Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
(NMCAL)
Nayabazar, Khusibu, Kathmandu
A Report On
In- plant training on CTL PHARMACEUTICAL Pvt. Ltd.
In partial fulfillment of the requirement for the degree of
Bachelor in Pharmacy
Submitted by:
Arjun Ghimire
4thBatch
Submitted to:
CTL PHARMACEUTICAL Pvt. Ltd.
Bhaktapur
ACKNOWLEDGEMENT
We take this opportunity to express our profound gratitude and deep regards to our program chief Dr. Madhav
Prasad Baral, program Director Mr. Prajwal Jung Pandey, our respected program coordinator Ms. Savyata
Gautam and faculty members Mrs. Junu Khatri Silwal, Mr. Anil Sah for their exemplary guidance, constant
support and encouragement through entire B. Pharm program, to undergo an In-plant training.
I would like to express my first and foremost gratitude to chairman Mr. Rabi krishna shrestha,
General manager Mr. Dipendra pradhan for providing me with an oppurtunity to train at CTL. I take my
pride to complete my in-plant training at CTL pharmaceuticals pvt. ltd., one of the most reputed
pharmaceutical companies of Nepal. I would like to express my special gratitude to factory manager Mr.
Amir bade for his support and guidance. I would like to express my most cordial and humble thanks to QA
manager , Mr. Ravi Maharjan for his support, motivation and guidance throughout my in-plant training at
CTL. I would like to offer my sincere gratitude to Mrs. Archana Pradhan QC manager, Mr. Dipesh
Shrestha QA officer, production head Rajendra Khadka , Rukesh Machamasi and Abhishek Shrestha for
their kind co-operation, support, guidance and constant supervision as well as for providing necessary
information during my training even in their busy schedule.I am highly indebted to all supervisors, analyst,
all the pharmacists of respective departments for giving me attention and time.I would like to give my
heartiest thanks to all the industrial staffs of CTL for their hospitality and encouragement and making my
stay at CTL a memorable time.
Arjun Ghimire
ABSTRACT
The in-plant training is required for the partial fulfillment of degree of Bachelor in Pharmacy under
Institute of Medicine and consists of in-plant training for 3 weeks at Pharmaceutical industry. The training
program consists of brief training in the different departments of the pharmaceutical industry. In the course
of training at CTL, I was exposed to the departments of CTL namely Production, Quality Assurance,
Quality Control, Store, Primary and secondary packaging. During the training period, I gained practical
knowledge on handling of raw materials, manufacturing process, operation of equipment, packaging of
product, quality testing of raw materials, intermediate products, finished products, and assurance of quality
through monitoring, controlling, documentation and other activities performed for achievement of quality
products. Moreover, I have also been aware of importance of quality in manufacturing of medicines and its
documentation. This training helped me in applying my theoretical knowledge to practical approach and to
use my theoretical knowledge to choose the specific department of my interest for my career.
Thus, this training has been very productive for me in my aim to be a competent pharmacist and to uplift
my profession.
ACRONYMS
AHU
BMR
BPR
HEPA
HPLC
HVAC
GMP
IPQC
KF
Karls Fischer
MFR
NMT
NLT
PVC
Polyvinyl Chloride
PVDC
Polyvinyl Dichloride
QA
Quality Assurance
QC
Quality Control
RH
Relative Humidity
RM
Raw Material
RMG
RO
Reverse Osmosis
R&D
SOP
UV
Ultraviolet
GRN
TABLE OF CONTENT
IN PLANT BRIEFING
With the aim of developing ability to translate theory into practice, the curriculum of Bachelor of
Pharmacy places students for in plant training in pharmaceutical manufacturing units for the duration of 3
weeks at the end of fourth year.
Area covered and duration : CTL Pharmaceutical Pvt. Ltd.
S.
N
Date
Concerned
department
Quality control
14th
Marchrd
23 March
Production
24th
Marchth
25 March
Quality assurance
Specific objectives:
To be familiar with the manufacturing of the pharmaceutical products in the industry so as to
gain
practical knowledge and experience.
To get detailed information regarding receipt of material, storage, dispensing of raw and
packaging materials.
To be familiar with various equipments and instruments used for the manufacturing of the drugs
in pharmaceutical industries.
To get overall ideas regarding operation, maintenance, assemblence and standardization of
water treatment plant, HVAC and other utilities.
To have idea about the flow of men and materials during manufacturing.
To know the different process of Quality Control and In-process Control of raw materials &
finished products.
To develop confidence and gain professional tips to work as capable pharmacist in near future.
To get idea regarding the waste disposal system.
2. COMPANY PROFILE
2
CTL Pharmaceutical Pvt. Ltd. established in 1990 is founded on a deep sense of National pride and
conviction to make a contribution to our countrys self reliance in the field of pharmaceutical formulation
and to ensure health and happiness for all by manufacturing the range of medicines of the highest quality at
affordable price and reaching out even to marginalized people of Nepal. It was established in 1994 as
Kathmandu Medical Hall, later in 1995, it is transformed to BR pharmaceuticals. All the activities are
carried out in dedicated areas with controlled environment as per GMP. Salient features of CTL
Pharmaceutical is committed to implement and maintain GMP norms, Quality assurance , quality and
environment policy at every stage from procurement, manufacture, packaging, storage, sales and
distribution to waste management. It is dedicated to manufacture and market pharmaceutical formulation of
requisite standard to cater customer need enhance the customer satisfaction and ensure better health care by
assuring continual and dynamic improvements in quality of its products and services. CTL Pharmaceuticals
is committed to create excellent working environments by improving its environmental performance
through continual improvement in environmental conditions, prevention of pollution and optimum
utilization of energy and resources. CTL ensures the occupational health and safety of its workers by
conducting regular health check-up. CTL produces a products which includes quality non-sterile
products among tablets, capsules.
General Manager
Factory Manager
Quality Assurance Manager
QC Head
QA Officer
HR Department
Maintenance Officer
R&D Officer
Assistant QA Officer
Microbiologist
QC officer
Production Head
Assistant QC officer
Production Pharmacist
4. OPERATIONAL PROCEDURE
Vendor (Supplier)
De dusting
4
Store incharge
Dispensing
(As
per
cross check by production)
BMR
in
presence
of
store,
Manufacturing
Intermediate (IPQC)
Finished product
Analysis by QC
QC release
QA documentation and Review
Fail (Hold and needs recommendation
5. VARIOUS DEPARTMENTS
1. Store department (raw material and packaging material store)
QA
and
This department receives, records, stores and dispenses the raw materials and packaging
materials to the various departments.
1. Production department
Cephalosporin
Non-penicillin
Penicillin
2. Quality Control department
Instrument room
Controlled sample room
Stability chamber room
Microbiology laboratory
Room for analysis
Office room
3. Quality Assurance department
Material, processing and document control
Validation
Documentation
Method development
DISCUSSION ON VARIOUS DEPARTMENTS
5.1.
Store department:
Storage is the process of keeping or holding goods in a systematic way preserving its quality and store is
the place where goods are kept safely for future use. Store is the first point of entry of material into the
factory and the last point at which the factory still has control of its product before they leave to go to a
6
customer. Store should therefore be properly maintained to prevent deterioration, contamination of stored
goods.
Requirements of storage area:
Storage areas should be of sufficient capacity to allow the orderly storage of the various categories
of materials and products.
Storage areas should be designed or adapted to ensure good storage conditions.
Storage areas should be clean, and free from accumulated waste and vermin.
Materials and pharmaceutical products should be handled and stored in such a manner as to prevent
contamination, mix-ups and cross-contamination.
Materials and pharmaceutical products should be handled and distributed according to GMP as
defined in this document.
Rejected materials and pharmaceutical products should be identified and controlled under a
quarantine system designed to prevent their use until a final decision is taken on their fate.
Materials and pharmaceutical products should be stored in conditions which assure that their quality
is maintained, and stock should be appropriately rotated. The first expired first out (FEFO)
principle should be followed.
Storage areas should provide adequate lighting to enable all operations to be carried out accurately
and safely.
Different labels used in stores are as follows:
CTL practices good storage and distribution practice. So the store scientifically designed to make it rodent
proof, adequate storage is maintained, and RH is adjusted to avoid the degradation of raw materials and
finished product. CTL has separate store room for RM/PM of non-penicillin, penicillin, cephalosporin, feed
supplement, and finished product. The store is very spacious and properly designed to ensure good storage
condition.
The goods when delivered are received and they are checked as per the purchase order. The data entry is
done via software programme. Afterwards the goods are cleaned and dedusted and stored in the quarantine
room. Sampling is performed by the QA officer in the sampling booth. The choice of a sampling plan
should always take into consideration the specific objectives of the sampling and the risks and
consequences associated with inherent decision errors. Sampling may be required for different purposes,
such as prequalification; acceptance of consignments; batch release testing; in-process control; special
controls; inspection for customs clearance, deterioration or adulteration; or for obtaining a retention
sample.
The tests to be applied to the sample may include:
verifying the identity;
performing complete pharmacopeial or analogous testing; and
performing special or specific tests.
In case of the active materials, all the containers need to be sampled whereas, for the excipients,
appropriate sampling plan needs to be carried out. Generally n-plan i.e. formula (n+1) is applied where
n is the number of containers to be sampled.
The sampled materials are sent to the QC lab for analysis and these products are tagged with yellow slip
notifying under test. The materials are stored in quarantine until QC approves for their further use. The
passed materials as per the specification are tagged with green slip whereas the failed ones are tagged with
red slip and are kept in the separate area. The rejected materials are either destroyed or returned to the
vendor.
5.1.1 Raw material store:
Active as well as excipients are stored in this store. RM store is separate for pharma product and veterinary
products. The approved products are stored in this store. RM is dispensed to production as per the
requisition following the BMR with the rule FIFO or FEFO. The amount of RM received and dispensed
each time is recorded in the register. The dispensing is done in the presence of QC personnel.
passed materials are stored and dispense to production as per requisition. The packaging materials are
grouped into primary and secondary packaging materials.
5.1.3 Finished product store:
After passing all the tests, finished product is packed well and transferred from packaging section to
finished product store room from where these products are released to the market. Delivery of finished
product is done only upon request from sales department. Delivery of FG also follows FEFO and FIFO
system. FG store in-charge dispatch the FG goods as mentioned in issue register (Challan) received from
Head Office and write details about product and quantity being dispatched to Head office. Gate pass is
prepared for all quantities being dispatched which are verified by security personnel at the gate. Dispatch
FG goods are loaded in Delivery van and dispatched to the destination place viz. Distributors.
Finished Goods store also receives the returned and expired product from distributer which is segregated
into different area to avoid mix-up. In case of expired products, destruction note is prepared by store which
is approved by QC in-charge, management and QA in-charge. Then, in presence of QC, expired products
are destroyed as per company rule.
Following is the chart showing system and practice followed by store for handling of new
raw materials
Store department transfers the approved raw materials into the main
store and register details are enter in the stock register.
Store department transfers the approved raw materials into the main
store and register details are enter in the stock register.
Dispensing of RM/PM for a batch is done in the dispensing booth by officer from
10
store, supervised by QC and counterchecked by production
on receiving RM/PM
requisition Slip from production which in turn is issued on release of BMR or BPR
on room pressure differentials cascades and cross contamination control. The prevention of contamination
and cross contamination is an essential design consideration of the HVAC.
It performs four basic functions:
Control airborne particles, dust and micro-organisms
Maintain pressure difference between two areas.
Maintain space moisture (Relative Humidity
Maintain space temperature.
12
Coil section
It consist heating and cooling coils. It maintains temperature and Relative Humidity of air.
Blower section
Sends air to supply duct according to the required CFM (Cubic feet/ min). The air change/hour in the
operating room has been maintained to be at least 20 changes / hour depending upon the volume of room,
products and personnel involved as per WHO-GMP Guideline.
13
14
The water should be free from unacceptable microbial, chemical or physical contamination.the water in the
factory comes from water supplier. After removing iron by aeration, the water is then pumped to the storage
tank kept on top floor. Then, it is subjected to treatment as follows:
Aeration
Chemical
system
Degasser
Sand filter
Carbon filter
Softener
Reverse osmosis
UV treatment
Specifications of PW:
15
16
Non-penicillin section
Cephalosporin section
Penicillin section
Areas
S.
N
Areas
Raw
Material
Dispensing Area
Tablet
area
Mixing,
Granulating
and
Drying Room
IPQC Room
Tablet
Compression
Room
Quarantine Store
Tablet
Room
Coating
18
Packing
Electronic Balance-Electronic
Granulating
Drug +
Diluent
(Pulverizati
Wet
mixing
Dry
mixing
Agent
Water/solvent
Dry
sieving
Wet
sieving
Drying
Blending
Compressi
on
Coating
Packaging
Disintegrant
+ Glidant +
Lubricant
Wet granulation is further of two types: Aqueous (water is used) and Non-aqueous (organic solvents are
used). Generally, starch paste and PVP are used as binding agents. These are kneaded for sometime
carefully. As longer the kneading time, longer will be the disintegration time and thus the rate of dissolution
will be decreased. Temperature is the critical parameter while preparing starch paste. Granulation can be
inspected by:
20
Mixing and granulation is performed in RMG. RMG has a stainless steel mixing bowl containing a three
bladed main impeller, which revolves in the horizontal plane, and a three-bladed auxiliary chopper, which
revolves either in the vertical or the horizontal plane. The unmixed dry powders are placed in the bowl and
mixed by rotating impeller for a few minutes. Granulating liquid is then added via a charging port in the lid
of the granulator while the impeller is turning. The granulating fluid is mixed into the powder by the
impeller. The chopper is usually switched on when the moist mass is formed so as to break up the wet mass
to produce a bed of granular material. Once the satisfactory granule has been produced, the granular
product is discharged, passing through a wire mesh, which breaks up any large aggregates. The major
benefit of this process is that mixing, massing and granulation are all performed within few minutes in the
same piece of equipment.
Another equipment used for the granulation is mass-mixer. It is used for making large quantity of
granules.
Drying
FBD is used for the drying of materials to get the desired moisture content in the tablet manufacturing
granules. It is the well known and widely used equipment in pharmaceutical manufacturing.
Principle of FBD: If air is allowed to flow through a bed of solid powdered material in upward direction
with the velocity greater than the settling rate of the particles, the solid particles will be blown up and
become suspended in the air stream. At the stage solid bed looks like the boiling liquid, therefore this stage
is called as fluidized. Use of hot air to fluidizing the bed will increase the drying rate of the material.
Components
Material container (material to be dried are placed)
Air suction fan (generate airflow necessary for fluidization of the powders)
Steam of hot air (for fluidization to the desired temperature)
Inlet air(filters the air used for fluidization of powders filter)
Exhaust air (filters to retain dust and fine particles)
Filter or FBD bag (increase surface area for drying)
21
Working
The material to be dried is placed in the material or product container. Air is introduced from the bottom of
the container and heated at required temperatures by the heaters. This air is filtered through the filtered and
then passes through the bed of the material. This air flow is generated by the fans fitted at the top of the
equipment. The flow rate and the operating temperature are adjusted by control panel. As the flow of air
increases, the bed known as FBD bag expands and the particles of powder starts a turbulent motion. Due to
the regular contact with air, material gets dry. The air leaving the FBD passes through the filter to collect
the fine particles of the material. FBD has a high drying rate and the material is dried in a very short time
i.e., about 15 min. Material remains free flowing and uniform. FBD bags are finger like in structure to
increase the surface area of the drying bed.
Blending or Lubrication room
After drying, dry screening of the material is carried out. Then it is send for lubrication. Various lubricating
agents like magnesium stearate, talc, colloidal silicon dioxide (aerosil) are used. These help in reducing
friction by interposing an intermediate layer between tablet constituents and the die wall during
compression and ejection. The equipment used for drying is double cone blender.
Compression room
Compression is done just after lubrication of granules. For this purpose, tablet compression machines of
various stations are used.
In CTL, 27D or 16D rotary compression machines are used in T ablet section and 10 station rotary
compression machines is used in R&D department. Humidity and temperature should be controlled in this
room by dehumidifier because excess moisture can affect the flow of granules causing weight variation and
various other problems like sticking, picking or chipping.
All the tablet presses employ the same basic principle: they compact the granular or powdered mixture of
ingredients in a die between two punches. Different shapes and sizes of dies and punches are available
according to the need. During compression, the ratio of granules and fine should also be maintained i.e.,
70:30. If the granules are more than fine, weight variation may occur. Likewise, if the ratio of fine exceeds
then improper flow property may exist. Other parameters like weight, hardness, thickness, speed have to be
equally considered during compression.
Hopper
22
Feed frame
Turret
Punches
Die table
Die
Cam track
Pressure roll
Chute
Coating room
Coating process is the last critical step in the tablet production cycle. Tablet coating is the application of a
coating composition to a moving bed of tablets with the concurrent use of heated air to facilitate
evaporation of solvent. The distribution of the coating is accomplished by the movement of the tablets
either perpendicular (coating pan) or vertical (air suspension coater) to the application of coating
composition. The successful application of the coating solution formula to a tablet provides the visual
characteristics for the product; thus, the quality of the product may be judged on this final production step.
23
In CTL, coating machine of perforated pan system i.e., semi automatic coater is used. Depending upon the
nature of drugs, tablets are either enteric or film coated.
Coating objectives
Types of coating
I.
II.
III.
Film coating
Addition of polymer film to the surface of tablet
Adds up to 2-3% weight to final tablet
Retains contour of original core and usually not shiny
Coating time 2-3 hrs
Prevents from moisture, mask bitterness, elegance and identity.
Sugar coating
Application of sucrose based solution to tablet core
Adds up to 30-50% weight to final tablet
Rounded with high degree of polish
Coating time more than 8 hrs
Masks bitter taste
Enteric coating
Polymer barrier applied on tablet core
Adds up to 9-10% weight to final tablet
For acid labile drugs, to deliver drugs with high bioavailability in basic medium to their primary
absorption site i.e. intestine and to prevent gastric irritation.
Coating pan
Spray Gun (sprays coating solution which works on the principle of compressed air sent through
Air Compressor)
Hot air Blower adjusted to required temp to facilitate effective drying.
Dust extractor is fitted properly so that dusts produced during coating are carried away.
Colloid mill is used in the coating room to ensure particle size reduction and proper dispersion.
24
Problems
of
Coating
Causes
Sticking &
picking
Over wetting
Excessive film
Inefficient
drying
Fast drying
High pigment
concentration
and polymer
concentration
with coating
solution
Decrease degree of
atomization
Optimise
concentration
High solution
viscosity
Inadequate
spreading of
coating
solution
before drying
Thinning
of
solution with more
solvent
Roughnes
s
Orange
peel effect
Remedies
Decrease
liquid
application
Increase in drying
air temperature and
air volume
the
Blister
forming
Rapid drying
High
temperature
Milder
drying
concentration
Hazing/
Dull film
High
temperature,
humidity
Control
temperature
humidity
Color
variation
Migration of
soluble dye
Improper
mixing
25
and
Bridging
and filling
uneven spray
pattern
insufficient
coating
The
film
shrink
and
pull away the
sharp corner
of bisect and
form bridge
Increase
plasticizers
concentration
Sorting of tablets
Sorting is done before packaging process to minimize the risks and chances of packing the deviated
tablet. Different parameters like shape, size, color, logo, breakage, cracking etc are observed manually.
IPQC
In-process inspection and testing should be performed by monitoring the process or by actual sample
analysis at defined locations and times. The results should conform to established process parameters or
acceptable tolerances. Work instructions should delineate the procedure to follow and how to use the
inspection and test data to control the process.
The works of IPQC are related with production, store and Quality Control. It also checks different
parameters for solid preparations. The in-process quality control for solid dosage form i.e., tablet are:
Checking the weight variation of the tablets at pre-determined intervals during manufacturing
Checking disintegration, hardness, thickness and friability of the tablet repeatedly each hour of
production
26
Specification
Standard Limit %
80 mg or less
10
>80 mg &<250
mg
7.5
250 mg or more
Tablets
Limit
Uncoated
NMT 15 min
Coated
NMT 30 min
In CTL has operated capsule filling machine with 300 holes is used for manual filling of hard gelatin
capsule.
IPQC for Capsules
It includes:
28
Weight variation.
Physical appearance(shape, size, color, locking etc)
Locked capsule length
Fill Weight
Disintegration Time (DT apparatus)
Wax vessel
Aqueous vessel
Anchor/ Manufacturing vessel
Ointment transfer tank
Semi-automatic ointment filling and crimping machine
29
QC
analysis and
release
RM Requisition from
Production
In presence of
production. QC
and store
personnel
RM Dispensing
by Store
Preparation of Oil
phase (Planetary
Mixer)
30
Liquid manufacturing:
In liquid section, various veterinary syrup and suspension are manufactured. The Water used for the
preparation of liquid formulation is RO water. Liquid section has following rooms:
31
Fill volume
Leak test
pH test
Physical parameter
I.
More protective
High light resistance
High moisture resistance
In this machine, two thin foils of aluminium are used for packing the tablets. One of the foils is printed in
which the batch no., mfg. date, exp.date and price are printed whereas other is plain. The printed foil
consists of heat seal lacquer which helps in sealing the two aluminium foils together. The air pressure is
required to run the machine which is supplied via the air compressor.
II.
Strip Packaging
Strip packing is done for moisture sensitive drugs as Aluminium foil is highly resistant to moisture
permeation.
Parts of a strip packing machine
1. Fixed parts: control panel, heater, felt bush roller
2. Changeable parts:
a) Washable: hopper, plate, chute
b) Non washable: roller, printing drum, gear
33
Process of packaging
Two webs of materials being fed between two heated crimping rollers on which there are circumferential
cavities of a size and depth appropriate to the shape, size and thickness of the article being packed. The
material to be packed is fed from a hopper through channels to drop between the two webs where they meet
between the crimping rolls and the cavities there in. the webs are then sealed together by the activation of
the thermoplastic coating on their inner surface
and pockets formed around the contents. To check that the packaging material is not perforated around the
periphery of the pockets and the heat seals are efficient, sample strips are taken at regular intervals and
tested.
HOPPER
PLAIN Al.
HEAT
FOIL
ER
TABLET FILTER
SETTING
PLATE
COMPRESSOR
140
CUTTER
CSTRIP PACKED PRODUCT
O
Al.
HEAT FOILBATCH
PRINTI
ER
NG
140O
ROLLE
C
R
I.
Blister packaging
Blister pack is a term for several types of pre-formed plastic packaging used for small consumer goods,
foods, and for pharmaceuticals. The primary component of a blister pack is a cavity or pocket made from a
formable web, usually a thermoformed plastic. This usually has a backing of paperboard or a lidding seal of
34
aluminium or plastic. Most commonly used thermoplastic are PVC and PVDC. PVDC provides more
protection against moisture than PVC.
Changing parts: forming roller, sealing roller, forming heater, sealing heater and the cutting gear
Process of blister packing
A sheet of thermoplastic resin is heat softened and vacuum is drawn to the softened sheet of plastic into a
contoured mold. Heat-softening is done by passing thermoplastic through forming heater heated at
temperature of 1400C-1600C and is cooled by passing through chiller. After cooling, the sheet of plastic is
released from the mould preceding it to guide track of packaging machine. The semi rigid blister previously
formed is filled with the product and lidded with an aluminum foil. Sealing is done at temperature above
1500C-1800C. Cutter is available to cut the blister pack into the desired size by the blade. The cutting gear
is set according to the size of blister/strip to be cut. After they are carried to secondary packing room by
conveyor belt.
HOPPER
VIBRATOR + SENSOR
FILLING PLATE
PVC/PVD
Al.
SETTING
BLIST
BATC
SEAL
SEALIN
C FOIL
FOIL
PLATE
ER
H
ING
G
SEALING HEATER
PRINT
HEA
HEATER FORMI
CUTTER
NGBLISTER PACKED PRODUCT
ING
TER
160OC- ROLLE
ROLL
180O
170OC
R
ER
C
35
Strip pack, Blister pack or Alu- alu packed tablets are packed in passed Printed Carton (Duplex
Box) and then in passed Corrugated Board Container.
m. Maintaining quality control test records of all the analysis i.e. RM, PM, IPS.
Flow chart of QC activities
AA
nc
at
li
yv
si
it
si
e
s
37
Document section
Microbiology section
HPLC section
Managers Office
Chemical reagents section
Heat generating room
Analysis area
Stability chamber sections
Instrumental section
UV spectrophotometer
Karl Fischer Titrimeter
Dessicator
Weighing Balance
Hardness tester
Polarimeter
High performance liquid chromatography (HPLC)
Digital Ph meter
Sonicator
Centrifuge machine
pH meter
Water bath
Leak test apparatus
Autoclave
Vernier Calliper digital
Melting Point Apparatus
Distillation unit
Humidity chamber
Stability chamber
38
Magnetic Stirrer
Muffle furnace
Disintegration Test Apparatus
Dissolution Apparatus
Oven
Flame photometer
Potentiometer
Laminar Air Flow
Incubator
FTIR apparatus
Friability tester
39
Swab test
This test is performed to ensure that equipments and utensils are properly cleaned and does not cross
contaminate the active ingredients to next batch production. It is provided to determine compliance with
the requirements given in the individual monograph / specifications. Once this test is failed cleaning is
repeated and again swab test is performed to confirm the cleanliness.
Stability studies
This stability testing is to provide evidence on how the quality of an active substance or pharmaceutical
product varies with time under the influence of a variety of environmental factors such as temperature,
humidity and light. This enables recommended storage conditions, re-testing intervals and shelf-lives to be
established. Insufficient stability of a drug product can result in changes in physical (like hardness,
dissolution rate, phase separation, etc.) as well as in chemical characteristics (high risk of decomposition of
active substances).
In Florid, basically two types of stability studies are carried out :
a) Real time (long term) stability study: It is carried out every 3 months over the first year, every 6
months over the second year, and annually thereafter throughout the proposed shelf-life. i.e. 0, 3, 6, 12
months, for a 12 months study.
b) Accelerated stability study: A minimum of three time points, including the initial and final time points
(e.g., 0, 3, and 6 months), for 6-months study is recommended.
Stabilit
y Study
Real
time
Storage
Minim
um
time
period
covere
d
by
data at
the
time of
submis
sion
Condition
Tempera
ture
R
H
300 50C
65
%
5
%
12
months
40
400 50C
Acceler
ated
75
%
5
%
6
months
Documentation, records and its renewal of each and every aspect of the industry
Qualification
Product Recall Handling.
Self-inspection
Training Program
Validation
Retrospective
Prospective
Concurrent validation
Re-validation
41
In CTL Pharmaceutical, all the activities related to the product quality is handled by QA, QC and
production department.
5.6.1 Documentation:
Good documentation is a crucial part of Quality Assurance System. The rationale behind documentation is
to record important information with substantiation. Documentation is written proof/ evidence of any
activity. GMP requires that the manufacturing process be adequately documented throughout all stages of
operation. Before releasing the product for distribution, Quality Assurance should review the batch records
of all in-process tests and controls and of all test of final product to determine whether they conform to
specification so that they can be confident in the final product release. CTL Pharmaceutical has been
practiced good documentation practice to ensure their product quality.
42
BMR
5.6.2 Validation:
Validation is defined as documented evidence which provides high degree of assurance that meets its
predetermined specifications and quality attributes. Validation is systematic approach to gathering and
analyzing sufficient data that will give reasonable assurance (documented evidence), based on scientific
judgment, that a process, when operating within specified parameters, will consistently produce results
within predetermined specifications.
43
3. Concurrent validation:
Concurrent validation is established documented evidence that a process is based on information generated
during actual implementation of the process.
4. Re-validation:
Repeated validation of an approved process to ensure continued compliance with established requirements.
5.6.3 Qualification:
Qualification proves that any premises, system and items of equipment work correctly and actually lead to
the expected results. New systems and equipment should pass through all stages of qualification including
design qualification (DQ), installation qualification (IQ), operational qualification (OQ) and performance
qualification (PQ) as appropriate.
Stages of qualification:
Design qualification
Installation qualification
Operational qualification
Performance qualification
Change control/Re-qualification
44
Product
name
Generic
name
strength
Dosage
form
1
.
ACEAID
Aceclofenac
100 mg
Tablet
2
.
ALEXOF
EN
Fexofenadine
hydrochlorid
e
120/180
mg
Tablet
3
.
ALEXOF
EN 60 ml
Fexofenadine
hydrochlorid
e
30 mg
Liquid
ALFRAD
Cefadroxil
500 mg
Capsule
45
OX 500
5
.
ALTRIN
Cetrizine
hydrochlorid
e
5 mg
Liquid
6
.
AMD
Amlodipine
2.5/5/10
mg
Tablet
7
.
AMD-AT
Atenolol+
amlodipine
50/5 mg
Tablet
8
.
AMOX
CTL
60/90 ml
Amoxycillin
125 mg
Dry syrup
1
0
.
AMOX
CTL
250/500
Amoxycillin
250/500
mg
Capsule
1
1
.
AMP GEL
170
Alumunium
hydroxide+
magnesium
hydroxide+
methyl
polysiloxane
250/250/
50 mg
Liquid
1
2
.
AZITOP
500
Azithromyci
n
500 mg
Tablet
1
3
.
AZITOP
15
Azithromyci
n
200 mg
Liquid
BRONKO
Salbutamol+
2/4 mg
Liquid
46
4
.
MOL
EXPECT
ORANT
bromhexine
hydrochlorid
e
1
5
.
BRONKO
MOL 100
ml
salbutamol
2 mg
Liquid
1
6
.
BURNHE
AL PLUS
25g
Silver
sufadiazine+
chlorhexidine
gluconate
1%w/w/
0.20%
w/w
Ointment
1
7
.
C-TAB
Paracetamol
+
chlorphenir
amine
maleate+
phenyl
epherine
HCl
500/4/10
mg
Tablet
1
8
.
CALFER
OL
Calcium+
Vitamin D3
500
mg/250
IU
Tablet
1
9
.
CALFER
OL-CM
Calcium+
Vitamin D3
250
MG/200
IU
Tablet
2
0
.
CAREBO
MET
500/850
Metformin
HCl
500/850
mg
Tablet
47
2
1
.
CARBO
MET-ER
500/1000
Metformin
HCl
500/1000
mg
Tablet
2
2
.
CEPHA
D/S
60
ML
Cephalexin
125 mg
Dry syrup
2
3
.
CEPHA
CTL
250/500
Cephalexin
250/500
mg
Capsule
2
4
.
CHLORA
CTL60
Chloramphe
nicol
125 mg
Liquid
2
5
.
CHLORA
CTL
250/500
Chloramphe
nicol
250/500
mg
Capsule
2
6
.
CLAMPI
CTL
Ampicillin+
cloxacillin
250/250
mg
Capsule
2
7
.
CLOTIF
15g
Clotrimazol
e
1% w/w
Ointment
2
8
.
CLOTIFB 15g
Clotrimazol
e+
beclomethas
one
1% w/w /
0.025%
w/w
Ointment
48
dipripionate
2
9
.
CLOVAT
E
Clobetasol
propionate
0.05%
w/w
Ointment
3
0
.
CLOVAT
E-S
Clobetasol
propionate+
salicylic acid
0.05
w/w /3%
w/w
Ointment
3
1
CLOVIR
5g
Aciclovir
5% w/w
Ointment
3
2
.
CLOVIR
200/400/8
00
Aciclovir
200/400/
800 mg
Tablet
3
3
.
CLOX
CTL
250/500
Cloxacillin
250/500
mg
Capsule
3
4
.
CODMIN
Codiene
phosphate
15 mg
Tablet
49
3
5
.
COPAR
Paracetamol
+
codiene
phosphate
500/10
mg
Tablet
S
.
N
o
Product
name
Generic
name
strength
Dosage
form
3
6
.
CUFSUP
100ml
Levodropro
pizine
30 mg
Liquid
3
7
.
CYCLOD
ON
Dicyclomine
HCl+
simethicone
10/40 mg
Liquid
3
8
.
DICONA
C 30g
Diclofenac
sodium
1% w/w
Gel
3
9
.
DICONA
C PLUS
30g
Diclofenac
diethylamin
e+
methyl
salicylate+
oleum lini+
menthol
1.16%w/
w
/
10%w/w/
3%w/w /
5% w/w
Gel
4
0
.
DOX
CTL 100
Doxycycline
100 mg
Capsule
50
4
1
.
DOXOFI
L
Doxofyline
400 mg
Tablet
4
2
.
DYSPAM
80
Drotaverine
HCl
80 mg
Tablet
4
3
.
ETHRO
CTL 60ml
Erythromyci
n
125 mg
Liquid
4
4
.
ETHRO
CTL
250/500
Erythromyci
n
250/500
mg
Tablet
4
5
.
EXPULI
N 100ml
Ammonium
chloride+
pheniramine
maleate+
menthol
120/12.5/
1.14 mg
Liquid
4
6
.
F-CLOX
250/500
Flucloxacilli
n
250/500
mg
Capsule
4
7
.
FERON
Elemental
iron+ folic
acid+ zinc
120/0.5/2
0 mg
Capsule
FERON-
Elemental
100/1.5
Tablet
51
8
.
XT
iron+
acid
folic
mg
4
9
.
GERMO
LIN
Chlorhexidi
ne gluconate
0.2% w/v
Liquid
5
0
.
GABANE
T 100/300
Gabapentin
100/300
mg
Capsule
5
1
.
GLOSA
500
Glucosamin
e sulphate
potassium
chloride
500 mg
Capsule
5
2
.
HALVAT
E 15g
Halobetasol
propionate
0.05%
w/w
Ointment
5
3
.
HALVAT
E-S 15g
Halobetasol
propionate+
salicyclic
acid
0.05%
w/w/ 3%
w/w
Ointment
5
4
.
INDOMO
D 25/50
Indomethaci
n
25/50 mg
Capsule
S
.
N
o
Product
name
Generic
name
strength
Dosage
form
52
5
5
.
Isolax
Isapgol husk
49% w/w
Powder
5
6
.
KEPODE
X 200
Cefpodoxim
e
200 mg
Tablet
5
7
.
KEPODE
X
dry
syrup
30ml
Cefpodoxim
e
50 mg
Powder
5
8
.
KEPODE
X
dry
syrup 60
ml
Cefpodoxim
e
50 mg
Dry syrup
5
9
.
LANSOP
AZ
lansoprazol
30 mg
Capsule
6
0
.
LIPILAG
E 10/20
Atorvastin
10/20 mg
Tablet
6
1
.
LOTACE
25/50
Losartan
potassium
25/50 mg
Tablet
6
2
LOTACE
A
Losartan+
amlodipine
50/5 mg
Tablet
53
6
3
.
LOTACE
H
Losartan+
hydrochloro
thiazide
50/12.5
mg
Tablet
6
4
.
METHE
X
Mecobalami
n
500/1500
mcg
Tablet
6
5
.
METOR
ATE
25/50
Metoprolol
tartrate
25/50 mg
Tablet
6
6
.
MEZOR
AX
Paracetamol
+
chlorzoxazo
ne
500/250
mg
Tablet
6
7
.
MUROB
AN 5g
Mupirocin
2% w/w
Ointment
6
8
.
MYPRID
E 1/2
Glimipiride
1/2 mg
Tablet
6
9
NIBUCID
Nimesulide
100 MG
Tablet
54
7
0
.
PENISOL
VK
Phenoxy
methyl
penicillin
250 mg
Tablet
7
1
.
7PLEX
syrup 200
ml
Thiamine
hydrochlori
de+
riboflavin+
nicotinamid
e+
cynacobala
mine+
Dpantheol+
pyridoxine
hydrochlori
de
2/2.5/20/
2/3/0.75
mg
Liquid
7
2
.
7 PLEX
capsule
Elemental
zinc+
thiamine+
riboflavin+
pyridoxine
HCl+
cynacobala
mine+
nicotinamid
e+ folic acid
15/10/10/
2/7.5/75/
1 mg
Capsule
7
3
.
PRAZOL
Omeprazol
20 mg
Capsule
7
4
PROFIX
dry syrup
Cefixime
50/100
mg
Dry syrup
55
60ml
7
5
PROFIX
200/400
Cefixime
200/400
mg
Tablet
7
6
.
P-ROXI
20
Piroxicam
20 mg
Tablet
7
7
.
ROSEMI
DE 40
Frusemide
40 mg
Tablet
7
8
.
ROSEMI
DE-A
Frusemide+
amiloride
40/5 mg
Tablet
7
9
.
ROSEMI
DE-S
Frusemide+
spironolacto
ne
20/50 mg
Tablet
8
0
.
ROUTIN
5/10/20/40
Rosuvastin
5/10/20/4
0 mg
Tablet
8
1
.
SHAKTIJ
AL
Sodium
chloride+
sodium
2.6/2.9/1.
5/13.5 g
Powder
56
citrate+pota
ssium
chloride+
glucose
anhydrous
8
2
.
TERBIN
A 10g
Terbinafine
HCl
1% w/w
Ointment
8
3
.
TETRA
CTL
250/500
Tetracycline
hydrochlori
de
250/500
mg
Capsule
8
4
.
TRICON
Itraconazole
(enteric
coated
granules)
100 mg
Capsule
8
5
.
WINMO
L
Paracetamol
125 mg
Liquid
8
6
.
WINMO
L PLUS
Paracetamol
+ ibuprofen
125/100
mg
Liquid
8
7
.
XORPIC
500
Ciprofloxaci
n
500 mg
Tablet
8
8
.
ZINCOV
A 20
Elemental
zinc
20 mg
Tablet
57
Conclusion
The 18 days In-plant training at CTL Pharmaceutical Pvt. Ltd. was very informative, fruitful and
productive for me. It was a great opportunity for me to complete my in-plant training at CTL
Pharmaceuticals Pvt. Ltd. I feel very glad to spend my short period of time at CTL with friendly, cooperative, helpful and supportive staffs. Their throughout guidance and support have really helped me to
understand and learn many fundamental and practical things of pharmaceutical manufacturing and its
regulation within a very short period of time , for which I am very grateful to all the CTL Pharmaceuticals
team. I am sure that knowledge and skills I gained here will help me to boost up my career.
In this training period I got the knowledge about different departments of pharmaceutical industry
like Production, Quality Control, Storage, Quality Assurance etc and various manufacturing processes of
medicines.
Lastly I would like to convey my best wishes to CTL for its success in upcoming days.
58
59