Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Abstract
A public-private partnership (PPP) is a government undertaking that is funded by an assistance of
two organizations, which usually entail a cathedral contract between a government authority and
a private company, in which the private company indulge a public serviceability of project and
also susceptive for financial, technical and operational risk involved with the project. Publicprivate partnership models are globally accepted and used in more than 90 countries. This paper
scrutinizes the structure, reliability, risks and uncertainty associated with PPP mega projects. The
work presents comprehensive contracting process and execution structure in implementing PPP
models in developing countries. This research is aimed to evaluate the current trends and
practices in PPP models.
Keywords: Contracting, Execution, Infrastructure, Megaprojects, PPP.
1. Introduction
Colossal projects are defined as million dollar mega infrastructure projects, normally deputized
by state or central government and handed over by private firm; and characterized as ambiguous,
convoluted, politically-tense projects involving large number of groups [1]. Prevalence of many
colossal projects engulfs on costs, decline behind schedule and abort to deliver on time, which is
in divergence to the scope of the project. One of the major causes of such overruns is a lack of
plausibility in fundamental cost estimates. The duration and cost of delays are undervalued;
exigencies are set too low [1, 2]. Projects can be chaotic in terms of cost and time due to exacting
design or composite social system [2, 3].
Robustness of a project contributes to the lifespan and effectiveness of a technical design and its
implementation. The more efficient a project is (in terms of feasibility and monetary gains); less
will be the chances of cost and time overruns. As robustness is often accompanied by a selfassured process of design, so, project managers should always follow the standards of robust
engineering [2].
Since 1990s, the PPP advent has been massively utilized in U.K and U.S.A [4]. Moreover,
private companies have been actively muddled in facilities development, including design,
finance, execution, insurance, operation and maintenance of a public sector utility. On the other
hand, in China Republic, international firms rather than domestic firms have been involved in
PPP projects [3].
Also, in Maharashtra (India), more than 50% of large-scale infrastructure projects are executed
on the PPP model. In the early 2000s, other states such, Uttar Pradesh, Karnataka, Gujarat, and
Tamil Nadu also endorsed this model.
Meticulous PPP is characterized by a model as shown in the shown in the fig. 1 below.
Ownership
Procurement
Contract
Contractual
PPP
Concession
Contract
PPP
Institutional
PPP
Joint Venture
Public Works
Contract
Public Service
Contract
Work
Concession
Contract
Service
Concession
Contract
Partnership
Acquisition
Contract
License
Contract
2. Research Methodology
An online survey was designed as a part of qualitative analysis for collecting information
regarding PPPs as a construction practice. The survey was then conveyed to different companies
and institutions in the country via Gmail and LinkedIn.
The survey was designed as a short survey as long surveys dont get quick responses, thus it was
divided into 10 questions in order to generate data regarding the awareness and knowledge of
PPP in construction industry.
The data was collected from professionals, after composing the data, results are shown.
Evaluations of the results were made, and conclusions and recommendations are presented.
Contractin
g Process
in PPP
Requests
for Bids
(Notice
Inviting
Tender)
Bid
Preparation
For Open
and
Selective
Bidding
Project
Outlining and
Research
Submission of
Technical and
Financial Bid
Tender
Analysis
Verdict Stage:
Letter of
Intent and
Work Order
Execution of
Mega Projects
Complete
Public
Participation
Conventional
Government
Contracting
Includes
Design, Build
and Maintain
Public-Private
Partnership
1. Service Contract
Example
Rebuild-Operate-Transfer (ROT)
2. Management Contract
Example:
Rebuild-Operate-Manage (ROM)
3. Lease Contract
Example:
Lease-Build-Operate (LBO)
4. Joint Investment
Example:
Build-Operate-Transfer (BOT)
Build-Transfer-Operate (BTO)
Build-Transfer (BT)
Build-Own-Operate-Tranfer (BOOT)
Design-Build-Finance-Operate
(DBFO)
Design-Build-Operate-Transfer
(DBOT)
Design-Construct-Manage-Finance
(DCMF)
Complete
Private
Participation
Private Bodies
Service
Accouterment
(Privatization)
5. Survey Results
The following section represents the survey questionnaire and their responses collected from
industry.
An online survey was designed through Survey Monkey, survey consists of 10 questions,
which were conveyed to 20 construction professionals and results are analyzed in the form of pie
charts.
Table 1: Background of construction professionals:
Background
No. of
Age
Participants
(Years)
Company/Institution
% of Total
Civil Engineers
25-30
30%
Contractors
30-35
20%
Construction
Managers
Academic
Researchers
35-40
22-28
20%
30%
Analysis
Question 1.1 was designed to check out that: Is there a strong need of PPP models for Indian
construction industry?
Responses are shown in the Fig. (20 Responses)
Majority of the people said yes (69.23%), while 23.08% people were not sure.
23%
Yes
No
8%
Can't Say
69%
Question 1.2 was designed to define the contracting process in PPP models.
Responses are shown in the Fig. (20 Responses)
Majority of the people (38.46%) said all statements contribute to the definition, while no one
said that contracting process in PPP is meant to minimize risk.
Contracting Process in PPP is defines as:
Precisely Managing Contract Formulation
Execution and Aanalysis of Contract for Improving Financial and Operational Procedure
31%
38%
Minimizing Risk
31%
Question 1.3 was designed as Contracting process in PPP projects does not involve which of
the following?
Responses are shown in the Fig. (20 Responses)
While planning and execution of project is not a part of contracting process, but only 25% people
voted for that.
25%
17%
25%
25%
8%
Question 1.4 was designed as Do key performance indicators actually influence the future
performance of projects?
Responses are shown in the Fig. (20 Responses)
Majority of the people said yes (53.85%), while 30.77% people were not sure about that.
31%
54%
Yes
No
Can't Say
15%
Question 1.5 was designed as Which of these is not a key performance indicator of PPP
projects?
Responses are shown in the Fig. (19 Responses, 1 Skipped)
Actually, financial status of employees has nothing to do with KPIs of any PPP project, but
shockingly only 15.38% people voted for that.
15%
23%
23%
8%
31%
Type of Project
Legal Status of Project
Cost-Benefit Ratio
Safety and Heath
Management
Financial Status of
Employees
Question 1.6 was designed as Do capital market plays a role in developing PPP projects?
Responses are shown in the Fig. (20 Responses)
While in this case, people were in two minds, thats why almost half said yes while others said
no.
1%
45%
54%
Yes
No
Can't Say
Question 1.7 was For what PPPs hold strong credibility on capital markets?
Responses are shown in the Fig. (20 Responses)
PPP projects hold strong credence on all below stated aspects and majority of people (46.15%)
voted for that.
15%
46%
15%
Reduction of Risk
Arbitration
Credit Intensification
Credit Valuation
All of the Above
8%
15%
23%
True
FALSE
77%
Question 1.9 was Execution of mega infrastructure projects should be done by?
Responses are shown in the Fig. (20 Responses)
This question got mixed responses, while majority of people said that both public and private
involvement should be there in mega projects.
23%
46%
8%
Complete Public
Participation
Complete Private
Participation
Public-Private Partnership
All of the Above
23%
Question 1.10 was Which of the following is not a part of PPP model?
Responses are shown in the Fig. (20 Responses)
In normal situations, marketing contract is not a part of PPP model, and 23.08% voted for this,
while, majority of people (30.77%) said that management contract is not a part of PPP models.
8%
23%
31%
15%
Service Contract
Lease Contract
Management Contract
Joint Investment Contract
Marketing Contract
23%
Globally, PPPs are being implemented across an immense variety of commercial and
communal infrastructure projects.
PPPs are attaining a number of compelling upgrades in major project acquisition and
enhanced public service delivery.
In antiphon to demanding need of urban development, many endeavors have been made
by both the public and private sectors to promote PPPs from the conventional format of
construction [4].
PPPs are more dependent on short term finances than long term finances.
Type of project, size, location, budget, safety is all the key performance indicators (KPIs)
for PPP projects.
The PPP model is achieving value for money, cutting down procurement costs and
conveying complicated projects without any delay and within cost than the classical
methods.
PPPs are improving the discipline of contracting methods with convincing benefits for
bidders [7].
PPPs hold strong reliability on capital markets for credit rise and valuation.
The journey to success has been long and is still long, because governments and their policy
counselor in some way have been reluctant to learn from mistakes.
Following are the recommended aspects:
Only few bidders are involved in bidding process of PPP projects.
Private funding is quite wide-ranging in PPPs.
There is susceptibility of investors to political and legal risk.
High agreement costs.
Long term obligation of the lease payment.
Acknowledgements
The author would like to thank Prof. Sakshi Gupta for applying her educational expertise in
refining this manuscript.
References
[1] A.V Marrewijk, S.R Clegg, T.S Pitsis and M. Veenswijk Managing public-private
megaprojects: Paradoxes, complexity and project design, International Journal of Project
Management, vol. 26, pp. 591-600, August 2008.
[2] Hugo Priemus, Bent Flyvbjerg and Bert van Wee, Decision-Making on Mega-Projects, 1 st ed.
Cheltenham, Edward Elgar, 2008.
[3] Li Yaning Tang, Qiping Shen and Eddie W.L. Cheng A review on studies on public private
partnership projects in the construction industry, International Journal of Project
Management, vol. 28, pp. 683-694, October 2010.
[4] Graeme A. Hodge and Carsten Greve PPPs: The passage of time permits a sober reflection,
Economic Affairs, vol. 29, pp. 33-39, March 2009.
[5] Martin de Jong, Mu Rui, Dominic Stead, Ma Yongchi and Xi Bao Introducing publicprivate partnerships for metropolitan subways in china: what is the evidence? Journal of
Transport Geography, vol. 18, pp. 301-313, March 2010.
[6] Matti Siemiatycki Implications of public-private partnerships on the development of urban
public transit infrastructure: The case of Vancouver, Canada, Journal of Planning Education
and research, vol. 26, pp. 137-151, December 2006.
[7] Steven De Schepper, Michael Dooms and Elvira Haezendonck Stakeholders dynamics and
responsibilities in public-private partnerships: A mixed experience, International Journal of
Project Management, vol. 32, pp. 1210-1222, October 2014.
[8] F. Blanc-Brude, Hugh Goldsmith and Timo Valila A comparison of construction contract
prices for traditionally procures roads and public-private partnerships, Review of Industrial
Organization, vol. 35, pp. 19-40, October 2009.
[9] Joe Sanderson Risk, uncertainty and governance in megaprojects: A critical discussion of
alternative explanations, International Journal of Project Management, vol. 30, pp. 432-443,
April 2012.
[10]
Rui Mu, Martin de Jong and Joop Koppenjan The rise and fall of publicprivate partnerships in China: A path dependent approach, Journal of Transport Geography,
vol. 19, pp. 794-806, July 2011.