Project
Processes
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Activity Relationships
Activity Relationship
S precedes T, which precedes U.
AOA
S
1
AON
T
2
U
3
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Activity Relationships
Activity Relationship
S and T must be completed before U can be started.
AOA
1
AON
S
U
T
2
U
T
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Activity Relationships
Activity Relationship
T and U cannot begin until S has been completed.
AOA
3
S
1
AON
T
S
U
4
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Activity Relationships
Activity Relationship
U and V cannot begin until both S and T have been
completed.
AOA
S
T
2
AON
U
3
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Activity Relationships
Activity Relationship
U cannot begin until both S and T have been completed;
V cannot begin until T has been completed.
AOA
S
AON
Dummy
V
4
6
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Activity Relationships
Activity Relationship
T and U cannot begin until S has been completed; V
cannot begin until both T and U have been completed.
AOA
S
1
AON
T
2
V
4
Dummy
U
3
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Activity
A
B
C
D
E
F
G
H
I
J
K
Description
Immediate
Predecessor(s)
A
B
B
A
C
D
A
E,G,H
F,I,J
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Immediate
Predecessor(s)
Activity
Description
AON Network
A Select administrative and medical staff.
B Select site and do site survey.
A
C Select equipment.
D Prepare final construction plans and layout.
E
Bring utilities to the site.
F
Interview
Start applicants and fill positions in nursing,
support staff, maintenance, and security.
G Purchase and take delivery of equipment.
H Construct the hospital.
I
Develop and information system.
J
Install the equipment.
K Train nurses and support staff.
A
B
B
A
C
D
A
E,G,H
F,I,J
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Immediate
Predecessor(s)
Activity
Description
AON Network
A Select administrative and medical staff.
B Select site and do site survey.
A
C Select equipment.
D Prepare final construction plans and layout.
E
Bring utilities to the site.
F
Interview
Start applicants and fill positions in nursing,
support staff, maintenance, and security.
G Purchase and take delivery of equipment.
H Construct the
B hospital.
I
Develop and information system.
J
Install the equipment.
K Train nurses and support staff.
A
B
B
A
C
D
A
E,G,H
F,I,J
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Immediate
Predecessor(s)
Activity
Description
AON Network
A Select administrative and medical staff.
B Select site and do site survey.
A
C Select equipment.
D Prepare final construction plans and layout.
E
Bring utilities to the site.
F
Interview
Start applicantsCand fill positions in nursing,
support staff, maintenance, and security.
G Purchase and take delivery of equipment.
H Construct the
B hospital.
I
Develop and information system.
J
Install the equipment.
K Train nurses and support staff.
A
B
B
A
C
D
A
E,G,H
F,I,J
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Immediate
Predecessor(s)
Activity
Description
AON Network
A Select administrative and medical staff.
B Select site and do site survey.
A
C Select equipment.
D Prepare final construction plans and layout.
E
Bring utilities to the site.
F
Interview
Start applicantsCand fill positions in nursing,
support staff, maintenance, and security.
G Purchase and take delivery of equipment.
H Construct the
D
B hospital.
I
Develop and information system.
J
Install the equipment.
K Train nurses and support staff.
A
B
B
A
C
D
A
E,G,H
F,I,J
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Immediate
Predecessor(s)
Activity
Description
AON Network
A Select administrative and medical staff.
B Select site and do site survey.
A
C Select equipment.
D Prepare final construction plans and layout.
E
Bring utilities to the site.
F
Interview
Start applicantsCand fill positions in nursing,
support staff, maintenance, and security.
G Purchase and take delivery of equipment.
H Construct the
D
B hospital.
I
Develop and information system.
J
Install the equipment.
K Train nurses and support
staff.
E
A
B
B
A
C
D
A
E,G,H
F,I,J
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Immediate
Predecessor(s)
Activity
Description
AON Network
A Select administrative and medical staff.
B Select site and do site survey.
A
F
C Select equipment.
D Prepare final construction plans and layout.
E
Bring utilities to the site.
F
Interview
Start applicantsCand fill positions in nursing,
support staff, maintenance, and security.
G Purchase and take delivery of equipment.
H Construct the
D
B hospital.
I
Develop and information system.
J
Install the equipment.
K Train nurses and support
staff.
E
A
B
B
A
C
D
A
E,G,H
F,I,J
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Immediate
Predecessor(s)
Activity
Description
AON Network
A Select administrative and medical staff.
B Select site and do site survey.
A
F
C Select equipment.
D Prepare final construction plans and layout.
E
Bring utilities to the site.
F
Interview
positions in nursing,
Start applicantsCand fillG
support staff, maintenance, and security.
G Purchase and take delivery of equipment.
H Construct the
D
B hospital.
I
Develop and information system.
J
Install the equipment.
K Train nurses and support
staff.
E
A
B
B
A
C
D
A
E,G,H
F,I,J
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Immediate
Predecessor(s)
Activity
Description
AON Network
A Select administrative and medical staff.
B Select site and do site survey.
A
F
C Select equipment.
D Prepare final construction plans and layout.
E
Bring utilities to the site.
F
Interview
positions in nursing,
Start applicantsCand fillG
support staff, maintenance, and security.
G Purchase and take delivery of equipment.
H Construct the
D
B hospital.
H
I
Develop and information system.
J
Install the equipment.
K Train nurses and support
staff.
E
A
B
B
A
C
D
A
E,G,H
F,I,J
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Immediate
Predecessor(s)
Activity
Description
AON Network
I
A Select administrative and medical staff.
B Select site and do site survey.
A
F
C Select equipment.
D Prepare final construction plans and layout.
E
Bring utilities to the site.
F
Interview
positions in nursing,
Start applicantsCand fillG
support staff, maintenance, and security.
G Purchase and take delivery of equipment.
H Construct the
D
B hospital.
H
I
Develop and information system.
J
Install the equipment.
K Train nurses and support
staff.
E
A
B
B
A
C
D
A
E,G,H
F,I,J
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Immediate
Predecessor(s)
Activity
Description
AON Network
I
A Select administrative and medical staff.
B Select site and do site survey.
A
F
C Select equipment.
D Prepare final construction plans and layout.
E
Bring utilities to the site.
F
Interview
positions in nursing,
Start applicantsCand fillG
support staff, maintenance, and security.
G Purchase and take delivery of equipment.
H Construct the
D
B hospital.
H
J
I
Develop and information system.
J
Install the equipment.
K Train nurses and support
staff.
E
A
B
B
A
C
D
A
E,G,H
F,I,J
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Immediate
Predecessor(s)
Activity
Description
AON Network
I
A Select administrative and medical staff.
B Select site and do site survey.
A
F
K
C Select equipment.
D Prepare final construction plans and layout.
E
Bring utilities to the site.
F
Interview
positions in nursing,
Start applicantsCand fillG
support staff, maintenance, and security.
G Purchase and take delivery of equipment.
H Construct the
D
B hospital.
H
J
I
Develop and information system.
J
Install the equipment.
K Train nurses and support
staff.
E
A
B
B
A
C
D
A
E,G,H
F,I,J
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Immediate
Predecessor(s)
Activity
Description
AON Network
I
A Select administrative and medical staff.
B Select site and do site survey.
A
F
K
C Select equipment.
D Prepare final construction plans and layout.
E
Bring utilities to the site.
F
Interview
positions in
nursing,
Start applicantsCand fillG
Finish
support staff, maintenance, and security.
G Purchase and take delivery of equipment.
H Construct the
D
B hospital.
H
J
I
Develop and information system.
J
Install the equipment.
K Train nurses and support
staff.
E
A
B
B
A
C
D
A
E,G,H
F,I,J
Figure 4.2
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Immediate
Predecessor(s)
Activity
Description
AOA Network
A Select administrative
and medical staff.
2
B Select site and do site survey.
C Select equipment.
D Prepare A
final construction plans and layout.
E
Bring utilities to the site.
F
Interview
Start applicants and fill positions in nursing,
1 staff, maintenance, and security.
support
G Purchase and take delivery of equipment.
H Construct the hospital.
I
Develop and information system.
J
Install the equipment.
K Train nurses and support staff.
A
B
B
A
C
D
A
E,G,H
F,I,J
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Immediate
Predecessor(s)
Activity
Description
AOA Network
A Select administrative
and medical staff.
2
B Select site and do site survey.
C Select equipment.
D Prepare A
final construction plans and layout.
E
Bring utilities to the site.
F
Interview
Start applicants and fill positions in nursing,
1 staff, maintenance, and security.
support
G Purchase and take delivery of equipment.
H Construct
B the hospital.
I
Develop and information system.
J
Install the equipment.
4 support staff.
K Train nurses and
A
B
B
A
C
D
A
E,G,H
F,I,J
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Immediate
Predecessor(s)
Activity
Description
AOA Network
A Select administrative
and medical staff.
2
B Select site and do site survey.
C
C Select equipment.
D Prepare A
final construction plans and layout.
3 the site.
E
Bring utilities to
F
Interview
Start applicants and fill positions in nursing,
1 staff, maintenance, and security.
support
G Purchase and 5take delivery of equipment.
H Construct
B the hospital.
I
Develop and information
system.
D
J
Install the equipment.
4 support staff.
K Train nurses and
A
B
B
A
C
D
A
E,G,H
F,I,J
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Immediate
Predecessor(s)
Activity
Description
AOA Network
F
A Select administrative
and medical
8 staff.
2
B Select site and do site
survey.
I
C
C Select equipment.
D Prepare A
final construction plans and layout.
3 the site.
7
E
Bring utilities to
F
Interview
Start applicantsGand fill positions in nursing,
1 staff, maintenance, and security.
support
H
G Purchase and 5take delivery
6 of equipment.
H Construct
B the hospital.
E
I
Develop and information
system.
D
J
Install the equipment.
4 support staff.
K Train nurses and
A
B
B
A
C
D
A
E,G,H
F,I,J
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Immediate
Predecessor(s)
Activity
Description
AOA Network
F
A Select administrative
and medical
8 staff.
2
B Select site and do site
survey.
I
C
C Select equipment.
D Prepare A
final construction plans and layout.
3 the site.
7
J
E
Bring utilities to
F
Interview
Start applicantsGand fill positions in nursing,
1 staff, maintenance, and security.
support
H
G Purchase and 5take delivery
6 of equipment.
H Construct
B the hospital.
E
I
Develop and information
system.
D
J
Install the equipment.
4 support staff.
K Train nurses and
A
B
B
A
C
D
A
E,G,H
F,I,J
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Immediate
Predecessor(s)
Activity
Description
AOA Network
F
A Select administrative
and medical
8 staff.
2
B Select site and do site
survey.
I Dummy
C
C Select equipment.
D Prepare A
final construction plans and layout.
3 the site.
7
J
E
Bring utilities to
F
Interview
Start applicantsGand fill positions in nursing,
1 staff, maintenance, and security.
support
H
G Purchase and 5take delivery
6 of equipment.
H Construct
B the hospital.
E
I
Develop and information
system.
D
J
Install the equipment.
4 support staff.
K Train nurses and
A
B
B
A
C
D
A
E,G,H
F,I,J
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Immediate
Predecessor(s)
Activity
Description
AOA Network
F
A Select administrative
and medical
8 staff.
2
B Select site and do site
survey.
I Dummy
C
C Select equipment.
K
A
D Prepare final construction plans and layout.
3 the site.
7
J
E
Bring utilities to
F
Interview
in nursing,
Start applicantsGand fill positionsFinish
1 staff, maintenance, and security.
support
9
H
G Purchase and 5take delivery
6 of equipment.
H Construct
B the hospital.
E
I
Develop and information
system.
D
J
Install the equipment.
4 support staff.
K Train nurses and
A
B
B
A
C
D
A
E,G,H
F,I,J
Figure 4.3
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Immediate
Predecessor(s)
Activity
I
Completion Time Description
15
A Select administrative and medical staff.
B Select site and do site survey.
A
F
K
C Select equipment.
12
10
6
D Prepare final construction plans and layout.
E
Bring utilities to the site.
C
G
F
Interview
nursing,
Start applicants and fill positions in Finish
10
35
support staff, maintenance, and security.
G Purchase and take delivery of equipment.
B
D
H
J
H Construct the
hospital.
9
10
40
4
I
Develop and information system.
J
Install the equipment.
E
K Train nurses and support
staff.
Figure 4.4
24
A
B
B
A
C
D
A
E,G,H
F,I,J
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Immediate
Predecessor(s)
Activity
I
Completion Time Description
15
A Select administrative and medical staff.
B Select site and do site survey.
A
F
K
C Select equipment.
12
10
6
D Prepare final construction plans and layout.
E
Bring utilities to the site.
C
G
F
Interview
nursing,
Start applicants and fill positions in Finish
10
35
support staff, maintenance, and security.
G Purchase and take delivery of equipment.
B
D
H
J
H Construct the
hospital.
9
10
40
4
I
Develop and information system.
J
Install the equipment.
E
K Train nurses and support
staff.
24
A
B
B
A
C
D
A
E,G,H
F,I,J
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Immediate
Predecessor(s)
Activity
I
Completion Time Description
15
A Select administrative and medical staff.
B Select site and do site survey.
A
F
K
C Select equipment.
12
10
6
D Prepare final construction plans and layout.
E
Bring utilities to the site.
C
G
F
Interview
nursing,
Start applicants and fill positions in Finish
10
35
support staff, maintenance, and security.
G Purchase and take delivery of equipment.
B
D
H
J
H Construct the
hospital.
9
10
40
4
I
Develop and information system.
J
Install the equipment.
E
K Train nurses and support
staff.
24
A
B
B
A
C
D
A
E,G,H
F,I,J
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Immediate
Predecessor(s)
Activity
I
Completion Time Description
15
A Select administrative and medical staff.
B Select site and do site survey.
A
F
K
C Select equipment.
12
10
6
D Prepare final construction plans and layout.
E
Bring utilities to the site.
C
G
F
Interview
nursing,
Start applicants and fill positions in Finish
10
35
support staff, maintenance, and security.
G Purchase and take delivery of equipment.
B
D
H
J
H Construct the
hospital.
9
10
40
4
I
Develop and information system.
J
Install the equipment.
E
K Train nurses and support
staff.
24
A
B
B
A
C
D
A
E,G,H
F,I,J
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Immediate
Predecessor(s)
Activity
I
Completion Time Description
15
A Select administrative and medical staff.
B Select site and do site survey.
A
F
K
C Select equipment.
12
10
6
D Prepare final construction plans and layout.
E
Bring utilities to the site.
C
G
F
Interview
nursing,
Start applicants and fill positions in Finish
10
35
support staff, maintenance, and security.
G Purchase and take delivery of equipment.
B
D
H
J
H Construct the
hospital.
9
10
40
4
I
Develop and information system.
J
Install the equipment.
E
K Train nurses and support
staff.
24
A
B
B
A
C
D
A
E,G,H
F,I,J
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Immediate
Predecessor(s)
Activity
I
Completion Time Description
15
A Select administrative and medical staff.
B Select site and do site survey.
A
F
K
C Select equipment.
12
10
6
D Prepare final construction plans and layout.
E
Bring utilities to the site.
C
G
F
Interview
nursing,
Start applicants and fill positions in Finish
10
35
support staff, maintenance, and security.
G Purchase and take delivery of equipment.
B
D
H
J
H Construct the
hospital.
9
10
40
4
I
Develop and information system.
J
Install the equipment.
E
K Train nurses and support
staff.
24
A
B
B
A
C
D
A
E,G,H
F,I,J
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Path
Immediate
Predecessor(s)
Activity
Description
I
Completion
Time
A-F-K
28
15
A Select administrative
and medical staff.
A-I-K
33
B Select site67and do site survey.
A-C-G-J-K
A
F
K
C
Select
equipment.
10
6
B-D-H-J-K
6912
D Prepare final
B-E-J-K
43 construction plans and layout.
E
Bring utilities to the site.
C
G
F
Interview
nursing,
Start applicants and fill positions in Finish
10
35
support staff, maintenance, and security.
G Purchase and take delivery of equipment.
B
D
H
J
H Construct the
hospital.
9
10
40
4
I
Develop and information system.
J
Install the equipment.
E
K Train nurses and support
staff.
24
A
B
B
A
C
D
A
E,G,H
F,I,J
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Path
Immediate
Predecessor(s)
Activity
Description
I
Completion
Time
A-F-K
28
15
A Select administrative
and medical staff.
A-I-K
33
B Select site67and do site survey.
A-C-G-J-K
A
F
K
C
Select
equipment.
10
6
B-D-H-J-K
6912
D Prepare final
B-E-J-K
43 construction plans and layout.
E
Bring utilities to the site.
C
G
F
Interview
nursing,
Start applicants and fill positions in Finish
10
35
support staff, maintenance, and security.
G Purchase and take delivery of equipment.
B
D
H
J
H Construct the
hospital.
9
10
40
4
I
Develop and information system.
J
Install the equipment.
E
K Train nurses and support
staff.
24
A
B
B
A
C
D
A
E,G,H
F,I,J
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Path
Immediate
Predecessor(s)
Activity
Description
I
Completion
Time
A-F-K
28
15
A Select administrative
and medical staff.
A-I-K
33
B Select site67and do site survey.
A-C-G-J-K
A
F
K
C
Select
equipment.
10
6
B-D-H-J-K
6912
D Prepare final
B-E-J-K
43 construction plans and layout.
E
Bring utilities to the site.
C
G
F
Interview
nursing,
Start applicants and fill positions in Finish
10
35
support staff, maintenance, and security.
G Purchase and take delivery of equipment.
B
D
H
J
H Construct the
hospital.
9
10
40
4
I
Develop and information system.
J
Install the equipment.
E
K Train nurses and support
staff.
24
A
B
B
A
C
D
A
E,G,H
F,I,J
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
I
15
12
10
Start
B
9
Earliest Start
and
Earliest Finish Times
Finish
10
35
10
40
E
24
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
I
15
12
10
Start
B
9
Earliest Start
and
Earliest Finish Times
Finish
10
35
10
40
E
24
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
I
15
A 12
12
10
Start
B
9
Earliest Start
and
Earliest Finish Times
Finish
10
35
10
40
E
24
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
I
15
A 12
12
10
Start
B 9
9
Earliest Start
and
Earliest Finish Times
Finish
10
35
10
40
E
24
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
I
15
A 12
12
10
Start
B 9
9
Earliest Start
and
Earliest Finish Times
Finish
10
35
D 19
10
40
9 E 33
24
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
12
I 27
15
A 12
12
12
12
Start
B 9
9
Earliest Start
and
Earliest Finish Times
F 22
10
C 22
10
35
D 19
10
40
Finish
9 E 33
24
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
12
I 27
15
A 12
12
12
12
Start
B 9
9
Earliest Start
and
Earliest Finish Times
F 22
10
C 22
10
35
D 19
10
19
Finish
H 59
40
9 E 33
24
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
12
I 27
15
A 12
12
12
12
Start
F 22
10
C 22
22
10
B 9
9
Earliest Start
and
Earliest Finish Times
D 19
10
G 57
Finish
35
19
H 59
40
9 E 33
24
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
12
I 27
15
A 12
12
12
12
Start
F 22
10
C 22
22
10
B 9
9
Earliest Start
and
Earliest Finish Times
D 19
10
G 57
Finish
35
19
H 59
40
59
J 63
4
9 E 33
24
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
12
I 27
15
A 12
12
12
Critical
path
0
B 9
9
Earliest Start
and
Earliest Finish Times
63 K 69
10
12
Start
F 22
C 22
22
10
D 19
10
G 57
Finish
35
19
H 59
40
59
J 63
4
9 E 33
24
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
12
I 27
15
A 12
12
63 K 69
10
12
12
Start
F 22
C 22
22
10
B 9
9
Latest Start
and
Latest Finish Times
D 19
10
G 57
Finish
35
19
H 59
40
59
J 63
4
9 E 33
24
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
12
I 27
15
A 12
12
63 K 69
63
69
10
12
12
Start
F 22
C 22
22
10
B 9
9
Latest Start
and
Latest Finish Times
D 19
10
G 57
Finish
35
19
H 59
40
Latest
finish
time
59
J 63
4
9 E 33
24
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
12
I 27
15
A 12
12
10
12
12
Start
F 22
C 22
Latest
start
time
22
10
B 9
9
Latest Start
and
Latest Finish Times
D 19
10
63 K 69
63
69
G 57
Finish
35
19
H 59
40
Latest
finish
time
59
J 63
4
9 E 33
24
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
12
27
48 15 63
A 12
12
12
Start
63 K 69
63
69
12
22
53 10 63
C 22
22
10
B 9
9
Latest Start
and
Latest Finish Times
D 19
10
G 57
Finish
35
19
H 59
40
59
63
59 4 63
9 E 33
24
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
12
27
48 15 63
A 12
12
12
Start
C 22
10
B 9
9
Latest Start
and
Latest Finish Times
63 K 69
63
69
12
22
53 10 63
D 19
10
22
57
24 35 59
19
59
19 40 59
Finish
59
63
59 4 63
9 E 33
35 24 59
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
12
27
48 15 63
A 12
12
12
22
14 10 24
Start
B 9
9
Latest Start
and
Latest Finish Times
63 K 69
63
69
12
22
53 10 63
9
19
9 10 19
22
57
24 35 59
19
59
19 40 59
Finish
59
63
59 4 63
9 E 33
35 24 59
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
0
12
2 12 14
12
27
48 15 63
Critical
path
0
0
B 9
9 9
Latest Start
and
Latest Finish Times
63 K 69
63
69
12
22
53 10 63
Start
12
22
14 10 24
9
19
9 10 19
22
57
24 35 59
19
59
19 40 59
Finish
59
63
59 4 63
9 E 33
35 24 59
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
12
27
48 15 63
0
12
2 12 14
12
22
14 10 24
Start
0
0
Activity Slack
Analysis
B 9
9 9
63 K 69
63
69
12
22
53 10 63
9
19
9 10 19
22
57
24 35 59
19
59
19 40 59
Finish
59
63
59 4 63
9 E 33
35 24 59
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Activity Slack
I
12
27
48 15 63
Slack = LS ES
or
0
12
2 12 14
Slack = LF EF
12
22
14 10 24
Start
0
0
Activity Slack
Analysis
B 9
9 9
63 K 69
63
69
12
22
53 10 63
9
19
9 10 19
22
57
24 35 59
19
59
19 40 59
Finish
59
63
59 4 63
9 E 33
35 24 59
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Activity Slack
I
12
27
48 15 63
SlackK = 63 63
or
0
12
2 12 14
SlackK = 69 69
12
22
14 10 24
Start
0
0
Activity Slack
Analysis
B 9
9 9
63 K 69
63
69
12
22
53 10 63
9
19
9 10 19
22
57
24 35 59
19
59
19 40 59
Finish
59
63
59 4 63
9 E 33
35 24 59
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Activity Slack
I
12
27
48 15 63
SlackK = 0
or
SlackK = 0
0
12
2 12 14
12
22
14 10 24
Start
0
0
Activity Slack
Analysis
B 9
9 9
63 K 69
63
69
12
22
53 10 63
9
19
9 10 19
22
57
24 35 59
19
59
19 40 59
Finish
59
63
59 4 63
9 E 33
35 24 59
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Node Duration ES
A
B
C
D
E
F
G
H
I
J
K
12
9
10
10
24
10
35
40
15
4
6
0
0
12
9
9
12
22
19
12
59
Start
63
LS
Slack
2
0
14
9
35
53
24
19
48
59
63
2
0
2
0
26
A 12
0
41
2 12 14
2
0
36
0
0
0
0
Activity Slack
Analysis
B 9
9 9
12
27
48 15 63
63 K 69
63
69
12
22
53 10 63
12
22
14 10 24
9
19
9 10 19
22
57
24 35 59
19
59
19 40 59
Finish
59
63
59 4 63
9 E 33
35 24 59
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Node Duration ES
A
B
C
D
E
F
G
H
I
J
K
12
9
10
10
24
10
35
40
15
4
6
0
0
12
9
9
12
22
19
12
59
63
LS
Slack
2
0
14
9
35
53
24
19
48
59
63
2
0
2
0
26
41
2
0
36
0
0
0
0
Critical Path
B 9
9 9
12
27
48 15 63
63 K 69
63
69
12
22
53 10 63
12
22
14 10 24
9
19
9 10 19
22
57
24 35 59
19
59
19 40 59
Finish
59
63
59 4 63
9 E 33
35 24 59
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
12
27
48 15 63
0
12
2 12 14
12
22
14 10 24
Start
0
0
Critical Path
B 9
9 9
63 K 69
63
69
12
22
53 10 63
9
19
9 10 19
22
57
24 35 59
19
59
19 40 59
Finish
59
63
59 4 63
9 E 33
35 24 59
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Project Crashing
Crashing
reducing project time by expending additional resources
Crash time
an amount of time an activity is reduced
Crash cost
cost of reducing activity time
Goal
reduce project duration at minimum cost
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
2
8
12
7
4
1
12
3
4
5
4
6
4
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
$5,000
Crashed activity
Slope = crash cost per week
$4,000
$3,000
$2,000
Normal activity
Normal cost
$1,000
Normal time
Crash time
|
2
|
4
|
6
|
8
|
10
|
12
|
14
Weeks
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
ACTIVITY
1
2
3
4
5
6
7
NORMAL
TIME
(WEEKS)
CRASH
TIME
(WEEKS)
NORMAL
COST
12
8
4
12
4
4
4
7
5
3
9
1
1
3
$3,000
2,000
4,000
50,000
500
500
15,000
$5,000
3,500
7,000
71,000
1,100
1,100
22,000
$75,000
$110,700
CRASH
COST
TOTAL
ALLOWABLE
CRASH TIME
(WEEKS)
5
3
1
3
3
3
1
CRASH
COST PER
WEEK
$400
500
3,000
7,000
200
200
7,000
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
$7000
$500
Project Duration:
36 weeks
2
8
$700
12
7
4
FROM
12
$400
3
4
6
4
5
4
$3000
$200
$200
$7000
$500
2
8
TO
Project Duration:
31 weeks
Additional Cost:
$2000
$700
12
7
4
1
7
$400
3
4
$3000
5
4
6
4
$200
$200
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Time-Cost Relationship
Crashing costs increase as project
duration decreases
Indirect costs increase as project
duration increases
Reduce project length as long as
crashing costs are less than indirect
costs
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Time-Cost Tradeoff
Minimum cost = optimal project time
Cost ($)
Indirect cost
Direct cost
Crashing
Time
Project duration
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Probability
Time
a
b
Mean
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Probability
3s
Time
3s
m
Mean
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Probabilistic
Time Estimates
Activity B
Most
Optimistic Likely Pessimistic
(a)
(m)
(b)
7
8
15
Start
Finish
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Probabilistic
Time Estimates
Activity B
Most
Optimistic Likely Pessimistic
(a)
(m)
(b)
7
8
15
7 + 4(8) + 15
te =
= 9 weeks
6
Start
Finish
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Probabilistic
Time Estimates
Activity B
Most
Optimistic Likely Pessimistic
(a)
(m)
(b)
7
8
15
7 + 4(8) + 15
te =
= 9 weeks
6
s2 =
15 - 7
6
Start
Finish
) = 1.78
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
11
7
5
8
14
6
25
35
10
1
5
Likely
(m)
Pessimistic
(b)
12
8
10
9
25
9
36
40
13
2
6
13
15
15
16
30
18
41
45
28
15
7
Activity Statistics
Expected Variance
Time (te )
(s2 )
12
9
10
10
24
10
35
40
15
4
6
0.11
1.78
2.78
1.78
7.11
4.00
7.11
2.78
9.00
5.44
0.11
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Probabilities
Critical Path = B - D - H - J - K
T = 72 days
TE = 69 days
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Probabilities
Critical Path = B - D - H - J - K
T = 72 days
s2
TE = 69 days
= (variances of activities)
T TE
z=
s2
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Probabilities
Critical Path = B - D - H - J - K
T = 72 days
s2
TE = 69 days
= (variances of activities)
T TE
z=
s2
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Probabilities
Critical Path = B - D - H - J - K
T = 72 days
s2
TE = 69 days
= (variances of activities)
T TE
z=
s2
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Probabilities
Critical Path = B - D - H - J - K
T = 72 days
s2
TE = 69 days
= (variances of activities)
T TE
z=
s2
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Probabilities
Critical Path = B - D - H - J - K
T = 72 days
s2
TE = 69 days
= (variances of activities)
T TE
z=
s2
From Appendix 2
Pz = .8078 .81
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Probabilities
Critical
Path
Length
of = B - D - H critical path
T = 72 days
s2
Probability of
meeting the of
(variances
schedule is
0.8078
Normal distribution:
J
- K= 69 weeks;
Mean
s = 3.45 weeks
TE = 69 days
activities)
T-T
Eof
z Probability
=
272
exceeding
s
weeks is 0.1922
Figure 4.12
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Probabilities
Path = A - C - G - J - K
T = 72 days
s2
TE = 67 days
= (variances of activities)
T TE
z=
s2
From Appendix 2
Pz = .8980 .90
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Resource requirements
Start
Planning
Execution
Time
Close out
Finish
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Activity
Precedences
Optimistic
Pessimistic
Most Likely
None
None
11
11
10
10
18
14
C, D
11
11
11
F, G
14
10
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
Job Description
Costs in dollars
Immediate
Predecessors
Normal
Crash
Normal
Crash
None
80
100
40
94
Rewind armature
12
100
184
Replace bearings
70
102
B, C and D
50
50
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.
i.
Draw the activity on arc network.
ii.
Find the optimum project
duration.
To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Sixth Edition 2002 Prentice Hall, Inc. All rights reserved.