Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Geomorphology
journal homepage: www.elsevier.com/locate/geomorph
a r t i c l e
i n f o
Article history:
Received 1 April 2013
Received in revised form 4 August 2013
Accepted 15 August 2013
Available online 29 August 2013
Keywords:
Brazos River
Channel adjustment
Environmental disturbances
Flow regulation
Sabine River
a b s t r a c t
Historical channel adjustments are documented and discussed in context with anthropogenic disturbances along
two meandering, coastal plain rivers the lower Brazos and Sabine Rivers in the south-central United States.
Hard-copy streamow-measurement notes of the U.S. Geological Survey were utilized to render historical
cross sections (19252007) at nine gauging stations, which were complemented with repeat photographs
and ood-frequency analysis to assess trajectories of channel change and interpret causative mechanisms.
Downstream- and upstream-propagating disturbances caused episodes of channel-bed incision and aggradation
at different locations for distinct time periods along both rivers. Incision associated with upstream dams is detected, but channels are compensated downstream with sediment inputs from lateral channel migration and tributaries. In one case, temporary aggradation along the Brazos River at Waco was likely caused by a combination of
dam construction and regional soil erosion. Channel-bed incision on the lowermost Brazos River is unrelated to
dams, but is associated with instream aggregate extraction, possibly in conjunction with downstream channelization. On the Sabine River, extensive aggradation during the 1930s might be associated with logging activities
(1880s1930s), but whether the cause is pervasive regional-scale hillslope erosion or local-scale mill-site activities
is indeterminate. Following passage of this sediment, the river generally recovered to pre-disturbance conditions
and has exhibited stability despite a mainstem reservoir. Translation of this sediment slug is attenuated by a
transition to a ood-prone, distributary-dominated system downstream of the HolocenePleistocene terrace
onlap position. Additional ndings include cross-channel hingepoints separating thalweg incision from simultaneous point-bar or bank accretion at meander bends, which indicates channel adjustment occurs along noncohesive beds in preference to cohesive or articially reinforced banks. Also, ood reduction has resulted in
bankfull stages that are higher than levels associated with the post-regulation 2-year return period. Finally,
vegetation encroachment along banks since the 1970s coupled with reduced ooding along the lower Brazos
River has promoted bank accretion deposits that, when fully developed, serve as morphologic indicators of the
post-regulation 1- to 2-year return period stage.
2013 Elsevier B.V. All rights reserved.
1. Introduction
Alluvial river channels are sensitive systems that integrate prevailing
environmental conditions from their drainage basins and can gradually
or rapidly adjust to variables including tectonics, sea-level uctuation,
discharge, sediment load, and a myriad of constraints imposed by
human land use and articial regulation (Knighton, 1998; Schumm,
2005). The wide-ranging spectrum of river channel controls has led to
a vast literature addressing channel adjustment through space and
time (Gregory, 1977; Hickin, 1983; Brookes, 1994; Gurnell and Petts,
1995), notably for rivers affected by human activities (Park, 1977;
Simon, 1989; Gregory, 2006; James et al., 2009a). The implications of
river channel changes to economic development, human health, and
ecological condition are substantial, and include increased ood risk
(Shankman and Samson, 1991; Poesen and Hooke, 1997; Criss and
Tel.: +1 601 266 5423; fax: +1 601 266 6219.
E-mail address: Franklin.Heitmuller@usm.edu.
0169-555X/$ see front matter 2013 Elsevier B.V. All rights reserved.
http://dx.doi.org/10.1016/j.geomorph.2013.08.020
Shock, 2001; Stover and Montgomery, 2001), aquatic and riparian habitat degradation (Petts, 1987; Brookes, 1994; Annear et al., 2004; Steiger
et al., 2005), and minimized nutrient and contaminant sequestration
(Bukaveckas, 2007; Hupp et al., 2009), among others. Knowledge about
modes of adjustment, rates of change, and the physical mechanisms responsible for change is useful to formulate strategies for channel rehabilitation (Kondolf and Larson, 1995; Tiegs and Pohl, 2005), manage uvial
systems (Brierley and Fryirs, 2005; Gregory et al., 2008), engineer or
mitigate problematic reaches (Patrick et al., 1982; Gilvear, 1999), and
possibly predict channel form (Hooke and Redmond, 1989).
1.1. Channel change concepts
River channel changes are induced by pulse- or ramp-style disturbances (Brunsden and Thornes, 1979), in which the former are characterized by brief, high magnitude events (e.g., 100-year oods) that are
usually followed by a period of recovery (Gupta and Fox, 1974; Pitlick
and Thorne, 1987) and the latter constitute an enduring change to
383
384
Fig. 1. Map of U.S. Geological Survey (USGS) streamow-gauging stations assessed for historical channel adjustments and hydrology along the lower Brazos and Sabine Rivers in the southcentral USA.
The earliest major regulation along the Brazos River upstream of the
study area is Possum Kingdom Lake, impounded in 1941, but the creation of Lake Whitney in 1951 resulted in substantial declines in water
volumes to Waco. Since 1951, the mean daily discharge at Waco has
slightly decreased from 73 to 63 m3/s (Table 1), whereas a considerable
385
Table 1
Hydrologic data (period of record through February 2008) for the lower Brazos River and selected tributaries and the lower Sabine River, Texas, USA. [Q, discharge; m3/s, cubic meters per
second].
USGS
streamow-gauging
station
Period of record
Major regulating
reservoir and date
of impoundment
Pre-regulation
daily mean
Q (m3/s)
Post-regulation
daily mean
Q (m3/s)
131
163
24.4
776
960
23.7
194
198
2.1
1050
1030
1.9
238
232
2.5
1230
1180
4.1
Toledo Bend
Reservoir;
Oct. 3, 1966
Toledo Bend
Reservoir;
Oct. 3, 1966
Toledo Bend
Reservoir;
Oct. 3, 1966
Lake Whitney;
Dec. 5, 1951
Belton Lake;
Mar. 8, 1954
Lake Whitney;
Dec. 5, 1951
73
63
13.7
1810
813
55.1
50
51
2.0
1590
838
47.3
159
144
9.4
2160
1440
33.3
12
12
473
501
5.9
15
17
13.3
378
494
30.7
210
197
6.2
1940
1480
23.7
218
213
2.3
1790
1480
17.3
08110500 Navasota
River near Easterly
08111000 Navasota
River near Bryanb
08111500 Brazos River
near Hempstead
08114000 Brazos River
at Richmond
a
b
Lake Limestone;
Oct. 16, 1978
Lake Limestone;
Oct. 16, 1978
Lake Whitney;
Dec. 5, 1951
Lake Whitney;
Dec. 5, 1951
Percent
difference
(daily mean Q)
Pre-regulation
mean annual
maximum
Q (m3/s)
Post-regulation
mean annual
maximum
Q (m3/s)
Percent difference
(mean annual
maximum Q)
Period of record combined with 08108700 Brazos River at State Highway 21 near Bryan and applied to post-impoundment statistics.
Period of record combined with 08110800 Navasota River at Old Spanish Road near Bryan and applied to post-impoundment statistics.
decrease of the mean annual peak discharge from 1810 to 813 m3/s reects ood control. Downstream of Waco, the Brazos River has three
important tributaries, the Little River (19,710 km2), Yegua Creek
(3440 km2), and the Navasota River (5850 km2). Although the lower
Brazos River is not interrupted by a reservoir, the three tributaries are
extensively impounded. Following the 1954 closure of Belton Lake for
ood control, the mean daily discharge of the Little River at Cameron
remained the same (50 m3/s), whereas the mean annual peak discharge
was reduced by over 47%. In addition to Belton Lake, three other oodcontrol reservoirs have been created in the Little River subbasin since
1954 and have decreased ooding. The Robinson Dam that created
Lake Limestone on the Navasota River in 1978 was not designed for
ood control. Subsequent to its construction, the mean daily discharge
of the Navasota River near Bryan increased by 2 m3/s while the mean
annual peak discharge increased by 30.7%, the latter explained by inclusion of drought years in the 1950s. Further downstream, the mean daily
discharge of the Brazos River at Richmond mostly remains unaffected by
upstream regulations, although a 17.3% reduction in mean annual peak
discharge after 1951 reects upstream ood-control reservoirs.
The lower Brazos River basin extends through three level III
ecoregions (Grifth et al., 2004): (i) Texas Blackland Prairies, (ii) Eastcentral Texas Plains, and (iii) Western Gulf Coastal Plain. These
ecoregions support a natural mix of open grasslands, savanna-type
oak woodlands, and coastal marsh. Most of the grasslands have been
converted to rangeland and agricultural elds in the basin; and areas
of urbanization include the Waco, BryanCollege Station, and Houston
metropolitan areas. Direct anthropogenic impacts on the river include
instream sand mining documented between Hempstead and Rosharon
(Dunn and Raines, 2001) and dredging associated with a shipping channel constructed in 1929 at Freeport, which diverts all streamow away
from the former river mouth.
2.2. Lower Sabine River
The lower Sabine River ows ~225 km from Toledo Bend Reservoir to
Sabine Lake, a Gulf Coast estuary. Dimensionless slope of the sand-bed
386
Table 2
Summary of time periods for cross-sectional and planform data used to analyze historical channel geometry along the lower Brazos and Sabine Rivers in Texas and Louisiana, USA.
USGS streamow-gauging station
Period(s) of cross-sectional
data used in this study
Year of contemporary
orthoimagery
Sept. 1955present
Oct. 1923present
Oct. 1924present
Oct. 1898present
Oct. 1965present
Aug. 1899Dec. 1902;
Mar. 1918Dec. 1925;
July 1926present
Oct. 1938present
Jan. 1903June 1906;
Oct. 1922present
April 1967present
19562001
19322005
19601999
19252002
19722004
19612007
2006
2006
2006
2004
2005
2006
a
a
1981
1960
1957
19391960; 19802000
19341958; 19861998
1952
2006
2005
19672000
1958
2005
387
12
974'W
973'30"W
973'W
EXPLANATION
08096500
Brazos River at Waco
gauging station
1981
2004
TX
Lo
op
34
0
11
3131'30"N
3132'N
A 974'30"W
To
Washington
Street & La
Salle Avenue
Bridges
Flow direction
A
UTM Zone 14N
NAD 1983
250
500
750
1,000 METERS
10
9
2-YEAR RETURN PERIOD (18991951) (1,440 m3/s)
APPROXIMATE STAGE IN 1925
8
7
6
5
BRIDGE
4
5/9/1925
9/30/1936
4/26/1942
5/18/1949
10/5/1959
5/4/1966
3
2
1
0
200
INITIAL CHANNEL-BED
AGGRADATION;
SUBSEQUENT INCISION
175
150
125
100
75
50
25
10
BANK EROSION
5
4
3
2
1
0
-1
-2
-3
-4
50
BRIDGE
11/11/1971
4/20/1977
10/21/1981
3/17/1998
2/20/2001
5/30/2002
INITIAL CHANNEL-BED
AGGRADATION;
SUBSEQUENT INCISION
9
8
7
2-YEAR RETURN PERIOD (1952PRESENT) (650 m3/s)
6
5
4
BANK
ACCRETION
3
2
BRIDGE
12/24/1986
6/13/1987
6/21/1989
12/28/1991
4/24/1995
CHANNEL-BED
INCISION
-1
-2
75
100
125
150
175
200
22
250
25
50
75
100
125
150
175
200
Fig. 2. Summary of historical channel adjustments for the Brazos River at Waco (USGS 08096500). (A) Planform adjustments downstream of the Loop 340 bridge (19812004). (B) Crosssectional adjustments at the Washington Avenue bridge (19251966). (C) Cross-sectional adjustments at the La Salle Avenue bridge (19712002). (D) Cross-sectional adjustments at the
Loop 340 bridge (19861995).
388
3
FM 1
EXPLANATION
1960
2005
318'N
73
08098290
Brazos River
near Highbank
gauging station
FM
41
Flow direction
317'N
A 9631'W
9629'W
9630'W
EXPLANATION
1957
2006
Flow direction
3037'N
B
NATIONAL WEATHER SERVICE FLOOD STAGE (10.67 m)
2-YEAR RETURN PERIOD (1966PRESENT) (752 m3/s) (5.30 m)
F
E
08109000
Brazos River near Bryan
gauging station
1/11/1972
2/3/1975
6/29/1976
6/3/1986
6/5/1987
3/31/1993
2/19/1997
2/20/2001
4/28/2004
CHANNEL-BED
INCISION
25
50
75
100
125
150
175
12
200
-1
0
BRIDGE
11
10
9
8
7
BANK
EROSION
6
5
BANK
ACCRETION
CABLEWAY
1/10/1961
5/3/1962
2/27/1968
6/19/1973
11/6/1974
2/25/1977
5/22/1985
6/15/1987
2
1
0
-1
THALWEG
INCISION
-2
-3
-4
25
50
75
100
125
150
175
200
12
11
2-YEAR RETURN PERIOD (1952PRESENT) (1,190 m3/s)
10
9
8
7
6
5
BRIDGE
4
3
6/16/1992
7/7/1993
10/7/1998
12/28/2000
3/4/2004
5/29/2007
2
1
0
-1
-2
40 50
HIGH-FLOW
SCOUR
75
100
125
150
175
200
225
240
9611'W
during high ows. The limited amount of bed incision, despite being an
easily erodible substrate as evidenced by scour-and-ll behavior, is
explained by sediment supply from (i) moderate rates of channel migration in the area and (ii) progressive channel-bed degradation of the Little
River (Heitmuller and Greene, 2009), a major upstream tributary that has
delivered additional sediment to the reach. Therefore, the Brazos River
from Bryan to downstream locations is presently insulated from the reduction of sediment loads by reservoirs upstream.
4.1.4. Brazos River near Hempstead
The Brazos River near Hempstead gauge (08111500) (88,870 km2)
has a long period of record (1938present), although measurement locations have frequently changed. In 1949, the measurement location
was moved from a bridge to a nearby cableway. Measurements were
re-located again in 1974 following construction of a new bridge. Other
complications with continuity result from measurements made from
both the upstream and downstream sides of the 1974 bridge. Additionally, eld measurement data for the 1960s and 1970s were not obtained.
Cross sections between 1939 and 1949 indicate substantial adjustments, including simultaneous right-bank accretion (3 m) and about
2.5 m of thalweg incision on the left side of the channel (Fig. 5B). In addition to the incision, the lower section of the left channel bank
retreated by about 35 m while the upper part accreted about 15 m,
resulting in an increasingly steep terrace scarp. The rapid nature of
right bank accretion combined with the near-vertical dropoff to the
thalweg indicates an articial origin, such as stabilization efforts along
9610'W
EXPLANATION
308'N
309'N
2006
US 290
08111500
Brazos River
near Hempstead
gauging station
307'N
Flow direction
400
389
14
13
12
11
10
9
8
7
6
5
4
3
2
1
0
-1
-2
-3
-4
100
UPPER BANK
ACCRETION
BANK
ACCRETION
(ARTIFICIAL?)
LOWER BANK
EROSION
HINGEPOINT?
BANK
ACCRETION
(ARTIFICIAL?)
BRIDGE
THALWEG INCISION
1/14/1939
12/2/1940
10/8/1945
3/13/1946
5/21/1949
125
ADDITIONAL
INCISION?;
HIGH-FLOW
SCOUR?
150
175
200
225
250
275
300
14
13
12
11
10
9
8
7
6
5
4
3
2
1
BANK
ACCRETION
CABLEWAY
0
-1
-2
-3
-4
25
2/13/1950
6/13/1950
5/5/1956
5/14/1956
10/8/1959
2/1/1960
50
INITIAL THALWEG
AGGRADATION;
SUBSEQUENT INCISION
75
100
125
150
175
200
225
14
13
12
11
10
9
8
7
6
5
4
3
2
1
0
-1
-2
-3
-4
100
BANK
ACCRETION
BRIDGE
2/13/1980
6/17/1981
1/9/1985
6/17/1987
11/6/2000
THALWEG
INCISION
HINGEPOINT
125
150
175
200
225
250
275
300
Fig. 5. Summary of historical channel adjustments for the Brazos River near Hempstead (USGS 08111500). (A) Map of the channel near the gauging station (2006 position). (B) Crosssectional adjustments at the old bridge (19391949). (C) Cross-sectional adjustments at the cableway immediately upstream of the bridge (19501960). (D) Cross-sectional adjustments
at the new bridge (19802000).
9547'W
9546'W
9545'W
9544'W
EXPLANATION
1952
2936'N
2005
Flow direction
ad
ilro
Ra
H
US
2935'N
08114000
Brazos River
at Richmond
gauging station
90
16
the right margin of the thalweg. Hydraulic forces during high ows
were concentrated in a smaller cross-sectional area, resulting in incision
into the erodible sandy bed and lower left bank erosion. Cross sections
between 1950 and 1960 show an initial phase of thalweg aggradation
(2 m) followed by incision (2.5 m) to a slightly lower elevation, which
is complemented by erosion of the lower left bank and 2 m of upper
left bank accretion (Fig. 5C). Finally, cross sections between 1980 and
2000 indicate a well-developed hingepoint separating 1.5 m of thalweg
incision and 2.5 m of vertical accretion on the right bank (Fig. 5D).
Articial reinforcement of the right bank has prevented its erosion
and likely promoted thalweg incision.
As a supplement to these data, historical ground photos from 1975
were compared to repeat photos from 2008. Although not as obvious
here as upstream near Highbank and Bryan, the photos generally
show denser vegetation along the channel banks and adjacent oodplain surfaces.
Despite the discontinuities at this station, some interpretations can
be made. Articial modications to the right bank in the 1940s resulted
in a substantial shift in cross-sectional shape. Subsequently, channelbed aggradation along the cableway transect in the early- and mid1950s coincided with a severe drought in central Texas. Reduced high
ows, coupled with extensive riparian clearance during this period
(Dunn and Raines, 2001; Heitmuller and Greene, 2009), resulted in sediment accumulations in the channel. In May 1957, the drought ended
with the largest ood on record at this station (4050 m3/s), which evacuated the excessive channel-bed material. Finally, the progressive
thalweg degradation since 1980 is probably related to instream sand
and gravel extraction activities reported between Hempstead and
Rosharon (Dunn and Raines, 2001). In other alluvial rivers, instream
mining has resulted in severe channel degradation and upstream propagation of erosional knickpoints (Kondolf, 1994; Rinaldi et al., 2005).
A hingepoint separating bed incision from bank accretion occurs on
the convex side of the meander bend (Fig. 5B and D). The following
sequence is hypothesized during moderate and high ows: (i) the deepened thalweg destabilizes the lowermost, submerged point bar resulting
in its erosion; (ii) the increase in available cross-sectional area further
isolates the upper point-bar surface from erosive, high velocity ows
during bankfull or overbank events; and (iii) bank accretion ensues. Alternatively, vegetation encroachment on the point bar would promote
accretion, thus constraining ow width and resulting in thalweg incision.
There also exists the possibility that a ow-separation zone near the
upper point bar could exacerbate sediment deposition along its surface
(Nanson and Page, 1983). Irrespective of these hypothesized dynamics,
additional examples provided below indicate that hingepoints develop
at meander bends.
15
14
13
12
11
1/23/1934
5/25/1935
5/23/1947
2/2/1948
10/21/1955
5/5/1957
10
9
CABLEWAY
LOWER BANK
ACCRETION (BENCH
DEVELOPMENT)
HINGEPOINT
6
5
4
INITIAL THALWEG
AGGRADATION;
SUBSEQUENT INCISION
3
2
1
0
200
BANK
EROSION
175
150
125
100
75
50
25
390
12
11
UPPER BANK
ACCRETION
10
9
8
8/13/1957
2/26/1958
6/19/1986
1/15/1991
2/23/1993
2/12/1998
BRIDGE
7
6
5
4
3
2
1
0
-1
-2
-3
150
CHANNEL-BED INCISION
BANK EROSION;
SUBSEQUENT ARTIFICIAL
REINFORCEMENT
175
20
225
250
275
300
325
350
migrated, the extended reach exhibits planform stability. As a supplement to these data, historical ground photos from May and August
1965 were compared to repeat photos from 2008. In general, additional
rip-rap reinforcement on the right bank and slightly more vegetated
oodplains are detected in the 2008 photos.
The cross-sectional adjustments occurring at Richmond are not
easily interpreted because the 1960s and 1970s are not represented
and articial bank-stabilization efforts interrupt any progressive trajectory of change. The development of low bank deposits was separated
from the thalweg by a subtle hingepoint that developed in the 1940s
and 1950s, and vertical point-bar accretion occurred since 1952 at
391
9535'W
9534'W
EXPLANATION
1958
2005
2921'N
FM 1462
J
08116650
Brazos River
near Rosharon
gauging station
2920'N
Flow direction
16
15
14
13
12
11
10
9
8
7
6
5
4
3
2
1
0
-1
-2
-3
-4
25
HINGEPOINT
BRIDGE
5/19/1967
7/2/1975
7/27/1976
5/16/1985
6/18/1986
1/31/1997
11/9/2000
50
THALWEG INCISION;
SHIFT TO LEFT
75
100
125
150
175
200
225
EXPLANATION
9337'W
314'N
2006
TX 6
9336'W
3046'N
9332'W
EXPLANATION
3045'N
392
08028500
Sabine River
near Bon Wier
gauging station
2006
08026000
Sabine River
near Burkeville
gauging station
Flow direction
313'N
US 190
Railroad
Flow direction
11
10
2-YEAR RETURN PERIOD (1956PRESENT) (724 m3/s)
11
9
BANK
EROSION
8
7
BRIDGE
HINGEPOINT
5
4
THALWEG
INCISION
INITIAL POINT-BAR
ACCRETION;
SUBSEQUENT
EROSION
3
2
100
125
150
175
200
225
250
2/8/1956
5/16/1963
5/12/1966
2/27/1980
1/7/1986
11/9/1994
1/27/1995
1/10/2001
275
300
12
3044'N
Fig. 8. Summary of historical channel adjustments for the Sabine River near Burkeville
(USGS 08026000). (A) Map of the channel near the gauging station (2006 position).
(B) Cross-sectional adjustments at the measurement location (19562001).
10
10/22/1957
1/14/1961
4/26/1966
6/22/1976
1/14/1932
4/30/1933
8/12/1940
1/16/1943
6/5/1952
8
7
6
BANK
EROSION
BRIDGE
5
4
INITIAL POINTBAR EROSION;
SUBSEQUENT
ACCRETION
3
2
1
0
INITIAL THALWEG
AGGRADATION;
SUBSEQUENT INCISION
-1
200
175
CHUTE CHANNEL
DEVELOPMENT;
SUBSEQUENT INFILLING
HINGEPOINT
150
125
100
75
50
25
9
8
ARTIFICIAL BANK
REINFORCEMENT
6
5
4
3
2
BRIDGE
HINGEPOINT?
1
0
2/15/1984
12/2/1986
1/15/1991
8/30/1994
1/15/2003
2/1/2005
INITIAL THALWEG
AGGRADATION;
SUBSEQUENT INCISION
-1
HIGH-FLOW
SCOUR
-2
-3
0
25
50
75
100
125
150
175
200
and 1979 indicate minor bed adjustments and an aggradational trajectory (1 m) (Fig. 10B). Cross sections of the Indian River distributary between 1976 and 1999 also show minor bed adjustments, with an initial
aggradational phase (b 1 m) nullied by subsequent incision (Fig. 10C).
393
3018'N
9345'W
9344'W
9343'W
9342'W
08030500
Sabine River
near Ruliff
gauging station
TX
EXPLANATION
2006
12
3017'N
Flow direction
Old River
Indian Bayou
10
6
5
4
3
BRIDGE
2
1
11/30/1960
1/11/1961
4/27/1966
12/8/1971
4/24/1979
0
-1
THALWEG AGGRADATION
-2
0
20
40
60
80
100
6
5
4
INITIAL CHANNEL-BED
AGGRADATION;
SUBSEQUENT INCISION
BOAT
8/5/1976
4/8/1977
2/26/1980
1/28/1985
6/7/1994
3/20/1995
6/2/1999
2
1
0
-1
10
-2
0
20
40
60
80
100
8/5/1976
4/8/1977
2/26/1980
1/28/1985
6/7/1994
3/20/1995
6/2/1999
BOAT
7
6
5
2
1
0
-1
INITIAL CHANNEL-BED
AGGRADATION;
SUBSEQUENT INCISION
-2
-3
-4
20
40
60
80
100
Fig. 10. Summary of historical channel adjustments for the Sabine River near Ruliff (USGS 08030500). (A) Map of the channel near the gauging station (2006 position). (B) Cross-sectional
adjustments at the bridge (19601979). (C) Cross-sectional adjustments at Indian Bayou (19761999). (D) Cross-sectional adjustments at Old River (19761999).
which included climatic extremes (e.g., 1930s Dust Bowl in the uppermost Brazos basin), agricultural expansion, urban-core development,
and ow-regulation infrastructure amidst few environmental impact
regulations. Presently, these conditions are not uncommon in many developing countries, thus much can be learned about predicting channel
adjustments to those activities from archival sources in previously
impacted areas. To a reasonable extent, limited historical data can
be remediated through analysis of hydrographic measurements at
long-term streamow-gauging stations (Juracek and Fitzpatrick,
2008), one of the great benets being an opportunity to render cross
sections to complement planform data. Although isolated to a limited
channel reach, historical trajectories of change can be inferred if site
characteristics (e.g., meander bend and bridge-dependent hydraulics)
are considered.
In this study, streamow-measurement data prior to 1950 were
used to analyze cross-sectional adjustments at four gauging stations
(Fig. 11). If a personal visit to the National Archives in Fort Worth had
been afforded, additional records possibly could have been located for
the Brazos River near Bryan and the Sabine River near Ruliff to further
extend their histories. The Brazos River at Waco aggraded from the
mid-1920s to the early 1940s, after which high ows reincised the
channel bed (Fig. 2B). Extremely arid conditions that affected the Brazos
River included two days of zero ow in August 1918 and several days in
August 1923, but the 1925 cross section is not aggraded. Effects of the
arid Dust Bowl event during the 1930s are largely conned to the uppermost drainage basin, much of which contributes to enclosed playa
depressions. Therefore, sediment contributions from the affected area
394
Waco
BRAZOS RIVER
D
A
Highbank
D
A
Bank
Bed
???
D
D
A
Minor adjustments
D
A
D
SABINE RIVER
1920
1930
1940
Bed
Lower bank
Bed
Lower bank
A
D
A
1950
Bryan
Bank
Bed
Bank
Bed
Bank
Bed
1960
1970
1980
1990
2000
Rosharon
2010
Bon Wier
???
A Aggradation / Accretion
Richmond
Burkeville
D
A
Hempstead
Ruliff
D Degradation / Erosion
Fig. 11. Summary of historical aggradation (accretion) and degradation (erosion) processes along the lower Brazos and Sabine Rivers. For each gauging station, a thin horizontal line
representing channel stability separates aggradation from degradation, such that more pronounced channel adjustments are more distant from the stability reference line.
to the middle Brazos River are probably limited to atmospheric deposition of ne-grained particulates that would have been easily ushed
downstream by a series of relatively high ows between 1930 and
1938, notably the peak recorded discharge of 6970 m3/s in 1936. The
aggradational period is thus attributed to those oods coupled with
land use practices in the watershed and the aforementioned dam construction for Lake Waco. Land use in this region during the 1930s was
mostly associated with cotton agriculture, and land-conservation practices were largely ignored. The native grassland cover was depleted
(Worster, 2013), and crop yields were bolstered by mechanized
plowing (Dethloff and Nall, 2013). Thus, the stage was set for delivery
of substantial sediment to the channel network during the storm events
of the 1930s, especially when combined with sediment derived from
dam site excavation and possibly urban development. If not for three
high peak ows in the early 1940s coupled with mandates for soil conservation practices following the Dust Bowl, the aggradational period at
Waco might have been more enduring.
The Brazos River near Hempstead and at Richmond was also examined for cross-sectional adjustments prior to 1950 (Fig. 11); however
both stations show variable responses, and localized factors complicate
addressing wholescale changes in environmental conditions. The channel near Hempstead underwent a period of channel narrowing and
deepening (Fig. 5B), which probably resulted from articial lling of
the right channel bank. At Richmond (Fig. 6B), minor bed aggradation
and incision episodes likely resulted from passage of a small sediment
slug derived from unknown sources. A fundamental difference between
Hempstead and Richmond is that accretion occurred along the upper
left bank in the former, while it occurred along the lower left bank in
the latter. As such, the vertical position of the hingepoint occurs at different stage levels.
Finally, the Sabine River near Bon Wier conveyed a large sediment
slug during the 1930s (Fig. 11) that ultimately widened the channel
and temporarily obliterated cross-sectional asymmetry normally
expected at a meander bend (Fig. 9B). Annual peak streamow during
this period was neither abnormally high nor low, ranging from
643 m3/s in 1937 to 2060 m3/s in 1935. Therefore, ood- or droughtrelated sedimentation is not likely the cause. Two possibilities are likely,
both related to the timber industry: (i) regional-scale logging and associated hillslope erosion or (ii) local-scale mill activities. The rst possibility is the downstream translation of a large sediment slug derived
from logged, barren hillslopes in the drainage basin. The logging industry in east Texas experienced a bonanza between the 1880s and 1920s
(Maxwell and Baker, 1983), and environmentally destructive skid trails
were made by dragging large logs across the ground surface. In the
(Fig. 5BD), at Richmond (Fig. 6BC), and near Rosharon (Fig. 7B). The
Sabine River channel near Burkeville (Fig. 8B) is also incised. At Waco,
the stage associated with the 2-year return period is about 2.5 m
lower than the National Weather Service (NWS) ood stage, which is
equaled or exceeded once every 5 years on average. Near Highbank,
the 2-year ow stage is more than 5 m lower than ood stage. Near
Hempstead, the 2-year ow stage is more than 4 m lower than ood
stage, and the channel at Richmond conveys the 2-year ow at a stage
that is more than 3.5 m lower than ood stage. Of all the Brazos River
sites, Rosharon has the closest association between ood stage and the
2-year stage, which is only 1 m lower. Finally, the Sabine River near
Burkeville has a 2-year ow stage that is more than 3.5 m lower than
ood stage, whereas the downstream station near Bon Wier has similar
bankfull and 2-year ow stages (Fig. 9BC). Deltaic aggradation is apparent near Ruliff (Fig. 10BD) where the 2-year ow exceeds ood
stage by about 0.8 m.
In large part, the inability of 2-year return period ows to ll the
bankfull channel along the Brazos River is because of ood regulation
by upstream reservoirs (Table 1). For example, the 2-year ow at
Waco declined from 1440 m3/s before 1952 to 650 m3/s thereafter.
Similarly, the 2-year ow near Bryan declined from 1930 m3/s before
1952 to 1190 m3/s thereafter. Thus, the reduced peak ows are conveyed in a channel previously established by a natural ood regime
and, at some stations, bed incision resulting from reduced sediment
loads exacerbates the disparity between bankfull stage and the 2-year
return period.
At some sites along the Brazos River, lateral and vertical bank accretion mechanisms have served to reestablish a morphologic indicator of
the 1- to 2-year return period for the regulated ow regime. At Texas
Loop 340 at Waco (Fig. 2B), a sediment bench ~10 m wide has vertically
accreted more than 2 m as it approached the 1.5-year ow stage. At the
discontinued station near Bryan (Fig. 4B), a sediment bench ~20 m
wide has vertically accreted more than 3 m to exceed the 1.1-year
ow stage. Bank accretion mechanisms are also apparent near Hempstead, notably between 1980 and 2000 (Fig. 5D) when a sediment
bench approximately 20 m wide vertically accreted about 3 m as it
approached the 1.5-year ow stage. The left channel bank at Richmond
has gradually accreted (Fig. 6C), although a vertical limit is not detectable in the data set. Finally, the left bank near Rosharon (Fig. 7B) has laterally accreted more than 25 m with an undetectable vertical limit. At
all sites, bank accretion occurred contemporaneously with bed incision,
which nullies wholescale aggradation by increased sediment loads as
an explanatory mechanism. The progressive and gradual growth of
bank accretion deposits spanning one or more decades precludes their
association with relatively short-term events, such as drought-related
benches documented on smaller streams (e.g., Royall et al., 2010).
One complicating factor for interpreting bank accretion along the
lower Brazos River concerns vegetation encroachment. As evidenced
by ground and aerial photos from the 1950s and 1960s, vegetation
was commonly removed along the banks. The concomitant decrease
in channel roughness and exposure of bank sediments would result in
a wider channel relative to that of a naturally vegetated condition. As riparian vegetation growth increased since the 1950s concurrent with
ood regulation, bank sedimentation ensued. Whether the accretion is
more strongly associated with reduced ooding, vegetation encroachment, or the degree to which both contributed is subject to debate.
6. Conclusions
This investigation of historical channel adjustments along two coastal plain rivers reveals several mechanisms and styles of change that operate independently of one another across space and time. Distinctions
can be drawn between (i) upstream- and downstream-propagating disturbances and (ii) pulse- and ramp-style disturbances. Downstreampropagating disturbances are the most commonly identied in the literature, and several are identied. Channel-bed incision along the Brazos
395
396
Dunn, D.D., Raines, T.H., 2001. Indications and potential sources of change in sand transport in the Brazos River, Texas. U.S. Geological Survey Water-Resources Investigations
Report 01-4057, Austin, TX.
Everitt, B., 1993. Channel responses to declining ow on the Rio Grande between Ft.
Quitman and Presidio, Texas. Geomorphology 6 (3), 225242.
Fitzpatrick, F.A., Knox, J.C., Schubauer-Berigan, J.P., 2009. Channel, oodplain, and wetland
responses to oods and overbank sedimentation, 18462006, Halfway Creek Marsh,
Upper Mississippi Valley, Wisconsin. In: James, L.A., Rathburn, S.L., Whittecar, G.R.
(Eds.), Management and restoration of uvial systems with broad historical changes
and human impacts. Geological Society of America Special Paper, 451, pp. 2342
(Boulder, CO).
Flynn, K.M., Kirby, W.H., Hummel, P.R., 2006. User's manual for program PeakFQ, annual
ood frequency analysis using bulletin 17B guidelines. U.S. Geological Survey Techniques and Methods Book, 4 (Chapter B4, Reston, VA).
Frankl, A., Nyssen, J., De Dapper, M., Haile, M., Billi, P., Munro, R.N., Deckers, J., Poesen, J.,
2011. Linking long-term gully and river channel dynamics to environmental change
using repeat photography (northern Ethiopia). Geomorphology 129 (34), 238251.
Fuller, I.C., 2007. Geomorphic work during a 150-year storm: contrasting behaviors of
river channels in a New Zealand catchment. Ann. Assoc. Am. Geogr. 97 (4), 665676.
Fuller, I.C., 2008. Geomorphic impacts of a 100-year ood: Kiwitea Stream, Manawatu
catchment, New Zealand. Geomorphology 98 (12), 8495.
Gillespie, B.M., Giardino, J.R., 1997. The nature of channel planform change: Brazos River,
Texas. Tex. J. Sci. 49 (2), 109142.
Gilvear, D.J., 1999. Fluvial geomorphology and river engineering: future roles utilizing a
uvial hydrosystems framework. Geomorphology 31 (14), 229245.
Gilvear, D.J., Harrison, D.J., 1991. Channel change and the signicance of oodplain stratigraphy: 1990 ood event, lower River Tay, Scotland. Earth Surf. Process. Landforms 16
(8), 753761.
Goff, J.R., Ashmore, P., 1994. Gravel transport and morphological change in braided
Sunwapta River, Alberta, Canada. Earth Surf. Process. Landforms 19 (3), 195212.
Gomez, B., Coleman, S.E., Sy, V.W.K., Peacock, D.H., Kent, M., 2007. Channel change,
bankfull and effective discharges on a vertically accreting, meandering, gravel-bed
river. Earth Surf. Process. Landforms 32 (5), 770785.
Goswami, U., Sarma, J.N., Patgiri, A.D., 1999. River channel changes of the Subansiri in
Assam, India. Geomorphology 30 (3), 227244.
Graf, W.L., 2001. Damage control: dams and the physical integrity of America's rivers.
Ann. Assoc. Am. Geogr. 91 (1), 127.
Graf, W.L., 2006. Downstream hydrologic and geomorphic effects of large dams on
American rivers. Geomorphology 79 (34), 336360.
Gregory, K.J., 1977. The context of river channel changes. In: Gregory, K.J. (Ed.), River
Channel Changes. Wiley, Chichester, UK, pp. 112.
Gregory, K.J., 2006. The human role in changing river channels. Geomorphology 79 (34),
172191.
Gregory, K.J., Benito, G., Downs, P.W., 2008. Applying uvial geomorphology to river
channel management: background for progress towards a palaeohydrology protocol.
Geomorphology 98 (12), 153172.
Grifth, G.E., Bryce, S.A., Omernik, J.M., Comstock, J.A., Rogers, A.C., Harrison, B., Hatch, S.L.,
Bezanson, D., 2004. Ecoregions of Texas (map). U.S. Geological Survey, Reston, VA.
Gupta, A., Fox, H., 1974. Effects of high-magnitude oods on channel form: a case study in
Maryland Piedmont. Water Resour. Res. 10 (3), 499509.
Gurnell, A., Petts, G. (Eds.), 1995. Changing River Channels. Wiley, Chichester, UK.
Harbor, D.J., Schumm, S.A., Harvey, M.D., 1994. Tectonic control of the Indus River in Sindh,
Pakistan. In: Schumm, S.A., Winkley, B.R. (Eds.), The Variability of Large Alluvial Rivers.
American Association of Civil Engineers Press, New York, pp. 161176.
Heitmuller, F.T., 2011. Utility of USGS streamow-gaging station records to assess historical geomorphic adjustments along the lower Brazos and Sabine Rivers, Texas and
Louisiana, USA. Geol. Soc. Am. Abstr. Programs 43 (3), 46.
Heitmuller, F.T., Greene, L.E., 2009. Historical channel adjustment and estimates of selected
hydraulic values in the Lower Sabine River and Lower Brazos River Basins, Texas and
Louisiana. U.S. Geological Survey Scientic Investigations Report 2009-5174 (Austin, TX).
Heo, J., Duc, T.A., Cho, H.S., Choi, S.U., 2009. Characterization and prediction of meandering
channel migration in the GIS environment: a case study of the Sabine River in the
USA. Environ. Monit. Assess. 152 (14), 155165.
Hickin, E.J., 1983. River channel changes: retrospect and prospect. In: Collinson, J.D.,
Lewin, J. (Eds.), Modern and ancient uvial systems. International Association of
Sedimentologists Special Publication, 6. Blackwell, Oxford, UK, pp. 6183.
Hickman, N.W., 1962. Mississippi Harvest: Lumbering in the Longleaf Pine Belt, 1840
1915. University Press of Mississippi, Jackson, MS.
Hooke, J.M., Redmond, C.E., 1989. Use of cartographic sources for analysing river channel
change with examples from Britain. In: Petts, G.E. (Ed.), Historical Change of Large
Alluvial Rivers: Western Europe. Wiley, Chichester, UK, pp. 7993.
Hudson, P.F., Heitmuller, F.T., 2008. Rivers and landscapes of the Texas Gulf Coastal Plain.
Southwest. Geogr. 12, 90123.
Hupp, C.R., Pierce, A.R., Noe, G.B., 2009. Floodplain geomorphic processes and environmental impacts of human alteration along coastal plain rivers, USA. Wetlands 29
(2), 413429.
Jacobson, R.B., Gran, K.B., 1999. Gravel sediment routing from widespread, low-intensity
landscape disturbance, Current River basin, Missouri. Earth Surf. Process. Landforms
24 (10), 897917.
James, L.A., 1991. Incision and morphologic evolution of an alluvial channel recovering
from hydraulic mining sediment. Geol. Soc. Am. Bull. 103 (6), 723736.
James, L.A., Rathburn, S.L., Whittecar, G.R., 2009a. Introduction: managing rivers with
broad historical changes and human impacts. In: James, L.A., Rathburn, S.L.,
Whittecar, G.R. (Eds.), Management and restoration of uvial systems with broad historical changes and human impacts. Geological Society of America Special Paper, 451,
pp. vx (Boulder, CO).
397
Phillips, J.D., Slattery, M.C., 2008. Antecedent alluvial morphology and sea-level controls
on formprocess transition zones in the lower Trinity River, Texas. River Res. Appl.
24 (3), 293309.
Phillips, J.D., Slattery, M.C., Musselman, Z.A., 2005. Channel adjustments of the lower
Trinity River, Texas, downstream of Livingston Dam. Earth Surf. Process. Landforms
30 (11), 14191439.
Pit, P., 2002. Channel evolution of the pre-channelized Danube River in Bratislava,
Slovakia (17121886). Earth Surf. Process. Landforms 27 (4), 369390.
Pitlick, J.C., Thorne, C.R., 1987. Sediment supply, movement and storage in an unstable
gravel-bed river. In: Thorne, C.R., Bathurst, J.C., Hey, R.D. (Eds.), Sediment Transport
in Gravel-bed Rivers. Wiley, Chichester, UK, pp. 151178.
Poesen, J.W.A., Hooke, J.M., 1997. Erosion, ooding, and channel management in
Mediterranean environments of southern Europe. Prog. Phys. Geogr. 21 (2), 157199.
Richards, K., Greenhalgh, C., 1984. River channel change: problems of interpretation
illustrated by the River Derwent, North Yorkshire. Earth Surf. Process. Landforms 9
(2), 175180.
Rinaldi, M., Simon, A., 1998. Bed-level adjustments in the Arno River, central Italy.
Geomorphology 22 (1), 5771.
Rinaldi, M., Wyga, B., Surian, N., 2005. Sediment mining in alluvial channels: physical
effects and management perspectives. River Res. Appl. 21 (7), 805828.
Royall, D., Davis, L., Kimbrow, D.R., 2010. In-channel benches in small watersheds:
examples from the southern Piedmont. Southeast. Geogr. 50 (4), 445467.
Schumm, S.A., 2005. River Variability and Complexity. Cambridge University Press,
Cambridge, UK.
Schumm, S.A., Lichty, R.W., 1965. Time, space, and causality in geomorphology. Am. J. Sci.
263 (2), 110119.
Sear, D.A., Newson, M.D., 2003. Environmental change in river channels: a neglected elementtowards geomorphological typologies, standards, and monitoring. Sci. Total.
Environ. 310 (13), 1723.
Shankman, D., Samson, S.A., 1991. Channelization effects on Obion River ooding, western Tennessee. J. Am. Water Res. Assoc. 27 (2), 247254.
Simon, A., 1989. A model of channel response in disturbed alluvial channels. Earth Surf.
Process. Landforms 14 (1), 1126.
Simon, A., 1992. Energy, time, and channel evolution in catastrophically disturbed uvial
systems. Geomorphology 5 (35), 345372.
Starkel, L., 1995. Changes of river channels in Europe during the Holocene. In: Gurnell, A.,
Petts, G. (Eds.), Changing River Channels. Wiley, Chichester, UK, pp. 2742.
Steiger, J., Tabacchi, E., Dufour, S., Corenblit, D., Peiry, J.L., 2005. Hydrogeomorphic processes affecting riparian habitat within alluvial channeloodplain river systems: a
review for the temperate zone. River Res. Appl. 21 (7), 719737.
Stover, S.C., Montgomery, D.R., 2001. Channel change and ooding, Skokomish River,
Washington. J. Hydrol. 243 (34), 272286.
Surian, N., Rinaldi, M., 2003. Morphological response to river engineering and management in alluvial channels in Italy. Geomorphology 50 (4), 307326.
Surian, N., Rinaldi, M., Pellegrini, L., Audisio, C., Maraga, F., Teruggi, L., Turitto, O., Ziliani, L.,
2009. Channel adjustments in northern and central Italy over the last 200 years. In:
James, L.A., Rathburn, S.L., Whittecar, G.R. (Eds.), Management and restoration of uvial systems with broad historical changes and human impacts. Geological Society of
America Special Paper, 451, pp. 8395 (Boulder, CO).
Swanson, B.J., Meyer, G.A., Coonrod, J.E., 2011. Historical channel narrowing along the Rio
Grande near Albuquerque, New Mexico in response to peak discharge reductions and
engineering: magnitude and uncertainty of change from air photo measurements.
Earth Surf. Process. Landforms 36 (7), 885900.
Sylvia, D.A., Galloway, W.E., 2006. Morphology and stratigraphy of the late Quaternary
lower Brazos valley: implications for paleo-climate, discharge and sediment delivery.
Sediment. Geol. 190 (14), 159175.
Ta, W., Xiao, H., Dong, Z., 2008. Long-term morphodynamic changes of a desert reach of
the Yellow River following upstream large reservoirs' operation. Geomorphology 97
(34), 249259.
Taha, Z.P., Anderson, J.B., 2008. The inuence of valley aggradation and listric normal
faulting on styles of river avulsion: a case study of the Brazos River, Texas, USA. Geomorphology 95 (34), 429448.
Takagi, T., Oguchi, T., Matsumoto, J., Grossman, M.J., Sarker, M.H., Matin, M.A., 2007. Channel braiding and stability of the Brahmaputra River, Bangladesh, since 1967: GIS and
remote sensing analyses. Geomorphology 85 (34), 294305.
Tiegs, S.D., Pohl, M., 2005. Planform channel dynamics of the lower Colorado River:
19762000. Geomorphology 69 (14), 1427.
U.S. Geological Survey (USGS), 2011. National Water Information System. http://
waterdata.usgs.gov/nwis (last accessed 18 June 2011).
U.S. Geological Survey (USGS), 2013. WaterWatch. http://waterwatch.usgs.gov/ (last
accessed 27 June 2013).
Urban, M.A., Rhoads, B.L., 2003. Catastrophic human-induced change in stream-channel
planform and geometry in an agricultural watershed, Illinois, USA. Ann. Assoc. Am.
Geogr. 93 (4), 783796.
Ursic, S.J., 1986. Sediment and forestry practices in the South. Proceedings of the Fourth
Federal Interagency Sedimentation Conference, Las Vegas, NV. Subcommittee on
Sedimentation, pp. 2-282-37 (2006).
Van Steeter, M.M., Pitlick, J., 1998. Geomorphology and endangered sh habitats of the
upper Colorado River1: historic changes in streamow, sediment load, and channel
morphology. Water Resour. Res. 34 (2), 287302.
Van Urt, G., Smit, H., 1989. The Lower Rhine geomorphological changes. In: Petts, G.E.
(Ed.), Historical Change of Large Alluvial Rivers: Western Europe. Wiley, Chichester,
UK, pp. 167182.
Warner, R.F., 2000. Gross channel changes along the Durance River, southern France,
over the last 100 years using cartographic data. Regul. Rivers Res. Manag. 16 (2),
141157.
398
Webb, R.H., Hereford, R., 2010. Historical arroyo formation: documentation of magnitude
and timing of historical changes using repeat photography. In: Webb, R.H., Boyer,
D.E., Turner, R.M. (Eds.), Repeat Photography: Methods and Applications in the
Natural Sciences. Island Press, Washington, DC, pp. 89104.
Wellmeyer, J.L., Slattery, M.C., Phillips, J.D., 2005. Quantifying downstream impacts of
impoundment on ow regime and channel planform, lower Trinity River, Texas. Geomorphology 69 (14), 113.
Williams, G.P., 1978. Bankfull discharge of rivers. Water Resour. Res. 14 (6), 11411154.
Winterbottom, S.J., 2000. Medium and short-term channel planform changes on the
Rivers Tay and Tummel, Scotland. Geomorphology 34 (34), 195208.
Wolman, M.G., 1967. A cycle of sedimentation and erosion in urban river channels. Geogr.
Ann. 49A (24), 385395.
Wooster, R., 2013. Bon Wier, TX. Handbook of Texas Online. Texas State Historical
Association, Austin, TX (http://www.tshaonline.org/handbook/online/articles/
hlb44/, last accessed 29 March 2013).
Worster, D., 2013. Dust Bowl. Handbook of Texas Online. Texas State Historical Association, Austin, TX (http://www.tshaonline.org/handbook/online/articles/ydd01/, last
accessed 26 June 2013).
Zawiejska, J., Wyga, B., 2010. Twentieth-century channel change on the Dunajec River,
southern Poland: patterns, causes, and controls. Geomorphology 117 (34), 234246.