Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Version:
Issue Date:
Review By Date:
Owned By:
Authorised By:
1.1
August 2006
June 2008
Engineering Manager D & P
Executive Manager D & P
REVISION TABLE
Version No
Date of Revision
1.0
June 2006
1.1
August 2006
Details of Amendment
Initial Release
Numbering changed to represent previous version
Document altered to allow the use of LCM 50 Tender Schedule
The above table lists in summary the amendments which have been made with most recent issues of this standard.
The table is updated with each re-issue. The latest amendments within the documents are marked with a change
indicator (|) in the outer margin.
CONTACT
This standard is the responsibility of the
Development and Projects Division, ElectraNet.
Please contact the indicated owner of the standard
with any inquiries.
ElectraNet
52-55 East Terrace, Adelaide, South Australia 5000
PO Box 7096, Hutt Street Post Office,
Adelaide, South Australia 5000
Ph (08) 8404 7966, Fx (08) 8404 7104
LI M I T AT I O N O F L I A B I LI T Y A N D
D I S C LA I M E R O F W A R R AN TY
ElectraNet makes no representation or warranty as
to the accuracy, reliability, completeness or
suitability for particular purposes of the information
in this document. ElectraNet and its employees,
agents and consultants shall have no liability
(including liability to any person by reason of
negligence or negligent misstatement) for any
statements, opinions, information or matter
(expressed or implied) arising out of, contained in or
derived from or for any omissions from the
information in this document, except in so far as
liability under any statute cannot be excluded.
2006 ElectraNet Pty Limited trading as ElectraNet. No part of this document may be reproduced
or copied in any form or by any means (graphic, electronic, mechanical, including photocopying,
recording, taping or information retrieval systems) without the prior written permission of ElectraNet.
LCM02
ElectraNet
TABLE OF CONTENTS
2.1
GENERAL..................................................................................................................................................3
2.1.1
MAJOR CROSSINGS (EG. TRANSMISSION LINES, RAILWAY LINES, HIGHWAYS AND RIVERS).................3
2.2
2.3
REFERENCES...........................................................................................................................................6
2.4
2.5
PROGRAM ................................................................................................................................................7
2.6
MATERIALS .............................................................................................................................................8
2.6.1
2.6.2
2.6.3
2.6.4
2.6.5
2.6.6
2.7
2.7.1
2.7.2
2.7.3
2.7.4
2.8
2.8.1
2.8.2
2.8.3
2.8.4
2.8.5
2.9
2.10
2.11
2.11.1
2.11.2
2.12
ENVIRONMENTAL MANAGEMENT.............................................................................................14
2.13
2.14
Version: 1.1
Page 2 of 14
ElectraNet
LCM02
2.1 GENERAL
A compulsory tender briefing and site visit will be conducted to ensure that the tenderers are fully
informed of the extent of work.
ElectraNet requires high levels of commitment towards the responsible and efficient management of
environmental, cultural heritage and native vegetation issues. The tenderer is also required to ensure
efficient management and communications/consultation with property owners along the line route to
ensure construction progresses smoothly. The tenderer will also be responsible for all QA
management issues during project construction.
RFT
SPECIFICATION
CLAUSE
REFERENCE
SPECIFICATION TITLE
AS1012
9.5.12
AS1046
6.2.1
AS1100(set)
6.2.1
Version: 1.1
Page 3 of 14
LCM02
ElectraNet
AS1101
6.2.1
AS1102
6.2.1
Graphical
Symbols
Documentation
AS1163
for
Electrotechnical
AS1214
9.1.5; 9.6.4
AS1289
9.4.10
AS1379
9.5.3; 9.5.13
AS1478
9.5.3
9.5.6
AS/NZS1554
.1
AS/NZS1554
.3
AS/NZS1554
.4
AS1559
5.4.4; 9.6.4
1986
(superseded)
AS1657
5.5.2
AS1882
AS1968
(withdrawn)
5.4.4; 9.6.4
AS2187
9.4.6
AS2239
AS2758.1
9.5.3
AS3582.1
9.5.3
AS3600
9.5.1;
9.5.10
AS3610
9.5.8
AS3972
9.5.3
AS4100
5.4.4; 9.1.2
Steel Structures
AS/NZS1554
9.1.6.4
AS/NZS3678
9.1.3
AS/NZS
3679.1
9.1.3
AS/NZS4671
9.5.3
Version: 1.1
9.5.15;
Page 4 of 14
ElectraNet
LCM02
AS/NZS4680
9.1.5; 9.1.6.3
AS/NZS
ISO9001
2.5.1
AS/ISO1000
6.2.1
AS2868
AS1317
Blended cement
AS1111.1
AS1112.3
AS1141.11
Methods for sampling and testing aggregates Particle size distribution by sieving
AS 1154.3
AS 2159
AS3799
ISO3098/1
6.2.2; 6.2.1
AS1553.1
AS1858.1
Electrodes and fluxes for submerged-arc welding Carbon steels and carbon-manganese steels
AS2203
AS2717.1
AS4065
AS3995
ESAA C(B)1
IEC 60652
Version: 1.1
Page 5 of 14
LCM02
ElectraNet
2.3 REFERENCES
LCM 01 Introduction
LCM 02 Project Specific
LCM 03 General Requirements
LCM 04 Design of Structures
LCM 05 Drawing Standards
LCM 06 Detail Design & Drawing
LCM 07 Tower Structure Supply & Fabrication
LCM 08 Tower Structure Prototype Assembly
LCM 09 Tower Structure Load Testing
LCM 10 Concrete Pole Manufacture
LCM 11 Steel Pole Fabrication
LCM 12 Stobie Pole Manufacture
LCM 13 Pole Structure Prototype Assembly
LCM 14 Pole Testing
LCM 15 Tower Foundation Construction
LCM 16 Pile Foundation Construction
LCM 18 Pole Foundation Construction
LCM 19 Pile Foundation Testing
LCM 20 Normal Class Concrete
LCM 21 Special Class Concrete
LCM 22 Tower Erection
LCM 23 Pole Erection
LCM 24 Line Erection
LCM 25 Structure Earthing
Version: 1.1
Page 6 of 14
ElectraNet
LCM02
i) Set up and facilitate a project risk assessment workshop in Adelaide with ElectraNet prior to any
work commencing on site;
j) Manage Variations and Delays as per Contract requirements set out in Part C Conditions of
Contract of this RFT;
k) Liaise with ElectraNet and endeavour to minimise the negative impact of issues which may
affect the project outcome or which provides a basis for a potential claim against ElectraNet;
l) Exercise a Duty of Care throughout the project and encourage fellow project members to do the
same;
m) Ensure that Invoices are issued in an accurate and timely manner;
n) Refer all media enquiries regarding the project to the Superintendent;
o) Ensure that QA procedures are adhered to and associated documentation is submitted to
ElectraNet on a weekly basis;
p) Obtain approval from Superintendent for as-built changes, prior to implementation;
q) Liaison and communication with property owners along the line easement.
2.5 PROGRAM
The Contractor shall provide a detailed baseline program to the Superintendent within 10 working
days of Contract award.
The program shall consist of a resourced critical path, analysed bar chart for the procurement,
manufacturing and construction of the project, and provide sufficient details to accurately monitor the
project progress. The program is to be updated bi-weekly and presented in Microsoft Project or
equivalent acceptable to ElectraNet.
The schedule is to show the following milestones as a minimum:
a)
b)
c)
d)
e)
f)
g)
h)
i)
j)
k)
l)
m)
Site access;
Placement of orders for materials and components;
Prototype Assemblies;
Completion of the manufacture of major components and sub components;
Delivery of major components to site;
Commencement of construction for each portion of the works;
Completion of construction for each portion of the works;
Required milestone date for any interface activity with a third party;
Commencement of commissioning;
Completion of commissioning;
Contracted Practical Completion Date;
Submission of As Built drawings and O and M documentation;
Project close-out.
The Project Program as submitted in accordance with the ElectraNet RFT Document and
encapsulated within this Contract shall not be altered or otherwise varied unless the alteration has
been submitted to and approved by the Superintendent.
The program shall be based on relevant dates provided in the ElectraNet RFT Document and stated
elsewhere in the Specification. The Contractor will be deemed to have made due allowance in their
tender for any reasonable action necessary to enable the dates specified to be met. The Program will
be deemed to include adequate allowance for all factors for which the Contractor shall not be entitled
to an extension of time or variation in payments.
Version: 1.1
Page 7 of 14
LCM02
ElectraNet
The Contractor and the Superintendent shall keep each other informed of occurrences that may affect
the programme. Both parties shall make all reasonable efforts to nullify delays to the overall
program.
The Contractor shall update his work program to show the progress of all activities and to illustrate
any deviation during the previous month from the planned program and shall include:
a) The forecast time to complete each activity delayed
b) Actual start and finish dates for activities
c) Milestones for delivery of information (refer Clause 2.8)
The program shall be used for the purpose of progress reporting.
2.6 MATERIALS
2.6.1 Materials Supplied By the Superintendent
(a)
All conductors;
(b)
All OPGW;
(c)
All insulators;
(d)
Conductor, Insulators and OPGW will be available from the ETSA Utilities Angle Park Warehouse
usually between the hours of 9:30am and 4:00pm, Monday to Friday, after 30th Sept 2005, unless
otherwise agreed.
The Contractor shall liaise with The ETSA Utilities Warehouse Manager to arrange timing and
release of these materials. Usually, 5 working days notice will be required to arrange release of any
materials, unless otherwise agreed with the ETSA Utilities Warehouse Manager.
The Contractor shall be responsible for the delivery of these materials to site, including unloading.
Version: 1.1
Page 8 of 14
ElectraNet
LCM02
(b) Prior to the transport of OPGW, the Contractor shall carryout the necessary tests to verify that
the fibres of the OPGW are in proper working order. The Contractor shall liaise with the
ETSA Utilities Warehouse Manager to make arrangements for this activity;
(c) The Contractor shall prepare suitable areas on the easement for these field dumps and shall be
responsible for provision of the access necessary to reach them. Access and site storage areas
shall not be prepared or used unless approved by the Superintendent. The approval of the
Superintendent shall not be unreasonably withheld but will take into account local land use
considerations, environmental factors and the possibility of damage to or vandalism of the
materials. The cost of field dumps and access to them and site weed management shall be
included in the schedule of rates for stringing;
(d) The Contractor shall be responsible for the security of these items from time of taking
possession from the Superintendent. Where the Contractor has made provision for the direct
delivery of conductor/OPGW, etc; to field dumps then the Contractor shall accept
responsibility for the security of these items upon delivery and for the workplace health and
safety of those in and around the dump (i.e.: private vehicle movement etc);
(e) The Contractor shall promptly return empty steel cable drums to the nominated freight depot
in Adelaide. The Contractor shall load and unload these here, including the provision of
necessary loading and unloading facilities. All empty drums are to be returned within one
month of completion of Stringing of each section of the work. The Contractor is to dispose of
wooden drums and packing in a manner approved by the Superintendent. Burning on-site is
not permitted;
(f) The Contractor shall be responsible for the cost of repair for any damage to steel conductor
drums whilst they are in the Contractors possession.
Version: 1.1
Page 9 of 14
LCM02
ElectraNet
Version: 1.1
Page 10 of 14
ElectraNet
LCM02
2.8.4 Traceability
Traceability requirements for this Contract are:
Item
Traceability Requirement
Foundation Excavations
Concrete foundations
Welding
2.8.5 Records
During the Contract:
The Contractor shall retain sufficient records as objective evidence to assure the Superintendent that
Contract requirements are being met.
A register of those records shall be maintained.
Subcontractors' records and suppliers' certificates pertinent to the Contract shall be included.
The Register of Records shall be made available to the SQAR for verification on request. Originals
of documents shall be provided for examination on request. The minimum records that the
Contractor is to maintain for this Contract are:
Version: 1.1
Page 11 of 14
LCM02
ElectraNet
DOCUMENT TITLE
TO BE
SUBMITTED
Foundation Record
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Stringing Programme
Yes
10
Yes
11
Yes
12
Yes
13
Yes
The Contractor shall supply to the Superintendent two copies of the above mentioned records within 2
weeks of the completion of each element of the work, i.e. foundations, tower fabrication, tower
erection, stringing etc.
The Contractor shall provide the Superintendent with copies of any test results requested by the
Superintendent, within the time stipulated by the Superintendent.
On Completion of the Contract:
The Contractor shall submit the Register of Records to the Superintendent within 4 weeks from the
Date of Practical Completion. The Superintendent may select specific records from the Register and
the Contractor shall provide these.
Records for products subject to approval by the relevant Regulatory Authority shall be delivered to
the Superintendent no later than when the product is delivered. The Contractor shall retain the records
for 18 months after Practical Completion.
Version: 1.1
Page 12 of 14
ElectraNet
LCM02
Contract documentation requirements. The supply / submission of notices / documents shall not be
limited to this schedule for either party to the Contract.
No of
Copies
Document / Notice
Timing
Construction Programme
Environmental
Construction Management
Plan
Revised programmes
fortnightly narratives
Fortnightly
&
Outage Plan
Statutory
Declarations
(for work as specified in the
contract
Terms
&
Conditions under Safety)
Notification
removed
of
earths
2
At Practical Completion
Assembly of prototype
tower for inspection
Welding Procedures
Test Reports
Stringing Program
Intention
to
cross
obstruction [this may need
clarification]
Clearing of crop
improved pasture
or
Version: 1.1
Page 13 of 14
LCM02
ElectraNet
The Contractor shall ensure that any calculations and drawings that are prepared by the Contractor for
permanent structures and foundations shall undergo independent design verification and be certified
by an ElectraNet nominated private certifier in accordance with the South Australian Development
Act 1993.
Should the Contractor wish to supply any alternative designs, the issue of certification must be
discussed with the Construction Manager regarding ElectraNet design management and quality
control process.
Prior to design verification, the contractor shall submit the proposed design including all design
documentation to the Construction Manager for functional engineering review to ensure compatibility
with the design intent and acceptance of the proposal.
General Access
The Contractor will be required to liaise with the substation works contractor to arrange access to the
substation. Only a properly endorsed contractor and individuals with the correct accreditation will be
granted permission of access.
2.11.2
Terminal Structure
The substation terminal structure will be available to take landing span loads as of 1st December 2005.
The Contractor should take this into account when developing the work programme.
Version: 1.1
Page 14 of 14