Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Item Code
PART-1
Page No.
i-xiv
IRRIGATION
Abstract of Items - Irrigation
XV-LIII
IRR-DAW
IRR-DAW-1
1-10
IRR-DAW-2
IRR-DAW-3
IRR-DAW-4
IRR-DAW-5
IRR-DAW-6
10-23
23-29
30-32
32-38
39-46
IRR-TAW
IRR-TAW-1
IRR-TAW-2
IRR-TAW-3
IRR-TAW-4
IRR-TAW-5
IRR-TAW-6
50-57
58-59
59-64
65-66
66-69
71-72
IRR-CAW
IRR-CAW-1
IRR-CAW-2
IRR-CAW-3
IRR-CAW-4
IRR-CAW-5
IRR-CAW-6
IRR-CAW-7
IRR-CAW-8
74-85
86-90
91-94
95-98
99-105
106-107
107-140
141-150
IRR-CCDW
IRR-CCDW-1
IRR-CCDW-2
IRR-CCDW-3
IRR-CCDW-4
IRR-CCDW-5
IRR-CCDW-6
IRR-CCDW-7
152-155
155-175
176-176
177-182
183-185
185-190
190-192
IRR_GAW
IRR_GAW-1
IRR_GAW-2
IRR_GAW-3
IRR_GAW-4
194-194
195-198
199-210
211-213
213-215
IRR-PMW
IRR-PMW-1
IRR-PMW-2
IRR-PMW-3
216-223
223-228
228-240
COM-LDLFT
A. Manual Works
B. Lead/Lift/Loading & Unloading Charges
(to follow MORTH standardsfor the items not covered ,as
applicable to roads and bridge works)
Notes on Lead and Lift
241-241
242-242
Item Code
COM-LDLFT-1
COM-LDLFT-2
COM-LDLFT-3
COM-LDLFT-4
Page No.
242-242
242-243
LOADING AND UNLOADING CHARGES BY MANUAL
MEANS (Idle hire charges of trucks are not added)
LOADING AND UNLOADING CHARGES BY MANUAL
MEANS (including idle hire charges of trucks )
LOADING AND UNLOADING CHARGES BY MECHANICAL
MEANS (including idle hire charges of trucks )
243-243
243-243
COM-LDLFT-5
LIFT CHARGES FOR MATERIALS BY HEAD LOAD
COM-LDLFT-6
COM-DTL-LDLFT-1 (Lead) Conveyance Charges for materials by head load
( Lead) Conveyance charges for machinery per kilometer for
transporting materials by tippers and trucks, excluding
loading, unloading and hire charges of machinery.
243-243
243-243
244-245
COM-DTL-LDLFT-2
245-250
250-251
251-253
253-254
254-255
PART-2
ROADS&BRIDGES
RBR
257-262
RBR-LUCC
263-276
RBR-STCL
RBR-EECD
RBR-SBBS
Site Clearance
Earthwork,Erosion Control And Drainage
Granular Sub-Bases, Bases (Non-Bituminous) And
Shoulders
277-292
293-313
314-348
RBR-BASC
RBR-CCPV
RBR-CWSB
RBR-HLRD
RBR-PCVT
RBR-TSRA
RBR-FNDN
RBR-SBST
RBR-SPST
RBR-PTWK
RBR-MTRD
RBR-GSRE
RBR-HRTC
RBR-RPRH
349-411
412-421
422-423
424-433
434-438
439-481
482-547
548-570
571-606
607-619
620-631
632-636
637-645
646-655
PART-3
BUILDINGS
BLD-CSTN
656-658
BLD-CSTN-1
BLD-CSTN-2
BLD-CSTN-3
Mortars
Concrete, Grouting, Damp Proof Course
Brick Work & Honey Comb Work
659-660
660-669
670-674
BLD-CSTN-5
BLD-CSTN-6
BLD-CSTN-7
BLD-CSTN-8
BLD-CSTN-9
BLD-CSTN-10
BLD-CSTN-11
BLD-CSTN-12
BLD-CSTN-13
BLD-CSTN-14
BLD-CSTN-15
BLD-ELEC
750-753
BLD-ELEC-1
BLD-ELEC-2
BLD-ELEC-3
BLD-ELEC-4
BLD-ELEC-5
BLD-ELEC-6
BLD-ELEC-7
BLD-ELEC-8
BLD-ELEC-9
BLD-ELEC-10
BLD-ELEC-11
BLD-ELEC-12
BLD-ELEC-13
BLD-ELEC-14
BLD-ELEC-15
BLD-ELEC-16
BLD-ELEC-17
BLD-ELEC-18
Conduit Laying
Wiring
Run Of Mains
Switch Gear & MCB Distribution Board
Earthing
Service Mains & LTOH Lines
Street Light Luminaries
Internal Luminaire
AC and Refrigeration
Water Heaters
Water Pumps
Bus Bars
Swaged Poles
Control Panel & Metering Equipment
Cables / Cable Glands / Lugs
Temporary Illumination
Generators and Transformers
Repairs to Motors & Rewinding
754-761
761-764
765-767
767-779
779-783
783-790
790-795
796-800
800-807
807-808
809-824
825-825
825-832
832-835
835-844
845-845
845-855
856-860
PART-4
PHE
861-863
PHE-LCIS-1
864-866
PHE-LCIF-2
866-867
PHE-JCIS-3
868-873
PHE-JCIR-4
Jointing C.I., D.I. pipes and fittings with rubber gasket (push- 873-879
on-joint)
PHE-JCIF-5
879-884
PHE-LRCS-6
884-888
PHE-LJGI-7
889-892
PHE-GIDM-8
892-892
PHE-LACP-9
893-895
Item Code
BLD-CSTN-4
Page No.
675-679
679-679
680-685
686-697
697-710
710-713
713-719
719-736
737-738
738-741
742-742
742-749
Item Code
PHE-JACP-10
Page No.
895-899
PHE-LJUP-11
899-900
PHE-LJHE-12
900-905
PHE-LJSW-13
905-908
PHE-CISP-14
PHE-CISV-15
908-910
PHE-DAAV-16
910-910
PHE-SFHD-17
910-910
PHE-DSFH-18
910-910
PHE-URCI-19
911-913
PHE-URRC-20
913-913
PHE-URSW-21
914-915
PHE-URGI-22
915-915
PHE-CCIP-23
915-916
PHE-DTCI-24
916-916
PHE-SHST-25
PHE-BHLW-26
PHE-RCVS-27
Providing RCC spun vent shaft with cowl 140 mm and 200
918-918
mm internal and external dia respectively at top, 300 and 450
mm internal and external dia respectively at bottom and
9.10m overall length
PHE-WSNP-28
918-919
PHE-WSOW-29
919-920
908-908
917-917
917-918
Item Code
PHE-WSPR-30
Page No.
920-921
PHE-CCCP-31
922-922
PHE-CSHR-32
922-922
PHE-EXRW-33
922-923
PHE-LUSS-34
923-923
PHE-LUMS-35
924-924
PHE-LUGS-36
924-924
PHE-LUBS-37
924-925
PHE-CSRC-38
925-926
PHE-HSSG-39
926-926
PHE-LCVS-40
926-926
PREAMBLE
1.
Accordingly the data has been revised adopting the procedures and
guidelines given by CWC, Report on committee on cost control of river
3.
4.
The Detailed draft data was communicated to all the HODs and
interacted through many seminars and discussions and incorporated the
relevant features.The Board of chief engineers in their meetings have
recommended for acceptance to the data formulated and schedule of rates.
It was proposed to examine the recommendations on important parameters,
to refer to high level committee, for their specific recommendations for
adoption, as they are common to all departments.
ii
5.
B. GUIDELINES
1)
The Revised Standard Data is formulated under four Parts which are
PART -4: Drinking Water Supply and Public Health (ONLY FOR WORKS
DONE BY MANUAL MEANS)
of working. Suitable job and management efficiency factors are considered while
working out the average output of machinery under field conditions. In case of
combination of machinery and manpower the assessment of manpower shall
match the output of machinery.
Though cycle time of operations is the criteria for hourly / daily out-put
of machinery work-force ,the actual progress of work depends on several other
factors such as power interruptions, minor break-downs, time for meals and other
needs of work-force, stray rains etc. Therefore, it is the general practice to
consider 50 minutes as the actual working time per hour for working out the
hourly / daily out-put of machinery / work-force.CWC / BIS guide-lines stipulate
the actual working hours for the purpose of equipment planning and utilisation.
The daily out-put is computed duly considering the actual available working time
and feed back from the field.
For gate and hoist works it is the general practice to specify the
quantity of work in terms of number of sets of embedded parts / gates.
The requirement of machinery and work-force for cutting, bending,
fabrication, erection, painting etc., is assessed to commensurate with
the task involved.
The data for gates and E.M. Parts is arrived per Ton quantity.
The data for Hoists and Gantry Cranes is worked out on the basis of
capacity in tonnage
4) The lead and lift charges provided in PART-I (B) are generally applicable
and common to all Departments. Any item is not covered in this part, the
rates as provided in the data of the relevant works may be adopted in
preparation of estimates.
5) The basic material inputs needed for all works are listed and incorporated in
the data. The requirements are analyzed and the specifications adopted shall
iv
For sand, gravel , murum, stones , course aggregates etc, the rates
are to be fixed for delivery at Quarry, adding seigniorage ( royality)
charges, loading charges by machinery / manual means and idle hire
charges of machinery (as per table under chapter conveyance or lead
and lift charges), as applicable.
For earth/ soil for embankment works from borrow areas, which is not
included in the material list of schedule of rates, seigniorage charges
are to be added separately,if applicable.
For steel, Cement, AC sheets, GI sheets, Hume pipes, wood and stone
slabs, the rates are to be taken prevailing at major commercial centre
near project area. The lead charges, as applicable are to be added in
preparing estimates.
The specifications of the aggregates for sizes and gradation and its
adoption shall be as per IS 383.
in
the
form
of
percentage,
as
recommended
by
the
However, If more than one area allowances, such as those for (1)
Municipalities (2) Agency / Tribal areas (3) Industrial areas are
applicable for a particular situation, only the maximum out of the
allowable percentages is to be allowed.
for items of works and their output has been worked based on the
availability of machinery generally in the market and working in the the
field successfully, duly considering cycle time, idle time, operator
efficiency, type of work etc. T
For the other machinery not covered by the list, the R&B and other
users may adopt hire charges as recommended by the MORTH.
8) Lead Charges
The lead charges per unit quantity for conveyance of the materials are
worked out,and included in the schedule of rates in increment of 50 m
for head load and in increment of 1 km for mechanical mode.
vi
The rates for lead charges by head load upto 150 meters and by
machinery up to 5 km, shall be cumulative and inclusive of lead charges
for preceding lead. For lead beyond 5 km the lead charges shall be
worked out on per km basis.
The data and rates for lift charges is cumulative and are inclusive of
rates for preceding lifts also .
vii
II) steel : The wastage of steel @ 2.5% is allowed for gates and allied
structures. For RCC works the wastage is @2.5% for the
reinforcement rods above 36mm did and @ 5% for rods below 36mm
dia. Including overlaps, if they are not welded.
If welding is adopted for the reinforcement rods even for below 36mm
dia, 2.5% of wastage is only recommended.
12) Provision for rate for water:The Committee has recommended not to consider the water charges in
the Irrigation Project works. But, it may be considered in specific cases as
per the site conditions.
13)
In respect of RCC works the rate for cement concrete for 1 cum
is worked separately for all grades based on Indian Standards. The
rate for ton is calculated separately and to be added separately in the
estimates of RCC works as a separate item.
viii
High Level Committee has recommended to add 14% plus 4% towards VAT
or as applicable on item rate towards overheads labour including importation
and
amenities
&
contractor
profits,
which
includes
various
items
recommended in MORTH .
Expenditure on:
site supervision
ix
Sundries
Financing Expenditure
3 percent
on the
20) For each chapter separate additional details are incorporated for clarity.
2. The common data items like, lead, lift, conveyance and manual
excavation (without involving contracting agencies) is applicable
to all Departments (volume-1)
xi
a)
The Board Of Chief Engineers under the chairman ship of Engineer-inchief, (administration) I&CAD Department is the competent authority to
finalise and recommend the Schedule of Rates applicable for all engineering
Departments. The board has to assess and incorporate only the three basic
inputs required to generate unit work item rates as below.
Materials rates:
The basic input material rates common to all departmental works are
listed out and incorporated (in the chapter Basic inputs) The material
specifications adopted shall confirm to Standards published by the BIS.
The Prevailing market rates for all basic input materials shall be
obtained from the major commercial centers near the project areas. Average
of the rates, ignoring freak rates, shall be reckoned as the prevailing market
rate.
Unless otherwise specified, all material rates shall be inclusive of
all taxes, duties, levies, royalty, transportation and handling costs up to
project area.
For sand, gravel , murrum, stones , aggregates etc, the rates are
xii
for delivery at Quarry including seigniorage, loading charges and idle hire
charges. For steel, Cement, AC sheets, GI sheets, Hume pipes, wood and
stone slabs, the rates prevailing at major commercial centre near project area
has to be adopted.
Use rate of machinery:
The third parameter for incorporation in the Basic Inputs, is the use rate
of machinery. To arrive at the use rate of machinery, the inputs to be
incorporated are
The prevailing fuel charges of petrol and diesel are ascertained and
average rate adopted
For the other machinery not covered by the list, the R&B and other
users may adopt hire charges as recommended by the MORTH
b)
xiii
Description of Items
The description of items is given briefly and linked with the relevant Sections and Clauses of the
Ministry of Rural Development (MORD) Specifications for Rural Roads 2004 / MORTH
Specifications (Fourth Revision 2001) referred as Technical Specifications in the description
of items, wherever feasible, which may be referred for detailed description, provisions and
interpretation.
2.
Use of Machinery
2.1. Due to mechanization of construction work inputs for various items have been indicated
using mechanical means. However, manual means have also been provided for certain
cases, where areas may be inaccessible for machines or quantum of work may not be large
enough to justify use of machines. Medium in put of Machinery is also proposed, where
ever required.
2.2. For rolling, use of static roller / vibratory / pneumatic tyre roller has been considered
wherever required as per provisions of Specifications. However alternatively vibratory
roller also proposed.
3.
Working Conditions
3.1. The inputs for the Data have been analysed for average working conditions prevailing in
the state.
3.2. Average achievable outputs of machinery and labour have been considered taking into
account the job and management factors.
3.3. Since, the outputs of machinery and labour reduces substantially in hilly areas as the altitude
increases, reduced outputs have been considered for hilly areas as indicated in the Preamble
of Chapter 8.
4.
Overheads
This is assumed to include interalia the following elements:
i.
Site accommodation, setting up plant, access road, water supply, electricity and general site
arrangements
v. Labour camps with minimum amenities required as per labour laws and transportation to
work sites
vi. Light vehicles for site supervision including administrative and managerial requirements
vii. Setting up of Laboratories for quality control, field and laboratory testing for control of
quality of various items of work and documentation of test results as per requirement of the
MORTH / MORD Specifications.
257
viii. Minor T&P including vibrators for concrete work and survey instruments and setting
outworks, including verification of line, dimensions, taking trial pits and bore holes, where
required.
ix. Watch and ward
x. Arrangement for Traffic and Traffic Management during construction.
xi. Provision towards safeguarding environment
xii. Sundries
xiii. Financing expenditure of the Contractor
xiv. Sales/Turnover Tax / VAT at 4%
xv. Work Insurance / compensation.
5.
Contractor's Profit
It is considered to allow 18% towards overheads (Item No. 4) & contractor profits put together
which includes various items recommended in Item 4 above. This includes 4% VAT which
should be exhibited separately. In agreements it should be mentioned that it will be reimbursed
as per actuals.
6.
General
6.1.
The Section and Clause numbers refer to the MORD Specifications for Rural Roads 2004
/ MORTH as the case may be.
6.2. Additional assumptions made for analysing different items have been indicated in respective
Chapters in the form of Preamble and notes/footnotes wherever required.
6.3. For some of the items, certain size/specifications have been assumed. If size/specifications
other than the same are adopted, corresponding modifications may be made in the inputs of
analysis.
6.4. While presenting the Data some items, the quantities of sub-items involved in that analysis,
like, excavation for foundation, foundation concrete, masonry work, painting, lettering, etc.
have been given. For required inputs of such sub-items, reference may be made to relevant
Chapters dealing with the sub-items.
6.5. The sources of all materials and samples of materials are required to be approved by the
Engineer before start of any work.
6.6.
For reinforcing steel both HYSD and TMT bars conforming to IS: 1786 have been
considered.
6.7. For pipe culverts both NP3 and NP4 pipes have been considered.
6.8. The Data include inputs for testing of soil, materials and works.
6.9. The use of surface by construction vehicles shall be governed by Clause 117 of MORD / 119
of MORTH Specifications.
6.10. The contractor shall arrange to provide and maintain an adequate equipped field laboratory as
per Clause 119 of MORD / 121 of MORTH.
6.11. Quality control of works shall be governed by the relevant MORD / MORTH Specifications.
6.12. Sundries to cater for unforeseen contingency and miscellaneous items have been added in the
overhead charges.
6.13. Arrangement for traffic during construction shall be as per Clause 112 of MORTH / 111 of
MORD specifications for Road & Bridge Works.
258
There is mixed traffic on urban roads like slow moving hand and animal driven carts,
rickshaws, cycles, two/ three wheeler apart from the usual vehicular traffic resulting
into traffic jams. This causes loss of working time which may be in the range of 10 15 per cent
b)
c)
Cost of living in urban areas is comparatively more resulting into higher wages.
d)
At times, work is executed during night time due to heavy traffic during day time.
This involves extra expenditure by way of making arrangement for lighting and
special transport for working parties due to odd hour
In the light of above, the authorities engaged in preparing the Data cost estimates may
exercise their judgment and cater for the additional cost to the extent of 2 to 3 per
cent, keeping in view the severity of factors mentioned above. Supporting details for
the extra cost based on the actual conditions in specific cases will have to give in
justification.
7.
Basic Inputs
7.1. The Standard Data Book is based on the requirements of basic inputs of materials, labour and
machineries for various items.
7.2. The rates for labour, material and usage charges of machinery for the area where the project is
located are to be ascertained from local authorities/enquiries to prepare Schedule of Rates
for the area.
7.3. The basic rates of materials, such as, stone boulders, stone for masonry, stone ballast,
stone dust, moorum, gravel, lime, manure, sludge, quarry sweep, kankar, bricks, brick
ballast, crushed slag, etc. at quarry / crusher sites shall be fixed by the Board of Chief
Engineers yearly (effective from 1st June to 31st May). However, the basic rate of
materials hand broken / machine broken, crushed aggregates shall be based on
Analysis in Chapter 1 of Roads and Bridges.
7.4.
The cost of materials should include the cost at source and the cost of their carriage (as per
Schedule of rates arrived in Chapter 1 for conveyance, loading and unloading charges) upto
the work site.
259
8.
9.
Labour
9.1 The labour wages should be as per rates fixed by the Board of Chief Engineers keeping the
minimum wages fixed as per Minimum Wages Act.
9.2 Skilled labour include mason, carpenter, blacksmith, mechanics and other trades.
10.
Materials
10.1. Quantities of materials considered in the rate analysis are approximate for the purpose of
estimation and include normal wastages. Actual consumption would depend on mix design.
10.2. The rates of material should include basic cost at locations of stone crushers/factory/rail head
and cost of its carriage to the site of work/plant including loading, unloading and stacking.
10.3. The supply of materials will be taken either at the location of mixing plant or at the
work site as per requirement of use.
10.4. Contractor will make his own arrangements for borrowing earth. However, compensation
for earth taken from private land has to be included in the rate analysis for construction of
embankment / sub-grade with borrowed earth.
10.5. Credit for Dismantled Material: The dismantled materials should be examined and a realistic
assessment made for credit for such materials, which can be utilized for works or auctioned.
10.6. The basic rates should include all octroi charges, toll tax, sale tax, VAT, municipal taxes and
other local taxes, etc.
10.7. The specifications of materials shall be governed by section 1000 of MORTH specifications
260
In case bridge construction works are to be done on wide and deep water channels in major
rivers or in sea creeks etc., provision of floating barrages etc. for taking the construction materials
and equipments inside water shall also be made separately.
(xi) Analysis for sinking of wells cover diameters from 6 m to 12 and Twin D Type of size 12 m x 6
m. For other shapes like rectangular or any other size, the inputs of sinking may be worked out on
pro-rata basis.
(xii) The lift for casting of concrete in well steining may be 2 to 2.5 m restricting the free fall of concrete to
261
16.
Privileged Document
The Standard Data Book is for Department use only. It should not be produced in any court of law as
reference/ authority and to that extent it is a privileged document.
262
RBR-LUCC
263
RBR-STCL
277
RBR-EECD
RBR-EECD
20. In the rate analyses of some items, the quantities of sub-items involved in that analyses, like, excavation
for foundation, foundation concrete, painting, lettering, etc. have been given. The rates for such items shall
be taken from relevant chapters where the same have already been analysed.
21. The item of preparation and surface treatment of formation (Clause 310) is required to be added in the
cost estimate only if there is substantial time lag between completion of sub-grade and laying of sub-base.
As this item is incidental to works, it is not required to be included in BOQ.
22. The items filling behind abutments and wing wall and provision of filter media has been included
in Chapter-15.
CLASSIFICATION OF EXCAVATED MATERIAL
CLASSIFICATION : All materials involved in excavation shall be classified by the Engineer as per
Specification No 302.2.1 of MORD /
MORTH , as under :
(a) Soil
(b) Ordinary Rock (not requiring blasting)
(c) Hard Rock
i.
requiring blasting
294
(i)
rock types such as laterites, shales and conglomerates, varieties of limestone and sandstone,
etc., which may be quarry or split with crow bars, also including any rock which in dry state
may be hard, requiring blasting but which, when wet, becomes soft and manageable by
means other than blasting.
(ii)
macadam surfaces such as water bound and bitumen / tar bound; soiling of roads, paths, etc.,
and hard core; compact moorum or stabilized soil requiring grafting tool or pick or both and
shovel, closely applied; gravel and cobble stone having maximum dimension in any one
direction between 75 mm and 300 mm;
(iii)
lime concrete, stone masonry in lime mortar and brick in lime / cement mortar below
ground level, reinforced cement concrete which may be broken up with crow bars or picks
and stone masonry in cement mortar below ground level; and
(iv)
boulders which do not require blasting having maximum dimension in any direction of more
than 300 mm, found lying loose on the surface or embedded in river bed, soil, talus, slope
wash and terrace material of dissimilar origin.
RBR-EECD
any rock or cement concrete for the excavation of which the use of mechanical plant and /
or blasting is required;
reinforced cement concrete (reinforcement cut through but not separated from the
concrete) below ground level; and
295
RBR-SBBS
b.
3. Construction of shoulders: - Earthen, Hard and Paved shoulders have been considered, the rates
applicable are for subgrade, sub-base and different layers of pavement respectively.
4. In the case of improvement of subgrade with lime stabilization, soil is assumed to be available at the
site and has not been provided for. Only lime has been catered. In the case of lime stabilization of subbase, soil has been provided to form the sub-base.
5. While providing for the rate of materials, SS Rates shall be applied in RMR keeping in view the
location of crushing plants / quarries and lead involved.
6. The quantities considered in the output are the compacted quantities. The quantities of aggregates
provided in the rate analysis under the head material are the uncompacted quantities.
7. In the case of medians, separators and footpaths, plate compactor has been catered for compaction
due to restricted space
8. It has been assumed in the case of crushed cement concrete sub-base/base that during the process of
dismantling, 25 per cent of aggregates will get segregated and only the remaining will have to be broken
/ crushed from dismantled concrete slab portions. Transportation of materials has been catered from place of
dismantling to work site. In case, site is the same, transportation cost can be deleted.
9. Separate rate for penetration coat over top layer of crushed cement concrete base has been provided, as
this item is optional
314
RBR-BASC
RBR-BASC
350
RBR-CCPV
412
RBR-CWSB
422
RBR-HLRD
Altitude in m
% of the value in
Manpower to be added to
rates
2100 to 2400
7%
3%
2401 to 2700
15%
6%
2701 to 3000
25%
9%
3001 to 3300
32%
12%
3301 to 3600
48%
15%
3601 to 3900
66%
18%
3901 to 4200
86%
21%
4201 to 4500
108%
24%
4501 to 4800
132%
27%
4801 to 5100
186%
30%
The above provisions are based on the report of Defence Institute of Physiology and Allied Sciences /
Delhi Cantt. regarding quantitative reduction in the physical work capacity of individuals working in high
altitude areas and the recommendation of the Committee on Cost of Construction set-up by Border
Roads Development Board for reduction in output of machines while working in high altitudes. The
figures are adopted from 'Standard Schedule of Rates' of BRO as applicable to high altitude areas,
3. The above addition is also to be applied on the analysis of rates for items provided in this Chapter.
4. In case of hill roads, the cut earth can be pushed down the valley in case there is no objection. In that
case, cost of disposal is not required to be provided.
5. In case of high altitudes areas above 2100 m, the percentage addition to the cost of manpower and
usage rates of machines are required to be made as per the Table given on next page.
424
RBR-PCVT
434
RBR-TSRA
4. Kerbstone laying and road marking has been provided for laying by mechanical means
5. Backfilling of foundation of boundary pillars has been proposed with stone spalls, tightly packed
and compacted.
6. The item pertaining to road traffic signals has not been analysed as this is a specialized work and
rates can be obtained from firms having specialisation for design and installation of this work.
7. Two supports have been provided for direction and place identification signs where size is more
than 0.9 square metres. Only one support is provided for size upto 0.9 square metres.
8. The traffic signs proposed are of retro- reflectorised types made of encapsulated lens type
reflective sheeting fixed over aluminum sheeting and semi-reflective type on M.S. sheet
9. The size and location of traffic signs shall be as per IRC:67.
10. Separate rate analysis has been made for tubular steel railing with RCC posts and MS steel posts.
11. For metal beam crash barrier, a W shaped beam of size 311 x 83 mm flange width made with
structural steel corrugated plate 3 mm thick and having a length of 4.5 m has been provided, over a
channel post of 150 x 75 x 5 mm with a spacer of channel section 150 x 75 x 5 mm, 330 mm long.
12. Printing of letters and signs on item Nos. 18 to 21 is required to be measured and paid separately. A
separate rate analysis for lettering has been prepared and included in this chapter for this purpose.
13. The analysis for rigid, semi-rigid and flexible crash barriers have been included.
14. Provision has been made for a crane for installation of overhead signs.
15. Separate rate analysis have been made for Tubular steel railing with RCC posts and MS steel posts.
16. The organization and financial aspects are required to be finalized in consultation with administrative
and traffic authorities
17. The rate for the message display board for gantry mounted variable message sign is required to be
ascertained from the market, this being a commercially produced item by specialised firms.
18. The rate analysis for traffic impact attenuators at abutments and piers have been included.
19. In the case of road signs and direction boards, the depth of foundation and quantity of cement
concrete provided in the rate analysis are indicative. These may be suitably increased in areas of
higher wind velocities, like, coastal areas.
439
RBR-TSRA
20. Ducts for Utility Services Along and Across the Expressway/Highway
The running metre cost of duct along the road including inspection chambers (where applicable) or
across the road will depend upon the approved design. The various items involved are earthen work,
plain cement concrete, brick stone masonry, reinforcement cement concrete, form work, steel
reinforcement, laying of pipe line (where duct is of pipe) and cast iron/RCC cover for the inspection
chamber. The rate for these items are available under respective clauses which can be applied and
running metre cost of duct worked out as per the approved design and drawing for particular situations. In
case cast iron cover for the inspection chamber, the rate can be ascertained from the market for the size
provided in the design and approved drawings.
21. Noise Barriers
Noise barrier can be provided in the form of a brick wall of a suitable height as per the site requirement and
approved design. The items involved for the construction of this barrier like earthwork, brick masonry, plain
cement concrete, etc. are available in the Data Book, which can be applied to arrive at the cost of noise
barrier based on the design adopted.
Alternatively, wherever space permits, cluster of trees, shrubs and plants can be grown by the road side 6
m away from the edge of the roadway. This will intercept the annoying sound waves and fumes from road
vehicles
440
RBR-FNDN
The amount required for testing of piles shall be depending upon market situation.
17.
The levelling course below the pile cap is proposed with M 15 grade concrete.
18. Steel reinforcement for cement concrete works are required to be provided separately. The rate for
the same has been analysed.
482
RBR-FNDN
19. Appendix-4 of IRC: 78-2000 may be referred regarding precautions to be taken during sinking of
wells.
20. In case of blasting during sinking of wells the inner face of the curb is required to be protected with
the steel plates of thickness not less than 10 mm upto top level of well curb. For height above top of
curb, the thickness of steel plate may be reduced to 6 mm. This extra height of steel lining should be
limited to 3 m.
21. The concrete mix used in bottom plug shall have a minimum cement content of 330 kg/cum and a
slump of about 150 mm to permit easy flow of concrete through tremie to fill-up all cavities.
22. Necessary safety precautions shall be taken for excavation on open foundations for which guidance
may be taken from IS:3764.
23. A levelling course of 100 mm thickness in M 10 (1:3:6) shall be provided before laying open
foundations.
24. In the case of open foundation, dewatering shall not be permitted from the time of placing of concrete
upto 24 hours after placement.
25. In case of open foundations in rock, the trenches around the footing shall be filled-up with
concrete of M 15 grade upto a level of 0.6 m for hard rock and 1.5 m for soft rock above the foundation
level. The portion above this may be filled by boulders grouted with cement.
26. When there are two or more compartments in a well, the lower edge of the cutting edge of the
middle stems of such wells shall be kept about 300 mm above that of outer stems to prevent rocking.
27. The well curb shall be in RCC of mix not leaner than M 25 grade with minimum steel
reinforcement of 72 kg/cum excluding bond rods.
28.
29. In case of cement concrete piles, the minimum grade of concrete shall be M 35 with minimum
cement content of 420 kg/cum.
30. The top of the pile shall project 50 mm into the pile cap and reinforcement of pile shall be fully
anchored in pile cap.
31. The minimum thickness of pile cap should be atleast 0.6 m or 1.5 times the diameter of the
pile whichever is more.
32.
33. Concrete in driven cast-in-situ piles shall be cast upto a minimum height of 600 mm above the
designed top level of pile, which shall be stripped off to obtain sound concrete either before final set or after
3 days.
34. The top of the bottom plug shall be atleast 300 mm above top of curb
35. In remote areas, for isolated slab culvert/box culvert upto 2 m span, concrete can be hand mixed
in accordance with Clause 806 of MORD Specifications. Therefore, in the analysis, for items of
concrete, the alternative of hand mixing has also been considered.
36. Steel reinforcement for cement concrete work is required to be provided separately. The rate for
the same has been analysed using HYSD, TMT and MS bars.
37. Necessary safety precautions shall be taken for excavation for open foundation for which
guidance may be taken from IS:3764. Cost of shoring and shuttering has been provided on
percentage basis, which may be adjusted according to site condition.
38. For brick masonry work, clay fly ash bricks of approved type can be used in accordance with
Section 600 of MORD Specifications and rate may be adopted accordingly.
39. Rates of all materials used in the analysis are at site and should include cartage from crusher.
483
RBR-SBST
548
RBR-SPST
b)
c)
The item may be selected as per approved design. In case the thickness of wearing coat is different
from that analysed, the rate for the desired thickness may be worked out on pro-rata basis.
2. The rate analysis has been done for the following types of railings & parapet, which can be
adopted as per approved design:
(i)
R.C.C. railing
(ii)
M.S. railing
(iii)
(iv)
(v)
(vi)
P.C.C. parapet
3. As per the MORD Specifications, the type of superstructure envisaged for minor bridges and
culverts for rural roads are R.C.C. slabs and box culverts not exceeding 15 m span, rates for which
have been analysed. Stone/Brick masonry arches can be adopted where hard strata is available at
shallow depth. R.C.C. arches can also be adopted as per IRC:SP:20. Hence rates for these types of
arches for span length upto 15 m have been analysed.
4. For composite type of superstructure, comprising of steel beams/built-up sections & R.C.C. deck
slab, analysis has been done for steel section separately.
5. For slab culverts and minor bridges of spans not more than 10 m, buried joint/filler joint may be
adequate. For relatively longer spans and for highly seismic intensity areas, electrometric slab
seal/compression seal joint may be provided as per the MORD Specifications. Rates have to be
analysed accordingly.
6. In remote areas, for slab culverts and box culverts upto 2 m span, concrete used in superstructure
can be hand mixed with 10 per cent extra cement at contractor's cost in accordance with Clause 806
of MORD Specifications. Hand mixing shall not be otherwise permitted.
7. Slab seal/compression seal expansion joints are specialized items commercially produced by a
number of firms. The rates for such items must be ascertained from firms pre-qualified by MORTH.
8. The length of drainage spout has been provided in such a way that it is connected to the drainage
system on the ground in case of flyovers and there is no splashing of water on the structure in case of
bridges.
9. The rate for anti-corrosive treatment is required to be ascertained from firms specialised in this work. In
this connection Circular No. RW/NH-34041/44/91-S&R dated 21.3.2000 of Ministry of Road Transport and
Highways may be referred for further details.
571
RBR-SPST
10. Expansion joints involving movements exceeding 40 mm are specialised readymade items commercially
produced by reputed firms with imported technology and parts. The rates for such joints are required to be
ascertained from the firms pre-qualified by the Ministry.
11. The rate analysis for pre-cast and pre-tensioned girders has also been included.
12. The rate analysis for prestressed cement concrete of M 60 grade has also been included which can be
adopted for bridges with innovative design/construction.
13. MORT&H letter No. RW/NH-34059/1/96 S&R dated 30.11.2000 and subsequent corrigendum dated
25.1.2001 may be referred for detailed specifications and provisions for various types of expansion joints.
14. Supply of new type of expansion joint may be obtained on the basis of competitive bidding from
amongst the suppliers pre-qualified by the Ministry of Road Transport and Highways. Further, a
warranty of 10 years of trouble free performance may be insisted from the suppliers.
15. For bridges having wide deck/span length of more than 120 m or/and involving complex movements /
rotations in different directions/planes, provision of special type of modular expansion joints such as swivel
joists joints are required for which firms specialised in this field may be consulted. Such cases will require
prior approval of Ministry
16. Note 7 to 18 of Chapter 11.
572
RBR-PTWK
607
RBR-MTRD
620
RBR-GSRE
632
RBR-HRTC
1.
The items of turfing with sods and seeding and mulching have been included in the chapter of
earthwork.
2.
The analysis of rates for grassing of lawns and hedges has been included, as the same may be
needed for resting places on highways.
3.
Selection from above may be made as per actual situation and design.
4.
Analysis of rates for wrought iron and mild steel welded work has been included to cater for
any miscellaneous work in connection with horticulture, fencing and traffic sign.
5.
Though the estimate for compensatory afforestation is made by the forest department, the rate for
this item has been analysed and included for the purpose of estimation.
6.
In the rate analysis of some items, the quantities of sub-items involved in that analysis, like,
excavation for foundation, foundation concrete, painting, lettering, etc. have been given. The rates for such
items may be taken from relevant chapters where the same have already been analysed.
7.
As grass and plantation need more care, one mate has been provided for every 10 mazdoors in
case of horticulture.
637
RBR-RPRH
646
PART-II
Rate Analysis as per Observations made by Engineering Staff Collage of India for Crushing of Stone Aggregate using
Primary, Secondary - Crushers & Conveyors
Data: Sizes of coarse aggregate considered for data rate analysis.
80 mm size
40 mm size
20 mm size
10 to 4.75 mm size range
Dust (powder)
1 No. primary jaw crusher of 120 tons / hour rated capacity each and 2 Nos. secondary jaw crushers are used
Single shift working for aggregate crushing
Daily output of crushing system with 70% efficiency and 50 minutes per hour working
Daily out turn = 1 x 120 x 0.70 x 8.00 x 50/60 = 560 tons or 350 cum
2 Nos secondary jaw crusher are used for recrushing over size aggregate
Capital cost of Crusher system : Rs. 72,82,167.00
Requirement of electric power : energy consumption per hour in kw.hr. = 190
Capital cost of Conveyer System (Excluding cost of belts) : Rs. 23,67,416.00
RATE ANALYSIS
Unit 343 cum
A. MATERIALS:
Sl.
Particulars
No
1. Cost of Rubble
Unit
Quantity
Rate in
Rs.
cum
350
175
hour
77.35
hour
42.97
788.72
Amount in
Rs.
61250
C) LABOUR:
Sl.No.
Particulars
Unit
Quantity
Rate in Rs.
165
Amount in
Rs.
1320
1.
hour
618.8
2.
hour
83
664
61.88
3.
Mazdoor
day
5 Nos.
101
505
343.76
34.38
hour
98.59
hour
24.9
199.2
hour
12.46
99.68
a.
Cost of materials
63,722.00
hour
8.3
66.4
b.
24,960.00
99.68
c.
cost of labour
2,489.00
159.44
d.
4,559.00
63,721.94
e.
Say
63,722.00
hour
12.46
hour
19.93
ABSTRACT
Rs. 95,730.00
B. MACHINERY:
Sl.
No.
2,489.00
Particulars
Unit
Quantity
Rate in
Rs.
Amount in
Rs.
hour
1500
12000
hour
1004
hour
353
hour
263
Crushing pattern %
Production in
cum / shift
% Cost
distribution
Amount
80 mm size
24
82.3
15
14360
Rs.174.00
8032
40 mm size
32
109.8
34
32548
Rs.296.00
2824
20 mm Size
22
75.5
33
31591
Rs.418.00
2104
10 - 4.75
mm
Dust
12
41.1
15
14360
Rs.349.00
10
34.3
2871
Rs. 84.00
100%
343.0 cum
100%
95730
Rs.279.00
24960
Size
Cost per
cum
RBR-LUCC
S. No
Description
Unit
Quantity
day
day
0.520
hour
0.500
Rate Amount
Rs.
Rs.
5
Remarks
7
RBR-LUCC-1
i
Unit = cum
Taking output = 5.5 cum
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Truck 10t
c&d) Overheads & Contractors Profit
Cost for 5.5 cum = a+b+c+d
Rate per cum = (a+b+c+d)/5.5
ii
Unit = cum
Taking output = 5.5 cum
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Truck 10t
c&d) Overheads & Contractors Profit
Cost for 5.5 cum = a+b+c+d
Rate per cum = (a+b+c+d)/5.5
iii
RBR-LUCC-2
day
0.260
hour
0.250
Unit = cum
Taking output = 5.5 cum
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Truck 10t
c&d) Overheads & Contractors Profit
Cost for 5.5 cum = a+b+c+d
Rate per cum = (a+b+c+d)/5.5
iv
day
day
day
0.260
hour
0.250
Unit = cum
Taking output = 5.5 cum
a) Labour
day
Mate
day
Mazdoor (Unskilled)
b) Machinery
hour
Truck 10t
c&d) Overheads & Contractors Profit
Cost for 5.5 cum = a+b+c+d
Rate per cum = (a+b+c+d)/5.5
Loading and Unloading Lime, Aggregate, Stone
Boulder, Brick Aggregate, Kankar, Building Rubbish,
Crushed Slag, Stone for Masonry Work by Mechanical
Means including hire charges of Tipper 10t for waiting
period and Front end loader 1cum capacity for loading
period.
Loading of Lime, Aggregate, Stone Boulder, Brick
Aggregate, Kankar, Building Rubbish, Crushed Slag,
Stone for Masonry Work by mechanical means
including a lead upto 30 m
Placing tipper at loading point, loading with front end loader
excluding time for haulage and return trip.
Unit = cum
Taking output = 5.5 cum
Time required for
Min
i) Positioning of tipper at loading point
ii) Loading by front end loader 1 cum bucket capacity @ 45 Min
cum per hour
Min
iii) Maneuvering, reversing, dumping and turning for return
0.130
0.166
1.000
7.330
-
264
RBR-LUCC
Index-code
S. No
Description
Unit
Quantity
3
Min
4
2.000
Min
10.330
ii
iii
hour
0.172
hour
0.122
Min
1.000
Min
3.300
Min
2.000
Min
Total
a) Machinery
hour
Tipper 10 t capacity
Front end-loader 1 cum bucket capacity @ 100 cum per hour
hour
c&d) Overheads & Contractors Profit
Cost for 5.5 cum = a+b+c
Rate per cum = (a+b+c)/5.5
6.300
Rate Amount
Rs.
Rs.
5
Remarks
7
0.105
0.055
Unit = cum
Taking output = 5.5 cum
Placing tipper at unloading point excluding time for haulage
and return trip
Time required for
i) Positioning of tipper at unloading point
ii) Manoeuvering, reversing, dumping and turning for return
Min
1.000
Min
2.000
265
RBR-LUCC
Index-code
S. No
Description
Unit
Quantity
3
Min
4
2.000
Min
5.000
hour
0.080
RBR-LUCC-3
i
ii
Remarks
7
Rate Amount
Rs.
Rs.
Min
Min
1.000
13.000
iii)
Maneuvering, reversing, dumping and turning for Min
return
Min
iv) Waiting time, unforeseen contingencies etc
Min
Total
a) Machinery
Tipper 5.5 tonnes capacity
hour
Front end-loader 1 cum bucket capacity @ 25 cum/hour
hour
c&d) Overheads & Contractors Profit
Cost for 5.5 cum = a+b+c
Rate per cum = (a+b+c)/ 5.5
Note : Unloading will be by tipping.
2.000
4.000
20.000
0.330
0.330
0.110
0.750
0.750
0.260
0.330
0.260
266
RBR-LUCC
Index-code
S. No
Description
Unit
Quantity
hour
0.330
b) Machinery
Truck 10t
c&d) Overheads & Contractors Profit
Cost for 2000 Nos. = a+b+c+d
Rate for 1000 bricks = (a+b+c+d)/2
4
Rate Amount
Rs.
Rs.
5
Remarks
7
RBR-LUCC-4
i
Unit = t
Taking output = 10 t
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Truck 10t
c&d) Overheads & Contractors Profit
Cost for 10 t = a+b+c+d
Rate per tonnes = (a+b+c+d)/10
ii
RBR-LUCC-5
i
day
1.560
hour
1.000
Unit = t
Taking output = 10 t
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Truck 10t
c&d) Overheads & Contractors Profit
Cost for 10 t = a+b+c+d
Rate per tonnes = (a+b+c+d)/10
iii
day
day
day
1.560
hour
1.000
Unit = t
Taking output = 10 t
a) Labour
day
Mate
day
Mazdoor (Unskilled)
b) Machinery
hour
Truck 10t
c&d) Overheads & Contractors Profit
Cost for 10 t = a+b+c+d
Rate per tonnes = (a+b+c+d)/10
Loading, Unloading and Sticking of Structural Steel and
Steel Bars by manual means including hire charges of
Truck 10t for waiting period.
Loading of Structural Steel, Steel Bars by manual
means including a lead upto 30 m
Unit = t
Taking output = 10 t
a) Labour
day
Mate
day
Mazdoor (Unskilled)
b) Machinery
hour
Truck 10t
c&d) Overheads & Contractors Profit
Cost for 10 t = a+b+c+d
Rate per tonnes = (a+b+c+d)/10
2.080
2.000
1.870
1.000
267
RBR-LUCC
Index-code
S. No
Description
Unit
Quantity
ii
iii
RBR-LUCC-6
i
ii
RBR-LUCC-7
Rate Amount
Rs.
Rs.
5
Remarks
7
1.870
1.000
Unit = t
Taking output = 10 t
a) Labour
day
Mate
day
Mazdoor (Unskilled)
b) Machinery
hour
Truck 10t
c&d) Overheads & Contractors Profit
Cost for 10 t = a+b+c+d
Rate per tonnes = (a+b+c+d)/10
Loading and Unloading of Bitumen Drums by Manual
Means including hirecharges of truck 10t for waiting
period
Loading of Bitumen Drums by manual means including
a lead upto 30 m
Unit = t
Taking output = 10 t
a) Labour
day
Mate
day
Mazdoor (Unskilled)
b) Machinery
hour
Truck 10t
c&d) Overheads & Contractors Profit
Cost for 10 t = a+b+c+d
Rate per tonnes = (a+b+c+d)/10
Unloading of Bitumen Drums by Manual Means
including a lead upto 30 m
Unit = t
Taking output = 10 t
a) Labour
day
Mate
day
Mazdoor (Unskilled)
b) Machinery
hour
Truck 10t
c&d) Overheads & Contractors Profit
Cost for 10 t = a+b+c+d
Rate per tonnes = (a+b+c+d)/10
Note : The weight is inclusive of the self weight of drum
Loading and Unloading of Timber by Manual Means
including hirecharges of truck 10t for waiting period
2.080
2.000
1.660
1.250
1.250
1.250
Unit = t
Taking output = 5 t
a) Labour
Mate
Mazdoor (Unskilled)
day
day
1.040
268
RBR-LUCC
Index-code
S. No
Description
Unit
Quantity
hour
1.000
b) Machinery
Truck 10t
c&d) Overheads & Contractors Profit
Cost for 5 t = a+b+c+d
Rate per t = (a+b+c+d)/5
ii
Rate Amount
Rs.
Rs.
5
Remarks
7
Unit = t
Taking output = 5 t
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Truck 10t
c&d) Overheads & Contractors Profit
Cost for 5 t = a+b+c+d
Rate per t = (a+b+c+d)/5
day
day
1.040
hour
1.000
Note : Density of wood has been assumed as 900 kg per cum. If the
density is less the output may be reduced proportionately.
RBR-LUCC-8
RBR-LUCC-9
Unit = cum
Taking output = 5.5 cum
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Truck 10t
c&d) Overheads & Contractors Profit
Cost for 5.5 cum = a+b+c+d
Rate per cum = (a+b+c+d)/5.5
ii Unloading with care C.C. Blocks, km Stone, 200 m
Stone, Boundary Pillar, Kerb, Channel, Bond Stone, etc.
by manual means including a lead upto 30 m
Unit = cum
Taking output = 5.5 cum
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Truck 10t
c&d) Overheads & Contractors Profit
Cost for 5.5 cum = a+b+c+d
Rate per cum = (a+b+c+d)/5.5
Loading and Unloading of RCC Hume Pipes including
hirecharges of truck 10 t for waiting period and Crane
3t capacity including all labour charges.
i Loading of RCC Hume pipes by mechanical means
including a lead upto 30 m
A 1000 / 1200 mm dia RCC Hume pipe
Unit = per pipe
Taking output = 9 pipes
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Truck 10t
Crane (3 T)
c&d) Overheads & Contractors Profit
Cost for 9 pipes = a+b+c+d
Rate per pipe = (a+b+c+d)/9
day
day
2.080
hour
1.500
day
day
2.080
hour
1.500
day
day
0.520
hour
0.330
hour
0.330
269
RBR-LUCC
Index-code
S. No
Description
Unit
Quantity
day
day
Mazdoor (Unskilled)
b) Machinery
hour
Truck 10t
hour
Crane
c&d) Overheads & Contractors Profit
Cost for 15 pipes = a+b+c+d
Rate per pipe = (a+b+c+d)/15
C 600/450 mm dia RCC Hume pipe
Unit = per pipe
Taking output = 21 pipes
a) Labour
day
Mate
day
Mazdoor (Unskilled)
b) Machinery
hour
Truck 10t
hour
Crane
c&d) Overheads & Contractors Profit
Cost for 21 pipes = a+b+c+d
Rate per pipe = (a+b+c+d)/21
ii Unloading of RCC Hume pipe by manual means
including a lead upto 30 m
A 1000/1200 mm dia RCC Hume pipes
Unit = per pipe
Taking output = 5 pipes
a) Labour
day
Mate
day
Mazdoor (Unskilled)
b) Machinery
hour
Truck 10t
c) Material
Wooden sleepers 250mm x 250mm x125mm hire charges 3 nos
sleeper
Crow bars 2 nos not less than 40 mm dia (hire-charges)
Rate Amount
Rs.
Rs.
5
Remarks
7
0.520
0.330
0.330
0.520
0.330
0.330
1.040
2.000
hour
2.000
hour
2.000
day
day
1.040
hour
2.000
hour
2.000
hour
2.000
270
RBR-LUCC
Index-code
S. No
Description
Unit
Quantity
day
day
1.040
hour
2.000
hour
2.000
hour
2.000
Rate Amount
Rs.
Rs.
5
Remarks
7
day
day
0.520
hour
hour
0.200
0.200
day
day
0.520
hour
0.200
hour
0.200
day
day
0.520
hour
0.200
hour
0.200
271
RBR-LUCC
Index-code
RBR-LUCC-10
S. No
Description
Unit
Quantity
hour
0.400
hour
0.290
10
Rate Amount
Rs.
Rs.
5
Remarks
7
Conveyance of Materials
Haulage of materials by tipper 10t capacity excluding cost of
Loading, Unloading & Stacking, but including hirecharges of
Machinery.
Surfaced Road
Speed with load: 25 km per hour
Speed while returning empty: 35 km per hour
a) Machinery
Tipper 10 t capacity
Haulage with load
Empty return trip
c&d) Overheads & Contractors Profit
Cost for 100 t.km = a+b+c
Rate per t.km = (a+b+c)/100
hour
0.500
hour
0.330
1.000
0.670
RBR-LUCC-11
11
Unit = cum
Taking output = 1 cum
a) Labour
Mate
Mazdoor (Unskilled)
b) Material
Supply of quarried stone 150-200 mm size
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
day
day
1.248
cum
1.100
272
RBR-LUCC
Index-code
S. No
1
Description
2
i A Hand Broken Stone aggregate 75 mm nominal size
Supply of quarried stone and hand breaking into coarse aggregate
75 mm nominal size (106-63 mm) as per Table 500-17MORD &
stacking as directed.
Unit = cum
Taking output = 1 cum
a) Labour
Mate
Mazdoor (Unskilled)
b) Material
Supply of quarried stone 150-200 mm size
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
ii
Unit
Quantity
day
day
1.248
cum
1.100
Rate Amount
Rs.
Rs.
5
Remarks
7
Unit = cum
Taking output = 1 cum
a) Labour
Mate
Mazdoor (Unskilled)
b) Material
Supply of quarried stone 150-200 mm size
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
day
day
1.560
cum
1.100
Unit = cum
Taking output = 1 cum
a) Labour
Mate
Mazdoor (Unskilled)
b) Material
Supply of quarried stone 150-200 mm size
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
iii
day
day
1.560
cum
1.100
Unit = cum
Taking output = 1 cum
a) Labour
Mate
Mazdoor (Unskilled)
b) Material
Supply of quarried stone 150-200 mm size
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
day
day
1.872
cum
1.100
a) Labour
Mate
Mazdoor (Unskilled)
b) Material
Supply of quarried stone 150-200 mm size
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
day
day
1.872
cum
1.100
273
RBR-LUCC
Index-code
S. No
Description
Unit
Quantity
2
Crushing of Stone Aggregates 100 per cent passing through 53
mm sieve as per Table 500.6 of Technical Specifications of
MORD / 500-7 of MORTH, and 45, 40, 37.5 mm, including
hirecharges of integrated stone crusher of 200 t/h including belt
conveyor and vibrating screens, tipper 5.5 cum (10t) capacity &
Frontend Loader and all labour charges complete.
Crushing of stone boulders of 150 mm size in an integrated stone
crushing unit of 200 t/h capacity comprising of primary and
secondary crushing units, belt conveyor and vibrating screens to
obtain stone aggregates 100 per cent passing through 53 mm sieve
as per Table 500.6 of Technical Specifications of MORD / 500-7 of
MORTH including the cost of stone.
12
RBR-LUCC-12
Unit = cum
Taking output = 750 cum at crusher location
a) Labour
day
Mate
day
Mazdoor (Skilled)
day
Mazdoor (Unskilled)
b) Material
cum
Stone Boulder of size 150 mm and below
c) Machinery
Integrated stone crusher of 200 t/h including belt conveyor hour
and vibrating screens
hour
Front end loader 1 cum bucket capacity
Tipper 5.5 cum capacity
d&e) Overheads & Contractors Profit
Total (a+b+c+d+e)
Cost for 750 cum = (a+b+c+d+e) x 0.85
Rate per cum =[ (a+b+c+d+e) x 0.85]/ 750
13
RBR-LUCC-13
Rate Amount
Rs.
Rs.
5
Remarks
7
2.760
17.000
800.000
6.000
20.000
hour
20.000
Note : 1) 800 cum of stone boulders are needed to get 750 cum of stone aggregates.
2) 85 per cent of above cost will be attributed to the production of 750 cum of stone aggregates of 40 mm
size and balance 15 per cent will be for smaller size aggregates and stone dust which comes out as a byproduct.
3) The integrated stone crusher includes primary and secondary crushing units.
Crushing of Stone Aggregates 100 per cent passing through
22.4 mm sieve as per Table 500.6 of Technical Specifications
(MORD) & 20mm, 19mm, including hirecharges of integrated
stone crusher of 200 t/h including belt conveyor and vibrating
screens, tipper 5.5 cum (10t) capacity & Frontend Loader and
all labour charges complete.
Crushing of stone boulders of 150 mm size in an integrated stone
crushing unit of 200 t/h capacity comprising of primary and
secondary crushing units, belt conveyor and vibrating screens to
obtain stone aggregates 100 per cent passing through 22.4 mm
sieve as per Table 500.6 of Technical Specifications & 20 mm and
19 mm including the cost of stone.
Unit = cum
Taking output = 670 cum at crusher location
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b) Material
Stone Boulder of size 150 mm and below
c) Machinery
day
day
day
2.760
17.000
cum
800.000
hour
6.000
hour
hour
20.000
20.000
Note : 1) 800 cum of stone boulders are needed to get 670 cum of stone aggregates.
2) 90 per cent of above cost will be attributed to the production of 670 cum of stone aggregate and
balance 10 per cent will be for smaller size aggregates and stone dust which comes out as a by-product.
14
RBR-LUCC-14
3) The integrated stone crusher includes primary and secondary crushing units.
Crushing of Stone Aggregates Nominal Size 13.2 mm as per
Table 500.9 of Technical Specifications (MORD) and Table 50021 MORTH and 14 mm, including hirecharges of integrated
stone crusher of 200 t/h including belt conveyor and vibrating
screens, tipper 5.5 cum (10t) capacity & Frontend Loader and
all labour charges complete.
Crushing of stone boulders of 150 mm size in an integrated stone
crushing unit of 200 t/h capacity comprising of primary and
secondary crushing units, belt conveyor and vibrating screens to
obtain stone aggregates of 13.2 mm nominal size as per Table
500.9 of Technical Specifications & 14 mm including the cost of
stone.
Unit = cum
Taking output = 600 cum at crusher location
a) Labour
Mate
day
274
RBR-LUCC
Index-code
S. No
Description
Unit
Quantity
3
day
4
2.760
Mazdoor (Skilled)
day
Mazdoor (Unskilled)
b) Material
cum
Stone Boulder of size 150 mm and below
c) Machinery
Integrated stone crusher of 200 t/h including belt conveyor hour
and vibrating screens
hour
Front end loader 1 cum bucket capacity
hour
Tipper 5.5 cum capacity
d&e) Overheads & Contractors Profit
Total (a+b+c+d+e)
Cost for 600 cum = (a+b+c+d+e) x 0.95
Rate per cum = [(a+b+c+d+e) x 0.95]/ 600
Rate Amount
Rs.
Rs.
5
Remarks
7
17.000
800.000
6.000
20.000
20.000
Note : 1) 800 cum of stone boulders are needed to get 600 cum of stone chips of size 13.2 mm and 125
cum stone dust.
2) 95 per cent of above cost will be attributed to the production of 600 cum of stone chips of 13.2 mm
size and balance 5 per cent to the production of stone dust which comes out as a by-product.
3) The analysis for crushing of stone chips of size 11.2 mm will be same as for 13.2 mm
A
15
RBR-LUCC-15
day
day
2.760
day
17.000
275
RBR-LUCC
Index-code
S. No
Description
Unit
Quantity
b) Material
cum
Stone Boulder of size 150 mm and below
c) Machinery
Integrated stone crusher of 200 t/h including belt conveyor hour
and vibrating screens
hour
Front end loader 1 cum bucket capacity
hour
Tipper 5.5 cum capacity
d&e) Overheads & Contractors Profit
Total (a+b+c+d+e)
Cost for 600 cum = (a+b+c+d+e) x 0.95
Rate per cum = [(a+b+c+d+e) x 0.95]/ 600
Rate Amount
Rs.
Rs.
5
Remarks
7
800.000
6.000
20.000
20.000
Note :- 1) 800 cum of stone boulders are needed to get 600 cum of stone chips of size 9.5 mm and 125
cum stone dust.
2) 95 per cent of above cost will be attributed to the production of 600 cum of stone chips of 9.5 mm size
and balance 5 per cent to the production of stone dust which comes out as a by-product.
3) The integrated stone crusher includes primary and secondary crushing units.
4) Cost of crushing of stone chips of size 6.7 mm will be 10 per cent extra over that of 9.5 mm size.
A
Unit = cum
a) Rate per cum for Crushing of Stone Aggregates 9.5 mm
as in S.No. 15
b) Add : 10% extra over that of 9.5 mm size
c) Total (a+b)
d) Overheads & Contractors Profit on (c)
Grand Total (c+d)
General Note
1. When materials are used for a finished item of work, overheads and Contractors
profit need not be included in cost of material data. Basic rates only to be carried out
as material cost.
2. Rates are for net quantities after deduction of voids.
Percentage reduction in volume of aggregates
As per Table 500 - 28 MORTH & Table 500 - 18 MORD
i.
75 mm and 63 mm
Percentage reduction in
volume computed by
stack measurements to
arrive at the volume to
be paid for
12.5
10
5
5
40
40
276
RBR-STCL
Chapter -2
SITE CLEARANCE
Index-code
RBR-STCL-1
S. No
Description
Unit
Quantity
Amount
Rs.
6
Remarks
7
RBR-STCL-2
Rate
Rs.
5
day
day
41.600
52.000
I
A
Unit = 10 sqm
Taking output = 1 hectare
By Manual Means
In area of non-thorny jungle (light jungle)
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Rate per hectare = a+b+c+d
Rate per 10 Sqm = (a+b+c+d)/1000
In area of thorny jungle
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Rate per hectare = a+b+c+d
Rate per 10 Sqm = (a+b+c+d)/1000
day
day
156.000
hour
1.000
day
day
208.000
hour
2.000
278
RBR-STCL
Index-code
S. No
Description
Unit
Quantity
II
A
By Mechanical Means
In area of non-thorny jungle (light jungle)
a) Labour
Day
Mate
Day
Mazdoor (Unskilled)
b) Machinery
Dozer D 50 with attachment or suitable machinery for hour
removal of trees & stumps
hour
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Rate per hectare = a+b+c+d
Rate per 10 Sqm = (a+b+c+d)/1000
In area of thorny jungle
a) labour
day
Mate
day
Mazdoor (Unskilled)
b) Machinery
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
4.160
10.00
1.00
6.240
hour
12.00
hour
1.50
Note : The top soil removed during clearing and grubbing of site, if
suitable for re-use shall be transported, conserved and stacked as
directed by the Engineer and shall be incidental to the work.
RBR-STCL-3
A
i
ii
iii
day
day
0.624
hour
0.070
day
day
0.936
hour
0.210
day
day
2.080
hour
0.280
279
RBR-STCL
Index-code
S. No
Description
Unit
Quantity
iv
vi
B
i
ii
iii
iv
day
day
4.160
hour
0.420
day
day
8.320
hour
1.000
day
day
26.000
hour
2.000
day
day
0.620
hour
0.100
day
day
0.936
hour
0.300
day
day
2.080
hour
0.400
day
day
4.160
hour
0.600
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
280
RBR-STCL
Index-code
S. No
Description
Unit
Quantity
vi
RBR-STCL-4
day
day
8.320
hour
1.200
day
day
26.000
hour
2.500
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
ii
iii
iv
day
day
0.416
hour
0.018
day
day
0.624
hour
0.050
day
day
1.383
hour
0.070
day
day
2.770
hour
0.110
day
day
5.540
hour
0.250
281
RBR-STCL
Index-code
S. No
Description
Unit
Quantity
vi
B
i
ii
iii
iv
day
day
15.600
hour
0.750
day
day
0.416
hour
0.025
day
day
0.624
hour
0.075
day
day
1.383
hour
0.100
day
day
2.770
hour
0.150
day
day
5.540
hour
0.300
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
282
RBR-STCL
Index-code
S. No
Description
Unit
Quantity
vi
RBR-STCL-5
day
day
15.600
hour
1.000
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
Unit = cum
Taking output = 1.25 cum
I
A
By Manual Means
Lime Concrete & CC upto M10
a) labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Cost for 1.25 cum = a+b+c+d
Rate per cum = (a+b+c+d)/1.25
II
By Mechanical Means
Cement Concrete
day
day
1.040
hour
0.27
day
day
1.300
prestressed
day
day
0.400
day
3.500
hour
0.270
a) labour
day
Mate
day
Mazdoor (Unskilled)
b) Machinery
Air compressor 210 / 250 cfm with 2 leads of pneumatic hour
breaker @1.5 cum per hour
hour
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Cost for 1.25 cum = a+b+c+d
Rate per cum = (a+b+c+d)/1.25
0.520
0.83
0.27
283
RBR-STCL
Index-code
S. No
1
B
Description
2
Reinforced Cement Concrete and prestressed Concrete
Unit
Quantity
a) labour
day
Mate
day
Mazdoor (Unskilled)
day
Blacksmith
b) Machinery
Air compressor 170-210 / 250 cfm working with 2 Jack hour
Hammers simultaneously @1.00 cum per hour
hour
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Cost for 1.25 cum = a+b+c+d
Rate per cum = (a+b+c+d)/1.25
RBR-STCL-6
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
0.960
0.25
1.25
0.27
Unit = cum
Taking output = 1.25 cum
A
Lime mortar
a) labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Cost for 1.25 cum = a+b+c+d
Rate per cum = (a+b+c+d)/1.25
Cement mortar
a) labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Cost for 1.25 cum = a+b+c+d
Rate per cum = (a+b+c+d)/1.25
Mud Mortar
a) labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Cost for 1.25 cum = a+b+c+d
Rate per cum = (a+b+c+d)/1.25
Dry Brick Pitching or Brick Solling
a) labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Cost for 1.25 cum = a+b+c+d
Rate per cum = (a+b+c+d)/1.25
day
day
0.520
hour
0.270
day
day
0.780
hour
0.270
day
day
0.416
hour
0.270
day
day
0.364
hour
0.270
284
RBR-STCL
Index-code
RBR-STCL-7
S. No
Description
Unit
Quantity
as
per
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
Technical
Unit = cum
Taking ouput = 1.25 cum
Rubble Stone Masonry in Lime Mortar
a) labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Cost for 1.25 cum = a+b+c+d
Rate per cum = (a+b+c+d)/1.25
Rubble Stone Masonry in Cement Mortar
a) labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Cost for 1.25 cum = a+b+c+d
Rate per cum = (a+b+c+d)/1.25
Rubble Stone Masonry in Mud Mortar
a) labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Cost for 1.25 cum = a+b+c+d
Rate per cum = (a+b+c+d)/1.25
Dry Rubble Masonry
a) labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Cost for 1.25 cum = a+b+c+d
Rate per cum = (a+b+c+d)/1.25
Dismantling Stone Pitching / Dry Stone Spalls
a) labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Cost for 1.25 cum = a+b+c+d
Rate per cum = (a+b+c+d)/1.25
day
day
0.620
hour
0.270
day
day
0.780
hour
0.270
day
day
0.520
hour
0.270
day
day
0.468
hour
0.270
day
day
0.416
hour
0.270
a) labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Cost for 1.25 cum = a+b+c+d
Rate per cum = (a+b+c+d)/1.25
day
day
0.520
hour
0.270
285
RBR-STCL
Index-code
S. No
Description
Unit
Quantity
day
day
0.500
day
1.060
hour
0.270
RBR-STCL-8
RBR-STCL-9
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
2.9
day
day
1.000
day
2.640
2.50%
hour
0.170
day
day
2.100
day
0.500
2.50%
hour
0.170
day
day
0.013
day
0.014
286
RBR-STCL
Index-code
S. No
Description
Unit
Quantity
10
RBR-STCL-10
11
RBR-STCL-11
12
RBR-STCL-12
13
RBR-STCL-13
day
day
3.640
day
day
1.300
day
day
1.460
day
day
0.310
day
day
4.160
hour
0.320
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
0.540
287
RBR-STCL
Index-code
S. No
Description
Unit
Quantity
RBR-STCL-14
14
I
A
Amount
Rs.
6
Remarks
7
0.730
1.250
1.560
0.380
Granular Courses
a) labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
II
Rate
Rs.
5
day
day
1.040
hour
0.330
By Mechanical Means
Bituminous Courses
a) labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with trolley 3t
Tractor with ripper @ 60 cum per hour
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
day
day
0.310
hour
0.380
hour
0.017
288
RBR-STCL
Index-code
RBR-STCL-15
S. No
Description
Unit
Quantity
15
16
Amount
Rs.
6
Remarks
7
RBR-STCL-16
Rate
Rs.
5
day
day
0.500
day
0.530
hour
1.000
hour
0.400
hour
1.000
RBR-STCL-17
17
day
day
0.156
hour
0.050
day
day
0.156
hour
0.200
289
RBR-STCL
Index-code
RBR-STCL-18
RBR-STCL-19
S. No
Description
Unit
Quantity
18
19
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
0.240
0.300
Unit = each
Taking output = 1 km stone
A
5th km Stone
day
day
0.780
hour
0.150
day
day
0.520
hour
0.075
day
day
0.104
hour
0.020
290
RBR-STCL
Index-code
RBR-STCL-20
S. No
Description
Unit
Quantity
20
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
Dismantling of Fencing
Dismantling of barbed wire fencing / wire mesh fencing
including posts, foundation concrete, backfilling of pit by
manual means including disposal of dismantled material
with all lifts and upto a lead of 1000 m, stacking
serviceable
material
and
unserviceable
material
separately as per Technical Specification Clause 202
MORD / MORTH.
Unit = running m
Taking output = 30 m
a) labour
Mate
Mazdoor (Unskilled)
Blacksmith
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Cost of 30 m = a+b+c+d
Rate per m = (a+b+c+d)/30
RBR-STCL-21
21
day
day
3.150
day
0.750
hour
0.150
day
day
2.090
day
0.250
hour
0.250
hour
0.500
Note : The rate analysis does not include any excavation in earth or
dismantling of masonry works which are to be measured and paid
separately.
RBR-STCL-22
22
RBR-STCL-23
23
Unit = running m
Taking output = 10 m
a) labour
day
Mate
day
Mazdoor (Unskilled)
b) Machinery
hour
Crane upto 8 t capacity
hour
Truck flat body 10 t
c&d) Overheads & Contractors Profit
Cost for 10 m = a+b+c+d
Rate per m = (a+b+c+d)/10
Note : The rate analysis does not include any excavation in
earth or dismantling of masonry works which are to be
measured and paid separately.
Removal of Telephone/Electric Poles and Lines
2.600
0.300
1.000
291
RBR-STCL
Index-code
S. No
Description
Unit
Quantity
a) labour
Mate
Mazdoor (Unskilled)
Electrician / Lineman
b) Machinery
Tractor with trolley 3t
c&d) Overheads & Contractors Profit
Cost for 30 poles = a+b+c+d
Rate per pole = (a+b+c+d)/30
day
day
10.480
day
2.000
hour
1.500
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
292
RBR-EECD
Chapter - 3
EARTHWORK, EROSION CONTROL AND DRAINAGE
Index-code
RBR-EECD-1
S. No
Description
Unit Quantity
3
Rate Amount
Rs.
Rs.
5
Remarks
7
ii
day
Mate
day
Mazdoor (Unskilled)
b) Machinery
hour
Tractor with trolley
c&d) Overheads & Contractors Profit
Cost for 100 sqm = a+b+c+d
Rate per sqm = (a+b+c+d)/100
Note : In case material is to be reused at site, transportation cost
catered above (Sub-item b) for disposal shall be deleted.
Scarifying existing granular surface to a depth of 50 mm and
disposal of scarified material with all lifts and leads upto
1000 m as per Technical Specification Clause 305.4.3
MORTH
4.160
1.500
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with trolley
c&d) Overheads & Contractors Profit
Cost for 100 sqm = a+b+c+d
Rate per sqm = (a+b+c+d)/100
day
day
5.200
hour
1.670
RBR-EECD-2
2
i
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with ripper attachment @ 60 cum per hour
Front end loader 1 cum bucket capacity @ 50 cum per hour
day
day
0.260
hour
0.250
hour
0.300
hour
0.680
296
RBR-EECD
Index-code
S. No
Description
2
ii
RBR-EECD-3
Rate Amount
Unit Quantity
Rs.
Rs.
3
Remarks
7
0.260
0.080
hour
0.200
hour
0.230
Unit = cum
Taking output = 100 cum
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Dozer D-50 for spreading @ 200 cum per hour
Motor grader for grading @ 200 cum per hour
Water tanker 6 kl capacity
Three wheel 80-100 kN Static Roller
(or)
Vibratory Roller 80 - 100 kN @ 100 cum per hour
c) Material
Water
d&e) Overheads & Contractors Profit
Cost for 100 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/100
Cost for 100 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/100
day
day
0.520
hour
0.500
hour
hour
0.500
2.000
hour
1.250
hour
1.000
kl
12.000
Note : In case the earth cutting is done by dozer and pushed for filling in
the embankment, the input of dozer in the cost of embankment shall be
deleted as the same is already provided in the cost of excavation.
However, if the earth is dumped by tippers from roadway cutting, the input
of dozer for spreading is required to be provided.
RBR-EECD-4
Unit = cum
Taking output = 100 cum
a) Labour
Mate
Mazdoor (Unskilled)
day
day
1.040
hour
hour
hour
1.670
4.500
0.500
b) Machinery
Hydraulic Excavator 0.9 cum bucket capacity @ 60 cum per hour
297
RBR-EECD
Index-code
S. No
Description
Rate Amount
Unit Quantity
Rs.
Rs.
3
hour
4
0.500
hour
2.000
hour
1.250
hour
1.000
Remarks
7
or
Vibratory Roller 80 - 100 kN @ 100 cum per hour
c) Material
kl
12.000
Water
cum 100.000
Compensation for earth taken from private land
d&e) Overheads & Contractors Profit
Cost for 100 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/100
Cost for 100 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/100
Note : 1. Compensation for earth will vary from place to place and
will have to be assessed realistically as per particular ground
situation. In case earth is available from Govt. land, compensation
for earth will not be required. The position is required to be clearly
stated in the cost estimate.
2. Loading & Unloading shall not be allowed since excavation
proposed with hydraulic excavator and unloading by tipping.
ii
Unit = cum
Taking output = 10 cum
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
day
day
0.104
hour
0.167
t.km
16 x L
hour
0.050
hour
0.100
hour
0.400
hour
0.100
c) Material
Water
Compensation for earth taken from private land
d&e) Overheads & Contractors Profit
Cost for 10 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/10
kl
0.240
cum
10.000
Note : Compensation for earth will vary from place to place and will have
to be assessed realistically as per particular ground situation. In case earth
is available from Govt. land, compensation for earth will not be required.
The position is required to be clearly stated in the cost estimate.
298
RBR-EECD
Index-code
S. No
Description
2
Forming embankment with Side earth by mechanical means
including pre-watering of soil, removal of top soil, excavation of
soils, depositing the soils on the embankment, spreading soils,
breaking clods, sectioning and consolidation with Vibratory
Road Roller @ OMC to meet requirement of table 300-2 of
MoRT&H, including all hire and operational charges of T&P
and seigniorage charges, complete for finished item of work as
per MoRT&H specification 305 (4th revision) (Payment will be
made based on level for finished item of work).
iii
Unit = cum
Taking output = 100 cum
a) Labour
Mate
Mazdoor (Unskilled)
Rate Amount
Unit Quantity
Rs.
Rs.
3
day
day
0.520
Remarks
7
b) Machinery
RBR-EECD-5
1.670
Hydraulic Excavator 0.9 cum bucket capacity @ 60 cum hr
per hour
hour
1.00
Motor grader for grading @ 200 cum per hour
hour
4.00
Water tanker 6 kl capacity
hour
1.00
Vibratory Roller 80 - 100 kN
kl
24.000
C) Water
cum 100.000
d) Seigniorage Charge
Total
e) Overheads & Contractors Profit
Cost for 100 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/100
Rate per cum
a) Excavation in Cutting in Soil by manual means with
lead upto 50 m
Excavation for roadway in soil using manual means for
carrying of cut earth to embankment site with initial lift of 3
mts and lead upto 50 m as per Technical Specification
Clause 302.3 MORD
Unit = cum
Taking output = 120 cum
a) Labour
day
Mate
day
46.800
Mazdoor (Unskilled)
b&c) Overheads & Contractors Profit
Cost of 120 cum = a+b+c
Rate per cum = (a+b+c)/120
46.800
10.000
Note : In case there is a situation where the cross-section is of cut and fill
and cut earth is required to be used in embankment in the immediate
vicinity, the item of carriage in the truck shall be omitted.
299
RBR-EECD
Index-code
S. No
1
ii
Rate Amount
Unit Quantity
Rs.
Rs.
Description
2
Excavation in Soil with Dozer with lead upto 100m
Remarks
7
iii
day
day
2.080
hour
3.600
and
Unit = cum
Taking output = 360 cum
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Hydraulic excavator 0.9 cum bucket capacity @ 100 cum/ hour
RBR-EECD-6
day
day
2.080
hour
hour
3.60
15.00
Unit = cum
Taking output = 300 cum
a) Labour
day
Mate
day
Mazdoor (Unskilled)
b) Machinery
Hydraulic excavator 0.90 cum bucket capacity @ 50 cum per hour
hour
hour
Tipper 5.5 cum capacity, 4 trips per hour.
c&d) Overheads & Contractors Profit
Cost for 300 cum = a+b+c+d
Rate per cum = (a+b+c+d)/300
2.080
6.00
12.50
300
RBR-EECD
Index-code
S. No
1
RBR-EECD-7
Description
2
Rate Amount
Unit Quantity
Rs.
Rs.
3
Remarks
7
Unit = cum
Taking output = 360 cum
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Excavator 0.90 cum bucket capacity @ 100 cum per hour
Tipper 5.5 cum capacity, 4 trips per hour
c&d) Overheads & Contractors Profit
Cost for 360 cum = a+b+c+d
Rate per cum = (a+b+c+d)/360
day
day
2.080
hour
hour
3.60
15.00
RBR-EECD-8
i
a
72.800
day
day
72.800
hour
10.000
301
RBR-EECD
Index-code
S. No
Description
2
c
Rate Amount
Unit Quantity
Rs.
Rs.
3
Remarks
7
day
Mazdoor (Unskilled)
day
2.080
3.000
b) Machinery
c) Seigniorage Charges
d) Overheads & Contractors Profit
Cost for 180 cum = a+b+c+d
cum
180.000
iii
3.120
2.160
day
day
2.080
hour
hour
6.00
11.00
302
RBR-EECD
Index-code
S. No
1
Description
2
iv
Rate Amount
Unit Quantity
Rs.
Rs.
3
RBR-EECD-9
Remarks
2.080
6.0000
16.00
cum
c) Seigniorage Charges
d) Overheads & Contractors Profit
Cost for 360 cum = a+b+c+d
Rate per cum a+b+c+d / 360 (OR)
Excavation in Hard Rock (requiring blasting) with
disposal upto 1000 m
Excavation for roadway in hard rock (requiring blasting) by
drilling, blasting and breaking, trimming of bottom and side
slopes in accordance with requirements of lines, grades and
cross-sections, loading and disposal of cut rock with all lifts
and leads upto 1000 m as per Technical Specification
Clause 302.3.5 MORD / 301 MORTH
Unit = cum
Taking output = 180 cum
a) Labour
Mate
Mazdoor (Unskilled)
Driller
Blaster
b) Machinery
Dozer D-50 @ 30 cum per hour
Air compressor, 210 cfm with 2 jack hammers
Front end loader 1 cum bucket capacity @ 30 cum / hour
Tipper 5.5 cum capacity, 2 trips per hour
c) Materials
Gelatine 80 per cent
Electric Detonators @ 1 detonator for 2 gelatine sticks of
285 gm each
Credit for excavated rock found suitable for use @ 50 per
cent quantity blasted
d&e) Overheads & Contractors Profit
Cost for 180 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/180
day
day
3.220
day
2.00
day
0.25
hour
6.00
hour
6.00
hour
hour
6.00
16.00
kg
70.00
each
252.00
cum
90.00
303
RBR-EECD
Index-code
S. No
Description
2
ii
Rate Amount
Unit Quantity
Rs.
Rs.
3
Remarks
7
day
day
17.640
day
24.00
day
1.00
hour
2.90
Credit for excavated rock found suitable for use @ 50 per cent of cum
excavated quantity
8.00
10.400
6.000
6.50
18.00
Unit = cum
Taking output = 180 cum
a) Labour
Mate
Mazdoor (Unskilled)
Driller
Blaster
day
day
3.220
day
2.00
day
0.50
304
RBR-EECD
Index-code
S. No
Description
b) Machinery
Dozer D-50 @ 30 cum per hour
Air compressor, 210 cfm with 2 jack hammers
Front end loader 1 cum bucket capacity
Tipper 5.5 cum capacity, 4 trips per hour
c) Materials
Gelatine 80 per cent
Electric detonators @ 1 detonator for 2 gelatine stick of 285
gm each
10
RBR-EECD-10
Rate Amount
Unit Quantity
Rs.
Rs.
3
hour
6.00
hour
6.00
hour
6.00
hour
8.20
kg
70.00
each
1008.00
Credit for excavated rock found suitable for use @ 50 per cum
cent quantity blasted
d&e) Overheads & Contractors Profit
Cost for 180 cum =a+b+c+d+e
Rate per cum = (a+b+c+d+e)/180
Note : 1. Credit is considered for 50 per cent of quantity of blasted
rock, if found suitable for construction.
2. In case some rock is issued to the Contractor at site, the item of
carriage shall be reduced to that extent.
Extra for every additional lift of 1.5 m or part thereof over
initial lift of 3 m in all kinds of soils & rock, when
executed manually
For every additional lift of 1.5 m
Remarks
7
90.00
Unit 40 cum
Labour
day
Mazdoor (Unskilled)
Overheads & Contractors Profit
Cost for 40 cum
Rate per 1 cum
Extra for every additional lead of 50 m or part thereof
over initial lead of 50 m in all kinds of soils & rock, when
executed manually
For every additional lead of 50 m
1.00
Unit 7 cum
Labour
day
Mazdoor (Unskilled)
Overheads & Contractors Profit
Cost for 7 cum
Rate per 1 cum
Note : Head Leads limited to 150 m. Beyond 150 m only
conveyance by machinery
RBR-EECD-11
11
1.00
5.200
0.100
305
RBR-EECD
Index-code
S. No
Description
RBR-EECD-12
RBR-EECD-13
12
13
14
Remarks
7
RBR-EECD-14
Rate Amount
Unit Quantity
Rs.
Rs.
Water
d&e) Overheads & Contractors Profit
Cost for 100 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/100
Seeding and Mulching
day
day
2.080
hour
6.000
day
day
3.120
hour
2.00
hour
1.00
cum
kl
0.18
12.00
Unit = sqm
Taking output = 240 sqm
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
day
day
10.400
hour
14.00
hour
2.40
kg
3.60
cum
0.43
litere
55.20
sqm
264.00
kl
84.00
306
RBR-EECD
Index-code
S. No
Description
RBR-EECD-15
15
Rate Amount
Unit Quantity
Rs.
Rs.
3
Remarks
7
Unit = cum
Taking output = 100 cum
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
day
day
1.040
hour
1.00
hour
4.50
cum
100.00
cum
100.00
hour
0.50
hour
0.50
hour
2.00
hour
1.43
hour
1.25
OR
Vibratory road roller 8-10 tonnes @ 80 cum per hour
c) Material
Water
Compensation for earth taken from private land
d&e) Overheads & Contractors Profit
Cost for 100 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/100
Cost for 100 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/100
RBR-EECD-16
16
kl
12.000
cum
100.000
day
day
2.080
hour
6.000
hour
7.500
hour
7.500
hour
4.000
kl
24.000
307
RBR-EECD
Index-code
S. No
1
Description
2
ii
Rate Amount
Unit Quantity
Rs.
Rs.
3
Remarks
7
Unit = cum
Taking output = 600 cum
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Tractor with ripper attachment
Motor grader for grading
Water tanker 6 kl capacity
Three wheel 80-100 kN Static Roller @70 cum per hour
OR
Vibratory road roller 8-10 tonnes @ 80 cum per hour
c) Material
Water
d&e) Overheads & Contractors Profit
Cost for 600 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/600
Cost for 600 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/600
RBR-EECD-17
17
day
day
3.120
hour
9.000
hour
6.000
hour
4.000
hour
8.600
hour
7.500
kl
24.000
RBR-EECD-18
18
Unit = sqm
Taking output = 3500 sqm
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor skilled
b) Machinery
Three wheel static roller 80-100 kN
Water tanker 6 kl, one trip per hour
c) Material
Water
d&e) Overheads & Contractors Profit
Cost for 3500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/3500
Presplitting Rock Excavation Slopes
day
day
6.280
day
1.00
hour
3.00
hour
2.00
kl
12.00
Unit = sqm
Taking output = 400 sqm (120 cum considering 300 mm
average depth of excavation over the existing rock face)
a) Labour
day
Mate
day
Mazdoor (Unskilled)
b) Machinery
Air compressor 250/210 cfm with 2 leads @ 20 cum per hour
hour
hour
Dozer D-50
hour
Front end loader 1 cum bucket capacity
hour
Tipper 5.5 cum capacity 2 trip per hour
c) Material
kg
Gelatine 80 per cent
Electric detonators @ 1 detonator for 2 gelatine sticks of 285 each
gm each
15.600
6.00
6.00
6.00
11.00
42.00
672.00
308
RBR-EECD
Index-code
S. No
Description
19
Rate Amount
Unit Quantity
Rs.
Rs.
3
Remarks
7
RBR-EECD-19
Unit = cum
Taking output = 360 cum
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
day
day
4.160
hour
6.00
hour
16.00
cum
360.00
cum
360.00
hour
1.80
hour
1.80
hour
9.00
hour
4.50
hour
3.60
kl
54.00
OR
RBR-EECD-20
20
Unit = m
Taking output = 10 m
(A) Manual Means
a) Labour
Mate
Mazdoor (Unskilled)
b&c) Overheads & Contractors Profit
Cost for 10 m = a+b+c
Rate per m = (a+b+c)/10
day
day
2.080
309
RBR-EECD
Index-code
S. No
Description
Rate Amount
Unit Quantity
Rs.
Rs.
3
Remarks
7
ii
day
day
0.260
hour
0.040
day
day
3.120
day
day
0.520
hour
0.100
RBR-EECD-21
21
A
cum
cum
cum
sqm
cum
310
RBR-EECD
Index-code
S. No
1
Description
2
Rate Amount
Unit Quantity
Rs.
Rs.
3
Remarks
7
cum
Rate as per item No.5 of Chapter 12.
(c) Coursed rubble stone masonry (2nd Sort) in cement
mortar 1:4
cum
Rate as per item No. 4 (II) (ii) of Chapter 12.
sqm
RBR-EECD-22
22
RBR-EECD-23
23
Unit = m
Taking output = 10 m
a) Labour
day
Mate
day
2.040
Mazdoor for excavation and back filling
c) Material
m
10.000
Perforated pipe of cement concrete, internal dia 100mm
cum
2.400
Crushed stone as per table 300-3
d&e) Overheads & Contractors Profit
Cost for 10 m = a+b+c+d+e
Rate per m = (a+b+c+d+e) /10
Note : Type of pipe may be modified depending upon provision in
design.
Aggregate Sub-Surface Drains
Construction of aggregate sub surface drain 300 mm x 450 mm with
aggregates conforming to table 300-4, excavated material to be
utilised in roadway as per Specification 309 MORTH
Unit = metre
Taking output = 10 metres
a) Labour
day
Mate
Mazdoor for excavation and back filling with aggregates day
b)
Material
cum
Crushed stone as per table 300-3 MORTH
c&d) Overheads & Contractors Profit
Cost for 10 metres = a+b+c+d
Rate per metre = (a+b+c+d)/10
Note : Provide suitable grading as per table 300-3 MORTH,
keeping classification of soils met.
1.520
1.350
311
RBR-EECD
Index-code
S. No
1
RBR-EECD-24
24
Description
2
Rate Amount
Unit Quantity
Rs.
Rs.
3
Remarks
7
RBR-EECD-25
25
1.500
0.495
RBR-EECD-26
24
Unit = sqm
Taking output = 3500sqm
a) Labour
Mate
Mazdoor
Mazdoor skilled
b)
Machinery
Smooth 3 wheeled steel roller 8-10 tonnes
Water tanker 6 KL, one trip per hour
c)
Material
Cost of water
d&e) Overheads & Contractors Profit
Cost for 3500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/3500
Construction of Rock fill Embankment
Construction of rock fill embankment with broken hard rock
fragments of size not exceeding 300 mm laid in layers not
exceeding 500 mm thick including filling of surface voids with
stone spalls, blinding top layer with granular material, rolled
with vibratory road roller, all complete as per clause 313
MORTH.
Unit = cum
Taking output = 100 cum
a) Labour
Mate
Mazdoor for excavation and back filling
b) Machinery
Dozer 80 HP for spreading @ 200 cum per hour
Vibratory road roller 8-10 tonnes @ 100 cum per hour
Water tanker 6 kl, one trip per hour
c) Material
Cost of Water
c&d) Overheads & Contractors Profit
Cost for 100 cum = a+b+c+d
Rate per cum = (a+b+c+d) / 100
day
day
day
6.280
1.000
hour
hour
3.000
3.000
KL
18.000
day
day
1.540
Hour
0.50
Hour
1.00
Hour
2.00
Kl
12.00
312
RBR-EECD
Index-code
S. No
Description
RBR-EECD-27
27
Rate Amount
Unit Quantity
Rs.
Rs.
3
Remarks
7
There is mixed traffic on urban roads like slow moving hand and animal driven carts,
rickshaws, cycles, two/ three wheeler apart from the usual vehicular traffic resulting into
traffic jams. This causes loss of working time which may be in the range of 10 -15 per cent
b)
There is considerable disruption of traffic adversely affecting the efficiency of the working
parties including machines due to congestion caused by pedestrian traffic, local road side
venders, parking of vehicles by the road side, encroachments by the shopkeepers and local
shops who make use of the berms of the road in front of these shops and unauthorised
conversion of road berms into mini local market The output of manpower and machines is
substantially reduced due to factors mentioned above.
c)
Cost of living in urban areas is comparatively more resulting into higher wages.
d)
At times, work is executed during night time due to heavy traffic during day time. This
involves extra expenditure by way of making arrangement for lighting and special transport
for working parties due to odd hour
In the light of above, the authorities engaged in preparing the cost estimates may exercise
their judgment and cater for the additional cost to the extent of 2 to 3 per cent, keeping in
view the severity of factors mentioned above. Supporting details for the extra cost based on
the actual conditions in specific cases will have to give in justification.
313
RBR-SBBS
Chapter - 4
GRANULAR SUB-BASES, BASES (NON-BITUMINOUS) AND SHOULDERS
Index-code
RBR-SBBS-1
S. No
Description
Unit
Quantity
day
day
day
2.48
10.00
hour
hour
6.00
30.00
hour
hour
6.00
12.00
hour
3.00
cum
cum
cum
kl
192.00
77.00
115.00
18.00
day
day
day
2.48
10.00
hour
hour
6.00
30.00
hour
hour
hour
6.00
12.00
3.00
cum
cum
cum
kl
134.00
96.00
153.00
18.00
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
ii
315
RBR-SBBS
Index-code
S. No
1
iii
Description
Unit
Quantity
day
day
day
2.40
8.00
hour
hour
6.00
30.00
hour
hour
hour
6.00
12.00
3.00
cum
cum
255.00
129.00
cum
cum
cum
kl
134.40
48.00
201.60
18.00
day
day
day
2.40
8.00
hour
hour
7.50
4.00
Front end loader 0.9 cum / 1 cum bucket capacity 37.5 cum per
hour
hour
6.00
hour
hour
hour
13.60
4.50
22.50
OR
vibratory roller 80-100 kN
hour
6.00
cum
cum
cum
kl
144.00
57.00
86.40
24.00
2
For Grading III Material (CBR Value minimum 20)
Unit = cum
Taking output = 300 cum
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b) Machinery
Motor Grader 110 HP @ 50 cum per hour
Three wheel 80-100 kN static roller @ 10 cum per hour
OR
vibratory roller 80-100 kN
Tractor with Rotavator 25 cum per hour
Water tanker 6 kl capacity
c) Material
Well graded/ Close Graded granular sub-base material as per
Table 400.1
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
Total
d&e) Overheads & Contractors Profit
Cost for 300cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/300
Cost for 300 cum = a+b+c+d+e (Vibratory Roller)
B
c) Material
Well graded/ Close Graded granular sub-base material
as per Table 400.1
53 mm to 9.5 mm @ 50 per cent
9.5 mm to 2.36 mm @ 20 per cent
2.36 mm below @ 30 per cent
Water
d&e) Overheads & Contractors Profit
Cost for 225 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/225
Cost for 225 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/225
316
RBR-SBBS
Index-code
S. No
1
ii
Description
2
For Grading II Material (CBR Value minimum 25)
Unit = cum
Taking output = 225 cum (450 t)
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b) Machinery
Wet mix plant @ 75 t capacity per hour
Water tanker 6 kl capacity 5 km lead with one trip per hour
Front end loader 0.9 cum bucket capacity 37.5 cum per hour
iii
Unit
Quantity
day
day
day
2.40
8.00
hour
hour
7.50
4.00
hour
hour
hour
hour
6.00
13.60
4.50
22.50
hour
6.00
cum
cum
cum
kl
100.80
72.00
115.20
24.00
day
day
day
2.40
8.00
hour
hour
7.50
4.00
hour
hour
hour
hour
6.00
13.60
4.50
22.50
hour
6.00
cum
cum
cum
kl
100.80
36.00
151.20
24.00
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
Unit = cum
Taking output = 225 cum (450 t)
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b) Machinery
Wet mix plant @ 60 t capacity per hour
Water tanker 6 kl capacity 5 km lead with one trip per hour
Front end loader 0.9 cum bucket capacity 37.5 cum per hour
317
RBR-SBBS
Index-code
RBR-SBBS-2
S. No
Description
Unit
Quantity
day
day
day
2.40
8.00
hour
hour
hour
6.00
6.00
3.00
cum
cum
cum
KL
134.40
172.80
76.80
18.00
cum
cum
KL
288.00
96.00
18.00
cum
cum
KL
255.00
129.00
18.00
day
day
day
2.40
8.00
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
Unit = cum
Taking output = 300 cum
a) Labour
Mate
Mazdoor skilled
Mazdoor
b)
Machinery
Mortar Grader 110 HP @ 50 cum per hour
Vibratory roller 8 -10 tonne
Water tanker 6 KL capacity
c)
Material
For coarse graded Granular sub-base Materials per table
400-2
For grading-I Material (CBR Value minimum 30)
53 mm to 26.5 mm @ 35 per cent
26.5 mm to 4.75 mm @ 45 per cent
2.36 mm below @ 20 per cent (Coarse Sand)
Cost of water
OR
For Grading-II Material (CBR Value minimum 25)
26.5 mm to 4.75 mm @ 75 per cent
2.36 mm below @ 25 per cent (Dust)
Cost of water
OR
For Grading-III Material (CBR Value minimum 20)
9.5 mm to 4.75 mm @ 66 per cent
2.36 mm below @ 34 per cent (Dust)
Cost of water
(i) Rate per cum for grading-I Material
d&e) Overheads & Contractors Profit
Cost for 300 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/300
(ii) Rate per cum for grading-II Material
d&e) Overheads & Contractors Profit
Cost for 300 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/300
(iii) Rate per cum for grading-III Material
d&e) Overheads & Contractors Profit
Cost for 300 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/300
Note : Any one of the grading for material may be
adopted as per design
B (i) Gravel / Soil - Aggregate Base (Table 400.2) Grading A
a) Construction of gravel / soil - aggregate base by providing
well graded material, spreading in uniform layers with motor
grader on prepared surface, mixing by mix in place method with
rotavator at OMC, and compacting with three wheel 80-100 kN
static roller / Vibratory Roller 80-100 kN to achieve the desired
density, complete as per Technical Specifications Clause 402
MORD.
Unit = cum
Taking output = 300 cum
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
318
RBR-SBBS
Index-code
S. No
Description
Unit
Quantity
hour
hour
6.00
30.00
hour
hour
hour
6.00
5.00
12.00
cum
cum
cum
kl
134.40
172.80
76.80
30.00
day
day
day
2.40
8.00
hour
hour
6.00
30.00
hour
hour
hour
6.00
5.00
12.00
cum
cum
kl
288.00
96.00
30.00
b) Machinery
Motor grader 110 HP @ 50 cum per hour
Three wheel 80-100 kN static roller @ 10 cum per hour
OR
Vibratory Roller 80-100 kN
Water tanker 6 kl capacity
Tractor with Rotavator 25 cum per hour
c) Material
For well graded granular sub-base materials as per Table
400.2
For Grading A Material
53 mm to 26.5 mm @ 35 per cent
26.5 mm to 4.75 mm @ 45 per cent
2.36 mm below @ 20 per cent
Water
d&e) Overheads & Contractors Profit
Cost for 300 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/300
Cost for 300 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/300
ii
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
OR
Vibratory Roller 80-100 kN
Water tanker 6 kl capacity
Tractor with Rotavator 25 cum per hour
c) Material
For well graded granular sub-base materials as per Table
400.2
For Grading B Material
26.5 mm to 4.75 mm @ 75 per cent
2.36 mm below @ 25 per cent
Water
d&e) Overheads & Contractors Profit
Cost for 300 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/300
Cost for 300 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/300
319
RBR-SBBS
Index-code
S. No
Description
Unit
Quantity
2
Gravel / Soil - Aggregate Base (Table 400.2) Grading C
a) Construction of granular sub-base by providing well graded
material, spreading in uniform layers with motor grader on
prepared surface, mixing by mix in place method with rotavator
at OMC, and compacting with three wheel 80-100 kN static
roller / Vibratory Roller 80-100 kN capacity to achieve the
desired density, complete as per Technical Specification Clause
402 MORD
day
day
day
2.40
8.00
iii
Unit = cum
Taking output = 300 cum
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b) Machinery
Motor grader 110 HP @ 50 cum per hour
hour
6.00
hour
30.00
hour
hour
hour
6.00
5.00
12.00
cum
cum
kl
255.00
129.00
30.00
day
day
day
2.40
8.00
hour
hour
6.00
30.00
hour
hour
hour
6.00
5.00
12.00
cum
cum
kl
153.60
210.40
30.00
OR
Vibratory Roller 80-100 kN
Water tanker 6 kl capacity
Tractor with Rotavator 25 cum per hour
c) Material
For well graded granular sub-base materials as per Table
400.2
For Grading C Material
9.5 mm to 4.75 mm @ 66 per cent
2.36 mm below @ 34 per cent
Water
d&e) Overheads & Contractors Profit
Cost for 300 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/300
Cost for 300 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/300
C
i
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
Unit = cum
Taking output = 300 cum
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b) Machinery
Motor grader 110 HP @ 50 cum per hour
Three wheel 80-100 kN static roller @ 10 cum per hour
OR
Vibratory Roller 80-100 kN
Water tanker 6 kl capacity
Tractor with Rotavator 25 cum per hour
c) Material
For well graded granular sub-base materials as per Table 400.3
320
RBR-SBBS
Index-code
RBR-SBBS-3
S. No
Description
Unit
Quantity
day
day
day
2.44
35.00
hour
2.15
hour
3.00
t
kl
5.26
18.00
day
day
day
1.36
8.00
hour
12.00
hour
hour
6.00
4.30
hour
5.00
t
kl
10.50
30.00
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
day
day
1.36
day
8.00
321
RBR-SBBS
Index-code
S. No
Description
Unit
Quantity
b)
Machinery
Tractor with ripper and rotavator attachments @ 60 cum
per hour for ripping and 25 cum per hour for mixing
hour
12.00
hour
Motor Grader 110 HP @ 50 cum per hour
hour
Vibratory roller 8 - 10 tonne capacity
hour
Water tanker 6 KL capacity
c)
Material
tonne
Lime at site
KL
Cost of water
d&e) Overheads & Contractors Profit
Cost for 300 cum= a+b+c+d+e
Rate per cum =( a+b+c+d+e)/300
Note : Though vibratory roller is required only for 3 hours as per
norms, but the same has to be available at site for 6 hours as
other machines for spreading and mixing will take 6 hours. The
usage rates of roller have been multiplied with a factor of 0.65.
RBR-SBBS-4
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
6.00
3.90
12.00
15.75
72.00
day
day
2.44
day
35.00
hour
2.50
hour
6.00
tonne
8.00
KL
36.00
day
day
day
2.48
10.00
Unit = cum
Taking output = 300 cum (525 t)
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b) Machinery
Hydraulic Excavator 0.90 cum bucket capacity
hour
5.00
hour
hour
hour
14.00
6.00
4.30
hour
hour
12.00
5.00
t
kl
21.00
30.00
322
RBR-SBBS
Index-code
S. No
Description
Unit
Quantity
2
Providing, laying and spreading soil on a prepared sub
grade, pulverising, mixing the spread soil in place with
rotavator with 3 per cent slaked lime with minimum
content of 70 per cent of CaO, grading with motor grader
and compacting with the road roller at OMC to achieve at
least 98 per cent of the max dry density to form a layer of
sub base as per Technical Specification 402 MORTH.
day
day
day
2.480
10.000
hour
6.000
Unit = cum
Taking output = 300 cum (525 tonnes)
a) Labour
Mate
Mazdoor skilled
Mazdoor
b)
Machinery
Excavator 0.90 cum bucket capacity
Tipper for carriage of soil
Tipper 5.5 cum 4 trips per hour
Motor Grader 110 HP @ 50 cum per hour
Vibratory roller 8 - 10 tonne
Tractor with Rotavator and blade @ 25 cum per hour
t.km
hour
hour
hour
hour
hour
14.00
6.000
6.000
12.000
12.000
tonne
KL
15.750
72.000
day
day
1.100
0.700
cum
hour
0.100
0.016
cum
1.100
cum
cum
kl
0.270
0.220
0.1
day
day
day
2.48
10.00
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
c)
RBR-SBBS-5
Unit = cum
Taking output = 1 cum
a) Labour
Men Mazdoor for conveyance & packing
Women Mazdoor
b) Machinery
RBR-SBBS-6
Unit = cum
Taking output = 300 cum (525 t)
For 4 per cent quantity of cement by weight of soil
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
323
RBR-SBBS
Index-code
S. No
Description
Unit
Quantity
b) Machinery
Hydraulic Excavator 0.90 cum bucket capacity
Tipper 5.5 cum
Motor grader 110 HP @ 50 cum per hour
hour
hour
hour
5.00
14.00
6.00
hour
4.30
hour
hour
6.00
12.00
5.00
21.00
kl
Water
d&e) Overheads & Contractors Profit
Cost for 300 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/300
Cost for 300 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/300
Note : The exact quantity of cement shall be as per design.
30.00
OR
vibratory roller 80-100 kN @ 60 cum per hour
Tractor with rotavator and blade @ 25 cum per hour
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
Unit = cum
Taking output = 300 cum (600 tonnes)
Quantity of cement assumed as 4 per cent of
quantity of crushed rock by weight.
a) Labour
day
Mate
day
Mazdoor skilled
day
Mazdoor
b)
Machinery
hour
Motor Grader 110 HP @ 50 cum per hour
hour
Vibratory roller 8 - 10 tonne
Tractor with Rotavator and blade @ 25 cum per hour hour
hour
Water tanker 6 KL capacity
c)
Material
tonne
Cement at site @ 4 per cent by weight of crushed
aggregate (600 tonne)
Grading of material for sub-base course
37.5 mm to 9.5 mm @ 55 per cent
9.5 mm to 4.75 mm @ 20 per cent
4.75 mm to 75 micron @ 25 per cent
Cost of water
2.48
10.00
6.00
6.00
12.00
10.00
24.00
cum
cum
cum
KL
211.20
76.80
96.00
60.00
cum
cum
cum
KL
124.80
19.20
240.00
60.00
or
Grading of material for Base course
37.5 mm to 9.5 mm @ 32.5 per cent
9.5 mm to 4.75 mm @ 5 per cent
4.75 mm to 75 micron @ 62.5 per cent
Cost of water
(i) For Sub-Base course
d&e) Overheads & Contractors Profit
Cost for 300 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/300
(ii) For Base course
d&e) Overheads & Contractors Profit
Cost for 300 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/300
Note : Quantities of aggregates provided under 'c' above are
uncompacted quantities.
324
RBR-SBBS
Index-code
RBR-SBBS-7
S. No
Description
Unit
Quantity
day
day
2.08
hour
0.20
day
day
4.16
hour
0.40
day
day
day
2.92
21.00
hour
hour
hour
6.00
6.00
18.00
cum
720.00
KL
108.00
day
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
Making 50 mm x 50 mm Furrows
Making 50 mm x 50 mm furrows, 25mm/ 50mm deep, 450 to the
center line of the road and at one metre interval in the existing
thin bituminous wearing coarse including sweeping and disposal
of excavated material within 1000 metres lead as per Technical
Specification 404.3.1 MORTH.
Unit = sqm
Taking output = 30 m x 7 m = 210 sqm
(i) 25mm deep furrow cutting
a)
Labour
Mate
Mazdoor
b)
Machinery
Tractor-trolley
c&d) Overheads & Contractors Profit
Cost for 210 sqm= a+b+c+d
Rate per sqm =(a+b+c+d)/210
(ii) 50mm deep furrow cutting
a) Labour
Mate
Mazdoor
b)
Machinery
Tractor-trolley
c&d) Overheads & Contractors Profit
Cost for 210 sqm= a+b+c+d
Rate per sqm =(a+b+c+d)/210
RBR-SBBS-8
Inverted Choke
Construction of inverted choke by providing, laying, spreading
and compacting screening B type/ coarse sand of specified
grade in uniform layer on a prepared surface with motor grader
and compacting with power roller etc as per Technical
Specification 404.3.2 MORTH.
RBR-SBBS-9
Unit = cum
Taking output = 600 cum
a) Labour
Mate
Mazdoor skilled
Mazdoor
b)
Machinery
Motor Grader 110 HP
Vibratory roller 8-10 tonnes @ 60 cum per hour
Water tanker 6 KL capacity
c)
Material
Screening type 'B' or coarse sand
Cost of water
d&e) Overheads & Contractors Profit
Cost for 600 cum = a+b+c+d+e
Rate per cum = ( a+b+c+d+e)/600
Water Bound Macadam Sub-base/base
A With stone screening / binding materials
I WBM Grading 1
(i) Providing, laying, spreading and compacting stone
aggregates of specific sizes to water bound macadam
specification including spreading in uniform thickness, hand
packing, rolling with three wheel 80 -100 kN static roller in
stages to proper grade and camber, applying and brooming,
stone screening/binding materials to fill-up the interstices of
coarse aggregate, watering and compacting to the required
density Grading 1 as per Technical Specification Clause 404
MORTH & 405 MORD. For compacted thickness of 100 mm.
325
RBR-SBBS
Index-code
S. No
Description
Unit
Quantity
3
day
day
4
12.08
250.00
Three wheel 80-100 kN static roller @ 10 cum per hour for Rural
Area works
(OR)
Three wheel 80-100 kN static roller @ 30 cum per hour for R&B
& Urban Works
(OR)
hour
36.00
hour
12.00
hour
6.00
hour
24.00
cum
435.60
cum
97.20
cum
28.80
kl
144.00
day
day
day
2.68
15.00
Mazdoor (Skilled)
Mazdoor (Unskilled)
b) Machinery
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
Aggregate
Grading 1 90 mm to 45 mm @ 1.21 cum per 10 sqm for
compacted thickness of 100 mm
Stone Screenings
Type A 13.2 mm for Grading-1 @ 0.27 cum per 10sqm
Binding Material
Binding Material @ 0.08 cum per 10 sqm for grading 1 material
Water
d&e) Overheads & Contractors Profit
Cost for 360 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/360
Cost for 360 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/360
By Mechanical Means
Unit = cum
Taking output = 360 cum
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b) Machinery
Motor grader 110 HP @ 50 cum per hour for spreading
hour
7.20
Three wheel 80-100 kN static roller @ 10 cum per hour for Rural
Area works
(OR)
Three wheel 80-100 kN static roller @ 30 cum per hour for R&B
& Urban Works
(OR)
hour
36.00
hour
12.00
hour
hour
6.00
24.00
cum
435.60
cum
97.20
cum
28.80
kl
144.00
Binding Material
Binding Material @ 0.08 cum per 10 sqm for Grading 2 material
Water
d&e) Overheads & Contractors Profit
Cost for 360 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/360
Cost for 360 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/360
326
RBR-SBBS
Index-code
S. No
Description
Unit
Quantity
day
day
day
12.08
250.00
Three wheel 80-100 kN static roller @ 10 cum per hour for Rural
Area works
(OR)
hour
36.00
Three wheel 80-100 kN static roller @ 30 cum per hour for R&B
& Urban Works
hour
12.00
II
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
WBM Grading 2
By Manual Means
Unit = cum
Taking output = 360 cum
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b) Machinery
(OR)
Vibratory roller 8-10 tonnes @ 60 cum per hour
Water tanker 6 kl capacity
c) Material (Refer Tables 400.7, 8, 9 and 10 MORD/
400.6, 7, 8 & 9 MORTH)
Aggregate
Grading 2 63 mm to 45 mm @ 0.91 cum per 10 sqm for
compacted thickness of 75 mm
Stone Screening
Type B 11.2 mm for Grading 2 @ 0.18 / 0.20 cum/10sqm
(OR)
Type B 13.2 mm for Grading 2 @ 0.12 cum per 10sqm
Binding Material
Binding Material @ 0.06 cum per 10 sqm for Grading 2
material
Water
d&e) Overheads & Contractors Profit
Using 11.2 mm for Grading 2 :
Cost for 360 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/360
Cost for 360 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/360
Using 13.2 mm for Grading 2
Cost for 360 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/360
Cost for 360 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/360
By Mechanical Means
Unit = cum
Taking output = 360 cum
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
hour
6.00
hour
24.00
cum
435.60
cum
86.40
cum
57.60
cum
28.80
kl
144.00
day
day
day
2.68
15.00
327
RBR-SBBS
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
b) Machinery
Motor grader 110 HP @ 50 cum per hour for spreading
hour
7.20
Three wheel 80-100 kN static roller @ 10 cum per hour for Rural
Area works
(OR)
Three wheel 80-100 kN static roller @ 30 cum per hour for R&B
& Urban Works
hour
36.00
hour
12.00
(OR)
Vibratory roller 8-10 tonnes @ 60 cum per hour
Water tanker 6 kl capacity
c) Material (Refer Tables 400.7, 8, 9 & 10 MORD/
400.6, 7, 8 & 9 MORTH)
Aggregate
Grading 2 63 mm to 45 mm @ 0.91 cum per 10 sqm for
compacted thickness of 75 mm
Stone Screening
Type B 11.2 mm for Grading 2 @ 0.20 cum per 10sqm
(OR)
Type B 13.2 mm for Grading 2 @ 0.12 cum per 10sqm
Binding Material
Binding Material @ 0.06 cum per 10 sqm for Grading 2
material
Water
d&e) Overheads & Contractors Profit
Using 11.2 mm for Grading 2 :
Cost for 360 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/360
hour
6.00
hour
24.00
cum
435.60
cum
86.40
cum
57.60
cum
28.80
kl
144.00
day
day
day
12.08
250.00
hour
36.00
hour
12.00
hour
hour
6.00
24.00
By Manual Means
Unit = cum
Taking output = 360 cum
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b) Machinery
Three wheel 80-100 kN static roller @ 10 cum per hour for Rural
Area works
(OR)
Three wheel 80-100 kN static roller @ 30 cum per hour for R&B
& Urban Works
(OR)
Vibratory roller 8-10 tonnes @ 60 cum per hour
Water tanker 6 kl capacity
328
RBR-SBBS
Index-code
S. No
Description
Unit
Quantity
cum
435.60
cum
86.40
cum
28.80
kl
144.00
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
hour
36.00
Three wheel 80-100 kN static roller @ 30 cum per hour for R&B
& Urban Works
hour
12.00
(OR)
Vibratory roller 8-10 tonnes @ 60 cum per hour
Water tanker 6 kl capacity
c) Material (Refer Tables 400.7, 8, 9 & 10 MORD/
400.6, 7, 8 & 9 MORTH)
Aggregate
Grading 3 53 mm to 22.4 mm @ 0.91 cum per 10 sqm
for compacted thickness of 75 mm
Stone Screening
Type B 11.2 mm for Grading 3 @ 0.18 cum per 10sqm
Binding Material
Binding Material @ 0.06 cum per 10 sqm for Grading 2
material
Water
d&e) Overheads & Contractors Profit
Cost for 360 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/360
Cost for 360 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/360
hour
6.00
hour
24.00
cum
435.60
cum
86.40
cum
28.80
kl
144.00
329
RBR-SBBS
Index-code
RBR-SBBS-10
S. No
Description
Unit
Quantity
day
day
day
12.08
250.00
hour
36.00
hour
12.00
hour
hour
6.00
24.00
cum
435.60
cum
108.00
cum
28.80
kl
144.00
day
day
day
2.68
15.00
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
I
(i) Providing, laying, spreading and compacting stone aggregates
of specific sizes to water bound macadam specification including
spreading in uniform thickness, hand packing, rolling with three
wheel 80-100 kN static roller / Vibratory Roller 80-100 kN in
stages to proper grade and camber, applying and brooming,
crushable screening to fill-up the interstices of coarse aggregate,
watering and compacting to the required density Grading 1 as
per Technical Specification Clause 405 MORD / 404 MORTH.
(OR)
vibratory roller 80-100 kN @ 60 cum per hour
Water tanker 6 kl capacity
c) Material (Refer Tables 400.7, 8, 9 & 10 MORD/
400.6, 7, 8 & 9 MORTH)
Aggregate
Grading 1 90 mm to 45 mm @ 1.21 cum per 10 sqm
for compacted thickness of 100 mm
Crushable type such as moorum or Gravel for grading 1
@ 0.30 cum per 10 sqm
Binding Material
Binding Material @ 0.06 cum per 10 sqm for Grading 1
material (for R&B & Urban Works Only)
Water
d&e) Overheads & Contractors Profit
Cost for 360 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/360
Cost for 360 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/360
(B) By Mechanical Means
Unit = cum
Taking output = 360 cum
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b) Machinery
Motor grader 110 HP @ 50 cum per hour for spreading
Three wheel 80-100 kN static roller @ 10 cum per hour for Rural
Area works
(OR)
Three wheel 80-100 kN static roller @ 30 cum per hour for R&B
& Urban Works
(OR)
vibratory roller 80-100 kN @ 60 cum per hour
Water tanker 6 kl capacity
hour
7.20
hour
36.00
hour
12.00
hour
hour
6.00
24.00
330
RBR-SBBS
Index-code
S. No
Description
Unit
Quantity
cum
435.60
cum
108.00
cum
28.80
kl
144.00
day
day
day
12.08
250.00
hour
36.00
hour
hour
6.00
24.00
cum
435.60
cum
108.00
kl
144.00
day
day
day
2.68
15.00
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
hour
7.20
hour
36.00
hour
hour
6.00
24.00
331
RBR-SBBS
Index-code
S. No
Description
Unit
Quantity
cum
435.60
cum
108.00
kl
144.00
day
day
day
12.08
250.00
hour
36.00
hour
12.00
hour
hour
6.00
24.00
cum
435.60
cum
105.59
cum
28.80
kl
144.00
day
day
day
2.68
15.00
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
(OR)
332
RBR-SBBS
Index-code
S. No
Description
Unit
Quantity
b) Machinery
Motor grader 110 HP @ 50 cum per hour for spreading
hour
7.20
Three wheel 80-100 kN static roller @ 10 cum per hour for Rural
Area works
(OR)
hour
36.00
Three wheel 80-100 kN static roller @ 30 cum per hour for R&B
& Urban Works
(OR)
hour
12.00
hour
hour
6.00
24.00
cum
435.60
cum
105.59
cum
28.80
kl
144.00
day
day
day
12.08
250.00
Three wheel 80-100 kN static roller @ 10 cum per hour for Rural
Area works
(OR)
Three wheel 80-100 kN static roller @ 30 cum per hour for R&B
& Urban Works
(OR)
hour
36.00
hour
12.00
hour
hour
6.00
24.00
cum
435.60
cum
105.59
kl
144.00
Water
d&e) Overheads & Contractors Profit
Cost for 360 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/360
Cost for 360 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/360
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
333
RBR-SBBS
Index-code
S. No
Description
Unit
Quantity
day
day
day
2.68
15.00
III
hour
7.20
Three wheel 80-100 kN static roller @ 10 cum per hour for Rural
Area works
(OR)
hour
36.00
Three wheel 80-100 kN static roller @ 30 cum per hour for R&B
& Urban Works
(OR)
hour
12.00
hour
hour
6.00
24.00
cum
435.60
cum
105.59
kl
144.00
day
day
day
12.08
250.00
Three wheel 80-100 kN static roller @ 10 cum per hour for Rural
Area works
(OR)
hour
36.00
Three wheel 80-100 kN static roller @ 30 cum per hour for R&B
& Urban Works
hour
12.00
hour
hour
6.00
24.00
cum
435.60
cum
105.59
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
(OR)
334
RBR-SBBS
Index-code
S. No
Description
Unit
Quantity
Binding Material
Binding Material @ 0.06 cum per 10 sqm for Grading 2
material (for R&B & Urban Works Only)
cum
28.80
kl
144.00
day
day
day
2.68
15.00
Water
d&e) Overheads & Contractors Profit
Cost for 360 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/360
Cost for 360 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/360
(B) By Mechanical Means
Unit = cum
Taking output = 360 cum
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b) Machinery
Motor grader 110 HP @ 50 cum per hour for spreading
Three wheel 80-100 kN static roller @ 10 cum per hour
for Rural Area works
hour
7.20
hour
36.00
hour
12.00
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
(OR)
hour
vibratory roller 80-100 kN @ 60 cum per hour
hour
Water tanker 6 kl capacity
c) Material (Refer Tables 400.7, 8, 9 & 10 MORD/
400.6, 7, 8 & 9 MORTH)
Aggregate
cum
Grading 3 53 mm to 22.4 mm @ 0.91 cum per 10 sqm
for compacted thickness of 75 mm
cum
Crushable type such as Moorum or gravel for Grading 3
@ 0.22 cum per 10 sqm
Binding Material
Binding Material @ 0.06 cum per 10 sqm for Grading 2 cum
material (for R&B & Urban Works Only)
kl
Water
d&e) Overheads & Contractors Profit
Cost for 360 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/360
Cost for 360 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/360
Note : Whenever BT is taken up simultaneously binding material
can be deleted
(ii) WBM Grading 3 (using Single Grade Metal)
6.00
24.00
435.60
105.59
28.80
144.00
day
day
day
12.08
250.00
335
RBR-SBBS
Index-code
S. No
Description
Unit
Quantity
hour
36.00
hour
hour
6.00
24.00
cum
435.60
cum
105.59
kl
144.00
day
day
day
2.68
15.00
b) Machinery
Three wheel 80-100 kN static roller @ 10 cum/ hour
or
vibratory roller 80-100 kN @ 60 cum per hour
Water tanker 6 kl capacity
c) Material (Refer Tables 400.7, 8, 9 and 10)
Aggregate
Grading 3 Hand broken stone aggregate 40 mm
nominal size @ 0.91 cum per 10 sqm for compacted
thickness of 75 mm
Crushable type such as Moorum or gravel for Grading 3 @ 0.22
cum per 10 sqm
Water
d&e) Overheads & Contractors Profit
Cost for 360 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/360
Cost for 360 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/360
(B) By Mechanical Means
Unit = cum
Taking output = 360 cum
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b) Machinery
RBR-SBBS-11
hour
7.20
hour
36.00
hour
hour
6.00
24.00
cum
435.60
cum
105.59
kl
144.00
day
day
day
8.00
2.40
Water
d&e) Overheads & Contractors Profit
Cost for 360 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/360
Cost for 360 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/360
Wet Mix Macadam
10
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
336
RBR-SBBS
Index-code
S. No
Description
Unit
Quantity
b) Machinery
Front end loader 1 cum capacity
Wet mix plant (Pug Mill)
Tipper/Dumper (10-t) capacity / 5-6 t capacity
Motor Grader @ 50 cum per hour
Water tanker 6 kl capacity
Three wheel 80-100 kN static roller @ 16cum per hour
(or)
hour
hour
hour
hour
hour
hour
4.00
4.00
5.00
2.00
1.33
6.25
hour
1.67
cum
cum
cum
39.90
53.20
39.90
Fine aggregate 10 mm
cum
Coarse Sand
Borrow area sand
Water
d&e) Overheads & Contractors Profit
Cost for 100 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/100
Cost for 100 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/100
B R&B and Urban Area Works :
Unit = cum
Taking output = 225 cum (495 tonnes)
a) Labour
Mate
Mazdoor skilled
Mazdoor
b)
Machinery
Wet mix plant of 75 tonne hourly capacity
Electric generator 125 KVA
Front end loader 1 cum capacity
Paver finisher
Vibratory roller 8 - 10 tonne
or
Smooth 3 wheeled steel roller @ 8-10 tonnes.
Water tanker 6 KL capacity
Tipper 10t
c)
Material ( Table 400-11)
45 mm to 22.4 mm@ 30 per cent
22.4 mm to 2.36 mm @ 40 per cent
2.36 mm to 75 micron@ 30 per cent
Cost of water
d&e) Overheads & Contractors Profit
Cost for 225 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/225
Cost for 225 cum = a+b+c+d+e (Smooth Roller)
Rate per cum = (a+b+c+d+e)/225
cum
cum
kl
8.00
day
day
day
2.48
10.00
hour
hour
hour
hour
hour
9.00
6.00
6.00
6.00
3.90
hour
hour
t.km
22.50
3.00
495 x L
cum
89.10
cum
cum
KL
118.80
89.10
18.00
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
337
RBR-SBBS
Index-code
S. No
Description
Unit
Quantity
2
Granular sub-base/base/surface course with local materials
(Table 400.13) by mix in place method normal Construction
of granular sub-base by providing local material spreading
in uniform layers with motor grader on prepared surface,
mixing by mix in place method with rotavator at once and
compacting with smooth wheel roller to achieve the
desired density complete as per Clause 401.4 as per
Technical Specification Clause 408 MORD.
day
day
day
2.48
10.00
hour
hour
hour
hour
6.00
30.00
12.00
5.00
cum
384.00
Water
d&e) Overheads & Contractors Profit
Cost for 300 cum = a+b+c+d+e
Rate per cum = a+b+c+d+e/300
Using Gravel mix soil using Soil Gravel Mixture /
quarry waste
Unit = cum
Taking output = 300 cum
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b) Machinery
Motor grader 110 HP 50 cum per hour
kl
30.00
day
day
day
2.40
8.00
hour
hour
hour
hour
6.00
30.00
5.00
12.00
cum
384.00
kl
30.00
11
RBR-SBBS-12
ii
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
338
RBR-SBBS
Index-code
RBR-SBBS-13
S. No
Description
Unit
Quantity
day
day
day
2.68
15.00
hour
hour
hour
7.20
36.00
24.00
cum
435.60
kl
144.00
day
day
day
12.08
250.00
hour
36.00
hour
24.00
cum
435.60
kl
144.00
12
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
By Mechanical Means
Unit = cum
Taking output = 360 cum
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b) Machinery
Motor grader 110 H.P @ 50 cum/hr for spreading
Three wheel 80-100 kN @ static roller 8 cum per hour
Water
d&e) Overheads & Contractors Profit
Cost for 360 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/360
B By Manual Means
Unit = cum
Taking output = 360 cum
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b) Machinery
Water
d&e) Overheads & Contractors Profit
Cost for 360 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/360
RBR-SBBS-14
13
Unit = cum
Taking output = 480 cum (720 t, density 1.50 t/cum)
339
RBR-SBBS
Index-code
S. No
Description
Unit
Quantity
day
day
day
1.24
6.00
hour
6.00
hour
hour
hour
16.00
5.50
3.80
cum
cum
480.00
480.00
-
hour
hour
6.00
3.20
hour
hour
hour
12.00
6.00
12.00
t
cum
kl
29.00
360.00
72.00
Assumptions made
Total mass taken for analysis = 720 t
Lime+Flyash admixture
@ 20% = 0.2 x 720=144 t
Soil = 720-144 = 576 t
(578/1.6 = 360 cum)
Lime + Flyash = 144 t
Ratio Lime 4 : Flyash 16
Lime = 29 t
Flyash = 115 t
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b) Machinery
Hydraulic Excavator 0.90 cum bucket capacity @ 60 cum
per hour for 360 cum soil
Tipper 10 t capacity for carriage of soil 578 t
Tipper 10 t capacity for carriage of 115 t flyash
Tipper 10 t capacity for carriage of 29 t of lime from
store to work site
Loading as per item 1.1 (ii)
Unloading as per item 1.1 (iv)
Add 10 per cent of cost of carriage to cover cost of
loading and unloading
Tractor with disc harrows for pulverisation
Motor Grader 110 HP @ 75 per cent 200 cum per hour
for mixing in-place and grading
Three wheel 80-100 kN static roller (or)
vibratory roller 80-100 kN @ 60 cum per hour
Water tanker 6 kl capacity
c) Material
Lime (Slaked)
Compensation for earth taken from private source
Water
d&e) Overheads & Contractors Profit
Cost for 480 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/480
Cost for 480 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/480
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
Note : 1. Compensation for earth will vary from place to place and will
have to be assessed realistically as per particular ground situation. In
case earth is available from Govt. land, compensation for earth will not be
required. The position is required to be clearly stated in the cost
estimate.
2. Cost of flyash has not been considered as same will be available free
of cost. Only carriage of flyash has been provided.
3. Lime + Flyash has been taken as 20 per cent of total mass and ratio of
lime and flyash as 1:4 for estimating purposes. Total quantities will be as
per approved design.
RBR-SBBS-15
14
day
day
day
2.48
10.00
340
RBR-SBBS
Index-code
S. No
Description
Unit
Quantity
hour
hour
6.00
30.00
hour
hour
12.00
5.00
cum
kl
384.00
30.00
day
day
day
12.08
250.00
hour
36.00
hour
24.00
cum
cum
kl
435.60
108.00
144.00
day
day
day
2.48
10.00
hour
15.00
hour
hour
6.00
4.30
hour
12.00
hour
7.00
b) Machinery
Motor Grader 110 HP @ 50 cum per hour
Three wheel 80-100 kN static roller @ 10 cum /hour
Tractor with Rotavator 25 cum per hour
Water tanker 6 kl capacity
c) Material
Crushed slag as per Clause 410.4.2 (i)
As per Item No.4.2 of Chapter 4
Water
d&e) Overheads & Contractors Profit
Cost for 300 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/300
RBR-SBBS-16
15
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
Unit = cum
Taking output = 360 cum
Manual Means
RBR-SBBS-17
16
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b) Machinery
Three wheel 80-100 kN static roller @ 10 cum/ hour
Water tanker 6 kl capacity
c) Material
As per Item No.4.7 (1)(A) of Chapter 4
Crushed slag as per Clause 410.4.2 (ii)
Crushable screening (Murram / Gravel)
Water
d&e) Overheads & Contractors Profit
Cost for 360 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/360
Cement Bound Granular Material sub-base/base
Providing laying and spreading granulated blast furnace slag on
a prepared sub-grade pulverising adding the designed quantity
of cement to the spread granulated blast furnace slag mixing in
place with rotavator grading with the mortar grader and
compacting with smooth wheel roller 80-100 kN at OMC to
achieve the desired unconfined compressive strength and to
form a layer of sub-base/base as per Technical Specification
Clauses 404.3 and 410.4.2 MORD
Unit = cum
Taking output = 300 cum (525 t)
For 4 per cent quantity of cement by wt of granulated
blast furnace slag
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b) Machinery
5.50 cum Tipper for carriage of GBFS add 10 per cent of
cost of carriage of cover cost of loading and unloading
341
RBR-SBBS
Index-code
RBR-SBBS-18
S. No
Description
Unit
Quantity
c) Material
t
Cement (4%)
kl
Water
d&e) Overheads & Contractors Profit
Cost for 300 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/300
Note : 1. The exact quantity of cement shall be as per design
2. Granulated ballast slag will be available free of cost
Crusher Run Macadam Base
17
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
21.00
42.00
By mix-in-place method
With 53 mm maximum size of aggregates
Unit = cum
Taking output = 360 cum
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b) Machinery
Tractor attached with rotavator @ 25 cum / 30 cum per hour
day
day
day
2.48
10.00
hour
hour
hour
12.00
6.00
36.00
hour
6.00
hour
6.00
cum
cum
cum
kl
157.46
151.06
116.68
36.00
day
day
day
2.48
10.00
hour
hour
hour
hour
12.00
6.00
36.00
6.00
cum
cum
cum
kl
24.12
237.60
213.48
36.00
of
aggregates
342
RBR-SBBS
Index-code
S. No
Description
Unit
Quantity
day
day
day
2.48
10.00
hour
hour
hour
hour
12.00
6.00
6.00
6.00
cum
cum
cum
KL
24.12
237.60
213.48
36.00
day
day
day
1.28
6.00
hour
hour
hour
hour
hour
6.00
6.00
6.00
6.00
22.50
hour
hour
hour
6.00
3.00
10.00
-
cum
cum
cum
kl
98.40
94.41
104.18
18.00
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
Or
iii For 45 mm maximum size of aggregate (MORTH only)
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b) Machinery
Tractor attached with rotavator @ 30 cum per hour
Motor-Grader 110 H.P
vibratory roller 80-100 kN @ 60 cum per hour
Water tanker 6 kl capacity
c) Material
Aggregate at site
45 mm to 22.5 mm@ 5 per cent
22.4 mm to 5.6 mm@ 50 per cent
Below 5.6 mm@ 45 per cent
Cost of water
d&e) Overheads & Contractors Profit
Cost for 360 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/360
B
i
Or
By mixing plant method
With 53 mm maximum size of aggregates
Unit = cum
Taking output = 225 cum (450 t)
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b) Machinery
Wet mix plant @ 75 t per hour
Electric generator set, 125 KVA
Front end loader 1 cum bucket capacity
Motor grader 110 HP
Three wheel roller 80-100 kN @ 8 cum /10 cum /hour
OR
vibratory roller 80-100 kN @ 60 cum per hour
Water tanker
Tipper
Add 10 per cent of cost of carriage to cover cost of
loading and unloading
c) Material
Aggregate at site
For 53 mm maximum size
63 mm to 45 mm @ 33 per cent
22.4 mm to 5.6 mm @ 32 per cent
Below 5.6 mm @ 35 per cent
Water
d&e) Overheads & Contractors Profit
Cost for 225 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/225
Cost for 225 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/225
343
RBR-SBBS
Index-code
S. No
Description
Unit
Quantity
day
day
day
1.28
6.00
hour
hour
hour
hour
hour
hour
hour
6.00
6.00
6.00
6.00
22.50
3.00
10.00
cum
cum
cum
kl
15.06
148.50
133.00
18.00
day
day
day
1.28
6.00
hour
hour
hour
hour
hour
6.00
6.00
6.00
6.00
22.50
hour
hour
t.km
6.00
3.00
-
hour
10.00
cum
cum
cum
KL
15.06
148.50
133.43
18.00
ii
iii
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
344
RBR-SBBS
Index-code
RBR-SBBS-19
S. No
Description
Unit
Quantity
day
day
day
10.52
3.00
hour
hour
1.00
1.00
No.
No.
cum
kl
8160.00
1100.00
5.66
6.00
day
day
53.16
13.00
hour
hour
2.00
1.00
cum
0.174
cum
15.437
Nos
5,168.00
Nos
kl
464.00
6.00
18
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
Brick Soling
Laying brick soling layer on prepared sub-grade with brick on
end edging according to lines, graded and cross-section shown
on the drawing filling joints with sand and earth, spreading 25
mm thick layer of earth over brick soling, watering and rolling the
same with three wheel road roller 80-100 kN as per Technical
Specification Clause 412 MORD
RBR-SBBS-20
19
Unit = sqm
Taking output = 150 sqm
a) Labour
Mate
Mazdoor (Unskilled)
Mason 1st Class
b) Machinery
Three wheel 80-100 kN static roller
Water tanker
c) Material
Brick 1st Class
Brick 1st Class on edging
Fine Sand
Water
d&e) Overheads & Contractors Profit
Cost for 150 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/150
Stone Set Pavement
Providing and laying stone set pavement on prepared surface
with sub-base 100 mm thick compacted Granular Sub-base as
per Clause 401.4 and base 75 mm thick compacted water bound
macadam grading 2 as per Clause 405.3. The 150 mm thick
hammer desired stones are laid in the herring one or stretched
bond pattern. The stones are compacted into the bedding sand
of 40 mm over the WBM base bounded by edge stone using
suitable compacting device. The gaps are filled with fine sand
stone dust as per Technical Specification Clause 413.4 MORD.
Unit = sqm
Taking output = 360 sqm
a) Labour
Mate
Mazdoor (Unskilled)
Mason 2nd class for laying set stone and edge stone
b) Machinery
Three wheel 80-100 kN static roller
Water tanker 6 kl capacity
c) Material
(1) Collection of fine sand
3.4x0.285x0.150x1.20 = 0.174
(2) Coarse sand
96x3.35x0.04x1.20 = 15.437 cum
(3) Collection of stone set stone
300 mmx200 mmx150 mm ; 17x304 = 5168 nos.
(4) Collection of edge stone
450 mmx200 mmx350 mm ; 2x232 = 464 nos.
(5) Water
d&e) Overheads & Contractors Profit
Cost of 360 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/360
345
RBR-SBBS
Index-code
RBR-SBBS-21
S. No
Description
Unit
Quantity
20
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
Unit = cum
Taking output =360 cum
a) Labour
Mate
day
Mazdoor skilled
day
6.16
day
102.00
hour
hour
6.00
6.00
hour
hour
t.km
12.00
6.00
720 x L
hour
12.00
KL
72.00
b)
Machinery
cum
cum
c)
Material
Material available from dismantled concrete slab after
crushing / breaking and only carriage is required to be
provided
Cost of water
d&e) Overheads & Contractors Profit
Cost for 360 cum = a+b+c+d+e (Vibratory Roller)
Rate per cum = (a+b+c+d+e)/360
Cost for 360 cum = a+b+c+d+e (Smooth Roller)
Rate per cum = (a+b+c+d+e)/360
RBR-SBBS-21
21
Unit = sqm
Taking output = 7500 sqm
a) Labour
Mate
Mazdoor skilled
Mazdoor (Unskilled)
b)
Machinery
Mechanical broom hydraulic @ 1250 sqm per hour
Hydraulic self propelled chips spreader
Front end loader 1 cum bucket capacity
Tipper 10 tonne capacity
day
day
day
2.56
12.00
hour
hour
hour
hour
6.00
6.00
6.00
6.00
346
RBR-SBBS
Index-code
S. No
Description
Unit
Quantity
3
hour
hour
4
3.9
4.28
cum
tonne
97.50
0.25
Material
Crushed stone aggregate 11.2 mm size
Bitumen (60-70 grade)
d&e) Overheads & Contractors Profit
Cost for 7500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/7500
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
c)
Note : Though vibratory roller is required only for 3 hours as per norms,
the same is required to be available at site for 6 hours to match with other
machines. The usage rates of vibratory roller may be multiplied with a
factor of 0.65.
RBR-SBBS-22
22
Unit = cum
Taking output =21 cum
a) Labour
Mate
Mazdoor
b)
Machinery
day
day
6.24
hour
1.00
hour
6.00
KL
6.00
Note : This analysis provides for median and island with earthen top. In case the surface is required to
be turfed or planted with shrubs, the same is required to be provided separately as per analysis given in
the chapter on horticulture. In case granular fill is required to be paved, quantities of paving are required
to be calculated as per approved design and paid separately.
RBR-SBBS-23
23
Unit = cum
Taking output = 21 cum
a) Labour
Mate
Mazdoor
b)
Machinery
Water tanker with 5 km lead
Plate Compactor @ 3.5 cum per hour
Hydraulic Excavator1.0 cum bucket capacity @60 cum
per hour
Tipper 10 tonne capacity
Loading Charges
Unloading Charges
c)
Material
Cost of water
d&e) Overheads & Contractors Profit
Cost for 21 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/ 21
day
day
4.16
hour
hour
hour
1.00
6.00
0.50
t.km
52.5 x L
cum
cum
KL
6.00
Note : This analysis provides for median and island with earthen top. In case the surface is required to
be turfed or planted with shrubs, the same is required to be provided separately as per analysis given in
the chapter on horticulture. In case surface finish is of hard type, the same may be provided separately
as per approved design.
Loading & unloading charges for actual quantity to be allowed.
347
RBR-SBBS
Index-code
S. No
Description
Unit
Quantity
day
day
day
4.00
31.36
hour
hour
hour
0.75
2.00
6.00
cum
20.79
cum
cum
26.73
11.88
cum
6.75
cum
tonne
3.38
1.88
cum
tonne
3.84
1.83
each
3300.00
metre
22.50
KL
12.00
RBR-SBBS-24
24
RBR-SBBS-25
25
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
Construction of Shoulders
A. Earthen Shoulders
The rate as applicable for sub-grade construction may be
adopted.
B. Hard Shoulders
Rate as applicable for sub-base and or base may be
adopted as per approved design.
C. Paved shoulders
The rate may be adopted as applicable for different
layers of pavement depending upon approved design of
paved shoulders.
Footpaths and Separators
Construction of footpath/separator by providing a 150 mm
compacted granular sub base as per clause 401 and 25 mm
thick cement concrete grade M15, over laid with pre-cast
concrete tiles in cement mortar 1:3 including provision of all
drainage arrangements but excluding kerb channel (MORTH)
Unit = sqm
Taking output = 300 sqm
a) Labour
Mate
Mason
Mazdoor (Unskilled)
b)
Machinery
Vibratory road roller 8 -10 tonnes @60 cum per hour
General Note : The provisions towards Mate is included in the provision towards
unskilled Mazdoor.
348
RBR-BASC
Chapter - 5
BASES AND SURFACE COURSES (BITUMINOUS)
Index-code
RBR-BASC-1
S. No
Description
1
i
a
Unit Quantity
3
Rate
Rs.
Amount
Rs.
Remarks
Prime Coat
Low porosity
Providing and applying primer coat with bitumen emulsion
(SS-1) on prepared surface of granular base including
cleaning of road surface and spraying primer at the rate of
0.70-1.0 kg/sqm using mechanical means as per Technical
Specification Clause 502 MORD (for use on Wet mix
macadam & WBM)
Unit = sqm
Taking output = 1750 sqm
a) Labour
day
Mate
day
1.040
Mazdoor (Unskilled)
b) Machinery
hour
1.400
Hydraulic broom @ 1250 sqm per hour
hour
1.400
Air compressor 210 cfm
hour
1.000
Bitumen emulsion pressure distributor @ 1750 sqm/hour
hour
0.500
Water tanker 6 kl capacity 1 trip per hour
c) Material
t
1.480
Bitumen emulsion (SS-1) @ 0.85 kg per sqm
kl
3.000
Water
d&e) Overheads & Contractors Profit
Cost of 1750 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/1750
Providing and applying primer coat with bitumen
emulsion (medium setting) on prepared surface of
granular Base including clearing of road surface and
spraying primer at the rate of 0.60 kg/sqm using
mechanical means as per Tech. specification No 502
MORTH.
Unit = sqm
Taking output = 3500 sqm
a) Labour
day
Mate
day
2.080
Mazdoor (Unskilled)
b) Machinery
hour
2.800
Mechanical broom @ 1250 sqm per hour
hour
2.800
Air compressor 250 cfm
hour
2.000
Bitumen pressure distributor @ 1750 sqm per hour
hour
1.000
Water tanker 6 KL capacity @ 1 trip per hour
c) Material
t
2.100
Bitumen emulsion @ 0.6 kg per sqm
KL
6.000
Requirement of Water
d&e) Overheads & Contractors Profit
Cost for 3500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/3500
Note : Bitumen primer has been provided @ 0.60 kg per sqm as per clause 502.8. Payment
shall be made with adjustment, plus or minus, for the variation between this quantity and the
actual quantity approved by the Engineer after the preliminary trials referred to in clause No.
502.4.3.
351
RBR-BASC
Index-code
S. No
Description
2
ii
Unit Quantity
3
Rate
Rs.
Amount
Rs.
Remarks
Medium porosity
Providing and applying primer coat with Bitumen emulsion (SS-1)
(slow setting) on prepared surface of granular base including
cleaning of road surface and spraying primer at the rate of 0.90- 1.2
kg/sqm using mechanical means as per Technical Specification
Clause 502 MORD. (for use on Cement Stebilized Soil.)
Unit = sqm
Taking output = 1750 sqm
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Hydraulic broom @ 1250 sqm per hour
Air compressor 210 cfm
Bitumen emulsion pressure distributor @ 1750 sqm per hour
day
day
2.100
hour
1.400
hour
1.400
hour
1.000
hour
0.500
t
kl
1.830
3.000
Unit = sqm
Taking output = 1750 sqm
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Hydraulic broom @ 1250 sqm per hour
Air compressor 210 cfm
Bitumen emulsion pressure distributor @ 1750 sqm per hour
RBR-BASC-2
2
i
day
day
3.120
hour
1.400
hour
1.400
hour
hour
1.000
0.500
2.360
kl
3.000
day
day
1.040
hour
1.400
hour
hour
1.400
1.000
0.390
Unit = sqm
Taking output = 1750 sqm
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Hydraulic broom @ 1250 sqm per hour
Air compressor 210 cfm
Emulsion pressure distributor @1750 sqm per hour
c) Material
Bitumen emulsion (RS-1) @ 0.225 kg per sqm
d&e) Overheads & Contractors Profit
Cost of 1750 sqm = (a+b+c+d+e)
Rate per sqm = a+b+c+d+e/1750
352
RBR-BASC
Index-code
S. No
Description
Providing and applying tack coat with Bitumen emulsion (RS1) using emulsion distributor at the rate of 0.25 to 0.30 kg
per sqm on the prepared dry and hungry bituminous surface
cleaned with Hydraulic broom as per Technical Specification
Clause 503 MORD.
Unit = sqm
Taking output = 1750 sqm
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Hydraulic broom @ 1250 sqm per hour
Air compressor 210 cfm
Emulsion pressure distributor @1750 sqm per hour
c) Material
Bitumen emulsion (RS-1) @ 0.275 kg per sqm
d&e) Overheads & Contractors Profit
Cost of 1750 sqm = (a+b+c+d+e)
Rate per sqm = a+b+c+d+e/1750
iii Providing and applying tack coat with Bitumen emulsion (RS1) using emulsion distributor at the rate of 0.25 to 0.30 kg
per sqm on the prepared granular surfaces treated with
primer & cleaned with Hydraulic broom as per Technical
Specification Clause 503 MORD.
Unit = sqm
Taking output = 1750 sqm
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Hydraulic broom @ 1250 sqm per hour
Air compressor 210 cfm
Emulsion pressure distributor @1750 sqm per hour
c) Material
Bitumen emulsion (RS-1) @ 0.275 kg per sqm
d&e) Overheads & Contractors Profit
Cost of 1750 sqm = (a+b+c+d+e)
Rate per sqm = a+b+c+d+e/1750
iv Providing and applying tack coat with Bitumen emulsion (RS1) using emulsion pressure distributor at the rate of 0.30 to
0.35 kg per sqm on the prepared non-bituminous surfaces
(cement concrete pavement) cleaned with Hydraulic broom
as per Technical Speciation 503 MORD.
Unit Quantity
3
Rate
Rs.
Amount
Rs.
Remarks
ii
Unit = sqm
Taking output = 1750 sqm
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Hydraulic broom @ 1250 sqm per hour
Air compressor 210 cfm
Emulsion pressure distributor @1750 sqm per hour
c) Material
Bitumen emulsion (RS-1) @ 0.325 kg per sqm
d&e) Overheads & Contractors Profit
Cost of 1750 sqm = (a+b+c+d+e)
Rate per sqm = a+b+c+d+e/1750
day
day
1.040
hour
1.400
hour
hour
1.400
1.000
0.480
day
day
1.040
hour
1.400
hour
1.400
hour
1.000
0.480
day
day
1.040
hour
1.400
hour
hour
1.400
1.000
0.570
Note : 1. An output of 1750 sqm has been considered in case of tack coat
which can be covered by bituminous courses on the same day.
2. The use of cutback bitumen (Medium Curing grade) as per IS:217 shall
be restricted only for sites at sub-zero temperature or for emergency
applications as directed by the Engineer.
353
RBR-BASC
Index-code
S. No
Description
2
Providing and applying tack coat with bitumen emulsion using
emulsion pressure distributor at the rate of 0.20 kg per sqm on
the prepared bituminous/granular surface cleaned with
mechanical broom as per Tech. specification No 503 MORTH
RBR-BASC-3
3
i
Unit Quantity
3
Rate
Rs.
Amount
Rs.
Remarks
Unit = sqm
Taking output = 3500 sqm
a) Labour
day
Mate
day
2.080
Mazdoor (Unskilled)
b) Machinery
hour
2.800
Mechanical broom @ 1250 sqm per hour
hour
2.800
Air compressor 250 cfm
hour
2.000
Emulsion pressure distributor @ 1750 sqm per hour
c) Material
t
0.700
Bitumen emulsion @ 0.2 kg per sqm
d&e) Overheads & Contractors Profit
Cost for 3500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/3500
Note : 1. Bitumen emulsion has been provided @ 0.20 kg per sqm as per clause 503.8.
Payment shall be made with adjustment, plus or minus, for the variation between this quantity
and actual quantity approved by the Engineer after preliminary trials referred to in clause No.
503.4.3
2. An output of 3500 sqm has been considered in case of prime coat and tack coat which can
be covered by bituminous courses on the same day.
Bituminous Macadam
Providing and laying bituminous macadam with 40-60 TPH
hot mix plant using crushed aggregates of grading as per
Table 500.4 premixed with bituminous binder, transported to
site upto a lead of 1000 m laid over a previously prepared
surface with paver finisher to the required grade, level and
alignment and rolled to achieved the desired compaction as
per Technical Specification Clause 504 MORD (using
vibratory Roller 80-100 KN for intermediate rolling and 3
wheel roller 80-100 KN for initial and final rolling).
Unit = cum
Taking output = 102.5 cum (225 t)
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Skilled)
b) Machinery
Batch mix HMP 40-60 THP @ 40 t per hour actual output
Hydraulic broom @ 1250 sqm per hour
Air compressor 210 cfm
Paver finisher
Generator 125 KVA
Front end loader 1 cum bucket capacity
Tipper 5.5 cum, 10 t / 5-6 t capacity
Three wheel 80-100 kN static roller for initial break down
rolling, final and finishing rolling
Vibratory roller 80-100 kN for intermediate rolling
c) Material
(i) Bitumen @ 3.3 per cent of mix
(Weight of mix = 102.5 x 2.2 = 225 t)
(ii) Aggregate
Total weight of mix = 225 t
Weight of bitumen = 7.425 t
Weight of aggregate = 225 7.425 = 217.575 t
Taking density of aggregate = 1.5 t/cum
Volume of aggregate = 145.05 cum
day
day
10.000
day
3.520
hour
hour
6.000
1.100
hour
1.100
hour
6.000
hour
6.000
hour
6.000
hour
6.210
hour
12.000
hour
6.000
7.425
354
RBR-BASC
Index-code
S. No
1
Description
2
Unit Quantity
3
cum
58.020
cum
58.020
cum
29.010
Rate
Rs.
Amount
Rs.
Remarks
Note : 1. Although the rollers are required only for 3 hours as per norms of output, but the same have to
be available at site for six hours as the hot mix plant and paver will take six hours for mixing and paving
the output of 225 t considered in these analysis.
2. Quantity of bitumen has been taken for analysis purpose. The actual quantity will depend upon job mix
formula.
3. Labour for traffic control, watch and ward and other miscellaneous duties at site, including sundries
have been included in administrative overheads of the contractor.
4. In case BM is laid over freshly laid tack coat, provision of Hydraulic broom and 2 mazdoor for the same
shall be deleted as the same has been included in the cost of tack coat.
5. Analysis is based on 1000 m lead of mixed material. Cost of additional cartage may be added as per
site requirements.
ii
14.000
day
5.840
Batch mix HMP 100-120 TPH @ 75 tonne per hour actual output
hour
6.000
hour
hour
hour
hour
hour
hour
hour
hour
12.000
2.200
6.000
6.000
6.000
3.900
3.900
3.900
14.850
cum
cum
cum
cum
43.510
130.550
72.530
43.510
OR
HMP 40-60 TPH @ 17 cum (37.5 Tonnes) / hour
Air compressor 250 cfm
Paver finisher 100 TPH
Generator 250 KVA
Front end loader 1 cum bucket capacity
Smooth wheeled roller 8-10 tonnes for initial break down rolling.
c) Material
i) Bitumen@ 3.3 per cent of mix
weight of mix = 205 x 2.2 = 450 tonne
ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 14.85 tonnes
Weight of aggregate = 450 -14.85 = 435.15 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 290.1 cum
Grading I ( 40 mm nominal size )
37.5 - 25 mm 15 per cent
25 - 10 mm 45 per cent
10 - 5 mm 25 per cent
5 mm and below15 per cent
or
355
RBR-BASC
Index-code
RBR-BASC-4
S. No
Description
Unit Quantity
3
Rate
Rs.
Amount
Rs.
Remarks
356
RBR-BASC
Index-code
S. No
Description
c) Material
Bitumen 30 kg per 10 sqm @ 15 kg per 10 sqm for each
layer (80 / 100 Grade)
Crushed stone coarse aggregate passing 53 mm and
retained on 2.8 mm sieve @ 0.5 cum per 10 sqm for each
layer
Key aggregates passing 22.4 mm and retained on 2.8 mm
sieve @ 0.13 cum per 10 sqm
d&e) Overheads & Contractors Profit
Cost of 800 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/800
(II) Bitumen (S-65)
a) Labour
Mate
Mazdoor (Unskilled)
Chips spreader (Stone Paker)
Bitumen Sprayer
Mazdoor (Semi-Skilled)
b) Machinery
Bitumen boiler oil fired, capacity 1000 litre fitted with spray set
Unit Quantity
3
2.400
cum
80.000
cum
10.400
day
day
106.000
day
10.000
day
2.500
day
25.500
hour
6.000
6.000
hour
Three wheel 80-100 kN static Roller
c) Material
Bitumen 30 kg per 10 sqm @ 15 kg per 10 sqm for each t
layer (60 / 70 Grade)
Crushed stone coarse aggregate passing 53 mm and retained on 2.8 cum
mm sieve @ 0.5 cum per 10 sqm for each layer
Key aggregates passing 22.4 mm and retained on 2.8 mm cum
Amount
Rs.
Remarks
2.400
80.000
10.400
day
day
8.000
day
2.400
hour
6.000
hour
hour
3.430
10.000
hour
22.500
hour
6.000
hour
5.000
9.000
Rate
Rs.
300.000
39.000
357
RBR-BASC
Index-code
RBR-BASC-5
S. No
Description
Unit Quantity
3
day
day
6.000
day
2.320
hour
6.000
hour
2.570
hour
10.000
hour
22.500
hour
6.000
7.870
cum
270.000
cum
81.000
day
day
8.000
day
2.400
hour
6.000
hour
2.570
hour
10.000
hour
33.750
hour
6.000
9.000
cum
405.000
cum
81.000
Rate
Rs.
Amount
Rs.
Remarks
358
RBR-BASC
Index-code
S. No
Description
Unit Quantity
3
Rate
Rs.
Amount
Rs.
Remarks
RBR-BASC-6
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Skilled)
b) Machinery
Hydraulic self propelled chip spreader both for aggregates
and key aggregates @ 1500 sqm per hour for 4500 x 2 sqm
= 9000 sqm
Bitumen pressure distributor for @ 1750 sqm per hour
Tipper 5.5 cum capacity for carriage of aggregates from
stockpile to chip spreader
Three wheel 80-100 kN Static Roller
Front end loader 1 cum bucked capacity
c) Material
Bitumen @ 2 kg per sqm
40 mm size hand broken metal @ 0.09 cum per sqm
12 mm size stone chips @ 0.018 cum per sqm
d&e) Overheads & Contractors Profit
Cost of 4500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/4500
Bituminous Penetration Macadam
Construction of penetration macadam over prepared Base by
providing a layer of compacted crushed coarse aggregate
using chips spreader with alternate applications of
bituminous binder and key aggregates and rolling with a
smooth wheeled steel roller 8-10 tonne capacity to achieve
the desired degree of compaction as per Tech. Specification
No 505 MORTH.
A 50 mm thick
day
day
8.000
day
2.400
hour
6.000
hour
2.570
hour
10.000
hour
33.750
hour
6.000
9.000
cum
405.000
cum
81.000
day
day
6.000
day
Mazdoor skilled
b) Machinery
Hydraulic self propelled chip spreader both for aggregates hour
and key aggregates@ 1500 sqm per hour for 4500 x 2 sqm =
9000 sqm
2.320
Unit = sqm
Taking output = 4500 sqm (225 cum)
a) Labour
Mate
Mazdoor (Unskilled) including for brooming of key aggregates
6.000
hour
2.570
hour
10.000
hour
hour
6.000
6.000
t
cum
22.500
270.000
cum
67.500
chip
359
RBR-BASC
Index-code
S. No
1
Description
2
75 mm thick
Unit = sqm
Taking output = 4500 sqm (337.5 cum compacted).
a) Labour
Mate
Mazdoor (Unskilled) including for brooming of key aggregates
Mazdoor skilled
b) Machinery
Hydraulic self propelled chip spreader both for aggregates
and key aggregates@ 1500 sqm per hour for 4500 x 2 sqm
Bitumen pressure distributor for@ 1750 sqm per hour
Tipper 5.5 cum capacity for carriage of aggregates from
stockpile to chip spreader
Vibratory roller 8 tonnes
Front end loader 1 cum bucket capacity
c) Material
Bitumen@ 6.8 kg per sqm
Crushed stone coarse aggregate (loose passing 63 mm and
retained on 2.8 mm sieve @ 0.09 cum per sqm
RBR-BASC-7
Unit Quantity
3
day
day
8.000
day
2.400
hour
6.000
hour
2.570
hour
10.000
hour
6.000
hour
6.000
t
cum
30.600
405.000
81.000
Rate
Rs.
Amount
Rs.
Remarks
Unit = cum
Taking output = 195 cum (450 tonnes)
a) Labour
Mate
Mazdoor (Unskilled) working with HMP, mechanical broom,
paver, roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction
Skilled mazdoor for checking line & levels
b) Machinery
Batch mix HMP @ 75 tonne per hour
Paver finisher hydrostatic with sensor control @ 75 cum per hour
day
day
16.000
day
5.840
hour
6.000
hour
hour
6.000
6.000
hour
6.000
t.km
450 x L
hour
3.900
hour
3.900
hour
3.900
360
RBR-BASC
Index-code
S. No
1
Description
2
c) Materials
Bitumen @ 4.25 per cent of weight of mix
Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 19.13 tonnes
Weight of aggregate = 450 -19.13 = 430.87 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 287.25 cum
Grading - I 40 mm (Nominal Size)
37.5 - 25 mm 22 per cent
25 - 10 mm 13 per cent
10 -4.75 mm 19 per cent
4.75 mm and below 44 per cent
Filler @ 2 per cent of weight of aggregates (Cement)
or
Grading - II 19 mm (Nominal Size)
25 - 10 mm 30 per cent
10 - 5 mm 28 per cent
5 mm and below 40 per cent
Filler @ 2 per cent of weight of aggregates (Cement).
Any one of the alternative may be adopted as per approved
design
(i) For Grading I ( 40 mm nominal size )
d&e) Overheads & Contractors Profit
Cost for 195 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/195
(ii) For GradingII(19 mm nominal size)
d&e) Overheads & Contractors Profit
Cost for 195 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/195
Unit Quantity
3
19.130
cum
63.190
cum
37.340
cum
54.580
cum
126.390
8.620
cum
86.160
cum
80.430
cum
114.900
8.620
Rate
Rs.
Amount
Rs.
Remarks
Note : 1. Although the roller are required only for 3 hours as per norms of output, but the same have to be
available at site for six hours as the hot mix plant and paver will take six hours for mixing and paving the
output of 450 tonnes considered in this analysis. To cater for the idle period of these rollers, their usage
rates have been multiplied by a factor of 0.65.
2. Quantity of Bitumen has been taken for analysis purpose. The actual quantity will depend upon job mix
formula.
3. Labour for traffic control, watch and ward and other miscellaneous duties at site including sundries have
been included in administrative overheads of the contractor.
4. In case DBM is laid over freshly laid tack coat, provision of mechanical broom and 2 mazdoors shall be
deleted as the same has been included in the cost of tack coat.
5. The individual density for each size of aggregates to be used for construction I.e. 37.5-25 mm, 25-10
mm etc. should be found in the laboratory and accordingly the quantities should be amended for use in
field. The average density of 1.5 tonne/cum is only a reference density in this Data Book.
6. The individual percentage of aggregates should be calculated from the total weight of dry aggregates
i.e.. excluding the weight of bitumen. The weight of filler will also be 2 per cent by weight of dry
aggregates.
RBR-BASC-8
Unit = cum
Taking output = 195 cum (450 tonnes)
a) Labour
day
Mate
Mazdoor (Unskilled) working with HMP, mechanical broom, day
paver, roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction
Skilled mazdoor for checking line & levels
b) Machinery
HMP 40-60 TPH
Paver finisher hydrostatic with sensor control @ 75 cum per
hour
Generator 250 KVA
Front end loader 1 cum bucket capacity
Smooth wheeled roller 8-10 tonnes for initial break rolling. (6
x 0.65)
Vibratory roller 8 tonnes for intermediate rolling.
Finish rolling with 6-8 tonnes smooth wheeled tandem roller
c) Material
Grading I: 13 mm (Nominal Size)
i) Bitumen@ 4.5 per cent of weight of mix
ii) Aggregate
14.000
day
5.840
hour
11.000
hour
6.000
hour
6.000
hour
6.000
hour
3.900
hour
3.900
hour
3.900
20.250
361
RBR-BASC
Index-code
S. No
1
Description
2
Unit Quantity
3
cum
57.300
cum
108.870
cum
114.600
8.620
22.500
OR
Bitumen 60/70 Grade @ 5 per cent of weight of mix
22.500
cum
81.225
cum
81.225
cum
58.425
cum
58.425
cum
5.700
Rate
Rs.
Amount
Rs.
Remarks
362
RBR-BASC
Index-code
S. No
1
Description
2
Unit Quantity
3
Rate
Rs.
Amount
Rs.
Remarks
RBR-BASC-9
Bituminous Concrete
Providing and laying bituminous concrete with 100-120 TPH
batch type hot mix plant producing an average output of 75
tonnes per hour using crushed aggregates of specified
grading, premixed with bituminous binder @ 5.4 to 5.6 per
cent of mix and filler, transporting the hot mix to work site,
laying with a hydrostatic paver finisher with sensor control to
the required grade, level and alignment, rolling with smooth
wheeled, vibratory and tandem rollers to achieve the desired
compaction as per MORTH specification clause No. 509
complete in all respects
Unit = cum
Taking output = 191 cum (450 tonnes)
a) Labour
Mate
Mazdoor (Unskilled) working with HMP, mechanical broom,
paver, roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction
Skilled mazdoor for checking line & levels
b) Machinery
Batch mix HMP @ 75 tonne per hour
Paver finisher hydrostatic with sensor control @ 75 cum per hour
day
day
16.000
day
5.840
hour
6.000
hour
hour
6.000
6.000
6.000
450 x L
hour
hour
3.900
3.900
hour
3.900
22.500
cum
99.750
c) Material
i) Bitumen@ 5 per cent of weight of mix
ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 22.5 tonnes
Weight of aggregate = 450 -22.50 = 427.50 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 285 cum
* Grading - I-19 mm (Nominal Size)
20 - 10 mm 35 per cent
10 - 5 mm 23 per cent
5 mm and below 40 per cent
Filler @ 2 per cent of weight of aggregates.(Cement)
cum
65.550
cum
114.000
8.620
363
RBR-BASC
Index-code
S. No
1
Description
2
Unit Quantity
3
or
Grading - II-13 mm (Nominal Size)
cum
13.2 - 10 mm 30 per cent
cum
10 - 5 mm 25 per cent
cum
5 mm and below43 per cent
t
Filler @ 2 per cent of weight of aggregates.(Cement)
Any one of the alternative may be adopted as per
approved design
(i) for Grading-I ( 19 mm nominal size )
d&e) Overheads & Contractors Profit
Cost for 191 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/191
(ii) For Grading-II(13 mm nominal size)
d&e) Overheads & Contractors Profit
Cost for 191 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/191
Rate
Rs.
Amount
Rs.
Remarks
85.500
71.250
122.550
8.620
Note : 1. Although the rollers are required only for 3 hours as per norms of output, but the same have to
be available at site for six hours as the hot mix plant and paver will take six hours for mixing and paving
the output of 450 tonnes considered in this analysis. To cater for the idle period of these rollers, their
usage rates have been multiplied by a factor of 0.65
2.Quantity of Bitumen has been taken for analysis purpose. The actual quantity will depend upon job mix
formula.
3. Labour for traffic control, watch and ward and other miscellaneous duties at site including sundries have
been included in administrative overheads of the contractor.
4. In case BC is laid over freshly laid tack coat, provision of mechanical broom and 2 mazdoors shall be
deleted as the same has been included in the cost of tack coat.
5. The individual density for each size of aggregates to be used for construction i.e. 37.5-25 mm, 25-10
mm etc. should be found in the laboratory and accordingly the quantities should be amended for use in
field. The average density of 1.5 tonne/cum is only a reference density in this Data Book.
6. The individual percentage of aggregates should be calculated from the total weight of dry aggregates
i.e.. excluding the weight of bitumen. The weight of filler will also be 2 per cent by weight of dry
aggregates.
RBR-BASC-10
10
By Manual Means
Case I: Using Nominal chipping size 13.2 mm
(I) Bitumen (S-90)
Unit = sqm
Taking output = 900 sqm
a) Labour
Mate
Bitumen Sprayer
Mazdoor (Unskilled)
Mazdoor (Semi-Skilled)
b) Machinery
day
day
1.000
day
58.000
day
8.600
hour
2.250
hour
Three wheel 80-100 kN static roller
L.S.
Add: 0.5 per cent of (a) Labour for sundries
c) Material
t
Bitumen (S-90) @ 1.00 kg per sqm
Crushed stone chipping, 13.2 mm nominal size @ 0.010 cum cum
per sqm
d&e) Overheads & Contractors Profit
Cost of 900 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/900
2.250
Bitumen boiler oil fired, capacity 1000 litre fitted with spray set
0.900
9.000
364
RBR-BASC
Index-code
S. No
Description
Unit Quantity
3
Rate
Rs.
Amount
Rs.
Remarks
Unit = sqm
Taking output = 900 sqm
a) Labour
Mate
Bitumen Sprayer
Mazdoor (Unskilled)
Mazdoor (Semi-Skilled)
b) Machinery
Bitumen boiler oil fired, capacity 1000 litre fitted with spray
set
Three wheel 80-100 kN static roller
Add: 0.5 per cent of (a) Labour for sundries
c) Material
Bitumen (S-65) @ 1.00 kg per sqm
Crushed stone chipping, 13.2 mm nominal size @ 0.010 cum
per sqm
d&e) Overheads & Contractors Profit
Cost of 900 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/900
(III) Polymer Modified Bitumen
Unit = sqm
Taking output = 900 sqm
a) Labour
Mate
Bitumen Sprayer
Mazdoor (Unskilled)
Mazdoor (Semi-Skilled)
b) Machinery
Bitumen boiler oil fired, capacity 1000 litre fitted with spray set
day
day
1.000
day
58.000
day
8.600
hour
2.250
hour
2.250
L.S.
t
0.900
cum
9.000
day
day
1.000
day
58.000
day
8.600
hour
2.250
hour
L.S.
2.250
0.900
cum
9.000
day
day
1.000
day
58.000
day
8.600
hour
2.250
hour
2.250
L.S.
t
cum
0.900
9.000
365
RBR-BASC
Index-code
S. No
1
Description
2
(V) Natural Rubber Modified Bitumen
Unit = sqm
Taking output = 900 sqm
a) Labour
Mate
Bitumen Sprayer
Mazdoor (Unskilled)
Mazdoor (Semi-Skilled)
b) Machinery
Bitumen boiler oil fired, capacity 1000 litre fitted with spray
set
Three wheel 80-100 kN static roller
Add: 0.5 per cent of (a) Labour for sundries
c) Material
Natural Rubber Modified Bitumen @ 1.00 kg per sqm
Crushed stone chipping, 13.2 mm nominal size @ 0.010 cum
per sqm
d&e) Overheads & Contractors Profit
Cost of 900 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/900
Case II: Using Nominal chipping size 9.5 mm
Manual Means
(I) Bitumen (S-90)
Unit = sqm
Taking output = 1000 sqm
a) Labour
Mate
Bitumen Sprayer
Mazdoor (Unskilled)
Mazdoor (Semi-Skilled)
b) Machinery
Bitumen boiler oil fired, capacity 1000 litre fitted with spray
set
Three wheel 80-100 kN static roller
c) Material
Bitumen (S-90) @ 0.90 kg per sqm
Crushed stone chipping, 9.5 mm nominal size @ 0.008 cum
per sqm
d&e) Overheads & Contractors Profit
Cost of 1000 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/1000
(II) Bitumen (S-65)
Unit = sqm
Taking output = 1000 sqm
a) Labour
Mate
Bitumen Sprayer
Mazdoor (Unskilled)
Mazdoor (Semi-Skilled)
b) Machinery
Bitumen boiler oil fired, capacity 1000 litre fitted with spray
set
Three wheel 80-100 kN static roller
c) Material
Bitumen (S-65) @ 0.90 kg per sqm
Crushed stone chipping, 9.5 mm nominal size @ 0.008 cum
per sqm
d&e) Overheads & Contractors Profit
Cost of 1000 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/1000
Unit Quantity
3
day
day
1.000
day
58.000
day
8.600
hour
2.250
hour
L.S.
2.250
0.900
cum
9.000
day
day
1.000
day
58.000
day
8.600
hour
2.000
hour
2.000
0.900
cum
8.000
day
day
1.000
day
58.000
day
8.600
hour
2.000
hour
2.000
0.900
cum
8.000
Rate
Rs.
Amount
Rs.
Remarks
366
RBR-BASC
Index-code
S. No
Description
Unit Quantity
3
Rate
Rs.
Amount
Rs.
Remarks
Unit = sqm
Taking output = 1000 sqm
a) Labour
Mate
Bitumen Sprayer
Mazdoor (Unskilled)
Mazdoor (Semi-Skilled)
b) Machinery
Bitumen boiler oil fired, capacity 1000 litre fitted with spray
set
Three wheel 80-100 kN static roller
c) Material
Polymer Modified Bitumen @ 0.90 kg per sqm
Crushed stone chipping, 9.5 mm nominal size @ 0.008 cum
per sqm
d&e) Overheads & Contractors Profit
Cost of 1000 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/1000
day
day
1.000
day
58.000
day
8.600
hour
2.000
hour
2.000
0.900
cum
8.000
Unit = sqm
Taking output = 1000 sqm
a) Labour
Mate
Bitumen Sprayer
Mazdoor (Unskilled)
Mazdoor (Semi-Skilled)
b) Machinery
Bitumen boiler oil fired, capacity 1000 litre fitted with spray
set
Three wheel 80-100 kN static roller
c) Material
Crumb Rubber Modified Bitumen @ 0.90 kg per sqm
Crushed stone chipping, 9.5 mm nominal size @ 0.008 cum
per sqm
d&e) Overheads & Contractors Profit
Cost of 1000 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/1000
day
day
1.000
day
58.000
day
8.600
hour
2.000
hour
2.000
0.900
cum
8.000
Unit = sqm
Taking output = 1000 sqm
a) Labour
Mate
Bitumen Sprayer
Mazdoor (Unskilled)
Mazdoor (Semi-Skilled)
b) Machinery
day
day
1.000
day
58.000
day
8.600
hour
2.000
hour
Three wheel 80-100 kN static roller
c) Material
t
Natural Rubber Modified Bitumen @ 0.90 kg per sqm
Crushed stone chipping, 9.5 mm nominal size @ 0.008 cum cum
per sqm
d&e) Overheads & Contractors Profit
Cost of 1000 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/1000
2.000
Bitumen boiler oil fired, capacity 1000 lt fitted with spray set
0.900
8.000
367
RBR-BASC
Index-code
S. No
Description
Unit Quantity
3
Rate
Rs.
Amount
Rs.
Remarks
By Mechanical Means
Case I: Using Nominal chipping size 13.2 mm
(I) Bitumen (S-90)
Unit = sqm
Taking output = 7500 sqm
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Skilled)
b) Machinery
Hydraulic broom @ 1250 sqm per hour
Air compressor 210 cfm
day
day
9.000
day
2.440
hour
hour
6.000
6.000
hour
6.000
Tipper 5.5 cum - 10 t capacity for carriage of stone chips from hour
stockpile on road side to chip spreader
hour
Front end loader 1 cum bucket capacity
hour
Bitumen pressure distributor
hour
Three wheel 80-100 kN static roller weight
6.000
c) Material
t
Bitumen (S-90) @ 1.00 kg per sqm
Crushed stone chipping, 13.2 mm nominal size @ 0.010 cum cum
per sqm
d&e) Overheads & Contractors Profit
Cost of 7500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/7500
(II) Bitumen (S-65)
Unit = sqm
Taking output = 7500 sqm
a) Labour
day
Mate
day
Mazdoor (Unskilled)
day
Mazdoor (Skilled)
b) Machinery
hour
Hydraulic broom @ 1250 sqm per hour
hour
Air compressor 210 cfm
Hydraulic self propelled chip spreader @ 1500 sqm per hour
hour
Tipper 5.5 cum - 10 t capacity for carriage of stone chips hour
hour
6.000
6.000
18.750
7.500
75.000
9.000
2.440
6.000
6.000
6.000
6.000
6.000
hour
6.000
hour
18.750
7.500
cum
75.000
day
day
9.000
day
2.440
hour
6.000
hour
6.000
hour
6.000
6.000
368
RBR-BASC
Index-code
S. No
Description
Unit Quantity
3
hour
4
6.000
hour
6.000
hour
18.750
7.500
cum
75.000
day
day
9.000
day
2.440
hour
6.000
hour
6.000
hour
6.000
hour
6.000
hour
6.000
hour
6.000
hour
18.750
7.500
cum
75.000
day
day
9.000
day
2.440
hour
6.000
hour
6.000
hour
Tipper 5.5 cum - 10 t capacity for carriage of stone chips hour
6.000
6.000
hour
6.000
hour
18.750
Amount
Rs.
Remarks
6.000
hour
Rate
Rs.
7.500
75.000
369
RBR-BASC
Index-code
S. No
Description
Unit Quantity
3
day
day
9.000
day
2.440
hour
6.000
hour
6.000
hour
Tipper 5.5 cum - 10 t capacity for carriage of stone chips hour
6.000
6.000
hour
Tipper 5.5 cum - 10 t capacity for carriage of stone chips hour
hour
Tipper 5.5 cum - 10 t capacity for carriage of stone chips hour
Rate
Rs.
Amount
Rs.
Remarks
6.000
6.000
15.000
6.750
60.000
9.000
2.440
6.000
6.000
6.000
6.000
6.000
6.000
15.000
6.750
60.000
9.000
2.440
6.000
6.000
6.000
6.000
370
RBR-BASC
Index-code
S. No
Description
Unit Quantity
3
hour
Front end loader 1 cum bucket capacity
hour
Bitumen pressure distributor @ 1750 sqm per hour
hour
Three wheel 80-100 kN static roller weight
c) Material
t
Polymer Modified Bitumen @ 0.90 kg per sqm
Crushed stone chipping, 9.5 mm nominal size @ 0.008 cum cum
per sqm
d&e) Overheads & Contractors Profit
Cost of 7500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/7500
(IV) Crumb Rubber Modified Bitumen
Unit = sqm
Taking output = 7500 sqm
a) Labour
day
Mate
day
Mazdoor (Unskilled)
day
Mazdoor (Skilled)
b) Machinery
hour
Hydraulic broom @ 1250 sqm per hour
hour
Air compressor 210 cfm
Hydraulic self propelled chips spreader @ 1500 sqm per hour
hour
Tipper 5.5 cum - 10 t capacity for carriage of stone chips hour
hour
hour
2.440
6.000
6.000
6.000
6.000
6.000
6.750
60.000
9.000
2.440
6.000
6.000
6.000
6.000
6.000
6.000
hour
15.000
9.000
hour
6.750
6.000
hour
Tipper 5.5 cum - 10 t capacity for carriage of stone chips hour
60.000
15.000
Remarks
6.000
hour
t
Amount
Rs.
15.000
hour
4
6.000
Rate
Rs.
6.750
60.000
371
RBR-BASC
Index-code
S. No
Description
1
11
RBR-BASC-11
Unit Quantity
3
Rate
Rs.
Amount
Rs.
Remarks
day
day
9.000
day
2.440
hour
7.200
hour
7.200
hour
6.000
hour
6.000
hour
6.000
hour
6.000
hour
6.000
10.800
cum
135.000
day
day
9.000
day
2.440
hour
7.200
hour
7.200
hour
6.000
hour
6.000
hour
6.000
hour
6.000
hour
6.000
9.000
cum
90.000
Note : 1. Where the proposed aggregate fails to pass the stripping test, an approved adhesion agent may
be added to the binder as per clause 510.2.4. Alternatively, chips may be pre-coated as per clause
510.2.5
2. Input for the second coat, where required, will be the same as per the Ist coat mentioned above
372
RBR-BASC
Index-code
S. No
1
Description
2
ii
12
Rate
Rs.
Amount
Rs.
Remarks
RBR-BASC-12
Unit Quantity
day
day
9.000
day
2.440
hour
7.200
hour
7.200
hour
6.000
hour
6.000
hour
6.000
hour
6.000
hour
6.000
MT
6.750
MT
6.750
cum
36.000
day
day
1.000
day
60.360
hour
2.250
hour
L.S.
2.250
1.350
cum
9.000
373
RBR-BASC
Index-code
S. No
1
Description
2
day
day
day
1.000
60.360
hour
hour
2.000
2.000
1.400
cum
8.000
day
day
day
9.000
2.440
hour
hour
Hydraulic self propelled chip spreader @ 1500 sqm / hour
hour
Tipper 5.5 cum - 10 t capacity for carriage of stone chips hour
6.000
6.000
6.000
6.000
Unit Quantity
hour
hour
hour
6.000
6.000
18.750
11.250
cum
75.000
day
day
9.000
day
2.440
hour
6.000
hour
6.000
hour
Tipper 5.5 cum - 10 t capacity for carriage of stone chips hour
6.000
6.000
hour
Rate
Rs.
Amount
Rs.
Remarks
6.000
hour
6.000
hour
15.000
10.500
cum
60.000
374
RBR-BASC
Index-code
S. No
1
RBR-BASC-13
13
14
RBR-BASC-14
Description
Unit Quantity
3
Rate
Rs.
Amount
Rs.
Remarks
Pre-coating Chips
Pre-coating of chips with 1 per cent of paving bitumen by
weight of chips in a suitable mixer duly heated to 160 degree
C as per Technical Specification Clause 507.2.5 MORD
Unit = cum
Taking output = 30 cum
(I) Bitumen (S-90)
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Bitumen boiler oil fired, capacity 1000 litre tire
Mixall 6-10 t capacity
c) Material
Bitumen @1 per cent by weight of chips (30x1.6)/100
d&e) Overheads & Contractors Profit
Cost of 30 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/30
(II) Bitumen (S-65)
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Bitumen boiler oil fired, capacity 1000 litre tire
Mixall 6-10 t capacity
c) Material
Bitumen @1 per cent by weight of chips (30x1.6)/100
d&e) Overheads & Contractors Profit
Cost of 30 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/30
i 20mm thick Open-Graded Premix Carpet using
Bituminous (penetration grade/modified bitumen) Binder
day
day
15.600
hour
6.000
hour
6.000
0.480
day
day
15.600
hour
6.000
hour
6.000
0.480
(I)
day
day
21.000
day
7.080
sqm
hour
4.000
hour
hour
4.000
2.000
0.730
13.500
375
RBR-BASC
Index-code
S. No
Description
Unit Quantity
3
Rate
Rs.
Amount
Rs.
Remarks
Unit = sqm
Taking output = 500 sqm (10 cum)
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Semi-Skilled)
b) Machinery
Mixall 6/10 t capacity
Bitumen boiler oil fired 1000 litre capacity fitted with spray set
day
day
21.000
day
7.080
hour
4.000
hour
hour
4.000
2.000
hour
hour
hour
hour
t
0.730
13.500
21.000
7.080
4.000
4.000
2.000
0.730
13.500
21.000
7.080
4.000
4.000
2.000
0.730
13.500
21.000
7.080
376
RBR-BASC
Index-code
S. No
Description
b) Machinery
Mixall 6/10 t capacity
Bitumen boiler oil fired 1000 litre capacity fitted with spray set
Unit Quantity
3
hour
4.000
hour
hour
4.000
2.000
Rate
Rs.
Amount
Rs.
Remarks
0.730
13.500
10.000
3.520
6.000
6.000
6.000
3.640
6.000
16.000
5.840
108.000
10.000
3.520
6.000
6.000
6.000
3.640
6.000
16.000
5.840
108.000
377
RBR-BASC
Index-code
S. No
Description
Unit Quantity
3
Rate
Rs.
Amount
Rs.
Remarks
Unit = sqm
Taking output = 4000 sqm (80 cum)
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Skilled)
b) Machinery
HMP 30/40 t per hour
Electric generator set 125 KVA
Front end loader 1 cum bucket capacity
Tipper 5.5 cum - 10 t capacity
Paver finisher
Three wheel 80-100 kN static roller
c) Material
Polymer Modified Bitumen @ 14.60 kg per 10 sqm
5.840
cum
108.000
day
day
10.000
day
3.520
hour
6.000
hour
6.000
hour
6.000
hour
3.640
hour
6.000
hour
16.000
day
day
10.000
day
3.520
hour
6.000
hour
6.000
hour
6.000
hour
3.640
hour
6.000
hour
16.000
5.840
cum
108.000
day
day
10.000
day
3.520
hour
6.000
hour
6.000
hour
6.000
hour
3.640
hour
6.000
hour
16.000
5.840
cum
108.000
378
RBR-BASC
Index-code
S. No
1
Description
2
ii
RBR-BASC-15
Unit Quantity
3
day
day
18.000
day
2.800
hour
6.000
hour
3.600
1.940
cum
24.300
Rate
Rs.
Amount
Rs.
Remarks
15
Unit = sqm
Taking output = 10250 sqm (205 cum)
Case - I: Mechanical method using Penetration grade
Bitumen and HMP of appropriate capacity not less than
75 tonnes/hour .
a) Labour
day
Mate
Mazdoor (Unskilled) working with HMP, road sweeper, paver and day
roller
day
Skilled mazdoor for checking line & levels
b) Machinery
hour
i) Batch type HMP 75 tonne per hour
hour
ii) Electric Generator Set 250 KVA
hour
iii) Front end loader 1 cum bucket capacity
t.km
iv) Tipper 10 tonne capacity
Add 10 per cent of cost of carriage to cover cost of loading
and unloading
hour
v) Paver finisher hydrostatic with sensor attachment
hour
iv) Smooth wheeled/tandom roller 8-10 tonnes weight
c) Material
Bitumen@ 14.60 kg per 10 sqm
Crushed stone chipping, 13.2 mm to 5.6 mm @ 0.27 cum/ 10 sqm
16.000
5.840
6.000
6.000
6.000
450 x L
6.000
6.000
14.970
cum
276.750
379
RBR-BASC
Index-code
S. No
1
Description
2
ii
Unit Quantity
3
18.000
24.300
cum
Rate
Rs.
Amount
Rs.
Remarks
2.800
6.000
6.000
1.940
RBR-BASC-16
16
Oil fired bitumen boiler 1000 litre capacity fitted with spray set
day
day
21.000
day
8.400
hour
6.000
hour
hour
6.000
6.000
hour
hour
1.100
13.500
21.000
8.400
6.000
6.000
6.000
380
RBR-BASC
Index-code
S. No
Description
Unit Quantity
3
c) Material
t
Bitumen (S-65) @ 22 kg per 10 sqm
Stone crushed aggregates 11.2 mm to 0.09 mm @ 0.27 cum cum
per 10 sqm
d&e) Overheads & Contractors Profit
Cost of 500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/500
(III) Polymer Modified Bitumen
Unit = sqm
Taking output = 500 sqm
a) Labour
day
Mate
day
Mazdoor (Unskilled)
day
Mazdoor (Skilled)
b) Machinery
hour
Mixall 6-10 t capacity
Oil fired bitumen boiler 1000 litre capacity fitted with spray set
hour
hour
hour
hour
hour
hour
Rate
Rs.
Amount
Rs.
Remarks
1.100
13.500
21.000
8.400
6.000
6.000
6.000
1.100
13.500
21.000
8.400
6.000
6.000
6.000
1.100
13.500
21.000
8.400
6.000
6.000
6.000
1.100
13.500
381
RBR-BASC
Index-code
S. No
Description
Type B
(I) Bitumen (S-90)
Unit = sqm
Taking output = 500 sqm
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Skilled)
b) Machinery
Mixall 6-10 t capacity
Unit Quantity
3
day
day
21.000
day
8.400
hour
6.000
hour
6.000
hour
Three wheel 80-100 kN static roller
c) Material
t
Bitumen (S-90) @ 19 kg per 10 sqm
Stone crushed aggregates 13.2 mm to 0.09 mm @ 0.27cum cum
per 10 sqm
d&e) Overheads & Contractors Profit
Cost of 500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/500
(II) Bitumen (S-65)
6.000
Oil fired bitumen boiler 1000 lt capacity fitted with spray set
Unit = sqm
Taking output = 500 sqm
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Skilled)
b) Machinery
Mixall 6-10 t capacity
Oil fired bitumen boiler 1000 lt capacity fitted with spray set
Remarks
0.950
day
21.000
day
8.400
hour
6.000
hour
hour
6.000
6.000
0.950
13.500
day
day
21.000
day
8.400
hour
6.000
hour
6.000
hour
Three wheel 80-100 kN static roller
c) Material
t
Polymer Modified Bitumen @ 19 kg per 10 sqm
Stone crushed aggregates 13.2 mm to 0.09 mm @ 0.27cum cum
per 10 sqm
d&e) Overheads & Contractors Profit
Cost of 500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/500
6.000
Oil fired bitumen boiler 1000 lt capacity fitted with spray set
Amount
Rs.
13.500
day
Rate
Rs.
0.950
13.500
382
RBR-BASC
Index-code
S. No
Description
1
2
(IV) Crumb Rubber Modified Bitumen
Unit = sqm
Taking output = 500 sqm
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Skilled)
b) Machinery
Mixall 6-10 t capacity
Oil fired bitumen boiler 1000 lt capacity fitted with spray set
Unit Quantity
3
day
day
21.000
day
8.400
hour
6.000
hour
hour
6.000
6.000
0.950
cum
13.500
day
day
21.000
day
8.400
hour
6.000
Oil fired bitumen boiler 1000 lt capacity fitted with spray set
hour
6.000
hour
6.000
0.950
cum
13.500
day
day
10.000
day
3.520
hour
6.000
hour
6.000
hour
6.000
hour
3.600
hour
6.000
hour
18.000
8.800
cum
108.000
Rate
Rs.
Amount
Rs.
Remarks
383
RBR-BASC
Index-code
S. No
Description
Unit Quantity
3
Rate
Rs.
Amount
Rs.
Remarks
Unit = sqm
Taking output = 4000 sqm (80 cum)
a) Labour
day
Mate
day
Mazdoor (Unskilled)
day
Mazdoor (Skilled)
b) Machinery
hour
HMP of appropriate capacity
hour
Electric generator set 125 KVA
hour
Front end loader 1 cum bucket capacity
hour
Tipper 5.5 cum - 10 t capacity
hour
Paver finisher
hour
Three wheel 80-100 kN static roller
c) Material
t
Bitumen (S-65) @ 22 kg per 10 sqm
Stone crushed aggregates 11.2 mm to 0.09 mm @ 0.27 cum cum
per 10 sqm
d&e) Overheads & Contractors Profit
Cost of 4000 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/4000
(III) Polymer Modified Bitumen
Unit = sqm
Taking output = 4000 sqm (80 cum)
a) Labour
day
Mate
day
Mazdoor (Unskilled)
day
Mazdoor (Skilled)
b) Machinery
hour
HMP of appropriate capacity
hour
Electric generator set 125 KVA
hour
Front end loader 1 cum bucket capacity
hour
Tipper 5.5 cum - 10 t capacity
hour
Paver finisher
hour
Three wheel 80-100 kN static roller
c) Material
t
Polymer Modified Bitumen @ 22 kg per 10 sqm
Stone crushed aggregates 11.2 mm to 0.09 mm @ 0.27 cum cum
per 10 sqm
d&e) Overheads & Contractors Profit
Cost of 4000 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/4000
(IV) Crumb Rubber Modified Bitumen
Unit = sqm
Taking output = 4000 sqm (80 cum)
a) Labour
day
Mate
day
Mazdoor (Unskilled)
day
Mazdoor (Skilled)
b) Machinery
hour
HMP of appropriate capacity
hour
Electric generator set 125 KVA
hour
Front end loader 1 cum bucket capacity
hour
Tipper 5.5 cum - 10 t capacity
hour
Paver finisher
hour
Three wheel 80-100 kN static roller
c) Material
t
Crumb Rubber Modified Bitumen @ 22 kg per 10 sqm
Stone crushed aggregates 11.2 mm to 0.09 mm @ 0.27 cum cum
per 10 sqm
d&e) Overheads & Contractors Profit
Cost of 4000 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/4000
10.000
3.520
6.000
6.000
6.000
3.600
6.000
18.000
8.800
108.000
10.000
3.520
6.000
6.000
6.000
3.600
6.000
18.000
8.800
108.000
10.000
3.520
6.000
6.000
6.000
3.600
6.000
18.000
8.800
108.000
384
RBR-BASC
Index-code
S. No
1
Description
2
(V) Natural Rubber Modified Bitumen
Unit = sqm
Taking output = 4000 sqm (80 cum)
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Skilled)
b) Machinery
HMP of appropriate capacity
Electric generator set 125 KVA
Front end loader 1 cum bucket capacity
Tipper 5.5 cum - 10 t capacity
Paver finisher
Three wheel 80-100 kN static roller
c) Material
Natural Rubber Modified Bitumen @ 22 kg per 10 sqm
Stone crushed aggregates 11.2 mm to 0.09 mm @ 0.27 cum
per 10 sqm
d&e) Overheads & Contractors Profit
Cost of 4000 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/4000
Type B
(I) Bitumen (S-90)
Unit = sqm
Taking output = 4000 sqm (80 cum)
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Skilled)
b) Machinery
HMP of appropriate capacity
Electric generator set 125 KVA
Front end loader 1 cum bucket capacity
Tipper 5.5 cum - 10 t / 5-6 t capacity
Add 10 per cent of cost of carriage to cover cost of loading
and unloading
Paver finisher
Three wheel 80-100 kN static roller
c) Material
Bitumen (S-90) @ 19 kg per 10 sqm
Stone crushed aggregates 13.2 mm to 0.09 mm @ 0.27 cum
per 10 sqm
d&e) Overheads & Contractors Profit
Cost of 4000 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/4000
(II) Bitumen (S-65)
Unit = sqm
Taking output = 4000 sqm (80 cum)
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Skilled)
b) Machinery
HMP of appropriate capacity
Electric generator set 125 KVA
Tipper 5.5 cum - 10 t capacity
Paver finisher
Three wheel 80-100 kN static roller
Unit Quantity
3
day
day
10.000
day
3.520
hour
6.000
hour
6.000
hour
6.000
hour
3.600
hour
6.000
hour
18.000
8.800
cum
108.000
day
day
10.000
day
3.520
hour
6.000
hour
6.000
hour
6.000
hour
3.600
hour
6.000
hour
18.000
7.600
cum
108.000
day
day
10.000
day
3.520
hour
6.000
hour
6.000
hour
3.600
hour
6.000
hour
18.000
Rate
Rs.
Amount
Rs.
Remarks
385
RBR-BASC
Index-code
S. No
Description
Unit Quantity
3
c) Material
t
Bitumen (S-65) @ 19 kg per 10 sqm
Stone crushed aggregates 13.2 mm to 0.09 mm @ 0.27 cum cum
per 10 sqm
d&e) Overheads & Contractors Profit
Cost of 4000 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/4000
(III) Polymer Modified Bitumen
Unit = sqm
Taking output = 4000 sqm (80 cum)
a) Labour
day
Mate
day
Mazdoor (Unskilled)
day
Mazdoor (Skilled)
b) Machinery
hour
HMP of appropriate capacity
hour
Electric generator set 125 KVA
hour
Tipper 5.5 cum - 10 t capacity
hour
Paver finisher
hour
Three wheel 80-100 kN static roller
c) Material
t
Polymer Modified Bitumen @ 19 kg per 10 sqm
Stone crushed aggregates 13.2 mm to 0.09 mm @ 0.27 cum cum
/10 sqm
d&e) Overheads & Contractors Profit
Cost of 4000 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/4000
(IV) Crumb Rubber Modified Bitumen
Unit = sqm
Taking output = 4000 sqm (80 cum)
a) Labour
day
Mate
day
Mazdoor (Unskilled)
day
Mazdoor (Skilled)
b) Machinery
hour
HMP of appropriate capacity
hour
Electric generator set 125 KVA
hour
Tipper 5.5 cum - 10 t capacity
hour
Paver finisher
hour
Three wheel 80-100 kN static roller
c) Material
t
Crumb Rubber Modified Bitumen @ 19 kg per 10 sqm
Stone crushed aggregates 13.2 mm to 0.09 mm @ 0.27 cum cum
/10 sqm
d&e) Overheads & Contractors Profit
Cost of 4000 sqm = a+b+c+d+e
Rate
Rs.
Amount
Rs.
Remarks
7.600
108.000
10.000
3.520
6.000
6.000
3.600
6.000
18.000
7.600
108.000
10.000
3.520
6.000
6.000
3.600
6.000
18.000
7.600
108.000
Unit = sqm
Taking output = 4000 sqm (80 cum)
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Skilled)
b) Machinery
HMP of appropriate capacity
Electric generator set 125 KVA
Tipper 5.5 cum - 10 t capacity
Paver finisher
Three wheel 80-100 kN static roller
day
day
10.000
day
3.520
hour
6.000
hour
6.000
hour
3.600
hour
6.000
hour
18.000
386
RBR-BASC
Index-code
S. No
Description
Unit Quantity
3
c) Material
t
Natural Rubber Modified Bitumen @ 19 kg per 10 sqm
Stone crushed aggregates 13.2 mm to 0.09 mm @ 0.27 cum cum
/10 sqm
d&e) Overheads & Contractors Profit
Cost of 4000 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/4000
ii
Rate
Rs.
Amount
Rs.
Remarks
7.600
108.000
Type - A
Unit = sqm
Taking output = 10250 sqm (205 cum)
a) Labour
Mate
day
Mazdoor (Unskilled) working with HMP, road sweeper, paver and day
roller
day
Skilled mazdoor for checking line & levels
b) Machinery
i) HMP of appropriate capacity.
ii) Electric Generator Set 250 KVA
iii) Front end loader 1 cum bucket capacity
iv) Tipper 10 tonne capacity
Add 10 per cent of cost of carriage to cover cost of loading
and unloading
v) Paver finisher hydrostatic with sensor attachment
iv) Smooth wheeled8-10 tonnes weight
c) Material
Type - A
* Bitumen@ 22 kg per 10 sqm
Stone crushed aggregates 11.2 mm to 0.09 @ 0.27 cum per
10 sqm
d&e) Overheads & Contractors Profit
Cost for 10250 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/10250
Type - B
Unit = sqm
Taking output = 10250 sqm (205 cum)
a) Labour
Mate
5.840
hour
6.000
hour
6.000
hour
6.000
t.km
450 x L
hour
6.000
hour
6.000
22.500
cum
276.750
day
Mazdoor (Unskilled) working with HMP, road sweeper, paver and day
roller
day
Skilled mazdoor for checking line & levels
b)
16.000
16.000
5.840
Machinery
hour
hour
ii) Electric Generator Set 250 KVA
hour
iii) Front end loader 1 cum bucket capacity
tkm
iv) Tipper 10 tonne capacity
Add 10 per cent of cost of carriage to cover cost of loading
and unloading
hour
v) Paver finisher hydrostatic with sensor attachment
hour
iv) Smooth wheeled8-10 tonnes weight
6.000
6.000
6.000
450 x L
6.000
6.000
387
RBR-BASC
Index-code
RBR-BASC-17
S. No
Description
17
c) Material
Type - B
Bitumen @ 19 kg per 10 sqm
Stone crushed aggregates 13.2 mm to 0.09 mm @ 0.27 cum
per 10 sqm
d&e) Overheads & Contractors Profit
Cost for 10250 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/10250
Seal Coat
i Providing and laying seal coat sealing the voids in a
bituminous surface laid to the specified levels, grade and
cross fall using Type A, Type B and Type C as per Technical
Specification Clause 510 MORD. (using Three wheel 80100 kN static roller)
A By Manual Means
Case - I : Type A
(I) Bitumen (S-90)
Unit = sqm
Taking output = 1100 sqm
a) Labour
Mate
Bitumen Sprayer
Mazdoor (Unskilled)
Mazdoor (Semi-Skilled)
b) Machinery
Bitumen boiler oil fired, capacity 1000 litre fitted with spray
set
Three wheel 80-100 kN static roller
c) Material
Bitumen (S-90) @ 9.80 kg per 10 sqm
Crushed stone chipping of 6.7 mm size 100 per cent passing
11.2 mm sieve and retained on 2.36 mm sieve applied @
0.09 cum per 10 sqm
d&e) Overheads & Contractors Profit
Cost of 1100 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/1100
(II) Bitumen (S-65)
Unit = sqm
Taking output = 1100 sqm
a) Labour
Mate
Bitumen Sprayer
Mazdoor (Unskilled)
Mazdoor (Semi-Skilled)
b) Machinery
Bitumen boiler oil fired, capacity 1000 litre fitted with spray
set
Three wheel 80-100 kN static roller
c) Material
Bitumen (S-65) @ 9.80 kg per 10 sqm
Crushed stone chipping of 6.7 mm size 100 per cent passing
11.2 mm sieve and retained on 2.36 mm sieve applied @
0.09 cum per 10 sqm
d&e) Overheads & Contractors Profit
Cost of 1100 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/1100
Unit Quantity
3
19.480
cum
276.750
day
day
1.000
day
22.000
day
7.150
hour
2.200
hour
2.200
1.078
cum
9.900
day
day
1.000
day
22.000
day
7.150
hour
2.200
hour
2.200
1.078
cum
9.900
Rate
Rs.
Amount
Rs.
Remarks
388
RBR-BASC
Index-code
S. No
Description
Unit Quantity
3
Rate
Rs.
Amount
Rs.
Remarks
Unit = sqm
Taking output = 1100 sqm
a) Labour
Mate
Bitumen Sprayer
Mazdoor (Unskilled)
Mazdoor (Semi-Skilled)
b) Machinery
Bitumen boiler oil fired, capacity 1000 litre fitted with spray
set
Three wheel 80-100 kN static roller
c) Material
Polymer Modified Bitumen @ 9.80 kg per 10 sqm
Crushed stone chipping of 6.7 mm size 100 per cent passing
11.2 mm sieve and retained on 2.36 mm sieve applied @
0.09 cum per 10 sqm
d&e) Overheads & Contractors Profit
Cost of 1100 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/1100
(IV) Crumb Rubber Modified Bitumen
Unit = sqm
Taking output = 1100 sqm
a) Labour
Mate
Bitumen Sprayer
Mazdoor (Unskilled)
Mazdoor (Semi-Skilled)
b) Machinery
Bitumen boiler oil fired, capacity 1000 litre / 245 kg fitted with
spray set
Three wheel 80-100 kN static roller
c) Material
Crumb Rubber Modified Bitumen @ 9.80 kg per 10 sqm
Crushed stone chipping of 6.7 mm size 100 per cent passing
11.2 mm sieve and retained on 2.36 mm sieve applied @
0.09 cum per 10 sqm
d&e) Overheads & Contractors Profit
Cost of 1100 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/1100
(V) Natural Rubber Modified Bitumen
Unit = sqm
Taking output = 1100 sqm
a) Labour
Mate
Bitumen Sprayer
Mazdoor (Unskilled)
Mazdoor (Semi-Skilled)
b) Machinery
Bitumen boiler oil fired, capacity 1000 litre fitted with spray
set
Three wheel 80-100 kN static roller
c) Material
Natural Rubber Modified Bitumen @ 9.80 kg per 10 sqm
Crushed stone chipping of 6.7 mm size 100 per cent passing
11.2 mm sieve and retained on 2.36 mm sieve applied @
0.09 cum per 10 sqm
d&e) Overheads & Contractors Profit
Cost of 1100 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/1100
day
day
1.000
day
22.000
day
7.150
hour
2.200
hour
2.200
1.078
cum
9.900
day
day
1.000
day
22.000
day
7.150
hour
2.200
hour
2.200
t
cum
1.078
9.900
day
day
1.000
day
22.000
day
7.150
hour
2.200
hour
2.200
1.078
cum
9.900
389
RBR-BASC
Index-code
S. No
Description
c) Material
Bitumen (S-90) @ 6.80 kg per 10 sqm
Unit Quantity
3
day
day
15.000
day
2.850
hour
2.500
hour
2.500
hour
2.500
0.850
Crushed sand or grit as passing 2.36 mm sieve and retained on 180 cum
micron sieve applied @ 0.06 cum per 10 sqm
c) Material
Bitumen (S-65) @ 6.80 kg per 10 sqm
Bitumen boiler oil fired 1000 litre capacity fitted with spray set
day
15.000
day
2.850
hour
2.500
hour
2.500
hour
2.500
0.850
Remarks
7.500
day
day
15.000
day
2.850
hour
2.500
hour
2.500
hour
2.500
c) Material
t
Polymer Modified Bitumen @ 6.80 kg per 10 sqm
Crushed sand or grit as passing 2.36 mm sieve and retained cum
on 180 micron sieve applied @ 0.06 cum/10 sqm
Amount
Rs.
7.500
day
Crushed sand or grit as passing 2.36 mm sieve and retained on 180 cum
micron sieve applied @ 0.06 cum/10 sqm
Rate
Rs.
0.850
7.500
390
RBR-BASC
Index-code
S. No
Description
1
2
(IV) Crumb Rubber Modified Bitumen
Unit = sqm
Taking output = 1250 sqm
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Semi-Skilled)
b) Machinery
Mixall 6/10 t capacity
Three wheel 80-100 kN static roller
Bitumen boiler oil fired 1000 litre capacity fitted with spray set
c) Material
Crumb Rubber Modified Bitumen @ 6.80 kg per 10 sqm
Crushed sand or grit as passing 2.36 mm sieve and retained
on 180 micron sieve applied @ 0.06 cum /10 sqm
d&e) Overheads & Contractors Profit
Cost of 1250 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/1250
(V) Natural Rubber Modified Bitumen
Unit = sqm
Taking output = 1250 sqm
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Semi-Skilled)
b) Machinery
Mixall 6/10 t capacity
Three wheel 80-100 kN static roller
Bitumen boiler oil fired 1000 litre capacity fitted with spray set
c) Material
Natural Rubber Modified Bitumen @ 6.80 kg per 10 sqm
Crushed sand or grit as passing 2.36 mm sieve and retained
on 180 micron sieve applied @ 0.06 cum /10 sqm
d&e) Overheads & Contractors Profit
Cost of 1250 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/1250
Case - III : Type C (510 - MORD)
(I) Bitumen (S-90)
Unit = sqm
Taking output = 1100 sqm
a) Labour
Mate
Bitumen Sprayer
Mazdoor (Unskilled) for carrying of chips & spraying
Mazdoor (Semi-Skilled)
b) Machinery
Bitumen boiler oil fired 1000 litre capacity fitted with spray set
Unit Quantity
3
day
day
15.000
day
2.850
hour
2.500
hour
2.500
hour
2.500
0.850
cum
7.500
day
day
15.000
day
2.850
hour
2.500
hour
2.500
hour
2.500
0.850
cum
7.500
day
day
1.000
day
22.000
day
6.150
hour
2.200
2.200
hour
Three wheel 80-100 kN static roller
c) Material
t
Bitumen (S-90) @ 6.50 kg per 10 sqm
Crushed stone chipping of 6.7 mm size defined as 100% cum
passing 9.5 mm sieve and retained on 2.36 mm sieve
applied @ 0.09 cum.
d&e) Overheads & Contractors Profit
Cost of 1100 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/1100
Rate
Rs.
Amount
Rs.
Remarks
0.715
9.900
391
RBR-BASC
Index-code
S. No
Description
Unit Quantity
3
Rate
Rs.
Amount
Rs.
Remarks
Unit = sqm
Taking output = 1100 sqm
a) Labour
Mate
Bitumen Sprayer
Mazdoor (Unskilled)
Mazdoor (Semi-Skilled)
b) Machinery
Bitumen boiler oil fired 1000 litre capacity fitted with spray set
day
day
1.000
day
22.000
day
6.150
hour
hour
2.200
2.200
0.715
Crushed stone chipping of 6.7 mm size defined as 100% passing 9.5 cum
mm sieve and retained on 2.36 mm sieve applied @ 0.09 cum.
day
day
1.000
day
22.000
day
6.150
hour
2.200
2.200
hour
Three wheel 80-100 kN static roller
c) Material
t
Polymer Modified Bitumen @ 6.50 kg per 10 sqm
Crushed stone chipping of 6.7 mm size defined as 100% cum
passing 9.5 mm sieve and retained on 2.36 mm sieve
applied @ 0.09 cum.
d&e) Overheads & Contractors Profit
Cost of 1100 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/1100
(IV) Crumb Rubber Modified Bitumen
Unit = sqm
Taking output = 1100 sqm
a) Labour
day
Mate
day
Bitumen Sprayer
day
Mazdoor (Unskilled)
day
Mazdoor (Semi-Skilled)
b) Machinery
Bitumen boiler oil fired 1000 litre capacity fitted with spray set
9.900
hour
hour
Three wheel 80-100 kN static roller
c) Material
t
Crumb Rubber Modified Bitumen @ 6.50 kg per 10 sqm
Crushed stone chipping of 6.7 mm size defined as 100% cum
passing 9.5 mm sieve and retained on 2.36 mm sieve
applied @ 0.09 cum.
d&e) Overheads & Contractors Profit
Cost of 1100 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/1100
0.715
9.900
1.000
22.000
6.150
2.200
2.200
0.715
9.900
392
RBR-BASC
Index-code
S. No
1
Description
2
(V) Natural Rubber Modified Bitumen
Unit = sqm
Taking output = 1100 sqm
a) Labour
Mate
Bitumen Sprayer
Mazdoor (Unskilled)
Mazdoor (Semi-Skilled)
b) Machinery
Bitumen boiler oil fired 1000 litre capacity fitted with spray set
Unit Quantity
3
day
day
1.000
day
22.000
day
6.150
hour
hour
2.200
2.200
0.715
Crushed stone chipping of 6.7 mm size defined as 100% passing 9.5 cum
mm sieve and retained on 2.36 mm sieve applied @ 0.09 cum.
Rate
Rs.
Amount
Rs.
Remarks
9.900
By Mechanical Means
Case - I : Type A
Bitumen (S-90)
Unit = sqm
Taking output = 7500 sqm (67.5 cum)
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Hydraulic self propelled chips spreader
Tipper 5.5 cum capacity
Front end loader 1 cum bucket capacity
Bitumen pressure distributor
Three wheel 80-100 kN static roller
c) Material
Bitumen (S-90) @ 9.80 kg per 10 sqm
day
day
6.240
hour
6.000
hour
6.000
hour
6.000
hour
6.000
hour
15.000
Crushed stone chipping of 6.7 mm size 100 per cent passing 11.2 cum
mm sieve and retained on 2.36 mm sieve applied @ 0.09 cum/10
sqm
7.350
67.500
day
day
6.240
hour
6.000
hour
6.000
hour
6.000
hour
6.000
hour
15.000
Crushed stone chipping of 6.7 mm size 100 per cent passing 11.2 cum
mm sieve and retained on 2.36 mm sieve applied @ 0.09 cum per 10
sqm
7.350
67.500
393
RBR-BASC
Index-code
S. No
Description
Unit Quantity
3
Rate
Rs.
Amount
Rs.
Remarks
Unit = sqm
Taking output = 7500 sqm (67.5 cum)
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Hydraulic self propelled chips spreader
Tipper 5.5 cum capacity
Front end loader 1 cum bucket capacity
Bitumen pressure distributor
Three wheel 80-100 kN static roller
c) Material
Polymer Modified Bitumen @ 9.80 kg per 10 sqm
day
day
6.240
hour
6.000
hour
6.000
hour
6.000
hour
6.000
hour
15.000
Crushed stone chipping of 6.7 mm size 100 per cent passing 11.2 cum
mm sieve and retained on 2.36 mm sieve applied @ 0.09 cum per 10
sqm
7.350
67.500
day
day
6.240
hour
6.000
hour
6.000
hour
6.000
hour
6.000
hour
15.000
Crushed stone chipping of 6.7 mm size 100 per cent passing cum
11.2 mm sieve and retained on 2.36 mm sieve applied @
0.09 cum/10 sqm
7.350
67.500
Unit = sqm
Taking output = 7500 sqm (67.5 cum)
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Hydraulic self propelled chips spreader
Tipper 5.5 cum capacity
Front end loader 1 cum bucket capacity
Bitumen pressure distributor
Three wheel 80-100 kN static roller
c) Material
day
day
6.240
hour
6.000
hour
6.000
hour
6.000
hour
6.000
hour
15.000
7.350
67.500
394
RBR-BASC
Index-code
S. No
Description
Unit Quantity
3
Rate
Rs.
Amount
Rs.
Remarks
Case - II : Type B
(I) Bitumen (S-90)
Unit = sqm
Taking output = 5000 sqm (30 cum)
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
HMP of 30/40 t per hour
Electric generator set 125 KVA
Front end loader 1 cum bucket capacity
Tipper 5.5 cum - 10 t capacity
Paver finisher
Three wheel 80-100 kN static roller
c) Material
Bitumen (S-90) @ 6.80 kg per 10 sqm
day
day
4.160
hour
2.000
hour
2.000
hour
2.000
hour
1.360
hour
2.000
hour
10.000
Crushed sand defined as passing 2.36 mm sieve and retained on 180 cum
micron sieve applied @ 0.06 cum per 10 sqm
day
day
4.160
hour
2.000
hour
2.000
hour
2.000
hour
1.360
hour
2.000
hour
10.000
Crushed sand defined as passing 2.36 mm sieve and retained on 180 cum
micron sieve applied @ 0.06 cum /10 sqm
3.400
30.000
3.400
30.000
day
day
4.160
hour
2.000
hour
2.000
hour
2.000
hour
1.360
hour
2.000
hour
10.000
Crushed sand defined as passing 2.36 mm sieve and retained on 180 cum
micron sieve applied @ 0.06 cum per 10 sqm
3.400
30.000
395
RBR-BASC
Index-code
S. No
Description
1
2
(IV) Crumb Rubber Modified Bitumen
Unit = sqm
Taking output = 5000 sqm (30 cum)
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
HMP of 30/40 t per hour
Electric generator set 125 KVA
Front end loader 1 cum bucket capacity
Tipper 5.5 cum - 10 t capacity
Paver finisher
Three wheel 80-100 kN static roller
c) Material
Crumb Rubber Modified Bitumen @ 6.80 kg per 10 sqm
Unit Quantity
3
day
day
4.160
hour
2.000
hour
2.000
hour
2.000
hour
hour
1.360
2.000
hour
10.000
Crushed sand defined as passing 2.36 mm sieve and retained on 180 cum
micron sieve applied @ 0.06 cum per 10 sqm
Remarks
3.400
day
4.160
hour
2.000
hour
2.000
hour
2.000
hour
1.360
hour
2.000
hour
10.000
Amount
Rs.
30.000
day
Crushed sand defined as passing 2.36 mm sieve and retained on 180 cum
micron sieve applied @ 0.06 cum per 10 sqm
Rate
Rs.
3.400
30.000
day
day
5.200
hour
hour
hour
hour
6.000
6.000
6.000
6.000
hour
15.000
t
Crushed stone chipping of 6.7 mm size 100 per cent passing 9.5 mm cum
sieve and retained on 2.36 mm sieve applied @ 0.09 cum per 10 sqm
4.880
67.500
396
RBR-BASC
Index-code
S. No
Description
Unit Quantity
3
Rate
Rs.
Amount
Rs.
Remarks
Unit = sqm
Taking output = 7500 sqm (67.5 cum)
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Hydraulic self propelled chips spreader
Tipper 5.5 cum capacity
Front end loader 1 cum bucket capacity
Bitumen pressure distributor
Three wheel 80-100 kN static roller
c) Material
Bitumen (S-65) @ 6.50 kg per 10 sqm
Crushed stone chipping of 6.7 mm size 100 per cent passing
9.5 mm sieve and retained on 2.36 mm sieve applied @ 0.09
cum per 10 sqm
d&e) Overheads & Contractors Profit
Cost of 7500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/7500
(III) Polymer Modified Bitumen
Unit = sqm
Taking output = 7500 sqm (67.5 cum)
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Hydraulic self propelled chips spreader
Tipper 5.5 cum capacity
Front end loader 1 cum bucket capacity
Bitumen pressure distributor
Three wheel 80-100 kN static roller
c) Material
Polymer Modified Bitumen @ 6.50 kg per 10 sqm
Crushed stone chipping of 6.7 mm size 100 per cent passing
9.5 mm sieve and retained on 2.36 mm sieve applied @ 0.09
cum per 10 sqm
d&e) Overheads & Contractors Profit
Cost of 7500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/7500
(IV) Crumb Rubber Modified Bitumen
Unit = sqm
Taking output = 7500 sqm (67.5 cum)
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Hydraulic self propelled chips spreader
Tipper 5.5 cum capacity
Front end loader 1 cum bucket capacity
Bitumen pressure distributor
Three wheel 80-100 kN static roller
c) Material
Crumb Rubber Modified Bitumen @ 6.50 kg per 10 sqm
Crushed stone chipping of 6.7 mm size 100 per cent passing
9.5 mm sieve and retained on 2.36 mm sieve applied @ 0.09
cum per 10 sqm
d&e) Overheads & Contractors Profit
Cost of 7500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/7500
day
day
5.200
hour
6.000
hour
6.000
hour
6.000
hour
6.000
hour
15.000
4.880
cum
67.500
day
day
5.200
hour
6.000
hour
6.000
hour
6.000
hour
6.000
hour
15.000
4.880
cum
67.500
day
day
5.200
hour
6.000
hour
6.000
hour
6.000
hour
6.000
hour
15.000
t
cum
4.880
67.500
397
RBR-BASC
Index-code
S. No
1
Description
2
(V) Natural Rubber Modified Bitumen
Unit = sqm
Taking output = 7500 sqm (67.5 cum)
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Hydraulic self propelled chips spreader
Tipper 5.5 cum capacity
Front end loader 1 cum bucket capacity
Bitumen pressure distributor
Three wheel 80-100 kN static roller
c) Material
Natural Rubber Modified Bitumen @ 6.50 kg per 10 sqm
Crushed stone chipping of 6.7 mm size 100 per cent passing
9.5 mm sieve and retained on 2.36 mm sieve applied @ 0.09
cum per 10 sqm
d&e) Overheads & Contractors Profit
Cost of 7500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/7500
Unit Quantity
3
day
day
5.200
hour
6.000
hour
6.000
hour
6.000
hour
6.000
hour
15.000
4.880
cum
67.500
Rate
Rs.
Amount
Rs.
Remarks
Note : Since seal coat is provided immediately over the bituminous layers,
Hydraulic broom for cleaning has not been catered.
ii
day
day
6.240
hour
6.000
hour
6.000
hour
6.000
hour
6.000
hour
6.000
t
Crushed stone chipping of 6.7 mm size defined as 100 per cent cum
passing 11.2 mm sieve and retained on 2.36 mm sieve applied @
0.09 cum per 10 sqm
10.050
92.250
398
RBR-BASC
Index-code
S. No
Description
Unit Quantity
3
Rate
Rs.
Amount
Rs.
Remarks
Case - II : Type B
Providing and laying of premix sand seal coat with HMP of
appropriate capacity not less than 75 tonnes/ hours using crushed
stone chipping 6.7 mm size and penetration bitumen of suitable
grade.
Unit = sqm
Taking output = 7858 sqm (47.16 cum)
a)
Labour
Mate
day
Mazdoor (Unskilled)
b) Machinery
HMP of 75 tonnes/hour.
day
4.160
hour
2.000
hour
2.000
hour
t.km
2.000
104 x 'L'
hour
2.000
hour
2.000
5.340
47.160
RBR-BASC-18
18
RBR-BASC-19
19
day
day
10.000
day
1.440
399
RBR-BASC
Index-code
S. No
1
Description
2
b) Machinery
Mechanical broom @ 1250 sqm per hour
Air compressor 250 cfm
Mastic cooker 1 tonne capacity
Bitumen boiler 1500 litres capacity
Tractor for towing and positioning of mastic cooker and
bitumen boiler
c) Material
Base mastic (without coarse aggregates) = 60 per cent
Coarse aggregate (6.3mm to 13.2 mm) = 40 per cent
Unit Quantity
3
hour
0.060
hour
0.060
hour
6.000
hour
6.000
hour
1.000
Rate
Rs.
Amount
Rs.
Remarks
0.204
0.390
0.360
0.550
0.018
0.500
RBR-BASC-20
20
Slurry Seal
Providing and laying slurry seal consisting of a mixture of fine
aggregates, portland cement filler, bituminous emulsion and
water on a road surface including cleaning of surface, mixing
of slurry seal in a suitable mobile plant, laying and
compacting to provide even riding surface as per Tech.
Specification 516 MORTH
(i) 5 mm thickness
Unit = sqm
Taking output = 16000 sqm (80 cum)
Taking density of 2.2 tonnes per cum
weight of mix = 176 tonnes
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Mechanical broom
Air compressor 250 cfm
Mobile slurry seal equipment
Front end loader 1 cum bucket capacity
Tipper 5.5 cum capacity for carriage of aggregate from
stockpile on road side to slurry equipment, bitumen emulsion
and filler.
day
day
6.240
hour
6.000
hour
6.000
hour
6.000
hour
6.000
hour
6.000
400
RBR-BASC
Index-code
S. No
1
Description
Unit Quantity
2
3
Pneumatic tyred roller with individual wheel load not exceeding 1.5 hour
tonnes
hour
Water tanker6 KL capacity
c) Material
Residual Binder (BT Emulsion - medium setting) @ 11 t
per cent of mix 80 x 2.2 x 0.11
Fine aggregate 4.75 mm and below 87 per cent of total cum
mix,80 x 2.2 x 0.87 = 153.12 tonnes. Taking density1.5, =
153.12/1.5 = 102.08 cum
t
Filler @ 2 per cent of total mix = 80 x 2.2 x 0.02 (Cement)
Cost of water
d&e) Overheads & Contractors Profit
Cost for 16000 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/16000
(ii) 3 mm thickness
Unit = sqm
Taking output = 20000 sqm (60 cum)
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Mechanical broom
Air compressor 250 cfm
Mobile slurry seal equipment
Front end loader 1 cum bucket capacity
KL
4
6.000
6.000
hour
6.000
hour
6.000
hour
6.000
Tipper 5.5 cum capacity for carriage of aggregate from stockpile on hour
road side to slurry equipment, bitumen emulsion and filler
hour
Water tanker6 KL capacity
6.000
2.000
17.160
cum
74.800
2.640
KL
12.000
day
day
5.200
hour
6.000
hour
6.000
hour
6.000
hour
Tipper 5.5 cum capacity for carriage of aggregate from stockpile on hour
road side to slurry equipment, bitumen emulsion and filler.
hour
Water tanker6 KL capacity
6.000
6.000
KL
12.000
hour
Cost of water
d&e) Overheads & Contractors Profit
Cost for 24000 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/24000
3.520
Fine aggregate 2.36 mm and below,82 per cent of total mix,36x 2.2 x cum
0.82 = 64.94 tonnes. Taking density 1.5
t
Filler @ 2 per cent of total mix = 36x 2.2 x 0.02
102.080
5.200
Remarks
19.360
day
c) Material
Residual Binder (BT Emulsion -Medium setting) @ 16 per
cent of mix, 36 x 2.2 x 0.16
Amount
Rs.
2.000
day
c) Material
Residual Binder (BT Emulsion - medium setting) @ 13 per
cent of mix = 60 x 2.2 x 0.13
Fine aggregate 3 mm and below 85 per cent of total mix,
60x 2.2 x 0.85 = 112.2 tonnes. Taking density 1.5,
Filler @ 2 per cent of total mix = 60x 2.2 x 0.02
Cost of water
d&e) Overheads & Contractors Profit
Cost for 20000 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/20000
(iii) 1.5 mm thickness
Unit = sqm
Taking output = 24000 sqm (36 cum)
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Mechanical broom
Air compressor 250 cfm
Mobile slurry seal equipment
Front end loader 1 cum bucket capacity
Rate
Rs.
2.000
12.670
43.300
1.580
12.000
Note : 1.Tack coat, if required to be provided, before laying slurry seal may be measured and paid
separately
401
RBR-BASC
Index-code
S. No
1
RBR-BASC-21
21
Description
Unit Quantity
Recycling of Bituminous
Recycling Plant
Pavement
with
Rate
Rs.
Amount
Rs.
Remarks
Central
Unit = cum
Taking output = 120 cum (276 tonnes)
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor skilled
b) Machinery
Cold milling machine @ 20 cum per hour
Mechanical broom @ 1250 sqm per hour
Air compressor 250 cfm
Bitumen pressure distributor @ 1750 sqm per hour
day
day
10.000
day
2.480
hour
6.000
hour
1.280
hour
1.280
hour
0.910
Hot mix plant 100-120 TPH producing an average of 75 tonnes per hour
hour
hour
Electric generator set 250 KVA
3.000
3.000
hour
3.000
hour
18.000
hour
1.950
hour
1.950
hour
1.950
1.987
7.728
28.440
18.550
24.730
49.460
5.520
Note : Although the total rolling time is only 4 hours as per norms, all the
three rollers have to be available at site for 3 hours each to match with the
output of re-cycling plant. To cater for their idling time, these have been
multiplied with a factor of 0.65.
402
RBR-BASC
Index-code
S. No
Description
RBR-BASC-22
22
Unit Quantity
3
Rate
Rs.
Amount
Rs.
Remarks
Fog Spray
Providing and applying low viscosity bitumen emulsion for sealing
cracks less than 3 mm wide or incipient fretting or disintegration in an
existing bituminous surfacing as per Tech. Specification 518 MORTH.
Unit = sqm
Taking output = 10500 sqm
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Mechanical broom @ 1250 sqm per hour
Air compressor 250 cfm
Bitumen emulsion pressure distributor @ 1750 sqm per hour
day
day
3.120
hour
6.000
hour
6.000
hour
6.000
c) Material
t
Bitumen emulsion (Medium setting) @ 0.75 kg/sqm
d&e) Overheads & Contractors Profit
Cost for 10500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/10500
1.In case it is decided by the engineer to blind the fog spray,
the following may be added
a) Labour
day
Mate
day
Mazdoor (Unskilled) for precoating of grit
b) Material
cum
Crushed stone grit 3 mm size @ 3.75 kg per sqm
Bitumen emulsion for precoating grit @ 2 per cent of t
grit,39.38 x 0.02
7.880
0.160
4.000
26.250
0.790
RBR-BASC-23
23
Unit = cum
Taking output = 205 cum (450 tonne)
(i) Using bitumen emulsion and 9.5 mm or 13.2 mm size
aggregate
Composition of mix (450 tonne) is assumed to be as under:-
day
day
16.000
day
5.840
hour
6.000
hour
6.000
hour
6.000
t.km
450 x L
hour
6.000
hour
3.900
hour
3.900
36.000
9.000
cum
75.000
cum
87.000
cum
Aggregates size 6 to 0.075 mm - 450 x 0.36 x 1/1.5
d&e) Overheads & Contractors Profit
Cost for 205 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/205
(Applicable to cases I to IV)
Note : 1. Density of aggregates has been assumed 1.5 gms/cc
108.000
403
RBR-BASC
Index-code
S. No
1
Description
2
Unit Quantity
3
Rate
Rs.
Amount
Rs.
Remarks
3. Though the rollers are required only for 3.5 hours each as per norms of output, but these are required
to be available at site for 6 hours as the drum mix plant and the paver would take 6 hours for mixing and
paving. To cater for the idle period, their usage rates have been multiplied by a factor of 0.65
(ii) Using bitumen emulsion and 19 mm or 26.5 mm nominal
size aggregate
Composition of mix (450 tonne) is assumed to be as under:Bitumen Emulsion 8 per cent
Filler2 per cent
Total aggregates 90 per cent
Proportion of aggregates
37.5 mm to 19 mm25 per cent
19 mm to 6 mm 30 per cent
6 mm to 0.075 mm 35 per cent
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor skilled
b) Machinery
Drum mix plant for cold mixes 60-90 tonne per hour
producing average output of 75 tonnes per hour
Electric generator 125 KVA
Front end loader 1 cum bucket capacity
Tipper 10 tonne capacity
day
day
16.000
day
5.840
hour
6.000
hour
6.000
hour
6.000
t.km
450 x L
6.000
3.900
3.900
36.000
9.000
75.000
90.000
105.000
404
RBR-BASC
Index-code
S. No
Description
1
2
(iii) Using cutback bitumen and 9.5 mm or 13.2 mm nominal
Unit Quantity
3
Rate
Rs.
Amount
Rs.
Remarks
size aggregate
Composition of mix (450 tonne) is assumed to be as under:Cutback bitumen 5 per cent
Filler (lime) 2 per cent
Total aggregates 93 per cent
Proportion of aggregates
19 mm to 9.5 mm26 per cent
9.5 mm to 6 mm31 per cent
6 mm to 0.075 mm 36 per cent
a) Labour
day
Mate
day
Mazdoor (Unskilled)
day
Mazdoor skilled
b) Machinery
Drum mix plant for cold mixes 60-90 tonne per hour hour
producing average output of 75 tonnes per hour
hour
Electric generator 125 KVA
hour
Front end loader 1 cum bucket capacity
t.km
Tipper 10 tonne capacity
16.000
5.840
6.000
6.000
6.000
450 x L
size aggregate
Composition of mix (450 tonne) is assumed to be as under:Cutback bitumen 5 per cent
Filler2 per cent
Total aggregates 93 per cent
Proportion of aggregates
37.5 mm to 19 mm25 per cent
19 mm to 6 mm 30 per cent
6 mm to 0.075 mm 38 per cent
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor skilled
b) Machinery
Drum mix plant for cold mixes 60-90 tonne per hour
producing output of 75 tonnes per hour
Electric generator 125 KVA
Front end loader 1 cum bucket capacity
Tipper 10 tonne capacity
Paver finisher
Pneumatic tyred roller 12-15 tonnes.
Smooth wheeled steel tandem roller 6-8 tonnes
c) Material
Cutback bitumen on @ 5 per cent
Filler (lime)@ 2 per cent
Aggregates size 37.5 to 19 mm - 450 x 0.25 x 1/1.5
Aggregates size 19 to 6 mm - 450 x 0.3 x 1/1.5
Aggregates size 6 to 0.075 mm - 450 x0.38 x 1/1.5
d&e) Overheads & Contractors Profit
Cost for 205 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/205
day
day
16.000
day
5.840
hour
6.000
hour
6.000
hour
6.000
t.km
450 x L
hour
6.000
hour
3.900
hour
3.900
22.500
9.000
cum
75.000
cum
90.000
cum
114.000
RBR-BASC-24
24
405
RBR-BASC
Index-code
S. No
Description
2
Providing, laying and rolling sand-asphalt base course composed of
sand, mineral filler and bituminous binder on a prepared sub-grade or
sub-base to the lines, levels, grades and cross sections as per the
drawings including mixing in a plant of suitable type and capacity,
transporting, laying, compacting and finishing as per Tech.
specification 520 MORTH.
Unit = cum
Taking output = 205 cum (450 tonne)
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor skilled
b) Machinery
Unit Quantity
3
day
day
16.000
day
5.840
Hot Mix Plant of appropriate capacity but not less than 75 tonnes/hour hour
6.000
hour
6.000
hour
6.000
t.km
450 x L
hour
6.000
hour
3.900
hour
3.900
hour
3.900
c) Material
Composition of mix (450 tonne) is assumed to be as
under:Density 2.20 tonne per cum
Weight450 tonne
Bitumen5 per cent
Filler2 per cent
Sand of size 4.75 to 0.075 mm 93 per cent
t
Bitumen@ 5 per cent
t
Filler (lime)@ 2 per cent
cum
Sand of size 4.75 to 0.075 mm - 450 x 0.93 x 1/1.5
d&e) Overheads & Contractors Profit
Cost for 205 cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d+e)/205
Rate
Rs.
Amount
Rs.
Remarks
22.500
9.000
288.620
406
RBR-BASC
Index-code
S. No
1
RBR-BASC-25
Description
2
25
Unit Quantity
3
Rate
Rs.
Amount
Rs.
Remarks
Modified Binder
Supply of modified binder produced by mixing bitumen with modifier such as natural rubber
or crumb rubber or any other polymer found compatible with bitumen and which allows
properties given in clause 521.3 and IRC:SP: 53 blending of modifier with bitumen to be done
either at the refinery or at central unit with all facilities by proper industrial process, is
essential. See Tech. specification 521 MORTH.
Unit = tonne
The use of modified binder is expected to result in an extended service life of bituminous
pavements subject to heavy traffic loads in extreme climatic conditions, thus justifying the
entire cost of adding modifiers/fibers. Other advantages include lower temperature
susceptibility, higher resistance to aging, higher fatigue life, higher resistance to cracking and
better adhesion between aggregates and binder.
Detailed information and inductive dose level on the use of polymer modified binder is
available in IRC : SP-53 / 2002. A number of proprietary products are now available in the
market. For such proprietary products, test reports and cost effectiveness should be the
basis for their selection in road works.
The modifier, in the required quantity shall be blended at the refinery or at central unit with all
facilities by proper industrial process, is essential. If supplied in drums it shall be agitated in
melted condition with suitable device for achieving homogeneity
Proposals to use glass fiber, polypropylene fibers or any other similar material in a
bituminous mixture should be substantiated, complete with all details including test results,
manufacturer's recommendations for addition or means of incorporating the fibers,
homogeneously, without segregation, into the mixture.
Before agreeing to the use of a fiber, it should have been proved to be satisfactory in use
under circumstances, similar to the work, elsewhere or it would have under gone appropriate
performance trials. Documented evidence of use and trials of the fiber, in any country having
conditions similar to Indian will be acceptable.
where information on use of trials is inadequate or lacking, trials may be required to be under
taken before agreeing to the use of the fiber.
Note : 1. The modified binder is usually manufactured by specialised firms as a proprietary product. The
rate for this product is required to be as certained from the market.
2.The specifications for various item of road works using polymer/rubber modified bitumens are same as
those for penetration grade bitumen except those for any special conditions which the manufacturer may
indicate
3.The other controls during mixing, laying shall be same as specified in IRC - 14, 29, 94 and 95 for open
graded premix carpet, bituminous concrete, DBM and SDBC respectively
4.The temperature of mixing and rolling will be slightly higher than conventional bituminous mixes as
indicated in Table 8 of IRC: SP: 53 - 2002
RBR-BASC-26
26
i
Unit = sqm
Taking output = 10500 sqm
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Mechanical broom @ 1250 sqm per hour
Air compressor 250 cfm
Bitumen pressure distributor @ 1750 sqm per hour
Hydraulic Chip spreader
Smooth wheeled road roller 8-10 tonne
c) Material
Modified binder
Crushed stone aggregates 5.6 mm size
d&e) Overheads & Contractors Profit
Cost for 10500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/10500
(ii) Stress absorbing membrane (SAM) with crack width 6
mm to 9 mm
day
day
6.240
hour
6.000
hour
6.000
hour
hour
hour
6.000
6.000
6.000
t
cum
9.450
105.000
day
day
6.240
hour
6.000
hour
6.000
hour
6.000
Unit = sqm
Taking output = 10500 sqm
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Mechanical broom @ 1250 sqm per hour
Air compressor 250 cfm capacity
Bitumen pressure distributor @ 1750 sqm per hour
407
RBR-BASC
Index-code
S. No
Description
Unit Quantity
3
hour
Hydraulic Chip spreader
hour
Smooth wheeled road roller 8-10 tonne
c) Material
t
Modified binder
cum
Crushed stone chipping 11.2 mm size
d&e) Overheads & Contractors Profit
Cost for 10500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/10500
(iii) Stress absorbing membrane (SAM) crack width above 9
mm and cracked area above 50 per cent
4
6.000
Rate
Rs.
Amount
Rs.
Remarks
6.000
11.550
105.000
Unit = sqm
Taking output = 10500 sqm
a) Labour
day
Mate
day
6.000
Mazdoor (Unskilled)
day
2.240
Mazdoor skilled
b) Machinery
hour
6.000
Mechanical broom @ 1250 sqm per hour
hour
6.000
Air compressor 250 cfm capacity
hour
6.000
Bitumen pressure distributor @ 1750 sqm per hour
hour
6.000
Hydraulic Chip spreader
hour
6.000
Smooth wheeled road roller 8-10 tonne
c) Material
t
15.750
Modified binder
cum 126.000
Crushed stone aggregates 11.2 mm size
d&e) Overheads & Contractors Profit
Cost for 10500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/10500
Note : In case 2nd coat is also required to be provided, material provided for the 2nd coat
shall be as per table 500-47.
408
RBR-BASC
Index-code
S. No
1
Description
2
(iv) Case-IV : Bitumen impregnated geotextile
Unit Quantity
3
day
day
12.000
day
2.560
hour
2.800
hour
2.800
2.000
hour
2.000
Rate
Rs.
Amount
Rs.
Remarks
t
3.680
sqm 3850.000
RBR-BASC-27
27
Unit = cum
Taking output = 205 sqm (450 tonnes)
(i) 75 mm thickness
a) Labour
day
Mate
day
Mazdoor (Unskilled)
day
Mazdoor skilled
b) Machinery
Drum mix plant for cold mixes 40 / 60 tonne per hour hour
producing output of 50 tonnes per hour
hour
Electric generator 125 KVA
hour
Front end loader 1 cum capacity
Paver finisher hydrostatic with sensor control @ 75 cum/ hour
hour
t.km
hour
hour
12.000
6.000
9.000
6.000
6.000
6.000
450 x L
3.900
3.900
1.000
20.250
cum
297.000
KL
6.000
409
RBR-BASC
Index-code
S. No
Description
2
ii
40 mm thickness
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor skilled
b) Machinery
Unit Quantity
3
day
day
12.000
day
6.000
9.000
Rate
Rs.
Amount
Rs.
Remarks
6.000
6.000
6.000
450 x L
hour
3.900
hour
3.900
hour
1.000
31.500
cum
287.000
KL
6.000
day
day
12.000
day
6.000
hour
hour
9.000
hour
6.000
hour
6.000
hour
6.000
t.km
450 x L
hour
hour
3.900
3.900
hour
1.000
38.250
cum
270.000
KL
6.000
410
RBR-BASC
Index-code
S. No
Description
Unit Quantity
3
Rate
Rs.
Amount
Rs.
Remarks
411
RBR-CCPV
Chapter - 6
CEMENT CONCRETE PAVEMENT
Index-code
S. No
1
RBR-CCPV-1
RBR-CCPV-2
RBR-CCPV-3
RBR-CCPV-4
Description
2
Unit Quantity
3
Rate
Rs.
Amount
Rs.
Remarks
Granual Sub-base
Rate as per item No. 1 or 2 of Chapter 4
Lime Treated Soil
Rate as per item No. 3 or 4 of Chapter 4
Water Bound Macadam (WBM) - Sub-base
(A) By Manual Means
As per item No.9 of Chapter 4
(B) By Mechanical Means
As per item No.9 of Chapter 4
Dry Lean Cement Concrete Sub- base
Construction of dry lean cement concrete Sub- base over a prepared
sub-grade with coarse and fine aggregate conforming to IS: 383, the
size of coarse aggregate not exceeding 25 mm, aggregate cement
ratio not to exceed 15:1, aggregate gradation after blending to be as
per table 600-1, cement content not to be less than 150 kg/ cum,
optimum moisture content to be determined during trial length
construction, concrete strength not to be less than 10 Mpa at 7 days,
mixed in a batching plant, transported to site, laid with a paver with
electronic sensor, compacting with 8-10 tonnes vibratory roller,
finishing and curing etc. complete as per Technical Specification 601
MORTH.
Unit = cum
Taking output = 450 cum (990 tonne)
a) Labour
Mate
Mazdoor skilled
Mazdoor (Unskilled)
b)
Machinery
Front end loader 1 cum bucket capacity
Cement concrete batch mix plant @ 75 cum per hour
Electric generator 100 KVA
Paver with electronic sensor
Vibratory roller 8-10 t capacity
Water tanker 6 KL capacity
Tipper
c)
Material
Crushed stone coarse aggregate of 25 mm and 12.5 mm
nominal sizes graded as per table 600-1 @ 0.90 cum/cum of
concrete conforming to clause 602.2.4.
Coarse Sand as per IS: 383 @ 0.45 cum/cum of concrete
Cement @ 150 kg/cum of concrete
Cost of water
d&e) Overheads & Contractors Profit
Cost for 450 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/450
day
day
7.12
day
22.00
hour
6.00
hour
6.00
hour
6.00
hour
6.00
hour
8.00
hour
8.00
t.km
990 x L
cum
405.00
cum
203.00
tonne
67.50
KL
48.00
413
RBR-CCPV
Index-code
RBR-CCPV-5
S. No
Description
Unit Quantity
3
Rate
Rs.
Amount
Rs.
Remarks
day
day
5.00
day
5.00
day
150.00
day
6.00
day
2.00
day
6.00
day
1.00
hour
36.00
hour
9.00
hour
9.00
hour
9.00
hour
4.00
hour
5.00
hour
2.00
cum
67.50
cum
33.75
26.25
sqm
Polythene sheet 125 micron
Mild steel dowel bar 25 mm dia of grade S 240. 500 mm long
20 Nos. at culvert/bridge slab and at construction joint
including 5 per cent wastage.
(4 x 20 x 0.500) + 5 per cent wastage = 42 m @ 2.80 kg per t
m = 117.6 kg.
kg
Bitumen primer @ 200 ml per joint for 23 joints
litre
Bituminous sealant 800 ml per joint for 23 joints
m
Jute rope 12 mm dia including 5 per cent wastage
Debonding strips 3.75 m (length) x 10 mm (width) x 5 mm m
(thick) cut-out of rubber filler board or similar material
including 5 per cent wastage
412.50
483.00
litre
122.00
litre
131.25
kl
18.00
sqm
3.00
0.118
5.00
19.00
90.00
90.00
414
RBR-CCPV
Index-code
S. No
Description
2
Construction of un-reinforced, dowel jointed, plain cement concrete
pavement over a prepared sub base with 43 grade cement @ 400 kg
per cum, coarse and fine aggregate conforming to IS 383, maximum
size of coarse aggregate not exceeding 25 mm, mixed in a batching
and mixing plant as per approved mix design, transported to site, laid
with a fixed form or slip form paver, spread, compacted and finished
in a continuous operation including provision of contraction,
expansion, construction and longitudinal joints, joint filler, separation
membrane, sealant primer, joint sealant, debonding strip, dowel bar,
tie rod, admixtures as approved, curing compound, finishing to lines
and grades as per drawing and Technical Specification 602 MORTH.
RBR-CCPV-6
Unit = cum
Taking output = 1050 cum (2415 tonne)
a) Labour
Mate
Mazdoor skilled
Mazdoor (Unskilled)
b)
Machinery
Road Sweeper @ 1250 sqm per hour
Front end loader 1 cum bucket capacity
Cement concrete batch mix plant @ 175 cum per hour
(effective
output) 250 KVA
Electric generator
Slip form paver with electronic sensor
Water tanker6 KL capacity
Transit truck agitator 5 cum capacity.
Concrete joint cutting machine
Texturing machine
c)
Material
Crushed stone coarse aggregates of 25mm and 12.5mm
nominal size @ 0.90 cum/cum of concrete conforming to
clause 602.2.4.
Sand as per IS: 383 and conforming to clause 602.2.4 @
0.45 cum/cum of concrete
Cement 43 grade @ 400 kg/cum of concrete
32 mm mild steel dowel bars of grade S 240
16 mm deformed steel tie bars of grade S 415
Separation Membrane of impermeable plastic sheeting 125
micron thick
Pre moulded Joint filler, 25 mm thick for expansion joint.
Joint sealant
Unit Quantity
3
day
day
15.00
day
37.00
hour
2.80
hour
18.00
hour
6.00
hour
6.00
hour
6.00
hour
36.00
Rate
Rs.
Amount
Rs.
Remarks
tonne 2415xL
.km
hour
12.00
hour
12.00
cum
945.00
cum
473.00
tonne
414.00
tonne
9.45
tonne
1.17
sqm
3675.00
sqm
16.33
kg
875.00
415
RBR-CCPV
Index-code
RBR-CCPV-7
S. No
Description
Unit Quantity
3
kg
4
116.67
Rate
Rs.
Amount
Rs.
Remarks
Sealant primer
sqm
46.67
Plastic sheath,1.25 mm thick for dowel bars
liter 1850.00
Curing compound
Super plastisizer admixture IS marked as per 9103-1999 @ kg 2070.00
0.5 per cent by weight of cement
KL
216.00
Cost of water
Add 1 per cent of material for cost of miscellaneous
materials like tarpaulin, Hessian cloth, metal cap, cotton /
compressible sponge and cradle for dowel bars, work
bridges for men to approach concrete surface without
walking over it, cutting blades and bites, minor equipments
like scrabbling machine, threads, ropes, guide wires and any
other unforeseen items.
d&e) Overheads & Contractors Profit
Cost for 1050 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/1050
Note : The quantities for cement, coarse aggregate and fine
aggregates are for estimating only .The exact quantities will be as
per mix design.
Roller Compacted Concrete Pavement
Construction of Roller Compacted Concrete Pavement (RCCP) with
coarse and fine aggregates conforming to IS:383, the size of coarse
aggregate not exceeding 25 mm with minimum aggregate cement
ratio of 5:1 and with minimum cement content of 310 kg per cum,
aggregate gradation to be as per Table 602.2 after blending, mixing in
concrete mixer at optimum moisture content, transporting to site,
laying with wheel barrows or steel pans or with mechanical paver,
compacting with 80-100 kN smooth wheel, tendem, vibratory roller, to
achieve, the designed flexural strength, finishing and curing as per
drawings and Technical Specification Clause 1502 MORD.
Unit = cum
Taking output = 75 cum
a) Labour
Mate
Mazdoor (Unskilled)
Mason (1st class)
Mason (2nd class)
Surveyor
b) Machinery
Concrete mixer 0.28 / 0.4 cum capacity (6 mixers) with weigh
batcher and suitable capacity calibrated water tank
Three wheel 80-100 kN static roller
OR
Vibratory roller 80-100 kN
Concrete joint cutting machine for days end work and
regulartanker
joint cutting.
Water
6 kl capacity
Air compressor (1 hour initial + 1 hour final)
c) Material
Crushed stone coarse aggregates grading as per Clause
1501.2.4.1 (Table 1500.3) @ 0.90 cum/cum of concrete
conforming to Clause 600.4.4 (25 mm & 12.5 mm blending)
day
day
152.00
day
4.00
day
4.00
day
2.00
hour
36.00
hour
7.50
hour
6.00
hour
6.00
hour
6.00
hour
2.00
cum
67.50
33.75
416
RBR-CCPV
Index-code
S. No
Description
Unit Quantity
3
t
4
23.25
kg
4.00
90.00
kg
16.80
131.25
kl
18.00
Rate
Rs.
Amount
Rs.
Remarks
Note : When curing compound is used 4-days water curing will be done
RBR-CCPV-8
Unit = cum
Taking output = 450 cum (990 tonne)
a) Labour
Mate
Mazdoor skilled
Mazdoor (Unskilled)
b)
Machinery
Front end loader 1 cum bucket capacity
Cement concrete batch mix plant @ 75 cum per hour
Electric generator 100 KVA
Paver with electronic sensor @ 75 cum/hr.
Vibratory roller 8-10 t capacity
Water tanker with 5 km lead 6 KL capacity
Tipper
day
day
7.00
day
24.20
hour
6.00
hour
6.00
hour
6.00
hour
6.00
hour
8.00
hour
tonne
Add 10 per cent of cost of carriage to cover cost of loading and .km
unloading
c)
8.00
990xL
Material
405.00
203.00
90.00
48.00
417
RBR-CCPV
Index-code
RBR-CCPV-9
S. No
Description
Unit Quantity
3
Rate
Rs.
Amount
Rs.
Remarks
RBR-CCPV-10
10
Unit = cum
Taking output = 450 cum (990 tonne)
a)
Labour
Mate
day
Mazdoor skilled
day
6.00
Mazdoor (Unskilled)
day
23.12
hour
6.00
hour
6.00
hour
6.00
hour
6.00
hour
8.00
hour
8.00
Tipper 10 T Capacity
t.km
990 x L
b)
Machinery
405.00
110.96
tonne
67.50
cum
91.54
418
RBR-CCPV
Index-code
RBR-CCPV-11
S. No
Description
11
Unit Quantity
3
Rate
Rs.
Amount
Rs.
Remarks
Unit = cum
Taking output = 1050 cum (2415 tonne)
a)
Labour
Mate
day
Mazdoor skilled
day
15.00
Mazdoor (Unskilled)
day
37.00
b)
Machinery
hour
2.80
hour
18.00
Cement concrete batch mix plant @ 175 cum per hour hour
(effective output)
hour
Electric generator 250 KVA
6.00
6.00
hour
6.00
hour
36.00
tonne 2415xL
hour
12.00
Texturing machine .
hour
12.00
945.00
cum
425.00
Cement 43 grade
tonne
357.00
tonne
109.00
tonne
9.45
tonne
c)
Material
1.17
3675.00
Pre moulded Joint filler, 25 mm thick for expansion joint ('SILFLEX' sqm
CAPCELL HD -100)
kg
Joint sealant
16.33
Sealant primer
kg
875.00
116.67
sqm
46.67
Curing compound
liter
1850.00
2070.00
KL
216.00
Cost of water
419
RBR-CCPV
Index-code
S. No
Description
2
Add 1 per cent of material for cost of miscellaneous materials like
tarpaulin, Hessian cloth, metal cap, cotton / compressible sponge and
cradle for dowel bars, work bridges for men to approach concrete
surface without walking over it, cutting blades and bites, minor
equipments like scabbling machine, threads, ropes, guide wires and
any other unforeseen items.
Unit Quantity
3
Rate
Rs.
Amount
Rs.
Remarks
RBR-CCPV-12
12
Unit = sqm
Taking output = 112.5 sqm
Concrete M30 grade for block, 400 x (0.450 x 0.300 x 0.150) cum
= 8.10
Concrete M30 for edge block, 2 x 50 x (0.300 x 0.300 x 0.150) = 1.35 cum
cum
cum
TOTAL
a) Labour
Labour for Manufacturing the Cement Concrete Block :
Mate
Mazdoor (Unskilled)
Mason (2nd class)
Bhisti
b) Machinery
Concrete mixer 0.28 / 0.4 cum
Plate vibrator
Water tanker 6 kl capacity
c) Material
For CC Blocks M 30
Coarse aggregates (9.45 x 0.90)
Sand (9.450 x 0.45)
Cement
Sand as per Table 1500.5
Bed = 60*0.025 = 1.5 cum
Joints = 1.5*0.15 = 0.225 cum
Cost of water
d) Formwork @ 3% of (a+b+c)
e&f) Overheads & Contractors Profit
Cost for 112.5 sqm = a+b+c+d+e+f
Rate per sqm = (a+b+c+d+e+f)/112.5
day
day
44.10
day
6.00
day
hour
6.00
hour
12.00
hour
2.00
cum
8.505
cum
4.25
3.80
cum
1.73
kl
6.00
Note : 1. In case curing compound is used in places where there is scarcity of water, the water curing will
be used for 4-days and rate analysis will be amended accordingly
2. Carriage of C.C. block to site of is payable separately as per Chapter of carriage of material from
manufacturing site to the site of work.
420
RBR-CCPV
Index-code
RBR-CCPV-13
S. No
Description
13
i
ii
Unit Quantity
3
Rate
Rs.
Amount
Rs.
Remarks
day
day
18.00
day
8.00
hour
2.00
sqm
225.00
120.00
cum
7.23
kl
3.00
Unit = sqm
Taking output = 225 sqm
a) Labour
day
Mate
day
Mazdoor (Unskilled)
day
Mason (2nd class)
b) Machinery
hour
Water tanker 6 kl capacity
c) Material
(i) Providing inter-locking blocks of approved shape, sqm
thickness and size.
m
(ii) Edge blocks 60 mx2
cum
(iii) Sand as per Table 1500.5
kl
(iv) Water
d&e) Overheads & Contractors Profit
Cost for 225 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/225
Note : 1. Carriage of interlocking blocks is payable separately as
per Chapter of carriage of material from manufacturing site to the
site of work.
2. Edge blocks may be cast-in-situ. Brick masonry toe wall or CC
block 300 mm x 300 mm x 150 mm or any other shape can also be
used and their cost shall be analysed/included accordingly
3. The rates for sub-grade, sub-base and base course can be
taken from Chapters 3 and 4
15.90
7.00
2.00
225.00
120.00
5.42
3.00
General Note :
The provisions towards Mate is included in the provision towards unskilled Mazdoor
421
RBR-CWSB
Chapter - 7
CAUSEWAY AND SUBMERSIBLE BRIDGES
Index-Code
RBR-CWSB-1
S. No
Description
1
i
ii
Unit Quantity
3
Rate
Rs.
Amount
Rs.
Remarks
RBR-CWSB-2
RBR-CWSB-3
RBR-CWSB-4
RBR-CWSB-5
5
6
RBR-CWSB-6
RBR-CWSB-7
RBR-CWSB-8
ii
9
10
RBR-CWSB-10
cum
m
cum
cum
cum
cum
cum
cum
cum
Guide Posts
Construction of R.C.C. guide posts of 250 mm dia, M25
grade as per drawing and technical specification Clause
1401.6
RBR-CWSB-9
cum
cum
423
RBR-HLRD
Chapter - 8
HILL ROADS
Index-code
S. No
Description
RBR-HLRD-1
RBR-HLRD-2
Unit Quantity
3
Rate Amount
Rs.
Rs.
5
Remarks
7
Site Clearance
As per Chapter 2
Setting Out
Unit = 1km
The analysis of rate per km shall account for the following:
(1) Construction of reference pillars (burjee) @ 20 m on both
sides as per Fig. 1600.1 (b) and @ 8.33 m interval on curves
1.20
1.20
4.00
3.60
3.60
45.00
0.10
cum
0.10
0.96
425
RBR-HLRD
Index-code
S. No
1
RBR-HLRD-3
Description
Unit Quantity
2
3
Note : 1. The dimensions of reference pillars, back pillars and job pillars
are as per figure/site conditions. The above items are covered under
different Chapters of MORD Specifications for payment.
2. The marking of centre line, setting out, curves, recording of levels,
etc. by the surveyor will be incidental to work and no extra payment shall
be made for the same.
3
i
A
ii
A
Rate Amount
Rs.
Rs.
5
Remarks
7
day
day
62.40
day
0.55
day
day
20.80
hour
6.00
hour
6.00
day
0.55
Note : 1. In case the land on the valley side is barren and there is no
objection for disposing of excavated earth on the valley side, the
provision of front end loader and tipper shall be deleted as excavated
earth shall be disposed off on the valley side.
426
RBR-HLRD
Index-code
S. No
Description
Unit Quantity
3
Unit = cum
Taking output = 260 cum
a) Labour
day
Mate
Mazdoor (Unskilled) for trimming slopes and helping in day
excavation
etc.
b)
Machinery
Dozer 80 HP (D-80 A 12)@ 43.28 cum per hour
Front end loader
Tipper 5.5cum capacity, 4 trips per hour.
c&d) Overheads & Contractors Profit
Cost for 260 cum = a+b+c+d
Rate per cum = (a+b+c+d)/260
hour
Rate Amount
Rs.
Rs.
5
Remarks
7
6.24
6.00
hour
6.00
hour
12.00
Note : In case the land on the valley side is barren and there is no
objection for disposing of excavated earth on the valley side, the
provision of front end loader and tipper shall be deleted as excavated
earth shall be disposed off on the valley side.
iii
Unit = cum
Taking output = 120 cum
a) Labour
Mate
Mazdoor (Unskilled)
b&c) Overheads & Contractors Profit
Cost for 120 cum = (a+b+c)
Rate per cum = (a+b+c)/120
Extra for Every Additional Lift of 1.5 m or Part thereof
For Ordinary Rock
Unit = cum
Taking output = 10 cum
a) Labour
Mazdoor (Unskilled)
b&c) Overheads & Contractors Profit
Cost for 10 cum = (a+b+c)
Rate per cum = (a+b+c)/10
day
5.28
day
132.00
day
0.86
427
RBR-HLRD
Index-code
S. No
Description
2
iv
A
Unit Quantity
3
Rate Amount
Rs.
Rs.
5
Remarks
7
day
day
17.68
day
9.00
hour
6.00
hour
4.25
Note : 1. In case the land on the valley side is barren and there is no
objection for disposing of excavated earth on the valley side, the
provision of front end loader and tipper shall be deleted as excavated
earth shall be disposed off on the valley side.
2. In case, alternative machine like hydraulic excavator 0.9 cum bucket
capacity is necessitude because of site conditions, the same can be
used.
B
8.32
hour
6.00
hour
7.00
hour
7.00
23.36
428
RBR-HLRD
Index-code
S. No
Description
Unit Quantity
3
day
4
2.00
Driller
Blaster
b) Machinery
Dozer D-50 @ 56.67 cum per hour (blasted rock)
day
10.00
hour
3.00
hour
5.00
Air compressor 210 cfm with two jack hammer @ 6 cum/ hour
hour
28.00
c) Material
Gelatin 80 per cent
Electric detonators @ 1 detonator for 1 Gelatin stick of 285
gm each
d&e) Overheads & Contractors Profit
Cost for 170 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/170
Extra for Every Additional Lift of 1.5 m or Part thereof
For Hard Rock
Unit = cum
Taking output = 10 cum
a) Labour
Mazdoor (Unskilled)
b&c) Overheads & Contractors Profit
Cost for 10 cum = (a+b+c)
Rate per cum = (a+b+c)/10
Excavation in hilly areas in hard rock requiring
blasting, by mechanical means including trimming of
slopes and disposal of cut material with all lifts and
lead upto 1000 metres as per Tech Specification 301
MORTH
Unit = cum
Taking output = 170 cum
a) Labour
Mate
Mazdoor (Unskilled)
Driller
Blaster
b)
Machinery
Dozer 80 HP (D-80 A 12)@ 28.32 cum per hour
kg
67.00
nos
235.00
day
1.08
day
day
10.49
day
2.00
day
0.25
hour
6.00
Air compressor 250 cfm with two jack hammer @ 20 cum per hour
hour
hour
Front end loader
5.00
hour
7.00
kg
Rate Amount
Rs.
Rs.
5
Remarks
7
7.00
35.00
140.00
429
RBR-HLRD
Index-code
RBR-HLRD-4
S. No
Description
Unit Quantity
3
Rate Amount
Rs.
Rs.
5
Remarks
7
cum
cum
cum
sqm
cum
cum
RBR-HLRD-5
cum
cum
Rate as per item No. 3 (A) or (B) or (C) of Chapter 12
(vi) Providing P.C.C. M20 architectural coping on top of
wall
m
Rate as per item No. 13 of Chapter 12
Rate per m length (i+ii+iii+iv+v+vi)
Note : 1. Quantities of material/work shall be as per design
and drawings
2. Earth work in excavation may be taken as per site
conditions. It may comprise of a number of sub-items
depending upon the type of soil/rock encountered.
430
RBR-HLRD
Index-code
RBR-HLRD-6
S. No
Description
Unit Quantity
3
Rate Amount
Rs.
Rs.
5
Remarks
7
cum
cum
cum
cum
cum
Rate as per item No. 3 (A) or (B) or (C) of Chapter 12
(vi) Providing P.C.C. M20 architectural coping on top of
wall
m
Rate as per item No. 13 of Chapter 12
Rate per m length (i+ii+iii+iv+v+vi)
Note : 1. Quantities of material/work shall be as per design
and drawings
2. Earth work in excavation may be taken as per site
conditions. It may comprise of a number of sub-items
depending upon the type of soil/rock encountered.
RBR-HLRD-7
Construction of Scupper
Construction of scupper with dry stone masonry as per
drawing and technical specifications as per Clause 1606.5.
Unit = 1 m
Taking output = 6 m
Earthwork in excavation for structures as per drawing
and technical specifications
Quantity for 6 m formation width of hill side rock cutting and
foundation as per plate No. 7.27 of Rural Road Manual
ii
cum
115.00
day
day
38.00
day
60.80
cum
nos
35.72
6.08
431
RBR-HLRD
Index-code
S. No
Description
2
iii
iv
ii
iii
iv
RBR-HLRD-9
day
day
6.00
day
12.72
nos
1335.00
day
day
3.12
cum
12.00
Rate Amount
Rs.
Rs.
5
Remarks
7
RBR-HLRD-8
Unit Quantity
cum
cum
sqm
day
day
3.18
432
RBR-HLRD
Index-code
RBR-HLRD-10
S. No
Description
10
Unit Quantity
3
day
4
1.50
Rate Amount
Rs.
Rs.
5
Remarks
7
100.00
22.50
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Water tanker including watering for 3 months
Tractor with Trolley
c) Material
Farmyard manure @ 0.18 cum per 100 sqm at site of work
RBR-HLRD-11
11
Water
d&e) Overheads & Contractors Profit
Cost for 100 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/100
Seeding and Mulching
Preparation of seed bed on previously laid top soil,
furnishing and placing of seeds, fertilizer, multching
material, applying bituminous emulsion at the rate of 0.23 l
per sqm and laying and fixing jute netting, including
watering for 3 months as per clause 310 & 1600 MORD.
day
day
4.16
hour
4.00
hour
1.00
cum
0.18
kl
24.00
Unit = sqm
Taking output = 240 sqm
a) Labour
day
Mate
day
Mazdoor (Unskilled)
b) Machinery
Water tanker 6 kl capacity including watering for 3 months hour
(for one hour per week)
Tractor with Trolley
c) Material
Seeds
Sludge / Farm yard manure @ 0.18 cum per 100 sqm
Bitumen Emulsion
Jute netting, open weave, 25 mm square opening
Water for 3 months
d&e) Overheads & Contractors Profit
Cost for 240 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/240
15.60
13.00
hour
2.40
kg
3.60
cum
t
0.43
0.06
sqm
264.00
kl
84.00
General Note :
The provisions towards Mate is included in the provision towards unskilled Mazdoor.
433
RBR-PCVT
Chapter - 9
PIPE CULVERTS
Index-code
RBR-PCVT-1
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
RBR-PCVT-2
RBR-PCVT-3
1.00
1.00
Unit = m
Taking output = 7.5 m
(3 pipes of 2.5 m length each)
A 1200 mm dia
a) Labour
day
Mate
day
Mason (1st Class)
day
Mazdoor (Unskilled)
Laying & fixing of Pipes with colors in position including rm
lifting, aligning etc.,
b) Material
cum
Sand at site
t
Cement at site
m
RCC pipe NP3 pipe including collar at site
Handling loading and unloading on (b)
c&d) Overheads & Contractors Profit
Cost for 7.5 m = a+b+c+d
Rate per m = (a+b+c+d)/7.5
0.50
3.14
0.05
0.07
7.50
435
RBR-PCVT
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
RBR-PCVT-4
1000 mm dia
a) Labour
day
Mate
day
Mason (1st Class)
day
Mazdoor (Unskilled)
Laying & fixing of Pipes with colors in position including rm
lifting, aligning etc.,
b) Material
cum
Sand at site
t
Cement at site
m
RCC pipe NP3 pipe including collar at site
c&d) Overheads & Contractors Profit
Cost for 7.5 m = a+b+c+d
Rate per m = (a+b+c+d)/7.5
750 mm dia
a) Labour
day
Mate
day
Mason (1st Class)
day
Mazdoor (Unskilled)
Laying & fixing of Pipes with colors in position including rm
lifting, aligning etc.,
b) Material
cum
Sand at site
t
Cement at site
m
RCC pipe NP3 pipe including collar at site
c&d) Overheads & Contractors Profit
Cost for 7.5 m = a+b+c+d
Rate per m = (a+b+c+d)/7.5
Note : The labour rate for 600 mm dia Hume pipe may be
derived from the rates for 750 dia by decreasing 20 per cent
Providing and Laying Reinforced Cement Concrete
Pipe NP4 as per design.
Providing and laying reinforced cement concrete pipe NP4
for culverts on first class bedding of granular material
including fixing collar with cement mortar 1:2 but
excluding excavation, protection works, backfilling,
concrete and masonry works in head walls and parapets
as per Clause 1106 MORD / 2900 MORTH
Unit = m
Taking output = 7.5 m
(3 pipes of 2.5 m length each)
(A) 1200 mm dia
a) Labour
day
Mate
day
Mason (1st Class)
day
Mazdoor (Unskilled)
b) Material
cum
Sand at site
t
Cement at site
m
RCC pipe NP4 pipe including collar at site
cum
Granular material passing 5.6 mm sieve for bedding
c&d) Overheads & Contractors Profit
Cost for 7.5 m = a+b+c+d
Rate per m = (a+b+c+d)/7.5
0.25
2.09
0.04
0.03
7.50
0.15
1.25
0.024
0.018
7.50
0.50
3.14
0.05
0.07
7.50
5.00
436
RBR-PCVT
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
day
day
0.25
day
2.09
cum
0.04
0.03
7.50
cum
4.50
Note : 1. In case of cement cradle bedding, quantity of PCC M15 is to be calculated as per design and
priced separately and added .
2. The rate analysis does not include excavation, cement /masonry works in head walls, backfilling,
protection works and parapet walls. The same are to be calculated as per approved design and drawings
and priced separately on rates available under respective sections.
RBR-PCVT-5
0.15
1.25
0.024
0.018
7.50
0.30
2.51
0.04
0.036
15.00
437
RBR-PCVT
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
RBR-PCVT-6
RBR-PCVT-7
RBR-PCVT-8
RBR-PCVT-9
0.02
0.01
7.50
cum
cum
RBR-PCVT-10
0.94
cum
Rate as per item No. 4 (A) (i) or (ii) of Chapter 11
Brick Masonry Work in cement mortar in foundation of
Head walls complete excluding pointing and plastering
as per drawing and technical specification Clause 1109
0.11
cum
10
11
12
13
sqm
RBR-PCVT-11
sqm
RBR-PCVT-12
RBR-PCVT-13
General Note :
The provisions towards Mate is included in the provision towards unskilled Mazdoor.
438
RBR-TSRA
Chapter - 10
TRAFFIC SIGNS, MARKINGS AND OTHER ROAD APPURTENANCES
Index-code
S. No
1
RBR-TSRA-1
Description
Unit
Quantity
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
day
day
2.00
day
day
1.12
litre
0.70
day
day
day
day
1.25
litre
0.50
cum
0.126
cum
0.126
Hyphens, commas and the like not to be measured and paid for.
0.57
Traffic Signs
A Retro-reflectorised Traffic Signs
i
Unit = each
Taking output = one traffic sign
(i) Excavation for foundation
As per item No. 1 of Chapter 11
(ii) Cement concrete M15 grade
As per item No. 4 (A) (iii) or (iv) of Chapter 11
441
RBR-TSRA
Index-code
S. No
1
Description
Unit
Quantity
sqm
sqm
0.887
0.43
day
day
0.26
kg
19.00
sqm
0.35
sqm
0.156
sqm
0.283
sqm
0.48
sqm
0.27
sqm
0.36
sqm
0.672
hour
0.01
cum
0.126
cum
0.126
day
day
0.26
3.00
(iii) Painting Angle Iron Post with Primer and two coats
of Epoxy Paint as per specifications
As per item No. 9 of this Chapter (or)
Painting Angle Iron Post with Primer and two coats item
6 of this chapter
(a) labour (For fixing at site)
Mate
Mazdoor (Unskilled)
b) Material
Mild steel angle iron 75 x 75 x 6 mm
Add 3 per cent of cost of angle iron towards cost of
fabrication, drilling holes, nuts, bolts etc.
Aluminum sheeting fixed with encapsulated lens type
reflective sheeting of size including lettering and signs as
applicable background with epoxy paint
(i) 900 mm equilateral triangle
OR
(ii) 600 mm equilateral triangle
OR
(iii) 600 mm circular
OR
(iv) 800 mm x 600 mm rectangular
OR
(v) 600 mm x 450 mm rectangular
OR
(vi) 600 mm x 600 mm square
OR
(vii) 900 mm side octagon
(c) Machinery
Tractor with trolley
d&e) Overheads & Contractors Profit
Rate per traffic sign = (i+ii+iii+a+b+c+d+e) (with Epoxy
Paint)
Rate per traffic sign = (i+ii+iii+a+b+c+d+e) (with Enamel
Paint)
ii
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
Unit = each
Taking output = one traffic sign
(i) Excavation for foundation
As per item No. 1 of Chapter 11
(ii) Cement concrete M15 grade
As per item No. 4 (A) (iii) or (iv) of Chapter 11
(a) labour (For fixing at site)
Mate
Mazdoor (Unskilled)
b) Material
50 mm dia GI Pipe 2.85 m long including 5% wastage
Add 3 per cent of cost of GI Pipe towards cost of fabrication,
drilling holes, nuts, bolts etc.
Aluminum sheeting fixed with encapsulated lens type reflective
sheeting of size including lettering and signs as applicable
background with epoxy paint
442
RBR-TSRA
Index-code
S. No
1
Description
Unit
Quantity
3
sqm
4
0.35
sqm
0.156
sqm
0.283
sqm
0.48
sqm
0.27
sqm
0.36
sqm
0.672
hour
0.08
cum
0.126
cum
0.126
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
Unit = each
Taking output = one traffic sign
(i) Excavation for foundation
As per item No. 1 of Chapter 11
(ii) Cement concrete M15 grade
As per item No. 4 (A) (iii) or (iv) of Chapter 11
(iii) Painting two coats including prime coat on concrete surface
with Epoxy Paint as per specifications
0.90
day
day
0.26
cum
0.0285
0.0077
sqm
0.35
sqm
0.156
sqm
0.283
sqm
0.48
sqm
0.27
sqm
0.36
sqm
0.672
hour
0.08
443
RBR-TSRA
Index-code
S. No
1
Rate Amount
Rs.
Rs.
2
3
4
5
6
Note : 1. Any one area of aluminum sheeting given at (i) to (vii) may be adopted as per site requirement
and in accordance with IRC:67.
Description
Unit
Quantity
Remarks
7
2. The rate for excavation, cement concrete M-15, RCC M-15 in Sub-structure, steel re-enforcement
and painting may be taken from respective Chapters.
3. The depth of foundation and quantity of cement concrete in the foundation are indicative. These
may be increased for areas having higher wind velocities like in coastal areas. This is applicable to
all road signs and directions boards.
B Semi Reflective Traffic Signs
cum
0.126
cum
0.126
sqm
0.46
day
day
0.26
kg
kg
12.40
1.06
sqm
0.35
sqm
0.156
sqm
0.283
sqm
0.48
sqm
0.27
sqm
0.36
sqm
0.672
hour
0.08
Note : 1. Any one area of M.S. Sheet given at (i) to (viii) may be adopted as per site requirement and in
accordance with IRC-67.
444
RBR-TSRA
Index-code
S. No
1
RBR-TSRA-3
Rate Amount
Rs.
Rs.
2
3
4
5
6
2. The rate for excavation, cement concrete M-15, and painting may be taken from respective
Chapters.
3. The depth of foundation and quantity of cement in the foundation are indicative. These may be
increased for areas having higher wind velocities like in coastal area. This is applicable to all road
signs and direction boards.
Description
Unit
Quantity
Remarks
7
Direction and Place Identification signs upto 0.9 sqm size board
A Retro-reflectorised Traffic Signs
i
Providing and erecting direction and place identification retroreflectorised sign as per IRC:67 made of encapsulated lens type
reflective sheeting vide Clause 1701.2.3 MORD / 801.3 MORTH,
fixed over aluminum sheeting, 2 mm thick with area not
exceeding 0.9 sqm supported on a mild steel single angle iron
post 75 x 75 x 6 mm firmly fixed to the ground by means of
properly designed foundation with M15 grade cement concrete
450 mm x 450 mm x 600 mm, 600 mm below ground level as per
drawings and Technical Specification Clause 1701 MORD / 801
MORTH
Unit = sqm
Taking output = 0.9 sqm
(i) Excavation for foundation
As per item No. 1 of Chapter 11
(ii) Cement concrete M15 grade
As per item No. 4 (A) (iii) or (iv) of Chapter 11
(iii) Painting Angle Iron Post with Primer and two coats
of Epoxy Paint as per specifications
As per item No. 9 of this Chapter OR
Painting Angle Iron Post with Primer and two coats as
per item 6 of this chapter.
(a) labour (For fixing at site)
Mate
Mazdoor (Unskilled)
b) Material
Mild steel angle iron 75 x 75 x 6 mm
cum
0.126
cum
0.12
sqm
0.887
0.43
day
day
0.21
kg
Aluminum sheeting fixed with encapsulated lens type reflective sqm
sheeting of size 0.90 sqm including lettering and signs as applicable
background with epoxy paint
Add 3 per cent of cost of angle iron towards cost of fabrication,
drilling holes, nuts, bolts, etc.
19
0.9
(c) Machinery
Tractor with trolley
d&e) Overheads & Contractors Profit
hour
0.02
cum
0.126
cum
0.126
Unit = sqm
Taking output = 0.9 sqm
(i) Excavation for foundation
As per item No. 1 of Chapter 11
(ii) Cement concrete M15 grade
As per item No. 4 (A) (iii) or (iv) of Chapter 11
445
RBR-TSRA
Index-code
S. No
1
Description
Unit
Quantity
day
day
0.26
3.00
0.90
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
0.08
(iii) Providing and erecting direction and place identification retroreflectorised sign as per IRC:67 made of encapsulated lens type
reflective sheeting vide Clause 1701.2.3, fixed over aluminum
sheeting, 2 mm thick with area not exceeding 0.9 sqm
supported on RCC Post 100 mm x 100 mm firmly fixed to the
ground by means of properly designed foundation with M15
grade cement concrete 450 mm x 450 mm x 600 mm, 600 mm
below ground level as per drawings and Technical Specification
Clause 1701 MORD.
Unit = sqm
Taking output = 0.9 sqm
(i) Excavation for foundation
As per item No. 1 of Chapter 11
(ii) Cement concrete M15 grade
As per item No. 4 (A) (iii) or (iv) of Chapter 11
cum
0.126
cum
0.126
0.90
day
day
0.26
cum
0.0285
0.0077
sqm
0.90
hour
0.08
Note : 1. Lettering and arrow markings on sign board to be provided separately as per actual
requirement. Rates for these items have been analysed separately.
2. The rate for excavation, cement concrete M15, RCC M15 in Sub-structure, steel re-enforcement
and painting may be taken from respective Chapters.
3. The depth of foundation and quantity of cement concrete in the foundation are indicative. These
may be increased for areas having higher wind velocities like in coastal areas. This is applicable to
all road signs and directions boards.
446
RBR-TSRA
Index-code
S. No
1
Description
2
B Semi-Reflective Traffic signs
Unit
Quantity
cum
0.126
cum
0.126
sqm
0.59
day
day
0.26
kg
kg
12.40
1.06
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
Unit = each
Take Output = 0.9 sqm
(i) Excavation for foundation
As per item No. 1 of Chapter 11
(ii) Cement concrete M15 grade
As per item No. 4 (A) (iii) or (iv) of Chapter 11
(iii) Painting on M.S. tube post with primer and two coat
of epoxy paint as per specifications
As per item No.9 of Chapter 10
(a) labour (For fixing at site)
Mate
Mazdoor (Unskilled)
b) Material
(i) Support of MS sheet tube
47 mm x 47 mm of 12 SWG sheet 3050 mm long
(ii) Angle iron 50 x 50 x 6 mm for lugs including 5% wastage
0.90
0.08
Note : Rate for excavation, cement concrete M15 and painting may be taken from respective
Chapters.
RBR-TSRA-4
Providing and erecting direction and place identification retro\reflectorised sign as per IRC:67 made of encapsulated lens
type reflective sheeting vide Clause 1701.2.3 MORD / 801.3
MORTH, fixed over aluminum sheeting, 2 mm thick with area
exceeding 0.9 sqm supported on mild steel angle iron posts 75
mm x 75 mm x 6 mm, 2 Nos. firmly fixed to the ground by
means of properly designed foundation with M15 grade cement
concrete 450 mm x 450 mm x 600 mm, 600 mm below ground
level as per drawings and Technical Specification Clause 1701
MORD / 801 MORTH
Unit = sqm
Taking output = 1.50 sqm
(i) Excavation for foundation
As per item No. 1 of Chapter 11
(ii) Cement concrete M15 grade
As per item No. 4 (A) (iii) or (iv) of Chapter 11
cum
0.252
cum
0.252
447
RBR-TSRA
Index-code
S. No
1
Description
Unit
Quantity
sqm
sqm
1.774
0.86
day
day
0.31
kg
38.00
sqm
1.50
(iii) Painting Angle Iron Post with Primer and two coats
of Epoxy Paint as per specifications
As per item No. 9 of this Chapter (or)
Painting Angle Iron Post with Primer and two coats (item 6
of this chapter)
(a) labour (For fixing at site)
Mate
Mazdoor (Unskilled)
b) Material
Mild steel angle iron 75 mm x 75 mm x 6 mm, 2.85 m long,
2 nos. with 5 per cent wastage
Aluminum sheeting fixed with encapsulated lens type
reflective sheeting of size including lettering and signs as
applicable background with epoxy paint
Add 2 per cent of cost of angle iron towards cost of
fabrication, drilling holes, nuts, bolts, etc.
(c) Machinery
Tractor with trolley
d&e) Overheads & Contractors Profit
Cost for 1.5 sqm = i+ii+iii+a+b+c+d+e (with epoxy paint)
Rate per sqm (for sign having area more than 0.9 sqm) =
(i+ii+iii+a+b+c+d+e)/1.50
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
2.00%
hour
0.02
cum
0.252
cum
0.252
day
day
0.52
6.00
1.50
Rate per sqm (for sign having area more than 0.9 sqm) =
(i+ii+iii+a+b+c+d+e)/1.50
(ii) Providing and erecting direction and place identification retroreflectorised sign as per IRC:67 made of encapsulated lens type
reflective sheeting vide Clause 1701.2.3, fixed over aluminum
sheeting, 2 mm thick with area exceeding 0.9 sqm supported on
dia GI Pipe firmly fixed to the ground by means of properly
designed foundation with M15 grade cement concrete 450 mm x
450 mm x 600 mm, 600 mm below ground level as per drawings
and Technical Specification Clause 1701 MORD.
Unit = sqm
Taking output = 1.50 sqm
(i) Excavation for foundation
As per item No. 1 of Chapter 11
(ii) Cement concrete M15 grade
As per item No. 4 (A) (iii) or (iv) of Chapter 11
(a) labour (For fixing at site)
Mate
Mazdoor (Unskilled)
b) Material
50 mm dia GI Pipe 2.85 m long including 5 per cent wastage
0.12
448
RBR-TSRA
Index-code
S. No
1
Description
2
(iii) Providing and erecting direction and place identification retroreflectorised sign as per IRC:67 made of encapsulated lens type
reflective sheeting vide Clause 1701.2.3, fixed over aluminum
sheeting, 2 mm thick with area exceeding 0.9 sqm supported on
RCC Posts 100 mm x 100 mm firmly fixed to the ground by
means of properly designed foundation with M15 grade cement
concrete 450 mm x 450 mm x 600 mm, 600 mm below ground
level as per drawings and Technical Specification Clause 1701
MORD.
Unit = sqm
Taking output = 1.50 sqm
(i) Excavation for foundation
As per item No. 1 of Chapter 11
(ii) Cement concrete M15 grade
As per item No. 4 (A) (iii) or (iv) of Chapter 11
(iii) Painting two coats including prime coat on concrete
surface with Epoxy Paint as per specifications
As per item No. 9 of this Chapter
(a) labour (For fixing at site)
Mate
Mazdoor (Unskilled)
b) Material
RCC M15 Grade in Sub-structure
As per item No.12.5 of Chapter 12
Steel reinforcement HYSD bars
As per item No.12.6 of Chapter 12
Aluminum sheeting fixed with encapsulated lens type
reflective sheeting of size including lettering and signs as
applicable background with epoxy paint
Unit
Quantity
cum
0.252
cum
0.252
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
1.00
day
day
0.52
cum
0.057
t
sqm
0.0154
1.50
0.12
Note : 1. Lettering and arrow markings on sign boards to be provided separately as per actual
requirement. Rates for these items have been analysed separately.
2. The rate for excavation, cement concrete M15, RCC M15 in Sub-structure, steel re-enforcement and
painting may be taken from respective Chapters.
3. The depth of foundation and quantity of cement concrete in the foundation are indicative. These may be
increased for areas having higher wind velocities like in coastal areas. This is applicable to all road signs
and directions boards.
449
RBR-TSRA
Index-code
S. No
1
Description
2
B Semi-Reflective Traffic signs
Unit
Quantity
cum
0.252
cum
0.252
sqm
0.92
day
day
0.52
kg
24.80
kg
2.12
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
Unit = each
Taking output = 1.5 sqm
(i) Excavation for foundation
As per item No. 1 of Chapter 11
(ii) Cement concrete M15 grade
As per item No. 4 (A) (iii) or (iv) of Chapter 11
(iii) Painting M.S. tube posts with primer and two coats
of epoxy paint as per specification
As per item No. 9 of chapter 10
(a) labour (For fixing at site)
Mate
Mazdoor (Unskilled)
b) Material
(i) Support of MS Sheet tubes 47 mm x 47 mm x 12 SWG
sheet 3050 mm long
(ii) Angle iron 50 mm x 50 mm x 6 mm for lugs
1.50
0.16
Note : Rate for excavation cement concrete M15 and painting may be taken
from respective chapter
RBR-TSRA-5
Overhead Signs
Providing and erecting overhead signs with a corrosion resistant
2mm thick aluminum alloy sheet reflectorised with high intensity retroreflective sheeting of encapsulated lense type with vertical and
lateral clearance given in clause 802.2 and 802.3 and installed as
per clause 802.7 over a designed support system of aluminum alloy
or galvanised steel trestles and trusses of sections and type as per
structural design requirements and approved plans as per clause
802 MORTH
A Truss and Vertical Support
Unit = tonne
Taking output = 1 tonne
a) Labour
Mate
day
Blacksmith
day
2.00
day
4.24
450
RBR-TSRA
Index-code
S. No
1
Description
Unit
Quantity
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
b) Material
tonne
Aluminum alloy / galvanised steel including 5% wastage
Add 1 per cent on cost of material for nuts, bolts and drilling
and welding consumables
1.05
hour
3.00
Truck
hour
0.50
Unit = sqm
Taking output = 1 sqm
a) Labour
Mate
day
Blacksmith
day
0.10
Mazdoor
day
0.17
1.00
b) Material
Miscellaneous
Add 1 per cent of cost of labour for lifting arrangement, like
ladders, pulleys, ropes etc
c&d) Overheads & Contractors Profit
Rate per sqm = (a+b+c+d)
Note : 1. The cost of excavation and foundation concrete for fixing of vertical support system to be
worked out separately as per the approved drawing/design and to be included in the estimate.
2. Lettering and arrow marks on sign board to be provided separately as per actual requirement. Rates for
these items have been included separately in this chapter.
RBR-TSRA-6
6
i
day
day
day
day
3.00
litre
litre
3.00
6.00
2.000
1.120
2.20
451
RBR-TSRA
Index-code
S. No
1
b)
Description
Unit
Quantity
Litre
6.000
7
i
day
day
day
0.25
0.60
0.40
litre
litre
0.60
1.25
day
day
day
0.45
0.28
Litre
1.25
day
day
day
0.60
0.65
litre
litre
0.60
1.25
Amount
Rs.
6
Remarks
7
Material
RBR-TSRA-7
Rate
Rs.
5
Unit = sqm
Taking output = 10 sqm
a)Labour
Mate
Painter (1st Class)
Mazdoor (Unskilled)
b) Material
Red-oxide Primer as per specifications
Paint ready mixed approved brand
Add @ 1 per cent on cost of material for scaffolding
wherever required
c&d) Overheads & Contractors Profit
Cost for 10 sqm = a+b+c+d
Rate per sqm = (a+b+c+d)/10
452
RBR-TSRA
Index-code
S. No
1
Description
2
iv Providing and applying two coats of ready mix paint
Unit
Quantity
day
day
day
0.45
0.28
Litre
1.25
day
day
day
0.50
0.23
litre
litre
0.60
1.5
1.00%
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
RBR-TSRA-8
8
i
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate
Painter
Mazdoor
b)
Material
Paint ready mixed approved brand.
Add @ 1 per cent on cost of material for scaffolding
c&d) Overheads & Contractors Profit
Cost for 10 sqm = a+b+c+d
Rate per sqm= (a+b+c+d)/10
Painting on Wood Surfaces
Providing and applying two coats of ready mix paint
including primer coat of approved brand on wood surface
after through cleaning of surface to give an even shade as
per drawing and Technical Specification Clause 803
MORTH
Unit = sqm
Taking output = 10 sqm
a)Labour
Mate
Painter (1st Class)
Mazdoor (Unskilled)
b) Material
Red-oxide Primer as per specifications
Paint ready mixed approved brand
Add @ 1 per cent on cost of material for scaffolding
wherever required
Add @ 5 per cent on cost of labour & materials to prepare the
surface by filling minutes roughness on the surface and priming the
surface before laying 2 coats of painting.
5.00%
day
day
day
litre
0.50
0.23
1.5
1.00%
453
RBR-TSRA
Index-code
S. No
1
RBR-TSRA-9
Description
Unit
Quantity
day
day
day
0.60
0.65
litre
litre
0.60
1.25
day
day
day
day
day
0.35
litre
1.48
day
day
day
day
day
0.55
litre
1.48
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
RBR-TSRA-10
10
1.42
1.64
454
RBR-TSRA
Index-code
S. No
1
RBR-TSRA-11
11
Description
Unit
Quantity
day
day
day
0.30
1.31
litre
0.90
day
day
day
0.35
1.42
litre
0.90
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
RBR-TSRA-12
Unit = sqm
Taking output = 600 sqm
a) Labour
day
Mate
day
0.78
Mazdoor
b) Machinery
hour
10.00
Road marking machine @ 60 sqm per hour
hour
0.50
Tractor-trolley
c) Material
Litre 1500.00
Hot applied thermoplastic compound
kg
150.00
Reflectorising glass beads
d&e) Overheads & Contractors Profit
Cost for 600 sqm = a+b+c+d+e
Rate per sqm = a+b+c+d+e)/600
Note : 1. A sealing primer may be applied in advance on cement concrete pavement to
ensure proper bonding. Any laitance and/or curing compound to be removed where paint is
required to be applied on concrete surface.
2. Cost of painter is already included in hire charges of road marking machine.
455
RBR-TSRA
Index-code
RBR-TSRA-13
S. No
Description
Unit
Quantity
13
Kilometre Stone
Reinforced cement concrete M15 grade kilometre
stone/local stone of standard design as per IRC:8 fixing in
position including painting and printing, etc as per drawing
and Technical Specification Clause 1703 MORD / 804
MORTH
(i) 5th Kilometre Stone (precast)
Unit = each
Taking output = 6 Nos.
a) M-15 grade of concrete
cum
As per item No. 5 (i) or (ii) of Chapter 12
b) Steel reinforcement @ 5 kg per sqm
kg
As per item No. 6 of Chapter 12
c) Excavation in soil for foundation
cum
As per item No. 1 of Chapter 11
d) Painting two coats on concrete surface
sqm
As per item No.5 of Chapter 10
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
2.35
22.08
1.68
9.85
per
cm
high
per
letter
1800.00
day
day
day
0.60
6.26
hour
6.00
cum
3.77
kg
26.32
cum
2.77
sqm
11.41
per
cm
high
per
letter
1680.00
day
day
day
1.00
7.32
hour
6.00
456
RBR-TSRA
Index-code
S. No
1
Description
2
(iii) 200 m / Hectometer stone (precast)
Unit = each
Taking output = 33 Nos.
a) M-15 grade of concrete
As per item No. 5 (i) or (ii) of Chapter 12
b) Steel reinforcement @ 5 kg per sqm
As per item No. 6 of Chapter 12
c) Excavation in soil for foundation
As per item No. 1 of Chapter 11
d) Painting two coats on concrete surface
As per item No.5 of Chapter 10
Unit
Quantity
cum
1.58
kg
66.00
cum
1.39
sqm
6.27
per
cm
high
per
letter
330.00
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
RBR-TSRA-14
14
Unit = Each
Taking output= 30 Nos.
a) Labour
day
Mate
day
Mazdoor for fixing
b) Material
Cost of approved type of delineators from ISI certified firm each
as per the standard drawing given in IRC - 79
Add 10 per cent cost of material for installation
c&d) Overheads & Contractors Profit
Cost for 30 Nos. delineators = (a+b+ c+d)
Rate per delineators = (a+b+c+d) /30
RBR-TSRA-15
15
1.04
30.00
Note : In case of soft ground, a proper foundation may be provided as per approved
design. In case foundation is required to be provided, the items of excavation and
foundation concrete are required to be measured and paid separately.
Boundary Pillar
Reinforced cement concrete M15 grade boundary pillars/local stone
of standard design as per IRC:25, fixed in position including finishing
and lettering but excluding painting as per drawing and Technical
Specification Clause 1704 MORD / 806 MORTH
Unit = each
Taking output = 57 Nos.
a) M-15 grade of concrete
As per item No. 5 (i) or (ii) of Chapter 12
cum
1.25
457
RBR-TSRA
Index-code
S. No
1
Description
Unit
Quantity
kg
79.80
cum
10.72
per
letter
per
cm
high
2280.00
day
day
14.82
hour
6.00
cum
11.97
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
RBR-TSRA-16
16
i
2. In case local stone is to be used in place of precast RCC stones, then rate of cement
concrete and steel reinforcement may be deleted.
G.I Barbed Wire Fencing 1.2 m high
Providing and fixing 1.2 m high GI barbed wire fencing with
1.8 m RCC posts 150 mm x 150 mm placed every 3 m
centre-to-centre founded in M15 grade cement concrete, 0.6
m below ground level, every 15th post, last but one end post
and corner post shall be strutted on both sides and end post
on one side only and provided with 9 horizontal lines and 2
diagonals interwoven with horizontal wires, fixed with GI
staples, turn buckles etc., complete as per Clause 1705
MORD.
Unit = per running m
Taking output = 30 m
a)Labour
day
Mate
day
0.25
Blacksmith
day
2.09
Mazdoor (Unskilled)
b) Machinery
kg
31.42
Barbed wire 335 m length @ 9.38 kg per 100 m
R.C.C. Post 150 mm x 150 mm x 1.80 m M15 Grade
concrete 13 x 150 mm x 150 mm x 1.8 m
cum
0.526
As per item No. 5 (i) or (ii) of Chapter 12
Add 5 per cent extra cost for formwork of M-15
Supply of HYSD Bars including cutting, bending, tying &
placing in position.
10 mm dia HYSD bars for posts
13 x 4 x 1.8 = 93.6 m @ 0.62 kg/mt = 43.60 kg
8 mm dia HYSD bars for rings
13 x 10 x 0.6 = 78 m @ 0.39 kg/mt = 30.42 kg
Total = 74.02 Kgs
As per item No. 6 of Chapter 12
Add for GI staple binding wire, drilling holes, etc. @ 2 per
cent of the cost of material
0.074
458
RBR-TSRA
Index-code
S. No
1
Description
Unit
Quantity
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
c) Painting
Applying two coats of painting including primer coat on
exposed surface of RCC posts
sqm
8.14
As per item No. 6 of this Chapter
d&e) Overheads & Contractors Profit
Cost for 30 m fencing = a+b+c+d+e
Rate per m = (a+b+c+d+e)/30
Note : Cost of excavation for foundation and foundation concrete to be added separately in
the cost estimate as per approved design. The rate for these items may be taken from
respective Chapters.
ii G.I Barbed Wire Fencing 1.8 m high
Providing and fixing 1.8 m high GI barbed wire fencing with
2.4 m RCC M15 grade 150 mm x 150 mm concrete post
placed every 3 m centre-to-centre founded in M15 grade
cement concrete, 0.6 m below ground level, every 15th
post, last but one end post and corner post shall be strutted
on both sides and end post on one side only and provided
with 9 horizontal lines and 2 diagonals interwoven with
horizontal wires, fixed with GI staples, turn buckles etc.
complete as per Clause 1705 MORD.
Unit = per running m
Taking output = 30 m
a)Labour
day
Mate
day
0.40
Blacksmith
day
2.62
Mazdoor (Unskilled)
b) Machinery
kg
40.15
Barbed wire 428 m length @ 9.38 kg per 100 m
R.C.C. Post 150 mm x 150 mm x 2.4 m High M-15 Grade
13 x 150 mm x 150 mm x 2.4 m
cum
0.702
As per item No. 5 (i) or (ii) of Chapter 12
Add 5 per cent extra cost of C.C. for formwork of M-15
Supply of HYSD Bars including cutting, bending, tying &
placing in position.
10 mm dia HYSD bars for posts 13 x 4 x 2.4 = 124.80 m
@ 0.62 kg/mt =
77.38 kg
8 mm dia HYSD bars for rings
13 x 11 x 0.6 =
85.80 m
@ 0.39 kg/m =
33.46 kg
Total = 110.84 Kgs
t
0.111
As per item No. 6 of Chapter 12
Add for GI staple, binding wire, drilling holes etc. @ 2 per
cent of the cost of material
c) Painting
Applying two coats of painting including primer coat on
exposed surface of RCC posts
sqm
12.10
As per item No. 6 of this Chapter
d&e) Overheads & Contractors Profit
Cost for 30 m fencing = a+b+c+d+e
Rate per m fencing = (a+b+c+d+e)/30
Note : Cost of excavation for foundation and foundation concrete to be added separately in
the cost estimate as per approved design. The rate for these items may be taken from
respective Chapters.
459
RBR-TSRA
Index-code
S. No
1
Description
2
iii G.I Barbed Wire Fencing 1.2 Metre High
Unit
Quantity
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
day
day
0.40
day
2.62
kg
40.15
kg
152.00
sqm
3.96
460
RBR-TSRA
Index-code
S. No
1
RBR-TSRA-17
17
Description
Unit
Quantity
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
RBR-TSRA-18
18
cum
1.296
cum
0.648
sqm
4.71
sqm
2.16
day
day
day
0.26
0.01
461
RBR-TSRA
Index-code
S. No
1
RBR-TSRA-19
19
Description
Unit
Quantity
b) Material
m
Steel pipe 50 mm external dia as per IS:1239
Medium weight steel channel (ISMC series) 100 mm x 50 kg
mm, 10.8 m length @ 9.2 kg per m
Add for drilling holes @ 3 per cent of cost of channels
c) Machinery
hour
50 HP Tractor with trolley
d&e) Overheads & Contractors Profit
Cost for 10 m = a+b+c+d+e
Rate per m = (a+b+c+d+e)/10
Tubular Steel Railing on Precast RCC posts, 1.2 m high
above Ground Level
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
30.00
99.36
0.04
Unit = Running m
Taking output = 10 m
i) Excavation for foundation (6 Nos.) 6 x 0.6 x 0.6 x 0.6
As per item No. 1 of Chapter 11
cum
1.296
cum
0.648
cum
0.32
sqm
4.71
day
day
day
0.364
0.01
m
t
30.00
0.032
hour
0.25
cum
0.252
cum
0.252
20
Unit = Each
Taking out put = one typical board
i) Excavation for foundation
As per item No. 1 of Chapter 11
(ii) Cement Concrete M15 grade
As per item No. 4 (A) (iii) or (iv) of Chapter 11
462
RBR-TSRA
Index-code
S. No
Description
Unit
Quantity
2
(iii) Painting on MS Steel tubes with primer and two coats of
epoxy paint
sqm
1.80
2x2.05x.30 = 1.23
1x1.10x188 = 0.21
As per item no. 9 of Chapter 10
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
(iv) Printing new letters and figures of any shade with synthetic
enamel paint black or any other approved colour to give an
even shade.
per
4532.50
cm
height
/
letter
day
day
0.78
kg
kg
kg
63.15
4.47
2.12
1.44
c) Machinery
hour
0.24
Tractor with trolley
d&e) Overheads & Contractors Profit
Cost for one Board= (i+ii+iii+iv+a+b+c+d+e)
Printing and lettering for blank spaces on the lower plate will be written as required and paid
separately.
Items Suggested by MORTH
RBR-TSRA-21
21
Traffic Cone
Provision of red fluorescent with white reflective sleeve
traffic cone made of Low Density Polyethylene (LDPE)
material with a square base of 390 x 390 x 35 mm and a
height of 770 mm, 4 kg in weight, placed at 1.5 m interval,
all as per BS:873
Unit = Each
Taking output = 68 Nos.
a) Labour
Mate
Mazdoor (Unskilled)
b) Material
Traffic cones with 150 mm reflective sleeve
c) Machinery
50 HP Tractor with trolley
d&e) Overheads & Contractors Profit
Cost for 68 Nos. = a+b+c+d+e
Rate for each cone = (a+b+c+d+e)/68
day
day
0.52
Nos.
68.00
Hour
0.10
463
RBR-TSRA
Index-code
S. No
Description
Unit
Quantity
cum
cum
cum
cum
sqm
2.50
day
day
day
day
1.09
1.00
0.25
metre
metre
kg
3.50
10.00
8.00
hour
0.50
RBR-TSRA-22
22
RBR-TSRA-23
23
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
Roadside Amenities
Rest areas
Providing plainly furnished accommodation for rest rooms,
dormitories, restaurants, stalls, shops, petrol pump, telephone booth,
first aid room, traffic aid post, police assistance booth, including
electricity, toilet and sewerage system
Pricing may be done based on current plinth area rates approved by
PWD/CPWD/MES for a particular zone. Area is required to be
assessed for specific location as per actual site conditions
light vehicles
Pricing of parking areas may be done for the quantities of various
items based on the approved dimensions and pavement design for a
particular terrain and soil. Rates for items may be from respective
chapters.
C Lawn
24
Policeman Umbrella
Provision of a 2 m high (floor to roof) umbrella for traffic policeman at
road crossings, where necessary, installed on a raised platform, built
on a central support of a steel pipe 100 mm dia, roof made of 25 mm
dia steel pipe to provide covered area of 3 sqm, roofed with CGI
sheets, all steel parts to be given 2 coats of paint
Unit = each
Taking output = one number
Quantities of these items to be
Earthwork
calculated as per approved design
Cement Concrete
and cost added as per rates of
these items given in chapter 3 and
brick masonry or
13
stone masonry
Painting
a) Labour
Mate
Mazdoor
Blacksmith
Welder
b)
Material
Steel pipe 100 mm dia
Steel pipe 25 mm dia
CGI sheets
Add 25 per cent of cost of material for fabrication
Add 2 percent of cost of material for welding consumables,
J-hooks, washers etc.
c)
Machinery
Tractor-trolley
d&e) Overheads & Contractors Profit
Rate per policeman umbrella = a+b+c+d+e
464
RBR-TSRA
Index-code
S. No
Description
Unit
Quantity
RBR-TSRA-25
25
RBR-TSRA-26
26
Toll Plaza
The construction, operation and maintenance of Toll Plaza
can be broken into separate items of work as under based
on the approved design and drawings:-
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
a)
Provision of toll collection service lane to separate
different categories of vehicles for purpose of toll collection.
This involves considerable increase in carriage way width
b)
Provision of 2.5 m wide separators for different toll
collection service lanes for safety
c)
Toll booths with integrated roof cover
d)
Barrier gates for individual lanes
e)
Provision of building to provide facility to toll plaza
personnel
f)
Toll plaza office equipment and furniture
g)
Water supply, electricity, sanitation, septic-tank
system and drainage
h)
Telephone, intercomes, wireless communication
system
i)
High mast lighting
j) Pavement marking
k) Overhead signs
l) Fixed message signs (Advance)
m) Variable message signs
n) Traffic cones and pylons
o) First aid post
p) Traffic aid post and security
The quantities for the above mentioned items may be
calculated from the approved design and drawings and their
rates adopted from respective chapters of the Standard
Data Book
465
RBR-TSRA
Index-code
S. No
1
RBR-TSRA-27
27
Description
Unit
Quantity
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
RBR-TSRA-28
28
1.04
466
RBR-TSRA
Index-code
S. No
Description
Unit
Quantity
RBR-TSRA-29
29
b) Material
Nos.
Aluminum studs 100x100 mm fitted with lense reflectors
Add 10 per cent of cost of material for fixing and installation.
c&d) Overheads & Contractors Profit
Cost for 50 studs = a+b+c+d
Rate per stud = (a+b+c+d)/50
Cast in Situ Cement Concrete M20 Kerb
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
50.00
Cement Concrete
Cement concrete of grade M20 = 12.60 cum
Cement concrete of grade M10 for base= 11.61 cum
Total Concrete = 24.21 cu.m
a)
Labour
Mate
day
Mason
day
2.00
Mazdoor
day
16.72
b)
Machinery
hour
6.00
hour
12.00
hour
5.00
cum
21.79
cum
10.90
c)
Material
5.70
KL
30.00
Cement Concrete
Cement concrete of grade M20 = 12.60 cum
Cement concrete of grade M10 for base = 11.61 cum
Total Concrete = 24.21 cu.m
a)
Labour
Mate
day
Mason
day
1.00
Mazdoor
day
2.12
hour
6.00
hour
1.60
hour
5.00
hour
6.00
cum
cum
t
21.79
10.90
5.70
b)
c)
Machinery
Material
467
RBR-TSRA
Index-code
S. No
Description
Unit
Quantity
3
KL
4
30.00
Cost of water
RBR-TSRA-30
30
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
Labour
Mate
day
Mason
day
2.00
Mazdoor
day
16.72
6.00
b)
Machinery
t
KL
16.00
6.00
36.59
18.30
9.01
36.00
Labour
Mate
day
Mason
day
1.00
Mazdoor
day
2.12
6.00
hour
6.00
hour
6.00
cum
36.59
cum
18.30
b)
c)
Machinery
2.70
Material
468
RBR-TSRA
Index-code
S. No
Description
Unit
Quantity
3
t
4
9.01
KL
36.00
cum
3.00
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
31
Labour
Mate
day
Mazdoor
day
1.04
0.28
sqm
0.32
c)
Material
RBR-TSRA-32
32
Note : i) Excavation and backfilling are incidental to work and not to be measured
separately.
ii) Rate for RCC M 20 may be taken from chapter on super structure.
Metal Beam Crash Barrier
A Type - A, "W" : Metal Beam Crash Barrier
Labour
Mate
day
Blacksmith
day
0.50
Mazdoor
day
1.06
hour
0.10
kg
41.21
kg
88.56
kg
16.24
kg
20.00
b)
Machinery
Tractor-trolley
c)
Material
469
RBR-TSRA
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
Labour
Mate
day
Blacksmith
day
0.50
Mazdoor
day
1.06
hour
0.10
kg
72.94
kg
98.40
kg
kg
26.86
30.00
b)
Machinery
Tractor-trolley
c)
Material
Note : In the case of median crash barrier, 'W' metal beam or thrie beam section should be provided on
both sides of the vertical posts fixed in the median. Extra provision for metal beam railing and spacer is
required to be made when fixed in the median depending on approved design.
RBR-TSRA-33
33
RBR-TSRA-34
34
day
day
2.12
470
RBR-TSRA
Index-code
S. No
Description
Unit
Quantity
3
day
4
1.00
kg
190.00
kg
kg
46.00
Blacksmith
b) Material
i) RS Joist 100 x 75 mm - 16.5 m @ 11.5 kg per metre
ii) Struts - 2 Nos. for terminal posts,2 m long each 2 x 2 x 11.50
RBR-TSRA-35
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
188.40
iii) Tie 2 Nos. of 8 mm steel plate,1.5 sqm each for terminal
posts @ 62.80 kg/sqm (2 x 1.5)
65.00
iv) Steel wire rope 40 mm, including 7.50 per cent extra for kg
fixing at ends 15 x 4 x 1.075 @ 1 kg per m
Add 5 per cent of cost of material for drilling, gripping,
fixing, fabrication and welding consumables
c)
Painting
sqm
16.50
Applying 2 coats of painting on exposed surface
d)
Machinery
hour
0.25
Tractor-trolley
e&f) Overheads & Contractors Profit
Cost for 15 m = a+b+c+d+e+f
Rate per m = (a+b+c+d+e+f)/15
Note : The items of excavations and cement concrete works will
be measured and included separately as per the approved designs
and drawings.
35 8.3 Anti-Glare Devices in Median
A Plantation
Plantation of shrubs and plants of approved species in the median.
apart from cutting off glare from vehicle coming from opposite
direction, these plants provide a pleasant environment and are ecofriendly. The rate for this item is available in the chapter 11 on
horticulture.
B Anti-glare screen with 25 mm steel pipe framework fixed with
circular and rectangular vans
Providing and erecting an anti - glare screen with 25 mm dia
vertical pipes fabricated and framed in the form of panels of one
metre length and 1.75 metre height fixed with circular vane 250
mm dia at top and rectangular vane 600 x 300 mm at the middle,
made out of steel sheet of 3 mm thickness, end vertical pipes of
the panel made larger for embedding in foundation concrete,
applying 2 coats of paint on all exposed surfaces, all as per
approved design and drawings.
Labour
Mate
day
Mazdoor
day
0.104
metre
16.00
kg
4.32
kg
4.80
sqm
1.83
b)
Material
i) 25 mm steel pipe
ii) MS sheet for 600 x 300 x 3 mm rectangular vane, one
number @ 24kg/sqm
iii) MS sheet for 250 mm dia circular vane 3 mm thick, 4
numbers @ 24 kg/sqm
Add 5 per cent cost of material for fabrication, welding,
bending, nuts, bolts etc
c)
Painting
Applying 2 coats of painting on exposed surface
d&e) Overheads & Contractors Profit
Rate per metre = a+b+c+d+e
471
RBR-TSRA
Index-code
S. No
1
Description
2
C Anti-glare screen with rectangular vane of MS sheet
Unit
Quantity
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
Labour
Mate
day
Mazdoor
day
0.104
kg
kg
10.58
9.00
hour
0.10
sqm
0.85
b)
Material
c)
Machinery
Tractor-trolley
d)
Painting
RBR-TSRA-36
36
Street Lighting
Providing and erecting street light mounted on a steel circular hollow
pole of standard specifications for street lighting, 9 m high spaced 40
m apart, 1.8 m overhang on both sides if fixed in the median and on
one side if fixed on the footpath, fitted with sodium vapour lamp and
fixed firmly in concrete foundation.
Unit = Each
Taking output = one light
a) Labour
Mate
Mazdoor
Electrician
day
day
day
0.53
0.25
1.00
b)
Material
1.00
5.75
4.63
472
RBR-TSRA
Index-code
S. No
Description
Unit
Quantity
RBR-TSRA-37
37
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
Lighting on Bridges
Providing and fixing lighting on bridges, mounted on steel
hollow circular poles of standard specifications, 5 m high
fixed on parapets with cement concrete, 20 m apart and
fitted with sodium vapour lamp
Unit = Each
Taking output = one light
a)
Labour
Mate
day
Mazdoor
day
0.42
Electrician
day
0.20
1.00
b)
Material
1.00
RBR-TSRA-38
2.76
38
2.36
Labour
Mate
day
Mazdoor
day
1.00
Mazdoor skilled
day
0.30
metre
20.00
c)
Material
Granular soil with PI less than 6 for bedding and sides of cum
pipe (0.6 x 0.6 x 20 m)
7.20
each
9.00
cum
0.02
hour
0.50
d)
Machinery
Tractor-trolley
e&f) Overheads & Contractors Profit
Cost for 20 metre = a+b+c+d+e+f
Rate per metre = (a+b+c+d+e+f)/20
473
RBR-TSRA
Index-code
S. No
Description
Unit
Quantity
1
ii
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
3.37
Labour
Mate
day
Mazdoor
day
2.00
Mazdoor skilled
day
0.30
metre
40.00
c)
Material
Granular soil with PI less than 6 for bedding and sides of cum
pipe (0.6 x 0.6 x 40 m)
14.40
each
18.00
cum
0.04
hour
1.00
4.38
d)
Machinery
Tractor-trolley
e&f) Overheads & Contractors Profit
Cost for 20 metre = a+b+c+d+e+f
Rate per metre = (a+b+c+d+e+f)/20
iii Triple Row for three utility services
b)
Labour
Mate
day
Mazdoor
day
3.00
Mazdoor skilled
day
1.16
metre
60.00
c)
Material
Granular soil with PI less than 6 for bedding and sides of cum
pipe (0.6 x 0.6 x 60 m)
21.60
each
27.00
cum
0.06
hour
1.50
d)
Machinery
Tractor-trolley
e&f) Overheads & Contractors Profit
Cost for 20 metre = a+b+c+d+e+f
Rate per metre = (a+b+c+d+e+f)/20
Note : 1. Inspection chamber at both ends is the responsibility of the agency who is laying
the duct. Hence not included.
2. The rates for stone masonry / brick masonry and cement mortar to be adopted from
respective clauses.
Sub Analysis :
Cement Mortar 1:2
Unit = cum
(a) Material
t
0.72
Cement
cum
1.05
Sand
(b) Labour
day
Mate
day
0.2
Mazdoor (Unskilled)
day
Bhisti
Total material and labour = (a+b)
474
RBR-TSRA
Index-code
S. No
Description
Unit
Quantity
day
day
day
2.12
1.00
tonne
1.05
Truck 10 tonne
hour
1.00
RBR-TSRA-39
39
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
40
RBR-TSRA-40
41
42
iii
RBR-TSRA-42
475
RBR-TSRA
Index-code
S. No
Description
Unit
Quantity
RBR-TSRA-43
43
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
Labour
Mate
day
Mazdoor
day
1.58
Blacksmith
day
0.25
b)
Material
each
80.00
kg
150.00
hour
3.00
day
day
day
3.13
0.25
each
50.00
each
cum
kg
50.00
8.00
15.00
hour
2.00
day
day
2.60
each
KL
kg
40.00
12.00
100.00
Machinery
Tractor-trolley
d&e) Overheads & Contractors Profit
Cost for 20 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/20
B Using Plastic/Steel Barrel, Filled with Sand
Provision and installation of traffic impact attenuator at abutment/pier
of flyovers bridges using plastic/steel barrels 0.60 m dia and 1.0 m in
height, filled with sand in three rows and tied with20 mm steel wire
rope as per approved design and drawings
Unit = sqm
Taking output = 20sqm
a) Labour
Mate
Mazdoor
Blacksmith
b)
Material
Plastic barrels
or
Steel barrels
Sand
20 mm steel wire rope
Add 1 per cent of cost of wire rope for clamps etc.
c)
Machinery
Tractor-trolley
d&e) Overheads & Contractors Profit
Cost for 20 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/20
C With HI - DRO cell Sandwich (Patented)
(In this patented HI - DRO cell system, water gets discharged from
plastic tubes on impact over a pre-determined time, thus absorbing
the energy)
Providing and installing a patentend HI - DRO cell system as a traffic
impact attenuators, using plastic tubes 50 cm dia, 1.2 m in height, 25
mm opening at the top, placed in three rows, filled with water and
tied with a 20 mm steel wire rope
Unit = sqm
Taking output = 10sqm
a) Labour
Mate
Mazdoor
b)
Material
476
RBR-TSRA
Index-code
S. No
1
RBR-TSRA-44
Description
Unit
Quantity
hour
hour
2.00
2.00
day
day
day
day
0.02
0.25
0.50
0.25
kg
kg
litre
25.00
15.00
0.50
44
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
Labour
Mate
Mazdoor
Painter
Welder
b)
Material
Angle iron 45 x 45 x 5 mm
MS sheet 300 mm wide,2.5 m long and 2.6 mm thick
Paint
Add 2 per cent of cost of steel for welding consumables,
nuts & bolts and drilling holes
c&d) Overheads & Contractors Profit
Rate per barricade = a+b+c+d
RBR-TSRA-45
45
Labour
Mate
day
Mazdoor
day
0.35
Painter
day
0.60
Welder
day
0.30
kg
kg
litre
15.00
50.00
1.00
b)
Material
Paint
Add 1 per cent of cost of steel for welding consumables,
nuts & bolts and drilling holes
c&d) Overheads & Contractors Profit
Rate per barricade = a+b+c+d
477
RBR-TSRA
Index-code
S. No
Description
Unit
Quantity
day
day
day
day
0.35
0.60
0.60
cum
0.18
1.00%
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
Unit = each
Taking output = one barricade
a) Labour
Mate
Mazdoor
Painter
Carpenter
b)
Material
Timber
Add 1percent of cost of timber for nuts & bolts, nails, etc.
c&d) Overheads & Contractors Profit
Rate per barricade = a+b+c+d
C With bricks
Construction of a permanent type barricade made with brick
work in mud mortar, 1.5 m high, 4 m long, 600 mm thick,
plastered with cement mortar 1:6, painted with yellow and
white strips
Unit = each
Taking output = one barricade
a)
Labour
Mate
day
Mazdoor
day
3.24
Painter
day
1.00
Mason
day
2.00
each
1800.00
kg
22.00
Sand
cum
0.09
Paint
litre
1.25
b)
Material
Brick
Cement
46
Labour
Mate
day
Mazdoor
day
0.27
Painter
day
0.25
each
1.00
Paint
litre
0.50
b)
Material
478
RBR-TSRA
Index-code
S. No
Description
Unit
Quantity
day
day
1.04
each
each
1.00
1.00
RBR-TSRA-47
47
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
Flagman
Positioning of a smart flagman with a yellow vest and a yellow cap
and a red flag 600 x 600 mm securely fastened to a staff 1 m in
length for guiding the traffic
Unit = each
Taking output = one flagman
a) Labour
Mate
Mazdoor
b)
Material
Flag of red color cloth 600 x 600 mm
Wooden staff for fastening of flag 25 mm dia, one m long
RBR-TSRA-48
9.000
Each
34.000
Each
50.000
RM
Each
220.000
84.000
1.000
49
RBR-TSRA-49
Total
Providing barricading arrangements with casuria posts for vertical to
be fixed at 3 mts (10'.0") intervals duly excavating a pit fixing the
vertical post firmly in the pit with excavated earth and metal for
additional gap, tying three horizontal casuarina posts to the verticals
with coconut rope firmly. Dismantling the barricading after the
programme including conveyance of all material, all labour charges,
hire charges of casurina posts, cost of coconut rope and all other
incidental charges etc., complete for finished item of work and as
directed by the Engineer -in- Charge.
Mazdoor (Unskilled)
For tying third horizontal row
Mazdoor (Unskilled)
day
9.000
day
1.000
479
RBR-TSRA
Index-code
S. No
1
Description
Unit
Quantity
4
34.000
Hire charges of vertical posts (2M long) Rs. 1.00 per day
I.E., 2daysX1.00
Hire charges of horizontal post of 4M long 100/4=25X3=75
Nos Rs. 2.50 per day I.e., 2X2.50
RM
Cost of coconut rope (55X3X2.00M=330RM)
Conveyance of vertical posts and horizontal posts including Each
loading and unloading at site and vice versa for two
operations.(55+75)
Mazdoor's (Unskilled) (NMR) for maintenance of
barricading such as refixing fallen posts if any in position
including watch and ward-3 shifts at 3 Nos. for each shift (1
no. for 600RM) 9/1800X2daysX100M=1No
Rate per 100 RM
Rate per 1RM
50
RBR-TSRA-50
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
75.000
330.000
130.000
1.000
day
Each
9.000
55.000
Each
50.000
RM
Each
220.000
105.000
15.000
RBR-TSRA-51
9.000
1.000
55.000
75.000
330.000
130.000
15.000
480
RBR-TSRA
Index-code
S. No
1
52
RBR-TSRA-52
Description
Unit
2
3
Providing barricading arrangements with iron posts (Departmental
Material) for vertical to be fixed at 3 mts (10'.0") intervals duly
excavating a pit fixing the vertical post firmly in the pit with excavated
earth and metal for additional gap, fixing three horizontal iron posts to
the verticals with bolts & nuts firmly. Dismantling the barricading after
the programme including conveyance of all material, all labour
charges, cost of bolts and nuts and all other incidental charges etc.,
complete for finished item of work and as directed by the Engineer -inCharge.
Quantity
4
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
Labour charges for digging pits fixing vertical post in the excavated
earth using crow bars for additional grip, tying horizontal posts two
rows with bolts & nuts firmly as directed by the departmental officer
and dismantling the entire work after the programme is over.
day
Mazdoor (Unskilled)
Cost of bolts and nuts for fixing horizontal posts to vertical Each
posts.(55X3=165 Nos)
Mazdoor's (Unskilled) (NMR) for maintenance of barricading such
as refixing fallen posts if any in position including watch and ward-3
shifts at 3 Nos. for each shift (1 no. for 600RM)
9/1800X2daysX100M=1No
53
RBR-TSRA-53
8.000
165.000
1.000
LS
8.000
165.000
7.500
LS
481
RBR_FNDN
Chapter - 11
FOUNDATION
Index-code
RBR-FNDN-1
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
3.64
Note : 1. Cost of dewatering may be added, where required, up to 5 per cent of labour cost. Assessment
for dewatering shall be made as per site conditions.
2. The cost of shoring and shuttering, where needed, may be added on cost of excavation for open
foundation.
3. The excavated earth if found suitable, can be used partly for backfilling in trenches & partly for road work.
Hence cost of disposal has not been added except for marshy soil. This note is common to all cases of
item 11.1 excluding 11.1 V
(B) Mechanical Means
i
Upto 3 m depth
Unit = cum
Taking output = 240 cum
a) Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Hydraulic Excavator 1 cum bucket capacity
c&d) Overheads & Contractors Profit
Cost for 240 cum = a+b+c+d
Rate per cum = (a+b+c+d)/240
day
day
8.32
hour
6.00
Note : 1. Cost of dewatering upto 5% of a+b may be added, where required, up to 10 per cent of labour
cost. Assessment for dewatering shall be made as per site conditions.
ii
3 m to 6 m depth
Unit = cum
(A) Manual Means
a) Labour
Mate / Supervisor
Mazdoor (Unskilled)
b&c) Overheads & Contractors Profit
Cost for 10 cum = a+b+c
Rate per cum = (a+b+c)/10
day
day
4.68
Note : 1. Cost of dewatering may be added, when needed, up to 5 per cent of labour cost.
2. Cost of shoring and shuttering, where needed, may be taken @ 10 per cent on cost of excavation for
open foundation.
484
RBR_FNDN
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
1
B
Mechanical Means
Unit = cum
Taking output = 210 cum
a) Labour
Mate
day
Mazdoor (Unskilled)
day
8.32
b)
Machinery
Hydraulic excavator 1.0 cum bucket capacity
hour
6.00
Unit = cum
Taking output = 10 cum
a) Labour
Mate/Supervisor
Mazdoor (Unskilled)
day
day
6.24
day
Mazdoor (Unskilled)
day
10.40
b)
Machinery
Hydraulic excavator 1.0 cum bucket capacity
hour
6.00
485
RBR_FNDN
Index-code
S. No
1
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
day
Mazdoor (Unskilled)
day
6.24
b) Machinery
Hydraulic Excavator 1 cum bucket capacity
hour
6.00
day
day
0.50
day
0.25
day
8.35
hour
kg
3.50
Nos.
14.00
5.20
6.00
486
RBR_FNDN
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
Unit = cum
Taking output = 10 cum
a) Labour
Mate
Mazdoor (Unskilled)
b&c) Overheads & Contractors Profit
Cost for 10 cum = a+b+c
Rate per cum = a+b+c)/10
day
day
15.60
day
Mazdoor (Unskilled)
day
10.40
b) Machinery
Tractor - Trally
hour
2.67
c) Material
Selected earth for refilling with conveyance from 1000m
cum
5.00
day
2.08
b) Machinery
Hydraulic Excavator 1 cum bucket capacity @ 60 cum / hour
hour
0.17
hour
0.45
c) Material
Selected earth for refilling
cum
5.00
2. Shoring and shuttering @ 10 per cent of (a+b) may be added where required.
3. It is assumed, that Marshy soil will be available upto 3 m depth only. For deeper
excavation below 3m depth, refer analysis in item (i) to (iv) for ordinary soil.
487
RBR_FNDN
Index-code
S. No
1
Description
2
VI Back Filling in Marshy Foundation Pits
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
Unit : Cum
Taking Output : 6 cum
a) Labour
day
Mate
Mazdoor (Unskilled) for dressing sides, bottom and day
backfilling
b)
Machinery
hour
Tractor-trolley for transportation
c&d) Overheads & Contractors Profit
Cost for 6 cum = a+b+c+d
Rate per cum = (a+b+c+d)/6
Filling in foundation trenches as per drawing and
technical specification Clause 305.3.9 MORD & 304
MORTH
RBR-FNDN-2
3.12
2.00
Sand filling
Unit = cum
a) Labour
day
Mate
day
0.31
Mazdoor (Unskilled)
b) Material
cum
1.00
Sand
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
II Earth filling (For marshy soil)
Unit = cum
Taking output = 6 cum
a) Labour
day
Mate
day
3.12
Mazdoor (Unskilled)
b&c) Overheads & Contractors Profit
Cost for 6 cum = a+b+c
Rate per cum = (a+b+c)/6
Note : Cost of transportation of good quality earth has not been included. Only labour for carrying carted
earth with a lead of 50 m to the foundation pits has been taken in the rate. The cost of carted earth may be
worked out separately if the same is not available from the adjoining area.
RBR-FNDN-3
Backfilling of foundation trenches shall normally be done with excavated earth. The cost of
this operation is included in item 11.1. Only in case the excavated earth is not of suitable
quality, sand filling or backfilling with carted earth may be resort to.
Filling annular space around footing in rock as per
technical specification Clause 1203.4.3. MORD
Unit = cum
P.C.C grade M 15
Nominal mix 1:2.5:5 (Hand mixing)
Unit = cum
(a) Material
t
0.275
Cement
cum
0.48
Coarse sand
cum
0.54
40 mm aggregate
cum
0.27
20 mm aggregate
cum
0.09
10 mm aggregate
(b) Labour
day
Mate
day
0.10
Mason (1st Class)
day
2.36
Mazdoor (Unskilled)
4.00%
(c) Formwork @ 4% on (a+b)
d&e) Overheads & Contractors Profit
Rate per cum = a+b+c+d+e
488
RBR_FNDN
Index-code
S. No
1
Description
2
(a) Filling Annular Space Around Footing in Rock with CC 1:3:6
nominal mix using 40mm nominal size stone aggregate as pre
Tech. Specification 304 & 2100 MORTH
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
Unit = cum
Taking out put = 1 cum
Lean cement concrete 1:3:6 nominal mix. Rate may be taken
as per item 11.4.
4
RBR-FNDN-4
Unit = cum
(a) Material
Cement
0.22
cum
0.45
cum
0.9
kl
1.2
day
day
day
0.1
1.39
Mechanical concrete mixer 0.4/0.28 cum capacity fitted with water hour
measuring device and preferably also with load cell.
hour
Water tanker 6 kl capacity
0.40
Coarse sand
40 mm aggregate
Water
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
(c) Machinery
0.220
0.45
0.570
0.280
0.050
day
day
day
0.10
2.36
0.13
4.00%
4.00%
t
cum
cum
0.275
0.48
0.48
cum
0.24
cum
0.08
day
day
0.10
day
1.39
489
RBR_FNDN
Index-code
S. No
1
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
(c) Machinery
hour
Concrete mixer 0.4/0.28 cum capacity
d) Formwork @ 4% on cost of material, labour and
machinery (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = a+b+c+d+e+f
0.40
4.00%
Note : Needle Vibrator is an item of minor T & P which is already included in overhead charges. Hence not
added in rate analysis of cement concrete works.
iv Nominal mix 1:2.5:5 (Hand mixing) (MORD)
Unit = cum
(a) Material
Cement
Coarse sand
40 mm aggregate
20 mm aggregate
10 mm aggregate
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
(c) Formwork @ 4% on (a+b)
d&e) Overheads & Contractors Profit
Rate per cum = a+b+c+d+e
V P.C.C. grade M 20 (MORD)
(i) Nominal mix (1:2:4) (Mechanical Mixer)
Unit = cum
(a) Material
Cement
Sand
40 mm aggregate
20 mm aggregate
10 mm aggregate
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
Bhisti
(c) Machinery
Concrete mixer 0.4/0.28 cum capacity
(d) Formwork @ 4% on (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = a+b+c+d+e+f
(ii) Nominal mix 1:2:4 (Hand mixed) (MORD)
Unit = cum
(a) Material
Cement
Sand
40 mm aggregate
20 mm aggregate
10 mm aggregate
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
(c) Formwork @ 4% out of material and labour (a+b)
d&e) Overheads & Contractors Profit
Rate per cum = a+b+c+d+e
0.275
cum
0.48
cum
0.54
cum
cum
0.27
0.09
day
day
day
0.10
2.36
4.00%
0.33
cum
0.45
cum
0.36
cum
0.36
cum
0.18
day
day
0.1
day
1.39
day
hour
0.4
4.00%
t
cum
0.33
0.45
cum
0.36
cum
0.36
cum
0.18
day
day
0.1
day
2.36
4.00%
490
RBR_FNDN
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
B
i
0.275
cum
0.45
cum
0.54
cum
0.27
cum
0.09
day
day
0.10
day
1.39
hour
0.40
hour
0.40
4.00%
0.343
cum
0.45
cum
0.36
cum
0.36
cum
0.18
day
day
0.1
day
1.39
hour
0.4
hour
0.4
4.00%
0.33
cum
0.45
cum
0.54
cum
0.36
day
day
0.1
day
1.39
hr /
cum
0.4
4.00%
491
RBR_FNDN
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
1
ii
cum
hour
0.347
0.45
0.54
0.36
0.1
1.39
0.4
0.4
4.00%
tonne
41.66
cum
54.00
cum
cum
64.80
43.20
day
0.84
day
3.00
day
18.00
hour
6.00
hour
hour
6.00
6.00
hour
t.km
15.00
300L
hour
6.00
4.00%
0.40
0.45
0.36
0.36
0.18
0.1
1.39
492
RBR_FNDN
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
hr /
cum
hour
0.40
c)
Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
d)
Formwork @ 3.75 per cent of (a+b+c)
e&f) Overheads & Contractors Profit
Rate for cum = a+b+c+d+e+f
CASE II : With Batching Plant, Transit Mixer and Concrete
Pump (M 25) (MORTH 12.8 D)
Unit : cum
Taking Output = 120 cum
a) Material
Cement
Coarse sand
40 mm Aggregate
20 mm Aggregate
10 mm Aggregate
b)
Labour
Mate
Mason
Mazdoor (Unskilled)
c)
Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader 1 cum capacity
Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity lead beyond 1 Km, L - lead in
Kilometer
Concrete Pump
0.40
4.00%
tonne
cum
cum
cum
cum
47.95
54.00
43.20
43.20
21.60
day
day
day
3.00
18.84
hour
hour
hour
hour
tonne
.km
hour
6.00
6.00
6.00
15.00
300L
d)
Formwork @ 3.75 per cent of cost of concrete i.e. cost of
material, labour and machinery
6.00
3.75%
0.403
cum
0.45
cum
0.54
cum
0.36
day
day
0.1
day
1.39
day
hr /
cum
0.4
3.75%
Unit: cum
Taking Output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
tonne
cum
cum
48.38
54.00
64.80
cum
43.20
493
RBR_FNDN
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
b)
Labour
Mate
Mason
Mazdoor (Unskilled)
c)
Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader 1 cum capacity 1 cum
Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity lead beyond 1 Km, L - lead in
Kilometer
Concrete Pump
d)
Formwork @ 3.75 per cent on cost of concrete i.e.
cost of material, labour and machinery
e&f) Overheads & Contractors Profit
cost of 120 cum = a+b+c+d+e+f
Rate per cum (a+b+c+d+e+f )/120
F PCC Grade M 30 (MORTH 12.8 F) Design Mix using 40
mm Graded Metal
CASE I : Using Concrete Mixer
Unit = cum
Taking output = cum
a) Material
Cement
Coarse sand
40 mm Aggregate
20 mm Aggregate
10 mm Aggregate
b)
Labour
Mate
Mason
Mazdoor (Unskilled)
c)
Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
d)
Formwork @ 3.5 per cent of (a+b+c)
e&f) Overheads & Contractors Profit
Rate for 1 cum = a+b+c+d+e+f
CASE II : With Batching Plant, Transit Mixer and Concrete
Pump (PCC M 30) Design Mix
Unit : cum
Taking Output = 120 cum
a) Material
Cement
Coarse sand
40 mm Aggregate
20 mm Aggregate
10 mm Aggregate
day
day
3.00
day
18.84
hour
6.00
hour
6.00
hour
6.00
hour
15.00
tonne
.km
300L
hour
6.00
3.75%
tonne
cum
0.405
0.45
cum
0.36
cum
0.36
cum
0.18
day
day
0.1
day
1.39
hour
0.4
hour
0.4
3.50%
tonne
cum
cum
48.60
54.00
43.20
cum
cum
43.20
21.60
b)
Labour
day
Mate
day
Mason
day
Mazdoor (Unskilled)
c)
Machinery
hour
Batching Plant @ 20 cum/hour
hour
Generator 100 KVA
hour
Loader 1 cum capacity
hour
Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity lead beyond 1 Km, L - lead in tonne
.km
Kilometer
hour
Concrete Pump
3.00
18.84
6.00
6.00
6.00
15.00
300L
6.00
494
RBR_FNDN
Index-code
S. No
1
Description
Unit
Quantity
4
3.50%
t
cum
0.407
0.45
cum
0.54
cum
0.36
d)
Formwork @ 3.5 per cent of cost of concrete i.e. cost
of material, labour and machinery
e&f) Overheads & Contractors Profit
cost of 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120
G
Amount
Rs.
Remarks
Rate
Rs.
day
day
0.1
day
1.39
hour
0.40
hour
0.40
3.50%
tonne
cum
48.80
54.00
cum
64.80
cum
43.20
day
day
3.00
day
18.84
hour
6.00
hour
6.00
hour
6.00
hour
15.00
tonne
.km
300L
hour
6.00
3.50%
0.422
0.45
0.54
0.36
495
RBR_FNDN
Index-code
S. No
1
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
(b) Labour
day
Mate
day
Mason (1st Class)
day
Mazdoor (Unskilled)
(c) Machinery
hour
Concrete mixer 0.4/0.28 cum capacity
hour
Generator 33 KVA
(d) Formwork @ 3% on (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = a+b+c+d+e+f
Case 2 : With Batching Plant, Transit Mixer and Concrete
Pump (RCC M35) Design Mix
Unit: cum
Taking Output = 120 cum
a) Material
tonne
Cement
cum
Coarse sand
cum
20 mm Aggregate
cum
10 mm Aggregate
b)
Labour
day
Mate
day
Mason
day
Mazdoor (Unskilled)
c)
Machinery
hour
Batching Plant @ 20 cum/hour
hour
Generator 100 KVA
hour
Loader 1 cum capacity 1 cum
hour
Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity lead beyond 1 Km, L - lead in Kilometer
t.km
hour
Concrete Pump
Vibrator
d)
Formwork @ 3 per cent on cost of concrete i.e. cost of
material, labour and machinery
e&f) Overheads & Contractors Profit
cost of 120 cum = a+b+c+d+e+f
Rate per cum (a+b+c+d+e+f )/120
0.1
1.39
0.40
0.40
3.00%
50.64
54.00
64.80
43.20
3.00
18.84
6.00
6.00
6.00
15.00
300L
6.00
3.00%
Note : Where ever concrete is carried out using batching plant, transit mixer, concrete pump, Admixtures @
0.4 per cent of weight of cement may be added for achieving desired slump of concrete.
NOTE : Concrete used in any component or structure shall be specified by designation along with
prescribed method of design of mix i.e., "Design Mix" or "Nominal Mix". For all items of concrete, only
"Design Mix" shall be used, except where "Nominal Mix" concrete is permitted as per drawing or by the
Engineer. "Nominal Mix" may be permitted only for minor bridges and culverts or other incidental
construction where strength requirements are upto M 20 only. "Nominal Mix" may also be permitted for nonstructural concrete or for screed below open foundations.
Note : Water : A provision for cost of water may be added at 1.2 kl / 1 cum (including curing
RBR-FNDN-5
Unit = cum
Brick masonry in 1:3 cement mortar
(a) Material
Bricks
Cement mortar 1:3 (Rate as per Sub-analysis)
(b) Labour
Mate
Mason (1st Class)
Nos.
512
cum
0.2
day
day
0.89
496
RBR_FNDN
Index-code
S. No
Description
Unit
Quantity
3
day
4
1.8
t
cum
0.48
1.05
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
Sub-analysis
Cement mortar 1:3 (1 cement : 3 sand)
Unit = cum
(a) Material
Cement
Sand
(b) Labour
Mate
Mazdoor (Unskilled)
Total material and labour = (a+b)
II Brick masonry in 1:4 cement mortar
Unit = cum
(a) Material
Bricks
Cement mortar 1:4
Rates as per sub-analysis
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
Sub-analysis
Cement mortar 1:4 (1 cement : 4 sand)
Unit = cum
(a) Material
Cement
Sand
(b) Labour
Mate
Mazdoor (Unskilled)
Total material and labour = (a+b)
III Brick masonry in cement-lime-mortar (1:0.5:4.5)
Unit = cum
(a) Material
Bricks
Cement lime mortar rates as per sub-analysis
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
Sub-analysis
day
day
0.2
Nos.
512
cum
0.2
Rate
Rs.
Amount
Rs.
Remarks
day
day
0.89
day
1.8
0.36
cum
1.05
day
day
0.2
Nos.
512
cum
0.20
day
day
0.89
day
1.80
Unit = cum
(a) Material
t
0.38
Cement
t
0.175
Lime putty
cum
1.05
Sand
(b) Labour
day
Mate
day
3.05
Mazdoor (Unskilled)
Total material and labour = (a+b)
Note : i. To provide 512 Nos Bricks Traditional size 23 x 11 x 7 cms and 520 Nos Modular
Bricks 19 x 9 x 9 cms
ii. Compressive strength of individual Brick shall not be less than 70 kg / cm 2
6
RBR-FNDN-6
Unit = cum
Coursed rubble masonry (1st sort)
(i) CRS 1st Sort in 1:3 cement mortar
Unit = cum
(a) Material
Stone for C.R. masonry 1st sort
Through bond stone (7 nos 0.24 x 0.24 x 0.39 = 0.16 cum)
I
cum
0.94
Nos.
0.16
cum
0.28
day
day
2.5
day
2.32
497
RBR_FNDN
Index-code
S. No
1
Description
2
(ii) CRS 1st Sort in 1:4 cement mortar
Unit = cum
(a) Material
Stone for C.R. masonry 1st sort
Through bond stone (7 nos 0.24 x 0.24 x 0.39 = 0.16 cum)
Cement mortar 1:4 (Rate as in item 11.5 II)
(b) Labour
Mate
Mason 1st Class
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
(iii) CRS First Sort in cement-lime-sand mortar (1:0.5:4.5)
Unit = cum
(a) Material
Stone for C.R. masonry 1st sort
Through bond stone (7 nos 0.24 x 0.24 x 0.39 = 0.16 cum)
Cement lime mortar (Rate as in item 11.5 III)
(b) Labour
Mate
Mason 1st Class
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
cum
0.94
Nos.
0.16
cum
0.28
day
day
2.5
day
2.32
cum
0.94
Nos.
0.16
cum
0.28
day
day
2.5
day
2.32
cum
0.94
Nos.
cum
0.16
0.32
Note : Quantity of required chips has not been provided for separately
as it is assumed that the same will be available from dressing of
stones.
II
Unit = cum
(a) Material
Stone for C.R. masonry 2nd sort
Through bond stone (7 nos 0.24 x 0.24 x 0.39 = 0.16 cum)
Cement mortar (Rate as in item 11.5 I.)
Water
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
day
day
1.5
day
2.22
498
RBR_FNDN
Index-code
S. No
1
Description
2
(ii) CRS 2nd Sort in 1:4 cement mortar
Unit = cum
(a) Material
Stone for C.R. masonry 2nd sort
Through bond stone (7 nos 0.24 x 0.24 x 0.39 = 0.16 cum)
Cement mortar (Rate as in item 11.5 II)
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
(iii) CRS 2nd Sort in cement-lime-mortar (1:0.5:4.5)
Unit = cum
(a) Material
Stone for C.R. masonry 2nd sort
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
cum
0.94
Nos.
0.16
cum
0.32
day
day
1.5
day
2.22
cum
0.94
Nos.
0.16
cum
0.32
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
III Random Rubble Masonry
(i) In 1:3 cement mortar
Unit = cum
(a) Material
CR Stone
Stone for R.R. masonry
Through bond stone (7 nos 0.24 x 0.24 x 0.39 = 0.16 cum)
Cement mortar (1:3) (Rate as in item 11.5 I)
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
(ii) RR Masonry in cement mortar 1:4
Unit = cum
(a) Material
CR Stone
Stone for R.R. masonry
Through bond stone (7 nos 0.24 x 0.24 x 0.39 = 0.16 cum)
Cement mortar (1:4) (Rate as in item 11.5 II)
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
day
day
1.50
day
2.22
cum
0.44
cum
0.5
Nos.
0.16
cum
0.33
day
day
1.2
day
cum
0.44
cum
0.5
Nos.
0.16
cum
0.33
day
day
1.2
day
499
RBR_FNDN
Index-code
S. No
1
RBR-FNDN-7
Description
2
(iii) RR Masonry in cement mortar 1:6
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
Unit = cum
(a) Material
cum
CR Stone
cum
Stone for R.R. masonry
Nos.
Through bond stone (7 nos 0.24 x 0.24 x 0.39 = 0.16 cum)
cum
Cement mortar (1:6) (Rate as in Sub Analysis)
(b) Labour
day
Mate
day
Mason (1st Class)
day
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
Sub Analysis :
Cement Mortar 1:6
Unit = cum
(a) Material
t
Cement
cum
Sand
(b) Labour
day
Mate
day
Mazdoor (Unskilled)
Total material and labour = (a+b)
(iv) RR Masonry in cement lime mortar (1:0.5:4.5)
Unit = cum
(a) Material
cum
CR Stone
cum
Stone for R.R. masonry
Nos.
Through bond stone (7 nos 0.24 x 0.24 x 0.39 = 0.16 cum)
cum
Cement lime mortar (Rate as in item 11.5 III)
(b) Labour
day
Mate
day
Mason (1st Class)
day
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
Note : Quantity of required chips has not been provided for
separately as it is assumed that the same will be available from
dressing of stones
Supplying, fitting and placing HYSD bar reinforcement in
foundation complete as per drawings and technical
specifications Clauses 1000 and 1202 MORD & 1100,
1600 MORTH for Bars below 36 mm dia including over
laps and wastage, where they are not welded.
Unit = t
(a) Material
HYSD bars including 5 per cent for overlaps and wastage
kg
Binding wire
(b) Labour for cutting, bending, shifting to site, tying and
placing in position
day
Mate
day
Blacksmith
day
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per t = a+b+c+d
0.44
0.5
0.16
0.33
1.2
2
0.24
1.05
0.2
0.44
0.5
0.16
0.33
1.20
2.00
1.05
6.00
2.00
6.40
500
RBR_FNDN
Index-code
S. No
1
RBR-FNDN-8
Description
2
A Supplying, fitting and placing HYSD bar reinforcement in
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
1.025
each
70.000
Hr
10.00
kg
6.00
day
2.50
day
2.00
day
6.40
1.05
kg
6.00
day
day
2.00
day
6.40
each
Welding Electrodes @ 5 per joint (14 joints / ton)
Hr
Welding Charges (Hire charges of Welding Machine)
kg
Binding wire
(b) Labour for cutting, bending, shifting to site, tying and
placing in position
day
Welder
day
Blacksmith
day
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per t = a+b+c+d
1.025
70.000
10.00
6.00
2.50
2.00
6.40
501
RBR_FNDN
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
RBR-FNDN-9
10
RBR-FNDN-10
Unit = 1No
Taking output = 1 No
a) Material
cum
904.32
Earth (compacted)
each 6000.00
Sand bags
each
95.00
Wooden ballies 8" Dia and 9 m long
m
190.00
Wooden ballies 2" Dia for bracing
b)
Labour
day
Mate
day
23.60
Mazdoor for piling 8" dia ballies for piling 8" dia ballies
day
12.00
Mazdoor for bracing with 2" dia ballies
day
110.00
Mazdoor for filling sand bags, stitching and placing
c)
Machinery
hour
50.00
Crane with grab 1 cum capacity
Consumables and other arrangements for piling ballies @ 2.5
per cent of (a+b+c).
d&e) Overheads & Contractors Profit
Rate per No. (a+b+c+d+e)
Note : For other well diameters rate can be worked out on the basis of cross-sectional area of
well. The diameter of the island shall be in the conformity with clause 1203.2 of MoRTH
specifications.
C Providing and constructing one span service road to
reach island location from one pier location to another
pier location as per Tech. Specification 1203 MORTH.
Assuming span length 30 m, width of service road 10m and
depth of water 1m
Unit = 1 meter
Taking output = 30 metre
a) Material
cum
Earth
each
Sand bags
450.00
300.00
b)
Labour
Mate
day
day
6.24
hour
27.00
hour
28.00
c)
Machinery
Front end Loader 1 cum capacity
Tipper 5.5 cum capacity
d&e) Overheads & Contractors Profit
502
RBR_FNDN
Index-code
S. No
1
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
1.05
Kg
20.00
RBR-FNDN-11
Unit = 1 MT
Taking output = 1 MT
a) Material
Structural steel in plates, angles, etc including 5 per cent wastage
Mate
Fitter
Blacksmith
Welder
Mazdoor (Unskilled)
day
day
5.50
day
5.50
day
5.50
day
17.82
cum
1.00
20.00%
12
RBR-FNDN-12
Well Curb
503
RBR_FNDN
Index-code
S. No
1
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
1.00
20.00%
Same as per 4.E except for formwork which shall be@ 20 per
cent of the cost of concrete instead of 3.75 per cent.
Case 1 : Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) cum
d) formwork @ 20 per cent of the cost of concrete
Water
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)
Case II : With Batching Plant, Transit Mixer and Concrete
Pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) as in 4.E cum
cum
1.00
20.00%
1.00
20.00%
1.00
20.00%
1.00
20.00%
Note : If curb concrete is carried out within steel liner, cost of formwork
shall be excluded.
(B)
Well staining
1.00
10.00%
1.00
10.00%
504
RBR_FNDN
Index-code
S. No
1
Description
2
III RCC M20 Grade (Design Mix) using 20 mm Graded Metal
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
cum
10.00%
1.00
cum
1.00
10.00%
cum
1.00
10.00%
1.00
10.00%
1.00
10.00%
1.00
10.00%
cum
1.00
10.00%
505
RBR_FNDN
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
cum
1.00
10.00%
1.00
10.00%
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) cum
as in 4G
d) formwork @ 10 per cent of the cost of concrete
e)
Overhead charges @ input on (a+b+c+d)
f)
Contractor's profit @ input on (a+b+c+d+e)
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)
VIII RCC M35 Grade
Same as for 4 (H) except for formwork which shall be @ 10
per cent of the cost of concrete instead of 3 per cent.
Case 1 : Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)
cum
1.00
10.00%
1.00
10.00%
1.00
10.00%
Unit = cum
Taking output = 120 cum
a) Material
Cement
Coarse Sand
20 mm Aggregate
10 mm Aggregate
Admixture
b)
Labour
Mate
Meson
Mazdoor (Unskilled)
c)
Machinery
Batching Plant
Generator 100 KVA
tonne
51.60
cum
54.00
cum
64.80
cum
43.20
kg
206.00
day
day
3.00
day
18.84
hour
6.00
hour
6.00
506
RBR_FNDN
Index-code
S. No
Description
Unit
Quantity
3
hour
4
6.00
hour
15.00
t.km
300xL
hour
Rate
Rs.
Amount
Rs.
Remarks
6.00
10.00%
tonne
cum
5.55
6.75
cum
5.40
cum
5.40
cum
2.70
Kg
18.60
day
day
1.50
day
20.90
hour
6.00
hour
6.00
hour
6.00
Add 5 per cent of cost of material and labour towards cost of forming
sump, protective bunds, chiselling and making arrangements for under
water concreting with tremie pipe.
44.40
54.00
64.80
43.20
148.80
3.00
18.88
6.00
6.00
6.00
15.00
507
RBR_FNDN
Index-code
S. No
Description
Unit
Quantity
3
t.km
4
300L
hour
6.00
tonne
5.99
cum
6.75
cum
5.40
cum
5.40
cum
2.70
Kg
21.60
day
day
1.50
day
20.90
hour
6.00
hour
6.00
hour
6.00
tonne
cum
47.88
54.00
Rate
Rs.
Amount
Rs.
Remarks
Add 5 per cent of cost of material and labour towards cost of forming
sump, protective bunds, chiselling and making arrangements for under
water concreting with tremie pipe.
cum
cum
64.80
cum
43.20
Kg
172.80
day
day
3.00
day
18.88
hour
6.00
hour
6.00
hour
6.00
hour
15.00
tonne
.km
300L
hour
6.00
508
RBR_FNDN
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
2
Add 5 per cent of cost of material and labour towards cost of forming
sump, protective bunds, chiselling and making arrangements for under
water concreting with tremie pipe.
6.08
cum
6.75
cum
5.40
cum
5.40
cum
2.70
Kg
21.60
day
day
1.50
day
20.90
hour
6.00
hour
6.00
hour
6.00
Add 5 per cent of cost of material and labour towards cost of forming
sump, protective bunds, chiselling and making arrangements for under
water concreting with tremie pipe.
Concrete Pump
tonne
.km
hour
48.64
54.00
64.80
43.20
172.80
3.00
18.88
6.00
6.00
6.00
15.00
300L
6.00
Add 5 per cent of cost of material and labour towards cost of forming
sump, protective bunds, chiselling and making arrangements for under
water concreting with tremie pipe.
509
RBR_FNDN
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
6.29
cum
6.75
cum
5.40
cum
5.40
cum
2.70
Kg
21.60
day
day
1.50
day
20.90
hour
6.00
hour
hour
6.00
6.00
Add 5 per cent of cost of material and labour towards cost of forming
sump, protective bunds, chiselling and making arrangements for under
water concreting with tremie pipe.
50.28
cum
54.00
cum
64.80
cum
43.20
Kg
172.80
day
day
3.00
day
18.88
hour
6.00
hour
6.00
hour
6.00
hour
15.00
tonne
.km
300L
hour
6.00
Add 5 per cent of cost of material and labour towards cost of forming
sump, protective bunds, chiselling and making arrangements for under
water concreting with tremie pipe.
510
RBR_FNDN
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
cum
1.00
cum
1.00
1.00
cum
1.00
cum
1.00
cum
1.00
cum
1.00
cum
1.00
cum
1.00
511
RBR_FNDN
Index-code
S. No
1
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
cum
1.00
cum
1.00
cum
1.00
t
cum
5.12
6.75
cum
8.10
cum
5.40
day
day
1.50
day
20.86
hour
6.00
hour
6.00
4.00%
Unit = cum
Taking output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
b)
Labour
Mate
Mason
Mazdoor (Unskilled)
c)
Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader (capacity 1 cum)
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity for lead upto 1 km.
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump
40.92
cum
54.00
cum
64.80
cum
43.20
day
day
3.00
day
18.84
hour
6.00
hour
6.00
hour
6.00
hour
15.00
t.km
300L
hour
6.00
512
RBR_FNDN
Index-code
S. No
Description
Unit
Quantity
3
cum
4
4.00%
t
cum
6.05
6.75
cum
8.10
cum
5.40
day
day
1.50
day
20.86
hour/
cum
hour
6.00
Generator 33 KVA
Form Work of a+b+c
cum
Centering Charges
Water
d&e) Overheads & Contractors Profit
cost of 15 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/15
Case II : Using Batching Plant, Transit Mixer and
Concrete Pump (RCC M 25)
Unit = cum
Taking output = 120 cum
a) Material
t
Cement
cum
Coarse sand
cum
20 mm Aggregate
cum
10 mm Aggregate
b)
Labour
day
Mate
day
Mason
day
Mazdoor (Unskilled)
c)
Machinery
hour
Batching Plant @ 20 cum/hour
hour
Generator 100 KVA
hour
Loader (capacity 1 cum)
Transit Mixer ( capacity 4.0 cu.m )
hour
Transit Mixer 4 cum capacity for lead upto 1 km.
t.km
Lead beyond 1 Km, L - lead in Kilometer
hour
Concrete Pump
cum
Formwork @ 3.75 per cent of ( a+b+c)
d&e) Overheads & Contractors Profit
cost of 120 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/120
Rate
Rs.
Amount
Rs.
Remarks
6.00
3.75%
48.40
54.00
64.80
43.20
3.00
18.84
6.00
6.00
6.00
15.00
300L
6.00
3.75%
513
RBR_FNDN
Index-code
S. No
1
Description
2
(iii) RCC Grade M30 (Design Mix)
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
6.10
6.75
8.10
5.40
1.50
20.86
6.00
6.00
3.50%
48.79
54.00
64.80
43.20
3.00
18.84
6.00
6.00
6.00
15.00
300L
6.00
3.50%
6.33
6.75
8.10
5.40
1.50
514
RBR_FNDN
Index-code
S. No
Description
Unit
Quantity
3
day
4
20.86
hour
6.00
Mazdoor (Unskilled)
c)
Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
Formwork @ 3 per cent of (a+b+c)
d&e) Overheads & Contractors Profit
cost of 15 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/15
Case II : Using Batching Plant, Transit Mixer and
Concrete Pump (RCC M 35)
Unit = cum
Taking output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
b)
Labour
Mate
Mason
Mazdoor (Unskilled)
c)
Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader (capacity 1 cum)
Transit Mixer ( capacity 4.0 cu.m ) :
Transit Mixer 4 cum capacity for lead upto 1 km.
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump
Formwork of (a+b+c)
d&e) Overheads & Contractors Profit
cost of 120 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/120
Note : Where ever concrete is carried out using batching
plant, transit mixer, concrete pump, Admixtures @ 0.4 per
cent of weight of cement may be added for achieving desired
slump of concrete.
(v) RCC M40 Grade (Design Mix)
Using Batching Plant, Transit Mixer and Concrete Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement
Coarse Sand
20 mm Aggregate
10 mm Aggregate
Admixture
b)
Labour
Mate
Mason
Mazdoor (Unskilled)
c)
Machinery
Batching Plant
Generator 100 KVA
Loader 1 cum capacity
Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity for lead beyond 1 km.
hour
6.00
cum
3.00%
t
cum
50.64
54.00
cum
64.80
cum
43.20
day
day
3.00
day
18.84
hour
6.00
hour
6.00
hour
6.00
hour
15.00
t.km
300L
hour
6.00
cum
3.00%
52.20
cum
54.00
cum
64.80
cum
43.20
kg
206.00
day
day
3.00
day
18.84
hour
6.00
hour
6.00
hour
6.00
hour
15.00
t.km
300.L
Rate
Rs.
Amount
Rs.
Remarks
515
RBR_FNDN
Index-code
S. No
1
Description
Unit
Quantity
4
6.00
hour
Concrete Pump
Formwork on cost of concrete i.e. cost of material, labour and cum
machinery
d)
Overhead charges @ input on (a+b+c)
e)
Contractor's profit @ input on (a+b+c+d)
d&e) Overheads & Contractors Profit
cost of 120 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/120
13
RBR-FNDN-13
(A)
(i)
(ii)
(iii)
(iv)
Rate
Rs.
Amount
Rs.
Remarks
3.00%
day
day
1.00
day
2.12
hour
2.00
10.00%
day
day
1.25
day
2.65
hour
3.00
10.00%
516
RBR_FNDN
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
(i)
(ii)
(iii)
(iv)
day
day
1.50
day
2.40
hour
3.00
10.00%
day
day
3.00
day
4.80
hour
6.00
hour
2.00
10.00%
day
day
3.00
day
20.92
day
0.50
517
RBR_FNDN
Index-code
S. No
1
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum hour
capacity and accessories.
hour
Air compressor with pneumatic breakers
Consumables in sinking @ 10 per cent of (b)
Add for dewatering @ of 5 per cent of (a+b), if required
14
RBR-FNDN-14
4.00
3.50
10.00%
Kg
4.00
each
18.00
day
day
2.00
day
0.25
day
13.56
day
4.00
hour
6.00
hour
2.00
10.00%
day
day
1.25
day
2.65
hour
3.25
10.00%
518
RBR_FNDN
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
day
day
1.50
day
3.18
hour
4.50
10.00%
a. Add 5 per cent for every additional meter depth of sinking over the
rate of sinking for the previous meter
(iv) Beyond 20m upto 30 m
a. Add 7.5 per cent for every additional meter depth of sinking over
the rate of sinking for the previous meter
b. Add 20 per cent of cost for Kentledge including supports, loading
arrangement and Labour).
(v) Beyond 30m upto 40 m
a. Add 10 per cent for every additional meter depth of sinking over the
rate of sinking for the previous meter
b. Add 20 per cent of cost for Kentledge including supports, loading
arrangement, and Labour etc.
(B) Clayey Soil ( 7m dia. Well )
day
day
1.50
day
3.18
hour
4.50
10.00%
day
day
2.00
day
4.26
hour
6.00
hour
3.25
10.00%
519
RBR_FNDN
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
day
day
4.00
day
10.58
day
0.75
hour
4.50
hour
3.75
10.00%
Kg
7.00
each
30.00
day
day
2.00
day
0.25
day
19.60
day
4.00
day
0.50
hour
6.00
hour
2.00
10.00%
520
RBR_FNDN
Index-code
S. No
1
15
RBR-FNDN-15
A
(i)
(ii)
(iii)
(iv)
(v)
(i)
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
day
day
1.50
day
3.18
hour
4.00
10.00%
day
day
1.75
day
3.75
hour
5.00
10.00%
day
day
2.00
hour
3.72
521
RBR_FNDN
Index-code
S. No
1
(ii)
(iii)
(iv)
(v)
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
hour
5.50
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum
capacity and accessories.
Consumables in sinking @ 10 per cent of (b)
c&d) Overheads & Contractors Profit
Rate per metre = (a+b+c+d)
Beyond 3m upto 10m depth
Rate of sinking @ 0.17 m/hour
a) Labour
Mate
Sinker
Sinking helper ( semi-skilled )
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum
capacity and accessories.
Air compressor with pneumatic chisel attachment for cutting
hard clay.
Consumables in sinking @ 10 per cent of (b)
c&d) Overheads & Contractors Profit
Rate per metre = (a+b+c+d)
Beyond 10 m upto 20 m
a. Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
b. Add for dewatering @ 5 per cent of cost, if required.
Beyond 20m upto 30 m
a. Add 7.5 per cent for every additional meter depth of
sinking over the rate of sinking for the previous meter
b. Add 5 per cent of cost for dewatering on the cost, if
c. Add 25 per cent of cost for Kentledge including supports,
loading arrangement and Labour ).
Beyond 30m upto 40 m
a. Add 10 per cent for every additional meter depth of
sinking over the rate of sinking for the previous meter
b. Add 5 per cent of cost for dewatering, if required
c. Add 20 per cent of cost for Kentledge including supports,
loading arrangement and Labour).
Soft Rock ( 8m dia well )
Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.20 m/hour
a) Labour
Mate
Sinker ( skilled )
Sinking helper ( semi-skilled )
Diver
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum
capacity and accessories.
Air compressor with pneumatic breakers
Consumables in sinking @ 10 per cent of (b)
Add for dewatering @ of 5 per cent of (a+b), if required
10.00%
day
day
2.50
day
4.82
hour
6.00
hour
3.50
10.00%
day
day
4.00
day
12.68
day
1.00
hour
5.00
hour
3.75
10.00%
522
RBR_FNDN
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
16
RBR-FNDN-16
Kg
8.00
each
32.00
day
day
2.00
day
0.25
day
21.09
day
4.00
hour
6.00
hour
2.00
10.00%
day
day
1.50
day
3.44
hour
4.00
10.00%
day
day
1.75
day
4.27
hour
5.50
10.00%
523
RBR_FNDN
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
(iv)
(v)
(i)
(ii)
(iii)
(iv)
(v)
day
day
2.25
day
3.99
hour
5.75
10.00%
day
day
2.50
day
5.34
hour
6.50
hour
3.75
10.00%
524
RBR_FNDN
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
RBR-FNDN-17
day
day
4.00
day
14.76
day
1.20
hour
6.50
hour
4.00
10.00%
Kg
10.00
each
40.00
day
day
2.00
day
0.25
day
23.17
day
4.00
day
1.00
hour
7.00
hour
2.50
10.00%
day
day
1.50
day
3.70
525
RBR_FNDN
Index-code
S. No
1
(ii)
(iii)
(iv)
(v)
(i)
(ii)
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
hour
5.00
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum
capacity and accessories.
Consumables in sinking @10 per cent of (b)
c&d) Overheads & Contractors Profit
Rate per metre = (a+b+c+d)
Beyond 3m upto 10m depth
Rate of sinking 0.17 m / hour
a) Labour
Mate
Sinker
Sinking helper ( semi-skilled )
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum
capacity and accessories.
Consumables in sinking @10 per cent of (b)
c&d) Overheads & Contractors Profit
Rate per metre = (a+b+c+d)
Beyond 10m upto 20m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Beyond 20m upto 30 m
a. Add 7.5 per cent for every additional meter depth of
sinking over the rate of sinking for the previous meter
b. Add 20 per cent of cost for Kentledge including supports,
loading arrangement and Labour.
Beyond 30m upto 40 m
a. Add 10 per cent for every additional meter depth of
sinking over the rate of sinking for the previous meter
b. Add 20 per cent of cost for Kentledge including supports,
loading arrangement, and Labour etc.
Clayey Soil (10m dia. Well )
Unit = Running Meter
Taking output = 1 cum
Depth below bed level upto 3.0 M
Rate of sinking 0.18m/hour.
a) Labour
Mate
Sinker ( skilled )
Sinking helper ( semi-skilled )
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum
capacity and accessories.
Consumables in sinking @ 10 per cent of (b)
c&d) Overheads & Contractors Profit
Rate per metre = (a+b+c+d)
Beyond 3m upto 10m depth
Rate of sinking 0.15m/hour.
a) Labour
Mate
Sinker
Sinking helper ( semi-skilled )
b)
Machinery
10.00%
day
day
2.00
day
4.56
hour
5.75
10.00%
day
day
2.50
day
5.75
hour
6.00
10.00%
day
day
3.00
day
5.90
a. Hire & running charges of crane with grab bucket of 0.75 cum hour
capacity and accessories.
b. Air compressor with pneumatic chisel attachment for cutting hard hour
clay
6.00
4.00
10.00%
526
RBR_FNDN
Index-code
S. No
1
Description
2
(iii) Beyond 10 m upto 20 m
a. Add 5 per cent for every additional meter depth of sinking over the
rate of sinking for the previous meter
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
day
day
4.00
day
16.86
day
1.40
hour
7.00
hour
4.25
10.00%
Kg
11.00
each
44.00
day
day
2.00
day
0.25
day
25.27
day
4.00
hour
8.50
hour
3.00
10.00%
527
RBR_FNDN
Index-code
S. No
1
18
RBR-FNDN-18
A
(i)
(ii)
(iii)
(iv)
(v)
(i)
(ii)
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
day
day
1.50
day
3.51
hour
6.00
10.00%
day
day
2.00
day
4.82
hour
4.00
10.00%
day
day
2.50
day
4.26
hour
5.00
10.00%
day
day
3.50
day
6.18
hour
6.00
hour
4.25
10.00%
528
RBR_FNDN
Index-code
S. No
1
(iii)
(iv)
(v)
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
day
day
4.25
day
18.95
day
1.50
hour
8.00
hour
4.50
10.00%
529
RBR_FNDN
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
Kg
12.00
each
48.00
19
RBR-FNDN-19
day
day
2.00
day
0.25
day
27.35
day
4.00
hour
10.00
hour
3.50
10.00%
day
day
1.75
day
4.22
hour
6.00
10.00%
day
day
2.50
day
5.12
Hire & running charges of crane with grab bucket of 0.75 cum capacity hour
and accessories.
6.50
10.00%
530
RBR_FNDN
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
(iv)
(v)
(i)
(ii)
(iii)
(iv)
day
day
3.00
day
4.80
hour
6.25
10.00%
day
day
3.75
day
6.48
hour
8.33
hour
4.50
10.00%
531
RBR_FNDN
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
day
day
4.50
day
21.06
day
1.75
hour
10.00
hour
4.75
10.00%
Kg
14.00
each
56.00
day
day
2.00
day
0.25
day
29.44
day
4.50
hour
12.50
hour
4.00
10.00%
532
RBR_FNDN
Index-code
S. No
1
20
RBR-FNDN-20
A
(i)
(ii)
(iii)
(iv)
(v)
(i)
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
day
day
day
1.25
3.95
hour
5.50
10.00%
day
day
day
1.50
4.30
hour
5.88
10.00%
day
day
day
2.50
4.26
hour
6.25
10.00%
533
RBR_FNDN
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
day
day
3.25
day
6.45
hour
6.67
hour
4.50
10.00%
a. Add 10 per cent for every additional meter depth of sinking over the
rate of sinking for the previous meter
day
day
4.50
day
15.86
day
1.50
Hire & running charges of crane with grab bucket of 0.75 cum capacity hour
and accessories.
hour
Air compressor with pneumatic breakers
8.33
6.00
10.00%
Kg
10.00
each
40.00
day
day
day
day
2.00
0.25
26.34
day
4.25
534
RBR_FNDN
Index-code
S. No
1
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
c)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum hour
capacity and accessories.
Hire & running charges of compressor with pneumatic hour
breaker/Jack hammer or drill
Dewatering @ 5 per cent of cost of (b+c), if required.
Consumables in sinking @ 10 per cent of (b).
d&e) Overheads & Contractors Profit
Rate per metre = (a+b+c+d+e)
21
RBR-FNDN-21
10.00
3.00
10.00%
Unit - 1 cum
Taking output = 5 cum
a) Material
M35 grade RCC corbel provided for supporting of equipment
(Dimensions as per ground conditions). Rate may be adopted
vide Item 4 (H)
HYSD bar reinforcement in corbel
Blasting material
Gelatine 80 per cent
Electric detonators
b)
Labour
Medical Officer
Para medical personnel
Mate
Driller
Blaster
Mazdoor unskilled (for cutting, blasting, cleaning, removal of
Material etc.)
Cum
8.00
0.48
Kg
1.50
each
6.00
day
day
day
day
day
day
0.50
1.00
1.00
0.50
31.86
Mazdoor (Skilled) (for fixation and removal of adopter for air lock, day
carrying out mechanical and electrical operations and repairs and other
skilled jobs.)
day
Diver
10.00
c)
Machinery
(i) Induction, denudation and erection of plant and
equipment including all components and accessories for
pneumatic method of well sinking.
Induction and denudation
Erection at site and commissioning
Usage of plant and equipment for pneumatic method of well
sinking
Air compressor 250 cfm, 2 nos.
Hire and running charges of crane of 15 tonne capacity
Motorised barge of 20 tonne capacity
Boat to carry at least 20 persons
Electric generating set 33 KVA
Tipper 10 tonne capacity
d&e) Overheads & Contractors Profit
Cost for 5 cum = a+b+c+d+e (see notes below)
Rate per cum = (a+b+c+d+e)/5
hour
4.00
6.00
L.S
L.S
hour
6.00
hour
12.00
hour
6.00
hour
6.00
hour
6.00
hour
6.00
hour
6.00
535
RBR_FNDN
Index-code
S. No
1
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
2
3
4
5
6
Note : 1. The cost of induction, denudation and erection of equipment shall be divided by the total quantity
of pneumatic sinking for all the wells of a particular bridge to arrive at the per cum rate on account of this
item.
2. Cost of pneumatic sinking per cum of individual wells will be added to the cost indicated at (1) above to
arrive at the final rate of pneumatic sinking per cum.
3. The cost of induction and denudation will depend upon the distance involved for shifting of equipment
which may be assessed in individual cases as per actual ground conditions at the time of making of cost
estimates.
4. In case pneumatic sinking is involved on a dry bed, the provision of barge and boat may be omitted.
Remarks
7
5. The necessity and dimensions of the corbel will be as per actual ground conditions.
RBR-FNDN-22
22
6. Small equipments like welding sets, pumps, vibrators, pneumatic tools, portable lamps, fire extinguishers,
hose pipes etc., have not been included as the same are covered as items of minor T&P under overhead
charges.
7. Depth of sinking shall be restricted to 30 m.
Sand Filling in Wells complete as per Drawing and Technical
Specifications 1207 MORTH.
Unit = 1 cum
Taking output = 1 cum
a) Material
Sand (assuming 20 per cent voids )
b)
Labour
Mate
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per cum (a+b+c+d)
23
RBR-FNDN-23
cum
1.00
day
day
0.31
1.05
Unit = 1 MT
Taking output = 1 MT
a) Material
i) Structural steel including 5 per cent wastage
b)
Labour
Mate
Fitter
Blacksmith
Welder
Mazdoor (Unskilled)
day
day
6.00
day
5.00
day
5.00
day
11.24
Pile diameter-750 mm
Unit = meter
Taking output = 15 m
a) Materials
cum
PCC Grade M35
Rate for concrete may be adopted same as for bottom plug
vide item no. 12( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia.
b)
Machinery( for boring and construction )
6.62
RBR-FNDN-24
Hire and running charges of hydraulic piling rig with power unit and hour
complete accessories including shifting from one bore location to
another.
hour
Hire and running charges of Bentonite pump
6.00
Hire and running charges of light crane for lowering reinforcement hour
cage
hour
Loader I cum bucket capacity.
0.50
Tipper 5.5 cum capacity for disposal of muck from pile bore hole
0.30
hour
6.00
0.30
536
RBR_FNDN
Index-code
S. No
1
Description
Unit
Quantity
3
kg
4
300.00
Bentonite
c)
Labour
Mate/Supervisor
Mazdoor (Unskilled)
d&e) Overheads & Contractors Profit
Cost for 15 m = a+b+c+d+d+e
Rate per metre (a+b+c+d+e)/15
25
RBR-FNDN-25
day
day
3.64
Pile diameter-1000 mm
Unit = meter
Taking output = 10 m
a) Materials
cum
PCC Grade M35
Rate for concrete may be adopted same as for bottom
plug vide item no. 12 ( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia.
b)
Machinery( for boring and construction )
7.85
Hire and running charges of hydraulic piling rig with power unit and hour
complete accessories including shifting from one bore location to
another.
hour
Hire and running charges of Bentonite pump
6.00
0.50
Bentonite
c)
Labour
Mate/Supervisor
Mazdoor (Unskilled)
d&e) Overheads & Contractors Profit
Cost for 10 m = a+b+c+d+d+e
Rate per metre (a+b+c+d+e)/10
26
Amount
Rs.
Remarks
Tipper 5.5 cum capacity for disposal of muck from pile bore hole
RBR-FNDN-26
Rate
Rs.
hour
kg
6.00
0.40
0.40
350.00
day
day
4.16
Pile diameter-1200 mm
Unit = meter
Taking output = 9 m
a) Materials
cum
PCC Grade M35
Rate for concrete may be adopted same as for bottom plug
vide item no. 12( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia.
b)
Machinery( for boring and construction )
10.17
Hire and running charges of hydraulic piling rig with power unit and hour
complete accessories including shifting from one bore location to
another.
hour
Hire and running charges of Bentonite pump
6.00
0.50
Tipper 5.5 cum capacity for disposal of muck from pile bore hole
Bentonite
c)
Labour
Mate/Supervisor
Mazdoor (Unskilled)
d&e) Overheads & Contractors Profit
Cost for 9 m = a+b+c+d+d+e
Rate per metre (a+b+c+d+e)/9
6.00
0.50
hour
0.50
kg
385.00
day
day
4.68
537
RBR_FNDN
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
2
Driven cast-in-place vertical M35 grade R.C.C. Pile excluding
Reinforcement complete as per Drawing and & Technical
Specification in Section 1100 & 1700 MORTH
cum
17.66
Kg
160.00
Kg
70.00
Kg
50.00
hour
6.00
hour
0.50
27
RBR-FNDN-27
day
day
3.12
Note : 1.The quantity of concrete required to be removed above the designed top level of concrete, if any,
will be provided for in the rate analysis.
2. In case steel lining is included in the design for driven cast-in-situ pile and is planned to be retained, the
same may be included in the rate analysis. In case the temporary steel casing used during casting is
planned to be removed, an additional cost @ 0.50 per cent of cost of concrete may be provided to cover its
usage.
28
RBR-FNDN-28
cum
23.55
Kg
160.00
Kg
70.00
Kg
50.00
hour
6.00
Hiring and running charges for light crane 5 tonnes lifting capacity for hour
lowering reinforcement and handling steel casing.
0.50
Hire and running charges for light crane for lowering hour
reinforcement cage.
d)
Labour
day
Mate/Supervisor
day
Mazdoor (Unskilled)
e&f) Overheads & Contractors Profit
Cost for 30 m = a+b+c+d+e
Rate per metre (a+b+c+d+e)/30
0.50
4.16
538
RBR_FNDN
Index-code
S. No
1
29
RBR-FNDN-29
Description
Unit
Amount
Rs.
Remarks
7
Hire and running charges of piling rig Including double acting pile hour
driving hammer complete with power unit and accessories.
Hiring and running charges for light crane 5 tonnes lifting capacity for hour
lowering reinforcement and handling steel casing.
d)
Labour
Mate/Supervisor
Mazdoor (Unskilled)
e&f) Overheads & Contractors Profit
Cost for 20 m = a+b+c+d+e
Rate per metre (a+b+c+d+e)/20
30
Rate
Rs.
2
3
4
5
6
Note : 1.The quantity of concrete required to be removed above the designed top level of concrete, if any,
will be provided for in the rate analysis.
2. In case steel lining is included in the design for driven cast-in-situ pile and is planned to be retained, the
same may be included in the rate analysis. In case the temporary steel casing used during casting is
planned to be removed, an additional cost @ 0.50 per cent of cost of concrete may be provided to cover its
usage.
RBR-FNDN-30
Quantity
22.61
160.00
70.00
50.00
6.00
0.50
day
day
4.68
Note : 1. The quantity of concrete required to be removed above the designed top level of concrete, if any,
will be provided for in the rate analysis.
2. In case steel lining is included in the design for driven cast-in-situ pile and is planned to be retained, the
same may be included in the rate analysis. In case the temporary steel casing used during casting is
planned to be removed, an additional cost @ 0.50 per cent of cost of concrete may be provided to cover its
usage.
Driven precast vertical M35 grade R.C.C. Piles excluding
Reinforcement complete as per Drawing and & Technical
Specification in Section 1100 & 1700 MORTH
11.78
240.00
105.00
Kg
30.00
hour
6.00
Vibrating Pile driving hammer complete with power unit and hour
accessories.
6.00
c)
Machinery
Crane20 t capacity
d)
Labour
Mate/Supervisor
Mazdoor (Unskilled)
day
day
3.12
RBR-FNDN-31
Note : The quantity of concrete required to be removed above the designed top level of concrete, if any, will
be provided for in the rate analysis.
Driven precast vertical M35 grade R.C.C. Piles excluding
Reinforcement complete as per Drawing and & Technical
Specification in Section 1100 & 1700 MORTH
c)
Kg
22.08
160.00
70.00
40.00
Machinery
539
RBR_FNDN
Index-code
S. No
Description
Unit
Quantity
3
hour
4
6.00
Vibrating Pile driving hammer complete with power unit and hour
accessories.
6.00
Crane 40 T capacity
d)
Labour
Mate/Supervisor
Mazdoor (Unskilled)
day
day
4.16
Rate
Rs.
Amount
Rs.
Remarks
RBR-FNDN-32
cum
31.40
Kg
160.00
Kg
70.00
c) Steel helmet and cushion block on top of pile head during driving.
Kg
50.00
hour
6.00
Vibrating Pile driving hammer complete with power unit and hour
accessories.
6.00
Rate for concrete may be adopted same as for bottom plug vide item
no. 12( F ) (IV)
c)
Machinery
Crane 50 t capacity.
d)
Labour
Mate/Supervisor
Mazdoor (Unskilled)
day
day
5.20
e)
Overhead charges @ input on (b+c+d)
f)
Contractor's profit @ input on (b+c+d+e)
e&f) Overheads & Contractors Profit
Cost for 40 m = a+b+c+d+e+f
Rate per metre (a+b+c+d+e+f)/40
Note : The quantity of concrete required to be removed above the designed top level of
concrete, if any, will be provided for in the rate analysis.
540
RBR_FNDN
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
2
Driven precast vertical M35 grade R.C.C. Piles excluding
Reinforcement complete as per Drawing and & Technical
Specification in Section 1100 & 1700 MORTH
33
RBR-FNDN-33
d ) Labour
Mate/Supervisor
Mazdoor (Unskilled)
5.40
240.00
105.00
30.00
6.00
6.00
day
day
3.12
Add 1 per cent of (a+b+c) for carriage of piles from casting yard to
work site and stacking, and other imponderables during installation.
e)
Overhead charges @ input on (b+c+d)
f)
Contractor's profit @ input on (b+c+d+e)
e&f) Overheads & Contractors Profit
Cost for 60 m = a+b+c+d+e+f
Rate per metre (a+b+c+d+e+f)/60
Note : The quantity of concrete required to be removed above the designed top level of
concrete, if any, will be provided for in the rate analysis.
34
RBR-FNDN-34
Vibrating Pile driving hammer complete with power unit and hour
accessories.
d ) Labour
Mate/Supervisor
Mazdoor (Unskilled)
12.50
160.00
70.00
30.00
6.00
6.00
day
day
4.16
541
RBR_FNDN
Index-code
S. No
1
35
RBR-FNDN-35
RBR-FNDN-36
36
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
hour
6.00
hour
6.00
day
day
3.12
0.50%
542
RBR_FNDN
Index-code
S. No
1
37
RBR-FNDN-37
38
RBR-FNDN-38
39
RBR-FNDN-39
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
tonne
s
5.83
hour
6.00
hour
6.00
day
day
3.64
0.50%
543
RBR_FNDN
Index-code
S. No
1
Description
2
(ii) RCC M 20 Design Mix Using Batching Plant, Transit Mixer
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
5.12
6.75
8.10
5.40
0.38
2.66
1.00
0.75
0.75
0.75
2.00
37.5L
0.75
4.00%
5.99
6.75
8.10
5.40
1.50
20.90
1.00
6.00
6.00
4.00%
544
RBR_FNDN
Index-code
S. No
1
Description
2
(ii) RCC M 25 Design Mix Using Batching Plant, Transit Mixer
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
5.99
6.75
8.10
5.40
0.38
2.66
1.00
0.75
0.75
0.75
2.00
37.5L
0.75
4.00%
6.10
6.75
8.10
5.40
1.50
20.90
1.00
6.00
6.00
4.00%
545
RBR_FNDN
Index-code
S. No
1
Description
2
(ii) RCC M 30 Design Mix Using Batching Plant, Transit Mixer
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
6.10
6.75
8.10
5.40
0.38
2.66
1.00
0.75
0.75
0.75
2.00
37.5L
0.75
4.00%
6.33
6.75
8.10
5.40
1.50
2.90
1.00
6.00
6.00
4.00%
6.33
6.75
8.10
5.40
0.38
546
RBR_FNDN
Index-code
S. No
1
RBR-FNDN-40
40
Description
Unit
Quantity
3
day
4
2.66
day
1.00
hour
0.75
hour
0.75
hour
0.75
hour
2.00
t.km
37.5L
hour
0.75
cum
4.00%
t
cum
4.13
6.75
cum
8.10
cum
4.05
cum
1.35
day
day
1.50
day
20.86
hour
6.00
hour
6.00
Rate
Rs.
Amount
Rs.
Remarks
General Note :
The provisions towards Mate is included in the provision towards unskilled Mazdoor.
547
RBR-SBST
Chapter - 12
SUBSTRUCTURE
Index-code
S. No
1
1
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
RBR-SBST-1
512
0.200
0.270
0.620
1.800
512
0.200
0.270
0.620
1.800
512
0.200
0.270
0.620
1.800
0.288
1.050
0.200
549
RBR-SBST
Index-code
S. No
1
Description
2
IV In cement lime mortar (1:0.5:4.5)
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
Unit = cum
(a) Material
Nos.
Bricks 1st class traditional size 23 x 11 x 7 cm
cum
Cement lime mortar (Rate as in item 11.5 III)
(b) Labour
day
Mate
day
Mason 1st Class
day
Mazdoor (Unskilled)
Add for scaffolding @ 5 per cent of cost of materials and
labour (a+b)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
V In 1:5 cement mortar (with Modular Bricks)
Unit = cum
(a) Material
Nos.
Bricks 1st class Modular size 19 x 9 x 9 cm
cum
Cement mortar
(b) Labour
day
Mate
day
Mason 1st Class
day
Mason 2nd Class
day
Mazdoor (Unskilled)
Add for scaffolding @ 5 per cent of cost of materials and
labour (a+b)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
512
0.200
0.620
1.800
520
0.200
0.270
0.620
1.800
Note : 1. The compressive strength of any individual Brick shall not be less than 70 Kg/cm2
2. When Mortar mix is changed as CM 1:3 & 1:4 proportionate quantity of cement has to be substituted. No
change in other data.
2
RBR-SBST-2
RBR-SBST-3
0.030
0.500
0.740
Unit = 10 sqm
Taking output = 10 sqm
(a) Material
cum
0.190
Cement mortar 1:4 (Rate as in item 11.5 II )
(b) Labour
day
Mate
day
0.600
Mason 1st Class
day
0.960
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per 10 sqm = (a+b+c+d)
Note : 1. Scaffolding is already included in item 12.1
2. Though cement mortar of leaner mix has been included in item 12.1, for cement plaster mix of 1:4 has
been proposed for better finishing
3. If cement plaster 12 mm or 18 mm thick is required elsewhere only the quantity of cement mortar may be
changed on prorata basis without any change in the labour.
550
RBR-SBST
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
2
Plastering with cement mortar (1:3), on brickwork in
substructure as per technical specification Section 1300 &
2200 MORTH
cum
0.144
Unit = 10 sqm
Taking output = 10 sqm
(a) Material
Cement mortar 1:3 (Rate as in item 11.5 II )
(b) Labour
Mate
Mason 1st Class
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per 10 sqm = (a+b+c+d)
Note : 1. Scaffolding is already included in item 12.1
C
day
0.500
day
0.540
cum
0.144
Unit = 10 sqm
Taking output = 10 sqm
(a) Material
Cement mortar 1:5 (Rate as in item 11.5 II )
(b) Labour
Mate
Mason 1st Class
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per 10 sqm = (a+b+c+d)
Note : 1. Scaffolding is already included in item 12.1
RBR-SBST-4
day
day
day
0.500
day
0.540
cum
Nos.
0.940
0.160
cum
0.280
Unit = cum
(a) Material
Stone for CR masonry 1st sort
Through and bond stone
(7 no x 0.24 x 0.24 m x 0.39 m = 0.16 cum)
Cement mortar (Rate as in item 11.5. I)
(b) Labour
Mate
Mason 1st Class
Mason 2nd Class
Mazdoor (Unskilled)
day
day
day
day
2.500
2.320
Add for scaffolding @ 5 per cent of cost of material (a) and labour
(b) (a+b)
cum
Nos.
0.940
0.160
cum
0.280
day
day
day
2.500
2.320
Add for scaffolding @ 5 per cent of cost of material (a) and labour
(b) 5% on (a+b)
551
RBR-SBST
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
cum
Nos.
0.940
0.160
cum
cum
0.280
day
day
day
2.500
2.320
cum
Nos.
0.940
0.160
cum
0.280
day
day
day
2.500
2.320
cum
Nos.
0.940
0.160
cum
cum
0.320
day
day
day
day
1.500
2.220
cum
Nos.
0.940
0.160
cum
cum
0.320
day
day
day
day
1.500
2.220
Unit = cum
(a) Material
Stone for CR masonry 1st sort
Through and bond stone
(7 no x 0.24 x 0.24 m x 0.39 m = 0.16 cum)
Spalls / blasted rubbles
Cement mortar (Rate same as in item 12.1 III)
(b) Labour
Mate
Mason 1st Class
Mazdoor (Unskilled)
As for scaffolding @ 5% on (a+b)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
(iv) In cement lime mortar (1:0.5:4.5)
Unit = cum
(a) Material
Stone for CR masonry 1st sort
Through and bond stone
(7 no x 0.24 x 0.24 m x 0.39 m = 0.16 cum)
Cement lime mortar (Rate as in item 11.5. III)
(b) Labour
Mate
Mason 1st Class
Mazdoor (Unskilled)
Add for scaffolding @ 5% of (a) and (b)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
II Coursed Rubble masonry (2nd sort)
(i) In cement mortar (1:3)
Unit = cum
(a) Material
Stone for CR masonry 2nd sort
Through and bond stone
(7 no x 0.24 x 0.24 m x 0.39 m = 0.16 cum)
Spalls/blasted rubbles
Cement mortar (Rate as in item 11.5 I)
(b) Labour
Mate
Mason 1st Class
Mason 2nd Class
Mazdoor (Unskilled)
Add for scaffolding @ 5 per cent of cost of material (a) and labour
(b)
552
RBR-SBST
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
cum
Nos.
0.940
0.160
cum
cum
0.320
day
day
day
day
1.500
2.220
cum
Nos.
0.940
0.160
cum
cum
0.320
day
day
day
1.500
2.220
cum
cum
Nos.
0.440
0.500
0.160
cum
0.330
day
day
day
day
1.200
2.000
cum
cum
Nos.
0.440
0.500
0.160
cum
0.330
day
day
day
day
1.200
2.000
Unit = cum
(a) Material
Stone for CR masonry 2nd sort
Through and bond stone
(7 no x 0.24 x 0.24 m x 0.39 m = 0.16 cum)
Spalls/blasted rubbles
Cement mortar (Rate same as in item 12.1 III)
(b) Labour
Mate
Mason 1st Class
Mason 2nd Class
Mazdoor (Unskilled)
Add for scaffolding @ 5 per cent on (a+b)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
(iv) In cement lime mortar (1:0.5:4.5)
Unit = cum
(a) Material
Stone for CR masonry 2nd sort
Through and bond stone
(7 no x 0.24 x 0.24 m x 0.39 m = 0.16 cum)
Spalls/blasted rubbles
Cement lime mortar (Rate as in item 11.5 III)
(b) Labour
Mate
Mason 1st Class
Mazdoor (Unskilled)
Add for scaffolding @ 5 per cent on (a+b)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
III Random rubble masonry
(i) In cement mortar (1:3)
Unit = cum
(a) Material
Coursed Rubble Stone
Stone for RR masonry
Through and bond stone
(7 no x 0.24 x 0.24 m x 0.39 m = 0.16 cum)
Cement mortar (Rate as in item 11.5 I)
(b) Labour
Mate
Mason 1st Class
Mason 2nd Class
Mazdoor (Unskilled)
Add for scaffolding @ 5 per cent of cost of material (a) and labour
(b)
553
RBR-SBST
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
cum
cum
Nos.
0.440
0.500
0.160
cum
0.330
day
day
day
day
1.200
2.000
cum
1.110
each
7.000
cum
0.280
Unit = cum
(a) Material
Coursed Rubble Stone
Stone for RR masonry
Through and bond stone
(7 no x 0.24 x 0.24 m x 0.39 m = 0.16 cum)
Cement mortar (Rate same as in item 12.1 III)
(b) Labour
Mate
Mason 1st Class
Mason 2nd Class
Mazdoor (Unskilled)
Add for scaffolding @ 5 per cent on (a+b)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
IV Ashlar masonry ( first sort ) Tech. Specification 1405.5
MORTH
Plain ashlar
Unit = cum
Taking output = 1 cum
a) Material
Stone
Through and bond stone
(7no.x0.24mx0.24mx0.39m = 0.16 cu.m)
Cement mortar 1:3 (Rate as in Item 11.5 I)
b) Labour for masonry work
Mate
Mason
Mazdoor (Unskilled)
Add for scaffolding @ 5 per cent of cost of a)
Labour
day
day
2.500
day
2.700
Material and b)
RBR-SBST-5
I
i
0.275
cum
0.480
cum
0.480
cum
0.240
cum
0.080
day
day
day
0.100
1.390
hour
0.400
10.00%
t
cum
0.275
0.480
cum
cum
0.540
0.270
cum
0.090
day
day
0.100
day
2.360
10.00%
554
RBR-SBST
Index-code
S. No
1
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
t
cum
cum
cum
cum
0.330
0.450
0.360
0.360
0.180
day
day
day
day
0.100
1.390
hour
hour
0.400
0.400
(a) Material
Cement
Coarse sand
40 mm aggregate
20 mm aggregate
10 mm aggregate
(b) Labour
Mate
Mason (1st Class)
Mason 2nd Class
Mazdoor (Unskilled)
(c) Machinery
Concrete mixer 0.4/0.28 cum capacity
Generator 63 KVA
Vibrator
(d) Formwork @ 10% on cost of material, labour and machinery
(a+b+c)
10.00%
1.000
d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork
Add
on cost of material, Labour and machinery excluding formwork
to cater for extra lift
10.00%
2.00%
t
cum
cum
cum
cum
0.330
0.450
0.360
0.360
0.180
day
day
day
0.100
2.360
10.00%
555
RBR-SBST
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
1.000
d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork
Add on cost of material, Labour and machinery excluding formwork
to cater for extra lift
10.00%
2.00%
d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)
III PCC Grade M20 (Design Mix) (MORTH) :
(C)
(ii) For height upto 5 m
Case I : Using Concrete mixer :
Rate per Cum
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) cum
of Chapter 11.4(B)(ii) of Chapter 11, excluding formwork.
d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)
III PCC Grade M25 (Design Mix) (MORTH):
(C) (i) For height upto 5 m
(iii)
i Case I : Using Concrete mixer :
Rate per Cum
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) cum
of Chapter 11.4 (D) Case I excluding formwork.
1.000
10.00%
1.000
10.00%
1.000
d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork
10.00%
1.000
d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork
10.00%
1.000
d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork
Add
on cost of material, Labour and machinery excluding formwork
to cater for extra lift
12.00%
2.00%
556
RBR-SBST
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
1.000
12.00%
2.00%
1.000
15.00%
4.00%
1.000
15.00%
4.00%
1.00
10.00%
1.00
10.00%
557
RBR-SBST
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork
Add on cost of material, Labour and machinery excluding
formwork to cater for extra lift
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)
1.00
12.00%
2.00%
d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork
Add on cost of material, Labour and machinery excluding
formwork to cater for extra lift
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)
(iii) Height above 10m
Case I : Using concrete Mixer
1.00
12.00%
2.00%
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) cum
of Chapter 11.4 (F) Case I excluding formwork.
1.00
d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork
Add
on cost of material, Labour and machinery excluding formwork
to cater for extra lift
15.00%
4.00%
1.00
d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork
Add on cost of material, Labour and machinery excluding formwork
to cater for extra lift
15.00%
4.00%
t
cum
0.330
0.450
cum
cum
0.540
0.360
day
day
day
day
0.100
1.390
hour
hour
0.400
0.400
10.00%
558
RBR-SBST
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
1.00
d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork
Add on cost of material, Labour and machinery excluding formwork
to cater for extra lift
12.00%
2.00%
1.00
d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork
Add
on cost of material, Labour and machinery excluding formwork
to cater for extra lift
15.00%
4.00%
t
cum
0.347
0.45
cum
cum
0.54
0.36
day
day
day
day
0.06
0.10
hour
hour
0.40
0.40
1.33
10.00%
1.00
d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork
10.00%
1.00
d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork
Add
on cost of material, Labour and machinery excluding formwork
to cater for extra lift
12.00%
2.00%
559
RBR-SBST
Index-code
S. No
1
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
1.00
d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork
Add
on cost of material, Labour and machinery excluding formwork
to cater for extra lift
12.00%
2.00%
1.00
d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork
Add
on cost of material, Labour and machinery excluding formwork
to cater for extra lift
15.00%
4.00%
1.00
d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork
Add on cost of material, Labour and machinery excluding formwork
to cater for extra lift
15.00%
4.00%
t
cum
cum
cum
0.403
0.450
0.540
0.360
day
day
day
0.10
1.39
hour
hour
hour
0.40
0.40
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) cum
of Chapter 11.4 (E) Case II excluding of Formwork
d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)
10.00%
10.00%
560
RBR-SBST
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
11.80%
1.80%
11.80%
1.80%
d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork
Add on cost of material, Labour and machinery excluding
formwork to cater for extra lift
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)
15.00%
4.00%
15.00%
4.00%
561
RBR-SBST
Index-code
S. No
1
Description
2
VII RCC Grade M30 (Design Mix)
(i) Height upto 5m
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
10.00%
d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork
10.00%
d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork
Add on cost of material, Labour and machinery excluding formwork
to cater for extra lift
11.50%
1.60%
d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork
Add on cost of material, Labour and machinery excluding formwork
to cater for extra lift
11.50%
1.60%
d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork
Add
on cost of material, Labour and machinery excluding formwork
to cater for extra lift
14.00%
3.50%
d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork
Add
on cost of material, Labour and machinery excluding formwork
to cater for extra lift
14.00%
3.50%
562
RBR-SBST
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
10.00%
1.000
d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork
10.00%
11.00%
1.40%
1.000
d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork
Add on cost of material, Labour and machinery excluding formwork
to cater for extra lift
11.00%
1.40%
13.00%
3.00%
1.000
d) formwork
Add on cost of material, labour and machinery (a+b+c) for
Formwork
Add on cost of material, Labour and machinery excluding formwork
to cater for extra lift
13.00%
3.00%
563
RBR-SBST
Index-code
S. No
1
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
2
3
4
5
6
Note in MORTH : The basic components of this analysis are the same as those of items 13.8 (A to H). The
only changes are as under:
a) Ramps/Stairs: Extra expenditure on structures which are more than 5 m high @ 2 per cent of cost for
height upto 10 m and 4 per cent for heights above 10 m will be involved for approaching the work spot by
providing higher ramp/stair case for use by the working parties.
Remarks
7
The above mentioned percentages have been suitably modified for different categories as cost for
b)
various categories varies, whereas effort for access for same height will be similar. As the cost of richer
concrete is comparatively more, the percentage to be added has been reduced to maintain the same cost
for extra efforts.
6
RBR-SBST-6
kg
Binding wire
(b) Labour for cutting, bending, shifting to site, tying,
and placing in position
day
Mate
day
Blacksmith
day
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per t = a+b+c+d
A
RBR-SBST-7
6.000
2.000
6.840
Unit = t
(a) Material
HYSD bars including 2.5 per cent for wastage
Welding Electrodes @ 5 per joint (14 joints / ton)
Welding Charges (Hire charges of Welding Machine)
Binding wire
(b) Labour for cutting, bending, shifting to site, tying,
and placing in position
Welder
Blacksmith/Bar Bender
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per t = a+b+c+d
7
1.050
t
each
1.025
70.000
Hr
10.00
kg
6.00
day
2.50
day
day
2.000
6.840
Unit = t
(a) Material
t
TMT bars including 5 per cent overlaps and wastage
kg
Binding wire
(b) Labour for cutting, bending, shifting to site, tying,
and placing in position
day
Mate
day
Blacksmith/Bar Bender
day
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per t = a+b+c+d
1.050
6.000
2.000
6.840
564
RBR-SBST
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
2
Supplying, fitting and placing TMT bar reinforcement (Fe 415)
in substructure complete including wastage, as per drawings
and technical specification Clauses 1002, 1005, 1010 & 1202
MORD / Sections 1600 & 2200 MORTH for Bars 36 mm dia and
above, where welding required to be done compulsorily.
Unit = t
(a) Material
TMT bars including 2.5 per cent for wastage
Welding Electrodes @ 5 per joint (14 joints / ton)
Welding Charges (Hire charges of Welding Machine)
Binding wire
(b) Labour for cutting, bending, shifting to site, tying,
and placing in position
Welder
Blacksmith/Bar Bender
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per t = a+b+c+d
8
RBR-SBST-8
1.025
each
70.000
Hr
10.00
kg
6.00
day
2.50
day
day
2.000
6.840
Unit = t
(a) Material
t
MS bars including 5 per cent overlaps and wastage
kg
Binding wire
(b) Labour for cutting, bending, shifting to site, tying,
and placing in position
day
Mate
day
Blacksmith
day
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per t = a+b+c+d
9
RBR-SBST-9
1.050
6.000
1.500
5.780
Unit = Nos
Taking output = 30 Nos
(a) Material
AC pipe 100 mm dia including wastage @ 5 per cent. Average
m
length of weep hole is taken as one metre for the purpose of
estimating
Nos.
MS clamps
31.500
10.00%
30.000
cum
0.050
day
day
day
0.500
0.280
Note in MORTH : 1. In case of stone masonry, the size of the weep hole shall be 150 mm x 80 mm or
circular with 150 mm diameter.
2. For structure in stone masonry, the weep holes shall be deemed to be included in the item of stone
masonry work and shall not be paid separately.
565
RBR-SBST
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
cum
12.000
day
day
7.280
hour
hour
2.500
0.050
cum
12.000
day
day
7.280
hour
hour
2.500
0.060
10
RBR-SBST-10
11
RBR-SBST-11
Unit = cum
Taking output = 10 cum
(a) Material
cum
Filter media as per specification
(b) Labour
day
Mate
day
Mazdoor (Unskilled)
day
Mazdoor (Skilled)
c)
Machinery
hour
Water Tanker of 6 KL capacity
d&e) Overheads & Contractors Profit
Cost for 10 cum of granular backfill = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/10
Note : Suitable Grade of Filter media shall be proposed as per
Specification in said IRC.
12.000
7.320
1.000
0.060
566
RBR-SBST
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
2
Supplying, fitting and fixing in position true to line and level
electrometric bearing conforming to IRC:83 (Part-II) Section IX
complete, including all accessories as per drawings and
technical specification Clause 1207.1 MORD
day
day
day
1.060
0.500
12
RBR-SBST-12
1.000
1.00%
per
cu.cm
of
elastomeric
bearing
(a+b+c+d)/19200
Note
: For such type of manufactured item, the overhead cost is taken as
30 per cent instead of 20 per cent
i
a) Labour
Mate
day
Mazdoor (Skilled)
day
0.500
Mazdoor (Unskilled)
day
1.060
b)
Material
1.000
a)
Labour
Mate
day
Mazdoor (Unskilled)
day
1.060
Mazdoor (Skilled)
day
0.500
567
RBR-SBST
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
b)
Material
1.000
a)
Labour
Mate
day
Mazdoor (Unskilled)
day
1.060
Mazdoor (Skilled)
day
0.500
b)
Material
1.000
level elastomeric bearing conforming to IRC: 83 (PartII) section IX and clause 2005 of MoRTH specifications
complete including all accessories as per drawing and
Technical Specifications 2000 & 2200 MORTH.
Unit: one cubic centimeter
Considering an elastomeric bearing of size 500 x 400 x 96
mm for this analysis.
Overall volume - 19200 cu.cm
Volume of 6 nos. 488 x 388 x 4 mm size reinforcing steel
plates = 4545 cu.cm.
Hence volume of elastometer = 14655 cu.cm.
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Skilled)
b)
Material
day
day
day
1.06
0.50
1.00
568
RBR-SBST
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
2
Supplying, fitting and fixing in position true to line and level
sliding plate bearing with stainless steel plate sliding on
stainless steel plate with mild steel matrix complete including
all accessories as per drawing and Technical Specifications
2000, & 2200 MORTH.
day
day
day
0.790
0.350
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Skilled)
b)
Material
1.000
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Skilled)
b)
Material
day
day
day
1.580
0.500
1.000
RBR-SBST-13
Unit = Running m
Taking output = 1 m
Assume wall thickness = 345 mm
Projection of the coping will be 25 mm wide on both side of
the wall = 345 + 50 = 395 mm
Quantity = 1 x 0.395 x 0.150 = 0.059
PCC M-20 Grade (1:2:4) Nominal Mix
As per item No. 12.5 (II)(i) including Overheads & Contractor's cum
Profit
0.059
RBR-SBST-14
Unit = Nos
(a) Material
AC pipe 100 mm dia i/c wastage of 5 per cent 600 mm long upto
m
the bottom of leveling course
Filter media base with stone aggregate as per specifications 0.5 m cum
x 0.5 m area 1 m deep
(b) Labour
Mate
Mason 1st Class
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per No = (a+b+c+d)
0.630
0.250
day
day
0.016
day
0.831
General Note :
The provisions towards Mate is included in the provision towards unskilled Mazdoor.
569
RBR-SPST
Chapter - 13
SUPERSTRUCTURE
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
t
cum
0.33
0.45
cum
0.54
cum
0.36
day
day
0.10
day
1.39
hr /
cum
0.40
RBR-SPST-1
25.00%
20.00%
30.00%
t
cum
0.341
0.45
cum
0.54
cum
0.36
573
RBR-SPST
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
c) Machinery
Concrete mixer 0.4/0.28 cum capacity
I
(i)
Generator 33 KVA
Total (a+b+c)
d) For formwork and staging add the following
percentage of (a+b+c):
Height upto 5 m @ 20 per cent
e&f) Overheads & Contractors Profit
Rate per cum = a+b+c+d+e+f
Note : 1. Height from 5 m to 10 m @ 25 %(MORD)
2. Height above 10 m @ 30 per cent (MORD)
RCC M 20 Design Mix (Using Concrete Mixture)
(MORTH)
Case I : (I) For solid slab super-structure (MORTH)
For formwork and staging add the following:
day
day
0.10
day
1.39
hr /
cum
hour
0.40
0.40
20.00%
cum
1.00
20.00%
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
(ii) Height 5m to 10m
(iii)
II
(i)
(ii)
(iii)
1.00
25.00%
1.00
30.00%
1.00
25.00%
1.00
30.00%
1.00
35.00%
Mixer and
t.km
0.341
cum
0.45
cum
0.54
cum
0.36
574
RBR-SPST
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
day
day
0.024
day
0.157
hour
0.05
hour
0.05
hour
0.05
hour
0.125
t.km
2.5 L
hour
0.05
cum
1.00
cum
1.00
20.00%
b)
Labour
Mate
Mason
Mazdoor (Unskilled)
c)
Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader
Transit Mixer ( capacity 4.0 cu.m ) :
Transit Mixer 4 cum capacity lead upto1 Km
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump
I
(i)
(ii)
(iii)
II
(i)
(ii)
(iii)
II
A
cum
1.00
25.00%
cum
1.00
30.00%
cum
cum
1.00
25.00%
1.00
30.00%
cum
1.00
35.00%
t
cum
cum
cum
0.40
0.45
0.54
0.36
day
day
day
0.10
1.39
hour/
cum
0.40
575
RBR-SPST
Index-code
S. No
Description
Unit
Quantity
3
hour
4
0.40
Generator 33 KVA
Rate
Rs.
Amount
Rs.
Remarks
cum
1.00
cum
1.00
20.00%
cum
1.00
25.00%
cum
1.00
30.00%
cum
1.00
25.00%
cum
1.00
30.00%
cum
1.00
35.00%
576
RBR-SPST
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
t
cum
cum
cum
0.407
0.45
0.54
0.36
day
day
day
0.10
1.39
hour
hour
0.40
0.40
cum
1.00
20.00%
Unit =cum
Case 1: Using Concrete Mixer
(a) Material
Cement
Coarse sand
20 mm aggregate
10 mm aggregate
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
c) Machinery
Concrete mixer 0.4/0.28 cum capacity
Generator 33 KVA
d) For formwork and stagings refer to sub-item (d) of I
(II) above
(I) For solid slab super-structure
(i) Height upto 5m
cum
1.00
25.00%
cum
1.00
30.00%
1.00
25.00%
1.00
30.00%
1.00
35.00%
0.407
0.46
0.54
0.36
0.024
0.157
0.05
0.05
0.05
0.125
300L
0.05
cum
1.00
20.00%
577
RBR-SPST
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
(iii)
II
(i)
(ii)
(iii)
cum
1.00
Basic Cost of Labour, Material & Machinery (a+b+c)
25.00%
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
Height above 10m
cum
1.00
Basic Cost of Labour, Material & Machinery (a+b+c)
30.00%
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
For T-beam & slab
Height upto 5m
cum
1.00
Basic Cost of Labour, Material & Machinery (a+b+c)
25.00%
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
Height 5m to 10m
cum
1.00
Basic Cost of Labour, Material & Machinery (a+b+c)
30.00%
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
Height above 10m
cum
1.00
Basic Cost of Labour, Material & Machinery (a+b+c)
35.00%
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
Note : Quantity of cement provided for various components of the superstructure is for
estimating purpose only. Actual quantity of cement will be as per approved mix design.
Similarly quantity for coarse and fine aggregates is for estimating purpose and the exact
quantity shall be as per the mix design.
Use of Design mix in place of nominal mix of concrete of M20 and higher grades shall be
preferred. Nominal mix of grades M20 is to be used with adequate supervision and quality
control requirements. Technical Specification Clause 803 MORD.
RCC/PSC Grade M35 Design Mix (MORTH)
Case I : Using Concrete Mixer.
Unit = 1 cum
Taking output = 1 cum
a) Material
tonne
0.422
Cement
cum
0.45
Coarse sand
cum
0.54
20 mm Aggregate
cum
0.36
10 mm Aggregate
578
RBR-SPST
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
b)
Labour
Mate
Mason
Mazdoor (Unskilled)
c)
Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
day
day
0.10
day
1.39
hour
0.40
hour
0.40
cum
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
(ii) Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
23.00%
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
(iii) Height above 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
28.00%
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
II For T-beam & slab
(i) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
23.00%
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
(ii) Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
28.00%
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
(iii) Height above 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
33.00%
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
III For box girder and balanced cantilever
(i) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
38.00%
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
(ii) Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
48.00%
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
(iii) Height above 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
cum
58.00%
579
RBR-SPST
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
t
cum
cum
cum
0.422
0.45
0.54
0.36
day
day
day
0.024
0.157
hour
hour
hour
0.05
0.05
0.05
hour
tkm
hour
0.125
2.5 L
0.05
I
(i)
(ii)
(iii)
II
(i)
(ii)
(iii)
III
(i)
Unit = cum
Taking output = 1 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
b)
Labour
Mate
Mason
Mazdoor (Unskilled)
c)
Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump
Basic Cost of Labour, Material & Machinery (a+b+c)
For formwork and staging add the following :
For solid slab super-structure
Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
Height above 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
For T-beam & slab
Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
Height above 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
For box girder and balanced cantilever
Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
cum
cum
23.00%
cum
28.00%
cum
23.00%
cum
28.00%
cum
33.00%
cum
38.00%
580
RBR-SPST
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
(iii)
I
(i)
(ii)
(iii)
II
cum
48.00%
cum
58.00%
t
cum
cum
cum
kg
0.43
0.45
0.54
0.36
1.72
day
day
day
0.133
1.53
hour
hour
0.40
0.40
cum
20.00%
cum
25.00%
cum
30.00%
cum
25.00%
cum
30.00%
35.00%
0.430
Coarse sand
cum
0.45
20 mm Aggregate
cum
0.54
10 mm Aggregate
Admixture @ 0.4 per cent of cement
b)
Labour
Mate
Mason
Mazdoor (Unskilled)
c)
Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
cum
0.36
kg
1.72
day
day
0.029
day
0.175
hour
0.05
hour
0.05
581
RBR-SPST
Index-code
S. No
Description
Unit
Quantity
3
hour
4
0.05
hour
0.125
tkm
2.5L
hour
0.05
I
(i)
(ii)
(iii)
II
(i)
(ii)
(iii)
Loader
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump
Basic Cost of Labour, Material & Machinery (a+b+c)
For formwork and staging add the following :
For solid / voided slab super-structure
Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
Height above 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
For T-beam & slab
Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
Height above 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
d)
Formwork and staging of (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e+f)
Rate
Rs.
Amount
Rs.
Remarks
cum
cum
23.00%
cum
28.00%
cum
23.00%
cum
28.00%
cum
33.00%
582
RBR-SPST
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
balanced cantilever
(i) Height upto 5m
cum
38.00%
cum
48.00%
cum
58.00%
Unit = 1 cum
Taking output = 1 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
Admixture @ 0.4 per cent of cement
b)
Labour
Mate
Mason
Mazdoor (Unskilled)
c)
Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump
Basic Cost of Labour, Material & Machinery (a+b+c)
For formwork and staging add the following :
For solid / voided slab super-structure
0.465
cum
0.450
cum
0.540
cum
0.360
kg
1.860
day
day
0.029
day
0.174
hour
0.050
hour
0.050
hour
0.050
hour
0.125
tkm
2.5 L
hour
0.050
16.00%
21.00%
26.00%
583
RBR-SPST
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
II
(i)
(ii)
(iii)
III
(i)
(ii)
(iii)
21.00%
26.00%
31.00%
36.00%
46.00%
56.00%
0.49
cum
0.45
cum
0.54
cum
0.36
kg
1.96
day
day
0.029
day
0.174
hour
0.05
hour
0.05
hour
0.05
hour
0.125
tkm
2.5 L
hour
0.05
584
RBR-SPST
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
III
(i)
(ii)
(iii)
cum
35.00%
cum
45.00%
cum
55.00%
0.529
cum
0.450
cum
0.540
cum
0.360
kg
2.120
day
day
0.029
day
0.174
hour
0.05
hour
0.05
hour
0.05
hour
0.125
tkm
2.5 L
hour
0.05
balanced cantilever
(i) Height upto 5m
cum
35.00%
cum
45.00%
cum
55.00%
585
RBR-SPST
Index-code
S. No
1
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
2
3
4
5
6
Note in MORTH : 1. Where ever concrete is carried out using batching plant, transit mixer, concrete
pump, admixers conforming IS: 9103 @ 0.4 per cent of weight of cement may be added for achieving
desired slump of concrete.
2. Cement provided for various components of the super structure is for estimating purpose only. Actual
quantity of cement will be as per approved mix design. Similarly, the provision for coarse and fine
aggregates is for estimating purpose and the exact quantity shall be as per the mix design.
Remarks
7
3. The items like needle and surface vibrators are part of minor T & P which is already covered under the
overhead charges. As such these items have not been added separately in the rate analysis.
2
RBR-SPST-2
RBR-SPST-3
(a) Material
HYSD bars including 5 per cent for laps and wastage
Binding wire
(b) Labour for cutting, bending, tying and placing in
position
Mate
Blacksmith/ Rod Binder
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per t = a+b+c+d
(ii) Supplying, fitting, and placing HYSD bar reinforcement
in superstructure complete including wastage, as per
drawing and technical specifications Clauses 1002,
1010 and 1202 MORD / 1600 MORTH, for Bars 36 mm
dia and above, where welding required to be done
compulsorily.
Unit = t
(a) Material
HYSD bars including 2.5 per cent for wastage
Welding Electrodes @ 5 per joint (14 joints / ton)
Welding Charges (Hire charges of Welding Machine)
Binding wire
(b) Labour for cutting, bending, tying and placing in
position
Welder
Blacksmith/ Rod Binder
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per t = a+b+c+d
(i) Supplying, fitting, and placing TMT bar reinforcement in
superstructure complete as per drawing and technical
specifications Clauses 1002, 1010 and 1202 MORD /
1600 MORTH for Bars below 36 mm dia including over
laps and wastage, where they are not welded.
t
kg
1.05
8.00
day
day
3.00
day
8.44
1.025
each
70.000
Hr
10.00
kg
8.00
day
2.50
day
3.00
day
8.44
Unit = t
(a) Material
t
TMT bars including 5 per cent for laps and wastage
kg
Binding wire
(b) Labour for cutting, bending, tying and placing in
day
position
Mate
day
Blacksmith/ Rod Binder
day
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per t = a+b+c+d
1.05
8.00
3.00
8.44
586
RBR-SPST
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
RBR-SPST-4
RBR-SPST-5
1.025
each
70.000
Hr
10.00
kg
8.00
day
2.50
day
3.00
day
8.44
1.05
kg
8.00
day
day
3.00
day
8.44
0.39
42.00
2.00
0.125
1.00
3.16
0.25
1.05
0.25
1.05
2.50
1.00
3.50
587
RBR-SPST
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
Unit = cum
(a) Material
Cement
Sand
20 mm aggregate
10 mm aggregate
HYSD bar reinforcement including binding wire (Rate as
per item 13.2) except OH & CP
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
Mazdoor (Unskilled) for cleaning deck slab concrete
surface
c) Machinery
Concrete mixer 0.4/0.28 cum capacity
Generator 33 KVA.
(d) Formwork @ 3% of cost of concrete
e&f) Overheads & Contractors Profit
Rate per cum = a+b+c+d+e+f
(ii) Providing and laying cement concrete wearing course
M 25 grade including reinforcement complete as per
drawing and technical specifications Clauses 800 and
1206.3 MORD
Unit = cum
(a) Material
Cement
Sand
20 mm aggregate
10 mm aggregate
HYSD bar reinforcement including binding wire (Rate as
per item 13.2) except OH & CP
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
Mazdoor (Unskilled) for cleaning deck slab concrete
surface
c) Machinery
Concrete mixer 0.4/0.28 cum capacity
Generator 33 KVA.
(d) Formwork @ 3% of cost of concrete
e&f) Overheads & Contractors Profit
Rate per cum = a+b+c+d+e+f
0.407
cum
0.45
cum
0.54
cum
0.36
0.075
day
day
0.10
day
1.39
day
0.15
hour
0.40
hour
0.40
3.00%
0.400
cum
0.45
cum
0.54
cum
0.36
0.075
day
day
0.10
day
1.39
day
0.15
hour
0.40
hour
0.40
3.00%
588
RBR-SPST
Index-code
RBR-SPST-6
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
Mastic Asphalt
Providing and laying 12 mm thick mastic asphalt wearing
course on top of deck slab excluding prime coat with paving
grade bitumen meeting the requirements given in table 500-29,
prepared by using mastic cooker and laid to required level and
slope after cleaning the surface, including providing antiskid
surface with bitumen precoated fine grained hard stone
chipping of 9.5 mm nominal size at the rate of 0.005cum per 10
sqm and at an approximate spacing of 10 cm center to center
in both directions, pressed into surface when the temperature
of surfaces not less than 100 deg. C, protruding 1 mm to 4 mm
over mastic surface, all complete as per clause 515 & 2702
MORTH.
Unit = sqm
Taking output = 72.46 sqm (2 tonnes)(0.869 cum)
assuming a density of 2.3 tonnes/cum.
a) Labour
day
Mate
day
Mazdoor (Unskilled)
day
Mazdoor (Skilled)
b) Machinery
hour
Mechanical broom @ 1250 sqm per hour
Air compressor 250 cfm
Mastic cooker 1 tonne capacity
Bitumen boiler 1500 litres capacity
Tractor for towing and positioning of mastic cooker and
bitumen boiler
c) Material
Base mastic (without coarse aggregates) = 60 per cent
Coarse aggregate(3.35mm to 9.5 mm size) = 40 %
11.49
1.25
0.06
hour
hour
hour
0.06
6.00
6.00
hour
1.00
0.204
0.39
0.36
0.55
0.036
1.05
Note : 1.The rates for 6 mm or any other thickness may be worked out on pro-rata basis.
2. Where tack coat is required to be provided before laying mastic asphalt, the same is
required to be measured and paid separately.
3.The quantities of binder, filler and aggregates are for estimating purpose. Exact quantities
shall be as per mix design.
4.This rate analysis is based on design made by CRRI for a specific case and is meant for
estimating purposes only. Actual design is required to be done for each case.
5.The quantity of bitumen works out 17 per cent of the mastic asphalt blocks without
aggregates and falls within the standards laid down by MoRTH Specifications.
589
RBR-SPST
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
RBR-SPST-7
Construction of R.C.C. railing of M 25 grade in cast-insitu with 20 mm nominal size aggregate, true to line
and grade, tolerance of vertical railing post not to
exceed 1 in 500, centre-to-centre spacing between
vertical posts not to exceed 2000 mm as per drawing
and technical specifications Clauses 800, 900 and
1208.3 MORD.
Unit = Running m
Taking output = 4x12 m
Span = 48 m
(a) M 25 grade R.C.C.
No. of vertical posts = (6+1) 4 = 28 nos
Cross-sectional area of vertical post = 0.25x0.275 = 0.069 sqm
Add 5 per cent of above cost for form work for casting in cum
casting yard.
5.00%
590
RBR-SPST
Index-code
S. No
Description
Unit
Quantity
3
t
4
0.865
Rate
Rs.
Amount
Rs.
Remarks
Unit = 1 RM
Taking output = 2 x 24 m span = 48 m.
a) Material
Cement concrete M30 Grade Refer relevant item of concrete in Item cum
14.1(C) by using batching plant, excluding formwork i.e. per cum
basic cost (a+b+c)
No. of vertical posts = (12 + 2)2 = 28 Nos., External area of vertical
post 0.25x0.275 = 0.069sqm, Concrete in vehicle posts = 0.069 x 28
= 1.932 cum, Hand rail in 3 tiers = 3 x 24 = 72 m, External area =
0.170 x 0.175 = 0.03 sqm, Concrete in hand rails = 0.03 x 72 = 2.16
cum, Total Concrete = 1.932 + 2.16 = 4.092 cum. (Refer MoRTH SD
/ 202).
cum
Add 12 per cent of above cost for form work.
HYSD bar reinforcement Rate as per item No 14.2 (Excluding OH &
t
CP)
4.092
10.00%
0.865
RBR-SPST-8
24 m
2.946
t
t
kg
1.01
0.18
150.00
day
day
30.00
day
42.80
5.00%
1.00%
591
RBR-SPST
Index-code
S. No
Description
Unit
Quantity
4
1.00%
RBR-SPST-9
RBR-SPST-10
11
RBR-SPST-11
Amount
Rs.
Remarks
10
Rate
Rs.
(b) Labour
Mate
Blacksmith
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Cost for 20 m steel railing = a+b+c+d
Rate per metre = (a+b+c+d)/20
Brick masonry work in cement mortar 1:3 in parapet
excluding pointing and plastering as per drawing and
technical specifications Clauses 600, 900 and 1208.4
MORD
Unit = cum
(a) Material
Bricks (Modular Bricks 19 x 9 x 9 cms)
Cement mortar (Rate as in item 11.5 I)
(b) Labour
Mate
Mason 1st Class
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
Drainage spouts complete as per drawing and
technical specifications Clause 1209 MORD & 2705
MORTH
Unit = 1 No
(a) Material
Corrosion resistant structural steel grating including 5 per
cent wastage
G I pipe 100 mm dia
GI bolt 10 mm Dia
Galvanised MS flat clamp
1.00%
day
day
6.00
day
8.56
Nos.
520.00
cum
0.20
day
day
0.89
day
1.80
kg
4.00
6.00
each
6.00
each
2.00
592
RBR-SPST
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
(b) Labour
For fabrication
Mate
Blacksmith, Welder etc. (Skilled)
Mazdoor (Unskilled)
For fixing in position
Mate
Mason (1st Class)
Mazdoor (Unskilled)
Add @ 5 per cent of cost of material and labour (a+b) for
electrodes, gas cutting, sealant, anti-corrosive bituminous
paint, mild steel grating etc.
c&d) Overheads & Contractors Profit
Rate per m = a+b+c+d
day
day
0.02
day
0.04
day
day
0.01
day
0.21
5.00%
Note in MORTH : 1. In case of viaducts in urban areas, the drainage spouts should be connected with
suitably located pipelines to discharge the surface run-off to drains provided at ground level.
2. In case of bridges, sufficient length of G.I Pipe shall be provided to ensure that there is no splashing of
water from the drainage spout on the structure.
12
RBR-SPST-12
0.275
cum
0.48
cum
0.54
cum
0.27
cum
0.09
day
day
0.10
day
1.39
hour
0.40
hour
0.40
0.275
cum
0.48
cum
0.54
cum
0.27
cum
0.09
day
day
0.10
day
2.36
593
RBR-SPST
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
2
Reinforced Cement Concrete M 25 grade approach slab
including reinforcement and formwork complete as per
drawing and technical specifications Clauses 800 and 1211
MORD / 1500, 1600, 1700 & 2704 MORTH
13
RBR-SPST-13
Unit = cum
(a) Material
Reinforced cement concrete M 25 grade
cum
Rate as per Item 11 (i)
HYSD reinforcement
t
Rate per item 2
Rate per cum = (a)
ii Reinforced cement concrete approach slab including
reinforcement and formwork complete as per drawing
and Technical specification 1500, 1600, 1700 & 2704
MORTH
Unit = 1 cum
Taking output = 1 cum
a) Material
Cement concrete M30 Grade Refer relevant item of concrete in item cum
1(III) by using batching plant, excluding formwork i.e. per cum basic
cost (a+b+c) (Excluding OH & CP)
Form Work : Refer relevant item of concrete in item No. cum
1.00
0.05
1.00
2.00%
0.05
OH&CP)
RBR-SPST-14
RBR-SPST-15
594
RBR-SPST
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
kg
446.00
5.00%
m
12.00
Add 1 per cent of cost of sealing element for lubricant-cumadhesive and other consumables.
(b) Labour
day
Mate
day
Mazdoor (Skilled)
day
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Cost for 12 m = a+b+c+d
Rate per m = (a+b+c+d)/ 12
(b) Unit = Running m
Taking output = 7.5 m
(a) Material
1.00%
293.00
kg
0.30
5.00%
m
(b) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Cost for 7.5 m = a+b+c+d
Rate per m = (a+b+c+d)/7.5
0.64
7.50
1.00%
day
day
0.224
day
0.40
Note : 1. The installation shall be done by the manufacturer or his authorised representative to the
satisfaction of the Engineer.
2. The concreting for joining the expansion joint assembly with the deck has not been included in this
analysis as the same is catered for in the quantities of R.C.C deck
3. The anchoring bars of the expansion joint assembly shall be welded to the main reinforcement of the
deck.
595
RBR-SPST
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
Buried Joint
Providing and laying a buried expansion joint, covered
with 12 mm thick, 200 mm wide galvanised weldable
structural steel plate as per IS:2062, placed
symmetrical to centre line of the joint, resting freely
over the top surface of the deck concrete, welding of 8
mm dia, 100 mm long galvanised nails spaced 300 mm
c/c along the centre line of the plate, as per Technical
Specification Clause 1207.2.3 MORD / 2604 MORTH.
16
RBR-SPST-16
Unit = Running m
Taking output = 12 m
(a) Material
Galvanised M.S. plate 200 mm wide 12 mm thick @ 94.20 kg
kg/sqm including 5 per cent wastage.
Add 1 per cent of cost of steel plate for cutting, welding,
consumables and galvanised nails.
(b) Labour
day
Mate
day
Mazdoor (Skilled)
day
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Cost for 12 m = a+b+c+d
Rate per m = (a+b+c+d)/ 12
17
1.00%
0.22
0.40
Unit = Running m
Taking output = 7.5 m
(a) Material
Galvanised M.S. plate 200 mm wide 12 mm thick @ 94.20
kg/sqm including 5 per cent wastage.
Add 1 per cent of cost of steel plate for cutting, welding,
consumables and galvanised nails.
(b) Labour
RBR-SPST-17
237.50
kg
150.00
1.00%
day
Mate
day
0.16
Mazdoor (Skilled)
day
0.25
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Cost for 7.5 m = a+b+c+d
Rate per m = (a+b+c+d)/ 7.5
NOTE : Guidelines laid down vide the MoRTH circular No. RW/NH-34059/1/96-S&R dated
30.11.2000 and subsequent corrigendum dated 25.01.2001 may be referred for expansion
joints.
Filler Joint
(I) Providing and fixing 2 mm thick corrugated copper
(A) plate in expansion joint as per drawing and technical
kg
34.00
day
day
0.35
day
0.37
kg
55.00
day
day
0.54
day
0.50
596
RBR-SPST
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
sqm
1.875
(II)
(A)
(B)
(III)
(A)
day
day
0.11
day
0.1
sqm
3.00
day
day
0.1
day
0.108
sqm
2.25
597
RBR-SPST
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
(b) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Skilled)
c&d) Overheads & Contractors Profit
Cost for 7.5 m = a+b+c+d
Rate per m = (a+b+c+d)/7.5
day
day
0.14
day
0.07
Unit = Running m
Taking output = 12 m
(a) Material
sqm
3.6
Premoulded joint filler 20 mm thick and 300 mm deep
(b) Labour
day
Mate
day
0.21
Mazdoor (Unskilled)
day
0.1
Mazdoor (Skilled)
c&d) Overheads & Contractors Profit
Cost for 12 m = a+b+c+d
Rate per m = (a+b+c+d)/ 12
(IV) Providing and filling joint sealing compound as per
(A) drawings and technical specifications with coarse sand
and 6 per cent bitumen by weight MORD
Unit = Running m
Taking output = 7.5 m
00 mm wide x 10 mm deep recess
(a) Material
cum
0.008
Sand
Volume = 7.5 x 0.1 x 0.01 = 0.008 cum
Weight = 0.008 x 1400 = 11.2 kg
t
0.0007
Bitumen-11.2 x 0.06 = 0.672 kg
(b) Labour
day
Mate
day
0.52
Mazdoor (Skilled)
day
0.10
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Cost for 7.5 m = a+b+c+d
Rate per m = ((a+b+c+d)/7.5) or ((a+b+c+d)/ 12)
(B) Providing and filling joint sealing compound as per
drawings and technical specifications with coarse sand
and 6 per cent bitumen by weight MORTH
Unit = Running m
Taking output = 12 m
00 mm wide x 10 mm deep recess
(a) Material
cum
0.012
Sand
Volume = 12 x 0.1 x 0.01 = 0.012 cum
Weight = 0.012 x 1400 = 16.8 kg
t
0.001
Bitumen-16.8 x 0.06 = 1.008 kg
(b) Labour
day
Mate
day
0.12
Mazdoor (Skilled)
day
0.5
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Cost for 12 m = a+b+c+d
Rate per m = (a+b+c+d)/ 12
Note : For arriving at the final rate for filler joints per m length and per cm depth of joint
filling compound, the rates of Sr. Nos (i), (ii), (iii) and (iv) shall be added.
598
RBR-SPST
Index-code
RBR-SPST-18
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
18
RBR-SPST-19
19
day
day
1.052
day
0.30
cum
0.75
kg
77.50
kg
113.00
1.00%
hour
1.00
hour
0.50
day
day
1.00
day
0.30
12.00
5.00%
Add 5 per cent of cost of material for anchorage
reinforcement, welding and other incidentals.
c&d) Overheads & Contractors Profit
Cost for 12 m = (a+b+c+d)
Rate per m = (a+b+c+d)/12
Note : 1. The installation shall be done by the manufacturer or his authorised representative
to the satisfaction of the Engineer.
2. The concreting for joining the expansion joint assembly with the deck has not been
included in this analysis as the same is catered in the quantities of RCC deck.
599
RBR-SPST
Index-code
RBR-SPST-20
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
20
RBR-SPST-21
21
22
RBR-SPST-23
23
0.46
12.00
RBR-SPST-22
1.00
day
day
1.25
day
0.57
12.00
600
RBR-SPST
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
0.47
cum
0.45
cum
0.54
cum
0.36
Kg
1.88
0.10
0.06
Litre
37.00
1.00%
day
day
0.41
day
1.40
day
day
0.16
day
0.50
day
day
1.12
day
2.00
day
day
0.08
day
0.60
601
RBR-SPST
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
RBR-SPST-24
day
day
0.36
day
day
0.26
day
day
0.07
day
0.24
hour
0.05
hour
0.05
hour
0.10
hour
0.05
hour
0.10
hour
0.10
hour
0.05
hour
0.15
t.km
2.5xL
hour
0.15
5.00%
1.00
1.00
RBR-SPST-25
25
b)
Labour
day
Mate
day
Fitter
day
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per cum (a+b+c+d)
Crash Barriers
The rate analysis for rigid crash barrier in reinforced
cement concrete, semi-rigid crash barrier with metal beam
and flexible crash barrier with wire ropes have been made
and included in chapter-8 on Traffic and Transportation as
per Specification 800 MORTH.
0.05
0.21
602
RBR-SPST
Index-code
RBR-SPST-26
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
26
27
RBR-SPST-27
28
RBR-SPST-28
29
RBR-SPST-29
30
RBR-SPST-30
31
RBR-SPST-31
32
RBR-SPST-32
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate
Painter
Mazdoor (Skilled)
b) Material
Water based paint of approved quality for cement concrete
surface
c&d) Overheads & Contractors Profit
Cost for 10 sqm (a+b+c+d)
Rate per sqm (a+b+c+d)/10
Stone masonry in cement mortar 1:3 for parapet
complete as per drawing and technical specifications
Clauses 700 and 1208.4 MORD
I. Random rubble masonry
Rate same as in Chapter 12.4 III (i)
II. Coursed rubble masonry (1st sort)
Rate same as in Chapter 12.4 I (i)
Pointing with cement mortar (1:3) on brickwork in
parapet as per technical specifications Clauses 613.3
and 1208.4 MORD
Rate same as in Chapter 12.2
Plastering with cement mortar (1:3) 15 mm thick on
brickwork in parapet as per technical specifications
Clauses 613.4 and 1208.4 MORD
Rate same as in Chapter 12.3
Providing and laying parapet with PCC M 15 as per
drawing & technical specifications Clauses 800 and
1208.4 MORD
I. Nominal mix 1:2.5:5 (Hand mixing)
Rate same as in item 12.5 I (ii)
II. Nominal mix (1:2.5:5)
Rate same as in item 12.5 I (i)
Providing bituminous wearing coat comprising of 20
mm thick premix carpet with 5 mm thick seal coat Type
B for culverts as per drawing and technical
specifications Clauses 1206.2 and 500 MORD
i.Rate for wearing coat as per item No. 5.9 of Chapter 5
ii.Rate for seal coat Type B as per item No. 5.12 of Chapter
5
day
day
0.25
day
0.26
5.00
cum
cum
sqm
sqm
cum
cum
603
RBR-SPST
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
33
RBR-SPST-33
RBR-SPST-34
cum
0.94
Nos.
0.16
cum
0.30
day
day
1.50
day
1.62
Note : 1. In case cement mortar 1:3 is used, rate for the same shall be as per item 11.5 I.
2. The addition for centering and sluttering at (c) above is for arch above 6 m span. For
lesser span length the addition shall be 80 per cent for span above 4 m length and 50 per
cent for spans less than 4 m.
Providing & Laying reinforced cement concrete arch
complete including centering and shuttering excluding
reinforcement as per drawings and technical
specifications Clauses 800, 900 and 1205.1 MORD
35
RBR-SPST-35
Unit = cum
RCC grade M20 (1:2.4) nominal mix
(a) Material
Cement
Coarse sand
20 mm aggregate
10 mm aggregate
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
Bhisti
(c) Machinery
Concrete mixer 0.4/0.28 cum capacity
(d) Add for cost of centering and shuttering @ 50 per
cent of (a+b) per sqm of surface of arch soffit
0.33
cum
0.45
cum
0.54
cum
0.36
day
day
0.20
day
2.15
day
hour
0.40
0.40
cum
0.45
cum
0.54
cum
0.36
day
day
0.20
day
2.15
day
604
RBR-SPST
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
(c) Machinery
hour
Concrete mixer 0.4/0.28 cum capacity
(d) Add for cost of centering and shuttering @ 45 % of
cost of (a+b) per sqm of surface of arch soffit
e&f) Overheads & Contractors Profit
Rate per cum = a+b+c+d+e+f
0.40
Note : The additional cost of centering and shuttering @ 50 / 45 per cent of cost of material and labour
shall hold good for arch spans of 6 m and above. For lesser length of spans, the corresponding additional
cost can be taken as 40 per cent for spans above 4 m length and 30 per cent for spans less than 4m.
36
RBR-SPST-36
(a) Material
R.S.Js 350 m x 200 mm @ 56.9 kg/m
6.0 m x 56.9 kg = 341.4 kg
Add 5 per cent for wastage = 17.87 kg
Total = 358.47 kg
25 cm wide x 12 mm thick plate
4x6x8.25 = 565.25 kg
Wastage 5 per cent = 28.3 kg
Total = 593.54 kg
Add shear connectors @ 10% = 59 kg
Total = 358.47 +593.5+59 = 1011 kg
Steel fabricated section
Rivets 22 mm dia = 240 Nos
Wastage @ 5 per cent = 12 Nos
Total = 252 Nos
Quantity of riveting @ 1.8 kg per 10 rivets = 45.35 kg
Add 5% of cost of material for painting one shop coat with red oxide
primer and three coats of synthetic enamel and consumables
10.11
0.454
5.00%
(b) Labour
day
6.00
Fitter
day
6.00
Blacksmith
day
12.00
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Cost for 10.11 q = a+b+c+d
Rate per quintal = (a+b+c+d)/10.11
Note : 1. In case of welded section, welding charges per cm length of welding shall
substitute cost of riveting
2. Shear connectors should always be welded to the top flange
3. The analysis of R.C.C. deck slab for the composite girder to be adopted from the item
13.1 of concrete superstructure
4. In the analysis of deck slab for composite girder superstructure, the component of
formwork for the same shall be 20 per cent of cost of materials, labour and machinery for
deck slab.
5. For spans upto 6 m with height above 5 m extra labour of mazdoor @ 3.0 days per
quintal may be added
6. For higher span lengths of different heights following additional labour for erection of steel
girders on pier/abutment caps may be provided:
Labour
day
Mate
day
0.06
Mazdoor (Skilled)
day
0.25
Mazdoor (Unskilled)
However, it is preferable to analyse the cost of erection of composite girder type of
superstructure for required span range and height range with a project - specific
methodology.
7. The provision of 10 per cent for shear connectors in the typical case is tentative. The
quantity shall be worked out as per design.
8. The cost of painting can also be analysed in detail in accordance with item 10.6 of
Chapter 10
General Note :
The provisions towards Mate is included in the provision towards unskilled Mazdoor.
605
RBR-PTWK
Chapter - 14
PROTECTION WORKS
Index-code
S. No
Description
RBR-PTWK-1
Unit Quantity
3
Mazdoor (Unskilled)
Overheads & Contractors Profit
Rate per cum
RBR-PTWK-2
Remarks
7
Providing and laying boulder apron for bed protection with stone
boulders of minimum size and weight as per Table 1300.1, no
fragment weighing less than 25 / 40 kg laid dry complete as per
drawing and technical specifications Clause 1301 MORD / 2503
MORTH
Unit = cum
(a) Material
cum
Stone boulder (25 kg / 40 Kg minimum)
cum
Stone spalls
(b) Labour
day
Mate
day
Mason 1st Class
day
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
Note : 1. Nominal excavation required for preparation of bed has
been taken into account while making provisions for labour.
2. Same data is hold good for stone boulders 25 kg / 40 kg only rate
may be substituted.
(i) Jeddy Stone Dry Packing for Aprons and Revetments
Section 1300 MORD
Unit = cum
(a) Material
cum
Jeddy Stone (Including small stone for wedging)
(b) Labour
day
Mason 1st Class
day
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
(ii) Removing old revetment and repacking with old stones
Unit = cum
cum
Rate as per Item 1(i) above for labour component only
Extra labour for removing old revetment including stacking
Rate Amount
Rs.
Rs.
1.00
0.20
0.35
0.79
1.20
0.35
1.05
1.00
day
0.20
cum
cum
kg
5.63
1.13
64.00
sqm
22.00
day
day
day
1.50
3.18
Unit = cum
Taking output = 3 m x 1.5 m x 1.25 m = 5.63 cum
(a) Material
Stone boulder (25 kg minimum) (MORTH - 40 kg)
Stone spalls
GI wires 4 mm dia @ 32 kg/10 sqm
(or)
4mm GI wire crates woven in mesh size of 100 mm x 100 mm.
(b) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
608
RBR-PTWK
Index-code
S. No
Description
Unit Quantity
3
Rate Amount
Rs.
Rs.
5
Remarks
7
Add for labour for weaving the wire crates @ 2 per cent of cost
of GI wire
c&d) Overheads & Contractors Profit
Cost for 5.63 cum = a+b+c+d
Rate per cum = (a+b+c+d)/5.63
Note : 1. Nominal cost of trimming for preparation of bed has been included in the cost of
labour
2. The analysis will by & large hold good for gabions
3. Readymade woven wire crate rolls have been considered in the rate analysis. In case
readymade rolls are not available, GI wire 4mm dia. @ 32 kg per 10 sqm may be provided. In
that case 2 per cent of the cost of GI wire may be added for weaving the wire crates.
3
RBR-PTWK-3
1.00
25.00
2.00%
RBR-PTWK-4
nos.
15.00
kg
0.15
LS
day
day
1.04
LS
(a) Material
2nd Class Bamboo 65 mm to 75 mm dia, (1.8 m-2.5 m) long
Binding Wire
Brush Wood (LS Rs.10.00)
(b) Labour
Mate
Mazdoor (Unskilled)
(c) Sundries
d&e) Overheads & Contractors Profit
Cost for 3 metre = a+b+c+d+e
Rate per metre = (a+b+c+d+e) / 3.00
nos.
kg
14.00
0.15
LS
day
day
1.04
LS
609
RBR-PTWK
Index-code
S. No
Description
RBR-PTWK-5
RBR-PTWK-6
RBR-PTWK-7
Unit Quantity
3
cum
1.00
cum
0.20
day
day
0.35
day
0.79
cum
1.00
Rate Amount
Rs.
Rs.
5
Remarks
7
2.00%
Nos.
500.00
cum
0.20
day
day
0.80
day
1.90
1.20
0.25
1.05
cum
1.1
day
0.7
610
RBR-PTWK
Index-code
S. No
1
RBR-PTWK-8
Description
2
(ii) Gravel Backing for Revetments as per APSS
Unit Quantity
3
Unit = cum
(a) Material
cum
Gravel
(b) Labour
day
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per cum = (a+b+c+d)
I Providing and laying flooring laid over cement concrete
bedding with M 10 grade complete as per drawing and
technical specification Clause 1303 MORD
i Rubble stone laid in cement mortar 1:3
Unit = cum
(a) Material
(i) Cement mortar (1:3) (For rate refer to item 6 (III) (i) of cum
Chapter 11
(ii) Add for cement concrete bedding (M 10) nominal mix) (For cum
rate refer to item 4 (I) (i) or (ii) of Chapter 11
Quantity shall be adopted as per design.
Add 1 per cent of cost to account for excavation for preparation
of bed
cum
(iii) Stone for rubble flooring 150 mm thick
cum
(iv) Stone spalls
(b) Labour
day
Mate
day
Mason 1st Class
day
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per cum = (a+b+c+d)
Note : Quantity of cement mortar is inclusive of mortar for laying and
filling of joints.
ii Providing and laying flooring laid over cement concrete
bedding with M 15 grade complete as per drawing and
technical specification Clause 2505 MORTH
Rubble stone laid in cement mortar 1:3
Unit = cum
(a) Material
(i) Cement mortar (1:3) (For rate refer to item 6 (III) (i) of cum
Chapter 11
b)
Add for cement concrete bedding (M15 Nominal mix) cum
vide 5 (I) (i) of Chapter 12 excluding OH & CP . Quantity
shall be adopted as per design (Assume Rubble stone
Flooring thickness 300mm and cement concrete bedding
thickness 100mm)
Add 1 per cent of cost to account for excavation for preparation
of bed
cum
(iii) Stone for rubble flooring 150 mm thick
cum
(iv) Stone spalls
(b) Labour
day
Mate
day
Mason 1st Class
day
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per cum = (a+b+c+d)
Note : Quantity of cement mortar is inclusive of mortar for laying and
filling of joints.
Rate Amount
Rs.
Rs.
5
Remarks
7
1.16
1.1
0.33
1.00
0.20
0.50
1.58
0.33
0.33
1.00
0.20
0.50
1.58
611
RBR-PTWK
Index-code
S. No
Description
1
2
II (i) Cement concrete blocks grade M 15 as per Specification
RBR-PTWK-9
RBR-PTWK-10
1300 MORD
Cement concrete blocks grade M 15 with 20 mm Graded metal
as per sizes in Table 1300.2
Add for Cement Concrete bedding (Quantity shall be as per
design)
Add 1 per cent of cost to account for excavation for preparation
of bed
Rate per cum
ii Cement concrete blocks grade M 15 as per Specification
2505 MORTH
Cement concrete blocks grade M 15 with 20 mm Graded metal
as per sizes in Table 1300.2
b)
Add for cement concrete bedding (M15 Nominal mix)
vide 5 (I) (i) of Chapter 12 excluding OH & CP. Quantity
shall be adopted as per design (Assume Cement Concrete
Blocks thickness 300mm and cement concrete bedding
thickness 100mm)
Add 1 per cent of cost to account for excavation for preparation
of bed
Rate per cum
III Brick on edge laid in cement mortar (1:3) for Flooring on
road sides 150 mm thick and each layer shall be bedded on
25 mm thick CM 1:5 & Joints filled with CM 1:3 as per
Technical Specifications Clause 1303 - MORD
Unit=cum
(a) Material
Bricks
Cement mortar (1:3)
Cement mortar bedding (1:5)
(b) Labour
Mate
Mason 1st Class
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per cum = (a+b+c+d)
Providing and laying of dry rubble flooring complete as per
drawings and technical specifications Clause 1303.3
MORD / 2506 MORTH
Unit = cum
(a) Material
Stone for rubble flooring 150 mm thick
Stone spalls
(b) Labour
Mate
Mason 1st Class
Mazdoor (Unskilled)
Add 1 per cent of (b) for trimming and preparation of base
c&d) Overheads & Contractors Profit
Rate per cum = (a+b+c+d)
Providing and laying curtain walls complete as per drawing
and technical specification Clause 1304 MORD / 2507
MORTH
Unit = cum
I Brick masonry in cement mortar (1:4)
(Rate same as in chapter 11
II (i) Coursed rubble masonry (2nd sort) in cement mortar (1:4)
Unit Quantity
3
cum
1.00
Rate Amount
Rs.
Rs.
5
Remarks
7
1.00%
1.00%
cum
1.00
cum
0.33
1.00%
Nos
500.00
cum
0.15
cum
0.25
day
day
0.80
day
1.90
cum
1.00
cum
0.20
day
day
0.50
day
1.60
cum
1.00
cum
(Rate same as in chapter 12
(ii) Coursed rubble masonry (1st sort) in cement mortar (1:3) cum
(Rate same as in chapter 12)
1.00
1.00
612
RBR-PTWK
Index-code
S. No
1
Description
2
III (i) Cement concrete grade M 10
Unit Quantity
3
cum
(Rate same as in chapter 11)
(ii) Cement concrete grade M 15
cum
(Rate same as in chapter 11)
Note : Other items like excavation for foundation, filling behind wall,
filter media, weep holes, etc. shall be added separately as per
approved design.
Construction of flexible apron 1 m thick comprising of
loose stone boulders weighing not less then 25 kg / 40 Kg
as per requirement beyond curtain wall as per Tech
Specification in Section 1300 MORD / 2507 MORTH.
Unit = cum
(a) Material
cum
Stone boulder (MORTH - 40 kg)
cum
Stone spalls
(b) Labour
day
Mate
day
Mason 1st Class
day
Mazdoor (Unskilled)
10
RBR-PTWK-11
Rate Amount
Rs.
Rs.
5
Remarks
7
1.00
1.00
1.00
0.20
0.25
1.05
11
RBR-PTWK-12
I
0.94
0.16
0.33
1.20
2.00
512.00
0.20
0.80
1.89
613
RBR-PTWK
Index-code
S. No
Description
Sub-analysis
Cement mortar 1:4 (1 cement : 4 sand)
Unit = cum
(a) Material
Cement
Sand
(b) Labour
Mate
Mazdoor (Unskilled)
Total material and labour = (a+b)
Unit Quantity
3
t
cum
0.36
1.05
Rate Amount
Rs.
Rs.
5
Remarks
7
day
day
0.20
0.220
Unit = cum
(i) P.C.C grade M 10 - Machine Mixed
RBR-PTWK-13
cum
0.45
cum
0.570
cum
0.280
cum
0.050
day
day
0.10
day
1.39
Mechanical concrete mixer 0.4/0.28 cum capacity fitted with water hour
measuring device and preferably also with load cell.
0.40
12
A toe wall for toe protection can either be in dry rubble masonry in case
of dry rubble pitching or pitching with stones in wire crates or it can be in
PCC M15 nominal mix if cement concrete block have been used for
pitching. Rates for toe wall can be adopted from respective clauses
depending upon approved design. The rate for excavation for
foundation, dry rubble masonry and PCC M15 have been analysed and
given in respective chapters.
13
RBR-PTWK-14
Nos
Kg.
18.00
0.15
LS
LS
day
day
1.04
LS
614
RBR-PTWK
Index-code
S. No
1
Description
2
ii Driven at least 900 mm below ground and 900 mm above ground on
average
14
RBR-PTWK-15
Unit Quantity
3
Nos
14.00
Kg.
0.15
LS
LS
Rate Amount
Rs.
Rs.
5
Remarks
7
day
day
1.04
LS
15.00
2.00
0.15
1.25
10.00
1.50
0.15
LS
1.04
615
RBR-PTWK
Index-code
S. No
1
Description
2
iii Driven at least 600 mm below ground and 1200 mm above
ground on average.
Unit = Running metre
Taking output = 3.00 metre
(a) Material
1st class bamboo (85-100 m dia, 2.0m long)
2nd class bamboo (85-100 mm dia, 2 m long)
Binding wire
Brush Wood (LS Rs.10.00)
(b) Labour
Mate
Mazdoor (Unskilled)
(c) Sundries
e&f) Overheads & Contractors Profit
Cost for 3 metre = a+b+c+d+e
Rate per metre = (a+b+c+d+e)/3
Bamboo spur 'A' type with whole bamboo 85mm-100mm
dia, placed 230 mm centre to centre driven 900 mm below
ground and 1200 mm to 1500 mm above ground tied with
2nd class bamboo (jati or Bethua) on either side at 450 mm
apart horizontally with galvanised wire etc. complete as per
drawings and technical specifications (MORD Suggestive)
15
RBR-PTWK-16
Unit Quantity
3
Nos
9.00
Nos
1.50
Kg.
0.15
LS
LS
day
day
1.04
Rate Amount
Rs.
Rs.
5
Remarks
7
LS
Nos
14.00
Nos
4.00
Kg.
0.75
day
day
1.04
LS
Nos
7.00
Nos
4.00
Kg.
1.00
LS
day
day
1.46
LS
616
RBR-PTWK
Index-code
S. No
Description
2
Providing 'A' type single spur with 1st class bamboo (Bholuka or
Barua) 85 mm to 100 mm dia. Driven closely placed 3m to 4m
above ground and 1200 mm to 1500 mm below ground tied with
cane or coir string, half 2nd class bamboo (jati or Bethua)
horizontally on both face placed not more than one metre apart
including whole bamboo struts inside one metre apart and 2 nos. of
purling at top and bottom fitted with vertical struts at 1500 mm
apart and filling with brushwood or jungle wood inside the spur
complete as per drawing and technical specifications (MORD
Suggestive)
16
RBR-PTWK-17
17
RBR-PTWK-18
18
RBR-PTWK-19
Unit Quantity
3
Nos
Nos
15.00
6.00
Kg.
2.00
Rate Amount
Rs.
Rs.
5
Remarks
7
LS
day
day
1.56
LS
Nos
Nos
67.00
6.00
kg
10.00
day
day
1.56
LS
Nos
68.00
cum
0.404
Kg
10.00
617
RBR-PTWK
Index-code
S. No
Description
19
RBR-PTWK-20
RBR-PTWK-21
20
Unit Quantity
3
Nos
4
5.00
Nos
5.00
Rate Amount
Rs.
Rs.
5
Remarks
7
LS
LS
Nos
1.20
Nos
Nos
31.20
LS
day
5.00
LS
Geotextile Filter
Laying of a geotextile filter between pitching and embankment slopes on
which pitching is laid to prevent escape of the embankment material
through the voids of the stone pitching/cement concrete blocks as well
as to allow free movement of water without creating any uplift head on
the pitching as per Tech Specifications in Section 700 & 2504 MORTH
RBR-PTWK-21
21
Unit = sqm
Taking output = 10 sqm.
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Skilled)
b)
Material
Permeable synthetic geotextile including 5 per cent for overlap
and wastage
c&d) Overheads & Contractors Profit
Cost for 10 sqm = a+b+c+d
Rate per sqm = (a+b+c+d)/10
Gabian Structure for Retaining Earth
day
day
0.30
day
0.12
sqm
11.00
Unit = cum
Taking output = 7 x 3 x 0.6 = 12.60 cum
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Skilled)
day
day
5.00
day
2.28
618
RBR-PTWK
Index-code
S. No
Description
b)
Unit Quantity
3
Rate Amount
Rs.
Rs.
5
Remarks
7
Material
Galvanised steel wire crates of mesh size 100 mm x 100 mm woven sqm
with 4mm dia. GI wire in rolls of required size.
61.00
cum
12.60
cum
2.52
Note : Readymade woven wire crate rolls have been considered in the rate
analysis. In case readymade rolls are not available, GI wire 4mm dia. @ 32 kg
per 10 sqm may be provided. In that case 2 per cent of the cost of GI wire
may be added for weaving the wire crates.
RBR-PTWK-22
22
General Note :
The provisions towards Mate is included in the provision towards unskilled Mazdoor.
619
RBR-MTRD
Chapter - 15
MAINTENANCE OF ROADS
Index-code
RBR-MTRD-1
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
Unit = cum
Taking output = 10 cum
(a) Labour
day
Mate
day
Mazdoor (Unskilled)
(b) Machinery
hour
Plate compactor
(c) Materials
cum
Compensation for earth Taken from private land
d&e) Overheads & Contractors Profit
Cost for 10 cum = a+b+c+d
Rate per cum = a+b+c+d/10
B Mechanical Means including conveyance of earth from
1000 M load
Unit = cum
Taking output = 50 cum
(a) Labour
day
Mate
day
Mazdoor (Unskilled)
(b) Machinery
hour
Hydraulic Excavator 0.9 cum bucket capacity @ 60 cum/h
RBR-MTRD-2
OR
hour
Hydraulic Excavator 1 cum bucket capacity @ 60 cum/h
hour
Tipper 5.5 cum, 10 t capacity
hour
Plate compactor 3.5 cum / hour capacity
(c) Materials
cum
Compensation for earth Taken from private land
d&e) Overheads & Contractors Profit
Cost for 50 cum = a+b+c+d+e
Rate per cum a+b+c+d+e/50
Note : Only 75% of fresh material has been provided as 25% can be
retrieved from site from earth i.e. flown down the slop in the form of
slurry and deposited at the foot of rain cuts.
Maintenance of Earthen shoulder (filling with fresh
selected soil)
(I) Making up loss of material/irregularities on shoulders to the
design level by adding fresh approved selected soil and
compacting it with appropriate equipment at OMC upto a lead
of 1000 m as per technical specification Clause 1903 MORD /
3003 MORTH
Unit = sqm
Taking output = 100 sqm
Assuming average thickness of filling to be 150 mm
Quality of fresh material = 15 cum
(a) Labour
day
Mate
day
Mazdoor (Unskilled)
6.240
3.000
7.500
10.400
0.830
0.650
2.270
15.000
37.500
4.680
621
RBR-MTRD
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
hour
0.250
hour
hour
0.680
4.000
cum
15.000
day
day
2.600
hour
4.000
(b) Machinery
Hydraulic Excavator 0.9 cum / 1.00 cum bucket capacity @
60 cum/h
Tipper 5.5 cum
Plate compactor @ 25 sqm per hour
(c) Materials
Compensation of earth
d&e) Overheads & Contractors Profit
Cost for 100 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/100
(II) Maintenance of Earthen shoulder (stripping of excess
soil)
Stripping excess soil from the shoulder surface to achieve the
approved level and compacting with plate compactor at OMC
as per drawings and Technical Specification Clause 1903
MORD / 3003 MORTH
Unit = sqm
Taking output = 100 sqm
Assuming height of stripping as 75 mm
Quantity of earth cutting involved = 7.5 cum
(a) Labour
Mate
Mazdoor (Unskilled)
(b) Machinery
Plate compactor @ 25 sqm per hour
c&d) Overheads & Contractors Profit
Cost for 100 sqm = a+b+c+d
Rate per sqm = a+b+c+d/100
RBR-MTRD-3
Amount
Rs.
Remarks
Unit = cum
Taking output = 187.5x0.075 = 14.06 cum = (30.94 Tonne)
(5% area of one km)
(a) Labour
day
Mate
day
Mazdoor (Unskilled)
(b) Machinery
hour
Jack hammer 25 kg with tractor
hour
Compressor 210 cfm with tractor
hour
Emulsion pressure distributor
hour
Mixall 6/10 t capacity
hour
Three wheeled 80-100 kN Static Roller
(c) Materials
Primer with bitumen emulsion @ 9 kg/10 sqm 187.5x9 = Tonne
168.75 kg.
Tack coat with bitumen emulsion @ 3.0 kg/ 10 sqm
Bottom = 187.5
Tonne
Sides = 28.27
Total = 215.77
Bitumen for BM @ 3.5% by weight of mix = 30.94 x 3.5 / 100 = 1.082
20.800
4.000
2.000
4.000
4.000
4.000
0.168
0.064
Tonne
1.082
cum
cum
cum
cum
2.985
8.955
4.975
2.985
622
RBR-MTRD
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
day
day
16.640
hour
hour
hour
2.000
2.000
4.000
tonne
0.292
tonne
0.040
tonne
0.136
cum
5.400
cum
1.200
day
day
20.800
hour
hour
hour
hour
2.000
2.000
2.000
4.000
t
t
0.064
0.292
0.136
cum
5.400
cum
1.200
day
day
16.640
hour
hour
hour
hour
2.500
2.000
2.000
4.000
tonne
0.060
tonn
0.430
tonn
Emulsion for seal coat @ 10 kg per 10 sqm
= 200 x 10 / 10 = 200 kg
Crushed stone aggregate 13.2 mm to 5.6 mm @ 0.27 cum per cum
10 sqm= 200x0.27/10=5.4cum
0.200
Amount
Rs.
Remarks
5.400
623
RBR-MTRD
Index-code
S. No
1
Description
Unit
Quantity
4
1.200
Rate
Rs.
Amount
Rs.
Remarks
RBR-MTRD-5
Day
Day
Day
90.000
7.760
hour
hour
hour
hour
6.000
6.000
45.000
12.000
cum
cum
tonne
184.500
92.250
14.970
tonne
2.460
Day
Day
Day
70.000
5.920
hour
hour
hour
hour
6.000
6.000
45.000
12.000
tonne
22.500
tonne
1.180
cum
cum
cum
99.750
65.550
114.000
cum
cum
cum
tonne
85.500
71.250
122.550
9.000
Unit = Sqm
Taking out put = 4900 sqm (196 cum)(450 Tonnes)
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor skilled
b)
Machinery
Air compressor 250 cfm
HMP 100-110 TPH Capacity
Tipper 10 tonnes capacity
Smooth wheeled roller 8-10 tonnes
c)
Material
I) Bitumen
ii) Bitumen emulsion for tack coat .
iii) Aggregates
Grading I - 19mm(Nominal size)
20-10mm 35 per cent
10-5 mm 23 per cent
5mm and below40 per cent
Add 5 per cent for wastage
or
Grading-II 13mm (Nominal size)
13.2-10 mm 30 per cent
10-5 mm 25 per cent
5 mm and Below43 per cent
Filler 2 per cent (Cement)
Add 5 per cent for wastage
Any one of the above alternatives of aggregate i.e. 19mm or 13mm
nominal size may be adopted as per approved design.
(i)
624
RBR-MTRD
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
RBR-MTRD-6
RBR-MTRD-7
RBR-MTRD-8
A
B
(C)
(D)
RBR-MTRD-9
1.040
33.000
0.020
day
day
2.080
cum
6.250
sqm
sqm
sqm
sqm
sqm
sqm
sqm
sqm
sqm
sqm
day
day
day
0.540
0.500
kg
kg
2.500
10.000
hour
0.050
625
RBR-MTRD
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
RBR-MTRD-11
10
11
RBR-MTRD-12
12
0.540
0.250
1.000
0.050
day
day
1.080
day
day
1.040
hour
1.670
Note : Land Slide clearance involves pushing of loose earth slided on the road surface from hill face on the
valley side. Since no cutting of original ground is involved, the output of dozer has been taken as 60 cum
per hour for soil, ordinary rock and blasted hard rock. However, if there are objection to disposing of earth
on valley side, additional resources for its disposal shall be considered as per site conditions.
RBR-MTRD-13
13
day
day
day
1.590
0.750
626
RBR-MTRD
Index-code
S. No
1
RBR-MTRD-14
14
Description
Unit
Quantity
4
0.070
day
Blaster
b)
Machinery
hour
Dozer D 80 A-12,180 HP @ 60 cum per hour
hour
Air compressor 250 cfm with two jack hammer
c)
Materials
kg
Gelatine 80 per cent @ 35 kg per 100 cum
Electric Detonators @ 1 Detonator for 2 Gelatine sticks of 125 each
gms each
c&d) Overheads & Contractors Profit
Cost for 100 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/100
Note : Credit for the rock if found acceptable as construction material
shall be afforded
Maintenance of Gravel Road
Maintenance of gravel road including making up the loss of
profile, rectifying corrugated surface, filling up of depressions,
pot holes and erosion gullies by adding fresh material and
compacting it with appropriate equipment or to strip excess
of material from the road surface as per drawings and
technical specification Clause 1905 MORD
RBR-MTRD-15
15
16
Amount
Rs.
Remarks
1.670
2.500
17.500
70.000
28.120
50%
RBR-MTRD-16
Rate
Rs.
14.060
50%
627
RBR-MTRD
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
day
day
day
1.100
1.400
L.S
LS
day
day
day
4.200
1.000
L.S
LS
day
day
day
2.400
4.000
LS
LS
day
day
day
2.090
0.125
LS
LS
RBR-MTRD-17
17
Amount
Rs.
Remarks
Maintenance of Culverts
(I) Maintenance of Hume pipe Culvert by way of Clearing, Cleaning,
Erosion repair, repairs to cracks, parapet wall and protection work as
per drawing and technical specification Clause 1908 MORD.
RBR-MTRD-18
18
RBR-MTRD-19
19
Unit = 1 km
All types of signs in one Km
a) Labour
Mate
Mazdoor (Unskilled)
Painter 1st Class
b) Material
Synthetic Enamel Paint, Engineering grade tape, welding
machine etc. (LS Rs.300)
c&d) Overheads & Contractors Profit
Cost for one Km = a+b+c+d
Rate per km = a+b+c+d
628
RBR-MTRD
Index-code
S. No
1
RBR-MTRD-20
20
i
Description
Unit
Quantity
Rate
Rs.
21
Remarks
Steel Railing
Unit = Running metre
Taking output = 10 metre
It is assumed that damage is to the extent of 10%
a) Labour
day
Mate
day
Mazdoor (Unskilled)
day
Painter 1st Class
day
Blacksmith
b)
Material
t
Mild steel (structural steel)
ISMC = 0.029T
MS plate = 0.01
t
Nuts and bolts
c) Machinery
LS
Welding set (LS Rs.100.00)
d&e) Overheads & Contractors Profit
Cost for 10 metre = a+b+c+d+e
Rate per metre = a+b+c+d+e/10
ii Repair of RCC railing to bring it to the original shape, cleaning
and repainting as per drawings and technical specification
Clause 1911 MORD
RCC Railing
Unit = running metre
Taking output = 1 metre
It is assumed that damage is to the extent of 10%
a) Labour
day
Mate
day
Mazdoor (Unskilled)
day
Mason 1st Class
b)
Material
M 30 grade cement concrete
cum
Rate as per item no. 13.1 (III) of Chapter 13
Steel bars reinforcement
t
Rate as per item no.13.2 of Chapter 13
c&d) Overheads & Contractors Profit
Rate per metre = a+b+c+d+e
RBR-MTRD-21
Amount
Rs.
0.324
0.100
0.200
0.039
0.001
LS
0.212
0.100
0.100
0.013
Unit = 1 km
Assuming 1 km stone, 4 nos 200 metre stone and 1/5th 5km
stone
Painting two coats with synthetic enamel paint
200 m stone 4 nos = 0.760 sqm.
One km stone = 0.815 sqm.
5th km stone 1x1/5 = 0.320 sqm.
Total = 1.895 sqm.
sqm
As per item No. 10.5 of chapter 10
1.895
per cm
height
220.000
629
RBR-MTRD
Index-code
S. No
1
RBR-MTRD-22
Description
Unit
Quantity
Rate
Rs.
day
day
day
0.524
0.100
LS
LS
day
day
day
1.120
2.000
day
day
2.080
day
day
10.400
day
day
day
0.153
0.143
quintal
kg
kg
0.045
0.100
0.013
a) Labour
Mate
Mazdoor (Unskilled)
Mason 1st Class
b)
Material
Cement, sand, aggregates etc.
(LS = Rs.100.00)
c&d) Overheads & Contractors Profit
Rate per/km = (i+ii+a+b+c+d)
Cutting of branches of trees shrubs and trimming of
grass and weeds
22
i
23
Remarks
RBR-MTRD-23
Amount
Rs.
Unit = sqm
Taking output = 1500 sqm
a) Labour
Mate
Mazdoor (Unskilled)
b&c) Overheads & Contractors Profit
Cost for 1500 sqm = a+b+c
Rate per sqm = a+b+c/1500
White washing of parapet walls of CD work and tree
truncks
White washing two coats on parapet walls and tree trunks including
preparation of surface by cleaning scraping etc. as per technical
specifications Clause 1915 MORD
RBR-MTRD-24
24
Unit = sqm
Taking output = 9 sqm
a) Labour
Mate
Mazdoor (Unskilled)
White washer
b)
Material
Lime
Fevicol adhesive
Indigo
c&d) Overheads & Contractors Profit
Cost for 9 sqm = a+b+c+d
Rate per sqm = a+b+c+d/9
Periodical Renewal to existing bituminous surface
I Open graded Premix carpet 20 mm thick
Unit = sqm
(i) Tack coat
With bituminous Emulsion (RS-1)
Rates as in Chapter 5
sqm
Rates as in Chapter 5
as relevant
Or
(iii) Premix carpet using bitumen Emulsion
Rates as in Chapter 5
sqm
sqm
630
RBR-MTRD
Index-code
S. No
Description
Unit
Quantity
Rate
Rs.
Amount
Rs.
Remarks
sqm
General Note :
The provisions towards Mate is included in the provision towards unskilled Mazdoor.
631
RBR-GSRE
RBR-GSRE-1
RBR-GSRE-2
S. No
Description
Unit
Quantity
2
Sub-Surface Drain with Geotextiles
Construction of sub surface drain 200 mm dia using geotextiles
treated with carbon black with physical properties as given in
clause 702.2.3 formed in to a stable network and a planar
geocomposite structure, joints wrapped with geotextile to prevent
ingress of soil, all as per clause 702 MORTH and approved
drawings including excavation and backfilling
Rate Amount
(Rs.)
(Rs.)
5
0.250
0.540
1.000
1.000
2.000
0.250
0.540
1.000
1.250
633
RBR-GSRE
Index-code
RBR-GSRE-3
S. No
Description
Unit
Quantity
2
Laying Paving Fabric Beneath a Pavement Overlay as per
Specification 703
Providing and laying paving fabric with physical requirements as
per table 704-2 over a tack coat of paving grade Bitumen 80-100
penetration, laid at the rate of 1 kg per sqm over thoroughly
cleaned and repaired surface to provide a water resistant
membrane and crack retarding layer. Paving fabric to be free of
wrinkling and folding and to be laid before cooling of tack coat,
brooming and rolling of surface with pneumatic roller to maximize
paving fabric contact with pavement surface
day
day
20.800
hour
hour
hour
2.240
1.400
1.680
sqm
tonne
2940.000
2.800
day
day
day
0.500
1.560
sqm
each
M
cum
cum
21.000
50.000
20.000
3.450
0.450
Unit = sqm
Taking output = 2800 sqm
a) Labour
Mate
Mazdoor (Unskilled)
b)
Machinery
Road sweeper 1250 sqm per hour
Pneumatic roller 14 tonnes 2000 sqm per hour
Bitumen pressure distributor 1750 sqm per hour
c)
Material
Paving Fabric
Paving Bitumen 80-100
RBR-GSRE-4
Rate Amount
(Rs.)
(Rs.)
5
634
RBR-GSRE
Index-code
RBR-GSRE-5
RBR-GSRE-6
S. No
Description
Unit
Quantity
2
Reinforced Earth Structures as per Specification 3100
MORTH
Reinforced earth Structures have four main components as
under:
a) Excavation for foundation, foundation concrete and cement
concrete grooved seating in the foundation for facing elements
(facia material).
b)
Facia material and its placement.
c)
Assembling, joining with facing elements and laying of the
reinforcing elements.
d)
Earth fill with granular material which is to be retained by
the wall.
Each component is analysed separately as under:
considering Average height of wall = 8 m.
(i) Assembling, joining and laying of reinforcing elements as
per Specification 3102 MORTH
A
With reinforcing element of steel / Aluminum strips /
polymeric strips.
Unit = Running Metre
Taking Output = 450 m
a) Labour
Mate
day
Mazdoor (Unskilled)
day
Mazdoor skilled
day
b)
Material
@ Reinforcement strips 60 mm wide 5 mm thick as per clause
3102.
1.Galvanised carbon steel strips
M
or
2.Copper Strips
M
or
3.Aluminium Strips
M
or
4.Stainless steel strips
M
or
5.Glass reinforced polymer/fiber reinforced polymer/polymeric M
strips
Rate Amount
(Rs.)
(Rs.)
5
6.360
3.000
450
450
450
450
450
II
III
IV
day
day
day
6.360
3.000
sqm
300.000
635
RBR-GSRE
Index-code
S. No
Description
Unit
Quantity
2
Add 10 per cent of the cost of reinforcing elements (synthetic
geogrids) for accessories like tie-strips, nuts and bolts and
loops/lugs for joining reinforcing elements with the facia panels,
overlaps and other protective elements for synthetic geogrids.
day
day
day
3.180
1.500
hour
6.000
cu.m
13.500
0.380
Rate Amount
(Rs.)
(Rs.)
5
Note : 1.The specification and construction details to be adopted shall be as per section 3100 of
MoRTH Specification.
2. Drainage arrangement shall be made as per approved design and drawings.
3. The quantity of filler media shall be calculated as per approved design and specifications and shall
be priced separately. The rate for same to be adopted from chapter 15.
4. Excavation for foundation including foundation concrete and groove in the foundation for seating of
bottom most facia panel and capping beam to be calculated as per design and priced separately. The
rates for excavation and foundation concrete shall be taken from the chapter 12 & 13 in bridge section.
5. The earth fill to be retained is not included in this analysis. The same is to be worked out and
provided separately complete as per clause 305.
6. For compaction of Earthwork, attention is invited to clause 3105.5 of MoRTH Specification.
7. Length of reinforcing strips will vary with the height of wall and will be as per approved design and
drawings.
8. The type of reinforcing elements to be adopted shall be as per approved design and specifications.
9. The market rate for supply of reinforcing elements and their accessories are to be ascertained from
reputed firms in the field of earth reinforcement.
10. The earth fill material shall be clean, free draining, granular with high friction and low cohesion, noncorrosive, coarse grained with not 10 per cent of particles passing 75 micron sieve, free of any
deleterious matter, chlorides, salts, acids, alkalies, mineral oil, fungus and microbes and shall be of
specified PH value.
11. Capping beam is to be priced separately as per approved design. The rate for cement concrete
shall be taken from the chapter of sub-structure in bridge section.
12. The cost of reinforced earth retaining wall shall include following:
(I) Excavation for foundation including backfilling.
(ii) Foundation concrete as per approved design.
(iii) Cost of facial panels and their erection .
(iv) Cost of reinforcing elements including their fixing and joining with the facial panels.
(v) Drainage arrangement including filter media as per approved design and drawings.
13. The compacted earth filling to be retained shall form part of embankment.
General Note :
The provisions towards Mate is included in the provision towards unskilled Mazdoor.
636
RBR-HRTC
Index-code
RBR-HRTC-1
S. No
Description
2
Spreading of Sludge Farm Yard Manure or/and good Earth as
per Specification 307 MORTH
Unit Quantity
3
Rate
(Rs.)
Amount
(Rs.)
Spreading of sludge farm yard manure or/ and good earth in required
thickness (cost of sludge, farm yard manure or/and good earth to be
paid for separately)
RBR-HRTC-2
Unit = cum
Taking output = 15 cum
a) Labour
Mate
day
Mazdoor (Unskilled)
day
b&c) Overheads & Contractors Profit
Cost for 15 cum= a+b+c
Rate per cum = (a+b+c)/15
Grassing with ' Doobs' Grass as per Specification 307 MORTH
Grassing with 'Doobs' grass including watering and maintenance of
the lawn for 30 days or more till the grass forms a thick lawn free
from weeds and fit for moving including supplying good earth if
needed
Unit = sqm
Taking output = 100 sqm
(i) In rows 15 cm apart in either direction
a) Labour
Mate
Mazdoor (Unskilled) for grassing
Mazdoor (Unskilled) for maintenance for 30 days
b)
Machinery
Water tanker6 KL capacity
c)
Material
Doob grass
d&e) Overheads & Contractors Profit
Cost for 100 sqm = a+b+c+d+e
Rate per sqm= (a+b+c+d+e)/100
(ii) In rows 7.5 cm apart in either direction
a) Labour
Mate
Mazdoor (Unskilled) for grassing.
Mazdoor (Unskilled) for maintenance for 30 days
b)
Machinery
Water tanker6 KL capacity
c)
Material
Doob grass
d&e) Overheads & Contractors Profit
Cost for 100 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/100
NOTE : In the case of horticulture one mate has been provided for
every 10 mazdoors as maintenance of grass and plants require more
care.
1.040
day
day
day
0.170
0.920
1.000
hour
0.500
kg
100.000
day
day
day
1.470
1.000
hour
0.750
kg
200.000
638
RBR-HRTC
Index-code
RBR-HRTC-3
RBR-HRTC-4
S. No
Description
2
Making Lawns including Ploughing and Dragging with 'Swagha'
Breaking of Clod as per Specification 307 MORTH
Making lawns including ploughing and breaking of clod, removal of
rubbish, dressing and supplying doobs grass roots and planting at 15
cm apart, including supplying and spreading of farm yard manure at
rate of 0.18 cum per 100 sqm
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate
Mazdoor (Unskilled) for preparation of ground
Mali for fetching doobs grass roots and grassing at 15 cm apart
b)
Machinery
Water tanker6 KL capacity
Tractor with tiller
c)
Material
Supply of farm yard manure at site of work
Fine grass
d&e) Overheads & Contractors Profit
Cost for 100 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/100
Maintenance of Lawns or Turfing of Slopes as per Specification
307 MORTH
Maintenance of lawns or Turfing of slopes (rough grassing)
for a
period of one year including watering etc
Unit = sqm
Taking output = 100 sqm
a) Labour
Mali
b)
Machinery
Water tanker6 KL capacity
c)
Material
Cost of water
d&e) Overheads & Contractors Profit
Cost for 100 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/100
RBR-HRTC-5
Unit Quantity
3
day
day
day
0.650
1.000
hour
hour
0.500
0.010
cum
kg
0.180
100.000
day
10.000
hour
15.000
KL
90.000
Rate
(Rs.)
Amount
(Rs.)
1.250
1.500
0.500
0.010
0.600
100.000
639
RBR-HRTC
Index-code
RBR-HRTC-6
S. No
Description
2
Maintenance of Lawns with Fine Grassing for the First Year as
per Specification 307 MORTH
Maintenance of lawns with fine grassing for the first year including
watering etc
Unit = sqm
Taking output = 100 sqm
a) Labour
Mali
b)
Machinery
Water tanker6 KL capacity
c)
Material
Cost of water
d&e) Overheads & Contractors Profit
Cost for 100 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/100
RBR-HRTC-7
Unit Quantity
3
day
10.000
hour
20.000
KL
60.000
Rate
(Rs.)
Amount
(Rs.)
day
day
Mazdoor (Unskilled) for refilling the excavated earth mixed with cow day
dung, preparation of ground and digging of plant, from the nursery
carriage to site and planting in position
b)
Machinery
Water tanker6 KL capacity
hour
c)
Material
Cost of hedge plants 2 rows at 30 cm apart
each
Supply of farm yard manure at site of work
cum
Pesticide
kg
Cost of water
KL
d&e) Overheads & Contractors Profit
Cost for 100 metres = a+b+c+d+e
Rate per metre = a+b+c+d+e)/100
(b) Maintenance of hedge for one year
Unit = Running metre
Taking output = 100 m
a) Labour
Mate
day
Mazdoor (Unskilled)
day
b)
Machinery
Water tanker6 KL capacity
hour
c)
Material
Manure sludge/Farm yard manure
cum
Pesticide
kg
Cost of water
KL
Cost of hedge plants @ 10 per cent casualty
each
d&e) Overheads & Contractors Profit
Cost for 100 metres = a+b+c+d+e
Rate per metre = a+b+c+d+e)/100
Mazdoor (Unskilled) for digging of trench 60 cm wide and 45 cm deep
10.000
5.400
0.500
2x340
4.670
0.250
3.000
33.000
5.000
2.000
0.500
30.000
68.000
640
RBR-HRTC
Index-code
S. No
1
RBR-HRTC-8
Description
2
Planting and Maintaining of Flowering Plants and Shrubs as per
Specification 307 MORTH
(a) Planting flowering plants and shrubs in central verge
Unit = Running metres 200 plants and 800 shrubs in two rows in
one km length of road where width of verge is 3m and above.
Unit Quantity
3
RBR-HRTC-9
Rate
(Rs.)
Amount
(Rs.)
13.200
6.000
200.000
800.000
63.640
0.500
36.000
401.000
90.000
10.000
180.000
20.000
80.000
day
day
day
3.700
15.000
hour
2.000
each
cum
kg
KL
10.000
0.940
0.500
12.000
641
RBR-HRTC
Index-code
S. No
Description
2
Renovation Lawns including, Weeding, Forking the Ground, Top
Dressing with Forked Soil as per Specification 308 MORTH
10
RBR-HRTC-10
RBR-HRTC-11
RBR-HRTC-12
11
12
RBR-HRTC-13 13
Unit Quantity
3
Rate
(Rs.)
Amount
(Rs.)
3.120
0.500
3.000
1.000
1.000
1.000
642
RBR-HRTC
Index-code
S. No
Description
2
Half Brick Circular Tree Guard, in 2nd Class Brick, internal
diameter 1.25 metres, and height 1.2 metres, above ground and
0.20 metre below ground
Half brick circular tree guard, in 2nd class brick, internal diametre
1.25 metres, and height 1.2 metres, above ground and 0.20 metre
below ground, bottom two courses laid dry, and top three courses in
cement mortar 1:6 (1 cement 6 sand) and the intermediate courses
being in dry honey comb masonry, as per design complete
14
RBR-HRTC-14
Unit = Each
Taking output = one tree guard
a) Labour
Mate
Mason
Mazdoor (Unskilled)
b)
Material
Brick 2nd class including carriage
Cement mortar 1:6
c&d) Overheads & Contractors Profit
Rate per tree Guard = a+b+c+d
RBR-HRTC-15 15
RBR-HRTC-16
16
Unit Quantity
3
day
day
day
0.250
0.300
Rate
(Rs.)
Amount
(Rs.)
each 230.000
cum
0.025
day
day
day
0.050
0.052
each
50.000
day
day
day
0.150
0.090
each
kg
each
1.000
0.650
22.000
Making Tree Guard 53 cm dia and 1.3 m High as per Design from
Empty Bitumen Drums
Making tree guard 53 cm dia and 1.3 m high as per design from
empty bitumen drum, slit suitably to permit sun and air, (supplied by
the department at stock issue rate) including providing and fixing 2
nos MS sheet rings 50 x 0.5 mm with rivets, complete in all respect
Unit = Each
Taking output = one tree guard
a) Labour
Mate
Blacksmith
Mazdoor (Unskilled)
b)
Material
Empty bitumen drum
MS sheet 50 x 0.5 mm
Rivets 6 mm dia and 10 mm in length
d&e) Overheads & Contractors Profit
Rate for each tree guard = a+b+c+d
643
RBR-HRTC
Index-code
RBR-HRTC-17
S. No
Description
2
Making Tree Guard 53 cm dia and 2 Metre High as per Design
from Empty Bitumen Drums
17
Unit Quantity
3
day
0.200
0.240
each
kg
each
1.500
0.650
50.000
day
day
day
2.000
2.950
quint
al
quint
al
1.050
0.050
day
day
day
0.250
0.300
kg
kg
19.200
9.600
hour
0.040
sqm
1.770
Rate
(Rs.)
Amount
(Rs.)
Making tree guard 53 cm dia and 2 metres high as per design from empty
bitumen drums, slit suitably to permit sun and air, ( supplied by the department
at stock issue rate)
including providing and fixing four legs 40 cm long of 30
x 3 mm MS riveted to tree guard and providing and fixing 2 nos MS sheet rings
50 x 0.5 mm with rivets complete in all respects
RBR-HRTC-18 18
Unit = Each
Taking output = one tree guard
a) Labour
Mate
Blacksmith
Mazdoor (Unskilled)
b)
Material
Empty bitumen drum
MS sheet 50 x 0.5 mm
Rivets 6 mm dia and 10 mm in length
c&d) Overheads & Contractors Profit
Rate for each tree guard = a+b+c+d
Wrought Iron and Mild Steel Welded Work
Wrought iron and mild steel welded work (using angles, square bars, tees and
channel grills, grating frames, gates and tree guards of any size and design etc.
including cost of screens and welding rods or bolts and nuts complete fixed in
position but without the cost of excavation and concrete for fixing which will be
paid separately
RBR-HRTC-19 19
Unit = quintal
Taking output = one quintal
a) Labour
Mate
Blacksmith/ welder for cutting to design and shape and jointing
Mazdoor (Unskilled) for fixing and helper for Blacksmith/welder
b)
Material
Angle, tees, channels etc
Deduct the cost of scrap
Add 5 per cent of cost of material for welding rods and other welding
accessories
c&d) Overheads & Contractors Profit
Rate per quintal = a+b+c+d
Tree Guard with MS Iron
Providing and fixing MS iron tree guard 60 cm dia and 2 metre high above
ground level formed of 4 Nos (25 x 6 mm) and 8 Nos (25 x 3 mm) vertical MS
riveted to 3 Nos (25 x 6 mm) iron rings in two halves, bolted together with 8 mm
dia and 30 mm long bolts including painting two coats with paint of approved
brand over a coat of priming, complete in all respects.
Unit = Each
Taking output = one tree guard
a) Labour
Mate
Blacksmith
Mazdoor (Unskilled)
b)
Material
MS iron 25 x 6 mm
MS iron 25 x 3 mm
Add 5 per cent of cost of material for riveting, bolting and welding accessories
c)
Machinery
Tractor-trolley
d)
Painting
Painting two coats including priming
e&f) Overheads & Contractors Profit
Rate per tree guard =a+b+c+d+e+f
1 The items of excavation and concreting to be measured and paid separately as per design .
2 . Rate of painting may be adopted from the chapter as Traffic signs.
RBR-HRTC-20 20
day
day
day
day
0.250
0.250
0.300
kg
kg
kg
13.500
18.000
6.000
644
RBR-HRTC
Index-code
S. No
1
RBR-HRTC-21 21
Description
Unit Quantity
2
3
Add 5 per cent of cost of material for riveting, bolting and welding
accessories
c)
Machinery
Tractor-trolley
hour
d)
Painting
Painting two coats including priming
sqm
e&f) Overheads & Contractors Profit
Rate per tree guard = a+b+c+d+e+f
Compensatory Afforestation
Planting trees as compensatory afforestation at the rate of 290 trees
per hectare at a spacing of 6 m by grubbing and leveling the ground
upto a depth of 150 mm, digging holes 0.9 m dia, 1 m deep, mixing
farm yard/sludge manure with soil, planting of sapling 2 m high with
25 cm dia stem, backfilling the hole and watering
Rate
(Rs.)
Amount
(Rs.)
0.040
1.500
Unit = Hectare
Taking output = one hectare
a) Labour
i) Planting
Mate
day
Mazdoor (Unskilled)
day
27.500
ii) For Maintenance for one year
Mate
day
Mazdoor (Unskilled)
day
50.500
b)
Machinery
Dozer 80 HP @ 1000 sqm/hour
hour 10.000
Water tanker6 KL capacity (for planting)
hour
3.000
Water tanker6 KL capacity (for maintenance)
hour 25.000
c)
Material
Sapling 1 to 1.5 m high 2 cm dia stem
each 290.000
Add 10 per cent of sapling
each 29.000
Decayed farm yard/sludge manure (planting)
cum 60.900
Decayed farm yard/sludge manure (maintenance)
cum
4.000
Pesticides for planting
kg
0.500
Pesticides for maintenance
kg
1.500
Cost of water
KL
18.000
d&e) Overheads & Contractors Profit
Rate per hectare = a+b+c+d+e
Cost of fencing to be provided as per size of plot and approved
design, measured and paid separately
General Note :
The provisions towards Mate is included in the provision towards unskilled Mazdoor.
645
RBR-RPRH
Index-code
S. No
Description
Unit
Quantity
Rate
(Rs.)
Amount
(Rs.)
2
Removal of existing cement concrete wearing coat including its
disposal complete as per Technical Specification 2809 MORTH
without causing any detrimental effect to any part of the bridge
structure and removal of dismantled material with all lifts and
lead upto 1000 m
Unit = Sq m ( Thickness 75 mm)
Taking output = 10 sqm
a) Labour
Mate
Mazdoor (Unskilled)
b)
Machinery
Air Compressor 250 cfm with pneumatic breaker/jack hammer along
with accessories.
Tractor-trolley.
c&d) Overheads & Contractors Profit
Cost for 10 sqm = (a+d+c+d)
Rate per sqm = (a+b+c+d)/10
Removal of existing asphaltic wearing coat comprising of 50 mm
thick asphaltic concert laid over 12 mm thick mastic asphalt
including disposal with all lift and lead upto 1000 m as per
Technical Specification 2809 MORTH.
Unit = Sq m
Taking output = 10 sqm
a) Labour
Mate
Mazdoor (Unskilled)
b)
Machinery
Air Compressor 250 cfm with pneumatic breaker.
Tractor-trolley.
c&d) Overheads & Contractors Profit
Cost for 10 sqm = (a+d+c+d)
Rate per sqm = (a+b+c+d)/10
Guniting concrete surface with cement mortar applied with
compressor after cleaning surface and spraying with epoxy
complete as per Technical Specification 2807 MORTH
Unit = Sq m
Taking output = 1 sqm
Assuming thickness 25 mm
a) Material
Cement
Graded sand
Wire mesh 50mm x 50mm size of 3mm wire
Epoxy
Accelerator compound for guniting @ 4 % of weight of cement
Add 2 per cent of cost of material for miscellaneous consumables like
nozzles, wire brush, cotton waste etc.
b)
Labour
Mate
Mason
Mazdoor (Unskilled)
c)
Machinery
Compressor with guniting equipment along with accessories
d&e) Overheads & Contractors Profit
Rate per sqm = (a+b+c+d+e)
day
day
1.06
hour
1.00
hour
0.50
day
day
0.78
hour
hour
0.75
0.40
kg
cum
kg
kg
kg
16.00
0.04
2.00
0.67
0.64
day
day
day
0.04
0.15
hour
0.10
RBR-RPRH-1
RBR-RPRH-2
RBR-RPRH-3
647
RBR-RPRH
Index-code
S. No
1
RBR-RPRH-4
Description
Unit
2
3
Providing and inserting nipples with approved fixing compound
after drilling holes for grouting as per Technical Specifications
2800 MORTH including subsequent cutting/removal and sealing
of the hole as necessary of nipples after completion of grouting
with Cement/Epoxy
Unit = Number
Taking output = 1 No.
a) Material
Nipples
each
Quantity
Rate
(Rs.)
Amount
(Rs.)
1.00
RBR-RPRH-5
RBR-RPRH-6
b)
Labour
Mate
Mazdoor (Skilled) labour for drilling
Mazdoor (Skilled) labour for fixing nipple and sealing inlets
Mazdoor (Unskilled) for cutting and removing of nipples
Add 10 per cent of labour cost for drilling holes etc
c&d) Overheads & Contractors Profit
Rate per No. = (a+b+c+d)
5
Sealing of cracks/porous concrete by injection process through
nipples/Grouting complete as per Technical Specification 2806
MORTH.
A Cement Grout
Unit = kg
Taking output = 1 kg
a) Material
Cement including 10 per cent wastage
Admixtures (anti shrinkage compound) @ 20 % of cost of cement
b)
Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
c)
Machinery
Grout pump with agitator and accessories
d&e) Overheads & Contractors Profit
Rate per kg = (a+b+c+d+e)
B Cement Mortar (1:1) Grouting
Unit = kg
Taking output = 1 kg
a) Material
Cement including 10 per cent wastage
Sand including 10 per cent wastage
Admixtures (anti shrinkage compound) @ 20 % of cost of cement
b)
Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
c)
Machinery
Grout pump with agitator and accessories
d&e) Overheads & Contractors Profit
Rate per kg = (a+b+c+d+e)
6
Patching of damaged concrete surface with polymer concrete
and curing compounds, initiator and promoter, available in
present formulations, to be applied as per instructions of
manufacturer and as approved by the Engineer as per Technical
Specification 2800 MORTH.
Unit = sqm
Taking output = 10 sqm for an average thickness of 25mm.
a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b)
Material
Pre-packed polymer concrete based on epoxy system complete with
curing compound, initiator and promoter including 5 per cent wastage.
day
day
day
day
0.08
0.08
0.05
kg
1.10
day
day
day
0.10
0.18
hour
0.10
kg
kg
0.55
0.55
day
day
day
0.10
0.18
hour
0.10
day
day
day
0.75
0.81
kg
315.00
c)
Machinery
Grout pump with agitator and accessories
hour
d&e) Overheads & Contractors Profit
Cost for 10 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/10
Note : This item is a proprietary item available in market as pre-packed
polymer concrete and is required to be applied as per instructions of the
manufacturer.
2.00
648
RBR-RPRH
Index-code
S. No
Description
Unit
Quantity
Rate
(Rs.)
Amount
(Rs.)
2
Sealing of crack / porous concrete with Epoxy Grout by injection
through nipples complete as per clause 2803.1 MORTH
kg
1.10
day
day
day
0.10
0.18
hour
0.10
kg
kg
kg
2.50
2.20
2.00
day
day
day
0.50
0.54
day
day
day
0.54
0.50
hour
hour
hour
1.00
1.00
0.02
kg
cum
cum
kg
KL
120.00
0.15
0.15
2.50
0.10
Litre
kg
1.40
12.00
day
day
0.50
RBR-RPRH-7
Unit = kg
Taking output = 1 kg
a) Material
Epoxy including 10 per cent wastage
b)
Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
c)
Machinery
Epoxy Injection gun
d&e) Overheads & Contractors Profit
Rate per kg = (a+b+c+d+e)
8
RBR-RPRH-8
RBR-RPRH-9
RBR-RPRH-10
10
649
RBR-RPRH
Index-code
RBR-RPRH-11
S. No
Description
Unit
Quantity
2
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Cost for 10 sqm = a+b+c+d
Rate per sqm = (a+b+c+d)/10
Epoxy bonding of new concrete to old concrete as per Technical
Specification 2805 MORTH.
Unit = sqm
Taking output = 10 sqm
a) Material
Epoxy resin with pot life not less than 60-90 minutes and satisfying
testing as per clause 2803.9
Add 3 per cent of (a ) above for wastage.
b)
Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Cost for 10 sqm = a+b+c+d
Rate per sqm = (a+b+c+d)/10
Providing external prestressing with high tensile steel
wires/strands including drilling for passage of prestessing steel,
all accessories for stressing and stressing operation and
grouting complete as per drawing and Technical Specification
2810 MORTH.
Span assumed: 25 m
No. of cables: 4 no.
No. of anchorages : 8 no.
Unit = MT
Taking output = 1 MT
Assume 12.7mm dia. Strand in 12T13 system. Weight-9.42 kg/m of
cable.
a) Material
3
day
4
0.54
kg
8.00
day
day
day
0.50
0.54
HTS strand including 5 per cent wastage and extra length for jacking
t
m
kg
1.05
112.00
400.00
11
12
RBR-RPRH-12
Rate
(Rs.)
Amount
(Rs.)
650
RBR-RPRH
Index-code
S. No
Description
Unit
Quantity
2
Tube anchorage set complete with bearing plate, permanent wedges
etc
Epoxy
MS plates for deviator (where deviator blocks are not provided)
Add 20 per cent cost of material for other materials like lead sheet,
sleeves, deviator fixtures etc.
b)
Labour
i) For making holes in the structure .
Mate
Mazdoor (Semi-skilled)
Mazdoor (Unskilled)
ii) For making and fixing anchorages for cables and placement of
cables .
Mate
Blacksmith
Mazdoor (Unskilled)
iii) For prestressing
Mate/Supervisor
Fitter
Mazdoor (Unskilled)
iv) For grouting
Mate/Supervisor
Mason
Mazdoor (Unskilled)
c)
Machinery
Stressing jack with pump
Grouting pump with agitator
d&e) Overheads & Contractors Profit
Rate per MT = (a+b+c+d+e)
Providing external prestressing with high tensile steel
wires/strands including drilling for passage of prestessing steel,
all accessories for stressing and stressing operation and
grouting complete as per drawing and Technical Specification
2810 MORTH.
Span assumed: 50 m
No. of cables: 4 no.
No. of anchorages : 8 no.
Unit = MT
Taking output = 3.10 MT
Assume 12.7mm dia. Strand in 19T13 system. Weight-14.73 kg/m of
cable.
a) Material
3
each
4
8.00
kg
t
6.00
2.10
day
day
day
3.00
3.24
day
day
day
3.00
8.44
day
day
day
0.70
2.78
day
day
day
0.70
2.78
hour
hour
4.00
1.35
HTS strand including 5 per cent wastage and extra length for jacking
t
m
t
each
3.10
224.00
1.01
8.00
kg
t
10.00
7.00
day
day
day
8.00
8.08
day
day
day
7.00
26.28
day
day
day
1.00
4.20
day
day
day
1.50
5.26
hour
hour
7.00
3.00
13
RBR-RPRH-13
Rate
(Rs.)
Amount
(Rs.)
651
RBR-RPRH
Index-code
S. No
Description
Unit
Quantity
Rate
(Rs.)
Amount
(Rs.)
2
Providing external prestressing with high tensile steel
wires/strands including drilling for passage of prestessing steel,
all accessories for stressing and stressing operation and
grouting complete as per drawing and Technical Specification
2810 MORTH.
Span assumed: 100 m
No. of cables: 6 no.
No. of anchorages : 12 no.
Unit = MT
Taking output = 9.28 MT
Assume 12.7mm dia. Strand in 19T13 system. Weight-14.73 kg/m of
cable.
a) Material
t
m
t
each
9.28
672.00
3.04
12.00
kg
t
14.00
20.00
day
day
day
18.00
26.72
day
day
day
20.00
84.00
day
day
day
1.50
6.30
day
day
day
5.00
21.00
hour
hour
10.00
10.00
14
RBR-RPRH-14
HTS strand including 5 per cent wastage and extra length for jacking
652
RBR-RPRH
Index-code
RBR-RPRH-15
S. No
Description
Unit
Quantity
Rate
(Rs.)
Amount
(Rs.)
2
Replacement of Bearings complete as per Technical Specification
2808 MORTH
Unit = No
Taking output = 3 No.
Lifting of superstructure span by jacking up from below i.e. by placing
the jacks on pier/abutment caps for span length of 30m.
15
a) Lifting of span
i) Hire charges for jack of 40 tonne lifting capacity.
Day
Mate
day
Mazdoor (Skilled)
day
Mazdoor (Unskilled)
day
v) Wooden packing
cum
b)
Replacement of bearing
Cost of bearing.
each
c&d) Overheads & Contractors Profit
Cost of repair of 3 bearings = a+b+c+d
Rate of repair per bearing = (a+b+c+d)/3
Note : The work entails replacement of all the bearings on one side of the span.
RBR-RPRH-16
RBR-RPRH-17
16
17
3.00
4.00
12.64
0.15
3.00
3.00
4.00
12.64
0.15
3.00
9.60
3.60
6.26
0.50
653
RBR-RPRH
Index-code
S. No
1
RBR-RPRH-18
18
Description
2
Replacement of Damaged Concrete Railing.
Unit = RM
Taking output = 10 RM
a) Labour
Unit
Quantity
Rate
(Rs.)
Amount
(Rs.)
RBR-RPRH-19
19
Mate
day
Mazdoor (Unskilled)
day
b)
Machinery
Tractor-trolley for disposal of dismantled material
hour
c&d) Overheads & Contractors Profit
Cost for 10 m = a+b+c+d
Rate per metre = (a+b+c+d)/10
Note : The rate for the provision of new railing may be adopted from the
chapter on superstructure.
Replacement of Crash Barrier.
Unit = RM
Taking output = 10 M
a) Labour
5.20
1.00
RBR-RPRH-20
20
Mate
day
Mazdoor (Unskilled)
day
b)
Machinery
Tractor-trolley for disposal of dismantled material
hour
c&d) Overheads & Contractors Profit
Cost for 10 m = a+b+c+d
Rate per metre = (a+b+c+d)/10
Note : The rate for the construction of new crash barrier may be adopted from
chapter 8 on Traffic and Transportation.
Replacement of Damaged Mild Steel Railing
Unit = RM
Taking output = 10 M
a) Labour
10.40
1.00
Mate
Mazdoor (Unskilled)
b)
Machinery
Tractor-trolley for disposal of dismantled material
c&d) Overheads & Contractors Profit
Cost for 10 m = a+b+c+d
Rate per metre = (a+b+c+d)/10
RBR-RPRH-21
21
day
day
4.16
hour
1.00
1.04
0.30
654
RBR-RPRH
Index-code
S. No
1
RBR-RPRH-22
22
Description
Unit
Quantity
Rate
(Rs.)
Amount
(Rs.)
RBR-RPRH-23
23
0.10
0.01
0.216
kg
kg
kg
29.00
10.00
1.00
day
day
day
0.20
0.216
General Note :
The provisions towards Mate is included in the provision towards unskilled Mazdoor.
655
BLD-CSTN
S No
Description
Unit
Quantity
BLD-CSTN-1
BLD-CSTN-1-1
BLD-CSTN-1-3
BLD-CSTN-1-4
BLD-CSTN-1-5
Amount
Rs.
6
MORTARS
1
Cement Mortar (1 : 1)
Unit : 1cum
A. MATERIALS:
Cement
Sand (including 5% wastage)
Seigniorage charges for sand
B. MACHINERY
- Nil C. LABOUR:
Man mazdoor for mixing mortar
Grand Total
BLD-CSTN-1-2
Rate
Rs.
5
kg.
1440.00
cum
1.05
cum
1.05
day
0.20
kg.
960.00
cum
1.05
cum
1.05
day
0.20
kg.
720.00
cum
1.05
cum
day
0.20
kg.
480.00
cum
1.05
cum
1.05
day
0.20
kg.
360.00
cum
1.05
cum
1.05
day
0.20
Grand Total
659
Remarks
7
BLD-CSTN
Index-code
S No
BLD-CSTN-1-6
1
6
BLD-CSTN-1-7
BLD-CSTN-1-8
Unit
Quantity
Cement Mortar (1 : 5)
Unit : 1cum
A. MATERIALS:
Cement
Sand (including 5% wastage)
Seigniorage charges for sand
B. MACHINERY
- Nil C. LABOUR:
Man mazdoor for mixing mortar
Grand Total
Cement Mortar (1 : 6)
Unit : 1cum
A. MATERIALS:
Cement
Sand (including 5% wastage)
Seigniorage charges for sand
B. MACHINERY
- Nil C. LABOUR:
Man mazdoor for mixing mortar
Grand Total
Cement Mortar (1 : 8)
Unit : 1cum
A. MATERIALS:
Cement
Sand (including 5% wastage)
Seigniorage charges for sand
B. MACHINERY
- Nil C. LABOUR:
Man mazdoor for mixing mortar
Grand Total
kg.
288.00
cum
1.05
cum
1.05
Rate
Rs.
5
Amount
Rs.
6
day
0.20
kg.
240.00
cum
1.05
cum
1.05
day
0.20
kg.
180.00
cum
1.05
cum
1.05
day
0.20
Kg
cum
cum
400.00
0.90
0.45
cum
0.90
cum
0.45
BLD-CSTN-2
BLD-CSTN-2-1
Description
day
Mason 1st class
day
Mazdoor (unskilled)
kl
Water (including for curing)
Grand Total
Note : For Nominal Mix : Considering table 9 IS 456 : 2000,
the quantity of cement needed is 405 kgs / cum. Hence
proposed 400 kgs of cement for cum of CC M20
0.10
2.36
1.20
660
Remarks
7
BLD-CSTN
Index-code
BLD-CSTN-2-2
S No
1
10
Description
Unit
Quantity
Kg
220.00
cum
cum
cum
0.90
0.45
0.90
cum
kl
0.45
1.20
hour
1.00
day
0.10
day
1.39
Rate
Rs.
5
Amount
Rs.
6
C. LABOUR:
Mason 1st class
Mazdoor (unskilled)
Grand Total
BLD-CSTN-2-3
BLD-CSTN-2-4
11
12
13
BLD-CSTN-2-5
kg
275.00
cum
0.48
cum
0.54
cum
0.27
cum
0.09
kl
1.20
day
0.10
day
2.36
kg
162.00
cum
0.90
cum
0.45
cum
0.90
cum
0.45
kl
1.20
day
0.10
day
2.36
kg
162.00
cum
0.90
cum
0.45
cum
0.90
cum
0.45
kl
1.20
hour
1.00
661
Remarks
7
BLD-CSTN
Index-code
S No
1
Description
Unit
Quantity
day
0.10
day
1.39
-
kg
cum
129.60
0.90
cum
0.45
cum
0.90
cum
0.45
kl
1.20
day
0.10
day
2.36
C. LABOUR:
Mason 1st class
Mazdoor (unskilled)
Water Charges 1%
Grand Total
BLD-CSTN-2-6
14
15
BLD-CSTN-2-7
Rate
Rs.
5
Amount
Rs.
6
plinth level.
Unit = 1cum
A. MATERIALS:
Cement
Coarse aggregate 40 mm
Fine aggregate (Sand)
Seigniorage charges for C.A
Seigniorage charges for F.A
Water (including for curing)
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity
C. LABOUR:
BLD-CSTN-2-8
BLD-CSTN-2-9
16
17
kg
129.60
cum
0.90
cum
0.45
cum
0.90
cum
0.45
kl
1.20
hour
1.00
day
0.10
day
1.39
kg
129.60
cum
0.90
cum
0.54
cum
0.90
cum
0.54
kl
1.20
day
0.10
day
2.36
kg
129.60
cum
0.90
cum
0.54
cum
0.90
cum
0.54
kl
1.20
662
Remarks
7
BLD-CSTN
Index-code
S No
1
Description
Unit
Quantity
hour
1.00
day
0.10
day
1.39
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity
C. LABOUR:
BLD-CSTN-2-10
BLD-CSTN-2-11
BLD-CSTN-2-12
18
19
20
Kg
220.00
cum
0.90
cum
0.45
cum
0.90
cum
0.45
kl
1.20
day
0.10
day
2.36
Kg
330.00
cum
0.90
cum
0.45
cum
0.90
cum
0.45
kl
1.20
hour
1.00
day
0.10
day
1.39
Kg
275.000
cum
0.540
cum
0.270
cum
0.090
cum
0.480
cum
0.900
cum
0.480
kl
1.20
hour
1.000
day
0.100
day
1.390
Rate
Rs.
5
Amount
Rs.
6
663
Remarks
7
BLD-CSTN
Index-code
BLD-CSTN-2-13
S No
Description
1
2
21 R.C.C. M-20 Nominal Mix
NEW RCC M- 20 Nominal mix (Cement:fine aggregate:
Unit
Quantity
cum
cum
Kgs
0.900
0.450
400.000
day
day
day
0.133
0.267
3.600
hour
Liters
Liters
kl
1.000
0.133
0.667
1.200
cum
cum
Kgs
0.900
0.450
400.000
day
day
day
0.167
0.167
4.700
hour
kl
1.000
1.200
cum
cum
Kgs
0.900
0.450
400.000
day
day
day
0.067
0.133
2.500
hour
kl
0.267
1.200
Rate
Rs.
5
Amount
Rs.
6
A. MATERIALS:
20mm HBG graded metal
Sand
Cement
B. LABOUR:
1st Class Mason
2nd Class Mason
Mazdoor (Both Men and Women)
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity
Cost of Diesel for Miller
Cost of Petrol for Vibrator
Water (including for curing)
BASIC COST per 1 cum
B
A. MATERIALS:
20mm HBG graded metal
Sand
Cement
B. LABOUR:
1st Class Mason
2nd Class Mason
Mazdoor (Both Men and Women)
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity
Water (including for curing)
BASIC COST per 1 cum
C
A. MATERIALS:
20mm HBG graded metal
Sand
Cement
B. LABOUR:
1st Class Mason
2nd Class Mason
Mazdoor (Both Men and Women)
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity
Water (including for curing)
BASIC COST per 1 cum
664
Remarks
7
BLD-CSTN
Index-code
S No
Description
Unit
Quantity
22
Rate
Rs.
5
Amount
Rs.
6
BLD-CSTN-2-14
cum
cum
day
day
day
h
0.80
0.40
0.133
0.267
4.600
1.333
kl
1.200
cum
cum
day
day
day
H
kl
0.80
0.40
0.167
0.167
5.600
1.333
1.200
cum
cum
day
day
day
h
kl
0.80
0.40
0.067
0.133
3.077
0.308
1.200
Grade
Kgs
M 20
350
M 25
M 30
M 35
M 40
380
400
420
430
665
Remarks
7
BLD-CSTN
Index-code
S No
1
23
BLD-CSTN-2-15
Description
Unit
Quantity
Rate
Rs.
5
Amount
Rs.
6
Unit : 1cum
A. MATERIALS:
Coarse aggregate 20mm graded
Fine aggregate (Sand)
Seigniorage charges for C.A
Seigniorage charges for F.A
Water (including for curing)
B. MACHINERY
Batching plant at 20 cum per hour
Transit mixer 4cum capacity for lead upto 1km
Concrete Pump
C. LABOUR:
Mason 1st class
Mason 2nd class
Mazdoor (unskilled)
Grand Total
Note : Wherever concrete is carried out using
batching plant, transit mixer, concrete pump, then
Admixtures @ 0.4% of weight of cement may be
added for achieving desired slump of concrete. If
concentrated Admixture is proposed, only 0.04% of
weight of Cement shall be used.
B
cum
0.80
cum
0.40
cum
0.80
cum
0.40
kl
1.20
hour
0.222
hour
0.222
day
0.222
day
0.056
day
0.056
day
0.917
cum
0.80
cum
0.40
cum
0.80
cum
0.40
Unit : 1cum
A. MATERIALS:
Coarse aggregate 20mm graded
Fine aggregate (Sand)
Seigniorage charges for C.A
Seigniorage charges for F.A
Water (including for curing)
B. MACHINERY
Batching plant at 20 cum per hour
kl
1.20
hour
0.444
hour
0.444
Concrete Pump
C. LABOUR:
day
0.444
day
0.111
day
0.222
day
1.556
cum
0.80
cum
0.40
cum
0.80
cum
0.40
kl
1.20
A. MATERIALS:
Coarse aggregate 20mm graded
Fine aggregate (Sand)
Seigniorage charges for C.A
Seigniorage charges for F.A
Water (including for curing)
666
Remarks
7
BLD-CSTN
Index-code
S No
Description
Unit
Quantity
hour
0.133
hour
day
0.133
0.133
day
0.033
day
0.067
day
0.433
B. MACHINERY
Batching plant at 20 cum per hour
Transit mixer 4cum capacity for lead upto 1km
Concrete Pump
C. LABOUR:
Mason 1st class
Mason 2nd class
Mazdoor (unskilled)
Grand Total
For Design mix concrete, allow Cement as follows (for
estimate purpose only) :
Rate
Rs.
5
Grade
Kgs
M 20
M 25
M 30
M 35
M 40
350
Amount
Rs.
6
380
400
420
430
24
BLD-CSTN-2-16
Description of Structure
Nil
for each
additional floor
(3.05 M) over
and above 2nd
floorNil
(6.1 M)
1.333
Hrs
10%
0.267
Hrs
10%
kgs
cum
320.00
0.90
cum
cum
cum
L.S.
0.45
0.90
0.45
hour
1.00
Unit = 25 sqm
A. MATERIALS:
Cement
Coarse aggregate 12mm
Fine aggregate (sand)
Seigniorage charges of coarse aggregate
day
0.1
day
1.98
667
Remarks
7
BLD-CSTN
Index-code
BLD-CSTN-2-17
S No
Description
Unit
Quantity
1
25
2
Damp proof course 50mm thick with 1:2:4 cement
concrete Nominal mix, using 12mm hard broken stone
aggregate including cost of all materials, seigniorage
charges, excluding conveyance charges of materials
including the cost of machinery, labour charges,
mixing, placing in position, leveling, vibrating, curing
etc. complete for finished item of work. (Using
concrete mixer)
kgs
cum
cum
cum
cum
L.S.
320.00
0.90
0.45
0.90
0.45
hour
1.00
day
day
0.1
1.98
1.05
kg
6.00
day
day
2.00
1.025
each
70.000
Hr
10.00
kg
6.00
Unit = 20 sqm
A. MATERIALS:
Cement
Coarse aggregate 12mm
Fine aggregate (sand)
Seigniorage charges of coarse aggregate
Rate
Rs.
5
Amount
Rs.
6
6.40
668
Remarks
7
BLD-CSTN
Index-code
S No
Description
Unit
Quantity
day
2.50
day
2.00
day
6.40
1.05
kg
6.00
day
day
2.00
27
11.8
BLD-CSTN-2-19
1000
&
1200
28
11.9
BLD-CSTN-2-20
1000
&
1200
Rate
Rs.
5
Amount
Rs.
6
6.40
1.025
each
70.000
Hr
10.00
kg
6.00
day
2.50
day
2.00
day
6.40
1.05
kg
6.00
day
day
2.00
6.40
669
Remarks
7
BLD-CSTN
Index-code
S No
1
Description
Unit
Quantity
Rate
Rs.
5
Amount
Rs.
6
BLD-CSTN-3
BLD-CSTN-3-1
Mason 2 class
Mazdoor (unskilled)
Grand Total
Note : For Bricks 2.4 % wastage taken.
ii
iii
Mason 2 class
Mazdoor (unskilled)
Grand Total
Brick Masonry in CM (1:5) with Bricks traditional
size 23 x 11 x 7 cms 2nd class
Unit = 1cum
A. MATERIALS:
Cement
Bricks traditional size 23 x 11 x 7 cms 2nd class
Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:
Mason 1st class
nd
Mason 2 class
Mazdoor (unskilled)
Grand Total
kg
96.00
Nos
cum
512.00
0.20
cum
0.20
day
0.24
day
0.56
day
1.89
kg
72.00
Nos
512.00
cum
0.20
cum
0.20
day
0.24
day
0.56
day
1.89
kg
57.60
Nos
cum
512.00
0.20
cum
0.20
day
0.24
day
0.56
day
1.89
670
Remarks
7
BLD-CSTN
Index-code
S No
1
iv
Description
Unit
Quantity
kg
48.00
Nos
cum
512.00
0.20
cum
0.20
day
0.24
day
0.56
day
1.89
kg
36.00
Nos
512.00
cum
0.20
cum
0.20
day
0.24
day
0.56
day
1.89
kg
96.00
Nos
512.00
cum
0.20
cum
0.20
day
0.24
day
0.56
Mason 2 class
day
Mazdoor (unskilled)
Grand Total
Note : 1. When Mortar mix is changed as CM 1:4, 1:5, 1:6
and 1:8, proportionate quantity of cement has to be
substituted. No change in other data.
Rate
Rs.
5
Amount
Rs.
6
1.89
671
Remarks
7
BLD-CSTN
Index-code
BLD-CSTN-3-2
S No
1
30
i
Description
Unit
Quantity
ii
Mason 2 class
Mazdoor (unskilled)
Grand Total
Brick Masonry in CM (1:4) with Modular Bricks
19 x 9 x 9 cms 2nd class
Unit = 1cum
A. MATERIALS:
Cement
Bricks modular size 19 x 9 x 9 cms 2nd class
Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:
Mason 1st class
nd
iii
Mason 2 class
Mazdoor (unskilled)
Grand Total
Brick Masonry in CM (1:5) with Modular Bricks
19 x 9 x 9 cms 2nd class
Unit = 1cum
A. MATERIALS:
Cement
Bricks modular size 19 x 9 x 9 cms 2nd class
Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:
iv
100.60
520.00
0.21
cum
0.21
day
0.24
day
0.56
day
1.89
kg
75.60
Nos
cum
520.00
0.21
cum
0.21
day
0.24
day
0.56
day
1.89
kg
60.48
Nos
cum
520.00
0.21
cum
0.21
day
0.24
day
0.56
day
1.89
kg
50.40
Nos
cum
520.00
0.21
cum
0.21
day
0.24
Mason 2 class
Mazdoor (unskilled)
Grand Total
Brick Masonry in CM (1:8) with Modular Bricks
19 x 9 x 9 cms 2nd class
Unit = 1cum
A. MATERIALS:
Cement
day
0.56
day
1.89
kg
37.80
Nos
cum
520.00
0.21
cum
0.21
iv
kg
Nos
cum
Rate
Rs.
5
Amount
Rs.
6
672
Remarks
7
BLD-CSTN
Index-code
S No
Description
Unit
Quantity
3
day
4
0.24
day
0.56
day
1.89
nos
565.000
31
BLD-CSTN-3-3
32
BLD-CSTN-3-4
BLD-CSTN-3-5
106.000
0.220
cum
0.220
day
0.600
day
0.600
day
Amount
Rs.
6
2.750
1.00%
Ground Floor :
A. MATERIALS:
II Class Bricks
C.M.(1:6)
B. LABOUR:
33
kg.
cum
Rate
Rs.
5
cum
512.000
cum
0.200
day
0.600
day
0.600
day
2.750
nos
kg.
520.000
48.00
673
Remarks
7
BLD-CSTN
Index-code
S No
Description
Unit
Quantity
3
cum
4
0.20
cum
0.20
Sand
Seigniorage charges for sand
B. LABOUR:
34
BLD-CSTN-3-6
35
BLD-CSTN-3-7
36
BLD-CSTN-3-8
Rate
Rs.
5
Amount
Rs.
6
day
0.57
Mason 1st class
nd
day
0.57
Mason 2 class
day
2.54
Mazdoor (unskilled)
1.00%
Add water charges 1%
Grand Total
Note : Compressive strength of individual Brick
shall not be less than 70 kg / cm2
Brickwork in arches in cement mortar 1:4
complete including centering and shuttering
excluding pointing and plastering as per
drawing and technical specifications Clauses
606 and 1205.1 MORD
Unit = cum
a) Material
Nos.
525.00
Brick 1st class
cum
0.24
Cement mortar (1:4)
b) Labour
day
1.88
Mazdoor (Unskilled)
day
2.00
Mason (1st Class)
c) Add for centering and shuttering @ 110% of
(a+b)
Grand Total
Note : 1 ) In case cement mortar 1:3 is used, proportionate rate is to be adopted.
2) Quantity of bricks for arches will be about 10 per cent more than that for ordinary
brickwork .
3) In case special arch bricks are used, the quantity of bricks per cum shall be taken as
580 Nos.
4) Rates for spandrel walls shall be taken same as for brickwork in substructure.
5) Rate for spandrel filling will depend on the filling material adopted
6) Compressive strength of individual Brick shall not be less than 70 kg / cm2
Honey Comb work with Bricks of traditional Size
and Plastered One Coat 10 mm. thick Cement
Mortar 1:5 including White Washing 2 Coats
Unit = cum
a) Material
Brick 2nd class 23 x 11 x 7
Cement mortar (1:5)
b) Labour
Mazdoor (Unskilled)
Mason (1st Class)
Mason (2nd Class)
White Washing 2 Coats
Grand Total
Honey Comb work with Bricks of Modular Size
and Plastered One Coat 10 mm. thick Cement
Mortar 1:5 including White Washing 2 Coats
Unit = cum
a) Material
Brick 2nd class 19 x 9 x 9
Cement mortar (1:5)
b) Labour
Mazdoor (Unskilled)
Mason (1st Class)
Mason (2nd Class)
White Washing 2 Coats
Grand Total
Nos.
750.00
cum
0.67
day
day
day
LS
6.60
2.41
6.21
LS
Nos.
790.00
cum
0.67
day
6.60
day
2.41
day
6.21
LS
LS
674
Remarks
7
BLD-CSTN
Index-code
S No
1
Unit
Quantity
Rate
Rs.
5
Amount
Rs.
6
BLD-CSTN-4
BLD-CSTN-4-1
Description
37
kg
115.20
cum
0.89
cum
0.16
cum
0.16
cum
0.16
day
day
1.05
2.45
day
3.50
day
2.80
BLD-CSTN-4-2
38
i
ii
iii
Unit = 1cum
A. MATERIALS:
Cement
Coursed Rubble Stone
Bond Stones 7Nos 0.24 x 0.24 x 0.39 = 0.16cum
Fine aggregate (Sand)
Seigniorage charges for F.A
Seigniorage charges for Stone
B. LABOUR:
Mason 1st class
Mazdoor (unskilled)
Grand Total
CRS Masonry in CM (1:3) 1st Sort
Unit = 1cum
A. MATERIALS:
Cement
Coursed Rubble Stone
Bond Stones 7Nos 0.24 x 0.24 x 0.39 = 0.16cum
Fine aggregate (Sand)
Seigniorage charges for F.A
Seigniorage charges for Stone
B. LABOUR:
Mason 1st class
Mazdoor (unskilled)
Grand Total
CRS Masonry in CM (1:4) 1st Sort
Unit = 1cum
A. MATERIALS:
Cement
Coursed Rubble Stone
Bond Stones 7Nos 0.24 x 0.24 x 0.39 = 0.16cum
Fine aggregate (Sand)
Seigniorage charges for F.A
Seigniorage charges for Stone
B. LABOUR:
Mason 1st class
Mazdoor (unskilled)
Grand Total
kg
201.60
cum
0.94
7Nos.
0.16
cum
0.28
cum
cum
0.28
1.10
day
day
2.50
2.32
kg
134.40
cum
0.94
7Nos.
0.16
cum
0.28
cum
cum
0.28
1.10
day
day
2.50
2.32
kg
100.80
cum
0.94
7Nos.
cum
0.16
0.28
cum
cum
0.28
1.10
day
day
2.50
2.32
675
Remarks
7
BLD-CSTN
Index-code
S No
1
iv
BLD-CSTN-4-3
39
Description
Unit
Quantity
kg
67.20
cum
0.94
7Nos.
cum
0.16
0.28
cum
cum
0.28
1.10
day
day
2.50
2.32
kg
76.80
cum
0.94
cum
0.16
cum
0.32
cum
0.32
cum
1.10
day
Mason 1st class
day
Mazdoor (unskilled)
Grand Total
Note : When Mortar mix is changed proportionate quantity of
cement has to be substituted. No change in other data.
BLD-CSTN-4-4
Amount
Rs.
6
Unit = 1cum
A. MATERIALS:
Cement
Coursed Rubble Stone
Bond Stones 7Nos 0.24 x 0.24 x 0.39 = 0.16cum
Fine aggregate (Sand)
Seigniorage charges for F.A
Seigniorage charges for Stone
B. LABOUR:
40
Rate
Rs.
5
1.50
2.32
cum
0.94
Nos.
0.16
cum
0.30
day
3.00
day
2.43
BLD-CSTN-4-5
41
Unit = 1cum
A. MATERIALS:
Cement
kg
57.60
cum
0.89
cum
0.16
0.16
cum
0.16
676
Remarks
7
BLD-CSTN
Index-code
S No
Description
Unit
Quantity
day
5.05
day
2.45
day
6.30
Rate
Rs.
5
Amount
Rs.
6
B. LABOUR:
BLD-CSTN-4-6
42
43
BLD-CSTN-4-7
LS
kg
cum
100.80
1.15
cum
cum
0.28
0.28
day
0.90
day
day
2.10
2.43
LS
0.40
cum
0.45
cum
0.54
cum
0.36
day
0.20
day
2.15
hour
0.40
II
Grand Total
RCC Grade M 25 (Design mix)
a) Material
Cement
Coarse sand
20 mm aggregate
10 mm aggregate
b) Labour
Mason (1st Class)
Mazdoor (Unskilled)
c) Machinery
Concrete mixer 0.4/0.28 cum capacity
0.38
cum
0.45
cum
0.54
cum
0.36
day
0.20
day
2.15
hour
0.40
Grand Total
Note : The additional cost of centering and shuttering @ 50 per cent
of cost of material and labour shall hold good for arch spans of 6 m
and above. For lesser length of spans, the corresponding additional
cost can be taken as 40 per cent for spans above 4 m length and 30
per cent for spans less than 4 m.
677
Remarks
7
BLD-CSTN
Index-code
S No
BLD-CSTN-4-8
1
44
BLD-CSTN-4-9
45
Description
Unit
Quantity
RR Masonry in CM (1:6)
Unit = 1cum
A. MATERIALS:
Cement
CR Stone
Rough Stone
Bond Stones 7Nos 0.24 x 0.24 x 0.39 = 0.16cum
Fine aggregate (Sand)
Seigniorage charges for F.A
Seigniorage charges for Stone
B. LABOUR:
Mason 1st class
Mazdoor (unskilled)
Grand Total
RR Masonry in CM (1:8)
Unit = 1cum
A. MATERIALS:
Cement
CR Stone
Rough Stone
Bond Stones 7Nos 0.24 x 0.24 x 0.39 = 0.16cum
Fine aggregate (Sand)
Seigniorage charges for F.A
Seigniorage charges for Stone
B. LABOUR:
kg
79.20
cum
0.44
cum
0.50
cum
cum
0.16
0.33
cum
cum
0.33
1.10
day
1.20
day
2.00
kg
59.40
cum
0.44
cum
0.50
cum
cum
0.16
0.33
cum
cum
0.33
1.10
day
Mason 1st class
day
Mazdoor (unskilled)
Grand Total
Note : When Mortar mix is changed proportionate quantity
of cement has to be substituted. No change in other data
BLD-CSTN-4-10
BLD-CSTN-4-11
46
47
Rate
Rs.
5
Amount
Rs.
6
Remarks
7
1.20
2.00
cum
cum
1.04
0.16
cum
1.20
day
0.33
day
0.77
day
1.10
cum
cum
1.04
0.16
cum
1.20
day
0.45
day
1.05
day
1.10
678
BLD-CSTN
Index-code
S No
1
48
BLD-CSTN-4-12
Description
Unit
Quantity
sqm
10.50
cum
0.15
day
0.90
day
2.10
day
2.00
BLD-CSTN-5-2
49
50
BLD-CSTN-5-3
51
52
BLD-CSTN-5-4
Amount
Rs.
6
POINTING
BLD-CSTN-5
BLD-CSTN-5-1
Rate
Rs.
5
kg
14.40
cum
0.03
cum
0.03
day
0.50
day
0.74
kg
14.40
cum
0.03
cum
0.03
day
0.50
day
0.74
kg
28.80
cum
0.06
cum
0.06
day
0.50
day
0.74
cum
0.038
day
day
1.460
2.260
679
Remarks
7
BLD-CSTN
Index-code
S No
1
BLD-CSTN-6
BLD-CSTN-6-1
Description
Unit
Quantity
cum
0.15
cum
0.15
day
0.60
day
0.96
cum
0.15
cum
0.15
day
0.60
day
0.96
BLD-CSTN-6-3
cum
0.150
cum
0.150
day
0.60
day
0.96
BLD-CSTN-6-4
cum
0.15
cum
0.15
day
0.60
day
0.96
BLD-CSTN-6-5
cum
0.15
cum
0.15
day
0.60
day
0.96
Amount
Rs.
6
PLASTERING
53
BLD-CSTN-6-2
Rate
Rs.
5
54
55
56
57
680
Remarks
7
BLD-CSTN
Index-code
S No
BLD-CSTN-6-6
1
58
Description
Unit
Quantity
cum
0.19
cum
0.19
day
0.60
day
0.96
BLD-CSTN-6-8
59
cum
0.210
cum
0.21
day
0.94
day
1.60
60
cum
0.210
cum
0.21
61
BLD-CSTN-6-9
day
Mason 2nd class
day
Mazdoor (unskilled)
Grand Total
Note : When Mortar mix is changed proportionate quantity of
cement has to be substituted
Plastering with CM 2 coats, 20 mm thick, base
coat in CM (1:6), 16mm thick and top coat in CM
(1:4), 4mm thick with Dubara sponze finishing.
Unit = 10 sqm
A. MATERIALS:
Base Coat in CM(1:6), 16 mm thick
Cement
Fine aggregate (Sand)
Top Coat in CM(1:4), 4 mm thick
Cement
Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:
BLD-CSTN-6-10
Remarks
7
0.94
1.60
kg
43.00
cum
0.18
kg
14.50
cum
0.04
cum
0.22
day
Mason 1st class
nd
day
Mason 2 class
day
Mazdoor (unskilled)
Grand Total
Note : When Mortar mix is changed proportionate quantity of
cement has to be substituted
62
Amount
Rs.
6
BLD-CSTN-6-7
Rate
Rs.
5
0.63
1.47
3.90
kg
31.70
cum
0.11
kg
19.20
cum
0.04
681
BLD-CSTN
Index-code
S No
1
Description
Unit
Quantity
3
cum
4
0.15
63
BLD-CSTN-6-11
day
Mason 1st class
nd
day
Mason 2 class
day
Mazdoor (unskilled)
Grand Total
Note : When Mortar mix is changed proportionate quantity of
cement has to be substituted
RCM FACIA WORKS
RCM facia 5cm thick in CM (1:3) for drop walls, fins with
rabbit wire mesh & nominal reinforcement as directed by
Engineer-in-charge with dubara sponge finishing, including
cost & conveyance of all materials to site, seigniorage
charges, sales & other taxes on all materials, operational &
incidental, cost and conveyance of cement, wire mesh, water
to work site, centering, scaffolding and form work, lift
charges etc., complete for finished items of work but
excluding cost of steel & its fabrication charges, for finished
item of work. (APSS No.403 & 903)
Unit - 10 sqm
A) MATERIALS
Rabbit wire mesh (1.0 M panna for 0.6 M drop)
Cement Mortar 1:3 for 25 mm thick
Dry Cement for making Lumps
12 mm Plastering 2 coats in 1:4 & 1:2 cm both sides
Excluding HYSD Steel/ Mild steel & Binding wire
B) LABOUR CHARGES
1st Class Mason
Miller Operator
Mazdoor (unskilled)
c) Machinery
Machine Mixing Mortar with Miller - Hire charges
BASIC COST per 10 sqm
64
BLD-CSTN-6-12
sqm
Rate
Rs.
5
Amount
Rs.
6
0.63
1.47
3.90
13.30
cum
0.25
kg
50.00
sqm
21.80
day
8.00
day
1.00
day
10.00
32.00
Hrs
2.00
cum
0.110
kg
52.800
cum
0.110
day
0.020
day
day
1.710
3.270
day
day
0.250
0.250
682
Remarks
7
BLD-CSTN
Index-code
S No
1
65
BLD-CSTN-6-13
Description
Unit
Quantity
cum
0.224
cum
0.100
kg
9.280
day
day
1.710
3.270
day
day
0.500
1.000
kg
6.000
kg
6.000
Rate
Rs.
5
Amount
Rs.
6
683
Remarks
7
BLD-CSTN
Index-code
S No
Description
Unit
Quantity
1
66
2
Pebble dash exterior plaster on walls upto a height of 10
metres above ground level with a mixture of washed
pebble or crushed stone graded from 6 mm to 12 mm
nominal size dashed over and including fresh cement
plaster in two coats, backing coat 10 mm cement plaster 1
: 3 (1 cement : 3 sand) and finishing coat 10 mm cement
plaster 1 : 3 (1 cement : 3 sand) mixed with 10% finely
grounded hydrated lime by volume of cement including
arrises, chamfers and/or rounded angles not exceeding 80
mm in girth
cum
kg
0.224
9.280
cum
0.100
day
day
1.710
3.270
day
day
0.500
0.610
cum
0.023
day
day
0.300
0.350
cum
0.023
day
day
0.300
0.350
cum
0.023
day
day
0.380
0.430
BLD-CSTN-6-14
Labour for backing coat and finishing coat :Mason llnd class
Mazdoor (unskilled)
Labour for pebble dashing
Mason llnd class
Mazdoor (unskilled)
Add for water charges @ 1 %
Cost for 10 sq.m.
Cost per sq.m
Plain Cement Mortar Bands :
67
BLD-CSTN-6-15
Rate
Rs.
5
Amount
Rs.
6
684
Remarks
7
BLD-CSTN
Index-code
BLD-CSTN-6-16
S No
Description
Unit
Quantity
1
68
cum
0.224
day
day
2.200
2.700
cum
0.224
day
day
2.500
3.000
cum
0.224
day
day
3.000
3.500
cum
0.023
day
day
0.870
0.920
BLD-CSTN-6-17
69
Rate
Rs.
5
Amount
Rs.
6
70
BLD-CSTN-6-18
day
110.000
cum
0.100
B. LABOUR
Mason 1st class
day
0.420
685
Remarks
7
BLD-CSTN
Index-code
S No
Description
Unit
Quantity
3
day
4
0.920
day
day
0.700
2.100
sqm
11.00
kg.
21.60
kg.
33.00
kg.
20.00
cum
0.12
cum
0.12
day
3.10
day
1.10
day
0.86
sqm
10.50
kg.
21.60
kg.
9.60
cum
0.12
cum
0.02
cum
0.14
day
0.960
day
2.240
day
3.30
Rate
Rs.
5
Amount
Rs.
6
FLOORING
BLD-CSTN-7
71
BLD-CSTN-7-1
72
BLD-CSTN-7-2
686
Remarks
7
BLD-CSTN
Index-code
S No
1
73
BLD-CSTN-7-3
Description
Unit
Quantity
sqm
10.10
kg.
48.00
kg.
33.00
kg.
cum
5.00
0.20
cum
0.20
day
1.00
day
2.10
day
3.00
day
5.00
sqm
10.05
kg.
28.80
kg.
33.00
kg.
6.00
BLD-CSTN-7-4
Amount
Rs.
6
74
Rate
Rs.
5
Unit = 10 sqm
A. MATERIALS:
Chequerred terrazzo tiles of 22 mm thick (medium
shade)
kg.
cum
0.12
cum
0.12
day
0.960
day
2.240
day
3.30
687
Remarks
7
BLD-CSTN
Index-code
S No
1
75
BLD-CSTN-7-5
76
BLD-CSTN-7-6
Description
Unit
Quantity
sqm
10.10
kg.
21.60
kg.
33.00
kg.
6.000
Rate
Rs.
5
Amount
Rs.
6
cum
0.12
cum
0.020
cum
0.140
day
0.96
day
2.24
day
3.30
1.00%
sqm
10.10
kg.
21.60
kg.
33.00
kg.
2.00
cum
0.12
cum
0.12
day
0.96
day
2.24
day
3.30
1.00%
688
Remarks
7
BLD-CSTN
Index-code
S No
1
77
BLD-CSTN-7-7
Description
Unit
Quantity
sqm
10.10
kg.
36.00
kg.
33.00
kg.
6.00
78
BLD-CSTN-7-8
Rate
Rs.
5
Amount
Rs.
6
kg.
cum
0.20
cum
0.20
day
3.00
day
1.00
day
8.00
1.00%
Unit = 10 sqm
A. MATERIALS:
Marble tiles polished 8 mm thick
Cement for CM (1:8) for base coat
Cement for slurry
White cement for jointing & pointing
Sand for CM (1:8)
Seigniorage charges of sand
B. LABOUR (including for polishing & rubbing)
Mason 1st class
Mazdoor (unskiled)
Add water charges 1%
Grand Total
sqm
10.10
kg.
36.00
kg.
33.00
kg.
5.00
cum
0.20
cum
0.20
day
4.00
day
8.00
1.00%
689
Remarks
7
BLD-CSTN
Index-code
S No
1
79
BLD-CSTN-7-9
80
BLD-CSTN-7-10
Description
Unit
Quantity
sqm
10.10
kg.
48.00
cum
0.20
cum
0.20
day
4.00
day
Rate
Rs.
5
Amount
Rs.
6
8.00
1.00%
Unit = 10 sqm
A. MATERIALS:
Decorated white back ground glazed tiles
sqm
kg.
10.10
28.80
kg.
33.00
kg.
6.00
cum
0.12
cum
0.12
day
0.96
day
2.24
day
3.30
1.00%
690
Remarks
7
BLD-CSTN
Index-code
S No
1
81
BLD-CSTN-7-11
Description
Unit
Quantity
1000
Nos
kg.
0.255
21.600
kg.
6.000
10sqm
1.000
82
BLD-CSTN-7-12
cum
0.040
cum
0.120
cum
0.120
day
0.960
day
2.240
A. MATERIALS:
Plain cement Tiles 20 x 20 cms
day
Amount
Rs.
6
4.30
1.00%
1000
Nos
0.255
kg.
21.600
kg.
6.000
10sqm
1.000
cum
0.040
cum
0.120
cum
0.120
day
0.960
day
2.240
Rate
Rs.
5
day
3.30
1.00%
691
Remarks
7
BLD-CSTN
Index-code
S No
Description
Unit
Quantity
Rate
Rs.
5
Amount
Rs.
6
BLD-CSTN-7-13
84
BLD-CSTN-7-14
85
86
BLD-CSTN-7-16
0.17
kg
120.00
cum
0.085
cum
0.085
day
1.25
day
0.06
day
3.00
1.00%
Unit = 10 sqm
A. MATERIALS:
Cement Concrete 1:6:10 using concrete mixer
Stone Chippings 3.34 mm - 10 mm
Cement
B. LABOUR
BLD-CSTN-7-15
cum
cum
1.000
cum
0.250
kg
120.000
day
Mason 1st class
nd
day
Mason 2 class
day
Mazdoor (unskiled)
Add water charges 1%
Grand Total
Flooring with Cement Concrete 1:6:10, using
40mm metal, 100mm thick and plastered over
with 12 mm thick in CM(1:3)
Unit = 10 sqm
A. MATERIALS:
cum
Cement Concrete 1:6:10 using concrete mixer
10 sqm
Plastering with CM (1:3), 12 mm thick
Grand Total
Flooring with Cement Concrete 1:6:10, using
40mm metal, 100mm thick and plastered over
with 12 mm thick in CM(1:3) using Red oxid,
with polished surface
Unit = 10 sqm
A. MATERIALS:
cum
Cement Concrete 1:6:10 using concrete mixer
10 sqm
Plastering with CM (1:3), 12 mm thick
kg
Red oxid
0.150
0.350
5.40
1.00%
1.00
1.00
1.00
1.00
10.00
692
Remarks
7
BLD-CSTN
Index-code
S No
1
87
BLD-CSTN-7-17
Description
Unit
Quantity
Nos
1.10
kg
17.000
B. LABOUR
Masons for polishing
Grand Total
6 mm thick terrazzo flooring in situ with white,
black, chocolate, gray, yellow or green superior
marble chips, over 20 mm thick base coat of CM
(1:3) laid over CC bed already laid or RCC roof
slab, including cost of all materials like cement
marble powder, marble chips, sand & water etc.,
complete including polishing to get high smooth
finishing, seigniorage charges, etc., complete
for finished item of work, but excluding the cost
of conveyance of all materials
Unit = 10 sqm
A. MATERIALS:
Marble Powder
Marble Chips
Cement for top layer
Cement for base coat in CM (1:3)
Sand for base coat
Seigniorage charges of sand
B. MACHINERY
Polishing Charges
C. LABOUR
88
BLD-CSTN-7-18
cum
0.060
kg.
50.000
kg.
96.000
cum
0.200
cum
0.200
sqm
10.000
day
0.960
day
2.240
day
3.30
sqm
10.00
cum
0.12
kgs
57.60
kgs
33.00
kgs
6.00
cum
0.12
day
0.77
day
0.80
Rate
Rs.
5
Amount
Rs.
6
693
Remarks
7
BLD-CSTN
Index-code
S No
1
89
BLD-CSTN-7-19
Description
Unit
Quantity
sqm
10.10
BLD-CSTN-7-20
Amount
Rs.
6
90
Rate
Rs.
5
cum
0.12
kg
57.60
kg
33.00
kg
5.00
RM
66.67
RM
67.67
cum
0.12
day
2.10
day
4.90
day
4.00
day
4.00
sqm
cum
kgs
kgs
kgs
cum
10.10
0.12
34.56
33.00
2.00
0.12
day
day
day
0.96
2.24
3.30
1.00%
Mason 2 class
Mazdoor (unskilled)
Add water charges 1%
Grand Total
694
Remarks
7
BLD-CSTN
Index-code
S No
1
91
BLD-CSTN-7-21
Description
Unit
Quantity
sqm
10.10
cum
kgs
kgs
kgs
cum
0.12
57.60
33.00
5.00
0.12
day
day
2.10
0.80
4.90
1.00%
sqm
10.10
cum
kgs
kgs
cum
0.12
57.60
33.00
0.12
day
day
day
0.96
2.24
3.10
1.00%
Rate
Rs.
5
Amount
Rs.
6
92
BLD-CSTN-7-22
materials
Unit = 10 sqm
A. MATERIALS:
25 mm thick polished Cuddapah stone
Sand for cm 1:3 base coat
Cement for cm 1:3 base coat
Cement for slurry
Seigniorage charges of sand
B. LABOUR
Mason Ist class
Mason 2nd class
Mazdoor (unskiled)
Add water charges 1%
Grand Total
695
Remarks
7
BLD-CSTN
Index-code
S No
1
93
BLD-CSTN-7-23
Description
Unit
Quantity
Rate
Rs.
5
Amount
Rs.
6
materials
Unit = 10 sqm
A. MATERIALS:
sqm
25 mm thick polished Shahabad stone (White)
cum
Sand for cm 1:3 base coat
kgs
Cement for cm 1:3 base coat
kgs
Cement for slurry
cum
Seigniorage charges of sand
B. LABOUR
day
Mason Ist class
Mason 2nd class
day
Mazdoor (unskiled)
Add water charges 1%
Grand Total
Note : When Mortar mix is changed proportionate quantity of
cement has to be substituted for all Skirting Items.
94
BLD-CSTN-7-24
10.10
0.12
57.60
33.00
0.12
0.96
2.24
3.10
1.00%
0.44
3.00
1.95
4.55
5.40
696
Remarks
7
BLD-CSTN
Index-code
S No
1
95
BLD-CSTN-7-25
Unit
Quantity
cum
1.53
day
1.10
day
0.50
kgs
103.09
nos
47.91
Rate
Rs.
5
Amount
Rs.
6
BLD-CSTN-8
96
BLD-CSTN-8-1
Description
nos
nos
43.90
nos
91.82
nos
91.82
litre
0.14
litre
0.20
day
0.84
day
0.91
day
0.06
day
0.06
day
0.14
day
0.14
LS
LS
Grand Total
Rate per 10 sqm = Grand Total/10
697
Remarks
7
BLD-CSTN
Index-code
S No
1
97
BLD-CSTN-8-2
98
BLD-CSTN-8-3
Description
Unit
Quantity
Rate
Rs.
5
Amount
Rs.
6
kgs
126.07
nos
47.91
nos
43.90
nos
91.82
nos
91.82
litre
0.14
litre
0.20
day
0.84
day
0.91
day
0.06
day
0.06
day
0.14
day
0.14
kgs
154.80
nos
47.91
nos
43.90
nos
91.82
nos
91.82
litre
0.14
litre
0.20
day
0.84
day
0.91
day
0.06
day
0.06
698
Remarks
7
BLD-CSTN
Index-code
BLD-CSTN-8-4
BLD-CSTN-8-5
S No
Description
Unit
Quantity
Amount
Rs.
6
0.14
0.14
0.15
22.03
22.03
22.03
0.43
0.54
Unit = 10 sqm
A. MATERIALS:
Pan Tiles 230 x (140 + 130)/2, 12 mm thick
1000 No
1560
1000 No
470
10RM
Teak Reepers 50 x 12 mm
kgs
Wire Nails 40 mm long
cum
Lime
cum
Lime Mortar
B. LABOUR
day
Carpenter
day
Bricklayers
day
Man mazdoor
day
Woman mazdoor
LS
Sundries including tarring reepers, extra labour / for
pointing the underside of flat tiles and white
washing the same.
Grand Total
Sub Analysis :
Lime Moratar 1:2
cum
lime
cum
Sand
cum
Grinding Lime Mortar
Total
Rate
Rs.
5
75.000
0.500
0.008
0.300
0.800
2.200
1.100
5.400
LS
0.500
1.000
1.000
699
Remarks
7
BLD-CSTN
Index-code
BLD-CSTN-8-6
S No
Description
Unit
Quantity
1000 No
1560
10RM
kgs
cum
107.000
0.700
0.120
day
day
day
day
1.100
1.400
1.100
3.200
1000 No
1560
RM
25
100 No
150
Bamboo mats
10 sqm
10.500
cum
0.120
day
day
day
day
1.100
1.400
1.100
3.200
1000 No
160
1000 No
470
1
2
101 Best Tiled Roofing with Pan tiles and Lime
197 mortar Borders including Teak Reapers at 100
mm. centres
Unit = 10 sqm
A. MATERIALS:
Pan Tiles 230 x (140 + 130)/2, 12 mm thick
Teak Reepers 50 x 12 mm
Wire Nails 40 mm long
Lime Moratar
B. LABOUR
Carpenter
Bricklayers
Man mazdoor
Woman mazdoor
Grand Total
BLD-CSTN-8-7
BLD-CSTN-8-8
Rate
Rs.
5
Amount
Rs.
6
10RM
Teak Reepers 50 x 12 mm
kgs
Wire Nails 40 mm long
cum
Lime
cum
Lime Moratar
B. LABOUR
day
Carpenter
day
Bricklayers
day
Man mazdoor
day
Woman mazdoor
LS
Sundries including tarring reepers iron wind ties 30
x 3 mm, G.I. Screw, washers etc., and extra labour
for pointing the underside of flat tiles and white
washing the same.
75.000
0.500
0.008
0.380
0.800
1.600
1.100
4.300
LS
Grand Total
700
Remarks
7
BLD-CSTN
Index-code
BLD-CSTN-8-9
S No
Description
1
2
104 Best Tiled Roofing with
200 including Teak Reepers
Mangalore
Quantity
1000 No
160
10RM
Teak Reepers 50 x 12 mm
kgs
Wire Nails 50 mm long
cum
Lime Moratar
B. LABOUR
day
Carpenter
day
Bricklayers
day
Man mazdoor
day
Woman mazdoor
Grand Total
105 Best Tiled Roofing with Mangalore tiles over
201 Ceiling Tiles with Air Spaces and including Teak
Reepers
Unit = 10 sqm
A. MATERIALS:
36.000
0.500
0.090
with 10 sqm
10.000
Rate
Rs.
5
Amount
Rs.
6
tiles
Unit = 10 sqm
A. MATERIALS:
Mangalore tiles (vide Stadard Specification)
BLD-CSTN-8-10
Unit
B. LABOUR
Bricklayers
Woman mazdoor
Grand Total
0.500
0.500
1.100
2.200
100 No
156
day
day
0.500
1.100
cum
cum
cum
LS
0.670
1.000
1.000
cum
cum
cum
0.180
0.080
0.023
day
day
LS
3.200
6.500
LS
Sub Analysis :
Lime Mortar (1: 1.5) :
Unit = 1 cum
BLD-CSTN-8-11
Lime
Fine Sand
Grinding Mortar (Spl Grinding)
Sundries
Total
106 Plastering with Lime Mortar 3 Coats, 25 mm
thick (Sebara Rendering)
Unit = 10 sqm
Lime Mortar (1:2)
Lime Mortar (1:1.5)
Lime
LABOUR
Bricklayers
Mazdoor (unskilled)
Sundries
Total
701
Remarks
7
BLD-CSTN
Index-code
BLD-CSTN-8-12
S No
Description
1
2
107 Terrace Roofing with Brick on edge 75 mm.
204 Concrete 2 Courses of Flat Tiles at Top and
Unit
Quantity
2000
100 No
900
cum
Broken brick 20 mm cube
cum
Lime
cum
Lime Moratar
Pointing with cement mortar 1:3 (for rate - vide 10 sqm
relevant schedule item)
cum
Cement Mortar 1:3
B. LABOUR
Bricklayers
Mazdoor (unskilled)
Grand Total
day
day
Rate
Rs.
5
Amount
Rs.
6
0.980
0.380
0.210
1.000
0.240
4.300
6.500
Note : The quantity proposed for broken brick allows for the
brick powder formed, replacing sand for concrete layers.
BLD-CSTN-8-13
10.000
cum
Cement Mortar 1:3
Pointing with cement mortar 1:3 (for rate - vide 10 sqm
relevant schedule item)
B. LABOUR
day
Bricklayers
day
Woman mazdoor
LS
Sundries including crude oil
Grand Total
Sub Analysis :
RCC (M 20) using 20 mm HG graded metal using
Concrete mixturefor Roofing 125 mm thick
0.260
1.000
BLD-CSTN-8-14
900
2.200
2.200
cum
1.250
10 sqm
1.000
Form Work
Total
109 Reinforced cement Concrete Roofing 140 mm
206 thick with CC (M 20) using 20 mm graded metal
and 2 courses of Flat Tiles at Top including
Pointing with Cement Mortar (1:3)
Unit = 10 sqm
A. MATERIALS:
Rate of "Reinforced cement Concrete Roofing 125 mm 10 sqm
thick and 2 courses of Flat Tiles at Top including pointing
with Cement Mortar (1:3)"
Add :
For extra thickness of roofing slab
Grand Total
cum
1.000
0.150
702
Remarks
7
BLD-CSTN
Index-code
BLD-CSTN-8-15
S No
Description
1
2
110 Reinforced cement Concrete Roofing 150 mm
207 thick with CC (M 20) using 20 mm graded metal
Unit
Quantity
Add :
For extra thickness of roofing slab
Grand Total
BLD-CSTN-8-17
Amount
Rs.
6
BLD-CSTN-8-16
Rate
Rs.
5
cum
1.000
0.250
1.000
0.250
1.000
1.000
10 sqm
1.000
kgs
1.500
703
Remarks
7
BLD-CSTN
Index-code
BLD-CSTN-8-18
S No
Description
1
2
113 Complete Surface Repairs to Leaky Terrace
208 Roofs with Flat Tiles
Unit = 10 sqm
A. MATERIALS:
Flat Tiles 150 x 150 x 15 mm
Unit
Quantity
1000 No
450
cum
Cement Mortar 1:3
Pointing with cement mortar 1:3 (for rate - vide 10 sqm
relevant schedule item)
BLD-CSTN-8-19
B. LABOUR
day
Bricklayers
day
Man Mazdoor
Clean removal of lime plaster from terraced roofs 10 sqm
and raking out joints 12 mm deep (for rate - vide
relevant schedule item)
Sub Analysis :
Day
Mazdoor (unskilled)
Day
Mate
LS
Sundries including crude oil
Grand Total
114 Best Sloping Bengal Terrace with 3 courses of
209 Flat Tiles at Top including Teak Wood Reepers
Rate
Rs.
5
Amount
Rs.
6
0.110
1.000
1.100
1.100
1.000
Unit = 10 sqm
A. MATERIALS:
1000 No
1350
cum
cum
10 RM
0.008
0.150
75.000
kgs
Wire Nails 40 mm long
Plastering with lime mortar 3 coats (for rate - vide 10 sqm
relevant schedule item)
0.500
1.000
B. LABOUR
Carpenter
Bricklayers
Woman mazdoor
Sundries including tarring reepers
Grand Total
day
day
day
LS
0.800
2.200
2.200
704
Remarks
7
BLD-CSTN
Index-code
BLD-CSTN-8-20
S No
1
2
115 Removing Old Tiles and Retiling with New Pan
212 Tiles over Old Teak Reepers including New
Unit
Quantity
BLD-CSTN-8-21 116
213
117
BLD-CSTN-8-22 214
BLD-CSTN-8-23
Description
cum
Lime Moratar
B. LABOUR
day
Bricklayers
day
Man Mazdoor
day
Woman mazdoor
LS
Sundries
Grand Total
Shifting Pan Tiles (Labour Only)
Unit = 10 sqm
day
Bricklayers
day
Man Mazdoor
Grand Total
Shifting Pan Tilesand forming new White
Washed Lime Mortar Boarders, 230 x 50 mm at 2
Metres Intervals
Unit = 10 sqm
10 sqm
Rate of "Shifting Pan Tiles"
LS
Add : Lime Mortar Borders and White Washing
Grand Total
118 12 mm. Teak Wood Plank Ceiling Tongued and
222 Grooved Planking
Unit = 10 sqm
A. MATERIALS:
cum
Teak Wood Planks 150 x 12 mm
100
No
Screws 40mm long
B. LABOUR
Carpenter
Man Mazdoor
Sundries
Grand Total
Note : Deduct 4.3 Nos Carpenters if plank rate is
for tongued and grooved ready planned.
day
day
LS
Rate
Rs.
5
Amount
Rs.
6
1560
0.120
1.400
1.100
4.300
1.100
0.800
1.000
0.132
300
6.500
5.400
BLD-CSTN-8-24 223
mm Teak Wood Battens
Unit = 10 sqm
Rate for "12 mm. Teak Wood Plank Ceiling 10 sqm
Tongued and Grooved Planking"
10 RM
Teak Wood Battens 40 x 12 mm
Brass screws 25 mm long
Deduct :
Carpenter
Sundries
Grand Total
10.000
66.000
100 No
240
day
LS
1.100
705
Remarks
7
BLD-CSTN
Index-code
S No
Description
1
2
120 Providing impervious coat to exposed RCC roof
BLD-CSTN-8-25
BLD-CSTN-8-26
BLD-CSTN-8-27
BLD-CSTN-8-28
B. LABOUR
Carpenter Ist class
Man mazdoor
Grand Total
Unit
Quantity
cum
0.210
kg
2.000
day
0.660
day
1.540
day
3.70
sqm
11.00
day
2.50
day
2.00
sqm
11.00
day
2.50
day
2.00
sqm
11.00
day
2.50
day
2.00
Rate
Rs.
5
Amount
Rs.
6
706
Remarks
7
BLD-CSTN
Index-code
S No
Description
1
2
124 Providing & fixing plain AC sheet ceiling of
BLD-CSTN-8-29
Unit
Quantity
sqm
11.00
day
2.50
day
2.00
cum
0.05
Rate
Rs.
5
Amount
Rs.
6
BLD-CSTN-8-30
BLD-CSTN-8-31
kg
0.75
sqm
10.20
kg
219.76
day
2.60
day
1.60
day
2.62
day
1.62
day
377.00
sqm
1.03
UNIT -1 sqm
A) Material requirement as per India Gypsum
12.5 mm Gypboard
1219 mm x 1829 mm size Boards
707
Remarks
7
BLD-CSTN
Index-code
S No
1
Description
Unit
Quantity
RM
Nos
0.64
1.84
RM
2.30
RM
0.84
RM
Nos
Nos
Nos
Kgs
RM
Lits
0.40
0.64
0.64
18.00
0.55
1.46
0.15
day
day
day
day
day
day
day
0.40
0.40
0.08
0.08
0.04
0.08
0.24
Hrs
Hrs
0.32
0.64
1%
sqm
1.00
RM
0.40
RM
1.60
RM
1.60
RM
Nos
Nos
Nos
1.28
1.28
1.28
5.36
Ceiling Angle
25 mm x 10 mm x 0.55 mm
Connecting Clips
Ceiling Section
51.5 mm x 26 mm x 10.5 mm x 0.55 mm thick
Intermediate Channel
45 mmx 15 mm x 15 mm x 0.9 mm
Perimeter Channel
20 mm x 27 mm x 30 mm(web) of 0.55 mm thick
Rawl Plug
Soffit Cleats
Drywall Screws - 25 mm
Jointing Compound
Jointing Paper Tape
Drywall Top Coat
B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
1st Class Painter
2nd Class Painter
Power Saw Cutter - Hand Operated - Operator
Power Drill - Hand Operated - Operator
Unskilled Mazdoor
C) Machinery
Power Saw Cutter - Hand Operated - Hire charges
Power Drill - Hand Operated - Hire Charges
Scaffolding charges
BASIC COST per 1 sqm
Gyp Board Fine Line Grid false ceiling
BLD-CSTN-8-32
Rate
Rs.
5
Amount
Rs.
6
127 Supplying and fixing Gyp Board Fine Line Grid false ceiling
(GS-FLC-4.6 as per India Gypsum) in size 600 mm x 600
mm using 12.5 mm thick/ 9.5 mm thick Gyp Board sheet
tiles of size 595 mm x 595 mm or 595 mm x 1195 mm
conforming to IS 2095 - 1982 fixing to Gyp steel precoated
GI wall angle of size 25 mm x 25 mm x of 0.70 mm thick
along the perimeter of ceiling screw fixed to brick work/
partition at 610 mm c/c and suspending the frame work
using precoated GI Tee section (24 mm x 38 mm x 0.7
mm) from soffit at 1220 mm c/c fixed with GI Soffit Cleat,
rawl plugs and steel expansion fasteners & connecting clip
to the GI T section with 4 mm dia GI Rod with galvanised
spring steel level clip of PVC unversal holding clips system
at 1200 mm c/c and fixing the 12.5 mm / 9.5 mm
Gypboard Sheet tiles of size 595 mm x 595 mm or 595 mm
x 1195 mm and finishing two coats of drywall topcoat
complete for finished item of work as per Idia Gypsum Ltd
specification.
UNIT -1 sqm
A) Material requirement as per India Gypsum
12.5 mm / 9.5 mm - Gypboard Tiles
Either - 595 mm x 595 mm Or - 595 mm x 1195 mm GI Angle - Precoated
25 mm x 25 mm x 0.7 mm
GI - Precoated - T Section - 3600 mm long
24 mm x 38 mm x 0.7 mm thick
GI - Precoated - T Section - 600 mm long
24 mm x 38 mm x 0.7 mm thick
GI Rod - 4 mm Dia
Connecting Rod
Rawl Plug
Soffit Cleats
Unversal Holding Clips
708
Remarks
7
BLD-CSTN
Index-code
S No
Description
Unit
Quantity
3
Lits
4
0.15
day
day
day
day
day
day
day
0.40
0.40
0.08
0.08
0.04
0.04
0.24
Hrs
Hrs
0.32
0.32
1%
sqm
1.00
RM
0.40
RM
1.60
RM
1.60
RM
Nos
1.28
1.28
day
day
day
day
day
day
day
0.40
0.40
0.08
0.08
0.04
0.04
0.24
Hrs
Hrs
0.32
0.32
1%
BLD-CSTN-8-33
Rate
Rs.
5
Amount
Rs.
6
UNIT 1 sqm
A) Material requirement
15 mm - Armstrong Mineral Fiber sheet 600 x 600
Hotdipped GI Angle - Precoated - Grid
19 mm x 19 mm
Polyster painted GI - T Section - 1200 mm
(1) 24 x 32 mm and (2) 24 x 25 mm (sub-cross Tee)
Polyster painted GI - T Section - 300 mm
24 mm x 27 mm
GI Rod - prestraightened - 2.0 mm dia
Connecting Rod
6 mm Nylon Rawl Plug
B) LABOUR CHARGES
PER UNIT 1 sqm
1st Class Carpenter
2nd Class Carpenter
1st Class Painter
2nd Class Painter
Power Saw Cutter - Hand Operated - Operator
Power Drill - Hand Operated - Operator
Unskilled Mazdoor
C) Machinery
Power Saw Cutter - Hand Operated - Hire charges
Power Drill - Hand Operated - Hire Charges
Scaffolding charges
BASIC COST per 1 sqm
709
Remarks
7
BLD-CSTN
Index-code
S No
1
Description
Unit
Quantity
sqm
1.00
RM
0.40
RM
3.20
Nos
Nos
1.28
1.28
day
day
day
day
day
day
day
0.36
0.36
0.00
0.00
0.02
0.04
0.20
Hrs
Hrs
0.16
0.32
1%
cum
0.005
L.S
day
day
LS
0.11
0.22
Rate
Rs.
5
Amount
Rs.
6
BLD-CSTN-8-34
UNIT 1 sqm
A) Material requirement
15 mm/ 19 mm Thermocole sheet 600 x 600
Alumninium Angle
24 mm x 24 mm
Anodised Aluminium T Section
(1) 24 x 24.5 x 2.4 mm mm
GI Rod - prestraightened - 2.0 mm dia
Connecting Rod
Rawl Plugs
B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
1st Class Painter
2nd Class Painter
Power Saw Cutter - Hand Operated - Operator
Power Drill - Hand Operated - Operator
Unskilled Mazdoor
C) Machinery
Power Saw Cutter - Hand Operated - Hire charges
Power Drill - Hand Operated - Hire Charges
Scaffolding charges
BASIC COST per 1 sqm
BLD-CSTN-9
BLD-CSTN-9-1
710
Remarks
7
BLD-CSTN
Index-code
S No
Description
1
2
131 White washing two coats with lime of approved
BLD-CSTN-9-2
BLD-CSTN-9-3
Unit
Quantity
cum
0.007
L.S
day
day
LS
0.160
0.32
cum
0.009
L.S
day
day
day
day
day
LS
0.220
0.43
Rate
Rs.
5
Amount
Rs.
6
133 White
BLD-CSTN-9-4
1.20
day
day
0.11
0.22
0.50%
711
Remarks
7
BLD-CSTN
Index-code
S No
Description
Unit
Quantity
cum / kg
2.00
1
134 White
BLD-CSTN-9-5
L.S
BLD-CSTN-9-7
Amount
Rs.
6
BLD-CSTN-9-6
Rate
Rs.
5
B. LABOUR
day
Brick Layers / Painter
day
Mazdoor (unskilled)
Sundries including brushes, ladders, etc.,
Total cost for 10 sqm
135 White washing three coats with whiting of
approved quality to give an even shade after
thoroughly brushing the surface to remove all
dirt and remains of loose powdered materials
including cost of all materials, labour charges
and incidental such as scaffolding, lift charges
etc., complete for finished item of work, but
excluding conveyance charges of materials
Unit: 10 sqm
A. MATERIALS :
cum / kg
Whiting / White Cement
Gum, conjee water, or prickly pear juice including
necessary fire wood
B. LABOUR
day
Brick Layers / Painter
day
Mazdoor (unskilled)
Total cost for 10 sqm
136 Colour Washing, One Coat
254 Unit: 10 sqm
10 sqm
Rate for "White Washing" one coat
0.210
0.320
1.00%
2.800
0.300
0.430
1.000
BLD-CSTN-9-8
BLD-CSTN-9-9
10 sqm
1.000
kg
1.340
day
day
0.500
1.300
1.000%
712
Remarks
7
BLD-CSTN
Index-code
BLD-CSTN-9-10
S No
Description
1
2
139 Distempering, 2 Coats with Oil Bound Distemper
257
Unit: 10 sqm
A. MATERIALS :
Distemper
B. LABOUR
Painter
Sundries including brushes, ladders, etc.,
Total cost for 10 sqm
PAINTING & VARNISHING
BLD-CSTN-10
Unit
Quantity
kg
1.700
day
1.200
1.000%
Lts
Nos
Nos
Lts
Nos
Nos
0.50
0.08
0.19
1.70
0.36
0.84
kg
1.00
day
0.700
0.500%
kg
2.000
day
day
0.300
1.500
1.000%
kg
3.500
day
day
0.500
1.500
1.000%
Rate
Rs.
5
Amount
Rs.
6
BLD-CSTN-10-1
PRIMARY COAT:
BLD-CSTN-10-2
Cost of Primer
Painter I st class
Pianter Iind class
Cost of washable Oil Bound Distemper
1st class painter
II class painter
Total cost
141 Painting, Priming Coat on New
270 Surface
142
BLD-CSTN-10-3 284
143
BLD-CSTN-10-4 285
Plastered
Unit: 10 sqm
A. MATERIALS :
Cement Primer
B. LABOUR
Painter
Sundries including brushes, soaps, putty etc.,
Total cost for 10 sqm
Painting Walls with Snowcem or other equal
and approved Water Proof Cement Paint over
Priming Coat, One Coat (All Colours)
Unit: 10 sqm
A. MATERIALS :
Cement Paint at 5 sqm., per kg
B. LABOUR
Painter
Mazdoor (unskilled)
Sundries including brushes, etc.,
Total cost for 10 sqm
Painting Walls with Snowcem or other equal
and approved Water Proof Cement Paint over
Priming Coat, 2 Coats (All Colours)
Unit: 10 sqm
A. MATERIALS :
Cement Paint at 3 sqm., per kg
B. LABOUR
Painter
Mazdoor (unskilled)
Sundries including brushes, etc.,
Total cost for 10 sqm
713
Remarks
7
BLD-CSTN
Index-code
S No
Description
1
2
144 Painting to new walls with 2 coats of water proof
Unit
Quantity
kg
day
day
kg
1.00
0.21
0.49
3.50
day
day
day
0.15
0.35
1.50
0.700
day
0.700
1.000%
0.70
day
0.70
L
L
0.800
0.600
day
day
0.700
0.700
Rate
Rs.
5
Amount
Rs.
6
BLD-CSTN-10-5
BLD-CSTN-10-6 268
Unit: 10 sqm
A. MATERIALS :
Wood Primer
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
146 Painting, Priming Coat on New Iron Work
BLD-CSTN-10-7 269
Unit: 10 sqm
A. MATERIALS :
Red Oxide Primer
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
A. MATERIALS :
Varnish
Linseed Oil - boiled
B. LABOUR
Painter
Man Mazdoor
Sundries including brushes,fuel, size etc.,
Total cost for 10 sqm
714
Remarks
7
BLD-CSTN
Index-code
BLD-CSTN-10-9
S No
Description
1
2
148 Varnishing to Wood Work, Two Coats
282
Unit: 10 sqm
A. MATERIALS :
Varnish
Linseed Oil - boiled
B. LABOUR
Painter
Man Mazdoor
Sundries including brushes,fuel, size etc.,
Total cost for 10 sqm
149 Painting with Ready mixed oil paint (all colours)
Unit
Quantity
L
L
1.200
1.100
day
day
1.100
1.100
kg
1.600
day
LS
0.700
kg
2.800
day
LS
1.200
kg
1.500
day
LS
0.700
kg
2.4.
day
LS
1.200
kg
1.200
day
LS
0.700
Rate
Rs.
5
Amount
Rs.
6
BLD-CSTN-10-10 256
to
i. One Coat - New Wood Work :
265
ii
iii
iv
Unit: 10 sqm
A. MATERIALS :
Ready mixed paint
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
Two Coats - New Wood Work :
Unit: 10 sqm
A. MATERIALS :
Ready mixed paint
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
One Coat - Old Wood Work & New Iron Work :
Unit: 10 sqm
A. MATERIALS :
Ready mixed paint
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
Two Coats - Old Wood Work & New Iron Work:
Unit: 10 sqm
A. MATERIALS :
Ready mixed paint
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
One Coat - Old Iron Work :
Unit: 10 sqm
A. MATERIALS :
Ready mixed paint
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
715
Remarks
7
BLD-CSTN
Index-code
S No
Description
Unit
Quantity
1
vi
kg
2.100
day
LS
1.100
kg
3.400
day
LS
1.500
kg
3.900
day
LS
1.600
0.500
day
0.700
0.400
day
0.700
0.900
day
1.200
Rate
Rs.
5
Amount
Rs.
6
ii
iii
716
Remarks
7
BLD-CSTN
Index-code
S No
1
iv
vi
vii
Description
Unit
Quantity
0.800
day
1.200
0.800
day
1.100
0.700
day
1.100
1.200
day
1.600
1.100
day
1.500
0.700
day
0.700
A. MATERIALS :
Plastic Emulsion paint (at 20 sqm / litre as per
British Paints (I) Ltd.
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
viii Plastic Emulsion paints - Three Coats for Old
Iron Work :
A. MATERIALS :
Plastic Emulsion paint (at 20 sqm / litre as per
British Paints (I) Ltd.
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
151 Painting with Synthetic Enamel paints - One
BLD-CSTN-10-12 i Coat - for New Wood Work, Old Wood Work &
New Iron Work
A. MATERIALS :
Synthetic Enamel paint (at 20 sqm / litre as per
British Paints (I) Ltd.
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
Rate
Rs.
5
Amount
Rs.
6
717
Remarks
7
BLD-CSTN
Index-code
S No
1
ii
iii
iv
Description
Unit
Quantity
0.500
day
0.700
1.200
day
1.200
1.100
day
1.200
1.100
day
1.100
0.900
day
1.100
1.700
day
1.600
Rate
Rs.
5
Amount
Rs.
6
vii
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
Painting with Synthetic Enamel paints - Three
Coats - for New Wood Work
A. MATERIALS :
Synthetic Enamel paint (at 20 sqm / litre as per
British Paints (I) Ltd.
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
718
Remarks
7
BLD-CSTN
Index-code
S No
1
viii
Description
Unit
Quantity
1.600
day
1.500
kg
0.500
day
day
LS
0.800
0.800
0.650
day
day
LS
0.800
0.800
kg
L
0.228
1.630
day
LS
3.200
cum
1.000
day
day
17.700
8.800
LS
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
152 Polishing on wood work with readymade wax
BLD-CSTN-10-13
polish of approved brand and manufacture
New Work :
A. MATERIALS :
Readymade wax polish
B. LABOUR
Painter
Healper
Sundries including brushes, soap, cloth etc.,
Total cost for 10 sqm
BLD-CSTN-10-14
Rate
Rs.
5
Amount
Rs.
6
coat)
New Work :
A. MATERIALS :
Melamine polish
B. LABOUR
Painter
Healper
Sundries for Spraying Machine etc.,
Total cost for 10 sqm
154 French Spirit polishing Two or more coats on
BLD-CSTN-10-15
new works including a coat of wood filler.
A. MATERIALS :
Shellac
Spirit
B. LABOUR
Painter
Sundries such as pigment, terpentaine, sand paper, putty,
wood filler, white woolen cloth, linseed oil, cotton etc.,
BLD-CSTN-11
BLD-CSTN-11-1
WOOD
WORK,
ALUMINUM
WINDOWS, VENTILATORS Etc.,
DOORS,
719
Remarks
7
BLD-CSTN
Index-code
S No
Description
1
2
156 Best Teak Wood wrought and put up over 2
BLD-CSTN-11-2
BLD-CSTN-11-3
BLD-CSTN-11-4
BLD-CSTN-11-5
Unit
Quantity
cum
1.000
day
day
17.700
8.800
LS
cum
1.000
day
17.700
day
8.800
Rate
Rs.
5
Amount
Rs.
6
Unit = 1 cum
Materials :
Teak wood large scantlings over 2 m and below 3 m
in length
Labour :
Carpenter
Man Mazdoor
Sundries including nails, screws etc.,
Cost per cum
158 Best Teak Wood wrought and put up for trusses
including straps and all iron work (Schedule
Item No 289)
Unit = 1 cum
Materials :
Teak wood large scantlings
Iron Work (average)
Labour :
Carpenter
Man Mazdoor
Sundries including nails, screws etc.,
Cost per cum
159 Fully Panelled doors - External or Internal Moulded panels (Schedule Item No 290)
A Single Shutter
i
800 x 2000 mm
*Teak wood
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of holdfasts and all wind
appliances (Vide relevant standard specification)
ii
LS
cum
1.000
kg
112.000
day
26.500
day
8.800
LS
cum
0.083
sqm
1.600
LS
cum
0.088
sqm
1.800
720
Remarks
7
BLD-CSTN
Index-code
S No
1
iii
iv
Description
Unit
Quantity
cum
0.109
sqm
2.200
1100 x 2000 mm
*Teak wood
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of holdfasts and all wind
appliances (Vide relevant standard specification)
Total for each door
1200 x 2100 mm
*Teak wood
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of holdfasts and all wind
appliances (Vide relevant standard specification)
Total for each door
900 x 2100 mm
*Teak wood
Labour, wrought and putup in position frame &
shutters
cum
0.123
sqm
2.520
cum
0.094
sqm
1.890
LS
cum
0.159
sqm
3.600
Amount
Rs.
6
LS
Rate
Rs.
5
LS
cum
0.096
sqm
1.800
cum
0.104
sqm
2.000
cum
0.134
sqm
2.860
iii
721
Remarks
7
BLD-CSTN
Index-code
S No
1
iv
Description
Unit
Quantity
cum
0.147
sqm
3.220
cum
0.068
sqm
0.720
sqm
1.600
1400 x 2300 mm
*Teak wood
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of holdfasts and all wind
appliances (Vide relevant standard specification)
Rate
Rs.
5
Amount
Rs.
6
BLD-CSTN-11-6
ii
iii
Single Shutter
800 x 2000 mm
*Teak wood
Five - Ply - Ply - Wood brich
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of holdfasts and all wind
appliances (Vide relevant standard specification)
Total for each door
900 x 2000 mm
*Teak wood
Five - Ply - Ply - Wood brich
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of holdfasts and all wind
appliances (Vide relevant standard specification)
Total for each door
1200 x 2100 mm
*Teak wood
Five - Ply - Ply - Wood brich
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of holdfasts and all wind
appliances (Vide relevant standard specification)
LS
cum
0.071
sqm
0.870
sqm
1.800
cum
0.100
sqm
1.160
sqm
2.520
LS
1300 x 2200 mm
*Teak wood
Five - Ply - Ply - Wood brich
Labour, wrought and putup in position frame &
shutters inclusive of holdfasts and all wind
Sundries
appliances (Vide relevant standard specification)
cum
0.106
sqm
1.390
sqm
2.860
cum
0.077
sqm
0.880
sqm
1.890
LS
722
Remarks
7
BLD-CSTN
Index-code
S No
1
vi
B
i
Description
Unit
Quantity
cum
0.091
sqm
0.880
sqm
2.100
cum
0.082
sqm
0.710
sqm
1.800
*Teak wood
cum
0.088
sqm
0.820
sqm
2.000
*Teak wood
cum
0.090
sqm
sqm
0.940
2.200
*Teak wood
cum
0.123
sqm
sqm
1.900
3.600
cum
sqm
sqm
0.130
1.280
3.600
1000 x 2100 mm
*Teak wood
Five - Ply - Ply - Wood brich
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of holdfasts and all wind
appliances (Vide relevant standard specification)
Total for each door
Double Shutter
900 x 2000 mm
*Teak wood
Five - Ply - Ply - Wood brich
Labour, wrought and putup in position frame &
shutters
Rate
Rs.
5
Amount
Rs.
6
1000 x 2000 mm
1100 x 2000 mm
1400 x 2300 mm
1500 x 2400 mm
*Teak wood
Five - Ply - Ply - Wood brich
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of holdfasts and all wind appliances
(Vide relevant standard specification)
723
Remarks
7
BLD-CSTN
Index-code
BLD-CSTN-11-7
S No
Description
Unit
Quantity
Item 292)
Top Tower bolts (Ave : Size)
Nos
Nos
Nos
Nos
Nos
293)
Top Tower bolts (Ave : Size)
Nos
Nos
Nos
Nos
cum
0.072
sqm
0.470
sqm
1.600
1
2
161 Furniture - Iron - for External doors (Schedule
Rate
Rs.
5
Amount
Rs.
6
BLD-CSTN-11-8
BLD-CSTN-11-9
294)
A
i
ii
iii
iv
Single Shutter
800 x 2000 mm
*Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and all
wind
appliances
(Vide
relevant
standard
specification)
Total for each door
900 x 2000 mm
*Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and all
wind
appliances
(Vide
relevant
standard
specification)
Total for each door
1200 x 2100 mm
*Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and all
wind
appliances
(Vide
relevant
standard
specification)
Total for each door
1300 x 2200 mm
*Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and all
wind
appliances
(Vide
relevant
standard
specification)
Total for each door
LS
cum
0.076
sqm
0.560
sqm
1.800
LS
cum
0.106
sqm
0.760
sqm
2.520
LS
cum
0.115
sqm
0.870
sqm
2.860
LS
724
Remarks
7
BLD-CSTN
Index-code
S No
1
B
i
ii
iii
iv
Description
Unit
Quantity
cum
0.087
sqm
0.420
sqm
1.800
Rate
Rs.
5
Amount
Rs.
6
Double Shutter
900 x 2000 mm
*Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and all
wind
appliances
(Vide
relevant
standard
specification)
Total for each door
1000 x 2000 mm
*Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and all
wind
appliances
(Vide
relevant
standard
specification)
Total for each door
1100 x 2000 mm
*Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and all
wind
appliances
(Vide
relevant
standard
specification)
Total for each door
1400 x 2300 mm
*Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and all
wind
appliances
(Vide
relevant
standard
specification)
Total for each door
1500 x 2400 mm
*Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and all
wind
appliances
(Vide
relevant
standard
specification)
Total for each door
* Note : Average rate for respective size scantlings
and rough planks.
LS
cum
0.092
sqm
0.510
sqm
2.000
LS
cum
0.096
sqm
0.600
sqm
2.200
LS
cum
0.123
sqm
1.060
sqm
3.220
LS
cum
0.130
sqm
1.280
sqm
3.600
LS
725
Remarks
7
BLD-CSTN
Index-code
BLD-CSTN-11-10
S No
Description
1
2
164 Furniture - Same as for Fully Panelled Doors
Unit
Quantity
cum
0.107
sqm
2.000
Rate
Rs.
5
Amount
Rs.
6
BLD-CSTN-11-11
ii
BLD-CSTN-11-12
296)
1000 x 2000 mm
*Teak wood
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and
wind appliances and screws for planks (Vide
standard specification)
Total for each door
1200 x 2100 mm
*Teak wood
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and
wind appliances and screws for planks (Vide
standard specification)
Total for each door
* Note : Average rate for respective size scantlings
and rough planks.
LS
cum
0.127
sqm
2.520
LS
1000 x 2000 mm
Country wood
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and
wind appliances and screws for planks (Vide
standard specification)
cum
sqm
0.107
2.000
LS
ii
cum
0.127
sqm
2.520
LS
cum
0.083
sqm
1.600
LS
LS
726
Remarks
7
BLD-CSTN
Index-code
S No
1
ii
Description
Unit
Quantity
cum
0.100
sqm
2.100
1000 x 2100 mm
*Teak wood
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of hold fasts and wind
appliances and nails for planks (Vide standard
specification)
** Furniture - 3 Nos T - hinges - Vide SS for size - 2
Nos Chain and slopes country make.
Total for each door
Note : * Average rate for respective size scantlings
and rough planks.
Rate
Rs.
5
Amount
Rs.
6
LS
LS
BLD-CSTN-11-15
ii
cum
0.083
sqm
1.600
LS
LS
cum
0.100
sqm
2.100
LS
LS
BLD-CSTN-11-16
cum
0.035
sqm
1.530
sqm
1.800
727
Remarks
7
BLD-CSTN
Index-code
S No
1
ii
Description
Unit
Quantity
cum
0.037
sqm
1.820
sqm
2.100
cum
0.028
sqm
0.390
sqm
0.720
cum
0.037
sqm
0.500
sqm
0.960
cum
0.041
sqm
0.700
sqm
1.200
cum
0.061
sqm
0.710
sqm
1.440
cum
0.072
sqm
0.920
sqm
1.800
cum
0.059
sqm
0.970
sqm
1.700
1000 x 2100 mm
*Teak wood
Flush Shutter 35mm thick (Vide relevant standard
specification)
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of hold fasts and all wind
appliances (Vide standard specification)
Total for each door
*Note : Average rate for respective size scantlings.
Rate
Rs.
5
Amount
Rs.
6
Single Shutter :
600 x 1200 mm
*Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and wind
appliances (Vide standard specification)
ii
B
i
ii
iii
iv
728
Remarks
7
BLD-CSTN
Index-code
S No
1
BLD-CSTN-11-18
BLD-CSTN-11-19
BLD-CSTN-11-20
172
173
174
BLD-CSTN-11-21 175
A
i
ii
B
i
ii
Description
Unit
Quantity
each
each
each
each
Rate
Rs.
5
Amount
Rs.
6
LS
each
each
each
LS
each
each
each
cum
0.039
sqm
0.720
cum
0.043
sqm
0.840
cum
0.051
sqm
0.960
cum
0.059
sqm
1.200
cum
0.081
sqm
1.440
729
Remarks
7
BLD-CSTN
Index-code
S No
1
iv
Description
Unit
Quantity
cum
0.056
sqm
1.080
cum
0.036
sqm
0.070
sqm
0.720
cum
0.052
sqm
0.100
sqm
1.080
cum
0.077
sqm
0.120
sqm
1.440
cum
0.094
sqm
0.150
sqm
1.800
each
each
each
each
each
each
each
each
900 x 1200 mm
**Teak wood
Labour, wrought and putup in position frame &
shutters
Rate
Rs.
5
Amount
Rs.
6
BLD-CSTN-11-22
B
i
307)
Single Shutter
600 x 1200 mm
**Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and
wind appliances (Vide standard specification)
Total for each window
Double Shutter
900 x 1200 mm
**Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty, brads, hold fasts and wind
appliances (Vide standard specification)
ii
730
Remarks
7
BLD-CSTN
Index-code
S No
1
i
Description
Unit
Quantity
cum
0.034
sqm
0.720
iii
iv
Amount
Rs.
6
LS
cum
0.048
sqm
0.960
LS
cum
0.052
sqm
1.080
LS
cum
0.052
sqm
1.200
Rate
Rs.
5
LS
BLD-CSTN-11-25
800 x 500 mm
*Teak wood
Glass
Wire netting
Labour, wrought and putup in position
Sundries inclusive of putty brads and iron hold fasts where
such are necessary say in 30 cm wall.
ii
iii
cum
0.012
sqm
0.240
sqm
0.190
sqm
0.400
LS
cum
0.014
sqm
0.310
sqm
0.240
sqm
0.500
LS
cum
0.018
sqm
0.480
sqm
0.290
sqm
0.720
LS
731
Remarks
7
BLD-CSTN
Index-code
BLD-CSTN-11-26
S No
Description
1
2
181 Swing Ventilators - Glazed (Schedule Item No.
i
ii
iii
313)
800 x 500 mm
*Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty brads sash centres brass
ring iron cleats and window card - vide relevant
standard specifications.
Total for each Ventilator
1000 x 500 mm
*Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty brads sash centres brass
ring iron cleats and window card - vide relevant
standard specifications.
Total for each Ventilator
1200 x 600 mm
*Teak wood
Glass
Labour, wrought and putup in position frame &
shutters
Sundries inclusive of putty brads sash centres brass
ring iron cleats and window card - vide relevant
standard specifications.
Total for each Ventilator
*Note : Average rate for respective size scantlings
and rough planks.
Unit
Quantity
cum
0.021
sqm
0.190
sqm
0.400
Rate
Rs.
5
Amount
Rs.
6
LS
cum
0.025
sqm
0.024
sqm
0.500
LS
cum
0.030
sqm
0.390
sqm
0.720
LS
BLD-CSTN-11-27
Unit - 1 sqm
A) MATERIAL REQUIREMENT
ALUMINIUM SECTION
GLAZING with GLASS
SILICON SEALANT
RUBBER BEADING
B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
Power Saw Cutter - Hand Operated - Operator
Power Drill - Hand Operated - Operator
Unskilled Mazdoor
C) Machinery
Power Saw Cutter - Hand Operated - Hire charges
Power Drill - Hand Operated - Hire Charges
Supervision Charges
Power charges for Motors
BASIC COST per 1 sqm
Aluminimum Partition partly glazed
day
0.947
day
1.158
day
0.105
day
0.211
day
0.632
Hrs
0.842
Hrs
1.684
Nos
0.211
1%
732
Remarks
7
BLD-CSTN
Index-code
S No
Description
1
2
183 Supply and fixing of aluminimum Partition partly
BLD-CSTN-11-28
Unit
Quantity
Rate
Rs.
5
Amount
Rs.
6
ALUMINIUM SECTION
PARTICLE BOARD - Prelaminated
GLAZING with GLASS
SILICON SEALANT
RUBBER BEADING
as per design
as per design
as per design
B) LABOUR CHARGES
day
1.042
day
1.042
day
0.104
day
0.139
day
0.347
Hrs
0.833
Hrs
1.111
Nos
0.174
1%
Unit - 1 sqm
A) MATERIAL REQUIREMENT
ALUMINIUM SECTION
GLAZING with GLASS
SILICON SEALANT
RUBBER BEADING
as per design
as per design
Alum.Anodised.PC Handles
B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
as per design
as per design
as per design
as per design
day
0.360
day
1.081
733
Remarks
7
BLD-CSTN
Index-code
S No
Description
Unit
Quantity
3
day
4
0.360
day
0.360
day
1.081
Hrs
2.883
Hrs
2.883
Nos
0.360
BLD-CSTN-11-30
Rate
Rs.
5
Amount
Rs.
6
1%
UNIT 1 sqm
A) MATERIAL REQUIREMENT
ALUMINIUM SECTION
GLAZING with GLASS
SILICON SEALANT
RUBBER BEADING
Alum.Anodised.PC Handles
as per design
as per design
as per design
as per design
as per design
B) LABOUR CHARGES
day
0.347
day
1.042
day
0.347
day
0.347
day
1.042
Hrs
2.778
Hrs
2.778
Nos
0.347
1%
734
Remarks
7
BLD-CSTN
Index-code
S No
1
Description
Unit
Quantity
Rate
Rs.
5
Amount
Rs.
6
BLD-CSTN-11-31
UNIT 1 sqm
A) MATERIAL REQUIREMENT
ALUMINIUM SECTION
GLAZING with GLASS
SILICON SEALANT
RUBBER BEADING
Alum.Anodised.PC Handles
Hydraulic Floor Spring/ Door Closure
B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
Power Saw Cutter - Hand Operated - Operator
Power Drill - Hand Operated - Operator
Unskilled Mazdoor
C) Machinery
Power Saw Cutter - Hand Operated - Hire charges
Power Drill - Hand Operated - Hire Charges
Supervision Charges
Power charges for Motors
BASIC COST per 1 sqm
187 Removing white wash or colour wash by steel wire
brushing and/or scraping; sand papering and
preparing the wall surface smooth including
BLD-CSTN-11-32
necessary repairs to scratches complete
as per design
as per design
as per design
as per design
as per design
as per design
day
0.417
day
0.833
day
0.417
day
0.417
day
1.250
Hrs
3.333
Hrs
3.333
Nos
0.417
1%
0.010
0.170
735
Remarks
7
BLD-CSTN
Index-code
S No
Description
1
2
189 Removing white wash or colour wash by steel wire
BLD-CSTN-11-34
Unit
Quantity
Rate
Rs.
5
Amount
Rs.
6
10 sqm
day
0.080
10 sqm
BLD-CSTN-11-36
day
day
0.010
0.170
day
day
0.010
0.170
BLD-CSTN-11-38
736
Remarks
7
BLD-CSTN
Index-code
S No
1
BLD-CSTN-12
BLD-CSTN-12-1
BLD-CSTN-12-2
BLD-CSTN-12-3
Description
Unit
Quantity
day
1.220
day
2.440
day
4.880
day
4.320
day
4.090
day
day
0.500
0.500
Rate
Rs.
5
Amount
Rs.
6
737
Remarks
7
BLD-CSTN
Index-code
S No
1
197 Dismantling
Unit
Quantity
day
day
day
0.100
0.200
0.050
day
day
day
0.130
0.270
0.070
day
day
0.060
0.120
day
day
0.080
0.160
ii
3.150
day
day
day
0.090
0.250
0.250
ii
BLD-CSTN-13
Rate
Rs.
5
Amount
Rs.
6
BLD-CSTN-12-4
BLD-CSTN-12-5
Description
BLD-CSTN-13-1
738
Remarks
7
BLD-CSTN
Index-code
S No
Description
1
2
200 Providing and fixing aluminium step edging 'L'
BLD-CSTN-13-2
Unit
Quantity
3.150
day
day
day
0.090
0.250
0.250
day
day
1.000
0.100
1.310
day
day
day
0.100
0.400
0.400
1.310
day
day
day
0.100
0.400
0.400
Rate
Rs.
5
Amount
Rs.
6
BLD-CSTN-13-3
BLD-CSTN-13-4
Cement Mortar
Labour :Mason, II Class
Mazdoor (male)
Add for water charges @ 1 %
Cost for 3 m
Cost per m
202 Providing and fixing 25 mm bore galvanised M.S.
tube (light grade) outlet in cement mortar 1:3(1
cement: 3 fine sand) including cutting and making
good the wall
Details of cost for 10 pipes 12.5 cm long day i.e.,
1.25 metres
Materials:
Galvanised mild steel tube (light grade) 25 mm
nominal bore 10 x 12.5 cm = 1.25 metre with
wastage of 5%
Labour :For cutting and fixing in position
Assistant fitter
Mason.
Mazdoor (male).
Sundries
Add for water charges @ 1 %
Cost for 1.25 m
Cost per m
203 Providing and fixing 1.80 metre long RCC fencing
BLD-CSTN-13-5
739
Remarks
7
BLD-CSTN
Index-code
BLD-CSTN-13-6
S No
Description
Unit
Quantity
cum
0.336
kg
26.440
cum
0.336
sqm
9.880
day
day
day
0.120
0.120
0.250
10 sqm
1.000
Deduct - CM 1:3
cum
0.025
cum
30.000
Rate
Rs.
5
Amount
Rs.
6
740
Remarks
7
BLD-CSTN
Index-code
S No
1
Description
Unit
Quantity
kg
9.380
Rate
Rs.
5
Amount
Rs.
6
0.2770*
3x0.165x0.75=0.3712
0.165x0.165=0.0272
0.10 x 0.10=0.0100/0.6992 Sq.m..
For ten posts=10 x 0.6992 = 6.992 Sq.m.
Quantity
of
surface
plaster
12.50+7.60+7.60=27.70 Cm.
xr=3.1416x5=15.71Cm./43.41Cm
1.05=0.4560 Sq.m.
BLD-CSTN-13-7
area
0.434
4x0.165x0.75=0.4950
0.165x0.165=0.0272
0.10 x 0.10=0.0100/0.9882 Sq.m.
For 10
posts = 10 x 0.9882=9.88 Sq.m.
205 Supplying and fixing galvanised steel barbed wire
(IS : 278-1962 Type I) weighing 9.38 Kg per 100
metres (min.), Straining and fixing to any type of
standard, rails, straining bolts, including securing
with and provision of galvanised mild steel wire,
stapples or steel pins, etc., as directed (Posts and
struts of wood, concrete, steel, etc.) and straining
bolts shall be paid for separately).
Details of Cost per 100 metres (day line of wire)
Materials:
Galvanised steel barbed wire IS type I weighing
9.38 Kg/100 metre
BLD-CSTN-13-8
LS
day
day
day
0.150
0.150
0.300
kg
cum
19.500
0.040
day
day
0.080
0.160
741
Remarks
7
BLD-CSTN
Index-code
S No
Description
Unit
Quantity
Amount
Rs.
6
ANTE-TERMITE TREATMENT
BLD-CSTN-14
BLD-CSTN-14-1
Rate
Rs.
5
Unit = 10 sqm
A) Chlorpyriphos/ Lindane emulsifiable concentrate of
20%
Lit
4.100
Liters
0.41
4.51
1%
day
day
3.0
0.22
Total Quantity
B) Add Water Charges @ 1%
C) Labour Charges
Man Mazdoor
Sprayer
D) Hire charges
Sprayer, drilling machine etc
sundries & contingencies
Water charges & electricity
10%
3%
1.50%
Add OH & CP
BASIC COST per 1 sqm
Note: CPWD - Rate Analysis per 9 Sqm
BLD-CSTN-15
BLD-CSTN-15-1
Vertical
Chloropyriphos
Earthwork excavation
Beldar
Horizontal
Chloropyriphos
Vertical
Beldar
Hire charges
Sprayer, drilling machine etc
sundries & contingencies
Water charges & electricity
Add OH & CP
CENTERING, FORM WORK etc.
208 Providing traditional centering, shuttering and
scaffolding using Cashewrina balli props and
bracings supporting wooden brackets, wooden wall
plates, wooden runners and steel plate form work
as per the approved plan and other accessories as
per the standard trade practice including hire
charges for ballies, runners, wooden members and
cost and conveyance of all other consumable
accessories, taxes etc complete for finished item of
work
(I)
Lit
cum
Nos
Lit
Nos
Nos
UNIT 1 sqm
Unsupported Roof Height up to - 3.66 M (12'0")
A) MATERIAL REQUIREMENT
Cashewrina Balli Props - 3" to 4" dia - 12'-0" Height
Nos
2.40
742
Remarks
7
BLD-CSTN
Index-code
S No
1
Description
Unit
Quantity
3
Nos
4
1.44
BLD-CSTN-15-2
B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
Unskilled Mazdoor
Supervision Charges
Consumables like Rope, Nails, de-shuttering oil
Tape, cover plates
Tools like Hammers etc.,
BASIC COST per 1 sqm
(II) Unsupported Roof Height up to - 4.60 M (15'0")
A) MATERIAL REQUIREMENT
Cashewrina Balli Props - 3" to 4" dia - 12'-0" Height
Wall Plate Brackets / beam bottom supports
Wedge Plate fixture
Runner beams of approximately 4" x 4" size
Steel Plate - form work plates B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
Unskilled Mazdoor
Supervision Charges
Consumables like Rope, Nails, de-shuttering oil
Tape, cover plates
Tools like Hammers etc.,
BASIC COST per 1 sqm
(III) Unsupported Roof Height up to - 7.30 M (24'0")
A) MATERIAL REQUIREMENT
Cashewrina Balli Props - 3" to 4" dia - 12'-0" Height
Wall Plate Brackets / beam bottom supports
Wedge Plate fixture
Runner beams of approximately 4" x 4" size
Steel Plate - form work plates B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
Unskilled Mazdoor
Supervision Charges
Consumables like Rope, Nails, de-shuttering oil
Tape, cover plates
Tools like Hammers etc.,
BASIC COST per 1 sqm
209 Providing rigid Steel centering, shuttering and
scaffolding using steel pipes, adjustable Jack screw
props, acro spans, couplers, tie rods, bracings
members, supporting brackets, acro span beams
and steel plate/ ply-wood form work as per the
approved shuttering designs & plan and other
accessories as per the IS Norms and stability
calculations including hire charges for jack pipes,
acro spans, runners, wooden members and cost
and conveyance of all other consumable
accessories, taxes etc complete for finished item of
work
(I)
Nos
1.44
RM
sqm
16.00
1.86
day
day
day
day
Rate
Rs.
5
Amount
Rs.
6
0.00
0.16
0.28
0.48
0.04
1%
1%
1%
Nos
Nos
4.32
1.44
Nos
RM
sqm
1.44
16.00
1.86
Nos
Nos
Nos
0.20
0.36
0.68
Nos
0.06
1%
1%
1%
Nos
Nos
Nos
RM
sqm
5.76
1.44
1.44
16.00
1.86
Nos
Nos
Nos
Nos
0.28
0.52
1.08
0.08
1%
1%
1%
UNIT 1 sqm
Unsupported Roof Height up to - 3.66 M (12'0")
A) MATERIAL REQUIREMENT
Jack Screw Adjsutable Props - 50 mm dia B Class
Pipes
for vertical props placed @ 3'0" c/c in bothways
Approximately 33'-0" x 33'-0" roof area
743
Remarks
7
BLD-CSTN
Index-code
S No
1
Description
Unit
Quantity
Kgs
62.51
day
day
day
day
0.22
0.38
0.72
0.04
1%
Rate
Rs.
5
Amount
Rs.
6
(II)
1%
1%
Kgs
112.635
day
0.32
day
0.52
day
1.28
day
0.06
1%
1%
1%
744
Remarks
7
BLD-CSTN
Index-code
S No
Description
Unit
Quantity
Rate
Rs.
5
Amount
Rs.
6
Note : Cost of Centering charges with different centering & scaffolding materials for
different structures may be calculated as per the guidelines given Below
TYPE OF STRUCTURE
UNIT
COS
CENTERING AREA T OF
CENT
ERIN
A
B
RCC
STRUCTU
RE UNIT
MEASUR
EMENT
C
FOOTINGS
3.88 sqm
per 1 cum
PEDESTALS
6.17 sqm
per 1 cum
PLINTH BEAMS
9.35 sqm
per 1 cum
LINTELS
7.94 sqm
per 1 cum
CHAJJAS - SUNSHADES
1.22 sqm
per 1 sqm
COLUMNS
11.15 sqm
per 1 cum
BEAMS
9.35 sqm
per 1 cum
1.05 sqm
per 1 sqm
1.09 sqm
per 1 sqm
1.14 sqm
per 1 sqm
3.85 sqm
per 1 sqm
2.70 sqm
per 1 sqm
10.63 sqm
per 1 cum
10.78 sqm
per 1 cum
DOME SLABS
17.19 sqm
per 1 cum
HELICAL STAIRCASES
1.31 sqm
per 1 sqm
For calculating centering charges of RCC Structures, using either cashewrina balli
scaffolding or steel pipe scaffolding, the respective cost may be arrived by taking the
above
values.
Therefore,
Centering charges for any structure:C= A x B
210 Providing STAGE SCAFFOLD with staging using
BLD-CSTN-15-3
(I)
UNIT 1 sqm
Unsupported Roof Height up to - 3.66 M (12'0")
A) MATERIAL REQUIREMENT
Cashewrina Balli Props - 3" to 4" dia - 12'-0" Height
Scaffold Boards - Bamboo scaffolds - Bamboos 8'0" long
B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
Unskilled Mazdoor
Supervision Charges
Consumables like Rope, Nails, de-shuttering oil
Nos
2.40
Nos
2.70
day
0.04
day
0.30
day
0.48
day
0.04
1%
745
Remarks
7
BLD-CSTN
Index-code
S No
Description
Unit
Quantity
4
1%
(II)
BLD-CSTN-15-4
4.32
Nos
2.70
day
0.08
day
0.38
day
0.68
day
0.06
Nos
5.76
Nos
2.70
day
0.12
day
0.54
day
1.08
day
0.08
UNIT 1 sqm
Up to - 3.66 M (12'0")
A) MATERIAL REQUIREMENT
Cashewrina Balli Props - 3" to 4" dia - 12'-0" Height
Scaffold Boards - Bamboo scaffolds - Bamboos 8'0" long
B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
Unskilled Mazdoor
Supervision Charges
Consumables like Rope, Nails, de-shuttering oil
Tape, cover plates
Tools like Hammers etc.,
Amount
Rs.
6
1%
Nos
(I)
Rate
Rs.
5
1%
1%
1%
1%
1%
1%
Nos
1.74
Nos
0.72
day
0.07
day
0.11
day
0.2
day
0.04
1%
1%
1%
Up to - 7.32 M (24'0")
A) MATERIAL REQUIREMENT
746
Remarks
7
BLD-CSTN
Index-code
S No
Description
Unit
Quantity
3
Nos
4
1.74
Nos
0.38
day
0.12
day
0.22
day
0.36
day
0.04
Rate
Rs.
5
Amount
Rs.
6
1%
1%
1%
BLD-CSTN-15-5
(I)
UNIT 1 sqm
Unsupported Roof Height up to - 3.66 M (12'0")
(II)
A) MATERIAL REQUIREMENT
Jack Screw Adjsutable Props - 50 mm dia B Class
Pipes
for vertical props placed @ 3'0" c/c in bothways
Lock Pins
LD Foot Plates
LD Couplers
Total Scaffolding Pipes - Appx B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
Unskilled Mazdoor
Supervision Charges
Consumables like Rope, Nails, de-shuttering oil
Tape, cover plates
Tools like Hammers etc.,
BASIC COST per 1 sqm - PLAN AREA
Unsupported Roof Height up to - 7.32 M (24'0")
A) MATERIAL REQUIREMENT
Heavy Frames - 50 mm dia B Class Pipes (HD
Towers)
Lock Pins
LD Foot Plates
LD Couplers
Total Scaffolding Pipes - Appx B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
Unskilled Mazdoor
Supervision Charges
Consumables like Rope, Nails, de-shuttering oil
Tape, cover plates
Tools like Hammers etc.,
BASIC COST per 1 sqm - PLAN AREA
Kgs
39.26
day
0.04
day
0.34
day
0.60
day
0.04
1%
1%
1%
Kgs
112.635
day
0.12
day
0.58
day
1.20
day
0.08
1%
1%
1%
747
Remarks
7
BLD-CSTN
Index-code
BLD-CSTN-15-6
S No
Description
1
2
213 Providing ACCESS SCAFFOLD using Steel Scaffolding
Pipe Frames made of 40 mmd ia MS Pipes and bracings
with scaffold boards including hire charges for MS Pipe
Frames scaffolds boards etc., and cost and conveyance of
all other consumable accessories, taxes etc complete for
finished item of work for ELEVATION AREA
(I)
Unit
Quantity
Kgs
19.7496
day
0.07
day
0.11
day
0.24
day
0.04
Rate
Rs.
5
Amount
Rs.
6
UNIT 1 sqm
Up to - 3.66 M (12'0")
A) MATERIAL REQUIREMENT
MS Pipe Scaffold Frames - 1.20 x 1.50 M
Approximately 27.3 M Long x 3.66 M High
1%
1%
1%
Up to - 7.32 M (24'0")
A) MATERIAL REQUIREMENT
MS Pipe Scaffold Frames - 1.20 x 1.50 M
Approximately 27.3 M Long x 3.66 M High
Kgs
19.14
day
0.12
day
0.22
day
0.44
day
0.04
1%
1%
1%
Rs. A
(Rs. A - Rs. B)
C
748
Remarks
7
BLD-CSTN
Index-code
S No
1
Description
2
(Usually B = A * 10%)
Period of Hire of Scaffolding materials, in years =
Life of Scaffolding materials, in years =
Therefore, Hire Charges of scaffolding Materials:
Unit
Quantity
Rate
Rs.
5
Amount
Rs.
6
C
D
[(Rs. A - Rs. B)*C]
D
Note: While calculating the Capital Cost of the materials, deprication shall be allowed
based on the service life of the materials.
Number of uses of Scaffolding materials (C )
Wooden Materials - No of Uses - 10 Times (C)
Period of Hire of Steel Scaffolding materials, in years = 1.64 (200 days per Annum)
Life of Steel Forms & Scafholding Material - 3 Years (D)
Period of Requirement of Centering Material
Slabs : 14 + 4 = 18 days
Columns : 1.50 days
Foundations : 2 days
749
Remarks
7
PHE
S No
1
Description
Unit
Quantity
Rate
Rs.
5
Amt
Rs.
6
Remarks
7
Sub Analysis
Lowering C.I. Pipes, A class and specials with s/s ends carefully
into trench and laying them true to alignment and gradient
including all sundries but excluding cost and conveyance of
pipes from source of supply. (Reference to specifications. BIS
No.3114/94)
Assumtion 10 m
Common Data
PHE-LCIS-1
ii
iii
iv
st
day
Plumber 1 class
nd
day
Plumber 2 class
day
Man mazdoor
(b) Cost for 10 metres
Rate per metre = b/10
Rate for 1 kg = b/514
Lowering C.I. / D.I. Pipes (all classes) and specials (fittings) with
s/s ends carefully into trenches and laying them true to
alignment and gradient including all sundries but excluding cost
and conveyance of pipes from source of supply (Ref to
specifications. BIS No.3114/1994)
Note : The Labour charges for cost of Lowering & Laying per 1
kg weight shall be as per sub-analysis made for 200 mm dia CI
Pipes S/s ends.
Details of cost for 5m
80 mm dia pipe
Weight of 5m length = (79 +85.5 + 92)/3 = 85.5 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
(c) Cost for 5 metres = a+b
Rate per metre = c/5
100 mm dia pipe
Weight of 5m length = (100+109+117)/3 = 108.67 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
(c) Cost for 5 metres = a+b
Rate per metre = c/5
125 mm dia pipe
Weight of 5m length = (130+141+153)/3 = 141.33 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
(c) Cost for 5 metres = a+b
Rate per metre = c/5
150mm dia pipe
Weight of 5m length = (162+178+191)/3 = 177 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
(c) Cost for 5 metres = a+b
Rate per metre = c/5
200 mm dia pipe
Weight of 5m length = (237+257+278)/3 = 257.33 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
(c) Cost for 5 metres = a+b
Rate per metre = c/5
0.102
0.238
1.330
kgs
85.500
kgs
108.670
kgs
141.330
kgs
177.000
kgs
257.330
864
Index-code
S No
1
vi
vii
viii
ix
xi
xii
xiii
xiv
xv
Description
Unit
Quantity
kgs
347.670
kgs
449.670
kgs
564.000
kgs
688.330
kgs
832.670
kgs
970.670
kgs
1296.000
kgs
1672.000
kgs
1874.330
kgs
2092.670
Rate
Rs.
5
Amt
Rs.
6
PHE
Remarks
7
865
Index-code
S No
1
Description
Unit
Quantity
kgs
2544.000
kgs
3068.000
kgs
22.490
kgs
28.450
kgs
36.950
kgs
46.470
kgs
66.860
kgs
90.530
kgs
116.860
kgs
147.320
Rate
Rs.
5
Amt
Rs.
6
PHE
Remarks
7
PHE-LCIF-2
Lowering C.I. / D.I. Pipes (all classes) and specials (fittings) with flanged
ends carefully into trench and laying them true to alignment and gradient
including all sundries but excluding cost and conveyance of pipes from
source of supply. (Reference to specifications. BIS No.3114/1994)
Note : The cost of lowering and laying is taken as per sub analysis made
for S/S ends.
866
Index-code
S No
Description
Unit
Quantity
kgs
179.620
kgs
216.270
kgs
252.650
kgs
338.500
kgs
437.860
kgs
494.490
day
day
3.000
3.000
Hire chargers for Hydralic field test pressure testing including days
transportation of water @ Rs. 1200/- (1000+200) / day
3.000
1
ix
xi
xii
xiii
xiv
PHE-LCIF-2A
2A
Rate
Rs.
5
Amt
Rs.
6
PHE
Remarks
7
(Length = 500 Mts) taking out put / 500 Mts. Unit = 1 Rmt.
Labour
Fitters (2 x 3 days)
Fitters I Class
Fitters II Class
Machinery
Materials
Pressure guage
3/4" G.I. Pipe (20 mm)
Specials
Dummies
Diesel (2 Lts. / Hr) 30 Hrs.
(T) Total Rate per 500 Mts.
(r) Rate per 1 Rmt for 450 mm dia
(R) Rate per 1 Rmt for 10 mm dia = (10/450) x r
Note : Proportionate Testing Charges may be arrived,
keeping the diametre of pipe based on this analysis, for an
varities of pipes for various Dia Pipes.
Nos
RM
Ls
No.
Lts.
0.050
3.000
0.100
60.000
867
Index-code
S No
Description
Unit
Quantity
Jointing CI /DI pipes & fittings with s/s ends including cost of
pig lead, hemp yarn and sundries such as cost of fuel for
melting lead, filling with water with lead up to 500m and testing
to required pressure complete. (Reference to specifications. BIS
No.3114/94/12288:1997)
Details of cost for 10 joints
80 mm dia pipe
a) Labour
day
0.135
day
0.320
day
1.200
0.190
litre
0.330
PHE-JCIS-3
st
Plumber 1 class
nd
Plumber 2 class
Man mazdoor
b) Material
Fuel wood
Kerosene
Spun yarn
Pig lead
c) Testing
Testing of Pipelines with required pressure as per relevant IS
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment and
Materials needed for testing (as per Sub Analysis 2 A)
(d) Total = a+b+c
(e) Add for water charges @ 1%on Labour & Testing Charges
ii
1.000
kg
20.000
rm
50.000
day
0.220
day
0.530
day
1.500
0.250
litre
0.330
Amt
Rs.
6
PHE
Remarks
7
Plumber 1 class
nd
Plumber 2 class
Man mazdoor
b) Material
Fuel wood
Kerosene
Spun yarn
Pig lead
c) Testing
Testing of Pipelines with required pressure as per relevant IS
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment and
Materials needed for testing (as per Sub Analysis 2 A)
iii
kg
Rate
Rs.
5
kg
1.800
kg
24.000
rm
50.000
day
0.220
day
0.530
day
1.500
0.370
litre
0.700
kg
2.000
kg
28.000
868
Index-code
S No
1
Description
Unit
Quantity
rm
50.000
day
0.270
day
0.630
day
1.650
0.420
litre
0.760
c) Testing
Testing of Pipelines with required pressure as per relevant IS
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)
iv
Amt
Rs.
6
PHE
Remarks
7
Plumber 1 class
nd
Plumber 2 class
Man mazdoor
b) Material
Fuel wood
Kerosene
Spun yarn
Pig lead
c) Testing
Testing of Pipelines with required pressure as per relevant IS
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)
Rate
Rs.
5
kg
2.000
kg
36.000
rm
50.000
day
0.270
day
0.630
day
1.650
0.560
litre
0.756
kg
3.000
kg
54.000
rm
50.000
869
Index-code
S No
1
vi
Description
Unit
Quantity
day
0.280
day
day
0.650
1.800
q
litre
kg
0.650
1.140
3.500
kg
66.000
rm
50.000
day
0.360
day
0.840
day
1.800
q
litre
kg
0.750
1.520
4.800
kg
76.000
rm
50.000
day
0.400
day
0.950
day
2.250
q
litre
0.930
1.700
Rate
Rs.
5
Amt
Rs.
6
PHE
Remarks
7
Plumber 1 class
nd
Plumber 2 class
Man mazdoor
b) Material
Fuel wood
Kerosene
Spun yarn
Pig lead
c) Testing
Testing of Pipelines with required pressure as per relevant IS
Specification including filling with water with a water lead upto 500 M,
including hire charges of testing equipment, labour and Materials needed
for testing (as per Sub Analysis 2 A)
Plumber 1 class
nd
Plumber 2 class
Man mazdoor
b) Material
Fuel wood
Kerosene
Spun yarn
Pig lead
c) Testing
Testing of Pipelines with required pressure as per relevant IS
Specification including filling with water with a water lead upto 500 M,
including hire charges of testing equipment, labour and Materials needed
for testing (as per Sub Analysis 2 A)
Plumber 2 class
Man mazdoor
b) Material
Fuel wood
Kerosene
Spun yarn
Pig lead
c) Testing
Testing of Pipelines with required pressure as per relevant IS
Specification including filling with water with a water lead upto 500 M,
including hire charges of testing equipment, labour and Materials needed
for testing (as per Sub Analysis 2 A)
kg
6.000
kg
90.000
rm
50.000
870
Index-code
S No
Description
Unit
Quantity
Plumber 1 class
nd
Plumber 2 class
Man mazdoor
b) Material
Fuel wood
Kerosene
Spun yarn
Pig lead
c) Testing
Testing of Pipelines with required pressure as per relevant IS
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)
day
0.310
day
0.740
day
2.250
q
litre
1.120
1.700
1
ix
Rate
Rs.
5
Amt
Rs.
6
PHE
Remarks
7
kg
7.500
kg
105.000
rm
50.000
day
0.540
day
1.260
day
2.550
1.210
litre
2.270
kg
9.500
kg
150.000
rm
50.000
day
0.580
day
1.370
day
2.700
1.310
xi
litre
2.270
kg
10.000
kg
160.000
rm
50.000
871
Index-code
S No
1
Description
Unit
Quantity
day
0.680
day
1.570
day
3.000
1.680
Rate
Rs.
5
Amt
Rs.
6
PHE
Remarks
7
(e) Add for water charges @ 1%on Labour & Testing Charges
(f) Total = d+e
(g) Overheads & Contractors Profit
(h) Cost for 10 joints (f+g)
Rate per joint =h/10
xii 600 mm dia pipe
a) Labour
Plumber 1st class
Plumber 2nd class
Man mazdoor
b) Material
Fuel wood
Kerosene
Spun yarn
Pig lead
c) Testing
Testing of Pipelines with required pressure as per relevant IS
Specification including filling with water with a water lead upto 500 M,
including hire charges of testing equipment, labour and Materials needed
for testing (as per Sub Analysis 2 A)
litre
2.540
kg
12.000
kg
205.000
rm
50.000
day
0.770
day
1.780
day
3.300
2.100
litre
3.200
kg
13.500
kg
240.000
rm
50.000
day
0.770
day
1.780
day
3.300
2.400
litre
3.500
kg
14.500
kg
270.000
872
Index-code
S No
Description
Unit
Quantity
rm
50.000
day
0.770
day
1.780
day
3.300
2.330
Rate
Rs.
5
Amt
Rs.
6
PHE
Remarks
7
c) Testing
Plumber 1 class
nd
Plumber 2 class
Man mazdoor
b) Material
Fuel wood
Kerosene
Spun yarn
Pig lead
c) Testing
Testing of Pipelines with required pressure as per relevant IS
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment and Labour,
Materials needed for testing (as per Sub Analysis 2 A)
litre
3.410
kg
15.300
kg
325.000
rm
50.000
PHE-JCIR-4
0.300
0.800
50.000
873
Index-code
S No
1
ii
Description
Unit
Quantity
Rate
Rs.
5
Amt
Rs.
6
PHE
Remarks
7
0.500
1.000
50.000
0.500
1.000
50.000
0.600
1.100
50.000
874
Index-code
S No
1
v
Description
Unit
Quantity
Rate
Rs.
5
Amt
Rs.
6
PHE
Remarks
7
0.600
1.100
50.000
0.620
1.200
50.000
0.800
1.200
50.000
875
Index-code
S No
1
Description
Unit
Quantity
Rate
Rs.
5
Amt
Rs.
6
PHE
Remarks
7
a)
Labour
nd
day
Plumber 2 class
day
Man mazdoor
b) Material
each
Rubber gasket
c) Testing
Testing of Pipelines with required pressure as per relevant IS rm
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)
0.900
1.500
50.000
a)
Labour
nd
day
Plumber 2 class
day
Man mazdoor
b) Material
each
Rubber gasket
c) Testing
Testing of Pipelines with required pressure as per relevant IS rm
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)
1.000
1.500
50.000
1.200
1.700
50.000
876
Index-code
S No
1
x
Description
Unit
Quantity
Rate
Rs.
5
Amt
Rs.
6
PHE
Remarks
7
1.300
1.800
50.000
1.500
2.000
50.000
1.600
2.100
50.000
877
Index-code
S No
1
Description
Unit
Quantity
Rate
Rs.
5
Amt
Rs.
6
PHE
Remarks
7
a)
Labour
nd
day
Plumber 2 class
day
Man mazdoor
b) Material
each
Rubber gasket
c) Testing
Testing of Pipelines with required pressure as per relevant IS rm
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)
1.700
2.200
50.000
a)
Labour
nd
day
Plumber 2 class
day
Man mazdoor
b) Material
each
Rubber gasket
c) Testing
Testing of Pipelines with required pressure as per relevant IS rm
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)
1.700
2.200
50.000
day
2.350
day
4.700
day
0.650
each
rm
50.000
878
Index-code
S No
Description
Unit
Quantity
Plumber 1 class
nd
Plumber 2 class
Foreman (work inspector) Non technical
b) Material
Rubber gasket
c) Testing
Testing of Pipelines with required pressure as per relevant IS
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)
day
2.750
day
5.500
day
0.700
Rate
Rs.
5
Amt
Rs.
6
PHE
Remarks
7
a)
Labour
st
each
rm
50.000
day
3.000
day
6.000
day
0.750
a)
Labour
st
Plumber 1 class
Plumber 2nd class
Foreman (work inspector) Non technical
b) Material
Rubber gasket
c) Testing
Testing of Pipelines with required pressure as per relevant IS
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)
each
rm
50.000
day
0.090
day
0.210
day
0.800
kg
kg
6.800
2.125
rm
PHE-JCIF-5
Jointing CI pipes, fittings and valves with flanged ends including cost of
jointing materials such as bolts, rubber insertion, white lead including
filling with water, with lead up to 500 meters and testing to required
pressure complete. (Reference to specifications. BIS No.3114/1994.)
27.500
879
Index-code
S No
1
ii
Description
Unit
Quantity
Rate
Rs.
5
Amt
Rs.
6
PHE
Remarks
7
0.150
0.350
1.000
13.600
2.540
27.500
Plumber 1 class
Plumber 2nd class
Man mazdoor
b) Material
Bolts and nuts 16mm dia 60mm long
Rubber insertion 5mm thick
White lead
c) Testing
day
0.150
day
0.350
day
1.000
kg
kg
13.600
3.140
rm
27.500
day
0.180
day
0.420
day
1.100
kg
kg
24.000
4.300
880
Index-code
S No
1
Description
Unit
Quantity
rm
27.500
c) Testing
Testing of Pipelines with required pressure as per relevant IS
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)
Rate
Rs.
5
Amt
Rs.
6
PHE
Remarks
7
0.180
0.420
1.100
25.200
6.160
27.500
0.200
0.420
1.200
39.600
8.500
27.500
881
Index-code
S No
Description
Unit
Quantity
Plumber 1 class
nd
Plumber 2 class
Man mazdoor
b) Material
Bolts and nuts 20mm dia 75mm long
Rubber insertion 5mm thick
White lead
c) Testing
day
0.240
day
0.560
day
1.200
kg
39.600
kg
10.280
rm
27.500
Plumber 1 class
Plumber 2nd class
Man mazdoor
b) Material
Bolts and nuts 20mm dia 80mm long
Rubber insertion 8mm thick
White lead
c) Testing
day
0.300
day
0.600
day
1.500
kg
54.400
kg
21.260
rm
27.500
day
0.300
day
0.700
day
1.500
kg
kg
98.400
27.640
rm
27.500
day
0.360
day
0.840
1
vii
Rate
Rs.
5
Amt
Rs.
6
PHE
Remarks
7
882
Index-code
S No
Description
Unit
Quantity
3
day
4
1.700
kg
kg
123.000
22.660
rm
27.500
day
0.390
day
0.910
day
1.800
kg
kg
134.000
38.190
rm
27.500
day
0.450
day
1.050
day
2.000
kg
192.000
kg
51.710
rm
27.500
Man mazdoor
b) Material
Bolts and nuts 24mm dia 85mm long
Rubber insertion 8mm thick
White lead
c) Testing
Testing of Pipelines with required pressure as per relevant IS
Specification including filling with water with a water lead upto 500 M,
including hire charges of testing equipment, labour and Materials needed
for testing (as per Sub Analysis 2 A)
xi
Rate
Rs.
5
Amt
Rs.
6
PHE
Remarks
7
883
Index-code
S No
1
Description
Unit
Quantity
Rate
Rs.
5
Amt
Rs.
6
PHE
Remarks
7
a) Labour
st
day
Plumber 1 class
nd
day
Plumber 2 class
day
Man mazdoor
b) Material
kg
Bolts and nuts 24mm dia 90mm long
kg
Rubber insertion 8mm thick
White lead
c) Testing
Testing of Pipelines with required pressure as per relevant IS rm
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)
0.510
1.190
2.200
244.800
68.910
27.500
a)
Labour
st
day
Plumber 1 class
nd
day
Plumber 2 class
day
Man mazdoor
b) Material
kg
Bolts and nuts 24mm dia 90mm long
kg
Rubber insertion 8mm thick
White lead
c) Testing
Testing of Pipelines with required pressure as per relevant IS rm
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)
PHE-LRCS-6
0.510
1.190
2.200
260.400
78.430
27.500
day
0.780
day
1.800
day
5.000
day
1.300
each
50.000
884
Index-code
S No
1
Description
Unit
Quantity
rm
100.000
day
0.960
day
2.240
day
6.300
day
1.600
each
50.000
rm
100.000
day
1.170
day
2.730
day
7.800
day
1.600
each
50.000
rm
100.000
c) Testing
Testing of Pipelines with required pressure as per relevant IS
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)
Rate
Rs.
5
Amt
Rs.
6
PHE
Remarks
7
100 mm dia
a) Labour
Mason 1st class
Mason 2nd class
Man mazdoor
Woman mazdoor(water carrier)
b) Material
Rubber rings conforming BIS 5382/1985
c) Testing
Testing of Pipelines with required pressure as per relevant IS
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)
(d) Total = a+b+c
(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e
(g) Overheads & Contractors Profit
(h) Cost for 100 rmt (f+g)
Rate per rmt = h/100
iii
150 mm dia
a) Labour
Mason 1st class
nd
Mason 2 class
Man mazdoor
Woman mazdoor(water carrier)
b) Material
Rubber rings conforming BIS 5382/1985
c) Testing
Testing of Pipelines with required pressure as per relevant IS
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)
(d) Total = a+b+c
(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e
(g) Overheads & Contractors Profit
(h) Cost for 100 rmt (f+g)
Rate per rmt = h/100
885
Index-code
S No
Description
Unit
Quantity
Mason 1 class
nd
Mason 2 class
Man mazdoor
Woman mazdoor(water carrier)
b) Material
Rubber rings conforming BIS 5382/1985
c) Testing
Testing of Pipelines with required pressure as per relevant IS
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)
day
1.170
day
2.730
day
7.800
day
1.600
each
50.000
rm
100.000
day
1.620
1
iv
Rate
Rs.
5
Amt
Rs.
6
PHE
Remarks
7
200 mm dia
a) Labour
st
225 mm dia
a) Labour
st
Mason 1 class
Mason 2nd class
Man mazdoor
Woman mazdoor(water carrier)
b) Material
Rubber rings conforming BIS 5382/1985
c) Testing
Testing of Pipelines with required pressure as per relevant IS
Specification including filling with water with a water lead upto 500 M,
including hire charges of testing equipment, labour and Materials needed
for testing (as per Sub Analysis 2 A)
day
3.780
day
10.500
day
2.300
each
50.000
rm
100.000
day
1.620
250 mm dia
a) Labour
Mason 1st class
Mason 2nd class
Man mazdoor
Woman mazdoor(water carrier)
b) Material
Rubber rings conforming BIS 5382/1985
c) Testing
Testing of Pipelines with required pressure as per relevant IS
Specification including filling with water with a water lead upto 500 M,
including hire charges of testing equipment, labour and Materials needed
for testing (as per Sub Analysis 2 A)
day
3.780
day
10.500
day
2.300
each
50.000
rm
100.000
886
Index-code
S No
1
vii
Description
Unit
Quantity
day
1.750
Rate
Rs.
5
Amt
Rs.
6
PHE
Remarks
7
300 mm dia
a) Labour
st
Mason 1 class
nd
Mason 2 class
Man mazdoor
Woman mazdoor(water carrier)
b) Material
Rubber rings conforming BIS 5382/1985
c) Testing
Testing of Pipelines with required pressure as per relevant IS
Specification including filling with water with a water lead upto 500 M,
including hire charges of testing equipment, labour and Materials needed
for testing (as per Sub Analysis 2 A)
day
4.140
day
11.600
day
2.300
each
40.000
rm
100.000
day
1.900
a)
Labour
st
Mason 1 class
Mason 2nd class
Man mazdoor
Woman mazdoor(water carrier)
b) Material
Rubber rings conforming BIS 5382/1985
c) Testing
Testing of Pipelines with required pressure as per relevant IS
Specification including filling with water with a water lead upto 500 M,
including hire charges of testing equipment, labour and Materials needed
for testing (as per Sub Analysis 2 A)
day
4.500
day
12.700
day
2.400
each
40.000
rm
100.000
day
2.100
400 mm dia
a) Labour
Mason 1st class
Mason 2nd class
Man mazdoor
Woman mazdoor(water carrier)
b) Material
Rubber rings conforming BIS 5382/1985
c) Testing
Testing of Pipelines with required pressure as per relevant IS
Specification including filling with water with a water lead upto 500 M,
including hire charges of testing equipment, labour and Materials needed
for testing (as per Sub Analysis 2 A)
day
4.900
day
13.900
day
2.900
each
40.000
rm
100.000
887
Index-code
S No
1
x
Description
Unit
Quantity
day
2.250
Amt
Rs.
6
PHE
Remarks
7
450 mm dia
a) Labour
st
Mason 1 class
nd
Mason 2 class
Man mazdoor
Woman mazdoor(water carrier)
b) Material
Rubber rings conforming BIS 5382/1985
c) Testing
Testing of Pipelines with required pressure as per relevant IS
Specification including filling with water with a water lead upto 500 M,
including hire charges of testing equipment, labour and Materials needed
for testing (as per Sub Analysis 2 A)
xi
Rate
Rs.
5
day
5.250
day
15.000
day
3.300
each
40.000
rm
100.000
day
day
day
day
2.430
5.670
16.200
3.300
each
40.000
rm
100.000
day
2.750
600 mm dia
a) Labour
Mason 1st class
Mason 2nd class
Man mazdoor
Woman mazdoor(water carrier)
b) Material
Rubber rings conforming BIS 5382/1985
c) Testing
Testing of Pipelines with required pressure as per relevant IS
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)
day
6.450
day
16.300
day
3.300
each
40.000
rm
100.000
888
Index-code
S No
1
7
PHE-LJGI-7
ii
iii
Description
Unit
Quantity
2
Lowering and Jointing G.I. pipes and specials / fittings including
excavation of trench of 0.5m width and 0.50 m depth in all soils except
rock requiring blasting and refilling trenches after laying and jointing
pipes and also including cost of jointing materials but excluding the cost
of pipes. Reference to specifications. BIS No.783/85
day
0.060
day
0.160
cum
2.500
10.000
Rate
Rs.
5
Amt
Rs.
6
PHE
Remarks
7
L.S.
day
0.060
day
0.160
cum
2.500
10.000
L.S.
day
0.120
day
0.250
cum
2.500
10.000
L.S.
889
Index-code
S No
Description
Unit
Quantity
iv
day
0.120
day
0.250
cum
2.500
10.000
vi
Rate
Rs.
5
Amt
Rs.
6
PHE
Remarks
7
L.S.
day
0.160
day
0.330
cum
2.500
10.000
L.S.
day
0.160
day
0.330
cum
2.500
10.000
L.S.
890
Index-code
S No
Description
Unit
Quantity
vii
day
0.250
day
0.660
cum
2.500
10.000
Rate
Rs.
5
Amt
Rs.
6
PHE
Remarks
7
L.S.
ix
a) Labour
day
Plumber 2nd class
day
Man mazdoor
cum
E.W.Excavation & refilling 10x0.50x0.50=2.50cum
b) Material
m
G.I. pipes
L.S.
white lead, hemp yarn, oil etc.
c) Machinery
Nil
(d) Total = a+b+c
(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e
(g) Overheads & Contractors Profit
(h) Cost for 100 rmt (f+g)
Rate per rmt = h/100
100mm dia nominal bore
a) Labour
day
Plumber 2nd class
day
Man mazdoor
cum
E.W.Excavation & refilling 10x0.50x0.50=2.50cum
b) Material
m
G.I. pipes
L.S.
white lead, hemp yarn, oil etc.
c) Machinery
Nil
(d) Total = a+b+c
0.250
0.660
2.500
10.000
0.370
0.970
2.500
10.000
day
0.580
day
1.540
cum
2.500
10.000
L.S.
891
Index-code
S No
1
Description
Unit
Quantity
day
0.330
day
0.330
Each
1.000
Each
1.000
Rate
Rs.
5
Amt
Rs.
6
PHE
Remarks
7
PHE-GIDM-8
ii
iii
Sundries
c) Machinery
Nil
(d) Total = a+b+c
(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e
(g) Overheads & Contractors Profit
Rate per 1No (f+g)
50 mm branch from 80 mm nominal dia main
a) Labour
day
Plumber 2nd class
day
Man mazdoor
b) Material
Each
G.I. tee 50mm dia.
Each
G.I. Jam nut 50mm
Sundries
c) Machinery
Nil
(d) Total = a+b+c
(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e
(g) Overheads & Contractors Profit
Rate per 1No (f+g)
100mm branch from 150mm nominal dia main
a) Labour
day
Plumber 2nd class
day
Man mazdoor
b) Material
Each
G.I. tee 150mm dia.
Each
G.I. Jam nut 150mm
0.450
0.450
1.000
1.000
0.450
0.450
1.000
1.000
Sundries
c) Machinery
Nil
(d) Total = a+b+c
(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e
(g) Overheads & Contractors Profit
Rate per 1No (f+g)
892
Index-code
S No
Description
Unit
Quantity
kgs
6.225
kgs
7.990
kgs
10.262
kgs
13.665
kgs
22.200
kgs
28.450
kgs
38.562
kgs
47.237
kgs
60.275
kgs
71.625
PHE-LACP-9
Rate
Rs.
5
Amt
Rs.
6
PHE
Remarks
7
80 mm dia pipe
Weight of 1m length = (6.225+6.225)/2 = 6.225 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
Rate per metre
ii 100 mm dia pipe
Weight of 1m length = (7.8+8.18)/2 = 7.99 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
Rate per metre
iii 125 mm dia pipe
Weight of 1m length = (9.8+10.725)/2 = 10.262 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
Rate per metre
iv 150 mm dia pipe
Weight of 1m length = (12.15+15.18)/2 = 13.665 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
Rate per metre
v 200 mm dia pipe
Weight of 1m length = (19.1+25.3)/2 = 22.2 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
Rate per metre
vi 250 mm dia pipe
Weight of 1m length = (24.9+32)/2 = 28.450 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
Rate per metre
vii 300 mm dia pipe
Weight of 1m length = (32.2+44.925)/2 =38.562 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
Rate per metre
viii 350 mm dia pipe
Weight of 1m length = (13.6+54.875)/2 = 47.237 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
Rate per metre
ix 400 mm dia pipe
Weight of 1m length = (49.125+71.425)/2 =60.275 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
Rate per metre
x 450 mm dia pipe
Weight of 1m length = (59.225+84.025)/2 = 71.625 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
Rate per metre
893
Index-code
S No
Description
Unit
Quantity
kgs
88.725
kgs
125.262
kgs
7.378
kgs
11.587
kgs
15.087
kgs
21.275
kgs
36.425
kgs
46.412
kgs
66.075
kgs
76.412
kgs
104.225
kgs
125.360
Rate
Rs.
5
Amt
Rs.
6
PHE
Remarks
7
xi
80 mm dia pipe
Weight of 1m length = (6.23+8.525)/2 = 7.378 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
Rate per metre
ii 100 mm dia pipe
Weight of 1m length = (10.35+12.825)/2 =11.587 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
Rate per metre
iii 125 mm dia pipe
Weight of 1m length = (13.35+16.825)/2 = 15.087 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
Rate per metre
iv 150 mm dia pipe
Weight of 1m length = (18.9+23.65)/2 = 21.275 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
Rate per metre
v 200 mm dia pipe
Weight of 1m length = (32.1+40.75)/2 = 36.425 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
Rate per metre
vi 250 mm dia pipe
Weight of 1m length = (41.175+51.65)/2 = 46.412 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
Rate per metre
vii 300 mm dia pipe
Weight of 1m length = (58.1+74.05)/2 = 66.075 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
Rate per metre
viii 350 mm dia pipe
Weight of 1m length = (71.275+81.55)/2 = 76.412 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
Rate per metre
ix 400 mm dia pipe
Weight of 1m length = (93.05+115.4)/2 = 104.225 kgs
(a) Labour charges for laying
(b) Overheads & Contractors Profit
Rate per metre
x 450 mm dia pipe
Weight of 1m length = (111.275+139.45)/2 = 125.36 kgs
894
Index-code
S No
Description
Unit
Quantity
Rate
Rs.
5
Amt
Rs.
6
PHE
Remarks
7
xi
PHE-JACP-10
153.800
219.412
(Length = 500 Mts) taking out put / 500 Mts. Unit = 1 Rmt.
Machinery
Hire chargers for Hydralic field test pressure testing including days
transportation of water @ Rs. 1200/- (1000+200) / day
Materials
Pressure guage
Nos
0.05
Mts
Specials
Ls
Dummies
No.
0.1
Lts.
60
0.180
0.420
1.600
40.000
895
Index-code
S No
1
ii
iii
iv
Description
Unit
Quantity
Rate
Rs.
5
Amt
Rs.
6
PHE
Remarks
7
day
Plumber 1st class
day
Plumber 2nd class
day
Man mazdoor
Total
(b) Machinery for Testing of Pipelines with required rm
pressure as per relevant IS Specification including hire
charges of testing equipment, labour and transportation of
water upto 500 M lead Materials needed for testing (as per
Sub Analysis 11 A)
(c) Add for water charges @ 1% on Labour & Testing
Charges
(d) Total = a+b+c
(e) Overheads & Contractors Profit
(f) Cost for 10 joints = d+e
Rate per each joint = f/10
200 mm dia meter pipe
(a) Labour
day
Plumber 1st class
nd
day
Plumber 2 class
day
Man mazdoor
Total
(b) Machinery for Testing of Pipelines with required rm
pressure as per relevant IS Specification including hire
charges of testing equipment, labour and transportation of
water upto 500 M lead Materials needed for testing (as per
Sub Analysis 11 A)
0.300
0.700
2.000
40.000
0.300
0.700
2.000
40.000
0.360
0.840
2.200
40.000
0.360
0.840
2.200
40.000
896
Index-code
S No
1
vi
Description
Unit
Quantity
Rate
Rs.
5
Amt
Rs.
6
PHE
Remarks
7
st
day
Plumber 1 class
nd
day
Plumber 2 class
day
Man mazdoor
Total
(b) Machinery for Testing of Pipelines with required rm
pressure as per relevant IS Specification including hire
charges of testing equipment, labour and transportation of
water upto 500 M lead Materials needed for testing (as per
Sub Analysis 11 A)
(c) Add for water charges @ 1% on Labour & Testing
Charges
(d) Total = a+b+c
(e) Overheads & Contractors Profit
(f) Cost for 10 joints = d+e
Rate per each joint = f/10
vii 300 mm dia meter pipe
(a) Labour
day
Plumber 1st class
day
Plumber 2nd class
day
Man mazdoor
Total
(b) Machinery for Testing of Pipelines with required rm
pressure as per relevant IS Specification including hire
charges of testing equipment, labour and transportation of
water upto 500 M lead Materials needed for testing (as per
Sub Analysis 11 A)
(c) Add for water charges @ 1% on Labour & Testing
Charges
(d) Total = a+b+c
(e) Overheads & Contractors Profit
(f) Cost for 10 joints = d+e
Rate per each joint = f/10
viii 350 mm dia meter pipe
(a) Labour
day
Plumber 1st class
day
Plumber 2nd class
day
Man mazdoor
Total
(b) Machinery for Testing of Pipelines with required rm
pressure as per relevant IS Specification including hire
charges of testing equipment, labour and transportation of
water upto 500 M lead Materials needed for testing (as per
Sub Analysis 11 A)
(c) Add for water charges @ 1% on Labour & Testing
Charges
(d) Total = a+b+c
(e) Overheads & Contractors Profit
(f) Cost for 10 joints = d+e
Rate per each joint = f/10
0.480
1.120
2.600
40.000
0.480
1.120
2.600
40.000
0.600
1.400
3.000
40.000
897
Index-code
S No
1
ix
xi
Description
Unit
Quantity
Rate
Rs.
5
Amt
Rs.
6
PHE
Remarks
7
day
Plumber 1st class
nd
day
Plumber 2 class
day
Man mazdoor
Total
(b) Machinery for Testing of Pipelines with required rm
pressure as per relevant IS Specification including hire
charges of testing equipment and transportation of water
upto 500 M lead Materials needed for testing (as per Sub
Analysis 11 A)
(c) Add for water charges @ 1% on Labour & Testing
Charges
(d) Total = a+b+c
(e) Overheads & Contractors Profit
(f) Cost for 10 joints = d+e
Rate per each joint = f/10
xii 600 mm dia meter pipe
(a) Labour
day
Plumber 1st class
nd
day
Plumber 2 class
day
Man mazdoor
Total
(b) Machinery for Testing of Pipelines with required rm
pressure as per relevant IS Specification including hire
charges of testing equipment and transportation of water
upto 500 M lead Materials needed for testing (as per Sub
Analysis 11 A)
0.600
1.400
3.000
40.000
0.720
1.680
3.400
40.000
0.720
1.680
3.400
40.000
0.840
1.960
3.800
40.000
898
Index-code
S No
1
Description
Unit
Quantity
Rate
Rs.
5
Amt
Rs.
6
PHE
Remarks
7
PHE-LJUP-11
63 mm dia pipe
Weight of 1m length = (0.468+0.666+1.01)/3 =0.715 kgs
(a) Labour charges for laying, jointing & testing
(b) Overheads & Contractors Profit
Rate per metre a+b
75 mm dia pipe
Weight of 1m length = (0.655+0.923+1.439)/3 =1.005 kgs
(a) Labour charges for laying, jointing & testing
(b) Overheads & Contractors Profit
Rate per metre a+b
90 mm dia pipe
Weight of 1m length = (0.924+1.321+2.032)/3 =1.426 kgs
(a) Labour charges for laying, jointing & testing
(b) Overheads & Contractors Profit
Rate per metre a+b
110 mm dia pipe
Weight of 1m length = (1.323+1.902+3.062)/3 =2.096 kgs
(a) Labour charges for laying, jointing & testing
(b) Overheads & Contractors Profit
Rate per metre a+b
125 mm dia pipe
Weight of 1m length = (1.722+2.511+3.929)/3 =2.72 kgs
(a) Labour charges for laying, jointing & testing
(b) Overheads & Contractors Profit
Rate per metre a+b
ii
iii
iv
7.000
2.000
4.000
500.000
Lt
rm
6.300
rm
7.500
rm
9.000
rm
11.000
rm
12.500
899
Index-code
S No
1
Description
Unit
Quantity
rm
14.000
rm
16.000
rm
18.000
rm
20.000
rm
22.500
rm
25.000
rm
28.000
rm
31.500
day
4.000
day
day
1.000
2.000
day
day
day
1.000
2.000
1.000
Rate
Rs.
5
Amt
Rs.
6
PHE
Remarks
7
vi
PHE-LJHE-12
900
Index-code
S No
1
Description
Unit
Quantity
day
1.000
Lt
Lt
Lt
day
4.000
8.000
day
4.000
day
day
1.000
2.000
day
day
day
1.000
2.000
1.000
day
1.000
Lt
Lt
Lt
day
4.000
8.000
day
5.000
day
day
1.000
2.000
day
day
day
1.000
2.000
1.000
day
1.000
Lt
Lt
Lt
day
5.000
8.000
day
6.000
day
day
1.000
2.000
Rate
Rs.
5
Amt
Rs.
6
PHE
Remarks
7
(b) Machinery
Hirecharges of Generator Set & Hydraulic Testing Equipment
(c) Material
Kerosene
Diesel
Water for Testing
Transport
Overheads & Contractors Profit
(d) Total (a+b+c)
Rate per RM =d/480
ii
1.000
75 mm Dia
Taking output : Length - 456 m ; Joints - 38 Nos
(a) Labour
For lowering / sub surface transport
Mazdoor
Jointing
Fitter
Mazdoor
Testing
Fitter
Mazdoor
Supervisor
Total
(b) Machinery
Hire charges of Generator Set & Hydraulic testing equipment
(c) Material
Kerosene
Diesel
Water for Testing
Transport
Overheads & Contractors Profit
(d) Total (a+b+c)
Rate per RM =d/456
iii
90 mm Dia
Taking output : Length - 432 m ; Joints - 36 Nos
(a) Labour
For lowering / sub surface transport
Mazdoor
Jointing
Fitter
Mazdoor
Testing
Fitter
Mazdoor
Supervisor
Total
(b) Machinery
Hire charges of Generator Set & Hydraulic testing equipment
(c) Material
Kerosene
Diesel
Water for Testing
Transport
Overheads & Contractors Profit
(d) Total (a+b+c)
Rate per RM =d/432
iv
1.000
1.000
110 mm Dia
Taking output : Length - 384 m ; Joints - 32 Nos
(a) Labour
For lowering / sub surface transport
Mazdoor
Jointing
Fitter
Mazdoor
901
Index-code
S No
1
Description
Unit
Quantity
day
day
day
1.000
2.000
1.000
day
1.000
Lt
Lt
Lt
day
6.000
8.000
day
7.000
day
day
2.000
3.000
day
day
day
1.000
2.000
1.000
day
1.000
Lt
Lt
Lt
day
7.000
8.000
day
7.000
day
day
2.000
3.000
day
day
day
1.000
2.000
1.000
day
1.000
Lt
Lt
Lt
day
8.000
8.000
Testing
Fitter
Mazdoor
Supervisor
Total
(b) Machinery
Hirecharges of Generator Set & Hydraulic Testing Equipment
(c) Material
Kerosene
Diesel
Water for Testing
Transport
Overheads & Contractors Profit
(d) Total (a+b+c)
Rate per RM =d/384
v
Rate
Rs.
5
Amt
Rs.
6
PHE
Remarks
7
1.000
125 mm Dia
Taking output : Length - 348 m ; Joints - 29 Nos
(a) Labour
For lowering / sub surface transport
Mazdoor
Jointing
Fitter
Mazdoor
Testing
Fitter
Mazdoor
Supervisor
Total
(b) Machinery
Hire charges of Generator Set & Hydraulic testing equipment
(c) Material
Kerosene
Diesel
Water for Testing
Transport
Overheads & Contractors Profit
(d) Total (a+b+c)
Rate per RM =d/348
vi
1.000
140 mm Dia
Taking output : Length - 300 m ; Joints - 25 Nos
(a) Labour
For lowering / sub surface transport
Mazdoor
Jointing
Fitter
Mazdoor
Testing
Fitter
Mazdoor
Supervisor
Total
(b) Machinery
Hire charges of Generator Set & Hydraulic testing equipment
(c) Material
Kerosene
Diesel
Water for Testing
Transport
Overheads & Contractors Profit
(d) Total (a+b+c)
Rate per RM =d/300
1.000
902
Index-code
S No
1
vii
Description
Unit
Quantity
day
7.000
day
day
2.000
4.000
day
day
day
1.000
2.000
1.000
day
1.000
Lt
Lt
Lt
day
9.000
8.000
day
8.000
day
day
2.000
4.000
day
day
day
1.000
2.000
1.000
day
1.000
Lt
Lt
Lt
day
10.000
8.000
day
10.000
day
day
2.000
6.000
day
day
day
1.000
2.000
1.000
day
1.000
Lt
Lt
Lt
day
11.000
8.000
160 mm Dia
Taking output : Length - 303 m ; Joints - 25 Nos
(a) Labour
For lowering / sub surface transport
Mazdoor
Jointing
Fitter
Mazdoor
Testing
Fitter
Mazdoor
Supervisor
Total
(b) Machinery
Hire charges of Generator Set & Hydraulic testing equipment
(c) Material
Kerosene
Diesel
Water for Testing
Transport
Overheads & Contractors Profit
(d) Total (a+b+c)
Rate per RM =d/303
viii 180 mm Dia
Taking output : Length - 240 m ; Joints - 20 Nos
(a) Labour
For lowering / sub surface transport
Mazdoor
Jointing
Fitter
Mazdoor
Testing
Fitter
Mazdoor
Supervisor
Total Labour
(b) Machinery
Hire charges of Generator Set & Hydraulic testing equipment
ix
(c) Material
Kerosene
Diesel
Water for Testing
Transport
Overheads & Contractors Profit
(d) Total (a+b+c)
Rate per RM =d/240
200 mm Dia
Taking output : Length - 240 m ; Joints - 20 Nos
(a) Labour
For lowering / sub surface transport
Mazdoor
Jointing
Fitter
Mazdoor
Testing
Fitter
Mazdoor
Supervisor
Total
(b) Machinery
Hire charges of Generator Set & Hydraulic testing equipment
(c) Material
Kerosene
Diesel
Water for Testing
Transport
Overheads & Contractors Profit
(d) Total (a+b+c)
Rate per RM =d/240
225 mm Dia
Taking output : Length - 216 m ; Joints -18 Nos
(a) Labour
For lowering / sub surface transport
Rate
Rs.
5
Amt
Rs.
6
PHE
Remarks
7
1.000
1.000
1.000
903
Index-code
S No
1
Description
Unit
Quantity
3
day
4
10.000
day
day
2.000
6.000
day
day
day
1.000
2.000
1.000
day
1.000
Lt
Lt
Lt
day
12.000
8.000
day
11.000
day
day
2.000
6.000
day
day
day
1.000
2.000
1.000
day
1.000
Lt
Lt
Lt
day
13.000
8.000
day
12.000
day
day
2.000
6.000
day
day
day
1.000
2.000
1.000
day
1.000
Lt
Lt
Lt
day
14.000
8.000
day
12.000
day
day
2.000
6.000
Mazdoor
Jointing
Fitter
Mazdoor
Testing
Fitter
Mazdoor
Supervisor
Total
(b) Machinery
Hire charges of Generator Set & Hydraulic testing equipment
xi
(c) Material
Kerosene
Diesel
Water for Testing
Transport
Overheads & Contractors Profit
(d) Total (a+b+c)
Rate per RM =d/216
250 mm Dia
Taking output : Length - 216 m ; Joints - 18 Nos
(a) Labour
For lowering / sub surface transport
Mazdoor
Jointing
Fitter
Mazdoor
Testing
Fitter
Mazdoor
Supervisor
Total
(b) Machinery
Hire charges of Generator Set & Hydraulic testing equipment
(c) Material
Kerosene
Diesel
Water for Testing
Transport
Overheads & Contractors Profit
(d) Total (a+b+c)
Rate per RM =d/216
xii 280 mm Dia
Taking output : Length - 192 m ; Joints - 16 Nos
(a) Labour
For lowering / sub surface transport
Mazdoor
Jointing
Fitter
Mazdoor
Testing
Fitter
Mazdoor
Supervisor
Total
(b) Machinery
Hire charges of Generator Set & Hydraulic testing equipment
(c) Material
Kerosene
Diesel
Water for Testing
Transport
Overheads & Contractors Profit
(d) Total (a+b+c)
Rate per RM =d/192
xiii 315 mm Dia
Taking output : Length - 180 m ; Joints - 15 Nos
(a) Labour
For lowering / sub surface transport
Mazdoor
Jointing
Fitter
Mazdoor
Rate
Rs.
5
Amt
Rs.
6
PHE
Remarks
7
1.000
1.000
1.000
904
Index-code
S No
1
Description
Unit
Quantity
day
day
day
1.000
2.000
1.000
day
1.000
Lt
Lt
Lt
day
15.000
8.000
day
14.000
day
day
2.000
8.000
day
day
day
1.000
2.000
1.000
day
1.000
Lt
Lt
Lt
day
16.000
8.000
day
0.600
day
1.400
day
3.000
day
1.000
each/r
m
t/kg
50.000
cum
0.045
kgs
4.500
Testing
Fitter
Mazdoor
Supervisor
Total
(b) Machinery
Hire charges of Generator Set & Hydraulic testing equipment
(c) Material
Kerosene
Diesel
Water for Testing
Transport
Overheads & Contractors Profit
(d) Total (a+b+c)
Rate per RM =d/180
xiv 355 mm Dia
Taking output : Length - 144 m ; Joints - 12 Nos
(a) Labour
For lowering / sub surface transport
Mazdoor
Jointing
Fitter
Mazdoor
Testing
Fitter
Mazdoor
Supervisor
Total
(b) Machinery
Hire charges of Generator Set & Hydraulic testing equipment
(c) Material
Kerosene
Diesel
Water for Testing
Transport
Overheads & Contractors Profit
(d) Total (a+b+c)
Rate per RM =d/144
13
PHE-LJSW-13
Rate
Rs.
5
Amt
Rs.
6
PHE
Remarks
7
1.000
1.000
Lowering and laying in ready made trench true to alignment and gradient,
jointing, and testing of stone ware pipes including cost of jointing material
such as cement mortar (1:1) proportion and hemp yarn but excluding
cost and conveyance of pipe. (Reference to specifications BIS No.
6530/72)
0.065
905
Index-code
S No
1
ii
Description
Unit
Quantity
day
0.900
day
2.100
day
4.000
day
1.000
each
t
50.000
0.097
cum
0.068
kgs
9.000
day
1.050
day
2.450
day
4.500
day
1.250
each
t
50.000
0.130
iv
Amt
Rs.
6
PHE
Remarks
7
iii
Rate
Rs.
5
Mason 1 class
Mason 2nd class
Man mazdoor
Woman mazdoor (Water carrier)
b) Material
150 mm dia SW pipe 60cm long
Cement for 50 joints =0.045 cum
Sand = 0.045 cum
Spun yarn = 0.09x50=4.50
(c) Total = a+b
(d) Add for water charges @ 1% on Labour & Testing
Charges
(e) Total = c+d
(f) Overheads & Contractors Profit
(g) Cost for 30 m (e+f)
Rate per metre = g/30
200 mm dia
(a) Labour
Mason 1st class
Mason 2nd class
Man mazdoor
Woman mazdoor (Water carrier)
b) Material
200 mm dia SW pipe 60cm long
Cement for 50 joints =0.045 cum
Sand = 0.045 cum
Spun yarn = 0.09x50=4.50
(c) Total = a+b
(d) Add for water charges @ 1% on Labour & Testing
Charges
(e) Total = c+d
(f) Overheads & Contractors Profit
(g) Cost for 30 m (e+f)
Rate per metre = g/30
230 mm dia
(a) Labour
Mason 1st class
Mason 2nd class
Man mazdoor
Woman mazdoor (Water carrier)
b) Material
230 mm dia SW pipe 60cm long
Cement for 50 joints =0.045 cum
Sand = 0.045 cum
Spun yarn = 0.09x50=4.50
(c) Total = a+b
(d) Add for water charges @ 1% on Labour & Testing
Charges
(e) Total = c+d
(f) Overheads & Contractors Profit
(g) Cost for 30 m (e+f)
Rate per metre = g/30
cum
0.091
kgs
12.000
day
1.200
day
2.800
day
5.000
day
1.500
each
t
50.000
0.146
cum
0.102
kgs
13.500
906
Index-code
S No
Description
Unit
Quantity
Mason 1 class
nd
Mason 2 class
Man mazdoor
Woman mazdoor (Water carrier)
b) Material
250 mm dia SW pipe 60cm long
Cement for 50 joints =0.045 cum
Sand = 0.045 cum
Spun yarn = 0.09x50=4.50
(c) Total = a+b
(d) Add for water charges @ 1% on Labour & Testing
Charges
(e) Total = c+d
(f) Overheads & Contractors Profit
(g) Cost for 30 m (e+f)
Rate per metre = g/30
300 mm dia
(a) Labour
day
1.350
day
3.150
day
5.500
day
1.500
each
t
50.000
0.162
1
v
Amt
Rs.
6
PHE
Remarks
7
250 mm dia
(a) Labour
st
vi
Rate
Rs.
5
st
Mason 1 class
nd
Mason 2 class
Man mazdoor
Woman mazdoor (Water carrier)
b) Material
300 mm dia SW pipe 60cm long
Cement for 50 joints =0.045 cum
Sand = 0.045 cum
Spun yarn = 0.09x50=4.50
(c) Total = a+b
(d) Add for water charges @ 1% on Labour & Testing
Charges
(e) Total = c+d
(f) Overheads & Contractors Profit
(g) Cost for 30 m (e+f)
Rate per metre = g/30
vii 350 mm dia
(a) Labour
Mason 1st class
Mason 2nd class
Man mazdoor
Woman mazdoor (Water carrier)
b) Material
350 mm dia SW pipe 60cm long
Cement for 50 joints =0.045 cum
Sand = 0.045 cum
Spun yarn = 0.09x50=4.50
(c) Total = a+b
(d) Add for water charges @ 1% on Labour & Testing
Charges
(e) Total = c+d
(f) Overheads & Contractors Profit
(g) Cost for 30 m (e+f)
Rate per metre = g/30
cum
0.113
kgs
15.000
day
1.500
day
3.500
day
6.000
day
1.500
each
t
50.000
0.194
cum
0.136
kgs
18.000
day
1.650
day
3.850
day
7.000
day
1.750
each
t
50.000
0.225
cum
0.159
kgs
21.000
907
Index-code
S No
Description
Unit
Quantity
Mason 1 class
nd
Mason 2 class
Man mazdoor
Woman mazdoor (Water carrier)
b) Material
400 mm dia SW pipe 60cm long
Cement for 50 joints =0.045 cum
Sand = 0.045 cum
Spun yarn = 0.09x50=4.50
(c) Total = a+b
(d) Add for water charges @ 1% on Labour & Testing
Charges
(e) Total = c+d
(f) Overheads & Contractors Profit
(g) Cost for 30 m (e+f)
Rate per metre = g/30
450 mm dia
(a) Labour
day
1.800
day
4.200
day
8.000
day
1.750
each
t
50.000
0.256
Rate
Rs.
5
Amt
Rs.
6
PHE
Remarks
7
(a) Labour
st
ix
st
Mason 1 class
Mason 2nd class
Man mazdoor
Woman mazdoor (Water carrier)
b) Material
450 mm dia SW pipe 60cm long
Cement for 50 joints =0.045 cum
Sand = 0.045 cum
Spun yarn = 0.09x50=4.50
(c) Total = a+b
(d) Add for water charges @ 1% on Labour & Testing
Charges
(e) Total = c+d
(f) Overheads & Contractors Profit
(g) Cost for 30 m (e+f)
Rate per metre = g/30
PHE-CISP14(sub_analys
is)
14
15
24.000
day
day
day
day
2.100
4.900
10.000
2.000
each
t
50.000
0.293
cum
0.204
kgs
27.000
day
day
0.465
1.094
day
2.480
kgs
35.470
Lowering, keeping in position and fixing C.I. sluice valves (with cap / with
hand wheel & reflex valves) excluding cost of bolts, nuts, rubber
insertion, sluice valve and tail pieces
ii
0.181
kgs
Sub Analysis :
Labour charges for laying in position S&S or flanged C.I.
specials such as tees, bends, collars tapers and caps etc
10 No. Tees of 200x150mm dia
Weight = 10x70kgs = 700 kgs
(a) Labour
Plumber 1st class
Plumber 2nd class
Man mazdoor
Cost for 700 kgs
Cost for 1kg
PHE-CISV-15
cum
47.100
908
Index-code
S No
1
Description
Unit
Quantity
kgs
61.770
kgs
79.830
kgs
131.700
kgs
187.160
kgs
266.460
kgs
450.000
kgs
552.500
kgs
722.500
kgs
837.500
kgs
1422.500
Rate
Rs.
5
Amt
Rs.
6
PHE
Remarks
7
iii
909
Index-code
S No
Description
Unit
Quantity
16
A
Providing and fixing double acting air valves including boring the
main threading the bore and fixing nipple etc.,excluding the cost
of rubber insertions, bolts & nuts, air valve & flanged tail pieces
complete
kgs
20.000
day
0.180
PHE-DAAV-16
Rate
Rs.
5
Amt
Rs.
6
PHE
Remarks
7
50 mm dia meter
(a) Labour
Labour for laying air valve
nd
Plumber 2 class
day
Man mazdoor
Overheads & Contractors Profit
Rate per each valve
16 Labour charges for fixing Air valves including boring the mains
B and threading the bore fixing nipple etc., complete.
i
Unit each
40 mm dia
(a) Labour
Lowering charges for air valve
Boring main & threding etc
0.180
kgs
27.000
day
0.140
day
0.140
kgs
20.000
day
0.110
day
0.110
day
Plumber 1st class
nd
day
Plumber 2 class
day
Man mazdoor
Overheads & Contractors Profit
Rate per each fire hydrant
Note : For other sizes proportionately allow the Data.
18 Dismantling of spindle fire hydrant including stacking of useful
materials within 50m lead
Details of cost for 10 Nos
65 mm dia
(a) Labour
Fitter 1st class
day
day
Fitter 2nd class
day
Man mazdoor
Overheads & Contractors Profit
Rate per each
0.750
nd
Plumber 2 class
Man mazdoor
Overheads & Contractors Profit
Rate per each valve
ii
25 mm dia
(a) Labour
Lowering charges for air valve
Boring main & threding etc
Plumber 2nd class
Man mazdoor
Overheads & Contractors Profit
Rate per each valve
17
PHE-SFHD-17
PHE-DSFH-18
65 mm dia
(a) Labour
1.750
4.000
0.750
1.750
4.000
910
Index-code
S No
1
19
PHE-URCI-19
i
ii
iii
iv
Description
Unit
Quantity
2
Uprooting of C.I. pipes by melting lead, loosening the joints, separating
the pipes, hoisting and keeping within a lead of 10 metres but excluding
earth work excavation and refilling
day
0.500
day
4.000
q
litre
0.373
0.379
day
0.630
day
4.500
0.466
litre
0.379
day
0.760
day
5.000
0.559
litre
0.562
day
0.830
day
5.500
0.663
litre
0.568
day
1.100
day
6.500
0.840
litre
0.757
Rate
Rs.
5
Amt
Rs.
6
PHE
Remarks
7
911
Index-code
S No
1
vi
Description
Unit
Quantity
day
1.300
day
7.500
nd
nd
Amt
Rs.
6
PHE
Remarks
7
ix
Rate
Rs.
5
1.026
litre
1.137
day
1.500
day
8.500
1.120
litre
1.515
day
1.750
day
9.500
1.231
litre
1.515
day
2.000
day
10.500
1.306
litre
1.894
day
2.250
day
11.500
1.400
litre
2.273
912
Index-code
S No
1
xi
Description
Unit
Quantity
nd
PHE-URRC-20
iii
iv
day
2.500
day
12.500
1.492
litre
2.652
day
3.000
day
14.500
1.580
litre
3.410
Remarks
7
Fitter 2 class
Man mazdoor
Women mazdoor
(b) Overheads & Contractors Profit
(c) Cost for 10 Rmt (a+b)
Rate per each Rmt = c/10
150mm dia
(a) Labour
day
0.100
day
0.400
day
0.450
day
0.100
day
0.490
day
0.560
day
0.100
day
0.490
day
0.670
day
0.100
day
0.490
day
0.790
ii
PHE
20
Amt
Rs.
6
xii
Rate
Rs.
5
913
Index-code
S No
Description
Unit
Quantity
21
day
0.490
day
0.360
day
0.490
day
0.450
day
0.490
day
0.510
day
0.490
day
0.540
day
0.490
day
0.570
day
0.490
day
0.630
day
day
0.490
0.690
PHE-URSW-21
Rate
Rs.
5
Amt
Rs.
6
PHE
Remarks
7
914
Index-code
S No
1
Description
Unit
Quantity
day
0.660
day
0.750
day
0.660
day
0.810
day
0.130
day
0.260
day
day
0.060
day
day
0.080
day
day
0.110
day
day
0.150
Rate
Rs.
5
Amt
Rs.
6
PHE
Remarks
7
PHE-URGI-22
(a) Labour
Man mazdoor
Women mazdoor
(b) Overheads & Contractors Profit
(c) Cost for 10 m (a+b)
Rate per each m =c/10
ix 450mm dia metre
(a) Labour
Man mazdoor
Women mazdoor
(b) Overheads & Contractors Profit
(c) Cost for 10 m (a+b)
Rate per each m =c/10
22 Removing old G.I.pipes and specials / fittings and cleaning,
scraping the pipes, hoisting and keeping with in 50m lead but
excluding earth work excavation of trenches and refilling
Details of cost for 10 m
15 to 40mm dia
(a) Labour
Plumber
(b) Overheads & Contractors Profit
(c) Cost for 10 m (a+b)
Rate per each m =c/10
ii Above 40mm dia
(a) Labour
Plumber
(b) Overheads & Contractors Profit
(c) Cost for 10 m (a+b)
Rate per each m =c/10
23 Cutting C.I. / D.I. pipes without water in mains
Details of cost for one cutting
i 80 mm dia
(a) Labour
Asst. Fitter / Plumber 2nd class
Man mazdoor
(b) Overheads & Contractors Profit
Rate per each m
ii 100 mm dia
(a) Labour
Asst. Fitter / Plumber 2nd class
Man mazdoor
(b) Overheads & Contractors Profit
Rate per each m
iii 125 mm dia
(a) Labour
Asst. Fitter / Plumber 2nd class
Man mazdoor
(b) Overheads & Contractors Profit
Rate per each m
iv 150 mm dia
(a) Labour
Asst. Fitter / Plumber 2nd class
Man mazdoor
(b) Overheads & Contractors Profit
Rate per each m
i
PHE-CCIP-23
0.060
0.080
0.110
0.150
915
Index-code
S No
1
Description
Unit
Quantity
day
day
0.200
day
day
0.250
day
day
0.300
day
day
0.350
day
day
0.400
day
day
0.450
day
day
0.500
day
day
0.600
Rate
Rs.
5
Amt
Rs.
6
PHE
Remarks
7
200 mm dia
(a) Labour
Asst. Fitter / Plumber 2nd class
Man mazdoor
(b) Overheads & Contractors Profit
Rate per each m
vi 250 mm dia
(a) Labour
Asst. Fitter / Plumber 2nd class
Man mazdoor
(b) Overheads & Contractors Profit
Rate per each m
vii 300 mm dia
(a) Labour
Asst. Fitter / Plumber 2nd class
Man mazdoor
(b) Overheads & Contractors Profit
Rate per each m
viii 350 mm dia
(a) Labour
Asst. Fitter / Plumber 2nd class
Man mazdoor
(b) Overheads & Contractors Profit
Rate per each m
ix 400 mm dia
(a) Labour
Asst. Fitter / Plumber 2nd class
Man mazdoor
(b) Overheads & Contractors Profit
Rate per each m
x 450 mm dia
(a) Labour
Asst. Fitter / Plumber 2nd class
Man mazdoor
(b) Overheads & Contractors Profit
Rate per each m
xi 500 mm dia
(a) Labour
Asst. Fitter / Plumber 2nd class
Man mazdoor
(b) Overheads & Contractors Profit
Rate per each m
xii 600 mm dia
(a) Labour
Asst. Fitter / Plumber 2nd class
Man mazdoor
(b) Overheads & Contractors Profit
Rate per each m
PHE-DTCI-24
24
ii
iii
Drilling and tapping C.I./D.I. main and fixing brass screw down
ferrule and C.I.mouth cover.(Labour charges only)
Details of cost for one no
15 mm dia
(a) Labour
Plumber
day
(b) Overheads & Contractors Profit
Rate per each m
20 mm dia
(a) Labour
Plumber
day
(b) Overheads & Contractors Profit
Rate per each m
25 mm dia
(a) Labour
Plumber
day
(b) Overheads & Contractors Profit
0.200
0.250
0.300
0.350
0.400
0.450
0.500
0.600
0.130
0.150
0.170
916
Index-code
S No
1
PHE-SHST-25
Description
Unit
Quantity
day
0.570
1.100
Rate
Rs.
5
Amt
Rs.
6
PHE
Remarks
7
Carpenter 2 class
Man mazdoor
b) Material
Polling boards and ballies
Requirement for 45 sqm :
Polling Boards of 250 mm x 35 mm (40 x 1.5 x 0.25 x 0.038)
Ballies 125 mm dia 1.5 mts long (60 x p x (0.125)2 / 4 x 1.5
day
sqm
cum
cum
c) Machinery
Nil
Overheads & Contractors Profit
(d) Cost for 45 sqm (a+b+c)
Rate per each sqm = d/45
(B) Double staging from 8 to 14 ( 2.5 to 4.5 Metre)
Depth not exceeding 1.5 M
Details of cost for an area 30 M long and 1.5 M deep.
Area = 30 x 1.5 = 45 Sqm
(a) Labour
Carpenter 2nd class
Man mazdoor
b) Material
Polling boards and ballies
Requirement for 45 sqm :
Polling Boards of 250 mm x 35 mm (40 x 1.5 x 0.25 x 0.038 =
0.57 cum)
Ballies 125 mm dia 1.5 mts long (60 x p x (0.125)2 / 4 x 1.5 =
1.1 cum
Deduct Credit for materials after use @ 80% of the cost of
materials = 0.8 x X
c) Machinery
Nil
Overheads & Contractors Profit
(d) Cost for 45 sqm (a+b+c)
Rate per each sqm = d/45
(C) Triple staging beyond 14 for every 2 meter (beyond 4.5 M)
Depth not exceeding 1.5 M.
Note : Add for every 2 Mts (difference of single and double
staging) for staging beyond 4.5 mts.
26 Barricading, hoarding, lighting and watching etc., for water
supply and sewerage works for trenches of depths upto 6-0 (2
PHE-BHLW-26
Meter) below G.L
Taking output 3 Rmt
Material
Bamboos of 1 dia 2.5 M long (5 ft c/c = 3 x 2.5)
Baboom of 1 dia 3.66 M long (5 ft c/c = 3x 3.66)
Cost of Bamboos
(a) Usage of Material 5 times. Thus Cost of Material taken as
20%
day
day
0.500
1.320
sqm
cum
0.110
cum
0.220
rmt
7.50
10.98
rmt
917
Index-code
S No
1
Description
Unit
Quantity
day
0.500
day
0.750
day
0.250
day
2.000
day
2.000
each
m
1.000
0.500
cum
0.920
cum
0.100
(b) Labour
Man mazdoor
(c) Sundries for Coir rope, nails, @ 1%
(d) Sundries for lighting and watching etc at 1%
Overheads & Contractors Profit
Cost for 3rmt (a+b+c+d)
Rate per each rmt = (a+b+c+d)/3
27
PHE-RCVS-27
Rate
Rs.
5
Amt
Rs.
6
PHE
Remarks
7
Providing RCC spun vent shaft with cowl 140 mm and 200 mm internal
and external dia respectively at top, 300 and 450 mm internal and
external dia respectively at bottom and 9.10m overall length. Bottom 1.25
m below ground level fixed in a pit 90cmx90cm x150 cm with cement
concrete 1:4:8, 25cm in bed and minimum 20cm all-round with top 15cm
in cement concrete 1:2:4. Junction of vent shaft and concrete grouted
with cement mortar 1:1 including making connection with sewer manhole
with 150 mm dia metre cement concrete pipe of required length complete
as per standard design
Mason 1 class
nd
Mason 2 class
Man mazdoor (bhandani)
Man mazdoor (beldar)
b) Material
RCC went shaft with cowl
RCC pipe 150 mm dia 0.50 m (NP-2 class)
Cement Concrete 1:4:8(plain)
0.90 x 0.90 x 135 = 1.094 cum
Less for shaft 22/7 x 4 x 0.452 x 1.1= 0.175cum = 0.919 cum
Cement Concrete 1:2:4 (plain)
0.90 x 0.90 x 0.15 = 0.122 cum
Less for shaft 22/7x4 x 0.452 x 0.15= 0.024cum = 0.098 cum
(c) Total (a+b)
(d) Add for water charges @ 1% on Labour & Testing
Charges on Labour Charges
(e) Total = c+d
(f) Overheads & Contractors Profit
(g) Cost for 1 No = e+f
Well Sinking
28 Well sinking in sandy and other loose soils under water either by
manual labour, divers or dredgers weighting the top of staining
to assist sinking etc., including dewatering and other incidental
PHE-WSNP-28
charges such as hire charges for mechanical equipment etc.,
complete upto 4.0 m dia (For non perennial rivers)
i
ii
iii
1%
day
105.000
day
70.000
35.000
day
hour
hour
hour
L
day
day
16.000
56.000
56.000
70.000
56.000
35.000
918
Index-code
S No
1
PHE-WSOW29
Description
Unit
3
hour
ii
hour
hour
L
day
day
hour
hour
hour
L
day
day
hour
Quantity
4
day
178.000
11.000
hour
L
64.000
40.000
168.000
hour
Remarks
56.000
56.000
56.000
140.000
day
day
PHE
56.000
35.000
hour
Amt
Rs.
6
56.000
56.000
56.000
105.000
64.000
64.000
64.000
140.000
hour
Rate
Rs.
5
88.000
88.000
440.000
919
Index-code
S No
1
Description
Unit
Quantity
day
157.000
48.000
12.000
Rate
Rs.
5
Amt
Rs.
6
PHE
Remarks
7
iii
day
day
hour
hour
hour
L
day
day
day
hour
hour
hour
L
day
day
day
hour
hour
hour
L
day
day
day
hour
hour
hour
L
day
day
day
hour
hour
96.000
102.000
96.000
1056.000
195.000
120.000
15.000
120.000
124.000
120.000
1334.000
272.000
204.000
17.000
124.000
124.000
136.000
1344.000
360.000
288.000
24.000
192.000
198.000
160.000
2148.000
32.000
64.000
4.00
32.00
32.00
920
Index-code
S No
1
ii
iii
iv
Description
Unit
Quantity
Rate
Rs.
5
Amt
Rs.
6
PHE
Remarks
7
L
Diesel
120.00
Overheads & Contractors Profit
c) Total
Rate per Rm = c/2
2.0 to 4.0 m below G.L. :
(a) Labour
day
Man mazdoor
40.000
day
Well sinkers
80.000
b) Machinery
day
Hire charges of set of Helmets & Air circulating pipes / valves
5.00
hour
Hire charges for crane
40.00
hour
Hire charges for compressors
40.00
L
Diesel
150.00
Overheads & Contractors Profit
c) Total
Rate per Rm = c/2
4.0 to 6.0 m below G.L. :
(a) Labour
day
Man mazdoor
48.000
day
Well sinkers
96.000
b) Machinery
day
Hire charges of set of Helmets & Air circulating pipes / valves
6.00
hour
Hire charges for crane
48.00
hour
Hire charges for compressors
48.00
L
Diesel
180.00
Overheads & Contractors Profit
c) Total
Rate per Rm = c/2
6.0 to 8.0 m below G.L. :
(a) Labour
day
Man mazdoor
56.000
day
Well sinkers
112.000
b) Machinery
day
Hire charges of set of Helmets & Air circulating pipes / valves
7.00
hour
Hire charges for crane
56.00
hour
Hire charges for compressors
56.00
L
Diesel
210.00
Overheads & Contractors Profit
c) Total
Rate per Rm = c/2
8.0 to 10.0 m below G.L. :
(a) Labour
day
Man mazdoor
64.000
day
Well sinkers
128.000
b) Machinery
day
Hire charges of set of Helmets & Air circulating pipes / valves
8.00
hour
Hire charges for crane
64.00
hour
Hire charges for compressors
64.00
L
Diesel
240.00
Overheads & Contractors Profit
c) Total
Rate per Rm = c/2
Note : This data shall be adopted for well sinking in perennial rivers.
For other rivers, data available for 4.0 m dia infiltration well may be
adopted for guidance
921
Index-code
PHE-CCCP-31
S No
Description
Unit
Quantity
31
day
42.000
PHE-CSHR-32
PHE-EXRW-33
32
cum
2.450
each
105.000
cum
2.450
18900.000
Rate
Rs.
5
Amt
Rs.
6
PHE
Remarks
7
water
60.000
342.000
3.000
10.000
Unit = cum
Taking output = 1 cum
a) Labour
Mate
Mazdoor (Unskilled)
Chiseller (Hammer Man)
Blacksmith
b) Machinery
Tipper 5.5 cum capacity, 1 trip per hour
Credit for excavated rock found suitable for use @ 50 per cent
of excavated quantity
Sundries on Labour
c&d) Overheads & Contractors Profit
Rate per cum = (a+b+c+d)
day
day
1.100
day
1.500
day
0.060
hour
0.180
cum
0.500
922
Index-code
S No
1
Description
Unit
Quantity
Rate
Rs.
5
Amt
Rs.
6
PHE
Remarks
7
Unit = cum
Taking output = 1 cum
a) Labour
day
Mate
day
Mazdoor (Unskilled)
b) Machinery
Hydraulic excavator 0.9 cum with rock breaker attachment @ 6 hour
cum per hour
hour
Tipper 5.5 cum capacity tipper, 1 trip per hour
Credit for excavated rock found suitable for use @ 50 per cent of cum
excavated quantity
0.289
0.167
0.180
0.500
Sundries on Labour
c&d) Overheads & Contractors Profit
Rate per cum = (a+b+c+d)
Note : 1. The quality and availability of rock shall be checked before affording
credit.
2. In case some rock is issued to the contractor at site, the item of carriage shall
be restricted/reduced to that extent.
3. Being small quantity, manual loading will be economical in this case and has
been provided accordingly.
34
PHE-LUSS-34
i
ii
iii
iv
day
6.000
1%
day
6.000
1%
day
6.000
1%
day
6.000
1%
923
Index-code
S No
1
Description
Unit
Quantity
day
6.000
Rate
Rs.
5
Amt
Rs.
6
PHE
Remarks
7
35
PHE-LUMS-35
PHE-LUGS-36
1%
day
6.000
1%
day
0.700
1%
day
0.700
1%
PHE-LUBS-37
day
0.710
1%
0.790
1%
0.714
1%
924
Index-code
S No
Description
Unit
Quantity
Rate
Rs.
5
Amt
Rs.
6
PHE
Remarks
7
ii
PHE-CSRC-38
0.780
1%
1.197
0.095
ii
cum
81.90 x x 0.125 / 4 =1.005 Cum
Assuming that timber shall become unserviceable after being
used for 5 times
Cost for 5 times
Rate per 1 time
b) Labour
Labour charges for assembling, erection, dismantling and
cleaning
day
Carpenter 2nd class
1.005
day
6.000
cum
1.204
cum
0.313
Man Mazdoor
Sundries for nails etc
Overheads & Contractors Profit
c) Cost for 30 Sqm
Rate per sqm =c/30
Side walls curved surfaces
7.500
Surface area:
Outside x 4.40 x 1.00 = 13.83 Sqm
Inside area = x 4 x 1 = 12.57 Sqm
= 26.40 Sqm
a) Materials
i) Planks 33 mm
26.40 x 0.038
=
1.003 cum
Extra & Wastage @ 20%
=
0.201 cum
=
1.204 Cum
ii) Hattens 75 x 38 mm
Inside 2 x 25 x 0.50 x 0.075 x 0.075 = 0.1406
Outside 2 x 28 x 0.50 x 0.075 x 0.175 = 0.1575
= 0.2981
Add 5% wastage
= 0.0149
= 0.3130 cum
925
Index-code
S No
Description
Unit
Quantity
cum
0.680
day
Mason 2nd class
day
Man Mazdoor
Total
(b) Overheads & Contractors Profit
c) Cost for 278.46 Sqm
Rate per sqm =c/278.46
Cost for 50 Kg
40 Labour charges for fixing ventilating shafts in sewerage
scheme complete with all accessories
Unit Each
a) Labour
1.000
Rate
Rs.
5
Amt
Rs.
6
PHE
Remarks
7
PHE-HSSG-39
PHE-LCVS-40
2.750
day
0.150
day
0.350
day
0.600
day
2.000
926
Part 1
For IRRIGATION & CAD WORKS
and
LEADS & LIFTS (Common to all Departments)
dt:30.05.2014
A.P.Revised Standard Data for I&CAD works(Part-I) for the year 2014-15 approvedPrinting & communication of Standard Data Reg.,
1)G.O.Ms.No.49,I&CAD (PW:Reforms)Dept., dt:2.3.2009
2)Minutes of BOCEs meeting for Schedule of Rates held on 24.05.2014.
3) SoR Procs.No.ENC/IW/P&M/EE.3/DEE-10/AE/13305/Vol.37 dt:30.05.2014
*****
The Board of Chief Engineers meeting for finalization of Schedule of Rates (SoR) for
I&CAD(Part-I),Road & Bridges(Part-II) and Public Health Items(Part-IV) was held on 24.05.2014 @
3.30 PM and approved the SoR. Based on the approval of BoCEs, the SoR for I&CAD Dept(basic input
required for arriving unit item rate as per A.P. Revised Standard data) ,R&B and Public Health
Department items were communicated vide this office proceedings 3rd cited.
Page No.
i-xiii
IRRIGATION
Abstract of Items - Irrigation
1-45
46-47
IRR-DAW
IRR-DAW-1
48-59
IRR-DAW-2
IRR-DAW-3
IRR-DAW-4
IRR-DAW-5
IRR-DAW-6
59-78
78-84
84-87
87-95
96-104
IRR-TAW
IRR-TAW-1
IRR-TAW-2
IRR-TAW-3
IRR-TAW-4
IRR-TAW-5
IRR-TAW-6
105-113
113-116
116-122
122-123
123-128
128-130
IRR-CAW
IRR-CAW-1
IRR-CAW-2
IRR-CAW-3
IRR-CAW-4
IRR-CAW-5
IRR-CAW-6
IRR-CAW-7
IRR-CAW-8
131-145
145-152
152-157
157-162
162-170
170-172
172-216
216-228
IRR-CCDW
IRR-CCDW-1
IRR-CCDW-2
IRR-CCDW-3
IRR-CCDW-4
IRR-CCDW-5
IRR-CCDW-6
IRR-CCDW-7
230-236
236-262
262-264
264-271
271-275
275-281
281-284
IRR_GAW
IRR_GAW-1
IRR_GAW-2
IRR_GAW-3
IRR_GAW-4
285
285-291
291-310
310-315
315-317
IRR-PMW
IRR-PMW-1
IRR-PMW-2
IRR-PMW-3
318-328
328-338
338-354
COM-LDLFT
COM-LDLFT-1
A. Manual Works
B. Lead/Lift/Loading & Unloading Charges
(to follow MORTH standardsfor the items not covered ,as
applicable to roads and bridge works)
Notes on Lead and Lift
(Lead) Conveyance Charges for materials by head load
( Lead) Conveyance charges for machinery per kilometer for
transporting materials by tippers and trucks, excluding
loading, unloading and hire charges of machinery.
COM-LDLFT-2
COM-LDLFT-3
COM-LDLFT-4
COM-LDLFT-5
COM-LDLFT-6
COM-DTL-LDLFT-1
COM-DTL-LDLFT-4
COM-DTL-LDLFT-5
COM-DTL-LDLFT-6
355-355
356-356
356-356
356-356
356-356
LOADING AND UNLOADING CHARGES BY MANUAL
MEANS (Idle hire charges of trucks are not added)
LOADING AND UNLOADING CHARGES BY MANUAL
MEANS (including idle hire charges of trucks )
LOADING AND UNLOADING CHARGES BY MECHANICAL
MEANS (including idle hire charges of trucks )
LIFT CHARGES FOR MATERIALS BY HEAD LOAD
(Lead) Conveyance Charges for materials by head load
( Lead) Conveyance charges for machinery per kilometer for
transporting materials by tippers and trucks, excluding
loading, unloading and hire charges of machinery.
COM-DTL-LDLFT-2
COM-DTL-LDLFT-3
Page No.
356-357
357-357
357-357
357-357
358-359
359-365
LOADING AND UNLOADING CHARGES BY MANUAL
MEANS (idle hire charges of trucks are not added)
LOADING AND UNLOADING CHARGES BY MANUAL
MEANS (including idle hire charges of trucks )
LOADING AND UNLOADING CHARGES BY MECHANICAL
MEANS (including idle hire charges of trucks )
LIFT CHARGES FOR MATERIALS BY HEAD LOAD
Hire Charges
365-366
366-367
367-368
368-369
370-371
The AP Revised Standard data for various construction items has come into
existence as per the Government orders G.O.Ms.No.49, I & CAD (PW:
Reforms) Dept., dt:.2-3-2009.
1.
with
has
(b) The second step is to work out the details of inputs. This enables to
generate the unit work item rates, by incorporating the use rates of
machinery, materials, labour charges and other supplementary parameters.
(c) The third step is to develop software tool to generate unit rate using
the software (completed for irrigation works by the SPI Unit of Irrigation)
3. The Detailed draft data was communicated to all the HODs and
through many seminars and discussions and incorporated the
features. The Board of chief engineers in their meetings have
interacted
relevant
recommended
for acceptance to the data formulated and schedule of rates. It was proposed
to examine the recommendations on important parameters,
to refer to high
level committee, for their specific recommendations for adoption, as they are
common to all departments.
The committee made in depth study on the methodology and systems
followed by the reputed National organizations and other States and made
detailed
ii
GUIDELINES
1)
The Revised Standard Data is formulated under four Parts, which are
applicable to all the Engineering Departments and other Organisations.
PART -1:
Irrigation& CAD (Dam and Allied Works, Canals and Allied Works,
Canal C.D. Works, Tunnels and Allied Works, Preliminary and
Maintenance Works, Hydraulic Gates and allied works and Leads and
Lifts applicable to all Departments
needs of work-force, stray rains etc. Therefore, it is the general practice to consider
50 minutes as the actual working time per hour for working out the hourly / daily
out-put of machinery / work-force. CWC / BIS guide-lines stipulate the actual
working hours for the purpose of equipment planning and utilisation. The daily output is computed duly considering the actual available working time and feed back
from the field.
For gate and hoist works, it is the general practice to specify the quantity
of work in terms of number of sets of embedded parts / gates. The
requirement of machinery and work-force for cutting, bending,
fabrication, erection, painting etc., is assessed to commensurate with the
task involved.
The data for gates and E.M. Parts is arrived per Ton quantity.
The data for Hoists and Gantry Cranes is worked out on the basis of
capacity in tonnage
4) The lead and lift charges provided in PART-I (B) are generally applicable
and common to all Departments. Any item is not covered in this part, the
rates as provided in the data of the relevant works may be adopted in
preparation of estimates.
5) The basic material inputs needed for all works are listed and incorporated in
the data. The requirements are analyzed and the specifications adopted shall
confirm to Standards published by the BIS.
For sand, gravel , murum, stones , course aggregates etc, the rates are
to be fixed for delivery at Quarry, adding loading charges by machinery /
manual means and idle hire charges of machinery (as per table under
chapter conveyance or lead and lift charges), as applicable.
iv
For steel, Cement, AC sheets, GI sheets, Hume pipes, wood and stone
slabs, the rates are to be taken prevailing at major commercial centre
near project area. The lead charges, as applicable are to be added in
preparing estimates.
The specifications of the aggregates for sizes and gradation and its
adoption shall be as per IS 383.
However, If more than one area allowances, such as those for (1)
Municipalities (2) Agency / Tribal areas (3) Industrial areas are applicable
for a particular situation, only the maximum out of the allowable
percentages is to be allowed.
based on the
For the other machinery not covered by the list, the R&B and other users
may adopt hire charges as recommended by the MORTH.
8) Lead Charges
The basic work item rates provided in the Standard Data & Schedule of
rates include 50 m or 1 km as initial lead and no lead charges shall be
allowed where the source of material is within the initial lead specified in
item rate. Additional lead charges shall be allowed for the lead exceeding
initial lead specified in the item rate. The Guidelines may be followed
regarding adding Lead charges as given against each chapter.
The lead charges per unit quantity for conveyance of the materials are
worked out, and included in the schedule of rates in increment of 50 m
for head load and in increment of 1 km for mechanical mode.
The rates for lead charges by head load up to 150 meters and by
machinery up to 5 km, shall be cumulative and inclusive of lead charges
for preceding lead. For lead beyond 5 km, the lead charges shall be
worked out on per km basis.
wherever
applicable.
vi
worked out,
The data and rates for lift charges is cumulative and are inclusive of rates
for preceding lifts also.
reinforcement rods above 36mm dia. and @ 5% for rods below 36mm
dia. Including overlaps, if they are not welded.
If welding is adopted for the reinforcement rods even for below 36mm
dia, 2.5% of wastage is only recommended.
12) Provision for rate for water:The Committee has recommended not to consider the water charges in
the Irrigation Project works. But, it may be considered in specific cases as per
the site conditions.
13)
In respect of RCC works the rate for cement concrete for 1 cum
is
worked separately for all grades based on Indian Standards. The rate for ton is
vii
The provision for VAT at 5% or as fixed by the Government from time to time
should be made separately in Part-B of the estimate. In the agreements it
should be mentioned that it will be reimbursed as per actual. The provisions
allowed in G.O.Ms.No.94, I&CAD, dt:01.07.03, need not be added separately
for the items covered in the contractor overhead charges.
The provision for labour Cess at 1% or as fixed by the Government from time to
time should be made separately in Part-B of the estimate.
viii
Site accommodation, setting up plant, access road, water supply, electricity and
general site arrangements.
Expenditure on:
site supervision
Laboratory equipment and quality control including field and laboratory testing.
Minor T & P and survey instruments and setting outworks, including verification
of line, dimensions, trial pits and bore holes, where required.
Sundries
Financing Expenditure
ix
20) For each chapter separate additional details are incorporated for clarity.
view
2.
The common data items like, lead, lift, conveyance and manual
excavation (without involving contracting agencies) is applicable
to all Departments (volume-1).
4.
Irrigation data, the MORTH data may be taken with the approval
of Board of Chief Engineers.
5. For
Drinking
water
Supply
works(PART-IV),
the
data
means of
xi
a) The Board Of Chief Engineers under the chairman ship of Engineer-inchief,(administration) I&CAD Department is the competent authority to
finalise and recommend the Schedule of Rates applicable for all engineering
Departments. The board has to assess and incorporate only the three basic
inputs required to generate unit work item rates as below.
Materials rates:
The basic input material rates common to all departmental works are
listed out and incorporated (in the chapter Basic inputs) The
material
all
xii
are
charges. For
stone slabs,
the rates prevailing at major commercial centre near project area has to be
adopted.
Use rate of machinery:
The third parameter for incorporation in the Basic Inputs, is the use rate
of machinery. To arrive at the use rate of machinery, the inputs to be
incorporated are
The
to be
used in the
The prevailing fuel charges of petrol and diesel are ascertained and
average rate adopted
For the other machinery not covered by the list, the R&B and other
users may adopt hire charges as recommended by the MORTH
xiii
Unit
Rate
cum
120.70
IRR-DAW-1
IRR-DAW-1-1
Item description
Excavation for foundation in all kinds of soil including boulders upto 0.30 m
diameter for dam, spillway, intake structure and other appurtenant works and
placing the excavated soil neatly in dump area or disposing off the same as
directed etc., complete with initial lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)
IRR-DAW-1-2
IRR-DAW-1-3
IRR-DAW-1-3-A
New Item 201415-1
cum
cum
22.50
159.90
cum
cum
29.20
240.50
cum
cum
52.00
360.50
61.20
cum
IRR-DAW-1-4(a)
IRR-DAW-1-5(b)
cum
428.50
cum
cum
100.40
662.70
cum
110.20
IRR-DAW-1-6(c)
cum
cum
909.60
290.20
Chapterwise item
S.NO
No.
1
IRR-DAW-1-7
IRR-DAW-1-8
IRR-DAW-1-9
10
Item description
Unit
Rate
3
Preparing foundation bed for masonry or concrete by benching, stepping,
removing all loose material by wedging / chiselling and disposing off the same as
directed and cleaning the surface with air and water jet etc.,complete with initial
lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)
sqm
33.90
Preparing foundation bed for cut-off trench filling in rock portion by removing
all loose materials by wedging / chiselling and disposing off the same as directed
etc., complete with initial lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)
Drilling 45 to 50 mm dia holes vertical or inclined upto 10 degrees to vertical in
rock /masonry / concrete by percussion drilling using waggon drill or any
other suitable equipment including cost of all materials, machinery, labour,
redrilling through partially set grout wherever required etc., complete for drilling
upto 6 m depth from surface.
sqm
sqm
26.60
22.50
sqm
22.50
Rm
199.80
Rm
Rm
Rm
Rm
Rm
Rm
Rm
Rm
219.80
241.80
266.00
292.60
321.90
354.10
389.50
Rm
50.90
The item rate for drilling through rock / masonry / concrete includes redrilling
through partially set grout, if any, in the portion of the hole drilled and grouted.
.
IRR-DAW-1-10
IRR-DAW-111(a)
IRR-DAW-112(b)
IRR-DAW-1-13
IRR-DAW-1-14
11
12
13
14
15
Flushing grout holes of all sizes with water and air jets alternatively for an
average period of 30 minutes including water intake observations after flushing,
cost of all materials, machinery, labour etc., complete.
Labour Component (including contractor's profit and Overheads)
Rm
tonne
tonne
Curtain grouting with neat cement grout mix of suitable consistency under
specified pressure as directed in drilled holes by stage grouting method
including cost of all materials, machinery, labour, redrilling if necessary etc.,
complete with initial lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)
tonne
17.20
8413.30
2775.80
9365.40
tonne
Providing and fixing 25 mm dia 3 m long cold twisted deformed steel dowel
bars with one end driven into 45 to 50 mm diameter 1.50 m deep hole drilled in
bed rock and other end provided with L-bend for embedding in concrete /
masonry of over flow / non-over flow blocks and other appertenant works
including cost of drilling and cleaning hole, filling hole with cement mortar 1 : 1
proportion, driving anchor rod, cost of all materials, machinery, labour etc.,
complete with initial lead upto 1 km and all lifts.
Each
Each
Providing and fixing 25 mm dia. 2.75 m long ribbed steel anchor rods with
one end split and driven firmly using steel wedge into 1.25 m deep 45 to 50 mm
dia. hole drilled in bed rock and other end provided with L- bend for embedding
in concrete / masonry for spillway and appurtenant works including drilling and
cleaning hole, filling hole with thick cement slurry, driving anchor rod, cost of all
materials, machinery, labour, steel wedge etc., complete with initial lead upto 1
km and all lifts.
Labour Component (including contractor's profit and Overheads)
43.80
Each
3573.80
1016.30
102.30
933.30
Each
115.60
IRR-DAW-2
IRR-DAW-2-1A
16
59857.87
tonne
tonne
3326.30
Chapterwise item
S.NO
No.
1
IRR-DAW-2-1B
IRR-DAW-2-2
17
18
IRR-DAW-2-2A
(new Item1 2010- 19
11)
IRR-DAW-2-3
IRR-DAW-2-4
20
21
IRR-DAW-2-4A
(new Item2 2010- 22
11)
IRR-DAW-2-4B
(new Item3 2010- 23
11)
Item description
Unit
Rate
cum
cum
Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength
not less than 20 N / sq mm ) grade cement concrete using 80 mm down size
approved, clean, hard, graded aggregates including cost of all materials,
machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing,
placing in position, levelling, vibrating, finishing, curing etc.,complete for plain
concrete works with initial lead upto 1 km and all lifts. ( Cement content : 300
kg /cum with use of super plasticiser equla to 0.4% of cement content, CA :
0.90 cum, Blending Ratio of CA -- 40:30:20:10, FA : 0.4 cum ))
cum
cum
Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength
not less than 10 N / sq mm ) grade cement concrete using 80 mm down size
approved, clean, hard, graded aggregates including cost of all materials,
machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing,
placing in position, levelling, vibrating, finishing, curing etc.,complete for plain
concrete works with initial lead upto 1 km and all lifts. ( Cement content : 220
kg /cum with use of super plasticiser, CA: 0.98 cum, Blending Ratio of CA -40:30:20:10, FA: 0.37 cum )
cum.
cum.
Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength
not less than 20 N / sq mm ) grade cement concrete using 40 mm down size
approved, clean, hard, graded aggregates including cost of all materials,
machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing,
placing in position, levelling, vibrating, finishing, curing etc.,complete for RCC
works of gallery, sluice, spillway crest, spillway d / s face, energy dissipating
structures, training walls, piers, abutments and such other locations with initial
lead upto 1 km and all lifts. ( Cement content : 310 kg / cum with use of super
plasticiser, CA : 0.90 cum, blending ratio of CA--50:30:20, FA : 0.40 cum)
cum.
cum.
Providing and laying insitu vibrated M-25 ( 28 days cube compressive strength
not less than 25 N / sq mm ) grade cement concrete using 40 mm down size
approved, clean, hard, graded aggregates including cost of all materials,
machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing,
placing in position, levelling, vibrating, finishing, curing etc.,complete for RCC
works of gallery, sluice, spillway crest, spillway d / s face, energy dissipating
structures, training walls, piers, abutments and such other locations with initial
lead upto 1 km and all lifts. ( Cement content : 360 kg / cum with use of super
plasticiser,CA : 0.90 cum, blending ratio of CA--50:30:20, FA : 0.40 cum)
Labour Component (including contractor's profit and Overheads)
Providing and laying insitu vibrated M-25 ( 28 days cube compressive strength
not less than 25 N / sq mm ) grade cement concrete using 20 mm down size
approved, clean, hard, graded aggregates including cost of all materials,
machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing,
placing in position, levelling, vibrating, finishing, curing etc.,complete for RCC
works of gallery, sluice, spillway crest, spillway d / s face, energy dissipating structures,
training walls, piers, abutments and such other locations with initial lead upto 1 km
and all lifts. ( Cement content : 380 kg / cum with use of super plasticiser,CA : 0.90
cum, blending ratio of CA--65:35, FA : 0.40 cum)
Labour Component (including contractor's profit and Overheads)
cum.
61009.05
4423.50
3454.20
160.90
3665.50
160.90
3300.90
160.90
4640.50
318.60
4916.40
cum.
cum.
cum.
318.60
5006.80
318.60
Chapterwise item
S.NO
No.
1
IRR-DAW-2-5
IRR-DAW-2-6
IRR-DAW-2-7
IRR-DAW-2-8
IRR-DAW-2-9
IRR-DAW-2-10
Item description
Unit
Rate
24
Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength
not less than 15 N / sq mm ) grade cement concrete using 40 mm down size
approved, clean, hard, graded aggregates including cost of all materials,
machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing,
placing in position, levelling, vibrating, finishing, curing etc.,complete for plain
concrete works with initial lead upto 1 km and all lifts. ( Cement content : 260
kg /cum with use of super plasticiser,CA : 0.90 cum, Blending Ratio of CA -50:30:20, FA : 0.40 cum)
cum.
4242.70
cum.
Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength
not less than 15 N / sq mm ) grade cement concrete using 40 mm down size
approved, clean, hard, graded aggregates with placing and sinking plums of
size 150 to 80 mm upto 15 percent for gravity type structures including cost of
all materials, machinery, labour, formwork, scaffolding, cleaning, batching,
mixing, placing in position, levelling, vibrating, finishing, curing etc.,complete
with initial lead upto 1 km and all lifts. ( Cement content : 260 kg / cum of
concrete with use of plums and super plasticiser,, CA : 0.77 cum, Blending
Ratio of CA : 50:30:20,FA : 0.34 cum, plums of size 150 to 80 mm : 0.25 cum)
cum.
cum.
25
26
27
28
29
Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength
not less than 10 N / sq mm ) grade cement concrete using 40 mm down size
approved, clean, hard, graded aggregates including cost of all materials,
machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing,
placing in position, levelling, vibrating, finishing, curing etc.,complete for plain
concrete works with initial lead upto 1 km and all lifts. ( Cement content 220
kg /cum with use of super plasticiser,CA : 0.90 cum, Blending Ratio of CA :
50:30:20, FA : 0.40 cum )
Labour Component (including contractor's profit and Overheads)
cum.
cum.
cum.
Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength
not less than 20 N / sq mm ) grade cement concrete using 20 mm down size
approved, clean, hard, graded aggregates including cost of all materials,
machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing,
placing in position, levelling, vibrating, finishing, curing etc.,complete for RCC
works of spillway bridge, blockouts and such other similar structures with
conjested reinforcement with initial lead upto 1 km and all lifts. ( Cement
content : 330 kg / cum with use of super plasticiser, CA : 0.80 cum, Blending
Ratio of CA -- 65:35, FA : 0.44 cum).
cum.
cum.
Providing and forming porous concrete body drain of size 68.5 x 68.5 cm with 23
cm diameter central hole using cement and 20 mm down approved, clean, hard,
graded coarse aggregates in 1 : 3.50 proportion by volume including cost of all
materials, machinery, labour, formwork, curing etc., complete with initial lead
upto 1 km and all lifts.(M15 Cement content : 400kg/cum, CA : 1cum, Blending
Ratio of CA -- 65:35)
Labour Component (including contractor's profit and Overheads)
1141.30
4108.80
1113.60
3921.10
cum.
Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength
not less than 15 N / sq mm ) grade cement concrete using 20 mm down size
approved, clean, hard, graded aggregates including cost of all materials,
machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing,
placing in position, levelling, vibrating, finishing, curing etc.,complete for plain
concrete works with initial lead upto 1 km and all lifts. ( Cement content : 280
kg /cum with use of super plasticiser,CA : 0.80 cum, Blending Ratio of CA -65:35, FA : 0.44 cum)
Rm
Rm
1033.20
4128.10
1058.00
5869.00
1499.60
2191.20
515.30
Chapterwise item
S.NO
No.
1
IRR-DAW-211(a)
IRR-DAW-212(b)
IRR-DAW-2-13
IRR-DAW-2-14
IRR-DAW-2-15
IRR-DAW-2-16
IRR-DAW-2-17
IRR_DAW-3
Item description
Unit
Rate
Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength
not less than 20 N / sq mm ) grade cement concrete using 20 mm down size
approved, clean, hard, graded aggregates including cost of all materials,
machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing,
placing in position, levelling, vibrating, finishing, curing etc.,complete for RCC
solid parapet consisting of 35 cm x 20 cm kerb, 35 cm x 35 cm x 1 m pillars
spaced approximately at 3.35 m c / c, 12.5 cm thick wall 80 cm height with 12.5
cm thick and 35 cm wide coping slab for wall and 12 .5 cm thick 40 cm x 40 cm
coping for pillars with top edges of kerb and coping chamferred / rounded as
directed etc., complete ( excluding cost of providing and placing
reinforcement steel and gate ) with initial lead upto 1 km and all lifts. (
Cement content 350 kg / cum with use of super plasticiser( 0.4% by wt.of
cement), CA : 0.80 cum, Blending Ratio of CA--65:35, FA : 0.44 cum)
Rm
2221.70
Rm
Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength
not less than 20 N / sq mm ) grade cement concrete using 20 mm down size
approved, clean, hard, graded aggregates including cost of all materials,
machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing,
placing in position, levelling, vibrating, finishing, curing etc.,complete for RCC
ornamental parapet consisting of 35 cm x 20 cm kerb, 35 cm x 35 cm x 1 m
pillars spaced approximately at 3.5 m apart, 20 cm x 15 cm posts 80 cm height
approximately 30 cm c / c with 12.5 cm thick and 35 cm wide coping slab for
posts and pillars with top edges of kerb and coping chamferred or rounded as
directed etc., complete ( excluding cost of providing and placing reinforcement
steel and gate ) with initial lead upto 1 km and all lifts. ( Cement content : 350
kg / cum with use of super plasticiser, CA : 0.80 cum, Blending Ratio of CA-65:35, FA : 0.44 cum)
Rm
Rm
Providing and laying insitu M- 25 ( 28 days cube compressive strength not less
than 25 N / sq mm ) grade cement concrete using 20 mm down size approved,
clean, hard, graded aggregates for wearing coat including cost of all materials,
machinery, labour, formwork, cleaning, batching, mixing, placing in position in
alternate panels, levelling, compacting, finishing, curing, packing joints with
asphalt mortar etc., complete with initial lead upto 1 km and all lifts. ( Cement
content : 380 kg / cum with use of super plasticiser, CA : 0.80 cum, Blending
Ratio of CA--65:35, FA : 0.45 cum)
cum
cum
cum
cum
30
31
32
33
34
35
36
Conveying and fixing elastomeric bearing for spillway bridge including cleaning
and preparing surface, mixing and applying adhesive, fixing bearing in correct
position etc., including cost of all materials except bearings, machinery, labour
etc., complete with all leads and lifts.
Labour Component (including contractor's profit and Overheads)
Each
639.00
2290.90
678.20
4725.50
1282.80
81.20
12.30
321.30
Each
Providing and constructing 150 mm dia hume pipe weep holes for concrete /
masonry walls including providing 20 x 20 x 20 cm size porous concrete block
made of cement and 20 mm down coarse aggregate in 1 : 4 proportion
including 10 cm thick sand backing at the junction of wall and soil back fill, cost of
all materials, machinery, labour etc., complete with lead upto 1 km and all lifts.
Rm
Rm
Rm
Rm
266.00
435.70
60.80
1909.40
277.80
Chapterwise item
S.NO
No.
1
IRR_DAW-3-1
37
IRR_DAW-3-2
IRR_DAW-3-3
38
39
Item description
Unit
Rate
3
Providing and constructing un-coursed rubble stone masonry using approved
stones in cement mortar 1 : 3 proportion including cost of all materials,
machinery, labour, scaffolding, cleaning, packing mortar, wedging stone chips,
curing etc., complete with initial lead upto 1 km and all lifts.( Cement content :
190 kg/cum of masonry, rubble stones : 0.85 cum,stone chips : 0.15 cum/cum,
FA : 0.4 cum)
Labour Component (including contractor's profit and Overheads)
cum
2584.70
IRR_DAW-3-4
IRR_DAW-3-5
40
41
IRR-DAW-3-7
IRR-DAW-3-8
42
43
44
IRR_DAW-4
IRR-DAW-4-1
cum
Providing and constructing chisel drafted and hammer dressed face stone
masonry with approved stones in cement mortar 1 : 3 proportion including
cost of all materials, machinery, labour, scaffolding, ramps, cleaning, packing
mortar, wedging stone chips, curing etc.,complete with initial lead upto 1 km
and all lifts.( Cement content : 167 kg/cum of masonry, rubble stones : 0.35
cum, stone chips : 0.15 cum/cum, FA : 0.35 cum, Dressed stones 30 x 30 x 45
cm : 10 No, Dressed stones 30 x 30 x 60 cm : 3.40 No)
972.50
2364.60
972.50
2750.10
cum
Providing and constructing coursed rubble face stone masonry using approved
rubble stones in cement mortar 1 : 4 proportion including cost of all materials,
machinery, labour, scaffolding,ramps, cleaning, packing mortar, wedging stone
cum
chips, curing etc., with initial lead upto 1 km and all lifts. ( Cement content :
134 kg/cum of masonry, rubble stones : 0.35 cum, stone chips : 0.15 cum/cum,
FA : 0.375 cum, CR stones 30 x 30 x 45 cm : 9.75 No, CR stones 30 x 30 x 60 cm :
3.25 No)
Labour Component (including contractor's profit and Overheads)
cum
IRR-DAW-3-6
cum
cum
1082.70
2543.90
1082.70
2935.40
cum
Providing and constructing chisel drafted and hammer dressed face stone
masonry with approved stones in cement mortar 1 : 4 proportion including
cost of all materials, machinery, labour, scaffolding, ramps, cleaning, packing
mortar, wedging stone chips, curing etc.,complete with initial lead upto 1 km
and all lifts.( Cement content : 125 kg/cum of masonry, rubble stones : 0.35
cum, stone chips : 0.15 cum/cum, FA : 0.35 cum, Dressed stones 30 x 30 x 45
cm : 10 No, Dressed stones 30 x 30 x 60 cm : 3.40 No)
cum
cum
sqm
sqm
sqm
sqm
1328.40
2738.60
1328.40
104.20
77.50
97.90
77.50
45
sqm
457.10
Chapterwise item
S.NO
No.
1
IRR-DAW-4-2
IRR-DAW-4-3
IRR-DAW-4-4
IRR-DAW-4-5
46
47
48
49
IRR-DAW-5-2
IRR-DAW-5-3
IRR-DAW-5-4
3
Labour Component (including contractor's profit and Overheads)
Providing and constructing contraction joints by fixing 16 SWG 60 cm wide
annealed copper sheets in two lines with 8 mm dia steel dowel rods on either side
at one metre interval, forming 125 x 125 mm size groove in between copper
strips for filling asphalt including fixing 15 mm dia two legged G.I pipe with U bend at bottom for circulation of steam at intervals and forming 150 mm dia
formed drain behind water seals including cost of all materials, machinery,
labour, filling asphalt, circulation of steam through pipes etc., complete with all
leads and lifts.
Labour Component (including contractor's profit and Overheads)
Providing and constructing contraction joints by fixing 310 mm wide central
bulb type approved quality PVC water stop in two lines with 8 mm diameter steel
dowel rods on either side at 1m interval, forming 125 x 125 mm size groove in
between two water stops, providing & fixing 15 mm dia two legged G.I pipe with
U-bend at bottom for circulation steam at interval, forming 150 mm diameter
formed drain behind water seals including filling groove with asphalt, circulation
of steam at intervals, cost of all materials, machinery, labour etc., complete with
all leads and lifts.
Labour Component (including contractor's profit and Overheads)
Providing and constructing contraction joints by fixing 16 SWG 60 cm wide
annealed copper sheets in single line with 8 mm dia steel dowel rods on either
side at 1 metre interval including cost of all materials, machinery, labour etc.,
complete with all leads and lifts.
Labour Component (including contractor's profit and Overheads)
Unit
Rate
4
sqm
Rm
15626.50
Rm
Rm
161.80
2480.90
Rm
Rm
106.90
7277.70
Rm
Rm
Rm
124.50
220.30
99.30
IRR-DAW-5
IRR-DAW-5-1
Item description
50
51
52
53
cum
cum
Providing cut-off trench filling using selected impervious soil from approved
borrow areas in layers of 25 to 30 cm before compaction including cost of all
materials, machinery, labour, all operations such as excavation, sorting out,
transportation, spreading soil to specified thickness, breaking clods, sectioning,
watering, compacting to density control of not less than 95 percent using Sheep
foot roller / Vibratory roller/ 8 to 10 tonne power roller as stipulated etc.,
complete with initial lead upto 1 km and all lifts.
cum
cum
cum
cum
cum
cum
139.20
19.00
149.40
20.70
149.90
20.60
126.00
17.60
Chapterwise item
S.NO
No.
1
IRR-DAW-5-4-A
(New Item1 2011-12)
IRR-DAW-5-5
IRR-DAW-5-6
Item description
Unit
Rate
54
cum
86.00
cum
cum
cum
55
56
IRR-DAW-5-7
IRR-DAW-5-8
IRR-DAW-5-9
57
58
59
IRR-DAW-5-9-A
(New Item4-2012- 60
13)
IRR-DAW-5-10
IRR-DAW-6
61
cum
cum
19.40
258.60
105.90
434.80
96.40
493.20
cum
cum
Note: Useful rubble and stone chips will be issued at dump yard at the issue rate
for usefull rubble /stone chips. Sorting out and breaking charges included in rate
analysis.
Labour Component (including contractor's profit and Overheads)
cum
Providing and laying 30 cm diameter open jointed hume pipes with collars in
rock-toe for drainage including cost of all materials, machinery, labour etc.,
complete with lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)
141.50
cum
Providing and constructing dry rubble rock-toe with rubble and stone chips
from dump yard including cost of all materials, machinery, labour, hand packing
rubble and stone chips, finishing top and sides to required slopes etc., complete
with initial lead upto 1 km and all lifts.
Providing and constructing Dry rock Pitching for Groynes using Un-Coursed
rubble stone of size 300 mm thick and Un-Coursed rubble stone chips from
Quarry to site of work including cost of all materials, Machinery, Labour charge
hand packing Un-Course rubble stone &chips to the designed profile with all
leads and lifts etc
Labour Component (including contractor's profit and Overheads)
17.60
cum
cum
cum
181.50
444.90
125.40
658.90
cum
Rm
Rm
125.40
769.00
28.00
Chapterwise item
S.NO
No.
1
IRR-DAW-6-1
IRR-DAW-6-2
IRR-DAW-6-3
IRR-DAW-6-4
Item description
Unit
Rate
62
Each
44110.40
Each
Providing and constructing longitudinal and cross graded filter drains using
sand and 80-20 mm and 20 mm down graded aggregates satisfying specified
filter creteria in layers as per specifications including cost of all materials,
machinery, labour, laying to required slopes, compaction etc. complete with
initial lead upto 50 m and all lifts.
cum
cum
cum
cum
63
64
65
IRR-DAW-6-4-A
(New Item2 2011- 66
12)
IRR-DAW-6-5
IRR-DAW-6-6
IRR-DAW-6-7
IRR-DAW-6-8
67
68
69
70
Providing and constructing graded filter media below and behind rock-toe
consisting of 20 cm thick sand, 25 cm thick 20 - 4.75 mm and 40 cm thick 80
- 20 mm size graded coarse aggregates satisfying filter creteria as per
specifications including cost of all materials, labour, machinery, laying to
required slope, compaction etc., complete with initial lead upto 50 m and all
lifts.
Labour Component (including contractor's profit and Overheads)
Providing and constructing graded filter media below and behind rock-toe
consisting of 30 cm thick, 80 - 20 mm size graded coarse aggregates
satisfying filter creteria as per specifications including cost of all materials,
labour, machinery, laying to required slope, compaction etc., complete with
initial lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)
Providing and laying filter media consisting of 2 layers of 250 gsm polypropeline non-woven filter fabric and 400 mm thick 20 mm down graded
coarse aggregate for vertical / inclined and horizontal filter blanket for
embankment including cost of all materials, machinery, labour etc., complete
with lead upto 50 m for aggregate and all leads for fabric and all lifts.
cum
956.60
132.00
1038.80
132.00
988.40
118.60
1134.70
cum
sqm
sqm
cum
cum
9462.90
cum
cum
cum
44.60
951.10
51.30
658.10
105.10
1020.20
cum
sqm
sqm
138.70
860.70
154.60
Chapterwise item
S.NO
No.
1
IRR-DAW-6-9
IRR-DAW-6-10
IRR-DAW-6-11
IRR-DAW-6-12
IRR-DAW-6-13
Item description
Unit
Rate
sqm
1025.20
sqm
71
72
73
74
75
Providing and constructing 60 cm thick hand packed rough stone riprap over
a backing of 45 cm thick graded filter media consisting of sand, 10 mm and 40
mm size graded approved aggregates laid in layers of 15 cm thick each
including cost of all materials, machinery, labour, laying to required slopes,
wedging with stone chips etc., complete with initial lead upto 50 m and all
lifts.
Labour Component (including contractor's profit and Overheads)
sqm
sqm
Providing and constructing 90 cm thick hand packed rough stone riprap over
a backing of 45 cm thick graded filter media consisting of sand, 10 mm and 40
mm size graded approved aggregates laid in layers of 15 cm thick each including
cost of all materials, machinery, labour, laying to required slopes, wedging with
stone chips etc., complete with initial lead upto 50 m and all lifts.
sqm
sqm
Providing and laying Hariyala or other approved quality turfing sods for the
slopes of earthen embankments over 20 mm thick sand backing including cost of
all materials, machinery, labour including preparing surface, spreading sand,
watering for 15 days etc., complete with initial lead upto 1 km and all lifts.
sqm
sqm
IRR-TAW-1
EXCAVATION :
IRR-TAW-1-2
IRR-TAW-1-3
IRR-TAW-1-4
76
77
78
79
174.80
803.40
sqm
Providing and constructing 75 cm thick hand packed rough stone riprap over
a backing of 45 cm thick graded filter media consisting of sand, 10 mm and 40
mm size graded approved aggregates laid in layers of 15 cm thick each including
cost of all materials, machinery, labour, laying to required slopes, wedging with
stone chips, etc., complete with initial lead upto 50 m and all lifts.
Chapter II
IRR-TAW
IRR-TAW-1-1
sqm
Excavation for adit by tunnelling methods in all types of rock including cost
of all materials, machinery, labour, scaling excavated surface, ventilation,
lighting, drainage, removing and hauling the excavated muck outside adit upto
specified dump area and all other ancillary operations etc., complete with
initial lead upto 50 m and all lifts.
cum
cum
Excavation for vertical / inclined shaft in all types of soft / hard rock
including cost of all materials, machinery, labour, shoring, strutting, scaling
excavated surface, ventilation, lighting, drainage, removing and hauling
excavated muck outside shaft upto specified dump area and all other ancillary
operations etc., complete with initial lead upto 1 km and all lifts.
cum
cum
cum
cum
cum
118.10
876.10
128.70
961.50
150.00
99.80
59.50
1713.00
551.50
2237.90
1104.70
1751.70
543.80
1803.30
10
Chapterwise item
S.NO
No.
1
IRR-TAW-1-5
80
Item description
3
Labour Component (including contractor's profit and Overheads)
Excavation for tunnel by heading and benching tunnelling methods including
excavation for supports in all types of soil / rock strata requiring supports (
excluding cost of providing supports ) for roof before benching including cost of
all other materials, machinery, labour, scaling excavated surface, ventilation,
lighting, drainage removing and hauling excavated muck outside tunnel upto
specified dump area and all other ancillary operations etc., complete with initial
lead upto 1 km and all lifts.
NOTE: Where mucking is to be carried out through shaft using winch and
mucking tub system increase the basic rates for items 3, 4 & 5 by 8 percent.
IRR-TAW-1-6
81
IRR-TAW-2-2
82
83
IRR-TAW-2-3
(new Item4 2010- 84
11)
IRR-TAW-3-2
IRR-TAW-3-3
cum
1848.30
cum
cum
603.10
362.60
cum
Kwhr
84.10
23.40
Kwhr
sqm
7.90
567.40
sqm
sqm
sqm
85
86
87
IRR-TAW-3-4
4
cum
174.00
1344.10
174.00
IRR-TAW-3
IRR-TAW-3-1
Rate
IRR-TAW-2
IRR-TAW-2-1
Unit
88
Rm
1116.60
Rm
Rm
294.50
1069.00
Rm
tonne
271.30
95183.90
tonne
tonne
tonne
15917.60
22295.80
7944.70
11
Chapterwise item
S.NO
No.
1
IRR-TAW-3-5
89
IRR-TAW-5-2
IRR-TAW-5-3
IRR-TAW-5-4
90
cum
32859.50
Providing and fixing hard variety cut jungle wood for lagging / blocking
locations in tunnel wherever required including cost of all materials, machinery,
labour, fixing in position, lighting, ventilation, drainage etc complete with all
leads and lifts.
Labour Component (including contractor's profit and Overheads)
cum
1412.00
cum
cum
2064.80
740.30
91
92
93
94
tonne
tonne
Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength
not less than 10 N / sq mm ) grade cement concrete using 40 mm down size
approved, clean, hard, graded aggregates crushed from tunnel excavated muck
for filling and levelling over-cuts in bed due to geological faults etc., including
cost of all materials, machinery, labour, cleaning bed, batching, mixing,
conveying and laying, levelling, compacting, finishing, curing, lighting,
ventilation, drainage etc., complete with initial lead upto 1 km and all lifts. (
Cement content : 220 kg / cum, CA : 0.90cum, Blending Ratio of CA--50:30:20,
FA : 0.40 cum, Superplasticizer 0.4% by wt. of cement)
cum
cum
Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength
not less than 20 N / sqmm ) grade cement concrete using 40 mm and down size
approved clean, hard, graded aggregates crushed from tunnel muck for kerb and
bed lining including cost of all materials, machinery, labour, formwork, batching,
mixing, conveying upto placing point in agitator cars, placing in position,
levelling, vibrating, finishing, curing, ventilation, lighting, drainage and all other
ancillary operations etc., complete with lead upto 1 km and all lifts. ( Cement
content 330 kg / cum for use of super plasticiser(0.4% by wt. of cement),CA :
0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
cum
cum
Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength
not less than 20 N / sqmm ) grade cement concrete using 40 mm and down size
approved clean, hard, graded aggregates crushed from tunnel muck for sides
and arch lining including cost of all materials, machinery, labour, formwork,
batching, mixing, conveying upto placing point in agitator cars, placing in
position, levelling, vibrating, finishing, curing, ventilation, lighting, drainage and
all other ancillary operations etc., complete with lead upto 1 km and all lifts. (
Cement content 330 kg / cum for use of super plasticiser(0.4% by wt. of
cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
cum
cum
73182.60
9661.50
5064.10
738.30
6099.40
920.00
#REF!
#REF!
IRR-TAW-6
IRR-TAW-6-1
Rate
MASONRY WORKS :
IRR-TAW-5
IRR-TAW-5-1
Unit
IRR-TAW-4
IRR-TAW-4-1
Item description
95
Rm
Rm
389.00
141.60
12
Chapterwise item
S.NO
No.
1
IRR-TAW-6-2
96
Item description
Unit
Rate
tonne
9052.90
IRR-TAW-6-3
97
Chapter III
IRR-CAW
IRR-CAW-1-2
98
99
cum
Excavation in all kinds of soil including boulders upto 0.30 m dia for field
channels, seating of embankment for field channels etc., including dressing of
bed and sides to required profile, cost of all materials, machinery, labour, placing
the excavated stuff for formation of service road / embankment as directed etc.,
complete with lead upto 10 m and lift upto 3 m.
cum
cum
IRR-CAW-1-4
IRR-CAW-1-5
360.70
Rm
EXCAVATION WORKS :
Excavation in all kinds of soil including boulders upto 0.3 m diameter for canal,
seating of embankment, filter drains / catch water drains etc., including dressing
bed and sides to required level and profile, cost of all materials, machinery,
labour, placing the excavated soil neatly in dump area or for the formation of
service road / embankment as directed etc., complete with initial lead upto 1
km and all lifts.
Labour Component (including contractor's profit and Overheads)
IRR-CAW-1-3
Rm
2173.80
58.50
IRR-CAW-1
IRR-CAW-1-1
tonne
94.00
cum
cum
22.50
49.60
18.10
127.30
cum
cum
33.30
82.10
cum
cum
30.00
194.80
cum
cum
i ) The rate under this item shall be adopted for canals designed for carrying
capacity of less than 15 cumecs or where the average depth excavation in hard
rock is less than 3 m.
ii ) The rate includes levelling canal bed by hammering / chiselling all rock
projections wherever required.
Labour Component (including contractor's profit and Overheads)
cum
60.40
484.80
129.70
13
Chapterwise item
S.NO
No.
1
Item description
Unit
Rate
cum
604.20
Excavation in hard rock of all toughness including boulders above 1.2 m dia.
by approved controlled blasting methods for canals, cut-off trench of
embankment, filter / catch-water drains etc., including controlling fly-rock by
muffling arrangements such as placing 50 x 50 mm opening chain link mesh or
waste tyres and sand bags, monitoring ground vibrations at specified locations,
costof all materials, machinery, labour, placing excavated rock neatly in
approved dump area or other place as directed etc., complete with lead upto 1
IRR-CAW-1-7 (b) 104
km and all lifts.
i) The rate under this item shall be adopted for canals designed for carrying
capacity of less than 15 cumecs or where the average depth excavation in hard
rock is less than 3 m.
ii ) The rate under this item shall be adopted where the control of fly-rock and
ground vibrations is required.
Labour Component (including contractor's profit and Overheads)
Excavation in hard rock of all toughness including boulders above 1.2 m dia.
for dressing canal sides neatly on either side to required profile by line drilling
and smooth blasting including removing under-cuts by chiselling / hammering,
placing the excavated rock neatly in dump area or other place as directed, cost
of all materials, machinery, labour etc., complete with lead upto 1 km and all
lifts.
i) For excavation of canal below free board level combination of normal
controlled blasting and line drilling and smooth blasting shall be adopted to
obtain neat side slopes. For the purpose of payment 1 m width of excavation on
IRR-CAW-1-8( c) 105
either side shall be treated as excavation by line drilling and smooth blasting and
remaining portion shall be treated as excavation by normal / controlled blasting
as the case may be.
ii ) The rate under this item shall be adopted for canals designed for carrying
capacity of less than 15 cumecs or where the average depth of excavation in
hard rock is less than 3 m.
iii ) The rate includes controlling fly-rock wherever required.
iv ) The rate under this item shall be paid only on ascertaining that the
excavated face has come off neatly as per specifications or atleast 50 percent of
Labour Component (including contractor's profit and Overheads)
cum
cum
128.10
1060.90
cum
341.90
Excavation in hard rock by blasting including boulders above 1.2 m dia. for
canals, seating embankment etc., including levelling bed by removing all
projections by hammering / chiselling, cost of all materials, machinery, labour,
placing the excavated rock neatly in approved dump area and levelling the same
as directed etc.,complete with initial lead upto 1 km and all lifts.
IRR-CAW-1-9(a)
106
cum
298.50
i ) The rate under this item shall be adopted for canals designed for carrying
capacity of more than 15 cumecs or where the average depth of excavation in
hard rock is more than 3 m.
ii ) The rate includes levelling canal bed by hammering /chiselling all rock
projections wherever required.
Labour Component (including contractor's profit and Overheads)
IRR-CAW-110(b)
Excavation in hard rock of all toughness including boulders above 1.2 m dia.
by approved controlled blasting methods for canals, cut-off trench of
embankment etc., including controlling fly-rock by muffling arrangements such
as placing 50 x 50 mm opening chain link mesh or waste tyres and sand bags,
monitoring ground vibrations at specified locations, cost of all materials,
machinery, labour, placing excavated rock neatly in approved dump area or
107 other place as directed etc., complete with lead upto 1 km and all lifts.
cum
cum
40.80
451.50
i ) The rate under this item shall be adopted for canals designed for carrying
capacity of more than 15 cumecs or where the average depth of excavation in
hard rock is more than 3 m.
ii ) The rate under this item shall be adopted where the control of fly-rock and
ground vibrations is required.
Labour Component (including contractor's profit and Overheads)
cum
46.70
14
Chapterwise item
S.NO
No.
1
IRR-CAW-111(c)
IRR-CAW-2
IRR-CAW-2-1
Item description
3
Excavation in hard rock of all toughness including boulders above 1.2 m dia.
for dressing canal sides neatly on either side to required profile by line drilling
and smooth blasting including removing under-cuts by chiselling / hammering,
placing the excavated rock neatly in dump area or other place as directed, cost
of all materials, machinery, labour etc., complete with lead upto 1 km and all
lifts.
i ) For excavation of canal below free board level combination of normal
controlled blasting and line drilling and smooth blasting shall be adopted to
obtain neat side slopes. For the purpose of payment 1 m width of excavation on
108
either side shall be treated as excavation by line drilling and smooth blasting and
remaining portion shall be treated as excavation by normal / controlled blasting
as the case may be.
ii ) The rate under this item shall be adopted for canals designed for carrying
capacity of more than 15 cumecs or where the average depth of excavation in
hard rock is more than 3 m.
iii ) The rate includes controlling fly-rock wherever required.
iv ) The rate under this item shall be paid only on ascertaining that the
excavated face has come off neatly as per specifications or atleast 50 percent
Labour Component (including contractor's profit and Overheads)
IRR-CAW-2-3
IRR-CAW-2-4
IRR-CAW-2-5
Rate
cum
753.80
cum
105.30
IRR-CAW-2-2
Unit
cum
198.00
cum
cum
30.70
191.20
cum
cum
30.10
197.60
cum
cum
30.70
193.20
cum
cum
cum
32.30
180.00
27.90
15
Chapterwise item
S.NO
No.
1
IRR-CAW-2-6
Item description
Unit
Rate
cum
171.10
IRR-CAW-2-7
IRR-CAW-2-8
IRR-CAW-3
IRR-CAW-3-1
IRR-CAW-3-2
IRR-CAW-3-3
cum
25.30
165.10
cum
cum
24.90
155.00
cum
22.80
IRR-CAW-3-4
cum
cum
150.10
cum
cum
23.50
144.80
cum
cum
23.10
145.80
cum
cum
cum
22.80
140.40
22.30
16
Chapterwise item
S.NO
No.
1
IRR-CAW-3-5
IRR-CAW-4
IRR-CAW-4-1
Item description
3
Providing semi-pervious / pervious casing embankment using soil from
approved dump area in layers of 25 cm before compaction including cost of
all materials, machinery, labour, all operations such as re-excavation, sorting
out, transporting, spreading in layer of specified thickness, breaking clods,
121
sectioning, compacting each layer without watering to density control of not
less than 95 percent or as stipulated by Sheep foot roller / Vibratory roller/ 8
to 10 tonne power roller etc., complete with initial lead upto 1 km and all
lifts.
Labour Component (including contractor's profit and Overheads)
IRR-CAW-4-3
IRR-CAW-4-4
IRR-CAW-4-5
IRR-CAW-4-6
Rate
cum
131.50
cum
20.50
IRR-CAW-4-2
Unit
cum
67.30
cum
cum
9.50
61.90
cum
cum
9.70
67.30
cum
cum
9.50
61.90
cum
cum
9.70
51.60
cum
cum
7.00
266.80
IRR-CAW-5-1
cum
262.40
cum
653.00
17
Chapterwise item
S.NO
No.
1
IRR-CAW-5-2
IRR-CAW-5-3
IRR-CAW-5-3-A
(New Item 3 2011-12)
IRR-CAW-5-4
IRR-CAW-5-5
IRR-CAW-5-6
IRR-CAW-5-7
IRR-CAW-5-8
IRR-CAW-5-9
IRR-CAW-510(a)
Item description
3
Labour Component (including contractor's profit and Overheads)
Rate
4
cum
cum
545.80
cum
sqm
134.50
114.30
sqm
cum
16.90
457.10
cum
Providing and constructing dry rubble rock-toe using rubble and stone chips
from approved source including cost of all materials, machinery, labour, hand
132
packing rubble and stone chips, finishing top and sides to required slopes etc.,
complete with initial lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)
Providing and constructing longitudinal and cross graded filter drains using
sand and 20 mm down graded aggregates satisfying specified filter creteria in
133 layers as per specifications including cost of all materials, machinery, labour,
laying to required slopes, compaction etc., complete with initial lead upto 50 m
and all lifts.
Labour Component (including contractor's profit and Overheads)
cum
cum
133
Rm
517.20
95.60
827.60
cum
Rm
Laying and fixing of 100 mm Dia 300 mm long precast porus CC plugs in bed
and sides using 1.181 Kgs of cement per each using 20 mm HG metal and
135
placing in local filters of size 600x600x750 mm in size including excavation of
drains and Cost of procuring of all materials
Labour Component (including contractor's profit and Overheads)
67.30
cum
Laying Longitudinal Drains and Transverse drains of Size 600 x600 x750 mm
134 in Bed and filling with 12 mm to 40 mm HG machine Crushed metal and sand in
bed including excavation of drains and Cost of procuring of all materials
IRR-CAW-511(b)
Unit
one plug
125.30
407.60
23.80
336.00
one plug
cum
100.90
954.90
cum
cum
125.30
1159.30
cum
sqm
117.10
600.60
sqm
sqm
27.80
653.20
18
Chapterwise item
S.NO
No.
1
IRR-CAW-6
IRR-CAW-6-1
IRR-CAW-6-2
Item description
3
Labour Component (including contractor's profit and Overheads)
IRR-CAW-7-1
IRR-CAW-7-2
IRR-CAW-7-3
IRR-CAW-7-4
Providing cohesive non-swelling ( CNS ) soil lining to canals using soil from
approved borrow area including spreading soil in layers of thickness not
142 more than 15 cm, breaking clods, watering, compacting to density control of not
less than 98 percent or as stipulated, dressing to required profile etc., complete
with initial lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)
Providing cohesive non-swelling ( CNS ) soil lining to canals using soil from
approved borrow area including spreading soil in layers of thickness not
143 more than 15 cm, breaking clods, watering, compacting to density control of not
less than 95 percent or as stipulated, dressing to required profile etc., complete
with initial lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)
Providing cohesive non-swelling ( CNS ) soil lining to canal using soil
collected in heaps along the edge of canal requiring CNS soil lining as part
of the disposal of excavated soil from canal excavation in CNS soil reach
144 including spreading in layers of thickness not more than 15 cm, breaking clods,
watering, compacting to density control of not less than 95 percent or as
stipulated, dressing to required profile etc., complete with lead upto upto 50 m
and all lifts.
Labour Component (including contractor's profit and Overheads)
Providing and fixing 20 x 20 x 75 cm size top surface neatly dressed canal
145 bed level stones including cost of all materials, labour, excavation, fixing in
position to correct level etc., complete with lead upto 50 m and all lifts.
Providing, fabricating and placing in position reinforcement steel bars for RCC
works including cleaning, straightening, cutting, bending, hooking, lapping, tying
146 with 1.25 mm dia.soft annealed steel wire, welding wherever required including
cost of all materials, machinery, labour etc., complete with initial lead upto 50
and all lifts.(1.05 tonne/tonne of steel)
Labour Component (including contractor's profit and Overheads)
IRR-CAW-7-6
4
sqm
cum
471.20
cum
cum
50.50
271.70
cum
65.10
IRR-CAW-7-5
Rate
Stones and spalls available in dump yard will be issued at specified issue rate.
Labour Component (including contractor's profit and Overheads)
IRR-CAW-7
Unit
cum
211.90
cum
cum
60.60
206.90
cum
cum
59.90
105.00
cum
Each
45.90
87.90
Each
kg
61.70
63.50
kg
sqm
sqm
6.70
390.40
27.70
19
Chapterwise item
S.NO
No.
1
IRR-CAW-7-7
Item description
Unit
Rate
sqm
406.30
IRR-CAW-7-8
Providing and laying 100 mm thick in situ M-15 (28 days cube compressive
strength not less than 15 N /Sqmm ) grade cement concrete with 20 mm down
size approved, clean, hard, graded aggregates for canal lining using, vibrating,
cylinder type mechanical paver including cost of all materials, machinery, labour,
cleaning, batching, mixing, placing in position, finishing, forming contraction
149 joints, fixing PVC joint sealing strips, curing, shifting of paver from one side to
othere side of canal etc., complete with initial lead upto 1 Km and all lifts. ( 43
Gr Cement content: (300kg /cum) 30 kg / sqm for use of super
plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35,
FA : 0.45 cum, equivalent concrete volume:88 cum including the extra
quantity of concrete for curvatures and bends etc.,)
Labour Component (including contractor's profit and Overheads)
IRR-CAW-7-9
IRR-CAW-7-10
Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength
not less than 10 N /sq mm ) grade cement concrete using 40 mm down size
approved, clean, hard, graded aggregates for bed and side lining of
canal(150mm thick) including finishing the junction of bed and sides to required
curveture, cost of all materials, machinery, labour, formwork including supports,
151 cleaning, batching, mixing, placing in position, levelling, vibrating, finishing,
curing etc., complete with initial lead upto 50 m and all lifts. ( 43 Gr Cement
content: 250 kg / cum for use of super plasticiser(0.4% by wt. of cement),CA :
0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
(Only forManually operated)
IRR-CAW-7-11
Providing and laying insitu vibrated M-10 (28 days cube compressive strength
not less than 10 N/sqm) grade cement concrete using 40 mm down size
approved, clean, hard, graded aggregade for bed and side lining of canal(100
mm thick) including, finishing the junction of bed and sides to required
152 curveture, cost of all materials, machinery, labour, formwork including supports
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing,
curing etc., complete with initial lead up to 50 m and all lifts ( 43 Gr Cement
content: 250 kg / cum for use of super plasticiser(0.4% by wt. of cement),CA :
0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
Labour Component (including contractor's profit and Overheads)
IRR-CAW-7-12
Providing and laying 100mm thick insitu vibrated M-10 (28 days cube
compressive strength-not less than 10.00 N / sq mm) grade cement concrete
using 40 mm down size approved, clean, hard, graded aggregates for bed and
side lining of canal lining using vibrating cylindertype mechanical paver
153 including cost of all materials mechinery labour batching mixing placing in
position forming contraction joints fixing pvc joint seiling strips shifting of paver
from one side of canal to other side etc.complete with all leads & lifts.
(Cement content: 250 kg / cum for use of super plasticiser(0.4% by wt. of
cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
Labour Component (including contractor's profit and Overheads)
sqm
sqm
27.70
491.10
sqm
shifting
32.00
8490.30
shifting
cum
6039.30
4110.40
cum
cum
1071.10
4253.20
cum
sqm
sqm
1103.00
474.20
32.00
20
Chapterwise item
S.NO
No.
1
IRR-CAW-7-13
Item description
Unit
Rate
cum
4154.90
IRR-CAW-7-14
IRR-CAW-7-15
Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength
not less than 15 N /sq mm ) grade cement concrete using 20 mm down size
approved, clean, hard, graded aggregates for bed and side lining(of thickness
100 mm) of canal including finishing the junction of bed and sides to required
156 curveture, cost of all materials, machinery, labour, formwork including supports,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing,
curing etc., complete with initial lead upto 50 m and all lifts. (Cement content:
300 kg / cum for use of super plasticiser(0.4% by wt. of cement),CA : 0.80
cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
Labour Component (including contractor's profit and Overheads)
IRR-CAW-7-16
Providing and laying 150mm thick insitu vibrated M-15 (28 days cube
compressive strength-not less than 15.00 N / sq mm) grade cement concrete
using 20 mm down size approved, clean, hard, graded aggregates for bed and
side lining of canal lining using vibrating cylindertype mechanical paver including
cost of all materials mechinery labour batching mixing placing in position forming
157
contractiom joints fixing pvc joint seiling strips shifting of paver from one side of
canal to other side etc.complete with all leads & lifts. (Cement content: 300
kg / cum for use of super plasticiser(0.4% by wt. of cement),CA : 0.80 cum,
Blending Ratio of CA--65:35, FA : 0.44 cum)
(Paver)
Labour Component (including contractor's profit and Overheads)
IRR-CAW-7-17
Providing and fixing pre-cast RCC template walls consisting of 0.05 cum M-15
grade concrete using 20 mm down size coarse aggregates and 10 kg
reinforcement steel moulded as per specifications and drawing in CM 1:4
158 proportion including cost of all materials, machinery, labour, formwork,
fabricating and placing reinforcement steel, mixing, laying, conveying and fixing
in position including necessary excavation for seating, finishing joints in CM 1:4,
curing etc., complete with initial lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)
IRR-CAW-7-18
IRR-CAW-7-19
cum
cum
1103.00
4441.60
cum
cum
1167.00
4570.00
cum
sqm
1232.50
647.00
sqm
Rm
32.00
1000.70
Rm
Each
242.60
136.60
Each
Each
Each
42.00
194.10
42.00
21
Chapterwise item
S.NO
No.
1
IRR-CAW-7-20
IRR-CAW-7-21
IRR-CAW-7-22
IRR-CAW-7-23
IRR-CAW-7-24
IRR-CAW-7-25
Item description
3
Providing and fixing 50 mm dia perforated GI pressure relief pipes 30 cm
long with one end closed with perforated GI plate and other end provided with
161
alluminium lid hinged to pipe including cost of all materials, labour, drilling 8 mm
dia holes etc., complete with all leads and lifts.
Labour Component (including contractor's profit and Overheads)
Providing and fixing 50 mm dia perforated GI pressure relief pipes 45 cm
long with one end closed with perforated GI plate and other end provided with
162
alluminium lid hinged to pipe including cost of all materials, labour, drilling 8 mm
dia holes etc., complete with all leads and lifts.
Labour Component (including contractor's profit and Overheads)
Providing and fixing 50 mm dia perforated GI pressure relief pipes 75 cm
long with one end closed with perforated GI plate and other end provided with
163
alluminium lid hinged to pipe including cost of all materials, labour, drilling 8 mm
dia holes etc., complete with all leads and lifts.
Labour Component (including contractor's profit and Overheads)
Providing and fixing 100 mm dia perforated PVC pipes 40 cm long for Weep
164 holes including cost of all materials, labour, drilling 8 mm dia holes etc. complete
with all leads and lifts.
Labour Component (including contractor's profit and Overheads)
Drilling 32 mm dia pressure relief hole below pressure relief pipe for bed and
165 side lining of canal laid on rock including cost of all materials, machinery, labour
etc., complete with all leads and lifts.
Labour Component (including contractor's profit and Overheads)
IRR-CAW-7-28
IRR-CAW-7-30
Each
230.80
Each
Each
171
Providing and fixing LDPE sheet for bed and sides of canal including cost of all
172 materials, labour, laying, joining etc., complete with all leads and lifts.
Using 750 micron thick LDPE sheet.
Labour Component (including contractor's profit and Overheads)
42.00
299.50
Each
Each
42.00
432.30
Each
Each
42.00
220.40
Each
Each
21.00
267.10
Each
sqm
IRR-CAW-7-31
IRR-CAW-7-29
Each
IRR-CAW-7-27
Rate
IRR-CAW-7-26
Unit
85.70
40.70
Each
7.30
351.40
sqm
sqm
63.30
75.30
sqm
Rm
58.70
43.90
Rm
Each
39.30
164.50
Each
sqm
164.50
128.00
sqm
sqm
11.90
37.30
sqm
sqm
sqm
8.10
180.00
16.20
22
Chapterwise item
S.NO
No.
1
IRR-CAW-7-32
Item description
Unit
Rate
sqm
248.40
Providing and fixing LDPE sheet for bed and sides of canal including cost of all
173 materials, labour, laying, joining etc., complete with all leads and lifts.
Using 1000 micron thick LDPE sheet.
Labour Component (including contractor's profit and Overheads)
IRR-CAW-7-33
IRR-CAW-7-34
IRR-CAW-7-35
IRR-CAW-7-36
IRR-CAW-7-37
Providing and fixing 12 mm thick 380 mm depth tarfelt expansion joint filler
174 boards for stone masonry lining of canal including cost of all materials, labour
etc., complete with all leads and lifts.
Labour Component (including contractor's profit and Overheads)
Providing and fixing 20 mm thick 100 mm depth tarfelt expansion joint filler
175 boards for cement concrete lining of canal including cost of all materials,
labour etc., complete with all leads and lifts.
Labour Component (including contractor's profit and Overheads)
Providing and fixing 20 mm thick 150 mm depth tarfelt expansion joint filler
176 boards for cement concrete lining of canal including cost of all materials,
labour etc., complete with all leads and lifts.
Labour Component (including contractor's profit and Overheads)
Providing and forming 35 mm wide and 10 mm thick construction /
177 contraction joints for concrete lining by mastic filler including cost of all
materials, labour etc., complete with all leads and lifts.
Labour Component (including contractor's profit and Overheads)
Manufacturing 550 x 550 x 55 mm size PCC lining slabs in M-15 grade ( 28
days cube compressive strength not less than 15 N /sqmm ) cement concrete
using 20 mm down graded coarse aggregate including cost of all materials,
178 machinery, labour, batching, mixing, laying, compacting, formwork, finishing,
curing etc.,complete with initial lead upto 50 m and all lifts. ( Cement content :
300 kg / cum with super plastcizer (0.4% by wt. of cement), CA : 0.80 cum,
Blending Ratio of CA : 65:35, FA : 0.45cum)
Labour Component (including contractor's profit and Overheads)
IRR-CAW-7-38
Manufacturing 550 x 300 x 55 mm size PCC lug slabs in M-15 grade ( 28 days
cube compressive strength not less than 15 N / sqmm ) cement concrete using
20 mm down graded coarse aggregate including cost of all materials,
179 machinery, labour, batching, mixing, laying, compacting, formwork, finishing,
curing etc.,complete with initial lead upto 50 m and all lifts. ( Cement content :
300 kg / cum with super plastcizer (0.4% by wt. of cement), CA : 0.80 cum,
Blending Ratio of CA : 65:35, FA : 0.45cum)
Labour Component (including contractor's profit and Overheads)
IRR-CAW-7-39
IRR-CAW-7-40
IRR-CAW-7-41
sqm
Rm
21.90
192.80
Rm
Rm
7.30
79.10
Rm
Rm
7.30
117.20
Rm
Rm
7.30
22.80
Rm
Each
5.40
88.20
Each
Each
23.00
62.00
Each
Each
23.00
31.50
Each
Each
14.80
24.00
Each
Each
Each
14.80
72.90
14.70
23
Chapterwise item
S.NO
No.
1
IRR-CAW-7-42
IRR-CAW-7-43
IRR-CAW-7-44
Item description
3
Manucturing 400 x 400 x 30 mm size PCC lining slabs in M-15 grade ( 28
days cube compressive strength not less than 15 N / sqmm )cement concrete
using 10 mm down graded coarse aggregate including cost of all materials,
183 machinery, labour, batching, mixing, laying, compacting, formwork, finishing,
curing etc.,complete with initial lead upto 50 m and all lifts. ( Cement content :
300 kg / cum with super plastcizer (0.4% by wt. of cement), CA : 0.68 cum, FA
: 0.43cum)
Labour Component (including contractor's profit and Overheads)
Manufacturing 400 x 150 x 30 mm size PCC lug slabs in M-15 grade ( 28 days
cube compressive strength not less than 15 N /sqmm ) cement concrete using
10 mm down graded coarse aggregate including cost of all materials,
184 machinery, labour, batching, mixing, laying, compacting, formwork, finishing,
curing etc.,complete with initial lead upto 50 m and all lifts. ( Cement content :
300 kg / cum with super plastcizer (0.4% by wt. of cement), CA : 0.68 cum, FA
: 0.43cum)
Labour Component (including contractor's profit and Overheads)
Providing and laying uncoursed rubble stone masonry in CM 1 : 5 proportion
for canal side lining using stones and chips from approved quarry including cost
of all materials, machinery, labour, forming weep holes at specified intervals,
185
finishing, curing etc., complete with initial lead upto 50 m and all
lifts.(Thickness of the masonry assumed: 0.3 m, rubble stones : 0.96 cum,
Stone Chips : 0.15cum,Through Stones 20 x 20 x 30cm : 1/sqm)
Labour Component (including contractor's profit and Overheads)
IRR-CAW-7-45
Providing and laying uncoursed rubble stone masonry in CM 1:5 proportion for
canal side lining using stones from approved quarry including cost of all
186 materials, machinery, labour, forming weep holes at specified intervals, finishing,
curing etc., complete with initial lead upto 50m and all lifts.(with no pin
headers)(Thickness of the Masonry assumed:0.3 m, rubble stones : 1.1 cum)
Labour Component (including contractor's profit and Overheads)
IRR-CAW-7-46
IRR-CAW-7-47
IRR-CAW-8
IRR-CAW-8-1
IRR-CAW-8-2
Rate
Each
33.40
Each
Each
14.80
23.40
Each
cum
14.80
1901.80
cum
cum
566.50
3009.10
cum
cum
1870.60
1764.50
cum
cum
639.40
2805.10
cum
1870.60
ROCK PITCHING
Providing and constructing 25 cm thick dry rubble stone pitching with pin
headers at 2 per sqm including cost of all materials, labour, hand packing,
189
finishing etc., complete with initial lead upto 50 m and all lifts.( rubble stones :
0.23 cum/sqm, Stone Chips : 0.0375cum/sqm, Pin Headers 30cm : 2/sqm)
Labour Component (including contractor's profit and Overheads)
If 15 cm thick murum bed is to be provided below pitching add
Labour Component (including contractor's profit and Overheads)
IRR-CAW-8-1-A
(New Item4 2011-12)
Unit
Providing and constructing 22.5 cm thick dry rubble stone pitching with pin
headers at 2 per sqm including cost of all materials, labour, hand packing,
190 finishing etc., complete with initial lead upto 50 m and all lifts.( rubble stones :
0.207 cum/sqm, Stone Chips : 0.3375cum/sqm, Pin Headers 30cm : 2/sqm)
(For Maintenance Works)
Labour Component (including contractor's profit and Overheads)
Providing and constructing 25 cm thick dry rubble stone pitching including
cost of all materials, labour, hand packing, finishing etc., complete with initial
191
lead upto 50 m and all lifts.(with no pin headers)( rubble stones : 0.33
cum/sqm)
Labour Component (including contractor's profit and Overheads)
sqm
194.40
sqm
sqm
sqm
44.10
35.40
sqm
184.60
13.50
sqm
sqm
sqm
44.10
204.60
104.90
24
Chapterwise item
S.NO
No.
1
IRR-CAW-8-2 A (New Item5 2011-12)
IRR-CAW-8-3
Item description
IRR-CAW-8-5
sqm
148.20
Providing and constructing 30 cm thick dry rubble stone pitching with pin
headers at 2 per sqm including cost of all materials, labour, hand packing,
193
finishing etc., complete with initial lead upto 50 m and all lifts.( rubble stones :
0.275 cum/sqm, Stone Chips : 0.045cum/sqm, Pin Headers 30cm : 2/sqm)
sqm
IRR-CAW-8-6
IRR-CAW-8-7
IRR-CAW-8-8
IRR-CAW-8-9
IRR-CAW-8-10
IRR-CAW-8-11
IRR-CAW-8-12
Rate
3
Providing and constructing 225 mmm thick dry rubble stone pitching
including cost of all materials, labour, hand packing, finishing etc., complete with
192
initial lead upto 50 m and all lifts.(with no pin headers)( rubble stones :
0.2475 cum/sqm) (For Maintenance Works)
Labour Component (including contractor's profit and Overheads)
IRR-CAW-8-4
Unit
sqm
94.40
213.60
sqm
sqm
44.10
245.50
sqm
sqm
125.90
322.10
sqm
sqm
62.00
368.20
sqm
sqm
188.80
456.50
sqm
sqm
75.50
361.30
sqm
sqm
16.80
291.80
sqm
sqm
44.10
310.30
sqm
sqm
62.00
521.10
sqm
sqm
72.00
632.90
25
Chapterwise item
S.NO
No.
1
IRR-CAW-8-13
IRR-CAW-8-14
Item description
3
Labour Component (including contractor's profit and Overheads)
Chapter IV
IRR-CCDW
4
sqm
sqm
96.20
sqm
sqm
56.50
64.50
sqm
32.60
IRR-CCDW-1-2
Rate
IRR-CCDW-1
IRR-CCDW-1-1
Unit
206
cum
212.30
cum
212.40
cum
93.00
cum
17.60
207
cum
310.70
cum
310.70
208
cum
120.00
cum
19.50
IRR-CCDW-1-5
cum
325.20
cum
241.30
IRR-CCDW-1-6
cum
cum
512.30
300.40
26
Chapterwise item
S.NO
No.
1
Item description
Unit
Rate
cum
991.10
IRR-CCDW-1-8
IRR-CCDW-2
IRR-CCDW-2-1
IRR-CCDW-2-2
IRR-CCDW-2-3
211
Providing and fixing 25 mm dia 2.50 m long cold twisted deformed steel
anchor rods with 1.25 m length driven into 32 mm dia hole drilled in bed rock
and remaining length embedded in concrete / masonry including cost of all
212
materials, machinery, labour, drilling and cleaning hole, driving anchor rod,
grouting hole with thick cement slurry etc., complete with initial lead upto 50 m
and all lifts.
Labour Component (including contractor's profit and Overheads)
IRR-CCDW-2-5
IRR-CCDW-2-6
Each
301.20
913.30
Each
185.70
IRR-CCDW-2-4
cum
kg
63.60
kg
kg
7.20
76.70
kg
cum
8.70
4219.80
cum
cum
1110.60
4196.90
cum
cum
1156.90
3964.00
cum
cum
1061.30
4039.00
27
Chapterwise item
S.NO
No.
1
IRR-CCDW-2-7
Item description
3
Labour Component (including contractor's profit and Overheads)
IRR-CCDW-2-8
IRR-CCDW-2-9
Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength
not less than 20 N / sq mm ) grade cement concrete using 20 mm down size
approved, clean, hard, graded aggregates for sub-structure / super- structure
works including cost of all materials, machinery, labour, formwork, scaffolding,
221
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing,
curing etc., complete with initial lead upto 50 m and all lifts.(Cement content:
330 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA :
0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
Labour Component (including contractor's profit and Overheads)
Unit
Rate
4
cum
cum
4536.30
cum
cum
1167.60
4971.30
cum
cum
1163.10
4968.80
cum
cum
1235.80
4725.30
cum
cum
1237.90
4322.70
cum
cum
cum
1150.50
6245.20
1493.90
28
Chapterwise item
S.NO
No.
1
Item description
Unit
Rate
cum
5634.20
IRR-CCDW-2-18
cum
cum
1365.20
4172.40
cum
cum
1074.60
3895.80
cum
cum
1055.90
4337.00
cum
cum
1074.60
5157.30
cum
cum
cum
1427.30
4999.40
1419.20
29
Chapterwise item
S.NO
No.
1
Item description
Unit
Rate
cum
4912.60
Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength
not less than 15 N / sq mm ) grade cement concrete using 80 mm down size
approved, clean, hard, graded aggregates for cast in-situ pipes including cost of
all materials, labour, machinery, formwork, cleaning, batching, mixing, placing in
position, levelling, vibrating, finishing, curing etc., complete with initial lead
IRR-CCDW-2-23 235
upto 50 m and all lifts. (Cement content: 250 kg / cum with use of super
plasticiser(0.4% by wt. of cement),CA : 0.98cum, Blending Ratio of CA-35:30:20:15, FA : 0.35 cum)
If water is to be brought from other place add only lead charges @ 500 ltr /
cum.
Labour Component (including contractor's profit and Overheads)
cum
cum
1312.80
5539.60
cum
cum
1359.10
4905.90
cum
cum
1272.70
4633.50
cum
cum
cum
1202.20
4604.50
1247.70
30
Chapterwise item
S.NO
No.
1
Item description
Unit
Rate
cum
7742.30
Providing and laying insitu M- 20 ( 28 days cube compressive strength not less
than 20 N / sqmm ) grade cement concrete using 20 mm down size approved,
clean, hard, graded aggregates for wearing coat including cost of all materials,
machinery, labour, formwork, cleaning, batching, mixing, placing in position in
alternate panels, levelling, compacting, finishing, curing, packing joints with
IRR-CCDW-2-26 238
asphalt mortar etc., complete with initial lead upto 50 m and all lifts. (Cement
content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),CA
: 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
If water is to be brought from other place add only lead charges @ 500 ltr /
cum.
Labour Component (including contractor's profit and Overheads)
Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength
not less than 20 N / sq mm ) grade cement concrete using 20 mm down size
approved, clean, hard, graded aggregates for troughs including cost of all
materials, machinery, labour, formwork, scaffolding, cleaning, batching, mixing,
placing in position,levelling, vibrating, finishing, curing etc., complete with initial
IRR-CCDW-2-27 239 lead upto 50 m and all lifts. (Cement content: 330 kg / cum with use of super
plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35,
FA : 0.45 cum)
If water is to be brought from other place add only lead charges @ 500 ltr /
cum.
Labour Component (including contractor's profit and Overheads)
IRR-CCDW-3
IRR-CCDW-3-1
Sinking RCC wells vertically for foundation of piers and abutments in all
kinds of soil, sand and soft rock by approved well sinking method including
cost of all materials, machinery, labour, kent - ledge arrangements, disposal of
240 excavated material as disposal of excavated material as directed etc., complete
with lead upto 50 m for disposal of excavated material.(diameter of well
6.00m) (Data adopted from MORTH)
IRR-CCDW-4
cum
1789.00
6708.70
cum
cum
1632.50
4238.60
cum
cum
1102.20
6066.20
cum
1514.30
IRR-CCDW-3-2
cum
*Rm
3654.20
*Rm
*Rm
*Rm
5191.60
cum
506.10
cum
1507.80
1972.00
96.70
MASONRY WORKS :
31
Chapterwise item
S.NO
No.
1
IRR-CCDW-4-1
Item description
Unit
Rate
cum
2074.90
IRR-CCDW-4-2
IRR-CCDW-4-3
IRR-CCDW-4-4
IRR-CCDW-4-5
IRR-CCDW-4-6
IRR-CCDW-4-7
IRR-CCDW-4-8
IRR-CCDW-4-9
cum
cum
692.10
2124.50
cum
cum
709.40
2590.20
cum
cum
795.80
2711.10
cum
sqm
916.80
108.40
sqm
sqm
81.70
102.10
sqm
sqm
81.70
154.10
sqm
sqm
115.40
146.80
sqm
sqm
115.40
218.80
sqm
sqm
sqm
154.10
206.50
154.10
32
Chapterwise item
S.NO
No.
1
IRR-CCDW-5
IRR-CCDW-5-1
Item description
Unit
Rate
sqm
581.00
IRR-CCDW-5-2
sqm
Providing and fixing 10 cm thick two line dressed burnt stone slabs for coping
set in CM 1: 6 proportion by volume with pointing to joints in CM 1 : 3 proportion
254 by volume including cost of all materials, machinery, labour, finishing, curing
etc., complete with initial lead upto 50 m and all lifts.(Cement content: 7.5 kg /
sqm, FA : 0.030 cum/sqm, Burnt stone slab 10 cm thick 1.05 sqm/ sqm)
sqm
IRR-CCDW-5-4
IRR-CCDW-5-5
Providing and laying insitu M-15 ( 28 days cube compressive strength not less
than 15 N / sqmm ) grade cement concrete using 20 mm down size approved
clean, hard, graded aggregates for coping slab including cost of all materials,
machinery, labour, formwork, cleaning surface, batching, mixing, placing in
255
position, levelling, compacting, finishing, curing etc., complete with initial lead
upto 50 m and initial lift upto 3 m. (Cement content: 300 kg / cum with use of
super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA-65:35, FA : 0.45 cum)
Labour Component (including contractor's profit and Overheads)
Providing and constructing protective railing consisting of in-situ railing posts
of size 15 x 15 cm at bottom, 10 x 10 cm at top and 75 cm height at 2 m centre
to centre in M-20 grade concrete using 20 mm down size graded aggregates and
with each post reinforced by 4 Nos. of 8 mm dia main bars embedded in kerb
256
concrete for a depth of 40 cm and 5 Nos. of 6 mm dia. stirrups including fixing 3
rows of 40 mm dia. GI pipes with one coat of red oxide primer and two coats of
synthetic enamel paint, cost of all materials, machinery, labour, formwork,
finishing, curing etc., complete with lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)
IRR-CCDW-6
IRR-CCDW-6-1
Laying and jointing 300 mm dia. NP- 2 class or IRC standard hume pipes in
CM 1 : 2 proportion by volume including cost of all materials ( excluding pipes
257 and collars ), machinery, labour, aligning, packing joints with hemp, finishing,
curing etc., complete with initial lead upto 50 m and all lifts.(Cement content:
9.9 kg / joint, FA : 0.01cum/joint, Hemp Yarn : 0.091kg/joint)
Laying and jointing 450 mm dia. NP- 2 class or IRC standard hume pipes in
CM 1 : 2 proportion by volume including cost of all materials ( excluding pipes
258 and collars ), machinery, labour, aligning, packing joints with hemp, finishing,
curing etc., complete with initial lead upto 50 m and all lifts.(Cement content:
17.4 kg / joint, FA : 0.022cum/joint, Hemp Yarn : 0.127kg/joint)
Labour Component (including contractor's profit and Overheads)
IRR-CCDW-6-3
167.00
717.30
sqm
303.20
892.80
sqm
cum
478.80
5853.00
cum
Rm
1436.30
1362.80
Rm
158.50
IRR-CCDW-6-2
sqm
Providing and fixing 10 cm thick one line dressed burnt stone slabs for coping
set in CM 1: 6 proportion by volume with pointing to joints in CM 1 : 3 proportion
253 by volume including cost of all materials, machinery, labour, finishing, curing
etc., complete with initial lead upto 50 m and all lifts.(Cement content: 7.5 kg /
sqm, FA : 0.030 cum/sqm, Burnt stone slab 10 cm thick 1.05 sqm/ sqm)
Labour Component (including contractor's profit and Overheads)
IRR-CCDW-5-3
Laying and jointing 600 mm dia. NP- 2 class or IRC standard hume pipes in
CM 1 : 2 proportion by volume including cost of all materials ( excluding pipes
259 and collars ), machinery, labour, aligning, packing joints with hemp, finishing,
curing etc., complete with initial lead upto 50 m and all lifts.(Cement content:
24.8 kg / joint, FA : 0.025cum/joint, Hemp Yarn : 0.22kg/joint)
Labour Component (including contractor's profit and Overheads)
Joint
281.30
Joint
Joint
221.70
326.70
Joint
Joint
Joint
221.70
423.40
275.10
33
Chapterwise item
S.NO
No.
1
IRR-CCDW-6-4
Item description
Unit
Rate
Joint
463.30
Laying and jointing 700 mm dia. NP- 2 class or IRC standard hume pipes in
CM 1 : 2 proportion by volume including cost of all materials ( excluding pipes
260 and collars ), machinery, labour, aligning, packing joints with hemp, finishing,
curing etc., complete with initial lead upto 50 m and all lifts.(Cement content:
32.1 kg / joint, FA : 0.031cum/joint, Hemp Yarn : 0.25kg/joint)
Labour Component (including contractor's profit and Overheads)
IRR-CCDW-6-5
Laying and jointing 800 mm dia. NP- 2 class or IRC standard hume pipes in
CM 1 : 2 proportion by volume including cost of all materials ( excluding pipes
261 and collars ), machinery, labour, aligning, packing joints with hemp, finishing,
curing etc., complete with initial lead upto 50 m and all lifts.(Cement content:
39.6 kg / joint, FA : 0.039cum/joint, Hemp Yarn : 0.31kg/joint)
Labour Component (including contractor's profit and Overheads)
IRR-CCDW-6-6
Laying and jointing 900 mm dia. NP- 2 class or IRC standard hume pipes in
CM 1 : 2 proportion by volume including cost of all materials ( excluding pipes
262 and collars ), machinery, labour, aligning, packing joints with hemp, finishing,
curing etc., complete with initial lead upto 50 m and all lifts.(Cement content:
44.6 kg / joint, FA : 0.045cum/joint, Hemp Yarn : 0.34kg/joint)
Labour Component (including contractor's profit and Overheads)
IRR-CCDW-6-7
Laying and jointing 1000 mm dia. NP- 2 class or IRC standard hume pipes in
CM 1 : 2 proportion by volume including cost of all materials ( excluding pipes
263 and collars ), machinery, labour, aligning, packing joints with hemp, finishing,
curing etc., complete with initial lead upto 50 m and all lifts.(Cement content:
49.5 kg / joint, FA : 0.05cum/joint, Hemp Yarn : 0.377kg/joint)
Labour Component (including contractor's profit and Overheads)
IRR-CCDW-6-8
Laying and jointing 1100 mm dia. NP- 2 class or IRC standard hume pipes in
CM 1 : 2 proportion by volume including cost of all materials ( excluding pipes
264 and collars ), machinery, labour, aligning, packing joints with hemp, finishing,
curing etc., complete with initial lead upto 50 m and all lifts.(Cement content:
56.9 kg / joint, FA : 0.058cum/joint, Hemp Yarn : 0.415kg/joint)
Labour Component (including contractor's profit and Overheads)
IRR-CCDW-6-9
Laying and jointing 1200 mm dia. NP- 2 class or IRC standard hume pipes in
CM 1 : 2 proportion by volume including cost of all materials ( excluding pipes
265 and collars ), machinery, labour, aligning, packing joints with hemp, finishing,
curing etc., complete with initial lead upto 50 m and all lifts.(Cement content:
66.8 kg / joint, FA : 0.069cum/joint, Hemp Yarn : 0.453kg/joint)
Labour Component (including contractor's profit and Overheads)
IRR-CCDW-7
IRR-CCDW-7-1
Providing rubble / boulder and sand filling behind abutment and return
266 walls in layers including cost of all materials, machinery, labour, watering,
ramming etc., complete with initial lead upto 50 m and initial lift upto 3 m.
Providing and filling murrum / gravely soil ( CNS soil ) for foundation or
around pipes including breaking clods, spreading in layers of 10 to 15 cm,
267
watering, compaction by earth masters to achieve density control of not less
than 95 percent etc., complete with lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)
IRR-CCDW-7-3
Joint
275.10
561.30
Joint
Joint
328.30
590.70
Joint
Joint
328.30
653.20
Joint
Joint
362.00
695.50
Joint
Joint
362.00
824.40
Joint
434.90
IRR-CCDW-7-2
Joint
Providing and filling murum / gravely soil ( CNS soil ) for foundation or
above pipes including breaking clods, spreading in layers of 10 to 15 cm,
268
watering, compaction by power roller to achieve density control of not less
than 98 percent etc., complete with lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)
cum
713.40
cum
cum
194.90
391.80
cum
cum
cum
245.40
262.70
97.60
34
Chapterwise item
S.NO
No.
1
IRR-CCDW-7-4
IRR-CCDW-7-5
Chapter V
IRR-GAW
IRR-GAW-1-1
IRR-GAW-1-2
IRR-GAW-1-3
Item description
3
Providing and fixing one line dressed 111x35x25 cm thick IRC standard
kilometre stone in cement concrete M-10 grade with 40 mm down size
aggregates including excavating pit of size 70x45x40 cm, embedding the stone
269 by 30 cm in concrete, providing 2 coats synthetic enamel paint of approved
quality and colour to exposed surfaces and lettering as directed, cost of all
materials, labour, finishing, curing etc., complete with initial lead upto 50 m and
all lifts.
Labour Component (including contractor's profit and Overheads)
Providing and fixing one line dressed 65x15x10 cm thick IRC standard
hectometre stone in cement concrete M-10 grade with 40 mm down size
aggregates including excavating pit of size 50x45x40 cm, embedding the stone
270 by 30 cm in concrete, providing 2 coats synthetic enamel paint of approved
quality and colour to exposed surfaces and lettering as directed, cost of all
materials, labour, finishing, curing etc., complete with initial lead upto 50 m and
all lifts.
Labour Component (including contractor's profit and Overheads)
Rate
Each
1323.70
Each
Each
413.30
945.50
Each
350.60
IRR-GAW-1-4
Unit
RADIAL GATES
Walk way(cat walk)
Design, fabrication, supply, erection and commissioning of 1 metre wide
walkway connecting spillway piers / abutments at trunnion platform level
274 including cost of all materials, machinery, labour, cutting, etc., complete as per
specifications and approved drawings
(without painting on sand-blasted or mechanical cleaning surfaces which are added
extra as per scedule of rates under items in this chapter and add as applicable
separately)
Labour Component (including contractor's profit and Overheads)
tonne
149350.80
tonne
tonne
40637.80
134658.00
tonne
tonne
capacity
30982.70
42629.40
tonne
capacity
Rm
Rm
2471.30
101753.40
29505.30
35
Chapterwise item
S.NO
No.
1
IRR-GAW-2-1
Item description
Unit
Rate
tonne
164527.20
tonne
48353.90
vertical lift gates and stop log gate elements ( SLIDING GATES)
IRR-GAW-2-2
IRR-GAW-2-3
IRR-GAW-2-4
IRR-GAW-2-5
IRR-GAW-2-6
tonne
137213.20
tonne
tonne
35746.40
120072.60
tonne
tonne
capacity
17970.00
237820.70
tonne
capacity
Rm
18145.40
7320.50
Rm
tonne
tonne
444.70
135722.10
33808.20
36
Chapterwise item
S.NO
No.
1
IRR-GAW-2-7
Item description
Unit
Rate
tonne
capacity
71620.70
IRR-GAW-2-8
IRR-GAW-2-9
IRR-GAW-2-10
IRR-GAW-2-11
tonne
capacity
tonne
2354.80
115727.40
tonne
tonne
capacity
30570.70
35397.90
tonne
capacity
tonne
capacity
997.80
33455.00
tonne
capacity
tonne
capacity
tonne
capacity
4508.50
76007.60
6040.10
37
Chapterwise item
S.NO
No.
1
IRR-GAW-2-12
New Item 201415-2
IRR-GAW-2-13
New Item 201415-3
IRR-GAW-2-14
New Item 201415-4
IRR-GAW-3
IRR-GAW-3-1
IRR-GAW-3-2
Item description
Unit
Rate
Tonne
124326.20
IRR-GAW-3-4
Tonne
22515.50
83401.00
Tonne
Tonne
18842.40
198547.40
Tonne
9581.20
IRR-GAW-3-3
Tonne
sqm
431.70
sqm
sqm
84.40
499.40
sqm
sqm
180.00
350.60
sqm
sqm
sqm
138.20
432.10
180.00
38
Chapterwise item
S.NO
No.
1
IRR-GAW-3-5
IRR-GAW-4
IRR-GAW-4-1
Item description
Unit
Rate
sqm
383.00
HOISTS:machineryCOMPONENTS-painting hoist machinery, on sand blasted surfaces with one coats of zinc
293
phosphate primer (airless spray preferred) 50microns/coat and three coats of
aluminium paint or synthetic enamel , 25 microns/coat cost of all materials,
labour, scaffolding etc., complete with all leads and all lifts
Labour Component (including contractor's profit and Overheads)
IRR-GAW-4-3
IRR-GAW-4-4
Chapter VI
IRR-PMW
IRR-PMW-1
IRR-PMW-1-1
IRR-PMW-1-2
IRR-PMW-1-3
IRR-PMW-1-4
180.00
IRR-GAW-4-2
sqm
sqm
568.60
sqm
180.00
sqm
401.70
sqm
sqm
180.00
477.80
sqm
121.40
Removing stumps, tree roots, roots of bamboo cluster etc., with girth above
300 1.50 m and upto 3.0 m including excavation, stacking the materials neatly and
levelling the area etc., complete with initial lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)
sqm
1.20
sqm
sqm
1.30
1.90
sqm
Each
1.90
43.20
Each
Each
Each
43.20
97.30
97.30
39
Chapterwise item
S.NO
No.
1
IRR-PMW-1-5
Item description
Unit
Rate
Each
311.20
Removing stumps, tree roots, roots of bamboo cluster etc., with girth above
301 3.0 m and upto 5.0 m including excavation, stacking the materials neatly and
levelling the area etc., complete with initial lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)
IRR-PMW-1-6
IRR-PMW-1-7
IRR-PMW-1-8
IRR-PMW-1-9
IRR-PMW-1-10
IRR-PMW-1-11
IRR-PMW-1-12
IRR-PMW-1-13
IRR-PMW-1-14
302
303
Cutting and removing jauliflora bushes upto 1.5 m girth excluding removal
304 of stumps and including burning or disposing off the materials as directed with
initial lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)
Cutting and removing jauliflora bushes above 1.5 m upto 3.0 m girth
305 excluding removal of stumps and including burning or disposing off the materials
as directed with initial lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)
Cutting trees above 0.3 m and upto 0.6 m girth excluding removal of stumps
306 and including stacking the materials neatly as directed with initial lead upto 50
m and all lifts.
Labour Component (including contractor's profit and Overheads)
Cutting trees above 0.6 m and upto 1.2 m girth excluding removal of stumps
307 and including stacking the materials neatly as directed with initial lead upto 50
m and all lifts.
Labour Component (including contractor's profit and Overheads)
Cutting trees above 1.2 m and upto 1.8 m girth excluding removal of stumps
308 and including stacking the materials neatly as directed with initial lead upto 50
m and all lifts.
Labour Component (including contractor's profit and Overheads)
Cutting trees above 1.8 m and upto 2.4 m girth excluding removal of stumps
309 and including stacking the materials neatly as directed with initial lead upto 50
m and all lifts.
Labour Component (including contractor's profit and Overheads)
Cutting trees above 2.4 m and upto 3.0 m girth excluding removal of stumps
310 and including stacking the materials neatly as directed with initial lead upto 50
m and all lifts.
Labour Component (including contractor's profit and Overheads)
Each
Each
311.20
55.30
Each
Each
55.30
12.60
Each
Each
12.60
12.20
Each
Each
12.20
24.40
Each
Each
24.40
82.70
Each
Each
79.60
289.30
Each
Each
278.60
578.60
Each
Each
557.20
1157.10
Each
Each
1114.40
1872.50
Each
1787.00
IRR-PMW-1-16
IRR-PMW-2
IRR-PMW-2-1
311
312
Additional rate for cutting tree for every 0.5 m increase in girth of tree beyond 3
m.
Labour Component (including contractor's profit and Overheads)
Cutting and burning or disposing off Apu / Jondu from marshy areas as
directed with initial lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)
656.40
Each
sqm
630.80
4.50
sqm
4.40
PRELIMINARY WORKS :
Earthwork excavation for trial pits / borrow pits and other investigation works
313 in all kinds of soil including boulders upto 30 cm dia and disposing off
excavated soil as directed with lead upto 10 m and lift upto 3 m.
Labour Component (including contractor's profit and Overheads)
IRR-PMW-2-2
Each
Earthwork excavation for trial pits / borrow pits and other investigation works
314 in soft rock including disposing off the excavated rock as directed with lead
upto 10 m and lift upto 3 m.
Labour Component (including contractor's profit and Overheads)
cum
222.90
cum
cum
cum
222.90
312.60
312.70
40
Chapterwise item
S.NO
No.
1
IRR-PMW-2-3
IRR-PMW-2-4
Item description
3
Conducting geophysical investigation studies by electrical resistivity
method in stages of 5m for sub-surface details such as depth of formations,
shear zones, classification of strata, depth of water table etc., including cost of
315
all materials, equipments, labour, analysing and reporting the details of field
studies conducted etc., complete excluding cost of transportation
arrangements.
Labour Component (including contractor's profit and Overheads)
Drilling 80 mm dia hole through over-burden using casing shoe bit vertical or
inclined upto 10 degrees to vertical as directed including cost of all materials,
machinery, labour, water charges, reaming, collection of wash samples at
suitable intervals, logging and lebelling, supplying honne wood core box, fixing
casing pipes ( excluding cost of casing pipes ) etc., complete for depth
316 upto 30 m from surface.
1. For driiling through over-burden beyond 30 m from surface increase the rate
per Rm by 10 percent.
2. For providing HDPE or light black MS casing pipe add the cost of pipe per
Rm.
Labour Component (including contractor's profit and Overheads)
IRR-PMW-2-5
Drilling 76 mm dia ( NX ) core hole in hard rock using diamond core bit
vertical / inclined upto 10 degree to vertical as directed including cost of all
materials, machinery, labour, water charges, collection of core samples, logging
and lebelling, supplying honne wood core box and redrilling in case of collapse of
317 sides etc., complete for depth upto 30 m from surface.
1. For driiling in hard rock beyond 30 m upto 60 m from surface increase the rate
per Rm by 25 percent.
2. For driiling in hard rock beyond 60 m upto 90 m from surface increase the rate
per Rm by 40 percent.
Labour Component (including contractor's profit and Overheads)
IRR-PMW-2-5-A
(New Item 201415)-5
Drilling 76 mm dia ( NX ) core hole in all types of rocks (other than Hard
Rock) including Masonry/CC (where drilling is not possible by casing
shoe) using diamond core bit vertical / inclined upto 10 degree to vertical as
directed including cost of all materials, machinery, labour, water charges, and
318 redrilling in case of collapse of sides etc., complete for depth upto 30 m from
surface for Primary and Secondary Holes
1. For drilling in all types of rocks (other than hard rock) including masonry/CC
beyond 30 m upto 60 m from surface increase the rate per Rm by 25 percent.
2. For drilling in all types of rocks (other than hard rock) including masonry/CC
beyond 60 m upto 90 m from surface increase the rate per Rm by 40 percent.
Labour Component (including contractor's profit and Overheads)
IRR-PMW-2-5-B
(New Item 201415)-6
Drilling 76 mm dia ( NX ) core hole in all types of rocks (other than Hard
Rock) including Masonry/CC (where drilling is not possible by casing
shoe) using diamond core bit vertical / inclined upto 10 degree to vertical as
directed including cost of all materials, machinery, labour, water charges,
collection of core samples, logging and lebelling, supplying honne wood core box
319
and redrilling in case of collapse of sides etc., complete for depth upto 30 m
from surface for Test Holes
1. For drilling in all types of rocks (other than hard rock) including masonry/CC
beyond 30 m upto 60 m from surface increase the rate per Rm by 25 percent.
2. For drilling in all types of rocks (other than hard rock) including masonry/CC
beyond 60 m upto 90 m from surface increase the rate per Rm by 40 percent.
Labour Component (including contractor's profit and Overheads)
Unit
Rate
stage
283.90
stage
Rm
218.10
1162.20
Rm
Rm
390.30
5942.70
Rm
Rm
1553.00
3809.60
Rm
Rm
Rm
926.60
4599.60
927.20
41
Chapterwise item
S.NO
No.
1
IRR-PMW-2-6
Item description
Unit
Rate
Rm
5781.60
Drilling 47 mm (BX )dia core hole in hard rock using diamond core bit vertical
/ inclined upto 10 degree to vertical as directed including cost of all materials,
machinery, labour, water charges,collection of core samples,logging, lebelling,
supplying honne wood core box and redrilling in case of collapse of sides etc.,
320 complete for depth upto 30 m from surface.
1. For drilling in hard rock beyond 30 m upto 60 m from surface increase the rate
per Rm by 25 percent.
2. For drilling in hard rock beyond 60 m upto 90 m from surface increase the rate
per Rm by 40 percent.
Labour Component (including contractor's profit and Overheads)
IRR-PMW-2-6-A
(New Item 201415)-7
Drilling 47 mm (BX )dia core hole in all types of rocks (other than Hard
Rock) including Masonry/CC (where drilling is not possible by casing shoe)
using diamond core bit vertical / inclined upto 10 degree to vertical as directed
321 including cost of all materials, machinery, labour, water charges, and redrilling
in case of collapse of sides etc., complete for depth upto 30 m
1. For drilling in all types of rocks (other than hard rock) including masonry/CC
beyond 30 m upto 60 m from surface increase the rate per Rm by 25 percent.
2. For drilling in all types of rocks (other than hard rock) including masonry/CC
beyond 60 m upto 90 m from surface increase the rate per Rm by 40 percent.
Labour Component (including contractor's profit and Overheads)
IRR-PMW-2-7
IRR-PMW-2-8
NOTE:
IRR-PMW-2-9
IRR-PMW-3-1
IRR-PMW-3-2
IRR-PMW-3-3
Rm
1553.00
3580.90
Rm
Each
926.60
136.90
Each
Rm
Each
103.90
452.60
308.40
4.00
5625.10
Each
2716.10
MAINTENANCE WORKS :
Removing dry stone rock-toe / rivetment and filter layers below rock-toe/
325 rivetment including stacking all materials separately as directed with initial
lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)
Re-constructing 60 cm thick hand packed rough stone revetment with
through stones at 1.5 m c / c over a backing of 45 cm thick graded filter media
consisting of sand, 10 mm and 40 mm size graded aggregates satisfying filter
criteria laid in layers of 15 cm thick each using sand from approved quarry and
326
stones and filter aggregates obtained from revetment removed for reconstruction including cost of all machinery, labour, laying filter and stones to
specified slopes, wedging with chips, finishing etc. complete with initial lead
upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)
Re-constructing dry rubble rock-toe and filter media for rock-toe consisting
of sand 20 mm and 80 mm size graded aggregates satisfying filter criteria laid in
layers of 15 cm thick each using sand from approved quarry and stones and filter
327
aggregates obtained from rock-toe removed for re-construction including cost of
all machinery, labour, laying filter and stones to specified slopes, wedging with
chips, finishing etc. complete with initial lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)
cum
180.20
cum
sqm
180.20
215.40
sqm
cum
cum
134.90
244.80
193.20
42
Chapterwise item
S.NO
No.
1
IRR-PMW-3-4
IRR-PMW-3-5
IRR-PMW-3-6
IRR-PMW-3-7
IRR-PMW-3-8
Item description
3
Removing and resetting disturbed Yarguntla / Shahabad / Talikot / PCC /
328 Other types of slab lining set in CM 1 : 3 including flush cement mortar
pointing in CM 1 : 3 with lead upto 50 m and all lifts.
Labour Component (including contractor's profit and Overheads)
Removing and resetting disturbed dry rubble / khandki stone pitching 25 to
329 45 cm thick including packing, wedging, finishing etc., complete with all leads
and lifts.
Labour Component (including contractor's profit and Overheads)
Removing and refixing disturbed chainage / demarcation / hectometre /
330 guard stones including excavation, back filling etc., complete with all leads and
lifts.
Labour Component (including contractor's profit and Overheads)
Removing and refixing disturbed km stone / sign board / hecto-metre stone
etc., including excavation, back filling with available stuff after refixing, forming
331
base platform of size 90 x 90 x 7.5 cm including watering, ramming etc complete
with all leads and lifts.
Labour Component (including contractor's profit and Overheads)
Providing impervious hearting for breached / damaged portion of
embankment with soil from approved borrow areas in layers of 10 to 15 cm
before compaction including cost of all materials, machinery, labour, all
332 operations such as collection of soil, sorting out, spreading soil to specified
thickness, breaking clods, sectioning, watering, compacting each layer to density
control of not less than 98 percent or as stipulated by rolling or by using
mechanical tampers etc., complete with initial lead upto 1 km and all lifts.
Labour Component (including contractor's profit and Overheads)
IRR-PMW-3-9
IRR-PMW-3-10
IRR-PMW-3-11
IRR-PMW-3-12
IRR-PMW-3-13
IRR-PMW-3-14
Repairing rain cuts / resectioning canal slopes to required lines and grades
336 as directed using available soil including dressing, clod breaking, packing,
tamping etc., complete with all leads and lifts.
Labour Component (including contractor's profit and Overheads)
Cleaning drainage gallery, adits, instrumentation galleries etc., by scrubbing
/ brushing including chiselling and removing leached lime deposit and disposing
337
off all the waste material out side adits in specified location etc., complete with
all leads and lifts.
Labour Component (including contractor's profit and Overheads)
Cleaning dam parapet inner face and top using oxalic acid and water by
338 scrubbing / brushing and washing to remove all surface coatings etc., complete
.
Labour Component (including contractor's profit and Overheads)
Unit
Rate
sqm
52.50
sqm
sqm
46.50
48.00
sqm
Each
48.00
60.80
Each
Each
60.80
136.80
Each
cum
136.80
185.60
cum
cum
27.80
212.30
cum
cum
33.20
168.60
cum
cum
26.60
192.10
cum
sqm
31.40
3.10
sqm
Rm
3.10
36.40
Rm
Rm
Rm
28.00
32.90
20.20
43
Chapterwise item
S.NO
No.
1
Item description
Unit
Rate
cum
134.50
IRR-PMW-3-15
IRR-PMW-3-16
IRR-PMW-3-17
IRR-PMW-3-18
IRR-PMW-3-19
IRR-PMW-3-20
IRR-PMW-3-21
Excavation and removal of silt and silt mixed with sand from canal bed in
dry condition including disposing off the same in spoil bank or on the canal
339
embankment in layers as directed etc., complete with initial lead upto 50 m
and all lifts.
Labour Component (including contractor's profit and Overheads)
Excavation and removal of silt or silt mixed with sand in slussy condition
from canal bed including disposing off the same in spoil bank or on the canal
340
embankment in layers as directed etc., complete with initial lead upto 50 m and
all lifts.
Labour Component (including contractor's profit and Overheads)
cum
cum
134.50
168.20
cum
cum
168.20
95.50
cum
cum
13.10
46.10
6.40
IRR-PMW-3-26
New Item 201415-8
COM-MWRK
cum
6.10
cum
1.10
349
Sqm
5.40
Sqm
7.40
Sqm
5.00
Sqm
4.20
Sqm
5.00
Sqm
1.60
Sqm
397.20
Sqm
145.92
New extra items-- common item for all earth works using only manual labour for all other works
44
Chapterwise item
S.NO
No.
1
COM-MWRK-1
COM-MWRK-2
COM-MWRK-3
COM-MWRK-4
Item description
Unit
Rate
3
without involving contractors
cum
98.30
cum
118
cum
221.80
cum
440.30
(Manual)Excavation in all kinds of soil including boulders upto 0.30 m dia. for
foundations of canal cross drainage and other appurtenant structures and
placing excavated stuff neatly in specified dump area or disposing off the same
351
as directed etc., complete with initial lead upto 10 m and initial lift upto 1.5 m.
(WIthout involving the contractors for specified works )
With 3 Cum per day output
(Manual)Excavation in all kinds of soil/HDR including boulders upto 0.30 m
dia. for foundations of canal cross drainage and other appurtenant structures
and placing excavated stuff neatly in specified dump area or disposing off the
352
same as directed etc., complete with initial lead upto 10 m and initial lift upto
1.5 m. (WIthout involving the contractors for specified works )
With 2.5 Cum per day output
45
COM-LDLFT
Abstract
LEAD, LIFT, LOADING AND UNLOADING CHARGES FOR MATERIALS
FOR THE YEAR: 2014-15
COM-LDLFT
1 For total lead upto 150 m ( including initial lead ) lead charges by head load only shall be adopted irrespective of
mode of conveyance.
2 For total lead exceeding 150 m conveyance by mechanical means only shall be adopted irrespective of
mode of conveyance.
3 The rates for loading at quarry including idle hire charges of trucks and hire charges per for each kilometer and
upto 5 km are cumulative and inclusive of total charges for preceding lead.
4 Unless otherwise specified lead charges for Earth / Sand / Gravel / Aggregates and Stones are for loose volume and
not for compacted or in-situ volume.
5 The rates for lift charges,lead charges hire cahrges are cumulative are cumulative and inclusive of rates for preceding
lift,load and hire charges
6 Lift charges are not payable where conveyance of materials is by mechanical means to final placing point.
7 Loading and unloading charges are not payable for conveyance by head load.
8 Loading charges are not payable for conveyance by mechanical means for disposal of excavated materials beyond
initial lead of 50 m wherever specified.
9 Loading and unloading charges are not payable for conveyance by mechanical means for disposal of excavated
materials beyond initial lead of 1 km wherever specified.
10 The rates for unloading of materials except earth, sand, gravel, coarse aggregate, rubble, size stone and cut stone
are inclusive of stacking.
11 Hire charges are per 1KM for tippers and trucks for tranport of materials from work site
to dump yard and other places are cumulative& includes previous km upto 5 kms
12 The lead & lift charges are inclusive of contractor's profit and overhead charges of 14%
13 During the BoCE meeting held on 24-05-2014, it is observed that in some of the estimates, Lead
Charges are being added directly to the material basic rates for arriving the finished item rate. In view
of that, the BoCE has instructed to see that while arriving the finished item rate, the lead
charges are to be added to the material basic rates only after deducting the provision of
"Contractor's Profit and Overhead charges"
COM-LDLFT-1 A. (Lead) Conveyance Charges for materials by head load
FOR THE YEAR: 2014-15
Sl No.
Total distance
( Total lead includes
initial lead )
Earth / Sand
/Gravel /
Murrum/ Lime/
Surki/ Size
stone / Cut
stone Rubble /
Coarse
3
1
2
3
initial lead
48.00
96.10
PCC slab/
Shahbad slab
Cement /
Reinforce-ment / CC block/
steel Str steel BS slab/ LateRs / tonne
rite / Wood
Rs / cum
4
initial lead
28.00
56.10
initial lead
61.10
122.30
Notes: 1. No loading or unloading charges are admissible for conveyance by head load.
2. For total lead exceeding 150 m conveyance charges by mechanical means only shall
be adopted irrespective of mode of conveyance.
3.The Lead & Lift Charges are inclusive of 14% Contractor's Profit and Over Head Charges
COM-LDLFT-2 B.( Lead) Conveyance charges for machinery per kilometer for transporting materials
by tippers and trucks excluding loading, unloading and idle hire charges of machinery
( No loading and unloading charges allowed for machinery loading and unloading )
Sl No.
Distance
(Lead)
charges for (Lead) charges
(Lead) charges
for trucks and
trucks and
(Lead) charges
(Lead) charges
for trucks and
tippers per
tippers for
for trucks and
for trucks and
tippers for
cu.meter for
Cement/
tippers for Earth
tippers per
Rubble/Size
PCC slabs/
Steel/ RCC
/ Sand /Gravel /
cu.meter for
stones/ Cut
Shahabad
poles/ AC &
Murrum/ Lime/
water/ 1000
Stones/ Coarse
slabs/ CC &
GI sheets/
Surki/ per
litres
aggregate per
Laterite blocks/
Packed
cu.meter
cu.meter
materials/tonn Wood/ cum
e
3
4
5
6
7
(Lead)
charge
s for
trucks
per
1000
Nos. of
Bricks
8
46
1
2
3
4
5
Lead upto 1 km
Lead upto 2 km
Lead upto 3 km
Lead upto 4 km
Lead upto 5 km
31.50
44.10
58.90
71.50
84.10
30.40
42.60
58.90
71.50
84.10
19.00
26.60
36.80
44.70
52.60
44.70
62.60
86.60
105.10
123.70
18.80
26.30
35.00
42.50
50.00
50.70
71.00
94.60
114.90
135.20
7.50
20.30
6.30
16.90
COM-LDLFT-3 C. LOADING AND UNLOADING CHARGES BY MANUAL MEANS (idle hire charges of trucks are not added)
Sl No.
Description of item
Earth / Sand
Rubble/ size
/Gravel
stone/ cut stone/
Murrum/ / Surki/
Coarse
aggregate,Lime
Rs / cum
in Rs/cum
cement in
Rs/tonne
steel in
Rs./tonne
1
2
3
4
5
6
1
Loading
16.00
32.00
52.80
63.30
2
Unloading
8.00
16.00
52.80
63.30
Note:The Lead & Lift Charges are inclusive of 14% Contractor's Profit and Over Head Charges
brick work
Rs/1000 No
7
44.00
44.00
COM-LDLFT-4 D. LOADING AND UNLOADING CHARGES BY MANUAL MEANS (including idle hire charges of trucks )
Sl No.
Description of item
Earth / Sand
Rubble/ size
/Gravel
stone/ cut stone/
Murrum/ / Surki/
Coarse
aggregate,Lime
Rs / cum
in Rs/cum
cement in
Rs/tonne
steel in
Rs./tonne
brick work
Rs/1000 No
1
2
3
4
5
6
7
1
Loading
108.20
124.20
154.20
164.70
211.30
2
Unloading
38.60
62.10
154.20
164.70
211.30
Note:The Loading & Unloading Charges are inclusive of 14% Contractor's Profit and Over Head Charges
47
COM-LDLFT-5 E. LOADING AND UNLOADING CHARGES BY MECHANICAL MEANS (including idle hire charges of trucks)
Sl No.
Description of item
Earth / Sand
Rubble/ size
/Gravel
stone/ cut stone/
Murrum/ / Surki/
Coarse
aggregate,Lime
Rs / cum
in Rs/cum
1
2
3
4
1
Loading
52.50
105.00
2
Unloading
15.90
15.90
Note:The Loading & Unloading Charges are inclusive of 14% Contractor's Profit and Over Head Charges
COM-LDLFT-6 F. LIFT CHARGES FOR MATERIALS BY HEAD LOAD
Sl No.
Total lift
( Total lift includes
initial lift )
Earth / Sand
/Gravel
Murrum/ Lime/
Surki/
Size stone / Cut
stone
Rubble / Coarse
aggregate
Rs / cum
Cement /
Reinforcement steel
Str steel
Rs / tonne
PCC slab/
Shahbad
slab / CC
block/ BS
slab / Laterite
/ Wood
Rs / cum
Initial lift
Initial lift
Initial lift
5.60
4.10
7.50
Note:The Lead & Lift Charges are inclusive of 14% Contractor's Profit and Over Head Charges
48
Chapter - I
DAM AND ALLIED WORKS - Standard Data
3. The Leads for Steel and Cement shall be from the nearest market place to the Project area
4. For earth/rockfill embankments wherever initial lead of 1km is considered in the basic rate, the additional lead charges are to be added as follows:
Additional lead charges for Earth, Murrum etc., shall be worked out for total lead involved and 1 km lead charges included in basic rate shall be deducted from total
lead charges. No loading and unloading charges shall be allowed for any item. (same as above)
Example:
Total lead for earth from approved borrow area :
15 Km
Initial lead included in the basic rate in the SR :
1 Km
Additional lead charges : Lead charges for 5 km
Rs.
84.10
Lead charges for next 10 km
Rs.
126
Total lead charges for 15 km /cum
Rs.
210.10
Less 1 km initial lead charges /cum Rs.
31.50 (-)
Net additional lead charges / cum
Rs.
178.60
5. The initial lead up to 50 m as mentioned in some standard data items is meant for manual lead within the working area. For conveyance of materials, the
lead required from quarry/Borrow area/ Dump Area to worksite shall be added to the data without deducting the 50 m initial lead charges
DAW - Work Items
IRR-DAW-1
IRR-DAW-1-1
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
Unit
Quantity
NIL
0.00
0.00
Rs:
UNIT
880 cum
Rate
Amount
in Rs.
in Rs
0.00 0.00
0.00 0.00
0.00
B. MACHINERY:
Sl No
1
2
Description
Shovel 0.85 cum capacity
Fuel / Energy charges
Dumpers 5 cum capacity 6 Nos
Unit
Hour
Hour
Hour
Quantity
8.00
8.00
48.00
Rate
Amount
in Rs.
in Rs
1706.60 13652.80
937.80 7502.40
580.70 27873.60
48
48.00
8.00
8.00
429.70
446.70
322.20
Rs:
20625.60
3573.60
2577.60
75805.60
204.10
195.90
153.10
370.00
295.00
Rs:
Amount
in Rs
1632.80
9403.20
1224.80
370.00
4720.00
17350.80
C. LABOUR:
Sl No
1
2
3
4
5
Description
Unit
Quantity
Hour
Hour
Hour
Day
Day
Total cost of Labour
labour component/unit qty
19.70
Add contractor's profit and overhead charges
14% 2.80
labour component/unit qty (including contractor's profit)
22.50
Rate
in Rs.
8.00
48.00
8.00
1.00
16.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:
Total
D.Add for contractor's profit and overheads on (A+B+C)
Total cost for
880.00
Rate per
cum (A+B+C+D)/880
IRR-DAW-1-2
14%
cum
0.00
75805.60
17350.80
93156.40
13041.9
106198.30
120.70
Excavation for foundation in ordinary rock (including HDR) without blasting including
boulders above 0.3 m upto 0.6 m dia for dam, spillway, intake structure and
other appurtenant works and placing the excavated material neatly in dump
area or disposing off the same as directed etc., complete with initial lead
upto 1 km and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
Particulars
Unit
Quantity
NIL
0.00
0.00
Total cost of Materials
UNIT :
520 cum
Rate
Amount
in Rs.
in Rs.
0.00 0.00
0.00 0.00
Rs: 0.00
B. MACHINERY:
Sl No Description
1
2
3
Unit
Quantity
Hour
Hour
Hour
Hour
Hour
Hour
8.00
8.00
32.00
32.00
8.00
8.00
Rate
in Rs.
1706.60
937.80
580.70
429.70
446.70
322.20
Rs:
Amount
in Rs
13652.80
7502.40
18582.40
13750.40
3573.60
2577.60
59639.20
Rate
in Rs.
204.10
195.90
153.10
370.00
345.00
295.00
Rs.
Amount
in Rs
1632.80
6268.80
1224.80
370.00
862.50
2950.00
13308.90
Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:
0.00
59639.20
13308.90
72948.10
10212.73
83160.83
159.90
C. LABOUR:
Sl No
1
2
3
4
5
6
Description
Unit
Quantity
Hour
Hour
Hour
Day
Day
Day
Total cost of Labour
labour component/unit qty
25.60
Add contractor's profit and overhead charges
14% 3.60
labour component/unit qty (including contractor's profit)
29.20
8.00
32.00
8.00
1.00
2.50
10.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D.Add for contractor's profit and overheads on (A+B+C)
Total cost for
520.00
Rate per
cum (A+B+C+D)/520
14%
cum
49
IRR-DAW-1-3
DATA:
Excavation for foundation in hard rock (including F&F rock) requiring blasting including
boulders above 0.6 m upto 1.2 m dia. for dam, spillway, intake structure
and other appurtenant works and placing the excavated material neatly in
dump area or disposing off the same as directed etc., complete with initial
lead upto 1 km and all lifts.
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
Description
Use rate of 1.5 m drill rod
Reconditioning charges @
Use rate of air hose 4 Nos.
Explosive small dia
Electric detonators
Fuse coil
Sundries
Total cost of Materials
Unit
UNIT :
520.00 cum.
Rate
Amount
in Rs.
in Rs
20.14 4350.24
435.02
10.94 284.38
70.00 7280.00
13.00 2002.00
11.00 3520.00
41.00 205.00
Rs. 18076.64
Quantity
Rm
216.00
10%
Hour
kg
Nos
Rm
LS
26.00
104.00
154.00
320.00
5.00
B. MACHINERY:
Sl No
Description
Unit
Quantity
Rate
in Rs.
1
2
3
4
5
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
8.00
8.00
32.00
32.00
8.00
8.00
13.00
13.00
26.00
26.00
1706.60
937.80
580.70
429.70
446.70
322.20
170.80
428.00
19.80
0.00
Rs:
Amount
in Rs
13652.80
7502.40
18582.40
13750.40
3573.60
2577.60
2220.40
5564.00
514.80
0.00
67938.40
C. LABOUR:
Sl No
Description
Unit
Quantity
Hour
Hour
Hour
Hour
Hour
Day
Day
Day
Day
Day
Day
Total cost of Labour
labour component/unit qty
45.60
Add contractor's profit and overhead charges
14% 6.40
labour component/unit qty (including contractor's profit)
52.00
1
2
3
4
5
6
7
8
9
10
11
Rate
in Rs.
8.00
32.00
8.00
13.00
26.00
1.00
1.00
1.00
2.50
1.00
10.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
14%
cum.
204.10
195.90
153.10
142.40
284.70
370.00
440.00
345.00
345.00
345.00
295.00
Rs.
Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:
Amount
in Rs
1632.80
6268.80
1224.80
1851.20
7402.20
370.00
440.00
345.00
862.50
345.00
2950.00
23692.30
18076.64
67938.40
23692.30
109707.34
15359.03
125066.37
240.50
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
Description
Use rate of 1.5 m drill rod
Reconditioning charges @
Unit
Rm
Quantity
216.00
10%
UNIT :
520.00 cum.
Rate
Amount
in Rs.
in Rs
20.14 4350.24
435.02
50
2
3
4
3
4
5
6
Hour
Sq m
Nos.
kg
Nos
Rm
LS
26.00
500.00
190.00
104.00
154.00
320.00
5.00
10.94
64.93
74.45
70.00
23.00
11.00
41.00
Rs.
284.38
32462.50
14145.50
7280.00
3542.00
3520.00
205.00
66224.64
1706.60
937.80
1715.50
656.00
580.70
429.70
446.70
322.20
170.80
428.00
19.80
0.00
Rs:
Amount
in Rs
13652.80
7502.40
1715.50
656.00
18582.40
13750.40
3573.60
2577.60
2220.40
5564.00
514.80
0.00
70309.90
B. MACHINERY:
Sl No
Description
Unit
Quantity
Rate
in Rs.
1
2
3
4
5
6
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
8.00
8.00
1.00
1.00
32.00
32.00
8.00
8.00
13.00
13.00
26.00
26.00
C. LABOUR:
Sl No
Description
1
2
3
4
5
6
7
8
9
10
11
12
Unit
Quantity
Hour
Hour
Hour
Hour
Hour
Hour
Day
Day
Day
Day
Day
Day
Total cost of Labour
labour component/unit qty
53.70
Add contractor's profit and overhead charges
14% 7.50
labour component/unit qty (including contractor's profit)
61.20
Rate
in Rs.
8.00
1.00
32.00
8.00
13.00
26.00
3.00
1.50
2.00
2.50
2.00
18.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
14%
cum.
IRR-DAW-1-4
(a)
204.10
204.10
195.90
153.10
142.40
284.70
370.00
440.00
345.00
345.00
345.00
295.00
Rs.
Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:
Amount
in Rs
1632.80
204.10
6268.80
1224.80
1851.20
7402.20
1110.00
660.00
690.00
862.50
690.00
5310.00
27906.40
66224.64
70309.90
27906.40
164440.94
23021.73
187462.67
360.50
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4
5
6
7
Unit
Quantity
Rm
310.00
10%
Hour
kg
Nos
Nos
Rm
LS
48.00
95.00
10.00
333.00
450.00
5.00
UNIT
320.00 cum
Rate
Amount
in Rs.
in Rs
26.85 8324.53
832.45
10.94 525.00
70.00 6650.00
9.00 90.00
13.00 4329.00
11.00 4950.00
41.00 205.00
Rs: 25905.98
51
B. MACHINERY:
Sl No
Description
1
2
3
4
5
6
C. LABOUR:
Sl No
Description
Unit
Quantity
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
8.00
8.00
24.00
24.00
4.00
4.00
1.00
1.00
24.00
24.00
48.00
48.00
Unit
Quantity
1
2
3
4
5
6
7
8
9
10
11
12
8.00
24.00
4.00
1.00
24.00
48.00
1.00
1.00
1.00
1.00
2.00
6.00
IRR-DAW-1-5
(b)
Amount
in Rs
13652.80
7502.40
13936.80
10312.80
1786.80
1288.80
1715.50
656.00
4099.20
10272.00
950.40
0.00
66173.50
Rate
in Rs.
Amount
in Rs
1632.80
4701.60
612.40
204.10
3417.60
13665.60
370.00
440.00
345.00
345.00
690.00
1770.00
28194.10
204.10
195.90
153.10
204.10
142.40
284.70
370.00
440.00
345.00
345.00
345.00
295.00
Rs.
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:
Total
14%
cum
Rate
in Rs.
1706.60
937.80
580.70
429.70
446.70
322.20
1715.50
656.00
170.80
428.00
19.80
0.00
Rs.
25905.98
66173.50
28194.10
120273.58
16838.3
137111.88
428.50
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4
5
6
7
8
9
B. MACHINERY:
Sl No
1
2
3
Particulars
Shovel 0.85 cum capacity
Fuel / Energy charges
Angle dozer 90 hp
Fuel / Energy charges
Dumpers 5 cum capacity 3 Nos.
Unit
Quantity
Rm
10%
Hour
sqm
Nos
kg
Nos
Nos
Rm
LS
Unit
Hour
Hour
Hour
Hour
Hour
UNIT :
480.00 cum
Rate
Amount
in Rs.
in Rs
26.85 12459.95
1246.00
10.94 765.63
64.93 46421.38
74.45 43181.00
70.00 10430.00
9.00 207.00
23.00 11500.00
11.00 7700.00
41.00 410.00
Rs: 134320.96
464.00
70.00
715.00
580.00
149.00
23.00
500.00
700.00
10.00
Quantity
Rate
in Rs.
12.00
12.00
2.00
2.00
36.00
1706.60
937.80
1715.50
656.00
580.70
Amount
in Rs
20479.20
11253.60
3431.00
1312.00
20905.20
52
36.00
4.00
4.00
35.00
35.00
70.00
70.00
Quantity
Hour
Hour
Hour
Hour
Hour
Hour
Day
Day
Day
Day
Day
Day
Total cost of Labour
labour component/unit qty
96.70
Add contractor's profit and overhead charges
14% 13.50
labour component/unit qty (including contractor's profit)
110.20
IRR-DAW-1-6
( c)
Note :
15469.20
1786.80
1288.80
5978.00
14980.00
1386.00
0.00
98269.80
204.10
204.10
195.90
153.10
142.40
284.70
370.00
440.00
345.00
345.00
345.00
295.00
Rs.
Amount
in Rs
2449.20
408.20
7052.40
612.40
4984.00
19929.00
1665.00
660.00
1035.00
862.50
862.50
5900.00
46420.20
Rate
in Rs.
12.00
2.00
36.00
4.00
35.00
70.00
4.50
1.50
3.00
2.50
2.50
20.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:
Total
14%
cum
429.70
446.70
322.20
170.80
428.00
19.80
0.00
Rs:
134320.96
98269.80
46420.20
279010.96
39061.53
318072.49
662.70
DATA:
RATE ANALYSIS
UNIT :
A. MATERIALS:
Sl No
Particulars
1
2
3
4
5
6
7
B. MACHINERY:
Sl No
Description
1
2
3
4
Unit
Quantity
Rm
138.00
10%
Hour
kg
Nos
Nos
Rm
LS
22.00
10.50
2.00
76.00
140.00
2.00
Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Quantity
1.00
1.00
0.25
0.25
3.00
3.00
11.00
40.00 cum
Rate
Amount
in Rs.
in Rs
26.85 3705.76
370.58
10.94 240.63
70.00 735.00
9.00 18.00
23.00 1748.00
11.00 1540.00
41.00 82.00
Rs. 8439.97
Rate
in Rs.
1706.60
937.80
1715.50
656.00
580.70
429.70
170.80
Amount
in Rs
1706.60
937.80
428.88
164.00
1742.10
1289.10
1878.80
53
C. LABOUR:
Sl No
Description
Unit
11.00
22.00
22.00
Quantity
1
2
3
4
5
6
7
8
9
10
11
IRR-DAW-1-7
204.10
204.10
195.90
142.40
284.70
370.00
440.00
345.00
345.00
345.00
295.00
Rs.
Amount
in Rs
204.10
51.03
587.70
1566.40
6263.40
185.00
220.00
172.50
172.50
172.50
590.00
10185.13
Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:
8439.97
13290.88
10185.13
31915.98
4468.24
36384.22
909.60
Total
14%
cum
DATA
RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
Unit
Quantity
NIL
UNIT:
100.00 sqm
Amount
in Rs
0.00 0.00
0.00 0.00
Rs. 0.00
Rate
in Rs.
0.00
0.00
C. LABOUR:
Sl No
Description
Unit
Quantity
Hour
Hour
Hour
Hour
Unit
1
2
3
4
5
Rate
in Rs.
1.00
1.00
1.00
1.00
Quantity
170.80
428.00
3.00
38.00
Rs.
Amount
in Rs
170.80
428.00
3.00
38.00
639.80
142.40
72.10
345.00
295.00
345.00
Rs:
Amount
in Rs
142.40
72.10
690.00
737.50
690.00
2332.00
Rate
in Rs.
1.00
1.00
2.00
2.50
2.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
IRR-DAW-1-8
4708.00
435.60
0.00
13290.88
Rate
in Rs.
1.00
0.25
3.00
11.00
22.00
0.50
0.50
0.50
0.50
0.50
2.00
428.00
19.80
0.00
Rs:
Total
14%
sqm
Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:
0.00
639.80
2332.00
2971.80
416.05
3387.85
33.90
54
removing all loose materials by wedging / chiselling and disposing off the
same as directed etc., complete with initial lead upto 50 m and all lifts.
DATA
RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
Unit
Quantity
NIL
UNIT:
100.00 sqm
Amount
in Rs
0.00 0.00
0.00 0.00
Rs. 0.00
Rate
in Rs.
0.00
0.00
Unit
Quantity
NIL
Rate
in Rs.
Amount
in Rs
0.00 0.00
0.00 0.00
Rs. 0.00
0.00
0.00
Total cost of Machinery
C. LABOUR:
Sl No
Description
1
2
3
Crowbar man
Stone breaker
mazdoor
Unit
Quantity
Day
Day
Day
Rate
in Rs.
2.00
2.00
2.00
345.00
345.00
295.00
Rs:
19.70
14% 2.80
22.50
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
NOTE:
Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:
Total
14%
sqm
IRR-DAW-1-9
Amount
in Rs
690.00
690.00
590.00
1970.00
0.00
0.00
1970.00
1970.00
275.8
2245.80
22.50
Data
RATE ANALYSIS
UNIT:
A. MATERIALS:
Sl No
Particulars
1
2
3
B. MACHINERY:
Sl No
Description
1
2
3
Waggon drill
Fuel / Energy charges
Air compressor 8.5 cmm ( ele )
Fuel / Energy charges
Sundries
Total hire charges of Machinery
C. LABOUR:
Sl No
Description
1
2
3
Unit
Quantity
Rm
Hour
Rm
Unit
96.00
8.00
96.00
Quantity
Hour
Hour
Hour
Hour
LS
Unit
96.00 Rm
Rate
Amount
in Rs.
in Rs
62.50 6000.00
18.63 149.00
6.36 610.56
Rs. 6759.56
Rate
in Rs.
8.00
8.00
8.00
8.00
2.00
Quantity
188.50
0.00
170.80
428.00
41.00
Rs:
Amount
in Rs
1508.00
0.00
1366.40
3424.00
82.00
6380.40
244.90
142.40
295.00
Rs:
Amount
in Rs
1959.20
1139.20
590.00
3688.40
Rate
in Rs.
8.00
8.00
2.00
ABSTRACT:
55
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
14%
Rm
IRR-DAW-1-10
Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:
6759.56
6380.40
3688.40
16828.36
2355.97
19184.33
199.80
199.80
Rs: 199.80
10%
Rs: 19.98
Rs: 219.80
Rs: 219.80
10%
Rs: 21.98
Rs: 241.80
:
Rs: 241.80
10%
Rs: 24.18
Rs: 266.00
:
Rs: 266.00
10%
Rs 26.60
Rs: 292.60
:
Rs: 292.60
10%
Rs: 29.26
Rs: 321.90
:
Rs: 321.90
10%
Rs: 32.19
Rs: 354.10
Rs: 354.10
10%
Rs: 35.41
Rs: 389.50
Flushing grout holes of all sizes with water and air jets alternatively for an
average period of 30 minutes including water intake observations after
flushing, cost of all materials, machinery, labour etc., complete.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
B. MACHINERY:
Sl No
Description
1
2
3
Unit
Quantity
Hour
Hour
LS
Unit
16.00
16.00
2.00
Quantity
C. LABOUR:
Sl No
Description
Unit
UNIT :
192.00 Rm.
Rate
Amount
in Rs.
in Rs
10.94 175.04
13.69 219.04
41.00 82.00
Rs: 476.08
Rate
in Rs.
8.00
8.00
8.00
8.00
2.00
Quantity
170.80
428.00
3.00
38.00
41.00
Rs:
Amount
in Rs
1366.40
3424.00
24.00
304.00
82.00
5200.40
142.40
72.10
295.00
Rs:
Amount
in Rs
1139.20
576.80
1180.00
2896.00
Rate
in Rs.
8.00
8.00
4.00
56
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
14%
Rm.
IRR-DAW-1-11
(a)
Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
Cement
Use rate of 50 m pressure hose
Sundries ( packer assembly etc )
Total cost of Materials
B. MACHINERY:
Sl No
Description
1
2
3
Unit
Quantity
tonne
Hour
LS
Unit
1.05
8.00
3.00
Quantity
Grouting equipment
Hour
Fuel / Energy charges
Hour
Pump 5 hp ( ele )
Hour
Fuel / Energy charges
Hour
Sundries
LS
Total hire charges of Machinery
C. LABOUR:
Sl No
Description
Unit
UNIT :
1.05 tonne
Rate
Amount
in Rs.
in Rs
4000.00 4200.00
10.94 87.52
41.00 123.00
Rs: 4410.52
Rate
in Rs.
8.00
8.00
2.00
2.00
2.00
Quantity
1
2
3
8.00
2.00
2.00
227.80
72.10
295.00
Rs:
Amount
in Rs
1822.40
144.20
590.00
2556.60
Rs:
Rs:
Rs:
Rs:
Rs.
Total
14%
24.90
38.00
3.00
38.00
41.00
Rs:
Amount
in Rs
199.20
304.00
6.00
76.00
82.00
667.20
Rate
in Rs.
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
IRR-DAW-1-12
(b)
476.08
5200.40
2896.00
8572.48
1200.15
9772.63
50.90
124.60 Rs/Tonne
tonne
4410.52
667.20
2556.60
7634.32
1068.8
130.83
Rs: 8833.95
Rs: 8413.30
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4
Cement
Use rate of 100 m pressure hose
Use rate of 400 m GI pipe
Sundries ( packer assembly etc )
Total cost of Materials
B. MACHINERY:
Sl No
Description
1
2
Grouting equipment
Fuel / Energy charges
Pump 5 hp ( ele )
Fuel / Energy charges
Unit
Quantity
tonne
Hour
Hour
LS
Unit
Hour
Hour
Hour
Hour
1.05
8.00
8.00
3.00
Quantity
UNIT :
1.05 tonne
Rate
Amount
in Rs.
in Rs
4000.00 4200.00
21.88 175.04
6.8 54.40
41.00 123.00
Rs: 4552.44
Rate
in Rs.
8.00
8.00
2.00
2.00
24.90
38.00
3.00
38.00
Amount
in Rs
199.20
304.00
6.00
76.00
57
Sundries
LS
Total hire charges of Machinery
C. LABOUR:
Sl No
Description
2.00
Unit
Quantity
1
2
3
4
41.00 82.00
Rs: 667.20
Rate
in Rs.
8.00
2.00
1.00
3.00
227.80
72.10
440.00
295.00
Rs:
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
14%
IRR-DAW-1-13
Rs:
Rs:
Rs:
Rs:
Rs.
124.60 Rs/Tonne
tonne
Amount
in Rs
1822.40
144.20
440.00
885.00
3291.60
4552.44
667.20
3291.60
8511.24
1191.57
130.83
Rs: 9833.64
Rs: 9365.40
DATA:
RATE ANALYSIS
A. MATERIALS
Sl No
Particulars
1
2
3
4
5
Unit
Quantity
Rm
Hour
kg
kg
cum
Unit
37.50
4.00
303.22
75.00
0.05
Quantity
C. LABOUR:
Sl No
Description
1
2
3
4
5
Unit
UNIT:
25 Nos.
Rate
Amount
in Rs.
in Rs
62.50 2343.75
18.63 74.52
46.50 14099.73
4.00 300.00
606.00 30.30
Rs: 16848.30
Rate
in Rs.
4.00
4.00
4.00
4.00
Quantity
Hour
Hour
Day
Day
Day
170.80
428.00
188.50
0.00
Rs:
Amount
in Rs
683.20
1712.00
754.00
0.00
3149.20
142.40
244.90
450.00
345.00
295.00
Rs:
Amount
in Rs
569.60
979.60
225.00
172.50
295.00
2241.70
Rate
in Rs.
4.00
4.00
0.50
0.50
1.00
89.70
14% 12.60
102.30
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D.Add for contractor's profit and overheads on (A+B+C)
Lead Charges for 1 Km for FA
0.05
cum @
Lead Charges for 1Km for Cement (including Loading
0.08
tonne @
and Unloading Charges)
Lead Charges for 1Km for Steel (including Loading
0.30
tonne @
and Unloading Charges)
Total cost for
25.00
Rs:
Rs:
Rs:
Rs:
Rs.
31.5 Rs./Cum
16848.30
3149.20
2241.70
22239.20
3113.49
1.575
124.6 Rs./Tonne
9.345
145.6 Rs./Tonne
44.148832
Rs: 25407.76
Total
14%
Nos.
58
Rate per
IRR-DAW-1-14
Each
(A+B+C+D)/25
Rs: 1016.30
Providing and fixing 25 mm dia. 2.75 m long ribbed steel anchor rods
with one end split and driven firmly using steel wedge into 1.25 m deep 45
to 50 mm dia. hole drilled in bed rock and other end provided with L- bend
for embedding in concrete / masonry for spillway and appurtenant works
including drilling and cleaning hole, filling hole with thick cement slurry,
driving anchor rod, cost of all materials, machinery, labour, steel wedge
etc., complete with initial lead upto 1 km and all lifts.
Consider 25 anchor rods for analysis.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
Unit
1
2
3
4
5
6
Quantity
Rm
Hour
kg
kg
LS
LS
31.25
3.00
277.92
62.50
5.00
10.00
Unit
Quantity
UNIT:
25.00 Nos.
Rate
Amount
in Rs.
in Rs
62.50 1953.13
18.63 55.89
46.50 12923.28
4.00 250.00
37.20 186.00
16.00 160.00
Rs: 15528.30
Rate
in Rs.
3.00
3.00
3.00
3.00
Quantity
1
2
3
4
5
6
170.80
428.00
188.50
0.00
Rs:
Amount
in Rs
512.40
1284.00
565.50
0.00
2361.90
142.40
244.90
450.00
345.00
385.00
295.00
Rs:
Amount
in Rs
427.20
734.70
225.00
172.50
385.00
590.00
2534.40
Rs:
Rs:
Rs:
Rs:
Rs.
15528.30
2361.90
2534.40
20424.60
2859.44
Rate
in Rs.
3.00
3.00
0.50
0.50
1.00
2.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
14%
tonne @
124.6 Rs./Tonne
7.7875
0.28
tonne @
25.00
(A+B+C+D)/25
145.6 Rs./Tonne
40.465152
Rs: 23332.29
Rs: 933.30
Nos.
IRR-DAW-2
IRR-DAW-2-1A
Providing, fabricating and placing in position reinforcement steel for RCC,below 36 dia rods
overlaps and wastages wherever required, tying with 1.25 mm diameter soft
annealed steel wire, including cost of all materials, machinery, labour etc.,
complete with initial lead upto 1 km and all lifts.
overlaps and wastage
as per NHAI-data
Lap jointing considered for bars upto 36 mm diameter.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
B. MACHINERY:
Sl No
Description
Unit
Quantity
tonne
kg
Unit
1.05
9.00
Quantity
UNIT :
1.00 tonne
Rate
Amount
in Rs.
in Rs
46500.00 48825.00
70.00 630.00
Rs: 49455.00
Rate
Amount
59
in Rs.
Total hire charges of Machinery
C. LABOUR:
Sl No
Description
1
2
Bar bender
mazdoor
Unit
Quantity
Rate
in Rs.
Day
Day
2.00
6.84
49455.00
0.00
2917.80
52372.80
14%
59857.87
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
Unit
welding machine
fuel charges
Unit
1.025
70.00
Quantity
hour
hour
Total hire charges of Machinery
C. LABOUR:
Sl No
Description
1
2
3
Quantity
welder
Bar bender
mazdoor
Quantity
day
Day
Day
DATA:
Rate
in Rs.
Amount
in Rs
16.00 160.00
91.30 913.00
Rs: 1073.00
Rate
in Rs.
Amount
in Rs
385.00 962.50
450.00 900.00
295.00 2017.80
3880.30
2.50
2.00
6.84
3880.30
14% 543.20
4423.50
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D.Add for contractor's profit and overheads on A+B+C
Lead Charges for 1Km for Steel (including Loading
and Unloading Charges)
145.60 Rs/Tonne
Total cost for
1.00
Rate per/ TON.=(A+B+C+D) / I
IRR-DAW-2-2
UNIT :
1.00 tonne
Rate
Amount
in Rs.
in Rs
46500.00 47662.50
11.00 770.00
Rs: 48432.50
10.00
10.00
Unit
7332.19
152.88
tonne 59857.87
IRR-DAW-2-1B
B. MACHINERY:
Sl No
Description
Amount
in Rs
450.00 900.00
295.00 2017.80
2917.80
2917.80
14% 408.50
3326.30
A.MATERIAL
B.MACHINERY
C. LABOUR
Total
D.Add for contractor's profit and overheads on A+B+C
Lead Charges for 1Km for Steel (including Loading
and Unloading Charges)
145.60 Rs/Tonne
Total cost for
1.00
Rate per/ TON.=(A+B+C+D) / I
1
3
in Rs
Rs: 0.00
14%
48432.50
1073.00
3880.30
53385.80
7474.01
149.24
tonne 61009.05
61009.05
60
A. MATERIALS:
Sl No
Particulars
1
2
3
4
5
B. MACHINERY:
Sl No
Description
1
2
3
4
5
6
7
8
Unit
Quantity
kg
kg
cum
cum
cum
cum
cum
kg
sqm
Unit
60000.00
720.00
94.08
70.56
47.04
23.52
84.00
240.00
120.00
Quantity
Batching plant
Hour
Fuel / Energy charges
Hour
Air compressor 7 cmm ( ele )
Hour
Fuel / Energy charges
Hour
Tipper
Hour
Fuel / Energy charges
Hour
Tower crane 5 t
Hour
Fuel / Energy charges
Hour
Concrete bucket
Hour
Fuel / Energy charges
Hour
10 hp pump ( ele )
Hour
Fuel / Energy charges
Hour
Needle vibrator 60 mm dia ( ele )
Hour
Fuel / Energy charges
Hour
Sundries
LS
Total hire charges of Machinery
C. LABOUR:
Sl No
Description
Unit
240.00 cum
Rate
Amount
in Rs.
in Rs
4.00 240000.00
4.00 2880.00
635.00 59740.80
1145.00 80791.20
1210.00 56918.40
875.00 20580.00
462.00 38808.00
80.00 19200.00
353.76 42451.20
Rs: 561369.60
Rate
in Rs.
518.10
418.50
131.90
342.40
446.70
322.20
867.10
197.80
15.80
0.00
6.70
76.10
9.70
11.40
41.00
Rs:
Amount
in Rs
4144.80
3348.00
1055.20
2739.20
14294.40
10310.40
13873.60
3164.80
632.00
0.00
53.60
608.80
155.20
182.40
410.00
54972.40
8.00
8.00
32.00
16.00
8.00
16.00
4.00
2.00
293.80
142.40
153.10
163.30
72.10
136.60
385.00
440.00
Amount
in Rs
2350.40
1139.20
4899.20
2612.80
576.80
2185.60
1540.00
880.00
2.00
2.00
2.00
6.00
2.00
120.00
295.00
295.00
295.00
295.00
295.00
112.95
Rs:
590.00
590.00
590.00
1770.00
590.00
13554.00
33868.00
8.00
8.00
8.00
8.00
32.00
32.00
16.00
16.00
40.00
40.00
8.00
8.00
16.00
16.00
10.00
Quantity
1
2
3
4
5
6
7
8
9
Rate
in Rs.
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Add for conveyor system @
Add for electric sub-station/ Demand charges @
Add for trestle bridge for tower crane track @
D.Add for contractor's profit and overheads on (A+B+C)
Lead Charges for 1 Km for FA
84.00
cum @
Lead Charges for 1 Km for CA
235.20 cum @
Lead Charges for 1Km for Cement (including Loading
and Unloading Charges)
60.72
tonne @
Total cost for
240.00
Rate per
cum
(A+B+C+D)/240
IRR-DAW-2-2A
New Item1-2010-11
Rs:
Rs:
Rs:
Rs:
Total
3.00%
2.5%
4.0%
Total
14%
31.5 Rs./Cum
30.4 Rs./Cum
124.6 Rs./Tonne
cum
561369.60
54972.40
33868.00
650210.00
19506.30
16255.25
26008.40
Rs: 711979.95
Rs. 99677.19
2646
7150.08
7565.712
Rs: 829018.93
Rs: 3454.20
61
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4
5
B. MACHINERY:
Sl No
Description
1
2
3
4
5
6
7
8
Unit
Quantity
kg
kg
cum
cum
cum
cum
cum
kg
sqm
Unit
72000.00
720.00
86.40
64.80
43.20
21.60
96.00
288.00
120.00
Quantity
Batching plant
Hour
Fuel / Energy charges
Hour
Air compressor 7 cmm ( ele )
Hour
Fuel / Energy charges
Hour
Tipper
Hour
Fuel / Energy charges
Hour
Tower crane 5 t
Hour
Fuel / Energy charges
Hour
Concrete bucket
Hour
Fuel / Energy charges
Hour
Hour
10 hp pump ( ele )
Fuel / Energy charges
Hour
Needle vibrator 60 mm dia ( ele )
Hour
Fuel / Energy charges
Hour
Sundries
LS
Total hire charges of Machinery
C. LABOUR:
Sl No
Description
Unit
UNIT:
240.00 cum
Rate
Amount
in Rs.
in Rs
4.00 288000.00
4.00 2880.00
635.00 54864.00
1145.00 74196.00
1210.00 52272.00
875.00 18900.00
462.00 44352.00
80.00 23040.00
353.76 42451.20
Rs: 600955.20
Rate
in Rs.
518.10
418.50
131.90
342.40
446.70
322.20
867.10
197.80
15.80
0.00
6.70
76.10
9.70
11.40
41.00
Rs:
Amount
in Rs
4144.80
3348.00
1055.20
2739.20
14294.40
10310.40
13873.60
3164.80
632.00
0.00
53.60
608.80
155.20
182.40
410.00
54972.40
8.00
8.00
32.00
16.00
8.00
16.00
4.00
2.00
293.80
142.40
153.10
163.30
72.10
136.60
385.00
440.00
Amount
in Rs
2350.40
1139.20
4899.20
2612.80
576.80
2185.60
1540.00
880.00
2.00
2.00
2.00
6.00
2.00
120.00
295.00
295.00
295.00
295.00
295.00
112.95
Rs:
590.00
590.00
590.00
1770.00
590.00
13554.00
33868.00
8.00
8.00
8.00
8.00
32.00
32.00
16.00
16.00
40.00
40.00
8.00
8.00
16.00
16.00
10.00
Quantity
1
2
3
4
5
6
7
8
9
Rate
in Rs.
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Add for conveyor system @
Add for electric sub-station/ Demand charges @
Add for trestle bridge for tower crane track @
D.Add for contractor's profit and overheads on (A+B+C)
Lead Charges for 1 Km for FA
96.00
cum @
Lead Charges for 1 Km for CA
216.00 cum @
Lead Charges for 1Km for Cement (including Loading
72.72
tonne @
and Unloading Charges)
Total cost for
240.00
Rate per
cum
(A+B+C+D)/240
IRR-DAW-2-3
Rs:
Rs:
Rs:
Rs:
Total
3.00%
2.5%
4.0%
Total
14%
31.5 Rs./Cum
30.4 Rs./Cum
124.6 Rs./Tonne
cum
600955.20
54972.40
33868.00
689795.60
20693.87
17244.89
27591.82
Rs: 755326.18
Rs. 105745.67
3024
6566.40
9060.912
Rs: 879723.16
Rs: 3665.50
62
RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4
5
B. MACHINERY:
Sl No
Description
1
2
3
4
5
6
7
8
Unit
Quantity
kg
kg
cum
cum
cum
cum
cum
kg
sqm
52800
720.00
94.08
70.56
47.04
23.52
88.8
211.20
120.00
Unit
Quantity
C. LABOUR:
Sl No
Description
Rate
in Rs.
518.10
418.50
131.90
342.40
446.70
322.20
867.10
197.80
15.80
0.00
6.70
76.10
9.70
11.40
41.00
Rs:
Amount
in Rs
4144.80
3348.00
1055.20
2739.20
14294.40
10310.40
13873.60
3164.80
632.00
0.00
53.60
608.80
155.20
182.40
410.00
54972.40
8.00
8.00
32.00
16.00
8.00
16.00
4.00
2.00
293.80
142.40
153.10
163.30
72.10
136.60
385.00
440.00
Amount
in Rs
2350.40
1139.20
4899.20
2612.80
576.80
2185.60
1540.00
880.00
2.00
2.00
2.00
6.00
2.00
120.00
295.00
295.00
295.00
295.00
295.00
112.95
Rs:
590.00
590.00
590.00
1770.00
590.00
13554.00
33868.00
8.00
8.00
8.00
8.00
32.00
32.00
16.00
16.00
40.00
40.00
8.00
8.00
16.00
16.00
10.00
Unit
Quantity
1
2
3
4
5
6
7
8
9
Rate
in Rs.
Rs:
Rs:
Rs:
Total
3.00%
2.5%
4.0%
Total
14%
UNIT:
240.00 cum
Rate
Amount
in Rs.
in Rs
4.00 211200.00
4.00 2880.00
635.00 59740.80
1145.00 80791.20
1210.00 56918.40
875.00 20580.00
462.00 41025.60
80.00 16896.00
353.76 42451.20
Rs: 532483.20
cum @
cum @
31.5 Rs./Cum
30.4 Rs./Cum
532483.20
54972.40
33868.00
Rs: 621323.60
18639.71
15533.09
24852.94
Rs: 680349.34
Rs. 95248.91
2797.2
7150.08
63
IRR-DAW-2-4
124.6 Rs./Tonne
cum
6668.592
Rs: 792214.12
Rs: 3300.90
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4
5
6
B. MACHINERY:
Sl No
Description
1
2
3
4
5
6
7
8
C. LABOUR:
Sl No
Description
1
2
3
4
5
6
7
8
9
Unit
kg
kg
cum
cum
cum
cum
kg
sqm
74400
720.00
108
64.8
43.2
96
297.60
360.00
15%
Unit
Quantity
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS
Unit
Quantity
UNIT:
240.00 cum
Rate
Amount
in Rs.
in Rs
4.00 297600.00
4.00 2880.00
1145.00 123660.00
1210.00 78408.00
875.00 37800.00
462.00 44352.00
80.00 23808.00
353.76 127353.60
19103.04
Rs: 754964.64
Rate
in Rs.
8.00
8.00
8.00
8.00
32.00
32.00
16.00
16.00
40.00
40.00
8.00
8.00
16.00
16.00
10.00
Quantity
518.10
418.50
131.90
342.40
446.70
322.20
867.10
197.80
15.80
0.00
6.70
76.10
9.70
11.40
41.00
Rs:
Rate
in Rs.
8.00
8.00
32.00
16.00
8.00
16.00
4.00
2.00
293.80
142.40
153.10
163.30
72.10
136.60
385.00
440.00
2.00
2.00
2.00
6.00
2.00
360.00
295.00
295.00
295.00
295.00
295.00
112.95
Rs:
Amount
in Rs
4144.80
3348.00
1055.20
2739.20
14294.40
10310.40
13873.60
3164.80
632.00
0.00
53.60
608.80
155.20
182.40
410.00
54972.40
Amount
in Rs
2350.40
1139.20
4899.20
2612.80
576.80
2185.60
1540.00
880.00
0.00
590.00
590.00
590.00
1770.00
590.00
40662.00
6099.30
67075.30
Rs: 754964.64
Rs: 54972.40
Rs: 67075.30
64
Total
3.0%
2.50%
4.0%
Total
14%
Rs: 877012.34
26310.37
21925.31
35080.49
Rs: 960328.51
Rs. 134445.99
3024
6566.40
31.5 Rs./Cum
30.4 Rs./Cum
124.6 Rs./Tonne
cum
9359.952
Rs: 1113724.85
Rs: 4640.50
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4
5
6
B. MACHINERY:
Sl No
Description
1
2
3
4
5
6
7
8
C. LABOUR:
Sl No
Description
1
2
3
4
5
6
7
8
9
Unit
Quantity
kg
kg
cum
cum
cum
cum
kg
sqm
86400
720.00
108
64.8
43.2
96
345.60
360.00
15%
Unit
Quantity
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS
UNIT:
240.00 cum
Rate
Amount
in Rs.
in Rs
4.00 345600.00
4.00 2880.00
1145.00 123660.00
1210.00 78408.00
875.00 37800.00
462.00 44352.00
80.00 27648.00
353.76 127353.60
19103.04
Rs: 806804.64
Rate
in Rs.
8.00
8.00
8.00
8.00
32.00
32.00
16.00
16.00
40.00
40.00
8.00
8.00
16.00
16.00
10.00
Unit
Quantity
518.10
418.50
131.90
342.40
446.70
322.20
867.10
197.80
15.80
0.00
6.70
76.10
9.70
11.40
41.00
Rs:
Rate
in Rs.
Hour
Hour
Hour
Hour
Hour
Hour
Day
Day
8.00
8.00
32.00
16.00
8.00
16.00
4.00
2.00
293.80
142.40
153.10
163.30
72.10
136.60
385.00
440.00
Day
Day
Day
Day
Day
sqm
2.00
2.00
2.00
6.00
2.00
360.00
295.00
295.00
295.00
295.00
295.00
112.95
15%
Rs:
Amount
in Rs
4144.80
3348.00
1055.20
2739.20
14294.40
10310.40
13873.60
3164.80
632.00
0.00
53.60
608.80
155.20
182.40
410.00
54972.40
Amount
in Rs
2350.40
1139.20
4899.20
2612.80
576.80
2185.60
1540.00
880.00
0.00
590.00
590.00
590.00
1770.00
590.00
40662.00
6099.30
67075.30
279.50
65
14% 39.10
318.60
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Add for aggregate conveyor system @
Add for electric sub-station / Demand charges @
Add for trestle bridge for tower crane track @
D.Add for contractor's profit and overheads on (A+B+C+other
Lead Charges for 1 Km for FA
96.00
cum @
Lead Charges for 1 Km for CA
216.00 cum @
Lead Charges for 1Km for Cement (including Loading
and Unloading Charges)
87.12
tonne @
Total cost for
240.00
Rate per
cum
(A+B+C+D)/240
IRR-DAW-2-4B
new Item3-2010-11
Rs:
Rs:
Rs:
Rs:
806804.64
54972.40
67075.30
928852.34
27865.57
23221.31
37154.09
Rs: 1017093.31
Rs. 142393.06
3024
6566.40
Total
3.0%
2.50%
4.0%
Total
14%
31.5 Rs./Cum
30.4 Rs./Cum
124.6 Rs./Tonne
cum
10855.152
Rs: 1179931.92
Rs: 4916.40
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4
5
6
B. MACHINERY:
Sl No
Description
1
2
3
4
5
6
7
8
C. LABOUR:
Sl No
Description
1
2
3
4
5
6
7
8
9
Unit
Quantity
kg
kg
cum
cum
cum
kg
sqm
91200
720.00
140.4
75.6
96
364.80
360.00
15%
Unit
Quantity
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS
Unit
UNIT:
240.00 cum
Rate
Amount
in Rs.
in Rs
4.00 364800.00
4.00 2880.00
1210.00 169884.00
875.00 66150.00
462.00 44352.00
80.00 29184.00
353.76 127353.60
19103.04
Rs: 823706.64
Rate
in Rs.
8.00
8.00
8.00
8.00
32.00
32.00
16.00
16.00
40.00
40.00
8.00
8.00
16.00
16.00
10.00
Quantity
518.10
418.50
131.90
342.40
446.70
322.20
867.10
197.80
15.80
0.00
6.70
76.10
9.70
11.40
41.00
Rs:
Rate
in Rs.
Hour
Hour
Hour
Hour
Hour
Hour
Day
Day
8.00
8.00
32.00
16.00
8.00
16.00
4.00
2.00
293.80
142.40
153.10
163.30
72.10
136.60
385.00
440.00
Day
Day
Day
2.00
2.00
2.00
295.00
295.00
295.00
Amount
in Rs
4144.80
3348.00
1055.20
2739.20
14294.40
10310.40
13873.60
3164.80
632.00
0.00
53.60
608.80
155.20
182.40
410.00
54972.40
Amount
in Rs
2350.40
1139.20
4899.20
2612.80
576.80
2185.60
1540.00
880.00
0.00
590.00
590.00
590.00
66
6.00
2.00
360.00
295.00 1770.00
295.00 590.00
112.95 40662.00
6099.30
Rs: 67075.30
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
823706.64
54972.40
67075.30
945754.34
28372.63
23643.86
37830.17
Rs: 1035601.00
Rs. 144984.14
3024
6566.40
Total
3.0%
2.50%
4.0%
Total
14%
Rs:
Rs:
Rs:
Rs:
31.5 Rs./Cum
30.4 Rs./Cum
124.6 Rs./Tonne
cum
11453.232
Rs: 1201628.77
Rs: 5006.80
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4
5
6
B. MACHINERY:
Sl No
Description
1
2
3
kg
kg
cum
cum
cum
cum
kg
sqm
Quantity
3640.00
42.00
6.3
3.78
2.52
5.6
14.56
14.00
15%
Unit
Quantity
C. LABOUR:
Sl No
Description
1
2
3
4
5
Unit
Unit
UNIT :
14.00 cum
Rate
Amount
in Rs.
in Rs
4.00 14560.00
4.00 168.00
1145.00 7213.50
1210.00 4573.80
875.00 2205.00
462.00 2587.20
80.00 1164.80
235.84 3301.76
495.26
Rs: 36269.32
Rate
in Rs.
8.0
8.0
1.0
1.0
8.0
8.0
Quantity
51.70
38.00
6.70
76.10
8.00
7.60
Rs:
Amount
in Rs
413.60
304.00
6.70
76.10
64.00
60.80
925.20
Amount
in Rs
1518.40
72.10
1092.80
385.00
Rate
in Rs.
Hour
Hour
Hour
Day
8.00
1.00
8.00
1.00
189.80
72.10
136.60
385.00
Day
Day
Day
Day
Day
Day
sqm
2.00
9.00
4.00
3.00
14.00
1.00
14.00
295.00
295.00
295.00
295.00
295.00
295.00
75.30
15%
590.00
2655.00
1180.00
885.00
4130.00
295.00
1054.20
158.13
Rs: 14015.63
1001.10
14% 140.20
67
1141.30
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Rs:
Rs:
Rs:
Rs:
Rs.
Total
D.Add for contractor's profit and overheads on (A+B+C)
Lead Charges for 1 Km for FA
5.60
Lead Charges for 1 Km for CA
12.60
14%
cum @
cum @
31.5 Rs./Cum
30.4 Rs./Cum
IRR-DAW-2-6
124.6 Rs./Tonne
cum
36269.32
925.20
14015.63
51210.15
7169.42
176.4
383.04
458.7772
Rs: 59397.79
Rs: 4242.70
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4
5
6
7
B. MACHINERY:
Sl No
Description
1
2
3
UNIT:
Unit
Quantity
kg
kg
cum
cum
cum
cum
cum
kg
sqm
4277
49.35
6.33
3.8
2.53
4.11
5.59
17.11
16.45
15%
Unit
Quantity
C. LABOUR:
Sl No
Description
1
2
3
4
5
6
Unit
16.45 cum
Rate
Amount
in Rs.
in Rs
4.00 17108.00
4.00 197.40
1145.00 7247.85
1210.00 4598.00
875.00 2213.75
340.00 1398.25
462.00 2583.97
80.00 1368.64
235.84 3879.57
581.94
Rs: 41177.37
Rate
in Rs.
51.70
38.00
6.70
76.10
9.70
11.40
Rs:
Amount
in Rs
413.60
304.00
6.70
76.10
77.60
91.20
969.20
8.00
1.00
8.00
1.00
1.00
189.80
72.10
136.60
385.00
370.00
Amount
in Rs
1518.40
72.10
1092.80
385.00
370.00
2.00
9.00
4.00
1.00
4.00
13.99
3.00
1.00
16.45
295.00
295.00
295.00
295.00
295.00
295.00
295.00
295.00
75.30
8.00
8.00
1.00
1.00
8.00
8.00
Quantity
Rate
in Rs.
590.00
2655.00
1180.00
295.00
1180.00
4125.87
885.00
295.00
1238.69
185.80
Rs: 16068.66
ABSTRACT:
68
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
14%
IRR-DAW-2-7
Rs:
Rs:
Rs:
Rs:
Rs.
31.5 Rs./Cum
30.4 Rs./Cum
124.6 Rs./Tonne
cum
41177.37
969.20
16068.66
58215.23
8150.13
176.1795
509.88
539.06321
Rs: 67590.49
Rs: 4108.80
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4
5
6
B. MACHINERY:
Sl No
Description
1
2
3
Unit
Quantity
kg
kg
cum
cum
cum
cum
kg
sqm
3636.60
49.59
7.44
4.46
2.98
6.61
14.55
16.53
15%
Unit
Quantity
C. LABOUR:
Sl No
Description
UNIT:
16.53 cum
Rate
Amount
in Rs.
in Rs
4.00 14546.40
4.00 198.36
1145.00 8517.08
1210.00 5400.35
875.00 2603.48
462.00 3054.74
80.00 1163.71
235.84 3898.44
584.77
Rs: 39967.33
Rate
in Rs.
51.70
38.00
6.70
76.10
8.00
7.60
Rs:
Amount
in Rs
413.60
304.00
6.70
76.10
64.00
60.80
925.20
8.00
1.00
8.00
1.00
189.80
72.10
136.60
385.00
Amount
in Rs
1518.40
72.10
1092.80
385.00
2.00
9.00
4.00
3.00
16.53
1.00
16.53
295.00
295.00
295.00
295.00
295.00
295.00
75.30
14%
Rs:
Rs:
Rs:
Rs:
Rs.
8.00
8.00
1.00
1.00
8.00
8.00
Unit
Quantity
1
2
3
4
5
Rate
in Rs.
590.00
2655.00
1180.00
885.00
4876.35
295.00
1244.71
186.71
Rs: 14981.07
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D.Add for contractor's profit and overheads on (A+B+C)
Lead Charges for 1 Km for FA
6.61
Lead Charges for 1 Km for CA
14.88
cum @
cum @
31.5 Rs./Cum
30.4 Rs./Cum
39967.33
925.20
14981.07
55873.60
7822.3
208.278
452.26
tonne @
124.6 Rs./Tonne
459.29927
Total
69
IRR-DAW-2-8
DATA:
cum
16.53
(A+B+C+D)/16.53
cum
Rs: 64815.74
Rs: 3921.10
B. MACHINERY:
Sl No
Description
1
2
3
Unit
Quantity
kg
kg
cum
cum
cum
kg
sqm
4443.6
47.61
8.25
4.44
6.98
17.77
15.87
15%
Unit
Quantity
C. LABOUR:
Sl No
Description
UNIT:
15.87 cum
Rate
Amount
in Rs.
in Rs
4.00 17774.40
4.00 190.44
1210.00 9985.40
875.00 3888.15
462.00 3226.05
80.00 1421.95
235.84 3742.78
561.42
Rs: 40790.59
Rate
in Rs.
51.70
38.00
6.70
76.10
8.00
7.60
Rs:
Amount
in Rs
413.60
304.00
6.70
76.10
64.00
60.80
925.20
8.00
1.00
8.00
1.00
189.80
72.10
136.60
385.00
Amount
in Rs
1518.40
72.10
1092.80
385.00
2.00
9.00
4.00
3.00
15.87
1.00
15.87
295.00
295.00
295.00
295.00
295.00
295.00
75.30
14%
Rs:
Rs:
Rs:
Rs:
Rs.
8.00
8.00
1.00
1.00
8.00
8.00
Unit
Quantity
1
2
3
4
5
Rate
in Rs.
590.00
2655.00
1180.00
885.00
4681.65
295.00
1195.01
179.25
Rs: 14729.21
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D.Add for contractor's profit and overheads on (A+B+C)
Lead Charges for 1 Km for FA
6.98
Lead Charges for 1 Km for CA
12.70
cum @
cum @
IRR-DAW-2-9
31.5 Rs./Cum
30.4 Rs./Cum
124.6 Rs./Tonne
cum
40790.59
925.20
14729.21
56445.00
7902.3
219.9582
385.96
559.60477
Rs: 65512.82
Rs: 4128.10
70
upto 1 km and all lifts. ( Cement content : 330 kg / cum with use of
super plasticiser, CA : 0.80 cum, Blending Ratio of CA -- 65:35,
FA : 0.44 cum)
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4
5
6
B. MACHINERY:
Sl No
Description
1
2
3
Unit
Quantity
kg
kg
cum
cum
cum
ltr
sqm
100%
Total cost of Materials
Unit
Quantity
C. LABOUR:
Sl No
Description
4445.1
40.41
7.00
3.77
5.93
17.78
33.68
UNIT:
13.47 cum
Rate
Amount
in Rs.
in Rs
4.00 17780.40
4.00 161.64
1210.00 8475.32
875.00 3300.15
462.00 2738.18
80.00 1422.43
235.84 7941.91
7941.91
Rs: 49761.94
Rate
in Rs.
8.00
8.00
1.00
1.00
8.00
8.00
Unit
Quantity
1
2
3
4
5
51.70
38.00
6.70
76.10
8.00
7.60
Rs:
Rate
in Rs.
8.00
1.00
8.00
1.00
189.80
72.10
136.60
385.00
2.00
9.00
4.00
3.00
13.47
1.00
33.68
295.00
295.00
295.00
295.00
295.00
295.00
75.30
Rs:
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Rs:
Rs:
Rs:
Rs:
Rs.
Total
D.Add for contractor's profit and overheads on (A+B+C)
Lead Charges for 1 Km for FA
5.93
cum @
Lead Charges for 1 Km for CA
10.78
cum @
Lead Charges for 1Km for Cement (including Loading
4.49
tonne @
and Unloading Charges)
Total cost for
13.47
Rate per
cum
(A+B+C+D)/13.47
IRR-DAW-2-10
14%
31.5 Rs./Cum
30.4 Rs./Cum
124.6 Rs./Tonne
cum
Amount
in Rs
413.60
304.00
6.70
76.10
64.00
60.80
925.20
Amount
in Rs
1518.40
72.10
1092.80
385.00
0.00
590.00
2655.00
1180.00
885.00
3973.65
295.00
2535.73
2535.73
17718.41
49761.94
925.20
17718.41
68405.55
9576.78
186.6942
327.59
558.89455
Rs: 79055.51
Rs: 5869.00
Providing and forming porous concrete body drain of size 68.5 x 68.5 cm
with 23 cm diameter central hole using cement and 20 mm down
approved, clean, hard, graded coarse aggregates in 1 : 3.50 proportion by
volume including cost of all materials, machinery, labour, formwork, curing
etc., complete with initial lead upto 1 km and all lifts.
(M15 Cement content : 400kg/cum, CA : 1cum,
Blending Ratio of CA -- 65:35)
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
Cement
Coarse aggregate 20-10 mm
Coarse aggregate 10-4.75 mm
Unit
kg
cum
cum
Quantity
3424
5.56
3.00
UNIT:
20.00 Rm
Rate
Amount
in Rs.
in Rs
4.00 13696.00
1210.00 6732.44
875.00 2621.50
71
B. MACHINERY:
Sl No
Description
1
2
sqm
76.00
Unit
Quantity
C. LABOUR:
Sl No
Description
65.68 4991.76
Rs: 28041.70
Rate
in Rs.
8.00
8.00
0.50
0.50
Unit
Quantity
1
2
3
4
51.70
38.00
6.70
76.10
Rs:
Rate
in Rs.
8.00
0.50
1.00
2.00
6.00
2.00
2.00
8.56
3.00
Amount
in Rs
189.80 1518.40
72.10 36.05
385.00 385.00
295.00
295.00
295.00
295.00
295.00
345.00
Rs:
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Rs:
Rs:
Rs:
Rs:
Rs.
Total
D.Add for contractor's profit and overheads on (A+B+C)
Lead Charges for 1 Km for CA
8.56
cum @
Lead Charges for 1Km for Cement (including Loading
and Unloading Charges)
3.42
tonne @
Total cost for
20.00
Rate per
Rm
(A+B+C+D)/20
IRR-DAW-2-11
(a)
14%
30.4 Rs./Cum
124.6 Rs./Tonne
Rm
Amount
in Rs
413.60
304.00
3.35
38.05
759.00
590.00
1770.00
590.00
590.00
2525.20
1035.00
9039.65
28041.70
759.00
9039.65
37840.35
5297.65
260.22
426.6304
Rs: 43824.85
Rs: 2191.20
72
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4
5
6
7
Cement mix
Cement for incidentals @ 5 kg / cum
Coarse aggregate 20-10 mm
Coarse aggregate 10-4.75 mm
Fine aggregate (Un-Screened )
Super plasticiser
Use rate of shuttering
Scaffolding of shuttering @
Sundries
Total cost of Materials
B. MACHINERY:
Sl No
Description
1
2
3
Unit
Quantity
kg
kg
cum
cum
cum
kg
sqm
3034.5
43.35
4.51
2.43
3.81
12.14
95.00
15%
LS
2.00
Unit
Quantity
C. LABOUR:
Sl No
Description
UNIT:
36.00 Rm
Rate
Amount
in Rs.
in Rs
4.00 12138.00
4.00 173.40
1210.00 5457.10
875.00 2126.25
462.00 1760.22
80.00 971.04
235.84 22404.80
3360.72
41.00 82.00
Rs: 48473.53
Rate
in Rs.
51.70
38.00
8.00
7.60
6.70
76.10
Rs:
Amount
in Rs
413.60
304.00
64.00
60.80
3.35
38.05
883.80
8.00
0.50
8.00
2.00
1.00
189.80
72.10
136.60
385.00
370.00
Amount
in Rs
1518.40
36.05
1092.80
770.00
370.00
2.00
9.00
4.00
2.00
8.67
2.00
95.00
295.00
295.00
295.00
295.00
295.00
295.00
75.30
14%
Rs:
Rs:
Rs:
Rs:
Rs.
8.00
8.00
8.00
8.00
0.50
0.50
Unit
Quantity
1
2
3
4
5
6
Rate
in Rs.
590.00
2655.00
1180.00
590.00
2557.65
590.00
7153.50
1073.03
Rs: 20176.43
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D.Add for contractor's profit and overheads on (A+B+C)
Lead Charges for 1 Km for FA
3.81
cum @
Lead Charges for 1 Km for CA
6.94
cum @
Lead Charges for 1Km for Cement (including Loading
and Unloading Charges)
3.08
tonne @
Total cost for
36.00
Rate per
Rm
(A+B+C+D)/36
IRR-DAW-2-12
(b)
31.5 Rs./Cum
30.4 Rs./Cum
124.6 Rs./Tonne
Rm
48473.53
883.80
20176.43
69533.76
9734.73
120.015
210.98
383.50011
Rs: 79982.98
Rs: 2221.70
73
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4
5
6
7
Cement mix
Cenent for incidentals @ 5 kg / cum
Coarse aggregate 20-10 mm
Coarse aggregate 10-4.75 mm
Fine aggregate (Un-Screened )
Super plasticiser
Use rate of shuttering
Scaffolding of shuttering @
Sundries
Total cost of Materials
B. MACHINERY:
Sl No
Description
1
2
3
Unit
Quantity
kg
kg
cum
cum
cum
kg
sqm
2450
35.00
3.64
1.96
3.08
9.80
115.00
15%
LS
2.00
Unit
Quantity
C. LABOUR:
Sl No
Description
UNIT:
36.00 Rm
Rate
Amount
in Rs.
in Rs
4.00 9800.00
4.00 140.00
1210.00 4404.40
875.00 1715.00
462.00 1422.96
80.00 784.00
235.84 27121.60
4068.24
41.00 82.00
Rs: 49538.20
Rate
in Rs.
51.70
38.00
8.00
7.60
6.70
76.10
Rs:
Amount
in Rs
413.60
304.00
64.00
60.80
3.35
38.05
883.80
8.00
0.50
8.00
2.00
1.00
189.80
72.10
136.60
385.00
370.00
Amount
in Rs
1518.40
36.05
1092.80
770.00
370.00
2.00
9.00
4.00
2.00
7.00
2.00
115.00
295.00
295.00
295.00
295.00
295.00
295.00
75.30
14%
Rs:
Rs:
Rs:
Rs:
Rs.
8.00
8.00
8.00
8.00
0.50
0.50
Unit
Quantity
1
2
3
4
5
6
Rate
in Rs.
590.00
2655.00
1180.00
590.00
2065.00
590.00
8659.50
1298.93
Rs: 21415.68
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D.Add for contractor's profit and overheads on (A+B+C)
Lead Charges for 1 Km for FA
3.08
cum @
Lead Charges for 1 Km for CA
5.60
cum @
Lead Charges for 1Km for Cement (including Loading
2.49
tonne @
and Unloading Charges)
Total cost for
36.00
Rate per
Rm
(A+B+C+D)/36
IRR-DAW-2-13
31.5 Rs./Cum
30.4 Rs./Cum
124.6 Rs./Tonne
Rm
49538.20
883.80
21415.68
71837.68
10057.27
97.02
170.24
309.631
Rs: 82471.84
Rs: 2290.90
74
RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4
5
6
B. MACHINERY:
Sl No
Description
1
2
Unit
Quantity
kg
kg
cum
cum
cum
kg
sqm
LS
4446
58.50
6.084
3.276
5.265
17.78
5.85
5.00
Unit
Quantity
C. LABOUR:
Sl No
Description
UNIT:
11.70 cum
Rate
Amount
in Rs.
in Rs
4.00
17784.00
4.00
234.00
1210.00
7361.64
875.00
2866.50
462.00
2432.43
80.00
1422.72
235.84
1379.66
41.00
205.00
Rs:
33685.95
Rate
in Rs.
51.70
38.00
6.70
76.10
Rs:
Amount
in Rs
413.60
304.00
3.35
38.05
759.00
8.00
0.50
3.00
1.00
189.80
72.10
385.00
370.00
Amount
in Rs
1518.40
36.05
1155.00
370.00
2.00
9.00
4.00
5.00
11.70
1.00
5.85
295.00
295.00
295.00
295.00
295.00
295.00
75.30
Rs:
590.00
2655.00
1180.00
1475.00
3451.50
295.00
440.51
13166.46
8.00
8.00
0.50
0.50
Unit
Quantity
1
2
3
4
5
Rate
in Rs.
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Rs:
33685.95
Rs:
759.00
Rs:
13166.46
Rs:
47611.41
Rs. 6665.6
165.8475
284.54
Total
D.Add for contractor's profit and overheads on (A+B+C)
Lead Charges for 1 Km for FA
5.27
Lead Charges for 1 Km for CA
9.36
14%
cum @
cum @
31.5 Rs./Cum
30.4 Rs./Cum
IRR-DAW-2-14
DATA:
124.6 Rs./Tonne
cum
561.2607
Rs: 55288.66
Rs: 4725.50
Unit
Quantity
LS
3.00
0.00
Unit
Hour
Quantity
UNIT:
500 cum
Rate
Amount
in Rs.
in Rs
41.00 123.00
0.00 0.00
Rs:
123.00
Rate
in Rs.
24.00
Amount
in Rs
170.20 4084.80
75
Compressor 125 hp - 1 No
Condenser with 30 hp motor - 1 No.
Ice makers 10 t / day each - 3 Nos.
Pump 2 hp for ice cutting - 3 Nos.
Pump 2 hp for pumping water-3 Nos.
Screw conveyor with 15 hp motor -1
Ice elevator with 5 hp motor - 1 No.
Fuel / Energy charges for system
Hour
Total hire charges of Machinery
C. LABOUR:
Sl No
Description
24.00
Unit
Quantity
1
2
1084.30 26023.20
Rs: 30108.00
Rate
in Rs.
24.00
6.00
3.00
295.00 1770.00
295.00 885.00
Rs: 5388.60
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:
Total
D.Add for contractor's profit and overheads on (A+B+C)
Total cost for
500.00 cum
Rate per
cum
(A+B+C+D)/500
IRR-DAW-2-15
14%
123.00
30108.00
5388.60
35619.60
4986.74
40606.34
81.20
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
Unit
Quantity
kg
LS
B. MACHINERY:
Sl No
Description
0.60
2.00
Unit
Quantity
Nil
UNIT:
6.00 Nos.
Rate
Amount
in Rs.
in Rs
348.00 208.80
41.00 82.00
Rs: 290.80
Rate
in Rs.
Amount
in Rs
0.00 0.00
0.00 0.00
Rs: 0.00
Rate
in Rs.
Amount
in Rs
440.00
370.00
590.00
1400.00
0.00
0.00
Total hire charges of Machinery
C. LABOUR:
Sl No
Description
1
2
3
Marker / Erector
work inspector
mazdoor
Unit
Quantity
Day
Day
Day
1.00
1.00
2.00
440.00
370.00
295.00
Rs:
233.30
0.14 32.70
266.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D.Add for contractor's profit and overheads on (A+B+C)
Total cost for
6.00 Nos.
Rate per
Each
(A+B+C+D)/6
IRR-DAW-2-16
Amount
in Rs
113.90 2733.60
Total
14%
Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:
290.80
0.00
1400.00
1690.80
236.71
1927.51
321.30
Providing and constructing 150 mm dia hume pipe weep holes for
concrete / masonry walls including providing 20 x 20 x 20 cm size porous
concrete block made of cement and 20 mm down coarse aggregate in
1 : 4 proportion including 10 cm thick sand backing at the junction of wall
and soil back fill, cost of all materials, machinery, labour etc., complete
with lead upto 1 km and all lifts.
76
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4
Unit
Rm
kg
cum
cum
B. MACHINERY:
Sl No
Description
1
Quantity
2.90
3.00
0.01
0.02
Unit
Quantity
Nil
UNIT:
3.00 Rm
Rate
Amount
in Rs.
in Rs
330.00 957.00
4.00 12.00
1210.00 9.68
342.00 6.84
Rs: 985.52
Rate
in Rs.
Amount
in Rs
0.00 0.00
0.00 0.00
Rs: 0.00
Rate
in Rs.
Amount
in Rs
345.00 86.25
295.00 73.75
Rs: 160.00
0.00
0.00
Total hire charges of Machinery
C. LABOUR:
Sl No
Description
1
2
Mason Class-II
mazdoor
Unit
Quantity
Day
Day
0.25
0.25
53.30
0.14 7.50
60.80
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Rs:
Rs:
Rs:
Rs:
Rs.
Total
D.Add for contractor's profit and overheads on (A+B+C)
Lead Charges for 1 Km for FA
0.02
cum @
Lead Charges for 1 Km for CA
0.01
cum @
Lead Charges for 1Km for Cement (including Loading
0.00
tonne @
and Unloading Charges)
Total cost for
3.00
Rate per
Rm
(A+B+C+D)/3
IRR-DAW-2-17
14%
31.5 Rs./Cum
30.4 Rs./Cum
124.6 Rs./Tonne
Rm
985.52
0.00
160.00
1145.52
160.37
0.63
0.24
0.3738
Rs: 1307.14
Rs: 435.70
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4
5
6
B. MACHINERY:
Sl No
Description
1
2
Quantity
kg
kg
kg
Nos
sqm
LS
Unit
50.70
104.50
27.40
70.00
1.00
1.50
Quantity
Welding set
Hour
Fuel / Energy charges
Hour
Sundries (cutting torch/ welding guns etc)
LS
Total hire charges of Machinery
C. LABOUR:
Sl No
Description
1
2
3
Unit
Unit
UNIT:
7.50 Rm
Rate
Amount
in Rs.
in Rs
46.00 2332.20
45.00 4702.50
46.50 1274.10
11.00 770.00
630.00 630.00
41.00 61.50
Rs: 9770.30
Rate
in Rs.
8.00
8.00
2.00
Quantity
Day
Day
Day
Total cost of Labour
labour component/unit qty
243.70
Add contractor's profit and overhead charges
0.14 34.10
labour component/unit qty (including contractor's profit)
277.80
16.00
91.30
41.00
Rs:
Amount
in Rs
128.00
730.40
82.00
940.40
440.00
385.00
295.00
Rs:
Amount
in Rs
660.00
577.50
590.00
1827.50
Rate
in Rs.
1.50
1.50
2.00
77
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
14%
0.18
tonne @
7.50
(A+B+C+D)/7.50
145.6 Rs./Tonne
Rm
IRR_DAW-3
IRR-DAW-3-1
DATA:
Rs:
Rs:
Rs:
Rs:
Rs.
26.58656
Rs: 14320.14
Rs: 1909.40
RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4
B. MACHINERY:
Sl No
Description
1
2
C. LABOUR:
Sl No
Description
UNIT:
25.00
Unit
Quantity
kg
cum
cum
cum
Total cost of Materials
Unit
Rate
in Rs.
4750
21.25
3.75
10
4.00
318.00
340.00
606.00
Rs:
Quantity
Hour
Hour
Hour
Hour
Rate
in Rs.
Unit
51.70
38.00
6.70
76.10
Rs:
8.00
1.00
1.00
2.50
4.00
16.00
189.80
72.10
370.00
385.00
345.00
345.00
Amount
in Rs
1518.40
72.10
370.00
962.50
1380.00
5520.00
2.00
6.00
4.00
10.00
1.00
4.00
12.00
295.00
295.00
295.00
295.00
295.00
295.00
295.00
Rs:
590.00
1770.00
1180.00
2950.00
295.00
1180.00
3540.00
21328.00
Rs:
Rs:
Rs:
Rs:
Rs.
33092.50
800.40
21328.00
55220.90
7730.93
315
760.00
Quantity
Rate
in Rs.
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D.Add for contractor's profit and overheads on (A+B+C)
Lead Charges for 1 Km for FA
10.00
cum @
Lead Charges for 1 Km for Stones/Stone Chips
25.00
cum @
Lead Charges for 1Km for Cement (including Loading
4.75
tonne @
and Unloading Charges)
Total cost for
25.00
Rate per
cum
(A+B+C+D)/25
cum
Amount
in Rs
19000.00
6757.50
1275.00
6060.00
33092.50
Amount
in Rs
413.60
304.00
6.70
76.10
800.40
8.00
8.00
1.00
1.00
1
2
3
4
5
6
7
IRR-DAW-3-2
9770.30
940.40
1827.50
12538.20
1755.35
14%
31.5 Rs./Cum
30.4 Rs./Cum
124.6 Rs./Tonne
cum
591.85
Rs: 64618.68
Rs: 2584.70
Providing and constructing un-coursed rubble stone masonry using approved stones in
cement mortar 1 : 4 proportion including cost of all materials, machinery, labour, scaffolding,
cleaning, packing mortar, wedging stone chips, curing etc., complete with initial lead upto
1 km and all lifts.
78
RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4
B. MACHINERY:
Sl No
Description
1
2
C. LABOUR:
Sl No
Description
Unit
Quantity
kg
cum
cum
cum
Unit
3575
21.25
3.75
10
Quantity
Hour
Hour
Hour
Hour
Unit
UNIT:
25.00 cum
Rate
Amount
in Rs.
in Rs
4.00 14300.00
318.00 6757.50
340.00 1275.00
606.00 6060.00
Rs:
28392.50
Rate
in Rs.
51.70
38.00
6.70
76.10
Rs:
Amount
in Rs
413.60
304.00
6.70
76.10
800.40
8.00
1.00
1.00
2.50
4.00
16.00
189.80
72.10
370.00
385.00
345.00
345.00
Amount
in Rs
1518.40
72.10
370.00
962.50
1380.00
5520.00
2.00
6.00
4.00
10.00
1.00
4.00
12.00
295.00
295.00
295.00
295.00
295.00
295.00
295.00
Rs:
590.00
1770.00
1180.00
2950.00
295.00
1180.00
3540.00
21328.00
Rs:
Rs:
Rs:
Rs:
Rs.
28392.50
800.40
21328.00
50520.90
7072.93
315
760.00
8.00
8.00
1.00
1.00
Quantity
1
2
3
4
5
6
7
Rate
in Rs.
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D.Add for contractor's profit and overheads on (A+B+C)
Lead Charges for 1 Km for FA
10.00
cum @
Lead Charges for 1 Km for Stones/Stone Chips
25.00
cum @
Lead Charges for 1Km for Cement (including Loading
and Unloading Charges)
3.58
tonne @
Total cost for
25.00
Rate per
cum
(A+B+C+D)/25
IRR-DAW-3-3
Total
14%
31.5 Rs./Cum
30.4 Rs./Cum
124.6 Rs./Tonne
cum
445.445
Rs: 59114.28
Rs: 2364.60
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4
5
6
Unit
Quantity
4450
244
82
8.75
3.75
9.375
UNIT:
25.00 cum
Rate
Amount
in Rs.
in Rs
4.00 17800.00
20.00 4880.00
23.00 1886.00
318.00 2782.50
340.00 1275.00
606.00 5681.25
Rs: 34304.75
79
B. MACHINERY:
Sl No
Description
Unit
Quantity
Rate
in Rs.
51.70
38.00
6.70
76.10
Rs:
Amount
in Rs
413.60
304.00
6.70
76.10
800.40
8.00
1.00
1.00
7.00
2.50
4.00
16.00
189.80
72.10
370.00
345.00
385.00
345.00
345.00
Amount
in Rs
1518.40
72.10
370.00
2415.00
962.50
1380.00
5520.00
2.00
6.00
4.00
10.00
1.00
4.00
12.00
295.00
295.00
295.00
295.00
295.00
295.00
295.00
Rs:
590.00
1770.00
1180.00
2950.00
295.00
1180.00
3540.00
23743.00
Rs:
Rs:
Rs:
Rs:
Rs.
34304.75
800.40
23743.00
58848.15
8238.74
295.3125
815.02
8.00
8.00
1.00
1.00
Quantity
1
2
3
4
5
6
7
8
Rate
in Rs.
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D.Add for contractor's profit and overheads on (A+B+C)
Lead Charges for 1 Km for FA
9.38
Lead Charges for 1 Km for Stones/Stone Chips
26.81
14%
cum @
cum @
31.5 Rs./Cum
30.4 Rs./Cum
IRR-DAW-3-4
124.6 Rs./Tonne
cum
554.47
Rs: 68751.70
Rs: 2750.10
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4
5
6
B. MACHINERY:
Sl No
Description
1
2
Unit
Quantity
kg
Nos
Nos
cum
cum
cum
Unit
3350
244
82
8.75
3.75
9.375
Quantity
C. LABOUR:
Sl No
Description
Unit
UNIT:
25.00 cum
Rate
Amount
in Rs.
in Rs
4.00 13400.00
20.00 4880.00
23.00 1886.00
318.00 2782.50
340.00 1275.00
606.00 5681.25
Rs: 29904.75
Rate
in Rs.
8.00
8.00
1.00
1.00
Quantity
51.70
38.00
6.70
76.10
Rs:
Rate
in Rs.
Amount
in Rs
413.60
304.00
6.70
76.10
800.40
Amount
in Rs
80
1
2
3
4
5
6
7
8
8.00
1.00
1.00
7.00
2.50
4.00
16.00
189.80
72.10
370.00
345.00
385.00
345.00
345.00
1518.40
72.10
370.00
2415.00
962.50
1380.00
5520.00
2.00
6.00
4.00
10.00
1.00
4.00
12.00
295.00
295.00
295.00
295.00
295.00
295.00
295.00
590.00
1770.00
1180.00
2950.00
295.00
1180.00
3540.00
23743.00
Rs:
Rs:
Rs:
Rs:
Rs.
29904.75
800.40
23743.00
54448.15
7622.74
295.3125
815.02
Rs:
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D.Add for contractor's profit and overheads on (A+B+C)
Lead Charges for 1 Km for FA
9.38
cum @
Lead Charges for 1 Km for Stones/Stone Chips
26.81
cum @
Lead Charges for 1Km for Cement (including Loading
3.35
tonne @
and Unloading Charges)
Total cost for
25.00
Rate per
cum
(A+B+C+D)/25
IRR-DAW-3-5
14%
31.5 Rs./Cum
30.4 Rs./Cum
124.6 Rs./Tonne
cum
417.41
Rs: 63598.64
Rs: 2543.90
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4
5
6
B. MACHINERY:
Sl No
Description
1
2
Quantity
kg
Nos
Nos
cum
cum
cum
Unit
4175
250
85
8.75
3.75
8.75
Quantity
C. LABOUR:
Sl No
Description
1
2
3
4
5
6
7
8
9
Unit
Unit
UNIT:
25.00 cum
Rate
Amount
in Rs.
in Rs
4.00 16700.00
20.00 5000.00
23.00 1955.00
318.00 2782.50
340.00 1275.00
606.00 5302.50
Rs: 33015.00
Rate
in Rs.
8.00
8.00
1.00
1.00
Quantity
51.70
38.00
6.70
76.10
Rs:
Amount
in Rs
413.60
304.00
6.70
76.10
800.40
Rate
in Rs.
Hour
Hour
Day
Day
Day
Day
Day
Day
8.00
1.00
1.00
14.00
7.00
2.50
4.00
16.00
189.80
72.10
370.00
385.00
345.00
385.00
345.00
345.00
Amount
in Rs
1518.40
72.10
370.00
5390.00
2415.00
962.50
1380.00
5520.00
Day
Day
Day
Day
2.00
6.00
4.00
10.00
295.00
295.00
295.00
295.00
590.00
1770.00
1180.00
2950.00
81
1.00
4.00
12.00
295.00
295.00
295.00
Rs:
295.00
1180.00
3540.00
29133.00
Rs:
Rs:
Rs:
Rs:
Rs.
33015.00
800.40
29133.00
62948.40
8812.78
275.625
827.34
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D.Add for contractor's profit and overheads on (A+B+C)
Lead Charges for 1 Km for FA
8.75
Lead Charges for 1 Km for Stones/Stone Chips
27.22
14%
cum @
cum @
31.5 Rs./Cum
30.4 Rs./Cum
IRR-DAW-3-6
124.6 Rs./Tonne
cum
520.205
Rs: 73384.35
Rs: 2935.40
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4
5
6
B. MACHINERY:
Sl No
Description
1
2
Unit
Quantity
kg
Nos
Nos
cum
cum
cum
Unit
3125
250
85
8.75
3.75
8.75
Quantity
C. LABOUR:
Sl No
Description
1
2
3
4
5
6
7
8
9
Unit
UNIT:
25.00 cum
Rate
Amount
in Rs.
in Rs
4.00 12500.00
20.00 5000.00
23.00 1955.00
318.00 2782.50
340.00 1275.00
606.00 5302.50
Rs: 28815.00
Rate
in Rs.
51.70
38.00
6.70
76.10
Rs:
Amount
in Rs
413.60
304.00
6.70
76.10
800.40
8.00
1.00
1.00
14.00
7.00
2.50
4.00
16.00
189.80
72.10
370.00
385.00
345.00
385.00
345.00
345.00
Amount
in Rs
1518.40
72.10
370.00
5390.00
2415.00
962.50
1380.00
5520.00
2.00
6.00
4.00
10.00
1.00
4.00
12.00
295.00
295.00
295.00
295.00
295.00
295.00
295.00
Rs:
590.00
1770.00
1180.00
2950.00
295.00
1180.00
3540.00
29133.00
8.00
8.00
1.00
1.00
Quantity
Rate
in Rs.
Rs: 28815.00
Rs: 800.40
82
C. Cost of Labour
Rs: 29133.00
Rs: 58748.40
Rs. 8224.78
275.625
827.34
Total
D.Add for contractor's profit and overheads on (A+B+C)
Lead Charges for 1 Km for FA
8.75
cum @
Lead Charges for 1 Km for Stones/Stone Chips
27.22
cum @
Lead Charges for 1Km for Cement (including Loading
and Unloading Charges)
3.13
tonne @
Total cost for
25.00
Rate per
cum
(A+B+C+D)/25
IRR-DAW-3-7
14%
31.5 Rs./Cum
30.4 Rs./Cum
124.6 Rs./Tonne
cum
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
Cement
Sand (Screened )
Unit
Quantity
kg
cum
455.446
0.735
Unit
Quantity
1 NIL
(Manual mixing )
UNIT:
100.00 sqm
Rate
Amount
in Rs.
in Rs
4.00 1821.78
606.00 445.41
Rs: 2267.19
Rate
in Rs.
Amount
in Rs
0.00 0.00
0.00 0.00
Rs: 0.00
Rate
in Rs.
Amount
in Rs
385.00 3850.00
295.00 2950.00
Rs: 6800.00
0.00
0.00
Total hire charges of Machinery
C. LABOUR:
Sl No
Description
1
2
Mason Class-I
mazdoor
Unit
Quantity
Day
Day
10.00
10.00
68.00
14% 9.50
77.50
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Rs:
Rs:
Rs:
Rs:
Rs.
Total
D.Add for contractor's profit and overheads on (A+B+C)
Lead Charges for 1 Km for FA
0.74
cum @
Lead Charges for 1Km for Cement (including Loading
and Unloading Charges)
0.46
tonne @
Total cost for
100.00
Rate per
sqm
(A+B+C+D)/100
IRR-DAW-3-8
389.375
Rs: 68465.52
Rs: 2738.60
14%
31.5 Rs./Cum
124.6 Rs./Tonne
sqm
2267.19
0.00
6800.00
9067.19
1269.41
23.1525
56.748572
Rs: 10416.51
Rs: 104.20
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
Cement
Sand (Screened )
Unit
Quantity
kg
cum
321.80
0.74
Unit
Quantity
NIL
Manual mixing )
UNIT:
100.00 sqm
Rate
Amount
in Rs.
in Rs
4.00 1287.20
606.00 445.41
Rs: 1732.61
Rate
in Rs.
Amount
in Rs
0.00 0.00
0.00 0.00
Rs: 0.00
Rate
in Rs.
Amount
in Rs
385.00 3850.00
0.00
0.00
Total hire charges of Machinery
C. LABOUR:
Sl No
Description
1
Mason Class-I
Unit
Day
Quantity
10.00
83
mazdoor
Day
10.00
295.00 2950.00
Rs: 6800.00
68.00
14% 9.50
77.50
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Rs:
Rs:
Rs:
Rs:
Rs.
Total
D.Add for contractor's profit and overheads on (A+B+C)
Lead Charges for 1 Km for FA
0.74
cum @
Lead Charges for 1Km for Cement (including Loading
and Unloading Charges)
0.32
tonne @
Total cost for
100.00
Rate per
sqm
(A+B+C+D)/100
IRR_DAW-4
IRR-DAW-4-1
DATA:
14%
31.5 Rs./Cum
124.6 Rs./Tonne
sqm
1732.61
0.00
6800.00
8532.61
1194.57
23.1525
40.09628
Rs: 9790.43
Rs: 97.90
RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4
5
6
Cement
Sand (Screened )
Use rate of grout hose 25 m
Use rate of water hose 25 m
Use rate of guniting nozzle
Sundries
Total cost of Materials
B. MACHINERY:
Sl No
Description
1
2
3
4
Unit
Quantity
kg
cum
Hour
Hour
Hour
LS
609.90
1.09
8.00
8.00
8.00
2.00
Unit
Quantity
Guniting equipment
Hour
Fuel / Energy charges
Hour
Air compressor 8.5 cmm ( ele )
Hour
Fuel / Energy charges
Hour
Pump 10 hp ( ele )
Hour
Fuel / Energy charges
Hour
Sundries
LS
Total hire charges of Machinery
C. LABOUR:
Sl No
Description
UNIT :
36.00 sqm
Rate
Amount
in Rs.
in Rs
4.00 2439.60
606.00 660.54
5.47 43.75
6.84 54.75
3.50 28.00
41.00 82.00
Rs: 3308.64
Rate
in Rs.
110.10
0.00
170.80
428.00
6.70
76.10
41.00
Rs:
Amount
in Rs
880.80
0.00
1366.40
3424.00
6.70
76.10
82.00
5836.00
8.00
8.00
1.00
1.00
189.80
142.40
72.10
345.00
Amount
in Rs
1518.40
1139.20
72.10
345.00
2.00
2.00
2.00
295.00
295.00
295.00
Rs:
590.00
590.00
590.00
4844.70
8.00
8.00
8.00
8.00
1.00
1.00
2.00
Unit
Quantity
1
2
3
4
5
Rate
in Rs.
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Rs:
Rs:
Rs:
Rs:
Total
Add for scaffolding
3%
Total
14%
31.5 Rs./Cum
124.6 Rs./Tonne
sqm
3308.64
5836.00
4844.70
13989.34
349.73
Rs: 14339.07
Rs. 2007.47
34.335
75.99354
Rs: 16456.87
Rs: 457.10
84
IRR-DAW-4-2
DATA:
Unit
Quantity
kg
kg
Rm
kg
LS
LS
B. MACHINERY:
Sl No
Description
215.00
30.00
24.00
192.00
5.00
40.00
Unit
Quantity
Welder
Tinsmith
Bar bender
Pipe fitter
Mason Class-I
mazdoor
Rate
in Rs.
Amount
in Rs
17.00 136.00
17.00 170.00
Rs: 306.00
Rate
in Rs.
Amount
in Rs
385.00
385.00
225.00
220.00
192.50
295.00
1702.50
8.00
10.00
Unit
Quantity
Day
Day
Day
Day
Day
Day
UNIT:
12.00 Rm
Rate
Amount
in Rs.
in Rs
695.00 149425.00
46.50 1395.00
110.00 2640.00
43.00 8256.00
17.00 85.00
17.00 680.00
Rs:
162481.00
1.00
1.00
0.50
0.50
0.50
1.00
385.00
385.00
450.00
440.00
385.00
295.00
Rs:
141.90
14% 19.90
161.80
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
14%
IRR-DAW-4-3
Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:
162481.00
306.00
1702.50
164489.50
23028.53
187518.03
15626.50
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4
5
6
B. MACHINERY:
Sl No
Description
Unit
Quantity
Rm
kg
Rm
kg
LS
LS
Unit
24.50
30.00
24.00
192.00
5.00
25.00
Quantity
UNIT:
12.00 Rm.
Rate
Amount
in Rs.
in Rs
485.00 11882.50
46.50 1395.00
110.00 2640.00
43.00 8256.00
17.00 85.00
17.00 425.00
Rs: 24683.50
Rate
in Rs.
Amount
in Rs
85
C. LABOUR:
Sl No
Description
1
2
3
4
5
Welder
Bar bender
Pipe fitter
Mason Class-I
mazdoor
8.00
10.00
Unit
Quantity
Day
Day
Day
Day
Day
17.00 136.00
17.00 170.00
Rs: 306.00
Rate
in Rs.
0.50
0.50
0.50
0.50
1.00
Total
14%
RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
Unit
Welder
Tinsmith
Bar bender
Mason Class-I
mazdoor
77.00
15.00
10.00
Unit
Quantity
LS
LS
C. LABOUR:
Sl No
Description
1
2
3
4
5
Quantity
kg
kg
LS
B. MACHINERY:
Sl No
Description
UNIT:
8.7 Rm
Rate
Amount
in Rs.
in Rs
695.00 53515.00
46.50 697.50
17.00 170.00
Rs: 54382.50
Rate
in Rs.
Amount
in Rs
41.00 123.00
17.00 85.00
Rs: 208.00
Rate
in Rs.
385.00
385.00
450.00
385.00
295.00
Rs:
Amount
in Rs
192.50
192.50
225.00
192.50
147.50
950.00
Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:
54382.50
208.00
950.00
55540.50
7775.67
63316.17
7277.70
3.00
5.00
Unit
Quantity
Day
Day
Day
Day
Day
0.5
0.5
0.5
0.5
0.5
109.20
14% 15.30
124.50
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D.Add for contractor's profit and overheads on (A+B+C)
Total cost for
8.70 Rm
Rate per
Rm
(A+B+C+D)/8.70
DATA:
24683.50
306.00
1125.00
26114.50
3656.03
29770.53
2480.90
DATA:
IRR-DAW-4-5
Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:
93.80
14% 13.10
106.90
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
IRR-DAW-4-4
385.00
450.00
440.00
385.00
295.00
Rs:
Amount
in Rs
192.50
225.00
220.00
192.50
295.00
1125.00
Total
14%
86
A. MATERIALS:
Sl No
Particulars
1
2
3
Unit
Rm
kg
LS
B. MACHINERY:
Sl No
Description
1
9.00
10.00
2.00
Unit
Quantity
C. LABOUR:
Sl No
Description
1
2
3
4
Quantity
Welder
Bar bender
Mason Class-I
mazdoor
Rate
in Rs.
Amount
in Rs
41.00 20.50
17.00 8.50
29.00
Rate
in Rs.
Amount
in Rs
192.50
225.00
192.50
147.50
757.50
0.50
0.50
Unit
Quantity
Day
Day
Day
Day
8.70 Rm
Rate
Amount
in Rs.
in Rs
44.00 396.00
46.50 465.00
17.00 34.00
Rs: 895.00
0.50
0.50
0.50
0.50
385.00
450.00
385.00
295.00
Rs:
87.10
14% 12.20
99.30
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:
Total
14%
IRR-DAW-5-1
DATA:
895.00
29.00
757.50
1681.50
235.41
1916.91
220.30
RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
Unit
Quantity
1 NIL
0.00
0.00
Total cost of Materials
B. MACHINERY:
Sl No
Description
1
2
3
4
5
6
7
Quantity
Angle dozer 90 hp
Hour
Fuel / Energy charges
Hour
Shovel 0.85 cum capacity
Hour
Fuel / Energy charges
Hour
Tippers 5.00 cum capacity 5 Nos.
Hour
Fuel / Energy charges
Hour
Pump 5 hp ( ele )
Hour
Fuel / Energy charges
Hour
Water tanker 8000 ltr
Hour
Fuel / Energy charges
Hour
Vibratory Roller 8 tonne
Hour
Fuel / Energy charges
Hour
Sundries
LS
Total hire charges of Machinery
C. LABOUR:
Sl No
Description
1
2
3
4
5
Unit
Unit
Hour
Hour
Hour
Hour
Hour
5.50
5.50
8.00
8.00
40.00
40.00
4.00
4.00
8.00
8.00
6.50
6.50
2.00
Quantity
5.50
8.00
40.00
4.00
8.00
UNIT
825.00 cum
Rate
Amount
in Rs.
in Rs
0.00 0.00
0.00 0.00
Rs: 0.00
Rate
in Rs.
1715.50
656.00
1706.60
937.80
446.70
322.20
3.00
38.00
402.50
322.20
1342.20
1108.30
41.00
Rs:
Amount
in Rs
9435.25
3608.00
13652.80
7502.40
17868.00
12888.00
12.00
152.00
3220.00
2577.60
8724.30
7203.95
82.00
86926.30
Rate
in Rs.
Amount
in Rs
1122.55
1632.80
6124.00
288.40
1224.80
204.10
204.10
153.10
72.10
153.10
87
6
7
8
Hour
Day
Day
6.50
2.00
4.00
227.80
370.00
295.00
Rs:
16.70
14% 2.30
19.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
0.00
86926.30
13793.25
100719.55
14100.74
114820.29
139.20
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
Unit
Quantity
1 NIL
0.00
0.00
Total cost of Materials
B. MACHINERY:
Sl No Description
1
2
3
4
5
6
7
Unit
Quantity
Angle dozer 90 hp
Hour
Fuel / Energy charges
Hour
Shovel 0.85 cum capacity
Hour
Fuel / Energy charges
Hour
Tippers 5.00 cum capacity 6 Nos.
Hour
Fuel / Energy charges
Hour
Pump 5 hp ( ele )
Hour
Fuel / Energy charges
Hour
Water tanker 8000 ltr
Hour
Fuel / Energy charges
Hour
Vibratory Roller 8 tonne
Hour
Fuel / Energy charges
Hour
Sundries
LS
Total hire charges of Machinery
C. LABOUR:
Sl No Description
Unit
5.50
5.50
8.00
8.00
48.00
48.00
4.00
4.00
8.00
8.00
6.50
6.50
2.00
Quantity
1
2
3
4
5
6
7
8
5.50
8.00
48.00
4.00
8.00
6.50
2.00
4.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D.Add for contractor's profit and overheads on (A+B+C)
Total cost for
825.00 cum
Rate per
cum
(A+B+C+D)/825
IRR-DAW-5-3
Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:
Total
14%
IRR-DAW-5-2
1480.70
740.00
1180.00
13793.25
Total
14%
UNIT :
825.00 cum
Rate
Amount
in Rs.
in Rs
0.00 0.00
0.00 0.00
Rs: 0.00
Rate
in Rs.
1715.50
656.00
1706.60
937.80
446.70
322.20
3.00
38.00
402.50
322.20
1342.20
1108.30
41.00
Rs:
Amount
in Rs
9435.25
3608.00
13652.80
7502.40
21441.60
15465.60
12.00
152.00
3220.00
2577.60
8724.30
7203.95
82.00
93077.50
Rate
in Rs.
204.10
204.10
153.10
72.10
153.10
227.80
370.00
295.00
Rs:
Amount
in Rs
1122.55
1632.80
7348.80
288.40
1224.80
1480.70
740.00
1180.00
15018.05
Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:
0.00
93077.50
15018.05
108095.55
15133.38
123228.93
149.40
88
RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
Unit
UNIT :
630 cum
Rate
Amount
in Rs.
in Rs
0.00 0.00
0.00 0.00
Rs: 0.00
Quantity
1 NIL
0.00
0.00
Total cost of Materials
B. MACHINERY:
Sl No
Description
1
2
3
4
5
6
7
Quantity
Angle dozer 90 hp
Hour
Fuel / Energy charges
Hour
Shovel 0.85 cum
Hour
Fuel / Energy charges
Hour
Tipper 5 cum
Hour
Fuel / Energy charges
Hour
Pump 5 hp ( ele )
Hour
Fuel / Energy charges
Hour
Water tanker 8000 ltr
Hour
Fuel / Energy charges
Hour
Vibratory Roller 8 tonne
Hour
Fuel / Energy charges
Hour
Sundries
LS
Total hire charges of Machinery
C. LABOUR:
Sl No
Description
1
2
3
4
5
6
7
8
Unit
Unit
4.00
4.00
8.00
8.00
32.00
32.00
3.00
3.00
5.00
5.00
5.00
5.00
5.00
Quantity
Hour
Hour
Hour
Hour
Hour
Hour
Day
Day
Total cost of Labour
labour component/unit qty
18.10
Add contractor's profit and overhead charges
14% 2.50
labour component/unit qty (including contractor's profit)
20.60
4.00
8.00
32.00
3.00
5.00
5.00
2.00
4.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
14%
IRR-DAW-5-4
Rate
in Rs.
1715.50
656.00
1706.60
937.80
446.70
322.20
3.00
38.00
402.50
322.20
1342.20
1108.30
41.00
Rs:
Amount
in Rs
6862.00
2624.00
13652.80
7502.40
14294.40
10310.40
9.00
114.00
2012.50
1611.00
6711.00
5541.50
205.00
71450.00
Rate
in Rs.
204.10
204.10
153.10
72.10
153.10
227.80
370.00
295.00
Rs:
Amount
in Rs
816.40
1632.80
4899.20
216.30
765.50
1139.00
740.00
1180.00
11389.20
Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:
0.00
71450.00
11389.20
82839.20
11597.49
94436.69
149.90
DATA:
RATE ANALYSIS
UNIT :
A. MATERIALS:
Sl No
Particulars
Unit
Quantity
1 NIL
0.00
0.00
Total cost of Materials
B. MACHINERY:
Sl No
Description
1
Angle dozer 90 hp
Fuel / Energy charges
Unit
Hour
Hour
Quantity
4.60
4.60
970.00 cum
Rate
Amount
in Rs.
in Rs
0.00 0.00
0.00 0.00
Rs: 0.00
Rate
Amount
in Rs.
in Rs
1715.50 7891.30
656.00 3017.60
89
2
3
4
5
6
7
C. LABOUR:
Sl No
Description
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS
Unit
8.00
8.00
48.00
48.00
4.00
4.00
8.00
8.00
7.00
7.00
5.00
1706.60
937.80
446.70
322.20
3.00
38.00
402.50
322.20
1342.20
1108.30
41.00
Rs:
Quantity
1
2
3
4
5
6
7
8
Rate
in Rs.
4.60
8.00
48.00
4.00
8.00
7.00
2.00
4.00
204.10
204.10
153.10
72.10
153.10
227.80
370.00
295.00
Rs:
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
14%
Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:
13652.80
7502.40
21441.60
15465.60
12.00
152.00
3220.00
2577.60
9395.40
7758.10
205.00
92291.40
Amount
in Rs
938.86
1632.80
7348.80
288.40
1224.80
1594.60
740.00
1180.00
14948.26
0.00
92291.40
14948.26
107239.66
15013.55
122253.21
126.00
DATA:
RATE ANALYSIS
UNIT :
A. MATERIALS:
Sl No
Particulars
Unit
Quantity
1 NIL
0.00
0.00
Total cost of Materials
B. MACHINERY:
Sl No
Description
1
2
3
4
5
6
7
Angle dozer 90 hp
Fuel / Energy charges
Shovel 0.85 cum
Fuel / Energy charges
Tipper 5 cum
Fuel / Energy charges
Pump 5 hp ( ele )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Vibratory Roller 8 tonne
Fuel / Energy charges
Sundries
Total hire charges of Machinery
C. LABOUR:
Sl No
Description
1
2
3
4
Unit
Quantity
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS
Unit
Hour
Hour
Hour
Hour
4.60
4.60
8.00
8.00
48.00
48.00
4.00
4.00
8.00
8.00
7.00
7.00
5.00
Quantity
4.60
8.00
48.00
4.00
970.00 cum
Rate
Amount
in Rs.
in Rs
0.00 0.00
0.00 0.00
Rs: 0.00
Rate
in Rs.
1715.50
656.00
1706.60
937.80
446.70
322.20
3.00
38.00
402.50
322.20
1342.20
1108.30
41.00
Rs:
Amount
in Rs
7891.30
3017.60
13652.80
7502.40
21441.60
15465.60
12.00
152.00
3220.00
2577.60
9395.40
7758.10
205.00
92291.40
Rate
in Rs.
Amount
in Rs
938.86
1632.80
7348.80
288.40
204.10
204.10
153.10
72.10
90
5
6
7
8
8.00
7.00
2.00
4.00
153.10
227.80
370.00
295.00
Rs:
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:
Total
14%
Rs.
1224.80
1594.60
740.00
1180.00
14948.26
0.00
92291.40
14948.26
107239.66
15013.55
122253.21
126.00
46.10
6.10
86.00
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
Unit
Quantity
NIL
0.00
0.00
Total cost of Materials
B. MACHINERY:
Sl No
Description
1
2
3
4
5
6
7
Unit
Quantity
Angle dozer 90 hp
Hour
Fuel / Energy charges
Hour
Shovel 0.85 cum capacity
Hour
Fuel / Energy charges
Hour
Tippers 5.00 cum capacity 5 Nos.
Hour
Fuel / Energy charges
Hour
Pump 5 hp ( ele )
Hour
Fuel / Energy charges
Hour
Water tanker 8000 ltr
Hour
Fuel / Energy charges
Hour
Vibratory Roller 8 tonne
Hour
Fuel / Energy charges
Hour
Sundries
LS
Total hire charges of Machinery
C. LABOUR:
Sl No
Description
Unit
1
2
3
4
5
6
7
8
5.40
5.40
8.00
8.00
40.00
40.00
4.00
4.00
8.00
8.00
6.40
6.40
2.00
Quantity
5.40
8.00
40.00
4.00
8.00
6.40
2.00
4.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D.Add for contractor's profit and overheads on (A+B+C)
Total cost for
807.00 cum
Rate per
cum
(A+B+C+D)/807
Total
14%
UNIT :
807.00 cum
Rate
Amount
in Rs.
in Rs
0.00 0.00
0.00 0.00
Rs: 0.00
Rate
in Rs.
1715.50
656.00
1706.60
937.80
446.70
322.20
3.00
38.00
402.50
322.20
1342.20
1108.30
41.00
Rs:
Amount
in Rs
9263.70
3542.40
13652.80
7502.40
17868.00
12888.00
12.00
152.00
3220.00
2577.60
8590.08
7093.12
82.00
86444.10
Rate
in Rs.
Amount
in Rs
1102.14
1632.80
6124.00
288.40
1224.80
1457.92
740.00
1180.00
13750.06
204.10
204.10
153.10
72.10
153.10
227.80
370.00
295.00
Rs:
Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:
0.00
86444.10
13750.06
100194.16
14027.18
114221.34
141.50
91
IRR-DAW-5-6
Providing embankment adjacent to masonry / concrete structures and filling trial pits
using impervious soil from approved borrow areas in layers of 10 to 15 cm and compacting
each layer to density control of not less than 95 percent using pneumatic tampers or by
vibratory earth rammers including cost of all materials, machinery, labour, picking previous
layer, spreading soil in layer, breaking clods, watering etc., complete with initial lead upto
1 km and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No Particulars
UNIT :
Unit
Quantity
Hour
16.00
0.00
Unit
Angle dozer 90 hp
Fuel / Energy charges
Shovel 0.85 cum
Fuel / Energy charges
Tipper 5 cum
Fuel / Energy charges
Air compressor 8.5 cmm ( ele )
Fuel / Energy charges
Pump 5 hp ( ele )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Pneumatic tampers 2 Nos.
Fuel / Energy charges
Sundries
Total hire charges of Machinery
C. LABOUR:
Sl No Description
Quantity
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS
0.15
0.15
0.80
0.80
3.00
3.00
8.00
8.00
0.40
0.40
0.80
0.80
16.00
16.00
1.00
Unit
Quantity
80 cum
Rate
Amount
in Rs.
in Rs
10.94
175.00
0.00
0.00
Rs:
175.00
Rate
in Rs.
1715.50
656.00
1706.60
937.80
446.70
322.20
170.80
428.00
3.00
38.00
402.50
322.20
20.70
0.00
41.00
Rs:
Amount
in Rs
257.33
98.40
1365.28
750.24
1340.10
966.60
1366.40
3424.00
1.20
15.20
322.00
257.76
331.20
0.00
41.00
10536.71
Rate
in Rs.
Amount
in Rs
30.62
163.28
459.30
1139.20
28.84
122.48
3644.80
370.00
1475.00
7433.52
0.15
0.80
3.00
8.00
0.40
0.80
16.00
1.00
5.00
1
2
3
4
5
6
7
8
9
204.10
204.10
153.10
142.40
72.10
153.10
227.80
370.00
295.00
Rs:
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
14%
IRR-DAW-5-7
Rs:
175.00
Rs:
10536.71
Rs:
7433.52
Rs:
18145.22
Rs. 2540.33
Rs: 20685.55
Rs: 258.60
Providing and constructing rockfill embankment with 300 mm down graded stones and
quarry spalls from approved source including cost of all materials, machinery, labour, spreading
stones and spalls in layers, hand packing, wedging, finishing the surface to required slopes
etc., complete with initial lead upto 1 km and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No Particulars
1
2
3
4
5
6
UNIT :
Unit
400
Quantity
Rate
in Rs.
Rm
387.00
41.69
10%
Hour
kg
Nos
Nos
Rm
60.00
118.00
159.00
8.00
200.00
10.94
70.00
13.00
9.00
11.00
cum
Amount
in Rs
16135.32
1613.53
656.25
8260.00
2067.00
72.00
2200.00
92
B. MACHINERY:
Sl No Description
1
2
3
4
5
LS
10.00
Unit
Quantity
C. LABOUR:
Sl No Description
Quantity
1
2
3
4
5
6
7
8
9
10
410.00
31414.10
275.60
959.10
19.80
0.00
1715.50
656.00
1706.60
937.80
446.70
322.20
Rs:
Amount
in Rs
8268.00
28773.00
1188.00
0.00
6862.00
2624.00
13652.80
7502.40
10720.80
7732.80
87323.80
Rate
in Rs.
30.00
30.00
60.00
60.00
4.00
4.00
8.00
8.00
24.00
24.00
Unit
41.00
Rs:
Rate
in Rs.
30.00
60.00
8.00
24.00
4.00
1.00
1.00
2.00
2.00
10.00
182.20
284.70
204.10
153.10
204.10
440.00
345.00
370.00
345.00
295.00
Rs:
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
IRR-DAW-5-8
Rs:
31414.10
Rs:
87323.80
Rs:
33836.60
Rs: 152574.50
Rs. 21360.43
Rs: 173934.93
Rs: 434.80
Total
14%
Amount
in Rs
5466.00
17082.00
1632.80
3674.40
816.40
440.00
345.00
740.00
690.00
2950.00
33836.60
Providing and constructing dry rubble rock-toe using rubble and stone chips from
approved source including cost of all materials, machinery, labour, hand packing rubble
and stone chips, finishing top and sides to required slopes etc., complete with initial lead upto
1 km and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No Particulars
1
2
3
4
5
6
7
B. MACHINERY:
Sl No Description
1
2
3
4
UNIT :
Unit
Quantity
Rm
97.00
10%
Hour
kg
Nos
Nos
Rm
LS
15.00
30.00
40.00
2.00
50.00
2.00
Unit
Quantity
100 cum
Rate
Amount
in Rs.
in Rs
41.69
4044.25
404.43
10.94
164.06
70.00
2100.00
13.00
520.00
9.00
18.00
11.00
550.00
41.00
82.00
Rs:
7882.74
Rate
in Rs.
7.50
7.50
15.00
15.00
2.00
2.00
6.00
6.00
275.60
959.10
19.80
0.00
1706.60
937.80
446.70
322.20
Rs:
Amount
in Rs
2067.00
7193.25
297.00
0.00
3413.20
1875.60
2680.20
1933.20
19459.45
C. LABOUR:
93
Sl No Description
Unit
Quantity
1
2
3
4
5
6
7
8
9
Rate
in Rs.
7.50
15.00
2.00
6.00
0.50
1.00
1.00
7.00
19.00
182.20
284.70
204.10
153.10
440.00
345.00
370.00
345.00
295.00
Rs:
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
IRR-DAW-5-9
Note:
DATA:
Rs:
7882.74
Rs:
19459.45
Rs:
15918.80
Rs:
43260.99
Rs. 6056.54
Rs: 49317.53
Rs: 493.20
Total
14.00%
Amount
in Rs
1366.50
4270.50
408.20
918.60
220.00
345.00
370.00
2415.00
5605.00
15918.80
Providing and constructing dry rubble rock-toe with rubble and stone chips from dump
yard (Spoil Bank) including cost of all materials, machinery, labour, hand packing rubble and stone chips,
finishing top and sides to required slopes etc., complete with initial lead upto 1 km and all
lifts.
Useful rubble and stone chips will be issued at dump yard at the issue rate for usefull rubble /
stone chips. Sorting out and breaking charges included in rate analysis.
RATE ANALYSIS
UNIT :
100 cum
A. MATERIALS:
Sl No Particulars
Unit
Quantity
Rate
Amount
in Rs.
in Rs
1
Useful rubble ( at dump yard )
cum
100.00
155.00
15500.00
2
Useful stone chips ( at dump yard )
cum
15.00
175.00
2625.00
Total cost of Materials
Rs:
18125.00
B. MACHINERY:
Sl No Description
1
2
Unit
C. LABOUR:
Sl No Description
1
2
3
4
6
7
Quantity
Unit
Hour
Hour
Day
Day
Day
Day
2.00
2.00
6.00
6.00
Quantity
2.00
6.00
7.00
1.00
2.00
21.00
Rate
in Rs.
1706.60
937.80
446.70
322.20
Rs:
Amount
in Rs
3413.20
1875.60
2680.20
1933.20
9902.20
Rate
in Rs.
Amount
in Rs
408.20
918.60
2415.00
370.00
690.00
6195.00
10996.80
204.10
153.10
345.00
370.00
345.00
295.00
Rs:
110.00
14% 15.40
125.40
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D.Add for contractor's profit and overheads on (A+B+C)
Total cost for
100.00 cum
Rate per
cum
(A+B+C+D)/100
Total
14%
Rs:
18125.00
Rs:
9902.20
Rs:
10996.80
Rs:
39024.00
Rs. 5463.36
Rs: 44487.36
Rs: 444.90
Providing and constructing Dry rock Pitching for Groynes using Un-Coursed rubble stone of size 300 mm thick
IRR-DAW-5-9-A
(New Item 4 -2012-13) and Un-Coursed rubble stone chips from Quarry to site of work including cost of all materials, Machinery, Labour charge
hand packing Un-Course rubble stone &chips to the designed profile with all leads and lifts etc
94
DATA:
RATE ANALYSIS
UNIT :
A. MATERIALS:
Sl No Particulars
1
2
Unit
100 cum
Quantity
cum
cum
Rate
in Rs.
100.00
15.00
318.00
340.00
Rs:
1
2
Unit
C. LABOUR:
Sl No Description
1
2
3
4
6
7
Quantity
2.00
2.00
6.00
6.00
Unit
Quantity
Hour
Hour
Day
Day
Day
Day
Rate
in Rs.
Rate
in Rs.
204.10
153.10
345.00
370.00
345.00
295.00
Rs:
3413.20
1875.60
2680.20
1933.20
9902.20
Amount
in Rs
408.20
918.60
2415.00
370.00
690.00
6195.00
10996.80
110.00
14% 15.40
125.40
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Rs:
36900.00
Rs:
9902.20
Rs:
10996.80
Rs:
57799.00
Rs. 8091.86
Rs: 65890.86
Rs: 658.90
Total
14%
IRR-DAW-5-10
Amount
in Rs
1706.60
937.80
446.70
322.20
Rs:
2.00
6.00
7.00
1.00
2.00
21.00
Amount
in Rs
31800.00
5100.00
36900.00
Providing and laying 30 cm diameter open jointed hume pipes with collars in rock-toe for
drainage including cost of all materials, machinery, labour etc., complete with lead upto 1 km
and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No Particulars
1
UNIT :
Unit
Quantity
Rm
100.00
0.00
Unit
Quantity
NIL
Rate
in Rs.
0.00
0.00
100 Rm
Rate
Amount
in Rs.
in Rs
650.00
65000.00
0.00
Rs:
65000.00
Mason Cl- II
mazdoor
Rs:
Unit
Day
Day
0.00
0.00
Quantity
Rate
in Rs.
2
6
345.00
295.00
Rs:
Amount
in Rs
0.00
0.00
0.00
Amount
in Rs
690.00
1770.00
2460.00
24.60
14% 3.40
28.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D.Add for contractor's profit and overheads on (A+B+C)
Total cost for
100.00 Rm
Rate per
Rm
(A+B+C+D)/100
Total
14%
Rs:
65000.00
Rs:
0.00
Rs:
2460.00
Rs:
67460.00
Rs. 9444.4
Rs: 76904.40
Rs: 769.00
95
IRR_DAW-6
IRR-DAW-6-1
Providing and constructing 1.20 m internal diameter and average 3 m height RCC manhole with
60 cm dia. top cover in M-15 grade cement concrete using 20 mm down graded, clean, hard
coarse aggregate, 20 cm thick for bed / sides / top slab / 1.5 m long cut-off wall and 7.5 cm
thick for cover including providing 12 mm dia reinforcement bars at 30 cm c / c bothways for
bed / sides / cut-off wall / top slab / rungs and 8 mm dia bars at 15 cm c / c bothways for cover,
excavation for foundation, providing 30 cm dia hume pipe outlet, cost of all materials, machinery,
labour, formwork, scaffolding, batching, mixing, laying, vibrating, finishing, curing etc., complete
with lead upto 1 km and all lifts.
( Cement content : 300 kg/cum , CA : 0.80 cum, Blending Ratioof CA -- 65:35,
FA : 0.44 cum, superplasticizer (0.4% by wt. of cement)
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No Particulars
1
2
3
4
5
6
7
8
9
10
Cement
Cement for incidentals @ 3 kg / cum
Coarse aggregate 20 to 10 mm
Coarse aggregate 10 to 4.75 mm
Fine aggregate (Un-Screened )
Super plasticiser
Reinforcement steel with 5 % wastage
Binding wire
Hume pipe 300 mm dia
Use rate of shuttering
Scaffolding of shuttering @
Sundries
B. MACHINERY:
Sl No Description
1
2
3
4
C. LABOUR:
Sl No Description
1
2
3
4
UNIT
Unit
kg
kg
cum
cum
cum
kg
kg
kg
Rm
sqm
1331.70
13.32
2.31
1.24
1.95
23.65
163.70
4.00
1.00
36.00
5%
LS
Total cost of Materials
Unit
Unit
2.00
Quantity
Hour
Hour
Hour
Hour
Hour
Hour
LS
Mason Cl- II
Day
Bar bender
Day
work inspector
Day
mazdoor
for excavation for foundation
Day
for bar bending
Day
for concreting
Day
for excavation for foundation
Day
for concreting
Day
for curing
Day
5
Labour for shuttering
sqm
Total cost of Labour
labour component/unit qty
8300.80
Add contractor's profit and overhead charges
0.14 1162.10
labour component/unit qty (including contractor's profit)
9462.90
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Quantity
1 Each
Rate
Amount
in Rs.
in Rs
4.00
5326.80
4.00
53.27
1210.00
2793.02
875.00
1087.56
462.00
902.36
80.00
1891.65
46.50
7611.82
70.00
280.00
650.00
650.00
235.84
8490.24
424.51
41.00
82.00
Rs:
29593.22
Rate
in Rs.
51.70
38.00
8.00
7.60
3.00
38.00
41.00
Rs:
Amount
in Rs
206.80
152.00
32.00
30.40
1.50
19.00
41.00
482.70
1.00
1.00
1.00
345.00
450.00
370.00
Amount
in Rs
345.00
450.00
370.00
2.00
1.00
5.00
2.00
4.00
1.00
36.00
295.00
295.00
295.00
295.00
295.00
295.00
75.30
Rs:
590.00
295.00
1475.00
590.00
1180.00
295.00
2710.80
8300.80
Rs:
Rs:
Rs:
29593.22
482.70
8300.80
4.00
4.00
4.00
4.00
0.50
0.50
1.00
Quantity
Rate
in Rs.
96
cum @
cum @
31.5 Rs./Cum
30.4 Rs./Cum
tonne @
124.6 Rs./Tonne
167.58912
tonne @
145.6 Rs./Tonne
23.833992
Rs: 44110.37
Rs: 44110.40
0.16
1.00
(A+B+C+D)/1.0
Each
Providing and constructing longitudinal and cross graded filter drains using sand and 80-20
mm and 20 mm down graded aggregates satisfying specified filter creteria in layers as per
specifications including cost of all materials, machinery, labour, laying to required slopes,
compaction etc. complete with initial lead upto 50 m and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No Particulars
1
2
3
4
5
UNIT :
Unit
Quantity
cum
cum
cum
cum
cum
B. MACHINERY:
Sl No Description
47.50
17.865
1.99
24.49
8.16
Unit
Quantity
NIL
100 cum
Rate
Amount
in Rs.
in Rs
462.00
21945.00
635.00
11344.28
1145.00
2272.83
1210.00
29629.88
875.00
7142.19
Rs:
72334.16
Rate
in Rs.
0.00
0.00
Unit
work inspector
mazdoor
Quantity
Day
Day
0.00
0.00
Rs:
Amount
in Rs
0.00
0.00
0.00
370.00
295.00
Rs:
Amount
in Rs
370.00
11210.00
11580.00
Rate
in Rs.
1.00
38.00
115.80
0.14 16.20
132.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Rs:
72334.16
Rs:
0.00
Rs:
11580.00
Rs:
83914.16
Rs. 11747.98
Rs: 95662.14
Rs: 956.60
Total
14%
IRR-DAW-6-3
Rs:
38376.72
Rs. 5372.74
61.52454
107.96
IRR-DAW-6-2
Total
14%
Providing and constructing 1.40 m thick vertical or inclined graded filter media consisting of
20 cm thick sand layers, 25 cm thick 20 mm down coarse aggregate layers and 50 cm thick
80-20 mm coarse aggregate layer using approved materials satisfying specified filter creteria as
per specifications including cost of all materials, machinery, labour, laying to required slope,
compaction etc., complete with initial lead upto 50 m and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No Particulars
1
2
3
4
5
UNIT :
Unit
B. MACHINERY:
Sl No Description
Quantity
cum
cum
cum
cum
cum
Total cost of Materials
Unit
1 NIL
28.60
32.13
3.57
28.13
8.93
Quantity
Rate
in Rs.
0.00
0.00
100 cum
Rate
Amount
in Rs.
in Rs
462.00
13213.20
635.00
20402.55
1145.00
4087.65
1210.00
34031.25
875.00
7809.38
Rs:
79544.03
0.00
0.00
Rs:
Amount
in Rs
0.00
0.00
0.00
97
C. LABOUR:
Sl No Description
1
2
Unit
work inspector
mazdoor
Quantity
Day
Day
Rate
in Rs.
1.00
38.00
370.00
295.00
Rs:
115.80
0.14 16.20
132.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Rs:
79544.03
Rs:
0.00
Rs:
11580.00
Rs:
91124.03
Rs. 12757.36
Rs: 103881.39
Rs: 1038.80
Total
14%
IRR-DAW-6-4
Providing and constructing graded filter media below and behind rock-toe consisting of
20 cm thick sand, 25 cm thick 20 - 4.75 mm and 40 cm thick 80 - 20 mm size graded coarse
aggregates satisfying filter creteria as per specifications including cost of all materials, labour,
machinery, laying to required slope, compaction etc., complete with initial lead upto 50 m and
all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No Particulars
1
2
3
4
5
UNIT
Unit
Quantity
cum
cum
cum
cum
cum
B. MACHINERY:
Sl No Description
23.55
42.39
4.71
22.05
7.35
Unit
Quantity
NIL
100 cum
Rate
Amount
in Rs.
in Rs
462.00
10880.10
635.00
26917.65
1145.00
5392.95
1210.00
26680.50
875.00
6431.25
Rs:
76302.45
Rate
in Rs.
0.00
0.00
Unit
work inspector
mazdoor
Quantity
Day
Day
1.00
34.00
370.00
295.00
Rs:
Amount
in Rs
370.00
10030.00
10400.00
104.00
0.14 14.60
118.60
Total
14%
0.00
0.00
Rs:
Amount
in Rs
0.00
0.00
0.00
Rate
in Rs.
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
IRR-DAW-6-4-A
Amount
in Rs
370.00
11210.00
11580.00
Rs:
76302.45
Rs:
0.00
Rs:
10400.00
Rs:
86702.45
Rs. 12138.34
Rs: 98840.79
Rs: 988.40
Providing and constructing graded filter media below and behind rock-toe consisting of
30 cm thick 80 - 20 mm size graded coarse
aggregates satisfying filter creteria as per specifications including cost of all materials, labour,
machinery, laying to required slope, compaction etc., complete with initial lead upto 50 m and
all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No Particulars
1
2
3
4
UNIT
Unit
cum
cum
cum
cum
Quantity
35.00
55.00
5.00
5.00
100 cum
Rate
Amount
in Rs.
in Rs
635.00
22225.00
1145.00
62975.00
1210.00
6050.00
875.00
4375.00
98
Unit
Quantity
NIL
Total hire charges of Machinery
1
2
Unit
work inspector
mazdoor
Quantity
Day
Day
0.00
0.00
Rs:
Amount
in Rs
0.00
0.00
0.00
370.00
295.00
Rs:
Amount
in Rs
370.00
3540.00
3910.00
Rate
in Rs.
1.00
12.00
39.10
0.14 5.50
44.60
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Rs:
95625.00
Rs:
0.00
Rs:
3910.00
Rs:
99535.00
Rs. 13934.9
Rs: 113469.90
Rs: 1134.70
Total
14%
IRR-DAW-6-5
95625.00
Rate
in Rs.
0.00
0.00
C. LABOUR:
Sl No Description
Rs:
Providing and laying filter media consisting of 2 layers of 250 gsm poly-propeline non-woven
filter fabric and 400 mm thick 20 mm down graded coarse aggregate for vertical / inclined
and horizontal filter blanket for embankment including cost of all materials, machinery, labour
etc., complete with lead upto 50 m for aggregate and all leads for fabric and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No Particulars
1
2
UNIT :
Unit
sqm
cum
cum
B. MACHINERY:
Sl No Description
1
Quantity
220.00
30.00
10.00
Unit
Quantity
NIL
100 sqm
Rate
Amount
in Rs.
in Rs
154.00
33880.00
1210.00
36300.00
875.00
8750.00
Rs:
78930.00
Rate
in Rs.
0.00
0.00
work inspector
mazdoor
Unit
Day
Day
Quantity
370.00
295.00
Rs:
Amount
in Rs
370.00
4130.00
4500.00
Rate
in Rs.
1.00
14.00
45.00
0.14 6.30
51.30
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D.Add for contractor's profit and overheads on (A+B+C)
0.00
0.00
Rs:
Amount
in Rs
0.00
0.00
0.00
Total
14%
Rs:
78930.00
Rs:
0.00
Rs:
4500.00
Rs:
83430.00
Rs. 11680.2
99
IRR-DAW-6-6
100.00 sqm
(A+B+C+D)/100
sqm
Rs: 95110.20
Rs: 951.10
Providing and constructing 45 cm thick chimney filter using clean approved sand satisfying
filter creteria including cost of all materials, machinery, labour, compacting etc., complete with
initial lead upto 50 m and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No Particulars
1
UNIT :
Unit
Sand (Un-Screened)
Quantity
cum
105.00
0.00
Unit
Quantity
NIL
100 cum
Rate
Amount
in Rs.
in Rs
462.00
48510.00
0.00
Rs:
48510.00
Rate
in Rs.
0.00
0.00
Unit
work inspector
mazdoor
Quantity
Day
Day
370.00
295.00
Rs:
Amount
in Rs
370.00
8850.00
9220.00
Rate
in Rs.
1.00
30.00
92.20
0.14 12.90
105.10
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Rs:
48510.00
Rs:
0.00
Rs:
9220.00
Rs:
57730.00
Rs. 8082.2
Rs: 65812.20
Rs: 658.10
Total
14%
IRR-DAW-6-7
0.00
0.00
Rs:
Amount
in Rs
0.00
0.00
0.00
Providing and constructing 90 cm thick transition cum filter media behind rockfill using
approved sand and 80-20 mm and 20 mm down graded aggregates satisfying the filter creteria
in layers of 30 cm thickness each as per specifications including cost of all materials,
machinery, labour, laying each layer to required slope, compaction etc., complete with initial
lead upto 50 m and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No Particulars
1
2
3
4
5
UNIT :
Unit
Sand (Un-Screened )
Coarse aggregate 80-40 mm
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm down
Total cost of Materials
cum
cum
cum
cum
cum
B. MACHINERY:
Sl No Description
1
Quantity
34.00
30.60
3.40
25.50
8.50
Unit
Quantity
NIL
100 cum.
Rate
Amount
in Rs.
in Rs
462.00
15708.00
635.00
19431.00
1145.00
3893.00
1210.00
30855.00
875.00
7437.50
Rs:
77324.50
Rate
in Rs.
0.00
0.00
work inspector
mazdoor
Unit
Day
Day
Quantity
0.00
0.00
Rs:
Amount
in Rs
0.00
0.00
0.00
370.00
295.00
Rs:
Amount
in Rs
370.00
11800.00
12170.00
Rate
in Rs.
1.00
40.00
121.70
0.14 17.00
138.70
ABSTRACT:
100
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
14%
IRR-DAW-6-8
Rs:
77324.50
Rs:
0.00
Rs:
12170.00
Rs:
89494.50
Rs. 12529.23
Rs: 102023.73
Rs: 1020.20
Providing and constructing 60 cm thick hand packed rough stone revetment with 65 to
75 cm long through stones at 1.50 m c / c over a backing of 45 cm thick graded filter media
consisting of sand, 10 mm and 40 mm size approved graded aggregates laid in layers of 15 cm
thick each including cost of all materials, machinery, labour, laying to required slopes, wedging
with chips, finishing etc. complete with initial lead upto 50 m and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No Particulars
1
2
3
4
5
6
UNIT :
Unit
Sand (Un-Screened )
Coarse aggregate 10 mm down
Coarse aggregate 40-20 mm
Stone chips
Rough stones ( rubble ) 30 to 45 cm long
Through stones 65 to 75 cm long
Total cost of Materials
cum
cum
cum
cum
cum
Nos
B. MACHINERY:
Sl No Description
1
Quantity
15.30
15.30
15.30
9.00
57.60
44.00
Unit
Quantity
NIL
100 sqm
Rate
Amount
in Rs.
in Rs
462.00
7068.60
875.00
13387.50
1145.00
17518.50
340.00
3060.00
318.00
18316.80
59.00
2596.00
Rs:
61947.40
Rate
in Rs.
0.00
0.00
Unit
work inspector
Mason Class-II
mazdoor
Quantity
Day
Day
Day
370.00
345.00
295.00
Rs:
Amount
in Rs
370.00
3450.00
9735.00
13555.00
Rate
in Rs.
1.00
10.00
33.00
135.60
0.14 19.00
154.60
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Rs:
61947.40
Rs:
0.00
Rs:
13555.00
Rs:
75502.40
Rs. 10570.34
Rs: 86072.74
Rs: 860.70
Total
14%
IRR-DAW-6-9
0.00
0.00
Rs:
Amount
in Rs
0.00
0.00
0.00
Providing and constructing 60 cm thick hand packed rough stone revetment with 65 to 75
cm long through stones at 1.50 m c / c over a backing of 60 cm thick graded filter media
consisting of sand, 10 mm and 40 mm size approved graded aggregates laid in layers of 20 cm
thick each including cost of all materials, machinery, labour, laying to required slopes, wedging
with chips, finishing etc. complete with initial lead upto 50 m and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No Particulars
1
2
3
4
5
6
Sand (Un-Screened )
Coarse aggregate 10 mm down
Coarse aggregate 40-20 mm
Stone chips
Rough stones ( rubble ) 30 to 45 cm long
Through stones 65 to 75 cm long
Total cost of Materials
B. MACHINERY:
Sl No Description
1
NIL
UNIT :
Unit
Quantity
cum
cum
cum
cum
cum
Nos
Unit
20.40
20.40
20.40
9.00
57.60
44.00
Quantity
100 sqm
Rate
Amount
in Rs.
in Rs
462.00
9424.80
875.00
17850.00
1145.00
23358.00
340.00
3060.00
318.00
18316.80
59.00
2596.00
Rs:
74605.60
Rate
in Rs.
0.00
0.00
Amount
in Rs
0.00
101
0.00
Total hire charges of Machinery
C. LABOUR:
Sl No Description
1
2
3
Unit
work inspector
Mason Class-II
mazdoor
Quantity
Day
Day
Day
1.00
10.00
39.00
370.00
345.00
295.00
Rs:
Amount
in Rs
370.00
3450.00
11505.00
15325.00
153.30
0.14 21.50
174.80
Rs:
74605.60
Rs:
0.00
Rs:
15325.00
Rs:
89930.60
Rs. 12590.28
Rs: 102520.88
Rs: 1025.20
Total
14%
Providing and constructing 60 cm thick hand packed rough stone riprap over a backing of
45 cm thick graded filter media consisting of sand, 10 mm and 40 mm size graded approved
aggregates laid in layers of 15 cm thick each including cost of all materials, machinery,
labour, laying to required slopes, wedging with stone chips etc., complete with initial lead upto
50 m and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No Particulars
1
2
3
4
5
UNIT :
Unit
Sand (Un-Screened )
Coarse aggregate 10 mm down
Coarse aggregate 40-20 mm
Stone chips
Rough stones ( rubble )
Total cost of Materials
Quantity
cum
cum
cum
cum
cum
B. MACHINERY:
Sl No Description
15.30
15.30
15.30
9.00
60.00
Unit
Quantity
NIL
100 sqm.
Rate
Amount
in Rs.
in Rs
462.00
7068.60
875.00
13387.50
1145.00
17518.50
340.00
3060.00
318.00
19080.00
Rs:
60114.60
Rate
in Rs.
0.00
0.00
Unit
work inspector
Mason Class-II
mazdoor
Quantity
Day
Day
Day
0.00
0.00
Rs:
Amount
in Rs
0.00
0.00
0.00
370.00
345.00
295.00
Rs:
Amount
in Rs
370.00
1725.00
8260.00
10355.00
Rate
in Rs.
1.00
5.00
28.00
103.60
0.14 14.50
118.10
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Rs:
60114.60
Rs:
0.00
Rs:
10355.00
Rs:
70469.60
Rs. 9865.74
Rs: 80335.34
Rs: 803.40
Total
14%
IRR-DAW-6-11
0.00
0.00
Rate
in Rs.
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
IRR-DAW-6-10
0.00
Rs:
Providing and constructing 75 cm thick hand packed rough stone riprap over a backing of
45 cm thick graded filter media consisting of sand, 10 mm and 40 mm size graded approved
aggregates laid in layers of 15 cm thick each including cost of all materials, machinery, labour,
laying to required slopes, wedging with stone chips, etc., complete with initial lead upto 50 m
and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No Particulars
UNIT :
Unit
Quantity
Rate
100 sqm
Amount
102
in Rs.
1
2
3
4
5
Sand (Un-Screened )
Coarse aggregate 10 mm down
Coarse aggregate 40-20 mm
Stone chips
Rough stones ( rubble )
cum
cum
cum
cum
cum
Total cost of Materials
B. MACHINERY:
Sl No Description
1
Unit
15.30
15.30
15.30
11.00
75.00
Quantity
NIL
462.00
875.00
1145.00
340.00
318.00
Rs:
Rate
in Rs.
0.00
0.00
Unit
work inspector
Mason Class-II
mazdoor
Quantity
Day
Day
Day
370.00
345.00
295.00
Rs:
Amount
in Rs
370.00
2070.00
8850.00
11290.00
112.90
0.14 15.80
128.70
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Rs:
65564.60
Rs:
0.00
Rs:
11290.00
Rs:
76854.60
Rs. 10759.64
Rs: 87614.24
Rs: 876.10
Total
14%
IRR-DAW-6-12
0.00
0.00
Rs:
Amount
in Rs
0.00
0.00
0.00
Rate
in Rs.
1.00
6.00
30.00
in Rs
7068.60
13387.50
17518.50
3740.00
23850.00
65564.60
Providing and constructing 90 cm thick hand packed rough stone riprap over a backing of
45 cm thick graded filter media consisting of sand, 10 mm and 40 mm size graded approved
aggregates laid in layers of 15 cm thick each including cost of all materials, machinery,
labour, laying to required slopes, wedging with stone chips etc., complete with initial lead upto
50 m and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No Particulars
1
2
3
4
5
UNIT :
Unit
Sand (Un-Screened )
Coarse aggregate 10 mm down
Coarse aggregate 40-20 mm
Stone chips
Rough stones ( rubble )
cum
cum
cum
cum
cum
Total cost of Materials
B. MACHINERY:
Sl No Description
1
Quantity
Unit
15.30
15.30
15.30
13.50
90.00
Quantity
NIL
100 sqm
Rate
Amount
in Rs.
in Rs
462.00
7068.60
875.00
13387.50
1145.00
17518.50
340.00
4590.00
318.00
28620.00
Rs:
71184.60
Rate
in Rs.
0.00
0.00
work inspector
Mason Class-II
mazdoor
Unit
Day
Day
Day
Quantity
0.00
0.00
Rs:
Amount
in Rs
0.00
0.00
0.00
370.00
345.00
295.00
Rs:
Amount
in Rs
370.00
2760.00
10030.00
13160.00
Rate
in Rs.
1.00
8.00
34.00
131.60
0.14 18.40
150.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D.Add for contractor's profit and overheads on (A+B+C)
Total cost for
100.00 sqm
Rate per
sqm
(A+B+C+D)/100
Total
14%
Rs:
71184.60
Rs:
0.00
Rs:
13160.00
Rs:
84344.60
Rs. 11808.24
Rs: 96152.84
Rs: 961.50
103
IRR-DAW-6-13
Providing and laying Hariyala or other approved quality turfing sods for the slopes of earthen
embankments over 20 mm thick sand backing including cost of all materials, machinery,
labour including preparing surface, spreading sand, watering for 15 days etc., complete with
initial lead upto 1 km and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No Particulars
1
2
UNIT :
Unit
B. MACHINERY:
Sl No Description
1
Quantity
cum
sqm
Unit
2.00
100.00
Quantity
NIL
100 sqm.
Rate
Amount
in Rs.
in Rs
342.00
684.00
28.00
2800.00
Rs:
3484.00
Rate
in Rs.
0.00
0.00
Unit
1
2
Quantity
395.00
295.00
Rs:
Amount
in Rs
790.00
4425.00
5215.00
Rate
in Rs.
2.00
15.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D.Add for contractor's profit and overheads on (A+B+C)
Lead Charges for 1 Km for FA
2.00
cum @
Total cost for
100.00 sqm.
Rate per
sqm.
(A+B+C+D)/100
0.00
0.00
Rs:
Amount
in Rs
0.00
0.00
0.00
Total
14%
31.5 Rs./Cum
Rs:
3484.00
Rs:
0.00
Rs:
5215.00
Rs:
8699.00
Rs. 1217.86
63
Rs: 9979.86
Rs: 99.80
104
Chapter - II
TUNNEL AND ALLIED WORKS - Standard Data
3. The Leads for Steel and Cement shall be from the nearest market place to the Project area
4. For earth/rockfill embankments wherever initial lead of 1km is considered in the basic rate, the additional lead charges are to be added
as follows:
Additional lead charges for Earth, Murrum etc., shall be worked out for total lead involved and 1 km lead charges included in basic
rate shall be deducted from total lead charges. No loading and unloading charges shall be allowed for any item. (same as above)
Example:
Total lead for earth from approved borrow area :
15 Km
Initial lead included in the basic rate in the SR :
1 Km
Additional lead charges : Lead charges for 5 km
Rs.
84.10
Lead charges for next 10 km
Rs.
126
Total lead charges for 15 km /cum
Rs.
210.10
Less 1 km initial lead charges /cum
Rs.
31.50 (-)
Net additional lead charges / cum
Rs.
178.60
5. The initial lead up to 50 m as mentioned in some standard data items is meant for manual lead within the working area. For
conveyance of materials, the lead required from quarry/Borrow area/ Dump Area to worksite shall be added to the data without
deducting the 50 m initial lead charges
TAW -Work Items
IRR-TAW-1
EXCAVATION :
IRR-TAW-1-1 Excavation for adit by tunnelling methods in all types of rock including cost of all materials,
machinery, labour, scaling excavated surface, ventilation, lighting, drainage, removing and
hauling the excavated muck outside adit upto specified dump area and all other ancillary
operations etc., complete with initial lead upto 1km and all lifts.
105
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
7
8
Particulars
Unit
kg
Nos
Nos
Rm
Rm
10%
Hour
Hour
LS
B. MACHINERY:
Sl No
1
2
3
4
5
6
7
8
9
Description
Unit
Drilling jumbo
Fuel / Energy charges
Air compressor 15 cmm ( ele )
Fuel / Energy charges
Jack hammer ( 4 x 5 hrs )
Fuel / Energy charges
Pusher leg
Fuel / Energy charges
Convey mucker
Fuel / Energy charges
Dumper ( 1 x 6.5 hrs )
Fuel / Energy charges
Pump 10 hp ( ele )
Fuel / Energy charges
Ventilation fans 20 hp
Fuel / Energy charges
Sundries(explosive van / magazine )
Total hire charges of Machinery
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS
C. LABOUR:
Sl No
1
2
3
4
5
6
7
8
9
10
11
UNIT :
Description
Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Day
Day
Day
Day
Quantity
38.50 cum
40.00
54.00
5.00
50.00
119.00
70.00
23.00
13.00
11.00
41.69
20.00
20.00
2.00
5.47
6.84
41.00
Rs:
Amount
in Rs.
2800.00
1242.00
65.00
550.00
4961.51
496.15
109.38
136.88
82.00
10442.91
Rate
in Rs.
368.40
46.00
138.80
951.20
19.80
0.00
12.70
0.00
822.80
264.80
580.70
429.70
6.70
76.10
11.50
152.20
41.00
Rs:
Amount
in Rs.
2947.20
368.00
694.00
4756.00
396.00
0.00
254.00
0.00
5348.20
1721.20
3774.55
2793.05
33.50
380.50
11.50
152.20
82.00
23711.90
Rate
in Rs.
151.80
151.80
284.70
151.80
195.90
72.10
24.90
550.00
440.00
385.00
440.00
Amount
in Rs.
1214.40
759.00
5694.00
986.70
1273.35
360.50
24.90
275.00
440.00
770.00
440.00
Quantity
8.00
8.00
5.00
5.00
20.00
20.00
20.00
20.00
6.50
6.50
6.50
6.50
5.00
5.00
1.00
1.00
2.00
Quantity
8.00
5.00
20.00
6.50
6.50
5.00
1.00
0.50
1.00
2.00
1.00
Rate
in Rs.
106
12
13
14
15
16
Helper blasting
Hammerman
work inspector 1 in each shift
Khalasi for mucking shift 4 Nos
mazdoor
for mucking shift 4 Nos
for other 2 shifts 1 No each shift
for cleaning & miscellaneous
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
Day
Day
Day
Day
2.00
2.00
3.00
4.00
345.00
345.00
370.00
385.00
690.00
690.00
1110.00
1540.00
Day
Day
Day
4.00
2.00
2.00
295.00
295.00
295.00
Rs:
1180.00
590.00
590.00
18627.85
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
10442.91
23711.90
18627.85
52782.66
527.83
2375.22
844.52
1319.57
57849.79
Rs:
Rs:
Rs:
8098.97
65948.76
1713.00
483.80
0.14 67.70
551.50
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Add for Air and Water line @
Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @
1.00%
4.50%
1.60%
2.50%
Total
14%
IRR-TAW-1-2 Excavation for vertical / inclined shaft in all types of soft / hard rock including cost of all
materials, machinery, labour, shoring, strutting, scaling excavated surface, ventilation, lighting,
drainage, removing and hauling excavated muck outside shaft upto specified dump area and
all other ancillary operations etc., complete with initial lead upto 1 km and all lifts.
DATA
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
7
8
9
10
Particulars
Unit
kg
Nos
Rm
Rm
10%
Hour
Hour
Shift
Hour
LS
B. MACHINERY:
Sl No
1
2
3
4
5
6
7
UNIT :
Description
Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS
Quantity
30.00 cum
32.00
65.00
50.00
95.00
70.00
13.00
11.00
26.85
18.00
16.00
3.00
24.00
2.00
21.88
27.38
127.46
24.19
41.00
Rs:
Amount
in Rs.
2240.00
845.00
550.00
2551.07
255.11
393.75
438.00
382.39
580.54
82.00
8317.85
Rate
in Rs.
138.80
951.20
19.80
0.00
6.70
76.10
12.30
152.20
129.40
186.40
64.20
0.00
41.00
Rs:
Amount
in Rs.
624.60
4280.40
316.80
0.00
26.80
304.40
24.60
304.40
3623.20
5219.20
1540.80
0.00
82.00
16347.20
Quantity
4.50
4.50
16.00
16.00
4.00
4.00
2.00
2.00
28.00
28.00
24.00
24.00
2.00
Rate
in Rs.
107
C. LABOUR:
Sl No
Description
1
2
3
4
5
6
7
8
9
10
11
12
13
14
Unit
Quantity
Hour
Hour
Hour
Hour
Hour
Day
Day
Day
Day
Day
Day
Day
Day
4.50
16.00
4.00
2.00
28.00
0.50
4.00
2.00
1.00
2.00
3.00
4.00
6.00
Day
Day
Day
24.00
2.00
2.00
Rate
in Rs.
151.80
284.70
72.10
72.10
227.80
550.00
440.00
385.00
440.00
345.00
345.00
370.00
385.00
Amount
in Rs.
683.10
4555.20
288.40
144.20
6378.40
275.00
1760.00
770.00
440.00
690.00
1035.00
1480.00
2310.00
295.00
295.00
295.00
Rs:
7080.00
590.00
590.00
29069.30
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
8317.85
16347.20
29069.30
53734.35
537.34
2418.05
859.75
1343.36
58892.85
Rs:
Rs:
Rs:
8245.00
67137.85
2237.90
969.00
0.14 135.70
1104.70
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Add for Air and Water line @
Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @
1.00%
4.50%
1.60%
2.50%
Total
14%
IRR-TAW-1-3 Excavation for tunnel by tunnelling methods in rock not requiring supports including cost
of all materials,machinery, labour, scaling excavated surface, removing under-cuts, ventilation,
lighting, drainage, removing and hauling the excavated muck outside tunnel upto specified
dump area and all other ancillary operations etc., complete with initial lead upto 1 km and
all lifts.
DATA:
DATA:
RATE ANALYSIS
:
:
:
:
:
:
:
:within
:
UNIT :
4.50 m dia
D - shape
4.50
1000
0.30
0.20
5.50
500
m
m
m
m
m
m
By dumpers
48.60 cum
108
A. MATERIALS:
Sl No
1
2
3
4
5
6
7
8
Particulars
Unit
kg
Nos
Nos
Rm
Rm
10%
Hour
Hour
LS
B. MACHINERY:
Sl No
1
2
3
4
5
6
7
8
9
Description
Unit
Drilling jumbo
Fuel / Energy charges
Air compressor 15 cmm ( ele )
Fuel / Energy charges
Jack hammer ( 4 x 6.5 hrs )
Fuel / Energy charges
Pusher leg
Fuel / Energy charges
Convey mucker
Fuel / Energy charges
Dumper ( 2 x 6 hrs )
Fuel / Energy charges
Pump 10 hp ( ele )
Fuel / Energy charges
Ventilation fans 20 hp
Fuel / Energy charges
Sundries(explosive van / magazine )
Total hire charges of Machinery
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS
C. LABOUR:
Sl No
Description
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
Unit
Quantity
54.00
68.00
10.00
50.00
150.00
70.00
23.00
13.00
11.00
41.69
24.00
24.00
2.00
5.47
6.84
41.00
Rs:
Amount
in Rs.
3780.00
1564.00
130.00
550.00
6254.00
625.40
131.25
164.25
82.00
13280.90
Rate
in Rs.
368.40
46.00
138.80
951.20
19.80
0.00
12.70
0.00
822.80
264.80
580.70
429.70
6.70
76.10
11.50
152.20
41.00
Rs:
Amount
in Rs.
3684.00
460.00
902.20
6182.80
514.80
0.00
330.20
0.00
4936.80
1588.80
6968.40
5156.40
43.55
494.65
23.00
304.40
82.00
31672.00
Rate
in Rs.
151.80
151.80
284.70
151.80
195.90
72.10
24.90
550.00
440.00
385.00
440.00
345.00
345.00
370.00
385.00
Amount
in Rs.
1518.00
986.70
7402.20
910.80
2350.80
468.65
49.80
275.00
440.00
770.00
440.00
690.00
690.00
1110.00
1540.00
295.00
295.00
295.00
Rs:
2360.00
590.00
590.00
23181.95
Rs:
Rs:
Rs:
Rs:
Rs:
13280.90
31672.00
23181.95
68134.85
681.35
Quantity
10.00
10.00
6.50
6.50
26.00
26.00
26.00
26.00
6.00
6.00
12.00
12.00
6.50
6.50
2.00
2.00
2.00
Quantity
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Day
Day
Day
Day
Day
Day
Day
Day
10.00
6.50
26.00
6.00
12.00
6.50
2.00
0.50
1.00
2.00
1.00
2.00
2.00
3.00
4.00
Day
Day
Day
8.00
2.00
2.00
Rate
in Rs.
477.00
0.14 66.80
543.80
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Add for Air and Water line @
1.00%
109
4.50%
1.60%
2.50%
Total
14%
Rs:
Rs:
Rs:
Rs:
3066.07
1090.16
1703.37
74675.80
Rs:
Rs:
Rs:
10454.61
85130.41
1751.70
IRR-TAW-1-4 Excavation for tunnel by tunnelling methods including excavation for supports in all types of
soil / rock strata requiring supports ( excluding cost of providing supports ) including cost of
all other materials, machinery, labour, scaling excavated surface, ventilation, lighting, drainage,
removing and hauling the excavated muck outside tunnel upto specified dump area and all
other ancillary operations etc., complete with initial lead upto 1 km and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
7
8
Particulars
Unit
kg
Nos
Nos
Rm
Rm
10%
Hour
Hour
LS
B. MACHINERY:
Sl No
1
2
3
4
5
6
7
8
9
Description
Unit
Drilling jumbo
Fuel / Energy charges
Air compressor 15 cmm ( ele )
Fuel / Energy charges
Jack hammer ( 4 x 6 hrs )
Fuel / Energy charges
Pusher leg
Fuel / Energy charges
Convey mucker
Fuel / Energy charges
Dumper ( 2 x 6 hrs )
Fuel / Energy charges
Pump 10 hp ( ele )
Fuel / Energy charges
Ventilation fans 20 hp
Fuel / Energy charges
Sundries(explosive van / magazine )
Total hire charges of Machinery
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS
C. LABOUR:
Sl No
1
2
3
4
5
6
7
8
9
10
11
12
UNIT :
Description
Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Day
Day
Day
Day
Day
Quantity
46.00 cum
41.00
77.00
10.00
50.00
144.00
70.00
23.00
13.00
11.00
41.69
24.00
24.00
2.00
5.47
6.84
41.00
Rs:
Amount
in Rs.
2870.00
1771.00
130.00
550.00
6003.84
600.38
131.25
164.25
82.00
12302.72
Rate
in Rs.
368.40
46.00
138.80
951.20
19.80
0.00
12.70
0.00
822.80
264.80
580.70
429.70
6.70
76.10
11.50
152.20
41.00
Rs:
Amount
in Rs.
4052.40
506.00
832.80
5707.20
475.20
0.00
304.80
0.00
4936.80
1588.80
6968.40
5156.40
40.20
456.60
23.00
304.40
82.00
31435.00
Rate
in Rs.
151.80
151.80
284.70
151.80
195.90
72.10
24.90
550.00
440.00
385.00
440.00
345.00
Amount
in Rs.
1669.80
910.80
6832.80
910.80
2350.80
432.60
49.80
275.00
440.00
770.00
440.00
690.00
Quantity
11.00
11.00
6.00
6.00
24.00
24.00
24.00
24.00
6.00
6.00
12.00
12.00
6.00
6.00
2.00
2.00
2.00
Quantity
11.00
6.00
24.00
6.00
12.00
6.00
2.00
0.50
1.00
2.00
1.00
2.00
Rate
in Rs.
110
13
14
15
16
Hammerman 2 Nos
work inspector 1 in each shift
Khalasi for mucking shift 4 Nos
mazdoor
for mucking shift 8 Nos
for other 2 shifts 1 No each shift
for cleaning & miscellaneous
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
Day
Day
Day
2.00
3.00
4.00
345.00
370.00
385.00
690.00
1110.00
1540.00
Day
Day
Day
8.00
2.00
2.00
295.00
295.00
295.00
Rs:
2360.00
590.00
590.00
22652.40
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
12302.72
31435.00
22652.40
66390.12
663.90
2987.56
1062.24
1659.75
72763.58
Rs:
Rs:
Rs:
10186.90
82950.48
1803.30
492.40
0.14 68.90
561.30
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Add for Air and Water line @
Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @
1.00%
4.50%
1.60%
2.50%
Total
14%
IRR-TAW-1-5 Excavation for tunnel by heading and benching tunnelling methods including excavation
for supports in all types of soil / rock strata requiring supports ( excluding cost of providing
supports ) for roof before benching including cost of all other materials, machinery, labour,
scaling excavated surface, ventilation, lighting, drainage removing and hauling excavated muck
outside tunnel upto specified dump area and all other ancillary operations etc., complete with
initial lead upto 1 km and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
7
8
Particulars
Unit
kg
Nos
Nos
Rm
Rm
10%
Hour
Hour
LS
B. MACHINERY:
Sl No
1
2
UNIT :
Description
Drilling jumbo
Fuel / Energy charges
Air compressor 15 cmm ( ele )
Unit
Hour
Hour
Hour
Quantity
50.00 cum
44.00
84.00
10.00
50.00
157.00
70.00
23.00
13.00
11.00
41.69
26.00
26.00
2.00
5.47
6.84
41.00
Rs:
Amount
in Rs.
3080.00
1932.00
130.00
550.00
6545.85
654.59
142.19
177.94
82.00
13294.56
Rate
in Rs.
368.40
46.00
138.80
Amount
in Rs.
4420.80
552.00
902.20
Quantity
12.00
12.00
6.50
Rate
in Rs.
111
3
4
5
6
7
8
9
C. LABOUR:
Sl No
Description
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS
Unit
6.50
26.00
26.00
26.00
26.00
6.50
6.50
13.00
13.00
6.50
6.50
3.00
3.00
2.00
Quantity
951.20
19.80
0.00
12.70
0.00
822.80
264.80
580.70
429.70
6.70
76.10
11.50
152.20
41.00
Rs:
6182.80
514.80
0.00
330.20
0.00
5348.20
1721.20
7549.10
5586.10
43.55
494.65
34.50
456.60
82.00
34218.70
Amount
in Rs.
1821.60
986.70
7402.20
986.70
2546.70
468.65
74.70
275.00
440.00
770.00
880.00
1380.00
690.00
1110.00
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Day
Day
Day
Day
Day
Day
Day
12.00
6.50
26.00
6.50
13.00
6.50
3.00
0.50
1.00
2.00
2.00
4.00
2.00
3.00
Rate
in Rs.
151.80
151.80
284.70
151.80
195.90
72.10
24.90
550.00
440.00
385.00
440.00
345.00
345.00
370.00
Day
Day
4.00
4.00
385.00
385.00
1540.00
1540.00
Day
Day
Day
8.00
2.00
2.00
295.00
295.00
295.00
Rs:
2360.00
590.00
590.00
26452.25
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
13294.56
34218.70
26452.25
73965.51
739.66
3328.45
1183.45
1849.14
81066.20
Rs:
Rs:
Rs:
11349.27
92415.47
1848.30
529.00
0.14 74.10
603.10
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Add for Air and Water line @
Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @
1.00%
4.50%
1.60%
2.50%
Total
14%
Where mucking is to be carried out through shaft using winch and mucking tub system
increase the basic rates for items IRR-TAW-1-3, IRR-TAW-1-4 & IRR-TAW-1-5 by 8 percent.
IRR-TAW-1-6 Removing and hauling muck overfallen due to natural causes such as geological faults
etc., out of tunnel including breaking large fragments by blasting if necessary and disposing off
the same in specified dump area or as directed including cost of all materials, machinery,
labour, ventilation, drainage, lighting and all other ancillary operations etc., complete with
initial lead upto 1 km and all lifts.
112
DATA
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
7
Particulars
Unit
Rm
10%
kg
Nos.
Rm
Hour
Hour
LS
B. MACHINERY:
Sl No
1
2
3
4
5
6
UNIT :
Description
Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS
C. LABOUR:
Sl No
Description
1
2
3
4
5
6
7
8
Unit
Quantity
15.00
26.85
8.00
30.00
20.00
4.00
4.00
1.00
70.00
13.00
11.00
5.47
6.84
41.00
Rs:
Amount
in Rs.
402.80
40.28
560.00
390.00
220.00
21.88
27.38
41.00
1703.33
Rate
in Rs.
138.80
951.20
19.80
0.00
6.70
76.10
822.80
264.80
580.70
429.70
41.00
Rs:
Amount
in Rs.
138.80
951.20
79.20
0.00
6.70
76.10
4936.80
1588.80
6968.40
5156.40
41.00
19943.40
Rate
in Rs.
151.80
284.70
72.10
151.80
195.90
440.00
345.00
295.00
Rs:
Amount
in Rs.
151.80
1138.80
72.10
910.80
2350.80
220.00
172.50
2360.00
7376.80
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
1703.33
19943.40
7376.80
29023.53
290.24
1306.06
464.38
725.59
31809.79
Rs:
Rs:
Rs:
4453.37
36263.16
362.60
Quantity
1.00
1.00
4.00
4.00
1.00
1.00
6.00
6.00
12.00
12.00
1.00
Quantity
Hour
Hour
Hour
Hour
Hour
Day
Day
Day
100.00 cum
1.00
4.00
1.00
6.00
12.00
0.50
0.50
8.00
Rate
in Rs.
73.80
0.14 10.30
84.10
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Add for Air and Water line @
Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @
1.00%
4.50%
1.60%
2.50%
Total
14%
113
DATA
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
Particulars
Unit
Hour
LS
B. MACHINERY:
Sl No
1
2
3
UNIT :
Description
Unit
Electric pump 20 hp
Fuel / Energy charges
Sundries(Starter/Switches ete)
Total hire charges of Machinery
Hour
Hour
LS
C. LABOUR:
Sl No
Description
1
2
3
Unit
Quantity
15.00 Kwhr
Rate
in Rs.
4.67
41.00
Rs:
Amount
in Rs.
4.67
4.10
8.77
12.30
152.20
41.00
Rs:
Amount
in Rs.
12.30
152.20
4.10
168.60
1.00
0.10
Quantity
Rate
in Rs.
1.00
1.00
0.10
Quantity
Hour
LS
Day
Rate
in Rs.
1.00
0.05
0.10
72.10
41.00
295.00
Rs:
Amount
in Rs.
72.10
2.05
29.50
103.65
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
8.77
168.60
103.65
281.02
2.81
12.65
4.50
7.03
307.99
Rs:
Rs:
Rs:
43.12
351.11
23.40
6.90
0.14 1.00
7.90
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Add for Air and Water line @
Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @
1.00%
4.50%
1.60%
2.50%
Total
IRR-TAW-2-2 Providing 25 mm thick guniting to sides and arch of tunnel in cement mortar 1 : 3 proportion
by weight including cost of all materials, machinery, labour, ventilation, lighting, drainage
and all other ancillary operations etc., complete with lead upto 1 km and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
Particulars
Unit
Cement
Sand (Screened)
Use rate of grout hose 20 m
Use rate of water hose 20 m
Use rate of guniting nozzle
Sundries
Total cost of Materials
kg
cum
Hour
Hour
Hour
LS
B. MACHINERY:
Sl No
1
2
3
UNIT :
Description
Guniting equipment
Fuel / Energy charges
Air compressor 8.5 cmm ( ele )
Fuel / Energy charges
Pump 10 hp ( ele )
Unit
Hour
Hour
Hour
Hour
Hour
Quantity
600.00
1.10
8.00
8.00
8.00
2.00
Quantity
8.00
8.00
8.00
8.00
1.00
36.00 sqm
Rate
in Rs.
4.00
606.00
5.47
6.84
3.50
41.00
Rs:
Amount
in Rs.
2400.00
666.60
43.75
54.75
28.00
82.00
3275.10
Rate
in Rs.
110.10
0.00
170.80
428.00
6.70
Amount
in Rs.
880.80
0.00
1366.40
3424.00
6.70
114
4
5
C. LABOUR:
Sl No
Hour
Hour
Hour
LS
Description
Unit
1
2
3
4
5
6
Hour
Hour
Hour
Hour
Day
Day
1.00
4.00
4.00
2.00
76.10
368.40
46.00
41.00
Rs:
76.10
1473.60
184.00
82.00
7493.60
Rate
in Rs.
189.80
142.40
72.10
151.80
385.00
295.00
Rs:
Amount
in Rs.
1518.40
1139.20
72.10
607.20
385.00
1770.00
5491.90
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
3275.10
7493.60
5491.90
16260.60
162.61
731.73
260.17
406.52
17821.62
14%
Rs:
cum @
31.5 Rs./Cum
2495.03
34.65
Quantity
8.00
8.00
1.00
4.00
1.00
6.00
152.60
0.14 21.40
174.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Add for Air and Water line @
Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @
1.00%
4.50%
1.60%
2.50%
Total
0.60
tonne @
36.00 sqm
(A+B+C+D)/36.0
124.6 Rs./Tonne
Rs:
Rs:
74.76
20426.05
567.40
IRR-TAW-2-3 Shortcreting in two layers (each layer+38 mm thickness) for slabs duly fixing chain weld wire mesh
(new4 - 201112)
100 x 100x5 mm in between the two layers including cost and conveyance of all materials,
labour charges, all heads, lifts, centering, scaffolding, machine mixing,
laying concrete with shortcrete machine etc. complete as per specification and as
directed by Engineer-in-Charge
Data
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
7
8
Cement
Sand (Screened)
Coarse aggregate 10-4.75 mm size
Use rate of grout hose 20 m
Use rate of water hose 20 m
Use rate of guniting nozzle
Welded steel wire fabric 100 x 100 x 5 mm
Sundries
Total cost of Materials
B. MACHINERY:
Sl No
1
2
3
Particulars
Description
Guniting equipment
Fuel / Energy charges
Air compressor 8.5 cmm ( ele )
Fuel / Energy charges
Pump 10 hp ( ele )
Fuel / Energy charges
UNIT :
Unit
kg
cum
cum
Hour
Hour
Hour
kg
LS
Unit
Hour
Hour
Hour
Hour
Hour
Hour
Quantity
1548.00
2.41
1.03
8.00
8.00
8.00
108.00
2.00
Quantity
8.00
8.00
8.00
8.00
1.00
1.00
36.00 sqm
Rate
in Rs.
4.00
606.00
875.00
5.47
6.84
3.50
155.00
41.00
Rs:
Amount
in Rs.
6192.00
1460.46
901.25
43.75
54.75
28.00
16740.00
82.00
25502.21
Rate
in Rs.
110.10
0.00
170.80
428.00
6.70
76.10
Amount
in Rs.
880.80
0.00
1366.40
3424.00
6.70
76.10
115
4
5
Drilling jumbo
Fuel / Energy charges
Sundries
Total hire charges of Machinery
C. LABOUR:
Sl No
Description
1
2
3
4
5
6
Hour
Hour
LS
Unit
Hour
Hour
Hour
Hour
Day
Day
4.00
4.00
2.00
Quantity
8.00
8.00
1.00
4.00
1.00
6.00
368.40
46.00
41.00
Rs:
1473.60
184.00
82.00
7493.60
Rate
in Rs.
189.80
142.40
72.10
151.80
385.00
295.00
Rs:
Amount
in Rs.
1518.40
1139.20
72.10
607.20
385.00
1770.00
5491.90
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
25502.21
7493.60
5491.90
38487.71
384.88
1731.95
615.80
962.19
42182.53
152.60
0.14 21.40
174.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Add for Air and Water line @
Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @
1.00%
4.50%
1.60%
2.50%
Total
5905.55
75.915
31.312
192.8808
48388.19
1344.10
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
7
Particulars
Unit
kg
kg
kg
kg
Rm
10%
Hour
Hour
LS
B. MACHINERY:
Sl No
1
2
UNIT :
Description
Unit
Hour
Hour
Hour
Quantity
20.00 Rm
86.91
65.94
6.18
4.00
20.00
46.50
46.00
46.00
90.00
41.69
6.00
6.00
5.00
5.47
6.84
41.00
Rs:
Amount
in Rs.
4041.49
3033.24
284.37
360.00
833.87
83.39
32.81
41.06
205.00
8915.22
Rate
in Rs.
138.80
951.20
6.70
Amount
in Rs.
208.20
1426.80
6.70
Quantity
1.50
1.50
1.00
Rate
in Rs.
116
3
4
5
6
C. LABOUR:
Sl No
Description
1
2
3
4
5
6
7
8
9
10
11
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS
Unit
Hour
Hour
Hour
Hour
Day
Day
Day
Day
Day
Day
Day
1.00
6.00
6.00
6.00
6.00
4.00
4.00
5.00
Quantity
1.50
1.00
6.00
4.00
0.50
1.00
1.00
1.00
1.00
0.50
2.00
76.10
19.80
0.00
12.70
0.00
368.40
46.00
41.00
Rs:
76.10
118.80
0.00
76.20
0.00
1473.60
184.00
205.00
3775.40
Rate
in Rs.
151.80
72.10
284.70
151.80
385.00
385.00
440.00
385.00
385.00
345.00
295.00
Rs:
Amount
in Rs.
227.70
72.10
1708.20
607.20
192.50
385.00
440.00
385.00
385.00
172.50
590.00
5165.20
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
8915.22
3775.40
5165.20
17855.82
178.56
803.51
285.69
446.40
19569.98
258.30
0.14 36.20
294.50
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Add for Air and Water line @
Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @
1.00%
4.50%
1.60%
2.50%
Total
2739.80
23.155587
22332.94
1116.60
IRR-TAW-3-2 Providing and fixing 25 mm diameter steel rock bolts with resin bond cement capsule
anchorage including drilling 35 mm dia holes, inserting grout capsule, driving bolt,fixing 10 mm
thick plate washers and nuts and tightening the same by torque wrench after hardening of
cement grout, cost of all materials, machinery, labour, ventilation, lighting, drainage and other
ancillary operations etc., complete with lead upto 1 km and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
7
8
UNIT :
Particulars
Unit
kg
kg
Nos.
kg
Rm
10%
Hour
Hour
LS
Quantity
20.00 Rm
Rate
in Rs.
86.91
65.94
2.00
4.00
20.00
46.50
46.00
46.00
90.00
41.69
6.00
6.00
3.00
5.47
6.84
41.00
Rs:
Amount
in Rs.
4041.49
3033.24
92.00
360.00
833.87
83.39
32.81
41.06
123.00
8640.86
117
B. MACHINERY:
Sl No
1
2
3
4
5
6
Description
Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS
C. LABOUR:
Sl No
Description
1
2
3
4
5
6
7
8
9
10
Unit
Hour
Hour
Hour
Hour
Day
Day
Day
Day
Day
Day
Quantity
1.50
1.50
1.00
1.00
6.00
6.00
6.00
6.00
4.00
4.00
3.00
Quantity
1.50
1.00
6.00
4.00
0.50
1.00
1.00
1.00
0.50
2.00
Rate
in Rs.
138.80
951.20
6.70
76.10
19.80
0.00
12.70
0.00
368.40
46.00
41.00
Rs:
Amount
in Rs.
208.20
1426.80
6.70
76.10
118.80
0.00
76.20
0.00
1473.60
184.00
123.00
3693.40
Rate
in Rs.
151.80
72.10
284.70
151.80
345.00
385.00
440.00
385.00
345.00
295.00
Rs:
Amount
in Rs.
227.70
72.10
1708.20
607.20
172.50
385.00
440.00
385.00
172.50
590.00
4760.20
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
8640.86
3693.40
4760.20
17094.46
170.94
769.25
273.51
427.36
18735.53
238.00
0.14 33.30
271.30
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Add for Air and Water line @
Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @
1.00%
4.50%
1.60%
2.50%
Total
2622.97
22.255506
21380.75
1069.00
IRR-TAW-3-3 Providing, fabricating and fixing in position permanent structural steel supports as per details
including cost of all materials, machinery, labour, cutting, bending, welding, grinding, lighting,
ventilation, drainage and all other ancillary operations etc., complete with initial lead upto
1 km and all lifts.
Data
RATE ANALYSIS
UNIT :
1.00 tonne
A. MATERIALS:
118
Sl No
Particulars
Unit
1
2
3
4
kg
kg
kg
5
6
7
B. MACHINERY:
Sl No
1
2
3
4
760.00
115.00
150.00
45.00
46.00
46.50
Amount
in Rs.
34200.00
5290.00
6975.00
cum
cum
2.40
0.80
52.00
320.00
124.80
256.00
Nos.
125.00
11.00
1375.00
kg
LS
50.00
5.00
90.00
41.00
Rs:
4500.00
205.00
52925.80
42.60
114.10
16.00
91.30
368.40
46.00
41.00
Rs:
Amount
in Rs.
340.80
912.80
256.00
1460.80
4420.80
552.00
1230.00
9173.20
Amount
in Rs.
1821.60
911.20
Description
Unit
Bending machine
Fuel / Energy charges
Welding set
Fuel / Energy charges
Drilling Jumbo
Fuel / Energy charges
Sundries ( lathe / drilling / grinder )
Total hire charges of Machinery
Hour
Hour
Hour
Hour
Hour
Hour
LS
C. LABOUR:
Sl No
Description
1
2
3
Unit
Quantity
Quantity
Rate
in Rs.
Rate
in Rs.
8.00
8.00
16.00
16.00
12.00
12.00
30.00
Quantity
Hour
Hour
12.00
8.00
Rate
in Rs.
151.80
113.90
Day
Day
Day
Day
Day
Day
1.00
2.00
2.00
3.00
2.00
4.00
440.00
385.00
385.00
440.00
385.00
345.00
440.00
770.00
770.00
1320.00
770.00
1380.00
Day
Day
Day
2.00
2.00
2.00
385.00
345.00
385.00
770.00
690.00
770.00
Day
Day
Day
Day
1.00
2.00
2.00
4.00
440.00
440.00
345.00
385.00
Rs:
440.00
880.00
690.00
1540.00
13962.80
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
52925.80
9173.20
13962.80
76061.80
760.62
3422.78
1216.99
1901.55
83363.73
Rs:
11670.92
13962.80
0.14 1954.80
15917.60
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Add for Air and Water line @
Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @
1.00%
4.50%
1.60%
2.50%
Total
14%
tonne @
1.00 tonne
145.6 Rs./Tonne
Rs:
149.24
95183.90
119
(A+B+C+D)/1.0
Rs:
95183.90
IRR-TAW-3-4 Providing, fabricating and fixing in position temperary structural steel supports as per details
and dismantling the same before concreting including cost of all materials, machinery, labour,
cutting, bending, welding, grinding, ventilation, lighting, drainage and all other ancillary
operations etc.,complete with initial lead upto 1 km and all lifts.
DATA
RATE ANALYSIS
A. MATERIALS (for 20 uses):
Sl No
Particulars
1
2
3
4
Bending machine
Fuel / Energy charges
Welding set
Fuel / Energy charges
Sundries
Total hire charges of Machinery
Cost per use considering
Drilling Jumbo
Fuel / Energy charges
Sundries
Total hire charges of Machinery
UNIT :
Unit
760.00
115.00
150.00
45.00
46.00
46.50
Amount
in Rs.
34200.00
5290.00
6975.00
cum
cum
2.40
0.80
52.00
320.00
124.80
256.00
Nos.
125.00
11.00
1375.00
kg
LS
50.00
20.00
90.00
41.00
Rs:
Rs:
4500.00
820.00
53540.80
2677.04
42.60
114.10
16.00
91.30
41.00
Rs:
Rs:
Amount
in Rs.
340.80
912.80
256.00
1460.80
1230.00
4200.40
210.02
Rate
in Rs.
368.40
46.00
41.00
Rs:
Amount
in Rs.
6631.20
828.00
410.00
7869.20
Amount
in Rs.
911.20
kg
kg
kg
Quantity
1.00 tonne
Rate
in Rs.
20 uses
Unit
Quantity
Hour
Hour
Hour
Hour
LS
8.00
8.00
16.00
16.00
30.00
20 uses
Unit
Quantity
Hour
Hour
LS
Unit
18.00
18.00
10.00
Quantity
Rate
in Rs.
Hour
8.00
Rate
in Rs.
113.90
Day
Day
Day
Day
Day
Day
1.00
2.00
2.00
3.00
2.00
4.00
440.00
385.00
385.00
440.00
385.00
345.00
440.00
770.00
770.00
1320.00
770.00
1380.00
Day
Day
Day
2.00
2.00
2.00
385.00
345.00
385.00
Rs:
Rs:
770.00
690.00
770.00
8591.20
429.56
Rate
in Rs.
151.80
Amount
in Rs.
1214.40
20 uses
Unit
Hour
Quantity
8.00
120
Foreman
Structural steel Erector
Helper erector
Khalasi
3
For dismantling of supports:
Foreman
Structural steel Erector
Helper erector
Khalasi
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
Day
Day
Day
Day
1.00
2.00
2.00
4.00
440.00
440.00
345.00
385.00
440.00
880.00
690.00
1540.00
Day
Day
Day
Day
0.50
1.00
1.00
2.00
440.00
440.00
345.00
385.00
Rs:
220.00
440.00
345.00
770.00
6539.40
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
2677.04
210.02
7869.20
429.56
6539.40
17725.22
177.25
797.63
283.60
443.13
19426.84
Rs:
2719.76
145.6 Rs./Tonne
Rs:
Rs:
149.24
22295.84
22295.80
6969.00
0.14 975.70
7944.70
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery for fabrication
C. Hire charges of Machinery for erection and dismantling
D. Cost of Labour for fabrication
E. Cost of Labour for erection and dismantling
Total
Add for Air and Water line @
Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @
1.00%
4.50%
1.60%
2.50%
Total
14%
IRR-TAW-3-5 Providing and fixing hard variety cut jungle wood for lagging / blocking locations in tunnel
wherever required including cost of all materials, machinery, labour, fixing in position, lighting,
ventilation, drainage etc complete with all leads and lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
Particulars
UNIT :
Unit
cum
LS
Quantity
1.05
2.00
Description
Unit
Drilling jumbo
Fuel / Energy charges
Total hire charges of Machinery
Hour
Hour
C. LABOUR:
Sl No
Description
1
2
3
Unit
Hour
Day
Day
Quantity
2.00
2.00
Quantity
2.00
1.00
2.00
1.00 cum
Rate
in Rs.
23000.00
41.00
Rs:
Amount
in Rs.
24150.00
82.00
24232.00
Rate
in Rs.
368.40
46.00
Rs:
Amount
in Rs.
736.80
92.00
828.80
Rate
in Rs.
151.80
345.00
295.00
Rs:
Amount
in Rs.
303.60
345.00
590.00
1238.60
Rs:
Rs:
24232.00
828.80
1238.60
0.14 173.40
1412.00
121
C. Cost of Labour
Total
Add for Air and Water line @
Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @
1.00%
4.50%
1.60%
2.50%
Total
14%
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
1238.60
26299.40
262.99
1183.47
420.79
657.49
28824.14
Rs:
Rs:
Rs:
4035.38
32859.52
32859.50
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
Particulars
Cement
Rubble stones
Stone chips
Sand (Screened)
UNIT :
Unit
kg
cum
cum
cum
Description
Unit
10 hp pump ( ele )
Fuel / energy charges
Total hire charges of Machinery
Hour
Hour
C. LABOUR:
Sl No
1
2
3
4
5
Description
Unit
Quantity
10.00 cum
Rate
in Rs.
950.00
8.30
1.25
4.00
TOTAL
2.5%
Quantity
4.00
318.00
340.00
606.00
Rs:
Rs:
Rs:
Rate
in Rs.
1.00
1.00
Quantity
Amount
in Rs.
3800.00
2639.40
425.00
2424.00
9288.40
232.21
9520.61
6.70
76.10
Rs:
Amount
in Rs.
6.70
76.10
82.80
Rate
in Rs.
Hour
Day
Day
Day
1.00
1.00
1.00
2.00
72.10
370.00
385.00
345.00
Amount
in Rs.
72.10
370.00
385.00
690.00
Day
Day
Day
Day
Day
Day
Day
1.00
2.00
2.00
1.00
4.00
1.00
3.00
TOTAL
15.0%
295.00
295.00
295.00
295.00
295.00
295.00
295.00
Rs:
Rs:
Rs:
295.00
590.00
590.00
295.00
1180.00
295.00
885.00
5647.10
847.07
6494.17
Rs:
Rs:
Rs:
Rs:
9520.61
82.80
6494.17
16097.58
649.42
0.14 90.90
740.30
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
122
1.00%
4.50%
1.60%
2.50%
Rs:
Rs:
Rs:
Rs:
Rs:
160.98
724.39
257.56
402.44
17642.94
14%
Rs:
cum @
31.5 Rs./Cum
cum @
30.4 Rs./Cum
2470.01
126
290.32
Total
D.Add for contractor's profit and overheads on (A+B+C+other
percentages)
Lead Charges for 1 Km for FA
4.00
Lead Charges for 1 Km for Stones and Stone Chips 9.55
Lead Charges for 1Km for Cement (including
Loading and Unloading Charges)
Total cost for
Rate per cum
0.95
tonne @
10.00 cum
(A+B+C+D)/10.0
124.6 Rs./Tonne
Rs:
Rs:
118.37
20647.64
2064.80
DATA
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
UNIT :
Particulars
Unit
tonne
kg
LS
B. MACHINERY:
Sl No
Description
Unit
Nil
Quantity
1.05
13.50
5.00
Quantity
1.00 tonne
Rate
in Rs.
46500.00
70.00
41.00
Rs:
Amount
in Rs.
48825.00
945.00
205.00
49975.00
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
450.00
295.00
Rs:
Amount
in Rs.
4050.00
4425.00
8475.00
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
49975.00
0.00
8475.00
58450.00
584.50
2630.25
935.20
1461.25
64061.20
0.00
0.00
Description
Bar bender
mazdoor
Unit
Day
Day
Quantity
9.00
15.00
8475.00
0.14 1186.50
9661.50
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Add for Air and Water line @
Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @
1.00%
4.50%
1.60%
2.50%
Total
8968.57
152.88
73182.65
73182.60
IRR-TAW-5-2 Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than
123
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
Particulars
Unit
kg
cum
cum
cum
cum
kg
LS
B. MACHINERY:
Sl No
1
2
3
4
5
UNIT :
Description
Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS
C. LABOUR:
Sl No
Description
1
2
3
4
5
6
7
Unit
Quantity
6160.00
12.60
7.56
5.04
11.20
24.64
2.00
Quantity
8.00
8.00
16.00
16.00
8.00
8.00
8.00
8.00
2.00
Quantity
Hour
Hour
Hour
Hour
Day
Day
8.00
16.00
8.00
8.00
1.00
1.00
Day
Day
Day
Day
Day
Day
Day
2.00
3.00
2.00
7.00
14.00
2.00
2.00
28.00 cum
Rate
in Rs.
4.00
1145.00
1210.00
875.00
462.00
80.00
41.00
Rs:
Amount
in Rs.
24640.00
14427.00
9147.60
4410.00
5174.40
1971.20
82.00
59852.20
Rate
in Rs.
405.40
342.40
758.40
937.80
6.70
76.10
8.00
7.60
41.00
Rs:
Amount
in Rs.
3243.20
2739.20
12134.40
15004.80
53.60
608.80
64.00
60.80
82.00
33990.80
Rate
in Rs.
293.80
244.90
72.10
136.60
385.00
370.00
Amount
in Rs.
2350.40
3918.40
576.80
1092.80
385.00
370.00
295.00
295.00
295.00
295.00
295.00
295.00
295.00
Rs:
590.00
885.00
590.00
2065.00
4130.00
590.00
590.00
18133.40
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
59852.20
33990.80
18133.40
111976.40
1119.76
5038.94
1791.62
2799.41
122726.13
Rs:
17181.66
647.60
0.14 90.70
738.30
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Add for Air and Water line @
Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @
1.00%
4.50%
1.60%
2.50%
Total
14%
124
11.20
25.20
cum @
cum @
6.16
tonne @
28.00 cum
(A+B+C+D)/28.0
31.5 Rs./Cum
30.4 Rs./Cum
124.6 Rs./Tonne
Rs:
Rs:
352.8
766.08
767.536
141794.21
5064.10
IRR-TAW-5-3 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than
20 N / sqmm ) grade cement concrete using 40 mm and down size approved clean, hard,
graded aggregates crushed from tunnel muck for kerb and bed lining including cost of all
materials, machinery, labour, formwork, batching, mixing, conveying upto placing point in
agitator cars, placing in position, levelling, vibrating, finishing, curing, ventilation, lighting,
drainage and all other ancillary operations etc., complete with lead upto 1 km and all lifts.
( Cement content 330 kg / cum for use of super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
DATA
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
1
2
3
4
5
6
7
8
9
Unit
kg
kg
cum
cum
cum
cum
kg
sqm
LS
Description
C. LABOUR:
Sl No
1
2
3
4
5
Particulars
Cement 43 Gr
Cement for incidentals @ 1 kg / cum
Fine aggregate (Un-Screened )
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10-4.75 mm
Super plasticiser
Use rate of shuttering for kerb / bed
Sundries
Total cost of Materials
B. MACHINERY:
Sl No
UNIT :
9240.00
28.00
11.20
12.60
7.56
5.04
36.96
28.00
2.00
Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS
Description
Quantity
Quantity
8.00
8.00
16.00
16.00
8.00
8.00
8.00
8.00
5.00
Unit
Quantity
28.00 cum
Rate
in Rs.
4.00
4.00
462.00
1145.00
1210.00
875.00
80.00
174.56
41.00
Rs:
Amount
in Rs.
36960.00
112.00
5174.40
14427.00
9147.60
4410.00
2956.80
4887.79
82.00
78157.59
Rate
in Rs.
405.40
342.40
758.40
937.80
8.00
7.60
6.70
76.10
41.00
Rs:
Amount
in Rs.
3243.20
2739.20
12134.40
15004.80
64.00
60.80
53.60
608.80
205.00
34113.80
Amount
in Rs.
2350.40
3918.40
1092.80
576.80
Hour
Hour
Hour
Hour
8.00
16.00
8.00
8.00
Rate
in Rs.
293.80
244.90
136.60
72.10
Day
Day
2.00
6.00
345.00
295.00
690.00
1770.00
Day
3.00
295.00
885.00
Day
2.00
295.00
590.00
Day
2.00
295.00
590.00
Day
Day
Day
Day
2.00
2.00
21.00
1.00
385.00
345.00
295.00
370.00
770.00
690.00
6195.00
370.00
125
28.00
75.30
Rs:
2108.40
22596.80
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
78157.59
34113.80
22596.80
134868.19
1348.68
6069.07
2157.89
3371.70
147815.54
807.00
0.14 113.00
920.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Add for Air and Water line @
Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @
1.00%
4.50%
1.60%
2.50%
Total
20694.18
352.8
766.08
1154.7928
170783.38
6099.40
IRR-TAW-5-4 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than
20 N / sqmm ) grade cement concrete using 40 mm and down size approved clean, hard,
graded aggregates crushed from tunnel muck for sides and arch lining including cost of all
materials, machinery, labour, formwork, batching, mixing, conveying upto placing point in
agitator cars, placing in position, levelling, vibrating, finishing, curing, ventilation, lighting,
drainage and all other ancillary operations etc., complete with lead upto 1 km and all lifts.
( Cement content 330 kg / cum for use of super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
7
Particulars
Cement 43 Gr
Cement for incidentals @ 1 kg / cum
Fine aggregate (Un-Screened )
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10-4.75 mm
Super plasticiser
Use rate of end shuttering
Use rate of steel gantry
Sundries ( placer pipe etc )
Total cost of Materials
B. MACHINERY:
Sl No
UNIT :
Unit
kg
kg
cum
cum
cum
cum
kg
sqm
sqm
LS
Description
15840.00
48.00
19.20
21.60
12.96
8.64
63.36
6.00
100.00
5.00
Unit
Hour
Hour
Quantity
Quantity
16.00
12.00
48.00 cum
Rate
in Rs.
4.00
4.00
462.00
1145.00
1210.00
875.00
80.00
174.56
75.30
41.00
Rs:
Amount
in Rs.
63360.00
192.00
8870.40
24732.00
15681.60
7560.00
5068.80
1047.38
7530.00
205.00
134247.18
Rate
in Rs.
170.80
428.00
Amount
in Rs.
2732.80
5136.00
126
2
3
4
5
6
7
C. LABOUR:
Sl No
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS
Description
12.00
12.00
32.00
32.00
16.00
16.00
8.00
8.00
8.00
8.00
5.00
Unit
1
2
3
4
5
6
7
405.40
342.40
758.40
937.80
#REF!
#REF!
8.00
7.60
6.70
76.10
41.00
Rs:
4864.80
4108.80
24268.80
30009.60
#REF!
#REF!
64.00
60.80
53.60
608.80
205.00
#REF!
16.00
16.00
32.00
16.00
8.00
8.00
Rate
in Rs.
142.40
293.80
244.90
#REF!
136.60
72.10
Amount
in Rs.
2278.40
4700.80
7836.80
#REF!
1092.80
576.80
0.50
1.00
345.00
295.00
172.50
295.00
0.50
0.50
1.00
3.00
1.00
550.00
345.00
345.00
385.00
295.00
275.00
172.50
345.00
1155.00
295.00
0.50
0.50
0.50
1.00
3.00
1.00
550.00
440.00
345.00
345.00
385.00
295.00
275.00
220.00
172.50
345.00
1155.00
295.00
5.00
295.00
1475.00
2.00
6.00
295.00
75.30
590.00
451.80
3.00
9.00
3.00
385.00
295.00
370.00
1155.00
2655.00
1110.00
3.00
295.00
Rs:
885.00
#REF!
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
134247.18
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
14%
Rs:
cum @
31.5 Rs./Cum
cum @
30.4 Rs./Cum
#REF!
604.8
1313.28
Quantity
#REF!
0.14 #REF!
#REF!
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Add for Air and Water line @
Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @
1.00%
4.50%
1.60%
2.50%
Total
127
15.89
tonne @
48.00 cum
(A+B+C+D)/48.0
124.6 Rs./Tonne
Rs:
Rs:
1979.6448
#REF!
#REF!
IRR-TAW-6-1 Drilling 32 mm diameter grout holes in concrete / rock by percussion drilling using jack
hammer or stooper drills as directed to specified depth for consolidation / contact grouting
including cost of all materials, machinery, labour, cleaning holes, ventilation, lighting, drainage
and all other ancillary operations etc., complete.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
1
2
3
4
5
6
Particulars
B. MACHINERY:
Sl No
Unit
Quantity
Rm
100.00 Rm
Rate
in Rs.
100.00
41.69
32.00
32.00
3.00
5.47
6.84
41.00
Rs:
Amount
in Rs.
4169.33
416.93
175.00
219.00
123.00
5103.27
Rate
in Rs.
138.80
951.20
6.70
76.10
19.80
0.00
12.70
0.00
368.40
46.00
41.00
Rs:
Amount
in Rs.
1110.40
7609.60
26.80
304.40
633.60
0.00
406.40
0.00
2947.20
368.00
205.00
13611.40
Rate
in Rs.
151.80
72.10
284.70
151.80
295.00
Rs:
Amount
in Rs.
1214.40
288.40
9110.40
1214.40
590.00
12417.60
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
5103.27
13611.40
12417.60
31132.27
311.32
1400.95
498.12
778.31
34120.96
Rs:
Rs:
Rs:
4776.93
38897.90
389.00
10%
Hour
Hour
LS
Description
C. LABOUR:
Sl No
UNIT :
Unit
Quantity
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS
Description
8.00
8.00
4.00
4.00
32.00
32.00
32.00
32.00
8.00
8.00
5.00
Unit
Quantity
1
2
3
4
5
8.00
4.00
32.00
8.00
2.00
124.20
0.14 17.40
141.60
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Add for Air and Water line @
Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @
1.00%
4.50%
1.60%
2.50%
Total
14%
128
IRR-TAW-6-2 Grouting cement slurry in grout holes under specified pressure for consolidation / contact
grouting including cost of all materials, machinery, labour, redrilling wherever necessary,
ventilation,lighting, drainage and other ancillary operations etc., complete with lead upto 1 km
and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
1
2
3
4
Particulars
Cement
Use rate of grouting hose 50 m
Use rate of water hose 50 m
Sundries
Total cost of Materials
B. MACHINERY:
Sl No
Unit
tonne
Hour
Hour
LS
Description
Grouting machine
Fuel / Energy charges
Pump 10 hp ( ele )
Fuel / Energy charges
Drilling jumbo
Fuel / Energy charges
Sundries
Total hire charges of Machinery
C. LABOUR:
Sl No
UNIT :
Unit
Hour
Hour
Hour
Hour
Hour
Hour
LS
Description
Quantity
1.50
8.00
8.00
2.00
Quantity
1.50 tonne
Rate
in Rs.
4000.00
10.94
13.69
41.00
Rs:
Amount
in Rs.
6000.00
87.50
109.50
82.00
6279.00
Rate
in Rs.
24.90
38.00
6.70
76.10
368.40
46.00
41.00
Rs:
Amount
in Rs.
199.20
304.00
13.40
152.20
736.80
92.00
82.00
1579.60
Rate
in Rs.
227.80
72.10
151.80
295.00
Rs:
Amount
in Rs.
1822.40
144.20
303.60
590.00
2860.20
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
6279.00
1579.60
2860.20
10718.80
107.19
482.35
171.50
267.97
11747.80
Rs:
1644.69
124.6 Rs./Tonne
Rs:
Rs:
186.9
13579.40
9052.90
8.00
8.00
2.00
2.00
2.00
2.00
2.00
Unit
1
2
3
4
Quantity
8.00
2.00
2.00
2.00
1906.80
0.14 267.00
2173.80
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Add for Air and Water line @
Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @
1.00%
4.50%
1.60%
2.50%
Total
14%
1.50
tonne @
1.50 tonne
(A+B+C+D)/1.50
IRR-TAW-6-3 Drilling 75 mm diameter drainage holes vertical or inclined in rock / concrete in tunnel by
percussion drilling using waggon drill or other suitable drilling equipment including cost of all
materials, machinery, labour, ventilation, lighting, drainage etc., complete.
DATA
RATE ANALYSIS
A. MATERIALS:
Sl No
1
UNIT :
Particulars
Unit
Rm
Quantity
120.00
120.00 Rm
Rate
in Rs.
125.00
Amount
in Rs.
15000.00
129
2
3
4
B. MACHINERY:
Sl No
1
2
3
4
Description
Waggon drill
Fuel / Energy charges
Air compressor 15 cmm ( ele )
Fuel / Energy charges
Pump 10 hp ( ele )
Fuel / Energy charges
Sundries
Total hire charges of Machinery
C. LABOUR:
Sl No
16.00
16.00
120.00
Unit
Quantity
Hour
Hour
Hour
Hour
Hour
Hour
LS
Description
16.00
16.00
8.00
8.00
6.00
6.00
2.00
Unit
Quantity
1
2
3
4
16.00
8.00
6.00
2.00
4.38
5.48
8.48
Rs:
70.00
87.60
1017.60
16175.20
Rate
in Rs.
188.50
0.00
138.80
951.20
6.70
76.10
41.00
Rs:
Amount
in Rs.
3016.00
0.00
1110.40
7609.60
40.20
456.60
82.00
12314.80
Rate
in Rs.
244.90
151.80
72.10
295.00
Rs:
Amount
in Rs.
3918.40
1214.40
432.60
590.00
6155.40
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
16175.20
12314.80
6155.40
34645.40
346.45
1559.04
554.33
866.14
37971.36
Rs:
Rs:
Rs:
5315.99
43287.35
360.70
51.30
0.14 7.20
58.50
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Add for Air and Water line @
Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @
1.00%
4.50%
1.60%
2.50%
Total
14%
130
Chapter III
CANAL AND ALLIED WORKS - Standard Data
3. The Leads for Steel and Cement shall be from the nearest market place to the Project area
4. For earth/rockfill embankments wherever initial lead of 1km is considered in the basic rate, the additional lead
charges are to be added as follows:
Additional lead charges for Earth, Murrum etc., shall be worked out for total lead involved and 1 km lead charges included
in basic rate shall be deducted from total lead charges. No loading and unloading charges shall be allowed for any item.
(same as above)
Example:
Total lead for earth from approved borrow area :
15 Km
Initial lead included in the basic rate in the SR :
1 Km
Additional lead charges :
Lead charges for 5 km
Rs.
84.10
Lead charges for next 10 km
Rs.
126
Total lead charges for 15 km /cum
Rs.
210.10
Less 1 km initial lead charges /cum
Rs.
31.50 (-)
Net additional lead charges / cum
Rs.
178.60
5. The initial lead up to 50 m as mentioned in some standard data items is meant for manual lead within the working area. For
conveyance of materials, the lead required from quarry/Borrow area/ Dump Area to worksite shall be added to the data without
deducting the 50 m initial lead charges
CAW-Work Items
IRR-CAW-1
EXCAVATION WORKS :
IRR-CAW-1-1
Excavation in all kinds of soil including boulders upto 0.3 m diameter for canal, seating of
embankment, filter drains / catch water drains etc., including dressing bed and sides to
required level and profile, cost of all materials, machinery, labour, placing the excavated soil
neatly in dump area or for the formation of service road / embankment as directed etc.,
complete with initial lead upto 1 km and all lifts.
131
RATE ANALYSIS
DATA:
A. MATERIALS:
Sl No
particulars
UNIT :
Unit
Quantity
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
1706.60
937.80
446.70
322.20
Rs:
Amount
in Rs.
13652.80
7502.40
21441.60
15465.60
58062.40
Rate
in Rs.
204.10
153.10
370.00
295.00
Rs:
Amount
in Rs.
1632.80
7348.80
370.00
8850.00
18201.60
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Rs:
Rs:
Rs:
Rs:
0.00
58062.40
18201.60
76264.00
Rs:
Rs:
Rs.
10676.96
86940.96
94.00
NIL
0.00
0.00
Description
Unit
Hour
Hour
Hour
Hour
Description
Unit
C. LABOUR:
Sl No
1
2
3
4
Hour
Hour
Day
Day
Quantity
8.00
8.00
48.00
48.00
Quantity
8.00
48.00
1.00
30.00
IRR-CAW-1-2
925.00 cum
19.70
0.14 2.80
22.50
Excavation in all kinds of soil including boulders upto 0.30 m dia for field channels, seating
of embankment for field channels etc., including dressing of bed and sides to required profile,
cost of all materials, machinery, labour, placing the excavated stuff for formation of service
road / embankment as directed etc., complete with lead upto 10 m and lift upto 3 m.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
particulars
UNIT :
Unit
NIL
Quantity
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
8.00 1003.10
8.00 511.50
Rs:
Amount
in Rs.
8024.80
4092.00
12116.80
0.00
0.00
C. LABOUR:
Sl No
Description
Unit
Hour
Hour
Description
Unit
440.00 cum
Quantity
Quantity
Rate
in Rs.
Amount
in Rs.
132
1
2
3
Hour
Day
Day
8.00
1.00
17.00
1632.80
370.00
5015.00
7017.80
Rs:
Rs:
Rs:
Rs:
0.00
12116.80
7017.80
19134.60
Rs:
Rs:
Rs.
2678.84
21813.44
49.60
15.90
0.14 2.20
18.10
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
440.00 cum
cum
(A+B+C+D)/440
Rate per
IRR-CAW-1-3
204.10
370.00
295.00
Rs:
Excavation in ordinary rock (including HDR) without blasting including boulders above 0.30 m upto 0.6 m dia. for
canals, seating of embankment, filter drain / catch water drains etc., including dressing of
bed and sides to required level and profile, cost of all materials, machinery, labour, placing the
excavated soft rock neatly in dump area or for formation of service road as directed etc.,
complete with lead upto 1 km and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
particulars
UNIT :
Unit
Quantity
NIL
0.00
0.00
C. LABOUR:
Sl No
1
2
3
4
5
Description
Unit
Hour
Hour
Hour
Hour
Description
Unit
Hour
Hour
Day
Day
Day
Quantity
8.00
8.00
40.00
40.00
Quantity
8.00
40.00
1.00
11.00
22.00
630.00 cum
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
1706.60
937.80
446.70
322.20
Rs:
Amount
in Rs.
13652.80
7502.40
17868.00
12888.00
51911.20
Rate
in Rs.
204.10
153.10
370.00
345.00
295.00
Rs:
Amount
in Rs.
1632.80
6124.00
370.00
3795.00
6490.00
18411.80
Rs:
Rs:
Rs:
Rs:
0.00
51911.20
18411.80
70323.00
Rs:
Rs:
Rs.
9845.22
80168.22
127.30
29.20
0.14 4.10
33.30
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
630.00 cum
cum
(A+B+C+D)/630
Rate per
133
IRR-CAW-1-4
Excavation in ordinary rock (including HDR) without blasting including boulders above 0.3 m upto 0.60 m dia. for
field channels, seating of embankment for field channels etc., including dressing of bed and
sides to required profile, cost of all materials, machinery, labour, placing the excavated stuff
for formation of service road as directed etc.,complete with lead upto 10 m and lift upto 3 m.
RATE ANALYSIS
DATA:
A. MATERIALS:
Sl No
particulars
UNIT :
Unit
Quantity
NIL
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
8.00 1003.10
8.00 511.50
Rs:
Amount
in Rs.
8024.80
4092.00
12116.80
0.00
0.00
Description
Unit
Hour
Hour
Description
Unit
C. LABOUR:
Sl No
1
2
3
4
Hour
Day
Day
Day
Quantity
Quantity
8.00
1.00
5.00
11.00
265.00 cum
Rate
in Rs.
204.10
370.00
345.00
295.00
Rs:
Amount
in Rs.
1632.80
370.00
1725.00
3245.00
6972.80
Rs:
Rs:
Rs:
Rs:
0.00
12116.80
6972.80
19089.60
Rs:
Rs:
Rs.
2672.54
21762.14
82.10
26.30
0.14 3.70
30.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
265.00 cum
cum
(A+B+C+D)/265
Rate per
IRR-CAW-1-5
Excavation in hard rock (including F&F rock) requiring blasting including boulders
above 0.6 m upto 1.2 m dia. for canals, seating of embankment, filter drain / catch water drains
etc., including dressing bed and sides to required level and profile, cost of all materials,
machinery, labour, placing the excavated rock in dump area or for formation of service
road as directed etc., complete with lead upto 1 km and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
Unit
Quantity
805.00 cum
Rm
10%
Hour
316.00
Rate
in Rs.
20.14
24.00
10.94
Amount
in Rs.
6364.24
636.42
262.50
3
4
5
6
7
kg
Nos
Nos
Rm
LS
161.00
12.00
215.00
520.00
5.00
70.00
9.00
13.00
11.00
41.00
11270.00
108.00
2795.00
5720.00
205.00
particulars
UNIT :
134
3
4
C. LABOUR:
Sl No
Description
Unit
Quantity
Hour
Hour
Hour
Hour
8.00
8.00
40.00
40.00
Hour
Hour
Hour
Hour
12.00
12.00
39.00
39.00
Description
Unit
Quantity
Rs:
27361.16
Rate
in Rs.
1706.60
937.80
446.70
322.20
Amount
in Rs.
13652.80
7502.40
17868.00
12888.00
275.60
959.10
19.80
0.00
Rs:
3307.20
11509.20
772.20
0.00
67499.80
Rate
in Rs.
204.10
153.10
182.20
284.70
370.00
440.00
345.00
345.00
345.00
295.00
Rs:
Amount
in Rs.
1632.80
6124.00
2186.40
11103.30
370.00
440.00
345.00
5520.00
5520.00
9440.00
42681.50
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
805.00 cum
cum
(A+B+C+D)/805
Rate per
IRR-CAW-1-6
(a)
Note:
Rs:
27361.16
Rs:
67499.80
Rs:
42681.50
Rs: 137542.46
Rs:
19255.94
Rs: 156798.40
Rs.
194.80
Excavation in hard rock of all toughness by blasting including boulders above 1.2 m dia. for
canals, seating of embankment, filter drain / catch water drains etc., including levelling the bed
by removing all projections by hammering / chiselling, cost of all materials, machinery, labour,
placing the excavated rock neatly in approved dump area and levelling the same as directed
etc., complete with initial lead upto 1 km and all lifts.
i ) The rate under this item shall be adopted for canals designed for carrying capacity of less
than 15 cumecs or where the average depth of excavation in hard rock is less than 3 m.
ii ) The rate includes levelling canal bed by hammering / chiselling all rock projections wherever
required.
135
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
7
1
2
3
4
5
C. LABOUR:
Sl No
1
2
3
4
5
6
7
8
9
10
11
Unit
Quantity
68.00 cum
Rm
10%
Hour
85.00
Rate
in Rs.
26.85
13.00
10.94
Amount
in Rs.
2282.53
228.25
142.19
kg
Nos
Nos
Rm
LS
21.20
4.00
59.00
90.00
2.00
70.00
9.00
13.00
11.00
41.00
Rs:
1484.00
36.00
767.00
990.00
82.00
6011.97
Rate
in Rs.
1706.60
937.80
1715.50
656.00
446.70
322.20
Amount
in Rs.
1877.26
1031.58
428.88
164.00
1965.48
1417.68
275.60
959.10
19.80
0.00
Rs:
1791.40
6234.15
257.40
0.00
15167.83
Rate
in Rs.
204.10
204.10
153.10
182.20
284.70
370.00
440.00
345.00
345.00
345.00
295.00
Amount
in Rs.
224.51
51.03
673.64
1184.30
3701.10
185.00
440.00
345.00
172.50
172.50
590.00
B. MACHINERY:
Sl No
particulars
UNIT :
Description
Unit
Quantity
Hour
Hour
Hour
Hour
Hour
Hour
1.10
1.10
0.25
0.25
4.40
4.40
Hour
Hour
Hour
Hour
6.50
6.50
13.00
13.00
Description
Unit
Hour
Hour
Hour
Hour
Hour
Day
Day
Day
Day
Day
Day
Quantity
1.10
0.25
4.40
6.50
13.00
0.50
1.00
1.00
0.50
0.50
2.00
136
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
68.00 cum
cum
(A+B+C+D)/68
Rate per
Note:
7739.58
Rs:
Rs:
Rs:
Rs:
6011.97
15167.83
7739.58
28919.37
Rs:
Rs:
Rs.
4048.71
32968.08
484.80
113.80
0.14 15.90
129.70
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
IRR-CAW-1-7
(b)
Rs:
Excavation in hard rock of all toughness including boulders above 1.2 m dia. by approved
controlled blasting methods for canals, cut-off trench of embankment, filter / catch-water
drains etc., including controlling fly-rock by muffling arrangements such as placing
50 x 50 mm opening chain link mesh or waste tyres and sand bags, monitoring ground
vibrations at specified locations, costof all materials, machinery, labour, placing excavated rock
neatly in approved dump area or other place as directed etc., complete with lead upto 1 km
and all lifts.
i ) The rate under this item shall be adopted for canals designed for carrying capacity of less
than 15 cumecs or where the average depth of excavation in hard rock is less than 3 m.
ii ) The rate under this item shall be adopted where the control of fly-rock and ground vibrations
is required.
DATA
RATE ANALYSIS
A. MATERIALS:
Sl No
particulars
UNIT :
Unit
Quantity
68.00 cum
Rate
in Rs.
Amount
in Rs.
137
1
2
3
4
5
6
7
8
9
Rm
10%
Hour
sqm
Nos
85.00
26.85
13.00
94.00
98.00
10.94
53.33
14.67
2282.53
228.25
142.19
5013.02
1437.66
kg
Nos
Nos
Rm
LS
21.20
4.00
59.00
90.00
2.00
70.00
9.00
23.00
11.00
41.00
Rs:
1484.00
36.00
1357.00
990.00
82.00
13052.65
Rate
in Rs.
1706.60
937.80
1715.50
656.00
446.70
322.20
Amount
in Rs.
1877.26
1031.58
428.88
164.00
1965.48
1417.68
275.60
959.10
19.80
0.00
Rs:
1791.40
6234.15
257.40
0.00
15167.83
Rate
in Rs.
204.10
204.10
153.10
182.20
284.70
370.00
440.00
345.00
345.00
345.00
295.00
Rs:
Amount
in Rs.
224.51
51.03
673.64
1184.30
3701.10
185.00
220.00
172.50
172.50
172.50
885.00
7642.08
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs.
13052.65
15167.83
7642.08
35862.55
179.31
36041.87
5045.86
41087.73
604.20
B. MACHINERY:
Sl No
1
2
3
4
5
C. LABOUR:
Sl No
Description
Unit
Quantity
Hour
Hour
Hour
Hour
Hour
Hour
1.10
1.10
0.25
0.25
4.40
4.40
Hour
Hour
Hour
Hour
6.50
6.50
13.00
13.00
Description
Unit
Quantity
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Add for blasting studies & monitoring vibrations etc
0.50%
Total
D. Add for contractor's profit and overheads on
14%
Total cost for
68.00 cum
cum
(A+B+C+D)/68
Rate per
IRR-CAW-1-8
( c)
Excavation in hard rock of all toughness including boulders above 1.2 m dia. for dressing
canal sides neatly on either side to required profile by line drilling and smooth blasting
including removing under-cuts by chiselling / hammering, placing the excavated rock neatly in
dump area or other place as directed, cost of all materials, machinery, labour etc., complete
with lead upto 1 km and all lifts.
138
Note:
i) For excavation of canal below free board level combination of normal / controlled blasting and
line drilling and smooth blasting shall be adopted to obtain neat side slopes. For the purpose
of payment 1 m width of excavation on either side shall be treated as excavation by line drilling
and smooth blasting and remaining portion shall be treated as excavation by normal / controlled
blasting as the case may be.
ii ) The rate under this item shall be adopted for canals designed for carrying capacity of less
than 15 cumecs or where the average depth of excavation in hard rock is less than 3 m.
iii ) The rate includes controlling fly-rock wherever required.
iv ) The rate under this item shall be paid only on ascertaining that the excavated face has
come off neatly as per specifications or atleast 50 percent of smooth blast holes are visible for
inspection and are spaced at specified interval.
v ) In case, where the above criteria is not fulfilled payment shall be restricted to rate provided
for excavation by normal blasting or controlled blasting as the case may be.
DATA
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
3
4
C. LABOUR:
Sl No
1
2
3
4
5
6
Unit
Rm
10%
Hour
63.00
kg
Nos
Rm
LS
3.50
22.00
20.00
1.00
B. MACHINERY:
Sl No
1
particulars
UNIT :
Quantity
10.00
Description
Unit
Quantity
Hour
Hour
Hour
Hour
0.28
0.28
1.12
1.12
Hour
Hour
Hour
Hour
5.00
5.00
10.00
10.00
Description
Unit
Hour
Hour
Hour
Hour
Day
Day
Quantity
0.50
1.12
5.00
10.00
0.50
0.50
17.50 cum
Rate
Amount
in Rs.
in Rs.
26.85
1691.76
169.18
10.94
109.38
70.00
23.00
11.00
41.00
Rs:
245.00
506.00
220.00
41.00
2982.31
Rate
in Rs.
1706.60
937.80
446.70
322.20
Amount
in Rs.
477.85
262.58
500.30
360.86
275.60
959.10
19.80
0.00
Rs:
1378.00
4795.50
198.00
0.00
7973.10
Rate
in Rs.
204.10
153.10
182.20
284.70
370.00
440.00
Amount
in Rs.
102.05
171.47
911.00
2847.00
185.00
220.00
139
7
8
9
10
Helper blaster
Stone breaker
Stone chiseller Cl - II
mazdoor
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
Day
Day
Day
Day
0.50
0.50
0.50
1.00
Total
Add for blasting studies & monitoring vibrations etc
0.50%
Total
D. Add for contractor's profit and overheads on
14%
Total cost for
17.50 cum
cum
(A+B+C+D)/17.50
Rate per
Note:
172.50
172.50
172.50
295.00
5249.02
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs.
2982.31
7973.10
5249.02
16204.43
81.02
16285.46
2279.96
18565.42
1060.90
299.90
0.14 42.00
341.90
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
IRR-CAW-1-9
(a)
345.00
345.00
345.00
295.00
Rs:
Excavation in hard rock by blasting including boulders above 1.2 m dia. for canals, seating
embankment etc., including levelling bed by removing all projections by hammering / chiselling,
cost of all materials, machinery, labour, placing the excavated rock neatly in approved dump
area and levelling the same as directed etc.,complete with initial lead upto 1 km and all lifts.
i ) The rate under this item shall be adopted for canals designed for carrying capacity of more
than 15 cumecs or where the average depth of excavation in hard rock is more than 3 m.
ii ) The rate includes levelling canal bed by hammering / chiselling all rock projections wherever
required.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
particulars
Unit:
Unit
Quantity
386.00 Cum
Rate
Amount
140
1
2
3
5
6
7
8
9
10
11
12
B. MACHINERY:
Sl No
1
2
3
4
5
6
C. LABOUR:
Sl No
Description
Rm
104.00
in Rs.
150.00
Rm
104.00
6.36
661.44
12.00
26.85
322.24
32.22
Hour
10.50
18.63
195.56
Hour
kg
kg
ltr
1.00
38.00
155.00
35.00
10.94
73.00
43.00
62.00
10.94
2774.00
6665.00
2170.00
kg
Nos
Rm
Rm
LS
4.00
20.00
145.00
20.00
5.00
70.00
9.00
10.00
11.00
41.00
Rs:
280.00
180.00
1450.00
220.00
205.00
30766.40
Rate
in Rs.
446.70
322.20
1706.60
937.80
1715.50
656.00
Amount
in Rs.
11096.03
8003.45
10597.99
5823.74
3431.00
1312.00
275.60
959.10
188.50
0.00
19.80
0.00
Rs:
3169.40
11029.65
1979.25
0.00
39.60
0.00
56482.10
Rate
in Rs.
153.10
204.10
204.10
182.20
244.90
284.70
370.00
440.00
345.00
345.00
345.00
295.00
Rs:
Amount
in Rs.
3803.00
1267.46
408.20
2095.30
2571.45
569.40
740.00
440.00
345.00
345.00
345.00
885.00
13814.82
Rm
10%
Unit
Quantity
Hour
Hour
Hour
Hour
Hour
Hour
24.84
24.84
6.21
6.21
2.00
2.00
Hour
Hour
Hour
Hour
Hour
Hour
11.50
11.50
10.50
10.50
2.00
2.00
Description
Unit
Quantity
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
in Rs.
15600.00
Rs:
30766.40
Rs:
56482.10
Rs:
13814.82
Rs: 101063.32
141
Rs:
14148.86
Rs: 115212.18
Rs.
298.50
IRR-CAW-1-10 Excavation in hard rock of all toughness including boulders above 1.2 m dia. by approved
(b)
controlled blasting methods for canals, cut-off trench of embankment etc., including
controlling fly-rock by muffling arrangements such as placing 50 x 50 mm opening
chain link mesh or waste tyres and sand bags, monitoring ground vibrations at specified
locations, cost of all materials, machinery, labour, placing excavated rock neatly in approved
dump area or other place as directed etc., complete with lead upto 1 km and all lifts.
Note:
i ) The rate under this item shall be adopted for canals designed for carrying capacity of more
than 15 cumecs or where the average depth of excavation in hard rock is more than 3 m.
ii ) The rate under this item shall be adopted where the control of fly-rock and ground vibrations
is required.
DATA
RATE ANALYSIS
A. MATERIALS:
Sl No
UNIT :
particulars
Unit
Rm
1
2
3
Quantity
386.00 cum
104.00
Rate
in Rs.
150.00
Amount
in Rs.
15600.00
Rm
104.00
6.36
661.44
Rm
10%
12.00
26.85
322.24
32.22
Hour
10.50
18.63
195.56
Hour
kg
2.00
38.00
10.94
73.00
21.88
2774.00
142
6
7
ANFO
Diesel oil
8
9
10
11
12
13
14
15
B. MACHINERY:
Sl No
1
2
3
4
5
6
C. LABOUR:
Sl No
Description
kg
ltr
155.00
35.00
43.00
62.00
6665.00
2170.00
kg
Nos
Rm
Nos
Rm
sqm
Nos
LS
4.00
20.00
120.00
12.00
20.00
132.00
110.00
20.00
70.00
9.00
65.00
21.00
11.00
190.80
11.17
41.00
Rs:
280.00
180.00
7800.00
252.00
220.00
25185.60
1228.70
820.00
64408.64
Rate
in Rs.
446.70
322.20
1706.60
937.80
1715.50
656.00
Amount
in Rs.
13401.00
9666.00
17066.00
9378.00
3431.00
1312.00
275.60
959.10
188.50
0.00
19.80
0.00
Rs:
3445.00
11988.75
2167.75
0.00
39.60
0.00
71895.10
Rate
in Rs.
153.10
204.10
204.10
182.20
244.90
284.70
370.00
440.00
345.00
345.00
345.00
295.00
Rs:
Amount
in Rs.
4593.00
2041.00
408.20
2277.50
2816.35
569.40
555.00
220.00
172.50
345.00
345.00
1475.00
15817.95
Unit
Quantity
Hour
Hour
Hour
Hour
Hour
Hour
30.00
30.00
10.00
10.00
2.00
2.00
Hour
Hour
Hour
Hour
Hour
Hour
12.50
12.50
11.50
11.50
2.00
2.00
Description
Unit
Quantity
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Add for blasting studies & monitoring vibrations etc
0.50%
Total
D. Add for contractor's profit and overheads on
14%
Total cost for
386.00 cum
cum
(A+B+C+D)/386
Rate per
Rs:
64408.64
Rs:
71895.10
Rs:
15817.95
Rs: 152121.69
Rs:
760.61
Rs: 152882.30
Rs:
21403.52
Rs: 174285.82
Rs.
451.50
IRR-CAW-1-11 Excavation in hard rock of all toughness including boulders above 1.2 m dia. for dressing
( c)
canal sides neatly on either side to required profile by line drilling and smooth blasting
143
including removing under-cuts by chiselling / hammering, placing the excavated rock neatly in
dump area or other place as directed, cost of all materials, machinery, labour etc., complete
with lead upto 1 km and all lifts.
Note:
i ) For excavation of canal below free board level combination of normal / controlled blasting and
line drilling and smooth blasting shall be adopted to obtain neat side slopes. For the purpose
of payment 1 m width of excavation on either side shall be treated as excavation by line drilling
and smooth blasting and remaining portion shall be treated as excavation by normal / controlled
blasting as the case may be.
ii ) The rate under this item shall be adopted for canals designed for carrying capacity of more
than 15 cumecs or where the average depth of excavation in hard rock is more than 3 m.
iii ) The rate includes controlling fly-rock wherever required.
iv ) The rate under this item shall be paid only on ascertaining that the excavated face has
come off neatly as per specifications or atleast 50 percent of smooth blast holes are visible for
inspection and are spaced at specified interval.
v ) In case, where the above criteria is not fulfilled payment shall be restricted to rate provided
for excavation by normal blasting or controlled blasting as the case may be.
DATA
RATE ANALYSIS
A. MATERIALS:
Sl No
UNIT :
particulars
Unit
Rm
5
6
7
1
2
3
8
9
10
11
12
13
121.00
Rate
in Rs.
150.00
Amount
in Rs.
18150.00
Rm
121.00
6.36
769.56
Rm
10%
3.00
26.85
80.56
8.06
Hour
12.00
18.63
223.50
Hour
kg
kg
ltr
0.50
5.00
19.00
4.50
10.94
73.00
43.00
62.00
5.47
365.00
817.00
279.00
kg
Nos
Rm
Nos
Rm
LS
1.00
5.00
70.00
4.00
10.00
2.00
70.00
9.00
65.00
21.00
11.00
41.00
Rs:
70.00
45.00
4550.00
84.00
110.00
82.00
25639.14
Rate
in Rs.
6.24 446.70
6.24 322.20
1.56 1706.60
Amount
in Rs.
2787.41
2010.53
2662.30
B. MACHINERY:
Sl No
1
2
Description
Unit
Hour
Hour
Hour
Quantity
97.00 cum
Quantity
144
4
5
6
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Description
Unit
C. LABOUR:
Sl No
1.56 937.80
0.50 1715.50
0.50 656.00
13.45
13.45
13.20
13.20
0.50
0.50
Quantity
1462.97
857.75
328.00
275.60
959.10
188.50
0.00
19.80
0.00
Rs:
3706.82
12899.90
2488.20
0.00
9.90
0.00
29213.77
Rate
in Rs.
153.10
204.10
204.10
182.20
244.90
284.70
370.00
440.00
345.00
345.00
345.00
295.00
Rs:
Amount
in Rs.
802.24
318.40
102.05
2450.59
3293.91
142.35
185.00
220.00
172.50
345.00
345.00
590.00
8967.04
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs.
25639.14
29213.77
8967.04
63819.94
319.10
64139.04
8979.47
73118.51
753.80
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Add for blasting studies & monitoring vibrations etc
0.50%
Total
D. Add for contractor's profit and overheads on
14%
Total cost for
97.00 cum
cum
(A+B+C+D)/97
Rate per
IRR-CAW-2
IRR-CAW-2-1
Providing impervious hearting embankment with selected soil from approved borrow areas in
layers of 25 cm before compaction including cost of all materials, machinery, labour,
all operations such as excavation, sorting out, transporting, spreading in layer of specified
thickness, breaking clods, sectioning, watering, compacting each layer to density control of
not less than 98 percent or as stipulated by Sheep foot roller / Vibratory roller/
8 to 10 tonne power roller etc., complete with initial lead upto 1 km and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
particulars
UNIT :
Unit
Nill
Quantity
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
3.40 1715.50
3.40 656.00
Amount
in Rs.
5832.70
2230.40
0.00
0.00
Description
Angle dozer
Fuel / Energy charges
Unit
Hour
Hour
412.80 cum
Quantity
145
2
3
4
5
6
7
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS
Description
Unit
C. LABOUR:
Sl No
8.00 1003.10
8.00 511.50
32.00 446.70
32.00 322.20
2.00
10.20
2.00
85.30
4.00 402.50
4.00 322.20
5.10 1342.20
5.10 1108.30
5.00
41.00
Rs:
Quantity
Rate
in Rs.
204.10
204.10
153.10
96.10
153.10
227.80
370.00
295.00
Rs:
Amount
in Rs.
693.94
1632.80
4899.20
192.20
612.40
1161.78
740.00
1180.00
11112.32
Rs:
Rs:
Rs:
Rs:
0.00
60577.05
11112.32
71689.37
Rs:
Rs:
Rs.
10036.51
81725.88
198.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
412.80 cum
cum
(A+B+C+D)/412.80
Rate per
IRR-CAW-2-2
8024.80
4092.00
14294.40
10310.40
20.40
170.60
1610.00
1288.80
6845.22
5652.33
205.00
60577.05
Providing impervious hearting embankment with selected soil from approved borrow areas in
layers of 25 cm before compaction including cost of all materials, machinery, labour,
all operations such as excavation, sorting out, transporting, spreading in layer of specified
thickness, breaking clods, sectioning, watering, compacting each layer to density control of
not less than 95 percent or as stipulated by Sheep foot roller / Vibratory roller/
8 to 10 tonne power roller etc., complete with initial lead upto 1 km and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
particulars
UNIT :
Unit
Nill
Quantity
0.00
0.00
Description
Angle dozer 90 hp
Fuel / Energy charges
Shovel 0.5 cum
Fuel / Energy charges
Tippers 5 cum
Fuel / Energy charges
Unit
Hour
Hour
Hour
Hour
Hour
Hour
Quantity
3.40
3.40
8.00
8.00
32.00
32.00
412.80 cum
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
1715.50
656.00
1003.10
511.50
446.70
322.20
Amount
in Rs.
5832.70
2230.40
8024.80
4092.00
14294.40
10310.40
146
4
5
6
7
Pump 5 hp ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Vibratory Roller 8 tonne
Fuel / Energy charges
Sundries
Total hire charges of Machinery
Hour
Hour
Hour
Hour
Hour
Hour
LS
Description
Unit
C. LABOUR:
Sl No
2.00
10.20
2.00
85.30
4.00 402.50
4.00 322.20
4.18 1342.20
4.18 1108.30
5.00
41.00
Rs:
Quantity
3.40
8.00
32.00
2.00
4.00
4.18
2.00
4.00
0.14
Rate
in Rs.
204.10
204.10
153.10
96.10
153.10
227.80
370.00
295.00
Rs:
26.40
3.70
30.10
Amount
in Rs.
693.94
1632.80
4899.20
192.20
612.40
952.20
740.00
1180.00
10902.74
Rs:
Rs:
Rs:
Rs:
0.00
58322.59
10902.74
69225.33
Rs:
Rs:
Rs.
9691.55
78916.88
191.20
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
412.80 cum
cum
(A+B+C+D)/412.80
Rate per
IRR-CAW-2-3
20.40
170.60
1610.00
1288.80
5610.40
4632.69
205.00
58322.59
Providing semi-pervious / pervious casing embankment using soil from approved borrow area
in layers of 25 cm before compaction including cost of all materials, machinery, labour,
all operations such as excavation, sortingout, transporting, spreading in layer of specified
thickness, breaking clods, sectioning, watering, compacting to density control of not less
than 98 percent or as stipulated by Sheep foot roller / Vibratory roller/ 8 to 10 tonne power roller
etc., complete with initial lead upto 1 km and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
particulars
UNIT :
Unit
Nill
Quantity
0.00
0.00
Description
Angle dozer 90 hp
Fuel / Energy charges
Shovel 0.50 cum capacity
Fuel / Energy charges
Tippers 5.00 cum capacity 3 Nos.
Fuel / Energy charges
Pump 5 hp ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Vibratory Roller 8 tonne
Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Quantity
3.40
3.40
8.00
8.00
32.00
32.00
2.00
2.00
4.00
4.00
5.10
412.80 cum
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
1715.50
656.00
1003.10
511.50
446.70
322.20
10.20
85.30
402.50
322.20
1342.20
Amount
in Rs.
5832.70
2230.40
8024.80
4092.00
14294.40
10310.40
20.40
170.60
1610.00
1288.80
6845.22
147
Hour
LS
Description
Unit
C. LABOUR:
Sl No
5.10 1108.30
2.00
41.00
Rs:
Quantity
3.40
8.00
32.00
2.00
4.00
5.10
2.00
4.00
0.14
Rate
in Rs.
204.10
204.10
153.10
96.10
153.10
227.80
370.00
295.00
Rs:
26.90
3.80
30.70
Amount
in Rs.
693.94
1632.80
4899.20
192.20
612.40
1161.78
740.00
1180.00
11112.32
Rs:
Rs:
Rs:
Rs:
0.00
60454.05
11112.32
71566.37
Rs:
Rs:
Rs.
10019.29
81585.66
197.60
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
412.80 cum
cum
(A+B+C+D)/412.80
Rate per
IRR-CAW-2-4
5652.33
82.00
60454.05
Providing semi-pervious / pervious casing embankment using soil from approved borrow area
in layers of 25cm before compaction including cost of all materials, machinery, labour,
all operations such as excavation, sortingout, transporting, spreading in layer of specified
thickness, breaking clods, sectioning, watering, compacting to density control of not less
than 95 percent or as stipulated by Sheep foot roller / Vibratory roller/ 8 to 10 tonne power roller
etc., complete with initial lead upto 1 km and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
particulars
UNIT :
Unit
Nill
Quantity
0.00
0.00
Description
Unit
Angle dozer 90 hp
Fuel / Energy charges
Shovel 0.5 cum
Fuel / Energy charges
Tippers 5 cum
Fuel / Energy charges
Pump 5 hp ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Vibratory Roller 8 tonne
Fuel / Energy charges
Sundries
Total hire charges of Machinery
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS
Quantity
3.40
3.40
8.00
8.00
32.00
32.00
2.00
2.00
4.00
4.00
4.17
4.17
5.00
412.80 cum
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
1715.50
656.00
1003.10
511.50
446.70
322.20
10.20
85.30
402.50
322.20
1342.20
1108.30
41.00
Rs:
Amount
in Rs.
5832.70
2230.40
8024.80
4092.00
14294.40
10310.40
20.40
170.60
1610.00
1288.80
5596.97
4621.61
205.00
58298.09
C. LABOUR:
148
Sl No
Description
Unit
Quantity
Rate
in Rs.
204.10
204.10
153.10
96.10
153.10
227.80
370.00
295.00
Rs:
Amount
in Rs.
693.94
1632.80
4899.20
192.20
612.40
911.20
1542.90
1180.00
11664.64
Rs:
Rs:
Rs:
Rs:
0.00
58298.09
11664.64
69962.73
Rs:
Rs:
Rs.
9794.78
79757.51
193.20
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
412.80 cum
cum
(A+B+C+D)/412.80
Rate per
IRR-CAW-2-5
Providing semi-pervious / pervious casing embankment using soil from approved borrow area
in layers of 25cm before compaction including cost of all materials, machinery, labour,
all operations such as excavation, sortingout, transporting, spreading in layer of specified
thickness, breaking clods, sectioning, compacting each layer without watering to density
control of not less than 95 percent or as stipulated by Sheep foot roller / Vibratory roller/
8 to 10 tonne power roller etc., complete with initial lead upto 1 km and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
particulars
UNIT :
Unit
Nill
Quantity
0.00
0.00
C. LABOUR:
Sl No
1
2
3
4
5
6
Description
Unit
Angle dozer 90 hp
Fuel / Energy charges
Shovel 0.50 cum capacity
Fuel / Energy charges
Tippers 5.00 cum capacity 3 Nos.
Fuel / Energy charges
Vibratory Roller 8 tonne
Fuel / Energy charges
Sundries
Total hire charges of Machinery
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS
Description
Unit
Hour
Hour
Hour
Hour
Day
Day
Total cost of Labour
Quantity
3.40
3.40
8.00
8.00
32.00
32.00
4.17
4.17
2.00
Quantity
3.40
8.00
32.00
4.17
2.00
4.00
412.80 cum
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
1715.50
656.00
1003.10
511.50
446.70
322.20
1342.20
1108.30
41.00
Rs:
Amount
in Rs.
5832.70
2230.40
8024.80
4092.00
14294.40
10310.40
5596.97
4621.61
82.00
55085.29
Rate
in Rs.
204.10
204.10
153.10
227.80
370.00
295.00
Rs:
Amount
in Rs.
693.94
1632.80
4899.20
949.93
740.00
1180.00
10095.87
149
24.50
0.14 3.40
27.90
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
412.80 cum
cum
(A+B+C+D)/412.80
Rate per
IRR-CAW-2-6
Rs:
Rs:
Rs:
Rs:
0.00
55085.29
10095.87
65181.15
Rs:
Rs:
Rs.
9125.36
74306.51
180.00
Providing hearting / casing embankment with homogeneous soil from approved borrow
areas in layers of 25 cm before compaction including cost of all materials, machinery,
labour, all operations such as excavation, sorting out, transporting, spreading in layer of
specified thickness, breaking clods, sectioning, watering, compacting each layer to density
control of not less than 98 percent or as stipulated by Sheep foot roller / Vibratory roller/
8 to 10 tonne power roller etc., complete with initial lead upto 1 km and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
particulars
UNIT :
Unit
Nill
Quantity
0.00
0.00
C. LABOUR:
Sl No
Description
Unit
Angle dozer
Fuel / Energy charges
Shovel 0.50 cum capacity
Fuel / Energy charges
Tippers 5.00 cum capacity 6 Nos.
Fuel / Energy charges
Pump 5 hp ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Vibratory Roller 8 tonne
Fuel / Energy charges
Sundries
Total hire charges of Machinery
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS
Description
Unit
Quantity
6.06
6.06
8.00
8.00
48.00
48.00
3.00
3.00
6.00
6.00
7.53
7.53
2.00
Quantity
677.28 cum
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
1715.50
656.00
1003.10
511.50
446.70
322.20
10.20
85.30
402.50
322.20
1342.20
1108.30
41.00
Rs:
Amount
in Rs.
10395.93
3975.36
8024.80
4092.00
21441.60
15465.60
30.60
255.90
2415.00
1933.20
10106.77
8345.50
82.00
86564.26
Rate
in Rs.
204.10
204.10
153.10
96.10
153.10
227.80
370.00
295.00
Rs:
Amount
in Rs.
1236.85
1632.80
7348.80
288.30
918.60
1715.33
740.00
1180.00
15060.68
150
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
677.28 cum
cum
(A+B+C+D)/677.28
Rate per
IRR-CAW-2-7
Rs:
0.00
Rs:
86564.26
Rs:
15060.68
Rs: 101624.94
Rs:
14227.49
Rs: 115852.43
Rs.
171.10
Providing hearting / casing embankment with homogeneous soil from approved borrow
areas in layers of 25 cm before compaction including cost of all materials, machinery,
labour, all operations such as excavation, sorting out, transporting, spreading in layer of
specified thickness, breaking clods, sectioning, watering, compacting each layer to density
control of not less than 95 percent or as stipulated by Sheep foot roller / Vibratory roller/
8 to 10 tonne power roller etc., complete with initial lead upto 1 km and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
particulars
UNIT :
Unit
Nill
Quantity
0.00
0.00
C. LABOUR:
Sl No
Description
Unit
Angle dozer 90 hp
Fuel / Energy charges
Shovel 0.5 cum
Fuel / Energy charges
Tippers 5 cum 3 Nos
Fuel / Energy charges
Pump 5 hp ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Vibratory Roller 8 tonne
Fuel / Energy charges
Sundries
Total hire charges of Machinery
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS
Description
Unit
Quantity
6.06
6.06
8.00
8.00
48.00
48.00
3.00
3.00
6.00
6.00
6.16
6.16
5.00
Quantity
677.28 cum
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
1715.50
656.00
1003.10
511.50
446.70
322.20
10.20
85.30
402.50
322.20
1342.20
1108.30
41.00
Rs:
Amount
in Rs.
10395.93
3975.36
8024.80
4092.00
21441.60
15465.60
30.60
255.90
2415.00
1933.20
8267.95
6827.13
205.00
83330.07
Rate
in Rs.
204.10
204.10
153.10
96.10
153.10
227.80
370.00
295.00
Rs:
Amount
in Rs.
1236.85
1632.80
7348.80
288.30
918.60
1403.25
740.00
1180.00
14748.59
Rs:
Rs:
Rs:
Rs:
0.00
83330.07
14748.59
98078.66
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
151
Rs:
13731.01
Rs: 111809.67
Rs.
165.10
Providing casing embankment using homogeneous soil from approved borrow area
in layers of 25 cm before compaction including cost of all materials, machinery, labour,
all operations such as excavation, sortingout, transporting, spreading in layer of specified
thickness, breaking clods, sectioning, compacting each layer without watering to density
control of not less than 95 percent or as stipulated by Sheep foot roller / Vibratory roller/
8 to 10 tonne power roller etc., complete with initial lead upto 1 km and all lifts.
RATE ANALYSIS
DATA:
A. MATERIALS:
Sl No
particulars
UNIT :
Unit
Quantity
Nill
0.00
0.00
C. LABOUR:
Sl No
1
2
3
4
5
6
Description
Unit
Angle dozer 90 hp
Fuel / Energy charges
Shovel 0.50 cum capacity
Fuel / Energy charges
Tippers 5.00 cum capacity 4 Nos.
Fuel / Energy charges
Vibratory Roller 8 tonne
Fuel / Energy charges
Sundries
Total hire charges of Machinery
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS
Description
Unit
Hour
Hour
Hour
Hour
Day
Day
Quantity
6.06
6.06
8.00
8.00
48.00
48.00
6.16
6.16
2.00
Quantity
6.06
8.00
48.00
6.16
2.00
4.00
677.28 cum
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
1715.50
656.00
1003.10
511.50
446.70
322.20
1342.20
1108.30
41.00
Rs:
Amount
in Rs.
10395.93
3975.36
8024.80
4092.00
21441.60
15465.60
8267.95
6827.13
82.00
78572.37
Rate
in Rs.
204.10
204.10
153.10
227.80
370.00
295.00
Rs:
Amount
in Rs.
1236.85
1632.80
7348.80
1403.25
740.00
1180.00
13541.69
Rs:
Rs:
Rs:
Rs:
0.00
78572.37
13541.69
92114.06
20.00
0.14 2.80
22.80
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
677.28 cum
cum
(A+B+C+D)/677.28
Rate per
Rs:
12895.97
Rs: 105010.03
Rs.
155.00
IRR-CAW-3
IRR-CAW-3-1
Providing impervious hearting embankment with soil from approved dump areas in layers
of 25 cm before compaction including cost of all materials, machinery, labour, all
operations such as re-excavation, sorting out, transporting, spreading in layer of specified
thickness, breaking clods, sectioning, watering, compacting each layer to achieve density
152
control of not less than 98 percent or as stipulated by Sheep foot roller / Vibratory roller/
8 to 10 tonne power roller etc.,complete with initial lead upto 1 km and all lifts.
RATE ANALYSIS
DATA:
A. MATERIALS:
Sl No
particulars
UNIT :
Unit
Nill
Quantity
0.00
0.00
C. LABOUR:
Sl No
Description
Unit
Angle dozer
Fuel / Energy charges
Shovel 0.50 cum capacity
Fuel / Energy charges
Tippers 5.00 cum capacity 6 Nos.
Fuel / Energy charges
Pump 5 hp ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Vibratory Roller 8 tonne
Fuel / Energy charges
Sundries
Total hire charges of Machinery
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS
Description
Unit
Quantity
4.04
4.04
8.00
8.00
48.00
48.00
3.00
3.00
6.00
6.00
7.50
7.50
2.00
Quantity
735.36 cum
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
1715.50
656.00
1003.10
511.50
446.70
322.20
10.20
85.30
402.50
322.20
1342.20
1108.30
41.00
Rs:
Amount
in Rs.
6930.62
2650.24
8024.80
4092.00
21441.60
15465.60
30.60
255.90
2415.00
1933.20
10066.50
8312.25
82.00
81700.31
Rate
in Rs.
204.10
204.10
153.10
96.10
153.10
227.80
370.00
295.00
Rs:
Amount
in Rs.
730.68
1632.80
7348.80
288.30
918.60
1708.50
740.00
1770.00
15137.68
Rs:
Rs:
Rs:
Rs:
0.00
81700.31
15137.68
96837.99
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
735.36 cum
cum
(A+B+C+D)/735.36
Rate per
IRR-CAW-3-2
DATA:
Rs:
13557.32
Rs: 110395.31
Rs.
150.10
Providing impervious hearting embankment with soil from approved dump areas in layers
of 25 cm before compaction including cost of all materials, machinery, labour, all
operations such as re-excavation, sorting out, transporting, spreading in layer of specified
thickness, breaking clods, sectioning, watering, compacting each layer to achieve density
control of not less than 95 percent or as stipulated by Sheep foot roller / Vibratory roller/
8 to 10 tonne power roller etc.,complete with initial lead upto 1 km and all lifts.
RATE ANALYSIS
UNIT :
735.36 cum
153
A. MATERIALS:
Sl No
particulars
Unit
Nill
Quantity
0.00
0.00
Description
Unit
Angle dozer 90 hp
Fuel / Energy charges
Shovel 0.5 cum
Fuel / Energy charges
Tippers 5 cum
Fuel / Energy charges
Pump 5 hp ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Vibratory Roller 8 tonne
Fuel / Energy charges
Sundries
Total hire charges of Machinery
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS
Description
Unit
C. LABOUR:
Sl No
Quantity
4.04
4.04
8.00
8.00
48.00
48.00
3.00
3.00
6.00
6.00
6.13
6.13
5.00
Quantity
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
1715.50
656.00
1003.10
511.50
446.70
322.20
10.20
85.30
402.50
322.20
1342.20
1108.30
41.00
Rs:
Amount
in Rs.
6930.62
2650.24
8024.80
4092.00
21441.60
15465.60
30.60
255.90
2415.00
1933.20
8227.69
6793.88
205.00
78466.13
Rate
in Rs.
204.10
204.10
153.10
96.10
153.10
227.80
370.00
295.00
Rs:
Amount
in Rs.
824.56
1632.80
7348.80
288.30
918.60
1396.41
740.00
1770.00
14919.48
Rs:
Rs:
Rs:
Rs:
0.00
78466.13
14919.48
93385.60
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
735.36 cum
cum
(A+B+C+D)/735.36
Rate per
IRR-CAW-3-3
Rs:
13073.98
Rs: 106459.58
Rs.
144.80
Providing semi-pervious / pervious casing embankment using soil from approved dump area
in layers of 25 cm before compaction including cost of all materials, machinery, labour,
all operations such as re-excavation, sorting out, transporting, spreading in layer of specified
thickness, breaking clods, sectioning, watering, compacting each layer to density control of
not less than 98 percent or as stipulated by Sheep foot roller / Vibratory roller/
8 to 10 tonne power roller etc., complete with initial lead upto 1 km and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
particulars
Nill
UNIT :
Unit
Quantity
0.00
0.00
768.00 cum
Rate
in Rs.
0.00
0.00
Amount
in Rs.
0.00
0.00
154
Description
Unit
Angle dozer 90 hp
Fuel / Energy charges
Shovel 0.50 cum capacity
Fuel / Energy charges
Tippers 5.00 cum capacity 6 Nos
Fuel / Energy charges
Pump 5 hp ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Vibratory Roller 8 tonne
Fuel / Energy charges
Sundries
Total hire charges of Machinery
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS
Description
Unit
C. LABOUR:
Sl No
Quantity
4.22
4.22
8.00
8.00
48.00
48.00
3.00
3.00
6.00
6.00
7.82
7.82
2.00
Quantity
Rs:
0.00
Rate
in Rs.
1715.50
656.00
1003.10
511.50
446.70
322.20
10.20
85.30
402.50
322.20
1342.20
1108.30
41.00
Rs:
Amount
in Rs.
7239.41
2768.32
8024.80
4092.00
21441.60
15465.60
30.60
255.90
2415.00
1933.20
10496.00
8666.91
82.00
82911.34
Rate
in Rs.
204.10
204.10
153.10
96.10
153.10
227.80
370.00
295.00
Rs:
Amount
in Rs.
861.30
1632.80
7348.80
288.30
918.60
1781.40
740.00
1770.00
15341.20
Rs:
Rs:
Rs:
Rs:
0.00
82911.34
15341.20
98252.54
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
768.00 cum
cum
(A+B+C+D)/768
Rate per
IRR-CAW-3-4
Rs:
13755.36
Rs: 112007.90
Rs.
145.80
Providing semi-pervious / pervious casing embankment using soil from approved dump area
in layers of 25 cm before compaction including cost of all materials, machinery, labour,
all operations such as re-excavation, sorting out, transporting, spreading in layer of specified
thickness, breaking clods, sectioning, watering, compacting each layer to density control of
not less than 95 percent or as stipulated by Sheep foot roller / Vibratory roller/
8 to 10 tonne power roller etc., complete with initial lead upto 1 km and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
particulars
UNIT :
Unit
Nill
Quantity
0.00
0.00
Description
Unit
Quantity
768.00 cum
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
Amount
155
1
2
3
4
5
6
7
Angle dozer 90 hp
Fuel / Energy charges
Shovel 0.5 cum
Fuel / Energy charges
Tippers 5 cum of 6 Nos
Fuel / Energy charges
Pump 5 hp ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Vibratory Roller 8 tonne
Fuel / Energy charges
Sundries
Total hire charges of Machinery
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS
Description
Unit
C. LABOUR:
Sl No
4.22
4.22
8.00
8.00
48.00
48.00
3.00
3.00
6.00
6.00
6.40
6.40
5.00
Quantity
4.22
8.00
48.00
3.00
6.00
6.40
2.00
6.00
0.14
in Rs.
1715.50
656.00
1003.10
511.50
446.70
322.20
10.20
85.30
402.50
322.20
1342.20
1108.30
41.00
Rs:
in Rs.
7239.41
2768.32
8024.80
4092.00
21441.60
15465.60
30.60
255.90
2415.00
1933.20
8590.08
7093.12
205.00
79554.63
Rate
in Rs.
204.10
204.10
153.10
96.10
153.10
227.80
370.00
295.00
Rs:
19.60
2.70
22.30
Amount
in Rs.
861.30
1632.80
7348.80
288.30
918.60
1457.92
740.00
1770.00
15017.72
Rs:
Rs:
Rs:
Rs:
0.00
79554.63
15017.72
94572.35
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
768.00 cum
cum
(A+B+C+D)/768
Rate per
IRR-CAW-3-5
Rs:
13240.13
Rs: 107812.48
Rs.
140.40
Providing semi-pervious / pervious casing embankment using soil from approved dump area
in layers of 25 cm before compaction including cost of all materials, machinery, labour,
all operations such as re-excavation, sorting out, transporting, spreading in layer of specified
thickness, breaking clods, sectioning, compacting each layer without watering to density
control of not less than 95 percent or as stipulated by Sheep foot roller / Vibratory roller/
8 to 10 tonne power roller etc., complete with initial lead upto 1 km and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
particulars
UNIT :
Unit
Nill
Quantity
0.00
0.00
Description
Angle dozer 90 hp
Fuel / Energy charges
Shovel 0.50 cum capacity
Fuel / Energy charges
Unit
Hour
Hour
Hour
Hour
Quantity
4.22
4.22
8.00
8.00
768.00 cum
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
1715.50
656.00
1003.10
511.50
Amount
in Rs.
7239.41
2768.32
8024.80
4092.00
156
3
4
5
Hour
Hour
Hour
Hour
LS
Description
Unit
C. LABOUR:
Sl No
1
2
3
4
5
6
Hour
Hour
Hour
Hour
Day
Day
48.00 446.70
48.00 322.20
6.40 1342.20
6.40 1108.30
2.00
41.00
Rs:
Quantity
4.22
8.00
48.00
6.40
2.00
6.00
21441.60
15465.60
8590.08
7093.12
82.00
74796.93
Rate
in Rs.
204.10
204.10
153.10
227.80
370.00
295.00
Rs:
Amount
in Rs.
861.30
1632.80
7348.80
1457.92
740.00
1770.00
13810.82
Rs:
Rs:
Rs:
Rs:
0.00
74796.93
13810.82
88607.75
18.00
0.14 2.50
20.50
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
768.00 cum
cum
(A+B+C+D)/768
Rate per
Rs:
12405.09
Rs: 101012.84
Rs.
131.50
IRR-CAW-4
IRR-CAW-4-1
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
particulars
UNIT :
Unit
Nill
Quantity
0.00
0.00
C. LABOUR:
Sl No
1
Description
Unit
Angle dozer 90 hp
Fuel / Energy charges
Pump 5 hp ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Vibratory Roller 8 tonne
Fuel / Energy charges
Sundries
Total hire charges of Machinery
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS
Description
Unit
Hour
Quantity
3.60
3.60
3.00
3.00
5.00
5.00
7.30
7.30
2.00
Quantity
3.60
600.00 cum
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
1715.50
656.00
10.20
85.30
402.50
322.20
1342.20
1108.30
41.00
Rs:
Amount
in Rs.
6175.80
2361.60
30.60
255.90
2012.50
1611.00
9798.06
8090.59
82.00
30418.05
Rate
in Rs.
204.10
Amount
in Rs.
734.76
157
2
3
4
5
6
3.00
5.00
7.30
1.00
4.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
600.00 cum
cum
(A+B+C+D)/600
Rate per
IRR-CAW-4-2
96.10
153.10
227.80
370.00
295.00
Rs:
288.30
765.50
1662.94
370.00
1180.00
5001.50
Rs:
Rs:
Rs:
Rs:
0.00
30418.05
5001.50
35419.55
Rs:
Rs:
Rs.
4958.74
40378.29
67.30
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
particulars
UNIT :
Unit
Quantity
Nill
0.00
0.00
C. LABOUR:
Sl No
Description
Unit
Angle dozer 90 hp
Fuel / Energy charges
Pump 5 hp ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Vibratory Roller 8 tonne
Fuel / Energy charges
Sundries
Total hire charges of Machinery
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS
Description
Unit
Quantity
3.60
3.60
3.00
3.00
5.00
5.00
6.06
6.06
5.00
Quantity
3.60
3.00
5.00
6.06
2.00
4.00
600.00 cum
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
1715.50
656.00
10.20
85.30
402.50
322.20
1342.20
1108.30
41.00
Rs:
Amount
in Rs.
6175.80
2361.60
30.60
255.90
2012.50
1611.00
8133.73
6716.30
205.00
27502.43
Rate
in Rs.
204.10
96.10
153.10
227.80
370.00
295.00
Rs:
Amount
in Rs.
734.76
288.30
765.50
1380.47
740.00
1180.00
5089.03
ABSTRACT:
158
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
600.00 cum
cum
(A+B+C+D)/600
Rate per
IRR-CAW-4-3
Rs:
Rs:
Rs:
Rs:
0.00
27502.43
5089.03
32591.46
Rs:
Rs:
Rs.
4562.8
37154.26
61.90
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
particulars
UNIT :
Unit
Quantity
Nill
0.00
0.00
C. LABOUR:
Sl No
Description
Unit
Angle dozer 90 hp
Fuel / Energy charges
Pump 5 hp ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Vibratory Roller 8 tonne
Fuel / Energy charges
Sundries
Total hire charges of Machinery
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS
Description
Unit
Quantity
3.60
3.60
3.00
3.00
5.00
5.00
7.30
7.30
2.00
Quantity
3.60
3.00
5.00
7.30
1.00
4.00
600.00 cum
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
1715.50
656.00
10.20
85.30
402.50
322.20
1342.20
1108.30
41.00
Rs:
Amount
in Rs.
6175.80
2361.60
30.60
255.90
2012.50
1611.00
9798.06
8090.59
82.00
30418.05
Rate
in Rs.
204.10
96.10
153.10
227.80
370.00
295.00
Rs:
Amount
in Rs.
734.76
288.30
765.50
1662.94
370.00
1180.00
5001.50
Rs:
Rs:
Rs:
Rs:
0.00
30418.05
5001.50
35419.55
Rs:
Rs:
Rs.
4958.74
40378.29
67.30
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
600.00 cum
cum
(A+B+C+D)/600
Rate per
159
IRR-CAW-4-4
RATE ANALYSIS
DATA:
A. MATERIALS:
Sl No
particulars
UNIT :
Unit
Quantity
Nill
0.00
0.00
Description
Unit
Angle dozer 90 hp
Fuel / Energy charges
Pump 5 hp ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Vibratory Roller 8 tonne
Fuel / Energy charges
Sundries
Total hire charges of Machinery
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS
Description
Unit
C. LABOUR:
Sl No
Quantity
3.60
3.60
3.00
3.00
5.00
5.00
6.1
6.1
5.00
Quantity
3.60
3.00
5.00
6.1
2.00
4.00
600.00 cum
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
1715.50
656.00
10.20
85.30
402.50
322.20
1342.20
1108.30
41.00
Rs:
Amount
in Rs.
6175.80
2361.60
30.60
255.90
2012.50
1611.00
8133.73
6716.30
205.00
27502.43
Rate
in Rs.
204.10
96.10
153.10
227.80
370.00
295.00
Rs:
Amount
in Rs.
734.76
288.30
765.50
1380.47
740.00
1180.00
5089.03
Rs:
Rs:
Rs:
Rs:
0.00
27502.43
5089.03
32591.46
Rs:
Rs:
Rs.
4562.8
37154.26
61.90
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
600.00 cum
cum
(A+B+C+D)/600
Rate per
IRR-CAW-4-5
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
particulars
UNIT :
Unit
Quantity
600.00 cum
Rate
Amount
160
Nill
0.00
Description
Unit
Angle dozer 90 hp
Fuel / Energy charges
Vibratory Roller 8 tonne
Fuel / Energy charges
Sundries
Total hire charges of Machinery
Hour
Hour
Hour
Hour
LS
Description
Unit
C. LABOUR:
Sl No
1
2
3
4
Quantity
3.60
3.60
6.06
6.06
2.00
Quantity
Hour
Hour
Day
Day
3.60
6.06
1.00
4.00
in Rs.
0.00
0.00
Rs:
0.00
Rate
in Rs.
1715.50
656.00
1342.20
1108.30
41.00
Rs:
Amount
in Rs.
6175.80
2361.60
8133.73
6716.30
82.00
23469.43
Rate
in Rs.
204.10
227.80
370.00
295.00
Rs:
Amount
in Rs.
734.76
1380.47
370.00
1180.00
3665.23
Rs:
Rs:
Rs:
Rs:
0.00
23469.43
3665.23
27134.66
Rs:
Rs:
Rs.
3798.85
30933.51
51.60
6.10
0.14 0.90
7.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
600.00 cum
cum
(A+B+C+D)/600
Rate per
IRR-CAW-4-6
in Rs.
Providing compacted embankment for field irrigation channels with gravely soil from
approved borrow area including sorting out, spreading in layers of 15 cm thickness, breaking
clods, watering, compacting, dressing sides to required slopes etc.,complete with lead upto
50 m and all lifts.
DATA
RATE ANALYSIS
A. MATERIALS:
Sl No
particulars
UNIT :
Unit
Nill
Quantity
0.00
0.00
C. LABOUR:
Sl No
1
2
3
4
Description
Unit
5 hp pump ( diesel )
Fuel / Energy charges
Total hire charges of Machinery
Hour
Hour
Description
Unit
Quantity
1.00
1.00
Quantity
25.00 cum
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
Rate
in Rs.
10.20
85.30
Rs:
Amount
in Rs.
10.20
85.30
95.50
Amount
in Rs.
96.10
370.00
862.50
1475.00
Hour
Day
Day
1.00
1.00
2.50
Rate
in Rs.
96.10
370.00
345.00
Day
5.00
295.00
0.00
161
Day
Day
2.50
5.00
295.00
295.00
737.50
1475.00
370.00
370.00
Rs:
370.00
370.00
5756.10
Rs:
Rs:
Rs:
Rs:
0.00
95.50
5756.10
5851.60
Rs:
Rs:
Rs.
819.22
6670.82
266.80
5
6
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
25.00 cum
cum
(A+B+C+D)/25
Rate per
IRR-CAW-5
IRR-CAW-5-1
Providing rubble and sand filling in layers of 22.5 to 30 cm including cost of all materials,
machinery, labour, watering, ramming etc., complete with initial lead upto 50 m and all lifts.
DATA
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
UNIT :
particulars
Unit
cum
cum
B. MACHINERY:
Sl No
Description
Unit
Nil
Quantity
10.00
4.00
Quantity
0.00
0.00
Description
mazdoor
Unit
Day
Quantity
4.00
10.00 cum
Rate
in Rs.
318.00
342.00
Rs:
Amount
in Rs.
3180.00
1368.00
4548.00
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
295.00
Rs:
Amount
in Rs.
1180.00
1180.00
Rs:
Rs:
Rs:
Rs:
4548.00
0.00
1180.00
5728.00
Rs:
Rs:
Rs.
801.92
6529.92
653.00
118.00
0.14 16.50
134.50
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
10.00 cum
cum
(A+B+C+D)/10
Rate per
IRR-CAW-5-2
Providing rubble and Murum filling in layers of 22.5 to 30 cm including cost of all materials,
machinery, labour, watering, ramming etc., complete with initial lead upto 50 m and all lifts.
162
RATE ANALYSIS
DATA
A. MATERIALS:
Sl No
1
2
UNIT :
particulars
Unit
cum
cum
B. MACHINERY:
Sl No
Description
Unit
Quantity
10.00
4.00
Quantity
Nil
0.00
0.00
Description
mazdoor
Unit
Quantity
Day
4.00
10.00 cum
Rate
in Rs.
318.00
107.00
Rs:
Amount
in Rs.
3180.00
428.00
3608.00
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
295.00
Rs:
Amount
in Rs.
1180.00
1180.00
Rs:
Rs:
Rs:
Rs:
3608.00
0.00
1180.00
4788.00
Rs:
Rs:
Rs.
670.32
5458.32
545.80
118.00
0.14 16.50
134.50
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
10.00 cum
cum
(A+B+C+D)/10
Rate per
IRR-CAW-5-3
Providing and laying 25 cm thick sand blanket below embankment including cost of all
materials, machinery, labour, spreading to specified thickness etc., complete with initial lead
upto 50 m and all lifts.
DATA
RATE ANALYSIS
A. MATERIALS:
Sl No
1
particulars
UNIT :
Unit
cum
Quantity
25.00
0.00
Description
Unit
Quantity
Nil
0.00
0.00
Description
mazdoor
Unit
Quantity
Day
Total cost of Labour
5.00
100.00 sqm
Rate
in Rs.
342.00
0.00
Rs:
Amount
in Rs.
8550.00
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
295.00
Rs:
Amount
in Rs.
1475.00
1475.00
8550.00
14.80
0.14 2.10
16.90
ABSTRACT:
163
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
100.00 sqm
sqm
(A+B+C+D)/100
Rate per
Rs:
Rs:
Rs:
Rs:
8550.00
0.00
1475.00
10025.00
Rs:
Rs:
Rs.
1403.5
11428.50
114.30
IRR-CAW-5-3-A Providing and laying sand blanket below embankment including cost of all
(New Item3- 2011-12)
materials, machinery, labour, spreading to specified thickness etc., complete with initial lead
DATA
RATE ANALYSIS
A. MATERIALS:
Sl No
1
particulars
UNIT :
Unit
cum
Quantity
100.00
0.00
Description
Unit
Quantity
Nil
0.00
0.00
Description
mazdoor
Unit
Day
Quantity
20.00
100.00 cum
Rate
in Rs.
342.00
0.00
Rs:
Amount
in Rs.
34200.00
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
295.00
Rs:
Amount
in Rs.
5900.00
5900.00
Rs:
Rs:
Rs:
Rs:
34200.00
0.00
5900.00
40100.00
Rs:
Rs:
Rs.
5614
45714.00
457.10
59.00
0.14 8.30
67.30
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
100.00 cum
cum
(A+B+C+D)/100
Rate per
IRR-CAW-5-4
34200.00
Providing and constructing dry rubble rock-toe using rubble and stone chips from
approved source including cost of all materials, machinery, labour, hand packing rubble
and stone chips, finishing top and sides to required slopes etc., complete with initial lead upto
50 m and all lifts.
DATA
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
particulars
Rubble
Stone chips
Sundries
UNIT :
Unit
cum
cum
LS
Quantity
100.00
15.00
2.00
100.00 cum
Rate
in Rs.
318.00
340.00
41.00
Rs:
Amount
in Rs.
31800.00
5100.00
82.00
36982.00
B. MACHINERY:
164
Sl No
Description
Nil
Unit
Quantity
0.00
0.00
Description
work inspector
Mason Class-II
mazdoor
Unit
Day
Day
Day
Quantity
1.00
7.00
19.00
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
Rate
in Rs.
370.00
345.00
295.00
Rs:
Amount
in Rs.
370.00
2415.00
5605.00
8390.00
Rs:
Rs:
Rs:
Rs:
36982.00
0.00
8390.00
45372.00
Rs:
Rs:
Rs.
6352.08
51724.08
517.20
83.90
0.14 11.70
95.60
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
100.00 cum
(A+B+C+D)/100
cum
Rate per
IRR-CAW-5-5
0.00
Providing and constructing longitudinal and cross graded filter drains using sand and
20 mm down graded aggregates satisfying specified filter creteria in layers as per specifications
including cost of all materials, machinery, labour, laying to required slopes, compaction etc.,
complete with initial lead upto 50 m and all lifts.
DATA
RATE ANALYSIS
A. MATERIALS:
Sl No
particulars
UNIT :
Unit
Quantity
100.00 cum
Rate
in Rs.
462.00
Amount
in Rs.
35481.60
21054.00
Sand (Un-Screened )
cum
76.80
cum
17.40 1210.00
cum
B. MACHINERY:
Sl No
Description
Unit
Nil
5.80
Quantity
0.00
0.00
Description
work inspector
mazdoor
Unit
Day
Day
Quantity
1.00
36.00
875.00
Rs:
5075.00
61610.60
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
Rate
in Rs.
370.00
295.00
Rs:
Amount
in Rs.
370.00
10620.00
10990.00
Rs:
Rs:
Rs:
61610.60
0.00
10990.00
0.00
109.90
0.14 15.40
125.30
165
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
100.00 cum
cum
(A+B+C+D)/100
Rate per
IRR-CAW-5-6
DATA:
Rs:
72600.60
Rs:
Rs:
Rs.
10164.08
82764.68
827.60
Laying Longitudinal Drains and Transverse drains of Size 600 x600 x750 mm in Bed and
filling with 12 mm to 40 mm HG machine Crushed metal and sand in bed including
Excavation of drains and Cost of procuring of all materials including 50 m lead and for all lifts.
RATE ANALYSIS
A. MATERIALS:
Particulars
Sl.No
12 mm to 40 mm metal
1
2
Sand (Un-Screened )
Total cost of Materials
B. MACHINERY
Description
Sl.No
1
Unit
Cum
cum
Unit
Unit:
Qty
100 mt
Rate in RAmount in Rs.
13.5 1145.00
15457.50
36 462.00
16632.00
Rs.
32089.5
Quantity
Cum
45
1575.00
1575
C. LABOUR
Sl.No
1
2
Particulars
Rate in RAmount in Rs.
Unit
Qty
Labour for Sand laying
Cum
5.14 295.00
1516.30
Labour for Metal laying
Cum
1.93 295.00
569.35
Total cost of Labour
Rs.
2085.65
labour component/unit qty
20.90
Add contractor's profit and overhead charges
0.14 2.90
labour component/unit qty (including contractor's profit)
23.80
ABSTRACT
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Rs.
Rs.
Rs.
Total
Rs:
IRR-CAW-5-7
Rs:
Rs:
Rs.
32089.5
1575
2085.65
35750.15
5005.02
40755.17
407.60
Laying and fixing of 100 mm Dia 300 mm long precast porus CC plugs in bed and sides
using 1.181 Kgs of cement per each using 20 mm HG metal and placing in local filters of size
600x600x750 mm in size including Excavation of drains and Cost of procuring of all materials
including 50 m lead and for all lifts.
DATA
Rate Analysis
Unit
1 Plug
A. MATERIALS:
Sl.No
1
2
3
Particulars
Coarse aggregate
Sand (Un-Screened )
Cement
Total cost of Materials
Unit
Cum
cum
Kg
Rate in Amount in
Qty
Rs
Rs.
0.08 1210.00
97.28
0.203 462.00
93.79
1.181
4.00
4.72
Rs.
195.79
B. MACHINERY
Sl.No
1
2
Description
Excavation of drain with Excavator
Machine mixing Charges
Total hire charges of Machinery
Unit
Cum
Cum
Quantity
0.27
0.003
Rate in
Rs.
35.00
328.60
Total Rs.
Amount in
Rs.
9.45
0.99
10.44
166
C. LABOUR
Rate in Amount in
Sl.No
Particulars
Unit
Qty
Rs
Rs.
1
Mazdoor
Day
0.30 295.00
88.50
Total cost of Labour
Rs.
88.50
labour component/unit qty
88.50
Add contractor's profit and overhead charges
0.14 12.40
labour component/unit qty (including contractor's profit)
100.90
ABSTRACT
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Rs.
Rs.
Rs.
Total
Rs:
IRR-CAW-5-8
195.79
10.44
88.50
294.73
Rs:
Rs:
Rs.
41.26
335.99
336.00
Providing and constructing 0.50 m thick vertical or inclined graded filter media consisting of
15 cm thick sand layers and 20 cm thick 20 mm down coarse aggregate layer using approved
materials satisfying specified filter creteria as per specifications including cost of all materials,
machinery, labour, laying to required slope, compaction etc., complete with initial lead upto
50 m and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
particulars
UNIT :
Unit
Quantity
100.00 cum
Rate
in Rs.
462.00
Amount
in Rs.
27720.00
Sand (Un-Screened )
cum
60.00
cum
30.00 1210.00
36300.00
cum
10.00
875.00
Rs:
8750.00
72770.00
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
370.00
295.00
Rs:
Amount
in Rs.
370.00
10620.00
10990.00
Rs:
Rs:
Rs:
Rs:
72770.00
0.00
10990.00
83760.00
Rs:
Rs:
Rs.
11726.4
95486.40
954.90
B. MACHINERY:
Sl No
Description
Unit
Nil
Quantity
0.00
0.00
Description
work inspector
mazdoor
Unit
Day
Day
Quantity
1.00
36.00
109.90
0.14 15.40
125.30
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
100.00 cum
cum
(A+B+C+D)/100.0
Rate per
167
IRR-CAW-5-9
Providing and constructing graded filter media below and behind rock-toe consisting of
20 cm thick sand, 15 cm thick 20 mm down and 15 cm thick 40 mm down size graded coarse
aggregates satisfying filter creteria behind rock-toe and 15 cm thick sand, 20 cm thick 20 mm
down coarse aggregate and 65 cm thick 40 mm down size coarse aggregate satisfying filter
creiteria below rock-toe as per specifications including cost of all materials, machinery, labour,
laying to required slope, compaction etc., complete with initial lead upto 50 m and all lifts.
RATE ANALYSIS
DATA:
A. MATERIALS:
Sl No
1
2
3
4
UNIT :
particulars
Unit
Sand (Un-Screened )
Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm down
Total cost of Materials
cum
cum
cum
cum
B. MACHINERY:
Sl No
Description
Unit
Nil
Quantity
58.77
52.70
50.70
13.80
Quantity
0.00
0.00
Description
work inspector
mazdoors
Unit
Day
Day
Quantity
1.00
60.00
176.00 cum
Rate
Amount
in Rs.
in Rs.
462.00
27151.74
1145.00
60341.50
1210.00
61347.00
875.00
12075.00
Rs: 160915.24
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
370.00
295.00
Rs:
Amount
in Rs.
370.00
17700.00
18070.00
102.70
0.14 14.40
117.10
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
176.00 cum
cum
(A+B+C+D)/176.0
Rate per
Rs: 160915.24
Rs:
0.00
Rs:
18070.00
Rs: 178985.24
Rs:
25057.93
Rs: 204043.17
Rs.
1159.30
IRR-CAW-5-10 Providing and laying filter media consisting of 2 layers of poly-propeline nonwoven filter
(a)
fabric and 200 mm thick 20 mm down graded coarse aggregate for embankment including
cost of all materials, machinery, labour, forming toe drain etc., complete with lead upto 50 m
a. for aggregate and all leads for fabric and all lifts.
Using 200 gsm filter fabric.
168
RATE ANALYSIS
DATA:
A. MATERIALS:
Sl No
1
2
particulars
B. MACHINERY:
Sl No
Description
UNIT :
Unit
sqm
cum
cum
Unit
Quantity
Rate
in Rs.
210.00 132.00
15.00 1210.00
5.00 875.00
Rs:
Quantity
Nil
0.00
0.00
Description
work inspector
mazdoor
Unit
Quantity
Day
Day
1.00
7.00
100.00 sqm
Amount
in Rs.
27720.00
18150.00
4375.00
50245.00
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
370.00
295.00
Rs:
Amount
in Rs.
370.00
2065.00
2435.00
Rs:
Rs:
Rs:
Rs:
50245.00
0.00
2435.00
52680.00
Rs:
Rs:
Rs.
7375.2
60055.20
600.60
24.40
0.14 3.40
27.80
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
100.00 sqm
sqm
(A+B+C+D)/100.0
Rate per
IRR-CAW-5-11 Providing and laying filter media consisting of 2 layers of poly-propeline nonwoven filter
(b)
fabric and 200 mm thick 20 mm down graded coarse aggregate for embankment including
cost of all materials, machinery, labour, forming toe drain etc., complete with lead upto 50 m
for aggregate and all leads for fabric and all lifts.
b. Using 250 gsm filter fabric.
Data
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
particulars
Unit
sqm
cum
cum
B. MACHINERY:
Sl No
1
UNIT :
Description
Unit
Nil
Quantity
Rate
in Rs.
210.00 154.00
15.00 1210.00
5.00 875.00
Rs:
Quantity
0.00
0.00
Description
Unit
100.00 sqm
Quantity
Amount
in Rs.
32340.00
18150.00
4375.00
54865.00
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
Amount
169
1
2
work inspector
mazdoor
Day
Day
1.00
7.00
in Rs.
370.00
295.00
Rs:
in Rs.
370.00
2065.00
2435.00
Rs:
Rs:
Rs:
Rs:
54865.00
0.00
2435.00
57300.00
Rs:
Rs:
Rs.
8022
65322.00
653.20
24.40
0.14 3.40
27.80
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
100.00 sqm
sqm
(A+B+C+D)/100.0
Rate per
IRR-CAW-6
IRR-CAW-6-1
Providing and constructing rockfill casing to canal embankment with graded stones and
spalls from approved quarry including cost of all materials, machinery, labour, spreading
stones and spalls in layers, hand packing, wedging, finishing surface to required slopes etc.,
complete with initial lead upto 50 m and all lifts.
DATA
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
UNIT :
particulars
Unit
cum
B. MACHINERY:
Sl No
Description
Unit
Quantity
100.00
15.00
Quantity
Nil
0.00
0.00
Description
Mason Cl- II
mazdoor
Unit
Quantity
Day
Day
6.00
8.00
100.00 cum
Rate
in Rs.
318.00
340.00
Rs:
Amount
in Rs.
31800.00
5100.00
36900.00
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
345.00
295.00
Rs:
Amount
in Rs.
2070.00
2360.00
4430.00
Rs:
Rs:
Rs:
Rs:
36900.00
0.00
4430.00
41330.00
Rs:
Rs:
Rs.
5786.2
47116.20
471.20
44.30
0.14 6.20
50.50
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
100.00 cum
cum
(A+B+C+D)/100.0
Rate per
IRR-CAW-6-2
Providing and constructing rockfill casing to canal embankment with graded stones and
spalls available in dump yard (spoil bank) including cost of all materials, machinery, labour, spreading
stones and spalls in layers, hand packing, wedging, finishing surface to required slopes etc.,
complete with initial lead upto 50 m and all lifts.
170
Note:
Stones and spalls available in dump yard shall be issued at specified issue rate.
DATA
RATE ANALYSIS
A. MATERIALS:
Sl No
particulars
B. MACHINERY:
Sl No
Description
UNIT :
Unit
cum
Quantity
100.00
Unit
Quantity
0.00
0.00
Description
Mason Cl- II
Crowbarman
mazdoor
Rate
in Rs.
155.00
Amount
in Rs.
15500.00
175.00
Rs:
2625.00
18125.00
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
345.00
345.00
295.00
Rs:
Amount
in Rs.
2070.00
690.00
2950.00
5710.00
Rs:
Rs:
Rs:
Rs:
18125.00
0.00
5710.00
23835.00
Rs:
Rs:
Rs.
3336.9
27171.90
271.70
15.00
Nil
100.00 cum
Unit
Day
Day
Day
Quantity
6.00
2.00
10.00
57.10
0.14 8.00
65.10
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
100.00 cum
cum
(A+B+C+D)/100.0
Rate per
IRR-CAW-7
IRR-CAW-7-1
Providing cohesive non-swelling ( CNS ) soil lining to canals using soil from approved borrow
area including spreading soil in layers of thickness not more than 15 cm, breaking clods,
watering, compacting to density control of not less than 98 percent or as stipulated,
dressing to required profile etc., complete with initial lead upto 1 km and all lifts.
DATA:
:
:
:
:
:
:
:
:
:
say :
say :
say :
0.50
0.58
5.00
1
20
25
2.00
32
0.50
4.00
8
4.30
cum
cum
cum
km
km / hr
km / hr
min
sec
cum
cum
buckets
min
:
:
:
:
:
4.30
3.00
2.00
2.40
0.50
min
min
min
min
min
171
Total
:
12.20 min
No. of tippers to match corrected cycle time of shovel ( 12.60 / 4.00 )
:
3 Nos
Output of tipper / hr with 50 min working / hr ( 50 x 4.00 / 12.20 )
:
16.40 cum
Output for 3 tippers per day ( 3 x 16.40 x 8 )
say :
394 cum
Stripping of borrow area :
Generally borrow area is stripped once in a week for 6 days requirement of soil.
Area to be stripped assuming 2.0 m depth of cut ( 394 x 6 / 2.0 )
:
1182 sqm
Depth of stripping
:
0.2 m
Quantity of stripping considering 5 % extra area ( 1182x1.05x0.20 )
:
248 cum
Output of dozer per hr with 50 min / hr working for stripping
:
72 cum
Time required for stripping 248 cum
:
3.5 hours
Consider 5 hours including time for levelling stripped siol / shifting time.
Requirement of dozer for one day work of 394 cum
say :
1.00 hours
Collection of soil for embankment:
Deploy one 0.50 cum capacity shovel for 8 hours for digging and loading soil.
Deploy 3 tippers of 5.00 cum capacity for 8 hours to convey soil to embankment area.
Spreading soil in 15 cm layer:
In view of narrow width spreading soil by dozer is generally not be possible.
Soil collected in heaps along the edge of the canal can be pushed down by dozer to the extent
required and further spreading in layers of specified thickness has to be carried out by manual
labour. Deploy dozer for 2.00 hour for pushing soil.
Output of mazdoor for levelling per day
:
20 cum
Consider 27 mazdoors for levelling 551.6 cum soil including extra soil to be laid for roller
margin.
Watering;
Generally soil in the borrow area will be in moist condition. In the beginning of the season no
watering may be necessary and in summer months about 8 to 10 percent watering may be
needed to maintain soil moisture within OMC plus or minus 3 percent limit. Assuming seasonal
average of 5 % watering by weight, the daily requirement of water for 394 cum of embankment
will be about 4 tanker loads of 8000 ltrs each.
Deploy 8000 ltr capacity water tanker for 4 hours daily for watering before rolling.
Consider 2 mazdoors for spraying water.
Compaction:
Since dozer is not considered for spreading soil about 25 percent extra roller passes needed.
Generally about 10 to 12 passes of diesel road roller is adequate for achieving 98 percent density
control for 25 cm thick loose layer.
Effective length of roller drum
:
1.50 m
Speed of roller per hour
:
3.00 km
Thickness of layer
:
0.15 m
Number of roller passes to achieve specified density control
:
12 Nos
Output of roller / hr with 50 min /hr working and 75 % effenciancy
50 / 60 ( 1.5 x 3000 x 0.15 x 0.75 / 12 )
35.15625 say :
35.15 cum/hour
Time for rolling 394 cum spread soil
11.2091 say :
11.5 hours
Sorting out/ sectioning etc :
Assume 4 mazdoors for sorting out.
No extra labour required for sectioning as trimming roller margin forms part of the soil collection
for bed lining.However 5 mazdoors considered for finishing to required slopes.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
particulars
UNIT :
Unit
Nil
Quantity
0.00
0.00
Description
Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Quantity
8.00
8.00
3.00
3.00
24.00
24.00
4.00
394.00 cum
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
1003.10
511.50
1715.50
656.00
446.70
322.20
10.20
Amount
in Rs.
8024.80
4092.00
5146.50
1968.00
10720.80
7732.80
40.80
172
5
6
7
Hour
Hour
Hour
Hour
Hour
LS
Description
Unit
C. LABOUR:
Sl No
4.00
4.00
4.00
11.50
11.50
5.00
Quantity
85.30
402.50
322.20
197.20
767.30
41.00
Rs:
341.20
1610.00
1288.80
2267.80
8823.95
205.00
52262.45
Rate
in Rs.
204.10
204.10
153.10
96.10
153.10
182.20
370.00
295.00
Rs:
Amount
in Rs.
1632.80
612.30
3674.40
384.40
612.40
2095.30
740.00
11210.00
20961.60
Rs:
Rs:
Rs:
Rs:
0.00
52262.45
20961.60
73224.05
Rs:
Rs:
Rs.
10251.37
83475.42
211.90
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
394.00 cum
cum
(A+B+C+D)/394.0
Rate per
IRR-CAW-7-2
Providing cohesive non-swelling ( CNS ) soil lining to canals using soil from approved borrow
area including spreading soil in layers of thickness not more than 15 cm, breaking clods,
watering, compacting to density control of not less than 95 percent or as stipulated,
dressing to required profile etc., complete with initial lead upto 1 km and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
particulars
UNIT :
Unit
Nil
Quantity
0.00
0.00
Description
Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Quantity
8.00
8.00
3.00
3.00
24.00
24.00
4.00
4.00
4.00
4.00
10.00
10.00
394.00 cum
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
1003.10
511.50
1715.50
656.00
446.70
322.20
10.20
85.30
402.50
322.20
197.20
767.30
Amount
in Rs.
8024.80
4092.00
5146.50
1968.00
10720.80
7732.80
40.80
341.20
1610.00
1288.80
1972.00
7673.00
173
Sundries
Total hire charges of Machinery
LS
Description
Unit
C. LABOUR:
Sl No
5.00
Quantity
41.00
Rs:
205.00
50815.70
Rate
in Rs.
204.10
204.10
153.10
96.10
153.10
182.20
370.00
295.00
Rs:
Amount
in Rs.
1632.80
612.30
3674.40
384.40
612.40
1822.00
740.00
11210.00
20688.30
Rs:
Rs:
Rs:
Rs:
0.00
50815.70
20688.30
71504.00
Rs:
Rs:
Rs.
10010.56
81514.56
206.90
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
394.00 cum
cum
(A+B+C+D)/394.0
Rate per
IRR-CAW-7-3
Providing cohesive non-swelling ( CNS ) soil lining to canal using soil collected in heaps
along the edge of canal requiring CNS soil lining as part of the disposal of excavated soil from
canal excavation in CNS soil reach including spreading in layers of thickness not more than
15 cm, breaking clods, watering, compacting to density control of not less than 95 percent
or as stipulated, dressing to required profile etc., complete with lead upto upto 50 m and all
lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
particulars
UNIT :
Unit
Nil
Quantity
0.00
0.00
C. LABOUR:
Sl No
1
2
3
Description
Unit
Angle Dozer 90 hp
Fuel / Energy charges
Pump 5 hp ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Diesel road roller 8-10 tonne
Fuel / Energy charges
Sundries
Total hire charges of Machinery
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS
Description
Unit
Hour
Hour
Hour
Quantity
1.50
1.50
5.00
5.00
5.00
5.00
13.00
13.00
5.00
Quantity
1.50
5.00
5.00
394.00 cum
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
1715.50
656.00
10.20
85.30
402.50
322.20
197.20
767.30
41.00
Rs:
Amount
in Rs.
2573.25
984.00
51.00
426.50
2012.50
1611.00
2563.60
9974.90
205.00
20401.75
Rate
in Rs.
204.10
96.10
153.10
Amount
in Rs.
306.15
480.50
765.50
174
4
5
6
IRR-CAW-7-4
2368.60
740.00
11210.00
15870.75
Rs:
Rs:
Rs:
Rs:
0.00
20401.75
15870.75
36272.50
Rs:
Rs:
Rs.
5078.15
41350.65
105.00
Providing and fixing 20 x 20 x 75 cm size top surface neatly dressed canal bed level
stones including cost of all materials, labour, excavation, fixing in position to correct level etc.,
complete with lead upto 50 m and all lifts.
DATA
RATE ANALYSIS
A. MATERIALS:
Sl No
1
particulars
UNIT :
Unit
Each
Quantity
32.00
0.00
Description
Unit
Nil
Quantity
0.00
0.00
Description
Unit
Quantity
work inspector
Day
1.00
Stone chiseller Cl- I
Day
2.00
mazdoor
Day
2.00
Total cost of Labour
labour component/unit qty
54.10
Add contractor's profit and overhead charges
0.14 7.60
labour component/unit qty (including contractor's profit)
61.70
1
2
3
32 Nos.
Rate
in Rs.
23.00
0.00
Rs:
Amount
in Rs.
736.00
0.00
736.00
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
Rate
in Rs.
370.00
385.00
295.00
Rs:
Amount
in Rs.
370.00
770.00
590.00
1730.00
Rs:
Rs:
Rs:
Rs:
736.00
0.00
1730.00
2466.00
Rs:
Rs:
Rs.
345.24
2811.24
87.90
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
32.00 Nos.
each
(A+B+C+D)/32.0
Rate per
IRR-CAW-7-5
182.20
370.00
295.00
Rs:
0.00
Providing, fabricating and placing in position reinforcement steel bars for RCC works
including cleaning, straightening, cutting, bending, hooking, lapping, tying with 1.25 mm dia.
soft annealed steel wire, welding wherever required including cost of all materials, machinery,
labour etc., complete with initial lead upto 50 and all lifts.
175
RATE ANALYSIS
DATA
A. MATERIALS:
Sl No
1
2
3
UNIT : 1000.00 kg
particulars
Unit
kg
kg
LS
B. MACHINERY:
Sl No
Description
Unit
Quantity
1050.00
8.00
10.00
Quantity
Nil
0.00
0.00
Description
Bar bender
mazdoor
Unit
Quantity
Day
Day
6.00
11.00
Rate
in Rs.
46.50
70.00
41.00
Rs:
Amount
in Rs.
48825.00
560.00
410.00
49795.00
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
450.00
295.00
Rs:
Amount
in Rs.
2700.00
3245.00
5945.00
Rs:
Rs:
Rs:
Rs:
49795.00
0.00
5945.00
55740.00
Rs:
Rs:
Rs.
7803.6
63543.60
63.50
5.90
0.14 0.80
6.70
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
1000.00 kg
(A+B+C+D)/1000.0
kg
Rate per
IRR-CAW-7-6
Providing and laying 75 mm thick in-situ M-15 ( 28 days cube compressive strength not less
than 15 N / sqmm ) grade cement concrete with 20 mm down size approved, clean, hard,
graded aggregates for canal lining using vibrating cylinder type mechanical paver including
cost of all materials, machinery, labour, cleaning, batching, mixing, placing in position,
finishing, forming contraction joints, fixing PVC joint sealing strips, curing, shifting of paver
from one side to other side of canal etc., complete with initial lead upto 1 km and all lifts.
(43 Gr Cement content: 300 kg /cum (22.5 kg/ sqm) for
use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35,
FA : 0.45 cum equivalent concrete volume:79.2 cum including the extra quantity of
concrete for curvatures and bends etc.,)
DATA:
RATE ANALYSIS
A. MATERIALS:
particulars
Sl No
1
2
3
4
5
6
7
Cement 43 Gr
Coarse aggregate 20-10 mm
Coarse aggregate 10-4.75 mm
Fine aggregate (Un-Screened )
Super plasticiser
PVC sealing strip
Use rate of paving cylinder
Sundries
Total cost of Materials
UNIT :
Unit
Quantity
kg
cum
cum
cum
kg
Rm
sqm
LS
23760.00
41.18
22.18
35.64
95.04
640.00
960.00
5.00
960 sqm
Rate
Amount
in Rs.
in Rs.
4.00
95040.00
1210.00
49832.64
875.00
19404.00
462.00
16465.68
80.00
7603.20
44.00
28160.00
0.88
842.40
41.00
205.00
Rs: 217552.92
B. MACHINERY:
176
Sl No
1
2
3
4
5
6
7
8
9
Description
Unit
Quantity
Batching plant
Lubricants etc @ 5 %
Transit mixer 3 Nos
Fuel / Energy charges
Mechanical paver
Lubricants etc @ 5 %
DG set for batching plant 50 KVA
Fuel / Energy charges
DG set for paver 30 KVA
Fuel / Energy charges
Shovel 0.5 cum / Loader
Fuel / Energy charges
Water tanker
Fuel / Energy charges
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
8.00
8.00
24.00
24.00
8.00
8.00
8.00
8.00
8.00
8.00
2.00
2.00
8.00
8.00
Hour
Hour
LS
8.00
8.00
5.00
C. LABOUR:
Description
Sl No
Unit
Quantity
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Add for shifting & re-erection of BP @
Add for LH / RH shifting & erection of Paver @
Add for ledge cutting / erection of tracks etc @
2%
0.5%
1%
Amount
in Rs.
3243.20
162.16
18201.60
22507.20
2852.00
142.60
680.80
8184.00
526.40
5456.00
2006.20
1023.00
3220.00
2577.60
10.20
85.30
41.00
Rs:
81.60
682.40
205.00
71751.76
Rate
Amount
in Rs.
in Rs.
293.80
2350.40
244.90
5877.60
364.40
2915.20
113.90
1822.40
204.10
408.20
153.10
1224.80
96.10
1537.60
385.00
770.00
385.00
385.00
385.00
385.00
440.00
440.00
370.00
740.00
295.00
1475.00
295.00
2950.00
Rs:
23281.20
Rs:
Rs:
Rs:
Total
Rs:
Rs:
Rs:
Total
Rs:
14%
Rs:
cum @
31.5 Rs./
cum @
30.4 Rs./
IRR-CAW-7-7
Rate
in Rs.
405.40
20.27
758.40
937.80
356.50
17.83
85.10
1023.00
65.80
682.00
1003.10
511.50
402.50
322.20
217552.92
71751.76
23281.2
312585.88
6251.7176
1562.9294
3125.8588
323526.39
45293.69
1122.66
1926.14
124.6 Rs 2960.496
Rs: 374829.38
Rs.
390.40
Providing and laying 80 mm thick in-situ M-15 ( 28 days cube compressive strength not less
than 15 N / sqmm ) grade cement concrete with 20 mm down size approved, clean, hard,
graded aggregates for canal lining using vibrating cylinder type mechanical paver including
cost of all materials, machinery, labour, cleaning, batching, mixing, placing in position,
177
finishing, forming contraction joints, fixing PVC joint sealing strips, curing, shifting of paver
from one side to other side of canal etc., complete with initial lead upto 1 km and all lifts.
(43 Gr Cement content: 300 kg /cum (24 kg/ sqm) for
use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35,
FA : 0.45 cum equivalent concrete volume:84.48 cum including the extra quantity of
concrete for curvatures and bends etc.,)
DATA:
RATE ANALYSIS
A. MATERIALS:
particulars
Sl No
1
2
3
4
5
6
7
Unit
Quantity
kg
cum
cum
cum
kg
Rm
sqm
LS
25344.00
43.93
23.65
38.02
101.38
640.00
960.00
5.00
Unit
Quantity
Batching plant
Lubricants etc @ 5 %
Transit mixer 3 Nos
Fuel / Energy charges
Mechanical paver
Lubricants etc @ 5 %
DG set for batching plant 50 KVA
Fuel / Energy charges
DG set for paver 30 KVA
Fuel / Energy charges
Shovel 0.5 cum / Loader
Fuel / Energy charges
Water tanker
Fuel / Energy charges
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
8.00
8.00
24.00
24.00
8.00
8.00
8.00
8.00
8.00
8.00
2.00
2.00
8.00
8.00
Hour
Hour
LS
8.00
8.00
5.00
Cement 43 Gr
Coarse aggregate 20-10 mm
Coarse aggregate 10-4.75 mm
Fine aggregate (Un-Screened )
Super plasticiser
PVC sealing strip
Use rate of paving cylinder
Sundries
Total cost of Materials
B. MACHINERY:
Description
Sl No
1
2
3
4
5
6
7
8
9
UNIT :
C. LABOUR:
Description
Sl No
Unit
Quantity
960 sqm
Rate
Amount
in Rs.
in Rs.
4.00 101376.00
1210.00
53154.82
875.00
20697.60
462.00
17563.39
80.00
8110.08
44.00
28160.00
0.88
842.40
41.00
205.00
Rs: 230109.29
Rate
in Rs.
405.40
20.27
758.40
937.80
356.50
17.83
85.10
1023.00
65.80
682.00
1003.10
511.50
402.50
322.20
Amount
in Rs.
3243.20
162.16
18201.60
22507.20
2852.00
142.60
680.80
8184.00
526.40
5456.00
2006.20
1023.00
3220.00
2577.60
10.20
85.30
41.00
Rs:
81.60
682.40
205.00
71751.76
Rate
Amount
in Rs.
in Rs.
293.80
2350.40
244.90
5877.60
364.40
2915.20
113.90
1822.40
204.10
408.20
153.10
1224.80
96.10
1537.60
385.00
770.00
385.00
385.00
385.00
385.00
440.00
440.00
370.00
740.00
295.00
1475.00
295.00
2950.00
Rs:
23281.20
178
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Add for shifting & re-erection of BP @
Add for LH / RH shifting & erection of Paver @
Add for ledge cutting / erection of tracks etc @
2%
0.5%
1%
Rs:
Rs:
Rs:
Total
Rs:
Rs:
Rs:
Total
Rs:
14%
Rs:
cum @
31.5 Rs./
cum @
30.4 Rs./
IRR-CAW-7-8
230109.29
71751.76
23281.2
325142.25
6502.845
1625.7112
3251.4225
336522.23
47113.11
1197.504
2054.55
124.6 Rs 3157.8624
Rs: 390045.26
Rs.
406.30
Providing and laying 100 mm thick in situ M-15 (28 days cube compressive strength not less than
15 N /Sqmm ) grade cement concrete with 20 mm down size approved, clean, hard, graded
aggregates for canal lining using, vibrating, cylinder type mechanical paver including cost of all
materials, machinery, labour, cleaning, batching, mixing, placing in position, finishing, forming
contraction joints, fixing PVC joint sealing strips, curing, shifting of paver from one side to othere
side of canal etc., complete with initial lead upto 1 Km and all lifts.
(43 Gr Cement content: 300 kg /cum (30 kg/ sqm) for
use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35,
FA : 0.45 cum equivalent concrete volume:88 cum including the extra quantity of
concrete for curvatures and bends etc.,)
DATA:
RATE ANALYSIS
A. MATERIALS:
Particulars
Sl.No
Cement 43 Gr
1
2
Coarse aggregate 20-10 mm
Coarse aggregate 10-4.75 mm
3
Fine aggregate (Un-Screened)
4
Super plasticiser
5
PVC sealing strip
6
Use rate of paving cylinder
Total cost of Materials
B. MACHINERY:
Particulars
Sl.No
Batching plant
1
2
Transit mixer 3 Nos
Fuel / Energy charges
3
Mechanical paver
lubricants etc @ 5%
4
DG set for batching plant 50 KVA
Fuel / Energy charges
5
DG set for paver 30 KVA
Fuel / Energy charges
6
Shovel 0.5 cum / Loader
Fuel / Energy charges
7
Water tanker
Fuel / Energy charges
8
UNIT
Unit
Kg
cum
cum
cum
kg
Rm
sqm
Qty
Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Qty
800 Sqm
26400
45.76
24.64
39.6
105.6
533
800
8
24
24
8
8
8
8
8
8
2.00
2.00
8
8
C. LABOUR:
Sl No
Description
Unit
8
8
Quantity
Rate in RAmount
4.00 105600.00
1210.00
55369.60
875.00
21560.00
462.00
18295.20
80.00
8448.00
44.00
23452.00
0.8775
702.00
Rs.
233426.8
Rate in RAmount
405.40
3243.20
758.40
18201.60
937.80
22507.20
356.50
2852.00
17.83
142.60
85.10
680.80
1023.00
8184.00
65.80
526.40
682.00
5456.00
1003.10
2006.20
511.50
1023.00
402.50
3220.00
322.20
2577.60
10.20
85.30
Rs.
Rate
81.60
682.40
71384.6
Amount
179
in Rs.
in Rs.
293.80
2350.40
244.90
5877.60
364.40
2915.20
113.90
1822.40
204.10
408.20
153.10
1224.80
96.10
768.80
385.00
770.00
385.00
385.00
385.00
385.00
440.00
440.00
370.00
740.00
295.00
1475.00
295.00
2950.00
Rs:
22512.40
ABSTRACT
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Rs.
233426.8
Rs.
71384.6
Rs.
22512.40
TOTAL R 327323.8
Add for shifting & re-erection of BP @
2% Rs.
6546.476
Add for LH / RH shifting & erection of Paver @
0.5% Rs.
1636.619
Add for ledge cutting / erection of tracks etc @
1% Rs.
3273.238
Total
Rs: 338780.13
D. Add for contractor's profit and overheads on (A+B+C+other
14%
Rs:
47429.22
39.60
cum @
31.5 Rs./
1247.4
Lead Charges for 1 Km for FA
70.40
cum @
30.4 Rs./
2140.16
Lead Charges for 1 Km for CA
Lead Charges for 1Km for Cement (including
Loading and Unloading Charges)
26.40
tonne @ 124.6 Rs
3289.44
Total cost for
800.00 Sqm
Rs: 392886.35
Sqm
(A+B+C+D)/800.0
Rs.
491.10
Rate per
IRR-CAW-7-9
Note:
Dismantling, shifting and re-erecting mechanical concrete paver and DG set with all
accessories across canal CD work or other locations wherever shifting and re-erecting is
necessary including aligning paver correctly for continuing canal lining work, cost of all
materials, machinery, labour etc., complete with all leads and lifts.
Local shifting and re-erection of paver for LH and RH side lining included in concrete lining rates
under items IRR-CAW-7-7 and IRR-CAW-7-8 and saperate rate for shifting shall not be allowed.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
particulars
UNIT :
Unit
NIL
Quantity
0.00
C. LABOUR:
Sl No
Description
Unit
Tipper
Fuel / Energy charges
Sundries (ropes / rails etc)
Total hire charges of Machinery
Hour
Hour
LS
Description
Unit
Quantity
4.00
1.00
1.00
Quantity
1.00 Shifting
Rate
in Rs.
0.00
Amount
in Rs.
Rs:
0.00
Rate
in Rs.
446.70
322.20
41.00
Rs:
Amount
in Rs.
1786.8
322.2
41
2150.00
Rate
Amount
180
1
2
3
Hour
Hour
Day
4.00
8.00
6.00
in Rs.
153.10
364.40
295.00
Rs:
in Rs.
612.4
2915.2
1770
5297.60
Rs:
Rs:
Rs:
Rs:
0.00
2150.00
5297.60
7447.60
Rs:
Rs:
Rs.
1042.66
8490.26
8490.30
5297.60
0.14 741.70
6039.30
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
1.00 Shifting
Shifting
(A+B+C+D)/1.0
Rate per
IRR-CAW-7-10 Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than
10 N /sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for bed and side lining of canal(150mm thick) including finishing the junction of bed and sides
to required curveture, cost of all materials, machinery, labour, formwork including supports,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
complete with initial lead upto 50 m and all lifts. ( Cement content : 250 kg / cum )
( 43 Gr Cement content: 250 kg / cum for use of super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
DATA
RATE ANALYSIS
A. MATERIALS:
Sl No
1
3
4
6
7
B. MACHINERY:
Sl No
particulars
Description
UNIT :
Unit
kg
kg
cum
cum
cum
cum
kg
sqm
LS
Unit
Hour
Hour
Quantity
7042.5
28.17 cum
Rate
in Rs.
4.00
Amount
in Rs.
28170
140.85
4.00
563.4
12.68 1145.00 14514.593
7.61 1210.00
9203.139
5.07 875.00
4436.775
11.27 462.00
5205.816
28.17
80.00
2253.6
180
29.02
5222.94
2
41.00
82
Rs:
69652.26
Quantity
16.00
16.00
Rate
in Rs.
92.70
170.50
Amount
in Rs.
1483.2
2728
181
2
3
C. LABOUR:
Sl No
5 hp pump ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Hour
Hour
Hour
Hour
0.50
0.50
1.00
1.00
10.20
85.30
402.50
322.20
5.1
42.65
402.5
322.2
Hour
Hour
16.00
16.00
7.60
21.50
Rs:
121.6
344
5449.25
Description
Unit
Rate
in Rs.
189.80
96.10
153.10
136.60
370.00
385.00
385.00
Amount
in Rs.
3036.8
48.05
153.1
2185.6
370
770
385
295.00
295.00
295.00
295.00
295.00
Rs:
6490
2360
1770
8310.15
590
26468.70
Quantity
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
28.17 cum
cum
(A+B+C+D)/28.17
Rate per
Rs:
69652.26
Rs:
5449.25
Rs:
26468.70
Rs: 101570.21
Rs:
14219.83
Rs: 115790.04
Rs.
4110.40
IRR-CAW-7-11 Providing and laying insitu vibrated M-10 (28 days cube compressive strength not less than
10 N/sqm) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregade for bed and side lining of canal(100 mm thick) including, finishing the junction of bed and sides
to required curvature, cost of all materials, machinery, labour, formwork including supports
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
complete with initial lead up to 50 m and all lifts (Cement content: 250 kg/cum)
( 43 Gr Cement content: 250 kg / cum for use of super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
DATA
RATE ANALYSIS
A. MATERIALS:
Particulars
Sl.No
Cement for mix
1
3
4
5
UNIT:
Unit
kg
kg
cum
cum
cum
cum
kg
sqm
27 cum
540.00
13911.75
8820.90
4252.50
4989.60
2160.00
7834.41
182
Total Rs.
Rs.
C. LABOUR:
Sl No
Particulars
Unit
Qty
69509.16
69509.16
Rate in Rs Amount
Hour
Hour
Hour
Hour
Hour
Hour
16.00
16.00
0.50
0.50
1.00
1.00
92.70
170.50
10.20
85.30
402.50
322.20
1483.20
2728.00
5.10
42.65
402.50
322.20
Hour
Hour
4.00
4.00
7.60
21.50
Rs.
30.40
86.00
5100.05
Rate
in Rs.
189.80
96.10
153.10
136.60
370.00
385.00
385.00
Amount
in Rs.
3036.8
48.05
153.1
2185.6
370
770
385
295.00
295.00
295.00
295.00
295.00
Rs:
6490
2360
1770
7965
590
26123.55
Description
Unit
Quantity
ABSTRACT:
A. Cost of Materials including royalty charges
B. Hire charges of Machinery
C. Cost of Labour
Rs.
69509.16
Rs.
5100.05
Rs.
26123.55
Total Rs. 100732.76
Rs:
14102.59
Rs: 114835.35
Rs.
4253.20
IRR-CAW-7-12 Providing and laying100mm thick insitu vibrated M-10 (28 days cube compressive strength-not less than
10.00 N / sq mm) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for bed and side lining of canal lining using vibrating cylindertype mechanical paver
including cost of all materials mechinery labour batching mixing placing in position forming
contraction joints fixing pvc joint seiling strips shifting of paver from one side of canal to other
side etc.complete with 1 km lead & all lifts.
(Cement content: 250 kg / cum for use of super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
DATA:
RATE ANALYSIS
A. MATERIALS:
Particulars
Sl.No
Cement 43 Gr
1
2
Coarse aggregate 40 mm
UNIT
Unit
Kg
cum
800 Sqm
Qty Rate in Rs Amount
22000.00
4.00
88000
39.60 1145.00
45342
183
3
4
5
6
Coarse aggregate 20 mm
Coarse aggregate 10 mm
Fine aggregate (Un-Screened)
Super plasticiser
PVC sealing strip
Use rate of paving cylinder
Total cost of Materials
B. MACHINERY:
Particulars
Sl.No
Batching plant
1
2
Transit mixer 3 Nos
Fuel / Energy charges
3
Mechanical paver
lubricants etc @ 5%
4
DG set for batching plant 50 KVA
Fuel / Energy charges
5
DG set for paver 30 KVA
Fuel / Energy charges
6
Shovel 0.5 cum / Loader
Fuel / Energy charges
7
Water tanker
Fuel / Energy charges
8
cum
cum
cum
kg
Rm
sqm
23.76 1210.00
28749.6
15.84 875.00
13860
35.20 462.00
16262.4
88.00
80.00
7040
533.00
44.00
23452
800.00
0.878
702
Rs.
223408.00
Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
C. LABOUR:
Description
Sl No
Unit
8.00
8.00
Quantity
10.20
85.30
Rs.
81.6
682.4
70261.63
Rate
Amount
in Rs.
in Rs.
293.80
2350.40
244.90
5877.60
364.40
2915.20
113.90
1822.40
204.10
408.20
153.10
1224.80
96.10
768.80
385.00
770.00
385.00
385.00
385.00
385.00
440.00
440.00
370.00
740.00
295.00
1475.00
295.00
2950.00
Rs:
22512.40
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Rs.
223408.00
Rs.
70261.63
Rs.
22512.40
TOTAL R 316182.03
Add for shifting & re-erection of BP @
2% Rs.
6323.64
Add for LH / RH shifting & erection of Paver @
0.5% Rs.
1580.91
Add for ledge cutting / erection of tracks etc @
1% Rs.
3161.82
Total
Rs: 327248.40
D. Add for contractor's profit and overheads on (A+B+C+other
14%
Rs:
45814.78
35.20
cum @
31.5 Rs./
1108.8
Lead Charges for 1 Km for FA
79.20
cum @
30.4 Rs./
2407.68
Lead Charges for 1 Km for CA
Lead Charges for 1Km for Cement (including
Loading and Unloading Charges)
22.00
tonne @
124.6 Rs
2741.2
184
800.00 Sqm
(A+B+C+D)/800.0
Rs: 379320.86
Rs.
474.20
IRR-CAW-7-13 Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than
10 N /sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
aggregates for bed and side lining of canal including finishing the junction of bed and sides
to required curveture, cost of all materials, machinery, labour, formwork including supports,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
complete with initial lead upto 50 m and all lifts. ( Cement content : 250 kg / cum )
(Cement content: 250 kg / cum for use of super plasticiser(0.4% by wt. of cement),
CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
DATA
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
B. MACHINERY:
Sl No
1
2
3
C. LABOUR:
Sl No
particulars
Description
UNIT :
Unit
kg
kg
cum
cum
cum
kg
sqm
LS
Unit
Quantity
Rate
in Rs.
4.00
Amount
in Rs.
27000
135
4.00
14.04 1210.00
7.56 875.00
12.15 462.00
27
80.00
270
29.02
2
41.00
Rs:
540
16988.4
6615
5613.3
2160
7834.41
82
66833.11
6750
Quantity
Rate
in Rs.
Amount
in Rs.
Hour
Hour
Hour
Hour
Hour
Hour
16.00
16.00
0.50
0.50
1.00
1.00
92.70
170.50
10.20
85.30
402.50
322.20
1483.2
2728
5.1
42.65
402.5
322.2
Hour
Hour
16.00
16.00
7.60
21.50
Rs:
121.6
344
5449.25
Description
Unit
Rate
in Rs.
189.80
96.10
153.10
136.60
385.00
370.00
385.00
Amount
in Rs.
3036.8
48.05
153.1
2185.60
770
370
385
295.00
295.00
295.00
295.00
295.00
Rs:
6490
2360
1770
7965
590
26123.55
Quantity
27.00 cum
185
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
27.00 cum
cum
(A+B+C+D)/27.0
Rate per
Rs:
Rs:
Rs:
Rs:
66833.11
5449.25
26123.55
98405.91
Rs:
13776.83
Rs: 112182.74
Rs.
4154.90
IRR-CAW-7-14 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than
15 N /sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for bed and side lining of canal(150 mm thick) including finishing the junction of bed and sides
to required curveture, cost of all materials, machinery, labour, formwork including supports,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
complete with initial lead upto 50 m and all lifts.
(Cement content: 290 kg / cum for use of super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
DATA
RATE ANALYSIS
A. MATERIALS:
Sl No
1
3
4
5
6
B. MACHINERY:
Sl No
1
2
3
C. LABOUR:
Sl No
1
2
3
4
5
6
7
8
particulars
Description
UNIT :
Unit
kg
kg
cum
cum
cum
cum
kg
sqm
LS
Unit
Quantity
24.92 cum
Rate
in Rs.
4.00
Amount
in Rs.
28907.20
124.6
4.00
11.21 1145.00
6.73 1210.00
4.49 875.00
9.97 462.00
28.91
80.00
166.14
29.02
2
41.00
Rs:
498.4
12840.03
8141.364
3924.90
4605.216
2312.58
4820.77
82.00
66132.46
7226.8
Quantity
Rate
in Rs.
Amount
in Rs.
Hour
Hour
Hour
Hour
Hour
Hour
16.00
16.00
0.50
0.50
1.00
1.00
92.70
170.50
10.20
85.30
402.50
322.20
1483.20
2728.00
5.10
42.65
402.50
322.20
Hour
Hour
16.00
16.00
7.60
21.50
Rs:
121.60
344.00
5449.25
Description
Unit
Hour
Hour
Hour
Hour
Day
Day
Day
16.00
0.50
1.00
16.00
2.00
1.00
1.00
Rate
in Rs.
189.80
96.10
153.10
136.60
385.00
370.00
385.00
Amount
in Rs.
3036.8
48.05
153.1
2185.60
770
370
385
Day
22.00
295.00
6490
Quantity
186
Day
Day
Day
Day
8.00
6.00
24.92
2.00
295.00
295.00
295.00
295.00
Rs:
2360
1770
7351.4
590
25509.95
Rs:
Rs:
Rs:
Rs:
66132.46
5449.25
25509.95
97091.66
1023.70
0.14 143.30
1167.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
24.92 cum
cum
(A+B+C+D)/24.92
Rate per
Rs:
13592.83
Rs: 110684.49
Rs.
4441.60
IRR-CAW-7-15 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than
15 N /sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
aggregates for bed and side lining of canal(100 mm thick) including finishing the junction of bed and sides
to required curveture, cost of all materials, machinery, labour, formwork including supports,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
complete with initial lead upto 50 m and all lifts.
(Cement content: 300 kg / cum for use of super plasticiser(0.4% by wt. of cement),
CA : 0.80 cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
DATA
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
6
7
B. MACHINERY:
Sl No
1
2
3
C. LABOUR:
Sl No
1
2
particulars
Description
UNIT :
Unit
kg
kg
cum
cum
cum
kg
sqm
LS
Unit
Quantity
23.10 cum
Rate
in Rs.
4.00
Amount
in Rs.
27720
115.5
4.00
12.01 1210.00
6.47 875.00
10.40 462.00
27.72
80.00
231
29.02
2
41.00
Rs:
462
14534.52
5659.5
4802.49
2217.60
6702.77
82
62180.88
6930
Quantity
Rate
in Rs.
Amount
in Rs.
Hour
Hour
Hour
Hour
Hour
Hour
16.00
16.00
0.50
0.50
1.00
1.00
92.70
170.50
10.20
85.30
402.50
322.20
1483.2
2728
5.1
42.65
402.5
322.2
Hour
Hour
16.00
16.00
7.60
21.50
Rs:
121.6
344
5449.25
Description
Unit
Hour
Hour
Rate
in Rs.
189.80
96.10
Amount
in Rs.
3036.8
48.05
Quantity
16.00
0.50
187
3
4
5
6
7
8
153.10
136.60
385.00
370.00
385.00
153.1
2185.6
770
370
385
295.00
295.00
295.00
295.00
295.00
Rs:
6490
2360
1770
6814.5
590
24973.05
Rs:
Rs:
Rs:
Rs:
62180.88
5449.25
24973.05
92603.18
Rs:
12964.45
Rs: 105567.63
Rs.
4570.00
IRR-CAW-7-16 Providing and laying150mm thick insitu vibrated M-15 (28 days cube compressive strength-not less than
15.00 N / sq mm) grade cement concrete using 20 mm down size approved, clean, hard, graded
aggregates for bed and side lining of canal lining using vibrating cylindertype mechanical paver
including cost of all materials mechinery labour batching mixing placing in position forming
contractiom joints fixing pvc joint seiling strips shifting of paver from one side of canal to other
side etc.complete with 1km lead & all lifts.
(43 Gr Cement content: 300 kg /cum (45 kg/ sqm) for
use of super plasticiser(0.4% by wt. of cement),CA : 0.80cum, Blending Ratio of CA--65:35,
FA : 0.44 cum equivalent concrete volume:132 cum including the extra quantity of
concrete for curvatures and bends etc.,)
DATA:
RATE ANALYSIS
A. MATERIALS:
Particulars
Sl.No
Cement 43 Gr
1
2
Coarse aggregate 20 mm
Coarse aggregate 10 mm
3
Fine aggregate (Un-Screened)
4
Super plasticiser
5
PVC sealing strip
6
Use rate of paving cylinder
Total cost of Materials
B. MACHINERY:
Particulars
Sl.No
Batching plant
1
2
Transit mixer 3 Nos
Fuel / Energy charges
3
Mechanical paver
lubricants etc @ 5%
4
DG set for batching plant 50 KVA
Fuel / Energy charges
5
DG set for paver 30 KVA
Fuel / Energy charges
6
Shovel 0.5 cum / Loader
Fuel / Energy charges
UNIT
Unit
Kg
cum
cum
cum
kg
Rm
sqm
Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
800 Sqm
Qty Rate in Rs Amount
39600.00
4.00
158400
68.64 1210.00
83054.4
36.96 875.00
32340
58.08 462.00
26832.96
158.40
80.00
12672
533.00
44.00
23452
800.00
0.878
702
Rs.
337453.36
188
Water tanker
Fuel / Energy charges
Hour
Hour
8.00
8.00
402.50
322.20
3220
2577.6
8.00
8.00
10.20
85.30
Rs.
81.6
682.4
70261.63
C. LABOUR:
Description
Sl No
Unit
Quantity
Rate
Amount
in Rs.
in Rs.
293.80
2350.40
244.90
5877.60
364.40
2915.20
113.90
1822.40
204.10
408.20
153.10
1224.80
96.10
768.80
385.00
770.00
385.00
385.00
385.00
385.00
440.00
440.00
370.00
740.00
295.00
1475.00
295.00
2950.00
Rs:
22512.40
ABSTRACT
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Rs.
337453.36
Rs.
70261.63
Rs.
22512.40
TOTAL R 430227.39
Add for shifting & re-erection of BP @
2% Rs.
8604.55
Add for LH / RH shifting & erection of Paver @
0.5% Rs.
2151.14
Add for ledge cutting / erection of tracks etc @
1% Rs.
4302.27
Total
Rs: 445285.35
D. Add for contractor's profit and overheads on (A+B+C+other
14%
Rs:
62339.95
58.08
cum @
31.5 Rs./
1829.52
Lead Charges for 1 Km for FA
105.60
30.4 Rs./
3210.24
cum @
Lead Charges for 1 Km for CA
Lead Charges for 1Km for Cement (including
Loading and Unloading Charges)
39.60
tonne @ 124.6 Rs
4934.16
Total cost for
800.00 Sqm
Rs: 517599.22
Sqm
(A+B+C+D)/800.0
Rs.
647.00
Rate per
IRR-CAW-7-17 Providing and fixing pre-cast RCC template walls consisting of 0.05 cum M-15 grade
concrete using 20 mm down size coarse aggregates and 10 kg reinforcement steel moulded
as per specifications and drawing in CM 1:4 proportion including cost of all materials,
machinery, labour, formwork, fabricating and placing reinforcement steel, mixing, laying,
conveying and fixing in position including necessary excavation for seating, finishing joints in
CM 1:4, curing etc., complete with initial lead upto 1 km and all lifts.
DATA
RATE ANALYSIS
UNIT :
20.00 templete
189
A. MATERIALS:
Sl No
1
2
3
4
5
6
7
particulars
Unit
Cement 43 Gr
Sand (Un-Screened )
Coarse aggregate 20-10 mm
Coarse aggregate 10-4.75 mm
Reinforcement steel
Binding wire
Use rate of mould
Sundries( water charges & misc. )
Total cost of Materials
kg
cum
cum
cum
kg
kg
set
LS
B. MACHINERY:
Sl No
1
Description
Hand mixer
Unit
Hour
Quantity
310.00
0.50
0.50
0.30
200.00
3.00
20.00
1.00
Quantity
Rate
in Rs.
5.50
0.00
Rs:
Amount
in Rs.
44
0
44.00
Rate
in Rs.
370.00
385.00
345.00
450.00
295.00
295.00
295.00
Rs:
Amount
in Rs.
370
385
690
450
1180
590
590
4255.00
Rs:
Rs:
Rs:
Total
Rs:
14%
Rs:
cum @
31.5 Rs./
30.4 Rs./
cum @
13163.30
44.00
4255.00
17462.30
2444.72
15.75
24.32
124.6 Rs
38.626
145.6 Rs
Rs:
Rs.
29.12
20014.83
1000.70
8.00
8.00
Description
work inspector
Mason Class I for fixing
Mason Class II for casting
Bar bender
mazdoor ( casting yard )
mazdoor ( for fixing )
mazdoor for conveying
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
1
2
3
4
5
Unit
Day
Day
Day
Day
Day
Day
Day
Rate
Amount
in Rs.
in Rs.
4.00
1240
462.00
231
1210.00
605
875.00
262.5
46.50
9300
70.00
210
63.69 1273.7956
41.00
41
Rs:
13163.30
Quantity
1.00
1.00
2.00
1.00
4.00
2.00
2.00
212.80
0.14 29.80
242.60
ABSTRACT:
A. Cost of Materials including serignorage charges
B. Hire charges of Machinery
C. Cost of Labour
IRR-CAW-7-18 Providing and fixing 50 mm dia perforated GI pressure relief pipes 12.50 cm long with
one end closed with perforated GI plate and other end provided with alluminium lid hinged
to pipe including cost of all materials, labour, drilling 8 mm dia holes etc., complete with all
leads and lifts.
DATA
RATE ANALYSIS
A. MATERIALS:
Sl No
particulars
UNIT :
Unit
Quantity
10 Nos.
Rm
1.25
Rate
in Rs.
320.00
LS
10.00
41.00
Amount
in Rs.
400
410
190
Description
Unit
Quantity
LS
0.50
0.00
Rs:
810.00
Rate
in Rs.
41.00
Amount
in Rs.
20.5
Rs:
20.50
Rate
in Rs.
440.00
295.00
Rs:
Amount
in Rs.
220
147.5
367.50
Rs:
Rs:
Rs:
Rs:
810.00
20.50
367.50
1198.00
Rs:
Rs:
Rs.
167.72
1365.72
136.60
Description
Pipe fitter
mazdoor
Unit
Quantity
Day
Day
0.50
0.50
36.80
0.14 5.20
42.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
10.00 Nos.
(A+B+C+D)/10.0
each
Rate per
IRR-CAW-7-19 Providing and fixing 50 mm dia perforated GI pressure relief pipes 22.50 cm long with
one end closed with perforated GI plate and other end provided with alluminium lid hinged
to pipe including cost of all materials, labour, drilling 8 mm dia holes etc., complete with all
leads and lifts.
DATA
RATE ANALYSIS
A. MATERIALS:
Sl No
particulars
UNIT :
Unit
Quantity
Rm
2.25
LS
10.00
B. MACHINERY:
Sl No
1
Description
Unit
Quantity
LS
5.00
0.00
Description
Pipe fitter
mazdoor
Unit
Quantity
Day
Day
Total cost of Labour
0.50
0.50
10 Nos.
Rate
in Rs.
320.00
Amount
in Rs.
720
41.00
Rs:
410
1130.00
Rate
in Rs.
41.00
Amount
in Rs.
205
Rs:
205.00
Rate
in Rs.
440.00
295.00
Rs:
Amount
in Rs.
220
147.5
367.50
Rs:
Rs:
1130.00
205.00
36.80
0.14 5.20
42.00
191
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
10.00 Nos.
No.
(A+B+C+D)/10.0
Rate per
Rs:
Rs:
367.50
1702.50
Rs:
Rs:
Rs.
238.35
1940.85
194.10
IRR-CAW-7-20 Providing and fixing 50 mm dia perforated GI pressure relief pipes 30 cm long with
one end closed with perforated GI plate and other end provided with alluminium lid hinged
to pipe including cost of all materials, labour, drilling 8 mm dia holes etc., complete with all
leads and lifts.
DATA
RATE ANALYSIS
A. MATERIALS:
Sl No
particulars
UNIT :
Unit
Quantity
Rm
3.00
LS
10.00
B. MACHINERY:
Sl No
1
Description
Unit
Quantity
LS
7.00
0.00
10 Nos.
Rate
in Rs.
320.00
Amount
in Rs.
960.00
41.00
Rs:
410.00
1370.00
Rate
in Rs.
41.00
Amount
in Rs.
287.00
Rs:
287.00
Rate
in Rs.
440.00
295.00
Rs:
Amount
in Rs.
220.00
147.50
367.50
Rs:
Rs:
Rs:
Rs:
1370.00
287.00
367.50
2024.50
Rs:
Rs:
Rs.
283.43
2307.93
230.80
Description
Pipe fitter
mazdoor
Unit
Quantity
Day
Day
0.50
0.50
36.80
0.14 5.20
42.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
10.00 Nos.
No.
(A+B+C+D)/10.0
Rate per
IRR-CAW-7-21 Providing and fixing 50 mm dia perforated GI pressure relief pipes 45 cm long with
one end closed with perforated GI plate and other end provided with alluminium lid hinged
to pipe including cost of all materials, labour, drilling 8 mm dia holes etc., complete with all
leads and lifts.
DATA
RATE ANALYSIS
A. MATERIALS:
Sl No
1
particulars
UNIT :
Unit
Rm
Quantity
4.50
10 Nos.
Rate
in Rs.
320.00
Amount
in Rs.
1440.00
192
B. MACHINERY:
Sl No
1
Description
LS
Unit
LS
10.00
Quantity
10.00
0.00
41.00
Rs:
410.00
1850.00
Rate
in Rs.
41.00
Amount
in Rs.
410.00
Rs:
410.00
Rate
in Rs.
440.00
295.00
Rs:
Amount
in Rs.
220.00
147.50
367.50
Rs:
Rs:
Rs:
Rs:
1850.00
410.00
367.50
2627.50
Rs:
Rs:
Rs.
367.85
2995.35
299.50
Description
Pipe fitter
mazdoor
Unit
Quantity
Day
Day
0.50
0.50
36.80
0.14 5.20
42.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
10.00 Nos.
No.
(A+B+C+D)/10.0
Rate per
IRR-CAW-7-22 Providing and fixing 50 mm dia perforated GI pressure relief pipes 75 cm long with
one end closed with perforated GI plate and other end provided with alluminium lid hinged
to pipe including cost of all materials, labour, drilling 8 mm dia holes etc., complete with all
leads and lifts.
DATA
RATE ANALYSIS
A. MATERIALS:
Sl No
particulars
UNIT :
Unit
Quantity
GI pipe 50 mm dia
Rm
7.50
LS
10.00
B. MACHINERY:
Sl No
1
Description
Unit
LS
Quantity
15.00
0.00
Description
Pipe fitter
mazdoor
Unit
Quantity
Day
Day
Total cost of Labour
0.50
0.50
10 Nos.
Rate
in Rs.
320.00
Amount
in Rs.
2400.00
41.00
Rs:
410.00
2810.00
Rate
in Rs.
41.00
Amount
in Rs.
615.00
Rs:
615.00
Rate
in Rs.
440.00
295.00
Rs:
Amount
in Rs.
220.00
147.50
367.50
36.80
0.14 5.20
42.00
ABSTRACT:
193
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
10.00 Nos.
No.
(A+B+C+D)/10.0
Rate per
Rs:
Rs:
Rs:
Rs:
2810.00
615.00
367.50
3792.50
Rs:
Rs:
Rs.
530.95
4323.45
432.30
IRR-CAW-7-23 Providing and fixing 100 mm dia perforated PVC pipes 40 cm long for Weep holes
including cost of all materials, labour, drilling 8 mm dia holes etc. complete with all
leads and lifts.
DATA
RATE ANALYSIS
UNIT:
10 Nos.
A. MATERIALS:
Sl.No
1
Particulars
PVC pipe 100 mm dia 10 Nos
Total cost of Materials
Unit
Rm
Rate in Amount in
Qty
Rs
Rs.
10.00 175.00
1750.00
Rs.
1750.00
B. MACHINERY
Sl.No
1
Description
Unit
Nill
Total hire chargs of Machinery
Rate in Amount in
Rs.
Rs.
0.00
0.00
0.00
0.00
Rs.
0.00
Quantity
C. LABOUR
Rate in Amount in
Sl.No
Particulars
Unit
Qty
Rs
Rs.
1
Pipe fitter
Day
0.25 440.00
110.00
2
Mazdoor
Day
0.25 295.00
73.75
Total cost of Labour
Rs.
183.75
labour component/unit qty
18.40
Add contractor's profit and overhead charges
0.14 2.60
labour component/unit qty (including contractor's profit)
21.00
ABSTRACT
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Rs.
Rs.
Rs.
Total
Rs:
Rs:
Rs:
Rs.
1750.00
0.00
183.75
1933.75
270.73
2204.48
220.40
IRR-CAW-7-24 Drilling 32 mm dia pressure relief hole below pressure relief pipe for bed and side lining of
canal laid on rock including cost of all materials, machinery, labour etc., complete with all
leads and lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
UNIT :
particulars
Unit
Rm
Hour
Quantity
10.00
10%
2.00
10 Nos.
Rate
in Rs.
26.85
10.94
Rs:
Amount
in Rs.
268.53
26.85
21.88
317.26
194
B. MACHINERY:
Sl No
1
2
Description
Unit
Hour
Hour
Hour
Hour
Description
Unit
C. LABOUR:
Sl No
Quantity
1.00
1.00
2.00
2.00
Quantity
Rate
in Rs.
275.60
959.10
19.80
0.00
Rs:
Amount
in Rs.
275.60
959.10
39.60
0.00
1274.30
Rate
in Rs.
182.20
284.70
Rs:
Amount
in Rs.
182.20
569.40
751.60
Rs:
Rs:
Rs:
Rs:
317.26
1274.30
751.60
2343.16
Rs:
Rs:
Rs.
328.04
2671.20
267.10
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
10.00 Nos.
No.
(A+B+C+D)/10.0
Rate per
DATA
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
UNIT :
particulars
Unit
cum
cum
B. MACHINERY:
Sl No
Description
Unit
Quantity
0.15
0.35
Quantity
Nil
0.00
Description
Mason Cl- II
mazdoor
Unit
Quantity
Day
Day
Total cost of Labour
0.10
0.10
10 Nos.
Rate
in Rs.
875.00
462.00
Rs:
Amount
in Rs.
131.25
161.70
292.95
Rate
in Rs.
0.00
Amount
in Rs.
Rs:
0.00
Rate
in Rs.
345.00
295.00
Rs:
Amount
in Rs.
34.50
29.50
64.00
Rs:
Rs:
Rs:
292.95
0.00
64.00
6.40
0.14 0.90
7.30
195
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
10.00 Nos.
No.
(A+B+C+D)/10.0
Rate per
Rs:
356.95
Rs:
Rs:
Rs.
49.97
406.92
40.70
IRR-CAW-7-26 Providing and fixing 25 to 40 mm thick Shahabad / Talikota / other similar stone slabs
with pointing and finishing joints neatly in CM 1:3 proportion for canal / field channel lining
including cutting slabs to required size, mixing mortar, finishing joints neatly, curing etc.,
complete with lead upto 50 m and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
particulars
Unit
sqm
kg
cum
B. MACHINERY:
Sl No
1
UNIT :
Description
Unit
5 hp pump ( diesel )
Fuel / Energy charges
Total hire charges of Machinery
Hour
Hour
Description
Unit
C. LABOUR:
Sl No
Quantity
105.00
200.00
0.40
Quantity
2.00
2.00
Quantity
Operator pump
Hour
2.00
work inspector
Day
1.00
Mason Class I
Day
4.00
Mason Class II
Day
2.00
mazdoor
Day
8.00
Cartman with Double Bullock cart for
6
water
Day
1.00
Total cost of Labour
labour component/unit qty
55.50
Add contractor's profit and overhead charges
0.14 7.80
labour component/unit qty (including contractor's profit)
63.30
1
2
3
4
5
100.00 sqm
Rate
in Rs.
229.00
4.00
606.00
Rs:
Amount
in Rs.
24045.00
800.00
242.40
25087.40
Rate
in Rs.
10.20
85.30
Rs:
Amount
in Rs.
20.40
170.60
191.00
Rate
in Rs.
96.10
370.00
385.00
345.00
295.00
Amount
in Rs.
192.20
370.00
1540.00
690.00
2360.00
395.00
Rs:
395.00
5547.20
Rs:
Rs:
Rs:
Rs:
25087.40
191.00
5547.20
30825.60
Rs:
Rs:
Rs.
4315.58
35141.18
351.40
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
100.00 sqm
sqm
(A+B+C+D)/100.0
Rate per
IRR-CAW-7-27 Fixing PCC slabs of various sizes in CM 1 : 3 proportion to the side slopes of canal
including preparing bed, flush pointing joints in CM 1 : 3 propn, cost of all materials ( excluding
PCC slabs ), labour, finishing, curing etc., complete with initial lead upto 50 m and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
particulars
UNIT :
Unit
Quantity
100.00 sqm
Rate
Amount
196
1
2
Cement 43 Gr
Sand (Screened)
Total cost of Materials
B. MACHINERY:
Sl No
1
kg
cum
Description
Unit
5 hp pump ( diesel )
Fuel / Energy charges
Total hire charges of Machinery
Hour
Hour
Description
Unit
C. LABOUR:
Sl No
240.00
0.50
Quantity
2.00
2.00
Quantity
Operator pump
Hour
2.00
work inspector
Day
1.00
Mason Class I
Day
4.00
mazdoor
Day
9.00
Cartman with Double Bullock cart for
5
water
Day
1.00
Total cost of Labour
labour component/unit qty
51.50
Add contractor's profit and overhead charges
0.14 7.20
labour component/unit qty (including contractor's profit)
58.70
1
2
3
4
in Rs.
4.00
606.00
Rs:
in Rs.
960.00
303.00
1263.00
Rate
in Rs.
10.20
85.30
Rs:
Amount
in Rs.
20.40
170.60
191.00
Rate
in Rs.
96.10
370.00
385.00
295.00
Amount
in Rs.
192.20
370.00
1540.00
2655.00
395.00
Rs:
395.00
5152.20
Rs:
Rs:
Rs:
Rs:
1263.00
191.00
5152.20
6606.20
Rs:
Rs:
Rs.
924.87
7531.07
75.30
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
100.00 sqm
(A+B+C+D)/100.0
sqm
Rate per
IRR-CAW-7-28 Fixing PCC lug slabs of various sizes in CM 1 : 3 proportion for supporting PCC slab lining
including necessary excavation, refilling, flush pointing joints in CM 1 : 3 propn, cost of all
materials ( excluding PCC lug slabs ), labour, finishing, curing etc., complete with initial lead
upto 50 m and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
particulars
Unit
Cement 43 Gr
Sand ( Screened)
Total cost of Materials
kg
cum
B. MACHINERY:
Sl No
1
C. LABOUR:
Sl No
1
2
3
4
UNIT :
Description
Unit
5 hp pump ( diesel )
Fuel / Energy charges
Total hire charges of Machinery
Hour
Hour
Description
Unit
Operator pump
work inspector
Mason Class I
Mason Class II
Hour
Day
Day
Day
Quantity
58.00
0.12
Quantity
1.00
1.00
Quantity
1.00
1.00
2.00
1.00
100.00 Rm
Rate
in Rs.
4.00
606.00
Rs:
Amount
in Rs.
232.00
72.72
304.72
Rate
in Rs.
10.20
85.30
Rs:
Amount
in Rs.
10.20
85.30
95.50
Rate
in Rs.
96.10
370.00
385.00
345.00
Amount
in Rs.
96.10
370.00
770.00
345.00
197
mazdoor
Day
5.00
Cartman with Double Bullock cart for
6
water
Day
1.00
Total cost of Labour
labour component/unit qty
34.50
Add contractor's profit and overhead charges
0.14 4.80
labour component/unit qty (including contractor's profit)
39.30
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
100.00 Rm
Rm
(A+B+C+D)/100.0
Rate per
295.00
1475.00
395.00
Rs:
395.00
3451.10
Rs:
Rs:
Rs:
Rs:
304.72
95.50
3451.10
3851.32
Rs:
Rs:
Rs.
539.18
4390.50
43.90
IRR-CAW-7-29 Fixing 30 cm height pre-cast drops for field channels as directed including excavation, etc.,
complete with all leads and lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
particulars
UNIT :
Unit
Nill
Quantity
0.00
0.00
Description
Unit
Nill
Quantity
0.00
0.00
Description
work inspector
Mason Cl- II
mazdoor
Unit
Day
Day
Day
Quantity
1.00
1.00
1.00
7 Nos.
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
Rate
in Rs.
370.00
345.00
295.00
Rs:
Amount
in Rs.
370.00
345.00
295.00
1010.00
Rs:
Rs:
Rs:
Rs:
0.00
0.00
1010.00
1010.00
Rs:
Rs:
Rs.
141.4
1151.40
164.50
0.00
0.00
144.30
0.14 20.20
164.50
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
7.00 Nos.
No.
(A+B+C+D)/7.00
Rate per
IRR-CAW-7-30 Providing and fixing LDPE sheet for bed and sides of canal including cost of all materials,
labour, laying, joining etc., complete with all leads and lifts.
a. Using 500 micron thick LDPE sheet.
198
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
UNIT :
particulars
Unit
sqm
kg
B. MACHINERY:
Sl No
Description
Unit
Quantity
275.00
4.00
Quantity
Nill
0.00
0.00
Description
Unit
Quantity
250.00 sqm
Rate
in Rs.
92.00
43.00
Rs:
Amount
in Rs.
25300.00
172.00
25472.00
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
Amount
in Rs.
9.20
295.00
Rs:
2300.00
295.00
2595.00
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs.
25472.00
0.00
2595.00
28067.00
3929.38
31996.38
128.00
i ) If the surface on which the LDPE sheet is to be laid is too rough and undulating provide
average 75 mm thick sand backing to LDPE sheet.
For providing average 75 mm thick sand backing :
DATA:
( 250 x 0.075 )
RATE ANALYSIS
A. MATERIALS:
Sl No
1
particulars
18.75 cum
UNIT :
Unit
cum
Quantity
18.75
250.00 sqm
Rate
in Rs.
342.00
Amount
in Rs.
6412.50
199
0.00
0.00
Rs:
6412.50
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
295.00
Rs:
Amount
in Rs.
1770.00
1770.00
Rs:
Rs:
Rs:
Rs:
6412.50
0.00
1770.00
8182.50
Rs:
Rs:
Rs.
1145.55
9328.05
37.30
Description
Unit
Quantity
Nill
0.00
0.00
Description
mazdoor
Unit
Quantity
Day
6.00
7.10
0.14 1.00
8.10
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
250.00 sqm
(A+B+C+D)/250.0
sqm
Rate per
IRR-CAW-7-31 Providing and fixing LDPE sheet for bed and sides of canal including cost of all materials,
labour, laying, joining etc., complete with all leads and lifts.
b. Using 750 micron thick LDPE sheet.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
particulars
UNIT :
Unit
B. MACHINERY:
Sl No
Description
275.00
4.00
Unit
Nill
Quantity
Quantity
0.00
0.00
Description
Unit
Quantity
250.00 sqm
Rate
in Rs.
130.00
43.00
Rs:
Amount
in Rs.
35750.00
172.00
35922.00
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
Rate
in Rs.
Amount
in Rs.
0.00
13.00
295.00
Rs:
3250.00
295.00
3545.00
Rs:
Rs:
Rs:
35922.00
0.00
3545.00
200
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
250.00 sqm
sqm
(A+B+C+D)/250.0
Rate per
Note :
Rs:
39467.00
Rs:
Rs:
Rs.
5525.38
44992.38
180.00
i ) If the surface on which the LDPE sheet is to be laid is too rough and undulating provide
average 75 mm thick unscreened sand backing to LDPE sheet.
For providing average 75 mm thick sand backing per sqm
Rs:
37.30
IRR-CAW-7-32 Providing and fixing LDPE sheet for bed and sides of canal including cost of all materials,
labour, laying, joining etc., complete with all leads and lifts.
c. Using 1000 micron thick LDPE sheet.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
particulars
UNIT :
Unit
B. MACHINERY:
Sl No
Description
275.00
4.00
Unit
Nill
Quantity
Quantity
0.00
0.00
Description
Unit
Quantity
250.00 sqm
Rate
in Rs.
180.00
43.00
Rs:
Amount
in Rs.
49500.00
172.00
49672.00
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
Amount
in Rs.
18.00
295.00
Rs:
4500.00
295.00
4795.00
Rs:
Rs:
Rs:
Rs:
49672.00
0.00
4795.00
54467.00
Rs:
Rs:
Rs.
7625.38
62092.38
248.40
i ) If the surface on which the LDPE sheet is to be laid is too rough and undulating provide
average 75 mm thick unscreened sand backing to LDPE sheet.
For providing average 75 mm thick sand backing per sqm
Rs:
37.30
IRR-CAW-7-33 Providing and fixing 12 mm thick 380 mm depth tarfelt expansion joint filler boards for
stone masonry lining of canal including cost of all materials, labour etc., complete with all
leads and lifts.
DATA
RATE ANALYSIS
UNIT :
100.00 Rm
201
A. MATERIALS:
Sl No
particulars
Unit
Quantity
sqm
Rate
in Rs.
Amount
in Rs.
420.00
0.00
Rs:
16275.00
38.75
0.00
Description
Unit
Quantity
Nill
0.00
0.00
Description
Carpenter Cl- II
mazdoor
Unit
Quantity
Day
Day
1.00
1.00
16275.00
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
Rate
in Rs.
345.00
295.00
Rs:
Amount
in Rs.
345.00
295.00
640.00
Rs:
Rs:
Rs:
Rs:
16275.00
0.00
640.00
16915.00
Rs:
Rs:
Rs.
2368.1
19283.10
192.80
0.00
6.40
0.14 0.90
7.30
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
100.00 Rm
Rm
(A+B+C+D)/100.00
Rate per
IRR-CAW-7-34 Providing and fixing 20 mm thick 100 mm depth tarfelt expansion joint filler boards for
cement concrete lining of canal including cost of all materials, labour etc., complete with all
leads and lifts.
DATA
RATE ANALYSIS
A. MATERIALS:
Sl No
particulars
UNIT :
Unit
Quantity
sqm
10.00
0.00
Description
Unit
Quantity
Nill
0.00
0.00
Description
Carpenter Cl- II
mazdoor
Unit
Quantity
Day
Day
Total cost of Labour
1.00
1.00
100.00 Rm
Rate
in Rs.
Amount
in Rs.
6300.00
630.00
0.00
Rs:
0.00
6300.00
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
345.00
295.00
Rs:
Amount
in Rs.
345.00
295.00
640.00
6.40
0.14 0.90
202
7.30
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
100.00 Rm
Rm
(A+B+C+D)/100.00
Rate per
Rs:
Rs:
Rs:
Rs:
6300.00
0.00
640.00
6940.00
Rs:
Rs:
Rs.
971.6
7911.60
79.10
IRR-CAW-7-35 Providing and fixing 20 mm thick 150 mm depth tarfelt expansion joint filler boards for
cement concrete lining of canal including cost of all materials, labour etc., complete with all
leads and lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
particulars
UNIT :
Unit
Quantity
sqm
100.00 Rm
Rate
in Rs.
15.30
0.00
630.00
0.00
Rs:
Description
Unit
Quantity
Nill
0.00
0.00
Description
Carpenter Cl- II
mazdoor
Unit
Quantity
Day
Day
1.00
1.00
Amount
in Rs.
9639.00
9639.00
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
Rate
in Rs.
345.00
295.00
Rs:
Amount
in Rs.
345.00
295.00
640.00
Rs:
Rs:
Rs:
Rs:
9639.00
0.00
640.00
10279.00
Rs:
Rs:
Rs.
1439.06
11718.06
117.20
0.00
6.40
0.14 0.90
7.30
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
100.00 Rm
Rm
(A+B+C+D)/100.00
Rate per
IRR-CAW-7-36 Providing and forming 35 mm wide and 10 mm thick construction / contraction joints
for concrete lining by mastic filler including cost of all materials, labour etc., complete with
all leads and lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
particulars
UNIT :
Unit
Quantity
100.00 Rm
Rate
Amount
203
Asphalt 80/100 Gr
Sand (Screened )
Total cost of Materials
B. MACHINERY:
Sl No
Description
kg
cum
Unit
35.00
0.04
Quantity
Nill
0.00
0.00
Description
Mason Cl- II
mazdoor
Unit
Quantity
Day
Day
0.50
1.00
in Rs.
43.00
606.00
Rs:
in Rs.
1505.00
24.24
1529.24
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
345.00
295.00
Rs:
Amount
in Rs.
172.50
295.00
467.50
Rs:
Rs:
Rs:
Rs:
1529.24
0.00
467.50
1996.74
Rs:
Rs:
Rs.
279.54
2276.28
22.80
4.70
0.14 0.70
5.40
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
100.00 Rm
Rm
(A+B+C+D)/100.00
Rate per
IRR-CAW-7-37 Manufacturing 550 x 550 x 55 mm size PCC lining slabs in M-15 grade ( 28 days cube
compressive strength not less than 15 N /sqmm ) cement concrete using 20 mm down graded
coarse aggregate including cost of all materials, machinery, labour, batching, mixing, laying,
compacting, formwork, finishing, curing etc.,complete with initial lead upto 50 m and all lifts.
( Cement content : 300 kg / cum with super plastcizer (0.4% by wt. of cement),
CA : 0.80 cum, Blending Ratio of CA : 65:35, FA : 0.45cum
equivalent concrete volume: 3.74 cum)
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
Unit
kg
kg
cum
cum
cum
kg
No.
B. MACHINERY:
Sl No
particulars
UNIT :
Description
Unit
Hour
Hour
Hour
Hour
Quantity
1122.00
225 Nos.
Rate
in Rs.
4.00
225.00
4.00
1.94 1210.00
1.05 875.00
1.68 462.00
4.49
80.00
225.00
8.54
Rs:
Quantity
8.00
8.00
0.10
0.10
Rate
in Rs.
53.50
85.30
10.20
85.30
Amount
in Rs.
4488.00
900.00
2353.21
916.30
777.55
359.04
1921.93
11716.03
Amount
in Rs.
428.00
682.40
1.02
8.53
204
Hour
Hour
Description
Unit
C. LABOUR:
Sl No
0.20
0.20
402.50
322.20
Rs:
80.50
64.44
1264.89
90%
Rs:
1138.40
Rate
in Rs.
189.80
96.10
153.10
385.00
370.00
Amount
in Rs.
1518.40
9.61
30.62
770.00
370.00
295.00
295.00
295.00
295.00
295.00
Rs:
885.00
590.00
295.00
295.00
295.00
5058.63
Rs:
4552.77
Rs:
Rs:
Rs:
Rs:
11716.03
1138.40
4552.77
17407.19
Rs:
Rs:
Rs.
2437.01
19844.20
88.20
Quantity
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
225.00 Nos.
each
(A+B+C+D)/225.0
Rate per
IRR-CAW-7-38 Manufacturing 550 x 300 x 55 mm size PCC lug slabs in M-15 grade ( 28 days cube
compressive strength not less than 15 N / sqmm ) cement concrete using 20 mm down graded
coarse aggregate including cost of all materials, machinery, labour, batching, mixing, laying,
compacting, formwork, finishing, curing etc.,complete with initial lead upto 50 m and all lifts.
( Cement content : 300 kg / cum with super plastcizer (0.4% by wt. of cement),
CA : 0.80 cum, Blending Ratio of CA : 65:35, FA : 0.45cum,
equivalent concrete volume: 0.23 cum)
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
particulars
UNIT :
Unit
Quantity
25 Nos.
Rate
in Rs.
4.00
kg
69.00
kg
cum
cum
cum
kg
No.
12.50
4.00
0.12 1210.00
0.06 875.00
0.10 462.00
0.28
80.00
25.00
5.25
Rs:
B. MACHINERY:
Sl No
Description
Unit
Quantity
Rate
in Rs.
Amount
in Rs.
276.00
50.00
144.72
56.35
47.82
22.08
131.33
728.30
Amount
in Rs.
205
428.00
1
2
3
Hour
Hour
Hour
Hour
Hour
Hour
Description
Unit
Hour
Hour
Hour
Day
Day
8.00
0.10
0.20
2.00
1.00
Day
Day
Day
Day
Day
C. LABOUR:
Sl No
1
2
3
4
5
6
8.00
8.00
0.10
0.10
0.20
0.20
53.50
85.30
10.20
85.30
402.50
322.20
Rs:
682.40
1.02
8.53
80.50
64.44
1264.89
10%
Rs:
126.49
Rate
in Rs.
189.80
96.10
153.10
385.00
370.00
Amount
in Rs.
1518.40
9.61
30.62
770.00
370.00
3.00
2.00
1.00
1.00
1.00
295.00
295.00
295.00
295.00
295.00
Rs:
885.00
590.00
295.00
295.00
295.00
5058.63
10%
Rs:
505.86
Rs:
Rs:
Rs:
Rs:
728.30
126.49
505.86
1360.65
Rs:
Rs:
Rs.
190.49
1551.14
62.00
Quantity
20.20
0.14 2.80
23.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
25.00 Nos.
each
(A+B+C+D)/25.0
Rate per
IRR-CAW-7-39 Manufacturing 450 x 300 x 30 mm size PCC lining slabs in M-15 grade ( 28 days cube
compressive strength not less than 15 N / sqmm ) cement concrete using 10 mm down graded
coarse aggregate including cost of all materials, machinery, labour, batching, mixing, laying,
compacting, formwork, finishing, curing etc.,complete with initial lead upto 50 m and all lifts.
( Cement content : 300 kg / cum with super plastcizer (0.4% by wt. of cement),
CA : 0.68 cum, FA : 0.43cum)
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
particulars
UNIT :
Unit
Quantity
kg
270.00
2
3
4
5
kg
cum
cum
kg
No.
112.50
0.61
0.39
1.08
225.00
225 Nos.
Rate
in Rs.
4.00
4.00
875.00
462.00
80.00
3.50
Rs:
Amount
in Rs.
1080.00
450.00
535.50
178.79
86.40
786.98
3117.68
206
B. MACHINERY:
Sl No
1
2
3
Description
Unit
Hour
Hour
Hour
Hour
Hour
Hour
Description
Unit
C. LABOUR:
Sl No
Quantity
8.00
8.00
0.10
0.10
0.20
0.20
90%
Quantity
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
225.00 Nos.
each
(A+B+C+D)/225.0
Rate per
Rate
in Rs.
5.50
0.00
10.20
85.30
402.50
322.20
Rs:
Amount
in Rs.
44.00
0.00
1.02
8.53
80.50
64.44
198.49
Rs:
178.64
Rate
in Rs.
96.10
153.10
385.00
370.00
Amount
in Rs.
9.61
30.62
770.00
370.00
295.00
295.00
295.00
295.00
295.00
Rs:
590.00
590.00
295.00
295.00
295.00
3245.23
Rs:
2920.71
Rs:
Rs:
Rs:
Rs:
3117.68
178.64
2920.71
6217.03
Rs:
Rs:
Rs.
870.38
7087.41
31.50
IRR-CAW-7-40 Manucturing 450 x 150 x 30 mm size PCC lug slabs in M-15 grade ( 28 days cube
compressive strength not less than 15 N / sqmm ) cement concrete using 10 mm down graded
coarse aggregate including cost of all materials, machinery, labour, batching, mixing, laying,
compacting, formwork, finishing, curing etc.,complete with initial lead upto 50 m and all lifts.
( Cement content : 300 kg / cum with super plastcizer (0.4% by wt. of cement),
CA : 0.68 cum, FA : 0.43cum)
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
particulars
UNIT :
Unit
Quantity
25 Nos.
kg
15.00
Rate
in Rs.
4.00
2
3
4
5
kg
cum
cum
kg
No.
7.50
0.03
0.02
0.06
25.00
4.00
875.00
462.00
80.00
1.86
Amount
in Rs.
60.00
30.00
29.75
9.93
4.80
46.59
207
Description
Unit
Hour
Hour
Hour
Hour
Hour
Hour
Description
Unit
C. LABOUR:
Sl No
Quantity
8.00
8.00
0.10
0.10
0.20
0.20
Rs:
181.07
Rate
in Rs.
5.50
0.00
10.20
85.30
402.50
322.20
Rs:
Amount
in Rs.
44.00
0.00
1.02
8.53
80.50
64.44
198.49
Rs:
19.85
Rate
in Rs.
96.10
153.10
385.00
370.00
Amount
in Rs.
9.61
30.62
770.00
370.00
295.00
295.00
295.00
295.00
295.00
Rs:
590.00
590.00
295.00
295.00
295.00
3245.23
Rs:
324.52
Rs:
Rs:
Rs:
Rs:
181.07
19.85
324.52
525.44
Rs:
Rs:
Rs.
73.56
599.00
24.00
10%
Quantity
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
25.00 Nos.
each
(A+B+C+D)/25.0
Rate per
IRR-CAW-7-41 Manufacturing 600 x 300 x 100mm size PCC lining slabs in M-15 grade (28 days cube
compressive strength not less than 15 N/Sqmm) cement concrete using 20mm down
grades coarse aggregate including cost of all materials, machinery, labour, batching,
mixing, laying, compacting, formwork, finishing, curing etc., complete with initial lead upto 50 m
and all lifts.
( Cement content : 300 kg / cum with super plastcizer (0.4% by wt. of cement),
CA : 0.80 cum, FA : 0.45cum, Blending Ratio of CA--65:35)
DATA:
RATE ANALYSIS
UNIT:
225
Nos.
A. MATERIALS :
Sl. No
1
2
3
Particulars
Cement for mix
Cement for incidentals @ 0.5kg/slab
Coarse aggregate 20 mm below
Unit
Kg
Kg
Cum
Quantity
Rate
Amount in
Rs.
in Rs.
1215
4860.00
4.00
112.5
450.00
4.00
2.11 1210.00
2548.26
208
4
5
6
7
Cum
Coarse aggregate 10 mm below
Cum
Fine aggregate (Un-Screened)
kg
Super Plasticizer
No.
Use rate of moulds for 250 uses
Total Cost of Materials Rs.
1.13
1.82
4.86
225
875.00
462.00
80.00
1.23
992.25
842.00
388.80
276.75
10358.06
B. MACHINERY :
Sl. No
1
2
3
Particulars
Unit
Hour
Diesel mixer 300/200
Hour
Fuel/Energy charges
Hour
5 hp pump (diesel)
Hour
Fuel/Energy charges
Hour
Water tanker 8000 ltr
Hour
Fuel/Energy charges
Total hire charges of Machinery
Aportioned hire charges of
machinery @ 90% for lining slab
Rs.
C. LABOUR :
Sl. No
Particulars
Unit
Quantity
8
8
0.1
0.1
0.2
0.2
Rs.
90%
Quantity
1
2
3
4
5
Hour
0.1
Crew for Pump
Hour
0.2
Crew for water tanker
Day
2
Mason Class-I
Day
1
Class II Mason
Mazdoor
Day
2
For batching materials/laying
2
For demoulding/cleaning/oiling
1
For shifting slabs to curing pond
1
For stacking after curing
Day
1
For cleaning & miscellaneous
Total Cost of Labour Rs.
Aportioned cost of labour for lining
90%
slabs Rs.
labour component/unit qty
12.90
Add contractor's profit and overhead charges
0.14 1.80
labour component/unit qty (including contractor's profit)
14.70
ABSTRACT :
A. Cost of Materials
B. Hire Charges of machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
225.00 Nos.
each
(A+B+C+D)/225.0
Rate per
Rate
Amount in
Rs.
in Rs.
428.00
53.50
682.40
85.30
1.02
10.20
8.53
85.30
80.50
402.50
64.44
322.20
1264.89
1138.40
Rate
Amount in
Rs.
in Rs.
9.61
96.10
30.62
153.10
770.00
385.00
345.00
345.00
295.00
295.00
295.00
295.00
295.00
590.00
590.00
295.00
295.00
295.00
3220.23
2898.21
Rs. 10358.055
Rs.
1138.40
Rs.
2898.21
Rs:
14394.66
Rs:
Rs:
Rs.
2015.25
16409.91
72.90
IRR-CAW-7-42 Manucturing 400 x 400 x 30 mm size PCC lining slabs in M-15 grade ( 28 days cube
compressive strength not less than 15 N / sqmm )cement concrete using 10 mm down graded
coarse aggregate including cost of all materials, machinery, labour, batching, mixing, laying,
compacting, formwork, finishing, curing etc.,complete with initial lead upto 50 m and all lifts.
( Cement content : 300 kg / cum with super plastcizer (0.4% by wt. of cement),
CA : 0.68 cum, FA : 0.43cum)
DATA:
RATE ANALYSIS
UNIT :
225 Nos.
A. MATERIALS:
209
Sl No
particulars
Unit
Quantity
kg
324.00
2
3
4
5
kg
cum
cum
kg
No.
112.50
0.73
0.46
1.30
225.00
B. MACHINERY:
Sl No
1
2
3
C. LABOUR:
Sl No
Description
Unit
Hour
Hour
Hour
Hour
Hour
Hour
Description
Unit
Quantity
8.00
8.00
0.10
0.10
0.20
0.20
90%
Quantity
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
225.00 Nos.
each
(A+B+C+D)/225.0
Rate per
Rate
in Rs.
4.00
Amount
in Rs.
1296.00
450.00
4.00
875.00
462.00
80.00
3.52
Rs:
642.60
214.55
103.68
793.05
3499.89
Rate
in Rs.
5.50
0.00
10.20
85.30
402.50
322.20
Rs:
Amount
in Rs.
44.00
0.00
1.02
8.53
80.50
64.44
198.49
Rs:
178.64
Rate
in Rs.
96.10
153.10
385.00
370.00
Amount
in Rs.
9.61
30.62
770.00
370.00
295.00
295.00
295.00
295.00
295.00
Rs:
590.00
590.00
295.00
295.00
295.00
3245.23
Rs:
2920.71
Rs:
Rs:
Rs:
Rs:
3499.89
178.64
2920.71
6599.23
Rs:
Rs:
Rs.
923.89
7523.12
33.40
IRR-CAW-7-43 Manufacturing 400 x 150 x 30 mm size PCC lug slabs in M-15 grade ( 28 days cube
compressive strength not less than 15 N /sqmm ) cement concrete using 10 mm down graded
coarse aggregate including cost of all materials, machinery, labour, batching, mixing, laying,
compacting, formwork, finishing, curing etc.,complete with initial lead upto 50 m and all lifts.
( Cement content : 300 kg / cum with super plastcizer (0.4% by wt. of cement),
CA : 0.68 cum, FA : 0.43cum)
DATA:
RATE ANALYSIS
UNIT :
25 Nos.
210
A. MATERIALS:
Sl No
particulars
Unit
Quantity
kg
13.50
2
3
4
5
kg
cum
cum
kg
No.
7.50
0.03
0.02
0.05
25.00
B. MACHINERY:
Sl No
1
2
3
C. LABOUR:
Sl No
Description
Unit
Hour
Hour
Hour
Hour
Hour
Hour
Description
Unit
Quantity
8.00
8.00
0.10
0.10
0.20
0.20
10%
Quantity
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
25.00 Nos.
each
(A+B+C+D)/25.0
Rate per
Rate
in Rs.
4.00
Amount
in Rs.
54.00
30.00
4.00
875.00
462.00
80.00
1.83
Rs:
26.78
8.94
4.32
45.74
169.78
Rate
in Rs.
5.50
0.00
10.20
85.30
402.50
322.20
Rs:
Amount
in Rs.
44.00
0.00
1.02
8.53
80.50
64.44
198.49
Rs:
19.85
Rate
in Rs.
96.10
153.10
385.00
370.00
Amount
in Rs.
9.61
30.62
770.00
370.00
295.00
295.00
295.00
295.00
295.00
Rs:
590.00
590.00
295.00
295.00
295.00
3245.23
Rs:
324.52
Rs:
Rs:
Rs:
Rs:
169.78
19.85
324.52
514.15
Rs:
Rs:
Rs.
71.98
586.13
23.40
IRR-CAW-7-44 Providing and laying uncoursed rubble stone masonry in CM 1 : 5 proportion for canal side
lining using stones and chips from approved quarry including cost of all materials,
machinery, labour, forming weep holes at specified intervals, finishing, curing etc., complete
with initial lead upto 50 m and all lifts.
(Thickness of the masonry assumed: 0.3 m, rubble stones : 0.96 cum, Stone Chips : 0.15cum,
Through Stones 20 x 20 x 30cm : 1/sqm)
DATA:
RATE ANALYSIS
UNIT :
10.00 cum
211
A. MATERIALS:
Sl No
particulars
Unit
Quantity
1
2
Cement 43 Gr
Sand (Screened )
kg
cum
1152.00
4.00
3
4
5
cum
Nos
cum
9.60
32.00
1.50
B. MACHINERY:
Sl No
1
C. LABOUR:
Sl No
Description
Unit
5 hp pump ( diesel )
Fuel / Energy charges
Total hire charges of Machinery
Hour
Hour
Description
Unit
Quantity
4.00
4.00
Quantity
Operator pump
Hour
4.00
work inspector
Day
1.00
Mason Class I
Day
2.00
Mason Class II
Day
2.00
mazdoor
Day
8.00
Cartman with Double Bullock cart for
6
Day
1.00
water
Total cost of Labour
labour component/unit qty
496.90
Add contractor's profit and overhead charges
0.14 69.60
labour component/unit qty (including contractor's profit)
566.50
1
2
3
4
5
Rate
in Rs.
4.00
606.00
Amount
in Rs.
4608.00
2424.00
3052.80
318.00
23.00
340.00
Rs:
736.00
510.00
11330.80
Rate
in Rs.
10.20
85.30
Rs:
Amount
in Rs.
40.80
341.20
382.00
Rate
in Rs.
96.10
370.00
385.00
345.00
295.00
Amount
in Rs.
384.40
370.00
770.00
690.00
2360.00
395.00
395.00
Rs:
4969.40
Rs:
Rs:
Rs:
Rs:
11330.80
382.00
4969.40
16682.20
Rs:
Rs:
Rs.
2335.51
19017.71
1901.80
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
10.00 cum
cum
(A+B+C+D)/10.0
Rate per
IRR-CAW-7-45 Providing and laying uncoursed rubble stone masonry in CM 1:5 proportion for canal side
lining using stones from approved quarry including cost of all materials, machinery,
labour, forming weep holes at specified intervals, finishing, curing etc., complete
with initial lead upto 50m and all lifts.(without pin headers) : 1.1 cum)
(Thickness of the Masonry assumed: 0.3 m , rubble stones
DATA:
RATE ANALYSIS
UNIT:
10
Cum
A.
MATERIALS
:
Sl. No
1
2
3
Particulars
Cement 43 Gr
Sand (Screened)
Uncoursed rubble stones at quarry
Unit
Kg
Cum
Cum
Quantity
Rate
Amount in
Rs.
in Rs.
979.2
3916.80
4.00
3.4 606.00
2060.40
11
3498.00
318.00
9475.2
212
B. MACHINERY :
Sl. No
1
2
Particulars
Unit
Quantity
Rate
Amount in
Rs.
in Rs.
8
5.50
44.00
4
40.80
10.20
5
426.50
85.30
511.30
Rs.
C. LABOUR :
Sl. No
Particulars
Unit
Quantity
1
2
3
4
5
Operator pump
Hour
4
Mason Class I
Day
13
Mason Class II
Day
6
Mazdoor
Day
29
Cartman with Double Bullock cart for
Day
1
water
Total Cost of Labour Rs.
labour component/unit qty
1640.90
Add contractor's profit and overhead charges
0.14 229.70
labour component/unit qty (including contractor's profit)
1870.60
ABSTRACT :
A. Cost of Materials
B. Hire Charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
10.00 Cum
Cum
(A+B+C+D)/10.0
Rate per
Rate
Amount in
Rs.
in Rs.
384.40
96.10
5005.00
385.00
2070.00
345.00
295.00
8555.00
395.00
395.00
16409.40
Rs.
Rs.
Rs.
Rs:
9475.2
511.3
16409.40
26395.90
Rs:
Rs:
Rs.
3695.43
30091.33
3009.10
IRR-CAW-7-46 Providing and laying uncoursed rubble stone masonry in CM 1 : 5 proportion for canal side
lining using stones and chips from canal excavation including cost of all materials,
machinery, labour, forming weep holes at specified interval, finishing, curing etc., complete
with initial lead upto 50 m and all lifts.
( rubble stones : 0.96 cum, Stone Chips : 0.15cum, Through Stones 20 x 20 x 30cm : 1/sqm)
Note:
Stones and chips will be issued from dump yard at specified issue rate.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
particulars
Unit
Cement 43 Gr
Sand (Screened )
Uncoursed rubble at dump yard
Through stones 20x20x30 cm
Stone chips at dump yard
Total cost of Materials
kg
cum
cum
Nos
cum
B. MACHINERY:
Sl No
1
C. LABOUR:
Sl No
UNIT :
Description
Unit
5 hp pump ( diesel )
Fuel / Energy charges
Total hire charges of Machinery
Hour
Hour
Description
Unit
Quantity
1144.00
4.00
9.60
32.00
1.50
Quantity
4.00
4.00
Quantity
10.00 cum
Rate
in Rs.
4.00
606.00
155.00
23.00
175.00
Rs:
Amount
in Rs.
4576.00
2424.00
1488.00
736.00
262.50
9486.50
Rate
in Rs.
10.20
85.30
Rs:
Amount
in Rs.
40.80
341.20
382.00
Rate
Amount
213
Operator pump
Hour
4.00
work inspector
Day
1.00
Mason Class I
Day
2.00
Mason Class II
Day
2.00
Crowbarman
Day
1.00
mazdoor
Day
9.00
Cartman with Double Bullock cart for
7
Day
1.00
water
Total cost of Labour
labour component/unit qty
560.90
Add contractor's profit and overhead charges
0.14 78.50
labour component/unit qty (including contractor's profit)
639.40
1
2
3
4
5
6
in Rs.
96.10
370.00
385.00
345.00
345.00
295.00
in Rs.
384.40
370.00
770.00
690.00
345.00
2655.00
395.00
395.00
Rs:
5609.40
Rs:
Rs:
Rs:
Rs:
9486.50
382.00
5609.40
15477.90
Rs:
Rs:
Rs.
2166.91
17644.81
1764.50
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
10.00 cum
cum
(A+B+C+D)/10.0
Rate per
IRR-CAW-7-47 Providing and laying uncoursed rubble stone masonry in CM 1:5 proportion for canal side lining
using stones from canal excavation including cost of all materials, machinery, labour, forming weep holes at
specified intervals, finishing, curing etc., complete with initial lead upto 50m and all lifts.
( rubble stones : 1.1cum, cement : 98kg, sand 0.34 cum)
DATA:
RATE ANALYSIS
UNIT:
10
Cum
A.
MATERIALS
:
Sl. No
1
2
3
Particulars
Unit
Quantity
Rate
Amount in
Rs.
in Rs.
980
3920.00
4.00
3.4 606.00
2060.40
11 155.00
1705.00
7685.4
Cement 43 Gr
Kg
Sand (Screened)
Cum
Uncoursed rubble at dump yard
Cum
Total Cost of Materials Rs.
B. MACHINERY :
Sl. No
1
2
Particulars
Unit
Quantity
Rs.
Rate
Amount in
Rs.
in Rs.
8
5.50
44.00
4
40.80
10.20
5
426.50
85.30
511.30
C. LABOUR :
Sl. No
1
2
3
4
5
Particulars
Unit
Quantity
Operator pump
Hour
4
Mason Class I
Day
13
Mason Class II
Day
6
Mazdoor
Day
29
Cartman with double bullock cart
Day
1
Total Cost of Labour Rs.
labour component/unit qty
1640.90
Add contractor's profit and overhead charges
0.14 229.70
labour component/unit qty (including contractor's profit)
1870.60
Rate
Amount in
Rs.
in Rs.
384.40
96.10
5005.00
385.00
2070.00
345.00
295.00
8555.00
395.00
395.00
16409.40
214
ABSTRACT :
A. Cost of Materials
B. Hire Charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
10.00 Cum
Cum
(A+B+C+D)/10.0
Rate per
Rs.
Rs.
Rs.
Rs:
7685.4
511.3
16409.40
24606.10
Rs:
Rs:
Rs.
3444.85
28050.95
2805.10
IRR-CAW-8
ROCK PITCHING:
IRR-CAW-8-1
Providing and constructing 25 cm thick dry rubble stone pitching with pin headers at 2 per
sqm including cost of all materials, labour, hand packing, finishing etc., complete with initial
lead upto 50 m and all lifts.
( rubble stones : 0.23 cum/sqm, Stone Chips : 0.0375cum/sqm, Pin Headers 30cm : 2/sqm)
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
particulars
UNIT :
Unit
cum
Quantity
23.00
100.00 sqm
Rate
in Rs.
Amount
in Rs.
7314.00
318.00
4600.00
2
3
B. MACHINERY:
Sl No
Description
Nos
cum
Unit
200.00
3.75
Quantity
Nill
0.00
0.00
Description
work inspector
Mason Class II
mazdoor
Unit
Quantity
Day
Day
Day
1.00
5.00
6.00
1275.00
13189.00
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
370.00
345.00
295.00
Rs:
Amount
in Rs.
370.00
1725.00
1770.00
3865.00
Rs:
Rs:
Rs:
Rs:
13189.00
0.00
3865.00
17054.00
Rs:
Rs:
Rs.
2387.56
19441.56
194.40
38.70
0.14 5.40
44.10
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
100.00 sqm
sqm
(A+B+C+D)/100.0
Rate per
Note:
23.00
340.00
Rs:
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
particulars
UNIT :
Unit
Quantity
100.00 sqm
Rate
Amount
215
Murum
cum
18.00
0.00
Description
Unit
Quantity
Nill
0.00
0.00
Description
mazdoor
Unit
Quantity
Day
4.00
in Rs.
107.00
0.00
Rs:
in Rs.
1926.00
0.00
1926.00
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
295.00
Rs:
Amount
in Rs.
1180.00
1180.00
Rs:
Rs:
Rs:
Rs:
1926.00
0.00
1180.00
3106.00
Rs:
Rs:
Rs.
434.84
3540.84
35.40
11.80
0.14 1.70
13.50
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
100.00 sqm
sqm
(A+B+C+D)/100.0
Rate per
IRR-CAW-8-1-A Providing and constructing 22.5 cm thick dry rubble stone pitching with pin headers at 2 per
(New Item4 - 201112)
sqm including cost of all materials, labour, hand packing, finishing etc., complete with initial
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
particulars
UNIT :
Unit
cum
Quantity
20.70
100.00 sqm
Rate
in Rs.
Amount
in Rs.
6582.60
318.00
4600.00
2
3
B. MACHINERY:
Sl No
Description
Nos
cum
Unit
200.00
3.375
Quantity
Nill
0.00
0.00
Description
work inspector
Mason Class II
mazdoor
Unit
Quantity
Day
Day
Day
1.00
5.00
6.00
23.00
340.00
Rs:
1147.50
12330.10
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
370.00
345.00
295.00
Rs:
Amount
in Rs.
370.00
1725.00
1770.00
3865.00
38.70
216
0.14 5.40
44.10
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
100.00 sqm
sqm
(A+B+C+D)/100.0
Rate per
IRR-CAW-8-2
Rs:
Rs:
Rs:
Rs:
12330.10
0.00
3865.00
16195.10
Rs:
Rs:
Rs.
2267.31
18462.41
184.60
Providing and constructing 25 cm thick dry rubble stone pitching including cost of all materials, labour,
hand packing, finishing etc., complete
( rubble stones : 0.275 cum/sqm)
DATA:
RATE ANALYSIS
UNIT:
100
Sqm.
A. MATERIALS :
Sl. No
1
Particulars
Uncoursed rubble stones at quarry
Unit
Quantity
Cum
Rate
in Rs.
Amount in
Rs.
8745.00
27.50
318.00
8745
B. MACHINERY :
Sl. No
Particulars
Nil
Unit
Quantity
0
0
Rate
in Rs.
Amount in
Rs.
0
0
Rs.
C. LABOUR :
Sl. No
Particulars
Unit
Quantity
Rate
Amount in
Rs.
in Rs.
1
Mason Class II
Day
5.50 345.00
1897.50
2
Day
24.75 295.00
7301.25
Mazdoor
Total Cost of Labour Rs.
9198.75
labour component/unit qty
92.00
Add contractor's profit and overhead charges
0.14 12.90
labour component/unit qty (including contractor's profit)
104.90
ABSTRACT :
A. Cost of Materials
B. Hire Charges of Machinery
C. Cost of Labour
Rs.
Rs.
Rs.
Rs:
8745
0
9198.75
17943.75
2512.13
20455.88
204.60
Total
35.40
IRR-CAW-8-2-A Providing and constructing 225 mm thick dry rubble stone pitching including cost of all materials, labour,
(New Item5 - 2011hand packing, finishing etc., complete
12)
217
RATE ANALYSIS
DATA:
UNIT:
100
Sqm.
A. MATERIALS :
Sl. No
1
2
Particulars
Unit
Quantity
Rate
Amount in
Rs.
in Rs.
24.75 144.00
3564.00
3.40 340.00
1156.00
4720
Sl. No
Particulars
Nil
Unit
Quantity
Rate
in Rs.
0
0
Amount in
Rs.
0
0
Rs.
C. LABOUR :
Sl. No
Particulars
Unit
Quantity
Rate
Amount in
Rs.
in Rs.
1
Mason Class II
Day
4.95 345.00
1707.75
2
Day
22.28 295.00
6571.13
Mazdoor
Total Cost of Labour Rs.
8278.88
labour component/unit qty
82.80
Add contractor's profit and overhead charges
0.14 11.60
labour component/unit qty (including contractor's profit)
94.40
ABSTRACT :
A. Cost of Materials
B. Hire Charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
100.00 Sqm.
Sqm.
(A+B+C+D)/100.0
Rate per
IRR-CAW-8-3
Rs.
Rs.
Rs.
Rs:
4720
0
8278.88
12998.88
Rs:
Rs:
Rs.
1819.84
14818.72
148.20
Providing and constructing 30 cm thick dry rubble stone pitching with pin headers at 2 per
sqm including cost of all materials, labour, hand packing, finishing etc., complete with initial
lead upto 50 m and all lifts.
( rubble stones : 0.275 cum/sqm, Stone Chips : 0.045cum/sqm, Pin Headers 30cm : 2/sqm)
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
particulars
UNIT :
Unit
cum
Quantity
27.50
100.00 sqm
Rate
in Rs.
Amount
in Rs.
8745.00
318.00
4600.00
2
3
B. MACHINERY:
Sl No
1
Description
Nill
Total hire charges of Machinery
Nos
cum
Unit
200.00
4.50
Quantity
0.00
0.00
23.00
340.00
Rs:
Rate
in Rs.
0.00
0.00
Rs:
1530.00
14875.00
Amount
in Rs.
0.00
218
C. LABOUR:
Sl No
1
2
3
Description
work inspector
Mason Class II
mazdoor
Unit
Quantity
Day
Day
Day
1.00
5.00
6.00
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
100.00 sqm
sqm
(A+B+C+D)/100.0
Rate per
If 15 cm thick murum bed is to be
NOTE:
provided below pitching add
( As per rate analysis under item IRRCAW-8-1- Note )
DATA:
Amount
in Rs.
370.00
1725.00
1770.00
3865.00
Rs:
Rs:
Rs:
Rs:
14875.00
0.00
3865.00
18740.00
Rs:
Rs:
Rs.
2623.6
21363.60
213.60
38.70
0.14 5.40
44.10
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
IRR-CAW-8-4
Rate
in Rs.
370.00
345.00
295.00
Rs:
35.40
RATE ANALYSIS
A. MATERIALS :
Sl No
Particulars
UNIT :
Unit
Cum
Quantity
33.00
100.00 sqm
Rate
in Rs
Amount
in Rs
10494.00
318.00
10494.00
B.MACHINERY :
Sl No
Description
Nill
Unit
Quantity
0.00
0.00
Rate
in Rs
Amount
in Rs
0.00
0.00
0.00
C.LABOUR :
Sl No
Description
1
2
Unit
Quantity
Mason Class II
Day
6.60
Mazdoor
Day
29.70
Total cost of labour
Rs :
labour component/unit qty
110.40
Add contractor's profit and overhead charges
0.14 15.50
labour component/unit qty (including contractor's profit)
125.90
ABSTRACT
A.Cost of Materials including ryolty charges
Rate
in Rs
345.00
295.00
Amount
in Rs
2277.00
8761.50
11038.50
Rs:
10494.00
219
IRR-CAW-8-5
Rs:
Rs:
Rs:
0.00
11038.50
21532.50
Rs:
Rs:
Rs.
3014.55
24547.05
245.50
Rs
35.40
Providing and constructing 45 cm thick dry rubble stone pitching with pin headers at 2 per
sqm including cost of all materials, labour, hand packing, finishing etc., complete with initial
lead upto 50 m and all lifts.
( rubble stones : 0.40 cum/sqm, Stone Chips : 0.0675cum/sqm, Pin Headers 45cm : 2/sqm)
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
particulars
UNIT :
Unit
cum
Quantity
40.00
100.00 sqm
Rate
in Rs.
Amount
in Rs.
12720.00
318.00
7800.00
2
3
B. MACHINERY:
Sl No
Description
Nos
cum
Unit
200.00
6.75
Quantity
Nill
0.00
0.00
Description
work inspector
Mason Class II
mazdoor
Unit
Quantity
Day
Day
Day
1.00
7.00
9.00
2295.00
22815.00
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
Rate
in Rs.
370.00
345.00
295.00
Rs:
Amount
in Rs.
370.00
2415.00
2655.00
5440.00
Rs:
Rs:
Rs:
Rs:
22815.00
0.00
5440.00
28255.00
Rs:
Rs:
Rs.
3955.7
32210.70
322.10
0.00
54.40
0.14 7.60
62.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
100.00 sqm
sqm
(A+B+C+D)/100.0
Rate per
If 15 cm thick murum bed is to be
NOTE:
provided below pitching add
( As per rate analysis under item IRRCAW-8-1 - Note )
IRR-CAW-8-6
39.00
340.00
Rs:
35.40
220
DATA:
RATE ANALYSIS
A. MATERIALS :
Sl No
UNIT :
Particulars
Unit
Cum
Quantity
49.50
100.00 sqm
Rate
in Rs
Amount
in Rs
15741.00
318.00
15741.00
B.MACHINERY :
Sl No
Description
Nill
Unit
Quantity
0.00
0.00
Rate
in Rs
Amount
in Rs
0.00
0.00
0.00
0.00
0.00
C.LABOUR :
Sl No
Description
Unit
Quantity
1
2
Mason Class II
Day
9.90
Mazdoor
Day
44.55
Total cost of labour
Rs :
labour component/unit qty
165.60
Add contractor's profit and overhead charges
0.14 23.20
labour component/unit qty (including contractor's profit)
188.80
ABSTRACT
A.Cost of Materials including ryolty charges
B. Hire charges of Machinery
C.Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
100.00 sqm
sqm
(A+B+C+D)/100.0
Rate per
If 15 cm thick murum bed is to be
NOTE:
provided below pitching
Add ( As per rate analysis under item
IRR-CAW-8-1 - Note)
IRR-CAW-8-7
Rate
in Rs
Amount
in Rs
345.00
295.00
3415.50
13142.25
16557.75
Rs:
Rs:
Rs:
Rs:
15741.00
0.00
16557.75
32298.75
Rs:
Rs:
Rs.
4521.83
36820.58
368.20
Rs
35.40
Providing and constructing 30 cm thick rubble stone pitching set in CM 1: 5 proportion with
pin headers at 2 per sqm in including cost of all materials, labour, packing chips and mortar,
finishing, curing etc., complete with initial lead upto 50 m and all lifts.
( rubble stones : 0.275 cum/sqm, Stone Chips : 0.045cum/sqm, Pin Headers 30cm : 2/sqm)
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
particulars
UNIT :
Unit
cum
Quantity
27.50
100.00 sqm
Rate
in Rs.
Amount
in Rs.
8745.00
318.00
4600.00
2
3
4
Nos
cum
kg
200.00
4.50
3000.00
23.00
340.00
4.00
1530.00
12000.00
221
Sand (Screened )
Total cost of Materials
B. MACHINERY:
Sl No
1
Description
cum
Unit
5 hp pump ( diesel )
Fuel / Energy charges
Total hire charges of Machinery
C. LABOUR:
Sl No
Description
10.50
Quantity
2.00
2.00
Unit
Quantity
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
100.00 sqm
sqm
(A+B+C+D)/100.0
Rate per
If 15 cm thick murum bed is to be
NOTE:
provided below pitching add
( As per rate analysis under item IRRCAW-8-1 - Note )
IRR-CAW-8-8
606.00
Rs:
6363.00
33238.00
Rate
in Rs.
10.20
85.30
Rs:
Amount
in Rs.
20.40
170.60
191.00
Rate
in Rs.
96.10
370.00
345.00
295.00
395.00
Rs:
Amount
in Rs.
192.20
370.00
1725.00
3540.00
790.00
6617.20
Rs:
Rs:
Rs:
Rs:
33238.00
191.00
6617.20
40046.20
Rs:
Rs:
Rs.
5606.47
45652.67
456.50
35.40
Providing and Constructing 30 cm thick rubble stone pitching set in CM 1:5 Proportion
including cost of all materials,labour, packing chips and mortar ,finishing etc.,complete
( rubble stones : 0.33 cum/sqm )
DATA:
RATE ANALYSIS
UNIT :
100.00 Sqm
A. MATERIALS :
Sl No
Particulars
Unit
Quantity
Cum
33.00
2
3
Cement
Sand (Screened)
Total Cost of materials
Kg
Cum
3232.00
11.22
Rate
in Rs
Amount
in Rs
10494.00
318.00
4.00
606.00
Rs :
12928.00
6799.32
30221.32
B.MACHINERY :
Sl No
Description
Nill
Total hire charges of machinery
Rs :
Unit
Quantity
0.00
Rate
in Rs
0.00
Amount
in Rs
0.00
0.00
C.LABOUR :
222
Sl No
Description
Unit
Quantity
1
2
3
Mason Class I
Day
0.54
Mason Class II
Day
1.26
Mazdoor
Day
2.80
Total cost of labour
Rs :
labour component/unit qty
14.70
Add contractor's profit and overhead charges
0.14 2.10
labour component/unit qty (including contractor's profit)
16.80
ABSTRACT
A.Cost of Materials
B. Hire charges of Machinery
C.Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
100.00 Sqm
Sqm
(A+B+C+D)/100.0
Rate per
If 15 cm thick murum bed is to be
NOTE:
provided below pitching
Add ( As per rate analysis under item
IRR-CAW-8-1 - Note)
IRR-CAW-8-9
Rate
in Rs
Amount
in Rs
207.90
434.70
826.00
385.00
345.00
295.00
1468.60
Rs:
Rs:
Rs:
Rs:
30221.32
0.00
1468.60
31689.92
Rs:
Rs:
Rs.
4436.59
36126.51
361.30
Rs
35.40
Providing and constructing 30 cm thick dry khandki stone pitching using 20 to 25 cm size
khandki stones with pin headers at 2 per sqm including cost of all materials, labour, hand
packing, finishing etc., complete with initial lead upto 50 m and all lifts.
( Khandki stones 20- 25 cm height : 1200 Nos/sqm, Stone Chips : 0.045cum/sqm,
Pin Headers 30cm : 2/sqm)
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
particulars
UNIT :
Unit
Quantity
Nos
1200.00
2
3
Nos
cum
200.00
4.50
B. MACHINERY:
Sl No
Description
Unit
Quantity
Nil
0.00
0.00
Description
work inspector
Mason Class II
mazdoor
Unit
Quantity
Day
Day
Day
Total cost of Labour
1.00
5.00
6.00
100.00 sqm
Rate
in Rs.
13.00
Amount
in Rs.
15600.00
4600.00
23.00
340.00
Rs:
1530.00
21730.00
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
370.00
345.00
295.00
Rs:
Amount
in Rs.
370.00
1725.00
1770.00
3865.00
Rs:
Rs:
Rs:
21730.00
0.00
3865.00
38.70
0.14 5.40
44.10
223
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
100.00 sqm
sqm
(A+B+C+D)/100.0
Rate per
If 15 cm thick murum bed is to be
NOTE:
provided below pitching add
( As per rate analysis under item IRRCAW-8-1 - Note )
Rs:
25595.00
Rs:
Rs:
Rs.
3583.3
29178.30
291.80
35.40
IRR-CAW-8-10 Providing and constructing 45 cm thick dry khandki stone pitching using 25 to 30 cm size
khandki stones with pin headers at 2 per sqm including cost of all materials, labour, hand
packing, finishing etc., complete with initial lead upto 50 m and all lifts.
( Khandki stones 25- 30 cm height : 1200 Nos/sqm, Stone Chips : 0.0675cum/sqm,
Pin Headers 45cm : 2/sqm)
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
UNIT :
particulars
Unit
Nos
Nos
cum
B. MACHINERY:
Sl No
Description
Unit
Quantity
730.00
200.00
6.75
Quantity
Nil
0.00
0.00
Description
work inspector
Mason Class II
mazdoor
Unit
Quantity
Day
Day
Day
1.00
7.00
9.00
100.00 sqm
Rate
in Rs.
16.00
39.00
340.00
Rs:
Amount
in Rs.
11680.00
7800.00
2295.00
21775.00
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
370.00
345.00
295.00
Rs:
Amount
in Rs.
370.00
2415.00
2655.00
5440.00
Rs:
Rs:
Rs:
Rs:
21775.00
0.00
5440.00
27215.00
Rs:
Rs:
Rs.
3810.1
31025.10
310.30
54.40
0.14 7.60
62.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
100.00 sqm
sqm
(A+B+C+D)/100.0
Rate per
If 15 cm thick murum bed is to be
NOTE:
provided below pitching add
( As per rate analysis under item IRRCAW-8-1 - Note )
35.40
IRR-CAW-8-11 Providing and constructing 30 cm thick khandki stone pitching using 20 to 25 cm size
khandki stones with pin headers at 2 per sqm set in CM 1 : 5 proportion with pointing joints in
CM 1:3 proportion including cost of all materials, labour, packing chips and mortar, finishing,
224
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
particulars
Unit
Nos
Nos
cum
kg
cum
B. MACHINERY:
Sl No
1
UNIT :
Description
Unit
5 hp diesel pump
Fuel / Energy charges
Total hire charges of Machinery
Hour
Hour
Description
Unit
C. LABOUR:
Sl No
Quantity
1200.00
200.00
4.50
2902.00
9.67
Quantity
2.00
2.00
Quantity
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
100.00 sqm
sqm
(A+B+C+D)/100.0
Rate per
If 15 cm thick murum bed is to be
NOTE:
provided below pitching add
( As per rate analysis under item IRRCAW-8-1 - Note )
100.00 sqm
Rate
in Rs.
13.00
23.00
340.00
4.00
606.00
Rs:
Amount
in Rs.
15600.00
4600.00
1530.00
11608.00
5860.02
39198.02
Rate
in Rs.
10.20
85.30
Rs:
Amount
in Rs.
20.40
170.60
191.00
Rate
in Rs.
96.10
370.00
395.00
345.00
295.00
Rs:
Amount
in Rs.
192.20
370.00
790.00
1725.00
3245.00
6322.20
Rs:
Rs:
Rs:
Rs:
39198.02
191.00
6322.20
45711.22
Rs:
Rs:
Rs.
6399.57
52110.79
521.10
35.40
IRR-CAW-8-12 Providing and constructing 45 cm thick khandki stone pitching using 25 to 30 cm stones
with pin headers at 2 per sqm set in CM 1 : 5 proportion with pointing joints in CM 1 : 3
proportion including cost of all materials, labour, packing chips and mortar, finishing, curing
etc., complete with initial lead upto 50 m and all lifts.
( Khandki stones 25- 30 cm height : 730 Nos/sqm, Stone Chips : 0.0675cum/sqm,
Pin Headers 45cm : 2/sqm)
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
particulars
UNIT :
Unit
Nos
Nos
Quantity
730.00
200.00
100.00 sqm
Rate
in Rs.
16.00
39.00
Amount
in Rs.
11680.00
7800.00
225
3
4
5
B. MACHINERY:
Sl No
1
cum
kg
cum
Description
Unit
5 hp diesel pump
Fuel / Energy charges
Total hire charges of Machinery
Hour
Hour
Description
Unit
C. LABOUR:
Sl No
6.75
4050.00
13.99
Quantity
4.00
4.00
Quantity
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
100.00 sqm
sqm
(A+B+C+D)/100.0
Rate per
If 15 cm thick murum bed is to be
NOTE:
provided below pitching add
( As per rate analysis under item IRRCAW-8-1 - Note )
340.00
4.00
606.00
Rs:
2295.00
16200.00
8477.94
46452.94
Rate
in Rs.
10.20
85.30
Rs:
Amount
in Rs.
40.80
341.20
382.00
Rate
in Rs.
96.10
370.00
395.00
345.00
295.00
Rs:
Amount
in Rs.
384.40
370.00
790.00
2415.00
4720.00
8679.40
Rs:
Rs:
Rs:
Rs:
46452.94
382.00
8679.40
55514.34
Rs:
Rs:
Rs.
7772.01
63286.35
632.90
35.40
IRR-CAW-8-13 Providing 10 cm thick approved type grass turfing to the side slopes of canal including cost of
all materials, labour, watering for minimum 15 days etc.,complete with lead 50 m and all lifts.
(FA : 2 cum/sqm)
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
particulars
Turfing sods
Sand for filling
UNIT :
Unit
sqm
cum
Quantity
100.00
2.00
Description
Unit
Nill
Quantity
0.00
0.00
Description
work inspector
Unit
Day
Quantity
0.10
100.00 sqm
Rate
in Rs.
28.00
342.00
Rs:
Amount
in Rs.
2800.00
684.00
3484.00
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
370.00
Amount
in Rs.
37.00
226
2
3
395.00
295.00
Rs:
790.00
4130.00
4957.00
Rs:
Rs:
Rs:
Rs:
3484.00
0.00
4957.00
8441.00
Rs:
Rs:
Rs.
1181.74
9622.74
96.20
IRR-CAW-8-14 Providing 10 cm Thick approved type gross turfing to the side slopes of canal including cost of
all materials ,labour,watering for minimum 15 days etc.,,complete.
with initial lead upto 50 m and all lifts ( WITHOUT USING SAND)
DATA:
RATE ANALYSIS
UNIT :
100.00 Sqm
A. MATERIALS :
Sl No
1
Particulars
Turfing Sods
Total Cost of materials
Unit
Sqm
Quantity
100.00
Rate
in Rs
28.00
Rs :
Amount
in Rs
2800.00
2800.00
B.MACHINERY :
Sl No
Description
Nill
Unit
Quantity
0.00
0.00
Rate
in Rs
0.00
0.00
Amount
in Rs
0.00
0.00
0.00
C.LABOUR :
Sl No
Description
Unit
Quantity
1
2
Mazdoor
Day
7.00
Cart men with double bullock cart
Day
2.00
Total cost of labour
Rs :
labour component/unit qty
28.60
Add contractor's profit and overhead charges
0.14 4.00
labour component/unit qty (including contractor's profit)
32.60
ABSTRACT
A.Cost of Materials including ryolty charges
B. Hire charges of Machinery
C.Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
14%
Total cost for
100.00 Sqm
Sqm
(A+B+C+D)/100.0
Rate per
Rate
in Rs
295.00
395.00
Amount
in Rs
2065.00
790.00
2855.00
Rs:
Rs:
Rs:
Rs:
2800.00
0.00
2855.00
5655.00
Rs:
Rs:
Rs.
791.7
6446.70
64.50
227
228
CHAPTER-IV
CANAL CROSS DRAINAGE WORKS - Standard Data
3. The Leads for Steel and Cement shall be from the nearest market place to the Project area
4. For earth/rockfill embankments wherever initial lead of 1km is considered in the basic rate, the additional lead charges are to be
added as follows:
Additional lead charges for Earth, Murrum etc., shall be worked out for total lead involved and 1 km lead charges included
in basic rate shall be deducted from total lead charges. No loading and unloading charges shall be allowed for any item.
(same as above)
Example:
Total lead for earth from approved borrow area :
15 Km
Initial lead included in the basic rate in the SR :
1 Km
Lead charges fo Rs.
84.10
Additional lead charges :
Lead charges for next 10 kmRs.
126
Total lead charges for 15 kmRs.
210.10
Less 1 km initial lead charg Rs.
31.50 (-)
Net additional lead charges Rs.
178.60
5. The initial lead up to 50 m as mentioned in some standard data items is meant for manual lead within the working area. For
conveyance of materials, the lead required from quarry/Borrow area/ Dump Area to worksite shall be added to the data without
deducting the 50 m initial lead charges
CCDW - Work Items
IRR-CCDW-1
IRR-CCDW-1-1
Excavation in all kinds of soil including boulders upto 0.30 m dia. for foundations of canal
cross drainage and other appurtenant structures and placing the excavated stuff neatly in
specified dump area or disposing off the same as directed etc., complete with initial lead upto
50 m and initial lift upto 3 m.
230
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
UNIT :
Unit
Quantity
NIL
0.00
0.00
Unit
Quantity
NIL
0.00
0.00
Unit
1
2
Day
Day
work inspector
mazdoor
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
Quantity
0.25
6.00
10.00 cum
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
370.00
295.00
Rs:
Amount
in Rs.
92.50
1770.00
1862.50
Rs:
Rs:
Rs:
Rs:
0.00
0.00
1862.50
1862.50
260.75
2123.25
212.30
186.30
0.14 26.10
212.40
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum
IRR-CCDW-1-2
DATA:
10.00 cum
(A+B+C+D)/10.0
Total
14.00% Rs:
Rs:
Rs.
hour
6.00
Rate
in Rs.
1706.60
hour
6.00
937.80
5626.80
15866.40
Rate
in Rs.
370.00
295.00
204.10
Amount
in Rs.
118.40
2360.00
1224.60
3703.00
C. Labour:
Sl No
Description
work inspector
Mazdoor
crew for excavator
Total in Rs.
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
1
2
3
Abstract
a) Material
Unit
Unit
Quantity
Amount
in Rs.
0.00
Quantity
day
day
hour
0.32
8.00
6.00
Amount
in Rs.
10239.60
15.40
0.14 2.20
17.60
Rs
0.00
231
b) Machinery
c) Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum
Rs
Rs
Rs
14.00% Rs:
240.00 cum
Rs:
(A+B+C+D)/240.0
Rs.
15866.40
3703.00
19569.40
2739.72
22309.12
93.00
IRR-CCDW-1-3
Excavation in ordnary rock (including HDR) without blasting including boulders above 0.3 m upto 0.60 m dia.
for foundations of canal cross drainage and other appurtenant structures and placing the
excavated stuff neatly in specified dump area or disposing off the same as directed etc.,
complete with initial lead upto 50 m and initial lift upto 3 m.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
UNIT :
Unit
Quantity
NIL
0.00
0.00
Unit
Quantity
NIL
0.00
0.00
Unit
1
2
3
4
Day
Day
Day
Day
Crowbarman
Stone breaker
work inspector
mazdoor
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
Quantity
1.25
1.25
0.25
6.00
10.00 cum
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
345.00
345.00
370.00
295.00
Rs:
Amount
in Rs.
431.25
431.25
92.50
1770.00
2725.00
Rs:
Rs:
Rs:
Rs:
0.00
0.00
2725.00
2725.00
381.5
3106.5
310.70
272.50
0.14 38.20
310.70
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum
IRR-CCDW-1-4
DATA:
10.00 cum
(A+B+C+D)/10.0
Total
14.00% Rs:
Rs:
Rs.
Excavation in ordnary rock without blasting for foundations of canal cross drainage
and other appurtenant structures and placing the excavated stuff neatly in specified dump
area or disposing off the same as directed etc., complete with initial
lead upto 50 m and initial lift upto 3 m.
( Data adopted from MORTH)
Mechanical Means
Unit = cum
Unit:
Taking output = 180 cum
180.00
A. Materials:
Sl No
Description
Unit
Quantity
Rate
in Rs.
NIL
0.00
0.00
B. Machinery:
Sl No
Description
1.0
Unit
hour
Quantity
6.00
Rate
in Rs.
1706.60
cum
Amount
in Rs.
0.00
Amount
in Rs.
10239.60
232
work inspector
Mazdoor
crew for excavator
Total in Rs.
hour
Unit
6.00
Quantity
day
day
hour
0.24
6.00
6.00
RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
B. MACHINERY:
Sl No
Description
1
2
UNIT :
Unit
Quantity
Rm
10%
Hour
kg
Nos
Rm
LS
Unit
43.50
6.00
20.00
29.00
70.00
0.50
Quantity
Hour
Hour
Hour
Hour
C. LABOUR:
Sl No
Description
Unit
1
2
3
4
5
6
7
8
Hour
Hour
Day
Day
Day
Day
Day
Day
Amount
in Rs.
88.80
1770.00
1224.60
3083.40
14.00% Rs:
180.00 cum
Rs:
(A+B+C+D)/180.0
Rs.
DATA:
2
3
4
5
6
Rate
in Rs.
370.00
295.00
204.10
Rs
Rs
Rs
Rs
Excavation in hard rock requiring blasting including boulders above 0.6 m upto 1.2 m dia. for
foundations of canal cross drainage and other appurtenant structures and placing the
excavated stuff neatly in specified dump area or disposing off the same as directed etc.,
complete with initial lead upto 50 m and initial lift upto 3 m.
5626.80
15866.40
17.10
0.14 2.40
19.50
IRR-CCDW-1-5
937.80
3.00
3.00
6.00
6.00
Quantity
3.00
6.00
1.00
0.50
0.50
6.00
3.00
51.00
0.00
15866.40
3083.40
18949.80
2652.97
21602.77
120.00
100 cum
Rate
in Rs.
20.14
0.22
70.00
13.00
11.00
41.00
Rs:
Amount
in Rs.
876.09
87.61
1.31
1400.00
377.00
770.00
20.50
3532.51
Rate
in Rs.
275.60
959.10
19.80
0.00
Rs:
Amount
in Rs.
826.80
2877.30
118.80
0.00
3822.90
Rate
in Rs.
182.20
284.70
370.00
440.00
345.00
345.00
345.00
295.00
Rs:
Amount
in Rs.
546.60
1708.20
370.00
220.00
172.50
2070.00
1035.00
15045.00
21167.30
211.70
0.14 29.60
241.30
233
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum
Rs:
Rs:
Rs:
Rs:
Total
14.00% Rs:
100.00 cum
Rs:
(A+B+C+D)/100.0
Rs.
IRR-CCDW-1-6
Excavation in hard rock of all toughness by blasting including boulders above 1.2 m dia. for
foundations of canal cross drainage and other appurtenant structures and placing the
excavated rock neatly in specified dump area or stack yard as directed etc., complete with
initial lead upto 50 m and initial lift upto 3 m.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4
5
6
B. MACHINERY:
Sl No
Description
1
2
UNIT :
Unit
kg
No.
No.
Rm
Hour
Rm
10%
Unit
32.00
8.00
104.00
150.00
16.00
98.30
Quantity
Hour
Hour
Hour
Hour
C. LABOUR:
Sl No
Description
Unit
1
2
3
4
5
6
7
8
Hour
Hour
Day
Day
Day
Day
Day
Day
Quantity
8.00
8.00
16.00
16.00
Quantity
8.00
16.00
1.00
1.00
1.00
6.00
6.00
51.00
100.00 cum
Rate
in Rs.
70.00
9.00
13.00
11.00
10.94
26.85
Rs:
Amount
in Rs.
2240.00
72.00
1352.00
1650.00
175.00
2639.68
263.97
8392.65
Rate
in Rs.
275.60
959.10
19.80
0.00
Rs:
Amount
in Rs.
2204.80
7672.80
316.80
0.00
10194.40
Rate
in Rs.
182.20
284.70
440.00
345.00
370.00
345.00
345.00
295.00
Rs:
Amount
in Rs.
1457.60
4555.20
440.00
345.00
370.00
2070.00
2070.00
15045.00
26352.80
Rs:
Rs:
Rs:
Rs:
8392.65
10194.40
26352.80
44939.85
6291.58
51231.43
512.30
263.50
0.14 36.90
300.40
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum
IRR-CCDW-1-7
3532.51
3822.90
21167.30
28522.71
3993.18
32515.892
325.20
Total
14.00% Rs:
100.00 cum
Rs:
(A+B+C+D)/100.0
Rs.
Excavation in hard rock with blasting prohibited for foundations of canal cross drainage
and other appurtenant structures and placing the excavated rock neatly in
or stack yard as directed etc., complete with specified dump area initial lead upto 50 m and
234
DATA:
Unit
Quantity
NIL
b)
Machinery
Sl No
Description
1.0
c) Labour
Sl No
Description
work inspector
Mazdoor
crew for compressor
Total in Rs.
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
1
2
3
Abstract
a) Material
b) Machinery
c) Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum
0.00
Unit
Amount
in Rs.
0.00
Amount
in Rs.
1447.80
hour
6.00
Rate
in Rs.
241.30
hour
6.00
767.30
4603.80
6051.60
Rate
in Rs.
370.00
295.00
182.20
Amount
in Rs.
74.00
1475.00
1093.20
2642.20
Unit
Quantity
Rate
in Rs.
0.00
Quantity
day
day
hour
0.20
5.00
6.00
264.20
0.14 37.00
301.20
Rs
Rs
Rs
Rs
10.00 cum
(A+B+C+D)/10.0
14.00% Rs:
Rs:
Rs.
IRR-CCDW-1-8
Providing and fixing 25 mm dia 2.50 m long cold twisted deformed steel anchor rods with
1.25 m length driven into 32 mm dia hole drilled in bed rock and remaining length embedded in
concrete / masonry including cost of all materials, machinery, labour, drilling and cleaning
hole, driving anchor rod, grouting hole with thick cement slurry etc., complete with initial lead
upto 50 m and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4
B. MACHINERY:
Sl No
Description
1
2
cum
10.00
UNIT :
Unit
kg
kg
Rm
10%
Hour
Unit
Hour
Hour
Hour
Hour
Quantity
5.00
101.00
12.50
2.00
Quantity
1.00
1.00
2.00
2.00
0.00
6051.60
2642.20
8693.80
1217.13
9910.93
991.10
10.00 Nos.
Rate
in Rs.
4.00
46.50
26.85
10.94
Rs:
Amount
in Rs.
20.00
4696.50
335.67
33.57
21.88
5107.61
Rate
in Rs.
275.60
959.10
19.80
0.00
Rs:
Amount
in Rs.
275.60
959.10
39.60
0.00
1274.30
C. LABOUR:
235
Sl No
Description
1
2
3
4
5
6
Unit
Quantity
Hour
Hour
Day
Day
Day
Day
1.00
2.00
0.50
0.50
0.50
1.00
Rate
in Rs.
182.20
284.70
345.00
450.00
370.00
295.00
Rs:
Amount
in Rs.
182.20
569.40
172.50
225.00
185.00
295.00
1629.10
Rs:
Rs:
Rs:
Rs:
5107.61
1274.30
1629.10
8011.01
1121.54
9132.55
913.30
162.90
0.14 22.80
185.70
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per each
10.00 Nos.
(A+B+C+D)/10.0
Total
14.00% Rs:
Rs:
Rs.
IRR-CCDW-2
IRR-CCDW-2-1
Providing, fabricating and placing in position reinforcement steel bars for RCC works including
cleaning, straightening, cutting, bending, hooking, lapping, welding wherever required,tying with
1.25 mm dia soft annealed steel wire, including cost of all materials, machinery, labour etc.,
complete with initial lead upto 50 and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
Unit
1
2
3
kg
kg
LS
B. MACHINERY:
Sl No
Description
1
UNIT :
Unit
Quantity
1050.00
8.00
3.00
Quantity
Nil
0.00
0.00
Unit
1
2
3
Day
Day
Day
work inspector
Bar bender
mazdoor
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
Quantity
1.00
6.00
11.00
1000.00 kg
Rate
in Rs.
46.50
70.00
41.00
Rs:
Amount
in Rs.
48825.00
560.00
123.00
49508.00
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
370.00
450.00
295.00
Rs:
Amount
in Rs.
370.00
2700.00
3245.00
6315.00
Rs:
Rs:
Rs:
Rs:
49508.00
0.00
6315.00
55823.00
7815.22
63638.22
63.60
6.30
0.14 0.90
7.20
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per kg
IRR-CCDW-2-2
Total
14.00% Rs:
1000.00 kg
Rs:
(A+B+C+D)/1000.0
Rs.
Providing, fabricating and fixing in position structural steel cutting edge consisting of 100 x
236
100 x 10 mm angle and 250 x 12 mm plate for sinking for sinking 4.50 m outer diameter
foundation wells foundation wells including cost of all materials, machinery, labour, bending,
welding, providing anchors etc., complete with initial lead upto 50 m and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
7
Particulars
Unit
kg
kg
kg
cum
cum
Nos
LS
B. MACHINERY:
Sl No
1
2
3
Description
Unit
Bending machine
Fuel / Energy charges
Welding set
Fuel / Energy charges
Sundries
Total hire charges of Machinery
Hour
Hour
Hour
Hour
LS
C. LABOUR:
Sl No
1
2
3
4
UNIT :
Description
Unit
Quantity
216.10
342.30
56.60
0.50
1.50
300.00
5.00
Quantity
8.00
8.00
30.00
30.00
10.00
Quantity
Day
Day
Day
Day
Total cost of Labour
2.00
5.00
1.00
5.00
615.00 kg
Rate
in Rs.
45.00
46.00
46.50
320.00
52.00
11.00
41.00
Rs:
Amount
in Rs.
9724.50
15745.80
2631.90
160.00
78.00
3300.00
205.00
31845.20
Rate
in Rs.
42.60
114.10
16.00
91.30
41.00
Rs:
Amount
in Rs.
340.80
912.80
480.00
2739.00
410.00
4882.60
Rate
in Rs.
440.00
385.00
370.00
295.00
Rs:
Amount
in Rs.
880.00
1925.00
370.00
1475.00
4650.00
Rs:
Rs:
Rs:
Rs:
31845.20
4882.60
4650.00
41377.80
5792.89
47170.69
76.70
7.60
0.14 1.10
8.70
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per kg
Total
14.00% Rs:
615.00 kg
Rs:
(A+B+C+D)/615.0
Rs.
IRR-CCDW-2-3 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than
15 N /sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for foundation filling including cost of all materials, machinery, labour, formwork,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
complete with initial lead upto 50 m and all lifts.
(Cement content: 260 kg / cum with use of super plasticiser(0.4% by wt. of cement),
237
Data
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
Particulars
Unit
kg
kg
cum
cum
cum
cum
kg
sqm
10%
LS
B. MACHINERY:
Sl No
1
2
3
4
UNIT :
Description
Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
C. LABOUR:
Sl No
Description
1
2
3
4
5
6
7
Quantity
3998.80
46.14
6.92
4.15
2.77
6.15
16.00
15.38
15.38 cum
Rate
in Rs.
4.00
4.00
1145.00
1210.00
875.00
462.00
80.00
244.56
41.00
Rs:
Amount
in Rs.
15995.20
184.56
7924.55
5024.65
2422.35
2842.22
1279.62
3761.39
376.14
20.50
39831.17
Rate
in Rs.
53.50
85.30
10.20
85.30
402.50
322.20
7.60
21.50
Rs:
Amount
in Rs.
428.00
682.40
5.10
42.65
402.50
322.20
60.80
172.00
2115.65
Amount
in Rs.
1518.40
48.05
153.10
1092.80
370.00
385.00
3245.00
1180.00
885.00
4537.10
295.00
1158.11
115.81
14983.38
0.50
Quantity
8.00
8.00
0.50
0.50
1.00
1.00
8.00
8.00
Hour
Hour
Hour
Hour
Day
Day
8.00
0.50
1.00
8.00
1.00
1.00
Rate
in Rs.
189.80
96.10
153.10
136.60
370.00
385.00
Day
Day
Day
Day
Day
sqm
10%
11.00
4.00
3.00
15.38
1.00
15.38
295.00
295.00
295.00
295.00
295.00
75.30
Unit
Quantity
Rs:
974.20
0.14 136.40
1110.60
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum
Total
14.00% Rs:
15.38 cum
Rs:
(A+B+C+D)/15.38
Rs.
Rs:
Rs:
Rs:
Rs:
39831.17
2115.65
14983.38
56930.20
7970.23
64900.43
4219.80
IRR-CCDW-2-4 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than
15 N / sq mm ) grade cement concrete using 80 mm down size approved, clean, hard, graded
aggregates for foundation filling including cost of all materials, machinery, labour, formwork,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
238
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
Particulars
Unit
kg
kg
cum
cum
cum
cum
cum
kg
sqm
10%
LS
B. MACHINERY:
Sl No
1
2
3
4
UNIT :
Description
Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
C. LABOUR:
Sl No
Description
1
2
3
4
5
6
7
Unit
Quantity
3600.00
43.20
4.94
4.23
2.82
2.12
5.04
14.40
14.40
14.40 cum
Rate
in Rs.
4.00
4.00
635.00
1145.00
1210.00
875.00
462.00
80.00
244.56
41.00
Rs:
Amount
in Rs.
14400.00
172.80
3136.39
4847.47
3415.10
1852.20
2328.48
1152.00
3521.72
352.17
20.50
35198.84
Rate
in Rs.
92.70
170.50
10.20
85.30
402.50
322.20
8.20
32.20
Rs:
Amount
in Rs.
741.60
1364.00
5.10
42.65
402.50
322.20
65.60
257.60
3201.25
Amount
in Rs.
1518.40
48.05
153.10
1092.80
385.00
370.00
3245.00
1180.00
885.00
4248.00
295.00
1084.32
108.43
14613.10
0.50
Quantity
8.00
8.00
0.50
0.50
1.00
1.00
8.00
8.00
Quantity
Hour
Hour
Hour
Hour
Day
Day
8.00
0.50
1.00
8.00
1.00
1.00
Rate
in Rs.
189.80
96.10
153.10
136.60
385.00
370.00
Day
Day
Day
Day
Day
sqm
10%
11.00
4.00
3.00
14.40
1.00
14.40
295.00
295.00
295.00
295.00
295.00
75.30
Rs:
1014.80
0.14 142.10
1156.90
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum
Total
14.00% Rs:
14.40 cum
Rs:
(A+B+C+D)/14.40
Rs.
Rs:
Rs:
Rs:
Rs:
35198.84
3201.25
14613.10
53013.19
7421.85
60435.04
4196.90
IRR-CCDW-2-5 Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than
239
10 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for foundation filling including cost of all materials, machinery, labour, formwork,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
complete with initial lead upto 50 m and all lifts.
(Cement content: 220 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
Particulars
Unit
kg
kg
cum
cum
cum
cum
kg
sqm
10%
LS
B. MACHINERY:
Sl No
1
2
3
4
Description
Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
C. LABOUR:
Sl No
1
2
3
4
5
6
7
8
9
UNIT :
Description
Unit
Quantity
3599.20
49.08
7.36
4.42
2.94
6.54
14.40
16.36
16.36 cum
Rate
in Rs.
4.00
4.00
1145.00
1210.00
875.00
462.00
80.00
244.56
41.00
Rs:
Amount
in Rs.
14396.80
196.32
8429.49
5344.81
2576.70
3023.33
1151.74
4001.07
400.11
20.50
39540.87
Rate
in Rs.
53.50
85.30
10.20
85.30
402.50
322.20
7.60
21.50
Rs:
Amount
in Rs.
428.00
682.40
5.10
42.65
402.50
322.20
60.80
172.00
2115.65
Rate
in Rs.
189.80
96.10
153.10
136.60
385.00
370.00
Amount
in Rs.
1518.40
48.05
153.10
1092.80
385.00
370.00
295.00
295.00
295.00
295.00
295.00
75.30
Rs:
3245.00
1180.00
885.00
4826.20
295.00
1231.91
15230.46
Rs:
Rs:
Rs:
Rs:
39540.87
2115.65
15230.46
56886.97
7964.18
64851.15
3964.00
0.50
Quantity
8.00
8.00
0.50
0.50
1.00
1.00
8.00
8.00
Quantity
Hour
Hour
Hour
Hour
Day
Day
8.00
0.50
1.00
8.00
1.00
1.00
Day
Day
Day
Day
Day
sqm
11.00
4.00
3.00
16.36
1.00
16.36
931.00
0.14 130.30
1061.30
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum
Total
14.00% Rs:
16.36 cum
Rs:
(A+B+C+D)/16.36
Rs.
240
IRR-CCDW-2-6 Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than
10 N / sq mm ) grade cement concrete using 80 mm down size approved, clean, hard, graded
aggregates for foundation filling including cost of all materials, machinery, labour, formwork,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
complete with initial lead upto 50 m and all lifts.
(Cement content: 220 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.98cum, Blending Ratio of CA--35:30:20:15, FA : 0.35 cum)
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
Particulars
Unit
kg
kg
cum
cum
cum
cum
cum
kg
sqm
10%
LS
B. MACHINERY:
Sl No
1
2
3
4
UNIT :
Description
Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
C. LABOUR:
Sl No
Description
1
2
3
4
5
6
7
Unit
Quantity
3201.00
43.65
4.99
4.28
2.85
2.14
5.09
12.80
14.55
14.55 cum
Rate
in Rs.
4.00
4.00
635.00
1145.00
1210.00
875.00
462.00
80.00
244.56
41.00
Rs:
Amount
in Rs.
12804.00
174.60
3169.06
4897.97
3450.68
1871.49
2352.74
1024.32
3558.41
355.84
20.50
33679.60
Rate
in Rs.
92.70
170.50
10.20
85.30
402.50
322.20
8.20
32.20
Rs:
Amount
in Rs.
741.60
1364.00
5.10
42.65
402.50
322.20
65.60
257.60
3201.25
Amount
in Rs.
1518.40
48.05
153.10
1092.80
385.00
370.00
3245.00
1180.00
885.00
4292.25
295.00
1095.62
109.56
14669.78
0.50
Quantity
8.00
8.00
0.50
0.50
1.00
1.00
8.00
8.00
Quantity
Hour
Hour
Hour
Hour
Day
Day
8.00
0.50
1.00
8.00
1.00
1.00
Rate
in Rs.
189.80
96.10
153.10
136.60
385.00
370.00
Day
Day
Day
Day
Day
sqm
10%
11.00
4.00
3.00
14.55
1.00
14.55
295.00
295.00
295.00
295.00
295.00
75.30
Rs:
1008.20
0.14 141.10
1149.30
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
14.55 cum
Total
14.00% Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
33679.60
3201.25
14669.78
51550.63
7217.09
58767.72
241
(A+B+C+D)/14.55
Rs.
4039.00
IRR-CCDW-2-7 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than
20 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for foundation filling including cost of all materials, machinery, labour, formwork,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
complete with initial lead upto 50 m and all lifts. ( Cement content : 220 kg / cum )
(Cement content: 310 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
Particulars
Unit
kg
kg
cum
cum
cum
cum
kg
sqm
10%
LS
B. MACHINERY:
Sl No
1
2
3
4
UNIT :
Description
Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
C. LABOUR:
Sl No
1
2
3
4
5
6
7
Description
Quantity
4398.90
42.57
6.39
3.83
2.55
5.68
17.60
14.19
14.19 cum
Rate
in Rs.
4.00
4.00
1145.00
1210.00
875.00
462.00
80.00
244.56
41.00
Rs:
Amount
in Rs.
17595.60
170.28
7311.40
4635.87
2234.93
2622.31
1407.65
3470.36
347.04
20.50
39815.93
Rate
in Rs.
53.50
85.30
10.20
85.30
402.50
322.20
7.60
21.50
Rs:
Amount
in Rs.
428.00
682.40
5.10
42.65
402.50
322.20
60.80
172.00
2115.65
Amount
in Rs.
1518.40
48.05
153.10
1092.80
385.00
370.00
Rs:
3245.00
1180.00
885.00
4186.05
295.00
1068.51
106.85
14533.76
Rs:
Rs:
Rs:
Rs:
39815.93
2115.65
14533.76
56465.34
0.50
Quantity
8.00
8.00
0.50
0.50
1.00
1.00
8.00
8.00
Hour
Hour
Hour
Hour
Day
Day
8.00
0.50
1.00
8.00
1.00
1.00
Rate
in Rs.
189.80
96.10
153.10
136.60
385.00
370.00
Day
Day
Day
Day
Day
sqm
10%
11.00
4.00
3.00
14.19
1.00
14.19
295.00
295.00
295.00
295.00
295.00
75.30
Unit
Quantity
1024.20
0.14 143.40
1167.60
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
242
14.00% Rs:
14.19 cum
Rs:
(A+B+C+D)/14.19
Rs.
7905.15
64370.49
4536.30
IRR-CCDW-2-8 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than
20 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for sub-structure / super- structure works including cost of all materials,
machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position,
levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts.
(Cement content: 320 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
Particulars
Unit
kg
kg
cum
cum
cum
cum
kg
sqm
25%
LS
B. MACHINERY:
Sl No
1
2
3
4
UNIT :
Description
Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
C. LABOUR:
Sl No
1
2
3
4
5
6
7
Description
Quantity
4800.00
75.00
6.75
4.05
2.70
6.00
19.20
30.00
0.50
Quantity
8.00
8.00
0.50
0.50
1.00
1.00
8.00
8.00
15.00 cum
Rate
in Rs.
4.00
4.00
1145.00
1210.00
875.00
462.00
80.00
244.56
41.00
Rs:
Amount
in Rs.
19200.00
300.00
7728.75
4900.50
2362.50
2772.00
1536.00
7336.92
1834.23
20.50
47991.40
Rate
in Rs.
53.50
85.30
10.20
85.30
402.50
322.20
7.60
21.50
Rs:
Amount
in Rs.
428.00
682.40
5.10
42.65
402.50
322.20
60.80
172.00
2115.65
Amount
in Rs.
1518.40
48.05
153.10
1092.80
385.00
370.00
Rs:
3245.00
1180.00
1180.00
4425.00
295.00
1129.50
282.38
15304.23
Rs:
Rs:
47991.40
2115.65
Hour
Hour
Hour
Hour
Day
Day
8.00
0.50
1.00
8.00
1.00
1.00
Rate
in Rs.
189.80
96.10
153.10
136.60
385.00
370.00
Day
Day
Day
Day
Day
sqm
25%
11.00
4.00
4.00
15.00
1.00
15.00
295.00
295.00
295.00
295.00
295.00
75.30
Unit
Quantity
1020.30
0.14 142.80
1163.10
243
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum
15.00 cum
(A+B+C+D)/15.0
Rs:
Rs:
Total
14.00% Rs:
Rs:
Rs.
15304.23
65411.27
9157.58
74568.85
4971.30
IRR-CCDW-2-9 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than
20 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
aggregates for sub-structure / super- structure works including cost of all materials,
machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position,
levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts.
(Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
Particulars
Unit
kg
kg
cum
cum
cum
kg
sqm
25%
LS
B. MACHINERY:
Sl No
1
2
3
4
UNIT :
Description
Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
C. LABOUR:
Sl No
Description
ABSTRACT:
A. Cost of Materials
Unit
Quantity
5200.80
78.80
8.20
4.41
7.09
20.80
31.52
0.50
Quantity
8.00
8.00
0.50
0.50
1.00
1.00
8.00
8.00
Quantity
15.76 cum
Rate
in Rs.
4.00
4.00
1210.00
875.00
462.00
80.00
244.56
41.00
Rs:
Amount
in Rs.
20803.20
315.20
9916.19
3861.20
3276.50
1664.26
7708.66
1927.16
20.50
49492.87
Rate
in Rs.
53.50
85.30
10.20
85.30
402.50
322.20
7.60
21.50
Rs:
Amount
in Rs.
428.00
682.40
5.10
42.65
402.50
322.20
60.80
172.00
2115.65
Amount
in Rs.
1518.40
48.05
153.10
1092.80
385.00
370.00
Rs:
3245.00
1180.00
1180.00
4649.20
295.00
2373.46
593.36
17083.37
Rs:
49492.87
Hour
Hour
Hour
Hour
Day
Day
8.00
0.50
1.00
8.00
1.00
1.00
Rate
in Rs.
189.80
96.10
153.10
136.60
385.00
370.00
Day
Day
Day
Day
Day
sqm
25%
11.00
4.00
4.00
15.76
1.00
31.52
295.00
295.00
295.00
295.00
295.00
75.30
1084.00
0.14 151.80
1235.80
244
Rs:
Rs:
Rs:
Total
14.00% Rs:
15.76 cum
Rs:
(A+B+C+D)/15.76
Rs.
2115.65
17083.37
68691.89
9616.86
78308.751
4968.80
IRR-CCDW-2-10 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than
15 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
aggregates for sub-structure / super- structure works including cost of all materials,
machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position,
levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts.
(Cement content: 280 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
Particulars
Unit
kg
kg
cum
cum
cum
kg
sqm
25%
LS
B. MACHINERY:
Sl No
1
2
3
4
UNIT :
Description
Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
C. LABOUR:
Sl No
Description
Unit
Quantity
4398.80
78.55
8.17
4.40
7.07
17.60
31.42
0.50
Quantity
8.00
8.00
0.50
0.50
1.00
1.00
8.00
8.00
Quantity
15.71 cum
Rate
in Rs.
4.00
4.00
1210.00
875.00
462.00
80.00
244.56
41.00
Rs:
Amount
in Rs.
17595.20
314.20
9884.73
3848.95
3266.11
1407.62
7684.20
1921.05
20.50
45942.56
Rate
in Rs.
53.50
85.30
10.20
85.30
402.50
322.20
7.60
21.50
Rs:
Amount
in Rs.
428.00
682.40
5.10
42.65
402.50
322.20
60.80
172.00
2115.65
Amount
in Rs.
1518.40
48.05
153.10
1092.80
385.00
370.00
3245.00
1180.00
1180.00
4634.45
295.00
2365.93
591.48
17059.21
Hour
Hour
Hour
Hour
Day
Day
8.00
0.50
1.00
8.00
1.00
1.00
Rate
in Rs.
189.80
96.10
153.10
136.60
385.00
370.00
Day
Day
Day
Day
Day
sqm
25%
11.00
4.00
4.00
15.71
1.00
31.42
295.00
295.00
295.00
295.00
295.00
75.30
Rs:
1085.90
0.14 152.00
1237.90
ABSTRACT:
245
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum
Rs:
Rs:
Rs:
Rs:
Total
14.00% Rs:
15.71 cum
Rs:
(A+B+C+D)/15.71
Rs.
45942.56
2115.65
17059.21
65117.41
9116.44
74233.853
4725.30
IRR-CCDW-2-11 Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than
10 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
aggregates for sub-structure / super- structure works including cost of all materials,
machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position,
levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts.
(Cement content: 220 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
Particulars
Unit
kg
kg
cum
cum
cum
kg
sqm
25%
LS
B. MACHINERY:
Sl No
1
2
3
4
Description
Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
C. LABOUR:
Sl No
Description
UNIT :
Unit
Quantity
3960.00
90.00
9.36
5.04
8.10
15.84
36.00
0.50
Quantity
8.00
8.00
0.50
0.50
1.00
1.00
8.00
8.00
Quantity
18.00 cum
Rate
in Rs.
4.00
4.00
1210.00
875.00
462.00
80.00
244.56
41.00
Rs:
Amount
in Rs.
15840.00
360.00
11325.60
4410.00
3742.20
1267.20
8804.30
2201.08
20.50
47970.88
Rate
in Rs.
53.50
85.30
10.20
85.30
402.50
322.20
7.60
21.50
Rs:
Amount
in Rs.
428.00
682.40
5.10
42.65
402.50
322.20
60.80
172.00
2115.65
Amount
in Rs.
1518.40
48.05
153.10
1092.80
385.00
370.00
3245.00
1180.00
1180.00
5310.00
295.00
2710.80
677.70
18165.85
Hour
Hour
Hour
Hour
Day
Day
8.00
0.50
1.00
8.00
1.00
1.00
Rate
in Rs.
189.80
96.10
153.10
136.60
385.00
370.00
Day
Day
Day
Day
Day
sqm
25%
11.00
4.00
4.00
18.00
1.00
36.00
295.00
295.00
295.00
295.00
295.00
75.30
Rs:
1009.20
0.14 141.30
1150.50
246
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum
18.00 cum
(A+B+C+D)/18.0
Rs:
Rs:
Rs:
Rs:
Total
14.00% Rs:
Rs:
Rs.
47970.88
2115.65
18165.85
68252.38
9555.33
77807.707
4322.70
IRR-CCDW-2-12 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than
20 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
aggregates for well kerb including cost of all materials, machinery, labour, formwork,
scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc., complete with initial lead upto 50 m and all lifts.
Note:
If water is to be brought from other place add only lead charges @ 500 ltr / cum.
(Cement content: 350 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
Particulars
Unit
kg
cum
cum
cum
kg
sqm
LS
B. MACHINERY:
Sl No
1
2
3
Description
Unit
Hour
Hour
Hour
Hour
Hour
Hour
C. LABOUR:
Sl No
1
2
3
4
5
6
UNIT :
Description
Unit
Quantity
5250.00
7.80
4.20
6.75
21.00
82.50
0.50
Quantity
8.00
8.00
0.50
0.50
8.00
8.00
Quantity
Hour
Hour
Hour
Day
Day
8.00
0.50
8.00
1.00
1.00
Day
Day
Day
Day
Day
sqm
11.00
4.00
3.00
15.00
1.00
82.50
15.00 cum
Rate
in Rs.
4.00
1210.00
875.00
462.00
80.00
269.02
41.00
Rs:
Amount
in Rs.
21000.00
9438.00
3675.00
3118.50
1680.00
22194.18
20.50
61126.18
Rate
in Rs.
53.50
85.30
10.20
85.30
7.60
21.50
Rs:
Amount
in Rs.
428.00
682.40
5.10
42.65
60.80
172.00
1390.95
Rate
in Rs.
189.80
96.10
136.60
385.00
370.00
Amount
in Rs.
1518.40
48.05
1092.80
385.00
370.00
295.00
295.00
295.00
295.00
295.00
75.30
Rs:
3245.00
1180.00
885.00
4425.00
295.00
6212.25
19656.50
Rs:
Rs:
Rs:
61126.18
1390.95
19656.50
1310.40
0.14 183.50
1493.90
247
15.00 cum
(A+B+C+D)/15.0
Total
14.00% Rs:
Rs:
Rs.
Rs:
82173.63
11504.31
93677.937
6245.20
IRR-CCDW-2-13 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than
20 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for well steining including cost of all materials, machinery, labour, formwork,
scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc., complete with initial lead upto 50 m and all lifts.
Note:
If water is to be brought from other place add only lead charges @ 500 ltr / cum.
(Cement content: 320 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
Particulars
Unit
kg
kg
cum
cum
cum
cum
kg
sqm
LS
B. MACHINERY:
Sl No
1
2
3
Description
Unit
Hour
Hour
Hour
Hour
Hour
Hour
C. LABOUR:
Sl No
1
2
3
4
5
6
UNIT :
Description
Unit
Quantity
4800.00
30.00
6.75
4.05
2.70
6.00
19.20
60.00
0.50
Quantity
8.00
8.00
0.50
0.50
8.00
8.00
Quantity
Hour
Hour
Hour
Day
Day
8.00
0.50
8.00
1.00
1.00
Day
Day
Day
Day
Day
sqm
11.00
4.00
3.00
15.00
1.00
60.00
15.00 cum
Rate
in Rs.
4.00
4.00
1145.00
1210.00
875.00
462.00
80.00
269.02
41.00
Rs:
Amount
in Rs.
19200.00
120.00
7728.75
4900.50
2362.50
2772.00
1536.00
16141.22
20.50
54781.47
Rate
in Rs.
53.50
85.30
10.20
85.30
7.60
21.50
Rs:
Amount
in Rs.
428.00
682.40
5.10
42.65
60.80
172.00
1390.95
Rate
in Rs.
189.80
96.10
136.60
385.00
370.00
Amount
in Rs.
1518.40
48.05
1092.80
385.00
370.00
295.00
295.00
295.00
295.00
295.00
75.30
Rs:
3245.00
1180.00
885.00
4425.00
295.00
4518.00
17962.25
Rs:
Rs:
Rs:
Rs:
54781.47
1390.95
17962.25
74134.67
10378.85
1197.50
0.14 167.70
1365.20
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total
14.00% Rs:
248
15.00 cum
(A+B+C+D)/15.0
Rs:
Rs.
84513.52
5634.20
IRR-CCDW-2-14 Providing and laying insitu M-15 ( 28 days cube compressive strength not less than 15 N / sq
mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
aggregates for well bottom plug by tremie or skip box method including cost of all materials,
machinery, labour, batching, mixing, placing in position as per detailed specifications etc.,
complete with initial lead upto 50 m and all lifts. ( Cement content : 350 kg / cum )
(Cement content: 350 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
Particulars
UNIT :
Unit
Quantity
kg
cum
cum
cum
kg
4900.00
7.28
3.92
6.30
19.60
TOTAL
1%
Description
Unit
Hour
Hour
Hour
Hour
LS
C. LABOUR:
Sl No
Description
1
2
3
4
5
Unit
Quantity
8.00
8.00
0.50
0.50
5.00
Quantity
Hour
Hour
Day
Day
8.00
0.50
1.00
1.00
Day
Day
Day
Day
Day
4.00
11.00
4.00
2.00
16.00
14.00 cum
Rate
in Rs.
4.00
1210.00
875.00
462.00
80.00
Rs:
Rs:
Rs:
Amount
in Rs.
19600.00
8808.80
3430.00
2910.60
1568.00
36317.40
363.17
36680.57
Rate
in Rs.
53.50
85.30
10.20
85.30
41.00
Rs:
Amount
in Rs.
428.00
682.40
5.10
42.65
205.00
1363.15
Rate
in Rs.
189.80
96.10
345.00
370.00
Amount
in Rs.
1518.40
48.05
345.00
370.00
295.00
295.00
295.00
295.00
295.00
Rs:
1180.00
3245.00
1180.00
590.00
4720.00
13196.45
Rs:
Rs:
Rs:
Rs:
36680.57
1363.15
13196.45
51240.17
7173.62
58413.79
4172.40
942.60
0.14 132.00
1074.60
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum
14.00 cum
(A+B+C+D)/14.0
Total
14.00% Rs:
Rs:
Rs.
IRR-CCDW-2-15 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than
15 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for well top plug including cost of all materials, machinery, labour, cleaning,
batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete with
249
Note:
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
Particulars
Unit
kg
cum
cum
cum
cum
kg
B. MACHINERY:
Sl No
1
2
3
Description
Unit
Hour
Hour
Hour
Hour
Hour
Hour
C. LABOUR:
Sl No
1
2
3
4
5
6
UNIT :
Description
Unit
Quantity
4001.20
6.43
3.86
2.57
5.72
16.00
Quantity
8.00
8.00
0.50
0.50
8.00
8.00
Quantity
Hour
Hour
Hour
Day
Day
8.00
0.50
8.00
1.00
1.00
Day
Day
Day
Day
Day
11.00
4.00
3.00
14.29
1.00
14.29 cum
Rate
in Rs.
4.00
1145.00
1210.00
875.00
462.00
80.00
Rs:
Amount
in Rs.
16004.80
7362.92
4668.54
2250.68
2640.79
1280.38
34208.12
Rate
in Rs.
53.50
85.30
10.20
85.30
7.60
21.50
Rs:
Amount
in Rs.
428.00
682.40
5.10
42.65
60.80
172.00
1390.95
Rate
in Rs.
189.80
96.10
136.60
385.00
370.00
Amount
in Rs.
1518.40
48.05
1092.80
385.00
370.00
295.00
295.00
295.00
295.00
295.00
Rs:
3245.00
1180.00
885.00
4215.55
295.00
13234.80
Rs:
Rs:
Rs:
Rs:
34208.12
1390.95
13234.80
48833.87
6836.74
55670.61
3895.80
926.20
0.14 129.70
1055.90
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum
Total
14.00% Rs:
14.29 cum
Rs:
(A+B+C+D)/14.29
Rs.
IRR-CCDW-2-16 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than
20 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
aggregates for well cap including cost of all materials, machinery, labour, formwork,
scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc., complete with initial lead upto 50 m and all lifts.
Note:
If water is to be brought from other place add only lead charges @ 500 ltr / cum.
(Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
250
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
Particulars
Unit
kg
kg
cum
cum
cum
kg
sqm
LS
B. MACHINERY:
Sl No
1
2
3
Description
Unit
Hour
Hour
Hour
Hour
Hour
Hour
C. LABOUR:
Sl No
1
2
3
4
5
6
UNIT :
Description
Unit
Quantity
5200.80
78.80
8.20
4.41
7.09
20.80
15.76
0.50
Quantity
8.00
8.00
0.50
0.50
8.00
8.00
Quantity
Hour
Hour
Hour
Day
Day
8.00
0.50
8.00
1.00
1.00
Day
Day
Day
Day
Day
sqm
11.00
4.00
3.00
15.76
1.00
15.76
15.76 cum
Rate
in Rs.
4.00
4.00
1210.00
875.00
462.00
80.00
244.56
41.00
Rs:
Amount
in Rs.
20803.20
315.20
9916.19
3861.20
3276.50
1664.26
3854.33
20.50
43711.38
Rate
in Rs.
53.50
85.30
10.20
85.30
7.60
21.50
Rs:
Amount
in Rs.
428.00
682.40
5.10
42.65
60.80
172.00
1390.95
Rate
in Rs.
189.80
96.10
136.60
385.00
370.00
Amount
in Rs.
1518.40
48.05
1092.80
385.00
370.00
295.00
295.00
295.00
295.00
295.00
75.30
Rs:
3245.00
1180.00
885.00
4649.20
295.00
1186.73
14855.18
Rs:
Rs:
Rs:
Rs:
43711.38
1390.95
14855.18
59957.51
8394.05
68351.56
4337.00
942.60
0.14 132.00
1074.60
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum
Total
14.00% Rs:
15.76 cum
Rs:
(A+B+C+D)/15.76
Rs.
IRR-CCDW-2-17 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than
15 N / sq mm ) grade cement concrete using 80 mm down size approved, clean, hard, graded
aggregates for piers and abutments including cost of all materials, labour, machinery,
formwork, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc., complete with initial lead upto 50 m and all lifts.
Note:
If water is to be brought from other place add only lead charges @ 500 ltr / cum.
(Cement content: 250 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.98cum, Blending Ratio of CA--35:30:20:15, FA : 0.35 cum)
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
UNIT :
Unit
Quantity
14.40 cum
Rate
Amount
251
1
2
3
4
5
6
B. MACHINERY:
Sl No
1
2
3
kg
kg
cum
cum
cum
cum
cum
kg
sqm
30%
Description
Unit
Hour
Hour
Hour
Hour
Hour
Hour
C. LABOUR:
Sl No
Description
Unit
1
2
3
4
5
6
3600.00
72.00
4.94
4.23
2.82
2.12
5.04
14.40
39.60
Quantity
8.00
8.00
0.50
0.50
8.00
8.00
Quantity
in Rs.
4.00
4.00
635.00
1145.00
1210.00
875.00
462.00
80.00
256.79
Rs:
in Rs.
14400.00
288.00
3136.39
4847.47
3415.10
1852.20
2328.48
1152.00
10168.97
3050.69
44639.31
Rate
in Rs.
92.70
170.50
10.20
85.30
8.20
32.20
Rs:
Amount
in Rs.
741.60
1364.00
5.10
42.65
65.60
257.60
2476.55
Amount
in Rs.
1518.40
48.05
1092.80
385.00
370.00
3245.00
1180.00
1770.00
4248.00
295.00
2981.88
894.56
18028.69
Hour
Hour
Hour
Day
Day
8.00
0.50
8.00
1.00
1.00
Rate
in Rs.
189.80
96.10
136.60
385.00
370.00
Day
Day
Day
Day
Day
sqm
30%
11.00
4.00
6.00
14.40
1.00
39.60
295.00
295.00
295.00
295.00
295.00
75.30
Rs:
1252.00
0.14 175.30
1427.30
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum
Rs:
Rs:
Rs:
Rs:
Total
14.00% Rs:
14.40 cum
Rs:
(A+B+C+D)/14.40
Rs.
44639.31
2476.55
18028.69
65144.55
9120.24
74264.791
5157.30
IRR-CCDW-2-18 Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than
10 N / sq mm ) grade cement concrete using 80 mm down size approved, clean, hard, graded
aggregates for piers and abutments including cost of all materials, labour, machinery,
formwork, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc., complete with initial lead upto 50 m and all lifts.
Note:
If water is to be brought from other place add only lead charges @ 500 ltr / cum.
(Cement content: 220 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.98cum, Blending Ratio of CA--35:30:20:15, FA : 0.35 cum)
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
UNIT :
Unit
Quantity
14.55 cum
Rate
Amount
252
1
2
3
4
5
6
B. MACHINERY:
Sl No
1
2
3
kg
kg
cum
cum
cum
cum
cum
kg
sqm
30%
Description
Unit
Hour
Hour
Hour
Hour
Hour
Hour
C. LABOUR:
Sl No
Description
Unit
1
2
3
4
5
6
3201.00
72.75
4.99
4.28
2.85
2.14
5.09
12.80
40.01
Quantity
8.00
8.00
0.50
0.50
8.00
8.00
Quantity
in Rs.
4.00
4.00
635.00
1145.00
1210.00
875.00
462.00
80.00
256.79
Rs:
in Rs.
12804.00
291.00
3169.06
4897.97
3450.68
1871.49
2352.74
1024.32
10274.90
3082.47
43218.62
Rate
in Rs.
92.70
170.50
10.20
85.30
8.20
32.20
Rs:
Amount
in Rs.
741.60
1364.00
5.10
42.65
65.60
257.60
2476.55
Amount
in Rs.
1518.40
48.05
1092.80
385.00
370.00
3245.00
1180.00
1770.00
4292.25
295.00
3012.94
903.88
18113.32
Hour
Hour
Hour
Day
Day
8.00
0.50
8.00
1.00
1.00
Rate
in Rs.
189.80
96.10
136.60
385.00
370.00
Day
Day
Day
Day
Day
sqm
30%
11.00
4.00
6.00
14.55
1.00
40.01
295.00
295.00
295.00
295.00
295.00
75.30
Rs:
1244.90
0.14 174.30
1419.20
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum
Rs:
Rs:
Rs:
Rs:
Total
14.00% Rs:
14.55 cum
Rs:
(A+B+C+D)/14.55
Rs.
43218.62
2476.55
18113.32
63808.49
8933.19
72741.68
4999.40
IRR-CCDW-2-19 Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than
10 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for piers and abutments including cost of all materials, labour, machinery,
formwork, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc., complete with initial lead upto 50 m and all lifts.
Note:
If water is to be brought from other place add only lead charges @ 500 ltr / cum.
(Cement content: 220 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
UNIT :
Unit
Quantity
16.36 cum
Rate
Amount
253
1
2
3
4
5
6
B. MACHINERY:
Sl No
1
2
3
kg
kg
cum
cum
cum
cum
kg
sqm
30%
Description
Unit
Hour
Hour
Hour
Hour
Hour
Hour
C. LABOUR:
Sl No
Description
Unit
1
2
3
4
5
6
3599.20
81.80
7.36
4.42
2.94
6.54
14.40
44.99
Quantity
8.00
8.00
0.50
0.50
8.00
8.00
Quantity
in Rs.
4.00
4.00
1145.00
1210.00
875.00
462.00
80.00
256.79
Rs:
in Rs.
14396.80
327.20
8429.49
5344.81
2576.70
3023.33
1151.74
11553.08
3465.92
50269.08
Rate
in Rs.
53.50
85.30
10.20
85.30
7.60
21.50
Rs:
Amount
in Rs.
428.00
682.40
5.10
42.65
60.80
172.00
1390.95
Amount
in Rs.
1518.40
48.05
1092.80
385.00
370.00
3245.00
1180.00
1475.00
4826.20
295.00
3387.75
1016.32
18839.52
Hour
Hour
Hour
Day
Day
8.00
0.50
8.00
1.00
1.00
Rate
in Rs.
189.80
96.10
136.60
385.00
370.00
Day
Day
Day
Day
Day
sqm
30%
11.00
4.00
5.00
16.36
1.00
44.99
295.00
295.00
295.00
295.00
295.00
75.30
Rs:
1151.60
0.14 161.20
1312.80
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum
Rs:
Rs:
Rs:
Rs:
Total
14.00% Rs:
16.36 cum
Rs:
(A+B+C+D)/16.36
Rs.
50269.08
1390.95
18839.52
70499.55
9869.94
80369.49
4912.60
IRR-CCDW-2-20 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than
20 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for cantiliver / counterfort retaining walls including cost of all materials,
machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position,
levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts.
(Cement content: 320 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
Note:
If water is to be brought from other place add only lead charges @ 500 ltr / cum.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
UNIT :
Unit
Quantity
16.25 cum
Rate
Amount
254
1
2
3
4
5
6
B. MACHINERY:
Sl No
1
2
3
kg
kg
cum
cum
cum
cum
kg
sqm
25%
LS
Description
Unit
Hour
Hour
Hour
Hour
Hour
Hour
C. LABOUR:
Sl No
Description
Unit
1
2
3
4
5
6
5200.00
81.25
7.31
4.39
2.93
6.50
20.80
52.81
in Rs.
4.00
4.00
1145.00
1210.00
875.00
462.00
80.00
244.56
41.00
Rs:
in Rs.
20800.00
325.00
8372.81
5308.88
2559.38
3003.00
1664.00
12916.03
3229.01
20.50
58198.60
Rate
in Rs.
53.50
85.30
10.20
85.30
7.60
21.50
Rs:
Amount
in Rs.
428.00
682.40
5.10
42.65
60.80
172.00
1390.95
Amount
in Rs.
1518.40
48.05
1092.80
385.00
370.00
3245.00
1180.00
1475.00
4793.75
295.00
3976.78
994.20
19373.98
0.50
Quantity
8.00
8.00
0.50
0.50
8.00
8.00
Quantity
Hour
Hour
Hour
Day
Day
8.00
0.50
8.00
1.00
1.00
Rate
in Rs.
189.80
96.10
136.60
385.00
370.00
Day
Day
Day
Day
Day
sqm
25%
11.00
4.00
5.00
16.25
1.00
52.81
295.00
295.00
295.00
295.00
295.00
75.30
Rs:
1192.20
0.14 166.90
1359.10
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum
Total
14.00% Rs:
16.25 cum
Rs:
(A+B+C+D)/16.25
Rs.
Rs:
Rs:
Rs:
Rs:
58198.60
1390.95
19373.98
78963.53
11054.89
90018.42
5539.60
IRR-CCDW-2-21 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than
15 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates with placing and sinking plums of size 150 to 80 mm upto 15 percent for gravity
type retaining walls / piers / abutments etc., including cost of all materials, machinery,
labour, formwork, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating,
finishing, curing etc.,complete with initial lead upto 50 m and all lifts.
Note:
If water is to be brought from other place add only lead charges @ 500 ltr / cum.
(Cement content: 260 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.765cum, Blending Ratio of CA--50:30:20, FA : 0.34 cum,
plums of size 150 to 80 mm : 0.25cum )
DATA:
RATE ANALYSIS
UNIT :
18.09 cum
255
A. MATERIALS:
Sl No
1
2
3
4
5
6
Particulars
Unit
kg
kg
cum
cum
cum
cum
cum
kg
sqm
30%
B. MACHINERY:
Sl No
1
2
3
Description
Unit
Hour
Hour
Hour
Hour
Hour
Hour
C. LABOUR:
Sl No
1
2
3
4
5
6
Description
Unit
Quantity
4703.40
72.36
6.92
4.15
2.77
4.52
6.15
18.81
49.75
Quantity
8.00
8.00
0.50
0.50
8.00
8.00
Quantity
Rate
in Rs.
4.00
4.00
1145.00
1210.00
875.00
340.00
462.00
80.00
244.56
Rs:
Amount
in Rs.
18813.60
289.44
7922.74
5023.50
2421.80
1537.65
2841.58
1505.09
12166.44
3649.93
56171.78
Rate
in Rs.
53.50
85.30
10.20
85.30
8.20
32.20
Rs:
Amount
in Rs.
428.00
682.40
5.10
42.65
65.60
257.60
1481.35
Amount
in Rs.
1518.40
48.05
1092.80
385.00
370.00
3245.00
1180.00
1475.00
590.00
4537.10
590.00
295.00
3745.99
1123.80
20196.13
Hour
Hour
Hour
Day
Day
8.00
0.50
8.00
1.00
1.00
Rate
in Rs.
189.80
96.10
136.60
385.00
370.00
Day
Day
Day
Day
Day
Day
Day
sqm
30%
11.00
4.00
5.00
2.00
15.38
2.00
1.00
49.75
295.00
295.00
295.00
295.00
295.00
295.00
295.00
75.30
Rs:
1116.40
0.14 156.30
1272.70
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum
Total
14.00% Rs:
18.09 cum
Rs:
(A+B+C+D)/18.09
Rs.
Rs:
Rs:
Rs:
Rs:
56171.78
1481.35
20196.13
77849.26
10898.9
88748.16
4905.90
IRR-CCDW-2-22 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than
15 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard,graded
aggregates for cast in-situ pipes including cost of all materials, machinery, labour, cleaning,
batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete with
initial lead upto 50 m and all lifts.
Note:
If water is to be brought from other place add only lead charges @ 500 ltr / cum.
(Cement content: 260 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
256
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
Particulars
Unit
kg
kg
cum
cum
cum
cum
kg
sqm
15%
LS
B. MACHINERY:
Sl No
1
2
3
Description
Unit
Hour
Hour
Hour
Hour
Hour
Hour
C. LABOUR:
Sl No
1
2
3
4
5
6
UNIT :
Description
Unit
Quantity
3998.80
76.90
6.92
4.15
2.77
6.15
16.00
30.76
15.38 cum
Rate
in Rs.
4.00
4.00
1145.00
1210.00
875.00
462.00
80.00
256.79
41.00
Rs:
Amount
in Rs.
15995.20
307.60
7924.55
5024.65
2422.35
2842.22
1279.62
7898.93
1184.84
20.50
44900.45
Rate
in Rs.
53.50
85.30
10.20
85.30
7.60
21.50
Rs:
Amount
in Rs.
428.00
682.40
5.10
42.65
60.80
172.00
1390.95
Amount
in Rs.
1518.40
48.05
1092.80
385.00
370.00
3245.00
1180.00
885.00
4537.10
295.00
2316.23
347.43
16220.01
0.50
Quantity
8.00
8.00
0.50
0.50
8.00
8.00
Quantity
Hour
Hour
Hour
Day
Day
8.00
0.50
8.00
1.00
1.00
Rate
in Rs.
189.80
96.10
136.60
385.00
370.00
Day
Day
Day
Day
Day
sqm
15%
11.00
4.00
3.00
15.38
1.00
30.76
295.00
295.00
295.00
295.00
295.00
75.30
Rs:
1054.60
0.14 147.60
1202.20
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum
Total
14.00% Rs:
15.38 cum
Rs:
(A+B+C+D)/15.38
Rs.
Rs:
Rs:
Rs:
Rs:
44900.45
1390.95
16220.01
62511.41
8751.6
71263.01
4633.50
IRR-CCDW-2-23 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than
15 N / sq mm ) grade cement concrete using 80 mm down size approved, clean, hard, graded
aggregates for cast in-situ pipes including cost of all materials, labour, machinery, formwork,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
complete with initial lead upto 50 m and all lifts.
Note:
If water is to be brought from other place add only lead charges @ 500 ltr / cum.
(Cement content: 250 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.98cum, Blending Ratio of CA--35:30:20:15, FA : 0.35 cum)
257
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
Particulars
Unit
kg
kg
cum
cum
cum
cum
cum
kg
sqm
15%
B. MACHINERY:
Sl No
1
2
3
UNIT :
Description
Unit
Hour
Hour
Hour
Hour
Hour
Hour
C. LABOUR:
Sl No
Description
1
2
3
4
5
6
Unit
Quantity
3600.00
72.00
4.94
4.23
2.82
2.12
5.04
14.40
28.80
Quantity
8.00
8.00
0.50
0.50
8.00
8.00
Quantity
14.40 cum
Rate
in Rs.
4.00
4.00
635.00
1145.00
1210.00
875.00
462.00
80.00
256.79
Rs:
Amount
in Rs.
14400.00
288.00
3136.39
4847.47
3415.10
1852.20
2328.48
1152.00
7395.61
1109.34
39924.60
Rate
in Rs.
92.70
170.50
10.20
85.30
8.20
32.20
Rs:
Amount
in Rs.
741.60
1364.00
5.10
42.65
65.60
257.60
2476.55
Amount
in Rs.
1518.40
48.05
1092.80
385.00
370.00
3245.00
1180.00
885.00
4248.00
295.00
2168.64
325.30
15761.19
Hour
Hour
Hour
Day
Day
8.00
0.50
8.00
1.00
1.00
Rate
in Rs.
189.80
96.10
136.60
385.00
370.00
Day
Day
Day
Day
Day
sqm
15%
11.00
4.00
3.00
14.40
1.00
28.80
295.00
295.00
295.00
295.00
295.00
75.30
Rs:
1094.50
0.14 153.20
1247.70
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum
Total
14.00% Rs:
14.40 cum
Rs:
(A+B+C+D)/14.40
Rs.
Rs:
Rs:
Rs:
Rs:
39924.60
2476.55
15761.19
58162.34
8142.73
66305.07
4604.50
IRR-CCDW-2-24 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than
20 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
aggregates for deck slab & kerb including cost of all materials,machinery, labour, formwork,
scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc., complete with initial lead upto 50 m and all lifts.
Note:
If water is to be brought from other place add only lead charges @ 500 ltr / cum.
(Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
258
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
Particulars
Unit
kg
kg
cum
cum
cum
kg
sqm
250%
LS
B. MACHINERY:
Sl No
1
2
3
UNIT :
Description
Unit
Hour
Hour
Hour
Hour
Hour
Hour
C. LABOUR:
Sl No
Description
1
2
3
4
5
6
Unit
Quantity
5200.80
78.80
8.20
4.41
7.09
20.80
39.40
15.76 cum
Rate
in Rs.
4.00
4.00
1210.00
875.00
462.00
80.00
297.55
41.00
Rs:
Amount
in Rs.
20803.20
315.20
9916.19
3861.20
3276.50
1664.26
11723.55
29308.86
41.00
80909.96
Rate
in Rs.
53.50
85.30
10.20
85.30
7.60
21.50
Rs:
Amount
in Rs.
428.00
682.40
5.10
42.65
60.80
172.00
1390.95
Amount
in Rs.
1518.40
48.05
1092.80
770.00
370.00
3245.00
1180.00
1180.00
4649.20
295.00
2966.82
7417.05
24732.32
1.00
Quantity
8.00
8.00
0.50
0.50
8.00
8.00
Quantity
Hour
Hour
Hour
Day
Day
8.00
0.50
8.00
2.00
1.00
Rate
in Rs.
189.80
96.10
136.60
385.00
370.00
Day
Day
Day
Day
Day
sqm
250%
11.00
4.00
4.00
15.76
1.00
39.40
295.00
295.00
295.00
295.00
295.00
75.30
Rs:
1569.30
0.14 219.70
1789.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum
Total
14.00% Rs:
15.76 cum
Rs:
(A+B+C+D)/15.76
Rs.
Rs:
Rs:
Rs:
Rs:
80909.96
1390.95
24732.32
107033.23
14984.65
122017.88
7742.30
IRR-CCDW-2-25 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than
20 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
aggregates for columns and beams including cost of all materials, labour, machinery,
formwork, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating,
finishing, curing etc.,complete with initial lead upto 50 m and all lifts.
Note:
If water is to be brought from other place add only lead charges @ 500 ltr / cum.
(Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
259
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
Particulars
Unit
kg
kg
cum
cum
cum
kg
sqm
50%
LS
B. MACHINERY:
Sl No
1
2
3
UNIT :
Description
Unit
Hour
Hour
Hour
Hour
Hour
Hour
C. LABOUR:
Sl No
Description
1
2
3
4
5
6
Unit
Quantity
5200.80
78.80
8.20
4.41
7.09
20.80
78.80
15.76 cum
Rate
in Rs.
4.00
4.00
1210.00
875.00
462.00
80.00
244.56
41.00
Rs:
Amount
in Rs.
20803.20
315.20
9916.19
3861.20
3276.50
1664.26
19271.64
9635.82
41.00
68785.01
Rate
in Rs.
53.50
85.30
10.20
85.30
7.60
21.50
Rs:
Amount
in Rs.
428.00
682.40
5.10
42.65
60.80
172.00
1390.95
Amount
in Rs.
1518.40
48.05
1092.80
385.00
370.00
3245.00
1180.00
885.00
4649.20
295.00
5933.64
2966.82
22568.91
1.00
Quantity
8.00
8.00
0.50
0.50
8.00
8.00
Quantity
Hour
Hour
Hour
Day
Day
8.00
0.50
8.00
1.00
1.00
Rate
in Rs.
189.80
96.10
136.60
385.00
370.00
Day
Day
Day
Day
Day
sqm
50%
11.00
4.00
3.00
15.76
1.00
78.80
295.00
295.00
295.00
295.00
295.00
75.30
Rs:
1432.00
0.14 200.50
1632.50
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum
Total
14.00% Rs:
15.76 cum
Rs:
(A+B+C+D)/15.76
Rs.
Rs:
Rs:
Rs:
Rs:
68785.01
1390.95
22568.91
92744.87
12984.28
105729.15
6708.70
IRR-CCDW-2-26 Providing and laying insitu M- 20 ( 28 days cube compressive strength not less than 20 N /
sqmm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
aggregates for wearing coat including cost of all materials, machinery, labour, formwork,
cleaning, batching, mixing, placing in position in alternate panels, levelling, compacting,
finishing, curing, packing joints with asphalt mortar etc., complete with initial lead upto 50 m
and all lifts.
Note:
If water is to be brought from other place add only lead charges @ 500 ltr / cum. to the data
(Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
260
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
Particulars
Unit
kg
kg
cum
cum
cum
kg
sqm
LS
B. MACHINERY:
Sl No
1
2
3
Description
Unit
Hour
Hour
Hour
Hour
Hour
Hour
C. LABOUR:
Sl No
1
2
3
4
5
6
UNIT :
Description
Unit
Quantity
5200.80
78.80
8.20
4.41
7.09
20.80
7.88
5.00
Quantity
8.00
8.00
0.50
0.50
8.00
8.00
Quantity
Hour
Hour
Hour
Day
Day
8.00
0.50
8.00
2.00
1.00
Day
Day
Day
Day
Day
sqm
11.00
4.00
4.00
15.76
2.00
7.88
15.76 cum
Rate
in Rs.
4.00
4.00
1210.00
875.00
462.00
80.00
244.56
41.00
Rs:
Amount
in Rs.
20803.20
315.20
9916.19
3861.20
3276.50
1664.26
1927.16
205.00
41968.72
Rate
in Rs.
53.50
85.30
10.20
85.30
7.60
21.50
Rs:
Amount
in Rs.
428.00
682.40
5.10
42.65
60.80
172.00
1390.95
Rate
in Rs.
189.80
96.10
136.60
385.00
370.00
Amount
in Rs.
1518.40
48.05
1092.80
770.00
370.00
295.00
295.00
295.00
295.00
295.00
75.30
Rs:
3245.00
1180.00
1180.00
4649.20
590.00
593.36
15236.81
Rs:
Rs:
Rs:
Rs:
41968.72
1390.95
15236.81
58596.48
8203.51
66799.99
4238.60
966.80
0.14 135.40
1102.20
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum
Total
14.00% Rs:
15.76 cum
Rs:
(A+B+C+D)/15.76
Rs.
IRR-CCDW-2-27 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than
20 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
aggregates for troughs including cost of all materials, machinery, labour, formwork,
scaffolding, cleaning, batching, mixing, placing in position,levelling, vibrating, finishing, curing
etc., complete with initial lead upto 50 m and all lifts.
Note:
If water is to be brought from other place add only lead charges @ 500 ltr / cum. to the data
(Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
DATA:
RATE ANALYSIS
UNIT :
15.76 cum
A. MATERIALS:
261
Sl No
Particulars
Unit
kg
kg
cum
cum
cum
kg
sqm
25%
LS
2
3
4
5
6
B. MACHINERY:
Sl No
1
2
3
Description
Unit
Hour
Hour
Hour
Hour
Hour
Hour
C. LABOUR:
Sl No
Description
1
2
3
4
5
6
Unit
Quantity
5200.80
78.80
8.20
4.41
7.09
20.80
70.92
Rate
in Rs.
4.00
4.00
1210.00
875.00
462.00
80.00
244.56
41.00
Rs:
Amount
in Rs.
20803.20
315.20
9916.19
3861.20
3276.50
1664.26
17344.47
4336.12
20.50
61537.64
Rate
in Rs.
53.50
85.30
10.20
85.30
7.60
21.50
Rs:
Amount
in Rs.
428.00
682.40
5.10
42.65
60.80
172.00
1390.95
Amount
in Rs.
1518.40
48.05
1092.80
385.00
370.00
3245.00
1180.00
1475.00
4649.20
295.00
5340.28
1335.07
20933.80
0.50
Quantity
8.00
8.00
0.50
0.50
8.00
8.00
Quantity
Hour
Hour
Hour
Day
Day
8.00
0.50
8.00
1.00
1.00
Rate
in Rs.
189.80
96.10
136.60
385.00
370.00
Day
Day
Day
Day
Day
sqm
25%
11.00
4.00
5.00
15.76
1.00
70.92
295.00
295.00
295.00
295.00
295.00
75.30
Rs:
1328.30
0.14 186.00
1514.30
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum
IRR-CCDW-3
Total
14.00% Rs:
15.76 cum
Rs:
(A+B+C+D)/15.76
Rs.
Rs:
Rs:
Rs:
Rs:
61537.64
1390.95
20933.80
83862.39
11740.73
95603.12
6066.20
IRR-CCDW-3-1 Sinking RCC wells vertically for foundation of piers and abutments in all kinds of soil, sand
DATA:
Unit = Running meter
Taking output = 1m
diameter of well = 6.00m
(i)
Depth below bed level upto 3.0m
Rate of sinking = 0.50 m /hour
a) Labour
0.12 Mate (Mason Cl- ll )
345.00 day
41.40
1.00 Sinker ( skilled)
385.00 day
385.00
2.00 Sinking helper ( Semi skilled)
295.00 day
590.00
sub total (a)
1016.40
b) Machinery
262
2.00
(ii)
1039.40
3654.16
3654.20
644.40
306.20
199.00
2189.00
3205.40
448.76
1322.60
185.20
1507.80
a) Labour
0.15
1.25
2.50
345.00 day
385.00 day
295.00 day
51.75
481.25
737.50
1270.50
1559.10
966.60
459.30
298.50
3283.50
4554.00
637.56
5191.56
5191.60
1729.80
242.20
1972.00
IRR-CCDW-3-2 Filling foundation wells with sand in layers of 25 to 30 cm and compacting by watering,
ramming as directed including cost of all materials, machinery, labour etc., complete with
initial lead upto 50 m and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
Particulars
UNIT :
Unit
cum
Quantity
15.75
Description
Unit
Nill
Quantity
0.00
0.00
Description
work inspector
mazdoor
Unit
Day
Day
Quantity
0.25
4.00
15.00 cum
Rate
in Rs.
342.00
0.00
Rs:
Amount
in Rs.
5386.50
0.00
5386.50
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
370.00
295.00
Rs:
Amount
in Rs.
92.50
1180.00
1272.50
263
84.80
0.14 11.90
96.70
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum
IRR-CCDW-4
15.00 cum
(A+B+C+D)/15.0
Rs:
Rs:
Rs:
Rs:
Total
14.00% Rs:
Rs:
Rs.
5386.50
0.00
1272.50
6659.00
932.26
7591.26
506.10
MASONRY WORKS :
IRR-CCDW-4-1 Providing and constructing un-coursed rubble stone masonry with approved stones in
CM 1 : 4 proportion for sub-structure portions of return walls / abutments etc., including
cost of all materials, machinery, labour, scaffolding, cleaning, packing cement mortar, wedging
stone chips, curing etc., complete with initial lead upto 50 m and all lifts.
(Cement content: 143 kg / cum of masonry, rubble stones : 0.85cum, FA : 0.40 cum,
Stone Chips : 0.15 cum)
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
Particulars
Cement
Rubble stones
Stone chips
Sand (Screened)
UNIT :
Unit
Quantity
kg
cum
cum
cum
1430.00
8.50
1.50
4.00
Description
Unit
Hour
Hour
Hour
Hour
C. LABOUR:
Sl No
Description
1
2
3
4
5
6
Unit
Quantity
1.00
1.00
0.50
0.50
Quantity
Hour
Hour
Day
Day
Day
1.00
0.50
1.00
1.00
2.00
Day
Day
Day
Day
Day
Day
4.00
2.00
1.00
3.00
1.00
4.00
10.00 cum
Rate
in Rs.
4.00
318.00
340.00
606.00
Rs:
Amount
in Rs.
5720.00
2703.00
510.00
2424.00
11357.00
Rate
in Rs.
402.50
322.20
10.20
85.30
Rs:
Amount
in Rs.
402.50
322.20
5.10
42.65
772.45
Rate
in Rs.
153.10
96.10
370.00
385.00
345.00
Amount
in Rs.
153.10
48.05
370.00
385.00
690.00
295.00
295.00
295.00
295.00
295.00
295.00
Rs:
1180.00
590.00
295.00
885.00
295.00
1180.00
6071.15
Rs:
Rs:
Rs:
Rs:
11357.00
772.45
6071.15
18200.60
2548.08
607.10
0.14 85.00
692.10
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total
14.00% Rs:
264
10.00 cum
(A+B+C+D)/10.0
Rs:
Rs.
20748.68
2074.90
IRR-CCDW-4-2 Providing and constructing un-coursed rubble stone masonry with approved stones in
CM 1 : 4 proportion for super-structure portions of return walls / abutments etc., including
cost of all materials, machinery, labour, scaffolding, cleaning, packing cement mortar, wedging
stone chips, curing etc., complete with initial lead upto 50 m and all lifts.
(Cement content: 143 kg / cum of masonry, rubble stones : 0.85cum, FA : 0.40 cum,
Stone Chips : 0.15 cum)
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
Particulars
Cement
Rubble stones
Stone chips
Sand (Screened)
UNIT :
Unit
Quantity
kg
cum
cum
cum
1430.00
8.50
1.50
4.00
TOTAL
2.5%
Description
Unit
Hour
Hour
Hour
Hour
C. LABOUR:
Sl No
1
2
3
4
5
6
Description
Unit
Quantity
1.00
1.00
0.50
0.50
Quantity
Hour
Hour
Day
Day
Day
1.00
0.50
1.00
1.00
2.00
Day
Day
Day
Day
Day
Day
4.00
2.00
1.00
3.00
1.00
4.00
TOTAL
2.5%
10.00 cum
Rate
in Rs.
4.00
318.00
340.00
606.00
Rs:
Rs:
Rs:
Amount
in Rs.
5720.00
2703.00
510.00
2424.00
11357.00
283.93
11640.93
Rate
in Rs.
402.50
322.20
10.20
85.30
Rs:
Amount
in Rs.
402.50
322.20
5.10
42.65
772.45
Rate
in Rs.
153.10
96.10
370.00
385.00
345.00
Amount
in Rs.
153.10
48.05
370.00
385.00
690.00
295.00
295.00
295.00
295.00
295.00
295.00
Rs:
Rs:
Rs:
1180.00
590.00
295.00
885.00
295.00
1180.00
6071.15
151.78
6222.93
Rs:
Rs:
Rs:
Rs:
11640.93
772.45
6222.93
18636.30
2609.08
21245.38
2124.50
622.30
0.14 87.10
709.40
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum
10.00 cum
(A+B+C+D)/10.0
Total
14.00% Rs:
Rs:
Rs.
IRR-CCDW-4-3 Providing and constructing coursed rubble masonry second sort in CM 1:4 proportion with
stones from approved source including cost of all materials, machinery, labour, scaffolding,
ramps, cleaning, packing mortar, wedging stone chips, finishing, curing etc., complete with
265
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
UNIT :
Particulars
Unit
Cement
Header stones 25x25x45 cm
Khandki stones 25x25x30 cm
Rubble stones
Stone chips
Sand (Screened)
kg
Nos
Nos
cum
cum
cum
Quantity
1330.00
60.00
180.00
4.50
1.50
3.50
TOTAL
2.5%
Description
Unit
Hour
Hour
Hour
Hour
C. LABOUR:
Sl No
1
2
3
4
5
6
7
Description
Unit
Quantity
1.00
1.00
0.50
0.50
Quantity
Hour
Hour
Day
Day
Day
Day
1.00
0.50
1.00
3.00
1.00
2.00
Day
Day
Day
Day
Day
Day
4.00
3.00
1.00
3.00
1.00
2.00
TOTAL
2.5%
10.00 cum
Rate
in Rs.
4.00
39.00
16.00
318.00
340.00
606.00
Rs:
Rs:
Rs:
Amount
in Rs.
5320.00
2340.00
2880.00
1431.00
510.00
2121.00
14602.00
365.05
14967.05
Rate
in Rs.
402.50
322.20
10.20
85.30
Rs:
Amount
in Rs.
402.50
322.20
5.10
42.65
772.45
Rate
in Rs.
153.10
96.10
370.00
345.00
385.00
345.00
Amount
in Rs.
153.10
48.05
370.00
1035.00
385.00
690.00
295.00
295.00
295.00
295.00
295.00
295.00
Rs:
Rs:
Rs:
1180.00
885.00
295.00
885.00
295.00
590.00
6811.15
170.28
6981.43
Rs:
Rs:
Rs:
Rs:
14967.05
772.45
6981.43
22720.93
3180.93
25901.86
2590.20
698.10
0.14 97.70
795.80
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum
10.00 cum
(A+B+C+D)/10.0
Total
14.00% Rs:
Rs:
Rs.
IRR-CCDW-4-4 Providing and constructing coursed rubble masonry first sort in CM 1:4 proportion with
stones from approved source including cost of all materials, machinery, labour, scaffolding,
ramps, cleaning, packing mortar, wedging stone chips, finishing, curing etc., complete with
initial lead upto 50 m and initial lift upto 3 m.
(Cement content: 133 kg / cum of masonry, rubble stones : 0.45cum, FA : 0.35 cum,
Stone Chips : 0.15 cum, Khandki stones 25 x 25 x 30 cm : 180 Nos, Header stones
25 x 25x 45 cm : 60 Nos)
266
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
UNIT :
Particulars
Unit
Cement
Header stones 25x25x45 cm
Khandki stones 25x25x30 cm
Rubble stones
Stone chips
Sand (Screened)
kg
Nos
Nos
cum
cum
cum
Quantity
1330.00
60.00
180.00
4.50
1.50
3.50
TOTAL
2.5%
Description
Unit
Hour
Hour
Hour
Hour
C. LABOUR:
Sl No
1
2
3
4
5
6
7
8
Description
Unit
Quantity
1.00
1.00
0.50
0.50
Quantity
Hour
Hour
Day
Day
Day
Day
1.00
0.50
1.00
6.00
1.00
2.00
Day
Day
Day
Day
Day
Day
4.00
3.00
1.00
3.00
1.00
2.00
TOTAL
2.5%
10.00 cum
Rate
in Rs.
4.00
39.00
16.00
318.00
340.00
606.00
Rs:
Rs:
Rs:
Amount
in Rs.
5320.00
2340.00
2880.00
1431.00
510.00
2121.00
14602.00
365.05
14967.05
Rate
in Rs.
402.50
322.20
10.20
85.30
Rs:
Amount
in Rs.
402.50
322.20
5.10
42.65
772.45
Rate
in Rs.
153.10
96.10
370.00
345.00
385.00
345.00
Amount
in Rs.
153.10
48.05
370.00
2070.00
385.00
690.00
295.00
295.00
295.00
295.00
295.00
295.00
Rs:
Rs:
Rs:
1180.00
885.00
295.00
885.00
295.00
590.00
7846.15
196.15
8042.30
Rs:
Rs:
Rs:
Rs:
14967.05
772.45
8042.30
23781.80
3329.45
27111.25
2711.10
804.20
0.14 112.60
916.80
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum
10.00 cum
(A+B+C+D)/10.0
Total
14.00% Rs:
Rs:
Rs.
IRR-CCDW-4-5 Providing cement mortar pointing to coursed rubble face stone masonry in CM 1 : 2
proportion by volume including raking and cleaning joints for 50 mm depth, pressing cement
mortar into joints, cost of all materials, labour, scaffolding, finishing, curing etc., complete with
initial lead upto 50 m and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
Cement
Particulars
UNIT :
Unit
kg
Quantity
456.00
100.00 sqm
Rate
in Rs.
4.00
Amount
in Rs.
1824.00
267
Sand (Screened)
cum
0.75
TOTAL
2.5%
Description
Quantity
Nil
( Manual mixing)
Total hire charges of Machinery
C. LABOUR:
Sl No
1
2
3
Unit
Description
0.00
0.00
Unit
Mason Cl- I
work inspector
mazdoor
Quantity
Day
Day
Day
10.00
1.00
10.00
606.00
Rs:
Rs:
Rs:
454.50
2278.50
56.96
2335.46
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
385.00
370.00
295.00
Rs:
Amount
in Rs.
3850.00
370.00
2950.00
7170.00
Rs:
Rs:
Rs:
Rs:
2335.46
0.00
7170.00
9505.46
1330.76
10836.22
108.40
71.70
0.14 10.00
81.70
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per sqm
Total
14.00% Rs:
100.00 sqm
Rs:
(A+B+C+D)/100.0
Rs.
IRR-CCDW-4-6 Providing cement mortar pointing to coursed rubble face stone masonry in CM 1 : 3
proportion by volume including raking and cleaning joints for 50 mm depth, pressing cement
mortar into joints, cost of all materials, labour, scaffolding, finishing, curing etc., complete with
initial lead upto 50 m and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
Particulars
Cement
Sand (Screened)
UNIT :
Unit
Quantity
kg
cum
322.00
0.75
TOTAL
2.5%
Unit
Quantity
Nil
( Manual mixing)
Total hire charges of Machinery
C. LABOUR:
Sl No
1
2
3
Description
Description
Mason Cl- I
work inspector
mazdoor
0.00
0.00
Unit
Quantity
Day
Day
Day
Total cost of Labour
10.00
1.00
10.00
100.00 sqm
Rate
in Rs.
4.00
606.00
Rs:
Rs:
Rs:
Amount
in Rs.
1288.00
454.50
1742.50
43.56
1786.06
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
385.00
370.00
295.00
Rs:
Amount
in Rs.
3850.00
370.00
2950.00
7170.00
71.70
0.14 10.00
81.70
ABSTRACT:
268
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per sqm
Total
14.00% Rs:
100.00 sqm
Rs:
(A+B+C+D)/100.0
Rs.
Rs:
Rs:
Rs:
Rs:
1786.06
0.00
7170.00
8956.06
1253.85
10209.91
102.10
IRR-CCDW-4-7 Providing 12 mm thick plastering in cement mortar 1:3 proportion by volume including cost
of all materials, machinery, labour, scaffolding, cleaning joints, smooth finishing, curing etc.,
complete with initial lead upto 50 m and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
Particulars
UNIT :
Unit
Cement
Sand (Screened)
Quantity
kg
cum
629.00
1.32
TOTAL
2.5%
Description
Quantity
Nil
( Manual mixing)
Total hire charges of Machinery
C. LABOUR:
Sl No
1
2
3
Unit
Description
0.00
0.00
Unit
Mason Cl- I
work inspector
mazdoor
Quantity
Day
Day
Day
10.00
1.00
20.00
100.00 sqm
Rate
in Rs.
4.00
606.00
Rs:
Rs:
Rs:
Amount
in Rs.
2516.00
799.92
3315.92
82.90
3398.82
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
385.00
370.00
295.00
Rs:
Amount
in Rs.
3850.00
370.00
5900.00
10120.00
Rs:
Rs:
Rs:
Rs:
3398.82
0.00
10120.00
13518.82
1892.63
15411.45
154.10
101.20
0.14 14.20
115.40
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per sqm
Total
14.00% Rs:
100.00 sqm
Rs:
(A+B+C+D)/100.0
Rs.
IRR-CCDW-4-8 Providing 12 mm thick plastering in cement mortar 1:4 proportion by volume including cost
of all materials, machinery, labour, scaffolding, cleaning joints, smooth finishing, curing etc.,
complete with initial lead upto 50 m and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
Particulars
Cement
Sand (Screened)
Add for scaffolding / ramps etc @
Total cost of Materials
UNIT :
Unit
kg
cum
Quantity
472.00
1.32
TOTAL
2.5%
100.00 sqm
Rate
in Rs.
4.00
606.00
Rs:
Rs:
Rs:
Amount
in Rs.
1888.00
799.92
2687.92
67.20
2755.12
B. MACHINERY:
269
Sl No
Description
Quantity
Nil
( Manual mixing)
Total hire charges of Machinery
C. LABOUR:
Sl No
1
2
3
Unit
Description
0.00
0.00
Unit
Mason Cl- I
work inspector
mazdoor
Quantity
Day
Day
Day
10.00
1.00
20.00
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
385.00
370.00
295.00
Rs:
Amount
in Rs.
3850.00
370.00
5900.00
10120.00
Rs:
Rs:
Rs:
Rs:
2755.12
0.00
10120.00
12875.12
1802.52
14677.638
146.80
101.20
0.14 14.20
115.40
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per sqm
Total
14.00% Rs:
100.00 sqm
Rs:
(A+B+C+D)/100.0
Rs.
IRR-CCDW-4-9 Providing 20 mm thick plastering in cement mortar 1:3 proportion by volume including cost
of all materials, machinery, labour, scaffolding, cleaning joints, smooth finishing, curing etc.,
complete with initial lead upto 50 m and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
Particulars
Cement
Sand (Screened)
UNIT :
Unit
Quantity
kg
cum
1050.00
2.20
TOTAL
2.5%
Description
Quantity
Nil
( Manual mixing)
Total hire charges of Machinery
C. LABOUR:
Sl No
1
2
3
Unit
Description
Mason Cl- I
work inspector
mazdoor
0.00
0.00
Unit
Quantity
Day
Day
Day
Total cost of Labour
15.00
1.00
25.00
100.00 sqm
Rate
in Rs.
4.00
606.00
Rs:
Rs:
Rs:
Amount
in Rs.
4200.00
1333.20
5533.20
138.33
5671.53
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
385.00
370.00
295.00
Rs:
Amount
in Rs.
5775.00
370.00
7375.00
13520.00
Rs:
Rs:
Rs:
Rs:
5671.53
0.00
13520.00
19191.53
2686.81
21878.34
218.80
135.20
0.14 18.90
154.10
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per sqm
Total
14.00% Rs:
100.00 sqm
Rs:
(A+B+C+D)/100.0
Rs.
270
IRR-CCDW-4-10 Providing 20 mm thick plastering in cement mortar 1:4 proportion by volume including cost
of all materials, machinery, labour, scaffolding, cleaning joints, smooth finishing, curing etc.,
complete with initial lead upto 50 m and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
Particulars
UNIT :
Unit
Cement
Sand (Screened)
Quantity
kg
cum
788.00
2.20
TOTAL
2.5%
Description
Quantity
Nil
( Manual mixing)
Total hire charges of Machinery
C. LABOUR:
Sl No
1
2
3
Unit
Description
0.00
0.00
Unit
Mason Cl- I
work inspector
mazdoor
Quantity
Day
Day
Day
15.00
1.00
25.00
100.00 sqm
Rate
in Rs.
4.00
606.00
Rs:
Rs:
Rs:
Amount
in Rs.
3152.00
1333.20
4485.20
112.13
4597.33
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
385.00
370.00
295.00
Rs:
Amount
in Rs.
5775.00
370.00
7375.00
13520.00
Rs:
Rs:
Rs:
Rs:
4597.33
0.00
13520.00
18117.33
2536.43
20653.76
206.50
135.20
0.14 18.90
154.10
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per sqm
IRR-CCDW-5
Total
14.00% Rs:
100.00 sqm
Rs:
(A+B+C+D)/100.0
Rs.
IRR-CCDW-5-1 Providing and fixing 10 cm thick roughly dressed burnt stone slabs for coping set in
CM 1: 6 proportion by volume with pointing to joints in CM 1 : 3 proportion by volume including
cost of all materials, machinery, labour, finishing, curing etc., complete with initial lead upto
50 m and all lifts.
(Cement content: 7.5 kg / sqm, FA : 0.030 cum/sqm,
Burnt stone slab 10 cm thick 1.05 sqm/ sqm)
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
Particulars
Unit
Cement
Sand (Screened)
Burnt stone slab 10 cm thick
Total cost of Materials
kg
cum
sqm
B. MACHINERY:
Sl No
1
UNIT :
Description
Nil
( Manual mixing)
Total hire charges of Machinery
Unit
Quantity
75.00
0.30
10.50
Quantity
0.00
0.00
10.00 sqm
Rate
in Rs.
4.00
606.00
300.00
Rs:
Amount
in Rs.
300.00
181.80
3150.00
3631.80
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
271
C. LABOUR:
Sl No
1
2
3
4
Description
Unit
Mason Cl- II
Stone chiseller Cl- II
work inspector
mazdoor
Quantity
Day
Day
Day
Day
1.00
1.00
0.50
2.00
Rate
in Rs.
345.00
345.00
370.00
295.00
Rs:
Amount
in Rs.
345.00
345.00
185.00
590.00
1465.00
Rs:
Rs:
Rs:
Rs:
3631.80
0.00
1465.00
5096.80
713.55
5810.35
581.00
146.50
0.14 20.50
167.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per sqm
10.00 sqm
(A+B+C+D)/10.0
Total
14.00% Rs:
Rs:
Rs.
IRR-CCDW-5-2 Providing and fixing 10 cm thick one line dressed burnt stone slabs for coping set in
CM 1: 6 proportion by volume with pointing to joints in CM 1 : 3 proportion by volume including
cost of all materials, machinery, labour, finishing, curing etc., complete with initial lead upto
50 m and all lifts.
(Cement content: 7.5 kg / sqm, FA : 0.030 cum/sqm, Burnt stone slab 10 cm
thick 1.05 sqm/ sqm)
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
Particulars
Unit
Cement
Sand (Screened)
Burnt stone slab 10 cm thick
Total cost of Materials
kg
cum
sqm
B. MACHINERY:
Sl No
1
Description
Unit
Quantity
75.00
0.30
10.50
Quantity
Nil
( Manual mixing)
Total hire charges of Machinery
C. LABOUR:
Sl No
1
2
3
4
UNIT :
Description
Mason Cl- II
Stone chiseller Cl- I
work inspector
mazdoor
0.00
0.00
Unit
Quantity
Day
Day
Day
Day
Total cost of Labour
1.00
4.00
0.50
2.00
10.00 sqm
Rate
in Rs.
4.00
606.00
300.00
Rs:
Amount
in Rs.
300.00
181.80
3150.00
3631.80
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
345.00
385.00
370.00
295.00
Rs:
Amount
in Rs.
345.00
1540.00
185.00
590.00
2660.00
Rs:
Rs:
Rs:
Rs:
3631.80
0.00
2660.00
6291.80
880.85
7172.65
717.30
266.00
0.14 37.20
303.20
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per sqm
10.00 sqm
(A+B+C+D)/10.0
Total
14.00% Rs:
Rs:
Rs.
272
IRR-CCDW-5-3 Providing and fixing 10 cm thick two line dressed burnt stone slabs for coping set in
CM 1: 6 proportion by volume with pointing to joints in CM 1 : 3 proportion by volume including
cost of all materials, machinery, labour, finishing, curing etc., complete with initial lead upto
50 m and all lifts.
(Cement content: 7.5 kg / sqm, FA : 0.030 cum/sqm, Burnt stone slab 10 cm
thick 1.05 sqm/ sqm)
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
Particulars
Unit
Cement
Sand (Screened)
Burnt stone slab 10 cm thick
Total cost of Materials
kg
cum
sqm
B. MACHINERY:
Sl No
1
Description
Unit
Quantity
75.00
0.30
10.50
Quantity
Nil
( Manual mixing)
Total hire charges of Machinery
C. LABOUR:
Sl No
1
2
3
4
UNIT :
Description
0.00
0.00
Unit
Mason Cl- II
Stone chiseller Cl-I
work inspector
mazdoor
Quantity
Day
Day
Day
Day
1.00
8.00
0.50
2.00
10.00 sqm
Rate
in Rs.
4.00
606.00
300.00
Rs:
Amount
in Rs.
300.00
181.80
3150.00
3631.80
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
345.00
385.00
370.00
295.00
Rs:
Amount
in Rs.
345.00
3080.00
185.00
590.00
4200.00
Rs:
Rs:
Rs:
Rs:
3631.80
0.00
4200.00
7831.80
1096.45
8928.25
892.80
420.00
0.14 58.80
478.80
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per sqm
10.00 sqm
(A+B+C+D)/10.0
Total
14.00% Rs:
Rs:
Rs.
IRR-CCDW-5-4 Providing and laying insitu M-15 ( 28 days cube compressive strength not less than 15 N /
sqmm ) grade cement concrete using 20 mm down size approved clean, hard, graded
aggregates for coping slab including cost of all materials, machinery, labour, formwork,
cleaning surface, batching, mixing, placing in position, levelling, compacting, finishing, curing
etc., complete with initial lead upto 50 m and initial lift upto 3 m.
(Cement content: 300 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
UNIT :
Particulars
Unit
kg
kg
cum
cum
cum
kg
sqm
sqm
Quantity
4401.00
73.35
7.63
4.11
6.60
17.60
80.69
1.00
14.67 cum
Rate
in Rs.
4.00
4.00
1210.00
875.00
462.00
80.00
244.56
41.00
Rs:
Amount
in Rs.
17604.00
293.40
9230.36
3594.15
3049.89
1408.32
19732.64
41.00
54953.77
273
B. MACHINERY:
Sl No
1
2
3
Description
Unit
Hour
Hour
Hour
Hour
Hour
Hour
C. LABOUR:
Sl No
Description
Unit
1
2
3
4
5
6
Quantity
8.00
8.00
0.50
0.50
1.00
1.00
Quantity
Hour
Hour
Hour
Day
Day
8.00
0.50
1.00
1.00
1.00
Day
Day
Day
Day
Day
sqm
11.00
4.00
3.00
14.67
1.00
80.69
Rate
in Rs.
53.50
85.30
10.20
85.30
402.50
322.20
Rs:
Amount
in Rs.
428.00
682.40
5.10
42.65
402.50
322.20
1882.85
Rate
in Rs.
189.80
96.10
153.10
385.00
370.00
Amount
in Rs.
1518.40
48.05
153.10
385.00
370.00
295.00
295.00
295.00
295.00
295.00
75.30
Rs:
3245.00
1180.00
885.00
4327.65
295.00
6075.58
18482.78
Rs:
Rs:
Rs:
Rs:
54953.77
1882.85
18482.78
75319.40
10544.72
85864.12
5853.00
1259.90
0.14 176.40
1436.30
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum
Total
14.00% Rs:
14.67 cum
Rs:
(A+B+C+D)/14.67
Rs.
IRR-CCDW-5-5 Providing and constructing protective railing consisting of in-situ railing posts of size 15 x
15 cm at bottom, 10 x 10 cm at top and 75 cm height at 2 m centre to centre in M-20 grade
concrete using 20 mm down size graded aggregates and with each post reinforced by 4 Nos.
of 8 mm dia main bars embedded in kerb concrete for a depth of 40 cm and 5 Nos. of 6 mm
dia. stirrups including fixing 3 rows of 40 mm dia. GI pipes with one coat of red oxide primer
and two coats of synthetic enamel paint, cost of all materials, machinery, labour, formwork,
finishing, curing etc., complete with lead upto 50 m and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
7
8
Particulars
Unit
Cement
20-10 mm coarse aggregate
10-4.75 mm coarse aggregate
Fine aggregate (Un-Screened)
Reinforcement steel
40 mm dia GI pipes B class
Use rate of shuttering
Sundries ( paints/ binding wire etc )
Total cost of Materials
kg
cum
cum
cum
kg
Rm
sqm
LS
B. MACHINERY:
Sl No
1
UNIT :
Description
Nill
Unit
Quantity
30.00
0.04
0.02
0.04
16.39
30.00
3.00
4.00
Quantity
0.00
10.00 Rm
Rate
in Rs.
4.00
1210.00
875.00
462.00
46.50
290.00
244.56
41.00
Rs:
Amount
in Rs.
120.00
48.40
17.50
18.48
762.14
8700.00
733.69
164.00
10564.21
Rate
in Rs.
0.00
Amount
in Rs.
0.00
274
0.00
0.00
Rs:
0.00
0.00
Rate
in Rs.
385.00
450.00
370.00
295.00
345.00
345.00
Rs:
Amount
in Rs.
192.50
225.00
185.00
442.50
172.50
172.50
1390.00
Rs:
Rs:
Rs:
Rs:
10564.21
0.00
1390.00
11954.21
1673.59
13627.80
1362.80
Description
Unit
Mason Class I
Bar bender
work inspector
mazdoor
Painter Cl- II
Fitter shuttering
Quantity
Day
Day
Day
Day
Day
Day
0.50
0.50
0.50
1.50
0.50
0.50
139.00
0.14 19.50
158.50
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per Rm
IRR-CCDW-6
10.00 Rm
(A+B+C+D)/10.0
Total
14.00% Rs:
Rs:
Rs.
IRR-CCDW-6-1 Laying and jointing 300 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2
proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,
labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto
50 m and all lifts.
(Cement content: 9.9 kg / joint, FA : 0.01cum/joint, Hemp Yarn : 0.091kg/joint)
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
Particulars
Cement
Sand (Screened)
Hemp yarn
UNIT :
Unit
Quantity
kg
cum
kg
99.00
0.10
0.91
Description
Quantity
Nill
( Manual mixing )
Total hire charges of Machinery
C. LABOUR:
Sl No
1
2
3
Unit
Description
Mason Cl- II
work inspector
mazdoor
0.00
0.00
Unit
Quantity
Day
Day
Day
Total cost of Labour
2.00
1.00
3.00
10.00 Joints
Rate
in Rs.
4.00
606.00
72.00
Rs:
Amount
in Rs.
396.00
60.60
65.52
522.12
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
345.00
370.00
295.00
Rs:
Amount
in Rs.
690.00
370.00
885.00
1945.00
Rs:
Rs:
Rs:
Rs:
522.12
0.00
1945.00
2467.12
194.50
0.14 27.20
221.70
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
275
14.00% Rs:
10.00 Joints
Rs:
(A+B+C+D)/10.0
Rs.
345.4
2812.52
281.30
(1) For NP3 Class - 10% extra over the rates of NP2 Class
(2) For NP4 Class - 20% extra over the rates of NP2 Class
Note:
IRR-CCDW-6-2 Laying and jointing 450 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2
proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,
labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto
50 m and all lifts.
(Cement content: 17.4 kg / joint, FA : 0.022cum/joint, Hemp Yarn : 0.127kg/joint)
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
Particulars
UNIT :
Unit
Cement
Sand (Screened)
Hemp yarn
Quantity
kg
cum
kg
174.00
0.22
1.27
Description
Quantity
Nill
( Manual mixing )
Total hire charges of Machinery
C. LABOUR:
Sl No
1
2
3
Unit
Description
0.00
0.00
Unit
Mason Cl- II
work inspector
mazdoor
Quantity
Day
Day
Day
2.00
1.00
3.00
10.00 Joints
Rate
in Rs.
4.00
606.00
72.00
Rs:
Amount
in Rs.
696.00
133.32
91.44
920.76
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
345.00
370.00
295.00
Rs:
Amount
in Rs.
690.00
370.00
885.00
1945.00
Rs:
Rs:
Rs:
Rs:
920.76
0.00
1945.00
2865.76
401.21
3266.97
326.70
194.50
0.14 27.20
221.70
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per joint
Total
14.00% Rs:
10.00 Joints
Rs:
(A+B+C+D)/10.0
Rs.
(1) For NP3 Class - 10% extra over the rates of NP2 Class
(2) For NP4 Class - 20% extra over the rates of NP2 Class
Note:
IRR-CCDW-6-3 Laying and jointing 600 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2
proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,
labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto
50 m and all lifts.
(Cement content: 24.8 kg / joint, FA : 0.025cum/joint, Hemp Yarn : 0.22kg/joint)
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
Particulars
Cement
Sand (Screened)
Hemp yarn
UNIT :
Unit
kg
cum
kg
Quantity
248.00
0.25
2.20
10.00 Joints
Rate
in Rs.
4.00
606.00
72.00
Rs:
Amount
in Rs.
992.00
151.50
158.40
1301.90
276
B. MACHINERY:
Sl No
1
Description
Quantity
Nill
( Manual mixing )
Total hire charges of Machinery
C. LABOUR:
Sl No
1
2
3
Unit
Description
0.00
0.00
Unit
Mason Cl- II
work inspector
mazdoor
Quantity
Day
Day
Day
2.50
1.00
4.00
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
345.00
370.00
295.00
Rs:
Amount
in Rs.
862.50
370.00
1180.00
2412.50
Rs:
Rs:
Rs:
Rs:
1301.90
0.00
2412.50
3714.40
520.02
4234.42
423.40
241.30
0.14 33.80
275.10
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per joint
Total
14.00% Rs:
10.00 Joints
Rs:
(A+B+C+D)/10.0
Rs.
(1) For NP3 Class - 10% extra over the rates of NP2 Class
(2) For NP4 Class - 20% extra over the rates of NP2 Class
Note:
IRR-CCDW-6-4 Laying and jointing 700 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2
proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,
labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto
50 m and all lifts.
(Cement content: 32.1 kg / joint, FA : 0.031cum/joint, Hemp Yarn : 0.25kg/joint)
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
Particulars
Cement
Sand (Screened)
Hemp yarn
UNIT :
Unit
Quantity
kg
cum
kg
321.00
0.31
2.50
Description
Quantity
Nill
( Manual mixing )
Total hire charges of Machinery
C. LABOUR:
Sl No
1
2
3
Unit
Description
Mason Cl- II
work inspector
mazdoor
0.00
0.00
Unit
Quantity
Day
Day
Day
Total cost of Labour
2.50
1.00
4.00
10.00 Joints
Rate
in Rs.
4.00
606.00
72.00
Rs:
Amount
in Rs.
1284.00
187.86
180.00
1651.86
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
345.00
370.00
295.00
Rs:
Amount
in Rs.
862.50
370.00
1180.00
2412.50
Rs:
Rs:
1651.86
0.00
241.30
0.14 33.80
275.10
277
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per joint
Rs:
Rs:
Total
14.00% Rs:
10.00 Joints
Rs:
(A+B+C+D)/10.0
Rs.
2412.50
4064.36
569.01
4633.37
463.30
(1) For NP3 Class - 10% extra over the rates of NP2 Class
(2) For NP4 Class - 20% extra over the rates of NP2 Class
Note:
IRR-CCDW-6-5 Laying and jointing 800 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2
proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,
labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto
50 m and all lifts.
(Cement content: 39.6 kg / joint, FA : 0.039cum/joint, Hemp Yarn : 0.31kg/joint)
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
Particulars
UNIT :
Unit
Cement
Sand (Screened)
Hemp yarn
Quantity
kg
cum
kg
396.00
0.39
3.10
Description
Quantity
Nill
( Manual mixing )
Total hire charges of Machinery
C. LABOUR:
Sl No
1
2
3
Unit
Description
0.00
0.00
Unit
Mason Cl- II
work inspector
mazdoor
Quantity
Day
Day
Day
3.00
1.00
5.00
10.00 Joints
Rate
in Rs.
4.00
606.00
72.00
Rs:
Amount
in Rs.
1584.00
236.34
223.20
2043.54
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
345.00
370.00
295.00
Rs:
Amount
in Rs.
1035.00
370.00
1475.00
2880.00
Rs:
Rs:
Rs:
Rs:
2043.54
0.00
2880.00
4923.54
689.3
5612.84
561.30
288.00
0.14 40.30
328.30
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per joint
Total
14.00% Rs:
10.00 Joints
Rs:
(A+B+C+D)/10.0
Rs.
(1) For NP3 Class - 10% extra over the rates of NP2 Class
(2) For NP4 Class - 20% extra over the rates of NP2 Class
Note:
IRR-CCDW-6-6 Laying and jointing 900 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2
proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,
labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto
50 m and all lifts.
(Cement content: 44.6 kg / joint, FA : 0.045cum/joint, Hemp Yarn : 0.34kg/joint)
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
Cement
Sand (Screened)
Particulars
UNIT :
Unit
kg
cum
Quantity
446.00
0.45
10.00 Joints
Rate
in Rs.
4.00
606.00
Amount
in Rs.
1784.00
272.70
278
Hemp yarn
kg
3.40
72.00
Rs:
244.80
2301.50
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
345.00
370.00
295.00
Rs:
Amount
in Rs.
1035.00
370.00
1475.00
2880.00
Rs:
Rs:
Rs:
Rs:
2301.50
0.00
2880.00
5181.50
725.41
5906.91
590.70
Description
Quantity
Nill
( Manual mixing )
Total hire charges of Machinery
C. LABOUR:
Sl No
1
2
3
Unit
Description
0.00
0.00
Unit
Mason Cl- II
work inspector
mazdoor
Quantity
Day
Day
Day
3.00
1.00
5.00
288.00
0.14 40.30
328.30
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per joint
Total
14.00% Rs:
10.00 Joints
Rs:
(A+B+C+D)/10.0
Rs.
(1) For NP3 Class - 10% extra over the rates of NP2 Class
(2) For NP4 Class - 20% extra over the rates of NP2 Class
Note:
IRR-CCDW-6-7 Laying and jointing 1000 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2
proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,
labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto
50 m and all lifts.
(Cement content: 49.5 kg / joint, FA : 0.05cum/joint, Hemp Yarn : 0.377kg/joint)
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
Particulars
Cement
Sand (Screened)
Hemp yarn
UNIT :
Unit
Quantity
kg
cum
kg
495.00
0.50
3.77
Unit
Quantity
Nill
( Manual mixing )
Total hire charges of Machinery
C. LABOUR:
Sl No
1
2
3
Description
Description
Mason Cl- II
work inspector
mazdoor
0.00
0.00
Unit
Quantity
Day
Day
Day
Total cost of Labour
3.00
1.00
6.00
10.00 Joints
Rate
in Rs.
4.00
606.00
72.00
Rs:
Amount
in Rs.
1980.00
303.00
271.44
2554.44
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
345.00
370.00
295.00
Rs:
Amount
in Rs.
1035.00
370.00
1770.00
3175.00
317.50
0.14 44.50
362.00
ABSTRACT:
279
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per joint
Rs:
Rs:
Rs:
Rs:
Total
14.00% Rs:
10.00 Joints
Rs:
(A+B+C+D)/10.0
Rs.
2554.44
0.00
3175.00
5729.44
802.12
6531.56
653.20
(1) For NP3 Class - 10% extra over the rates of NP2 Class
(2) For NP4 Class - 20% extra over the rates of NP2 Class
Note:
IRR-CCDW-6-8 Laying and jointing 1100 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2
proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,
labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto
50 m and all lifts.
(Cement content: 56.9 kg / joint, FA : 0.058cum/joint, Hemp Yarn : 0.415kg/joint)
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
Particulars
UNIT :
Unit
Cement
Sand (Screened)
Hemp yarn
Quantity
kg
cum
kg
569.00
0.58
4.15
Description
Quantity
Nill
( Manual mixing )
Total hire charges of Machinery
C. LABOUR:
Sl No
1
2
3
Unit
Description
0.00
0.00
Unit
Mason Cl- II
work inspector
mazdoor
Quantity
Day
Day
Day
3.00
1.00
6.00
10.00 Joints
Rate
in Rs.
4.00
606.00
72.00
Rs:
Amount
in Rs.
2276.00
351.48
298.80
2926.28
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
345.00
370.00
295.00
Rs:
Amount
in Rs.
1035.00
370.00
1770.00
3175.00
Rs:
Rs:
Rs:
Rs:
2926.28
0.00
3175.00
6101.28
854.18
6955.46
695.50
317.50
0.14 44.50
362.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per joint
Total
14.00% Rs:
10.00 Joints
Rs:
(A+B+C+D)/10.0
Rs.
(1) For NP3 Class - 10% extra over the rates of NP2 Class
(2) For NP4 Class - 20% extra over the rates of NP2 Class
Note:
IRR-CCDW-6-9 Laying and jointing 1200 mm dia. NP- 2 class or IRC standard hume pipes in CM 1 : 2
proportion by volume including cost of all materials ( excluding pipes and collars ), machinery,
labour, aligning, packing joints with hemp, finishing, curing etc., complete with initial lead upto
50 m and all lifts.
(Cement content: 66.8 kg / joint, FA : 0.069cum/joint, Hemp Yarn : 0.453kg/joint)
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
UNIT :
Unit
Quantity
10.00 Joints
Rate
in Rs.
Amount
in Rs.
280
1
2
3
Cement
Sand (Screened)
Hemp yarn
kg
cum
kg
668.00
0.69
4.53
4.00
606.00
72.00
Rs:
2672.00
418.14
326.16
3416.30
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
345.00
370.00
295.00
Rs:
Amount
in Rs.
1380.00
370.00
2065.00
3815.00
Rs:
Rs:
Rs:
Rs:
3416.30
0.00
3815.00
7231.30
1012.38
8243.68
824.40
Description
Quantity
Nill
( Manual mixing )
Total hire charges of Machinery
C. LABOUR:
Sl No
1
2
3
Unit
Description
0.00
0.00
Unit
Mason Cl- II
work inspector
mazdoor
Quantity
Day
Day
Day
4.00
1.00
7.00
381.50
0.14 53.40
434.90
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per joint
Total
14.00% Rs:
10.00 Joints
Rs:
(A+B+C+D)/10.0
Rs.
(1) For NP3 Class - 10% extra over the rates of NP2 Class
(2) For NP4 Class - 20% extra over the rates of NP2 Class
Note:
IRR-CCDW-7
IRR-CCDW-7-1 Providing rubble / boulder and sand filling behind abutment and return walls in layers
including cost of all materials, machinery, labour, watering, ramming etc., complete with initial
lead upto 50 m and initial lift upto 3 m.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
Particulars
Rubble / Boulder
Sand for filling
UNIT :
Unit
Quantity
cum
cum
10.00
4.00
Unit
Quantity
Nill
( Manual mixing )
Total hire charges of Machinery
C. LABOUR:
Sl No
1
2
3
Description
Description
work inspector
Mason Cl II
mazdoor
0.00
0.00
Unit
Quantity
Day
Day
Day
Total cost of Labour
0.50
1.00
4.00
10.00 cum
Rate
in Rs.
318.00
342.00
Rs:
Amount
in Rs.
3180.00
1368.00
4548.00
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
370.00
345.00
295.00
Rs:
Amount
in Rs.
185.00
345.00
1180.00
1710.00
171.00
0.14 23.90
194.90
281
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum
10.00 cum
(A+B+C+D)/10.0
Total
14.00% Rs:
Rs:
Rs.
Rs:
Rs:
Rs:
Rs:
4548.00
0.00
1710.00
6258.00
876.12
7134.12
713.40
IRR-CCDW-7-2 Providing and filling murrum / gravely soil ( CNS soil ) for foundation or around pipes
including breaking clods, spreading in layers of 10 to 15 cm, watering, compaction by earth
masters to achieve density control of not less than 95 percent etc., complete with lead
upto 50 m and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
Particulars
UNIT :
Unit
Murum
Quantity
cum
12.00
0.00
Description
Unit
Quantity
Nill
0.00
0.00
Description
Unit
1
2
3
Quantity
Day
Day
Day
0.50
0.50
6.00
10.00 cum
Rate
in Rs.
107.00
0.00
Rs:
Amount
in Rs.
1284.00
0.00
1284.00
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
395.00
370.00
295.00
Rs:
Amount
in Rs.
197.50
185.00
1770.00
2152.50
Rs:
Rs:
Rs:
Rs:
1284.00
0.00
2152.50
3436.50
481.11
3917.61
391.80
215.30
0.14 30.10
245.40
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum
10.00 cum
(A+B+C+D)/10.0
Total
14.00% Rs:
Rs:
Rs.
IRR-CCDW-7-3 Providing and filling murum / gravely soil ( CNS soil ) for foundation or above pipes
including breaking clods, spreading in layers of 10 to 15 cm, watering, compaction by power
roller to achieve density control of not less than 98 percent etc., complete with lead upto
50 m and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
Particulars
Murum
UNIT :
Unit
cum
Quantity
12.00
0.00
Description
Unit
Quantity
10.00 cum
Rate
in Rs.
107.00
0.00
Rs:
Amount
in Rs.
1284.00
0.00
1284.00
Rate
Amount
282
C. LABOUR:
Sl No
Description
Hour
Hour
Unit
1
2
3
4
0.17
0.17
Quantity
Hour
Day
Day
Day
0.17
0.50
0.50
1.50
in Rs.
197.20
767.30
Rs:
in Rs.
33.65
130.94
164.59
Rate
in Rs.
182.20
395.00
370.00
295.00
Rs:
Amount
in Rs.
31.09
197.50
185.00
442.50
856.09
Rs:
Rs:
Rs:
Rs:
1284.00
164.59
856.09
2304.68
322.66
2627.34
262.70
85.60
0.14 12.00
97.60
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per cum
10.00 cum
(A+B+C+D)/10.0
Total
14.00% Rs:
Rs:
Rs.
IRR-CCDW-7-4 Providing and fixing one line dressed 111x35x25 cm thick IRC standard kilometre stone in
cement concrete M-10 grade with 40 mm down size aggregates including excavating pit of
size 70x45x40 cm, embedding the stone by 30 cm in concrete, providing 2 coats synthetic
enamel paint of approved quality and colour to exposed surfaces and lettering as directed, cost
of all materials, labour, finishing, curing etc., complete with initial lead upto 50 m and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
7
8
Particulars
Unit
No.
cum
cum
cum
cum
kg
ltr
LS
B. MACHINERY:
Sl No
1
Description
Unit
Quantity
4.00
0.20
0.15
0.10
0.20
100.00
1.00
4.00
Quantity
NIL
( Manual mixing )
Total hire charges of Machinery
C. LABOUR:
Sl No
1
2
3
4
UNIT :
Description
Mason Cl- II
work inspector
mazdoor
Painter Cl- I
0.00
0.00
Unit
Quantity
Day
Day
Day
Day
Total cost of Labour
1.00
1.00
1.00
1.00
4 Nos.
Rate
in Rs.
450.00
1145.00
1210.00
875.00
462.00
4.00
240.00
41.00
Rs:
Amount
in Rs.
1800.00
229.00
181.50
87.50
92.40
400.00
240.00
164.00
3194.40
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
345.00
370.00
295.00
440.00
Rs:
Amount
in Rs.
345.00
370.00
295.00
440.00
1450.00
Rs:
3194.40
362.50
0.14 50.80
413.30
283
4.00 Nos.
(A+B+C+D)/4.0
Total
14.00% Rs:
Rs:
Rs.
Rs:
Rs:
Rs:
0.00
1450.00
4644.40
650.22
5294.62
1323.70
IRR-CCDW-7-5 Providing and fixing one line dressed 65x15x10 cm thick IRC standard hectometre stone in
cement concrete M-10 grade with 40 mm down size aggregates including excavating pit of
size 50x45x40 cm, embedding the stone by 30 cm in concrete, providing 2 coats synthetic
enamel paint of approved quality and colour to exposed surfaces and lettering as directed, cost
of all materials, labour, finishing, curing etc., complete with initial lead upto 50 m and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1
2
3
4
5
6
7
8
Unit
Quantity
No.
cum
cum
cum
cum
kg
ltr
LS
Unit
4.00
0.20
0.15
0.10
0.20
100.00
0.40
1.00
Quantity
NIL
( Manual mixing )
Total hire charges of Machinery
C. LABOUR:
Sl No
1
2
3
4
UNIT :
Description
Mason Cl- II
work inspector
mazdoor
Painter Cl- I
0.00
0.00
Unit
Quantity
Day
Day
Day
Day
Total cost of Labour
1.00
1.00
1.00
0.50
4 Nos.
Rate
in Rs.
240.00
1145.00
1210.00
875.00
462.00
4.00
240.00
41.00
Rs:
Amount
in Rs.
960.00
229.00
181.50
87.50
92.40
400.00
96.00
41.00
2087.40
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
345.00
370.00
295.00
440.00
Rs:
Amount
in Rs.
345.00
370.00
295.00
220.00
1230.00
Rs:
Rs:
Rs:
Rs:
2087.40
0.00
1230.00
3317.40
464.44
3781.84
945.50
307.50
0.14 43.10
350.60
4.00 Nos.
(A+B+C+D)/4.0
Total
14.00% Rs:
Rs:
Rs.
284
CHAPTER-V
HYDRAULIC GATES AND ALLIED EQUIPMENT - Standard Data
2014-15
IRR-GAW
1
All materials / bought out components for embedded parts, gates, hoists and allied works
shall conform to relevant Indian standards / technical specifications and approved drawings.
The basic rates are EXCLUSIVEof preparation of designs / drawings / material schedules etc.,
as per specifications and other technical data including revisions.
If designs &drawings are to be done by private agency 2% of estimated cost be added
The basic rates are inclusive of cost of all materials, machinery, labour, fabrication, erection,
commissioning and testing of gates, hoists and other related components as per technical
specifications.
The basic rates are inclusive of finishing, wastage of materials , incidental works, temperary
supports, all enabling works, profit, overheads, small tools / plants, hidden cost
on labour etc.
The basic rates are inclusive of taxes, duties (excise ), levies and all other incidental charges including
turn over tax/sales tax on works contract. Separate provision shall be made in the estimate towards such
tax on works contract at the rate prevailing at the time of preparation of estimate.
The basic rates are inclusive of all leads and lifts including rehandling.
The basic rates are inclusive of preparatory works such as rectification of damages, repairing
shop painting, cleaning, positioning and anchoring first stage embedments,
The basic rates are not inclusive of painting with or without sand blasting,and are to be added to the rate as
perschedule rates formulated in the same chapter as per applicability and specifications
10
The basic rates are exclusive of cost of river diversion arrangements, dewatering, desilting ,secondary concreting
of EM parts etc., which form part of civil works.
11
12
Add AREA ALLOWANCES AS APPLICABLE ON LABOUR COMPONENT ONLY ( SHOWN UNDER EACH ITEM)
13
14
Painting Charges added extra to the data items as per applicability wherver necessary
15
HOIST EQUIPMENT1.-where sand blasting is not possible, hand and power tool cleaning be
adopted - Guidance may be taken from Mechanical workshop in this regard
2. Machined surfaces should not be painted
3. for maintenance unless sand blasting is essential hand and power tool cleaning be adopted
Painting of Hoast Gates is to be done as per IS 14177:1994
16
TYPES OF GATES:
IRR-GAW-1
A. SPILLWAY RADIAL GATES
IRR-GAW-1-1 E.M Parts and anchorages
fabrication, supply, erection, testing and commissioning of Embedded parts for radial gate
consists of sill beam, wall plates, anchor girders , yoke girders, tie flats, trunnion supports etc., including
285
cost of all materials, machinery, labour, welding, finishing, with leads and lifts &all accessories
(without painting on sand-blasted or mechanical cleaning surfaces which are added extra
as perscedule of rates under itemsinthis chapter and add as applicable separately)
Drawing no. MD/CDO/VRSP/90-92/85-86 (Vengalaraya Sagar - Gomukhi Project)
Vent Size:
DATA:
RATE ANALYSIS
Sl No
1
2
3
4
5
6
7
8
9
10
11
12
A. MATERIALS:
particulars
Str steel angle / beam / channel / bars
Structural steel plate / flats
Stainless steel plate / flats
MS bolts and nuts
Oxygen gas
Acetyline gas
Welding electrodes
Welding electrodes ( LH )
Welding electrodes ( stainless steel )
Use rate welding holder set
Use rate gas cutting torch set
Sundries
B. MACHINERY:
Sl No
1
2
3
4
5
6
7
8
9
10
11
Welding transformer
Fuel / Energy charges
Tower crane/heavy duty tyre mounted
crane
Fuel / Energy charges
Plate shearing machine
Fuel / Energy charges
Pug cutting machine
Fuel / Energy charges
Mobile crane 16 Tonnes
Fuel / Energy charges
Stationery derric crane
Fuel / Energy charges
Grinding machine
Fuel / Energy charges
Drilling machines
Fuel / Energy charges
Planing machine
Fuel / Energy charges
Bending Machine
Fuel / Energy charges
Sundries
Total hire charges of Machinery
C. LABOUR:
Sl No
1
2
3
4
5
6
7
8
9
10
11
12
Description
Description
Unit
UNIT :
Quantity
kg
3467.00
kg
11261.00
kg
515.00
kg
48.00
cum
158.00
cum
53.00
Nos
11520.00
Nos
2880.00
Nos
1160.00
Hour
1945.00
Hour
158.00
LS
100.00
Total cost of Materials
Unit
Quantity
Hour
Hour
1945.00
1945.00
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS
16.00
16.00
16.00
16.00
76.00
76.00
22.00
22.00
64.00
64.00
30.00
30.00
30.00
30.00
100.00
100.00
30.00
30.00
100.00
Unit
Hour
Hour
Hour
Hour
Hour
Hour
Day
Day
Day
Day
Day
Quantity
16.00
22.00
16.00
100.00
30.00
30.00
30.00
15.00
75.00
20.00
212.00
48.00
15.300 tonne
Rate
in Rs.
45.00
46.00
275.00
90.00
52.00
320.00
11.00
18.00
26.00
7.35
23.67
41.00
Rs:
Amount
in Rs.
156015.00
518006.00
141625.00
4320.00
8216.00
16960.00
126720.00
51840.00
30160.00
14295.75
3740.12
4100.00
1075997.87
Rate
in Rs.
16.00
91.30
Amount
in Rs.
31120.00
177578.50
867.10
197.80
41.90
152.20
6.40
3.80
2278.10
75.00
86.10
0.00
22.50
38.00
22.50
38.00
117.80
114.10
42.60
114.10
41.00
Rs:
13873.60
3164.80
670.40
2435.20
486.40
288.80
50118.20
1650.00
5510.40
0.00
675.00
1140.00
675.00
1140.00
11780.00
11410.00
1278.00
3423.00
4100.00
322517.30
Rate
in Rs.
163.30
454.30
122.50
182.20
171.60
171.60
113.90
440.00
440.00
385.00
385.00
440.00
Amount
in Rs.
2612.80
9994.60
1960.00
18220.00
5148.00
5148.00
3417.00
6600.00
33000.00
7700.00
81620.00
21120.00
286
13
14
15
Khalasi
Helper fabrication / erection
Electrician
Day
345.00
Day
255.00
Day
5.00
Total cost of Labour
Add towards highly skilled labour charges @ 30% on total cost of labour
Total Cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
385.00
345.00
440.00
Rs:
132825.00
87975.00
2200.00
419540.40
125862.12
545402.52
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
1075997.87
322517.30
545402.52
1943917.69
0.00
1943917.69
58317.53
2002235.22
280312.93
35647.20
0.14 4990.60
40637.80
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0.00%
Total
3%
14%
R
581.4
1936.98
Rs:
2285066.54
Rs:
149350.80
15.300 tonne
Rate per tonne
RADIAL GATES
A-2
Gates
IRR-GAW-1-2 fabrication, supply, erection, testing and commissioning of radial gate consisting
of skin plate, stiffeners, horizontal girders, radial arms, trunnion assemblies, tie beam, pulley
supports, bracings, rubber seals, clamps etc., with all accessories for spillway/canals including cost
of all materials, machinery, labour, seal fixing etc., complete as per specifications and approved drawings
(without painting on sand-blasted or mechanical cleaning surfaces which are added extra
as perscedule of rates under itemsinthis chapter and add as applicable separately)
Drawing no. MD/CDO/VRSP/170-172/85-86(Vengalaraya Sagar - Gomukhi Project)
Vent Size: 12 X 6.6 Mtr
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
3
4
5
6
7
8
9
10
11
12
13
particulars
Structural steel :
Angles / beams / channels / bars
Plates / flats
Cast steel components :
Trunnion hubs / Guide rollers
Alluminium / Bronze alloy
components :
Bush for Trunnion / Guide roller
Bolt / Nut / Washer :
GI bolts / nuts / washers
Zinc/Babbit Metal
Rubber seals :
Bottom seal
Side seals ( Z - type )
Oxygen gas
Acetyline gas
Welding electrodes ( std )
Welding electrodes ( LH )
Use rate welding holder set
Use rate gas cutting torch set
Sundries
UNIT :
Unit
Quantity
29.000 tonne
Rate
in Rs.
Amount
in Rs.
kg
kg
9700.00
16850.00
45.00
46.00
436500.00
775100.00
kg
2100.00
180.00
378000.00
kg
350.00
912.00
319200.00
kg
kg
250.00
50.00
130.00
170.00
32500.00
8500.00
Rm
12.00
Rm
14.00
cum
228.00
cum
76.00
Nos
1000.00
Nos
250.00
Hour
156.00
Hour
228.00
LS
500.00
Total cost of Materials
759.00
1457.00
52.00
320.00
11.00
18.00
7.35
23.67
41.00
Rs:
9108.00
20398.00
11856.00
24320.00
11000.00
4500.00
1146.60
5397.14
20500.00
2058025.74
287
B. MACHINERY:
Sl No
1
2
3
4
5
6
7
8
9
10
11
Unit
Welding transformer
Fuel / Energy charges
Plate shearing machine
Fuel / Energy charges
Pug cutting machine
Fuel / Energy charges
Bending machine
Fuel / Energy charges
Tower crane 5 t cpacity
Fuel / Energy charges
Mobile derric crane
Fuel / Energy charges
Stationery derric crane
Fuel / Energy charges
Grinding machine
Fuel / Energy charges
Drilling machines
Fuel / Energy charges
Mobile Crane 30 T
Fuel / Energy charges
Sundries
Total hire charges of Machinery
C. LABOUR:
Sl No
1
2
3
4
5
6
7
8
9
10
11
12
13
Description
Quantity
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS
Description
156.00
156.00
29.00
29.00
114.00
114.00
116.00
116.00
29.00
29.00
58.00
58.00
58.00
58.00
58.00
58.00
58.00
58.00
100.00
100.00
500.00
Unit
Quantity
Hour
100.00
Hour
29.00
Hour
116.00
Hour
58.00
Hour
58.00
Day
29.00
Day
145.00
Day
29.00
Day
17.00
Day
5.00
Day
493.00
Day
667.00
Day
15.00
Total cost of Labour
Add towards highly skilled labour charges @ 30% on total cost of labour
Total Cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
Rate
in Rs.
16.00
91.30
41.90
152.20
6.40
3.80
42.60
114.10
867.10
197.80
519.70
322.20
86.10
0.00
22.50
38.00
22.50
38.00
3096.80
118.80
41.00
Rs:
Amount
in Rs.
2496.00
14242.80
1215.10
4413.80
729.60
433.20
4941.60
13235.60
25145.90
5736.20
30142.60
18687.60
4993.80
0.00
1305.00
2204.00
1305.00
2204.00
309680.00
11880.00
20500.00
475491.80
Rate
in Rs.
454.30
163.30
113.90
171.60
171.60
440.00
440.00
385.00
385.00
440.00
385.00
345.00
440.00
Rs:
Amount
in Rs.
45430.00
4735.70
13212.40
9952.80
9952.80
12760.00
63800.00
11165.00
6545.00
2200.00
189805.00
230115.00
6600.00
606273.70
181882.11
788155.81
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
2058025.74
475491.80
788155.81
3321673.35
0.00
3321673.35
99650.20
3421323.55
478985.30
27177.80
0.14 3804.90
30982.70
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0.00%
Total
3%
1102
3671.4
Rs:
3905082.25
Rs.
134658.00
288
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
Structural steel
Angles / beams / channels / bars
Plates / flats
Cast steel components :
Rope drums 2 Nos / Gears 4 Nos
Pinions
Pulleys 720 PCD 6 Nos
Plummer blocks / Hubs
Alloy steel components
Shafts
Pins
Bronze alloy components :
Bronze bearings / bush
Wire rope 36 mm dia 6/37
construction
MS Bolt / Nut / Washer
Worm reducers
Electric motor 20 hp
Floating shaft 300 mm dia
Manual operating system
Gate position indicator
Ele-magnetic brake
Electric cable / switch / control panel
etc
Oxygen gas
Acetyline gas
Welding electrodes
Welding electrodes ( LH )
Grease
Use rate welding holder set
Use rate gas cutting torch set
Sundries ( hand rail /staircase / gate et
B. MACHINERY:
Sl No
1
2
3
4
5
6
7
particulars
Description
Welding transformer
Fuel / Energy charges
Tower crane 5 t capacity
Fuel / Energy charges
Pug cutting machine
Fuel / Energy charges
Mobile derric crane
Fuel / Energy charges
Grinding machine
Fuel / Energy charges
Drilling machines
Fuel / Energy charges
Sundries
Total hire charges of Machinery
C. LABOUR:
Sl No
Description
UNIT :
Unit
Quantity
15.440 tonne wt
90.00 t capacity
Rate
Amount
in Rs.
in Rs.
kg
kg
2571.00
3632.00
45.00
46.00
115695.00
167072.00
kg
kg
kg
kg
3680.00
218.00
1080.00
322.00
220.00
210.00
180.00
180.00
809600.00
45780.00
194400.00
57960.00
kg
kg
557.00
546.00
210.00
420.00
116970.00
229320.00
kg
144.00
912.00
131328.00
kg
kg
No.
No.
kg
No.
No.
No.
448.00
85.00
1.00
1.00
1000.00
1.00
1.00
1.00
250.00
90.00
224400.00
121000.00
180.00
28820.00
195800.00
35200.00
112000.00
7650.00
224400.00
121000.00
180000.00
28820.00
195800.00
35200.00
LS
1.00
cum
213.00
cum
71.00
Nos
530.00
Nos
4776.00
kg
50.00
Hour
566.00
Hour
90.00
LS
200.00
Total cost of Materials
50380.00
52.00
320.00
11.00
18.00
260.00
7.35
23.67
41.00
Rs:
50380.00
11076.00
22720.00
5830.00
85968.00
13000.00
4160.10
2130.45
8200.00
2976459.55
Rate
in Rs.
16.00
91.30
867.10
197.80
6.40
3.80
519.70
322.20
22.50
38.00
22.50
38.00
41.00
Rs:
Amount
in Rs.
9056.00
32228.90
3468.40
791.20
339.20
201.40
25985.00
16110.00
180.00
304.00
360.00
608.00
4100.00
93732.10
Rate
in Rs.
Amount
in Rs.
Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS
Unit
Quantity
566.00
353.00
4.00
4.00
53.00
53.00
50.00
50.00
8.00
8.00
16.00
16.00
100.00
Quantity
289
1
2
3
4
5
50.00
4.00
16.00
8.00
35.00
153.10
163.30
171.60
171.60
440.00
7655.00
653.20
2745.60
1372.80
15400.00
Day
58.00
Day
18.00
Day
53.00
Day
20.00
Day
175.00
Day
3.00
Total cost of Labour
Add towards highly skilled labour charges @ 30% on total cost of labour
Total Cost of Labour
440.00
385.00
385.00
385.00
345.00
440.00
Rs:
25520.00
6930.00
20405.00
7700.00
60375.00
1320.00
150076.60
45022.98
195099.58
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
2976459.55
93732.10
195099.58
3265291.23
0.00
3265291.23
97958.74
3363249.97
470855.00
6
7
8
9
10
11
Hour
Hour
Hour
Hour
Day
2167.80
0.14 303.50
2471.30
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0.00%
Total
3%
14%
R
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
7
8
Structural steel
Angles / beams / channels / bars
Plates / flats
Chequered plates
MS bolts / nuts / washers
Oxygen gas
Acetyline gas
Welding electrodes
Use rate welding holder set
Use rate gas cutting torch set
Sundries
B. MACHINERY:
Sl No
1
particulars
Description
Welding transformer
UNIT :
Unit
Quantity
kg
4258.00
kg
98.00
kg
856.00
kg
8.00
cum
51.00
cum
17.00
Nos
1195.00
Hour
150.00
Hour
30.00
LS
10.00
Total cost of Materials
Unit
Hour
Quantity
150.00
5.22 MT
Rate
in Rs.
Amount
in Rs.
45.00
46.00
60.00
90.00
52.00
320.00
11.00
7.35
23.67
41.00
Rs:
191610.00
4508.00
51360.00
720.00
2652.00
5440.00
13145.00
1102.50
710.15
410.00
271657.65
Rate
in Rs.
16.00
Amount
in Rs.
2400.00
290
2
3
4
5
6
7
8
C. LABOUR:
Sl No
1
2
3
4
5
6
7
8
9
10
11
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS
Description
150.00
6.00
6.00
12.00
12.00
8.00
8.00
12.00
12.00
12.00
12.00
10.00
10.00
10.00
Unit
Quantity
Hour
10.00
Hour
6.00
Hour
12.00
Hour
12.00
Hour
10.00
Day
6.00
Day
25.00
Day
5.00
Day
20.00
Day
200.00
Day
2.00
Total cost of Labour
Add towards highly skilled labour charges @ 30% on total cost of labour
Total Cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
91.30
867.10
197.80
6.40
3.80
2278.10
75.00
22.50
38.00
22.50
38.00
42.60
114.10
41.00
Rs:
13695.00
5202.60
1186.80
76.80
45.60
18224.80
600.00
270.00
456.00
270.00
456.00
426.00
1141.00
410.00
44860.60
Rate
in Rs.
454.30
163.30
171.60
171.60
113.90
440.00
440.00
385.00
385.00
345.00
440.00
Rs:
Amount
in Rs.
4543.00
979.80
2059.20
2059.20
1139.00
2640.00
11000.00
1925.00
7700.00
69000.00
880.00
103925.20
31177.56
135102.76
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
271657.65
44860.60
135102.76
451621.01
0.00
451621.01
13548.63
465169.64
65123.75
25881.80
0.14 3623.50
29505.30
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0.00%
Total
3%
14%
R
198.36
660.852
Rs:
531152.60
Rs:
101753.40
5.22 MT
Rate per MT
IRR-GAW-2
VERTICAL LIFT GATES-EM PARTS
IRR-GAW-2-1 Design, fabrication, supply, erection and commissioning of embedded parts consisting of
sill beam, slide tracks, seal seats, guide rails, dogging sets for storage of stoplog elements
etc., with all accessories for spillway stop log gates and other vertical lift elements including cost of all materials,
machinery, labour, etc., complete as per specifications and approved drawings
(without painting on sand-blasted or mechanical cleaning surfaces which are added extra
as perscedule of rates under items in this chapter and add as applicable separately)
Drawing No. MD/CDO/GNCP/HR/1759,1760/94 (GNSS Project)
Vent Size:
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
particulars
UNIT :
Unit
Quantity
Amount
291
1
2
3
4
5
6
7
8
9
10
11
12
B. MACHINERY:
Sl No
1
2
3
4
5
6
7
8
9
10
1
2
3
4
5
6
7
8
9
10
11
12
Description
Welding transformer
Fuel / Energy charges
Plate shearing machine
Fuel / Energy charges
Pug cutting machine
Fuel / Energy charges
Planing machine
Fuel / Energy charges
Mobile Crane 16 T
Fuel / Energy charges
Stationery derric crane
Fuel / Energy charges
Grinding machine
Fuel / Energy charges
Drilling machines
Fuel / Energy charges
Bending Machine
Fuel / Energy charges
Sundries
Total hire charges of Machinery
C. LABOUR:
Sl No
kg
1885.00
kg
3890.00
kg
271.00
kg
50.00
cum
225.00
cum
75.00
Nos
1410.00
Nos
350.00
Nos
1320.00
Hour
385.00
Hour
225.00
LS
40.00
Total cost of Materials
Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS
Description
Quantity
385.00
385.00
8.00
8.00
110.00
110.00
270.00
270.00
24.00
24.00
14.00
14.00
14.00
14.00
21.00
21.00
14.00
14.00
40.00
Unit
Quantity
Hour
24.00
Hour
270.00
Hour
21.00
Hour
14.00
Hour
14.00
Day
32.00
Day
35.00
Day
9.00
Day
46.00
Day
6.00
Day
240.00
Day
4.00
Total cost of Labour
Add towards highly skilled labour charges @ 30% on total cost of labour
Total Cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
in Rs.
84825.00
178940.00
74525.00
4500.00
11700.00
24000.00
15510.00
6300.00
34320.00
2829.75
5326.13
1640.00
444415.88
Rate
in Rs.
16.00
91.30
41.90
152.20
6.40
3.80
117.80
114.10
2278.10
75.00
86.10
0.00
22.50
38.00
22.50
38.00
42.60
114.10
41.00
Rs:
Amount
in Rs.
6160.00
35150.50
335.20
1217.60
704.00
418.00
31806.00
30807.00
54674.40
1800.00
1205.40
0.00
315.00
532.00
472.50
798.00
596.40
1597.40
1640.00
170229.40
Rate
in Rs.
454.30
182.20
171.60
171.60
113.90
440.00
440.00
385.00
385.00
440.00
345.00
440.00
Rs:
Amount
in Rs.
10903.20
49194.00
3603.60
2402.40
1594.60
14080.00
15400.00
3465.00
17710.00
2640.00
82800.00
1760.00
205552.80
61665.84
267218.64
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
444415.88
170229.40
267218.64
881863.92
0.00
881863.92
42415.70
0.14 5938.20
48353.90
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for excise duty
(on 75 percent cost excluding cost of materials)
in Rs.
45.00
46.00
275.00
90.00
52.00
320.00
11.00
18.00
26.00
7.35
23.67
41.00
Rs:
Total
0.00%
Total
292
3%
Rs:
Rs:
Rs:
Total
F. Add for contractor's profit and overheads on (A+B
Add 2 leads
Add 1 km lead charges for fabricated parts
Unloading charges of fabricated parts Rs
Total cost for
14%
R
26455.92
908319.83
127164.78
239.4
797.58
Rs:
1036521.59
Rs:
164527.20
6.30 tonne
Rate per tonne
vertical lift gates and stop log gate elements ( SLIDING GATES)
IRR-GAW-2-2 Design, fabrication, supply, erection, testing and commissioning of vertical lift gates and
stoplog gate elements, consisting of skin plate,
horizontal and vertical girders, stiffeners, lifting pins, bronze padded slide blocks/bearings, guide shoes,
rubber seals, clamps etc., with all accessories including cost of all materials,
machinery, labour, seal fixing etc.,complete as per specifications and approved drawings
(without painting on sand-blasted or mechanical cleaning surfaces which are added extra
as perscedule of rates under items in this chapter and add as applicable separately)
Drawing NO. CE/CDO/CL3/MRP/783/2002 (Spillway Stop log gate Elements of Madduvalasa Project)
Vent Size: 12.624 X 0.50 M 16 Elements
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
7
8
9
10
11
Structural steel
Angles / beams / channels / bars
Plates / flats
Alloy steel components
Lifting pins
Bolt / Nut / Washer
GI bolts / nuts / washers
Rubber seals
Bottom seal
Side seals
Oxygen gas
Acetyline gas
Welding electrodes
Welding electrodes ( LH )
Use rate welding holder set
Use rate gas cutting torch set
Sundries
B. MACHINERY:
Sl No
1
2
3
4
5
6
7
8
particulars
Description
Welding transformer
Fuel / Energy charges
Pug cutting machine
Fuel / Energy charges
Mobile crane 16 T
Fuel / Energy charges
Stationery derric crane
Fuel / Energy charges
Grinding machine
Fuel / Energy charges
Drilling machines
Fuel / Energy charges
Bending Machine
Fuel / Energy charges
Sundries
Total hire charges of Machinery
C. LABOUR:
Sl No
Description
UNIT :
Unit
Quantity
119.000 tonne
Rate
in Rs.
Amount
in Rs.
kg
kg
5280.00
112880.00
45.00
46.00
237600.00
5192480.00
kg
520.00
420.00
218400.00
kg
600.00
130.00
78000.00
Rm
210.00
Rm
18.00
cum
2714.00
cum
905.00
Nos
86554.00
Nos
16486.00
Hour
12880.00
Hour
2714.00
LS
400.00
Total cost of Materials
759.00
1155.00
52.00
320.00
11.00
18.00
7.35
23.67
41.00
Rs:
159390.00
20790.00
141128.00
289600.00
952094.00
296748.00
94668.00
64244.90
16400.00
7761542.90
Rate
in Rs.
16.00
91.30
6.40
3.80
2278.10
75.00
86.10
0.00
22.50
38.00
22.50
38.00
42.60
114.10
41.00
Rs:
Amount
in Rs.
206080.00
1175944.00
41216.00
24472.00
820116.00
27000.00
20491.80
0.00
5355.00
9044.00
8032.50
13566.00
10224.00
27384.00
7380.00
2396305.30
Rate
in Rs.
Amount
in Rs.
Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS
Unit
Quantity
12880.00
12880.00
6440.00
6440.00
360.00
360.00
238.00
238.00
238.00
238.00
357.00
357.00
240.00
240.00
180.00
Quantity
293
1
2
3
4
5
6
7
8
9
10
11
12
Hour
360.00
Hour
357.00
Hour
238.00
Hour
240.00
Day
120.00
Day
195.00
Day
100.00
Day
1442.00
Day
275.00
Day
2023.00
Day
2727.00
Day
10.00
Total cost of Labour
Add towards highly skilled labour charges @ 30% on total cost of labour
Total Cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
454.30
171.60
171.60
113.90
440.00
440.00
385.00
385.00
440.00
385.00
345.00
440.00
Rs:
163548.00
61261.20
40840.80
27336.00
52800.00
85800.00
38500.00
555170.00
121000.00
778855.00
940815.00
4400.00
2870326.00
861097.80
3731423.80
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
7761542.90
2396305.30
3731423.80
13889272.00
0.00
13889272.00
416678.16
14305950.16
2002833.02
31356.50
0.14 4389.90
35746.40
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0.00%
Total
3%
14%
R
4522.000
15065.4
Rs:
16328370.59
Rs:
137213.20
119.00 tonne
Rate per tonne
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
7
8
9
10
11
12
13
particulars
Structural steel
Angles / beams / channels / bars
Plates / flats
Alloy steel components
Lifting pins
Bronze alloy components :
Bronze bush
Forged steel components :
Lifting hooks
MS pipe 100 mm dia
Bolt / Nut / Washer
MS bolts / nuts / washers
Oxygen gas
Acetyline gas
Welding electrodes
Welding electrodes ( LH )
Use rate welding holder set
Use rate gas cutting torch set
Sundries
UNIT :
Unit
Quantity
3.528 tonne
Rate
in Rs.
Amount
in Rs.
kg
kg
13.00
3389.00
45.00
46.00
585.00
155894.00
kg
101.00
420.00
42420.00
kg
5.00
912.00
4560.00
kg
kg
103.00
11.00
260.00
175.00
26780.00
1925.00
3.00
126.00
42.00
175.00
1575.00
187.00
24.00
25.00
90.00
52.00
320.00
11.00
18.00
7.35
23.67
41.00
270.00
6552.00
13440.00
1925.00
28350.00
1374.45
568.12
1025.00
kg
cum
cum
Nos
Nos
Hour
Hour
LS
294
Welding transformer
Fuel / Energy charges
Pug cutting machine
Fuel / Energy charges
Mobile derric crane
Fuel / Energy charges
Stationery derric crane
Fuel / Energy charges
Grinding machine
Fuel / Energy charges
Drilling machines
Fuel / Energy charges
Sundries
Total hire charges of Machinery
C. LABOUR:
Sl No
1
2
3
4
5
6
7
8
9
Description
Unit
Quantity
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS
Description
187.00
117.00
60.00
60.00
4.00
4.00
8.00
8.00
2.00
2.00
2.00
2.00
10.00
Unit
Quantity
Hour
4.00
Hour
2.00
Hour
2.00
Day
10.00
Day
18.00
Day
10.00
Day
18.00
Day
52.00
Day
1.00
Total cost of Labour
Add towards highly skilled labour charges @ 30% on total cost of labour
Total Cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
Rs:
285668.57
Rate
in Rs.
16.00
91.30
6.40
3.80
519.70
322.20
86.10
0.00
22.50
38.00
22.50
38.00
41.00
Rs:
Amount
in Rs.
2992.00
10682.10
384.00
228.00
2078.80
1288.80
688.80
0.00
45.00
76.00
45.00
76.00
410.00
18994.50
Rate
in Rs.
153.10
171.60
171.60
440.00
440.00
385.00
385.00
345.00
440.00
Rs:
Amount
in Rs.
612.40
343.20
343.20
4400.00
7920.00
3850.00
6930.00
17940.00
440.00
42778.80
12833.64
55612.44
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
285668.57
18994.50
55612.44
360275.51
0.00
360275.51
10808.27
371083.78
51951.73
15763.20
0.14 2206.80
17970.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0.00%
Total
3%
14%
R
3.528 tonne
Rate per tonne
134.064
446.644
Rs:
423616.21
Rs:
120072.60
295
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
2
3
4
5
6
7
Description
Welding transformer
Fuel / Energy charges
Tower crane 5 t capacity
Fuel / Energy charges
Pug cutting machine
Fuel / Energy charges
Mobile derric crane
Fuel / Energy charges
Grinding machine
Fuel / Energy charges
Drilling machines
Fuel / Energy charges
Sundries
Total hire charges of Machinery
C. LABOUR:
Sl No
1
2
3
4
5
6
7
Unit
Quantity
Structural steel
Angles / beams / channels / bars
kg
1743.00
Plates / flats
kg
19700.00
Chequered plates
kg
820.00
Cast steel components :
Rope drums 2 Nos/Gears
kg
1320.00
pinions
kg
1165.00
Wheels / Pulleys
kg
2255.00
Plummer blocks / Couplings
kg
817.00
Forged steel components
Hook / Shackle
kg
127.00
Alloy steel components
Shafts
kg
556.00
Pins
kg
524.00
Bronze alloy components :
Bronze bearings / bush
kg
181.00
Wire rope 28 mm dia 6/37 construction kg
406.00
MS Bolt / Nut / Washer
kg
63.00
MS pipe 32 mm dia for railing
Rm
50.00
Worm reducers
Nos.
4.00
Electric motor 17.5 hp
No.
1.00
Electric motor 5 hp
Nos.
2.00
Electric motor 3 hp
No.
1.00
Ele-magnetic / Thruster brakes
Nos.
4.00
Electric cable / switch / control panel
etc
LS
3.00
Oxygen gas
cum
579.00
Acetyline gas
cum
193.00
Welding electrodes
Nos
1123.00
Welding electrodes ( LH )
Nos
10110.00
Grease
kg
50.00
Use rate welding holder set
Hour
1197.00
Use rate gas cutting torch set
Hour
150.00
Sundries
LS
200.00
Total cost of Materials
B. MACHINERY:
Sl No
1
particulars
UNIT :
Description
Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS
Unit
Hour
Hour
Hour
Hour
Day
Day
Day
Quantity
1197.00
748.00
6.00
6.00
235.00
235.00
100.00
100.00
32.00
32.00
16.00
16.00
500.00
Quantity
100.00
6.00
16.00
32.00
74.00
124.00
48.00
30.856 tonne
25 t capacity
Rate
Amount
in Rs.
in Rs.
45.00
46.00
60.00
78435.00
906200.00
49200.00
220.00
210.00
180.00
180.00
290400.00
244650.00
405900.00
147060.00
260.00
33020.00
210.00
420.00
116760.00
220080.00
912.00
250.00
90.00
185.00
224400.00
85800.00
33000.00
23100.00
35200.00
165072.00
101500.00
5670.00
9250.00
897600.00
85800.00
66000.00
23100.00
140800.00
50380.00
52.00
320.00
11.00
18.00
260.00
7.35
23.67
41.00
Rs:
151140.00
30108.00
61760.00
12353.00
181980.00
13000.00
8797.95
3550.75
8200.00
4457386.70
Rate
in Rs.
16.00
91.30
867.10
197.80
6.40
3.80
519.70
322.20
22.50
38.00
22.50
38.00
41.00
Rs:
Amount
in Rs.
19152.00
68292.40
5202.60
1186.80
1504.00
893.00
51970.00
32220.00
720.00
1216.00
360.00
608.00
20500.00
203824.80
Rate
in Rs.
153.10
163.30
171.60
171.60
440.00
440.00
385.00
Amount
in Rs.
15310.00
979.80
2745.60
5491.20
32560.00
54560.00
18480.00
296
8
9
10
11
Welder ( General )
Khalasi
Helper fabrication / erection
Electrician
Day
112.00
Day
20.00
Day
350.00
Day
10.00
Total cost of Labour
Add towards highly skilled labour charges @ 30% on total cost of labour
Total Cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
385.00
385.00
345.00
440.00
Rs:
43120.00
7700.00
120750.00
4400.00
306096.60
91828.98
397925.58
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
4457386.70
203824.80
397925.58
5059137.08
0.00
5059137.08
151774.11
5210911.19
729527.57
15917.00
0.14 2228.40
18145.40
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0.00%
Total
3%
14%
R
30.856
25.000
Rate per
Rate per
tonne
t capacity
tonne
tonne capac
1172.528
3906.37
Rs:
5945517.66
Rs:
Rs:
192685.90
Rs:
237820.70
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
7
8
9
10
B. MACHINERY:
Sl No
1
2
3
4
5
particulars
Description
Welding transformer
Fuel / Energy charges
Mobile derric crane
Fuel / Energy charges
Grinding machine
Fuel / Energy charges
Drilling machines
Fuel / Energy charges
Sundries
Total hire charges of Machinery
UNIT :
Unit
Quantity
kg
1570.00
kg
975.00
kg
18450.00
kg
246.00
cum
201.00
cum
67.00
Nos
1805.00
Hour
193.00
Hour
133.00
LS
10.00
Total cost of Materials
Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS
Quantity
193.00
121.00
4.00
4.00
8.00
8.00
50.00
50.00
10.00
200.000 Rm
Rate
in Rs.
Amount
in Rs.
45.00
46.00
51.50
90.00
52.00
320.00
11.00
7.35
23.67
41.00
Rs:
70650.00
44850.00
950175.00
22140.00
10452.00
21440.00
19855.00
1418.55
3148.33
410.00
1144538.88
Rate
in Rs.
16.00
91.30
519.70
322.20
22.50
38.00
22.50
38.00
41.00
Rs:
Amount
in Rs.
3088.00
11047.30
2078.80
1288.80
180.00
304.00
1125.00
1900.00
410.00
21421.90
297
C. LABOUR:
Sl No
1
2
3
4
5
6
7
8
9
Description
Unit
Quantity
Hour
4.00
Hour
50.00
Hour
8.00
Day
8.00
Day
32.00
Day
17.00
Day
18.00
Day
52.00
Day
1.00
Total cost of Labour
Add towards highly skilled labour charges @ 30% on total cost of labour
Total Cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
Rate
in Rs.
153.10
171.60
171.60
440.00
440.00
385.00
385.00
345.00
440.00
Rs:
Amount
in Rs.
612.40
8580.00
1372.80
3520.00
14080.00
6545.00
6930.00
17940.00
440.00
60020.20
18006.06
78026.26
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
1144538.88
21421.90
78026.26
1243987.04
0.00
1243987.04
37319.61
1281306.65
179382.93
390.10
0.14 54.60
444.70
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0.00%
Total
3%
Total
14%
R
787.436
2623.406
Rs:
1464100.43
Rs:
7320.50
200.000 Rm
Rate per Rm
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
particulars
Structural steel
Plates / flats
Beams/Channels
Alloy steel components
Wheel axles / Pins
Cast steel components
Wheels / Guide rollers
Alluminium / Bronze alloy
components
Bearings
Bolt / Nut / Washer
GI bolts / nuts / washers
MS bolts / nuts / washers
Rubber seals
Bottom seal ( flat uncladed )
UNIT :
Unit
Quantity
10.000 tonne
Rate
in Rs.
Amount
in Rs.
kg
kg
7103.00
2727.00
46.00
45.00
326738.00
122715.00
kg
108.00
420.00
45360.00
kg
504.00
180.00
90720.00
kg
12.00
912.00
10944.00
kg
kg
36.00
6.00
106.00
90.00
3816.00
540.00
Rm
3.72
759.00
2823.48
298
7
8
9
10
11
12
13
B. MACHINERY:
Sl No
1
2
3
4
5
6
7
8
9
Description
Welding transformer
Fuel / Energy charges
Pug cutting machine
Fuel / Energy charges
Tower crane
Fuel / Energy charges
Mobile crane 16 T
Fuel / Energy charges
Stationery derric crane
Fuel / Energy charges
Grinding machine
Fuel / Energy charges
Drilling machines
Fuel / Energy charges
Bending machine
Fuel / Energy charges
Sundries
Total hire charges of Machinery
C. LABOUR:
Sl No
1
2
3
4
5
6
7
8
9
10
11
12
13
Rm
12.30
Rm
3.72
Nos
2.00
cum
170.00
cum
56.00
Nos
3200.00
Nos
800.00
Hour
500.00
Hour
40.00
LS
60.00
Total cost of Materials
Unit
Quantity
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS
Description
500.00
500.00
85.00
85.00
10.00
10.00
30.00
30.00
20.00
20.00
10.00
10.00
30.00
30.00
10.00
10.00
50.00
Unit
Quantity
Hour
30.00
Hour
10.00
Hour
30.00
Hour
10.00
Hour
10.00
Day
16.00
Day
50.00
Day
8.00
Day
52.00
Day
14.00
Day
170.00
Day
230.00
Day
4.00
Total cost of Labour
Add towards highly skilled labour charges @ 30% on total cost of labour
Total Cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
18671.40
5646.96
2970.00
8840.00
17920.00
35200.00
14400.00
3675.00
946.87
2460.00
714386.71
Rate
in Rs.
16.00
91.30
6.40
3.80
867.10
197.80
2278.10
75.00
86.10
0.00
22.50
38.00
22.50
38.00
42.60
114.10
41.00
Rs:
Amount
in Rs.
8000.00
45650.00
544.00
323.00
8671.00
1978.00
68343.00
2250.00
1722.00
0.00
225.00
380.00
675.00
1140.00
426.00
1141.00
2050.00
143518.00
Rate
in Rs.
454.30
163.30
171.60
171.60
113.90
440.00
440.00
385.00
385.00
440.00
385.00
345.00
440.00
Rs:
Amount
in Rs.
13629.00
1633.00
5148.00
1716.00
1139.00
7040.00
22000.00
3080.00
20020.00
6160.00
65450.00
79350.00
1760.00
228125.00
68437.50
296562.50
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
714386.71
143518.00
296562.50
1154467.21
0.00
1154467.21
34634.02
1189101.22
166474.17
29656.30
0.14 4151.90
33808.20
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0.00%
Total
3%
1518.00
1518.00
1485.00
52.00
320.00
11.00
18.00
7.35
23.67
41.00
Rs:
14%
299
10.000 tonne
Rate per tonne
380
1266
Rs:
Rs:
1357221.39
135722.10
VERTICAL LIFT GATES-ROPE DRUM HOIST UPTO 30 TON CAP. POWER OPERATED
IRR-GAW-2-7 Design, fabrication, supply, erection, testing and commissioning of adequate capacity rope
drum hoist consisting of hoist platform, rope drum, gear system, electric motor, electromagnetic brake system, hand operation assembly, control panel, wire rope, pulleys, ladder etc.,
with all accessories for operating river sluice / canal sluice service gate including cost of
all materials, machinery, labour, , complete as per specifications and drawings with all leads and lifts
(without painting on sand-blasted or mechanical cleaning surfaces which are added extra
as perscedule of rates under items in this chapter and add as applicable separately)
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
Structural steel
Angles / beams / channels / bars
Plates / flats
Chequered plate
Cast steel components :
Rope drums 2 Nos / Gears
Pinions
Pulleys 3 Nos / Couplings 2 Nos
Plummer blocks / Hubs
Alloy steel components
Shafts
Pins
Bronze alloy components :
Bronze bearings / bush
Wire rope 28 mm dia 6/37
construction
MS Bolt / Nut / Washer
Worm reducers
Electric motor 5 hp
Manual operating system
Gate position indicator
Ele-magnetic brake
Electric cable / switch / control panel
etc
Oxygen gas
Acetyline gas
Welding electrodes
Welding electrodes ( LH )
Grease
Use rate welding holder set
Use rate gas cutting torch set
Sundries
B. MACHINERY:
Sl No
1
2
3
4
5
6
particulars
UNIT :
Unit
Quantity
6.243 tonne wt
25 t capacity
Rate
Amount
in Rs.
in Rs.
kg
kg
kg
1487.00
402.00
290.00
45.00
46.00
60.00
66915.00
18492.00
17400.00
kg
kg
kg
kg
1926.00
79.00
306.00
72.00
220.00
210.00
180.00
180.00
423720.00
16590.00
55080.00
12960.00
kg
kg
346.00
73.00
210.00
420.00
72660.00
30660.00
kg
57.00
912.00
51984.00
kg
kg
No.
No.
No.
No.
No.
325.00
32.00
1.00
1.00
1.00
1.00
1.00
250.00
90.00
224400.00
33000.00
28820.00
195800.00
35200.00
81250.00
2880.00
224400.00
33000.00
28820.00
195800.00
35200.00
LS
1.00
cum
45.00
cum
15.00
Nos
80.00
Nos
720.00
kg
50.00
Hour
85.00
Hour
16.00
LS
25.00
Total cost of Materials
50380.00
52.00
320.00
11.00
18.00
260.00
7.35
23.67
41.00
Rs:
50380.00
2340.00
4800.00
880.00
12960.00
13000.00
624.75
378.75
1025.00
1454199.50
Rate
in Rs.
16.00
91.30
867.10
197.80
6.40
3.80
519.70
322.20
22.50
38.00
22.50
38.00
Amount
in Rs.
1360.00
4838.90
1734.20
395.60
96.00
57.00
5197.00
3222.00
45.00
76.00
45.00
76.00
Description
Unit
Welding transformer
Fuel / Energy charges
Tower crane 5 t capacity
Fuel / Energy charges
Pug cutting machine
Fuel / Energy charges
Mobile derric crane
Fuel / Energy charges
Grinding machine
Fuel / Energy charges
Drilling machines
Fuel / Energy charges
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Quantity
85.00
53.00
2.00
2.00
15.00
15.00
10.00
10.00
2.00
2.00
2.00
2.00
300
Sundries
Total hire charges of Machinery
C. LABOUR:
Sl No
1
2
3
4
5
6
7
8
9
10
11
LS
Description
25.00
Unit
Quantity
Hour
10.00
Hour
2.00
Hour
2.00
Hour
2.00
Day
15.00
Day
19.00
Day
4.00
Day
8.00
Day
4.00
Day
44.00
Day
2.00
Total cost of Labour
Add towards highly skilled labour charges @ 30% on total cost of labour
Total Cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
41.00
Rs:
1025.00
18167.70
Rate
in Rs.
153.10
163.30
171.60
171.60
440.00
440.00
385.00
385.00
385.00
345.00
440.00
Rs:
Amount
in Rs.
1531.00
326.60
343.20
343.20
6600.00
8360.00
1540.00
3080.00
1540.00
15180.00
880.00
39724.00
11917.20
51641.20
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
1454199.50
18167.70
51641.20
1524008.40
0.00
1524008.40
45720.25
1569728.65
219762.01
2065.60
0.14 289.20
2354.80
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0.00%
Total
3%
14%
R
237.234
790.364
Rs:
1790518.26
Rs:
Rs:
286804.10
Rs:
71620.70
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
2
3
4
5
6
7
particulars
Unit
kg
kg
kg
Rm
kg
cum
cum
Nos
Hour
Quantity
1494.00
6564.00
2442.00
60.00
18.00
105.00
35.00
3150.00
394.00
Rate
in Rs.
45.00
46.00
60.00
150.00
90.00
52.00
320.00
11.00
7.35
Amount
in Rs.
67230.00
301944.00
146520.00
9000.00
1620.00
5460.00
11200.00
34650.00
2895.90
301
8
9
B. MACHINERY:
Sl No
1
2
3
4
5
6
7
8
Description
Welding transformer
Fuel / Energy charges
Pug cutting machine
Fuel / Energy charges
Mobile crane 30 T
Fuel / Energy charges
Stationery derric crane
Fuel / Energy charges
Drilling machine
Fuel / Energy charges
Grinding machine
Fuel / Energy charges
Tower Crane
Fuel / Energy charges
Sundries
Total hire charges of Machinery
C. LABOUR:
Sl No
1
2
3
4
5
6
7
8
9
10
Hour
105.00
LS
50.00
Total cost of Materials
Unit
Quantity
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS
Description
394.00
394.00
52.00
52.00
30.00
30.00
20.00
20.00
20.00
20.00
20.00
20.00
20.00
20.00
50.00
Unit
Quantity
Hour
30.00
Hour
20.00
Hour
20.00
20.00
Hour
Day
10.00
Day
50.00
Day
14.00
Day
53.00
Day
400.00
Day
6.00
Total cost of Labour
Add towards highly skilled labour charges @ 30% on total cost of labour
Total Cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
23.67
41.00
Rs:
2485.53
2050.00
585055.43
Rate
in Rs.
16.00
91.30
6.40
3.80
3096.80
118.80
86.10
0.00
22.50
38.00
22.50
38.00
867.10
197.80
41.00
Rs:
Amount
in Rs.
6304.00
35972.20
332.80
197.60
92904.00
3564.00
1722.00
0.00
450.00
760.00
450.00
760.00
17342.00
3956.00
2050.00
166764.60
Rate
in Rs.
454.30
171.60
171.60
163.30
440.00
440.00
385.00
385.00
345.00
440.00
Rs:
Amount
in Rs.
13629.00
3432.00
3432.00
3266.00
4400.00
22000.00
5390.00
20405.00
138000.00
2640.00
216594.00
64978.20
281572.20
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
585055.43
166764.60
281572.20
1033392.23
0.00
1033392.23
31001.77
1064393.99
149015.16
26816.40
0.14 3754.30
30570.70
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0.00%
Total
3%
14%
R
10.500 tonne
Rate per tonne
399
1329.3
Rs:
1215137.45
Rs:
115727.40
302
(without painting on sand-blasted or mechanical cleaning surfaces which are added extra
as perscedule of rates under items in this chapter and add as applicable separately)
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
Structural steel
Angles / beams / channels / bars
Plates / flats
Cast steel components :
Rope drums 2 Nos / Gears
Pinions
Pulleys 3 Nos / Couplings 2 Nos
Plummer blocks / Hubs
Alloy steel components
Shafts / Keys
Pins
Bronze alloy components :
Bronze bearings / bush
Wire rope 28 mm dia 6/37
construction
MS Bolt / Nut / Washer
Worm reducers
Electric motor 12.5 hp
Manual operating system
Gate position indicator
Ele-magnetic brake
Electric cable / switch / control panel
etc
Oxygen gas
Acetyline gas
Welding electrodes
Welding electrodes ( LH )
Grease
Use rate welding holder set
Use rate gas cutting torch set
Sundries
B. MACHINERY:
Sl No
1
2
3
4
5
6
7
Description
Welding transformer
Fuel / Energy charges
Tower crane 5 t capacity
Fuel / Energy charges
Pug cutting machine
Fuel / Energy charges
Mobile derric crane
Fuel / Energy charges
Grinding machine
Fuel / Energy charges
Drilling machines
Fuel / Energy charges
Sundries
Total hire charges of Machinery
C. LABOUR:
Sl No
1
2
3
4
5
6
7
8
particulars
Description
UNIT :
Unit
Quantity
5.069 tonne wt
50.00 t capacity
Rate
Amount
in Rs.
in Rs.
kg
kg
420.00
225.00
45.00
46.00
18900.00
10350.00
kg
kg
kg
kg
1290.00
98.00
650.00
250.00
220.00
210.00
180.00
180.00
283800.00
20580.00
117000.00
45000.00
kg
kg
350.00
96.00
210.00
420.00
73500.00
40320.00
kg
100.00
912.00
91200.00
kg
kg
No.
No.
No.
No.
No.
435.00
26.00
1.00
1.00
1.00
1.00
1.00
250.00
90.00
224400.00
72600.00
28820.00
195800.00
35200.00
108750.00
2340.00
224400.00
72600.00
28820.00
195800.00
35200.00
LS
1.00
cum
30.00
cum
10.00
Nos
44.00
Nos
392.00
kg
50.00
Hour
47.00
Hour
12.00
LS
25.00
Total cost of Materials
50380.00
52.00
320.00
11.00
18.00
260.00
7.35
23.67
41.00
Rs:
50380.00
1560.00
3200.00
484.00
7056.00
13000.00
345.45
284.06
1025.00
1445894.51
Rate
in Rs.
16.00
91.30
867.10
197.80
6.40
3.80
519.70
322.20
22.50
38.00
22.50
38.00
41.00
Rs:
Amount
in Rs.
752.00
4291.10
1734.20
395.60
57.60
34.20
5197.00
3222.00
45.00
76.00
45.00
76.00
1025.00
16950.70
Rate
in Rs.
153.10
163.30
171.60
171.60
440.00
440.00
385.00
385.00
Amount
in Rs.
1531.00
326.60
343.20
343.20
5720.00
7480.00
1155.00
1925.00
Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS
Unit
Hour
Hour
Hour
Hour
Day
Day
Day
Day
Quantity
47.00
47.00
2.00
2.00
9.00
9.00
10.00
10.00
2.00
2.00
2.00
2.00
25.00
Quantity
10.00
2.00
2.00
2.00
13.00
17.00
3.00
5.00
303
9
10
11
Khalasi
Helper fabrication / erection
Electrician
Day
4.00
Day
36.00
Day
2.00
Total cost of Labour
Add towards highly skilled labour charges @ 30% on total cost of labour
Total Cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
385.00
345.00
440.00
Rs:
1540.00
12420.00
880.00
33664.00
10099.20
43763.20
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
1445894.51
16950.70
43763.20
1506608.41
0.00
1506608.41
45198.25
1551806.66
217252.93
875.30
0.14 122.50
997.80
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0.00%
Total
3%
14%
R
192.622
641.736
Rs:
1769893.95
Rs:
Rs:
349160.40
Rs:
35397.90
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
7
8
9
10
11
12
13
Structural steel
Angles / beams / channels / bars
Plates / flats
Chequered plate
Cast iron components :
Hoist body / Lock nut / Main nut
Alloy steel components
Hoist stem
Bronze alloy components :
Thrust bearings
MS Bolt / Nut / Washer
Oxygen gas
Acetyline gas
Welding electrodes
Welding electrodes ( LH )
Grease
Use rate welding holder set
Use rate gas cutting torch set
Sundries
B. MACHINERY:
Sl No
1
particulars
Description
Welding transformer
UNIT :
Unit
Quantity
0.871 tonne
3.00 t capacity
Rate
Amount
in Rs.
in Rs.
kg
kg
kg
402.00
145.00
176.00
45.00
46.00
60.00
18090.00
6670.00
10560.00
kg
55.00
220.00
12100.00
kg
75.00
210.00
15750.00
kg
4.00
kg
8.00
cum
18.00
cum
6.00
Nos
7.00
Nos
66.00
kg
2.00
Hour
8.00
Hour
11.00
LS
2.00
Total cost of Materials
912.00
90.00
52.00
320.00
11.00
18.00
260.00
7.35
23.67
41.00
Rs:
3648.00
720.00
936.00
1920.00
77.00
1188.00
520.00
58.80
260.39
82.00
72580.19
Rate
in Rs.
16.00
Amount
in Rs.
128.00
Unit
Hour
Quantity
8.00
304
2
3
4
C. LABOUR:
Sl No
1
2
3
4
5
6
7
8
Hour
Hour
Hour
Hour
Hour
LS
Description
5.00
2.00
2.00
2.00
2.00
2.00
Unit
Quantity
Hour
2.00
Hour
2.00
Day
4.00
Day
5.00
Day
2.00
Day
1.00
Day
9.00
Day
0.50
Total cost of Labour
Add towards highly skilled labour charges @ 30% on total cost of labour
Total Cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
91.30
22.50
38.00
22.50
38.00
41.00
Rs:
456.50
45.00
76.00
45.00
76.00
82.00
908.50
Rate
in Rs.
171.60
171.60
440.00
440.00
385.00
385.00
345.00
440.00
Rs:
Amount
in Rs.
343.20
343.20
1760.00
2200.00
770.00
385.00
3105.00
220.00
9126.40
2737.92
11864.32
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
72580.19
908.50
11864.32
85353.01
0.00
85353.01
2560.59
87913.60
12307.90
3954.80
0.14 553.70
4508.50
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0.00%
Total
3%
14%
R
33.098
110.268
Rs:
100364.87
Rs:
Rs:
115229.50
Rs:
33455.00
0.871 tonne
3.000 t capacity
Rate per tonne
Rate per tonne capacity
RATE ANALYSIS
A. MATERIALS:
Sl No
particulars
1
Structural steel
Angles / beams / channels / bars
Plates / flats
Chequered plate
Cast steel components :
Rope drums 2 Nos / Gears
Pinions
Pulleys 6 Nos
Plummer blocks / Couplings
UNIT :
2.804
10.00
Rate
in Rs.
tonne
t capacity
Amount
in Rs.
Unit
Quantity
kg
kg
kg
1229.00
453.00
195.00
45.00
46.00
60.00
55305.00
20838.00
11700.00
kg
kg
kg
kg
384.00
14.00
108.00
47.00
220.00
210.00
180.00
180.00
84480.00
2940.00
19440.00
8460.00
305
5
6
7
8
9
10
11
12
13
14
15
16
17
18
B. MACHINERY:
Sl No
Description
1
2
3
4
5
6
7
Welding transformer
Fuel / Energy charges
Pug cutting machine
Fuel / Energy charges
Mobile derric crane
Fuel / Energy charges
Stationery derric crane
Fuel / Energy charges
Grinding machine
Fuel / Energy charges
Drilling machines
Fuel / Energy charges
Sundries
Total hire charges of Machinery
C. LABOUR:
Sl No
Description
1
2
3
4
5
6
7
8
9
kg
kg
75.00
24.00
210.00
420.00
15750.00
10080.00
kg
11.00
912.00
10032.00
kg
42.00
kg
64.00
No.
1.00
No.
1.00
No.
1.00
No
2.00
cum
75.00
cum
25.00
Nos
69.00
Nos
622.00
kg
10.00
Hour
73.00
Hour
42.00
LS
25.00
Total cost of Materials
250.00
90.00
224400.00
28820.00
35200.00
4620.00
52.00
320.00
11.00
18.00
260.00
7.35
23.67
41.00
Rs:
10500.00
5760.00
224400.00
28820.00
35200.00
9240.00
3900.00
8000.00
759.00
11196.00
2600.00
536.55
994.21
1025.00
581955.76
Unit
Quantity
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS
Unit
Rate Amount
in Rs. in Rs.
16.00
1168.00
91.30
4199.80
6.40
51.20
3.80
30.40
519.70
2078.80
322.20
1288.80
86.10
688.80
0.00
0.00
22.50
180.00
38.00
304.00
22.50
360.00
38.00
608.00
41.00
1025.00
Rs:
11982.80
73.00
46.00
8.00
8.00
4.00
4.00
8.00
8.00
8.00
8.00
16.00
16.00
25.00
Quantity
Rate
in Rs.
Hour
4.00
Hour
16.00
Hour
8.00
Day
14.00
Day
20.00
Day
6.00
Day
7.00
Day
44.00
Day
2.00
Total cost of Labour
Rs:
Add towards highly skilled labour charges @ 30% on total cost of labour
Total Cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
Amount
in Rs.
153.10
171.60
171.60
440.00
440.00
385.00
385.00
345.00
440.00
612.40
2745.60
1372.80
6160.00
8800.00
2310.00
2695.00
15180.00
880.00
40755.80
12226.74
52982.54
5298.30
0.14 741.80
6040.10
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Rs:
Rs:
Rs:
Total
0.00%
Total
3%
Rs:
Rs:
Rs:
Rs:
Rs:
581955.76
11982.80
52982.54
646921.10
0.00
646921.10
19407.63
666328.73
306
14%
R
Rs:
19.00 per tonne
63.30 per tonne
2.804 tonne
10.000 t capacity
tonne
Rate per
tonne
capacity of hoist
Rate per
93286.02
106.552
354.986
Rs:
760076.29
Rs:
Rs:
271068.60
76007.60
IRR-GAW-212
New Item 201415-2
OT SLUICE SHUTTERS Screw Gear Hoist Including Platform for below 5 Tons Capacity (Small Gates)
As per Guidelines of Chief Engineer, Central Designs Organization, Hyderabad Specification drawing for
Krishna Delta System
Fabrication, supply, erection, testing and commissioning of Embedded parts consisting of supporting structure,
platform etc. with all accessories for operating canal escape/ regulator gate with all accessories including cost of all
materials, machinery, labour, cutting, bending, aligning, anchoring, welding, finishing etc. complete
as per Specification and approved drawings
(without painting on mechanical cleaning surfaces which are added extra as per schedule of rates
under items in this chapter and add as applicable separately)
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
7
8
9
10
11
12
13
B. MACHINERY:
Sl No
1
2
3
4
5
6
Description
Welding transformer
Fuel / Energy charges
Pug cutting machine
Fuel / Energy charges
Drilling machine
Fuel / Energy charges
Grinding machine
Fuel / Energy charges
Lathe machine (Screw Rod M/C)
Sundries
Total hire charges of Machinery
C. LABOUR:
Sl No
1
2
3
4
5
particulars
Description
UNIT :
Unit
kg
kg
kg
445.78
28.00
144.80
Rate
in Rs.
45.00
46.00
60.00
Kg
83.00
220.00
18260.00
kg
3.00
kg
16.00
cum
21.00
cum
7.00
Nos
200.00
Nos
40.00
Hour
72.00
Hour
36.00
LS
20.00
Total cost of Materials
912.00
90.00
52.00
320.00
11.00
18.00
7.35
23.67
41.00
Rs:
2736.00
1440.00
1092.00
2240.00
2200.00
720.00
529.20
852.18
820.00
60925.48
Rate
in Rs.
16.00
91.30
6.40
3.80
22.50
38.00
22.50
38.00
300.00
41.00
Rs:
Amount
in Rs.
480.00
2739.00
76.80
45.60
180.00
304.00
810.00
1368.00
4800.00
410.00
11213.40
Rate
in Rs.
171.60
171.60
440.00
440.00
385.00
Amount
in Rs.
1372.80
6177.60
880.00
4400.00
1540.00
Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS
Unit
Hour
Hour
Day
Day
Day
Quantity
0.869 tonne
Quantity
30.00
30.00
12.00
12.00
8.00
8.00
36.00
36.00
16.00
10.00
Quantity
8.00
36.00
2.00
10.00
4.00
Amount
in Rs.
20060.10
1288.00
8688.00
307
6
7
8
Welder ( General )
Mazdoors
Helper fabrication / erection
Day
4.00
Day
6.00
Day
6.00
Total cost of Labour
labour component/unit qty
19750.40
Add contractor's profit and overhead charges
0.14 2765.10
labour component/unit qty (including contractor's profit)
22515.50
385.00
295.00
345.00
Rs:
1540.00
1770.00
2070.00
19750.40
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
60925.48
11213.40
19750.40
91889.28
0.00
91889.28
2756.68
94645.96
13250.43
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0.00%
Total
3%
14%
R
0.869 tonne
Rate per tonne
33.022
110.016
Rs:
108039.43
Rs:
124326.20
IRR-GAW-213
New Item 201415-3
OT SLUICE SHUTTERS EM parts for Below 5 Tons capacity (small gates)
As per Guidelines of Chief Engineer, Central Designs Organization, Hyderabad Specification drawing for
Krishna Delta System
Fabrication, supply, erection, testing and commissioning of Embedded parts consisting of sil beam, slide tracks,
seal seats, Guide plates etc. with all accessories including cost of all materials, machinery, labour, etc.
complete as per specifications and approved drawings.
(without painting on mechanical cleaning surfaces which are added extra as per schedule of rates
under items in this chapter and add as applicable separately)
Height of EM parts: 5.4 M
DATA:
Gate Size:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
7
8
9
10
B. MACHINERY:
Sl No
1
2
3
4
5
particulars
Description
Welding transformer
Fuel / Energy charges
Pug cutting machine
Fuel / Energy charges
Drilling machine
Fuel / Energy charges
Grinding machine
Fuel / Energy charges
Sundries
UNIT :
Unit
Quantity
kg
440.57
kg
869.00
kg
25.12
cum
12.00
cum
4.00
Nos
210.00
Nos
30.00
Hour
62.00
Hour
32.00
LS
3.00
Total cost of Materials
Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS
Quantity
30.00
30.00
20.00
20.00
4.00
4.00
20.00
20.00
3.00
0.99 X 0.875 M
1.334 tonne
Rate
in Rs.
45.00
46.00
275.00
52.00
320.00
11.00
26.00
7.35
23.67
41.00
Rs:
Amount
in Rs.
19825.65
39974.00
6908.00
624.00
1280.00
2310.00
780.00
455.70
757.49
123.00
73037.84
Rate
in Rs.
16.00
91.30
6.40
3.80
22.50
38.00
22.50
38.00
41.00
Amount
in Rs.
480.00
2739.00
128.00
76.00
90.00
152.00
450.00
760.00
123.00
308
Description
Unit
Quantity
Hour
4.00
Hour
20.00
Day
8.00
Day
6.00
Day
2.00
Day
4.00
Day
4.00
Day
8.00
Total cost of Labour
labour component/unit qty
16528.40
Add contractor's profit and overhead charges
0.14 2314.00
labour component/unit qty (including contractor's profit)
18842.40
Rs:
4998.00
Rate
in Rs.
171.60
171.60
440.00
440.00
385.00
385.00
295.00
345.00
Rs:
Amount
in Rs.
686.40
3432.00
3520.00
2640.00
770.00
1540.00
1180.00
2760.00
16528.40
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
73037.84
4998.00
16528.40
94564.24
0.00
94564.24
2836.93
97401.17
13636.16
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0.00%
Total
3%
14%
R
50.692
168.884
Rs:
111256.91
Rs:
83401.00
1.334 tonne
Rate per tonne
IRR-GAW-214
New Item 201415 -4
OT SLUICE SHUTTERS for Below 5 Tons capacity (small gates)
As per Guidelines of Chief Engineer, Central Designs Organization, Hyderabad Specification drawing for
Krishna Delta System
Fabrication, supply, erection, testing and commissioning of Sluice Shutters consisting of skin plate, horizontal
and vertical angles, stiffeners, rubber seals, clamps with all accessories for sluice shutters including cost
of all materials, machinery, labour, seal fixing etc., complete as per specifications and approved drawings
(without painting on mechanical cleaning surfaces which are added extra as per schedule of rates
under items in this chapter and add as applicable separately)
Gate Size: 0.99 X 0.875 M
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
7
8
9
10
11
particulars
B. MACHINERY:
Sl No
Description
UNIT :
Unit
63.72
96.50
20.00
Rate
in Rs.
45.00
46.00
130.00
Amount
in Rs.
2867.40
4439.00
2600.00
Rm
0.82
Rm
1.75
cum
15.00
cum
5.00
Nos
110.00
Hour
30.00
Hour
12.00
LS
3.00
Total cost of Materials
759.00
1155.00
52.00
320.00
11.00
7.35
23.67
41.00
Rs:
622.38
2021.25
780.00
1600.00
1210.00
220.50
284.06
123.00
16767.59
kg
kg
kg
Unit
Quantity
0.161 tonne
Quantity
Rate
Amount
309
1
2
3
4
5
Welding transformer
Fuel / Energy charges
Pug cutting machine
Fuel / Energy charges
Drilling machine
Fuel / Energy charges
Grinding machine
Fuel / Energy charges
Sundries
Total hire charges of Machinery
C. LABOUR:
Sl No
1
2
3
4
5
6
7
8
Description
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS
14.00
14.00
4.00
4.00
2.00
2.00
4.00
4.00
3.00
Unit
Quantity
Hour
2.00
Hour
4.00
Day
2.00
Day
3.00
Day
1.00
Day
4.00
Day
4.00
Day
6.00
Total cost of Labour
labour component/unit qty
8404.60
Add contractor's profit and overhead charges
0.14 1176.60
labour component/unit qty (including contractor's profit)
9581.20
in Rs.
16.00
91.30
6.40
3.80
22.50
38.00
22.50
38.00
41.00
Rs:
in Rs.
224.00
1278.20
25.60
15.20
45.00
76.00
90.00
152.00
123.00
2029.00
Rate
in Rs.
171.60
171.60
440.00
440.00
385.00
385.00
295.00
345.00
Rs:
Amount
in Rs.
343.20
686.40
880.00
1320.00
385.00
1540.00
1180.00
2070.00
8404.60
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
16767.59
2029.00
8404.60
27201.19
0.00
27201.19
816.04
28017.23
3922.41
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0.00%
Total
3%
IRR-GAW-3
14%
R
0.161 tonne
Rate per tonne
6.118
20.382
Rs:
Rs:
31966.14
198547.40
IRR-GAW-3-1 Cleaning gates / hoists / embedded parts/lifting beams etc, to expose fresh metal surface
for painting by sand blasting method as per specifications including cost of all materials, l
abour, machinery, scaffolding, etc., complete with initial lead for sand upto 1 km and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
particulars
UNIT : 100
Unit
Quantity
cum
30.00
Hour
8.00
Hour
8.00
LS
5.00
Total
Add 10% towards scaffolding/laddor @
Total cost of Materials
B. MACHINERY:
Sl No
Description
Unit
Quantity
1
2
Sand (Screened)
Use rate of air hose
Use rate of sand blast gun nozzle
Sundries( Rust inhibitive, seive etc )
Hour
Hour
Hour
8.00
8.00
8.00
sqm
Rate
in Rs.
606.00
18.63
3.50
41.00
0.10
Rate
in Rs.
241.30
767.30
110.10
Amount
in Rs.
18180.00
149.00
28.00
205.00
18562.00
1856.20
20418.20
Amount
in Rs.
1930.40
6138.40
880.80
310
Hour
8.00
Total hire charges of Machinery
Description
Unit
Quantity
Hour
8.00
Hour
8.00
Day
15.00
Total cost of Labour
labour component/unit qty
74.00
Add contractor's profit and overhead charges
0.14 10.40
labour component/unit qty (including contractor's profit)
84.40
0.00
0.00
8949.60
Rate
in Rs.
182.20
189.80
295.00
Amount
in Rs.
1457.60
1518.40
4425.00
7401.00
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
20418.20
8949.60
7401.00
36768.80
0.00
36768.80
1103.06
37871.86
5302.06
43173.92
431.70
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0.00%
Total
3%
14%
100.00 sqm
Rate per sqm
IRR-GAW-3-2 painting of embedded metal parts and all types of gates, stoplogs,etc, on sand blasted
surfaces with one coat of inorganic zinc silicate (airless spray preferred)70+/- 5
and two super coats with a total thickness of 300 microns
(each 150+/- 5) of solventless coaltar epoxy paint each coat 150 microns ( total 300 microns)
cost of all materials, labour, scaffolding etc., complete with all leads and
all lifts
(Upstream surface of gates portion may be painted with solventless coaltar epoxy brown paint
instead of solventless coaltar black. The rate for coaltar epoxy brown shall be adopted in data
for Upstream side painting)
DATA:
17.50 Sqm/Hr
5.71
Hr
6
Hr
Say
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
1
2
3
UNIT :
particulars
Unit
Quantity
ltr
ltr
ltr
ltr
12.00
1.20
40.00
4.00
B. MACHINERY:
Sl No
Description
Sqm/Hr
3.00
Total cost of Materials
Unit
Quantity
Hr
Hr
Hr
100 sqm
Rate
in Rs.
689.00
140.00
271.00
140.00
Amount
in Rs.
8268
168
10840
560
41.00
123
19959.00
Rs:
6.00
Rate
in Rs.
121.40
Amount
in Rs.
728.40
6.00
6.00
241.30
767.30
1447.80
4603.80
Rs:
6780.00
311
C. LABOUR:
Sl No
1
2
3
Description
Unit
Quantity
Day
6.00
Day
20.00
Day
20.00
Total cost of Labour
labour component/unit qty
157.90
Add contractor's profit and overhead charges
0.14 22.10
labour component/unit qty (including contractor's profit)
180.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0
Total
0.03
14%
Rs:
Rate
in Rs.
182.20
440.00
295.00
Rs:
Amount
in Rs.
1093.20
8800.00
5900.00
15793.20
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
6133.14
Rs:
Rs:
19959.00
6780.00
15793.20
42532.20
0.00
42532.20
1275.97
43808.17
6133.14
49941.31
499.40
IRR-GAW-3-3
painting of Lifting beams,cat walks and other similar structures-painting hoist machinery,
on sand blasted surfaces with two coats of zinc phosphate primer (airless spray preferred)
40microns/coat and twocoats of alkyd based micaccous iron oxide paint , 65 microns/coat
cost of all materials, labour, scaffolding etc., complete with all leads and
all lifts
DATA:
17.50 Sqm/Hr
5.71
Hr
6
Hr
Say
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
particulars
B. MACHINERY:
Sl No
Description
Sqm/Hr
UNIT :
Unit
Quantity
ltr
ltr
ltr
ltr
100 sqm
28.00
2.80
Rate
in Rs.
223.00
140.00
Amount
in Rs.
6244
392
20.00
2.00
196.00
140.00
3920
280
3.00
Total cost of Materials
41.00
123
10959.00
Unit
Quantity
Hr
Hr
Hr
Unit
Rs:
6.00
Rate
in Rs.
121.40
Amount
in Rs.
728.40
6.00
6.00
241.30
767.30
RS:
1447.80
4603.80
6780.00
Rs:
Amount
in Rs.
1093.20
6600.00
4425.00
12118.20
Quantity
Day
6.00
Day
15.00
Day
15.00
Total cost of Labour
Rate
in Rs.
182.20
440.00
295.00
312
121.20
0.14 17.00
138.20
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0
Total
0.03
IRR-GAW-3-4
.
DATA:
14%
100.00 sqm
Rate per sqm
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
4305.41
Rs:
Rs:
10959.00
6780.00
12118.20
29857.20
0.00
29857.20
895.72
30752.92
4305.41
35058.32
350.60
17.50 Sqm/Hr
5.71
Hr
6
Hr
Say
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
7
1
2
3
Unit
Quantity
ltr
ltr
ltr
ltr
ltr
ltr
Description
C. LABOUR:
Sl No
1
2
3
UNIT :
particulars
B. MACHINERY:
Sl No
Description
Sqm/Hr
100 sqm
28.00
2.80
Rate
in Rs.
223.00
140.00
Amount
in Rs.
6244
392
15.00
1.50
17.00
1.70
196.00
140.00
240.00
140.00
2940
210
4080
238
3.00
Total cost of Materials
41.00
123
14227.00
Unit
Quantity
Hr
6.00
Hr
6.00
Hr
6.00
Total cost of Machinery
Unit
Quantity
Day
6.00
Day
20.00
Day
20.00
Total cost of Labour
labour component/unit qty
157.90
Add contractor's profit and overhead charges
0.14 22.10
labour component/unit qty (including contractor's profit)
180.00
Rs:
Rate
in Rs.
121.40
Amount
in Rs.
728.40
241.30
767.30
Rs:
1447.80
4603.80
6780.00
Rs:
Amount
in Rs.
1093.20
8800.00
5900.00
15793.20
Rate
in Rs.
182.20
440.00
295.00
ABSTRACT:
313
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
5306.59
Rs:
Rs:
Total
0
Total
0.03
IRR-GAW-3-5
DATA:
14%
100.00 sqm
Rate per sqm
Rs:
14227.00
6780.00
15793.20
36800.20
0.00
36800.20
1104.01
37904.21
5306.59
43210.79
432.10
17.50 Sqm/Hr
5.71
Hr
6
Hr
Say
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
1
2
3
Unit
Quantity
ltr
ltr
ltr
ltr
Description
C. LABOUR:
Sl No
1
2
3
UNIT :
particulars
B. MACHINERY:
Sl No
Description
100 sqm
14.00
1.40
Rate
in Rs.
223.00
140.00
Amount
in Rs.
3122
196
26.00
2.60
240.00
140.00
6240
364
3.00
Total cost of Materials
41.00
Rs:
123
10045.00
Rate
in Rs.
121.40
Amount
in Rs.
728.40
241.30
767.30
1447.80
4603.80
6780.00
Rate
in Rs.
182.20
440.00
295.00
Amount
in Rs.
1093.20
8800.00
5900.00
15793.20
Unit
Quantity
Hr
6.00
Hr
6.00
Hr
6.00
Total cost of Machinery
Unit
Quantity
Day
6.00
Day
20.00
Day
20.00
Total cost of Labour
labour component/unit qty
157.90
Add contractor's profit and overhead charges
0.14 22.10
labour component/unit qty (including contractor's profit)
180.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for excise duty
(on 75 percent cost excluding cost of materials)
E. Add for transportation upto work site @
Sqm/Hr
Total
0
Total
0.03
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
10045.00
6780.00
15793.20
32618.20
0.00
32618.20
978.55
314
Total
F. Add for contractor's profit and overheads on (A+B
Total cost for
IRR-GAW-4
14%
100.00 sqm
Rate per sqm
Rs:
Rs:
4703.54
Rs:
Rs:
33596.75
4703.54
38300.29
383.00
17.50 Sqm/Hr
5.71
Hr
6
Hr
Say
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
7
B. MACHINERY:
Sl No
1
2
3
Unit
Quantity
ltr
13
ltr
25
ltr
2.5
ltr
40.00
ltr
4
Nos
2
LS
3.00
Total cost of Materials
Description
C. LABOUR:
Sl No
1
2
3
UNIT :
particulars
Description
Unit
Quantity
Hr
100.000 Sq.m
Rate
in Rs.
140
483
140.00
271.00
140.00
41.00
41.00
Rs:
Amount
in Rs.
1820.00
12075.00
350.00
10840.00
560.00
82.00
123.00
25850.00
6.00
Rate
in Rs.
121.40
Amount
in Rs.
728.40
Hr
Hr
6.00
6.00
241.30
767.30
1447.80
4603.80
6780.00
Unit
Quantity
Rate
in Rs.
182.20
440.00
295.00
Amount
in Rs.
1093.20
8800.00
5900.00
15793.20
Day
6.00
Day
20.00
Day
20.00
Total cost of Labour
labour component/unit qty
157.90
Add contractor's profit and overhead charges
0.14 22.10
labour component/unit qty (including contractor's profit)
180.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0.00%
Total
3%
Sqm/Hr
14%
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
25850.00
6780.00
15793.20
48423.20
0.00
48423.20
1452.70
49875.90
6982.63
315
100.00 sqm
Rate per sq.meter
Rs:
Rs:
56858.52
568.60
17.50 Sqm/Hr
5.71
Hr
6
Hr
Say
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
7
B. MACHINERY:
Sl No
1
2
3
C. LABOUR
Sl No
1
2
3
UNIT :
particulars
Unit
Quantity
ltr
13
ltr
28
ltr
2.8
ltr
17.00
ltr
1.7
Nos
2
LS
3.00
Total cost of Materials
Description
Unit
Quantity
Hr
6.00
Hr
6.00
Hr
6.00
Total cost of Machinery
Description
Unit
Quantity
Day
6.00
Day
20.00
Day
20.00
Total cost of Labour
labour component/unit qty
157.90
Add contractor's profit and overhead charges
0.14 22.10
labour component/unit qty (including contractor's profit)
180.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0.00%
Total
3%
Sqm/Hr
14%
100.000 Sq.m
Rate
in Rs.
140
175
140.00
240.00
140.00
41.00
41.00
Amount
in Rs.
1820.00
4900.00
392.00
4080.00
238.00
82.00
123.00
11635.00
Rate
in Rs.
121.40
Amount
in Rs.
728.40
241.30
767.30
1447.80
4603.80
6780.00
Rate
in Rs.
182.20
440.00
295.00
Amount
in Rs.
1093.20
8800.00
5900.00
15793.20
Rs.
Rs.
Rs.
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
11635.00
6780.00
15793.20
34208.20
0.00
34208.20
1026.25
35234.45
4932.82
316
100.00 sqm
Rate per sq.meter
Rs:
40167.27
401.70
17.50 Sqm/Hr
5.71
Hr
6
Hr
Say
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
7
B. MACHINERY:
Sl No
1
2
3
1
2
3
Unit
Quantity
ltr
13
ltr
14
ltr
1.4
ltr
40
ltr
4
Nos
2
LS
3
Total cost of Materials
Description
C. LABOUR:
Sl No
UNIT :
particulars
Unit
Quantity
Hr
6.00
Hr
6.00
Hr
6.00
Total cost of Machinery
Description
Unit
Quantity
Day
6.00
Day
13.00
Day
13.00
Total cost of Labour
labour component/unit qty
106.50
Add contractor's profit and overhead charges
0.14 14.90
labour component/unit qty (including contractor's profit)
121.40
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0.00%
Total
3%
Sqm/Hr
14%
100.00 sqm
Rate per sq.meter
100.000 Sq.m
Rate
in Rs.
140
689
140.00
271
140.00
41
41
Rs:
Amount
in Rs.
1820.00
9646.00
196.00
10840.00
560.00
82.00
123.00
23267.00
Rate
in Rs.
121.40
Amount
in Rs.
728.40
241.30
767.30
Rs:
1447.80
4603.80
6780.00
Rs:
Amount
in Rs.
1093.20
5720.00
3835.00
10648.20
Rate
in Rs.
182.20
440.00
295.00
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
23267.00
6780.00
10648.20
40695.20
0.00
40695.20
1220.86
41916.06
5868.25
47784.30
477.80
317
CHAPTER-VI
3. The Leads for Steel and Cement shall be from the nearest market place to the Project area
4. For earth/rockfill embankments wherever initial lead of 1km is considered in the basic rate, the additional lead
charges are to be added as follows:
Additional lead charges for Earth, Murrum etc., shall be worked out for total lead involved and 1 km lead charges included
in basic rate shall be deducted from total lead charges. No loading and unloading charges shall be allowed for any item.
(same as above)
Example:
Total lead for earth from approved borrow area :
15 Km
Initial lead included in the basic rate in the SR :
1 Km
Lead chargRs.
84.10
Additional lead charges :
Lead charges for next 10Rs.
126
Total lead charges for 15Rs.
210.10
Less 1 km initial lead chaRs.
31.50 (-)
Net additional lead chargRs.
178.60
5. The initial lead up to 50 m as mentioned in some standard data items is meant for manual lead within the working area.
For conveyance of materials, the lead required from quarry/Borrow area/ Dump Area to worksite shall be added to the
data without deducting the 50 m initial lead charges
JUNGLE CLEARANCE :
Clearing thin jungle growth ( more than 50 percent open space ) including bushes
upto 30 cm / parthenium and other weeds including burning or disposing off the same
as directed etc., complete.
DATA:
RATE ANALYSIS
UNIT :
1000 sqm
A. MATERIALS:
318
Sl No
particulars
NIL
Unit
Quantity
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
370.00
295.00
Rs:
Amount
in Rs.
185.00
885.00
1070.00
0.00
0.00
Total cost of Materials
B. MACHINERY:
Sl No
Description
Unit
Quantity
NIL
Rate
in Rs.
0.00
0.00
Total hire charges of Machinery
C. LABOUR:
Sl No
1
2
Description
Unit
Quantity
work inspector
mazdoor
Day
Day
Total cost of Labour
labour component/unit qty
1.10
Add contractor's profit and overhead charges
0.14 0.20
labour component/unit qty (including contractor's profit)
1.30
0.50
3.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Rs:
Rs:
Rs:
Rs:
Total
D. Add for contractor's profit and overheads on
(A+B+C)
14.00% Rs:
Total cost for
1000.00 sqm
Rs:
Rate per
sqm
(A+B+C+D)/1000.0
Rs.
IRR-PMW-1-2
0.00
0.00
1070.00
1070.00
149.8
1219.80
1.20
Clearing thick jungle growth ( less than 50 percent open space ) including bushes
upto 30 cm / parthenium and other weeds including burning or disposing off the same as
directed etc., complete.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
particulars
UNIT :
Unit
Quantity
NIL
1000 sqm
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
370.00
295.00
Rs:
Amount
in Rs.
185.00
1475.00
1660.00
0.00
0.00
Total cost of Materials
B. MACHINERY:
Sl No
Description
Unit
Quantity
NIL
0.00
0.00
Total hire charges of Machinery
C. LABOUR:
Sl No
1
2
Description
work inspector
mazdoor
Unit
Day
Day
Total cost of Labour
labour component/unit qty
1.70
Add contractor's profit and overhead charges
0.14 0.20
labour component/unit qty (including contractor's profit)
1.90
Quantity
0.50
5.00
Rate
in Rs.
ABSTRACT:
319
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Rs:
Rs:
Rs:
Rs:
Total
0.00
0.00
1660.00
1660.00
IRR-PMW-1-3
232.4
1892.40
1.90
Removing stumps, tree roots, roots of bamboo clusters etc., upto 1.50 m girth
including excavation, stacking the materials neatly and levelling the surface etc., complete with
initial lead upto 50 m and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
particulars
UNIT :
Unit
Quantity
NIL
18 Nos.
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
370.00
295.00
Rs:
Amount
in Rs.
92.50
590.00
682.50
0.00
0.00
Total cost of Materials
B. MACHINERY:
Sl No
Description
Unit
Quantity
NIL
Rate
in Rs.
0.00
0.00
Total hire charges of Machinery
C. LABOUR:
Sl No
1
2
Description
Unit
Quantity
work inspector
mazdoor
Day
Day
Total cost of Labour
labour component/unit qty
37.90
Add contractor's profit and overhead charges
0.14 5.30
labour component/unit qty (including contractor's profit)
43.20
0.25
2.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Rs:
Rs:
Rs:
Rs:
Total
0.00
0.00
682.50
682.50
IRR-PMW-1-4
95.55
778.05
43.20
Removing stumps, tree roots, roots of bamboo cluster etc., with girth above 1.50 m
and upto 3.0 m including excavation, stacking the materials neatly and levelling the area etc.,
complete with initial lead upto 50 m and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
particulars
UNIT :
Unit
NIL
Quantity
8 Nos.
Rate
in Rs.
0.00
0.00
0.00
0.00
Rs:
Description
Unit
Quantity
Rate
Amount
in Rs.
0.00
0.00
0.00
Amount
320
in Rs.
NIL
0.00
0.00
Rs:
in Rs.
0.00
0.00
0.00
Rate
in Rs.
370.00
295.00
Rs:
Amount
in Rs.
92.50
590.00
682.50
0.00
0.00
Total hire charges of Machinery
C. LABOUR:
Sl No
1
2
Description
Unit
Quantity
work inspector
mazdoor
Day
Day
Total cost of Labour
labour component/unit qty
85.31
Add contractor's profit and overhead charges
0.14 11.94
labour component/unit qty (including contractor's profit)
97.30
0.25
2.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Rs:
Rs:
Rs:
Rs:
Total
0.00
0.00
682.50
682.50
IRR-PMW-1-5
95.55
778.10
97.30
Removing stumps, tree roots, roots of bamboo cluster etc., with girth
above 3.0 m and upto 5.0 m including excavation, stacking the materials neatly and levelling
the area etc., complete with initial lead upto 50 m and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
particulars
UNIT :
Unit
Quantity
NIL
5 Nos.
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
370.00
295.00
Rs:
Amount
in Rs.
185.00
1180.00
1365.00
0.00
0.00
Total cost of Materials
B. MACHINERY:
Sl No
Description
Unit
Quantity
NIL
0.00
0.00
Total hire charges of Machinery
C. LABOUR:
Sl No
1
2
Description
Unit
Quantity
work inspector
mazdoor
Day
Day
Total cost of Labour
labour component/unit qty
273.00
Add contractor's profit and overhead charges
0.14 38.20
labour component/unit qty (including contractor's profit)
311.20
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on
(A+B+C)
14.00% Rs:
Total cost for
5.00 Nos.
Rs:
Rate per each
(A+B+C+D)/5.0
Rs.
0.50
4.00
Rs:
Rs:
Rs:
Rs:
Rate
in Rs.
0.00
0.00
1365.00
1365.00
191.1
1556.10
311.20
321
IRR-PMW-1-6
Additional rate for every 0.5 m increase in girth of tree stump / stumps of bamboo cluster
beyond 5 m.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
particulars
UNIT :
Unit
Quantity
NIL
7 Nos.
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
370.00
295.00
Rs:
Amount
in Rs.
81.40
258.13
339.53
0.00
0.00
Total cost of Materials
B. MACHINERY:
Sl No
Description
Unit
Quantity
NIL
Rate
in Rs.
0.00
0.00
Total hire charges of Machinery
C. LABOUR:
Sl No
1
2
Description
Unit
Quantity
work inspector
mazdoor
Day
Day
Total cost of Labour
labour component/unit qty
48.50
Add contractor's profit and overhead charges
0.14 6.80
labour component/unit qty (including contractor's profit)
55.30
0.22
0.88
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Rs:
Rs:
Rs:
Rs:
Total
D. Add for contractor's profit and overheads on
(A+B+C)
14.00% Rs:
Total cost for
7.00 Nos.
Rs:
Rate per each
(A+B+C+D)/7.0
Rs.
IRR-PMW-1-7
0.00
0.00
339.53
339.53
47.5335
387.06
55.30
Cutting and stacking bamboos excluding removing stumps and roots etc., complete with
initial lead upto 50 m and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
particulars
UNIT :
Unit
Quantity
NIL
150 Nos.
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
370.00
Amount
in Rs.
185.00
0.00
0.00
Total cost of Materials
B. MACHINERY:
Sl No
Description
Unit
Quantity
NIL
0.00
0.00
Total hire charges of Machinery
C. LABOUR:
Sl No
1
Description
work inspector
Unit
Day
Quantity
0.50
Rate
in Rs.
322
mazdoor
Day
Total cost of Labour
labour component/unit qty
11.07
Add contractor's profit and overhead charges
0.14 1.55
labour component/unit qty (including contractor's profit)
12.60
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
5.00
295.00
Rs:
Rs:
Rs:
Rs:
Rs:
0.00
0.00
1660.00
1660.00
IRR-PMW-1-8
232.4
1892.40
12.60
Cutting and removing jauliflora bushes upto 1.5 m girth excluding removal of stumps and
including burning or disposing off the materials as directed with initial lead upto 50 m and all
lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
particulars
UNIT :
Unit
Quantity
NIL
100 Nos.
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
370.00
295.00
Rs:
Amount
in Rs.
185.00
885.00
1070.00
0.00
0.00
Total cost of Materials
B. MACHINERY:
Sl No
Description
Unit
Quantity
NIL
Rate
in Rs.
0.00
0.00
Total hire charges of Machinery
C. LABOUR:
Sl No
1
2
Description
Unit
Quantity
Day
Day
Total cost of Labour
labour component/unit qty
10.70
Add contractor's profit and overhead charges
0.14 1.50
labour component/unit qty (including contractor's profit)
12.20
work inspector
mazdoor
0.50
3.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Rs:
Rs:
Rs:
Rs:
Total
D. Add for contractor's profit and overheads on
(A+B+C)
14.00% Rs:
Total cost for
100.00 Nos
Rs:
Rate per each
(A+B+C+D)/100.0
Rs.
IRR-PMW-1-9
1475.00
1660.00
0.00
0.00
1070.00
1070.00
149.8
1219.80
12.20
Cutting and removing jauliflora bushes above 1.5 m upto 3.0 m girth excluding
removal of stumps and including burning or disposing off the materials as directed
with initial lead upto 50 m and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
particulars
UNIT :
Unit
Quantity
50 Nos
Rate
in Rs.
Amount
in Rs.
323
NIL
0.00
0.00
0.00
0.00
Rs:
0.00
0.00
0.00
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
370.00
295.00
Rs:
Amount
in Rs.
185.00
885.00
1070.00
Description
Unit
Quantity
NIL
Rate
in Rs.
0.00
0.00
Total hire charges of Machinery
C. LABOUR:
Sl No
1
2
Description
Unit
Quantity
work inspector
mazdoor
Day
Day
Total cost of Labour
labour component/unit qty
21.40
Add contractor's profit and overhead charges
0.14 3.00
labour component/unit qty (including contractor's profit)
24.40
0.50
3.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Rs:
Rs:
Rs:
Rs:
Total
0.00
0.00
1070.00
1070.00
IRR-PMW-1-10
149.8
1219.80
24.40
Cutting trees above 0.3 m and upto 0.6 m girth excluding removal of stumps and including
stacking the materials neatly as directed with initial lead upto 50 m and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
UNIT :
particulars
Unit
Quantity
LS
0.25
0.00
Description
Unit
Quantity
NIL
0.00
0.00
Total hire charges of Machinery
C. LABOUR:
Sl No
1
2
Description
Unit
work inspector
mazdoor
Day
Day
Total cost of Labour
labour component/unit qty
69.80
Add contractor's profit and overhead charges
0.14 9.80
labour component/unit qty (including contractor's profit)
79.60
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
Quantity
0.25
3.00
Rs:
Rs:
Rs:
Rs:
14 Nos.
Rate
in Rs.
150.00
0.00
Rs:
Amount
in Rs.
37.50
0.00
37.50
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
370.00
295.00
Rs:
Amount
in Rs.
92.50
885.00
977.50
37.50
0.00
977.50
1015.00
324
IRR-PMW-1-11
142.1
1157.10
82.70
Cutting trees above 0.6 m and upto 1.2 m girth excluding removal of stumps and including
stacking the materials neatly as directed with initial lead upto 50 m and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
UNIT :
particulars
Unit
Quantity
LS
0.25
0.00
Description
Unit
Quantity
NIL
4 Nos.
Rate
in Rs.
150.00
0.00
Rs:
Amount
in Rs.
37.50
0.00
37.50
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
370.00
295.00
Rs:
Amount
in Rs.
92.50
885.00
977.50
0.00
0.00
Total hire charges of Machinery
C. LABOUR:
Sl No
1
2
Description
Unit
Quantity
work inspector
mazdoor
Day
Day
Total cost of Labour
labour component/unit qty
244.40
Add contractor's profit and overhead charges
0.14 34.20
labour component/unit qty (including contractor's profit)
278.60
0.25
3.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Rs:
Rs:
Rs:
Rs:
Total
37.50
0.00
977.50
1015.00
IRR-PMW-1-12
142.1
1157.10
289.30
Cutting trees above 1.2 m and upto 1.8 m girth excluding removal of stumps and including
stacking the materials neatly as directed with initial lead upto 50 m and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
UNIT :
particulars
Unit
Quantity
LS
0.25
0.00
Description
Unit
Quantity
NIL
0.00
0.00
Total hire charges of Machinery
2 Nos.
Rate
in Rs.
150.00
0.00
Rs:
Amount
in Rs.
37.50
0.00
37.50
Rate
in Rs.
Amount
in Rs.
0.00
0.00
0.00
0.00
0.00
Rs:
C. LABOUR:
325
Sl No
1
2
Description
Unit
Quantity
work inspector
mazdoor
Day
Day
Total cost of Labour
labour component/unit qty
488.80
Add contractor's profit and overhead charges
0.14 68.40
labour component/unit qty (including contractor's profit)
557.20
0.25
3.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Rate
in Rs.
370.00
295.00
Rs:
Rs:
Rs:
Rs:
Rs:
Total
37.50
0.00
977.50
1015.00
IRR-PMW-1-13
142.1
1157.10
578.60
Cutting trees above 1.8 m and upto 2.4 m girth excluding removal of stumps and including
stacking the materials neatly as directed with initial lead upto 50 m and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
UNIT :
particulars
Unit
Quantity
LS
0.25
0.00
Description
Unit
Quantity
NIL
1 No.
Rate
in Rs.
150.00
0.00
Rs:
Amount
in Rs.
37.50
0.00
37.50
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
370.00
295.00
Rs:
Amount
in Rs.
92.50
885.00
977.50
0.00
0.00
Total hire charges of Machinery
C. LABOUR:
Sl No
1
2
Description
Unit
Quantity
Day
Day
Total cost of Labour
labour component/unit qty
977.50
Add contractor's profit and overhead charges
0.14 136.90
labour component/unit qty (including contractor's profit)
1114.40
work inspector
mazdoor
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0.25
3.00
Rs:
Rs:
Rs:
Rs:
IRR-PMW-1-14
DATA:
Amount
in Rs.
92.50
885.00
977.50
37.50
0.00
977.50
1015.00
142.1
1157.10
1157.10
Cutting trees above 2.4 m and upto 3.0 m girth excluding removal of stumps and including
stacking the materials neatly as directed with initial lead upto 50 m and all lifts.
RATE ANALYSIS
UNIT :
1 Nos.
326
A. MATERIALS:
Sl No
1
particulars
Unit
Quantity
LS
0.50
0.00
B. MACHINERY:
Sl No
Description
Unit
Quantity
NIL
Rate
in Rs.
150.00
0.00
Rs:
Amount
in Rs.
75.00
0.00
75.00
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
370.00
295.00
Rs:
Amount
in Rs.
92.50
1475.00
1567.50
0.00
0.00
Total hire charges of Machinery
C. LABOUR:
Sl No
1
2
Description
Unit
Quantity
work inspector
mazdoor
Day
Day
Total cost of Labour
labour component/unit qty
1567.50
Add contractor's profit and overhead charges
0.14 219.50
labour component/unit qty (including contractor's profit)
1787.00
0.25
5.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Rs:
Rs:
Rs:
Rs:
Total
D. Add for contractor's profit and overheads on
(A+B+C)
14.00% Rs:
Total cost for
1.00 Nos.
Rs:
Rate per each
(A+B+C+D)/1.0
Rs.
IRR-PMW-1-15
75.00
0.00
1567.50
1642.50
229.95
1872.45
1872.50
Additional rate for cutting tree for every 0.5 m increase in girth of tree beyond 3 m.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
UNIT :
particulars
Unit
Quantity
LS
0.15
0.00
B. MACHINERY:
Sl No
Description
Unit
Quantity
NIL
0.00
0.00
Total hire charges of Machinery
C. LABOUR:
Sl No
1
2
Description
work inspector
mazdoor
Unit
Day
Day
Total cost of Labour
labour component/unit qty
553.30
Add contractor's profit and overhead charges
0.14 77.50
labour component/unit qty (including contractor's profit)
630.80
Quantity
0.10
1.75
1 No
Rate
in Rs.
150.00
0.00
Rs:
Amount
in Rs.
22.50
0.00
22.50
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
370.00
295.00
Rs:
Amount
in Rs.
37.00
516.25
553.25
327
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Rs:
Rs:
Rs:
Rs:
Total
22.50
0.00
553.25
575.75
IRR-PMW-1-16
80.605
656.36
656.40
Cutting and burning or disposing off Apu / Jondu from marshy areas as directed with
initial lead upto 50 m and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
particulars
UNIT :
Unit
Quantity
NIL
1000 sqm
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
370.00
295.00
Rs:
Amount
in Rs.
370.00
3540.00
3910.00
0.00
0.00
Total cost of Materials
B. MACHINERY:
Sl No
Description
Unit
Quantity
NIL
Rate
in Rs.
0.00
0.00
Total hire charges of Machinery
C. LABOUR:
Sl No
1
2
Description
Unit
Quantity
work inspector
mazdoor
Day
Day
Total cost of Labour
labour component/unit qty
3.90
Add contractor's profit and overhead charges
0.14 0.50
labour component/unit qty (including contractor's profit)
4.40
1.00
12.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Rs:
Rs:
Rs:
Rs:
Total
D. Add for contractor's profit and overheads on
(A+B+C)
14.00% Rs:
Total cost for
1000.00 sqm
Rs:
Rate per sqm
(A+B+C+D)/1000.0
Rs.
IRR-PMW-2
IRR-PMW-2-1
0.00
0.00
3910.00
3910.00
547.4
4457.40
4.50
PRELIMINARY WORKS :
Earthwork excavation for trial pits / borrow pits and other investigation works in all kinds of
soil including boulders upto 30 cm dia and disposing off excavated soil as directed with lead
upto 10 m and lift upto 3 m.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
particulars
UNIT :
Unit
NIL
Quantity
0.00
0.00
10 cum
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
328
B. MACHINERY:
Sl No
Description
Unit
Quantity
NIL
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
370.00
295.00
Rs:
Amount
in Rs.
185.00
1770.00
1955.00
0.00
0.00
Total hire charges of Machinery
C. LABOUR:
Sl No
1
2
Description
Unit
Quantity
work inspector
mazdoor
Day
Day
Total cost of Labour
labour component/unit qty
195.50
Add contractor's profit and overhead charges
0.14 27.37
labour component/unit qty (including contractor's profit)
222.90
0.50
6.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Rs:
Rs:
Rs:
Rs:
Total
D. Add for contractor's profit and overheads on
(A+B+C)
14.00% Rs:
Total cost for
10.00 cum
Rs:
Rate per cum
(A+B+C+D)/100.0
Rs.
IRR-PMW-2-2
0.00
0.00
1955.00
1955.00
273.7
2228.70
222.90
Earthwork excavation for trial pits / borrow pits and other investigation works in soft
rock including disposing off the excavated rock as directed with lead upto 10 m and lift
upto 3 m.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
particulars
UNIT :
Unit
Quantity
NIL
10 cum
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
370.00
345.00
295.00
Rs:
Amount
in Rs.
185.00
345.00
2212.50
2742.50
0.00
0.00
Total cost of Materials
B. MACHINERY:
Sl No
Description
Unit
Quantity
NIL
0.00
0.00
Total hire charges of Machinery
C. LABOUR:
Sl No
1
2
3
Description
Unit
Quantity
work inspector
Crowbarman
mazdoor
Day
Day
Day
Total cost of Labour
labour component/unit qty
274.30
Add contractor's profit and overhead charges
0.14 38.40
labour component/unit qty (including contractor's profit)
312.70
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on
(A+B+C)
14.00% Rs:
Total cost for
10.00 cum
Rs:
Rate per cum
(A+B+C+D)/10.0
Rs.
0.50
1.00
7.50
Rs:
Rs:
Rs:
Rs:
Rate
in Rs.
0.00
0.00
2742.50
2742.50
383.95
3126.45
312.60
329
IRR-PMW-2-3
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
particulars
UNIT :
Unit
Quantity
5.00
0.00
Total cost of Materials
B. MACHINERY:
Sl No
1
C. LABOUR:
Sl No
1
2
3
4
Description
Description
Unit
Quantity
Hour
8.00
Rate
in Rs.
41.00
0.00
Rs:
Amount
in Rs.
205.00
0.00
205.00
Rate
in Rs.
99.00
Rs:
Amount
in Rs.
792.00
158.40
950.40
Rate
in Rs.
735.00
735.00
440.00
295.00
Rs:
Amount
in Rs.
1470.00
735.00
440.00
1180.00
3825.00
20%
Total hire charges of Machinery
Unit
Quantity
Day
Day
Day
Day
Total cost of Labour
labour component/unit qty
191.30
Add contractor's profit and overhead charges
0.14 26.80
labour component/unit qty (including contractor's profit)
218.10
Geophysist / Geologist
Graduate Engineer
Lab Assistant
mazdoor
2.00
1.00
1.00
4.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Rs:
Rs:
Rs:
Rs:
Total
D. Add for contractor's profit and overheads on
(A+B+C)
14.00% Rs:
Total cost for
20.00 Stages
Rs:
Rate per stage
(A+B+C+D)/20.0
Rs.
IRR-PMW-2-4
20 Stages
205.00
950.40
3825.00
4980.40
697.256
5677.66
283.90
Drilling 80 mm dia hole through over-burden using casing shoe bit vertical or inclined
upto 10 degrees to vertical as directed including cost of all materials, machinery, labour, water
charges, reaming, collection of wash samples at suitable intervals, logging and lebelling,
supplying honne wood core box, fixing casing pipes ( excluding cost of casing pipes ) etc.,
complete for depth upto 30 m from surface.
Note: 1. For drilling through over-burden beyond 30 m from surface increase the basic rate per
Rm by 10 percent.
Data:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
Unit
B. MACHINERY:
Sl No
1
particulars
UNIT :
Description
Unit
Hour
Quantity
3.00
3.00
3.00
3.00
Quantity
1.00
3.00 Rm
Rate
in Rs.
116.67
28.61
1.75
247.50
Rs:
Amount
in Rs.
350.00
85.83
5.25
742.50
1183.58
Rate
in Rs.
319.00
Amount
in Rs.
319.00
330
2
3
C. LABOUR:
Sl No
1
2
3
Description
Hour
Hour
Hour
LS
Total hire charges of Machinery
Unit
1.00
2.00
2.00
2.00
Quantity
Hour
Hour
Day
Total cost of Labour
labour component/unit qty
342.40
Add contractor's profit and overhead charges
0.14 47.90
labour component/unit qty (including contractor's profit)
390.30
1.00
2.00
2.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
255.80
20.40
170.60
82.00
847.80
Rate
in Rs.
244.90
96.10
295.00
Rs:
Amount
in Rs.
244.90
192.20
590.00
1027.10
Rs:
Rs:
Rs:
Rs:
Total
D. Add for contractor's profit and overheads on
(A+B+C)
14.00% Rs:
Total cost for
3.00 Rm
Rs:
Rate per Rm
(A+B+C+D)/3.0
Rs.
IRR-PMW-2-5
255.80
10.20
85.30
41.00
Rs:
1183.58
847.80
1027.10
3058.48
428.1872467
3486.67
1162.20
Drilling 76 mm dia ( NX ) core hole in hard rock using diamond core bit vertical / inclined
upto 10 degree to vertical as directed including cost of all materials, machinery, labour, water
charges, collection of core samples, logging and lebelling, supplying honne wood core box
and redrilling in case of collapse of sides etc., complete for depth upto 30 m from surface.
Data:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
2
3
Description
C. LABOUR:
Sl No
1
2
3
Unit
B. MACHINERY:
Sl No
1
particulars
UNIT :
Description
Unit
Quantity
3.00
3.00
3.00
3.00
3.00
Quantity
Hour
8.00
Hour
8.00
Hour
16.00
Hour
16.00
LS
5.00
Total hire charges of Machinery
Unit
Hour
Hour
Day
Total cost of Labour
labour component/unit qty
1362.30
Add contractor's profit and overhead charges
0.14 190.70
labour component/unit qty (including contractor's profit)
1553.00
Quantity
8.00
16.00
2.00
3.00 Rm
Rate
in Rs.
848.00
85.83
226.13
23.32
556.88
Rs:
Amount
in Rs.
2544.00
257.50
678.40
69.96
1670.63
5220.49
Rate
in Rs.
319.00
255.80
10.20
85.30
41.00
Rs:
Amount
in Rs.
2552.00
2046.40
163.20
1364.80
205.00
6331.40
Rate
in Rs.
244.90
96.10
295.00
Rs:
Amount
in Rs.
1959.20
1537.60
590.00
4086.80
331
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Rs:
Rs:
Rs:
Rs:
Total
D. Add for contractor's profit and overheads on
(A+B+C)
14.00% Rs:
Total cost for
3.00 Rm
Rs:
Rate per Rm
(A+B+C+D)/3.0
Rs.
NOTE:
5220.49
6331.40
4086.80
15638.69
2189.4159
17828.10
5942.70
1. For drilling in hard rock beyond 30 m upto 60 m from surface increase the basic
rate per Rm by 25 percent.
2. For drilling in hard rock beyond 60 m upto 90 m from surface increase the basic
rate per Rm by 40 percent.
IRR-PMW-2-5-A
New Item 2014-155
Drilling 76 mm dia ( NX ) core hole in all types of rocks (other than Hard Rock) including
Masonry/CC (where drilling is not possible by casing shoe) using diamond core bit vertical /
inclined upto 10 degree to vertical as directed including cost of all materials, machinery, labour,
water charges, and redrilling in case of collapse of sides etc., complete for depth upto 30 m from
surface for Primary and Secondary Holes
Drilling 76 mm dia ( NX ) core hole in all types of rock
DATA:
For drilling upto 30 m from surface the rate of drilling is assumed at 3 m per day for analysis.
For rate analysis combination of diamond bit and reamer shell is assumed.
500 m long 25 mm dia GI pipe line and 50 m long 25 mm dia water hose are assumed.
For 30 m drilling average 16.5 m extension rods with coupling sleeves required.
Use rate of materials :
Cost of NX diamond core bit @
Rs:
12720.00 / Each
Life of diamond core bit in all types of rock (other than hard rock)
:
Use rate of diamond core bit per m drilling
( cost / life )
Cost of reamer shell @
Rs:
5150.00 / Each
Life of reamer shell in all types of rock (other than hard rock)
:
Use rate of reamer shell per m drilling
( cost / life )
Cost of 16.5 m extension rod @
Rs:
2120.00 / Rm
Life of extension rods
:
Use rate of 16.5 m length extension rods
( cost / life )
Data:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
4
2
3
Description
C. LABOUR:
Sl No
1
2
3
Unit
Quantity
B. MACHINERY:
Sl No
1
particulars
UNIT :
Description
Unit
3.00
3.00
3.00
Quantity
Hour
Hour
Hour
Hour
LS
Total hire charges of Machinery
Unit
Hour
Hour
Day
Total cost of Labour
labour component/unit qty
812.80
Add contractor's profit and overhead charges
0.14 113.80
labour component/unit qty (including contractor's profit)
926.60
4.78
4.78
9.55
9.55
2.99
Quantity
4.78
9.55
1.19
Rs:
10.57
Rs:
Rs:
100
Rs:
Rs:
2500
Rs:
12720.00
m
1203.41
5150.00
m
51.50
34980.00
m
13.99
3.00 Rm
Rate
in Rs.
1203.41
51.50
13.99
Rs:
Amount
in Rs.
3610.22
154.50
41.98
3806.69
Rate
in Rs.
319.00
255.80
10.20
85.30
41.00
Rs:
Amount
in Rs.
1523.54
1221.70
97.43
814.79
122.59
3780.05
Rate
in Rs.
244.90
96.10
295.00
Rs:
Amount
in Rs.
1169.64
917.76
351.05
2438.45
332
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on
14.00% Rs:
Total cost for
3.00 Rm
Rs:
Rate per Rm
(A+B+C+D)/3.0
Rs.
NOTE:
Rs:
Rs:
Rs:
Rs:
3806.69
3780.05
2438.45
10025.19
1403.526852
11428.72
3809.60
1. For drilling in all types of rocks (other than hard rock) including masonry/CC beyond 30 m
upto 60 m from surface increase the basic rate per Rm by 25 percent.
2. For drilling in all types of rocks (other than hard rock) including masonry/CC m from
surface increase the basic beyond 60 m upto 90 rate per Rm by 40 percent.
IRR-PMW-2-5-B
New Item 2014-156
Drilling 76 mm dia ( NX ) core hole in all types of rocks (other than Hard Rock) including
Masonry/CC (where drilling is not possible by casing shoe) using diamond core bit vertical /
inclined upto 10 degree to vertical as directed including cost of all materials, machinery, labour,
water charges, collection of core samples, logging and lebelling, supplying honne wood core box
and redrilling in case of collapse of sides etc., complete for depth upto 30 m from surface
for Test Holes
DATA:
For drilling upto 30 m from surface the rate of drilling is assumed at 3 m per day for analysis.
For rate analysis combination of diamond bit and reamer shell is assumed.
500 m long 25 mm dia GI pipe line and 50 m long 25 mm dia water hose are assumed.
For 30 m drilling average 16.5 m extension rods with coupling sleeves required.
Use rate of materials :
Cost of NX diamond core bit @
Rs:
12720.00 / Each
Life of diamond core bit in all types of rock (other than hard rock)
:
Use rate of diamond core bit per m drilling
( cost / life )
Cost of reamer shell @
Rs:
5150.00 / Each
Life of reamer shell in all types of rock (other than hard rock)
:
Use rate of reamer shell per m drilling
( cost / life )
Cost of double core barrel @
Rs:
13568.00 / Each
Life of double tube core barrel
:
Use rate of double tube core barrel per m drilling
( cost / life )
Cost of 16.5 m extension rod @
Rs:
2120.00 / Rm
Life of extension rods
:
Use rate of 16.5 m length extension rods
( cost / life )
Honne wood core box 1.5 x 0.32 x 0.12 m
Honne wood 0.033 cum @
Rs:
54000.00 / cum
Add for fixtures and painting @
10%
Add for labour charges @
15%
Cost of one box for storing
4 m samples
Use rate of core box per m drilling
Data:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
2
3
Unit
B. MACHINERY:
Sl No
1
particulars
UNIT :
Description
Unit
Hour
Hour
Hour
Hour
LS
Quantity
3.00
3.00
3.00
3.00
3.00
Quantity
4.78
4.78
9.55
9.55
2.99
Rs:
10.57
Rs:
Rs:
100
Rs:
Rs:
100
Rs:
Rs:
2500
Rs:
12720.00
m
1203.41
5150.00
m
51.50
13568.00
m
135.68
34980.00
m
13.99
Rs:
Rs:
Rs:
Rs:
Rs:
1782.00
178.20
267.30
2227.50
556.88
3.00 Rm
Rate
in Rs.
1203.41
51.50
135.68
13.99
556.88
Rs:
Amount
in Rs.
3610.22
154.50
407.04
41.98
1670.63
5884.36
Rate
in Rs.
319.00
255.80
10.20
85.30
41.00
Amount
in Rs.
1523.54
1221.70
97.43
814.79
122.59
333
Description
Unit
Quantity
Hour
Hour
Day
Total cost of Labour
labour component/unit qty
813.30
Add contractor's profit and overhead charges
0.14 113.90
labour component/unit qty (including contractor's profit)
927.20
4.78
9.55
1.19
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on
14.00% Rs:
Total cost for
3.00 Rm
Rs:
Rate per Rm
(A+B+C+D)/3.0
Rs.
NOTE:
IRR-PMW-2-6
Rs:
Rs:
Rs:
Rs:
Rs:
3780.05
Rate
in Rs.
244.90
96.10
295.00
Rs:
Amount
in Rs.
1169.64
917.95
352.23
2439.82
5884.36
3780.05
2439.82
12104.23
1694.59206
13798.82
4599.60
1. For drilling in all types of rocks (other than hard rock) including masonry/CC beyond 30 m
upto 60 m from surface increase the basic rate per Rm by 25 percent.
2. For drilling in all types of rocks (other than hard rock) including masonry/CC m from
surface increase the basic beyond 60 m upto 90 rate per Rm by 40 percent.
Drilling 47 mm (BX )dia core hole in hard rock using diamond core bit vertical / inclined
upto 10 degree to vertical as directed including cost of all materials, machinery, labour, water
charges,collection of core samples,logging, lebelling, supplying honne wood core box
and redrilling in case of collapse of sides etc., complete for depth upto 30 m from surface.
Data:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
2
3
Description
C. LABOUR:
Sl No
1
2
3
Unit
B. MACHINERY:
Sl No
1
particulars
UNIT :
Description
Unit
3.00
3.00
3.00
3.00
3.00
Quantity
Hour
8.00
Hour
8.00
Hour
16.00
Hour
16.00
LS
5.00
Total hire charges of Machinery
Unit
Hour
Hour
Day
Total cost of Labour
labour component/unit qty
1362.30
Add contractor's profit and overhead charges
0.14 190.70
labour component/unit qty (including contractor's profit)
1553.00
ABSTRACT:
A. Cost of Materials
Quantity
Quantity
8.00
16.00
2.00
Rs:
3.00 Rm
Rate
in Rs.
706.67
85.83
226.13
23.32
556.88
Rs:
Amount
in Rs.
2120.00
257.50
678.40
69.96
1670.63
4796.49
Rate
in Rs.
319.00
255.80
10.20
85.30
41.00
Rs:
Amount
in Rs.
2552.00
2046.40
163.20
1364.80
205.00
6331.40
Rate
in Rs.
244.90
96.10
295.00
Rs:
Amount
in Rs.
1959.20
1537.60
590.00
4086.80
4796.49
334
Rs:
Rs:
Rs:
Total
D. Add for contractor's profit and overheads on
(A+B+C)
14.00% Rs:
Total cost for
3.00 Rm
Rs:
Rate per Rm
(A+B+C+D)/3.0
Rs.
NOTE:
6331.40
4086.80
15214.69
2130.0559
17344.74
5781.60
1. For drilling in hard rock beyond 30 m upto 60 m from surface increase the
basic rate for drilling upto 30 m from surface by 25 percent per Rm.
2. For drilling in hard rock beyond 60 m upto 90 m from surface increase the basic
rate for drilling upto 30 m from surface by 40 percent per Rm.
IRR-PMW-2-6-A
New Item 2014-157
Drilling 47 mm (BX )dia core hole in all types of rocks (other than Hard Rock) including
Masonry/CC (where drilling is not possible by casing shoe) using diamond core bit vertical /
inclined upto 10 degree to vertical as directed including cost of all materials, machinery, labour,
water charges, and redrilling in case of collapse of sides etc., complete for depth upto 30 m
DATA:
For drilling upto 30 m from surface the rate of drilling is assumed at 3 m per day for analysis.
For rate analysis combination of diamond bit and reamer shell is assumed.
500 m long 25 mm dia GI pipe line and 50 m long 25 mm dia water hose are assumed.
For 30 m drilling average 16.5 m extension rods with coupling sleeves required.
Use rate of materials :
Cost of BX diamond core bit @
Rs:
10600.00 / Each
Life of diamond core bit in all types of rock (other than hard rock)
:
Use rate of diamond core bit per m drilling
( cost / life )
Cost of reamer shell @
Rs:
5150.00 / Each
Life of reamer shell in all types of rock (other than hard rock)
:
Use rate of reamer shell per m drilling
( cost / life )
Cost of 16.5 m extension rod @
Rs:
2120.00 / Rm
Life of extension rods
:
Use rate of 16.5 m length extension rods
( cost / life )
Data:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
4
2
3
Description
C. LABOUR:
Sl No
1
2
3
Unit
Quantity
B. MACHINERY:
Sl No
1
particulars
UNIT :
Description
Unit
3.00
3.00
3.00
Quantity
Hour
Hour
Hour
Hour
LS
Total hire charges of Machinery
Unit
Hour
Hour
Day
Total cost of Labour
labour component/unit qty
812.80
Add contractor's profit and overhead charges
0.14 113.80
labour component/unit qty (including contractor's profit)
926.60
4.78
4.78
9.55
9.55
2.99
Quantity
4.78
9.55
1.19
Rs:
10.57
Rs:
Rs:
100
Rs:
Rs:
2500
Rs:
10600.00
m
1002.84
5150.00
m
51.50
34980.00
m
13.99
3.00 Rm
Rate
in Rs.
1002.84
51.50
13.99
Rs:
Amount
in Rs.
3008.51
154.50
41.98
3204.99
Rate
in Rs.
319.00
255.80
10.20
85.30
41.00
Rs:
Amount
in Rs.
1523.54
1221.70
97.43
814.79
122.59
3780.05
Rate
in Rs.
244.90
96.10
295.00
Rs:
Amount
in Rs.
1169.64
917.76
351.05
2438.45
335
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Rs:
Rs:
Rs:
Rs:
Total
D. Add for contractor's profit and overheads on
14.00% Rs:
Total cost for
3.00 Rm
Rs:
Rate per Rm
(A+B+C+D)/3.0
Rs.
NOTE:
IRR-PMW-2-7
3204.99
3780.05
2438.45
9423.49
1319.288441
10742.78
3580.90
1. For drilling in all types of rocks (other than hard rock) including masonry/CC beyond 30 m
upto 60 m from surface increase the basic rate per Rm by 25 percent.
2. For drilling in all types of rocks (other than hard rock) including masonry/CC m from
surface increase the basic beyond 60 m upto 90 rate per Rm by 40 percent.
Data:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
particulars
B. MACHINERY:
Sl No
1
Description
UNIT :
Unit
Quantity
Each
cum
Total cost of Materials
Unit
18.00
1.00
Quantity
NIL
0.00
0.00
Total hire charges of Machinery
C. LABOUR:
Sl No
1
2
3
Description
Unit
Quantity
work inspector
Stone chiseller Cl- I
mazdoor
Day
Day
Day
Total cost of Labour
labour component/unit qty
91.10
Add contractor's profit and overhead charges
0.14 12.80
labour component/unit qty (including contractor's profit)
103.90
1.00
1.00
3.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Rs:
Rs:
Rs:
Rs:
Total
D. Add for contractor's profit and overheads on
(A+B+C)
14.00% Rs:
Total cost for
18.00 Nos.
Rs:
Rate per each
(A+B+C+D)/18.0
Rs.
IRR-PMW-2-8
18 Nos.
Rate
in Rs.
23.00
107.00
Rs:
Amount
in Rs.
414.00
107.00
521.00
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
370.00
385.00
295.00
Rs:
Amount
in Rs.
370.00
385.00
885.00
1640.00
521.00
0.00
1640.00
2161.00
302.54
2463.54
136.90
Data:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
particulars
UNIT :
Unit
Each
kg
cum
Quantity
10.00
91.00
0.25
10 Nos.
Rate
in Rs.
23.00
4.00
1145.00
Amount
in Rs.
230.00
364.00
286.25
336
B. MACHINERY:
Sl No
Description
cum
cum
cum
Total cost of Materials
Unit
0.15
0.10
0.25
Quantity
NIL
1210.00
875.00
462.00
Rs:
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
370.00
385.00
295.00
Rs:
Amount
in Rs.
370.00
1155.00
1180.00
2705.00
0.00
0.00
Total hire charges of Machinery
C. LABOUR:
Sl No
1
2
3
Description
Unit
Quantity
work inspector
Stone chiseller Cl- I
mazdoor
Day
Day
Day
Total cost of Labour
labour component/unit qty
270.50
Add contractor's profit and overhead charges
0.14 37.90
labour component/unit qty (including contractor's profit)
308.40
1.00
3.00
4.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Rs:
Rs:
Rs:
Rs:
Total
IRR-PMW-2-9
181.50
87.50
115.50
1264.75
1264.75
0.00
2705.00
3969.75
555.765
4525.52
452.60
Rs:
4.00
Data:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
particulars
B. MACHINERY:
Sl No
Description
UNIT :
Unit
Each
kg
cum
cum
cum
cum
cum
cum
Total cost of Materials
Unit
Quantity
1.00
262.00
0.50
0.30
0.20
0.25
0.04
0.60
Quantity
NIL
0.00
0.00
Total hire charges of Machinery
C. LABOUR:
Sl No
1
Description
work inspector
Unit
Day
Quantity
1.00
1 No.
Rate
in Rs.
23.00
4.00
1145.00
1210.00
875.00
318.00
340.00
462.00
Rs:
Amount
in Rs.
23.00
1048.00
572.50
363.00
175.00
79.50
13.60
277.20
2551.80
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
370.00
Amount
in Rs.
370.00
337
2
3
4
Day
Day
Day
Total cost of Labour
labour component/unit qty
2382.50
Add contractor's profit and overhead charges
0.14 333.60
labour component/unit qty (including contractor's profit)
2716.10
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
0.50
1.00
5.00
385.00
345.00
295.00
Rs:
Rs:
Rs:
Rs:
Rs:
2551.80
0.00
2382.50
4934.30
690.802
5625.10
5625.10
MAINTENANCE WORKS :
Removing dry stone rock-toe / rivetment and filter layers below rock-toe/ rivetment
including stacking all materials separately as directed with initial lead upto 50 m and all lifts.
Data:
RATE ANALYSIS
A. MATERIALS:
Sl No
particulars
UNIT :
Unit
Quantity
NIL
105 cum
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
370.00
345.00
295.00
Rs:
Amount
in Rs.
370.00
2070.00
14160.00
16600.00
0.00
0.00
Total cost of Materials
B. MACHINERY:
Sl No
Description
Unit
Quantity
NIL
Rate
in Rs.
0.00
0.00
Total hire charges of Machinery
C. LABOUR:
Sl No
1
2
3
Description
Unit
Quantity
Day
Day
Day
Total cost of Labour
labour component/unit qty
158.10
Add contractor's profit and overhead charges
0.14 22.10
labour component/unit qty (including contractor's profit)
180.20
work inspector
Mason Cl- II
mazdoor
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on
(A+B+C)
14.00% Rs:
Total cost for
105.00 cum
Rs:
Rate per cum
(A+B+C+D)/105.0
Rs.
IRR-PMW-3-2
192.50
345.00
1475.00
2382.50
1.00
6.00
48.00
Rs:
Rs:
Rs:
Rs:
0.00
0.00
16600.00
16600.00
2324
18924.00
180.20
338
Data:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
6
particulars
UNIT :
Unit
Quantity
B. MACHINERY:
Sl No
Description
Unit
15.30
15.30
15.30
9.00
57.60
44.00
Quantity
NIL
100 sqm
Rate
in Rs.
462.00
0.00
0.00
0.00
0.00
0.00
Rs:
Amount
in Rs.
7068.60
0.00
0.00
0.00
0.00
0.00
7068.60
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
370.00
345.00
295.00
Rs:
Amount
in Rs.
370.00
1725.00
9735.00
11830.00
0.00
0.00
Total hire charges of Machinery
C. LABOUR:
Sl No
1
2
3
Description
Unit
Quantity
work inspector
Mason Cl- II
mazdoor
Day
Day
Day
Total cost of Labour
labour component/unit qty
118.30
Add contractor's profit and overhead charges
0.14 16.60
labour component/unit qty (including contractor's profit)
134.90
1.00
5.00
33.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Rs:
Rs:
Rs:
Rs:
Total
D. Add for contractor's profit and overheads on
(A+B+C)
14.00% Rs:
Total cost for
100.00 sqm
Rs:
(A+B+C+D)/100.0
Rs.
Rate per sqm
IRR-PMW-3-3
7068.60
0.00
11830.00
18898.60
2645.804
21544.40
215.40
Re-constructing dry rubble rock-toe and filter media for rock-toe consisting of
sand 20 mm and 80 mm size graded aggregates satisfying filter criteria laid in layers of 15 cm
thick each using sand from approved quarry and stones and filter aggregates obtained from
rock-toe removed for re-construction including cost of all machinery, labour, laying filter and
stones to specified slopes, wedging with chips, finishing etc. complete with initial lead upto
50 m and all lifts.
Data:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
5
Unit
Quantity
Rubble ( available )
cum
Stone chips ( available )
cum
80-20 mm filter ( available )
cum
20 mm down filter ( available )
cum
Sand (Un-Screened) ( fresh from quarry )
cum
Total cost of Materials
B. MACHINERY:
Sl No
1
particulars
UNIT :
Description
Unit
58.20
8.70
19.40
12.10
9.80
Quantity
NIL
0.00
0.00
Total hire charges of Machinery
100 cum
Rate
in Rs.
0.00
0.00
0.00
0.00
462.00
Rs:
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
0.00
4527.60
4527.60
Amount
in Rs.
0.00
0.00
0.00
339
C. LABOUR:
Sl No
1
2
3
Description
Unit
Quantity
work inspector
Mason Cl- II
mazdoor
Day
Day
Day
Total cost of Labour
labour component/unit qty
169.50
Add contractor's profit and overhead charges
0.14 23.70
labour component/unit qty (including contractor's profit)
193.20
1.00
7.00
48.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Rs:
Rs:
Rs:
Rs:
Total
D. Add for contractor's profit and overheads on
(A+B+C)
14.00% Rs:
Total cost for
100.00 cum
Rs:
Rate per cum
(A+B+C+D)/100.0
Rs.
IRR-PMW-3-4
Amount
in Rs.
370.00
2415.00
14160.00
16945.00
4527.60
0.00
16945.00
21472.60
3006.164
24478.76
244.80
Removing and resetting disturbed Yarguntla / Shahabad / Talikot / PCC / Other types
of slab lining set in CM 1 : 3 including flush cement mortar pointing in CM 1 : 3 with
lead upto 50 m and all lifts.
Data:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
particulars
Cement 43 Gr
Sand (Screened )
B. MACHINERY:
Sl No
1
Description
UNIT :
Unit
Quantity
kg
cum
Total cost of Materials
Unit
101.00
0.21
Quantity
NIL
0.00
0.00
Total hire charges of Machinery
C. LABOUR:
Sl No
Description
Unit
Quantity
1
2
3
4
work inspector
Day
Mason Class I
Day
mazdoor
Day
Cartman with Double Bullock cart for water
Day
Total cost of Labour
labour component/unit qty
40.80
Add contractor's profit and overhead charges
0.14 5.70
labour component/unit qty (including contractor's profit)
46.50
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
1.00
4.00
6.00
1.00
Rs:
Rs:
Rs:
Rs:
IRR-PMW-3-5
Rate
in Rs.
370.00
345.00
295.00
Rs:
100 sqm
Rate
in Rs.
4.00
606.00
Rs:
Rate
in Rs.
Amount
in Rs.
404.00
127.26
531.26
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
370.00
385.00
295.00
395.00
Rs:
Amount
in Rs.
370.00
1540.00
1770.00
395.00
4075.00
531.26
0.00
4075.00
4606.26
644.8764
5251.14
52.50
340
Data:
RATE ANALYSIS
A. MATERIALS:
Sl No
particulars
UNIT :
Unit
Quantity
NIL
100 sqm
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
370.00
345.00
295.00
Rs:
Amount
in Rs.
370.00
2070.00
1770.00
4210.00
0.00
0.00
Total cost of Materials
B. MACHINERY:
Sl No
Description
Unit
Quantity
NIL
Rate
in Rs.
0.00
0.00
Total hire charges of Machinery
C. LABOUR:
Sl No
1
2
3
Description
Unit
Quantity
work inspector
Mason Class II
mazdoor
Day
Day
Day
Total cost of Labour
labour component/unit qty
42.10
Add contractor's profit and overhead charges
0.14 5.90
labour component/unit qty (including contractor's profit)
48.00
1.00
6.00
6.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Rs:
Rs:
Rs:
Rs:
Total
D. Add for contractor's profit and overheads on
(A+B+C)
14.00% Rs:
Total cost for
100.00 sqm
Rs:
Rate per sqm
(A+B+C+D)/100.0
Rs.
IRR-PMW-3-6
0.00
0.00
4210.00
4210.00
589.4
4799.40
48.00
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
particulars
UNIT :
Unit
Quantity
NIL
18 Nos.
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
370.00
295.00
Rs:
Amount
in Rs.
370.00
590.00
960.00
0.00
0.00
Total cost of Materials
B. MACHINERY:
Sl No
Description
Unit
Quantity
NIL
0.00
0.00
Total hire charges of Machinery
C. LABOUR:
Sl No
1
2
Description
work inspector
mazdoor
Unit
Day
Day
Total cost of Labour
labour component/unit qty
53.33
Add contractor's profit and overhead charges
0.14 7.47
labour component/unit qty (including contractor's profit)
60.80
Quantity
1.00
2.00
Rate
in Rs.
341
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Rs:
Rs:
Rs:
Rs:
Total
0.00
0.00
960.00
960.00
IRR-PMW-3-7
134.4
1094.40
60.80
Removing and refixing disturbed km stone / sign board / hecto-metre stone etc., including
excavation, back filling with available stuff after refixing, forming base platform of size 90 x 90 x
7.5 cm including watering, ramming etc complete with all leads and lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
particulars
UNIT :
Unit
Quantity
NIL
8 Nos.
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
370.00
295.00
Rs:
Amount
in Rs.
370.00
590.00
960.00
0.00
0.00
Total cost of Materials
B. MACHINERY:
Sl No
Description
Unit
Quantity
NIL
Rate
in Rs.
0.00
0.00
Total hire charges of Machinery
C. LABOUR:
Sl No
1
2
Description
Unit
Quantity
work inspector
mazdoor
Day
Day
Total cost of Labour
labour component/unit qty
120.00
Add contractor's profit and overhead charges
0.14 16.80
labour component/unit qty (including contractor's profit)
136.80
1.00
2.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Rs:
Rs:
Rs:
Rs:
Total
0.00
0.00
960.00
960.00
134.4
1094.40
136.80
Data:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
particulars
UNIT :
Unit
NIL
Quantity
480 cum
Rate
in Rs.
0.00
0.00
0.00
0.00
Rs:
Description
Unit
Quantity
Rate
Amount
in Rs.
0.00
0.00
0.00
Amount
342
1
2
3
4
5
6
7
Angle dozer
Fuel / Energy charges
Shovel 0.50 cum capacity
Fuel / Energy charges
Tippers 5.00 cum capacity 4 Nos.
Fuel / Energy charges
Pump 5 hp ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Vibratory pad foot roller 8 tonne
Fuel / Energy charges
Sundries
C. LABOUR:
Sl No
1
2
3
4
5
6
7
8
Description
Hour
5.00
Hour
5.00
Hour
8.00
Hour
8.00
Hour
32.00
Hour
32.00
Hour
2.00
Hour
2.00
Hour
4.00
Hour
4.00
Hour
6.00
Hour
6.00
LS
2.00
Total hire charges of Machinery
Unit
Quantity
Hour
Hour
Hour
Hour
Hour
Hour
Day
Day
Total cost of Labour
labour component/unit qty
24.40
Add contractor's profit and overhead charges
0.14 3.40
labour component/unit qty (including contractor's profit)
27.80
4.00
8.00
32.00
3.00
5.00
6.00
2.00
4.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Rs:
Rs:
Rs:
Rs:
Total
D. Add for contractor's profit and overheads on
(A+B+C)
14.00% Rs:
Total cost for
480.00 cum
Rs:
Rate per cum
(A+B+C+D)/480.0
Rs.
IRR-PMW-3-9
in Rs.
1715.50
656.00
1003.10
511.50
446.70
322.20
10.20
85.30
402.50
322.20
1342.20
1108.30
41.00
Rs:
in Rs.
8577.50
3280.00
8024.80
4092.00
14294.40
10310.40
20.40
170.60
1610.00
1288.80
8053.20
6649.80
82.00
66453.90
Rate
in Rs.
204.10
204.10
153.10
96.10
153.10
227.80
370.00
295.00
Rs:
Amount
in Rs.
816.40
1632.80
4899.20
288.30
765.50
1366.80
740.00
1180.00
11689.00
0.00
66453.90
11689.00
78142.90
10940.006
89082.91
185.60
Data:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
particulars
UNIT :
Unit
NIL
Quantity
0.00
0.00
Description
Angle dozer 90 hp
Fuel / Energy charges
Shovel 0.50 cum capacity
Fuel / Energy charges
Tippers 5.00 cum capacity 3 Nos.
Fuel / Energy charges
Unit
Hour
Hour
Hour
Hour
Hour
Hour
Quantity
3.50
3.50
8.00
8.00
24.00
24.00
325 cum
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
1715.50
656.00
1003.10
511.50
446.70
322.20
Amount
in Rs.
6004.25
2296.00
8024.80
4092.00
10720.80
7732.80
343
4
5
6
7
Pump 5 hp ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Vibratory pad foot roller 8 tonne
Fuel / Energy charges
Sundries
C. LABOUR:
Sl No
1
2
3
4
5
6
7
8
Description
Hour
Hour
Hour
Hour
Hour
Hour
LS
Total hire charges of Machinery
Unit
1.50
1.50
3.00
3.00
4.00
4.00
2.00
Quantity
Hour
Hour
Hour
Hour
Hour
Hour
Day
Day
Total cost of Labour
labour component/unit qty
29.10
Add contractor's profit and overhead charges
0.14 4.10
labour component/unit qty (including contractor's profit)
33.20
3.50
8.00
24.00
1.50
3.00
4.00
2.00
4.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
10.20
85.30
402.50
322.20
1342.20
1108.30
41.00
Rs:
15.30
127.95
1207.50
966.60
5368.80
4433.20
82.00
51072.00
Rate
in Rs.
204.10
204.10
153.10
96.10
153.10
227.80
370.00
295.00
Rs:
Amount
in Rs.
714.35
1632.80
3674.40
144.15
459.30
911.20
740.00
1180.00
9456.20
Rs:
Rs:
Rs:
Rs:
Total
0.00
51072.00
9456.20
60528.20
IRR-PMW-3-10
8473.948
69002.15
212.30
Data:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
particulars
UNIT :
Unit
NIL
Quantity
0.00
0.00
Description
Angle dozer
Fuel / Energy charges
Shovel 0.50 cum capacity
Fuel / Energy charges
Tippers 5.00 cum capacity 5 Nos.
Fuel / Energy charges
Pump 5 hp ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Vibratory pad foot roller 8 tonne
Fuel / Energy charges
Sundries
Unit
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS
Quantity
4.00
4.00
8.00
8.00
40.00
40.00
4.00
4.00
7.00
7.00
7.50
7.50
2.00
612 cum
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
1715.50
656.00
1003.10
511.50
446.70
322.20
10.20
85.30
402.50
322.20
1342.20
1108.30
41.00
Amount
in Rs.
6862.00
2624.00
8024.80
4092.00
17868.00
12888.00
40.80
341.20
2817.50
2255.40
10066.50
8312.25
82.00
344
Description
Unit
Quantity
Hour
Hour
Hour
Hour
Hour
Hour
Day
Day
Total cost of Labour
labour component/unit qty
23.30
Add contractor's profit and overhead charges
0.14 3.30
labour component/unit qty (including contractor's profit)
26.60
4.00
8.00
40.00
4.00
7.00
7.50
2.00
6.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
76274.45
Rate
in Rs.
204.10
204.10
153.10
96.10
153.10
227.80
370.00
295.00
Rs:
Amount
in Rs.
816.40
1632.80
6124.00
384.40
1071.70
1708.50
740.00
1770.00
14247.80
Rs:
Rs:
Rs:
Rs:
Total
D. Add for contractor's profit and overheads on
(A+B+C)
14.00% Rs:
Total cost for
612.00 cum
Rs:
Rate per cum
(A+B+C+D)/612.0
Rs.
IRR-PMW-3-11
Rs:
0.00
76274.45
14247.80
90522.25
12673.115
103195.37
168.60
Data:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
particulars
UNIT :
Unit
NIL
Quantity
0.00
0.00
Angle dozer 90 hp
Fuel / Energy charges
Shovel 0.50 cum capacity
Fuel / Energy charges
Tippers 5.00 cum capacity 4 Nos.
Fuel / Energy charges
Pump 5 hp ( diesel )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Vibratory pad foot roller 8 tonne
Fuel / Energy charges
Sundries
C. LABOUR:
Sl No
1
2
Description
Description
Unit
Quantity
Hour
3.00
Hour
3.00
Hour
8.00
Hour
8.00
Hour
32.00
Hour
32.00
Hour
3.00
Hour
3.00
Hour
6.00
Hour
6.00
Hour
5.50
Hour
5.50
LS
2.00
Total hire charges of Machinery
Unit
Hour
Hour
Quantity
3.00
8.00
440 cum
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
1715.50
656.00
1003.10
511.50
446.70
322.20
10.20
85.30
402.50
322.20
1342.20
1108.30
41.00
Rs:
Amount
in Rs.
5146.50
1968.00
8024.80
4092.00
14294.40
10310.40
30.60
255.90
2415.00
1933.20
7382.10
6095.65
82.00
62030.55
Rate
in Rs.
204.10
204.10
Amount
in Rs.
612.30
1632.80
345
3
4
5
6
7
8
Hour
Hour
Hour
Hour
Day
Day
Total cost of Labour
labour component/unit qty
27.50
Add contractor's profit and overhead charges
0.14 3.90
labour component/unit qty (including contractor's profit)
31.40
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
32.00
3.00
6.00
5.50
2.00
6.00
153.10
96.10
153.10
227.80
370.00
295.00
Rs:
Rs:
Rs:
Rs:
Rs:
0.00
62030.55
12114.10
74144.65
IRR-PMW-3-12
10380.251
84524.90
192.10
Repairing rain cuts / resectioning canal slopes to required lines and grades as directed
using available soil including dressing, clod breaking, packing, tamping etc., complete with
all leads and lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
particulars
UNIT :
Unit
Quantity
NIL
1000 sqm
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
370.00
295.00
Rs:
Amount
in Rs.
370.00
2360.00
2730.00
0.00
0.00
Total cost of Materials
B. MACHINERY:
Sl No
Description
Unit
Quantity
NIL
Rate
in Rs.
0.00
0.00
Total hire charges of Machinery
C. LABOUR:
Sl No
1
2
Description
Unit
Quantity
Day
Day
Total cost of Labour
labour component/unit qty
2.73
Add contractor's profit and overhead charges
0.14 0.38
labour component/unit qty (including contractor's profit)
3.10
work inspector
mazdoor
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on
(A+B+C)
14.00% Rs:
Total cost for
1000.00 sqm
Rs:
Rate per sqm
(A+B+C+D)/1000.0
Rs.
IRR-PMW-3-13
4899.20
288.30
918.60
1252.90
740.00
1770.00
12114.10
1.00
8.00
Rs:
Rs:
Rs:
Rs:
0.00
0.00
2730.00
2730.00
382.2
3112.20
3.10
346
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
particulars
Wire brush
Coir brush
Sundries ( brooms, gloves etc )
B. MACHINERY:
Sl No
Description
UNIT :
Unit
Quantity
Each
Each
LS
Total cost of Materials
Unit
5.00
10.00
2.00
Quantity
NIL
100 Rm
Rate
in Rs.
41.00
45.00
41.00
Rs:
Amount
in Rs.
205.00
450.00
82.00
737.00
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
345.00
295.00
Rs:
Amount
in Rs.
690.00
1770.00
2460.00
0.00
0.00
Total hire charges of Machinery
C. LABOUR:
Sl No
1
2
Description
Unit
Quantity
Chiseller Cl II
mazdoor
Day
Day
Total cost of Labour
labour component/unit qty
24.60
Add contractor's profit and overhead charges
0.14 3.40
labour component/unit qty (including contractor's profit)
28.00
2.00
6.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Rs:
Rs:
Rs:
Rs:
Total
D. Add for contractor's profit and overheads on
(A+B+C)
14.00% Rs:
Total cost for
100.00 Rm
Rs:
Rate per Rm
(A+B+C+D)/100.0
Rs.
IRR-PMW-3-14
737.00
0.00
2460.00
3197.00
447.58
3644.58
36.40
Cleaning dam parapet inner face and top using oxalic acid and water by scrubbing /
brushing and washing to remove all surface coatings etc., complete .
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4
particulars
Oxalic acid
Wire brush
Coir brush
Sundries ( brooms, gloves etc )
B. MACHINERY:
Sl No
1
Description
UNIT :
Unit
Quantity
ltr
Each
Each
LS
Total cost of Materials
Unit
5.00
5.00
10.00
2.00
Quantity
NIL
0.00
0.00
Total hire charges of Machinery
C. LABOUR:
Sl No
1
mazdoor
Description
Unit
Day
Total cost of Labour
labour component/unit qty
17.70
Add contractor's profit and overhead charges
0.14 2.50
labour component/unit qty (including contractor's profit)
20.20
Quantity
6.00
100 Rm
Rate
in Rs.
76.00
41.00
45.00
41.00
Rs:
Amount
in Rs.
380.00
205.00
450.00
82.00
1117.00
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
295.00
Rs:
Amount
in Rs.
1770.00
1770.00
ABSTRACT:
347
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Rs:
Rs:
Rs:
Rs:
Total
D. Add for contractor's profit and overheads on
(A+B+C)
14.00% Rs:
Total cost for
100.00 Rm
Rs:
Rate per Rm
(A+B+C+D)/100.0
Rs.
IRR-PMW-3-20
1117.00
0.00
1770.00
2887.00
404.18
3291.18
32.90
Excavation and removal of silt and silt mixed with sand from canal bed in dry condition
including disposing off the same in spoil bank or on the canal embankment in layers as
directed etc., complete with initial lead upto 50 m and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
particulars
UNIT :
Unit
Quantity
NIL
10 cum
Rate
in Rs.
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
Rate
in Rs.
295.00
Rs:
Amount
in Rs.
1180.00
1180.00
0.00
0.00
Total cost of Materials
B. MACHINERY:
Sl No
1
Description
Unit
Quantity
NIL
Rate
in Rs.
0.00
0.00
Total hire charges of Machinery
C. LABOUR:
Sl No
1
Description
Unit
Quantity
mazdoor
Day
Total cost of Labour
labour component/unit qty
118.00
Add contractor's profit and overhead charges
0.14 16.50
labour component/unit qty (including contractor's profit)
134.50
4.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Rs:
Rs:
Rs:
Rs:
Total
D. Add for contractor's profit and overheads on
(A+B+C)
14.00% Rs:
Total cost for
10.00 cum
Rs:
Rate per cum
(A+B+C+D)/10.0
Rs.
IRR-PMW-3-21
0.00
0.00
1180.00
1180.00
165.2
1345.20
134.50
Excavation and removal of silt or silt mixed with sand in slussy condition from canal bed
including disposing off the same in spoil bank or on the canal embankment in layers as
directed etc., complete with initial lead upto 50 m and all lifts.
DATA:
RATE ANALYSIS
A. MATERIALS:
Sl No
1
particulars
UNIT :
Unit
NIL
Quantity
12 cum
Rate
in Rs.
0.00
0.00
Total cost of Materials
B. MACHINERY:
Sl No
1
Description
NIL
Unit
Quantity
0.00
0.00
0.00
0.00
Rs:
Amount
in Rs.
0.00
0.00
0.00
0.00
0.00
Amount
in Rs.
0.00
0.00
Rate
in Rs.
348
Description
Unit
Quantity
mazdoor
Day
Total cost of Labour
labour component/unit qty
147.50
Add contractor's profit and overhead charges
0.14 20.70
labour component/unit qty (including contractor's profit)
168.20
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
6.00
Rs:
Rs:
Rs:
Rs:
Total
D. Add for contractor's profit and overheads on
(A+B+C)
14.00% Rs:
Total cost for
12.00 cum
Rs:
Rate per cum
(A+B+C+D)/12.0
Rs.
IRR-PMW-3-22
New Item5 - 2010-11
0.00
Rate
in Rs.
295.00
Rs:
Amount
in Rs.
1770.00
1770.00
0.00
0.00
1770.00
1770.00
247.8
2017.80
168.20
A. MATERIALS:
Sl No
Particulars
1
1
2
3
RATE ANALYSIS
Unit:
Unit
Quantity
NIL
C. LABOUR:
Sl No
Description
0.00
0.00
Unit
Hour
Hour
Hour
Hour
Hour
Hour
Unit
Quantity
2.70
2.70
8.00
8.00
40.00
40.00
Quantity
1
2
3
4
5
Rs:
807.00
Rate
in Rs.
0.00
0.00
Rs:
cum
Amount
in Rs
0.00
0.00
0.00
Rate
in Rs.
1715.50
656.00
1706.60
937.80
446.70
322.20
Rs:
Amount
in Rs
4631.85
1771.20
13652.80
7502.40
17868.00
12888.00
58314.25
Rate
in Rs.
204.10
204.10
153.10
370.00
295.00
Rs:
Amount
in Rs
551.07
1632.80
6124.00
370.00
590.00
9267.87
Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:
0.00
58314.25
9267.87
67582.12
9461.5
77043.62
95.50
349
A. MATERIALS:
Sl No
Particulars
1
NIL
RATE ANALYSIS
UNIT :
Unit
Quantity
Angle dozer 90 hp
Fuel / Energy charges
Pump 5 hp ( ele )
Fuel / Energy charges
Water tanker 8000 ltr
Fuel / Energy charges
Vibratory pad foot roller 8 tonne
Fuel / Energy charges
Sundries
Total hire charges of Machinery
C. LABOUR:
Sl No
Description
0.00
0.00
Unit
Quantity
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
LS
Unit
1
4
5
6
7
8
2.70
2.70
4.00
4.00
8.00
8.00
6.40
6.40
2.00
Quantity
2.70
4.00
8.00
6.40
1.00
2.00
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
14%
D.Add for contractor's profit and overheads on (A+B+C)
Total cost
for
807.00 cum
Rate per cum
(A+B+C+D)/807
IRR-PMW-3-24
A. MATERIALS:
Sl No
Particulars
1
NIL
807.00
Rate
in Rs.
0.00
0.00
Rs:
cum
Amount
in Rs
0.00
0.00
0.00
Rate
in Rs.
1715.50
656.00
3.00
38.00
402.50
322.20
1342.20
1108.30
41.00
Rs:
Amount
in Rs
4631.85
1771.20
12.00
152.00
3220.00
2577.60
8590.08
7093.12
82.00
28129.85
Rate
in Rs.
204.10
72.10
153.10
227.80
370.00
295.00
Rs:
Amount
in Rs
551.07
288.40
1224.80
1457.92
370.00
590.00
4482.19
Rs:
Rs:
Rs:
Rs:
Rs.
0.00
28129.85
4482.19
32612.04
4565.69
Rs: 37177.73
Rs: 46.10
RATE ANALYSIS
UNIT :
807.00 cum
Unit
Quantity
Rate
Amount
in Rs.
in Rs
0.00
0.00 0.00
0.00
0.00 0.00
Rs: 0.00
Unit
Hour
Quantity
10.00
Rate
Amount
in Rs.
in Rs
345.00 3450.00
350
Sundries
Total hire charges of Machinery
LS
C. LABOUR:
Sl No
Description
2.00
Unit
41.00 82.00
Rs: 3532.00
Quantity
Rate
Amount
in Rs.
in Rs
370.00 185.00
295.00 590.00
Rs: 775.00
1
2
work inspector
Day
0.50
mazdoor
Day
2.00
Total cost of Labour
labour component/unit qty
1.00
Add contractor's profit and overhead charges
14% 0.10
labour component/unit qty (including contractor's profit)
1.10
ABSTRAC
T:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
(A+B+C)
Total cost for
Rate per cum
IRR-PMW-3-25
Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:
14%
807.00 cum
(A+B+C+D)/807
0.00
3532.00
775.00
4307.00
602.98
4909.98
6.10
IRR-PMW-3-25(a)
2000 Sqm
A. MATERIALS
Sl. No.
1
Unit
Quantity
Description
Unit
NIL
Total hire charges of Machinery
Quantity
Description
Unit
Work Inspector
Day
Mazdoor
Day
Total Cost of Labour
Particulars
NIL
Total Cost of Materials
B. MACHINERY
Sl. No.
1
C. LABOUR
Sl. No.
1
2
ABSTRACT:
A.COST OF MATERIALS
B.COST OF MACHINERY
C.COST OF LABOUR
Rs.
Rs.
Rs.
0.00
0.00
9555.00
9555.00
1337.7
10892.70
5.4
Total
D. Add for Contractor's Profit and overheads
Total Cost for removal weed in the extent of
Rate per Sqm
IRR-PMW-3-25(b)
14%
2000 Sqm
(A+B+C+D)/2000
2000 Sqm
A. MATERIALS
Sl. No.
1
Particulars
NIL
Unit
Total Cost of Materials
Quantity
351
B. MACHINERY
Sl. No.
1
Description
Unit
NIL
Total hire charges of Machinery
Quantity
Description
Unit
Work Inspector
Day
Mazdoor
Day
Total Cost of Labour
Quantity
C. LABOUR
Sl. No.
1
2
ABSTRACT:
A.COST OF MATERIALS
B.COST OF MACHINERY
C.COST OF LABOUR
Rs.
Rs.
Rs.
0.00
0.00
13060.00
13060.00
1828.4
14888.40
7.4
Total
D. Add for Contractor's Profit and overheads
Total Cost for removal weed in the extent of
Rate per Sqm
IRR-PMW-3-25(c)
14%
2000 Sqm
(A+B+C+D)/2000
2000 Sqm
A. MATERIALS
Sl. No.
1
Unit
Quantity
Description
Unit
NIL
Total hire charges of Machinery
Quantity
Description
Unit
Work Inspector
Day
Mazdoor
Day
Total Cost of Labour
Quantity
Particulars
NIL
Total Cost of Materials
B. MACHINERY
Sl. No.
1
C. LABOUR
Sl. No.
1
2
ABSTRACT:
A.COST OF MATERIALS
B.COST OF MACHINERY
C.COST OF LABOUR
Rs.
Rs.
Rs.
0.00
0.00
8780.00
8780.00
1229.2
10009.20
5
Total
D. Add for Contractor's Profit and overheads
Total Cost for removal weed in the extent of
Rate per Sqm
IRR-PMW-3-25(d)
14%
2000 Sqm
(A+B+C+D)/2000
Removal of Jammu
RATE ANALYSIS
Unit :
2000 Sqm
A. MATERIALS
Sl. No.
1
Particulars
NIL
Unit
Quantity
Unit
Quantity
Description
NIL
352
Rs.
0.00
C. LABOUR
Sl. No.
1
2
Description
Unit
Work Inspector
Day
Mazdoor
Day
Total Cost of Labour
ABSTRACT:
A.COST OF MATERIALS
B.COST OF MACHINERY
C.COST OF LABOUR
Rs.
Rs.
Rs.
0.00
0.00
7415.00
7415.00
1038.1
8453.10
4.2
Total
D. Add for Contractor's Profit and overheads
Total Cost for removal weed in the extent of
Rate per Sqm
IRR-PMW-3-25(e)
14%
2000 Sqm
(A+B+C+D)/2000
2000 Sqm
A. MATERIALS
Sl. No.
1
Unit
Quantity
Description
Unit
NIL
Total hire charges of Machinery
Quantity
Description
Unit
Work Inspector
Day
Mazdoor
Day
Total Cost of Labour
Quantity
Particulars
NIL
Total Cost of Materials
B. MACHINERY
Sl. No.
1
C. LABOUR
Sl. No.
1
2
ABSTRACT:
A.COST OF MATERIALS
B.COST OF MACHINERY
C.COST OF LABOUR
Rs.
Rs.
Rs.
0.00
0.00
8780.00
8780.00
1229.2
10009.20
5
Total
D. Add for Contractor's Profit and overheads
Total Cost for removal weed in the extent of
Rate per Sqm
IRR-PMW-3-25(f)
14%
2000 Sqm
(A+B+C+D)/2000
2000 Sqm
A. MATERIALS
Sl. No.
1
Unit
Quantity
Description
Unit
NIL
Total hire charges of Machinery
Quantity
Particulars
NIL
Total Cost of Materials
B. MACHINERY
Sl. No.
1
C. LABOUR
353
Sl. No.
1
2
Description
Unit
Work Inspector
Day
Mazdoor
Day
Total Cost of Labour
ABSTRACT:
A.COST OF MATERIALS
B.COST OF MACHINERY
C.COST OF LABOUR
Rs.
Rs.
Rs.
0.00
0.00
2804.00
2804.00
392.56
3196.56
1.6
Total
D. Add for Contractor's Profit and overheads
Total Cost for removal weed in the extent of
Rate per Sqm
14%
2000 Sqm
(A+B+C+D)/2000
IRR-PMW-3-26
New Item 2014-158
PAINTING OF SLUICES FOR MAINTENANCE WORKS
Surface cleaning of metal surfaces by chemical cleaners and then by hand and power tool cleaners
and removing dust. After cleaniong, applying primary coat with one coat of Zinc rich
epoxy primer to a thickness of 100 microns, followed by finishing coats 2 coats with
Coal tar epoxy with material, labour, and all accessories with all leads and lifts.
Data:
A. Materials
Rate Analysis
Sl. No.
1
2
3
4
5
6
7
Particulars
Rust Cleaner/ Inhibitor
Zinc rich epoxy primer
Thinner@10%
Coal Tar epoxy paint
Thinner@10%
Wire Brush
Sundries (brushes, Ladders,
platforms)
Unit:
Unit
ltr
ltr
ltr
ltr
ltr
ltr
Quantity
13
14
1.4
40
4
2
LS
3
Total Cost of Materials
100 Sqm
Rate in Rs. Amount in Rs.
140.00
1820
689.00
9646
140.00
196
215
8600
140.00
560
41
82
41
123
21027
B. Machinery
Sl. No.
Particulars
Unit
Quantity
NIL
Total Cost of Machinery
C. Labour
Sl. No.
1
2
Particulars
Painter Class-II
Helper
Unit
Quantity Rate in Rs. Amount in Rs.
Day
20
345.00
6900
Day
20
295.00
5900
Total Cost of Machinery
12800
Labour Component/ Unit Qty.
128
Add Contractor's Profit and and Overhead Charges @
14%
17.92
Labour Component/ Unit Qty (including contractor' profit)
145.92
ABSTRACT:
A. Cost of Materials:
B. Hire Charges of Machinery
C. Cost of Labour
21027
0
12800
Total
33827
D. Add for Excise Duty on 75% cost excluding cost of material
0%
0
Total
33827
E. Add for transportation Charges upto worksite @
3% 1014.81
Total
34841.81
F. Add for Contractor's Profit and Overhead Charges @ 14%
14% 4877.8534
Total Cost per
100 Sqm
39719.6634
Rate per
Sqm
397.2
354
A. Manual Works
New extra items-- common item for all earth works using only manual labour
for all other works without involving contractors
COM_MWRK-1 (Manual)Excavation in all kinds of soil including boulders upto 0.30 m dia. for
foundations of canal cross drainage and other appurtenant structures
and placing excavated stuff neatly in specified dump area or disposing
off the same as directed etc., complete with initial lead upto 10 m and
per cum
initial lift upto 1.5 m. (WIthout involving the contractors for specified works )
With 3 Cum per day output
COM_MWRK-2 (Manual)Excavation in all kinds of soil/ HDR including boulders upto 0.30 m dia. for
foundations of canal cross drainage and other appurtenant structures
and placing excavated stuff neatly in specified dump area or disposing
off the same as directed etc., complete with initial lead upto 10 m and
per cum
initial lift upto 1.5 m. (WIthout involving the contractors for specified works )
With 2.5 Cum per day output
98.30
118.00
COM_MWRK-3 (Manual)Excavation in soft rock (including F&F) without blasting, including boulders upto 0.30 m dia. for
foundations of canal cross drainage and other appurtenant structures
and placing excavated stuff neatly in specified dump area or disposing
off the same as directed etc., complete with initial lead upto 10 m and
per cum
221.80
initial lift upto 1.5 m. (WIthout involving the contractors for specified works )
Soft rock 1.33 Cum/Day
COM_MWRK-4 (Manual)Excavation in hard rock, including boulders upto 0.30 m dia. for
foundations of canal cross drainage and other appurtenant structures
and placing excavated stuff neatly in specified dump area or disposing
off the same as directed etc., complete with initial lead upto 10 m and
per cum
initial lift upto 1.5 m. (WIthout involving the contractors for specified works )
Hard rock 0.67Cum/ day
440.30
355
COM-LDLFT-2014-15
COM-LDLFT
Chapter VII
LEAD/LIFT/LOADING & UNLOADING CHARGES
(WLL BE WITH E-N-C & TO INCORPORATE CHANGES YEARLY/ AS NEEDED)
FOR THE YEAR : 2014-15
COM-LDLFT
COM-LDLFT-1
1. For total lead upto 150 m ( including initial lead ) lead charges by head load only shall be
adopted irrespective of mode of conveyance.
2. For total lead exceeding 150 m conveyance by mechanical means only shall be adopted
irrespective of mode of conveyance.
3. The rates for loading at quarry including idle hire charges of trucks and hire charges per for
each kilometer and upto 5 km are cumulative and inclusive of total charges for preceding lead.
4. Unless otherwise specified lead charges for Earth / Sand / Gravel / Aggregates and Stones
are for loose volume and not for compacted or in-situ volume.
5. The rates for lift charges,lead charges, hire charges are cumulative and inclusive of
rates for preceding lift,lead and hire charges
6. Lift charges are not payable where conveyance of materials is by mechanical means to
final placing point.
7. Loading and unloading charges are not payable for conveyance by head load.
8. Loading charges are not payable for conveyance by mechanical means for disposal of
excavated materials beyond initial lead of 50 m wherever specified.
9. Loading and unloading charges are not payable for conveyance by mechanical means for
disposal of excavated materials beyond initial lead of 1 km wherever specified.
10. The rates for unloading of materials except earth, sand, gravel, coarse aggregate, rubble,
size stone and cut stone are inclusive of stacking.
11. Hire charges are per 1KM for tippers and trucks for tranport of materials from work site to dump
yard and other places are cumulative& includes previous km upto 5 kms
12. The lead & lift charges are inclusive of contractor's profit and overhead charges of
14%
FOR THE YEAR: 2013-14
A. (Lead) Conveyance Charges for materials by head load
Earth / Sand
/Gravel / Murrum/ Cement /
Total distance
Lime/ Surki/ Size ReinforceSl No. ( Total lead includes initial stone / Cut stone ment steel
lead )
Rubble / Coarse Str steel
aggregate Rs/ Rs / tonne
Cum
1
2
3
4
Total lead upto 50 m
1
(covered by item rate)
initial lead
initial lead
2
Total lead upto 100 m
48.00
28.00
3
Total lead upto 150 m
96.10
56.10
Notes: 1. No loading or unloading charges are admissible for conveyance by head load.
2. For total lead exceeding 150 m conveyance charges by mechanical means only shall
be adopted irrespective of mode of conveyance.
3. The Lead Charges are inclusive of 14% Contractor Profit and Overhead charges
COM-LDLFT-2
B.( Lead) Conveyance charges for machinery per kilometer for transporting materials
by tippers and trucks excluding loading, unloading and idle hire charges of machinery.
FOR THE YEAR: 2013-14
( No loading and unloading charges allowed for machinery loading and unloading )
Sl No.
Distance
1
1
2
3
4
5
2
Lead upto 1 km
Lead upto 2 km
Lead upto 3 km
Lead upto 4 km
Lead upto 5 km
for Every km beyond 5 km
upto 30 km
(Lead)
(Lead) charges
charges for
for trucks and
(Lead) charges
(Lead)
(Lead) charges for
trucks and
(Lead)
tippers per
for trucks and
charges charges
tippers for trucks and tippers for
cu.meter for
tippers for Earth
for per for trucks
Rubble/Size Cement/ Steel/ RCC
PCC slabs/
/ Sand /Gravel /
cu.meter per 1000
stones/ Cut poles/ AC & GI sheets/
Shahabad
Murrum/ Lime/
for water/ Nos. of
Packed
Stones/
slabs/ CC &
Surki/ per
1000 litres Bricks
materials/tonne
Coarse
Laterite blocks/
cu.meter
aggregate
Wood/ cum
per cu.meter
3
31.50
44.10
58.90
71.50
84.10
4
30.40
42.60
58.90
71.50
84.10
5
19.00
26.60
36.80
44.70
52.60
6
44.70
62.60
86.60
105.10
123.70
7
18.80
26.30
35.00
42.50
50.00
8
50.70
71.00
94.60
114.90
135.20
12.60
12.60
7.90
18.50
7.50
20.30
15.50
6.30
62.60
7
for Every km beyond 30 km
10.50
10.50
6.60
Note: The Lead Charges are inclusive of 14% Contractor Profit and Overhead charges
356
COM-LDLFT-2014-15
COM-LDLFT-3
C. LOADING AND UNLOADING CHARGES BY MANUAL MEANS (idle hire charges of trucks are not added)
Rubble/ size
stone/ cut
Earth / Sand
stone/
brick work
/Gravel
steel in
Coarse
Sl No.
Description of item
Murrum/ / Surki/
cement in Rs/tonne
Rs/1000
Rs./tonne
aggregate,Li
No
me in
Rs / cum
Rs/cum
1
2
3
4
5
6
7
1
Loading
16.00
32.00
52.80
63.30
44.00
2
Unloading
8.00
16.00
52.80
63.30
44.00
Note: The Lead Charges are inclusive of 14% Contractor Profit and Overhead charges
COM-LDLFT-4
D. LOADING AND UNLOADING CHARGES BY MANUAL MEANS (including idle hire charges of trucks )
Rubble/ size
Earth / Sand
stone/ cut
/Gravel
stone/
steel in
Sl No.
Description of item
Murrum/ / Surki/
Coarse
cement in Rs/tonne
Rs./tonne
aggregate,Li
Rs / cum
me in
Rs/cum
1
2
3
4
5
6
1
Loading
108.20
124.20
154.20
164.70
2
Unloading
38.60
62.10
154.20
164.70
Note: The Lead Charges are inclusive of 14% Contractor Profit and Overhead charges
COM-LDLFT-5
brick work
Rs/1000
No
7
211.30
211.30
E. LOADING AND UNLOADING CHARGES BY MECHANICAL MEANS (including idle hire charges of trucks)
Rubble/ size
Earth / Sand
stone/ cut
/Gravel
stone/
Sl No.
Description of item
Murrum/ / Surki/
Coarse
aggregate,Li
Rs / cum
me in
Rs/cum
1
2
3
4
1
Loading
52.50
105.00
2
Unloading
15.90
15.90
Note: The Lead Charges are inclusive of 14% Contractor Profit and Overhead charges
F. LIFT CHARGES FOR MATERIALS BY HEAD LOAD
COM-LDLFT-6
Sl No.
1
1
2
Earth / Sand
/Gravel
Murrum/ Lime/
Surki/
Total lift
( Total lift includes initial lift Size stone / Cut
stone
)
Rubble / Coarse
aggregate
Rs / cum
2
Total lift upto 3 m (covered
by item rate)
For Every 1.00 Lift beyond
initial lift of 3 meters
Cement /
Reinforcement steel
Str steel
Rs / tonne
PCC slab/
Shahbad
slab / CC
block/ BS
slab / Laterite
/ Wood
Rs / cum
Initial lift
5.60
Initial lift
4.10
Initial lift
7.50
DETAILED DATA
LEAD / LIFT / LOADING & UNLOADING CHARGES - DATA RATES
Note: The Lead Charges are inclusive of 14% Contractor Profit and Overhead charges
357
COM-LDLFT-2014-15
COM-DTL-LDLFT-1
Description
Mazdoor
Unit
Day
Quantity
1
Total Rs:
cum
cum
Description
Mazdoor
Unit
Day
Quantity
2
Total Rs:
cum
cum
25
60
m
m / minute
1
480
0.015
7
min
7
Rate
in Rs.
295
cum
cum
cum
Amount in Rs.
295
295
41.3
336.3
48.00
Rs:
Rs:
m
7
Rate
in Rs.
295
cum
Amount in Rs.
590
590
82.6
672.6
96.10
Rs:
Rs:
25
30
m
m / minute
2
240
50
12
min
kg
tonne
12
Rate in Rs.
tonne
Amount in Rs.
295
295
295
41.3
336.3
28.00
Rs:
Rs:
m
12
Rate in Rs.
tonne
Amount in Rs.
295
590
590
82.6
672.6
Rs:
56.10
CATEGORY : PCC slab / Shahabad stone slab / CC block / Laterite stone / BS slab / Wood
Lead: Upto 50 m :
This is initial lead and cost is covered under item basic rate.
Lead: Upto 100 m :
Average distance to be covered beyond initial lead of 50 m
Average speed of conveyance by head load
Round trip cycle time for 25 m considering 50 min/ hr working
( 2 x 25 x 60 / 50 / 40 )
25
40
m
m / minute
1.5
min
358
COM-LDLFT-2014-15
No. of trips per day for lead upto 100 m ( 8 x 60 / 1.5 )
Quantity of material by head load per load
Quantity of material by head load per day ( 320 x 0.017 ) say
Deploy one mazdoor for every 50 m additional lead beyond initial lead.
Unit:
Sl No.
Description
Unit
Quantity
1
Mazdoor
Day
1
Total Rs:
Contractor's profit and
overhead charges
14%
cum
Total for materials under this Category 5.5
Rate per
cum
Lead: Upto 150 m :
Average distance to be covered beyond initial of 50 m :
Deploy two mazdoors for conveyance beyond initial lead.
Sl No.
1
Description
Mazdoor
Unit
Day
COM-DTL-LDLFT-2
Unit:
Quantity
2
Total Rs:
cum
cum
320
0.017
5.5
5.5
Rate in Rs.
295
cum
cum
cum
Amount in Rs.
295
295
Rs:
Rs:
41.3
336.3
61.10
50
5.5
Rate in Rs.
295
cum
Amount in Rs.
590
590
Rs:
Rs:
82.6
672.6
122.30
B.( Lead) Conveyance charges for machinery per kilometer for transporting materials by tippers and trucks
excluding loading, unloading and idle hire charges of machinery.
CATEGORY : Earth / Sand / Gravel / Murrum / Lime / Surki /
For total lead upto 1 km
Sl No.
Description
1
Tipper hire charges
Fuel charges
2
Crew charges
Contractor's profit and
overhead charges
Total for
Rate per cum
Unit
Hour
Hour
Hour
14%
5
14%
5
Description
Tipper hire charges
Fuel charges
Crew charges
Unit
Hour
Hour
Hour
14%
5
Description
Tipper hire charges
Fuel charges
Crew charges
Unit
Hour
Hour
Hour
14%
5
Description
Tipper hire charges
Fuel charges
Crew charges
Unit
Hour
Hour
Hour
Unit:
Quantity
0.15
0.15
0.15
Total Rs:
5
Rate in Rs.
446.70
322.20
153.10
cum
Rs:
Unit:
Quantity
0.21
0.21
0.21
Total Rs:
5
Rate in Rs.
446.70
322.20
153.10
cum
Rs:
Unit:
Quantity
0.28
0.28
0.28
Total Rs:
Rate in Rs.
446.70
322.20
153.10
cum
Rs:
Unit:
5
Rate
in Rs.
446.70
322.20
153.10
Quantity
0.34
0.34
0.34
Total Rs:
cum
Rs:
Unit:
5
Rate
in Rs.
446.70
322.20
153.10
Quantity
0.4
0.4
0.4
Total Rs:
cum
Amount in Rs.
67.01
48.33
22.97
138.31
19.36
157.67
31.50
cum
Amount in Rs.
93.81
67.66
32.15
193.62
27.11
220.73
44.10
cum
Amount
in Rs.
125.08
90.22
42.87
258.17
36.14
294.31
58.90
cum
Amount
in Rs.
151.88
109.55
52.05
313.48
43.89
357.37
71.50
cum
Amount
in Rs.
178.68
128.88
61.24
368.80
359
COM-LDLFT-2014-15
Contractor's profit and
overhead charges
Total for
Rate per cum
14%
5
cum
Rs:
Unit:
Sl No.
1
Quantity
0.06
0.06
0.06
Total Rs:
5
Rate
in Rs.
446.70
322.20
153.10
Description
Tipper hire charges
Fuel charges
Crew charges
Unit
Hour
Hour
Hour
14%
5
Description
Tipper hire charges
Fuel charges
Crew charges
Unit
Hour
Hour
Hour
14%
5
cum
Rs:
Unit:
5
Rate
in Rs.
446.70
322.20
153.10
Quantity
0.05
0.05
0.05
Total Rs:
cum
Rs:
51.63
420.43
84.10
cum
Amount
in Rs.
26.80
19.33
9.19
55.32
7.74
63.06
12.60
cum
Amount
in Rs.
22.34
16.11
7.66
46.11
6.46
52.57
10.50
Unit:
Description
Truck hire charges
Fuel charges
Crew charges
Unit
Hour
Hour
Hour
14%
5
Description
Truck hire charges
Fuel charges
Crew charges
Unit
Hour
Hour
Hour
14%
5
Description
Tipper hire charges
Fuel charges
Crew charges
Unit
Hour
Hour
Hour
14%
5
Description
Tipper hire charges
Fuel charges
Crew charges
Unit
Hour
Hour
Hour
14%
5
Description
Tipper hire charges
Fuel charges
Crew charges
Unit
Hour
Hour
Hour
Quantity
0.15
0.15
0.15
Total Rs:
5
Rate
in Rs.
414.10
322.20
153.10
cum
Rs:
Unit:
5
Rate
in Rs.
414.10
322.20
153.10
Quantity
0.21
0.21
0.21
Total Rs:
cum
Rs:
Unit:
5
Rate
in Rs.
446.70
322.20
153.10
Quantity
0.28
0.28
0.28
Total Rs:
cum
Rs:
Unit:
5
Rate
in Rs.
446.70
322.20
153.10
Quantity
0.34
0.34
0.34
Total Rs:
cum
Amount
in Rs.
62.12
48.33
22.97
133.42
18.68
152.10
30.40
cum
Amount
in Rs.
86.96
67.66
32.15
186.77
26.15
212.92
42.60
cum
Amount
in Rs.
125.08
90.22
42.87
258.17
36.14
294.31
58.90
cum
Amount
in Rs.
151.88
109.55
52.05
313.48
cum
Rs:
43.89
357.37
71.50
Unit:
5
Rate
in Rs.
446.70
322.20
153.10
cum
Amount
in Rs.
178.68
128.88
61.24
Quantity
0.4
0.4
0.4
360
COM-LDLFT-2014-15
Total Rs:
0.00
368.80
cum
Rs:
51.63
420.43
84.10
Unit:
Sl No.
1
Quantity
0.06
0.06
0.06
Total Rs:
5
Rate
in Rs.
446.70
322.20
153.10
14%
5
Description
Tipper hire charges
Fuel charges
Crew charges
Unit
Hour
Hour
Hour
14%
5
Description
Tipper hire charges
Fuel charges
Crew charges
Unit
Hour
Hour
Hour
14%
5
cum
Rs:
Unit:
5
Rate
in Rs.
446.70
322.20
153.10
Quantity
0.05
0.05
0.05
Total Rs:
cum
Rs:
cum
Amount
in Rs.
26.80
19.33
9.19
55.32
7.74
63.06
12.60
cum
Amount
in Rs.
22.34
16.11
7.66
46.11
6.46
52.57
10.50
CATEGORY : Cement/ Steel/ Pipes/ RCC poles/ AC & GI sheets/ Packed materials
For total lead upto 1 km
Sl No.
1
2
Unit:
Description
Truck hire charges
Fuel charges
Crew charges
Unit
Hour
Hour
Hour
14%
8
Description
Truck hire charges
Fuel charges
Crew charges
Unit
Hour
Hour
Hour
14%
8
Description
Tipper hire charges
Fuel charges
Crew charges
Unit
Hour
Hour
Hour
14%
8
Description
Tipper hire charges
Fuel charges
Crew charges
Unit
Hour
Hour
Hour
14%
8
Description
Tipper hire charges
Fuel charges
Unit
Hour
Hour
Quantity
0.15
0.15
0.15
Total Rs:
8
Rate
in Rs.
414.10
322.20
153.10
tonne
Rs:
Unit:
8
Rate
in Rs.
414.10
322.20
153.10
Quantity
0.21
0.21
0.21
Total Rs:
tonne
Rs:
Unit:
8
Rate
in Rs.
446.70
322.20
153.10
Quantity
0.28
0.28
0.28
Total Rs:
tonne
Rs:
Unit:
8
Rate
in Rs.
446.70
322.20
153.10
Quantity
0.34
0.34
0.34
Total Rs:
tonne
Amount
in Rs.
62.12
48.33
22.97
133.42
18.68
152.10
19.00
tonne
Amount
in Rs.
86.96
67.66
32.15
186.77
26.15
212.92
26.60
tonne
Amount
in Rs.
125.08
90.22
42.87
258.17
36.14
294.31
36.80
tonne
Amount
in Rs.
151.88
109.55
52.05
313.48
tonne
Rs:
43.89
357.37
44.70
Unit:
8
Rate
in Rs.
446.70
322.20
tonne
Amount
in Rs.
178.68
128.88
Quantity
0.4
0.4
361
COM-LDLFT-2014-15
2
Crew charges
Hour
14%
8
0.4
Total Rs:
153.10
tonne
Rs:
Unit:
Sl No.
1
Quantity
0.06
0.06
0.06
Total Rs:
8
Rate
in Rs.
446.70
322.20
153.10
Description
Tipper hire charges
Fuel charges
Crew charges
Unit
Hour
Hour
Hour
14%
8
Description
Tipper hire charges
Fuel charges
Crew charges
Unit
Hour
Hour
Hour
14%
8
tonne
Rs:
Unit:
8
Rate
in Rs.
446.70
322.20
153.10
Quantity
0.05
0.05
0.05
Total Rs:
tonne
Rs:
61.24
368.80
51.63
420.43
52.60
tonne
Amount
in Rs.
26.80
19.33
9.19
55.32
7.74
63.06
7.90
tonne
Amount
in Rs.
22.34
16.11
7.66
46.11
6.46
52.57
6.60
CATEGORY : PCC slabs/ Shahabad slabs/ BS slabs/ CC & Laterite blocks/ Wood
For total lead upto 1 km
Sl No.
1
2
Unit:
Description
Truck hire charges
Fuel charges
Crew charges
Unit
Hour
Hour
Hour
14%
3.4
Description
Truck hire charges
Fuel charges
Crew charges
Unit
Hour
Hour
Hour
14%
3.4
Description
Tipper hire charges
Fuel charges
Crew charges
Unit
Hour
Hour
Hour
14%
3.4
Description
Tipper hire charges
Fuel charges
Crew charges
Unit
Hour
Hour
Hour
14%
3.4
Description
Tipper hire charges
Unit
Hour
Quantity
0.15
0.15
0.15
Total Rs:
3.4
Rate
in Rs.
414.10
322.20
153.10
cum
Rs:
Unit:
3.4
Rate
in Rs.
414.10
322.20
153.10
Quantity
0.21
0.21
0.21
Total Rs:
cum
Rs:
Unit:
3.4
Rate
in Rs.
446.70
322.20
153.10
Quantity
0.28
0.28
0.28
Total Rs:
cum
Rs:
Unit:
3.4
Rate
in Rs.
446.70
322.20
153.10
Quantity
0.34
0.34
0.34
Total Rs:
cum
Amount
in Rs.
62.12
48.33
22.97
133.42
18.68
152.10
44.70
cum
Amount
in Rs.
86.96
67.66
32.15
186.77
26.15
212.92
62.60
cum
Amount
in Rs.
125.08
90.22
42.87
258.17
36.14
294.31
86.60
cum
Amount
in Rs.
151.88
109.55
52.05
313.48
cum
Rs:
43.89
357.37
105.10
Unit:
3.4
Rate
in Rs.
446.70
cum
Amount
in Rs.
178.68
Quantity
0.4
362
COM-LDLFT-2014-15
Fuel charges
Crew charges
Hour
Hour
14%
3.4
0.4
0.4
Total Rs:
322.20
153.10
cum
Rs:
Unit:
Sl No.
1
Quantity
0.06
0.06
0.06
Total Rs:
3.4
Rate
in Rs.
446.70
322.20
153.10
Description
Tipper hire charges
Fuel charges
Crew charges
Unit
Hour
Hour
Hour
14%
3.4
Description
Tipper hire charges
Fuel charges
Crew charges
Unit
Hour
Hour
Hour
14%
3.4
cum
Rs:
Unit:
3.4
Rate
in Rs.
446.70
322.20
153.10
Quantity
0.05
0.05
0.05
Total Rs:
cum
Rs:
Unit:
8000
Rate
in Rs.
402.50
322.20
153.10
128.88
61.24
368.80
51.63
420.43
123.70
cum
Amount
in Rs.
26.80
19.33
9.19
55.32
7.74
63.06
18.50
cum
Amount
in Rs.
22.34
16.11
7.66
46.11
6.46
52.57
15.50
CATEGORY : water
For total lead upto 1 km
Sl No.
1
2
Description
Water tanker hire charges
Fuel charges
Crew charges
Unit
Hour
Hour
Hour
14%
8000
Description
Water tanker hire charges
Fuel charges
Crew charges
Unit
Hour
Hour
Hour
14%
8000
Description
Water tanker hire charges
Fuel charges
Crew charges
Unit
Hour
Hour
Hour
14%
8000
Description
Water tanker hire charges
Fuel charges
Crew charges
Unit
Hour
Hour
Hour
14%
8000
Description
Unit
Quantity
0.15
0.15
0.15
Total Rs:
litres
Rs:
Unit:
8000
Rate
in Rs.
402.50
322.20
153.10
Quantity
0.21
0.21
0.21
Total Rs:
litres
Rs:
Unit:
8000
Rate
in Rs.
402.50
322.20
153.10
Quantity
0.28
0.28
0.28
Total Rs:
litres
Rs:
Unit:
8000
Rate
in Rs.
402.50
322.20
153.10
Quantity
0.34
0.34
0.34
Total Rs:
litres
Amount
in Rs.
60.38
48.33
22.97
131.68
18.44
150.12
18.80
litres
Amount
in Rs.
84.53
67.66
32.15
184.34
25.81
210.15
26.30
litres
Amount
in Rs.
112.70
90.22
42.87
245.79
34.41
280.20
35.00
litres
Amount
in Rs.
136.85
109.55
52.05
298.45
litres
Rs:
41.78
340.23
42.50
Unit:
8000
Rate
in Rs.
litres
Amount
in Rs.
Quantity
363
COM-LDLFT-2014-15
1
2
Hour
Hour
Hour
14%
8000
0.4
0.4
0.4
Total Rs:
402.50
322.20
153.10
litres
Rs:
Unit:
Sl No.
1
Quantity
0.06
0.06
0.06
Total Rs:
8000
Rate
in Rs.
402.50
322.20
153.10
Description
Water tanker hire charges
Fuel charges
Crew charges
Unit
Hour
Hour
Hour
14%
8000
Description
Water tanker hire charges
Fuel charges
Crew charges
Unit
Hour
Hour
Hour
14%
8000
litres
Rs:
Unit:
8000
Rate
in Rs.
402.50
322.20
153.10
Quantity
0.05
0.05
0.05
Total Rs:
litres
Rs:
Unit:
3000
Rate
in Rs.
414.10
322.20
153.10
161.00
128.88
61.24
351.12
49.16
400.28
50.00
litres
Amount
in Rs.
24.15
19.33
9.19
52.67
7.37
60.04
7.50
litres
Amount
in Rs.
20.13
16.11
7.66
43.90
6.15
50.05
6.30
Description
Truck 10 T charges
Fuel charges
Crew charges
Unit
Hour
Hour
Hour
14%
3000
Description
Truck 10 T charges
Fuel charges
Crew charges
Unit
Hour
Hour
Hour
14%
3000
Description
Truck 10 T charges
Fuel charges
Crew charges
Unit
Hour
Hour
Hour
14%
3000
Description
Truck 10 T charges
Fuel charges
Crew charges
Unit
Hour
Hour
Hour
14%
3000
Quantity
0.15
0.15
0.15
Total Rs:
bricks
Rs:
Unit:
3000
Rate
in Rs.
414.10
322.20
153.10
Quantity
0.21
0.21
0.21
Total Rs:
bricks
Rs:
Unit:
3000
Rate
in Rs.
414.10
322.20
153.10
Quantity
0.28
0.28
0.28
Total Rs:
bricks
Rs:
Unit:
3000
Rate
in Rs.
414.10
322.20
153.10
Quantity
0.34
0.34
0.34
Total Rs:
bricks
Amount
in Rs.
62.12
48.33
22.97
133.42
18.68
152.10
50.70
bricks
Amount
in Rs.
86.96
67.66
32.15
186.77
26.15
212.92
71.00
bricks
Amount
in Rs.
115.95
90.22
42.87
249.04
34.87
283.91
94.60
bricks
Amount
in Rs.
140.79
109.55
52.05
302.39
bricks
Rs:
42.33
344.72
114.90
Unit:
3000
bricks
364
COM-LDLFT-2014-15
Sl No.
1
2
Description
Truck 10 T charges
Fuel charges
Crew charges
Unit
Hour
Hour
Hour
14%
3000
bricks
Rs:
Unit:
Sl No.
1
Quantity
0.06
0.06
0.06
Total Rs:
3000
Rate
in Rs.
414.10
322.20
153.10
Description
Truck 10 T charges
Fuel charges
Crew charges
Unit
Hour
Hour
Hour
14%
3000
COM-DTL-LDLFT-3
Quantity
0.4
0.4
0.4
Total Rs:
Rate
in Rs.
414.10
322.20
153.10
Description
Truck 10 T charges
Fuel charges
Crew charges
Unit
Hour
Hour
Hour
14%
3000
bricks
Rs:
Unit:
3000
Rate
in Rs.
414.10
322.20
153.10
Quantity
0.05
0.05
0.05
Total Rs:
bricks
Amount
in Rs.
165.64
128.88
61.24
355.76
49.81
405.57
135.20
bricks
Amount
in Rs.
24.85
19.33
9.19
53.37
7.47
60.84
20.30
bricks
Amount
in Rs.
20.71
16.11
7.66
44.48
6.23
50.71
16.90
Rs:
C. LOADING AND UNLOADING CHARGES BY MANUAL MEANS (idle hire charges of trucks are not added)
MORD -data
1
Loading of Lime, Aggregate, Stone Boulder,
a) Loading Brick Aggregate, Kankar, Building Rubbish,
Unit
Quantity
Rate Rs.
Amount Rs.
Building Rubbish, Crushed Slag, Stone for Masonry
Work by manual means including a lead upto 30 m
Unit = cum
Taking output = 5.5 cum
Labour
Head Mazdoor
day
0.02
345.00
6.90
Mazdoor
day
0.5
295
147.50
Total in Rs.
154.40
contractor's profit and
overhead charges
14%
21.62
Rate per cum =
Rs.
32.00
b) Unloading50% of the loading charges 16.00
Quantity
Rate Rs.
345.00
295
Amount
Rs.
3.45
73.75
77.20
10.81
16.00
Rs.
Unit
day
day
Quantity
0.01
0.25
Rate Rs.
345.00
295
Amount Rs.
3.45
73.75
77.20
10.81
44.00
Rs.
44.00
Unit
Quantity
Rate Rs.
Amount Rs.
365
COM-LDLFT-2014-15
a) Loading including a lead upto 30 m
Unit = 1 t
Taking output = 10 t
a) Labour
Head mazdoor
Mazdoor
Cost for 10 t =
contractor's profit and
overhead charges
14%
Rate per 1 tonne =
day
day
0.06
1.5
345.00
295
20.70
442.50
463.20
64.85
52.80
Rs.
COM-DTL-LDLFT-4
0.07
1.8
Rate Rs.
345.00
295
Amount Rs.
24.15
531.00
555.15
77.72
63.30
Rs.
63.30
6
Unit
Loading of Bricks - 1000 Nos (Regular sizes a) Loading 225x140x70 mm) by manual means including
Unit = 1000 Nos.
Taking output = 2000 Nos.
a) Labour
head Mazdoor
day
Mazdoor
day
Cost for 2000 Nos. =
contractor's profit and
overhead charges
14%
Rate per 1000 Nos. =
100% of loading charges
b) UnloadingI.e., Rs.
Quantity
Quantity
0.01
0.25
Rate Rs.
345.00
295.00
Amount Rs.
3.45
73.75
77.20
10.81
44.00
Rs.
44.00
D. LOADING AND UNLOADING CHARGES BY MANUAL MEANS (including idle hire charges of trucks )
1
Loading of Lime, Aggregate, Stone Boulder,
a) Loading Brick Aggregate, Kankar, Building Rubbish,
Building Rubbish, Crushed Slag, Stone for Mas
Unit
Work by manual means including a lead upto 30 m
Unit = cum
Taking output = 5.5 cum
a) Labour
Head Mazdoor
day
Mazdoor
day
b) Machinery
Truck 10t
hour
Cost for 5.5 cum =
contractor's profit and
overhead charges
14%
Rate per cum =
b) Unloading50% of the loading charges i.e.,
Quantity
Rate Rs.
Amount Rs.
0.02
0.5
345.00
295
6.90
147.50
0.5
889.40
444.70
599.10
83.87
124.20
Rs.
62.1
2
Loading of Earth, Sand, Moorum, Manure, Flya
Unit
a) Loading by manual means including a lead upto 30 m
Unit = cum
Taking output = 5.5 cum
Labour
Head Mazdoor
day
Mazdoor
day
b) Machinery
Truck 10t
hour
Cost for 5.5 cum =
contractor's profit and
overhead charges
14%
Rate per cum =
b) UnloadingUnloading of Earth, Sand, Moorum, Manure, F
Unit
by manual means including a lead upto 30 m
Unit = cum
Taking output = 5.5 cum
a) Labour
Mate
day
Mazdoor(unskilled)
day
Quantity
Rate Rs.
Amount Rs.
0.01
0.25
345.00
295
3.45
73.75
0.5
889.40
444.70
521.90
73.07
108.20
Rs.
Quantity
0.005
0.125
Rate Rs.
345.00
295
Amount Rs.
1.73
36.88
366
COM-LDLFT-2014-15
b) Machinery
Truck 10t
Cost for 5.5 cum =
contractor's profit and
overhead charges
Rate per cum =
hour
0.166
889.40
14%
26.08
38.60
Rs.
Unit
Quantity
147.64
186.25
Rate Rs.
Total
day
day
0.01
0.25
345.00
295
3.45
73.75
hour
0.33
889.40
293.50
370.70
51.90
211.30
Rs.
Unit
Quantity
Rate Rs.
Total
day
day
0.06
1.5
345.00
295
20.70
442.50
hour
889.40
889.40
1352.60
189.36
154.20
Rs.
Quantity
Rate Rs.
Total
0.07
1.8
345.00
295
24.15
531.00
889.40
889.40
1444.55
202.24
164.70
Rs.
E. LOADING AND UNLOADING CHARGES BY MECHANICAL MEANS (including idle hire charges of trucks)
COM-DTL-LDLFT-5-A
1
Loading of Lime, Aggregate, Stone Boulder,
a) Loading Brick Aggregate, Kankar, Building Rubbish,
Crushed Slag, Stone for Masonry work by
mechanical means including a lead upto 30 m
Unit
Placing tipper at loading point, loading with front end
loader excluding time for haulage and return trip.
Unit = cum
Taking output = 5.5 cum
Time required for
i) Positioning of tipper at loading point
Min
ii) Loading by front end loader 1 cum bucket caMin
@ 45 / 25 cum per hour
iii) Manoevouring, reversing, dumping and turn Min
for return
iv) Waiting time, unforeseen contingencies, etcMin
Total
Min
a) Machinery
Tipper 10 t capacity
hour
Front end-loader 1 cum bucket capacity @ 45 chour
per hour
Cost for 5.5 cum =
b) contractor's profit and
overhead charges
14%
Rate per cum = (a+b)/5.5
Quantity
Rate Rs.
Total
1
7.33
2
10.33
0.17
0.12
922.00
2848.50
158.74
347.99
506.73
Rs.
70.94
105.00
367
COM-LDLFT-2014-15
COM-DTL-LDLFT-5-B
2
Loading of Earth, sand, Moorum, Manure, Flyash,
a) Loading by mechanical means including a lead upto 30 m
Placing tipper at loading point, loading with front
end loader excluding time for haulage and retu
Unit
Placing tipper at loading point, loading with front
end loader excluding time for haulage and return trip.
Unit = cum
Taking output = 5.5 cum
Time required for
i) Positioning of tipper at loading point
Min
ii) Loading by front end loader 1 cum bucket caMin
@ 45 / 25 cum per hour
iii) Waiting time, unforeseen contingencies, etcMin
Total
Min
a) Machinery
Tipper 10 t capacity
hour
Front end-loader 1 cum bucket capacity @ 45 chour
per hour
Cost for 5.5 cum =
b) contractor's profit and
overhead charges
14%
Rate per cum = (a+b)/5.5
b) UnloadingUnloading of Earth, sand, Moorum, Manure, Flyash,
lime, Aggregate, Stone boulder, Brick aggregate,
Kankar, Building rubbish, Manure, Crushed Sla
Unit
Flyash, Stone for Masonry work by mechanical
means including a lead upto 30 m
Placing tipper at unloading point, excluding time
for haulage and return trip.
Taking output = 5.5 cum
Time required for
i) Positioning of tipper at loading point
Min
ii) Loading by front end loader 1 cum bucket caMin
@ 45 / 25 cum per hour
iii) Waiting time, unforeseen contingencies, etcMin
Total
a) Machinery
Tipper 10 t capacity
hour
Cost for 5.5 cum =
b) contractor's profit and
overhead charges
14%
Rate per cum = (a+b)/5.5
COM-DTL-LDLFT-6
Quantity
Rate Rs.
Total
1
3.3
2
6.3
0.105
0.055
922.00 96.81
2848.50 156.67
253.48
35.49
52.50
Rs.
Quantity
Rate Rs.
Total
1
2
2
5
0.08
922.00 76.83
76.83
10.76
15.90
Description
2
Mazdoor
contractor's profit and
overhead charges
Unit
3
Day
Quantity
4
1.00
60 m/minute
0.12
4000
0.015
60
min
cum
cum
60
Rate
in Rs.
5
295.00
14%
Total Rs: for 60
cum
cum
Amount
in Rs.
6
295.00
41.30
336.30
5.60
Lift : ADDITIONAL LIFT CHARGES FOR each 1 METER LIFT BEYOND 3 M INITIAL LIFT
For additional lift of 1m beyond initial lift of 3 m
one meter lift is taken equivalent to 6 meters lead
average speed of conveyance by head load
Round trip cycle time for 1.00 m considering 50 min/ hr working
25 m/minute
368
COM-LDLFT-2014-15
1 x6x 60 / 50 / 25 )
0.29
min
No. of trips per day foradditional lift 1.0 m above 3 m ( 8 x 60 / 0.29)
1655
Quantity of material by head load
50
kgs
Quantity of material by head load per day ( 1655x50x 0.015 )
83
tons
Deploy 1 mazdoor for every additional lift of 1.5 m beyond initial lift.or2/3 mazdoor
Lift : Upto 3.00 m for materials under this Category
Unit:
83
TONS
Rate
Amount
Sl No.
Description
Unit
Quantity
in Rs.
in Rs.
1
2
3
4
5
6
Mazdoor
Day
1.00
295.00
295.00
contractor's profit and
overhead charges
14%
41.30
Total Rs: for 83
Tonnes
336.30
Rate per tonne
4.10
FOR CATEGORY : PCC slab / Shahabad stone slab / CC block / Laterite stone / BS slab / Wood
Lift : Upto 3.00 m
This is the initial lift and forms integral part of the activities in the basic rate of work item.
Lift charges are admissible only lifting effort beyond initial lift specified in the work item.
Lift : ADDITIONAL LIFT CHARGES FOR EACH 1 METER LIFT BEYOND 3 M INITIAL LIFT
For additional lift of 1m beyond initial lift of 3 m
one meter lift is taken equivalent to 6 meters lead
average speed of conveyance by head load
40 m/minute
Round trip cycle time for 1.00 m considering 50 min/ hr working
1 x6x 60 / 50 / 40 )
0.18
No. of trips per day for lift 1.0 m ( 8 x 60 / 0.18 )
2667
Quantity of material by head load
0.017
Quantity of material by head load per day ( 1667x 0.018 )
45
Deploy 1 mazdoor for every additional lift of 1.5 m beyond initial lift.or2/3 mazdoor
Lift : Upto 3.00 m for materials under Category
Sl No.
1
Description
2
Mazdoor
contractor's profit and
overhead charges
Unit:
Unit
3
Day
14%
Total Rs: for 45
cum
Quantity
4
1.00
45
Rate
in Rs.
5
295.00
min
cum
cum
cum
Amount
in Rs.
6
295.00
41.30
336.30
7.50
369
1
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
Description of machinery
2
Agitator car / Transit mixer 2 cum
Air compressor 5 cmm ( electric )
Air compressor 7 cmm ( diesel )
Air compressor 7 cmm ( electric )
Air compressor 8.5 cmm ( diesel
Air compressor 8.5 cmm ( electric)
Air compressor 15 cmm ( electric)
Angle Dozer 90 hp
Batching plant 0.5 cum( 6 cum/hr)
Batching plant 2 x 1.00 cum(15 cum/hr)
Batching plant 2 x 1.50 cum(50 cum/hr)
Bending machine 3000 x 12 mm
Clamp shell and hoisting ropes
Concrete bucket 1.5 cum
Concrete hand mixer 45 / 30 ltr
Concrete mixer 300 / 200 ( diesel)
Concrete mixer 300 / 200 ltr ( electric)
Concrete mixer 600 / 400 ( diesel)
Concrete mixer 600 / 400 ltr ( electric
Concrete paver 100 sqm / hr
Convey mucker
Core drilling machine
Diesel generating set 30 KVA
Diesel generating set 50 KVA
Diesel Loco 45 hp
Dewatering pump 5 hp ( diesel )
Dewatering pump 5 hp ( electric )
Dewatering pump 10 hp ( diesel )
Dewatering pump 10 hp ( electric
Dewatering pump 20 hp ( diesel )
Dewatering pump 20 hp ( electric
Drifter
Drilling jumbo
Dumper 4.5 cum
Geophysical Electric resistivity meter
Grouting pump
Guniting / sand blast equipment
Ice plant & accessories 30 t / day
Jack hammer
Needle vibrator 40 mm ( petrol )
Needle vibrator 40 mm ( electric )
Needle vibrator 60 mm ( petrol )
Needle vibrator 60 mm ( electric )
Planing machine 4 m stroke
Plate shearing machine upto 12 mm
Pneumatic placer 0.5 cum
Pneumatic tamper
Pug cutting machine
Pusher leg
Road roller diesel 10 t
Unit
3
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
5
937.80
256.80
767.30
342.40
959.10
428.00
951.20
656.00
114.10
342.40
418.50
114.10
0.00
0.00
0.00
85.30
38.00
170.50
76.10
0.00
264.80
255.80
682.00
1023.00
575.40
85.30
38.00
170.50
76.10
341.00
152.20
0.00
46.00
429.70
0.00
38.00
0.00
1084.30
0.00
21.50
7.60
32.20
11.40
114.10
152.20
0.00
0.00
3.80
0.00
767.30
6
244.90
142.40
182.20
142.40
182.20
142.40
151.80
204.10
293.80
293.80
293.80
113.90
0.00
0.00
0.00
189.80
189.80
189.80
189.80
364.40
151.80
244.90
113.90
113.90
142.40
96.10
72.10
96.10
72.10
96.10
72.10
306.20
151.80
195.90
0.00
227.80
189.80
113.90
284.70
136.60
136.60
136.60
136.60
182.20
122.50
75.10
227.80
0.00
0.00
182.20
Total in Rs
7
1941.10
507.50
1190.80
616.70
1416.90
741.20
1241.80
2575.60
522.50
1041.60
1230.40
270.60
5.40
15.80
5.50
328.60
279.50
453.00
356.90
720.90
1239.40
819.70
861.70
1222.00
1099.40
191.60
113.10
281.80
154.90
485.40
236.60
628.90
566.20
1206.30
99.00
290.70
299.90
1368.40
304.50
165.70
152.20
177.00
157.70
414.10
316.60
246.20
248.50
10.20
12.70
1146.70
370
Description of machinery
Unit
1
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
2
Shovel 0.50 cum 75 hp
Shovel 0.85 cum 110 hp
Stationery derric crane
Tipper 5 cum
Tipping tub 1.5 cum
Tower crane 5 tonne
Transformer 250 KVA
Truck 10 t
Truck mounted derric crane 5 t
Upright drilling machine/Grinder
Ventilation fan 20 hp
Vibratory pad foot roller 8 t
Wagon drill
Water tanker 8000 ltr
Welding set
Winch 35 hp ( electric )
Tractor with 2T roller
3
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
Hour
4
1003.10
1706.60
86.10
446.70
64.20
867.10
5041.00
414.10
519.70
22.50
11.50
1342.20
188.50
402.50
16.00
129.40
5
511.50
937.80
0.00
322.20
0.00
197.80
0.00
322.20
322.20
38.00
152.20
1108.30
0.00
322.20
91.30
186.40
6
204.10
204.10
0.00
153.10
0.00
163.30
0.00
153.10
153.10
171.60
24.90
227.80
244.90
153.10
0.00
227.80
Total in Rs
7
1718.70
2848.50
86.10
922.00
64.20
1228.20
5041.00
889.40
995.00
232.10
188.60
2678.30
433.40
877.80
107.30
543.60
345.00
Hour
Hour
3096.80
2278.10
118.80
75.00
454.30
454.30
3669.90
2807.40
71
Hour
121.40
121.40
371