Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
REV
DATE
PURPOSE OF ISSUE
AUTHOR
20-DEC-16
SPONSOR
___________________ ___________________
G. SAENZ
R. DAVES
DESCRIPTION OF CHANGE:
DATE
AUTHORIZED BY:
__________________________________
J. SACHS
PROPRIETARY INFORMATION
This document contains proprietary information belonging to
KBR. It may neither be wholly or partially reproduced
nor be disclosed without the prior
written permission of KBR.
DATE
1. SCOPE:
2. OBJECTIVE:
3. PHILOSOPHY AND APPROACH
4. SCHEDULE REPORTING
5. SCHEDULE ANALYSIS
5A
Critical Path Analysis
5B
Float Analysis
5C
Milestone Analysis
5D
Construction Impact Analysis
6. PROGRESS REPORTING
6A
Engineering Progress
6B
Construction Progress
7. PROGRESS ANALYSIS
8. PROJECT MANAGEMENT REPORTING
8A
Verbal Communication
8B
Formal Communication
9. RISK ELEMENT REVIEW
10. RECORD KEEPING
11. PROJECT COMPLETION REPORTING
Page 2 of 13
Maintain an on going assessment of all activity start and finish dates to determine
if the project is proceeding as planned.
Timely identification of schedule delays and the reasons for the delay.
Facilitate recovery efforts to mitigate negative impacts.
Forecast of major milestone completion dates.
Ensure that EPC reporting effectively plans and tracks deliverables in order to
sustain the construction required dates and predict project completion.
Assess that the physical earned value progress, schedule status, resource
requirements, and trends support the project completion goals.
Page 3 of 13
Page 4 of 13
Page 5 of 13
Page 6 of 13
Page 7 of 13
Piling/Drilled Footings
U/G Piping
U/G Electrical
Major Equipment
Structural Steel
A/G Piping
A/G Electrical
Instrumentation
Painting
Insulation
Hydro testing
Loop Checking
7. Progress Analysis
In general the various progress curves described above should be reviewed in
detailed to verify accuracy and to identify negative trends.
Listed below are guidelines for the routine analysis for each update reporting cycle.
Results should be advised to the Project Management Team with emphasis on the
reasons that progress deviations may be occurring. Communication should
preferably be in written form for record keeping purposes which will later support Job
Close Out reporting and Lessons Learned efforts.
Informal and verbal
communications are still necessary
Page 8 of 13
Page 9 of 13
Page 10 of 13
Keep a copy of the outputs resulting from the First Planner process.
Keep a copy of the major inputs and back up for the development of the
Baseline EPC Work Package Schedule, Detailed Construction Schedule,
Baseline Progress curves, and Basis of Schedule.
Keep a copy of the initially defined Work Packages, Milestone, Chains, and
Work Breakdown Structure.
For each update period, a copy of the resulting Schedule update, progress
update, and monthly Schedule and Progress report should be kept on file.
Files should be kept by the Scheduler for at least one year after project
completion to allow for any follow up study of project execution which may
come up.
Page 11 of 13
Page 12 of 13
Fore cast
Schedule
Date
EPC Start
29-Oct-02
29-Oct-02 A
14-Dec-01
04-Jan-02 A
-21
Mechanical Completion
01-Sep-03
01-Sep-03
Engineering Complete(90%)
28-Jun-02
28-Jun-02
26-Mar-02
08-May-02
-43
MILESTONE DESCRIPTION
Variance
(Days )
Com m ents
GENERAL
ENGINEERING
SYSTEMS
All P&ID's Issued f or Design
CIVIL / STRUCTURAL
First IFC Foundation Dw gs
28-Feb-02
28-Mar-02 A
-28
29-Apr-02
31-May-02
-32
28-Feb-02
20-May-02
-81
17-May-02
13-Jun-02
-27
PIPING DESIGN
First Planning Release
14-Feb-02
22-Feb-02 A
26-Mar-02
08-May-02
-43
-8
26-Apr-02
10-May-02
-14
01-Aug-02
13-Aug-02
-12
03-Jul-02
03-Jul-02
02-Jul-02
02-Jul-02
26-Aug-02
16-Sep-02
-21
22-Oct-02
22-Oct-02
Delivery of Compressor
Last Delivery of (other) Major Process
Equipment
19-Sep-02
27-Sep-02
-8
03-Sep-02
03-Sep-02
19-Dec-01
11-Dec-01 A
10-Apr-02
22-Apr-02 A
-12
Civil (AWARD)
13-Jun-02
22-Apr-02 A
52
Mechanical (AWARD)
12-Aug-02
03-Oct-02
-52
177
ELECTRICAL / INSTRUMENTATION
PROCUREMENT
SUBCONTRACTS
16-Oct-02
22-Apr-02 A
E&I (AWARD)
22-Nov-02
22-Nov-02
Insulation (AWARD)
11-Sep-02
11-Sep-02
CONSTRUCTION
Mobilization to site
15-Apr-02
25-Apr-02 A
Start Piling
06-May-02
06-May-02
13-May-02
29-May-02
-16
Start Foundations
-10
08-Jul-02
25-Jun-02
13
30-Sep-02
30-Sep-02
05-Nov-02
05-Nov-02
08-Oct-02
08-Oct-02
01-Aug-03
01-Aug-03
15-Aug-03
15-Aug-03
15-Aug-03
15-Aug-03
Page 13 of 13