Managing

Project
Processes
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Activity Relationships
Activity Relationship
S precedes T, which precedes U.

AOA
S
1

AON

T
2

U
3

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Activity Relationships
Activity Relationship
S and T must be completed before U can be started.

AOA
1

AON

S
U

T
2

U
T

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Activity Relationships
Activity Relationship
T and U cannot begin until S has been completed.

AOA
3

S
1

AON

T
S

U
4

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Activity Relationships
Activity Relationship
U and V cannot begin until both S and T have been
completed.

AOA
S

T
2

AON

U
3

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Activity Relationships
Activity Relationship
U cannot begin until both S and T have been completed;
V cannot begin until T has been completed.

AOA
S

AON

Dummy
V
4
6

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Activity Relationships
Activity Relationship
T and U cannot begin until S has been completed; V
cannot begin until both T and U have been completed.

AOA
S
1

AON

T
2

V
4

Dummy

U
3

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Activity
A
B
C
D
E
F

G
H
I
J
K

Description

Immediate
Predecessor(s)

Select administrative and medical staff.


Select site and do site survey.
Select equipment.
Prepare final construction plans and layout.
Bring utilities to the site.
Interview applicants and fill positions in nursing,
support staff, maintenance, and security.
Purchase and take delivery of equipment.
Construct the hospital.
Develop an information system.
Install the equipment.
Train nurses and support staff.

A
B
B
A
C
D
A
E,G,H
F,I,J

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Immediate
Predecessor(s)

Activity
Description
AON Network
A Select administrative and medical staff.
B Select site and do site survey.
A
C Select equipment.
D Prepare final construction plans and layout.
E
Bring utilities to the site.
F
Interview
Start applicants and fill positions in nursing,
support staff, maintenance, and security.
G Purchase and take delivery of equipment.
H Construct the hospital.
I
Develop and information system.
J
Install the equipment.
K Train nurses and support staff.

A
B
B
A
C
D
A
E,G,H
F,I,J

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Immediate
Predecessor(s)

Activity
Description
AON Network
A Select administrative and medical staff.
B Select site and do site survey.
A
C Select equipment.
D Prepare final construction plans and layout.
E
Bring utilities to the site.
F
Interview
Start applicants and fill positions in nursing,
support staff, maintenance, and security.
G Purchase and take delivery of equipment.
H Construct the
B hospital.
I
Develop and information system.
J
Install the equipment.
K Train nurses and support staff.

A
B
B
A
C
D
A
E,G,H
F,I,J

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Immediate
Predecessor(s)

Activity
Description
AON Network
A Select administrative and medical staff.
B Select site and do site survey.
A
C Select equipment.
D Prepare final construction plans and layout.
E
Bring utilities to the site.
F
Interview
Start applicantsCand fill positions in nursing,
support staff, maintenance, and security.
G Purchase and take delivery of equipment.
H Construct the
B hospital.
I
Develop and information system.
J
Install the equipment.
K Train nurses and support staff.

A
B
B
A
C
D
A
E,G,H
F,I,J

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Immediate
Predecessor(s)

Activity
Description
AON Network
A Select administrative and medical staff.
B Select site and do site survey.
A
C Select equipment.
D Prepare final construction plans and layout.
E
Bring utilities to the site.
F
Interview
Start applicantsCand fill positions in nursing,
support staff, maintenance, and security.
G Purchase and take delivery of equipment.
H Construct the
D
B hospital.
I
Develop and information system.
J
Install the equipment.
K Train nurses and support staff.

A
B
B
A
C
D
A
E,G,H
F,I,J

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Immediate
Predecessor(s)

Activity
Description
AON Network
A Select administrative and medical staff.
B Select site and do site survey.
A
C Select equipment.
D Prepare final construction plans and layout.
E
Bring utilities to the site.
F
Interview
Start applicantsCand fill positions in nursing,
support staff, maintenance, and security.
G Purchase and take delivery of equipment.
H Construct the
D
B hospital.
I
Develop and information system.
J
Install the equipment.
K Train nurses and support
staff.
E

A
B
B
A
C
D
A
E,G,H
F,I,J

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Immediate
Predecessor(s)

Activity
Description
AON Network
A Select administrative and medical staff.
B Select site and do site survey.
A
F
C Select equipment.
D Prepare final construction plans and layout.
E
Bring utilities to the site.
F
Interview
Start applicantsCand fill positions in nursing,
support staff, maintenance, and security.
G Purchase and take delivery of equipment.
H Construct the
D
B hospital.
I
Develop and information system.
J
Install the equipment.
K Train nurses and support
staff.
E

A
B
B
A
C
D
A
E,G,H
F,I,J

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Immediate
Predecessor(s)

Activity
Description
AON Network
A Select administrative and medical staff.
B Select site and do site survey.
A
F
C Select equipment.
D Prepare final construction plans and layout.
E
Bring utilities to the site.
F
Interview
positions in nursing,
Start applicantsCand fillG
support staff, maintenance, and security.
G Purchase and take delivery of equipment.
H Construct the
D
B hospital.
I
Develop and information system.
J
Install the equipment.
K Train nurses and support
staff.
E

A
B
B
A
C
D
A
E,G,H
F,I,J

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Immediate
Predecessor(s)

Activity
Description
AON Network
A Select administrative and medical staff.
B Select site and do site survey.
A
F
C Select equipment.
D Prepare final construction plans and layout.
E
Bring utilities to the site.
F
Interview
positions in nursing,
Start applicantsCand fillG
support staff, maintenance, and security.
G Purchase and take delivery of equipment.
H Construct the
D
B hospital.
H
I
Develop and information system.
J
Install the equipment.
K Train nurses and support
staff.
E

A
B
B
A
C
D
A
E,G,H
F,I,J

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Immediate
Predecessor(s)

Activity
Description
AON Network
I
A Select administrative and medical staff.
B Select site and do site survey.
A
F
C Select equipment.
D Prepare final construction plans and layout.
E
Bring utilities to the site.
F
Interview
positions in nursing,
Start applicantsCand fillG
support staff, maintenance, and security.
G Purchase and take delivery of equipment.
H Construct the
D
B hospital.
H
I
Develop and information system.
J
Install the equipment.
K Train nurses and support
staff.
E

A
B
B
A
C
D
A
E,G,H
F,I,J

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Immediate
Predecessor(s)

Activity
Description
AON Network
I
A Select administrative and medical staff.
B Select site and do site survey.
A
F
C Select equipment.
D Prepare final construction plans and layout.
E
Bring utilities to the site.
F
Interview
positions in nursing,
Start applicantsCand fillG
support staff, maintenance, and security.
G Purchase and take delivery of equipment.
H Construct the
D
B hospital.
H
J
I
Develop and information system.
J
Install the equipment.
K Train nurses and support
staff.
E

A
B
B
A
C
D
A
E,G,H
F,I,J

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Immediate
Predecessor(s)

Activity
Description
AON Network
I
A Select administrative and medical staff.
B Select site and do site survey.
A
F
K
C Select equipment.
D Prepare final construction plans and layout.
E
Bring utilities to the site.
F
Interview
positions in nursing,
Start applicantsCand fillG
support staff, maintenance, and security.
G Purchase and take delivery of equipment.
H Construct the
D
B hospital.
H
J
I
Develop and information system.
J
Install the equipment.
K Train nurses and support
staff.
E

A
B
B
A
C
D
A
E,G,H
F,I,J

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Immediate
Predecessor(s)

Activity
Description
AON Network
I
A Select administrative and medical staff.
B Select site and do site survey.
A
F
K
C Select equipment.
D Prepare final construction plans and layout.
E
Bring utilities to the site.
F
Interview
positions in
nursing,
Start applicantsCand fillG
Finish
support staff, maintenance, and security.
G Purchase and take delivery of equipment.
H Construct the
D
B hospital.
H
J
I
Develop and information system.
J
Install the equipment.
K Train nurses and support
staff.
E

A
B
B
A
C
D
A
E,G,H
F,I,J

Figure 4.2
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Immediate
Predecessor(s)

Activity
Description
AOA Network
A Select administrative
and medical staff.
2
B Select site and do site survey.
C Select equipment.
D Prepare A
final construction plans and layout.
E
Bring utilities to the site.
F
Interview
Start applicants and fill positions in nursing,
1 staff, maintenance, and security.
support
G Purchase and take delivery of equipment.
H Construct the hospital.
I
Develop and information system.
J
Install the equipment.
K Train nurses and support staff.

A
B
B
A
C
D
A
E,G,H
F,I,J

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Immediate
Predecessor(s)

Activity
Description
AOA Network
A Select administrative
and medical staff.
2
B Select site and do site survey.
C Select equipment.
D Prepare A
final construction plans and layout.
E
Bring utilities to the site.
F
Interview
Start applicants and fill positions in nursing,
1 staff, maintenance, and security.
support
G Purchase and take delivery of equipment.
H Construct
B the hospital.
I
Develop and information system.
J
Install the equipment.
4 support staff.
K Train nurses and

A
B
B
A
C
D
A
E,G,H
F,I,J

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Immediate
Predecessor(s)

Activity
Description
AOA Network
A Select administrative
and medical staff.
2
B Select site and do site survey.
C
C Select equipment.
D Prepare A
final construction plans and layout.
3 the site.
E
Bring utilities to
F
Interview
Start applicants and fill positions in nursing,
1 staff, maintenance, and security.
support
G Purchase and 5take delivery of equipment.
H Construct
B the hospital.
I
Develop and information
system.
D
J
Install the equipment.
4 support staff.
K Train nurses and

A
B
B
A
C
D
A
E,G,H
F,I,J

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Immediate
Predecessor(s)

Activity
Description
AOA Network
F
A Select administrative
and medical
8 staff.
2
B Select site and do site
survey.
I
C
C Select equipment.
D Prepare A
final construction plans and layout.
3 the site.
7
E
Bring utilities to
F
Interview
Start applicantsGand fill positions in nursing,
1 staff, maintenance, and security.
support
H
G Purchase and 5take delivery
6 of equipment.
H Construct
B the hospital.
E
I
Develop and information
system.
D
J
Install the equipment.
4 support staff.
K Train nurses and

A
B
B
A
C
D
A
E,G,H
F,I,J

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Immediate
Predecessor(s)

Activity
Description
AOA Network
F
A Select administrative
and medical
8 staff.
2
B Select site and do site
survey.
I
C
C Select equipment.
D Prepare A
final construction plans and layout.
3 the site.
7
J
E
Bring utilities to
F
Interview
Start applicantsGand fill positions in nursing,
1 staff, maintenance, and security.
support
H
G Purchase and 5take delivery
6 of equipment.
H Construct
B the hospital.
E
I
Develop and information
system.
D
J
Install the equipment.
4 support staff.
K Train nurses and

A
B
B
A
C
D
A
E,G,H
F,I,J

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Immediate
Predecessor(s)

Activity
Description
AOA Network
F
A Select administrative
and medical
8 staff.
2
B Select site and do site
survey.
I Dummy
C
C Select equipment.
D Prepare A
final construction plans and layout.
3 the site.
7
J
E
Bring utilities to
F
Interview
Start applicantsGand fill positions in nursing,
1 staff, maintenance, and security.
support
H
G Purchase and 5take delivery
6 of equipment.
H Construct
B the hospital.
E
I
Develop and information
system.
D
J
Install the equipment.
4 support staff.
K Train nurses and

A
B
B
A
C
D
A
E,G,H
F,I,J

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Immediate
Predecessor(s)

Activity
Description
AOA Network
F
A Select administrative
and medical
8 staff.
2
B Select site and do site
survey.
I Dummy
C
C Select equipment.
K
A
D Prepare final construction plans and layout.
3 the site.
7
J
E
Bring utilities to
F
Interview
in nursing,
Start applicantsGand fill positionsFinish
1 staff, maintenance, and security.
support
9
H
G Purchase and 5take delivery
6 of equipment.
H Construct
B the hospital.
E
I
Develop and information
system.
D
J
Install the equipment.
4 support staff.
K Train nurses and

A
B
B
A
C
D
A
E,G,H
F,I,J

Figure 4.3

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Immediate
Predecessor(s)

Activity
I
Completion Time Description
15
A Select administrative and medical staff.
B Select site and do site survey.
A
F
K
C Select equipment.
12
10
6
D Prepare final construction plans and layout.
E
Bring utilities to the site.
C
G
F
Interview
nursing,
Start applicants and fill positions in Finish
10
35
support staff, maintenance, and security.
G Purchase and take delivery of equipment.
B
D
H
J
H Construct the
hospital.
9
10
40
4
I
Develop and information system.
J
Install the equipment.
E
K Train nurses and support
staff.
Figure 4.4

24

A
B
B
A
C
D
A
E,G,H
F,I,J

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Immediate
Predecessor(s)

Activity
I
Completion Time Description
15
A Select administrative and medical staff.
B Select site and do site survey.
A
F
K
C Select equipment.
12
10
6
D Prepare final construction plans and layout.
E
Bring utilities to the site.
C
G
F
Interview
nursing,
Start applicants and fill positions in Finish
10
35
support staff, maintenance, and security.
G Purchase and take delivery of equipment.
B
D
H
J
H Construct the
hospital.
9
10
40
4
I
Develop and information system.
J
Install the equipment.
E
K Train nurses and support
staff.
24

A
B
B
A
C
D
A
E,G,H
F,I,J

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Immediate
Predecessor(s)

Activity
I
Completion Time Description
15
A Select administrative and medical staff.
B Select site and do site survey.
A
F
K
C Select equipment.
12
10
6
D Prepare final construction plans and layout.
E
Bring utilities to the site.
C
G
F
Interview
nursing,
Start applicants and fill positions in Finish
10
35
support staff, maintenance, and security.
G Purchase and take delivery of equipment.
B
D
H
J
H Construct the
hospital.
9
10
40
4
I
Develop and information system.
J
Install the equipment.
E
K Train nurses and support
staff.
24

A
B
B
A
C
D
A
E,G,H
F,I,J

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Immediate
Predecessor(s)

Activity
I
Completion Time Description
15
A Select administrative and medical staff.
B Select site and do site survey.
A
F
K
C Select equipment.
12
10
6
D Prepare final construction plans and layout.
E
Bring utilities to the site.
C
G
F
Interview
nursing,
Start applicants and fill positions in Finish
10
35
support staff, maintenance, and security.
G Purchase and take delivery of equipment.
B
D
H
J
H Construct the
hospital.
9
10
40
4
I
Develop and information system.
J
Install the equipment.
E
K Train nurses and support
staff.
24

A
B
B
A
C
D
A
E,G,H
F,I,J

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Immediate
Predecessor(s)

Activity
I
Completion Time Description
15
A Select administrative and medical staff.
B Select site and do site survey.
A
F
K
C Select equipment.
12
10
6
D Prepare final construction plans and layout.
E
Bring utilities to the site.
C
G
F
Interview
nursing,
Start applicants and fill positions in Finish
10
35
support staff, maintenance, and security.
G Purchase and take delivery of equipment.
B
D
H
J
H Construct the
hospital.
9
10
40
4
I
Develop and information system.
J
Install the equipment.
E
K Train nurses and support
staff.
24

A
B
B
A
C
D
A
E,G,H
F,I,J

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Immediate
Predecessor(s)

Activity
I
Completion Time Description
15
A Select administrative and medical staff.
B Select site and do site survey.
A
F
K
C Select equipment.
12
10
6
D Prepare final construction plans and layout.
E
Bring utilities to the site.
C
G
F
Interview
nursing,
Start applicants and fill positions in Finish
10
35
support staff, maintenance, and security.
G Purchase and take delivery of equipment.
B
D
H
J
H Construct the
hospital.
9
10
40
4
I
Develop and information system.
J
Install the equipment.
E
K Train nurses and support
staff.
24

A
B
B
A
C
D
A
E,G,H
F,I,J

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Path

Expected Time (wks)

Immediate
Predecessor(s)

Activity
Description
I
Completion
Time
A-F-K
28
15
A Select administrative
and medical staff.
A-I-K
33
B Select site67and do site survey.
A-C-G-J-K
A
F
K
C
Select
equipment.
10
6
B-D-H-J-K
6912
D Prepare final
B-E-J-K
43 construction plans and layout.
E
Bring utilities to the site.
C
G
F
Interview
nursing,
Start applicants and fill positions in Finish
10
35
support staff, maintenance, and security.
G Purchase and take delivery of equipment.
B
D
H
J
H Construct the
hospital.
9
10
40
4
I
Develop and information system.
J
Install the equipment.
E
K Train nurses and support
staff.
24

A
B
B
A
C
D
A
E,G,H
F,I,J

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Path

Expected Time (wks)

Immediate
Predecessor(s)

Activity
Description
I
Completion
Time
A-F-K
28
15
A Select administrative
and medical staff.
A-I-K
33
B Select site67and do site survey.
A-C-G-J-K
A
F
K
C
Select
equipment.
10
6
B-D-H-J-K
6912
D Prepare final
B-E-J-K
43 construction plans and layout.
E
Bring utilities to the site.
C
G
F
Interview
nursing,
Start applicants and fill positions in Finish
10
35
support staff, maintenance, and security.
G Purchase and take delivery of equipment.
B
D
H
J
H Construct the
hospital.
9
10
40
4
I
Develop and information system.
J
Install the equipment.
E
K Train nurses and support
staff.
24

A
B
B
A
C
D
A
E,G,H
F,I,J

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Path

Expected Time (wks)

Immediate
Predecessor(s)

Activity
Description
I
Completion
Time
A-F-K
28
15
A Select administrative
and medical staff.
A-I-K
33
B Select site67and do site survey.
A-C-G-J-K
A
F
K
C
Select
equipment.
10
6
B-D-H-J-K
6912
D Prepare final
B-E-J-K
43 construction plans and layout.
E
Bring utilities to the site.
C
G
F
Interview
nursing,
Start applicants and fill positions in Finish
10
35
support staff, maintenance, and security.
G Purchase and take delivery of equipment.
B
D
H
J
H Construct the
hospital.
9
10
40
4
I
Develop and information system.
J
Install the equipment.
E
K Train nurses and support
staff.
24

A
B
B
A
C
D
A
E,G,H
F,I,J

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

I
15

12

10

Start

B
9
Earliest Start
and
Earliest Finish Times

Finish

10

35

10

40

E
24

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

I
15

Earliest start time


0

12

10

Start

B
9
Earliest Start
and
Earliest Finish Times

Finish

10

35

10

40

E
24

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

I
15

Earliest start time


0

Earliest finish time

A 12

12

10

Start

B
9
Earliest Start
and
Earliest Finish Times

Finish

10

35

10

40

E
24

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

I
15

A 12

12

10

Start

B 9

9
Earliest Start
and
Earliest Finish Times

Finish

10

35

10

40

E
24

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

I
15

A 12

12

10

Start

B 9

9
Earliest Start
and
Earliest Finish Times

Finish

10

35

D 19

10

40

9 E 33

24

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

12

I 27
15

A 12

12

12

12

Start

B 9

9
Earliest Start
and
Earliest Finish Times

F 22

10

C 22

10

35

D 19

10

40

Finish

9 E 33

24

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

12

I 27
15

A 12

12

12

12

Start

B 9

9
Earliest Start
and
Earliest Finish Times

F 22

10

C 22

10

35

D 19
10

19

Finish

H 59

40

9 E 33

24

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

12

I 27
15

A 12

12

12

12

Start

F 22

10

C 22

22

10

B 9

9
Earliest Start
and
Earliest Finish Times

D 19
10

G 57

Finish

35

19

H 59

40

9 E 33

24

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

12

I 27
15

A 12

12

12

12

Start

F 22

10

C 22

22

10

B 9

9
Earliest Start
and
Earliest Finish Times

D 19
10

G 57

Finish

35

19

H 59
40

59

J 63
4

9 E 33

24

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Earliest start time

12

I 27

Earliest finish time

15

A 12

12

12

Critical
path
0

B 9

9
Earliest Start
and
Earliest Finish Times

63 K 69

10

12

Start

F 22

C 22

22

10

D 19
10

G 57

Finish

35

19

H 59
40

59

J 63
4

9 E 33

24

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

12

I 27
15

A 12

12

63 K 69

10

12

12

Start

F 22

C 22

22

10

B 9

9
Latest Start
and
Latest Finish Times

D 19
10

G 57

Finish

35

19

H 59
40

59

J 63
4

9 E 33

24

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

12

I 27
15

A 12

12

63 K 69
63
69

10

12

12

Start

F 22

C 22

22

10

B 9

9
Latest Start
and
Latest Finish Times

D 19
10

G 57

Finish

35

19

H 59
40

Latest
finish
time

59

J 63
4

9 E 33

24

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

12

I 27
15

A 12

12

10

12

12

Start

F 22

C 22

Latest
start
time
22

10

B 9

9
Latest Start
and
Latest Finish Times

D 19
10

63 K 69
63
69

G 57

Finish

35

19

H 59
40

Latest
finish
time

59

J 63
4

9 E 33

24

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

12
27
48 15 63

A 12
12

12

Start

63 K 69
63
69

12
22
53 10 63

C 22

22

10

B 9

9
Latest Start
and
Latest Finish Times

D 19
10

G 57

Finish

35

19

H 59
40

59
63
59 4 63

9 E 33

24

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

12
27
48 15 63

A 12
12

12

Start

C 22
10

B 9

9
Latest Start
and
Latest Finish Times

63 K 69
63
69

12
22
53 10 63

D 19
10

22
57
24 35 59

19
59
19 40 59

Finish

59
63
59 4 63

9 E 33
35 24 59

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

12
27
48 15 63

A 12
12

12
22
14 10 24

Start

B 9

9
Latest Start
and
Latest Finish Times

63 K 69
63
69

12
22
53 10 63

9
19
9 10 19

22
57
24 35 59

19
59
19 40 59

Finish

59
63
59 4 63

9 E 33
35 24 59

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Earliest start time


Latest start time
A

0
12
2 12 14

12
27
48 15 63

Critical
path
0
0

B 9
9 9

Latest Start
and
Latest Finish Times

Latest finish time

63 K 69
63
69

12
22
53 10 63

Start

Earliest finish time

12
22
14 10 24

9
19
9 10 19

22
57
24 35 59

19
59
19 40 59

Finish

59
63
59 4 63

9 E 33
35 24 59

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

12
27
48 15 63

0
12
2 12 14

12
22
14 10 24

Start

0
0

Activity Slack
Analysis

B 9
9 9

63 K 69
63
69

12
22
53 10 63

9
19
9 10 19

22
57
24 35 59

19
59
19 40 59

Finish

59
63
59 4 63

9 E 33
35 24 59

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Activity Slack
I

12
27
48 15 63

Slack = LS ES
or

0
12
2 12 14

Slack = LF EF

12
22
14 10 24

Start

0
0

Activity Slack
Analysis

B 9
9 9

63 K 69
63
69

12
22
53 10 63

9
19
9 10 19

22
57
24 35 59

19
59
19 40 59

Finish

59
63
59 4 63

9 E 33
35 24 59

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Activity Slack
I

12
27
48 15 63

SlackK = 63 63
or

0
12
2 12 14

SlackK = 69 69

12
22
14 10 24

Start

0
0

Activity Slack
Analysis

B 9
9 9

63 K 69
63
69

12
22
53 10 63

9
19
9 10 19

22
57
24 35 59

19
59
19 40 59

Finish

59
63
59 4 63

9 E 33
35 24 59

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Activity Slack
I

12
27
48 15 63

SlackK = 0
or

SlackK = 0

0
12
2 12 14

12
22
14 10 24

Start

0
0

Activity Slack
Analysis

B 9
9 9

63 K 69
63
69

12
22
53 10 63

9
19
9 10 19

22
57
24 35 59

19
59
19 40 59

Finish

59
63
59 4 63

9 E 33
35 24 59

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Node Duration ES
A
B
C
D
E
F
G
H
I
J
K

12
9
10
10
24
10
35
40
15
4
6

0
0
12
9
9
12
22
19
12
59
Start
63

LS

Slack

2
0
14
9
35
53
24
19
48
59
63

2
0
2
0
26
A 12
0
41
2 12 14
2
0
36
0
0

0
0

Activity Slack
Analysis

B 9
9 9

12
27
48 15 63

63 K 69
63
69

12
22
53 10 63

12
22
14 10 24

9
19
9 10 19

22
57
24 35 59

19
59
19 40 59

Finish

59
63
59 4 63

9 E 33
35 24 59

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Node Duration ES
A
B
C
D
E
F
G
H
I
J
K

12
9
10
10
24
10
35
40
15
4
6

0
0
12
9
9
12
22
19
12
59
63

LS

Slack

2
0
14
9
35
53
24
19
48
59
63

2
0
2
0
26
41
2
0
36
0
0

0
0

Critical Path

B 9
9 9

12
27
48 15 63

63 K 69
63
69

12
22
53 10 63

12
22
14 10 24

9
19
9 10 19

22
57
24 35 59

19
59
19 40 59

Finish

59
63
59 4 63

9 E 33
35 24 59

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

12
27
48 15 63

0
12
2 12 14

12
22
14 10 24

Start

0
0

Critical Path

B 9
9 9

63 K 69
63
69

12
22
53 10 63

9
19
9 10 19

22
57
24 35 59

19
59
19 40 59

Finish

59
63
59 4 63

9 E 33
35 24 59

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Project Crashing
Crashing
reducing project time by expending additional resources

Crash time
an amount of time an activity is reduced

Crash cost
cost of reducing activity time

Goal
reduce project duration at minimum cost

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Project Crashing: Example

2
8

12

7
4

1
12

3
4

5
4

6
4

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Project Crashing: Example


(cont.)
$7,000
$6,000
Crash cost

$5,000

Crashed activity
Slope = crash cost per week

$4,000

$3,000
$2,000

Normal activity

Normal cost

$1,000
Normal time

Crash time

|
2

|
4

|
6

|
8

|
10

|
12

|
14

Weeks

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Normal Activity and Crash


Data

ACTIVITY

1
2
3
4
5
6
7

NORMAL
TIME
(WEEKS)

CRASH
TIME
(WEEKS)

NORMAL
COST

12
8
4
12
4
4
4

7
5
3
9
1
1
3

$3,000
2,000
4,000
50,000
500
500
15,000

$5,000
3,500
7,000
71,000
1,100
1,100
22,000

$75,000

$110,700

CRASH
COST

TOTAL
ALLOWABLE
CRASH TIME
(WEEKS)

5
3
1
3
3
3
1

CRASH
COST PER
WEEK

$400
500
3,000
7,000
200
200
7,000

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

$7000

$500

Project Duration:
36 weeks

2
8

$700

12

7
4

FROM

12

$400

3
4

6
4

5
4

$3000

$200

$200
$7000

$500

2
8

TO
Project Duration:
31 weeks
Additional Cost:
$2000

$700

12

7
4

1
7

$400

3
4

$3000

5
4

6
4
$200

$200

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Time-Cost Relationship
Crashing costs increase as project
duration decreases
Indirect costs increase as project
duration increases
Reduce project length as long as
crashing costs are less than indirect
costs

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Time-Cost Tradeoff
Minimum cost = optimal project time

Total project cost

Cost ($)

Indirect cost

Direct cost
Crashing

Time

Project duration
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Probability

Probabilistic Time Estimates

Time
a

b
Mean

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Probabilistic Time Estimates

Probability

Area under curve


between a and b
is 99.74%

3s

Time

3s

m
Mean

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Probabilistic
Time Estimates

Activity B
Most
Optimistic Likely Pessimistic
(a)
(m)
(b)
7
8
15

Start

Finish

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Probabilistic
Time Estimates

Activity B
Most
Optimistic Likely Pessimistic
(a)
(m)
(b)
7
8
15

7 + 4(8) + 15
te =
= 9 weeks
6

Start

Finish

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Probabilistic
Time Estimates

Activity B
Most
Optimistic Likely Pessimistic
(a)
(m)
(b)
7
8
15

7 + 4(8) + 15
te =
= 9 weeks
6

s2 =

15 - 7
6

Start

Finish

) = 1.78

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Time Estimates (wk)


Optimistic
Activity
(a)
A
B
C
D
E
F
G
H
I
J
K

11
7
5
8
14
6
25
35
10
1
5

Likely
(m)

Pessimistic
(b)

12
8
10
9
25
9
36
40
13
2
6

13
15
15
16
30
18
41
45
28
15
7

Activity Statistics
Expected Variance
Time (te )
(s2 )
12
9
10
10
24
10
35
40
15
4
6

0.11
1.78
2.78
1.78
7.11
4.00
7.11
2.78
9.00
5.44
0.11

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Probabilities
Critical Path = B - D - H - J - K
T = 72 days

TE = 69 days

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Probabilities
Critical Path = B - D - H - J - K
T = 72 days

s2

TE = 69 days

= (variances of activities)

T TE
z=
s2

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Probabilities
Critical Path = B - D - H - J - K
T = 72 days

s2

TE = 69 days

= (variances of activities)

T TE
z=
s2

s2 = 1.78 + 1.78 + 2.78 + 5.44 + 0.11 = 11.89

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Probabilities
Critical Path = B - D - H - J - K
T = 72 days

s2

TE = 69 days

= (variances of activities)

T TE
z=
s2

s2 = 1.78 + 1.78 + 2.78 + 5.44 + 0.11 = 11.89


72 69
z=
11.89

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Probabilities
Critical Path = B - D - H - J - K
T = 72 days

s2

TE = 69 days

= (variances of activities)

T TE
z=
s2

s2 = 1.78 + 1.78 + 2.78 + 5.44 + 0.11 = 11.89


72 69
z=
= 0.87
11.89

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Probabilities
Critical Path = B - D - H - J - K
T = 72 days

s2

TE = 69 days

= (variances of activities)

T TE
z=
s2

s2 = 1.78 + 1.78 + 2.78 + 5.44 + 0.11 = 11.89


72 69
z=
= 0.87
11.89

From Appendix 2
Pz = .8078 .81

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Probabilities
Critical
Path
Length
of = B - D - H critical path

T = 72 days

s2

Probability of
meeting the of
(variances
schedule is
0.8078

Normal distribution:
J
- K= 69 weeks;
Mean
s = 3.45 weeks

TE = 69 days

activities)

T-T

Eof
z Probability
=
272
exceeding
s
weeks is 0.1922

s2 = 1.78 + 1.78 + 2.78 + 5.44 + 0.11 = 11.89


72 - 69
69 72
z=
= 0.87
11.89
Project duration (weeks)

Figure 4.12

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Probabilities
Path = A - C - G - J - K
T = 72 days

s2

TE = 67 days

= (variances of activities)

T TE
z=
s2

s2 = 0.11 + 2.78 + 7.11 + 5.44 + 0.11 = 15.55


72 67
z=
= 1.27
15.55

From Appendix 2
Pz = .8980 .90

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Resource requirements

Project Life Cycle


Definition
and
organization

Start

Planning

Execution

Time

Close out

Finish

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Construct a PERT Network from the following


set of activities, their precedences requirements
and 3 time-estimates of completion time.
Compute the slack for each activity and
determine the critical path.

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Activity

Precedences

Time Estimates (Weeks)

Optimistic

Pessimistic

Most Likely

None

None

11

11

10

10

18

14

C, D

11

11

11

F, G

14

10

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

Activity Durations (days)


Job
Co
de

Job Description

Costs in dollars

Immediate
Predecessors

Normal

Crash

Normal

Crash

None

80

100

Remove and disassemble the motor

Clean and paint the frame

40

94

Rewind armature

12

100

184

Replace bearings

70

102

Assemble and install the motor

B, C and D

50

50

To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.

The fixed cost per day is $ 20 per day. As a


policy the firm does not allow an activity to be
crashed by more than a day for fear of poor
quality. (Except in case of C which can be
crashed by a maximum of 4 days)

i.
Draw the activity on arc network.

ii.
Find the optimum project
duration.
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.