Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Sl. No.
1)
2)
3)
4)
5)
6)
given replies.
Consultancy Services for Rehabilitation and Expansion of Cuamba City
water Supply (Contract No. FIPAG/NPTWSSP/W-02/12).
The works completed for this Month are given below:
i.
4.128 km DN 500 Pipe laying for Raw water Pipeline have been completed ;
ii.
198mts DN 500 Pipe laying for Transmission Pipeline have been completed
iii.
iv.
completed;
v.
7)
8)
15% concrete work of Slow Sand Filters walls have been completed;
vi.
20% concrete work of Grade Level Reservoir 1&2 has been completed;
Techno Economical Appraisal of Detailed Project Reports of Infrastructure
projects submitted by State government of NE Region under NLCPR
scheme.
Total invoice of 48 lakh have been raised and submitted to the client.
Meeting held with the client regarding the realization of the pending payment.
Project Monitoring and Supervision of Quality Works Under RGGVY 11th
Scheme for MPPKVVCL In 7 Districts: Shahdol, Rewa, Mandla, Satna,
Dindori, Annuppur & Sidhi.
client.
Oct2014
Nov2014
Progr
ess
Oct2014
Nov2014
Progr
ess
Total Progress in
November-2014
I ReInspect
ion
2nd ReInspect
ion
280
251
280
251
1065
500
404
1090
500
404
25
25
Total 25
villages pole
erection
completed
9)
10)
11)
process.
Project Monitoring And Construction Supervision Along With Quality
Control Of Sewerage Project In Jabalpur City Under JNNURM:
Day wise Monthly progress report of the work executed during month of Oct
2014 submitted to the client.
The Inspection report and status of road restoration has been submitted to
client.
12)
13)
14)
15)
at an earliest time. During the meeting Rewa & Shahdol District progress has
been discussed. Also the Contractor of Rewa District has been directed to
carry out the compliance works at the earliest.
A time limit meeting held on every Saturday along with SE, Nodal Officers,
Contractor and Site Engineers WAPCOS Ltd. for progress and maintaining the
Quality Standards at Site. In Satna & Chhatarpur District the progress is too
slow. SE RGGVY has directed the Contractor to carry out the Quality works in
rapid speed.
PROJECT MANAGEMENT CONSULTANCY SERVICES- DESIGN & SUPERVISION
FOR AUGMENTATION OF WATER SUPPLY SCHEME IN DAR ES SALAAM AND
CHALINZE.
Manufacturing of the two vertical pumps for the raw water pumping station is
in progress. The inspection of pumps was carried during November 2014 and
delivered soon.
Manufacturing of prelift pumps is in progress after the approval of drawings
on 23rd September. The inspection of pumps was carried during November
2014 and delivered soon.
PROVISION OF CONSULTANCY SERVICES ON WATER SUPPLY SYSTEM AT
IGURUSI TRAINING INSTITUTE
Contract agreement was signed on 10th Nov 2014.
Meeting held with the client in the second week on November and data
to be collected was discussed.
Preparation of Feasibility Report and Detailed Project Report on Sewerage
and Sewage Treatment for Bhopal City
Detailed design and cost estimate of Lift stations are under Progress.
Detailed design and cost estimate of Pumping stations are under Progress.
Detailed design of 8 WWTPs are under Progress.
Detailed Project Report is under Preparation.
A Comprehensive Development Plan (CDP) for Majuli Cultural Landscape
Region (MCLR) in the state of Assam, India
Meeting was held with the Commissioner Upper Assam Division and other
committee members. Also pervious raised queries were clarified point wise.
Some of the observations have been carried out in revised concept report.
CDP draft final report is under process.
16)
17)
18)
19)
20)
21)
22)
23)