Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Problem
Methodology for
communicating system
changes
Need to have access to
current status of IPMS
system
Category
Source
Jul-00
Jul-00
Dec-99
Status
Complete
Set-up
QChem
Dec-99
Training
QChem
Dec-99
Dec-99
Communication QChem
Training
QChem
Dec-99
Training
QChem
Dec-99
Complete
Complete
Ongoing
Training ongoing
as required
Ongoing
REVISION DATE:
Problem
Paperless and IPMS do not
fit hand in glove. With IPMS,
progress is measured as
deliverables are issued,
milestones are reached
(discipline comments). IPMS
requires the disciplines to
log their review/comments
with documentation for
IPMS credit.
Inflexibility reporting
capabilities
Category
System
Development
Training
Training
Training
System
Development
Source
QChem
QChem
QChem
QChem
QChem
Status
Dec-99
Feb-00
Team in place
Feb-00
Team in place
Feb-00
Make system flexible to produce high Custom reports are possible. But
level reports and flexible in formatting recommendation forthcoming from IPMS
per client and JV partner requirements start-up team.
Dec-99
Action deferred
until
documentum is
beta tested.
Part of start-up
training
Working
REVISION DATE:
Problem
Category
System
Development
System
Development
System
Development
Training
Source
QChem
Feb-00
QChem
Feb-00
QChem
Feb-00
QChem
Feb-00
Status
Complete
Review required
for each project
Under review
System
Development
ARCO
CARSON
Each project is
reviewed to
This resulted in handling the subdetermine the
projects individually, then
Recommend setting up projects as one large
best WBS
incorporating into the primary projects. job segregated by multiple cost areas
structure
The project buys material from local
vendors, but Purchasing cannot
Project purchasing needs to request
commit PO in IPMS due to the local
Houston to put vendor ID's on the list.
vendor not on the approved vendor
Purchasing has given the authority to input
list.
vendor ID's
Complete
System
Development
ARCO
CARSON
Training
Phenolchemie
Nov-98
Nov-99
Ongoing
REVISION DATE:
Problem
IPMS was not operational in
the material control offices
when we moved to the
field. Lost 2 weeks
Not all disciplines used IPMS
as their materials catalog
and index.
Staff IPMS earlier on the
project
Third party (Lurgi) piping
specifications and material
identification did not meet
the needs of IPMS, PDS and
KBR procurement
Schedulers had problems
getting Early Start Dates
from Primavera into IPMS
IPMS start-up team did not
include Engineering
Roll-up drawing milestone
progress item level to
package level was
extremely difficult to
execute; too many bugs
existed.
Need to be aware of
shortcuts
Had problems printing when
Cost puts in a lot of their
runs at one time
Category
Source
Training
Set-up
Phenolchemie
Nov-99
Set-up
Phenolchemie
Nov-99
Set-up
Phenolchemie
Nov-99
Phenolchemie
Nov-99
Phenolchemie
Nov-99
Training
Status
Ongoing
Complete
Ongoing
As required
Ongoing
Set-up
Phenolchemie
Nov-99
Complete
Training
Phenolchemie
Nov-99
Ongoing
Training
Phenolchemie
Nov-99
Complete
Systems
problem
Phenolchemie
Nov-99
Complete
REVISION DATE:
Problem
Category
Training
Source
Phenolchemie
Nov-99
Phenolchemie
Nov-99
Status
Complete
Complete
We are not
changing to
system at this
time.
Phenolchemie
Nov-99
Phenolchemie
Nov-99
Phenolchemie
Nov-99
Ongoing
Phenolchemie
Nov-99
Ongoing
No action, leave
as is.
REVISION DATE:
Problem
All project leadership needs
to understand how the
modules are integrated,
work and impact the
project, cost and timing.
Process 5040 , importing
Control packages from IPMS
to ACLS does not work at
all. When attempted, all of
the existing Control
packages.
BOM's should be completely
updateable by field
personnel (remove
spool/class splits, etc.)
The Work Plan is a
cumbersome operation;
taking a week to process a
work plan is not realistic
and a waste of time.
Expediting Report needs to
be able to be sorted by
P.O., tag, current promise,
ETA date.
Document Control should be
connected to Expedition if
data is being tracked.
Needs to be easier to move
between expediting screen
and multi-line expediting
status screen. It would
help if both screens cold be
open a the same time.
When performing mass
updates, the screen will go
back to a previous P.O.
when complete. This
causes errors in updating.
Category
Source
Training
Phenolchemie
Nov-99
Training
Phenolchemie
Training/
Security
Status
Ongoing
Nov-99
Complete
Phenolchemie
Nov-99
Complete
Training
Phenolchemie
Nov-99
Training required.
Ongoing
System
Phenolchemie
Nov-99
To review
Training
Phenolchemie
Nov-99
Ongoing
Training
Phenolchemie
Nov-99
Complete
Training
Phenolchemie
Nov-99
Complete
REVISION DATE:
Problem
Need prompt or flag for
partial deliveries or
automatic subline for
remaining items.
An icon or key is needed to
ascertain warehouse
request numbers rather
than going through a time
consuming 8 step process
from the BOM line to the
request number
Obtain an illegal operation
message 95% of the time
when in summary and
searching for an item/PO
Cannot back a material
reference item out unless
everything received against
the material ref. Which
requires backing out pick
tickets or doing a lump sum
return.
Enlab labor and SAP
interface download into
IPMS (not timely with no
control) depended on the
IPMS support person make
the file available.
When a problem occurs,
sometime it takes hours or
the next day before we can
get some one in Houston
Category
Source
System
Phenolchemie
Nov-99
To review
Training
Phenolchemie
Nov-99
Ongoing
System
Phenolchemie
Nov-99
This is fixed.
Complete
Training
Phenolchemie
Nov-99
Complete
System
Phenolchemie
Nov-99
Complete
Set-up
Phenolchemie
Nov-99
Complete
Status
REVISION DATE:
Problem
Category
Source
Status