter
day
Bricklayers
day
Man mazdoor
day
Woman mazdoor
LS
Sundries including tarring reepers iron wind ties 30
x 3 mm, G.I. Screw, washers etc., and extra labour
for pointing the underside of flat tiles and white
washing the same.

75.000
0.500
0.008
0.380
0.800
1.600
1.100
4.300
LS

Grand Total

700

Remarks
7

BLD-CSTN
Index-code

BLD-CSTN-8-9

S No

Description

1
2
104 Best Tiled Roofing with
200 including Teak Reepers

Mangalore

Quantity

1000 No

160

10RM
Teak Reepers 50 x 12 mm
kgs
Wire Nails 50 mm long
cum
Lime Moratar
B. LABOUR
day
Carpenter
day
Bricklayers
day
Man mazdoor
day
Woman mazdoor
Grand Total
105 Best Tiled Roofing with Mangalore tiles over
201 Ceiling Tiles with Air Spaces and including Teak
Reepers
Unit = 10 sqm
A. MATERIALS:

36.000
0.500
0.090

with 10 sqm

10.000

Rate for "Best Mangalore tiled roofing


Mangalore tiles including teak reeper".
Add
Terracing tiles

Rate
Rs.
5

Amount
Rs.
6

tiles

Unit = 10 sqm
A. MATERIALS:
Mangalore tiles (vide Stadard Specification)

BLD-CSTN-8-10

Unit

B. LABOUR
Bricklayers
Woman mazdoor
Grand Total

0.500
0.500
1.100
2.200

100 No

156

day
day

0.500
1.100

cum
cum
cum
LS

0.670
1.000
1.000

cum
cum
cum

0.180
0.080
0.023

day
day
LS

3.200
6.500
LS

Common note Applicabable for Items 196 to


201 :1. The quantity proposed for Pan Tiles / Mangalore Tiles
includes allowance for cost of special tiles for ridges and
hips.
2. Reepers size is for rafter spacing 600 mm. including
allowance for eves and valleys.
3. Labour including fixing galvanized iron sheeting-cost of
sheeting to be paid separately.

Sub Analysis :
Lime Mortar (1: 1.5) :

Unit = 1 cum

BLD-CSTN-8-11

Lime
Fine Sand
Grinding Mortar (Spl Grinding)
Sundries
Total
106 Plastering with Lime Mortar 3 Coats, 25 mm
thick (Sebara Rendering)
Unit = 10 sqm
Lime Mortar (1:2)
Lime Mortar (1:1.5)
Lime
LABOUR
Bricklayers
Mazdoor (unskilled)
Sundries
Total

701

Remarks
7

BLD-CSTN
Index-code

BLD-CSTN-8-12

S No

Description

1
2
107 Terrace Roofing with Brick on edge 75 mm.
204 Concrete 2 Courses of Flat Tiles at Top and

Unit

Quantity

pointing Flat Tiles in Cement Mortar (1:3) and


one coat of Cement Plaster (1:3)
Unit = 10 sqm
A. MATERIALS:
1000 No
Terracing Bricks 150 x 75 x 25mm

2000

100 No

900

Flat Tiles 150 x 150 x 15 mm

cum
Broken brick 20 mm cube
cum
Lime
cum
Lime Moratar
Pointing with cement mortar 1:3 (for rate - vide 10 sqm
relevant schedule item)
cum
Cement Mortar 1:3

B. LABOUR
Bricklayers
Mazdoor (unskilled)
Grand Total

day
day

Rate
Rs.
5

Amount
Rs.
6

0.980
0.380
0.210
1.000
0.240
4.300
6.500

Note : The quantity proposed for broken brick allows for the
brick powder formed, replacing sand for concrete layers.

BLD-CSTN-8-13

108 Reinforced cement Concrete Roofing 125 mm


205 thick with CC (M 20) using 20 mm graded metal

and 2 courses of Flat Tiles at Top including


pointing with Cement Mortar (1:3)
Unit = 10 sqm
A. MATERIALS:
Reinforced Concrete Roofing slab 125 mm thick (for rate - 10 sqm
vide relevant schedule item)
100 No
Flat Tiles 150 x 150 x 20 mm

10.000

cum
Cement Mortar 1:3
Pointing with cement mortar 1:3 (for rate - vide 10 sqm
relevant schedule item)
B. LABOUR
day
Bricklayers
day
Woman mazdoor
LS
Sundries including crude oil
Grand Total
Sub Analysis :
RCC (M 20) using 20 mm HG graded metal using
Concrete mixturefor Roofing 125 mm thick

0.260
1.000

CC (M 20) (Item No.


Centering Charges

BLD-CSTN-8-14

900

2.200
2.200

cum

1.250

10 sqm

1.000

Form Work
Total
109 Reinforced cement Concrete Roofing 140 mm
206 thick with CC (M 20) using 20 mm graded metal
and 2 courses of Flat Tiles at Top including
Pointing with Cement Mortar (1:3)
Unit = 10 sqm
A. MATERIALS:
Rate of "Reinforced cement Concrete Roofing 125 mm 10 sqm
thick and 2 courses of Flat Tiles at Top including pointing
with Cement Mortar (1:3)"

Add :
For extra thickness of roofing slab
Grand Total

cum

1.000

0.150

702

Remarks
7

BLD-CSTN
Index-code

BLD-CSTN-8-15

S No

Description

1
2
110 Reinforced cement Concrete Roofing 150 mm
207 thick with CC (M 20) using 20 mm graded metal

Unit

Quantity

Add :
For extra thickness of roofing slab
Grand Total

BLD-CSTN-8-17

Amount
Rs.
6

and 2 courses of Flat Tiles at Top including


Pointing with Cement Mortar (1:3)
Rate of "Reinforced cement Concrete Roofing 125 mm 10 sqm
thick and 2 courses of Flat Tiles at Top including pointing
with Cement Mortar (1:3)"

BLD-CSTN-8-16

Rate
Rs.
5

cum

1.000

0.250

111 Reinforced cement Concrete Roofing 100 mm


207 thick with CC (M 20) using 20 mm graded metal

and 2 courses of Flat Tiles at Top including


Pointing with Cement Mortar (1:3)
Rate of "Reinforced cement Concrete Roofing 125 10 sqm
mm thick and 2 courses of Flat Tiles at Top
including pointing with Cement Mortar (1:3)"
Deduct :
cum
For Less thickness of roofing slab
Grand Total
112 Reinforced cement Concrete Roofing 100 mm
207 thick with CC (M 20) using 20 mm graded metal
with Imprevious Coat with 12 mm thick
Plastering in CM (1:3) with 1 kg. of Impermo
Compound or ACCO Proof per Bag of Cement
and laid when slab is Green.
Unit = 10 sqm
Reinforced Concrete Roofing slab 100 mm thick (for 10 sqm
rate - vide relevant schedule item)
10 sqm
Centering Charges
Plastering with CM (1:3), 12 mm thick
Impermo Compound
Grand Total
Note for Items 204 - 207 :
1. No extra rate will be paid for finishing the bottom
surface of the roofing slab as described in SS No.

1.000

0.250

1.000
1.000

10 sqm

1.000

kgs

1.500

"For estimating purpose the extra allowance for


camber concrete, when such is required may be
given under sundries."

703

Remarks
7

BLD-CSTN
Index-code

BLD-CSTN-8-18

S No

Description

1
2
113 Complete Surface Repairs to Leaky Terrace
208 Roofs with Flat Tiles

Unit = 10 sqm
A. MATERIALS:
Flat Tiles 150 x 150 x 15 mm

Unit

Quantity

1000 No

450

cum
Cement Mortar 1:3
Pointing with cement mortar 1:3 (for rate - vide 10 sqm
relevant schedule item)

BLD-CSTN-8-19

B. LABOUR
day
Bricklayers
day
Man Mazdoor
Clean removal of lime plaster from terraced roofs 10 sqm
and raking out joints 12 mm deep (for rate - vide
relevant schedule item)
Sub Analysis :
Day
Mazdoor (unskilled)
Day
Mate
LS
Sundries including crude oil
Grand Total
114 Best Sloping Bengal Terrace with 3 courses of
209 Flat Tiles at Top including Teak Wood Reepers

Rate
Rs.
5

Amount
Rs.
6

0.110
1.000

1.100
1.100
1.000

Unit = 10 sqm
A. MATERIALS:
1000 No

1350

cum
cum
10 RM

0.008
0.150
75.000

kgs
Wire Nails 40 mm long
Plastering with lime mortar 3 coats (for rate - vide 10 sqm
relevant schedule item)

0.500
1.000

Flat Tiles 150 x 150 x 15 mm


Lime
Lime Moratar (1:1.5)
Teak Reepers 52 x 12 mm

B. LABOUR
Carpenter
Bricklayers
Woman mazdoor
Sundries including tarring reepers
Grand Total

day
day
day
LS

0.800
2.200
2.200

Note : 1. Reepers size is for rafter spacing 600 mm.


including allowance for eves and valleys.
2. No extra rate will bepaid for finishing the bottom
surface of the roofing slab as described in SS No.

704

Remarks
7

BLD-CSTN
Index-code

BLD-CSTN-8-20

S No

1
2
115 Removing Old Tiles and Retiling with New Pan
212 Tiles over Old Teak Reepers including New

Unit

Quantity

White Washed Lime Mortar Borders 230 x 50


mm. at 2 Metres Intervals
Unit = 10 sqm
A. MATERIALS:
1000 No
Pan Tiles 230 x (140 + 130)/2, 12 mm thick

BLD-CSTN-8-21 116
213

117

BLD-CSTN-8-22 214

BLD-CSTN-8-23

Description

cum
Lime Moratar
B. LABOUR
day
Bricklayers
day
Man Mazdoor
day
Woman mazdoor
LS
Sundries
Grand Total
Shifting Pan Tiles (Labour Only)
Unit = 10 sqm
day
Bricklayers
day
Man Mazdoor
Grand Total
Shifting Pan Tilesand forming new White
Washed Lime Mortar Boarders, 230 x 50 mm at 2
Metres Intervals
Unit = 10 sqm
10 sqm
Rate of "Shifting Pan Tiles"

LS
Add : Lime Mortar Borders and White Washing
Grand Total
118 12 mm. Teak Wood Plank Ceiling Tongued and
222 Grooved Planking
Unit = 10 sqm
A. MATERIALS:
cum
Teak Wood Planks 150 x 12 mm
100
No
Screws 40mm long

B. LABOUR
Carpenter
Man Mazdoor
Sundries
Grand Total
Note : Deduct 4.3 Nos Carpenters if plank rate is
for tongued and grooved ready planned.

day
day
LS

Rate
Rs.
5

Amount
Rs.
6

1560
0.120
1.400
1.100
4.300

1.100
0.800

1.000

0.132
300

6.500
5.400

119 12 mm. Teak Wood Plank Ceiling with 40 x 12

BLD-CSTN-8-24 223
mm Teak Wood Battens

Unit = 10 sqm
Rate for "12 mm. Teak Wood Plank Ceiling 10 sqm
Tongued and Grooved Planking"
10 RM
Teak Wood Battens 40 x 12 mm
Brass screws 25 mm long
Deduct :
Carpenter
Sundries
Grand Total

10.000
66.000

100 No

240

day
LS

1.100

705

Remarks
7

BLD-CSTN
Index-code

S No

Description

1
2
120 Providing impervious coat to exposed RCC roof

BLD-CSTN-8-25

BLD-CSTN-8-26

BLD-CSTN-8-27

BLD-CSTN-8-28

slab surface with CM(1:3), 20mm thick with 1kg


of water proof compound per bag of cement
laid over roof when it is green including cost of
all materials, seigniorage charges, excluding
conveyance charges of materials and including
all operational, incidental and labour charges for
mixing mortar, laying, rendering smooth and
thread lining, curing, rounding off junctions of
wall and slab etc,, complete for finished item of
work
Unit = 10 sqm
A. MATERIALS:
Cement Mortal 1:3
Water proof compound
B. LABOUR
Mason 1st class
Mason 2nd class
Mazdoor (unskiled)
Grand Total
121 Providing & fixing insulating board ceiling of
approved quality with nails etc., complete,
excluding the cost of frame work for base and
cost of conveyance of all materials
Unit = 10 sqm
A. MATERIALS:
12 mm thick insulating board
B. LABOUR
Carpenter Ist class
Man mazdoor
Grand Total
122 Providing & fixing hard board sheet ceiling of
approved quality with nails etc., complete,
excluding the cost of frame work for base and
cost of conveyance of all materials
Unit = 10 sqm
A. MATERIALS:
3 mm thick standard quality of hard board
B. LABOUR
Carpenter Ist class
Man mazdoor
Grand Total
123 Providing & fixing flat pressed 3 layer medium
density particle board sheet with necessary
nails etc., complete, excluding the cost of frame
work for base and cost of conveyance of all
materials
Unit = 10 sqm
A. MATERIALS:
Standard quality of flat pressed 3 layer medium density
board sheet 4.50 mm thick

B. LABOUR
Carpenter Ist class
Man mazdoor
Grand Total

Unit

Quantity

cum

0.210

kg

2.000

day

0.660

day

1.540

day

3.70

sqm

11.00

day

2.50

day

2.00

sqm

11.00

day

2.50

day

2.00

sqm

11.00

day

2.50

day

2.00

Rate
Rs.
5

Amount
Rs.
6

706

Remarks
7

BLD-CSTN
Index-code

S No

Description

1
2
124 Providing & fixing plain AC sheet ceiling of

BLD-CSTN-8-29

approved quality with necessary nails etc.,


complete, excluding the cost of frame work for
base and cost of conveyance of all materials
Unit = 10 sqm
A. MATERIALS:
Plain AC sheet for ceiling
B. LABOUR
Carpenter Ist class
Man mazdoor
Grand Total

Unit

Quantity

sqm

11.00

day

2.50

day

2.00

cum

0.05

Rate
Rs.
5

Amount
Rs.
6

125 Providing 10 mm thick plaster of paris (Gypsum

BLD-CSTN-8-30

anhydrous) ceiling upto a height of 5 m above


floor level over first class BT wood strips 25 x 6
mm with 10 mm gap in between and reinforced
with rabbit wire mesh fixed to wooden frame
excluding cost of wooden frame for base & cost
of conveyance of all materials.
Unit = 10 sqm
A. MATERIALS:
Wooden strips 1st class BT wood 25 x 6 mm size
Nails
Rabbit wire mesh
Plaster of paris
B. LABOUR
for Jointing the wooden strips including fixing
the rabbit mesh
Carpenter Ist class
Man mazdoor (beldar)
For doing plaster of paris over wooden strips
Mason Ist class
Mason IInd class
Mazdoor (unskilled)
Grand Total
Gypboard Suspended false ceiling

BLD-CSTN-8-31

kg

0.75

sqm

10.20

kg

219.76

day

2.60

day

1.60

day

2.62

day

1.62

day

377.00

sqm

1.03

126 Supplying and fixing Gyp Board Suspended regular single


layer false ceiling (GS-MFSC-4.1 as per India Gypsum)
using 12.5 mm thick Gyp Board conforming to IS 2095 1982 fixing to Gyp steel GI perimeter channels of size 20
mm x 27 mm x 30 mm(web) of 0.55 mm thick along the
perimeter of ceiling screw fixed to brick work/ partition at
610 mm c/c and suspending the frame work using
Intermediate channels (45 mm x 15mm x 15mm x 0.9 mm)
from soffit at 1220 mm c/c with ceiling angle (25 mm x 10
mm x 0.55 mm) fixed with GI Cleat and steel expansion
fasteners & connecting clip to the ceiling channels (with
knurled web of 51.5 mm x 26 mm x 10.5 mm x 0.55 mm)
fixed in direction perpendicular to the intermediate channel
at 457 mm c/c and fixing the 12.5 mm tapered edge
Gypboard with 25 mm drywall screws at 230 mm c/c &
jointing and finishing using joint compound and paper tape
to have a flush look including filling the tapered & square
edges with jointing compound, two coats of drywall topcoat
complete for finished item of work as per Idia Gypsum Ltd
specification.

UNIT -1 sqm
A) Material requirement as per India Gypsum
12.5 mm Gypboard
1219 mm x 1829 mm size Boards

707

Remarks
7

BLD-CSTN
Index-code

S No
1

Description

Unit

Quantity

RM
Nos

0.64
1.84

RM

2.30

RM

0.84

RM
Nos
Nos
Nos
Kgs
RM
Lits

0.40
0.64
0.64
18.00
0.55
1.46
0.15

day
day
day
day
day
day
day

0.40
0.40
0.08
0.08
0.04
0.08
0.24

Hrs
Hrs

0.32
0.64
1%

sqm

1.00

RM

0.40

RM

1.60

RM

1.60

RM
Nos
Nos
Nos

1.28
1.28
1.28
5.36

Ceiling Angle
25 mm x 10 mm x 0.55 mm
Connecting Clips
Ceiling Section
51.5 mm x 26 mm x 10.5 mm x 0.55 mm thick
Intermediate Channel
45 mmx 15 mm x 15 mm x 0.9 mm
Perimeter Channel
20 mm x 27 mm x 30 mm(web) of 0.55 mm thick
Rawl Plug
Soffit Cleats
Drywall Screws - 25 mm
Jointing Compound
Jointing Paper Tape
Drywall Top Coat
B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
1st Class Painter
2nd Class Painter
Power Saw Cutter - Hand Operated - Operator
Power Drill - Hand Operated - Operator
Unskilled Mazdoor
C) Machinery
Power Saw Cutter - Hand Operated - Hire charges
Power Drill - Hand Operated - Hire Charges
Scaffolding charges
BASIC COST per 1 sqm
Gyp Board Fine Line Grid false ceiling

BLD-CSTN-8-32

Rate
Rs.
5

Amount
Rs.
6

127 Supplying and fixing Gyp Board Fine Line Grid false ceiling
(GS-FLC-4.6 as per India Gypsum) in size 600 mm x 600
mm using 12.5 mm thick/ 9.5 mm thick Gyp Board sheet
tiles of size 595 mm x 595 mm or 595 mm x 1195 mm
conforming to IS 2095 - 1982 fixing to Gyp steel precoated
GI wall angle of size 25 mm x 25 mm x of 0.70 mm thick
along the perimeter of ceiling screw fixed to brick work/
partition at 610 mm c/c and suspending the frame work
using precoated GI Tee section (24 mm x 38 mm x 0.7
mm) from soffit at 1220 mm c/c fixed with GI Soffit Cleat,
rawl plugs and steel expansion fasteners & connecting clip
to the GI T section with 4 mm dia GI Rod with galvanised
spring steel level clip of PVC unversal holding clips system
at 1200 mm c/c and fixing the 12.5 mm / 9.5 mm
Gypboard Sheet tiles of size 595 mm x 595 mm or 595 mm
x 1195 mm and finishing two coats of drywall topcoat
complete for finished item of work as per Idia Gypsum Ltd
specification.

UNIT -1 sqm
A) Material requirement as per India Gypsum
12.5 mm / 9.5 mm - Gypboard Tiles
Either - 595 mm x 595 mm Or - 595 mm x 1195 mm GI Angle - Precoated
25 mm x 25 mm x 0.7 mm
GI - Precoated - T Section - 3600 mm long
24 mm x 38 mm x 0.7 mm thick
GI - Precoated - T Section - 600 mm long
24 mm x 38 mm x 0.7 mm thick
GI Rod - 4 mm Dia
Connecting Rod
Rawl Plug
Soffit Cleats
Unversal Holding Clips

708

Remarks
7

BLD-CSTN
Index-code

S No

Description

Unit

Quantity

3
Lits

4
0.15

day
day
day
day
day
day
day

0.40
0.40
0.08
0.08
0.04
0.04
0.24

Hrs
Hrs

0.32
0.32
1%

sqm

1.00

RM

0.40

RM

1.60

RM

1.60

RM
Nos

1.28
1.28

day
day
day
day
day
day
day

0.40
0.40
0.08
0.08
0.04
0.04
0.24

Hrs
Hrs

0.32
0.32
1%

Drywall Top Coat


B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
1st Class Painter
2nd Class Painter
Power Saw Cutter - Hand Operated - Operator
Power Drill - Hand Operated - Operator
Unskilled Mazdoor
C) Machinery
Power Saw Cutter - Hand Operated - Hire charges
Power Drill - Hand Operated - Hire Charges
Scaffolding charges
BASIC COST per 1 sqm
Armstrong False ceiling

BLD-CSTN-8-33

Rate
Rs.
5

Amount
Rs.
6

128 Providing and fixing in true horizontal level 600 mm x 600


mm 15 mm thick Arm strong false ceiling system
manufactured by M/s Arm strong world Industries using hot
dipped Galvanised Steel section exposed surface with precoated capping, main Tee of size 24 x 32 mm at every
1200 mm c/c maximum and rotary stiched cross tee of size
24 x 27 mm at evry 600 mm c/c and sub-cross tee of size
24 mm x 25 mm at 1200 mm c/c and wall angle of size 19
x 19 mm fixed to periphery of the wall and the above grid is
suspended at every 1200 mm c/c in both directions using
2.0 mm thick pre-straightened GI Wire laying fine fissured
butt edge ceiling tiles of 15 mm thick mineral fiber Board
manufactured by M/s Arm Strong World Industries Ltd.,
having RH 99% and for finished of size 600 x 600 mm
including Cost &conveyance of all materials and labour
charges such as cutting , fixing of standing of frame work
exposing roof making complete for finished item of work

UNIT 1 sqm
A) Material requirement
15 mm - Armstrong Mineral Fiber sheet 600 x 600
Hotdipped GI Angle - Precoated - Grid
19 mm x 19 mm
Polyster painted GI - T Section - 1200 mm
(1) 24 x 32 mm and (2) 24 x 25 mm (sub-cross Tee)
Polyster painted GI - T Section - 300 mm
24 mm x 27 mm
GI Rod - prestraightened - 2.0 mm dia
Connecting Rod
6 mm Nylon Rawl Plug
B) LABOUR CHARGES
PER UNIT 1 sqm
1st Class Carpenter
2nd Class Carpenter
1st Class Painter
2nd Class Painter
Power Saw Cutter - Hand Operated - Operator
Power Drill - Hand Operated - Operator
Unskilled Mazdoor
C) Machinery
Power Saw Cutter - Hand Operated - Hire charges
Power Drill - Hand Operated - Hire Charges
Scaffolding charges
BASIC COST per 1 sqm

709

Remarks
7

BLD-CSTN
Index-code

S No
1

Description

Unit

Quantity

sqm

1.00

RM

0.40

RM

3.20

Nos
Nos

1.28
1.28

day
day
day
day
day
day
day

0.36
0.36
0.00
0.00
0.02
0.04
0.20

Hrs
Hrs

0.16
0.32
1%

cum

0.005
L.S

day
day
LS

0.11
0.22

Rate
Rs.
5

Amount
Rs.
6

Thermocole False ceiling

BLD-CSTN-8-34

129 Providing and fixing Thermocole False ceiling in true


horizontal level 600 mm x 600 mm using 15 mm/ 19 mm
thick Thermocole sheet anodised Aluminium Tee sections
of size 24.50 mm x 24.0 mm x 2.4 mm in grid with cross
tee of size 24 x 24.5 mm at every 600 mm c/c and
anodised aluminium wall angle of size 24 x 24 mm fixed to
periphery of the wall and the above grid is suspended at
every 1200 mm c/c in both directions using 2.0 mm thick
GI Wire for finished of size 600 x 600 mm including Cost
&conveyance of all materials and labour charges such as
cutting , fixing of standing of frame work exposing roof
making complete for finished item of work

UNIT 1 sqm
A) Material requirement
15 mm/ 19 mm Thermocole sheet 600 x 600
Alumninium Angle
24 mm x 24 mm
Anodised Aluminium T Section
(1) 24 x 24.5 x 2.4 mm mm
GI Rod - prestraightened - 2.0 mm dia
Connecting Rod
Rawl Plugs
B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
1st Class Painter
2nd Class Painter
Power Saw Cutter - Hand Operated - Operator
Power Drill - Hand Operated - Operator
Unskilled Mazdoor
C) Machinery
Power Saw Cutter - Hand Operated - Hire charges
Power Drill - Hand Operated - Hire Charges
Scaffolding charges
BASIC COST per 1 sqm

BLD-CSTN-9

WHITE WASHING, COLOUR WASHING &


DISTEMPERING
130 White washing one coat with lime of approved

BLD-CSTN-9-1

quality to give an even shade after thoroughly


brushing the surface to remove all dirt and
remains of loose powdered materials including
cost of all materials, labour charges and
incidental such as scaffolding, lift charges etc.,
complete for finished item of work, but
excluding conveyance charges of materials
Unit: 10 sqm
A. MATERIALS :
Fine screened shell lime
Gum, conjee water, or prickly pear juice including
necessary fire wood
B. LABOUR
Brick Layers
Mazdoor (unskilled)
Sundries including brushes etc.,
Total cost for 10 sqm

710

Remarks
7

BLD-CSTN
Index-code

S No

Description

1
2
131 White washing two coats with lime of approved

BLD-CSTN-9-2

BLD-CSTN-9-3

quality to give an even shade after thoroughly


brushing the surface to remove all dirt and
remains of loose powdered materials including
cost of all materials, labour charges and
incidental such as scaffolding, lift charges etc.,
complete for finished item of work, but
excluding conveyance charges of materials
Unit: 10 sqm
A. MATERIALS :
Fine screened shell lime
Gum, conjee water, or prickly pear juice including
necessary fire wood
B. LABOUR
Brick Layers
Mazdoor (unskilled)
Sundries including brushes etc.,
Total cost for 10 sqm
132 White washing three coats with lime of
approved quality to give an even shade after
thoroughly brushing the surface to remove all
dirt and remains of loose powdered materials
including cost of all materials, labour charges
and incidental such as scaffolding, lift charges
etc., complete for finished item of work, but
excluding conveyance charges of materials
Unit: 10 sqm
A. MATERIALS :
Fine screened shell lime
Gum, conjee water, or prickly pear juice including
necessary fire wood
B. LABOUR
White washer
Brick Layers
Man Mazdoor
Women mazdoor
Mazdoor (unskilled)
Sundries including brushes, ladders etc.,
Total cost for 10 sqm

Unit

Quantity

cum

0.007
L.S

day
day
LS

0.160
0.32

cum

0.009
L.S

day
day
day
day
day
LS

0.220
0.43

Rate
Rs.
5

Amount
Rs.
6

133 White

BLD-CSTN-9-4

washing one coat with whiting of


approved quality to give an even shade after
thoroughly brushing the surface to remove all
dirt and remains of loose powdered materials
including cost of all materials, labour charges
and incidental such as scaffolding, lift charges
etc., complete for finished item of work, but
excluding conveyance charges of materials
Unit: 10 sqm
A. MATERIALS :
cum / kg
Whiting / White Cement

with White Cement


Grade II

1.20

Gum, conjee water, or prickly pear juice including


necessary fire wood
B. LABOUR
Brick Layers / Painter
Mazdoor (unskilled)
Sundries including brushes, ladders, etc.,
Total cost for 10 sqm

day
day

0.11
0.22
0.50%

711

Remarks
7

BLD-CSTN
Index-code

S No

Description

Unit

Quantity

cum / kg

2.00

1
134 White

BLD-CSTN-9-5

L.S

Gum, conjee water, or prickly pear juice including


necessary fire wood

BLD-CSTN-9-7

Amount
Rs.
6

washing two coats with whiting of


approved quality to give an even shade after
thoroughly brushing the surface to remove all
dirt and remains of loose powdered materials
including cost of all materials, labour charges
and incidental such as scaffolding, lift charges
etc., complete for finished item of work, but
excluding conveyance charges of materials
Unit: 10 sqm
A. MATERIALS :
Whiting / White Cement

BLD-CSTN-9-6

Rate
Rs.
5

B. LABOUR
day
Brick Layers / Painter
day
Mazdoor (unskilled)
Sundries including brushes, ladders, etc.,
Total cost for 10 sqm
135 White washing three coats with whiting of
approved quality to give an even shade after
thoroughly brushing the surface to remove all
dirt and remains of loose powdered materials
including cost of all materials, labour charges
and incidental such as scaffolding, lift charges
etc., complete for finished item of work, but
excluding conveyance charges of materials
Unit: 10 sqm
A. MATERIALS :
cum / kg
Whiting / White Cement
Gum, conjee water, or prickly pear juice including
necessary fire wood
B. LABOUR
day
Brick Layers / Painter
day
Mazdoor (unskilled)
Total cost for 10 sqm
136 Colour Washing, One Coat
254 Unit: 10 sqm
10 sqm
Rate for "White Washing" one coat

0.210
0.320
1.00%

2.800

0.300
0.430

1.000

Add: For Colours, etc., (50 percent of above rate)


Total

BLD-CSTN-9-8

137 Colour Washing, Two Coats


255 Unit: 10 sqm

Rate for "White Washing" two coats

BLD-CSTN-9-9

Add: For Colours, etc., (50 percent of above rate)


Total
138 Distempering, 2 Coats with Water Bound
256 Distemper
Unit: 10 sqm
A. MATERIALS :
Distemper
B. LABOUR
Painter
Mazdoor (unskilled)
Sundries including brushes, ladders, etc.,
Total cost for 10 sqm

10 sqm

1.000

kg

1.340

day
day

0.500
1.300
1.000%

712

Remarks
7

BLD-CSTN
Index-code

BLD-CSTN-9-10

S No

Description

1
2
139 Distempering, 2 Coats with Oil Bound Distemper
257

Unit: 10 sqm
A. MATERIALS :
Distemper
B. LABOUR
Painter
Sundries including brushes, ladders, etc.,
Total cost for 10 sqm
PAINTING & VARNISHING

BLD-CSTN-10

Unit

Quantity

kg

1.700

day

1.200
1.000%

Lts
Nos
Nos
Lts
Nos
Nos

0.50
0.08
0.19
1.70
0.36
0.84

kg

1.00

day

0.700
0.500%

kg

2.000

day
day

0.300
1.500
1.000%

kg

3.500

day
day

0.500
1.500
1.000%

Rate
Rs.
5

Amount
Rs.
6

140 Painting to new walls with 2 coats of ready mixed oil

bound wahsable distemper of approved brand and


shade over a base coat of appropriate primer of
approved brand, making 3 coats in all to give an
even shade after thourughly brushing the surface to
remove all dirt and remains of loose powdered
materials, including cost and conveyance of all
materials to work site and all operational, incidental,
labour charges etc. complete for finished item of
work as per SS 911 for internal walls

BLD-CSTN-10-1

PRIMARY COAT:

BLD-CSTN-10-2

Cost of Primer
Painter I st class
Pianter Iind class
Cost of washable Oil Bound Distemper
1st class painter
II class painter
Total cost
141 Painting, Priming Coat on New
270 Surface

142

BLD-CSTN-10-3 284

143

BLD-CSTN-10-4 285

Plastered

Unit: 10 sqm
A. MATERIALS :
Cement Primer
B. LABOUR
Painter
Sundries including brushes, soaps, putty etc.,
Total cost for 10 sqm
Painting Walls with Snowcem or other equal
and approved Water Proof Cement Paint over
Priming Coat, One Coat (All Colours)
Unit: 10 sqm
A. MATERIALS :
Cement Paint at 5 sqm., per kg
B. LABOUR
Painter
Mazdoor (unskilled)
Sundries including brushes, etc.,
Total cost for 10 sqm
Painting Walls with Snowcem or other equal
and approved Water Proof Cement Paint over
Priming Coat, 2 Coats (All Colours)
Unit: 10 sqm
A. MATERIALS :
Cement Paint at 3 sqm., per kg
B. LABOUR
Painter
Mazdoor (unskilled)
Sundries including brushes, etc.,
Total cost for 10 sqm

713

Remarks
7

BLD-CSTN
Index-code

S No

Description

1
2
144 Painting to new walls with 2 coats of water proof

Unit

Quantity

kg
day
day
kg

1.00
0.21
0.49
3.50

day
day
day

0.15
0.35
1.50

0.700

day

0.700
1.000%

0.70

day

0.70

L
L

0.800
0.600

day
day

0.700
0.700

Rate
Rs.
5

Amount
Rs.
6

cement paint of apporved brand and shade over a


base coat of approved cement primer grade I
making making 3 coats in all to give an even shade
after thourughly brushing the surface to remove all
dirt and remains of loose powdered materials,
including cost and conveyance of all materials to
work site and all operational, incidental, labour
charges etc. complete for finished item of work as
per SS 912 for internal walls

BLD-CSTN-10-5

Cost of Cement Primer


Ist class painter
2nd class painter
Cost of water proof cement Paint of approved
quality
1st class painter
2nd class painter
Mazdoor (unskilled)
Total cost
145 Painting, Priming Coat on New Wood Work

BLD-CSTN-10-6 268

Unit: 10 sqm
A. MATERIALS :
Wood Primer
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
146 Painting, Priming Coat on New Iron Work

BLD-CSTN-10-7 269

Unit: 10 sqm
A. MATERIALS :
Red Oxide Primer
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm

BLD-CSTN-10-8 147 Varnishing to Wood Work, One Coat


281 Unit: 10 sqm

A. MATERIALS :
Varnish
Linseed Oil - boiled
B. LABOUR
Painter
Man Mazdoor
Sundries including brushes,fuel, size etc.,
Total cost for 10 sqm

714

Remarks
7

BLD-CSTN
Index-code

BLD-CSTN-10-9

S No

Description

1
2
148 Varnishing to Wood Work, Two Coats
282

Unit: 10 sqm
A. MATERIALS :
Varnish
Linseed Oil - boiled
B. LABOUR
Painter
Man Mazdoor
Sundries including brushes,fuel, size etc.,
Total cost for 10 sqm
149 Painting with Ready mixed oil paint (all colours)

Unit

Quantity

L
L

1.200
1.100

day
day

1.100
1.100

kg

1.600

day
LS

0.700

kg

2.800

day
LS

1.200

kg

1.500

day
LS

0.700

kg

2.4.

day
LS

1.200

kg

1.200

day
LS

0.700

Rate
Rs.
5

Amount
Rs.
6

BLD-CSTN-10-10 256

to
i. One Coat - New Wood Work :
265

ii

iii

iv

Unit: 10 sqm
A. MATERIALS :
Ready mixed paint
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
Two Coats - New Wood Work :
Unit: 10 sqm
A. MATERIALS :
Ready mixed paint
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
One Coat - Old Wood Work & New Iron Work :
Unit: 10 sqm
A. MATERIALS :
Ready mixed paint
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
Two Coats - Old Wood Work & New Iron Work:
Unit: 10 sqm
A. MATERIALS :
Ready mixed paint
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
One Coat - Old Iron Work :
Unit: 10 sqm
A. MATERIALS :
Ready mixed paint
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm

715

Remarks
7

BLD-CSTN
Index-code

S No

Description

Unit

Quantity

1
vi

kg

2.100

day
LS

1.100

kg

3.400

day
LS

1.500

kg

3.900

day
LS

1.600

0.500

day

0.700

0.400

day

0.700

0.900

day

1.200

Two Coats - Old Iron Work :


Unit: 10 sqm
A. MATERIALS :
Ready mixed paint
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
vii Three Coats - Old Iron Work :
Unit: 10 sqm
A. MATERIALS :
Ready mixed paint
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
viii Three Coats - New Wood Work :
Unit: 10 sqm
A. MATERIALS :
Ready mixed paint
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm

Rate
Rs.
5

Amount
Rs.
6

BLD-CSTN-10-11 150 Painting with :


266 i. Plastic Emulsion paint Grade I - One Coat for

ii

iii

New Wood Work, Old Wood Work & New Iron


Work :
A. MATERIALS :
Plastic Emulsion paint (at 20 sqm / litre as per
British Paints (I) Ltd.
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
Plastic Emulsion paints - One Coat for Old Iron
A. MATERIALS :
Plastic Emulsion paint (at 20 sqm / litre as per
British Paints (I) Ltd.
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
Plastic Emulsion paints - Two Coats for New
Wood Work :
A. MATERIALS :
Plastic Emulsion paint (at 20 sqm / litre as per
British Paints (I) Ltd.
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm

716

Remarks
7

BLD-CSTN
Index-code

S No
1
iv

vi

vii

Description

Unit

Quantity

0.800

day

1.200

0.800

day

1.100

0.700

day

1.100

1.200

day

1.600

1.100

day

1.500

0.700

day

0.700

Plastic Emulsion paints - Two Coats for Old


Wood Work & New Iron Work :
A. MATERIALS :
Plastic Emulsion paint (at 20 sqm / litre as per
British Paints (I) Ltd.
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
Plastic Emulsion paints - Two Coats for New
Iron Work :
A. MATERIALS :
Plastic Emulsion paint (at 20 sqm / litre as per
British Paints (I) Ltd.
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
Plastic Emulsion paints - Two Coats for Old Iron
Work :
A. MATERIALS :
Plastic Emulsion paint (at 20 sqm / litre as per
British Paints (I) Ltd.
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
Plastic Emulsion paints - Three Coats for New
Wood Work :

A. MATERIALS :
Plastic Emulsion paint (at 20 sqm / litre as per
British Paints (I) Ltd.
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
viii Plastic Emulsion paints - Three Coats for Old
Iron Work :
A. MATERIALS :
Plastic Emulsion paint (at 20 sqm / litre as per
British Paints (I) Ltd.
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
151 Painting with Synthetic Enamel paints - One
BLD-CSTN-10-12 i Coat - for New Wood Work, Old Wood Work &
New Iron Work
A. MATERIALS :
Synthetic Enamel paint (at 20 sqm / litre as per
British Paints (I) Ltd.
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm

Rate
Rs.
5

Amount
Rs.
6

717

Remarks
7

BLD-CSTN
Index-code

S No
1
ii

iii

iv

Description

Unit

Quantity

0.500

day

0.700

1.200

day

1.200

1.100

day

1.200

1.100

day

1.100

0.900

day

1.100

1.700

day

1.600

Painting with Synthetic Enamel paints - One


Coat - For Old Iron Work
A. MATERIALS :
Synthetic Enamel paint (at 20 sqm / litre as per
British Paints (I) Ltd.
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
Painting with Synthetic Enamel paints - Two
Coats - for New Wood Work
A. MATERIALS :
Synthetic Enamel paint (at 20 sqm / litre as per
British Paints (I) Ltd.
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
Painting with Synthetic Enamel paints - Two
Coats - For Old Wood Work
A. MATERIALS :
Synthetic Enamel paint (at 20 sqm / litre as per
British Paints (I) Ltd.
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
Painting with Synthetic Enamel paints - Two
Coats - For New Iron Work
A. MATERIALS :
Synthetic Enamel paint (at 20 sqm / litre as per
British Paints (I) Ltd.
B. LABOUR
Painter

Rate
Rs.
5

Amount
Rs.
6

Sundries including brushes, soap, putty etc.,


vi

Total cost for 10 sqm


Painting with Synthetic Enamel paints - Two
Coats - For Old Iron Work
A. MATERIALS :
Synthetic Enamel paint (at 20 sqm / litre as per
British Paints (I) Ltd.

vii

B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
Painting with Synthetic Enamel paints - Three
Coats - for New Wood Work
A. MATERIALS :
Synthetic Enamel paint (at 20 sqm / litre as per
British Paints (I) Ltd.
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm

718

Remarks
7

BLD-CSTN
Index-code

S No
1
viii

Description

Unit

Quantity

1.600

day

1.500

kg

0.500

day
day
LS

0.800
0.800

0.650

day
day
LS

0.800
0.800

kg
L

0.228
1.630

day
LS

3.200

cum

1.000

day
day

17.700
8.800
LS

Painting with Synthetic Enamel paints - Three


Coats - For Old Iron Work
A. MATERIALS :
Synthetic Enamel paint (at 20 sqm / litre as per
British Paints (I) Ltd.

B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
152 Polishing on wood work with readymade wax
BLD-CSTN-10-13
polish of approved brand and manufacture
New Work :
A. MATERIALS :
Readymade wax polish
B. LABOUR
Painter
Healper
Sundries including brushes, soap, cloth etc.,
Total cost for 10 sqm

BLD-CSTN-10-14

Rate
Rs.
5

Amount
Rs.
6

153 Melamine polishing on wood work (one or more

coat)
New Work :
A. MATERIALS :
Melamine polish
B. LABOUR
Painter
Healper
Sundries for Spraying Machine etc.,
Total cost for 10 sqm
154 French Spirit polishing Two or more coats on
BLD-CSTN-10-15
new works including a coat of wood filler.
A. MATERIALS :
Shellac
Spirit
B. LABOUR
Painter
Sundries such as pigment, terpentaine, sand paper, putty,
wood filler, white woolen cloth, linseed oil, cotton etc.,

Total cost for 10 sqm

BLD-CSTN-11
BLD-CSTN-11-1

WOOD
WORK,
ALUMINUM
WINDOWS, VENTILATORS Etc.,

DOORS,

155 Best Teak Wood wrought and put up to 2 meters

(Schedule Item No 286)


Unit = 1 cum
Materials :
Teak wood large scantlings upto 2 m
Labour :
Carpenter
Man Mazdoor
Sundries including nails, screws etc.,
Cost per cum

719

Remarks
7

BLD-CSTN
Index-code

S No

Description

1
2
156 Best Teak Wood wrought and put up over 2

BLD-CSTN-11-2

BLD-CSTN-11-3

BLD-CSTN-11-4

BLD-CSTN-11-5

metres and below 3 metres in length (Schedule


Item No 287)
Unit = 1 cum
Materials :
Teak wood large scantlings over 2 m and below 3 m
in length
Labour :
Carpenter
Man Mazdoor
Sundries including nails, screws etc.,
Cost per cum

Unit

Quantity

cum

1.000

day
day

17.700
8.800
LS

cum

1.000

day

17.700

day

8.800

Rate
Rs.
5

Amount
Rs.
6

157 Best Teak Wood wrought and put up in large scantling


of over 3 metres in length (Schedule Item No 288)

Unit = 1 cum
Materials :
Teak wood large scantlings over 2 m and below 3 m
in length
Labour :
Carpenter
Man Mazdoor
Sundries including nails, screws etc.,
Cost per cum
158 Best Teak Wood wrought and put up for trusses
including straps and all iron work (Schedule
Item No 289)
Unit = 1 cum
Materials :
Teak wood large scantlings
Iron Work (average)
Labour :
Carpenter
Man Mazdoor
Sundries including nails, screws etc.,
Cost per cum
159 Fully Panelled doors - External or Internal Moulded panels (Schedule Item No 290)
A Single Shutter
i
800 x 2000 mm
*Teak wood
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of holdfasts and all wind
appliances (Vide relevant standard specification)

ii

Total for each door


900 x 2000 mm
*Teak wood
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of holdfasts and all wind
appliances (Vide relevant standard specification)

LS

cum

1.000

kg

112.000

day

26.500

day

8.800
LS

cum

0.083

sqm

1.600
LS

cum

0.088

sqm

1.800

Total for each door

720

Remarks
7

BLD-CSTN
Index-code

S No
1
iii

iv

Description

Unit

Quantity

cum

0.109

sqm

2.200

1100 x 2000 mm
*Teak wood
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of holdfasts and all wind
appliances (Vide relevant standard specification)
Total for each door
1200 x 2100 mm
*Teak wood
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of holdfasts and all wind
appliances (Vide relevant standard specification)
Total for each door
900 x 2100 mm
*Teak wood
Labour, wrought and putup in position frame &
shutters

Total for each door


1500 x 2400 mm
*Teak wood
Labour, wrought and putup in position frame &
shutters

cum

0.123

sqm

2.520

cum

0.094

sqm

1.890
LS

cum

0.159

sqm

3.600

Sundries inclusive of holdfasts and all wind appliances


(Vide relevant standard specification)
B
i

Total for each door


Double Shutter
900 x 2000 mm
*Teak wood
Labour, wrought and putup in position frame &
shutters

Amount
Rs.
6

LS

Sundries inclusive of holdfasts and all wind appliances


(Vide relevant standard specification)
vi

Rate
Rs.
5

LS

cum

0.096

sqm

1.800

cum

0.104

sqm

2.000

cum

0.134

sqm

2.860

Sundries inclusive of holdfasts and all wind appliances


(Vide relevant standard specification)
ii

iii

Total for each door


1000 x 2000 mm
*Teak wood
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of holdfasts and all wind
appliances (Vide relevant standard specification)
Total for each door
1300 x 2200 mm
*Teak wood
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of holdfasts and all wind
appliances (Vide relevant standard specification)
Total for each door

721

Remarks
7

BLD-CSTN
Index-code

S No
1
iv

Description

Unit

Quantity

cum

0.147

sqm

3.220

cum

0.068

sqm

0.720

sqm

1.600

1400 x 2300 mm
*Teak wood
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of holdfasts and all wind
appliances (Vide relevant standard specification)

Rate
Rs.
5

Amount
Rs.
6

Total for each door


* Note : Average rate for respective size scantlings
and rough plank

BLD-CSTN-11-6

160 Fully Panelled doors - Internal Five Ply - Ply-

wood Panels (Schedule Item No 291)


A
i

ii

iii

Single Shutter
800 x 2000 mm
*Teak wood
Five - Ply - Ply - Wood brich
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of holdfasts and all wind
appliances (Vide relevant standard specification)
Total for each door
900 x 2000 mm
*Teak wood
Five - Ply - Ply - Wood brich
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of holdfasts and all wind
appliances (Vide relevant standard specification)
Total for each door
1200 x 2100 mm
*Teak wood
Five - Ply - Ply - Wood brich
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of holdfasts and all wind
appliances (Vide relevant standard specification)

LS

cum

0.071

sqm

0.870

sqm

1.800

cum

0.100

sqm

1.160

sqm

2.520
LS

Total for each door


iv

1300 x 2200 mm

*Teak wood
Five - Ply - Ply - Wood brich
Labour, wrought and putup in position frame &
shutters inclusive of holdfasts and all wind
Sundries
appliances (Vide relevant standard specification)

Total for each door


900 x 2100 mm
*Teak wood
Five - Ply - Ply - Wood brich
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of holdfasts and all wind
appliances (Vide relevant standard specification)

cum

0.106

sqm

1.390

sqm

2.860

cum

0.077

sqm

0.880

sqm

1.890
LS

Total for each door

722

Remarks
7

BLD-CSTN
Index-code

S No
1
vi

B
i

Description

Unit

Quantity

cum

0.091

sqm

0.880

sqm

2.100

cum

0.082

sqm

0.710

sqm

1.800

*Teak wood

cum

0.088

Five - Ply - Ply - Wood brich

sqm

0.820

Labour, wrought and putup in position frame &


shutters
Sundries inclusive of holdfasts and all wind
appliances (Vide relevant standard specification)

sqm

2.000

*Teak wood

cum

0.090

Five - Ply - Ply - Wood brich


Labour, wrought and putup in position frame &
shutters
Sundries inclusive of holdfasts and all wind
appliances (Vide relevant standard specification)

sqm
sqm

0.940
2.200

*Teak wood

cum

0.123

Five - Ply - Ply - Wood brich


Labour, wrought and putup in position frame &
shutters
Sundries inclusive of holdfasts and all wind
appliances (Vide relevant standard specification)

sqm
sqm

1.900
3.600

cum
sqm
sqm

0.130
1.280
3.600

1000 x 2100 mm
*Teak wood
Five - Ply - Ply - Wood brich
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of holdfasts and all wind
appliances (Vide relevant standard specification)
Total for each door
Double Shutter
900 x 2000 mm
*Teak wood
Five - Ply - Ply - Wood brich
Labour, wrought and putup in position frame &
shutters

Rate
Rs.
5

Amount
Rs.
6

Sundries inclusive of holdfasts and all wind appliances


(Vide relevant standard specification)

Total for each door


ii

1000 x 2000 mm

Total for each door


iii

1100 x 2000 mm

Total for each door


iv

1400 x 2300 mm

Total for each door


v

1500 x 2400 mm
*Teak wood
Five - Ply - Ply - Wood brich
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of holdfasts and all wind appliances
(Vide relevant standard specification)

Total for each door


* Note : Average rate for respective size scantlings
and rough plank

723

Remarks
7

BLD-CSTN
Index-code

BLD-CSTN-11-7

S No

Description

Unit

Quantity

Item 292)
Top Tower bolts (Ave : Size)

Nos

Bottom Tower bolts 150mm long

Nos

Parliament hings with screws

Nos

Oxidised aldrop with bolts

Nos

Wind cleats with hings

Nos

293)
Top Tower bolts (Ave : Size)

Nos

Bottom Tower bolts 150mm long

Nos

Butt hings with screws

Nos

Wind cleats with hings

Nos

cum

0.072

sqm

0.470

sqm

1.600

1
2
161 Furniture - Iron - for External doors (Schedule

Rate
Rs.
5

Amount
Rs.
6

(Same for all doors)

BLD-CSTN-11-8

162 Furniture - Iron - Internal doors (Schedule Item

(Same for all doors)

BLD-CSTN-11-9

163 Glazed and Panelled doors (Schedule Item No.

294)
A
i

ii

iii

iv

Single Shutter
800 x 2000 mm
*Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and all
wind
appliances
(Vide
relevant
standard
specification)
Total for each door
900 x 2000 mm
*Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and all
wind
appliances
(Vide
relevant
standard
specification)
Total for each door
1200 x 2100 mm
*Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and all
wind
appliances
(Vide
relevant
standard
specification)
Total for each door
1300 x 2200 mm
*Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and all
wind
appliances
(Vide
relevant
standard
specification)
Total for each door

LS

cum

0.076

sqm

0.560

sqm

1.800

LS

cum

0.106

sqm

0.760

sqm

2.520

LS

cum

0.115

sqm

0.870

sqm

2.860

LS

724

Remarks
7

BLD-CSTN
Index-code

S No
1
B
i

ii

iii

iv

Description

Unit

Quantity

cum

0.087

sqm

0.420

sqm

1.800

Rate
Rs.
5

Amount
Rs.
6

Double Shutter
900 x 2000 mm
*Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and all
wind
appliances
(Vide
relevant
standard
specification)
Total for each door
1000 x 2000 mm
*Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and all
wind
appliances
(Vide
relevant
standard
specification)
Total for each door
1100 x 2000 mm
*Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and all
wind
appliances
(Vide
relevant
standard
specification)
Total for each door
1400 x 2300 mm
*Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and all
wind
appliances
(Vide
relevant
standard
specification)
Total for each door
1500 x 2400 mm
*Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and all
wind
appliances
(Vide
relevant
standard
specification)
Total for each door
* Note : Average rate for respective size scantlings
and rough planks.

LS

cum

0.092

sqm

0.510

sqm

2.000

LS

cum

0.096

sqm

0.600

sqm

2.200

LS

cum

0.123

sqm

1.060

sqm

3.220

LS

cum

0.130

sqm

1.280

sqm

3.600

LS

725

Remarks
7

BLD-CSTN
Index-code

BLD-CSTN-11-10

S No

Description

1
2
164 Furniture - Same as for Fully Panelled Doors

Unit

Quantity

cum

0.107

sqm

2.000

Rate
Rs.
5

Amount
Rs.
6

External (Schedule Item No. 295)


Total for each door

BLD-CSTN-11-11

165 Framed and Planked Doors (Schedule Item No.


i

ii

BLD-CSTN-11-12

296)
1000 x 2000 mm
*Teak wood
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and
wind appliances and screws for planks (Vide
standard specification)
Total for each door
1200 x 2100 mm
*Teak wood
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and
wind appliances and screws for planks (Vide
standard specification)
Total for each door
* Note : Average rate for respective size scantlings
and rough planks.

LS

cum

0.127

sqm

2.520

LS

166 Country wood

Framed and Planked Doors


(Schedule Item No. 297)
Single Shutter :

1000 x 2000 mm
Country wood
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and
wind appliances and screws for planks (Vide
standard specification)

Total for each door


1200 x 2100 mm
Country wood
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and
wind appliances and screws for planks (Vide
standard specification)
Total for each door
167 Furniture - 6 Butt Hings - 1 Top and 2 Bottom
BLD-CSTN-11-13
Tower Bolts and One Wrought steel safety Hasp
L.S. (Schedule Item No. 298)
Each Door
168 Ledged Braced and Planked Doors (Schedule
BLD-CSTN-11-14
Item No. 299)
Single Shutter :
i
800 x 2000 mm
*Teak wood
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of hold fasts and wind
appliances and nails for planks (Vide standard
specification)
** Furniture - 3 Nos T - hinges - Vide SS for size - 2
Nos Chain and slopes country make.
Total for each door

cum
sqm

0.107
2.000

LS

ii

cum

0.127

sqm

2.520

LS

cum

0.083

sqm

1.600

LS

LS

726

Remarks
7

BLD-CSTN
Index-code

S No
1
ii

Description

Unit

Quantity

cum

0.100

sqm

2.100

1000 x 2100 mm
*Teak wood
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of hold fasts and wind
appliances and nails for planks (Vide standard
specification)
** Furniture - 3 Nos T - hinges - Vide SS for size - 2
Nos Chain and slopes country make.
Total for each door
Note : * Average rate for respective size scantlings
and rough planks.

Rate
Rs.
5

Amount
Rs.
6

LS

LS

** Note that for this type of door the furniture will be


supplied and fixed by the contractor.

BLD-CSTN-11-15

169 * Country wood Ledged Braced and Planked


i

ii

Doors (Schedule Item No. 300)


800 x 2000 mm
Country wood
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of hold fasts and wind
appliances and nails for planks (Vide standard
specification)
** Furniture - 3 Nos T - hinges - Vide SS for size - 2
Nos Chain and slopes country make.
Total for each door
1000 x 2100 mm
Country wood
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of hold fasts and wind
appliances and nails for planks (Vide standard
specification)
** Furniture - 3 Nos T - hinges - Vide SS for size - 2
Nos Chain and slopes country make.
Total for each door
** Note that for this type of door the furniture will be
supplied and fixed by the contractor.

cum

0.083

sqm

1.600

LS

LS

cum

0.100

sqm

2.100

LS

LS

Note : * Class of Country wood to be defined in


relevent schedule item.
170 Flush

BLD-CSTN-11-16

type Doors with 35mm Thick Flush


Shutters with Bondwood solied Block Board
Type Faced on Both the sides with Commercial
Type Plywood (Schedule Item No. 301.)
Single Shutter :
900 x 2000 mm
*Teak wood
Flush Shutter 35mm thick (Vide relevant standard
specification)
Labour, wrought and putup in position frame &
shutters

cum

0.035

sqm

1.530

sqm

1.800

Sundries inclusive of hold fasts and all wind appliances


(Vide standard specification)

Total for each door

727

Remarks
7

BLD-CSTN
Index-code

S No
1
ii

Description

Unit

Quantity

cum

0.037

sqm

1.820

sqm

2.100

cum

0.028

sqm

0.390

sqm

0.720

cum

0.037

sqm

0.500

sqm

0.960

cum

0.041

sqm

0.700

sqm

1.200

cum

0.061

sqm

0.710

sqm

1.440

cum

0.072

sqm

0.920

sqm

1.800

cum

0.059

sqm

0.970

sqm

1.700

1000 x 2100 mm
*Teak wood
Flush Shutter 35mm thick (Vide relevant standard
specification)
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of hold fasts and all wind
appliances (Vide standard specification)
Total for each door
*Note : Average rate for respective size scantlings.

Rate
Rs.
5

Amount
Rs.
6

BLD-CSTN-11-17 171 Windows Glazed (Schedule Item No. 302)


A
i

Single Shutter :
600 x 1200 mm
*Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and wind
appliances (Vide standard specification)

ii

Total for each window


800 x 1200 mm
*Teak wood
Glass
Labour, wrought and putup in position frame & shutters

B
i

ii

Sundries inclusive of putty, brads, hold fasts and


wind appliances (Vide standard specification)
Total for each window
Double Shutter :
1000 x 1200 mm
*Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and
wind appliances (Vide standard specification)
Total for each window
1200 x 1200 mm
*Teak wood
Glass
Labour, wrought and putup in position frame & shutters
Sundries inclusive of putty, brads, hold fasts and wind
appliances (Vide standard specification)

iii

Total for each window


1500 x 1200 mm (3 Pannels)
*Teak wood
Glass
Labour, wrought and putup in position frame & shutters
Sundries inclusive of putty, brads, hold fasts and wind
appliances (Vide standard specification)

iv

Total for each window


1000 x 1700 mm (2 Pannels)
*Teak wood
Glass
Labour, wrought and putup in position frame & shutters

Sundries inclusive of putty, brads, hold fasts and


wind appliances (Vide standard specification)
Total for each window

728

Remarks
7

BLD-CSTN
Index-code

S No
1

BLD-CSTN-11-18

BLD-CSTN-11-19

BLD-CSTN-11-20

172

173

174

BLD-CSTN-11-21 175
A
i

ii

B
i

ii

Description

Unit

Quantity

each

each

each

each

*Note : Average rate for respective size scantlings.


Furniture for Double Leaf Windows Glazed With
Top Lights (Schedule Item No. 303)
Banel Bolts 100 mm long
Top tower bolts 150 mm long
Bottom bolts 150 mm long
Parliament hinges
Furniture for Double Leaf Windows Glazed
without Top Lights (Schedule Item No. 304)
Top tower bolts 150 mm long
Bottom bolts 150 mm long
Parliament hinges
Same for all such windows
Furniture for Single Leaf Windows Glazed
without Top Lights (Schedule Item No. 305)
Top tower bolts 150 mm long
Bottom tower bolts 150 mm long
Parliament hinges
Same for all such windows
Windows Panelled (Schedule Item No. 306)
Single Shutter
600 x 1200 mm
*Teak wood
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of hold fasts and wind
appliances (Vide standard specification)
Total for each window
700 x 1200 mm
**Teak wood
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of hold fasts and wind
appliances (Vide standard specification)
Total for each window
Double Shutter
800 x 1200 mm
*Teak wood
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of hold fasts and wind
appliances (Vide standard specification)
Total for each window
1000 x 12000 mm
*Teak wood
Labour, wrought and putup in position frame &
shutters

Rate
Rs.
5

Amount
Rs.
6

LS
each

each

each

LS
each

each

each

cum

0.039

sqm

0.720

cum

0.043

sqm

0.840

cum

0.051

sqm

0.960

cum

0.059

sqm

1.200

cum

0.081

sqm

1.440

Sundries inclusive of hold fasts and wind appliances (Vide


standard specification)
iii

Total for each window


1200 x 1200 mm
*Teak wood
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of hold fasts and wind appliances (Vide
standard specification)

Total for each window


*Note : Average rate for respective size scantlings.

729

Remarks
7

BLD-CSTN
Index-code

S No
1
iv

Description

Unit

Quantity

cum

0.056

sqm

1.080

cum

0.036

sqm

0.070

sqm

0.720

cum

0.052

sqm

0.100

sqm

1.080

cum

0.077

sqm

0.120

sqm

1.440

cum

0.094

sqm

0.150

sqm

1.800

each

each

each

each

each

each

each

each

900 x 1200 mm
**Teak wood
Labour, wrought and putup in position frame &
shutters

Rate
Rs.
5

Amount
Rs.
6

Sundries inclusive of hold fasts and wind appliances (Vide


standard specification)

Total for each window


**Note : Average rate for respective size scantlings
and rough planks.

BLD-CSTN-11-22

176 Windows Panelled & Glazed (Schedule Item No.


A

B
i

307)
Single Shutter
600 x 1200 mm
**Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and
wind appliances (Vide standard specification)
Total for each window
Double Shutter
900 x 1200 mm
**Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and wind
appliances (Vide standard specification)

ii

Total for each window


1200 x 1200 mm
**Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and wind
appliances (Vide standard specification)

Total for each window


1500 x 1200 mm (3 Pannels)
**Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and
wind appliances (Vide standard specification)
Total for each window

**Note : Average rate for respective size scantlings and


rough planks.
177 Furniture for Windows Panelled : Single Leaf with half
Shutters (Schedule Item No. 308)

Cabin hooks and eyes 200 mm long


Butt hinges 75 mm size
Top tower bolts 150 mm long
Bottom bolts 150 mm long
Same for all such windows
178 Furniture for Windows Panelled : Double Leaf
BLD-CSTN-11-23
with half Shutters (Schedule Item No. 309)
Cabin hooks and eyes 200 mm long
Butt hinges 75 mm size
Top tower bolts 150 mm long
Bottom bolts 150 mm long
Same for all such windows
179 Teak Wood Windows - Ledged Braced and
BLD-CSTN-11-24
Planked (Schedule Item No. 310)

730

Remarks
7

BLD-CSTN
Index-code

S No
1
i

Description

Unit

Quantity

600 x 1200 mm (half Shutters)


*Teak wood

cum

0.034

Labour, wrought and putup in position frame & shutters

sqm

0.720

Sundries inclusive of all furniture and fitting in accordance


with relevant standard specification
ii

Total for each window


800 x 1200 mm (half Shutters)
*Teak wood
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of all furniture and fitting in accordance
with relevant standard specification

iii

Total for each window


900 x 1200 mm (half Shutters)
*Teak wood
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of all furniture and fitting in accordance
with relevant standard specification

iv

Amount
Rs.
6

LS

cum

0.048

sqm

0.960

LS

cum

0.052

sqm

1.080

LS

Total for each window


1000 x 1200 mm (half Shutters)
*Teak wood

cum

0.052

Labour, wrought and putup in position frame & shutters

sqm

1.200

Sundries inclusive of all furniture and fitting in accordance


with relevant standard specification

Rate
Rs.
5

LS

Total for each window


*Note : Average rate for respective size scantlings
and rough planks.

BLD-CSTN-11-25

180 Ventilators Glazed - Fixed Double Frame and

with Wire Netting (Schedule Item No. 312)


i

800 x 500 mm
*Teak wood
Glass
Wire netting
Labour, wrought and putup in position
Sundries inclusive of putty brads and iron hold fasts where
such are necessary say in 30 cm wall.

ii

Total for each Ventilator


1000 x 500 mm
*Teak wood
Glass
Wire netting
Labour, wrought and putup in position
Sundries inclusive of putty brads and iron hold fasts where
such are necessary say in 30 cm wall.

iii

Total for each Ventilator


1200 x 600 mm
*Teak wood
Glass
Wire netting
Labour, wrought and putup in position
Sundries inclusive of putty brads and iron hold fasts
where such are necessary say in 30 cm wall.

cum

0.012

sqm

0.240

sqm

0.190

sqm

0.400

LS

cum

0.014

sqm

0.310

sqm

0.240

sqm

0.500

LS

cum

0.018

sqm

0.480

sqm

0.290

sqm

0.720

LS

Total for each Ventilator


*Note : Average rate for respective size scantlings

731

Remarks
7

BLD-CSTN
Index-code

BLD-CSTN-11-26

S No

Description

1
2
181 Swing Ventilators - Glazed (Schedule Item No.
i

ii

iii

313)
800 x 500 mm
*Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty brads sash centres brass
ring iron cleats and window card - vide relevant
standard specifications.
Total for each Ventilator
1000 x 500 mm
*Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty brads sash centres brass
ring iron cleats and window card - vide relevant
standard specifications.
Total for each Ventilator
1200 x 600 mm
*Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty brads sash centres brass
ring iron cleats and window card - vide relevant
standard specifications.
Total for each Ventilator
*Note : Average rate for respective size scantlings
and rough planks.

Unit

Quantity

cum

0.021

sqm

0.190

sqm

0.400

Rate
Rs.
5

Amount
Rs.
6

LS

cum

0.025

sqm

0.024

sqm

0.500

LS

cum

0.030

sqm

0.390

sqm

0.720

LS

Aluminium Fixed Glazing

BLD-CSTN-11-27

182 Supply and fixing of aluminimum fixed glazing as per


drawing using standard powder coated/ anodised
aluminimum section of 101.4 x 44.45 x 3.18 mm thick fitted
with 6.0mm thick / 4.0 mm thick plain glass glazing fitted
with suitable Aluminimum glazing clips and aproved brand
silicon sealant including cost and conveyance of all
materials labour charges for manufacturing fixing in
position using wooden blocks and sheet metal screw etc.
to complete for finished item of work as approved by
Engineer-in-charge

Unit - 1 sqm
A) MATERIAL REQUIREMENT
ALUMINIUM SECTION
GLAZING with GLASS
SILICON SEALANT
RUBBER BEADING

B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
Power Saw Cutter - Hand Operated - Operator
Power Drill - Hand Operated - Operator
Unskilled Mazdoor
C) Machinery
Power Saw Cutter - Hand Operated - Hire charges
Power Drill - Hand Operated - Hire Charges
Supervision Charges
Power charges for Motors
BASIC COST per 1 sqm
Aluminimum Partition partly glazed

day

0.947

day

1.158

day

0.105

day

0.211

day

0.632

Hrs

0.842

Hrs

1.684

Nos

0.211
1%

732

Remarks
7

BLD-CSTN
Index-code

S No

Description

1
2
183 Supply and fixing of aluminimum Partition partly

BLD-CSTN-11-28

Unit

Quantity

Rate
Rs.
5

Amount
Rs.
6

glazed as per drawing using standard powder


coated/ anodised aluminimum section of 101.4 x
44.45 x 3.18 mm thick fitted with 12.0mm thick
Particle Boards - prelaminated up to 2.1 M height
and balance height provided with 5.0 mm thick plain
glass glazing fitted with suitable Aluminimum
glazing clips and aproved brand silicon sealant
including cost and conveyance of all materials
labour charges for manufacturing fixing in position
using wooden blocks and sheet metal screw etc. to
complete for finished item of work as approved by
Engineer-in-charge
Unit - 1 sqm
A) MATERIAL REQUIREMENT

ALUMINIUM SECTION
PARTICLE BOARD - Prelaminated
GLAZING with GLASS
SILICON SEALANT
RUBBER BEADING

as per design
as per design
as per design

B) LABOUR CHARGES

1st Class Carpenter


2nd Class Carpenter
Power Saw Cutter - Hand Operated - Operator
Power Drill - Hand Operated - Operator
Unskilled Mazdoor
C) Machinery
Power Saw Cutter - Hand Operated - Hire charges
Power Drill - Hand Operated - Hire Charges
Supervision Charges
Power charges for Motors
BASIC COST per 1 sqm
BLD-CSTN-11-29 184 Aluminium Anodised Casement windows
Unit - 1 sqm

day

1.042

day

1.042

day

0.104

day

0.139

day

0.347

Hrs

0.833

Hrs

1.111

Nos

0.174
1%

Supply and fixing Aluminium Anodised Casement windows


as per approved drawing with aluminium anodised
sections of Series C Jindal Hollow sections and outer
frame of 8804 of size 46 x 44 mm, Shutter frame of 8802
of size 44 mm x 46 mm and Mullion frame of 8803 of size
59 x 38 and glazing section of 4433 with plain clear float
glass 6 mm thick fixed including supply and fixing
aluminium powder coated 1 No.of casement friction stay
hinges for each shutter, 1 Nos. aluminium handles of 150
mm for each shutter and all labour charges for fixing the
fixtures with required no.of screws, bolts and nuts and
including labour charges for fixing the frame in position,
fixing shutter to frame etc. completed for finished item of
work

Unit - 1 sqm
A) MATERIAL REQUIREMENT

ALUMINIUM SECTION
GLAZING with GLASS
SILICON SEALANT
RUBBER BEADING

as per design

Alum.Anodised.PC Friction stay casement hinges

as per design

Alum.Anodised.PC Handles
B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter

as per design

as per design
as per design
as per design

day

0.360

day

1.081

733

Remarks
7

BLD-CSTN
Index-code

S No

Description

Unit

Quantity

3
day

4
0.360

day

0.360

day

1.081

Hrs

2.883

Hrs

2.883

Nos

0.360

Power Saw Cutter - Hand Operated - Operator


Power Drill - Hand Operated - Operator
Unskilled Mazdoor
C) Machinery
Power Saw Cutter - Hand Operated - Hire charges
Power Drill - Hand Operated - Hire Charges
Supervision Charges
Power charges for Motors
BASIC COST per 1 sqm
Aluminium Two/ Three Track Sliding Windows

BLD-CSTN-11-30

Rate
Rs.
5

Amount
Rs.
6

1%

185 Supply and fixing Aluminium Anodised Two/ Three Track


Sliding Windows as per approved drawing with aluminium
anodised sections of Series C Jindal sections and outer
frame top horizontals & both verticals of 8774 of size 62 x
29.5 mm and bottom horizontal - two track frame of 8773
of size 62 x 29.5 mm, Shutter frame top, bottom and
verticals of 8304 of size 50 mm x 20 mm and Weather
interlocking frame of 8306 of size 50 x 20 with plain clear
float glass 5 mm thick fixed including supply and fixing
aluminium handles of 100 mm for each shutter, nylon
rollers assembly and all labour charges for fixing the
fixtures with required no.of screws, bolts and nuts and
including labour charges for fixing the frame in position,
fixing shutter to frame etc. completed for finished item of
work

UNIT 1 sqm
A) MATERIAL REQUIREMENT

ALUMINIUM SECTION
GLAZING with GLASS
SILICON SEALANT
RUBBER BEADING
Alum.Anodised.PC Handles

as per design
as per design
as per design
as per design
as per design

B) LABOUR CHARGES

1st Class Carpenter


2nd Class Carpenter
Power Saw Cutter - Hand Operated - Operator
Power Drill - Hand Operated - Operator
Unskilled Mazdoor
C) Machinery
Power Saw Cutter - Hand Operated - Hire charges
Power Drill - Hand Operated - Hire Charges
Supervision Charges
Power charges for Motors
BASIC COST per 1 sqm

day

0.347

day

1.042

day

0.347

day

0.347

day

1.042

Hrs

2.778

Hrs

2.778

Nos

0.347
1%

734

Remarks
7

BLD-CSTN
Index-code

S No
1

Description

Unit

Quantity

Rate
Rs.
5

Amount
Rs.
6

Aluminium Anodised Doors - Single Shutter

BLD-CSTN-11-31

186 Supply and fixing Aluminium Anodised Doors - Single


Shutter as per approved drawing with aluminium anodised
sections of Jindal sections and outer frame top horizontals
& both verticals of 2408 of size 101.6 x 44.75 x 3.18 mm
Shutter frame top, bottom and verticals of 4504 of size
44.45 mm x 47.62 mm x 3.18 and Middle lock rail of 4621
of size 49.91 x 44.45 x 3 mm with plain clear float glass 5
mm thick fixed including supply and fixing aluminium
handles of 100 mm for each shutter, floor springs/
hydraulic door closure assembly and all labour charges for
fixing the fixtures with required no.of screws, bolts and
nuts and including labour charges for fixing the frame in
position, fixing shutter to frame etc. completed for finished
item of work

UNIT 1 sqm
A) MATERIAL REQUIREMENT
ALUMINIUM SECTION
GLAZING with GLASS
SILICON SEALANT
RUBBER BEADING
Alum.Anodised.PC Handles
Hydraulic Floor Spring/ Door Closure
B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
Power Saw Cutter - Hand Operated - Operator
Power Drill - Hand Operated - Operator
Unskilled Mazdoor
C) Machinery
Power Saw Cutter - Hand Operated - Hire charges
Power Drill - Hand Operated - Hire Charges
Supervision Charges
Power charges for Motors
BASIC COST per 1 sqm
187 Removing white wash or colour wash by steel wire
brushing and/or scraping; sand papering and
preparing the wall surface smooth including
BLD-CSTN-11-32
necessary repairs to scratches complete

as per design
as per design
as per design
as per design
as per design
as per design
day

0.417

day

0.833

day

0.417

day

0.417

day

1.250

Hrs

3.333

Hrs

3.333

Nos

0.417

Details of cost for 10 sq.m


Labour :
day
White washer / Mason 2nd Class
day
Mazdoor (unskilled)
Sundries such as sand paper and scraper etc.
Scaffolding
Add for water charges @ 1 %
Add for contractor's profit and overheads
Cost for 10 sq.m.
Cost per sq.m
188 Removing white wash or colour wash by steel wire
brushing and/or scraping; sand papering and
preparing the ceiling and/or sloping roofs surface
BLD-CSTN-11-33
smooth including necessary repairs to scratches
complete
Deatailed cost for 10 sqm
10 sqm
Rate as per above item

1%

0.010
0.170

Add 10 % extra for ceiling / sloping roof


Cost per 10 sq.m
Cost per sq.m

735

Remarks
7

BLD-CSTN
Index-code

S No

Description

1
2
189 Removing white wash or colour wash by steel wire

BLD-CSTN-11-34

Unit

Quantity

Rate
Rs.
5

Amount
Rs.
6

brushing and/or scraping; sand papering and


preparing the wall surface smooth including
necessary repairs to scratches complete for the wall
surface spoiled by smoke soot
Rate as per Item No (203)

10 sqm

For washing the wall surface spoiled by smoke soot


with clear water before sand papering the surface
smooth and including necessary repairs to the
scratches complete
Details of cost for 10 sq.m
Labour :
Mazdoor (unskilled)
Sundries
Add for water charges @ 1 %
Add for contractor's profit and overheads
Cost for 10 sq.m.
Cost per sq.m
190 Removing white wash or colour wash by steel wire
brushing and/or scraping; sand papering and
preparing the ceiling and/or sloping roofs surface
BLD-CSTN-11-35
smooth including necessary repairs to scratches
complete for the ceiling surface spoiled by smoke
soot
Rate as per Item No (205)

day

0.080

10 sqm

Extra 10% for washing the surface with clean water


on ceiling and/or sloping roofs
Cost per 10 sq.m
Cost per sq.m

BLD-CSTN-11-36

191 Washing and cleaning of decorated wall surfaces

with soap, soda and water


Details of cost for 10 sq.m
Labour :
White washer / Mason 2nd Class
Mazdoor (unskilled)
Sundries such as soap, soda, sand paper and
scaper etc

day
day

0.010
0.170

day
day

0.010
0.170

Add for water charges @ 1 %


Cost for 10 sq.m.
Cost per sq.m
192 Washing and cleaning of the old plastered ceiling
and/or sloping roofs with soap, soda and water
BLD-CSTN-11-37
Rate as per Item above
Extra 10% over
Cost per 10 sq.m
Cost per sq.m

BLD-CSTN-11-38

193 Washing and cleaning of oil and grease spots on

decorated wall surface by suitable chemical


Details of cost for 10 sq.m
Labour :
White washer / Mason 2nd Class
Mazdoor (unskilled)
Sundries, such as chemical etc.
Add for water charges @ 1 %
Cost for 10 sq.m.
Cost per sq.m

736

Remarks
7

BLD-CSTN
Index-code

S No
1

BLD-CSTN-12
BLD-CSTN-12-1

BLD-CSTN-12-2

BLD-CSTN-12-3

Description

Unit

Quantity

day

1.220

day

2.440

day

4.880

day

4.320

day

4.090

day
day

0.500
0.500

Rate
Rs.
5

Amount
Rs.
6

DISMANTLING & DEMOLITION


194 Demolishing

and disposal of unserviceable


materials within 100 metres lead
i
Lime concrete.
Details of cost for 1 cu.m.
Labour :Mazdoor (unskilled)
Sundries
Add for water charges @ 1 %
Cost per cu m
ii
Unreinforced cement concrete upto 15 cm
thicknes
Details of cost for 1 cu.m.
Labour :Mazdoor (unskilled)
Sundries
Add for water charges @ 1 %
Cost per cu m
iii Unreinforced cement concrete more than 15 cm
thickness
Details of cost for 1 cu.m.
Labour :Mazdoor (unskilled)
Sundries
Add for water charges @ 1 %
Cost per cu m
195 Demolition including stacking of serviceable
materials and disposal of unserviceable materials
within 100 metres lead
i
R.C.C. work
Details of cost for 1 cu.m.
Labour :Mazdoor (unskilled)
Sundries
Add for water charges @ 1 %
Cost per cu m
ii
Reinforced Brick work:
Details of cost for 1 cu.m.
Labour :Mazdoor (unskilled)
Sundries
Add for water charges @ 1 %
Cost per cu m
196 Extra over item 20.3 for cutting steel bars in R.C.C.
of R.B. work (sectional area of R.C.C. or R.B. Work
to be measured) Details of cost for one Sq.m. of
sectional area
Reinforced area considering 1% Labour for
cuttings 0.01 Sq.m. reinforcement
Blacksmith 2nd class
Mazdoor (Male)
Sundries
Add for water charges @ 1 %
Cost per sq m

737

Remarks
7

BLD-CSTN
Index-code

S No
1
197 Dismantling

Unit

Quantity

day
day
day

0.100
0.200
0.050

day
day
day

0.130
0.270
0.070

day
day

0.060
0.120

day
day

0.080
0.160

ii

3.150

day
day
day

0.090
0.250
0.250

Not exceeding 3 sq.m. in area:


Details of cost per each
Labour :Mason, II class
Mazdoor (male)
Blacksmith II class
Sundries
Add for water charges @ 1 %
Cost per each
Exceeding 3 sq.m. in area

Details of cost per each


Labour :Mason, II class
Mazdoor (male)
Blacksmith II class
Sundries
Add for water charges @ 1 %
Cost per each
198 Taking out doors, windows and clearestorey
window shutters (steel or wood) including stacking
within 100 metres lead
i
Not exceeding 3 sq.m. in area:

ii

Details of cost per each


Labour :Carpenter II class
Mazdoor (male)
Sundries
Add for water charges @ 1 %
Cost per each
Exceeding 3 sq.m. in area
Details of cost per each
Labour :Carpenter II class
Mazdoor (male)
Sundries
Add for water charges @ 1 %
Cost per each

BLD-CSTN-13

Rate
Rs.
5

Amount
Rs.
6

doors, windows and clear storey


windows, ventilators etc.; (wood or steel) shutters
including chowkhats, architraves, hold fasts and
other attachments etc., complete and stacking them
within 100 metre lead

BLD-CSTN-12-4

BLD-CSTN-12-5

Description

MISCELLANEOUS BUILDING ITEMS


199 Providing and fixing aluminium step edging 'L'

BLD-CSTN-13-1

shape of size 38 mm x 12 mm x 3 mm (thick) to


stairs

Details of cost for 3 metres length


Materials:
Aluminium step edging 'L' shape 38 x 12 x 3mm
(thick) = 3.00 metres with 5% wasage
Carriage of materials
Sundries (Wooden plugs, screws and painting
underneath of strips with bitumanistic paint, etc.,)
Labour :Carpenter II class
Mason I class
Mazdoor (male)
Add for water charges @ 1 %
Cost for 3 m
Cost per m

738

Remarks
7

BLD-CSTN
Index-code

S No

Description

1
2
200 Providing and fixing aluminium step edging 'L'

BLD-CSTN-13-2

Unit

Quantity

3.150

day
day
day

0.090
0.250
0.250

day
day

1.000
0.100

1.310

day
day
day

0.100
0.400
0.400

1.310

day
day
day

0.100
0.400
0.400

Rate
Rs.
5

Amount
Rs.
6

shape of size 57 mm x16 mm x 3 mm (thick) to


stairs

Details of cost for 3 metres length


Materials:
Aluminium step edging 'L' shape 57 mm x16 mm x 3
mm (thick) with 5% wasage
Carriage of materials
Sundries (Wooden plugs, screws and painting
underneath of strips with bitumanistic paint, etc.,)
Labour :Carpenter II class
Mason I class
Mazdoor (male)
Add for water charges @ 1 %
Cost for 3 m
Cost per m
201 Cutting RCC steps for fixing of aluminium step

BLD-CSTN-13-3

edging and make good to match the surroundings

Details of cost for 3 metres

BLD-CSTN-13-4

Cement Mortar
Labour :Mason, II Class
Mazdoor (male)
Add for water charges @ 1 %
Cost for 3 m
Cost per m
202 Providing and fixing 25 mm bore galvanised M.S.
tube (light grade) outlet in cement mortar 1:3(1
cement: 3 fine sand) including cutting and making
good the wall
Details of cost for 10 pipes 12.5 cm long day i.e.,
1.25 metres
Materials:
Galvanised mild steel tube (light grade) 25 mm
nominal bore 10 x 12.5 cm = 1.25 metre with
wastage of 5%
Labour :For cutting and fixing in position
Assistant fitter
Mason.
Mazdoor (male).
Sundries
Add for water charges @ 1 %
Cost for 1.25 m
Cost per m
203 Providing and fixing 1.80 metre long RCC fencing

BLD-CSTN-13-5

posts with 6 mm bar nibs as per design in plate No.


22/2/2. (earth work & concrete to be paid for
separately)
Details of cost for 10 pipes 12.5 cm long day i.e.,
1.25 metres
Materials:
Galvanised mild steel tube (light grade) 40 mm
nominal bore 10 x 12.5 cm = 1.25 metre with
wastage of 5%
Labour :For cutting and fixing in position
Assistant fitter
Mason.
Mazdoor (male).
Sundries

739

Remarks
7

BLD-CSTN
Index-code

BLD-CSTN-13-6

S No

Description

Unit

Quantity

cum

0.336

kg

26.440

Centering and shuttering


(Details as per Annexure 'X')
(Rate as per item No.9.1.8. of Section 9 Form
work).

cum

0.336

10 mm cement plaster with cement mortar 1:2 (1


cement: 2 sand)

sqm

9.880

day
day
day

0.120
0.120
0.250

10 sqm

1.000

Deduct - CM 1:3

cum

0.025

Add - Cement (720-480 x .125)

cum

30.000

Rate
Rs.
5

Amount
Rs.
6

Add for water charges @ 1 %


Cost for 1.25 m
Cost per m
204 Providing and fixing 1.80 metre long RCC fencing
posts with 6 mm bar bibs as per design in plate No.
22/2/2. (earth work & concrete to be paid for
separately)
Details of cost for 10 posts, i.e., 0.336 Cu. m

(Details as per Annexure ' X ' at the end of this item)


Materials:
Cement concrete 1:2:4 (1 cement : 2 coarse sand :4
graded stone aggregate 12.5 mm nominal size)
(Rate as per item No.5.42.d Section Concrete work)
M.S. reinforcement 6 mm dia bars
10 x 4 x
1.88 = 75.20 metres
10 x 9 x 0.50 =
45.00 metres./ l20.00 m 120.20 m @ 0.22
Kg/m=26.44 Kg
(Rate as per item No.5.51 Section Concrete work)

(Details as per Annexure 'X')


Carriage of R.C.C. posts
6 mm bar bibs
Sundries
Labour for fixing posts in line
Mason, 1st Class
Mason, 2nd Class
Mazdoor (Male)
Add Water charges on A @ 1%
Add Contractor's profit and overheads on 'A' + 'B' +
'C @ 10%
Cost for 10 posts
Cost per post
Sub Analysis :
Plastering with CM 1:3, 12 mm thick

Rate for 10 sqm


Rate per sqm
Annexure - 'X'
Details of quantities for RCC posts
Concrete quantity
Area of bottom A, =15+12.5/2 x 8.75+1/2 x 22/7
(6.25) = 120.31+61.38=181.69 Sq.m.
Area of top A2= 10+7.5/1 x 6.25 + 1/2 x 22 x (3.75)2/
7= 54.69+22.10=76.79 Sq.Cm.
Av A2 = 118.12 Sq. Cm.
Volume = h/3(A, + A2 + VA,A2)
A2+A2+A, A2=0.V03766 Sq.m

740

Remarks
7

BLD-CSTN
Index-code

S No
1

Description

Unit

Quantity

kg

9.380

Rate
Rs.
5

Amount
Rs.
6

Volume = 1.05/3 * 0.03766 = 0.0131810 Cu.m.


=0.0132 Cu.m.
Volume of lower square portion =0.165x0.165x0.75
=0.0204 Cu.m
Total volume = 0.0336 Cu. m
Quantity for 10 posts = 0.336 Cu.m
Quantity of centring & shuttering
1.05=0.2908 Sq.m.

0.2770*

3x0.165x0.75=0.3712
0.165x0.165=0.0272
0.10 x 0.10=0.0100/0.6992 Sq.m..
For ten posts=10 x 0.6992 = 6.992 Sq.m.
Quantity
of
surface
plaster
12.50+7.60+7.60=27.70 Cm.
xr=3.1416x5=15.71Cm./43.41Cm
1.05=0.4560 Sq.m.

BLD-CSTN-13-7

area

0.434

4x0.165x0.75=0.4950
0.165x0.165=0.0272
0.10 x 0.10=0.0100/0.9882 Sq.m.
For 10
posts = 10 x 0.9882=9.88 Sq.m.
205 Supplying and fixing galvanised steel barbed wire
(IS : 278-1962 Type I) weighing 9.38 Kg per 100
metres (min.), Straining and fixing to any type of
standard, rails, straining bolts, including securing
with and provision of galvanised mild steel wire,
stapples or steel pins, etc., as directed (Posts and
struts of wood, concrete, steel, etc.) and straining
bolts shall be paid for separately).
Details of Cost per 100 metres (day line of wire)
Materials:
Galvanised steel barbed wire IS type I weighing
9.38 Kg/100 metre

BLD-CSTN-13-8

Carriage of barbed wire.


G.I. staples steel pins or binding wire
Labour :For fixing & stretching wire
Blacksmith, 1st Class
Blacksmith, 2nd Class
Mazdoor (male).
Sundries.
Add water charges @ 1 %
Cost for 100 metres day line of wire
Rate per m
206 Broken glass coping as specified on top of walls
In cement mortar 1:3 (1 cement: 3 sand)
Details of cost per one Sq.m.
Materials:
Broken glass.
Cement mortar 1:3(1 cement: 3 sand)
Labour :Mason (Skilled)
Mazdoor (Male)
Scaffolding etc
Add water charges @ 1 %
Cost per Sq.metre

LS

day
day
day

0.150
0.150
0.300

kg
cum

19.500
0.040

day
day

0.080
0.160

741

Remarks
7

BLD-CSTN
Index-code

S No

Description

Unit

Quantity

Amount
Rs.
6

ANTE-TERMITE TREATMENT

BLD-CSTN-14

BLD-CSTN-14-1

Rate
Rs.
5

207 Providing Antitermite treatment as per IS 6315 (Part - 2)


2001 (Pre-constructional chemical treatment measures)
along the internal & external vertical faces of the columns,
plinth beams, basement and top surface of the basement
filling below flooring bed as per the specified procedure
conforming to IS 6315 (Part-2) 2001 and other relevant
approved specification duly using Chlorpyriphos/ Lindane
emulsifiable concentrate 20% with 1% concentration @ 7.5
Liters/ sqm of the vertical surface & @ 5.0 Liters/ sqm of
the horizontal surface of the substructure to a depth of 500
mm around columns & 300 mm deep around plinth beams,
basements & floor filling area including excavation channel
along the wall & rodding etc & cost & conveyance of all
materials to the site, cost of labour for spraying, rodding
etc complete for finished item of work as per the approval
of the Engineer-in-Charge

Unit = 10 sqm
A) Chlorpyriphos/ Lindane emulsifiable concentrate of
20%

1 liter : 19 Parts water Therefore: 868.55 L /20


Add 12%wastage

Lit

4.100

Liters

0.41
4.51
1%

day
day

3.0
0.22

Total Quantity
B) Add Water Charges @ 1%
C) Labour Charges

Man Mazdoor
Sprayer
D) Hire charges
Sprayer, drilling machine etc
sundries & contingencies
Water charges & electricity

10%
3%
1.50%

Add OH & CP
BASIC COST per 1 sqm
Note: CPWD - Rate Analysis per 9 Sqm

BLD-CSTN-15

BLD-CSTN-15-1

Vertical
Chloropyriphos
Earthwork excavation
Beldar
Horizontal
Chloropyriphos
Vertical
Beldar
Hire charges
Sprayer, drilling machine etc
sundries & contingencies
Water charges & electricity
Add OH & CP
CENTERING, FORM WORK etc.
208 Providing traditional centering, shuttering and
scaffolding using Cashewrina balli props and
bracings supporting wooden brackets, wooden wall
plates, wooden runners and steel plate form work
as per the approved plan and other accessories as
per the standard trade practice including hire
charges for ballies, runners, wooden members and
cost and conveyance of all other consumable
accessories, taxes etc complete for finished item of
work
(I)

Lit
cum
Nos
Lit
Nos
Nos

UNIT 1 sqm
Unsupported Roof Height up to - 3.66 M (12'0")
A) MATERIAL REQUIREMENT
Cashewrina Balli Props - 3" to 4" dia - 12'-0" Height

Nos

2.40

742

Remarks
7

BLD-CSTN
Index-code

S No
1

Description

Unit

Quantity

3
Nos

4
1.44

Wall Plate Brackets / beam bottom supports


Wedge Plate fixture
Runner beams of approximately 4" x 4" size
Steel Plate - form work plates -

BLD-CSTN-15-2

B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
Unskilled Mazdoor
Supervision Charges
Consumables like Rope, Nails, de-shuttering oil
Tape, cover plates
Tools like Hammers etc.,
BASIC COST per 1 sqm
(II) Unsupported Roof Height up to - 4.60 M (15'0")
A) MATERIAL REQUIREMENT
Cashewrina Balli Props - 3" to 4" dia - 12'-0" Height
Wall Plate Brackets / beam bottom supports
Wedge Plate fixture
Runner beams of approximately 4" x 4" size
Steel Plate - form work plates B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
Unskilled Mazdoor
Supervision Charges
Consumables like Rope, Nails, de-shuttering oil
Tape, cover plates
Tools like Hammers etc.,
BASIC COST per 1 sqm
(III) Unsupported Roof Height up to - 7.30 M (24'0")
A) MATERIAL REQUIREMENT
Cashewrina Balli Props - 3" to 4" dia - 12'-0" Height
Wall Plate Brackets / beam bottom supports
Wedge Plate fixture
Runner beams of approximately 4" x 4" size
Steel Plate - form work plates B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
Unskilled Mazdoor
Supervision Charges
Consumables like Rope, Nails, de-shuttering oil
Tape, cover plates
Tools like Hammers etc.,
BASIC COST per 1 sqm
209 Providing rigid Steel centering, shuttering and
scaffolding using steel pipes, adjustable Jack screw
props, acro spans, couplers, tie rods, bracings
members, supporting brackets, acro span beams
and steel plate/ ply-wood form work as per the
approved shuttering designs & plan and other
accessories as per the IS Norms and stability
calculations including hire charges for jack pipes,
acro spans, runners, wooden members and cost
and conveyance of all other consumable
accessories, taxes etc complete for finished item of
work
(I)

Nos

1.44

RM
sqm

16.00
1.86

day
day
day
day

Rate
Rs.
5

Amount
Rs.
6

0.00
0.16
0.28
0.48
0.04
1%
1%
1%

Nos
Nos

4.32
1.44

Nos
RM
sqm

1.44
16.00
1.86

Nos
Nos
Nos

0.20
0.36
0.68

Nos

0.06
1%
1%
1%

Nos
Nos
Nos
RM
sqm

5.76
1.44
1.44
16.00
1.86

Nos
Nos
Nos
Nos

0.28
0.52
1.08
0.08
1%
1%
1%

UNIT 1 sqm
Unsupported Roof Height up to - 3.66 M (12'0")
A) MATERIAL REQUIREMENT
Jack Screw Adjsutable Props - 50 mm dia B Class
Pipes
for vertical props placed @ 3'0" c/c in bothways
Approximately 33'-0" x 33'-0" roof area

743

Remarks
7

BLD-CSTN
Index-code

S No
1

Description

Unit

Quantity

Kgs

62.51

day
day
day
day

0.22
0.38
0.72
0.04
1%

Rate
Rs.
5

Amount
Rs.
6

Span Beams - 2.4 M Long (Acro Spans) Approximtely


Wallers, Couplers, Foot Plates
Steel Plate Beam Bottom - form work plates - 9"
wide
230 mm wide plate x 80 RM
Beam Sides - form work plates - 15" wide

(II)

400 mm wide plate x 80 RM - both sides


Slab Bottom Plates - formwork plates
3'-0" x 4'-0" - 7 Nos
3'-0" x 2'-0" - 2 Nos
1'-0" x 4'-0" - 1 Nos
Slab Sides - 0-6" Height - 40.0 RM
Total Scaffolding Pipes & Centering Plates Appx B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
Unskilled Mazdoor
Supervision Charges
Consumables like Rope, Nails, de-shuttering oil
Tape, cover plates
Tools like Hammers etc.,
BASIC COST per 1 sqm
Unsupported Roof Height up to - 7.32 M (24'0")
A) MATERIAL REQUIREMENT
Heavy Frames - 50 mm dia B Class Pipes (HD
Span Beams - 2.4 M Long (Acro Spans) Approximtely
Wallers, Couplers, Foot Plates
Steel Plate Beam Bottom - form work plates - 9"
wide
230 mm wide plate x 80 RM
Beam Sides - form work plates - 15" wide
400 mm wide plate x 80 RM - both sides
Slab Bottom Plates - formwork plates
3'-0" x 4'-0" - 7 Nos
3'-0" x 2'-0" - 2 Nos
1'-0" x 4'-0" - 1 Nos
Slab Sides - 0-6" Height - 40.0 RM
Total Scaffolding Pipes & Centering Plates Appx B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
Unskilled Mazdoor
Supervision Charges
Consumables like Rope, Nails, de-shuttering oil
Tape, cover plates
Tools like Hammers etc.,
BASIC COST per 1 sqm

1%
1%

Kgs

112.635

day

0.32

day

0.52

day

1.28

day

0.06
1%
1%
1%

744

Remarks
7

BLD-CSTN
Index-code

S No

Description

Unit

Quantity

Rate
Rs.
5

Amount
Rs.
6

Note : Cost of Centering charges with different centering & scaffolding materials for
different structures may be calculated as per the guidelines given Below

TYPE OF STRUCTURE

UNIT
COS
CENTERING AREA T OF
CENT
ERIN
A
B

RCC
STRUCTU
RE UNIT
MEASUR
EMENT
C

FOOTINGS

3.88 sqm

per 1 cum

PEDESTALS

6.17 sqm

per 1 cum

PLINTH BEAMS

9.35 sqm

per 1 cum

LINTELS

7.94 sqm

per 1 cum

CHAJJAS - SUNSHADES

1.22 sqm

per 1 sqm

COLUMNS

11.15 sqm

per 1 cum

BEAMS

9.35 sqm

per 1 cum

SLABS - Up to 150 mm thick

1.05 sqm

per 1 sqm

SLABS - above 150 mm - Up to 300 mm thick

1.09 sqm

per 1 sqm

SLABS - above 300 mm thick

1.14 sqm

per 1 sqm

WAFFLE - (GRID) SLABS (Rib Beams with Slabs)

3.85 sqm

per 1 sqm

PERGOLA SLABS (Only Rib Beams)

2.70 sqm

per 1 sqm

ARCHE BEAMS - up to 1.5 M Span

10.63 sqm

per 1 cum

ARCHE BEAMS - above 1.5 M Span

10.78 sqm

per 1 cum

DOME SLABS

17.19 sqm

per 1 cum

HELICAL STAIRCASES

1.31 sqm

per 1 sqm

For calculating centering charges of RCC Structures, using either cashewrina balli
scaffolding or steel pipe scaffolding, the respective cost may be arrived by taking the
above
values.
Therefore,
Centering charges for any structure:C= A x B
210 Providing STAGE SCAFFOLD with staging using

Cashewrina balli props and bracings supporting


wooden brackets, wooden stage scaffold boards
including hire charges for cashewrina ballies,
wooden baords, scaffolds etc., and cost and
conveyance of all other consumable accessories,
taxes etc complete for finished item of work for
PLAN AREA

BLD-CSTN-15-3

(I)

UNIT 1 sqm
Unsupported Roof Height up to - 3.66 M (12'0")
A) MATERIAL REQUIREMENT
Cashewrina Balli Props - 3" to 4" dia - 12'-0" Height
Scaffold Boards - Bamboo scaffolds - Bamboos 8'0" long
B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
Unskilled Mazdoor
Supervision Charges
Consumables like Rope, Nails, de-shuttering oil

Nos

2.40

Nos

2.70

day

0.04

day

0.30

day

0.48

day

0.04
1%

745

Remarks
7

BLD-CSTN
Index-code

S No

Description

Unit

Quantity

4
1%

(II)

BLD-CSTN-15-4

Tape, cover plates


Tools like Hammers etc.,
BASIC COST per 1 sqm - PLAN AREA
Unsupported Roof Height up to - 4.60 M (15'0")
A) MATERIAL REQUIREMENT
Cashewrina Balli Props - 3" to 4" dia - 12'-0" Height

4.32

Scaffold Boards - Bamboo scaffolds - Bamboos 8'0" long


B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
Unskilled Mazdoor
Supervision Charges
Consumables like Rope, Nails, de-shuttering oil
Tape, cover plates
Tools like Hammers etc.,
BASIC COST per 1 sqm - PLAN AREA
(III) Unsupported Roof Height up to - 7.30 M (24'0")
A) MATERIAL REQUIREMENT
Cashewrina Balli Props - 3" to 4" dia - 12'-0" Height

Nos

2.70

day

0.08

day

0.38

day

0.68

day

0.06

Nos

5.76

Scaffold Boards - Bamboo scaffolds - Bamboos 8'0" long


B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
Unskilled Mazdoor
Supervision Charges
Consumables like Rope, Nails, de-shuttering oil
Tape, cover plates
Tools like Hammers etc.,
BASIC COST per 1 sqm - PLAN AREA
211 Providing ACCESS SCAFFOLD using Cashewrina
balli props and bracings supporting wooden
brackets, wooden stage scaffold boards including
hire charges for cashewrina ballies, wooden baords,
scaffolds etc., and cost and conveyance of all other
consumable accessories, taxes etc complete for
finished item of work for ELEVATION AREA

Nos

2.70

day

0.12

day

0.54

day

1.08

day

0.08

UNIT 1 sqm
Up to - 3.66 M (12'0")
A) MATERIAL REQUIREMENT
Cashewrina Balli Props - 3" to 4" dia - 12'-0" Height
Scaffold Boards - Bamboo scaffolds - Bamboos 8'0" long
B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
Unskilled Mazdoor
Supervision Charges
Consumables like Rope, Nails, de-shuttering oil
Tape, cover plates
Tools like Hammers etc.,

Amount
Rs.
6

1%

Nos

(I)

Rate
Rs.
5

1%
1%
1%

1%
1%
1%

Nos

1.74

Nos

0.72

day

0.07

day

0.11

day

0.2

day

0.04
1%
1%
1%

BASIC COST per 1 sqm - VERTICAL ELEVATION AREA


(II)

Up to - 7.32 M (24'0")
A) MATERIAL REQUIREMENT

746

Remarks
7

BLD-CSTN
Index-code

S No

Description

Unit

Quantity

3
Nos

4
1.74

Nos

0.38

day

0.12

day

0.22

day

0.36

day

0.04

Cashewrina Balli Props - 3" to 4" dia - 12'-0" Height


Scaffold Boards - Bamboo scaffolds - Bamboos 8'0" long
B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
Unskilled Mazdoor
Supervision Charges
Consumables like Rope, Nails,de-shuttering oil

Rate
Rs.
5

Amount
Rs.
6

1%
1%

Tape, cover plates


Tools like Hammers etc.,

1%

BASIC COST per 1 sqm - VERTICAL ELEVATION AREA

BLD-CSTN-15-5

212 Providing STAGE SCAFFOLD using Steel Scaffolding Pipe


Frames made of 40 mmd ia MS Pipes and bracings with
scaffold boards including hire charges for MS Pipe Frames
scaffolds boards etc., and cost and conveyance of all other
consumable accessories, taxes etc complete for finished
item of work for PLAN AREA

(I)

UNIT 1 sqm
Unsupported Roof Height up to - 3.66 M (12'0")

(II)

A) MATERIAL REQUIREMENT
Jack Screw Adjsutable Props - 50 mm dia B Class
Pipes
for vertical props placed @ 3'0" c/c in bothways
Lock Pins
LD Foot Plates
LD Couplers
Total Scaffolding Pipes - Appx B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
Unskilled Mazdoor
Supervision Charges
Consumables like Rope, Nails, de-shuttering oil
Tape, cover plates
Tools like Hammers etc.,
BASIC COST per 1 sqm - PLAN AREA
Unsupported Roof Height up to - 7.32 M (24'0")
A) MATERIAL REQUIREMENT
Heavy Frames - 50 mm dia B Class Pipes (HD
Towers)
Lock Pins
LD Foot Plates
LD Couplers
Total Scaffolding Pipes - Appx B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
Unskilled Mazdoor
Supervision Charges
Consumables like Rope, Nails, de-shuttering oil
Tape, cover plates
Tools like Hammers etc.,
BASIC COST per 1 sqm - PLAN AREA

Kgs

39.26

day

0.04

day

0.34

day

0.60

day

0.04
1%
1%
1%

Kgs

112.635

day

0.12

day

0.58

day

1.20

day

0.08
1%
1%
1%

747

Remarks
7

BLD-CSTN
Index-code

BLD-CSTN-15-6

S No

Description

1
2
213 Providing ACCESS SCAFFOLD using Steel Scaffolding
Pipe Frames made of 40 mmd ia MS Pipes and bracings
with scaffold boards including hire charges for MS Pipe
Frames scaffolds boards etc., and cost and conveyance of
all other consumable accessories, taxes etc complete for
finished item of work for ELEVATION AREA

(I)

Unit

Quantity

Kgs

19.7496

day

0.07

day

0.11

day

0.24

day

0.04

Rate
Rs.
5

Amount
Rs.
6

UNIT 1 sqm
Up to - 3.66 M (12'0")
A) MATERIAL REQUIREMENT
MS Pipe Scaffold Frames - 1.20 x 1.50 M
Approximately 27.3 M Long x 3.66 M High

MS Pipe Bracing structure - 1.5 x 2.25 M


Scaffold Board
Lock Pins
LD Foot Plates
LD Couplers
Total Scaffolding Pipes - Appx B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
Unskilled Mazdoor
Supervision Charges
Consumables like Rope, Nails, de-shuttering oil
Tape, cover plates
Tools like Hammers etc.,

1%
1%
1%

BASIC COST per 1 sqm - VERTICAL ELEVATION AREA


(II)

Up to - 7.32 M (24'0")
A) MATERIAL REQUIREMENT
MS Pipe Scaffold Frames - 1.20 x 1.50 M
Approximately 27.3 M Long x 3.66 M High

MS Pipe Bracing structure - 1.5 x 2.25 M


Scaffold Board
Lock Pins
LD Foot Plates
LD Couplers
Total Scaffolding Pipes - Appx B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
Unskilled Mazdoor
Supervision Charges
Consumables like Rope, Nails, de-shuttering oil
Tape, cover plates
Tools like Hammers etc.,

Kgs

19.14

day

0.12

day

0.22

day

0.44

day

0.04
1%
1%
1%

BASIC COST per 1 sqm - VERTICAL ELEVATION AREA


Note: HIRE & LIFT CHARGES - for all Scaffolding Materials
1. For Material Lift Charges & Labour rate for scaffolding above 7.32 M - increase @ 50% on
labour component for each upper floor on First Floor Rate (7.32 M)
2. For Hire Charges of scaffolding Materials following ratesmay be allowed:
Description of Structure
a

Cashewrina Ballies, Bamboos, Wooden Reapers, Runners,


Wood Posts, Wall Plates etc.,
Let :
Cost of Scaffolding materials =

Rs. A

Scrap value of Scaffolding materials = Rs. B


(Usually B = A * 10%)
Number of uses of Scaffolding materials =
C
Therefore, Hire Charges of scaffolding Materials:
b

(Rs. A - Rs. B)
C

Steel scaffolding pipes, jack Props, wallers, Foot plates,


brackets, steel Centering Plates,etc.,
Let :
Cost of Scaffolding materials = Rs. A
Scrap value of Scaffolding materials = Rs. B

748

Remarks
7

BLD-CSTN
Index-code

S No
1

Description
2
(Usually B = A * 10%)
Period of Hire of Scaffolding materials, in years =
Life of Scaffolding materials, in years =
Therefore, Hire Charges of scaffolding Materials:

Unit

Quantity

Rate
Rs.
5

Amount
Rs.
6

C
D
[(Rs. A - Rs. B)*C]
D

Note: While calculating the Capital Cost of the materials, deprication shall be allowed
based on the service life of the materials.
Number of uses of Scaffolding materials (C )
Wooden Materials - No of Uses - 10 Times (C)
Period of Hire of Steel Scaffolding materials, in years = 1.64 (200 days per Annum)
Life of Steel Forms & Scafholding Material - 3 Years (D)
Period of Requirement of Centering Material
Slabs : 14 + 4 = 18 days
Columns : 1.50 days
Foundations : 2 days

749

Remarks
7

PHE

Statement Showing Comparative Data


Drinking Water Supply Schemes (Public Health)
Index-code

S No
1

Description

Unit

Quantity

Rate
Rs.
5

Amt
Rs.
6

Remarks
7

Sub Analysis

Lowering C.I. Pipes, A class and specials with s/s ends carefully
into trench and laying them true to alignment and gradient
including all sundries but excluding cost and conveyance of
pipes from source of supply. (Reference to specifications. BIS
No.3114/94)
Assumtion 10 m

Common Data

200 mm dia CI pipes 5m long (class A)


Weight = 2 x 257 kgs = 514 kgs = 5.14 quintal
(a) LABOUR:

PHE-LCIS-1

ii

iii

iv

st
day
Plumber 1 class
nd
day
Plumber 2 class
day
Man mazdoor
(b) Cost for 10 metres
Rate per metre = b/10
Rate for 1 kg = b/514
Lowering C.I. / D.I. Pipes (all classes) and specials (fittings) with
s/s ends carefully into trenches and laying them true to
alignment and gradient including all sundries but excluding cost
and conveyance of pipes from source of supply (Ref to
specifications. BIS No.3114/1994)

Note : The Labour charges for cost of Lowering & Laying per 1
kg weight shall be as per sub-analysis made for 200 mm dia CI
Pipes S/s ends.
Details of cost for 5m
80 mm dia pipe
Weight of 5m length = (79 +85.5 + 92)/3 = 85.5 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
(c) Cost for 5 metres = a+b
Rate per metre = c/5
100 mm dia pipe
Weight of 5m length = (100+109+117)/3 = 108.67 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
(c) Cost for 5 metres = a+b
Rate per metre = c/5
125 mm dia pipe
Weight of 5m length = (130+141+153)/3 = 141.33 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
(c) Cost for 5 metres = a+b
Rate per metre = c/5
150mm dia pipe
Weight of 5m length = (162+178+191)/3 = 177 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
(c) Cost for 5 metres = a+b
Rate per metre = c/5
200 mm dia pipe
Weight of 5m length = (237+257+278)/3 = 257.33 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
(c) Cost for 5 metres = a+b
Rate per metre = c/5

0.102
0.238
1.330

kgs

85.500

kgs

108.670

kgs

141.330

kgs

177.000

kgs

257.330

864

Index-code

S No
1
vi

vii

viii

ix

xi

xii

xiii

xiv

xv

Description

Unit

Quantity

kgs

347.670

kgs

449.670

kgs

564.000

kgs

688.330

kgs

832.670

kgs

970.670

kgs

1296.000

kgs

1672.000

kgs

1874.330

kgs

2092.670

250 mm dia pipe


Weight of 5m length = (319+348+376)/3 = 347.67 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
(c) Cost for 5 metres = a+b
Rate per metre = c/5
300 mm dia pipe
Weight of 5m length = (412+450+487)/3 = 449.67 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
(c) Cost for 5 metres = a+b
Rate per metre = c/5
350 mm dia pipe
Weight of 5m length =(519+563+610)/3=564
(a) Labour charges for laying
(b) Overheads & Contractors Profit
(c) Cost for 5 metres = a+b
Rate per metre = c/5
400 mm dia pipe
Weight of 5m length =(631+690+744)/3=688.33
(a) Labour charges for laying
(b) Overheads & Contractors Profit
(c) Cost for 5 metres = a+b
Rate per metre = c/5
450mm dia pipe s/s for 5m
Weight of 5m length =(761+836+901)/3=832.67
(a) Labour charges for laying
(b) Overheads & Contractors Profit
(c) Cost for 5 metres = a+b
Rate per metre = c/5
500 mm dia pipe
Weight of 5m length =(892+971+1049)/3=970.67
(a) Labour charges for laying
(b) Overheads & Contractors Profit
(c) Cost for 5 metres = a+b
Rate per metre = c/5
600 mm dia pipe
Weight of 5m length =(1188+1296+1404)/3=1296
(a) Labour charges for laying
(b) Overheads & Contractors Profit
(c) Cost for 5 metres = a+b
Rate per metre = c/5
700mm dia pipe s/s for 5m
Weight of 5m length =(1533+1675+1808)/3=1672
(a) Labour charges for laying
(b) Overheads & Contractors Profit
(c) Cost for 5 metres = a+b
Rate per metre = c/5
750 mm dia pipe
Weight of 5m length =(1718+1876+2029)/3=1874.33
(a) Labour charges for laying
(b) Overheads & Contractors Profit
(c) Cost for 5 metres = a+b
Rate per metre = c/5
800 mm dia pipe
Weight of 5m length =(1922+2093+2263)/3=2092.67
(a) Labour charges for laying
(b) Overheads & Contractors Profit
(c) Cost for 5 metres = a+b
Rate per metre = c/5

Rate
Rs.
5

Amt
Rs.
6

PHE
Remarks
7

865

Index-code

S No
1

Description

Unit

Quantity

kgs

2544.000

kgs

3068.000

kgs

22.490

kgs

28.450

kgs

36.950

kgs

46.470

kgs

66.860

kgs

90.530

kgs

116.860

kgs

147.320

Rate
Rs.
5

Amt
Rs.
6

PHE
Remarks
7

xvi 900 mm dia pipe

Weight of 5m length =(2342+2544+2766)/3=2554


(a) Labour charges for laying
(b) Overheads & Contractors Profit
(c) Cost for 5 metres = a+b
Rate per metre = c/5
xvii 1000 mm dia pipe
Weight of 5m length =(2814+3072+3318)/3=3068
(a) Labour charges for laying
(b) Overheads & Contractors Profit
(c) Cost for 5 metres = a+b
Rate per metre = c/5
2

PHE-LCIF-2

Lowering C.I. / D.I. Pipes (all classes) and specials (fittings) with flanged
ends carefully into trench and laying them true to alignment and gradient
including all sundries but excluding cost and conveyance of pipes from
source of supply. (Reference to specifications. BIS No.3114/1994)
Note : The cost of lowering and laying is taken as per sub analysis made
for S/S ends.

Details of cost for 10m


80 mm dia pipe
Weight of 1m length = 19.8+(2x3.7)/2.75 = 22.49 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
Rate per metre
ii 100 mm dia pipe
Weight of 1m length = 25.4+(2x4.2)/2.75 = 28.45 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
Rate per metre
iii 125 mm dia pipe
Weight of 1m length = 33.1+(2x5.3)/2.75 = 36.95 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
Rate per metre
iv 150mm dia pipe
Weight of 1m length = 41.6+(2x6.7)/2.75 = 46.47 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
Rate per metre
v 200 mm dia pipe
Weight of 1m length = 60.1+(2x9.3)/2.75 = 66.86 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
Rate per metre
vi 250 mm dia pipe
Weight of 1m length = 81.8+(2x12)/2.75 = 90.53 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
Rate per metre
vii 300 mm dia pipe
Weight of 1m length = 106.1+(2x14.8)/2.75 = 116.86 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
Rate per metre
viii 350 mm dia pipe
Weight of 1m length = 133.5+(2x19)/2.75 = 147.32 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
Rate per metre
i

866

Index-code

S No

Description

Unit

Quantity

kgs

179.620

kgs

216.270

kgs

252.650

kgs

338.500

kgs

437.860

kgs

494.490

day
day

3.000
3.000

Hire chargers for Hydralic field test pressure testing including days
transportation of water @ Rs. 1200/- (1000+200) / day

3.000

1
ix

xi

xii

xiii

xiv

PHE-LCIF-2A

2A

400 mm dia pipe


Weight of 1m length = 162.6+(2x23.4)/2.75 = 179.62 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
Rate per metre
450mm dia pipe
Weight of 1m length = 197+(2x26.5)/2.75 = 216.27 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
Rate per metre
500 mm dia pipe
Weight of 1m length = 229.3+(2x32.1)/2.75 = 252.65 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
Rate per metre
600 mm dia pipe
Weight of 1m length = 306.5+(2x44)/2.75 = 338.5 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
Rate per metre
700mm dia pipe s/s for 5m
Weight of 1m length = 394.3+(2x59.9)/2.75 = 437.86 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
Rate per metre
750 mm dia pipe
Weight of 1m length = 443.8+(2x59.7)/2.75 = 494.49 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
Rate per metre
Sub Analysis : (Basic Data)

Rate
Rs.
5

Amt
Rs.
6

PHE
Remarks
7

OBSERVED DATA FOR TESTING OF 450 MM DIA PSC MAIN :


Pumping main to Hydralic field test pressure including
transportation of Water with minimum lead of 500 M

(Length = 500 Mts) taking out put / 500 Mts. Unit = 1 Rmt.
Labour
Fitters (2 x 3 days)
Fitters I Class
Fitters II Class
Machinery

Materials
Pressure guage
3/4" G.I. Pipe (20 mm)
Specials
Dummies
Diesel (2 Lts. / Hr) 30 Hrs.
(T) Total Rate per 500 Mts.
(r) Rate per 1 Rmt for 450 mm dia
(R) Rate per 1 Rmt for 10 mm dia = (10/450) x r
Note : Proportionate Testing Charges may be arrived,
keeping the diametre of pipe based on this analysis, for an
varities of pipes for various Dia Pipes.

Nos
RM
Ls
No.
Lts.

0.050
3.000
0.100
60.000

867

Index-code

S No

Description

Unit

Quantity

Jointing CI /DI pipes & fittings with s/s ends including cost of
pig lead, hemp yarn and sundries such as cost of fuel for
melting lead, filling with water with lead up to 500m and testing
to required pressure complete. (Reference to specifications. BIS
No.3114/94/12288:1997)
Details of cost for 10 joints
80 mm dia pipe
a) Labour
day

0.135

day

0.320

day

1.200

0.190

litre

0.330

PHE-JCIS-3

st

Plumber 1 class
nd
Plumber 2 class
Man mazdoor
b) Material
Fuel wood
Kerosene
Spun yarn
Pig lead
c) Testing
Testing of Pipelines with required pressure as per relevant IS
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment and
Materials needed for testing (as per Sub Analysis 2 A)
(d) Total = a+b+c
(e) Add for water charges @ 1%on Labour & Testing Charges

ii

1.000

kg

20.000

rm

50.000

day

0.220

day

0.530

day

1.500

0.250

litre

0.330

Amt
Rs.
6

PHE
Remarks
7

(f) Total = d+e


(g) Overheads & Contractors Profit
(h) Cost for 10 joints (f+g)
Rate per joint =h/10
100 mm dia pipe
a) Labour
st

Plumber 1 class
nd
Plumber 2 class
Man mazdoor
b) Material
Fuel wood
Kerosene
Spun yarn
Pig lead
c) Testing
Testing of Pipelines with required pressure as per relevant IS
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment and
Materials needed for testing (as per Sub Analysis 2 A)

iii

kg

Rate
Rs.
5

kg

1.800

kg

24.000

rm

50.000

day

0.220

day

0.530

day

1.500

0.370

litre

0.700

(d) Total = a+b+c


(e) Add for water charges @ 1% on Labour & Testing Charges
(f) Total = d+e
(g) Overheads & Contractors Profit
(h) Cost for 10 joints (f+g)
Rate per joint =h/10
125 mm dia pipe
a) Labour
Plumber 1st class
Plumber 2nd class
Man mazdoor
b) Material
Fuel wood
Kerosene
Spun yarn
Pig lead

kg

2.000

kg

28.000

868

Index-code

S No
1

Description

Unit

Quantity

rm

50.000

day

0.270

day

0.630

day

1.650

0.420

litre

0.760

c) Testing
Testing of Pipelines with required pressure as per relevant IS
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)

iv

Amt
Rs.
6

PHE
Remarks
7

(d) Total = a+b+c


(e) Add for water charges @ 1%on Labour & Testing Charges
(f) Total = d+e
(g) Overheads & Contractors Profit
(h) Cost for 10 joints (f+g)
Rate per joint =h/10
150 mm dia pipe
a) Labour
st

Plumber 1 class
nd
Plumber 2 class
Man mazdoor
b) Material
Fuel wood
Kerosene
Spun yarn
Pig lead
c) Testing
Testing of Pipelines with required pressure as per relevant IS
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)

Rate
Rs.
5

kg

2.000

kg

36.000

rm

50.000

day

0.270

day

0.630

day

1.650

0.560

litre

0.756

(d) Total = a+b+c


(e) Add for water charges @ 1%on Labour & Testing Charges
(f) Total = d+e
(g) Overheads & Contractors Profit
(h) Cost for 10 joints (f+g)
Rate per joint =h/10
200 mm dia pipe
a) Labour
Plumber 1st class
Plumber 2nd class
Man mazdoor
b) Material
Fuel wood
Kerosene
Spun yarn
Pig lead
c) Testing
Testing of Pipelines with required pressure as per relevant IS
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)

kg

3.000

kg

54.000

rm

50.000

(d) Total = a+b+c


(e) Add for water charges @ 1%on Labour & Testing Charges
(f) Total = d+e
(g) Overheads & Contractors Profit
(h) Cost for 10 joints (f+g)
Rate per joint =h/10

869

Index-code

S No
1
vi

Description

Unit

Quantity

day

0.280

day
day

0.650
1.800

q
litre
kg

0.650
1.140
3.500

kg

66.000

rm

50.000

day

0.360

day

0.840

day

1.800

q
litre
kg

0.750
1.520
4.800

kg

76.000

rm

50.000

day

0.400

day

0.950

day

2.250

q
litre

0.930
1.700

Rate
Rs.
5

Amt
Rs.
6

PHE
Remarks
7

250 mm dia pipe


a) Labour
st

Plumber 1 class
nd
Plumber 2 class
Man mazdoor
b) Material
Fuel wood
Kerosene
Spun yarn
Pig lead
c) Testing
Testing of Pipelines with required pressure as per relevant IS
Specification including filling with water with a water lead upto 500 M,
including hire charges of testing equipment, labour and Materials needed
for testing (as per Sub Analysis 2 A)

(d) Total = a+b+c


(e) Add for water charges @ 1%on Labour & Testing Charges
(f) Total = d+e
(g) Overheads & Contractors Profit
(h) Cost for 10 joints (f+g)
Rate per joint =h/10
vii 300 mm dia pipe
a) Labour
st

Plumber 1 class
nd
Plumber 2 class
Man mazdoor
b) Material
Fuel wood
Kerosene
Spun yarn
Pig lead
c) Testing
Testing of Pipelines with required pressure as per relevant IS
Specification including filling with water with a water lead upto 500 M,
including hire charges of testing equipment, labour and Materials needed
for testing (as per Sub Analysis 2 A)

(d) Total = a+b+c


(e) Add for water charges @ 1%on Labour & Testing Charges
(f) Total = d+e
(g) Overheads & Contractors Profit
(h) Cost for 10 joints (f+g)
Rate per joint =h/10
viii 350 mm dia pipe
a) Labour
Plumber 1st class
nd

Plumber 2 class
Man mazdoor
b) Material
Fuel wood
Kerosene
Spun yarn
Pig lead
c) Testing
Testing of Pipelines with required pressure as per relevant IS
Specification including filling with water with a water lead upto 500 M,
including hire charges of testing equipment, labour and Materials needed
for testing (as per Sub Analysis 2 A)

kg

6.000

kg

90.000

rm

50.000

(d) Total = a+b+c


(e) Add for water charges @ 1%on Labour & Testing Charges
(f) Total = d+e
(g) Overheads & Contractors Profit
(h) Cost for 10 joints (f+g)
Rate per joint =h/10

870

Index-code

S No

Description

Unit

Quantity

Plumber 1 class
nd
Plumber 2 class
Man mazdoor
b) Material
Fuel wood
Kerosene
Spun yarn
Pig lead
c) Testing
Testing of Pipelines with required pressure as per relevant IS
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)

day

0.310

day

0.740

day

2.250

q
litre

1.120
1.700

1
ix

Rate
Rs.
5

Amt
Rs.
6

PHE
Remarks
7

400 mm dia pipe


a) Labour
st

kg

7.500

kg

105.000

rm

50.000

day

0.540

day

1.260

day

2.550

1.210

litre

2.270

(d) Total = a+b+c


(e) Add for water charges @ 1%on Labour & Testing Charges

(f) Total = d+e


(g) Overheads & Contractors Profit
(h) Cost for 10 joints (f+g)
Rate per joint =h/10
450 mm dia pipe
a) Labour
Plumber 1st class
Plumber 2nd class
Man mazdoor
b) Material
Fuel wood
Kerosene
Spun yarn
Pig lead
c) Testing
Testing of Pipelines with required pressure as per relevant IS
Specification including filling with water with a water lead upto 500 M,
including hire charges of testing equipment, labour and Materials needed
for testing (as per Sub Analysis 2 A)

kg

9.500

kg

150.000

rm

50.000

day

0.580

day

1.370

day

2.700

1.310

(d) Total = a+b+c


(e) Add for water charges @ 1%on Labour & Testing Charges

xi

(f) Total = d+e


(g) Overheads & Contractors Profit
(h) Cost for 10 joints (f+g)
Rate per joint =h/10
500 mm dia pipe
a) Labour
Plumber 1st class
Plumber 2nd class
Man mazdoor
b) Material
Fuel wood
Kerosene
Spun yarn
Pig lead
c) Testing
Testing of Pipelines with required pressure as per relevant IS
Specification including filling with water with a water lead upto 500 M,
including hire charges of testing equipment, labour and Materials needed
for testing (as per Sub Analysis 2 A)

litre

2.270

kg

10.000

kg

160.000

rm

50.000

(d) Total = a+b+c

871

Index-code

S No
1

Description

Unit

Quantity

day

0.680

day

1.570

day

3.000

1.680

Rate
Rs.
5

Amt
Rs.
6

PHE
Remarks
7

(e) Add for water charges @ 1%on Labour & Testing Charges
(f) Total = d+e
(g) Overheads & Contractors Profit
(h) Cost for 10 joints (f+g)
Rate per joint =h/10
xii 600 mm dia pipe
a) Labour
Plumber 1st class
Plumber 2nd class
Man mazdoor
b) Material
Fuel wood
Kerosene
Spun yarn
Pig lead
c) Testing
Testing of Pipelines with required pressure as per relevant IS
Specification including filling with water with a water lead upto 500 M,
including hire charges of testing equipment, labour and Materials needed
for testing (as per Sub Analysis 2 A)

litre

2.540

kg

12.000

kg

205.000

rm

50.000

day

0.770

day

1.780

day

3.300

2.100

(d) Total = a+b+c


(e) Add for water charges @ 1%on Labour & Testing Charges
(f) Total = d+e
(g) Overheads & Contractors Profit
(h) Cost for 10 joints (f+g)
Rate per joint =h/10
xiii 700 mm dia pipe
a) Labour
Plumber 1st class
Plumber 2nd class
Man mazdoor
b) Material
Fuel wood
Kerosene
Spun yarn
Pig lead
c) Testing
Testing of Pipelines with required pressure as per relevant IS
Specification including filling with water with a water lead upto 500 M,
including hire charges of testing equipment, labour and Materials needed
for testing (as per Sub Analysis 2 A)

litre

3.200

kg

13.500

kg

240.000

rm

50.000

day

0.770

day

1.780

day

3.300

2.400

(d) Total = a+b+c


(e) Add for water charges @ 1%on Labour & Testing Charges
(f) Total = d+e
(g) Overheads & Contractors Profit
(h) Cost for 10 joints (f+g)
Rate per joint =h/10
xiv 750 mm dia pipe
a) Labour
Plumber 1st class
Plumber 2nd class
Man mazdoor
b) Material
Fuel wood
Kerosene
Spun yarn
Pig lead

litre

3.500

kg

14.500

kg

270.000

872

Index-code

S No

Description

Unit

Quantity

Testing of Pipelines with required pressure as per relevant IS


Specification including filling with water with a water lead upto 500 M,
including hire charges of testing equipment, labour and Materials needed
for testing (as per Sub Analysis 2 A)

rm

50.000

day

0.770

day

1.780

day

3.300

2.330

Rate
Rs.
5

Amt
Rs.
6

PHE
Remarks
7

c) Testing

(d) Total = a+b+c


(e) Add for water charges @ 1%on Labour & Testing Charges
(f) Total = d+e
(g) Overheads & Contractors Profit
(h) Cost for 10 joints (f+g)
Rate per joint =h/10
xv 800 mm dia pipe
a) Labour
st

Plumber 1 class
nd
Plumber 2 class
Man mazdoor
b) Material
Fuel wood
Kerosene
Spun yarn
Pig lead
c) Testing
Testing of Pipelines with required pressure as per relevant IS
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment and Labour,
Materials needed for testing (as per Sub Analysis 2 A)

litre

3.410

kg

15.300

kg

325.000

rm

50.000

(d) Total = a+b+c


(e) Add for water charges @ 1% on Labour & Testing Charges

PHE-JCIR-4

(f) Total = d+e


(g) Overheads & Contractors Profit
(h) Cost for 10 joints (f+g)
Rate per joint =h/10
Jointing C.I., D.I. pipes and fittings with rubber gasket (push-onjoint), excluding the cost of the gasket but including all sundries
filling with water, with a water lead up to 500m and testing to
required pressure, etc. complete Reference to specifications IS
3114/1994/12888/1987
Note : Rubber Gaskets shall be added seperately.
Details of cost for 10 Joints
80 mm dia pipe
a) Labour
day
Plumber 2nd class
day
Man mazdoor
b) Material
each
Rubber gasket
c) Testing
Testing of Pipelines with required pressure as per relevant IS rm
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)

0.300
0.800
50.000

(d) Total = a+b+c


(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e+f
(g) Overheads & Contractors Profit
(h) Cost for 10 joints (f+g)
Rate per joint = h/10

873

Index-code

S No
1
ii

Description

Unit

Quantity

Rate
Rs.
5

Amt
Rs.
6

PHE
Remarks
7

100 mm dia pipe


a) Labour
nd
day
Plumber 2 class
day
Man mazdoor
b) Material
each
Rubber gasket
c) Testing
Testing of Pipelines with required pressure as per relevant IS rm
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)

0.500
1.000

50.000

(d) Total = a+b+c


(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e+f
(g) Overheads & Contractors Profit
(h) Cost for 10 joints (f+g)
Rate per joint = h/10
iii

125 mm dia pipe


a) Labour
nd
day
Plumber 2 class
day
Man mazdoor
b) Material
each
Rubber gasket
c) Testing
Testing of Pipelines with required pressure as per relevant IS rm
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)

0.500
1.000

50.000

(d) Total = a+b+c


(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e+f
(g) Overheads & Contractors Profit
(h) Cost for 10 joints (f+g)
Rate per joint = h/10
iv

150 mm dia pipe


a) Labour
day
Plumber 2nd class
day
Man mazdoor
b) Material
each
Rubber gasket
c) Testing
Testing of Pipelines with required pressure as per relevant IS rm
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)

0.600
1.100

50.000

(d) Total = a+b+c


(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e+f
(g) Overheads & Contractors Profit
(h) Cost for 10 joints (f+g)
Rate per joint = h/10

874

Index-code

S No
1
v

Description

Unit

Quantity

Rate
Rs.
5

Amt
Rs.
6

PHE
Remarks
7

200 mm dia pipe


a) Labour
nd
day
Plumber 2 class
day
Man mazdoor
b) Material
each
Rubber gasket
c) Testing
Testing of Pipelines with required pressure as per relevant IS rm
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)

0.600
1.100

50.000

(d) Total = a+b+c


(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e+f
(g) Overheads & Contractors Profit
(h) Cost for 10 joints (f+g)
Rate per joint = h/10
vi

250 mm dia pipe


a) Labour
nd
day
Plumber 2 class
day
Man mazdoor
b) Material
each
Rubber gasket
c) Testing
Testing of Pipelines with required pressure as per relevant IS rm
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)

0.620
1.200

50.000

(d) Total = a+b+c


(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e+f
(g) Overheads & Contractors Profit
(h) Cost for 10 joints (f+g)
Rate per joint = h/10
vii

300 mm dia pipe


a) Labour
day
Plumber 2nd class
day
Man mazdoor
b) Material
each
Rubber gasket
c) Testing
Testing of Pipelines with required pressure as per relevant IS rm
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)

0.800
1.200

50.000

(d) Total = a+b+c


(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e+f
(g) Overheads & Contractors Profit
(h) Cost for 10 joints (f+g)
Rate per joint = h/10

875

Index-code

S No
1

Description

Unit

Quantity

Rate
Rs.
5

Amt
Rs.
6

PHE
Remarks
7

viii 350 mm dia pipe

a)

Labour
nd
day
Plumber 2 class
day
Man mazdoor
b) Material
each
Rubber gasket
c) Testing
Testing of Pipelines with required pressure as per relevant IS rm
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)

0.900
1.500

50.000

(d) Total = a+b+c


(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e+f
(g) Overheads & Contractors Profit
(h) Cost for 10 joints (f+g)
Rate per joint = h/10
viii 400 mm dia pipe

a)

Labour
nd
day
Plumber 2 class
day
Man mazdoor
b) Material
each
Rubber gasket
c) Testing
Testing of Pipelines with required pressure as per relevant IS rm
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)

1.000
1.500

50.000

(d) Total = a+b+c


(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e+f
(g) Overheads & Contractors Profit
(h) Cost for 10 joints (f+g)
Rate per joint = h/10
ix

450 mm dia pipe


a) Labour
day
Plumber 2nd class
day
Man mazdoor
b) Material
each
Rubber gasket
c) Testing
Testing of Pipelines with required pressure as per relevant IS rm
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)

1.200
1.700

50.000

(d) Total = a+b+c


(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e+f
(g) Overheads & Contractors Profit
(h) Cost for 10 joints (f+g)
Rate per joint = h/10

876

Index-code

S No
1
x

Description

Unit

Quantity

Rate
Rs.
5

Amt
Rs.
6

PHE
Remarks
7

500 mm dia pipe


a) Labour
nd
day
Plumber 2 class
day
Man mazdoor
b) Material
each
Rubber gasket
c) Testing
Testing of Pipelines with required pressure as per relevant IS rm
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)

1.300
1.800

50.000

(d) Total = a+b+c


(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e+f
(g) Overheads & Contractors Profit
(h) Cost for 10 joints (f+g)
Rate per joint = h/10
xi

600 mm dia pipe


a) Labour
nd
day
Plumber 2 class
day
Man mazdoor
b) Material
each
Rubber gasket
c) Testing
Testing of Pipelines with required pressure as per relevant IS rm
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)

1.500
2.000

50.000

(d) Total = a+b+c


(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e+f
(g) Overheads & Contractors Profit
(h) Cost for 10 joints (f+g)
Rate per joint = h/10
xii

650 mm dia pipe


a) Labour
day
Plumber 2nd class
day
Man mazdoor
b) Material
each
Rubber gasket
c) Testing
Testing of Pipelines with required pressure as per relevant IS rm
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)

1.600
2.100

50.000

(d) Total = a+b+c


(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e+f
(g) Overheads & Contractors Profit
(h) Cost for 10 joints (f+g)
Rate per joint = h/10

877

Index-code

S No
1

Description

Unit

Quantity

Rate
Rs.
5

Amt
Rs.
6

PHE
Remarks
7

xiii 700 mm dia pipe

a)

Labour
nd
day
Plumber 2 class
day
Man mazdoor
b) Material
each
Rubber gasket
c) Testing
Testing of Pipelines with required pressure as per relevant IS rm
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)

1.700
2.200

50.000

(d) Total = a+b+c


(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e+f
(g) Overheads & Contractors Profit
(h) Cost for 10 joints (f+g)
Rate per joint = h/10
xix 750 mm dia pipe

a)

Labour
nd
day
Plumber 2 class
day
Man mazdoor
b) Material
each
Rubber gasket
c) Testing
Testing of Pipelines with required pressure as per relevant IS rm
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)

1.700
2.200

50.000

(d) Total = a+b+c


(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e+f
(g) Overheads & Contractors Profit
(h) Cost for 10 joints (f+g)
Rate per joint = h/10
xx

800 mm dia pipe


a) Labour
Plumber 1st class
Plumber 2nd class
Foreman (work inspector) Non technical
b) Material
Rubber gasket
c) Testing
Testing of Pipelines with required pressure as per relevant IS
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)

day

2.350

day

4.700

day

0.650

each
rm

50.000

(d) Total = a+b+c


(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e+f
(g) Overheads & Contractors Profit
(h) Cost for 10 joints (f+g)
Rate per joint = h/10

878

Index-code

S No

Description

Unit

Quantity

Plumber 1 class
nd
Plumber 2 class
Foreman (work inspector) Non technical
b) Material
Rubber gasket
c) Testing
Testing of Pipelines with required pressure as per relevant IS
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)

day

2.750

day

5.500

day

0.700

Rate
Rs.
5

Amt
Rs.
6

PHE
Remarks
7

xxi 900 mm dia pipe

a)

Labour
st

each
rm

50.000

day

3.000

day

6.000

day

0.750

(d) Total = a+b+c


(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e+f
(g) Overheads & Contractors Profit
(h) Cost for 10 joints (f+g)
Rate per joint = h/10
xxii 1000 mm dia pipe

a)

Labour
st

Plumber 1 class
Plumber 2nd class
Foreman (work inspector) Non technical
b) Material
Rubber gasket
c) Testing
Testing of Pipelines with required pressure as per relevant IS
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)

each
rm

50.000

Plumber 1st class


Plumber 2nd class
Man mazdoor
b) Material
Bolts and nuts 16mm dia 60mm long
Rubber insertion 5mm thick
White lead
c) Testing

day

0.090

day

0.210

day

0.800

kg
kg

6.800
2.125

Testing of Pipelines with required pressure as per relevant IS


Specification including filling with water with a water lead upto 500 M,
including hire charges of testing equipment, labour and Materials needed
for testing (as per Sub Analysis 2 A)

rm

(d) Total = a+b+c


(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e+f
(g) Overheads & Contractors Profit
(h) Cost for 10 joints (f+g)
Rate per joint = h/10
5

PHE-JCIF-5

Jointing CI pipes, fittings and valves with flanged ends including cost of
jointing materials such as bolts, rubber insertion, white lead including
filling with water, with lead up to 500 meters and testing to required
pressure complete. (Reference to specifications. BIS No.3114/1994.)

Details of cost for 10 joints


80 mm dia pipe
a) Labour

27.500

(d) Total = a+b+c

879

Index-code

S No
1

ii

Description

Unit

Quantity

(e) Add for water charges @ 1% on Labour & Testing


Charges
(f) Total = d+e+f
(g) Overheads & Contractors Profit
(h) Cost for 10 joints (f+g)
Rate per joint = h/10
100 mm dia pipe
a) Labour
day
Plumber 1st class
nd
day
Plumber 2 class
day
Man mazdoor
b) Material
kg
Bolts and nuts 16mm dia 60mm long
kg
Rubber insertion 5mm thick
White lead
c) Testing
Testing of Pipelines with required pressure as per relevant IS rm
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)

Rate
Rs.
5

Amt
Rs.
6

PHE
Remarks
7

0.150
0.350
1.000
13.600
2.540

27.500

(d) Total = a+b+c


(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e+f
(g) Overheads & Contractors Profit
(h) Cost for 10 joints (f+g)
Rate per joint = h/10
iii

125 mm dia pipe


a) Labour
st

Plumber 1 class
Plumber 2nd class
Man mazdoor
b) Material
Bolts and nuts 16mm dia 60mm long
Rubber insertion 5mm thick
White lead
c) Testing

day

0.150

day

0.350

day

1.000

kg
kg

13.600
3.140

Testing of Pipelines with required pressure as per relevant IS


Specification including filling with water with a water lead upto 500 M,
including hire charges of testing equipment, labour and Materials needed
for testing (as per Sub Analysis 2 A)

rm

27.500

day

0.180

day

0.420

day

1.100

kg
kg

24.000
4.300

(d) Total = a+b+c


(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e+f
(g) Overheads & Contractors Profit
(h) Cost for 10 joints (f+g)
Rate per joint = h/10
iv

150 mm dia pipe


a) Labour
Plumber 1st class
Plumber 2nd class
Man mazdoor
b) Material
Bolts and nuts 20mm dia 65mm long
Rubber insertion 5mm thick
White lead

880

Index-code

S No
1

Description

Unit

Quantity

rm

27.500

c) Testing
Testing of Pipelines with required pressure as per relevant IS
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)

Rate
Rs.
5

Amt
Rs.
6

PHE
Remarks
7

(d) Total = a+b+c


(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e+f
(g) Overheads & Contractors Profit
(h) Cost for 10 joints (f+g)
Rate per joint = h/10
200 mm dia pipe
a) Labour
st
day
Plumber 1 class
nd
day
Plumber 2 class
day
Man mazdoor
b) Material
kg
Bolts and nuts 20mm dia 70mm long
kg
Rubber insertion 5mm thick
White lead
c) Testing
Testing of Pipelines with required pressure as per relevant IS rm
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)

0.180
0.420
1.100
25.200
6.160

27.500

(d) Total = a+b+c


(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e+f
(g) Overheads & Contractors Profit
(h) Cost for 10 joints (f+g)
Rate per joint = h/10
vi

250 mm dia pipe


a) Labour
day
Plumber 1st class
nd
day
Plumber 2 class
day
Man mazdoor
b) Material
kg
Bolts and nuts 20mm dia 75mm long
kg
Rubber insertion 5mm thick
White lead
c) Testing
Testing of Pipelines with required pressure as per relevant IS rm
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)
(d) Total = a+b+c
(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e+f
(g) Overheads & Contractors Profit
(h) Cost for 10 joints (f+g)
Rate per joint = h/10

0.200
0.420
1.200
39.600
8.500

27.500

881

Index-code

S No

Description

Unit

Quantity

Plumber 1 class
nd
Plumber 2 class
Man mazdoor
b) Material
Bolts and nuts 20mm dia 75mm long
Rubber insertion 5mm thick
White lead
c) Testing

day

0.240

day

0.560

day

1.200

kg

39.600

kg

10.280

Testing of Pipelines with required pressure as per relevant IS


Specification including filling with water with a water lead upto 500 M,
including hire charges of testing equipment, labour and Materials needed
for testing (as per Sub Analysis 2 A)

rm

27.500

Plumber 1 class
Plumber 2nd class
Man mazdoor
b) Material
Bolts and nuts 20mm dia 80mm long
Rubber insertion 8mm thick
White lead
c) Testing

day

0.300

day

0.600

day

1.500

kg

54.400

kg

21.260

Testing of Pipelines with required pressure as per relevant IS


Specification including filling with water with a water lead upto 500 M,
including hire charges of testing equipment, labour and Materials needed
for testing (as per Sub Analysis 2 A)

rm

27.500

Plumber 1st class


Plumber 2nd class
Man mazdoor
b) Material
Bolts and nuts 24mm dia 85mm long
Rubber insertion 8mm thick
White lead
c) Testing

day

0.300

day

0.700

day

1.500

kg
kg

98.400
27.640

Testing of Pipelines with required pressure as per relevant IS


Specification including filling with water with a water lead upto 500 M,
including hire charges of testing equipment, labour and Materials needed
for testing (as per Sub Analysis 2 A)

rm

27.500

day

0.360

day

0.840

1
vii

Rate
Rs.
5

Amt
Rs.
6

PHE
Remarks
7

300 mm dia pipe


a) Labour
st

(d) Total = a+b+c


(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e+f
(g) Overheads & Contractors Profit
(h) Cost for 10 joints (f+g)
Rate per joint = h/10
viii 350 mm dia pipe
a) Labour
st

(d) Total = a+b+c


(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e+f
(g) Overheads & Contractors Profit
(h) Cost for 10 joints (f+g)
Rate per joint = h/10
ix

350 mm dia pipe


a) Labour

(d) Total = a+b+c


(e) Add for water charges @ 1% on Labour & Testing Charges

(f) Total = d+e+f


(g) Overheads & Contractors Profit
(h) Cost for 10 joints (f+g)
Rate per joint = h/10
450 mm dia pipe
a) Labour
Plumber 1st class
Plumber 2nd class

882

Index-code

S No

Description

Unit

Quantity

3
day

4
1.700

kg
kg

123.000
22.660

rm

27.500

Plumber 1st class


Plumber 2nd class
Man mazdoor
b) Material
Bolts and nuts 24mm dia 90mm long
Rubber insertion 8mm thick
White lead
c) Testing

day

0.390

day

0.910

day

1.800

kg
kg

134.000
38.190

Testing of Pipelines with required pressure as per relevant IS


Specification including filling with water with a water lead upto 500 M,
including hire charges of testing equipment, labour and Materials needed
for testing (as per Sub Analysis 2 A)

rm

27.500

Plumber 1st class


Plumber 2nd class
Man mazdoor
b) Material
Bolts and nuts 24mm dia 90mm long
Rubber insertion 8mm thick
White lead
c) Testing

day

0.450

day

1.050

day

2.000

kg

192.000

kg

51.710

Testing of Pipelines with required pressure as per relevant IS


Specification including filling with water with a water lead upto 500 M,
including hire charges of testing equipment, labour and Materials needed
for testing (as per Sub Analysis 2 A)

rm

27.500

Man mazdoor
b) Material
Bolts and nuts 24mm dia 85mm long
Rubber insertion 8mm thick
White lead
c) Testing
Testing of Pipelines with required pressure as per relevant IS
Specification including filling with water with a water lead upto 500 M,
including hire charges of testing equipment, labour and Materials needed
for testing (as per Sub Analysis 2 A)

xi

Rate
Rs.
5

Amt
Rs.
6

PHE
Remarks
7

(d) Total = a+b+c


(e) Add for water charges @ 1% on Labour & Testing
(f) Total = d+e+f
(g) Overheads & Contractors Profit
(h) Cost for 10 joints (f+g)
Rate per joint = h/10
500 mm dia pipe
a) Labour

(d) Total = a+b+c


(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e+f
(g) Overheads & Contractors Profit
(h) Cost for 10 joints (f+g)
Rate per joint = h/10
xii

600 mm dia pipe


a) Labour

(d) Total = a+b+c


(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e+f
(g) Overheads & Contractors Profit
(h) Cost for 10 joints (f+g)
Rate per joint = h/10

883

Index-code

S No
1

Description

Unit

Quantity

Rate
Rs.
5

Amt
Rs.
6

PHE
Remarks
7

xiii 700 mm dia pipe

a) Labour
st
day
Plumber 1 class
nd
day
Plumber 2 class
day
Man mazdoor
b) Material
kg
Bolts and nuts 24mm dia 90mm long
kg
Rubber insertion 8mm thick
White lead
c) Testing
Testing of Pipelines with required pressure as per relevant IS rm
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)

0.510
1.190
2.200
244.800
68.910

27.500

(d) Total = a+b+c


(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e+f
(g) Overheads & Contractors Profit
(h) Cost for 10 joints (f+g)
Rate per joint = h/10
xiv 750 mm dia pipe

a)

Labour
st
day
Plumber 1 class
nd
day
Plumber 2 class
day
Man mazdoor
b) Material
kg
Bolts and nuts 24mm dia 90mm long
kg
Rubber insertion 8mm thick
White lead
c) Testing
Testing of Pipelines with required pressure as per relevant IS rm
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)

PHE-LRCS-6

0.510
1.190
2.200
260.400
78.430

27.500

(d) Total = a+b+c


(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e+f
(g) Overheads & Contractors Profit
(h) Cost for 10 joints (f+g)
Rate per joint = h/10
Lowering the RCC S/S pipes carefully into the trenches laying
them true to alignment and gradient, jointing with rubber rings
and testing including filling with water with a water lead upto 500
meters including cost of rubber rings as per BIS No. 783/1985
Unit= 1 rmt
Taking out put 100 rmt
80 mm dia
a) Labour
Mason 1st class
Mason 2nd class
Man mazdoor
Woman mazdoor(water carrier)
b) Material
Rubber rings conforming BIS 5382/1985

day

0.780

day

1.800

day

5.000

day

1.300

each

50.000

884

Index-code

S No
1

Description

Unit

Quantity

rm

100.000

day

0.960

day

2.240

day

6.300

day

1.600

each

50.000

rm

100.000

day

1.170

day

2.730

day

7.800

day

1.600

each

50.000

rm

100.000

c) Testing
Testing of Pipelines with required pressure as per relevant IS
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)

Rate
Rs.
5

Amt
Rs.
6

PHE
Remarks
7

(d) Total = a+b+c


(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e
(g) Overheads & Contractors Profit
(h) Cost for 100 rmt (f+g)
Rate per rmt = h/100
ii

100 mm dia
a) Labour
Mason 1st class
Mason 2nd class
Man mazdoor
Woman mazdoor(water carrier)
b) Material
Rubber rings conforming BIS 5382/1985
c) Testing
Testing of Pipelines with required pressure as per relevant IS
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)
(d) Total = a+b+c
(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e
(g) Overheads & Contractors Profit
(h) Cost for 100 rmt (f+g)
Rate per rmt = h/100

iii

150 mm dia
a) Labour
Mason 1st class
nd
Mason 2 class
Man mazdoor
Woman mazdoor(water carrier)
b) Material
Rubber rings conforming BIS 5382/1985
c) Testing
Testing of Pipelines with required pressure as per relevant IS
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)
(d) Total = a+b+c
(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e
(g) Overheads & Contractors Profit
(h) Cost for 100 rmt (f+g)
Rate per rmt = h/100

885

Index-code

S No

Description

Unit

Quantity

Mason 1 class
nd
Mason 2 class
Man mazdoor
Woman mazdoor(water carrier)
b) Material
Rubber rings conforming BIS 5382/1985
c) Testing
Testing of Pipelines with required pressure as per relevant IS
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)

day

1.170

day

2.730

day

7.800

day

1.600

each

50.000

rm

100.000

day

1.620

1
iv

Rate
Rs.
5

Amt
Rs.
6

PHE
Remarks
7

200 mm dia
a) Labour
st

(d) Total = a+b+c


(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e
(g) Overheads & Contractors Profit
(h) Cost for 100 rmt (f+g)
Rate per rmt = h/100
v

225 mm dia
a) Labour
st

Mason 1 class
Mason 2nd class
Man mazdoor
Woman mazdoor(water carrier)
b) Material
Rubber rings conforming BIS 5382/1985
c) Testing
Testing of Pipelines with required pressure as per relevant IS
Specification including filling with water with a water lead upto 500 M,
including hire charges of testing equipment, labour and Materials needed
for testing (as per Sub Analysis 2 A)

day

3.780

day

10.500

day

2.300

each

50.000

rm

100.000

day

1.620

(d) Total = a+b+c


(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e
(g) Overheads & Contractors Profit
(h) Cost for 100 rmt (f+g)
Rate per rmt = h/100
vi

250 mm dia
a) Labour
Mason 1st class
Mason 2nd class
Man mazdoor
Woman mazdoor(water carrier)
b) Material
Rubber rings conforming BIS 5382/1985
c) Testing
Testing of Pipelines with required pressure as per relevant IS
Specification including filling with water with a water lead upto 500 M,
including hire charges of testing equipment, labour and Materials needed
for testing (as per Sub Analysis 2 A)

day

3.780

day

10.500

day

2.300

each

50.000

rm

100.000

(d) Total = a+b+c


(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e
(g) Overheads & Contractors Profit
(h) Cost for 100 rmt (f+g)
Rate per rmt = h/100

886

Index-code

S No
1
vii

Description

Unit

Quantity

day

1.750

Rate
Rs.
5

Amt
Rs.
6

PHE
Remarks
7

300 mm dia
a) Labour
st

Mason 1 class
nd
Mason 2 class
Man mazdoor
Woman mazdoor(water carrier)
b) Material
Rubber rings conforming BIS 5382/1985
c) Testing
Testing of Pipelines with required pressure as per relevant IS
Specification including filling with water with a water lead upto 500 M,
including hire charges of testing equipment, labour and Materials needed
for testing (as per Sub Analysis 2 A)

day

4.140

day

11.600

day

2.300

each

40.000

rm

100.000

day

1.900

(d) Total = a+b+c


(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e
(g) Overheads & Contractors Profit
(h) Cost for 100 rmt (f+g)
Rate per rmt = h/100
viii 350 mm dia

a)

Labour
st

Mason 1 class
Mason 2nd class
Man mazdoor
Woman mazdoor(water carrier)
b) Material
Rubber rings conforming BIS 5382/1985
c) Testing
Testing of Pipelines with required pressure as per relevant IS
Specification including filling with water with a water lead upto 500 M,
including hire charges of testing equipment, labour and Materials needed
for testing (as per Sub Analysis 2 A)

day

4.500

day

12.700

day

2.400

each

40.000

rm

100.000

day

2.100

(d) Total = a+b+c


(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e
(g) Overheads & Contractors Profit
(h) Cost for 100 rmt (f+g)
Rate per rmt = h/100
ix

400 mm dia
a) Labour
Mason 1st class
Mason 2nd class
Man mazdoor
Woman mazdoor(water carrier)
b) Material
Rubber rings conforming BIS 5382/1985
c) Testing
Testing of Pipelines with required pressure as per relevant IS
Specification including filling with water with a water lead upto 500 M,
including hire charges of testing equipment, labour and Materials needed
for testing (as per Sub Analysis 2 A)

day

4.900

day

13.900

day

2.900

each

40.000

rm

100.000

(d) Total = a+b+c


(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e
(g) Overheads & Contractors Profit
(h) Cost for 100 rmt (f+g)
Rate per rmt = h/100

887

Index-code

S No
1
x

Description

Unit

Quantity

day

2.250

Amt
Rs.
6

PHE
Remarks
7

450 mm dia
a) Labour
st

Mason 1 class
nd
Mason 2 class
Man mazdoor
Woman mazdoor(water carrier)
b) Material
Rubber rings conforming BIS 5382/1985
c) Testing
Testing of Pipelines with required pressure as per relevant IS
Specification including filling with water with a water lead upto 500 M,
including hire charges of testing equipment, labour and Materials needed
for testing (as per Sub Analysis 2 A)

xi

Rate
Rs.
5

day

5.250

day

15.000

day

3.300

each

40.000

rm

100.000

day
day
day
day

2.430
5.670
16.200
3.300

each

40.000

rm

100.000

day

2.750

(d) Total = a+b+c


(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e
(g) Overheads & Contractors Profit
(h) Cost for 100 rmt (f+g)
Rate per rmt = h/100
500 mm dia
a) Labour
Mason 1st class
nd
Mason 2 class
Man mazdoor
Woman mazdoor(water carrier)
b) Material
Rubber rings conforming BIS 5382/1985
c) Testing
Testing of Pipelines with required pressure as per relevant IS
Specification including filling with water with a water lead upto 500 M,
including hire charges of testing equipment, labour and Materials needed
for testing (as per Sub Analysis 2 A)

(d) Total = a+b+c


(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e
(g) Overheads & Contractors Profit
(h) Cost for 100 rmt (f+g)
Rate per rmt = h/100
xii

600 mm dia
a) Labour
Mason 1st class
Mason 2nd class
Man mazdoor
Woman mazdoor(water carrier)
b) Material
Rubber rings conforming BIS 5382/1985
c) Testing
Testing of Pipelines with required pressure as per relevant IS
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)

day

6.450

day

16.300

day

3.300

each

40.000

rm

100.000

(d) Total = a+b+c


(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e
(g) Overheads & Contractors Profit
(h) Cost for 100 rmt (f+g)
Rate per rmt = h/100

888

Index-code

S No
1
7

PHE-LJGI-7

ii

iii

Description

Unit

Quantity

2
Lowering and Jointing G.I. pipes and specials / fittings including
excavation of trench of 0.5m width and 0.50 m depth in all soils except
rock requiring blasting and refilling trenches after laying and jointing
pipes and also including cost of jointing materials but excluding the cost
of pipes. Reference to specifications. BIS No.783/85

day

0.060

day

0.160

cum

2.500

10.000

Details of cost for 10m


15mm dia nominal bore
a) Labour
Plumber 2nd class
Man mazdoor
E.W.Excavation & refilling 10x0.50x0.50=2.50cum
b) Material
G.I. pipes
white lead, hemp yarn, oil etc.
c) Machinery
Nil
(d) Total = a+b+c
(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e
(g) Overheads & Contractors Profit
(h) Cost for 100 rmt (f+g)
Rate per rmt = h/100
20mm dia nominal bore
a) Labour
Plumber 2nd class
Man mazdoor
E.W.Excavation & refilling 10x0.50x0.50=2.50cum
b) Material
G.I. pipes
white lead, hemp yarn, oil etc.
c) Machinery
Nil
(d) Total = a+b+c
(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e
(g) Overheads & Contractors Profit
(h) Cost for 100 rmt (f+g)
Rate per rmt = h/100
25mm dia nominal bore
a) Labour
Plumber 2nd class
Man mazdoor
E.W.Excavation & refilling 10x0.50x0.50=2.50cum
b) Material
G.I. pipes
white lead, hemp yarn, oil etc.
c) Machinery
Nil
(d) Total = a+b+c
(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e
(g) Overheads & Contractors Profit
(h) Cost for 100 rmt (f+g)
Rate per rmt = h/100

Rate
Rs.
5

Amt
Rs.
6

PHE
Remarks
7

L.S.

day

0.060

day

0.160

cum

2.500

10.000

L.S.

day

0.120

day

0.250

cum

2.500

10.000

L.S.

889

Index-code

S No

Description

Unit

Quantity

iv

32mm dia nominal bore


a) Labour
Plumber 2nd class
Man mazdoor
E.W.Excavation & refilling 10x0.50x0.50=2.50cum
b) Material
G.I. pipes
white lead, hemp yarn, oil etc.
c) Machinery
Nil
(d) Total = a+b+c
(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e
(g) Overheads & Contractors Profit
(h) Cost for 100 rmt (f+g)
Rate per rmt = h/100

day

0.120

day

0.250

cum

2.500

10.000

vi

40mm dia nominal bore


a) Labour
Plumber 2nd class
Man mazdoor
E.W.Excavation & refilling 10x0.50x0.50=2.50cum
b) Material
G.I. pipes
white lead, hemp yarn, oil etc.
c) Machinery
Nil
(d) Total = a+b+c
(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e
(g) Overheads & Contractors Profit
(h) Cost for 100 rmt (f+g)
Rate per rmt = h/100
50mm dia nominal bore
a) Labour
Plumber 2nd class
Man mazdoor
E.W.Excavation & refilling 10x0.50x0.50=2.50cum
b) Material
G.I. pipes
white lead, hemp yarn, oil etc.
c) Machinery
Nil
(d) Total = a+b+c
(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e
(g) Overheads & Contractors Profit
(h) Cost for 100 rmt (f+g)
Rate per rmt = h/100

Rate
Rs.
5

Amt
Rs.
6

PHE
Remarks
7

L.S.

day

0.160

day

0.330

cum

2.500

10.000

L.S.

day

0.160

day

0.330

cum

2.500

10.000

L.S.

890

Index-code

S No

Description

Unit

Quantity

vii

65mm dia nominal bore


a) Labour
Plumber 2nd class
Man mazdoor
E.W.Excavation & refilling 10x0.50x0.50=2.50cum
b) Material
G.I. pipes
white lead, hemp yarn, oil etc.
c) Machinery
Nil
(d) Total = a+b+c
(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e
(g) Overheads & Contractors Profit
(h) Cost for 100 rmt (f+g)
Rate per rmt = h/100

day

0.250

day

0.660

cum

2.500

10.000

Rate
Rs.
5

Amt
Rs.
6

PHE
Remarks
7

L.S.

viii 80mm dia nominal bore

ix

a) Labour
day
Plumber 2nd class
day
Man mazdoor
cum
E.W.Excavation & refilling 10x0.50x0.50=2.50cum
b) Material
m
G.I. pipes
L.S.
white lead, hemp yarn, oil etc.
c) Machinery
Nil
(d) Total = a+b+c
(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e
(g) Overheads & Contractors Profit
(h) Cost for 100 rmt (f+g)
Rate per rmt = h/100
100mm dia nominal bore
a) Labour
day
Plumber 2nd class
day
Man mazdoor
cum
E.W.Excavation & refilling 10x0.50x0.50=2.50cum
b) Material
m
G.I. pipes
L.S.
white lead, hemp yarn, oil etc.
c) Machinery
Nil
(d) Total = a+b+c

0.250
0.660
2.500
10.000

0.370
0.970
2.500
10.000

(e) Add for water charges @ 1% on Labour & Testing Charges

(f) Total = d+e


(g) Overheads & Contractors Profit
(h) Cost for 100 rmt (f+g)
Rate per rmt = h/100
150mm dia nominal bore
a) Labour
Plumber 2nd class
Man mazdoor
E.W.Excavation & refilling 10x0.50x0.50=2.50cum
b) Material
G.I. pipes
white lead, hemp yarn, oil etc.
c) Machinery
Nil
(d) Total = a+b+c

day

0.580

day

1.540

cum

2.500

10.000

L.S.

891

Index-code

S No
1

Description

Unit

Quantity

day

0.330

day

0.330

Each

1.000

Each

1.000

Rate
Rs.
5

Amt
Rs.
6

PHE
Remarks
7

(e) Add for water charges @ 1% on Labour & Testing


Charges
(f) Total = d+e
(g) Overheads & Contractors Profit
(h) Cost for 100 rmt (f+g)
Rate per rmt = h/100
8

PHE-GIDM-8

ii

iii

Making connection of G.I. distribution branch with G.I. main by


providing and fixing tee, including cutting and threading the
pipes and fixing tee etc., complete. Reference to specifications.
BIS No.783/85
Details of cost for 1 No
25mm branch from 40mm nominal dia main
a) Labour
Plumber 2nd class
Man mazdoor
b) Material
G.I. tee 25mm dia.
G.I. Jam nut 25mm

Sundries
c) Machinery
Nil
(d) Total = a+b+c
(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e
(g) Overheads & Contractors Profit
Rate per 1No (f+g)
50 mm branch from 80 mm nominal dia main
a) Labour
day
Plumber 2nd class
day
Man mazdoor
b) Material
Each
G.I. tee 50mm dia.
Each
G.I. Jam nut 50mm
Sundries
c) Machinery
Nil
(d) Total = a+b+c
(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e
(g) Overheads & Contractors Profit
Rate per 1No (f+g)
100mm branch from 150mm nominal dia main
a) Labour
day
Plumber 2nd class
day
Man mazdoor
b) Material
Each
G.I. tee 150mm dia.
Each
G.I. Jam nut 150mm

0.450
0.450
1.000
1.000

0.450
0.450
1.000
1.000

Sundries
c) Machinery
Nil
(d) Total = a+b+c
(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e
(g) Overheads & Contractors Profit
Rate per 1No (f+g)

892

Index-code

S No

Description

Unit

Quantity

Lowering and laying AC pressure pipes (class 5 & 10) in ready


made trenches true to alignment and gradient including all
sundries but excluding conveyance from source of supply.
Reference to specifications BIS 6530/72
Details of cost for 1rmt
Note : The Coat of lowring, laying is taken for 1 kg weight as per
sub-analysis made for CI SS ends.

Class 10 & 15 pipes :

kgs

6.225

kgs

7.990

kgs

10.262

kgs

13.665

kgs

22.200

kgs

28.450

kgs

38.562

kgs

47.237

kgs

60.275

kgs

71.625

PHE-LACP-9

Rate
Rs.
5

Amt
Rs.
6

PHE
Remarks
7

80 mm dia pipe
Weight of 1m length = (6.225+6.225)/2 = 6.225 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
Rate per metre
ii 100 mm dia pipe
Weight of 1m length = (7.8+8.18)/2 = 7.99 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
Rate per metre
iii 125 mm dia pipe
Weight of 1m length = (9.8+10.725)/2 = 10.262 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
Rate per metre
iv 150 mm dia pipe
Weight of 1m length = (12.15+15.18)/2 = 13.665 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
Rate per metre
v 200 mm dia pipe
Weight of 1m length = (19.1+25.3)/2 = 22.2 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
Rate per metre
vi 250 mm dia pipe
Weight of 1m length = (24.9+32)/2 = 28.450 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
Rate per metre
vii 300 mm dia pipe
Weight of 1m length = (32.2+44.925)/2 =38.562 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
Rate per metre
viii 350 mm dia pipe
Weight of 1m length = (13.6+54.875)/2 = 47.237 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
Rate per metre
ix 400 mm dia pipe
Weight of 1m length = (49.125+71.425)/2 =60.275 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
Rate per metre
x 450 mm dia pipe
Weight of 1m length = (59.225+84.025)/2 = 71.625 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
Rate per metre

893

Index-code

S No

Description

Unit

Quantity

kgs

88.725

kgs

125.262

kgs

7.378

kgs

11.587

kgs

15.087

kgs

21.275

kgs

36.425

kgs

46.412

kgs

66.075

kgs

76.412

kgs

104.225

kgs

125.360

Rate
Rs.
5

Amt
Rs.
6

PHE
Remarks
7

xi

500 mm dia pipe


Weight of 1m length = (73.2+104.25)/2 = 88.725 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
Rate per metre
xii 600 mm dia pipe
Weight of 1m length = (102.5+148.025)/2 = 125.262 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
Rate per metre
B

Class 20 & 25 pipes :

80 mm dia pipe
Weight of 1m length = (6.23+8.525)/2 = 7.378 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
Rate per metre
ii 100 mm dia pipe
Weight of 1m length = (10.35+12.825)/2 =11.587 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
Rate per metre
iii 125 mm dia pipe
Weight of 1m length = (13.35+16.825)/2 = 15.087 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
Rate per metre
iv 150 mm dia pipe
Weight of 1m length = (18.9+23.65)/2 = 21.275 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
Rate per metre
v 200 mm dia pipe
Weight of 1m length = (32.1+40.75)/2 = 36.425 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
Rate per metre
vi 250 mm dia pipe
Weight of 1m length = (41.175+51.65)/2 = 46.412 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
Rate per metre
vii 300 mm dia pipe
Weight of 1m length = (58.1+74.05)/2 = 66.075 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
Rate per metre
viii 350 mm dia pipe
Weight of 1m length = (71.275+81.55)/2 = 76.412 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
Rate per metre
ix 400 mm dia pipe
Weight of 1m length = (93.05+115.4)/2 = 104.225 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
Rate per metre
x 450 mm dia pipe
Weight of 1m length = (111.275+139.45)/2 = 125.36 kgs

(a) Labour charges for laying


(b) Overheads & Contractors Profit

Rate per metre

894

Index-code

S No

Description

Unit

Quantity

Rate
Rs.
5

Amt
Rs.
6

PHE
Remarks
7

xi

PHE-JACP-10

500 mm dia pipe


Weight of 1m length = (136.325+171.275)/2 = 153.8 kgs
kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
Rate per metre
xii 600 mm dia pipe
Weight of 1m length = (192.925+245.9)/2 = 219.412 kgs
kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
Rate per metre
10 Jointing A.C. pressure pipes with A.C. coupling or C.I.
detachable joints complete with rubber rings including filling with
water, with a water lead up to 500m and testing to required
pressure etc., complete but excluding cost of jointing materials
and conveyance of pipe from source of supply. Reference to
specifications BIS No.6530/72 (Labour Charges Only)

153.800

219.412

Detail of cost for 10 joints


Sub Analysis : For Machinery used for testing
OBSERVED DATA FOR TESTING OF 450 MM DIA PSC MAIN :
Pumping main to Hydralic field test pressure including
transportation of Water with minimum lead of 500 M

(Length = 500 Mts) taking out put / 500 Mts. Unit = 1 Rmt.
Machinery
Hire chargers for Hydralic field test pressure testing including days
transportation of water @ Rs. 1200/- (1000+200) / day

Materials
Pressure guage

Nos

0.05

3/4" G.I. Pipe

Mts

Specials

Ls

Dummies

No.

0.1

Diesel (2 Lts. / Hr) 30 Hrs.

Lts.

60

(T) Total Rate per 500 Mts.


(r) Rate per 1 Rmt for 450 mm dia
(R) Rate per 1 Rmt for 10 mm dia = (10/450) x r
i

80 mm dia meter pipe


(a) Labour
day
Plumber 1st class
day
Plumber 2nd class
day
Man mazdoor
Total
(b) Machinery for Testing of Pipelines with required rm
pressure as per relevant IS Specification including hire
charges of testing equipment, labour and transportation of
water upto 500 M lead Materials needed for testing (as per
Sub Analysis 11 A)
(c) Add for water charges @ 1% on Labour & Testing
Charges
(d) Total = a+b+c
(e) Overheads & Contractors Profit
(f) Cost for 10 joints = d+e
Rate per each joint = f/10

0.180
0.420
1.600
40.000

895

Index-code

S No
1
ii

iii

iv

Description

Unit

Quantity

Rate
Rs.
5

Amt
Rs.
6

PHE
Remarks
7

100 mm dia meter pipe


(a) Labour
st
day
Plumber 1 class
nd
day
Plumber 2 class
day
Man mazdoor
Total
(b) Machinery for Testing of Pipelines with required rm
pressure as per relevant IS Specification including hire
charges of testing equipment, labour and transportation of
water upto 500 M lead Materials needed for testing (as per
Sub Analysis 11 A)
(c) Add for water charges @ 1% on Labour & Testing
Charges
(d) Total = a+b+c
(e) Overheads & Contractors Profit
(f) Cost for 10 joints = d+e
Rate per each joint = f/10
125 mm dia meter pipe
(a) Labour
st
day
Plumber 1 class
nd
day
Plumber 2 class
day
Man mazdoor
Total
(b) Machinery for Testing of Pipelines with required rm
pressure as per relevant IS Specification including hire
charges of testing equipment, labour and transportation of
water upto 500 M lead Materials needed for testing (as per
Sub Analysis 11 A)
(c) Add for water charges @ 1% on Labour & Testing
Charges
(d) Total = a+b+c
(e) Overheads & Contractors Profit
(f) Cost for 10 joints = d+e
Rate per each joint = f/10
150 mm dia meter pipe
(a) Labour

day
Plumber 1st class
day
Plumber 2nd class
day
Man mazdoor
Total
(b) Machinery for Testing of Pipelines with required rm
pressure as per relevant IS Specification including hire
charges of testing equipment, labour and transportation of
water upto 500 M lead Materials needed for testing (as per
Sub Analysis 11 A)
(c) Add for water charges @ 1% on Labour & Testing
Charges
(d) Total = a+b+c
(e) Overheads & Contractors Profit
(f) Cost for 10 joints = d+e
Rate per each joint = f/10
200 mm dia meter pipe
(a) Labour
day
Plumber 1st class
nd
day
Plumber 2 class
day
Man mazdoor
Total
(b) Machinery for Testing of Pipelines with required rm
pressure as per relevant IS Specification including hire
charges of testing equipment, labour and transportation of
water upto 500 M lead Materials needed for testing (as per
Sub Analysis 11 A)

0.300
0.700
2.000
40.000

0.300
0.700
2.000
40.000

0.360
0.840
2.200
40.000

0.360
0.840
2.200
40.000

896

Index-code

S No
1

vi

Description

Unit

Quantity

Rate
Rs.
5

Amt
Rs.
6

PHE
Remarks
7

(c) Add for water charges @ 1% on Labour & Testing


Charges
(d) Total = a+b+c
(e) Overheads & Contractors Profit
(f) Cost for 10 joints = d+e
Rate per each joint = f/10
250 mm dia meter pipe
(a) Labour

st
day
Plumber 1 class
nd
day
Plumber 2 class
day
Man mazdoor
Total
(b) Machinery for Testing of Pipelines with required rm
pressure as per relevant IS Specification including hire
charges of testing equipment, labour and transportation of
water upto 500 M lead Materials needed for testing (as per
Sub Analysis 11 A)
(c) Add for water charges @ 1% on Labour & Testing
Charges
(d) Total = a+b+c
(e) Overheads & Contractors Profit
(f) Cost for 10 joints = d+e
Rate per each joint = f/10
vii 300 mm dia meter pipe
(a) Labour

day
Plumber 1st class
day
Plumber 2nd class
day
Man mazdoor
Total
(b) Machinery for Testing of Pipelines with required rm
pressure as per relevant IS Specification including hire
charges of testing equipment, labour and transportation of
water upto 500 M lead Materials needed for testing (as per
Sub Analysis 11 A)
(c) Add for water charges @ 1% on Labour & Testing
Charges
(d) Total = a+b+c
(e) Overheads & Contractors Profit
(f) Cost for 10 joints = d+e
Rate per each joint = f/10
viii 350 mm dia meter pipe
(a) Labour
day
Plumber 1st class
day
Plumber 2nd class
day
Man mazdoor
Total
(b) Machinery for Testing of Pipelines with required rm
pressure as per relevant IS Specification including hire
charges of testing equipment, labour and transportation of
water upto 500 M lead Materials needed for testing (as per
Sub Analysis 11 A)
(c) Add for water charges @ 1% on Labour & Testing
Charges
(d) Total = a+b+c
(e) Overheads & Contractors Profit
(f) Cost for 10 joints = d+e
Rate per each joint = f/10

0.480
1.120
2.600
40.000

0.480
1.120
2.600
40.000

0.600
1.400
3.000
40.000

897

Index-code

S No
1
ix

xi

Description

Unit

Quantity

Rate
Rs.
5

Amt
Rs.
6

PHE
Remarks
7

400 mm dia meter pipe


(a) Labour
st
day
Plumber 1 class
nd
day
Plumber 2 class
day
Man mazdoor
Total
(b) Machinery for Testing of Pipelines with required rm
pressure as per relevant IS Specification including hire
charges of testing equipment and transportation of water
upto 500 M lead Materials needed for testing (as per Sub
Analysis 11 A)
(c) Add for water charges @ 1% on Labour & Testing
Charges
(d) Total = a+b+c
(e) Overheads & Contractors Profit
(f) Cost for 10 joints = d+e
Rate per each joint = f/10
450 mm dia meter pipe
(a) Labour
st
day
Plumber 1 class
day
Plumber 2nd class
day
Man mazdoor
Total
(b) Machinery for Testing of Pipelines with required rm
pressure as per relevant IS Specification including hire
charges of testing equipment and transportation of water
upto 500 M lead Materials needed for testing (as per Sub
Analysis 11 A)
(c) Add for water charges @ 1% on Labour & Testing
Charges
(d) Total = a+b+c
(e) Overheads & Contractors Profit
(f) Cost for 10 joints = d+e
Rate per each joint = f/10
500 mm dia meter pipe
(a) Labour

day
Plumber 1st class
nd
day
Plumber 2 class
day
Man mazdoor
Total
(b) Machinery for Testing of Pipelines with required rm
pressure as per relevant IS Specification including hire
charges of testing equipment and transportation of water
upto 500 M lead Materials needed for testing (as per Sub
Analysis 11 A)
(c) Add for water charges @ 1% on Labour & Testing
Charges
(d) Total = a+b+c
(e) Overheads & Contractors Profit
(f) Cost for 10 joints = d+e
Rate per each joint = f/10
xii 600 mm dia meter pipe
(a) Labour
day
Plumber 1st class
nd
day
Plumber 2 class
day
Man mazdoor
Total
(b) Machinery for Testing of Pipelines with required rm
pressure as per relevant IS Specification including hire
charges of testing equipment and transportation of water
upto 500 M lead Materials needed for testing (as per Sub
Analysis 11 A)

0.600
1.400
3.000
40.000

0.720
1.680
3.400
40.000

0.720
1.680
3.400
40.000

0.840
1.960
3.800
40.000

898

Index-code

S No
1

Description

Unit

Quantity

Rate
Rs.
5

Amt
Rs.
6

PHE
Remarks
7

(c) Add for water charges @ 1% on Labour & Testing


Charges
(d) Total = a+b+c
(e) Overheads & Contractors Profit
(f) Cost for 10 joints = d+e
Rate per each joint = f/10
11

PHE-LJUP-11

Lowering, laying, jointing and testing to hydralic test pressure


including cost of water with minimum water lead of 500m for
UPVC pressure pipes in ready made trenches true to alignment
and gradient including all sundries but excluding cost &
conveyance of pipes from source of supply and jointing
materials as per BIS No. 7634 - Part III - 1975
Sub Analysis for 160 mm Dia :
Taking output : Length - 500 m ; Joints - 83 Nos
(a) Labour
For lowering / sub surface transport
day
Mazdoor
Jointing
day
Fitter
day
Mazdoor
Testing
Testing of Pipelines with required pressure as per relevant IS rm
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment and labour,
Materials needed for testing (as per Sub Analysis 2 A)
Total
(b) Material
Add for Water charges at 1% on Labour & Testing
(c) Overheads & Contractors Profit
(d) Total (a+b+c)
Rate per RM =d/500
Rate per 10 mm / 1rm

All Classes pipes :

63 mm dia pipe
Weight of 1m length = (0.468+0.666+1.01)/3 =0.715 kgs
(a) Labour charges for laying, jointing & testing
(b) Overheads & Contractors Profit
Rate per metre a+b
75 mm dia pipe
Weight of 1m length = (0.655+0.923+1.439)/3 =1.005 kgs
(a) Labour charges for laying, jointing & testing
(b) Overheads & Contractors Profit
Rate per metre a+b
90 mm dia pipe
Weight of 1m length = (0.924+1.321+2.032)/3 =1.426 kgs
(a) Labour charges for laying, jointing & testing
(b) Overheads & Contractors Profit
Rate per metre a+b
110 mm dia pipe
Weight of 1m length = (1.323+1.902+3.062)/3 =2.096 kgs
(a) Labour charges for laying, jointing & testing
(b) Overheads & Contractors Profit
Rate per metre a+b
125 mm dia pipe
Weight of 1m length = (1.722+2.511+3.929)/3 =2.72 kgs
(a) Labour charges for laying, jointing & testing
(b) Overheads & Contractors Profit
Rate per metre a+b

ii

iii

iv

7.000
2.000
4.000
500.000

Lt

rm

6.300

rm

7.500

rm

9.000

rm

11.000

rm

12.500

899

Index-code

S No
1

Description

Unit

Quantity

rm

14.000

rm

16.000

rm

18.000

rm

20.000

rm

22.500

rm

25.000

rm

28.000

rm

31.500

day

4.000

day
day

1.000
2.000

day
day
day

1.000
2.000
1.000

Rate
Rs.
5

Amt
Rs.
6

PHE
Remarks
7

vi

140 mm dia pipe


Weight of 1m length = (2.144+3.116+4.905)/3 =3.388 kgs
(a) Labour charges for laying, jointing & testing
(b) Overheads & Contractors Profit
Rate per metre a+b
vii 160 mm dia pipe
Weight of 1m length = (2.799+4.012+6.414)/3 =4.408 kgs
(a) Labour charges for laying, jointing & testing
(b) Overheads & Contractors Profit
Rate per metre a+b
viii 180 mm dia pipe
Weight of 1m length = (3.581+5.134+8.092)/3 =5.602 kgs
(a) Labour charges for laying, jointing & testing
(b) Overheads & Contractors Profit
Rate per metre a+b
ix 200 mm dia pipe
Weight of 1m length = (4.331+6.351+10.001)/3 =6.894 kgs
(a) Labour charges for laying, jointing & testing
(b) Overheads & Contractors Profit
Rate per metre a+b
x 225 mm dia pipe
Weight of 1m length = (5.511+7.975+12.675)/3 =8.72 kgs
(a) Labour charges for laying, jointing & testing
(b) Overheads & Contractors Profit
Rate per metre a+b
xi 250 mm dia pipe
Weight of 1m length = (6.674+9.886+15.666)/3 =10.742 kgs
(a) Labour charges for laying, jointing & testing
(b) Overheads & Contractors Profit
Rate per metre a+b
xii 280 mm dia pipe
Weight of 1m length = (8.453+12.404+19.616)/3 =13.491 kgs
(a) Labour charges for laying, jointing & testing
(b) Overheads & Contractors Profit
Rate per metre a+b
xiii 315 mm dia pipe
Weight of 1m length = (10.682+15.723+24.732)/3 =17.046 kgs
(a) Labour charges for laying, jointing & testing
(b) Overheads & Contractors Profit
Rate per metre a+b
12

PHE-LJHE-12

Laying and jointing of HDPE pipes by butt fusion welding as per


IS:7634 part-II/1975 as amended from time to time to the
alignment and gradient and testing the pipeline to the required
pressure.
Note : Specialized labour is needed for execution of laying &
jointing for HDPE Pipes with buttfusion welding technique as per
IS Specification.
63 mm Dia
Taking output : Length - 480 m ; Joints - 40 Nos
(a) Labour
For lowering / sub surface transport
Mazdoor
Jointing
Fitter
Mazdoor
Testing
Fitter
Mazdoor
Supervisor
Total

900

Index-code

S No
1

Description

Unit

Quantity

day

1.000

Lt
Lt
Lt
day

4.000
8.000

day

4.000

day
day

1.000
2.000

day
day
day

1.000
2.000
1.000

day

1.000

Lt
Lt
Lt
day

4.000
8.000

day

5.000

day
day

1.000
2.000

day
day
day

1.000
2.000
1.000

day

1.000

Lt
Lt
Lt
day

5.000
8.000

day

6.000

day
day

1.000
2.000

Rate
Rs.
5

Amt
Rs.
6

PHE
Remarks
7

(b) Machinery
Hirecharges of Generator Set & Hydraulic Testing Equipment

(c) Material
Kerosene
Diesel
Water for Testing
Transport
Overheads & Contractors Profit
(d) Total (a+b+c)
Rate per RM =d/480
ii

1.000

75 mm Dia
Taking output : Length - 456 m ; Joints - 38 Nos
(a) Labour
For lowering / sub surface transport
Mazdoor
Jointing
Fitter
Mazdoor
Testing
Fitter
Mazdoor
Supervisor
Total
(b) Machinery
Hire charges of Generator Set & Hydraulic testing equipment

(c) Material
Kerosene
Diesel
Water for Testing
Transport
Overheads & Contractors Profit
(d) Total (a+b+c)
Rate per RM =d/456
iii

90 mm Dia
Taking output : Length - 432 m ; Joints - 36 Nos
(a) Labour
For lowering / sub surface transport
Mazdoor
Jointing
Fitter
Mazdoor
Testing
Fitter
Mazdoor
Supervisor
Total
(b) Machinery
Hire charges of Generator Set & Hydraulic testing equipment

(c) Material
Kerosene
Diesel
Water for Testing
Transport
Overheads & Contractors Profit
(d) Total (a+b+c)
Rate per RM =d/432
iv

1.000

1.000

110 mm Dia
Taking output : Length - 384 m ; Joints - 32 Nos
(a) Labour
For lowering / sub surface transport
Mazdoor
Jointing
Fitter
Mazdoor

901

Index-code

S No
1

Description

Unit

Quantity

day
day
day

1.000
2.000
1.000

day

1.000

Lt
Lt
Lt
day

6.000
8.000

day

7.000

day
day

2.000
3.000

day
day
day

1.000
2.000
1.000

day

1.000

Lt
Lt
Lt
day

7.000
8.000

day

7.000

day
day

2.000
3.000

day
day
day

1.000
2.000
1.000

day

1.000

Lt
Lt
Lt
day

8.000
8.000

Testing
Fitter
Mazdoor
Supervisor
Total
(b) Machinery
Hirecharges of Generator Set & Hydraulic Testing Equipment

(c) Material
Kerosene
Diesel
Water for Testing
Transport
Overheads & Contractors Profit
(d) Total (a+b+c)
Rate per RM =d/384
v

Rate
Rs.
5

Amt
Rs.
6

PHE
Remarks
7

1.000

125 mm Dia
Taking output : Length - 348 m ; Joints - 29 Nos
(a) Labour
For lowering / sub surface transport
Mazdoor
Jointing
Fitter
Mazdoor
Testing
Fitter
Mazdoor
Supervisor
Total
(b) Machinery
Hire charges of Generator Set & Hydraulic testing equipment

(c) Material
Kerosene
Diesel
Water for Testing
Transport
Overheads & Contractors Profit
(d) Total (a+b+c)
Rate per RM =d/348
vi

1.000

140 mm Dia
Taking output : Length - 300 m ; Joints - 25 Nos
(a) Labour
For lowering / sub surface transport
Mazdoor
Jointing
Fitter
Mazdoor
Testing
Fitter
Mazdoor
Supervisor
Total
(b) Machinery
Hire charges of Generator Set & Hydraulic testing equipment

(c) Material
Kerosene
Diesel
Water for Testing
Transport
Overheads & Contractors Profit
(d) Total (a+b+c)
Rate per RM =d/300

1.000

902

Index-code

S No
1
vii

Description

Unit

Quantity

day

7.000

day
day

2.000
4.000

day
day
day

1.000
2.000
1.000

day

1.000

Lt
Lt
Lt
day

9.000
8.000

day

8.000

day
day

2.000
4.000

day
day
day

1.000
2.000
1.000

day

1.000

Lt
Lt
Lt
day

10.000
8.000

day

10.000

day
day

2.000
6.000

day
day
day

1.000
2.000
1.000

day

1.000

Lt
Lt
Lt
day

11.000
8.000

160 mm Dia
Taking output : Length - 303 m ; Joints - 25 Nos
(a) Labour
For lowering / sub surface transport
Mazdoor
Jointing
Fitter
Mazdoor
Testing
Fitter
Mazdoor
Supervisor
Total
(b) Machinery
Hire charges of Generator Set & Hydraulic testing equipment

(c) Material
Kerosene
Diesel
Water for Testing
Transport
Overheads & Contractors Profit
(d) Total (a+b+c)
Rate per RM =d/303
viii 180 mm Dia
Taking output : Length - 240 m ; Joints - 20 Nos
(a) Labour
For lowering / sub surface transport
Mazdoor
Jointing
Fitter
Mazdoor
Testing
Fitter
Mazdoor
Supervisor
Total Labour
(b) Machinery
Hire charges of Generator Set & Hydraulic testing equipment

ix

(c) Material
Kerosene
Diesel
Water for Testing
Transport
Overheads & Contractors Profit
(d) Total (a+b+c)
Rate per RM =d/240
200 mm Dia
Taking output : Length - 240 m ; Joints - 20 Nos
(a) Labour
For lowering / sub surface transport
Mazdoor
Jointing
Fitter
Mazdoor
Testing
Fitter
Mazdoor
Supervisor
Total
(b) Machinery
Hire charges of Generator Set & Hydraulic testing equipment

(c) Material
Kerosene
Diesel
Water for Testing
Transport
Overheads & Contractors Profit
(d) Total (a+b+c)
Rate per RM =d/240
225 mm Dia
Taking output : Length - 216 m ; Joints -18 Nos
(a) Labour
For lowering / sub surface transport

Rate
Rs.
5

Amt
Rs.
6

PHE
Remarks
7

1.000

1.000

1.000

903

Index-code

S No
1

Description

Unit

Quantity

3
day

4
10.000

day
day

2.000
6.000

day
day
day

1.000
2.000
1.000

day

1.000

Lt
Lt
Lt
day

12.000
8.000

day

11.000

day
day

2.000
6.000

day
day
day

1.000
2.000
1.000

day

1.000

Lt
Lt
Lt
day

13.000
8.000

day

12.000

day
day

2.000
6.000

day
day
day

1.000
2.000
1.000

day

1.000

Lt
Lt
Lt
day

14.000
8.000

day

12.000

day
day

2.000
6.000

Mazdoor
Jointing
Fitter
Mazdoor
Testing
Fitter
Mazdoor
Supervisor
Total
(b) Machinery
Hire charges of Generator Set & Hydraulic testing equipment

xi

(c) Material
Kerosene
Diesel
Water for Testing
Transport
Overheads & Contractors Profit
(d) Total (a+b+c)
Rate per RM =d/216
250 mm Dia
Taking output : Length - 216 m ; Joints - 18 Nos
(a) Labour
For lowering / sub surface transport
Mazdoor
Jointing
Fitter
Mazdoor
Testing
Fitter
Mazdoor
Supervisor
Total
(b) Machinery
Hire charges of Generator Set & Hydraulic testing equipment

(c) Material
Kerosene
Diesel
Water for Testing
Transport
Overheads & Contractors Profit
(d) Total (a+b+c)
Rate per RM =d/216
xii 280 mm Dia
Taking output : Length - 192 m ; Joints - 16 Nos
(a) Labour
For lowering / sub surface transport
Mazdoor
Jointing
Fitter
Mazdoor
Testing
Fitter
Mazdoor
Supervisor
Total
(b) Machinery
Hire charges of Generator Set & Hydraulic testing equipment

(c) Material
Kerosene
Diesel
Water for Testing
Transport
Overheads & Contractors Profit
(d) Total (a+b+c)
Rate per RM =d/192
xiii 315 mm Dia
Taking output : Length - 180 m ; Joints - 15 Nos
(a) Labour
For lowering / sub surface transport
Mazdoor
Jointing
Fitter
Mazdoor

Rate
Rs.
5

Amt
Rs.
6

PHE
Remarks
7

1.000

1.000

1.000

904

Index-code

S No
1

Description

Unit

Quantity

day
day
day

1.000
2.000
1.000

day

1.000

Lt
Lt
Lt
day

15.000
8.000

day

14.000

day
day

2.000
8.000

day
day
day

1.000
2.000
1.000

day

1.000

Lt
Lt
Lt
day

16.000
8.000

day

0.600

day

1.400

day

3.000

day

1.000

each/r
m
t/kg

50.000

cum

0.045

kgs

4.500

Testing
Fitter
Mazdoor
Supervisor
Total
(b) Machinery
Hire charges of Generator Set & Hydraulic testing equipment

(c) Material
Kerosene
Diesel
Water for Testing
Transport
Overheads & Contractors Profit
(d) Total (a+b+c)
Rate per RM =d/180
xiv 355 mm Dia
Taking output : Length - 144 m ; Joints - 12 Nos
(a) Labour
For lowering / sub surface transport
Mazdoor
Jointing
Fitter
Mazdoor
Testing
Fitter
Mazdoor
Supervisor
Total
(b) Machinery
Hire charges of Generator Set & Hydraulic testing equipment

(c) Material
Kerosene
Diesel
Water for Testing
Transport
Overheads & Contractors Profit
(d) Total (a+b+c)
Rate per RM =d/144
13

PHE-LJSW-13

Rate
Rs.
5

Amt
Rs.
6

PHE
Remarks
7

1.000

1.000

Lowering and laying in ready made trench true to alignment and gradient,
jointing, and testing of stone ware pipes including cost of jointing material
such as cement mortar (1:1) proportion and hemp yarn but excluding
cost and conveyance of pipe. (Reference to specifications BIS No.
6530/72)

Detail cost for 30 meters


100 mm dia
(a) Labour
Mason 1st class
nd
Mason 2 class
Man mazdoor
Woman mazdoor (Water carrier)
b) Material
100 mm dia SW pipe 60cm long
Cement for 50 joints =0.045 cum
Sand = 0.045 cum
Spun yarn = 0.09x50=4.50
(c) Total = a+b

0.065

905

Index-code

S No
1

ii

Description

Unit

Quantity

day

0.900

day

2.100

day

4.000

day

1.000

each
t

50.000
0.097

cum

0.068

kgs

9.000

day

1.050

day

2.450

day

4.500

day

1.250

each
t

50.000
0.130

iv

Amt
Rs.
6

PHE
Remarks
7

(d) Add for water charges @ 1% on Labour & Testing


Charges
(e) Total = c+d
(f) Overheads & Contractors Profit
(g) Cost for 30 m (e+f)
Rate per metre = g/30
150 mm dia
(a) Labour
st

iii

Rate
Rs.
5

Mason 1 class
Mason 2nd class
Man mazdoor
Woman mazdoor (Water carrier)
b) Material
150 mm dia SW pipe 60cm long
Cement for 50 joints =0.045 cum
Sand = 0.045 cum
Spun yarn = 0.09x50=4.50
(c) Total = a+b
(d) Add for water charges @ 1% on Labour & Testing
Charges
(e) Total = c+d
(f) Overheads & Contractors Profit
(g) Cost for 30 m (e+f)
Rate per metre = g/30
200 mm dia
(a) Labour
Mason 1st class
Mason 2nd class
Man mazdoor
Woman mazdoor (Water carrier)
b) Material
200 mm dia SW pipe 60cm long
Cement for 50 joints =0.045 cum
Sand = 0.045 cum
Spun yarn = 0.09x50=4.50
(c) Total = a+b
(d) Add for water charges @ 1% on Labour & Testing
Charges
(e) Total = c+d
(f) Overheads & Contractors Profit
(g) Cost for 30 m (e+f)
Rate per metre = g/30
230 mm dia
(a) Labour
Mason 1st class
Mason 2nd class
Man mazdoor
Woman mazdoor (Water carrier)
b) Material
230 mm dia SW pipe 60cm long
Cement for 50 joints =0.045 cum
Sand = 0.045 cum
Spun yarn = 0.09x50=4.50
(c) Total = a+b
(d) Add for water charges @ 1% on Labour & Testing
Charges
(e) Total = c+d
(f) Overheads & Contractors Profit
(g) Cost for 30 m (e+f)
Rate per metre = g/30

cum

0.091

kgs

12.000

day

1.200

day

2.800

day

5.000

day

1.500

each
t

50.000
0.146

cum

0.102

kgs

13.500

906

Index-code

S No

Description

Unit

Quantity

Mason 1 class
nd
Mason 2 class
Man mazdoor
Woman mazdoor (Water carrier)
b) Material
250 mm dia SW pipe 60cm long
Cement for 50 joints =0.045 cum
Sand = 0.045 cum
Spun yarn = 0.09x50=4.50
(c) Total = a+b
(d) Add for water charges @ 1% on Labour & Testing
Charges
(e) Total = c+d
(f) Overheads & Contractors Profit
(g) Cost for 30 m (e+f)
Rate per metre = g/30
300 mm dia
(a) Labour

day

1.350

day

3.150

day

5.500

day

1.500

each
t

50.000
0.162

1
v

Amt
Rs.
6

PHE
Remarks
7

250 mm dia
(a) Labour
st

vi

Rate
Rs.
5

st

Mason 1 class
nd
Mason 2 class
Man mazdoor
Woman mazdoor (Water carrier)
b) Material
300 mm dia SW pipe 60cm long
Cement for 50 joints =0.045 cum
Sand = 0.045 cum
Spun yarn = 0.09x50=4.50
(c) Total = a+b
(d) Add for water charges @ 1% on Labour & Testing
Charges
(e) Total = c+d
(f) Overheads & Contractors Profit
(g) Cost for 30 m (e+f)
Rate per metre = g/30
vii 350 mm dia
(a) Labour
Mason 1st class
Mason 2nd class
Man mazdoor
Woman mazdoor (Water carrier)
b) Material
350 mm dia SW pipe 60cm long
Cement for 50 joints =0.045 cum
Sand = 0.045 cum
Spun yarn = 0.09x50=4.50
(c) Total = a+b
(d) Add for water charges @ 1% on Labour & Testing
Charges
(e) Total = c+d
(f) Overheads & Contractors Profit
(g) Cost for 30 m (e+f)
Rate per metre = g/30

cum

0.113

kgs

15.000

day

1.500

day

3.500

day

6.000

day

1.500

each
t

50.000
0.194

cum

0.136

kgs

18.000

day

1.650

day

3.850

day

7.000

day

1.750

each
t

50.000
0.225

cum

0.159

kgs

21.000

907

Index-code

S No

Description

Unit

Quantity

Mason 1 class
nd
Mason 2 class
Man mazdoor
Woman mazdoor (Water carrier)
b) Material
400 mm dia SW pipe 60cm long
Cement for 50 joints =0.045 cum
Sand = 0.045 cum
Spun yarn = 0.09x50=4.50
(c) Total = a+b
(d) Add for water charges @ 1% on Labour & Testing
Charges
(e) Total = c+d
(f) Overheads & Contractors Profit
(g) Cost for 30 m (e+f)
Rate per metre = g/30
450 mm dia
(a) Labour

day

1.800

day

4.200

day

8.000

day

1.750

each
t

50.000
0.256

Rate
Rs.
5

Amt
Rs.
6

PHE
Remarks
7

viii 400 mm dia

(a) Labour
st

ix

st

Mason 1 class
Mason 2nd class
Man mazdoor
Woman mazdoor (Water carrier)
b) Material
450 mm dia SW pipe 60cm long
Cement for 50 joints =0.045 cum
Sand = 0.045 cum
Spun yarn = 0.09x50=4.50
(c) Total = a+b
(d) Add for water charges @ 1% on Labour & Testing
Charges
(e) Total = c+d
(f) Overheads & Contractors Profit
(g) Cost for 30 m (e+f)
Rate per metre = g/30

PHE-CISP14(sub_analys
is)

14

15

24.000

day
day
day
day

2.100
4.900
10.000
2.000

each
t

50.000
0.293

cum

0.204

kgs

27.000

day
day

0.465
1.094

day

2.480

kgs

35.470

Lowering, keeping in position and fixing C.I. sluice valves (with cap / with
hand wheel & reflex valves) excluding cost of bolts, nuts, rubber
insertion, sluice valve and tail pieces

Details of cost for 1No


80 mm dia meter
(a) Labour
Labour for laying Sluice Valve with cap, with hand wheel & reflex valves Weight (32.3+34.1+40)/3=35.47

ii

0.181

kgs

Sub Analysis :
Labour charges for laying in position S&S or flanged C.I.
specials such as tees, bends, collars tapers and caps etc
10 No. Tees of 200x150mm dia
Weight = 10x70kgs = 700 kgs
(a) Labour
Plumber 1st class
Plumber 2nd class
Man mazdoor
Cost for 700 kgs
Cost for 1kg

PHE-CISV-15

cum

Overheads & Contractors Profit


Rate per 1 Sluice valve
100 mm dia meter
(a) Labour
Labour for laying Sluice Valve with cap, with hand wheel & reflex kgs
valves - Weight (44.3+47+50)/3=47.1
(g) Overheads & Contractors Profit
Rate per 1 Sluice valve

47.100

908

Index-code

S No
1

Description

Unit

Quantity

kgs

61.770

kgs

79.830

kgs

131.700

kgs

187.160

kgs

266.460

kgs

450.000

kgs

552.500

kgs

722.500

kgs

837.500

kgs

1422.500

Rate
Rs.
5

Amt
Rs.
6

PHE
Remarks
7

iii

125 mm dia meter


(a) Labour
Labour for laying Sluice Valve with cap, with hand wheel & reflex
valves - Weight (56.3+59+70)/3=61.77
(g) Overheads & Contractors Profit
Rate per 1 Sluice valve
iv 150 mm dia meter
(a) Labour
Labour for laying Sluice Valve with cap, with hand wheel & reflex
valves - (72.5+77+90)/3=79.83
(g) Overheads & Contractors Profit
Rate per 1 Sluice valve
v 200 mm dia meter
(a) Labour
Labour for laying Sluice Valve with cap, with hand wheel & reflex
valves - (121.5+128.6+145)/3=131.7
(g) Overheads & Contractors Profit
Rate per 1 Sluice valve
vi 250 mm dia meter
Labour for laying Sluice Valve with cap, with hand wheel & reflex
valves - (179.9+186.6+195)/3=187.16
(g) Overheads & Contractors Profit
Rate per 1 Sluice valve
vii 300 mm dia meter
(a) Labour
Labour for laying Sluice Valve with cap, with hand wheel & reflex
valves - (242.4+257+300)/3=266.46
(g) Overheads & Contractors Profit
Rate per 1 Sluice valve
viii 350 mm dia meter
(a) Labour
Labour for laying Sluice Valve with cap, with hand wheel & reflex
valves - (430+470)/2=450
Overheads & Contractors Profit
Rate per each
ix 400 mm dia meter
(a) Labour
Labour for laying Sluice Valve with cap, with hand wheel & reflex
valves - (525+580)/2=552.5
Overheads & Contractors Profit
Rate per each
x 450 mm dia meter
(a) Labour
Labour for laying Sluice Valve with cap, with hand wheel & reflex
valves - (635+810)/2=722.5
Overheads & Contractors Profit
Rate per each
xi 500 mm dia meter
(a) Labour
Labour for laying Sluice Valve with cap, with hand wheel & reflex
valves - (775+900)/2=837.5
Overheads & Contractors Profit
Rate per each
xii 600 mm dia meter
(a) Labour
Labour for laying Sluice Valve with cap, with hand wheel & reflex
valves - (1220+1625)/2=1422.5
Overheads & Contractors Profit
Rate per each

909

Index-code

S No

Description

Unit

Quantity

16
A

Providing and fixing double acting air valves including boring the
main threading the bore and fixing nipple etc.,excluding the cost
of rubber insertions, bolts & nuts, air valve & flanged tail pieces
complete

kgs

20.000

day

0.180

PHE-DAAV-16

Rate
Rs.
5

Amt
Rs.
6

PHE
Remarks
7

Details of cost for each


i

50 mm dia meter
(a) Labour
Labour for laying air valve
nd

Plumber 2 class
day
Man mazdoor
Overheads & Contractors Profit
Rate per each valve
16 Labour charges for fixing Air valves including boring the mains
B and threading the bore fixing nipple etc., complete.
i

Unit each
40 mm dia
(a) Labour
Lowering charges for air valve
Boring main & threding etc

0.180

kgs

27.000

day

0.140

day

0.140

kgs

20.000

day

0.110

day

0.110

day
Plumber 1st class
nd
day
Plumber 2 class
day
Man mazdoor
Overheads & Contractors Profit
Rate per each fire hydrant
Note : For other sizes proportionately allow the Data.
18 Dismantling of spindle fire hydrant including stacking of useful
materials within 50m lead
Details of cost for 10 Nos
65 mm dia
(a) Labour
Fitter 1st class
day
day
Fitter 2nd class
day
Man mazdoor
Overheads & Contractors Profit
Rate per each

0.750

nd

Plumber 2 class
Man mazdoor
Overheads & Contractors Profit
Rate per each valve
ii

25 mm dia
(a) Labour
Lowering charges for air valve
Boring main & threding etc
Plumber 2nd class
Man mazdoor
Overheads & Contractors Profit
Rate per each valve

17

PHE-SFHD-17

Providing and fixing spindle fire hydrant with 65 mm outlet.


Complete with bolts, nuts, and rubber insertion etc. complete but
excluding cost of Materials.
Details of cost for 1fire hydrants

PHE-DSFH-18

65 mm dia
(a) Labour
1.750
4.000

0.750
1.750
4.000

910

Index-code

S No
1
19

PHE-URCI-19
i

ii

iii

iv

Description

Unit

Quantity

2
Uprooting of C.I. pipes by melting lead, loosening the joints, separating
the pipes, hoisting and keeping within a lead of 10 metres but excluding
earth work excavation and refilling

day

0.500

day

4.000

q
litre

0.373
0.379

day

0.630

day

4.500

Details of cost for 40.26 m


80mm dia metre
(a) Labour
nd
Assistant fitter(plumber 2 class)
Man mazdoor
b) Material
For breacking lead coulked joints, melting lead etc.,
Fuel wood
Kerosene oil
(c) Total = a+b
(d) Overheads & Contractors Profit
(e) Cost for 40.26 m (c+d)
Rate per each m = e/40.26
100mm dia metre
(a) Labour
Assistant fitter(plumber 2nd class)
Man mazdoor
b) Material
For breacking lead coulked joints, melting lead etc.,
Fuel wood
Kerosene oil
(c) Total = a+b
(d) Overheads & Contractors Profit
(e) Cost for 40.26 m (c+d)
Rate per each m = e/40.26
125mm dia metre
(a) Labour
nd
Assistant fitter(plumber 2 class)
Man mazdoor
b) Material
For breacking lead coulked joints, melting lead etc.,
Fuel wood
Kerosene oil
(c) Total = a+b
(d) Overheads & Contractors Profit
(e) Cost for 40.26 m (c+d)
Rate per each m = e/40.26
150mm dia metre
(a) Labour
Assistant fitter(plumber 2nd class)
Man mazdoor
b) Material
For breacking lead coulked joints, melting lead etc.,
Fuel wood
Kerosene oil
(c) Total = a+b
(d) Overheads & Contractors Profit
(e) Cost for 40.26 m (c+d)
Rate per each m = e/40.26
200mm dia metre
(a) Labour
Assistant fitter(plumber 2nd class)
Man mazdoor
b) Material
For breacking lead coulked joints, melting lead etc.,
Fuel wood
Kerosene oil
(c) Total = a+b
(d) Overheads & Contractors Profit
(e) Cost for 40.26 m (c+d)
Rate per each m = e/40.26

0.466

litre

0.379

day

0.760

day

5.000

0.559

litre

0.562

day

0.830

day

5.500

0.663

litre

0.568

day

1.100

day

6.500

0.840

litre

0.757

Rate
Rs.
5

Amt
Rs.
6

PHE
Remarks
7

911

Index-code

S No
1
vi

Description

Unit

Quantity

day

1.300

day

7.500

nd

nd

Assistant fitter(plumber 2 class)


Man mazdoor
b) Material
For breacking lead coulked joints, melting lead etc.,
Fuel wood
Kerosene oil
(c) Total = a+b
(d) Overheads & Contractors Profit
(e) Cost for 40.26 m (c+d)
Rate per each m = e/40.26
viii 350mm dia metre
(a) Labour

Amt
Rs.
6

PHE
Remarks
7

250mm dia metre


(a) Labour

Assistant fitter(plumber 2 class)


Man mazdoor
b) Material
For breacking lead coulked joints, melting lead etc.,
Fuel wood
Kerosene oil
(c) Total = a+b
(d) Overheads & Contractors Profit
(e) Cost for 40.26 m (c+d)
Rate per each m = e/40.26
vii 300mm dia metre
(a) Labour

ix

Rate
Rs.
5

Assistant fitter(plumber 2nd class)


Man mazdoor
b) Material
For breacking lead coulked joints, melting lead etc.,
Fuel wood
Kerosene oil
(c) Total = a+b
(d) Overheads & Contractors Profit
(e) Cost for 40.26 m (c+d)
Rate per each m = e/40.26
400mm dia metre
(a) Labour
Assistant fitter(plumber 2nd class)
Man mazdoor
b) Material
For breacking lead coulked joints, melting lead etc.,
Fuel wood
Kerosene oil
(c) Total = a+b
(d) Overheads & Contractors Profit
(e) Cost for 40.26 m (c+d)
Rate per each m = e/40.26
450mm dia metre
(a) Labour
Assistant fitter(plumber 2nd class)
Man mazdoor
b) Material
For breacking lead coulked joints, melting lead etc.,
Fuel wood
Kerosene oil
(c) Total = a+b
(d) Overheads & Contractors Profit
(e) Cost for 40.26 m (c+d)
Rate per each m = e/40.26

1.026

litre

1.137

day

1.500

day

8.500

1.120

litre

1.515

day

1.750

day

9.500

1.231

litre

1.515

day

2.000

day

10.500

1.306

litre

1.894

day

2.250

day

11.500

1.400

litre

2.273

912

Index-code

S No
1
xi

Description

Unit

Quantity

nd

PHE-URRC-20

iii

iv

day

2.500

day

12.500

1.492

litre

2.652

day

3.000

day

14.500

1.580

litre

3.410

Remarks
7

Fitter 2 class
Man mazdoor
Women mazdoor
(b) Overheads & Contractors Profit
(c) Cost for 10 Rmt (a+b)
Rate per each Rmt = c/10
150mm dia
(a) Labour

day

0.100

day

0.400

day

0.450

Fitter 2nd class


Man mazdoor
Women mazdoor
(b) Overheads & Contractors Profit
(c) Cost for 10 Rmt (a+b)
Rate per each Rmt = c/10
225mm dia
(a) Labour

day

0.100

day

0.490

day

0.560

Fitter 2nd class


Man mazdoor
Women mazdoor
(b) Overheads & Contractors Profit
(c) Cost for 10 Rmt (a+b)
Rate per each Rmt = c/10
300mm dia
(a) Labour

day

0.100

day

0.490

day

0.670

Fitter 2nd class


Man mazdoor
Women mazdoor
(b) Overheads & Contractors Profit
(c) Cost for 10 Rmt (a+b)
Rate per each Rmt = c/10

day

0.100

day

0.490

day

0.790

Uprooting of R.C.C. Pipes including breaking the collars, loosing


the joint, scraping the pipe, hoisting and keeping within a lead of
10 M but excluding earthwork excavation and refilling
Taking output 10.00 Rmt
100mm dia
(a) Labour
nd

ii

PHE

600mm dia metre


(a) Labour
Assistant fitter(plumber 2nd class)
Man mazdoor
b) Material
For breacking lead coulked joints, melting lead etc.,
Fuel wood
Kerosene oil
(c) Total = a+b
(d) Overheads & Contractors Profit
(e) Cost for 40.26 m (c+d)
Rate per each m = e/40.26

20

Amt
Rs.
6

500mm dia metre


(a) Labour
Assistant fitter(plumber 2 class)
Man mazdoor
b) Material
For breacking lead coulked joints, melting lead etc.,
Fuel wood
Kerosene oil
(c) Total = a+b
(d) Overheads & Contractors Profit
(e) Cost for 40.26 m (c+d)
Rate per each m = e/40.26

xii

Rate
Rs.
5

913

Index-code

S No

Description

Unit

Quantity

21

Uprooting of old S.W. pipes including breaking of joints and bed


concrete stacking of useful materials near the site with in 50m
lead and disposal of un serviceable materials in to municipal
dumps excluding the cost of earth work excavation. (Reference
to specifications BIS No.)

day

0.490

day

0.360

day

0.490

day

0.450

day

0.490

day

0.510

day

0.490

day

0.540

day

0.490

day

0.570

day

0.490

day

0.630

day
day

0.490
0.690

PHE-URSW-21

Details of cost for 10 m


100mm dia metre
(a) Labour
Man mazdoor
Women mazdoor
(b) Overheads & Contractors Profit
(c) Cost for 10 m (a+b)
Rate per each m =c/10
ii 150mm dia metre
(a) Labour
Man mazdoor
Women mazdoor
(b) Overheads & Contractors Profit
(c) Cost for 10 m (a+b)
Rate per each m =c/10
iii 200mm dia metre
(a) Labour
Man mazdoor
Women mazdoor
(b) Overheads & Contractors Profit
(c) Cost for 10 m (a+b)
Rate per each m =c/10
iv 230mm dia metre
(a) Labour
Man mazdoor
Women mazdoor
(b) Overheads & Contractors Profit
(c) Cost for 10 m (a+b)
Rate per each m =c/10
v 250mm dia metre
(a) Labour
Man mazdoor
Women mazdoor
(b) Overheads & Contractors Profit
(c) Cost for 10 m (a+b)
Rate per each m =c/10
vi 300mm dia metre
(a) Labour
Man mazdoor
Women mazdoor
(b) Overheads & Contractors Profit
(c) Cost for 10 m (a+b)
Rate per each m =c/10
vii 350mm dia metre
(a) Labour
Man mazdoor
Women mazdoor
(b) Overheads & Contractors Profit
(c) Cost for 10 m (a+b)
Rate per each m =c/10

Rate
Rs.
5

Amt
Rs.
6

PHE
Remarks
7

914

Index-code

S No
1

Description

Unit

Quantity

day

0.660

day

0.750

day

0.660

day

0.810

day

0.130

day

0.260

day
day

0.060

day
day

0.080

day
day

0.110

day
day

0.150

Rate
Rs.
5

Amt
Rs.
6

PHE
Remarks
7

viii 400mm dia metre

PHE-URGI-22

(a) Labour
Man mazdoor
Women mazdoor
(b) Overheads & Contractors Profit
(c) Cost for 10 m (a+b)
Rate per each m =c/10
ix 450mm dia metre
(a) Labour
Man mazdoor
Women mazdoor
(b) Overheads & Contractors Profit
(c) Cost for 10 m (a+b)
Rate per each m =c/10
22 Removing old G.I.pipes and specials / fittings and cleaning,
scraping the pipes, hoisting and keeping with in 50m lead but
excluding earth work excavation of trenches and refilling
Details of cost for 10 m
15 to 40mm dia
(a) Labour
Plumber
(b) Overheads & Contractors Profit
(c) Cost for 10 m (a+b)
Rate per each m =c/10
ii Above 40mm dia
(a) Labour
Plumber
(b) Overheads & Contractors Profit
(c) Cost for 10 m (a+b)
Rate per each m =c/10
23 Cutting C.I. / D.I. pipes without water in mains
Details of cost for one cutting
i 80 mm dia
(a) Labour
Asst. Fitter / Plumber 2nd class
Man mazdoor
(b) Overheads & Contractors Profit
Rate per each m
ii 100 mm dia
(a) Labour
Asst. Fitter / Plumber 2nd class
Man mazdoor
(b) Overheads & Contractors Profit
Rate per each m
iii 125 mm dia
(a) Labour
Asst. Fitter / Plumber 2nd class
Man mazdoor
(b) Overheads & Contractors Profit
Rate per each m
iv 150 mm dia
(a) Labour
Asst. Fitter / Plumber 2nd class
Man mazdoor
(b) Overheads & Contractors Profit
Rate per each m
i

PHE-CCIP-23

0.060

0.080

0.110

0.150

915

Index-code

S No
1

Description

Unit

Quantity

day
day

0.200

day
day

0.250

day
day

0.300

day
day

0.350

day
day

0.400

day
day

0.450

day
day

0.500

day
day

0.600

Rate
Rs.
5

Amt
Rs.
6

PHE
Remarks
7

200 mm dia
(a) Labour
Asst. Fitter / Plumber 2nd class
Man mazdoor
(b) Overheads & Contractors Profit
Rate per each m
vi 250 mm dia
(a) Labour
Asst. Fitter / Plumber 2nd class
Man mazdoor
(b) Overheads & Contractors Profit
Rate per each m
vii 300 mm dia
(a) Labour
Asst. Fitter / Plumber 2nd class
Man mazdoor
(b) Overheads & Contractors Profit
Rate per each m
viii 350 mm dia
(a) Labour
Asst. Fitter / Plumber 2nd class
Man mazdoor
(b) Overheads & Contractors Profit
Rate per each m
ix 400 mm dia
(a) Labour
Asst. Fitter / Plumber 2nd class
Man mazdoor
(b) Overheads & Contractors Profit
Rate per each m
x 450 mm dia
(a) Labour
Asst. Fitter / Plumber 2nd class
Man mazdoor
(b) Overheads & Contractors Profit
Rate per each m
xi 500 mm dia
(a) Labour
Asst. Fitter / Plumber 2nd class
Man mazdoor
(b) Overheads & Contractors Profit
Rate per each m
xii 600 mm dia
(a) Labour
Asst. Fitter / Plumber 2nd class
Man mazdoor
(b) Overheads & Contractors Profit
Rate per each m

PHE-DTCI-24

24

ii

iii

Drilling and tapping C.I./D.I. main and fixing brass screw down
ferrule and C.I.mouth cover.(Labour charges only)
Details of cost for one no
15 mm dia
(a) Labour
Plumber
day
(b) Overheads & Contractors Profit
Rate per each m
20 mm dia
(a) Labour
Plumber
day
(b) Overheads & Contractors Profit
Rate per each m
25 mm dia
(a) Labour
Plumber
day
(b) Overheads & Contractors Profit

0.200

0.250

0.300

0.350

0.400

0.450

0.500

0.600

0.130

0.150

0.170

916

Index-code

S No
1

PHE-SHST-25

Description

Unit

Quantity

day

0.570
1.100

Rate
Rs.
5

Amt
Rs.
6

PHE
Remarks
7

Rate per each m


25 Shoring and strutting of trenches for water and sewer lines
(A) Single staging from 0 to 8-0 ( 0 to 2.5 Metre)

Depth not exceeding 1.5 M


Details of cost for an area 30 M long and 1.5 M deep.
Area = 30 x 1.5 = 45 sqm
(a) Labour
nd

Carpenter 2 class
Man mazdoor
b) Material
Polling boards and ballies
Requirement for 45 sqm :
Polling Boards of 250 mm x 35 mm (40 x 1.5 x 0.25 x 0.038)
Ballies 125 mm dia 1.5 mts long (60 x p x (0.125)2 / 4 x 1.5

day
sqm
cum
cum

DeductCredit for materials after use @ 80% of the cost of materials


=0.8 x X

c) Machinery
Nil
Overheads & Contractors Profit
(d) Cost for 45 sqm (a+b+c)
Rate per each sqm = d/45
(B) Double staging from 8 to 14 ( 2.5 to 4.5 Metre)
Depth not exceeding 1.5 M
Details of cost for an area 30 M long and 1.5 M deep.
Area = 30 x 1.5 = 45 Sqm
(a) Labour
Carpenter 2nd class
Man mazdoor
b) Material
Polling boards and ballies
Requirement for 45 sqm :
Polling Boards of 250 mm x 35 mm (40 x 1.5 x 0.25 x 0.038 =
0.57 cum)
Ballies 125 mm dia 1.5 mts long (60 x p x (0.125)2 / 4 x 1.5 =
1.1 cum
Deduct Credit for materials after use @ 80% of the cost of
materials = 0.8 x X
c) Machinery
Nil
Overheads & Contractors Profit
(d) Cost for 45 sqm (a+b+c)
Rate per each sqm = d/45
(C) Triple staging beyond 14 for every 2 meter (beyond 4.5 M)
Depth not exceeding 1.5 M.
Note : Add for every 2 Mts (difference of single and double
staging) for staging beyond 4.5 mts.
26 Barricading, hoarding, lighting and watching etc., for water
supply and sewerage works for trenches of depths upto 6-0 (2
PHE-BHLW-26
Meter) below G.L
Taking output 3 Rmt
Material
Bamboos of 1 dia 2.5 M long (5 ft c/c = 3 x 2.5)
Baboom of 1 dia 3.66 M long (5 ft c/c = 3x 3.66)
Cost of Bamboos
(a) Usage of Material 5 times. Thus Cost of Material taken as
20%

day
day

0.500
1.320

sqm
cum

0.110

cum

0.220

rmt

7.50
10.98

rmt

917

Index-code

S No
1

Description

Unit

Quantity

day

0.500

day

0.750

day

0.250

day

2.000

day

2.000

each
m

1.000
0.500

cum

0.920

cum

0.100

(b) Labour
Man mazdoor
(c) Sundries for Coir rope, nails, @ 1%
(d) Sundries for lighting and watching etc at 1%
Overheads & Contractors Profit
Cost for 3rmt (a+b+c+d)
Rate per each rmt = (a+b+c+d)/3
27

PHE-RCVS-27

Rate
Rs.
5

Amt
Rs.
6

PHE
Remarks
7

Providing RCC spun vent shaft with cowl 140 mm and 200 mm internal
and external dia respectively at top, 300 and 450 mm internal and
external dia respectively at bottom and 9.10m overall length. Bottom 1.25
m below ground level fixed in a pit 90cmx90cm x150 cm with cement
concrete 1:4:8, 25cm in bed and minimum 20cm all-round with top 15cm
in cement concrete 1:2:4. Junction of vent shaft and concrete grouted
with cement mortar 1:1 including making connection with sewer manhole
with 150 mm dia metre cement concrete pipe of required length complete
as per standard design

Details of cost for one vent shaft


(a) Labour
st

Mason 1 class
nd
Mason 2 class
Man mazdoor (bhandani)
Man mazdoor (beldar)
b) Material
RCC went shaft with cowl
RCC pipe 150 mm dia 0.50 m (NP-2 class)
Cement Concrete 1:4:8(plain)
0.90 x 0.90 x 135 = 1.094 cum
Less for shaft 22/7 x 4 x 0.452 x 1.1= 0.175cum = 0.919 cum
Cement Concrete 1:2:4 (plain)
0.90 x 0.90 x 0.15 = 0.122 cum
Less for shaft 22/7x4 x 0.452 x 0.15= 0.024cum = 0.098 cum
(c) Total (a+b)
(d) Add for water charges @ 1% on Labour & Testing
Charges on Labour Charges
(e) Total = c+d
(f) Overheads & Contractors Profit
(g) Cost for 1 No = e+f
Well Sinking
28 Well sinking in sandy and other loose soils under water either by
manual labour, divers or dredgers weighting the top of staining
to assist sinking etc., including dewatering and other incidental
PHE-WSNP-28
charges such as hire charges for mechanical equipment etc.,
complete upto 4.0 m dia (For non perennial rivers)
i

ii

iii

Upto 2.0 m below G.L. :


(a) Labour
Man mazdoor
(b) Total
Rate per Rm = b/2
2.0 to 4.0 m below G.L. :
(a) Labour
Man mazdoor
Sinkers
b) Machinery
Hire charges for crane
Hire charges for Air compressor
Hire charges for Generator
Diesel
Overheads & Contractors Profit
c) Total
Rate per Rm = c/2
4.0 to 6.0 m below G.L. :
(a) Labour
Man mazdoor
Sinkers
b) Machinery

1%

day

105.000

day

70.000
35.000

day
hour
hour
hour
L

day
day

16.000
56.000
56.000
70.000

56.000
35.000

918

Index-code

S No
1

PHE-WSOW29

Description

Unit

3
hour

Hire charges for crane


Hire charges for Air compressor
Hire charges for Generator
Diesel
Overheads & Contractors Profit
c) Total
Rate per Rm = c/2
iv 6.0 to 8.0 m below G.L. :
(a) Labour
Man mazdoor
Sinkers
b) Machinery
Hire charges for crane
Hire charges for Air compressor
Hire charges for Generator
Diesel
Overheads & Contractors Profit
c) Total
Rate per Rm = c/2
v 8.0 to 10.0 m below G.L. :
(a) Labour
Man mazdoor
Sinkers
b) Machinery
Hire charges for crane
Hire charges for Air compressor
Hire charges for Generator
Diesel
Overheads & Contractors Profit
c) Total
Rate per Rm = c/2
29 Sinking of RCC 12 m dia well in sandy soils, soft disintegrated
rock, loamy and clayey soils etc; under water by manual or
mechanical means including dewatering until the completion of
sinking of the well to the required depth, the dummies of the
weep holes pipes are opened for seepage of water into well,
including all hire charges complete as per SS and as directed by
the departmental officers (Open well excavation)
i

ii

Upto 2.0 m below G.L. :


(a) Labour
Man mazdoor
(b) Total
Rate per Rm = b/2
2.0 to 4.0 m below G.L. :
(a) Labour
Man mazdoor
Crane Operator
b) Machinery
Hire charges for crane
Hire charges for Generator
Diesel
Overheads & Contractors Profit
c) Total
Rate per Rm = c/2

hour
hour
L

day
day
hour
hour
hour
L

day
day
hour

Quantity
4

day

178.000
11.000

hour
L

64.000
40.000

168.000

hour

Remarks

56.000
56.000
56.000
140.000

day

day

PHE

56.000
35.000

hour

Amt
Rs.
6

56.000
56.000
56.000
105.000

64.000
64.000
64.000
140.000

hour

Rate
Rs.
5

88.000
88.000
440.000

919

Index-code

S No
1

Description

Unit

Quantity

day

157.000
48.000
12.000

Rate
Rs.
5

Amt
Rs.
6

PHE
Remarks
7

iii

4.0 to 6.0 m below G.L. :


(a) Labour
Man mazdoor
Sinkers
Crane Operator
b) Machinery
Hire charges for crane
Hire charges for Air compressor
Hire charges for Generator
Diesel
Overheads & Contractors Profit
c) Total
Rate per Rm = c/2
iv 6.0 to 8.0 m below G.L. :
(a) Labour
Man mazdoor
Sinkers
Crane Operator
b) Machinery
Hire charges for crane
Hire charges for Air compressor
Hire charges for Generator
Diesel
Overheads & Contractors Profit
c) Total
Rate per Rm = c/2
v 8.0 to 10.0 m below G.L. :
(a) Labour
Man mazdoor
Sinkers
Crane Operator
b) Machinery
Hire charges for crane
Hire charges for Air compressor
Hire charges for Generator
Diesel
Overheads & Contractors Profit
c) Total
Rate per Rm = c/2
vi 10.0 to 12.85 m below G.L. :
(a) Labour
Man mazdoor
Sinkers
Crane Operator
b) Machinery
Hire charges for crane
Hire charges for Air compressor
Hire charges for Generator
Diesel
Overheads & Contractors Profit
c) Total
Rate per Rm = c/2.85
30 Well sinking in sandy and other loose soils under water either by
manual labour, divers or dredgers weighting the top of steining
to assist sinking etc., including dewatering and other incidental
PHE-WSPR-30
charges such as hire charges for mechanical equipment etc.,
complete upto 7 m dia (In Perennial Rivers only)
i

Upto 2.0 m below G.L. :


(a) Labour
Man mazdoor
Well sinkers
b) Machinery
Hire charges of set of Helmets & Air circulating pipes / valves
Hire charges for crane
Hire charges for compressors

day
day
hour
hour
hour
L

day
day
day
hour
hour
hour
L

day
day
day
hour
hour
hour
L

day
day
day
hour
hour
hour
L

day
day
day
hour
hour

96.000
102.000
96.000
1056.000

195.000
120.000
15.000
120.000
124.000
120.000
1334.000

272.000
204.000
17.000
124.000
124.000
136.000
1344.000

360.000
288.000
24.000
192.000
198.000
160.000
2148.000

32.000
64.000
4.00
32.00
32.00

920

Index-code

S No
1

ii

iii

iv

Description

Unit

Quantity

Rate
Rs.
5

Amt
Rs.
6

PHE
Remarks
7

L
Diesel
120.00
Overheads & Contractors Profit
c) Total
Rate per Rm = c/2
2.0 to 4.0 m below G.L. :
(a) Labour
day
Man mazdoor
40.000
day
Well sinkers
80.000
b) Machinery
day
Hire charges of set of Helmets & Air circulating pipes / valves
5.00
hour
Hire charges for crane
40.00
hour
Hire charges for compressors
40.00
L
Diesel
150.00
Overheads & Contractors Profit
c) Total
Rate per Rm = c/2
4.0 to 6.0 m below G.L. :
(a) Labour
day
Man mazdoor
48.000
day
Well sinkers
96.000
b) Machinery
day
Hire charges of set of Helmets & Air circulating pipes / valves
6.00
hour
Hire charges for crane
48.00
hour
Hire charges for compressors
48.00
L
Diesel
180.00
Overheads & Contractors Profit
c) Total
Rate per Rm = c/2
6.0 to 8.0 m below G.L. :
(a) Labour
day
Man mazdoor
56.000
day
Well sinkers
112.000
b) Machinery
day
Hire charges of set of Helmets & Air circulating pipes / valves
7.00
hour
Hire charges for crane
56.00
hour
Hire charges for compressors
56.00
L
Diesel
210.00
Overheads & Contractors Profit
c) Total
Rate per Rm = c/2
8.0 to 10.0 m below G.L. :
(a) Labour
day
Man mazdoor
64.000
day
Well sinkers
128.000
b) Machinery
day
Hire charges of set of Helmets & Air circulating pipes / valves
8.00
hour
Hire charges for crane
64.00
hour
Hire charges for compressors
64.00
L
Diesel
240.00
Overheads & Contractors Profit
c) Total
Rate per Rm = c/2
Note : This data shall be adopted for well sinking in perennial rivers.
For other rivers, data available for 4.0 m dia infiltration well may be
adopted for guidance

921

Index-code

PHE-CCCP-31

S No

Description

Unit

Quantity

31

Curing of CC pavement for 21 days including cost and


conveyance of water, labour charges, etc., complete

day

42.000

Areas Considered 3 . 5 x 100 mts = 350 sqm


Units = 1 sqm
Mud quantity is required = 14% of CC area x 5 cm
(a) Labour
Man mazdoor (21 x 2).
b) Machinery
Carting earth for 3 kms
Hire charges for Water Drum (5 x 21 days)
c) Material
Earth Work (100 x 3.5 x 14/100 x .05)
Supply of Water (240 Lts / cum / day)
Overheads & Contractors Profit
(d) Total = a+b+c
Rate per sqm =d/350
Note : 1. When Curing compound is used @ 1.97 kgs/cum,
requirement is 206 Lts / cum per 14 days.
2. This data is for urban areas only

PHE-CSHR-32

PHE-EXRW-33

32

cum

2.450

each

105.000

cum

2.450

18900.000

Rate
Rs.
5

Amt
Rs.
6

PHE
Remarks
7

water

Cutting sheet rock including stocking of excavated material.

Quality of sheet rock as per stock measurement = 36.53 cumm


(taking out put = 36.53 cum)
(a) Labour
day
Man mazdoor
b) Machinery
each
Drilling of holes
hr
Hire charges for JCB
each
MS Nokkulu
Overheads & Contractors Profit
(c) Total = a+b
Rate per cum =c/36.53
33 Excavation in Hard Rock (blasting prohibited)

60.000
342.000
3.000
10.000

Excavation for roadway in hard rock (blasting prohibited) with


rock breakers including breaking rock, loading in tippers and
disposal with all lifts and lead upto 1000 metres, trimming
bottom and side slopes in accordance with requirements of
lines, grades and cross- sections as per Technical Specification
Clause 302.3.5
(A) Manual Means

Unit = cum
Taking output = 1 cum
a) Labour
Mate
Mazdoor (Unskilled)
Chiseller (Hammer Man)
Blacksmith
b) Machinery
Tipper 5.5 cum capacity, 1 trip per hour
Credit for excavated rock found suitable for use @ 50 per cent
of excavated quantity
Sundries on Labour
c&d) Overheads & Contractors Profit
Rate per cum = (a+b+c+d)

day

day

1.100

day

1.500

day

0.060

hour

0.180

cum

0.500

Note : 1. Credit is considered for 50 per cent of quantity of work.


2. Loading for disposal will be done manually, being small quantity.
3. In case some rock is issued to contractor at site, the item of carriage shall be
omitted to the extent of quantity issued to the Contractor.

922

Index-code

S No
1

Description

Unit

Quantity

Rate
Rs.
5

Amt
Rs.
6

PHE
Remarks
7

(B) Mechanical Means

Unit = cum
Taking output = 1 cum
a) Labour
day
Mate
day
Mazdoor (Unskilled)
b) Machinery
Hydraulic excavator 0.9 cum with rock breaker attachment @ 6 hour
cum per hour
hour
Tipper 5.5 cum capacity tipper, 1 trip per hour
Credit for excavated rock found suitable for use @ 50 per cent of cum
excavated quantity

0.289
0.167
0.180
0.500

Sundries on Labour
c&d) Overheads & Contractors Profit
Rate per cum = (a+b+c+d)
Note : 1. The quality and availability of rock shall be checked before affording
credit.
2. In case some rock is issued to the contractor at site, the item of carriage shall
be restricted/reduced to that extent.
3. Being small quantity, manual loading will be economical in this case and has
been provided accordingly.
34

PHE-LUSS-34
i

ii

iii

iv

Loading or Unloading materials such as C.I / D.I Pipes, R.C.C.


Pipes, P.V.C. pipes, A.C. Pressure pipes and Specials less
than 300 mm upto 4 mts in length including stacking.
C.I Pipes and Specials (load per truck =6.50 T)
Taking Output = 13.00 MT (Load for each Truck 6.5 MT)
a) Labour
Man Mazdoor
Add sundries at 1% towards Nylon rope, Tyres etc
Overheads & Contractors Profit
Cost for 13 MT
Rate per MT
RCC Pipes and Collars (load per truck =7.205 T)
Taking Output = 14.41 MT
a) Labour
Man Mazdoor
Add sundries at 1% towards Nylon rope, Tyres etc
Overheads & Contractors Profit
Cost for 14.41 MT
Rate per MT
AC Pipes and Collars (load per truck = 5.40 T)
Taking Output = 10.8 MT
a) Labour
Man Mazdoor
Add sundries at 1% towards Nylon rope, Tyres etc
Overheads & Contractors Profit
Cost for 10.8 MT
Rate per MT
Stone ware pipes (load per truck = 5.40 T)
Taking Output = 10.8 MT
a) Labour
Man Mazdoor
Add sundries at 1% towards Nylon rope, Tyres etc
Overheads & Contractors Profit
Cost for 10.8 MT
Rate per MT

day

6.000
1%

day

6.000
1%

day

6.000
1%

day

6.000
1%

923

Index-code

S No
1

Description

Unit

Quantity

day

6.000

Loading or unloading materials such as C.I / D.I. Pipes, stone


ware pipes, R.C.C. pipes, A.C. Pressure pipes and specials
from 300 mm to 600 mm dia upto 4 mts in length including
stacking.
i C.I. / D.I. Pipes (load per truck = 5.5 T)
Taking Output = 11 MT
a) Labour
Man Mazdoor
Add sundries at 1% towards Nylon rope, Tyres etc
Overheads & Contractors Profit
Cost for 11 MT
Rate per MT
ii RCC Pipes and Collars (load per truck =5.75 T)
Taking Output = 11.5 MT
a) Labour
Man Mazdoor
Add sundries at 1% towards Nylon rope, Tyres etc
Overheads & Contractors Profit
Cost for 11.5 MT
Rate per MT
iii AC Pipes
Taking Output = 1MT
a) Labour
Man Mazdoor
Add sundries at 1% towards Nylon rope, Tyres etc
Overheads & Contractors Profit
Cost for MT
iv Stone ware pipes
Taking Output = 1MT
a) Labour
Man Mazdoor
Add sundries at 1% towards Nylon rope, Tyres etc
Overheads & Contractors Profit
Cost for MT
36 Loading or unloading materials such as CI / DI Pipes, A.C.
pressure pipes less than 300 mm dia above 4.00 M in length
including stacking

Rate
Rs.
5

Amt
Rs.
6

PHE
Remarks
7

35

PHE-LUMS-35

PHE-LUGS-36

1%

day

6.000
1%

day

0.700
1%

day

0.700
1%

PHE-LUBS-37

C.I. / D.I. Pipes (load per truck = 8.46 T)


Taking Output = 1 MT
a) Labour
day
Man Mazdoor
Add sundries at 1% towards Nylon rope, Tyres etc
Overheads & Contractors Profit
Cost for 1 MT
ii AC Pipes (load per truck = 3.78 T)
Taking Output = 1MT
a) Labour
day
Man Mazdoor
Add sundries at 1% towards Nylon rope, Tyres etc
Overheads & Contractors Profit
Cost for MT
37 Loading or Unloading materials such as C.I / D.I. Pipes, A.C.
Pressure pipes from 300 to 600mm dia above 4.00 m including
stacking
i

AC Pipes (load per truck = 4.3 T)


Taking Output = 1 MT
a) Labour
Man Mazdoor
Add sundries at 1% towards Nylon rope, Tyres etc
Overheads & Contractors Profit
Cost for 1 MT

day

0.710
1%

0.790
1%

0.714
1%

924

Index-code

S No

Description

Unit

Quantity

Rate
Rs.
5

Amt
Rs.
6

PHE
Remarks
7

ii

PHE-CSRC-38

C.I. Pipes (load per truck = 3.85 T)


Taking Output = 1MT
a) Labour
day
Man Mazdoor
Add sundries at 1% towards Nylon rope, Tyres etc
Overheads & Contractors Profit
Cost for MT
38 Centering and scaffolding charges for R.C.C. members
including all materials and labour charges for forming and
dismantling
A For R.C.C. Elevated Service Reservoir of Staging upto 40 Ft.
below G.W.L.
i Side wall straight surfaces:
Details cost for 15 M long and 1 M height wall
Surface area = 2 x 15 x 1 = 30 Sqm
a) Materials
i) Planks 33 mm thick
2 x 15 x 1 =
30.00 sqm
Add 5% wastage = 1.5
=31.50 sqm
31.50 x 0.038 = 1.197 Cum
cum
ii) Batters 75 x 50 mm
cum
2 x 13 x 0.075 x 0.05 = 0.095 cum
iii) Ballies 125 dia for strutting
ver
13 x 1.5 = 19.5
13 x 4.5 = 58.5
= 78.00

0.780
1%

1.197
0.095

5% for wastage = 3.9


= 81.90
2

ii

cum
81.90 x x 0.125 / 4 =1.005 Cum
Assuming that timber shall become unserviceable after being
used for 5 times
Cost for 5 times
Rate per 1 time
b) Labour
Labour charges for assembling, erection, dismantling and
cleaning
day
Carpenter 2nd class

1.005

day

6.000

cum

1.204

cum

0.313

Man Mazdoor
Sundries for nails etc
Overheads & Contractors Profit
c) Cost for 30 Sqm
Rate per sqm =c/30
Side walls curved surfaces

7.500

Considering 4 M internal dia and 1 Meter depth. Consider 30 mm thick.

Surface area:
Outside x 4.40 x 1.00 = 13.83 Sqm
Inside area = x 4 x 1 = 12.57 Sqm
= 26.40 Sqm
a) Materials
i) Planks 33 mm
26.40 x 0.038
=
1.003 cum
Extra & Wastage @ 20%
=
0.201 cum
=
1.204 Cum
ii) Hattens 75 x 38 mm
Inside 2 x 25 x 0.50 x 0.075 x 0.075 = 0.1406
Outside 2 x 28 x 0.50 x 0.075 x 0.175 = 0.1575
= 0.2981
Add 5% wastage
= 0.0149
= 0.3130 cum

925

Index-code

S No

Description

Unit

Quantity

cum

0.680

day
Mason 2nd class
day
Man Mazdoor
Total
(b) Overheads & Contractors Profit
c) Cost for 278.46 Sqm
Rate per sqm =c/278.46
Cost for 50 Kg
40 Labour charges for fixing ventilating shafts in sewerage
scheme complete with all accessories
Unit Each
a) Labour

1.000

Rate
Rs.
5

Amt
Rs.
6

PHE
Remarks
7

iii) Ballion 125 mm dia


Inside 25 x 1 = 25 m
Outside 28 x 1 = 28 m
= 53.00 m
Add 5% wastage = 2.65 m
2

PHE-HSSG-39

PHE-LCVS-40

55.65 x 0.125 = 0.68 cum


Assuming that timber shall become unserviceable after being
used for 5 times
Cost for 5 times
Rate per 1 time
b) Labour
Add labour charges for assembling, erection and dismantling
etc., @ 1/6 cost of materia
c) Total
Overheads & Contractors Profit
c) Cost for 26.04 Sqm
Rate per sqm =c/26.04
B For Ground level works
i R.C.C. vertical wells of plane surface upto 3 meters height such
as G.L. tanks clarifiers and sludge digestor etc,
Rate per Sqm (as arrived in item A (i) above)
ii R.C.C. Vertical walls of circular faces upto 3 meters height
Rate per Sqm (as arrived in item A (ii) above)
39 Hoisting of S.S. Girders in pump house etc.
Detail cost of S.S. Joist = 300 x 140 mm - 6 M long
Wt. 44.2 Kgs/M
= 6 x 44.20
= 265.20 kgs
Tolerances @ 5%
= 13.26 kgs
= 278.46 kgs
a) Labour
Labour for hoisting inn position:

Mason 1st class


Mason 2nd class
Plumber 2nd Class
Man Mazdoor
Overheads & Contractors Profit
Rate

2.750

day

0.150

day

0.350

day

0.600

day

2.000

926

Government of Andhra Pradesh

A.P. Revised Standard Data


(With Schedule of Rates 2014-15)
(Effective from 01-06-2014)

Part 1
For IRRIGATION & CAD WORKS
and
LEADS & LIFTS (Common to all Departments)

BOARD OF CHIEF ENGINEERS

Office of the Engineer-in-Chief(I.W)


I&cad Dept., Errummanzil,Hyderabad
Procs.No.ENC/IW/P&M/EE.3/DEE-10/AE/13305/Vol.37
Sub:
Ref:

dt:30.05.2014

A.P.Revised Standard Data for I&CAD works(Part-I) for the year 2014-15 approvedPrinting & communication of Standard Data Reg.,
1)G.O.Ms.No.49,I&CAD (PW:Reforms)Dept., dt:2.3.2009
2)Minutes of BOCEs meeting for Schedule of Rates held on 24.05.2014.
3) SoR Procs.No.ENC/IW/P&M/EE.3/DEE-10/AE/13305/Vol.37 dt:30.05.2014
*****
The Board of Chief Engineers meeting for finalization of Schedule of Rates (SoR) for

I&CAD(Part-I),Road & Bridges(Part-II) and Public Health Items(Part-IV) was held on 24.05.2014 @
3.30 PM and approved the SoR. Based on the approval of BoCEs, the SoR for I&CAD Dept(basic input
required for arriving unit item rate as per A.P. Revised Standard data) ,R&B and Public Health
Department items were communicated vide this office proceedings 3rd cited.

During the BoCE meeting held on 24-05-2014, it is observed that in some


of the estimates, Lead Charges are being added directly to the material basic
rates for arriving the finished item rate. In view of that, the BoCE has instructed
to see that while arriving the finished item rate, the lead charges are to be added
to the material basic rates only after deducting the provision of "Contractor's
Profit and Overhead charges"
By incorporating the items, the A.P. Revised Standard Data (unit rate for work items) for the
year 2014-15 is finalized. Any additions, modifications or deletions in the existing data must be
approved by BoCEs. One soft copy is herewith enclosed.
Encl: Soft copy of A.P. Revised Standard Data for I&CAD Department for the year 2014-15
Sd/- L.Narayan Reddy, Dt. 30.05.2014
Engineer-in-Chief(I.W.)
Chairman, BOCE(S.R)
I) Copy communicated to the Principal Secretary to Govt.,I&CAD Dept.,J-Block, A.P.Secretariat
Buildings,Hyderabad.
II) Copy Communicated to the following Heads of Departments along with Enclosures for information.
1) Engineer-in-Chief (Admn & NH)., Roads & Buildings Department.
2) Engineer-in-Chief (P.H.), Public Health Department.
3) Engineer-in-Chief (P.R.), Panchayath Raj Department.
4) Engineer-in-Chief (RWS) R W S, Department.

5) Chief Engineer (Buildings), R&B Department.


6) Copy of C.D containing Schedule of Rates 2014-15 & Standard data, part-1 (Irrigation & CAD
works) to all Engineers-in-Chief, Chief Engineers of Irrigation & CAD Department for favour of
information.
III) Copy to the Superintending Engineer, Irrigation Circle, Irrigation & CAD Department, Red Hill,
Hyderabad for necessary action.
Sd/- L.Narayan Reddy, Dt. 30.05.2014
Engineer-in-Chief(I.W.)
Chairman, BOCE(S.R)

code and index for work items of standard data


Item Code

Item of the work

Proceedings for the Standard Data


Copy of the G.O.Ms.No.49, I & CAD (PW: Reforms) Dept., dt:.2-3-2009.
PREAMBLE & GUIDELINES
PART-1

Page No.

i-xiii

IRRIGATION
Abstract of Items - Irrigation

1-45

Abstract of Leads and Lifts

46-47

IRR-DAW
IRR-DAW-1

Dam And Allied Works (48-104)


EXCAVATION & FOUNDATION TREATMENT WORKS:

48-59

IRR-DAW-2
IRR-DAW-3
IRR-DAW-4
IRR-DAW-5
IRR-DAW-6

REINFORCEMENT & CEMENT CONCRETE WORKS :


MASONRY & GUNITING WORKS :
CONTRACTION JOINT WORKS:
EARTH / ROCKFILL EMBANKMENT WORKS :
FILTER & PITCHING WORKS :

59-78
78-84
84-87
87-95
96-104

IRR-TAW
IRR-TAW-1
IRR-TAW-2
IRR-TAW-3
IRR-TAW-4
IRR-TAW-5
IRR-TAW-6

Tunnel & Allied Works (105-130)


EXCAVATION :
DEWATERING & GUNITING WORKS :
TEMPORARY & PERMANENT SUPPORTS :
MASONRY WORKS :
REINFORCEMENT & CONCRETE WORKS :
DRILLING & GROUTING WORKS :

105-113
113-116
116-122
122-123
123-128
128-130

IRR-CAW
IRR-CAW-1
IRR-CAW-2
IRR-CAW-3
IRR-CAW-4
IRR-CAW-5
IRR-CAW-6
IRR-CAW-7
IRR-CAW-8

Canal And Allied Works (131-230)


EXCAVATION WORKS :
EMBANKMENT WORKS USING BORROW AREA SOIL :
EMBANKMENT WORKS USING DUMP AREA SOIL :
EMBANKMENT WORKS USING EXCAVATED SOIL :
FOUNDATION FILLING WORKS :
ROCK FILL WORKS :
CANAL LINING WORKS :
ROCK PITCHING:

131-145
145-152
152-157
157-162
162-170
170-172
172-216
216-228

IRR-CCDW
IRR-CCDW-1
IRR-CCDW-2
IRR-CCDW-3
IRR-CCDW-4
IRR-CCDW-5
IRR-CCDW-6
IRR-CCDW-7

Canal & Cross Drainage Works (229-284)


EXCAVATION & FOUNDATION TREATMENT WORKS :
STEEL AND CEMENT CONCRETE WORKS :
FOUNDATION WELL SINKING WORKS :
MASONRY WORKS :
COPING & RAILING WORKS :
HUME PIPE LAYING & JOINTING WORKS :
BACK FILLING & OTHER WORKS :

230-236
236-262
262-264
264-271
271-275
275-281
281-284

IRR_GAW
IRR_GAW-1
IRR_GAW-2
IRR_GAW-3
IRR_GAW-4

Gates/Hoists And Allied Works (285-317)


NOTES ON GATES/HOISTS AND ALLIED WORKS
RADIAL GATES
VERTICAL LIFT GATES
SAND BLASTING AND PAINTING:
PAINTING WITHOUT SAND BLASTING:

285
285-291
291-310
310-315
315-317

IRR-PMW
IRR-PMW-1
IRR-PMW-2
IRR-PMW-3

Preliminary And Maintenance Works (318-354)


JUNGLE CLEARANCE :
PRELIMINARY WORKS :
MAINTENANCE WORKS :

318-328
328-338
338-354

Item of the work


Item Code
COMMON ITEMS TO ALL DEPARTMENTS (unless specified)
COM-MWRK
COM-LDLFT

COM-LDLFT
COM-LDLFT-1

A. Manual Works
B. Lead/Lift/Loading & Unloading Charges
(to follow MORTH standardsfor the items not covered ,as
applicable to roads and bridge works)
Notes on Lead and Lift
(Lead) Conveyance Charges for materials by head load
( Lead) Conveyance charges for machinery per kilometer for
transporting materials by tippers and trucks, excluding
loading, unloading and hire charges of machinery.

COM-LDLFT-2
COM-LDLFT-3
COM-LDLFT-4

COM-LDLFT-5
COM-LDLFT-6
COM-DTL-LDLFT-1

COM-DTL-LDLFT-4

COM-DTL-LDLFT-5
COM-DTL-LDLFT-6

355-355
356-356

356-356
356-356

356-356
LOADING AND UNLOADING CHARGES BY MANUAL
MEANS (Idle hire charges of trucks are not added)
LOADING AND UNLOADING CHARGES BY MANUAL
MEANS (including idle hire charges of trucks )
LOADING AND UNLOADING CHARGES BY MECHANICAL
MEANS (including idle hire charges of trucks )
LIFT CHARGES FOR MATERIALS BY HEAD LOAD
(Lead) Conveyance Charges for materials by head load
( Lead) Conveyance charges for machinery per kilometer for
transporting materials by tippers and trucks, excluding
loading, unloading and hire charges of machinery.

COM-DTL-LDLFT-2
COM-DTL-LDLFT-3

Page No.

356-357
357-357

357-357
357-357
358-359

359-365
LOADING AND UNLOADING CHARGES BY MANUAL
MEANS (idle hire charges of trucks are not added)
LOADING AND UNLOADING CHARGES BY MANUAL
MEANS (including idle hire charges of trucks )
LOADING AND UNLOADING CHARGES BY MECHANICAL
MEANS (including idle hire charges of trucks )
LIFT CHARGES FOR MATERIALS BY HEAD LOAD
Hire Charges

365-366
366-367

367-368
368-369
370-371

A.P. REVISED STANDARD DATA


PREAMBLE

The AP Revised Standard data for various construction items has come into
existence as per the Government orders G.O.Ms.No.49, I & CAD (PW:
Reforms) Dept., dt:.2-3-2009.

The background for adoption of A.P. Revised Standard Data is:

1.

Government, in GO 7326 (GAD-GPM& AR), Dated 26-10-2005, has observed


that the age old

Standard data requires revision and updation

with

reference to the latest machinery and contemporary practices and

has

constituted a High Level Committee to advise on updating and revision of


standard data and schedule of rates. The work has been taken up by CGG
and SPIU-irrigation. The secretary (Irrigation ) is the member- convener of
the committee
Accordingly the data has been revised adopting the procedures and
guidelines given by CWC, Report on committee on cost control of river valley
Projects, BIS specifications, NHAI, MORTH, MORD, CPWD and Government of
Karnataka and revised data and formulated schedule of rates for all
infrastructure Departments (I&CAD, R&B, PR and PH). The team of senior
engineers interacted with the S.R Committee of Karnataka on implementation
and improvements needed. For irrigation works, the data pattern as adopted by
Karnataka has been considered and for other Departments, the data adopted by
MORTH,MORD and NHAI etc. is adopted

2. Sequence followed in revision of standard data is,


(a) The first step is the revision and formulation of standard data for each
work component.

(b) The second step is to work out the details of inputs. This enables to
generate the unit work item rates, by incorporating the use rates of
machinery, materials, labour charges and other supplementary parameters.
(c) The third step is to develop software tool to generate unit rate using
the software (completed for irrigation works by the SPI Unit of Irrigation)

3. The Detailed draft data was communicated to all the HODs and
through many seminars and discussions and incorporated the
features. The Board of chief engineers in their meetings have

interacted
relevant

recommended

for acceptance to the data formulated and schedule of rates. It was proposed
to examine the recommendations on important parameters,

to refer to high

level committee, for their specific recommendations for adoption, as they are
common to all departments.
The committee made in depth study on the methodology and systems
followed by the reputed National organizations and other States and made
detailed

deliberations with HODs

Association of India and

and representatives of Builders

made recommendations to the Government, on

adoption of such parameters in A.P.

4. The Chief Secretary held a detailed discussions on 04-07-2007,with the


Secretaries of the Departments and Heads of Departments.

ii

GUIDELINES

1)

The Revised Standard Data is formulated under four Parts, which are
applicable to all the Engineering Departments and other Organisations.

PART -1:

Irrigation& CAD (Dam and Allied Works, Canals and Allied Works,
Canal C.D. Works, Tunnels and Allied Works, Preliminary and
Maintenance Works, Hydraulic Gates and allied works and Leads and
Lifts applicable to all Departments

PART -2: Roads and Bridges


PART -3: Buildings including Electrical Works
PART -4: Drinking Water Supply and Public Health (ONLY FOR WORKS
DONE BY MANUAL MEANS)

2) Brief description of item of work. :


Brief description of the item of work to cover all important aspects of the
work included in the in the Data . On reading the item description, the user should
be in a position to assess the various cost components involved in the work.
3) Data for assessing quantities:
The data reflects various assessments / assumptions made in arriving at
the quantities of materials, machinery, labour and other in-puts. In case of plants
and equipment the output of main plant is worked out and the requirement of all
other inputs and assessed to match the output of the main plant. Cycle time of
operations is the criteria for assessing the output of equipment. Generally the
equipment manufacturers furnish the output of machinery under ideal conditions of
working. Suitable job and management efficiency factors are considered while
working out the average output of machinery under field conditions. In case of
combination of machinery and manpower, the assessment of manpower shall
match the output of machinery.
Though cycle time of operations is the criteria for hourly / daily out-put of
machinery work-force ,the actual progress of work depends on several other
factors such as power interruptions, minor break-downs, time for meals and other
iii

needs of work-force, stray rains etc. Therefore, it is the general practice to consider
50 minutes as the actual working time per hour for working out the hourly / daily
out-put of machinery / work-force. CWC / BIS guide-lines stipulate the actual
working hours for the purpose of equipment planning and utilisation. The daily output is computed duly considering the actual available working time and feed back
from the field.

For gate and hoist works, it is the general practice to specify the quantity
of work in terms of number of sets of embedded parts / gates. The
requirement of machinery and work-force for cutting, bending,
fabrication, erection, painting etc., is assessed to commensurate with the
task involved.

The data for gates and E.M. Parts is arrived per Ton quantity.

The data for Hoists and Gantry Cranes is worked out on the basis of
capacity in tonnage

4) The lead and lift charges provided in PART-I (B) are generally applicable
and common to all Departments. Any item is not covered in this part, the
rates as provided in the data of the relevant works may be adopted in
preparation of estimates.

5) The basic material inputs needed for all works are listed and incorporated in
the data. The requirements are analyzed and the specifications adopted shall
confirm to Standards published by the BIS.

The labour and material rates will be communicated by the Board of


Chief engineers.

Unless otherwise specified, all material rates shall be inclusive of all


taxes, duties, levies, transportation and handling costs up to project area.

For sand, gravel , murum, stones , course aggregates etc, the rates are
to be fixed for delivery at Quarry, adding loading charges by machinery /
manual means and idle hire charges of machinery (as per table under
chapter conveyance or lead and lift charges), as applicable.
iv

For steel, Cement, AC sheets, GI sheets, Hume pipes, wood and stone
slabs, the rates are to be taken prevailing at major commercial centre
near project area. The lead charges, as applicable are to be added in
preparing estimates.

The specifications of the aggregates for sizes and gradation and its
adoption shall be as per IS 383.

6) The labour component in the data is mentioned for unit work.

No allowance towards labour importation and labour amenities added


extra as they are included in the recommended overheads.

On Labour Component: Certain additional allowances are added extra to


the wages of labour (,i.e. only on labour component in the work item) in
the form of percentage, as recommended by the Government/Board of
chief engineers due to statutory and other provisions.

However, If more than one area allowances, such as those for (1)
Municipalities (2) Agency / Tribal areas (3) Industrial areas are applicable
for a particular situation, only the maximum out of the allowable
percentages is to be allowed.

7) HIRE CHARGES OF MACHINERY : The machinery and /or group of machinery

for items of works and their output has been worked

based on the

availability of machinery generally in the market and working in the


field successfully, duly considering cycle time, idle time, operator
efficiency, type of work etc.

The hire charge of a machinery / equipment is worked out based on the


guidelines published by CWC and BIS codes.

For the other machinery not covered by the list, the R&B and other users
may adopt hire charges as recommended by the MORTH.

8) Lead Charges

The high level committee has recommended to adopt, for conveyance by


head load, a minimum lead of 50 meters and additional lead up to 150
meters in the intervals of 50 meters. Beyond 150 meters lead ,only
machinery rates are to be adopted.

The basic work item rates provided in the Standard Data & Schedule of
rates include 50 m or 1 km as initial lead and no lead charges shall be
allowed where the source of material is within the initial lead specified in
item rate. Additional lead charges shall be allowed for the lead exceeding
initial lead specified in the item rate. The Guidelines may be followed
regarding adding Lead charges as given against each chapter.

The lead charges per unit quantity for conveyance of the materials are
worked out, and included in the schedule of rates in increment of 50 m
for head load and in increment of 1 km for mechanical mode.

The rates for lead charges by head load up to 150 meters and by
machinery up to 5 km, shall be cumulative and inclusive of lead charges
for preceding lead. For lead beyond 5 km, the lead charges shall be
worked out on per km basis.

9) Loading and Unloading charges for Materials


The following features are considered:
1. Loading and unloading charges are not payable for conveyance by head load.
2. Loading and unloading charges are not payable for conveyance by mechanical
means, for disposal of excavated material unless specified.
3. The rates for unloading of materials except earth, sand, gravel, coarse
aggregate, rubble, size stone and cut stone, are inclusive of stacking

wherever

applicable.

vi

10) LIFT CHARGES :

The data includes initial lift charges of

3 meters ,for materials

conveyance by head load, Additional leads in the interval of 1.0 meters


are

worked out,

as additional labour input and incorporated in the

chapter on Lead and lifts .

Where the conveyance / lifting of material is done by mechanical means,


lift charges shall not be considered, as the cycle time of operation of the
machine includes lifts involved.

The data and rates for lift charges is cumulative and are inclusive of rates
for preceding lifts also.

11) Wastage of Materials


I) Cement : No wastage allowance is recommended towards the quantity of

cement used in works, as the wastage is already included in the input


and in major works , bulk quantities are used.

II) steel : The wastage

of steel @ 2.5% is allowed for gates and allied

structures. For RCC works

the wastage is @2.5% for the

reinforcement rods above 36mm dia. and @ 5% for rods below 36mm
dia. Including overlaps, if they are not welded.
If welding is adopted for the reinforcement rods even for below 36mm
dia, 2.5% of wastage is only recommended.

12) Provision for rate for water:The Committee has recommended not to consider the water charges in
the Irrigation Project works. But, it may be considered in specific cases as per
the site conditions.

13)

In respect of RCC works the rate for cement concrete for 1 cum

is

worked separately for all grades based on Indian Standards. The rate for ton is
vii

calculated separately and to be added separately in the estimates of RCC works


as a separate item.

14) Soil classification: The Committee recommended to allow uniform


classification of soils for all Departments and data is worked out accordingly.
1. all soils
2. Marshy soil
3. ordinary rock ( not requiring blasting),
4. hard rock
a. hard rock (requiring blasting)
b. hard rock (controlled blasting)
c. removable by chiseling(blasting prohibited)

15) Use of Super Plasticizers and Admixtures:

Concrete admixtures such as Air-Entraining Agent ( AEA ) / Water reducing agent


can be used advantageously for better quality concrete. The high level committee
has recommended to adopt for super plasticizers and admixtures at 0.4% on
cement for concrete work as per MORTH standards for batching plants.

16) Contractors overheads, profit and other provisions :

High Level Committee has recommended adding 14% towards contractor


overheads and profit including labour importation and amenities etc., as given
below which includes various items recommended in MORTH.

The provision for VAT at 5% or as fixed by the Government from time to time
should be made separately in Part-B of the estimate. In the agreements it
should be mentioned that it will be reimbursed as per actual. The provisions
allowed in G.O.Ms.No.94, I&CAD, dt:01.07.03, need not be added separately
for the items covered in the contractor overhead charges.

The provision for labour Cess at 1% or as fixed by the Government from time to
time should be made separately in Part-B of the estimate.
viii

The overhead charges include the following elements:

Site accommodation, setting up plant, access road, water supply, electricity and
general site arrangements.

Office furniture, equipment and communications

Expenditure on:

Corporate office of contractor

site supervision

Documentation and as built drawings

Mobilisation/ de-mobilisation of resources

Labour camps with minimum amenities and transportation to work sites.

Light vehicles for site supervision including administrative and managerial


requirements.

Laboratory equipment and quality control including field and laboratory testing.

Minor T & P and survey instruments and setting outworks, including verification
of line, dimensions, trial pits and bore holes, where required.

Watch and ward

Traffic management during construction

Expenditure on safeguarding environment

Sundries

Financing Expenditure

Sales/ Turn overtax

Work Insurance/ compensation

17) EXCISE DUTY ON SUPPLIES :


In respect of gates, hoists and allied works, excise duty is applicable on
the value of fabricated components supplied to site. Excise duty is not applicable
on erection charges. Further, the excise duty shall not be considered in the rate
analysis on material component, as basic material rates are inclusive of excise
duty.

ix

Therefore, excise duty is considered in the rate analysis only on


machinery and labour components required for fabrication of gates and hoists at
the central fabrication yard. It is difficult to determine the machinery and labour
components separately for fabrication and erection.
For the purpose of computation of excise duty to be included in the rate analysis
the machinery and labour components may apportioned at 75 % for central
fabrication yard and 25 % for field erection and commissioning. Therefore, 75 % of
the machinery and labour components may be considered for assessing the extent
of excise duty to be added in the rate analysis.

18) DEWATERING & DESILTING:


The High level committee considering the local conditions of rainfall / seepage has
recommended towards de-watering and de-silting at 3 percent on the relevant
work component for which dewatering is required.
It is also proposed as per CWC guidelines, to keep a condition in the agreements
shall be incorporated, to fix a ceiling of 5% in extreme cases, with the specific
approval of chief engineer/Government.

19) Computerization Of Data :

A software program is developed by the SPI Unit(Irrigation), which


facilitates automatic changes and

generation of unit rates, based on

basic input rates of Labour, materials and capital cost of machinery.

A soft ware tool is also developed for auto preparation of estimates


based on in put quantities.

Other Departments are also advised to develop such program.

20) For each chapter separate additional details are incorporated for clarity.

USER GUIDELINES OF REVISED STANDARD DATA


1. Please select the item of work, as given in Index Code, and

view

the relevant data.

2.

The common data items like, lead, lift, conveyance and manual
excavation (without involving contracting agencies) is applicable
to all Departments (volume-1).

3. The departments have to adopt the relevant data from other


Departments, if such works are executed by them.

4.

The unit rate /hire charges, of

machinery not covered in the

Irrigation data, the MORTH data may be taken with the approval
of Board of Chief Engineers.

5. For

Drinking

water

Supply

works(PART-IV),

incorporated is generally applicable only for manual

the

data

means of

execution. The rates deploying machinery have to be worked out


by the Board of Chief engineers and approved for adoption.

xi

ROLE OF CENTRAL COMPETENT AGENCY FOR SCHEDULE OF RATES


( BOARD OF CHIEF ENGINEERS)

a) The Board Of Chief Engineers under the chairman ship of Engineer-inchief,(administration) I&CAD Department is the competent authority to
finalise and recommend the Schedule of Rates applicable for all engineering
Departments. The board has to assess and incorporate only the three basic
inputs required to generate unit work item rates as below.

Basic rates of labour:


Wages of labour commonly required in execution of works has to be
arrived and incorporated in the schedule of rates ( Basic Input Of Labour
Wages), without adding extra towards area allowances ( like municipality
allowance, tribal area and ghat road allowances etc, which shall be added to
the rates where applicable in the form of separate percentage as explained
in the preceding paras. The rates shall be the prevailing daily rates in the
State and shall not be less than the minimum wages fixed by the
Government from time to time.

Materials rates:
The basic input material rates common to all departmental works are
listed out and incorporated (in the chapter Basic inputs) The

material

specifications adopted shall confirm to Standards published by the BIS.


The Prevailing market rates for all basic input materials shall be
obtained from the major commercial centers near the project areas. Average
of the rates, ignoring freak rates, shall be reckoned as the prevailing market
rate.
Unless otherwise specified, all material rates shall be inclusive of

all

taxes, duties, levies, royalty, transportation and handling costs up to


project area.

xii

For sand, gravel , murrum, stones , aggregates etc, the rates

are

for delivery at Quarry including loading charges and idle hire

charges. For

steel, Cement, AC sheets, GI sheets, Hume pipes, wood and

stone slabs,

the rates prevailing at major commercial centre near project area has to be
adopted.
Use rate of machinery:
The third parameter for incorporation in the Basic Inputs, is the use rate
of machinery. To arrive at the use rate of machinery, the inputs to be
incorporated are

The

list and capital cost of machinery required

to be

used in the

construction activity, The rate has to be obtained from major


manufacturers and outlet sources and the rate shall be the current
market price inclusive of all taxes, duties and freight charges.

The prevailing fuel charges of petrol and diesel are ascertained and
average rate adopted

Borrow rate of interest as fixed by the Government/competent authority


be indicated.

For the other machinery not covered by the list, the R&B and other
users may adopt hire charges as recommended by the MORTH

b) The Chairman, Board of Chief Engineers or competent authority appointed


by the Government, based on the approved basic inputs, load the above three
basic parameters in the software program. The unit rate of all works including
hire charges of all machinery will be generated automatically for adoption.

He shall communicate the uniform Schedule of rates arrived from


Standard Data, to all users for uniform and direct adoption in all
infrastructure Departments, as applicable

xiii

Abstract of work items_UNit Rates for the year 2014-15

WORK ITEM RATES


FOR THE YEAR - 2014-15
* Add Leads and Lifts, Area Allowance and VAT as applicable in the estimate
** Area Allowance includes profit component also
*** Unit Rates arrived without Seigniorage Charges
Chapterwise item
S.NO
No.
1
Chapter I
IRR-DAW

Unit

Rate

cum

120.70

DAM AND ALLIED WORKS


EXCAVATION & FOUNDATION TREATMENT WORKS:

IRR-DAW-1

IRR-DAW-1-1

Item description

Excavation for foundation in all kinds of soil including boulders upto 0.30 m
diameter for dam, spillway, intake structure and other appurtenant works and
placing the excavated soil neatly in dump area or disposing off the same as
directed etc., complete with initial lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)

IRR-DAW-1-2

IRR-DAW-1-3

IRR-DAW-1-3-A
New Item 201415-1

Itemwise unit rate


for Labour
Component
6

Excavation for foundation in ordinary rock (including HDR) without blasting


including boulders above 0.3 m upto 0.6 m dia for dam, spillway, intake
structure and other appurtenant works and placing the excavated material neatly
in dump area or disposing off the same as directed etc., complete with initial
lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)
Excavation for foundation in hard rock (including F&F) requiring blasting
including boulders above 0.6 m upto 1.2 m dia. for dam, spillway, intake
structure and other appurtenant works and placing the excavated material neatly
in dump area or disposing off the same as directed etc., complete with initial
lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)

Excavation for foundation in hard rock (including F&F rock) including


boulders above 0.6 m upto 1.2 m dia. by controlled blasting and controlling
fly rock by muffling arrangements for dam, spillway, intake structure and other
appurtenant works and other open foundation works and placing the excavated
material neatly in dump area or disposing off the same as directed etc.,
complete with initial lead upto 1 km and all leads
Labour Component (including contractor's profit and Overheads)

cum

cum

22.50

159.90

cum

cum

29.20

240.50

cum

cum

52.00

360.50

61.20
cum

IRR-DAW-1-4(a)

IRR-DAW-1-5(b)

Excavation for foundation in hard rock of all toughness by blasting including


boulders above 1.2 m dia. for dam, spillway, intake structure and other
appurtenant works and placing the excavated rock neatly in dump area or stack
yard including levelling as directed etc., complete with initial lead upto 1 km
and all lifts.
Labour Component (including contractor's profit and Overheads)
Excavation for foundation in hard rock of all toughness including boulders
above 1.2 m dia. by controlled blasting method and controlling fly-rock by
muffling arrangements for dam, spillway, intake structure and other appurtenant
structures etc., including placing and levelling the excavated rock neatly in dump
area or other place as directed etc., complete with lead upto upto 1 km and all
lifts.
Labour Component (including contractor's profit and Overheads)

cum

428.50

cum

cum

100.40

662.70

cum

110.20

Excavation for foundation in hard rock of all toughness including boulders


above 1.2 m dia. by line drilling and smooth blasting and controlling fly-rock by
muffling arrangements for dam, spillway, intake structure and other appurtenant
structures etc., including dressing sides and bed to required level / profile,
placing and levelling the excavated rock neatly in dump area or other place as
directed etc., complete with lead upto 1 km and all lifts.

IRR-DAW-1-6(c)

i ) For the purpose of payment 1 m width of excavation along boundary of


excavation shall be treated as excavation by line drilling and smooth blasting
and remaining portion shall be treated as excavation by normal / controlled
blasting as the case may be.
ii ) The rate includes controlling fly-rock wherever required.
iii ) The rate under this item shall be paid only on ascertaining that the
excavated face has come off neatly as per specifications or atleast 50 percent of
smooth blast holes are visible for inspection and are spaced at specified interval.
iv ) In case, where the above criteria is not fulfilled payment shall be restricted to
rate provided for excavation by normal blasting or controlled blasting as the case
may be.
Labour Component (including contractor's profit and Overheads)

cum

cum

909.60

290.20

Abstract of work items_UNit Rates for the year 2014-15

Chapterwise item
S.NO
No.
1

IRR-DAW-1-7

IRR-DAW-1-8

IRR-DAW-1-9

10

Item description

Unit

Rate

3
Preparing foundation bed for masonry or concrete by benching, stepping,
removing all loose material by wedging / chiselling and disposing off the same as
directed and cleaning the surface with air and water jet etc.,complete with initial
lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)

sqm

33.90

Preparing foundation bed for cut-off trench filling in rock portion by removing
all loose materials by wedging / chiselling and disposing off the same as directed
etc., complete with initial lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)
Drilling 45 to 50 mm dia holes vertical or inclined upto 10 degrees to vertical in
rock /masonry / concrete by percussion drilling using waggon drill or any
other suitable equipment including cost of all materials, machinery, labour,
redrilling through partially set grout wherever required etc., complete for drilling
upto 6 m depth from surface.

sqm

sqm

Itemwise unit rate


for Labour
Component
6

26.60

22.50

sqm

22.50

Rm

199.80

Rm
Rm
Rm
Rm
Rm
Rm
Rm
Rm

219.80
241.80
266.00
292.60
321.90
354.10
389.50

Rm

50.90

The item rate for drilling through rock / masonry / concrete includes redrilling
through partially set grout, if any, in the portion of the hole drilled and grouted.
.

IRR-DAW-1-10

IRR-DAW-111(a)

IRR-DAW-112(b)

IRR-DAW-1-13

IRR-DAW-1-14

11

12

13

14

15

Flushing grout holes of all sizes with water and air jets alternatively for an
average period of 30 minutes including water intake observations after flushing,
cost of all materials, machinery, labour etc., complete.
Labour Component (including contractor's profit and Overheads)

Rm

Consolidation grouting with neat cement grout mix of suitable consistency


under specified pressure as directed in drilled holes by stage grouting method
including cost of all materials, machinery, labour, redrilling if necessary
etc.,complete with initial lead upto 1 km and all lifts.

tonne

Labour Component (including contractor's profit and Overheads)

tonne

Curtain grouting with neat cement grout mix of suitable consistency under
specified pressure as directed in drilled holes by stage grouting method
including cost of all materials, machinery, labour, redrilling if necessary etc.,
complete with initial lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)

tonne

17.20

8413.30

2775.80

9365.40

tonne

Providing and fixing 25 mm dia 3 m long cold twisted deformed steel dowel
bars with one end driven into 45 to 50 mm diameter 1.50 m deep hole drilled in
bed rock and other end provided with L-bend for embedding in concrete /
masonry of over flow / non-over flow blocks and other appertenant works
including cost of drilling and cleaning hole, filling hole with cement mortar 1 : 1
proportion, driving anchor rod, cost of all materials, machinery, labour etc.,
complete with initial lead upto 1 km and all lifts.

Each

Labour Component (including contractor's profit and Overheads)

Each

Providing and fixing 25 mm dia. 2.75 m long ribbed steel anchor rods with
one end split and driven firmly using steel wedge into 1.25 m deep 45 to 50 mm
dia. hole drilled in bed rock and other end provided with L- bend for embedding
in concrete / masonry for spillway and appurtenant works including drilling and
cleaning hole, filling hole with thick cement slurry, driving anchor rod, cost of all
materials, machinery, labour, steel wedge etc., complete with initial lead upto 1
km and all lifts.
Labour Component (including contractor's profit and Overheads)

43.80

Each

3573.80

1016.30

102.30

933.30

Each

115.60

REINFORCEMENT & CEMENT CONCRETE WORKS :

IRR-DAW-2

IRR-DAW-2-1A

Beyond 6 m upto 12 m from surface :


Beyond 12 m upto 18 m from surface :
Beyond 18 m upto 24 m from surface
Beyond 24 m upto 30 m from surface
Beyond 30 m upto 36 m from surface
Beyond 36 m upto 42 m from surface
Beyond 42 m upto 48 m from surface
Labour Component (including contractor's profit and Overheads)

16

Providing, fabricating and placing in position reinforcement steel for


RCC,below 36 dia rods overlaps and wastages wherever required, tying with
1.25 mm diameter soft annealed steel wire, including cost of all materials,
machinery, labour etc., complete with initial lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)

59857.87
tonne
tonne

3326.30

Abstract of work items_UNit Rates for the year 2014-15

Chapterwise item
S.NO
No.
1

IRR-DAW-2-1B

IRR-DAW-2-2

17

18

IRR-DAW-2-2A
(new Item1 2010- 19
11)

IRR-DAW-2-3

IRR-DAW-2-4

20

21

IRR-DAW-2-4A
(new Item2 2010- 22
11)

IRR-DAW-2-4B
(new Item3 2010- 23
11)

Item description

Unit

Rate

Providing, fabricating and placing in position reinforcement steel for RCC


above 36 dia with welding and wastage at 2.5%, tying with 1.25 mm diameter
soft annealed steel wire, including cost of all materials, machinery, labour etc.,
complete with initial lead upto 1 km and all lifts.
tonne
Labour Component (including contractor's profit and Overheads)
tonne
Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength
not less than 15 N / sq mm ) grade cement concrete using 80 mm down size
approved, clean, hard, graded aggregates including cost of all materials,
machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing,
placing in position, levelling, vibrating, finishing, curing etc.,complete for plain
concrete works with initial lead upto 1 km and all lifts. ( Cement content : 250
kg /cum with use of super plasticiser equla to 0.4% of cement content, CA :
0.98 cum, Blending Ratio of CA -- 40:30:20:10, FA : 0.35 cum ))

cum

Labour Component (including contractor's profit and Overheads)

cum

Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength
not less than 20 N / sq mm ) grade cement concrete using 80 mm down size
approved, clean, hard, graded aggregates including cost of all materials,
machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing,
placing in position, levelling, vibrating, finishing, curing etc.,complete for plain
concrete works with initial lead upto 1 km and all lifts. ( Cement content : 300
kg /cum with use of super plasticiser equla to 0.4% of cement content, CA :
0.90 cum, Blending Ratio of CA -- 40:30:20:10, FA : 0.4 cum ))

cum

Labour Component (including contractor's profit and Overheads)

cum

Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength
not less than 10 N / sq mm ) grade cement concrete using 80 mm down size
approved, clean, hard, graded aggregates including cost of all materials,
machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing,
placing in position, levelling, vibrating, finishing, curing etc.,complete for plain
concrete works with initial lead upto 1 km and all lifts. ( Cement content : 220
kg /cum with use of super plasticiser, CA: 0.98 cum, Blending Ratio of CA -40:30:20:10, FA: 0.37 cum )

cum.

Labour Component (including contractor's profit and Overheads)

cum.

Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength
not less than 20 N / sq mm ) grade cement concrete using 40 mm down size
approved, clean, hard, graded aggregates including cost of all materials,
machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing,
placing in position, levelling, vibrating, finishing, curing etc.,complete for RCC
works of gallery, sluice, spillway crest, spillway d / s face, energy dissipating
structures, training walls, piers, abutments and such other locations with initial
lead upto 1 km and all lifts. ( Cement content : 310 kg / cum with use of super
plasticiser, CA : 0.90 cum, blending ratio of CA--50:30:20, FA : 0.40 cum)

cum.

Labour Component (including contractor's profit and Overheads)

cum.

Providing and laying insitu vibrated M-25 ( 28 days cube compressive strength
not less than 25 N / sq mm ) grade cement concrete using 40 mm down size
approved, clean, hard, graded aggregates including cost of all materials,
machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing,
placing in position, levelling, vibrating, finishing, curing etc.,complete for RCC
works of gallery, sluice, spillway crest, spillway d / s face, energy dissipating
structures, training walls, piers, abutments and such other locations with initial
lead upto 1 km and all lifts. ( Cement content : 360 kg / cum with use of super
plasticiser,CA : 0.90 cum, blending ratio of CA--50:30:20, FA : 0.40 cum)
Labour Component (including contractor's profit and Overheads)

Providing and laying insitu vibrated M-25 ( 28 days cube compressive strength
not less than 25 N / sq mm ) grade cement concrete using 20 mm down size
approved, clean, hard, graded aggregates including cost of all materials,
machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing,
placing in position, levelling, vibrating, finishing, curing etc.,complete for RCC
works of gallery, sluice, spillway crest, spillway d / s face, energy dissipating structures,
training walls, piers, abutments and such other locations with initial lead upto 1 km
and all lifts. ( Cement content : 380 kg / cum with use of super plasticiser,CA : 0.90
cum, blending ratio of CA--65:35, FA : 0.40 cum)
Labour Component (including contractor's profit and Overheads)

cum.

61009.05

4423.50

3454.20

160.90

3665.50

160.90

3300.90

160.90

4640.50

318.60

4916.40

cum.

cum.

cum.

Itemwise unit rate


for Labour
Component
6

318.60

5006.80

318.60

Abstract of work items_UNit Rates for the year 2014-15

Chapterwise item
S.NO
No.
1

IRR-DAW-2-5

IRR-DAW-2-6

IRR-DAW-2-7

IRR-DAW-2-8

IRR-DAW-2-9

IRR-DAW-2-10

Item description

Unit

Rate

24

Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength
not less than 15 N / sq mm ) grade cement concrete using 40 mm down size
approved, clean, hard, graded aggregates including cost of all materials,
machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing,
placing in position, levelling, vibrating, finishing, curing etc.,complete for plain
concrete works with initial lead upto 1 km and all lifts. ( Cement content : 260
kg /cum with use of super plasticiser,CA : 0.90 cum, Blending Ratio of CA -50:30:20, FA : 0.40 cum)

cum.

4242.70

Labour Component (including contractor's profit and Overheads)

cum.

Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength
not less than 15 N / sq mm ) grade cement concrete using 40 mm down size
approved, clean, hard, graded aggregates with placing and sinking plums of
size 150 to 80 mm upto 15 percent for gravity type structures including cost of
all materials, machinery, labour, formwork, scaffolding, cleaning, batching,
mixing, placing in position, levelling, vibrating, finishing, curing etc.,complete
with initial lead upto 1 km and all lifts. ( Cement content : 260 kg / cum of
concrete with use of plums and super plasticiser,, CA : 0.77 cum, Blending
Ratio of CA : 50:30:20,FA : 0.34 cum, plums of size 150 to 80 mm : 0.25 cum)

cum.

Labour Component (including contractor's profit and Overheads)

cum.

25

26

27

28

29

Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength
not less than 10 N / sq mm ) grade cement concrete using 40 mm down size
approved, clean, hard, graded aggregates including cost of all materials,
machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing,
placing in position, levelling, vibrating, finishing, curing etc.,complete for plain
concrete works with initial lead upto 1 km and all lifts. ( Cement content 220
kg /cum with use of super plasticiser,CA : 0.90 cum, Blending Ratio of CA :
50:30:20, FA : 0.40 cum )
Labour Component (including contractor's profit and Overheads)

cum.

cum.

Labour Component (including contractor's profit and Overheads)

cum.

Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength
not less than 20 N / sq mm ) grade cement concrete using 20 mm down size
approved, clean, hard, graded aggregates including cost of all materials,
machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing,
placing in position, levelling, vibrating, finishing, curing etc.,complete for RCC
works of spillway bridge, blockouts and such other similar structures with
conjested reinforcement with initial lead upto 1 km and all lifts. ( Cement
content : 330 kg / cum with use of super plasticiser, CA : 0.80 cum, Blending
Ratio of CA -- 65:35, FA : 0.44 cum).

cum.

Labour Component (including contractor's profit and Overheads)

cum.

Providing and forming porous concrete body drain of size 68.5 x 68.5 cm with 23
cm diameter central hole using cement and 20 mm down approved, clean, hard,
graded coarse aggregates in 1 : 3.50 proportion by volume including cost of all
materials, machinery, labour, formwork, curing etc., complete with initial lead
upto 1 km and all lifts.(M15 Cement content : 400kg/cum, CA : 1cum, Blending
Ratio of CA -- 65:35)
Labour Component (including contractor's profit and Overheads)

1141.30

4108.80

1113.60

3921.10

cum.

Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength
not less than 15 N / sq mm ) grade cement concrete using 20 mm down size
approved, clean, hard, graded aggregates including cost of all materials,
machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing,
placing in position, levelling, vibrating, finishing, curing etc.,complete for plain
concrete works with initial lead upto 1 km and all lifts. ( Cement content : 280
kg /cum with use of super plasticiser,CA : 0.80 cum, Blending Ratio of CA -65:35, FA : 0.44 cum)

Rm

Rm

Itemwise unit rate


for Labour
Component
6

1033.20

4128.10

1058.00

5869.00

1499.60

2191.20

515.30

Abstract of work items_UNit Rates for the year 2014-15

Chapterwise item
S.NO
No.
1

IRR-DAW-211(a)

IRR-DAW-212(b)

IRR-DAW-2-13

IRR-DAW-2-14

IRR-DAW-2-15

IRR-DAW-2-16

IRR-DAW-2-17

IRR_DAW-3

Item description

Unit

Rate

Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength
not less than 20 N / sq mm ) grade cement concrete using 20 mm down size
approved, clean, hard, graded aggregates including cost of all materials,
machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing,
placing in position, levelling, vibrating, finishing, curing etc.,complete for RCC
solid parapet consisting of 35 cm x 20 cm kerb, 35 cm x 35 cm x 1 m pillars
spaced approximately at 3.35 m c / c, 12.5 cm thick wall 80 cm height with 12.5
cm thick and 35 cm wide coping slab for wall and 12 .5 cm thick 40 cm x 40 cm
coping for pillars with top edges of kerb and coping chamferred / rounded as
directed etc., complete ( excluding cost of providing and placing
reinforcement steel and gate ) with initial lead upto 1 km and all lifts. (
Cement content 350 kg / cum with use of super plasticiser( 0.4% by wt.of
cement), CA : 0.80 cum, Blending Ratio of CA--65:35, FA : 0.44 cum)

Rm

2221.70

Labour Component (including contractor's profit and Overheads)

Rm

Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength
not less than 20 N / sq mm ) grade cement concrete using 20 mm down size
approved, clean, hard, graded aggregates including cost of all materials,
machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing,
placing in position, levelling, vibrating, finishing, curing etc.,complete for RCC
ornamental parapet consisting of 35 cm x 20 cm kerb, 35 cm x 35 cm x 1 m
pillars spaced approximately at 3.5 m apart, 20 cm x 15 cm posts 80 cm height
approximately 30 cm c / c with 12.5 cm thick and 35 cm wide coping slab for
posts and pillars with top edges of kerb and coping chamferred or rounded as
directed etc., complete ( excluding cost of providing and placing reinforcement
steel and gate ) with initial lead upto 1 km and all lifts. ( Cement content : 350
kg / cum with use of super plasticiser, CA : 0.80 cum, Blending Ratio of CA-65:35, FA : 0.44 cum)

Rm

Labour Component (including contractor's profit and Overheads)

Rm

Providing and laying insitu M- 25 ( 28 days cube compressive strength not less
than 25 N / sq mm ) grade cement concrete using 20 mm down size approved,
clean, hard, graded aggregates for wearing coat including cost of all materials,
machinery, labour, formwork, cleaning, batching, mixing, placing in position in
alternate panels, levelling, compacting, finishing, curing, packing joints with
asphalt mortar etc., complete with initial lead upto 1 km and all lifts. ( Cement
content : 380 kg / cum with use of super plasticiser, CA : 0.80 cum, Blending
Ratio of CA--65:35, FA : 0.45 cum)

cum

Labour Component (including contractor's profit and Overheads)

cum

Pre-cooling to control placement temperature of cement concrete in the range of


18 to 21 C at the concrete placement point by inundation of coarse aggregates
and adding flaked ice as part of mixing water including cost of all materials,
machinery, labour etc., complete with all leads and lifts.

cum

Labour Component (including contractor's profit and Overheads)

cum

30

31

32

33

34

35

36

Conveying and fixing elastomeric bearing for spillway bridge including cleaning
and preparing surface, mixing and applying adhesive, fixing bearing in correct
position etc., including cost of all materials except bearings, machinery, labour
etc., complete with all leads and lifts.
Labour Component (including contractor's profit and Overheads)

Each

639.00

2290.90

678.20

4725.50

1282.80

81.20

12.30

321.30

Each

Providing and constructing 150 mm dia hume pipe weep holes for concrete /
masonry walls including providing 20 x 20 x 20 cm size porous concrete block
made of cement and 20 mm down coarse aggregate in 1 : 4 proportion
including 10 cm thick sand backing at the junction of wall and soil back fill, cost of
all materials, machinery, labour etc., complete with lead upto 1 km and all lifts.

Rm

Labour Component (including contractor's profit and Overheads)

Rm

Providing and forming expansion joint for spillway bridge consisting of 75 x


75 x 6 mm angles 2 numbers provided with 25 cm long 12 mm dia. anchors
fixed to both flanges at 15 cm c /c and 140 x 6 mm plate welded on top of one of
the angle including cost of all materials, machinery, labour, providing and fixing
38 mm thick joint filler board matching the thickness of wearing coat, painting
etc., complete with lead upto 1 km and all lifts.

Rm

Labour Component (including contractor's profit and Overheads)

Rm

Itemwise unit rate


for Labour
Component
6

266.00

435.70

60.80

1909.40

277.80

MASONRY & GUNITING WORKS :

Abstract of work items_UNit Rates for the year 2014-15

Chapterwise item
S.NO
No.
1

IRR_DAW-3-1

37

IRR_DAW-3-2

IRR_DAW-3-3

38

39

Item description

Unit

Rate

3
Providing and constructing un-coursed rubble stone masonry using approved
stones in cement mortar 1 : 3 proportion including cost of all materials,
machinery, labour, scaffolding, cleaning, packing mortar, wedging stone chips,
curing etc., complete with initial lead upto 1 km and all lifts.( Cement content :
190 kg/cum of masonry, rubble stones : 0.85 cum,stone chips : 0.15 cum/cum,
FA : 0.4 cum)
Labour Component (including contractor's profit and Overheads)

cum

2584.70

Providing and constructing un-coursed rubble stone masonry using approved


stones in cement mortar 1 : 4 proportion including cost of all materials,
machinery, labour, scaffolding, cleaning, packing mortar, wedging stone chips,
curing etc., complete with initial lead upto 1 km and all lifts.( Cement content :
143 kg/cum of masonry, rubble stones : 0.85 cum, stone chips : 0.15 cum/cum,
cum
FA : 0.4 cum)
Labour Component (including contractor's profit and Overheads)
cum
Providing and constructing coursed rubble face stone masonry using approved
rubble stones in cement mortar 1 : 3 proportion including cost of all materials,
machinery, labour, scaffolding, ramps, cleaning, packing mortar, wedging stone
chips, curing etc., with initial lead upto 1 km and all lifts.( Thickness of the CR
face assumed: 0.75 m, Cement content : 178 kg/cum of masonry, rubble
stones : 0.35 cum, stone chips : 0.15 cum/cum, FA : 0.375 cum, CR stones 30 x
30 x 45 cm : 9.75 No, CR stones 30 x 30 x 60 cm : 3.25 No)
Labour Component (including contractor's profit and Overheads)

IRR_DAW-3-4

IRR_DAW-3-5

40

41

IRR-DAW-3-7

IRR-DAW-3-8

42

43

44

IRR_DAW-4

IRR-DAW-4-1

cum

Providing and constructing chisel drafted and hammer dressed face stone
masonry with approved stones in cement mortar 1 : 3 proportion including
cost of all materials, machinery, labour, scaffolding, ramps, cleaning, packing
mortar, wedging stone chips, curing etc.,complete with initial lead upto 1 km
and all lifts.( Cement content : 167 kg/cum of masonry, rubble stones : 0.35
cum, stone chips : 0.15 cum/cum, FA : 0.35 cum, Dressed stones 30 x 30 x 45
cm : 10 No, Dressed stones 30 x 30 x 60 cm : 3.40 No)

972.50

2364.60

972.50

2750.10

cum

Providing and constructing coursed rubble face stone masonry using approved
rubble stones in cement mortar 1 : 4 proportion including cost of all materials,
machinery, labour, scaffolding,ramps, cleaning, packing mortar, wedging stone
cum
chips, curing etc., with initial lead upto 1 km and all lifts. ( Cement content :
134 kg/cum of masonry, rubble stones : 0.35 cum, stone chips : 0.15 cum/cum,
FA : 0.375 cum, CR stones 30 x 30 x 45 cm : 9.75 No, CR stones 30 x 30 x 60 cm :
3.25 No)
Labour Component (including contractor's profit and Overheads)
cum

Labour Component (including contractor's profit and Overheads)

IRR-DAW-3-6

cum

cum

1082.70

2543.90

1082.70

2935.40

cum

Providing and constructing chisel drafted and hammer dressed face stone
masonry with approved stones in cement mortar 1 : 4 proportion including
cost of all materials, machinery, labour, scaffolding, ramps, cleaning, packing
mortar, wedging stone chips, curing etc.,complete with initial lead upto 1 km
and all lifts.( Cement content : 125 kg/cum of masonry, rubble stones : 0.35
cum, stone chips : 0.15 cum/cum, FA : 0.35 cum, Dressed stones 30 x 30 x 45
cm : 10 No, Dressed stones 30 x 30 x 60 cm : 3.40 No)

cum

Labour Component (including contractor's profit and Overheads)

cum

Providing cement mortar pointing to coursed rubble face stone masonry 50


mm deep in CM 1 : 2 proportion by volume including raking and cleaning joints,
pressing mortar into joints, cost of all materials, labour, scaffolding, finishing,
curing etc., complete with initial lead upto 1 km and all lifts.

sqm

Labour Component (including contractor's profit and Overheads)

sqm

Providing cement mortar pointing to coursed rubble face stone masonry 50


mm deep in CM 1 : 3 proportion by volume including raking and cleaning joints,
pressing mortar into joints, cost of all materials, labour, scaffolding, finishing,
curing etc., complete with initial lead upto 1 km and all lifts.

sqm

Labour Component (including contractor's profit and Overheads)

sqm

Itemwise unit rate


for Labour
Component
6

1328.40

2738.60

1328.40

104.20

77.50

97.90

77.50

CONTRACTION JOINT WORKS:

45

Providing 25 mm thick guniting to rock or masonry surface in cement mortar


1 : 3 proportion by weight including cost of all materials, machinery, labour,
raking-out and cleaning joints, scaffolding wherever required and all other
ancillary operations etc., complete with initial lead upto 1 km and all lifts.

sqm

457.10

Abstract of work items_UNit Rates for the year 2014-15

Chapterwise item
S.NO
No.
1

IRR-DAW-4-2

IRR-DAW-4-3

IRR-DAW-4-4

IRR-DAW-4-5

46

47

48

49

IRR-DAW-5-2

IRR-DAW-5-3

IRR-DAW-5-4

3
Labour Component (including contractor's profit and Overheads)
Providing and constructing contraction joints by fixing 16 SWG 60 cm wide
annealed copper sheets in two lines with 8 mm dia steel dowel rods on either side
at one metre interval, forming 125 x 125 mm size groove in between copper
strips for filling asphalt including fixing 15 mm dia two legged G.I pipe with U bend at bottom for circulation of steam at intervals and forming 150 mm dia
formed drain behind water seals including cost of all materials, machinery,
labour, filling asphalt, circulation of steam through pipes etc., complete with all
leads and lifts.
Labour Component (including contractor's profit and Overheads)
Providing and constructing contraction joints by fixing 310 mm wide central
bulb type approved quality PVC water stop in two lines with 8 mm diameter steel
dowel rods on either side at 1m interval, forming 125 x 125 mm size groove in
between two water stops, providing & fixing 15 mm dia two legged G.I pipe with
U-bend at bottom for circulation steam at interval, forming 150 mm diameter
formed drain behind water seals including filling groove with asphalt, circulation
of steam at intervals, cost of all materials, machinery, labour etc., complete with
all leads and lifts.
Labour Component (including contractor's profit and Overheads)
Providing and constructing contraction joints by fixing 16 SWG 60 cm wide
annealed copper sheets in single line with 8 mm dia steel dowel rods on either
side at 1 metre interval including cost of all materials, machinery, labour etc.,
complete with all leads and lifts.
Labour Component (including contractor's profit and Overheads)

Unit

Rate

4
sqm

Rm

15626.50

Rm

Rm

161.80

2480.90

Rm

Rm

106.90

7277.70

Rm

Providing and constructing contraction joints by fixing 23 cm wide central bulb


type PVC water stop in single line supported by 10 mm dia steel dowel rods on
either side at 1 metre interval including cost of all materials, machinery, labour,
valcunising joints etc., complete with all leads and lifts.

Rm

Labour Component (including contractor's profit and Overheads)

Rm

124.50

220.30

99.30

EARTH / ROCKFILL EMBANKMENT WORKS :

IRR-DAW-5

IRR-DAW-5-1

Item description

Itemwise unit rate


for Labour
Component
6
153.40

50

51

52

53

Providing hearting embankment using selected impervious soil from


approved borrow areas in layers of 25 to 30 cm before compaction including
cost of all materials, machinery, labour, all operations such as excavation,
sorting out, transportation, spreading soil in layer of specified thickness,
breaking clods, sectioning, watering, compacting to density control of not less
than 95 percent or as stipulated using Sheep foot roller / Vibratory roller/ 8 to
10 tonne power roller etc., complete with initial lead upto 1 km and all lifts.

cum

Labour Component (including contractor's profit and Overheads)

cum

Providing cut-off trench filling using selected impervious soil from approved
borrow areas in layers of 25 to 30 cm before compaction including cost of all
materials, machinery, labour, all operations such as excavation, sorting out,
transportation, spreading soil to specified thickness, breaking clods, sectioning,
watering, compacting to density control of not less than 95 percent using Sheep
foot roller / Vibratory roller/ 8 to 10 tonne power roller as stipulated etc.,
complete with initial lead upto 1 km and all lifts.

cum

Labour Component (including contractor's profit and Overheads)

cum

Providing casing embankment using semi-pervious soil from approved


borrow areas in layers of 25 to 30 cm before compaction including cost of all
materials, machinery, labour, all other operations such as excavation, sorting
out, transportation, spreading soil in layers of specified thickness, breaking
clods, sectioning, watering, compacting to density control of not less than 95
percent using Sheep foot roller / Vibratory roller/ 8 to 10 tonne power roller
as stipulated etc., complete with initial lead upto 1 km and all lifts.

cum

Labour Component (including contractor's profit and Overheads)

cum

Providing casing embankment using semi-pervious soil available from


excavation in layers of 25 to 30 cm before compaction including cost of all
materials, machinery, labour, all other operations such as re-excavation, sorting
out, transportation, spreading in layers of specified thickness, breaking clods,
sectioning, watering, compacting to specified density control of not less than 95
percent using Sheep foot roller / Vibratory roller/ 8 to 10 tonne power roller
as stipulated etc., complete with initial lead upto 1 km and all lifts.

cum

Labour Component (including contractor's profit and Overheads)

cum

139.20

19.00

149.40

20.70

149.90

20.60

126.00

17.60

Abstract of work items_UNit Rates for the year 2014-15

Chapterwise item
S.NO
No.
1

IRR-DAW-5-4-A
(New Item1 2011-12)

IRR-DAW-5-5

IRR-DAW-5-6

Item description

Unit

Rate

54

Providing casing embankment using semi-pervious soil available from


excavation in layers of 25 to 30 cm before compaction including cost of all
materials, machinery, labour, all other operations such as re-excavation, sorting
out, transportation, spreading in layers of specified thickness, breaking clods,
sectioning, watering, compacting to specified density control of not less than 90
percent using 2Tonne Roller as stipulated etc., complete with initial lead upto
1 km and all lifts. (For Maintenance Works)

cum

86.00

Labour Component (including contractor's profit and Overheads)

cum

Providing homogeneous embankment using soil from approved borrow area


in layers of 25 to 30 cm before compaction including cost of all materials,
machinery, labour, all operations such as excavation, sorting out, transportation,
spreading soil in layer of specified thickness, breaking clods, sectioning,
watering, compacting to density control of not less than 95 percent or as
stipulated using Sheep foot roller / Vibratory roller/ 8 to 10 tonne power
roller etc., complete with initial lead upto 1 km and all lifts.

cum

Labour Component (including contractor's profit and Overheads)

cum

55

56

Providing embankment adjacent to masonry / concrete structures and filling


trial pits using impervious soil from approved borrow areas in layers of 10 to
15 cm and compacting each layer to density control of not less than 95 percent
using pneumatic tampers or by vibratory earth rammers including cost of all
materials, machinery, labour, picking previous layer, spreading soil in layer,
breaking clods, watering etc., complete with initial lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)

IRR-DAW-5-7

IRR-DAW-5-8

IRR-DAW-5-9

57

58

59

IRR-DAW-5-9-A
(New Item4-2012- 60
13)

IRR-DAW-5-10

IRR-DAW-6

61

Providing and constructing rockfill embankment with 300 mm down graded


stones and quarry spalls from approved source including cost of all materials,
machinery, labour, spreading stones and spalls in layers, hand packing,
wedging, finishing the surface to required slopes etc., complete with initial
lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)
Providing and constructing dry rubble rock-toe using rubble and stone chips
from approved source including cost of all materials, machinery, labour, hand
packing rubble and stone chips, finishing top and sides to required slopes etc.,
complete with initial lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)

cum

cum

19.40

258.60

105.90

434.80

96.40

493.20

cum

cum

Note: Useful rubble and stone chips will be issued at dump yard at the issue rate
for usefull rubble /stone chips. Sorting out and breaking charges included in rate
analysis.
Labour Component (including contractor's profit and Overheads)

cum

Providing and laying 30 cm diameter open jointed hume pipes with collars in
rock-toe for drainage including cost of all materials, machinery, labour etc.,
complete with lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)

141.50

cum

Providing and constructing dry rubble rock-toe with rubble and stone chips
from dump yard including cost of all materials, machinery, labour, hand packing
rubble and stone chips, finishing top and sides to required slopes etc., complete
with initial lead upto 1 km and all lifts.

Providing and constructing Dry rock Pitching for Groynes using Un-Coursed
rubble stone of size 300 mm thick and Un-Coursed rubble stone chips from
Quarry to site of work including cost of all materials, Machinery, Labour charge
hand packing Un-Course rubble stone &chips to the designed profile with all
leads and lifts etc
Labour Component (including contractor's profit and Overheads)

17.60

cum

cum

cum

181.50

444.90

125.40

658.90

cum

Rm
Rm

Itemwise unit rate


for Labour
Component
6

125.40

769.00
28.00

FILTER & PITCHING WORKS :

Abstract of work items_UNit Rates for the year 2014-15

Chapterwise item
S.NO
No.
1

IRR-DAW-6-1

IRR-DAW-6-2

IRR-DAW-6-3

IRR-DAW-6-4

Item description

Unit

Rate

62

Providing and constructing 1.20 m internal diameter and average 3 m height


RCC manhole with 60 cm dia. top cover in M-15 grade cement concrete using 20
mm down graded, clean, hard coarse aggregate, 20 cm thick for bed / sides /
top slab / 1.5 m long cut-off wall and 7.5 cm thick for cover including providing
12 mm dia reinforcement bars at 30 cm c / c bothways for bed / sides / cut-off
wall / top slab / rungs and 8 mm dia bars at 15 cm c / c bothways for cover,
excavation for foundation, providing 30 cm dia hume pipe outlet, cost of all
materials, machinery, labour, formwork, scaffolding, batching, mixing, laying,
vibrating, finishing, curing etc., complete with lead upto 1 km and all lifts.(
Cement content : 300 kg/cum , CA : 0.80 cum, Blending Ratioof CA -- 65:35,FA :
0.44 cum, superplasticizer (0.4% by wt. of cement)

Each

44110.40

Labour Component (including contractor's profit and Overheads)

Each

Providing and constructing longitudinal and cross graded filter drains using
sand and 80-20 mm and 20 mm down graded aggregates satisfying specified
filter creteria in layers as per specifications including cost of all materials,
machinery, labour, laying to required slopes, compaction etc. complete with
initial lead upto 50 m and all lifts.

cum

Labour Component (including contractor's profit and Overheads)

cum

Providing and constructing 1.40 m thick vertical or inclined graded filter


media consisting of 20 cm thick sand layers, 25 cm thick 20 mm down
coarse aggregate layers and 50 cm thick 80-20 mm coarse aggregate layer
using approved materials satisfying specified filter creteria as per specifications
including cost of all materials, machinery, labour, laying to required slope,
compaction etc., complete with initial lead upto 50 m and all lifts.

cum

Labour Component (including contractor's profit and Overheads)

cum

63

64

65

IRR-DAW-6-4-A
(New Item2 2011- 66
12)

IRR-DAW-6-5

IRR-DAW-6-6

IRR-DAW-6-7

IRR-DAW-6-8

67

68

69

70

Providing and constructing graded filter media below and behind rock-toe
consisting of 20 cm thick sand, 25 cm thick 20 - 4.75 mm and 40 cm thick 80
- 20 mm size graded coarse aggregates satisfying filter creteria as per
specifications including cost of all materials, labour, machinery, laying to
required slope, compaction etc., complete with initial lead upto 50 m and all
lifts.
Labour Component (including contractor's profit and Overheads)
Providing and constructing graded filter media below and behind rock-toe
consisting of 30 cm thick, 80 - 20 mm size graded coarse aggregates
satisfying filter creteria as per specifications including cost of all materials,
labour, machinery, laying to required slope, compaction etc., complete with
initial lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)
Providing and laying filter media consisting of 2 layers of 250 gsm polypropeline non-woven filter fabric and 400 mm thick 20 mm down graded
coarse aggregate for vertical / inclined and horizontal filter blanket for
embankment including cost of all materials, machinery, labour etc., complete
with lead upto 50 m for aggregate and all leads for fabric and all lifts.

cum

956.60

132.00

1038.80

132.00

988.40

118.60

1134.70

cum

sqm

Labour Component (including contractor's profit and Overheads)

sqm

Providing and constructing 45 cm thick chimney filter using clean approved


sand satisfying filter creteria including cost of all materials, machinery, labour,
compacting etc., complete with initial lead upto 50 m and all lifts.

cum

Labour Component (including contractor's profit and Overheads)

cum

Providing and constructing 90 cm thick transition cum filter media behind


rockfill using approved sand and 80-20 mm and 20 mm down graded
aggregates satisfying the filter creteria in layers of 30 cm thickness each as per
specifications including cost of all materials, machinery, labour, laying each layer
to required slope, compaction etc., complete with initial lead upto 50 m and all
lifts.
Labour Component (including contractor's profit and Overheads)

9462.90

cum

cum

cum

44.60

951.10

51.30

658.10
105.10

1020.20

cum

Providing and constructing 60 cm thick hand packed rough stone revetment


with 65 to 75 cm long through stones at 1.50 m c / c over a backing of 45 cm
thick graded filter media consisting of sand, 10 mm and 40 mm size approved
graded aggregates laid in layers of 15 cm thick each including cost of all
materials, machinery, labour, laying to required slopes, wedging with chips,
finishing etc. complete with initial lead upto 50 m and all lifts.

sqm

Labour Component (including contractor's profit and Overheads)

sqm

Itemwise unit rate


for Labour
Component
6

138.70

860.70

154.60

Abstract of work items_UNit Rates for the year 2014-15

Chapterwise item
S.NO
No.
1

IRR-DAW-6-9

IRR-DAW-6-10

IRR-DAW-6-11

IRR-DAW-6-12

IRR-DAW-6-13

Item description

Unit

Rate

Providing and constructing 60 cm thick hand packed rough stone revetment


with 65 to 75 cm long through stones at 1.50 m c / c over a backing of 60 cm
thick graded filter media consisting of sand, 10 mm and 40 mm size approved
graded aggregates laid in layers of 20 cm thick each including cost of all
materials, machinery, labour, laying to required slopes, wedging with chips,
finishing etc. complete with initial lead upto 50 m and all lifts.

sqm

1025.20

Labour Component (including contractor's profit and Overheads)

sqm

71

72

73

74

75

Providing and constructing 60 cm thick hand packed rough stone riprap over
a backing of 45 cm thick graded filter media consisting of sand, 10 mm and 40
mm size graded approved aggregates laid in layers of 15 cm thick each
including cost of all materials, machinery, labour, laying to required slopes,
wedging with stone chips etc., complete with initial lead upto 50 m and all
lifts.
Labour Component (including contractor's profit and Overheads)

sqm

Labour Component (including contractor's profit and Overheads)

sqm

Providing and constructing 90 cm thick hand packed rough stone riprap over
a backing of 45 cm thick graded filter media consisting of sand, 10 mm and 40
mm size graded approved aggregates laid in layers of 15 cm thick each including
cost of all materials, machinery, labour, laying to required slopes, wedging with
stone chips etc., complete with initial lead upto 50 m and all lifts.

sqm

Labour Component (including contractor's profit and Overheads)

sqm

Providing and laying Hariyala or other approved quality turfing sods for the
slopes of earthen embankments over 20 mm thick sand backing including cost of
all materials, machinery, labour including preparing surface, spreading sand,
watering for 15 days etc., complete with initial lead upto 1 km and all lifts.

sqm

Labour Component (including contractor's profit and Overheads)

sqm

TUNNEL AND ALLIED WORKS

IRR-TAW-1

EXCAVATION :

IRR-TAW-1-2

IRR-TAW-1-3

IRR-TAW-1-4

76

77

78

79

174.80

803.40

sqm

Providing and constructing 75 cm thick hand packed rough stone riprap over
a backing of 45 cm thick graded filter media consisting of sand, 10 mm and 40
mm size graded approved aggregates laid in layers of 15 cm thick each including
cost of all materials, machinery, labour, laying to required slopes, wedging with
stone chips, etc., complete with initial lead upto 50 m and all lifts.

Chapter II
IRR-TAW

IRR-TAW-1-1

sqm

Excavation for adit by tunnelling methods in all types of rock including cost
of all materials, machinery, labour, scaling excavated surface, ventilation,
lighting, drainage, removing and hauling the excavated muck outside adit upto
specified dump area and all other ancillary operations etc., complete with
initial lead upto 50 m and all lifts.

cum

Labour Component (including contractor's profit and Overheads)

cum

Excavation for vertical / inclined shaft in all types of soft / hard rock
including cost of all materials, machinery, labour, shoring, strutting, scaling
excavated surface, ventilation, lighting, drainage, removing and hauling
excavated muck outside shaft upto specified dump area and all other ancillary
operations etc., complete with initial lead upto 1 km and all lifts.

cum

Labour Component (including contractor's profit and Overheads)

cum

Excavation for tunnel by tunnelling methods in rock not requiring supports


including cost of all materials,machinery, labour, scaling excavated surface,
removing under-cuts, ventilation, lighting, drainage, removing and hauling the
excavated muck outside tunnel upto specified dump area and all other ancillary
operations etc., complete with initial lead upto 1 km and all lifts.

cum

Labour Component (including contractor's profit and Overheads)

cum

Excavation for tunnel by tunnelling methods including excavation for


supports in all types of soil / rock strata requiring supports ( excluding cost
of providing supports ) including cost of all other materials, machinery, labour,
scaling excavated surface, ventilation, lighting, drainage, removing and hauling
the excavated muck outside tunnel upto specified dump area and all other
ancillary operations etc., complete with initial lead upto 1 km and all lifts.

cum

Itemwise unit rate


for Labour
Component
6

118.10

876.10

128.70

961.50

150.00

99.80

59.50

1713.00

551.50

2237.90

1104.70

1751.70

543.80

1803.30

10

Abstract of work items_UNit Rates for the year 2014-15

Chapterwise item
S.NO
No.
1

IRR-TAW-1-5

80

Item description
3
Labour Component (including contractor's profit and Overheads)
Excavation for tunnel by heading and benching tunnelling methods including
excavation for supports in all types of soil / rock strata requiring supports (
excluding cost of providing supports ) for roof before benching including cost of
all other materials, machinery, labour, scaling excavated surface, ventilation,
lighting, drainage removing and hauling excavated muck outside tunnel upto
specified dump area and all other ancillary operations etc., complete with initial
lead upto 1 km and all lifts.
NOTE: Where mucking is to be carried out through shaft using winch and
mucking tub system increase the basic rates for items 3, 4 & 5 by 8 percent.

Labour Component (including contractor's profit and Overheads)

IRR-TAW-1-6

81

IRR-TAW-2-2

82

83

IRR-TAW-2-3
(new Item4 2010- 84
11)

IRR-TAW-3-2

IRR-TAW-3-3

Dewatering tunnel by pumping out water collected by natural drainage inside


tunnel including providing sump wherever necessary, cost of all materials,
machinery, labour, drainage, lighting, ventilation and all other ancillary
operations etc., complete.
Labour Component (including contractor's profit and Overheads)
Providing 25 mm thick guniting to sides and arch of tunnel in cement mortar
1 : 3 proportion by weight including cost of all materials, machinery, labour,
ventilation, lighting, drainage and all other ancillary operations etc., complete
with lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)

cum

1848.30

cum

cum

603.10

362.60

cum

Kwhr

84.10

23.40

Kwhr

sqm

7.90

567.40

sqm

Shortcreting in two layers (each layer+38 mm thickness) for slabs duly


fixing chain weld wire mesh 100 x 100x5 mm in between the two layers including
cost and conveyance of all materials, labour charges, all heads, lifts, centering,
scaffolding, machine mixing, laying concrete with shortcrete machine etc.
complete as per specification and as directed by Engineer-in-Charge

sqm

Labour Component (including contractor's profit and Overheads)

sqm

85

86

87

Providing and fixing 25 mm diameter steel rock bolts with mechanical /


wedge type anchorage including drilling 35 mm dia holes, providing 15 cm long
20 mm thick steel tapered wedge, 10 mm thick plate washers and nuts,
tightening bolt by torque wrench, cost of all materials, machinery, labour,
ventilation, lighting, drainage and all other ancillary operations etc., complete
with lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)
Providing and fixing 25 mm diameter steel rock bolts with resin bond cement
capsule anchorage including drilling 35 mm dia holes, inserting grout capsule,
driving bolt,fixing 10 mm thick plate washers and nuts and tightening the same
by torque wrench after hardening of cement grout, cost of all materials,
machinery, labour, ventilation, lighting, drainage and other ancillary operations
etc., complete with lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)
Providing, fabricating and fixing in position permanent structural steel
supports as per details including cost of all materials, machinery, labour,
cutting, bending, welding, grinding, lighting, ventilation, drainage and all other
ancillary operations etc., complete with initial lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)

IRR-TAW-3-4

4
cum

174.00

1344.10

174.00

TEMPORARY & PERMANENT SUPPORTS :

IRR-TAW-3

IRR-TAW-3-1

Rate

DEWATERING & GUNITING WORKS :

IRR-TAW-2

IRR-TAW-2-1

Removing and hauling muck overfallen due to natural causes such as


geological faults etc., out of tunnel including breaking large fragments by blasting
if necessary and disposing off the same in specified dump area or as directed
including cost of all materials, machinery, labour, ventilation, drainage, lighting
and all other ancillary operations etc., complete with initial lead upto 1 km and
all lifts.
Labour Component (including contractor's profit and Overheads)

Unit

Itemwise unit rate


for Labour
Component
6
561.30

88

Providing, fabricating and fixing in position temperary structural steel


supports as per details and dismantling the same before concreting including
cost of all materials, machinery, labour, cutting, bending, welding, grinding,
ventilation, lighting, drainage and all other ancillary operations etc.,complete
with initial lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)

Rm

1116.60

Rm

Rm

294.50

1069.00

Rm

tonne

271.30

95183.90

tonne

tonne

tonne

15917.60

22295.80

7944.70

11

Abstract of work items_UNit Rates for the year 2014-15

Chapterwise item
S.NO
No.
1

IRR-TAW-3-5

89

IRR-TAW-5-2

IRR-TAW-5-3

IRR-TAW-5-4

90

cum

32859.50

Providing and fixing hard variety cut jungle wood for lagging / blocking
locations in tunnel wherever required including cost of all materials, machinery,
labour, fixing in position, lighting, ventilation, drainage etc complete with all
leads and lifts.
Labour Component (including contractor's profit and Overheads)

cum

1412.00

Providing and constructing un-coursed rubble stone masonry with approved


stones from tunnel excavated muck in cement mortar 1 : 6 proportion for
backfilling over cuts / slips on tunnel sides due to geological faults etc., including
cost of all materials, machinery, labour, cleaning,scaffolding, packing mortar,
wedging stone chips, curing, ventilation, lighting, drainage complete with lead
upto 1 km and all lifts.(cement content : 95 kg/cum of masonry, Rubble stones
: 0.83 cum, Stone chips : 0.13 cum,FA : 0.40 cum)

cum

Labour Component (including contractor's profit and Overheads)

cum

2064.80

740.30

REINFORCEMENT & CONCRETE WORKS :

91

92

93

94

Providing, fabricating and placing in position reinforcement steel for tunnel


RCC works including cleaning, straightening, cutting, bending, hooking, lapping
/ welding joints wherever required, tying with 1.25 mm dia.soft annealed steel
wire, including cost of all materials, labour, machinery, ventilation, lighting,
drainage etc.,complete with initial lead upto 1 km and all lifts.

tonne

Labour Component (including contractor's profit and Overheads)

tonne

Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength
not less than 10 N / sq mm ) grade cement concrete using 40 mm down size
approved, clean, hard, graded aggregates crushed from tunnel excavated muck
for filling and levelling over-cuts in bed due to geological faults etc., including
cost of all materials, machinery, labour, cleaning bed, batching, mixing,
conveying and laying, levelling, compacting, finishing, curing, lighting,
ventilation, drainage etc., complete with initial lead upto 1 km and all lifts. (
Cement content : 220 kg / cum, CA : 0.90cum, Blending Ratio of CA--50:30:20,
FA : 0.40 cum, Superplasticizer 0.4% by wt. of cement)

cum

Labour Component (including contractor's profit and Overheads)

cum

Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength
not less than 20 N / sqmm ) grade cement concrete using 40 mm and down size
approved clean, hard, graded aggregates crushed from tunnel muck for kerb and
bed lining including cost of all materials, machinery, labour, formwork, batching,
mixing, conveying upto placing point in agitator cars, placing in position,
levelling, vibrating, finishing, curing, ventilation, lighting, drainage and all other
ancillary operations etc., complete with lead upto 1 km and all lifts. ( Cement
content 330 kg / cum for use of super plasticiser(0.4% by wt. of cement),CA :
0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

cum

Labour Component (including contractor's profit and Overheads)

cum

Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength
not less than 20 N / sqmm ) grade cement concrete using 40 mm and down size
approved clean, hard, graded aggregates crushed from tunnel muck for sides
and arch lining including cost of all materials, machinery, labour, formwork,
batching, mixing, conveying upto placing point in agitator cars, placing in
position, levelling, vibrating, finishing, curing, ventilation, lighting, drainage and
all other ancillary operations etc., complete with lead upto 1 km and all lifts. (
Cement content 330 kg / cum for use of super plasticiser(0.4% by wt. of
cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

cum

Labour Component (including contractor's profit and Overheads)

cum

73182.60

9661.50

5064.10

738.30

6099.40

920.00

#REF!

#REF!

DRILLING & GROUTING WORKS :

IRR-TAW-6

IRR-TAW-6-1

Rate

MASONRY WORKS :

IRR-TAW-5

IRR-TAW-5-1

Unit

IRR-TAW-4

IRR-TAW-4-1

Item description

Itemwise unit rate


for Labour
Component
6

95

Drilling 32 mm diameter grout holes in concrete / rock by percussion


drilling using jack hammer or stooper drills as directed to specified depth for
consolidation / contact grouting including cost of all materials, machinery, labour,
cleaning holes, ventilation, lighting, drainage and all other ancillary operations
etc., complete.
Labour Component (including contractor's profit and Overheads)

Rm

Rm

389.00

141.60

12

Abstract of work items_UNit Rates for the year 2014-15

Chapterwise item
S.NO
No.
1

IRR-TAW-6-2

96

Item description

Unit

Rate

tonne

9052.90

Grouting cement slurry in grout holes under specified pressure for


consolidation / contact grouting including cost of all materials, machinery,
labour, redrilling wherever necessary, ventilation,lighting, drainage and other
ancillary operations etc., complete with lead upto 1 km and all lifts.

Labour Component (including contractor's profit and Overheads)

IRR-TAW-6-3

97

Chapter III
IRR-CAW

IRR-CAW-1-2

98

99

cum

Excavation in all kinds of soil including boulders upto 0.30 m dia for field
channels, seating of embankment for field channels etc., including dressing of
bed and sides to required profile, cost of all materials, machinery, labour, placing
the excavated stuff for formation of service road / embankment as directed etc.,
complete with lead upto 10 m and lift upto 3 m.

cum

Labour Component (including contractor's profit and Overheads)

cum

Excavation in ordinary rock (including HDR) without blasting including


boulders above 0.30 m upto 0.6 m dia. for canals, seating of embankment, filter
drain / catch water drains etc., including dressing of bed and sides to required
100
level and profile, cost of all materials, machinery, labour, placing the excavated
soft rock neatly in dump area or for formation of service road as directed etc.,
complete with lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)

IRR-CAW-1-4

Excavation in ordinary rock (including HDR) without blasting including


boulders above 0.3 m upto 0.60 m dia. for field channels, seating of
embankment for field channels etc., including dressing of bed and sides to
required profile, cost of all materials, machinery, labour, placing the excavated
101
stuff for formation of service road as directed etc.,complete with lead upto 10 m
and lift upto 3 m.
(Machinery excavation and manual conveyance)
Labour Component (including contractor's profit and Overheads)

IRR-CAW-1-5

360.70

Rm

EXCAVATION WORKS :
Excavation in all kinds of soil including boulders upto 0.3 m diameter for canal,
seating of embankment, filter drains / catch water drains etc., including dressing
bed and sides to required level and profile, cost of all materials, machinery,
labour, placing the excavated soil neatly in dump area or for the formation of
service road / embankment as directed etc., complete with initial lead upto 1
km and all lifts.
Labour Component (including contractor's profit and Overheads)

(Machinery excavation and manual conveyance)

IRR-CAW-1-3

Rm

2173.80

58.50

CANAL AND ALLIED WORKS

IRR-CAW-1

IRR-CAW-1-1

Drilling 75 mm diameter drainage holes vertical or inclined in rock / concrete


in tunnel by percussion drilling using waggon drill or other suitable drilling
equipment including cost of all materials, machinery, labour, ventilation, lighting,
drainage etc., complete.
Labour Component (including contractor's profit and Overheads)

tonne

Itemwise unit rate


for Labour
Component
6

Excavation in hard rock (including F&F rock) requiring blasting including


boulders above 0.6 m upto 1.2 m dia. for canals, seating of embankment, filter
drain / catch water drains etc., including dressing bed and sides to required level
102
and profile, cost of all materials, machinery, labour, placing the excavated rock
in dump area or for formation of service road as directed etc., complete with
lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)

IRR-CAW-1-6 (a) 103

94.00

cum

cum

22.50

49.60

18.10

127.30

cum

cum

33.30

82.10

cum

cum

30.00

194.80

cum

Excavation in hard rock of all toughness by blasting including boulders above


1.2 m dia. for canals, seating of embankment, filter drain / catch water drains
etc., including levelling the bed by removing all projections by hammering /
chiselling, cost of all materials, machinery, labour, placing the excavated rock
neatly in approved dump area and levelling the same as directed etc., complete
with initial lead upto 1 km and all lifts.

cum

i ) The rate under this item shall be adopted for canals designed for carrying
capacity of less than 15 cumecs or where the average depth excavation in hard
rock is less than 3 m.
ii ) The rate includes levelling canal bed by hammering / chiselling all rock
projections wherever required.
Labour Component (including contractor's profit and Overheads)

cum

60.40

484.80

129.70

13

Abstract of work items_UNit Rates for the year 2014-15

Chapterwise item
S.NO
No.
1

Item description

Unit

Rate

cum

604.20

Excavation in hard rock of all toughness including boulders above 1.2 m dia.
by approved controlled blasting methods for canals, cut-off trench of
embankment, filter / catch-water drains etc., including controlling fly-rock by
muffling arrangements such as placing 50 x 50 mm opening chain link mesh or
waste tyres and sand bags, monitoring ground vibrations at specified locations,
costof all materials, machinery, labour, placing excavated rock neatly in
approved dump area or other place as directed etc., complete with lead upto 1
IRR-CAW-1-7 (b) 104
km and all lifts.
i) The rate under this item shall be adopted for canals designed for carrying
capacity of less than 15 cumecs or where the average depth excavation in hard
rock is less than 3 m.
ii ) The rate under this item shall be adopted where the control of fly-rock and
ground vibrations is required.
Labour Component (including contractor's profit and Overheads)
Excavation in hard rock of all toughness including boulders above 1.2 m dia.
for dressing canal sides neatly on either side to required profile by line drilling
and smooth blasting including removing under-cuts by chiselling / hammering,
placing the excavated rock neatly in dump area or other place as directed, cost
of all materials, machinery, labour etc., complete with lead upto 1 km and all
lifts.
i) For excavation of canal below free board level combination of normal
controlled blasting and line drilling and smooth blasting shall be adopted to
obtain neat side slopes. For the purpose of payment 1 m width of excavation on
IRR-CAW-1-8( c) 105
either side shall be treated as excavation by line drilling and smooth blasting and
remaining portion shall be treated as excavation by normal / controlled blasting
as the case may be.
ii ) The rate under this item shall be adopted for canals designed for carrying
capacity of less than 15 cumecs or where the average depth of excavation in
hard rock is less than 3 m.
iii ) The rate includes controlling fly-rock wherever required.
iv ) The rate under this item shall be paid only on ascertaining that the
excavated face has come off neatly as per specifications or atleast 50 percent of
Labour Component (including contractor's profit and Overheads)

cum

cum

Itemwise unit rate


for Labour
Component
6

128.10

1060.90

cum

341.90

Excavation in hard rock by blasting including boulders above 1.2 m dia. for
canals, seating embankment etc., including levelling bed by removing all
projections by hammering / chiselling, cost of all materials, machinery, labour,
placing the excavated rock neatly in approved dump area and levelling the same
as directed etc.,complete with initial lead upto 1 km and all lifts.
IRR-CAW-1-9(a)

106

cum

298.50

i ) The rate under this item shall be adopted for canals designed for carrying
capacity of more than 15 cumecs or where the average depth of excavation in
hard rock is more than 3 m.
ii ) The rate includes levelling canal bed by hammering /chiselling all rock
projections wherever required.
Labour Component (including contractor's profit and Overheads)

IRR-CAW-110(b)

Excavation in hard rock of all toughness including boulders above 1.2 m dia.
by approved controlled blasting methods for canals, cut-off trench of
embankment etc., including controlling fly-rock by muffling arrangements such
as placing 50 x 50 mm opening chain link mesh or waste tyres and sand bags,
monitoring ground vibrations at specified locations, cost of all materials,
machinery, labour, placing excavated rock neatly in approved dump area or
107 other place as directed etc., complete with lead upto 1 km and all lifts.

cum

cum

40.80

451.50

i ) The rate under this item shall be adopted for canals designed for carrying
capacity of more than 15 cumecs or where the average depth of excavation in
hard rock is more than 3 m.
ii ) The rate under this item shall be adopted where the control of fly-rock and
ground vibrations is required.
Labour Component (including contractor's profit and Overheads)

cum

46.70

14

Abstract of work items_UNit Rates for the year 2014-15

Chapterwise item
S.NO
No.
1

IRR-CAW-111(c)

IRR-CAW-2

IRR-CAW-2-1

Item description

3
Excavation in hard rock of all toughness including boulders above 1.2 m dia.
for dressing canal sides neatly on either side to required profile by line drilling
and smooth blasting including removing under-cuts by chiselling / hammering,
placing the excavated rock neatly in dump area or other place as directed, cost
of all materials, machinery, labour etc., complete with lead upto 1 km and all
lifts.
i ) For excavation of canal below free board level combination of normal
controlled blasting and line drilling and smooth blasting shall be adopted to
obtain neat side slopes. For the purpose of payment 1 m width of excavation on
108
either side shall be treated as excavation by line drilling and smooth blasting and
remaining portion shall be treated as excavation by normal / controlled blasting
as the case may be.
ii ) The rate under this item shall be adopted for canals designed for carrying
capacity of more than 15 cumecs or where the average depth of excavation in
hard rock is more than 3 m.
iii ) The rate includes controlling fly-rock wherever required.
iv ) The rate under this item shall be paid only on ascertaining that the
excavated face has come off neatly as per specifications or atleast 50 percent
Labour Component (including contractor's profit and Overheads)

Providing impervious hearting embankment with selected soil from approved


borrow areas in layers of 25 cm before compaction including cost of all
materials, machinery, labour, all operations such as excavation, sorting out,
109 transporting, spreading in layer of specified thickness, breaking clods,
sectioning, watering, compacting each layer to density control of not less than
98 percent or as stipulated by Sheep foot roller / Vibratory roller/ 8 to 10
tonne power roller etc., complete with initial lead upto 1 km and all lifts.

Providing impervious hearting embankment with selected soil from approved


borrow areas in layers of 25 cm before compaction including cost of all
materials, machinery, labour, all operations such as excavation, sorting out,
110 transporting, spreading in layer of specified thickness, breaking clods,
sectioning, watering, compacting each layer to density control of not less than
95 percent or as stipulated by Sheep foot roller / Vibratory roller/ 8 to 10
tonne power roller etc., complete with initial lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)

IRR-CAW-2-3

Providing semi-pervious / pervious casing embankment using soil from


approved borrow area in layers of 25 cm before compaction including cost of
all materials, machinery, labour, all operations such as excavation, sortingout,
111 transporting, spreading in layer of specified thickness, breaking clods,
sectioning, watering, compacting to density control of not less than 98 percent
or as stipulated by Sheep foot roller / Vibratory roller/ 8 to 10 tonne power
roller etc., complete with initial lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)

IRR-CAW-2-4

Providing semi-pervious / pervious casing embankment using soil from


approved borrow area in layers of 25cm before compaction including cost of
all materials, machinery, labour, all operations such as excavation, sortingout,
112 transporting, spreading in layer of specified thickness, breaking clods,
sectioning, watering, compacting to density control of not less than 95 percent
or as stipulated by Sheep foot roller / Vibratory roller/ 8 to 10 tonne power
roller etc., complete with initial lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)

IRR-CAW-2-5

Rate

cum

753.80

cum

105.30

EMBANKMENT WORKS USING BORROW AREA SOIL :

Labour Component (including contractor's profit and Overheads)

IRR-CAW-2-2

Unit

Itemwise unit rate


for Labour
Component
6

Providing semi-pervious / pervious casing embankment using soil from


approved borrow area in layers of 25cm before compaction including cost of
all materials, machinery, labour, all operations such as excavation, sortingout,
transporting, spreading in layer of specified thickness, breaking clods,
113
sectioning, compacting each layer without watering to density control of not
less than 95 percent or as stipulated by Sheep foot roller / Vibratory roller/ 8
to 10 tonne power roller etc., complete with initial lead upto 1 km and all
lifts.
Labour Component (including contractor's profit and Overheads)

cum

198.00

cum

cum

30.70

191.20

cum

cum

30.10

197.60

cum

cum

30.70

193.20

cum

cum

cum

32.30

180.00

27.90

15

Abstract of work items_UNit Rates for the year 2014-15

Chapterwise item
S.NO
No.
1

IRR-CAW-2-6

Item description

Unit

Rate

cum

171.10

Providing hearting / casing embankment with homogeneous soil from


approved borrow areas in layers of 25 cm before compaction including cost of
all materials, machinery, labour, all operations such as excavation, sorting out,
114 transporting, spreading in layer of specified thickness, breaking clods,
sectioning, watering, compacting each layer to density control of not less than
98 percent or as stipulated by Sheep foot roller / Vibratory roller/ 8 to 10
tonne power roller etc., complete with initial lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)

IRR-CAW-2-7

Providing hearting / casing embankment with homogeneous soil from


approved borrow areas in layers of 25 cm before compaction including cost of
all materials, machinery, labour, all operations such as excavation, sorting out,
115 transporting, spreading in layer of specified thickness, breaking clods,
sectioning, watering, compacting each layer to density control of not less than
95 percent or as stipulated by Sheep foot roller / Vibratory roller/ 8 to 10
tonne power roller etc., complete with initial lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)

IRR-CAW-2-8

Providing casing embankment using homogeneous soil from approved


borrow area in layers of 25 cm before compaction including cost of all materials,
machinery, labour, all operations such as excavation, sortingout, transporting,
116 spreading in layer of specified thickness, breaking clods, sectioning, compacting
each layer without watering to density control of not less than 95 percent or as
stipulated by Sheep foot roller / Vibratory roller/ 8 to 10 tonne power roller
etc., complete with initial lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)

IRR-CAW-3

IRR-CAW-3-1

IRR-CAW-3-2

IRR-CAW-3-3

cum

25.30

165.10

cum

cum

24.90

155.00

cum

22.80

EMBANKMENT WORKS USING DUMP AREA SOIL :


Providing impervious hearting embankment with soil from approved dump
areas in layers of 25 cm before compaction including cost of all materials,
machinery, labour, all operations such as re-excavation, sorting out,
transporting, spreading in layer of specified thickness, breaking clods,
117
sectioning, watering, compacting each layer to achieve density control of not
less than 98 percent or as stipulated by Sheep foot roller / Vibratory roller/ 8
to 10 tonne power roller etc.,complete with initial lead upto 1 km and all
lifts.
Labour Component (including contractor's profit and Overheads)
Providing impervious hearting embankment with soil from approved dump
areas in layers of 25 cm before compaction including cost of all materials,
machinery, labour, all operations such as re-excavation, sorting out,
transporting, spreading in layer of specified thickness, breaking clods,
118
sectioning, watering, compacting each layer to achieve density control of not
less than 95 percent or as stipulated by Sheep foot roller / Vibratory roller/ 8
to 10 tonne power roller etc.,complete with initial lead upto 1 km and all
lifts.
Labour Component (including contractor's profit and Overheads)
Providing semi-pervious / pervious casing embankment using soil from
approved dump area in layers of 25 cm before compaction including cost of all
materials, machinery, labour, all operations such as re-excavation, sorting out,
119 transporting, spreading in layer of specified thickness, breaking clods,
sectioning, watering, compacting each layer to density control of not less than
98 percent or as stipulated by Sheep foot roller / Vibratory roller/ 8 to 10
tonne power roller etc., complete with initial lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)

IRR-CAW-3-4

cum

Itemwise unit rate


for Labour
Component
6

Providing semi-pervious / pervious casing embankment using soil from


approved dump area in layers of 25 cm before compaction including cost of all
materials, machinery, labour, all operations such as re-excavation, sorting out,
120 transporting, spreading in layer of specified thickness, breaking clods,
sectioning, watering, compacting each layer to density control of not less than
95 percent or as stipulated by Sheep foot roller / Vibratory roller/ 8 to 10
tonne power roller etc., complete with initial lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)

cum

150.10

cum

cum

23.50

144.80

cum

cum

23.10

145.80

cum

cum

cum

22.80

140.40

22.30

16

Abstract of work items_UNit Rates for the year 2014-15

Chapterwise item
S.NO
No.
1

IRR-CAW-3-5

IRR-CAW-4

IRR-CAW-4-1

Item description

3
Providing semi-pervious / pervious casing embankment using soil from
approved dump area in layers of 25 cm before compaction including cost of
all materials, machinery, labour, all operations such as re-excavation, sorting
out, transporting, spreading in layer of specified thickness, breaking clods,
121
sectioning, compacting each layer without watering to density control of not
less than 95 percent or as stipulated by Sheep foot roller / Vibratory roller/ 8
to 10 tonne power roller etc., complete with initial lead upto 1 km and all
lifts.
Labour Component (including contractor's profit and Overheads)

Providing impervious hearting embankment with soil collected in


embankment area in heaps as part of disposal of excavated soil from canal
including cost of all materials,machinery, labour, all operations such as
122 sortingout, spreading in layer of 25 cm before compaction, breaking
clods,sectioning, watering and compacting each layer to density control of not
less than 98 percent or as stipulated by Sheep foot roller / Vibratory roller/ 8
to 10 tonne power roller etc., complete with lead upto 1 km for water.

Providing impervious hearting embankment with soil collected in


embankment area in heaps as part of disposal of excavated soil from canal
including cost of all materials,machinery, labour, all operations such as
123 sortingout, spreading in layer of 25 cm before compaction, breaking
clods,sectioning, watering and compacting each layer to density control of not
less than 95 percent or as stipulated by Sheep foot roller / Vibratory roller/ 8
to 10 tonne power roller etc., complete with lead upto 1 km for water.
Labour Component (including contractor's profit and Overheads)

IRR-CAW-4-3

Providing semi-pervious / pervious casing hearting embankment using soil


collected in heaps in embankment area as part of disposal of excavated soil from
canal including cost of all materials, machinery, labour, all operations such as
124 sorting-out, spreading in layers of 25 cm before compaction, breaking clods,
sectioning, watering and compacting each layer to density control of not less
than 98 percent or as stipulated by Sheep foot roller / Vibratory roller/ 8 to 10
tonne power roller etc., complete with lead upto 1 km for water.
Labour Component (including contractor's profit and Overheads)

IRR-CAW-4-4

Providing semi-pervious / pervious casing embankment using soil collected in


heaps in embankment area as part of disposal of excavated soil from canal
including cost of all materials, machinery, labour, all operations such as sorting125 out, spreading in layers of 25 cm before compaction, breaking clods,
sectioning, watering and compacting each layer to density control of not less
than 95 percent or as stipulated by Sheep foot roller / Vibratory roller/ 8 to 10
tonne power roller etc., complete with lead upto 1 km for water.
Labour Component (including contractor's profit and Overheads)

IRR-CAW-4-5

Providing semi-pervious / pervious casing embankment using soil collected in


heaps in embankment area as part of disposal of excavated soil from canal
including cost of all materials, machinery, labour, all operations such as sorting126 out, spreading in layers of 25 cm before compaction, breaking clods, sectioning
and compacting each layer without watering to density control of not less than
95 percent or as stipulated by Sheep foot roller / Vibratory roller/ 8 to 10
tonne power roller etc., complete.
Labour Component (including contractor's profit and Overheads)

IRR-CAW-4-6

Rate

cum

131.50

cum

20.50

EMBANKMENT WORKS USING EXCAVATED SOIL :

Labour Component (including contractor's profit and Overheads)

IRR-CAW-4-2

Unit

Itemwise unit rate


for Labour
Component
6

Providing compacted embankment for field irrigation channels with gravely


soil from approved borrow area including sorting out, spreading in layers of 15
cm thickness, breaking clods, watering, compacting, dressing sides to required
127
slopes etc.,complete with lead upto 50 m and all lifts.

cum

67.30

cum

cum

9.50

61.90

cum

cum

9.70

67.30

cum

cum

9.50

61.90

cum

cum

9.70

51.60

cum

cum

7.00

266.80

( manual work with water pump)


Labour Component (including contractor's profit and Overheads)
IRR-CAW-5

IRR-CAW-5-1

cum

262.40

FOUNDATION FILLING WORKS :


Providing rubble and sand filling in layers of 22.5 to 30 cm including cost of all
128 materials, machinery, labour, watering, ramming etc., complete with initial lead
upto 50 m and all lifts.

cum

653.00

17

Abstract of work items_UNit Rates for the year 2014-15

Chapterwise item
S.NO
No.
1

IRR-CAW-5-2

IRR-CAW-5-3

IRR-CAW-5-3-A
(New Item 3 2011-12)

IRR-CAW-5-4

IRR-CAW-5-5

IRR-CAW-5-6

IRR-CAW-5-7

IRR-CAW-5-8

IRR-CAW-5-9

IRR-CAW-510(a)

Item description
3
Labour Component (including contractor's profit and Overheads)

Providing rubble and Murum filling in layers of 22.5 to 30 cm including cost of


129 all materials, machinery, labour, watering, ramming etc., complete with initial
lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)
Providing and laying 25 cm thick sand blanket below embankment including
130 cost of all materials, machinery, labour, spreading to specified thickness etc.,
complete with initial lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)
Providing and laying sand blanket below embankment including cost of all
131 materials, machinery, labour, spreading to specified thickness etc., complete
with initial lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)

Rate

4
cum

cum

545.80

cum

sqm

134.50

114.30

sqm

cum

16.90

457.10

cum

Providing and constructing dry rubble rock-toe using rubble and stone chips
from approved source including cost of all materials, machinery, labour, hand
132
packing rubble and stone chips, finishing top and sides to required slopes etc.,
complete with initial lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)
Providing and constructing longitudinal and cross graded filter drains using
sand and 20 mm down graded aggregates satisfying specified filter creteria in
133 layers as per specifications including cost of all materials, machinery, labour,
laying to required slopes, compaction etc., complete with initial lead upto 50 m
and all lifts.
Labour Component (including contractor's profit and Overheads)

cum

cum

133

Rm

Providing and constructing 0.50 m thick vertical or inclined graded filter


media consisting of 15 cm thick sand layers and 20 cm thick 20 mm down coarse
aggregate layer using approved materials satisfying specified filter creteria as
136
per specifications including cost of all materials, machinery, labour, laying to
required slope, compaction etc., complete with initial lead upto 50 m and all
lifts.
Labour Component (including contractor's profit and Overheads)
Providing and constructing graded filter media below and behind rock-toe
consisting of 20 cm thick sand, 15 cm thick 20 mm down and 15 cm thick 40 mm
down size graded coarse aggregates satisfying filter creteria behind rock-toe
and 15 cm thick sand, 20 cm thick 20 mm down coarse aggregate and 65 cm
137
thick 40 mm down size coarse aggregate satisfying filter creiteria below rock-toe
as per specifications including cost of all materials, machinery, labour, laying to
required slope, compaction etc., complete with initial lead upto 50 m and all
lifts.
Labour Component (including contractor's profit and Overheads)
Providing and laying filter media consisting of 2 layers of poly-propeline
nonwoven filter fabric and 200 mm thick 20 mm down graded coarse aggregate
for embankment including cost of all materials, machinery, labour, forming toe
138 drain etc., complete with lead upto 50 m for aggregate and all leads for fabric
and all lifts.

Providing and laying filter media consisting of 2 layers of poly-propeline


nonwoven filter fabric and 200 mm thick 20 mm down graded coarse aggregate
for embankment including cost of all materials, machinery, labour, forming toe
139 drain etc., complete with lead upto 50 m for aggregate and all leads for fabric
and all lifts.

517.20
95.60

827.60

cum

Rm

Laying and fixing of 100 mm Dia 300 mm long precast porus CC plugs in bed
and sides using 1.181 Kgs of cement per each using 20 mm HG metal and
135
placing in local filters of size 600x600x750 mm in size including excavation of
drains and Cost of procuring of all materials
Labour Component (including contractor's profit and Overheads)

67.30

cum

Laying Longitudinal Drains and Transverse drains of Size 600 x600 x750 mm
134 in Bed and filling with 12 mm to 40 mm HG machine Crushed metal and sand in
bed including excavation of drains and Cost of procuring of all materials

Using 200 gsm filter fabric.


Labour Component (including contractor's profit and Overheads)

IRR-CAW-511(b)

Unit

one plug

125.30

407.60
23.80

336.00

one plug

cum

100.90

954.90

cum

cum

125.30

1159.30

cum

sqm

117.10

600.60

sqm

sqm

Itemwise unit rate


for Labour
Component
6
134.50

27.80

653.20

Using 250 gsm filter fabric.

18

Abstract of work items_UNit Rates for the year 2014-15

Chapterwise item
S.NO
No.
1

IRR-CAW-6

IRR-CAW-6-1

IRR-CAW-6-2

Item description
3
Labour Component (including contractor's profit and Overheads)

IRR-CAW-7-1

IRR-CAW-7-2

IRR-CAW-7-3

IRR-CAW-7-4

Providing and constructing rockfill casing to canal embankment with graded


stones and spalls from approved quarry including cost of all materials,
140 machinery, labour, spreading stones and spalls in layers, hand packing,
wedging, finishing surface to required slopes etc., complete with initial lead
upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)

Providing and constructing rockfill casing to canal embankment with graded


stones and spalls available in dump yard including cost of all materials,
machinery, labour, spreading stones and spalls in layers, hand packing,
141
wedging, finishing surface to required slopes etc., complete with initial lead
upto 50 m and all lifts.

Providing cohesive non-swelling ( CNS ) soil lining to canals using soil from
approved borrow area including spreading soil in layers of thickness not
142 more than 15 cm, breaking clods, watering, compacting to density control of not
less than 98 percent or as stipulated, dressing to required profile etc., complete
with initial lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)
Providing cohesive non-swelling ( CNS ) soil lining to canals using soil from
approved borrow area including spreading soil in layers of thickness not
143 more than 15 cm, breaking clods, watering, compacting to density control of not
less than 95 percent or as stipulated, dressing to required profile etc., complete
with initial lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)
Providing cohesive non-swelling ( CNS ) soil lining to canal using soil
collected in heaps along the edge of canal requiring CNS soil lining as part
of the disposal of excavated soil from canal excavation in CNS soil reach
144 including spreading in layers of thickness not more than 15 cm, breaking clods,
watering, compacting to density control of not less than 95 percent or as
stipulated, dressing to required profile etc., complete with lead upto upto 50 m
and all lifts.
Labour Component (including contractor's profit and Overheads)
Providing and fixing 20 x 20 x 75 cm size top surface neatly dressed canal
145 bed level stones including cost of all materials, labour, excavation, fixing in
position to correct level etc., complete with lead upto 50 m and all lifts.

Providing, fabricating and placing in position reinforcement steel bars for RCC
works including cleaning, straightening, cutting, bending, hooking, lapping, tying
146 with 1.25 mm dia.soft annealed steel wire, welding wherever required including
cost of all materials, machinery, labour etc., complete with initial lead upto 50
and all lifts.(1.05 tonne/tonne of steel)
Labour Component (including contractor's profit and Overheads)

IRR-CAW-7-6

4
sqm

cum

471.20

cum

cum

50.50

271.70

cum

65.10

CANAL LINING WORKS :

Labour Component (including contractor's profit and Overheads)

IRR-CAW-7-5

Rate

ROCK FILL WORKS :

Stones and spalls available in dump yard will be issued at specified issue rate.
Labour Component (including contractor's profit and Overheads)
IRR-CAW-7

Unit

Itemwise unit rate


for Labour
Component
6
27.80

Providing and laying 75 mm thick in-situ M-15 ( 28 days cube compressive


strength not less than 15 N / sqmm ) grade cement concrete with 20 mm down
size approved, clean, hard, graded aggregates for canal lining using vibrating
cylinder type mechanical paver including cost of all materials, machinery, labour,
cleaning, batching, mixing, placing in position,finishing, forming contraction
147 joints, fixing PVC joint sealing strips, curing, shifting of paver from one side to
other side of canal etc., complete with initial lead upto 1 km and all lifts. ( 43
Gr Cement content: (300kg /cum) 22.5 kg / sqm for use of super
plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35,
FA : 0.45 cum, equivalent concrete volume:79.2 cum including the extra
quantity of concrete for curvatures and bends etc.,)
Labour Component (including contractor's profit and Overheads)

cum

211.90

cum

cum

60.60

206.90

cum

cum

59.90

105.00

cum

Each

45.90

87.90

Each

kg

61.70

63.50

kg

sqm

sqm

6.70

390.40

27.70

19

Abstract of work items_UNit Rates for the year 2014-15

Chapterwise item
S.NO
No.
1

IRR-CAW-7-7

Item description

Unit

Rate

sqm

406.30

Providing and laying 80 mm thick in-situ M-15 ( 28 days cube compressive


strength not less than 15 N / sqmm ) grade cement concrete with 20 mm down
size approved, clean, hard, graded aggregates for canal lining using vibrating
cylinder type mechanical paver including cost of all materials, machinery, labour,
cleaning, batching, mixing, placing in position, finishing, forming contraction
148 joints, fixing PVC joint sealing strips, curing, shifting of paver from one side to
other side of canal etc., complete with initial lead upto 1 km and all lifts. ( 43
Gr Cement content: (300kg /cum) 24 kg / sqm for use of super
plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35,
FA : 0.45 cum, equivalent concrete volume:84.48 cum including the extra
quantity of concrete for curvatures and bends etc.,)
Labour Component (including contractor's profit and Overheads)

IRR-CAW-7-8

Providing and laying 100 mm thick in situ M-15 (28 days cube compressive
strength not less than 15 N /Sqmm ) grade cement concrete with 20 mm down
size approved, clean, hard, graded aggregates for canal lining using, vibrating,
cylinder type mechanical paver including cost of all materials, machinery, labour,
cleaning, batching, mixing, placing in position, finishing, forming contraction
149 joints, fixing PVC joint sealing strips, curing, shifting of paver from one side to
othere side of canal etc., complete with initial lead upto 1 Km and all lifts. ( 43
Gr Cement content: (300kg /cum) 30 kg / sqm for use of super
plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35,
FA : 0.45 cum, equivalent concrete volume:88 cum including the extra
quantity of concrete for curvatures and bends etc.,)
Labour Component (including contractor's profit and Overheads)

IRR-CAW-7-9

Dismantling, shifting and re-erecting mechanical concrete paver and DG set


with all accessories across canal CD work or other locations wherever shifting
and re-erecting is necessary including aligning paver correctly for continuing
canal lining work, cost of all materials, machinery, labour etc., complete with all
150 leads and lifts.
Note: Local shifting and re-erection of paver for LH and RH side lining included
in concrete lining rates under items IRR-CAW-7-7 and IRR-CAW-7-8 and
saperate rate for shifting shall not be allowed.
Labour Component (including contractor's profit and Overheads)

IRR-CAW-7-10

Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength
not less than 10 N /sq mm ) grade cement concrete using 40 mm down size
approved, clean, hard, graded aggregates for bed and side lining of
canal(150mm thick) including finishing the junction of bed and sides to required
curveture, cost of all materials, machinery, labour, formwork including supports,
151 cleaning, batching, mixing, placing in position, levelling, vibrating, finishing,
curing etc., complete with initial lead upto 50 m and all lifts. ( 43 Gr Cement
content: 250 kg / cum for use of super plasticiser(0.4% by wt. of cement),CA :
0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
(Only forManually operated)

Labour Component (including contractor's profit and Overheads)

IRR-CAW-7-11

Providing and laying insitu vibrated M-10 (28 days cube compressive strength
not less than 10 N/sqm) grade cement concrete using 40 mm down size
approved, clean, hard, graded aggregade for bed and side lining of canal(100
mm thick) including, finishing the junction of bed and sides to required
152 curveture, cost of all materials, machinery, labour, formwork including supports
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing,
curing etc., complete with initial lead up to 50 m and all lifts ( 43 Gr Cement
content: 250 kg / cum for use of super plasticiser(0.4% by wt. of cement),CA :
0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
Labour Component (including contractor's profit and Overheads)

IRR-CAW-7-12

Providing and laying 100mm thick insitu vibrated M-10 (28 days cube
compressive strength-not less than 10.00 N / sq mm) grade cement concrete
using 40 mm down size approved, clean, hard, graded aggregates for bed and
side lining of canal lining using vibrating cylindertype mechanical paver
153 including cost of all materials mechinery labour batching mixing placing in
position forming contraction joints fixing pvc joint seiling strips shifting of paver
from one side of canal to other side etc.complete with all leads & lifts.
(Cement content: 250 kg / cum for use of super plasticiser(0.4% by wt. of
cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
Labour Component (including contractor's profit and Overheads)

sqm

sqm

27.70

491.10

sqm

shifting

32.00

8490.30

shifting

cum

6039.30

4110.40

cum

cum

1071.10

4253.20

cum

sqm

sqm

Itemwise unit rate


for Labour
Component
6

1103.00

474.20

32.00

20

Abstract of work items_UNit Rates for the year 2014-15

Chapterwise item
S.NO
No.
1

IRR-CAW-7-13

Item description

Unit

Rate

cum

4154.90

Providing and laying insitu vibrated M-10 ( 28 days cube compressive


strength not less than 10 N /sq mm ) grade cement concrete using 20 mm down
size approved, clean, hard, graded aggregates for bed and side lining of canal
including finishing the junction of bed and sides to required curveture, cost of all
154 materials, machinery, labour, formwork including supports, cleaning, batching,
mixing, placing in position, levelling, vibrating, finishing, curing etc., complete
with initial lead upto 50 m and all lifts. (Cement content: 250 kg / cum for use
of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA-65:35, FA : 0.45 cum)
Labour Component (including contractor's profit and Overheads)

IRR-CAW-7-14

Providing and laying insitu vibrated M-15 ( 28 days cube compressive


strength not less than 15 N /sq mm ) grade cement concrete using 40 mm down
size approved, clean, hard, graded aggregates for bed and side lining(150 mm
thick) of canal including finishing the junction of bed and sides to required
155 curveture, cost of all materials, machinery, labour, formwork including supports,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing,
curing etc., complete with initial lead upto 50 m and all lifts. (Cement content:
290 kg / cum for use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum,
Blending Ratio of CA--50:30:20, FA : 0.40 cum)
Labour Component (including contractor's profit and Overheads)

IRR-CAW-7-15

Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength
not less than 15 N /sq mm ) grade cement concrete using 20 mm down size
approved, clean, hard, graded aggregates for bed and side lining(of thickness
100 mm) of canal including finishing the junction of bed and sides to required
156 curveture, cost of all materials, machinery, labour, formwork including supports,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing,
curing etc., complete with initial lead upto 50 m and all lifts. (Cement content:
300 kg / cum for use of super plasticiser(0.4% by wt. of cement),CA : 0.80
cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
Labour Component (including contractor's profit and Overheads)

IRR-CAW-7-16

Providing and laying 150mm thick insitu vibrated M-15 (28 days cube
compressive strength-not less than 15.00 N / sq mm) grade cement concrete
using 20 mm down size approved, clean, hard, graded aggregates for bed and
side lining of canal lining using vibrating cylindertype mechanical paver including
cost of all materials mechinery labour batching mixing placing in position forming
157
contractiom joints fixing pvc joint seiling strips shifting of paver from one side of
canal to other side etc.complete with all leads & lifts. (Cement content: 300
kg / cum for use of super plasticiser(0.4% by wt. of cement),CA : 0.80 cum,
Blending Ratio of CA--65:35, FA : 0.44 cum)
(Paver)
Labour Component (including contractor's profit and Overheads)

IRR-CAW-7-17

Providing and fixing pre-cast RCC template walls consisting of 0.05 cum M-15
grade concrete using 20 mm down size coarse aggregates and 10 kg
reinforcement steel moulded as per specifications and drawing in CM 1:4
158 proportion including cost of all materials, machinery, labour, formwork,
fabricating and placing reinforcement steel, mixing, laying, conveying and fixing
in position including necessary excavation for seating, finishing joints in CM 1:4,
curing etc., complete with initial lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)

IRR-CAW-7-18

IRR-CAW-7-19

Providing and fixing 50 mm dia perforated GI pressure relief pipes 12.50 cm


long with one end closed with perforated GI plate and other end provided with
159
alluminium lid hinged to pipe including cost of all materials, labour, drilling 8 mm
dia holes etc., complete with all leads and lifts.
Labour Component (including contractor's profit and Overheads)
Providing and fixing 50 mm dia perforated GI pressure relief pipes 22.50 cm
long with one end closed with perforated GI plate and other end provided with
160
alluminium lid hinged to pipe including cost of all materials, labour, drilling 8 mm
dia holes etc., complete with all leads and lifts.
Labour Component (including contractor's profit and Overheads)

cum

cum

1103.00

4441.60

cum

cum

1167.00

4570.00

cum

sqm

1232.50

647.00

sqm

Rm

32.00

1000.70

Rm

Each

242.60

136.60

Each

Each
Each

Itemwise unit rate


for Labour
Component
6

42.00

194.10
42.00

21

Abstract of work items_UNit Rates for the year 2014-15

Chapterwise item
S.NO
No.
1
IRR-CAW-7-20

IRR-CAW-7-21

IRR-CAW-7-22

IRR-CAW-7-23

IRR-CAW-7-24

IRR-CAW-7-25

Item description

3
Providing and fixing 50 mm dia perforated GI pressure relief pipes 30 cm
long with one end closed with perforated GI plate and other end provided with
161
alluminium lid hinged to pipe including cost of all materials, labour, drilling 8 mm
dia holes etc., complete with all leads and lifts.
Labour Component (including contractor's profit and Overheads)
Providing and fixing 50 mm dia perforated GI pressure relief pipes 45 cm
long with one end closed with perforated GI plate and other end provided with
162
alluminium lid hinged to pipe including cost of all materials, labour, drilling 8 mm
dia holes etc., complete with all leads and lifts.
Labour Component (including contractor's profit and Overheads)
Providing and fixing 50 mm dia perforated GI pressure relief pipes 75 cm
long with one end closed with perforated GI plate and other end provided with
163
alluminium lid hinged to pipe including cost of all materials, labour, drilling 8 mm
dia holes etc., complete with all leads and lifts.
Labour Component (including contractor's profit and Overheads)
Providing and fixing 100 mm dia perforated PVC pipes 40 cm long for Weep
164 holes including cost of all materials, labour, drilling 8 mm dia holes etc. complete
with all leads and lifts.
Labour Component (including contractor's profit and Overheads)
Drilling 32 mm dia pressure relief hole below pressure relief pipe for bed and
165 side lining of canal laid on rock including cost of all materials, machinery, labour
etc., complete with all leads and lifts.
Labour Component (including contractor's profit and Overheads)

IRR-CAW-7-28

IRR-CAW-7-30

Each

230.80

Each

Each

Fixing PCC slabs of various sizes in CM 1 : 3 proportion to the side slopes of


canal including preparing bed, flush pointing joints in CM 1 : 3 propn, cost of all
168
materials ( excluding PCC slabs ), labour, finishing, curing etc., complete with
initial lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)
Fixing PCC lug slabs of various sizes in CM 1 : 3 proportion for supporting
PCC slab lining including necessary excavation, refilling, flush pointing joints in
169
CM 1 : 3 propn, cost of all materials ( excluding PCC lug slabs ), labour, finishing,
curing etc., complete with initial lead upto 50 m and all lifts.
170

171

Fixing 30 cm height pre-cast drops for field channels as directed including


excavation, etc., complete with all leads and lifts.
Labour Component (including contractor's profit and Overheads)
Providing and fixing LDPE sheet for bed and sides of canal including cost of all
materials, labour, laying, joining etc., complete with all leads and lifts.
Labour Component (including contractor's profit and Overheads)
If the surface on which the LDPE sheet is to be laid is too rough and undulating
provide 75 mm thick sand backing to LDPE sheet. For providing 75 mm thick
Sand for backing add
Labour Component (including contractor's profit and Overheads)

Providing and fixing LDPE sheet for bed and sides of canal including cost of all
172 materials, labour, laying, joining etc., complete with all leads and lifts.
Using 750 micron thick LDPE sheet.
Labour Component (including contractor's profit and Overheads)

42.00

299.50

Each

Each

42.00

432.30

Each

Each

42.00

220.40

Each

Each

21.00

267.10

Each

sqm

Using 500 micron thick LDPE sheet.

IRR-CAW-7-31

Providing and fixing 25 to 40 mm thick Shahabad / Talikota / other similar


stone slabs with pointing and finishing joints neatly in CM 1:3 proportion for
167
canal / field channel lining including cutting slabs to required size, mixing mortar,
finishing joints neatly, curing etc., complete with lead upto 50 m and all lifts.

Labour Component (including contractor's profit and Overheads)

IRR-CAW-7-29

Each

Labour Component (including contractor's profit and Overheads)

IRR-CAW-7-27

Rate

Providing and forming 35 x 35 x 40 cm deep filter drain consisting of 75 mm


thick 10 mm down coarse aggregate around pressure relief pipe and 75 mm thick
166
sand around coarse aggregate filter including cost of all materials, labour,
excavation of pit etc., complete with lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)

IRR-CAW-7-26

Unit

85.70

40.70

Each

7.30

351.40

sqm

sqm

63.30

75.30

sqm

Rm

58.70

43.90

Rm
Each

39.30
164.50

Each

sqm

164.50

128.00

sqm
sqm

11.90
37.30

sqm

sqm

sqm

Itemwise unit rate


for Labour
Component
6

8.10

180.00

16.20

22

Abstract of work items_UNit Rates for the year 2014-15

Chapterwise item
S.NO
No.
1

IRR-CAW-7-32

Item description

Unit

Rate

sqm

248.40

Providing and fixing LDPE sheet for bed and sides of canal including cost of all
173 materials, labour, laying, joining etc., complete with all leads and lifts.
Using 1000 micron thick LDPE sheet.
Labour Component (including contractor's profit and Overheads)

IRR-CAW-7-33

IRR-CAW-7-34

IRR-CAW-7-35

IRR-CAW-7-36

IRR-CAW-7-37

Providing and fixing 12 mm thick 380 mm depth tarfelt expansion joint filler
174 boards for stone masonry lining of canal including cost of all materials, labour
etc., complete with all leads and lifts.
Labour Component (including contractor's profit and Overheads)
Providing and fixing 20 mm thick 100 mm depth tarfelt expansion joint filler
175 boards for cement concrete lining of canal including cost of all materials,
labour etc., complete with all leads and lifts.
Labour Component (including contractor's profit and Overheads)
Providing and fixing 20 mm thick 150 mm depth tarfelt expansion joint filler
176 boards for cement concrete lining of canal including cost of all materials,
labour etc., complete with all leads and lifts.
Labour Component (including contractor's profit and Overheads)
Providing and forming 35 mm wide and 10 mm thick construction /
177 contraction joints for concrete lining by mastic filler including cost of all
materials, labour etc., complete with all leads and lifts.
Labour Component (including contractor's profit and Overheads)
Manufacturing 550 x 550 x 55 mm size PCC lining slabs in M-15 grade ( 28
days cube compressive strength not less than 15 N /sqmm ) cement concrete
using 20 mm down graded coarse aggregate including cost of all materials,
178 machinery, labour, batching, mixing, laying, compacting, formwork, finishing,
curing etc.,complete with initial lead upto 50 m and all lifts. ( Cement content :
300 kg / cum with super plastcizer (0.4% by wt. of cement), CA : 0.80 cum,
Blending Ratio of CA : 65:35, FA : 0.45cum)
Labour Component (including contractor's profit and Overheads)

IRR-CAW-7-38

Manufacturing 550 x 300 x 55 mm size PCC lug slabs in M-15 grade ( 28 days
cube compressive strength not less than 15 N / sqmm ) cement concrete using
20 mm down graded coarse aggregate including cost of all materials,
179 machinery, labour, batching, mixing, laying, compacting, formwork, finishing,
curing etc.,complete with initial lead upto 50 m and all lifts. ( Cement content :
300 kg / cum with super plastcizer (0.4% by wt. of cement), CA : 0.80 cum,
Blending Ratio of CA : 65:35, FA : 0.45cum)
Labour Component (including contractor's profit and Overheads)

IRR-CAW-7-39

IRR-CAW-7-40

IRR-CAW-7-41

Manufacturing 450 x 300 x 30 mm size PCC lining slabs in M-15 grade ( 28


days cube compressive strength not less than 15 N / sqmm ) cement concrete
using 10 mm down graded coarse aggregate including cost of all materials,
180 machinery, labour, batching, mixing, laying, compacting, formwork, finishing,
curing etc.,complete with initial lead upto 50 m and all lifts. ( Cement content :
300 kg / cum with super plastcizer (0.4% by wt. of cement), CA : 0.68 cum, FA
: 0.43cum)
Labour Component (including contractor's profit and Overheads)
Manucturing 450 x 150 x 30 mm size PCC lug slabs in M-15 grade ( 28 days
cube compressive strength not less than 15 N / sqmm ) cement concrete using
10 mm down graded coarse aggregate including cost of all materials,
181 machinery, labour, batching, mixing, laying, compacting, formwork, finishing,
curing etc.,complete with initial lead upto 50 m and all lifts. ( Cement content :
300 kg / cum with super plastcizer (0.4% by wt. of cement),CA : 0.68 cum, FA :
0.43cum)
Labour Component (including contractor's profit and Overheads)
Manufacturing 600 x 300 x 100mm size PCC lining slabs in M-15 grade (28
days cube compressive strength not less than 15 N/Sqmm) cement concrete
using 20 mm down grades coarse aggregate including cost of all materials,
182 machinery, labour, batching, mixing, laying, compacting, formwork, finishing,
curing etc., complete with initial lead upto 50 m and all lifts. ( Cement content
: 300 kg / cum with super plastcizer (0.4% by wt. of cement), CA : 0.80 cum,
FA : 0.45cum, Blending Ratio of CA--65:35)
Labour Component (including contractor's profit and Overheads)

sqm

Rm

21.90

192.80

Rm

Rm

7.30

79.10

Rm

Rm

7.30

117.20

Rm

Rm

7.30

22.80

Rm

Each

5.40

88.20

Each

Each

23.00

62.00

Each

Each

23.00

31.50

Each

Each

14.80

24.00

Each

Each

Each

Itemwise unit rate


for Labour
Component
6

14.80

72.90

14.70

23

Abstract of work items_UNit Rates for the year 2014-15

Chapterwise item
S.NO
No.
1

IRR-CAW-7-42

IRR-CAW-7-43

IRR-CAW-7-44

Item description

3
Manucturing 400 x 400 x 30 mm size PCC lining slabs in M-15 grade ( 28
days cube compressive strength not less than 15 N / sqmm )cement concrete
using 10 mm down graded coarse aggregate including cost of all materials,
183 machinery, labour, batching, mixing, laying, compacting, formwork, finishing,
curing etc.,complete with initial lead upto 50 m and all lifts. ( Cement content :
300 kg / cum with super plastcizer (0.4% by wt. of cement), CA : 0.68 cum, FA
: 0.43cum)
Labour Component (including contractor's profit and Overheads)
Manufacturing 400 x 150 x 30 mm size PCC lug slabs in M-15 grade ( 28 days
cube compressive strength not less than 15 N /sqmm ) cement concrete using
10 mm down graded coarse aggregate including cost of all materials,
184 machinery, labour, batching, mixing, laying, compacting, formwork, finishing,
curing etc.,complete with initial lead upto 50 m and all lifts. ( Cement content :
300 kg / cum with super plastcizer (0.4% by wt. of cement), CA : 0.68 cum, FA
: 0.43cum)
Labour Component (including contractor's profit and Overheads)
Providing and laying uncoursed rubble stone masonry in CM 1 : 5 proportion
for canal side lining using stones and chips from approved quarry including cost
of all materials, machinery, labour, forming weep holes at specified intervals,
185
finishing, curing etc., complete with initial lead upto 50 m and all
lifts.(Thickness of the masonry assumed: 0.3 m, rubble stones : 0.96 cum,
Stone Chips : 0.15cum,Through Stones 20 x 20 x 30cm : 1/sqm)
Labour Component (including contractor's profit and Overheads)

IRR-CAW-7-45

Providing and laying uncoursed rubble stone masonry in CM 1:5 proportion for
canal side lining using stones from approved quarry including cost of all
186 materials, machinery, labour, forming weep holes at specified intervals, finishing,
curing etc., complete with initial lead upto 50m and all lifts.(with no pin
headers)(Thickness of the Masonry assumed:0.3 m, rubble stones : 1.1 cum)
Labour Component (including contractor's profit and Overheads)

IRR-CAW-7-46

IRR-CAW-7-47

Providing and laying uncoursed rubble stone masonry in CM 1 : 5 proportion


for canal side lining using stones and chips from canal excavation including cost
of all materials, machinery, labour, forming weep holes at specified interval,
187
finishing, curing etc., complete with initial lead upto 50 m and all lifts.( rubble
stones : 0.96 cum, Stone Chips : 0.15cum, Through Stones 20 x 20 x 30cm :
1/sqm)
Labour Component (including contractor's profit and Overheads)
Providing and laying uncoursed rubble stone masonry in CM 1:5 proportion for
canal side lining using stones from canal excavation including cost of all
188 materials, machinery, labour, forming weep holes at specified intervals,
finishing, curing etc., complete with initial lead upto 50m and all lifts.(with no
pin headers)( rubble stones : 1.1cum, cement : 98kg, sand 0.34 cum)
Labour Component (including contractor's profit and Overheads)

IRR-CAW-8

IRR-CAW-8-1

IRR-CAW-8-2

Rate

Each

33.40

Each

Each

14.80

23.40

Each

cum

14.80

1901.80

cum

cum

566.50

3009.10

cum

cum

1870.60

1764.50

cum

cum

639.40

2805.10

cum

1870.60

ROCK PITCHING
Providing and constructing 25 cm thick dry rubble stone pitching with pin
headers at 2 per sqm including cost of all materials, labour, hand packing,
189
finishing etc., complete with initial lead upto 50 m and all lifts.( rubble stones :
0.23 cum/sqm, Stone Chips : 0.0375cum/sqm, Pin Headers 30cm : 2/sqm)
Labour Component (including contractor's profit and Overheads)
If 15 cm thick murum bed is to be provided below pitching add
Labour Component (including contractor's profit and Overheads)

IRR-CAW-8-1-A
(New Item4 2011-12)

Unit

Itemwise unit rate


for Labour
Component
6

Providing and constructing 22.5 cm thick dry rubble stone pitching with pin
headers at 2 per sqm including cost of all materials, labour, hand packing,
190 finishing etc., complete with initial lead upto 50 m and all lifts.( rubble stones :
0.207 cum/sqm, Stone Chips : 0.3375cum/sqm, Pin Headers 30cm : 2/sqm)
(For Maintenance Works)
Labour Component (including contractor's profit and Overheads)
Providing and constructing 25 cm thick dry rubble stone pitching including
cost of all materials, labour, hand packing, finishing etc., complete with initial
191
lead upto 50 m and all lifts.(with no pin headers)( rubble stones : 0.33
cum/sqm)
Labour Component (including contractor's profit and Overheads)

sqm

194.40

sqm
sqm
sqm

44.10
35.40

sqm

184.60

13.50

sqm

sqm
sqm

44.10

204.60
104.90

24

Abstract of work items_UNit Rates for the year 2014-15

Chapterwise item
S.NO
No.
1
IRR-CAW-8-2 A (New Item5 2011-12)

IRR-CAW-8-3

Item description

IRR-CAW-8-5

sqm

148.20

Providing and constructing 30 cm thick dry rubble stone pitching with pin
headers at 2 per sqm including cost of all materials, labour, hand packing,
193
finishing etc., complete with initial lead upto 50 m and all lifts.( rubble stones :
0.275 cum/sqm, Stone Chips : 0.045cum/sqm, Pin Headers 30cm : 2/sqm)

sqm

Providing and constructing 30 cm thick dry rubble stone pitching including


cost of all materials, labour, hand packing, finishing etc., complete with initial
194
lead upto 50 m and all lifts.(with no pin headers)( rubble stones : 0.33
cum/sqm)
Labour Component (including contractor's profit and Overheads)
Providing and constructing 45 cm thick dry rubble stone pitching with pin
headers at 2 per sqm including cost of all materials, labour, hand packing,
195
finishing etc., complete with initial lead upto 50 m and all lifts.( rubble stones :
0.40 cum/sqm, Stone Chips : 0.0675cum/sqm, Pin Headers 45cm : 2/sqm)
Labour Component (including contractor's profit and Overheads)

IRR-CAW-8-6

IRR-CAW-8-7

IRR-CAW-8-8

IRR-CAW-8-9

Providing and constructing 45 cm thick dry rubble stone pitching including


cost of all materials, labour, hand packing, finishing etc., complete with initial
196
lead upto 50 m and all lifts.(with no pin headers)( rubble stones : 0.495
cum/sqm)
Labour Component (including contractor's profit and Overheads)
Providing and constructing 30 cm thick rubble stone pitching set in CM 1: 5
proportion with pin headers at 2 per sqm in including cost of all materials,
197 labour, packing chips and mortar, finishing, curing etc., complete with initial
lead upto 50 m and all lifts.( rubble stones : 0.275 cum/sqm, Stone Chips :
0.045cum/sqm, Pin Headers 30cm : 2/sqm)
Labour Component (including contractor's profit and Overheads)
Providing and Constructing 30 cm thick rubble stone pitching set in CM 1:5
198 Proportion including cost of all materials,labour, packing chips and mortar
,finishing etc.,complete( rubble stones : 0.33 cum/sqm )
Labour Component (including contractor's profit and Overheads)
Providing and constructing 30 cm thick dry khandki stone pitching using 20
to 25 cm size khandki stones with pin headers at 2 per sqm including cost of all
199 materials, labour, hand packing, finishing etc., complete with initial lead upto
50 m and all lifts.( Khandki stones 20- 25 cm height : 1200 Nos/sqm, Stone
Chips : 0.045cum/sqm, Pin Headers 30cm : 2/sqm)
Labour Component (including contractor's profit and Overheads)

IRR-CAW-8-10

Providing and constructing 45 cm thick dry khandki stone pitching using 25


to 30 cm size khandki stones with pin headers at 2 per sqm including cost of all
200 materials, labour, hand packing, finishing etc., complete with initial lead upto
50 m and all lifts.( Khandki stones 25- 30 cm height : 1200 Nos/sqm, Stone
Chips : 0.0675cum/sqm, Pin Headers 45cm : 2/sqm)
Labour Component (including contractor's profit and Overheads)

IRR-CAW-8-11

Providing and constructing 30 cm thick khandki stone pitching using 20 to 25


cm size khandki stones with pin headers at 2 per sqm set in CM 1 : 5 proportion
with pointing joints in CM 1:3 proportion including cost of all materials, labour,
201
packing chips and mortar, finishing, curing etc.complete with initial lead upto
50 m and all lifts.( Khandki stones 20- 25 cm height : 1200 Nos/sqm, Stone
Chips : 0.045cum/sqm, Pin Headers 30cm : 2/sqm)
Labour Component (including contractor's profit and Overheads)

IRR-CAW-8-12

Rate

3
Providing and constructing 225 mmm thick dry rubble stone pitching
including cost of all materials, labour, hand packing, finishing etc., complete with
192
initial lead upto 50 m and all lifts.(with no pin headers)( rubble stones :
0.2475 cum/sqm) (For Maintenance Works)
Labour Component (including contractor's profit and Overheads)

Labour Component (including contractor's profit and Overheads)

IRR-CAW-8-4

Unit

Providing and constructing 45 cm thick khandki stone pitching using 25 to 30


cm stones with pin headers at 2 per sqm set in CM 1 : 5 proportion with pointing
joints in CM 1 : 3 proportion including cost of all materials, labour, packing chips
202
and mortar, finishing, curing etc., complete with initial lead upto 50 m and all
lifts.( Khandki stones 25- 30 cm height : 730 Nos/sqm, Stone Chips :
0.0675cum/sqm, Pin Headers 45cm : 2/sqm)

sqm

94.40

213.60

sqm

sqm

44.10

245.50

sqm

sqm

125.90

322.10

sqm

sqm

62.00

368.20

sqm

sqm

188.80

456.50

sqm

sqm

75.50

361.30

sqm

sqm

16.80

291.80

sqm

sqm

44.10

310.30

sqm

sqm

62.00

521.10

sqm

sqm

Itemwise unit rate


for Labour
Component
6

72.00

632.90

25

Abstract of work items_UNit Rates for the year 2014-15

Chapterwise item
S.NO
No.
1

IRR-CAW-8-13

IRR-CAW-8-14

Item description
3
Labour Component (including contractor's profit and Overheads)

Providing 10 cm thick approved type grass turfing to the side slopes of


203 canal icluding cost of all materials, labour, watering for minimum 15 days
etc.,complete with lead 50 m and all lifts.(FA : 2 cum/sqm)
Labour Component (including contractor's profit and Overheads)
Providing 10 cm thick approved type grass turfing to the side slopes of
canal icluding cost of all materials, labour, watering for minimum 15 days
204 etc.,complete with lead 50 m and all lifts.
with no sand
Labour Component (including contractor's profit and Overheads)

Chapter IV
IRR-CCDW

4
sqm

sqm

96.20

sqm

sqm

56.50

64.50

sqm

32.60

EXCAVATION & FOUNDATION TREATMENT WORKS :


(manual means of excavation and conveyance)
Excavation in all kinds of soil including boulders upto 0.30 m dia. for
205 foundations of canal cross drainage and other appurtenant structures and
placing the excavated stuff neatly in specified dump area or disposing off the
same as directed etc., complete with initial lead upto 50 m and initial lift upto
3 m.
Labour Component (including contractor's profit and Overheads)
Excavation for Structures- Mechanical Means
MORTH)

IRR-CCDW-1-2

Rate

CANAL CROSS DRAINAGE WORKS

IRR-CCDW-1

IRR-CCDW-1-1

Unit

Itemwise unit rate


for Labour
Component
6
99.00

206

cum

212.30

cum

212.40

( Data adopted from

Earth work in excavation in all kinds of soils of foundation of structures as


per drawing and technical specification, including setting out, construction of
shoring and bracing, removal of stumps and other deleterious matter, dressing
of sides and bottom and backfilling with approved material. ( depth upto 3
meters)
Labour Component (including contractor's profit and Overheads)

cum

93.00

cum

17.60

(manual means of excavation and conveyance)


IRR-CCDW-1-3

207

Excavation in ordnary rock (including HDR) without blasting including


boulders above 0.3 m upto 0.60 m dia. for foundations of canal cross
drainage and other appurtenant structures and placing the excavated stuff
neatly in specified dump area or disposing off the same as directed etc.,
complete with initial lead upto 50 m and initial lift upto 3 m.
Labour Component (including contractor's profit and Overheads)

cum

310.70

cum

310.70

( Data adopted from MORTH) (manual means of excavation and conveyance)


IRR-CCDW-1-4

208

Excavation in ordnary rock (including HDR) without blasting for foundations


of canal cross drainage and other appurtenant structures and placing the
excavated stuff neatly in specified dump area or disposing off the same as
directed etc., complete with initial lead upto 50 m and initial lift upto 3 m.
Labour Component (including contractor's profit and Overheads)

cum

120.00

cum

19.50

(manual means of excavation after blasting and conveyance)

IRR-CCDW-1-5

Excavation in hard rock requiring blasting including boulders above 0.6 m


209 upto 1.2 m dia. for foundations of canal cross drainage and other appurtenant
structures and placing the excavated stuff neatly in specified dump area or
disposing off the same as directed etc., complete with initial lead upto 50 m
and initial lift upto 3 m.
Labour Component (including contractor's profit and Overheads)

cum

325.20

cum

241.30

(manual means of excavation after blasting and conveyance)

IRR-CCDW-1-6

Excavation in hard rock of all toughness by blasting including boulders


210 above 1.2 m dia. for foundations of canal cross drainage and other
appurtenant structures and placing the excavated rock neatly in specified dump
area or stack yard as directed etc., complete with initial lead upto 50 m and
initial lift upto 3 m.
Labour Component (including contractor's profit and Overheads)

cum

cum

512.30

300.40

26

Abstract of work items_UNit Rates for the year 2014-15

Chapterwise item
S.NO
No.
1

Item description

Unit

Rate

cum

991.10

Itemwise unit rate


for Labour
Component
6

(manual means of excavation after controlled blasting and conveyance)


Hard Rock ( blasting prohibited ) ( Data adopted from MORTH)
IRR-CCDW-1-7

IRR-CCDW-1-8

IRR-CCDW-2

IRR-CCDW-2-1

IRR-CCDW-2-2

IRR-CCDW-2-3

211

Excavation in hard rock with blasting ( blasting prohibited )prohibited for


foundations of canal cross drainage and other appurtenant structures and
placing the excavated rock neatly in or stack yard as directed etc., complete
with specified dump area initial lead upto 50 m and initial lift upto 3 m.
Labour Component (including contractor's profit and Overheads)

Providing and fixing 25 mm dia 2.50 m long cold twisted deformed steel
anchor rods with 1.25 m length driven into 32 mm dia hole drilled in bed rock
and remaining length embedded in concrete / masonry including cost of all
212
materials, machinery, labour, drilling and cleaning hole, driving anchor rod,
grouting hole with thick cement slurry etc., complete with initial lead upto 50 m
and all lifts.
Labour Component (including contractor's profit and Overheads)

Providing, fabricating and placing in position reinforcement steel bars for


RCC works including cleaning, straightening, cutting, bending, hooking, lapping,
213 welding wherever required,tying with 1.25 mm dia soft annealed steel wire,
including cost of all materials, machinery, labour etc., complete with initial lead
upto 50 and all lifts.
Labour Component (including contractor's profit and Overheads)
Providing, fabricating and fixing in position structural steel cutting edge
consisting of 100 x 100 x 10 mm angle and 250 x 12 mm plate for sinking 4.50 m
214 outer diameter foundation wells foundation wells including cost of all materials,
machinery, labour, bending, welding, providing anchors etc., complete with
initial lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)
Providing and laying insitu vibrated M-15 ( 28 days cube compressive
strength not less than 15 N /sq mm ) grade cement concrete using 40 mm down
size approved, clean, hard, graded aggregates for foundation filling including
cost of all materials, machinery, labour, formwork, cleaning, batching, mixing,
215
placing in position, levelling, vibrating, finishing, curing etc., complete with
initial lead upto 50 m and all lifts. (Cement content: 260 kg / cum with use of
super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA-50:30:20, FA : 0.40 cum)

Providing and laying insitu vibrated M-15 ( 28 days cube compressive


strength not less than 15 N / sq mm ) grade cement concrete using 80 mm
down size approved, clean, hard, graded aggregates for foundation filling
including cost of all materials, machinery, labour, formwork, cleaning, batching,
216
mixing, placing in position, levelling, vibrating, finishing, curing etc., complete
with initial lead upto 50 m and all lifts. (Cement content: 250 kg / cum with
use of super plasticiser(0.4% by wt. of cement),CA : 0.98cum, Blending Ratio
of CA--35:30:20:15, FA : 0.35 cum)
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-2-5

Providing and laying insitu vibrated M-10 ( 28 days cube compressive


strength not less than 10 N / sq mm ) grade cement concrete using 40 mm
down size approved, clean, hard, graded aggregates for foundation filling
including cost of all materials, machinery, labour, formwork, cleaning, batching,
217
mixing, placing in position, levelling, vibrating, finishing, curing etc., complete
with initial lead upto 50 m and all lifts. (Cement content: 220 kg / cum with
use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio
of CA--50:30:20, FA : 0.40 cum)
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-2-6

Each

301.20

913.30

Each

185.70

STEEL AND CEMENT CONCRETE WORKS :

Labour Component (including contractor's profit and Overheads)

IRR-CCDW-2-4

cum

Providing and laying insitu vibrated M-10 ( 28 days cube compressive


strength not less than 10 N / sq mm ) grade cement concrete using 80 mm
down size approved, clean, hard, graded aggregates for foundation filling
including cost of all materials, machinery, labour, formwork, cleaning, batching,
218
mixing, placing in position, levelling, vibrating, finishing, curing etc., complete
with initial lead upto 50 m and all lifts. (Cement content: 220 kg / cum with
use of super plasticiser(0.4% by wt. of cement),CA : 0.98cum, Blending Ratio
of CA--35:30:20:15, FA : 0.35 cum)

kg

63.60

kg

kg

7.20

76.70

kg

cum

8.70

4219.80

cum

cum

1110.60

4196.90

cum

cum

1156.90

3964.00

cum

cum

1061.30

4039.00

27

Abstract of work items_UNit Rates for the year 2014-15

Chapterwise item
S.NO
No.
1

IRR-CCDW-2-7

Item description
3
Labour Component (including contractor's profit and Overheads)

Providing and laying insitu vibrated M-20 ( 28 days cube compressive


strength not less than 20 N / sq mm ) grade cement concrete using 40 mm
down size approved, clean, hard, graded aggregates for foundation filling
including cost of all materials, machinery, labour, formwork, cleaning, batching,
219
mixing, placing in position, levelling, vibrating, finishing, curing etc., complete
with initial lead upto 50 m and all lifts. (Cement content: 310 kg / cum with
use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio
of CA--50:30:20, FA : 0.40 cum)
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-2-8

Providing and laying insitu vibrated M-20 ( 28 days cube compressive


strength not less than 20 N / sq mm ) grade cement concrete using 40 mm
down size approved, clean, hard, graded aggregates for sub-structure / superstructure works including cost of all materials, machinery, labour, formwork,
220
scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating,
finishing, curing etc., complete with initial lead upto 50 m and all lifts.(Cement
content: 320 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA
: 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-2-9

Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength
not less than 20 N / sq mm ) grade cement concrete using 20 mm down size
approved, clean, hard, graded aggregates for sub-structure / super- structure
works including cost of all materials, machinery, labour, formwork, scaffolding,
221
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing,
curing etc., complete with initial lead upto 50 m and all lifts.(Cement content:
330 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA :
0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
Labour Component (including contractor's profit and Overheads)

Providing and laying insitu vibrated M-15 ( 28 days cube compressive


strength not less than 15 N / sq mm ) grade cement concrete using 20 mm
down size approved, clean, hard, graded aggregates for sub-structure / superstructure works including cost of all materials, machinery, labour, formwork,
IRR-CCDW-2-10 222
scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating,
finishing, curing etc., complete with initial lead upto 50 m and all lifts.(Cement
content: 280 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA
: 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
Labour Component (including contractor's profit and Overheads)
Providing and laying insitu vibrated M-10 ( 28 days cube compressive
strength not less than 10 N / sq mm ) grade cement concrete using 20 mm
down size approved, clean, hard, graded aggregates for sub-structure / superstructure works including cost of all materials, machinery, labour, formwork,
IRR-CCDW-2-11 223
scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating,
finishing, curing etc., complete with initial lead upto 50 m and all lifts. (Cement
content: 220 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA
: 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
Labour Component (including contractor's profit and Overheads)
Providing and laying insitu vibrated M-20 ( 28 days cube compressive
strength not less than 20 N / sq mm ) grade cement concrete using 20 mm
down size approved, clean, hard, graded aggregates for well kerb including
cost of all materials, machinery, labour, formwork, scaffolding, cleaning,
batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
IRR-CCDW-2-12 224 complete with initial lead upto 50 m and all lifts. (Cement content: 350 kg /
cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum,
Blending Ratio of CA--65:35, FA : 0.45 cum)
If water is to be brought from other place add only lead charges @ 500 ltr /
cum.
Labour Component (including contractor's profit and Overheads)

Unit

Rate

4
cum

cum

4536.30

cum

cum

1167.60

4971.30

cum

cum

1163.10

4968.80

cum

cum

1235.80

4725.30

cum

cum

1237.90

4322.70

cum

cum

cum

Itemwise unit rate


for Labour
Component
6
1149.30

1150.50

6245.20

1493.90

28

Abstract of work items_UNit Rates for the year 2014-15

Chapterwise item
S.NO
No.
1

Item description

Unit

Rate

cum

5634.20

Providing and laying insitu vibrated M-20 ( 28 days cube compressive


strength not less than 20 N / sq mm ) grade cement concrete using 40 mm
down size approved, clean, hard, graded aggregates for well steining including
cost of all materials, machinery, labour, formwork, scaffolding, cleaning,
batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
IRR-CCDW-2-13 225
complete with initial lead upto 50 m and all lifts. (Cement content: 320 kg /
cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum,
Blending Ratio of CA--50:30:20, FA : 0.40 cum)
If water is to be brought from other place add only lead charges @ 500 ltr /
cum.
Labour Component (including contractor's profit and Overheads)
Providing and laying insitu M-15 ( 28 days cube compressive strength not less
than 15 N / sq mm ) grade cement concrete using 20 mm down size approved,
clean, hard, graded aggregates for well bottom plug by tremie or skip box
IRR-CCDW-2-14 226
method including cost of all materials, complete with initial lead upto 50 m and
all lifts.(Cement content: 350 kg / cum with use of super plasticiser(0.4% by
wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
Labour Component (including contractor's profit and Overheads)
Providing and laying insitu vibrated M-15 ( 28 days cube compressive
strength not less than 15 N / sq mm ) grade cement concrete using 40 mm
down size approved, clean, hard, graded aggregates for well top plug including
cost of all materials, machinery, labour, cleaning, batching, mixing, placing in
position, levelling, vibrating, finishing, curing etc., complete with initial lead
IRR-CCDW-2-15 227 upto 50 m and all lifts. (Cement content: 280 kg / cum with use of super
plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA-50:30:20, FA : 0.40 cum)
If water is to be brought from other place add only lead charges @ 500 ltrs /
cum
Labour Component (including contractor's profit and Overheads)
Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength
not less than 20 N / sq mm ) grade cement concrete using 20 mm down size
approved, clean, hard, graded aggregates for well cap including cost of all
materials, machinery, labour, formwork, scaffolding, cleaning, batching, mixing,
placing in position, levelling, vibrating, finishing, curing etc., complete with initial
IRR-CCDW-2-16 228 lead upto 50 m and all lifts. (Cement content: 330 kg / cum with use of super
plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35,
FA : 0.45 cum)
If water is to be brought from other place add only lead charges @ 500 ltr /
cum.
Labour Component (including contractor's profit and Overheads)

Providing and laying insitu vibrated M-15 ( 28 days cube compressive


strength not less than 15 N / sq mm ) grade cement concrete using 80 mm
down size approved, clean, hard, graded aggregates for piers and abutments
including cost of all materials, labour, machinery, formwork, cleaning, batching,
mixing, placing in position, levelling, vibrating, finishing, curing etc., complete
IRR-CCDW-2-17 229
with initial lead upto 50 m and all lifts. (Cement content: 250 kg / cum with
use of super plasticiser(0.4% by wt. of cement),CA : 0.98cum, Blending Ratio
of CA--35:30:20:15, FA : 0.35 cum)
If water is to be brought from other place add only lead charges @ 500 ltr /
cum.
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-2-18

Providing and laying insitu vibrated M-10 ( 28 days cube compressive


strength not less than 10 N / sq mm ) grade cement concrete using 80 mm
down size approved, clean, hard, graded aggregates for piers and abutments
including cost of all materials, labour, machinery, formwork, cleaning, batching,
mixing, placing in position, levelling, vibrating, finishing, curing etc., complete
230
with initial lead upto 50 m and all lifts. (Cement content: 220 kg / cum with
use of super plasticiser(0.4% by wt. of cement),CA : 0.98cum, Blending Ratio
of CA--35:30:20:15, FA : 0.35 cum)
If water is to be brought from other place add only lead charges @ 500 ltr /
cum.
Labour Component (including contractor's profit and Overheads)

cum

cum

1365.20

4172.40

cum

cum

1074.60

3895.80

cum

cum

1055.90

4337.00

cum

cum

1074.60

5157.30

cum

cum

cum

Itemwise unit rate


for Labour
Component
6

1427.30

4999.40

1419.20

29

Abstract of work items_UNit Rates for the year 2014-15

Chapterwise item
S.NO
No.
1

Item description

Unit

Rate

cum

4912.60

Providing and laying insitu vibrated M-10 ( 28 days cube compressive


strength not less than 10 N / sq mm ) grade cement concrete using 40 mm
down size approved, clean, hard, graded aggregates for piers and abutments
including cost of all materials, labour, machinery, formwork, cleaning, batching,
mixing, placing in position, levelling, vibrating, finishing, curing etc., complete
IRR-CCDW-2-19 231
with initial lead upto 50 m and all lifts. (Cement content: 220 kg / cum with
use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio
of CA--50:30:20, FA : 0.40 cum)
If water is to be brought from other place add only lead charges @ 500 ltr /
cum.
Labour Component (including contractor's profit and Overheads)

Providing and laying insitu vibrated M-20 ( 28 days cube compressive


strength not less than 20 N / sq mm ) grade cement concrete using 40 mm
down size approved, clean, hard, graded aggregates for cantiliver /
counterfort retaining walls including cost of all materials, machinery, labour,
formwork, scaffolding, cleaning, batching, mixing, placing in position, levelling,
IRR-CCDW-2-20 232
vibrating, finishing, curing etc., complete with initial lead upto 50 m and all
lifts. (Cement content: 320 kg / cum with use of super plasticiser(0.4% by wt.
of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
If water is to be brought from other place add only lead charges @ 500 ltr /
cum.
Labour Component (including contractor's profit and Overheads)

Providing and laying insitu vibrated M-15 ( 28 days cube compressive


strength not less than 15 N / sq mm ) grade cement concrete using 40 mm
down size approved, clean, hard, graded aggregates with placing and sinking
plums of size 150 to 80 mm upto 15 percent for gravity type retaining walls /
piers / abutments etc., including cost of all materials, machinery, labour,
formwork, scaffolding, cleaning, batching, mixing, placing in position, levelling,
IRR-CCDW-2-21 233
vibrating, finishing, curing etc.,complete with initial lead upto 50 m and all
lifts. (Cement content: 260 kg / cum with use of super plasticiser(0.4% by
wt. of cement),CA : 0.765cum, Blending Ratio of CA--50:30:20, FA : 0.34
cum, plums of size 150 to 80 mm : 0.25cum )
If water is to be brought from other place add only lead charges @ 500 ltr /
cum.
Labour Component (including contractor's profit and Overheads)
Providing and laying insitu vibrated M-15 ( 28 days cube compressive
strength not less than 15 N / sq mm ) grade cement concrete using 40 mm
down size approved, clean, hard,graded aggregates for cast in-situ pipes
including cost of all materials, machinery, labour, cleaning, batching, mixing,
placing in position, levelling, vibrating, finishing, curing etc., complete with
IRR-CCDW-2-22 234 initial lead upto 50 m and all lifts.(Cement content: 260 kg / cum with use of
super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA-50:30:20, FA : 0.40 cum)
If water is to be brought from other place add only lead charges @ 500 ltr /
cum.
Labour Component (including contractor's profit and Overheads)

Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength
not less than 15 N / sq mm ) grade cement concrete using 80 mm down size
approved, clean, hard, graded aggregates for cast in-situ pipes including cost of
all materials, labour, machinery, formwork, cleaning, batching, mixing, placing in
position, levelling, vibrating, finishing, curing etc., complete with initial lead
IRR-CCDW-2-23 235
upto 50 m and all lifts. (Cement content: 250 kg / cum with use of super
plasticiser(0.4% by wt. of cement),CA : 0.98cum, Blending Ratio of CA-35:30:20:15, FA : 0.35 cum)
If water is to be brought from other place add only lead charges @ 500 ltr /
cum.
Labour Component (including contractor's profit and Overheads)

cum

cum

1312.80

5539.60

cum

cum

1359.10

4905.90

cum

cum

1272.70

4633.50

cum

cum

cum

Itemwise unit rate


for Labour
Component
6

1202.20

4604.50

1247.70

30

Abstract of work items_UNit Rates for the year 2014-15

Chapterwise item
S.NO
No.
1

Item description

Unit

Rate

cum

7742.30

Providing and laying insitu vibrated M-20 ( 28 days cube compressive


strength not less than 20 N / sq mm ) grade cement concrete using 20 mm
down size approved, clean, hard, graded aggregates for deck slab & kerb
including cost of all materials,machinery, labour, formwork, scaffolding, cleaning,
batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
IRR-CCDW-2-24 236
complete with initial lead upto 50 m and all lifts. (Cement content: 330 kg /
cum with use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum,
Blending Ratio of CA--65:35, FA : 0.45 cum)
If water is to be brought from other place add only lead charges @ 500 ltr /
cum.
Labour Component (including contractor's profit and Overheads)

Providing and laying insitu vibrated M-20 ( 28 days cube compressive


strength not less than 20 N / sq mm ) grade cement concrete using 20 mm
down size approved, clean, hard, graded aggregates for columns and beams
including cost of all materials, labour, machinery, formwork, scaffolding,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing,
IRR-CCDW-2-25 237
curing etc.,complete with initial lead upto 50 m and all lifts. (Cement content:
330 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA :
0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
If water is to be brought from other place add only lead charges @ 500 ltr /
cum.
Labour Component (including contractor's profit and Overheads)

Providing and laying insitu M- 20 ( 28 days cube compressive strength not less
than 20 N / sqmm ) grade cement concrete using 20 mm down size approved,
clean, hard, graded aggregates for wearing coat including cost of all materials,
machinery, labour, formwork, cleaning, batching, mixing, placing in position in
alternate panels, levelling, compacting, finishing, curing, packing joints with
IRR-CCDW-2-26 238
asphalt mortar etc., complete with initial lead upto 50 m and all lifts. (Cement
content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA
: 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
If water is to be brought from other place add only lead charges @ 500 ltr /
cum.
Labour Component (including contractor's profit and Overheads)
Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength
not less than 20 N / sq mm ) grade cement concrete using 20 mm down size
approved, clean, hard, graded aggregates for troughs including cost of all
materials, machinery, labour, formwork, scaffolding, cleaning, batching, mixing,
placing in position,levelling, vibrating, finishing, curing etc., complete with initial
IRR-CCDW-2-27 239 lead upto 50 m and all lifts. (Cement content: 330 kg / cum with use of super
plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35,
FA : 0.45 cum)
If water is to be brought from other place add only lead charges @ 500 ltr /
cum.
Labour Component (including contractor's profit and Overheads)
IRR-CCDW-3

IRR-CCDW-3-1

Sinking RCC wells vertically for foundation of piers and abutments in all
kinds of soil, sand and soft rock by approved well sinking method including
cost of all materials, machinery, labour, kent - ledge arrangements, disposal of
240 excavated material as disposal of excavated material as directed etc., complete
with lead upto 50 m for disposal of excavated material.(diameter of well
6.00m) (Data adopted from MORTH)

Filling foundation wells with sand in layers of 25 to 30 cm and compacting


241 by watering, ramming as directed including cost of all materials, machinery,
labour etc., complete with initial lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-4

cum

1789.00

6708.70

cum

cum

1632.50

4238.60

cum

cum

1102.20

6066.20

cum

1514.30

FOUNDATION WELL SINKING WORKS :

Labour Component (including contractor's profit and Overheads)


for 3 to 10 meters for each running meter
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-3-2

cum

Itemwise unit rate


for Labour
Component
6

*Rm

3654.20

*Rm
*Rm
*Rm

5191.60

cum

506.10

cum

1507.80
1972.00

96.70

MASONRY WORKS :

31

Abstract of work items_UNit Rates for the year 2014-15

Chapterwise item
S.NO
No.
1

IRR-CCDW-4-1

Item description

Unit

Rate

cum

2074.90

Providing and constructing un-coursed rubble stone masonry with approved


stones in CM 1 : 4 proportion for sub-structure portions of return walls /
abutments etc., including cost of all materials, machinery, labour, scaffolding,
242
cleaning, packing cement mortar, wedging stone chips, curing etc., complete
with initial lead upto 50 m and all lifts.(Cement content: 143 kg / cum of
masonry, rubble stones : 0.85cum, FA : 0.40 cum,Stone Chips : 0.15 cum)
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-4-2

Providing and constructing un-coursed rubble stone masonry with approved


stones in CM 1 : 4 proportion for super-structure portions of return walls /
abutments etc., including cost of all materials, machinery, labour, scaffolding,
243
cleaning, packing cement mortar, wedging stone chips, curing etc., complete
with initial lead upto 50 m and all lifts.(Cement content: 143 kg / cum of
masonry, rubble stones : 0.85cum, FA : 0.40 cum,Stone Chips : 0.15 cum)
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-4-3

Providing and constructing coursed rubble masonry second sort in CM 1:4


proportion with stones from approved source including cost of all materials,
machinery, labour, scaffolding, ramps, cleaning, packing mortar, wedging stone
244 chips, finishing, curing etc., complete with initial lead upto 50 m and initial lift
upto 3 m.(Cement content: 133 kg / cum of masonry, rubble stones : 0.45cum,
FA : 0.35 cum,Stone Chips : 0.15 cum, Khandki stones 25 x 25 x 30 cm : 180
Nos, Header stones 25 x 25x 45 cm : 60 Nos)
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-4-4

Providing and constructing coursed rubble masonry first sort in CM 1:4


proportion with stones from approved source including cost of all materials,
machinery, labour, scaffolding, ramps, cleaning, packing mortar, wedging stone
245 chips, finishing, curing etc., complete with initial lead upto 50 m and initial lift
upto 3 m.(Cement content: 133 kg / cum of masonry, rubble stones : 0.45cum,
FA : 0.35 cum,Stone Chips : 0.15 cum, Khandki stones 25 x 25 x 30 cm : 180
Nos, Header stones 25 x 25x 45 cm : 60 Nos)
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-4-5

IRR-CCDW-4-6

IRR-CCDW-4-7

Providing cement mortar pointing to coursed rubble face stone masonry in


CM 1 : 2 proportion by volume including raking and cleaning joints for 50 mm
246 depth, pressing cement mortar into joints, cost of all materials, labour,
scaffolding, finishing, curing etc., complete with initial lead upto 50 m and all
lifts.
246
Providing cement mortar pointing to coursed rubble face stone masonry in
CM 1 : 3 proportion by volume including raking and cleaning joints for 50 mm
247 depth, pressing cement mortar into joints, cost of all materials, labour,
scaffolding, finishing, curing etc., complete with initial lead upto 50 m and all
lifts.
Labour Component (including contractor's profit and Overheads)
Providing 12 mm thick plastering in cement mortar 1:3 proportion by volume
248 including cost of all materials, machinery, labour, scaffolding, cleaning joints,
smooth finishing, curing etc., complete with initial lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-4-8

Providing 12 mm thick plastering in cement mortar 1:4 proportion by volume


249 including cost of all materials, machinery, labour, scaffolding, cleaning joints,
smooth finishing, curing etc., complete with initial lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-4-9

Providing 20 mm thick plastering in cement mortar 1:3 proportion by volume


250 including cost of all materials, machinery, labour, scaffolding, cleaning joints,
smooth finishing, curing etc., complete with initial lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)

Providing 20 mm thick plastering in cement mortar 1:4 proportion by volume


IRR-CCDW-4-10 251 including cost of all materials, machinery, labour, scaffolding, cleaning joints,
smooth finishing, curing etc., complete with initial lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)

cum

cum

692.10

2124.50

cum

cum

709.40

2590.20

cum

cum

795.80

2711.10

cum

sqm

916.80

108.40

sqm

sqm

81.70

102.10

sqm

sqm

81.70

154.10

sqm

sqm

115.40

146.80

sqm

sqm

115.40

218.80

sqm

sqm
sqm

Itemwise unit rate


for Labour
Component
6

154.10

206.50
154.10

32

Abstract of work items_UNit Rates for the year 2014-15

Chapterwise item
S.NO
No.
1
IRR-CCDW-5

IRR-CCDW-5-1

Item description

Unit

Rate

sqm

581.00

COPING & RAILING WORKS :


Providing and fixing 10 cm thick roughly dressed burnt stone slabs for coping
set in CM 1: 6 proportion by volume with pointing to joints in CM 1 : 3 proportion
252 by volume including cost of all materials, machinery, labour, finishing, curing
etc., complete with initial lead upto 50 m and all lifts.(Cement content: 7.5 kg /
sqm, FA : 0.030 cum/sqm, Burnt stone slab 10 cm thick 1.05 sqm/ sqm)
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-5-2

sqm

Providing and fixing 10 cm thick two line dressed burnt stone slabs for coping
set in CM 1: 6 proportion by volume with pointing to joints in CM 1 : 3 proportion
254 by volume including cost of all materials, machinery, labour, finishing, curing
etc., complete with initial lead upto 50 m and all lifts.(Cement content: 7.5 kg /
sqm, FA : 0.030 cum/sqm, Burnt stone slab 10 cm thick 1.05 sqm/ sqm)

sqm

Labour Component (including contractor's profit and Overheads)

IRR-CCDW-5-4

IRR-CCDW-5-5

Providing and laying insitu M-15 ( 28 days cube compressive strength not less
than 15 N / sqmm ) grade cement concrete using 20 mm down size approved
clean, hard, graded aggregates for coping slab including cost of all materials,
machinery, labour, formwork, cleaning surface, batching, mixing, placing in
255
position, levelling, compacting, finishing, curing etc., complete with initial lead
upto 50 m and initial lift upto 3 m. (Cement content: 300 kg / cum with use of
super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA-65:35, FA : 0.45 cum)
Labour Component (including contractor's profit and Overheads)
Providing and constructing protective railing consisting of in-situ railing posts
of size 15 x 15 cm at bottom, 10 x 10 cm at top and 75 cm height at 2 m centre
to centre in M-20 grade concrete using 20 mm down size graded aggregates and
with each post reinforced by 4 Nos. of 8 mm dia main bars embedded in kerb
256
concrete for a depth of 40 cm and 5 Nos. of 6 mm dia. stirrups including fixing 3
rows of 40 mm dia. GI pipes with one coat of red oxide primer and two coats of
synthetic enamel paint, cost of all materials, machinery, labour, formwork,
finishing, curing etc., complete with lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-6

IRR-CCDW-6-1

Laying and jointing 300 mm dia. NP- 2 class or IRC standard hume pipes in
CM 1 : 2 proportion by volume including cost of all materials ( excluding pipes
257 and collars ), machinery, labour, aligning, packing joints with hemp, finishing,
curing etc., complete with initial lead upto 50 m and all lifts.(Cement content:
9.9 kg / joint, FA : 0.01cum/joint, Hemp Yarn : 0.091kg/joint)

Laying and jointing 450 mm dia. NP- 2 class or IRC standard hume pipes in
CM 1 : 2 proportion by volume including cost of all materials ( excluding pipes
258 and collars ), machinery, labour, aligning, packing joints with hemp, finishing,
curing etc., complete with initial lead upto 50 m and all lifts.(Cement content:
17.4 kg / joint, FA : 0.022cum/joint, Hemp Yarn : 0.127kg/joint)
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-6-3

167.00

717.30

sqm

303.20

892.80

sqm

cum

478.80

5853.00

cum

Rm

1436.30

1362.80

Rm

158.50

HUME PIPE LAYING & JOINTING WORKS :

Labour Component (including contractor's profit and Overheads)

IRR-CCDW-6-2

sqm

Providing and fixing 10 cm thick one line dressed burnt stone slabs for coping
set in CM 1: 6 proportion by volume with pointing to joints in CM 1 : 3 proportion
253 by volume including cost of all materials, machinery, labour, finishing, curing
etc., complete with initial lead upto 50 m and all lifts.(Cement content: 7.5 kg /
sqm, FA : 0.030 cum/sqm, Burnt stone slab 10 cm thick 1.05 sqm/ sqm)
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-5-3

Itemwise unit rate


for Labour
Component
6

Laying and jointing 600 mm dia. NP- 2 class or IRC standard hume pipes in
CM 1 : 2 proportion by volume including cost of all materials ( excluding pipes
259 and collars ), machinery, labour, aligning, packing joints with hemp, finishing,
curing etc., complete with initial lead upto 50 m and all lifts.(Cement content:
24.8 kg / joint, FA : 0.025cum/joint, Hemp Yarn : 0.22kg/joint)
Labour Component (including contractor's profit and Overheads)

Joint

281.30

Joint

Joint

221.70

326.70

Joint

Joint

Joint

221.70

423.40

275.10

33

Abstract of work items_UNit Rates for the year 2014-15

Chapterwise item
S.NO
No.
1

IRR-CCDW-6-4

Item description

Unit

Rate

Joint

463.30

Laying and jointing 700 mm dia. NP- 2 class or IRC standard hume pipes in
CM 1 : 2 proportion by volume including cost of all materials ( excluding pipes
260 and collars ), machinery, labour, aligning, packing joints with hemp, finishing,
curing etc., complete with initial lead upto 50 m and all lifts.(Cement content:
32.1 kg / joint, FA : 0.031cum/joint, Hemp Yarn : 0.25kg/joint)
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-6-5

Laying and jointing 800 mm dia. NP- 2 class or IRC standard hume pipes in
CM 1 : 2 proportion by volume including cost of all materials ( excluding pipes
261 and collars ), machinery, labour, aligning, packing joints with hemp, finishing,
curing etc., complete with initial lead upto 50 m and all lifts.(Cement content:
39.6 kg / joint, FA : 0.039cum/joint, Hemp Yarn : 0.31kg/joint)
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-6-6

Laying and jointing 900 mm dia. NP- 2 class or IRC standard hume pipes in
CM 1 : 2 proportion by volume including cost of all materials ( excluding pipes
262 and collars ), machinery, labour, aligning, packing joints with hemp, finishing,
curing etc., complete with initial lead upto 50 m and all lifts.(Cement content:
44.6 kg / joint, FA : 0.045cum/joint, Hemp Yarn : 0.34kg/joint)
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-6-7

Laying and jointing 1000 mm dia. NP- 2 class or IRC standard hume pipes in
CM 1 : 2 proportion by volume including cost of all materials ( excluding pipes
263 and collars ), machinery, labour, aligning, packing joints with hemp, finishing,
curing etc., complete with initial lead upto 50 m and all lifts.(Cement content:
49.5 kg / joint, FA : 0.05cum/joint, Hemp Yarn : 0.377kg/joint)
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-6-8

Laying and jointing 1100 mm dia. NP- 2 class or IRC standard hume pipes in
CM 1 : 2 proportion by volume including cost of all materials ( excluding pipes
264 and collars ), machinery, labour, aligning, packing joints with hemp, finishing,
curing etc., complete with initial lead upto 50 m and all lifts.(Cement content:
56.9 kg / joint, FA : 0.058cum/joint, Hemp Yarn : 0.415kg/joint)
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-6-9

Laying and jointing 1200 mm dia. NP- 2 class or IRC standard hume pipes in
CM 1 : 2 proportion by volume including cost of all materials ( excluding pipes
265 and collars ), machinery, labour, aligning, packing joints with hemp, finishing,
curing etc., complete with initial lead upto 50 m and all lifts.(Cement content:
66.8 kg / joint, FA : 0.069cum/joint, Hemp Yarn : 0.453kg/joint)
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-7

IRR-CCDW-7-1

Providing rubble / boulder and sand filling behind abutment and return
266 walls in layers including cost of all materials, machinery, labour, watering,
ramming etc., complete with initial lead upto 50 m and initial lift upto 3 m.

Providing and filling murrum / gravely soil ( CNS soil ) for foundation or
around pipes including breaking clods, spreading in layers of 10 to 15 cm,
267
watering, compaction by earth masters to achieve density control of not less
than 95 percent etc., complete with lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)

IRR-CCDW-7-3

Joint

275.10

561.30

Joint

Joint

328.30

590.70

Joint

Joint

328.30

653.20

Joint

Joint

362.00

695.50

Joint

Joint

362.00

824.40

Joint

434.90

BACK FILLING & OTHER WORKS :

Labour Component (including contractor's profit and Overheads)

IRR-CCDW-7-2

Joint

Itemwise unit rate


for Labour
Component
6

Providing and filling murum / gravely soil ( CNS soil ) for foundation or
above pipes including breaking clods, spreading in layers of 10 to 15 cm,
268
watering, compaction by power roller to achieve density control of not less
than 98 percent etc., complete with lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)

cum

713.40

cum

cum

194.90

391.80

cum

cum

cum

245.40

262.70

97.60

34

Abstract of work items_UNit Rates for the year 2014-15

Chapterwise item
S.NO
No.
1

IRR-CCDW-7-4

IRR-CCDW-7-5

Chapter V
IRR-GAW

IRR-GAW-1-1

IRR-GAW-1-2

IRR-GAW-1-3

Item description

3
Providing and fixing one line dressed 111x35x25 cm thick IRC standard
kilometre stone in cement concrete M-10 grade with 40 mm down size
aggregates including excavating pit of size 70x45x40 cm, embedding the stone
269 by 30 cm in concrete, providing 2 coats synthetic enamel paint of approved
quality and colour to exposed surfaces and lettering as directed, cost of all
materials, labour, finishing, curing etc., complete with initial lead upto 50 m and
all lifts.
Labour Component (including contractor's profit and Overheads)
Providing and fixing one line dressed 65x15x10 cm thick IRC standard
hectometre stone in cement concrete M-10 grade with 40 mm down size
aggregates including excavating pit of size 50x45x40 cm, embedding the stone
270 by 30 cm in concrete, providing 2 coats synthetic enamel paint of approved
quality and colour to exposed surfaces and lettering as directed, cost of all
materials, labour, finishing, curing etc., complete with initial lead upto 50 m and
all lifts.
Labour Component (including contractor's profit and Overheads)

Rate

Each

1323.70

Each

Each

413.30

945.50

Each

350.60

GATES / HOISTS AND ALLIED WORKS

SPILLWAY RADIAL GATES


E.M Parts and anchorages
fabrication, supply, erection, testing and commissioning of embedded parts
for radial gate consists of sill beam, wall plates, anchor girders , yoke girders,
271
tie flats, trunnion supports etc., including cost of all materials, machinery, labour,
welding, finishing, with leads and lifts &all accessories
(without painting on sand-blasted or mechanical cleaning surfaces which are added
extra as per scedule of rates under itemsinthis chapter and add as applicable
separately)
Labour Component (including contractor's profit and Overheads)
RADIAL GATES
fabrication, supply, erection, testing and commissioning of radial gate
consisting of skin plate, stiffeners, horizontal girders, radial arms, trunnion
assemblies, tie beam, pulley supports, bracings, rubber seals, clamps etc., with
all accessories for spillway/canals including cost of all materials, machinery,
272
labour, seal fixing etc., complete as per specifications and approved
drawings
(without painting on sand-blasted or mechanical cleaning surfaces which are added
extra as per scedule of rates under itemsinthis chapter and add as applicable
separately)
Labour Component (including contractor's profit and Overheads)
RADIAL GATES-ROPE DRUM HOISTS WITH HOIST BRIDGES
fabrication, supply, erection, testing and commissioning of electrically
operated rope drum hoist of adequate capacity consisting of base frames,
rope drums,connecting shaft, gear system, brake system, electric motor, wire
ropes, gate position indicator, manual operation arrangement etc., with all
273
accessories for spillway radial gate including cost of all materials, machinery,
labour,, greasing, providing hand railing and approach staircase with gate to
hoist platform, , complete as per specifications and approved drawings
(without painting on sand-blasted or mechanical cleaning surfaces which are added
extra as per scedule of rates under itemsinthis chapter and add as applicable
separately)
Labour Component (including contractor's profit and Overheads)

IRR-GAW-1-4

Unit

Itemwise unit rate


for Labour
Component
6

RADIAL GATES
Walk way(cat walk)
Design, fabrication, supply, erection and commissioning of 1 metre wide
walkway connecting spillway piers / abutments at trunnion platform level
274 including cost of all materials, machinery, labour, cutting, etc., complete as per
specifications and approved drawings
(without painting on sand-blasted or mechanical cleaning surfaces which are added
extra as per scedule of rates under items in this chapter and add as applicable
separately)
Labour Component (including contractor's profit and Overheads)

tonne

149350.80

tonne

tonne

40637.80

134658.00

tonne

tonne
capacity

30982.70

42629.40

tonne
capacity

Rm

Rm

2471.30

101753.40

29505.30

35

Abstract of work items_UNit Rates for the year 2014-15

Chapterwise item
S.NO
No.
1

IRR-GAW-2-1

Item description

Unit

Rate

tonne

164527.20

VERTICAL LIFT GATES-EM PARTS


Design, fabrication, supply, erection and commissioning of embedded parts
consisting of sill beam, slide tracks, seal seats, guide rails, dogging sets for
storage of stoplog elements etc., with all accessories for spillway stop log gates
275
and other vertical lift elements including cost of all materials, machinery, labour,
etc., complete as per specifications and approved drawings
(without painting on sand-blasted or mechanical cleaning surfaces which are added
extra as per scedule of rates under items in this chapter and add as applicable
separately)
Labour Component (including contractor's profit and Overheads)

tonne

Itemwise unit rate


for Labour
Component
6

48353.90

vertical lift gates and stop log gate elements ( SLIDING GATES)

IRR-GAW-2-2

Design, fabrication, supply, erection, testing and commissioning of vertical lift


gates and stoplog gate elements, consisting of skin plate, horizontal and
vertical girders, stiffeners, lifting pins, bronze padded slide blocks/bearings,
guide shoes, rubber seals, clamps etc., with all accessories including cost of all
276
materials, machinery, labour, seal fixing etc.,complete as per specifications
and approved drawings
(without painting on sand-blasted or mechanical cleaning surfaces which are added
extra as perscedule of rates under items in this chapter and add as applicable
separately)2
Labour Component (including contractor's profit and Overheads)

IRR-GAW-2-3

IRR-GAW-2-4

STOP LOGS-automatic lifting beam


fabrication, supply, erection, testing and commissioning of automatic lifting
beam with all accessories for handling, lowering and lifting of spillway stop log
gate elements including cost of all materials, machinery, labour, cutting, aligning,
277 welding, finishing, etc., complete as per specifications and drawings with all
leads and lifts.
(without painting on sand-blasted or mechanical cleaning surfaces which are added
extra as per scedule of rates under items in this chapter and add as applicable
separately)
Labour Component (including contractor's profit and Overheads)
MOVING GANTRY CRANE-CLASS II
fabrication, supply, erection, testing and commissioning of adequate capacity
Class- II type moving gantry crane consisting of rail mounted gantry frame, top
platform with hand railing, long / cross travel arrangements, rope drums, gear
systems, electric motors, electro-magnetic brake system, cabin, control panel,
278 wire rope, ladder, motorised cable reeling drum etc., with all accessories for
operating spillway stop log gate elements and river sluice / canal sluice
emergency gates including cost of all materials, machinery, labour, etc.,
complete with all leads and lifts.
(without painting on sand-blasted or mechanical cleaning surfaces which are added
extra as per scedule of rates under items in this chapter and add as applicable
separately)
Labour Component (including contractor's profit and Overheads)

IRR-GAW-2-5

IRR-GAW-2-6

RAIL TRACK FOR GANTRY CRANE


Design, fabrication, supply, erection and commissioning of rail track using 45
kg / m standard rails on spillway bridge for movement of gantry crane for
handling and operating spillway stoplog gate elements / river sluice / canal sluice
279 emergency gate including cost of all materials, machinery, labour, complete as
per specifications
(without painting on sand-blasted or mechanical cleaning surfaces which are added
extra as per scedule of rates under items in this chapter and add as applicable
separately)
Labour Component (including contractor's profit and Overheads)
VERTICAL LIFT GATES/STOP LOGS - ROLLER MOUNTED
Design, fabrication, supply, erection, testing and commissioning of fixed wheel
type vertical lift service gate consisting of skin plate, vertical and horizontal
girders, wheels, stiffeners, lifting brackets, guide rollers, ballast blocks, teflon
claded rubber seals etc., with all accessories for river sluice / canal sluice vent
280 including cost of all materials, machinery, labour,welding ,aligning finishing seal
fixing etc.with all leads and lifts, complete as per specifications and approved
drawings
(without painting on sand-blasted or mechanical cleaning surfaces which are added
extra as per scedule of rates under items in this chapter and add as applicable
separately)
Labour Component (including contractor's profit and Overheads)

tonne

137213.20

tonne

tonne

35746.40

120072.60

tonne

tonne
capacity

17970.00

237820.70

tonne
capacity

Rm

18145.40

7320.50

Rm

tonne

tonne

444.70

135722.10

33808.20

36

Abstract of work items_UNit Rates for the year 2014-15

Chapterwise item
S.NO
No.
1

IRR-GAW-2-7

Item description

Unit

Rate

tonne
capacity

71620.70

VERTICAL LIFT GATES-ROPE DRUM HOIST UPTO 30 TON CAP. POWER


OPERATED
Design, fabrication, supply, erection, testing and commissioning of adequate
capacity rope drum hoist consisting of hoist platform, rope drum, gear system,
electric motor, electro-magnetic brake system, hand operation assembly, control
281
panel, wire rope, pulleys, ladder etc., with all accessories for operating river
sluice / canal sluice service gate including cost of all materials, machinery,
labour, , complete as per specifications and drawings with all leads and lifts
(without painting on sand-blasted or mechanical cleaning surfaces which are added
extra as per scedule of rates under items in this chapter and add as applicable
separately)
Labour Component (including contractor's profit and Overheads)

IRR-GAW-2-8

IRR-GAW-2-9

HOIST BRIDGE/ WITH TRESSELS


Design, fabrication, supply, erection and commissioning of structural steel
hoist bridge consisting of columns, beams, bracings, stiffeners, ties, chequered
plate covering, hand railing, ladder etc., with all accessories for supporting rope
282 drum hoist for operating barrage gates including cost of all materials, machinery,
labour, welding, finishing, etc., complete complete as per specifications and
drawings with all leads and lifts
(without painting on sand-blasted or mechanical cleaning surfaces which are added
extra as per scedule of rates under items in this chapter and add as applicable
separately)
Labour Component (including contractor's profit and Overheads)
ROPE DRUM HOIST WITHOUT HOIST BRIDGE FOR BARRAGE GATES
Design, fabrication, supply, erection, testing and commissioning of adequate
capacity rope drum hoist consisting of rope drum, pulleys, gear system,
electric motor, electro-magnetic brake system, manual operation assembly,
position indicator, control panel, wire rope etc., with all accessories for operating
283
vertical lift roller gates for barrage including cost of all materials, machinery,
labour, cutting, bending, aligning, anchoring, welding, finishing etc., complete
with all leads and lifts.
(without painting on sand-blasted or mechanical cleaning surfaces which are added
extra as per scedule of rates under items in this chapter and add as applicable
separately)
Labour Component (including contractor's profit and Overheads)

IRR-GAW-2-10

SCREW GEAR HOISTS INCLUDING PLATFORM ( UPTO 10 TON CAP)


Design, fabrication, supply, erection, testing and commissioning of adequate
capacity screw gear type hoist consisting of supporting structure, platform,
284 ladder etc., with all accessories for operating canal escape / regulator gate
including cost of all materials, machinery, labour, cutting, bending, aligning,
anchoring, welding,finishing etc.,complete with all leads and lifts.
(without painting on sand-blasted or mechanical cleaning surfaces which are added
extra as per scedule of rates under items in this chapter and add as applicable
separately)
Labour Component (including contractor's profit and Overheads)

IRR-GAW-2-11

MANUAL OPERATED ROPE DRUM HOISTS


Design, fabrication, supply, erection, testing and commissioning of adequate
capacity manually operated rope drum hoist consisting of hoist platform, rope
drum, gear system, brake system, wire rope, ladder etc., with all accessories for
285
operating canal regulator radial gate including cost of all materials, machinery,
labour, welding, finishing, cleaning, ., complete with all leads and lifts
(without painting on sand-blasted or mechanical cleaning surfaces which are added
extra as per scedule of rates under items in this chapter and add as applicable
separately)
Labour Component (including contractor's profit and Overheads)

tonne
capacity

tonne

2354.80

115727.40

tonne

tonne
capacity

30570.70

35397.90

tonne
capacity

tonne
capacity

997.80

33455.00

tonne
capacity

tonne
capacity

tonne
capacity

Itemwise unit rate


for Labour
Component
6

4508.50

76007.60

6040.10

37

Abstract of work items_UNit Rates for the year 2014-15

Chapterwise item
S.NO
No.
1

IRR-GAW-2-12
New Item 201415-2

IRR-GAW-2-13
New Item 201415-3

IRR-GAW-2-14
New Item 201415-4

IRR-GAW-3

IRR-GAW-3-1

IRR-GAW-3-2

Item description

Unit

Rate

Tonne

124326.20

OT SLUICE SHUTTERS Screw Gear Hoist Including Platform for below 5


Tons Capacity (Small Gates)
As per Guidelines of Chief Engineer, Central Designs Organization, Hyderabad
Specification drawing for Krishna Delta System
Fabrication, supply, erection, testing and commissioning of Embedded parts
286
consisting of supporting structure, platform etc. with all accessories for
operating canal escape/ regulator gate with all accessories including cost of all
materials, machinery, labour, cutting, bending, aligning, anchoring, welding,
finishing etc. complete as per Specification and approved drawings (without
painting on mechanical cleaning surfaces which are added extra as per schedule
of rates under items in this chapter and add as applicable separately)
Labour Component (including contractor's profit and Overheads)

OT SLUICE SHUTTERS EM parts for Below 5 Tons capacity (small gates)


As per Guidelines of Chief Engineer, Central Designs Organization, Hyderabad
Specification drawing for Krishna Delta System
Fabrication, supply, erection, testing and commissioning of Embedded parts
287
consisting of sil beam, slide tracks, seal seats, Guide plates etc. with all
accessories including cost of all materials, machinery, labour, etc. complete as
per specifications and approved drawings. (without painting on mechanical
cleaning surfaces which are added extra as per schedule of rates under items in
this chapter and add as applicable separately)
Labour Component (including contractor's profit and Overheads)
OT SLUICE SHUTTERS for Below 5 Tons capacity (small gates)
As per Guidelines of Chief Engineer, Central Designs Organization, Hyderabad
Specification drawing for Krishna Delta System
Fabrication, supply, erection, testing and commissioning of Sluice Shutters
consisting of skin plate, horizontal and vertical angles, stiffeners, rubber seals,
288
clamps with all accessories for sluice shutters including cost of all materials,
machinery, labour, seal fixing etc., complete as per specifications and approved
drawings (without painting on mechanical cleaning surfaces which are added
extra as per schedule of rates under items in this chapter and add as applicable
separately)
Labour Component (including contractor's profit and Overheads)

IRR-GAW-3-4

Tonne

22515.50

83401.00

Tonne

Tonne

18842.40

198547.40

Tonne

9581.20

SAND BLASTING AND PAINTING


Cleaning gates / hoists / embedded parts/lifting beams etc, to expose fresh
289 metal surface for painting by sand blasting method as per specifications
including cost of all materials, labour, machinery, scaffolding, etc., complete
with initial lead for sand upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)
painting of embedded metal parts and all types of gates, stoplogs,etc, on
sand blasted surfaces with one coat of inorganic zinc silicate (airless spray
preferred)70+/- 5 and two super coats with a total thickness of 300 microns
(each 150+/- 5) of solventless coaltar epoxy paint each coat 150 microns ( total
300 microns) cost of all materials, labour, scaffolding etc., complete with all leads
290 and all lifts
(Upstream surface of gates portion may be painted with solventless
coaltar epoxy brown paint instead of solventless coaltar black. The rate
for coaltar epoxy brown shall be adopted in data for Upstream side
painting)
Labour Component (including contractor's profit and Overheads)

IRR-GAW-3-3

Tonne

Itemwise unit rate


for Labour
Component
6

painting of Lifting beams,cat walks and other similar structures-painting


hoist machinery, on sand blasted surfaces with two coats of zinc phosphate
291
primer (airless spray preferred) 40microns/coat and twocoats of alkyd based
micaccous iron oxide paint , 65 microns/coat cost of all materials, labour,
scaffolding etc., complete with all leads and all lifts
Labour Component (including contractor's profit and Overheads)
HOISTS:STRUCTURAL COMPONENTS-painting structurals on sand blasted surfaces with two coats of zinc
phosphate primer (airless spray preferred) 40microns/coat and one coat 65+/292
5 of alkyd based micaccous iron oxide paint followed by two coats of synthetic
enamel paint 25 microns/coat cost of all materials, labour, scaffolding etc.,
complete with all leads and all lifts
Labour Component (including contractor's profit and Overheads)

sqm

431.70

sqm

sqm

84.40

499.40

sqm

sqm

180.00

350.60

sqm

sqm

sqm

138.20

432.10

180.00

38

Abstract of work items_UNit Rates for the year 2014-15

Chapterwise item
S.NO
No.
1

IRR-GAW-3-5

IRR-GAW-4

IRR-GAW-4-1

Item description

Unit

Rate

sqm

383.00

HOISTS:machineryCOMPONENTS-painting hoist machinery, on sand blasted surfaces with one coats of zinc
293
phosphate primer (airless spray preferred) 50microns/coat and three coats of
aluminium paint or synthetic enamel , 25 microns/coat cost of all materials,
labour, scaffolding etc., complete with all leads and all lifts
Labour Component (including contractor's profit and Overheads)

IRR-GAW-4-3

IRR-GAW-4-4

Chapter VI
IRR-PMW
IRR-PMW-1
IRR-PMW-1-1

IRR-PMW-1-2

IRR-PMW-1-3

IRR-PMW-1-4

180.00

PAINTING WITHOUT SAND BLASTING

E.M Parts OF ALL TYPES OF GATES


Surface cleaning of metal surfaces by chemical cleaners and then by hand and
power tool cleaners and removing dust. After cleaning,applying primary coat
with one coat of Protective Mastic to athickness of 70+5 microns ,followed by
294
finishing coats 2 coats with coal tar epoxy each coat with a DFT of 150+5
microns and total DFT of all coats including Primary coat should not be less than
350 microns with material, labour and all accessories with all leads and lifts
(in respect of Heavily rusted (30 to 40% rusted) surfaces)
Labour Component (including contractor's profit and Overheads)

IRR-GAW-4-2

sqm

Itemwise unit rate


for Labour
Component
6

sqm

568.60

sqm

180.00

Deleted from the year 2014-15 onwards

HOIST BRIDGES ,HOISTING EQUIPMENT AND CRANES,Etc,


Surface cleaning of metal surfaces by chemical cleaners and then by hand and
power tool cleaners and removing dust. After cleaning,applying primary coat
with two coats of Zinc chromite red oxide primer , followed by finishing coats
3 coats with synthetic enamel paint with material, labour,and all accessories
295
with all leads and lifts
where surface cleaning by sand blasting is not feasible and based on specific
recommendations of designers, it is to adopt surface preperation done
manually by hand and power tool after cleaning by chemical treatment to
remove grease, rust, scaling etc., and to form phasphate coating to prevent
further rusting, before applying primer painting.
Labour Component (including contractor's profit and Overheads)
WALK WAYS( CAT WALKS), LIFTING BEAMS,etc,
Surface cleaning of metal surfaces by chemical cleaners and then by hand and
power tool cleaners and removing dust. After cleaning,applying primary coat
296
with one coat of Zinc rich epoxy primer to a thickness of 40 microns ,followed
by finishing coats 2 coats with coal tar epoxy with material, labour, and all
accessories with all leads and lifts
Labour Component (including contractor's profit and Overheads)

sqm

401.70

sqm

sqm

180.00

477.80

sqm

121.40

PRELIMINARY AND MAINTENANCE WORKS


JUNGLE CLEARANCE :
Clearing thin jungle growth ( more than 50 percent open space ) including
297 bushes upto 30 cm / parthenium and other weeds including burning or
disposing off the same as directed etc., complete.
Labour Component (including contractor's profit and Overheads)
Clearing thick jungle growth ( less than 50 percent open space ) including
298 bushes upto 30 cm / parthenium and other weeds including burning or
disposing off the same as directed etc., complete.
Labour Component (including contractor's profit and Overheads)
Removing stumps, tree roots, roots of bamboo clusters etc., upto 1.50 m girth
299 including excavation, stacking the materials neatly and levelling the surface etc.,
complete with initial lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)

Removing stumps, tree roots, roots of bamboo cluster etc., with girth above
300 1.50 m and upto 3.0 m including excavation, stacking the materials neatly and
levelling the area etc., complete with initial lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)

sqm

1.20

sqm

sqm

1.30

1.90

sqm

Each

1.90

43.20

Each

Each
Each

43.20

97.30
97.30

39

Abstract of work items_UNit Rates for the year 2014-15

Chapterwise item
S.NO
No.
1
IRR-PMW-1-5

Item description

Unit

Rate

Each

311.20

Removing stumps, tree roots, roots of bamboo cluster etc., with girth above
301 3.0 m and upto 5.0 m including excavation, stacking the materials neatly and
levelling the area etc., complete with initial lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)

IRR-PMW-1-6

IRR-PMW-1-7

IRR-PMW-1-8

IRR-PMW-1-9

IRR-PMW-1-10

IRR-PMW-1-11

IRR-PMW-1-12

IRR-PMW-1-13

IRR-PMW-1-14

302

303

Additional rate for every 0.5 m increase in girth of tree stump/stumps of


bamboo cluster beyond 5 m
Labour Component (including contractor's profit and Overheads)
Cutting and stacking bamboos excluding removing stumps and roots etc.,
complete with initial lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)

Cutting and removing jauliflora bushes upto 1.5 m girth excluding removal
304 of stumps and including burning or disposing off the materials as directed with
initial lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)
Cutting and removing jauliflora bushes above 1.5 m upto 3.0 m girth
305 excluding removal of stumps and including burning or disposing off the materials
as directed with initial lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)
Cutting trees above 0.3 m and upto 0.6 m girth excluding removal of stumps
306 and including stacking the materials neatly as directed with initial lead upto 50
m and all lifts.
Labour Component (including contractor's profit and Overheads)
Cutting trees above 0.6 m and upto 1.2 m girth excluding removal of stumps
307 and including stacking the materials neatly as directed with initial lead upto 50
m and all lifts.
Labour Component (including contractor's profit and Overheads)
Cutting trees above 1.2 m and upto 1.8 m girth excluding removal of stumps
308 and including stacking the materials neatly as directed with initial lead upto 50
m and all lifts.
Labour Component (including contractor's profit and Overheads)
Cutting trees above 1.8 m and upto 2.4 m girth excluding removal of stumps
309 and including stacking the materials neatly as directed with initial lead upto 50
m and all lifts.
Labour Component (including contractor's profit and Overheads)
Cutting trees above 2.4 m and upto 3.0 m girth excluding removal of stumps
310 and including stacking the materials neatly as directed with initial lead upto 50
m and all lifts.
Labour Component (including contractor's profit and Overheads)

Each
Each

311.20
55.30

Each
Each

55.30
12.60

Each

Each

12.60

12.20

Each

Each

12.20

24.40

Each

Each

24.40

82.70

Each

Each

79.60

289.30

Each

Each

278.60

578.60

Each

Each

557.20

1157.10

Each

Each

Itemwise unit rate


for Labour
Component
6

1114.40

1872.50

Each

1787.00

For every 0.5 m increase in girth of tree beyond 3 m add


IRR-PMW-1-15

IRR-PMW-1-16

IRR-PMW-2

IRR-PMW-2-1

311

312

Additional rate for cutting tree for every 0.5 m increase in girth of tree beyond 3
m.
Labour Component (including contractor's profit and Overheads)
Cutting and burning or disposing off Apu / Jondu from marshy areas as
directed with initial lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)

656.40

Each
sqm

630.80
4.50

sqm

4.40

PRELIMINARY WORKS :
Earthwork excavation for trial pits / borrow pits and other investigation works
313 in all kinds of soil including boulders upto 30 cm dia and disposing off
excavated soil as directed with lead upto 10 m and lift upto 3 m.
Labour Component (including contractor's profit and Overheads)

IRR-PMW-2-2

Each

Earthwork excavation for trial pits / borrow pits and other investigation works
314 in soft rock including disposing off the excavated rock as directed with lead
upto 10 m and lift upto 3 m.
Labour Component (including contractor's profit and Overheads)

cum

222.90

cum

cum
cum

222.90

312.60
312.70

40

Abstract of work items_UNit Rates for the year 2014-15

Chapterwise item
S.NO
No.
1

IRR-PMW-2-3

IRR-PMW-2-4

Item description

3
Conducting geophysical investigation studies by electrical resistivity
method in stages of 5m for sub-surface details such as depth of formations,
shear zones, classification of strata, depth of water table etc., including cost of
315
all materials, equipments, labour, analysing and reporting the details of field
studies conducted etc., complete excluding cost of transportation
arrangements.
Labour Component (including contractor's profit and Overheads)
Drilling 80 mm dia hole through over-burden using casing shoe bit vertical or
inclined upto 10 degrees to vertical as directed including cost of all materials,
machinery, labour, water charges, reaming, collection of wash samples at
suitable intervals, logging and lebelling, supplying honne wood core box, fixing
casing pipes ( excluding cost of casing pipes ) etc., complete for depth
316 upto 30 m from surface.
1. For driiling through over-burden beyond 30 m from surface increase the rate
per Rm by 10 percent.
2. For providing HDPE or light black MS casing pipe add the cost of pipe per
Rm.
Labour Component (including contractor's profit and Overheads)

IRR-PMW-2-5

Drilling 76 mm dia ( NX ) core hole in hard rock using diamond core bit
vertical / inclined upto 10 degree to vertical as directed including cost of all
materials, machinery, labour, water charges, collection of core samples, logging
and lebelling, supplying honne wood core box and redrilling in case of collapse of
317 sides etc., complete for depth upto 30 m from surface.
1. For driiling in hard rock beyond 30 m upto 60 m from surface increase the rate
per Rm by 25 percent.
2. For driiling in hard rock beyond 60 m upto 90 m from surface increase the rate
per Rm by 40 percent.
Labour Component (including contractor's profit and Overheads)

IRR-PMW-2-5-A
(New Item 201415)-5

Drilling 76 mm dia ( NX ) core hole in all types of rocks (other than Hard
Rock) including Masonry/CC (where drilling is not possible by casing
shoe) using diamond core bit vertical / inclined upto 10 degree to vertical as
directed including cost of all materials, machinery, labour, water charges, and
318 redrilling in case of collapse of sides etc., complete for depth upto 30 m from
surface for Primary and Secondary Holes
1. For drilling in all types of rocks (other than hard rock) including masonry/CC
beyond 30 m upto 60 m from surface increase the rate per Rm by 25 percent.
2. For drilling in all types of rocks (other than hard rock) including masonry/CC
beyond 60 m upto 90 m from surface increase the rate per Rm by 40 percent.
Labour Component (including contractor's profit and Overheads)

IRR-PMW-2-5-B
(New Item 201415)-6

Drilling 76 mm dia ( NX ) core hole in all types of rocks (other than Hard
Rock) including Masonry/CC (where drilling is not possible by casing
shoe) using diamond core bit vertical / inclined upto 10 degree to vertical as
directed including cost of all materials, machinery, labour, water charges,
collection of core samples, logging and lebelling, supplying honne wood core box
319
and redrilling in case of collapse of sides etc., complete for depth upto 30 m
from surface for Test Holes
1. For drilling in all types of rocks (other than hard rock) including masonry/CC
beyond 30 m upto 60 m from surface increase the rate per Rm by 25 percent.
2. For drilling in all types of rocks (other than hard rock) including masonry/CC
beyond 60 m upto 90 m from surface increase the rate per Rm by 40 percent.
Labour Component (including contractor's profit and Overheads)

Unit

Rate

stage

283.90

stage

Rm

218.10

1162.20

Rm

Rm

390.30

5942.70

Rm

Rm

1553.00

3809.60

Rm

Rm

Rm

Itemwise unit rate


for Labour
Component
6

926.60

4599.60

927.20

41

Abstract of work items_UNit Rates for the year 2014-15

Chapterwise item
S.NO
No.
1

IRR-PMW-2-6

Item description

Unit

Rate

Rm

5781.60

Drilling 47 mm (BX )dia core hole in hard rock using diamond core bit vertical
/ inclined upto 10 degree to vertical as directed including cost of all materials,
machinery, labour, water charges,collection of core samples,logging, lebelling,
supplying honne wood core box and redrilling in case of collapse of sides etc.,
320 complete for depth upto 30 m from surface.
1. For drilling in hard rock beyond 30 m upto 60 m from surface increase the rate
per Rm by 25 percent.
2. For drilling in hard rock beyond 60 m upto 90 m from surface increase the rate
per Rm by 40 percent.
Labour Component (including contractor's profit and Overheads)

IRR-PMW-2-6-A
(New Item 201415)-7

Drilling 47 mm (BX )dia core hole in all types of rocks (other than Hard
Rock) including Masonry/CC (where drilling is not possible by casing shoe)
using diamond core bit vertical / inclined upto 10 degree to vertical as directed
321 including cost of all materials, machinery, labour, water charges, and redrilling
in case of collapse of sides etc., complete for depth upto 30 m
1. For drilling in all types of rocks (other than hard rock) including masonry/CC
beyond 30 m upto 60 m from surface increase the rate per Rm by 25 percent.
2. For drilling in all types of rocks (other than hard rock) including masonry/CC
beyond 60 m upto 90 m from surface increase the rate per Rm by 40 percent.
Labour Component (including contractor's profit and Overheads)

IRR-PMW-2-7

IRR-PMW-2-8

NOTE:

IRR-PMW-2-9

Providing and fixing 20 x 20 x 75 cm size roughly dressed boundary /


demarcation / chainage / arrow stones including cost of all materials, labour,
322
engraving marks, fixing in position, murum filling etc., complete with lead upto
50 m and all lifts.
Labour Component (including contractor's profit and Overheads)

IRR-PMW-3-1

IRR-PMW-3-2

IRR-PMW-3-3

Rm

Providing and fixing 20 x 20 x 75 cm size permanent bench mark stone in CC


1 :3 : 6 block of size 90 x 90 x 120 cm using 40 mm down size graded coarse
324 aggregate and providing 35 cm thick 30 cm high UCR masonry in CM 1 : 5
proportion protective wall alround the BM stone, including cost of all materials,
labour, dressing top surface of stone, engraving BM data

1553.00

3580.90

Rm

Each

926.60

136.90

Each

Providing and fixing 20 x 20 x 75 cm size temporary bench mark stone in CC


1 : 4 : 8 using 40 mm down size graded coarse aggregate including cost of all
Each
323
materials, labour, dressing top surface, engraving BM data etc.,complete with
lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)
Each
For providing 30 cm thick compacted murum bed in B.C soil area including additional
excavation for thickness of murum bedding add per
Each

Labour Component (including contractor's profit and Overheads)


IRR-PMW-3

Rm

Each

Itemwise unit rate


for Labour
Component
6

103.90

452.60
308.40
4.00

5625.10

Each

2716.10

MAINTENANCE WORKS :
Removing dry stone rock-toe / rivetment and filter layers below rock-toe/
325 rivetment including stacking all materials separately as directed with initial
lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)
Re-constructing 60 cm thick hand packed rough stone revetment with
through stones at 1.5 m c / c over a backing of 45 cm thick graded filter media
consisting of sand, 10 mm and 40 mm size graded aggregates satisfying filter
criteria laid in layers of 15 cm thick each using sand from approved quarry and
326
stones and filter aggregates obtained from revetment removed for reconstruction including cost of all machinery, labour, laying filter and stones to
specified slopes, wedging with chips, finishing etc. complete with initial lead
upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)
Re-constructing dry rubble rock-toe and filter media for rock-toe consisting
of sand 20 mm and 80 mm size graded aggregates satisfying filter criteria laid in
layers of 15 cm thick each using sand from approved quarry and stones and filter
327
aggregates obtained from rock-toe removed for re-construction including cost of
all machinery, labour, laying filter and stones to specified slopes, wedging with
chips, finishing etc. complete with initial lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)

cum

180.20

cum

sqm

180.20

215.40

sqm

cum

cum

134.90

244.80

193.20

42

Abstract of work items_UNit Rates for the year 2014-15

Chapterwise item
S.NO
No.
1
IRR-PMW-3-4

IRR-PMW-3-5

IRR-PMW-3-6

IRR-PMW-3-7

IRR-PMW-3-8

Item description

3
Removing and resetting disturbed Yarguntla / Shahabad / Talikot / PCC /
328 Other types of slab lining set in CM 1 : 3 including flush cement mortar
pointing in CM 1 : 3 with lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)
Removing and resetting disturbed dry rubble / khandki stone pitching 25 to
329 45 cm thick including packing, wedging, finishing etc., complete with all leads
and lifts.
Labour Component (including contractor's profit and Overheads)
Removing and refixing disturbed chainage / demarcation / hectometre /
330 guard stones including excavation, back filling etc., complete with all leads and
lifts.
Labour Component (including contractor's profit and Overheads)
Removing and refixing disturbed km stone / sign board / hecto-metre stone
etc., including excavation, back filling with available stuff after refixing, forming
331
base platform of size 90 x 90 x 7.5 cm including watering, ramming etc complete
with all leads and lifts.
Labour Component (including contractor's profit and Overheads)
Providing impervious hearting for breached / damaged portion of
embankment with soil from approved borrow areas in layers of 10 to 15 cm
before compaction including cost of all materials, machinery, labour, all
332 operations such as collection of soil, sorting out, spreading soil to specified
thickness, breaking clods, sectioning, watering, compacting each layer to density
control of not less than 98 percent or as stipulated by rolling or by using
mechanical tampers etc., complete with initial lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)

IRR-PMW-3-9

Providing pervious/semi-pervious casing for breached / damaged portion


of embankment with soil from approved borrow areas in layers of 10 to 15
cm before compaction including cost of all materials, machinery, labour, all
333 operations such as collection of soil, sorting out, spreading soil to specified
thickness, breaking clods, sectioning, watering, compacting each layer to density
control of not less than 98 percent or as stipulated by rolling or by using
mechanical tampers etc., complete with initial lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)

IRR-PMW-3-10

Providing impervious hearting for breached / damaged portion of


embankment with soil from approved dump areas in layers of 10 to 15 cm
before compaction including cost of all materials, machinery, labour, all
334 operations such as collection of soil,sorting out, spreading soil to specified
thickness, breaking clods, sectioning, watering, compacting each layer to density
control of not less than 98 percent or as stipulated by rolling or by using
mechanical tampers etc., complete with initial lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)

IRR-PMW-3-11

Providing pervious /semi-pervious casing for breached /damaged portion of


embankment with soil from approved dump areas in layers of 10 to 15 cm
before compaction including cost of all materials, machinery, labour, all
335 operations such as collection of soil, sorting out, spreading soil to specified
thickness, breaking clods, sectioning, watering, compacting each layer to density
control of not less than 98 percent or as stipulated by rolling or by using
mechanical tampers etc., complete with initial lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)

IRR-PMW-3-12

IRR-PMW-3-13

IRR-PMW-3-14

Repairing rain cuts / resectioning canal slopes to required lines and grades
336 as directed using available soil including dressing, clod breaking, packing,
tamping etc., complete with all leads and lifts.
Labour Component (including contractor's profit and Overheads)
Cleaning drainage gallery, adits, instrumentation galleries etc., by scrubbing
/ brushing including chiselling and removing leached lime deposit and disposing
337
off all the waste material out side adits in specified location etc., complete with
all leads and lifts.
Labour Component (including contractor's profit and Overheads)
Cleaning dam parapet inner face and top using oxalic acid and water by
338 scrubbing / brushing and washing to remove all surface coatings etc., complete
.
Labour Component (including contractor's profit and Overheads)

Unit

Rate

sqm

52.50

sqm

sqm

46.50

48.00

sqm

Each

48.00

60.80

Each

Each

60.80

136.80

Each

cum

136.80

185.60

cum

cum

27.80

212.30

cum

cum

33.20

168.60

cum

cum

26.60

192.10

cum

sqm

31.40

3.10

sqm

Rm

3.10

36.40

Rm

Rm
Rm

Itemwise unit rate


for Labour
Component
6

28.00

32.90
20.20

43

Abstract of work items_UNit Rates for the year 2014-15

Chapterwise item
S.NO
No.
1

Item description

Unit

Rate

cum

134.50

IRR-PMW-3-15

Deleted from the year 2014-15 onwards

IRR-PMW-3-16

Deleted from the year 2014-15 onwards

IRR-PMW-3-17

Deleted from the year 2014-15 onwards

IRR-PMW-3-18

Deleted from the year 2014-15 onwards

IRR-PMW-3-19

Deleted from the year 2014-15 onwards

IRR-PMW-3-20

IRR-PMW-3-21

Excavation and removal of silt and silt mixed with sand from canal bed in
dry condition including disposing off the same in spoil bank or on the canal
339
embankment in layers as directed etc., complete with initial lead upto 50 m
and all lifts.
Labour Component (including contractor's profit and Overheads)
Excavation and removal of silt or silt mixed with sand in slussy condition
from canal bed including disposing off the same in spoil bank or on the canal
340
embankment in layers as directed etc., complete with initial lead upto 50 m and
all lifts.
Labour Component (including contractor's profit and Overheads)

Providing homogeneous embankment using soil from approved borrow area


IRR-PMW-3-22
in layers of 25 to 30 cm before compaction including cost of all materials,
(new Item5 2010341 machinery, labour, all operations such as excavation, sorting out, transportation,
11) (for Minor
spreading soil in layer of specified thickness, breaking clods,
Works)
sectioning,etc.,complete with initial lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)
Providing homogeneous embankment using soil from approved borrow area
IRR-PMW-3-23
in layers of 25 to 30 cm before compaction including cost of all materials,
(new Item6 2010342 machinery, labour, all operations such as watering, compactingto density control
11) (for Minor
of not less than 95 percent or as stipulated using 8T roller etc., complete
Works)
with initial lead upto 1 km and all lifts.

cum

cum

134.50

168.20

cum

cum

168.20

95.50

cum

cum

13.10

46.10

6.40

Labour Component (including contractor's profit and Overheads)


Providing homogeneous embankment using soil from approved borrow area
IRR-PMW-3-24
in layers of 25 to 30 cm before compaction including cost of all materials,
(new Item7 2010- 343 machinery, labour, all operations such as compactingto density control of not
11)
less than 90 percent or as stipulated using 2T roller etc., complete with
initial lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)
(New Item 201213-3)
IRR-PMW-325(a)
IRR-PMW-325(b)
IRR-PMW-3-25(
c)
IRR-PMW-325(d)
IRR-PMW-325(e)
IRR-PMW-325(f)
(new Item 201213-6)

IRR-PMW-3-26
New Item 201415-8

COM-MWRK

Itemwise unit rate


for Labour
Component
6

cum

6.10

cum

1.10

Weed Removal by Manual Means


344
345
346
347
348

Removal of Water Hyacinth up to 30 cm thick


Removal of Water Hyacinth beyond 30 cm thick
Clearing Alchi Tilla
Removal of Jammu
Removal of Imponea, Cornea

349

Sqm

5.40

Sqm

7.40

Sqm

5.00

Sqm

4.20

Sqm

5.00

Sqm

1.60

Sqm

397.20

Removal of Natchu, goobi, thooti, etc.


PAINTING OF SLUICES FOR MAINTENANCE WORKS
Surface cleaning of metal surfaces by chemical cleaners and then by hand and
power tool cleaners and removing dust. After cleaniong, applying primary coat
350
with one coat of Zinc rich epoxy primer to a thickness of 100 microns, followed
by finishing coats 2 coats with Coal tar epoxy with material, labour, and all
accessories with all leads and lifts.
Labour Component (including contractor's profit and Overheads)

Sqm

145.92

New extra items-- common item for all earth works using only manual labour for all other works

44

Abstract of work items_UNit Rates for the year 2014-15

Chapterwise item
S.NO
No.
1

COM-MWRK-1

COM-MWRK-2

COM-MWRK-3

COM-MWRK-4

Item description

Unit

Rate

3
without involving contractors

cum

98.30

cum

118

cum

221.80

cum

440.30

(Manual)Excavation in all kinds of soil including boulders upto 0.30 m dia. for
foundations of canal cross drainage and other appurtenant structures and
placing excavated stuff neatly in specified dump area or disposing off the same
351
as directed etc., complete with initial lead upto 10 m and initial lift upto 1.5 m.
(WIthout involving the contractors for specified works )
With 3 Cum per day output
(Manual)Excavation in all kinds of soil/HDR including boulders upto 0.30 m
dia. for foundations of canal cross drainage and other appurtenant structures
and placing excavated stuff neatly in specified dump area or disposing off the
352
same as directed etc., complete with initial lead upto 10 m and initial lift upto
1.5 m. (WIthout involving the contractors for specified works )
With 2.5 Cum per day output

(Manual)Excavation in soft rock (including F&F rock) without blasting,


including boulders upto 0.30 m dia. for foundations of canal cross drainage and
other appurtenant structures and placing excavated stuff neatly in specified
353 dump area or disposing off the same as directed etc., complete with initial lead
upto 10 m and initial lift upto 1.5 m. (WIthout involving the contractors for
specified works )
Soft rock 1.33 Cum/Day
(Manual)Excavation in hard rock, including boulders upto 0.30 m dia. for
foundations of canal cross drainage and other appurtenant structures and
placing excavated stuff neatly in specified dump area or disposing off the same
354
as directed etc., complete with initial lead upto 10 m and initial lift upto 1.5 m.
(WIthout involving the contractors for specified works )
Hard rock 0.67Cum/ day

Itemwise unit rate


for Labour
Component
6

45

Abstract of leads and lifts - for the year 2014-15

COM-LDLFT

Abstract
LEAD, LIFT, LOADING AND UNLOADING CHARGES FOR MATERIALS
FOR THE YEAR: 2014-15

COM-LDLFT

1 For total lead upto 150 m ( including initial lead ) lead charges by head load only shall be adopted irrespective of
mode of conveyance.
2 For total lead exceeding 150 m conveyance by mechanical means only shall be adopted irrespective of
mode of conveyance.
3 The rates for loading at quarry including idle hire charges of trucks and hire charges per for each kilometer and
upto 5 km are cumulative and inclusive of total charges for preceding lead.
4 Unless otherwise specified lead charges for Earth / Sand / Gravel / Aggregates and Stones are for loose volume and
not for compacted or in-situ volume.
5 The rates for lift charges,lead charges hire cahrges are cumulative are cumulative and inclusive of rates for preceding
lift,load and hire charges
6 Lift charges are not payable where conveyance of materials is by mechanical means to final placing point.
7 Loading and unloading charges are not payable for conveyance by head load.
8 Loading charges are not payable for conveyance by mechanical means for disposal of excavated materials beyond
initial lead of 50 m wherever specified.
9 Loading and unloading charges are not payable for conveyance by mechanical means for disposal of excavated
materials beyond initial lead of 1 km wherever specified.
10 The rates for unloading of materials except earth, sand, gravel, coarse aggregate, rubble, size stone and cut stone
are inclusive of stacking.
11 Hire charges are per 1KM for tippers and trucks for tranport of materials from work site
to dump yard and other places are cumulative& includes previous km upto 5 kms
12 The lead & lift charges are inclusive of contractor's profit and overhead charges of 14%
13 During the BoCE meeting held on 24-05-2014, it is observed that in some of the estimates, Lead

Charges are being added directly to the material basic rates for arriving the finished item rate. In view
of that, the BoCE has instructed to see that while arriving the finished item rate, the lead
charges are to be added to the material basic rates only after deducting the provision of
"Contractor's Profit and Overhead charges"
COM-LDLFT-1 A. (Lead) Conveyance Charges for materials by head load
FOR THE YEAR: 2014-15

Sl No.

Total distance
( Total lead includes
initial lead )

Earth / Sand
/Gravel /
Murrum/ Lime/
Surki/ Size
stone / Cut
stone Rubble /
Coarse
3

1
2
3

Total lead upto 50 m


(covered by item rate)
Total lead upto 100 m
Total lead upto 150 m

initial lead
48.00
96.10

PCC slab/
Shahbad slab
Cement /
Reinforce-ment / CC block/
steel Str steel BS slab/ LateRs / tonne
rite / Wood
Rs / cum
4

initial lead
28.00
56.10

initial lead
61.10
122.30

Notes: 1. No loading or unloading charges are admissible for conveyance by head load.
2. For total lead exceeding 150 m conveyance charges by mechanical means only shall
be adopted irrespective of mode of conveyance.
3.The Lead & Lift Charges are inclusive of 14% Contractor's Profit and Over Head Charges
COM-LDLFT-2 B.( Lead) Conveyance charges for machinery per kilometer for transporting materials
by tippers and trucks excluding loading, unloading and idle hire charges of machinery
( No loading and unloading charges allowed for machinery loading and unloading )

Sl No.

Distance

(Lead)
charges for (Lead) charges
(Lead) charges
for trucks and
trucks and
(Lead) charges
(Lead) charges
for trucks and
tippers per
tippers for
for trucks and
for trucks and
tippers for
cu.meter for
Cement/
tippers for Earth
tippers per
Rubble/Size
PCC slabs/
Steel/ RCC
/ Sand /Gravel /
cu.meter for
stones/ Cut
Shahabad
poles/ AC &
Murrum/ Lime/
water/ 1000
Stones/ Coarse
slabs/ CC &
GI sheets/
Surki/ per
litres
aggregate per
Laterite blocks/
Packed
cu.meter
cu.meter
materials/tonn Wood/ cum
e
3
4
5
6
7

(Lead)
charge
s for
trucks
per
1000
Nos. of
Bricks
8

46

Abstract of leads and lifts - for the year 2014-15

1
2
3
4
5

Lead upto 1 km
Lead upto 2 km
Lead upto 3 km
Lead upto 4 km
Lead upto 5 km

31.50
44.10
58.90
71.50
84.10

30.40
42.60
58.90
71.50
84.10

19.00
26.60
36.80
44.70
52.60

44.70
62.60
86.60
105.10
123.70

for Every km beyond


5 km upto 30 km
6
12.60
12.60
7.90
18.50
for Every km beyond
30 km
7
10.50
10.50
6.60
15.50
Note:The Lead & Lift Charges are inclusive of 14% Contractor's Profit and Over Head Charges

18.80
26.30
35.00
42.50
50.00

50.70
71.00
94.60
114.90
135.20

7.50

20.30

6.30

16.90

COM-LDLFT-3 C. LOADING AND UNLOADING CHARGES BY MANUAL MEANS (idle hire charges of trucks are not added)

Sl No.

Description of item

Earth / Sand
Rubble/ size
/Gravel
stone/ cut stone/
Murrum/ / Surki/
Coarse
aggregate,Lime
Rs / cum
in Rs/cum

cement in
Rs/tonne

steel in
Rs./tonne

1
2
3
4
5
6
1
Loading
16.00
32.00
52.80
63.30
2
Unloading
8.00
16.00
52.80
63.30
Note:The Lead & Lift Charges are inclusive of 14% Contractor's Profit and Over Head Charges

brick work
Rs/1000 No

7
44.00
44.00

COM-LDLFT-4 D. LOADING AND UNLOADING CHARGES BY MANUAL MEANS (including idle hire charges of trucks )

Sl No.

Description of item

Earth / Sand
Rubble/ size
/Gravel
stone/ cut stone/
Murrum/ / Surki/
Coarse
aggregate,Lime
Rs / cum
in Rs/cum

cement in
Rs/tonne

steel in
Rs./tonne

brick work
Rs/1000 No

1
2
3
4
5
6
7
1
Loading
108.20
124.20
154.20
164.70
211.30
2
Unloading
38.60
62.10
154.20
164.70
211.30
Note:The Loading & Unloading Charges are inclusive of 14% Contractor's Profit and Over Head Charges

47

Abstract of leads and lifts - for the year 2014-15

COM-LDLFT-5 E. LOADING AND UNLOADING CHARGES BY MECHANICAL MEANS (including idle hire charges of trucks)

Sl No.

Description of item

Earth / Sand
Rubble/ size
/Gravel
stone/ cut stone/
Murrum/ / Surki/
Coarse
aggregate,Lime
Rs / cum
in Rs/cum

1
2
3
4
1
Loading
52.50
105.00
2
Unloading
15.90
15.90
Note:The Loading & Unloading Charges are inclusive of 14% Contractor's Profit and Over Head Charges
COM-LDLFT-6 F. LIFT CHARGES FOR MATERIALS BY HEAD LOAD

Sl No.

Total lift
( Total lift includes
initial lift )

Earth / Sand
/Gravel
Murrum/ Lime/
Surki/
Size stone / Cut
stone
Rubble / Coarse
aggregate
Rs / cum

Cement /
Reinforcement steel
Str steel
Rs / tonne

PCC slab/
Shahbad
slab / CC
block/ BS
slab / Laterite
/ Wood
Rs / cum

Initial lift

Initial lift

Initial lift

5.60

4.10

7.50

Total lift upto 3 m


(covered by item rate)
For Every 1.00 Lift
beyond initial lift of 3
meters

Note:The Lead & Lift Charges are inclusive of 14% Contractor's Profit and Over Head Charges

48

Dam and Allied Works - Item Unit Rates 2014-15

Chapter - I
DAM AND ALLIED WORKS - Standard Data

(WLL BE WITH E-N-C & TO INCORPORATE CHANGES YEARLY/ AS NEEDED)


FOR THE YEAR :2014-15
Index- code
IRR-DAW

DAM AND ALLIED WORKS - DATA RATES

Directions to add Seigniorage Charges and Additional Lead Charges


Seigniorage Charges:
1. The unit rate for work item in the Standard Data is exclusive of Seigniorage Charges wherever applicable.
2. The appropriate Seigniorage Charges for relevant materials are to be added to the Unit rate of work item while preparing the estimate. (i.e., to the data itself)
3. The Provision towards Contractor's Profit and Overhead charges should not be operated on the Seigniorage Charges while adding Seigniorage Charges
to the data in the estimate
Additional Lead and Lift Charges:
1. Unless otherwise specified the basic rates are inclusive of all lifts.
2. For concrete, masonry and reinforcement items wherever initial lead of 1km is considered in the basic rate, the additional lead charges are to be added
as follows:
Additional lead charges for Cement, Steel, sand, coarse aggregate, stones and stone chips shall be worked out for total lead involved and 1 km lead charges
included in basic rate shall be deducted from total lead charges. No loading and unloading charges shall be allowed for any item.
In case of Cement and Steel, Loading and unloading charges are already added in the work item while arriving the unit rate and hence should not be added again
Example:
Total lead for sand from approved sand quarry :
15 Km
Initial lead included in the basic rate in the SR :
1 Km
Additional lead charges : Lead charges for 5 km
Rs.
84.10
Lead charges for next 10 km
Rs.
126
Total lead charges for 15 km /cum
Rs.
210.10
Less 1 km initial lead charges /cum Rs.
31.50 (-)
Net additional lead charges / cum
Rs.
178.60

3. The Leads for Steel and Cement shall be from the nearest market place to the Project area
4. For earth/rockfill embankments wherever initial lead of 1km is considered in the basic rate, the additional lead charges are to be added as follows:
Additional lead charges for Earth, Murrum etc., shall be worked out for total lead involved and 1 km lead charges included in basic rate shall be deducted from total
lead charges. No loading and unloading charges shall be allowed for any item. (same as above)
Example:
Total lead for earth from approved borrow area :
15 Km
Initial lead included in the basic rate in the SR :
1 Km
Additional lead charges : Lead charges for 5 km
Rs.
84.10
Lead charges for next 10 km
Rs.
126
Total lead charges for 15 km /cum
Rs.
210.10
Less 1 km initial lead charges /cum Rs.
31.50 (-)
Net additional lead charges / cum
Rs.
178.60
5. The initial lead up to 50 m as mentioned in some standard data items is meant for manual lead within the working area. For conveyance of materials, the
lead required from quarry/Borrow area/ Dump Area to worksite shall be added to the data without deducting the 50 m initial lead charges
DAW - Work Items

IRR-DAW-1

EXCAVATION & FOUNDATION TREATMENT WORKS:

IRR-DAW-1-1

Excavation for foundation in all kinds of soil including boulders upto


0.30 m diameter for dam, spillway, intake structure and other appurtenant
works and placing the excavated soil neatly in dump area or disposing off
the same as directed etc., complete with initial lead upto 1 km
and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

Particulars

Unit

Quantity

NIL

0.00
0.00

Total cost of Materials

Rs:

UNIT
880 cum
Rate
Amount
in Rs.
in Rs
0.00 0.00
0.00 0.00
0.00

B. MACHINERY:
Sl No
1
2

Description
Shovel 0.85 cum capacity
Fuel / Energy charges
Dumpers 5 cum capacity 6 Nos

Unit
Hour
Hour
Hour

Quantity
8.00
8.00
48.00

Rate
Amount
in Rs.
in Rs
1706.60 13652.80
937.80 7502.40
580.70 27873.60

48

Dam and Allied Works - Item Unit Rates 2014-15

Fuel / Energy charges


Hour
Tipper 5 cum capacity 1 No
Hour
Fuel / Energy charges
Hour
Total hire charges of Machinery

48.00
8.00
8.00

429.70
446.70
322.20
Rs:

20625.60
3573.60
2577.60
75805.60

204.10
195.90
153.10
370.00
295.00
Rs:

Amount
in Rs
1632.80
9403.20
1224.80
370.00
4720.00
17350.80

C. LABOUR:
Sl No
1
2
3
4
5

Description

Unit

Quantity

Crew for Shovel


Crew for Dumper
Crew for Tipper
work inspector
mazdoor

Hour
Hour
Hour
Day
Day
Total cost of Labour
labour component/unit qty
19.70
Add contractor's profit and overhead charges
14% 2.80
labour component/unit qty (including contractor's profit)
22.50

Rate
in Rs.
8.00
48.00
8.00
1.00
16.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:

Total
D.Add for contractor's profit and overheads on (A+B+C)
Total cost for
880.00
Rate per
cum (A+B+C+D)/880

IRR-DAW-1-2

14%
cum

0.00
75805.60
17350.80
93156.40
13041.9
106198.30
120.70

Excavation for foundation in ordinary rock (including HDR) without blasting including
boulders above 0.3 m upto 0.6 m dia for dam, spillway, intake structure and
other appurtenant works and placing the excavated material neatly in dump
area or disposing off the same as directed etc., complete with initial lead
upto 1 km and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

Particulars

Unit

Quantity

NIL

0.00
0.00
Total cost of Materials

UNIT :
520 cum
Rate
Amount
in Rs.
in Rs.
0.00 0.00
0.00 0.00
Rs: 0.00

B. MACHINERY:
Sl No Description
1
2
3

Unit

Shovel 0.85 cum capacity


Fuel / Energy charges
Dumpers 5 cum capacity( 4 Nos)
Fuel / Energy charges
Tipper 5 cum capacity( 1 No)
Fuel / Energy charges
Total hire charges of Machinery

Quantity

Hour
Hour
Hour
Hour
Hour
Hour

8.00
8.00
32.00
32.00
8.00
8.00

Rate
in Rs.
1706.60
937.80
580.70
429.70
446.70
322.20
Rs:

Amount
in Rs
13652.80
7502.40
18582.40
13750.40
3573.60
2577.60
59639.20

Rate
in Rs.
204.10
195.90
153.10
370.00
345.00
295.00
Rs.

Amount
in Rs
1632.80
6268.80
1224.80
370.00
862.50
2950.00
13308.90

Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:

0.00
59639.20
13308.90
72948.10
10212.73
83160.83
159.90

C. LABOUR:
Sl No
1
2
3
4
5
6

Description

Unit

Crew for Shovel


Crew for Dumper
Crew for Tipper
work inspector
Crowbarman
mazdoor

Quantity

Hour
Hour
Hour
Day
Day
Day
Total cost of Labour
labour component/unit qty
25.60
Add contractor's profit and overhead charges
14% 3.60
labour component/unit qty (including contractor's profit)
29.20

8.00
32.00
8.00
1.00
2.50
10.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D.Add for contractor's profit and overheads on (A+B+C)
Total cost for
520.00
Rate per
cum (A+B+C+D)/520

14%
cum

49

Dam and Allied Works - Item Unit Rates 2014-15

IRR-DAW-1-3

DATA:

Excavation for foundation in hard rock (including F&F rock) requiring blasting including
boulders above 0.6 m upto 1.2 m dia. for dam, spillway, intake structure
and other appurtenant works and placing the excavated material neatly in
dump area or disposing off the same as directed etc., complete with initial
lead upto 1 km and all lifts.
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6

Description
Use rate of 1.5 m drill rod
Reconditioning charges @
Use rate of air hose 4 Nos.
Explosive small dia
Electric detonators
Fuse coil
Sundries
Total cost of Materials

Unit

UNIT :
520.00 cum.
Rate
Amount
in Rs.
in Rs
20.14 4350.24
435.02
10.94 284.38
70.00 7280.00
13.00 2002.00
11.00 3520.00
41.00 205.00
Rs. 18076.64

Quantity

Rm

216.00

10%
Hour
kg
Nos
Rm
LS

26.00
104.00
154.00
320.00
5.00

B. MACHINERY:
Sl No

Description

Unit

Quantity

Rate
in Rs.

1
2
3
4
5

Shovel 0.85 cum capacity


Fuel / Energy charges
Dumpers 5 cum capacity 4 Nos.
Fuel / Energy charges
Tipper 5 cum capacity 1 No
Fuel / Energy charges
Air compressor 8.5 cmm ( ele ) 2 Nos
Fuel / Energy charges
Jack hammers 4 Nos.
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour

8.00
8.00
32.00
32.00
8.00
8.00
13.00
13.00
26.00
26.00

1706.60
937.80
580.70
429.70
446.70
322.20
170.80
428.00
19.80
0.00
Rs:

Amount
in Rs
13652.80
7502.40
18582.40
13750.40
3573.60
2577.60
2220.40
5564.00
514.80
0.00
67938.40

C. LABOUR:
Sl No

Description

Unit

Quantity

Hour
Hour
Hour
Hour
Hour
Day
Day
Day
Day
Day
Day
Total cost of Labour
labour component/unit qty
45.60
Add contractor's profit and overhead charges
14% 6.40
labour component/unit qty (including contractor's profit)
52.00
1
2
3
4
5
6
7
8
9
10
11

Crew for Shovel


Crew for Dumper
Crew for Tipper
Crew for Air compressor
Crew for Jack hammer
work inspector
Blaster
Helper blaster
Crowbarman
Stone breaker
mazdoor

Rate
in Rs.
8.00
32.00
8.00
13.00
26.00
1.00
1.00
1.00
2.50
1.00
10.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
14%
cum.

D.Add for contractor's profit and overheads on (A+B+C)


Total cost for
520.00
Rate per
cum. (A+B+C+D)/520
IRR-DAW-1-3A
New Item 2014-15-1

204.10
195.90
153.10
142.40
284.70
370.00
440.00
345.00
345.00
345.00
295.00
Rs.

Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:

Amount
in Rs
1632.80
6268.80
1224.80
1851.20
7402.20
370.00
440.00
345.00
862.50
345.00
2950.00
23692.30

18076.64
67938.40
23692.30
109707.34
15359.03
125066.37
240.50

Excavation for foundation in hard rock (including F&F rock) including


boulders above 0.6 m upto 1.2 m dia. by controlled blasting and controlling fly rock by muffling arrangements
for dam, spillway, intake structure and other appurtenant works and other open foundation works and placing the excavated
material neatly in dump area or disposing off the same as directed etc., complete with initial lead upto 1 km and all leads

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

Description
Use rate of 1.5 m drill rod
Reconditioning charges @

Unit
Rm

Quantity
216.00

10%

UNIT :
520.00 cum.
Rate
Amount
in Rs.
in Rs
20.14 4350.24
435.02

50

Dam and Allied Works - Item Unit Rates 2014-15

2
3
4
3
4
5
6

Use rate of air hose 4 Nos.


Use rate of chain link wire mesh
Use rate of Sand Bags
Explosive small dia
Electric delay detonators
Fuse coil
Sundries
Total cost of Materials

Hour
Sq m
Nos.
kg
Nos
Rm
LS

26.00
500.00
190.00
104.00
154.00
320.00
5.00

10.94
64.93
74.45
70.00
23.00
11.00
41.00
Rs.

284.38
32462.50
14145.50
7280.00
3542.00
3520.00
205.00
66224.64

1706.60
937.80
1715.50
656.00
580.70
429.70
446.70
322.20
170.80
428.00
19.80
0.00
Rs:

Amount
in Rs
13652.80
7502.40
1715.50
656.00
18582.40
13750.40
3573.60
2577.60
2220.40
5564.00
514.80
0.00
70309.90

B. MACHINERY:
Sl No

Description

Unit

Quantity

Rate
in Rs.

1
2
3
4
5
6

Shovel 0.85 cum capacity


Fuel / Energy charges
Angle dozer 90 hp
Fuel / Energy charges
Dumpers 5 cum capacity 4 Nos.
Fuel / Energy charges
Tipper 5 cum capacity 1 No
Fuel / Energy charges
Air compressor 8.5 cmm ( ele ) 2 Nos
Fuel / Energy charges
Jack hammers 4 Nos.
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour

8.00
8.00
1.00
1.00
32.00
32.00
8.00
8.00
13.00
13.00
26.00
26.00

C. LABOUR:
Sl No

Description

1
2
3
4
5
6
7
8
9
10
11
12

Crew for Shovel


Crew for Angle dozer
Crew for Dumper
Crew for Tipper
Crew for Air compressor
Crew for Jack hammer
work inspector
Blaster
Helper blaster
Crowbarman
Stone breaker
mazdoor

Unit

Quantity

Hour
Hour
Hour
Hour
Hour
Hour
Day
Day
Day
Day
Day
Day
Total cost of Labour
labour component/unit qty
53.70
Add contractor's profit and overhead charges
14% 7.50
labour component/unit qty (including contractor's profit)
61.20

Rate
in Rs.
8.00
1.00
32.00
8.00
13.00
26.00
3.00
1.50
2.00
2.50
2.00
18.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
14%
cum.

D.Add for contractor's profit and overheads on (A+B+C)


Total cost for
520.00
Rate per
cum. (A+B+C+D)/520

IRR-DAW-1-4
(a)

204.10
204.10
195.90
153.10
142.40
284.70
370.00
440.00
345.00
345.00
345.00
295.00
Rs.

Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:

Amount
in Rs
1632.80
204.10
6268.80
1224.80
1851.20
7402.20
1110.00
660.00
690.00
862.50
690.00
5310.00
27906.40

66224.64
70309.90
27906.40
164440.94
23021.73
187462.67
360.50

Excavation for foundation in hard rock of all toughness by blasting


including boulders above 1.2 m dia. for dam, spillway, intake structure and
other appurtenant works and placing the excavated rock neatly in dump area
or stack yard including levelling as directed etc., complete with
initial lead upto 1 km and all lifts.

DATA:

RATE ANALYSIS

A. MATERIALS:
Sl No
Particulars
1
2
3
4
5
6
7

Use rate of drill rod 1.5 m long


Reconditioning charges @
Use rate of air hose 4 Nos.
Explosive small dia
Ordinary detonators
Electric detonators
Fuse coil
Sundries
Total cost of Materials

Unit

Quantity

Rm

310.00

10%
Hour
kg
Nos
Nos
Rm
LS

48.00
95.00
10.00
333.00
450.00
5.00

UNIT
320.00 cum
Rate
Amount
in Rs.
in Rs
26.85 8324.53
832.45
10.94 525.00
70.00 6650.00
9.00 90.00
13.00 4329.00
11.00 4950.00
41.00 205.00
Rs: 25905.98

51

Dam and Allied Works - Item Unit Rates 2014-15

B. MACHINERY:
Sl No
Description
1
2
3
4
5
6

Shovel 0.85 cum capacity


Fuel / Energy charges
Dumpers 5 cum capacity 3 Nos.
Fuel / Energy charges
Tipper 5 cum capacity 1 No
Fuel / Energy charges
Angle dozer 90 hp
Fuel / Energy charges
Air compressor 8.5 cmm (ele) 2 Nos.
Fuel / Energy charges
Jack hammers 4 Nos.
Fuel / Energy charges
Total hire charges of Machinery

C. LABOUR:
Sl No
Description

Unit

Quantity

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour

8.00
8.00
24.00
24.00
4.00
4.00
1.00
1.00
24.00
24.00
48.00
48.00

Unit

Quantity

1
2
3
4
5
6
7
8
9
10
11
12

Crew for Shovel


Hour
Crew for Dumper
Hour
Crew for Tipper
Hour
Crew for Dozer
Hour
Crew for Air compressor
Hour
Crew for Jack hammer
Hour
work inspector
Day
Blaster
Day
Helper blaster
Day
Crowbarman
Day
Stone breaker
Day
mazdoor
Day
Total cost of Labour
labour component/unit qty
88.10
Add contractor's profit and overhead charges
14% 12.30
labour component/unit qty (including contractor's profit)
100.40

8.00
24.00
4.00
1.00
24.00
48.00
1.00
1.00
1.00
1.00
2.00
6.00

IRR-DAW-1-5
(b)

Amount
in Rs
13652.80
7502.40
13936.80
10312.80
1786.80
1288.80
1715.50
656.00
4099.20
10272.00
950.40
0.00
66173.50

Rate
in Rs.

Amount
in Rs
1632.80
4701.60
612.40
204.10
3417.60
13665.60
370.00
440.00
345.00
345.00
690.00
1770.00
28194.10

204.10
195.90
153.10
204.10
142.40
284.70
370.00
440.00
345.00
345.00
345.00
295.00
Rs.

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:

Total
14%
cum

D.Add for contractor's profit and overheads on (A+B+C)


Total cost for
320.00
Rate per
cum (A+B+C+D)/320

Rate
in Rs.
1706.60
937.80
580.70
429.70
446.70
322.20
1715.50
656.00
170.80
428.00
19.80
0.00
Rs.

25905.98
66173.50
28194.10
120273.58
16838.3
137111.88
428.50

Excavation for foundation in hard rock of all toughness including boulders


above 1.2 m dia. by controlled blasting method and controlling fly-rock
by muffling arrangements for dam, spillway, intake structure and other
appurtenant structures etc., including placing and levelling the excavated
rock neatly in dump area or other place as directed etc., complete with
lead upto upto 1 km and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4
5
6
7
8
9

Use rate of drill rod 1.5 m length


Reconditioning charges @
Use rate of 50 m air hose 4 Nos.
Use rate of chain link wire mesh
Use rate of sand bag
Explosive small dia.
Ordinary detonators
Electric delay detonators
Fuse coil
Sundries
Total cost of Materials

B. MACHINERY:
Sl No
1
2
3

Particulars
Shovel 0.85 cum capacity
Fuel / Energy charges
Angle dozer 90 hp
Fuel / Energy charges
Dumpers 5 cum capacity 3 Nos.

Unit

Quantity

Rm
10%
Hour
sqm
Nos
kg
Nos
Nos
Rm
LS

Unit
Hour
Hour
Hour
Hour
Hour

UNIT :
480.00 cum
Rate
Amount
in Rs.
in Rs
26.85 12459.95
1246.00
10.94 765.63
64.93 46421.38
74.45 43181.00
70.00 10430.00
9.00 207.00
23.00 11500.00
11.00 7700.00
41.00 410.00
Rs: 134320.96

464.00
70.00
715.00
580.00
149.00
23.00
500.00
700.00
10.00

Quantity

Rate
in Rs.
12.00
12.00
2.00
2.00
36.00

1706.60
937.80
1715.50
656.00
580.70

Amount
in Rs
20479.20
11253.60
3431.00
1312.00
20905.20

52

Dam and Allied Works - Item Unit Rates 2014-15

Fuel / Energy charges


Hour
4
Tipper 5 cum capacity 1 No
Hour
Fuel / Energy charges
Hour
5
Air compressor 8.5 cmm ( ele ) 2 Nos
Hour
Fuel / Energy charges
Hour
6
Jack hammers 4 Nos.
Hour
Fuel / Energy charges
Hour
Total hire charges of Machinery
C. LABOUR:
Sl No
Description
Unit
1
2
3
4
5
6
7
8
9
10
11
13

36.00
4.00
4.00
35.00
35.00
70.00
70.00

Quantity

Crew for Shovel


Crew for Angle dozer
Crew for Dumper
Crew for Tipper
Crew for Air compressor
Crew for Jack hammer
work inspector
Blaster
Helper blaster
Crowbarman
Stone breaker
mazdoor

Hour
Hour
Hour
Hour
Hour
Hour
Day
Day
Day
Day
Day
Day
Total cost of Labour
labour component/unit qty
96.70
Add contractor's profit and overhead charges
14% 13.50
labour component/unit qty (including contractor's profit)
110.20

IRR-DAW-1-6
( c)

Note :

15469.20
1786.80
1288.80
5978.00
14980.00
1386.00
0.00
98269.80

204.10
204.10
195.90
153.10
142.40
284.70
370.00
440.00
345.00
345.00
345.00
295.00
Rs.

Amount
in Rs
2449.20
408.20
7052.40
612.40
4984.00
19929.00
1665.00
660.00
1035.00
862.50
862.50
5900.00
46420.20

Rate
in Rs.
12.00
2.00
36.00
4.00
35.00
70.00
4.50
1.50
3.00
2.50
2.50
20.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:

Total
14%
cum

D.Add for contractor's profit and overheads on (A+B+C)


Total cost for
480.00
Rate per
cum
(A+B+C+D)/480

429.70
446.70
322.20
170.80
428.00
19.80
0.00
Rs:

134320.96
98269.80
46420.20
279010.96
39061.53
318072.49
662.70

Excavation for foundation in hard rock of all toughness including boulders


above 1.2 m dia. by line drilling and smooth blasting and controlling
fly-rock by muffling arrangements for dam, spillway, intake structure and
other appurtenant structures etc., including dressing sides and bed to
required level / profile, placing and levelling the excavated rock neatly in
dump area or other place as directed etc., complete with lead upto 1 km and
all lifts.
i ) 1 m width of excavation along the face to be dressed shall be treated as
excavation by line drilling and smooth blasting.
ii) The rate includes controlling fly-rock wherever required.
iii ) The rate under this item shall be paid only on ascertaining that the
surface requiring dressing has come off neatly as per specifications or
atleast 50 percent of smooth blast holes are visible for inspection and are
spaced at specified interval.
iv ) In case, where the above criteria is not fulfilled payment shall be
restricted to the rate provided for excavation by normal or controlled blasting
as the case may be..

DATA:

RATE ANALYSIS
UNIT :
A. MATERIALS:
Sl No
Particulars
1
2
3
4
5
6
7

Use rate of drill rod 1.5 m length


Reconditioning charges @
Use rate of 50 m air hose 4 Nos.
Explosive small dia.
Ordinary detonators
Electric delay detonators
Fuse coil
Sundries
Total cost of Materials

B. MACHINERY:
Sl No
Description
1
2
3
4

Shovel 0.85 cum capacity


Fuel / Energy charges
Angle dozer 90 hp
Fuel / Energy charges
Dumpers 5 cum capacity 3 Nos.
Fuel / Energy charges
Air compressor 8.5 cmm ( ele ) 2 Nos

Unit

Quantity

Rm

138.00

10%
Hour
kg
Nos
Nos
Rm
LS

22.00
10.50
2.00
76.00
140.00
2.00

Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour

Quantity
1.00
1.00
0.25
0.25
3.00
3.00
11.00

40.00 cum
Rate
Amount
in Rs.
in Rs
26.85 3705.76
370.58
10.94 240.63
70.00 735.00
9.00 18.00
23.00 1748.00
11.00 1540.00
41.00 82.00
Rs. 8439.97

Rate
in Rs.
1706.60
937.80
1715.50
656.00
580.70
429.70
170.80

Amount
in Rs
1706.60
937.80
428.88
164.00
1742.10
1289.10
1878.80

53

Dam and Allied Works - Item Unit Rates 2014-15

Fuel / Energy charges


Hour
Jack hammers 4 Nos.
Hour
Fuel / Energy charges
Hour
Total hire charges of Machinery

C. LABOUR:
Sl No

Description

Unit

11.00
22.00
22.00

Quantity

1
2
3
4
5
6
7
8
9
10
11

Crew for Shovel


Hour
Crew for Angle dozer
Hour
Crew for Dumper
Hour
Crew for Air compressor
Hour
Crew for Jack hammer
Hour
work inspector
Day
Blaster
Day
Helper blaster
Day
Crowbarman
Day
Stone breaker
Day
mazdoor
Day
Total cost of Labour
labour component/unit qty
254.60
Add contractor's profit and overhead charges
14% 35.60
labour component/unit qty (including contractor's profit)
290.20
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

IRR-DAW-1-7

204.10
204.10
195.90
142.40
284.70
370.00
440.00
345.00
345.00
345.00
295.00
Rs.

Amount
in Rs
204.10
51.03
587.70
1566.40
6263.40
185.00
220.00
172.50
172.50
172.50
590.00
10185.13

Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:

8439.97
13290.88
10185.13
31915.98
4468.24
36384.22
909.60

Total
14%
cum

Preparing foundation bed for masonry or concrete by benching,


stepping, removing all loose material by wedging / chiselling and disposing
off the same as directed and cleaning the surface with air and water jet etc.
,complete with initial lead upto 50 m and all lifts.

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1

Unit

Quantity

NIL

UNIT:
100.00 sqm
Amount
in Rs
0.00 0.00
0.00 0.00
Rs. 0.00

Rate
in Rs.
0.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No
Description
1
2

Air compressor 8.5 cmm ( ele )


Fuel / Energy charges
Pump 5 hp ( ele )
Fuel / Energy charges
Total hire charges of Machinery

C. LABOUR:
Sl No
Description

Unit

Quantity

Hour
Hour
Hour
Hour

Unit

1
2
3
4
5

Crew for Air compressor


Hour
Crew for Pump
Hour
Stone breaker
Day
mazdoor
Day
Crowbar man
Day
Total cost of Labour
labour component/unit qty
23.30
Add contractor's profit and overhead charges
14% 3.30
labour component/unit qty (including contractor's profit)
26.60

Rate
in Rs.
1.00
1.00
1.00
1.00

Quantity

D.Add for contractor's profit and overheads on (A+B+C)


Total cost for
100.00
Rate per
sqm
(A+B+C+D)/100

170.80
428.00
3.00
38.00
Rs.

Amount
in Rs
170.80
428.00
3.00
38.00
639.80

142.40
72.10
345.00
295.00
345.00
Rs:

Amount
in Rs
142.40
72.10
690.00
737.50
690.00
2332.00

Rate
in Rs.
1.00
1.00
2.00
2.50
2.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

IRR-DAW-1-8

4708.00
435.60
0.00
13290.88

Rate
in Rs.
1.00
0.25
3.00
11.00
22.00
0.50
0.50
0.50
0.50
0.50
2.00

D.Add for contractor's profit and overheads on (A+B+C)


Total cost for
40.00
Rate per
cum
(A+B+C+D)/40

428.00
19.80
0.00
Rs:

Total
14%
sqm

Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:

0.00
639.80
2332.00
2971.80
416.05
3387.85
33.90

Preparing foundation bed for cut-off trench filling in rock portion by

54

Dam and Allied Works - Item Unit Rates 2014-15

removing all loose materials by wedging / chiselling and disposing off the
same as directed etc., complete with initial lead upto 50 m and all lifts.
DATA

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1

Unit

Quantity

NIL

UNIT:
100.00 sqm
Amount
in Rs
0.00 0.00
0.00 0.00
Rs. 0.00

Rate
in Rs.
0.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No
Description
1

Unit

Quantity

NIL

Rate
in Rs.

Amount
in Rs
0.00 0.00
0.00 0.00
Rs. 0.00

0.00
0.00
Total cost of Machinery

C. LABOUR:
Sl No
Description
1
2
3

Crowbar man
Stone breaker
mazdoor

Unit

Quantity

Day
Day
Day

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Rate
in Rs.
2.00
2.00
2.00

345.00
345.00
295.00
Rs:

19.70
14% 2.80
22.50

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

NOTE:

Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:

Total
14%
sqm

D.Add for contractor's profit and overheads on (A+B+C)


Total cost for
100.00
Rate per
sqm
(A+B+C+D)/100

IRR-DAW-1-9

Amount
in Rs
690.00
690.00
590.00
1970.00

0.00
0.00
1970.00
1970.00
275.8
2245.80
22.50

Drilling 45 to 50 mm dia holes vertical or inclined upto 10 degrees to


vertical in rock /masonry/ concrete by percussion drilling using waggon
drill or any other suitable equipment including cost of all materials,
machinery, labour, redrilling through partially set grout wherever required
etc., complete.
for drilling upto 6 m depth from surface.
The item rate for drilling through rock / masonry / concrete includes redrilling
through partially set grout, if any, in the portion of hole already grouted.

Data

RATE ANALYSIS
UNIT:
A. MATERIALS:
Sl No
Particulars
1
2
3

Use rate of cross bit 50 mm dia


Use rate of 50 mm dia air hose 50 m
Use rate of extension rod 4.5 m
Total cost of Materials

B. MACHINERY:
Sl No
Description
1
2
3

Waggon drill
Fuel / Energy charges
Air compressor 8.5 cmm ( ele )
Fuel / Energy charges
Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No
Description
1
2
3

Unit

Quantity

Rm
Hour
Rm

Unit

96.00
8.00
96.00

Quantity

Hour
Hour
Hour
Hour
LS

Unit

Crew for Waggon drill


Hour
Crew for Air compressor
Hour
mazdoor
Day
Total cost of Labour
labour component/unit qty
38.40
Add contractor's profit and overhead charges
14% 5.40
labour component/unit qty (including contractor's profit)
43.80

96.00 Rm
Rate
Amount
in Rs.
in Rs
62.50 6000.00
18.63 149.00
6.36 610.56
Rs. 6759.56

Rate
in Rs.
8.00
8.00
8.00
8.00
2.00

Quantity

188.50
0.00
170.80
428.00
41.00
Rs:

Amount
in Rs
1508.00
0.00
1366.40
3424.00
82.00
6380.40

244.90
142.40
295.00
Rs:

Amount
in Rs
1959.20
1139.20
590.00
3688.40

Rate
in Rs.
8.00
8.00
2.00

ABSTRACT:

55

Dam and Allied Works - Item Unit Rates 2014-15

A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
14%
Rm

D.Add for contractor's profit and overheads on (A+B+C)


Total cost for
96.00
Rate per
Rm
(A+B+C+D)/96
Upto 6 m from surface
Beyond 6 m upto 12 m from surface :
Upto 6 m from surface
Rate per Rm
Add for redrilling through partially set grout / additional
extension rods / reduction in rate of drilling etc @
Beyond 6 m upto 12 m from surface
Rate / Rm
Beyond 12 m upto 18 m from surface :
For 6 m to 12 m from surface
Rate per Rm
Add for redrilling through partially set grout / additional
extension rods / reduction in rate of drilling etc @
Beyond 12 m upto 18 m from surface
Rate / Rm
Beyond 18 m upto 24 m from surface
For 12 m to 18 m from surface
Rate per Rm
Add for redrilling through partially set grout / additional
extension rods / reduction in rate of drilling etc @
Beyond 18 m upto 24 m from surface
Rate / Rm
Beyond 24 m upto 30 m from surface
For 18 m to 24 m from surface
Rate per Rm
Add for redrilling through partially set grout / additional
extension rods / reduction in rate of drilling etc @ :
Beyond 24 m upto 30 m from surface
Rate / Rm
Beyond 30 m upto 36 m from surface
For 24 m to 30 m from surface
Rate per Rm
Add for redrilling through partially set grout / additional
extension rods / reduction in rate of drilling etc @
Beyond 30 m upto 36 m from surface
Rate / Rm
Beyond 36 m upto 42 m from surface
For 30 m to 36 m from surface
Rate per Rm
Add for redrilling through partially set grout / additional
extension rods / reduction in rate of drilling etc @
Beyond 36 m upto 42 m from surface
Rate / Rm
Beyond 42 m upto 48 m from surface
For 36 m to 42 m from surface
Rate per Rm
Add for redrilling through partially set grout / additional
extension rods / reduction in rate of drilling etc @
Beyond 42 m upto 48 m from surface
Rate / Rm

IRR-DAW-1-10

Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:

6759.56
6380.40
3688.40
16828.36
2355.97
19184.33
199.80
199.80

Rs: 199.80
10%

Rs: 19.98
Rs: 219.80
Rs: 219.80

10%

Rs: 21.98
Rs: 241.80
:
Rs: 241.80

10%

Rs: 24.18
Rs: 266.00
:
Rs: 266.00

10%

Rs 26.60
Rs: 292.60
:
Rs: 292.60

10%

Rs: 29.26
Rs: 321.90
:
Rs: 321.90

10%

Rs: 32.19
Rs: 354.10
Rs: 354.10

10%

Rs: 35.41
Rs: 389.50

Flushing grout holes of all sizes with water and air jets alternatively for an
average period of 30 minutes including water intake observations after
flushing, cost of all materials, machinery, labour etc., complete.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3

Use rate of air hose 2 Nos x 8 hrs


Use rate of water hose 2 Nos x 8 hrs
Sundries
Total cost of Materials

B. MACHINERY:
Sl No
Description
1
2
3

Unit

Quantity

Hour
Hour
LS

Unit

16.00
16.00
2.00

Quantity

Air compressor 8.5 cmm ( ele )


Hour
Fuel / Energy charges
Hour
Pump 5 hp ( ele )
Hour
Fuel / Energy charges
Hour
Sundries
LS
Total hire charges of Machinery

C. LABOUR:
Sl No
Description

Unit

1 Crew for Air compressor


Hour
2 Crew for Pump
Hour
3 mazdoor
Day
Total cost of Labour
labour component/unit qty
15.10
Add contractor's profit and overhead charges
14% 2.10
labour component/unit qty (including contractor's profit)
17.20

UNIT :
192.00 Rm.
Rate
Amount
in Rs.
in Rs
10.94 175.04
13.69 219.04
41.00 82.00
Rs: 476.08

Rate
in Rs.
8.00
8.00
8.00
8.00
2.00

Quantity

170.80
428.00
3.00
38.00
41.00
Rs:

Amount
in Rs
1366.40
3424.00
24.00
304.00
82.00
5200.40

142.40
72.10
295.00
Rs:

Amount
in Rs
1139.20
576.80
1180.00
2896.00

Rate
in Rs.
8.00
8.00
4.00

56

Dam and Allied Works - Item Unit Rates 2014-15

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
14%
Rm.

D.Add for contractor's profit and overheads on (A+B+C)


Total cost for
192.00
Rate per
Rm.
(A+B+C+D)/192

IRR-DAW-1-11
(a)

Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:

Consolidation grouting with neat cement grout mix of suitable


consistency under specified pressure as directed in drilled holes by stage
grouting method including cost of all materials, machinery, labour,
redrilling if necessary etc.,complete with initial lead upto 1 km and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3

Cement
Use rate of 50 m pressure hose
Sundries ( packer assembly etc )
Total cost of Materials

B. MACHINERY:
Sl No
Description
1
2
3

Unit

Quantity

tonne
Hour
LS

Unit

1.05
8.00
3.00

Quantity

Grouting equipment
Hour
Fuel / Energy charges
Hour
Pump 5 hp ( ele )
Hour
Fuel / Energy charges
Hour
Sundries
LS
Total hire charges of Machinery

C. LABOUR:
Sl No
Description

Unit

UNIT :
1.05 tonne
Rate
Amount
in Rs.
in Rs
4000.00 4200.00
10.94 87.52
41.00 123.00
Rs: 4410.52

Rate
in Rs.
8.00
8.00
2.00
2.00
2.00

Quantity

1
2
3

Crew for Grout pump


Hour
Crew for Pump
Hour
mazdoor ( cement handling)
Day
Total cost of Labour
labour component/unit qty
2434.90
Add contractor's profit and overhead charges
14% 340.90
labour component/unit qty (including contractor's profit)
2775.80

8.00
2.00
2.00

227.80
72.10
295.00
Rs:

Amount
in Rs
1822.40
144.20
590.00
2556.60

Rs:
Rs:
Rs:
Rs:
Rs.

Total
14%

D.Add for contractor's profit and overheads on (A+B+C)


Lead Charges for 1Km for Cement 1.05 Tonne @ (including
Loading and Unloading Charges)
Total cost for
1.05
Rate per
tonne
(A+B+C+D)/1.05

24.90
38.00
3.00
38.00
41.00
Rs:

Amount
in Rs
199.20
304.00
6.00
76.00
82.00
667.20

Rate
in Rs.

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

IRR-DAW-1-12
(b)

476.08
5200.40
2896.00
8572.48
1200.15
9772.63
50.90

124.60 Rs/Tonne
tonne

4410.52
667.20
2556.60
7634.32
1068.8

130.83
Rs: 8833.95
Rs: 8413.30

Curtain grouting with neat cement grout mix of suitable consistency


under specified pressure as directed in drilled holes by stage grouting
method including cost of all materials, machinery, labour, redrilling if
necessary etc., complete with initial lead upto 1 km and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4

Cement
Use rate of 100 m pressure hose
Use rate of 400 m GI pipe
Sundries ( packer assembly etc )
Total cost of Materials

B. MACHINERY:
Sl No
Description
1
2

Grouting equipment
Fuel / Energy charges
Pump 5 hp ( ele )
Fuel / Energy charges

Unit

Quantity

tonne
Hour
Hour
LS

Unit
Hour
Hour
Hour
Hour

1.05
8.00
8.00
3.00

Quantity

UNIT :
1.05 tonne
Rate
Amount
in Rs.
in Rs
4000.00 4200.00
21.88 175.04
6.8 54.40
41.00 123.00
Rs: 4552.44

Rate
in Rs.
8.00
8.00
2.00
2.00

24.90
38.00
3.00
38.00

Amount
in Rs
199.20
304.00
6.00
76.00

57

Dam and Allied Works - Item Unit Rates 2014-15

Sundries

LS
Total hire charges of Machinery

C. LABOUR:
Sl No
Description

2.00

Unit

Quantity

1
2
3
4

Crew for Grout pump


Hour
Crew for Pump
Hour
Pipe fitter
Day
mazdoor ( cement handling )
Day
Total cost of Labour
labour component/unit qty
3134.90
Add contractor's profit and overhead charges
14% 438.90
labour component/unit qty (including contractor's profit)
3573.80

41.00 82.00
Rs: 667.20

Rate
in Rs.
8.00
2.00
1.00
3.00

227.80
72.10
440.00
295.00
Rs:

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
14%

D.Add for contractor's profit and overheads on (A+B+C)


Lead Charges for 1Km for Cement 1.05 Tonne @ (including
Loading and Unloading Charges)
Total cost for
1.05
Rate per
tonne
(A+B+C+D)/1.05

IRR-DAW-1-13

Rs:
Rs:
Rs:
Rs:
Rs.

124.60 Rs/Tonne
tonne

Amount
in Rs
1822.40
144.20
440.00
885.00
3291.60

4552.44
667.20
3291.60
8511.24
1191.57

130.83
Rs: 9833.64
Rs: 9365.40

Providing and fixing 25 mm dia 3 m long cold twisted deformed steel


dowel bars with one end driven into 45 to 50 mm diameter 1.50 m deep
hole drilled in bed rock and other end provided with L-bend for embedding in
concrete / masonry of over flow / non-over flow blocks and other appertenant
works including cost of drilling and cleaning hole, filling hole with cement
mortar 1 : 1 proportion, driving anchor rod, cost of all materials, machinery,
labour etc., complete with initial lead upto 1 km and all lifts.
Consider 25 anchor rods for analysis.

DATA:

RATE ANALYSIS
A. MATERIALS
Sl No
Particulars
1
2
3
4
5

Use rate of drill bit 50 mm dia


Use rate of air hose 50 m
Anchor rod 25 mm dia
Cement
Sand ( screened )
Total cost of Materials
B. MACHINERY:
Sl No
Description
1
2

Unit

Quantity

Rm
Hour
kg
kg
cum

Unit

37.50
4.00
303.22
75.00
0.05

Quantity

Air compressor 8.5 cmm ( ele )


Hour
Fuel / Energy charges
Hour
Waggon drill
Hour
Fuel / Energy charges
Hour
Total hire charges of Machinery

C. LABOUR:
Sl No
Description
1
2
3
4
5

Crew for Air compressor


Crew for Waggon drill
Bar bender
Mason Cl- II
mazdoor
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Unit

UNIT:
25 Nos.
Rate
Amount
in Rs.
in Rs
62.50 2343.75
18.63 74.52
46.50 14099.73
4.00 300.00
606.00 30.30
Rs: 16848.30
Rate
in Rs.

4.00
4.00
4.00
4.00

Quantity

Hour
Hour
Day
Day
Day

170.80
428.00
188.50
0.00
Rs:

Amount
in Rs
683.20
1712.00
754.00
0.00
3149.20

142.40
244.90
450.00
345.00
295.00
Rs:

Amount
in Rs
569.60
979.60
225.00
172.50
295.00
2241.70

Rate
in Rs.
4.00
4.00
0.50
0.50
1.00

89.70
14% 12.60
102.30

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D.Add for contractor's profit and overheads on (A+B+C)
Lead Charges for 1 Km for FA
0.05
cum @
Lead Charges for 1Km for Cement (including Loading
0.08
tonne @
and Unloading Charges)
Lead Charges for 1Km for Steel (including Loading
0.30
tonne @
and Unloading Charges)
Total cost for
25.00

Rs:
Rs:
Rs:
Rs:
Rs.
31.5 Rs./Cum

16848.30
3149.20
2241.70
22239.20
3113.49
1.575

124.6 Rs./Tonne

9.345

145.6 Rs./Tonne

44.148832
Rs: 25407.76

Total
14%

Nos.

58

Dam and Allied Works - Item Unit Rates 2014-15

Rate per

IRR-DAW-1-14

Each

(A+B+C+D)/25

Rs: 1016.30

Providing and fixing 25 mm dia. 2.75 m long ribbed steel anchor rods
with one end split and driven firmly using steel wedge into 1.25 m deep 45
to 50 mm dia. hole drilled in bed rock and other end provided with L- bend
for embedding in concrete / masonry for spillway and appurtenant works
including drilling and cleaning hole, filling hole with thick cement slurry,
driving anchor rod, cost of all materials, machinery, labour, steel wedge
etc., complete with initial lead upto 1 km and all lifts.
Consider 25 anchor rods for analysis.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars

Unit

1
2
3
4
5
6

Use rate of 50 mm dia drill bit


Use rate of air hose 50 m 1 Nos.
Anchor rod 25 mm dia
Cement
Gas for splitting anchor rods
Steel wedges
Total cost of Materials
B. MACHINERY:
Sl No
Description

Quantity

Rm
Hour
kg
kg
LS
LS

31.25
3.00
277.92
62.50
5.00
10.00

Unit

Quantity

Air compressor 8.5 cmm ( ele )


Hour
Fuel / Energy charges
Hour
2
Waggon drill
Hour
Fuel / Energy charges
Hour
Total hire charges of Machinery
C. LABOUR:
Sl No
Description
Unit

UNIT:
25.00 Nos.
Rate
Amount
in Rs.
in Rs
62.50 1953.13
18.63 55.89
46.50 12923.28
4.00 250.00
37.20 186.00
16.00 160.00
Rs: 15528.30
Rate
in Rs.

3.00
3.00
3.00
3.00

Quantity

1
2
3
4
5
6

Crew for Air compressor


Hour
Crew for Waggon drill
Hour
Bar bender
Day
Mason Cl- II
Day
Gas cutter
Day
mazdoor
Day
Total cost of Labour
labour component/unit qty
101.40
Add contractor's profit and overhead charges
14% 14.20
labour component/unit qty (including contractor's profit)
115.60

170.80
428.00
188.50
0.00
Rs:

Amount
in Rs
512.40
1284.00
565.50
0.00
2361.90

142.40
244.90
450.00
345.00
385.00
295.00
Rs:

Amount
in Rs
427.20
734.70
225.00
172.50
385.00
590.00
2534.40

Rs:
Rs:
Rs:
Rs:
Rs.

15528.30
2361.90
2534.40
20424.60
2859.44

Rate
in Rs.
3.00
3.00
0.50
0.50
1.00
2.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
14%

D.Add for contractor's profit and overheads on (A+B+C)


Lead Charges for 1Km for Cement (including Loading
and Unloading Charges)
0.06
Lead Charges for 1Km for Steel (including Loading
and Unloading Charges)
Total cost for
Rate per
Each

tonne @

124.6 Rs./Tonne

7.7875

0.28
tonne @
25.00
(A+B+C+D)/25

145.6 Rs./Tonne

40.465152
Rs: 23332.29
Rs: 933.30

Nos.

IRR-DAW-2

REINFORCEMENT & CEMENT CONCRETE WORKS :

IRR-DAW-2-1A

Providing, fabricating and placing in position reinforcement steel for RCC,below 36 dia rods
overlaps and wastages wherever required, tying with 1.25 mm diameter soft
annealed steel wire, including cost of all materials, machinery, labour etc.,
complete with initial lead upto 1 km and all lifts.
overlaps and wastage
as per NHAI-data
Lap jointing considered for bars upto 36 mm diameter.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2

Rein.Steel with 5 % wastage


Binding wire 1.25 mm dia
Total cost of Materials

B. MACHINERY:
Sl No
Description

Unit

Quantity

tonne
kg

Unit

1.05
9.00

Quantity

UNIT :
1.00 tonne
Rate
Amount
in Rs.
in Rs
46500.00 48825.00
70.00 630.00
Rs: 49455.00

Rate

Amount

59

Dam and Allied Works - Item Unit Rates 2014-15

in Rs.
Total hire charges of Machinery
C. LABOUR:
Sl No
Description
1
2

Bar bender
mazdoor

Unit

Quantity

Rate
in Rs.

Day
Day

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

2.00
6.84

49455.00
0.00
2917.80
52372.80
14%

59857.87

Providing, fabricating and placing in position reinforcement steel for RCC


above 36 dia with welding and wastage at 2.5%, tying with 1.25 mm diameter soft
annealed steel wire, including cost of all materials, machinery, labour etc.,
complete with initial lead upto 1 km and all lifts.
overlaps and wastage
as per NHAI-data
welding joints considered for bars above 36 mm diameter.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars

Unit

welding machine
fuel charges

Unit

1.025
70.00

Quantity

hour
hour
Total hire charges of Machinery

C. LABOUR:
Sl No
Description
1
2
3

Quantity

Rein.Steel with 2.5 % wastage


tonne
Welding electrodes 5 per joint and 14 joints pe One
Total cost of Materials

welder
Bar bender
mazdoor

Quantity

day
Day
Day

DATA:

Rate
in Rs.

Amount
in Rs
16.00 160.00
91.30 913.00
Rs: 1073.00

Rate
in Rs.

Amount
in Rs
385.00 962.50
450.00 900.00
295.00 2017.80
3880.30

2.50
2.00
6.84
3880.30
14% 543.20
4423.50

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D.Add for contractor's profit and overheads on A+B+C
Lead Charges for 1Km for Steel (including Loading
and Unloading Charges)
145.60 Rs/Tonne
Total cost for
1.00
Rate per/ TON.=(A+B+C+D) / I

IRR-DAW-2-2

UNIT :
1.00 tonne
Rate
Amount
in Rs.
in Rs
46500.00 47662.50
11.00 770.00
Rs: 48432.50

10.00
10.00

Unit

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

7332.19

152.88
tonne 59857.87

IRR-DAW-2-1B

B. MACHINERY:
Sl No
Description

Amount
in Rs
450.00 900.00
295.00 2017.80
2917.80

2917.80
14% 408.50
3326.30

A.MATERIAL
B.MACHINERY
C. LABOUR
Total
D.Add for contractor's profit and overheads on A+B+C
Lead Charges for 1Km for Steel (including Loading
and Unloading Charges)
145.60 Rs/Tonne
Total cost for
1.00
Rate per/ TON.=(A+B+C+D) / I

1
3

in Rs
Rs: 0.00

14%

48432.50
1073.00
3880.30
53385.80
7474.01

149.24
tonne 61009.05
61009.05

Providing and laying insitu vibrated M-15 ( 28 days cube compressive


strength not less than 15 N / sq mm ) grade cement concrete using 80 mm
down size approved, clean, hard, graded aggregates including cost of all
materials, machinery, labour, formwork, centering, scaffolding, cleaning,
batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc.,complete for plain concrete works with initial lead upto 1 km and
all lifts. ( Cement content : 250 kg /cum with use of super plasticiser
equal to 0.4% of cement content , CA : 0.98 cum,
Blending Ratio of CA -- 40:30:20:10, FA : 0.35 cum )
RATE ANALYSIS
UNIT:

60

Dam and Allied Works - Item Unit Rates 2014-15

A. MATERIALS:
Sl No
Particulars
1
2

3
4
5

Cement for mix


Cement for incidentals @ 3 kg / cum
Coarse aggregate 80-40 mm
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-screened )
Super Plasticizer or AEA
Use rate of shuttering
Total cost of Materials

B. MACHINERY:
Sl No
Description
1
2
3
4
5
6
7
8

Unit

Quantity

kg
kg
cum
cum
cum
cum
cum
kg
sqm

Unit

60000.00
720.00
94.08
70.56
47.04
23.52
84.00
240.00
120.00

Quantity

Batching plant
Hour
Fuel / Energy charges
Hour
Air compressor 7 cmm ( ele )
Hour
Fuel / Energy charges
Hour
Tipper
Hour
Fuel / Energy charges
Hour
Tower crane 5 t
Hour
Fuel / Energy charges
Hour
Concrete bucket
Hour
Fuel / Energy charges
Hour
10 hp pump ( ele )
Hour
Fuel / Energy charges
Hour
Needle vibrator 60 mm dia ( ele )
Hour
Fuel / Energy charges
Hour
Sundries
LS
Total hire charges of Machinery

C. LABOUR:
Sl No
Description

Unit

240.00 cum
Rate
Amount
in Rs.
in Rs
4.00 240000.00
4.00 2880.00
635.00 59740.80
1145.00 80791.20
1210.00 56918.40
875.00 20580.00
462.00 38808.00
80.00 19200.00
353.76 42451.20
Rs: 561369.60

Rate
in Rs.
518.10
418.50
131.90
342.40
446.70
322.20
867.10
197.80
15.80
0.00
6.70
76.10
9.70
11.40
41.00
Rs:

Amount
in Rs
4144.80
3348.00
1055.20
2739.20
14294.40
10310.40
13873.60
3164.80
632.00
0.00
53.60
608.80
155.20
182.40
410.00
54972.40

8.00
8.00
32.00
16.00
8.00
16.00
4.00
2.00

293.80
142.40
153.10
163.30
72.10
136.60
385.00
440.00

Amount
in Rs
2350.40
1139.20
4899.20
2612.80
576.80
2185.60
1540.00
880.00

2.00
2.00
2.00
6.00
2.00
120.00

295.00
295.00
295.00
295.00
295.00
112.95
Rs:

590.00
590.00
590.00
1770.00
590.00
13554.00
33868.00

8.00
8.00
8.00
8.00
32.00
32.00
16.00
16.00
40.00
40.00
8.00
8.00
16.00
16.00
10.00

Quantity

1
2
3
4
5
6
7
8
9

Crew for Batching plant


Hour
Crew for Air compressor
Hour
Crew for Tipper ( 4 )
Hour
Crew for Tower crane ( 2 )
Hour
Crew for Pump
Hour
Crew for Needle vibrator ( 2 )
Hour
Mason Class-I
Day
Foreman
Day
mazdoor
for silo ( cement handling )
Day
for batching plant
Day
for conveyor system
Day
for laying & vibrating
Day
for cleaning / washing / curing
Day
10 Labour cost for shuttering
sqm
Total cost of Labour
labour component/unit qty
141.10
Add contractor's profit and overhead charges
14% 19.80
labour component/unit qty (including contractor's profit)
160.90

Rate
in Rs.

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Add for conveyor system @
Add for electric sub-station/ Demand charges @
Add for trestle bridge for tower crane track @
D.Add for contractor's profit and overheads on (A+B+C)
Lead Charges for 1 Km for FA
84.00
cum @
Lead Charges for 1 Km for CA
235.20 cum @
Lead Charges for 1Km for Cement (including Loading
and Unloading Charges)
60.72
tonne @
Total cost for
240.00
Rate per
cum
(A+B+C+D)/240
IRR-DAW-2-2A
New Item1-2010-11

Rs:
Rs:
Rs:
Rs:

Total
3.00%
2.5%
4.0%
Total
14%
31.5 Rs./Cum
30.4 Rs./Cum
124.6 Rs./Tonne
cum

561369.60
54972.40
33868.00
650210.00
19506.30
16255.25
26008.40
Rs: 711979.95
Rs. 99677.19
2646
7150.08
7565.712
Rs: 829018.93
Rs: 3454.20

Providing and laying insitu vibrated M-20 ( 28 days cube compressive


strength not less than 20 N / sq mm ) grade cement concrete using 80 mm
down size approved, clean, hard, graded aggregates including cost of all
materials, machinery, labour, formwork, centering, scaffolding, cleaning,
batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc.,complete for plain concrete works with initial lead upto 1 km and
all lifts. ( Cement content : 300 kg /cum with use of

61

Dam and Allied Works - Item Unit Rates 2014-15

0.4% of cement content super plasticiser , CA : 0.90 cum,


Blending Ratio of CA -- 40:30:20:10, FA : 0.40 cum )

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2

3
4
5

Cement for mix


Cement for incidentals @ 3 kg / cum
Coarse aggregate 80-40 mm
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened )
Super Plasticizer or AEA
Use rate of shuttering
Total cost of Materials

B. MACHINERY:
Sl No
Description
1
2
3
4
5
6
7
8

Unit

Quantity

kg
kg
cum
cum
cum
cum
cum
kg
sqm

Unit

72000.00
720.00
86.40
64.80
43.20
21.60
96.00
288.00
120.00

Quantity

Batching plant
Hour
Fuel / Energy charges
Hour
Air compressor 7 cmm ( ele )
Hour
Fuel / Energy charges
Hour
Tipper
Hour
Fuel / Energy charges
Hour
Tower crane 5 t
Hour
Fuel / Energy charges
Hour
Concrete bucket
Hour
Fuel / Energy charges
Hour
Hour
10 hp pump ( ele )
Fuel / Energy charges
Hour
Needle vibrator 60 mm dia ( ele )
Hour
Fuel / Energy charges
Hour
Sundries
LS
Total hire charges of Machinery

C. LABOUR:
Sl No
Description

Unit

UNIT:
240.00 cum
Rate
Amount
in Rs.
in Rs
4.00 288000.00
4.00 2880.00
635.00 54864.00
1145.00 74196.00
1210.00 52272.00
875.00 18900.00
462.00 44352.00
80.00 23040.00
353.76 42451.20
Rs: 600955.20

Rate
in Rs.
518.10
418.50
131.90
342.40
446.70
322.20
867.10
197.80
15.80
0.00
6.70
76.10
9.70
11.40
41.00
Rs:

Amount
in Rs
4144.80
3348.00
1055.20
2739.20
14294.40
10310.40
13873.60
3164.80
632.00
0.00
53.60
608.80
155.20
182.40
410.00
54972.40

8.00
8.00
32.00
16.00
8.00
16.00
4.00
2.00

293.80
142.40
153.10
163.30
72.10
136.60
385.00
440.00

Amount
in Rs
2350.40
1139.20
4899.20
2612.80
576.80
2185.60
1540.00
880.00

2.00
2.00
2.00
6.00
2.00
120.00

295.00
295.00
295.00
295.00
295.00
112.95
Rs:

590.00
590.00
590.00
1770.00
590.00
13554.00
33868.00

8.00
8.00
8.00
8.00
32.00
32.00
16.00
16.00
40.00
40.00
8.00
8.00
16.00
16.00
10.00

Quantity

1
2
3
4
5
6
7
8
9

Crew for Batching plant


Hour
Crew for Air compressor
Hour
Crew for Tipper ( 4 )
Hour
Crew for Tower crane ( 2 )
Hour
Crew for Pump
Hour
Crew for Needle vibrator ( 2 )
Hour
Mason Class-I
Day
Foreman
Day
mazdoor
for silo ( cement handling )
Day
for batching plant
Day
for conveyor system
Day
for laying & vibrating
Day
for cleaning / washing / curing
Day
10 Labour cost for shuttering
sqm
Total cost of Labour
labour component/unit qty
141.10
Add contractor's profit and overhead charges
14% 19.80
labour component/unit qty (including contractor's profit)
160.90

Rate
in Rs.

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Add for conveyor system @
Add for electric sub-station/ Demand charges @
Add for trestle bridge for tower crane track @
D.Add for contractor's profit and overheads on (A+B+C)
Lead Charges for 1 Km for FA
96.00
cum @
Lead Charges for 1 Km for CA
216.00 cum @
Lead Charges for 1Km for Cement (including Loading
72.72
tonne @
and Unloading Charges)
Total cost for
240.00
Rate per
cum
(A+B+C+D)/240
IRR-DAW-2-3

Rs:
Rs:
Rs:
Rs:

Total
3.00%
2.5%
4.0%
Total
14%
31.5 Rs./Cum
30.4 Rs./Cum
124.6 Rs./Tonne
cum

600955.20
54972.40
33868.00
689795.60
20693.87
17244.89
27591.82
Rs: 755326.18
Rs. 105745.67
3024
6566.40

9060.912
Rs: 879723.16
Rs: 3665.50

Providing and laying insitu vibrated M-10 ( 28 days cube compressive

62

Dam and Allied Works - Item Unit Rates 2014-15

strength not less than10 N / sq mm ) grade cement concrete using 80 mm


down size approved, clean, hard, graded aggregates including cost of all
materials, machinery, labour, formwork, centering, scaffolding, cleaning,
batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc.,complete for plain concrete works with initial lead upto 1 km and
all lifts. ( Cement content : 220 kg /cum with use of super plasticiser,
CA: 0.98 cum, Blending Ratio of CA --40:30:20:10, FA: 0.37 cum)
DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2

3
4
5

Cement for mix


Cement for incidentals @ 3 kg / cum
Coarse aggregate 80-40 mm
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened )
Super Plasticizer or AEA
Use rate of shuttering
Total cost of Materials

B. MACHINERY:
Sl No
Description
1
2
3
4
5
6
7
8

Unit

Quantity

kg
kg
cum
cum
cum
cum
cum
kg
sqm

52800
720.00
94.08
70.56
47.04
23.52
88.8
211.20
120.00

Unit

Quantity

Batching plant 2 x 1.5 cum


Hour
Fuel / Energy charges
Hour
Air compressor 7 cmm ( ele )
Hour
Fuel / Energy charges
Hour
Tipper
Hour
Fuel / Energy charges
Hour
Tower crane 5 t
Hour
Fuel / Energy charges
Hour
Concrete bucket
Hour
Fuel / Energy charges
Hour
10 hp pump ( ele )
Hour
Fuel / Energy charges
Hour
Needle vibrator 60 mm dia ( ele )
Hour
Fuel / Energy charges
Hour
Sundries
LS
Total hire charges of Machinery

C. LABOUR:
Sl No
Description

Rate
in Rs.
518.10
418.50
131.90
342.40
446.70
322.20
867.10
197.80
15.80
0.00
6.70
76.10
9.70
11.40
41.00
Rs:

Amount
in Rs
4144.80
3348.00
1055.20
2739.20
14294.40
10310.40
13873.60
3164.80
632.00
0.00
53.60
608.80
155.20
182.40
410.00
54972.40

8.00
8.00
32.00
16.00
8.00
16.00
4.00
2.00

293.80
142.40
153.10
163.30
72.10
136.60
385.00
440.00

Amount
in Rs
2350.40
1139.20
4899.20
2612.80
576.80
2185.60
1540.00
880.00

2.00
2.00
2.00
6.00
2.00
120.00

295.00
295.00
295.00
295.00
295.00
112.95
Rs:

590.00
590.00
590.00
1770.00
590.00
13554.00
33868.00

8.00
8.00
8.00
8.00
32.00
32.00
16.00
16.00
40.00
40.00
8.00
8.00
16.00
16.00
10.00

Unit

Quantity

1
2
3
4
5
6
7
8
9

Crew for Batching plant


Hour
Crew for Air compressor
Hour
Crew for Tipper ( 4 )
Hour
Crew for Tower crane ( 2 )
Hour
Crew for Pump
Hour
Crew for Needle vibrator ( 2 )
Hour
Mason Class-I
Day
Foreman
Day
mazdoor
for silo ( cement handling )
Day
for batching plant
Day
for conveyor system
Day
for laying & vibrating
Day
for cleaning / washing / curing
Day
10 Labour cost for shuttering
sqm
Total cost of Labour
labour component/unit qty
141.10
Add contractor's profit and overhead charges
14% 19.80
labour component/unit qty (including contractor's profit)
160.90
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rate
in Rs.

Rs:
Rs:
Rs:
Total
3.00%
2.5%
4.0%
Total
14%

Add for conveyor system @


Add for electric sub-station/ Demand charges @
Add for trestle bridge for tower crane track @
D.Add for contractor's profit and overheads on (A+B+C+other
Lead Charges for 1 Km for FA
88.80
Lead Charges for 1 Km for CA
235.20

UNIT:
240.00 cum
Rate
Amount
in Rs.
in Rs
4.00 211200.00
4.00 2880.00
635.00 59740.80
1145.00 80791.20
1210.00 56918.40
875.00 20580.00
462.00 41025.60
80.00 16896.00
353.76 42451.20
Rs: 532483.20

cum @
cum @

31.5 Rs./Cum
30.4 Rs./Cum

532483.20
54972.40
33868.00
Rs: 621323.60
18639.71
15533.09
24852.94
Rs: 680349.34
Rs. 95248.91
2797.2
7150.08

63

Dam and Allied Works - Item Unit Rates 2014-15

Lead Charges for 1Km for Cement (including Loading


and Unloading Charges)
53.52
tonne @
Total cost for
240.00
Rate per
cum
(A+B+C+D)/240

IRR-DAW-2-4

124.6 Rs./Tonne
cum

6668.592
Rs: 792214.12
Rs: 3300.90

Providing and laying insitu vibrated M-20 ( 28 days cube compressive


strength not less than 20 N / sq mm ) grade cement concrete using 40 mm
down size approved, clean, hard, graded aggregates including cost of all
materials, machinery, labour, formwork, centering, scaffolding, cleaning,
batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc.,complete for RCC works of gallery, sluice, spillway crest, spillway d / s
face, energy dissipating structures, training walls, piers, abutments and
such other locations with initial lead upto 1 km and all lifts.
( Cement content : 310 kg / cum with use of super plasticiser,
CA : 0.90 cum, blending ratio of CA--50:30:20, FA : 0.40 cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2

3
4
5
6

Cement for mix


Cement for incidentals @ 3 kg / cum
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened )
Super Plasticizer or AEA
Use rate of shuttering
Scaffolding of shuttering @
Total cost of Materials

B. MACHINERY:
Sl No
Description
1
2
3
4
5
6
7
8

Batching plant 2 x 1.5 cum


Fuel / Energy charges
Air compressor 7 cmm ( ele )
Fuel / Energy charges
Tipper
Fuel / Energy charges
Tower crane 5 t
Fuel / Energy charges
Concrete bucket
Fuel / Energy charges
10 hp pump ( ele )
Fuel / Energy charges
Needle vibrator 60 mm dia ( ele )
Fuel / Energy charges
Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No
Description
1
2
3
4
5
6
7
8
9

Unit
kg
kg
cum
cum
cum
cum
kg
sqm

74400
720.00
108
64.8
43.2
96
297.60
360.00
15%

Unit

Quantity

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Unit

Crew for Batching plant


Hour
Crew for Air compressor
Hour
Crew for Tipper ( 4 )
Hour
Crew for Tower crane ( 2 )
Hour
Crew for Pump
Hour
Crew for Needle vibrator ( 2 )
Hour
Mason Class-I
Day
Foreman
Day
mazdoor
for silo ( cement handling )
Day
for batching plant
Day
for conveyor system
Day
for laying & vibrating
Day
for cleaning / washing / curing
Day
10 Labour cost for shuttering
sqm
11 Labour cost for scaffolding @
15%
Total cost of Labour
labour component/unit qty
279.50
Add contractor's profit and overhead charges
14% 39.10
labour component/unit qty (including contractor's profit)
318.60
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Quantity

UNIT:
240.00 cum
Rate
Amount
in Rs.
in Rs
4.00 297600.00
4.00 2880.00
1145.00 123660.00
1210.00 78408.00
875.00 37800.00
462.00 44352.00
80.00 23808.00
353.76 127353.60
19103.04
Rs: 754964.64

Rate
in Rs.
8.00
8.00
8.00
8.00
32.00
32.00
16.00
16.00
40.00
40.00
8.00
8.00
16.00
16.00
10.00

Quantity

518.10
418.50
131.90
342.40
446.70
322.20
867.10
197.80
15.80
0.00
6.70
76.10
9.70
11.40
41.00
Rs:

Rate
in Rs.
8.00
8.00
32.00
16.00
8.00
16.00
4.00
2.00

293.80
142.40
153.10
163.30
72.10
136.60
385.00
440.00

2.00
2.00
2.00
6.00
2.00
360.00

295.00
295.00
295.00
295.00
295.00
112.95
Rs:

Amount
in Rs
4144.80
3348.00
1055.20
2739.20
14294.40
10310.40
13873.60
3164.80
632.00
0.00
53.60
608.80
155.20
182.40
410.00
54972.40

Amount
in Rs
2350.40
1139.20
4899.20
2612.80
576.80
2185.60
1540.00
880.00
0.00
590.00
590.00
590.00
1770.00
590.00
40662.00
6099.30
67075.30

Rs: 754964.64
Rs: 54972.40
Rs: 67075.30

64

Dam and Allied Works - Item Unit Rates 2014-15

Add for aggregate conveyor system @


Add for electric sub-station / Demand charges @
Add for trestle bridge for tower crane track @
D.Add for contractor's profit and overheads on (A+B+C+other
Lead Charges for 1 Km for FA
96.00
cum @
Lead Charges for 1 Km for CA
216.00 cum @
Lead Charges for 1Km for Cement (including Loading
75.12
tonne @
and Unloading Charges)
Total cost for
240.00
Rate per
cum
(A+B+C+D)/240
IRR-DAW-2-4A
new Item2-2010-11

Total
3.0%
2.50%
4.0%
Total
14%

Rs: 877012.34
26310.37
21925.31
35080.49
Rs: 960328.51
Rs. 134445.99
3024
6566.40

31.5 Rs./Cum
30.4 Rs./Cum
124.6 Rs./Tonne
cum

9359.952
Rs: 1113724.85
Rs: 4640.50

Providing and laying insitu vibrated M-25 ( 28 days cube compressive


strength not less than 25 N / sq mm ) grade cement concrete using 40 mm
down size approved, clean, hard, graded aggregates including cost of all
materials, machinery, labour, formwork, centering, scaffolding, cleaning,
batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc.,complete for RCC works of gallery, sluice, spillway crest, spillway d / s
face, energy dissipating structures, training walls, piers, abutments and
such other locations with initial lead upto 1 km and all lifts.
( Cement content : 360 kg / cum with use of super plasticiser,
CA : 0.90 cum, blending ratio of CA--50:30:20, FA : 0.40 cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2

3
4
5
6

Cement for mix


Cement for incidentals @ 3 kg / cum
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened )
Super Plasticizer or AEA
Use rate of shuttering
Scaffolding of shuttering @
Total cost of Materials

B. MACHINERY:
Sl No
Description
1
2
3
4
5
6
7
8

Batching plant 2 x 1.5 cum


Fuel / Energy charges
Air compressor 7 cmm ( ele )
Fuel / Energy charges
Tipper
Fuel / Energy charges
Tower crane 5 t
Fuel / Energy charges
Concrete bucket
Fuel / Energy charges
10 hp pump ( ele )
Fuel / Energy charges
Needle vibrator 60 mm dia ( ele )
Fuel / Energy charges
Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No
Description
1
2
3
4
5
6
7
8
9

Crew for Batching plant


Crew for Air compressor
Crew for Tipper ( 4 )
Crew for Tower crane ( 2 )
Crew for Pump
Crew for Needle vibrator ( 2 )
Mason Class-I
Foreman
mazdoor
for silo ( cement handling )
for batching plant
for conveyor system
for laying & vibrating
for cleaning / washing / curing
10 Labour cost for shuttering
11 Labour cost for scaffolding @
Total cost of Labour
labour component/unit qty

Unit

Quantity

kg
kg
cum
cum
cum
cum
kg
sqm

86400
720.00
108
64.8
43.2
96
345.60
360.00
15%

Unit

Quantity

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

UNIT:
240.00 cum
Rate
Amount
in Rs.
in Rs
4.00 345600.00
4.00 2880.00
1145.00 123660.00
1210.00 78408.00
875.00 37800.00
462.00 44352.00
80.00 27648.00
353.76 127353.60
19103.04
Rs: 806804.64

Rate
in Rs.
8.00
8.00
8.00
8.00
32.00
32.00
16.00
16.00
40.00
40.00
8.00
8.00
16.00
16.00
10.00

Unit

Quantity

518.10
418.50
131.90
342.40
446.70
322.20
867.10
197.80
15.80
0.00
6.70
76.10
9.70
11.40
41.00
Rs:

Rate
in Rs.

Hour
Hour
Hour
Hour
Hour
Hour
Day
Day

8.00
8.00
32.00
16.00
8.00
16.00
4.00
2.00

293.80
142.40
153.10
163.30
72.10
136.60
385.00
440.00

Day
Day
Day
Day
Day
sqm

2.00
2.00
2.00
6.00
2.00
360.00

295.00
295.00
295.00
295.00
295.00
112.95

15%
Rs:

Amount
in Rs
4144.80
3348.00
1055.20
2739.20
14294.40
10310.40
13873.60
3164.80
632.00
0.00
53.60
608.80
155.20
182.40
410.00
54972.40

Amount
in Rs
2350.40
1139.20
4899.20
2612.80
576.80
2185.60
1540.00
880.00
0.00
590.00
590.00
590.00
1770.00
590.00
40662.00
6099.30
67075.30

279.50

65

Dam and Allied Works - Item Unit Rates 2014-15

Add contractor's profit and overhead charges


labour component/unit qty (including contractor's profit)

14% 39.10
318.60

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Add for aggregate conveyor system @
Add for electric sub-station / Demand charges @
Add for trestle bridge for tower crane track @
D.Add for contractor's profit and overheads on (A+B+C+other
Lead Charges for 1 Km for FA
96.00
cum @
Lead Charges for 1 Km for CA
216.00 cum @
Lead Charges for 1Km for Cement (including Loading
and Unloading Charges)
87.12
tonne @
Total cost for
240.00
Rate per
cum
(A+B+C+D)/240
IRR-DAW-2-4B
new Item3-2010-11

Rs:
Rs:
Rs:
Rs:

806804.64
54972.40
67075.30
928852.34
27865.57
23221.31
37154.09
Rs: 1017093.31
Rs. 142393.06
3024
6566.40

Total
3.0%
2.50%
4.0%
Total
14%
31.5 Rs./Cum
30.4 Rs./Cum
124.6 Rs./Tonne
cum

10855.152
Rs: 1179931.92
Rs: 4916.40

Providing and laying insitu vibrated M-25 ( 28 days cube compressive


strength not less than 25 N / sq mm ) grade cement concrete using 20 mm
down size approved, clean, hard, graded aggregates including cost of all
materials, machinery, labour, formwork, centering, scaffolding, cleaning,
batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc.,complete for RCC works of gallery, sluice, spillway crest, spillway d / s
face, energy dissipating structures, training walls, piers, abutments and
such other locations with initial lead upto 1 km and all lifts.
( Cement content : 380 kg / cum with use of super plasticiser,
CA : 0.90 cum, blending ratio of CA--65:35, FA : 0.40 cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2

3
4
5
6

Cement for mix


Cement for incidentals @ 3 kg / cum
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened )
Super Plasticizer or AEA
Use rate of shuttering
Scaffolding of shuttering @
Total cost of Materials

B. MACHINERY:
Sl No
Description
1
2
3
4
5
6
7
8

Batching plant 2 x 1.5 cum


Fuel / Energy charges
Air compressor 7 cmm ( ele )
Fuel / Energy charges
Tipper
Fuel / Energy charges
Tower crane 5 t
Fuel / Energy charges
Concrete bucket
Fuel / Energy charges
10 hp pump ( ele )
Fuel / Energy charges
Needle vibrator 60 mm dia ( ele )
Fuel / Energy charges
Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No
Description
1
2
3
4
5
6
7
8
9

Crew for Batching plant


Crew for Air compressor
Crew for Tipper ( 4 )
Crew for Tower crane ( 2 )
Crew for Pump
Crew for Needle vibrator ( 2 )
Mason Class-I
Foreman
mazdoor
for silo ( cement handling )
for batching plant
for conveyor system

Unit

Quantity

kg
kg
cum
cum
cum
kg
sqm

91200
720.00
140.4
75.6
96
364.80
360.00
15%

Unit

Quantity

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Unit

UNIT:
240.00 cum
Rate
Amount
in Rs.
in Rs
4.00 364800.00
4.00 2880.00
1210.00 169884.00
875.00 66150.00
462.00 44352.00
80.00 29184.00
353.76 127353.60
19103.04
Rs: 823706.64

Rate
in Rs.
8.00
8.00
8.00
8.00
32.00
32.00
16.00
16.00
40.00
40.00
8.00
8.00
16.00
16.00
10.00

Quantity

518.10
418.50
131.90
342.40
446.70
322.20
867.10
197.80
15.80
0.00
6.70
76.10
9.70
11.40
41.00
Rs:

Rate
in Rs.

Hour
Hour
Hour
Hour
Hour
Hour
Day
Day

8.00
8.00
32.00
16.00
8.00
16.00
4.00
2.00

293.80
142.40
153.10
163.30
72.10
136.60
385.00
440.00

Day
Day
Day

2.00
2.00
2.00

295.00
295.00
295.00

Amount
in Rs
4144.80
3348.00
1055.20
2739.20
14294.40
10310.40
13873.60
3164.80
632.00
0.00
53.60
608.80
155.20
182.40
410.00
54972.40

Amount
in Rs
2350.40
1139.20
4899.20
2612.80
576.80
2185.60
1540.00
880.00
0.00
590.00
590.00
590.00

66

Dam and Allied Works - Item Unit Rates 2014-15

for laying & vibrating


Day
for cleaning / washing / curing
Day
10 Labour cost for shuttering
sqm
11 Labour cost for scaffolding @
15%
Total cost of Labour
labour component/unit qty
279.50
Add contractor's profit and overhead charges
14% 39.10
labour component/unit qty (including contractor's profit)
318.60

6.00
2.00
360.00

295.00 1770.00
295.00 590.00
112.95 40662.00
6099.30
Rs: 67075.30

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

823706.64
54972.40
67075.30
945754.34
28372.63
23643.86
37830.17
Rs: 1035601.00
Rs. 144984.14
3024
6566.40

Total
3.0%
2.50%
4.0%
Total
14%

Add for aggregate conveyor system @


Add for electric sub-station / Demand charges @
Add for trestle bridge for tower crane track @
D.Add for contractor's profit and overheads on (A+B+C+other
Lead Charges for 1 Km for FA
96.00
cum @
Lead Charges for 1 Km for CA
216.00 cum @
Lead Charges for 1Km for Cement (including Loading
and Unloading Charges)
91.92
tonne @
Total cost for
240.00
Rate per
cum
(A+B+C+D)/240
IRR-DAW-2-5

Rs:
Rs:
Rs:
Rs:

31.5 Rs./Cum
30.4 Rs./Cum
124.6 Rs./Tonne
cum

11453.232
Rs: 1201628.77
Rs: 5006.80

Providing and laying insitu vibrated M-15 ( 28 days cube compressive


strength not less than 15 N / sq mm ) grade cement concrete using 40 mm
down size approved, clean, hard, graded aggregates including cost of all
materials, machinery, labour, formwork, centering, scaffolding, cleaning,
batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc.,complete for plain concrete works with initial lead upto 1 km and
all lifts. ( Cement content : 260 kg / cum with use of super plasticiser,
CA : 0.90 cum, Blending Ratio of CA -- 50:30:20, FA : 0.40 cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2

3
4
5
6

Cement for mix


Cement for incidentals @ 3 kg
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened )
Super plasticizer
Use rate of shuttering
Use rate of scaffolding @
Total cost of Materials

B. MACHINERY:
Sl No
Description
1
2
3

kg
kg
cum
cum
cum
cum
kg
sqm

Quantity
3640.00
42.00
6.3
3.78
2.52
5.6
14.56
14.00

15%

Unit

Quantity

Concrete mixer 300 / 200 ltr ( ele )


Hour
Fuel / Energy charges
Hour
10 hp pump ( ele )
Hour
Fuel / Energy charges
Hour
Needle vibrator 40 mm dia ( ele )
Hour
Fuel / Energy charges
Hour
Total hire charges of Machinery

C. LABOUR:
Sl No
Description
1
2
3
4
5

Unit

Crew for Concrete mixer


Crew for Pump
Crew for Needle vibrator
Mason Class-I
mazdoor
for batching cement ( cement handling
for batching other materials
for loading mortar pans
for laying
for conveying concrete
for cleaning / washing / curing
6
Labour cost of shuttering
7
Labour cost of scaffolding @
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges

Unit

UNIT :
14.00 cum
Rate
Amount
in Rs.
in Rs
4.00 14560.00
4.00 168.00
1145.00 7213.50
1210.00 4573.80
875.00 2205.00
462.00 2587.20
80.00 1164.80
235.84 3301.76
495.26
Rs: 36269.32

Rate
in Rs.
8.0
8.0
1.0
1.0
8.0
8.0

Quantity

51.70
38.00
6.70
76.10
8.00
7.60
Rs:

Amount
in Rs
413.60
304.00
6.70
76.10
64.00
60.80
925.20

Amount
in Rs
1518.40
72.10
1092.80
385.00

Rate
in Rs.

Hour
Hour
Hour
Day

8.00
1.00
8.00
1.00

189.80
72.10
136.60
385.00

Day
Day
Day
Day
Day
Day
sqm

2.00
9.00
4.00
3.00
14.00
1.00
14.00

295.00
295.00
295.00
295.00
295.00
295.00
75.30

15%

590.00
2655.00
1180.00
885.00
4130.00
295.00
1054.20
158.13
Rs: 14015.63

1001.10
14% 140.20

67

Dam and Allied Works - Item Unit Rates 2014-15

labour component/unit qty (including contractor's profit)

1141.30

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:
Rs.

Total
D.Add for contractor's profit and overheads on (A+B+C)
Lead Charges for 1 Km for FA
5.60
Lead Charges for 1 Km for CA
12.60

14%
cum @
cum @

31.5 Rs./Cum
30.4 Rs./Cum

Lead Charges for 1Km for Cement (including Loading


and Unloading Charges)
3.68
tonne @
Total cost for
14.00
Rate per
cum
(A+B+C+D)/14

IRR-DAW-2-6

124.6 Rs./Tonne
cum

36269.32
925.20
14015.63
51210.15
7169.42
176.4
383.04

458.7772
Rs: 59397.79
Rs: 4242.70

Providing and laying insitu vibrated M-15 ( 28 days cube compressive


strength not less than 15 N / sq mm ) grade cement concrete using 40 mm
down size approved, clean, hard, graded aggregates with placing and
sinking plums of size 150 to 80 mm upto 15 percent for gravity type
structures including cost of all materials, machinery, labour, formwork,
scaffolding, cleaning, batching, mixing, placing in position, levelling,
vibrating, finishing, curing etc.,complete with initial lead upto 1 km and
all lifts. ( Cement content : 260 kg / cum of concrete with use of plums
and super plasticiser of 0.4% of cement quantity, CA : 0.77 cum,
Blending Ratio of CA : 50:30:20,FA : 0.34 cum,
plums of size 150 to 80 mm : 0.25 cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2

3
4
5
6
7

Cement for mix


Cement for incidentals @ 3 kg / cum
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Plums of size 150 to 80 mm
Fine aggregate (Un-Screened )
Super Plasticizer
Use rate of shuttering for 40 uses
Scaffolding of shuttering @
Total cost of Materials

B. MACHINERY:
Sl No
Description
1
2
3

UNIT:
Unit

Quantity

kg
kg
cum
cum
cum
cum
cum
kg
sqm

4277
49.35
6.33
3.8
2.53
4.11
5.59
17.11
16.45
15%

Unit

Quantity

Concrete mixer 300 / 200 ltr ( ele )


Hour
Fuel / Energy charges
Hour
10 hp pump ( ele )
Hour
Fuel / Energy charges
Hour
Needle vibrator 60 mm dia ( ele )
Hour
Fuel / Energy charges
Hour
Total hire charges of Machinery

C. LABOUR:
Sl No
Description
1
2
3
4
5
6

Unit

Crew for Concrete mixer


Hour
Crew for Pump
Hour
Crew for Needle vibrator
Hour
Mason Class-I
Day
work inspector
Day
mazdoor
for batching cement ( cement handling
Day
for batching other materials
Day
for loading mortar pans
Day
for loading plums
Day
for laying concrete and plums
Day
for conveying concrete
Day
for conveying plums
Day
for cleaning / washing / curing
Day
7
Labour for shuttering
sqm
8
Labour for scaffolding @
15%
Total cost of Labour
labour component/unit qty
976.80
Add contractor's profit and overhead charges
14% 136.80
labour component/unit qty (including contractor's profit)
1113.60

16.45 cum
Rate
Amount
in Rs.
in Rs
4.00 17108.00
4.00 197.40
1145.00 7247.85
1210.00 4598.00
875.00 2213.75
340.00 1398.25
462.00 2583.97
80.00 1368.64
235.84 3879.57
581.94
Rs: 41177.37

Rate
in Rs.
51.70
38.00
6.70
76.10
9.70
11.40
Rs:

Amount
in Rs
413.60
304.00
6.70
76.10
77.60
91.20
969.20

8.00
1.00
8.00
1.00
1.00

189.80
72.10
136.60
385.00
370.00

Amount
in Rs
1518.40
72.10
1092.80
385.00
370.00

2.00
9.00
4.00
1.00
4.00
13.99
3.00
1.00
16.45

295.00
295.00
295.00
295.00
295.00
295.00
295.00
295.00
75.30

8.00
8.00
1.00
1.00
8.00
8.00

Quantity

Rate
in Rs.

590.00
2655.00
1180.00
295.00
1180.00
4125.87
885.00
295.00
1238.69
185.80
Rs: 16068.66

ABSTRACT:

68

Dam and Allied Works - Item Unit Rates 2014-15

A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
14%

D.Add for contractor's profit and overheads on (A+B+C)


Lead Charges for 1 Km for FA
5.59
cum @
Lead Charges for 1 Km for CA and Plums
16.77
cum @
Lead Charges for 1Km for Cement (including Loading
4.33
tonne @
and Unloading Charges)
Total cost for
16.45
Rate per
cum
(A+B+C+D)/16.45

IRR-DAW-2-7

Rs:
Rs:
Rs:
Rs:
Rs.
31.5 Rs./Cum
30.4 Rs./Cum
124.6 Rs./Tonne

cum

41177.37
969.20
16068.66
58215.23
8150.13
176.1795
509.88

539.06321
Rs: 67590.49
Rs: 4108.80

Providing and laying insitu vibrated M-10 ( 28 days cube compressive


strength not less than 10 N / sq mm ) grade cement concrete using 40 mm
down size approved, clean, hard, graded aggregates including cost of all
materials, machinery, labour, formwork, centering, scaffolding, cleaning,
batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc.,complete for plain concrete works with initial lead upto 1 km and all
lifts. ( Cement content 220 kg / cum with use of super plasticiser,
CA : 0.90 cum, Blending Ratio of CA : 50:30:20, FA : 0.40 cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2

3
4
5
6

Cement for mix


Cement for incidentals @ 3 kg/ cum
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened )
Super plasticizer
Use rate of shuttering
Use rate of scaffolding @
Total cost of Materials

B. MACHINERY:
Sl No
Description
1
2
3

Unit

Quantity

kg
kg
cum
cum
cum
cum
kg
sqm

3636.60
49.59
7.44
4.46
2.98
6.61
14.55
16.53
15%

Unit

Quantity

Concrete mixer 300 / 200 ltr ( ele )


Hour
Fuel / Energy charges
Hour
10 hp pump ( ele )
Hour
Fuel / Energy charges
Hour
Needle vibrator 40 mm dia ( ele )
Hour
Fuel / Energy charges
Hour
Total hire charges of Machinery

C. LABOUR:
Sl No
Description

UNIT:
16.53 cum
Rate
Amount
in Rs.
in Rs
4.00 14546.40
4.00 198.36
1145.00 8517.08
1210.00 5400.35
875.00 2603.48
462.00 3054.74
80.00 1163.71
235.84 3898.44
584.77
Rs: 39967.33

Rate
in Rs.
51.70
38.00
6.70
76.10
8.00
7.60
Rs:

Amount
in Rs
413.60
304.00
6.70
76.10
64.00
60.80
925.20

8.00
1.00
8.00
1.00

189.80
72.10
136.60
385.00

Amount
in Rs
1518.40
72.10
1092.80
385.00

2.00
9.00
4.00
3.00
16.53
1.00
16.53

295.00
295.00
295.00
295.00
295.00
295.00
75.30

14%

Rs:
Rs:
Rs:
Rs:
Rs.

8.00
8.00
1.00
1.00
8.00
8.00

Unit

Quantity

1
2
3
4
5

Crew for Concrete mixer


Hour
Crew for Pump
Hour
Crew for Needle vibrator
Hour
Mason Class-I
Day
mazdoor
for batching cement ( cement handling
Day
for batching other materials
Day
for loading mortar pans
Day
for laying
Day
for conveying concrete
Day
for cleaning / washing / curing
Day
6
Labour cost of shuttering
sqm
7
Labour cost of scaffolding @
15%
Total cost of Labour
labour component/unit qty
906.30
Add contractor's profit and overhead charges
14% 126.90
labour component/unit qty (including contractor's profit)
1033.20

Rate
in Rs.

590.00
2655.00
1180.00
885.00
4876.35
295.00
1244.71
186.71
Rs: 14981.07

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D.Add for contractor's profit and overheads on (A+B+C)
Lead Charges for 1 Km for FA
6.61
Lead Charges for 1 Km for CA
14.88

cum @
cum @

31.5 Rs./Cum
30.4 Rs./Cum

39967.33
925.20
14981.07
55873.60
7822.3
208.278
452.26

Lead Charges for 1Km for Cement (including Loading


and Unloading Charges)
3.69

tonne @

124.6 Rs./Tonne

459.29927

Total

69

Dam and Allied Works - Item Unit Rates 2014-15

Total cost for


Rate per

IRR-DAW-2-8

DATA:

cum

16.53
(A+B+C+D)/16.53

cum

Rs: 64815.74
Rs: 3921.10

Providing and laying insitu vibrated M-15 ( 28 days cube compressive


strength not less than 15 N / sq mm ) grade cement concrete using 20 mm
down size approved, clean, hard, graded aggregates including cost of all
materials, machinery, labour, formwork, centering, scaffolding, cleaning,
batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc.,complete for plain concrete works with initial lead upto 1 km and all
lifts. ( Cement content : 280 kg / cum with use of super plasticiser,
CA : 0.80 cum, Blending Ratio of CA -- 65:35, FA : 0.44 cum)
RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4
5
6

Cement for mix


Cement for incidentals @ 3 kg/ cum
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened )
Super plasticiser
Use rate of shuttering
Use rate of scaffolding @
Total cost of Materials

B. MACHINERY:
Sl No
Description
1
2
3

Unit

Quantity

kg
kg
cum
cum
cum
kg
sqm

4443.6
47.61
8.25
4.44
6.98
17.77
15.87
15%

Unit

Quantity

Concrete mixer 300 / 200 ltr ( ele )


Hour
Fuel / Energy charges
Hour
10 hp pump ( ele )
Hour
Fuel / Energy charges
Hour
Needle vibrator 40 mm dia ( ele )
Hour
Fuel / Energy charges
Hour
Total hire charges of Machinery

C. LABOUR:
Sl No
Description

UNIT:
15.87 cum
Rate
Amount
in Rs.
in Rs
4.00 17774.40
4.00 190.44
1210.00 9985.40
875.00 3888.15
462.00 3226.05
80.00 1421.95
235.84 3742.78
561.42
Rs: 40790.59

Rate
in Rs.
51.70
38.00
6.70
76.10
8.00
7.60
Rs:

Amount
in Rs
413.60
304.00
6.70
76.10
64.00
60.80
925.20

8.00
1.00
8.00
1.00

189.80
72.10
136.60
385.00

Amount
in Rs
1518.40
72.10
1092.80
385.00

2.00
9.00
4.00
3.00
15.87
1.00
15.87

295.00
295.00
295.00
295.00
295.00
295.00
75.30

14%

Rs:
Rs:
Rs:
Rs:
Rs.

8.00
8.00
1.00
1.00
8.00
8.00

Unit

Quantity

1
2
3
4
5

Crew for Concrete mixer


Hour
Crew for Pump
Hour
Crew for Needle vibrator
Hour
Mason Class-I
Day
mazdoor
for batching cement ( cement handling
Day
for batching other materials
Day
for loading mortar pans
Day
for laying
Day
for conveying concrete
Day
for cleaning / washing / curing
Day
6
Labour cost of shuttering
sqm
7
Labour cost of scaffolding @
15%
Total cost of Labour
labour component/unit qty
928.10
Add contractor's profit and overhead charges
14% 129.90
labour component/unit qty (including contractor's profit)
1058.00

Rate
in Rs.

590.00
2655.00
1180.00
885.00
4681.65
295.00
1195.01
179.25
Rs: 14729.21

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D.Add for contractor's profit and overheads on (A+B+C)
Lead Charges for 1 Km for FA
6.98
Lead Charges for 1 Km for CA
12.70

cum @
cum @

Lead Charges for 1Km for Cement (including Loading


and Unloading Charges)
4.49
tonne @
Total cost for
15.87
Rate per
cum
(A+B+C+D)/15.87

IRR-DAW-2-9

31.5 Rs./Cum
30.4 Rs./Cum
124.6 Rs./Tonne
cum

40790.59
925.20
14729.21
56445.00
7902.3
219.9582
385.96

559.60477
Rs: 65512.82
Rs: 4128.10

Providing and laying insitu vibrated M-20 ( 28 days cube compressive


strength not less than 20 N / sq mm ) grade cement concrete using 20 mm
down size approved, clean, hard, graded aggregates including cost of all
materials, machinery, labour, formwork, centering, scaffolding, cleaning,
batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc.,complete for RCC works of spillway bridge, blockouts and such
other similar structures with conjested reinforcement with initial lead

70

Dam and Allied Works - Item Unit Rates 2014-15

upto 1 km and all lifts. ( Cement content : 330 kg / cum with use of
super plasticiser, CA : 0.80 cum, Blending Ratio of CA -- 65:35,
FA : 0.44 cum)
DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4
5
6

Cement for mix


Cement for incidentals @ 3 kg/ cum
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened )
Super plasticiser
Use rate of shuttering
Scaffolding of shuttering @

B. MACHINERY:
Sl No
Description
1
2
3

Unit

Quantity

kg
kg
cum
cum
cum
ltr
sqm
100%
Total cost of Materials

Unit

Quantity

Concrete mixer 300 / 200 ltr ( ele


Hour
Fuel / Energy charges
Hour
10 hp pump ( ele )
Hour
Fuel / Energy charges
Hour
Needle vibrator 40 mm dia ( ele )
Hour
Fuel / Energy charges
Hour
Total hire charges of Machinery

C. LABOUR:
Sl No
Description

4445.1
40.41
7.00
3.77
5.93
17.78
33.68

UNIT:
13.47 cum
Rate
Amount
in Rs.
in Rs
4.00 17780.40
4.00 161.64
1210.00 8475.32
875.00 3300.15
462.00 2738.18
80.00 1422.43
235.84 7941.91
7941.91
Rs: 49761.94

Rate
in Rs.
8.00
8.00
1.00
1.00
8.00
8.00

Unit

Quantity

1
2
3
4
5

Crew for Concrete mixer


Hour
Crew for Pump
Hour
Crew for Needle vibrator
Hour
Mason Class-I
Day
mazdoor
for batching cement ( cement handling )
Day
for batching other materials
Day
for loading mortar pans
Day
for laying
Day
for conveying concrete
Day
for cleaning/ washing/ curing
Day
6
Labour cost of shuttering
sqm
7
Labour cost of scaffolding @
100%
Total cost of Labour
labour component/unit qty
1315.40
Add contractor's profit and overhead charges
14% 184.20
labour component/unit qty (including contractor's profit)
1499.60

51.70
38.00
6.70
76.10
8.00
7.60
Rs:

Rate
in Rs.
8.00
1.00
8.00
1.00

189.80
72.10
136.60
385.00

2.00
9.00
4.00
3.00
13.47
1.00
33.68

295.00
295.00
295.00
295.00
295.00
295.00
75.30
Rs:

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:
Rs.

Total
D.Add for contractor's profit and overheads on (A+B+C)
Lead Charges for 1 Km for FA
5.93
cum @
Lead Charges for 1 Km for CA
10.78
cum @
Lead Charges for 1Km for Cement (including Loading
4.49
tonne @
and Unloading Charges)
Total cost for
13.47
Rate per
cum
(A+B+C+D)/13.47

IRR-DAW-2-10

14%
31.5 Rs./Cum
30.4 Rs./Cum
124.6 Rs./Tonne
cum

Amount
in Rs
413.60
304.00
6.70
76.10
64.00
60.80
925.20

Amount
in Rs
1518.40
72.10
1092.80
385.00
0.00
590.00
2655.00
1180.00
885.00
3973.65
295.00
2535.73
2535.73
17718.41

49761.94
925.20
17718.41
68405.55
9576.78
186.6942
327.59

558.89455
Rs: 79055.51
Rs: 5869.00

Providing and forming porous concrete body drain of size 68.5 x 68.5 cm
with 23 cm diameter central hole using cement and 20 mm down
approved, clean, hard, graded coarse aggregates in 1 : 3.50 proportion by
volume including cost of all materials, machinery, labour, formwork, curing
etc., complete with initial lead upto 1 km and all lifts.
(M15 Cement content : 400kg/cum, CA : 1cum,
Blending Ratio of CA -- 65:35)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3

Cement
Coarse aggregate 20-10 mm
Coarse aggregate 10-4.75 mm

Unit
kg
cum
cum

Quantity
3424
5.56
3.00

UNIT:
20.00 Rm
Rate
Amount
in Rs.
in Rs
4.00 13696.00
1210.00 6732.44
875.00 2621.50

71

Dam and Allied Works - Item Unit Rates 2014-15

Use rate of shuttering


Total cost of Materials

B. MACHINERY:
Sl No
Description
1
2

sqm

76.00

Unit

Quantity

Concrete mixer 300 / 200 ltr ( ele )


Hour
Fuel / Energy charges
Hour
10 hp pump ( ele )
Hour
Fuel / Energy charges
Hour
Total hire charges of Machinery

C. LABOUR:
Sl No
Description

65.68 4991.76
Rs: 28041.70

Rate
in Rs.
8.00
8.00
0.50
0.50

Unit

Quantity

1
2
3
4

Crew for Concrete mixer


Hour
Crew for Pump
Hour
Mason Class-I
Day
mazdoor
for batching cement ( cement handling
Day
for batching other materials
Day
for loading mortar pans
Day
for laying & packing concrete
Day
for conveying concrete
Day
5
Fitter shuttering
Day
Total cost of Labour
labour component/unit qty
452.00
Add contractor's profit and overhead charges
14% 63.30
labour component/unit qty (including contractor's profit)
515.30

51.70
38.00
6.70
76.10
Rs:

Rate
in Rs.
8.00
0.50
1.00
2.00
6.00
2.00
2.00
8.56
3.00

Amount
in Rs
189.80 1518.40
72.10 36.05
385.00 385.00
295.00
295.00
295.00
295.00
295.00
345.00
Rs:

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:
Rs.

Total
D.Add for contractor's profit and overheads on (A+B+C)
Lead Charges for 1 Km for CA
8.56
cum @
Lead Charges for 1Km for Cement (including Loading
and Unloading Charges)
3.42
tonne @
Total cost for
20.00
Rate per
Rm
(A+B+C+D)/20

IRR-DAW-2-11
(a)

14%
30.4 Rs./Cum
124.6 Rs./Tonne
Rm

Amount
in Rs
413.60
304.00
3.35
38.05
759.00

590.00
1770.00
590.00
590.00
2525.20
1035.00
9039.65

28041.70
759.00
9039.65
37840.35
5297.65
260.22

426.6304
Rs: 43824.85
Rs: 2191.20

Providing and laying insitu vibrated M-20 ( 28 days cube compressive


strength not less than 20 N / sq mm ) grade cement concrete using 20 mm
down size approved, clean, hard, graded aggregates including cost of
all materials, machinery, labour, formwork, centering, scaffolding, cleaning,
batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc.,complete for RCC solid parapet consisting of 35 cm x 20 cm kerb,
35 cm x 35 cm x 1 m pillars spaced approximately at 3.35 m c / c, 12.5 cm
thick wall 80 cm height with 12.5 cm thick and 35 cm wide coping slab for
wall and 12 .5 cm thick 40 cm x 40 cm coping for pillars with top edges of
kerb and coping chamferred / rounded as directed etc., complete
( excluding cost of providing and placing reinforcement steel and gate )
with initial lead upto 1 km and all lifts.
( Cement content 350 kg / cum with use of super plasticiser( 0.4% by wt.
of cement), CA : 0.80 cum, Blending Ratio of CA--65:35, FA : 0.44 cum)

72

Dam and Allied Works - Item Unit Rates 2014-15

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4
5
6
7

Cement mix
Cement for incidentals @ 5 kg / cum
Coarse aggregate 20-10 mm
Coarse aggregate 10-4.75 mm
Fine aggregate (Un-Screened )
Super plasticiser
Use rate of shuttering
Scaffolding of shuttering @
Sundries
Total cost of Materials

B. MACHINERY:
Sl No
Description
1
2
3

Unit

Quantity

kg
kg
cum
cum
cum
kg
sqm

3034.5
43.35
4.51
2.43
3.81
12.14
95.00
15%

LS

2.00

Unit

Quantity

Concrete mixer 300 / 200 ltr ( ele )


Hour
Fuel / Energy charges
Hour
Needle vibrator 40 mm ( ele )
Hour
Fuel / Energy charges
Hour
10 hp pump ( ele )
Hour
Fuel / Energy charges
Hour
Total hire charges of Machinery

C. LABOUR:
Sl No
Description

UNIT:
36.00 Rm
Rate
Amount
in Rs.
in Rs
4.00 12138.00
4.00 173.40
1210.00 5457.10
875.00 2126.25
462.00 1760.22
80.00 971.04
235.84 22404.80
3360.72
41.00 82.00
Rs: 48473.53

Rate
in Rs.
51.70
38.00
8.00
7.60
6.70
76.10
Rs:

Amount
in Rs
413.60
304.00
64.00
60.80
3.35
38.05
883.80

8.00
0.50
8.00
2.00
1.00

189.80
72.10
136.60
385.00
370.00

Amount
in Rs
1518.40
36.05
1092.80
770.00
370.00

2.00
9.00
4.00
2.00
8.67
2.00
95.00

295.00
295.00
295.00
295.00
295.00
295.00
75.30

14%

Rs:
Rs:
Rs:
Rs:
Rs.

8.00
8.00
8.00
8.00
0.50
0.50

Unit

Quantity

1
2
3
4
5
6

Crew for Concrete mixer


Hour
Crew for Pump
Hour
Crew for Vibrator
Hour
Mason Class-I
Day
work inspector
Day
mazdoor
for batching cement ( cement handling )
Day
for batching other materials
Day
for loading mortar pans
Day
for laying & packing concrete
Day
for conveying concrete
Day
for curing & miscellaneous
Day
7
Labour for shuttering
sqm
8
Labour for scaffolding @
15%
Total cost of Labour
labour component/unit qty
560.50
Add contractor's profit and overhead charges
0.14 78.50
labour component/unit qty (including contractor's profit)
639.00

Rate
in Rs.

590.00
2655.00
1180.00
590.00
2557.65
590.00
7153.50
1073.03
Rs: 20176.43

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D.Add for contractor's profit and overheads on (A+B+C)
Lead Charges for 1 Km for FA
3.81
cum @
Lead Charges for 1 Km for CA
6.94
cum @
Lead Charges for 1Km for Cement (including Loading
and Unloading Charges)
3.08
tonne @
Total cost for
36.00
Rate per
Rm
(A+B+C+D)/36

IRR-DAW-2-12
(b)

31.5 Rs./Cum
30.4 Rs./Cum
124.6 Rs./Tonne
Rm

48473.53
883.80
20176.43
69533.76
9734.73
120.015
210.98

383.50011
Rs: 79982.98
Rs: 2221.70

Providing and laying insitu vibrated M-20 ( 28 days cube compressive


strength not less than 20 N / sq mm ) grade cement concrete using 20 mm
down size approved, clean, hard, graded aggregates including cost of all
materials, machinery, labour, formwork, centering, scaffolding, cleaning,
batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc.,complete for RCC ornamental parapet consisting of 35 cm x 20 cm
kerb, 35 cm x 35 cm x 1 m pillars spaced approximately at 3.5 m apart,
20 cm x 15 cm posts 80 cm height approximately 30 cm c / c with 12.5 cm
thick and 35 cm wide coping slab for posts and pillars with top edges of
kerb and coping chamferred or rounded as directed etc., complete
( excluding cost of providing and placing reinforcement steel and gate ) with
initial lead upto 1 km and all lifts.
( Cement content : 350 kg / cum with use of super plasticiser(0.4% by wt.
of cement, CA : 0.80 cum, Blending Ratio of CA--65:35, FA : 0.44 cum)

73

Dam and Allied Works - Item Unit Rates 2014-15

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4
5
6
7

Cement mix
Cenent for incidentals @ 5 kg / cum
Coarse aggregate 20-10 mm
Coarse aggregate 10-4.75 mm
Fine aggregate (Un-Screened )
Super plasticiser
Use rate of shuttering
Scaffolding of shuttering @
Sundries
Total cost of Materials

B. MACHINERY:
Sl No
Description
1
2
3

Unit

Quantity

kg
kg
cum
cum
cum
kg
sqm

2450
35.00
3.64
1.96
3.08
9.80
115.00
15%

LS

2.00

Unit

Quantity

Concrete mixer 300 / 200 ltr ( ele


Hour
Fuel / Energy charges
Hour
Needle vibrator 40 mm ( ele )
Hour
Fuel / Energy charges
Hour
10 hp pump ( ele )
Hour
Fuel / Energy charges
Hour
Total hire charges of Machinery

C. LABOUR:
Sl No
Description

UNIT:
36.00 Rm
Rate
Amount
in Rs.
in Rs
4.00 9800.00
4.00 140.00
1210.00 4404.40
875.00 1715.00
462.00 1422.96
80.00 784.00
235.84 27121.60
4068.24
41.00 82.00
Rs: 49538.20

Rate
in Rs.
51.70
38.00
8.00
7.60
6.70
76.10
Rs:

Amount
in Rs
413.60
304.00
64.00
60.80
3.35
38.05
883.80

8.00
0.50
8.00
2.00
1.00

189.80
72.10
136.60
385.00
370.00

Amount
in Rs
1518.40
36.05
1092.80
770.00
370.00

2.00
9.00
4.00
2.00
7.00
2.00
115.00

295.00
295.00
295.00
295.00
295.00
295.00
75.30

14%

Rs:
Rs:
Rs:
Rs:
Rs.

8.00
8.00
8.00
8.00
0.50
0.50

Unit

Quantity

1
2
3
4
5
6

Crew for Concrete mixer


Hour
Crew for Pump
Hour
Crew for Vibrator
Hour
Mason Class-I
Day
work inspector
Day
mazdoor
for batching cement ( cement handling )
Day
for batching other materials
Day
for loading mortar pans
Day
for laying & packing concrete
Day
for conveying concrete
Day
for curing & miscellaneous
Day
7
Labour for shuttering
sqm
8
Labour for scaffolding @
15%
Total cost of Labour
labour component/unit qty
594.90
Add contractor's profit and overhead charges
0.14 83.30
labour component/unit qty (including contractor's profit)
678.20

Rate
in Rs.

590.00
2655.00
1180.00
590.00
2065.00
590.00
8659.50
1298.93
Rs: 21415.68

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D.Add for contractor's profit and overheads on (A+B+C)
Lead Charges for 1 Km for FA
3.08
cum @
Lead Charges for 1 Km for CA
5.60
cum @
Lead Charges for 1Km for Cement (including Loading
2.49
tonne @
and Unloading Charges)
Total cost for
36.00
Rate per
Rm
(A+B+C+D)/36

IRR-DAW-2-13

31.5 Rs./Cum
30.4 Rs./Cum
124.6 Rs./Tonne
Rm

49538.20
883.80
21415.68
71837.68
10057.27
97.02
170.24

309.631
Rs: 82471.84
Rs: 2290.90

Providing and laying insitu M- 25 ( 28 days cube compressive strength not


less than 25 N / sq mm ) grade cement concrete using 20 mm down size
approved, clean, hard, graded aggregates for wearing coat including cost
of all materials, machinery, labour, formwork, cleaning, batching, mixing,
placing in position in alternate panels, levelling, compacting, finishing,

74

Dam and Allied Works - Item Unit Rates 2014-15

curing, packing joints with asphalt mortar etc., complete


with initial lead upto 1 km and all lifts.
( Cement content : 380 kg / cum with use of super plasticiser(0.4% by
wt. of cement, CA : 0.80 cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4
5
6

Cement for mix


Cement for incidentals @ 5 kg / cum
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened )
Super Plasticizer
Use rate of shuttering
Sundries ( asphalt mortar etc )
Total cost of Materials

B. MACHINERY:
Sl No
Description
1
2

Unit

Quantity

kg
kg
cum
cum
cum
kg
sqm
LS

4446
58.50
6.084
3.276
5.265
17.78
5.85
5.00

Unit

Quantity

Concrete mixer 300/200 ltr ( ele )


Hour
Fuel / Energy charges
Hour
10 hp pump ( ele )
Hour
Fuel / Energy charges
Hour
Total hire charges of Machinery

C. LABOUR:
Sl No
Description

UNIT:
11.70 cum
Rate
Amount
in Rs.
in Rs
4.00
17784.00
4.00
234.00
1210.00
7361.64
875.00
2866.50
462.00
2432.43
80.00
1422.72
235.84
1379.66
41.00
205.00
Rs:
33685.95

Rate
in Rs.
51.70
38.00
6.70
76.10
Rs:

Amount
in Rs
413.60
304.00
3.35
38.05
759.00

8.00
0.50
3.00
1.00

189.80
72.10
385.00
370.00

Amount
in Rs
1518.40
36.05
1155.00
370.00

2.00
9.00
4.00
5.00
11.70
1.00
5.85

295.00
295.00
295.00
295.00
295.00
295.00
75.30
Rs:

590.00
2655.00
1180.00
1475.00
3451.50
295.00
440.51
13166.46

8.00
8.00
0.50
0.50

Unit

Quantity

1
2
3
4
5

Crew for Concrete mixer


Hour
Crew for Pump
Hour
Mason Class-I
Day
work inspector
Day
mazdoor
for batching cement ( cement handling )
Day
for batching materials
Day
for loading mortar pans
Day
for laying & compacting
Day
for conveying concrete
Day
for cleaning/ washing/ curing
Day
6
Labour cost for shuttering
sqm
Total cost of Labour
labour component/unit qty
1125.30
Add contractor's profit and overhead charges
0.14 157.50
labour component/unit qty (including contractor's profit)
1282.80

Rate
in Rs.

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
33685.95
Rs:
759.00
Rs:
13166.46
Rs:
47611.41
Rs. 6665.6
165.8475
284.54

Total
D.Add for contractor's profit and overheads on (A+B+C)
Lead Charges for 1 Km for FA
5.27
Lead Charges for 1 Km for CA
9.36

14%
cum @
cum @

31.5 Rs./Cum
30.4 Rs./Cum

Lead Charges for 1Km for Cement (including Loading


and Unloading Charges)
4.50
tonne @
Total cost for
11.70
Rate per
cum
(A+B+C+D)/11.70

IRR-DAW-2-14

DATA:

124.6 Rs./Tonne
cum

561.2607
Rs: 55288.66
Rs: 4725.50

Pre-cooling to control placement temperature of cement concrete in the


range of 18 to 21 C at the concrete placement point by inundation of coarse
aggregates and adding flaked ice as part of mixing water including cost of
all materials, machinery, labour etc., complete with all leads and lifts.
RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1

Sundries ( amonia gas etc)

Unit

Quantity

LS

3.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No
Description
1

Ice maker unit consisting of:

Unit
Hour

Quantity

UNIT:
500 cum
Rate
Amount
in Rs.
in Rs
41.00 123.00
0.00 0.00
Rs:
123.00

Rate
in Rs.
24.00

Amount
in Rs
170.20 4084.80

75

Dam and Allied Works - Item Unit Rates 2014-15

Compressor 125 hp - 1 No
Condenser with 30 hp motor - 1 No.
Ice makers 10 t / day each - 3 Nos.
Pump 2 hp for ice cutting - 3 Nos.
Pump 2 hp for pumping water-3 Nos.
Screw conveyor with 15 hp motor -1
Ice elevator with 5 hp motor - 1 No.
Fuel / Energy charges for system
Hour
Total hire charges of Machinery
C. LABOUR:
Sl No
Description

24.00

Unit

Quantity

1
2

Crew for Ice maker unit


Hour
mazdoor
for Ice chamber ( 2 x 3 )
Day
for miscellaneous works ( 1 x 3 )
Day
Total cost of Labour
labour component/unit qty
10.80
Add contractor's profit and overhead charges
0.14 1.50
labour component/unit qty (including contractor's profit)
12.30

1084.30 26023.20
Rs: 30108.00

Rate
in Rs.
24.00
6.00
3.00

295.00 1770.00
295.00 885.00
Rs: 5388.60

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:

Total
D.Add for contractor's profit and overheads on (A+B+C)
Total cost for
500.00 cum
Rate per
cum
(A+B+C+D)/500

IRR-DAW-2-15

14%

123.00
30108.00
5388.60
35619.60
4986.74
40606.34
81.20

Conveying and fixing elastomeric bearing for spillway bridge including


cleaning and preparing surface, mixing and applying adhesive, fixing bearing
in correct position etc., including cost of all materials except bearings,
machinery, labour etc., complete with all leads and lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2

Synthetic adhesive ( Resin + Hardener)


Sundries
Total cost of Materials

Unit

Quantity

kg
LS

B. MACHINERY:
Sl No
Description

0.60
2.00

Unit

Quantity

Nil

UNIT:
6.00 Nos.
Rate
Amount
in Rs.
in Rs
348.00 208.80
41.00 82.00
Rs: 290.80

Rate
in Rs.

Amount
in Rs
0.00 0.00
0.00 0.00
Rs: 0.00

Rate
in Rs.

Amount
in Rs
440.00
370.00
590.00
1400.00

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
Description
1
2
3

Marker / Erector
work inspector
mazdoor

Unit

Quantity

Day
Day
Day

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

1.00
1.00
2.00

440.00
370.00
295.00
Rs:

233.30
0.14 32.70
266.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D.Add for contractor's profit and overheads on (A+B+C)
Total cost for
6.00 Nos.
Rate per
Each
(A+B+C+D)/6

IRR-DAW-2-16

Amount
in Rs
113.90 2733.60

Total
14%

Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:

290.80
0.00
1400.00
1690.80
236.71
1927.51
321.30

Providing and constructing 150 mm dia hume pipe weep holes for
concrete / masonry walls including providing 20 x 20 x 20 cm size porous
concrete block made of cement and 20 mm down coarse aggregate in
1 : 4 proportion including 10 cm thick sand backing at the junction of wall
and soil back fill, cost of all materials, machinery, labour etc., complete
with lead upto 1 km and all lifts.

76

Dam and Allied Works - Item Unit Rates 2014-15

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4

150 mm dia hume pipe


Cement
20 - 10 mm coarse aggregate
Sand for filling
Total cost of Materials

Unit
Rm
kg
cum
cum

B. MACHINERY:
Sl No
Description
1

Quantity
2.90
3.00
0.01
0.02

Unit

Quantity

Nil

UNIT:
3.00 Rm
Rate
Amount
in Rs.
in Rs
330.00 957.00
4.00 12.00
1210.00 9.68
342.00 6.84
Rs: 985.52

Rate
in Rs.

Amount
in Rs
0.00 0.00
0.00 0.00
Rs: 0.00

Rate
in Rs.

Amount
in Rs
345.00 86.25
295.00 73.75
Rs: 160.00

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
Description
1
2

Mason Class-II
mazdoor

Unit

Quantity

Day
Day

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

0.25
0.25
53.30
0.14 7.50
60.80

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:
Rs.

Total
D.Add for contractor's profit and overheads on (A+B+C)
Lead Charges for 1 Km for FA
0.02
cum @
Lead Charges for 1 Km for CA
0.01
cum @
Lead Charges for 1Km for Cement (including Loading
0.00
tonne @
and Unloading Charges)
Total cost for
3.00
Rate per
Rm
(A+B+C+D)/3

IRR-DAW-2-17

14%
31.5 Rs./Cum
30.4 Rs./Cum
124.6 Rs./Tonne
Rm

985.52
0.00
160.00
1145.52
160.37
0.63
0.24

0.3738
Rs: 1307.14
Rs: 435.70

Providing and forming expansion joint for spillway bridge consisting of


75 x 75 x 6 mm angles 2 numbers provided with 25 cm long 12 mm dia.
anchors fixed to both flanges at 15 cm c /c and 140 x 6 mm plate welded
on top of one of the angle including cost of all materials, machinery, labour,
providing and fixing 38 mm thick joint filler board matching the thickness of
wearing coat, painting etc., complete with lead upto 1 km and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4
5
6

Structural steel plate


Structural steel angle
12 dia steel anchors
Welding electrodes
Joint filler board 19 mm thick
Sundries ( cutting gas / paint etc )
Total cost of Materials

B. MACHINERY:
Sl No
Description
1
2

Quantity

kg
kg
kg
Nos
sqm
LS

Unit

50.70
104.50
27.40
70.00
1.00
1.50

Quantity

Welding set
Hour
Fuel / Energy charges
Hour
Sundries (cutting torch/ welding guns etc)
LS
Total hire charges of Machinery

C. LABOUR:
Sl No
Description
1
2
3

Unit

Marker / Fabricator / Erector


Gas cutter / Welder
mazdoor

Unit

UNIT:
7.50 Rm
Rate
Amount
in Rs.
in Rs
46.00 2332.20
45.00 4702.50
46.50 1274.10
11.00 770.00
630.00 630.00
41.00 61.50
Rs: 9770.30

Rate
in Rs.
8.00
8.00
2.00

Quantity

Day
Day
Day
Total cost of Labour
labour component/unit qty
243.70
Add contractor's profit and overhead charges
0.14 34.10
labour component/unit qty (including contractor's profit)
277.80

16.00
91.30
41.00
Rs:

Amount
in Rs
128.00
730.40
82.00
940.40

440.00
385.00
295.00
Rs:

Amount
in Rs
660.00
577.50
590.00
1827.50

Rate
in Rs.
1.50
1.50
2.00

77

Dam and Allied Works - Item Unit Rates 2014-15

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
14%

D.Add for contractor's profit and overheads on (A+B+C)


Lead Charges for 1Km for Steel (including Loading
and Unloading Charges)
Total cost for
Rate per
Rm

0.18

tonne @

7.50
(A+B+C+D)/7.50

145.6 Rs./Tonne
Rm

IRR_DAW-3

MASONRY & GUNITING WORKS :

IRR-DAW-3-1

Providing and constructing un-coursed rubble stone masonry using


approved stones in cement mortar 1 : 3 proportion including cost of all
materials, machinery, labour, scaffolding, cleaning, packing mortar, wedging
stone chips, curing etc., complete with initial lead upto 1 km and all lifts.
( Cement content : 190 kg/cum of masonry, rubble stones : 0.85 cum,
stone chips : 0.15 cum/cum, FA : 0.4 cum)

DATA:

Rs:
Rs:
Rs:
Rs:
Rs.

26.58656
Rs: 14320.14
Rs: 1909.40

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4

Cement for mortar


Rubble stones
Stone chips
Sand (Screened )

B. MACHINERY:
Sl No
Description
1
2

Concrete mixer 300 / 200 ltr ( ele )


Fuel / Energy charges
10 hp pump ( ele )
Fuel / Energy charges
Total hire charges of Machinery

C. LABOUR:
Sl No
Description

UNIT:
25.00
Unit

Quantity

kg
cum
cum
cum
Total cost of Materials

Unit

Rate
in Rs.
4750
21.25
3.75
10

4.00
318.00
340.00
606.00
Rs:

Quantity

Hour
Hour
Hour
Hour

Rate
in Rs.

Unit

51.70
38.00
6.70
76.10
Rs:

8.00
1.00
1.00
2.50
4.00
16.00

189.80
72.10
370.00
385.00
345.00
345.00

Amount
in Rs
1518.40
72.10
370.00
962.50
1380.00
5520.00

2.00
6.00
4.00
10.00
1.00
4.00
12.00

295.00
295.00
295.00
295.00
295.00
295.00
295.00
Rs:

590.00
1770.00
1180.00
2950.00
295.00
1180.00
3540.00
21328.00

Rs:
Rs:
Rs:
Rs:
Rs.

33092.50
800.40
21328.00
55220.90
7730.93
315
760.00

Quantity

Crew for Concrete mixer


Hour
Crew for Pump
Hour
work inspector
Day
Mason Class-I
Day
Mason Class-II
Day
Chavali
Day
mazdoor
for batching cement ( cement handling )
Day
for batching sand
Day
for loading mortar pans
Day
for laying & packing mortar
Day
for loading chips
Day
for washing rubble / finishing / curing
Day
for conveying mortar / chips
Day
Total cost of Labour
labour component/unit qty
853.10
Add contractor's profit and overhead charges
0.14 119.40
labour component/unit qty (including contractor's profit)
972.50

Rate
in Rs.

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D.Add for contractor's profit and overheads on (A+B+C)
Lead Charges for 1 Km for FA
10.00
cum @
Lead Charges for 1 Km for Stones/Stone Chips
25.00
cum @
Lead Charges for 1Km for Cement (including Loading
4.75
tonne @
and Unloading Charges)
Total cost for
25.00
Rate per
cum
(A+B+C+D)/25

cum
Amount
in Rs
19000.00
6757.50
1275.00
6060.00
33092.50

Amount
in Rs
413.60
304.00
6.70
76.10
800.40

8.00
8.00
1.00
1.00

1
2
3
4
5
6
7

IRR-DAW-3-2

9770.30
940.40
1827.50
12538.20
1755.35

14%
31.5 Rs./Cum
30.4 Rs./Cum
124.6 Rs./Tonne
cum

591.85
Rs: 64618.68
Rs: 2584.70

Providing and constructing un-coursed rubble stone masonry using approved stones in
cement mortar 1 : 4 proportion including cost of all materials, machinery, labour, scaffolding,
cleaning, packing mortar, wedging stone chips, curing etc., complete with initial lead upto
1 km and all lifts.

78

Dam and Allied Works - Item Unit Rates 2014-15

( Cement content : 143 kg/cum of masonry, rubble stones : 0.85 cum,


stone chips : 0.15 cum/cum, FA : 0.4 cum)
For 1 cum masonry :DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4

Cement for mortar


Rubble stones
Stone chips
Sand (Screened )
Total cost of Materials

B. MACHINERY:
Sl No
Description
1
2

Concrete mixer 300 / 200 ltr(ele)


Fuel / Energy charges
10 hp pump
Fuel / Energy charges
Total hire charges of Machinery

C. LABOUR:
Sl No
Description

Unit

Quantity

kg
cum
cum
cum

Unit

3575
21.25
3.75
10

Quantity

Hour
Hour
Hour
Hour

Unit

UNIT:
25.00 cum
Rate
Amount
in Rs.
in Rs
4.00 14300.00
318.00 6757.50
340.00 1275.00
606.00 6060.00
Rs:
28392.50

Rate
in Rs.
51.70
38.00
6.70
76.10
Rs:

Amount
in Rs
413.60
304.00
6.70
76.10
800.40

8.00
1.00
1.00
2.50
4.00
16.00

189.80
72.10
370.00
385.00
345.00
345.00

Amount
in Rs
1518.40
72.10
370.00
962.50
1380.00
5520.00

2.00
6.00
4.00
10.00
1.00
4.00
12.00

295.00
295.00
295.00
295.00
295.00
295.00
295.00
Rs:

590.00
1770.00
1180.00
2950.00
295.00
1180.00
3540.00
21328.00

Rs:
Rs:
Rs:
Rs:
Rs.

28392.50
800.40
21328.00
50520.90
7072.93
315
760.00

8.00
8.00
1.00
1.00

Quantity

1
2
3
4
5
6
7

Crew for Concrete mixer


Hour
Crew for Pump
Hour
work inspector
Day
Mason Class-I
Day
Mason Class-II
Day
Chavali
Day
mazdoor
for batching cement ( cement handling )
Day
for batching sand
Day
for loading mortar pans
Day
for laying & packing mortar
Day
for loading chips
Day
for washing rubble / finishing / curing
Day
for conveying mortar / chips
Day
Total cost of Labour
labour component/unit qty
853.10
Add contractor's profit and overhead charges
0.14 119.40
labour component/unit qty (including contractor's profit)
972.50

Rate
in Rs.

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D.Add for contractor's profit and overheads on (A+B+C)
Lead Charges for 1 Km for FA
10.00
cum @
Lead Charges for 1 Km for Stones/Stone Chips
25.00
cum @
Lead Charges for 1Km for Cement (including Loading
and Unloading Charges)
3.58
tonne @
Total cost for
25.00
Rate per
cum
(A+B+C+D)/25

IRR-DAW-3-3

Total
14%
31.5 Rs./Cum
30.4 Rs./Cum
124.6 Rs./Tonne
cum

445.445
Rs: 59114.28
Rs: 2364.60

Providing and constructing coursed rubble face stone masonry using


approved rubble stones in cement mortar 1 : 3 proportion including cost
of all materials, machinery, labour, scaffolding, ramps, cleaning, packing
mortar, wedging stone chips, curing etc., with initial lead upto 1 km
and all lifts.
( Thickness of the CR face assumed: 0.75 m,Cement content : 178 kg/cum of masonry,
rubble stones : 0.35 cum, stone chips : 0.15 cum/cum, FA : 0.375 cum,
CR stones 30 x 30 x 45 cm : 9.75 No, CR stones 30 x 30 x 60 cm : 3.25 No)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4
5
6

Unit

Cement for mortar


kg
Coursed rubble stone 30 x 30 x 45 cm
Nos
Coursed rubble stone 30 x 30 x 60 cm
Nos
Rubble stones
cum
Stone chips
cum
Sand (Screened )
cum
Total cost of Materials

Quantity
4450
244
82
8.75
3.75
9.375

UNIT:
25.00 cum
Rate
Amount
in Rs.
in Rs
4.00 17800.00
20.00 4880.00
23.00 1886.00
318.00 2782.50
340.00 1275.00
606.00 5681.25
Rs: 34304.75

79

Dam and Allied Works - Item Unit Rates 2014-15

B. MACHINERY:
Sl No
Description

Unit

Quantity

Concrete mixer 300 / 200 ltr ( ele )


Hour
Fuel / Energy charges
Hour
2
10 hp pump ( ele )
Hour
Fuel / Energy charges
Hour
Total hire charges of Machinery
C. LABOUR:
Sl No
Description
Unit

Rate
in Rs.
51.70
38.00
6.70
76.10
Rs:

Amount
in Rs
413.60
304.00
6.70
76.10
800.40

8.00
1.00
1.00
7.00
2.50
4.00
16.00

189.80
72.10
370.00
345.00
385.00
345.00
345.00

Amount
in Rs
1518.40
72.10
370.00
2415.00
962.50
1380.00
5520.00

2.00
6.00
4.00
10.00
1.00
4.00
12.00

295.00
295.00
295.00
295.00
295.00
295.00
295.00
Rs:

590.00
1770.00
1180.00
2950.00
295.00
1180.00
3540.00
23743.00

Rs:
Rs:
Rs:
Rs:
Rs.

34304.75
800.40
23743.00
58848.15
8238.74
295.3125
815.02

8.00
8.00
1.00
1.00

Quantity

1
2
3
4
5
6
7
8

Crew for Concrete mixer


Hour
Crew for Pump
Hour
work inspector
Day
Stone chiseller Cl -II
Day
Mason Class-I
Day
Mason Class-II
Day
Chavali
Day
mazdoor
for batching cement ( cement handling )
Day
for batching sand
Day
for loading mortar pans
Day
for laying & packing mortar
Day
for loading chips
Day
for washing rubble / finishing / curing
Day
for conveying mortar / chips
Day
Total cost of Labour
labour component/unit qty
949.70
Add contractor's profit and overhead charges
0.14 133.00
labour component/unit qty (including contractor's profit)
1082.70

Rate
in Rs.

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D.Add for contractor's profit and overheads on (A+B+C)
Lead Charges for 1 Km for FA
9.38
Lead Charges for 1 Km for Stones/Stone Chips
26.81

14%
cum @
cum @

31.5 Rs./Cum
30.4 Rs./Cum

Lead Charges for 1Km for Cement (including Loading


and Unloading Charges)
4.45
tonne @
Total cost for
25.00
Rate per
cum
(A+B+C+D)/25

IRR-DAW-3-4

124.6 Rs./Tonne
cum

554.47
Rs: 68751.70
Rs: 2750.10

Providing and constructing coursed rubble face stone masonry using


approved rubble stones in cement mortar 1 : 4 proportion including cost of
all materials, machinery, labour, scaffolding, ramps, cleaning, packing
mortar, wedging stone chips, curing etc., with initial lead upto 1 km and
all lifts.
( Cement content : 134 kg/cum of masonry, rubble stones : 0.35 cum,
stone chips : 0.15 cum/cum, FA : 0.375 cum,
CR stones 30 x 30 x 45 cm : 9.75 No, CR stones 30 x 30 x 60 cm : 3.25 No)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4
5
6

Cement for mortar


Coursed rubble stone 30 x 30 x 45 cm
Coursed rubble stone 30 x 30 x 60 cm
Rubble stones
Stone chips
Sand (Screened )
Total cost of Materials

B. MACHINERY:
Sl No
Description
1
2

Unit

Quantity

kg
Nos
Nos
cum
cum
cum

Unit

3350
244
82
8.75
3.75
9.375

Quantity

Concrete mixer 300 / 200 ltr ( ele )


Hour
Fuel / Energy charges
Hour
10 hp pump ( ele )
Hour
Fuel / Energy charges
Hour
Total hire charges of Machinery

C. LABOUR:
Sl No
Description

Unit

UNIT:
25.00 cum
Rate
Amount
in Rs.
in Rs
4.00 13400.00
20.00 4880.00
23.00 1886.00
318.00 2782.50
340.00 1275.00
606.00 5681.25
Rs: 29904.75

Rate
in Rs.
8.00
8.00
1.00
1.00

Quantity

51.70
38.00
6.70
76.10
Rs:

Rate
in Rs.

Amount
in Rs
413.60
304.00
6.70
76.10
800.40

Amount
in Rs

80

Dam and Allied Works - Item Unit Rates 2014-15

1
2
3
4
5
6
7
8

Crew for Concrete mixer


Hour
Crew for Pump
Hour
work inspector
Day
Stone chiseller Cl -II
Day
Mason Class-I
Day
Mason Class-II
Day
Chavali
Day
mazdoor
for batching cement ( cement handling )
Day
for batching sand
Day
for loading mortar pans
Day
for laying & packing mortar
Day
for loading chips
Day
for washing rubble / finishing / curing
Day
for conveying mortar / chips
Day
Total cost of Labour
labour component/unit qty
949.70
Add contractor's profit and overhead charges
14% 133.00
labour component/unit qty (including contractor's profit)
1082.70

8.00
1.00
1.00
7.00
2.50
4.00
16.00

189.80
72.10
370.00
345.00
385.00
345.00
345.00

1518.40
72.10
370.00
2415.00
962.50
1380.00
5520.00

2.00
6.00
4.00
10.00
1.00
4.00
12.00

295.00
295.00
295.00
295.00
295.00
295.00
295.00

590.00
1770.00
1180.00
2950.00
295.00
1180.00
3540.00
23743.00

Rs:
Rs:
Rs:
Rs:
Rs.

29904.75
800.40
23743.00
54448.15
7622.74
295.3125
815.02

Rs:

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D.Add for contractor's profit and overheads on (A+B+C)
Lead Charges for 1 Km for FA
9.38
cum @
Lead Charges for 1 Km for Stones/Stone Chips
26.81
cum @
Lead Charges for 1Km for Cement (including Loading
3.35
tonne @
and Unloading Charges)
Total cost for
25.00
Rate per
cum
(A+B+C+D)/25

IRR-DAW-3-5

14%
31.5 Rs./Cum
30.4 Rs./Cum
124.6 Rs./Tonne
cum

417.41
Rs: 63598.64
Rs: 2543.90

Providing and constructing chisel drafted and hammer dressed face


stone masonry with approved stones in cement mortar 1 : 3 proportion
including cost of all materials, machinery, labour, scaffolding, ramps,
cleaning, packing mortar, wedging stone chips, curing etc.,complete with
initial lead upto 1 km and all lifts.
( Cement content : 167 kg/cum of masonry, rubble stones : 0.35 cum,
stone chips : 0.15 cum/cum, FA : 0.35 cum,
Dressed stones 30 x 30 x 45 cm : 10 No, Dressed stones 30 x 30 x 60 cm : 3.40 No)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4
5
6

Cement for mortar


Coursed rubble stone 30 x 30 x 45 cm
Coursed rubble stone 30 x 30 x 60 cm
Rubble stones
Stone chips
Sand (Screened )
Total cost of Materials

B. MACHINERY:
Sl No
Description
1
2

Quantity

kg
Nos
Nos
cum
cum
cum

Unit

4175
250
85
8.75
3.75
8.75

Quantity

Concrete mixer 300 / 200 ltr ( ele )


Hour
Fuel / Energy charges
Hour
10 hp pump ( ele )
Hour
Fuel / Energy charges
Hour
Total hire charges of Machinery

C. LABOUR:
Sl No
Description
1
2
3
4
5
6
7
8
9

Unit

Crew for Concrete mixer


Crew for Pump
work inspector
Stone chiseller Cl -I
Stone chiseller Cl -II
Mason Class-I
Mason Class-II
Chavali
mazdoor
for batching cement ( cement handling )
for batching sand
for loading mortar pans
for laying & packing mortar

Unit

UNIT:
25.00 cum
Rate
Amount
in Rs.
in Rs
4.00 16700.00
20.00 5000.00
23.00 1955.00
318.00 2782.50
340.00 1275.00
606.00 5302.50
Rs: 33015.00

Rate
in Rs.
8.00
8.00
1.00
1.00

Quantity

51.70
38.00
6.70
76.10
Rs:

Amount
in Rs
413.60
304.00
6.70
76.10
800.40

Rate
in Rs.

Hour
Hour
Day
Day
Day
Day
Day
Day

8.00
1.00
1.00
14.00
7.00
2.50
4.00
16.00

189.80
72.10
370.00
385.00
345.00
385.00
345.00
345.00

Amount
in Rs
1518.40
72.10
370.00
5390.00
2415.00
962.50
1380.00
5520.00

Day
Day
Day
Day

2.00
6.00
4.00
10.00

295.00
295.00
295.00
295.00

590.00
1770.00
1180.00
2950.00

81

Dam and Allied Works - Item Unit Rates 2014-15

for loading chips


Day
for washing rubble / finishing / curing
Day
for conveying mortar / chips
Day
Total cost of Labour
labour component/unit qty
1165.30
Add contractor's profit and overhead charges
14% 163.10
labour component/unit qty (including contractor's profit)
1328.40

1.00
4.00
12.00

295.00
295.00
295.00
Rs:

295.00
1180.00
3540.00
29133.00

Rs:
Rs:
Rs:
Rs:
Rs.

33015.00
800.40
29133.00
62948.40
8812.78
275.625
827.34

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D.Add for contractor's profit and overheads on (A+B+C)
Lead Charges for 1 Km for FA
8.75
Lead Charges for 1 Km for Stones/Stone Chips
27.22

14%
cum @
cum @

31.5 Rs./Cum
30.4 Rs./Cum

Lead Charges for 1Km for Cement (including Loading


and Unloading Charges)
4.18
tonne @
Total cost for
25.00
Rate per
cum
(A+B+C+D)/25

IRR-DAW-3-6

124.6 Rs./Tonne
cum

520.205
Rs: 73384.35
Rs: 2935.40

Providing and constructing chisel drafted and hammer dressed face


stone masonry with approved stones in cement mortar 1 : 4 proportion
including cost of all materials, machinery, labour, scaffolding, ramps,
cleaning, packing mortar, wedging stone chips, curing etc.,complete with
initial lead upto 1 km and all lifts.
( Cement content : 125 kg/cum of masonry, rubble stones : 0.35 cum,
stone chips : 0.15 cum/cum, FA : 0.35 cum,
Dressed stones 30 x 30 x 45 cm : 10 No, Dressed stones 30 x 30 x 60 cm : 3.40 No)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4
5
6

Cement for mortar


Coursed rubble stone 30 x 30 x 45 cm
Coursed rubble stone 30 x 30 x 60 cm
Rubble stones
Stone chips
Sand (Screened )
Total cost of Materials

B. MACHINERY:
Sl No
Description
1
2

Unit

Quantity

kg
Nos
Nos
cum
cum
cum

Unit

3125
250
85
8.75
3.75
8.75

Quantity

Concrete mixer 300 / 200 ltr ( ele )


Hour
Fuel / Energy charges
Hour
10 hp pump ( ele )
Hour
Fuel / Energy charges
Hour
Total hire charges of Machinery

C. LABOUR:
Sl No
Description
1
2
3
4
5
6
7
8
9

Unit

Crew for Concrete mixer


Hour
Crew for Pump
Hour
work inspector
Day
Stone chiseller Cl -I
Day
Stone chiseller Cl -II
Day
Mason Class-I
Day
Mason Class-II
Day
Chavali
Day
mazdoor
for batching cement ( cement handling
Day
for batching sand
Day
for loading mortar pans
Day
for laying & packing mortar
Day
for loading chips
Day
for washing rubble / finishing / curing
Day
for conveying mortar / chips
Day
Total cost of Labour
labour component/unit qty
1165.30
Add contractor's profit and overhead charges
14% 163.10
labour component/unit qty (including contractor's profit)
1328.40
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery

UNIT:
25.00 cum
Rate
Amount
in Rs.
in Rs
4.00 12500.00
20.00 5000.00
23.00 1955.00
318.00 2782.50
340.00 1275.00
606.00 5302.50
Rs: 28815.00

Rate
in Rs.
51.70
38.00
6.70
76.10
Rs:

Amount
in Rs
413.60
304.00
6.70
76.10
800.40

8.00
1.00
1.00
14.00
7.00
2.50
4.00
16.00

189.80
72.10
370.00
385.00
345.00
385.00
345.00
345.00

Amount
in Rs
1518.40
72.10
370.00
5390.00
2415.00
962.50
1380.00
5520.00

2.00
6.00
4.00
10.00
1.00
4.00
12.00

295.00
295.00
295.00
295.00
295.00
295.00
295.00
Rs:

590.00
1770.00
1180.00
2950.00
295.00
1180.00
3540.00
29133.00

8.00
8.00
1.00
1.00

Quantity

Rate
in Rs.

Rs: 28815.00
Rs: 800.40

82

Dam and Allied Works - Item Unit Rates 2014-15

C. Cost of Labour

Rs: 29133.00
Rs: 58748.40
Rs. 8224.78
275.625
827.34

Total
D.Add for contractor's profit and overheads on (A+B+C)
Lead Charges for 1 Km for FA
8.75
cum @
Lead Charges for 1 Km for Stones/Stone Chips
27.22
cum @
Lead Charges for 1Km for Cement (including Loading
and Unloading Charges)
3.13
tonne @
Total cost for
25.00
Rate per
cum
(A+B+C+D)/25

IRR-DAW-3-7

14%
31.5 Rs./Cum
30.4 Rs./Cum
124.6 Rs./Tonne
cum

Providing cement mortar pointing to coursed rubble face stone masonry


50 mm deep in CM 1 : 2 proportion by volume including raking and cleaning
joints, pressing mortar into joints, cost of all materials, labour, scaffolding,
finishing, curing etc., complete with initial lead upto 1 km and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2

Cement
Sand (Screened )

Unit

Quantity

kg
cum

455.446
0.735

Total cost of Materials


B. MACHINERY:
Sl No
Description

Unit

Quantity

1 NIL
(Manual mixing )

UNIT:
100.00 sqm
Rate
Amount
in Rs.
in Rs
4.00 1821.78
606.00 445.41
Rs: 2267.19

Rate
in Rs.

Amount
in Rs
0.00 0.00
0.00 0.00
Rs: 0.00

Rate
in Rs.

Amount
in Rs
385.00 3850.00
295.00 2950.00
Rs: 6800.00

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
Description
1
2

Mason Class-I
mazdoor

Unit

Quantity

Day
Day

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

10.00
10.00
68.00
14% 9.50
77.50

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:
Rs.

Total
D.Add for contractor's profit and overheads on (A+B+C)
Lead Charges for 1 Km for FA
0.74
cum @
Lead Charges for 1Km for Cement (including Loading
and Unloading Charges)
0.46
tonne @
Total cost for
100.00
Rate per
sqm
(A+B+C+D)/100

IRR-DAW-3-8

389.375
Rs: 68465.52
Rs: 2738.60

14%
31.5 Rs./Cum
124.6 Rs./Tonne
sqm

2267.19
0.00
6800.00
9067.19
1269.41
23.1525

56.748572
Rs: 10416.51
Rs: 104.20

Providing cement mortar pointing to coursed rubble face stone masonry


50 mm deep in CM 1 : 3 proportion by volume including raking and cleaning
joints, pressing mortar into joints, cost of all materials, labour, scaffolding,
finishing, curing etc., complete with initial lead upto 1 km and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2

Cement
Sand (Screened )

Unit

Quantity

kg
cum

321.80
0.74

Total cost of Materials


B. MACHINERY:
Sl No
Description
1

Unit

Quantity

NIL
Manual mixing )

UNIT:
100.00 sqm
Rate
Amount
in Rs.
in Rs
4.00 1287.20
606.00 445.41
Rs: 1732.61

Rate
in Rs.

Amount
in Rs
0.00 0.00
0.00 0.00
Rs: 0.00

Rate
in Rs.

Amount
in Rs
385.00 3850.00

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
Description
1

Mason Class-I

Unit
Day

Quantity
10.00

83

Dam and Allied Works - Item Unit Rates 2014-15

mazdoor

Day

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

10.00

295.00 2950.00
Rs: 6800.00

68.00
14% 9.50
77.50

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:
Rs.

Total
D.Add for contractor's profit and overheads on (A+B+C)
Lead Charges for 1 Km for FA
0.74
cum @
Lead Charges for 1Km for Cement (including Loading
and Unloading Charges)
0.32
tonne @
Total cost for
100.00
Rate per
sqm
(A+B+C+D)/100
IRR_DAW-4

CONTRACTION JOINT WORKS:

IRR-DAW-4-1

Providing 25 mm thick guniting to rock or masonry surface in cement


mortar 1 : 3 proportion by weight including cost of all materials, machinery,
labour, raking-out and cleaning joints, scaffolding wherever required and all
other ancillary operations etc., complete with initial lead upto 1 km and
all lifts.

DATA:

14%
31.5 Rs./Cum
124.6 Rs./Tonne
sqm

1732.61
0.00
6800.00
8532.61
1194.57
23.1525

40.09628
Rs: 9790.43
Rs: 97.90

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4
5
6

Cement
Sand (Screened )
Use rate of grout hose 25 m
Use rate of water hose 25 m
Use rate of guniting nozzle
Sundries
Total cost of Materials

B. MACHINERY:
Sl No
Description
1
2
3
4

Unit

Quantity

kg
cum
Hour
Hour
Hour
LS

609.90
1.09
8.00
8.00
8.00
2.00

Unit

Quantity

Guniting equipment
Hour
Fuel / Energy charges
Hour
Air compressor 8.5 cmm ( ele )
Hour
Fuel / Energy charges
Hour
Pump 10 hp ( ele )
Hour
Fuel / Energy charges
Hour
Sundries
LS
Total hire charges of Machinery

C. LABOUR:
Sl No
Description

UNIT :
36.00 sqm
Rate
Amount
in Rs.
in Rs
4.00 2439.60
606.00 660.54
5.47 43.75
6.84 54.75
3.50 28.00
41.00 82.00
Rs: 3308.64

Rate
in Rs.
110.10
0.00
170.80
428.00
6.70
76.10
41.00
Rs:

Amount
in Rs
880.80
0.00
1366.40
3424.00
6.70
76.10
82.00
5836.00

8.00
8.00
1.00
1.00

189.80
142.40
72.10
345.00

Amount
in Rs
1518.40
1139.20
72.10
345.00

2.00
2.00
2.00

295.00
295.00
295.00
Rs:

590.00
590.00
590.00
4844.70

8.00
8.00
8.00
8.00
1.00
1.00
2.00

Unit

Quantity

1
2
3
4
5

Crew for Guniting equipment


Hour
Crew for Air compressor
Hour
Crew for pump
Hour
Day
Mason Cl II
mazdoor
for cement handling
Day
for sand
Day
mazdoor for other works
Day
Total cost of Labour
labour component/unit qty
134.60
Add contractor's profit and overhead charges
14% 18.80
labour component/unit qty (including contractor's profit)
153.40

Rate
in Rs.

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:

Total
Add for scaffolding

3%

D.Add for contractor's profit and overheads on (A+B+C+other


Lead Charges for 1 Km for FA
1.09
cum @
Lead Charges for 1Km for Cement (including Loading
and Unloading Charges)
0.61
tonne @
Total cost for
36.00
Rate per
sqm
(A+B+C+D)/36

Total
14%
31.5 Rs./Cum
124.6 Rs./Tonne
sqm

3308.64
5836.00
4844.70
13989.34
349.73
Rs: 14339.07
Rs. 2007.47
34.335
75.99354
Rs: 16456.87
Rs: 457.10

84

Dam and Allied Works - Item Unit Rates 2014-15

IRR-DAW-4-2

DATA:

Providing and constructing contraction joints by fixing 16 SWG 60 cm


wide annealed copper sheets in two lines with 8 mm dia steel dowel
rods on either side at one metre interval, forming 125 x 125 mm size groove
in between copper strips for filling asphalt including fixing 15 mm dia two
legged G.I pipe with U - bend at bottom for circulation of steam at intervals
and forming 150 mm dia formed drain behind water seals including cost of
all materials, machinery, labour, filling asphalt, circulation of steam through
pipes etc., complete with all leads and lifts. consider 12 m height of
contraction joint for analysis.
RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4
5
6

Copper sheet 16 SWG


Reinforcement steel 8 mm dia
GI pipe 15 mm dia
Asphalt
Elbows / Nipple / Plugs etc.,
Soldering materials
Total cost of Materials

Unit

Quantity

kg
kg
Rm
kg
LS
LS

B. MACHINERY:
Sl No
Description

215.00
30.00
24.00
192.00
5.00
40.00

Unit

Quantity

1 Steam circulation arrangement


LS
Fuel charges ( gas for heating )
LS
Total hire charges of Machinery
C. LABOUR:
Sl No
Description
1
2
3
4
5
6

Welder
Tinsmith
Bar bender
Pipe fitter
Mason Class-I
mazdoor

Rate
in Rs.

Amount
in Rs
17.00 136.00
17.00 170.00
Rs: 306.00

Rate
in Rs.

Amount
in Rs
385.00
385.00
225.00
220.00
192.50
295.00
1702.50

8.00
10.00

Unit

Quantity

Day
Day
Day
Day
Day
Day

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

UNIT:
12.00 Rm
Rate
Amount
in Rs.
in Rs
695.00 149425.00
46.50 1395.00
110.00 2640.00
43.00 8256.00
17.00 85.00
17.00 680.00
Rs:
162481.00

1.00
1.00
0.50
0.50
0.50
1.00

385.00
385.00
450.00
440.00
385.00
295.00
Rs:

141.90
14% 19.90
161.80

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
14%

D.Add for contractor's profit and overheads on (A+B+C)


Total cost for
12.00 Rm
Rate per
Rm
(A+B+C+D)/12

IRR-DAW-4-3

Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:

162481.00
306.00
1702.50
164489.50
23028.53
187518.03
15626.50

Providing and constructing contraction joints by fixing 310 mm wide


central bulb type approved quality PVC water stop in two lines with 8 mm
diameter steel dowel rods on either side at 1m interval, forming 125 x 125
mm size groove in between two water stops, providing & fixing 15 mm dia
two legged G.I pipe with U-bend at bottom for circulation steam at interval,
forming 150 mm diameter formed drain behind water seals including filling
groove with asphalt, circulation of steam at intervals, cost of all materials,
machinery, labour etc., complete with all leads and lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4
5
6

PVC water stops 310 mm wide


Reinforcement steel 8 mm dia
GI pipe 15 mm dia
Asphalt
Elbows / Nipple / Plugs etc.,
Vulcanizing materials
Total cost of Materials

B. MACHINERY:
Sl No
Description

Unit

Quantity

Rm
kg
Rm
kg
LS
LS

Unit

24.50
30.00
24.00
192.00
5.00
25.00

Quantity

UNIT:
12.00 Rm.
Rate
Amount
in Rs.
in Rs
485.00 11882.50
46.50 1395.00
110.00 2640.00
43.00 8256.00
17.00 85.00
17.00 425.00
Rs: 24683.50

Rate
in Rs.

Amount
in Rs

85

Dam and Allied Works - Item Unit Rates 2014-15

Steam circulation arrangement


LS
Fuel charges ( gas for heating )
LS
Total hire charges of Machinery

C. LABOUR:
Sl No
Description
1
2
3
4
5

Welder
Bar bender
Pipe fitter
Mason Class-I
mazdoor

8.00
10.00

Unit

Quantity

Day
Day
Day
Day
Day

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

17.00 136.00
17.00 170.00
Rs: 306.00

Rate
in Rs.
0.50
0.50
0.50
0.50
1.00

Total
14%

D.Add for contractor's profit and overheads on (A+B+C)


Total cost for
12.00 Rm.
Rate per
Rm.
(A+B+C+D)/12

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3

Copper sheet 16 SWG


Reinforcement steel 8 mm dia
Soldering materials
Total cost of Materials

Unit

Sundries such as soldering gun etc.,


Fuel charges ( gas )
Total hire charges of Machinery

Welder
Tinsmith
Bar bender
Mason Class-I
mazdoor

77.00
15.00
10.00

Unit

Quantity

LS
LS

C. LABOUR:
Sl No
Description
1
2
3
4
5

Quantity

kg
kg
LS

B. MACHINERY:
Sl No
Description

UNIT:
8.7 Rm
Rate
Amount
in Rs.
in Rs
695.00 53515.00
46.50 697.50
17.00 170.00
Rs: 54382.50

Rate
in Rs.

Amount
in Rs
41.00 123.00
17.00 85.00
Rs: 208.00

Rate
in Rs.
385.00
385.00
450.00
385.00
295.00
Rs:

Amount
in Rs
192.50
192.50
225.00
192.50
147.50
950.00

Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:

54382.50
208.00
950.00
55540.50
7775.67
63316.17
7277.70

3.00
5.00

Unit

Quantity

Day
Day
Day
Day
Day

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

0.5
0.5
0.5
0.5
0.5
109.20
14% 15.30
124.50

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D.Add for contractor's profit and overheads on (A+B+C)
Total cost for
8.70 Rm
Rate per
Rm
(A+B+C+D)/8.70

DATA:

24683.50
306.00
1125.00
26114.50
3656.03
29770.53
2480.90

Providing and constructing contraction joints by fixing 16 SWG 60 cm


wide annealed copper sheets in single line with 8 mm dia steel dowel
rods on either side at 1 metre interval including cost of all materials,
machinery, labour etc., complete with all leads and lifts.

DATA:

IRR-DAW-4-5

Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:

93.80
14% 13.10
106.90

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

IRR-DAW-4-4

385.00
450.00
440.00
385.00
295.00
Rs:

Amount
in Rs
192.50
225.00
220.00
192.50
295.00
1125.00

Total
14%

Providing and constructing contraction joints by fixing 23 cm wide central


bulb type PVC water stop in single line supported by 10 mm dia steel
dowel rods on either side at 1 metre interval including cost of all materials,
machinery, labour, valcunising joints etc., complete with all leads and
lifts.
RATE ANALYSIS
UNIT:

86

Dam and Allied Works - Item Unit Rates 2014-15

A. MATERIALS:
Sl No
Particulars
1
2
3

PVC water seal 23 cm wide


Reinforcement steel 10 mm dia
Vulcanising materials
Total cost of Materials

Unit
Rm
kg
LS

B. MACHINERY:
Sl No
Description
1

9.00
10.00
2.00

Unit

Quantity

Sundries such as heater etc.,


LS
Fuel charges for heating
LS
Total hire charges of Machinery

C. LABOUR:
Sl No
Description
1
2
3
4

Quantity

Welder
Bar bender
Mason Class-I
mazdoor

Rate
in Rs.

Amount
in Rs
41.00 20.50
17.00 8.50
29.00

Rate
in Rs.

Amount
in Rs
192.50
225.00
192.50
147.50
757.50

0.50
0.50

Unit

Quantity

Day
Day
Day
Day

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

8.70 Rm
Rate
Amount
in Rs.
in Rs
44.00 396.00
46.50 465.00
17.00 34.00
Rs: 895.00

0.50
0.50
0.50
0.50

385.00
450.00
385.00
295.00
Rs:

87.10
14% 12.20
99.30

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:

Total
14%

D.Add for contractor's profit and overheads on (A+B+C)


Total cost for
8.70 Rm
Rate per
Rm
(A+B+C+D)/8.70
IRR_DAW-5

EARTH / ROCKFILL EMBANKMENT WORKS :

IRR-DAW-5-1

Providing hearting embankment using selected impervious soil from


approved borrow areas in layers of 25 to 30 cm before compaction
including cost of all materials, machinery, labour, all operations such as
excavation, sorting out, transportation, spreading soil in layer of specified
thickness, breaking clods, sectioning, watering, compacting to density
control of not less than 95 percent or as stipulated using Sheep foot roller /
Vibratory roller/ 8 to 10 tonne power roller etc., complete with initial lead upto 1 km and all lifts.

DATA:

895.00
29.00
757.50
1681.50
235.41
1916.91
220.30

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars

Unit

Quantity

1 NIL

0.00
0.00
Total cost of Materials

B. MACHINERY:
Sl No
Description
1
2
3
4
5
6
7

Quantity

Angle dozer 90 hp
Hour
Fuel / Energy charges
Hour
Shovel 0.85 cum capacity
Hour
Fuel / Energy charges
Hour
Tippers 5.00 cum capacity 5 Nos.
Hour
Fuel / Energy charges
Hour
Pump 5 hp ( ele )
Hour
Fuel / Energy charges
Hour
Water tanker 8000 ltr
Hour
Fuel / Energy charges
Hour
Vibratory Roller 8 tonne
Hour
Fuel / Energy charges
Hour
Sundries
LS
Total hire charges of Machinery

C. LABOUR:
Sl No
Description
1
2
3
4
5

Unit

Crew for Dozer


Crew for Shovel
Crew for Tipper
Crew for Pump
Crew for Water tanker

Unit
Hour
Hour
Hour
Hour
Hour

5.50
5.50
8.00
8.00
40.00
40.00
4.00
4.00
8.00
8.00
6.50
6.50
2.00

Quantity
5.50
8.00
40.00
4.00
8.00

UNIT
825.00 cum
Rate
Amount
in Rs.
in Rs
0.00 0.00
0.00 0.00
Rs: 0.00

Rate
in Rs.
1715.50
656.00
1706.60
937.80
446.70
322.20
3.00
38.00
402.50
322.20
1342.20
1108.30
41.00
Rs:

Amount
in Rs
9435.25
3608.00
13652.80
7502.40
17868.00
12888.00
12.00
152.00
3220.00
2577.60
8724.30
7203.95
82.00
86926.30

Rate
in Rs.

Amount
in Rs
1122.55
1632.80
6124.00
288.40
1224.80

204.10
204.10
153.10
72.10
153.10

87

Dam and Allied Works - Item Unit Rates 2014-15

6
7
8

Crew for Roller


work inspector
mazdoor

Hour
Day
Day

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

6.50
2.00
4.00

227.80
370.00
295.00
Rs:

16.70
14% 2.30
19.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

0.00
86926.30
13793.25
100719.55
14100.74
114820.29
139.20

Providing cut-off trench filling using selected impervious soil from


approved borrow areas in layers of 25 to 30 cm before compaction
including cost of all materials, machinery, labour, all operations such as
excavation, sorting out, transportation, spreading soil to specified thickness,
breaking clods, sectioning, watering, compacting to density control of not
less than 95 percent using Sheep foot roller / Vibratory roller/ 8 to 10 tonne power roller as stipulated etc.,
complete with initial lead upto 1 km and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars

Unit

Quantity

1 NIL

0.00
0.00
Total cost of Materials

B. MACHINERY:
Sl No Description
1
2
3
4
5
6
7

Unit

Quantity

Angle dozer 90 hp
Hour
Fuel / Energy charges
Hour
Shovel 0.85 cum capacity
Hour
Fuel / Energy charges
Hour
Tippers 5.00 cum capacity 6 Nos.
Hour
Fuel / Energy charges
Hour
Pump 5 hp ( ele )
Hour
Fuel / Energy charges
Hour
Water tanker 8000 ltr
Hour
Fuel / Energy charges
Hour
Vibratory Roller 8 tonne
Hour
Fuel / Energy charges
Hour
Sundries
LS
Total hire charges of Machinery

C. LABOUR:
Sl No Description

Unit

5.50
5.50
8.00
8.00
48.00
48.00
4.00
4.00
8.00
8.00
6.50
6.50
2.00

Quantity

1
2
3
4
5
6
7
8

Crew for Dozer


Hour
Crew for Shovel
Hour
Crew for Tipper
Hour
Crew for Pump
Hour
Crew for Water tanker
Hour
Crew for Roller
Hour
work inspector
Day
mazdoor
Day
Total cost of Labour
labour component/unit qty
18.20
Add contractor's profit and overhead charges
14% 2.50
labour component/unit qty (including contractor's profit)
20.70

5.50
8.00
48.00
4.00
8.00
6.50
2.00
4.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D.Add for contractor's profit and overheads on (A+B+C)
Total cost for
825.00 cum
Rate per
cum
(A+B+C+D)/825

IRR-DAW-5-3

Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:

Total
14%

D.Add for contractor's profit and overheads on (A+B+C)


Total cost for
825.00 cum
Rate per
cum
(A+B+C+D)/825

IRR-DAW-5-2

1480.70
740.00
1180.00
13793.25

Total
14%

UNIT :
825.00 cum
Rate
Amount
in Rs.
in Rs
0.00 0.00
0.00 0.00
Rs: 0.00

Rate
in Rs.
1715.50
656.00
1706.60
937.80
446.70
322.20
3.00
38.00
402.50
322.20
1342.20
1108.30
41.00
Rs:

Amount
in Rs
9435.25
3608.00
13652.80
7502.40
21441.60
15465.60
12.00
152.00
3220.00
2577.60
8724.30
7203.95
82.00
93077.50

Rate
in Rs.
204.10
204.10
153.10
72.10
153.10
227.80
370.00
295.00
Rs:

Amount
in Rs
1122.55
1632.80
7348.80
288.40
1224.80
1480.70
740.00
1180.00
15018.05

Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:

0.00
93077.50
15018.05
108095.55
15133.38
123228.93
149.40

Providing casing embankment using semi-pervious soil from approved


borrow areas in layers of 25 to 30 cm before compaction including cost of

88

Dam and Allied Works - Item Unit Rates 2014-15

all materials, machinery, labour, all other operations such as excavation,


sorting out, transportation, spreading soil in layers of specified thickness,
breaking clods, sectioning, watering, compacting to density control of not
less than 95 percent using Sheep foot roller / Vibratory roller/ 8 to 10 tonne power roller as stipulated etc.,
complete with initial lead upto 1 km and all lifts.
DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars

Unit

UNIT :
630 cum
Rate
Amount
in Rs.
in Rs
0.00 0.00
0.00 0.00
Rs: 0.00

Quantity

1 NIL

0.00
0.00
Total cost of Materials

B. MACHINERY:
Sl No
Description
1
2
3
4
5
6
7

Quantity

Angle dozer 90 hp
Hour
Fuel / Energy charges
Hour
Shovel 0.85 cum
Hour
Fuel / Energy charges
Hour
Tipper 5 cum
Hour
Fuel / Energy charges
Hour
Pump 5 hp ( ele )
Hour
Fuel / Energy charges
Hour
Water tanker 8000 ltr
Hour
Fuel / Energy charges
Hour
Vibratory Roller 8 tonne
Hour
Fuel / Energy charges
Hour
Sundries
LS
Total hire charges of Machinery

C. LABOUR:
Sl No
Description
1
2
3
4
5
6
7
8

Unit

Unit

4.00
4.00
8.00
8.00
32.00
32.00
3.00
3.00
5.00
5.00
5.00
5.00
5.00

Quantity

Crew for Dozer


Crew for Shovel
Crew for Tipper
Crew for Pump
Crew for Water tanker
Crew for Roller
work inspector
mazdoor

Hour
Hour
Hour
Hour
Hour
Hour
Day
Day
Total cost of Labour
labour component/unit qty
18.10
Add contractor's profit and overhead charges
14% 2.50
labour component/unit qty (including contractor's profit)
20.60

4.00
8.00
32.00
3.00
5.00
5.00
2.00
4.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
14%

D.Add for contractor's profit and overheads on (A+B+C)


Total cost for
630.00 cum
Rate per
cum
(A+B+C+D)/630

IRR-DAW-5-4

Rate
in Rs.
1715.50
656.00
1706.60
937.80
446.70
322.20
3.00
38.00
402.50
322.20
1342.20
1108.30
41.00
Rs:

Amount
in Rs
6862.00
2624.00
13652.80
7502.40
14294.40
10310.40
9.00
114.00
2012.50
1611.00
6711.00
5541.50
205.00
71450.00

Rate
in Rs.
204.10
204.10
153.10
72.10
153.10
227.80
370.00
295.00
Rs:

Amount
in Rs
816.40
1632.80
4899.20
216.30
765.50
1139.00
740.00
1180.00
11389.20

Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:

0.00
71450.00
11389.20
82839.20
11597.49
94436.69
149.90

Providing casing embankment using semi-pervious soil available


from excavation in layers of 25 to 30 cm before compaction including cost
of all materials, machinery, labour, all other operations such as re-excavation,
sorting out, transportation, spreading in layers of specified thickness,
breaking clods, sectioning, watering, compacting to specified density
control of not less than 95 percent using Sheep foot roller / Vibratory roller/ 8 to 10 tonne power roller as
stipulated etc.,complete with initial lead upto 1 km and all lifts.

DATA:

RATE ANALYSIS
UNIT :
A. MATERIALS:
Sl No
Particulars

Unit

Quantity

1 NIL

0.00
0.00
Total cost of Materials

B. MACHINERY:
Sl No
Description
1

Angle dozer 90 hp
Fuel / Energy charges

Unit
Hour
Hour

Quantity
4.60
4.60

970.00 cum
Rate
Amount
in Rs.
in Rs
0.00 0.00
0.00 0.00
Rs: 0.00

Rate
Amount
in Rs.
in Rs
1715.50 7891.30
656.00 3017.60

89

Dam and Allied Works - Item Unit Rates 2014-15

2
3
4
5
6
7

Shovel 0.85 cum


Fuel / Energy charges
Tipper 5 cum
Fuel / Energy charges
Pump 5 hp ( ele )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Vibratory Roller 8 tonne
Fuel / Energy charges
Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No
Description

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Unit

8.00
8.00
48.00
48.00
4.00
4.00
8.00
8.00
7.00
7.00
5.00

1706.60
937.80
446.70
322.20
3.00
38.00
402.50
322.20
1342.20
1108.30
41.00
Rs:

Quantity

1
2
3
4
5
6
7
8

Crew for Dozer


Hour
Crew for Shovel
Hour
Crew for Tipper
Hour
Crew for Pump
Hour
Crew for Water tanker
Hour
Crew for Roller
Hour
work inspector
Day
mazdoor
Day
Total cost of Labour
labour component/unit qty
15.40
Add contractor's profit and overhead charges
14% 2.20
labour component/unit qty (including contractor's profit)
17.60

Rate
in Rs.
4.60
8.00
48.00
4.00
8.00
7.00
2.00
4.00

204.10
204.10
153.10
72.10
153.10
227.80
370.00
295.00
Rs:

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
14%

D.Add for contractor's profit and overheads on (A+B+C)


Total cost for
970.00 cum
Rate per
cum
(A+B+C+D)/970
IRR-DAW-5-4-A
(New Item1 - 2011-12)

Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:

13652.80
7502.40
21441.60
15465.60
12.00
152.00
3220.00
2577.60
9395.40
7758.10
205.00
92291.40

Amount
in Rs
938.86
1632.80
7348.80
288.40
1224.80
1594.60
740.00
1180.00
14948.26

0.00
92291.40
14948.26
107239.66
15013.55
122253.21
126.00

Providing casing embankment using semi-pervious soil available


from excavation in layers of 25 to 30 cm before compaction including cost
of all materials, machinery, labour, all other operations such as re-excavation,
sorting out, transportation, spreading in layers of specified thickness,
breaking clods, sectioning, watering, compacting to specified density
control of not less than 90 percent using 2 Tonne Roller as
stipulated etc.,complete with initial lead upto 1 km and all lifts.
(For Maintenance Works)

DATA:

RATE ANALYSIS
UNIT :
A. MATERIALS:
Sl No
Particulars

Unit

Quantity

1 NIL

0.00
0.00
Total cost of Materials

B. MACHINERY:
Sl No
Description
1
2
3
4
5
6
7

Angle dozer 90 hp
Fuel / Energy charges
Shovel 0.85 cum
Fuel / Energy charges
Tipper 5 cum
Fuel / Energy charges
Pump 5 hp ( ele )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Vibratory Roller 8 tonne
Fuel / Energy charges
Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No
Description
1
2
3
4

Crew for Dozer


Crew for Shovel
Crew for Tipper
Crew for Pump

Unit

Quantity

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Unit
Hour
Hour
Hour
Hour

4.60
4.60
8.00
8.00
48.00
48.00
4.00
4.00
8.00
8.00
7.00
7.00
5.00

Quantity
4.60
8.00
48.00
4.00

970.00 cum
Rate
Amount
in Rs.
in Rs
0.00 0.00
0.00 0.00
Rs: 0.00

Rate
in Rs.
1715.50
656.00
1706.60
937.80
446.70
322.20
3.00
38.00
402.50
322.20
1342.20
1108.30
41.00
Rs:

Amount
in Rs
7891.30
3017.60
13652.80
7502.40
21441.60
15465.60
12.00
152.00
3220.00
2577.60
9395.40
7758.10
205.00
92291.40

Rate
in Rs.

Amount
in Rs
938.86
1632.80
7348.80
288.40

204.10
204.10
153.10
72.10

90

Dam and Allied Works - Item Unit Rates 2014-15

5
6
7
8

Crew for Water tanker


Hour
Crew for Roller
Hour
work inspector
Day
mazdoor
Day
Total cost of Labour
labour component/unit qty
15.40
Add contractor's profit and overhead charges
14% 2.20
labour component/unit qty (including contractor's profit)
17.60

8.00
7.00
2.00
4.00

153.10
227.80
370.00
295.00
Rs:

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:

Total
14%

D.Add for contractor's profit and overheads on (A+B+C)


Total cost for
970.00 cum
Rate per
cum
(A+B+C+D)/970
Deduct Rate for Proctar's density Control of 95% using 8T roller as per IRR-PMW-3-23
Add Rate for Proctor's Density control of 90% using 2T Roller as per IRR-PMW-3-24
Rate per
cum
IRR-DAW-5-5

Rs.

1224.80
1594.60
740.00
1180.00
14948.26

0.00
92291.40
14948.26
107239.66
15013.55
122253.21
126.00
46.10
6.10
86.00

Providing homogeneous embankment using soil from approved borrow


area in layers of 25 to 30 cm before compaction including cost of all
materials, machinery, labour, all operations such as excavation, sorting out,
transportation, spreading soil in layer of specified thickness, breaking clods,
sectioning, watering, compacting to density control of not less than
95 percent or as stipulated using Sheep foot roller / Vibratory roller/ 8 to 10 tonne power roller etc., complete
with initial lead upto 1 km and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1

Unit

Quantity

NIL

0.00
0.00
Total cost of Materials

B. MACHINERY:
Sl No
Description
1
2
3
4
5
6
7

Unit

Quantity

Angle dozer 90 hp
Hour
Fuel / Energy charges
Hour
Shovel 0.85 cum capacity
Hour
Fuel / Energy charges
Hour
Tippers 5.00 cum capacity 5 Nos.
Hour
Fuel / Energy charges
Hour
Pump 5 hp ( ele )
Hour
Fuel / Energy charges
Hour
Water tanker 8000 ltr
Hour
Fuel / Energy charges
Hour
Vibratory Roller 8 tonne
Hour
Fuel / Energy charges
Hour
Sundries
LS
Total hire charges of Machinery

C. LABOUR:
Sl No
Description

Unit

1
2
3
4
5
6
7
8

Crew for Dozer


Hour
Crew for Shovel
Hour
Crew for Tipper
Hour
Crew for Pump
Hour
Crew for Water tanker
Hour
Crew for Roller
Hour
work inspector
Day
mazdoor
Day
Total cost of Labour
labour component/unit qty
17.00
Add contractor's profit and overhead charges
14% 2.40
labour component/unit qty (including contractor's profit)
19.40

5.40
5.40
8.00
8.00
40.00
40.00
4.00
4.00
8.00
8.00
6.40
6.40
2.00

Quantity
5.40
8.00
40.00
4.00
8.00
6.40
2.00
4.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D.Add for contractor's profit and overheads on (A+B+C)
Total cost for
807.00 cum
Rate per
cum
(A+B+C+D)/807

Total
14%

UNIT :
807.00 cum
Rate
Amount
in Rs.
in Rs
0.00 0.00
0.00 0.00
Rs: 0.00

Rate
in Rs.
1715.50
656.00
1706.60
937.80
446.70
322.20
3.00
38.00
402.50
322.20
1342.20
1108.30
41.00
Rs:

Amount
in Rs
9263.70
3542.40
13652.80
7502.40
17868.00
12888.00
12.00
152.00
3220.00
2577.60
8590.08
7093.12
82.00
86444.10

Rate
in Rs.

Amount
in Rs
1102.14
1632.80
6124.00
288.40
1224.80
1457.92
740.00
1180.00
13750.06

204.10
204.10
153.10
72.10
153.10
227.80
370.00
295.00
Rs:

Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:

0.00
86444.10
13750.06
100194.16
14027.18
114221.34
141.50

91

Dam and Allied Works - Item Unit Rates 2014-15

IRR-DAW-5-6

Providing embankment adjacent to masonry / concrete structures and filling trial pits
using impervious soil from approved borrow areas in layers of 10 to 15 cm and compacting
each layer to density control of not less than 95 percent using pneumatic tampers or by
vibratory earth rammers including cost of all materials, machinery, labour, picking previous
layer, spreading soil in layer, breaking clods, watering etc., complete with initial lead upto
1 km and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No Particulars

UNIT :
Unit

1 Use rate of air hose

Quantity

Hour

16.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No Description
1
2
3
4
5
6
7
8

Unit

Angle dozer 90 hp
Fuel / Energy charges
Shovel 0.85 cum
Fuel / Energy charges
Tipper 5 cum
Fuel / Energy charges
Air compressor 8.5 cmm ( ele )
Fuel / Energy charges
Pump 5 hp ( ele )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Pneumatic tampers 2 Nos.
Fuel / Energy charges
Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No Description

Quantity

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

0.15
0.15
0.80
0.80
3.00
3.00
8.00
8.00
0.40
0.40
0.80
0.80
16.00
16.00
1.00

Unit

Quantity

80 cum
Rate
Amount
in Rs.
in Rs
10.94
175.00
0.00
0.00
Rs:
175.00

Rate
in Rs.
1715.50
656.00
1706.60
937.80
446.70
322.20
170.80
428.00
3.00
38.00
402.50
322.20
20.70
0.00
41.00
Rs:

Amount
in Rs
257.33
98.40
1365.28
750.24
1340.10
966.60
1366.40
3424.00
1.20
15.20
322.00
257.76
331.20
0.00
41.00
10536.71

Rate
in Rs.

Amount
in Rs
30.62
163.28
459.30
1139.20
28.84
122.48
3644.80
370.00
1475.00
7433.52

0.15
0.80
3.00
8.00
0.40
0.80
16.00
1.00
5.00

1
2
3
4
5
6
7
8
9

Crew for Dozer


Hour
Crew for Shovel
Hour
Crew for Tipper
Hour
Crew for Air compressor
Hour
Crew for Pump
Hour
Crew for Water tanker
Hour
Crew for Pneumatic tamper
Hour
work inspector
Day
mazdoor
Day
Total cost of Labour
labour component/unit qty
92.90
Add contractor's profit and overhead charges
14% 13.00
labour component/unit qty (including contractor's profit)
105.90

204.10
204.10
153.10
142.40
72.10
153.10
227.80
370.00
295.00
Rs:

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
14%

D.Add for contractor's profit and overheads on (A+B+C)


Total cost for
80.00 cum
Rate per
cum
(A+B+C+D)/80

IRR-DAW-5-7

Rs:
175.00
Rs:
10536.71
Rs:
7433.52
Rs:
18145.22
Rs. 2540.33
Rs: 20685.55
Rs: 258.60

Providing and constructing rockfill embankment with 300 mm down graded stones and
quarry spalls from approved source including cost of all materials, machinery, labour, spreading
stones and spalls in layers, hand packing, wedging, finishing the surface to required slopes
etc., complete with initial lead upto 1 km and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No Particulars
1
2
3
4
5
6

Use rate of drill rod 2.5 m long


Reconditioning charges @
Use rate of air hose 6 Nos.
Explosive small dia
Electric detonators
Detonator ordinary
Fuse coil

UNIT :
Unit

400
Quantity

Rate
in Rs.

Rm

387.00

41.69

10%
Hour
kg
Nos
Nos
Rm

60.00
118.00
159.00
8.00
200.00

10.94
70.00
13.00
9.00
11.00

cum
Amount
in Rs
16135.32
1613.53
656.25
8260.00
2067.00
72.00
2200.00

92

Dam and Allied Works - Item Unit Rates 2014-15

Sundries ( waste tyres etc )


Total cost of Materials

B. MACHINERY:
Sl No Description
1
2
3
4
5

LS

10.00

Unit

Quantity

Air compressor 8.5cmm( diesel )3 Nos


Hour
Fuel / Energy charges
Hour
Jack hammer 6 Nos
Hour
Fuel / Energy charges
Hour
Angle dozer 90 hp
Hour
Fuel / Energy charges
Hour
Shovel 0.85 cum
Hour
Fuel / Energy charges
Hour
Tipper 5 cum
Hour
Fuel / Energy charges
Hour
Total hire charges of Machinery

C. LABOUR:
Sl No Description

Quantity

1
2
3
4
5
6
7
8
9
10

Crew for Air compressor


Hour
Crew for Jack hammer
Hour
Crew for Shovel
Hour
Crew for Tipper
Hour
Crew for Dozer
Hour
Blaster
Day
Helper blaster
Day
work inspector
Day
Mason Class-II
Day
mazdoor
Day
Total cost of Labour
labour component/unit qty
84.60
Add contractor's profit and overhead charges
14% 11.80
labour component/unit qty (including contractor's profit)
96.40

410.00
31414.10

275.60
959.10
19.80
0.00
1715.50
656.00
1706.60
937.80
446.70
322.20
Rs:

Amount
in Rs
8268.00
28773.00
1188.00
0.00
6862.00
2624.00
13652.80
7502.40
10720.80
7732.80
87323.80

Rate
in Rs.
30.00
30.00
60.00
60.00
4.00
4.00
8.00
8.00
24.00
24.00

Unit

41.00
Rs:

Rate
in Rs.
30.00
60.00
8.00
24.00
4.00
1.00
1.00
2.00
2.00
10.00

182.20
284.70
204.10
153.10
204.10
440.00
345.00
370.00
345.00
295.00
Rs:

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

IRR-DAW-5-8

Rs:
31414.10
Rs:
87323.80
Rs:
33836.60
Rs: 152574.50
Rs. 21360.43
Rs: 173934.93
Rs: 434.80

Total
14%

D.Add for contractor's profit and overheads on (A+B+C)


Total cost for
400.00 cum
Rate per
cum
(A+B+C+D)/400

Amount
in Rs
5466.00
17082.00
1632.80
3674.40
816.40
440.00
345.00
740.00
690.00
2950.00
33836.60

Providing and constructing dry rubble rock-toe using rubble and stone chips from
approved source including cost of all materials, machinery, labour, hand packing rubble
and stone chips, finishing top and sides to required slopes etc., complete with initial lead upto
1 km and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No Particulars
1
2
3
4
5
6
7

Use rate of drill rod 1.5 m long


Reconditionong charges @
Use rate of air hose
Explosive small dia
Electric detonator
Detonator ordinary
Fuse coil
Sundries
Total cost of Materials

B. MACHINERY:
Sl No Description
1
2
3
4

UNIT :
Unit

Quantity

Rm

97.00

10%
Hour
kg
Nos
Nos
Rm
LS

15.00
30.00
40.00
2.00
50.00
2.00

Unit

Air compressor 8.5 cmm ( diesel )


Hour
Fuel / Energy charges
Hour
Jack hammer
Hour
Fuel / Energy charges
Hour
Shovel 0.85 cum
Hour
Fuel / Energy charges
Hour
Tipper 5 cum
Hour
Fuel / Energy charges
Hour
Total hire charges of Machinery

Quantity

100 cum
Rate
Amount
in Rs.
in Rs
41.69
4044.25
404.43
10.94
164.06
70.00
2100.00
13.00
520.00
9.00
18.00
11.00
550.00
41.00
82.00
Rs:
7882.74

Rate
in Rs.
7.50
7.50
15.00
15.00
2.00
2.00
6.00
6.00

275.60
959.10
19.80
0.00
1706.60
937.80
446.70
322.20
Rs:

Amount
in Rs
2067.00
7193.25
297.00
0.00
3413.20
1875.60
2680.20
1933.20
19459.45

C. LABOUR:

93

Dam and Allied Works - Item Unit Rates 2014-15

Sl No Description

Unit

Quantity

1
2
3
4
5
6
7
8
9

Crew for Air compressor


Hour
Crew for Jack hammer
Hour
Crew for Shovel
Hour
Crew for Tipper
Hour
Blaster
Day
Helper blaster
Day
work inspector
Day
Mason Class-II
Day
mazdoor
Day
Total cost of Labour
labour component/unit qty
159.20
Add contractor's profit and overhead charges
14.00% 22.30
labour component/unit qty (including contractor's profit)
181.50

Rate
in Rs.
7.50
15.00
2.00
6.00
0.50
1.00
1.00
7.00
19.00

182.20
284.70
204.10
153.10
440.00
345.00
370.00
345.00
295.00
Rs:

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

IRR-DAW-5-9

Note:
DATA:

Rs:
7882.74
Rs:
19459.45
Rs:
15918.80
Rs:
43260.99
Rs. 6056.54
Rs: 49317.53
Rs: 493.20

Total
14.00%

D.Add for contractor's profit and overheads on (A+B+C)


Total cost for
100.00 cum
Rate per
cum
(A+B+C+D)/100

Amount
in Rs
1366.50
4270.50
408.20
918.60
220.00
345.00
370.00
2415.00
5605.00
15918.80

Providing and constructing dry rubble rock-toe with rubble and stone chips from dump
yard (Spoil Bank) including cost of all materials, machinery, labour, hand packing rubble and stone chips,
finishing top and sides to required slopes etc., complete with initial lead upto 1 km and all
lifts.
Useful rubble and stone chips will be issued at dump yard at the issue rate for usefull rubble /
stone chips. Sorting out and breaking charges included in rate analysis.
RATE ANALYSIS
UNIT :
100 cum
A. MATERIALS:
Sl No Particulars
Unit
Quantity
Rate
Amount
in Rs.
in Rs
1
Useful rubble ( at dump yard )
cum
100.00
155.00
15500.00
2
Useful stone chips ( at dump yard )
cum
15.00
175.00
2625.00
Total cost of Materials
Rs:
18125.00
B. MACHINERY:
Sl No Description
1
2

Unit

Shovel 0.85 cum


Hour
Fuel / Energy charges
Hour
Tipper 5 cum
Hour
Fuel / Energy charges
Hour
Total hire charges of Machinery

C. LABOUR:
Sl No Description
1
2
3
4
6
7

Quantity

Crew for Shovel


Crew for Tipper
Mason Class-II
work inspector
Stone breaker
mazdoor

Unit
Hour
Hour
Day
Day
Day
Day

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

2.00
2.00
6.00
6.00

Quantity
2.00
6.00
7.00
1.00
2.00
21.00

Rate
in Rs.
1706.60
937.80
446.70
322.20
Rs:

Amount
in Rs
3413.20
1875.60
2680.20
1933.20
9902.20

Rate
in Rs.

Amount
in Rs
408.20
918.60
2415.00
370.00
690.00
6195.00
10996.80

204.10
153.10
345.00
370.00
345.00
295.00
Rs:

110.00
14% 15.40
125.40

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D.Add for contractor's profit and overheads on (A+B+C)
Total cost for
100.00 cum
Rate per
cum
(A+B+C+D)/100

Total
14%

Rs:
18125.00
Rs:
9902.20
Rs:
10996.80
Rs:
39024.00
Rs. 5463.36
Rs: 44487.36
Rs: 444.90

Providing and constructing Dry rock Pitching for Groynes using Un-Coursed rubble stone of size 300 mm thick
IRR-DAW-5-9-A
(New Item 4 -2012-13) and Un-Coursed rubble stone chips from Quarry to site of work including cost of all materials, Machinery, Labour charge
hand packing Un-Course rubble stone &chips to the designed profile with all leads and lifts etc

94

Dam and Allied Works - Item Unit Rates 2014-15

DATA:

RATE ANALYSIS
UNIT :
A. MATERIALS:
Sl No Particulars
1
2

Unit

Un Coursed Rubble Stones at quarry


Stone Chips at Quarry

100 cum
Quantity

cum
cum

Rate
in Rs.
100.00
15.00

318.00
340.00
Rs:

Total cost of Materials


B. MACHINERY:
Sl No Description

1
2

Unit

Shovel 0.85 cum for loading tipper at the


Hour
worksite
Fuel / Energy charges
Hour
Tipper 5 cum
Hour
Fuel / Energy charges
Hour
Total hire charges of Machinery

C. LABOUR:
Sl No Description
1
2
3
4
6
7

Quantity

2.00
2.00
6.00
6.00

Unit

Crew for Shovel


Crew for Tipper
Mason Class-II
work inspector
Stone breaker
mazdoor

Quantity

Hour
Hour
Day
Day
Day
Day

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Rate
in Rs.

Rate
in Rs.
204.10
153.10
345.00
370.00
345.00
295.00
Rs:

3413.20
1875.60
2680.20
1933.20
9902.20

Amount
in Rs
408.20
918.60
2415.00
370.00
690.00
6195.00
10996.80

110.00
14% 15.40
125.40

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
36900.00
Rs:
9902.20
Rs:
10996.80
Rs:
57799.00
Rs. 8091.86
Rs: 65890.86
Rs: 658.90

Total
14%

D.Add for contractor's profit and overheads on (A+B+C)


Total cost for
100.00 cum
Rate per
cum
(A+B+C+D)/100

IRR-DAW-5-10

Amount
in Rs

1706.60
937.80
446.70
322.20
Rs:

2.00
6.00
7.00
1.00
2.00
21.00

Amount
in Rs
31800.00
5100.00
36900.00

Providing and laying 30 cm diameter open jointed hume pipes with collars in rock-toe for
drainage including cost of all materials, machinery, labour etc., complete with lead upto 1 km
and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No Particulars
1

UNIT :
Unit

Hume pipe 300 mm dia.with collar

Quantity

Rm

100.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No Description
1

Unit

Quantity

NIL

Rate
in Rs.
0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No Description
1
2

100 Rm
Rate
Amount
in Rs.
in Rs
650.00
65000.00
0.00
Rs:
65000.00

Mason Cl- II
mazdoor

Rs:

Unit
Day
Day

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

0.00
0.00

Quantity

Rate
in Rs.
2
6

345.00
295.00
Rs:

Amount
in Rs
0.00
0.00
0.00

Amount
in Rs
690.00
1770.00
2460.00

24.60
14% 3.40
28.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D.Add for contractor's profit and overheads on (A+B+C)
Total cost for
100.00 Rm
Rate per
Rm
(A+B+C+D)/100

Total
14%

Rs:
65000.00
Rs:
0.00
Rs:
2460.00
Rs:
67460.00
Rs. 9444.4
Rs: 76904.40
Rs: 769.00

95

Dam and Allied Works - Item Unit Rates 2014-15

IRR_DAW-6

FILTER & PITCHING WORKS :

IRR-DAW-6-1

Providing and constructing 1.20 m internal diameter and average 3 m height RCC manhole with
60 cm dia. top cover in M-15 grade cement concrete using 20 mm down graded, clean, hard
coarse aggregate, 20 cm thick for bed / sides / top slab / 1.5 m long cut-off wall and 7.5 cm
thick for cover including providing 12 mm dia reinforcement bars at 30 cm c / c bothways for
bed / sides / cut-off wall / top slab / rungs and 8 mm dia bars at 15 cm c / c bothways for cover,
excavation for foundation, providing 30 cm dia hume pipe outlet, cost of all materials, machinery,
labour, formwork, scaffolding, batching, mixing, laying, vibrating, finishing, curing etc., complete
with lead upto 1 km and all lifts.
( Cement content : 300 kg/cum , CA : 0.80 cum, Blending Ratioof CA -- 65:35,
FA : 0.44 cum, superplasticizer (0.4% by wt. of cement)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No Particulars
1
2
3
4
5
6
7
8
9
10

Cement
Cement for incidentals @ 3 kg / cum
Coarse aggregate 20 to 10 mm
Coarse aggregate 10 to 4.75 mm
Fine aggregate (Un-Screened )
Super plasticiser
Reinforcement steel with 5 % wastage
Binding wire
Hume pipe 300 mm dia
Use rate of shuttering
Scaffolding of shuttering @
Sundries

B. MACHINERY:
Sl No Description
1
2
3
4

Concrete mixer 300 / 200 ( ele )


Fuel / Energy charges
Needle vibrator 40 mm dia ( ele )
Fuel / Energy charges
Pump 5 hp ( ele )
Fuel / Energy charges
Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No Description
1
2
3
4

UNIT
Unit
kg
kg
cum
cum
cum
kg
kg
kg
Rm
sqm

1331.70
13.32
2.31
1.24
1.95
23.65
163.70
4.00
1.00
36.00
5%

LS
Total cost of Materials

Unit

Unit

2.00

Quantity

Hour
Hour
Hour
Hour
Hour
Hour
LS

Mason Cl- II
Day
Bar bender
Day
work inspector
Day
mazdoor
for excavation for foundation
Day
for bar bending
Day
for concreting
Day
for excavation for foundation
Day
for concreting
Day
for curing
Day
5
Labour for shuttering
sqm
Total cost of Labour
labour component/unit qty
8300.80
Add contractor's profit and overhead charges
0.14 1162.10
labour component/unit qty (including contractor's profit)
9462.90
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Quantity

1 Each
Rate
Amount
in Rs.
in Rs
4.00
5326.80
4.00
53.27
1210.00
2793.02
875.00
1087.56
462.00
902.36
80.00
1891.65
46.50
7611.82
70.00
280.00
650.00
650.00
235.84
8490.24
424.51
41.00
82.00
Rs:
29593.22

Rate
in Rs.
51.70
38.00
8.00
7.60
3.00
38.00
41.00
Rs:

Amount
in Rs
206.80
152.00
32.00
30.40
1.50
19.00
41.00
482.70

1.00
1.00
1.00

345.00
450.00
370.00

Amount
in Rs
345.00
450.00
370.00

2.00
1.00
5.00
2.00
4.00
1.00
36.00

295.00
295.00
295.00
295.00
295.00
295.00
75.30
Rs:

590.00
295.00
1475.00
590.00
1180.00
295.00
2710.80
8300.80

Rs:
Rs:
Rs:

29593.22
482.70
8300.80

4.00
4.00
4.00
4.00
0.50
0.50
1.00

Quantity

Rate
in Rs.

96

Dam and Allied Works - Item Unit Rates 2014-15

cum @
cum @

31.5 Rs./Cum
30.4 Rs./Cum

Lead Charges for 1Km for Cement (including Loading


and Unloading Charges)
1.35

tonne @

124.6 Rs./Tonne

167.58912

tonne @

145.6 Rs./Tonne

23.833992
Rs: 44110.37
Rs: 44110.40

0.16

1.00
(A+B+C+D)/1.0

Each

Providing and constructing longitudinal and cross graded filter drains using sand and 80-20
mm and 20 mm down graded aggregates satisfying specified filter creteria in layers as per
specifications including cost of all materials, machinery, labour, laying to required slopes,
compaction etc. complete with initial lead upto 50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No Particulars
1
2
3
4
5

UNIT :
Unit

Fine aggregate (Un-Screened )


Coarse aggregate 80-40 mm
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm down
Total cost of Materials

Quantity

cum
cum
cum
cum
cum

B. MACHINERY:
Sl No Description

47.50
17.865
1.99
24.49
8.16

Unit

Quantity

NIL

100 cum
Rate
Amount
in Rs.
in Rs
462.00
21945.00
635.00
11344.28
1145.00
2272.83
1210.00
29629.88
875.00
7142.19
Rs:
72334.16

Rate
in Rs.
0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No Description
1
2

Unit

work inspector
mazdoor

Quantity

Day
Day

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

0.00
0.00
Rs:

Amount
in Rs
0.00
0.00
0.00

370.00
295.00
Rs:

Amount
in Rs
370.00
11210.00
11580.00

Rate
in Rs.
1.00
38.00

115.80
0.14 16.20
132.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
72334.16
Rs:
0.00
Rs:
11580.00
Rs:
83914.16
Rs. 11747.98
Rs: 95662.14
Rs: 956.60

Total
14%

D.Add for contractor's profit and overheads on (A+B+C)


Total cost for
100.00 cum
Rate per
cum
(A+B+C+D)/100

IRR-DAW-6-3

Rs:
38376.72
Rs. 5372.74
61.52454
107.96

D.Add for contractor's profit and overheads on (A+B+C)


Lead Charges for 1 Km for FA
1.95
Lead Charges for 1 Km for CA
3.55

Lead Charges for 1Km for Steel (including Loading


and Unloading Charges)
Total cost for
Rate per
Each

IRR-DAW-6-2

Total
14%

Providing and constructing 1.40 m thick vertical or inclined graded filter media consisting of
20 cm thick sand layers, 25 cm thick 20 mm down coarse aggregate layers and 50 cm thick
80-20 mm coarse aggregate layer using approved materials satisfying specified filter creteria as
per specifications including cost of all materials, machinery, labour, laying to required slope,
compaction etc., complete with initial lead upto 50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No Particulars
1
2
3
4
5

UNIT :
Unit

Fine aggregate (Un-Screened )


Coarse aggregate 80-40 mm
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm down

B. MACHINERY:
Sl No Description

Quantity

cum
cum
cum
cum
cum
Total cost of Materials

Unit

1 NIL

28.60
32.13
3.57
28.13
8.93

Quantity

Rate
in Rs.
0.00
0.00

Total hire charges of Machinery

100 cum
Rate
Amount
in Rs.
in Rs
462.00
13213.20
635.00
20402.55
1145.00
4087.65
1210.00
34031.25
875.00
7809.38
Rs:
79544.03

0.00
0.00
Rs:

Amount
in Rs
0.00
0.00
0.00

97

Dam and Allied Works - Item Unit Rates 2014-15

C. LABOUR:
Sl No Description
1
2

Unit

work inspector
mazdoor

Quantity

Day
Day

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Rate
in Rs.
1.00
38.00

370.00
295.00
Rs:

115.80
0.14 16.20
132.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
79544.03
Rs:
0.00
Rs:
11580.00
Rs:
91124.03
Rs. 12757.36
Rs: 103881.39
Rs: 1038.80

Total
14%

D.Add for contractor's profit and overheads on (A+B+C)


Total cost for
100.00 cum
Rate per
cum
(A+B+C+D)/100

IRR-DAW-6-4

Providing and constructing graded filter media below and behind rock-toe consisting of
20 cm thick sand, 25 cm thick 20 - 4.75 mm and 40 cm thick 80 - 20 mm size graded coarse
aggregates satisfying filter creteria as per specifications including cost of all materials, labour,
machinery, laying to required slope, compaction etc., complete with initial lead upto 50 m and
all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No Particulars
1
2
3
4
5

UNIT
Unit

Fine aggregate (Un-Screened )


Coarse aggregate 80-40 mm
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm down
Total cost of Materials

Quantity

cum
cum
cum
cum
cum

B. MACHINERY:
Sl No Description

23.55
42.39
4.71
22.05
7.35

Unit

Quantity

NIL

100 cum
Rate
Amount
in Rs.
in Rs
462.00
10880.10
635.00
26917.65
1145.00
5392.95
1210.00
26680.50
875.00
6431.25
Rs:
76302.45

Rate
in Rs.
0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No Description
1
2

Unit

work inspector
mazdoor

Quantity

Day
Day

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

1.00
34.00

370.00
295.00
Rs:

Amount
in Rs
370.00
10030.00
10400.00

104.00
0.14 14.60
118.60

Total
14%

D.Add for contractor's profit and overheads on (A+B+C)


Total cost for
100.00 cum
Rate per
cum
(A+B+C+D)/100

(New Item2- 2011-12)

0.00
0.00
Rs:

Amount
in Rs
0.00
0.00
0.00

Rate
in Rs.

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

IRR-DAW-6-4-A

Amount
in Rs
370.00
11210.00
11580.00

Rs:
76302.45
Rs:
0.00
Rs:
10400.00
Rs:
86702.45
Rs. 12138.34
Rs: 98840.79
Rs: 988.40

Providing and constructing graded filter media below and behind rock-toe consisting of
30 cm thick 80 - 20 mm size graded coarse
aggregates satisfying filter creteria as per specifications including cost of all materials, labour,
machinery, laying to required slope, compaction etc., complete with initial lead upto 50 m and
all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No Particulars
1
2
3
4

Coarse aggregate 80-40 mm


Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm down

UNIT
Unit
cum
cum
cum
cum

Quantity
35.00
55.00
5.00
5.00

100 cum
Rate
Amount
in Rs.
in Rs
635.00
22225.00
1145.00
62975.00
1210.00
6050.00
875.00
4375.00

98

Dam and Allied Works - Item Unit Rates 2014-15

Total cost of Materials


B. MACHINERY:
Sl No Description
1

Unit

Quantity

NIL
Total hire charges of Machinery

1
2

Unit

work inspector
mazdoor

Quantity

Day
Day

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

0.00
0.00
Rs:

Amount
in Rs
0.00
0.00
0.00

370.00
295.00
Rs:

Amount
in Rs
370.00
3540.00
3910.00

Rate
in Rs.
1.00
12.00

39.10
0.14 5.50
44.60

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
95625.00
Rs:
0.00
Rs:
3910.00
Rs:
99535.00
Rs. 13934.9
Rs: 113469.90
Rs: 1134.70

Total
14%

D.Add for contractor's profit and overheads on (A+B+C)


Total cost for
100.00 cum
Rate per
cum
(A+B+C+D)/100

IRR-DAW-6-5

95625.00

Rate
in Rs.
0.00
0.00

C. LABOUR:
Sl No Description

Rs:

Providing and laying filter media consisting of 2 layers of 250 gsm poly-propeline non-woven
filter fabric and 400 mm thick 20 mm down graded coarse aggregate for vertical / inclined
and horizontal filter blanket for embankment including cost of all materials, machinery, labour
etc., complete with lead upto 50 m for aggregate and all leads for fabric and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No Particulars
1
2

UNIT :
Unit

PP filter fabric 250 gsm


20 - 10 mm CA @ 75 %
10 mm down CA @ 25 %
Total cost of Materials

sqm
cum
cum

B. MACHINERY:
Sl No Description
1

Quantity
220.00
30.00
10.00

Unit

Quantity

NIL

100 sqm
Rate
Amount
in Rs.
in Rs
154.00
33880.00
1210.00
36300.00
875.00
8750.00
Rs:
78930.00

Rate
in Rs.
0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No Description
1
2

work inspector
mazdoor

Unit
Day
Day

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Quantity

370.00
295.00
Rs:

Amount
in Rs
370.00
4130.00
4500.00

Rate
in Rs.
1.00
14.00

45.00
0.14 6.30
51.30

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D.Add for contractor's profit and overheads on (A+B+C)

0.00
0.00
Rs:

Amount
in Rs
0.00
0.00
0.00

Total
14%

Rs:
78930.00
Rs:
0.00
Rs:
4500.00
Rs:
83430.00
Rs. 11680.2

99

Dam and Allied Works - Item Unit Rates 2014-15

Total cost for


Rate per

IRR-DAW-6-6

100.00 sqm
(A+B+C+D)/100

sqm

Rs: 95110.20
Rs: 951.10

Providing and constructing 45 cm thick chimney filter using clean approved sand satisfying
filter creteria including cost of all materials, machinery, labour, compacting etc., complete with
initial lead upto 50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No Particulars
1

UNIT :
Unit

Sand (Un-Screened)

Quantity

cum

105.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No Description
1

Unit

Quantity

NIL

100 cum
Rate
Amount
in Rs.
in Rs
462.00
48510.00
0.00
Rs:
48510.00

Rate
in Rs.
0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No Description
1
2

Unit

work inspector
mazdoor

Quantity

Day
Day

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

370.00
295.00
Rs:

Amount
in Rs
370.00
8850.00
9220.00

Rate
in Rs.
1.00
30.00

92.20
0.14 12.90
105.10

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
48510.00
Rs:
0.00
Rs:
9220.00
Rs:
57730.00
Rs. 8082.2
Rs: 65812.20
Rs: 658.10

Total
14%

D.Add for contractor's profit and overheads on (A+B+C)


Total cost for
100.00 cum
Rate per
cum
(A+B+C+D)/100

IRR-DAW-6-7

0.00
0.00
Rs:

Amount
in Rs
0.00
0.00
0.00

Providing and constructing 90 cm thick transition cum filter media behind rockfill using
approved sand and 80-20 mm and 20 mm down graded aggregates satisfying the filter creteria
in layers of 30 cm thickness each as per specifications including cost of all materials,
machinery, labour, laying each layer to required slope, compaction etc., complete with initial
lead upto 50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No Particulars
1
2
3
4
5

UNIT :
Unit

Sand (Un-Screened )
Coarse aggregate 80-40 mm
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm down
Total cost of Materials

cum
cum
cum
cum
cum

B. MACHINERY:
Sl No Description
1

Quantity
34.00
30.60
3.40
25.50
8.50

Unit

Quantity

NIL

100 cum.
Rate
Amount
in Rs.
in Rs
462.00
15708.00
635.00
19431.00
1145.00
3893.00
1210.00
30855.00
875.00
7437.50
Rs:
77324.50

Rate
in Rs.
0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No Description
1
2

work inspector
mazdoor

Unit
Day
Day

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Quantity

0.00
0.00
Rs:

Amount
in Rs
0.00
0.00
0.00

370.00
295.00
Rs:

Amount
in Rs
370.00
11800.00
12170.00

Rate
in Rs.
1.00
40.00

121.70
0.14 17.00
138.70

ABSTRACT:

100

Dam and Allied Works - Item Unit Rates 2014-15

A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
14%

D.Add for contractor's profit and overheads on (A+B+C)


Total cost for
100.00 cum.
Rate per
cum.
(A+B+C+D)/100

IRR-DAW-6-8

Rs:
77324.50
Rs:
0.00
Rs:
12170.00
Rs:
89494.50
Rs. 12529.23
Rs: 102023.73
Rs: 1020.20

Providing and constructing 60 cm thick hand packed rough stone revetment with 65 to
75 cm long through stones at 1.50 m c / c over a backing of 45 cm thick graded filter media
consisting of sand, 10 mm and 40 mm size approved graded aggregates laid in layers of 15 cm
thick each including cost of all materials, machinery, labour, laying to required slopes, wedging
with chips, finishing etc. complete with initial lead upto 50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No Particulars
1
2
3
4
5
6

UNIT :
Unit

Sand (Un-Screened )
Coarse aggregate 10 mm down
Coarse aggregate 40-20 mm
Stone chips
Rough stones ( rubble ) 30 to 45 cm long
Through stones 65 to 75 cm long
Total cost of Materials

cum
cum
cum
cum
cum
Nos

B. MACHINERY:
Sl No Description
1

Quantity
15.30
15.30
15.30
9.00
57.60
44.00

Unit

Quantity

NIL

100 sqm
Rate
Amount
in Rs.
in Rs
462.00
7068.60
875.00
13387.50
1145.00
17518.50
340.00
3060.00
318.00
18316.80
59.00
2596.00
Rs:
61947.40

Rate
in Rs.
0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No Description
1
2
3

Unit

work inspector
Mason Class-II
mazdoor

Quantity

Day
Day
Day

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

370.00
345.00
295.00
Rs:

Amount
in Rs
370.00
3450.00
9735.00
13555.00

Rate
in Rs.
1.00
10.00
33.00

135.60
0.14 19.00
154.60

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
61947.40
Rs:
0.00
Rs:
13555.00
Rs:
75502.40
Rs. 10570.34
Rs: 86072.74
Rs: 860.70

Total
14%

D.Add for contractor's profit and overheads on (A+B+C)


Total cost for
100.00 sqm
Rate per
sqm
(A+B+C+D)/100

IRR-DAW-6-9

0.00
0.00
Rs:

Amount
in Rs
0.00
0.00
0.00

Providing and constructing 60 cm thick hand packed rough stone revetment with 65 to 75
cm long through stones at 1.50 m c / c over a backing of 60 cm thick graded filter media
consisting of sand, 10 mm and 40 mm size approved graded aggregates laid in layers of 20 cm
thick each including cost of all materials, machinery, labour, laying to required slopes, wedging
with chips, finishing etc. complete with initial lead upto 50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No Particulars
1
2
3
4
5
6

Sand (Un-Screened )
Coarse aggregate 10 mm down
Coarse aggregate 40-20 mm
Stone chips
Rough stones ( rubble ) 30 to 45 cm long
Through stones 65 to 75 cm long
Total cost of Materials

B. MACHINERY:
Sl No Description
1

NIL

UNIT :
Unit

Quantity

cum
cum
cum
cum
cum
Nos

Unit

20.40
20.40
20.40
9.00
57.60
44.00

Quantity

100 sqm
Rate
Amount
in Rs.
in Rs
462.00
9424.80
875.00
17850.00
1145.00
23358.00
340.00
3060.00
318.00
18316.80
59.00
2596.00
Rs:
74605.60

Rate
in Rs.
0.00

0.00

Amount
in Rs
0.00

101

Dam and Allied Works - Item Unit Rates 2014-15

0.00
Total hire charges of Machinery
C. LABOUR:
Sl No Description
1
2
3

Unit

work inspector
Mason Class-II
mazdoor

Quantity

Day
Day
Day

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

1.00
10.00
39.00

370.00
345.00
295.00
Rs:

Amount
in Rs
370.00
3450.00
11505.00
15325.00

153.30
0.14 21.50
174.80

Rs:
74605.60
Rs:
0.00
Rs:
15325.00
Rs:
89930.60
Rs. 12590.28
Rs: 102520.88
Rs: 1025.20

Total
14%

D.Add for contractor's profit and overheads on (A+B+C)


Total cost for
100.00 sqm
Rate per
sqm
(A+B+C+D)/100

Providing and constructing 60 cm thick hand packed rough stone riprap over a backing of
45 cm thick graded filter media consisting of sand, 10 mm and 40 mm size graded approved
aggregates laid in layers of 15 cm thick each including cost of all materials, machinery,
labour, laying to required slopes, wedging with stone chips etc., complete with initial lead upto
50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No Particulars
1
2
3
4
5

UNIT :
Unit

Sand (Un-Screened )
Coarse aggregate 10 mm down
Coarse aggregate 40-20 mm
Stone chips
Rough stones ( rubble )
Total cost of Materials

Quantity

cum
cum
cum
cum
cum

B. MACHINERY:
Sl No Description

15.30
15.30
15.30
9.00
60.00

Unit

Quantity

NIL

100 sqm.
Rate
Amount
in Rs.
in Rs
462.00
7068.60
875.00
13387.50
1145.00
17518.50
340.00
3060.00
318.00
19080.00
Rs:
60114.60

Rate
in Rs.
0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No Description
1
2
3

Unit

work inspector
Mason Class-II
mazdoor

Quantity

Day
Day
Day

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

0.00
0.00
Rs:

Amount
in Rs
0.00
0.00
0.00

370.00
345.00
295.00
Rs:

Amount
in Rs
370.00
1725.00
8260.00
10355.00

Rate
in Rs.
1.00
5.00
28.00

103.60
0.14 14.50
118.10

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
60114.60
Rs:
0.00
Rs:
10355.00
Rs:
70469.60
Rs. 9865.74
Rs: 80335.34
Rs: 803.40

Total
14%

D.Add for contractor's profit and overheads on (A+B+C)


Total cost for
100.00 sqm.
Rate per
sqm.
(A+B+C+D)/100

IRR-DAW-6-11

0.00
0.00

Rate
in Rs.

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

IRR-DAW-6-10

0.00
Rs:

Providing and constructing 75 cm thick hand packed rough stone riprap over a backing of
45 cm thick graded filter media consisting of sand, 10 mm and 40 mm size graded approved
aggregates laid in layers of 15 cm thick each including cost of all materials, machinery, labour,
laying to required slopes, wedging with stone chips, etc., complete with initial lead upto 50 m
and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No Particulars

UNIT :
Unit

Quantity

Rate

100 sqm
Amount

102

Dam and Allied Works - Item Unit Rates 2014-15

in Rs.
1
2
3
4
5

Sand (Un-Screened )
Coarse aggregate 10 mm down
Coarse aggregate 40-20 mm
Stone chips
Rough stones ( rubble )

cum
cum
cum
cum
cum
Total cost of Materials

B. MACHINERY:
Sl No Description
1

Unit

15.30
15.30
15.30
11.00
75.00

Quantity

NIL

462.00
875.00
1145.00
340.00
318.00
Rs:

Rate
in Rs.
0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No Description
1
2
3

Unit

work inspector
Mason Class-II
mazdoor

Quantity

Day
Day
Day

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

370.00
345.00
295.00
Rs:

Amount
in Rs
370.00
2070.00
8850.00
11290.00

112.90
0.14 15.80
128.70

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
65564.60
Rs:
0.00
Rs:
11290.00
Rs:
76854.60
Rs. 10759.64
Rs: 87614.24
Rs: 876.10

Total
14%

D.Add for contractor's profit and overheads on (A+B+C)


Total cost for
100.00 sqm
Rate per
sqm
(A+B+C+D)/100

IRR-DAW-6-12

0.00
0.00
Rs:

Amount
in Rs
0.00
0.00
0.00

Rate
in Rs.
1.00
6.00
30.00

in Rs
7068.60
13387.50
17518.50
3740.00
23850.00
65564.60

Providing and constructing 90 cm thick hand packed rough stone riprap over a backing of
45 cm thick graded filter media consisting of sand, 10 mm and 40 mm size graded approved
aggregates laid in layers of 15 cm thick each including cost of all materials, machinery,
labour, laying to required slopes, wedging with stone chips etc., complete with initial lead upto
50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No Particulars
1
2
3
4
5

UNIT :
Unit

Sand (Un-Screened )
Coarse aggregate 10 mm down
Coarse aggregate 40-20 mm
Stone chips
Rough stones ( rubble )

cum
cum
cum
cum
cum
Total cost of Materials

B. MACHINERY:
Sl No Description
1

Quantity

Unit

15.30
15.30
15.30
13.50
90.00

Quantity

NIL

100 sqm
Rate
Amount
in Rs.
in Rs
462.00
7068.60
875.00
13387.50
1145.00
17518.50
340.00
4590.00
318.00
28620.00
Rs:
71184.60

Rate
in Rs.
0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No Description
1
2
3

work inspector
Mason Class-II
mazdoor

Unit
Day
Day
Day

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Quantity

0.00
0.00
Rs:

Amount
in Rs
0.00
0.00
0.00

370.00
345.00
295.00
Rs:

Amount
in Rs
370.00
2760.00
10030.00
13160.00

Rate
in Rs.
1.00
8.00
34.00

131.60
0.14 18.40
150.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D.Add for contractor's profit and overheads on (A+B+C)
Total cost for
100.00 sqm
Rate per
sqm
(A+B+C+D)/100

Total
14%

Rs:
71184.60
Rs:
0.00
Rs:
13160.00
Rs:
84344.60
Rs. 11808.24
Rs: 96152.84
Rs: 961.50

103

Dam and Allied Works - Item Unit Rates 2014-15

IRR-DAW-6-13

Providing and laying Hariyala or other approved quality turfing sods for the slopes of earthen
embankments over 20 mm thick sand backing including cost of all materials, machinery,
labour including preparing surface, spreading sand, watering for 15 days etc., complete with
initial lead upto 1 km and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No Particulars
1
2

UNIT :
Unit

Sand for filling


Hariyala turfing sods
Total cost of Materials

B. MACHINERY:
Sl No Description
1

Quantity

cum
sqm

Unit

2.00
100.00

Quantity

NIL

100 sqm.
Rate
Amount
in Rs.
in Rs
342.00
684.00
28.00
2800.00
Rs:
3484.00

Rate
in Rs.
0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No Description

Unit

1
2

Cartman with double bullock cart


Day
mazdoor
Day
Total cost of Labour
labour component/unit qty
52.20
Add contractor's profit and overhead charges
0.14 7.30
labour component/unit qty (including contractor's profit)
59.50

Quantity

395.00
295.00
Rs:

Amount
in Rs
790.00
4425.00
5215.00

Rate
in Rs.
2.00
15.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D.Add for contractor's profit and overheads on (A+B+C)
Lead Charges for 1 Km for FA
2.00
cum @
Total cost for
100.00 sqm.
Rate per
sqm.
(A+B+C+D)/100

0.00
0.00
Rs:

Amount
in Rs
0.00
0.00
0.00

Total
14%
31.5 Rs./Cum

Rs:
3484.00
Rs:
0.00
Rs:
5215.00
Rs:
8699.00
Rs. 1217.86
63
Rs: 9979.86
Rs: 99.80

104

Tunnel and Allied Works - Item Unit Rates 2014-15

Chapter - II
TUNNEL AND ALLIED WORKS - Standard Data

(WLL BE WITH E-N-C & TO INCORPORATE CHANGES YEARLY/ AS NEEDED)


FOR THE YEAR :2014-15
Index- code
TUNNEL AND ALLIED WORKS - DATA RATES
IRR-TAW

Directions to add Seigniorage Charges and Additional Lead Charges


Seigniorage Charges:
1. The unit rate for work item in the Standard Data is exclusive of Seigniorage Charges wherever applicable.
2. The appropriate Seigniorage Charges for relevant materials are to be added to the Unit rate of work item while preparing the estimate.
(i.e., to the data itself)
3. The Provision towards Contractor's Profit and Overhead charges should not be operated on the Seigniorage Charges
while adding Seigniorage Charges to the data in the estimate
Additional Lead and Lift Charges:
1. Unless otherwise specified the basic rates are inclusive of all lifts.
2. For concrete, masonry and reinforcement items wherever initial lead of 1km is considered in the basic rate, the additional lead
charges are to be added as follows:
Additional lead charges for Cement, Steel, sand, coarse aggregate, stones and stone chips shall be worked out for total lead involved
and 1 km lead charges included in basic rate shall be deducted from total lead charges. No loading and unloading charges shall be
allowed for any item.
In case of Cement and Steel, Loading and unloading charges are already added in the work item while arriving the unit rate and
hence should not be added again
Example:
Total lead for sand from approved sand quarry :
15 Km
Initial lead included in the basic rate in the SR :
1 Km
Additional lead charges : Lead charges for 5 km
Rs.
84.10
Lead charges for next 10 km
Rs.
126
Total lead charges for 15 km /cum
Rs.
210.10
Less 1 km initial lead charges /cum
Rs.
31.50 (-)
Net additional lead charges / cum
Rs.
178.60

3. The Leads for Steel and Cement shall be from the nearest market place to the Project area
4. For earth/rockfill embankments wherever initial lead of 1km is considered in the basic rate, the additional lead charges are to be added
as follows:
Additional lead charges for Earth, Murrum etc., shall be worked out for total lead involved and 1 km lead charges included in basic
rate shall be deducted from total lead charges. No loading and unloading charges shall be allowed for any item. (same as above)
Example:
Total lead for earth from approved borrow area :
15 Km
Initial lead included in the basic rate in the SR :
1 Km
Additional lead charges : Lead charges for 5 km
Rs.
84.10
Lead charges for next 10 km
Rs.
126
Total lead charges for 15 km /cum
Rs.
210.10
Less 1 km initial lead charges /cum
Rs.
31.50 (-)
Net additional lead charges / cum
Rs.
178.60
5. The initial lead up to 50 m as mentioned in some standard data items is meant for manual lead within the working area. For
conveyance of materials, the lead required from quarry/Borrow area/ Dump Area to worksite shall be added to the data without
deducting the 50 m initial lead charges
TAW -Work Items
IRR-TAW-1

EXCAVATION :

IRR-TAW-1-1 Excavation for adit by tunnelling methods in all types of rock including cost of all materials,
machinery, labour, scaling excavated surface, ventilation, lighting, drainage, removing and
hauling the excavated muck outside adit upto specified dump area and all other ancillary
operations etc., complete with initial lead upto 1km and all lifts.

105

Tunnel and Allied Works - Item Unit Rates 2014-15

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
7
8

Particulars

Unit

Small dia explosive


Delay detonators
Electric detonators
Detonating fuse coil
Use rate of drill rod 2.5 m long
Reconditioning charges @
Use rate of air hose
Use rate of water hose
Sundries( paint / template etc )
Total cost of Materials

kg
Nos
Nos
Rm
Rm
10%
Hour
Hour
LS

B. MACHINERY:
Sl No
1
2
3
4
5
6
7
8
9

Description

Unit

Drilling jumbo
Fuel / Energy charges
Air compressor 15 cmm ( ele )
Fuel / Energy charges
Jack hammer ( 4 x 5 hrs )
Fuel / Energy charges
Pusher leg
Fuel / Energy charges
Convey mucker
Fuel / Energy charges
Dumper ( 1 x 6.5 hrs )
Fuel / Energy charges
Pump 10 hp ( ele )
Fuel / Energy charges
Ventilation fans 20 hp
Fuel / Energy charges
Sundries(explosive van / magazine )
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

C. LABOUR:
Sl No
1
2
3
4
5
6
7
8
9
10
11

UNIT :

Description

Crew for Drilling jumbo


Crew for Air compressor
Crew for Jack hammer
Crew for Convey mucker
Crew for Dumper
Crew for Pump
Crew for ventilation fans
Surveyor
Foreman
Fitter / Mechanic
Blaster ( Licensed )

Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Day
Day
Day
Day

Quantity

38.50 cum

40.00
54.00
5.00
50.00
119.00

70.00
23.00
13.00
11.00
41.69

20.00
20.00
2.00

5.47
6.84
41.00
Rs:

Amount
in Rs.
2800.00
1242.00
65.00
550.00
4961.51
496.15
109.38
136.88
82.00
10442.91

Rate
in Rs.
368.40
46.00
138.80
951.20
19.80
0.00
12.70
0.00
822.80
264.80
580.70
429.70
6.70
76.10
11.50
152.20
41.00
Rs:

Amount
in Rs.
2947.20
368.00
694.00
4756.00
396.00
0.00
254.00
0.00
5348.20
1721.20
3774.55
2793.05
33.50
380.50
11.50
152.20
82.00
23711.90

Rate
in Rs.
151.80
151.80
284.70
151.80
195.90
72.10
24.90
550.00
440.00
385.00
440.00

Amount
in Rs.
1214.40
759.00
5694.00
986.70
1273.35
360.50
24.90
275.00
440.00
770.00
440.00

Quantity
8.00
8.00
5.00
5.00
20.00
20.00
20.00
20.00
6.50
6.50
6.50
6.50
5.00
5.00
1.00
1.00
2.00

Quantity
8.00
5.00
20.00
6.50
6.50
5.00
1.00
0.50
1.00
2.00
1.00

Rate
in Rs.

106

Tunnel and Allied Works - Item Unit Rates 2014-15

12
13
14
15
16

Helper blasting
Hammerman
work inspector 1 in each shift
Khalasi for mucking shift 4 Nos
mazdoor
for mucking shift 4 Nos
for other 2 shifts 1 No each shift
for cleaning & miscellaneous
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Day
Day
Day
Day

2.00
2.00
3.00
4.00

345.00
345.00
370.00
385.00

690.00
690.00
1110.00
1540.00

Day
Day
Day

4.00
2.00
2.00

295.00
295.00
295.00
Rs:

1180.00
590.00
590.00
18627.85

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

10442.91
23711.90
18627.85
52782.66
527.83
2375.22
844.52
1319.57
57849.79

Rs:
Rs:
Rs:

8098.97
65948.76
1713.00

483.80
0.14 67.70
551.50

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Add for Air and Water line @
Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @

1.00%
4.50%
1.60%
2.50%
Total

D.Add for contractor's profit and overheads on (A+B+C+other


percentages)
Total cost for
38.50 cum
Rate per cum
(A+B+C+D)/38.50

14%

IRR-TAW-1-2 Excavation for vertical / inclined shaft in all types of soft / hard rock including cost of all
materials, machinery, labour, shoring, strutting, scaling excavated surface, ventilation, lighting,
drainage, removing and hauling excavated muck outside shaft upto specified dump area and
all other ancillary operations etc., complete with initial lead upto 1 km and all lifts.

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
7
8
9
10

Particulars

Unit

Small dia explosive


Electric detonator
Detonating fuse coil
Use rate of drill rod 1.6 m long
Reconditioning charges @
Use rate of air hose
Use rate of water hose
Use rate of rail track
Use rate of mucking bucket
Sundries( paint / template etc )
Total cost of Materials

kg
Nos
Rm
Rm
10%
Hour
Hour
Shift
Hour
LS

B. MACHINERY:
Sl No
1
2
3
4
5
6
7

UNIT :

Description

Unit

Air compressor 15 cmm ( ele )


Fuel / Energy charges
Jack hammer ( 4 x 4 hrs )
Fuel / Energy charges
Pump 10 hp ( ele )
Fuel / Energy charges
Pump 20 hp electric
Fuel / Energy charges
Winch 35 hp electric
Fuel / Energy charges
Tipping tub 1.5 cum
Fuel / Energy charges
Sundries(explosive van / magazine )
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Quantity

30.00 cum

32.00
65.00
50.00
95.00

70.00
13.00
11.00
26.85

18.00
16.00
3.00
24.00
2.00

21.88
27.38
127.46
24.19
41.00
Rs:

Amount
in Rs.
2240.00
845.00
550.00
2551.07
255.11
393.75
438.00
382.39
580.54
82.00
8317.85

Rate
in Rs.
138.80
951.20
19.80
0.00
6.70
76.10
12.30
152.20
129.40
186.40
64.20
0.00
41.00
Rs:

Amount
in Rs.
624.60
4280.40
316.80
0.00
26.80
304.40
24.60
304.40
3623.20
5219.20
1540.80
0.00
82.00
16347.20

Quantity
4.50
4.50
16.00
16.00
4.00
4.00
2.00
2.00
28.00
28.00
24.00
24.00
2.00

Rate
in Rs.

107

Tunnel and Allied Works - Item Unit Rates 2014-15

C. LABOUR:
Sl No

Description

1
2
3
4
5
6
7
8
9
10
11
12
13
14

Crew for Air compressor


Crew for Jack hammer
Crew for Pump 10 hp
Crew for Pump 20 hp
Crew for Winch
Surveyor
Foreman
Fitter / Mechanic
Blaster ( Licensed )
Helper blasting
Hammerman 1 No. in each shift
work inspector 1 in each shift
Khalasi for mucking 2 Nos in each shift
mazdoor
for mucking 8 Nos in each shift
for other 2 shifts 1 No / shift
for cleaning & miscellaneous
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Unit

Quantity

Hour
Hour
Hour
Hour
Hour
Day
Day
Day
Day
Day
Day
Day
Day

4.50
16.00
4.00
2.00
28.00
0.50
4.00
2.00
1.00
2.00
3.00
4.00
6.00

Day
Day
Day

24.00
2.00
2.00

Rate
in Rs.
151.80
284.70
72.10
72.10
227.80
550.00
440.00
385.00
440.00
345.00
345.00
370.00
385.00

Amount
in Rs.
683.10
4555.20
288.40
144.20
6378.40
275.00
1760.00
770.00
440.00
690.00
1035.00
1480.00
2310.00

295.00
295.00
295.00
Rs:

7080.00
590.00
590.00
29069.30

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

8317.85
16347.20
29069.30
53734.35
537.34
2418.05
859.75
1343.36
58892.85

Rs:
Rs:
Rs:

8245.00
67137.85
2237.90

969.00
0.14 135.70
1104.70

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Add for Air and Water line @
Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @

1.00%
4.50%
1.60%
2.50%
Total

D.Add for contractor's profit and overheads on (A+B+C+other


percentages)
Total cost for
30.00 cum
Rate per cum
(A+B+C+D)/30.0

14%

IRR-TAW-1-3 Excavation for tunnel by tunnelling methods in rock not requiring supports including cost
of all materials,machinery, labour, scaling excavated surface, removing under-cuts, ventilation,
lighting, drainage, removing and hauling the excavated muck outside tunnel upto specified
dump area and all other ancillary operations etc., complete with initial lead upto 1 km and
all lifts.
DATA:

DATA:

Size of tunnel assumed ( finished section )


Shape of tunnel assumed for excavation
Height of tunnel assumed ( finished section )
Length of tunnel assumed
Thickness of CC lining
Pay-line margin assumed
Diameter of tunnel upto pay line for excavation
Distance of dump yard from face
Haulage of excavated muck

RATE ANALYSIS

:
:
:
:
:
:
:
:within
:

UNIT :

4.50 m dia
D - shape
4.50
1000
0.30
0.20
5.50
500

m
m
m
m
m
m

By dumpers

48.60 cum

108

Tunnel and Allied Works - Item Unit Rates 2014-15

A. MATERIALS:
Sl No
1
2
3
4
5
6
7
8

Particulars

Unit

Small dia explosive


Delay detonators
Electric detonators
Detonating fuse coil
Use rate of drill rod 2.5 m long
Reconditioning charges @
Use rate of air hose
Use rate of water hose
Sundries( paint / template etc )
Total cost of Materials

kg
Nos
Nos
Rm
Rm
10%
Hour
Hour
LS

B. MACHINERY:
Sl No
1
2
3
4
5
6
7
8
9

Description

Unit

Drilling jumbo
Fuel / Energy charges
Air compressor 15 cmm ( ele )
Fuel / Energy charges
Jack hammer ( 4 x 6.5 hrs )
Fuel / Energy charges
Pusher leg
Fuel / Energy charges
Convey mucker
Fuel / Energy charges
Dumper ( 2 x 6 hrs )
Fuel / Energy charges
Pump 10 hp ( ele )
Fuel / Energy charges
Ventilation fans 20 hp
Fuel / Energy charges
Sundries(explosive van / magazine )
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

C. LABOUR:
Sl No

Description

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16

Crew for Drilling jumbo


Crew for Air compressor
Crew for Jack hammer
Crew for Convey mucker
Crew for Dumper
Crew for Pump
Crew for ventilation fans
Surveyor
Foreman
Fitter / Mechanic
Blaster ( Licensed )
Helper blasting
Hammerman
work inspector 1 in each shift
Khalasi for mucking shift 4 Nos
mazdoor
for mucking shift 8 Nos
for other 2 shifts 1 No each shift
for cleaning & miscellaneous
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Unit

Quantity
54.00
68.00
10.00
50.00
150.00

70.00
23.00
13.00
11.00
41.69

24.00
24.00
2.00

5.47
6.84
41.00
Rs:

Amount
in Rs.
3780.00
1564.00
130.00
550.00
6254.00
625.40
131.25
164.25
82.00
13280.90

Rate
in Rs.
368.40
46.00
138.80
951.20
19.80
0.00
12.70
0.00
822.80
264.80
580.70
429.70
6.70
76.10
11.50
152.20
41.00
Rs:

Amount
in Rs.
3684.00
460.00
902.20
6182.80
514.80
0.00
330.20
0.00
4936.80
1588.80
6968.40
5156.40
43.55
494.65
23.00
304.40
82.00
31672.00

Rate
in Rs.
151.80
151.80
284.70
151.80
195.90
72.10
24.90
550.00
440.00
385.00
440.00
345.00
345.00
370.00
385.00

Amount
in Rs.
1518.00
986.70
7402.20
910.80
2350.80
468.65
49.80
275.00
440.00
770.00
440.00
690.00
690.00
1110.00
1540.00

295.00
295.00
295.00
Rs:

2360.00
590.00
590.00
23181.95

Rs:
Rs:
Rs:
Rs:
Rs:

13280.90
31672.00
23181.95
68134.85
681.35

Quantity
10.00
10.00
6.50
6.50
26.00
26.00
26.00
26.00
6.00
6.00
12.00
12.00
6.50
6.50
2.00
2.00
2.00

Quantity

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Day
Day
Day
Day
Day
Day
Day
Day

10.00
6.50
26.00
6.00
12.00
6.50
2.00
0.50
1.00
2.00
1.00
2.00
2.00
3.00
4.00

Day
Day
Day

8.00
2.00
2.00

Rate
in Rs.

477.00
0.14 66.80
543.80

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Add for Air and Water line @

1.00%

109

Tunnel and Allied Works - Item Unit Rates 2014-15

Add for Ventilation @


Add for Lighting @
Add for Ele sub-station / Demand charges @

4.50%
1.60%
2.50%
Total

D.Add for contractor's profit and overheads on (A+B+C+other


percentages)
Total cost for
48.60 cum
Rate per cum
(A+B+C+D)/48.60

14%

Rs:
Rs:
Rs:
Rs:

3066.07
1090.16
1703.37
74675.80

Rs:
Rs:
Rs:

10454.61
85130.41
1751.70

IRR-TAW-1-4 Excavation for tunnel by tunnelling methods including excavation for supports in all types of
soil / rock strata requiring supports ( excluding cost of providing supports ) including cost of
all other materials, machinery, labour, scaling excavated surface, ventilation, lighting, drainage,
removing and hauling the excavated muck outside tunnel upto specified dump area and all
other ancillary operations etc., complete with initial lead upto 1 km and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
7
8

Particulars

Unit

Small dia explosive


Delay detonators
Electric detonators
Detonating fuse coil
Use rate of drill rod 2.5 m long
Reconditioning charges @
Use rate of air hose
Use rate of water hose
Sundries( paint / template etc )
Total cost of Materials

kg
Nos
Nos
Rm
Rm
10%
Hour
Hour
LS

B. MACHINERY:
Sl No
1
2
3
4
5
6
7
8
9

Description

Unit

Drilling jumbo
Fuel / Energy charges
Air compressor 15 cmm ( ele )
Fuel / Energy charges
Jack hammer ( 4 x 6 hrs )
Fuel / Energy charges
Pusher leg
Fuel / Energy charges
Convey mucker
Fuel / Energy charges
Dumper ( 2 x 6 hrs )
Fuel / Energy charges
Pump 10 hp ( ele )
Fuel / Energy charges
Ventilation fans 20 hp
Fuel / Energy charges
Sundries(explosive van / magazine )
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

C. LABOUR:
Sl No
1
2
3
4
5
6
7
8
9
10
11
12

UNIT :

Description

Crew for Drilling jumbo


Crew for Air compressor
Crew for Jack hammer
Crew for Convey mucker
Crew for Dumper
Crew for Pump
Crew for ventilation fans
Surveyor
Foreman
Fitter / Mechanic
Blaster ( Licensed )
Helper blasting

Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Day
Day
Day
Day
Day

Quantity

46.00 cum

41.00
77.00
10.00
50.00
144.00

70.00
23.00
13.00
11.00
41.69

24.00
24.00
2.00

5.47
6.84
41.00
Rs:

Amount
in Rs.
2870.00
1771.00
130.00
550.00
6003.84
600.38
131.25
164.25
82.00
12302.72

Rate
in Rs.
368.40
46.00
138.80
951.20
19.80
0.00
12.70
0.00
822.80
264.80
580.70
429.70
6.70
76.10
11.50
152.20
41.00
Rs:

Amount
in Rs.
4052.40
506.00
832.80
5707.20
475.20
0.00
304.80
0.00
4936.80
1588.80
6968.40
5156.40
40.20
456.60
23.00
304.40
82.00
31435.00

Rate
in Rs.
151.80
151.80
284.70
151.80
195.90
72.10
24.90
550.00
440.00
385.00
440.00
345.00

Amount
in Rs.
1669.80
910.80
6832.80
910.80
2350.80
432.60
49.80
275.00
440.00
770.00
440.00
690.00

Quantity
11.00
11.00
6.00
6.00
24.00
24.00
24.00
24.00
6.00
6.00
12.00
12.00
6.00
6.00
2.00
2.00
2.00

Quantity
11.00
6.00
24.00
6.00
12.00
6.00
2.00
0.50
1.00
2.00
1.00
2.00

Rate
in Rs.

110

Tunnel and Allied Works - Item Unit Rates 2014-15

13
14
15
16

Hammerman 2 Nos
work inspector 1 in each shift
Khalasi for mucking shift 4 Nos
mazdoor
for mucking shift 8 Nos
for other 2 shifts 1 No each shift
for cleaning & miscellaneous
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Day
Day
Day

2.00
3.00
4.00

345.00
370.00
385.00

690.00
1110.00
1540.00

Day
Day
Day

8.00
2.00
2.00

295.00
295.00
295.00
Rs:

2360.00
590.00
590.00
22652.40

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

12302.72
31435.00
22652.40
66390.12
663.90
2987.56
1062.24
1659.75
72763.58

Rs:
Rs:
Rs:

10186.90
82950.48
1803.30

492.40
0.14 68.90
561.30

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Add for Air and Water line @
Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @

1.00%
4.50%
1.60%
2.50%
Total

D.Add for contractor's profit and overheads on (A+B+C+other


percentages)
Total cost for
46.00 cum
Rate per cum
(A+B+C+D)/46.0

14%

IRR-TAW-1-5 Excavation for tunnel by heading and benching tunnelling methods including excavation
for supports in all types of soil / rock strata requiring supports ( excluding cost of providing
supports ) for roof before benching including cost of all other materials, machinery, labour,
scaling excavated surface, ventilation, lighting, drainage removing and hauling excavated muck
outside tunnel upto specified dump area and all other ancillary operations etc., complete with
initial lead upto 1 km and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
7
8

Particulars

Unit

Small dia explosive


Delay detonators
Electric detonator
Detonating fuse coil
Use rate of drill rod 2.5 m long
Reconditioning charges @
Use rate of air hose
Use rate of water hose
Sundries( paint / template etc )
Total cost of Materials

kg
Nos
Nos
Rm
Rm
10%
Hour
Hour
LS

B. MACHINERY:
Sl No
1
2

UNIT :

Description

Drilling jumbo
Fuel / Energy charges
Air compressor 15 cmm ( ele )

Unit
Hour
Hour
Hour

Quantity

50.00 cum

44.00
84.00
10.00
50.00
157.00

70.00
23.00
13.00
11.00
41.69

26.00
26.00
2.00

5.47
6.84
41.00
Rs:

Amount
in Rs.
3080.00
1932.00
130.00
550.00
6545.85
654.59
142.19
177.94
82.00
13294.56

Rate
in Rs.
368.40
46.00
138.80

Amount
in Rs.
4420.80
552.00
902.20

Quantity
12.00
12.00
6.50

Rate
in Rs.

111

Tunnel and Allied Works - Item Unit Rates 2014-15

3
4
5
6
7
8
9

Fuel / Energy charges


Jack hammer ( 4 x 6.5 hrs )
Fuel / Energy charges
Pusher leg
Fuel / Energy charges
Convey mucker
Fuel / Energy charges
Dumper ( 2 x 6.5 hrs )
Fuel / Energy charges
Pump 10 hp ( ele )
Fuel / Energy charges
Ventilation fans 20 hp
Fuel / Energy charges
Sundries(explosive van / magazine )
Total hire charges of Machinery

C. LABOUR:
Sl No

Description

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15

Crew for Drilling jumbo


Crew for Air compressor
Crew for Jack hammer
Crew for Convey mucker
Crew for Dumper
Crew for Pump
Crew for Ventilation fan
Surveyor
Foreman
Fitter / Mechanic
Blaster ( Licensed )
Helper blasting
Hammerman 2 Nos
work inspector 1 in each shift
Khalasi
for pushing muck in heading portion
for mucking shift 4 Nos
16
mazdoor
for mucking shift 8 Nos
for other 2 shifts 1 No each shift
for cleaning &miscellaneous
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Unit

6.50
26.00
26.00
26.00
26.00
6.50
6.50
13.00
13.00
6.50
6.50
3.00
3.00
2.00

Quantity

951.20
19.80
0.00
12.70
0.00
822.80
264.80
580.70
429.70
6.70
76.10
11.50
152.20
41.00
Rs:

6182.80
514.80
0.00
330.20
0.00
5348.20
1721.20
7549.10
5586.10
43.55
494.65
34.50
456.60
82.00
34218.70

Amount
in Rs.
1821.60
986.70
7402.20
986.70
2546.70
468.65
74.70
275.00
440.00
770.00
880.00
1380.00
690.00
1110.00

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Day
Day
Day
Day
Day
Day
Day

12.00
6.50
26.00
6.50
13.00
6.50
3.00
0.50
1.00
2.00
2.00
4.00
2.00
3.00

Rate
in Rs.
151.80
151.80
284.70
151.80
195.90
72.10
24.90
550.00
440.00
385.00
440.00
345.00
345.00
370.00

Day
Day

4.00
4.00

385.00
385.00

1540.00
1540.00

Day
Day
Day

8.00
2.00
2.00

295.00
295.00
295.00
Rs:

2360.00
590.00
590.00
26452.25

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

13294.56
34218.70
26452.25
73965.51
739.66
3328.45
1183.45
1849.14
81066.20

Rs:
Rs:
Rs:

11349.27
92415.47
1848.30

529.00
0.14 74.10
603.10

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Add for Air and Water line @
Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @

1.00%
4.50%
1.60%
2.50%
Total

D.Add for contractor's profit and overheads on (A+B+C+other


percentages)
Total cost for
50.00 cum
Rate per cum
(A+B+C+D)/50.0
NOTE:

14%

Where mucking is to be carried out through shaft using winch and mucking tub system
increase the basic rates for items IRR-TAW-1-3, IRR-TAW-1-4 & IRR-TAW-1-5 by 8 percent.

IRR-TAW-1-6 Removing and hauling muck overfallen due to natural causes such as geological faults
etc., out of tunnel including breaking large fragments by blasting if necessary and disposing off
the same in specified dump area or as directed including cost of all materials, machinery,
labour, ventilation, drainage, lighting and all other ancillary operations etc., complete with
initial lead upto 1 km and all lifts.

112

Tunnel and Allied Works - Item Unit Rates 2014-15

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
7

Particulars

Unit

Use rate of drill rod


Reconditioning charges @
Explosive small dia.
Detonator ( ele )
Detonating fuse coil
Use rate of air hose
Use rate of water hose
Sundries
Total cost of Materials

Rm
10%
kg
Nos.
Rm
Hour
Hour
LS

B. MACHINERY:
Sl No
1
2
3
4
5
6

UNIT :

Description

Unit

Air compressor 15 cmm ( ele )


Fuel / Energy charges
Jack hammer
Fuel / Energy charges
Pump 10 hp ( ele )
Fuel / Energy charges
Convey mucker
Fuel / Energy charges
Dumper 4.5 cum
Fuel / Energy charges
Sundries
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

C. LABOUR:
Sl No

Description

1
2
3
4
5
6
7
8

Crew for Air compressor


Crew for Jack hammer
Crew for Pump
Crew for Convey mucker
Crew for Dumper
Blaster ( Licensed )
Helper blasting
mazdoor
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Unit

Quantity
15.00

26.85

8.00
30.00
20.00
4.00
4.00
1.00

70.00
13.00
11.00
5.47
6.84
41.00
Rs:

Amount
in Rs.
402.80
40.28
560.00
390.00
220.00
21.88
27.38
41.00
1703.33

Rate
in Rs.
138.80
951.20
19.80
0.00
6.70
76.10
822.80
264.80
580.70
429.70
41.00
Rs:

Amount
in Rs.
138.80
951.20
79.20
0.00
6.70
76.10
4936.80
1588.80
6968.40
5156.40
41.00
19943.40

Rate
in Rs.
151.80
284.70
72.10
151.80
195.90
440.00
345.00
295.00
Rs:

Amount
in Rs.
151.80
1138.80
72.10
910.80
2350.80
220.00
172.50
2360.00
7376.80

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

1703.33
19943.40
7376.80
29023.53
290.24
1306.06
464.38
725.59
31809.79

Rs:
Rs:
Rs:

4453.37
36263.16
362.60

Quantity
1.00
1.00
4.00
4.00
1.00
1.00
6.00
6.00
12.00
12.00
1.00

Quantity

Hour
Hour
Hour
Hour
Hour
Day
Day
Day

100.00 cum

1.00
4.00
1.00
6.00
12.00
0.50
0.50
8.00

Rate
in Rs.

73.80
0.14 10.30
84.10

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Add for Air and Water line @
Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @

1.00%
4.50%
1.60%
2.50%
Total

D.Add for contractor's profit and overheads on (A+B+C+other


percentages)
Total cost for
100.00 cum
Rate per cum
(A+B+C+D)/100.0

14%

IRR_TAW-2 DEWATERING & GUNITING WORKS :


IRR-TAW-2-1 Dewatering tunnel by pumping out water collected by natural drainage inside tunnel including
providing sump wherever necessary, cost of all materials, machinery, labour, drainage, lighting,
ventilation and all other ancillary operations etc., complete.

113

Tunnel and Allied Works - Item Unit Rates 2014-15

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

Particulars

Unit

Use rate of G.I.pipe 100 mm dia


Sundries
Total cost of Materials

Hour
LS

B. MACHINERY:
Sl No
1
2
3

UNIT :

Description

Unit

Electric pump 20 hp
Fuel / Energy charges
Sundries(Starter/Switches ete)
Total hire charges of Machinery

Hour
Hour
LS

C. LABOUR:
Sl No

Description

1
2
3

Crew charges for Pump


Laying & dismantling pipe
mazdoor
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Unit

Quantity

15.00 Kwhr
Rate
in Rs.
4.67
41.00
Rs:

Amount
in Rs.
4.67
4.10
8.77

12.30
152.20
41.00
Rs:

Amount
in Rs.
12.30
152.20
4.10
168.60

1.00
0.10

Quantity

Rate
in Rs.

1.00
1.00
0.10

Quantity

Hour
LS
Day

Rate
in Rs.

1.00
0.05
0.10

72.10
41.00
295.00
Rs:

Amount
in Rs.
72.10
2.05
29.50
103.65

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

8.77
168.60
103.65
281.02
2.81
12.65
4.50
7.03
307.99

Rs:
Rs:
Rs:

43.12
351.11
23.40

6.90
0.14 1.00
7.90

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Add for Air and Water line @
Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @

1.00%
4.50%
1.60%
2.50%
Total

D.Add for contractor's profit and overheads on (A+B+C+other


14%
percentages)
Total cost for
15.00 Kwhr
(A+B+C+D)/15.0
Rate per Kwhr

IRR-TAW-2-2 Providing 25 mm thick guniting to sides and arch of tunnel in cement mortar 1 : 3 proportion
by weight including cost of all materials, machinery, labour, ventilation, lighting, drainage
and all other ancillary operations etc., complete with lead upto 1 km and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6

Particulars

Unit

Cement
Sand (Screened)
Use rate of grout hose 20 m
Use rate of water hose 20 m
Use rate of guniting nozzle
Sundries
Total cost of Materials

kg
cum
Hour
Hour
Hour
LS

B. MACHINERY:
Sl No
1
2
3

UNIT :

Description

Guniting equipment
Fuel / Energy charges
Air compressor 8.5 cmm ( ele )
Fuel / Energy charges
Pump 10 hp ( ele )

Unit
Hour
Hour
Hour
Hour
Hour

Quantity
600.00
1.10
8.00
8.00
8.00
2.00

Quantity
8.00
8.00
8.00
8.00
1.00

36.00 sqm
Rate
in Rs.
4.00
606.00
5.47
6.84
3.50
41.00
Rs:

Amount
in Rs.
2400.00
666.60
43.75
54.75
28.00
82.00
3275.10

Rate
in Rs.
110.10
0.00
170.80
428.00
6.70

Amount
in Rs.
880.80
0.00
1366.40
3424.00
6.70

114

Tunnel and Allied Works - Item Unit Rates 2014-15

4
5

Fuel / Energy charges


Drilling jumbo
Fuel / Energy charges
Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No

Hour
Hour
Hour
LS

Description

Unit

1
2
3
4
5
6

Crew for Guniting equipment


Crew for Air compressor
Crew for pump
Crew for Drilling jumbo
Mason Cl I
mazdoor
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Hour
Hour
Hour
Hour
Day
Day

1.00
4.00
4.00
2.00

76.10
368.40
46.00
41.00
Rs:

76.10
1473.60
184.00
82.00
7493.60

Rate
in Rs.
189.80
142.40
72.10
151.80
385.00
295.00
Rs:

Amount
in Rs.
1518.40
1139.20
72.10
607.20
385.00
1770.00
5491.90

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

3275.10
7493.60
5491.90
16260.60
162.61
731.73
260.17
406.52
17821.62

14%
Rs:
cum @
31.5 Rs./Cum

2495.03
34.65

Quantity
8.00
8.00
1.00
4.00
1.00
6.00
152.60
0.14 21.40
174.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Add for Air and Water line @
Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @

1.00%
4.50%
1.60%
2.50%
Total

D.Add for contractor's profit and overheads on (A+B+C+other


percentages)
Lead Charges for 1 Km for FA
1.10
Lead Charges for 1Km for Cement (including
Loading and Unloading Charges)
Total cost for
Rate per sqm

0.60

tonne @
36.00 sqm
(A+B+C+D)/36.0

124.6 Rs./Tonne
Rs:
Rs:

74.76
20426.05
567.40

IRR-TAW-2-3 Shortcreting in two layers (each layer+38 mm thickness) for slabs duly fixing chain weld wire mesh
(new4 - 201112)

100 x 100x5 mm in between the two layers including cost and conveyance of all materials,
labour charges, all heads, lifts, centering, scaffolding, machine mixing,
laying concrete with shortcrete machine etc. complete as per specification and as
directed by Engineer-in-Charge

Data

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
7
8

Cement
Sand (Screened)
Coarse aggregate 10-4.75 mm size
Use rate of grout hose 20 m
Use rate of water hose 20 m
Use rate of guniting nozzle
Welded steel wire fabric 100 x 100 x 5 mm
Sundries
Total cost of Materials

B. MACHINERY:
Sl No
1
2
3

Particulars

Description

Guniting equipment
Fuel / Energy charges
Air compressor 8.5 cmm ( ele )
Fuel / Energy charges
Pump 10 hp ( ele )
Fuel / Energy charges

UNIT :
Unit
kg
cum
cum
Hour
Hour
Hour
kg
LS

Unit
Hour
Hour
Hour
Hour
Hour
Hour

Quantity
1548.00
2.41
1.03
8.00
8.00
8.00
108.00
2.00

Quantity
8.00
8.00
8.00
8.00
1.00
1.00

36.00 sqm
Rate
in Rs.
4.00
606.00
875.00
5.47
6.84
3.50
155.00
41.00
Rs:

Amount
in Rs.
6192.00
1460.46
901.25
43.75
54.75
28.00
16740.00
82.00
25502.21

Rate
in Rs.
110.10
0.00
170.80
428.00
6.70
76.10

Amount
in Rs.
880.80
0.00
1366.40
3424.00
6.70
76.10

115

Tunnel and Allied Works - Item Unit Rates 2014-15

4
5

Drilling jumbo
Fuel / Energy charges
Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No

Description

1
2
3
4
5
6

Crew for Guniting equipment


Crew for Air compressor
Crew for pump
Crew for Drilling jumbo
Mason Cl I
mazdoor
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Hour
Hour
LS

Unit
Hour
Hour
Hour
Hour
Day
Day

4.00
4.00
2.00

Quantity
8.00
8.00
1.00
4.00
1.00
6.00

368.40
46.00
41.00
Rs:

1473.60
184.00
82.00
7493.60

Rate
in Rs.
189.80
142.40
72.10
151.80
385.00
295.00
Rs:

Amount
in Rs.
1518.40
1139.20
72.10
607.20
385.00
1770.00
5491.90

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

25502.21
7493.60
5491.90
38487.71
384.88
1731.95
615.80
962.19
42182.53

152.60
0.14 21.40
174.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Add for Air and Water line @
Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @

1.00%
4.50%
1.60%
2.50%
Total

D.Add for contractor's profit and overheads on (A+B+C+other


14%
Rs:
percentages)
Lead Charges for 1 Km for FA
2.41
cum @
31.5 Rs./Cum
Lead Charges for 1 Km for CA
1.03
cum @
30.4 Rs./Cum
Lead Charges for 1Km for Cement (including
Loading and Unloading Charges)
1.55
tonne @ 124.6 Rs./Tonne
Total cost for
36.00 sqm
Rs:
Rate per sqm
(A+B+C+D)/36.0
Rs:

5905.55
75.915
31.312
192.8808
48388.19
1344.10

IRR_TAW-3 TEMPORARY & PERMANENT SUPPORTS :


IRR-TAW-3-1 Providing and fixing 25 mm diameter steel rock bolts with mechanical / wedge type
anchorage including drilling 35 mm dia holes, providing 15 cm long 20 mm thick steel tapered
wedge, 10 mm thick plate washers and nuts, tightening bolt by torque wrench, cost of all
materials, machinery, labour, ventilation, lighting, drainage and all other ancillary operations
etc., complete with lead upto 1 km and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
7

Particulars

Unit

Rein.Steel with 5 % wastage


Steel plate for washers
Steel plate for wedges
M S Nuts for bolts
Use rate of drill rod
Reconditioning charges @
Use rate of air hose 4 Nos
Use rate of water hose 4 Nos
Sundries ( gas for cutting / heating etc )
Total cost of Materials

kg
kg
kg
kg
Rm
10%
Hour
Hour
LS

B. MACHINERY:
Sl No
1
2

UNIT :

Description

Air compressor 15 cmm ( ele )


Fuel / Energy charges
Pump 10 hp ( ele )

Unit
Hour
Hour
Hour

Quantity

20.00 Rm

86.91
65.94
6.18
4.00
20.00

46.50
46.00
46.00
90.00
41.69

6.00
6.00
5.00

5.47
6.84
41.00
Rs:

Amount
in Rs.
4041.49
3033.24
284.37
360.00
833.87
83.39
32.81
41.06
205.00
8915.22

Rate
in Rs.
138.80
951.20
6.70

Amount
in Rs.
208.20
1426.80
6.70

Quantity
1.50
1.50
1.00

Rate
in Rs.

116

Tunnel and Allied Works - Item Unit Rates 2014-15

3
4
5
6

Fuel / Energy charges


Jack hammer
Fuel / Energy charges
Pusher leg
Fuel / Energy charges
Drilling jumbo
Fuel / Energy charges
Sundries ( lathe, blower etc )
Total hire charges of Machinery

C. LABOUR:
Sl No

Description

1
2
3
4
5
6
7
8
9
10
11

Crew for Air compressor


Crew for pump
Crew for Jack hammer
Crew for Drilling jumbo
Fitter
Gas cutter
Turner
Blacksmith
Khalasi ( 2 x 0.5 )
Hammerman
mazdoor
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Unit
Hour
Hour
Hour
Hour
Day
Day
Day
Day
Day
Day
Day

1.00
6.00
6.00
6.00
6.00
4.00
4.00
5.00

Quantity
1.50
1.00
6.00
4.00
0.50
1.00
1.00
1.00
1.00
0.50
2.00

76.10
19.80
0.00
12.70
0.00
368.40
46.00
41.00
Rs:

76.10
118.80
0.00
76.20
0.00
1473.60
184.00
205.00
3775.40

Rate
in Rs.
151.80
72.10
284.70
151.80
385.00
385.00
440.00
385.00
385.00
345.00
295.00
Rs:

Amount
in Rs.
227.70
72.10
1708.20
607.20
192.50
385.00
440.00
385.00
385.00
172.50
590.00
5165.20

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

8915.22
3775.40
5165.20
17855.82
178.56
803.51
285.69
446.40
19569.98

258.30
0.14 36.20
294.50

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Add for Air and Water line @
Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @

1.00%
4.50%
1.60%
2.50%
Total

D.Add for contractor's profit and overheads on (A+B+C+other


14%
Rs:
percentages)
Lead Charges for 1Km for Steel (including Loading
and Unloading Charges)
0.16
tonne @ 145.6 Rs./Tonne
Total cost for
20.00 Rm
Rs:
Rate per Rm
(A+B+C+D)/20.0
Rs:

2739.80
23.155587
22332.94
1116.60

IRR-TAW-3-2 Providing and fixing 25 mm diameter steel rock bolts with resin bond cement capsule
anchorage including drilling 35 mm dia holes, inserting grout capsule, driving bolt,fixing 10 mm
thick plate washers and nuts and tightening the same by torque wrench after hardening of
cement grout, cost of all materials, machinery, labour, ventilation, lighting, drainage and other
ancillary operations etc., complete with lead upto 1 km and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
7
8

UNIT :

Particulars

Unit

Rein.Steel with 5 % wastage


Steel plate for washers
Resin bond cement grout capsule
M S Nuts for bolts
Use rate of drill rod
Reconditioning charges @
Use rate of air hose 4 Nos
Use rate of water hose 4 Nos
Sundries(gas for cutting etc)
Total cost of Materials

kg
kg
Nos.
kg
Rm
10%
Hour
Hour
LS

Quantity

20.00 Rm
Rate
in Rs.

86.91
65.94
2.00
4.00
20.00

46.50
46.00
46.00
90.00
41.69

6.00
6.00
3.00

5.47
6.84
41.00
Rs:

Amount
in Rs.
4041.49
3033.24
92.00
360.00
833.87
83.39
32.81
41.06
123.00
8640.86

117

Tunnel and Allied Works - Item Unit Rates 2014-15

B. MACHINERY:
Sl No
1
2
3
4
5
6

Description

Unit

Air compressor 15 cmm ( ele )


Fuel / Energy charges
Pump 10 hp ( ele )
Fuel / Energy charges
Jack hammer
Fuel / Energy charges
Pusher leg
Fuel / Energy charges
Drilling jumbo
Fuel / Energy charges
Sundries ( lathe, etc )
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

C. LABOUR:
Sl No

Description

1
2
3
4
5
6
7
8
9
10

Crew for Air compressor


Crew for pump
Crew for Jack hammer
Crew for Drilling jumbo
Fitter
Gas cutter
Turner
Khalasi ( 2 x 0.5 )
Hammerman
mazdoor
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Unit
Hour
Hour
Hour
Hour
Day
Day
Day
Day
Day
Day

Quantity
1.50
1.50
1.00
1.00
6.00
6.00
6.00
6.00
4.00
4.00
3.00

Quantity
1.50
1.00
6.00
4.00
0.50
1.00
1.00
1.00
0.50
2.00

Rate
in Rs.
138.80
951.20
6.70
76.10
19.80
0.00
12.70
0.00
368.40
46.00
41.00
Rs:

Amount
in Rs.
208.20
1426.80
6.70
76.10
118.80
0.00
76.20
0.00
1473.60
184.00
123.00
3693.40

Rate
in Rs.
151.80
72.10
284.70
151.80
345.00
385.00
440.00
385.00
345.00
295.00
Rs:

Amount
in Rs.
227.70
72.10
1708.20
607.20
172.50
385.00
440.00
385.00
172.50
590.00
4760.20

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

8640.86
3693.40
4760.20
17094.46
170.94
769.25
273.51
427.36
18735.53

238.00
0.14 33.30
271.30

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Add for Air and Water line @
Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @

1.00%
4.50%
1.60%
2.50%
Total

D.Add for contractor's profit and overheads on (A+B+C+other


14%
Rs:
percentages)
Lead Charges for 1Km for Steel (including Loading
and Unloading Charges)
0.15
tonne @ 145.6 Rs./Tonne
Total cost for
20.00 Rm
Rs:
Rate per Rm
(A+B+C+D)/20.0
Rs:

2622.97
22.255506
21380.75
1069.00

IRR-TAW-3-3 Providing, fabricating and fixing in position permanent structural steel supports as per details
including cost of all materials, machinery, labour, cutting, bending, welding, grinding, lighting,
ventilation, drainage and all other ancillary operations etc., complete with initial lead upto
1 km and all lifts.

Data

RATE ANALYSIS

UNIT :

1.00 tonne

A. MATERIALS:

118

Tunnel and Allied Works - Item Unit Rates 2014-15

Sl No

Particulars

Unit

1
2
3
4

Structural steel beams


Structural steel plates
Steel bars for tie rods & anchors
For cutting sections:
Oxygen gas @ 2.4 cum / t
Acetylene gas @ 0.8 cum / t
For welding sections:
Electrodes 4 x 300 mm @ 125 Nos / t
For field connections:
M.S.Bolts / Nuts & Washers
Sundries
Total cost of Materials

kg
kg
kg

5
6
7

B. MACHINERY:
Sl No
1
2
3
4

760.00
115.00
150.00

45.00
46.00
46.50

Amount
in Rs.
34200.00
5290.00
6975.00

cum
cum

2.40
0.80

52.00
320.00

124.80
256.00

Nos.

125.00

11.00

1375.00

kg
LS

50.00
5.00

90.00
41.00
Rs:

4500.00
205.00
52925.80

42.60
114.10
16.00
91.30
368.40
46.00
41.00
Rs:

Amount
in Rs.
340.80
912.80
256.00
1460.80
4420.80
552.00
1230.00
9173.20

Amount
in Rs.
1821.60
911.20

Description

Unit

Bending machine
Fuel / Energy charges
Welding set
Fuel / Energy charges
Drilling Jumbo
Fuel / Energy charges
Sundries ( lathe / drilling / grinder )
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
LS

C. LABOUR:
Sl No

Description

1
2
3

Crew for Drilling Jumbo


Crew fir Bending machine
For cutting & preparing sections:
Structural steel Marker
Gas cutter
Fitter
Turner / Driller
Khalasi
Helper fabrication
4
For welding sections:
Welder
Helper fabrication
Khalasi
5
For erection of supports:
Foreman
Structural steel Erector
Helper erector
Khalasi
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Unit

Quantity

Quantity

Rate
in Rs.

Rate
in Rs.

8.00
8.00
16.00
16.00
12.00
12.00
30.00

Quantity

Hour
Hour

12.00
8.00

Rate
in Rs.
151.80
113.90

Day
Day
Day
Day
Day
Day

1.00
2.00
2.00
3.00
2.00
4.00

440.00
385.00
385.00
440.00
385.00
345.00

440.00
770.00
770.00
1320.00
770.00
1380.00

Day
Day
Day

2.00
2.00
2.00

385.00
345.00
385.00

770.00
690.00
770.00

Day
Day
Day
Day

1.00
2.00
2.00
4.00

440.00
440.00
345.00
385.00
Rs:

440.00
880.00
690.00
1540.00
13962.80

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

52925.80
9173.20
13962.80
76061.80
760.62
3422.78
1216.99
1901.55
83363.73

Rs:

11670.92

13962.80
0.14 1954.80
15917.60

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Add for Air and Water line @
Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @

1.00%
4.50%
1.60%
2.50%
Total

D.Add for contractor's profit and overheads on (A+B+C+other


percentages)
Lead Charges for 1Km for Steel (including Loading
and Unloading Charges)
1.03
Total cost for

14%
tonne @
1.00 tonne

145.6 Rs./Tonne
Rs:

149.24
95183.90

119

Tunnel and Allied Works - Item Unit Rates 2014-15

Rate per tonne

(A+B+C+D)/1.0

Rs:

95183.90

IRR-TAW-3-4 Providing, fabricating and fixing in position temperary structural steel supports as per details
and dismantling the same before concreting including cost of all materials, machinery, labour,
cutting, bending, welding, grinding, ventilation, lighting, drainage and all other ancillary
operations etc.,complete with initial lead upto 1 km and all lifts.

DATA

RATE ANALYSIS
A. MATERIALS (for 20 uses):
Sl No
Particulars
1
2
3
4

Structural steel beams


Structural steel plates
Tie rods & anchors
For cutting sections:
Oxygen gas @ 2.40 cum / t
Acetylene @ 0.8 cum / t
5
For welding sections:
Electrodes @ 125 Nos / t
6
For field connections:
M.S.Bolts / Nuts / Washers
7
Sundries
Total cost of Materials for 20 uses of supports
Cost per use considering

B. MACHINERY (for fabrication):


Sl No
Description
1
2
3

Bending machine
Fuel / Energy charges
Welding set
Fuel / Energy charges
Sundries
Total hire charges of Machinery
Cost per use considering

B. MACHINERY (for erection and dismantling):


Sl No
Description
1
2

Drilling Jumbo
Fuel / Energy charges
Sundries
Total hire charges of Machinery

C. LABOUR ( for fabrication ):


Sl No
Description
1
2

Crew for Bending machine


For cutting & preparing sections:
Structural steel Marker
Gas cutter
Fitter
Turner / Driller
Khalasi
Helper fabrication
For welding sections:
Welder
Helper fabrication
Khalasi
Total cost of Labour
Cost per use considering

C. LABOUR ( for erection ):


Sl No
Description
1
2

Crew for Drilling jumbo


For erection of supports:

UNIT :
Unit

760.00
115.00
150.00

45.00
46.00
46.50

Amount
in Rs.
34200.00
5290.00
6975.00

cum
cum

2.40
0.80

52.00
320.00

124.80
256.00

Nos.

125.00

11.00

1375.00

kg
LS

50.00
20.00

90.00
41.00
Rs:
Rs:

4500.00
820.00
53540.80
2677.04

42.60
114.10
16.00
91.30
41.00
Rs:
Rs:

Amount
in Rs.
340.80
912.80
256.00
1460.80
1230.00
4200.40
210.02

Rate
in Rs.
368.40
46.00
41.00
Rs:

Amount
in Rs.
6631.20
828.00
410.00
7869.20

Amount
in Rs.
911.20

kg
kg
kg

Quantity

1.00 tonne
Rate
in Rs.

20 uses

Unit

Quantity

Hour
Hour
Hour
Hour
LS

8.00
8.00
16.00
16.00
30.00
20 uses

Unit

Quantity

Hour
Hour
LS

Unit

18.00
18.00
10.00

Quantity

Rate
in Rs.

Hour

8.00

Rate
in Rs.
113.90

Day
Day
Day
Day
Day
Day

1.00
2.00
2.00
3.00
2.00
4.00

440.00
385.00
385.00
440.00
385.00
345.00

440.00
770.00
770.00
1320.00
770.00
1380.00

Day
Day
Day

2.00
2.00
2.00

385.00
345.00
385.00
Rs:
Rs:

770.00
690.00
770.00
8591.20
429.56

Rate
in Rs.
151.80

Amount
in Rs.
1214.40

20 uses

Unit
Hour

Quantity
8.00

120

Tunnel and Allied Works - Item Unit Rates 2014-15

Foreman
Structural steel Erector
Helper erector
Khalasi
3
For dismantling of supports:
Foreman
Structural steel Erector
Helper erector
Khalasi
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Day
Day
Day
Day

1.00
2.00
2.00
4.00

440.00
440.00
345.00
385.00

440.00
880.00
690.00
1540.00

Day
Day
Day
Day

0.50
1.00
1.00
2.00

440.00
440.00
345.00
385.00
Rs:

220.00
440.00
345.00
770.00
6539.40

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

2677.04
210.02
7869.20
429.56
6539.40
17725.22
177.25
797.63
283.60
443.13
19426.84

Rs:

2719.76

145.6 Rs./Tonne
Rs:
Rs:

149.24
22295.84
22295.80

6969.00
0.14 975.70
7944.70

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery for fabrication
C. Hire charges of Machinery for erection and dismantling
D. Cost of Labour for fabrication
E. Cost of Labour for erection and dismantling
Total
Add for Air and Water line @
Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @

1.00%
4.50%
1.60%
2.50%
Total

D.Add for contractor's profit and overheads on (A+B+C+other


percentages)

14%

Lead Charges for 1Km for Steel (including Loading


and Unloading Charges)
1.03
tonne @
Total cost for
1.00 tonne
Rate per tonne
(A+B+C+D)/1.0

IRR-TAW-3-5 Providing and fixing hard variety cut jungle wood for lagging / blocking locations in tunnel
wherever required including cost of all materials, machinery, labour, fixing in position, lighting,
ventilation, drainage etc complete with all leads and lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

Particulars

Cut jungle wood


Sundries

UNIT :
Unit
cum
LS

Quantity
1.05
2.00

Total cost of Materials


B. MACHINERY:
Sl No
1

Description

Unit

Drilling jumbo
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour

C. LABOUR:
Sl No

Description

1
2
3

Crew for Drilling jumbo


Carpenter Cl II
mazdoor
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery

Unit
Hour
Day
Day

Quantity
2.00
2.00

Quantity
2.00
1.00
2.00

1.00 cum
Rate
in Rs.
23000.00
41.00
Rs:

Amount
in Rs.
24150.00
82.00
24232.00

Rate
in Rs.
368.40
46.00
Rs:

Amount
in Rs.
736.80
92.00
828.80

Rate
in Rs.
151.80
345.00
295.00
Rs:

Amount
in Rs.
303.60
345.00
590.00
1238.60

Rs:
Rs:

24232.00
828.80

1238.60
0.14 173.40
1412.00

121

Tunnel and Allied Works - Item Unit Rates 2014-15

C. Cost of Labour
Total
Add for Air and Water line @
Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @

1.00%
4.50%
1.60%
2.50%
Total

D.Add for contractor's profit and overheads on (A+B+C+other


percentages)
Total cost for
1.00 cum
Rate per cum
(A+B+C+D)/1.0

14%

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

1238.60
26299.40
262.99
1183.47
420.79
657.49
28824.14

Rs:
Rs:
Rs:

4035.38
32859.52
32859.50

IRR_TAW-4 MASONRY WORKS :


IRR-TAW-4-1 Providing and constructing un-coursed rubble stone masonry with approved stones from
tunnel excavated muck in cement mortar 1 : 6 proportion for backfilling over cuts / slips on
tunnel sides due to geological faults etc., including cost of all materials, machinery, labour,
cleaning,scaffolding, packing mortar, wedging stone chips, curing, ventilation, lighting, drainage
complete with lead upto 1 km and all lifts.
(cement content : 95 kg/cum of masonry, Rubble stones : 0.83 cum, Stone chips : 0.13 cum,
FA : 0.40 cum)
DATA

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4

Particulars

Cement
Rubble stones
Stone chips
Sand (Screened)

UNIT :
Unit
kg
cum
cum
cum

Add for scaffolding @


Total cost of Materials
B. MACHINERY:
Sl No
1

Description

Unit

10 hp pump ( ele )
Fuel / energy charges
Total hire charges of Machinery

Hour
Hour

C. LABOUR:
Sl No
1
2
3
4
5

Description

Crew for Pump


work inspector
Mason Class-I
Mason Class-II
mazdoor
for sorting out rubble in dump yard
for conveying rubble
for preparing mortar
for loading mortar pans
for laying & packing mortar
for washing rubble / finishing / curing
for conveying mortar / chips

Add for labour for scaffolding @


Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Unit

Quantity

10.00 cum
Rate
in Rs.

950.00
8.30
1.25
4.00
TOTAL
2.5%

Quantity

4.00
318.00
340.00
606.00
Rs:
Rs:
Rs:

Rate
in Rs.

1.00
1.00

Quantity

Amount
in Rs.
3800.00
2639.40
425.00
2424.00
9288.40
232.21
9520.61

6.70
76.10
Rs:

Amount
in Rs.
6.70
76.10
82.80

Rate
in Rs.

Hour
Day
Day
Day

1.00
1.00
1.00
2.00

72.10
370.00
385.00
345.00

Amount
in Rs.
72.10
370.00
385.00
690.00

Day
Day
Day
Day
Day
Day
Day

1.00
2.00
2.00
1.00
4.00
1.00
3.00
TOTAL
15.0%

295.00
295.00
295.00
295.00
295.00
295.00
295.00
Rs:
Rs:
Rs:

295.00
590.00
590.00
295.00
1180.00
295.00
885.00
5647.10
847.07
6494.17

Rs:
Rs:
Rs:
Rs:

9520.61
82.80
6494.17
16097.58

649.42
0.14 90.90
740.30

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total

122

Tunnel and Allied Works - Item Unit Rates 2014-15

Add for Air and Water line @


Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @

1.00%
4.50%
1.60%
2.50%

Rs:
Rs:
Rs:
Rs:
Rs:

160.98
724.39
257.56
402.44
17642.94

14%
Rs:
cum @
31.5 Rs./Cum
cum @
30.4 Rs./Cum

2470.01
126
290.32

Total
D.Add for contractor's profit and overheads on (A+B+C+other
percentages)
Lead Charges for 1 Km for FA
4.00
Lead Charges for 1 Km for Stones and Stone Chips 9.55
Lead Charges for 1Km for Cement (including
Loading and Unloading Charges)
Total cost for
Rate per cum

0.95

tonne @
10.00 cum
(A+B+C+D)/10.0

124.6 Rs./Tonne
Rs:
Rs:

118.37
20647.64
2064.80

IRR_TAW-5 REINFORCEMENT & CONCRETE WORKS :


IRR-TAW-5-1 Providing, fabricating and placing in position reinforcement steel for tunnel RCC works
including cleaning, straightening, cutting, bending, hooking, lapping / welding joints wherever
required, tying with 1.25 mm dia.soft annealed steel wire, including cost of all materials, labour,
machinery, ventilation, lighting, drainage etc.,complete with initial lead upto 1 km and all lifts.

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3

UNIT :

Particulars

Unit

Rein.Steel with 5 % wastage


Binding wire 1.25 mm dia
Sundries ( chairs / spacers etc )
Total cost of Materials

tonne
kg
LS

B. MACHINERY:
Sl No

Description

Unit

Nil

Quantity
1.05
13.50
5.00

Quantity

1.00 tonne
Rate
in Rs.
46500.00
70.00
41.00
Rs:

Amount
in Rs.
48825.00
945.00
205.00
49975.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
450.00
295.00
Rs:

Amount
in Rs.
4050.00
4425.00
8475.00

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

49975.00
0.00
8475.00
58450.00
584.50
2630.25
935.20
1461.25
64061.20

0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No
1
2

Description

Bar bender
mazdoor

Unit
Day
Day

Quantity
9.00
15.00

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

8475.00
0.14 1186.50
9661.50

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Add for Air and Water line @
Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @

1.00%
4.50%
1.60%
2.50%
Total

D.Add for contractor's profit and overheads on (A+B+C+other


14%
Rs:
percentages)
Lead Charges for 1Km for Steel (including Loading
and Unloading Charges)
1.05
tonne @ 145.6 Rs./Tonne
Total cost for
1.00 tonne
Rs:
Rate per tonne
(A+B+C+D)/1.0
Rs:

8968.57
152.88
73182.65
73182.60

IRR-TAW-5-2 Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than

123

Tunnel and Allied Works - Item Unit Rates 2014-15

10 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard,


graded aggregates crushed from tunnel excavated muck for filling and levelling over-cuts
in bed due to geological faults etc., including cost of all materials, machinery, labour, cleaning
bed, batching, mixing, conveying and laying, levelling, compacting, finishing, curing, lighting,
ventilation, drainage etc., complete with initial lead upto 1 km and all lifts. ( Cement
content : 220 kg / cum, CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum,
Superplasticizer 0.4% by wt. of cement)
DATA

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

3
4
5

Particulars

Unit

Cement for mix


Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened )
Super Plasticizer
Sundries
Total cost of Materials

kg
cum
cum
cum
cum
kg
LS

B. MACHINERY:
Sl No
1
2
3
4
5

UNIT :

Description

Unit

Batching plant 2 x 1 cum


Fuel / Energy charges
Agitator car 2 cum
Fuel / Energy charges
10 hp pump ( ele )
Fuel / Energy charges
Needle vibrator 40 mm dia
Fuel / Energy charges
Sundries
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

C. LABOUR:
Sl No

Description

1
2
3
4
5
6
7

Crew for Batching plant


Crew for Agitator car
Crew for Pump
Crew for Needle vibrator
Mason Class-I
work inspector
mazdoor
for cleaning bed
for loading material bin ( Cement )
for miscellaneous works at BP
for laying concrete
for conveying laying concrete
for cleaning bed
for washing CA / curing
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Unit

Quantity
6160.00
12.60
7.56
5.04
11.20
24.64
2.00

Quantity
8.00
8.00
16.00
16.00
8.00
8.00
8.00
8.00
2.00

Quantity

Hour
Hour
Hour
Hour
Day
Day

8.00
16.00
8.00
8.00
1.00
1.00

Day
Day
Day
Day
Day
Day
Day

2.00
3.00
2.00
7.00
14.00
2.00
2.00

28.00 cum
Rate
in Rs.
4.00
1145.00
1210.00
875.00
462.00
80.00
41.00
Rs:

Amount
in Rs.
24640.00
14427.00
9147.60
4410.00
5174.40
1971.20
82.00
59852.20

Rate
in Rs.
405.40
342.40
758.40
937.80
6.70
76.10
8.00
7.60
41.00
Rs:

Amount
in Rs.
3243.20
2739.20
12134.40
15004.80
53.60
608.80
64.00
60.80
82.00
33990.80

Rate
in Rs.
293.80
244.90
72.10
136.60
385.00
370.00

Amount
in Rs.
2350.40
3918.40
576.80
1092.80
385.00
370.00

295.00
295.00
295.00
295.00
295.00
295.00
295.00
Rs:

590.00
885.00
590.00
2065.00
4130.00
590.00
590.00
18133.40

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

59852.20
33990.80
18133.40
111976.40
1119.76
5038.94
1791.62
2799.41
122726.13

Rs:

17181.66

647.60
0.14 90.70
738.30

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Add for Air and Water line @
Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @

1.00%
4.50%
1.60%
2.50%
Total

D.Add for contractor's profit and overheads on (A+B+C+other


percentages)

14%

124

Tunnel and Allied Works - Item Unit Rates 2014-15

Lead Charges for 1 Km for FA


Lead Charges for 1 Km for CA

11.20
25.20

Lead Charges for 1Km for Cement (including


Loading and Unloading Charges)
Total cost for
Rate per cum

cum @
cum @

6.16

tonne @
28.00 cum
(A+B+C+D)/28.0

31.5 Rs./Cum
30.4 Rs./Cum
124.6 Rs./Tonne
Rs:
Rs:

352.8
766.08
767.536
141794.21
5064.10

IRR-TAW-5-3 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than
20 N / sqmm ) grade cement concrete using 40 mm and down size approved clean, hard,
graded aggregates crushed from tunnel muck for kerb and bed lining including cost of all
materials, machinery, labour, formwork, batching, mixing, conveying upto placing point in
agitator cars, placing in position, levelling, vibrating, finishing, curing, ventilation, lighting,
drainage and all other ancillary operations etc., complete with lead upto 1 km and all lifts.
( Cement content 330 kg / cum for use of super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3

4
5
6

1
2
3
4
5

6
7
8
9

Unit
kg
kg
cum
cum
cum
cum
kg
sqm
LS

Description

Batching plant 2 x 1.00 cum


Fuel / Energy charges
Agitator car 2 cum ( 2 Nos )
Fuel / Energy charges
Needle Vibrator
Fuel / Energy charges
Pump 10 hp ( Ele )
Fuel / Energy charges
Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3
4
5

Particulars

Cement 43 Gr
Cement for incidentals @ 1 kg / cum
Fine aggregate (Un-Screened )
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10-4.75 mm
Super plasticiser
Use rate of shuttering for kerb / bed
Sundries
Total cost of Materials

B. MACHINERY:
Sl No

UNIT :

Crew for Batching plant


Crew for Agitator car
Crew for vibrator
Crew for pump
For scaling & cleaning bed
Hammerman
mazdoor
For loading cement to BP bin
mazdoor
For miscellaneous work at BP
mazdoor
For wetting C.A & curing
mazdoor
Laying concrete for kerb/ invert
Mason Cl I
Mason Cl II
mazdoor
work inspector

9240.00
28.00
11.20
12.60
7.56
5.04
36.96
28.00
2.00

Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Description

Quantity

Quantity
8.00
8.00
16.00
16.00
8.00
8.00
8.00
8.00
5.00

Unit

Quantity

28.00 cum
Rate
in Rs.
4.00
4.00
462.00
1145.00
1210.00
875.00
80.00
174.56
41.00
Rs:

Amount
in Rs.
36960.00
112.00
5174.40
14427.00
9147.60
4410.00
2956.80
4887.79
82.00
78157.59

Rate
in Rs.
405.40
342.40
758.40
937.80
8.00
7.60
6.70
76.10
41.00
Rs:

Amount
in Rs.
3243.20
2739.20
12134.40
15004.80
64.00
60.80
53.60
608.80
205.00
34113.80

Amount
in Rs.
2350.40
3918.40
1092.80
576.80

Hour
Hour
Hour
Hour

8.00
16.00
8.00
8.00

Rate
in Rs.
293.80
244.90
136.60
72.10

Day
Day

2.00
6.00

345.00
295.00

690.00
1770.00

Day

3.00

295.00

885.00

Day

2.00

295.00

590.00

Day

2.00

295.00

590.00

Day
Day
Day
Day

2.00
2.00
21.00
1.00

385.00
345.00
295.00
370.00

770.00
690.00
6195.00
370.00

125

Tunnel and Allied Works - Item Unit Rates 2014-15

10 Labour charges for shuttering


sqm
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

28.00

75.30
Rs:

2108.40
22596.80

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

78157.59
34113.80
22596.80
134868.19
1348.68
6069.07
2157.89
3371.70
147815.54

807.00
0.14 113.00
920.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Add for Air and Water line @
Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @

1.00%
4.50%
1.60%
2.50%
Total

D.Add for contractor's profit and overheads on (A+B+C+other


14%
Rs:
percentages)
Lead Charges for 1 Km for FA
11.20
cum @
31.5 Rs./Cum
Lead Charges for 1 Km for CA
25.20
cum @
30.4 Rs./Cum
Lead Charges for 1Km for Cement (including
Loading and Unloading Charges)
9.27
tonne @ 124.6 Rs./Tonne
Total cost for
28.00 cum
Rs:
Rate per cum
(A+B+C+D)/28.0
Rs:

20694.18
352.8
766.08
1154.7928
170783.38
6099.40

IRR-TAW-5-4 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than
20 N / sqmm ) grade cement concrete using 40 mm and down size approved clean, hard,
graded aggregates crushed from tunnel muck for sides and arch lining including cost of all
materials, machinery, labour, formwork, batching, mixing, conveying upto placing point in
agitator cars, placing in position, levelling, vibrating, finishing, curing, ventilation, lighting,
drainage and all other ancillary operations etc., complete with lead upto 1 km and all lifts.
( Cement content 330 kg / cum for use of super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3

4
5
6
7

Particulars

Cement 43 Gr
Cement for incidentals @ 1 kg / cum
Fine aggregate (Un-Screened )
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10-4.75 mm
Super plasticiser
Use rate of end shuttering
Use rate of steel gantry
Sundries ( placer pipe etc )
Total cost of Materials

B. MACHINERY:
Sl No

UNIT :
Unit
kg
kg
cum
cum
cum
cum
kg
sqm
sqm
LS

Description

Air compressor ( Ele ) 8.5 cmm


Fuel / Energy charges @ 75 % load

15840.00
48.00
19.20
21.60
12.96
8.64
63.36
6.00
100.00
5.00

Unit
Hour
Hour

Quantity

Quantity
16.00
12.00

48.00 cum
Rate
in Rs.
4.00
4.00
462.00
1145.00
1210.00
875.00
80.00
174.56
75.30
41.00
Rs:

Amount
in Rs.
63360.00
192.00
8870.40
24732.00
15681.60
7560.00
5068.80
1047.38
7530.00
205.00
134247.18

Rate
in Rs.
170.80
428.00

Amount
in Rs.
2732.80
5136.00

126

Tunnel and Allied Works - Item Unit Rates 2014-15

2
3
4
5
6
7

Batching plant 2 x 1.00 cum


Fuel / Energy charges
Agitator car 2 cum ( 2 Nos )
Fuel / Energy charges
Concrete placer pump
Fuel / Energy charges
Needle Vibrator / Shutter vibrator
Fuel / Energy charges
Pump 10 hp ( Ele )
Fuel / Energy charges
Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Description

12.00
12.00
32.00
32.00
16.00
16.00
8.00
8.00
8.00
8.00
5.00

Unit

1
2
3
4
5
6
7

Crew charges for Air compressor


Hour
Crew charges for Batching plant
Hour
Crew charges for Agitator car
Hour
Crew charges for placer pump
Hour
Crew charges for vibrator
Hour
Crew charges for Pump
Hour
For scaling & cleaning
Stone chiseller Cl II
Day
mazdoor
Day
8
For dismantling / Laying track
Surveyer
Day
Fitter shuttering
Day
Helper shuttering 2 x 0.5
Day
Khalasi 6 x 0.5
Day
mazdoor 2 x 0.5
Day
9
For Moving / Positioning gantry
Surveyer
Day
Foreman
Day
Fitter shuttering
Day
Helper shuttering 2 x 0.5
Day
Khalasi 6 x 0.5
Day
mazdoor 2 x 0.5
Day
10
For loading cement to BP bin
mazdoor
Day
11
For miscellaneous works of BP
mazdoor
Day
12
For Erection/Dismantling bulk head
sqm
13
For Laying concrete by placer
Masom Cl I
Day
mazdoor
Day
work inspector
Day
14
For wetting C.A / Curing etc
mazdoor
Day
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

405.40
342.40
758.40
937.80
#REF!
#REF!
8.00
7.60
6.70
76.10
41.00
Rs:

4864.80
4108.80
24268.80
30009.60
#REF!
#REF!
64.00
60.80
53.60
608.80
205.00
#REF!

16.00
16.00
32.00
16.00
8.00
8.00

Rate
in Rs.
142.40
293.80
244.90
#REF!
136.60
72.10

Amount
in Rs.
2278.40
4700.80
7836.80
#REF!
1092.80
576.80

0.50
1.00

345.00
295.00

172.50
295.00

0.50
0.50
1.00
3.00
1.00

550.00
345.00
345.00
385.00
295.00

275.00
172.50
345.00
1155.00
295.00

0.50
0.50
0.50
1.00
3.00
1.00

550.00
440.00
345.00
345.00
385.00
295.00

275.00
220.00
172.50
345.00
1155.00
295.00

5.00

295.00

1475.00

2.00
6.00

295.00
75.30

590.00
451.80

3.00
9.00
3.00

385.00
295.00
370.00

1155.00
2655.00
1110.00

3.00

295.00
Rs:

885.00
#REF!

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

134247.18
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

14%
Rs:
cum @
31.5 Rs./Cum
cum @
30.4 Rs./Cum

#REF!
604.8
1313.28

Quantity

#REF!
0.14 #REF!
#REF!

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Add for Air and Water line @
Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @

1.00%
4.50%
1.60%
2.50%
Total

D.Add for contractor's profit and overheads on (A+B+C+other


percentages)
19.20
Lead Charges for 1 Km for FA
Lead Charges for 1 Km for CA
43.20

127

Tunnel and Allied Works - Item Unit Rates 2014-15

Lead Charges for 1Km for Cement (including


Loading and Unloading Charges)
Total cost for
Rate per cum
IRR-TAW-6

15.89

tonne @
48.00 cum
(A+B+C+D)/48.0

124.6 Rs./Tonne
Rs:
Rs:

1979.6448
#REF!
#REF!

DRILLING & GROUTING WORKS :

IRR-TAW-6-1 Drilling 32 mm diameter grout holes in concrete / rock by percussion drilling using jack
hammer or stooper drills as directed to specified depth for consolidation / contact grouting
including cost of all materials, machinery, labour, cleaning holes, ventilation, lighting, drainage
and all other ancillary operations etc., complete.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4

1
2
3
4
5
6

Particulars

Use rate of drill rod


Reconditioning charges @
Use rate of air hose 4 Nos
Use rate of water hose 4 Nos
Sundries
Total cost of Materials

B. MACHINERY:
Sl No

Unit

Quantity

Rm

100.00 Rm
Rate
in Rs.

100.00

41.69

32.00
32.00
3.00

5.47
6.84
41.00
Rs:

Amount
in Rs.
4169.33
416.93
175.00
219.00
123.00
5103.27

Rate
in Rs.
138.80
951.20
6.70
76.10
19.80
0.00
12.70
0.00
368.40
46.00
41.00
Rs:

Amount
in Rs.
1110.40
7609.60
26.80
304.40
633.60
0.00
406.40
0.00
2947.20
368.00
205.00
13611.40

Rate
in Rs.
151.80
72.10
284.70
151.80
295.00
Rs:

Amount
in Rs.
1214.40
288.40
9110.40
1214.40
590.00
12417.60

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

5103.27
13611.40
12417.60
31132.27
311.32
1400.95
498.12
778.31
34120.96

Rs:
Rs:
Rs:

4776.93
38897.90
389.00

10%
Hour
Hour
LS

Description

Air compressor 15 cmm ( ele )


Fuel / Energy charges
Pump 10 hp ( ele )
Fuel / Energy charges
Jack hammer
Fuel / Energy charges
Pusher leg
Fuel / Energy charges
Drilling jumbo
Fuel / Energy charges
Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No

UNIT :

Unit

Quantity

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Description

Crew charges for Air compressor


Hour
Crew charges for Pump
Hour
Crew charges for Jack Hammer
Hour
Crew charges for Drilling Jumbo
Hour
mazdoor
Day
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

8.00
8.00
4.00
4.00
32.00
32.00
32.00
32.00
8.00
8.00
5.00

Unit

Quantity

1
2
3
4
5

8.00
4.00
32.00
8.00
2.00
124.20
0.14 17.40
141.60

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Add for Air and Water line @
Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @

1.00%
4.50%
1.60%
2.50%
Total

D.Add for contractor's profit and overheads on (A+B+C+other


percentages)
Total cost for
100.00 Rm
Rate per Rm
(A+B+C+D)/100.0

14%

128

Tunnel and Allied Works - Item Unit Rates 2014-15

IRR-TAW-6-2 Grouting cement slurry in grout holes under specified pressure for consolidation / contact
grouting including cost of all materials, machinery, labour, redrilling wherever necessary,
ventilation,lighting, drainage and other ancillary operations etc., complete with lead upto 1 km
and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4

1
2
3
4

Particulars

Cement
Use rate of grouting hose 50 m
Use rate of water hose 50 m
Sundries
Total cost of Materials

B. MACHINERY:
Sl No

Unit
tonne
Hour
Hour
LS

Description

Grouting machine
Fuel / Energy charges
Pump 10 hp ( ele )
Fuel / Energy charges
Drilling jumbo
Fuel / Energy charges
Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No

UNIT :

Unit
Hour
Hour
Hour
Hour
Hour
Hour
LS

Description

Quantity
1.50
8.00
8.00
2.00

Quantity

1.50 tonne
Rate
in Rs.
4000.00
10.94
13.69
41.00
Rs:

Amount
in Rs.
6000.00
87.50
109.50
82.00
6279.00

Rate
in Rs.
24.90
38.00
6.70
76.10
368.40
46.00
41.00
Rs:

Amount
in Rs.
199.20
304.00
13.40
152.20
736.80
92.00
82.00
1579.60

Rate
in Rs.
227.80
72.10
151.80
295.00
Rs:

Amount
in Rs.
1822.40
144.20
303.60
590.00
2860.20

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

6279.00
1579.60
2860.20
10718.80
107.19
482.35
171.50
267.97
11747.80

Rs:

1644.69

124.6 Rs./Tonne
Rs:
Rs:

186.9
13579.40
9052.90

8.00
8.00
2.00
2.00
2.00
2.00
2.00

Unit

1
2
3
4

Crew for Grout pump


Hour
Crew for pump
Hour
Crew for Drilling jumbo
Hour
mazdoor
Day
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Quantity
8.00
2.00
2.00
2.00
1906.80
0.14 267.00
2173.80

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Add for Air and Water line @
Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @

1.00%
4.50%
1.60%
2.50%
Total

D.Add for contractor's profit and overheads on (A+B+C+other


percentages)
Lead Charges for 1Km for Cement (including
Loading and Unloading Charges)
Total cost for
Rate per tonne

14%

1.50

tonne @
1.50 tonne
(A+B+C+D)/1.50

IRR-TAW-6-3 Drilling 75 mm diameter drainage holes vertical or inclined in rock / concrete in tunnel by
percussion drilling using waggon drill or other suitable drilling equipment including cost of all
materials, machinery, labour, ventilation, lighting, drainage etc., complete.

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No
1

UNIT :

Particulars

Use rate of cross bit 75 mm dia

Unit
Rm

Quantity
120.00

120.00 Rm
Rate
in Rs.
125.00

Amount
in Rs.
15000.00

129

Tunnel and Allied Works - Item Unit Rates 2014-15

2
3
4

Use rate of air hose 20 m


Hour
Use rate of water hose 20 m
Hour
Use rate of extension rods
Rm
Total cost of Materials

B. MACHINERY:
Sl No
1
2
3
4

Description

Waggon drill
Fuel / Energy charges
Air compressor 15 cmm ( ele )
Fuel / Energy charges
Pump 10 hp ( ele )
Fuel / Energy charges
Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No

16.00
16.00
120.00

Unit

Quantity

Hour
Hour
Hour
Hour
Hour
Hour
LS

Description

Crew for Waggon drill


Hour
Crew for Air compressor
Hour
Crew for Pump
Hour
mazdoor
Day
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

16.00
16.00
8.00
8.00
6.00
6.00
2.00

Unit

Quantity

1
2
3
4

16.00
8.00
6.00
2.00

4.38
5.48
8.48
Rs:

70.00
87.60
1017.60
16175.20

Rate
in Rs.
188.50
0.00
138.80
951.20
6.70
76.10
41.00
Rs:

Amount
in Rs.
3016.00
0.00
1110.40
7609.60
40.20
456.60
82.00
12314.80

Rate
in Rs.
244.90
151.80
72.10
295.00
Rs:

Amount
in Rs.
3918.40
1214.40
432.60
590.00
6155.40

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

16175.20
12314.80
6155.40
34645.40
346.45
1559.04
554.33
866.14
37971.36

Rs:
Rs:
Rs:

5315.99
43287.35
360.70

51.30
0.14 7.20
58.50

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Add for Air and Water line @
Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @

1.00%
4.50%
1.60%
2.50%
Total

D.Add for contractor's profit and overheads on (A+B+C+other


percentages)
Total cost for
120.00 Rm
Rate per Rm
(A+B+C+D)/120.0

14%

130

Canal and Allied Works - Item Unit Rates 2014-15

Chapter III
CANAL AND ALLIED WORKS - Standard Data

(WLL BE WITH E-N-C & TO INCORPORATE CHANGES YEARLY/ AS NEEDED)


FOR THE YEAR : 2014-15
Index- code
IRR-CAW

CANAL AND ALLIED WORKS - DATA RATES

Directions to add Seigniorage Charges and Additional Lead Charges


Seigniorage Charges:
1. The unit rate for work item in the Standard Data is exclusive of Seigniorage Charges wherever applicable.
2. The appropriate Seigniorage Charges for relevant materials are to be added to the Unit rate of work item while preparing
the estimate. (i.e., to the data itself)
3. The Provision towards Contractor's Profit and Overhead charges should not be operated on the Seigniorage Charges
while adding Seigniorage Charges to the data in the estimate
Additional Lead and Lift Charges:
1. Unless otherwise specified the basic rates are inclusive of all lifts.
2. For concrete, masonry and reinforcement items wherever initial lead of 1km is considered in the basic rate, the additional lead
charges are to be added as follows:
Additional lead charges for Cement, Steel, sand, coarse aggregate, stones and stone chips shall be worked out for total
lead involved and 1 km lead charges included in basic rate shall be deducted from total lead charges. No loading and
unloading charges shall be allowed for any item.
In case of Cement and Steel, Loading and unloading charges are already added in the work item while arriving the unit rate
and hence should not be added again
Example:
Total lead for sand from approved sand quarry :
15 Km
Initial lead included in the basic rate in the SR :
1 Km
Additional lead charges :
Lead charges for 5 km
Rs.
84.10
Lead charges for next 10 km
Rs.
126
Total lead charges for 15 km /cum
Rs.
210.10
Less 1 km initial lead charges /cum
Rs.
31.50 (-)
Net additional lead charges / cum
Rs.
178.60

3. The Leads for Steel and Cement shall be from the nearest market place to the Project area
4. For earth/rockfill embankments wherever initial lead of 1km is considered in the basic rate, the additional lead
charges are to be added as follows:
Additional lead charges for Earth, Murrum etc., shall be worked out for total lead involved and 1 km lead charges included
in basic rate shall be deducted from total lead charges. No loading and unloading charges shall be allowed for any item.
(same as above)
Example:
Total lead for earth from approved borrow area :
15 Km
Initial lead included in the basic rate in the SR :
1 Km
Additional lead charges :
Lead charges for 5 km
Rs.
84.10
Lead charges for next 10 km
Rs.
126
Total lead charges for 15 km /cum
Rs.
210.10
Less 1 km initial lead charges /cum
Rs.
31.50 (-)
Net additional lead charges / cum
Rs.
178.60
5. The initial lead up to 50 m as mentioned in some standard data items is meant for manual lead within the working area. For
conveyance of materials, the lead required from quarry/Borrow area/ Dump Area to worksite shall be added to the data without
deducting the 50 m initial lead charges
CAW-Work Items
IRR-CAW-1

EXCAVATION WORKS :

IRR-CAW-1-1

Excavation in all kinds of soil including boulders upto 0.3 m diameter for canal, seating of
embankment, filter drains / catch water drains etc., including dressing bed and sides to
required level and profile, cost of all materials, machinery, labour, placing the excavated soil
neatly in dump area or for the formation of service road / embankment as directed etc.,
complete with initial lead upto 1 km and all lifts.

131

Canal and Allied Works - Item Unit Rates 2014-15

RATE ANALYSIS

DATA:
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Quantity

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
1706.60
937.80
446.70
322.20
Rs:

Amount
in Rs.
13652.80
7502.40
21441.60
15465.60
58062.40

Rate
in Rs.
204.10
153.10
370.00
295.00
Rs:

Amount
in Rs.
1632.80
7348.80
370.00
8850.00
18201.60

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total

Rs:
Rs:
Rs:
Rs:

0.00
58062.40
18201.60
76264.00

D. Add for contractor's profit and overheads on (A+B+C)


14%
Total cost for
925.00 cum
cum
(A+B+C+D)/925
Rate per

Rs:
Rs:
Rs.

10676.96
86940.96
94.00

NIL

0.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No
1
2

Description

Unit

Shovel 0.85 cum capacity


Fuel / Energy charges
Tippers 5 cum capacity 6 Nos
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour

Description

Unit

C. LABOUR:
Sl No
1
2
3
4

Crew for Shovel


Crew for Tipper
work inspector
mazdoor

Hour
Hour
Day
Day

Quantity
8.00
8.00
48.00
48.00

Quantity
8.00
48.00
1.00
30.00

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

IRR-CAW-1-2

925.00 cum

19.70
0.14 2.80
22.50

Excavation in all kinds of soil including boulders upto 0.30 m dia for field channels, seating
of embankment for field channels etc., including dressing of bed and sides to required profile,
cost of all materials, machinery, labour, placing the excavated stuff for formation of service
road / embankment as directed etc., complete with lead upto 10 m and lift upto 3 m.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

NIL

Quantity

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
8.00 1003.10
8.00 511.50
Rs:

Amount
in Rs.
8024.80
4092.00
12116.80

0.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No
1

C. LABOUR:
Sl No

Description

Unit

Shovel 0.50 cum capacity


Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour

Description

Unit

440.00 cum

Quantity

Quantity

Rate
in Rs.

Amount
in Rs.

132

Canal and Allied Works - Item Unit Rates 2014-15

1
2
3

Crew for Shovel


work inspector
mazdoor

Hour
Day
Day

8.00
1.00
17.00

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

1632.80
370.00
5015.00
7017.80

Rs:
Rs:
Rs:
Rs:

0.00
12116.80
7017.80
19134.60

Rs:
Rs:
Rs.

2678.84
21813.44
49.60

15.90
0.14 2.20
18.10

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
440.00 cum
cum
(A+B+C+D)/440
Rate per

IRR-CAW-1-3

204.10
370.00
295.00
Rs:

Excavation in ordinary rock (including HDR) without blasting including boulders above 0.30 m upto 0.6 m dia. for
canals, seating of embankment, filter drain / catch water drains etc., including dressing of
bed and sides to required level and profile, cost of all materials, machinery, labour, placing the
excavated soft rock neatly in dump area or for formation of service road as directed etc.,
complete with lead upto 1 km and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Quantity

NIL

0.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No
1
2

C. LABOUR:
Sl No
1
2
3
4
5

Description

Unit

Shovel 0.85 cum capacity


Fuel / Energy charges
Tippers 5 cum capacity 5 Nos
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour

Description

Unit

Crew for Shovel


Crew for Tipper
work inspector
Crowbarman
mazdoor

Hour
Hour
Day
Day
Day

Quantity
8.00
8.00
40.00
40.00

Quantity
8.00
40.00
1.00
11.00
22.00

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

630.00 cum
Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
1706.60
937.80
446.70
322.20
Rs:

Amount
in Rs.
13652.80
7502.40
17868.00
12888.00
51911.20

Rate
in Rs.
204.10
153.10
370.00
345.00
295.00
Rs:

Amount
in Rs.
1632.80
6124.00
370.00
3795.00
6490.00
18411.80

Rs:
Rs:
Rs:
Rs:

0.00
51911.20
18411.80
70323.00

Rs:
Rs:
Rs.

9845.22
80168.22
127.30

29.20
0.14 4.10
33.30

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
630.00 cum
cum
(A+B+C+D)/630
Rate per

133

Canal and Allied Works - Item Unit Rates 2014-15

IRR-CAW-1-4

Excavation in ordinary rock (including HDR) without blasting including boulders above 0.3 m upto 0.60 m dia. for
field channels, seating of embankment for field channels etc., including dressing of bed and
sides to required profile, cost of all materials, machinery, labour, placing the excavated stuff
for formation of service road as directed etc.,complete with lead upto 10 m and lift upto 3 m.

RATE ANALYSIS

DATA:
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Quantity

NIL

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
8.00 1003.10
8.00 511.50
Rs:

Amount
in Rs.
8024.80
4092.00
12116.80

0.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No
1

Description

Unit

Shovel 0.50 cum capacity


Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour

Description

Unit

C. LABOUR:
Sl No
1
2
3
4

Crew for Shovel


work inspector
Crowbarman
mazdoor

Hour
Day
Day
Day

Quantity

Quantity
8.00
1.00
5.00
11.00

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

265.00 cum

Rate
in Rs.
204.10
370.00
345.00
295.00
Rs:

Amount
in Rs.
1632.80
370.00
1725.00
3245.00
6972.80

Rs:
Rs:
Rs:
Rs:

0.00
12116.80
6972.80
19089.60

Rs:
Rs:
Rs.

2672.54
21762.14
82.10

26.30
0.14 3.70
30.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
265.00 cum
cum
(A+B+C+D)/265
Rate per

IRR-CAW-1-5

Excavation in hard rock (including F&F rock) requiring blasting including boulders
above 0.6 m upto 1.2 m dia. for canals, seating of embankment, filter drain / catch water drains
etc., including dressing bed and sides to required level and profile, cost of all materials,
machinery, labour, placing the excavated rock in dump area or for formation of service
road as directed etc., complete with lead upto 1 km and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

Unit

Quantity

805.00 cum

Rm
10%
Hour

316.00

Use rate of drill rod 1.5 m length


Reconditioning charges @
Use rate of 50 m air hose 2 Nos

Rate
in Rs.
20.14

24.00

10.94

Amount
in Rs.
6364.24
636.42
262.50

3
4
5
6
7

Explosive small dia ( Kelvex-220 )


Ordinary detonators
Electric detonators
Fuse coil
Sundries

kg
Nos
Nos
Rm
LS

161.00
12.00
215.00
520.00
5.00

70.00
9.00
13.00
11.00
41.00

11270.00
108.00
2795.00
5720.00
205.00

particulars

UNIT :

134

Canal and Allied Works - Item Unit Rates 2014-15

Total cost of Materials


B. MACHINERY:
Sl No
1
2

3
4

C. LABOUR:
Sl No

Description

Unit

Quantity

Shovel 0.85 cum capacity


Fuel / Energy charges
Tippers 5 cum capacity 5 Nos.
Fuel / Energy charges

Hour
Hour
Hour
Hour

8.00
8.00
40.00
40.00

Air compressor 8.5 cmm ( diesel )


Fuel / Energy charges
Jack hammers 3 Nos.
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour

12.00
12.00
39.00
39.00

Description

Unit

Quantity

Crew for Shovel


Hour
8.00
Crew for Tipper
Hour
40.00
Crew for Air compressor
Hour
12.00
Crew for Jack hammer
Hour
39.00
work inspector
Day
1.00
Blaster
Day
1.00
Helper blaster
Day
1.00
Crowbarman
Day
16.00
Stone breaker
Day
16.00
mazdoor
Day
32.00
Total cost of Labour
labour component/unit qty
53.00
Add contractor's profit and overhead charges
0.14 7.40
labour component/unit qty (including contractor's profit)
60.40
1
2
3
4
5
6
7
8
9
10

Rs:

27361.16

Rate
in Rs.
1706.60
937.80
446.70
322.20

Amount
in Rs.
13652.80
7502.40
17868.00
12888.00

275.60
959.10
19.80
0.00
Rs:

3307.20
11509.20
772.20
0.00
67499.80

Rate
in Rs.
204.10
153.10
182.20
284.70
370.00
440.00
345.00
345.00
345.00
295.00
Rs:

Amount
in Rs.
1632.80
6124.00
2186.40
11103.30
370.00
440.00
345.00
5520.00
5520.00
9440.00
42681.50

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
805.00 cum
cum
(A+B+C+D)/805
Rate per

IRR-CAW-1-6
(a)

Note:

Rs:
27361.16
Rs:
67499.80
Rs:
42681.50
Rs: 137542.46
Rs:
19255.94
Rs: 156798.40
Rs.
194.80

Excavation in hard rock of all toughness by blasting including boulders above 1.2 m dia. for
canals, seating of embankment, filter drain / catch water drains etc., including levelling the bed
by removing all projections by hammering / chiselling, cost of all materials, machinery, labour,
placing the excavated rock neatly in approved dump area and levelling the same as directed
etc., complete with initial lead upto 1 km and all lifts.
i ) The rate under this item shall be adopted for canals designed for carrying capacity of less
than 15 cumecs or where the average depth of excavation in hard rock is less than 3 m.
ii ) The rate includes levelling canal bed by hammering / chiselling all rock projections wherever
required.

135

Canal and Allied Works - Item Unit Rates 2014-15

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
7

1
2
3

4
5

C. LABOUR:
Sl No
1
2
3
4
5
6
7
8
9
10
11

Unit

Quantity

68.00 cum

Use rate of drill rod 1.5 m length


Reconditioning charges @
Use rate of 50 m air hose 2 Nos.

Rm
10%
Hour

85.00

Rate
in Rs.
26.85

13.00

10.94

Amount
in Rs.
2282.53
228.25
142.19

Explosive small dia. (Kelvex-220 )


Ordinary detonators
Electric detonators
Fuse coil
Sundries
Total cost of Materials

kg
Nos
Nos
Rm
LS

21.20
4.00
59.00
90.00
2.00

70.00
9.00
13.00
11.00
41.00
Rs:

1484.00
36.00
767.00
990.00
82.00
6011.97

Rate
in Rs.
1706.60
937.80
1715.50
656.00
446.70
322.20

Amount
in Rs.
1877.26
1031.58
428.88
164.00
1965.48
1417.68

275.60
959.10
19.80
0.00
Rs:

1791.40
6234.15
257.40
0.00
15167.83

Rate
in Rs.
204.10
204.10
153.10
182.20
284.70
370.00
440.00
345.00
345.00
345.00
295.00

Amount
in Rs.
224.51
51.03
673.64
1184.30
3701.10
185.00
440.00
345.00
172.50
172.50
590.00

B. MACHINERY:
Sl No

particulars

UNIT :

Description

Unit

Quantity

Shovel 0.85 cum capacity


Fuel / energy charges
Angle dozer 90 hp
Fuel / Energy charges
Tippers 5 cum capacity 4 Nos.
Fuel / Energy charges
Air compressor 8.5 cmm ( diesel ) 1
Nos
Fuel / Energy charges
Jack hammers 2 Nos.
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour

1.10
1.10
0.25
0.25
4.40
4.40

Hour
Hour
Hour
Hour

6.50
6.50
13.00
13.00

Description

Unit

Crew for Shovel


Crew for Dozer
Crew for Tipper
Crew for Air compressor
Crew for Jack hammer
work inspector
Blaster
Helper blaster
Crowbarman
Stone breaker
mazdoor

Hour
Hour
Hour
Hour
Hour
Day
Day
Day
Day
Day
Day

Quantity
1.10
0.25
4.40
6.50
13.00
0.50
1.00
1.00
0.50
0.50
2.00

136

Canal and Allied Works - Item Unit Rates 2014-15

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
68.00 cum
cum
(A+B+C+D)/68
Rate per

Note:

7739.58

Rs:
Rs:
Rs:
Rs:

6011.97
15167.83
7739.58
28919.37

Rs:
Rs:
Rs.

4048.71
32968.08
484.80

113.80
0.14 15.90
129.70

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

IRR-CAW-1-7
(b)

Rs:

Excavation in hard rock of all toughness including boulders above 1.2 m dia. by approved
controlled blasting methods for canals, cut-off trench of embankment, filter / catch-water
drains etc., including controlling fly-rock by muffling arrangements such as placing
50 x 50 mm opening chain link mesh or waste tyres and sand bags, monitoring ground
vibrations at specified locations, costof all materials, machinery, labour, placing excavated rock
neatly in approved dump area or other place as directed etc., complete with lead upto 1 km
and all lifts.
i ) The rate under this item shall be adopted for canals designed for carrying capacity of less
than 15 cumecs or where the average depth of excavation in hard rock is less than 3 m.
ii ) The rate under this item shall be adopted where the control of fly-rock and ground vibrations
is required.

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Quantity

68.00 cum
Rate
in Rs.

Amount
in Rs.

137

Canal and Allied Works - Item Unit Rates 2014-15

1
2
3
4
5
6
7
8
9

Use rate of drill rod 1.5 m length


Reconditioning charges @
Use rate of 50 m air hose 2 Nos.
Use rate of wire mesh
Use rate of sand bag

Rm
10%
Hour
sqm
Nos

85.00

26.85

13.00
94.00
98.00

10.94
53.33
14.67

2282.53
228.25
142.19
5013.02
1437.66

Explosive small dia. (Kelvex-220 )


Ordinary detonators
Electric delay detonators
Fuse coil
Sundries
Total cost of Materials

kg
Nos
Nos
Rm
LS

21.20
4.00
59.00
90.00
2.00

70.00
9.00
23.00
11.00
41.00
Rs:

1484.00
36.00
1357.00
990.00
82.00
13052.65

Rate
in Rs.
1706.60
937.80
1715.50
656.00
446.70
322.20

Amount
in Rs.
1877.26
1031.58
428.88
164.00
1965.48
1417.68

275.60
959.10
19.80
0.00
Rs:

1791.40
6234.15
257.40
0.00
15167.83

Rate
in Rs.
204.10
204.10
153.10
182.20
284.70
370.00
440.00
345.00
345.00
345.00
295.00
Rs:

Amount
in Rs.
224.51
51.03
673.64
1184.30
3701.10
185.00
220.00
172.50
172.50
172.50
885.00
7642.08

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs.

13052.65
15167.83
7642.08
35862.55
179.31
36041.87
5045.86
41087.73
604.20

B. MACHINERY:
Sl No
1
2
3

4
5

C. LABOUR:
Sl No

Description

Unit

Quantity

Shovel 0.85 cum capacity


Fuel / Energy charges
Angle dozer 90 hp
Fuel / Energy charges
Tippers 5 cum capacity 3 Nos.
Fuel / Energy charges
Air compressor 8.5 cmm ( diesel ) 1
No
Fuel / Energy charges
Jack hammers 2 Nos.
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour

1.10
1.10
0.25
0.25
4.40
4.40

Hour
Hour
Hour
Hour

6.50
6.50
13.00
13.00

Description

Unit

Quantity

Crew for Shovel


Hour
1.10
Crew for Angle dozer
Hour
0.25
Crew for Tipper
Hour
4.40
Crew for Air compressor
Hour
6.50
Crew for Jack hammer
Hour
13.00
work inspector
Day
0.50
Blaster
Day
0.50
Helper blaster
Day
0.50
Stone chiseller Cl - II
Day
0.50
Stone breaker
Day
0.50
mazdoor
Day
3.00
Total cost of Labour
labour component/unit qty
112.40
Add contractor's profit and overhead charges
0.14 15.70
labour component/unit qty (including contractor's profit)
128.10
1
2
3
4
5
6
7
8
9
10
11

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Add for blasting studies & monitoring vibrations etc
0.50%
Total
D. Add for contractor's profit and overheads on
14%
Total cost for
68.00 cum
cum
(A+B+C+D)/68
Rate per

IRR-CAW-1-8
( c)

Excavation in hard rock of all toughness including boulders above 1.2 m dia. for dressing
canal sides neatly on either side to required profile by line drilling and smooth blasting
including removing under-cuts by chiselling / hammering, placing the excavated rock neatly in
dump area or other place as directed, cost of all materials, machinery, labour etc., complete
with lead upto 1 km and all lifts.

138

Canal and Allied Works - Item Unit Rates 2014-15

Note:

i) For excavation of canal below free board level combination of normal / controlled blasting and
line drilling and smooth blasting shall be adopted to obtain neat side slopes. For the purpose
of payment 1 m width of excavation on either side shall be treated as excavation by line drilling
and smooth blasting and remaining portion shall be treated as excavation by normal / controlled
blasting as the case may be.
ii ) The rate under this item shall be adopted for canals designed for carrying capacity of less
than 15 cumecs or where the average depth of excavation in hard rock is less than 3 m.
iii ) The rate includes controlling fly-rock wherever required.
iv ) The rate under this item shall be paid only on ascertaining that the excavated face has
come off neatly as per specifications or atleast 50 percent of smooth blast holes are visible for
inspection and are spaced at specified interval.
v ) In case, where the above criteria is not fulfilled payment shall be restricted to rate provided
for excavation by normal blasting or controlled blasting as the case may be.

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6

3
4

C. LABOUR:
Sl No
1
2
3
4
5
6

Unit

Use rate of drill rod 1.5 m length


Reconditioning charges @
Use rate of 50 m air hose 2 Nos.

Rm
10%
Hour

63.00

Explosive small dia. (Kelvex-220 )


Electric delay detonators
Fuse coil
Sundries
Total cost of Materials

kg
Nos
Rm
LS

3.50
22.00
20.00
1.00

B. MACHINERY:
Sl No
1

particulars

UNIT :
Quantity

10.00

Description

Unit

Quantity

Shovel 0.85 cum capacity


Fuel / Energy charges
Tippers 5 cum capacity 4 Nos.
Fuel / Energy charges
Air compressor 8.5 cmm ( diesel ) 1
Nos
Fuel / Energy charges
Jack hammers 2 Nos.
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour

0.28
0.28
1.12
1.12

Hour
Hour
Hour
Hour

5.00
5.00
10.00
10.00

Description

Unit

Crew for Shovel


Crew for Tipper
Crew for Air compressor
Crew for Jack hammer
work inspector
Blaster

Hour
Hour
Hour
Hour
Day
Day

Quantity
0.50
1.12
5.00
10.00
0.50
0.50

17.50 cum
Rate
Amount
in Rs.
in Rs.
26.85
1691.76
169.18
10.94
109.38
70.00
23.00
11.00
41.00
Rs:

245.00
506.00
220.00
41.00
2982.31

Rate
in Rs.
1706.60
937.80
446.70
322.20

Amount
in Rs.
477.85
262.58
500.30
360.86

275.60
959.10
19.80
0.00
Rs:

1378.00
4795.50
198.00
0.00
7973.10

Rate
in Rs.
204.10
153.10
182.20
284.70
370.00
440.00

Amount
in Rs.
102.05
171.47
911.00
2847.00
185.00
220.00

139

Canal and Allied Works - Item Unit Rates 2014-15

7
8
9
10

Helper blaster
Stone breaker
Stone chiseller Cl - II
mazdoor
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Day
Day
Day
Day

0.50
0.50
0.50
1.00

Total
Add for blasting studies & monitoring vibrations etc
0.50%
Total
D. Add for contractor's profit and overheads on
14%
Total cost for
17.50 cum
cum
(A+B+C+D)/17.50
Rate per

Note:

172.50
172.50
172.50
295.00
5249.02

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs.

2982.31
7973.10
5249.02
16204.43
81.02
16285.46
2279.96
18565.42
1060.90

299.90
0.14 42.00
341.90

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

IRR-CAW-1-9
(a)

345.00
345.00
345.00
295.00
Rs:

Excavation in hard rock by blasting including boulders above 1.2 m dia. for canals, seating
embankment etc., including levelling bed by removing all projections by hammering / chiselling,
cost of all materials, machinery, labour, placing the excavated rock neatly in approved dump
area and levelling the same as directed etc.,complete with initial lead upto 1 km and all lifts.
i ) The rate under this item shall be adopted for canals designed for carrying capacity of more
than 15 cumecs or where the average depth of excavation in hard rock is more than 3 m.
ii ) The rate includes levelling canal bed by hammering / chiselling all rock projections wherever
required.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

Unit:
Unit

Quantity

386.00 Cum
Rate

Amount

140

Canal and Allied Works - Item Unit Rates 2014-15

1
2
3

5
6
7
8
9
10
11
12

Use rate of T.C bit 100 mm dia


Use rate of Extension rod with
coupling sleeve
Use rate of Jack hammer drill rod 1.5
m
reconditioning charges @
Use rate of 50 m air hose for waggon
drill
Use rate of 25 m air hose for JH 2
Nos
High strength ANFO booster
ANFO
Diesel oil
Explosive small dia ( Kelvex-220 )
Ordinary detonators
D-cord
Detonating fuse coil
Sundries
Total cost of Materials

B. MACHINERY:
Sl No
1
2
3

4
5
6

C. LABOUR:
Sl No

Description

Rm

104.00

in Rs.
150.00

Rm

104.00

6.36

661.44

12.00

26.85

322.24
32.22

Hour

10.50

18.63

195.56

Hour
kg
kg
ltr

1.00
38.00
155.00
35.00

10.94
73.00
43.00
62.00

10.94
2774.00
6665.00
2170.00

kg
Nos
Rm
Rm
LS

4.00
20.00
145.00
20.00
5.00

70.00
9.00
10.00
11.00
41.00
Rs:

280.00
180.00
1450.00
220.00
205.00
30766.40

Rate
in Rs.
446.70
322.20
1706.60
937.80
1715.50
656.00

Amount
in Rs.
11096.03
8003.45
10597.99
5823.74
3431.00
1312.00

275.60
959.10
188.50
0.00
19.80
0.00
Rs:

3169.40
11029.65
1979.25
0.00
39.60
0.00
56482.10

Rate
in Rs.
153.10
204.10
204.10
182.20
244.90
284.70
370.00
440.00
345.00
345.00
345.00
295.00
Rs:

Amount
in Rs.
3803.00
1267.46
408.20
2095.30
2571.45
569.40
740.00
440.00
345.00
345.00
345.00
885.00
13814.82

Rm
10%

Unit

Quantity

Tippers 5 cum capacity


Fuel / Energy charges
Shovel 0.85 cum capacity
Fuel / Energy charges
Angle dozer
Fuel / Energy charges

Hour
Hour
Hour
Hour
Hour
Hour

24.84
24.84
6.21
6.21
2.00
2.00

Air compressor 8.5 cmm ( diesel )


Fuel / Energy charges
Waggon drill
Fuel / Energy charges
Jack hammer
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour

11.50
11.50
10.50
10.50
2.00
2.00

Description

Unit

Quantity

Crew for Tipper


Hour
24.84
Crew for Shovel
Hour
6.21
Crew for Dozer
Hour
2.00
Crew for Air compressor
Hour
11.50
Crew for Waggon drill
Hour
10.50
Crew for Jack hammer
Hour
2.00
work inspector
Day
2.00
Blaster
Day
1.00
Helper blaster
Day
1.00
Stone chiseller Cl - II
Day
1.00
Stone breaker
Day
1.00
mazdoor
Day
3.00
Total cost of Labour
labour component/unit qty
35.80
Add contractor's profit and overhead charges
0.14 5.00
labour component/unit qty (including contractor's profit)
40.80
1
2
3
4
5
6
7
8
9
10
11
12

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total

in Rs.
15600.00

Rs:
30766.40
Rs:
56482.10
Rs:
13814.82
Rs: 101063.32

141

Canal and Allied Works - Item Unit Rates 2014-15

D. Add for contractor's profit and overheads on (A+B+C)


14%
Total cost for
386.00 Cum
Cum
(A+B+C+D)/386
Rate per

Rs:
14148.86
Rs: 115212.18
Rs.
298.50

IRR-CAW-1-10 Excavation in hard rock of all toughness including boulders above 1.2 m dia. by approved
(b)
controlled blasting methods for canals, cut-off trench of embankment etc., including
controlling fly-rock by muffling arrangements such as placing 50 x 50 mm opening
chain link mesh or waste tyres and sand bags, monitoring ground vibrations at specified
locations, cost of all materials, machinery, labour, placing excavated rock neatly in approved
dump area or other place as directed etc., complete with lead upto 1 km and all lifts.
Note:

i ) The rate under this item shall be adopted for canals designed for carrying capacity of more
than 15 cumecs or where the average depth of excavation in hard rock is more than 3 m.
ii ) The rate under this item shall be adopted where the control of fly-rock and ground vibrations
is required.

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No

UNIT :

particulars

Unit
Rm

Use rate of T.C bit 100 mm dia


Use rate of Extension rod with
coupling sleeve
Use rate of Jack hammer drill rod 1.6
m
reconditioning charges @
Use rate of 50 m air hose 50 mm 1
No.

Use rate of 25 mm air hose 2 Nos


High strength ANFO booster

1
2
3

Quantity

386.00 cum

104.00

Rate
in Rs.
150.00

Amount
in Rs.
15600.00

Rm

104.00

6.36

661.44

Rm
10%

12.00

26.85

322.24
32.22

Hour

10.50

18.63

195.56

Hour
kg

2.00
38.00

10.94
73.00

21.88
2774.00

142

Canal and Allied Works - Item Unit Rates 2014-15

6
7

ANFO
Diesel oil

8
9
10
11
12
13
14
15

Explosive small dia ( Kelvex-220 )


Ordinary detonators
Shock tube detonators
Noiseless trunk line delays
Detonating fuse coil
Use rate of chain link wire mesh
Use rate of sand bag
Sundries
Total cost of Materials

B. MACHINERY:
Sl No
1
2
3

4
5
6

C. LABOUR:
Sl No

Description

kg
ltr

155.00
35.00

43.00
62.00

6665.00
2170.00

kg
Nos
Rm
Nos
Rm
sqm
Nos
LS

4.00
20.00
120.00
12.00
20.00
132.00
110.00
20.00

70.00
9.00
65.00
21.00
11.00
190.80
11.17
41.00
Rs:

280.00
180.00
7800.00
252.00
220.00
25185.60
1228.70
820.00
64408.64

Rate
in Rs.
446.70
322.20
1706.60
937.80
1715.50
656.00

Amount
in Rs.
13401.00
9666.00
17066.00
9378.00
3431.00
1312.00

275.60
959.10
188.50
0.00
19.80
0.00
Rs:

3445.00
11988.75
2167.75
0.00
39.60
0.00
71895.10

Rate
in Rs.
153.10
204.10
204.10
182.20
244.90
284.70
370.00
440.00
345.00
345.00
345.00
295.00
Rs:

Amount
in Rs.
4593.00
2041.00
408.20
2277.50
2816.35
569.40
555.00
220.00
172.50
345.00
345.00
1475.00
15817.95

Unit

Quantity

Tippers 5 cum capacity


Fuel / Energy charges
Shovel 0.85 cum capacity
Fuel / Energy charges
Angle dozer
Fuel / Energy charges

Hour
Hour
Hour
Hour
Hour
Hour

30.00
30.00
10.00
10.00
2.00
2.00

Air compressor 8.5 cmm ( diesel )


Fuel / Energy charges
Waggon drill
Fuel / Energy charges
Jack hammer
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour

12.50
12.50
11.50
11.50
2.00
2.00

Description

Unit

Quantity

Crew for Tipper


Hour
30.00
Crew for Shovel
Hour
10.00
Crew for Dozer
Hour
2.00
Crew for Air compressor
Hour
12.50
Crew for Waggon drill
Hour
11.50
Crew for Jack hammer
Hour
2.00
work inspector
Day
1.50
Blaster
Day
0.50
Helper blaster
Day
0.50
Stone chiseller Cl - II
Day
1.00
Stone breaker
Day
1.00
mazdoor
Day
5.00
Total cost of Labour
labour component/unit qty
41.00
Add contractor's profit and overhead charges
0.14 5.70
labour component/unit qty (including contractor's profit)
46.70
1
2
3
4
5
6
7
8
9
10
11
12

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Add for blasting studies & monitoring vibrations etc
0.50%
Total
D. Add for contractor's profit and overheads on
14%
Total cost for
386.00 cum
cum
(A+B+C+D)/386
Rate per

Rs:
64408.64
Rs:
71895.10
Rs:
15817.95
Rs: 152121.69
Rs:
760.61
Rs: 152882.30
Rs:
21403.52
Rs: 174285.82
Rs.
451.50

IRR-CAW-1-11 Excavation in hard rock of all toughness including boulders above 1.2 m dia. for dressing
( c)
canal sides neatly on either side to required profile by line drilling and smooth blasting

143

Canal and Allied Works - Item Unit Rates 2014-15

including removing under-cuts by chiselling / hammering, placing the excavated rock neatly in
dump area or other place as directed, cost of all materials, machinery, labour etc., complete
with lead upto 1 km and all lifts.
Note:

i ) For excavation of canal below free board level combination of normal / controlled blasting and
line drilling and smooth blasting shall be adopted to obtain neat side slopes. For the purpose
of payment 1 m width of excavation on either side shall be treated as excavation by line drilling
and smooth blasting and remaining portion shall be treated as excavation by normal / controlled
blasting as the case may be.
ii ) The rate under this item shall be adopted for canals designed for carrying capacity of more
than 15 cumecs or where the average depth of excavation in hard rock is more than 3 m.
iii ) The rate includes controlling fly-rock wherever required.
iv ) The rate under this item shall be paid only on ascertaining that the excavated face has
come off neatly as per specifications or atleast 50 percent of smooth blast holes are visible for
inspection and are spaced at specified interval.
v ) In case, where the above criteria is not fulfilled payment shall be restricted to rate provided
for excavation by normal blasting or controlled blasting as the case may be.

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No

UNIT :

particulars

Unit
Rm

Use rate of T.C bit 100 mm dia


Use rate of Extension rod with
coupling sleeve
Use rate of Jack hammer drill rod 1.6
m
reconditioning charges @
Use rate of 50 m air hose 50 mm 1
No.

5
6
7

1
2
3

8
9
10
11
12
13

121.00

Rate
in Rs.
150.00

Amount
in Rs.
18150.00

Rm

121.00

6.36

769.56

Rm
10%

3.00

26.85

80.56
8.06

Hour

12.00

18.63

223.50

Use rate of 25 mm air hose 2 Nos


High strength ANFO booster
ANFO
Diesel oil

Hour
kg
kg
ltr

0.50
5.00
19.00
4.50

10.94
73.00
43.00
62.00

5.47
365.00
817.00
279.00

Explosive small dia ( Kelvex-220 )


Ordinary detonators
Detonating shock tube
Noiseless trunk line delays
Fuse coil
Sundries
Total cost of Materials

kg
Nos
Rm
Nos
Rm
LS

1.00
5.00
70.00
4.00
10.00
2.00

70.00
9.00
65.00
21.00
11.00
41.00
Rs:

70.00
45.00
4550.00
84.00
110.00
82.00
25639.14

Rate
in Rs.
6.24 446.70
6.24 322.20
1.56 1706.60

Amount
in Rs.
2787.41
2010.53
2662.30

B. MACHINERY:
Sl No
1
2

Description

Tippers 5 cum capacity


Fuel / Energy charges
Shovel 0.85 cum capacity

Unit
Hour
Hour
Hour

Quantity

97.00 cum

Quantity

144

Canal and Allied Works - Item Unit Rates 2014-15

4
5
6

Fuel / Energy charges


Angle dozer
Fuel / Energy charges

Hour
Hour
Hour

Air compressor 8.5 cmm ( diesel )


Fuel / Energy charges
Waggon drill
Fuel / Energy charges
Jack hammer
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour

Description

Unit

C. LABOUR:
Sl No

1.56 937.80
0.50 1715.50
0.50 656.00
13.45
13.45
13.20
13.20
0.50
0.50

Quantity

Crew for Tipper


Hour
5.24
Crew for Shovel
Hour
1.56
Crew for Dozer
Hour
0.50
Crew for Air compressor
Hour
13.45
Crew for Waggon drill
Hour
13.45
Crew for Jack hammer
Hour
0.50
work inspector
Day
0.50
Blaster
Day
0.50
Helper blaster
Day
0.50
Stone breaker
Day
1.00
Stone chiseller Cl- II
Day
1.00
mazdoor
Day
2.00
Total cost of Labour
labour component/unit qty
92.40
Add contractor's profit and overhead charges
0.14 12.90
labour component/unit qty (including contractor's profit)
105.30
1
2
3
4
5
6
7
8
9
10
11
12

1462.97
857.75
328.00

275.60
959.10
188.50
0.00
19.80
0.00
Rs:

3706.82
12899.90
2488.20
0.00
9.90
0.00
29213.77

Rate
in Rs.
153.10
204.10
204.10
182.20
244.90
284.70
370.00
440.00
345.00
345.00
345.00
295.00
Rs:

Amount
in Rs.
802.24
318.40
102.05
2450.59
3293.91
142.35
185.00
220.00
172.50
345.00
345.00
590.00
8967.04

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs.

25639.14
29213.77
8967.04
63819.94
319.10
64139.04
8979.47
73118.51
753.80

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Add for blasting studies & monitoring vibrations etc
0.50%
Total
D. Add for contractor's profit and overheads on
14%
Total cost for
97.00 cum
cum
(A+B+C+D)/97
Rate per
IRR-CAW-2

EMBANKMENT WORKS USING BORROW AREA SOIL :

IRR-CAW-2-1

Providing impervious hearting embankment with selected soil from approved borrow areas in
layers of 25 cm before compaction including cost of all materials, machinery, labour,
all operations such as excavation, sorting out, transporting, spreading in layer of specified
thickness, breaking clods, sectioning, watering, compacting each layer to density control of
not less than 98 percent or as stipulated by Sheep foot roller / Vibratory roller/
8 to 10 tonne power roller etc., complete with initial lead upto 1 km and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Nill

Quantity

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
3.40 1715.50
3.40 656.00

Amount
in Rs.
5832.70
2230.40

0.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No
1

Description

Angle dozer
Fuel / Energy charges

Unit
Hour
Hour

412.80 cum

Quantity

145

Canal and Allied Works - Item Unit Rates 2014-15

2
3
4
5
6
7

Shovel 0.50 cum capacity


Fuel / Energy charges
Tippers 5.00 cum capacity 4 Nos.
Fuel / Energy charges
Pump 5 hp ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Vibratory Roller 8 tonne
Fuel / Energy charges
Sundries
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Description

Unit

C. LABOUR:
Sl No

8.00 1003.10
8.00 511.50
32.00 446.70
32.00 322.20
2.00
10.20
2.00
85.30
4.00 402.50
4.00 322.20
5.10 1342.20
5.10 1108.30
5.00
41.00
Rs:

Quantity

Crew for Dozer


Hour
3.40
Crew for Shovel
Hour
8.00
Crew for Tipper
Hour
32.00
Crew for Pump
Hour
2.00
Crew for Water tanker
Hour
4.00
Crew for Roller
Hour
5.10
work inspector
Day
2.00
mazdoor
Day
4.00
Total cost of Labour
labour component/unit qty
26.90
Add contractor's profit and overhead charges
0.14 3.80
labour component/unit qty (including contractor's profit)
30.70
1
2
3
4
5
6
7
8

Rate
in Rs.
204.10
204.10
153.10
96.10
153.10
227.80
370.00
295.00
Rs:

Amount
in Rs.
693.94
1632.80
4899.20
192.20
612.40
1161.78
740.00
1180.00
11112.32

Rs:
Rs:
Rs:
Rs:

0.00
60577.05
11112.32
71689.37

Rs:
Rs:
Rs.

10036.51
81725.88
198.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
412.80 cum
cum
(A+B+C+D)/412.80
Rate per

IRR-CAW-2-2

8024.80
4092.00
14294.40
10310.40
20.40
170.60
1610.00
1288.80
6845.22
5652.33
205.00
60577.05

Providing impervious hearting embankment with selected soil from approved borrow areas in
layers of 25 cm before compaction including cost of all materials, machinery, labour,
all operations such as excavation, sorting out, transporting, spreading in layer of specified
thickness, breaking clods, sectioning, watering, compacting each layer to density control of
not less than 95 percent or as stipulated by Sheep foot roller / Vibratory roller/
8 to 10 tonne power roller etc., complete with initial lead upto 1 km and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Nill

Quantity
0.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No
1
2
3

Description

Angle dozer 90 hp
Fuel / Energy charges
Shovel 0.5 cum
Fuel / Energy charges
Tippers 5 cum
Fuel / Energy charges

Unit
Hour
Hour
Hour
Hour
Hour
Hour

Quantity
3.40
3.40
8.00
8.00
32.00
32.00

412.80 cum
Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
1715.50
656.00
1003.10
511.50
446.70
322.20

Amount
in Rs.
5832.70
2230.40
8024.80
4092.00
14294.40
10310.40

146

Canal and Allied Works - Item Unit Rates 2014-15

4
5
6
7

Pump 5 hp ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Vibratory Roller 8 tonne
Fuel / Energy charges
Sundries
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
LS

Description

Unit

C. LABOUR:
Sl No

Crew for Dozer


Hour
Crew for Shovel
Hour
Crew for Tipper
Hour
Crew for Pump
Hour
Crew for Water tanker
Hour
Crew for Roller
Hour
work inspector
Day
mazdoor
Day
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
1
2
3
4
5
6
7
8

2.00
10.20
2.00
85.30
4.00 402.50
4.00 322.20
4.18 1342.20
4.18 1108.30
5.00
41.00
Rs:

Quantity
3.40
8.00
32.00
2.00
4.00
4.18
2.00
4.00

0.14

Rate
in Rs.
204.10
204.10
153.10
96.10
153.10
227.80
370.00
295.00
Rs:
26.40
3.70
30.10

Amount
in Rs.
693.94
1632.80
4899.20
192.20
612.40
952.20
740.00
1180.00
10902.74

Rs:
Rs:
Rs:
Rs:

0.00
58322.59
10902.74
69225.33

Rs:
Rs:
Rs.

9691.55
78916.88
191.20

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
412.80 cum
cum
(A+B+C+D)/412.80
Rate per

IRR-CAW-2-3

20.40
170.60
1610.00
1288.80
5610.40
4632.69
205.00
58322.59

Providing semi-pervious / pervious casing embankment using soil from approved borrow area
in layers of 25 cm before compaction including cost of all materials, machinery, labour,
all operations such as excavation, sortingout, transporting, spreading in layer of specified
thickness, breaking clods, sectioning, watering, compacting to density control of not less
than 98 percent or as stipulated by Sheep foot roller / Vibratory roller/ 8 to 10 tonne power roller
etc., complete with initial lead upto 1 km and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Nill

Quantity
0.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No
1
2
3
4
5
6

Description

Angle dozer 90 hp
Fuel / Energy charges
Shovel 0.50 cum capacity
Fuel / Energy charges
Tippers 5.00 cum capacity 3 Nos.
Fuel / Energy charges
Pump 5 hp ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Vibratory Roller 8 tonne

Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour

Quantity
3.40
3.40
8.00
8.00
32.00
32.00
2.00
2.00
4.00
4.00
5.10

412.80 cum
Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
1715.50
656.00
1003.10
511.50
446.70
322.20
10.20
85.30
402.50
322.20
1342.20

Amount
in Rs.
5832.70
2230.40
8024.80
4092.00
14294.40
10310.40
20.40
170.60
1610.00
1288.80
6845.22

147

Canal and Allied Works - Item Unit Rates 2014-15

Fuel / Energy charges


Sundries
Total hire charges of Machinery

Hour
LS

Description

Unit

C. LABOUR:
Sl No

Crew for Dozer


Hour
Crew for Shovel
Hour
Crew for Tipper
Hour
Crew for Pump
Hour
Crew for Water tanker
Hour
Crew for Roller
Hour
work inspector
Day
mazdoor
Day
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
1
2
3
4
5
6
7
8

5.10 1108.30
2.00
41.00
Rs:

Quantity
3.40
8.00
32.00
2.00
4.00
5.10
2.00
4.00

0.14

Rate
in Rs.
204.10
204.10
153.10
96.10
153.10
227.80
370.00
295.00
Rs:
26.90
3.80
30.70

Amount
in Rs.
693.94
1632.80
4899.20
192.20
612.40
1161.78
740.00
1180.00
11112.32

Rs:
Rs:
Rs:
Rs:

0.00
60454.05
11112.32
71566.37

Rs:
Rs:
Rs.

10019.29
81585.66
197.60

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
412.80 cum
cum
(A+B+C+D)/412.80
Rate per

IRR-CAW-2-4

5652.33
82.00
60454.05

Providing semi-pervious / pervious casing embankment using soil from approved borrow area
in layers of 25cm before compaction including cost of all materials, machinery, labour,
all operations such as excavation, sortingout, transporting, spreading in layer of specified
thickness, breaking clods, sectioning, watering, compacting to density control of not less
than 95 percent or as stipulated by Sheep foot roller / Vibratory roller/ 8 to 10 tonne power roller
etc., complete with initial lead upto 1 km and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Nill

Quantity
0.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No
1
2
3
4
5
6
7

Description

Unit

Angle dozer 90 hp
Fuel / Energy charges
Shovel 0.5 cum
Fuel / Energy charges
Tippers 5 cum
Fuel / Energy charges
Pump 5 hp ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Vibratory Roller 8 tonne
Fuel / Energy charges
Sundries
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Quantity
3.40
3.40
8.00
8.00
32.00
32.00
2.00
2.00
4.00
4.00
4.17
4.17
5.00

412.80 cum
Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
1715.50
656.00
1003.10
511.50
446.70
322.20
10.20
85.30
402.50
322.20
1342.20
1108.30
41.00
Rs:

Amount
in Rs.
5832.70
2230.40
8024.80
4092.00
14294.40
10310.40
20.40
170.60
1610.00
1288.80
5596.97
4621.61
205.00
58298.09

C. LABOUR:

148

Canal and Allied Works - Item Unit Rates 2014-15

Sl No

Description

Unit

Quantity

Crew for Dozer


Hour
3.40
Crew for Shovel
Hour
8.00
Crew for Tipper
Hour
32.00
Crew for Pump
Hour
2.00
Crew for Water tanker
Hour
4.00
Crew for Roller
Hour
4.00
work inspector
Day
4.17
mazdoor
Day
4.00
Total cost of Labour
labour component/unit qty
28.30
Add contractor's profit and overhead charges
0.14 4.00
labour component/unit qty (including contractor's profit)
32.30
1
2
3
4
5
6
7
8

Rate
in Rs.
204.10
204.10
153.10
96.10
153.10
227.80
370.00
295.00
Rs:

Amount
in Rs.
693.94
1632.80
4899.20
192.20
612.40
911.20
1542.90
1180.00
11664.64

Rs:
Rs:
Rs:
Rs:

0.00
58298.09
11664.64
69962.73

Rs:
Rs:
Rs.

9794.78
79757.51
193.20

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
412.80 cum
cum
(A+B+C+D)/412.80
Rate per

IRR-CAW-2-5

Providing semi-pervious / pervious casing embankment using soil from approved borrow area
in layers of 25cm before compaction including cost of all materials, machinery, labour,
all operations such as excavation, sortingout, transporting, spreading in layer of specified
thickness, breaking clods, sectioning, compacting each layer without watering to density
control of not less than 95 percent or as stipulated by Sheep foot roller / Vibratory roller/
8 to 10 tonne power roller etc., complete with initial lead upto 1 km and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Nill

Quantity
0.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No
1
2
3
4
5

C. LABOUR:
Sl No
1
2
3
4
5
6

Description

Unit

Angle dozer 90 hp
Fuel / Energy charges
Shovel 0.50 cum capacity
Fuel / Energy charges
Tippers 5.00 cum capacity 3 Nos.
Fuel / Energy charges
Vibratory Roller 8 tonne
Fuel / Energy charges
Sundries
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Description

Unit

Crew for Dozer


Crew for Shovel
Crew for Tipper
Crew for Roller
work inspector
mazdoor

Hour
Hour
Hour
Hour
Day
Day
Total cost of Labour

Quantity
3.40
3.40
8.00
8.00
32.00
32.00
4.17
4.17
2.00

Quantity
3.40
8.00
32.00
4.17
2.00
4.00

412.80 cum
Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
1715.50
656.00
1003.10
511.50
446.70
322.20
1342.20
1108.30
41.00
Rs:

Amount
in Rs.
5832.70
2230.40
8024.80
4092.00
14294.40
10310.40
5596.97
4621.61
82.00
55085.29

Rate
in Rs.
204.10
204.10
153.10
227.80
370.00
295.00
Rs:

Amount
in Rs.
693.94
1632.80
4899.20
949.93
740.00
1180.00
10095.87

149

Canal and Allied Works - Item Unit Rates 2014-15

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

24.50
0.14 3.40
27.90

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
412.80 cum
cum
(A+B+C+D)/412.80
Rate per

IRR-CAW-2-6

Rs:
Rs:
Rs:
Rs:

0.00
55085.29
10095.87
65181.15

Rs:
Rs:
Rs.

9125.36
74306.51
180.00

Providing hearting / casing embankment with homogeneous soil from approved borrow
areas in layers of 25 cm before compaction including cost of all materials, machinery,
labour, all operations such as excavation, sorting out, transporting, spreading in layer of
specified thickness, breaking clods, sectioning, watering, compacting each layer to density
control of not less than 98 percent or as stipulated by Sheep foot roller / Vibratory roller/
8 to 10 tonne power roller etc., complete with initial lead upto 1 km and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Nill

Quantity
0.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No
1
2
3
4
5
6
7

C. LABOUR:
Sl No

Description

Unit

Angle dozer
Fuel / Energy charges
Shovel 0.50 cum capacity
Fuel / Energy charges
Tippers 5.00 cum capacity 6 Nos.
Fuel / Energy charges
Pump 5 hp ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Vibratory Roller 8 tonne
Fuel / Energy charges
Sundries
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Description

Unit

Quantity
6.06
6.06
8.00
8.00
48.00
48.00
3.00
3.00
6.00
6.00
7.53
7.53
2.00

Quantity

Crew for Dozer


Hour
6.06
Crew for Shovel
Hour
8.00
Crew for Tipper
Hour
48.00
Crew for Pump
Hour
3.00
Crew for Water tanker
Hour
6.00
Crew for Roller
Hour
7.53
work inspector
Day
2.00
mazdoor
Day
4.00
Total cost of Labour
labour component/unit qty
22.20
Add contractor's profit and overhead charges
0.14 3.10
labour component/unit qty (including contractor's profit)
25.30
1
2
3
4
5
6
7
8

677.28 cum
Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
1715.50
656.00
1003.10
511.50
446.70
322.20
10.20
85.30
402.50
322.20
1342.20
1108.30
41.00
Rs:

Amount
in Rs.
10395.93
3975.36
8024.80
4092.00
21441.60
15465.60
30.60
255.90
2415.00
1933.20
10106.77
8345.50
82.00
86564.26

Rate
in Rs.
204.10
204.10
153.10
96.10
153.10
227.80
370.00
295.00
Rs:

Amount
in Rs.
1236.85
1632.80
7348.80
288.30
918.60
1715.33
740.00
1180.00
15060.68

150

Canal and Allied Works - Item Unit Rates 2014-15

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
677.28 cum
cum
(A+B+C+D)/677.28
Rate per

IRR-CAW-2-7

Rs:
0.00
Rs:
86564.26
Rs:
15060.68
Rs: 101624.94
Rs:
14227.49
Rs: 115852.43
Rs.
171.10

Providing hearting / casing embankment with homogeneous soil from approved borrow
areas in layers of 25 cm before compaction including cost of all materials, machinery,
labour, all operations such as excavation, sorting out, transporting, spreading in layer of
specified thickness, breaking clods, sectioning, watering, compacting each layer to density
control of not less than 95 percent or as stipulated by Sheep foot roller / Vibratory roller/
8 to 10 tonne power roller etc., complete with initial lead upto 1 km and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Nill

Quantity
0.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No
1
2
3
4
5
6
7

C. LABOUR:
Sl No

Description

Unit

Angle dozer 90 hp
Fuel / Energy charges
Shovel 0.5 cum
Fuel / Energy charges
Tippers 5 cum 3 Nos
Fuel / Energy charges
Pump 5 hp ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Vibratory Roller 8 tonne
Fuel / Energy charges
Sundries
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Description

Unit

Quantity
6.06
6.06
8.00
8.00
48.00
48.00
3.00
3.00
6.00
6.00
6.16
6.16
5.00

Quantity

Crew for Dozer


Hour
6.06
Crew for Shovel
Hour
8.00
Crew for Tipper
Hour
48.00
Crew for Pump
Hour
3.00
Crew for Water tanker
Hour
6.00
Crew for Roller
Hour
6.16
work inspector
Day
2.00
mazdoor
Day
4.00
Total cost of Labour
labour component/unit qty
21.80
Add contractor's profit and overhead charges
0.14 3.10
labour component/unit qty (including contractor's profit)
24.90
1
2
3
4
5
6
7
8

677.28 cum
Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
1715.50
656.00
1003.10
511.50
446.70
322.20
10.20
85.30
402.50
322.20
1342.20
1108.30
41.00
Rs:

Amount
in Rs.
10395.93
3975.36
8024.80
4092.00
21441.60
15465.60
30.60
255.90
2415.00
1933.20
8267.95
6827.13
205.00
83330.07

Rate
in Rs.
204.10
204.10
153.10
96.10
153.10
227.80
370.00
295.00
Rs:

Amount
in Rs.
1236.85
1632.80
7348.80
288.30
918.60
1403.25
740.00
1180.00
14748.59

Rs:
Rs:
Rs:
Rs:

0.00
83330.07
14748.59
98078.66

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total

151

Canal and Allied Works - Item Unit Rates 2014-15

D. Add for contractor's profit and overheads on (A+B+C)


14%
Total cost for
677.28 cum
cum
(A+B+C+D)/677.28
Rate per
IRR-CAW-2-8

Rs:
13731.01
Rs: 111809.67
Rs.
165.10

Providing casing embankment using homogeneous soil from approved borrow area
in layers of 25 cm before compaction including cost of all materials, machinery, labour,
all operations such as excavation, sortingout, transporting, spreading in layer of specified
thickness, breaking clods, sectioning, compacting each layer without watering to density
control of not less than 95 percent or as stipulated by Sheep foot roller / Vibratory roller/
8 to 10 tonne power roller etc., complete with initial lead upto 1 km and all lifts.

RATE ANALYSIS

DATA:
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Quantity

Nill

0.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No
1
2
3
4
5

C. LABOUR:
Sl No
1
2
3
4
5
6

Description

Unit

Angle dozer 90 hp
Fuel / Energy charges
Shovel 0.50 cum capacity
Fuel / Energy charges
Tippers 5.00 cum capacity 4 Nos.
Fuel / Energy charges
Vibratory Roller 8 tonne
Fuel / Energy charges
Sundries
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Description

Unit

Crew for Dozer


Crew for Shovel
Crew for Tipper
Crew for Roller
work inspector
mazdoor

Hour
Hour
Hour
Hour
Day
Day

Quantity
6.06
6.06
8.00
8.00
48.00
48.00
6.16
6.16
2.00

Quantity
6.06
8.00
48.00
6.16
2.00
4.00

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

677.28 cum
Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
1715.50
656.00
1003.10
511.50
446.70
322.20
1342.20
1108.30
41.00
Rs:

Amount
in Rs.
10395.93
3975.36
8024.80
4092.00
21441.60
15465.60
8267.95
6827.13
82.00
78572.37

Rate
in Rs.
204.10
204.10
153.10
227.80
370.00
295.00
Rs:

Amount
in Rs.
1236.85
1632.80
7348.80
1403.25
740.00
1180.00
13541.69

Rs:
Rs:
Rs:
Rs:

0.00
78572.37
13541.69
92114.06

20.00
0.14 2.80
22.80

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
677.28 cum
cum
(A+B+C+D)/677.28
Rate per

Rs:
12895.97
Rs: 105010.03
Rs.
155.00

IRR-CAW-3

EMBANKMENT WORKS USING DUMP AREA SOIL :

IRR-CAW-3-1

Providing impervious hearting embankment with soil from approved dump areas in layers
of 25 cm before compaction including cost of all materials, machinery, labour, all
operations such as re-excavation, sorting out, transporting, spreading in layer of specified
thickness, breaking clods, sectioning, watering, compacting each layer to achieve density

152

Canal and Allied Works - Item Unit Rates 2014-15

control of not less than 98 percent or as stipulated by Sheep foot roller / Vibratory roller/
8 to 10 tonne power roller etc.,complete with initial lead upto 1 km and all lifts.

RATE ANALYSIS

DATA:
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Nill

Quantity
0.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No
1
2
3
4
5
6
7

C. LABOUR:
Sl No

Description

Unit

Angle dozer
Fuel / Energy charges
Shovel 0.50 cum capacity
Fuel / Energy charges
Tippers 5.00 cum capacity 6 Nos.
Fuel / Energy charges
Pump 5 hp ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Vibratory Roller 8 tonne
Fuel / Energy charges
Sundries
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Description

Unit

Quantity
4.04
4.04
8.00
8.00
48.00
48.00
3.00
3.00
6.00
6.00
7.50
7.50
2.00

Quantity

Crew for Dozer


Hour
3.58
Crew for Shovel
Hour
8.00
Crew for Tipper
Hour
48.00
Crew for Pump
Hour
3.00
Crew for Water tanker
Hour
6.00
Crew for Roller
Hour
7.50
work inspector
Day
2.00
mazdoor
Day
6.00
Total cost of Labour
labour component/unit qty
20.60
Add contractor's profit and overhead charges
0.14 2.90
labour component/unit qty (including contractor's profit)
23.50
1
2
3
4
5
6
7
8

735.36 cum
Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
1715.50
656.00
1003.10
511.50
446.70
322.20
10.20
85.30
402.50
322.20
1342.20
1108.30
41.00
Rs:

Amount
in Rs.
6930.62
2650.24
8024.80
4092.00
21441.60
15465.60
30.60
255.90
2415.00
1933.20
10066.50
8312.25
82.00
81700.31

Rate
in Rs.
204.10
204.10
153.10
96.10
153.10
227.80
370.00
295.00
Rs:

Amount
in Rs.
730.68
1632.80
7348.80
288.30
918.60
1708.50
740.00
1770.00
15137.68

Rs:
Rs:
Rs:
Rs:

0.00
81700.31
15137.68
96837.99

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
735.36 cum
cum
(A+B+C+D)/735.36
Rate per

IRR-CAW-3-2

DATA:

Rs:
13557.32
Rs: 110395.31
Rs.
150.10

Providing impervious hearting embankment with soil from approved dump areas in layers
of 25 cm before compaction including cost of all materials, machinery, labour, all
operations such as re-excavation, sorting out, transporting, spreading in layer of specified
thickness, breaking clods, sectioning, watering, compacting each layer to achieve density
control of not less than 95 percent or as stipulated by Sheep foot roller / Vibratory roller/
8 to 10 tonne power roller etc.,complete with initial lead upto 1 km and all lifts.

RATE ANALYSIS

UNIT :

735.36 cum

153

Canal and Allied Works - Item Unit Rates 2014-15

A. MATERIALS:
Sl No

particulars

Unit

Nill

Quantity
0.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No
1
2
3
4
5
6
7

Description

Unit

Angle dozer 90 hp
Fuel / Energy charges
Shovel 0.5 cum
Fuel / Energy charges
Tippers 5 cum
Fuel / Energy charges
Pump 5 hp ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Vibratory Roller 8 tonne
Fuel / Energy charges
Sundries
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Description

Unit

C. LABOUR:
Sl No

Quantity
4.04
4.04
8.00
8.00
48.00
48.00
3.00
3.00
6.00
6.00
6.13
6.13
5.00

Quantity

Crew for Dozer


Hour
4.04
Crew for Shovel
Hour
8.00
Crew for Tipper
Hour
48.00
Crew for Pump
Hour
3.00
Crew for Water tanker
Hour
6.00
Crew for Roller
Hour
6.13
work inspector
Day
2.00
mazdoor
Day
6.00
Total cost of Labour
labour component/unit qty
20.30
Add contractor's profit and overhead charges
0.14 2.80
labour component/unit qty (including contractor's profit)
23.10
1
2
3
4
5
6
7
8

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
1715.50
656.00
1003.10
511.50
446.70
322.20
10.20
85.30
402.50
322.20
1342.20
1108.30
41.00
Rs:

Amount
in Rs.
6930.62
2650.24
8024.80
4092.00
21441.60
15465.60
30.60
255.90
2415.00
1933.20
8227.69
6793.88
205.00
78466.13

Rate
in Rs.
204.10
204.10
153.10
96.10
153.10
227.80
370.00
295.00
Rs:

Amount
in Rs.
824.56
1632.80
7348.80
288.30
918.60
1396.41
740.00
1770.00
14919.48

Rs:
Rs:
Rs:
Rs:

0.00
78466.13
14919.48
93385.60

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
735.36 cum
cum
(A+B+C+D)/735.36
Rate per

IRR-CAW-3-3

Rs:
13073.98
Rs: 106459.58
Rs.
144.80

Providing semi-pervious / pervious casing embankment using soil from approved dump area
in layers of 25 cm before compaction including cost of all materials, machinery, labour,
all operations such as re-excavation, sorting out, transporting, spreading in layer of specified
thickness, breaking clods, sectioning, watering, compacting each layer to density control of
not less than 98 percent or as stipulated by Sheep foot roller / Vibratory roller/
8 to 10 tonne power roller etc., complete with initial lead upto 1 km and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

particulars
Nill

UNIT :
Unit

Quantity
0.00
0.00

768.00 cum
Rate
in Rs.
0.00
0.00

Amount
in Rs.
0.00
0.00

154

Canal and Allied Works - Item Unit Rates 2014-15

Total cost of Materials


B. MACHINERY:
Sl No
1
2
3
4
5
6
7

Description

Unit

Angle dozer 90 hp
Fuel / Energy charges
Shovel 0.50 cum capacity
Fuel / Energy charges
Tippers 5.00 cum capacity 6 Nos
Fuel / Energy charges
Pump 5 hp ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Vibratory Roller 8 tonne
Fuel / Energy charges
Sundries
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Description

Unit

C. LABOUR:
Sl No

Quantity
4.22
4.22
8.00
8.00
48.00
48.00
3.00
3.00
6.00
6.00
7.82
7.82
2.00

Quantity

Crew for Dozer


Hour
4.22
Crew for Shovel
Hour
8.00
Crew for Tipper
Hour
48.00
Crew for Pump
Hour
3.00
Crew for Water tanker
Hour
6.00
Crew for Roller
Hour
7.82
work inspector
Day
2.00
mazdoor
Day
6.00
Total cost of Labour
labour component/unit qty
20.00
Add contractor's profit and overhead charges
0.14 2.80
labour component/unit qty (including contractor's profit)
22.80
1
2
3
4
5
6
7
8

Rs:

0.00

Rate
in Rs.
1715.50
656.00
1003.10
511.50
446.70
322.20
10.20
85.30
402.50
322.20
1342.20
1108.30
41.00
Rs:

Amount
in Rs.
7239.41
2768.32
8024.80
4092.00
21441.60
15465.60
30.60
255.90
2415.00
1933.20
10496.00
8666.91
82.00
82911.34

Rate
in Rs.
204.10
204.10
153.10
96.10
153.10
227.80
370.00
295.00
Rs:

Amount
in Rs.
861.30
1632.80
7348.80
288.30
918.60
1781.40
740.00
1770.00
15341.20

Rs:
Rs:
Rs:
Rs:

0.00
82911.34
15341.20
98252.54

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
768.00 cum
cum
(A+B+C+D)/768
Rate per

IRR-CAW-3-4

Rs:
13755.36
Rs: 112007.90
Rs.
145.80

Providing semi-pervious / pervious casing embankment using soil from approved dump area
in layers of 25 cm before compaction including cost of all materials, machinery, labour,
all operations such as re-excavation, sorting out, transporting, spreading in layer of specified
thickness, breaking clods, sectioning, watering, compacting each layer to density control of
not less than 95 percent or as stipulated by Sheep foot roller / Vibratory roller/
8 to 10 tonne power roller etc., complete with initial lead upto 1 km and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

particulars

UNIT :
Unit

Nill

Quantity
0.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No

Description

Unit

Quantity

768.00 cum
Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate

Amount

155

Canal and Allied Works - Item Unit Rates 2014-15

1
2
3
4
5
6
7

Angle dozer 90 hp
Fuel / Energy charges
Shovel 0.5 cum
Fuel / Energy charges
Tippers 5 cum of 6 Nos
Fuel / Energy charges
Pump 5 hp ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Vibratory Roller 8 tonne
Fuel / Energy charges
Sundries
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Description

Unit

C. LABOUR:
Sl No

Crew for Dozer


Hour
Crew for Shovel
Hour
Crew for Tipper
Hour
Crew for Pump
Hour
Crew for Water tanker
Hour
Crew for Roller
Hour
work inspector
Day
mazdoor
Day
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
1
2
3
4
5
6
7
8

4.22
4.22
8.00
8.00
48.00
48.00
3.00
3.00
6.00
6.00
6.40
6.40
5.00

Quantity
4.22
8.00
48.00
3.00
6.00
6.40
2.00
6.00

0.14

in Rs.
1715.50
656.00
1003.10
511.50
446.70
322.20
10.20
85.30
402.50
322.20
1342.20
1108.30
41.00
Rs:

in Rs.
7239.41
2768.32
8024.80
4092.00
21441.60
15465.60
30.60
255.90
2415.00
1933.20
8590.08
7093.12
205.00
79554.63

Rate
in Rs.
204.10
204.10
153.10
96.10
153.10
227.80
370.00
295.00
Rs:
19.60
2.70
22.30

Amount
in Rs.
861.30
1632.80
7348.80
288.30
918.60
1457.92
740.00
1770.00
15017.72

Rs:
Rs:
Rs:
Rs:

0.00
79554.63
15017.72
94572.35

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
768.00 cum
cum
(A+B+C+D)/768
Rate per
IRR-CAW-3-5

Rs:
13240.13
Rs: 107812.48
Rs.
140.40

Providing semi-pervious / pervious casing embankment using soil from approved dump area
in layers of 25 cm before compaction including cost of all materials, machinery, labour,
all operations such as re-excavation, sorting out, transporting, spreading in layer of specified
thickness, breaking clods, sectioning, compacting each layer without watering to density
control of not less than 95 percent or as stipulated by Sheep foot roller / Vibratory roller/
8 to 10 tonne power roller etc., complete with initial lead upto 1 km and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Nill

Quantity
0.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No
1
2

Description

Angle dozer 90 hp
Fuel / Energy charges
Shovel 0.50 cum capacity
Fuel / Energy charges

Unit
Hour
Hour
Hour
Hour

Quantity
4.22
4.22
8.00
8.00

768.00 cum
Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
1715.50
656.00
1003.10
511.50

Amount
in Rs.
7239.41
2768.32
8024.80
4092.00

156

Canal and Allied Works - Item Unit Rates 2014-15

3
4
5

Tippers 5.00 cum capacity 6 Nos.


Fuel / Energy charges
Vibratory Roller 8 tonne
Fuel / Energy charges
Sundries
Total hire charges of Machinery

Hour
Hour
Hour
Hour
LS

Description

Unit

C. LABOUR:
Sl No
1
2
3
4
5
6

Crew for Dozer


Crew for Shovel
Crew for Tipper
Crew for Roller
work inspector
mazdoor

Hour
Hour
Hour
Hour
Day
Day

48.00 446.70
48.00 322.20
6.40 1342.20
6.40 1108.30
2.00
41.00
Rs:

Quantity
4.22
8.00
48.00
6.40
2.00
6.00

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

21441.60
15465.60
8590.08
7093.12
82.00
74796.93

Rate
in Rs.
204.10
204.10
153.10
227.80
370.00
295.00
Rs:

Amount
in Rs.
861.30
1632.80
7348.80
1457.92
740.00
1770.00
13810.82

Rs:
Rs:
Rs:
Rs:

0.00
74796.93
13810.82
88607.75

18.00
0.14 2.50
20.50

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
768.00 cum
cum
(A+B+C+D)/768
Rate per

Rs:
12405.09
Rs: 101012.84
Rs.
131.50

IRR-CAW-4

EMBANKMENT WORKS USING EXCAVATED SOIL :

IRR-CAW-4-1

Providing impervious hearting embankment with soil collected in embankment area in


heaps as part of disposal of excavated soil from canal including cost of all materials,machinery,
labour, all operations such as sortingout, spreading in layer of 25 cm before compaction,
breaking clods,sectioning, watering and compacting each layer to density control of not less
than 98 percent or as stipulated by Sheep foot roller / Vibratory roller/
8 to 10 tonne power roller etc., complete with lead upto 1 km for water.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Nill

Quantity
0.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No
1
2
3
4
5

C. LABOUR:
Sl No
1

Description

Unit

Angle dozer 90 hp
Fuel / Energy charges
Pump 5 hp ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Vibratory Roller 8 tonne
Fuel / Energy charges
Sundries
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Description

Unit

Crew for Dozer

Hour

Quantity
3.60
3.60
3.00
3.00
5.00
5.00
7.30
7.30
2.00

Quantity
3.60

600.00 cum
Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
1715.50
656.00
10.20
85.30
402.50
322.20
1342.20
1108.30
41.00
Rs:

Amount
in Rs.
6175.80
2361.60
30.60
255.90
2012.50
1611.00
9798.06
8090.59
82.00
30418.05

Rate
in Rs.
204.10

Amount
in Rs.
734.76

157

Canal and Allied Works - Item Unit Rates 2014-15

2
3
4
5
6

Crew for Pump


Hour
Crew for Water tanker
Hour
Crew for Roller
Hour
work inspector
Day
mazdoor
Day
Total cost of Labour
labour component/unit qty
8.30
Add contractor's profit and overhead charges
0.14 1.20
labour component/unit qty (including contractor's profit)
9.50

3.00
5.00
7.30
1.00
4.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
600.00 cum
cum
(A+B+C+D)/600
Rate per

IRR-CAW-4-2

96.10
153.10
227.80
370.00
295.00
Rs:

288.30
765.50
1662.94
370.00
1180.00
5001.50

Rs:
Rs:
Rs:
Rs:

0.00
30418.05
5001.50
35419.55

Rs:
Rs:
Rs.

4958.74
40378.29
67.30

Providing impervious hearting embankment with soil collected in embankment area in


heaps as part of disposal of excavated soil from canal including cost of all materials,machinery,
labour, all operations such as sortingout, spreading in layer of 25 cm before compaction,
breaking clods,sectioning, watering and compacting each layer to density control of not less
than 95 percent or as stipulated by Sheep foot roller / Vibratory roller/
8 to 10 tonne power roller etc., complete with lead upto 1 km for water.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Quantity

Nill

0.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No
1
2
3
4
5

C. LABOUR:
Sl No

Description

Unit

Angle dozer 90 hp
Fuel / Energy charges
Pump 5 hp ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Vibratory Roller 8 tonne
Fuel / Energy charges
Sundries
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Description

Unit

Quantity
3.60
3.60
3.00
3.00
5.00
5.00
6.06
6.06
5.00

Quantity

Crew for Dozer


Hour
Crew for Pump
Hour
Crew for Water tanker
Hour
Crew for Roller
Hour
work inspector
Day
mazdoor
Day
Total cost of Labour
labour component/unit qty
8.50
Add contractor's profit and overhead charges
0.14 1.20
labour component/unit qty (including contractor's profit)
9.70
1
2
3
4
5
6

3.60
3.00
5.00
6.06
2.00
4.00

600.00 cum
Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
1715.50
656.00
10.20
85.30
402.50
322.20
1342.20
1108.30
41.00
Rs:

Amount
in Rs.
6175.80
2361.60
30.60
255.90
2012.50
1611.00
8133.73
6716.30
205.00
27502.43

Rate
in Rs.
204.10
96.10
153.10
227.80
370.00
295.00
Rs:

Amount
in Rs.
734.76
288.30
765.50
1380.47
740.00
1180.00
5089.03

ABSTRACT:

158

Canal and Allied Works - Item Unit Rates 2014-15

A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
600.00 cum
cum
(A+B+C+D)/600
Rate per

IRR-CAW-4-3

Rs:
Rs:
Rs:
Rs:

0.00
27502.43
5089.03
32591.46

Rs:
Rs:
Rs.

4562.8
37154.26
61.90

Providing semi-pervious / pervious casing hearting embankment using soil collected in


heaps in embankment area as part of disposal of excavated soil from canal including cost of
all materials, machinery, labour, all operations such as sorting-out, spreading in layers of 25
cm before compaction, breaking clods, sectioning, watering and compacting each layer
to density control of not less than 98 percent or as stipulated by Sheep foot roller / Vibratory roller/
8 to 10 tonne power roller etc., complete with lead upto 1 km for water.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Quantity

Nill

0.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No
1
2
3
4
5

C. LABOUR:
Sl No

Description

Unit

Angle dozer 90 hp
Fuel / Energy charges
Pump 5 hp ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Vibratory Roller 8 tonne
Fuel / Energy charges
Sundries
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Description

Unit

Quantity
3.60
3.60
3.00
3.00
5.00
5.00
7.30
7.30
2.00

Quantity

Crew for Dozer


Hour
Crew for Pump
Hour
Crew for Water tanker
Hour
Crew for Roller
Hour
work inspector
Day
mazdoor
Day
Total cost of Labour
labour component/unit qty
8.30
Add contractor's profit and overhead charges
0.14 1.20
labour component/unit qty (including contractor's profit)
9.50
1
2
3
4
5
6

3.60
3.00
5.00
7.30
1.00
4.00

600.00 cum
Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
1715.50
656.00
10.20
85.30
402.50
322.20
1342.20
1108.30
41.00
Rs:

Amount
in Rs.
6175.80
2361.60
30.60
255.90
2012.50
1611.00
9798.06
8090.59
82.00
30418.05

Rate
in Rs.
204.10
96.10
153.10
227.80
370.00
295.00
Rs:

Amount
in Rs.
734.76
288.30
765.50
1662.94
370.00
1180.00
5001.50

Rs:
Rs:
Rs:
Rs:

0.00
30418.05
5001.50
35419.55

Rs:
Rs:
Rs.

4958.74
40378.29
67.30

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
600.00 cum
cum
(A+B+C+D)/600
Rate per

159

Canal and Allied Works - Item Unit Rates 2014-15

IRR-CAW-4-4

Providing semi-pervious / pervious casing embankment using soil collected in heaps in


embankment area as part of disposal of excavated soil from canal including cost of all
materials, machinery, labour, all operations such as sorting-out, spreading in layers of 25
cm before compaction, breaking clods, sectioning, watering and compacting each layer
to density control of not less than 95 percent or as stipulated by Sheep foot roller / Vibratory roller/
8 to 10 tonne power roller etc., complete with lead upto 1 km for water.

RATE ANALYSIS

DATA:
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Quantity

Nill

0.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No
1
2
3
4
5

Description

Unit

Angle dozer 90 hp
Fuel / Energy charges
Pump 5 hp ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Vibratory Roller 8 tonne
Fuel / Energy charges
Sundries
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Description

Unit

C. LABOUR:
Sl No

Quantity
3.60
3.60
3.00
3.00
5.00
5.00
6.1
6.1
5.00

Quantity

Crew for Dozer


Hour
Crew for Pump
Hour
Crew for Water tanker
Hour
Crew for Roller
Hour
work inspector
Day
mazdoor
Day
Total cost of Labour
labour component/unit qty
8.50
Add contractor's profit and overhead charges
0.14 1.20
labour component/unit qty (including contractor's profit)
9.70
1
2
3
4
5
6

3.60
3.00
5.00
6.1
2.00
4.00

600.00 cum
Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
1715.50
656.00
10.20
85.30
402.50
322.20
1342.20
1108.30
41.00
Rs:

Amount
in Rs.
6175.80
2361.60
30.60
255.90
2012.50
1611.00
8133.73
6716.30
205.00
27502.43

Rate
in Rs.
204.10
96.10
153.10
227.80
370.00
295.00
Rs:

Amount
in Rs.
734.76
288.30
765.50
1380.47
740.00
1180.00
5089.03

Rs:
Rs:
Rs:
Rs:

0.00
27502.43
5089.03
32591.46

Rs:
Rs:
Rs.

4562.8
37154.26
61.90

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
600.00 cum
cum
(A+B+C+D)/600
Rate per

IRR-CAW-4-5

Providing semi-pervious / pervious casing embankment using soil collected in heaps in


embankment area as part of disposal of excavated soil from canal including cost of all
materials, machinery, labour, all operations such as sorting-out, spreading in layers of 25
cm before compaction, breaking clods, sectioning and compacting each layer without
watering to density control of not less than 95 percent or as stipulated by Sheep foot roller /
Vibratory roller/ 8 to 10 tonne power roller etc., complete.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Quantity

600.00 cum
Rate

Amount

160

Canal and Allied Works - Item Unit Rates 2014-15

Nill

0.00

Total cost of Materials


B. MACHINERY:
Sl No
1
2
3

Description

Unit

Angle dozer 90 hp
Fuel / Energy charges
Vibratory Roller 8 tonne
Fuel / Energy charges
Sundries
Total hire charges of Machinery

Hour
Hour
Hour
Hour
LS

Description

Unit

C. LABOUR:
Sl No
1
2
3
4

Crew for Dozer


Crew for Roller
work inspector
mazdoor

Quantity
3.60
3.60
6.06
6.06
2.00

Quantity

Hour
Hour
Day
Day

3.60
6.06
1.00
4.00

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

in Rs.
0.00
0.00
Rs:

0.00

Rate
in Rs.
1715.50
656.00
1342.20
1108.30
41.00
Rs:

Amount
in Rs.
6175.80
2361.60
8133.73
6716.30
82.00
23469.43

Rate
in Rs.
204.10
227.80
370.00
295.00
Rs:

Amount
in Rs.
734.76
1380.47
370.00
1180.00
3665.23

Rs:
Rs:
Rs:
Rs:

0.00
23469.43
3665.23
27134.66

Rs:
Rs:
Rs.

3798.85
30933.51
51.60

6.10
0.14 0.90
7.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
600.00 cum
cum
(A+B+C+D)/600
Rate per
IRR-CAW-4-6

in Rs.

Providing compacted embankment for field irrigation channels with gravely soil from
approved borrow area including sorting out, spreading in layers of 15 cm thickness, breaking
clods, watering, compacting, dressing sides to required slopes etc.,complete with lead upto
50 m and all lifts.

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Nill

Quantity
0.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No
1

C. LABOUR:
Sl No
1
2
3
4

Description

Unit

5 hp pump ( diesel )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour

Description

Unit

Crew for pump


work inspector
Crowbarman for loosening soil
mazdoor
For excavation at borrow area

Quantity
1.00
1.00

Quantity

25.00 cum
Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.

Rate
in Rs.
10.20
85.30
Rs:

Amount
in Rs.
10.20
85.30
95.50

Amount
in Rs.
96.10
370.00
862.50
1475.00

Hour
Day
Day

1.00
1.00
2.50

Rate
in Rs.
96.10
370.00
345.00

Day

5.00

295.00

0.00

161

Canal and Allied Works - Item Unit Rates 2014-15

For spreading / levelling / sectioning


for loading soil

Day
Day

2.50
5.00

295.00
295.00

737.50
1475.00

Cartman with Bullock cart for water


Day
1.00
Bullock drawn roller for rolling
Day
1.00
Total cost of Labour
labour component/unit qty
230.20
Add contractor's profit and overhead charges
0.14 32.20
labour component/unit qty (including contractor's profit)
262.40

370.00
370.00
Rs:

370.00
370.00
5756.10

Rs:
Rs:
Rs:
Rs:

0.00
95.50
5756.10
5851.60

Rs:
Rs:
Rs.

819.22
6670.82
266.80

5
6

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
25.00 cum
cum
(A+B+C+D)/25
Rate per
IRR-CAW-5

FOUNDATION FILLING WORKS :

IRR-CAW-5-1

Providing rubble and sand filling in layers of 22.5 to 30 cm including cost of all materials,
machinery, labour, watering, ramming etc., complete with initial lead upto 50 m and all lifts.

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

UNIT :

particulars

Unit

Rubble stones at quarry


Sand for filling
Total cost of Materials

cum
cum

B. MACHINERY:
Sl No

Description

Unit

Nil

Quantity
10.00
4.00

Quantity
0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No
1

Description
mazdoor

Unit
Day

Quantity
4.00

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

10.00 cum
Rate
in Rs.
318.00
342.00
Rs:

Amount
in Rs.
3180.00
1368.00
4548.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
295.00
Rs:

Amount
in Rs.
1180.00
1180.00

Rs:
Rs:
Rs:
Rs:

4548.00
0.00
1180.00
5728.00

Rs:
Rs:
Rs.

801.92
6529.92
653.00

118.00
0.14 16.50
134.50

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
10.00 cum
cum
(A+B+C+D)/10
Rate per

IRR-CAW-5-2

Providing rubble and Murum filling in layers of 22.5 to 30 cm including cost of all materials,
machinery, labour, watering, ramming etc., complete with initial lead upto 50 m and all lifts.

162

Canal and Allied Works - Item Unit Rates 2014-15

RATE ANALYSIS

DATA
A. MATERIALS:
Sl No
1
2

UNIT :

particulars

Unit

Rubble stones at quarry


Murum
Total cost of Materials

cum
cum

B. MACHINERY:
Sl No

Description

Unit

Quantity
10.00
4.00

Quantity

Nil

0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No
1

Description
mazdoor

Unit

Quantity

Day

4.00

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

10.00 cum
Rate
in Rs.
318.00
107.00
Rs:

Amount
in Rs.
3180.00
428.00
3608.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
295.00
Rs:

Amount
in Rs.
1180.00
1180.00

Rs:
Rs:
Rs:
Rs:

3608.00
0.00
1180.00
4788.00

Rs:
Rs:
Rs.

670.32
5458.32
545.80

118.00
0.14 16.50
134.50

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
10.00 cum
cum
(A+B+C+D)/10
Rate per

IRR-CAW-5-3

Providing and laying 25 cm thick sand blanket below embankment including cost of all
materials, machinery, labour, spreading to specified thickness etc., complete with initial lead
upto 50 m and all lifts.

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No
1

particulars

Sand for Filling

UNIT :
Unit
cum

Quantity
25.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No

Description

Unit

Quantity

Nil

0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No
1

Description
mazdoor

Unit

Quantity

Day
Total cost of Labour

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

5.00

100.00 sqm
Rate
in Rs.
342.00
0.00
Rs:

Amount
in Rs.
8550.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
295.00
Rs:

Amount
in Rs.
1475.00
1475.00

8550.00

14.80
0.14 2.10
16.90

ABSTRACT:

163

Canal and Allied Works - Item Unit Rates 2014-15

A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
100.00 sqm
sqm
(A+B+C+D)/100
Rate per

Rs:
Rs:
Rs:
Rs:

8550.00
0.00
1475.00
10025.00

Rs:
Rs:
Rs.

1403.5
11428.50
114.30

IRR-CAW-5-3-A Providing and laying sand blanket below embankment including cost of all
(New Item3- 2011-12)
materials, machinery, labour, spreading to specified thickness etc., complete with initial lead

upto 50 m and all lifts.

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No
1

particulars

Sand for Filling

UNIT :
Unit
cum

Quantity
100.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No

Description

Unit

Quantity

Nil

0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No
1

Description
mazdoor

Unit
Day

Quantity
20.00

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

100.00 cum
Rate
in Rs.
342.00
0.00
Rs:

Amount
in Rs.
34200.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
295.00
Rs:

Amount
in Rs.
5900.00
5900.00

Rs:
Rs:
Rs:
Rs:

34200.00
0.00
5900.00
40100.00

Rs:
Rs:
Rs.

5614
45714.00
457.10

59.00
0.14 8.30
67.30

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
100.00 cum
cum
(A+B+C+D)/100
Rate per
IRR-CAW-5-4

34200.00

Providing and constructing dry rubble rock-toe using rubble and stone chips from
approved source including cost of all materials, machinery, labour, hand packing rubble
and stone chips, finishing top and sides to required slopes etc., complete with initial lead upto
50 m and all lifts.

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3

particulars

Rubble
Stone chips
Sundries

UNIT :
Unit
cum
cum
LS

Total cost of Materials

Quantity
100.00
15.00
2.00

100.00 cum
Rate
in Rs.
318.00
340.00
41.00
Rs:

Amount
in Rs.
31800.00
5100.00
82.00
36982.00

B. MACHINERY:

164

Canal and Allied Works - Item Unit Rates 2014-15

Sl No

Description

Nil

Unit

Quantity
0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No
1
2
3

Description
work inspector
Mason Class-II
mazdoor

Unit
Day
Day
Day

Quantity
1.00
7.00
19.00

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.

Rate
in Rs.
370.00
345.00
295.00
Rs:

Amount
in Rs.
370.00
2415.00
5605.00
8390.00

Rs:
Rs:
Rs:
Rs:

36982.00
0.00
8390.00
45372.00

Rs:
Rs:
Rs.

6352.08
51724.08
517.20

83.90
0.14 11.70
95.60

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
100.00 cum
(A+B+C+D)/100
cum
Rate per

IRR-CAW-5-5

0.00

Providing and constructing longitudinal and cross graded filter drains using sand and
20 mm down graded aggregates satisfying specified filter creteria in layers as per specifications
including cost of all materials, machinery, labour, laying to required slopes, compaction etc.,
complete with initial lead upto 50 m and all lifts.

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Quantity

100.00 cum
Rate
in Rs.
462.00

Amount
in Rs.
35481.60
21054.00

Sand (Un-Screened )

cum

76.80

Coarse aggregate 20-10 mm 75 %

cum

17.40 1210.00

Coarse aggregate 10 mm down 25 %


Total cost of Materials

cum

B. MACHINERY:
Sl No

Description

Unit

Nil

5.80

Quantity
0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No
1
2

Description
work inspector
mazdoor

Unit
Day
Day

Quantity
1.00
36.00

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

875.00
Rs:

5075.00
61610.60

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.

Rate
in Rs.
370.00
295.00
Rs:

Amount
in Rs.
370.00
10620.00
10990.00

Rs:
Rs:
Rs:

61610.60
0.00
10990.00

0.00

109.90
0.14 15.40
125.30

165

Canal and Allied Works - Item Unit Rates 2014-15

Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
100.00 cum
cum
(A+B+C+D)/100
Rate per

IRR-CAW-5-6

DATA:

Rs:

72600.60

Rs:
Rs:
Rs.

10164.08
82764.68
827.60

Laying Longitudinal Drains and Transverse drains of Size 600 x600 x750 mm in Bed and
filling with 12 mm to 40 mm HG machine Crushed metal and sand in bed including
Excavation of drains and Cost of procuring of all materials including 50 m lead and for all lifts.
RATE ANALYSIS
A. MATERIALS:
Particulars
Sl.No
12 mm to 40 mm metal
1
2
Sand (Un-Screened )
Total cost of Materials
B. MACHINERY
Description
Sl.No
1

Unit
Cum
cum

Unit

Excavation of drain with Excavator


Total hire charges of Machinery

Unit:
Qty

100 mt
Rate in RAmount in Rs.
13.5 1145.00
15457.50
36 462.00
16632.00
Rs.
32089.5

Quantity

Cum

45

Rate in RAmount in Rs.


35.00
Total Rs.

1575.00
1575

C. LABOUR
Sl.No
1
2

Particulars
Rate in RAmount in Rs.
Unit
Qty
Labour for Sand laying
Cum
5.14 295.00
1516.30
Labour for Metal laying
Cum
1.93 295.00
569.35
Total cost of Labour
Rs.
2085.65
labour component/unit qty
20.90
Add contractor's profit and overhead charges
0.14 2.90
labour component/unit qty (including contractor's profit)
23.80
ABSTRACT
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs.
Rs.
Rs.
Total
Rs:

D. Add for contractor's profit and overheads on (A+B+C)


14%
Total cost for
100.00 mt
mt
(A+B+C+D)/100
Rate per

IRR-CAW-5-7

Rs:
Rs:
Rs.

32089.5
1575
2085.65
35750.15
5005.02
40755.17
407.60

Laying and fixing of 100 mm Dia 300 mm long precast porus CC plugs in bed and sides
using 1.181 Kgs of cement per each using 20 mm HG metal and placing in local filters of size
600x600x750 mm in size including Excavation of drains and Cost of procuring of all materials
including 50 m lead and for all lifts.

DATA

Rate Analysis

Unit

1 Plug

A. MATERIALS:
Sl.No
1
2
3

Particulars
Coarse aggregate
Sand (Un-Screened )
Cement
Total cost of Materials

Unit
Cum
cum
Kg

Rate in Amount in
Qty
Rs
Rs.
0.08 1210.00
97.28
0.203 462.00
93.79
1.181
4.00
4.72
Rs.
195.79

B. MACHINERY
Sl.No
1
2

Description
Excavation of drain with Excavator
Machine mixing Charges
Total hire charges of Machinery

Unit
Cum
Cum

Quantity
0.27
0.003

Rate in
Rs.
35.00
328.60
Total Rs.

Amount in
Rs.
9.45
0.99
10.44

166

Canal and Allied Works - Item Unit Rates 2014-15

C. LABOUR
Rate in Amount in
Sl.No
Particulars
Unit
Qty
Rs
Rs.
1
Mazdoor
Day
0.30 295.00
88.50
Total cost of Labour
Rs.
88.50
labour component/unit qty
88.50
Add contractor's profit and overhead charges
0.14 12.40
labour component/unit qty (including contractor's profit)
100.90
ABSTRACT
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs.
Rs.
Rs.
Total
Rs:

D. Add for contractor's profit and overheads on (A+B+C)


14%
Total cost for
1.00 Plug
each plug
(A+B+C+D)/1.0
Rate per

IRR-CAW-5-8

195.79
10.44
88.50
294.73

Rs:
Rs:
Rs.

41.26
335.99
336.00

Providing and constructing 0.50 m thick vertical or inclined graded filter media consisting of
15 cm thick sand layers and 20 cm thick 20 mm down coarse aggregate layer using approved
materials satisfying specified filter creteria as per specifications including cost of all materials,
machinery, labour, laying to required slope, compaction etc., complete with initial lead upto
50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Quantity

100.00 cum
Rate
in Rs.
462.00

Amount
in Rs.
27720.00

Sand (Un-Screened )

cum

60.00

Coarse aggregate 20-10 mm 75 %

cum

30.00 1210.00

36300.00

Coarse aggregate 10 mm down 25 %


Total cost of Materials

cum

10.00

875.00
Rs:

8750.00
72770.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
370.00
295.00
Rs:

Amount
in Rs.
370.00
10620.00
10990.00

Rs:
Rs:
Rs:
Rs:

72770.00
0.00
10990.00
83760.00

Rs:
Rs:
Rs.

11726.4
95486.40
954.90

B. MACHINERY:
Sl No

Description

Unit

Nil

Quantity
0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No
1
2

Description
work inspector
mazdoor

Unit
Day
Day

Quantity
1.00
36.00

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

109.90
0.14 15.40
125.30

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
100.00 cum
cum
(A+B+C+D)/100.0
Rate per

167

Canal and Allied Works - Item Unit Rates 2014-15

IRR-CAW-5-9

Providing and constructing graded filter media below and behind rock-toe consisting of
20 cm thick sand, 15 cm thick 20 mm down and 15 cm thick 40 mm down size graded coarse
aggregates satisfying filter creteria behind rock-toe and 15 cm thick sand, 20 cm thick 20 mm
down coarse aggregate and 65 cm thick 40 mm down size coarse aggregate satisfying filter
creiteria below rock-toe as per specifications including cost of all materials, machinery, labour,
laying to required slope, compaction etc., complete with initial lead upto 50 m and all lifts.

RATE ANALYSIS

DATA:
A. MATERIALS:
Sl No
1
2
3
4

UNIT :

particulars

Unit

Sand (Un-Screened )
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm down
Total cost of Materials

cum
cum
cum
cum

B. MACHINERY:
Sl No

Description

Unit

Nil

Quantity
58.77
52.70
50.70
13.80

Quantity
0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No
1
2

Description
work inspector
mazdoors

Unit
Day
Day

Quantity
1.00
60.00

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

176.00 cum
Rate
Amount
in Rs.
in Rs.
462.00
27151.74
1145.00
60341.50
1210.00
61347.00
875.00
12075.00
Rs: 160915.24

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
370.00
295.00
Rs:

Amount
in Rs.
370.00
17700.00
18070.00

102.70
0.14 14.40
117.10

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
176.00 cum
cum
(A+B+C+D)/176.0
Rate per

Rs: 160915.24
Rs:
0.00
Rs:
18070.00
Rs: 178985.24
Rs:
25057.93
Rs: 204043.17
Rs.
1159.30

IRR-CAW-5-10 Providing and laying filter media consisting of 2 layers of poly-propeline nonwoven filter
(a)
fabric and 200 mm thick 20 mm down graded coarse aggregate for embankment including
cost of all materials, machinery, labour, forming toe drain etc., complete with lead upto 50 m
a. for aggregate and all leads for fabric and all lifts.
Using 200 gsm filter fabric.

168

Canal and Allied Works - Item Unit Rates 2014-15

RATE ANALYSIS

DATA:
A. MATERIALS:
Sl No
1
2

particulars

PP filter fabric 200 gsm


20 - 10 mm CA @ 75 %
10 mm down CA @ 25 %
Total Cost of materials

B. MACHINERY:
Sl No

Description

UNIT :
Unit
sqm
cum
cum

Unit

Quantity

Rate
in Rs.
210.00 132.00
15.00 1210.00
5.00 875.00
Rs:

Quantity

Nil

0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No
1
2

Description
work inspector
mazdoor

Unit

Quantity

Day
Day

1.00
7.00

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

100.00 sqm
Amount
in Rs.
27720.00
18150.00
4375.00
50245.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
370.00
295.00
Rs:

Amount
in Rs.
370.00
2065.00
2435.00

Rs:
Rs:
Rs:
Rs:

50245.00
0.00
2435.00
52680.00

Rs:
Rs:
Rs.

7375.2
60055.20
600.60

24.40
0.14 3.40
27.80

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
100.00 sqm
sqm
(A+B+C+D)/100.0
Rate per

IRR-CAW-5-11 Providing and laying filter media consisting of 2 layers of poly-propeline nonwoven filter
(b)
fabric and 200 mm thick 20 mm down graded coarse aggregate for embankment including
cost of all materials, machinery, labour, forming toe drain etc., complete with lead upto 50 m
for aggregate and all leads for fabric and all lifts.
b. Using 250 gsm filter fabric.

Data

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

particulars

Unit

PP filter fabric 250 gsm


20 - 10 mm CA @ 75 %
10 mm down CA @ 25 %
Total cost of Materials

sqm
cum
cum

B. MACHINERY:
Sl No
1

UNIT :

Description

Unit

Nil

Quantity

Rate
in Rs.
210.00 154.00
15.00 1210.00
5.00 875.00
Rs:

Quantity
0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No

Description

Unit

100.00 sqm

Quantity

Amount
in Rs.
32340.00
18150.00
4375.00
54865.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate

Amount

169

Canal and Allied Works - Item Unit Rates 2014-15

1
2

work inspector
mazdoor

Day
Day

1.00
7.00

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

in Rs.
370.00
295.00
Rs:

in Rs.
370.00
2065.00
2435.00

Rs:
Rs:
Rs:
Rs:

54865.00
0.00
2435.00
57300.00

Rs:
Rs:
Rs.

8022
65322.00
653.20

24.40
0.14 3.40
27.80

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
100.00 sqm
sqm
(A+B+C+D)/100.0
Rate per
IRR-CAW-6

ROCK FILL WORKS :

IRR-CAW-6-1

Providing and constructing rockfill casing to canal embankment with graded stones and
spalls from approved quarry including cost of all materials, machinery, labour, spreading
stones and spalls in layers, hand packing, wedging, finishing surface to required slopes etc.,
complete with initial lead upto 50 m and all lifts.

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

UNIT :

particulars

Unit

Rubble stones ( at quarry )


Stone chips / spalls ( at quarry )
Total cost of Materials

cum

B. MACHINERY:
Sl No

Description

Unit

Quantity
100.00
15.00

Quantity

Nil

0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No
1
2

Description
Mason Cl- II
mazdoor

Unit

Quantity

Day
Day

6.00
8.00

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

100.00 cum
Rate
in Rs.
318.00
340.00
Rs:

Amount
in Rs.
31800.00
5100.00
36900.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
345.00
295.00
Rs:

Amount
in Rs.
2070.00
2360.00
4430.00

Rs:
Rs:
Rs:
Rs:

36900.00
0.00
4430.00
41330.00

Rs:
Rs:
Rs.

5786.2
47116.20
471.20

44.30
0.14 6.20
50.50

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
100.00 cum
cum
(A+B+C+D)/100.0
Rate per

IRR-CAW-6-2

Providing and constructing rockfill casing to canal embankment with graded stones and
spalls available in dump yard (spoil bank) including cost of all materials, machinery, labour, spreading
stones and spalls in layers, hand packing, wedging, finishing surface to required slopes etc.,
complete with initial lead upto 50 m and all lifts.

170

Canal and Allied Works - Item Unit Rates 2014-15

Note:

Stones and spalls available in dump yard shall be issued at specified issue rate.

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

Rubble stones at dump yard

Stone chips ( spalls ) at dump yard


Total cost of Materials

B. MACHINERY:
Sl No

Description

UNIT :
Unit
cum

Quantity
100.00

Unit

Quantity
0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No
1
2
3

Description
Mason Cl- II
Crowbarman
mazdoor

Rate
in Rs.
155.00

Amount
in Rs.
15500.00

175.00
Rs:

2625.00
18125.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
345.00
345.00
295.00
Rs:

Amount
in Rs.
2070.00
690.00
2950.00
5710.00

Rs:
Rs:
Rs:
Rs:

18125.00
0.00
5710.00
23835.00

Rs:
Rs:
Rs.

3336.9
27171.90
271.70

15.00

Nil

100.00 cum

Unit
Day
Day
Day

Quantity
6.00
2.00
10.00

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

57.10
0.14 8.00
65.10

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
100.00 cum
cum
(A+B+C+D)/100.0
Rate per
IRR-CAW-7

CANAL LINING WORKS :

IRR-CAW-7-1

Providing cohesive non-swelling ( CNS ) soil lining to canals using soil from approved borrow
area including spreading soil in layers of thickness not more than 15 cm, breaking clods,
watering, compacting to density control of not less than 98 percent or as stipulated,
dressing to required profile etc., complete with initial lead upto 1 km and all lifts.

DATA:

Capacity of shovel bucket


Capacity of shovel bucket under heaped condition
Capacity of tipper
Lead for conveyance of soil
Speed for loaded tipper under haul road condition
Speed for empty tipper under haul road condition
Turning and unloading time
Shovel digging and loading cycle per bucket
In-situ qty / bucket for 15 % bulkage of soil ( 0.58 /1.15 )
In-situ quantity per load for 20 % bulkage of soil ( 5.0 /1.2 )
Number of buckets per load ( 4.00 / 0.50 )
Cycle time for loading 8 buckets ( 8 x 32 / 60 )
Round trip cycle time for tipper:
Ideal cycle time of shovel for digging & loading
Time for 1km haulage under load ( 60 / 20 )
Time for turning and un-loading
Time for 1 km return trip ( 60 / 25 )
Time for turning and spotting

:
:
:
:
:
:
:
:
:
say :
say :
say :

0.50
0.58
5.00
1
20
25
2.00
32
0.50
4.00
8
4.30

cum
cum
cum
km
km / hr
km / hr
min
sec
cum
cum
buckets
min

:
:
:
:
:

4.30
3.00
2.00
2.40
0.50

min
min
min
min
min

171

Canal and Allied Works - Item Unit Rates 2014-15

Total
:
12.20 min
No. of tippers to match corrected cycle time of shovel ( 12.60 / 4.00 )
:
3 Nos
Output of tipper / hr with 50 min working / hr ( 50 x 4.00 / 12.20 )
:
16.40 cum
Output for 3 tippers per day ( 3 x 16.40 x 8 )
say :
394 cum
Stripping of borrow area :
Generally borrow area is stripped once in a week for 6 days requirement of soil.
Area to be stripped assuming 2.0 m depth of cut ( 394 x 6 / 2.0 )
:
1182 sqm
Depth of stripping
:
0.2 m
Quantity of stripping considering 5 % extra area ( 1182x1.05x0.20 )
:
248 cum
Output of dozer per hr with 50 min / hr working for stripping
:
72 cum
Time required for stripping 248 cum
:
3.5 hours
Consider 5 hours including time for levelling stripped siol / shifting time.
Requirement of dozer for one day work of 394 cum
say :
1.00 hours
Collection of soil for embankment:
Deploy one 0.50 cum capacity shovel for 8 hours for digging and loading soil.
Deploy 3 tippers of 5.00 cum capacity for 8 hours to convey soil to embankment area.
Spreading soil in 15 cm layer:
In view of narrow width spreading soil by dozer is generally not be possible.
Soil collected in heaps along the edge of the canal can be pushed down by dozer to the extent
required and further spreading in layers of specified thickness has to be carried out by manual
labour. Deploy dozer for 2.00 hour for pushing soil.
Output of mazdoor for levelling per day
:
20 cum
Consider 27 mazdoors for levelling 551.6 cum soil including extra soil to be laid for roller
margin.
Watering;
Generally soil in the borrow area will be in moist condition. In the beginning of the season no
watering may be necessary and in summer months about 8 to 10 percent watering may be
needed to maintain soil moisture within OMC plus or minus 3 percent limit. Assuming seasonal
average of 5 % watering by weight, the daily requirement of water for 394 cum of embankment
will be about 4 tanker loads of 8000 ltrs each.
Deploy 8000 ltr capacity water tanker for 4 hours daily for watering before rolling.
Consider 2 mazdoors for spraying water.
Compaction:
Since dozer is not considered for spreading soil about 25 percent extra roller passes needed.
Generally about 10 to 12 passes of diesel road roller is adequate for achieving 98 percent density
control for 25 cm thick loose layer.
Effective length of roller drum
:
1.50 m
Speed of roller per hour
:
3.00 km
Thickness of layer
:
0.15 m
Number of roller passes to achieve specified density control
:
12 Nos
Output of roller / hr with 50 min /hr working and 75 % effenciancy
50 / 60 ( 1.5 x 3000 x 0.15 x 0.75 / 12 )
35.15625 say :
35.15 cum/hour
Time for rolling 394 cum spread soil
11.2091 say :
11.5 hours
Sorting out/ sectioning etc :
Assume 4 mazdoors for sorting out.
No extra labour required for sectioning as trimming roller margin forms part of the soil collection
for bed lining.However 5 mazdoors considered for finishing to required slopes.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Nil

Quantity
0.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No
1
2
3
4

Description

Shovel 0.5 cum


Fuel / Energy charges
Angle dozer 90 hp
Fuel / Energy charges
Tipper 5 cum
Fuel / Energy charges
Pump 5 hp ( diesel )

Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour

Quantity
8.00
8.00
3.00
3.00
24.00
24.00
4.00

394.00 cum
Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
1003.10
511.50
1715.50
656.00
446.70
322.20
10.20

Amount
in Rs.
8024.80
4092.00
5146.50
1968.00
10720.80
7732.80
40.80

172

Canal and Allied Works - Item Unit Rates 2014-15

5
6
7

Fuel / Energy charges


Water tanker 8000 ltr
Fuel / Energy charges
Diesel road roller 8-10 tonne
Fuel / Energy charges
Sundries
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
LS

Description

Unit

C. LABOUR:
Sl No

4.00
4.00
4.00
11.50
11.50
5.00

Quantity

Crew for Shovel


Hour
8.00
Crew for Dozer
Hour
3.00
Crew for Tipper
Hour
24.00
Crew for Pump
Hour
4.00
Crew for Water tanker
Hour
4.00
Crew for Road roller
Hour
11.50
work inspector
Day
2.00
mazdoor
Day
38.00
Total cost of Labour
labour component/unit qty
53.20
Add contractor's profit and overhead charges
0.14 7.40
labour component/unit qty (including contractor's profit)
60.60
1
2
3
4
5
6
7
8

85.30
402.50
322.20
197.20
767.30
41.00
Rs:

341.20
1610.00
1288.80
2267.80
8823.95
205.00
52262.45

Rate
in Rs.
204.10
204.10
153.10
96.10
153.10
182.20
370.00
295.00
Rs:

Amount
in Rs.
1632.80
612.30
3674.40
384.40
612.40
2095.30
740.00
11210.00
20961.60

Rs:
Rs:
Rs:
Rs:

0.00
52262.45
20961.60
73224.05

Rs:
Rs:
Rs.

10251.37
83475.42
211.90

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
394.00 cum
cum
(A+B+C+D)/394.0
Rate per

IRR-CAW-7-2

Providing cohesive non-swelling ( CNS ) soil lining to canals using soil from approved borrow
area including spreading soil in layers of thickness not more than 15 cm, breaking clods,
watering, compacting to density control of not less than 95 percent or as stipulated,
dressing to required profile etc., complete with initial lead upto 1 km and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Nil

Quantity
0.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No
1
2
3
4
5
6

Description

Shovel 0.5 cum


Fuel / Energy charges
Angle dozer 90 hp
Fuel / Energy charges
Tippers 5 cum
Fuel / Energy charges
Pump 5 hp ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Diesel road roller 8-10 tonnes
Fuel / Energy charges

Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour

Quantity
8.00
8.00
3.00
3.00
24.00
24.00
4.00
4.00
4.00
4.00
10.00
10.00

394.00 cum
Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
1003.10
511.50
1715.50
656.00
446.70
322.20
10.20
85.30
402.50
322.20
197.20
767.30

Amount
in Rs.
8024.80
4092.00
5146.50
1968.00
10720.80
7732.80
40.80
341.20
1610.00
1288.80
1972.00
7673.00

173

Canal and Allied Works - Item Unit Rates 2014-15

Sundries
Total hire charges of Machinery

LS

Description

Unit

C. LABOUR:
Sl No

5.00

Quantity

Crew for Shovel


Hour
8.00
Crew for Dozer
Hour
3.00
Crew for Tipper
Hour
24.00
Crew for Pump
Hour
4.00
Crew for Water tanker
Hour
4.00
Crew for Road roller
Hour
10.00
work inspector
Day
2.00
mazdoor
Day
38.00
Total cost of Labour
labour component/unit qty
52.50
Add contractor's profit and overhead charges
0.14 7.40
labour component/unit qty (including contractor's profit)
59.90
1
2
3
4
5
6
7
8

41.00
Rs:

205.00
50815.70

Rate
in Rs.
204.10
204.10
153.10
96.10
153.10
182.20
370.00
295.00
Rs:

Amount
in Rs.
1632.80
612.30
3674.40
384.40
612.40
1822.00
740.00
11210.00
20688.30

Rs:
Rs:
Rs:
Rs:

0.00
50815.70
20688.30
71504.00

Rs:
Rs:
Rs.

10010.56
81514.56
206.90

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
394.00 cum
cum
(A+B+C+D)/394.0
Rate per

IRR-CAW-7-3

Providing cohesive non-swelling ( CNS ) soil lining to canal using soil collected in heaps
along the edge of canal requiring CNS soil lining as part of the disposal of excavated soil from
canal excavation in CNS soil reach including spreading in layers of thickness not more than
15 cm, breaking clods, watering, compacting to density control of not less than 95 percent
or as stipulated, dressing to required profile etc., complete with lead upto upto 50 m and all
lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Nil

Quantity
0.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No
1
2
3
4
5

C. LABOUR:
Sl No
1
2
3

Description

Unit

Angle Dozer 90 hp
Fuel / Energy charges
Pump 5 hp ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Diesel road roller 8-10 tonne
Fuel / Energy charges
Sundries
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Description

Unit

Crew for Dozer


Crew for Pump
Crew for Water tanker

Hour
Hour
Hour

Quantity
1.50
1.50
5.00
5.00
5.00
5.00
13.00
13.00
5.00

Quantity
1.50
5.00
5.00

394.00 cum
Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
1715.50
656.00
10.20
85.30
402.50
322.20
197.20
767.30
41.00
Rs:

Amount
in Rs.
2573.25
984.00
51.00
426.50
2012.50
1611.00
2563.60
9974.90
205.00
20401.75

Rate
in Rs.
204.10
96.10
153.10

Amount
in Rs.
306.15
480.50
765.50

174

Canal and Allied Works - Item Unit Rates 2014-15

4
5
6

Crew for Road roller


Hour
13.00
work inspector
Day
2.00
mazdoor
Day
38.00
Total cost of Labour
labour component/unit qty
40.30
Add contractor's profit and overhead charges
0.14 5.60
labour component/unit qty (including contractor's profit)
45.90
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
394.00 cum
cum
(A+B+C+D)/394.0
Rate per

IRR-CAW-7-4

2368.60
740.00
11210.00
15870.75

Rs:
Rs:
Rs:
Rs:

0.00
20401.75
15870.75
36272.50

Rs:
Rs:
Rs.

5078.15
41350.65
105.00

Providing and fixing 20 x 20 x 75 cm size top surface neatly dressed canal bed level
stones including cost of all materials, labour, excavation, fixing in position to correct level etc.,
complete with lead upto 50 m and all lifts.

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No
1

particulars

Rough stone 20x20x75 cm

UNIT :
Unit
Each

Quantity
32.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No

Description

Unit

Nil

Quantity
0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No

Description

Unit

Quantity

work inspector
Day
1.00
Stone chiseller Cl- I
Day
2.00
mazdoor
Day
2.00
Total cost of Labour
labour component/unit qty
54.10
Add contractor's profit and overhead charges
0.14 7.60
labour component/unit qty (including contractor's profit)
61.70
1
2
3

32 Nos.
Rate
in Rs.
23.00
0.00
Rs:

Amount
in Rs.
736.00
0.00
736.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.

Rate
in Rs.
370.00
385.00
295.00
Rs:

Amount
in Rs.
370.00
770.00
590.00
1730.00

Rs:
Rs:
Rs:
Rs:

736.00
0.00
1730.00
2466.00

Rs:
Rs:
Rs.

345.24
2811.24
87.90

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
32.00 Nos.
each
(A+B+C+D)/32.0
Rate per

IRR-CAW-7-5

182.20
370.00
295.00
Rs:

0.00

Providing, fabricating and placing in position reinforcement steel bars for RCC works
including cleaning, straightening, cutting, bending, hooking, lapping, tying with 1.25 mm dia.
soft annealed steel wire, welding wherever required including cost of all materials, machinery,
labour etc., complete with initial lead upto 50 and all lifts.

175

Canal and Allied Works - Item Unit Rates 2014-15

RATE ANALYSIS

DATA
A. MATERIALS:
Sl No
1
2
3

UNIT : 1000.00 kg

particulars

Unit

Rein.Steel with 5 % wastage


Binding wire 1.25 mm dia
Sundries ( chairs / spacers etc )
Total cost of Materials

kg
kg
LS

B. MACHINERY:
Sl No

Description

Unit

Quantity
1050.00
8.00
10.00

Quantity

Nil

0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No
1
2

Description
Bar bender
mazdoor

Unit

Quantity

Day
Day

6.00
11.00

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Rate
in Rs.
46.50
70.00
41.00
Rs:

Amount
in Rs.
48825.00
560.00
410.00
49795.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
450.00
295.00
Rs:

Amount
in Rs.
2700.00
3245.00
5945.00

Rs:
Rs:
Rs:
Rs:

49795.00
0.00
5945.00
55740.00

Rs:
Rs:
Rs.

7803.6
63543.60
63.50

5.90
0.14 0.80
6.70

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
1000.00 kg
(A+B+C+D)/1000.0
kg
Rate per

IRR-CAW-7-6

Providing and laying 75 mm thick in-situ M-15 ( 28 days cube compressive strength not less
than 15 N / sqmm ) grade cement concrete with 20 mm down size approved, clean, hard,
graded aggregates for canal lining using vibrating cylinder type mechanical paver including
cost of all materials, machinery, labour, cleaning, batching, mixing, placing in position,
finishing, forming contraction joints, fixing PVC joint sealing strips, curing, shifting of paver
from one side to other side of canal etc., complete with initial lead upto 1 km and all lifts.
(43 Gr Cement content: 300 kg /cum (22.5 kg/ sqm) for
use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35,
FA : 0.45 cum equivalent concrete volume:79.2 cum including the extra quantity of
concrete for curvatures and bends etc.,)

DATA:

RATE ANALYSIS
A. MATERIALS:
particulars
Sl No
1
2
3
4
5
6
7

Cement 43 Gr
Coarse aggregate 20-10 mm
Coarse aggregate 10-4.75 mm
Fine aggregate (Un-Screened )
Super plasticiser
PVC sealing strip
Use rate of paving cylinder
Sundries
Total cost of Materials

UNIT :
Unit

Quantity

kg
cum
cum
cum
kg
Rm
sqm
LS

23760.00
41.18
22.18
35.64
95.04
640.00
960.00
5.00

960 sqm
Rate
Amount
in Rs.
in Rs.
4.00
95040.00
1210.00
49832.64
875.00
19404.00
462.00
16465.68
80.00
7603.20
44.00
28160.00
0.88
842.40
41.00
205.00
Rs: 217552.92

B. MACHINERY:

176

Canal and Allied Works - Item Unit Rates 2014-15

Sl No
1
2
3
4
5
6
7

8
9

Description

Unit

Quantity

Batching plant
Lubricants etc @ 5 %
Transit mixer 3 Nos
Fuel / Energy charges
Mechanical paver
Lubricants etc @ 5 %
DG set for batching plant 50 KVA
Fuel / Energy charges
DG set for paver 30 KVA
Fuel / Energy charges
Shovel 0.5 cum / Loader
Fuel / Energy charges
Water tanker
Fuel / Energy charges

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour

8.00
8.00
24.00
24.00
8.00
8.00
8.00
8.00
8.00
8.00
2.00
2.00
8.00
8.00

Pump 5 hp(diesel) 2 Nos. 4 hrs each


Fuel / Energy charges
Sundries ( power line etc )
Total hire charges of Machinery

Hour
Hour
LS

8.00
8.00
5.00

C. LABOUR:
Description
Sl No

Unit

Quantity

Crew for Batching plant


Hour
8.00
Crew for Transit mixer
Hour
24.00
Crew for Concrete paver
Hour
8.00
Crew for DG set
Hour
16.00
Crew for Shovel
Hour
2.00
Crew for Water tanker
Hour
8.00
Crew for Pump
Hour
16
Mason Class I
Day
2
Mechanic
Day
1
Fitter
Day
1
Electrician
Day
1
work inspector
Day
2
mazdoor ( BP site )
Day
5
mazdoor ( Paver site )
Day
10
Total cost of Labour
labour component/unit qty
24.30
Add contractor's profit and overhead charges
0.14 3.40
labour component/unit qty (including contractor's profit)
27.70
1
2
3
4
5
6
7
8
9
10
11
12
13
14

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Add for shifting & re-erection of BP @
Add for LH / RH shifting & erection of Paver @
Add for ledge cutting / erection of tracks etc @

2%
0.5%
1%

Amount
in Rs.
3243.20
162.16
18201.60
22507.20
2852.00
142.60
680.80
8184.00
526.40
5456.00
2006.20
1023.00
3220.00
2577.60

10.20
85.30
41.00
Rs:

81.60
682.40
205.00
71751.76

Rate
Amount
in Rs.
in Rs.
293.80
2350.40
244.90
5877.60
364.40
2915.20
113.90
1822.40
204.10
408.20
153.10
1224.80
96.10
1537.60
385.00
770.00
385.00
385.00
385.00
385.00
440.00
440.00
370.00
740.00
295.00
1475.00
295.00
2950.00
Rs:
23281.20

Rs:
Rs:
Rs:
Total
Rs:
Rs:
Rs:
Total
Rs:
14%
Rs:
cum @
31.5 Rs./
cum @
30.4 Rs./

D. Add for contractor's profit and overheads on (A+B+C+other


35.64
Lead Charges for 1 Km for FA
63.36
Lead Charges for 1 Km for CA
Lead Charges for 1Km for Cement (including
Loading and Unloading Charges)
23.76
tonne @
Total cost for
960.00 sqm
sqm
(A+B+C+D)/960.0
Rate per

IRR-CAW-7-7

Rate
in Rs.
405.40
20.27
758.40
937.80
356.50
17.83
85.10
1023.00
65.80
682.00
1003.10
511.50
402.50
322.20

217552.92
71751.76
23281.2
312585.88
6251.7176
1562.9294
3125.8588
323526.39
45293.69
1122.66
1926.14

124.6 Rs 2960.496
Rs: 374829.38
Rs.
390.40

Providing and laying 80 mm thick in-situ M-15 ( 28 days cube compressive strength not less
than 15 N / sqmm ) grade cement concrete with 20 mm down size approved, clean, hard,
graded aggregates for canal lining using vibrating cylinder type mechanical paver including
cost of all materials, machinery, labour, cleaning, batching, mixing, placing in position,

177

Canal and Allied Works - Item Unit Rates 2014-15

finishing, forming contraction joints, fixing PVC joint sealing strips, curing, shifting of paver
from one side to other side of canal etc., complete with initial lead upto 1 km and all lifts.
(43 Gr Cement content: 300 kg /cum (24 kg/ sqm) for
use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35,
FA : 0.45 cum equivalent concrete volume:84.48 cum including the extra quantity of
concrete for curvatures and bends etc.,)

DATA:

RATE ANALYSIS
A. MATERIALS:
particulars
Sl No
1
2
3
4
5
6
7

Unit

Quantity

kg
cum
cum
cum
kg
Rm
sqm
LS

25344.00
43.93
23.65
38.02
101.38
640.00
960.00
5.00

Unit

Quantity

Batching plant
Lubricants etc @ 5 %
Transit mixer 3 Nos
Fuel / Energy charges
Mechanical paver
Lubricants etc @ 5 %
DG set for batching plant 50 KVA
Fuel / Energy charges
DG set for paver 30 KVA
Fuel / Energy charges
Shovel 0.5 cum / Loader
Fuel / Energy charges
Water tanker
Fuel / Energy charges

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour

8.00
8.00
24.00
24.00
8.00
8.00
8.00
8.00
8.00
8.00
2.00
2.00
8.00
8.00

Pump 5 hp(diesel) 2 Nos. 4 hrs each


Fuel / Energy charges
Sundries ( power line etc )
Total hire charges of Machinery

Hour
Hour
LS

8.00
8.00
5.00

Cement 43 Gr
Coarse aggregate 20-10 mm
Coarse aggregate 10-4.75 mm
Fine aggregate (Un-Screened )
Super plasticiser
PVC sealing strip
Use rate of paving cylinder
Sundries
Total cost of Materials

B. MACHINERY:
Description
Sl No
1
2
3
4
5
6
7

8
9

UNIT :

C. LABOUR:
Description
Sl No

Unit

Quantity

Crew for Batching plant


Hour
8.00
Crew for Transit mixer
Hour
24.00
Crew for Concrete paver
Hour
8.00
Crew for DG set
Hour
16.00
Crew for Shovel
Hour
2.00
Crew for Water tanker
Hour
8.00
Crew for Pump
Hour
16
Mason Class I
Day
2
Mechanic
Day
1
Fitter
Day
1
Electrician
Day
1
work inspector
Day
2
mazdoor ( BP site )
Day
5
mazdoor ( Paver site )
Day
10
Total cost of Labour
labour component/unit qty
24.30
Add contractor's profit and overhead charges
0.14 3.40
labour component/unit qty (including contractor's profit)
27.70
1
2
3
4
5
6
7
8
9
10
11
12
13
14

960 sqm
Rate
Amount
in Rs.
in Rs.
4.00 101376.00
1210.00
53154.82
875.00
20697.60
462.00
17563.39
80.00
8110.08
44.00
28160.00
0.88
842.40
41.00
205.00
Rs: 230109.29

Rate
in Rs.
405.40
20.27
758.40
937.80
356.50
17.83
85.10
1023.00
65.80
682.00
1003.10
511.50
402.50
322.20

Amount
in Rs.
3243.20
162.16
18201.60
22507.20
2852.00
142.60
680.80
8184.00
526.40
5456.00
2006.20
1023.00
3220.00
2577.60

10.20
85.30
41.00
Rs:

81.60
682.40
205.00
71751.76

Rate
Amount
in Rs.
in Rs.
293.80
2350.40
244.90
5877.60
364.40
2915.20
113.90
1822.40
204.10
408.20
153.10
1224.80
96.10
1537.60
385.00
770.00
385.00
385.00
385.00
385.00
440.00
440.00
370.00
740.00
295.00
1475.00
295.00
2950.00
Rs:
23281.20

178

Canal and Allied Works - Item Unit Rates 2014-15

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Add for shifting & re-erection of BP @
Add for LH / RH shifting & erection of Paver @
Add for ledge cutting / erection of tracks etc @

2%
0.5%
1%

Rs:
Rs:
Rs:
Total
Rs:
Rs:
Rs:
Total
Rs:
14%
Rs:
cum @
31.5 Rs./
cum @
30.4 Rs./

D. Add for contractor's profit and overheads on (A+B+C+other


38.02
Lead Charges for 1 Km for FA
67.58
Lead Charges for 1 Km for CA
Lead Charges for 1Km for Cement (including
Loading and Unloading Charges)
25.34
tonne @
Total cost for
960.00 sqm
sqm
(A+B+C+D)/960.0
Rate per

IRR-CAW-7-8

230109.29
71751.76
23281.2
325142.25
6502.845
1625.7112
3251.4225
336522.23
47113.11
1197.504
2054.55

124.6 Rs 3157.8624
Rs: 390045.26
Rs.
406.30

Providing and laying 100 mm thick in situ M-15 (28 days cube compressive strength not less than
15 N /Sqmm ) grade cement concrete with 20 mm down size approved, clean, hard, graded
aggregates for canal lining using, vibrating, cylinder type mechanical paver including cost of all
materials, machinery, labour, cleaning, batching, mixing, placing in position, finishing, forming
contraction joints, fixing PVC joint sealing strips, curing, shifting of paver from one side to othere
side of canal etc., complete with initial lead upto 1 Km and all lifts.
(43 Gr Cement content: 300 kg /cum (30 kg/ sqm) for
use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35,
FA : 0.45 cum equivalent concrete volume:88 cum including the extra quantity of
concrete for curvatures and bends etc.,)

DATA:

RATE ANALYSIS
A. MATERIALS:
Particulars
Sl.No
Cement 43 Gr
1
2
Coarse aggregate 20-10 mm
Coarse aggregate 10-4.75 mm
3
Fine aggregate (Un-Screened)
4
Super plasticiser
5
PVC sealing strip
6
Use rate of paving cylinder
Total cost of Materials
B. MACHINERY:
Particulars
Sl.No
Batching plant
1
2
Transit mixer 3 Nos
Fuel / Energy charges
3
Mechanical paver
lubricants etc @ 5%
4
DG set for batching plant 50 KVA
Fuel / Energy charges
5
DG set for paver 30 KVA
Fuel / Energy charges
6
Shovel 0.5 cum / Loader
Fuel / Energy charges
7
Water tanker
Fuel / Energy charges
8

UNIT

Unit
Kg
cum
cum
cum
kg
Rm
sqm

Qty

Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour

Qty

800 Sqm

26400
45.76
24.64
39.6
105.6
533
800

8
24
24
8
8
8
8
8
8
2.00
2.00
8
8

Pump 5 hp (diesel) 2 Nos. 4 hrs each Hour


Fuel / Energy charges
Total hire charges of Machinery

C. LABOUR:
Sl No
Description

Unit

8
8

Quantity

Rate in RAmount
4.00 105600.00
1210.00
55369.60
875.00
21560.00
462.00
18295.20
80.00
8448.00
44.00
23452.00
0.8775
702.00
Rs.
233426.8

Rate in RAmount
405.40
3243.20
758.40
18201.60
937.80
22507.20
356.50
2852.00
17.83
142.60
85.10
680.80
1023.00
8184.00
65.80
526.40
682.00
5456.00
1003.10
2006.20
511.50
1023.00
402.50
3220.00
322.20
2577.60
10.20
85.30
Rs.

Rate

81.60
682.40
71384.6

Amount

179

Canal and Allied Works - Item Unit Rates 2014-15

Crew for Batching plant


Hour
8.00
Crew for Transit mixer
Hour
24.00
Crew for Concrete paver
Hour
8.00
Crew for DG set
Hour
16.00
Crew for Shovel
Hour
2.00
Crew for Water tanker
Hour
8
Crew for Pump
Hour
8
Mason Class I
Day
2
Mechanic
Day
1
Fitter
Day
1
Electrician
Day
1
work inspector
Day
2
mazdoor ( BP site )
Day
5
mazdoor ( Paver site )
Day
10
Total cost of Labour
labour component/unit qty
28.10
Add contractor's profit and overhead charges
0.14 3.90
labour component/unit qty (including contractor's profit)
32.00
1
2
3
4
5
6
7
8
9
10
11
12
13
14

in Rs.
in Rs.
293.80
2350.40
244.90
5877.60
364.40
2915.20
113.90
1822.40
204.10
408.20
153.10
1224.80
96.10
768.80
385.00
770.00
385.00
385.00
385.00
385.00
440.00
440.00
370.00
740.00
295.00
1475.00
295.00
2950.00
Rs:
22512.40

ABSTRACT
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs.
233426.8
Rs.
71384.6
Rs.
22512.40
TOTAL R 327323.8
Add for shifting & re-erection of BP @
2% Rs.
6546.476
Add for LH / RH shifting & erection of Paver @
0.5% Rs.
1636.619
Add for ledge cutting / erection of tracks etc @
1% Rs.
3273.238
Total
Rs: 338780.13
D. Add for contractor's profit and overheads on (A+B+C+other
14%
Rs:
47429.22
39.60
cum @
31.5 Rs./
1247.4
Lead Charges for 1 Km for FA
70.40
cum @
30.4 Rs./
2140.16
Lead Charges for 1 Km for CA
Lead Charges for 1Km for Cement (including
Loading and Unloading Charges)
26.40
tonne @ 124.6 Rs
3289.44
Total cost for
800.00 Sqm
Rs: 392886.35
Sqm
(A+B+C+D)/800.0
Rs.
491.10
Rate per

IRR-CAW-7-9

Note:

Dismantling, shifting and re-erecting mechanical concrete paver and DG set with all
accessories across canal CD work or other locations wherever shifting and re-erecting is
necessary including aligning paver correctly for continuing canal lining work, cost of all
materials, machinery, labour etc., complete with all leads and lifts.
Local shifting and re-erection of paver for LH and RH side lining included in concrete lining rates
under items IRR-CAW-7-7 and IRR-CAW-7-8 and saperate rate for shifting shall not be allowed.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

particulars

UNIT :
Unit

NIL

Quantity
0.00

Total cost of Materials


B. MACHINERY:
Sl No
1
2

C. LABOUR:
Sl No

Description

Unit

Tipper
Fuel / Energy charges
Sundries (ropes / rails etc)
Total hire charges of Machinery

Hour
Hour
LS

Description

Unit

Quantity
4.00
1.00
1.00

Quantity

1.00 Shifting
Rate
in Rs.
0.00

Amount
in Rs.

Rs:

0.00

Rate
in Rs.
446.70
322.20
41.00
Rs:

Amount
in Rs.
1786.8
322.2
41
2150.00

Rate

Amount

180

Canal and Allied Works - Item Unit Rates 2014-15

1
2
3

Crew for Tipper


Crew for Paver
mazdoor

Hour
Hour
Day

4.00
8.00
6.00

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

in Rs.
153.10
364.40
295.00
Rs:

in Rs.
612.4
2915.2
1770
5297.60

Rs:
Rs:
Rs:
Rs:

0.00
2150.00
5297.60
7447.60

Rs:
Rs:
Rs.

1042.66
8490.26
8490.30

5297.60
0.14 741.70
6039.30

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
1.00 Shifting
Shifting
(A+B+C+D)/1.0
Rate per

IRR-CAW-7-10 Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than
10 N /sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for bed and side lining of canal(150mm thick) including finishing the junction of bed and sides
to required curveture, cost of all materials, machinery, labour, formwork including supports,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
complete with initial lead upto 50 m and all lifts. ( Cement content : 250 kg / cum )
( 43 Gr Cement content: 250 kg / cum for use of super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No
1

3
4
6
7

Cement for mix


Cement for incidentals @ 5 kg / cum
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened)
Super Plasticizer
Use rate of manual paver
Sundries
Total cost of Materials

B. MACHINERY:
Sl No

particulars

Description

Concrete mixer 600/400 ltr ( diesel )


Fuel / Energy charges

UNIT :
Unit
kg
kg
cum
cum
cum
cum
kg
sqm
LS

Unit

Hour
Hour

Quantity
7042.5

28.17 cum
Rate
in Rs.
4.00

Amount
in Rs.
28170

140.85
4.00
563.4
12.68 1145.00 14514.593
7.61 1210.00
9203.139
5.07 875.00
4436.775
11.27 462.00
5205.816
28.17
80.00
2253.6
180
29.02
5222.94
2
41.00
82
Rs:
69652.26

Quantity

16.00
16.00

Rate
in Rs.
92.70
170.50

Amount
in Rs.
1483.2
2728

181

Canal and Allied Works - Item Unit Rates 2014-15

2
3

C. LABOUR:
Sl No

5 hp pump ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges

Hour
Hour
Hour
Hour

0.50
0.50
1.00
1.00

10.20
85.30
402.50
322.20

5.1
42.65
402.5
322.2

Needle vibrator 40 mm dia ( petrol )


Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour

16.00
16.00

7.60
21.50
Rs:

121.6
344
5449.25

Description

Unit

Rate
in Rs.
189.80
96.10
153.10
136.60
370.00
385.00
385.00

Amount
in Rs.
3036.8
48.05
153.1
2185.6
370
770
385

295.00
295.00
295.00
295.00
295.00
Rs:

6490
2360
1770
8310.15
590
26468.70

Quantity

Crew for Concrete mixer


Hour
16.00
Crew for Pump
Hour
0.50
Crew for Water tanker
Hour
1.00
Crew for Needle vibrator
Hour
16.00
work inspector
Day
1.00
Mason Class-I
Day
2.00
Fitter
Day
1.00
mazdoor
for batching materials
Day
22.00
for loading mortar pans
Day
8.00
for laying and moving paver
Day
6.00
for conveying concrete
Day
28.17
for cleaning/ washing/ curing
Day
2.00
Total cost of Labour
labour component/unit qty
939.60
Add contractor's profit and overhead charges
0.14 131.50
labour component/unit qty (including contractor's profit)
1071.10
1
2
3
4
5
6
7
8

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
28.17 cum
cum
(A+B+C+D)/28.17
Rate per

Rs:
69652.26
Rs:
5449.25
Rs:
26468.70
Rs: 101570.21
Rs:
14219.83
Rs: 115790.04
Rs.
4110.40

IRR-CAW-7-11 Providing and laying insitu vibrated M-10 (28 days cube compressive strength not less than
10 N/sqm) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregade for bed and side lining of canal(100 mm thick) including, finishing the junction of bed and sides
to required curvature, cost of all materials, machinery, labour, formwork including supports
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
complete with initial lead up to 50 m and all lifts (Cement content: 250 kg/cum)
( 43 Gr Cement content: 250 kg / cum for use of super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

DATA

RATE ANALYSIS
A. MATERIALS:
Particulars
Sl.No
Cement for mix
1

3
4
5

Cement for incidentals @ 5 Kg / cum


Coarse aggregate 40mm
Coarse aggregate 20 mm .
Coarse aggregate 10 mm .
Fine aggregate (Un-Screened)
Super Plasticizer
Use rate of manual paver

UNIT:

Unit
kg
kg
cum
cum
cum
cum
kg
sqm

27 cum

Qty Rate in Rs Amount


6750
4.00
27000.00
135
4.00
12.15 1145.00
7.29 1210.00
4.86 875.00
10.8 462.00
27
80.00
270
29.02

540.00
13911.75
8820.90
4252.50
4989.60
2160.00
7834.41

182

Canal and Allied Works - Item Unit Rates 2014-15

Total Rs.
Rs.

Total cost of Materials


B. MACHINERY:
Sl.No
1
2
3

C. LABOUR:
Sl No

Particulars

Unit

Qty

69509.16
69509.16

Rate in Rs Amount

Concrete mixer 600/400 ltr (diesel)


Fuel / Energy charges
5 hp pump (diesl)
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges

Hour
Hour
Hour
Hour
Hour
Hour

16.00
16.00
0.50
0.50
1.00
1.00

92.70
170.50
10.20
85.30
402.50
322.20

1483.20
2728.00
5.10
42.65
402.50
322.20

Needle vibrator 40 mm die (petrol)


Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour

4.00
4.00

7.60
21.50
Rs.

30.40
86.00
5100.05

Rate
in Rs.
189.80
96.10
153.10
136.60
370.00
385.00
385.00

Amount
in Rs.
3036.8
48.05
153.1
2185.6
370
770
385

295.00
295.00
295.00
295.00
295.00
Rs:

6490
2360
1770
7965
590
26123.55

Description

Unit

Quantity

Crew for Concrete mixer


Hour
16.00
Crew for Pump
Hour
0.50
Crew for Water tanker
Hour
1.00
Crew for Needle vibrator
Hour
16.00
work inspector
Day
1.00
Mason Class-I
Day
2.00
Fitter
Day
1.00
mazdoor
for batching materials
Day
22.00
for loading mortar pans
Day
8.00
for laying and moving paver
Day
6.00
for conveying concrete
Day
27.00
for cleaning/ washing/ curing
Day
2.00
Total cost of Labour
labour component/unit qty
967.50
Add contractor's profit and overhead charges
0.14 135.50
labour component/unit qty (including contractor's profit)
1103.00
1
2
3
4
5
6
7
8

ABSTRACT:
A. Cost of Materials including royalty charges
B. Hire charges of Machinery
C. Cost of Labour

Rs.
69509.16
Rs.
5100.05
Rs.
26123.55
Total Rs. 100732.76

D. Add for contractor's profit and overheads on (A+B+C)


14%
Total cost for
27.00 cum
cum
(A+B+C+D)/27.0
Rate per

Rs:
14102.59
Rs: 114835.35
Rs.
4253.20

IRR-CAW-7-12 Providing and laying100mm thick insitu vibrated M-10 (28 days cube compressive strength-not less than
10.00 N / sq mm) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for bed and side lining of canal lining using vibrating cylindertype mechanical paver
including cost of all materials mechinery labour batching mixing placing in position forming
contraction joints fixing pvc joint seiling strips shifting of paver from one side of canal to other
side etc.complete with 1 km lead & all lifts.
(Cement content: 250 kg / cum for use of super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Particulars
Sl.No
Cement 43 Gr
1
2
Coarse aggregate 40 mm

UNIT
Unit
Kg
cum

800 Sqm
Qty Rate in Rs Amount
22000.00
4.00
88000
39.60 1145.00
45342

183

Canal and Allied Works - Item Unit Rates 2014-15

3
4
5
6

Coarse aggregate 20 mm
Coarse aggregate 10 mm
Fine aggregate (Un-Screened)
Super plasticiser
PVC sealing strip
Use rate of paving cylinder
Total cost of Materials

B. MACHINERY:
Particulars
Sl.No
Batching plant
1
2
Transit mixer 3 Nos
Fuel / Energy charges
3
Mechanical paver
lubricants etc @ 5%
4
DG set for batching plant 50 KVA
Fuel / Energy charges
5
DG set for paver 30 KVA
Fuel / Energy charges
6
Shovel 0.5 cum / Loader
Fuel / Energy charges
7
Water tanker
Fuel / Energy charges
8

cum
cum
cum
kg
Rm
sqm

23.76 1210.00
28749.6
15.84 875.00
13860
35.20 462.00
16262.4
88.00
80.00
7040
533.00
44.00
23452
800.00
0.878
702
Rs.
223408.00

Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour

Qty Rate in Rs Amount


8.00 405.40
3243.2
24.00 758.40
18201.6
24.00 937.80
22507.2
5.00 356.50
1782.5
5.00
17.83
89.125
8.00
85.10
680.8
8.00 1023.00
8184
8.00
65.80
526.4
8.00 682.00
5456
2.00 1003.10
2006.20
2.00 511.50
1023.00
8.00 402.50
3220
8.00 322.20
2577.6

Pump 5 hp (diesel) 2 Nos. 4 hrs each Hour


Fuel / Energy charges
Hour
Total hire charges of Machinery

C. LABOUR:
Description
Sl No

Unit

8.00
8.00

Quantity

Crew for Batching plant


Hour
8.00
Crew for Transit mixer
Hour
24.00
Crew for Concrete paver
Hour
8.00
Crew for DG set
Hour
16.00
Crew for Shovel
Hour
2.00
Crew for Water tanker
Hour
8
Crew for Pump
Hour
8
Mason Class I
Day
2
Mechanic
Day
1
Fitter
Day
1
Electrician
Day
1
work inspector
Day
2
mazdoor ( BP site )
Day
5
mazdoor ( Paver site )
Day
10
Total cost of Labour
labour component/unit qty
28.10
Add contractor's profit and overhead charges
0.14 3.90
labour component/unit qty (including contractor's profit)
32.00
1
2
3
4
5
6
7
8
9
10
11
12
13
14

10.20
85.30
Rs.

81.6
682.4
70261.63

Rate
Amount
in Rs.
in Rs.
293.80
2350.40
244.90
5877.60
364.40
2915.20
113.90
1822.40
204.10
408.20
153.10
1224.80
96.10
768.80
385.00
770.00
385.00
385.00
385.00
385.00
440.00
440.00
370.00
740.00
295.00
1475.00
295.00
2950.00
Rs:
22512.40

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs.
223408.00
Rs.
70261.63
Rs.
22512.40
TOTAL R 316182.03
Add for shifting & re-erection of BP @
2% Rs.
6323.64
Add for LH / RH shifting & erection of Paver @
0.5% Rs.
1580.91
Add for ledge cutting / erection of tracks etc @
1% Rs.
3161.82
Total
Rs: 327248.40
D. Add for contractor's profit and overheads on (A+B+C+other
14%
Rs:
45814.78
35.20
cum @
31.5 Rs./
1108.8
Lead Charges for 1 Km for FA
79.20
cum @
30.4 Rs./
2407.68
Lead Charges for 1 Km for CA
Lead Charges for 1Km for Cement (including
Loading and Unloading Charges)

22.00

tonne @

124.6 Rs

2741.2

184

Canal and Allied Works - Item Unit Rates 2014-15

Total cost for


Sqm
Rate per

800.00 Sqm
(A+B+C+D)/800.0

Rs: 379320.86
Rs.
474.20

IRR-CAW-7-13 Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than
10 N /sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
aggregates for bed and side lining of canal including finishing the junction of bed and sides
to required curveture, cost of all materials, machinery, labour, formwork including supports,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
complete with initial lead upto 50 m and all lifts. ( Cement content : 250 kg / cum )
(Cement content: 250 kg / cum for use of super plasticiser(0.4% by wt. of cement),
CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No
1

2
3
4
5
6

Cement for mix


Cement for incidentals @ 5 kg / cum
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened)
Super Plasticizer
Use rate of manual paver
Sundries
Total cost of Materials

B. MACHINERY:
Sl No

1
2
3

C. LABOUR:
Sl No

particulars

Description

UNIT :
Unit
kg
kg
cum
cum
cum
kg
sqm
LS

Unit

Quantity

Rate
in Rs.
4.00

Amount
in Rs.
27000

135
4.00
14.04 1210.00
7.56 875.00
12.15 462.00
27
80.00
270
29.02
2
41.00
Rs:

540
16988.4
6615
5613.3
2160
7834.41
82
66833.11

6750

Quantity

Rate
in Rs.

Amount
in Rs.

Concrete mixer 600/400 ltr ( diesel )


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges

Hour
Hour
Hour
Hour
Hour
Hour

16.00
16.00
0.50
0.50
1.00
1.00

92.70
170.50
10.20
85.30
402.50
322.20

1483.2
2728
5.1
42.65
402.5
322.2

Needle vibrator 40 mm dia ( petrol )


Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour

16.00
16.00

7.60
21.50
Rs:

121.6
344
5449.25

Description

Unit

Rate
in Rs.
189.80
96.10
153.10
136.60
385.00
370.00
385.00

Amount
in Rs.
3036.8
48.05
153.1
2185.60
770
370
385

295.00
295.00
295.00
295.00
295.00
Rs:

6490
2360
1770
7965
590
26123.55

Quantity

Crew for Concrete mixer


Hour
16.00
Crew for Pump
Hour
0.50
Crew for Water tanker
Hour
1.00
Crew for Vibrator
Hour
16.00
Mason Class-I
Day
2.00
work inspector
Day
1.00
Fitter
Day
1.00
mazdoor
for batching materials
Day
22.00
for loading mortar pans
Day
8.00
for laying and moving paver
Day
6.00
for conveying concrete
Day
27.00
for cleaning/ washing/ curing
Day
2.00
Total cost of Labour
labour component/unit qty
967.50
Add contractor's profit and overhead charges
0.14 135.50
labour component/unit qty (including contractor's profit)
1103.00
1
2
3
4
5
6
7
8

27.00 cum

185

Canal and Allied Works - Item Unit Rates 2014-15

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
27.00 cum
cum
(A+B+C+D)/27.0
Rate per

Rs:
Rs:
Rs:
Rs:

66833.11
5449.25
26123.55
98405.91

Rs:
13776.83
Rs: 112182.74
Rs.
4154.90

IRR-CAW-7-14 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than
15 N /sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for bed and side lining of canal(150 mm thick) including finishing the junction of bed and sides
to required curveture, cost of all materials, machinery, labour, formwork including supports,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
complete with initial lead upto 50 m and all lifts.
(Cement content: 290 kg / cum for use of super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No
1

3
4
5
6

Cement for mix


Cement for incidentals @ 5 kg / cum
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened)
Super Plasticizer
Use rate of manual paver
Sundries
Total cost of Materials

B. MACHINERY:
Sl No

1
2
3

C. LABOUR:
Sl No
1
2
3
4
5
6
7
8

particulars

Description

UNIT :
Unit
kg
kg
cum
cum
cum
cum
kg
sqm
LS

Unit

Quantity

24.92 cum
Rate
in Rs.
4.00

Amount
in Rs.
28907.20

124.6
4.00
11.21 1145.00
6.73 1210.00
4.49 875.00
9.97 462.00
28.91
80.00
166.14
29.02
2
41.00
Rs:

498.4
12840.03
8141.364
3924.90
4605.216
2312.58
4820.77
82.00
66132.46

7226.8

Quantity

Rate
in Rs.

Amount
in Rs.

Concrete mixer 600/400 ltr ( diesel )


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges

Hour
Hour
Hour
Hour
Hour
Hour

16.00
16.00
0.50
0.50
1.00
1.00

92.70
170.50
10.20
85.30
402.50
322.20

1483.20
2728.00
5.10
42.65
402.50
322.20

Needle vibrator 40 mm dia ( petrol )


Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour

16.00
16.00

7.60
21.50
Rs:

121.60
344.00
5449.25

Description

Unit

Crew for Concrete mixer


Crew for Pump
Crew for Water tanker
Crew for Vibrator
Mason Class-I
work inspector
Fitter
mazdoor
for batching materials

Hour
Hour
Hour
Hour
Day
Day
Day

16.00
0.50
1.00
16.00
2.00
1.00
1.00

Rate
in Rs.
189.80
96.10
153.10
136.60
385.00
370.00
385.00

Amount
in Rs.
3036.8
48.05
153.1
2185.60
770
370
385

Day

22.00

295.00

6490

Quantity

186

Canal and Allied Works - Item Unit Rates 2014-15

for loading mortar pans


for laying
for conveying concrete
for cleaning/ washing/ curing
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Day
Day
Day
Day

8.00
6.00
24.92
2.00

295.00
295.00
295.00
295.00
Rs:

2360
1770
7351.4
590
25509.95

Rs:
Rs:
Rs:
Rs:

66132.46
5449.25
25509.95
97091.66

1023.70
0.14 143.30
1167.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
24.92 cum
cum
(A+B+C+D)/24.92
Rate per

Rs:
13592.83
Rs: 110684.49
Rs.
4441.60

IRR-CAW-7-15 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than
15 N /sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
aggregates for bed and side lining of canal(100 mm thick) including finishing the junction of bed and sides
to required curveture, cost of all materials, machinery, labour, formwork including supports,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
complete with initial lead upto 50 m and all lifts.
(Cement content: 300 kg / cum for use of super plasticiser(0.4% by wt. of cement),
CA : 0.80 cum, Blending Ratio of CA--65:35, FA : 0.45 cum)

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No
1

2
3
4
6
7

Cement for mix


Cement for incidentals @ 5 kg / cum
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened)
Super Plasticizer
Use rate of manual paver
Sundries
Total cost of Materials

B. MACHINERY:
Sl No

1
2
3

C. LABOUR:
Sl No
1
2

particulars

Description

UNIT :
Unit
kg
kg
cum
cum
cum
kg
sqm
LS

Unit

Quantity

23.10 cum
Rate
in Rs.
4.00

Amount
in Rs.
27720

115.5
4.00
12.01 1210.00
6.47 875.00
10.40 462.00
27.72
80.00
231
29.02
2
41.00
Rs:

462
14534.52
5659.5
4802.49
2217.60
6702.77
82
62180.88

6930

Quantity

Rate
in Rs.

Amount
in Rs.

Concrete mixer 600/400 ltr ( diesel )


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges

Hour
Hour
Hour
Hour
Hour
Hour

16.00
16.00
0.50
0.50
1.00
1.00

92.70
170.50
10.20
85.30
402.50
322.20

1483.2
2728
5.1
42.65
402.5
322.2

Needle vibrator 40 mm dia ( petrol )


Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour

16.00
16.00

7.60
21.50
Rs:

121.6
344
5449.25

Description

Unit

Crew for Concrete mixer


Crew for Pump

Hour
Hour

Rate
in Rs.
189.80
96.10

Amount
in Rs.
3036.8
48.05

Quantity
16.00
0.50

187

Canal and Allied Works - Item Unit Rates 2014-15

3
4
5
6
7
8

Crew for Water tanker


Hour
1.00
Crew for Vibrator
Hour
16.00
Mason Class-I
Day
2.00
work inspector
Day
1.00
Fitter
Day
1.00
mazdoor
for batching materials
Day
22.00
for loading mortar pans
Day
8.00
for laying and moving paver
Day
6.00
for conveying concrete
Day
23.10
for cleaning/ washing/ curing
Day
2.00
Total cost of Labour
labour component/unit qty
1081.10
Add contractor's profit and overhead charges
0.14 151.40
labour component/unit qty (including contractor's profit)
1232.50
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
23.10 cum
cum
(A+B+C+D)/23.10
Rate per

153.10
136.60
385.00
370.00
385.00

153.1
2185.6
770
370
385

295.00
295.00
295.00
295.00
295.00
Rs:

6490
2360
1770
6814.5
590
24973.05

Rs:
Rs:
Rs:
Rs:

62180.88
5449.25
24973.05
92603.18

Rs:
12964.45
Rs: 105567.63
Rs.
4570.00

IRR-CAW-7-16 Providing and laying150mm thick insitu vibrated M-15 (28 days cube compressive strength-not less than
15.00 N / sq mm) grade cement concrete using 20 mm down size approved, clean, hard, graded
aggregates for bed and side lining of canal lining using vibrating cylindertype mechanical paver
including cost of all materials mechinery labour batching mixing placing in position forming
contractiom joints fixing pvc joint seiling strips shifting of paver from one side of canal to other
side etc.complete with 1km lead & all lifts.
(43 Gr Cement content: 300 kg /cum (45 kg/ sqm) for
use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35,
FA : 0.44 cum equivalent concrete volume:132 cum including the extra quantity of
concrete for curvatures and bends etc.,)

DATA:

RATE ANALYSIS
A. MATERIALS:
Particulars
Sl.No
Cement 43 Gr
1
2
Coarse aggregate 20 mm
Coarse aggregate 10 mm
3
Fine aggregate (Un-Screened)
4
Super plasticiser
5
PVC sealing strip
6
Use rate of paving cylinder
Total cost of Materials
B. MACHINERY:
Particulars
Sl.No
Batching plant
1
2
Transit mixer 3 Nos
Fuel / Energy charges
3
Mechanical paver
lubricants etc @ 5%
4
DG set for batching plant 50 KVA
Fuel / Energy charges
5
DG set for paver 30 KVA
Fuel / Energy charges
6
Shovel 0.5 cum / Loader
Fuel / Energy charges

UNIT
Unit
Kg
cum
cum
cum
kg
Rm
sqm

Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour

800 Sqm
Qty Rate in Rs Amount
39600.00
4.00
158400
68.64 1210.00
83054.4
36.96 875.00
32340
58.08 462.00
26832.96
158.40
80.00
12672
533.00
44.00
23452
800.00
0.878
702
Rs.
337453.36

Qty Rate in Rs Amount


8.00 405.40
3243.2
24.00 758.40
18201.6
24.00 937.80
22507.2
5.00 356.50
1782.5
5.00
17.83
89.125
8.00
85.10
680.8
8.00 1023.00
8184
8.00
65.80
526.4
8.00 682.00
5456
2.00 1003.10
2006.20
2.00 511.50
1023.00

188

Canal and Allied Works - Item Unit Rates 2014-15

Water tanker
Fuel / Energy charges

Hour
Hour

8.00
8.00

402.50
322.20

3220
2577.6

Pump 5 hp (diesel) 2 Nos. 4 hrs each Hour


Fuel / Energy charges
Hour
Total hire charges of Machinery

8.00
8.00

10.20
85.30
Rs.

81.6
682.4
70261.63

C. LABOUR:
Description
Sl No

Unit

Quantity

Crew for Batching plant


Hour
8.00
Crew for Transit mixer
Hour
24.00
Crew for Concrete paver
Hour
8.00
Crew for DG set
Hour
16.00
Crew for Shovel
Hour
2.00
Crew for Water tanker
Hour
8
Crew for Pump
Hour
8
Mason Class I
Day
2
Mechanic
Day
1
Fitter
Day
1
Electrician
Day
1
work inspector
Day
2
mazdoor ( BP site )
Day
5
mazdoor ( Paver site )
Day
10
Total cost of Labour
labour component/unit qty
28.10
Add contractor's profit and overhead charges
0.14 3.90
labour component/unit qty (including contractor's profit)
32.00
1
2
3
4
5
6
7
8
9
10
11
12
13
14

Rate
Amount
in Rs.
in Rs.
293.80
2350.40
244.90
5877.60
364.40
2915.20
113.90
1822.40
204.10
408.20
153.10
1224.80
96.10
768.80
385.00
770.00
385.00
385.00
385.00
385.00
440.00
440.00
370.00
740.00
295.00
1475.00
295.00
2950.00
Rs:
22512.40

ABSTRACT
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs.
337453.36
Rs.
70261.63
Rs.
22512.40
TOTAL R 430227.39
Add for shifting & re-erection of BP @
2% Rs.
8604.55
Add for LH / RH shifting & erection of Paver @
0.5% Rs.
2151.14
Add for ledge cutting / erection of tracks etc @
1% Rs.
4302.27
Total
Rs: 445285.35
D. Add for contractor's profit and overheads on (A+B+C+other
14%
Rs:
62339.95
58.08
cum @
31.5 Rs./
1829.52
Lead Charges for 1 Km for FA
105.60
30.4 Rs./
3210.24
cum @
Lead Charges for 1 Km for CA
Lead Charges for 1Km for Cement (including
Loading and Unloading Charges)
39.60
tonne @ 124.6 Rs
4934.16
Total cost for
800.00 Sqm
Rs: 517599.22
Sqm
(A+B+C+D)/800.0
Rs.
647.00
Rate per

IRR-CAW-7-17 Providing and fixing pre-cast RCC template walls consisting of 0.05 cum M-15 grade
concrete using 20 mm down size coarse aggregates and 10 kg reinforcement steel moulded
as per specifications and drawing in CM 1:4 proportion including cost of all materials,
machinery, labour, formwork, fabricating and placing reinforcement steel, mixing, laying,
conveying and fixing in position including necessary excavation for seating, finishing joints in
CM 1:4, curing etc., complete with initial lead upto 1 km and all lifts.

DATA

RATE ANALYSIS

UNIT :

20.00 templete

189

Canal and Allied Works - Item Unit Rates 2014-15

A. MATERIALS:
Sl No
1
2
3
4
5
6
7

particulars

Unit

Cement 43 Gr
Sand (Un-Screened )
Coarse aggregate 20-10 mm
Coarse aggregate 10-4.75 mm
Reinforcement steel
Binding wire
Use rate of mould
Sundries( water charges & misc. )
Total cost of Materials

kg
cum
cum
cum
kg
kg
set
LS

B. MACHINERY:
Sl No
1

Description

Hand mixer

Unit
Hour

Quantity
310.00
0.50
0.50
0.30
200.00
3.00
20.00
1.00

Quantity

Rate
in Rs.
5.50
0.00
Rs:

Amount
in Rs.
44
0
44.00

Rate
in Rs.
370.00
385.00
345.00
450.00
295.00
295.00
295.00
Rs:

Amount
in Rs.
370
385
690
450
1180
590
590
4255.00

Rs:
Rs:
Rs:
Total
Rs:
14%
Rs:
cum @
31.5 Rs./
30.4 Rs./
cum @

13163.30
44.00
4255.00
17462.30
2444.72
15.75
24.32

124.6 Rs

38.626

145.6 Rs
Rs:
Rs.

29.12
20014.83
1000.70

8.00
8.00

Total hire charges of Machinery


C. LABOUR:
Sl No

Description

work inspector
Mason Class I for fixing
Mason Class II for casting
Bar bender
mazdoor ( casting yard )
mazdoor ( for fixing )
mazdoor for conveying
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
1
2
3
4
5

Unit
Day
Day
Day
Day
Day
Day
Day

Rate
Amount
in Rs.
in Rs.
4.00
1240
462.00
231
1210.00
605
875.00
262.5
46.50
9300
70.00
210
63.69 1273.7956
41.00
41
Rs:
13163.30

Quantity
1.00
1.00
2.00
1.00
4.00
2.00
2.00

212.80
0.14 29.80
242.60

ABSTRACT:
A. Cost of Materials including serignorage charges
B. Hire charges of Machinery
C. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)


0.50
Lead Charges for 1 Km for FA
0.80
Lead Charges for 1 Km for CA
Lead Charges for 1Km for Cement (including
Loading and Unloading Charges)
0.31
tonne @
Lead Charges for 1Km for Steel (including Loading
and Unloading Charges)
0.20
tonne @
Total cost for
20.00 templete
templete
(A+B+C+D)/20.0
Rate per

IRR-CAW-7-18 Providing and fixing 50 mm dia perforated GI pressure relief pipes 12.50 cm long with
one end closed with perforated GI plate and other end provided with alluminium lid hinged
to pipe including cost of all materials, labour, drilling 8 mm dia holes etc., complete with all
leads and lifts.

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Quantity

10 Nos.

GI pipe 50 mm dia 10 Nos

Rm

1.25

Rate
in Rs.
320.00

GI plate & Alluminium lid ( hinged )

LS

10.00

41.00

Amount
in Rs.
400
410

190

Canal and Allied Works - Item Unit Rates 2014-15

Total cost of Materials


B. MACHINERY:
Sl No
1

Description

Drilling 8 mm dia holes

Unit

Quantity

LS

0.50
0.00

Rs:

810.00

Rate
in Rs.
41.00

Amount
in Rs.
20.5

Rs:

20.50

Rate
in Rs.
440.00
295.00
Rs:

Amount
in Rs.
220
147.5
367.50

Rs:
Rs:
Rs:
Rs:

810.00
20.50
367.50
1198.00

Rs:
Rs:
Rs.

167.72
1365.72
136.60

Total hire charges of Machinery


C. LABOUR:
Sl No
1

Description
Pipe fitter
mazdoor

Unit

Quantity

Day
Day

0.50
0.50

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

36.80
0.14 5.20
42.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
10.00 Nos.
(A+B+C+D)/10.0
each
Rate per

IRR-CAW-7-19 Providing and fixing 50 mm dia perforated GI pressure relief pipes 22.50 cm long with
one end closed with perforated GI plate and other end provided with alluminium lid hinged
to pipe including cost of all materials, labour, drilling 8 mm dia holes etc., complete with all
leads and lifts.

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Quantity

GI pipe 50 mm dia 10 Nos

Rm

2.25

GI plate & Alluminium lid ( hinged )


Total cost of Materials

LS

10.00

B. MACHINERY:
Sl No
1

Description

Drilling 8 mm dia holes

Unit

Quantity

LS

5.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No
1

Description
Pipe fitter
mazdoor

Unit

Quantity

Day
Day
Total cost of Labour

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery

0.50
0.50

10 Nos.
Rate
in Rs.
320.00

Amount
in Rs.
720

41.00
Rs:

410
1130.00

Rate
in Rs.
41.00

Amount
in Rs.
205

Rs:

205.00

Rate
in Rs.
440.00
295.00
Rs:

Amount
in Rs.
220
147.5
367.50

Rs:
Rs:

1130.00
205.00

36.80
0.14 5.20
42.00

191

Canal and Allied Works - Item Unit Rates 2014-15

C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
10.00 Nos.
No.
(A+B+C+D)/10.0
Rate per

Rs:
Rs:

367.50
1702.50

Rs:
Rs:
Rs.

238.35
1940.85
194.10

IRR-CAW-7-20 Providing and fixing 50 mm dia perforated GI pressure relief pipes 30 cm long with
one end closed with perforated GI plate and other end provided with alluminium lid hinged
to pipe including cost of all materials, labour, drilling 8 mm dia holes etc., complete with all
leads and lifts.

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Quantity

GI pipe 50 mm dia 10 Nos

Rm

3.00

GI plate & Alluminium lid ( hinged )


Total cost of Materials

LS

10.00

B. MACHINERY:
Sl No
1

Description

Drilling 8 mm dia holes

Unit

Quantity

LS

7.00
0.00

10 Nos.
Rate
in Rs.
320.00

Amount
in Rs.
960.00

41.00
Rs:

410.00
1370.00

Rate
in Rs.
41.00

Amount
in Rs.
287.00

Rs:

287.00

Rate
in Rs.
440.00
295.00
Rs:

Amount
in Rs.
220.00
147.50
367.50

Rs:
Rs:
Rs:
Rs:

1370.00
287.00
367.50
2024.50

Rs:
Rs:
Rs.

283.43
2307.93
230.80

Total hire charges of Machinery


C. LABOUR:
Sl No
1

Description
Pipe fitter
mazdoor

Unit

Quantity

Day
Day

0.50
0.50

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

36.80
0.14 5.20
42.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
10.00 Nos.
No.
(A+B+C+D)/10.0
Rate per

IRR-CAW-7-21 Providing and fixing 50 mm dia perforated GI pressure relief pipes 45 cm long with
one end closed with perforated GI plate and other end provided with alluminium lid hinged
to pipe including cost of all materials, labour, drilling 8 mm dia holes etc., complete with all
leads and lifts.

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No
1

particulars

GI pipe 50 mm dia 10 Nos

UNIT :
Unit
Rm

Quantity
4.50

10 Nos.
Rate
in Rs.
320.00

Amount
in Rs.
1440.00

192

Canal and Allied Works - Item Unit Rates 2014-15

GI plate & Alluminium lid ( hinged )


Total cost of Materials

B. MACHINERY:
Sl No
1

Description

Drilling 8 mm dia holes

LS

Unit
LS

10.00

Quantity
10.00
0.00

41.00
Rs:

410.00
1850.00

Rate
in Rs.
41.00

Amount
in Rs.
410.00

Rs:

410.00

Rate
in Rs.
440.00
295.00
Rs:

Amount
in Rs.
220.00
147.50
367.50

Rs:
Rs:
Rs:
Rs:

1850.00
410.00
367.50
2627.50

Rs:
Rs:
Rs.

367.85
2995.35
299.50

Total hire charges of Machinery


C. LABOUR:
Sl No
1

Description
Pipe fitter
mazdoor

Unit

Quantity

Day
Day

0.50
0.50

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

36.80
0.14 5.20
42.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
10.00 Nos.
No.
(A+B+C+D)/10.0
Rate per

IRR-CAW-7-22 Providing and fixing 50 mm dia perforated GI pressure relief pipes 75 cm long with
one end closed with perforated GI plate and other end provided with alluminium lid hinged
to pipe including cost of all materials, labour, drilling 8 mm dia holes etc., complete with all
leads and lifts.

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Quantity

GI pipe 50 mm dia

Rm

7.50

GI plate & Alluminium lid ( hinged )


Total cost of Materials

LS

10.00

B. MACHINERY:
Sl No
1

Description

Drilling 8 mm dia holes

Unit
LS

Quantity
15.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No
1
2

Description
Pipe fitter
mazdoor

Unit

Quantity

Day
Day
Total cost of Labour

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

0.50
0.50

10 Nos.
Rate
in Rs.
320.00

Amount
in Rs.
2400.00

41.00
Rs:

410.00
2810.00

Rate
in Rs.
41.00

Amount
in Rs.
615.00

Rs:

615.00

Rate
in Rs.
440.00
295.00
Rs:

Amount
in Rs.
220.00
147.50
367.50

36.80
0.14 5.20
42.00

ABSTRACT:

193

Canal and Allied Works - Item Unit Rates 2014-15

A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
10.00 Nos.
No.
(A+B+C+D)/10.0
Rate per

Rs:
Rs:
Rs:
Rs:

2810.00
615.00
367.50
3792.50

Rs:
Rs:
Rs.

530.95
4323.45
432.30

IRR-CAW-7-23 Providing and fixing 100 mm dia perforated PVC pipes 40 cm long for Weep holes
including cost of all materials, labour, drilling 8 mm dia holes etc. complete with all
leads and lifts.

DATA

RATE ANALYSIS

UNIT:

10 Nos.

A. MATERIALS:
Sl.No
1

Particulars
PVC pipe 100 mm dia 10 Nos
Total cost of Materials

Unit
Rm

Rate in Amount in
Qty
Rs
Rs.
10.00 175.00
1750.00
Rs.
1750.00

B. MACHINERY
Sl.No
1

Description

Unit

Nill
Total hire chargs of Machinery

Rate in Amount in
Rs.
Rs.
0.00
0.00
0.00
0.00
Rs.
0.00

Quantity

C. LABOUR
Rate in Amount in
Sl.No
Particulars
Unit
Qty
Rs
Rs.
1
Pipe fitter
Day
0.25 440.00
110.00
2
Mazdoor
Day
0.25 295.00
73.75
Total cost of Labour
Rs.
183.75
labour component/unit qty
18.40
Add contractor's profit and overhead charges
0.14 2.60
labour component/unit qty (including contractor's profit)
21.00
ABSTRACT
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs.
Rs.
Rs.
Total
Rs:

D. Add for contractor's profit and overheads on (A+B+C)


14%
Total cost for
10.00 Nos.
No.
(A+B+C+D)/10.0
Rate per

Rs:
Rs:
Rs.

1750.00
0.00
183.75
1933.75
270.73
2204.48
220.40

IRR-CAW-7-24 Drilling 32 mm dia pressure relief hole below pressure relief pipe for bed and side lining of
canal laid on rock including cost of all materials, machinery, labour etc., complete with all
leads and lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

UNIT :

particulars

Unit

Use rate of drill rod 1.6 m long


Reconditioning charges @
Use rate of air hose 2 Nos.
Total cost of Materials

Rm
Hour

Quantity
10.00
10%
2.00

10 Nos.
Rate
in Rs.
26.85
10.94
Rs:

Amount
in Rs.
268.53
26.85
21.88
317.26

194

Canal and Allied Works - Item Unit Rates 2014-15

B. MACHINERY:
Sl No
1
2

Description

Unit

Air compressor 8.5 cmm diesel


Fuel / Energy charges
Jack hammer 2 Nos.
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour

Description

Unit

C. LABOUR:
Sl No

Quantity
1.00
1.00
2.00
2.00

Quantity

Crew for Air compressor


Hour
1.00
Crew for Jack hammer
Hour
2.00
Total cost of Labour
labour component/unit qty
75.20
Add contractor's profit and overhead charges
0.14 10.50
labour component/unit qty (including contractor's profit)
85.70
1
2

Rate
in Rs.
275.60
959.10
19.80
0.00
Rs:

Amount
in Rs.
275.60
959.10
39.60
0.00
1274.30

Rate
in Rs.
182.20
284.70
Rs:

Amount
in Rs.
182.20
569.40
751.60

Rs:
Rs:
Rs:
Rs:

317.26
1274.30
751.60
2343.16

Rs:
Rs:
Rs.

328.04
2671.20
267.10

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
10.00 Nos.
No.
(A+B+C+D)/10.0
Rate per

IRR-CAW-7-25 Providing and forming 35 x 35 x 40 cm deep filter drain consisting of 75 mm thick 10 mm


down coarse aggregate around pressure relief pipe and 75 mm thick sand around coarse
aggregate filter including cost of all materials, labour, excavation of pit etc., complete with
lead upto 50 m and all lifts.

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

UNIT :

particulars

Unit

Coarse aggregate 10-4.75 mm


Sand (Un-Screened )
Total cost of Materials

cum
cum

B. MACHINERY:
Sl No

Description

Unit

Quantity
0.15
0.35

Quantity

Nil

0.00

Total hire charges of Machinery


C. LABOUR:
Sl No
1
2

Description
Mason Cl- II
mazdoor

Unit

Quantity

Day
Day
Total cost of Labour

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

0.10
0.10

10 Nos.
Rate
in Rs.
875.00
462.00
Rs:

Amount
in Rs.
131.25
161.70
292.95

Rate
in Rs.
0.00

Amount
in Rs.

Rs:

0.00

Rate
in Rs.
345.00
295.00
Rs:

Amount
in Rs.
34.50
29.50
64.00

Rs:
Rs:
Rs:

292.95
0.00
64.00

6.40
0.14 0.90
7.30

195

Canal and Allied Works - Item Unit Rates 2014-15

Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
10.00 Nos.
No.
(A+B+C+D)/10.0
Rate per

Rs:

356.95

Rs:
Rs:
Rs.

49.97
406.92
40.70

IRR-CAW-7-26 Providing and fixing 25 to 40 mm thick Shahabad / Talikota / other similar stone slabs
with pointing and finishing joints neatly in CM 1:3 proportion for canal / field channel lining
including cutting slabs to required size, mixing mortar, finishing joints neatly, curing etc.,
complete with lead upto 50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3

particulars

Unit

Shahabad Stone slabs


Cement 43 Gr
Sand (Screened )
Total cost of Materials

sqm
kg
cum

B. MACHINERY:
Sl No
1

UNIT :

Description

Unit

5 hp pump ( diesel )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour

Description

Unit

C. LABOUR:
Sl No

Quantity
105.00
200.00
0.40

Quantity
2.00
2.00

Quantity

Operator pump
Hour
2.00
work inspector
Day
1.00
Mason Class I
Day
4.00
Mason Class II
Day
2.00
mazdoor
Day
8.00
Cartman with Double Bullock cart for
6
water
Day
1.00
Total cost of Labour
labour component/unit qty
55.50
Add contractor's profit and overhead charges
0.14 7.80
labour component/unit qty (including contractor's profit)
63.30
1
2
3
4
5

100.00 sqm
Rate
in Rs.
229.00
4.00
606.00
Rs:

Amount
in Rs.
24045.00
800.00
242.40
25087.40

Rate
in Rs.
10.20
85.30
Rs:

Amount
in Rs.
20.40
170.60
191.00

Rate
in Rs.
96.10
370.00
385.00
345.00
295.00

Amount
in Rs.
192.20
370.00
1540.00
690.00
2360.00

395.00
Rs:

395.00
5547.20

Rs:
Rs:
Rs:
Rs:

25087.40
191.00
5547.20
30825.60

Rs:
Rs:
Rs.

4315.58
35141.18
351.40

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
100.00 sqm
sqm
(A+B+C+D)/100.0
Rate per

IRR-CAW-7-27 Fixing PCC slabs of various sizes in CM 1 : 3 proportion to the side slopes of canal
including preparing bed, flush pointing joints in CM 1 : 3 propn, cost of all materials ( excluding
PCC slabs ), labour, finishing, curing etc., complete with initial lead upto 50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Quantity

100.00 sqm
Rate

Amount

196

Canal and Allied Works - Item Unit Rates 2014-15

1
2

Cement 43 Gr
Sand (Screened)
Total cost of Materials

B. MACHINERY:
Sl No
1

kg
cum

Description

Unit

5 hp pump ( diesel )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour

Description

Unit

C. LABOUR:
Sl No

240.00
0.50

Quantity
2.00
2.00

Quantity

Operator pump
Hour
2.00
work inspector
Day
1.00
Mason Class I
Day
4.00
mazdoor
Day
9.00
Cartman with Double Bullock cart for
5
water
Day
1.00
Total cost of Labour
labour component/unit qty
51.50
Add contractor's profit and overhead charges
0.14 7.20
labour component/unit qty (including contractor's profit)
58.70
1
2
3
4

in Rs.
4.00
606.00
Rs:

in Rs.
960.00
303.00
1263.00

Rate
in Rs.
10.20
85.30
Rs:

Amount
in Rs.
20.40
170.60
191.00

Rate
in Rs.
96.10
370.00
385.00
295.00

Amount
in Rs.
192.20
370.00
1540.00
2655.00

395.00
Rs:

395.00
5152.20

Rs:
Rs:
Rs:
Rs:

1263.00
191.00
5152.20
6606.20

Rs:
Rs:
Rs.

924.87
7531.07
75.30

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
100.00 sqm
(A+B+C+D)/100.0
sqm
Rate per

IRR-CAW-7-28 Fixing PCC lug slabs of various sizes in CM 1 : 3 proportion for supporting PCC slab lining
including necessary excavation, refilling, flush pointing joints in CM 1 : 3 propn, cost of all
materials ( excluding PCC lug slabs ), labour, finishing, curing etc., complete with initial lead
upto 50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

particulars

Unit

Cement 43 Gr
Sand ( Screened)
Total cost of Materials

kg
cum

B. MACHINERY:
Sl No
1

C. LABOUR:
Sl No
1
2
3
4

UNIT :

Description

Unit

5 hp pump ( diesel )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour

Description

Unit

Operator pump
work inspector
Mason Class I
Mason Class II

Hour
Day
Day
Day

Quantity
58.00
0.12

Quantity
1.00
1.00

Quantity
1.00
1.00
2.00
1.00

100.00 Rm
Rate
in Rs.
4.00
606.00
Rs:

Amount
in Rs.
232.00
72.72
304.72

Rate
in Rs.
10.20
85.30
Rs:

Amount
in Rs.
10.20
85.30
95.50

Rate
in Rs.
96.10
370.00
385.00
345.00

Amount
in Rs.
96.10
370.00
770.00
345.00

197

Canal and Allied Works - Item Unit Rates 2014-15

mazdoor
Day
5.00
Cartman with Double Bullock cart for
6
water
Day
1.00
Total cost of Labour
labour component/unit qty
34.50
Add contractor's profit and overhead charges
0.14 4.80
labour component/unit qty (including contractor's profit)
39.30
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
100.00 Rm
Rm
(A+B+C+D)/100.0
Rate per

295.00

1475.00

395.00
Rs:

395.00
3451.10

Rs:
Rs:
Rs:
Rs:

304.72
95.50
3451.10
3851.32

Rs:
Rs:
Rs.

539.18
4390.50
43.90

IRR-CAW-7-29 Fixing 30 cm height pre-cast drops for field channels as directed including excavation, etc.,
complete with all leads and lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Nill

Quantity
0.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No

Description

Unit

Nill

Quantity
0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No
1
2
3

Description
work inspector
Mason Cl- II
mazdoor

Unit
Day
Day
Day

Quantity
1.00
1.00
1.00

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

7 Nos.
Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.

Rate
in Rs.
370.00
345.00
295.00
Rs:

Amount
in Rs.
370.00
345.00
295.00
1010.00

Rs:
Rs:
Rs:
Rs:

0.00
0.00
1010.00
1010.00

Rs:
Rs:
Rs.

141.4
1151.40
164.50

0.00

0.00

144.30
0.14 20.20
164.50

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
7.00 Nos.
No.
(A+B+C+D)/7.00
Rate per

IRR-CAW-7-30 Providing and fixing LDPE sheet for bed and sides of canal including cost of all materials,
labour, laying, joining etc., complete with all leads and lifts.
a. Using 500 micron thick LDPE sheet.

198

Canal and Allied Works - Item Unit Rates 2014-15

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

UNIT :

particulars

Unit

LDPE sheet 500 micron thick


Bitumen 85 / 25 and 80 / 100 Gr
Total cost of Materials

sqm
kg

B. MACHINERY:
Sl No

Description

Unit

Quantity
275.00
4.00

Quantity

Nill

0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No

Description

Unit

Quantity

250.00 sqm
Rate
in Rs.
92.00
43.00
Rs:

Amount
in Rs.
25300.00
172.00
25472.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.

Amount
in Rs.

Joining & laying @ 10 % of sheet


1
sqm
250.00
cost
mazdoor
Day
1.00
2
Total cost of Labour
labour component/unit qty
10.40
Add contractor's profit and overhead charges
0.14 1.50
labour component/unit qty (including contractor's profit)
11.90
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
14%

D. Add for contractor's profit and overheads on (A+B+C)


Total cost for
250.00 sqm
sqm
(A+B+C+D)/250.0
Rate per
Note :

9.20
295.00
Rs:

2300.00
295.00
2595.00

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs.

25472.00
0.00
2595.00
28067.00
3929.38
31996.38
128.00

i ) If the surface on which the LDPE sheet is to be laid is too rough and undulating provide
average 75 mm thick sand backing to LDPE sheet.
For providing average 75 mm thick sand backing :

DATA:

Quantity of sand ( unscreened )


2 mazdoors for laying 6 cum per day.

( 250 x 0.075 )

RATE ANALYSIS
A. MATERIALS:
Sl No
1

particulars

Sand for filling

18.75 cum

UNIT :
Unit
cum

Quantity
18.75

250.00 sqm
Rate
in Rs.
342.00

Amount
in Rs.
6412.50

199

Canal and Allied Works - Item Unit Rates 2014-15

0.00

0.00
Rs:

6412.50

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
295.00
Rs:

Amount
in Rs.
1770.00
1770.00

Rs:
Rs:
Rs:
Rs:

6412.50
0.00
1770.00
8182.50

Rs:
Rs:
Rs.

1145.55
9328.05
37.30

Total cost of Materials


B. MACHINERY:
Sl No

Description

Unit

Quantity

Nill

0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No
1

Description
mazdoor

Unit

Quantity

Day

6.00

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

7.10
0.14 1.00
8.10

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
250.00 sqm
(A+B+C+D)/250.0
sqm
Rate per

IRR-CAW-7-31 Providing and fixing LDPE sheet for bed and sides of canal including cost of all materials,
labour, laying, joining etc., complete with all leads and lifts.
b. Using 750 micron thick LDPE sheet.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

particulars

UNIT :
Unit

LDPE sheet 750 micron thick


Bitumen 85 / 25 and 80 / 100 Gr
Total cost of Materials

B. MACHINERY:
Sl No

Description

275.00
4.00

Unit

Nill

Quantity

Quantity
0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No

Description

Unit

Quantity

Joining & laying @ 10 % of sheet


1
cost
sqm
250.00
mazdoor
Day
1.00
2
Total cost of Labour
labour component/unit qty
14.20
Add contractor's profit and overhead charges
0.14 2.00
labour component/unit qty (including contractor's profit)
16.20
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

250.00 sqm
Rate
in Rs.
130.00
43.00
Rs:

Amount
in Rs.
35750.00
172.00
35922.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.

Rate
in Rs.

Amount
in Rs.

0.00

13.00
295.00
Rs:

3250.00
295.00
3545.00

Rs:
Rs:
Rs:

35922.00
0.00
3545.00

200

Canal and Allied Works - Item Unit Rates 2014-15

Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
250.00 sqm
sqm
(A+B+C+D)/250.0
Rate per
Note :

Rs:

39467.00

Rs:
Rs:
Rs.

5525.38
44992.38
180.00

i ) If the surface on which the LDPE sheet is to be laid is too rough and undulating provide
average 75 mm thick unscreened sand backing to LDPE sheet.
For providing average 75 mm thick sand backing per sqm
Rs:
37.30

IRR-CAW-7-32 Providing and fixing LDPE sheet for bed and sides of canal including cost of all materials,
labour, laying, joining etc., complete with all leads and lifts.
c. Using 1000 micron thick LDPE sheet.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

particulars

UNIT :
Unit

LDPE sheet 1000 micron thick


Bitumen 85 / 25 and 80 / 100 Gr
Total cost of Materials

B. MACHINERY:
Sl No

Description

275.00
4.00

Unit

Nill

Quantity

Quantity
0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No

Description

Unit

Quantity

250.00 sqm
Rate
in Rs.
180.00
43.00
Rs:

Amount
in Rs.
49500.00
172.00
49672.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.

Amount
in Rs.

Joining & laying @ 10 % of sheet


1
cost
sqm
250.00
mazdoor
Day
1.00
2
Total cost of Labour
labour component/unit qty
19.20
Add contractor's profit and overhead charges
0.14 2.70
labour component/unit qty (including contractor's profit)
21.90
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
250.00 sqm
sqm
(A+B+C+D)/250.0
Rate per
Note :

18.00
295.00
Rs:

4500.00
295.00
4795.00

Rs:
Rs:
Rs:
Rs:

49672.00
0.00
4795.00
54467.00

Rs:
Rs:
Rs.

7625.38
62092.38
248.40

i ) If the surface on which the LDPE sheet is to be laid is too rough and undulating provide
average 75 mm thick unscreened sand backing to LDPE sheet.
For providing average 75 mm thick sand backing per sqm
Rs:
37.30

IRR-CAW-7-33 Providing and fixing 12 mm thick 380 mm depth tarfelt expansion joint filler boards for
stone masonry lining of canal including cost of all materials, labour etc., complete with all
leads and lifts.

DATA

RATE ANALYSIS

UNIT :

100.00 Rm

201

Canal and Allied Works - Item Unit Rates 2014-15

A. MATERIALS:
Sl No

particulars

Tarfelt joint filler board 12 mm thick

Unit

Quantity

sqm

Rate
in Rs.

Amount
in Rs.

420.00
0.00
Rs:

16275.00

38.75
0.00

Total cost of Materials


B. MACHINERY:
Sl No

Description

Unit

Quantity

Nill

0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No
1
2

Description
Carpenter Cl- II
mazdoor

Unit

Quantity

Day
Day

1.00
1.00

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

16275.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.

Rate
in Rs.
345.00
295.00
Rs:

Amount
in Rs.
345.00
295.00
640.00

Rs:
Rs:
Rs:
Rs:

16275.00
0.00
640.00
16915.00

Rs:
Rs:
Rs.

2368.1
19283.10
192.80

0.00

6.40
0.14 0.90
7.30

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
100.00 Rm
Rm
(A+B+C+D)/100.00
Rate per

IRR-CAW-7-34 Providing and fixing 20 mm thick 100 mm depth tarfelt expansion joint filler boards for
cement concrete lining of canal including cost of all materials, labour etc., complete with all
leads and lifts.

DATA

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

Tarfelt joint filler board 20 mm thick

UNIT :
Unit

Quantity

sqm

10.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No

Description

Unit

Quantity

Nill

0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No
1
2

Description
Carpenter Cl- II
mazdoor

Unit

Quantity

Day
Day
Total cost of Labour

labour component/unit qty


Add contractor's profit and overhead charges

1.00
1.00

100.00 Rm
Rate
in Rs.

Amount
in Rs.
6300.00

630.00
0.00
Rs:

0.00
6300.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
345.00
295.00
Rs:

Amount
in Rs.
345.00
295.00
640.00

6.40
0.14 0.90

202

Canal and Allied Works - Item Unit Rates 2014-15

labour component/unit qty (including contractor's profit)

7.30

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
100.00 Rm
Rm
(A+B+C+D)/100.00
Rate per

Rs:
Rs:
Rs:
Rs:

6300.00
0.00
640.00
6940.00

Rs:
Rs:
Rs.

971.6
7911.60
79.10

IRR-CAW-7-35 Providing and fixing 20 mm thick 150 mm depth tarfelt expansion joint filler boards for
cement concrete lining of canal including cost of all materials, labour etc., complete with all
leads and lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

Tarfelt joint filler board 20 mm thick

UNIT :
Unit

Quantity

sqm

100.00 Rm
Rate
in Rs.

15.30
0.00

630.00
0.00
Rs:

Total cost of Materials


B. MACHINERY:
Sl No

Description

Unit

Quantity

Nill

0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No
1
2

Description
Carpenter Cl- II
mazdoor

Unit

Quantity

Day
Day

1.00
1.00

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Amount
in Rs.
9639.00

9639.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.

Rate
in Rs.
345.00
295.00
Rs:

Amount
in Rs.
345.00
295.00
640.00

Rs:
Rs:
Rs:
Rs:

9639.00
0.00
640.00
10279.00

Rs:
Rs:
Rs.

1439.06
11718.06
117.20

0.00

6.40
0.14 0.90
7.30

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
100.00 Rm
Rm
(A+B+C+D)/100.00
Rate per

IRR-CAW-7-36 Providing and forming 35 mm wide and 10 mm thick construction / contraction joints
for concrete lining by mastic filler including cost of all materials, labour etc., complete with
all leads and lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Quantity

100.00 Rm
Rate

Amount

203

Canal and Allied Works - Item Unit Rates 2014-15

Asphalt 80/100 Gr
Sand (Screened )
Total cost of Materials

B. MACHINERY:
Sl No

Description

kg
cum

Unit

35.00
0.04

Quantity

Nill

0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No
1
2

Description
Mason Cl- II
mazdoor

Unit

Quantity

Day
Day

0.50
1.00

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

in Rs.
43.00
606.00
Rs:

in Rs.
1505.00
24.24
1529.24

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
345.00
295.00
Rs:

Amount
in Rs.
172.50
295.00
467.50

Rs:
Rs:
Rs:
Rs:

1529.24
0.00
467.50
1996.74

Rs:
Rs:
Rs.

279.54
2276.28
22.80

4.70
0.14 0.70
5.40

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
100.00 Rm
Rm
(A+B+C+D)/100.00
Rate per

IRR-CAW-7-37 Manufacturing 550 x 550 x 55 mm size PCC lining slabs in M-15 grade ( 28 days cube
compressive strength not less than 15 N /sqmm ) cement concrete using 20 mm down graded
coarse aggregate including cost of all materials, machinery, labour, batching, mixing, laying,
compacting, formwork, finishing, curing etc.,complete with initial lead upto 50 m and all lifts.
( Cement content : 300 kg / cum with super plastcizer (0.4% by wt. of cement),
CA : 0.80 cum, Blending Ratio of CA : 65:35, FA : 0.45cum
equivalent concrete volume: 3.74 cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

2
3
4
5

Unit

Cement for mix

kg

Cement for incidentals @ 1 kg / slab


Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened )
Super Plasticizer
Use rate of moulds for 500 uses
Total cost of Materials

kg
cum
cum
cum
kg
No.

B. MACHINERY:
Sl No

particulars

UNIT :

Description

Concrete mixer 300/200 ltr ( diesel)


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges

Unit

Hour
Hour
Hour
Hour

Quantity
1122.00

225 Nos.
Rate
in Rs.
4.00

225.00
4.00
1.94 1210.00
1.05 875.00
1.68 462.00
4.49
80.00
225.00
8.54
Rs:

Quantity

8.00
8.00
0.10
0.10

Rate
in Rs.
53.50
85.30
10.20
85.30

Amount
in Rs.
4488.00
900.00
2353.21
916.30
777.55
359.04
1921.93
11716.03

Amount
in Rs.
428.00
682.40
1.02
8.53

204

Canal and Allied Works - Item Unit Rates 2014-15

Water tanker 8000 ltr


Fuel / Energy charges
Total hire charges of Machinery
Aportioned hire charges of
machinery for lining slab

Hour
Hour

Description

Unit

C. LABOUR:
Sl No

0.20
0.20

402.50
322.20
Rs:

80.50
64.44
1264.89

90%

Rs:

1138.40

Rate
in Rs.
189.80
96.10
153.10
385.00
370.00

Amount
in Rs.
1518.40
9.61
30.62
770.00
370.00

295.00
295.00
295.00
295.00
295.00
Rs:

885.00
590.00
295.00
295.00
295.00
5058.63

Rs:

4552.77

Rs:
Rs:
Rs:
Rs:

11716.03
1138.40
4552.77
17407.19

Rs:
Rs:
Rs.

2437.01
19844.20
88.20

Quantity

Crew for Concrete mixer


Hour
8.00
Crew for Pump
Hour
0.10
Crew for Water tanker
Hour
0.20
Mason Class-I
Day
2.00
work inspector
Day
1.00
mazdoor
for batching materials / laying CC
Day
3.00
for demoulding / oiling / laying
Day
2.00
for shifting slabs to curing pond
Day
1.00
for stacking after curing
Day
1.00
for cleaning & miscellaneous
Day
1.00
Total cost of Labour
Aportioned cost of labour for lining
slabs
90%
labour component/unit qty
20.20
Add contractor's profit and overhead charges
0.14 2.80
labour component/unit qty (including contractor's profit)
23.00
1
2
3
4
5
6

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
225.00 Nos.
each
(A+B+C+D)/225.0
Rate per

IRR-CAW-7-38 Manufacturing 550 x 300 x 55 mm size PCC lug slabs in M-15 grade ( 28 days cube
compressive strength not less than 15 N / sqmm ) cement concrete using 20 mm down graded
coarse aggregate including cost of all materials, machinery, labour, batching, mixing, laying,
compacting, formwork, finishing, curing etc.,complete with initial lead upto 50 m and all lifts.
( Cement content : 300 kg / cum with super plastcizer (0.4% by wt. of cement),
CA : 0.80 cum, Blending Ratio of CA : 65:35, FA : 0.45cum,
equivalent concrete volume: 0.23 cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

2
3
4
5

particulars

UNIT :
Unit

Quantity

25 Nos.
Rate
in Rs.
4.00

Cement for mix

kg

69.00

Cement for incidentals @ 0.5 kg/slab


Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened )
Super Plasticizer
Use rate of moulds for 500 uses
Total cost of Materials

kg
cum
cum
cum
kg
No.

12.50
4.00
0.12 1210.00
0.06 875.00
0.10 462.00
0.28
80.00
25.00
5.25
Rs:

B. MACHINERY:
Sl No

Description

Unit

Quantity

Rate
in Rs.

Amount
in Rs.
276.00
50.00
144.72
56.35
47.82
22.08
131.33
728.30

Amount
in Rs.

205

Canal and Allied Works - Item Unit Rates 2014-15

428.00
1
2
3

Concrete mixer 300/200 ltr ( diesel)


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Total hire charges of Machinery
Aportioned hire charges of
machinery for lug slabs

Hour
Hour
Hour
Hour
Hour
Hour

Description

Unit

Crew for Concrete mixer


Crew for Pump
Crew for Water tanker
Mason Class-I
work inspector
mazdoor
for batching materials / laying CC
for demoulding / oiling / laying
for shifting slabs to curing pond
for stacking after curing
for cleaning & miscellaneous
Total cost of Labour

Hour
Hour
Hour
Day
Day

8.00
0.10
0.20
2.00
1.00

Day
Day
Day
Day
Day

C. LABOUR:
Sl No
1
2
3
4
5
6

Aportioned cost of labourfor lug slabs


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

8.00
8.00
0.10
0.10
0.20
0.20

53.50
85.30
10.20
85.30
402.50
322.20
Rs:

682.40
1.02
8.53
80.50
64.44
1264.89

10%

Rs:

126.49

Rate
in Rs.
189.80
96.10
153.10
385.00
370.00

Amount
in Rs.
1518.40
9.61
30.62
770.00
370.00

3.00
2.00
1.00
1.00
1.00

295.00
295.00
295.00
295.00
295.00
Rs:

885.00
590.00
295.00
295.00
295.00
5058.63

10%

Rs:

505.86

Rs:
Rs:
Rs:
Rs:

728.30
126.49
505.86
1360.65

Rs:
Rs:
Rs.

190.49
1551.14
62.00

Quantity

20.20
0.14 2.80
23.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
25.00 Nos.
each
(A+B+C+D)/25.0
Rate per

IRR-CAW-7-39 Manufacturing 450 x 300 x 30 mm size PCC lining slabs in M-15 grade ( 28 days cube
compressive strength not less than 15 N / sqmm ) cement concrete using 10 mm down graded
coarse aggregate including cost of all materials, machinery, labour, batching, mixing, laying,
compacting, formwork, finishing, curing etc.,complete with initial lead upto 50 m and all lifts.
( Cement content : 300 kg / cum with super plastcizer (0.4% by wt. of cement),
CA : 0.68 cum, FA : 0.43cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Quantity

Cement for mix

kg

270.00

2
3
4
5

Cement for incidentals @ 0.5 kg/slab


Coarse aggregate 10 mm below
Fine aggregate (Un-Screened )
Super Plasticizer
Use rate of moulds for 250 uses
Total cost of Materials

kg
cum
cum
kg
No.

112.50
0.61
0.39
1.08
225.00

225 Nos.
Rate
in Rs.
4.00
4.00
875.00
462.00
80.00
3.50
Rs:

Amount
in Rs.
1080.00
450.00
535.50
178.79
86.40
786.98
3117.68

206

Canal and Allied Works - Item Unit Rates 2014-15

B. MACHINERY:
Sl No
1
2
3

Description

Unit

Hand mixer 45 / 30 ltr


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Total hire charges of Machinery
Aportioned hire charges of
machinery for lining slab

Hour
Hour
Hour
Hour
Hour
Hour

Description

Unit

C. LABOUR:
Sl No

Quantity
8.00
8.00
0.10
0.10
0.20
0.20

90%

Quantity

Crew for Pump


Hour
0.10
Crew for Water tanker
Hour
0.20
Mason Class-I
Day
2.00
work inspector
Day
1.00
mazdoor
for batching / mixing / laying
Day
2.00
for demoulding / cleaning / oiling
Day
2.00
for shifting slabs to curing pond
Day
1.00
for stacking after curing
Day
1.00
for cleaning & miscellaneous
Day
1.00
Total cost of Labour
Aportioned cost of labour for lining
slabs
90%
labour component/unit qty
13.00
Add contractor's profit and overhead charges
0.14 1.80
labour component/unit qty (including contractor's profit)
14.80
1
2
3
4
5

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
225.00 Nos.
each
(A+B+C+D)/225.0
Rate per

Rate
in Rs.
5.50
0.00
10.20
85.30
402.50
322.20
Rs:

Amount
in Rs.
44.00
0.00
1.02
8.53
80.50
64.44
198.49

Rs:

178.64

Rate
in Rs.
96.10
153.10
385.00
370.00

Amount
in Rs.
9.61
30.62
770.00
370.00

295.00
295.00
295.00
295.00
295.00
Rs:

590.00
590.00
295.00
295.00
295.00
3245.23

Rs:

2920.71

Rs:
Rs:
Rs:
Rs:

3117.68
178.64
2920.71
6217.03

Rs:
Rs:
Rs.

870.38
7087.41
31.50

IRR-CAW-7-40 Manucturing 450 x 150 x 30 mm size PCC lug slabs in M-15 grade ( 28 days cube
compressive strength not less than 15 N / sqmm ) cement concrete using 10 mm down graded
coarse aggregate including cost of all materials, machinery, labour, batching, mixing, laying,
compacting, formwork, finishing, curing etc.,complete with initial lead upto 50 m and all lifts.
( Cement content : 300 kg / cum with super plastcizer (0.4% by wt. of cement),
CA : 0.68 cum, FA : 0.43cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Quantity

25 Nos.

Cement for mix

kg

15.00

Rate
in Rs.
4.00

2
3
4
5

Cement for incidentals @ 0.3 kg/slab


Coarse aggregate 10 mm below
Fine aggregate (Un-Screened )
Super Plasticizer
Use rate of moulds for 250 uses

kg
cum
cum
kg
No.

7.50
0.03
0.02
0.06
25.00

4.00
875.00
462.00
80.00
1.86

Amount
in Rs.
60.00
30.00
29.75
9.93
4.80
46.59

207

Canal and Allied Works - Item Unit Rates 2014-15

Total cost of Materials


B. MACHINERY:
Sl No
1
2
3

Description

Unit

Hand mixer 45 / 30 ltr


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Total hire charges of Machinery
Aportioned hire charges of
machinery for lug slabs

Hour
Hour
Hour
Hour
Hour
Hour

Description

Unit

C. LABOUR:
Sl No

Quantity
8.00
8.00
0.10
0.10
0.20
0.20

Rs:

181.07

Rate
in Rs.
5.50
0.00
10.20
85.30
402.50
322.20
Rs:

Amount
in Rs.
44.00
0.00
1.02
8.53
80.50
64.44
198.49

Rs:

19.85

Rate
in Rs.
96.10
153.10
385.00
370.00

Amount
in Rs.
9.61
30.62
770.00
370.00

295.00
295.00
295.00
295.00
295.00
Rs:

590.00
590.00
295.00
295.00
295.00
3245.23

Rs:

324.52

Rs:
Rs:
Rs:
Rs:

181.07
19.85
324.52
525.44

Rs:
Rs:
Rs.

73.56
599.00
24.00

10%

Quantity

Crew for Pump


Hour
0.10
Crew for Water tanker
Hour
0.20
Mason Class-I
Day
2.00
work inspector
Day
1.00
mazdoor
for batching / mixing / laying
Day
2.00
for demoulding / cleaning / oiling
Day
2.00
for shifting slabs to curing pond
Day
1.00
for stacking after curing
Day
1.00
for cleaning & miscellaneous
Day
1.00
Total cost of Labour
Aportioned cost of labour for lug
slabs
10%
labour component/unit qty
13.00
Add contractor's profit and overhead charges
0.14 1.80
labour component/unit qty (including contractor's profit)
14.80
1
2
3
4
5

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
25.00 Nos.
each
(A+B+C+D)/25.0
Rate per

IRR-CAW-7-41 Manufacturing 600 x 300 x 100mm size PCC lining slabs in M-15 grade (28 days cube
compressive strength not less than 15 N/Sqmm) cement concrete using 20mm down
grades coarse aggregate including cost of all materials, machinery, labour, batching,
mixing, laying, compacting, formwork, finishing, curing etc., complete with initial lead upto 50 m
and all lifts.
( Cement content : 300 kg / cum with super plastcizer (0.4% by wt. of cement),
CA : 0.80 cum, FA : 0.45cum, Blending Ratio of CA--65:35)

DATA:

RATE ANALYSIS

UNIT:

225

Nos.

A. MATERIALS :
Sl. No
1
2
3

Particulars
Cement for mix
Cement for incidentals @ 0.5kg/slab
Coarse aggregate 20 mm below

Unit
Kg
Kg
Cum

Quantity

Rate
Amount in
Rs.
in Rs.
1215
4860.00
4.00
112.5
450.00
4.00
2.11 1210.00
2548.26

208

Canal and Allied Works - Item Unit Rates 2014-15

4
5
6
7

Cum
Coarse aggregate 10 mm below
Cum
Fine aggregate (Un-Screened)
kg
Super Plasticizer
No.
Use rate of moulds for 250 uses
Total Cost of Materials Rs.

1.13
1.82
4.86
225

875.00
462.00
80.00
1.23

992.25
842.00
388.80
276.75
10358.06

B. MACHINERY :
Sl. No
1
2
3

Particulars

Unit

Hour
Diesel mixer 300/200
Hour
Fuel/Energy charges
Hour
5 hp pump (diesel)
Hour
Fuel/Energy charges
Hour
Water tanker 8000 ltr
Hour
Fuel/Energy charges
Total hire charges of Machinery
Aportioned hire charges of
machinery @ 90% for lining slab
Rs.

C. LABOUR :
Sl. No

Particulars

Unit

Quantity
8
8
0.1
0.1
0.2
0.2
Rs.
90%

Quantity

1
2
3
4
5

Hour
0.1
Crew for Pump
Hour
0.2
Crew for water tanker
Day
2
Mason Class-I
Day
1
Class II Mason
Mazdoor
Day
2
For batching materials/laying
2
For demoulding/cleaning/oiling
1
For shifting slabs to curing pond
1
For stacking after curing
Day
1
For cleaning & miscellaneous
Total Cost of Labour Rs.
Aportioned cost of labour for lining
90%
slabs Rs.
labour component/unit qty
12.90
Add contractor's profit and overhead charges
0.14 1.80
labour component/unit qty (including contractor's profit)
14.70

ABSTRACT :
A. Cost of Materials
B. Hire Charges of machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
225.00 Nos.
each
(A+B+C+D)/225.0
Rate per

Rate
Amount in
Rs.
in Rs.
428.00
53.50
682.40
85.30
1.02
10.20
8.53
85.30
80.50
402.50
64.44
322.20
1264.89
1138.40

Rate
Amount in
Rs.
in Rs.
9.61
96.10
30.62
153.10
770.00
385.00
345.00
345.00
295.00
295.00
295.00
295.00
295.00

590.00
590.00
295.00
295.00
295.00
3220.23
2898.21

Rs. 10358.055
Rs.
1138.40
Rs.
2898.21
Rs:
14394.66
Rs:
Rs:
Rs.

2015.25
16409.91
72.90

IRR-CAW-7-42 Manucturing 400 x 400 x 30 mm size PCC lining slabs in M-15 grade ( 28 days cube
compressive strength not less than 15 N / sqmm )cement concrete using 10 mm down graded
coarse aggregate including cost of all materials, machinery, labour, batching, mixing, laying,
compacting, formwork, finishing, curing etc.,complete with initial lead upto 50 m and all lifts.
( Cement content : 300 kg / cum with super plastcizer (0.4% by wt. of cement),
CA : 0.68 cum, FA : 0.43cum)

DATA:

RATE ANALYSIS

UNIT :

225 Nos.

A. MATERIALS:

209

Canal and Allied Works - Item Unit Rates 2014-15

Sl No

particulars

Unit

Quantity

Cement for mix

kg

324.00

2
3
4
5

Cement for incidentals @ 0.5 kg/slab


Coarse aggregate 10 mm below
Fine aggregate (Un-Screened )
Super Plasticizer
Use rate of moulds for 250 uses
Total cost of Materials

kg
cum
cum
kg
No.

112.50
0.73
0.46
1.30
225.00

B. MACHINERY:
Sl No
1
2
3

C. LABOUR:
Sl No

Description

Unit

Hand mixer 45 / 30 ltr


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Total hire charges of Machinery
Aportioned hire charges of
machinery for lining slab

Hour
Hour
Hour
Hour
Hour
Hour

Description

Unit

Quantity
8.00
8.00
0.10
0.10
0.20
0.20

90%

Quantity

Crew for Pump


Hour
0.10
Crew for Water tanker
Hour
0.20
Mason Class-I
Day
2.00
work inspector
Day
1.00
mazdoor
for batching / mixing / laying
Day
2.00
for demoulding / cleaning / oiling
Day
2.00
for shifting slabs to curing pond
Day
1.00
for stacking after curing
Day
1.00
for cleaning & miscellaneous
Day
1.00
Total cost of Labour
Aportioned cost of labour for lining
slabs
90%
labour component/unit qty
13.00
Add contractor's profit and overhead charges
0.14 1.80
labour component/unit qty (including contractor's profit)
14.80
1
2
3
4
5

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
225.00 Nos.
each
(A+B+C+D)/225.0
Rate per

Rate
in Rs.
4.00

Amount
in Rs.
1296.00
450.00

4.00
875.00
462.00
80.00
3.52
Rs:

642.60
214.55
103.68
793.05
3499.89

Rate
in Rs.
5.50
0.00
10.20
85.30
402.50
322.20
Rs:

Amount
in Rs.
44.00
0.00
1.02
8.53
80.50
64.44
198.49

Rs:

178.64

Rate
in Rs.
96.10
153.10
385.00
370.00

Amount
in Rs.
9.61
30.62
770.00
370.00

295.00
295.00
295.00
295.00
295.00
Rs:

590.00
590.00
295.00
295.00
295.00
3245.23

Rs:

2920.71

Rs:
Rs:
Rs:
Rs:

3499.89
178.64
2920.71
6599.23

Rs:
Rs:
Rs.

923.89
7523.12
33.40

IRR-CAW-7-43 Manufacturing 400 x 150 x 30 mm size PCC lug slabs in M-15 grade ( 28 days cube
compressive strength not less than 15 N /sqmm ) cement concrete using 10 mm down graded
coarse aggregate including cost of all materials, machinery, labour, batching, mixing, laying,
compacting, formwork, finishing, curing etc.,complete with initial lead upto 50 m and all lifts.
( Cement content : 300 kg / cum with super plastcizer (0.4% by wt. of cement),
CA : 0.68 cum, FA : 0.43cum)

DATA:

RATE ANALYSIS

UNIT :

25 Nos.

210

Canal and Allied Works - Item Unit Rates 2014-15

A. MATERIALS:
Sl No

particulars

Unit

Quantity

Cement for mix

kg

13.50

2
3
4
5

Cement for incidentals @ 0.3 kg/slab


Coarse aggregate 10 mm below
Fine aggregate (Un-Screened )
Super Plasticizer
Use rate of moulds for 250 uses
Total cost of Materials

kg
cum
cum
kg
No.

7.50
0.03
0.02
0.05
25.00

B. MACHINERY:
Sl No
1
2
3

C. LABOUR:
Sl No

Description

Unit

Hand mixer 45 / 30 ltr


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Total hire charges of Machinery
Aportioned hire charges of
machinery for lug slabs

Hour
Hour
Hour
Hour
Hour
Hour

Description

Unit

Quantity
8.00
8.00
0.10
0.10
0.20
0.20

10%

Quantity

Crew for Pump


Hour
0.10
Crew for Water tanker
Hour
0.20
Mason Class-I
Day
2.00
work inspector
Day
1.00
mazdoor
for batching / mixing / laying
Day
2.00
for demoulding / cleaning / oiling
Day
2.00
for shifting slabs to curing pond
Day
1.00
for stacking after curing
Day
1.00
for cleaning & miscellaneous
Day
1.00
Total cost of Labour
Aportioned cost of labour for lug
10%
slabs
labour component/unit qty
13.00
Add contractor's profit and overhead charges
0.14 1.80
labour component/unit qty (including contractor's profit)
14.80
1
2
3
4
5

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
25.00 Nos.
each
(A+B+C+D)/25.0
Rate per

Rate
in Rs.
4.00

Amount
in Rs.
54.00
30.00

4.00
875.00
462.00
80.00
1.83
Rs:

26.78
8.94
4.32
45.74
169.78

Rate
in Rs.
5.50
0.00
10.20
85.30
402.50
322.20
Rs:

Amount
in Rs.
44.00
0.00
1.02
8.53
80.50
64.44
198.49

Rs:

19.85

Rate
in Rs.
96.10
153.10
385.00
370.00

Amount
in Rs.
9.61
30.62
770.00
370.00

295.00
295.00
295.00
295.00
295.00
Rs:

590.00
590.00
295.00
295.00
295.00
3245.23

Rs:

324.52

Rs:
Rs:
Rs:
Rs:

169.78
19.85
324.52
514.15

Rs:
Rs:
Rs.

71.98
586.13
23.40

IRR-CAW-7-44 Providing and laying uncoursed rubble stone masonry in CM 1 : 5 proportion for canal side
lining using stones and chips from approved quarry including cost of all materials,
machinery, labour, forming weep holes at specified intervals, finishing, curing etc., complete
with initial lead upto 50 m and all lifts.
(Thickness of the masonry assumed: 0.3 m, rubble stones : 0.96 cum, Stone Chips : 0.15cum,
Through Stones 20 x 20 x 30cm : 1/sqm)

DATA:

RATE ANALYSIS

UNIT :

10.00 cum

211

Canal and Allied Works - Item Unit Rates 2014-15

A. MATERIALS:
Sl No

particulars

Unit

Quantity

1
2

Cement 43 Gr
Sand (Screened )

kg
cum

1152.00
4.00

3
4
5

Uncoursed rubble stones at quarry


Through stones 20x20x30 cm
Stone chips at quarry
Total cost of Materials

cum
Nos
cum

9.60
32.00
1.50

B. MACHINERY:
Sl No
1

C. LABOUR:
Sl No

Description

Unit

5 hp pump ( diesel )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour

Description

Unit

Quantity
4.00
4.00

Quantity

Operator pump
Hour
4.00
work inspector
Day
1.00
Mason Class I
Day
2.00
Mason Class II
Day
2.00
mazdoor
Day
8.00
Cartman with Double Bullock cart for
6
Day
1.00
water
Total cost of Labour
labour component/unit qty
496.90
Add contractor's profit and overhead charges
0.14 69.60
labour component/unit qty (including contractor's profit)
566.50
1
2
3
4
5

Rate
in Rs.
4.00
606.00

Amount
in Rs.
4608.00
2424.00
3052.80

318.00
23.00
340.00
Rs:

736.00
510.00
11330.80

Rate
in Rs.
10.20
85.30
Rs:

Amount
in Rs.
40.80
341.20
382.00

Rate
in Rs.
96.10
370.00
385.00
345.00
295.00

Amount
in Rs.
384.40
370.00
770.00
690.00
2360.00
395.00

395.00
Rs:

4969.40

Rs:
Rs:
Rs:
Rs:

11330.80
382.00
4969.40
16682.20

Rs:
Rs:
Rs.

2335.51
19017.71
1901.80

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
10.00 cum
cum
(A+B+C+D)/10.0
Rate per

IRR-CAW-7-45 Providing and laying uncoursed rubble stone masonry in CM 1:5 proportion for canal side
lining using stones from approved quarry including cost of all materials, machinery,
labour, forming weep holes at specified intervals, finishing, curing etc., complete
with initial lead upto 50m and all lifts.(without pin headers) : 1.1 cum)
(Thickness of the Masonry assumed: 0.3 m , rubble stones

DATA:

RATE ANALYSIS

UNIT:

10

Cum

A.
MATERIALS
:
Sl. No
1
2
3

Particulars
Cement 43 Gr
Sand (Screened)
Uncoursed rubble stones at quarry

Unit
Kg
Cum
Cum

Total Cost of Materials Rs.

Quantity

Rate
Amount in
Rs.
in Rs.
979.2
3916.80
4.00
3.4 606.00
2060.40
11
3498.00
318.00
9475.2

212

Canal and Allied Works - Item Unit Rates 2014-15

B. MACHINERY :
Sl. No
1
2

Particulars

Unit

Hand Mixing Charges


Hour
5 hp pump (diesel)
Hour
Fuel / Energy charges
Hour
Total hire charges of Machinery

Quantity

Rate
Amount in
Rs.
in Rs.
8
5.50
44.00
4
40.80
10.20
5
426.50
85.30
511.30

Rs.

C. LABOUR :
Sl. No

Particulars

Unit

Quantity

1
2
3
4
5

Operator pump
Hour
4
Mason Class I
Day
13
Mason Class II
Day
6
Mazdoor
Day
29
Cartman with Double Bullock cart for
Day
1
water
Total Cost of Labour Rs.
labour component/unit qty
1640.90
Add contractor's profit and overhead charges
0.14 229.70
labour component/unit qty (including contractor's profit)
1870.60

ABSTRACT :
A. Cost of Materials
B. Hire Charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
10.00 Cum
Cum
(A+B+C+D)/10.0
Rate per

Rate
Amount in
Rs.
in Rs.
384.40
96.10
5005.00
385.00
2070.00
345.00
295.00
8555.00
395.00
395.00
16409.40

Rs.
Rs.
Rs.
Rs:

9475.2
511.3
16409.40
26395.90

Rs:
Rs:
Rs.

3695.43
30091.33
3009.10

IRR-CAW-7-46 Providing and laying uncoursed rubble stone masonry in CM 1 : 5 proportion for canal side
lining using stones and chips from canal excavation including cost of all materials,
machinery, labour, forming weep holes at specified interval, finishing, curing etc., complete
with initial lead upto 50 m and all lifts.
( rubble stones : 0.96 cum, Stone Chips : 0.15cum, Through Stones 20 x 20 x 30cm : 1/sqm)
Note:

Stones and chips will be issued from dump yard at specified issue rate.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5

particulars

Unit

Cement 43 Gr
Sand (Screened )
Uncoursed rubble at dump yard
Through stones 20x20x30 cm
Stone chips at dump yard
Total cost of Materials

kg
cum
cum
Nos
cum

B. MACHINERY:
Sl No
1

C. LABOUR:
Sl No

UNIT :

Description

Unit

5 hp pump ( diesel )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour

Description

Unit

Quantity
1144.00
4.00
9.60
32.00
1.50

Quantity
4.00
4.00

Quantity

10.00 cum
Rate
in Rs.
4.00
606.00
155.00
23.00
175.00
Rs:

Amount
in Rs.
4576.00
2424.00
1488.00
736.00
262.50
9486.50

Rate
in Rs.
10.20
85.30
Rs:

Amount
in Rs.
40.80
341.20
382.00

Rate

Amount

213

Canal and Allied Works - Item Unit Rates 2014-15

Operator pump
Hour
4.00
work inspector
Day
1.00
Mason Class I
Day
2.00
Mason Class II
Day
2.00
Crowbarman
Day
1.00
mazdoor
Day
9.00
Cartman with Double Bullock cart for
7
Day
1.00
water
Total cost of Labour
labour component/unit qty
560.90
Add contractor's profit and overhead charges
0.14 78.50
labour component/unit qty (including contractor's profit)
639.40
1
2
3
4
5
6

in Rs.
96.10
370.00
385.00
345.00
345.00
295.00

in Rs.
384.40
370.00
770.00
690.00
345.00
2655.00
395.00

395.00
Rs:

5609.40

Rs:
Rs:
Rs:
Rs:

9486.50
382.00
5609.40
15477.90

Rs:
Rs:
Rs.

2166.91
17644.81
1764.50

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
10.00 cum
cum
(A+B+C+D)/10.0
Rate per

IRR-CAW-7-47 Providing and laying uncoursed rubble stone masonry in CM 1:5 proportion for canal side lining
using stones from canal excavation including cost of all materials, machinery, labour, forming weep holes at
specified intervals, finishing, curing etc., complete with initial lead upto 50m and all lifts.
( rubble stones : 1.1cum, cement : 98kg, sand 0.34 cum)

DATA:

RATE ANALYSIS

UNIT:

10

Cum

A.
MATERIALS
:
Sl. No
1
2
3

Particulars

Unit

Quantity

Rate
Amount in
Rs.
in Rs.
980
3920.00
4.00
3.4 606.00
2060.40
11 155.00
1705.00
7685.4

Cement 43 Gr
Kg
Sand (Screened)
Cum
Uncoursed rubble at dump yard
Cum
Total Cost of Materials Rs.
B. MACHINERY :

Sl. No
1
2

Particulars

Unit

Hand Mixing Charges


Hour
5 hp pump (diesel)
Hour
Fuel / Energy charges
Hour
Total hire charges of Machinery

Quantity

Rs.

Rate
Amount in
Rs.
in Rs.
8
5.50
44.00
4
40.80
10.20
5
426.50
85.30
511.30

C. LABOUR :
Sl. No
1
2
3
4
5

Particulars

Unit

Quantity

Operator pump
Hour
4
Mason Class I
Day
13
Mason Class II
Day
6
Mazdoor
Day
29
Cartman with double bullock cart
Day
1
Total Cost of Labour Rs.
labour component/unit qty
1640.90
Add contractor's profit and overhead charges
0.14 229.70
labour component/unit qty (including contractor's profit)
1870.60

Rate
Amount in
Rs.
in Rs.
384.40
96.10
5005.00
385.00
2070.00
345.00
295.00
8555.00
395.00
395.00
16409.40

214

Canal and Allied Works - Item Unit Rates 2014-15

ABSTRACT :
A. Cost of Materials
B. Hire Charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
10.00 Cum
Cum
(A+B+C+D)/10.0
Rate per

Rs.
Rs.
Rs.
Rs:

7685.4
511.3
16409.40
24606.10

Rs:
Rs:
Rs.

3444.85
28050.95
2805.10

IRR-CAW-8

ROCK PITCHING:

IRR-CAW-8-1

Providing and constructing 25 cm thick dry rubble stone pitching with pin headers at 2 per
sqm including cost of all materials, labour, hand packing, finishing etc., complete with initial
lead upto 50 m and all lifts.
( rubble stones : 0.23 cum/sqm, Stone Chips : 0.0375cum/sqm, Pin Headers 30cm : 2/sqm)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

Uncoursed rubble stones at quarry

UNIT :
Unit

cum

Quantity

23.00

100.00 sqm
Rate
in Rs.

Amount
in Rs.
7314.00

318.00
4600.00

2
3

Pin header (Through stone) 30 cm


Stone chips at quarry
Total cost of Materials

B. MACHINERY:
Sl No

Description

Nos
cum

Unit

200.00
3.75

Quantity

Nill

0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No
1
2
3

Description
work inspector
Mason Class II
mazdoor

Unit

Quantity

Day
Day
Day

1.00
5.00
6.00

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

1275.00
13189.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
370.00
345.00
295.00
Rs:

Amount
in Rs.
370.00
1725.00
1770.00
3865.00

Rs:
Rs:
Rs:
Rs:

13189.00
0.00
3865.00
17054.00

Rs:
Rs:
Rs.

2387.56
19441.56
194.40

38.70
0.14 5.40
44.10

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
100.00 sqm
sqm
(A+B+C+D)/100.0
Rate per
Note:

23.00
340.00
Rs:

If 15 cm thick murum bed is to be provided below pitching


(Murum : 0.18 cum/sqm)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Quantity

100.00 sqm
Rate

Amount

215

Canal and Allied Works - Item Unit Rates 2014-15

Murum

cum

18.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No

Description

Unit

Quantity

Nill

0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No
1

Description
mazdoor

Unit

Quantity

Day

4.00

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

in Rs.
107.00
0.00
Rs:

in Rs.
1926.00
0.00
1926.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
295.00
Rs:

Amount
in Rs.
1180.00
1180.00

Rs:
Rs:
Rs:
Rs:

1926.00
0.00
1180.00
3106.00

Rs:
Rs:
Rs.

434.84
3540.84
35.40

11.80
0.14 1.70
13.50

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
100.00 sqm
sqm
(A+B+C+D)/100.0
Rate per

IRR-CAW-8-1-A Providing and constructing 22.5 cm thick dry rubble stone pitching with pin headers at 2 per
(New Item4 - 201112)
sqm including cost of all materials, labour, hand packing, finishing etc., complete with initial

lead upto 50 m and all lifts.


( rubble stones : 0.207 cum/sqm, Stone Chips : 0.03375cum/sqm, Pin Headers 30cm : 2/sqm)
(For Maintenance works)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

Uncoursed rubble stones at quarry

UNIT :
Unit

cum

Quantity

20.70

100.00 sqm
Rate
in Rs.

Amount
in Rs.
6582.60

318.00
4600.00

2
3

Pin header (Through stone) 30 cm


Stone chips at quarry
Total cost of Materials

B. MACHINERY:
Sl No

Description

Nos
cum

Unit

200.00
3.375

Quantity

Nill

0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No
1
2
3

Description
work inspector
Mason Class II
mazdoor

Unit

Quantity

Day
Day
Day

1.00
5.00
6.00

Total cost of Labour


labour component/unit qty

23.00
340.00
Rs:

1147.50
12330.10

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
370.00
345.00
295.00
Rs:

Amount
in Rs.
370.00
1725.00
1770.00
3865.00

38.70

216

Canal and Allied Works - Item Unit Rates 2014-15

Add contractor's profit and overhead charges


labour component/unit qty (including contractor's profit)

0.14 5.40
44.10

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
100.00 sqm
sqm
(A+B+C+D)/100.0
Rate per
IRR-CAW-8-2

Rs:
Rs:
Rs:
Rs:

12330.10
0.00
3865.00
16195.10

Rs:
Rs:
Rs.

2267.31
18462.41
184.60

Providing and constructing 25 cm thick dry rubble stone pitching including cost of all materials, labour,
hand packing, finishing etc., complete
( rubble stones : 0.275 cum/sqm)

DATA:

RATE ANALYSIS

UNIT:

100

Sqm.

A. MATERIALS :
Sl. No
1

Particulars
Uncoursed rubble stones at quarry

Unit

Quantity

Cum

Rate
in Rs.

Amount in
Rs.
8745.00

27.50
318.00

Total Cost of Materials Rs.

8745

B. MACHINERY :
Sl. No

Particulars

Nil

Unit

Quantity
0
0

Total hire charges of Machinery

Rate
in Rs.

Amount in
Rs.
0
0

Rs.

C. LABOUR :
Sl. No

Particulars

Unit

Quantity

Rate
Amount in
Rs.
in Rs.
1
Mason Class II
Day
5.50 345.00
1897.50
2
Day
24.75 295.00
7301.25
Mazdoor
Total Cost of Labour Rs.
9198.75
labour component/unit qty
92.00
Add contractor's profit and overhead charges
0.14 12.90
labour component/unit qty (including contractor's profit)
104.90

ABSTRACT :
A. Cost of Materials
B. Hire Charges of Machinery
C. Cost of Labour

Rs.
Rs.
Rs.
Rs:

8745
0
9198.75
17943.75

D. Add for contractor's profit and overheads on (A+B+C)


14%
Rs:
Total cost for
100.00 Sqm.
Rs:
Sqm.
(A+B+C+D)/100.0
Rs.
Rate per
If 15 cm thick murum bed is to be
NOTE:
provided below pitching add
in Rs.
( As per rate analysis under item IRR-CAW-8-1- Note )

2512.13
20455.88
204.60

Total

35.40

IRR-CAW-8-2-A Providing and constructing 225 mm thick dry rubble stone pitching including cost of all materials, labour,
(New Item5 - 2011hand packing, finishing etc., complete
12)

( rubble stones : 0.2475 cum/sqm) (For Maintenance Works)

217

Canal and Allied Works - Item Unit Rates 2014-15

RATE ANALYSIS

DATA:

UNIT:

100

Sqm.

A. MATERIALS :
Sl. No
1
2

Particulars

Unit

Quantity

Rate
Amount in
Rs.
in Rs.
24.75 144.00
3564.00
3.40 340.00
1156.00
4720

Rough Stone for Revetment


Cum
Stone Chips at Quarry
Cum
Total Cost of Materials Rs.
B. MACHINERY :

Sl. No

Particulars

Nil

Unit

Quantity

Rate
in Rs.

0
0

Total hire charges of Machinery

Amount in
Rs.
0
0

Rs.

C. LABOUR :
Sl. No

Particulars

Unit

Quantity

Rate
Amount in
Rs.
in Rs.
1
Mason Class II
Day
4.95 345.00
1707.75
2
Day
22.28 295.00
6571.13
Mazdoor
Total Cost of Labour Rs.
8278.88
labour component/unit qty
82.80
Add contractor's profit and overhead charges
0.14 11.60
labour component/unit qty (including contractor's profit)
94.40

ABSTRACT :
A. Cost of Materials
B. Hire Charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
100.00 Sqm.
Sqm.
(A+B+C+D)/100.0
Rate per
IRR-CAW-8-3

Rs.
Rs.
Rs.
Rs:

4720
0
8278.88
12998.88

Rs:
Rs:
Rs.

1819.84
14818.72
148.20

Providing and constructing 30 cm thick dry rubble stone pitching with pin headers at 2 per
sqm including cost of all materials, labour, hand packing, finishing etc., complete with initial
lead upto 50 m and all lifts.
( rubble stones : 0.275 cum/sqm, Stone Chips : 0.045cum/sqm, Pin Headers 30cm : 2/sqm)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

Uncoursed rubble stones at quarry

UNIT :
Unit

cum

Quantity

27.50

100.00 sqm
Rate
in Rs.

Amount
in Rs.
8745.00

318.00
4600.00

2
3

Pin header (Through stone) 30 cm


Stone chips at quarry
Total cost of Materials

B. MACHINERY:
Sl No
1

Description
Nill
Total hire charges of Machinery

Nos
cum

Unit

200.00
4.50

Quantity
0.00
0.00

23.00
340.00
Rs:

Rate
in Rs.
0.00
0.00
Rs:

1530.00
14875.00

Amount
in Rs.

0.00

218

Canal and Allied Works - Item Unit Rates 2014-15

C. LABOUR:
Sl No
1
2
3

Description
work inspector
Mason Class II
mazdoor

Unit

Quantity

Day
Day
Day

1.00
5.00
6.00

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
100.00 sqm
sqm
(A+B+C+D)/100.0
Rate per
If 15 cm thick murum bed is to be
NOTE:
provided below pitching add
( As per rate analysis under item IRRCAW-8-1- Note )

DATA:

Amount
in Rs.
370.00
1725.00
1770.00
3865.00

Rs:
Rs:
Rs:
Rs:

14875.00
0.00
3865.00
18740.00

Rs:
Rs:
Rs.

2623.6
21363.60
213.60

38.70
0.14 5.40
44.10

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

IRR-CAW-8-4

Rate
in Rs.
370.00
345.00
295.00
Rs:

35.40

Providing and Constructing 30 cm thick dry rubble stone pitching


including cost of all materials,labour,hand packing,finishing etc.,complete
( rubble stones : 0.33 cum/sqm)

RATE ANALYSIS
A. MATERIALS :
Sl No

Particulars

Uncoursed rubble stones at Quarry

UNIT :
Unit

Cum

Quantity

33.00

100.00 sqm
Rate
in Rs

Amount
in Rs
10494.00

318.00

( Included in material Rate)


Total Cost of materials
Rs :

10494.00

B.MACHINERY :
Sl No

Description

Nill

Unit

Quantity
0.00
0.00

Rate
in Rs

Amount
in Rs

0.00
0.00

Total hire charges of machinery


Rs :

0.00

C.LABOUR :
Sl No

Description

1
2

Unit

Quantity

Mason Class II
Day
6.60
Mazdoor
Day
29.70
Total cost of labour
Rs :
labour component/unit qty
110.40
Add contractor's profit and overhead charges
0.14 15.50
labour component/unit qty (including contractor's profit)
125.90
ABSTRACT
A.Cost of Materials including ryolty charges

Rate
in Rs
345.00
295.00

Amount
in Rs
2277.00
8761.50
11038.50

Rs:

10494.00

219

Canal and Allied Works - Item Unit Rates 2014-15

B. Hire charges of Machinery


C.Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
100.00 sqm
sqm
(A+B+C+D)/100.0
Rate per
If 15 cm thick murum bed is to be
NOTE:
provided below pitching
Add ( As per rate analysis under item
IRR-CAW-8-1 - Note)

IRR-CAW-8-5

Rs:
Rs:
Rs:

0.00
11038.50
21532.50

Rs:
Rs:
Rs.

3014.55
24547.05
245.50

Rs

35.40

Providing and constructing 45 cm thick dry rubble stone pitching with pin headers at 2 per
sqm including cost of all materials, labour, hand packing, finishing etc., complete with initial
lead upto 50 m and all lifts.
( rubble stones : 0.40 cum/sqm, Stone Chips : 0.0675cum/sqm, Pin Headers 45cm : 2/sqm)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

Uncoursed rubble stones at quarry

UNIT :
Unit

cum

Quantity

40.00

100.00 sqm
Rate
in Rs.

Amount
in Rs.
12720.00

318.00
7800.00

2
3

Pin header (Through stone) 45 cm


Stone chips at quarry
Total cost of Materials

B. MACHINERY:
Sl No

Description

Nos
cum

Unit

200.00
6.75

Quantity

Nill

0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No
1
2
3

Description
work inspector
Mason Class II
mazdoor

Unit

Quantity

Day
Day
Day

1.00
7.00
9.00

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

2295.00
22815.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.

Rate
in Rs.
370.00
345.00
295.00
Rs:

Amount
in Rs.
370.00
2415.00
2655.00
5440.00

Rs:
Rs:
Rs:
Rs:

22815.00
0.00
5440.00
28255.00

Rs:
Rs:
Rs.

3955.7
32210.70
322.10

0.00

54.40
0.14 7.60
62.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
100.00 sqm
sqm
(A+B+C+D)/100.0
Rate per
If 15 cm thick murum bed is to be
NOTE:
provided below pitching add
( As per rate analysis under item IRRCAW-8-1 - Note )

IRR-CAW-8-6

39.00
340.00
Rs:

35.40

Providing and Constructing 45 cm thick dry rubble stone pitching


including cost of all materials,labour,hand packing,finishing etc.,complete

220

Canal and Allied Works - Item Unit Rates 2014-15

( rubble stones : 0.495 cum/sqm)

DATA:

RATE ANALYSIS
A. MATERIALS :
Sl No

UNIT :

Particulars

Uncoursed rubble stones at Quarry

Unit

Cum

Quantity

49.50

100.00 sqm
Rate
in Rs

Amount
in Rs
15741.00

318.00

( Included in material Rate)


Total Cost of materials
Rs :

15741.00

B.MACHINERY :
Sl No

Description

Nill

Unit

Quantity
0.00
0.00

Rate
in Rs

Amount
in Rs
0.00
0.00

0.00
0.00

Total hire charges of machinery


Rs :

0.00

C.LABOUR :
Sl No

Description

Unit

Quantity

1
2

Mason Class II
Day
9.90
Mazdoor
Day
44.55
Total cost of labour
Rs :
labour component/unit qty
165.60
Add contractor's profit and overhead charges
0.14 23.20
labour component/unit qty (including contractor's profit)
188.80
ABSTRACT
A.Cost of Materials including ryolty charges
B. Hire charges of Machinery
C.Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
100.00 sqm
sqm
(A+B+C+D)/100.0
Rate per
If 15 cm thick murum bed is to be
NOTE:
provided below pitching
Add ( As per rate analysis under item
IRR-CAW-8-1 - Note)

IRR-CAW-8-7

Rate
in Rs

Amount
in Rs

345.00
295.00

3415.50
13142.25
16557.75

Rs:
Rs:
Rs:
Rs:

15741.00
0.00
16557.75
32298.75

Rs:
Rs:
Rs.

4521.83
36820.58
368.20

Rs

35.40

Providing and constructing 30 cm thick rubble stone pitching set in CM 1: 5 proportion with
pin headers at 2 per sqm in including cost of all materials, labour, packing chips and mortar,
finishing, curing etc., complete with initial lead upto 50 m and all lifts.
( rubble stones : 0.275 cum/sqm, Stone Chips : 0.045cum/sqm, Pin Headers 30cm : 2/sqm)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

Uncoursed rubble stones at quarry

UNIT :
Unit

cum

Quantity

27.50

100.00 sqm
Rate
in Rs.

Amount
in Rs.
8745.00

318.00
4600.00

2
3
4

Pin header (Through stone) 30 cm


Stone chips @ 15 % at quarry
Cement

Nos
cum
kg

200.00
4.50
3000.00

23.00
340.00
4.00

1530.00
12000.00

221

Canal and Allied Works - Item Unit Rates 2014-15

Sand (Screened )
Total cost of Materials

B. MACHINERY:
Sl No
1

Description

cum

Unit

5 hp pump ( diesel )
Fuel / Energy charges
Total hire charges of Machinery

C. LABOUR:
Sl No

Description

10.50

Quantity
2.00
2.00

Unit

Quantity

Crew for Pump


Hour
2.00
work inspector
Day
1.00
Mason Class II
Day
5.00
mazdoor
Day
12.00
Catrman with double bullock cart
Day
2.00
Total cost of Labour
labour component/unit qty
66.20
Add contractor's profit and overhead charges
0.14 9.30
labour component/unit qty (including contractor's profit)
75.50
1
2
3
4
5

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
100.00 sqm
sqm
(A+B+C+D)/100.0
Rate per
If 15 cm thick murum bed is to be
NOTE:
provided below pitching add
( As per rate analysis under item IRRCAW-8-1 - Note )

IRR-CAW-8-8

606.00
Rs:

6363.00
33238.00

Rate
in Rs.
10.20
85.30
Rs:

Amount
in Rs.
20.40
170.60
191.00

Rate
in Rs.
96.10
370.00
345.00
295.00
395.00
Rs:

Amount
in Rs.
192.20
370.00
1725.00
3540.00
790.00
6617.20

Rs:
Rs:
Rs:
Rs:

33238.00
191.00
6617.20
40046.20

Rs:
Rs:
Rs.

5606.47
45652.67
456.50
35.40

Providing and Constructing 30 cm thick rubble stone pitching set in CM 1:5 Proportion
including cost of all materials,labour, packing chips and mortar ,finishing etc.,complete
( rubble stones : 0.33 cum/sqm )

DATA:

RATE ANALYSIS

UNIT :

100.00 Sqm

A. MATERIALS :
Sl No

Particulars

Unit

Quantity

Uncoursed rubble stones at Quarry

Cum

33.00

2
3

Cement
Sand (Screened)
Total Cost of materials

Kg
Cum

3232.00
11.22

Rate
in Rs

Amount
in Rs
10494.00

318.00
4.00
606.00

Rs :

12928.00
6799.32
30221.32

B.MACHINERY :
Sl No

Description

Nill
Total hire charges of machinery
Rs :

Unit

Quantity
0.00

Rate
in Rs
0.00

Amount
in Rs
0.00
0.00

C.LABOUR :

222

Canal and Allied Works - Item Unit Rates 2014-15

Sl No

Description

Unit

Quantity

1
2
3

Mason Class I
Day
0.54
Mason Class II
Day
1.26
Mazdoor
Day
2.80
Total cost of labour
Rs :
labour component/unit qty
14.70
Add contractor's profit and overhead charges
0.14 2.10
labour component/unit qty (including contractor's profit)
16.80
ABSTRACT
A.Cost of Materials
B. Hire charges of Machinery
C.Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
100.00 Sqm
Sqm
(A+B+C+D)/100.0
Rate per
If 15 cm thick murum bed is to be
NOTE:
provided below pitching
Add ( As per rate analysis under item
IRR-CAW-8-1 - Note)

IRR-CAW-8-9

Rate
in Rs

Amount
in Rs
207.90
434.70
826.00

385.00
345.00
295.00

1468.60

Rs:
Rs:
Rs:
Rs:

30221.32
0.00
1468.60
31689.92

Rs:
Rs:
Rs.

4436.59
36126.51
361.30

Rs

35.40

Providing and constructing 30 cm thick dry khandki stone pitching using 20 to 25 cm size
khandki stones with pin headers at 2 per sqm including cost of all materials, labour, hand
packing, finishing etc., complete with initial lead upto 50 m and all lifts.
( Khandki stones 20- 25 cm height : 1200 Nos/sqm, Stone Chips : 0.045cum/sqm,
Pin Headers 30cm : 2/sqm)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Quantity

Khandki stones 20-25 cm height

Nos

1200.00

2
3

Pin header (Through stone) 30 cm


Stone chips
Total cost of Materials

Nos
cum

200.00
4.50

B. MACHINERY:
Sl No

Description

Unit

Quantity

Nil

0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No
1
2
3

Description
work inspector
Mason Class II
mazdoor

Unit

Quantity

Day
Day
Day
Total cost of Labour

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

1.00
5.00
6.00

100.00 sqm
Rate
in Rs.
13.00

Amount
in Rs.
15600.00
4600.00

23.00
340.00
Rs:

1530.00
21730.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
370.00
345.00
295.00
Rs:

Amount
in Rs.
370.00
1725.00
1770.00
3865.00

Rs:
Rs:
Rs:

21730.00
0.00
3865.00

38.70
0.14 5.40
44.10

223

Canal and Allied Works - Item Unit Rates 2014-15

Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
100.00 sqm
sqm
(A+B+C+D)/100.0
Rate per
If 15 cm thick murum bed is to be
NOTE:
provided below pitching add
( As per rate analysis under item IRRCAW-8-1 - Note )

Rs:

25595.00

Rs:
Rs:
Rs.

3583.3
29178.30
291.80
35.40

IRR-CAW-8-10 Providing and constructing 45 cm thick dry khandki stone pitching using 25 to 30 cm size
khandki stones with pin headers at 2 per sqm including cost of all materials, labour, hand
packing, finishing etc., complete with initial lead upto 50 m and all lifts.
( Khandki stones 25- 30 cm height : 1200 Nos/sqm, Stone Chips : 0.0675cum/sqm,
Pin Headers 45cm : 2/sqm)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3

UNIT :

particulars

Unit

Khandki stones 25-30 cm height


Pin headers 45 cm
Stone chips
Total cost of Materials

Nos
Nos
cum

B. MACHINERY:
Sl No

Description

Unit

Quantity
730.00
200.00
6.75

Quantity

Nil

0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No
1
2
3

Description
work inspector
Mason Class II
mazdoor

Unit

Quantity

Day
Day
Day

1.00
7.00
9.00

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

100.00 sqm
Rate
in Rs.
16.00
39.00
340.00
Rs:

Amount
in Rs.
11680.00
7800.00
2295.00
21775.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
370.00
345.00
295.00
Rs:

Amount
in Rs.
370.00
2415.00
2655.00
5440.00

Rs:
Rs:
Rs:
Rs:

21775.00
0.00
5440.00
27215.00

Rs:
Rs:
Rs.

3810.1
31025.10
310.30

54.40
0.14 7.60
62.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
100.00 sqm
sqm
(A+B+C+D)/100.0
Rate per
If 15 cm thick murum bed is to be
NOTE:
provided below pitching add
( As per rate analysis under item IRRCAW-8-1 - Note )

35.40

IRR-CAW-8-11 Providing and constructing 30 cm thick khandki stone pitching using 20 to 25 cm size
khandki stones with pin headers at 2 per sqm set in CM 1 : 5 proportion with pointing joints in
CM 1:3 proportion including cost of all materials, labour, packing chips and mortar, finishing,

224

Canal and Allied Works - Item Unit Rates 2014-15

curing etc.complete with initial lead upto 50 m and all lifts.


( Khandki stones 20- 25 cm height : 1200 Nos/sqm, Stone Chips : 0.045cum/sqm,
Pin Headers 30cm : 2/sqm)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5

particulars

Unit

Khandki stones 20-25 cm height


Pin headers 30 cm long
Stone chips @ 15 % at quarry
Cement
Sand (Screened )
Total cost of Materials

Nos
Nos
cum
kg
cum

B. MACHINERY:
Sl No
1

UNIT :

Description

Unit

5 hp diesel pump
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour

Description

Unit

C. LABOUR:
Sl No

Quantity
1200.00
200.00
4.50
2902.00
9.67

Quantity
2.00
2.00

Quantity

Crew for Pump


Hour
2.00
work inspector
Day
1.00
Cartman with double bullock cart
Day
2.00
Mason Class II
Day
5.00
mazdoor
Day
11.00
Total cost of Labour
labour component/unit qty
63.20
Add contractor's profit and overhead charges
0.14 8.80
labour component/unit qty (including contractor's profit)
72.00
1
2
3
4
5

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
100.00 sqm
sqm
(A+B+C+D)/100.0
Rate per
If 15 cm thick murum bed is to be
NOTE:
provided below pitching add
( As per rate analysis under item IRRCAW-8-1 - Note )

100.00 sqm
Rate
in Rs.
13.00
23.00
340.00
4.00
606.00
Rs:

Amount
in Rs.
15600.00
4600.00
1530.00
11608.00
5860.02
39198.02

Rate
in Rs.
10.20
85.30
Rs:

Amount
in Rs.
20.40
170.60
191.00

Rate
in Rs.
96.10
370.00
395.00
345.00
295.00
Rs:

Amount
in Rs.
192.20
370.00
790.00
1725.00
3245.00
6322.20

Rs:
Rs:
Rs:
Rs:

39198.02
191.00
6322.20
45711.22

Rs:
Rs:
Rs.

6399.57
52110.79
521.10
35.40

IRR-CAW-8-12 Providing and constructing 45 cm thick khandki stone pitching using 25 to 30 cm stones
with pin headers at 2 per sqm set in CM 1 : 5 proportion with pointing joints in CM 1 : 3
proportion including cost of all materials, labour, packing chips and mortar, finishing, curing
etc., complete with initial lead upto 50 m and all lifts.
( Khandki stones 25- 30 cm height : 730 Nos/sqm, Stone Chips : 0.0675cum/sqm,
Pin Headers 45cm : 2/sqm)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

particulars

Khandki stones 25-30 cm height


Pin headers 45 cm

UNIT :
Unit
Nos
Nos

Quantity
730.00
200.00

100.00 sqm
Rate
in Rs.
16.00
39.00

Amount
in Rs.
11680.00
7800.00

225

Canal and Allied Works - Item Unit Rates 2014-15

3
4
5

Stone chips @ 15 % at quarry


Cement
Sand (Screened )
Total cost of Materials

B. MACHINERY:
Sl No
1

cum
kg
cum

Description

Unit

5 hp diesel pump
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour

Description

Unit

C. LABOUR:
Sl No

6.75
4050.00
13.99

Quantity
4.00
4.00

Quantity

Crew for Pump


Hour
4.00
work inspector
Day
1.00
Cartman with double bullock cart
Day
2.00
Mason Class II
Day
7.00
mazdoor
Day
16.00
Total cost of Labour
labour component/unit qty
86.80
Add contractor's profit and overhead charges
0.14 12.20
labour component/unit qty (including contractor's profit)
99.00
1
2
3
4
5

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
100.00 sqm
sqm
(A+B+C+D)/100.0
Rate per
If 15 cm thick murum bed is to be
NOTE:
provided below pitching add
( As per rate analysis under item IRRCAW-8-1 - Note )

340.00
4.00
606.00
Rs:

2295.00
16200.00
8477.94
46452.94

Rate
in Rs.
10.20
85.30
Rs:

Amount
in Rs.
40.80
341.20
382.00

Rate
in Rs.
96.10
370.00
395.00
345.00
295.00
Rs:

Amount
in Rs.
384.40
370.00
790.00
2415.00
4720.00
8679.40

Rs:
Rs:
Rs:
Rs:

46452.94
382.00
8679.40
55514.34

Rs:
Rs:
Rs.

7772.01
63286.35
632.90
35.40

IRR-CAW-8-13 Providing 10 cm thick approved type grass turfing to the side slopes of canal including cost of
all materials, labour, watering for minimum 15 days etc.,complete with lead 50 m and all lifts.
(FA : 2 cum/sqm)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

particulars

Turfing sods
Sand for filling

UNIT :
Unit
sqm
cum

Quantity
100.00
2.00

Total cost of Materials


B. MACHINERY:
Sl No

Description

Unit

Nill

Quantity
0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No
1

Description
work inspector

Unit
Day

Quantity
0.10

100.00 sqm
Rate
in Rs.
28.00
342.00
Rs:

Amount
in Rs.
2800.00
684.00
3484.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
370.00

Amount
in Rs.
37.00

226

Canal and Allied Works - Item Unit Rates 2014-15

2
3

Cartman with double bullock cart


Day
2.00
mazdoor
Day
14.00
Total cost of Labour
labour component/unit qty
49.60
Add contractor's profit and overhead charges
0.14 6.90
labour component/unit qty (including contractor's profit)
56.50
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
100.00 sqm
(A+B+C+D)/100.0
sqm
Rate per

395.00
295.00
Rs:

790.00
4130.00
4957.00

Rs:
Rs:
Rs:
Rs:

3484.00
0.00
4957.00
8441.00

Rs:
Rs:
Rs.

1181.74
9622.74
96.20

IRR-CAW-8-14 Providing 10 cm Thick approved type gross turfing to the side slopes of canal including cost of
all materials ,labour,watering for minimum 15 days etc.,,complete.
with initial lead upto 50 m and all lifts ( WITHOUT USING SAND)

DATA:

RATE ANALYSIS

UNIT :

100.00 Sqm

A. MATERIALS :
Sl No
1

Particulars
Turfing Sods
Total Cost of materials

Unit
Sqm

Quantity
100.00

Rate
in Rs
28.00

Rs :

Amount
in Rs
2800.00
2800.00

B.MACHINERY :
Sl No

Description

Nill

Unit

Quantity
0.00
0.00

Rate
in Rs
0.00
0.00

Total hire charges of machinery


Rs :

Amount
in Rs
0.00
0.00
0.00

C.LABOUR :
Sl No

Description

Unit

Quantity

1
2

Mazdoor
Day
7.00
Cart men with double bullock cart
Day
2.00
Total cost of labour
Rs :
labour component/unit qty
28.60
Add contractor's profit and overhead charges
0.14 4.00
labour component/unit qty (including contractor's profit)
32.60
ABSTRACT
A.Cost of Materials including ryolty charges
B. Hire charges of Machinery
C.Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
100.00 Sqm
Sqm
(A+B+C+D)/100.0
Rate per

Rate
in Rs
295.00
395.00

Amount
in Rs
2065.00
790.00
2855.00

Rs:
Rs:
Rs:
Rs:

2800.00
0.00
2855.00
5655.00

Rs:
Rs:
Rs.

791.7
6446.70
64.50

227

Canal and Allied Works - Item Unit Rates 2014-15

228

Canal Cross Drainage Works - Item Unit Rates 2014-15

CHAPTER-IV
CANAL CROSS DRAINAGE WORKS - Standard Data

(WLL BE WITH E-N-C & TO INCORPORATE CHANGES YEARLY/ AS NEEDED)


FOR THE YEAR :2014-15
Index- code
IRR-CCDW

CANAL CROSS DRAINAGE WORKS - DATA RATES

Directions to add Seigniorage Charges and Additional Lead Charges


Seigniorage Charges:
1. The unit rate for work item in the Standard Data is exclusive of Seigniorage Charges wherever applicable.
2. The appropriate Seigniorage Charges for relevant materials are to be added to the Unit rate of work item while preparing
the estimate. (i.e., to the data itself)
3. The Provision towards Contractor's Profit and Overhead charges should not be operated on the Seigniorage Charges
while adding Seigniorage Charges to the data in the estimate
Additional Lead and Lift Charges:
1. Unless otherwise specified the basic rates are inclusive of all lifts.
2. For concrete, masonry and reinforcement items wherever initial lead of 1km is considered in the basic rate, the additional lead
as follows:
Additional lead charges for Cement, Steel, sand, coarse aggregate, stones and stone chips shall be worked out for total
lead involved and 1 km lead charges included in basic rate shall be deducted from total lead charges. No loading and
unloading charges shall be allowed for any item.
In case of Cement and Steel, Loading and unloading charges are already added in the work item while arriving the unit rate
and hence should not be added again
Example:
Total lead for sand from approved sand quarry :
15 Km
Initial lead included in the basic rate in the SR :
1 Km
Lead charges fo Rs.
84.10
Additional lead charges :
Lead charges for next 10 kmRs.
126
Total lead charges for 15 kmRs.
210.10
Less 1 km initial lead charg Rs.
31.50 (-)
Net additional lead charges Rs.
178.60

3. The Leads for Steel and Cement shall be from the nearest market place to the Project area
4. For earth/rockfill embankments wherever initial lead of 1km is considered in the basic rate, the additional lead charges are to be
added as follows:
Additional lead charges for Earth, Murrum etc., shall be worked out for total lead involved and 1 km lead charges included
in basic rate shall be deducted from total lead charges. No loading and unloading charges shall be allowed for any item.
(same as above)
Example:
Total lead for earth from approved borrow area :
15 Km
Initial lead included in the basic rate in the SR :
1 Km
Lead charges fo Rs.
84.10
Additional lead charges :
Lead charges for next 10 kmRs.
126
Total lead charges for 15 kmRs.
210.10
Less 1 km initial lead charg Rs.
31.50 (-)
Net additional lead charges Rs.
178.60
5. The initial lead up to 50 m as mentioned in some standard data items is meant for manual lead within the working area. For
conveyance of materials, the lead required from quarry/Borrow area/ Dump Area to worksite shall be added to the data without
deducting the 50 m initial lead charges
CCDW - Work Items
IRR-CCDW-1

EXCAVATION & FOUNDATION TREATMENT WORKS :

IRR-CCDW-1-1

Excavation in all kinds of soil including boulders upto 0.30 m dia. for foundations of canal
cross drainage and other appurtenant structures and placing the excavated stuff neatly in
specified dump area or disposing off the same as directed etc., complete with initial lead upto
50 m and initial lift upto 3 m.

230

Canal Cross Drainage Works - Item Unit Rates 2014-15

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1

UNIT :
Unit

Quantity

NIL

0.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No
Description
1

Unit

Quantity

NIL

0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No
Description

Unit

1
2

Day
Day

work inspector
mazdoor
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Quantity
0.25
6.00

10.00 cum
Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
370.00
295.00
Rs:

Amount
in Rs.
92.50
1770.00
1862.50

Rs:
Rs:
Rs:
Rs:

0.00
0.00
1862.50
1862.50
260.75
2123.25
212.30

186.30
0.14 26.10
212.40

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

IRR-CCDW-1-2

DATA:

10.00 cum
(A+B+C+D)/10.0

Total
14.00% Rs:
Rs:
Rs.

Excavation for Structures- Mechanical Means


( Data adopted from MORTH)
Earth work in excavation in all kinds of soils of foundation of structures as per drawing and
technical specification, including setting out, construction of shoring and bracing, removal of stumps
and other deleterious matter, dressing of sides and bottom and backfilling with approved material.
Depth upto 3 m
Unit = cum
cum
Taking output = 240 cum
Unit
240.00
A. Materials:
Sl No
Description
Unit
Quantity
Rate
in Rs.
NIL
0.00
0.00
B. Machinery:
Sl No
Description
1

Hydraulic excavator 1.0 cum bucket capacity

hour

6.00

Rate
in Rs.
1706.60

Fuel/ Energy charges


Total in Rs.

hour

6.00

937.80

5626.80
15866.40

Rate
in Rs.
370.00
295.00
204.10

Amount
in Rs.
118.40
2360.00
1224.60
3703.00

C. Labour:
Sl No
Description
work inspector
Mazdoor
crew for excavator
Total in Rs.
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
1
2
3

Abstract
a) Material

Unit

Unit

Quantity

Amount
in Rs.
0.00

Quantity

day
day
hour

0.32
8.00
6.00

Amount
in Rs.
10239.60

15.40
0.14 2.20
17.60

Rs

0.00

231

Canal Cross Drainage Works - Item Unit Rates 2014-15

b) Machinery
c) Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

Rs
Rs
Rs
14.00% Rs:
240.00 cum
Rs:
(A+B+C+D)/240.0
Rs.

15866.40
3703.00
19569.40
2739.72
22309.12
93.00

IRR-CCDW-1-3

Excavation in ordnary rock (including HDR) without blasting including boulders above 0.3 m upto 0.60 m dia.
for foundations of canal cross drainage and other appurtenant structures and placing the
excavated stuff neatly in specified dump area or disposing off the same as directed etc.,
complete with initial lead upto 50 m and initial lift upto 3 m.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1

UNIT :
Unit

Quantity

NIL

0.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No
Description
1

Unit

Quantity

NIL

0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No
Description

Unit

1
2
3
4

Day
Day
Day
Day

Crowbarman
Stone breaker
work inspector
mazdoor
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Quantity
1.25
1.25
0.25
6.00

10.00 cum
Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
345.00
345.00
370.00
295.00
Rs:

Amount
in Rs.
431.25
431.25
92.50
1770.00
2725.00

Rs:
Rs:
Rs:
Rs:

0.00
0.00
2725.00
2725.00
381.5
3106.5
310.70

272.50
0.14 38.20
310.70

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

IRR-CCDW-1-4

DATA:

10.00 cum
(A+B+C+D)/10.0

Total
14.00% Rs:
Rs:
Rs.

Excavation in ordnary rock without blasting for foundations of canal cross drainage
and other appurtenant structures and placing the excavated stuff neatly in specified dump
area or disposing off the same as directed etc., complete with initial
lead upto 50 m and initial lift upto 3 m.
( Data adopted from MORTH)
Mechanical Means
Unit = cum
Unit:
Taking output = 180 cum
180.00
A. Materials:
Sl No
Description
Unit
Quantity
Rate
in Rs.
NIL
0.00
0.00
B. Machinery:
Sl No
Description
1.0

Hydraulic excavator 1.0 cum bucket capacity

Unit
hour

Quantity
6.00

Rate
in Rs.
1706.60

cum
Amount
in Rs.
0.00

Amount
in Rs.
10239.60

232

Canal Cross Drainage Works - Item Unit Rates 2014-15

Fuel/ Energy charges


Total in Rs.
C. Labour:
Sl No
Description
1
2
3

work inspector
Mazdoor
crew for excavator
Total in Rs.

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
Abstract
a) Material
b) Machinery
c) Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

hour

Unit

6.00

Quantity

day
day
hour

0.24
6.00
6.00

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars

B. MACHINERY:
Sl No
Description
1
2

Air compressor 8.5 cmm ( diesel )


Fuel / Energy charges
Jack hammers 2 Nos.
Fuel / Energy charges
Total hire charges of Machinery

UNIT :
Unit

Quantity

Rm
10%
Hour
kg
Nos
Rm
LS

Unit

43.50
6.00
20.00
29.00
70.00
0.50

Quantity

Hour
Hour
Hour
Hour

C. LABOUR:
Sl No
Description

Unit

1
2
3
4
5
6
7
8

Hour
Hour
Day
Day
Day
Day
Day
Day

Crew for Air compressor


Crew for Jack hammer
work inspector
Blaster
Helper blaster
Crowbarman
Stone breaker
mazdoor
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Amount
in Rs.
88.80
1770.00
1224.60
3083.40

14.00% Rs:
180.00 cum
Rs:
(A+B+C+D)/180.0
Rs.

DATA:

2
3
4
5
6

Rate
in Rs.
370.00
295.00
204.10

Rs
Rs
Rs
Rs

Excavation in hard rock requiring blasting including boulders above 0.6 m upto 1.2 m dia. for
foundations of canal cross drainage and other appurtenant structures and placing the
excavated stuff neatly in specified dump area or disposing off the same as directed etc.,
complete with initial lead upto 50 m and initial lift upto 3 m.

Use rate of drill rod 1.6 m length


Reconditioning charges @
Use rate of air hose 2 Nos.
Explosive small dia ( Kelvex-220 )
Electric detonators
Detonating fuse coil
Sundries
Total cost of Materials

5626.80
15866.40

17.10
0.14 2.40
19.50

IRR-CCDW-1-5

937.80

3.00
3.00
6.00
6.00

Quantity
3.00
6.00
1.00
0.50
0.50
6.00
3.00
51.00

0.00
15866.40
3083.40
18949.80
2652.97
21602.77
120.00

100 cum
Rate
in Rs.
20.14
0.22
70.00
13.00
11.00
41.00
Rs:

Amount
in Rs.
876.09
87.61
1.31
1400.00
377.00
770.00
20.50
3532.51

Rate
in Rs.
275.60
959.10
19.80
0.00
Rs:

Amount
in Rs.
826.80
2877.30
118.80
0.00
3822.90

Rate
in Rs.
182.20
284.70
370.00
440.00
345.00
345.00
345.00
295.00
Rs:

Amount
in Rs.
546.60
1708.20
370.00
220.00
172.50
2070.00
1035.00
15045.00
21167.30

211.70
0.14 29.60
241.30

233

Canal Cross Drainage Works - Item Unit Rates 2014-15

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

Rs:
Rs:
Rs:
Rs:

Total
14.00% Rs:
100.00 cum
Rs:
(A+B+C+D)/100.0
Rs.

IRR-CCDW-1-6

Excavation in hard rock of all toughness by blasting including boulders above 1.2 m dia. for
foundations of canal cross drainage and other appurtenant structures and placing the
excavated rock neatly in specified dump area or stack yard as directed etc., complete with
initial lead upto 50 m and initial lift upto 3 m.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4
5
6

Explosive small dia ( Kelvex-220 )


Ordinary detonator
Electric detonator
Detonating fuse coil
Use rate of air hose 2 Nos.
Use rate of drill rod
Reconditioning charges @
Total cost of Materials

B. MACHINERY:
Sl No
Description
1
2

Air compressor 8.5 cmm ( diesel )


Fuel / Energy charges
Jack hammer 2 Nos
Fuel / Energy charges
Total hire charges of Machinery

UNIT :
Unit
kg
No.
No.
Rm
Hour
Rm
10%

Unit

32.00
8.00
104.00
150.00
16.00
98.30

Quantity

Hour
Hour
Hour
Hour

C. LABOUR:
Sl No
Description

Unit

1
2
3
4
5
6
7
8

Hour
Hour
Day
Day
Day
Day
Day
Day

Crew for Air compressor


Crew for Jack hammer
Blaster licensed
Helper blasting
work inspector
Crowbarman
Stone breaker
mazdoor
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Quantity

8.00
8.00
16.00
16.00

Quantity
8.00
16.00
1.00
1.00
1.00
6.00
6.00
51.00

100.00 cum
Rate
in Rs.
70.00
9.00
13.00
11.00
10.94
26.85
Rs:

Amount
in Rs.
2240.00
72.00
1352.00
1650.00
175.00
2639.68
263.97
8392.65

Rate
in Rs.
275.60
959.10
19.80
0.00
Rs:

Amount
in Rs.
2204.80
7672.80
316.80
0.00
10194.40

Rate
in Rs.
182.20
284.70
440.00
345.00
370.00
345.00
345.00
295.00
Rs:

Amount
in Rs.
1457.60
4555.20
440.00
345.00
370.00
2070.00
2070.00
15045.00
26352.80

Rs:
Rs:
Rs:
Rs:

8392.65
10194.40
26352.80
44939.85
6291.58
51231.43
512.30

263.50
0.14 36.90
300.40

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

IRR-CCDW-1-7

3532.51
3822.90
21167.30
28522.71
3993.18
32515.892
325.20

Total
14.00% Rs:
100.00 cum
Rs:
(A+B+C+D)/100.0
Rs.

Excavation in hard rock with blasting prohibited for foundations of canal cross drainage
and other appurtenant structures and placing the excavated rock neatly in
or stack yard as directed etc., complete with specified dump area initial lead upto 50 m and

234

Canal Cross Drainage Works - Item Unit Rates 2014-15

DATA:

initial lift upto 3 m.


Hard Rock ( blasting prohibited )
Unit = cum
Taking output = 10 cum
Mechanical Means
A.Materials:
Sl No
Description

( Data adopted from MORTH)

Unit

Quantity

NIL
b)
Machinery
Sl No
Description
1.0

Air Compressor 250 cft with 2 leads of


pneumatic breaker
Fuel/ Energy charges
Total in Rs.

c) Labour
Sl No
Description
work inspector
Mazdoor
crew for compressor
Total in Rs.
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
1
2
3

Abstract
a) Material
b) Machinery
c) Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

0.00

Unit

Amount
in Rs.
0.00

Amount
in Rs.
1447.80

hour

6.00

Rate
in Rs.
241.30

hour

6.00

767.30

4603.80
6051.60

Rate
in Rs.
370.00
295.00
182.20

Amount
in Rs.
74.00
1475.00
1093.20
2642.20

Unit

Quantity

Rate
in Rs.
0.00

Quantity

day
day
hour

0.20
5.00
6.00

264.20
0.14 37.00
301.20

Rs
Rs
Rs
Rs
10.00 cum
(A+B+C+D)/10.0

14.00% Rs:
Rs:
Rs.

IRR-CCDW-1-8

Providing and fixing 25 mm dia 2.50 m long cold twisted deformed steel anchor rods with
1.25 m length driven into 32 mm dia hole drilled in bed rock and remaining length embedded in
concrete / masonry including cost of all materials, machinery, labour, drilling and cleaning
hole, driving anchor rod, grouting hole with thick cement slurry etc., complete with initial lead
upto 50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4

Cement for grouting


25 mm dia steel
Use rate of 32 mm dia drill rod
Reconditioning charges @
Use rate of air hose
Total cost of Materials

B. MACHINERY:
Sl No
Description
1
2

Air compressor 8.5 cmm ( diesel )


Fuel / Energy charges
Jack hammer 2 Nos
Fuel / Energy charges
Total hire charges of Machinery

cum

10.00

UNIT :
Unit
kg
kg
Rm
10%
Hour

Unit
Hour
Hour
Hour
Hour

Quantity
5.00
101.00
12.50
2.00

Quantity
1.00
1.00
2.00
2.00

0.00
6051.60
2642.20
8693.80
1217.13
9910.93
991.10

10.00 Nos.
Rate
in Rs.
4.00
46.50
26.85
10.94
Rs:

Amount
in Rs.
20.00
4696.50
335.67
33.57
21.88
5107.61

Rate
in Rs.
275.60
959.10
19.80
0.00
Rs:

Amount
in Rs.
275.60
959.10
39.60
0.00
1274.30

C. LABOUR:

235

Canal Cross Drainage Works - Item Unit Rates 2014-15

Sl No

Description

1
2
3
4
5
6

Crew for Air compressor


Crew for Jack hammer
Mason Class-II
Bar bender
work inspector
mazdoor
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Unit

Quantity

Hour
Hour
Day
Day
Day
Day

1.00
2.00
0.50
0.50
0.50
1.00

Rate
in Rs.
182.20
284.70
345.00
450.00
370.00
295.00
Rs:

Amount
in Rs.
182.20
569.40
172.50
225.00
185.00
295.00
1629.10

Rs:
Rs:
Rs:
Rs:

5107.61
1274.30
1629.10
8011.01
1121.54
9132.55
913.30

162.90
0.14 22.80
185.70

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per each

10.00 Nos.
(A+B+C+D)/10.0

Total
14.00% Rs:
Rs:
Rs.

IRR-CCDW-2

STEEL AND CEMENT CONCRETE WORKS :

IRR-CCDW-2-1

Providing, fabricating and placing in position reinforcement steel bars for RCC works including
cleaning, straightening, cutting, bending, hooking, lapping, welding wherever required,tying with
1.25 mm dia soft annealed steel wire, including cost of all materials, machinery, labour etc.,
complete with initial lead upto 50 and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars

Unit

1
2
3

kg
kg
LS

Rein.Steel with 5 % wastage


Binding wire 1.25 mm dia
Sundries ( chairs / spacers etc )
Total cost of Materials

B. MACHINERY:
Sl No
Description
1

UNIT :

Unit

Quantity
1050.00
8.00
3.00

Quantity

Nil

0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No
Description

Unit

1
2
3

Day
Day
Day

work inspector
Bar bender
mazdoor
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Quantity
1.00
6.00
11.00

1000.00 kg
Rate
in Rs.
46.50
70.00
41.00
Rs:

Amount
in Rs.
48825.00
560.00
123.00
49508.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
370.00
450.00
295.00
Rs:

Amount
in Rs.
370.00
2700.00
3245.00
6315.00

Rs:
Rs:
Rs:
Rs:

49508.00
0.00
6315.00
55823.00
7815.22
63638.22
63.60

6.30
0.14 0.90
7.20

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per kg

IRR-CCDW-2-2

Total
14.00% Rs:
1000.00 kg
Rs:
(A+B+C+D)/1000.0
Rs.

Providing, fabricating and fixing in position structural steel cutting edge consisting of 100 x

236

Canal Cross Drainage Works - Item Unit Rates 2014-15

100 x 10 mm angle and 250 x 12 mm plate for sinking for sinking 4.50 m outer diameter
foundation wells foundation wells including cost of all materials, machinery, labour, bending,
welding, providing anchors etc., complete with initial lead upto 50 m and all lifts.

DETAILS OF FOUNDATION WELL CUTTING EDGE

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
7

Particulars

Unit

Str.Steel angle with 2.5 % wastage


Str.Steel plate with 2.5 % wastage
Steel for anchors
Acetyline gas
Oxygen gas
Welding electrodes
Sundries
Total cost of Materials

kg
kg
kg
cum
cum
Nos
LS

B. MACHINERY:
Sl No
1
2
3

Description

Unit

Bending machine
Fuel / Energy charges
Welding set
Fuel / Energy charges
Sundries
Total hire charges of Machinery

Hour
Hour
Hour
Hour
LS

C. LABOUR:
Sl No
1
2
3
4

UNIT :

Description

Str. Steel fabricator


Welder / Gas cutter
work inspector
mazdoor

Unit

Quantity
216.10
342.30
56.60
0.50
1.50
300.00
5.00

Quantity
8.00
8.00
30.00
30.00
10.00

Quantity

Day
Day
Day
Day
Total cost of Labour

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

2.00
5.00
1.00
5.00

615.00 kg
Rate
in Rs.
45.00
46.00
46.50
320.00
52.00
11.00
41.00
Rs:

Amount
in Rs.
9724.50
15745.80
2631.90
160.00
78.00
3300.00
205.00
31845.20

Rate
in Rs.
42.60
114.10
16.00
91.30
41.00
Rs:

Amount
in Rs.
340.80
912.80
480.00
2739.00
410.00
4882.60

Rate
in Rs.
440.00
385.00
370.00
295.00
Rs:

Amount
in Rs.
880.00
1925.00
370.00
1475.00
4650.00

Rs:
Rs:
Rs:
Rs:

31845.20
4882.60
4650.00
41377.80
5792.89
47170.69
76.70

7.60
0.14 1.10
8.70

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per kg

Total
14.00% Rs:
615.00 kg
Rs:
(A+B+C+D)/615.0
Rs.

IRR-CCDW-2-3 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than
15 N /sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for foundation filling including cost of all materials, machinery, labour, formwork,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
complete with initial lead upto 50 m and all lifts.
(Cement content: 260 kg / cum with use of super plasticiser(0.4% by wt. of cement),

237

Canal Cross Drainage Works - Item Unit Rates 2014-15

CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

Data

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

3
4
5
6

Particulars

Unit

Cement for mix


Cement for incidentals @ 3 kg / cum
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened)
Super Plasticizer
Use rate of shuttering for 40 uses
Scaffolding @ of shuttering
Sundries
Total cost of Materials

kg
kg
cum
cum
cum
cum
kg
sqm
10%
LS

B. MACHINERY:
Sl No
1
2
3
4

UNIT :

Description

Unit

Concrete mixer 300/200 ltr ( diesel )


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Needle vibrator 40 mm dia ( petrol )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour

C. LABOUR:
Sl No

Description

1
2
3
4
5
6
7

Crew for Concrete mixer


Crew for Pump
Crew for Water tanker
Crew for Needle vibrator
work inspector
Mason Class-I
mazdoor
for batching materials
for loading mortar pans
for laying
for conveying concrete
for cleaning/ washing/ curing
8
Labour cost for shuttering
Labour cost for scaffolding @
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Quantity
3998.80
46.14
6.92
4.15
2.77
6.15
16.00
15.38

15.38 cum
Rate
in Rs.
4.00
4.00
1145.00
1210.00
875.00
462.00
80.00
244.56
41.00
Rs:

Amount
in Rs.
15995.20
184.56
7924.55
5024.65
2422.35
2842.22
1279.62
3761.39
376.14
20.50
39831.17

Rate
in Rs.
53.50
85.30
10.20
85.30
402.50
322.20
7.60
21.50
Rs:

Amount
in Rs.
428.00
682.40
5.10
42.65
402.50
322.20
60.80
172.00
2115.65

Amount
in Rs.
1518.40
48.05
153.10
1092.80
370.00
385.00
3245.00
1180.00
885.00
4537.10
295.00
1158.11
115.81
14983.38

0.50

Quantity
8.00
8.00
0.50
0.50
1.00
1.00
8.00
8.00

Hour
Hour
Hour
Hour
Day
Day

8.00
0.50
1.00
8.00
1.00
1.00

Rate
in Rs.
189.80
96.10
153.10
136.60
370.00
385.00

Day
Day
Day
Day
Day
sqm
10%

11.00
4.00
3.00
15.38
1.00
15.38

295.00
295.00
295.00
295.00
295.00
75.30

Unit

Quantity

Rs:
974.20
0.14 136.40
1110.60

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

Total
14.00% Rs:
15.38 cum
Rs:
(A+B+C+D)/15.38
Rs.

Rs:
Rs:
Rs:
Rs:

39831.17
2115.65
14983.38
56930.20
7970.23
64900.43
4219.80

IRR-CCDW-2-4 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than
15 N / sq mm ) grade cement concrete using 80 mm down size approved, clean, hard, graded
aggregates for foundation filling including cost of all materials, machinery, labour, formwork,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,

238

Canal Cross Drainage Works - Item Unit Rates 2014-15

complete with initial lead upto 50 m and all lifts.


(Cement content: 250 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.98cum, Blending Ratio of CA--35:30:20:15, FA : 0.35 cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

3
4
5
6

Particulars

Unit

Cement for mix


Cement for incidentals @ 3 kg / cum
Coarse aggregate 80-40 mm
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened)
Super Plasticizer
Use rate of shuttering for 40 uses
Scaffolding @ of shuttering
Sundries
Total cost of Materials

kg
kg
cum
cum
cum
cum
cum
kg
sqm
10%
LS

B. MACHINERY:
Sl No
1
2
3
4

UNIT :

Description

Unit

Concrete mixer 600/400 ltr ( diesel)


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Needle vibrator 60 mm dia ( petrol)
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour

C. LABOUR:
Sl No

Description

1
2
3
4
5
6
7

Crew for Concrete mixer


Crew for Pump
Crew for Water tanker
Crew for Needle vibrator
Mason Class-I
work inspector
mazdoor
for batching materials
for loading mortar pans
for laying
for conveying concrete
for cleaning/ washing/ curing
8
Labour cost for shuttering
Labour cost for scaffolding @
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Unit

Quantity
3600.00
43.20
4.94
4.23
2.82
2.12
5.04
14.40
14.40

14.40 cum
Rate
in Rs.
4.00
4.00
635.00
1145.00
1210.00
875.00
462.00
80.00
244.56
41.00
Rs:

Amount
in Rs.
14400.00
172.80
3136.39
4847.47
3415.10
1852.20
2328.48
1152.00
3521.72
352.17
20.50
35198.84

Rate
in Rs.
92.70
170.50
10.20
85.30
402.50
322.20
8.20
32.20
Rs:

Amount
in Rs.
741.60
1364.00
5.10
42.65
402.50
322.20
65.60
257.60
3201.25

Amount
in Rs.
1518.40
48.05
153.10
1092.80
385.00
370.00
3245.00
1180.00
885.00
4248.00
295.00
1084.32
108.43
14613.10

0.50

Quantity
8.00
8.00
0.50
0.50
1.00
1.00
8.00
8.00

Quantity

Hour
Hour
Hour
Hour
Day
Day

8.00
0.50
1.00
8.00
1.00
1.00

Rate
in Rs.
189.80
96.10
153.10
136.60
385.00
370.00

Day
Day
Day
Day
Day
sqm
10%

11.00
4.00
3.00
14.40
1.00
14.40

295.00
295.00
295.00
295.00
295.00
75.30
Rs:

1014.80
0.14 142.10
1156.90

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

Total
14.00% Rs:
14.40 cum
Rs:
(A+B+C+D)/14.40
Rs.

Rs:
Rs:
Rs:
Rs:

35198.84
3201.25
14613.10
53013.19
7421.85
60435.04
4196.90

IRR-CCDW-2-5 Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than

239

Canal Cross Drainage Works - Item Unit Rates 2014-15

10 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for foundation filling including cost of all materials, machinery, labour, formwork,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
complete with initial lead upto 50 m and all lifts.
(Cement content: 220 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

3
4
5
6

Particulars

Unit

Cement for mix


Cement for incidentals @ 3 kg / cum
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened)
Super Plasticizer
Use rate of shuttering for 40 uses
Scaffolding @ of shuttering
Sundries
Total cost of Materials

kg
kg
cum
cum
cum
cum
kg
sqm
10%
LS

B. MACHINERY:
Sl No
1
2
3
4

Description

Unit

Concrete mixer 300/200 ltr ( diesel )


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Needle vibrator 40 mm dia ( petrol )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour

C. LABOUR:
Sl No
1
2
3
4
5
6
7

8
9

UNIT :

Description

Crew for Concrete mixer


Crew for Pump
Crew for Water tanker
Crew for Vibrator
Mason Class-I
work inspector
mazdoor
for batching materials
for loading mortar pans
for laying
for conveying concrete
for cleaning/ washing/ curing
Labour cost for shuttering

Unit

Quantity
3599.20
49.08
7.36
4.42
2.94
6.54
14.40
16.36

16.36 cum
Rate
in Rs.
4.00
4.00
1145.00
1210.00
875.00
462.00
80.00
244.56
41.00
Rs:

Amount
in Rs.
14396.80
196.32
8429.49
5344.81
2576.70
3023.33
1151.74
4001.07
400.11
20.50
39540.87

Rate
in Rs.
53.50
85.30
10.20
85.30
402.50
322.20
7.60
21.50
Rs:

Amount
in Rs.
428.00
682.40
5.10
42.65
402.50
322.20
60.80
172.00
2115.65

Rate
in Rs.
189.80
96.10
153.10
136.60
385.00
370.00

Amount
in Rs.
1518.40
48.05
153.10
1092.80
385.00
370.00

295.00
295.00
295.00
295.00
295.00
75.30
Rs:

3245.00
1180.00
885.00
4826.20
295.00
1231.91
15230.46

Rs:
Rs:
Rs:
Rs:

39540.87
2115.65
15230.46
56886.97
7964.18
64851.15
3964.00

0.50

Quantity
8.00
8.00
0.50
0.50
1.00
1.00
8.00
8.00

Quantity

Hour
Hour
Hour
Hour
Day
Day

8.00
0.50
1.00
8.00
1.00
1.00

Day
Day
Day
Day
Day
sqm

11.00
4.00
3.00
16.36
1.00
16.36

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

931.00
0.14 130.30
1061.30

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

Total
14.00% Rs:
16.36 cum
Rs:
(A+B+C+D)/16.36
Rs.

240

Canal Cross Drainage Works - Item Unit Rates 2014-15

IRR-CCDW-2-6 Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than
10 N / sq mm ) grade cement concrete using 80 mm down size approved, clean, hard, graded
aggregates for foundation filling including cost of all materials, machinery, labour, formwork,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
complete with initial lead upto 50 m and all lifts.
(Cement content: 220 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.98cum, Blending Ratio of CA--35:30:20:15, FA : 0.35 cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

3
4
5
6

Particulars

Unit

Cement for mix


Cement for incidentals @ 3 kg / cum
Coarse aggregate 80-40 mm
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened)
Super Plasticizer
Use rate of shuttering for 40 uses
Scaffolding @ of shuttering
Sundries
Total cost of Materials

kg
kg
cum
cum
cum
cum
cum
kg
sqm
10%
LS

B. MACHINERY:
Sl No
1
2
3
4

UNIT :

Description

Unit

Concrete mixer 600/400 ltr ( diesel )


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Needle vibrator 60 mm dia ( petrol )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour

C. LABOUR:
Sl No

Description

1
2
3
4
5
6
7

Crew for Concrete mixer


Crew for Pump
Crew for Water tanker
Crew for Vibrator
Mason Class-I
work inspector
mazdoor
for batching materials
for loading mortar pans
for laying
for conveying concrete
for cleaning/ washing/ curing
8
Labour cost for shuttering
Labour cost for scaffolding @
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Unit

Quantity
3201.00
43.65
4.99
4.28
2.85
2.14
5.09
12.80
14.55

14.55 cum
Rate
in Rs.
4.00
4.00
635.00
1145.00
1210.00
875.00
462.00
80.00
244.56
41.00
Rs:

Amount
in Rs.
12804.00
174.60
3169.06
4897.97
3450.68
1871.49
2352.74
1024.32
3558.41
355.84
20.50
33679.60

Rate
in Rs.
92.70
170.50
10.20
85.30
402.50
322.20
8.20
32.20
Rs:

Amount
in Rs.
741.60
1364.00
5.10
42.65
402.50
322.20
65.60
257.60
3201.25

Amount
in Rs.
1518.40
48.05
153.10
1092.80
385.00
370.00
3245.00
1180.00
885.00
4292.25
295.00
1095.62
109.56
14669.78

0.50

Quantity
8.00
8.00
0.50
0.50
1.00
1.00
8.00
8.00

Quantity

Hour
Hour
Hour
Hour
Day
Day

8.00
0.50
1.00
8.00
1.00
1.00

Rate
in Rs.
189.80
96.10
153.10
136.60
385.00
370.00

Day
Day
Day
Day
Day
sqm
10%

11.00
4.00
3.00
14.55
1.00
14.55

295.00
295.00
295.00
295.00
295.00
75.30
Rs:

1008.20
0.14 141.10
1149.30

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for

14.55 cum

Total
14.00% Rs:
Rs:

Rs:
Rs:
Rs:
Rs:

33679.60
3201.25
14669.78
51550.63
7217.09
58767.72

241

Canal Cross Drainage Works - Item Unit Rates 2014-15

Rate per cum

(A+B+C+D)/14.55

Rs.

4039.00

IRR-CCDW-2-7 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than
20 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for foundation filling including cost of all materials, machinery, labour, formwork,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
complete with initial lead upto 50 m and all lifts. ( Cement content : 220 kg / cum )
(Cement content: 310 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

3
4
5
6

Particulars

Unit

Cement for mix


Cement for incidentals @ 3 kg / cum
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened)
Super Plasticizer
Use rate of shuttering for 40 uses
Scaffolding @ of shuttering
Sundries
Total cost of Materials

kg
kg
cum
cum
cum
cum
kg
sqm
10%
LS

B. MACHINERY:
Sl No
1
2
3
4

UNIT :

Description

Unit

Concrete mixer 300/200 ltr ( diesel )


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Needle vibrator 40 mm dia ( petrol )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour

C. LABOUR:
Sl No
1
2
3
4
5
6
7

Description

Crew for Concrete mixer


Crew for Pump
Crew for Water tanker
Crew for Vibrator
Mason Class-I
work inspector
mazdoor
for batching materials
for loading mortar pans
for laying
for conveying concrete
for cleaning/ washing/ curing
8
Labour cost for shuttering
Labour cost for scaffolding @
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Quantity
4398.90
42.57
6.39
3.83
2.55
5.68
17.60
14.19

14.19 cum
Rate
in Rs.
4.00
4.00
1145.00
1210.00
875.00
462.00
80.00
244.56
41.00
Rs:

Amount
in Rs.
17595.60
170.28
7311.40
4635.87
2234.93
2622.31
1407.65
3470.36
347.04
20.50
39815.93

Rate
in Rs.
53.50
85.30
10.20
85.30
402.50
322.20
7.60
21.50
Rs:

Amount
in Rs.
428.00
682.40
5.10
42.65
402.50
322.20
60.80
172.00
2115.65

Amount
in Rs.
1518.40
48.05
153.10
1092.80
385.00
370.00

Rs:

3245.00
1180.00
885.00
4186.05
295.00
1068.51
106.85
14533.76

Rs:
Rs:
Rs:
Rs:

39815.93
2115.65
14533.76
56465.34

0.50

Quantity
8.00
8.00
0.50
0.50
1.00
1.00
8.00
8.00

Hour
Hour
Hour
Hour
Day
Day

8.00
0.50
1.00
8.00
1.00
1.00

Rate
in Rs.
189.80
96.10
153.10
136.60
385.00
370.00

Day
Day
Day
Day
Day
sqm
10%

11.00
4.00
3.00
14.19
1.00
14.19

295.00
295.00
295.00
295.00
295.00
75.30

Unit

Quantity

1024.20
0.14 143.40
1167.60

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total

242

Canal Cross Drainage Works - Item Unit Rates 2014-15

D. Add for contractor's profit and overheads on (A+B+C)


Total cost for
Rate per cum

14.00% Rs:
14.19 cum
Rs:
(A+B+C+D)/14.19
Rs.

7905.15
64370.49
4536.30

IRR-CCDW-2-8 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than
20 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for sub-structure / super- structure works including cost of all materials,
machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position,
levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts.
(Cement content: 320 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

3
4
5
6

Particulars

Unit

Cement for mix


Cement for incidentals @ 5 kg / cum
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened)
Super Plasticizer
Use rate of shuttering
Scaffolding @ of shuttering
Sundries
Total cost of Materials

kg
kg
cum
cum
cum
cum
kg
sqm
25%
LS

B. MACHINERY:
Sl No
1
2
3
4

UNIT :

Description

Unit

Concrete mixer 300/200 ltr ( diesel )


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Needle vibrator 40 mm dia ( petrol )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour

C. LABOUR:
Sl No
1
2
3
4
5
6
7

Description

Crew for Concrete mixer


Crew for Pump
Crew for Water tanker
Crew for Vibrator
Mason Class-I
work inspector
mazdoor
for batching materials
for loading mortar pans
for laying including lifting
for conveying concrete
for cleaning/ washing/ curing
8
Labour cost for shuttering
Labour cost for scaffolding @
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery

Quantity
4800.00
75.00
6.75
4.05
2.70
6.00
19.20
30.00
0.50

Quantity
8.00
8.00
0.50
0.50
1.00
1.00
8.00
8.00

15.00 cum
Rate
in Rs.
4.00
4.00
1145.00
1210.00
875.00
462.00
80.00
244.56
41.00
Rs:

Amount
in Rs.
19200.00
300.00
7728.75
4900.50
2362.50
2772.00
1536.00
7336.92
1834.23
20.50
47991.40

Rate
in Rs.
53.50
85.30
10.20
85.30
402.50
322.20
7.60
21.50
Rs:

Amount
in Rs.
428.00
682.40
5.10
42.65
402.50
322.20
60.80
172.00
2115.65

Amount
in Rs.
1518.40
48.05
153.10
1092.80
385.00
370.00

Rs:

3245.00
1180.00
1180.00
4425.00
295.00
1129.50
282.38
15304.23

Rs:
Rs:

47991.40
2115.65

Hour
Hour
Hour
Hour
Day
Day

8.00
0.50
1.00
8.00
1.00
1.00

Rate
in Rs.
189.80
96.10
153.10
136.60
385.00
370.00

Day
Day
Day
Day
Day
sqm
25%

11.00
4.00
4.00
15.00
1.00
15.00

295.00
295.00
295.00
295.00
295.00
75.30

Unit

Quantity

1020.30
0.14 142.80
1163.10

243

Canal Cross Drainage Works - Item Unit Rates 2014-15

C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

15.00 cum
(A+B+C+D)/15.0

Rs:
Rs:

Total
14.00% Rs:
Rs:
Rs.

15304.23
65411.27
9157.58
74568.85
4971.30

IRR-CCDW-2-9 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than
20 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
aggregates for sub-structure / super- structure works including cost of all materials,
machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position,
levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts.
(Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6

Particulars

Unit

Cement for mix


Cement for incidentals @ 5 kg / cum
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened)
Super Plasticizer
Use rate of shuttering
Scaffolding @ of shuttering
Sundries
Total cost of Materials

kg
kg
cum
cum
cum
kg
sqm
25%
LS

B. MACHINERY:
Sl No
1
2
3
4

UNIT :

Description

Unit

Concrete mixer 300/200 ltr ( diesel )


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Needle vibrator 40 mm dia ( petrol )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour

C. LABOUR:
Sl No

Description

Crew for Concrete mixer


Crew for Pump
Crew for Water tanker
Crew for Vibrator
Mason Class-I
work inspector
mazdoor
for batching materials
for loading mortar pans
for laying
for conveying concrete
for cleaning/ washing/ curing
8
Labour cost for shuttering
Labour cost for scaffolding @
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
1
2
3
4
5
6
7

ABSTRACT:
A. Cost of Materials

Unit

Quantity
5200.80
78.80
8.20
4.41
7.09
20.80
31.52
0.50

Quantity
8.00
8.00
0.50
0.50
1.00
1.00
8.00
8.00

Quantity

15.76 cum
Rate
in Rs.
4.00
4.00
1210.00
875.00
462.00
80.00
244.56
41.00
Rs:

Amount
in Rs.
20803.20
315.20
9916.19
3861.20
3276.50
1664.26
7708.66
1927.16
20.50
49492.87

Rate
in Rs.
53.50
85.30
10.20
85.30
402.50
322.20
7.60
21.50
Rs:

Amount
in Rs.
428.00
682.40
5.10
42.65
402.50
322.20
60.80
172.00
2115.65

Amount
in Rs.
1518.40
48.05
153.10
1092.80
385.00
370.00

Rs:

3245.00
1180.00
1180.00
4649.20
295.00
2373.46
593.36
17083.37

Rs:

49492.87

Hour
Hour
Hour
Hour
Day
Day

8.00
0.50
1.00
8.00
1.00
1.00

Rate
in Rs.
189.80
96.10
153.10
136.60
385.00
370.00

Day
Day
Day
Day
Day
sqm
25%

11.00
4.00
4.00
15.76
1.00
31.52

295.00
295.00
295.00
295.00
295.00
75.30

1084.00
0.14 151.80
1235.80

244

Canal Cross Drainage Works - Item Unit Rates 2014-15

B. Hire charges of Machinery


C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

Rs:
Rs:
Rs:

Total
14.00% Rs:
15.76 cum
Rs:
(A+B+C+D)/15.76
Rs.

2115.65
17083.37
68691.89
9616.86
78308.751
4968.80

IRR-CCDW-2-10 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than
15 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
aggregates for sub-structure / super- structure works including cost of all materials,
machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position,
levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts.
(Cement content: 280 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6

Particulars

Unit

Cement for mix


Cement for incidentals @ 5 kg / cum
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened)
Super Plasticizer
Use rate of shuttering for 40 uses
Scaffolding @ of shuttering
Sundries
Total cost of Materials

kg
kg
cum
cum
cum
kg
sqm
25%
LS

B. MACHINERY:
Sl No
1
2
3
4

UNIT :

Description

Unit

Concrete mixer 300/200 ltr ( diesel )


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Needle vibrator 40 mm dia ( petrol )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour

C. LABOUR:
Sl No

Description

Crew for Concrete mixer


Crew for Pump
Crew for Water tanker
Crew for Vibrator
Mason Class-I
work inspector
mazdoor
for batching materials
for loading mortar pans
for laying
for conveying concrete
for cleaning/ washing/ curing
8
Labour cost for shuttering
Labour cost for scaffolding @
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
1
2
3
4
5
6
7

Unit

Quantity
4398.80
78.55
8.17
4.40
7.07
17.60
31.42
0.50

Quantity
8.00
8.00
0.50
0.50
1.00
1.00
8.00
8.00

Quantity

15.71 cum
Rate
in Rs.
4.00
4.00
1210.00
875.00
462.00
80.00
244.56
41.00
Rs:

Amount
in Rs.
17595.20
314.20
9884.73
3848.95
3266.11
1407.62
7684.20
1921.05
20.50
45942.56

Rate
in Rs.
53.50
85.30
10.20
85.30
402.50
322.20
7.60
21.50
Rs:

Amount
in Rs.
428.00
682.40
5.10
42.65
402.50
322.20
60.80
172.00
2115.65

Amount
in Rs.
1518.40
48.05
153.10
1092.80
385.00
370.00
3245.00
1180.00
1180.00
4634.45
295.00
2365.93
591.48
17059.21

Hour
Hour
Hour
Hour
Day
Day

8.00
0.50
1.00
8.00
1.00
1.00

Rate
in Rs.
189.80
96.10
153.10
136.60
385.00
370.00

Day
Day
Day
Day
Day
sqm
25%

11.00
4.00
4.00
15.71
1.00
31.42

295.00
295.00
295.00
295.00
295.00
75.30
Rs:

1085.90
0.14 152.00
1237.90

ABSTRACT:

245

Canal Cross Drainage Works - Item Unit Rates 2014-15

A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

Rs:
Rs:
Rs:
Rs:

Total
14.00% Rs:
15.71 cum
Rs:
(A+B+C+D)/15.71
Rs.

45942.56
2115.65
17059.21
65117.41
9116.44
74233.853
4725.30

IRR-CCDW-2-11 Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than
10 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
aggregates for sub-structure / super- structure works including cost of all materials,
machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position,
levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts.
(Cement content: 220 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6

Particulars

Unit

Cement for mix


Cement for incidentals @ 5 kg / cum
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened)
Super Plasticizer
Use rate of shuttering for 40 uses
Scaffolding @ of shuttering
Sundries
Total cost of Materials

kg
kg
cum
cum
cum
kg
sqm
25%
LS

B. MACHINERY:
Sl No
1
2
3
4

Description

Unit

Concrete mixer 300/200 ltr ( diesel )


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Needle vibrator 40 mm dia ( petrol )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour

C. LABOUR:
Sl No

Description

Crew for Concrete mixer


Crew for Pump
Crew for Water tanker
Crew for Vibrator
Mason Class-I
work inspector
mazdoor
for batching materials
for loading mortar pans
for laying
for conveying concrete
for cleaning/ washing/ curing
8
Labour cost for shuttering
Labour cost for scaffolding @
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
1
2
3
4
5
6
7

UNIT :

Unit

Quantity
3960.00
90.00
9.36
5.04
8.10
15.84
36.00
0.50

Quantity
8.00
8.00
0.50
0.50
1.00
1.00
8.00
8.00

Quantity

18.00 cum
Rate
in Rs.
4.00
4.00
1210.00
875.00
462.00
80.00
244.56
41.00
Rs:

Amount
in Rs.
15840.00
360.00
11325.60
4410.00
3742.20
1267.20
8804.30
2201.08
20.50
47970.88

Rate
in Rs.
53.50
85.30
10.20
85.30
402.50
322.20
7.60
21.50
Rs:

Amount
in Rs.
428.00
682.40
5.10
42.65
402.50
322.20
60.80
172.00
2115.65

Amount
in Rs.
1518.40
48.05
153.10
1092.80
385.00
370.00
3245.00
1180.00
1180.00
5310.00
295.00
2710.80
677.70
18165.85

Hour
Hour
Hour
Hour
Day
Day

8.00
0.50
1.00
8.00
1.00
1.00

Rate
in Rs.
189.80
96.10
153.10
136.60
385.00
370.00

Day
Day
Day
Day
Day
sqm
25%

11.00
4.00
4.00
18.00
1.00
36.00

295.00
295.00
295.00
295.00
295.00
75.30
Rs:

1009.20
0.14 141.30
1150.50

246

Canal Cross Drainage Works - Item Unit Rates 2014-15

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

18.00 cum
(A+B+C+D)/18.0

Rs:
Rs:
Rs:
Rs:

Total
14.00% Rs:
Rs:
Rs.

47970.88
2115.65
18165.85
68252.38
9555.33
77807.707
4322.70

IRR-CCDW-2-12 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than
20 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
aggregates for well kerb including cost of all materials, machinery, labour, formwork,
scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc., complete with initial lead upto 50 m and all lifts.
Note:
If water is to be brought from other place add only lead charges @ 500 ltr / cum.
(Cement content: 350 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6

Particulars

Unit

Cement for mix


Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened)
Super Plasticizer
Use rate of curved shutter (40 uses)
Sundries
Total cost of Materials

kg
cum
cum
cum
kg
sqm
LS

B. MACHINERY:
Sl No
1
2
3

Description

Unit

Concrete mixer 300/200 ltr ( diesel )


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Needle vibrator 40 mm dia ( petrol )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour

C. LABOUR:
Sl No
1
2
3
4
5
6

UNIT :

Description

Crew for Concrete mixer


Crew for Pump
Crew for Vibrator
Mason Class-I
work inspector
mazdoor
for batching materials
for loading mortar pans
for laying
for conveying concrete
for cleaning/ washing/ curing
Labour cost for shuttering

Unit

Quantity
5250.00
7.80
4.20
6.75
21.00
82.50
0.50

Quantity
8.00
8.00
0.50
0.50
8.00
8.00

Quantity

Hour
Hour
Hour
Day
Day

8.00
0.50
8.00
1.00
1.00

Day
Day
Day
Day
Day
sqm

11.00
4.00
3.00
15.00
1.00
82.50

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

15.00 cum
Rate
in Rs.
4.00
1210.00
875.00
462.00
80.00
269.02
41.00
Rs:

Amount
in Rs.
21000.00
9438.00
3675.00
3118.50
1680.00
22194.18
20.50
61126.18

Rate
in Rs.
53.50
85.30
10.20
85.30
7.60
21.50
Rs:

Amount
in Rs.
428.00
682.40
5.10
42.65
60.80
172.00
1390.95

Rate
in Rs.
189.80
96.10
136.60
385.00
370.00

Amount
in Rs.
1518.40
48.05
1092.80
385.00
370.00

295.00
295.00
295.00
295.00
295.00
75.30
Rs:

3245.00
1180.00
885.00
4425.00
295.00
6212.25
19656.50

Rs:
Rs:
Rs:

61126.18
1390.95
19656.50

1310.40
0.14 183.50
1493.90

247

Canal Cross Drainage Works - Item Unit Rates 2014-15

D. Add for contractor's profit and overheads on (A+B+C)


Total cost for
Rate per cum

15.00 cum
(A+B+C+D)/15.0

Total
14.00% Rs:
Rs:
Rs.

Rs:

82173.63
11504.31
93677.937
6245.20

IRR-CCDW-2-13 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than
20 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for well steining including cost of all materials, machinery, labour, formwork,
scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc., complete with initial lead upto 50 m and all lifts.
Note:
If water is to be brought from other place add only lead charges @ 500 ltr / cum.
(Cement content: 320 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

3
4
5
6

Particulars

Unit

Cement for mix


Cement for incidentals @ 2 kg / cum
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened)
Super Plasticizer
Use rate of curved shutter (40 uses)
Sundries
Total cost of Materials

kg
kg
cum
cum
cum
cum
kg
sqm
LS

B. MACHINERY:
Sl No
1
2
3

Description

Unit

Concrete mixer 300/200 ltr ( diesel )


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Needle vibrator 40 mm dia ( petrol )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour

C. LABOUR:
Sl No
1
2
3
4
5
6

UNIT :

Description

Crew for Concrete mixer


Crew for Pump
Crew for Vibrator
Mason Class-I
work inspector
mazdoor
for batching materials
for loading mortar pans
for laying
for conveying concrete
for cleaning/ washing/ curing
Labour cost for shuttering

Unit

Quantity
4800.00
30.00
6.75
4.05
2.70
6.00
19.20
60.00
0.50

Quantity
8.00
8.00
0.50
0.50
8.00
8.00

Quantity

Hour
Hour
Hour
Day
Day

8.00
0.50
8.00
1.00
1.00

Day
Day
Day
Day
Day
sqm

11.00
4.00
3.00
15.00
1.00
60.00

15.00 cum
Rate
in Rs.
4.00
4.00
1145.00
1210.00
875.00
462.00
80.00
269.02
41.00
Rs:

Amount
in Rs.
19200.00
120.00
7728.75
4900.50
2362.50
2772.00
1536.00
16141.22
20.50
54781.47

Rate
in Rs.
53.50
85.30
10.20
85.30
7.60
21.50
Rs:

Amount
in Rs.
428.00
682.40
5.10
42.65
60.80
172.00
1390.95

Rate
in Rs.
189.80
96.10
136.60
385.00
370.00

Amount
in Rs.
1518.40
48.05
1092.80
385.00
370.00

295.00
295.00
295.00
295.00
295.00
75.30
Rs:

3245.00
1180.00
885.00
4425.00
295.00
4518.00
17962.25

Rs:
Rs:
Rs:
Rs:

54781.47
1390.95
17962.25
74134.67
10378.85

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

1197.50
0.14 167.70
1365.20

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)

Total
14.00% Rs:

248

Canal Cross Drainage Works - Item Unit Rates 2014-15

Total cost for


Rate per cum

15.00 cum
(A+B+C+D)/15.0

Rs:
Rs.

84513.52
5634.20

IRR-CCDW-2-14 Providing and laying insitu M-15 ( 28 days cube compressive strength not less than 15 N / sq
mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
aggregates for well bottom plug by tremie or skip box method including cost of all materials,
machinery, labour, batching, mixing, placing in position as per detailed specifications etc.,
complete with initial lead upto 50 m and all lifts. ( Cement content : 350 kg / cum )
(Cement content: 350 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4

Particulars

Cement for mix


Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened)
Super Plasticizer

UNIT :
Unit

Quantity

kg
cum
cum
cum
kg

4900.00
7.28
3.92
6.30
19.60
TOTAL
1%

Add for tremie arrangement @


Total cost of Materials
B. MACHINERY:
Sl No
1
2
3

Description

Unit

Concrete mixer 300/200 ltr ( diesel )


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Sundries( Hopper etc. )
Total hire charges of Machinery

Hour
Hour
Hour
Hour
LS

C. LABOUR:
Sl No

Description

1
2
3
4
5

Crew for Concrete mixer


Crew for Pump
Fitter shuttering
work inspector
mazdoor
for erecting/ dismantling tremie
for batching materials
for loading mortar pans
for feeding tremie hopper
for conveying concrete
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Unit

Quantity
8.00
8.00
0.50
0.50
5.00

Quantity

Hour
Hour
Day
Day

8.00
0.50
1.00
1.00

Day
Day
Day
Day
Day

4.00
11.00
4.00
2.00
16.00

14.00 cum
Rate
in Rs.
4.00
1210.00
875.00
462.00
80.00
Rs:
Rs:
Rs:

Amount
in Rs.
19600.00
8808.80
3430.00
2910.60
1568.00
36317.40
363.17
36680.57

Rate
in Rs.
53.50
85.30
10.20
85.30
41.00
Rs:

Amount
in Rs.
428.00
682.40
5.10
42.65
205.00
1363.15

Rate
in Rs.
189.80
96.10
345.00
370.00

Amount
in Rs.
1518.40
48.05
345.00
370.00

295.00
295.00
295.00
295.00
295.00
Rs:

1180.00
3245.00
1180.00
590.00
4720.00
13196.45

Rs:
Rs:
Rs:
Rs:

36680.57
1363.15
13196.45
51240.17
7173.62
58413.79
4172.40

942.60
0.14 132.00
1074.60

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

14.00 cum
(A+B+C+D)/14.0

Total
14.00% Rs:
Rs:
Rs.

IRR-CCDW-2-15 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than
15 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for well top plug including cost of all materials, machinery, labour, cleaning,
batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete with

249

Canal Cross Drainage Works - Item Unit Rates 2014-15

Note:

initial lead upto 50 m and all lifts.


If water is to be brought from other place add only lead charges @ 500 ltr / cum.
(Cement content: 280 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

3
4

Particulars

Unit

Cement for mix


Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened)
Super Plasticizer
Total cost of Materials

kg
cum
cum
cum
cum
kg

B. MACHINERY:
Sl No
1
2
3

Description

Unit

Concrete mixer 300/200 ltr ( diesel )


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Needle vibrator 40 mm dia ( petrol )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour

C. LABOUR:
Sl No
1
2
3
4
5
6

UNIT :

Description

Crew for Concrete mixer


Crew for Pump
Crew for Needle vibrator
Mason Class-I
work inspector
mazdoor
for batching materials
for loading mortar pans
for laying
for conveying concrete
for cleaning/ washing/ curing

Unit

Quantity
4001.20
6.43
3.86
2.57
5.72
16.00

Quantity
8.00
8.00
0.50
0.50
8.00
8.00

Quantity

Hour
Hour
Hour
Day
Day

8.00
0.50
8.00
1.00
1.00

Day
Day
Day
Day
Day

11.00
4.00
3.00
14.29
1.00

14.29 cum
Rate
in Rs.
4.00
1145.00
1210.00
875.00
462.00
80.00
Rs:

Amount
in Rs.
16004.80
7362.92
4668.54
2250.68
2640.79
1280.38
34208.12

Rate
in Rs.
53.50
85.30
10.20
85.30
7.60
21.50
Rs:

Amount
in Rs.
428.00
682.40
5.10
42.65
60.80
172.00
1390.95

Rate
in Rs.
189.80
96.10
136.60
385.00
370.00

Amount
in Rs.
1518.40
48.05
1092.80
385.00
370.00

295.00
295.00
295.00
295.00
295.00
Rs:

3245.00
1180.00
885.00
4215.55
295.00
13234.80

Rs:
Rs:
Rs:
Rs:

34208.12
1390.95
13234.80
48833.87
6836.74
55670.61
3895.80

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

926.20
0.14 129.70
1055.90

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

Total
14.00% Rs:
14.29 cum
Rs:
(A+B+C+D)/14.29
Rs.

IRR-CCDW-2-16 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than
20 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
aggregates for well cap including cost of all materials, machinery, labour, formwork,
scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc., complete with initial lead upto 50 m and all lifts.
Note:
If water is to be brought from other place add only lead charges @ 500 ltr / cum.
(Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)

250

Canal Cross Drainage Works - Item Unit Rates 2014-15

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6

Particulars

Unit

Cement for mix


Cement for incidentals @ 5 kg / cum
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened)
Super Plasticizer
Use rate of curved shutter (40 uses)
Sundries
Total cost of Materials

kg
kg
cum
cum
cum
kg
sqm
LS

B. MACHINERY:
Sl No
1
2
3

Description

Unit

Concrete mixer 300/200 ltr ( diesel )


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Needle vibrator 40 mm dia ( petrol )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour

C. LABOUR:
Sl No
1
2
3
4
5
6

UNIT :

Description

Unit

Crew for Concrete mixer


Crew for Pump
Crew for Needle vibrator
Mason Class-I
work inspector
mazdoor
for batching materials
for loading mortar pans
for laying
for conveying concrete
for cleaning/ washing/ curing
Labour cost for shuttering

Quantity
5200.80
78.80
8.20
4.41
7.09
20.80
15.76
0.50

Quantity
8.00
8.00
0.50
0.50
8.00
8.00

Quantity

Hour
Hour
Hour
Day
Day

8.00
0.50
8.00
1.00
1.00

Day
Day
Day
Day
Day
sqm

11.00
4.00
3.00
15.76
1.00
15.76

15.76 cum
Rate
in Rs.
4.00
4.00
1210.00
875.00
462.00
80.00
244.56
41.00
Rs:

Amount
in Rs.
20803.20
315.20
9916.19
3861.20
3276.50
1664.26
3854.33
20.50
43711.38

Rate
in Rs.
53.50
85.30
10.20
85.30
7.60
21.50
Rs:

Amount
in Rs.
428.00
682.40
5.10
42.65
60.80
172.00
1390.95

Rate
in Rs.
189.80
96.10
136.60
385.00
370.00

Amount
in Rs.
1518.40
48.05
1092.80
385.00
370.00

295.00
295.00
295.00
295.00
295.00
75.30
Rs:

3245.00
1180.00
885.00
4649.20
295.00
1186.73
14855.18

Rs:
Rs:
Rs:
Rs:

43711.38
1390.95
14855.18
59957.51
8394.05
68351.56
4337.00

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

942.60
0.14 132.00
1074.60

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

Total
14.00% Rs:
15.76 cum
Rs:
(A+B+C+D)/15.76
Rs.

IRR-CCDW-2-17 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than
15 N / sq mm ) grade cement concrete using 80 mm down size approved, clean, hard, graded
aggregates for piers and abutments including cost of all materials, labour, machinery,
formwork, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc., complete with initial lead upto 50 m and all lifts.
Note:
If water is to be brought from other place add only lead charges @ 500 ltr / cum.
(Cement content: 250 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.98cum, Blending Ratio of CA--35:30:20:15, FA : 0.35 cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

Particulars

UNIT :
Unit

Quantity

14.40 cum
Rate

Amount

251

Canal Cross Drainage Works - Item Unit Rates 2014-15

1
2

3
4
5
6

Cement for mix


Cement for incidentals @ 5 kg / cum
Coarse aggregate 80-40 mm
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened)
Super Plasticizer
Use rate of shuttering for 40 uses
Scaffolding @ of shuttering
Total cost of Materials

B. MACHINERY:
Sl No
1
2
3

kg
kg
cum
cum
cum
cum
cum
kg
sqm
30%

Description

Unit

Concrete mixer 600/400 ltr ( diesel )


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Needle vibrator 60 mm dia ( petrol )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour

C. LABOUR:
Sl No

Description

Unit

1
2
3
4
5
6

Crew for Concrete mixer


Crew for Pump
Crew for Needle vibrator
Mason Class-I
work inspector
mazdoor
for batching materials
for loading mortar pans
for laying
for conveying concrete
for cleaning/ washing/ curing
7
Labour cost for shuttering
Labour cost for scaffolding @
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

3600.00
72.00
4.94
4.23
2.82
2.12
5.04
14.40
39.60

Quantity
8.00
8.00
0.50
0.50
8.00
8.00

Quantity

in Rs.
4.00
4.00
635.00
1145.00
1210.00
875.00
462.00
80.00
256.79
Rs:

in Rs.
14400.00
288.00
3136.39
4847.47
3415.10
1852.20
2328.48
1152.00
10168.97
3050.69
44639.31

Rate
in Rs.
92.70
170.50
10.20
85.30
8.20
32.20
Rs:

Amount
in Rs.
741.60
1364.00
5.10
42.65
65.60
257.60
2476.55

Amount
in Rs.
1518.40
48.05
1092.80
385.00
370.00
3245.00
1180.00
1770.00
4248.00
295.00
2981.88
894.56
18028.69

Hour
Hour
Hour
Day
Day

8.00
0.50
8.00
1.00
1.00

Rate
in Rs.
189.80
96.10
136.60
385.00
370.00

Day
Day
Day
Day
Day
sqm
30%

11.00
4.00
6.00
14.40
1.00
39.60

295.00
295.00
295.00
295.00
295.00
75.30
Rs:

1252.00
0.14 175.30
1427.30

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

Rs:
Rs:
Rs:
Rs:

Total
14.00% Rs:
14.40 cum
Rs:
(A+B+C+D)/14.40
Rs.

44639.31
2476.55
18028.69
65144.55
9120.24
74264.791
5157.30

IRR-CCDW-2-18 Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than
10 N / sq mm ) grade cement concrete using 80 mm down size approved, clean, hard, graded
aggregates for piers and abutments including cost of all materials, labour, machinery,
formwork, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc., complete with initial lead upto 50 m and all lifts.
Note:
If water is to be brought from other place add only lead charges @ 500 ltr / cum.
(Cement content: 220 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.98cum, Blending Ratio of CA--35:30:20:15, FA : 0.35 cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

Particulars

UNIT :
Unit

Quantity

14.55 cum
Rate

Amount

252

Canal Cross Drainage Works - Item Unit Rates 2014-15

1
2

3
4
5
6

Cement for mix


Cement for incidentals @ 5 kg / cum
Coarse aggregate 80-40 mm
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened)
Super Plasticizer
Use rate ofshuttering for 40 uses
Scaffolding @ of shuttering
Total cost of Materials

B. MACHINERY:
Sl No
1
2
3

kg
kg
cum
cum
cum
cum
cum
kg
sqm
30%

Description

Unit

Concrete mixer 600/400 ltr ( diesel )


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Needle vibrator 60 mm dia ( petrol )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour

C. LABOUR:
Sl No

Description

Unit

1
2
3
4
5
6

Crew for Concrete mixer


Crew for Pump
Crew for Needle vibrator
Mason Class-I
work inspector
mazdoor
for batching materials
for loading mortar pans
for laying
for conveying concrete
for cleaning/ washing/ curing
7
Labour cost for shuttering
Labour cost for scaffolding @
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

3201.00
72.75
4.99
4.28
2.85
2.14
5.09
12.80
40.01

Quantity
8.00
8.00
0.50
0.50
8.00
8.00

Quantity

in Rs.
4.00
4.00
635.00
1145.00
1210.00
875.00
462.00
80.00
256.79
Rs:

in Rs.
12804.00
291.00
3169.06
4897.97
3450.68
1871.49
2352.74
1024.32
10274.90
3082.47
43218.62

Rate
in Rs.
92.70
170.50
10.20
85.30
8.20
32.20
Rs:

Amount
in Rs.
741.60
1364.00
5.10
42.65
65.60
257.60
2476.55

Amount
in Rs.
1518.40
48.05
1092.80
385.00
370.00
3245.00
1180.00
1770.00
4292.25
295.00
3012.94
903.88
18113.32

Hour
Hour
Hour
Day
Day

8.00
0.50
8.00
1.00
1.00

Rate
in Rs.
189.80
96.10
136.60
385.00
370.00

Day
Day
Day
Day
Day
sqm
30%

11.00
4.00
6.00
14.55
1.00
40.01

295.00
295.00
295.00
295.00
295.00
75.30
Rs:

1244.90
0.14 174.30
1419.20

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

Rs:
Rs:
Rs:
Rs:

Total
14.00% Rs:
14.55 cum
Rs:
(A+B+C+D)/14.55
Rs.

43218.62
2476.55
18113.32
63808.49
8933.19
72741.68
4999.40

IRR-CCDW-2-19 Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than
10 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for piers and abutments including cost of all materials, labour, machinery,
formwork, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc., complete with initial lead upto 50 m and all lifts.
Note:
If water is to be brought from other place add only lead charges @ 500 ltr / cum.
(Cement content: 220 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

Particulars

UNIT :
Unit

Quantity

16.36 cum
Rate

Amount

253

Canal Cross Drainage Works - Item Unit Rates 2014-15

1
2

3
4
5
6

Cement for mix


Cement for incidentals @ 5 kg / cum
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened)
Super Plasticizer
Use rate of shuttering for 40 uses
Scaffolding @ of shuttering
Total cost of Materials

B. MACHINERY:
Sl No
1
2
3

kg
kg
cum
cum
cum
cum
kg
sqm
30%

Description

Unit

Concrete mixer 300/200 ltr ( diesel )


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Needle vibrator 40 mm dia ( petrol )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour

C. LABOUR:
Sl No

Description

Unit

1
2
3
4
5
6

Crew for Concrete mixer


Crew for Pump
Crew for Needle vibrator
Mason Class-I
work inspector
mazdoor
for batching materials
for loading mortar pans
for laying
for conveying concrete
for cleaning/ washing/ curing
7
Labour cost for shuttering
Labour cost for scaffolding @
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

3599.20
81.80
7.36
4.42
2.94
6.54
14.40
44.99

Quantity
8.00
8.00
0.50
0.50
8.00
8.00

Quantity

in Rs.
4.00
4.00
1145.00
1210.00
875.00
462.00
80.00
256.79
Rs:

in Rs.
14396.80
327.20
8429.49
5344.81
2576.70
3023.33
1151.74
11553.08
3465.92
50269.08

Rate
in Rs.
53.50
85.30
10.20
85.30
7.60
21.50
Rs:

Amount
in Rs.
428.00
682.40
5.10
42.65
60.80
172.00
1390.95

Amount
in Rs.
1518.40
48.05
1092.80
385.00
370.00
3245.00
1180.00
1475.00
4826.20
295.00
3387.75
1016.32
18839.52

Hour
Hour
Hour
Day
Day

8.00
0.50
8.00
1.00
1.00

Rate
in Rs.
189.80
96.10
136.60
385.00
370.00

Day
Day
Day
Day
Day
sqm
30%

11.00
4.00
5.00
16.36
1.00
44.99

295.00
295.00
295.00
295.00
295.00
75.30
Rs:

1151.60
0.14 161.20
1312.80

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

Rs:
Rs:
Rs:
Rs:

Total
14.00% Rs:
16.36 cum
Rs:
(A+B+C+D)/16.36
Rs.

50269.08
1390.95
18839.52
70499.55
9869.94
80369.49
4912.60

IRR-CCDW-2-20 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than
20 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for cantiliver / counterfort retaining walls including cost of all materials,
machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position,
levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts.
(Cement content: 320 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
Note:

If water is to be brought from other place add only lead charges @ 500 ltr / cum.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

Particulars

UNIT :
Unit

Quantity

16.25 cum
Rate

Amount

254

Canal Cross Drainage Works - Item Unit Rates 2014-15

1
2

3
4
5
6

Cement for mix


Cement for incidentals @ 5 kg / cum
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened)
Super Plasticizer
Use rate of shuttering for 40 uses
Scaffolding @ of shuttering
Sundries
Total cost of Materials

B. MACHINERY:
Sl No
1
2
3

kg
kg
cum
cum
cum
cum
kg
sqm
25%
LS

Description

Unit

Concrete mixer 300/200 ltr ( diesel )


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Needle vibrator 40 mm dia ( petrol )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour

C. LABOUR:
Sl No

Description

Unit

1
2
3
4
5
6

Crew for Concrete mixer


Crew for Pump
Crew for Needle vibrator
Mason Class-I
work inspector
mazdoor
for batching materials
for loading mortar pans
for laying
for conveying concrete
for cleaning/ washing/ curing
7
Labour cost for shuttering
Labour cost for scaffolding @
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

5200.00
81.25
7.31
4.39
2.93
6.50
20.80
52.81

in Rs.
4.00
4.00
1145.00
1210.00
875.00
462.00
80.00
244.56
41.00
Rs:

in Rs.
20800.00
325.00
8372.81
5308.88
2559.38
3003.00
1664.00
12916.03
3229.01
20.50
58198.60

Rate
in Rs.
53.50
85.30
10.20
85.30
7.60
21.50
Rs:

Amount
in Rs.
428.00
682.40
5.10
42.65
60.80
172.00
1390.95

Amount
in Rs.
1518.40
48.05
1092.80
385.00
370.00
3245.00
1180.00
1475.00
4793.75
295.00
3976.78
994.20
19373.98

0.50

Quantity
8.00
8.00
0.50
0.50
8.00
8.00

Quantity

Hour
Hour
Hour
Day
Day

8.00
0.50
8.00
1.00
1.00

Rate
in Rs.
189.80
96.10
136.60
385.00
370.00

Day
Day
Day
Day
Day
sqm
25%

11.00
4.00
5.00
16.25
1.00
52.81

295.00
295.00
295.00
295.00
295.00
75.30
Rs:

1192.20
0.14 166.90
1359.10

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

Total
14.00% Rs:
16.25 cum
Rs:
(A+B+C+D)/16.25
Rs.

Rs:
Rs:
Rs:
Rs:

58198.60
1390.95
19373.98
78963.53
11054.89
90018.42
5539.60

IRR-CCDW-2-21 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than
15 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates with placing and sinking plums of size 150 to 80 mm upto 15 percent for gravity
type retaining walls / piers / abutments etc., including cost of all materials, machinery,
labour, formwork, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating,
finishing, curing etc.,complete with initial lead upto 50 m and all lifts.
Note:
If water is to be brought from other place add only lead charges @ 500 ltr / cum.
(Cement content: 260 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.765cum, Blending Ratio of CA--50:30:20, FA : 0.34 cum,
plums of size 150 to 80 mm : 0.25cum )

DATA:

RATE ANALYSIS

UNIT :

18.09 cum

255

Canal Cross Drainage Works - Item Unit Rates 2014-15

A. MATERIALS:
Sl No
1
2

3
4
5
6

Particulars

Unit

Cement for mix


Cement for incidentals @ 4 kg / cum
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Plums of size 150 to 80 mm
Fine aggregate (Un-Screened)
Super Plasticizer
Use rate of shuttering for 40 uses
Scaffolding @ of shuttering
Total cost of Materials

kg
kg
cum
cum
cum
cum
cum
kg
sqm
30%

B. MACHINERY:
Sl No
1
2
3

Description

Unit

Concrete mixer 300/200 ltr ( diesel )


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Needle vibrator 60 mm dia ( petrol )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour

C. LABOUR:
Sl No
1
2
3
4
5
6

Description

Crew for Concrete mixer


Crew for Pump
Crew for Needle vibrator
Mason Class-I
work inspector
mazdoor
for batching materials
for loading mortar pans
for laying
for placing plums
for conveying concrete
for conveying plums
for cleaning/ washing/ curing
Labour for shuttering
Labour for scaffolding @

Unit

Quantity
4703.40
72.36
6.92
4.15
2.77
4.52
6.15
18.81
49.75

Quantity
8.00
8.00
0.50
0.50
8.00
8.00

Quantity

Rate
in Rs.
4.00
4.00
1145.00
1210.00
875.00
340.00
462.00
80.00
244.56
Rs:

Amount
in Rs.
18813.60
289.44
7922.74
5023.50
2421.80
1537.65
2841.58
1505.09
12166.44
3649.93
56171.78

Rate
in Rs.
53.50
85.30
10.20
85.30
8.20
32.20
Rs:

Amount
in Rs.
428.00
682.40
5.10
42.65
65.60
257.60
1481.35

Amount
in Rs.
1518.40
48.05
1092.80
385.00
370.00
3245.00
1180.00
1475.00
590.00
4537.10
590.00
295.00
3745.99
1123.80
20196.13

Hour
Hour
Hour
Day
Day

8.00
0.50
8.00
1.00
1.00

Rate
in Rs.
189.80
96.10
136.60
385.00
370.00

Day
Day
Day
Day
Day
Day
Day
sqm
30%

11.00
4.00
5.00
2.00
15.38
2.00
1.00
49.75

295.00
295.00
295.00
295.00
295.00
295.00
295.00
75.30

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Rs:
1116.40
0.14 156.30
1272.70

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

Total
14.00% Rs:
18.09 cum
Rs:
(A+B+C+D)/18.09
Rs.

Rs:
Rs:
Rs:
Rs:

56171.78
1481.35
20196.13
77849.26
10898.9
88748.16
4905.90

IRR-CCDW-2-22 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than
15 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard,graded
aggregates for cast in-situ pipes including cost of all materials, machinery, labour, cleaning,
batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete with
initial lead upto 50 m and all lifts.
Note:
If water is to be brought from other place add only lead charges @ 500 ltr / cum.
(Cement content: 260 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

256

Canal Cross Drainage Works - Item Unit Rates 2014-15

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

3
4
5
6

Particulars

Unit

Cement for mix


Cement for incidentals @ 5 kg / cum
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened)
Super Plasticizer
Use rate of shuttering for 40 uses
Scaffolding @ of shuttering
Sundries
Total cost of Materials

kg
kg
cum
cum
cum
cum
kg
sqm
15%
LS

B. MACHINERY:
Sl No
1
2
3

Description

Unit

Concrete mixer 300/200 ltr ( diesel )


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Needle vibrator 40 mm dia ( petrol )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour

C. LABOUR:
Sl No
1
2
3
4
5
6

UNIT :

Description

Crew for Concrete mixer


Crew for Pump
Crew for Needle vibrator
Mason Class-I
work inspector
mazdoor
for batching materials
for loading mortar pans
for laying
for conveying concrete
for cleaning/ washing/ curing
Labour for shuttering
Labour for scaffolding @

Unit

Quantity
3998.80
76.90
6.92
4.15
2.77
6.15
16.00
30.76

15.38 cum
Rate
in Rs.
4.00
4.00
1145.00
1210.00
875.00
462.00
80.00
256.79
41.00
Rs:

Amount
in Rs.
15995.20
307.60
7924.55
5024.65
2422.35
2842.22
1279.62
7898.93
1184.84
20.50
44900.45

Rate
in Rs.
53.50
85.30
10.20
85.30
7.60
21.50
Rs:

Amount
in Rs.
428.00
682.40
5.10
42.65
60.80
172.00
1390.95

Amount
in Rs.
1518.40
48.05
1092.80
385.00
370.00
3245.00
1180.00
885.00
4537.10
295.00
2316.23
347.43
16220.01

0.50

Quantity
8.00
8.00
0.50
0.50
8.00
8.00

Quantity

Hour
Hour
Hour
Day
Day

8.00
0.50
8.00
1.00
1.00

Rate
in Rs.
189.80
96.10
136.60
385.00
370.00

Day
Day
Day
Day
Day
sqm
15%

11.00
4.00
3.00
15.38
1.00
30.76

295.00
295.00
295.00
295.00
295.00
75.30

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Rs:
1054.60
0.14 147.60
1202.20

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

Total
14.00% Rs:
15.38 cum
Rs:
(A+B+C+D)/15.38
Rs.

Rs:
Rs:
Rs:
Rs:

44900.45
1390.95
16220.01
62511.41
8751.6
71263.01
4633.50

IRR-CCDW-2-23 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than
15 N / sq mm ) grade cement concrete using 80 mm down size approved, clean, hard, graded
aggregates for cast in-situ pipes including cost of all materials, labour, machinery, formwork,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
complete with initial lead upto 50 m and all lifts.
Note:
If water is to be brought from other place add only lead charges @ 500 ltr / cum.
(Cement content: 250 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.98cum, Blending Ratio of CA--35:30:20:15, FA : 0.35 cum)

257

Canal Cross Drainage Works - Item Unit Rates 2014-15

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

3
4
5
6

Particulars

Unit

Cement for mix


Cement for incidentals @ 5 kg / cum
Coarse aggregate 80-40 mm
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened)
Super Plasticizer
Use rate of shuttering for 40 uses
Scaffolding @ of shuttering
Total cost of Materials

kg
kg
cum
cum
cum
cum
cum
kg
sqm
15%

B. MACHINERY:
Sl No
1
2
3

UNIT :

Description

Unit

Concrete mixer 600/400 ltr ( diesel )


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Needle vibrator 60 mm dia ( petrol )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour

C. LABOUR:
Sl No

Description

1
2
3
4
5
6

Crew for Concrete mixer


Crew for Pump
Crew for Needle vibrator
Mason Class-I
work inspector
mazdoor
for batching materials
for loading mortar pans
for laying
for conveying concrete
for cleaning/ washing/ curing
7
Labour cost for shuttering
Labour cost for scaffolding @
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Unit

Quantity
3600.00
72.00
4.94
4.23
2.82
2.12
5.04
14.40
28.80

Quantity
8.00
8.00
0.50
0.50
8.00
8.00

Quantity

14.40 cum
Rate
in Rs.
4.00
4.00
635.00
1145.00
1210.00
875.00
462.00
80.00
256.79
Rs:

Amount
in Rs.
14400.00
288.00
3136.39
4847.47
3415.10
1852.20
2328.48
1152.00
7395.61
1109.34
39924.60

Rate
in Rs.
92.70
170.50
10.20
85.30
8.20
32.20
Rs:

Amount
in Rs.
741.60
1364.00
5.10
42.65
65.60
257.60
2476.55

Amount
in Rs.
1518.40
48.05
1092.80
385.00
370.00
3245.00
1180.00
885.00
4248.00
295.00
2168.64
325.30
15761.19

Hour
Hour
Hour
Day
Day

8.00
0.50
8.00
1.00
1.00

Rate
in Rs.
189.80
96.10
136.60
385.00
370.00

Day
Day
Day
Day
Day
sqm
15%

11.00
4.00
3.00
14.40
1.00
28.80

295.00
295.00
295.00
295.00
295.00
75.30
Rs:

1094.50
0.14 153.20
1247.70

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

Total
14.00% Rs:
14.40 cum
Rs:
(A+B+C+D)/14.40
Rs.

Rs:
Rs:
Rs:
Rs:

39924.60
2476.55
15761.19
58162.34
8142.73
66305.07
4604.50

IRR-CCDW-2-24 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than
20 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
aggregates for deck slab & kerb including cost of all materials,machinery, labour, formwork,
scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc., complete with initial lead upto 50 m and all lifts.
Note:
If water is to be brought from other place add only lead charges @ 500 ltr / cum.
(Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)

258

Canal Cross Drainage Works - Item Unit Rates 2014-15

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6

Particulars

Unit

Cement for mix


Cement for incidentals @ 5 kg / cum
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened)
Super Plasticizer
Use rate of shuttering for 30 uses
Scaffolding @ of shuttering
Sundries
Total cost of Materials

kg
kg
cum
cum
cum
kg
sqm
250%
LS

B. MACHINERY:
Sl No
1
2
3

UNIT :

Description

Unit

Concrete mixer 300/200 ltr ( diesel )


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Needle vibrator 40 mm dia ( petrol )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour

C. LABOUR:
Sl No

Description

1
2
3
4
5
6

Crew for Concrete mixer


Crew for Pump
Crew for Needle vibrator
Mason Class-I
work inspector
mazdoor
for batching materials
for loading mortar pans
for laying
for conveying concrete
for cleaning/ washing/ curing
7
Labour cost for shuttering
Labour cost for scaffolding @
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Unit

Quantity
5200.80
78.80
8.20
4.41
7.09
20.80
39.40

15.76 cum
Rate
in Rs.
4.00
4.00
1210.00
875.00
462.00
80.00
297.55
41.00
Rs:

Amount
in Rs.
20803.20
315.20
9916.19
3861.20
3276.50
1664.26
11723.55
29308.86
41.00
80909.96

Rate
in Rs.
53.50
85.30
10.20
85.30
7.60
21.50
Rs:

Amount
in Rs.
428.00
682.40
5.10
42.65
60.80
172.00
1390.95

Amount
in Rs.
1518.40
48.05
1092.80
770.00
370.00
3245.00
1180.00
1180.00
4649.20
295.00
2966.82
7417.05
24732.32

1.00

Quantity
8.00
8.00
0.50
0.50
8.00
8.00

Quantity

Hour
Hour
Hour
Day
Day

8.00
0.50
8.00
2.00
1.00

Rate
in Rs.
189.80
96.10
136.60
385.00
370.00

Day
Day
Day
Day
Day
sqm
250%

11.00
4.00
4.00
15.76
1.00
39.40

295.00
295.00
295.00
295.00
295.00
75.30
Rs:

1569.30
0.14 219.70
1789.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

Total
14.00% Rs:
15.76 cum
Rs:
(A+B+C+D)/15.76
Rs.

Rs:
Rs:
Rs:
Rs:

80909.96
1390.95
24732.32
107033.23
14984.65
122017.88
7742.30

IRR-CCDW-2-25 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than
20 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
aggregates for columns and beams including cost of all materials, labour, machinery,
formwork, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating,
finishing, curing etc.,complete with initial lead upto 50 m and all lifts.
Note:

If water is to be brought from other place add only lead charges @ 500 ltr / cum.
(Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)

259

Canal Cross Drainage Works - Item Unit Rates 2014-15

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6

Particulars

Unit

Cement for mix


Cement for incidentals @ 5 kg / cum
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened)
Super Plasticizer
Use rate of shuttering
Scaffolding @ of shuttering
Sundries
Total cost of Materials

kg
kg
cum
cum
cum
kg
sqm
50%
LS

B. MACHINERY:
Sl No
1
2
3

UNIT :

Description

Unit

Concrete mixer 300/200 ltr ( diesel )


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Needle vibrator 40 mm dia ( petrol )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour

C. LABOUR:
Sl No

Description

1
2
3
4
5
6

Crew for Concrete mixer


Crew for Pump
Crew for Needle vibrator
Mason Class-I
work inspector
mazdoor
for batching materials
for loading mortar pans
for laying
for conveying concrete
for cleaning/ washing/ curing
7
Labour cost for shuttering
Labour cost for scaffolding @
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Unit

Quantity
5200.80
78.80
8.20
4.41
7.09
20.80
78.80

15.76 cum
Rate
in Rs.
4.00
4.00
1210.00
875.00
462.00
80.00
244.56
41.00
Rs:

Amount
in Rs.
20803.20
315.20
9916.19
3861.20
3276.50
1664.26
19271.64
9635.82
41.00
68785.01

Rate
in Rs.
53.50
85.30
10.20
85.30
7.60
21.50
Rs:

Amount
in Rs.
428.00
682.40
5.10
42.65
60.80
172.00
1390.95

Amount
in Rs.
1518.40
48.05
1092.80
385.00
370.00
3245.00
1180.00
885.00
4649.20
295.00
5933.64
2966.82
22568.91

1.00

Quantity
8.00
8.00
0.50
0.50
8.00
8.00

Quantity

Hour
Hour
Hour
Day
Day

8.00
0.50
8.00
1.00
1.00

Rate
in Rs.
189.80
96.10
136.60
385.00
370.00

Day
Day
Day
Day
Day
sqm
50%

11.00
4.00
3.00
15.76
1.00
78.80

295.00
295.00
295.00
295.00
295.00
75.30
Rs:

1432.00
0.14 200.50
1632.50

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

Total
14.00% Rs:
15.76 cum
Rs:
(A+B+C+D)/15.76
Rs.

Rs:
Rs:
Rs:
Rs:

68785.01
1390.95
22568.91
92744.87
12984.28
105729.15
6708.70

IRR-CCDW-2-26 Providing and laying insitu M- 20 ( 28 days cube compressive strength not less than 20 N /
sqmm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
aggregates for wearing coat including cost of all materials, machinery, labour, formwork,
cleaning, batching, mixing, placing in position in alternate panels, levelling, compacting,
finishing, curing, packing joints with asphalt mortar etc., complete with initial lead upto 50 m
and all lifts.
Note:
If water is to be brought from other place add only lead charges @ 500 ltr / cum. to the data
(Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)

260

Canal Cross Drainage Works - Item Unit Rates 2014-15

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6

Particulars

Unit

Cement for mix


Cement for incidentals @ 5 kg / cum
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened)
Super Plasticizer
Use rate of shuttering
Sundries ( asphalt mortar etc )
Total cost of Materials

kg
kg
cum
cum
cum
kg
sqm
LS

B. MACHINERY:
Sl No
1
2
3

Description

Unit

Concrete mixer 300/200 ltr ( diesel )


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Needle vibrator 40 mm dia ( petrol )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour

C. LABOUR:
Sl No
1
2
3
4
5
6

UNIT :

Description

Unit

Crew for Concrete mixer


Crew for Pump
Crew for Needle vibrator
Mason Class-I
work inspector
mazdoor
for batching materials
for loading mortar pans
for laying
for conveying concrete
for cleaning/ washing/ curing
Labour cost for shuttering

Quantity
5200.80
78.80
8.20
4.41
7.09
20.80
7.88
5.00

Quantity
8.00
8.00
0.50
0.50
8.00
8.00

Quantity

Hour
Hour
Hour
Day
Day

8.00
0.50
8.00
2.00
1.00

Day
Day
Day
Day
Day
sqm

11.00
4.00
4.00
15.76
2.00
7.88

15.76 cum
Rate
in Rs.
4.00
4.00
1210.00
875.00
462.00
80.00
244.56
41.00
Rs:

Amount
in Rs.
20803.20
315.20
9916.19
3861.20
3276.50
1664.26
1927.16
205.00
41968.72

Rate
in Rs.
53.50
85.30
10.20
85.30
7.60
21.50
Rs:

Amount
in Rs.
428.00
682.40
5.10
42.65
60.80
172.00
1390.95

Rate
in Rs.
189.80
96.10
136.60
385.00
370.00

Amount
in Rs.
1518.40
48.05
1092.80
770.00
370.00

295.00
295.00
295.00
295.00
295.00
75.30
Rs:

3245.00
1180.00
1180.00
4649.20
590.00
593.36
15236.81

Rs:
Rs:
Rs:
Rs:

41968.72
1390.95
15236.81
58596.48
8203.51
66799.99
4238.60

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

966.80
0.14 135.40
1102.20

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

Total
14.00% Rs:
15.76 cum
Rs:
(A+B+C+D)/15.76
Rs.

IRR-CCDW-2-27 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than
20 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
aggregates for troughs including cost of all materials, machinery, labour, formwork,
scaffolding, cleaning, batching, mixing, placing in position,levelling, vibrating, finishing, curing
etc., complete with initial lead upto 50 m and all lifts.
Note:
If water is to be brought from other place add only lead charges @ 500 ltr / cum. to the data
(Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)

DATA:

RATE ANALYSIS

UNIT :

15.76 cum

A. MATERIALS:

261

Canal Cross Drainage Works - Item Unit Rates 2014-15

Sl No

Particulars

Unit

Cement for mix


Cement for incidentals @ 5 kg / cum
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened)
Super Plasticizer
Use rate of shuttering for 40 uses
Scaffolding @ of shuttering
Sundries
Total cost of Materials

kg
kg
cum
cum
cum
kg
sqm
25%
LS

2
3
4
5
6

B. MACHINERY:
Sl No
1
2
3

Description

Unit

Concrete mixer 300/200 ltr ( diesel )


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Needle vibrator 40 mm dia ( diesel )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour

C. LABOUR:
Sl No

Description

1
2
3
4
5
6

Crew for Concrete mixer


Crew for Pump
Crew for Needle vibrator
Mason Class-I
work inspector
mazdoor
for batching materials
for loading mortar pans
for laying
for conveying concrete
for cleaning/ washing/ curing
7
Labour cost for shuttering
Labour cost for scaffolding @
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Unit

Quantity
5200.80
78.80
8.20
4.41
7.09
20.80
70.92

Rate
in Rs.
4.00
4.00
1210.00
875.00
462.00
80.00
244.56
41.00
Rs:

Amount
in Rs.
20803.20
315.20
9916.19
3861.20
3276.50
1664.26
17344.47
4336.12
20.50
61537.64

Rate
in Rs.
53.50
85.30
10.20
85.30
7.60
21.50
Rs:

Amount
in Rs.
428.00
682.40
5.10
42.65
60.80
172.00
1390.95

Amount
in Rs.
1518.40
48.05
1092.80
385.00
370.00
3245.00
1180.00
1475.00
4649.20
295.00
5340.28
1335.07
20933.80

0.50

Quantity
8.00
8.00
0.50
0.50
8.00
8.00

Quantity

Hour
Hour
Hour
Day
Day

8.00
0.50
8.00
1.00
1.00

Rate
in Rs.
189.80
96.10
136.60
385.00
370.00

Day
Day
Day
Day
Day
sqm
25%

11.00
4.00
5.00
15.76
1.00
70.92

295.00
295.00
295.00
295.00
295.00
75.30
Rs:

1328.30
0.14 186.00
1514.30

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum
IRR-CCDW-3

Total
14.00% Rs:
15.76 cum
Rs:
(A+B+C+D)/15.76
Rs.

Rs:
Rs:
Rs:
Rs:

61537.64
1390.95
20933.80
83862.39
11740.73
95603.12
6066.20

FOUNDATION WELL SINKING WORKS :

IRR-CCDW-3-1 Sinking RCC wells vertically for foundation of piers and abutments in all kinds of soil, sand
DATA:
Unit = Running meter
Taking output = 1m
diameter of well = 6.00m
(i)
Depth below bed level upto 3.0m
Rate of sinking = 0.50 m /hour
a) Labour
0.12 Mate (Mason Cl- ll )
345.00 day
41.40
1.00 Sinker ( skilled)
385.00 day
385.00
2.00 Sinking helper ( Semi skilled)
295.00 day
590.00
sub total (a)
1016.40
b) Machinery

262

Canal Cross Drainage Works - Item Unit Rates 2014-15

2.00

(ii)

Hire & running charges of crane with grab


519.70 hour
bucket of 0.75 cum capacity and accessories.
Fuel Charges
322.20 hour
Crew Charges
153.10 hour
Consumables in sinking @ 10% of machinery charges
sub total (b)
sub total (a+b)
c) Add for Contractor's profit and overhead
charges on (A+B)
14.00%

1039.40

Rate per metre = (a+b+c)/1.0


or say ( Rate upto 3.0m for 6.0 m well sinking )
labour component/unit qty
Contractor's profit and overhead charges
14.00%
labour component/unit qty(including contractor's profit)

3654.16
3654.20

644.40
306.20
199.00
2189.00
3205.40
448.76

1322.60
185.20
1507.80

Beyond 3m and upto 10m depth


Rate of sinking = 0.33 m per hour.

a) Labour
0.15
1.25
2.50

Mate (Mason Cl- ll )


Sinker ( skilled)
Sinking helper ( Semi skilled)

345.00 day
385.00 day
295.00 day

51.75
481.25
737.50
1270.50

sub total (a)


b) Machinery
3.00 Hire & running charges of crane with grab
519.70 hour
bucket of 0.75 cum capacity and accessories.
Fuel Charges
322.20 hour
Crew Charges
153.10 hour
Consumables in sinking @ 10% of machinery charges
sub total (b)
sub total (a+b)
c) Add for Contractor's profit and overhead
charges on (A+B)
14.00%
Rate per metre = (a+b+c)
or say ( Rate for 3.0m to 10m well sinking )

1559.10
966.60
459.30
298.50
3283.50
4554.00
637.56
5191.56
5191.60

labour component/unit qty


Contractor's profit and overhead charges
0.14
labour component/unit qty(including contractor's profit)

1729.80
242.20
1972.00

IRR-CCDW-3-2 Filling foundation wells with sand in layers of 25 to 30 cm and compacting by watering,
ramming as directed including cost of all materials, machinery, labour etc., complete with
initial lead upto 50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

Particulars

Sand for filling

UNIT :
Unit
cum

Quantity
15.75

Total cost of Materials


B. MACHINERY:
Sl No
1

Description

Unit

Nill

Quantity
0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No
1
2

Description

work inspector
mazdoor

Unit
Day
Day

Total cost of Labour

Quantity
0.25
4.00

15.00 cum
Rate
in Rs.
342.00
0.00
Rs:

Amount
in Rs.
5386.50
0.00
5386.50

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
370.00
295.00
Rs:

Amount
in Rs.
92.50
1180.00
1272.50

263

Canal Cross Drainage Works - Item Unit Rates 2014-15

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

84.80
0.14 11.90
96.70

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum
IRR-CCDW-4

15.00 cum
(A+B+C+D)/15.0

Rs:
Rs:
Rs:
Rs:

Total
14.00% Rs:
Rs:
Rs.

5386.50
0.00
1272.50
6659.00
932.26
7591.26
506.10

MASONRY WORKS :

IRR-CCDW-4-1 Providing and constructing un-coursed rubble stone masonry with approved stones in
CM 1 : 4 proportion for sub-structure portions of return walls / abutments etc., including
cost of all materials, machinery, labour, scaffolding, cleaning, packing cement mortar, wedging
stone chips, curing etc., complete with initial lead upto 50 m and all lifts.
(Cement content: 143 kg / cum of masonry, rubble stones : 0.85cum, FA : 0.40 cum,
Stone Chips : 0.15 cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4

Particulars

Cement
Rubble stones
Stone chips
Sand (Screened)

UNIT :
Unit

Quantity

kg
cum
cum
cum

1430.00
8.50
1.50
4.00

Total cost of Materials


B. MACHINERY:
Sl No
1
2

Description

Unit

Water tanker 8000 ltr


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour

C. LABOUR:
Sl No

Description

1
2
3
4
5
6

Crew for Water tanker


Crew for Pump
work inspector
Mason Class-I
Mason Class-II
mazdoor
for conveying rubble stones
for preparing mortar
for loading mortar pans
for laying & packing mortar
for washing rubble / finishing / curing
for conveying mortar / chips
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Unit

Quantity
1.00
1.00
0.50
0.50

Quantity

Hour
Hour
Day
Day
Day

1.00
0.50
1.00
1.00
2.00

Day
Day
Day
Day
Day
Day

4.00
2.00
1.00
3.00
1.00
4.00

10.00 cum
Rate
in Rs.
4.00
318.00
340.00
606.00
Rs:

Amount
in Rs.
5720.00
2703.00
510.00
2424.00
11357.00

Rate
in Rs.
402.50
322.20
10.20
85.30
Rs:

Amount
in Rs.
402.50
322.20
5.10
42.65
772.45

Rate
in Rs.
153.10
96.10
370.00
385.00
345.00

Amount
in Rs.
153.10
48.05
370.00
385.00
690.00

295.00
295.00
295.00
295.00
295.00
295.00
Rs:

1180.00
590.00
295.00
885.00
295.00
1180.00
6071.15

Rs:
Rs:
Rs:
Rs:

11357.00
772.45
6071.15
18200.60
2548.08

607.10
0.14 85.00
692.10

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)

Total
14.00% Rs:

264

Canal Cross Drainage Works - Item Unit Rates 2014-15

Total cost for


Rate per cum

10.00 cum
(A+B+C+D)/10.0

Rs:
Rs.

20748.68
2074.90

IRR-CCDW-4-2 Providing and constructing un-coursed rubble stone masonry with approved stones in
CM 1 : 4 proportion for super-structure portions of return walls / abutments etc., including
cost of all materials, machinery, labour, scaffolding, cleaning, packing cement mortar, wedging
stone chips, curing etc., complete with initial lead upto 50 m and all lifts.
(Cement content: 143 kg / cum of masonry, rubble stones : 0.85cum, FA : 0.40 cum,
Stone Chips : 0.15 cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4

Particulars

Cement
Rubble stones
Stone chips
Sand (Screened)

UNIT :
Unit

Quantity

kg
cum
cum
cum

1430.00
8.50
1.50
4.00
TOTAL
2.5%

Add for scaffolding @


Total cost of Materials
B. MACHINERY:
Sl No
1
2

Description

Unit

Water tanker 8000 ltr


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour

C. LABOUR:
Sl No
1
2
3
4
5
6

Description

Crew for Water tanker


Crew for Pump
work inspector
Mason Class-I
Mason Class-II
mazdoor
for conveying rubble stones
for preparing mortar
for loading mortar pans
for laying & packing mortar
for washing rubble / finishing / curing
for conveying mortar / chips

Add for labour for scaffolding @


Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Unit

Quantity
1.00
1.00
0.50
0.50

Quantity

Hour
Hour
Day
Day
Day

1.00
0.50
1.00
1.00
2.00

Day
Day
Day
Day
Day
Day

4.00
2.00
1.00
3.00
1.00
4.00
TOTAL
2.5%

10.00 cum
Rate
in Rs.
4.00
318.00
340.00
606.00
Rs:
Rs:
Rs:

Amount
in Rs.
5720.00
2703.00
510.00
2424.00
11357.00
283.93
11640.93

Rate
in Rs.
402.50
322.20
10.20
85.30
Rs:

Amount
in Rs.
402.50
322.20
5.10
42.65
772.45

Rate
in Rs.
153.10
96.10
370.00
385.00
345.00

Amount
in Rs.
153.10
48.05
370.00
385.00
690.00

295.00
295.00
295.00
295.00
295.00
295.00
Rs:
Rs:
Rs:

1180.00
590.00
295.00
885.00
295.00
1180.00
6071.15
151.78
6222.93

Rs:
Rs:
Rs:
Rs:

11640.93
772.45
6222.93
18636.30
2609.08
21245.38
2124.50

622.30
0.14 87.10
709.40

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

10.00 cum
(A+B+C+D)/10.0

Total
14.00% Rs:
Rs:
Rs.

IRR-CCDW-4-3 Providing and constructing coursed rubble masonry second sort in CM 1:4 proportion with
stones from approved source including cost of all materials, machinery, labour, scaffolding,
ramps, cleaning, packing mortar, wedging stone chips, finishing, curing etc., complete with

265

Canal Cross Drainage Works - Item Unit Rates 2014-15

initial lead upto 50 m and initial lift upto 3m.


(Cement content: 133 kg / cum of masonry, rubble stones : 0.45cum, FA : 0.35 cum,
Stone Chips : 0.15 cum, Khandki stones 25 x 25 x 30 cm : 180 Nos, Header stones
25 x 25x 45 cm : 60 Nos)
DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6

UNIT :

Particulars

Unit

Cement
Header stones 25x25x45 cm
Khandki stones 25x25x30 cm
Rubble stones
Stone chips
Sand (Screened)

kg
Nos
Nos
cum
cum
cum

Quantity
1330.00
60.00
180.00
4.50
1.50
3.50
TOTAL
2.5%

Add for scaffolding materials @


Total cost of Materials
B. MACHINERY:
Sl No
1
2

Description

Unit

Water tanker 8000 ltr


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour

C. LABOUR:
Sl No
1
2
3
4
5
6
7

Description

Crew for Water tanker


Crew for Pump
work inspector
Stone chiseller Cl -II
Mason Class-I
Mason Class-II
mazdoor
for conveying stones / rubble
for preparation of mortar
for loading mortar pans
for laying & packing mortar
for washing rubble / finishing / curing
for conveying mortar / chips

Add for labour for scaffolding @


Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Unit

Quantity
1.00
1.00
0.50
0.50

Quantity

Hour
Hour
Day
Day
Day
Day

1.00
0.50
1.00
3.00
1.00
2.00

Day
Day
Day
Day
Day
Day

4.00
3.00
1.00
3.00
1.00
2.00
TOTAL
2.5%

10.00 cum
Rate
in Rs.
4.00
39.00
16.00
318.00
340.00
606.00
Rs:
Rs:
Rs:

Amount
in Rs.
5320.00
2340.00
2880.00
1431.00
510.00
2121.00
14602.00
365.05
14967.05

Rate
in Rs.
402.50
322.20
10.20
85.30
Rs:

Amount
in Rs.
402.50
322.20
5.10
42.65
772.45

Rate
in Rs.
153.10
96.10
370.00
345.00
385.00
345.00

Amount
in Rs.
153.10
48.05
370.00
1035.00
385.00
690.00

295.00
295.00
295.00
295.00
295.00
295.00
Rs:
Rs:
Rs:

1180.00
885.00
295.00
885.00
295.00
590.00
6811.15
170.28
6981.43

Rs:
Rs:
Rs:
Rs:

14967.05
772.45
6981.43
22720.93
3180.93
25901.86
2590.20

698.10
0.14 97.70
795.80

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

10.00 cum
(A+B+C+D)/10.0

Total
14.00% Rs:
Rs:
Rs.

IRR-CCDW-4-4 Providing and constructing coursed rubble masonry first sort in CM 1:4 proportion with
stones from approved source including cost of all materials, machinery, labour, scaffolding,
ramps, cleaning, packing mortar, wedging stone chips, finishing, curing etc., complete with
initial lead upto 50 m and initial lift upto 3 m.
(Cement content: 133 kg / cum of masonry, rubble stones : 0.45cum, FA : 0.35 cum,
Stone Chips : 0.15 cum, Khandki stones 25 x 25 x 30 cm : 180 Nos, Header stones
25 x 25x 45 cm : 60 Nos)

266

Canal Cross Drainage Works - Item Unit Rates 2014-15

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6

UNIT :

Particulars

Unit

Cement
Header stones 25x25x45 cm
Khandki stones 25x25x30 cm
Rubble stones
Stone chips
Sand (Screened)

kg
Nos
Nos
cum
cum
cum

Quantity
1330.00
60.00
180.00
4.50
1.50
3.50
TOTAL
2.5%

Add for scaffolding materials @


Total cost of Materials
B. MACHINERY:
Sl No
1
2

Description

Unit

Water tanker 8000 ltr


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour

C. LABOUR:
Sl No
1
2
3
4
5
6
7
8

Description

Unit

Crew for Water tanker


Crew for Pump
work inspector
Stone chiseller Cl -II
Mason Class-I
Mason Class-II
mazdoor
for conveying rubble/ stones
for preparation of mortar
for loading mortar pans
for laying & packing mortar
for washing rubble / finishing / curing
for conveying mortar / chips

Add for labour for scaffolding @


Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Quantity
1.00
1.00
0.50
0.50

Quantity

Hour
Hour
Day
Day
Day
Day

1.00
0.50
1.00
6.00
1.00
2.00

Day
Day
Day
Day
Day
Day

4.00
3.00
1.00
3.00
1.00
2.00
TOTAL
2.5%

10.00 cum
Rate
in Rs.
4.00
39.00
16.00
318.00
340.00
606.00
Rs:
Rs:
Rs:

Amount
in Rs.
5320.00
2340.00
2880.00
1431.00
510.00
2121.00
14602.00
365.05
14967.05

Rate
in Rs.
402.50
322.20
10.20
85.30
Rs:

Amount
in Rs.
402.50
322.20
5.10
42.65
772.45

Rate
in Rs.
153.10
96.10
370.00
345.00
385.00
345.00

Amount
in Rs.
153.10
48.05
370.00
2070.00
385.00
690.00

295.00
295.00
295.00
295.00
295.00
295.00
Rs:
Rs:
Rs:

1180.00
885.00
295.00
885.00
295.00
590.00
7846.15
196.15
8042.30

Rs:
Rs:
Rs:
Rs:

14967.05
772.45
8042.30
23781.80
3329.45
27111.25
2711.10

804.20
0.14 112.60
916.80

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

10.00 cum
(A+B+C+D)/10.0

Total
14.00% Rs:
Rs:
Rs.

IRR-CCDW-4-5 Providing cement mortar pointing to coursed rubble face stone masonry in CM 1 : 2
proportion by volume including raking and cleaning joints for 50 mm depth, pressing cement
mortar into joints, cost of all materials, labour, scaffolding, finishing, curing etc., complete with
initial lead upto 50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

Cement

Particulars

UNIT :
Unit
kg

Quantity
456.00

100.00 sqm
Rate
in Rs.
4.00

Amount
in Rs.
1824.00

267

Canal Cross Drainage Works - Item Unit Rates 2014-15

Sand (Screened)

cum

0.75
TOTAL
2.5%

Add for scaffolding / ramps etc @


Total cost of Materials
B. MACHINERY:
Sl No
1

Description

Quantity

Nil
( Manual mixing)
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3

Unit

Description

0.00
0.00

Unit

Mason Cl- I
work inspector
mazdoor

Quantity

Day
Day
Day

10.00
1.00
10.00

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

606.00
Rs:
Rs:
Rs:

454.50
2278.50
56.96
2335.46

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
385.00
370.00
295.00
Rs:

Amount
in Rs.
3850.00
370.00
2950.00
7170.00

Rs:
Rs:
Rs:
Rs:

2335.46
0.00
7170.00
9505.46
1330.76
10836.22
108.40

71.70
0.14 10.00
81.70

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per sqm

Total
14.00% Rs:
100.00 sqm
Rs:
(A+B+C+D)/100.0
Rs.

IRR-CCDW-4-6 Providing cement mortar pointing to coursed rubble face stone masonry in CM 1 : 3
proportion by volume including raking and cleaning joints for 50 mm depth, pressing cement
mortar into joints, cost of all materials, labour, scaffolding, finishing, curing etc., complete with
initial lead upto 50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

Particulars

Cement
Sand (Screened)

UNIT :
Unit

Quantity

kg
cum

322.00
0.75
TOTAL
2.5%

Add for scaffolding / ramps etc @


Total cost of Materials
B. MACHINERY:
Sl No
1

Unit

Quantity

Nil
( Manual mixing)
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3

Description

Description

Mason Cl- I
work inspector
mazdoor

0.00
0.00

Unit

Quantity

Day
Day
Day
Total cost of Labour

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

10.00
1.00
10.00

100.00 sqm
Rate
in Rs.
4.00
606.00
Rs:
Rs:
Rs:

Amount
in Rs.
1288.00
454.50
1742.50
43.56
1786.06

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
385.00
370.00
295.00
Rs:

Amount
in Rs.
3850.00
370.00
2950.00
7170.00

71.70
0.14 10.00
81.70

ABSTRACT:

268

Canal Cross Drainage Works - Item Unit Rates 2014-15

A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per sqm

Total
14.00% Rs:
100.00 sqm
Rs:
(A+B+C+D)/100.0
Rs.

Rs:
Rs:
Rs:
Rs:

1786.06
0.00
7170.00
8956.06
1253.85
10209.91
102.10

IRR-CCDW-4-7 Providing 12 mm thick plastering in cement mortar 1:3 proportion by volume including cost
of all materials, machinery, labour, scaffolding, cleaning joints, smooth finishing, curing etc.,
complete with initial lead upto 50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

Particulars

UNIT :
Unit

Cement
Sand (Screened)

Quantity

kg
cum

629.00
1.32
TOTAL
2.5%

Add for scaffolding / ramps etc @


Total cost of Materials
B. MACHINERY:
Sl No
1

Description

Quantity

Nil
( Manual mixing)
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3

Unit

Description

0.00
0.00

Unit

Mason Cl- I
work inspector
mazdoor

Quantity

Day
Day
Day

10.00
1.00
20.00

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

100.00 sqm
Rate
in Rs.
4.00
606.00
Rs:
Rs:
Rs:

Amount
in Rs.
2516.00
799.92
3315.92
82.90
3398.82

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
385.00
370.00
295.00
Rs:

Amount
in Rs.
3850.00
370.00
5900.00
10120.00

Rs:
Rs:
Rs:
Rs:

3398.82
0.00
10120.00
13518.82
1892.63
15411.45
154.10

101.20
0.14 14.20
115.40

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per sqm

Total
14.00% Rs:
100.00 sqm
Rs:
(A+B+C+D)/100.0
Rs.

IRR-CCDW-4-8 Providing 12 mm thick plastering in cement mortar 1:4 proportion by volume including cost
of all materials, machinery, labour, scaffolding, cleaning joints, smooth finishing, curing etc.,
complete with initial lead upto 50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

Particulars

Cement
Sand (Screened)
Add for scaffolding / ramps etc @
Total cost of Materials

UNIT :
Unit
kg
cum

Quantity
472.00
1.32
TOTAL
2.5%

100.00 sqm
Rate
in Rs.
4.00
606.00
Rs:
Rs:
Rs:

Amount
in Rs.
1888.00
799.92
2687.92
67.20
2755.12

B. MACHINERY:

269

Canal Cross Drainage Works - Item Unit Rates 2014-15

Sl No

Description

Quantity

Nil
( Manual mixing)
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3

Unit

Description

0.00
0.00

Unit

Mason Cl- I
work inspector
mazdoor

Quantity

Day
Day
Day

10.00
1.00
20.00

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
385.00
370.00
295.00
Rs:

Amount
in Rs.
3850.00
370.00
5900.00
10120.00

Rs:
Rs:
Rs:
Rs:

2755.12
0.00
10120.00
12875.12
1802.52
14677.638
146.80

101.20
0.14 14.20
115.40

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per sqm

Total
14.00% Rs:
100.00 sqm
Rs:
(A+B+C+D)/100.0
Rs.

IRR-CCDW-4-9 Providing 20 mm thick plastering in cement mortar 1:3 proportion by volume including cost
of all materials, machinery, labour, scaffolding, cleaning joints, smooth finishing, curing etc.,
complete with initial lead upto 50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

Particulars

Cement
Sand (Screened)

UNIT :
Unit

Quantity

kg
cum

1050.00
2.20
TOTAL
2.5%

Add for scaffolding / ramps etc @


Total cost of Materials
B. MACHINERY:
Sl No
1

Description

Quantity

Nil
( Manual mixing)
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3

Unit

Description

Mason Cl- I
work inspector
mazdoor

0.00
0.00

Unit

Quantity

Day
Day
Day
Total cost of Labour

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

15.00
1.00
25.00

100.00 sqm
Rate
in Rs.
4.00
606.00
Rs:
Rs:
Rs:

Amount
in Rs.
4200.00
1333.20
5533.20
138.33
5671.53

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
385.00
370.00
295.00
Rs:

Amount
in Rs.
5775.00
370.00
7375.00
13520.00

Rs:
Rs:
Rs:
Rs:

5671.53
0.00
13520.00
19191.53
2686.81
21878.34
218.80

135.20
0.14 18.90
154.10

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per sqm

Total
14.00% Rs:
100.00 sqm
Rs:
(A+B+C+D)/100.0
Rs.

270

Canal Cross Drainage Works - Item Unit Rates 2014-15

IRR-CCDW-4-10 Providing 20 mm thick plastering in cement mortar 1:4 proportion by volume including cost
of all materials, machinery, labour, scaffolding, cleaning joints, smooth finishing, curing etc.,
complete with initial lead upto 50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

Particulars

UNIT :
Unit

Cement
Sand (Screened)

Quantity

kg
cum

788.00
2.20
TOTAL
2.5%

Add for scaffolding / ramps etc @


Total cost of Materials
B. MACHINERY:
Sl No
1

Description

Quantity

Nil
( Manual mixing)
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3

Unit

Description

0.00
0.00

Unit

Mason Cl- I
work inspector
mazdoor

Quantity

Day
Day
Day

15.00
1.00
25.00

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

100.00 sqm
Rate
in Rs.
4.00
606.00
Rs:
Rs:
Rs:

Amount
in Rs.
3152.00
1333.20
4485.20
112.13
4597.33

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
385.00
370.00
295.00
Rs:

Amount
in Rs.
5775.00
370.00
7375.00
13520.00

Rs:
Rs:
Rs:
Rs:

4597.33
0.00
13520.00
18117.33
2536.43
20653.76
206.50

135.20
0.14 18.90
154.10

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per sqm
IRR-CCDW-5

Total
14.00% Rs:
100.00 sqm
Rs:
(A+B+C+D)/100.0
Rs.

COPING & RAILING WORKS :

IRR-CCDW-5-1 Providing and fixing 10 cm thick roughly dressed burnt stone slabs for coping set in
CM 1: 6 proportion by volume with pointing to joints in CM 1 : 3 proportion by volume including
cost of all materials, machinery, labour, finishing, curing etc., complete with initial lead upto
50 m and all lifts.
(Cement content: 7.5 kg / sqm, FA : 0.030 cum/sqm,
Burnt stone slab 10 cm thick 1.05 sqm/ sqm)
DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3

Particulars

Unit

Cement
Sand (Screened)
Burnt stone slab 10 cm thick
Total cost of Materials

kg
cum
sqm

B. MACHINERY:
Sl No
1

UNIT :

Description
Nil
( Manual mixing)
Total hire charges of Machinery

Unit

Quantity
75.00
0.30
10.50

Quantity
0.00
0.00

10.00 sqm
Rate
in Rs.
4.00
606.00
300.00
Rs:

Amount
in Rs.
300.00
181.80
3150.00
3631.80

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

271

Canal Cross Drainage Works - Item Unit Rates 2014-15

C. LABOUR:
Sl No
1
2
3
4

Description

Unit

Mason Cl- II
Stone chiseller Cl- II
work inspector
mazdoor

Quantity

Day
Day
Day
Day

1.00
1.00
0.50
2.00

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Rate
in Rs.
345.00
345.00
370.00
295.00
Rs:

Amount
in Rs.
345.00
345.00
185.00
590.00
1465.00

Rs:
Rs:
Rs:
Rs:

3631.80
0.00
1465.00
5096.80
713.55
5810.35
581.00

146.50
0.14 20.50
167.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per sqm

10.00 sqm
(A+B+C+D)/10.0

Total
14.00% Rs:
Rs:
Rs.

IRR-CCDW-5-2 Providing and fixing 10 cm thick one line dressed burnt stone slabs for coping set in
CM 1: 6 proportion by volume with pointing to joints in CM 1 : 3 proportion by volume including
cost of all materials, machinery, labour, finishing, curing etc., complete with initial lead upto
50 m and all lifts.
(Cement content: 7.5 kg / sqm, FA : 0.030 cum/sqm, Burnt stone slab 10 cm
thick 1.05 sqm/ sqm)
DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3

Particulars

Unit

Cement
Sand (Screened)
Burnt stone slab 10 cm thick
Total cost of Materials

kg
cum
sqm

B. MACHINERY:
Sl No
1

Description

Unit

Quantity
75.00
0.30
10.50

Quantity

Nil
( Manual mixing)
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3
4

UNIT :

Description

Mason Cl- II
Stone chiseller Cl- I
work inspector
mazdoor

0.00
0.00

Unit

Quantity

Day
Day
Day
Day
Total cost of Labour

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

1.00
4.00
0.50
2.00

10.00 sqm
Rate
in Rs.
4.00
606.00
300.00
Rs:

Amount
in Rs.
300.00
181.80
3150.00
3631.80

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
345.00
385.00
370.00
295.00
Rs:

Amount
in Rs.
345.00
1540.00
185.00
590.00
2660.00

Rs:
Rs:
Rs:
Rs:

3631.80
0.00
2660.00
6291.80
880.85
7172.65
717.30

266.00
0.14 37.20
303.20

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per sqm

10.00 sqm
(A+B+C+D)/10.0

Total
14.00% Rs:
Rs:
Rs.

272

Canal Cross Drainage Works - Item Unit Rates 2014-15

IRR-CCDW-5-3 Providing and fixing 10 cm thick two line dressed burnt stone slabs for coping set in
CM 1: 6 proportion by volume with pointing to joints in CM 1 : 3 proportion by volume including
cost of all materials, machinery, labour, finishing, curing etc., complete with initial lead upto
50 m and all lifts.
(Cement content: 7.5 kg / sqm, FA : 0.030 cum/sqm, Burnt stone slab 10 cm
thick 1.05 sqm/ sqm)
DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3

Particulars

Unit

Cement
Sand (Screened)
Burnt stone slab 10 cm thick
Total cost of Materials

kg
cum
sqm

B. MACHINERY:
Sl No
1

Description

Unit

Quantity
75.00
0.30
10.50

Quantity

Nil
( Manual mixing)
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3
4

UNIT :

Description

0.00
0.00

Unit

Mason Cl- II
Stone chiseller Cl-I
work inspector
mazdoor

Quantity

Day
Day
Day
Day

1.00
8.00
0.50
2.00

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

10.00 sqm
Rate
in Rs.
4.00
606.00
300.00
Rs:

Amount
in Rs.
300.00
181.80
3150.00
3631.80

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
345.00
385.00
370.00
295.00
Rs:

Amount
in Rs.
345.00
3080.00
185.00
590.00
4200.00

Rs:
Rs:
Rs:
Rs:

3631.80
0.00
4200.00
7831.80
1096.45
8928.25
892.80

420.00
0.14 58.80
478.80

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per sqm

10.00 sqm
(A+B+C+D)/10.0

Total
14.00% Rs:
Rs:
Rs.

IRR-CCDW-5-4 Providing and laying insitu M-15 ( 28 days cube compressive strength not less than 15 N /
sqmm ) grade cement concrete using 20 mm down size approved clean, hard, graded
aggregates for coping slab including cost of all materials, machinery, labour, formwork,
cleaning surface, batching, mixing, placing in position, levelling, compacting, finishing, curing
etc., complete with initial lead upto 50 m and initial lift upto 3 m.
(Cement content: 300 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6

UNIT :

Particulars

Unit

Cement for mix


Cement for incidentals @ 5 kg / cum
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
Fine aggregate (Un-Screened)
Super Plasticizer
Use rate of shuttering
Sundries
Total cost of Materials

kg
kg
cum
cum
cum
kg
sqm
sqm

Quantity
4401.00
73.35
7.63
4.11
6.60
17.60
80.69
1.00

14.67 cum
Rate
in Rs.
4.00
4.00
1210.00
875.00
462.00
80.00
244.56
41.00
Rs:

Amount
in Rs.
17604.00
293.40
9230.36
3594.15
3049.89
1408.32
19732.64
41.00
54953.77

273

Canal Cross Drainage Works - Item Unit Rates 2014-15

B. MACHINERY:
Sl No
1
2
3

Description

Unit

Concrete mixer 300/200 ltr ( diesel )


Fuel / Energy charges
5 hp pump ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Total hire charges of Machinery

Hour
Hour
Hour
Hour
Hour
Hour

C. LABOUR:
Sl No

Description

Unit

1
2
3
4
5
6

Crew for Concrete mixer


Crew for Pump
Crew for Water tanker
Mason Class-I
work inspector
mazdoor
for batching materials
for loading mortar pans
for laying and tamping
for conveying concrete
for cleaning/ washing/ curing
7
Labour cost for shuttering/scaffolding
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Quantity
8.00
8.00
0.50
0.50
1.00
1.00

Quantity

Hour
Hour
Hour
Day
Day

8.00
0.50
1.00
1.00
1.00

Day
Day
Day
Day
Day
sqm

11.00
4.00
3.00
14.67
1.00
80.69

Rate
in Rs.
53.50
85.30
10.20
85.30
402.50
322.20
Rs:

Amount
in Rs.
428.00
682.40
5.10
42.65
402.50
322.20
1882.85

Rate
in Rs.
189.80
96.10
153.10
385.00
370.00

Amount
in Rs.
1518.40
48.05
153.10
385.00
370.00

295.00
295.00
295.00
295.00
295.00
75.30
Rs:

3245.00
1180.00
885.00
4327.65
295.00
6075.58
18482.78

Rs:
Rs:
Rs:
Rs:

54953.77
1882.85
18482.78
75319.40
10544.72
85864.12
5853.00

1259.90
0.14 176.40
1436.30

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

Total
14.00% Rs:
14.67 cum
Rs:
(A+B+C+D)/14.67
Rs.

IRR-CCDW-5-5 Providing and constructing protective railing consisting of in-situ railing posts of size 15 x
15 cm at bottom, 10 x 10 cm at top and 75 cm height at 2 m centre to centre in M-20 grade
concrete using 20 mm down size graded aggregates and with each post reinforced by 4 Nos.
of 8 mm dia main bars embedded in kerb concrete for a depth of 40 cm and 5 Nos. of 6 mm
dia. stirrups including fixing 3 rows of 40 mm dia. GI pipes with one coat of red oxide primer
and two coats of synthetic enamel paint, cost of all materials, machinery, labour, formwork,
finishing, curing etc., complete with lead upto 50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
7
8

Particulars

Unit

Cement
20-10 mm coarse aggregate
10-4.75 mm coarse aggregate
Fine aggregate (Un-Screened)
Reinforcement steel
40 mm dia GI pipes B class
Use rate of shuttering
Sundries ( paints/ binding wire etc )
Total cost of Materials

kg
cum
cum
cum
kg
Rm
sqm
LS

B. MACHINERY:
Sl No
1

UNIT :

Description
Nill

Unit

Quantity
30.00
0.04
0.02
0.04
16.39
30.00
3.00
4.00

Quantity
0.00

10.00 Rm
Rate
in Rs.
4.00
1210.00
875.00
462.00
46.50
290.00
244.56
41.00
Rs:

Amount
in Rs.
120.00
48.40
17.50
18.48
762.14
8700.00
733.69
164.00
10564.21

Rate
in Rs.
0.00

Amount
in Rs.
0.00

274

Canal Cross Drainage Works - Item Unit Rates 2014-15

0.00

0.00
Rs:

0.00
0.00

Rate
in Rs.
385.00
450.00
370.00
295.00
345.00
345.00
Rs:

Amount
in Rs.
192.50
225.00
185.00
442.50
172.50
172.50
1390.00

Rs:
Rs:
Rs:
Rs:

10564.21
0.00
1390.00
11954.21
1673.59
13627.80
1362.80

Total hire charges of Machinery


C. LABOUR:
Sl No
1
2
3
4
5
6

Description

Unit

Mason Class I
Bar bender
work inspector
mazdoor
Painter Cl- II
Fitter shuttering

Quantity

Day
Day
Day
Day
Day
Day

0.50
0.50
0.50
1.50
0.50
0.50

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

139.00
0.14 19.50
158.50

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per Rm
IRR-CCDW-6

10.00 Rm
(A+B+C+D)/10.0

Total
14.00% Rs:
Rs:
Rs.

HUME PIPE LAYING & JOINTING WORKS :

IRR-CCDW-6-1 Laying and jointing 300 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2
proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,
labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto
50 m and all lifts.
(Cement content: 9.9 kg / joint, FA : 0.01cum/joint, Hemp Yarn : 0.091kg/joint)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3

Particulars

Cement
Sand (Screened)
Hemp yarn

UNIT :
Unit

Quantity

kg
cum
kg

99.00
0.10
0.91

Total cost of Materials


B. MACHINERY:
Sl No
1

Description

Quantity

Nill
( Manual mixing )
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3

Unit

Description

Mason Cl- II
work inspector
mazdoor

0.00
0.00

Unit

Quantity

Day
Day
Day
Total cost of Labour

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

2.00
1.00
3.00

10.00 Joints
Rate
in Rs.
4.00
606.00
72.00
Rs:

Amount
in Rs.
396.00
60.60
65.52
522.12

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
345.00
370.00
295.00
Rs:

Amount
in Rs.
690.00
370.00
885.00
1945.00

Rs:
Rs:
Rs:
Rs:

522.12
0.00
1945.00
2467.12

194.50
0.14 27.20
221.70

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total

275

Canal Cross Drainage Works - Item Unit Rates 2014-15

D. Add for contractor's profit and overheads on (A+B+C)


Total cost for
Rate per joint

14.00% Rs:
10.00 Joints
Rs:
(A+B+C+D)/10.0
Rs.

345.4
2812.52
281.30

(1) For NP3 Class - 10% extra over the rates of NP2 Class
(2) For NP4 Class - 20% extra over the rates of NP2 Class

Note:

IRR-CCDW-6-2 Laying and jointing 450 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2
proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,
labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto
50 m and all lifts.
(Cement content: 17.4 kg / joint, FA : 0.022cum/joint, Hemp Yarn : 0.127kg/joint)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3

Particulars

UNIT :
Unit

Cement
Sand (Screened)
Hemp yarn

Quantity

kg
cum
kg

174.00
0.22
1.27

Total cost of Materials


B. MACHINERY:
Sl No
1

Description

Quantity

Nill
( Manual mixing )
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3

Unit

Description

0.00
0.00

Unit

Mason Cl- II
work inspector
mazdoor

Quantity

Day
Day
Day

2.00
1.00
3.00

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

10.00 Joints
Rate
in Rs.
4.00
606.00
72.00
Rs:

Amount
in Rs.
696.00
133.32
91.44
920.76

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
345.00
370.00
295.00
Rs:

Amount
in Rs.
690.00
370.00
885.00
1945.00

Rs:
Rs:
Rs:
Rs:

920.76
0.00
1945.00
2865.76
401.21
3266.97
326.70

194.50
0.14 27.20
221.70

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per joint

Total
14.00% Rs:
10.00 Joints
Rs:
(A+B+C+D)/10.0
Rs.

(1) For NP3 Class - 10% extra over the rates of NP2 Class
(2) For NP4 Class - 20% extra over the rates of NP2 Class

Note:

IRR-CCDW-6-3 Laying and jointing 600 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2
proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,
labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto
50 m and all lifts.
(Cement content: 24.8 kg / joint, FA : 0.025cum/joint, Hemp Yarn : 0.22kg/joint)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3

Particulars

Cement
Sand (Screened)
Hemp yarn

UNIT :
Unit
kg
cum
kg

Total cost of Materials

Quantity
248.00
0.25
2.20

10.00 Joints
Rate
in Rs.
4.00
606.00
72.00
Rs:

Amount
in Rs.
992.00
151.50
158.40
1301.90

276

Canal Cross Drainage Works - Item Unit Rates 2014-15

B. MACHINERY:
Sl No
1

Description

Quantity

Nill
( Manual mixing )
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3

Unit

Description

0.00
0.00

Unit

Mason Cl- II
work inspector
mazdoor

Quantity

Day
Day
Day

2.50
1.00
4.00

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
345.00
370.00
295.00
Rs:

Amount
in Rs.
862.50
370.00
1180.00
2412.50

Rs:
Rs:
Rs:
Rs:

1301.90
0.00
2412.50
3714.40
520.02
4234.42
423.40

241.30
0.14 33.80
275.10

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per joint

Total
14.00% Rs:
10.00 Joints
Rs:
(A+B+C+D)/10.0
Rs.

(1) For NP3 Class - 10% extra over the rates of NP2 Class
(2) For NP4 Class - 20% extra over the rates of NP2 Class

Note:

IRR-CCDW-6-4 Laying and jointing 700 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2
proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,
labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto
50 m and all lifts.
(Cement content: 32.1 kg / joint, FA : 0.031cum/joint, Hemp Yarn : 0.25kg/joint)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3

Particulars

Cement
Sand (Screened)
Hemp yarn

UNIT :
Unit

Quantity

kg
cum
kg

321.00
0.31
2.50

Total cost of Materials


B. MACHINERY:
Sl No
1

Description

Quantity

Nill
( Manual mixing )
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3

Unit

Description

Mason Cl- II
work inspector
mazdoor

0.00
0.00

Unit

Quantity

Day
Day
Day
Total cost of Labour

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery

2.50
1.00
4.00

10.00 Joints
Rate
in Rs.
4.00
606.00
72.00
Rs:

Amount
in Rs.
1284.00
187.86
180.00
1651.86

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
345.00
370.00
295.00
Rs:

Amount
in Rs.
862.50
370.00
1180.00
2412.50

Rs:
Rs:

1651.86
0.00

241.30
0.14 33.80
275.10

277

Canal Cross Drainage Works - Item Unit Rates 2014-15

C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per joint

Rs:
Rs:

Total
14.00% Rs:
10.00 Joints
Rs:
(A+B+C+D)/10.0
Rs.

2412.50
4064.36
569.01
4633.37
463.30

(1) For NP3 Class - 10% extra over the rates of NP2 Class
(2) For NP4 Class - 20% extra over the rates of NP2 Class

Note:

IRR-CCDW-6-5 Laying and jointing 800 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2
proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,
labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto
50 m and all lifts.
(Cement content: 39.6 kg / joint, FA : 0.039cum/joint, Hemp Yarn : 0.31kg/joint)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3

Particulars

UNIT :
Unit

Cement
Sand (Screened)
Hemp yarn

Quantity

kg
cum
kg

396.00
0.39
3.10

Total cost of Materials


B. MACHINERY:
Sl No
1

Description

Quantity

Nill
( Manual mixing )
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3

Unit

Description

0.00
0.00

Unit

Mason Cl- II
work inspector
mazdoor

Quantity

Day
Day
Day

3.00
1.00
5.00

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

10.00 Joints
Rate
in Rs.
4.00
606.00
72.00
Rs:

Amount
in Rs.
1584.00
236.34
223.20
2043.54

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
345.00
370.00
295.00
Rs:

Amount
in Rs.
1035.00
370.00
1475.00
2880.00

Rs:
Rs:
Rs:
Rs:

2043.54
0.00
2880.00
4923.54
689.3
5612.84
561.30

288.00
0.14 40.30
328.30

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per joint

Total
14.00% Rs:
10.00 Joints
Rs:
(A+B+C+D)/10.0
Rs.

(1) For NP3 Class - 10% extra over the rates of NP2 Class
(2) For NP4 Class - 20% extra over the rates of NP2 Class

Note:

IRR-CCDW-6-6 Laying and jointing 900 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2
proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,
labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto
50 m and all lifts.
(Cement content: 44.6 kg / joint, FA : 0.045cum/joint, Hemp Yarn : 0.34kg/joint)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

Cement
Sand (Screened)

Particulars

UNIT :
Unit
kg
cum

Quantity
446.00
0.45

10.00 Joints
Rate
in Rs.
4.00
606.00

Amount
in Rs.
1784.00
272.70

278

Canal Cross Drainage Works - Item Unit Rates 2014-15

Hemp yarn

kg

3.40

72.00
Rs:

244.80
2301.50

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
345.00
370.00
295.00
Rs:

Amount
in Rs.
1035.00
370.00
1475.00
2880.00

Rs:
Rs:
Rs:
Rs:

2301.50
0.00
2880.00
5181.50
725.41
5906.91
590.70

Total cost of Materials


B. MACHINERY:
Sl No
1

Description

Quantity

Nill
( Manual mixing )
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3

Unit

Description

0.00
0.00

Unit

Mason Cl- II
work inspector
mazdoor

Quantity

Day
Day
Day

3.00
1.00
5.00

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

288.00
0.14 40.30
328.30

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per joint

Total
14.00% Rs:
10.00 Joints
Rs:
(A+B+C+D)/10.0
Rs.

(1) For NP3 Class - 10% extra over the rates of NP2 Class
(2) For NP4 Class - 20% extra over the rates of NP2 Class

Note:

IRR-CCDW-6-7 Laying and jointing 1000 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2
proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,
labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto
50 m and all lifts.
(Cement content: 49.5 kg / joint, FA : 0.05cum/joint, Hemp Yarn : 0.377kg/joint)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3

Particulars

Cement
Sand (Screened)
Hemp yarn

UNIT :
Unit

Quantity

kg
cum
kg

495.00
0.50
3.77

Total cost of Materials


B. MACHINERY:
Sl No
1

Unit

Quantity

Nill
( Manual mixing )
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3

Description

Description

Mason Cl- II
work inspector
mazdoor

0.00
0.00

Unit

Quantity

Day
Day
Day
Total cost of Labour

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

3.00
1.00
6.00

10.00 Joints
Rate
in Rs.
4.00
606.00
72.00
Rs:

Amount
in Rs.
1980.00
303.00
271.44
2554.44

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
345.00
370.00
295.00
Rs:

Amount
in Rs.
1035.00
370.00
1770.00
3175.00

317.50
0.14 44.50
362.00

ABSTRACT:

279

Canal Cross Drainage Works - Item Unit Rates 2014-15

A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per joint

Rs:
Rs:
Rs:
Rs:

Total
14.00% Rs:
10.00 Joints
Rs:
(A+B+C+D)/10.0
Rs.

2554.44
0.00
3175.00
5729.44
802.12
6531.56
653.20

(1) For NP3 Class - 10% extra over the rates of NP2 Class
(2) For NP4 Class - 20% extra over the rates of NP2 Class

Note:

IRR-CCDW-6-8 Laying and jointing 1100 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2
proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,
labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto
50 m and all lifts.
(Cement content: 56.9 kg / joint, FA : 0.058cum/joint, Hemp Yarn : 0.415kg/joint)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3

Particulars

UNIT :
Unit

Cement
Sand (Screened)
Hemp yarn

Quantity

kg
cum
kg

569.00
0.58
4.15

Total cost of Materials


B. MACHINERY:
Sl No
1

Description

Quantity

Nill
( Manual mixing )
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3

Unit

Description

0.00
0.00

Unit

Mason Cl- II
work inspector
mazdoor

Quantity

Day
Day
Day

3.00
1.00
6.00

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

10.00 Joints
Rate
in Rs.
4.00
606.00
72.00
Rs:

Amount
in Rs.
2276.00
351.48
298.80
2926.28

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
345.00
370.00
295.00
Rs:

Amount
in Rs.
1035.00
370.00
1770.00
3175.00

Rs:
Rs:
Rs:
Rs:

2926.28
0.00
3175.00
6101.28
854.18
6955.46
695.50

317.50
0.14 44.50
362.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per joint

Total
14.00% Rs:
10.00 Joints
Rs:
(A+B+C+D)/10.0
Rs.

(1) For NP3 Class - 10% extra over the rates of NP2 Class
(2) For NP4 Class - 20% extra over the rates of NP2 Class

Note:

IRR-CCDW-6-9 Laying and jointing 1200 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2
proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,
labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto
50 m and all lifts.
(Cement content: 66.8 kg / joint, FA : 0.069cum/joint, Hemp Yarn : 0.453kg/joint)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

Particulars

UNIT :
Unit

Quantity

10.00 Joints
Rate
in Rs.

Amount
in Rs.

280

Canal Cross Drainage Works - Item Unit Rates 2014-15

1
2
3

Cement
Sand (Screened)
Hemp yarn

kg
cum
kg

668.00
0.69
4.53

4.00
606.00
72.00
Rs:

2672.00
418.14
326.16
3416.30

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
345.00
370.00
295.00
Rs:

Amount
in Rs.
1380.00
370.00
2065.00
3815.00

Rs:
Rs:
Rs:
Rs:

3416.30
0.00
3815.00
7231.30
1012.38
8243.68
824.40

Total cost of Materials


B. MACHINERY:
Sl No
1

Description

Quantity

Nill
( Manual mixing )
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3

Unit

Description

0.00
0.00

Unit

Mason Cl- II
work inspector
mazdoor

Quantity

Day
Day
Day

4.00
1.00
7.00

Total cost of Labour


labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

381.50
0.14 53.40
434.90

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per joint

Total
14.00% Rs:
10.00 Joints
Rs:
(A+B+C+D)/10.0
Rs.

(1) For NP3 Class - 10% extra over the rates of NP2 Class
(2) For NP4 Class - 20% extra over the rates of NP2 Class

Note:

IRR-CCDW-7

BACK FILLING & OTHER WORKS :

IRR-CCDW-7-1 Providing rubble / boulder and sand filling behind abutment and return walls in layers
including cost of all materials, machinery, labour, watering, ramming etc., complete with initial
lead upto 50 m and initial lift upto 3 m.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

Particulars

Rubble / Boulder
Sand for filling

UNIT :
Unit

Quantity

cum
cum

10.00
4.00

Total cost of Materials


B. MACHINERY:
Sl No
1

Unit

Quantity

Nill
( Manual mixing )
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3

Description

Description

work inspector
Mason Cl II
mazdoor

0.00
0.00

Unit

Quantity

Day
Day
Day
Total cost of Labour

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

0.50
1.00
4.00

10.00 cum
Rate
in Rs.
318.00
342.00
Rs:

Amount
in Rs.
3180.00
1368.00
4548.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
370.00
345.00
295.00
Rs:

Amount
in Rs.
185.00
345.00
1180.00
1710.00

171.00
0.14 23.90
194.90

281

Canal Cross Drainage Works - Item Unit Rates 2014-15

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

10.00 cum
(A+B+C+D)/10.0

Total
14.00% Rs:
Rs:
Rs.

Rs:
Rs:
Rs:
Rs:

4548.00
0.00
1710.00
6258.00
876.12
7134.12
713.40

IRR-CCDW-7-2 Providing and filling murrum / gravely soil ( CNS soil ) for foundation or around pipes
including breaking clods, spreading in layers of 10 to 15 cm, watering, compaction by earth
masters to achieve density control of not less than 95 percent etc., complete with lead
upto 50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

Particulars

UNIT :
Unit

Murum

Quantity

cum

12.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No

Description

Unit

Quantity

Nill

0.00
0.00

Total hire charges of Machinery


C. LABOUR:
Sl No

Description

Unit

1
2
3

Cartman with double bullock cart


work inspector
mazdoor
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Quantity

Day
Day
Day

0.50
0.50
6.00

10.00 cum
Rate
in Rs.
107.00
0.00
Rs:

Amount
in Rs.
1284.00
0.00
1284.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
395.00
370.00
295.00
Rs:

Amount
in Rs.
197.50
185.00
1770.00
2152.50

Rs:
Rs:
Rs:
Rs:

1284.00
0.00
2152.50
3436.50
481.11
3917.61
391.80

215.30
0.14 30.10
245.40

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

10.00 cum
(A+B+C+D)/10.0

Total
14.00% Rs:
Rs:
Rs.

IRR-CCDW-7-3 Providing and filling murum / gravely soil ( CNS soil ) for foundation or above pipes
including breaking clods, spreading in layers of 10 to 15 cm, watering, compaction by power
roller to achieve density control of not less than 98 percent etc., complete with lead upto
50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

Particulars

Murum

UNIT :
Unit
cum

Quantity
12.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No

Description

Unit

Quantity

10.00 cum
Rate
in Rs.
107.00
0.00
Rs:

Amount
in Rs.
1284.00
0.00
1284.00

Rate

Amount

282

Canal Cross Drainage Works - Item Unit Rates 2014-15

Diesel road roller 8-10 tonne


Fuel / Energy charges
Total hire charges of Machinery

C. LABOUR:
Sl No

Description

Hour
Hour

Unit

1
2
3
4

Operator road roller


Cartman with double bullock cart
work inspector
mazdoor
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

0.17
0.17

Quantity

Hour
Day
Day
Day

0.17
0.50
0.50
1.50

in Rs.
197.20
767.30
Rs:

in Rs.
33.65
130.94
164.59

Rate
in Rs.
182.20
395.00
370.00
295.00
Rs:

Amount
in Rs.
31.09
197.50
185.00
442.50
856.09

Rs:
Rs:
Rs:
Rs:

1284.00
164.59
856.09
2304.68
322.66
2627.34
262.70

85.60
0.14 12.00
97.60

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum

10.00 cum
(A+B+C+D)/10.0

Total
14.00% Rs:
Rs:
Rs.

IRR-CCDW-7-4 Providing and fixing one line dressed 111x35x25 cm thick IRC standard kilometre stone in
cement concrete M-10 grade with 40 mm down size aggregates including excavating pit of
size 70x45x40 cm, embedding the stone by 30 cm in concrete, providing 2 coats synthetic
enamel paint of approved quality and colour to exposed surfaces and lettering as directed, cost
of all materials, labour, finishing, curing etc., complete with initial lead upto 50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
7
8

Particulars

Unit

One line dressed Km stone


40-20 mm coarse aggregate
20-10 mm coarse aggregate
10-4.75 mm coarse aggregate
Sand (Un-Screened)
Cement
Synthetic enamel paint I st quality
Sundries ( brush / oil etc )
Total cost of Materials

No.
cum
cum
cum
cum
kg
ltr
LS

B. MACHINERY:
Sl No
1

Description

Unit

Quantity
4.00
0.20
0.15
0.10
0.20
100.00
1.00
4.00

Quantity

NIL
( Manual mixing )
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3
4

UNIT :

Description

Mason Cl- II
work inspector
mazdoor
Painter Cl- I

0.00
0.00

Unit

Quantity

Day
Day
Day
Day
Total cost of Labour

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
ABSTRACT:
A. Cost of Materials

1.00
1.00
1.00
1.00

4 Nos.
Rate
in Rs.
450.00
1145.00
1210.00
875.00
462.00
4.00
240.00
41.00
Rs:

Amount
in Rs.
1800.00
229.00
181.50
87.50
92.40
400.00
240.00
164.00
3194.40

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
345.00
370.00
295.00
440.00
Rs:

Amount
in Rs.
345.00
370.00
295.00
440.00
1450.00

Rs:

3194.40

362.50
0.14 50.80
413.30

283

Canal Cross Drainage Works - Item Unit Rates 2014-15

B. Hire charges of Machinery


C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per No.

4.00 Nos.
(A+B+C+D)/4.0

Total
14.00% Rs:
Rs:
Rs.

Rs:
Rs:
Rs:

0.00
1450.00
4644.40
650.22
5294.62
1323.70

IRR-CCDW-7-5 Providing and fixing one line dressed 65x15x10 cm thick IRC standard hectometre stone in
cement concrete M-10 grade with 40 mm down size aggregates including excavating pit of
size 50x45x40 cm, embedding the stone by 30 cm in concrete, providing 2 coats synthetic
enamel paint of approved quality and colour to exposed surfaces and lettering as directed, cost
of all materials, labour, finishing, curing etc., complete with initial lead upto 50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

Particulars

1
2
3
4
5
6
7
8

One line dressed hectometre stone


40-20 mm coarse aggregate
20-10 mm coarse aggregate
10-4.75 mm coarse aggregate
Sand (Un-Screened)
Cement
Synthetic enamel paint I st quality
Sundries ( brush / oil etc )
Total cost of Materials
B. MACHINERY:
Sl No
Description
1

Unit

Quantity

No.
cum
cum
cum
cum
kg
ltr
LS

Unit

4.00
0.20
0.15
0.10
0.20
100.00
0.40
1.00

Quantity

NIL
( Manual mixing )
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3
4

UNIT :

Description

Mason Cl- II
work inspector
mazdoor
Painter Cl- I

0.00
0.00

Unit

Quantity

Day
Day
Day
Day
Total cost of Labour

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per No.

1.00
1.00
1.00
0.50

4 Nos.
Rate
in Rs.
240.00
1145.00
1210.00
875.00
462.00
4.00
240.00
41.00
Rs:

Amount
in Rs.
960.00
229.00
181.50
87.50
92.40
400.00
96.00
41.00
2087.40

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
345.00
370.00
295.00
440.00
Rs:

Amount
in Rs.
345.00
370.00
295.00
220.00
1230.00

Rs:
Rs:
Rs:
Rs:

2087.40
0.00
1230.00
3317.40
464.44
3781.84
945.50

307.50
0.14 43.10
350.60

4.00 Nos.
(A+B+C+D)/4.0

Total
14.00% Rs:
Rs:
Rs.

284

Gates and Allied Works - Item Unit Rates 2014-15

CHAPTER-V
HYDRAULIC GATES AND ALLIED EQUIPMENT - Standard Data

(WLL BE WITH E-N-C & TO INCORPORATE CHANGES YEARLY/ AS NEEDED)


FOR THE YEAR :

2014-15

GATE HOIST AND ALLIED WORKS - DATA RATES

IRR-GAW
1

All materials / bought out components for embedded parts, gates, hoists and allied works
shall conform to relevant Indian standards / technical specifications and approved drawings.

The basic rates are EXCLUSIVEof preparation of designs / drawings / material schedules etc.,
as per specifications and other technical data including revisions.
If designs &drawings are to be done by private agency 2% of estimated cost be added

The basic rates are inclusive of cost of all materials, machinery, labour, fabrication, erection,
commissioning and testing of gates, hoists and other related components as per technical
specifications.

The basic rates are inclusive of finishing, wastage of materials , incidental works, temperary
supports, all enabling works, profit, overheads, small tools / plants, hidden cost
on labour etc.

The basic rates are inclusive of taxes, duties (excise ), levies and all other incidental charges including
turn over tax/sales tax on works contract. Separate provision shall be made in the estimate towards such
tax on works contract at the rate prevailing at the time of preparation of estimate.

The basic rates are inclusive of all leads and lifts including rehandling.

no provision is made for stitch welding and it is part of welding work

The basic rates are inclusive of preparatory works such as rectification of damages, repairing
shop painting, cleaning, positioning and anchoring first stage embedments,

The basic rates are not inclusive of painting with or without sand blasting,and are to be added to the rate as
perschedule rates formulated in the same chapter as per applicability and specifications

10

The basic rates are exclusive of cost of river diversion arrangements, dewatering, desilting ,secondary concreting
of EM parts etc., which form part of civil works.

11

DESIGNS AND DRAWING CHARGES AT 2% BE ADDED EXTRA TO THE ESTIMATES, IF CONTRACTOR'S


SCOPE OF WORK INVOLVES DESIGNS COMPONENT ALSO

12

Add AREA ALLOWANCES AS APPLICABLE ON LABOUR COMPONENT ONLY ( SHOWN UNDER EACH ITEM)

13

Add contractors profit and overheads at 14% to all items

14

Painting Charges added extra to the data items as per applicability wherver necessary

15

HOIST EQUIPMENT1.-where sand blasting is not possible, hand and power tool cleaning be
adopted - Guidance may be taken from Mechanical workshop in this regard
2. Machined surfaces should not be painted
3. for maintenance unless sand blasting is essential hand and power tool cleaning be adopted
Painting of Hoast Gates is to be done as per IS 14177:1994

16

DATA and RATES

---GATE / HOIST AND ALLIED WORKS -

(STORED WITH E-N-C &TO INCORPORATE CHANGES YEARLY/AS NEEDED)


GAW - Work Items
Index- code
IRR-GAW

TYPES OF GATES:

IRR-GAW-1
A. SPILLWAY RADIAL GATES
IRR-GAW-1-1 E.M Parts and anchorages
fabrication, supply, erection, testing and commissioning of Embedded parts for radial gate
consists of sill beam, wall plates, anchor girders , yoke girders, tie flats, trunnion supports etc., including

285

Gates and Allied Works - Item Unit Rates 2014-15

cost of all materials, machinery, labour, welding, finishing, with leads and lifts &all accessories
(without painting on sand-blasted or mechanical cleaning surfaces which are added extra
as perscedule of rates under itemsinthis chapter and add as applicable separately)
Drawing no. MD/CDO/VRSP/90-92/85-86 (Vengalaraya Sagar - Gomukhi Project)
Vent Size:

DATA:

RATE ANALYSIS
Sl No
1
2
3
4
5
6
7
8
9
10
11
12

A. MATERIALS:
particulars
Str steel angle / beam / channel / bars
Structural steel plate / flats
Stainless steel plate / flats
MS bolts and nuts
Oxygen gas
Acetyline gas
Welding electrodes
Welding electrodes ( LH )
Welding electrodes ( stainless steel )
Use rate welding holder set
Use rate gas cutting torch set
Sundries

B. MACHINERY:
Sl No
1

2
3
4
5
6
7
8
9
10
11

Welding transformer
Fuel / Energy charges
Tower crane/heavy duty tyre mounted
crane
Fuel / Energy charges
Plate shearing machine
Fuel / Energy charges
Pug cutting machine
Fuel / Energy charges
Mobile crane 16 Tonnes
Fuel / Energy charges
Stationery derric crane
Fuel / Energy charges
Grinding machine
Fuel / Energy charges
Drilling machines
Fuel / Energy charges
Planing machine
Fuel / Energy charges
Bending Machine
Fuel / Energy charges
Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3
4
5
6
7
8
9
10
11
12

Description

Description

Crew for Tower crane


Crew for Mobile crane 16 T
Crew for Shearing machine
Crew for Planing machine
Crew for Drilling machine
Crew for Grinding machine
Crew for Bending machine
Foreman
Marker / Fabricator / Erector
Gas cutter
Welder ( General )
Welder ( X - ray )

Unit

UNIT :
Quantity

kg
3467.00
kg
11261.00
kg
515.00
kg
48.00
cum
158.00
cum
53.00
Nos
11520.00
Nos
2880.00
Nos
1160.00
Hour
1945.00
Hour
158.00
LS
100.00
Total cost of Materials

Unit

Quantity

Hour
Hour

1945.00
1945.00

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

16.00
16.00
16.00
16.00
76.00
76.00
22.00
22.00
64.00
64.00
30.00
30.00
30.00
30.00
100.00
100.00
30.00
30.00
100.00

Unit
Hour
Hour
Hour
Hour
Hour
Hour
Day
Day
Day
Day
Day

Quantity
16.00
22.00
16.00
100.00
30.00
30.00
30.00
15.00
75.00
20.00
212.00
48.00

12.00 X 6.6 Mtrs

15.300 tonne
Rate
in Rs.
45.00
46.00
275.00
90.00
52.00
320.00
11.00
18.00
26.00
7.35
23.67
41.00
Rs:

Amount
in Rs.
156015.00
518006.00
141625.00
4320.00
8216.00
16960.00
126720.00
51840.00
30160.00
14295.75
3740.12
4100.00
1075997.87

Rate
in Rs.
16.00
91.30

Amount
in Rs.
31120.00
177578.50

867.10
197.80
41.90
152.20
6.40
3.80
2278.10
75.00
86.10
0.00
22.50
38.00
22.50
38.00
117.80
114.10
42.60
114.10
41.00
Rs:

13873.60
3164.80
670.40
2435.20
486.40
288.80
50118.20
1650.00
5510.40
0.00
675.00
1140.00
675.00
1140.00
11780.00
11410.00
1278.00
3423.00
4100.00
322517.30

Rate
in Rs.
163.30
454.30
122.50
182.20
171.60
171.60
113.90
440.00
440.00
385.00
385.00
440.00

Amount
in Rs.
2612.80
9994.60
1960.00
18220.00
5148.00
5148.00
3417.00
6600.00
33000.00
7700.00
81620.00
21120.00

286

Gates and Allied Works - Item Unit Rates 2014-15

13
14
15

Khalasi
Helper fabrication / erection
Electrician

Day
345.00
Day
255.00
Day
5.00
Total cost of Labour
Add towards highly skilled labour charges @ 30% on total cost of labour
Total Cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

385.00
345.00
440.00
Rs:

132825.00
87975.00
2200.00
419540.40
125862.12
545402.52

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

1075997.87
322517.30
545402.52
1943917.69
0.00
1943917.69
58317.53
2002235.22
280312.93

35647.20
0.14 4990.60
40637.80

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0.00%
Total
3%

D.Add for excise duty


(on 75 percent cost excluding cost of materials)
E. Add for transportation upto work site @
Total
F. Add for contractor's profit and overheads on
Add 2 leads
Add 1 km lead charges for fabricated parts
Unloading charges of fabricated parts Rs
Total cost for

14%
R

19.00 per tonne


63.30 per tonne

581.4
1936.98
Rs:
2285066.54
Rs:
149350.80

15.300 tonne
Rate per tonne

RADIAL GATES
A-2
Gates
IRR-GAW-1-2 fabrication, supply, erection, testing and commissioning of radial gate consisting
of skin plate, stiffeners, horizontal girders, radial arms, trunnion assemblies, tie beam, pulley
supports, bracings, rubber seals, clamps etc., with all accessories for spillway/canals including cost
of all materials, machinery, labour, seal fixing etc., complete as per specifications and approved drawings
(without painting on sand-blasted or mechanical cleaning surfaces which are added extra
as perscedule of rates under itemsinthis chapter and add as applicable separately)
Drawing no. MD/CDO/VRSP/170-172/85-86(Vengalaraya Sagar - Gomukhi Project)
Vent Size: 12 X 6.6 Mtr
DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

3
4
5
6

7
8
9
10
11
12
13

particulars

Structural steel :
Angles / beams / channels / bars
Plates / flats
Cast steel components :
Trunnion hubs / Guide rollers
Alluminium / Bronze alloy
components :
Bush for Trunnion / Guide roller
Bolt / Nut / Washer :
GI bolts / nuts / washers
Zinc/Babbit Metal
Rubber seals :
Bottom seal
Side seals ( Z - type )
Oxygen gas
Acetyline gas
Welding electrodes ( std )
Welding electrodes ( LH )
Use rate welding holder set
Use rate gas cutting torch set
Sundries

UNIT :
Unit

Quantity

29.000 tonne
Rate
in Rs.

Amount
in Rs.

kg
kg

9700.00
16850.00

45.00
46.00

436500.00
775100.00

kg

2100.00

180.00

378000.00

kg

350.00

912.00

319200.00

kg
kg

250.00
50.00

130.00
170.00

32500.00
8500.00

Rm
12.00
Rm
14.00
cum
228.00
cum
76.00
Nos
1000.00
Nos
250.00
Hour
156.00
Hour
228.00
LS
500.00
Total cost of Materials

759.00
1457.00
52.00
320.00
11.00
18.00
7.35
23.67
41.00
Rs:

9108.00
20398.00
11856.00
24320.00
11000.00
4500.00
1146.60
5397.14
20500.00
2058025.74

287

Gates and Allied Works - Item Unit Rates 2014-15

B. MACHINERY:
Sl No
1
2
3
4
5
6
7
8
9
10
11

Unit

Welding transformer
Fuel / Energy charges
Plate shearing machine
Fuel / Energy charges
Pug cutting machine
Fuel / Energy charges
Bending machine
Fuel / Energy charges
Tower crane 5 t cpacity
Fuel / Energy charges
Mobile derric crane
Fuel / Energy charges
Stationery derric crane
Fuel / Energy charges
Grinding machine
Fuel / Energy charges
Drilling machines
Fuel / Energy charges
Mobile Crane 30 T
Fuel / Energy charges
Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3
4
5
6
7
8
9
10
11
12
13

Description

Quantity

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Description

156.00
156.00
29.00
29.00
114.00
114.00
116.00
116.00
29.00
29.00
58.00
58.00
58.00
58.00
58.00
58.00
58.00
58.00
100.00
100.00
500.00

Unit

Quantity

Crew for Mobile crane 30T


Crew for Tower crane
Crew for Bending machine
Crew for Drilling machine
Crew for Grinding machine
Foreman
Marker / Fabricator / Erector
Gas cutter
Welder ( General )
Welder ( X - ray )
Khalasi
Helper fabrication / erection
Electrician

Hour
100.00
Hour
29.00
Hour
116.00
Hour
58.00
Hour
58.00
Day
29.00
Day
145.00
Day
29.00
Day
17.00
Day
5.00
Day
493.00
Day
667.00
Day
15.00
Total cost of Labour
Add towards highly skilled labour charges @ 30% on total cost of labour
Total Cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Rate
in Rs.
16.00
91.30
41.90
152.20
6.40
3.80
42.60
114.10
867.10
197.80
519.70
322.20
86.10
0.00
22.50
38.00
22.50
38.00
3096.80
118.80
41.00
Rs:

Amount
in Rs.
2496.00
14242.80
1215.10
4413.80
729.60
433.20
4941.60
13235.60
25145.90
5736.20
30142.60
18687.60
4993.80
0.00
1305.00
2204.00
1305.00
2204.00
309680.00
11880.00
20500.00
475491.80

Rate
in Rs.
454.30
163.30
113.90
171.60
171.60
440.00
440.00
385.00
385.00
440.00
385.00
345.00
440.00
Rs:

Amount
in Rs.
45430.00
4735.70
13212.40
9952.80
9952.80
12760.00
63800.00
11165.00
6545.00
2200.00
189805.00
230115.00
6600.00
606273.70
181882.11
788155.81

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

2058025.74
475491.80
788155.81
3321673.35
0.00
3321673.35
99650.20
3421323.55
478985.30

27177.80
0.14 3804.90
30982.70

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0.00%
Total
3%

D. Add for excise duty


(on 75 percent cost excluding cost of materials)
E. Add for transportation upto work site @
Total

F. Add for contractor's profit and overheads on (A+B


14%
Add 2 leads
Add 1 km lead charges for fabricated parts
R
19.00 per tonne
Unloading charges of fabricated parts Rs
63.30 per tonne
Total cost for
29.000 tonne
Rate per
tonne

IRR-GAW-1-3 RADIAL GATES-ROPE DRUM HOISTS

1102
3671.4
Rs:
3905082.25
Rs.
134658.00

WITH HOIST BRIDGES

288

Gates and Allied Works - Item Unit Rates 2014-15

fabrication, supply, erection, testing and commissioning of electrically operated rope


drum hoist of adequate capacity consisting of base frames, rope drums,connecting shaft, gear
system, brake system, electric motor, wire ropes, gate position indicator, manual operation
arrangement etc., with all accessories for spillway radial gate including cost of all materials,
machinery, labour,, greasing, providing hand railing and approach staircase with gate to hoist platform,
, complete as per specifications and approved drawings
(without painting on sand-blasted or mechanical cleaning surfaces which are added extra
as perscedule of rates under itemsinthis chapter and add as applicable separately)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21

Structural steel
Angles / beams / channels / bars
Plates / flats
Cast steel components :
Rope drums 2 Nos / Gears 4 Nos
Pinions
Pulleys 720 PCD 6 Nos
Plummer blocks / Hubs
Alloy steel components
Shafts
Pins
Bronze alloy components :
Bronze bearings / bush
Wire rope 36 mm dia 6/37
construction
MS Bolt / Nut / Washer
Worm reducers
Electric motor 20 hp
Floating shaft 300 mm dia
Manual operating system
Gate position indicator
Ele-magnetic brake
Electric cable / switch / control panel
etc
Oxygen gas
Acetyline gas
Welding electrodes
Welding electrodes ( LH )
Grease
Use rate welding holder set
Use rate gas cutting torch set
Sundries ( hand rail /staircase / gate et

B. MACHINERY:
Sl No
1
2
3
4
5
6
7

particulars

Description

Welding transformer
Fuel / Energy charges
Tower crane 5 t capacity
Fuel / Energy charges
Pug cutting machine
Fuel / Energy charges
Mobile derric crane
Fuel / Energy charges
Grinding machine
Fuel / Energy charges
Drilling machines
Fuel / Energy charges
Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No

Description

UNIT :
Unit

Quantity

15.440 tonne wt
90.00 t capacity
Rate
Amount
in Rs.
in Rs.

kg
kg

2571.00
3632.00

45.00
46.00

115695.00
167072.00

kg
kg
kg
kg

3680.00
218.00
1080.00
322.00

220.00
210.00
180.00
180.00

809600.00
45780.00
194400.00
57960.00

kg
kg

557.00
546.00

210.00
420.00

116970.00
229320.00

kg

144.00

912.00

131328.00

kg
kg
No.
No.
kg
No.
No.
No.

448.00
85.00
1.00
1.00
1000.00
1.00
1.00
1.00

250.00
90.00
224400.00
121000.00
180.00
28820.00
195800.00
35200.00

112000.00
7650.00
224400.00
121000.00
180000.00
28820.00
195800.00
35200.00

LS
1.00
cum
213.00
cum
71.00
Nos
530.00
Nos
4776.00
kg
50.00
Hour
566.00
Hour
90.00
LS
200.00
Total cost of Materials

50380.00
52.00
320.00
11.00
18.00
260.00
7.35
23.67
41.00
Rs:

50380.00
11076.00
22720.00
5830.00
85968.00
13000.00
4160.10
2130.45
8200.00
2976459.55

Rate
in Rs.
16.00
91.30
867.10
197.80
6.40
3.80
519.70
322.20
22.50
38.00
22.50
38.00
41.00
Rs:

Amount
in Rs.
9056.00
32228.90
3468.40
791.20
339.20
201.40
25985.00
16110.00
180.00
304.00
360.00
608.00
4100.00
93732.10

Rate
in Rs.

Amount
in Rs.

Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Unit

Quantity
566.00
353.00
4.00
4.00
53.00
53.00
50.00
50.00
8.00
8.00
16.00
16.00
100.00

Quantity

289

Gates and Allied Works - Item Unit Rates 2014-15

1
2
3
4
5

50.00
4.00
16.00
8.00
35.00

153.10
163.30
171.60
171.60
440.00

7655.00
653.20
2745.60
1372.80
15400.00

Day
58.00
Day
18.00
Day
53.00
Day
20.00
Day
175.00
Day
3.00
Total cost of Labour
Add towards highly skilled labour charges @ 30% on total cost of labour
Total Cost of Labour

440.00
385.00
385.00
385.00
345.00
440.00
Rs:

25520.00
6930.00
20405.00
7700.00
60375.00
1320.00
150076.60
45022.98
195099.58

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

2976459.55
93732.10
195099.58
3265291.23
0.00
3265291.23
97958.74
3363249.97
470855.00

6
7
8
9
10
11

Crew for Mobile crane


Crew for Tower crane
Crew for Drilling machine
Crew for Grinding machine
Foreman
Marker / Fabricator / Erector /
Mechanic
Gas cutter
Welder ( General )
Khalasi
Helper fabrication / erection
Electrician

Hour
Hour
Hour
Hour
Day

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

2167.80
0.14 303.50
2471.30

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0.00%
Total
3%

D. Add for excise duty


(on 75 percent cost excluding cost of materials)
E. Add for transportation upto work site @
Total
F. Add for contractor's profit and overheads on (A+B
Add 2 leads
Add 1 km lead charges for fabricated parts
Unloading charges of fabricated parts Rs
Total cost for
Total cost for

14%
R

19.00 per tonne


586.72
63.30 per tonne
1954.704
15.440 tonne wt
Rs:
3836646.39
90.00 t capacity
Rs:
Rate per tonne wt
Rs:
248487.50
Rate per tonne capacity of hoist
42629.40

IRR-GAW-1-4 Walk way(cat walk)


fabrication, supply, erection and commissioning of 1 metre wide walkway connecting
spillway piers / abutments at trunnion platform level including cost of all materials,
machinery, labour, cutting, welding etc, complete as per specifications and approved drawings
(without painting on sand-blasted or mechanical cleaning surfaces which are added extra
as perscedule of rates under itemsinthis chapter and add as applicable separately)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

2
3
4
5
6
7
8

Structural steel
Angles / beams / channels / bars
Plates / flats
Chequered plates
MS bolts / nuts / washers
Oxygen gas
Acetyline gas
Welding electrodes
Use rate welding holder set
Use rate gas cutting torch set
Sundries

B. MACHINERY:
Sl No
1

particulars

Description

Welding transformer

UNIT :
Unit

Quantity

kg
4258.00
kg
98.00
kg
856.00
kg
8.00
cum
51.00
cum
17.00
Nos
1195.00
Hour
150.00
Hour
30.00
LS
10.00
Total cost of Materials

Unit
Hour

Quantity
150.00

5.22 MT
Rate
in Rs.

Amount
in Rs.

45.00
46.00
60.00
90.00
52.00
320.00
11.00
7.35
23.67
41.00
Rs:

191610.00
4508.00
51360.00
720.00
2652.00
5440.00
13145.00
1102.50
710.15
410.00
271657.65

Rate
in Rs.
16.00

Amount
in Rs.
2400.00

290

Gates and Allied Works - Item Unit Rates 2014-15

2
3
4
5
6
7
8

Fuel / Energy charges


Tower crane
Fuel / Energy charges
Pug cutting machine
Fuel / Energy charges
Mobile CRANE 16T
Fuel / Energy charges
Grinding machine
Fuel / Energy charges
Drilling machines
Fuel / Energy charges
Bending Machine
Fuel / Energy charges
Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3
4
5
6
7
8
9
10
11

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Description

150.00
6.00
6.00
12.00
12.00
8.00
8.00
12.00
12.00
12.00
12.00
10.00
10.00
10.00

Unit

Quantity

Crew for Mobile crane 16T


Crew for Tower crane
Crew for Drilling machine
Crew for Grinding machine
Crew for Bending machine
Foreman
Marker / Fabricator / Erector
Gas cutter
Welder ( General )
Helper fabrication / erection
Electrician

Hour
10.00
Hour
6.00
Hour
12.00
Hour
12.00
Hour
10.00
Day
6.00
Day
25.00
Day
5.00
Day
20.00
Day
200.00
Day
2.00
Total cost of Labour
Add towards highly skilled labour charges @ 30% on total cost of labour
Total Cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

91.30
867.10
197.80
6.40
3.80
2278.10
75.00
22.50
38.00
22.50
38.00
42.60
114.10
41.00
Rs:

13695.00
5202.60
1186.80
76.80
45.60
18224.80
600.00
270.00
456.00
270.00
456.00
426.00
1141.00
410.00
44860.60

Rate
in Rs.
454.30
163.30
171.60
171.60
113.90
440.00
440.00
385.00
385.00
345.00
440.00
Rs:

Amount
in Rs.
4543.00
979.80
2059.20
2059.20
1139.00
2640.00
11000.00
1925.00
7700.00
69000.00
880.00
103925.20
31177.56
135102.76

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

271657.65
44860.60
135102.76
451621.01
0.00
451621.01
13548.63
465169.64
65123.75

25881.80
0.14 3623.50
29505.30

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0.00%
Total
3%

D. Add for excise duty


(on 75 percent cost excluding cost of materials)
E. Add for transportation upto work site @
Total
F. Add for contractor's profit and overheads on (A+B
Add 2 leads
Add 1 km lead charges for fabricated parts
Unloading charges of fabricated parts Rs
Total cost for

14%
R

19.00 per tonne


63.30 per tonne

198.36
660.852
Rs:
531152.60
Rs:
101753.40

5.22 MT
Rate per MT

IRR-GAW-2
VERTICAL LIFT GATES-EM PARTS
IRR-GAW-2-1 Design, fabrication, supply, erection and commissioning of embedded parts consisting of
sill beam, slide tracks, seal seats, guide rails, dogging sets for storage of stoplog elements
etc., with all accessories for spillway stop log gates and other vertical lift elements including cost of all materials,
machinery, labour, etc., complete as per specifications and approved drawings
(without painting on sand-blasted or mechanical cleaning surfaces which are added extra
as perscedule of rates under items in this chapter and add as applicable separately)
Drawing No. MD/CDO/GNCP/HR/1759,1760/94 (GNSS Project)
Vent Size:
DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Quantity

3.6 X 6.1 Mtr


6.300 tonne
Rate

Amount

291

Gates and Allied Works - Item Unit Rates 2014-15

1
2
3
4
5
6
7
8
9
10
11
12

Str steel angle / beam / channel / bars


Structural steel plate / flats
Stainless steel plate / flats
MS bolts and nuts
Oxygen gas
Acetyline gas
Welding electrodes
Welding electrodes ( LH )
Welding electrodes ( stainless steel )
Use rate welding holder set
Use rate gas cutting torch set
Sundries

B. MACHINERY:
Sl No
1
2
3
4
5
6
7
8
9
10

1
2
3
4
5
6
7
8
9
10
11
12

Description

Welding transformer
Fuel / Energy charges
Plate shearing machine
Fuel / Energy charges
Pug cutting machine
Fuel / Energy charges
Planing machine
Fuel / Energy charges
Mobile Crane 16 T
Fuel / Energy charges
Stationery derric crane
Fuel / Energy charges
Grinding machine
Fuel / Energy charges
Drilling machines
Fuel / Energy charges
Bending Machine
Fuel / Energy charges
Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No

kg
1885.00
kg
3890.00
kg
271.00
kg
50.00
cum
225.00
cum
75.00
Nos
1410.00
Nos
350.00
Nos
1320.00
Hour
385.00
Hour
225.00
LS
40.00
Total cost of Materials

Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Description

Quantity
385.00
385.00
8.00
8.00
110.00
110.00
270.00
270.00
24.00
24.00
14.00
14.00
14.00
14.00
21.00
21.00
14.00
14.00
40.00

Unit

Quantity

Crew for Mobile crane 16 T


Crew for Planing machine
Crew for Drilling machine
Crew for Grinding machine
Crew for Bending machine
Foreman
Marker / Fabricator / Erector
Gas cutter
Welder ( General )
Welder ( X - ray )
Helper fabrication / erection
Electrician

Hour
24.00
Hour
270.00
Hour
21.00
Hour
14.00
Hour
14.00
Day
32.00
Day
35.00
Day
9.00
Day
46.00
Day
6.00
Day
240.00
Day
4.00
Total cost of Labour
Add towards highly skilled labour charges @ 30% on total cost of labour
Total Cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

in Rs.
84825.00
178940.00
74525.00
4500.00
11700.00
24000.00
15510.00
6300.00
34320.00
2829.75
5326.13
1640.00
444415.88

Rate
in Rs.
16.00
91.30
41.90
152.20
6.40
3.80
117.80
114.10
2278.10
75.00
86.10
0.00
22.50
38.00
22.50
38.00
42.60
114.10
41.00
Rs:

Amount
in Rs.
6160.00
35150.50
335.20
1217.60
704.00
418.00
31806.00
30807.00
54674.40
1800.00
1205.40
0.00
315.00
532.00
472.50
798.00
596.40
1597.40
1640.00
170229.40

Rate
in Rs.
454.30
182.20
171.60
171.60
113.90
440.00
440.00
385.00
385.00
440.00
345.00
440.00
Rs:

Amount
in Rs.
10903.20
49194.00
3603.60
2402.40
1594.60
14080.00
15400.00
3465.00
17710.00
2640.00
82800.00
1760.00
205552.80
61665.84
267218.64

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

444415.88
170229.40
267218.64
881863.92
0.00
881863.92

42415.70
0.14 5938.20
48353.90

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for excise duty
(on 75 percent cost excluding cost of materials)

in Rs.
45.00
46.00
275.00
90.00
52.00
320.00
11.00
18.00
26.00
7.35
23.67
41.00
Rs:

Total
0.00%
Total

292

Gates and Allied Works - Item Unit Rates 2014-15

E. Add for transportation upto work site @

3%

Rs:
Rs:
Rs:

Total
F. Add for contractor's profit and overheads on (A+B
Add 2 leads
Add 1 km lead charges for fabricated parts
Unloading charges of fabricated parts Rs
Total cost for

14%
R

19.00 per tonne


63.30 per tonne

26455.92
908319.83
127164.78

239.4
797.58
Rs:
1036521.59
Rs:
164527.20

6.30 tonne
Rate per tonne

vertical lift gates and stop log gate elements ( SLIDING GATES)
IRR-GAW-2-2 Design, fabrication, supply, erection, testing and commissioning of vertical lift gates and
stoplog gate elements, consisting of skin plate,
horizontal and vertical girders, stiffeners, lifting pins, bronze padded slide blocks/bearings, guide shoes,
rubber seals, clamps etc., with all accessories including cost of all materials,
machinery, labour, seal fixing etc.,complete as per specifications and approved drawings
(without painting on sand-blasted or mechanical cleaning surfaces which are added extra
as perscedule of rates under items in this chapter and add as applicable separately)
Drawing NO. CE/CDO/CL3/MRP/783/2002 (Spillway Stop log gate Elements of Madduvalasa Project)
Vent Size: 12.624 X 0.50 M 16 Elements

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

2
3
4

5
6
7
8
9
10
11

Structural steel
Angles / beams / channels / bars
Plates / flats
Alloy steel components
Lifting pins
Bolt / Nut / Washer
GI bolts / nuts / washers
Rubber seals
Bottom seal
Side seals
Oxygen gas
Acetyline gas
Welding electrodes
Welding electrodes ( LH )
Use rate welding holder set
Use rate gas cutting torch set
Sundries

B. MACHINERY:
Sl No
1
2
3
4
5
6
7
8

particulars

Description

Welding transformer
Fuel / Energy charges
Pug cutting machine
Fuel / Energy charges
Mobile crane 16 T
Fuel / Energy charges
Stationery derric crane
Fuel / Energy charges
Grinding machine
Fuel / Energy charges
Drilling machines
Fuel / Energy charges
Bending Machine
Fuel / Energy charges
Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No

Description

UNIT :
Unit

Quantity

119.000 tonne
Rate
in Rs.

Amount
in Rs.

kg
kg

5280.00
112880.00

45.00
46.00

237600.00
5192480.00

kg

520.00

420.00

218400.00

kg

600.00

130.00

78000.00

Rm
210.00
Rm
18.00
cum
2714.00
cum
905.00
Nos
86554.00
Nos
16486.00
Hour
12880.00
Hour
2714.00
LS
400.00
Total cost of Materials

759.00
1155.00
52.00
320.00
11.00
18.00
7.35
23.67
41.00
Rs:

159390.00
20790.00
141128.00
289600.00
952094.00
296748.00
94668.00
64244.90
16400.00
7761542.90

Rate
in Rs.
16.00
91.30
6.40
3.80
2278.10
75.00
86.10
0.00
22.50
38.00
22.50
38.00
42.60
114.10
41.00
Rs:

Amount
in Rs.
206080.00
1175944.00
41216.00
24472.00
820116.00
27000.00
20491.80
0.00
5355.00
9044.00
8032.50
13566.00
10224.00
27384.00
7380.00
2396305.30

Rate
in Rs.

Amount
in Rs.

Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Unit

Quantity
12880.00
12880.00
6440.00
6440.00
360.00
360.00
238.00
238.00
238.00
238.00
357.00
357.00
240.00
240.00
180.00

Quantity

293

Gates and Allied Works - Item Unit Rates 2014-15

1
2
3
4
5
6
7
8
9
10
11
12

Crew for Mobile crane 16T


Crew for Drilling machine
Crew for Grinding machine
Crew for Bending machine
Foreman
Marker / Fabricator / Erector
Gas cutter
Welder ( General )
Welder ( X - ray )
Khalasi
Helper fabrication / erection
Electrician

Hour
360.00
Hour
357.00
Hour
238.00
Hour
240.00
Day
120.00
Day
195.00
Day
100.00
Day
1442.00
Day
275.00
Day
2023.00
Day
2727.00
Day
10.00
Total cost of Labour
Add towards highly skilled labour charges @ 30% on total cost of labour
Total Cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

454.30
171.60
171.60
113.90
440.00
440.00
385.00
385.00
440.00
385.00
345.00
440.00
Rs:

163548.00
61261.20
40840.80
27336.00
52800.00
85800.00
38500.00
555170.00
121000.00
778855.00
940815.00
4400.00
2870326.00
861097.80
3731423.80

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

7761542.90
2396305.30
3731423.80
13889272.00
0.00
13889272.00
416678.16
14305950.16
2002833.02

31356.50
0.14 4389.90
35746.40

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0.00%
Total
3%

D. Add for excise duty


(on 75 percent cost excluding cost of materials)
E. Add for transportation upto work site @
Total
F. Add for contractor's profit and overheads on (A+B
Add 2 leads
Add 1 km lead charges for fabricated parts
Unloading charges of fabricated parts Rs
Total cost for

14%
R

19.00 per tonne


63.30 per tonne

4522.000
15065.4
Rs:
16328370.59
Rs:
137213.20

119.00 tonne
Rate per tonne

STOP LOGS-automatic lifting beam


IRR-GAW-2-3 fabrication, supply, erection, testing and commissioning of automatic lifting beam
with all accessories for handling, lowering and lifting of spillway stop log gate elements
including cost of all materials, machinery, labour, cutting, aligning, welding, finishing,
etc., complete as per specifications and drawings with all leads and lifts.
(without painting on sand-blasted or mechanical cleaning surfaces which are added extra
as perscedule of rates under items in this chapter and add as applicable separately)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

2
3
4
5
6
7
8
9
10
11
12
13

particulars

Structural steel
Angles / beams / channels / bars
Plates / flats
Alloy steel components
Lifting pins
Bronze alloy components :
Bronze bush
Forged steel components :
Lifting hooks
MS pipe 100 mm dia
Bolt / Nut / Washer
MS bolts / nuts / washers
Oxygen gas
Acetyline gas
Welding electrodes
Welding electrodes ( LH )
Use rate welding holder set
Use rate gas cutting torch set
Sundries

UNIT :
Unit

Quantity

3.528 tonne
Rate
in Rs.

Amount
in Rs.

kg
kg

13.00
3389.00

45.00
46.00

585.00
155894.00

kg

101.00

420.00

42420.00

kg

5.00

912.00

4560.00

kg
kg

103.00
11.00

260.00
175.00

26780.00
1925.00

3.00
126.00
42.00
175.00
1575.00
187.00
24.00
25.00

90.00
52.00
320.00
11.00
18.00
7.35
23.67
41.00

270.00
6552.00
13440.00
1925.00
28350.00
1374.45
568.12
1025.00

kg
cum
cum
Nos
Nos
Hour
Hour
LS

294

Gates and Allied Works - Item Unit Rates 2014-15

Total cost of Materials


B. MACHINERY:
Sl No
1
2
3
4
5
6
7

Welding transformer
Fuel / Energy charges
Pug cutting machine
Fuel / Energy charges
Mobile derric crane
Fuel / Energy charges
Stationery derric crane
Fuel / Energy charges
Grinding machine
Fuel / Energy charges
Drilling machines
Fuel / Energy charges
Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3
4
5
6
7
8
9

Description

Unit

Quantity

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Description

187.00
117.00
60.00
60.00
4.00
4.00
8.00
8.00
2.00
2.00
2.00
2.00
10.00

Unit

Quantity

Crew for Mobile crane


Crew for Drilling machine
Crew for Grinding machine
Foreman
Marker / Fabricator / Erector
Gas cutter
Welder ( General )
Helper fabrication / erection
Electrician

Hour
4.00
Hour
2.00
Hour
2.00
Day
10.00
Day
18.00
Day
10.00
Day
18.00
Day
52.00
Day
1.00
Total cost of Labour
Add towards highly skilled labour charges @ 30% on total cost of labour
Total Cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Rs:

285668.57

Rate
in Rs.
16.00
91.30
6.40
3.80
519.70
322.20
86.10
0.00
22.50
38.00
22.50
38.00
41.00
Rs:

Amount
in Rs.
2992.00
10682.10
384.00
228.00
2078.80
1288.80
688.80
0.00
45.00
76.00
45.00
76.00
410.00
18994.50

Rate
in Rs.
153.10
171.60
171.60
440.00
440.00
385.00
385.00
345.00
440.00
Rs:

Amount
in Rs.
612.40
343.20
343.20
4400.00
7920.00
3850.00
6930.00
17940.00
440.00
42778.80
12833.64
55612.44

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

285668.57
18994.50
55612.44
360275.51
0.00
360275.51
10808.27
371083.78
51951.73

15763.20
0.14 2206.80
17970.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0.00%
Total
3%

D. Add for excise duty


(on 75 percent cost excluding cost of materials)
E. Add for transportation upto work site @
Total
F. Add for contractor's profit and overheads on (A+B
Add 2 leads
Add 1 km lead charges for fabricated parts
Unloading charges of fabricated parts Rs
Total cost for

14%
R
3.528 tonne
Rate per tonne

19.00 per tonne


63.30 per tonne

134.064
446.644
Rs:
423616.21
Rs:
120072.60

MOVING GANTRY CRANE-CLASS II


IRR-GAW-2-4 fabrication, supply, erection, testing and commissioning of adequate capacity Class- II
type moving gantry crane consisting of rail mounted gantry frame, top platform with hand
railing, long / cross travel arrangements, rope drums, gear systems, electric motors, electromagnetic brake system, cabin, control panel, wire rope, ladder, motorised cable reeling drum
etc., with all accessories for operating spillway stop log gate elements and river sluice /
canal sluice emergency gates including cost of all materials, machinery, labour,
etc., complete with all leads and lifts.
(without painting on sand-blasted or mechanical cleaning surfaces which are added extra
as perscedule of rates under items in this chapter and add as applicable separately)

295

Gates and Allied Works - Item Unit Rates 2014-15

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

3
4

5
6
7
8
9
10

11
12
13
14
15
16
17
18
19
20

2
3
4
5
6
7

Description

Welding transformer
Fuel / Energy charges
Tower crane 5 t capacity
Fuel / Energy charges
Pug cutting machine
Fuel / Energy charges
Mobile derric crane
Fuel / Energy charges
Grinding machine
Fuel / Energy charges
Drilling machines
Fuel / Energy charges
Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3
4
5
6
7

Unit

Quantity

Structural steel
Angles / beams / channels / bars
kg
1743.00
Plates / flats
kg
19700.00
Chequered plates
kg
820.00
Cast steel components :
Rope drums 2 Nos/Gears
kg
1320.00
pinions
kg
1165.00
Wheels / Pulleys
kg
2255.00
Plummer blocks / Couplings
kg
817.00
Forged steel components
Hook / Shackle
kg
127.00
Alloy steel components
Shafts
kg
556.00
Pins
kg
524.00
Bronze alloy components :
Bronze bearings / bush
kg
181.00
Wire rope 28 mm dia 6/37 construction kg
406.00
MS Bolt / Nut / Washer
kg
63.00
MS pipe 32 mm dia for railing
Rm
50.00
Worm reducers
Nos.
4.00
Electric motor 17.5 hp
No.
1.00
Electric motor 5 hp
Nos.
2.00
Electric motor 3 hp
No.
1.00
Ele-magnetic / Thruster brakes
Nos.
4.00
Electric cable / switch / control panel
etc
LS
3.00
Oxygen gas
cum
579.00
Acetyline gas
cum
193.00
Welding electrodes
Nos
1123.00
Welding electrodes ( LH )
Nos
10110.00
Grease
kg
50.00
Use rate welding holder set
Hour
1197.00
Use rate gas cutting torch set
Hour
150.00
Sundries
LS
200.00
Total cost of Materials

B. MACHINERY:
Sl No
1

particulars

UNIT :

Description

Crew for Mobile crane


Crew for Tower crane
Crew for Drilling machine
Crew for Grinding machine
Foreman
Marker / Fabricator / Erector
Gas cutter

Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Unit
Hour
Hour
Hour
Hour
Day
Day
Day

Quantity
1197.00
748.00
6.00
6.00
235.00
235.00
100.00
100.00
32.00
32.00
16.00
16.00
500.00

Quantity
100.00
6.00
16.00
32.00
74.00
124.00
48.00

30.856 tonne
25 t capacity
Rate
Amount
in Rs.
in Rs.
45.00
46.00
60.00

78435.00
906200.00
49200.00

220.00
210.00
180.00
180.00

290400.00
244650.00
405900.00
147060.00

260.00

33020.00

210.00
420.00

116760.00
220080.00

912.00
250.00
90.00
185.00
224400.00
85800.00
33000.00
23100.00
35200.00

165072.00
101500.00
5670.00
9250.00
897600.00
85800.00
66000.00
23100.00
140800.00

50380.00
52.00
320.00
11.00
18.00
260.00
7.35
23.67
41.00
Rs:

151140.00
30108.00
61760.00
12353.00
181980.00
13000.00
8797.95
3550.75
8200.00
4457386.70

Rate
in Rs.
16.00
91.30
867.10
197.80
6.40
3.80
519.70
322.20
22.50
38.00
22.50
38.00
41.00
Rs:

Amount
in Rs.
19152.00
68292.40
5202.60
1186.80
1504.00
893.00
51970.00
32220.00
720.00
1216.00
360.00
608.00
20500.00
203824.80

Rate
in Rs.
153.10
163.30
171.60
171.60
440.00
440.00
385.00

Amount
in Rs.
15310.00
979.80
2745.60
5491.20
32560.00
54560.00
18480.00

296

Gates and Allied Works - Item Unit Rates 2014-15

8
9
10
11

Welder ( General )
Khalasi
Helper fabrication / erection
Electrician

Day
112.00
Day
20.00
Day
350.00
Day
10.00
Total cost of Labour
Add towards highly skilled labour charges @ 30% on total cost of labour
Total Cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

385.00
385.00
345.00
440.00
Rs:

43120.00
7700.00
120750.00
4400.00
306096.60
91828.98
397925.58

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

4457386.70
203824.80
397925.58
5059137.08
0.00
5059137.08
151774.11
5210911.19
729527.57

15917.00
0.14 2228.40
18145.40

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0.00%
Total
3%

D. Add for excise duty


(on 75 percent cost excluding cost of materials)
E. Add for transportation upto work site @
Total
F. Add for contractor's profit and overheads on (A+B
Add 2 leads
Add 1 km lead charges for fabricated parts
Unloading charges of fabricated parts Rs
Total cost for

14%
R

30.856
25.000
Rate per
Rate per

19.00 per tonne


63.30 per tonne

tonne
t capacity
tonne
tonne capac

1172.528
3906.37
Rs:
5945517.66
Rs:
Rs:
192685.90
Rs:
237820.70

RAIL TRACK FOR GANTRY CRANE


IRR-GAW-2-5 Design, fabrication, supply, erection and commissioning of rail track using 45 kg / m standard
rails on spillway bridge for movement of gantry crane for handling and operating spillway
stoplog gate elements / river sluice / canal sluice emergency gate including cost of all materials,
machinery, labour, complete as per specifications
(without painting on sand-blasted or mechanical cleaning surfaces which are added extra
as perscedule of rates under items in this chapter and add as applicable separately)
DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

1
2
3
4
5
6
7
8
9
10

Str steel angle / beam / channel / bars


Structural steel plate / flats
Rails
MS bolts and nuts
Oxygen gas
Acetyline gas
Welding electrodes
Use rate welding holder set
Use rate gas cutting torch set
Sundries

B. MACHINERY:
Sl No
1
2
3
4
5

particulars

Description

Welding transformer
Fuel / Energy charges
Mobile derric crane
Fuel / Energy charges
Grinding machine
Fuel / Energy charges
Drilling machines
Fuel / Energy charges
Sundries
Total hire charges of Machinery

UNIT :
Unit

Quantity

kg
1570.00
kg
975.00
kg
18450.00
kg
246.00
cum
201.00
cum
67.00
Nos
1805.00
Hour
193.00
Hour
133.00
LS
10.00
Total cost of Materials

Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Quantity
193.00
121.00
4.00
4.00
8.00
8.00
50.00
50.00
10.00

200.000 Rm
Rate
in Rs.

Amount
in Rs.

45.00
46.00
51.50
90.00
52.00
320.00
11.00
7.35
23.67
41.00
Rs:

70650.00
44850.00
950175.00
22140.00
10452.00
21440.00
19855.00
1418.55
3148.33
410.00
1144538.88

Rate
in Rs.
16.00
91.30
519.70
322.20
22.50
38.00
22.50
38.00
41.00
Rs:

Amount
in Rs.
3088.00
11047.30
2078.80
1288.80
180.00
304.00
1125.00
1900.00
410.00
21421.90

297

Gates and Allied Works - Item Unit Rates 2014-15

C. LABOUR:
Sl No
1
2
3
4
5
6
7
8
9

Description

Unit

Quantity

Crew for Mobile crane


Crew for Drilling machine
Crew for Grinding machine
Foreman
Marker / Fabricator / Erector
Gas cutter
Welder ( General )
Helper fabrication / erection
Electrician

Hour
4.00
Hour
50.00
Hour
8.00
Day
8.00
Day
32.00
Day
17.00
Day
18.00
Day
52.00
Day
1.00
Total cost of Labour
Add towards highly skilled labour charges @ 30% on total cost of labour
Total Cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Rate
in Rs.
153.10
171.60
171.60
440.00
440.00
385.00
385.00
345.00
440.00
Rs:

Amount
in Rs.
612.40
8580.00
1372.80
3520.00
14080.00
6545.00
6930.00
17940.00
440.00
60020.20
18006.06
78026.26

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

1144538.88
21421.90
78026.26
1243987.04
0.00
1243987.04
37319.61
1281306.65
179382.93

390.10
0.14 54.60
444.70

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0.00%
Total
3%
Total

D. Add for excise duty


(on 75 percent cost excluding cost of materials)
E. Add for transportation upto work site @
F. Add for contractor's profit and overheads on (A+B
Add 2 leads
Add 1 km lead charges for fabricated parts
Unloading charges of fabricated parts Rs
Total cost for

14%
R

19.00 per tonne


63.30 per tonne

787.436
2623.406
Rs:
1464100.43
Rs:
7320.50

200.000 Rm
Rate per Rm

VERTICAL LIFT GATES/STOP LOGS - ROLLER MOUNTED


IRR-GAW-2-6 Design, fabrication, supply, erection, testing and commissioning of fixed wheel type vertical
lift service gate consisting of skin plate, vertical and horizontal girders, wheels, stiffeners, lifting
brackets, guide rollers, ballast blocks, teflon claded rubber seals etc., with all accessories for
river sluice / canal sluice vent including cost of all materials, machinery, labour,welding ,aligning finishing
seal fixing etc.with allleads and lifts, complete as per specifications andvapproved drawings
(without painting on sand-blasted or mechanical cleaning surfaces which are added extra
as perscedule of rates under items in this chapter and add as applicable separately)
Drawing No. CE/CDO/DEE/DEE4/GNC/HR/2150/96,2137/98 (GNSS Project)
Gate Size: 3.66 X 6.1 Mtr
DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

2
3

4
5

particulars

Structural steel
Plates / flats
Beams/Channels
Alloy steel components
Wheel axles / Pins
Cast steel components
Wheels / Guide rollers
Alluminium / Bronze alloy
components
Bearings
Bolt / Nut / Washer
GI bolts / nuts / washers
MS bolts / nuts / washers
Rubber seals
Bottom seal ( flat uncladed )

UNIT :
Unit

Quantity

10.000 tonne
Rate
in Rs.

Amount
in Rs.

kg
kg

7103.00
2727.00

46.00
45.00

326738.00
122715.00

kg

108.00

420.00

45360.00

kg

504.00

180.00

90720.00

kg

12.00

912.00

10944.00

kg
kg

36.00
6.00

106.00
90.00

3816.00
540.00

Rm

3.72

759.00

2823.48

298

Gates and Allied Works - Item Unit Rates 2014-15

7
8
9
10
11
12
13

Side seals ( bulb teflon claded )


Top seal ( bulb teflon claded )
Corner seals ( bulb teflon claded )
Oxygen gas
Acetyline gas
Welding electrodes
Welding electrodes ( LH )
Use rate welding holder set
Use rate gas cutting torch set
Sundries

B. MACHINERY:
Sl No
1
2
3
4
5
6
7
8
9

Description

Welding transformer
Fuel / Energy charges
Pug cutting machine
Fuel / Energy charges
Tower crane
Fuel / Energy charges
Mobile crane 16 T
Fuel / Energy charges
Stationery derric crane
Fuel / Energy charges
Grinding machine
Fuel / Energy charges
Drilling machines
Fuel / Energy charges
Bending machine
Fuel / Energy charges
Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3
4
5
6
7
8
9
10
11
12
13

Rm
12.30
Rm
3.72
Nos
2.00
cum
170.00
cum
56.00
Nos
3200.00
Nos
800.00
Hour
500.00
Hour
40.00
LS
60.00
Total cost of Materials

Unit

Quantity

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Description

500.00
500.00
85.00
85.00
10.00
10.00
30.00
30.00
20.00
20.00
10.00
10.00
30.00
30.00
10.00
10.00
50.00

Unit

Quantity

Crew for Mobile crane 16 T


Crew for Tower crane
Crew for Drilling machine
Crew for Grinding machine
Crew for Bending machine
Foreman
Marker / Fabricator / Erector
Gas cutter
Welder ( General )
Welder ( X - ray grade )
Khalasi
Helper fabrication / erection
Electrician

Hour
30.00
Hour
10.00
Hour
30.00
Hour
10.00
Hour
10.00
Day
16.00
Day
50.00
Day
8.00
Day
52.00
Day
14.00
Day
170.00
Day
230.00
Day
4.00
Total cost of Labour
Add towards highly skilled labour charges @ 30% on total cost of labour
Total Cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

18671.40
5646.96
2970.00
8840.00
17920.00
35200.00
14400.00
3675.00
946.87
2460.00
714386.71

Rate
in Rs.
16.00
91.30
6.40
3.80
867.10
197.80
2278.10
75.00
86.10
0.00
22.50
38.00
22.50
38.00
42.60
114.10
41.00
Rs:

Amount
in Rs.
8000.00
45650.00
544.00
323.00
8671.00
1978.00
68343.00
2250.00
1722.00
0.00
225.00
380.00
675.00
1140.00
426.00
1141.00
2050.00
143518.00

Rate
in Rs.
454.30
163.30
171.60
171.60
113.90
440.00
440.00
385.00
385.00
440.00
385.00
345.00
440.00
Rs:

Amount
in Rs.
13629.00
1633.00
5148.00
1716.00
1139.00
7040.00
22000.00
3080.00
20020.00
6160.00
65450.00
79350.00
1760.00
228125.00
68437.50
296562.50

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

714386.71
143518.00
296562.50
1154467.21
0.00
1154467.21
34634.02
1189101.22
166474.17

29656.30
0.14 4151.90
33808.20

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0.00%
Total
3%

D. Add for excise duty


(on 75 percent cost excluding cost of materials)
E. Add for transportation upto work site @
Total
F. Add for contractor's profit and overheads on (A+B
Add 2 leads

1518.00
1518.00
1485.00
52.00
320.00
11.00
18.00
7.35
23.67
41.00
Rs:

14%

299

Gates and Allied Works - Item Unit Rates 2014-15

Add 1 km lead charges for fabricated parts


Unloading charges of fabricated parts Rs
Total cost for

19.00 per tonne


63.30 per tonne

10.000 tonne
Rate per tonne

380
1266
Rs:
Rs:

1357221.39
135722.10

VERTICAL LIFT GATES-ROPE DRUM HOIST UPTO 30 TON CAP. POWER OPERATED
IRR-GAW-2-7 Design, fabrication, supply, erection, testing and commissioning of adequate capacity rope
drum hoist consisting of hoist platform, rope drum, gear system, electric motor, electromagnetic brake system, hand operation assembly, control panel, wire rope, pulleys, ladder etc.,
with all accessories for operating river sluice / canal sluice service gate including cost of
all materials, machinery, labour, , complete as per specifications and drawings with all leads and lifts
(without painting on sand-blasted or mechanical cleaning surfaces which are added extra
as perscedule of rates under items in this chapter and add as applicable separately)
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1

5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20

Structural steel
Angles / beams / channels / bars
Plates / flats
Chequered plate
Cast steel components :
Rope drums 2 Nos / Gears
Pinions
Pulleys 3 Nos / Couplings 2 Nos
Plummer blocks / Hubs
Alloy steel components
Shafts
Pins
Bronze alloy components :
Bronze bearings / bush
Wire rope 28 mm dia 6/37
construction
MS Bolt / Nut / Washer
Worm reducers
Electric motor 5 hp
Manual operating system
Gate position indicator
Ele-magnetic brake
Electric cable / switch / control panel
etc
Oxygen gas
Acetyline gas
Welding electrodes
Welding electrodes ( LH )
Grease
Use rate welding holder set
Use rate gas cutting torch set
Sundries

B. MACHINERY:
Sl No
1
2
3
4
5
6

particulars

UNIT :
Unit

Quantity

6.243 tonne wt
25 t capacity
Rate
Amount
in Rs.
in Rs.

kg
kg
kg

1487.00
402.00
290.00

45.00
46.00
60.00

66915.00
18492.00
17400.00

kg
kg
kg
kg

1926.00
79.00
306.00
72.00

220.00
210.00
180.00
180.00

423720.00
16590.00
55080.00
12960.00

kg
kg

346.00
73.00

210.00
420.00

72660.00
30660.00

kg

57.00

912.00

51984.00

kg
kg
No.
No.
No.
No.
No.

325.00
32.00
1.00
1.00
1.00
1.00
1.00

250.00
90.00
224400.00
33000.00
28820.00
195800.00
35200.00

81250.00
2880.00
224400.00
33000.00
28820.00
195800.00
35200.00

LS
1.00
cum
45.00
cum
15.00
Nos
80.00
Nos
720.00
kg
50.00
Hour
85.00
Hour
16.00
LS
25.00
Total cost of Materials

50380.00
52.00
320.00
11.00
18.00
260.00
7.35
23.67
41.00
Rs:

50380.00
2340.00
4800.00
880.00
12960.00
13000.00
624.75
378.75
1025.00
1454199.50

Rate
in Rs.
16.00
91.30
867.10
197.80
6.40
3.80
519.70
322.20
22.50
38.00
22.50
38.00

Amount
in Rs.
1360.00
4838.90
1734.20
395.60
96.00
57.00
5197.00
3222.00
45.00
76.00
45.00
76.00

Description

Unit

Welding transformer
Fuel / Energy charges
Tower crane 5 t capacity
Fuel / Energy charges
Pug cutting machine
Fuel / Energy charges
Mobile derric crane
Fuel / Energy charges
Grinding machine
Fuel / Energy charges
Drilling machines
Fuel / Energy charges

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour

Quantity
85.00
53.00
2.00
2.00
15.00
15.00
10.00
10.00
2.00
2.00
2.00
2.00

300

Gates and Allied Works - Item Unit Rates 2014-15

Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3
4
5
6
7
8
9
10
11

LS

Description

25.00

Unit

Quantity

Crew for Mobile crane


Crew for Tower crane
Crew for Drilling machine
Crew for Grinding machine
Foreman
Marker / Fabricator / Erector
Gas cutter
Welder ( General )
Khalasi
Helper fabrication / erection
Electrician

Hour
10.00
Hour
2.00
Hour
2.00
Hour
2.00
Day
15.00
Day
19.00
Day
4.00
Day
8.00
Day
4.00
Day
44.00
Day
2.00
Total cost of Labour
Add towards highly skilled labour charges @ 30% on total cost of labour
Total Cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

41.00
Rs:

1025.00
18167.70

Rate
in Rs.
153.10
163.30
171.60
171.60
440.00
440.00
385.00
385.00
385.00
345.00
440.00
Rs:

Amount
in Rs.
1531.00
326.60
343.20
343.20
6600.00
8360.00
1540.00
3080.00
1540.00
15180.00
880.00
39724.00
11917.20
51641.20

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

1454199.50
18167.70
51641.20
1524008.40
0.00
1524008.40
45720.25
1569728.65
219762.01

2065.60
0.14 289.20
2354.80

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0.00%
Total
3%

D. Add for excise duty


(on 75 percent cost excluding cost of materials)
E. Add for transportation upto work site @
Total
F. Add for contractor's profit and overheads on (A+B
Add 2 leads
Add 1 km lead charges for fabricated parts
Unloading charges of fabricated parts Rs
Total cost for

14%
R

19.00 per tonne


63.30 per tonne
6.243 tonne wt
25.000 t capacity
Rate per tonne wt
Rate per tonne capacity of hoist

237.234
790.364
Rs:
1790518.26
Rs:
Rs:
286804.10
Rs:
71620.70

HOIST BRIDGE/ WITH TRESSELS


IRR-GAW-2-8 Design, fabrication, supply, erection and commissioning of structural steel hoist bridge
consisting of columns, beams, bracings, stiffeners, ties, chequered plate covering, hand railing,
ladder etc., with all accessories for supporting rope drum hoist for operating barrage
gates including cost of all materials, machinery, labour, welding, finishing, etc., complete
complete as per specifications and drawings with all leads and lifts
(without painting on sand-blasted or mechanical cleaning surfaces which are added extra
as perscedule of rates under items in this chapter and add as applicable separately)
Drawing No. CE/CDO/VRSP/215,216/86-87 (Vengalaraya Sagar - Gomukhi Project)

DATA:

Vent Size: 12 X 6.6 Mtr


UNIT :
10.500 tonne

RATE ANALYSIS
A. MATERIALS:
Sl No

2
3
4
5
6
7

particulars

Structural steel angles/ beams /


channels
Structural steel plates / flats
Chequered plate
MS pipe 25 mm dia
Bolt / Nut / Washers
Oxygen gas
Acetyline gas
Welding electrodes
Use rate welding holder set

Unit

kg
kg
kg
Rm
kg
cum
cum
Nos
Hour

Quantity

1494.00
6564.00
2442.00
60.00
18.00
105.00
35.00
3150.00
394.00

Rate
in Rs.
45.00
46.00
60.00
150.00
90.00
52.00
320.00
11.00
7.35

Amount
in Rs.
67230.00
301944.00
146520.00
9000.00
1620.00
5460.00
11200.00
34650.00
2895.90

301

Gates and Allied Works - Item Unit Rates 2014-15

8
9

Use rate gas cutting torch set


Sundries

B. MACHINERY:
Sl No
1
2
3
4
5
6
7
8

Description

Welding transformer
Fuel / Energy charges
Pug cutting machine
Fuel / Energy charges
Mobile crane 30 T
Fuel / Energy charges
Stationery derric crane
Fuel / Energy charges
Drilling machine
Fuel / Energy charges
Grinding machine
Fuel / Energy charges
Tower Crane
Fuel / Energy charges
Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3
4
5
6
7
8
9
10

Hour
105.00
LS
50.00
Total cost of Materials

Unit

Quantity

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Description

394.00
394.00
52.00
52.00
30.00
30.00
20.00
20.00
20.00
20.00
20.00
20.00
20.00
20.00
50.00

Unit

Quantity

Crew for Mobile crane 30 T


Crew for Drilling machine
Crew for Grinding machine
Crew for Tower Crane
Foreman
Marker / Fabricator / Erector
Gas cutter
Welder ( General )
Helper fabrication / erection
Electrician

Hour
30.00
Hour
20.00
Hour
20.00
20.00
Hour
Day
10.00
Day
50.00
Day
14.00
Day
53.00
Day
400.00
Day
6.00
Total cost of Labour
Add towards highly skilled labour charges @ 30% on total cost of labour
Total Cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

23.67
41.00
Rs:

2485.53
2050.00
585055.43

Rate
in Rs.
16.00
91.30
6.40
3.80
3096.80
118.80
86.10
0.00
22.50
38.00
22.50
38.00
867.10
197.80
41.00
Rs:

Amount
in Rs.
6304.00
35972.20
332.80
197.60
92904.00
3564.00
1722.00
0.00
450.00
760.00
450.00
760.00
17342.00
3956.00
2050.00
166764.60

Rate
in Rs.
454.30
171.60
171.60
163.30
440.00
440.00
385.00
385.00
345.00
440.00
Rs:

Amount
in Rs.
13629.00
3432.00
3432.00
3266.00
4400.00
22000.00
5390.00
20405.00
138000.00
2640.00
216594.00
64978.20
281572.20

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

585055.43
166764.60
281572.20
1033392.23
0.00
1033392.23
31001.77
1064393.99
149015.16

26816.40
0.14 3754.30
30570.70

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0.00%
Total
3%

D. Add for excise duty


(on 75 percent cost excluding cost of materials)
E. Add for transportation upto work site @
Total
F. Add for contractor's profit and overheads on (A+B
Add 2 leads
Add 1 km lead charges for fabricated parts
Unloading charges of fabricated parts Rs
Total cost for

14%
R
10.500 tonne
Rate per tonne

19.00 per tonne


63.30 per tonne

399
1329.3
Rs:
1215137.45
Rs:
115727.40

ROPE DRUM HOIST WITHOUT HOIST BRIDGE FOR BARRAGE GATES


IRR-GAW-2-9 Design, fabrication, supply, erection, testing and commissioning of adequate capacity rope
drum hoist consisting of rope drum, pulleys, gear system, electri c motor,
electro-magnetic brake system, manual operation assembly, position indicator, control panel,
wire rope etc., with all accessories for operating vertical lift roller gates for barrage
including cost of all materials, machinery, labour, cutting, bending, aligning, anchoring, welding,
finishing etc., complete with all leads and lifts.

302

Gates and Allied Works - Item Unit Rates 2014-15

(without painting on sand-blasted or mechanical cleaning surfaces which are added extra
as perscedule of rates under items in this chapter and add as applicable separately)
DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20

Structural steel
Angles / beams / channels / bars
Plates / flats
Cast steel components :
Rope drums 2 Nos / Gears
Pinions
Pulleys 3 Nos / Couplings 2 Nos
Plummer blocks / Hubs
Alloy steel components
Shafts / Keys
Pins
Bronze alloy components :
Bronze bearings / bush
Wire rope 28 mm dia 6/37
construction
MS Bolt / Nut / Washer
Worm reducers
Electric motor 12.5 hp
Manual operating system
Gate position indicator
Ele-magnetic brake
Electric cable / switch / control panel
etc
Oxygen gas
Acetyline gas
Welding electrodes
Welding electrodes ( LH )
Grease
Use rate welding holder set
Use rate gas cutting torch set
Sundries

B. MACHINERY:
Sl No
1
2
3
4
5
6
7

Description

Welding transformer
Fuel / Energy charges
Tower crane 5 t capacity
Fuel / Energy charges
Pug cutting machine
Fuel / Energy charges
Mobile derric crane
Fuel / Energy charges
Grinding machine
Fuel / Energy charges
Drilling machines
Fuel / Energy charges
Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3
4
5
6
7
8

particulars

Description

Crew for Mobile crane


Crew for Tower crane
Crew for Drilling machine
Crew for Grinding machine
Foreman
Marker / Fabricator / Erector
Gas cutter
Welder ( General )

UNIT :
Unit

Quantity

5.069 tonne wt
50.00 t capacity
Rate
Amount
in Rs.
in Rs.

kg
kg

420.00
225.00

45.00
46.00

18900.00
10350.00

kg
kg
kg
kg

1290.00
98.00
650.00
250.00

220.00
210.00
180.00
180.00

283800.00
20580.00
117000.00
45000.00

kg
kg

350.00
96.00

210.00
420.00

73500.00
40320.00

kg

100.00

912.00

91200.00

kg
kg
No.
No.
No.
No.
No.

435.00
26.00
1.00
1.00
1.00
1.00
1.00

250.00
90.00
224400.00
72600.00
28820.00
195800.00
35200.00

108750.00
2340.00
224400.00
72600.00
28820.00
195800.00
35200.00

LS
1.00
cum
30.00
cum
10.00
Nos
44.00
Nos
392.00
kg
50.00
Hour
47.00
Hour
12.00
LS
25.00
Total cost of Materials

50380.00
52.00
320.00
11.00
18.00
260.00
7.35
23.67
41.00
Rs:

50380.00
1560.00
3200.00
484.00
7056.00
13000.00
345.45
284.06
1025.00
1445894.51

Rate
in Rs.
16.00
91.30
867.10
197.80
6.40
3.80
519.70
322.20
22.50
38.00
22.50
38.00
41.00
Rs:

Amount
in Rs.
752.00
4291.10
1734.20
395.60
57.60
34.20
5197.00
3222.00
45.00
76.00
45.00
76.00
1025.00
16950.70

Rate
in Rs.
153.10
163.30
171.60
171.60
440.00
440.00
385.00
385.00

Amount
in Rs.
1531.00
326.60
343.20
343.20
5720.00
7480.00
1155.00
1925.00

Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Unit
Hour
Hour
Hour
Hour
Day
Day
Day
Day

Quantity
47.00
47.00
2.00
2.00
9.00
9.00
10.00
10.00
2.00
2.00
2.00
2.00
25.00

Quantity
10.00
2.00
2.00
2.00
13.00
17.00
3.00
5.00

303

Gates and Allied Works - Item Unit Rates 2014-15

9
10
11

Khalasi
Helper fabrication / erection
Electrician

Day
4.00
Day
36.00
Day
2.00
Total cost of Labour
Add towards highly skilled labour charges @ 30% on total cost of labour
Total Cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

385.00
345.00
440.00
Rs:

1540.00
12420.00
880.00
33664.00
10099.20
43763.20

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

1445894.51
16950.70
43763.20
1506608.41
0.00
1506608.41
45198.25
1551806.66
217252.93

875.30
0.14 122.50
997.80

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0.00%
Total
3%

D. Add for excise duty


(on 75 percent cost excluding cost of materials)
E. Add for transportation upto work site @
Total
F. Add for contractor's profit and overheads on (A+B
Add 2 leads
Add 1 km lead charges for fabricated parts
Unloading charges of fabricated parts Rs
Total cost for

14%
R

19.00 per tonne


63.30 per tonne
5.069 tonne wt
50.000 t capacity
Rate per tonne wt
Rate per tonne capacity of hoist

192.622
641.736
Rs:
1769893.95
Rs:
Rs:
349160.40
Rs:
35397.90

SCREW GEAR HOISTS including plat form( UPTO 10 TON CAP)


IRR-GAW-2-10
Design, fabrication, supply, erection, testing and commissioning of adequate capacity screw gear
type hoist consisting of supporting structure, platform, ladder etc., with all accessories for
operating canal escape / regulator gate including cost of all materials, machinery, labour,
cutting, bending, aligning, anchoring, welding,finishing etc.,complete with all leads and lifts.
(without painting on sand-blasted or mechanical cleaning surfaces which are added extra
as perscedule of rates under items in this chapter and add as applicable separately)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

2
3
4
5
6
7
8
9
10
11
12
13

Structural steel
Angles / beams / channels / bars
Plates / flats
Chequered plate
Cast iron components :
Hoist body / Lock nut / Main nut
Alloy steel components
Hoist stem
Bronze alloy components :
Thrust bearings
MS Bolt / Nut / Washer
Oxygen gas
Acetyline gas
Welding electrodes
Welding electrodes ( LH )
Grease
Use rate welding holder set
Use rate gas cutting torch set
Sundries

B. MACHINERY:
Sl No
1

particulars

Description

Welding transformer

UNIT :
Unit

Quantity

0.871 tonne
3.00 t capacity
Rate
Amount
in Rs.
in Rs.

kg
kg
kg

402.00
145.00
176.00

45.00
46.00
60.00

18090.00
6670.00
10560.00

kg

55.00

220.00

12100.00

kg

75.00

210.00

15750.00

kg
4.00
kg
8.00
cum
18.00
cum
6.00
Nos
7.00
Nos
66.00
kg
2.00
Hour
8.00
Hour
11.00
LS
2.00
Total cost of Materials

912.00
90.00
52.00
320.00
11.00
18.00
260.00
7.35
23.67
41.00
Rs:

3648.00
720.00
936.00
1920.00
77.00
1188.00
520.00
58.80
260.39
82.00
72580.19

Rate
in Rs.
16.00

Amount
in Rs.
128.00

Unit
Hour

Quantity
8.00

304

Gates and Allied Works - Item Unit Rates 2014-15

2
3
4

Fuel / Energy charges


Grinding machine
Fuel / Energy charges
Drilling machines
Fuel / Energy charges
Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3
4
5
6
7
8

Hour
Hour
Hour
Hour
Hour
LS

Description

5.00
2.00
2.00
2.00
2.00
2.00

Unit

Quantity

Crew for Drilling machine


Crew for Grinding machine
Foreman
Marker / Fabricator / Erector
Gas cutter
Welder ( General )
Helper fabrication / erection
Electrician

Hour
2.00
Hour
2.00
Day
4.00
Day
5.00
Day
2.00
Day
1.00
Day
9.00
Day
0.50
Total cost of Labour
Add towards highly skilled labour charges @ 30% on total cost of labour
Total Cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

91.30
22.50
38.00
22.50
38.00
41.00
Rs:

456.50
45.00
76.00
45.00
76.00
82.00
908.50

Rate
in Rs.
171.60
171.60
440.00
440.00
385.00
385.00
345.00
440.00
Rs:

Amount
in Rs.
343.20
343.20
1760.00
2200.00
770.00
385.00
3105.00
220.00
9126.40
2737.92
11864.32

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

72580.19
908.50
11864.32
85353.01
0.00
85353.01
2560.59
87913.60
12307.90

3954.80
0.14 553.70
4508.50

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0.00%
Total
3%

D. Add for excise duty


(on 75 percent cost excluding cost of materials)
E. Add for transportation upto work site @
Total
F. Add for contractor's profit and overheads on (A+B
Add 2 leads
Add 1 km lead charges for fabricated parts
Unloading charges of fabricated parts Rs
Total cost for

14%
R

19.00 per tonne


63.30 per tonne

33.098
110.268
Rs:
100364.87
Rs:
Rs:
115229.50
Rs:
33455.00

0.871 tonne
3.000 t capacity
Rate per tonne
Rate per tonne capacity

MANUAL OPERATED ROPE DRUM HOISTS


IRR-GAW-2-11
Design, fabrication, supply, erection, testing and commissioning of adequate capacity
manually operated rope drum hoist consisting of hoist platform, rope drum, gear system,
brake system, wire rope, ladder etc., with all accessories for operating canal regulator
radial gate including cost of all materials, machinery, labour, welding, finishing, cleaning,
., complete with all leads and lifts
(without painting on sand-blasted or mechanical cleaning surfaces which are added extra
as perscedule of rates under items in this chapter and add as applicable separately)
DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
particulars
1

Structural steel
Angles / beams / channels / bars
Plates / flats
Chequered plate
Cast steel components :
Rope drums 2 Nos / Gears
Pinions
Pulleys 6 Nos
Plummer blocks / Couplings

UNIT :

2.804
10.00
Rate
in Rs.

tonne
t capacity
Amount
in Rs.

Unit

Quantity

kg
kg
kg

1229.00
453.00
195.00

45.00
46.00
60.00

55305.00
20838.00
11700.00

kg
kg
kg
kg

384.00
14.00
108.00
47.00

220.00
210.00
180.00
180.00

84480.00
2940.00
19440.00
8460.00

305

Gates and Allied Works - Item Unit Rates 2014-15

5
6
7
8
9
10
11
12
13
14
15
16
17
18

Alloy steel components


Shafts
Pins
Bronze alloy components :
Bronze bearings / bush
Wire rope 12 mm dia 6/36
construction
MS Bolt / Nut / Washer
Worm reducers
Manual operating system
Brake
Wire rope sockets
Oxygen gas
Acetyline gas
Welding electrodes
Welding electrodes ( LH )
Grease
Use rate welding holder set
Use rate gas cutting torch set
Sundries

B. MACHINERY:
Sl No
Description
1
2
3
4
5
6
7

Welding transformer
Fuel / Energy charges
Pug cutting machine
Fuel / Energy charges
Mobile derric crane
Fuel / Energy charges
Stationery derric crane
Fuel / Energy charges
Grinding machine
Fuel / Energy charges
Drilling machines
Fuel / Energy charges
Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No
Description
1
2
3
4
5
6
7
8
9

kg
kg

75.00
24.00

210.00
420.00

15750.00
10080.00

kg

11.00

912.00

10032.00

kg
42.00
kg
64.00
No.
1.00
No.
1.00
No.
1.00
No
2.00
cum
75.00
cum
25.00
Nos
69.00
Nos
622.00
kg
10.00
Hour
73.00
Hour
42.00
LS
25.00
Total cost of Materials

250.00
90.00
224400.00
28820.00
35200.00
4620.00
52.00
320.00
11.00
18.00
260.00
7.35
23.67
41.00
Rs:

10500.00
5760.00
224400.00
28820.00
35200.00
9240.00
3900.00
8000.00
759.00
11196.00
2600.00
536.55
994.21
1025.00
581955.76

Unit

Quantity

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Unit

Rate Amount
in Rs. in Rs.
16.00
1168.00
91.30
4199.80
6.40
51.20
3.80
30.40
519.70
2078.80
322.20
1288.80
86.10
688.80
0.00
0.00
22.50
180.00
38.00
304.00
22.50
360.00
38.00
608.00
41.00
1025.00
Rs:
11982.80

73.00
46.00
8.00
8.00
4.00
4.00
8.00
8.00
8.00
8.00
16.00
16.00
25.00

Quantity

Crew for Mobile crane


Crew for Drilling machine
Crew for Grinding machine
Foreman
Marker / Fabricator / Erector
Gas cutter
Welder ( General )
Helper fabrication / erection
Electrician

Rate
in Rs.

Hour
4.00
Hour
16.00
Hour
8.00
Day
14.00
Day
20.00
Day
6.00
Day
7.00
Day
44.00
Day
2.00
Total cost of Labour
Rs:
Add towards highly skilled labour charges @ 30% on total cost of labour
Total Cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Amount
in Rs.
153.10
171.60
171.60
440.00
440.00
385.00
385.00
345.00
440.00

612.40
2745.60
1372.80
6160.00
8800.00
2310.00
2695.00
15180.00
880.00
40755.80
12226.74
52982.54

5298.30
0.14 741.80
6040.10

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Total
0.00%
Total
3%

D. Add for excise duty


(on 75 percent cost excluding cost of materials)
E. Add for transportation upto work site @
Total

Rs:
Rs:
Rs:
Rs:
Rs:

581955.76
11982.80
52982.54
646921.10
0.00
646921.10
19407.63
666328.73

306

Gates and Allied Works - Item Unit Rates 2014-15

F. Add for contractor's profit and overheads on (A+B


Add 2 leads
Add 1 km lead charges for fabricated parts
Unloading charges of fabricated parts Rs
Total cost for

14%
R

Rs:
19.00 per tonne
63.30 per tonne

2.804 tonne
10.000 t capacity
tonne
Rate per
tonne
capacity of hoist

Rate per

93286.02

106.552
354.986
Rs:
760076.29

Rs:
Rs:

271068.60
76007.60

IRR-GAW-212
New Item 201415-2
OT SLUICE SHUTTERS Screw Gear Hoist Including Platform for below 5 Tons Capacity (Small Gates)
As per Guidelines of Chief Engineer, Central Designs Organization, Hyderabad Specification drawing for
Krishna Delta System
Fabrication, supply, erection, testing and commissioning of Embedded parts consisting of supporting structure,
platform etc. with all accessories for operating canal escape/ regulator gate with all accessories including cost of all
materials, machinery, labour, cutting, bending, aligning, anchoring, welding, finishing etc. complete
as per Specification and approved drawings
(without painting on mechanical cleaning surfaces which are added extra as per schedule of rates
under items in this chapter and add as applicable separately)

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
7
8
9
10
11
12
13

Structural steel angles/ beams / chann


Structural steel plates / flats
Chequered plate
Cast iron Components
Hoist Body/lock nut/Main Nut etc.
Bronze Alloy Steel Components
Thrust Bearings
MS Bolt/Nut/ Washer
Oxygen gas
Acetyline gas
Welding electrodes
Welding electrodes (LH)
Use rate welding holder set
Use rate gas cutting torch set
Sundries

B. MACHINERY:
Sl No
1
2
3
4
5
6

Description

Welding transformer
Fuel / Energy charges
Pug cutting machine
Fuel / Energy charges
Drilling machine
Fuel / Energy charges
Grinding machine
Fuel / Energy charges
Lathe machine (Screw Rod M/C)
Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3
4
5

particulars

Description

Crew for Drilling machine


Crew for Grinding machine
Foreman
Marker / Fabricator / Erector
Gas cutter

UNIT :
Unit
kg
kg
kg

445.78
28.00
144.80

Rate
in Rs.
45.00
46.00
60.00

Kg

83.00

220.00

18260.00

kg
3.00
kg
16.00
cum
21.00
cum
7.00
Nos
200.00
Nos
40.00
Hour
72.00
Hour
36.00
LS
20.00
Total cost of Materials

912.00
90.00
52.00
320.00
11.00
18.00
7.35
23.67
41.00
Rs:

2736.00
1440.00
1092.00
2240.00
2200.00
720.00
529.20
852.18
820.00
60925.48

Rate
in Rs.
16.00
91.30
6.40
3.80
22.50
38.00
22.50
38.00
300.00
41.00
Rs:

Amount
in Rs.
480.00
2739.00
76.80
45.60
180.00
304.00
810.00
1368.00
4800.00
410.00
11213.40

Rate
in Rs.
171.60
171.60
440.00
440.00
385.00

Amount
in Rs.
1372.80
6177.60
880.00
4400.00
1540.00

Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Unit
Hour
Hour
Day
Day
Day

Quantity

0.869 tonne

Quantity
30.00
30.00
12.00
12.00
8.00
8.00
36.00
36.00
16.00
10.00

Quantity
8.00
36.00
2.00
10.00
4.00

Amount
in Rs.
20060.10
1288.00
8688.00

307

Gates and Allied Works - Item Unit Rates 2014-15

6
7
8

Welder ( General )
Mazdoors
Helper fabrication / erection

Day
4.00
Day
6.00
Day
6.00
Total cost of Labour
labour component/unit qty
19750.40
Add contractor's profit and overhead charges
0.14 2765.10
labour component/unit qty (including contractor's profit)
22515.50

385.00
295.00
345.00
Rs:

1540.00
1770.00
2070.00
19750.40

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

60925.48
11213.40
19750.40
91889.28
0.00
91889.28
2756.68
94645.96
13250.43

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0.00%
Total
3%

D. Add for excise duty


(on 75 percent cost excluding cost of materials)
E. Add for transportation upto work site @
Total
F. Add for contractor's profit and overheads on (A+B
Add 2 leads
Add 1 km lead charges for fabricated parts
Unloading charges of fabricated parts Rs
Total cost for

14%
R

19.00 per tonne


63.30 per tonne

0.869 tonne
Rate per tonne

33.022
110.016
Rs:
108039.43
Rs:
124326.20

IRR-GAW-213
New Item 201415-3
OT SLUICE SHUTTERS EM parts for Below 5 Tons capacity (small gates)
As per Guidelines of Chief Engineer, Central Designs Organization, Hyderabad Specification drawing for
Krishna Delta System
Fabrication, supply, erection, testing and commissioning of Embedded parts consisting of sil beam, slide tracks,
seal seats, Guide plates etc. with all accessories including cost of all materials, machinery, labour, etc.
complete as per specifications and approved drawings.
(without painting on mechanical cleaning surfaces which are added extra as per schedule of rates
under items in this chapter and add as applicable separately)
Height of EM parts: 5.4 M

DATA:

Gate Size:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
7
8
9
10

Structural steel angles/ beams / chann


Structural steel plates / flats
Stainless Steel Flats
Oxygen gas
Acetyline gas
Welding electrodes
Welding electrodes (Stainless Steel)
Use rate welding holder set
Use rate gas cutting torch set
Sundries

B. MACHINERY:
Sl No
1
2
3
4
5

particulars

Description

Welding transformer
Fuel / Energy charges
Pug cutting machine
Fuel / Energy charges
Drilling machine
Fuel / Energy charges
Grinding machine
Fuel / Energy charges
Sundries

UNIT :
Unit

Quantity

kg
440.57
kg
869.00
kg
25.12
cum
12.00
cum
4.00
Nos
210.00
Nos
30.00
Hour
62.00
Hour
32.00
LS
3.00
Total cost of Materials

Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Quantity
30.00
30.00
20.00
20.00
4.00
4.00
20.00
20.00
3.00

0.99 X 0.875 M

1.334 tonne
Rate
in Rs.
45.00
46.00
275.00
52.00
320.00
11.00
26.00
7.35
23.67
41.00
Rs:

Amount
in Rs.
19825.65
39974.00
6908.00
624.00
1280.00
2310.00
780.00
455.70
757.49
123.00
73037.84

Rate
in Rs.
16.00
91.30
6.40
3.80
22.50
38.00
22.50
38.00
41.00

Amount
in Rs.
480.00
2739.00
128.00
76.00
90.00
152.00
450.00
760.00
123.00

308

Gates and Allied Works - Item Unit Rates 2014-15

Total hire charges of Machinery


C. LABOUR:
Sl No
1
2
3
4
5
6
7
8

Description

Unit

Quantity

Crew for Drilling machine


Crew for Grinding machine
Foreman
Marker / Fabricator / Erector
Gas cutter
Welder ( General )
Mazdoors
Helper fabrication / erection

Hour
4.00
Hour
20.00
Day
8.00
Day
6.00
Day
2.00
Day
4.00
Day
4.00
Day
8.00
Total cost of Labour
labour component/unit qty
16528.40
Add contractor's profit and overhead charges
0.14 2314.00
labour component/unit qty (including contractor's profit)
18842.40

Rs:

4998.00

Rate
in Rs.
171.60
171.60
440.00
440.00
385.00
385.00
295.00
345.00
Rs:

Amount
in Rs.
686.40
3432.00
3520.00
2640.00
770.00
1540.00
1180.00
2760.00
16528.40

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

73037.84
4998.00
16528.40
94564.24
0.00
94564.24
2836.93
97401.17
13636.16

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0.00%
Total
3%

D. Add for excise duty


(on 75 percent cost excluding cost of materials)
E. Add for transportation upto work site @
Total
F. Add for contractor's profit and overheads on (A+B
Add 2 leads
Add 1 km lead charges for fabricated parts
Unloading charges of fabricated parts Rs
Total cost for

14%
R

19.00 per tonne


63.30 per tonne

50.692
168.884
Rs:
111256.91
Rs:
83401.00

1.334 tonne
Rate per tonne

IRR-GAW-214
New Item 201415 -4
OT SLUICE SHUTTERS for Below 5 Tons capacity (small gates)
As per Guidelines of Chief Engineer, Central Designs Organization, Hyderabad Specification drawing for
Krishna Delta System
Fabrication, supply, erection, testing and commissioning of Sluice Shutters consisting of skin plate, horizontal
and vertical angles, stiffeners, rubber seals, clamps with all accessories for sluice shutters including cost
of all materials, machinery, labour, seal fixing etc., complete as per specifications and approved drawings
(without painting on mechanical cleaning surfaces which are added extra as per schedule of rates
under items in this chapter and add as applicable separately)
Gate Size: 0.99 X 0.875 M
DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
7
8
9
10
11

particulars

Structural steel angles/ beams / chann


Structural steel plates / flats
GI Bolts/Nut/Washer
Rubber Seals
Bottom Seal
Side Seal/ Top Seal
Oxygen gas
Acetyline gas
Welding electrodes
Use rate welding holder set
Use rate gas cutting torch set
Sundries

B. MACHINERY:
Sl No

Description

UNIT :
Unit

63.72
96.50
20.00

Rate
in Rs.
45.00
46.00
130.00

Amount
in Rs.
2867.40
4439.00
2600.00

Rm
0.82
Rm
1.75
cum
15.00
cum
5.00
Nos
110.00
Hour
30.00
Hour
12.00
LS
3.00
Total cost of Materials

759.00
1155.00
52.00
320.00
11.00
7.35
23.67
41.00
Rs:

622.38
2021.25
780.00
1600.00
1210.00
220.50
284.06
123.00
16767.59

kg
kg
kg

Unit

Quantity

0.161 tonne

Quantity

Rate

Amount

309

Gates and Allied Works - Item Unit Rates 2014-15

1
2
3
4
5

Welding transformer
Fuel / Energy charges
Pug cutting machine
Fuel / Energy charges
Drilling machine
Fuel / Energy charges
Grinding machine
Fuel / Energy charges
Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3
4
5
6
7
8

Description

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

14.00
14.00
4.00
4.00
2.00
2.00
4.00
4.00
3.00

Unit

Quantity

Crew for Drilling machine


Crew for Grinding machine
Foreman
Marker / Fabricator / Erector
Gas cutter
Welder ( General )
Mazdoors
Helper fabrication / erection

Hour
2.00
Hour
4.00
Day
2.00
Day
3.00
Day
1.00
Day
4.00
Day
4.00
Day
6.00
Total cost of Labour
labour component/unit qty
8404.60
Add contractor's profit and overhead charges
0.14 1176.60
labour component/unit qty (including contractor's profit)
9581.20

in Rs.
16.00
91.30
6.40
3.80
22.50
38.00
22.50
38.00
41.00
Rs:

in Rs.
224.00
1278.20
25.60
15.20
45.00
76.00
90.00
152.00
123.00
2029.00

Rate
in Rs.
171.60
171.60
440.00
440.00
385.00
385.00
295.00
345.00
Rs:

Amount
in Rs.
343.20
686.40
880.00
1320.00
385.00
1540.00
1180.00
2070.00
8404.60

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

16767.59
2029.00
8404.60
27201.19
0.00
27201.19
816.04
28017.23
3922.41

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0.00%
Total
3%

D. Add for excise duty


(on 75 percent cost excluding cost of materials)
E. Add for transportation upto work site @
Total
F. Add for contractor's profit and overheads on (A+B
Add 2 leads
Add 1 km lead charges for fabricated parts
Unloading charges of fabricated parts Rs
Total cost for

IRR-GAW-3

14%
R

19.00 per tonne


63.30 per tonne

0.161 tonne
Rate per tonne

6.118
20.382
Rs:
Rs:

31966.14
198547.40

SAND BLASTING AND PAINTING AS PER IS:14177-1994

IRR-GAW-3-1 Cleaning gates / hoists / embedded parts/lifting beams etc, to expose fresh metal surface
for painting by sand blasting method as per specifications including cost of all materials, l
abour, machinery, scaffolding, etc., complete with initial lead for sand upto 1 km and all lifts.
DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4

particulars

UNIT : 100
Unit

Quantity

cum
30.00
Hour
8.00
Hour
8.00
LS
5.00
Total
Add 10% towards scaffolding/laddor @
Total cost of Materials
B. MACHINERY:
Sl No
Description
Unit
Quantity
1
2

Sand (Screened)
Use rate of air hose
Use rate of sand blast gun nozzle
Sundries( Rust inhibitive, seive etc )

Air compressor 7 cmm diesel


Fuel / Energy charges
Sand blasting equipment

Hour
Hour
Hour

8.00
8.00
8.00

sqm
Rate
in Rs.
606.00
18.63
3.50
41.00
0.10

Rate
in Rs.
241.30
767.30
110.10

Amount
in Rs.
18180.00
149.00
28.00
205.00
18562.00
1856.20
20418.20
Amount
in Rs.
1930.40
6138.40
880.80

310

Gates and Allied Works - Item Unit Rates 2014-15

Fuel / Energy charges


C. LABOUR:
Sl No
1
2
3

Hour
8.00
Total hire charges of Machinery

Description

Unit

Quantity

Crew for Air compressor


Crew for Sand blasting equipment
mazdoor

Hour
8.00
Hour
8.00
Day
15.00
Total cost of Labour
labour component/unit qty
74.00
Add contractor's profit and overhead charges
0.14 10.40
labour component/unit qty (including contractor's profit)
84.40

0.00

0.00
8949.60

Rate
in Rs.
182.20
189.80
295.00

Amount
in Rs.
1457.60
1518.40
4425.00
7401.00

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

20418.20
8949.60
7401.00
36768.80
0.00
36768.80
1103.06
37871.86
5302.06
43173.92
431.70

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0.00%
Total
3%

D. Add for excise duty


(on 75 percent cost excluding cost of materials)
E. Add for transportation upto work site @
Total
F. Add for contractor's profit and overheads on (A+B
Total cost for

14%
100.00 sqm
Rate per sqm

IRR-GAW-3-2 painting of embedded metal parts and all types of gates, stoplogs,etc, on sand blasted
surfaces with one coat of inorganic zinc silicate (airless spray preferred)70+/- 5
and two super coats with a total thickness of 300 microns
(each 150+/- 5) of solventless coaltar epoxy paint each coat 150 microns ( total 300 microns)
cost of all materials, labour, scaffolding etc., complete with all leads and
all lifts
(Upstream surface of gates portion may be painted with solventless coaltar epoxy brown paint
instead of solventless coaltar black. The rate for coaltar epoxy brown shall be adopted in data
for Upstream side painting)
DATA:

Consider 100 sqm area for painting:


Requirement of materials :
Theoretical spreading rate per one Coat of Paint
25
Assume Losses at 30% of the spreading area (as per field obserations)
Actual Spreading Area
Total time required for 100 Sqm Area

17.50 Sqm/Hr
5.71
Hr
6
Hr

Say

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5

1
2
3

UNIT :

particulars

Unit

Quantity

inorganic zinc silicate


Thinner @ 10%
Solventless Coal tar epoxy paint
Thinner @ 10%
Sundries ( brushes,ladders,platforms
etc )

ltr
ltr
ltr
ltr

12.00
1.20
40.00
4.00

B. MACHINERY:
Sl No

Description

Hire Charges of Airless Spray Gun


Hire Charges of Air Compressor-7
Cmm (diesel)
Fuel Charges of Air Compressor

Sqm/Hr

3.00
Total cost of Materials
Unit

Quantity

Hr
Hr
Hr

100 sqm
Rate
in Rs.
689.00
140.00
271.00
140.00

Amount
in Rs.
8268
168
10840
560

41.00

123
19959.00

Rs:

6.00

Rate
in Rs.
121.40

Amount
in Rs.
728.40

6.00
6.00

241.30
767.30

1447.80
4603.80

Total cost of Machinery

Rs:

6780.00

311

Gates and Allied Works - Item Unit Rates 2014-15

C. LABOUR:
Sl No
1
2
3

Description

Unit

Quantity

Crew Charges of Air Compressor


Painter Class-I
Helper

Day
6.00
Day
20.00
Day
20.00
Total cost of Labour
labour component/unit qty
157.90
Add contractor's profit and overhead charges
0.14 22.10
labour component/unit qty (including contractor's profit)
180.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0
Total
0.03

D. Add for excise duty


(on 75 percent cost excluding cost of materials)
E. Add for transportation upto work site @
Total
F. Add for contractor's profit and overheads on
Total cost fo
100.00 sqm
Rate per sqm

14%

Rs:

Rate
in Rs.
182.20
440.00
295.00
Rs:

Amount
in Rs.
1093.20
8800.00
5900.00
15793.20

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
6133.14
Rs:
Rs:

19959.00
6780.00
15793.20
42532.20
0.00
42532.20
1275.97
43808.17
6133.14
49941.31
499.40

IRR-GAW-3-3
painting of Lifting beams,cat walks and other similar structures-painting hoist machinery,
on sand blasted surfaces with two coats of zinc phosphate primer (airless spray preferred)
40microns/coat and twocoats of alkyd based micaccous iron oxide paint , 65 microns/coat
cost of all materials, labour, scaffolding etc., complete with all leads and
all lifts
DATA:

Consider 100 sqm area for painting:


Requirement of materials :
Theoretical spreading rate per one Coat of Paint
25
Assume Losses at 30% of the spreading area (as per field obserations)
Actual Spreading Area
Total time required for 100 Sqm Area

17.50 Sqm/Hr
5.71
Hr
6
Hr

Say

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5

particulars

zinc phosphate primer


Thinner@10%
alkyd based micaccous iron oxide
paint
Thinner@10%
Sundries ( brushes,ladders,platforms
etc )

B. MACHINERY:
Sl No

Description

Hire Charges of Airless Spray Gun


Hire Charges of Air Compressor-7
Cmm (diesel)
2
3
Fuel Charges of Air Compressor
Total cost of machinery
C. LABOUR:
Sl No
Description
1
2
3

Crew Charges of Air Compressor


Painter Class-I
Helper

Sqm/Hr

UNIT :
Unit

Quantity

ltr
ltr
ltr
ltr

100 sqm

28.00
2.80

Rate
in Rs.
223.00
140.00

Amount
in Rs.
6244
392

20.00
2.00

196.00
140.00

3920
280

3.00
Total cost of Materials

41.00

123
10959.00

Unit

Quantity

Hr
Hr
Hr

Unit

Rs:

6.00

Rate
in Rs.
121.40

Amount
in Rs.
728.40

6.00
6.00

241.30
767.30
RS:

1447.80
4603.80
6780.00

Rs:

Amount
in Rs.
1093.20
6600.00
4425.00
12118.20

Quantity

Day
6.00
Day
15.00
Day
15.00
Total cost of Labour

Rate
in Rs.
182.20
440.00
295.00

312

Gates and Allied Works - Item Unit Rates 2014-15

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

121.20
0.14 17.00
138.20

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0
Total
0.03

D. Add for excise duty


(on 75 percent cost excluding cost of materials)
E. Add for transportation upto work site @
Total
F. Add for contractor's profit and overheads on (A+B
Total cost for

IRR-GAW-3-4

.
DATA:

14%
100.00 sqm
Rate per sqm

Rs:

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
4305.41
Rs:
Rs:

10959.00
6780.00
12118.20
29857.20
0.00
29857.20
895.72
30752.92
4305.41
35058.32
350.60

HOISTS:STRUCTURAL COMPONENTS--painting structurals on sand blasted surfaces with


two coats of zinc phosphate primer (airless spray preferred) 40microns/coat
and one coat 65+/-5 of alkyd based micaccous iron oxide paint
followed by two coats of synthetic enamel paint 25 microns/coat
cost of all materials, labour, scaffolding etc., complete with all leads and
all lifts
Consider 100 sqm area for painting:
Requirement of materials :
Theoretical spreading rate per one Coat of Paint
25
Assume Losses at 30% of the spreading area (as per field obserations)
Actual Spreading Area
Total time required for 100 Sqm Area

17.50 Sqm/Hr
5.71
Hr
6
Hr

Say

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
7

1
2
3

Unit

Quantity

zinc phosphate primer


Thinner@10%
alkyd based micaccous iron oxide
paint
Thinner@10%
synthetic enamel paint
Thinner@10%
Sundries ( brushes,ladders,platforms
etc )

ltr
ltr
ltr
ltr
ltr
ltr

Description

Hire Charges of Airless Spray Gun


Hire Charges of Air Compressor-7
Cmm (diesel)
Fuel Charges of Air Compressor

C. LABOUR:
Sl No
1
2
3

UNIT :

particulars

B. MACHINERY:
Sl No

Description

Crew Charges of Air Compressor


Painter Class-I
Helper

Sqm/Hr

100 sqm

28.00
2.80

Rate
in Rs.
223.00
140.00

Amount
in Rs.
6244
392

15.00
1.50
17.00
1.70

196.00
140.00
240.00
140.00

2940
210
4080
238

3.00
Total cost of Materials

41.00

123
14227.00

Unit

Quantity

Hr

6.00

Hr
6.00
Hr
6.00
Total cost of Machinery
Unit

Quantity

Day
6.00
Day
20.00
Day
20.00
Total cost of Labour
labour component/unit qty
157.90
Add contractor's profit and overhead charges
0.14 22.10
labour component/unit qty (including contractor's profit)
180.00

Rs:
Rate
in Rs.
121.40

Amount
in Rs.
728.40

241.30
767.30
Rs:

1447.80
4603.80
6780.00

Rs:

Amount
in Rs.
1093.20
8800.00
5900.00
15793.20

Rate
in Rs.
182.20
440.00
295.00

ABSTRACT:

313

Gates and Allied Works - Item Unit Rates 2014-15

A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
5306.59
Rs:
Rs:

Total
0
Total
0.03

D. Add for excise duty


(on 75 percent cost excluding cost of materials)
E. Add for transportation upto work site @
Total
F. Add for contractor's profit and overheads on (A+B
Total cost for

IRR-GAW-3-5

DATA:

14%
100.00 sqm
Rate per sqm

Rs:

14227.00
6780.00
15793.20
36800.20
0.00
36800.20
1104.01
37904.21
5306.59
43210.79
432.10

HOISTS:machineryCOMPONENTS--painting hoist machinery, on sand blasted surfaces with


one coats of zinc phosphate primer (airless spray preferred) 50microns/coat
and three coats of aluminium paint or synthetic enamel , 25 microns/coat
cost of all materials, labour, scaffolding etc., complete with all leads and
all lifts
Consider 100 sqm area for painting:
Requirement of materials :
Theoretical spreading rate per one Coat of Paint
25
Assume Losses at 30% of the spreading area (as per field obserations)
Actual Spreading Area
Total time required for 100 Sqm Area

17.50 Sqm/Hr
5.71
Hr
6
Hr

Say

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5

1
2
3

Unit

Quantity

zinc phosphate primer


Thinner@10%
aluminium paint or synthetic enamel
per coat
Thinner@10%
Sundries ( brushes,ladders,platforms
etc )

ltr
ltr
ltr
ltr

Description

Hire Charges of Airless Spray Gun


Hire Charges of Air Compressor-7
Cmm (diesel)
Fuel Charges of Air Compressor

C. LABOUR:
Sl No
1
2
3

UNIT :

particulars

B. MACHINERY:
Sl No

Description

100 sqm

14.00
1.40

Rate
in Rs.
223.00
140.00

Amount
in Rs.
3122
196

26.00
2.60

240.00
140.00

6240
364

3.00
Total cost of Materials

41.00
Rs:

123
10045.00

Rate
in Rs.
121.40

Amount
in Rs.
728.40

241.30
767.30

1447.80
4603.80
6780.00

Rate
in Rs.
182.20
440.00
295.00

Amount
in Rs.
1093.20
8800.00
5900.00
15793.20

Unit

Quantity

Hr

6.00

Hr
6.00
Hr
6.00
Total cost of Machinery
Unit

Quantity

Crew Charges of Air Compressor


Painter Class-I
Helper

Day
6.00
Day
20.00
Day
20.00
Total cost of Labour
labour component/unit qty
157.90
Add contractor's profit and overhead charges
0.14 22.10
labour component/unit qty (including contractor's profit)
180.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for excise duty
(on 75 percent cost excluding cost of materials)
E. Add for transportation upto work site @

Sqm/Hr

Total
0
Total
0.03

Rs:

Rs:

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

10045.00
6780.00
15793.20
32618.20
0.00
32618.20
978.55

314

Gates and Allied Works - Item Unit Rates 2014-15

Total
F. Add for contractor's profit and overheads on (A+B
Total cost for

IRR-GAW-4

14%
100.00 sqm
Rate per sqm

Rs:

Rs:
4703.54
Rs:
Rs:

33596.75
4703.54
38300.29
383.00

PAINTING WITHOUT SAND BLASTING

IRR-GAW-4-1 E.M Parts OF ALL TYPES OF GATES


Surface cleaning of metal surfaces by chemical cleaners and then by hand and power tool cleaners and removing
dust. After cleaning,applying primary coat with one coat of Protective Mastic to athickness of 70+5 microns
,followed by finishing coats 2 coats with Solventless Coal tar epoxy each coat with a DFT of 150+5 microns
and total DFT of all coats including Primary coat should not be less than 350 microns with material, labour and all
accessories with all leads and lifts
(in respect of Heavily rusted (30 to 40% rusted) surfaces)
DATA:

Consider 100 sqm area for painting:


Requirement of materials :
Theoretical spreading rate per one Coat of Paint
25
Assume Losses at 30% of the spreading area (as per field obserations)
Actual Spreading Area
Total time required for 100 Sqm Area

17.50 Sqm/Hr
5.71
Hr
6
Hr

Say
DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
7

Rust cleaner / inhibitor


Protective Mastic
Thinner@10%
Solventless Coal tar epoxy paint
Thinner@10%
Wire brush
Sundries

B. MACHINERY:
Sl No
1
2
3

Unit

Quantity

ltr
13
ltr
25
ltr
2.5
ltr
40.00
ltr
4
Nos
2
LS
3.00
Total cost of Materials

Description

Hire Charges of Airless Spray Gun


Hire Charges of Air Compressor-7
Cmm (diesel)
Fuel Charges of Air Compressor
Total cost of Machinery

C. LABOUR:
Sl No
1
2
3

UNIT :

particulars

Description

Unit

Quantity

Hr

100.000 Sq.m
Rate
in Rs.
140
483
140.00
271.00
140.00
41.00
41.00
Rs:

Amount
in Rs.
1820.00
12075.00
350.00
10840.00
560.00
82.00
123.00
25850.00

6.00

Rate
in Rs.
121.40

Amount
in Rs.
728.40

Hr
Hr

6.00
6.00

241.30
767.30

1447.80
4603.80
6780.00

Unit

Quantity

Rate
in Rs.
182.20
440.00
295.00

Amount
in Rs.
1093.20
8800.00
5900.00
15793.20

Crew Charges of Air Compressor


Painter Class-I
Helper

Day
6.00
Day
20.00
Day
20.00
Total cost of Labour
labour component/unit qty
157.90
Add contractor's profit and overhead charges
0.14 22.10
labour component/unit qty (including contractor's profit)
180.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0.00%
Total
3%

D. Add for excise duty


(on 75 percent cost excluding cost of materials)
E. Add for transportation upto work site @
Total
F. Add for contractor's profit and overheads on (A+B

Sqm/Hr

14%

Rs:

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

25850.00
6780.00
15793.20
48423.20
0.00
48423.20
1452.70
49875.90
6982.63

315

Gates and Allied Works - Item Unit Rates 2014-15

Total cost for

100.00 sqm
Rate per sq.meter

Rs:
Rs:

56858.52
568.60

IRR-GAW-4-3 HOIST BRIDGES ,HOISTING EQUIPMENT AND CRANES,Etc,


Surface cleaning of metal surfaces by chemical cleaners and then by hand and power tool cleaners
and removing dust. After cleaning,applying primary coat with two coats of Zinc chromite red oxide primer ,
followed by finishing coats 3 coats with synthetic enamel paint with material, labour,and all accessories
with all leads and lifts where surface cleaning by sand blasting is not feasible and based on specific
recommendations of designers, it is to adopt surface preperation done manually by hand and power tool
after cleaning by chemical treatment to remove grease, rust, scaling etc., and to form phasphate coating
to prevent further rusting, before applying primer painting.
DATA:

Consider 100 sqm area for painting:


Requirement of materials :
Theoretical spreading rate per one Coat of Paint
25
Assume Losses at 30% of the spreading area (as per field obserations)
Actual Spreading Area
Total time required for 100 Sqm Area

17.50 Sqm/Hr
5.71
Hr
6
Hr

Say

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
7

Rust cleaner / inhibitor


Zinc Chromite Red Oxide Primer
Thinner@10%
Synthetic enamel Paint
Thinner@10%
Wire brush
Sundries

B. MACHINERY:
Sl No
1
2
3

C. LABOUR
Sl No
1
2
3

UNIT :

particulars

Unit

Hire Charges of Airless Spray Gun


Hire Charges of Air Compressor-7
Cmm (diesel)
Fuel Charges of Air Compressor

Quantity

ltr
13
ltr
28
ltr
2.8
ltr
17.00
ltr
1.7
Nos
2
LS
3.00
Total cost of Materials

Description

Unit

Quantity

Hr

6.00

Hr
6.00
Hr
6.00
Total cost of Machinery

Description

Unit

Quantity

Crew Charges of Air Compressor


Painter Class-I
Helper

Day
6.00
Day
20.00
Day
20.00
Total cost of Labour
labour component/unit qty
157.90
Add contractor's profit and overhead charges
0.14 22.10
labour component/unit qty (including contractor's profit)
180.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0.00%
Total
3%

D. Add for excise duty


(on 75 percent cost excluding cost of materials)
E. Add for transportation upto work site @
Total
F. Add for contractor's profit and overheads on (A+B

Sqm/Hr

14%

100.000 Sq.m
Rate
in Rs.
140
175
140.00
240.00
140.00
41.00
41.00

Amount
in Rs.
1820.00
4900.00
392.00
4080.00
238.00
82.00
123.00
11635.00

Rate
in Rs.
121.40

Amount
in Rs.
728.40

241.30
767.30

1447.80
4603.80
6780.00

Rate
in Rs.
182.20
440.00
295.00

Amount
in Rs.
1093.20
8800.00
5900.00
15793.20

Rs.
Rs.
Rs.
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

11635.00
6780.00
15793.20
34208.20
0.00
34208.20
1026.25
35234.45
4932.82

316

Gates and Allied Works - Item Unit Rates 2014-15

Total cost for

100.00 sqm
Rate per sq.meter

Rs:

40167.27
401.70

WALK WAYS( CAT WALKS), LIFTING BEAMS,etc,


IRR-GAW-4-4 Surface cleaning of metal surfaces by chemical cleaners and then by hand and power tool cleaners
and removing dust. After cleaning,applying primary coat with one coat of Zinc rich epoxy primer to
a thickness of 40 microns ,followed by finishing coats 2 coats with Solventless Coal tar epoxy with material,
labour and all accessories with all leads and lifts
DATA:

Consider 100 sqm area for painting:


Requirement of materials :
Theoretical spreading rate per one Coat of Paint
25
Assume Losses at 30% of the spreading area (as per field obserations)
Actual Spreading Area
Total time required for 100 Sqm Area

17.50 Sqm/Hr
5.71
Hr
6
Hr

Say
DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
7

Rust cleaner / inhibitor


Zinc rich epoxy primer
Thinner@10%
Solvetnless Coal tar epoxy paint
Thinner@10%
Wire brush
Sundries

B. MACHINERY:
Sl No
1
2
3

1
2
3

Unit

Quantity

ltr
13
ltr
14
ltr
1.4
ltr
40
ltr
4
Nos
2
LS
3
Total cost of Materials

Description

Hire Charges of Airless Spray Gun


Hire Charges of Air Compressor-7
Cmm (diesel)
Fuel Charges of Air Compressor

C. LABOUR:
Sl No

UNIT :

particulars

Unit

Quantity

Hr

6.00

Hr
6.00
Hr
6.00
Total cost of Machinery

Description

Unit

Quantity

Crew Charges of Air Compressor


Painter Class-I
Helper

Day
6.00
Day
13.00
Day
13.00
Total cost of Labour
labour component/unit qty
106.50
Add contractor's profit and overhead charges
0.14 14.90
labour component/unit qty (including contractor's profit)
121.40
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0.00%
Total
3%

D. Add for excise duty


(on 75 percent cost excluding cost of materials)
E. Add for transportation upto work site @
Total
F. Add for contractor's profit and overheads on (A+B
Total cost for

Sqm/Hr

14%
100.00 sqm
Rate per sq.meter

100.000 Sq.m
Rate
in Rs.
140
689
140.00
271
140.00
41
41
Rs:

Amount
in Rs.
1820.00
9646.00
196.00
10840.00
560.00
82.00
123.00
23267.00

Rate
in Rs.
121.40

Amount
in Rs.
728.40

241.30
767.30
Rs:

1447.80
4603.80
6780.00

Rs:

Amount
in Rs.
1093.20
5720.00
3835.00
10648.20

Rate
in Rs.
182.20
440.00
295.00

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

23267.00
6780.00
10648.20
40695.20
0.00
40695.20
1220.86
41916.06
5868.25
47784.30
477.80

317

CHAPTER-VI

Preliminary and Maintenance Works - Item Unit Rates 2014-15

PRELIMINARY AND MAINTENANCE WORKS - Standard Data


(STORED WITH E-N-C & TO INCORPORATE CHANGES YEARLY/ AS NEEDED)
For the Year:2014-15
Index- code
IRR-PMW

PRELIMINARY & MAINTENANCE WORKS - DATA RATES

Directions to add Seigniorage Charges and Additional Lead Charges


Seigniorage Charges:
1. The unit rate for work item in the Standard Data is exclusive of Seigniorage Charges wherever applicable.
2. The appropriate Seigniorage Charges for relevant materials are to be added to the Unit rate of work item while preparing
the estimate. (i.e., to the data itself)
3. The Provision towards Contractor's Profit and Overhead charges should not be operated on the Seigniorage Charges
while adding Seigniorage Charges to the data in the estimate
Additional Lead and Lift Charges:
1. Unless otherwise specified the basic rates are inclusive of all lifts.
2. For concrete, masonry and reinforcement items wherever initial lead of 1km is considered in the basic rate,
the additional lead as follows:
Additional lead charges for Cement, Steel, sand, coarse aggregate, stones and stone chips shall be worked out for total
lead involved and 1 km lead charges included in basic rate shall be deducted from total lead charges. No loading and
unloading charges shall be allowed for any item.
In case of Cement and Steel, Loading and unloading charges are already added in the work item while arriving the unit rate
and hence should not be added again
Example:
Total lead for sand from approved sand quarry :
15 Km
Initial lead included in the basic rate in the SR :
1 Km
Lead chargRs.
84.10
Additional lead charges :
Lead charges for next 10Rs.
126
Total lead charges for 15Rs.
210.10
Less 1 km initial lead chaRs.
31.50 (-)
Net additional lead chargRs.
178.60

3. The Leads for Steel and Cement shall be from the nearest market place to the Project area
4. For earth/rockfill embankments wherever initial lead of 1km is considered in the basic rate, the additional lead
charges are to be added as follows:
Additional lead charges for Earth, Murrum etc., shall be worked out for total lead involved and 1 km lead charges included
in basic rate shall be deducted from total lead charges. No loading and unloading charges shall be allowed for any item.
(same as above)
Example:
Total lead for earth from approved borrow area :
15 Km
Initial lead included in the basic rate in the SR :
1 Km
Lead chargRs.
84.10
Additional lead charges :
Lead charges for next 10Rs.
126
Total lead charges for 15Rs.
210.10
Less 1 km initial lead chaRs.
31.50 (-)
Net additional lead chargRs.
178.60
5. The initial lead up to 50 m as mentioned in some standard data items is meant for manual lead within the working area.
For conveyance of materials, the lead required from quarry/Borrow area/ Dump Area to worksite shall be added to the
data without deducting the 50 m initial lead charges

PMW - Work Items


IRR-PMW-1
IRR-PMW-1-1

JUNGLE CLEARANCE :
Clearing thin jungle growth ( more than 50 percent open space ) including bushes
upto 30 cm / parthenium and other weeds including burning or disposing off the same
as directed etc., complete.

DATA:

RATE ANALYSIS

UNIT :

1000 sqm

A. MATERIALS:

318

Sl No

particulars

NIL

Unit

Preliminary and Maintenance Works - Item Unit Rates 2014-15

Quantity

Rate
in Rs.

0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
370.00
295.00
Rs:

Amount
in Rs.
185.00
885.00
1070.00

0.00
0.00
Total cost of Materials

B. MACHINERY:
Sl No

Description

Unit

Quantity

NIL

Rate
in Rs.

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2

Description

Unit

Quantity

work inspector
mazdoor

Day
Day
Total cost of Labour
labour component/unit qty
1.10
Add contractor's profit and overhead charges
0.14 0.20
labour component/unit qty (including contractor's profit)
1.30

0.50
3.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:

Total
D. Add for contractor's profit and overheads on
(A+B+C)
14.00% Rs:
Total cost for
1000.00 sqm
Rs:
Rate per
sqm
(A+B+C+D)/1000.0
Rs.

IRR-PMW-1-2

0.00
0.00
1070.00
1070.00
149.8
1219.80
1.20

Clearing thick jungle growth ( less than 50 percent open space ) including bushes
upto 30 cm / parthenium and other weeds including burning or disposing off the same as
directed etc., complete.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Quantity

NIL

1000 sqm
Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
370.00
295.00
Rs:

Amount
in Rs.
185.00
1475.00
1660.00

0.00
0.00
Total cost of Materials

B. MACHINERY:
Sl No

Description

Unit

Quantity

NIL

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2

Description

work inspector
mazdoor

Unit

Day
Day
Total cost of Labour
labour component/unit qty
1.70
Add contractor's profit and overhead charges
0.14 0.20
labour component/unit qty (including contractor's profit)
1.90

Quantity
0.50
5.00

Rate
in Rs.

ABSTRACT:

319

Preliminary and Maintenance Works - Item Unit Rates 2014-15

A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:

Total

0.00
0.00
1660.00
1660.00

D. Add for contractor's profit and overheads on


(A+B+C)
14.00% Rs:
Total cost for
1000.00 sqm
Rs:
Rate per
sqm
(A+B+C+D)/1000.0
Rs.

IRR-PMW-1-3

232.4
1892.40
1.90

Removing stumps, tree roots, roots of bamboo clusters etc., upto 1.50 m girth
including excavation, stacking the materials neatly and levelling the surface etc., complete with
initial lead upto 50 m and all lifts.

DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :

Unit

Quantity

NIL

18 Nos.

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
370.00
295.00
Rs:

Amount
in Rs.
92.50
590.00
682.50

0.00
0.00
Total cost of Materials

B. MACHINERY:
Sl No

Description

Unit

Quantity

NIL

Rate
in Rs.

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2

Description

Unit

Quantity

work inspector
mazdoor

Day
Day
Total cost of Labour
labour component/unit qty
37.90
Add contractor's profit and overhead charges
0.14 5.30
labour component/unit qty (including contractor's profit)
43.20

0.25
2.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:

Total

0.00
0.00
682.50
682.50

D. Add for contractor's profit and overheads on


(A+B+C)
14.00% Rs:
Total cost for
18.00 Nos.
Rs:
Rate per each
(A+B+C+D)/18.0
Rs.

IRR-PMW-1-4

95.55
778.05
43.20

Removing stumps, tree roots, roots of bamboo cluster etc., with girth above 1.50 m
and upto 3.0 m including excavation, stacking the materials neatly and levelling the area etc.,
complete with initial lead upto 50 m and all lifts.

DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1

particulars

UNIT :

Unit

NIL

Quantity

8 Nos.

Rate
in Rs.

0.00
0.00

0.00
0.00
Rs:

Total cost of Materials


B. MACHINERY:
Sl No

Description

Unit

Quantity

Rate

Amount
in Rs.
0.00
0.00
0.00

Amount

320

Preliminary and Maintenance Works - Item Unit Rates 2014-15

in Rs.

NIL

0.00
0.00
Rs:

in Rs.
0.00
0.00
0.00

Rate
in Rs.
370.00
295.00
Rs:

Amount
in Rs.
92.50
590.00
682.50

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2

Description

Unit

Quantity

work inspector
mazdoor

Day
Day
Total cost of Labour
labour component/unit qty
85.31
Add contractor's profit and overhead charges
0.14 11.94
labour component/unit qty (including contractor's profit)
97.30

0.25
2.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:

Total

0.00
0.00
682.50
682.50

D. Add for contractor's profit and overheads on


(A+B+C)
14.00% Rs:
Total cost for
8.00 Nos.
Rs:
Rate per each
(A+B+C+D)/8.0
Rs.

IRR-PMW-1-5

95.55
778.10
97.30

Removing stumps, tree roots, roots of bamboo cluster etc., with girth
above 3.0 m and upto 5.0 m including excavation, stacking the materials neatly and levelling
the area etc., complete with initial lead upto 50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :

Unit

Quantity

NIL

5 Nos.

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
370.00
295.00
Rs:

Amount
in Rs.
185.00
1180.00
1365.00

0.00
0.00
Total cost of Materials

B. MACHINERY:
Sl No

Description

Unit

Quantity

NIL

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2

Description

Unit

Quantity

work inspector
mazdoor

Day
Day
Total cost of Labour
labour component/unit qty
273.00
Add contractor's profit and overhead charges
0.14 38.20
labour component/unit qty (including contractor's profit)
311.20
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on
(A+B+C)
14.00% Rs:
Total cost for
5.00 Nos.
Rs:
Rate per each
(A+B+C+D)/5.0
Rs.

0.50
4.00

Rs:
Rs:
Rs:
Rs:

Rate
in Rs.

0.00
0.00
1365.00
1365.00
191.1
1556.10
311.20

321

IRR-PMW-1-6

Preliminary and Maintenance Works - Item Unit Rates 2014-15

Additional rate for every 0.5 m increase in girth of tree stump / stumps of bamboo cluster
beyond 5 m.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :

Unit

Quantity

NIL

7 Nos.

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
370.00
295.00
Rs:

Amount
in Rs.
81.40
258.13
339.53

0.00
0.00
Total cost of Materials

B. MACHINERY:
Sl No

Description

Unit

Quantity

NIL

Rate
in Rs.

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2

Description

Unit

Quantity

work inspector
mazdoor

Day
Day
Total cost of Labour
labour component/unit qty
48.50
Add contractor's profit and overhead charges
0.14 6.80
labour component/unit qty (including contractor's profit)
55.30

0.22
0.88

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:

Total
D. Add for contractor's profit and overheads on
(A+B+C)
14.00% Rs:
Total cost for
7.00 Nos.
Rs:
Rate per each
(A+B+C+D)/7.0
Rs.

IRR-PMW-1-7

0.00
0.00
339.53
339.53
47.5335
387.06
55.30

Cutting and stacking bamboos excluding removing stumps and roots etc., complete with
initial lead upto 50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :

Unit

Quantity

NIL

150 Nos.

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
370.00

Amount
in Rs.
185.00

0.00
0.00
Total cost of Materials

B. MACHINERY:
Sl No

Description

Unit

Quantity

NIL

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
1

Description

work inspector

Unit
Day

Quantity
0.50

Rate
in Rs.

322

mazdoor

Day
Total cost of Labour
labour component/unit qty
11.07
Add contractor's profit and overhead charges
0.14 1.55
labour component/unit qty (including contractor's profit)
12.60

Preliminary and Maintenance Works - Item Unit Rates 2014-15

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total

5.00

295.00
Rs:

Rs:
Rs:
Rs:
Rs:

0.00
0.00
1660.00
1660.00

D. Add for contractor's profit and overheads on


(A+B+C)
14.00% Rs:
Total cost for
150.00 Nos.
Rs:
Rate per each
(A+B+C+D)/150.0
Rs.

IRR-PMW-1-8

232.4
1892.40
12.60

Cutting and removing jauliflora bushes upto 1.5 m girth excluding removal of stumps and
including burning or disposing off the materials as directed with initial lead upto 50 m and all
lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :

Unit

Quantity

NIL

100 Nos.

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
370.00
295.00
Rs:

Amount
in Rs.
185.00
885.00
1070.00

0.00
0.00
Total cost of Materials

B. MACHINERY:
Sl No

Description

Unit

Quantity

NIL

Rate
in Rs.

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2

Description

Unit

Quantity

Day
Day
Total cost of Labour
labour component/unit qty
10.70
Add contractor's profit and overhead charges
0.14 1.50
labour component/unit qty (including contractor's profit)
12.20

work inspector
mazdoor

0.50
3.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:

Total
D. Add for contractor's profit and overheads on
(A+B+C)
14.00% Rs:
Total cost for
100.00 Nos
Rs:
Rate per each
(A+B+C+D)/100.0
Rs.

IRR-PMW-1-9

1475.00
1660.00

0.00
0.00
1070.00
1070.00
149.8
1219.80
12.20

Cutting and removing jauliflora bushes above 1.5 m upto 3.0 m girth excluding
removal of stumps and including burning or disposing off the materials as directed
with initial lead upto 50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :

Unit

Quantity

50 Nos

Rate
in Rs.

Amount
in Rs.

323

Preliminary and Maintenance Works - Item Unit Rates 2014-15

NIL

0.00
0.00

0.00
0.00
Rs:

0.00
0.00
0.00

0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
370.00
295.00
Rs:

Amount
in Rs.
185.00
885.00
1070.00

Total cost of Materials


B. MACHINERY:
Sl No

Description

Unit

Quantity

NIL

Rate
in Rs.

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2

Description

Unit

Quantity

work inspector
mazdoor

Day
Day
Total cost of Labour
labour component/unit qty
21.40
Add contractor's profit and overhead charges
0.14 3.00
labour component/unit qty (including contractor's profit)
24.40

0.50
3.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:

Total

0.00
0.00
1070.00
1070.00

D. Add for contractor's profit and overheads on


(A+B+C)
14.00% Rs:
Total cost for
50.00 Nos
Rs:
Rate per each
(A+B+C+D)/50.0
Rs.

IRR-PMW-1-10

149.8
1219.80
24.40

Cutting trees above 0.3 m and upto 0.6 m girth excluding removal of stumps and including
stacking the materials neatly as directed with initial lead upto 50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

UNIT :

particulars

Use rate of ropes etc

Unit

Quantity

LS

0.25
0.00

Total cost of Materials


B. MACHINERY:
Sl No

Description

Unit

Quantity

NIL

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2

Description

Unit

work inspector
mazdoor

Day
Day
Total cost of Labour
labour component/unit qty
69.80
Add contractor's profit and overhead charges
0.14 9.80
labour component/unit qty (including contractor's profit)
79.60
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total

Quantity
0.25
3.00

Rs:
Rs:
Rs:
Rs:

14 Nos.

Rate
in Rs.
150.00
0.00
Rs:

Amount
in Rs.
37.50
0.00
37.50

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
370.00
295.00
Rs:

Amount
in Rs.
92.50
885.00
977.50

37.50
0.00
977.50
1015.00

324

Preliminary and Maintenance Works - Item Unit Rates 2014-15

D. Add for contractor's profit and overheads on


(A+B+C)
14.00% Rs:
Total cost for
14.00 Nos.
Rs:
Rate per each
(A+B+C+D)/14.0
Rs.

IRR-PMW-1-11

142.1
1157.10
82.70

Cutting trees above 0.6 m and upto 1.2 m girth excluding removal of stumps and including
stacking the materials neatly as directed with initial lead upto 50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

UNIT :

particulars

Use rate of ropes etc

Unit

Quantity

LS

0.25
0.00

Total cost of Materials


B. MACHINERY:
Sl No

Description

Unit

Quantity

NIL

4 Nos.

Rate
in Rs.
150.00
0.00
Rs:

Amount
in Rs.
37.50
0.00
37.50

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
370.00
295.00
Rs:

Amount
in Rs.
92.50
885.00
977.50

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2

Description

Unit

Quantity

work inspector
mazdoor

Day
Day
Total cost of Labour
labour component/unit qty
244.40
Add contractor's profit and overhead charges
0.14 34.20
labour component/unit qty (including contractor's profit)
278.60

0.25
3.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:

Total

37.50
0.00
977.50
1015.00

D. Add for contractor's profit and overheads on


(A+B+C)
14.00% Rs:
Total cost for
4.00 Nos.
Rs:
Rate per each
(A+B+C+D)/4.0
Rs.

IRR-PMW-1-12

142.1
1157.10
289.30

Cutting trees above 1.2 m and upto 1.8 m girth excluding removal of stumps and including
stacking the materials neatly as directed with initial lead upto 50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

UNIT :

particulars

Use rate of ropes etc

Unit

Quantity

LS

0.25
0.00

Total cost of Materials


B. MACHINERY:
Sl No
1

Description

Unit

Quantity

NIL

0.00
0.00
Total hire charges of Machinery

2 Nos.

Rate
in Rs.
150.00
0.00
Rs:

Amount
in Rs.
37.50
0.00
37.50

Rate
in Rs.

Amount
in Rs.
0.00
0.00
0.00

0.00
0.00
Rs:

C. LABOUR:

325

Sl No
1
2

Description

Unit

Preliminary and Maintenance Works - Item Unit Rates 2014-15

Quantity

work inspector
mazdoor

Day
Day
Total cost of Labour
labour component/unit qty
488.80
Add contractor's profit and overhead charges
0.14 68.40
labour component/unit qty (including contractor's profit)
557.20

0.25
3.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rate
in Rs.
370.00
295.00
Rs:

Rs:
Rs:
Rs:
Rs:

Total

37.50
0.00
977.50
1015.00

D. Add for contractor's profit and overheads on


(A+B+C)
14.00% Rs:
Total cost for
2.00 Nos.
Rs:
Rate per each
(A+B+C+D)/2.0
Rs.

IRR-PMW-1-13

142.1
1157.10
578.60

Cutting trees above 1.8 m and upto 2.4 m girth excluding removal of stumps and including
stacking the materials neatly as directed with initial lead upto 50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

UNIT :

particulars

Use rate of ropes etc

Unit

Quantity

LS

0.25
0.00

Total cost of Materials


B. MACHINERY:
Sl No

Description

Unit

Quantity

NIL

1 No.

Rate
in Rs.
150.00
0.00
Rs:

Amount
in Rs.
37.50
0.00
37.50

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
370.00
295.00
Rs:

Amount
in Rs.
92.50
885.00
977.50

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2

Description

Unit

Quantity

Day
Day
Total cost of Labour
labour component/unit qty
977.50
Add contractor's profit and overhead charges
0.14 136.90
labour component/unit qty (including contractor's profit)
1114.40

work inspector
mazdoor

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total

0.25
3.00

Rs:
Rs:
Rs:
Rs:

D. Add for contractor's profit and overheads on


(A+B+C)
14.00% Rs:
Total cost for
1.00 No.
Rs:
Rate per each
(A+B+C+D)/1.0
Rs.

IRR-PMW-1-14

DATA:

Amount
in Rs.
92.50
885.00
977.50

37.50
0.00
977.50
1015.00
142.1
1157.10
1157.10

Cutting trees above 2.4 m and upto 3.0 m girth excluding removal of stumps and including
stacking the materials neatly as directed with initial lead upto 50 m and all lifts.

RATE ANALYSIS

UNIT :

1 Nos.

326

A. MATERIALS:
Sl No
1

Preliminary and Maintenance Works - Item Unit Rates 2014-15

particulars

Use rate of ropes etc

Unit

Quantity

LS

0.50
0.00

Total cost of Materials

B. MACHINERY:
Sl No

Description

Unit

Quantity

NIL

Rate
in Rs.
150.00
0.00
Rs:

Amount
in Rs.
75.00
0.00
75.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
370.00
295.00
Rs:

Amount
in Rs.
92.50
1475.00
1567.50

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2

Description

Unit

Quantity

work inspector
mazdoor

Day
Day
Total cost of Labour
labour component/unit qty
1567.50
Add contractor's profit and overhead charges
0.14 219.50
labour component/unit qty (including contractor's profit)
1787.00

0.25
5.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:

Total
D. Add for contractor's profit and overheads on
(A+B+C)
14.00% Rs:
Total cost for
1.00 Nos.
Rs:
Rate per each
(A+B+C+D)/1.0
Rs.

IRR-PMW-1-15

75.00
0.00
1567.50
1642.50
229.95
1872.45
1872.50

Additional rate for cutting tree for every 0.5 m increase in girth of tree beyond 3 m.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

UNIT :

particulars

Use rate of ropes etc

Unit

Quantity

LS

0.15
0.00

Total cost of Materials

B. MACHINERY:
Sl No

Description

Unit

Quantity

NIL

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2

Description

work inspector
mazdoor

Unit

Day
Day
Total cost of Labour
labour component/unit qty
553.30
Add contractor's profit and overhead charges
0.14 77.50
labour component/unit qty (including contractor's profit)
630.80

Quantity
0.10
1.75

1 No

Rate
in Rs.
150.00
0.00
Rs:

Amount
in Rs.
22.50
0.00
22.50

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
370.00
295.00
Rs:

Amount
in Rs.
37.00
516.25
553.25

327

Preliminary and Maintenance Works - Item Unit Rates 2014-15

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:

Total

22.50
0.00
553.25
575.75

D. Add for contractor's profit and overheads on


14.00% Rs:
(A+B+C)
Total cost for
1.00 No
Rs:
Rate per each
(A+B+C+D)/1.0
Rs.

IRR-PMW-1-16

80.605
656.36
656.40

Cutting and burning or disposing off Apu / Jondu from marshy areas as directed with
initial lead upto 50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :

Unit

Quantity

NIL

1000 sqm

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
370.00
295.00
Rs:

Amount
in Rs.
370.00
3540.00
3910.00

0.00
0.00
Total cost of Materials

B. MACHINERY:
Sl No

Description

Unit

Quantity

NIL

Rate
in Rs.

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2

Description

Unit

Quantity

work inspector
mazdoor

Day
Day
Total cost of Labour
labour component/unit qty
3.90
Add contractor's profit and overhead charges
0.14 0.50
labour component/unit qty (including contractor's profit)
4.40

1.00
12.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:

Total
D. Add for contractor's profit and overheads on
(A+B+C)
14.00% Rs:
Total cost for
1000.00 sqm
Rs:
Rate per sqm
(A+B+C+D)/1000.0
Rs.

IRR-PMW-2
IRR-PMW-2-1

0.00
0.00
3910.00
3910.00
547.4
4457.40
4.50

PRELIMINARY WORKS :
Earthwork excavation for trial pits / borrow pits and other investigation works in all kinds of
soil including boulders upto 30 cm dia and disposing off excavated soil as directed with lead
upto 10 m and lift upto 3 m.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

particulars

UNIT :

Unit

NIL

Quantity
0.00
0.00

Total cost of Materials

10 cum

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

328

B. MACHINERY:
Sl No

Preliminary and Maintenance Works - Item Unit Rates 2014-15

Description

Unit

Quantity

NIL

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
370.00
295.00
Rs:

Amount
in Rs.
185.00
1770.00
1955.00

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2

Description

Unit

Quantity

work inspector
mazdoor

Day
Day
Total cost of Labour
labour component/unit qty
195.50
Add contractor's profit and overhead charges
0.14 27.37
labour component/unit qty (including contractor's profit)
222.90

0.50
6.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:

Total
D. Add for contractor's profit and overheads on
(A+B+C)
14.00% Rs:
Total cost for
10.00 cum
Rs:
Rate per cum
(A+B+C+D)/100.0
Rs.
IRR-PMW-2-2

0.00
0.00
1955.00
1955.00
273.7
2228.70
222.90

Earthwork excavation for trial pits / borrow pits and other investigation works in soft
rock including disposing off the excavated rock as directed with lead upto 10 m and lift
upto 3 m.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :

Unit

Quantity

NIL

10 cum

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
370.00
345.00
295.00
Rs:

Amount
in Rs.
185.00
345.00
2212.50
2742.50

0.00
0.00
Total cost of Materials

B. MACHINERY:
Sl No

Description

Unit

Quantity

NIL

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3

Description

Unit

Quantity

work inspector
Crowbarman
mazdoor

Day
Day
Day
Total cost of Labour
labour component/unit qty
274.30
Add contractor's profit and overhead charges
0.14 38.40
labour component/unit qty (including contractor's profit)
312.70
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on
(A+B+C)
14.00% Rs:
Total cost for
10.00 cum
Rs:
Rate per cum
(A+B+C+D)/10.0
Rs.

0.50
1.00
7.50

Rs:
Rs:
Rs:
Rs:

Rate
in Rs.

0.00
0.00
2742.50
2742.50
383.95
3126.45
312.60

329

Preliminary and Maintenance Works - Item Unit Rates 2014-15

IRR-PMW-2-3

Conducting geophysical investigation studies by electrical resistivity method in


stages of 5m for sub-surface details such as depth of formations, shear zones, classification
of strata, depth of water table etc., including cost of all materials, equipments, labour,
analysing and reporting the details of field studies conducted etc., complete excluding cost of
transportation arrangements.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

particulars

UNIT :
Unit

Quantity

Sundries ( misc. consumables )

5.00
0.00
Total cost of Materials

B. MACHINERY:
Sl No
1

Electric resistivity meter


Battery / charging cost etc @

C. LABOUR:
Sl No
1
2
3
4

Description

Description

Unit

Quantity

Hour

8.00

Rate
in Rs.
41.00
0.00
Rs:

Amount
in Rs.
205.00
0.00
205.00

Rate
in Rs.
99.00
Rs:

Amount
in Rs.
792.00
158.40
950.40

Rate
in Rs.
735.00
735.00
440.00
295.00
Rs:

Amount
in Rs.
1470.00
735.00
440.00
1180.00
3825.00

20%
Total hire charges of Machinery

Unit

Quantity

Day
Day
Day
Day
Total cost of Labour
labour component/unit qty
191.30
Add contractor's profit and overhead charges
0.14 26.80
labour component/unit qty (including contractor's profit)
218.10

Geophysist / Geologist
Graduate Engineer
Lab Assistant
mazdoor

2.00
1.00
1.00
4.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:

Total
D. Add for contractor's profit and overheads on
(A+B+C)
14.00% Rs:
Total cost for
20.00 Stages
Rs:
Rate per stage
(A+B+C+D)/20.0
Rs.

IRR-PMW-2-4

20 Stages

205.00
950.40
3825.00
4980.40
697.256
5677.66
283.90

Drilling 80 mm dia hole through over-burden using casing shoe bit vertical or inclined
upto 10 degrees to vertical as directed including cost of all materials, machinery, labour, water
charges, reaming, collection of wash samples at suitable intervals, logging and lebelling,
supplying honne wood core box, fixing casing pipes ( excluding cost of casing pipes ) etc.,
complete for depth upto 30 m from surface.
Note: 1. For drilling through over-burden beyond 30 m from surface increase the basic rate per
Rm by 10 percent.

Data:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4

Unit

Use rate of casing shoe bit


Rm
Use rate of reamer shell
Rm
Use rate of extension rod set 16.5 m
Rm
Use rate of honne core box
Rm
Total cost of Materials

B. MACHINERY:
Sl No
1

particulars

UNIT :

Description

Core drilling machine

Unit
Hour

Quantity
3.00
3.00
3.00
3.00

Quantity
1.00

3.00 Rm
Rate
in Rs.
116.67
28.61
1.75
247.50
Rs:

Amount
in Rs.
350.00
85.83
5.25
742.50
1183.58

Rate
in Rs.
319.00

Amount
in Rs.
319.00

330

2
3

Fuel / Energy charges


5 hp pump ( diesel ) 2 Nos.
Fuel / Energy charges
Sundries ( samplers etc )

C. LABOUR:
Sl No
1
2
3

Description

Preliminary and Maintenance Works - Item Unit Rates 2014-15

Hour
Hour
Hour
LS
Total hire charges of Machinery

Unit

1.00
2.00
2.00
2.00

Quantity

Crew for Core drilling machine


Crew for Pump
mazdoor

Hour
Hour
Day
Total cost of Labour
labour component/unit qty
342.40
Add contractor's profit and overhead charges
0.14 47.90
labour component/unit qty (including contractor's profit)
390.30

1.00
2.00
2.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

255.80
20.40
170.60
82.00
847.80

Rate
in Rs.
244.90
96.10
295.00
Rs:

Amount
in Rs.
244.90
192.20
590.00
1027.10

Rs:
Rs:
Rs:
Rs:

Total
D. Add for contractor's profit and overheads on
(A+B+C)
14.00% Rs:
Total cost for
3.00 Rm
Rs:
Rate per Rm
(A+B+C+D)/3.0
Rs.

IRR-PMW-2-5

255.80
10.20
85.30
41.00
Rs:

1183.58
847.80
1027.10
3058.48
428.1872467
3486.67
1162.20

Drilling 76 mm dia ( NX ) core hole in hard rock using diamond core bit vertical / inclined
upto 10 degree to vertical as directed including cost of all materials, machinery, labour, water
charges, collection of core samples, logging and lebelling, supplying honne wood core box
and redrilling in case of collapse of sides etc., complete for depth upto 30 m from surface.

Data:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5

2
3

Description

Core drilling machine


Fuel / Energy charges
5 hp pump ( diesel ) 2 Nos.
Fuel / Energy charges
Sundries

C. LABOUR:
Sl No
1
2
3

Unit

Use rate of diamond core bit


Rm
Use rate of reamer shell
Rm
Use rate of double tube core barrel
Rm
Use rate of extension rod set 16.5 m
Rm
Use rate of honne core box
Rm
Total cost of Materials

B. MACHINERY:
Sl No
1

particulars

UNIT :

Description

Crew for Core drilling machine


Crew for Pump
mazdoor

Unit

Quantity
3.00
3.00
3.00
3.00
3.00

Quantity

Hour
8.00
Hour
8.00
Hour
16.00
Hour
16.00
LS
5.00
Total hire charges of Machinery

Unit

Hour
Hour
Day
Total cost of Labour
labour component/unit qty
1362.30
Add contractor's profit and overhead charges
0.14 190.70
labour component/unit qty (including contractor's profit)
1553.00

Quantity
8.00
16.00
2.00

3.00 Rm

Rate
in Rs.
848.00
85.83
226.13
23.32
556.88
Rs:

Amount
in Rs.
2544.00
257.50
678.40
69.96
1670.63
5220.49

Rate
in Rs.
319.00
255.80
10.20
85.30
41.00
Rs:

Amount
in Rs.
2552.00
2046.40
163.20
1364.80
205.00
6331.40

Rate
in Rs.
244.90
96.10
295.00
Rs:

Amount
in Rs.
1959.20
1537.60
590.00
4086.80

331

Preliminary and Maintenance Works - Item Unit Rates 2014-15

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:

Total
D. Add for contractor's profit and overheads on
(A+B+C)
14.00% Rs:
Total cost for
3.00 Rm
Rs:
Rate per Rm
(A+B+C+D)/3.0
Rs.
NOTE:

5220.49
6331.40
4086.80
15638.69
2189.4159
17828.10
5942.70

1. For drilling in hard rock beyond 30 m upto 60 m from surface increase the basic
rate per Rm by 25 percent.
2. For drilling in hard rock beyond 60 m upto 90 m from surface increase the basic
rate per Rm by 40 percent.

IRR-PMW-2-5-A
New Item 2014-155
Drilling 76 mm dia ( NX ) core hole in all types of rocks (other than Hard Rock) including
Masonry/CC (where drilling is not possible by casing shoe) using diamond core bit vertical /
inclined upto 10 degree to vertical as directed including cost of all materials, machinery, labour,
water charges, and redrilling in case of collapse of sides etc., complete for depth upto 30 m from
surface for Primary and Secondary Holes
Drilling 76 mm dia ( NX ) core hole in all types of rock
DATA:

For drilling upto 30 m from surface the rate of drilling is assumed at 3 m per day for analysis.
For rate analysis combination of diamond bit and reamer shell is assumed.
500 m long 25 mm dia GI pipe line and 50 m long 25 mm dia water hose are assumed.
For 30 m drilling average 16.5 m extension rods with coupling sleeves required.
Use rate of materials :
Cost of NX diamond core bit @
Rs:
12720.00 / Each
Life of diamond core bit in all types of rock (other than hard rock)
:
Use rate of diamond core bit per m drilling
( cost / life )
Cost of reamer shell @
Rs:
5150.00 / Each
Life of reamer shell in all types of rock (other than hard rock)
:
Use rate of reamer shell per m drilling
( cost / life )
Cost of 16.5 m extension rod @
Rs:
2120.00 / Rm
Life of extension rods
:
Use rate of 16.5 m length extension rods
( cost / life )

Data:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
4

2
3

Description

Core drilling machine


Fuel / Energy charges
5 hp pump ( diesel ) 2 Nos.
Fuel / Energy charges
Sundries

C. LABOUR:
Sl No
1
2
3

Unit

Quantity

Use rate of diamond core bit


Rm
Use rate of reamer shell
Rm
Use rate of extension rod set 16.5 m
Rm
Total cost of Materials

B. MACHINERY:
Sl No
1

particulars

UNIT :

Description

Crew for Core drilling machine


Crew for Pump
mazdoor

Unit

3.00
3.00
3.00

Quantity

Hour
Hour
Hour
Hour
LS
Total hire charges of Machinery

Unit

Hour
Hour
Day
Total cost of Labour
labour component/unit qty
812.80
Add contractor's profit and overhead charges
0.14 113.80
labour component/unit qty (including contractor's profit)
926.60

4.78
4.78
9.55
9.55
2.99

Quantity
4.78
9.55
1.19

Rs:
10.57
Rs:
Rs:
100
Rs:
Rs:
2500
Rs:

12720.00
m
1203.41
5150.00
m
51.50
34980.00
m
13.99

3.00 Rm

Rate
in Rs.
1203.41
51.50
13.99
Rs:

Amount
in Rs.
3610.22
154.50
41.98
3806.69

Rate
in Rs.
319.00
255.80
10.20
85.30
41.00
Rs:

Amount
in Rs.
1523.54
1221.70
97.43
814.79
122.59
3780.05

Rate
in Rs.
244.90
96.10
295.00
Rs:

Amount
in Rs.
1169.64
917.76
351.05
2438.45

332

Preliminary and Maintenance Works - Item Unit Rates 2014-15

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on
14.00% Rs:
Total cost for
3.00 Rm
Rs:
Rate per Rm
(A+B+C+D)/3.0
Rs.
NOTE:

Rs:
Rs:
Rs:
Rs:

3806.69
3780.05
2438.45
10025.19
1403.526852
11428.72
3809.60

1. For drilling in all types of rocks (other than hard rock) including masonry/CC beyond 30 m
upto 60 m from surface increase the basic rate per Rm by 25 percent.
2. For drilling in all types of rocks (other than hard rock) including masonry/CC m from
surface increase the basic beyond 60 m upto 90 rate per Rm by 40 percent.

IRR-PMW-2-5-B
New Item 2014-156
Drilling 76 mm dia ( NX ) core hole in all types of rocks (other than Hard Rock) including
Masonry/CC (where drilling is not possible by casing shoe) using diamond core bit vertical /
inclined upto 10 degree to vertical as directed including cost of all materials, machinery, labour,
water charges, collection of core samples, logging and lebelling, supplying honne wood core box
and redrilling in case of collapse of sides etc., complete for depth upto 30 m from surface
for Test Holes
DATA:

For drilling upto 30 m from surface the rate of drilling is assumed at 3 m per day for analysis.
For rate analysis combination of diamond bit and reamer shell is assumed.
500 m long 25 mm dia GI pipe line and 50 m long 25 mm dia water hose are assumed.
For 30 m drilling average 16.5 m extension rods with coupling sleeves required.
Use rate of materials :
Cost of NX diamond core bit @
Rs:
12720.00 / Each
Life of diamond core bit in all types of rock (other than hard rock)
:
Use rate of diamond core bit per m drilling
( cost / life )
Cost of reamer shell @
Rs:
5150.00 / Each
Life of reamer shell in all types of rock (other than hard rock)
:
Use rate of reamer shell per m drilling
( cost / life )
Cost of double core barrel @
Rs:
13568.00 / Each
Life of double tube core barrel
:
Use rate of double tube core barrel per m drilling
( cost / life )
Cost of 16.5 m extension rod @
Rs:
2120.00 / Rm
Life of extension rods
:
Use rate of 16.5 m length extension rods
( cost / life )
Honne wood core box 1.5 x 0.32 x 0.12 m
Honne wood 0.033 cum @
Rs:
54000.00 / cum
Add for fixtures and painting @
10%
Add for labour charges @
15%
Cost of one box for storing
4 m samples
Use rate of core box per m drilling

Data:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5

2
3

Unit

Use rate of diamond core bit


Rm
Use rate of reamer shell
Rm
Use rate of double tube core barrel
Rm
Use rate of extension rod set 16.5 m
Rm
Use rate of honne core box
Rm
Total cost of Materials

B. MACHINERY:
Sl No
1

particulars

UNIT :

Description

Core drilling machine


Fuel / Energy charges
5 hp pump ( diesel ) 2 Nos.
Fuel / Energy charges
Sundries

Unit
Hour
Hour
Hour
Hour
LS

Quantity
3.00
3.00
3.00
3.00
3.00

Quantity
4.78
4.78
9.55
9.55
2.99

Rs:
10.57
Rs:
Rs:
100
Rs:
Rs:
100
Rs:
Rs:
2500
Rs:

12720.00
m
1203.41
5150.00
m
51.50
13568.00
m
135.68
34980.00
m
13.99

Rs:
Rs:
Rs:
Rs:
Rs:

1782.00
178.20
267.30
2227.50
556.88

3.00 Rm

Rate
in Rs.
1203.41
51.50
135.68
13.99
556.88
Rs:

Amount
in Rs.
3610.22
154.50
407.04
41.98
1670.63
5884.36

Rate
in Rs.
319.00
255.80
10.20
85.30
41.00

Amount
in Rs.
1523.54
1221.70
97.43
814.79
122.59

333

Preliminary and Maintenance Works - Item Unit Rates 2014-15

Total hire charges of Machinery


C. LABOUR:
Sl No
1
2
3

Description

Unit

Quantity

Crew for Core drilling machine


Crew for Pump
mazdoor

Hour
Hour
Day
Total cost of Labour
labour component/unit qty
813.30
Add contractor's profit and overhead charges
0.14 113.90
labour component/unit qty (including contractor's profit)
927.20

4.78
9.55
1.19

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on
14.00% Rs:
Total cost for
3.00 Rm
Rs:
Rate per Rm
(A+B+C+D)/3.0
Rs.
NOTE:

IRR-PMW-2-6

Rs:
Rs:
Rs:
Rs:

Rs:

3780.05

Rate
in Rs.
244.90
96.10
295.00
Rs:

Amount
in Rs.
1169.64
917.95
352.23
2439.82

5884.36
3780.05
2439.82
12104.23
1694.59206
13798.82
4599.60

1. For drilling in all types of rocks (other than hard rock) including masonry/CC beyond 30 m
upto 60 m from surface increase the basic rate per Rm by 25 percent.
2. For drilling in all types of rocks (other than hard rock) including masonry/CC m from
surface increase the basic beyond 60 m upto 90 rate per Rm by 40 percent.

Drilling 47 mm (BX )dia core hole in hard rock using diamond core bit vertical / inclined
upto 10 degree to vertical as directed including cost of all materials, machinery, labour, water
charges,collection of core samples,logging, lebelling, supplying honne wood core box
and redrilling in case of collapse of sides etc., complete for depth upto 30 m from surface.

Data:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5

2
3

Description

Core drilling machine


Fuel / Energy charges
5 hp pump ( diesel ) 2 Nos.
Fuel / Energy charges
Sundries

C. LABOUR:
Sl No
1
2
3

Unit

Use rate of diamond core bit


Rm
Use rate of reamer shell
Rm
Use rate of double tube core barrel
Rm
Use rate of extension rod set 16.5 m
Rm
Use rate of honne core box
Rm
Total cost of Materials

B. MACHINERY:
Sl No
1

particulars

UNIT :

Description

Crew for Core drilling machine


Crew for Pump
mazdoor

Unit

3.00
3.00
3.00
3.00
3.00

Quantity

Hour
8.00
Hour
8.00
Hour
16.00
Hour
16.00
LS
5.00
Total hire charges of Machinery

Unit

Hour
Hour
Day
Total cost of Labour
labour component/unit qty
1362.30
Add contractor's profit and overhead charges
0.14 190.70
labour component/unit qty (including contractor's profit)
1553.00
ABSTRACT:
A. Cost of Materials

Quantity

Quantity
8.00
16.00
2.00

Rs:

3.00 Rm
Rate
in Rs.
706.67
85.83
226.13
23.32
556.88
Rs:

Amount
in Rs.
2120.00
257.50
678.40
69.96
1670.63
4796.49

Rate
in Rs.
319.00
255.80
10.20
85.30
41.00
Rs:

Amount
in Rs.
2552.00
2046.40
163.20
1364.80
205.00
6331.40

Rate
in Rs.
244.90
96.10
295.00
Rs:

Amount
in Rs.
1959.20
1537.60
590.00
4086.80

4796.49

334

Preliminary and Maintenance Works - Item Unit Rates 2014-15

B. Hire charges of Machinery


C. Cost of Labour

Rs:
Rs:
Rs:

Total
D. Add for contractor's profit and overheads on
(A+B+C)
14.00% Rs:
Total cost for
3.00 Rm
Rs:
Rate per Rm
(A+B+C+D)/3.0
Rs.
NOTE:

6331.40
4086.80
15214.69

2130.0559
17344.74
5781.60

1. For drilling in hard rock beyond 30 m upto 60 m from surface increase the
basic rate for drilling upto 30 m from surface by 25 percent per Rm.
2. For drilling in hard rock beyond 60 m upto 90 m from surface increase the basic
rate for drilling upto 30 m from surface by 40 percent per Rm.

IRR-PMW-2-6-A
New Item 2014-157
Drilling 47 mm (BX )dia core hole in all types of rocks (other than Hard Rock) including
Masonry/CC (where drilling is not possible by casing shoe) using diamond core bit vertical /
inclined upto 10 degree to vertical as directed including cost of all materials, machinery, labour,
water charges, and redrilling in case of collapse of sides etc., complete for depth upto 30 m

DATA:

For drilling upto 30 m from surface the rate of drilling is assumed at 3 m per day for analysis.
For rate analysis combination of diamond bit and reamer shell is assumed.
500 m long 25 mm dia GI pipe line and 50 m long 25 mm dia water hose are assumed.
For 30 m drilling average 16.5 m extension rods with coupling sleeves required.
Use rate of materials :
Cost of BX diamond core bit @
Rs:
10600.00 / Each
Life of diamond core bit in all types of rock (other than hard rock)
:
Use rate of diamond core bit per m drilling
( cost / life )
Cost of reamer shell @
Rs:
5150.00 / Each
Life of reamer shell in all types of rock (other than hard rock)
:
Use rate of reamer shell per m drilling
( cost / life )
Cost of 16.5 m extension rod @
Rs:
2120.00 / Rm
Life of extension rods
:
Use rate of 16.5 m length extension rods
( cost / life )

Data:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
4

2
3

Description

Core drilling machine


Fuel / Energy charges
5 hp pump ( diesel ) 2 Nos.
Fuel / Energy charges
Sundries

C. LABOUR:
Sl No
1
2
3

Unit

Quantity

Use rate of diamond core bit


Rm
Use rate of reamer shell
Rm
Use rate of extension rod set 16.5 m
Rm
Total cost of Materials

B. MACHINERY:
Sl No
1

particulars

UNIT :

Description

Crew for Core drilling machine


Crew for Pump
mazdoor

Unit

3.00
3.00
3.00

Quantity

Hour
Hour
Hour
Hour
LS
Total hire charges of Machinery

Unit

Hour
Hour
Day
Total cost of Labour
labour component/unit qty
812.80
Add contractor's profit and overhead charges
0.14 113.80
labour component/unit qty (including contractor's profit)
926.60

4.78
4.78
9.55
9.55
2.99

Quantity
4.78
9.55
1.19

Rs:
10.57
Rs:
Rs:
100
Rs:
Rs:
2500
Rs:

10600.00
m
1002.84
5150.00
m
51.50
34980.00
m
13.99

3.00 Rm

Rate
in Rs.
1002.84
51.50
13.99
Rs:

Amount
in Rs.
3008.51
154.50
41.98
3204.99

Rate
in Rs.
319.00
255.80
10.20
85.30
41.00
Rs:

Amount
in Rs.
1523.54
1221.70
97.43
814.79
122.59
3780.05

Rate
in Rs.
244.90
96.10
295.00
Rs:

Amount
in Rs.
1169.64
917.76
351.05
2438.45

335

Preliminary and Maintenance Works - Item Unit Rates 2014-15

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:

Total
D. Add for contractor's profit and overheads on
14.00% Rs:
Total cost for
3.00 Rm
Rs:
Rate per Rm
(A+B+C+D)/3.0
Rs.
NOTE:

IRR-PMW-2-7

3204.99
3780.05
2438.45
9423.49
1319.288441
10742.78
3580.90

1. For drilling in all types of rocks (other than hard rock) including masonry/CC beyond 30 m
upto 60 m from surface increase the basic rate per Rm by 25 percent.
2. For drilling in all types of rocks (other than hard rock) including masonry/CC m from
surface increase the basic beyond 60 m upto 90 rate per Rm by 40 percent.

Providing and fixing 20 x 20 x 75 cm size roughly dressed boundary / demarcation /


chainage / arrow stones including cost of all materials, labour, engraving marks, fixing in
position, murum filling etc., complete with lead upto 50 m and all lifts.

Data:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

particulars

Rough stone 20x20x75 cm


Murrum

B. MACHINERY:
Sl No
1

Description

UNIT :
Unit

Quantity

Each
cum
Total cost of Materials

Unit

18.00
1.00

Quantity

NIL

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3

Description

Unit

Quantity

work inspector
Stone chiseller Cl- I
mazdoor

Day
Day
Day
Total cost of Labour
labour component/unit qty
91.10
Add contractor's profit and overhead charges
0.14 12.80
labour component/unit qty (including contractor's profit)
103.90

1.00
1.00
3.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:

Total
D. Add for contractor's profit and overheads on
(A+B+C)
14.00% Rs:
Total cost for
18.00 Nos.
Rs:
Rate per each
(A+B+C+D)/18.0
Rs.

IRR-PMW-2-8

18 Nos.
Rate
in Rs.
23.00
107.00
Rs:

Amount
in Rs.
414.00
107.00
521.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
370.00
385.00
295.00
Rs:

Amount
in Rs.
370.00
385.00
885.00
1640.00

521.00
0.00
1640.00
2161.00
302.54
2463.54
136.90

Providing and fixing 20 x 20 x 75 cm size temporary bench mark stone in CC 1 : 4 : 8


using 40 mm down size graded coarse aggregate including cost of all materials, labour,
dressing top surface, engraving BM data etc.,complete with lead upto 50 m and all lifts.

Data:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3

particulars

Rough stone 20x20x75 cm


Cement for CC & top finishing
Coarse aggregate 40-20 mm

UNIT :
Unit
Each
kg
cum

Quantity
10.00
91.00
0.25

10 Nos.
Rate
in Rs.
23.00
4.00
1145.00

Amount
in Rs.
230.00
364.00
286.25

336

Coarse aggregate 20-10 mm


Coarse aggregate 10-4.75 mm
Sand (Un-Screened )

B. MACHINERY:
Sl No

Description

cum
cum
cum
Total cost of Materials

Unit

Preliminary and Maintenance Works - Item Unit Rates 2014-15

0.15
0.10
0.25

Quantity

NIL

1210.00
875.00
462.00
Rs:

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
370.00
385.00
295.00
Rs:

Amount
in Rs.
370.00
1155.00
1180.00
2705.00

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3

Description

Unit

Quantity

work inspector
Stone chiseller Cl- I
mazdoor

Day
Day
Day
Total cost of Labour
labour component/unit qty
270.50
Add contractor's profit and overhead charges
0.14 37.90
labour component/unit qty (including contractor's profit)
308.40

1.00
3.00
4.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:

Total

D. Add for contractor's profit and overheads on


(A+B+C)
14.00% Rs:
Total cost for
10.00 Nos.
Rs:
Rate per each
(A+B+C+D)/10.0
Rs.
NOTE: For providing 30 cm thick compacted murum bed in B.C soil area including
additional excavation for thickness of murum bedding add peEach

IRR-PMW-2-9

181.50
87.50
115.50
1264.75

1264.75
0.00
2705.00
3969.75
555.765
4525.52
452.60
Rs:

4.00

Providing and fixing 20 x 20 x 75 cm size permanent bench mark stone in CC 1 :3 : 6


block of size 90 x 90 x 120 cm using 40 mm down size graded coarse aggregate and providing
35 cm thick 30 cm high UCR masonry in CM 1 : 5 proportion protective wall alround the BM
stone, including cost of all materials, labour, dressing top surface of stone, engraving BM data
on top surface, excavation, finishing, curing etc., complete with lead upto 50 m and all lifts.

Data:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3

4
5
6

particulars

Rough stone 20x20x75 cm


Cement
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10-4.75 mm
Rubble stone at quarry
Stone chips at quarry
Sand (Un-Screened )

B. MACHINERY:
Sl No

Description

UNIT :
Unit
Each
kg
cum
cum
cum
cum
cum
cum
Total cost of Materials

Unit

Quantity
1.00
262.00
0.50
0.30
0.20
0.25
0.04
0.60

Quantity

NIL

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
1

Description

work inspector

Unit
Day

Quantity
1.00

1 No.
Rate
in Rs.
23.00
4.00
1145.00
1210.00
875.00
318.00
340.00
462.00
Rs:

Amount
in Rs.
23.00
1048.00
572.50
363.00
175.00
79.50
13.60
277.20
2551.80

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
370.00

Amount
in Rs.
370.00

337

2
3
4

Stone chiseller Cl- I


Mason Cl- II
mazdoor

Day
Day
Day
Total cost of Labour
labour component/unit qty
2382.50
Add contractor's profit and overhead charges
0.14 333.60
labour component/unit qty (including contractor's profit)
2716.10

Preliminary and Maintenance Works - Item Unit Rates 2014-15

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total

0.50
1.00
5.00

385.00
345.00
295.00
Rs:

Rs:
Rs:
Rs:
Rs:

2551.80
0.00
2382.50
4934.30

D. Add for contractor's profit and overheads on


(A+B+C)
14.00% Rs:
Total cost for
1.00 No.
Rs:
Rate per each
(A+B+C+D)/1.0
Rs.
IRR-PMW-3
IRR-PMW-3-1

690.802
5625.10
5625.10

MAINTENANCE WORKS :
Removing dry stone rock-toe / rivetment and filter layers below rock-toe/ rivetment
including stacking all materials separately as directed with initial lead upto 50 m and all lifts.

Data:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Quantity

NIL

105 cum
Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
370.00
345.00
295.00
Rs:

Amount
in Rs.
370.00
2070.00
14160.00
16600.00

0.00
0.00
Total cost of Materials

B. MACHINERY:
Sl No

Description

Unit

Quantity

NIL

Rate
in Rs.

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3

Description

Unit

Quantity

Day
Day
Day
Total cost of Labour
labour component/unit qty
158.10
Add contractor's profit and overhead charges
0.14 22.10
labour component/unit qty (including contractor's profit)
180.20

work inspector
Mason Cl- II
mazdoor

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on
(A+B+C)
14.00% Rs:
Total cost for
105.00 cum
Rs:
Rate per cum
(A+B+C+D)/105.0
Rs.

IRR-PMW-3-2

192.50
345.00
1475.00
2382.50

1.00
6.00
48.00

Rs:
Rs:
Rs:
Rs:

0.00
0.00
16600.00
16600.00
2324
18924.00
180.20

Re-constructing 60 cm thick hand packed rough stone revetment with through


stones at 1.5 m c / c over a backing of 45 cm thick graded filter media consisting of sand,
10 mm and 40 mm size graded aggregates satisfying filter criteria laid in layers of 15 cm thick
each using sand from approved quarry and stones and filter aggregates obtained from
revetment removed for re-construction including cost of all machinery, labour, laying filter and
stones to specified slopes, wedging with chips, finishing etc. complete with initial
lead upto 50 m and all lifts.

338

Preliminary and Maintenance Works - Item Unit Rates 2014-15

Data:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6

particulars

UNIT :
Unit

Quantity

Sand (Un-Screened ) ( from quarry)


cum
Coarse aggregate 10 mm (available)
cum
Coarse aggr. 40-20 mm ( available)
cum
Stone chips ( available )
cum
Rough stones ( available )
cum
Through stones ( available )
Nos
Total cost of Materials

B. MACHINERY:
Sl No

Description

Unit

15.30
15.30
15.30
9.00
57.60
44.00

Quantity

NIL

100 sqm
Rate
in Rs.
462.00
0.00
0.00
0.00
0.00
0.00
Rs:

Amount
in Rs.
7068.60
0.00
0.00
0.00
0.00
0.00
7068.60

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
370.00
345.00
295.00
Rs:

Amount
in Rs.
370.00
1725.00
9735.00
11830.00

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3

Description

Unit

Quantity

work inspector
Mason Cl- II
mazdoor

Day
Day
Day
Total cost of Labour
labour component/unit qty
118.30
Add contractor's profit and overhead charges
0.14 16.60
labour component/unit qty (including contractor's profit)
134.90

1.00
5.00
33.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:

Total
D. Add for contractor's profit and overheads on
(A+B+C)
14.00% Rs:
Total cost for
100.00 sqm
Rs:
(A+B+C+D)/100.0
Rs.
Rate per sqm

IRR-PMW-3-3

7068.60
0.00
11830.00
18898.60
2645.804
21544.40
215.40

Re-constructing dry rubble rock-toe and filter media for rock-toe consisting of
sand 20 mm and 80 mm size graded aggregates satisfying filter criteria laid in layers of 15 cm
thick each using sand from approved quarry and stones and filter aggregates obtained from
rock-toe removed for re-construction including cost of all machinery, labour, laying filter and
stones to specified slopes, wedging with chips, finishing etc. complete with initial lead upto
50 m and all lifts.

Data:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5

Unit

Quantity

Rubble ( available )
cum
Stone chips ( available )
cum
80-20 mm filter ( available )
cum
20 mm down filter ( available )
cum
Sand (Un-Screened) ( fresh from quarry )
cum
Total cost of Materials

B. MACHINERY:
Sl No
1

particulars

UNIT :

Description

Unit

58.20
8.70
19.40
12.10
9.80

Quantity

NIL

0.00
0.00
Total hire charges of Machinery

100 cum
Rate
in Rs.
0.00
0.00
0.00
0.00
462.00
Rs:

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00
0.00
4527.60
4527.60

Amount
in Rs.
0.00
0.00
0.00

339

Preliminary and Maintenance Works - Item Unit Rates 2014-15

C. LABOUR:
Sl No
1
2
3

Description

Unit

Quantity

work inspector
Mason Cl- II
mazdoor

Day
Day
Day
Total cost of Labour
labour component/unit qty
169.50
Add contractor's profit and overhead charges
0.14 23.70
labour component/unit qty (including contractor's profit)
193.20

1.00
7.00
48.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:

Total
D. Add for contractor's profit and overheads on
(A+B+C)
14.00% Rs:
Total cost for
100.00 cum
Rs:
Rate per cum
(A+B+C+D)/100.0
Rs.

IRR-PMW-3-4

Amount
in Rs.
370.00
2415.00
14160.00
16945.00

4527.60
0.00
16945.00
21472.60
3006.164
24478.76
244.80

Removing and resetting disturbed Yarguntla / Shahabad / Talikot / PCC / Other types
of slab lining set in CM 1 : 3 including flush cement mortar pointing in CM 1 : 3 with
lead upto 50 m and all lifts.

Data:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2

particulars

Cement 43 Gr
Sand (Screened )

B. MACHINERY:
Sl No
1

Description

UNIT :
Unit

Quantity

kg
cum
Total cost of Materials

Unit

101.00
0.21

Quantity

NIL

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No

Description

Unit

Quantity

1
2
3
4

work inspector
Day
Mason Class I
Day
mazdoor
Day
Cartman with Double Bullock cart for water
Day
Total cost of Labour
labour component/unit qty
40.80
Add contractor's profit and overhead charges
0.14 5.70
labour component/unit qty (including contractor's profit)
46.50
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total

1.00
4.00
6.00
1.00

Rs:
Rs:
Rs:
Rs:

D. Add for contractor's profit and overheads on


(A+B+C)
14.00% Rs:
Total cost for
100.00 sqm
Rs:
Rate per sqm
(A+B+C+D)/100.0
Rs.

IRR-PMW-3-5

Rate
in Rs.
370.00
345.00
295.00
Rs:

100 sqm
Rate
in Rs.
4.00
606.00
Rs:

Rate
in Rs.

Amount
in Rs.
404.00
127.26
531.26

0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
370.00
385.00
295.00
395.00
Rs:

Amount
in Rs.
370.00
1540.00
1770.00
395.00
4075.00

531.26
0.00
4075.00
4606.26
644.8764
5251.14
52.50

Removing and resetting disturbed dry rubble / khandki stone pitching 25 to 45 cm


thick including packing, wedging, finishing etc., complete with all leads and lifts.

340

Preliminary and Maintenance Works - Item Unit Rates 2014-15

Data:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Quantity

NIL

100 sqm
Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
370.00
345.00
295.00
Rs:

Amount
in Rs.
370.00
2070.00
1770.00
4210.00

0.00
0.00
Total cost of Materials

B. MACHINERY:
Sl No

Description

Unit

Quantity

NIL

Rate
in Rs.

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2
3

Description

Unit

Quantity

work inspector
Mason Class II
mazdoor

Day
Day
Day
Total cost of Labour
labour component/unit qty
42.10
Add contractor's profit and overhead charges
0.14 5.90
labour component/unit qty (including contractor's profit)
48.00

1.00
6.00
6.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:

Total
D. Add for contractor's profit and overheads on
(A+B+C)
14.00% Rs:
Total cost for
100.00 sqm
Rs:
Rate per sqm
(A+B+C+D)/100.0
Rs.

IRR-PMW-3-6

0.00
0.00
4210.00
4210.00
589.4
4799.40
48.00

Removing and refixing disturbed chainage / demarcation / hectometre / guard stones


including excavation, back filling etc., complete with all leads and lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Quantity

NIL

18 Nos.
Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
370.00
295.00
Rs:

Amount
in Rs.
370.00
590.00
960.00

0.00
0.00
Total cost of Materials

B. MACHINERY:
Sl No

Description

Unit

Quantity

NIL

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2

Description

work inspector
mazdoor

Unit

Day
Day
Total cost of Labour
labour component/unit qty
53.33
Add contractor's profit and overhead charges
0.14 7.47
labour component/unit qty (including contractor's profit)
60.80

Quantity
1.00
2.00

Rate
in Rs.

341

Preliminary and Maintenance Works - Item Unit Rates 2014-15

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:

Total

0.00
0.00
960.00
960.00

D. Add for contractor's profit and overheads on


(A+B+C)
14.00% Rs:
Total cost for
18.00 Nos.
Rs:
Rate per each
(A+B+C+D)/18.0
Rs.

IRR-PMW-3-7

134.4
1094.40
60.80

Removing and refixing disturbed km stone / sign board / hecto-metre stone etc., including
excavation, back filling with available stuff after refixing, forming base platform of size 90 x 90 x
7.5 cm including watering, ramming etc complete with all leads and lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Quantity

NIL

8 Nos.
Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
370.00
295.00
Rs:

Amount
in Rs.
370.00
590.00
960.00

0.00
0.00
Total cost of Materials

B. MACHINERY:
Sl No

Description

Unit

Quantity

NIL

Rate
in Rs.

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2

Description

Unit

Quantity

work inspector
mazdoor

Day
Day
Total cost of Labour
labour component/unit qty
120.00
Add contractor's profit and overhead charges
0.14 16.80
labour component/unit qty (including contractor's profit)
136.80

1.00
2.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:

Total

0.00
0.00
960.00
960.00

D. Add for contractor's profit and overheads on


(A+B+C)
14.00% Rs:
Total cost for
8.00 Nos.
Rs:
Rate per each
(A+B+C+D)/18.0
Rs.
IRR-PMW-3-8

134.4
1094.40
136.80

Providing impervious hearting for breached / damaged portion of embankment


with soil from approved borrow areas in layers of 10 to 15 cm before compaction including
cost of all materials, machinery, labour, all operations such as collection of soil, sorting out,
spreading soil to specified thickness, breaking clods, sectioning, watering, compacting each
layer to density control of not less than 98 percent or as stipulated by rolling or
by using mechanical tampers etc., complete with initial lead upto 1 km and all lifts.

Data:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

particulars

UNIT :
Unit

NIL

Quantity

480 cum
Rate
in Rs.

0.00
0.00

0.00
0.00
Rs:

Total cost of Materials


B. MACHINERY:
Sl No

Description

Unit

Quantity

Rate

Amount
in Rs.
0.00
0.00
0.00

Amount

342

Preliminary and Maintenance Works - Item Unit Rates 2014-15

1
2
3
4
5
6
7

Angle dozer
Fuel / Energy charges
Shovel 0.50 cum capacity
Fuel / Energy charges
Tippers 5.00 cum capacity 4 Nos.
Fuel / Energy charges
Pump 5 hp ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Vibratory pad foot roller 8 tonne
Fuel / Energy charges
Sundries

C. LABOUR:
Sl No
1
2
3
4
5
6
7
8

Description

Hour
5.00
Hour
5.00
Hour
8.00
Hour
8.00
Hour
32.00
Hour
32.00
Hour
2.00
Hour
2.00
Hour
4.00
Hour
4.00
Hour
6.00
Hour
6.00
LS
2.00
Total hire charges of Machinery

Unit

Quantity

Crew for Dozer


Crew for Shovel
Crew for Tipper
Crew for Pump
Crew for Water tanker
Crew for Roller
work inspector
mazdoor

Hour
Hour
Hour
Hour
Hour
Hour
Day
Day
Total cost of Labour
labour component/unit qty
24.40
Add contractor's profit and overhead charges
0.14 3.40
labour component/unit qty (including contractor's profit)
27.80

4.00
8.00
32.00
3.00
5.00
6.00
2.00
4.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:

Total
D. Add for contractor's profit and overheads on
(A+B+C)
14.00% Rs:
Total cost for
480.00 cum
Rs:
Rate per cum
(A+B+C+D)/480.0
Rs.

IRR-PMW-3-9

in Rs.
1715.50
656.00
1003.10
511.50
446.70
322.20
10.20
85.30
402.50
322.20
1342.20
1108.30
41.00
Rs:

in Rs.
8577.50
3280.00
8024.80
4092.00
14294.40
10310.40
20.40
170.60
1610.00
1288.80
8053.20
6649.80
82.00
66453.90

Rate
in Rs.
204.10
204.10
153.10
96.10
153.10
227.80
370.00
295.00
Rs:

Amount
in Rs.
816.40
1632.80
4899.20
288.30
765.50
1366.80
740.00
1180.00
11689.00

0.00
66453.90
11689.00
78142.90
10940.006
89082.91
185.60

Providing pervious/semi-pervious casing for breached / damaged portion of


embankment with soil from approved borrow areas in layers of 10 to 15 cm before
compaction including cost of all materials, machinery, labour, all operations such as collection
of soil, sorting out, spreading soil to specified thickness, breaking clods, sectioning, watering,
compacting each layer to density control of not less than 98 percent or as stipulated by rolling
or by using mechanical tampers etc., complete with initial lead upto 1 km and all lifts.

Data:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

particulars

UNIT :
Unit

NIL

Quantity
0.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No
1
2
3

Description

Angle dozer 90 hp
Fuel / Energy charges
Shovel 0.50 cum capacity
Fuel / Energy charges
Tippers 5.00 cum capacity 3 Nos.
Fuel / Energy charges

Unit
Hour
Hour
Hour
Hour
Hour
Hour

Quantity
3.50
3.50
8.00
8.00
24.00
24.00

325 cum
Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
1715.50
656.00
1003.10
511.50
446.70
322.20

Amount
in Rs.
6004.25
2296.00
8024.80
4092.00
10720.80
7732.80

343

4
5
6
7

Pump 5 hp ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Vibratory pad foot roller 8 tonne
Fuel / Energy charges
Sundries

C. LABOUR:
Sl No
1
2
3
4
5
6
7
8

Description

Preliminary and Maintenance Works - Item Unit Rates 2014-15

Hour
Hour
Hour
Hour
Hour
Hour
LS
Total hire charges of Machinery

Unit

1.50
1.50
3.00
3.00
4.00
4.00
2.00

Quantity

Crew for Dozer


Crew for Shovel
Crew for Tipper
Crew for Pump
Crew for Water tanker
Crew for Roller
work inspector
mazdoor

Hour
Hour
Hour
Hour
Hour
Hour
Day
Day
Total cost of Labour
labour component/unit qty
29.10
Add contractor's profit and overhead charges
0.14 4.10
labour component/unit qty (including contractor's profit)
33.20

3.50
8.00
24.00
1.50
3.00
4.00
2.00
4.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

10.20
85.30
402.50
322.20
1342.20
1108.30
41.00
Rs:

15.30
127.95
1207.50
966.60
5368.80
4433.20
82.00
51072.00

Rate
in Rs.
204.10
204.10
153.10
96.10
153.10
227.80
370.00
295.00
Rs:

Amount
in Rs.
714.35
1632.80
3674.40
144.15
459.30
911.20
740.00
1180.00
9456.20

Rs:
Rs:
Rs:
Rs:

Total

0.00
51072.00
9456.20
60528.20

D. Add for contractor's profit and overheads on


(A+B+C)
14.00% Rs:
Total cost for
325.00 cum
Rs:
Rs.
Rate per cum
(A+B+C+D)/325.0

IRR-PMW-3-10

8473.948
69002.15
212.30

Providing impervious hearting for breached / damaged portion of embankment with


soil from approved dump areas in layers of 10 to 15 cm before compaction including cost
of all materials, machinery, labour, all operations such as collection of soil,sorting out,
spreading soil to specified thickness, breaking clods, sectioning, watering, compacting each
layer to density control of not less than 98 percent or as stipulated by rolling or by using
mechanical tampers etc., complete with initial lead upto 1 km and all lifts.

Data:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

particulars

UNIT :
Unit

NIL

Quantity
0.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No
1
2
3
4
5
6
7

Description

Angle dozer
Fuel / Energy charges
Shovel 0.50 cum capacity
Fuel / Energy charges
Tippers 5.00 cum capacity 5 Nos.
Fuel / Energy charges
Pump 5 hp ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Vibratory pad foot roller 8 tonne
Fuel / Energy charges
Sundries

Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Quantity
4.00
4.00
8.00
8.00
40.00
40.00
4.00
4.00
7.00
7.00
7.50
7.50
2.00

612 cum
Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
1715.50
656.00
1003.10
511.50
446.70
322.20
10.20
85.30
402.50
322.20
1342.20
1108.30
41.00

Amount
in Rs.
6862.00
2624.00
8024.80
4092.00
17868.00
12888.00
40.80
341.20
2817.50
2255.40
10066.50
8312.25
82.00

344

Preliminary and Maintenance Works - Item Unit Rates 2014-15

Total hire charges of Machinery


C. LABOUR:
Sl No
1
2
3
4
5
6
7
8

Description

Unit

Quantity

Crew for Dozer


Crew for Shovel
Crew for Tipper
Crew for Pump
Crew for Water tanker
Crew for Roller
work inspector
mazdoor

Hour
Hour
Hour
Hour
Hour
Hour
Day
Day
Total cost of Labour
labour component/unit qty
23.30
Add contractor's profit and overhead charges
0.14 3.30
labour component/unit qty (including contractor's profit)
26.60

4.00
8.00
40.00
4.00
7.00
7.50
2.00
6.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

76274.45

Rate
in Rs.
204.10
204.10
153.10
96.10
153.10
227.80
370.00
295.00
Rs:

Amount
in Rs.
816.40
1632.80
6124.00
384.40
1071.70
1708.50
740.00
1770.00
14247.80

Rs:
Rs:
Rs:
Rs:

Total
D. Add for contractor's profit and overheads on
(A+B+C)
14.00% Rs:
Total cost for
612.00 cum
Rs:
Rate per cum
(A+B+C+D)/612.0
Rs.

IRR-PMW-3-11

Rs:

0.00
76274.45
14247.80
90522.25
12673.115
103195.37
168.60

Providing pervious /semi-pervious casing for breached /damaged portion of embankment


with soil from approved dump areas in layers of 10 to 15 cm before compaction including
cost of all materials, machinery, labour, all operations such as collection of soil, sorting out,
spreading soil to specified thickness, breaking clods, sectioning, watering, compacting each
layer to density control of not less than 98 percent or as stipulated by rolling or by using
mechanical tampers etc., complete with initial lead upto 1 km and all lifts.

Data:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

particulars

UNIT :
Unit

NIL

Quantity
0.00
0.00

Total cost of Materials


B. MACHINERY:
Sl No
1
2
3
4
5
6
7

Angle dozer 90 hp
Fuel / Energy charges
Shovel 0.50 cum capacity
Fuel / Energy charges
Tippers 5.00 cum capacity 4 Nos.
Fuel / Energy charges
Pump 5 hp ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Vibratory pad foot roller 8 tonne
Fuel / Energy charges
Sundries

C. LABOUR:
Sl No
1
2

Description

Description

Crew for Dozer


Crew for Shovel

Unit

Quantity

Hour
3.00
Hour
3.00
Hour
8.00
Hour
8.00
Hour
32.00
Hour
32.00
Hour
3.00
Hour
3.00
Hour
6.00
Hour
6.00
Hour
5.50
Hour
5.50
LS
2.00
Total hire charges of Machinery

Unit
Hour
Hour

Quantity
3.00
8.00

440 cum
Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
1715.50
656.00
1003.10
511.50
446.70
322.20
10.20
85.30
402.50
322.20
1342.20
1108.30
41.00
Rs:

Amount
in Rs.
5146.50
1968.00
8024.80
4092.00
14294.40
10310.40
30.60
255.90
2415.00
1933.20
7382.10
6095.65
82.00
62030.55

Rate
in Rs.
204.10
204.10

Amount
in Rs.
612.30
1632.80

345

3
4
5
6
7
8

Crew for Tipper


Crew for Pump
Crew for Water tanker
Crew for Roller
work inspector
mazdoor

Hour
Hour
Hour
Hour
Day
Day
Total cost of Labour
labour component/unit qty
27.50
Add contractor's profit and overhead charges
0.14 3.90
labour component/unit qty (including contractor's profit)
31.40

Preliminary and Maintenance Works - Item Unit Rates 2014-15

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total

32.00
3.00
6.00
5.50
2.00
6.00

153.10
96.10
153.10
227.80
370.00
295.00
Rs:

Rs:
Rs:
Rs:
Rs:

0.00
62030.55
12114.10
74144.65

D. Add for contractor's profit and overheads on


(A+B+C)
14.00% Rs:
Total cost for
440.00 cum
Rs:
Rate per cum
(A+B+C+D)/440.0
Rs.

IRR-PMW-3-12

10380.251
84524.90
192.10

Repairing rain cuts / resectioning canal slopes to required lines and grades as directed
using available soil including dressing, clod breaking, packing, tamping etc., complete with
all leads and lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No

particulars

UNIT :
Unit

Quantity

NIL

1000 sqm
Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
370.00
295.00
Rs:

Amount
in Rs.
370.00
2360.00
2730.00

0.00
0.00
Total cost of Materials

B. MACHINERY:
Sl No

Description

Unit

Quantity

NIL

Rate
in Rs.

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2

Description

Unit

Quantity

Day
Day
Total cost of Labour
labour component/unit qty
2.73
Add contractor's profit and overhead charges
0.14 0.38
labour component/unit qty (including contractor's profit)
3.10

work inspector
mazdoor

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on
(A+B+C)
14.00% Rs:
Total cost for
1000.00 sqm
Rs:
Rate per sqm
(A+B+C+D)/1000.0
Rs.

IRR-PMW-3-13

4899.20
288.30
918.60
1252.90
740.00
1770.00
12114.10

1.00
8.00

Rs:
Rs:
Rs:
Rs:

0.00
0.00
2730.00
2730.00
382.2
3112.20
3.10

Cleaning drainage gallery, adits, instrumentation galleries etc., by scrubbing / brushing


including chiselling and removing leached lime deposit and disposing off all the waste material
out side adits in specified location etc., complete with all leads and lifts.

346

DATA:

Preliminary and Maintenance Works - Item Unit Rates 2014-15

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3

particulars

Wire brush
Coir brush
Sundries ( brooms, gloves etc )

B. MACHINERY:
Sl No

Description

UNIT :

Unit

Quantity

Each
Each
LS
Total cost of Materials

Unit

5.00
10.00
2.00

Quantity

NIL

100 Rm

Rate
in Rs.
41.00
45.00
41.00
Rs:

Amount
in Rs.
205.00
450.00
82.00
737.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
345.00
295.00
Rs:

Amount
in Rs.
690.00
1770.00
2460.00

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2

Description

Unit

Quantity

Chiseller Cl II
mazdoor

Day
Day
Total cost of Labour
labour component/unit qty
24.60
Add contractor's profit and overhead charges
0.14 3.40
labour component/unit qty (including contractor's profit)
28.00

2.00
6.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:

Total
D. Add for contractor's profit and overheads on
(A+B+C)
14.00% Rs:
Total cost for
100.00 Rm
Rs:
Rate per Rm
(A+B+C+D)/100.0
Rs.

IRR-PMW-3-14

737.00
0.00
2460.00
3197.00
447.58
3644.58
36.40

Cleaning dam parapet inner face and top using oxalic acid and water by scrubbing /
brushing and washing to remove all surface coatings etc., complete .

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4

particulars

Oxalic acid
Wire brush
Coir brush
Sundries ( brooms, gloves etc )

B. MACHINERY:
Sl No
1

Description

UNIT :
Unit

Quantity

ltr
Each
Each
LS
Total cost of Materials

Unit

5.00
5.00
10.00
2.00

Quantity

NIL

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
1

mazdoor

Description

Unit

Day
Total cost of Labour
labour component/unit qty
17.70
Add contractor's profit and overhead charges
0.14 2.50
labour component/unit qty (including contractor's profit)
20.20

Quantity
6.00

100 Rm
Rate
in Rs.
76.00
41.00
45.00
41.00
Rs:

Amount
in Rs.
380.00
205.00
450.00
82.00
1117.00

Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
295.00
Rs:

Amount
in Rs.
1770.00
1770.00

ABSTRACT:

347

Preliminary and Maintenance Works - Item Unit Rates 2014-15

A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:

Total
D. Add for contractor's profit and overheads on
(A+B+C)
14.00% Rs:
Total cost for
100.00 Rm
Rs:
Rate per Rm
(A+B+C+D)/100.0
Rs.

IRR-PMW-3-20

1117.00
0.00
1770.00
2887.00
404.18
3291.18
32.90

Excavation and removal of silt and silt mixed with sand from canal bed in dry condition
including disposing off the same in spoil bank or on the canal embankment in layers as
directed etc., complete with initial lead upto 50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

particulars

UNIT :
Unit

Quantity

NIL

10 cum
Rate
in Rs.
0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

Rate
in Rs.
295.00
Rs:

Amount
in Rs.
1180.00
1180.00

0.00
0.00
Total cost of Materials

B. MACHINERY:
Sl No
1

Description

Unit

Quantity

NIL

Rate
in Rs.

0.00
0.00
Total hire charges of Machinery

C. LABOUR:
Sl No
1

Description

Unit

Quantity

mazdoor

Day
Total cost of Labour
labour component/unit qty
118.00
Add contractor's profit and overhead charges
0.14 16.50
labour component/unit qty (including contractor's profit)
134.50

4.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Rs:
Rs:
Rs:
Rs:

Total
D. Add for contractor's profit and overheads on
(A+B+C)
14.00% Rs:
Total cost for
10.00 cum
Rs:
Rate per cum
(A+B+C+D)/10.0
Rs.

IRR-PMW-3-21

0.00
0.00
1180.00
1180.00
165.2
1345.20
134.50

Excavation and removal of silt or silt mixed with sand in slussy condition from canal bed
including disposing off the same in spoil bank or on the canal embankment in layers as
directed etc., complete with initial lead upto 50 m and all lifts.

DATA:

RATE ANALYSIS
A. MATERIALS:
Sl No
1

particulars

UNIT :
Unit

NIL

Quantity

12 cum
Rate
in Rs.

0.00
0.00
Total cost of Materials

B. MACHINERY:
Sl No
1

Description
NIL

Unit

Quantity
0.00
0.00

0.00
0.00
Rs:

Amount
in Rs.
0.00
0.00
0.00

0.00
0.00

Amount
in Rs.
0.00
0.00

Rate
in Rs.

348

Preliminary and Maintenance Works - Item Unit Rates 2014-15

Total hire charges of Machinery


C. LABOUR:
Sl No
1

Description

Unit

Quantity

mazdoor

Day
Total cost of Labour
labour component/unit qty
147.50
Add contractor's profit and overhead charges
0.14 20.70
labour component/unit qty (including contractor's profit)
168.20
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

6.00

Rs:
Rs:
Rs:
Rs:

Total
D. Add for contractor's profit and overheads on
(A+B+C)
14.00% Rs:
Total cost for
12.00 cum
Rs:
Rate per cum
(A+B+C+D)/12.0
Rs.
IRR-PMW-3-22
New Item5 - 2010-11

(For Minor Works)

0.00

Rate
in Rs.
295.00
Rs:

Amount
in Rs.
1770.00
1770.00

0.00
0.00
1770.00
1770.00
247.8
2017.80
168.20

Providing homogeneous embankment using soil from approved borrow


area in layers of 25 to 30 cm before compaction including cost of all
materials, machinery, labour, all operations such as excavation, sorting out,
transportation, spreading soil in layer of specified thickness, breaking clods,
sectioning,etc.,complete with initial lead upto 1 km and all lifts.

A. MATERIALS:
Sl No
Particulars
1

1
2
3

RATE ANALYSIS
Unit:
Unit
Quantity

NIL

Total cost of Materials


B. MACHINERY:
Sl No
Description
Angle dozer 90 hp
Fuel / Energy charges
Shovel 0.85 cum capacity
Fuel / Energy charges
Tippers 5.00 cum capacity 5 Nos.
Fuel / Energy charges
Total hire charges of Machinery

C. LABOUR:
Sl No
Description

0.00
0.00

Unit
Hour
Hour
Hour
Hour
Hour
Hour

Unit

Quantity
2.70
2.70
8.00
8.00
40.00
40.00

Quantity

1
2
3
4
5

Crew for Dozer


Hour
2.70
Crew for Shovel
Hour
8.00
Crew for Tipper
Hour
40.00
work inspector
Day
1.00
mazdoor
Day
2.00
Total cost of Labour
labour component/unit qty
11.50
Add contractor's profit and overhead charges
14% 1.60
labour component/unit qty (including contractor's profit)
13.10
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
14%
D.Add for contractor's profit and overheads on (A+B+C)
Total cost for
807.00 cum
Rate per cum
(A+B+C+D)/807
IRR-PMW-3-23

Rs:

807.00
Rate
in Rs.
0.00
0.00
Rs:

cum
Amount
in Rs
0.00
0.00
0.00

Rate
in Rs.
1715.50
656.00
1706.60
937.80
446.70
322.20
Rs:

Amount
in Rs
4631.85
1771.20
13652.80
7502.40
17868.00
12888.00
58314.25

Rate
in Rs.
204.10
204.10
153.10
370.00
295.00
Rs:

Amount
in Rs
551.07
1632.80
6124.00
370.00
590.00
9267.87

Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:

0.00
58314.25
9267.87
67582.12
9461.5
77043.62
95.50

Providing homogeneous embankment using soil from approved borrow

349

New Item6 - 2010-11

(For Minor Works)

area in layers of 25 to 30 cm before compaction including cost of all


materials, machinery, labour, all operations such as watering, compacting
to density control of not less than 95 percent or as stipulated using
8T roller etc., complete with initial lead upto 1 km and all lifts.

A. MATERIALS:
Sl No
Particulars
1

NIL

Total cost of Materials


B. MACHINERY:
Sl No
Description
1
2
3
4
5

RATE ANALYSIS
UNIT :
Unit
Quantity

Angle dozer 90 hp
Fuel / Energy charges
Pump 5 hp ( ele )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Vibratory pad foot roller 8 tonne
Fuel / Energy charges
Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No
Description

0.00
0.00

Unit

Quantity

Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS

Unit

1
4
5
6
7
8

2.70
2.70
4.00
4.00
8.00
8.00
6.40
6.40
2.00

Quantity

Crew for Dozer


Hour
Crew for Pump
Hour
Crew for Water tanker
Hour
Crew for Roller
Hour
work inspector
Day
mazdoor
Day
Total cost of Labour
labour component/unit qty
5.60
Add contractor's profit and overhead charges
14% 0.80
labour component/unit qty (including contractor's profit)
6.40

2.70
4.00
8.00
6.40
1.00
2.00

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
14%
D.Add for contractor's profit and overheads on (A+B+C)
Total cost
for
807.00 cum
Rate per cum
(A+B+C+D)/807
IRR-PMW-3-24

Providing homogeneous embankment using soil from approved borrow

New Item 7 - 2010-11

area in layers of 25 to 30 cm before compaction including cost of all


materials, machinery, labour, all operations such as compacting
to density control of not less than 90 percent or as stipulated using
2T roller etc., complete with initial lead upto 1 km and all lifts.

A. MATERIALS:
Sl No
Particulars
1

NIL

Total cost of Materials


B. MACHINERY:
Sl No
Description
1

Tractor with 2T Roller

Preliminary and Maintenance Works - Item Unit Rates 2014-15

807.00
Rate
in Rs.
0.00
0.00
Rs:

cum
Amount
in Rs
0.00
0.00
0.00

Rate
in Rs.
1715.50
656.00
3.00
38.00
402.50
322.20
1342.20
1108.30
41.00
Rs:

Amount
in Rs
4631.85
1771.20
12.00
152.00
3220.00
2577.60
8590.08
7093.12
82.00
28129.85

Rate
in Rs.
204.10
72.10
153.10
227.80
370.00
295.00
Rs:

Amount
in Rs
551.07
288.40
1224.80
1457.92
370.00
590.00
4482.19

Rs:
Rs:
Rs:
Rs:
Rs.

0.00
28129.85
4482.19
32612.04
4565.69

Rs: 37177.73
Rs: 46.10

RATE ANALYSIS
UNIT :
807.00 cum
Unit
Quantity
Rate
Amount
in Rs.
in Rs
0.00
0.00 0.00
0.00
0.00 0.00
Rs: 0.00
Unit
Hour

Quantity
10.00

Rate
Amount
in Rs.
in Rs
345.00 3450.00

350

Sundries
Total hire charges of Machinery

LS

C. LABOUR:
Sl No
Description

2.00

Unit

Preliminary and Maintenance Works - Item Unit Rates 2014-15

41.00 82.00
Rs: 3532.00

Quantity

Rate
Amount
in Rs.
in Rs
370.00 185.00
295.00 590.00
Rs: 775.00

1
2

work inspector
Day
0.50
mazdoor
Day
2.00
Total cost of Labour
labour component/unit qty
1.00
Add contractor's profit and overhead charges
14% 0.10
labour component/unit qty (including contractor's profit)
1.10
ABSTRAC
T:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
(A+B+C)
Total cost for
Rate per cum
IRR-PMW-3-25

Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:

14%
807.00 cum
(A+B+C+D)/807

0.00
3532.00
775.00
4307.00
602.98
4909.98
6.10

Weed Removal by Manual Means

(New Item 2012-13-3)

IRR-PMW-3-25(a)

Removal of Water Hyacinth up to 30 cm thick


RATE ANALYSIS
Unit :

2000 Sqm

A. MATERIALS
Sl. No.
1

Unit

Quantity

Rate in Rs. Amount in Rs.


0
0
0
Rs.
0.00

Description
Unit
NIL
Total hire charges of Machinery

Quantity

Rate in Rs. Amount in Rs.


0
0
0
Rs.
0.00

Description
Unit
Work Inspector
Day
Mazdoor
Day
Total Cost of Labour

Quantity Rate in Rs. Amount in Rs.


3.5
370.00
1295
28
295.00
8260
Rs.
9555.00

Particulars
NIL
Total Cost of Materials

B. MACHINERY
Sl. No.
1

C. LABOUR
Sl. No.
1
2

ABSTRACT:
A.COST OF MATERIALS
B.COST OF MACHINERY
C.COST OF LABOUR

Rs.
Rs.
Rs.

0.00
0.00
9555.00
9555.00
1337.7
10892.70
5.4

Total
D. Add for Contractor's Profit and overheads
Total Cost for removal weed in the extent of
Rate per Sqm
IRR-PMW-3-25(b)

14%
2000 Sqm
(A+B+C+D)/2000

Removal of Water Hyacinth beyond 30 cm thick


RATE ANALYSIS
Unit :

2000 Sqm

A. MATERIALS
Sl. No.
1

Particulars
NIL

Unit
Total Cost of Materials

Quantity

Rate in Rs. Amount in Rs.


0
0
0
Rs.
0.00

351

Preliminary and Maintenance Works - Item Unit Rates 2014-15

B. MACHINERY
Sl. No.
1

Description
Unit
NIL
Total hire charges of Machinery

Quantity

Description
Unit
Work Inspector
Day
Mazdoor
Day
Total Cost of Labour

Quantity

Rate in Rs. Amount in Rs.


0
0
0
Rs.
0.00

C. LABOUR
Sl. No.
1
2

Rate in Rs. Amount in Rs.


5
370.00
1850
38
295.00
11210
Rs.
13060.00

ABSTRACT:
A.COST OF MATERIALS
B.COST OF MACHINERY
C.COST OF LABOUR

Rs.
Rs.
Rs.

0.00
0.00
13060.00
13060.00
1828.4
14888.40
7.4

Total
D. Add for Contractor's Profit and overheads
Total Cost for removal weed in the extent of
Rate per Sqm
IRR-PMW-3-25(c)

14%
2000 Sqm
(A+B+C+D)/2000

Clearing Alchi Tilla


RATE ANALYSIS
Unit :

2000 Sqm

A. MATERIALS
Sl. No.
1

Unit

Quantity

Rate in Rs. Amount in Rs.


0
0
0
Rs.
0.00

Description
Unit
NIL
Total hire charges of Machinery

Quantity

Rate in Rs. Amount in Rs.


0
0
0
Rs.
0.00

Description
Unit
Work Inspector
Day
Mazdoor
Day
Total Cost of Labour

Quantity

Particulars
NIL
Total Cost of Materials

B. MACHINERY
Sl. No.
1

C. LABOUR
Sl. No.
1
2

Rate in Rs. Amount in Rs.


3
370.00
1110
26
295.00
7670
Rs.
8780.00

ABSTRACT:
A.COST OF MATERIALS
B.COST OF MACHINERY
C.COST OF LABOUR

Rs.
Rs.
Rs.

0.00
0.00
8780.00
8780.00
1229.2
10009.20
5

Total
D. Add for Contractor's Profit and overheads
Total Cost for removal weed in the extent of
Rate per Sqm
IRR-PMW-3-25(d)

14%
2000 Sqm
(A+B+C+D)/2000

Removal of Jammu
RATE ANALYSIS
Unit :

2000 Sqm

A. MATERIALS
Sl. No.
1

Particulars
NIL

Unit

Quantity

Rate in Rs. Amount in Rs.


0
0
0
Rs.
0.00

Unit

Quantity

Rate in Rs. Amount in Rs.


0
0
0

Total Cost of Materials


B. MACHINERY
Sl. No.
1

Description
NIL

352

Preliminary and Maintenance Works - Item Unit Rates 2014-15

Total hire charges of Machinery

Rs.

0.00

C. LABOUR
Sl. No.
1
2

Description
Unit
Work Inspector
Day
Mazdoor
Day
Total Cost of Labour

Quantity Rate in Rs. Amount in Rs.


2.5
370.00
925
22
295.00
6490
Rs.
7415.00

ABSTRACT:
A.COST OF MATERIALS
B.COST OF MACHINERY
C.COST OF LABOUR

Rs.
Rs.
Rs.

0.00
0.00
7415.00
7415.00
1038.1
8453.10
4.2

Total
D. Add for Contractor's Profit and overheads
Total Cost for removal weed in the extent of
Rate per Sqm
IRR-PMW-3-25(e)

14%
2000 Sqm
(A+B+C+D)/2000

Removal of Imponea, Cornea


RATE ANALYSIS
Unit :

2000 Sqm

A. MATERIALS
Sl. No.
1

Unit

Quantity

Rate in Rs. Amount in Rs.


0
0
0
Rs.
0.00

Description
Unit
NIL
Total hire charges of Machinery

Quantity

Rate in Rs. Amount in Rs.


0
0
0
Rs.
0.00

Description
Unit
Work Inspector
Day
Mazdoor
Day
Total Cost of Labour

Quantity

Particulars
NIL
Total Cost of Materials

B. MACHINERY
Sl. No.
1

C. LABOUR
Sl. No.
1
2

Rate in Rs. Amount in Rs.


3
370.00
1110
26
295.00
7670
Rs.
8780.00

ABSTRACT:
A.COST OF MATERIALS
B.COST OF MACHINERY
C.COST OF LABOUR

Rs.
Rs.
Rs.

0.00
0.00
8780.00
8780.00
1229.2
10009.20
5

Total
D. Add for Contractor's Profit and overheads
Total Cost for removal weed in the extent of
Rate per Sqm
IRR-PMW-3-25(f)

14%
2000 Sqm
(A+B+C+D)/2000

Removal of Natchu, goobi, thooti, etc.


RATE ANALYSIS
Unit :

2000 Sqm

A. MATERIALS
Sl. No.
1

Unit

Quantity

Rate in Rs. Amount in Rs.


0
0
0
Rs.
0.00

Description
Unit
NIL
Total hire charges of Machinery

Quantity

Rate in Rs. Amount in Rs.


0
0
0
Rs.
0.00

Particulars
NIL
Total Cost of Materials

B. MACHINERY
Sl. No.
1

C. LABOUR

353

Preliminary and Maintenance Works - Item Unit Rates 2014-15

Sl. No.
1
2

Description
Unit
Work Inspector
Day
Mazdoor
Day
Total Cost of Labour

Quantity Rate in Rs. Amount in Rs.


1.2
370.00
444
8
295.00
2360
Rs.
2804.00

ABSTRACT:
A.COST OF MATERIALS
B.COST OF MACHINERY
C.COST OF LABOUR

Rs.
Rs.
Rs.

0.00
0.00
2804.00
2804.00
392.56
3196.56
1.6

Total
D. Add for Contractor's Profit and overheads
Total Cost for removal weed in the extent of
Rate per Sqm

14%
2000 Sqm
(A+B+C+D)/2000

IRR-PMW-3-26
New Item 2014-158
PAINTING OF SLUICES FOR MAINTENANCE WORKS
Surface cleaning of metal surfaces by chemical cleaners and then by hand and power tool cleaners

and removing dust. After cleaniong, applying primary coat with one coat of Zinc rich
epoxy primer to a thickness of 100 microns, followed by finishing coats 2 coats with
Coal tar epoxy with material, labour, and all accessories with all leads and lifts.
Data:
A. Materials

Rate Analysis
Sl. No.
1
2
3
4
5
6
7

Particulars
Rust Cleaner/ Inhibitor
Zinc rich epoxy primer
Thinner@10%
Coal Tar epoxy paint
Thinner@10%
Wire Brush
Sundries (brushes, Ladders,
platforms)

Unit:
Unit
ltr
ltr
ltr
ltr
ltr
ltr

Quantity
13
14
1.4
40
4
2

LS
3
Total Cost of Materials

100 Sqm
Rate in Rs. Amount in Rs.
140.00
1820
689.00
9646
140.00
196
215
8600
140.00
560
41
82
41

123
21027

B. Machinery
Sl. No.

Particulars

Unit

Quantity

Rate in Rs. Amount in Rs.

NIL
Total Cost of Machinery

C. Labour
Sl. No.
1
2

Particulars
Painter Class-II
Helper

Unit
Quantity Rate in Rs. Amount in Rs.
Day
20
345.00
6900
Day
20
295.00
5900
Total Cost of Machinery
12800
Labour Component/ Unit Qty.
128
Add Contractor's Profit and and Overhead Charges @
14%
17.92
Labour Component/ Unit Qty (including contractor' profit)
145.92
ABSTRACT:
A. Cost of Materials:
B. Hire Charges of Machinery
C. Cost of Labour

21027
0
12800
Total
33827
D. Add for Excise Duty on 75% cost excluding cost of material
0%
0
Total
33827
E. Add for transportation Charges upto worksite @
3% 1014.81
Total
34841.81
F. Add for Contractor's Profit and Overhead Charges @ 14%
14% 4877.8534
Total Cost per
100 Sqm
39719.6634
Rate per
Sqm
397.2

354

Manual works - 2014-15

(Common to all Departments)


Index_code
COM_MWRK

A. Manual Works
New extra items-- common item for all earth works using only manual labour
for all other works without involving contractors
COM_MWRK-1 (Manual)Excavation in all kinds of soil including boulders upto 0.30 m dia. for
foundations of canal cross drainage and other appurtenant structures
and placing excavated stuff neatly in specified dump area or disposing
off the same as directed etc., complete with initial lead upto 10 m and
per cum
initial lift upto 1.5 m. (WIthout involving the contractors for specified works )
With 3 Cum per day output
COM_MWRK-2 (Manual)Excavation in all kinds of soil/ HDR including boulders upto 0.30 m dia. for
foundations of canal cross drainage and other appurtenant structures
and placing excavated stuff neatly in specified dump area or disposing
off the same as directed etc., complete with initial lead upto 10 m and
per cum
initial lift upto 1.5 m. (WIthout involving the contractors for specified works )
With 2.5 Cum per day output

98.30

118.00

COM_MWRK-3 (Manual)Excavation in soft rock (including F&F) without blasting, including boulders upto 0.30 m dia. for
foundations of canal cross drainage and other appurtenant structures
and placing excavated stuff neatly in specified dump area or disposing
off the same as directed etc., complete with initial lead upto 10 m and
per cum
221.80
initial lift upto 1.5 m. (WIthout involving the contractors for specified works )
Soft rock 1.33 Cum/Day
COM_MWRK-4 (Manual)Excavation in hard rock, including boulders upto 0.30 m dia. for
foundations of canal cross drainage and other appurtenant structures
and placing excavated stuff neatly in specified dump area or disposing
off the same as directed etc., complete with initial lead upto 10 m and
per cum
initial lift upto 1.5 m. (WIthout involving the contractors for specified works )
Hard rock 0.67Cum/ day

440.30

355

COM-LDLFT-2014-15
COM-LDLFT

Chapter VII
LEAD/LIFT/LOADING & UNLOADING CHARGES
(WLL BE WITH E-N-C & TO INCORPORATE CHANGES YEARLY/ AS NEEDED)
FOR THE YEAR : 2014-15

LEAD, LIFT, LOADING AND UNLOADING CHARGES FOR MATERIALS

COM-LDLFT

COM-LDLFT-1

1. For total lead upto 150 m ( including initial lead ) lead charges by head load only shall be
adopted irrespective of mode of conveyance.
2. For total lead exceeding 150 m conveyance by mechanical means only shall be adopted
irrespective of mode of conveyance.
3. The rates for loading at quarry including idle hire charges of trucks and hire charges per for
each kilometer and upto 5 km are cumulative and inclusive of total charges for preceding lead.
4. Unless otherwise specified lead charges for Earth / Sand / Gravel / Aggregates and Stones
are for loose volume and not for compacted or in-situ volume.
5. The rates for lift charges,lead charges, hire charges are cumulative and inclusive of
rates for preceding lift,lead and hire charges
6. Lift charges are not payable where conveyance of materials is by mechanical means to
final placing point.
7. Loading and unloading charges are not payable for conveyance by head load.
8. Loading charges are not payable for conveyance by mechanical means for disposal of
excavated materials beyond initial lead of 50 m wherever specified.
9. Loading and unloading charges are not payable for conveyance by mechanical means for
disposal of excavated materials beyond initial lead of 1 km wherever specified.
10. The rates for unloading of materials except earth, sand, gravel, coarse aggregate, rubble,
size stone and cut stone are inclusive of stacking.
11. Hire charges are per 1KM for tippers and trucks for tranport of materials from work site to dump
yard and other places are cumulative& includes previous km upto 5 kms
12. The lead & lift charges are inclusive of contractor's profit and overhead charges of
14%
FOR THE YEAR: 2013-14
A. (Lead) Conveyance Charges for materials by head load
Earth / Sand
/Gravel / Murrum/ Cement /
Total distance
Lime/ Surki/ Size ReinforceSl No. ( Total lead includes initial stone / Cut stone ment steel
lead )
Rubble / Coarse Str steel
aggregate Rs/ Rs / tonne
Cum
1
2
3
4
Total lead upto 50 m
1
(covered by item rate)
initial lead
initial lead
2
Total lead upto 100 m
48.00
28.00
3
Total lead upto 150 m
96.10
56.10

PCC slab/ Shahbad


slab / CC block/ BS
slab/ Late-rite / Wood
Rs / cum
5
initial lead
61.10
122.30

Notes: 1. No loading or unloading charges are admissible for conveyance by head load.
2. For total lead exceeding 150 m conveyance charges by mechanical means only shall
be adopted irrespective of mode of conveyance.
3. The Lead Charges are inclusive of 14% Contractor Profit and Overhead charges

COM-LDLFT-2

B.( Lead) Conveyance charges for machinery per kilometer for transporting materials
by tippers and trucks excluding loading, unloading and idle hire charges of machinery.
FOR THE YEAR: 2013-14
( No loading and unloading charges allowed for machinery loading and unloading )

Sl No.

Distance

1
1
2
3
4
5

2
Lead upto 1 km
Lead upto 2 km
Lead upto 3 km
Lead upto 4 km
Lead upto 5 km
for Every km beyond 5 km
upto 30 km

(Lead)
(Lead) charges
charges for
for trucks and
(Lead) charges
(Lead)
(Lead) charges for
trucks and
(Lead)
tippers per
for trucks and
charges charges
tippers for trucks and tippers for
cu.meter for
tippers for Earth
for per for trucks
Rubble/Size Cement/ Steel/ RCC
PCC slabs/
/ Sand /Gravel /
cu.meter per 1000
stones/ Cut poles/ AC & GI sheets/
Shahabad
Murrum/ Lime/
for water/ Nos. of
Packed
Stones/
slabs/ CC &
Surki/ per
1000 litres Bricks
materials/tonne
Coarse
Laterite blocks/
cu.meter
aggregate
Wood/ cum
per cu.meter
3
31.50
44.10
58.90
71.50
84.10

4
30.40
42.60
58.90
71.50
84.10

5
19.00
26.60
36.80
44.70
52.60

6
44.70
62.60
86.60
105.10
123.70

7
18.80
26.30
35.00
42.50
50.00

8
50.70
71.00
94.60
114.90
135.20

12.60

12.60

7.90

18.50

7.50

20.30

15.50

6.30

62.60

7
for Every km beyond 30 km
10.50
10.50
6.60
Note: The Lead Charges are inclusive of 14% Contractor Profit and Overhead charges

356

COM-LDLFT-2014-15
COM-LDLFT-3

C. LOADING AND UNLOADING CHARGES BY MANUAL MEANS (idle hire charges of trucks are not added)
Rubble/ size
stone/ cut
Earth / Sand
stone/
brick work
/Gravel
steel in
Coarse
Sl No.
Description of item
Murrum/ / Surki/
cement in Rs/tonne
Rs/1000
Rs./tonne
aggregate,Li
No
me in
Rs / cum
Rs/cum
1
2
3
4
5
6
7
1
Loading
16.00
32.00
52.80
63.30
44.00
2
Unloading
8.00
16.00
52.80
63.30
44.00
Note: The Lead Charges are inclusive of 14% Contractor Profit and Overhead charges

COM-LDLFT-4

D. LOADING AND UNLOADING CHARGES BY MANUAL MEANS (including idle hire charges of trucks )
Rubble/ size
Earth / Sand
stone/ cut
/Gravel
stone/
steel in
Sl No.
Description of item
Murrum/ / Surki/
Coarse
cement in Rs/tonne
Rs./tonne
aggregate,Li
Rs / cum
me in
Rs/cum
1
2
3
4
5
6
1
Loading
108.20
124.20
154.20
164.70
2
Unloading
38.60
62.10
154.20
164.70
Note: The Lead Charges are inclusive of 14% Contractor Profit and Overhead charges

COM-LDLFT-5

brick work
Rs/1000
No

7
211.30
211.30

E. LOADING AND UNLOADING CHARGES BY MECHANICAL MEANS (including idle hire charges of trucks)
Rubble/ size
Earth / Sand
stone/ cut
/Gravel
stone/
Sl No.
Description of item
Murrum/ / Surki/
Coarse
aggregate,Li
Rs / cum
me in
Rs/cum
1
2
3
4
1
Loading
52.50
105.00
2
Unloading
15.90
15.90
Note: The Lead Charges are inclusive of 14% Contractor Profit and Overhead charges
F. LIFT CHARGES FOR MATERIALS BY HEAD LOAD

COM-LDLFT-6

Sl No.

1
1
2

Earth / Sand
/Gravel
Murrum/ Lime/
Surki/
Total lift
( Total lift includes initial lift Size stone / Cut
stone
)
Rubble / Coarse
aggregate
Rs / cum
2
Total lift upto 3 m (covered
by item rate)
For Every 1.00 Lift beyond
initial lift of 3 meters

Cement /
Reinforcement steel
Str steel
Rs / tonne

PCC slab/
Shahbad
slab / CC
block/ BS
slab / Laterite
/ Wood
Rs / cum

Initial lift
5.60

Initial lift
4.10

Initial lift
7.50

DETAILED DATA
LEAD / LIFT / LOADING & UNLOADING CHARGES - DATA RATES
Note: The Lead Charges are inclusive of 14% Contractor Profit and Overhead charges

I. GENERAL DATA FOR LEAD / LIFT / LOADING & UNLOADING:


A . DATA FOR LEAD CHARGES BY HEAD LOAD :
For the purpose of working out conveyance charges by head load the category of materials as
classified in ( I ) above are grouped together as under :
CATEGORY : Earth / Sand / Gravel / Murrum / Lime / Surki / Coarse aggregate /
Rubble stone / Size stone / Cut stone
In this group materials which are comperatively lighter and generally conveyed by head load
by light / heavy mazdoor are included. Method of conveyance, approximate weight per load
and time required to cover specified additional distance will be generally same
Therefore common data is considered for conveyance by head load for materials under this category.
CATEGORY : Cement in bag / Reinforcement steel / Structural steel sections
In this group the materials in packed / rolled / fabricated condition which are heavier per load
compared to the materials under Category above and which can not be split into small
quantities for the purpose of conveyance are included. The unit of measurement for these
materials is per tonne.
CATEGORY : PCC slab / Shahabad stone slab / CC block / Laterite stone / BS slab / Wood
In this group the materials in moulded condition / cut to standard size which are heavier per
load compared to materials under Category above are included.

357

COM-LDLFT-2014-15
COM-DTL-LDLFT-1

A. (Lead) Conveyance Charges for materials by head load


CATEGORY : Earth / Sand / Gravel / Murrum / Lime / Surki / Coarse aggregate / Rubble stone
/ Size stone / Cut stone
Lead: Upto 50 m :
This is initial lead and cost is covered under item basic rate.
Lead: Upto 100 m :
Average distance to be covered beyond initial lead of 50 m
Average speed of conveyance by head load
Round trip cycle time for 25 m considering 50 min/ hr working
( 2 x 25 x 60 / 50 / 60 )
No. of trips per day for additional lead ( 8 x 60 / 1 )
Quantity of material by head load per load
Quantity of material by head load per day ( 480 x 0.015 ) say
Deploy one mazdoor for every 50 m additional lead beyond initial lead.
Unit:
Sl No.
1

Description
Mazdoor

Unit
Day

Contractor's profit and


14%
overhead charges
Total for materials under this Category 7
Rate per

Quantity
1
Total Rs:

cum
cum

Lead: Upto 150 m :


Average distance to be covered beyond initial of 50 m :
50
Deploy two mazdoors for conveyance beyond initial lead.
Unit:
Sl No.
1

Description
Mazdoor

Unit
Day

Contractor's profit and


overhead charges
14%
Total for materials under this Category 7
Rate per

Quantity
2
Total Rs:

cum
cum

25
60

m
m / minute

1
480
0.015
7

min

7
Rate
in Rs.
295

cum
cum
cum
Amount in Rs.
295
295
41.3
336.3
48.00

Rs:
Rs:

m
7
Rate
in Rs.
295

cum
Amount in Rs.
590
590
82.6
672.6
96.10

Rs:
Rs:

CATEGORY : Cement in bag / Reinforcement steel / Structural steel sections


Lead: Upto 50 m :
This is initial lead and cost is covered under item basic rate.
Lead: Upto 100 m :
Average distance to be covered beyond initial lead of 50 m
Average speed of conveyance by head load
Round trip cycle time for 25 m considering 50 min/ hr working
( 2 x 25 x 60 / 50 / 30 )
No. of trips per day for lead upto 100 m ( 8 x 60 / 2 )
Quantity of material by head load per load
Quantity of material by head load per day ( 240 x 50 / 1000 )
Deploy one mazdoor for every 50 m additional lead beyond initial lead.
Unit:
Sl No.
Description
Unit
Quantity
Cement /steel handling
mazdoor
1
Day
1
Total Rs:
Contractor's profit and
overhead charges
14%
tonne
Total for materials under this Category 12.00
Rate per
tonne
Lead: Upto 150 m :
Average distance to be covered beyond initial of 50 m :
50
Deploy two mazdoors for conveyance beyond initial lead.
Unit:
Sl No.
Description
Unit
Quantity
Cement /steel handling
1
Mazdoor
Day
2
Total Rs:
Contractor's profit and
overhead charges
14%
tonne
Total for materials under this Category 12.00
Rate per
tonne
Rs:

25
30

m
m / minute

2
240
50
12

min
kg
tonne

12
Rate in Rs.

tonne
Amount in Rs.

295

295
295
41.3
336.3
28.00

Rs:
Rs:

m
12
Rate in Rs.

tonne
Amount in Rs.

295

590
590
82.6
672.6

Rs:
56.10

CATEGORY : PCC slab / Shahabad stone slab / CC block / Laterite stone / BS slab / Wood
Lead: Upto 50 m :
This is initial lead and cost is covered under item basic rate.
Lead: Upto 100 m :
Average distance to be covered beyond initial lead of 50 m
Average speed of conveyance by head load
Round trip cycle time for 25 m considering 50 min/ hr working
( 2 x 25 x 60 / 50 / 40 )

25
40

m
m / minute

1.5

min

358

COM-LDLFT-2014-15
No. of trips per day for lead upto 100 m ( 8 x 60 / 1.5 )
Quantity of material by head load per load
Quantity of material by head load per day ( 320 x 0.017 ) say
Deploy one mazdoor for every 50 m additional lead beyond initial lead.
Unit:
Sl No.
Description
Unit
Quantity
1
Mazdoor
Day
1
Total Rs:
Contractor's profit and
overhead charges
14%
cum
Total for materials under this Category 5.5
Rate per
cum
Lead: Upto 150 m :
Average distance to be covered beyond initial of 50 m :
Deploy two mazdoors for conveyance beyond initial lead.
Sl No.
1

Description
Mazdoor

Unit
Day

Contractor's profit and


14%
overhead charges
Total for materials under this Category 5.5
Rate per

COM-DTL-LDLFT-2

Unit:
Quantity
2
Total Rs:

cum
cum

320
0.017
5.5
5.5
Rate in Rs.
295

cum
cum
cum
Amount in Rs.
295
295

Rs:
Rs:

41.3
336.3
61.10

50

5.5
Rate in Rs.
295

cum
Amount in Rs.
590
590

Rs:
Rs:

82.6
672.6
122.30

B.( Lead) Conveyance charges for machinery per kilometer for transporting materials by tippers and trucks
excluding loading, unloading and idle hire charges of machinery.
CATEGORY : Earth / Sand / Gravel / Murrum / Lime / Surki /
For total lead upto 1 km
Sl No.
Description
1
Tipper hire charges
Fuel charges
2
Crew charges
Contractor's profit and
overhead charges
Total for
Rate per cum

Unit
Hour
Hour
Hour

14%
5

For total lead more than 1 km upto 2 km


Sl No.
Description
Unit
1
Tipper hire charges
Hour
Fuel charges
Hour
2
Crew charges
Hour
Contractor's profit and
overhead charges
Total for
Rate per cum

14%
5

For total lead more than 2 km upto 3 km


Sl No.
1
2

Description
Tipper hire charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per cum

14%
5

For total lead more than 3 km upto 4 km


Sl No.
1
2

Description
Tipper hire charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per cum

14%
5

For total lead more than 4 km upto 5 km


Sl No.
1
2

Description
Tipper hire charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Unit:
Quantity
0.15
0.15
0.15
Total Rs:

5
Rate in Rs.
446.70
322.20
153.10

cum

Rs:

Unit:
Quantity
0.21
0.21
0.21
Total Rs:

5
Rate in Rs.
446.70
322.20
153.10

cum

Rs:

Unit:

Quantity
0.28
0.28
0.28
Total Rs:

Rate in Rs.
446.70
322.20
153.10

cum

Rs:

Unit:

5
Rate
in Rs.
446.70
322.20
153.10

Quantity
0.34
0.34
0.34
Total Rs:

cum

Rs:

Unit:

5
Rate
in Rs.
446.70
322.20
153.10

Quantity
0.4
0.4
0.4
Total Rs:

cum
Amount in Rs.
67.01
48.33
22.97
138.31
19.36
157.67
31.50
cum
Amount in Rs.
93.81
67.66
32.15
193.62
27.11
220.73
44.10
cum
Amount
in Rs.
125.08
90.22
42.87
258.17
36.14
294.31
58.90
cum
Amount
in Rs.
151.88
109.55
52.05
313.48
43.89
357.37
71.50
cum
Amount
in Rs.
178.68
128.88
61.24
368.80

359

COM-LDLFT-2014-15
Contractor's profit and
overhead charges
Total for
Rate per cum

14%
5

cum

Rs:

For lead beyond 5 km upto 30 km for every km

Unit:

Sl No.
1

Quantity
0.06
0.06
0.06
Total Rs:

5
Rate
in Rs.
446.70
322.20
153.10

Description
Tipper hire charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per cum

14%
5

For lead beyond 30 km for every km


Sl No.
1
2

Description
Tipper hire charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per cum

14%
5

cum

Rs:

Unit:

5
Rate
in Rs.
446.70
322.20
153.10

Quantity
0.05
0.05
0.05
Total Rs:

cum

Rs:

51.63
420.43
84.10
cum
Amount
in Rs.
26.80
19.33
9.19
55.32
7.74
63.06
12.60
cum
Amount
in Rs.
22.34
16.11
7.66
46.11
6.46
52.57
10.50

CATEGORY : Coarse aggregate / Rubble stone / Size stone / Cut stone


For total lead upto 1 km
Sl No.
1
2

Unit:

Description
Truck hire charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per cum

14%
5

For total lead more than 1 km upto 2 km


Sl No.
1
2

Description
Truck hire charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per cum

14%
5

For total lead more than 2 km upto 3 km


Sl No.
1
2

Description
Tipper hire charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per cum

14%
5

For total lead more than 3 km upto 4 km


Sl No.
1
2

Description
Tipper hire charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per cum

14%
5

For total lead more than 4 km upto 5 km


Sl No.
1
2

Description
Tipper hire charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Quantity
0.15
0.15
0.15
Total Rs:

5
Rate
in Rs.
414.10
322.20
153.10

cum

Rs:

Unit:

5
Rate
in Rs.
414.10
322.20
153.10

Quantity
0.21
0.21
0.21
Total Rs:

cum

Rs:

Unit:

5
Rate
in Rs.
446.70
322.20
153.10

Quantity
0.28
0.28
0.28
Total Rs:

cum

Rs:

Unit:

5
Rate
in Rs.
446.70
322.20
153.10

Quantity
0.34
0.34
0.34
Total Rs:

cum
Amount
in Rs.
62.12
48.33
22.97
133.42
18.68
152.10
30.40
cum
Amount
in Rs.
86.96
67.66
32.15
186.77
26.15
212.92
42.60
cum
Amount
in Rs.
125.08
90.22
42.87
258.17
36.14
294.31
58.90
cum
Amount
in Rs.
151.88
109.55
52.05
313.48

cum

Rs:

43.89
357.37
71.50

Unit:

5
Rate
in Rs.
446.70
322.20
153.10

cum
Amount
in Rs.
178.68
128.88
61.24

Quantity
0.4
0.4
0.4

360

COM-LDLFT-2014-15
Total Rs:

0.00

368.80

cum

Rs:

51.63
420.43
84.10

For lead beyond 5 km upto 30 km for every km

Unit:

Sl No.
1

Quantity
0.06
0.06
0.06
Total Rs:

5
Rate
in Rs.
446.70
322.20
153.10

Contractor's profit and


overhead charges
Total for
Rate per cum

14%
5

Description
Tipper hire charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per cum

14%
5

For lead beyond 30 km for every km


Sl No.
1
2

Description
Tipper hire charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per cum

14%
5

cum

Rs:

Unit:

5
Rate
in Rs.
446.70
322.20
153.10

Quantity
0.05
0.05
0.05
Total Rs:

cum

Rs:

cum
Amount
in Rs.
26.80
19.33
9.19
55.32
7.74
63.06
12.60
cum
Amount
in Rs.
22.34
16.11
7.66
46.11
6.46
52.57
10.50

CATEGORY : Cement/ Steel/ Pipes/ RCC poles/ AC & GI sheets/ Packed materials
For total lead upto 1 km
Sl No.
1
2

Unit:

Description
Truck hire charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per tonne

14%
8

For total lead more than 1 km upto 2 km


Sl No.
1
2

Description
Truck hire charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per tonne

14%
8

For total lead more than 2 km upto 3 km


Sl No.
1
2

Description
Tipper hire charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per tonne

14%
8

For total lead more than 3 km upto 4 km


Sl No.
1
2

Description
Tipper hire charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per tonne

14%
8

For total lead more than 4 km upto 5 km


Sl No.
1

Description
Tipper hire charges
Fuel charges

Unit
Hour
Hour

Quantity
0.15
0.15
0.15
Total Rs:

8
Rate
in Rs.
414.10
322.20
153.10

tonne

Rs:

Unit:

8
Rate
in Rs.
414.10
322.20
153.10

Quantity
0.21
0.21
0.21
Total Rs:

tonne

Rs:

Unit:

8
Rate
in Rs.
446.70
322.20
153.10

Quantity
0.28
0.28
0.28
Total Rs:

tonne

Rs:

Unit:

8
Rate
in Rs.
446.70
322.20
153.10

Quantity
0.34
0.34
0.34
Total Rs:

tonne
Amount
in Rs.
62.12
48.33
22.97
133.42
18.68
152.10
19.00
tonne
Amount
in Rs.
86.96
67.66
32.15
186.77
26.15
212.92
26.60
tonne
Amount
in Rs.
125.08
90.22
42.87
258.17
36.14
294.31
36.80
tonne
Amount
in Rs.
151.88
109.55
52.05
313.48

tonne

Rs:

43.89
357.37
44.70

Unit:

8
Rate
in Rs.
446.70
322.20

tonne
Amount
in Rs.
178.68
128.88

Quantity
0.4
0.4

361

COM-LDLFT-2014-15
2

Crew charges

Hour

Contractor's profit and


overhead charges
Total for
Rate per tonne

14%
8

0.4
Total Rs:

153.10

tonne

Rs:

For lead beyond 5 km upto 30 km for every km

Unit:

Sl No.
1

Quantity
0.06
0.06
0.06
Total Rs:

8
Rate
in Rs.
446.70
322.20
153.10

Description
Tipper hire charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per tonne

14%
8

For lead beyond 30 km for every km


Sl No.
1
2

Description
Tipper hire charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per tonne

14%
8

tonne

Rs:

Unit:

8
Rate
in Rs.
446.70
322.20
153.10

Quantity
0.05
0.05
0.05
Total Rs:

tonne

Rs:

61.24
368.80
51.63
420.43
52.60
tonne
Amount
in Rs.
26.80
19.33
9.19
55.32
7.74
63.06
7.90
tonne
Amount
in Rs.
22.34
16.11
7.66
46.11
6.46
52.57
6.60

CATEGORY : PCC slabs/ Shahabad slabs/ BS slabs/ CC & Laterite blocks/ Wood
For total lead upto 1 km
Sl No.
1
2

Unit:

Description
Truck hire charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per cum

14%
3.4

For total lead more than 1 km upto 2 km


Sl No.
1
2

Description
Truck hire charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per cum

14%
3.4

For total lead more than 2 km upto 3 km


Sl No.
1
2

Description
Tipper hire charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per cum

14%
3.4

For total lead more than 3 km upto 4 km


Sl No.
1
2

Description
Tipper hire charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per cum

14%
3.4

For total lead more than 4 km upto 5 km


Sl No.
1

Description
Tipper hire charges

Unit
Hour

Quantity
0.15
0.15
0.15
Total Rs:

3.4
Rate
in Rs.
414.10
322.20
153.10

cum

Rs:

Unit:

3.4
Rate
in Rs.
414.10
322.20
153.10

Quantity
0.21
0.21
0.21
Total Rs:

cum

Rs:

Unit:

3.4
Rate
in Rs.
446.70
322.20
153.10

Quantity
0.28
0.28
0.28
Total Rs:

cum

Rs:

Unit:

3.4
Rate
in Rs.
446.70
322.20
153.10

Quantity
0.34
0.34
0.34
Total Rs:

cum
Amount
in Rs.
62.12
48.33
22.97
133.42
18.68
152.10
44.70
cum
Amount
in Rs.
86.96
67.66
32.15
186.77
26.15
212.92
62.60
cum
Amount
in Rs.
125.08
90.22
42.87
258.17
36.14
294.31
86.60
cum
Amount
in Rs.
151.88
109.55
52.05
313.48

cum

Rs:

43.89
357.37
105.10

Unit:

3.4
Rate
in Rs.
446.70

cum
Amount
in Rs.
178.68

Quantity
0.4

362

COM-LDLFT-2014-15

Fuel charges
Crew charges

Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per cum

14%
3.4

0.4
0.4
Total Rs:

322.20
153.10

cum

Rs:

For lead beyond 5 km upto 30 km for every km

Unit:

Sl No.
1

Quantity
0.06
0.06
0.06
Total Rs:

3.4
Rate
in Rs.
446.70
322.20
153.10

Description
Tipper hire charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per cum

14%
3.4

For lead beyond 30 km for every km


Sl No.
1
2

Description
Tipper hire charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per cum

14%
3.4

cum

Rs:

Unit:

3.4
Rate
in Rs.
446.70
322.20
153.10

Quantity
0.05
0.05
0.05
Total Rs:

cum

Rs:

Unit:

8000
Rate
in Rs.
402.50
322.20
153.10

128.88
61.24
368.80
51.63
420.43
123.70
cum
Amount
in Rs.
26.80
19.33
9.19
55.32
7.74
63.06
18.50
cum
Amount
in Rs.
22.34
16.11
7.66
46.11
6.46
52.57
15.50

CATEGORY : water
For total lead upto 1 km
Sl No.
1
2

Description
Water tanker hire charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per 1000 litres

14%
8000

For total lead more than 1 km upto 2 km


Sl No.
1
2

Description
Water tanker hire charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per 1000 litres

14%
8000

For total lead more than 2 km upto 3 km


Sl No.
1
2

Description
Water tanker hire charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per 1000 litres

14%
8000

For total lead more than 3 km upto 4 km


Sl No.
1
2

Description
Water tanker hire charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per 1000 litres

14%
8000

For total lead more than 4 km upto 5 km


Sl No.

Description

Unit

Quantity
0.15
0.15
0.15
Total Rs:

litres

Rs:

Unit:

8000
Rate
in Rs.
402.50
322.20
153.10

Quantity
0.21
0.21
0.21
Total Rs:

litres

Rs:

Unit:

8000
Rate
in Rs.
402.50
322.20
153.10

Quantity
0.28
0.28
0.28
Total Rs:

litres

Rs:

Unit:

8000
Rate
in Rs.
402.50
322.20
153.10

Quantity
0.34
0.34
0.34
Total Rs:

litres
Amount
in Rs.
60.38
48.33
22.97
131.68
18.44
150.12
18.80
litres
Amount
in Rs.
84.53
67.66
32.15
184.34
25.81
210.15
26.30
litres
Amount
in Rs.
112.70
90.22
42.87
245.79
34.41
280.20
35.00
litres
Amount
in Rs.
136.85
109.55
52.05
298.45

litres

Rs:

41.78
340.23
42.50

Unit:

8000
Rate
in Rs.

litres
Amount
in Rs.

Quantity

363

COM-LDLFT-2014-15
1
2

Water tanker hire charges


Fuel charges
Crew charges

Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per 1000 litres

14%
8000

0.4
0.4
0.4
Total Rs:

402.50
322.20
153.10

litres

Rs:

For lead beyond 5 km upto 30 km for every km

Unit:

Sl No.
1

Quantity
0.06
0.06
0.06
Total Rs:

8000
Rate
in Rs.
402.50
322.20
153.10

Description
Water tanker hire charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per 1000 litres

14%
8000

For lead beyond 30 km for every km


Sl No.
1
2

Description
Water tanker hire charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per 1000 litres

14%
8000

litres

Rs:

Unit:

8000
Rate
in Rs.
402.50
322.20
153.10

Quantity
0.05
0.05
0.05
Total Rs:

litres

Rs:

Unit:

3000
Rate
in Rs.
414.10
322.20
153.10

161.00
128.88
61.24
351.12
49.16
400.28
50.00
litres
Amount
in Rs.
24.15
19.33
9.19
52.67
7.37
60.04
7.50
litres
Amount
in Rs.
20.13
16.11
7.66
43.90
6.15
50.05
6.30

CATEGORY : Bricks (as adopted by R&B(Buildings))


For total lead upto 1 km
Sl No.
1
2

Description
Truck 10 T charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per 1000 bricks

14%
3000

For total lead more than 1 km upto 2 km


Sl No.
1
2

Description
Truck 10 T charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per 1000 bricks

14%
3000

For total lead more than 2 km upto 3 km


Sl No.
1
2

Description
Truck 10 T charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per 1000 bricks

14%
3000

For total lead more than 3 km upto 4 km


Sl No.
1
2

Description
Truck 10 T charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per 1000 bricks

14%
3000

For total lead more than 4 km upto 5 km

Quantity
0.15
0.15
0.15
Total Rs:

bricks

Rs:

Unit:

3000
Rate
in Rs.
414.10
322.20
153.10

Quantity
0.21
0.21
0.21
Total Rs:

bricks

Rs:

Unit:

3000
Rate
in Rs.
414.10
322.20
153.10

Quantity
0.28
0.28
0.28
Total Rs:

bricks

Rs:

Unit:

3000
Rate
in Rs.
414.10
322.20
153.10

Quantity
0.34
0.34
0.34
Total Rs:

bricks
Amount
in Rs.
62.12
48.33
22.97
133.42
18.68
152.10
50.70
bricks
Amount
in Rs.
86.96
67.66
32.15
186.77
26.15
212.92
71.00
bricks
Amount
in Rs.
115.95
90.22
42.87
249.04
34.87
283.91
94.60
bricks
Amount
in Rs.
140.79
109.55
52.05
302.39

bricks

Rs:

42.33
344.72
114.90

Unit:

3000

bricks

364

COM-LDLFT-2014-15

Sl No.
1
2

Description
Truck 10 T charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per 1000 bricks

14%
3000

bricks

Rs:

For lead beyond 5 km upto 30 km for every km

Unit:

Sl No.
1

Quantity
0.06
0.06
0.06
Total Rs:

3000
Rate
in Rs.
414.10
322.20
153.10

Description
Truck 10 T charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per 1000 bricks

14%
3000

For lead beyond 30 km for every km


Sl No.
1
2

COM-DTL-LDLFT-3

Quantity
0.4
0.4
0.4
Total Rs:

Rate
in Rs.
414.10
322.20
153.10

Description
Truck 10 T charges
Fuel charges
Crew charges

Unit
Hour
Hour
Hour

Contractor's profit and


overhead charges
Total for
Rate per 1000 litres

14%
3000

bricks

Rs:

Unit:

3000
Rate
in Rs.
414.10
322.20
153.10

Quantity
0.05
0.05
0.05
Total Rs:

bricks

Amount
in Rs.
165.64
128.88
61.24
355.76
49.81
405.57
135.20
bricks
Amount
in Rs.
24.85
19.33
9.19
53.37
7.47
60.84
20.30
bricks
Amount
in Rs.
20.71
16.11
7.66
44.48
6.23
50.71
16.90

Rs:

C. LOADING AND UNLOADING CHARGES BY MANUAL MEANS (idle hire charges of trucks are not added)
MORD -data
1
Loading of Lime, Aggregate, Stone Boulder,
a) Loading Brick Aggregate, Kankar, Building Rubbish,
Unit
Quantity
Rate Rs.
Amount Rs.
Building Rubbish, Crushed Slag, Stone for Masonry
Work by manual means including a lead upto 30 m
Unit = cum
Taking output = 5.5 cum
Labour
Head Mazdoor
day
0.02
345.00
6.90
Mazdoor
day
0.5
295
147.50
Total in Rs.
154.40
contractor's profit and
overhead charges
14%
21.62
Rate per cum =
Rs.
32.00
b) Unloading50% of the loading charges 16.00

Loading of Earth, Sand, Moorum, Manure, Flya


Unit
2
a) Loading by manual means including a lead upto 30 m
Unit = cum
Taking output = 5.5 cum
Labour
Head Mazdoor
day
0.01
Mazdoor
day
0.25
Total in Rs.
contractor's profit and
overhead charges
14%
Rate per cum =

Quantity

Rate Rs.

345.00
295

Amount
Rs.

3.45
73.75
77.20
10.81
16.00

Rs.

b) Unloading50% of the loading charges 8.00


3
Loading of Bricks by manual means
a) Loading including a lead upto 30 m
Unit = 1000 Nos.
Taking output = 2000 Nos
a) Labour
Head Mazdoor
Mazdoor
Cost for 2000 Nos. =
contractor's profit and
overhead charges
14%
Rate per cum =
100% of loading charges
b) Unloadingi.e., Rs.
4

Unit

day
day

Quantity

0.01
0.25

Rate Rs.

345.00
295

Amount Rs.

3.45
73.75
77.20
10.81
44.00

Rs.

44.00

Loading of Cement by manual means

Unit

Quantity

Rate Rs.

Amount Rs.

365

COM-LDLFT-2014-15
a) Loading including a lead upto 30 m
Unit = 1 t
Taking output = 10 t
a) Labour
Head mazdoor
Mazdoor
Cost for 10 t =
contractor's profit and
overhead charges
14%
Rate per 1 tonne =

day
day

0.06
1.5

345.00
295

20.70
442.50
463.20
64.85
52.80

Rs.

b) Unloading100% of loading charges I.e 52.80


5
Loading of Structural Steel, Steel Bars by man
Unit
a) Loading including a lead upto 30 m
Unit = 1 t
Taking output = 10 t
a) Labour
head Mazdoor
day
Mazdoor
day
Cost for 10 t =
contractor's profit and
14%
overhead charges
Rate per 1 tonne =
100% of loading charges
b) UnloadingI.e., Rs.

COM-DTL-LDLFT-4

0.07
1.8

Rate Rs.

345.00
295

Amount Rs.

24.15
531.00
555.15
77.72
63.30

Rs.

63.30

6
Unit
Loading of Bricks - 1000 Nos (Regular sizes a) Loading 225x140x70 mm) by manual means including
Unit = 1000 Nos.
Taking output = 2000 Nos.
a) Labour
head Mazdoor
day
Mazdoor
day
Cost for 2000 Nos. =
contractor's profit and
overhead charges
14%
Rate per 1000 Nos. =
100% of loading charges
b) UnloadingI.e., Rs.

Quantity

Quantity

0.01
0.25

Rate Rs.

345.00
295.00

Amount Rs.

3.45
73.75
77.20
10.81
44.00

Rs.

44.00

D. LOADING AND UNLOADING CHARGES BY MANUAL MEANS (including idle hire charges of trucks )
1
Loading of Lime, Aggregate, Stone Boulder,
a) Loading Brick Aggregate, Kankar, Building Rubbish,
Building Rubbish, Crushed Slag, Stone for Mas
Unit
Work by manual means including a lead upto 30 m
Unit = cum
Taking output = 5.5 cum
a) Labour
Head Mazdoor
day
Mazdoor
day
b) Machinery
Truck 10t
hour
Cost for 5.5 cum =
contractor's profit and
overhead charges
14%
Rate per cum =
b) Unloading50% of the loading charges i.e.,

Quantity

Rate Rs.

Amount Rs.

0.02
0.5

345.00
295

6.90
147.50

0.5

889.40

444.70
599.10
83.87
124.20

Rs.

62.1

2
Loading of Earth, Sand, Moorum, Manure, Flya
Unit
a) Loading by manual means including a lead upto 30 m
Unit = cum
Taking output = 5.5 cum
Labour
Head Mazdoor
day
Mazdoor
day
b) Machinery
Truck 10t
hour
Cost for 5.5 cum =
contractor's profit and
overhead charges
14%
Rate per cum =
b) UnloadingUnloading of Earth, Sand, Moorum, Manure, F
Unit
by manual means including a lead upto 30 m
Unit = cum
Taking output = 5.5 cum
a) Labour
Mate
day
Mazdoor(unskilled)
day

Quantity

Rate Rs.

Amount Rs.

0.01
0.25

345.00
295

3.45
73.75

0.5

889.40

444.70
521.90
73.07
108.20

Rs.
Quantity

0.005
0.125

Rate Rs.

345.00
295

Amount Rs.

1.73
36.88

366

COM-LDLFT-2014-15
b) Machinery
Truck 10t
Cost for 5.5 cum =
contractor's profit and
overhead charges
Rate per cum =

hour

0.166

889.40

14%

Loading of Bricks by manual means


3
a) Loading including a lead upto 30 m
Unit = 1000 Nos.
Taking output = 2000 Nos
a) Labour
Mate
Mazdoor(unskilled)
b) Machinery
Truck 10t
Cost for 2000 Nos. =
contractor's profit and
overhead charges
14%
Rate per 1000 bricks =

26.08
38.60

Rs.

Unit

Quantity

147.64
186.25

Rate Rs.

Total

day
day

0.01
0.25

345.00
295

3.45
73.75

hour

0.33

889.40

293.50
370.70
51.90
211.30

Rs.

b) Unloading100% of loading charges i.e 211.30


4
Loading of Cement by manual means
a) Loading including a lead upto 30 m
Unit = 1 t
Taking output = 10 t
a) Labour
Mate
Mazdoor(unskilled)
b) Machinery
Truck 10t
Cost for 10 t =
contractor's profit and
overhead charges
14%
Rate per 1 tonne =

Unit

Quantity

Rate Rs.

Total

day
day

0.06
1.5

345.00
295

20.70
442.50

hour

889.40

889.40
1352.60
189.36
154.20

Rs.

b) Unloading100% of loading charges i.e 154.20


5
Loading of Structural Steel, Steel Bars by man
Unit
a) Loading including a lead upto 30 m
Unit = 1 t
Taking output = 10 t
a) Labour
Mate
day
Mazdoor(unskilled)
day
b) Machinery
Truck 10t
hour
Cost for 10 t =
contractor's profit and
overhead charges
14%
Rate per 1 tonne =

Quantity

Rate Rs.

Total

0.07
1.8

345.00
295

24.15
531.00

889.40

889.40
1444.55
202.24
164.70

Rs.

b) Unloading100% of loading charges i.e 164.70


COM-DTL-LDLFT-5

E. LOADING AND UNLOADING CHARGES BY MECHANICAL MEANS (including idle hire charges of trucks)

COM-DTL-LDLFT-5-A

1
Loading of Lime, Aggregate, Stone Boulder,
a) Loading Brick Aggregate, Kankar, Building Rubbish,
Crushed Slag, Stone for Masonry work by
mechanical means including a lead upto 30 m
Unit
Placing tipper at loading point, loading with front end
loader excluding time for haulage and return trip.
Unit = cum
Taking output = 5.5 cum
Time required for
i) Positioning of tipper at loading point
Min
ii) Loading by front end loader 1 cum bucket caMin
@ 45 / 25 cum per hour
iii) Manoevouring, reversing, dumping and turn Min
for return
iv) Waiting time, unforeseen contingencies, etcMin
Total
Min
a) Machinery
Tipper 10 t capacity
hour
Front end-loader 1 cum bucket capacity @ 45 chour
per hour
Cost for 5.5 cum =
b) contractor's profit and
overhead charges
14%
Rate per cum = (a+b)/5.5

Quantity

Rate Rs.

Total

1
7.33
2
10.33
0.17
0.12

922.00
2848.50

158.74
347.99
506.73

Rs.

70.94
105.00

b) Unloadingsee below. COM-LDLFT-5-B

367

COM-LDLFT-2014-15
COM-DTL-LDLFT-5-B

2
Loading of Earth, sand, Moorum, Manure, Flyash,
a) Loading by mechanical means including a lead upto 30 m
Placing tipper at loading point, loading with front
end loader excluding time for haulage and retu
Unit
Placing tipper at loading point, loading with front
end loader excluding time for haulage and return trip.
Unit = cum
Taking output = 5.5 cum
Time required for
i) Positioning of tipper at loading point
Min
ii) Loading by front end loader 1 cum bucket caMin
@ 45 / 25 cum per hour
iii) Waiting time, unforeseen contingencies, etcMin
Total
Min
a) Machinery
Tipper 10 t capacity
hour
Front end-loader 1 cum bucket capacity @ 45 chour
per hour
Cost for 5.5 cum =
b) contractor's profit and
overhead charges
14%
Rate per cum = (a+b)/5.5
b) UnloadingUnloading of Earth, sand, Moorum, Manure, Flyash,
lime, Aggregate, Stone boulder, Brick aggregate,
Kankar, Building rubbish, Manure, Crushed Sla
Unit
Flyash, Stone for Masonry work by mechanical
means including a lead upto 30 m
Placing tipper at unloading point, excluding time
for haulage and return trip.
Taking output = 5.5 cum
Time required for
i) Positioning of tipper at loading point
Min
ii) Loading by front end loader 1 cum bucket caMin
@ 45 / 25 cum per hour
iii) Waiting time, unforeseen contingencies, etcMin
Total
a) Machinery
Tipper 10 t capacity
hour
Cost for 5.5 cum =
b) contractor's profit and
overhead charges
14%
Rate per cum = (a+b)/5.5

COM-DTL-LDLFT-6

Quantity

Rate Rs.

Total

1
3.3
2
6.3
0.105
0.055

922.00 96.81
2848.50 156.67
253.48
35.49
52.50

Rs.

Quantity

Rate Rs.

Total

1
2
2
5
0.08

922.00 76.83
76.83
10.76
15.90

F. LIFT CHARGES FOR MATERIALS BY HEAD LOAD


FOR CATEGORY : Earth / Sand / Gravel / Murrum / Lime / Surki / Coarse aggregate /
Rubble stone / Size stone / Cut stone
Lift : Upto 3.00 m
This is the initial lift and forms integral part of the activities in the basic rate of work item.
Lift charges are admissible only lifting effort beyond initial lift specified in the work item.
Lift : ADDITIONAL LIFT CHARGES FOR each 1 METER LIFT BEYOND 3 M INITIAL LIFT
For additional lift of 1m beyond initial lift of 3 m
one meter lift is taken equivalent to 6 meters lead
average speed of conveyance by head load
Round trip cycle time for 1.00 m considering 50 min/ hr working
1 x6x 60 / 50 / 60 )
No. of trips per day for lift 1.0 m above 3 m ( 8 x 60 / 0..12)
Quantity of material by head load
Quantity of material by head load per day ( 4000x 0.015 )
Deploy 1 mazdoor for every additional lift of 1.0 m beyond initial lift.
Lift : Upto 3.00 m for materials under this Category
Unit:
Sl No.
1

Description
2
Mazdoor
contractor's profit and
overhead charges

Unit
3
Day

Quantity
4
1.00

60 m/minute
0.12
4000
0.015
60

min
cum
cum

60
Rate
in Rs.
5
295.00

14%
Total Rs: for 60
cum

cum
Amount
in Rs.
6
295.00
41.30

Rate per cum


FOR CATEGORY: Cement bag / Reinforcement steel / Structural steel sections
Lift : Upto 3.00 m
This is the initial lift and forms integral part of the activities in the basic rate of work item.
Lift charges are admissible only lifting effort beyond initial lift specified in the work item.

336.30
5.60

Lift : ADDITIONAL LIFT CHARGES FOR each 1 METER LIFT BEYOND 3 M INITIAL LIFT
For additional lift of 1m beyond initial lift of 3 m
one meter lift is taken equivalent to 6 meters lead
average speed of conveyance by head load
Round trip cycle time for 1.00 m considering 50 min/ hr working

25 m/minute

368

COM-LDLFT-2014-15
1 x6x 60 / 50 / 25 )
0.29
min
No. of trips per day foradditional lift 1.0 m above 3 m ( 8 x 60 / 0.29)
1655
Quantity of material by head load
50
kgs
Quantity of material by head load per day ( 1655x50x 0.015 )
83
tons
Deploy 1 mazdoor for every additional lift of 1.5 m beyond initial lift.or2/3 mazdoor
Lift : Upto 3.00 m for materials under this Category
Unit:
83
TONS
Rate
Amount
Sl No.
Description
Unit
Quantity
in Rs.
in Rs.
1
2
3
4
5
6
Mazdoor
Day
1.00
295.00
295.00
contractor's profit and
overhead charges
14%
41.30
Total Rs: for 83
Tonnes
336.30
Rate per tonne
4.10
FOR CATEGORY : PCC slab / Shahabad stone slab / CC block / Laterite stone / BS slab / Wood
Lift : Upto 3.00 m
This is the initial lift and forms integral part of the activities in the basic rate of work item.
Lift charges are admissible only lifting effort beyond initial lift specified in the work item.
Lift : ADDITIONAL LIFT CHARGES FOR EACH 1 METER LIFT BEYOND 3 M INITIAL LIFT
For additional lift of 1m beyond initial lift of 3 m
one meter lift is taken equivalent to 6 meters lead
average speed of conveyance by head load
40 m/minute
Round trip cycle time for 1.00 m considering 50 min/ hr working
1 x6x 60 / 50 / 40 )
0.18
No. of trips per day for lift 1.0 m ( 8 x 60 / 0.18 )
2667
Quantity of material by head load
0.017
Quantity of material by head load per day ( 1667x 0.018 )
45
Deploy 1 mazdoor for every additional lift of 1.5 m beyond initial lift.or2/3 mazdoor
Lift : Upto 3.00 m for materials under Category
Sl No.
1

Description
2
Mazdoor
contractor's profit and
overhead charges

Rate per cum

Unit:
Unit
3

Day
14%
Total Rs: for 45
cum

Quantity
4
1.00

45
Rate
in Rs.
5
295.00

min
cum
cum

cum
Amount
in Rs.
6
295.00
41.30
336.30
7.50

369

Hire Charges- for the year 2014-15

HIRE CHARGES OF MACHINERY


FOR THE YEAR : 2014-15
S.No

1
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50

Description of machinery

2
Agitator car / Transit mixer 2 cum
Air compressor 5 cmm ( electric )
Air compressor 7 cmm ( diesel )
Air compressor 7 cmm ( electric )
Air compressor 8.5 cmm ( diesel
Air compressor 8.5 cmm ( electric)
Air compressor 15 cmm ( electric)
Angle Dozer 90 hp
Batching plant 0.5 cum( 6 cum/hr)
Batching plant 2 x 1.00 cum(15 cum/hr)
Batching plant 2 x 1.50 cum(50 cum/hr)
Bending machine 3000 x 12 mm
Clamp shell and hoisting ropes
Concrete bucket 1.5 cum
Concrete hand mixer 45 / 30 ltr
Concrete mixer 300 / 200 ( diesel)
Concrete mixer 300 / 200 ltr ( electric)
Concrete mixer 600 / 400 ( diesel)
Concrete mixer 600 / 400 ltr ( electric
Concrete paver 100 sqm / hr
Convey mucker
Core drilling machine
Diesel generating set 30 KVA
Diesel generating set 50 KVA
Diesel Loco 45 hp
Dewatering pump 5 hp ( diesel )
Dewatering pump 5 hp ( electric )
Dewatering pump 10 hp ( diesel )
Dewatering pump 10 hp ( electric
Dewatering pump 20 hp ( diesel )
Dewatering pump 20 hp ( electric
Drifter
Drilling jumbo
Dumper 4.5 cum
Geophysical Electric resistivity meter
Grouting pump
Guniting / sand blast equipment
Ice plant & accessories 30 t / day
Jack hammer
Needle vibrator 40 mm ( petrol )
Needle vibrator 40 mm ( electric )
Needle vibrator 60 mm ( petrol )
Needle vibrator 60 mm ( electric )
Planing machine 4 m stroke
Plate shearing machine upto 12 mm
Pneumatic placer 0.5 cum
Pneumatic tamper
Pug cutting machine
Pusher leg
Road roller diesel 10 t

Unit

3
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour

Hire charge Fuel


Crew
in Rs
charge in Charge
Rs
in Rs.
4
758.40
108.30
241.30
131.90
275.60
170.80
138.80
1715.50
114.60
405.40
518.10
42.60
5.40
15.80
5.50
53.50
51.70
92.70
91.00
356.50
822.80
319.00
65.80
85.10
381.60
10.20
3.00
15.20
6.70
48.30
12.30
322.70
368.40
580.70
99.00
24.90
110.10
170.20
19.80
7.60
8.00
8.20
9.70
117.80
41.90
171.10
20.70
6.40
12.70
197.20

5
937.80
256.80
767.30
342.40
959.10
428.00
951.20
656.00
114.10
342.40
418.50
114.10
0.00
0.00
0.00
85.30
38.00
170.50
76.10
0.00
264.80
255.80
682.00
1023.00
575.40
85.30
38.00
170.50
76.10
341.00
152.20
0.00
46.00
429.70
0.00
38.00
0.00
1084.30
0.00
21.50
7.60
32.20
11.40
114.10
152.20
0.00
0.00
3.80
0.00
767.30

6
244.90
142.40
182.20
142.40
182.20
142.40
151.80
204.10
293.80
293.80
293.80
113.90
0.00
0.00
0.00
189.80
189.80
189.80
189.80
364.40
151.80
244.90
113.90
113.90
142.40
96.10
72.10
96.10
72.10
96.10
72.10
306.20
151.80
195.90
0.00
227.80
189.80
113.90
284.70
136.60
136.60
136.60
136.60
182.20
122.50
75.10
227.80
0.00
0.00
182.20

Total in Rs
7
1941.10
507.50
1190.80
616.70
1416.90
741.20
1241.80
2575.60
522.50
1041.60
1230.40
270.60
5.40
15.80
5.50
328.60
279.50
453.00
356.90
720.90
1239.40
819.70
861.70
1222.00
1099.40
191.60
113.10
281.80
154.90
485.40
236.60
628.90
566.20
1206.30
99.00
290.70
299.90
1368.40
304.50
165.70
152.20
177.00
157.70
414.10
316.60
246.20
248.50
10.20
12.70
1146.70

370

Hire Charges- for the year 2014-15

HIRE CHARGES OF MACHINERY


FOR THE YEAR : 2014-15
S.No

Description of machinery

Unit

Hire charge Fuel


Crew
in Rs
charge in Charge
Rs
in Rs.

1
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70

2
Shovel 0.50 cum 75 hp
Shovel 0.85 cum 110 hp
Stationery derric crane
Tipper 5 cum
Tipping tub 1.5 cum
Tower crane 5 tonne
Transformer 250 KVA
Truck 10 t
Truck mounted derric crane 5 t
Upright drilling machine/Grinder
Ventilation fan 20 hp
Vibratory pad foot roller 8 t
Wagon drill
Water tanker 8000 ltr
Welding set
Winch 35 hp ( electric )
Tractor with 2T roller

3
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour

4
1003.10
1706.60
86.10
446.70
64.20
867.10
5041.00
414.10
519.70
22.50
11.50
1342.20
188.50
402.50
16.00
129.40

5
511.50
937.80
0.00
322.20
0.00
197.80
0.00
322.20
322.20
38.00
152.20
1108.30
0.00
322.20
91.30
186.40

6
204.10
204.10
0.00
153.10
0.00
163.30
0.00
153.10
153.10
171.60
24.90
227.80
244.90
153.10
0.00
227.80

Total in Rs
7
1718.70
2848.50
86.10
922.00
64.20
1228.20
5041.00
889.40
995.00
232.10
188.60
2678.30
433.40
877.80
107.30
543.60
345.00

Hydraulic Truck Crane 30T


Hydraulic Truck Crane 16T

Hour
Hour

3096.80
2278.10

118.80
75.00

454.30
454.30

3669.90
2807.40

71

Heavy Duty Airless Spray Painting


Equipment

Hour

121.40

121.40

371

Potrebbero piacerti anche