Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
PS.05
Converting Linear Schedules to
Critical Path Method Precedence
Dr. Douglas D. Gransberg, PE CCE
he critical path method (CPM) of scheduling is used
widely in many project controls applications [1, 4]. A
number of commercial scheduling software packages
are in use throughout the construction industry. Most
of these software packages are based on the CPM using the
precedence diagram method (PDM) as the network analysis
algorithm [5]. The PDM scheduling method is an activitybased methodology. Its output can be structured to furnish
powerful project control tools that are useful in executing the
project plan in a manner that fits both cost and time constraints.
Because this scheduling method has no inherent algorithmic
mechanism to manage both space and time simultaneously, the
cost engineer must assume that the durations derived from the
production rates for the crews associated with each activity will
not be hindered or conflicted by on-going work on parallel
activities [2]. Thus, there is always a possibility that two sets of
equipment and their crews will converge on the ground and
need to use the same space in order to maintain their target production rates. If this occurs, one crew will inevitably delay the
other until the space conflict is over. When a disruption occurs
for this reason on a labor-intensive project such as a building
project, the cost is usually not as high as it is on equipmentintensive heavy-civil construction project.
As a result of the above issue, many heavy-civil construction
project managers prefer to use linear scheduling to furnish the
basis for their project planning and scheduling system. Linear
schedules display time and space graphically on the same
instrument [1]. This allows the cost engineer to visually deconflict production activities on the project space representation.
Additionally, instead of being activity-based, they are production-based and allow the cost engineer to synchronize the
schedule with the same assumed production rates that were
used in the project cost estimate. This furnishes a method for
seamlessly transitioning from project planning to project execution. A succinct synopsis of the advantages of linear scheduling
is contained in the training course material from Peter Kiewit
and Sons, Inc., a large heavy-civil construction company. It is
described as follows:
PS.05
verts A&B and pour concrete culverts C&D of one-day duration each. Finally, each culvert is assigned a separate form culvert activity with a one-day duration. The resulting output is
shown in table 2 and the fragmentary network (fragnet) for this
series of activities is shown in figure 2.
This project has some miscellaneous activities that were not
included in the linear schedule. The activities, their durations
and precedence relationships are as follows:
REFERENCES
1. Callahan, M.T., D.G. Quackenbush, , and J.E. Rowings.
Construction Project Scheduling, New York : McGraw-Hill,
(1992): pp. 86-112, 200-210.
2. Gransberg, D.D., C. M. Popescu and R.C. Ryan.
Construction Equipment Management for Engineers,
Estimators, and Construction Managers, Taylor and Francis
Books, Inc., (2006): pp.174-182.
3. Jones, C., Linear Scheduling. Presentation Slides
Unpublished Lecture given at Norman, Oklahoma, (April
4, 2005), Peter Kiewit and Sons, Inc., Dallas, Texas.
PS.05.5