Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Acknowledgment
We would like to acknowledge Ato Kibrom Legesse, B.Sc. in civil
engineering for his limited less support during the out come of
this project, starting form supplying the necessary data ,reference
books, computers and office access. Beside this, we would like
to thank again, for his friendly and professional approach to
advise us. It would have been impossible to have this project
finished with out the help of the above mentioned person. Finally
,yet importantly, we would like to thank our families for their
support during our stay in Mekelle University.
Table of content
page
UNIT ONE
TOPOGRAPHY--------------------------------------------------5
DESIGN SPEED------------------------------------------------5
TRAFFIC FACTOR----------------------------------------------6
VOLUME AND CAPACITY FACTOR--------------------------6
ENVIROMENTAL FACTOR------------------------------------6
iii
BACK GROUND
This two-lane highway project is located in Mekelle town, around
Abreha Castle hotel. The project is intended for reduction of
traffic load currently and for the expected traffic load in the
future, because the town is developing at high rate.
The project is done based on surveying data on existing road.
When we come to our case, we were given full surveying data for
the vertical profile and data for the horizontal profile, another
surveying data is provided which is not related to the vertical
profile data. As a result we design the Abreha Castle ring road for
vertical curve design and for horizontal curve we used the other
data.
Other design data, which are related to the geometry of the road
and drainage system, are taken from ERA2001 manual and other
standards design manuals.
iv
ABSTRACT
This project divided in to five units ,the first unit give the general
idea about route surveying and type of rout surveying .the second
chapter deals with geometric design of high way in general and
the design procedure and computation of vertical and horizontal
elements.
The third unit deals about the cross section of the road like
lane width carriage way side and back slope.
The forth unit deals about the earth work and quantity of the
project. Here the method of earth work computation and
determination of economical hauling distance is included.
The last unit deals with the high way drainage especially
about the design and hydrological analysis of the drainage.
vi
Introduction
horizontal alignment
vertical alignment
sight distance requirements
cross sectional elements
side drainage etc
-1-
Unit one
ROUTE SURVEYING
The need to do route surveying
If an adequate route surveying are not carried out properly, there will
be deficiencies in the selected alignment, specification and design are
to come to in trouble during execution of the work.
The quality of the survey has influence on the cost of the project. A
number of alternatives should be examined and the most appropriate
solution should be selected out. This is possible only if exhaustive
investigations are to be carried out.
Failures are encountered if the survey is not properly done.
Embankment subsidence, flooding of roads, land slide, deposition of
sand-dunes, and erosion of river or sea are some of the problems
which can be avoided by proper route surveying.
A) Reconnaissance survey
The initial reconnaissance survey of the region implies an
examination of relatively large areas between the terminals for the
purpose of determining broad corridors through which alignment
may pass. This survey should be aided by available maps and
stereoscopic Ariel photographic coverage of the area.
The probable alignment can be located on the map from the
following details available on the map
-alignment avoiding valleys, ponds or lakes
-when the road has to cross a row hills, possibility of crossing the
mountains
pass
-approximate location of bridge sites for crossing rivers, avoiding
bending of river.
-2-
B) Preliminary survey
The preliminary survey consists in running an accurate traverse line
along the routes already recommended as a result of reconnaissance
survey in order to attain sufficient data for final location.
The main objectives of preliminary survey are:
To survey the various alternative alignment proposed
after reconnaissance and collect all necessary details of
topography drainage and soil
to fined the best alignment from all considerations
to compare the different proposal in view of the
requirement of a good alignment
-4-
Unit two
GEOMETRIC DESIGN
Geometric design in a highway design ,deals with the visible
dimensions of a road way. Properly designed highway geometries
provide optimum efficiency in the operation of traffic with safety.
TOPOGRAPHY
DESIGN SPEED
TRAFFIC FACTOR
VOLUME AND CAPACITY FACTOR
ENVIROMENTAL FACTOR
DESIGN CLASS
2.2.1 TOPOGRAPHY
Topography of the area affects geometric design of a highway. The
areas under consideration are
plain
rolling
mountainous
steep
2.2.2 Design speed
It is the most important factor controlling the geometric design element
of a highway. Design speed is a speed determined for design and
correlation of the physical features of a highway that influences
vehicular operation. It is the maximum safe speed that can be
obtained over a specified section of a highway when conditions are so
-5-
as
Physical characteristics
of a high way and its
surrounding
Weather condition in the area.
Presence of other vehicles and their nature.
Speed limitations place up on the vehicle either by law or
mechanical devices.
-6-
-7-
PI
PC
90
90
PT
-8-
-9-
- 10 -
- 11 -
Sight Distance
Highway Centerline
Line of sight
PC
PT
Sight Obstruction
Centerline of inside lane
- 12 -
- 13 -
- 14 -
Calculation of station
Sc=station Ts+ Ls
=26+870.85+44
=26+914.85
CS=station of Sc+Lc
=26+914.85+119.19
=27+034
ST=station of cs+Ls
=27+034+44
=27+078
Deflection angle ()
=(l/ Ls)2 s/2- CS, but CS=0 because s is laser than 16.
Curve se t out for the centeral curve by using deflection angle ()
= *d= ( r c l/lc
- 15 -
St
Curve 2
PI=27+352.98
(Dela) =6401006
Calculation of minimum radius of the curve
Rmin=vd2/127(e+f)
VD=50
from the table
e=4%
from the table for urban area(ERA table 2.6)
f=0.22
Rmin= 75.712m
But Rmin is less than from Rmin in the table recommended in ERA
manual so we use the minimum recommended value from table
- 16 -
sin
s=21.98
S= Ls2/24Rc2=.81
The tangent distance between pi and Ts
Ts=k+(R+s)tan/2
=85.18
Calculation of station
Sc=station Ts+ Ls
=27+311.8
CS=station of Sc+Lc
=27+311.8+68
=27+379.8
ST=station of cs+Ls
=27+379+44
- 17 -
=27+423
Deflection angle ()
=(l/ Ls)2 s/2- CS, but CS=0 because s is laser than 16.for the
spiral curve .
Curve se t out for the central curve by using deflection angle ()
= *d= ( r c l/
Table2
enterance transtion
curve
station
27+267.8
27+280
27+300
27+311.8
L(m)
0
12.2
32.2
44
Diflaction
angle
0
0.322897
2.249343
4.2
remark
TS
Sc
0
8.2
28.2
48.2
68
0
2.350318
8.082803
13.81529
19.49045
Sc
Cs
exittransitioncurve
27+379.8
27+380
27+400
27+420
27+423.8
44
43.8
23.8
3.8
0
4.2
4.161905
1.228847
0.031326
0
Cs
TS
Curve 3
PI=28+121.54
Dela=2101724
In this curve, hence delta() from the give data is small so the
topography relatively flat , use sample circular curve with a
radius of 150m.
- 18 -
length
Deflec
tion a
Remark
- 19 -
We=nL2/2R+vd/10R1/2
We=2*72/2*100 + 50/10 100
=0.99m
Therefore provide 1m widening, 0.5m on both sides of the road
2.4. 2 Super-elevation
Super elevating on curves is intended to counter act of the centrifugal
force, the remaining part being resisted by the lateral friction. Also,
super-elevating results in economics in maintenance. This is because
skidding and unequal pressure on the wheels of vehicles, which
results from high value of side way force between the tyres and the
road way surface, give rise to potholes and necessitate frequent
attention to the surface.
Generally super-elevation rate, e is the raising of the outer edge of the
road along a curve
in order to counteract the effect of radial centrifugal force in
combination with the friction between the surface and tyres developed
in the lateral direction.
- 20 -
In the second stage the surface of the road is rotated about the centre line of
the carriage way and gradually lowering the inner edge keeping the level of
the centre line (crown) constant as shown on the diagrams.
with spiral
The method of attainment is by rotating the surface about the centre of the
road.
Curve one
At the entrance of the curve
Tangent run out (crown runoff) section: Length of roadway needed to
Accomplish a change in out-side cross slope from normal cross slope
Rate to zero which is the tangent distance needed to avoid sudden change.
It is computed from geometry of the cross slop and design supper elevation
as follows
First the vertical distance b/n the edge to centre of the road , y, can be
calculated from the width of the lane and cross slope as
Y=w*s
Where
w= lane width
S=cross slope
Y=7m*2.5%
Y=0.175m
Then the longitudinal length required is determined from y and design
supper elevation
Lt=y/e
Lt=0.175/0.04
== 4.375m
- 21 -
- 22 -
The inner edge starts to rotate at a distance equal to tangent run out
from the point where the out-side cross slope is zero.
L=4.375m
The full supper elevation is attaining at sc. which is 4%as shown in the
fig.
Curve two
At the entrance of the curve
Tangent run out (crown runoff) section: Length of roadway needed to
Accomplish a change in out-side cross slope from normal cross slope
Rate to zero which is the tangent distance needed to avoid sudden change.
It is computed from geometry of the cross slop and design supper elevation
as follows
First the vertical distance b/n the edge to centre of the road, y, can be
calculated from the width of the lane and cross slope as
Y=w*s
Where
w= lane width
S=cross slope
Y=7m*2.5%
Y=0.175m
Then the longitudinal length required is determined from y and design
supper elevation
Lt=y/e
Lt=0.175/0.04
== 4.375m
use 5.00m
- 23 -
- 24 -
from
y and design
The full supper elevation is attain at sc.which is 4%as shown in the fig.
- 25 -
in to the tangent
- 26 -
- 27 -
- 28 -
general appurtenance
50km pr hr
Rolling
7%
9%
0.5%
55
175m
Station of PVI
0+100
Elevation
2105.294
Gradient, g1
-0.508%
Gradient, g2
-2.086%
A= g2-g1
A=-.02086-(-0.00508) =/-0.01578/
1.57%
= 0.0157
or
=10*1.578
=15.78m
2. Length required for safe stopping
when Sd < Lc
L = 2SD -2(h1+h2+2 h1 * h2
A
Lc=2*55-2(1.2+0.15+2 1.2 * 0.15
1.578
Lc=-168.65m
3. Length required for safe passing
A
L = 2SD -2(h1+h2+2 h1 * h2
Lc=2*175-2(1.07+1.3+2 1.07 + 1.3
1.578
Lc=-249.34m
Here the negative sign indicates that the curve length is visible
and no need for sight distance consideration.
4. Length required for passengers comfort
Lc = Vd2*A
3.89
=50*50*1.578
3.89
= 10.14m
5.
- 31 -
L
2
2
Y=e*x
= -0.000039 x2
Therefore
Ex = 2117.151-0.05375-0.001164 x2
All the values at full station are shown on the table attached
bellow.
Location of the highest points on the curve is required for
the determination of drainage patterns, and computed as
follow
Location
X m =-g1*L
A
= . 508*200
1.578
= 64.38m
There fore the highest point is at 0+64.38 from pvc
The elevation of the curve at this poet
Ex = 2105.802 - 0.00508x + 0.00003965 x2
Ex = 2105.802 - 0.00508(64.38) + 0.00003965(64.38)*64.38
=2105.3106
- 32 -
Table 1
station dista.
0+000 0
0+003 3
0+020 20
0+040 40
0+060 60
0+080 80
0+100 100
0+120 120
0+140 140
0+160 160
grade
0.00508
0.00508
0.00508
0.00508
0.00508
0.00508
0.00508
0.00508
0.00508
0.00508
0+180 180
0+200 200
e
0.00003965
0.00003965
0.00003965
0.00003965
0.00003965
0.00003965
0.00003965
0.00003965
0.00003965
0.00003965
elevation
2105.802
2105.802
2105.685
2105.535
2105.354
2105.142
2104.898
2104.621
2104.314
2103.974
Gr.elevation cut/fill
2105.802
2106.109
2106.466
2106.636
2106.205
2105.935
2105.568
2105.084
2104.402
Curve two
Sag curve
Station of PVI = 0+330
Elevation
= 2102.913
g1 = -0.02086 = 2.086 %
g2 = 0.05372 = 5.0375%
A = g2-g1
=.05372-(-0.02086)
=0.07458 =7.458%
Computation of the curve length
1. Curve length required for minimum curvature, k
L =AK
= 7.458*12 =890496
2. Length required for safe stopping
When Sd< Lc
Lc = Sd2*A / 2(hasten )
- 33 -
remark
pvc
0
0.42446
0.93064
1.28154
1.06316
1.0375 pvi
0.94656
0.77034
0.42784
0.15294
-0.462 pvt
Where for sag curve, the height from the ground to the
eye of the driver, h =0.6 and
The angle b/n the ray from the observers eye to the object , =
1o
Then, the required curve length is:
Lc =552*0.07458 /2(0.6+55tan1)
= 72.3078m
3. Length required for safe passing
Lc = 2*Sd - 2(hasten )
A
Lc = 2*175 2(0.6+ 175tan1)
0.07458
Lc = 251.994m
To get full station, lets use Lc =260m
4. Length required for passengers comfort
Lc = Vd2*A
3.89
Lc = 47.93
Length required for aesthetic (appearance)
Lc = 30 *A
Lc = 30*7.458
= 223.74m
there fore the maximum of the above values i.e. Lc = 260m is to
be provided as curve length.
determination of the curve elements
station of PVI =0+330
Elevation = 2102.912
station of PVC = phi- L1
= 0+330 - 130
=0+200
Elevation
= 2103.200
station of PVT =PVI + L2
=0+330 + 130 = 0+460
Determination of elevations on the curves at x distance from PVC
(STATION 0+200)
EX = Epic + g1 + y
where y =offset at x distance from pvc
= (g2-g1)*L*4x2
800*L2
= 7.458*260*4*x2
800*260*260
5.
- 34 -
=0.0001434 x2
Therefore
Ex = 2103.2 - 0.02086x + 0.00014348 x2
all the values are shown on the table attached bellow.
location of the lowest points on the curve is required for the
determination of drainage patterns, and computed as follow
location
Xm =-g1*L
A
= 2.086*260
7.458
= 72.72m
from PVC (0+200)
There for the location of the lowest point is at
0+272.7
Elevation of the curve at this station is:
E0+272.72 = 2102.913 - 0.02086*72.72 +0.0001434*72.722
= 2102.150
TABLE 2
station
0+220
dista.
20
grade
0.02086
e
0.00014348
elevation
2102.84
Gr.elevation
2102.425
cut/fill
-0.415192
0+240
40
0.02086
0.00014348
2102.595
2102.164
-0.431168
0+260
60
0.02086
0.00014348
2102.465
2102.023
-0.441928
0+280
0+300
0+320
0+340
0+360
0+380
0+400
0+420
0+440
0+460
80
100
120
140
160
180
200
220
240
260
0.02086
0.02086
0.02086
0.02086
0.02086
0.02086
0.02086
0.02086
0.02086
0.02086
0.00014348
0.00014348
0.00014348
0.00014348
0.00014348
0.00014348
0.00014348
0.00014348
0.00014348
0.00014348
2102.449
2102.549
2102.763
2103.092
2103.535
2104.094
2104.767
2105.555
2106.458
2107.476
2102.009
2101.897
2102.046
2102.145
2102.737
2103.56
2104.509
2105.51
2106.5
2107.526
-0.440472
-0.6518
-0.716912
-0.946808
-0.798488
-0.533952
-0.2582
-0.045232
0.041952
0.050352
Curve three
Crest curve
Station of pvi =0+740
Elevation =2121.361
=0+740
- 35 -
remark
pvc
pvt
4.655
Lc=15.50m
3. Length required for safe passing
L = 2SD -2(h1+h2+2 h1 * h2
A
Lc=2*175-2(1.07+1.3+2 1.07 + 1.3
4.655
Lc=146.83m
4 . length required for passengers comfort
Lc = Vd2*A
3.89
=50*50*4.655
3.89
= 29.92m
5. Length required for aesthetic (appearance)
Lc = 30 *A
=30*4.655
=139.65m
There fore the maximum of the above values i.e. Lc = 146.83m is
less than the minimum curve length recommended by ERA2001
,which is LC=200m. so this value is provided as curve length.
Determination of the curve elements
By providing symmetrical curve of equal tangent length
L1=L2=
L
2
=100m
- 36 -
=0+640
Elevation = 2121.361
Station of PVC = phi- L1
=0+740+100
=0+840
Elevation
2117.151
= 2103.200
station of PVT =PVI + L2
=0+740+100=0+840
=0+840
Elevation
=2123.240
Determination of elevations on the curve at x distance from
PVC (station 0+200)
EX = Epvc + g1 + y
Where y =offset at x distance from pvc
= (g2-g1)*L*4x2
800*L2
where
e=4(g2-g1)*L
800*L2
2
Y=e*x
= -4.655*x2
200*200
= -0.001164 x2
Therefore:
Ex = 2117.151+0.05375x-0.001164 x2
all the values are shown on the table 3 attached bellow.
Location of the highest points on the curve is required for
the determination of drainage patterns, and computed as
follow
Location
Xm =-g1*L
A
= 5.375*200
4.655
= 240.73m
This value shows that the curve is an increasing curve
- 37 -
Table 3
station
dista.
grade
elevation
Gr.elevation
cut/fill
0+640
0.05375
0.00011652
2117.151
2117.572
0.421
0+660
20
0.05375
0.00011652
2118.179
2118.827
0.6476068
0+680
40
0.05375
0.00011652
2119.115
2119.586
0.4714272
0+700
60
0.05375
0.00011652
2119.957
2120.268
0.3114612
0+720
80
0.05375
0.00011652
2120.705
2121.028
0.3227088
0+740
100
0.05375
0.00011652
2121.361
2121.518
0.15717
0+760
120
0.05375
0.00011652
2121.923
2121.843
-0.0801552
0+780
140
0.05375
0.00011652
2122.392
2122.367
-0.0252668
0+800
160
0.05375
0.00011652
2122.768
2122.973
0.2048352
0+820
180
0.05375
0.00011652
2123.051
2123.377
0.3261508
0+840
200
0.05375
0.00011652
2123.24
2123.788
0.54768
Curve four
Sag curve
Station of PVI = 1+170
Elevation
= 2124.176
g1 =0.0072 =0.72%
g2 = 0.0572 = 5.072%
A = g2-g1
=.0572-(-0.0072)
=0.05 =5
- 38 -
remark
EX = Epic + g1 + y
where y =offset at x distance from pvc
= (g2-g1)*L*4x2
800*L2
= 5*200*4*x2
800*200*200
y= ex2
=0.000125 x2
therefore
Ex = 2124.896 - 0.0072x + 0.000125 x2.
All the values at each full station are shown on the table4
attached bellow.
Location of the lowest points on the curve is required for the
determination of drainage patterns, and computed as follow
location
Xm =-g1*L
A
= 0.0072*200
0.05
= 28.80m
from PVC (1+070)
There for the location of the lowest point at that station(1+098.80)
is
E1+098.80 = 2124.896 0.0072*28.8+0.000125*28.8*28.8
= 2124.585
Table 4
station
1+070
1+080
1+100
dista.
0
10
30
grade
0.0072
0.0072
0.0072
e
0.000125
0.000125
0.000125
elevation
2124.896
2124.981
2125.225
Gr.elevation
cut/fill
2124.353
2124.578
-0.6275
-0.6465
1+120
1+140
1+160
1+180
1+200
1+220
1+240
1+260
1+270
50
70
90
110
130
150
170
190
200
0.0072
0.0072
0.0072
0.0072
0.0072
0.0072
0.0072
0.0072
0.0072
0.000125
0.000125
0.000125
0.000125
0.000125
0.000125
0.000125
0.000125
0.000125
2125.569
2126.013
2126.557
2127.201
2127.945
2128.789
2129.733
2130.777
2131.336
2125.053
2125.663
2126.365
2126.995
2127.745
2128.659
2129.672
2130.646
-0.5155
-0.3495
-0.1915
-0.2055
-0.1995
-0.1295
-0.0605
-0.1305
Curve five
- 40 -
remark
pvc
pvt
Crest curve
Station of VPI =1+440
Elevation = 2139.827
g1 =0.0572=5072%
g2=0.005=0.5%
A=0.005-0.0572
=/-0.0522/ =0.0522
Determination of the curve length
1. Length required for the minimum curvature
Lc=A*K
=10*5.22
=52.2m
2.Length required for stopping
When Lc<Sd
Lc=2*55-2(1.2+.15+2
5.22
=25.76m
3. Length required for safe passing
When Sd > L
Lc=2*175 2(1.07+1.3+2
5.22
=168.82m
4. Length required for aesthetic
Lc=30*A
=30*5.22
=156.60m
Hence all the above values are less than the minimum
requirement, for this curve the minimum curve length
recommended by ERA2001, which is 200m is used.
Elements of the curve
By providing symmetrical curve
L1=L2=L/2=100
Station of VPI =1+440
Elevation = 2139.827
Station of pvc =(1+440)-100
=1+340
Elevation =2135.421
Station of pvt =(1+440)+100
- 41 -
of
equal
tangent
length,
=1+540
Elevation=2141.632
Elevation of the curve, Ex ,at x distance from pvc (1+340)
Ex=Evpc+g1x - y
Where y=Ax2
200*L
= 5.22*X2
200*200
Y =0.0001305X2
There fore
Ex=2135.421+0.0572-0.0001305x2
Location of the highest point on the curve
X m =-g1L
A
=5.72*200
5.22
=219.15
This shows that the curve is an increasing curve and no drainage
problem
Table 5
station dista. grade e
elevation Gr.elevation cut/fill remark
1+340 0
0.0572 0.0001305 2135.412 2135.557
0.145
pvc
1+360 20
0.3382
1+380 40
0.5778
1+400
1+420
1+440
1+460
1+480
1+500
1+520
1+540
0.0572
0.0572
0.0572
0.0572
0.0572
0.0572
0.0572
0.0572
0.5878
0.4582
0.425
phi
0.2762
0.1458
0.3968
0.8702
1.185
pvt
60
80
100
120
140
160
180
200
0.0001305
0.0001305
0.0001305
0.0001305
0.0001305
0.0001305
0.0001305
0.0001305
- 42 -
2138.374
2139.153
2139.827
2140.397
2140.862
2141.223
2141.48
2141.632
2138.962
2139.611
2140.252
2140.673
2141.008
2141.62
2142.35
2142.817
- 43 -
Unit three
ROAD CROSS SECTIONS
3.1 INTRODACTION
A cross section will normally consist of the carriage way,
shoulders, or curbs, drainage features and earth work profiles.
3.2 Carriage way: the part 0f the road constructed for use by
moving traffic. Includes
Traffic lanes
Auxiliary lanes such as acceleration and declaration lanes
Climbing lanes
Passing lanes
3.3 Road way: consists of the carriage way and shoulders and
parking lanes.
3.4 Earth work profile: includes side slop and back slope.
For urban cross section cross section elements may also
includes facilities for
Pedestrians
Cyclist
And other special user groups these includes curbs, foot
way and islands. Since this particular project is urban and
design standard four (DS4) ROAD it contains the above
mentioned elements.
Lane width and shoulder width should be adjusted to traffic
requirements and characteristics of the terrain. The cross
section may vary over the particular rout because of these the
terrain but for this particular project all the cross sections are
assumed to be equal because the terrain and the traffic
character are constant thought the entire road.
3.5 LANE WIDTH
Feature of a high way having great influence on safety and
comfort in the width of the carriage way, due to this we use a
lane width of 3.5 mare used which is recommended for DS4
road are shown in table 2.1 ERA2001 for all roads design
standards.
- 44 -
3.6 SHOULDERS
Shoulders is a portion of the road way contiguous to carriage way
for the accumulation of stopped vehicles, traditional and
intimidate non motorized traffic, animals, pedestrians and
emergency use. And also used for the recovery of stopped vehicles
and lateral support of the pavement course. Shoulder width are
specified on ERA 2001 standards for this particular project we
choose a shoulder width of 3.5 m. where the carriage is paved the
shoulder also be sealed with single bituminous surface treatment
.
3.7 NORMAL CROSS FALL
Normal cross fall should be sufficient to provide adequate surface
drainage whilst not being so great as to make steering difficult.
According to ERA normal cross fall should be 2.5%on paved roads
and 4% on unpaved road. Shoulders are the some as normal
cross fall. Since the project is paved road we take a normal cross
fall of 2.5%for all the shoulders and carriage way.
3.8 SIDE SLOPE AND BAK SLOPE
Side slopes and back slopes should be designed to insure the
stability of the road way and to provide a reasonable opportunity
for recovery of un out of control vehicle.
Three regions of road side important which evaluating the
safety of aspect of such as
The top of the slope (hinge point)
The side slope
The toe of the slope (intersection of the for slope and with level
ground or with back slope )
The selection of a side slope and back slope is depend on safety
consideration , height of cut or fill and economic consideration
.ERA 2001 table 6.1 indicates the side slope recommended for
use in the design according to the height of cut and fill and the
material.
Depending to the given standard ratio our project is designed
and set out the appropriate and economical road section.
- 45 -
- 46 -
Chapter three
EARTH WORK AND QUANTITY
3.1 INTRODACTION
Earth work is conversion of natural condition to required section and
grade. Earth work in high way design includes determination of cuts
and fills, location of borrow, waste sites, the free haul and over haul
distance determination.
The most common item of work encountered in high project is earth
work. the estimation of earth quantities that deserves a detailed
treatment. According to ERA specification the rate of earth work in it
such as
Excavation in borrow area
Transporting to the site of embankment including all lifting and
loads not greater than 50 meter.
The quantity of work in embankment and cuts are computed by the
cross sectional end area method. The area of earth work in each cross
section is computed by the help of mm paper or Plano meter and also
can be calculated by using soft ware programs.
- 47 -
- 48 -
10 x10
0 x1
0 x2 5 x3
10 x4 12 x5
10 x67 x7
0 x8
-7 x9
-13 x11
-9.8 x12
-5 y1
24.94 y2
24.74 y324.8 y424.8 y5
23.59 y623.5 y7
23.67 y823.5 y9
23.59 y10
25.2 y11
25.2 y12
24.91 9.962
0 0
5 10
12.2
10
7 0 -7 10 -14 -10
-5 24.98
24.9 25.16 25.16 23.88 23.79 23.96 23.79 23.88 25.76 25.66 25.03 18.77
-5
10
10.5
10
5
0 -5
-5 10
-13 -10
-10
-5 24.54
6.109 24.36
6.188 24.45
5.982 5.902
5.56 24.07
5.56 24.08
5.685 23.85
5.56 23.88
5.56 23.88
6.794 6.679
-12.8
0 0
0
7 10
12.5
8
5 0
10 -13
-7
23.95 23.95
24.45 6.308
24.36 35.02
-7
12
10
7
-5
5.45 24.27
5.41 24.34
5.535
5.41 23.85
5.45 24.85
6.904 6.904
0 0
0
7 10
10
13
10
5 0
0 -5
-5 10
-13 -10
-10
-7 6.466
24.84 6.524
24.65 6.434
24.39 6.434
23.6 23.07
24.4
24.39 6.606
24.65 34.56
6.143
10 -13
-5
12.3
10
5
-14 -10
-10
-5 25.23
6.636 25.05
6.549 25.06
6.544 24.37
6.544 24.37
5.27 24.54
5.229 24.58
5.354 24.49
5.22
5.27
6.936 6.836
17.3
0 0
0
7 10
10
12.5
10
5 0
0 -5
-5 10
10 -15
-7
24 23.49
25.06 6.644
25.05 32.25
-5 10
10
13 9.8
10
5
-13 -10
-10
-5 26.01
6.205 25.84
6.355 25.93
6.323 6.523
5.04 25.53
5 5.142
5 25.48
5.04 6.405
0 0
0
7
11
5 0
0 -5
-5 10
10 -13
-7
25.58 25.57
25.66 25.45
25.5 6.305
25.93 6.253
25.84 31.91
33.66
-0 0
0
7
13.5
10
7 0
0 -5
-7 10
10 -12
-10
-7 5.568
5.506 27.12
5.438 27.16
5.68 4.536
4.446 4.621
5.5 7.196
33.02
0
7 10
10
11
10
5
-11 -10
-7
27.2 27.03
27.16 26.91
27 4.446
26.85 4.526
26.95 5.256
26.95 5.356
27.12 27.03
-0
5
11.8
10
5
-12 -10
-10
-7 38.07
4.402 38.85
4.598 38.83
4.522 4.522
3.88 37.32
3.8 3.974
3.88 38.95
4.4 38.95
4.486 37.92
4.39 1.024
0 0
0
5 10
10
12.7
10
7 0
0 -7
-7 10
10 -13
-5
38.82 37.32
37.49 3.799
37.32 37.41
22.83
-0
5
12
10
5
-5
3.2 39.43
3.186 39.69
3.166 2.879
3.115 39.07
3.18 2.738
3.1 39.99
3.1 39.99
3.115 39.45
3.1
3.1
0 0
0
5 10
10
12
10
7 0
0 -5
-7 10
10 -11
-12 -10
-10
-5 39.61
39.7 38.98
39.15 2.928
38.07 38.98
16.2
-0 0
0
7 10
10
11.5
10
5 0
0 -7
-5 10
10 -11
-10
-7 40.67
2.595 40.56
2.42 40.41
2.51 40.41
2.253 40.31
2.25 40.22
2.442 2.164
2.682 40.31
2.42 40.65
2.42 40.63
2.42 40.43
2.42 0.692
0
5
10.5
10
7
-11 -10
-5
40.4 40.22
18.63
-0
7
14.2
10
5
-7 4.3
2.3 0.994
2.247 41.14
2.049 41.65
2.364 2.274
2.28 13.61
0 0
0
5 10
10
11.5
10
7 0
0 -4
-7 11
-12 -10
-5 2.449
41.62 2.274
41.54 41.64
41.65 2.304
41.14 2.097
41.05 2.009
41.22 41.05
41.65 41.54
9.933
10 -10
--0
7
11.5
10
5 0
0 -7
-5 10
-11 -10
-10
-7 42.35
2.549 42.25
2.347 42.08
2.464 1.414
2.47 2.464
0 0
0
5 10
10
12
10
7
10 -13
-5
42 2.321
41.4 2.045
41.31 1.897
41.48 2.247
41.31 2.247
41.4 42.82
42.81 2.374
42.37 3.226
14.23
0 0
7 10
11
10
7 0 -5 10 -15 -10
-7 2.763 2.588 2.678 2.436 2.436 2.429 2.046 1.051 1.026 1.029 2.678 2.588 50.62
0 0
7 10
12.7
10
5 0 -5 10 -13 -10
-7 3.535
3.36
3.45 2.646 2.174 2.763 2.737 2.667 2.906 2.909
3.45
3.36 10.64
11
10
10
11
10
11
10
10
12
10
10
13.5
10
10
11.1
10
10
10.6
10
5 9.5
12.6
10
-7 10
-7 10
-7 10
-7 10
-7 10
-7 10
-7 10
-7 10
-12
-10
-11
-10
-11 -9.3
-5 9.706 9.563 9.758 9.958 9.541 9.451 9.626 9.451 9.541 10.24 10.24 9.696 25.35
-5 11.77 11.06 11.66 11.65 11.69 11.01 11.78
11.6 11.69 11.89 11.89 11.64 3.504
-13
-10
-5 13.81 13.72 13.72 13.72 13.84 13.75 13.92 13.75 13.84 13.72 13.72 13.35 1.088
-5 16.23
15.9
16.8 15.99 15.99
15.9 16.08
15.9 15.94
16.9 16.87
16.2 9.038
-12
-11
-5 18.83 18.87
-11
-11
-13
-11
-13 -9.4
18.9
18.9 18.09
0.68 FILL
8.029
3.47 FILL
-25.7
8.33 CUT
24.7
- 49 -
18 18.18
Where
9 V= volume in m3
9 A1and A2 is area of successive cross-section in m2
9 L= distance between successive cross section in m in this case
we use 40m.
The average end area method is simple and is generally preferred by
most high engineers, so we choose this method for this particular
project
The volume computed by this formula is likely to be higher than the
true value in the case of the section changing rapidly.
- 50 -
estimate of quantities
Rate of abstract of work
Shrinkage and swelling should be included in estimating the quantities.
According to ERA 2001 there is a recommended shrinkage and swelling
factor there fore the following tables show the recommended values of
Shrinkage factors
Type of soil
Shrinkage factor
Light soil (ordinary ground)
10-25%
Light soil(swamp ground)
20-40%
Heavy soil
up to10%
cut
Fill
Cut
Cut
Adjusted Fill
Fill
section volume Cut
section volume
m2
m3
volume
M3
M2
3
m
Cumulat
ive
adj
volume
fill
volume or mass
ordinate
m3
M3
- 51 -
- 52 -
distance
20
40
60
80
120
160
200
240
280
300
320
360
420
460
500
540
580
620
660
700
740
780
820
860
900
940
980
1020
1060
1100
1140
1180
1220
1260
1300
1340
1380
1420
1460
1500
1520
total
cut
16.62
27.60
33.70
30.62
24.63
15.41
0.00
0.00
0.00
0.00
0.00
0.00
4.12
3.58
7.42
0.00
0.00
8.33
19.53
10.87
2.25
0.50
10.90
24.54
32.44
31.59
2.00
0.00
0.00
0.00
0.00
0.00
0.50
0.90
0.80
2.50
27.40
18.99
7.38
12.31
24.16
fill
0.00
0.00
0.00
0.00
0.00
0.00
-1.69
-1.78
-4.06
-6.69
-21.86
-17.51
-1.00
-0.51
0.00
-0.68
-3.47
0.00
0.00
0.00
-1.30
-2.20
0.00
0.00
0.00
0.00
-3.50
-10.60
-14.02
-16.83
-8.11
-3.08
-1.80
-1.40
-3.00
-1.00
0.00
0.00
0.00
0.00
0.00
factored
fill
0.00
0.00
0.00
0.00
0.00
0.00
-2.11
-2.22
-5.07
-8.36
-27.32
-21.89
-1.25
-0.64
0.00
-0.85
-4.34
0.00
0.00
0.00
-1.63
-2.75
0.00
0.00
0.00
0.00
-4.38
-13.26
-17.53
-21.04
-10.13
-3.85
-2.25
-1.75
-3.75
-1.25
0.00
0.00
0.00
0.00
0.00
- 53 -
avg
area
8.31
22.11
30.65
32.16
27.62
20.02
5.60
-2.16
-3.65
-6.72
-17.84
-24.61
-8.89
0.85
5.18
3.28
-2.59
2.00
13.93
15.20
5.75
-1.06
4.08
17.72
28.49
32.02
13.61
-8.82
-15.39
-19.29
-15.59
-6.99
-2.80
-1.55
-2.35
-1.25
14.32
23.19
13.18
9.84
18.24
length
17
20
20
20
40
40
40
40
40
20
20
40
80
40
40
40
40
40
40
40
40
40
40
40
40
40
40
40
40
40
40
40
40
40
40
40
40
40
40
40
20
volume
141.24
442.16
612.95
643.13
1104.98
800.83
223.83
-86.59
-145.86
-134.36
-356.87
-984.33
-711.11
33.85
207.17
131.31
-103.76
79.86
557.17
608.05
229.99
-42.50
163.08
708.84
1139.60
1280.62
544.28
-352.60
-615.68
-771.41
-623.46
-279.65
-112.03
-62.00
-94.00
-50.00
572.92
927.75
527.34
393.72
364.76
cumulative
volume
141.24
583.40
1196.35
1839.48
2944.46
3745.29
3969.12
3882.53
3736.68
3602.31
3245.44
2261.12
1550.01
1583.86
1791.03
1922.34
1818.58
1898.44
2455.61
3063.67
3293.66
3251.16
3414.24
4123.07
5262.67
6543.29
7087.57
6734.97
6119.29
5347.88
4724.43
4444.78
4332.75
4270.75
4176.75
4126.75
4699.67
5627.42
6154.76
6548.48
6913.23
Le=Cb /Coh
Where we assumed that
Ce=5birr/m3
C b=10 birr/m3
C oh=1 birr/m3-station and one station = 20m
There fore Le=Cb/Coh =10/1=10 station=200 m
And we assume also free haul distance F=300m
Therefore LT=300+200=500M
To calculate the over haul we see each loop in the mass haul diagram
1st loop
- 55 -
=118,978.3975birr
Borrow cost=0 no borrow requirement
Over haul cost=8.5 station x (2000-1500) x 1birr/station=4250birr
Total
cost=118,978.3975birr+4250bir=123,228.397birr
- 56 -
Chapter five
5. Highway Drainage
High way drainage is the process of removing and controlling excess surface
and sub-surface water within the right of way. The includes interception and
diversion of water from the road surface and sub-grade.
During rains, part of the rain water flows on surface and part of it percolates
through the soil mass as gravitational water until it reaches the ground
water below the water table. Removal and diversion of surface water from the
roadway and adjoining land is termed as surface drainage. Diversion or
removal of excess soil-water from the sub grade is termed as sub-surface
drainage.
Importance of highway drainage
An increasing moisture content cause decrease in strength or stability of soil
mass; the variation in soil strength with moisture content also depends on
the soil type and the mode of stress application. Highway drainage is
important because of the following reasons:
Excess moisture in soil sub grade causes considerable lowering of
its stability. The pavement is likely to fail due to sub grade failure.
In some clay soils variation in volume of sub grade. This sometimes
contributes to pavement failure.
Sustained contact of water with bituminous pavements causes
failures due to stripping of bitumen from aggregates like loosing or
detachment of the bituminous pavement layers and formation of pot
holes.
The prime cause of failures in rigid pavements by mud pumping is
due to the presence of water in fine sub grade soil.
Excess water in shoulders and pavement edge causes considerable
damage.
Erosion of soil from top of un surfaced roads and slopes of
embankment, cut and hill side is also due to surface water.
Requirements of highway drainage system.
The surface water from the carriage way and shoulder should
effectively be drained off without allowing it to percolate to sub
grade.
The surface water from the adjoining land should be prevented
from entering the roadway.
The side drain should have sufficient capacity and longitudinal
slope to carry away all the surface water collected.
Flow of surface water across the road and shoulders and along
slopes should not cause formation of cross ruts or erosion.
Seepage and other sources of under ground water should be
drained off by the sub surface drainage system.
Highest level of GWT should be kept well below the level of sub
grade, preferably by at least 1.2m.
- 57 -
To
In the hydrologic analysis for a drainage facility, Some of the factors which
need to be recognized and considered on an individual site by site basis
include:
Hence the drainage should enable to drain the surface water efficiently;
the designer should determine peak flows with an acceptable approach or
hydrological methods.
In this project we use the rational formula , hence it is widely used for
- 58 -
WHERE
Q= peak flow in cubic meters per second m3/s
A= drainage area
Basic Assumptions
1. The peak rate of runoff (Q) at any point is a direct function of the average
rainfall intensity (I) for the time of concentration (Tc) to that point.
2. The recurrence interval of the peak discharge is the same as the
recurrence interval of the average rainfall intensity.
3. The time of concentration is the time required for the runoff to become
established and flow from the most distant point of the drainage area to the
point of discharge.
Procedure to determine Q.
We have asphalt, concrete and soil covered with grass
surfaces to be considered.
1. Select the appropriate C value.
The runoff coefficient (C) accounts for the effects of
infiltration, detention storage, evapo-transpiration, surface
retention, flow routing and interception.
- 59 -
w=
=0.61
- 60 -
T2=1199/2.5
=479.6s
- 61 -
use Tt=10min.
Q= CiA
Where A= TOTAL AREA
Q=0.61*0.0444*41.996
=1.14m3/sed
Hydraulic design
Pipe Diameter in meters
Compute the required pipe diameter using Manning's equation
based on full flow. The tail water is assumed to be at the elevation
of the pipe sofIt
From peak flow, Q and the velocity through the pipe ,it is
possible to get area of the pipe needed,
A=Q/V
A=1.14/2.5 =0.456m2
- 62 -
- 63 -
Q=9.10m3/sed
Hence 9.10m3/sed or the capacity of the pipe provided is
greater than the required one, which is 1.14m3/sed ,so it is
safe to use.
For the minimum slope case s=0.005
Q=1/0.013*(0.785*0.52/3*0.0051/2)q
Q=2.69m3/S
Hence 2.69 m3/sed or the capacity of the pipe provided is
greater than the required one, which is 1.14m3/sed ,so it is
safe to use.
- 64 -
- 65 -
Conclusion
First of all, to design a safe and economical highway through
the desired design period, social and environmental factors
and traffic volume should be studied.
Next to these, safe and economical geometric alignment
design is provided based on the limits set by
ERA2001manual and engineering judgments which are
related to the condition of the project. Survey data and
hydrological data are the basic to do the design.
Thirdly, providing appropriate gradients, which is the basic
factor which controls economy and aesthetic as well as
drainage of the highway.
In addition to the above, clear and precise working drawings
and typical sections, where ever necessary, are necessary for
the contractors and consultants.
- 66 -
- 67 -
- 68 -
REFERENCE BOOKS
1.
2.
3.
4.
AASHTO MANUAL
ERA MANNUAL
Internet Source
High way engineering , by new chanal and bros,roorkee(U.A)
8th edition.
5. Principles and practise
of high way engineering by
Dr.L.R.Kadiyali
Khanna publishers , third edition .
6. Standard hand book of civil engineering ,by gurcharan A.K
Jain publisher 9th edition .
- 69 -
- 70 -