Sei sulla pagina 1di 164

King Abdulaziz International Airport

Development Project (Phase -1),


Jeddah, KSA
Contract Title

: J-10-421-PF-0, J-10-422-PF-0

Construction Manager : Dar Al-Handasah


Contractor

: Saudi Binladin Group

PROJECT HSE PLAN

Submittal and Approval Record


Revision

Date

Reason

Submitted By

Reviewed By

Approved By

1-5-2011

Approval

SBG-Safety
Manager

CM Sr. Safety
Engineer

CM Project
Manager

Distribution List
Copy No.

Name

Organization

Designation

Eng. John MacDonald

DAR (CM)

Project Manager

Eng. John Selwyn Moses

DAR (CM)

Sr. Health & Safety


Engineer

Eng. louay khayat


Eng. Monib dalloul

SBG

Project Manager, P 421

SBG

Safety Manager, P 422

Date &
Signature

Item No.

Description

Page No.

Introduction

Document Control

REFERENCES

Definitions

4 -5

Hazard Analysis

5 -11

Traffic

11

Typical Safety Organization Chart

12

Company Safety Policy

13 -20

Safety Inspection

21 -22

10

Safety Reports & Records

22

11

Contractors Site Sanitation

22 -23

12

Work Permit

23 -24

13

Welding & Cutting Equipment

24 - 25

14

Personal Protective Equipment

25 -26

15

Tools & Portable Power Tools

26

16

Ladders

27

17

Electrical Installations & Equipment

27 -28

18

Scaffolding

28 -29

19

Crane & Lifting Equipment

29 -32

20

Mechanical Equipment

32 -35

21

Transportation and Traffic Safety

35 -37

22

Injury and Damage Reporting

37 -38

23

Excavations

38 -40

24

Fire Prevention

40 -42

25

Formwork

42

26

First Aid Facilities

42 -44

27

Dust Control (construction and road area)

44

28

Job site Inspections

44 -45

29

General Safety Rules

45

30

Emergency Procedures

45 -52
Page 1 of 59

31

Hazardous Material & Waste Management

53

32

Construction Site Security Procedures

53

33

Demobilization Plan

54

34

Abrasive Blasting & Painting/Coating

54

35

Lock Out and Tag out System

54

36

Safety Training & Meetings, Rewards and committees -

55 -58

37

Demolitions

58

38

Signage

58

39

Monitoring System Performance

58 -59

40

Records

59

ANNEX A

AND SEARCH & RESCUE OPERATIONS

A (1 7)

WASTE MANAGEMENT PLAN

B ( 1- 9)

EMERGENCY PROCEDURES
& FATAL ACCIDENT PROCEDURES

C( 1 13)

SAMPLE SAFETY FORMS

D ( 1 20)

PROJECT ENVIRONMENTAL PLAN

E ( 1 7)

SUMMARY OF STAFF RESPONSIBILITIES

F ( 1 4)

SCAFFOLDING PROCEDURES

G (1 9)

H (1 5)

REQUIREMENTS FOR HOT WEATHER


AND HEAT STRESS

K (1 4)

REQUIREMENTS FOR MEDICAL


FACILITIES

L (1 8 )

PERMIT TO WORK SCHEME

M (1 7 )

ANNEX B

ANNEX C

ANNEX D

ANNEX E

ANNEX F

ANNEX G

OFF ROAD DRIVING PROCEDURES

ANNEX H - REQUIREMENTS FOR SAFE


WORKING IN A CONFINED SPACE
ANNEX K
ANNEX L
ANNEX L

Page 2 of 59

1.0

INTRODUCTION

1.1

It is the policy of Saudi Binladin to implement a safety management system complying


with the applicable sections of OHSAS 18001:2007 and the Contract, as described in
the Corporate Quality Manual.

1.2

This plan is applicable to all of the activities in connection with the King Abdulaziz
International Airport Development project. King Abdulaziz International Airport
(KAIA) is located approximately 25 km North of Jeddah city centre and 90 km West of
Makkah, and has an estimated total land area of 105 km2. KAIA was commissioned in
1981, and has since become the busiest and the fastest growing airport in the Kingdom
of Saudi Arabia, providing commercial operations and acting as the gateway to the holy
cities of Makkah and Madinah.
The Government of the Kingdom of Saudi Arabia, Ministry of Defense and Aviation
and Inspectorate General, General Authority of Civil Aviation are expanding KAIA
which shall take place first development Phase for 30 million passengers capacity, is
scheduled to be completed by 2013.The Project currently consists of the following:1. Contract 421: Terminal Complex, Control Towers and Supporting
Facilities.
2. Contract 422: Aprons, Taxiways, Roads, Tunnels, Bridges, Load Centers
and Infrastructure, Transportation Center and Supporting Facilities

1.3

Reference should be made to the Project Quality Plan, which is the top-level document,
for a complete understanding of the management system applied to the project.

2.0

DOCUMENT CONTROL
The Project Safety Plan is a controlled document means a document that is registered
and has its distribution controlled so that a holder has the correct issue of the document
at all times. All amendments, revision, will be subject to CM review and approval.

3.0

REFERENCES

ISO 9001:2008 Quality management systems Requirements


OHSAS 18001:2007 Occupational health and safety systems Specification

Page 3 of 59

4.0

DEFINITIONS:

The following is a table of definitions for abbreviations used throughout this manual:
29-CFR-1926
AD
CLIENT
CM
CP
CPR
CSM
E&M Staff
EMS
ERT
FAC
FAT
FOD
GFCI
GI
HIP
LTA
LTAF
LTI
MS
MSDS
MTC
MVA
NAVAIDS
NM
OIH
OSHA
PEL
PPE
RTA
RWC
SAFETY

United States Code of Federal Register, Section 1926 (that


pertains to construction safety)
Asset Damages
The owner of a private project or a governmental authority for
public and government projects, for this project:
Clients Construction Management Team
Competent Person
First Aid Procedures
Construction Safety Manual
Electrical & Mechanical Staff
Emergency Medical Services
Emergency Response Team
First Aid Cases
Fatalities
Foreign Object Debris
Ground Fault Circuit Interrupters
General Instruction
Hazard Identification Plan
Lost Time Accidents
Lost Time Accident Frequency
Lost Time Injury
Method Statement Briefing
Material Safety Data Sheet
Medical Treatment Cases
Motor Vehicle Accident
Navigational Aids
Near Misses
Occupational Ill-health Cases
United States Occupational Safety & Health Administration
Permissible Exposure Limits
Personal Protective Equipment
Road Traffic Accidents
Restricted Work Cases
Department responsible for Safety Audits and Control in the
Page 4 of 59

SECTION
SAG
SBG
TRI
TRIR
TSA
UL
FM

5.0

project
Saudi Arab Government
SAUDI BINLADIN GROUP
Total Recordable Incidents
Total Recordable Incident Rate
Task Safety Analysis Briefings
Underwriters Laboratories
Factory Mutual Insurance Company

HAZARD ANALYSIS

Proposed Site Safety Advisor (and Safety Officers), shall conduct a walk-through of
the project site and shall identify potential hazard areas and/or situations, and record
the findings on the Plot Plan. A report will be submitted to the CM and as and when
require CM Safety Staff will join the walk-though.
Once the hazards have been identified, they are to be classified as Class A, B or
C to describe the potential severity as noted below:

Class A Hazards. A condition or practice likely to cause permanent disability,


loss of life or body part and/or extensive loss of equipment or materials.

Class B Hazards. A condition or practice likely to cause serious injury or


illness (resulting in temporary disability) or property damage that is disruptive, but
less severe than Class A.

Class C Hazards. A condition or practice likely to cause minor (non-disability)


injury or illness or non-disruptive property damage.

HAZARDS TO BE ADDRESSED
Outlined below are the various types of hazards typical in a construction site. In the event a
hazard has not been covered in the findings during HIP walk-through, the following will be a
guide to ensure all hazards are covered:

Page 5 of 59

a)

CLASS A HAZARDS
Activities

Description of Potential Hazard &


Preventive Measures

Temporary & Permanent Electricity

Distribution of electricity in the construction site


is different from a permanent installation.
Hazards will arise when unskilled or unqualified
electricians carry out electrical work. The use of
Lock-Out and Hold Tags maybe called for on
certain operations. The use of GFCIs is required
on all Construction sites.
Crane & critical lifts like equipment that will be
Crane & Critical Lifts
utilized for dynamic compaction & dynamic
replacement are major hazards. Where large or
heavy pieces of equipment, inexperienced
workmen, uncertified operators and unapproved
equipment are combined, accidents can occur.
Procedures as outlined in CLIENT Construction
Safety Manual & Crane Safety Handbook must
be followed.
Slings & Lifting Gear
Exceeding the safe working load of rigging
equipment, using un-inspected or damaged slings
or using untrained personnel can cause accidents.
Compliance with approved procedures as
outlined in the latest CLIENT Construction
Safety Manual and Crane Safety Handbook is a
must.
Welding, cutting and brazing are safe operations
Welding, Cutting & Brazing
if carried out in the correct manner. Where
equipment is defective, or there is no wellarranged plan to carry out this type of work,
hazards can arise. Ensure that only safe
equipments are being used and works carried-out
by competent personnel.
The use of sub-standard material, combined with
Scaffolding & Ladders
inexperienced, untrained and not certified
workmen, presents a hazard when using a
scaffold and ladder. Only competent, trained,
certified workmen will erect scaffolding,
supervised by Certified Scaffolding Supervisor
and inspected by a Certified Scaffolding
Inspector. Careful erection and inspection of
scaffolding is essential to prevent accidents.
Manholes/Excavations, Pits, Trenching & No ground containing an excavation can be relied
upon to support its own weight. No pit or
Shoring
manhole can be considered safe. Rescue
equipment and a procedure for a rescue operation
Page 6 of 59

a)

CLASS A HAZARDS
Activities

Overhead Obstruction

Road Construction & Re-routing of


Existing Roads {As prescribed By
CLIENT}

Concrete, Concrete Forms & Shoring

Sandblasting

Thrust Boring

Description of Potential Hazard &


Preventive Measures
must be in place prior to start of any work these
areas.
Should work be carried out in close proximity to
existing obstructions, specifically, hydrocarbon
related pipe bridges, caution shall be taken to
ensure that damage is not caused to CLIENT
facilities, or Contractors equipment or
employees during excavations or lifting
operations. Goal posts shall be installed to
establish a safe distance between work area and
overhead obstruction.
Several factors must be taken into account before
any road is blocked or re-routed. Prior to the
method of blockage being decided, or prime
importance are the methods of construction and
the surround hazards, i.e. high water table and
pump requirement, traffic flow at various times
of the day, etc. CLIENT and Safety Section shall
be notified prior to any proposed road blockage
or re-routing and traffic plan shall be submitted
for review/approval. Road blockage/re-routing
shall be made to comply with CLIENT General
Instructions.
This covers several area of work, all of which
present hazards. The placement of reinforcing
steel, concrete, vertical shoring, formwork and
shuttering, are but a few to the concerns that
should be considered in any HIP. Accidents can
be caused by employees actions/inactions, and/or
unanticipated failure of mechanical devices,
concrete forms or shuttering.
Sandblasting can cause hazards not only to the
operators, but also assistants and other people in
the area, if hydrocarbons are present, if
sandblasting equipment is incorrectly grounded or
if proper protective is not worn.
Boring underneath roadways can cause
subsidence, cave-in, damage to other underground
utilities and can create traffic flow disruption.
Prior to carrying out this work, a method
statement, including detour plan, shall be
submitted to CLIENT/Safety Section for
review/approval.
Page 7 of 59

a)

CLASS A HAZARDS
Activities

Hot Taps

Personal Safety

Paints & Coatings

Explosive Material
Piling Operations

Asbestos & Other Fibers

Demolition

Description of Potential Hazard &


Preventive Measures
Installation of hot taps by inexperienced
workmen, H2S presence, working in confined
areas and unmaintained hot tap machines, can all
cause accidents.
Incorrect types or sub-standard personal
protective equipment can lead to accidents. All
PPE must be made to comply with ANSI or
OSHA Standards. This includes hard hats, safety
glasses, safety shoes/boots and full body
harnesses.
Paints and coatings, improperly handled, stored,
prepared and applied, can cause harmful
conditions. Ventilation is a prime area of concern
in the application of any paint or coating being
applied on the Construction site. Note: See
Chemicals section of this program for details on
maintaining a MSDS. Additionally, special
attention must be taken in the storage of paints &
coatings.
Handling, storage, transportation and misfires
using explosives all can cause hazardous
conditions.
Widely used in constructions operations, piling
without good experienced workmen, well
maintained equipment and with the stress and
vibration imposed on that equipment, can lead to
hazardous conditions.
Asbestos has been widely used in the construction
industry, and is the generic name given to a
number of inorganic fibrous silicate minerals.
Disposal,
storage,
handling,
ventilation,
transportation and over exposure can all cause
hazardous conditions.
Many factors must be considered prior to any
demolition including the structures age, method
of construction, state of preservation, its previous
use, the type of material used in the construction
and/or renovations and the surrounding
environment (see the notes on Asbestos & Other
Fibers above). Accidents can happen when due
consideration is not given to all the foregoing, as
Page 8 of 59

a)

CLASS A HAZARDS
Activities

Chemical

Liquefied Petroleum Gas (LPG)

Fuel

Plant Operation & Hydrocarbon

Ionizing Radiation

Description of Potential Hazard &


Preventive Measures
well as cleansing and degreasing equipment.
Any chemical should be treated as hazardous.
Handling, storage, identification and labels which
are incorrectly tagged and spillages can cause
extremely
hazardous
conditions.
Follow
procedures as outlined in Contractors Safety Plan.
Material Safety Data Sheets (MSDS) shall be
established and maintained by the Contractor.
Liquefied Petroleum Gas (LPG), widely used in
the construction industry, is normally odourless,
colorless and heavier than air. In commercial
usage, an odorizing agent is added to facilitate
detection of accidental gas escapes. Incorrect
handling, storage or labelling can cause extremely
hazardous conditions.
Fuel incorrectly stored or mishandled can cause
accidents. Refuelling operations require special
attention. Fuel must not be stored or transported
in plastic containers. All containers, including
fuel tanks, must be grounded and bonded to the
equipment into which fuel is being transferred.
Berms are required to contain spillages in larger
fuel storage tanks.
Construction operations could affect the
movement of hydrocarbons if not planned and
performed in accordance with the standard
operating procedures.
Ionizing industrial radiation, such as X-Rays
generated by equipment or gamma rays emitted
spontaneously by radioactive materials, are
widely used for non-destructive testing, without
damaging the tested materials. However, they can
penetrate the human body, unknown, as the senses
cannot recognize them, causing living cells in the
body harm.

Page 9 of 59

b)

CLASS B HAZARDS
Activities

Description of Potential Hazard &


Preventive Measures

Heavy Equipment Operation

Heavy equipment operated by uncertified operators,


equipment lacking maintenance or lack of a back-up
spotter (banks-man) are potential hazards. These
operations could be reclassified as Class A if the
physical layout of the area offers additional hazards,
such tank farms, congested traffic flow, etc. Equipment
shall only be operated by certified and competent
operators who know the limitation of his equipment.

Material Handling

Material handling forms a large part of construction


work. How these materials are handled and stored can
have a considerable effect on the job safety. The type
of material being handled may require up-grading to
Class A Hazard and handling should also be
upgraded accordingly.

Hand/Power Tools

Power tools allow many jobs to be carried out more


efficiently and with greater speed and accuracy.
However, hazards will arise when unskilled and
untrained workers are allowed to operate hand/power
tools. Proper training and experience must be the
criteria for allowing a worker to use hand/power tools.

Site Office & Lay-down Yard

Site offices and lay-down yard, including flammable


storage facilities shall be constructed with safety and
efficiency in mind. Negligence of such factors could
lead to unfortunate incidents. All utilities shall be made
to comply with CSM requirement. Proper operation and
maintenance shall be established. Layouts shall be
submitted to CM /Safety Section for review/approval
prior to construction.

Mechanical Equipment

Mechanical equipment can cause hazard if the


operators are not properly trained and the equipment is
poorly maintained. Only trained operators shall operate
properly maintained equipment.

Page 10 of 59

c)

CLASS C HAZARDS
Activities

Sanitation & Housekeeping

6.0

Description of Potential Hazard &


Preventive Measures
A major factor influencing the health of
individuals is sanitation & housekeeping.
Diseases and sickness could easily be
transmitted without the practice of proper
sanitation and hygiene. And no work can be
considered as complete unless housekeeping
is done and done regularly. Waste disposal
system shall be established and maintained,
insect, rodent and pest control shall also be
conducted regularly.

TRAFFIC:

The general traffic plan applicable for this project at the commencement of the work shall be the
result of a careful study in the actual traffic flow in the area. Considering the nature of the project
area, an accurate traffic plan will be prepared by the field Safety Supervisor, specifically on the
working areas and will be distributed at various departments at site and implemented
accordingly, prior to start of work.

Page 11 of 59

7.0

TYPICAL SAFETY ORGANIZATION CHART

Note:

Resumes for the above proposed positions shall be submitted to CM for


review/approval.

Names shown could be changed depending on availability of personnel.

Page 12 of 59

8.0

COMPANYS SAFETY POLICY

Page 13 of 59

8.1
8.1.1

Contractors Responsibility
General

8.1.1.1 The Project Manager will issue from time to time an organisation chart showing the site
management team dedicated to executing the Works. As required by clause 4.4.1 of
OHSAS 18001:1999 the project management team will be sufficient in numbers and
suitably experienced and competent to perform the work and successfully implement
the management system.
8.1.1.2 The Project Manager has overall responsibility for all matters related to health and
safety and has assigned the management of this function to the HSE Advisor. The HSE
section has HSE Officers to assist in the discharge of this responsibility
8.1.1.3 The Project Manager shall assign responsibility for a particular task or function to a
member of his management team, and delegate the authority to enable him to perform
his duties; guidelines are given in the following sections. Notwithstanding such
assignment, overall responsibility remains with the Project Manager.
8.1.1.4

The Project Manager shall ensure that effective means of communication are put into
place to advise employees on safety issues. These are to include the display of notices,
regular toolbox talks and the facility at all levels of project management to discuss,
provide and source information.

8.1.1.5 The Project Manager shall take the lead in developing and promoting initiatives in
safety matters and shall use the management system to establish the required standards.
He shall monitor the performance of the workforce in achieving the targets set for the
project on a regular basis.
8.1.1.6 Managers and supervisors are responsible for implementing the management system
within their own area of the project. Queries on the application or interpretation of the
system are to be discussed with the HSE Manager or HSE Advisor who will be full time
available at site during working hours (dedicated). Personal name will be assigned prior
to any action being taken.
8.1.1.7

Each person is responsible for fulfilling his obligations under the system. A summary
of the basic responsibilities of project staff and workers with respect to occupational
health and safety is given in Appendix f.

8.1.2

Managers, Engineers and Supervisors

8.1.2.1 Every manager, engineer and supervisor who is responsible for staff and/or an area of
the project under his control has the following general safety responsibilities,
appropriate to the nature of his work:

He is to safeguard the health and safety of his permanent and temporary staff and of
others affected by his work.

Page 14 of 59

8.1.3

He is to ensure that all necessary risk assessments are carried out, that the work is
programmed to ensure compliance with the Contract, local legislation and the
Companys policies and procedures and that risk are monitored through regular and
systematic health and safety inspections of the work area.
He has a duty of care for all visitors and subcontractors.
He is to ensure that effective response arrangements are in place to deal with
incidents, accidents and emergencies.
He is to take all reasonable and practicable steps to ensure and improve the health
and safety at work of his staff, subcontractors and the general public.
He is to establish action plans to implement the objectives for improved safety
performance, in compliance with the system.
He is to ensure that arrangements are in place for fire precaution management.
He is to ensure that all staffs are trained with regard to safety responsibilities and
that the necessary information, instruction and training is provided to subcontractors
and visitors, as appropriate.
He is to ensure the efficient distribution and understanding of safety instructions and
publications.
He is to ensure that all necessary equipment and systems are provided and
maintained safe for use without known risks to health.
He is to ensure that all materials, new machinery and equipment purchased comply
with the any legislative requirements and/or the manufacturers recommendations
and that information is available to employees for safe use.
He is to ensure that the use, handling and storage of articles and substances are
conducted safely without known risks to health.
He is to pay special attention to the training of inexperienced employees or those
that have special needs.
He is to ensure that any issue raised by an employee that could reasonably be
foreseen as causing a threat or potential hazard is dealt with and reported to those
responsible for taking action and monitoring health and safety issues.
He is to ensure that personal protective clothing and equipments issued to staff are
appropriate.
He is to ensure that all practical steps are taken to provide a safe working
environment without known risks to health, including the reduction of noise or
sound levels to an acceptable degree.

HSE Department Personnel

8.1.3.1 The project management team is supported by the HSE team under the responsibility of
the HSE Manager.
8.1.3.2 The HSE Advisor has been designated as the Responsible Person on this project with
respect to the day-to-day management of health and safety issues. He and his team, as
applicable, have the following responsibilities:

To maintain regular and effective liaison with all levels of management and the
health and safety authorities.
Page 15 of 59

To investigate accidents and dangerous occurrences.


To monitor and maintain health and safety records.
To recommend changes to the management system as required.
To ensure that all personnel attend the site safety induction program and other
specific training modules.
To perform regular surveillance audits on our own workforce and our subcontractors
to identify compliance with the management system, including recommendations for
corrective or preventive action where appropriate.
To ensure that a system to record and monitor potentially hazardous substances
brought to site is in place.
To assist all the members of the project management team to work safely.
The HSE Advisor will report to the Project Manager.

8.1.3.3 The HSE Officers are responsible with respect to the day-to-day management of health
and safety issues. They have the following responsibilities:
To maintain regular and effective liaison with all levels of management and the
health and safety authorities.
To assist in the investigation of accidents and dangerous occurrences.
To develop and maintain safe working procedures and health and safety plans as
necessary for controlling site and associated office activities.
To ensure that all personnel attend the site safety induction program and other
specific training modules.
To perform regular inspections of subcontractors to confirm compliance with the
management system.
To ensure that a system to record and monitor potentially hazardous substances
brought to site is in place.
HSE Officers should be reporting to the dedicated HSE Advisor at the site.
8.2

Company Employees

Each employee has the personal responsibility to:

Take reasonable care for the health and safety of themselves, their fellow employees
and all other persons attending the workplace.
To co-operate with management in the performance of their duties and to work in
accordance with the management system policies and procedures.
To avoid intentionally or recklessly interfering with or misusing anything provided
in the interests of health and safety.
To call attention to any potential hazard and/or to raise any point relating to health
and safety issues by contacting their immediate supervisor and manager or, if they
are unavailable, the HSE Advisor or HSE Officers full time available at site.
To perform only those duties for which they are authorised and for which training
has been given.
To follow all project safety regulations and follow all additional rules those are
notified and apply to their particular area of work.
Page 16 of 59

8.3

Subcontractors and Visitors

Subcontractors and visitors are required to follow the management system by:

8.4

Taking reasonable care of the health and safety of themselves and others.
Co-operating with project management in the performance of their duties.
Avoiding intentionally or recklessly interfering with or misusing anything provided
in the interests of health and safety.

Safety Program

(1)
Purpose
The following presented program was developed to provide management and supervisory staff
with guidelines of the techniques and procedures essential for the protection of the companys
prime asset: its personnel.
We emphasize that the topics covered by this program will become the basic part of our policy.
All levels of supervisory staff shall be responsible for the procedures and standards stipulated
and that they are strictly adhered to and ensure a safer and more efficient operation in the field.
(2)

Safety Policies of the Company

The management of Saudi Binladin Group sets a high standard for the protection of its
employees in safety, health and welfare.
Production is not that urgent that we cannot allocate time so as to ensure that our work is carried
out in a safe and proper manner. Recognizing this and in the best interest of modern management
practices, we will be constantly working for:
a. The application of the safety rules and regulations, general instructions, codes and procedures
as lay down by CLIENT.
b. The maintenance of safe and healthy working conditions.
c. Constant adherence to safe operating procedures and practices so as to ensure effective
control against accidents and illness.
d. Providing an adequate and safe place to accommodate our personnel on site with potable
water, first aid facilities and proper sanitation.
e. To educate all personnel in the method of safety procedures, using personnel protective
equipment and advise them of existing restrictions unique to the working area.
f. A weekly Tool Box meeting will be conducted every Sunday each week at 0700 hours.
Selected employees will attend. Attendance will be taken and employees will sign the
attendees list (see Annex D, [A]-SP-01-S15).
g. Training will be given to workers on the use of Fire Equipment.
h. Safety posters, notices and video films relevant to site works will be made available and used
on the site.

Page 17 of 59

8.5

Safety Training Program

1. The Law and Safety


Statutory requirement
Appropriate regulations
Duties of employer and employee
Schedule D (Contractual Safety Requirements)
3. Safety and the Supervisor
Safety and efficient production go together
Accidents affect morale and public relations
5. Site Inspection
The role of management
Hazard Identification Procedure
Records results
Follow-up procedures
Feedback
7. Site Tidiness
Site
organization
Relationship of site housekeeping to accident
occurrence
Site
access
Equipment
storage
Material
stacking
Materials handling
9. Personal Protective Equipment
Eye, face, ear, hands, feet and leg protections
Respiratory protective equipment
Protection against ionizing radiation

11. Oxygen and Acetylene Equipment


Cylinder storage and maintenance
Condition and maintenance of valves, regulators,
and gauges
Condition and maintenance of hoses and fittings
Pressures
13. Transportation
Transport to and from site
Hazard connected with site transport
Competent drivers
Dumpers
Tipping trucks
Movement near excavations

2. Policy and Administration


Effect of incentive on accident prevention
Human relations
Consultation
Safety Officer: duties, aims, objectives
4. Principles of Accident Prevention
Attitudes of management, supervision and
operations
Methods of achieving safe operations
Accident and injury causes
6. Human Behaviour
Motivating agencies
Individual behaviour
Environmental effects
Techniques of persuasion
8. Health
Medical examination
Hazard to health on site
Sanitation and welfare
Protective clothing
First Aid/CPR
10. Electricity
Appreciation of electrical hazards
Power tools
Arc welding
Low voltage system
Lighting and power system on sites
Grounding/Ground fault circuit interrupters
(GFCIs)
12. Equipment
Accidents related to moving parts of machinery
Appreciation of principles of guarding
Importance of regular maintenance
14. Excavations
Method of shoring
Precautions while shoring
Precautions at edge of excavations
Removal of shoring
Sheet steel piling

Page 18 of 59

15. Working Places, Ladders, and Scaffolding


Hazards connected with the use of ladders
Maintenance and inspection
Type of scaffold
Overloading
Work on roofs
Fragile material
Openings in walls and floors
Use of safety belts and nets
17. Lifting Tackle
Slings single and multi-legged
Safe working loads (SWLs)
Safety hooks and eyebolts
Cause of failure
Maintenance and examination

16. Cranes and other Lifting Machines


Licensing, certification and training required for
operation of cranes
Slinging methods
Signalling
Access to crane(s)
Maintenance and examination
Ground
conditions
Hazards and accident prevention methods connected
with the use of different types of cranes/heavy
equipment
Crane Lift Plan for all lifts
18. Fire Prevention and Control
Principle causes determining fire
Understanding fire chemistry
Fire fighting equipment
Fire fighting training

19. Communications
Effective methods of communication (particular interest to non-English speaking workers)
Method and preparation of reports
Safety committees
Safety meeting

It has to be noted that the above training topics shall be adapted to be site-specific to cover the
scope of work and the various levels of workers being trained (i.e. engineers, foremen, ..etc.),
including managers and senior staff members.
8.6

Induction Safety Course for Workmen

The safety supervisor will present this course and it should be given to personnel at the following
times:
(1)
(2)

Upon worker(s) initial arrival in the Kingdom prior to deployment to worksite.


Change to new project or location where there are new/different/revised safety
rules/policy/practice/procedure different from previous project or location.

The following topics will be covered in this course:


a)

Health Exposure on and off site.


i) Personal hygiene
ii) Living Quarters cleanliness
iii) Smoking and eating while or after handling chemical materials.
iv) Hearing conservation
v) Respiratory Protection (where applicable)
vi) Handling Chemical Materials safely and identifying hazards of Chemical Materials.
Page 19 of 59

b)

First Aid/Medical Treatment Procedures:


1) Company Safety Policy
2) Excavations
3) Basic Material Handling - Mechanical and Manual
4) Tool Safety
5) Fire Prevention Protection

As mentioned under Section 8.5 (, Licensing, Certification and training required for
operation of Cranes), training (related to safety for cranes and heavy equipment) is
applicable to all the personal regardless of his position including Managers and Senior
Staff members.

SBG shall arrange Orientation Training in a brief manner to all who visit the Site
including Suppliers or any third party intend to be present at construction area.

Subcontractors shall be similarly briefed

SBG also, shall attach a sticker for all the personal inducted by the Safety Section
including Visitors and all site based non SBG staff also.
Containing the information below:
Company Name and logo
Induction no

Company Logo or Name


INDUCTED

Employee inducted date


Safety Reps Signature

Induction #
Inducted Date
Safety Reps Sig.

Employee #

M#

Alphabet as code for Trade (M- Mason)


Details shall be marked with a permanent marker.

Size Approx: 40 mm x 50 mm or enough to accommodate the information and in a


suitable color.

Above details shall be recorded in the Employees individual induction sign off form.

A pre briefing shall be conducted for any person prior to he is being brought to the site
about the location they are going to enter.

Page 20 of 59

9.0

SAFETY INSPECTION

(1)

In order to achieve uniformity and assure no element of the contractor safety inspection
program is being overlooked, the weekly site safety inspection checklist will be
completed.

(2)

A daily safety check list which shall be filled by the Safety Supervisor and Safety
Officers in their relevant areas and as and when noticed to report. A copy of which is
attached in Annex-D of this plan. It has to be noted that a weekly checklist shall be
prepared from the daily checklist as shown on Annex-D.

(3)

This check list does not replace any ongoing safety inspection procedures but reinforces
our safety program efforts.

(4)

These safety inspections will be carried out periodically (i.e. daily and weekly as noted)
by the contractor safety supervisor.

(5)

The inspection check sheet will be submitted to CM as part of the weekly job site
progress meetings. Corrective action items on the inspection check list can be a topic for
discussion at the weekly progress meetings, with follow-up action items to be discussed
each week until the items are cleared.

(6)

Checklist will be signed by all applicable parties as indicated on the form. A copy will be
maintained by Contractors Site safety Advisor.

(7)

Contractor site safety advisor shall monitor all construction activities to ensure that
services are performed in conformity with CM Safety Section Policies, and Contractors
HSE Plan, principles and practices, and do not imperil any person or property.

(8)

Contractor Safety Supervisor will perform a weekly inspection which will be recorded on
CLIENT form Weekly Site Inspection Checklist signed by all required and placed in
the Site Safety File for review by CM Safety Engineer as may be required. This
inspection would be more beneficial if the Contractors Project Management and
CLIENT Representative accompany the walk through. However, if CM does not have an
inspection form, SBG daily safety inspection check list shall be used and then compiled
and submitted on weekly basis to CM.

(9)

Site is aware that a CM Safety Engineer visits the site regularly to ensure that works are
being performed in compliance with Contractors HSE Plan. Findings of the visit shall
receive immediate corrective action, or a written justification provided to CM Safety
Staff by the close of business the following day.

(10)

An Observation Report (Non Conformance Report: NCR) or similar (see Annex-D) to


be filled by Safety Person and get the signature from the Supervisor responsible for the
violation with a time schedule for correction. One copy shall be handed over to
Supervisor and he shall return the same on completion to Safety Supervisor. The events
shall be categorized as follows:

Page 21 of 59

A for Stop work, immediate rectification in dangerous situation.


B for within 24 Hours if there is no immediate hazard.
C for with in negotiated period where no work shall be allowed till rectified.
(11)

The Contractors Safety Advisor will be available at site during working hours and when
required to join for site inspections carried out by the contractors staff.

These events shall be recoded and shall be inspected by CMs Staff when and as required.

10.0

SAFETY REPORTS AND RECORDS

The Site Safety Advisor will prepare the Monthly Safety Report which will be attached to the
Monthly Progress Report. In addition, Minutes of the Weekly Safety Meeting will be prepared
by the Safety Advisor and will be submitted together with the weekly progress report.
Duplicates of this report will be forwarded to the Main Office and will be kept on the site for
reference and file records.
A monthly report showing monthly man-hours and number and type of any accidents shall be
submitted to CM no later than the third day of the following month.
The Site Safety Advisor will maintain copies and listing of all current on site crane and
equipment operators, riggers, CPR qualified/First Aiders, and competent persons as required on
the Competent Person Listing form.
Weekly Site Inspection Checklist will be prepared by the Site Safety Advisor and Safety
Officers in their relevant areas and as and when noticed to report. The completed checklist will
be furnished to CM and be available for CM Safety Representative Review.
Contractors Monthly Safety Report will be completed at the end of each month and will be
submitted to CM Representative.
It has to be noted that all Competent Persons (CP) shall be trained and certified by an
independent 3rd party Organization accepted by SAG

11.0

CONTRACTORS SITE SANITATION

1. The services of Environmental Coordinator and reliable workers trained in providing


excellent housekeeping services will be utilized.
2. Cleanliness at both CM and Saudi Binladin Group offices, accommodations, toilets and
other facilities, as well as the areas surrounding these facilities.
3. Covered containers and drums will be provided at various locations throughout the site
for disposal of trash and will be emptied daily.

Page 22 of 59

4. Maintenance personnel will insure that the storage yard/workshop area is properly
maintained, clean and clear from garbage, trash, etc., so as to have safe access and clean
work conditions.
5. Wild life management- Material such as food scraps thrown unattended by site personal,
trash, garbage, grass seeds or pond water on or closer to the site shall be continuously
removed, to avoid birds, animals and reptiles coming in to the site.
6. FOD (Foreign Object Debris) Management.-Waste and loose materials like construction
debris (gravel, sand, mud paving material), small pieces of wood, cloth, paper/trash must
be removed from site movement area.
7. Loose material if not secured may blow about thus causing personal injury or equipment
damage. Materials tracked in to such areas shall be continuously removed during the
construction work. In addition all waste or loose materials that might attract wild life
shall be controlled and removed continuously.
Waste segregation shall be carried out by using different colored drums.
(eg. Plastic, Food waste and general waste etc.)
8. If any hazardous waste generated within the site premises such as used oil or any other
material can cause hazards to the environment shall be transported by an authorized
hazard material collector licensed by the Environmental authority of Kingdom of Saudi
Arabia.
9. On completion of transportation, a certificate shall be obtained from the Authorized
Transporter and End Receiver of Hazardous material and shall be recorded for inspection
by CM.

12.0

WORK PERMIT

(1) No work in a restricted area or any crane operations will be carried out without a valid
work permit.
(2) Air Operations Area (AOA) should be needed the work permit from the General
Authority of Civil Aviation (GACA). We should follow up the recommendation and
instruction of GACA, and also follow the rules and regulations of Air Traffic Control
Unit according to safety requirement of GACA.
(3) Function of Work Permits:
A work permit authorizes specific construction maintenance, inspection, demolition or
repair work to be conducted in a restricted area and to reduce potential hazards in
operation. This serves as a record that steps have been taken to ensure safe working
conditions in all areas concerned.
(4) Type of Work Permits is available for the following activities:

Extended Hours and Night Shift Working


Man Basket Operation
Page 23 of 59

Confined Space Entry


(5) A job site tour will be conducted with work permit issuer, before job start and a job site
tour will be made for close out of the work permit with issuer. Do not start any job
without a valid work permit.
(6) Work Permit receiver must be in the immediate work area at all times. When receiver
leaves the work area, the permit must be signed by the issuer, receiver and senior crew
member acting in place of the original receiver.
(7) Work Permit Procedure can be seen in ANNEX M:

13.0

WELDING AND CUTTING EQUIPMENT

(1)

All welding and cutting equipment will be of approved type by (American Welding
Society, Safety in Welding and Cutting, ANSI-Z49.1, and the recommendation of the
National Fire Protection Association), and shall be maintained in good condition.

(2)

Cylinders will be transported, stored and used securely fixed in the upright position.
When not in use, they will be stored on a cart in a specially designated area with valve
caps on. Longer storage of gas cylinders will be in covered sheds, covered roof and
enclosed in three sides, separated by a fire resistant wall. When lifted by crane, holders or
trolleys will be used of Standard type. Various sets of oxygen and acetylene cylinders
will be used at site at one time. The oxyacetylene set will be normally in the fabrication
yard, in secure racks and separated.

(3)

Ground return clamps will be attached to the work piece. Cable runs will be as short as
possible and joints, if any will be with approved connectors. The generator will be
equipped with an approved fire extinguisher. Electrodes will be removed from the
holders when not in use. Holder will be in good condition and cables will have no
defects.
A certified welder will be working in and around the fabrication yard, welding pipe
flanges to new pipes and fabricating spools. Welder certificates will be submitted to
CLIENT before the start of the job. Special welding standards are required; the Welders
shall have Competency Certification from an Independent 3rd Party Organization. (shall
be tested for 3G to 6G levels of welding etc.)

(4)

(5)

Welding presents possible molten slag fires. Dry chemical fire extinguisher (A, B, C
Type) will be placed near the welders at all times, and one (1) additional fire extinguisher
in the fabrication area.

(6)

A hazard may develop from flying particles during welding. Proper shielding and masks
will be provided for the welders and the fabricators.

(7)

Compressed Gas cylinders will be capped at all times when not in use. At the close of the
business day, cylinders in use will have the gauges removed and caps put in place until
their requirement for service the following day.
Page 24 of 59

(8)

Flashback arresters will be provided on all regulators & torches of the acetylene welding
sets.

(9)

Insure the special safety precautions are taken when unique welding operations are
undertaken.

(10)

Type A-B-C Multi-purpose Extinguisher will be available.

14.0

PERSONAL PROTECTIVE EQUIPMENT (PPE)

All PPEs to be provided by Saudi Binladin Group shall be subject for approval by CM before
purchase to ensure they are the standard materials. In addition, PPE samples shall be forwarded
with Product Safety Data supplied by the manufacturers for approval.
(1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)

WORKER
CATEGORY
Manager &
Supervisor

Personal protective equipment will be provided to the personnel as per the attached chart.
Different categories of workers in different areas will be given personal protective
equipment as required by the job and hazard.
For example, Class C hazard for an equipment operator working on a dusty day,
personal protective equipment such as goggles and dust mask will be provided.
Persons wearing prescription eye wear will be provided with safety glasses as required of
their jobs. Saudi Binladin Group will provide flexible fitting goggles.
Persons working in high noise areas 90 decibels or more will be provided with hearing
protection. (Jack Hammer and Operators be provided with Ear Muffs).
Eye Protection to be worn at all times by all personnel on site.
Rubber Boots/Gloves will be provided for concrete operations.
The table below is a list of basic personal protective equipment. Many job classifications
may require additional personal protective equipment depending on the work location,
type of job, local hazards, conditions, etc. The Safety Section or Industrial Hygiene office
should be contacted for further details.
COVER
ALL

HARD
HAT

SAFETY
SHOES

GLOVES

SAFETY
GOGGLES

FACE
SHIELD

EAR
PLUG

EYE
PROTECTION

X1

Foremen

X1

Eqpt. Optr/
Drivers

Welders

X5

X4

Masons

X1

Carpenters

X1

Electricians

X3

X1

Plumbers

X1

X1

Jackhammer
& Operator
All
Construction
Workers

SAFETY
BELT

DUST MASK /
RESPIRATOR

X
X

Page 25 of 59

NOTE:
1-

When required

2-

Electrician Type Hard Hat

3-

Rubber gloves where required

4-

Welding hood (leather, welder jacket where required) shade, goggles and clipping
goggles

5-

Fire Resistant

All personal protective equipment shall meet ANSI/OSHA or their equivalent requirements. Any
worker 1.82 m (6 ft.) above ground without the protection of a guard rail system, or in a confined
space, shall wear a full body harness and standard lanyard (as a part of SBG's fall protection
plan). Respiratory protection shall be used any time workers could inhale air contaminants
exceeding permissible exposure limits (PEL), and when an oxygen deficient atmosphere could
be encountered. Breathing quality air shall be supplied to the worker through the use of an air fed
hood or self contained breathing apparatus. SBG will supply PPE to Subcontractors and staff
from the Engineer.

15.0

TOOLS AND PORTABLE POWER TOOLS

(1)

All tools will be of best quality free from any defects, well maintained and be suitable for
the job.

(2)

All tools and power tools will be used, cleaned and stored as per the general requirements
to protect them.

(3)

Tools such as shovels, etc., will be used for small excavation where heavy equipment
excavation is not advisable. Screwdrivers, hammers, pliers, wrenches, pipe wrenches, and
other small electrical tools etc., will be used by plumbers, electricians, carpenters, etc.

(4)

Dust masks will be provided for workers working in dusty areas. Dust control will be
provided by spraying water as required by the site condition.

(5)

A hazard may exist in the use of wrenches and other small tools. Workers will be advised
on the use of right tools; proper tools for the job required and not abuse the tools.

(6)

When using small power tools, only 220 volts, single phase grounded or double insulated,
portable tools on GFCI circuits will be used and guards will be provided for equipment
such as grinders and power saws.

(7)

A face shield may be required, by the operator, in addition to Safety Glasses for
personnel operating power tools.

(8)

All power tools must prominently display the manufacturers data plate.

(9)

Use power tools for every job. Hand-made or home-made tools are not allowed in the
project or fabrication site.
Page 26 of 59

16.0

LADDERS

(1)

Ladders will be of metal or timber of a type approved by OSHA and will be in good
condition. In addition, ladders shall be from a reputed manufacturer who can provide a
Product Safety Data Sheet.

(2)

Every work place ladder will be safe and tied off and have protection against falls of men
and material. A safe means of getting up to and from every work place will be provided.

(3)

Ladders will be used for access or egress to/from excavated trenches, to reach a platform
or scaffolding of higher elevation, etc. Ladders will be placed in the immediate work area
and every 25 feet in excavations.

(4)

Ladders will be in good condition. Ladders used will rise at least three (3) rungs above
the stepping off point for that ladder. Ladders will be securely and evenly supported on
both sides and shall not be footed on loose material.

(5)

Ladders will be tied off at the top where possible.

(6)

Use of metal ladders to perform electrical work or to work on electrical component is


prohibited. Suitable wood or fiberglass ladders shall be used.

(7)

Ladders not in accordance with OSHA standards or defective shall immediately be


removed from the site.

(8)

Job made ladders will be provided conforming to OSHA standards. Job made ladders
brought on site will be inspected before use by CM Safety Engineer with respect to
certification submitted by Contractors.

(9)

All straight ladders will be tied off at top and bottom.

(10)

All ladder shoes shall be checked before and after use and shall be maintained regularly.

(11)

Ladders shall be angled 75 deg. to horizontal ground (1:4 Slope) whenever possible.

17.0

ELECTRICAL INSTALLATION AND EQUIPMENT

(1)

All materials and equipment used in temporary electrical installation will be of Standard
and approved type as per the national electric code and maintained in good work
condition.

(2)

All appliances, equipment and materials used for temporary electrical installation will be
constructed, installed, protected, worked and maintained so as to prevent danger.

(3)

Temporary electrical installation will be used for lighting and portable power tools.

(4)

All temporary electrical circuits shall be protected by Ground Fault Circuit Interrupters
(GFCIs).
Page 27 of 59

(5)

All work on electrical equipment shall be carried out by or under the supervision of a
qualified craftsman. All portable tools will be 110 volts, single phase double insulated
and operated through GFCI devices.

(6)

Extension cords will be kept clear of walkways, water pools, and other locations where
they may be exposed to damage, creates trip hazards, or set up other hazardous
conditions.

(7)

Color tagging, following inspection by a qualified electrician, of hand held power tools,
GFCI Units, all electrical equipment/boards, extension cords, table saws, appliances, and
etc. is required monthly. It is understood a color scheme has been provided and this
requirement is subject to change.

(8)

All electrical installation, permanent or temporary, shall be made to comply with


international standards such as NFPA 70 standards.

18.0

SCAFFOLDING

All scaffold structures shall be erected with approved metal components, shall be erected and
dismantled by certified scaffolders, supervised by a Certified Scaffolding Supervisor and
inspected by a Certified Scaffolding Inspector. It shall be stored properly to prevent damage and
permit easy access for use. Scaffolding Layout Plans will be submitted to CM for approval.
Such scaffolds shall be designed by a competent Engineer by the Contractor and prior approval
shall be obtained from CM for fabrication and on completion shall be inspected by CLIENTs
Safety Section. Scaffold should not be used unless approved for working on from Engineer.
Details of scaffolding design procedure can be show in Annex-G.
(1)

Foundations an adequate base is essential to erect scaffolds. Timber plates of not less
than 4 cm. thick and 25 cm. will be used to spread load on surfaces such as sand, made up
ground, slippery surfaces, asphalt pavement and wooden floors. Smaller timber pads will
be used on hard surfaces such as concrete or rock to prevent the base plate from striking
off. (OSHA Approved timber)

(2)

Standards shall be pitched on 15 x 15 cm (6 x 6) steel base plates. Inner row of


standards will be placed as close as possible to the face of the building or structure. To
avoid projections the posts may be up to 41 cm. (16) away from the wall, provided that
the gap is closed by planks (using outrigger parts).

(3)

Ledgers shall be fixed 90 to standards and will be horizontal. They will also be
vertically spaced at 2 meters to allow for adequate headroom.

(4)

Bracing shall be extended diagonally to the full height of the scaffolds at an angle as
near as possible to 45.

(5)

Ties shall be used at every 20 feet and at each vertical 13 feet level as necessary to
prevent movement of the scaffolds towards or away from the structure.

Page 28 of 59

(6)

Decking all decking will be closed planks 5 cm. thick to the full width of the scaffold
(at all working platforms), clean from oil and slippery materials and will be secured in
position to prevent displacement. Supports for planks shall never be more than 3 meters
apart. Planks will extend over the end supports to 30 cm. There will also be adequate
space for men to pass in safety on decking whenever materials are placed on top.

(7)

Guard Rails, Mid Rails and Toe Boards shall be fitted at edges of decking to prevent
men from falling off. Guard rails will be about 106 cm. in height and toe boards not less
than 15 cm. in height. Both will be securely fixed to the inside of standards.

(8)

Access ladders will be provided up to 3 steps over the decking and will be secured
properly to the scaffolds.

(9)

Inspector all scaffolds will be inspected regularly to make sure that stability is not
affected, with inspection stickers attached to the structure (approved for use or not
approved for use). Scaffold Inspection will be submitted to CM for approval.

(10)

The height of rolling scaffold will not exceed for (4) times the minimum base width
(which shall never be less than 4 ft.) unless provided with adequate directional outriggers
or lateral bracing.

(11)

The Scaffolds designed by Competent Scaffold Engineer, erected by competent scaffold


erector, and inspected by competent Scaffold Inspection. The report will be submitted to
HSE Advisor for tagging.

(12)

When using scaffold when working more than 6 ft. high, permanent decking, parts of a
structure, walkways, footbridges, etc., which workers use in the course of their work for
access, shall be provided with a guardrail system and toe-boards at all edges from which
men or objects could fall. Holes & gaps shall be securely covered. Stairs shall have all
treads properly secured and shall be fitted with handrails throughout their length. If the
provisions of these safeguards be impractical, fall protection devices such as full body
safety harness shall be used (it has to be noted that the use of safety belts is prohibited as
of January 1st, 1998 on all US construction sites). Full body harnesses shall comply with
ANSI & OSHA standards and should pass inspection by Safety Section before use.

(13)

Scaffolds required for special applications and those required for unusual heights (more
than 40 ft.) or for use in abnormal circumstances shall be of a special design and shall be
approved by Safety Section through a licensed professional engineer or a certified
scaffolding inspector). No scaffolds of this type shall be used without approval by Safety
Section of Contractor without designed by contractor scaffold engineer.

19.0 CRANE AND LIFTING EQUIPMENT


Cranes should be inspected by CM before use by contractor in any of the sites. It has to be noted
that Cranes and all lifting tackles shall be inspected and certified by an independent 3rd party
Surveyor accepted by SAG. If new lifting tackles are purchased those shall be produced with
certification for approval. Generally, the following is to be noted:
Page 29 of 59

(1)

The contractor will provide the 3rd Party Certificate for CM review and Site HSE advisor
will issues stickers.

(2)

All lifting appliances and every part thereof, including all working gear and all other
plant or equipment for anchoring or fixing will be of good mechanical construction,
sound material, adequate strength and free from patent defects and are properly inspected
and maintained.

(3)

All cranes and items of equipment used for lifting and rigging shall be in good condition
and suitable for the work they are required to do. Outrigger pads will be used at all times.
All critical crane lifts will be submitted to CM for approval.

(4)

Cranes will be used for unloading and installation of pipes, pumps, tanks and other
equipment and materials.

(5)

All crane operators will have valid SAG licenses and valid 3rd Party Crane Operators
Certification. SWL will be marked on equipment and lifting tackles and the crane will be
operated only on firm level standing with outrigger pads in place. The crane operator will
act on the signals of one man only. The operator will not leave the crane with load
suspended. Damaged hooks, rings, eye bolts, slings, etc. will not be used.

(6)

Cranes and Heavy Equipment will not operate under electrical power lines without
Contractor. Safety Advisor approval as per Contractors HSE Plan (or applicable OSHA
standards).

(7)

Conduct pre-use checks before operating any lifting device. Pre-lift Operation Checklist
should be satisfactorily completed by the Safety Supervisor and operator before any crane
operation, as follows:
o Check that all protective guards and panels are secure before operating.
o Check all hydraulic hoses for chafing, bulging, or other damage.
o Visually inspect all gear cases for leakage or damage. If leakage is evident, fill
the case to the proper level before operating.
o Check all controls for correctness and ease of operation.
o Check tire pressures and wheel studs. Tire wear can be greatly reduced and
stability of the machine increase by matching tires carefully for size and degree of
wear. Maintain proper inflation at all times.
o Check brake air pressure.
o Check low air pressure warning devices.
o Check foot brake operation.
Page 30 of 59

o Check headlights, clearance lights, turn signals, parking lights, tail and stop
lights, windshield wipers, horn, etc.
o Check all instrument panel gauges.
o Visually inspect the entire machine for loose or missing bolts, or cotter pins,
cracked welds, frayed or damaged ropes, dented or damaged boom chords or
lattice, etc.
o Visually inspect all clutch and brake linings for evidence of wear, or grease and
oil on the linings. Serious injury to ground personnel or damage to property and
equipment could result if adjustments are neglected.
o Read the maintenance section of the manufactures manual. Knowledge of
preventive maintenance may allow the operator to spot a malfunction in the
machine before an accident occurs.
o Inspection will be made in a daily basis or prior to any lifting jobs to be done.
Records will be kept by the Safety Supervisor.
Marking Lifting Tackle
Tags
In order to facilitate proper marking, all equipment (in particular wire rope slings, nylon slings,
shackles and specialised lifting devices) shall be equipped with a marking tag. The
marking tag shall be locked onto the lifting equipment so as not to interfere with its
function.
The marking standard shall be as follows: On press
fittings (Flemish eye ferrule)
Name and/or initials of the manufacturer
Safe working load
Certificate number
On marker tag
SBG.
Safe working load.
Certificate number.
Colour Coding
All lifting tackle shall be colour coded after its three monthly inspections in order to:
Identify the period in which lifting tackle was inspected.
Identify slings and equipment that have been inspected, tested and approved by
the Competent person, Cranes & Lifting Equipment for service.
Slings shall be colour coded by painting, on both ends, as follows:
Page 31 of 59

JANUARY
APRIL
JULY
OCTOBER

to
to
to
to

MARCH
JUNE
SEPTEMBER
DECEMBER

BLUE
GREEN
RED
YELLOW

At the end of the approved three (3) month period the slings and equipment shall, regardless of
condition, be taken out of service for the prescribed inspection and approved and color coded for the
next three month period.
Slings and equipment that have been discarded during their time in service shall be replaced
with new or approved items colour coded according to the current period.
Rigging Study
A work method statement used in conjunction with the job safety analysis, detailing the
sequences of work, the weights involved, equipment to be used, precautions to be taken, and
persons employed to do the task.
Cranes are not to be operated unless the machine has a valid load test certificate from a qualified
third party inspection company and the operator and the accompanying riggers each has a valid
certificate of competence or an equivalent document issued by an authority recognised by the
Company.

20.0

MECHANICAL EQUIPMENT:

Mechanical Equipment should be inspected by CM Safety Staff before use by contractor in any
project facility. It has to be noted that Mechanical Equipment shall be inspected and certified by an
independent 3rd party Surveyor accepted by SAG, subject to certification a sticker shall be issued
by Contractor Safety Advisor prior to commence work. If new Mechanical Equipment are
purchased those shall be produced with certification for approval. Generally, the following is to be
noted:
(1)
(2)
(3)
(4)

(5)

(6)

All mechanical equipment will be of Standard and approved type and maintained in good
working condition. All moving parts of any equipment will be provided with safety
guards;
Equipment will be adequate and suitable for the work to be done. All equipment will be
maintained in a safe and operational condition;
Mechanical equipment such as dump trucks, loaders, cranes, heavy equipment etc., shall
be used for loading and transporting materials;
Equipment will be used only by those who are experienced in the use of such equipment.
This will be monitored by checking their licenses. All moving parts will be securely
guarded. Dozer blades and tipper bodies will always be lowered after use.
Heavy equipment, dump truck, loaders etc., will be equipped with back-up alarms and/or
will have an assistant (back-up spotter) when maneuvering and to warn the operator of
unseen hazards. Passengers will not be carried on any equipment not intended to carry
passengers;
Only trained personnel shall operate any mechanical equipment. Operators shall be
Page 32 of 59

(7)

(8)

trained in the procedures and functions relevant to a specific piece of equipment; they
must be fully aware of the capabilities and limitations of the machine and have
knowledge of the day-to-day maintenance that it requires;
Dumpers and Dump Trucks shall be extensively used for this project. Thus it is essential
that they be properly maintained. The latch on dumper skips must be in good working
order, and the release mechanism should function smoothly. Dumpers are not designed to
carry passengers. It must be strictly forbidden for employees to ride in the skip or on the
engine cover. When repairs or maintenance are being carried out on a hydraulically
operated dump truck, the dump body should be fully lowered. Dump Truck Drivers shall
have a SAG license;
Trailers, Dozers, Loaders and Mini-loaders Heavy earth moving equipment only allows
the operator a limited view of the immediate area. It is, therefore, essential that a banksman be appointed to warn the operator of hazards that cannot be seen from the operators
position.
-

This equipment shall be equipped with roll over protection. A valid Saudi Arab
Government heavy equipment license and by an independent 3rd party testing and
certification as mentioned earlier.
Before moving his machine, the operator must walk around it to see that the area is clear.
Men must not be allowed to sit or lie in the area around the machine. The engine shall not
be left running when the operator is not at the controls. Before leaving his machine,
operator must shut off the engine and remove the ignition key.
Blades, buckets, etc. must be lowered to the ground before the operator leaves his unit.
The wheels should be properly chocked. If there is work to be done underneath such as
hydraulic equipment, the equipment must be blocked in position.
(9)

All operators of mobile heavy equipment must be in possession of a valid Saudi Arab
Government (SAG) license for that particular class of machinery and by an independent
3rd party testing and certification as mentioned earlier.

(10)

Excavators
Excavations are carried out using very specialized equipment that basically falls into two
categories: 1) fixed position machines, and 2) moving machines.
The choice of equipment to be used is determined by the size of the project, topography,
volume of earth to be hauled out and many other factors. Fixed position machines
include, but are not limited to, face shovels, backhoes, draglines and grabs. The fixed
excavator loosens the soil and loads from a stationary position. They are useful to
perform specific excavation tasks at a single location.
Their loss of mobility is compensated by the fact that greater force can be applied at the
excavation face. Moving machines include, but are not limited to, bulldozers, loaders,
Page 33 of 59

trailers and trenching machines. They remove, transport and deposit excavated material
all in one cycle of operation. They are used in applications where large volumes of earth
need to be moved over uneven ground. In this process, they also help to level the ground
over which they operate.
Operators of excavators must possess a valid Saudi Arab Government license for the
machine and a valid independent 3rd party Certification.
Outriggers must be fully extended when operating a mechanical excavator so fitted. An
attendant must be appointed and be available at all times during excavation to assist and
guide the operator.
Excavators with a swinging motion must have a clearance of at least 0.6 meter (2 feet)
from any fixed object. Booms on excavators must be latched before travel.
Do not excavate closer than 10 feet to the nearest pipeline or other equipment in place.
Saudi Binladin Group shall control all excavation work associated in this project. This is
to include the generation of excavation permits and the appointment of a competent
person to oversee the operations.
(11)

Generators
A competent electrician shall be available to ensure that electrical connections are
properly made. The operator should be responsible only for the mechanical function of
the machine. All pulleys, belts, and fans must be totally enclosed or otherwise guarded.
The side panels to the engine cover are designed to give access to the machinery for
maintenance or repair. They must be closed at all times when the engine is running. The
machine must be properly grounded before each use.
With regards to all electrical jobs job description shall be in writing with permit to work
and a sign off for that the Electricians well aware of the detailed task. Certificate of
competencies of Electrician and Supervisors shall be recoded.
Sound Level of Generator should be checked and approved from Engineer prior to
operation for the first time.
Voltage regulators are placed between incoming power source and equipment
(Laboratory and computers).
Fire Prevention Guide for Portable Generators:
The following is a typical check list of the major items to look for. There may be other
potential fire hazards not listed, therefore a thorough inspection must be made.

Repair all fuel Tanks.


Check hose and pipe connections for wear and cracks.
Clean up all combustible trash around the generator.
Clean up all fuel spills and place clean sand around area when required.
Sheds constructed of combustible materials placed around generators and wooden
Page 34 of 59

base frames are prohibited.


Exhaust piping system shall be kept away from work areas and combustible
materials.
Generator sets shall be located at least 50 feet from buildings or materials that
may catch fire.
Inspect all wiring for damage or improper splices/repairs.
Electrically ground all generator sets (system and frame ground).
Fire extinguishers must be readily accessible. One CO2 extinguisher for the
generator and a dry chemical extinguisher for the engine drive is recommended
(the use of All-Purpose fire extinguishers is recommended).
Conduct daily inspections of all generator sets.
Generator shall have 220 volts power out. GFCI shall be provided.

(12)

Effective January 2002, all Scissor-Lift and Boom-Truck operators will be required to
have a valid 3rd Party certificate to operate such equipment.

(13)

All equipment shall be parked when not in used at an area where it will not affect traffic,
be visible to other moving vehicles/equipment and away from danger to other moving
vehicles/equipment especially at night.

(14)

A full time Mechanic will be assigned at site for the maintenance of all equipment. He
will keep all records of any repair being made so as the defect of each equipment (if any).

(15)

A fuel truck will be standby at the site for refueling equipments at work.

(16)

Operators for Forklift Operator shall have at least 3 years experience on this type of
equipment.

21.0

TRANSPORTATION AND TRAFFIC SAFETY:

(1)

The employees traveling to and from the work site will travel only in vehicles with
Contractor stickers. Seat belts will be provided on all the vehicles for all the passengers
except for buses designed for 14 or more passengers where the seat belt will be provided
only for the driver. Seat belts should be checked to ensure that they are working properly.
Damaged seat belts should be replaced and tested before putting the vehicle back in to
service.

(2)

Make sure that all drivers engaged on this specific project are holders of a valid SAG
license and they shall be well aware of all traffic rules both of the Kingdom and CLIENT.

(3)

The drivers shall be responsible for checking his vehicles steering system, brakes, tires,
seat belts, horn, lighting, signal system, rear view mirror, wind shield wipers, oil level,
radiator level, exhaust system, gas tank cap and the free unobstructed and easy operation
of the emergency door.

(4)

Personnel will ride in vehicles only where the manufacture has provided designated
seating.

Page 35 of 59

(5)

All vehicle accidents on Project Site facilities or involving a CM Staff vehicle shall be
reported immediately to CM. A complete accident report shall be prepared and furnished
within 72 hours.

(6)

A comprehensive Traffic Safety Plan, addressing, CM and Saudi Arab Government


traffic regulations, shall be prepared and submitted to CM Safety Section for
review/approval prior to start of work affecting access to Project Site Facilities or in the
public areas.
Vehicle Safety Inspection Every vehicle operated in Operational Area shall be
inspected by contractor despite the 3rd party certifications.

(7)

Vehicle marking/lighting-Rules and regulations specified in CLIENT safety manual


for vehicle identifying, marking, lighting and operation during day and night shall be
followed if used or operated in Airport controlled Area.
Accident /Incident reporting procedure- as per Contractor Project HSE Plan
Penalties- Penalties for non compliance with driving rules and regulations shall be
enforced by CLIENT Authority.
Entry/Exit and parking areas (If Applicable)-Construction employees and drivers shall
enter/exit through designated access points created by Client for passage of construction
vehicles and personal. The parking location of all such vehicles and equipment shall be
outside the safety areas. Procedures for proper vehicle operation on airside/landside areas
during normal, lost communications and emergency conditions shall be adopted.
Fuel trucks and site tankers precautions
Light and medium vehicles shall refuel at public filling stations.
Heavy vehicles may refuel at public filling stations depending upon journey needs
and convenience. Heavy vehicles may also refuel on site from a road tanker.
Road tankers shall refuel mobile and static plant.
Road tankers that refuel vehicles, mobile and static plant on site shall be subject to
inspection. The objective of inspection will be to:
Verify the road condition and equipment of the vehicle.
Verify the integrity of the road tankers fuel pumping and transfer system.
Verify the road tankers earth bonding system.
Where refueling of mobile or static equipment takes place on site, the following criteria
shall be communicated and enforced to those involved:
a. The location selected for refueling shall be safe in terms of position.
b. Refueling activities shall not take place on site traffic access routes.
c. Refueling shall not take place within 30m of any hot work activity.
Page 36 of 59

d. The fuel tanker and receiving vehicle shall not be parked on any
environmentally sensitive surface.
e. Engines shall be switched off before refueling.
f. ) Earth bonding shall take place at every fuel transfer.
g. ) No smoking shall be permitted during refueling activities.
h. ) DCP fire extinguishers shall be available at the refueling point.
Refueling from a road tanker is recognised by the Company as a critical activity in
terms of safety and the environment. As such, the refueling procedure, as defined
below in chronological order, shall be communicated to those concerned via toolbox talks
and its sequence shall be rigidly followed:
Place the fuel tanker and the receiving vehicle in a safe location inclusive.
Switch off engines.
Hook up earth bonding between fuel tanker and receiving vehicle or plant. Ensure
metal to metal contact.
Check tanker delivery hose for residual fuel from last fuelling operation. If there is
residual fuel, handle the delivery hose accordingly.
Connect up fuel delivery pipe. Ensure the integrity of all terminal and in-line
connections.
Place drip trays beneath all terminal and in-line connections.

22.0

INJURY AND DAMAGE REPORTING:

(1)

All accidents/incidents will be fully investigated to determine the cause of the accident.
Unless the actual cause is known, the hazard cannot be controlled in the future. Near-miss
incidents will also be thoroughly investigated.

(2)

An immediate oral report will be made to the company representative and CM


representative in all cases of:
a. Injury any personnel injury shall be reported immediately to CM. A preliminary
report must be submitted within 24 hours. A full report must be furnished within 72
hours;
b. Fires;
c. Fatal injuries shall be submitted to CM; all Quality, Health and Safety for Reporting
of Safety Statistics (see Annex-D);
d. Injuries requiring medical attention which result in lost time;
e. Damage over SR 10,000 to contractors plant or equipment;
f. Damage in any amount of CMs equipment or property;
g. Damage and near misses to cranes and heavy equipment.
-

(3)

A written report will be made within 24 hours followed by a detailed report when an
accident involving contractor employees, fatalities, to any one minor or serious injury or
more employees or damage to CM equipment or property occurs.

(4)

An engineering review committee will be formed by Contractor to investigate certain


Page 37 of 59

classes of accidents in coordination with CM


(5)

Contractor will maintain, in a format which will be included in HSE Plan, a current
record showing all:

Fires
Work injuries
Incidents of property damage over SR 10,000
Motor vehicle collisions and
Incidents involving damages to CM equipment and property.

(6)

This record will be available for inspection at all times. Formats are also shown on the
following pages.

(7)

Contractor will submit a Monthly Contractor Safety Report. It will be provided to CM


site representative no later than 5th day of the month following the month being reported.

(8)

Any Near Miss incidents shall be reported to CM and a written report of the occurrence
will be provided.

(9)

All site employees shall be compelled to report any accident/incident, near misses, major
or minor, to the Safety Advisor. Safety Advisor should immediately respond to any
accident/incident reported, investigate the cause, damages or injuries etc. and
accordingly, report the same to CM Representative, along with proposed
corrective/preventive measures.

(10)

Proper contractor forms for injury and damage reporting, as provided for in the
Contractor HSE Plan, shall be used (see attachment).

(11)

All incidents shall be reported with Safety Section Participation and Contractors site
(HSE) Safety advisor will report to CM Staff.

(12)

Ad Hoc Safety Auditing:


When so required, Ad Hoc Safety Auditing shall be carried out by CM and the Contractor
site HSE Advisor who shall be available at site.
After every fatal accident an Ad hoc Audit shall be performed by Project Manager, also
by a part led or appointed by CM.

23.0

EXCAVATIONS:

(1)

All excavations will be made to conform to Contractors Project HSE Plan


a. Whenever there is likelihood of a collapse of the side of an excavation, the sides shall
be suitably shored or sloped to a safe angle. Excavation reaching a depth of 4 or
more shall be shored.
b. Spoil materials will be set back at least 2 from the edge of the excavation. Heavy
Page 38 of 59

equipment and vehicles will be kept as far away as practicable from the excavation.
c. Suitable stop blocks will be used where vehicles or equipment tip material into an
excavation.
d. Persons will not be permitted to work in any place where they could be struck by any
part of mechanical equipment. Signs will be posted to warn personnel to keep out.
e. Gas/Oxygen level tests will be conducted by the proponent where there is reason to
suspect the presence of hazardous atmosphere in an excavation. Tests will be
conducted of every excavation before men are allowed to enter.
f. Whenever there is likelihood of persons, equipment or vehicle falling into an
excavation it will be properly marked and barricaded.
g. Confined Space Entry Work Permit shall be obtained for any excavation 4 ft. or more
deep.
(2)

Excavations are required at the site for the pipe laying, cable laying, for manholes, valve
boxes, etc.

(3)

In any excavation, the following precautions will be taken:


No mechanical excavation will be undertaken at a place if there is a possibility of
underground utilities.
Shoring or proper angle of repose will be provided, if there is a possibility of a
collapse and the depth reaching 4 ft. or more.
All excavations will be checked daily and especially after rain storms for the
following:

(4)

(5)

a. Shoring/trench box/slopping;
b. Blower;
c. Spoil Clearance;
d. Barrier/warning signs/lights;
e. Access/Egress (ladders);
f. Crossovers;
g. Void space procedures;
h. Air-test;
i. Rescue equipment.
Prior permission shall be obtained from CLIENT through CM, providing sufficient
number of days according to construction manual for the clearance from the underground
utility services users.
Protection of existing utilities- Procedure shall be developed for locating and protecting
existing underground utilities, cables / wires and other underground facilities before start

Page 39 of 59

of excavation in the work area. Exposed wiring in the work area must be secured as it
may create electrocution or fire ignition hazard.
(6)

For all excavations method statements for depths in excess of 1.8m to be approved by the
site safety department.

24.0

FIRE PREVENTION:

A.

Fire Fighting Equipment

(1)

Adequate fire-fighting equipment will be provided (dry chemical, CO2, water barrel, etc.)
numbered and maintained in good working order. Personnel shall be properly trained in
the use of fire-fighting equipment. Storage yards will be provided in accordance to
Standard requirements. (The Site Safety Advisor will train a group of men who will be
designated as the Fire Brigade).

(2)

The layout of temporary facilities will be planned so as to minimize the risk of fire
spreading from one building to another. Sketches showing the layout of the temporary
facilities are attached, along with fire prevention system.

(3)

Fire fighting equipment which complies with Standard and specific requirements shall be
provided throughout and maintained in good condition (by a certified fire equipment
provider), especially at the offices, storage yard, fabrication yard, etc. Fuel, oil and other
combustible and flammable materials will be stored separately at designated areas as
shown in the layout sketch. Smoking will be allowed only in designated areas.
Good housekeeping will be implemented and personnel will be trained in the use of firefighting equipment. (The Site Safety Advisor will ensure that these tasks are done by the
Safety Section).

(4)

Fire extinguishers will be inspected initially on first installation and then every month.
Inspection tag to be signed and dated. (The Site Safety Advisor will arrange these
inspections). In addition, Extinguishers must undergo a maintenance check and
certification each year or as per the Standard requirements of the Kingdom.

(5)

The Site Safety Advisor will conduct fire drills and/or Fire Extinguisher Training on a
quarterly basis. All documentation and records will be kept by the Site Safety Advisor
and shall be distributed accordingly to all concerned personnel.

(6)

A list of Trained Fire Fighters shall be provided to CM. Those personal shall have
identification on their Hard Hat for everyone to know that they are Fire Fighters and list
of names shall be published in all notice boards with photographs.

(7)

A fire extinguisher, rated not less than 2A, shall be provided for each 300 square meters
of a combustible building area, or major fraction thereof. Travel distance from any point
of the protection area to the nearest fire extinguisher shall not exceed a horizontal
distance of 30 meters. When 20 liters or more of a flammable or combustible liquid is
being used, an extinguisher must be within 15 meters.
Page 40 of 59

(8)

Extinguishers must be maintained in a fully charged and operable condition. The area in
front of fire extinguishers must be kept clear.

(9)

Post Exit signs over exiting doors, and post Fire Extinguisher signs over
extinguisher locations.

B.

Flammable Liquids

(1)

Flammable liquids are those that can produce a flammable mixture in air at ambient
temperature. Flash point is defined as the lowest temperature at which a liquid will give
off sufficient vapor to ignite when exposed to open flame.

(2)

Storage
All flammable liquids shall be kept in securely approved capped metal containers, or steel
drums clearly labeled to prevent mixture with other substances, and must be stored in
approved storage cabinets. Gasoline, acetone, spirits and other volatile
liquids with flash points below 32C (90F) should be kept in strong metal lockers
located in well-ventilated, non-combustible huts or sheds. Drums containing flammable
fluids shall be provided with proper bung vents. Flammable storage areas must be
securely locked (or fenced), posted with warning signs such as Danger: Flammable
Area and must be located at least 15 meters (50 feet) away from the nearest building or
storage area for combustibles. No other materials should be stored with flammable
liquids.
All these materials shall be properly labelled and shall be available with the Records for
inspection at any time by CM Staff.
This condition applies to all the materials under the Control of Substances Hazardous to
Health.

(3)

Solvent waste and oily rags must be kept in a fire resistant, covered container until
removed from the site. All these material shall be collected separately for disposal.

(4)

Flammable gases in cylinders (acetylene, propane, etc.) shall be segregated from other
materials, preferably under an open, well-ventilated sun shade. Oxidizing gases (oxygen,
chlorine, nitrous oxide, etc.) shall be stored separately.

(5)

In handling flammable material, the following precautions should be observed:


(a) Transportation must always be in (closed) metal containers. (Plastic or rubber
containers are prohibited.)
(b) Transfer operations should be carried out with funnels and there should be no open
flames within 15 meters (50 feet) of the operation unless conditions warrant greater
clearance.
(c) Containers are to be grounded and bonded during transfer operations.
(d) Screw tops and stoppers should be replaced immediately.
Page 41 of 59

(e) Any metal container holding flammable liquid must be a FM (or UL) approved type
of safety container.
(6)

Ventilation
Gasoline and diesel powered equipment should only be used in well-ventilated areas.
Exhaust pipes should be kept away from any source of ignition. Engines must be stopped
before refueling takes place and warning sign such as Stop Engine Before Refueling
shall be posted to ensure compliance.

(7)

Fire drills shall be conducted regularly during construction period.

25.0

FORM WORK:

(1)

All form work support will be of Standard approved type. The timber will be of suitable
quality and strength. Prior to any concrete pouring into any supported form work
structure, will be inspected by Contractor Engineer and Safety Advisor prior inspection
request to CM.
a. Form work will be designated, erected, supported, braced and maintained so that it
will safely support all vertical and lateral loads that may be imposed upon during
placement of concrete.
b. Stripped formwork will be removed and stockpiled promptly after removing all
protruding nails, wire ties, etc.
c. Wood will be stacked separate in the lay-down area, away from any combustible
materials. For long term storage, the material shall be protected from the elements.

(2)

Only approved types of form work, for the required finish and strength of the concrete to
be poured will be used.

(3)

Form work will be fabricated for the concrete pouring both in-situ and precast.

(4)

Forms plan will be submitted to CM for approval.

(5)

Work platforms will be provided for workmen on all forms above six feet.

26.0

FIRST AID FACILITIES (Annex L) :

(1)

Adequate first aid facilities will be provided and maintained at work site in accordance
with Article 134 and 135 of the Saudi Labor Laws.
One (1) qualified Nurse and one (1) dedicated emergency vehicles (ambulance) properly
supplied and marked, to transport personnel to the nearest health care facility (to be
arranged by SBG) will be provided when manpower strength reaches 50 or more. (A list
of First Aid supplies required is given below under item#6).
Page 42 of 59

(2)

A posted notice at site will indicate the following:


a.
b.
c.
d.

Name of the person who is in charge of the first aid and cabinet.
The hospital to which any injured person that requires hospital treatment is to be sent.
The telephone number of the doctor or first aid attendant employed by the contractor.
The emergency telephone number to be called for assistance.

(3)

A site injury summary will be maintained listing all medical treatment (first aid) given at
the site.

(4)

A map showing directions to Hospital selected for treatment of injuries will be posted
outside the clinic and a copy will be maintained in the ambulance.

(5)

Antidotes for poisonous snake/insect bites and/or irritations will be made available in the
clinic at all times.

(6)

LIST OF FIRST AID SUPPLIES


a.
b.
c.
d.

e.
f.
g.
h.
i.
j.
k.

l.
m.
n.
o.
p.
q.
(7)

A sufficient number of not less than 12 sterile, small size finger dressings.
A sufficient number of not less than 6 sterile, medium-size hand dressings.
A sufficient number of not less than 6 sterile, large- size hand dressings.
A sufficient supply of absorbent cotton wool for packing and firming up splints. Such
supply shall not be less than 200 grams of cotton wool in small 25 grams packages
and two 500 gram packages.
A sufficient number of not less than 12 gauze bandage 7 cm. in width.
A sufficient number of not less than 12 gauze bandages 11 cm. in width.
Not less than 4 yards of adhesive tape in rolls, 1 cm. in width.
Not less than 100 grams of mercurochrome in aqueous solution.
Two 10 gram shakers of sulfa powder for sterilization wounds.
100 grams of aromatic ammonia solution in a glass bottle with a glass stopper.
A medium-sized Thomas thigh splint, a wooden posterior leg splint, a wooden elbow
splint, a wooden Carr splint for the forearm, a wooden palm splint, and other types of
ready-to-use splints.
A minimum of 6 triangle bandages.
A minimum of safety pins.
Ointment for burns containing a disinfectant and an analgesic.
A minimum often 70 x 70 bandages for burns.
A pair of scissors with blunt ends.
A sufficient number of stretchers for moving injured persons.

MEDICAL EVACUATION PROCEDURE:


In the event of an accident or a serious sickness involving any of the workers on site, an
emergency evacuation will be required. In such cases, the following system will be used.
Page 43 of 59

For the evacuation of injured or sick persons, there would be a standby ambulance on
site, maintained in good condition and a driver to transport the sick or the injured worker.
Information would be made available at the site office and with the driver, regarding the
name, address and telephone number of the nearest hospital, the distance and
approximate travel time to reach there.
(8)

FIRST AID TRAINING & CERTIFICATION


Personal intended to be trained as First Aiders shall be identified within one month of the
Notice to Proceed. All First Aiders shall be trained and certified by an approved 3rd Party
Trainer and Certifier. Records shall be forwarded to CM. Furthermore, First Aiders shall
have sticker of identification on the hard hat on a specified side of the Hard Hat for
everyone to know that they are First Aiders, and list of names shall be published in all
notice boards with photographs.
Our Site Nurse will conduct training of our Work Crews on first aid techniques for
injuries that are based on our experience in working in the same environment, commonly
occurring in the jobsite. Personnel will be taught and trained regarding safety precautions
and first aid techniques regarding snake bites and other poisonous insects, work-related
injuries and any other injuries requiring first aid.
Each Work Crews will be represented, to ensure that a Trained First Aider is always
available when and if required. When enough competency is achieved, all Trained First
Aider will be sent for certification by accredited certifying agencies (i.e. Red Crescent
Society, etc.) as shown in the attached certificate.

27.0

DUST CONTROL (CONSTRUCTION AND ROAD AREAS)

(1)
(2)

Water trucks equipped with hoses and sprinklers will be used in dampening roads and
work areas during the dry season or as directed.
Strict limitation of speed will be observed to help control dust.

28.0

JOB SITE INSPECTIONS

(1)

Job Site Safety Inspections will be conducted at least daily and inspection check list
submitted to CM weekly as part of the weekly site meeting minutes.

(2)

These Weekly Safety Inspections will be carried out in addition to the daily inspections
by the contractor Safety Representative.

(3)

The Contractor Site Safety Advisor will monitor all construction activities at the site to
ensure that services are performed in conformity with Contractors Project HSE Plan.
Contractor Site Safety Advisor will visit the site regularly to ensure the work performed
by the contractor is in compliance and persons or property are not being exposed to
undue risk. Regular site inspections will also be conducted by the Area Safety Section
Representative.

(4)

(5)

Comments concerning violations found by CM shall be entered in the site safety log
Page 44 of 59

which remains at the site during the project duration. Contractor will take immediate
action to correct any deficiency or hazards noted. Remedial action and/or training will be
taken to preclude a repeat of any safety discrepancies found.

29.0

GENERAL SAFETY RULES

(1)

All employees shall comply fully with all laws, orders, citations, rules, regulations,
standards and statutes with respect to occupational health and safety, accident prevention,
safety equipment and practices prescribed by CLIENT, CM, SBG and the Saudi
Government.
Stress will be made on proper housekeeping. Training, lectures and follow up will be
made on this subject.

(2)

Employees physical and mental abilities will be considered to ensure proper job
placement.

(3)

Each employee has a personal responsibility to prevent injury/damage to oneself, to


others and to property.

(4)

Supervisors will conduct frequent inspection of their work areas with the intent of
discovering any hazardous or unsafe conditions that may exist and to eliminate or correct
such condition.

(5)

Soap for hand-washing will be available in ALL toilets at ALL times with an adequate
supply of paper towels.

(6)

Disposable paper drinking water cups are to be used at ALL times. No common metal or
plastic cups are to be used or found on site.

30.0

EMERGENCY PROCEDURES
Different types of emergencies might occur during the period while the Contractor is
operating at this site. There may be an emergency in case of fire. In such an eventuality,
at the guidance of the Project Manager / Site Safety Advisor, the gate watchman will
sound the emergency bell; everyone in the site will assemble at a pre-determined place
(Designated Assembly Area marked with signage) where they will be advised of the
nature of the emergency and what they will have to do etc. Periodic drills will be
arranged to prepare the personnel for this.
At the main gate of the site, an electric bell will be provided which will sound in the case
of an emergency. All will be given enough training to gather near the gate, at an open
area, when the Emergency bell rings.
Depending upon the seriousness of the emergency, the men will be moved out of the site,
or out of the area, through buses, car or by Air as required/demanded.
Page 45 of 59

(1)
(a)

IN CASE OF MAJOR EVACUATION:

Safety Supervisor
The Safety Supervisor is responsible for the organization and controls at the site and
provides direction to all personnel at the scene.
His specific responsibilities are to:
[1]
Develop and implement control tactics
[2]
Assess the situation and direct action to minimize damage and loss of life
[3]
Maintain contact with upper management
[4]
Declare the emergency under control and authorize the all clear signal

(b)

Emergency Coordinator shall:


[1]
Order the general alarm
[2]
Delegate communications controller
[3]
Act as focal point for all information
[4]
Authorize any release of information
[5]
Address all personnel at assembly point

(c)

Security shall:
[1]
Control traffic and personnel entries
[2]
Control road crossing
[3]
Provide head count lists for emergency coordinator
[4]
Prepare for departure
[5]
Log out transportation before personal departure

(d)

Warehouse personnel shall:


[1]
Proceed to assembly point for information
[2]
Man and control warehouse
[3]
Issue emergency equipment as necessary
[4]
Prepare for departure
[5]
Secure warehouse/lay-down yard before departure

(e)

Drivers of evacuation transportation shall:


[1]
Proceed to assembly point for information
[2]
Establish schedule and crew
[3]
Form crew
[4]
Prepare allocated vehicle with the crew
[5]
Prepare for departure on time

(f)

All personnel shall:


[1]
Proceed to assembly point for information
[2]
Establish schedule and vehicle crew
[3]
Assist in vehicle preparations

(g)

Safety Coordinator shall:


[1]
Proceed to assembly point
[2]
Establish schedule
Page 46 of 59

[3]
[4]
[5]

Prepare for departure


Check out all vehicles for emergency provisions and loading
Ensure all personnel are evacuated before departure.

(2)

IN CASE OF FIRE:

(a)

The person discovering the fire shall:


[1]
Sound the alarm
[2]
Fight the fire if safe to do so
[3]
Leave the building
[4]
Proceed to assembly point
[5]
Report to Emergency Coordinator

(b)

Emergency team shall:


[1]
Proceed to assembly point for information
[2]
Form team and plan of action
[3]
Shut off electrical and gas supply risks
[4]
Fight the fire
[5]
Request and direct volunteer assistance if required.

(c)

On duty security officer shall:


[1]
Sound the general alarm
[2]
Man the gate
[3]
Control traffic and personnel entry
[4]
Receive emergency services

(d)

Medical team shall


[1]
Man the first aid center
[2]
Set-up forward emergency post
[3]
Assist emergency team with rescues
[4]
Receive casualties
[5]
Keep ambulance on standby

(e)

Emergency Coordinator shall:


[1]
Direct and coordinate all Emergency Action Plans
[2]
Authorize any requests for outside assistance
[3]
Delegate communication controller
[4]
Act as focal point for all information
[5]
Authorize any release of information

(f)

Safety Coordinator shall:


[1]
Proceed to assembly point for information
[2]
Form emergency team and plan of action
[3]
Lead emergency operations
[4]
Look for the safety of the emergency team
[5]
Advise and keep the Emergency Coordinator informed

Page 47 of 59

(g)

Off duty security shall:


[1]
Proceed to assembly point for information
[2]
Man and control access gates as required
[3]
Control road crossings if required
[4]
Marshall assembly areas
[5]
Provide head count lists for Emergency Coordinator

(h)

General Instruction to be posted in each building:


[1]
On discovering a fire, sound the alarm
[2]
Fight the fire if safe to do so, if not leave the building
[3]
On hearing the alarm, leave the building; walk, do not run
[4]
Make your way to the assembly area, cooperate with any instructions
[5]
Do not return to the building until all clear signal is given

(i)

General Instructions to be posted in security:


[1]
In case of fire, sound the alarm
[2]
Man the main gate, control traffic and personnel movement
[3]
Provide head count list for emergency Coordinator
[4]
Alert off duty security personnel
[5]
Direct personnel to marshalling area

(3)

IN CASE OF GAS CYLINDER INCIDENT:

(a)

Gas leakage:
[1]
Clear the area of non-essential personnel and fire sources
[2]
Wear heat resistant gloves
[3]
Take wrench where required
[4]
Approach from upwind with back up fire cover
[5]
Turn off escape at gas cylinder valve

(b)

Escaping is on fire:
[1]
Clear the area of non-essential personnel and fire sources
[2]
Wear heat resistant gloves and other protective clothing
[3]
Take wrench where required.
[4]
Approach from upwind applying fire fighting agent
[5]
Turn off supply at gas cylinder valve

(c)

Gas cylinder heated by fire:


[1]
Clear the area of non-essential personnel and fire sources
[2]
Fight fire if safe to do so
[3]
Cool cylinders evenly
[4]
Improvise a water reservoir
[5]
Immerse cylinders fully in water for 24 hours

Page 48 of 59

(4)

IN CASE OF SERIOUS ACCIDENT:

At the construction site


[1]
Immediately make the situation safe against immediate danger
[2]
Inform the Safety Supervisor and Medical personnel regarding the accident
[3]
Supervisors/inspectors to assess the accident, e.g. if ambulance and medical team
required to move/transport casualty to the clinic and/or the nearest hospital.
[4]
Victims incurring minor injuries will be brought to the clinic by service vehicles
readily available at the job site.
(5)

EMERGENCY RESPONSE PLAN:

(a)

Purpose
To incorporate OSHA procedures in SBG Project Site emergency response plan.

(b)

Scope
This procedure includes plan development actions in cases of emergencies that might
occur in site during the course of the operation.

(c)

Definitions
[1]

[2]

[3]
[4]
(d)

Emergency is an abnormal incident posing as a threat to the safety of workers,


residents, the environment or property at a facility or site and which can be
brought under control using the resources and procedures for emergency response
in place for the facility or site.
Disaster is an emergency that poses a more serious threat to the safety of
workers, residents, the environment or property at a facility or site and which
cannot be brought under control using the resources and procedures for
emergency response in place for the facility or site.
DCC Disaster Command Center
DCP Disaster Command Post

Responsibilities
[1]
[2]
[3]

Planning Committee to develop an emergency plan using the broad expertise of


its members.
Planning Coordinator to develop an emergency plan and direct its development
through a planning committee.
Safety Manager also responsible for the overall organization and strategy of the
emergency response, coordinates logistical efforts and has the authority for the
final decision in any emergency action. Assume control of DCC.

Page 49 of 59

[4]

Incident Commander (Senior Operations Person) responsible for suppression


and control tactics at site. Establish DCP at a safe location near the emergency
site.

(e)

Emergency Response Procedure (ERP)

[1]

Reporting Emergencies person or persons who first discover the incident should report
to senior operations person using the nearest available communication facility (if
telephone is available, dial 9998 and follow the posted emergency reporting instructions).
Also, Senior operations person could be CM Representative who would report the
incident to the Proponent Representative (or Shift Superintendent) who in turn would
report to the Safety Manager or Contractor Site Safety Advisor who would report to CM
Representative.

[2]

[3]

Initiating the Alarm pre-established appropriate signal alarm (i.e. stop work,
evacuation and all clear) should be sounded to inform all concerned persons within
the vicinity of the emergency and guide them on the specific action they need to take.
Assessing the Situation Senior Operations Persons (i.e. Proponent Representative, CM
Safety Representative will assist on required if necessary) shall assess:
[a]
[b]
[c]
[d]

[4]

The emergency response action taken or being taken.


Additional actions and resources required to control the situation.
Extent of damage to property and harm or negative impact to life.
Existing hazardous condition and their likelihood to escalate.

Mobilization of Resources:
[a]
[b]
[c]

[d]

[e]

A combine resources of both facility & contractors personnel & equipment will
be mobilized to bring the emergency under control. If required, external groups
will be contacted.
Personnel of the combined resources are to proceed to their pre-assigned locations
and await instruction from the Senior Operations Person.
Non-essential plant & contractors personnel are to be evacuated to pre-assigned
assembly areas at a safe distance from the incident scene. Supervisory or assigned
personnel are to take head count and DCC is to organize search and rescue for any
missing personnel.
Support groups such as Security, Medical, and Fire Protection & Maintenance are
to report to their pre-assigned locations and must commence any preauthorized
emergency response related actions.
At least two methods of communication should be available (e.g. radio and
telephone). One in-plant radio channel is reserved as the main communication
link between the Safety Manager and Incident Coordinator.
Page 50 of 59

A telephone number with a pre-recorded message providing essential up-to-date


information on the incident will be established.
[5]

Suppression/Control of Incident Senior Operations Person will identify


emergency/disaster scenario and apply the appropriate suppression/control of the
incident. For instance, when dealing with fire that is generally caused as a result of
ignition of a gas (or liquid) hydrocarbon leak under pressure, unburned liquid
hydrocarbon should not be allowed to pool in the ground and fuel the fire. Capabilities of
the fire fighting system and personnel in place should be continuously monitored and
evaluated to ensure that it is sufficient to suppress or control the incident and if help is
required, to ensure that its quick enough to arrive on time.

[6]

Post Incident Action once an emergency is declared under control by the Safety
Manager, the following actions shall be undertaken:
[a]

Stand Down & Fire Watch the Safety Manager gives the stand down order to
emergency response personnel. Some personnel are released from duty, some are
assigned to gather evidence and others are to maintain a fire watch if there is
danger of re-ignition.

[b]

Investigate and Report incident investigation of causes will be made according to


prescribed procedures.

[c]

Restore Operations post emergency actions which must be followed to restore


normal operations at the facility.

[d]

Revise the Plan all new information gathered as a result of the incident should be
analyzed to determine what improvements could be made to the facility and the work
areas ERP. These improvements should be incorporated into the Plan and all emergency
response personnel should be retrained and drilled to ensure that they are familiar with
and proficient in the updated procedures. All the names related to ERP will be published
in site Notice board with Telephone / Contact No.s to be sent by all at site.

[e]

All the names related to ERP will be published on site notice board with contact Nos. to
been seen by all at the site.

Page 51 of 59

e)

ERP Flow Chart


Emergency Incident
(Fire, Explosion, Flammable Vapor Release etc.)

Initiate the Alarm


(Stop Work, Evacuation, All Clear)

Emergency Reporting
(Methods & Availability of Comm.s. Equipment)
(Reporting to Safety Manager)
(Reporting to CM)

Assess the Situation


(Emergency {e.g. Minor Acc. & Small Fire} or
Disaster {e.g. Major Acc. & Major Fire} )

Mobilize Resources
(Store-yard & Contractors Personnel/Equipment &
External Help when required)

Control the Incident


(Emergency/Disaster Scenario Appropriate
Suppression Methods)

Post-Incident Actions
(Stand Down & Fire Watch, Investigate & Report,
Restore Operations, Revise ERP)

Page 52 of 59

31.0

HAZARDOUS MATERIAL AND WASTE MANAGEMENT

(1)

Wastes such as used oils, used motor vehicle, stationary engine coolant and dead
batteries, etc. shall be collected in proper and sealed containers and disposed off away
from the jobsite, on an approved dumping area or recycling center. Each disposal shall
have a Waste Disposal Certificate noting the waste material producer, transporters, and
end receiver. Each certificate Format shall be made by SBG (or its approved waste subcontractor) and submitted to CM for approval (Contractor to follow S.A.G. certification
guide lines).

(2)

Personnel handling non-toxic materials or waste such as paints, thinners, etc. shall wear
appropriate filtered masks and proper clothing.

(3)

Hazardous chemicals and/or wastes shall be handled in accordance with its corresponding
MSDS.

32.0

CONSTRUCTION SITE SECURITY PROCEDURES


A safe and secure plan will be implemented upon starting mobilization. Two security
men will be in charge of the site security at all times and one additional guardsman will
be on duty during night shift to help securing the site. In addition, Security Personal shall
be trained for Basic Fire Fighting in case of emergency during Night.
Proper logging will be made for all incoming and outgoing men and materials. Regular
workers will have valid ID cards at all times while they are at work site and visitors will
have visitors pass to enter the area. Material receipt forms and delivery logbook will be
available for the incoming and outgoing materials. All tool boxes and high value
equipment will be secured after working hours. All the incoming and outgoing men and
vehicles will be logged in. All the vehicles will be checked when coming in and going
out.
Visitors entry would be restricted and will be allowed only with the proper authorization
of a responsible person.
The lay-down area and offices will be properly fenced to prevent unauthorized entry to
and from site. The numbers of guards will be suitably amended depending on the
requirement. Proper lighting will be installed in the site area.
The logging system will include all the activities of the area, such as the change of shift,
any movement of men and materials, any unusual incident that occurs.
No cooking or open fires will be allowed on the site. All equipment operators and drivers
will have valid driving licenses and all the equipment will have valid stickers (as may be
required).
Contractors security force will inform CLIENT security personnel of any unusual events
at any time and they will be provided with emergency numbers to call.
Page 53 of 59

33.0

DEMOBILIZATION PLAN
On satisfactory completion of this project, the Contractor will prepare a detailed
mobilization plan and submit to CM for approval. This will include removal of all the
manpower, equipment and facilities in a phased manner. The office and lay-down areas
and any other areas utilized during construction will be returned to its original condition
and the site will be free from debris & foreign objects. Site inspection will be requested
from CM Representative to ensure that the site is satisfactorily cleaned and restored.

34.0

ABRASIVE BLASTING & PAINTING/COATING


In addition to the usual hazards associated with construction activities, workmen
engaged in painting shall be provided with masks having appropriate filters for the vapor
involved.
There is no abrasive cleaning operations associated with this project. (If used the correct
protective clothing and gear should be used)

35.0

LOCK OUT AND TAG OUT SYSTEM


A lock out and tag system will be established in strict compliance with CLIENT &
SBG standard procedures and as stated in HSE Plan.
Maintenance men will ensure that the controls of the equipment they are working on
will be properly locked and tagged in the off position before leaving.
To prevent any accident caused by mistakes such as starting equipment on which
maintenance men are currently working on, controls will be locked in the off position.
Supervisors and maintenance personnel will become knowledgeable of the rules in
SBG standard procedures Isolation, Lock Out and Use of Hold Tags, and will teach
their crew the lockout procedures and ensure that they are followed accordingly.
-

The purpose of the Lockout System is to render controllers inoperative, i.e. circuit
breakers, disconnect switches, valves etc. on any system (electrical steam, water, acid
etc.) where the operation of the control device could be hazardous to personnel.
Hold Tags and Locks are primarily intended to protect the individual doing the work
from being injured by an inadvertent start-up.
Work permit issuers and operations supervisors shall ensure that hold tags and lock
outs are used and noted on the work permit. The use of hold tags/lock outs shall be
strictly enforced.

Page 54 of 59

36.0

SAFETY TRAINING, MEETINGS, REWARDS, and COMMITTEES:


It has to be noted that apart from Induction Training and Tool box meetings, there are
some other training, meetings, rewards, and committees that are part of SBG safety
program as detailed herewith:
Daily Safety Briefing-Contractor shall conduct a Daily Muster for all personal and a Site
briefing about the day to day safety requirements and the good work, problems and safety
violations encountered during the previous day, Warning, dismissals and the precautions
taken.
Contractor shall make the work groups aware of the days work and when any specific
job is carried out. Contractor will also make use of this occasion as a Head count for the
days start and punctuality.
Daily Safety Pre-Task Planning and Training-Contractors supervisors shall hold
informational safety training with each member of their crew. Information discussed and
training performed shall pertain to current work activities and scope of work. A Sign Off
shall be arranged after every days briefing by the Supervisor of the group, for recording.
Contractors shall use this time for employee input and task-specific training and shall
daily recoded for review at any instant by Safety Representatives of CM.
Toolbox Meetings-Contractors Safety Representative shall coordinate and implement
Safety Tool Box meetings.
Emergency Response Plan Training-Contractor shall arrange Emergency Response
Plan (ERP) training during the employee orientation and re-training shall be conducted
periodically in safety meetings. The ERP training shall include the procedures for
reporting to external emergency response organizations, building or site evacuation,
designated evacuation assembly areas, and methods of accounting for staff upon
evacuation. Emergency drills will be performed periodically, but at least twice per year
and as and when required by CM.
Competent Persons Training-Contractor shall arrange training programs for certain
Tradesmen for getting the Certification as Competent Persons by a 3rd Party Organization
approved by SAG.
Training shall be arranged for Crane Operators, Banks Man, Wire Rope Inspector,
Electricians, Gas Tester for confined spaces, Confined space workers, Scaffold Inspector,
Scaffold Erector and First Aider each as require by the Site activity.
Contractor can Asses and Certify certain other trades man as Competent Persons with
their Service Certificates and Trade Training Certificates obtained from their home
countries, their Documents shall be submitted to CM prior to the personal commence

Page 55 of 59

work at site. Their documents shall be approved subject to supervision of their work by
Resident Engineer.
Contractor shall arrange sign off form from individual personal that he is being well
briefed about his job and his profession; this will include general construction helpers
too. (e.g.: Carpenters, Masons and Tile Workers etc.)
The Training Programs which are conducted by Saudi Government Authorities (If
Applicable) and Related Institutions too will be considered as Competent Persons
Training as they will be issued with a Permit or Certification to Attend to the particular
job.
Contractor shall provide a list of competent persons to CM prior start work. When new
personal are brought to site same procedure shall be followed.
Contractors Site Safety Committees-Contractor shall call a site safety committee to
address issues pertinent to the construction activities. This committee will be chaired by
the Project Manager and meet a minimum of once per month, with more frequent
meetings called in the event of a serious incident or in any special event. The committee
shall compose of Management, Engineers, Supervisors, Site Safety Advisor and
Construction representatives from each work group or each subcontractor.
Contractor shall appoint committee members from all trade groups as required. The
committee will review items that affect the health and safety of workers onsite and
develop/update rules and regulations based on activities and past experience on the
worksite. It is the committees responsibility to review all serious incidents, near misses,
and dangerous occurrences. CM and Staffs Site Audits and Inspections findings and
corrective action taken by Contractor shall be presented to the committee at the meeting.
Each month, one committee member will speak on health and safety at the worksite to
promote safety awareness.
Contractors Site Safety Advisor shall act as Secretary and Advisor to the Project
Manager and committee and shall keep records of the meeting minutes and inspection
reports.
These documents will remain onsite until completion of the Site. Minutes of the meeting
will be copied to CM. Meeting agenda will be as follows:

Confirmation of Minutes.

Matters arising from previous meetings.

Chairmans (PM) Review/Overview of Site Safety Performance and/or condition.

Report from the Site Safety Advisor and his Staff.

Page 56 of 59

Review of project Health and Safety Plan Identification of changes and new
hazards.

Incident and Accident Investigation/Dangerous Occurrence Report.

Safety Talk by Committee Members.

Report from the Health and Safety Representative.

Any Other Business/ and conclude.

Supervisors Meeting after Lost Time Injury.(LTI)-Contractor PM shall arrange a


meeting with all the Supervisors after any incident causing Lost Time (LTI).
LTI Any other injury, excluding occupational disease, which results in the person being
hospitalized for more than 24 hours, unless detained solely for observation.
Contractors Manager and Safety Representative shall lead the meeting and Discuss
about the incident highlighting the immediate Cause, Root Cause and basic Cause of the
incident / accident.
Contractors Safety Representative Shall discuss the possibilities of eliminating the facts
lead to accident and Answers to who, what, when, where, and how questions.
Contractor shall determine where supervision failure occurred and what the cause was,
and why it was not foreseen whether due to personal/job factors. Contractors remedial
actions shall be taken to avoid repetitions of such incidents.
This meeting shall be notified to CM, he may decide to participate or appoint CMs
Safety Representative. A sign off document shall be completed, and at the end of it shall
be attached with Minutes of meeting for future references and a copy to be forwarded to
CM.
Safety Representatives Meetings-Contractor shall appoint minimum of one Safety
Coordinator from each work group to deal Safety matters with Site Safety Advisor /
Safety Officers of the Contractor.
Contractors Site Safety Advisor shall constantly have coordination and conduct pocket
meetings with them related to Safety matters in weekly basis for duration of 10 minutes
at a site location and have a Sign Off from all attended.
Reward Scheme-Reward scheme shall be introduce by the Contractor in order to reward
the employees in monthly basis with a Certificate and a Cash reward to encourage the
employees in Safety. This shall be awarded monthly for one or more employees
depending upon the no of employees available at Site.
This Reward will be awarded in the Monthly Safety Meeting which will be held at Site
and where all the Contractors Staff and Employees will be present.
Page 57 of 59

Persons will be named as SAFE WORKER/WORKERS of the Month and his name
will be published in Site Notice Boards and in the Site.
Actions that qualify are those that go above and beyond what is expected:

Interest shown to use his own safety equipment, seatbelt etc.

Actions that will be rewarded include spotting and correcting a hazard

Bringing a hazard to the attention of your foreman

Telling your foreman about an incident

Coming up with a safer way to get the work done

Stopping a crew member from doing something unsafe etc.

Doing the work according to the requirement using correct methodology and
follow instructions of superiors as required for work.

For punctuality

Reporting Unsafe Conditions or Practices

Responsibility for effective HS management extends to all levels of the Construction and
requires good communication between subcontractors, employees, supervisors, and
management. Accident prevention requires a pro-active policy on near misses, close calls,
unsafe conditions, and unsafe practices. All personnel must report any situation, practice,
or condition which might jeopardize the safety of the Site. All unsafe conditions or
unsafe practices shall be corrected immediately.

37.0

DEMOLITIONS:
All demolition activities shall strictly follow OSHA Subpart T Section 1926.850
through 1926.859. CM will be notified for inspection on require by Construction
Procedure.

38.0

SIGNAGE:
All project signage shall follow applicable SAG, regulations and specifications. A sample
from each sign to be used shall be submitted to CM for approval before fabrications.
Additional final inspections shall be requested before using any signage after installation.

39.0

MONITORING SYSTEM PERFORMANCE

39.1

A set of health and safety targets has been issued by the HSE Department that meet the
objectives set by the Company addressing the topics listed below.

First aid cases


Accidents that result in lost working time
Reported near misses
Page 58 of 59

The number of toolbox talks held


The number of surveillance audits and inspections
The number of incidents involving asset damage

39.2

The project managements performance against these targets is monitored by internal


audit, surveillance audit and routine inspection (see system procedure Maintenance of
project) and by accident investigation (see general procedure Emergency Planning and
Accident Reporting). The statistics are reviewed monthly by the HSE Department led by
site safety advisors and any action to correct deficiencies in implementation or to
prevent a potential deficiency are discussed and developed with project management.

39.3

The HSE Advisor shall conduct a surveillance audit at least once every three months
and issue the report, with an evaluation of the projects safety performance, to the Site
Project Manager.

39.4

Selected processes related to the management of safety may be monitored from time to
time.

40.0

RECORDS

40.1

No records are generated by this project Safety plan.

40.2

Records generated by referenced procedures shall be managed in accordance with the


originating procedure.

Page 59 of 59

ANNEX A
OFFROAD DRIVING PROCEDURES
AND SEARCH & RESCUE OPERATIONS

A-1

SAUDI BINLADIN GROUP

Project: King Abdulaziz International Airport Development Project Phase-1

OFF-ROAD DRIVING PROCEDURES AND


SEARCH & RESCUE OPERATIONS

CONTROLLED COPY :
COPY NO. :
UNCONTROLLED :

A-2

AMENDMENT RECORD
DOC
REF.

CHANGE
NO.

REVISION
FROM
TO

BRIEF DESCRIPTION
OF CHANGE

DATE

SIGN

A-3

INDEX

Cover sheet
Amendment Record
Index
1.0

Objective

2.0

Scope

3.0

Definitions

4.0

Responsibilities

5.0

Associated Documents

6.0

Methods

7.0

Records

A-4

1.0
1.1

OBJECTIVE
To provide guidelines for safe off-road driving to all drivers and/or commuters driving
within the vicinity of THE PROJECT Site Preparation Area I and establish procedure
for search & rescue operations in case of loss or when getting stranded.

2.0
2.1

SCOPE
This procedure includes guidelines and practices for off-road driving and search & rescue
operations applicable to the terrain of THE PROJECT Site.

3.0
3.1
3.2
3.3

DEFINITIONS
DIP Driver Improvement Program (as mention in Section 8.5, Training in site,
Induction)
G.I. General Instruction
EMS Emergency Medical Services

4.0

RESPONSIBILITIES:

4.1

PROJECT MANAGER ensure compliance by all personnel, including Sub-Contractor


and all parties, to this procedure and the Project Safety Program. Review and approve
DIPs.

4.2

PROJECT SITE SAFETY ADVISOR shall be responsible to the Project Manager for
the actual implementation, monitoring and revise, if necessary, of this procedure. Ensure
that all drivers are being oriented, trained and comply with the requirements of this
procedure.

4.3

TRANSPORTATION MANAGER reporting to the Project Manager and responsible


for vehicle conditioning, including repair, maintenance, vehicle distribution and trips
scheduling. Ensure that all drivers comply with Saudi Arab Government, and company
requirements.

4.4

DRIVERS:
a.
b.
c.
d.
e.

Ensure that his vehicle is safe to drive.


Comply with repair & maintenance when they are scheduled.
Loads are properly secured and tied-down.
The use of seat belts, including passengers.
Follow all the requirements of this procedure.

5.0

ASSOCIATED DOCUMENTS

5.1
5.2

Contractors HSE Plan


G.I. Control of Remote Area Travel and Search & Rescue Procedures

6.0

METHODS

A-5

This Procedure describes the actual steps to be taken and sequence of activities required
for proper implementation of this procedure:
6.1

Preparation prior to embarking on an off-road trip, specifically, in THE PROJECT


Area, the following requirement shall be satisfied first:

6.1.1

Vehicle Condition condition of the vehicle shall be evaluated if it can effectively handle
the rigors of off-road driving (engine, lights, tires, windows & windshields, doors,
mirrors, etc.)

6.1.2

Vehicle Identification vehicle number, company name, license plates (front & back) shall
be legible and in place.

6.1.3

Seat Belt & other vehicle safety features are in good working order.

6.1.4

Driver Training drivers shall undergo orientation of the hazards of their destination and
shall be trained on how to avoid and/or prevent being a victim of those hazards.
Basically, no driver shall be allowed to drive off-road without proper training &
orientation on survival and rescue techniques and procedures.

6.2

Off-Road Driving the following steps shall be followed when driving off-road:

6.2.1

Destination, route, expected time of arrival to/from site/base shall be advised to the
Transportation Manager. Search and rescue shall be conducted immediately should the
driver didnt come back or arrive at his destination at expected time. EMS shall be made
part of the search and rescue team.

6.2.2

Adequate fuel, oil, spares, food and water shall be taken along when embarking on a trip
with unfamiliar terrain and/or to sustain the driver and passenger until rescue, should he
be stranded.

6.2.3

When unsure of the off-road surface being driven over, stop the vehicle and investigate
the surface. Only when driver is satisfied that the vehicle can safely pass over the
investigated surface should he proceed with the trip.

6.2.4

If communication gadget is working on the area of the drive, periodically report location
and speed to base. Base should record the time of the report, speed & location reported,
to calculate approximate location should communication will no longer be available
during the course of the drive.

6.2.5

When lost or stranded, dont panic, driver including passengers, must stay with the
vehicle as it provides shelter and to make it easier for searchers to locate them. On
scheduled stops, as much as possible, ensure that vehicle is always visible.

6.2.6

Drivers who have successfully traveled an unfamiliar route and/or destination shall report
to Transportation Manager and assist in mapping out the route for use by others who will
be utilizing the same route. Such report shall include problems encountered, safe stop-

A-6

overs, source of food and water, if any, plus improvements that can be made for the next
traveler.
7.0

RECORDS

All records attesting to conformity to this procedure, relevant standards and resulting
work, shall be kept, maintained and revalidation performed as necessary, by the Projects
Safety Department.

A-7

ANNEX B
WASTE MANAGEMENT PLAN

B-1

SAUDI BINLADIN GROUP

Project: King Abdulaziz International Airport Development Project Phase-1

WASTE MANAGEMENT PLAN

CONTROLLED COPY :
COPY NO. :
UNCONTROLLED :

B-2

AMENDMENT RECORD
DOC
REF.

CHANGE
NO.

REVISION
FROM
TO

BRIEF DESCRIPTION
OF CHANGE

DATE

SIGN

B-3

INDEX

Cover sheet
Amendment Record
Index
1.0

Objective

2.0

Scope

3.0

Definitions

4.0

Responsibilities

5.0

Associated Documents

6.0

Methods

7.0

Records

B-4

1.0

OBJECTIVE

1.1

To ensure implementation of waste management plan complies with generally accepted health
concepts and provides protection of health and welfare of users.

2.0

SCOPE

2.1

This procedure includes waste management practices (construction & maintenance)


applicable to Contractor provided Temporary Facilities to a quality level based on
applicable industry codes and standards and/or as determined by Project

3.0

DEFINITIONS/REFERENCES

3.1

3.2
3.3

SAG Sanitary Code


MSDS Material Safety Data Sheets
G.I. General Instruction

4.0

RESPONSIBILITIES:

4.1

PROJECT MANAGER ensure compliance by all personnel, including Sub-Contractor

and all parties, to this procedure, the Project Safety Plan and relevant Clients
Specifications.
4.2

PROJECT SITE SAFETY ADVISOR shall be responsible to the Project Manager for all

waste management activities performed by site personnel. Ensure that all these activities
are done in a timely manner and in compliance with the approved procedures,
specifications, drawings and all relevant documents. Coordinate with Project Manager for
the determination of problems that may arise during construction and implementation.
4.3

ENVIRONMENTAL COORDINATOR responsible in the actual implementation of this

procedure and coordinate with Project Safety Manager regarding schedule of activities,
manpower & equipment requirement and any other incidentals required in performing the
works.
5.0

ASSOCIATED DOCUMENTS

5.1
5.2
5.3
5.4
5.5

The Contract
Project Specifications
Contractor Project HSE Plan
SAG Sanitary Code
Material Safety Data Sheets

B-5

6.0

METHODS
This Procedure describes the actual steps to be taken and sequence of activities required
for proper implementation of the waste management plan:

6.1

Waste Classification SBG envisaged to handle three (3) types of wastes, as follows:

6.1.1

Solid Waste composed of construction debris, concrete truck mixer, solid trash,
leftover food, packaging, and any other type of solid waste that can be delivered to
designated waste handling facility without special requirements.

6.1.2

Sanitary Wastewater and Sewage used water and sludge from toilet/bathroom.

6.1.3

Chemical Waste chemicals & gases required for construction, operation and
maintenance of equipment, water treatment and insect/rodent control.

6.2

Waste Management

6.2.1

Construction & Operation of Waste Management Facilities


Waste management facilities shall be provided to commensurate with the type of waste to
be handled or treated. The following facilities shall be constructed (required if hook-up to
existing facility is not possible) and maintained in accordance with
MSDS requirements and any other generally accepted industry codes and standards:
6.2.1.1 Solid Waste Processing & Disposal Facility SBG, with the approval of CM
Representative, is planning to utilize existing facilities within THE PROJECT
Site or if not available, the nearest government approved disposal area, for
processing and disposal of solid waste. Prior to final disposal, the following shall
be done:
6.2.1.1.1

Trashcans shall be provided in certain areas of the site, offices, laydown yard and construction site to collect trash. These shall be
emptied and sanitized regularly.

6.2.1.1.2

Trash collected shall be transported in such a way as to prevent


spillage during transportation and shall be disposed in the designated
disposal area only.

6.2.1.1.3

Final disposal shall be done in accordance with the established


procedures for operation and maintenance of the existing facility.

B-6

6.2.1.2 Sanitary Wastewater and Sewerage System this facility shall be provided to
be used for handling liquid waste and sludge. The whole system will be composed
of:
6.2.1.2.1
6.2.1.2.2

6.2.1.2.3

Sewer System shall be constructed to service temporary facilities


such as site, offices and lay-down yard. For workers toilet in the
jobsite, portable chemical toilets shall be utilized.
Septic Tanks should hook-up to existing sewage disposal system is
not possible, a septic tank shall be provided and shall be emptied
regularly by Vacuum Tanker.
Disposal of Raw Sewage SBG shall dispose raw sewage to a
facility as designated by CM Representative, preferably within the
vicinity of the project Area or to a government approved disposal area
nearest the project site.

Construction of Sanitary Wastewater Facility & Sewerage System shall be in


accordance with all applicable requirements.
6.2.1.3 Chemical Waste this type of waste shall be kept in containers clearly labeled
with each content and only one type of waste shall be kept in each container. A
control system shall be established with a file and data sheets made available at
the work area and to ensure that all precautions are applied when handling,
storing, and disposal of this type of waste, as follows:

6.2.1.3.1

Handling orientation and briefing of personnel working with or


handling certain type of chemicals shall be done to identify the health
hazards, flammable limits, handling & storage and first aid should an
incident occurs, for every specific chemical that will be used in site.

6.2.1.3.2

Storage chemical waste shall be stored in approved areas only


using airtight containers and clearly labeled. Segregation of each type
of chemical shall be done to prevent chemical reaction and to identify
which type could be recycled and those intended for final disposal.
Project Site Safety Advisor, in coordination with the site Supervisor,
shall determine type and volume of waste to be stored

6.2.1.3.2

Disposal chemical waste identified for final disposal shall be


disposed in an approved SAG facility and will be notified to CM.

Even though the type of chemical waste that will be used in this project has been predetermined to be minimal in terms of toxicity and quantity, regulations concerning
delivery, reception and disposal will be followed as outlined by CM guidelines.
Handling, storage and disposal of chemical waste shall be in accordance with applicable
provisions of Material Safety Data Sheets.
B-7

6.2.2

Insect & Rodent Control it is SBG primary objective to ensure that the site with all its
-

facilities and its surrounding areas shall be insect and rodent free. Residents shall be
briefed on diseases and inconvenience that these insects and rodents would bring and
shall be advised to abstain from doing acts that would attract the same.
In order to ensure that this objective will be achieved, SBG shall employ the services of
Insect & Rodent Control Specialist, who would have a periodic visit in site to apply
preventive measures. Such measures shall be made to comply with applicable provisions
of Saudi Agent Sanitary Code (SASC-S-08.)
6.2.3 Oil Spillage Control personnel handling fuel/oil shall be briefed on the preventive
measures required to prevent fuel/oil spillage. Probable causes have been determined to
have originated from fuel transfer operation and during equipment maintenance. To
prevent spillage, leak free equipment shall be provided during fuel transfer and airtight
containers shall also be provided during equipment maintenance. In the event of a major
spillage, the following shall be done:

6.2.3.1 SBG shall promptly notify the CM.


6.2.3.2 SBG shall comply with the land oil spill General Instruction (OSHA, 1910.1052,
APP. A), A summary of the typical response is given below: Notify the HSE Advisor and the Project Manager immediately. Eliminate sources of
ignition near spill area.
When it can be performed safely, stop source of spill and contain spilled material using
absorbent pads and booms within as small an area as possible. The spill should
not be rinsed away.
The HSE Advisor and the Project Manager will secure the area and establish perimeter
control at a safe distance from the spill.
Screen and cover stockpiles of polluted matter to prevent dispersion. Seal off drains that
polluting matter may enter.
If an immediate threat to human health or the environment does not exist, the HSE
Advisor and the Construction Manager will arrange for safe clean up of the spilled
materials.
Contaminated soils and clean-up materials from such spills must be handled properly and
placed in a suitable container that is then labeled and stored in the appropriate location
for subsequent disposal.
If the pollution incident impacts any resources, the appropriate agency or authority must
be contacted as soon as possible.
A hazardous material incident control guide will be developed for use by the emergency
response team to achieve the above.
The pollutant shall be contained and cleaned up, and the incident reported to the
appropriate authorities.
6.2.3.3 Any recovered hydrocarbon or hydrocarbon-contaminated material shall be
properly disposed, recycled if possible or disposed as per G.I.
B-8

7.0

RECORDS

All records attesting to conformity to this procedure, relevant standards and resulting
work, shall be kept, maintained and revalidation performed as necessary, by the Projects
Safety Department.

B-9

ANNEX C
EMERGENCY PROCEDURES
INCLUDING (FATAL ACCIDENT PROCEDURES)

C-1

SAUDI BINLADIN GROUP

Project: King Abdulaziz International Airport Development Project Phase-1

EMERGENCY PROCEDURES

CONTROLLED COPY :
COPY NO. :
UNCONTROLLED :

C-2

AMENDMENT RECORD
DOC
REF.

CHANGE
NO.

REVISION
FROM
TO

BRIEF DESCRIPTION
OF CHANGE

DATE

SIGN

CM
Approval

C-3

INDEX

Cover sheet
Amendment Record
Index
1.0

Objective

2.0

Scope

3.0

Definitions

4.0

Responsibilities

5.0

Associated Documents

6.0

Methods

7.0

Records

C-4

1.0

OBJECTIVE

1.1

To provide a guideline on the proper and organized response in cases of emergencies that
may occur within the vicinity of the project Site Preparation.

2.0

SCOPE

2.1

This procedure applies to cases of emergencies deemed specific to SBG Project Site
Preparation.

3.0

DEFINITIONS

3.1
3.2
3.3
3.4

CSM Construction Safety Manual


G.I. General Instruction
EMS Emergency Medical Services
ERT Emergency Response Team

4.0

RESPONSIBILITIES:

4.1

PROJECT MANAGER - ensure compliance by all personnel, including Sub-Contractor


and all parties, to this procedure and the Project Safety Plan. He shall also act as the
Emergency Commander and assume control of emergency response activities,
coordination with CM on-site Emergency Commander, assess the emergency situation
and direct actions to minimize damage and injury, ensure adequate facilities and
equipment is on site to conduct rescues.

4.2

CONSTRUCTION MANAGER serves as the direct and immediate contact for


workers on site during emergency situation, determine and ensure that the work site is
under control and safe to work in and provide assistance to the Project Manager in
implementing the Emergency Response and Evacuation Plan. Evacuation plan will be
submitted for each site. He shall also act as Emergency Commander and assume all
responsibilities in the absence of Emergency Commander.

4.3

PROJECT SITE SAFETY ADVISOR reporting to the Project Manager and shall be
responsible for the actual implementation, monitoring and revise, if necessary, of this
procedure. Ensure that all site personnel are being oriented, trained and comply with the
requirements of this procedure. In cases of actual emergency, shall also act as the Team
Leader of the Emergency Response Team (ERT).

4.4

PROJECT SAFETY OFFICERS - shall be responsible in monitoring &


implementation of this procedure thru the supervision and instruction of the Project
Safety Supervisor.

4.5

FIRE BRIGADE in case of fire, shall be responsible for fire fighting and the safe
evacuation of personnel and properties. Conduct inspection, testing & maintenance of fire
protection equipment in accordance with standard procedures of SAG.

C-5

4.6

MEDICAL TEAM led by the Site Nurse and shall be responsible in providing first
aid, EMS and medical evacuation should more medical attention is required.
Medical Team shall also:
-

Assess injuries, provide medical emergency medical care and triage tags
appropriately.

Advise the Emergency Commander regarding injured personnel, medical


requirements, evacuation priorities or the need to implement Medivac Procedures.

Maintain disaster supplies for use in the emergency vehicles during search and rescue
operations.

4.7

EMERGENCY RESPONSE TEAM shall be responsible in responding to


emergency situations (this will be organized by the Safety Supervisor and shall be
composed mostly of the key personnel in the Fire Brigade and the Medical Team).

4.8

ALL EMPLOYEES all employees with assigned responsibilities, upon hearing the
alarm shall proceed to the Assembly Areas and await instructions (Assembly Areas are
designated & identified with posted signboards inside the site Offices. Worksite
assembly areas are the loading/unloading areas of workers in their respective sites).

5.0

ASSOCIATED DOCUMENTS

5.1

Contracts Safety, Health & Environmental HSE Plan

6.0

METHODS
Different types of emergencies might occur during the course of the project, with our
previous experience in working on the same type of work, and in the same work
locations, combined with relevant provisions from SBGs (HSE) Safety Plan; we
developed and maintained the following emergency response procedures to emergency
cases that has the possibility of occurring in the jobsite.

6.1
6.1.1

Emergency Response Procedures:


Identification & Classification of Emergency Response Levels Saudi Binladin Group
& Sons Co., have identified four (4) response levels according to the nature of the
problem and are deemed applicable to all Saudi Projects:
Level 1 Minor Incidents incidents that have no serious risk to facilities or
personnel and can be handled by personnel in the immediate work area. Such incident
shall be resolved and documented and to be reported to the concerned person of the
company, as well as CM.

C-6

Level 2 Emergency incidents that require assistance of CM and Safety Section and
can be controlled by local resources and services within the vicinity (this does not require
total site evacuation, however, in case of fire, it will require initiation of alarm and
evacuation of affected facilities, medical treatment and hospitalization of injured
personnel.)
Level 3 Search and Rescue shall be initiated when an employees expected arrival
time at his destination is overdue or he needs assistance in a remote area and/or in the
desert. This may also require assistance from CM.
Level 4 Disaster incidents that cannot be controlled by local resources and needs
CLIENTs assistance or calling 9998(Airport) for further assistance. It is the highest level
of emergency that requires the initiation of alarms or siren, total evacuation of the
worksite and requires all personnel to proceed immediately to the designated evacuation
assembly areas.
6.1.2

Reporting Emergencies all personnel, during one of the Tool Box Talks, were briefed
on how to report incidents. Person or persons who first discover the incident should
immediately report to any of the responsible persons as shown in the attached listing.
Responsible person, whom the incident is reported, will immediately take action or
contact the appropriate personnel or department available, who could best respond to the
incident effectively.

6.1.3

Sounding The Alarm in incidents where the attention of all site occupants or site
personnel are required, the alarm (siren) shall be sounded, to inform everybody within the
vicinity of the emergency and guide them on the specific action they need to take. Alarm
system shall be regularly tested and tagged and can be heard throughout the site.

6.1.4

Assessing the Situation & Mobilization of Resources Site Safety Advisor, along with
the responsible persons of the site, shall assess the emergency and shall act accordingly.
Ensure enough resources are being mobilized and suitable measures applied.

6.1.5

Suppression/Control of Incident ERT shall take control of the situation and ensure
appropriate suppression/control of the incident had been applied with. Provide additional
resources, if required, to control the situation or when condition becomes hazardous or
there is likelihood of escalation. Monitoring and supervision of applied actions shall be
continuously conducted until such time the situation is under control.

6.1.6

Post-Incident Actions:
-

The ERT Team Leader gives the stand down order to emergency response team,
with a few team members maintaining a fire watch (if fire incident) and prevent reignition. Restore normal operations when deemed safe to do so.

C-7

6.2

Investigate & Report ERT Team Leader to investigate causes and effects of the
incident in accordance with applicable procedures, as per SBG HSE Plan and
prepare/submit report of the incident.

Lessons Learned the incident shall be made as basis for establishing and
preparation of future actions to prevent recurrence of the same incident.

Emergency Procedures:
Below are some of the emergency procedures established to certain emergency cases, and
discussed during Site Tool Box Talks (all employees shall be instructed in the Emergency
Procedures for them to know what do or where to go in cases of emergency). In all cases
and to some other emergencies not mentioned, the sequence of activities shall be in
accordance with the above Emergency Response Procedures.

6.2.1

In Case of Fire
- Sound Alarm
- Inform Responsible Persons or ERT (see attached listing)
- Mobilize Site Fire Brigade
- If Site Fire Brigade is not sufficient, call CLIENT or 9998 for Airport Fire
Department.
- Those who are not involved in fire-fighting should follow in orderly manner, the
instruction of ERT Team Leader.

6.2.2

In Case of Injuries
- Inform the Medical Team (or any of the Responsible Persons who will arrange for the
appropriate person to attend to the incident).
- Medical Team to apply first aid.
- If Medical Teams first aid is not enough, call the nearest Hospital (see attached list)
and bring patient by Site Ambulance. If medi-vac (air-lift) is required, dial 998 or
ERT Team Leader to coordinate with CLIENT Fire Dept (Airport).

6.2.3

In Case of Vehicular Accident


- Inform Responsible Persons or ERT
- ERT to secure the area to prevent other accidents
- Medical Team to apply first aid or bring patient to nearest hospital. ERT Team
Leader to arrange medi-vac (air-lift: if required.
- Dial 999 for SAG Police and/or 9998 (note: do not attempt to move the vehicles
involved in the accident unless advised by the police).
- Clear the accident area (after police permission).

7.0

RECORDS
All records attesting to conformity to this procedure, relevant standards and resulting
work, shall be kept, maintained and revalidation performed as necessary, by the Projects
Safety Department.
C-8

SAUDI BINLADIN GROUP

Project: King Abdulaziz International Airport Development Project Phase-1

FATAL ACCIDENT PROCEDURES

CONTROLLED COPY :
COPY NO. :
UNCONTROLLED :

C-9

INDEX

Cover sheet
Amendment Record
Index
1.0 Objective
2.0 Scope
3.0 Definitions
4.0 Responsibilities
5.0 Associated Documents
6.0 Methods
7.0 Records

C-10

1.0

OBJECTIVE

1.2

To provide a guideline on the proper and organized response in cases of fatal accidents
that may occur within the vicinity of the project Site Preparation.

2.0

SCOPE

2.1

This procedure applies to cases of fatality deemed specific to SBG Project Site
Preparation.

3.0

DEFINITIONS

3.1
3.2
3.3

C S M Construction Safety Plan


G.I. General Instruction
H S E Health and Safety Engineer

4.0

RESPONSIBILITIES:

4.1

PROJECT MANAGER - ensure compliance by all personnel, including Sub-Contractor


and all parties, to this procedure and the Project Safety Program. ensure adequate
facilities and equipment is on site to conduct rescues.

4.2

CONSTRUCTION MANAGER serves as the direct and immediate contact for


workers on site during fatal situation.

4.3

PROJECT SITE SAFETY ADVISOR reporting to the Project Manager and shall be
responsible for the actual implementation, monitoring and revise, if necessary, of this
procedure. Ensure that all site personnel are being oriented, trained and comply with the
requirements of this procedure.

4.4

PROJECT SAFETY OFFICERS - shall be responsible in monitoring &


implementation of this procedure thru the supervision and instruction of the Project
Safety Supervisor.

5.0

ASSOCIATED DOCUMENTS

5.1

Contracts Safety, Health & Environmental (HSE) Plan.

6.0

METHODS

In the event of fatal accident, SBG shall immediately inform CM supervising engineer and CM
HSE coordinator and submit with 24 hours of the accident at least (as a form [A]-SP-01-S11,
App. D), the following information in the specified format to CM:
1. A completed accident report, including photographs;
2. An event log;
3. Site medical report;
C-11

4.
5.
6.
7.

Hospital medical report;


Police case number;
Police investigation report;
Written police permission to reopen construction site area where accident
occurred;
8. Where applicable, a list of persons charged by police;
9. Where applicable, the names of persons or persons dismissed by the contractor
who, in his opinion, failed in their safety responsibilities;
10. Insurance settlement to the next of kin of deceased;
11. Proposed changes to site conditions to prevent a recurrence of events that lead
to the accident
NOTE: where some of the above are not available at the time of submission, these shall
be submitted when available.
After each and every fatal accident, the PM shall hold a formal enquiry into the accident
attended by senior CM site management, the contractors site and head office
management and CM SAFETY Section. The outcome of the PM enquiry will be
submitted to all parties, and CM SAFETY Section.
7.0

RECORDS
All records attesting to conformity to this procedure, relevant standards and resulting
work, shall be kept, maintained and revalidation performed as necessary, by the Projects
Safety Department. It has to be noted that fatal accident form as shown in see Annex-D.

C-12

ANNEX - D
SAFETY REPORTING FORMS

SAUDI BINLADIN GROUP

Project: King Abdulaziz International Airport Development Project


Phase-1
SAFETY REPORTING FORMS

CONTROLLED COPY :
COPY NO. :
UNCONTROLLED :

STANDARD FORMS
Title

Reference

Rev.

Pages

MONTHLY CONTRACTORS SAFETY REPORT

[A]-SP-01-S01

INJURY SUMMARY

[A]-SP-01-S02

PRELIMINARY ACCIDENT REPORT

[A]-SP-01-S03

FATAL ACCIDENT REPORT

[A]-SP-01-S04

INTERNAL INCIDENT REPORT

[A]-SP-01-S05

VOILATION REPORT

[A]-SP-01-S06

DAILY INSPECTION CHECK-LIST

[A]-SP-01-S07

DAILY REPORT

[A]-SP-01-S08

PROJECT SITE SAFETY COLOR CODING

[A]-SP-01-S09

FIRE FIGHTING EQUIPMENT, EMERGENCY


LIGHTING

[A]-SP-01-S10

TRAVEL LOG

[A]-SP-01-S11

VISITORS LOG

[A]-SP-01-S12

STATISTICAL MONTHLY SAFETY REPORT

[A]-SP-01-S13

STATISTICAL WEEKLY SAFETY REPORT

[A]-SP-01-S14

TOOL BOX MEETING MINUTES

[A]-SP-01-S15

SAFETY BOARD

[A]-SP-01-S01
[A]-SP-01-S01

MONTHLY CONTRACTORS SAFETY REPORT (Page 1 of 2)


PROJECT TITLE

LOCATION:

CONTRACTOR:

MONTH:_

CONTRACT NO.:

1.

2.

PROJECT INFORMATION:
a)

Total Man-hours Worked /Monthly

b)

No of Employees (Last Day)

c)

No of Safety Officers at Site

HEALTH & SAFETY INCIDENTS /MOMTHLY :


d)

Fatalities (FAT)

e)

Lost Time Accident (LTA)

f)

Restricted Work Cases (RWC)

g)

Medical Treatment Cases (MTC)

h)

Occupational I11-health Cases (OIH)

i)

Total Recordable Incidents (TRI)

j)

First Aid Cases (FAC)

k)

Near Misses (NM)

l)

Asset Damages (AD)

m) Road Traffic Accidents (RTA)


3.

TRAINING & AWARNESS:


n)

4.

Tool Box Talks in Health & Safety Topics

o)

Method Statement (MS) Briefings

p)

Task Safety Analysis (TSA) Briefings

q)

Safety Representatives Meetings

r)

Meetings Due to an Accident (FAT or LTA)

s)

Internal Training in IMS Procedures

t)

External Training Courses

MONITOR & AUDIT:


u)

No of Internal Audits

v)

No of site HSE Inspections

w) Project Management Safety Tours

5.

x)

Operational Meetings (HSE aspects)

y)

Construction Managers HSE Visits

z)

AD Hoc Audits by CM, CLIENT & Others

PERFORMANCE:
aa) Total Recordable Incident Rate (TRIR)
bb) Lost Time Accident Frequency (LTAF)
cc) Days Lost due to LTA
dd) No of Warning Letters
ee) No of Staff Dismissal for Safety Violations
ff) Safety Violations Raised

[A]-SP-01-S01
[A]-SP-01-S01
gg) Safety Violations Closed
hh) Safety Violations Close out Ratio
EQUIPMENT LIST :
ii) No. of Cranes
jj) No. of Operation Equipment
kk) No. of Riggers
COMPETENT PERSON :
mm) No. of CPR Qualified / First Aiders
nn)

No. of Competent Person ( Scaffold & Welding & ..)

3rd PARTY TRAINING & CERTIFIED :


oo)

No. of 3rd party training

pp)

No. of person certified by 3rd party

Topics Discussed

Attendance

6.

ATTACHMENTS: -none-

Instructor(s):

PREPARED BY:

Site Safety Advisor


DATE:

SIGNED BY:
Project Manager

(Page 2 of 2)

[A]-SP-01-S02

Injury Summary for the Month of:


Contractor Name: Saudi Binladin Group

Case No.

Date of
Injury

Report Prepared by:

Name of Injured

Project Location:

Badge No.

Craft

Title: Site Safety Advisor

BI Number:
Nature of Injury,
Body parts affected

Brief Description of Accident

Signature:

Days
Lost

Tel No.
Project Manager

Light Duty

[A]-SP-01-S3

PRELIMINARY ACCIDENT REPORT


DETAILED REPORT TO BE SUBMITTED WITHIN 3 DAYS

ACCIDENT PERSON(S), MOTOR VEHICLE, EQUIPMENT OR PROPERTY


Motor Vehicle Accident
Date:
DESCRIBE ACCIDENT:

Personal Injury
Time:

Environmental Accident

Near Miss

Location:

IMMEDIATE CORRECTIVE ACTION(S) TAKEN TO PREVENT RECURRENCE:

COMPANY

INJURED NAME(S) AND BADGE#(S):

INJURY OR ILLNESS:

WITNESS STATEMENT(S):

MOTOR VEHICLE (ADDITIONAL INFORMATION)


NAME OF DRIVER

BADGE#

VEHICLE# &/OR PLATE#

CM
OTHER

ACCIDENT INVOLVED THE FOLLOWING


OTHER

SA VEHICLE
SA VEHICLE

CONTRACTOR VEHICLE
SUB-CONTRACTOR

FIXED OBJECT
PRIVATE

VEHICLE

VEHICLE

NO. OF PEOPLE IN
1ST VEHICLE?

HOW MANY
INJURED?

OF THOSE INJURED, HOW MANY


WERE WEARING SEAT BELTS?

NO. OF PEOPLE IN
2ND VEHICLE?

HOW MANY
INJURED?

OF THOSE INJURED, HOW MANY


WERE WEARING SEAT BELTS?

NATIONALITIES

WHO REPORTED TO THE ACCIDENT SCENE?


CM/CONTRACTOR SAFETY

SAFETY SECTION

GOVT. AFFAIRS

LOCAL POLICE

SECURITY

PREPARED BY:

CM REP.:

POSITION:

POSITION:

SIGNATURE:

SIGNATURE:

(Project Manager)
DATE:

DATE:

[A]-SP-01-S4

FATAL ACCIDENT REPORT


DETAILED REPORT TO BE SUBMITTED WITHIN 24 HOURS

INVOLVED PARTIES
Motor Vehicle
Date:

Personal
Time:

Equipment

Property

Location:

DESCRIBE ACCIDENT:

COMPANY

DECEASED NAME(S) AND BADGE#(S):

POLICE CASE NO. :

NO. OF PHOTOGRAPHS:

LIST OF PERSONS FAILED IN THEIR SAFETY


RESPONSIBILITIES:

LIST OF PERSONS CHARGED BY POLICE:

PROPOSED CHANGES TO SITE CONDITIONS TO PREVENT A RECURRANCE OF EVENTS THAT LEAD TO THE ACCIDENT:

WITNESS STATEMENT(S):

PREPARED BY:

CM REP.:

POSITION:

POSITION:

SIGNATURE:

SIGNATURE:

(Project Manager)
DATE:

DATE:

[A]-SP-01-S5

[A]-SP-01-S05

INTERNAL INCIDENT REPORT


LOCATION:

DATE:

TYPE:

TIME:

INVOLVED PERSON:

COMPANY:

BADGE NO./IQAMA NO:

Reference No.:

DESCRIPTION OF INCIDENT:

PREVENTIVE ACTION:

RECOMMENDATION:

ROOT CAUSES OF INCIDENT:


ACTION:

Reported by:

Checked and Approved by:

Position:

Position:

Date of Report:

Signature: (Project Manager)

Signature:

Date:

[A]-SP-01-S6

VOILATION REPORT
NON CONFORMANCE REPORT

(NCR)
INVOLVED PARTIES
Motor Vehicle

Personal

Equipment

Property

Others (specify):
Date:
Time:
Location:
DESCRIPTION OF NONCONFORMITIES (Attach Pictures If Applicable):

Issued to:

CORRECTIVE ACTION:

PREPARED BY:

CM REP.:

POSITION:

POSITION:

SIGNATURE:

SIGNATURE: (Project Manager)

DATE:

DATE:

[A]-SP-01-S07

Daily Inspection Check-List


Item
House Keeping:

Construction
Personal
Protective
Equipment
(PPE)
Construction
Hazard

Supported Pipe
Scaffolding

Description YES
Work zone
protection (barriers
& warning tapes &
signs)
Flagging
Lighting
Driving (seat belts
and roll over
protection)
Foot Protection
Hand Protection
Head Protection
Hearing Protection
Fall Protection (Full
Body Harness)
Fall Prevention
Struck-By
Prevention
Caught-In/Between
Prevention
Electrocutions
Prevention (By a
CP)
Tripping Hazard
Mud sells
Base Plates
Screw Jacks @ Base
Bracing
Shear pins
Full Working
Platforms
Wall/Building Ties

NO N/A

Comments (if NO)

[A]-SP-01-S07

Trenches

Item
Trenches
(Cont.)

Debris Netting
Lighting
Fall Protection
(Guardrails)
Two safe means of
Egress Available
(within 8 m of
workers in a trench)
Sloped for Stability
Cut or Stepped
Benches Grades

Description YES
Supported by a
shoring system
Supported by Trench
Box
Excavated material
60 cm back from the
edge of a trench
Engineers Shoring
Excavations
Report Available
Barricades &
warning signs
(lights) Available
around excavation
Excavated material
1.50 m back from
the edge of an
excavation
Traffic Control &
Protection around an
excavation

NO N/A

Comments (if NO)

[A]-SP-01-S07
Tower Cranes
Mobile Cranes
Heavy
Equipments &
Trucks
Demolition

Item
Demolition
(Cont.)

Respirators

Daily Inspection
Report by a CP is
available at site
Inspection Report by
a CP is available at
site
Inspection Report by
a CP is available at
site
Demolition
Approved PE Plans
& Programs (by a
CP)
Sufficient Shoring
(by a CP)
Dust Control
Proper PPE
Shut off of cap all
electric , gas, water,
steam, sewer &
other service lines
Guard wall openings
to a height of 1 m
Cover floor
openings
Description YES
Dangerous Areas
clearly marked (Not
Accessible) or CAZ
(Controlled Access
Zone)
Single-strap dust
masks

NO N/A

Comments (if NO)

[A]-SP-01-S07

Fire Protection
& Prevention

Approved filtering
face-pieces
Half-face respirators
Loose-fitting
Powered-AirPurifying
Respirators (PAPR)
A Self-Contained
Breathing Apparatus
All Purpose Fire
Extinguishers
(A,B,C) at PortCabins
All Purpose Mobile
Fire Extinguishers
(A,B,C) at Work
Areas
Trained Fire
Fighters Present at
site (SBG own
workers)
Location of Fire
Extinguishers
clearly marked
Availability of
warning signs
N/A: Not Applicable

Name of Safety Officer Conducting above Daily Inspection:


-------------------------------------------------------------------------------------------Signature of Site Safety Advisor:
--------------------------------------

Date of Inspection:
--------------------------------

Approved By
Project Manager
--------------------------

[A]-SP-01-S08

King AbdulAziz International Airport


Development Project
Daily Report (for safety situation)

No.

Item

Comment

Prepared by

Site Safety Advisor

[A]-SP-01-S09

SAUDI BINLADIN GROUP


PROJECT SITE SAFETY COLOR CODING
For the Month of

is

It is certified that I have inspected, maintained and repaired the following items, equipment, tools etc.
under my charge/responsibility and color coded these as
for the month of
.
The following are the items inspected:
Remarks

I. CRANE & LIFTING EQUIPMENT

OK

i. Lifting Tackles (Slings, Chains, Hoist, Come-A-Long, Shackles)


ii. Fire Extinguisher
iii. Others (Specify)

iv. Equipment Details:


Type:
Capacity:
Registration Valid up to:
v. Third Party Inspection:
Sticker No.:
vi. Operator Details:
Name:
SAG License No.
S.A. Certificate No.:
Signature:
Remarks:

Model No.:
Plate No.:

KS No.

Valid up to:
Comp.#
Valid up to:
Valid up to:
Date:

Not OK

[A]-SP-01-S09

SAUDI BINLADIN GROUP


PROJECT SITE SAFETY COLOR CODING
For the Month of

is

It is certified that I have inspected, maintained and repaired the following items, equipment, tools etc.
under my charge/responsibility and color coded these as
for the month of
.
The following are the items inspected:
Remarks

II. TRANSPORT AND HEAVY EQUIPMENT


i.

Lights:

Head Lights

Hazard Lights

Reverse Lights

Signal Lights

Brake Lights

ii.

Horn

iii.

Wind Screen

iv.

Wipers

v.

Seat Belt

vi.

Tires

vii.

Mirrors

viii.

Fire Extinguisher

ix.

General Condition

x.

Equipment Details:
Type:

Model No.:

Capacity:

Plate No.:

OK

KS No.

Registration Valid up to:


xi.

Operator Details:
Name:

Comp.#

SAG License No.

_Valid up to:

S.A. Certificate No.:

_Valid up to:

Driver/Operator Signature:

_Date:

Mechanic Signature:

Date:

Auto Electrician Signature:

_Date:

Tire man Signature:

_Date:

Remarks:

Not OK

[A]-SP-01-S09

SAUDI BINLADIN GROUP


PROJECT SITE SAFETY COLOR CODING
For the Month of

is

It is certified that I have inspected, maintained and repaired the following items, equipment, tools etc.
under my charge/responsibility and color coded these as
for the month of
.
The following are the items inspected:
III.
i.

Regulators

ii.

Gauges

iii.

Hoses

iv.

Torches

v.

Flashback Arrester

vi.

Trolley with Chain

vii.

Fire Extinguisher

viii.

Cables

ix.

Clamps

x.

GFCI

xi.

Grinder

xii.

Extension Cables

xiii.

Grounding System

xiv.

Fire Extinguisher

xv.

Others (specify):

xvi.

OK

Equipment Details:
Type:
Calibration No.:

xvii.

Remarks

GAS CUTTING APPARATUS

Model No.:
_Valid up to:

Welder Details:
Name:
Certificate No.:
Signature:

Remarks:

Comp.#
_Valid up to:
Date:

KS No.

Not OK

[A]-SP-01-S09
[A]-SP-01-S9

SAUDI BINLADIN GROUP


PROJECT SITE SAFETY COLOR CODING
For the Month of

is

It is certified that I have inspected, maintained and repaired the following items, equipment, tools etc.
under my charge/responsibility and color coded these as
for the month of
.
The following are the items inspected:
IV.
i.

Safety Guard

ii.

Power Cables

iii.

Clamps

iv.

Grounding System

v.

Extension Cables

vi.

Fire Extinguisher

vii.

Others (specify):

viii.

OK

Equipment Details:
Type:
Calibration No.:

ix.

Remarks

ELECTRICALLY OPERATED HAND/POWER TOOLS

Model No.:
_Valid up to:

User Details:
Name:
Certificate No.:
Signature:

Remarks:

Comp.#
Valid up to:
Date:

KS No.

Not OK

[A]-SP-01-S10
[A]-SP-01-S10

SAUDI BINLADIN GROUP


FIRE FIGHTING EQUIPMENT, EMERGENCY LIGHTING & INSECT KILLER INSPECTION LOG
MONTH OF:

NO.

LEGEND

Inspected by:

FACILITY/LOCATION

COLOR CODE:

NOS.

FH
CABINET

FIRE FIGHTING EQUIPMENT


FW
FW
FIRE
DRUMS
BUCKET
EXT.

SMOKE
DET.

Date Inspected:

EMER.
LIGHT

INSECT
KILLER

[A]-SP-01-S11

[A]-SP-01-S11

SAUDI BINLADIN GROUP

TRAVEL LOG
Date

Name

Vehicle
No.

Destination

Time
Out

Expected
Time of
Arrival

Remarks

[A]-SP-01-S12

SAUDI BINLADIN GROUP

VISITORS LOG
S.
No.

Name

Prepared By

--------------------------Safety Person

Company

Vehicle
No.

Purpose

Time
in

Time
Out

Signature

Remarks

Approved By

---------------------------Site Project Manager

[A]-SP-01-S13

STATISTICAL MONTHLY SAFETY REPORT


MONTH:

Prepared day:

CLIENT:
Construction Manager:
Contractor:

SAUDI BINLADIN GROUP

Contract Number:
NO OF MAN HOURS WORKED
NO OF INDUCTION TRAINING
NO OF INDUCTED EMPLOYEES
FIRST AID TREATMENT
LOST TIME INJURIES
DANGEROUS INCIDENTS
FATAL ACCIDENTS
NO OF TRAINING PROGRAMS
TASK SAFETY ANALYSIS

The information provided above is a true and accurate record.


Prepared By:
Signed:
Date:

[A]-SP-01-S14
[A]-SP-01-S14

STATISTICAL WEEKLY SAFETY REPORT


Weeks start:

end:

CLIENT:
Construction Manager:
Contractor:

SAUDI BINLADIN GROUP

Contract Number:
NO OF MAN HOURS WORKED
NO OF INDUCTION TRAINING
NO OF INDUCTED EMPLOYEES
FIRST AID TREATMENT
LOST TIME INJURIES
DANGEROUS INCIDENTS
FATAL ACCIDENTS
NO OF TRAINING PROGRAMS
TASK SAFETY ANALYSIS

The information provided above is a true and accurate record.


Prepared By:
Signed:
Date:

[A]-SP-01-S15
[A]-SP-01-S15
SAUDI BINLADIN GROUP

TOOL BOX MEETING MINUTES


TOPIC:
Place & Date of Meeting:

Time Started:

Time Finished:

Minutes of Meeting:

Safety Reminder:

(an attendance Sheet must be attached)

Prepared By:

SITE SAFETY ADVISOR

Approved By:

PROJECT MANAGER

[A]-SP-01-S16

ANNEX - E
PROJECT
ENVIRONMENTAL PLAN
.

E- 1

1.0

INTRODUCTION

1.1

It is the policy of Saudi Binladin Group to implement an environmental management


system complying with the applicable sections of ISO 14001:2004 and the Contract.

1.2

This plan is applicable to all of the activities in connection with the [King AbdulAziz
International Airport Development Project]. The scope of work is summarized below.
The Government of the Kingdom of Saudi Arabia, Ministry of Defense and
Aviation and Inspectorate General, General Authority of Civil Aviation are
expanding KAIA which shall take place first development Phase for 30
million passengers capacity, is scheduled to be completed by 2013.The
Project currently consists of the following:1.
Contract 421: Terminal Complex, Control Towers and Supporting
Facilities.
2.
Contract 422: Aprons, Taxiways, Roads, Tunnels, Bridges, Load Centers
and Infrastructure, Transportation Center and Supporting Facilities
This general procedure applies to all projects and offices.

1.3

Reference should be made to the Project Quality Plan, which is the top-level document,
for a complete understanding of the management system applied to the project.

2.0

DOCUMENT CONTROL

2.1

This Procedure will be a properly to this project. It is a controlled document means a document
that is registered and has its distribution controlled so that a holder has the correct issue of the
document at all times. All amendments, revision, will be subject to CM review and approval.

3.0

DEFINITIONS, TERMS AND ABBREVIATIONS

3.1

Project Manager The person who has the responsibility for all aspects of the project,
including health and safety.

3.2

Construction Manager

3.3

Section Engineers A person responsible for controlling the actions of others within a
defined work area or scope of the project.

4.0

REFERENCES

A person responsible for a portion of the Works.

ISO 9001:2008 Quality management systems Requirements


ISO 14001:2004 Environmental management systems Specification with guidance
for use
E- 2

5.0

ENVIRONMENTAL POLICY AND OBJECTIVES

5.1

SBGs environmental policy is reproduced below from the Corporate Quality Manual.
SBG is committed to conducting all of its activities with the proper regard for the
environment in which we work. This not only means the prevention of pollution,
or its minimisation where prevention is impossible, but also compliance with our
contracts and all laws and legislation relating to the environment wherever we
conduct our business.
All of our construction and related activities are assessed for any adverse impact
on the environment and measures taken to control them, documented in method
statements on a project and in the Operations Plan for our offices and other
facilities. In addition, each project or facility is set targets to measure
performance against our policy and senior management regularly reviews these
with the aim of continual improvement of the system.
SBG is also committed to enhancing the environment where possible by the
minimum use of resources through the reduction or elimination of waste, the
recycling of waste and the use of appropriate technology. Accordingly, all
personnel are required to implement the environmental management system in so
far as it applies to their work and to contribute actively to its improvement during
the course of their duties.

5.2

Our principal environmental objectives are

To prevent incidents at the workplace that result in pollution.


To minimise our use of natural resources.
To minimise the adverse impact on the environment due to our construction
activities.

6.0

PLANNING FOR THE ENVIRONMENT

6.1

The Project Manager will ensure that the Permanent Works are constructed such that
they have the minimal adverse impact on the environment. An environmental impact
assessment will be performed on all aspects of the work described in each method
statement. The resultant Environmental Impact Statement, developed to eliminate the
impact or reduce it to a tolerable level, is included in the method statement and is
approved prior to the work commencing.

6.2

It is also SBGs policy that other activities on the project such as the plant workshop
and the workers site also adopt environmentally responsible work practices in
accordance with our environmental management system. Where appropriate,
environmental impact control programmers for standard activities will be issued to
assure compliance with our requirements.

E- 3

6.3

All work and support activities shall aim to avoid or reduce to a practical minimum
common pollution such as dust, noise, waste and gases such as NO (nitrogen oxides),
SO2 (sulphur dioxide) and CO2 (carbon dioxide). To reduce air pollution to a minimum
there will be no unnecessary idling of vehicles.

6.4

All subcontractors appointed to construct the Permanent Works are assessed and
selected in accordance with general procedure on the basis not only of their capability to
meet both the quality requirements and the programme but also to meet acceptable
environmental standards and local legislation.

6.5

Each subcontractor is required to work in a way that is compatible with our system. A
subcontractors environmental plan, if prepared, is reviewed and approved by the
Project Manager and the Site HSE Advisor in advance of work starting. A subcontractor
that does not develop his own environmental plan will be required to work under ours.

7.0

MANAGEMENT RESPONSIBILITY

7.1

General

7.1.1

The Project Manager will issue from time to time an organisation chart showing the site
management team dedicated to executing the Works. As required by clause 4.4.1 of ISO
14001:2008 the project management team will be sufficient in numbers and suitably
experienced and competent to perform the work and successfully implement the
environmental management system.

7.1.2

The Project Manager has overall responsibility for all matters related to the environment
and he has assigned the management of this function to the Site HSE Advisor. This
responsibility includes compliance with the Contract, the Companys requirements,
environmental permits and approvals and all applicable laws and regulations. The HSE
section has HSE Officers to assist in the discharge of this responsibility.

7.1.3

The Project Manager shall assign responsibility for a particular task or function to a
member of his management team, and delegate the authority to enable him to perform
his duties; guidelines are given in the following sections. Notwithstanding such
assignment, overall responsibility remains with the Project Manager.

7.1.4

The Project Manager shall ensure that effective means of communication are put into
place to advice employees on environmental issues. These are to include the display of
notices, regular toolbox talks and the facility at all levels of project management to
discuss, provide and source information.

7.1.5

The Project Manager shall take the lead in developing and promoting initiatives in
environmental matters and shall use the management system to establish the required
standards. He shall monitor the performance of the workforce in achieving the targets
set for the project on a regular basis.
E- 4

7.1.6

Managers and supervisors are responsible for implementing the requirements of the
environmental system within their own area of the project. Queries on the application or
interpretation of the system are to be discussed with the Site HSE Advisor prior to any
action being taken.

7.2

Construction Manager

7.2.1

The Construction Manager is responsible for ensuring that all construction activities on
the project comply with the applicable environmental commitments and requirements
given in this plan, the Contract and local regulations. He shall also be the primary
contact with the Client and other concerned parties for the communication of site
environmental issues or status.

7.2.2

The Construction Manager serves as the primary Site Emergency Co-ordinator and is
responsible for:

The management of all day-to-day construction activities performed by the


Company and its subcontractor personnel.
Implementing and enforcing the environmental commitments.
Reviewing performance of subcontractor activities.
Setting up contracts for waste removal.
Ensuring that all necessary environmental impact assessments are carried out to
ensure compliance with the Contract, local legislation and the Companys policies
and that the Environmental Impact Statement is included in each method statement.

7.3

HSE Advisor

7.3.1

The HSE Advisor is to provide technical support services to the Construction Manager so that
construction of the project proceeds in compliance with the project's environmental
commitments.

7.3.2

The HSE Advisors duties include the following:

Ensuring that all engineering activities are planned and conducted in accordance
with the applicable environmental regulations and site-specific procedures.
Liaison with the Construction Manager and the Clients representative.
Management of the project environmental program on a day-to-day basis.
Distributing appropriate environmental commitment information to subcontractors
and direct-hire personnel, and monitoring their compliance.
Conducting regular field inspections of construction activities (including
subcontractors) for compliance with the Contract, existing permits and approvals,
and other applicable environmental regulations and commitments.
Conducting the Environmental Awareness Training programme for all new entrants
to the project.
Serving as the Interim Emergency Co-ordinator in the absence of the Construction
Manager.
E- 5

Performing hazardous waste identification and classification for the type and hazard
class for all wastes generated during project activities.
Maintaining records related to the handling, storage and disposal of hazardous waste
generated on the project in accordance with all applicable regulations.
Identifying locations for the waste containers.
Providing input for the selection of a waste management contractor.
Dealing with housekeeping issues through the Site Supervisor.

7.4

HSE Officer

7.4.1

The HSE Officer is responsible for providing primary and continuing environmental
support to the HSE Advisor and the Construction Manager with respect to the
development, implementation and enhancement to the project environmental
compliance programme and for project environmental compliance issues.

7.4.2

The HSE Officers duties include the following:

Assisting the Site HSE Advisor to develop, update and maintain the projects
environmental compliance plans and procedures.
Ensuring that the project management team, as well as other project personnel, have
been informed of the potential environmental impact of planned activities and of the
mitigation measures and actions that should be taken to maintain compliance with
the applicable permits, laws, and regulations.
Working in conjunction with the Site HSE Advisor to develop and implement the
project environmental compliance programme comprising all the necessary plans
and procedures, and for developing, implementing and conducting Environmental
Awareness Training Programmes.
Assisting the Site HSE Advisor in identifying and classifying all hazardous or
unknown wastes generated during construction activities.
Assisting the Site HSE Advisor and Construction Manager as requested in
identifying and resolving site environmental compliance issues.

7.5

Section Supervisor

7.5.1

Section Supervisors have responsibility for the following:

Supervising the Company workforce in a manner consistent with the Companys


environmental policy.
Establishing cleanup crews.
Dealing with project housekeeping issues.

7.6

Subcontractor Management

7.6.1

The subcontractors project manager shall:

E- 6

Enforce the requirement in the subcontract with the Company that makes
subcontractors responsible for complying with all applicable environmental
regulations and Company procedures related to their scope of works (see below).

Submit information to the HSE Advisor on their activities that involve the use or
generation of hazardous substances and wastes that can potentially violate the
provisions of existing permits, or that have the potential to affect the environment
detrimentally.

Verify that he has provided all necessary submittals as required for materials that he
has brought to site.

7.6.2

The subcontractor shall comply fully with all applicable environmental laws, rules, and
regulations. The subcontractor is also responsible for becoming familiar with all project
environmental plans and procedures, in particular those contained in this plan.

7.6.3

The subcontractor shall also acquire, handle, transport and store regulated substances
(e.g. hazardous wastes) that have environmental aspects in a safe and appropriate
manner as defined by the applicable laws and regulations and the project management
system.

7.7

Subcontractor Workforce
It is the responsibility of the subcontractors workforce to ensure that they read,
understand and adhere to the environmental requirements of their subcontract and
perform all their work in an environmentally responsible manner. They shall also:

Comply with all the applicable national and local laws, safety regulations and
standards.

Attend the Companys environmental awareness training program.

Maintain all records of environmental compliance activities including hazardous


waste disposal.

E- 7

ANNEX F
Summary of Staff
Responsibilities

F-1

1.

2.

Appendix F Health and Safety Responsibilities of Managers


To ensure the inclusion of health and safety considerations when planning work or
work schedules.
Promptly responding to all reports received from subordinates and other persons of
non-compliance, unsafe conditions and activities, accidents and near misses.

3.

Taking prompt corrective action on observed non-compliance and substandard


industrial practice with respect to occupational health and safety.

4.

Taking prompt corrective action and advising the Site HSE Advisor accordingly
with regard to potential health and safety hazards.

5.

Setting a personal example and encouraging health and safety awareness among
individual subordinates, the managed workforce and subcontractor workforce.

6.

Actively contributing to the investigation and reporting of all accidents, incidents


and near misses.

7.

Ensuring that all activities, within his area of management responsibility, whether
executed by Company personnel or subcontractor personnel, are carried out with
full regard to Company regulations and health and safety policies.

8.

Confirming that all persons, whether employed by the Company or its


subcontractors, engaged in activities or on facilities for which he has a
management responsibility are competent to execute safely the required work, and
that the applicable work procedures are communicated, understood and in place.

9.

Ensuring within his area of management responsibility and through his supervisory
line that his workforce and other applicable persons are advised of any health and
safety hazards and that the necessary controls and contingency arrangements
associated with the work activities are in place.

10.

Ensuring through his supervisory line that his workforce and, where applicable, his
subcontractor workforce, make correct use of personal protective equipment and
that such equipment is in good condition, is suitably rated with consideration to the
hazards involved and is, as closely as possible, suitable to the user.

11.

Ensuring through his supervisory line that health, safety and emergency
equipment, whether portable or installed, is maintained in a proper operational
condition and that such equipment is correctly used.

12.

Ensuring through his supervisory line that all facilities, tools, equipment, plant and
vehicles in use within his area of management responsibility, whether
owned/operated by the Company or its subcontractors, are maintained in a safe
operational condition and are used correctly.

13.

Maintaining, and participating in, the schedule of meetings, emergency exercises,


inspections and audits that are programmed for his area of management
responsibility.

14.

Participating in the follow-up and close-out of corrective actions that arise from
operational activities, meetings, accidents, incidents, near misses, emergency
exercises, inspections or audits that take place within his area of management
responsibility.
F-2

Appendix F Health and Safety Responsibilities of Engineers and Supervisors


1.
To ensure the inclusion of health and safety considerations when issuing day to
day work instructions and monitoring their execution within Company activities.
2.

Promptly responding to all reports received from subordinates or other persons of


non-compliance, unsafe conditions, unsafe activities, accidents and near misses.

3.

Taking prompt corrective action on observed non-compliance and substandard


industrial practice with respect to occupational health and safety.

4.

Taking prompt corrective action and notifying line management accordingly with
regard to accidents, incidents and near misses.

5.

Taking prompt corrective action and notifying line management accordingly with
regard to potential health and safety hazards.

6.

Setting a personal example and encouraging health and safety awareness amongst
individual subordinates and the supervised workforce.

7.

Adequately contributing to the investigation and reporting of all accidents,


incidents and near misses.

8.

Ensuring that all activities, within his area of supervisory responsibility, are carried
out according to Company regulations and health and safety policies.

9.

Confirming that all persons, whether or not employed by the Company, engaged in
activities or on facilities for which he has a supervisory responsibility, are
competent to execute the work safely, and that the applicable work procedures are
communicated, understood and in place.

10.

Ensuring within his area of supervisory responsibility that his workforce and other
applicable persons are advised of any health and safety hazards and that the
necessary hazard controls and contingency arrangements associated with the work
activities are in place.

11.

Ensuring that his workforce and, where applicable, subcontractors workforce,


make correct use of personal protective equipment and that such equipment is
suitably rated with consideration to the hazards involved, and is, as closely as
possible, suitable for the user.

12.

Ensuring that safety and emergency equipment, whether portable or installed, is


maintained in a proper operational condition, and that such equipment is correctly
used.

13.

Ensuring that all facilities, tools, equipment, plant and vehicles in use within his
area of supervisory responsibility, whether owned/operated by the Company or a
third party, are maintained in a safe operational condition and are used correctly.

14.

Maintaining and participating in the schedule of toolbox talks, meetings,


emergency exercises, inspections and audits that are programmed for his area of
supervisory responsibility.

15.

Participating in the follow-up and closeout of corrective actions that arise from
operational activities, toolbox talks, meetings, accidents, incidents, near misses,
emergency exercises, inspections and audits and that take place in his area of
supervisory responsibility.
F-3

Appendix F Health and Safety Responsibilities of All Employees


1.

To participate in any Company training for which he is nominated by his


supervisor.

2.

To participate in any emergency exercises that take place at his work location.

3.

To participating in toolbox talks that are scheduled for his workgroup.

4.

To become sufficiently familiar with the management system and operating


procedures that are applicable to himself and his job.

5.

To follow all work instructions relating to occupational health and safety that are
issued by his Supervisor and Management.

6.

To use correctly the personal protective clothing (PPE) and equipment provided by
the Company for his protection and welfare.

7.

To comply with all work, operational, security, behavioural and social procedures
and regulations issued by the Company.

8.

To comply with all posted signs, including those related to safety and road and site
traffic, whether temporary or permanent.

9.

To comply with all audible warnings and alarms.

10.

To inspect daily and prior to use all PPE, tools, equipment, vehicles and similar
resources that are used by him in the execution of his job, and the reporting to his
Supervisor any inadequacies, defects or damage noted.

11.

To report promptly any accidents, incidents and near misses, however small, to his
Supervisor.

12.

To communicate with his colleagues, and report to his Supervisor, any condition or
situation that he feels may be unsafe, unhealthy or damaging to the environment.

F-4

ANNEX G
Scaffolding Procedures

G-1

1.0

PROCEDURE

1.1

Materials

1.1.1

General

1.1.1.1

All scaffolding material will be of sound construction and adequate strength and will
be manufactured, constructed and maintained to international standards (OSHA).

1.1.2

Tubes, Units and Frames

1.1.2.1

Tubes, units, frames, etc. shall be straight to the eye and shall be free of cracks,
splits, excessive corrosion or other defects. The ends shall be cut square with the
axis of the tube.

1.1.2.2

Any tube, unit or frame requiring a high degree of maintenance such as wire brushing or
scraping shall be replaced.

1.1.2.3

No tube, unit or frame will be painted. The only acceptable coating will be galvanising
and zinc primer.

1.1.2.4

No black steel tube shall be used.

1.1.3

Scaffolding Boards

1.1.3.1

Scaffold boards shall be one of three thicknesses, i.e. 38mm, 50mm and 63mm.
All boards will be 225mm wide.

1.1.3.2

Boards of similar thickness will be used to deck out individual scaffolds.

1.1.3.3

Scaffolding boards are not acceptable if they have a knot larger than 50mm diameter.

1.1.3.4

Edge knots shall not exceed 50% of the thickness of the board.

1.1.3.5

Warped boards shall not be used.

1.1.3.6

Scaffold boards with splits are not acceptable.

1.1.3.7

There shall be no cut outs, burns, oil stains or projecting nails.

1.1.3.8

Boards shall not be painted or treated in any other way that may conceal defects.
They may be fireproofed using an approved flame retardant material.

1.1.3.9

Boards that are broken or excessively worn shall not be used.

1.1.3.10 Boards shall be square cut and bound with a hoop iron.

G-2

1.1.3.11 As a minimum the hoop iron shall be stamped with the following information:
The international standard with which board complies.
The maximum span in metres over which the board has to be supported.
1.1.4

Couplers

1.1.4.1

Couplers will be inspected weekly by a Competent Scaffold Inspector.

1.1.4.2

Any coupler found to be broken or damaged or found to have rusty or damaged


threads will be discarded.

1.1.4.3

Couplers will be sorted by type. They will be kept clean and lightly oiled to prevent rust.

1.1.5

Storage of Materials

1.1.5.1

All scaffolding material will be properly and neatly stored.


Tubes will be sorted and stored by length.
Couplers will be sorted and stored by type.
Boards will be stored no more than 20 high.

1.1.5.2

Where materials are being stored at the site of erection for immediate use, they will
be stored in a neat manner that does not present a tripping hazard or block access
routes.

1.2

General Rules for Scaffolding

1.2.1

Foundations

1.2.1.1

The foundations shall be adequate to carry the load and, as far as possible, level.

1.2.1.2

A base plate shall be placed under every standard irrespective of the foundation
surface.
A sole plate shall be placed under every base plate where the foundation is other
than concrete or metal plate decking. This rule shall apply to open deck grating.

1.2.1.3
1.2.1.4

Sole plates, where required, shall be placed underneath the base plates on two
adjacent standards, normally at right angles to the face of the scaffold. The sole
plate will extent 600mm either side of two adjacent standards which it supports.

1.2.1.5

Under no circumstances will any excavation be performed within 3m of the foundations


of a scaffold to prevent undermining.

1.2.2

Standards (Tube & Coupler Scaffolds)

1.2.2.1

Standards shall be plumbed vertical.


G-3

1.2.2.2

The spacing between standards is determined by the intended use of the scaffold.
Under no circumstances will the bay length exceed those distances given in Table 1.1.

1.2.2.3

Joints in standards can be made with sleeve couplers or spigots (joint pins).
Joints must be staggered, i.e. they must not occur at the same level in adjacent
standards.

1.2.3

Ledgers (Tube & Coupler Scaffolds)

1.2.3.1

Ledgers must be plumbed level and fixed to the inside of standards using right
angle, load-bearing couplers.

1.2.3.2

The vertical distance (lift height) between ledgers must not exceed 2m.

1.2.3.3

Joints in ledgers will be made with sleeve couplers; spigots (joint pins) are not
acceptable. All joints must be staggered.
Table 1.1 General Requirements for Tube and Coupler Scaffolds

Duty

Use of platform

Inspection, painting,
Inspection
stone cleaning, light
and very
cleaning, cleaning
light duty
and access.
Plastering, painting,
Light
stone cleaning,
duty
glazing and pointing
General building
work including
General
brickwork, window
purpose
and mullion fixing,
rendering, plastering
Heavy
duty
Masonr
y
or
special
duty

Block work,
brickwork, heavy
cladding
Masonry work,
concrete block work,
and very heavy
cladding

Commonly
used widths
using
225mm
boards

Max.
bay
length
m

Distributed
loads on
platforms
kN/m2

Maximum
number of
platforms

0.75

1 working
platform

3 boards

2.5

1.50

2 working
platforms

4 boards

2.4

2.00

2 working
platforms +
1 at very
light duty

5 boards or
4 boards +
1 inside

2.1

2.50

2 working
platforms +
1 at very
light duty

5 boards or
5 boards +
1 inside or
4 boards +
1 inside

2.0

3.00

1 working
platform +
1 at very
light duty

6 to 8
boards

1.8

G-4

1.2.4

Transoms

1.2.4.1

Transoms should, whenever possible, be secured to standards using right angle


couplers. They may however, be laid across ledgers and secured with putlog clips
provided that they are not more than 300mm from each pair of standards.

1.2.5

Ties

1.2.5.1

Ties must be fixed at every second lift and every second standard.

1.2.5.2

Where a scaffold has been sheeted out with tarpaulins, consideration will be given to
additional wind loading and the insertion of additional ties.

1.2.5.3

All ties will be positive two way ties i.e. they will prevent movement of the scaffold either
into or away from the building. Positive two-way ties are:
Box tie
Screw or anchor ties

Through tie
Ties secured with couplers

1.2.5.4

All ties must be secured as near to the node point as is possible. No other coupler will
be acceptable.

1.2.5.5

The anchorage point to which a tie is secured must be of sufficient strength to


withstand the load imposed upon it. Under no circumstances will guardrails be
used as an anchorage point for ties.

1.2.5.6

As a general rule, ties must always be inserted. Where this is not possible, one of
the following actions may be taken.
On small scaffolds not extending above three lifts, adequate stability of the
scaffold can be achieved by rakers. The raker will be secured with right angle
couplers to the ledger at the second lift. The load in the raker will be distributed
through a base plate or if required a sole plate. The foot of the raker will be
tied back to the main scaffold. Rakers will be inserted at the same standard
spacing as ties.
Where a scaffold extends above three lifts, a well-braced buttress shall be erected
along the total length of the structure. The buttress shall be erected to a height
no lower than the third lift from the top of the scaffold. The scaffold will
then be raked back from the second top lift to the buttress, using right-angled
couplers.

1.2.5.7

No raker shall extend more than 3m without being tied back at its mid point.

1.2.6

Braces

1.2.6.1

All scaffolds will be braced in both directions. Braces, whether faade or ledger to
ledger, will extend to the full height of the structure.
G-5

1.2.6.2

Faade braces will be repeated at a maximum distance of every 10m.

1.2.6.3

Ledger to ledger bracing will be repeated at every alternate set of standards.

1.2.6.4

Joints in faade braces will be made with sleeve couplers; spigots are not
acceptable.

1.2.6.5

Where braces are fixed to transoms, the transom itself must be fixed with right
angle couplers.

1.2.7

Working Platform

1.2.7.1

Working platforms will normally be five boards wide but may be reduced to three
boards where the scaffold has been erected for inspection purposes only.

1.2.7.2

All working platforms will be close boarded with boards butted end to end.

1.2.7.3

Each individual board will be securely lashed.

1.2.7.4

Guardrails will be fixed to the inside of the standards on all working platforms to
a height of between 1.10m (minimum) and 1.50m (maximum). The space between the
top of the toe board and the underside of the guardrail will not exceed 690mm.

1.2.7.5

An intermediate guardrail will be fixed to the inside of standards in every instance.

1.2.7.6

Toe boards including stop end boards will be fitted to all working platforms.
The minimum height will be 150mm.

1.2.7.7

If materials are to be stacked above the height of the toe board, a suitable barrier
(brick guards) will be erected.

1.2.7.8

Ladder access openings will be not more than 500mm wide (2 boards) and will be
as short as possible in the other direction.

1.2.7.9

The maximum span of any board forming the working platform will be 1.20m.

1.2.7.10 The minimum overhang of any board will be not less than 50mm and the maximum
overhang will not exceed 150mm.
1.2.7.11 No more than 2 boards width will be supported on needle transoms unless the
transoms are fixed with right angle coupler and picked up.
1.2.7.12 Sign boards in appropriate languages shall be permanently displayed on each working
platform. These shall state the maximum allowable weight of tools and materials and the
maximum number of men per bay appropriate to the type of scaffold.

G-6

1.2.8

Ladder Access Platforms

1.2.8.1

The vertical height between ladder access platforms will not exceed 9m.

1.2.8.2

Ladder access platforms will be close boarded and will have guardrails and toe
boards secured as described in section 1.2.7 above.

1.2.9

Ladders

1.2.9.1

Ladders will project beyond working platforms or ladder access platforms by a


minimum distance of 1.05m (five rungs).

1.2.9.2

Ladders will be based on a sound footing. They will be lashed or secured by a


proprietary clamp at both the foot and near the top.

1.2.9.3 The angle at which the ladder is set will (with the exception of scaffold towers)
be 75 or 300mm out for every 1.20m of vertical length.
1.2.9.4

Long ladders will be supported and lashed at their mid point to remove any bounce.

1.2.9.5

Ladders may be of aluminium. Only properly constructed and manufactured ladders shall
be used. Home made ladders are strictly forbidden.

1.2.9.6

All ladders will be of good repair and sound construction. They will be checked for
damage, faults and wear & tear by the Competent Scaffold Inspector before use.

1.2.9.7

Ladders will not be painted or treated in any other way likely to conceal defects.

1.2.9.8

Stiles will not be excessively warped.

1.2.9.9

Rungs will not be excessively worn, broken or missing.

1.2.9.10 Metal tie rods will be in place.


1.2.9.11 Ladders may be on the outside of a scaffold for the first two lifts above ground
level. In every other instance, the ladder run will be internal to the scaffold.
1.2.10

Protective Fans

1.2.10.1 Where it is likely that material may fall from a scaffold and where people are
working or passing in close proximity to the structure, a protective fan will be
erected.
1.2.10.2 Protective fans will not be used to store scaffolding or other materials.

G-7

1.2.10.3 The protective fan shall not be more than 5m above ground level, shall be at
least 2m wide and at an angle not exceeding 20 to the horizontal.
1.2.11

Check Fittings

1.2.11.1 Without exception, check fittings will be used whenever a scaffold tube is punched up,
picked up, rakered or hanging.
1.2.12

Scaffold Loading

1.2.12.1 It is the responsibility of the Competent Person, Scaffold Systems to ensure that the
scaffold construction and strength are suitable for the purpose to which the structure will
be put.
1.2.12.2 Design calculations shall be submitted to the Engineer for any scaffolding other than a
common access scaffold for approval. The calculations are to show both dead and live
loading.
1.2.13

Traffic Movements

1.2.13.1 Where a scaffold is erected in an area where it is likely to be struck by a vehicle, the
base of the scaffold shall be properly protected with hard barriers. The barrier shall be
illuminated with flashing warning lights during the hours of darkness.
1.3

Erection of Scaffolding

1.3.1

Scaffolds shall be erected by capable workmen (Competent Persons) who have


undergone a course of training as scaffold erectors.

1.3.2

Scaffoders shall operate under the control of a Competent Person, who is trained as a
scaffold inspector.

1.3.3

Whenever possible, the scaffolders erecting the scaffold will work from the minimum of
a three board run. It is not acceptable for scaffolders to be perched on tubes, unless
a fall arrest device is provided and secured to a suitable anchorage point at all
times.

1.3.4

Ladders will be properly lashed throughout the vertical height of a scaffold as it


progresses. Scaffolders erecting the scaffold will use the ladders to gain access to
the working level.

1.3.5

Tubes or boards being used in the construction of the scaffold will be stored flat in a
neat and tidy manner. They will not be stacked vertically against the scaffold.

1.3.6

Loose tubes or boards will not be left on a scaffold after its completion.

G-8

1.3.7

In order to assist the section engineer in planning a safe scaffold system the HSE is to
be notified of the intended work at least seven days before the scaffold is due to be
erected.

1.3.8

Where men are erecting a slung or cantilevered section or crawling around on a


pipe bridge or other structural steelwork they will, in all instances where there is a
possibility of falling more than 2m, wear a full body harness suitably anchored.

1.3.9

Where men are working near an area of water where the danger of drowning
exists, they will in all instances wear a full body harness.

1.3.10

Where a scaffold is left in an incomplete state, the bottom ladder will be removed and a
notice will be secured to the lower lift stating Danger Incomplete Scaffold Keep
Off. This notice will be in the appropriate languages.

1.3.11

Where one section of a working platform is incomplete, access may be gained to


the completed section provided that a stop end, preventing entry, is placed over the
working platform at guardrail height. A notice stating Danger Incomplete Scaffold
Keep Off will be secured to the stop end. This notice will be in the appropriate
languages.

1.3.12

Handballing will be the normal method of erecting a scaffold. Where, however, a


scaffold consists of a considerable number of lifts a gin wheel may be used, provided the
following requirements are met:
The gin wheel has a valid certificate not more than six months old issued by a
Competent Scaffold Inspector.
The cantilevered tube to which the gin wheel is secured does not project more than
760mm beyond the scaffold, unless it is adequately supported.
The cantilevered tube is secured to the inside and outside standard using right angle
couplers. Both standards to be diagonally braced.
The fibre rope, which shall have a minimum diameter of 18mm, will be checked
daily by the Competent Scaffold Inspector and discarded if unfit for use.
The maximum load to be lifted by a gin wheel will not exceed 50kg.

1.4

Inspection

1.4.1

All scaffolds will be inspected by a Competent Scaffold Inspector prior to use and
at seven-day periods thereafter.

1.4.2

The Competent Scaffold Inspector will complete the relevant sections of the scaffold
tag if he finds the scaffold to be acceptable for use.

1.4.3

Where the Competent Scaffold Inspector finds the scaffold to be unsafe, he will
remove the scaffold tag and place a notice on the bottom lift stating Danger
G-9

Incomplete Scaffold Keep Off. This notice will be in the appropriate languages.
Where access is by ladder, he will also ensure that immediate action is taken to
remove the lower ladder.
1.4.4

These actions will be in force until such times as the Competent Scaffold Inspector
declares the scaffold safe for use.

1.5

Scaffold Users

1.5.1

Scaffolds will be used for the purpose for which they have been erected. Under no
circumstances will they be overloaded.

1.5.2

Scaffold users will under no circumstances interfere with, modify or remove any part of a
scaffold (this includes scaffold boards). Interference with a scaffold will result in
disciplinary action.

1.5.3

Only a Competent Scaffold Inspector is authorised to modify a scaffold.

1.5.4

If for any reason a user considers a scaffold to be unsafe, he will immediately


contact his supervisor. The supervisor will immediately remove the scaffold tag and place
barrier tape through the lower rungs of the first access ladder.

G-10

ANNEX H

REQUIREMENTS FOR
SAFE WORKING IN A
CONFINED SPACE

H- 1

1.0

PURPOSE

1.1

To define the minimum requirements and procedures to ensure the safety and health of
personnel who work in or in connection with confined spaces.

2.0

SCOPE

2.1

This technical procedure applies to all personnel entering, working in and


exiting a Confined Space on all projects.

3.0

DOCUMENT CONTROL

3.1

This Procedure will be a properly to this project. It is a controlled document means a document
that is registered and has its distribution controlled so that a holder has the correct issue of the
document at all times. All amendments, revision, will be subject to CM review and approval.

4.0

DEFINITIONS, TERMS AND ABBREVIATIONS

4.1

Confined Space An area where there is a possibility of exposure to toxic or


flammable gases and/or a deficiency or excess of oxygen and which requires a
permit to work.

4.2

Entry: The action by which a person passes through an opening into a Confined Space.

4.3

Competent Person, Confined Spaces


A person assessed for his knowledge and
experience of working in confined spaces and entered on the Register of
Competent Persons.

4.4

Competent Person, Gas Testing A person assessed for his knowledge and experience
of working with gas detection apparatus (as the 3rd Party Certification).

4.5

Standby Man
An individual who is stationed immediately outside the Confined Space,
whose sole duty is to monitor the authorised entrants in the Confined Space. He is also
required to assist in the execution of the emergency procedures.

4.6

Hazardous Atmosphere An atmosphere that may expose employees to the risk of


death, incapacitation, impairment of ability to self-rescue (i.e. to leave unaided), injury, or
acute illness.

5.0

RESPONSIBILITY

5.1

The Project Manager has overall responsibility for the implementation of this technical
procedure.

5.2

The Competent Person, Confined Spaces is responsible for the following:


H- 2

Initially inspecting the area to ensure all hazards or potential hazards have been
identified and controlled.
Testing the Confined Space for atmospheric hazards and documenting the test results
on the work permit.
Verifying that the Confined Space has been isolated by locking and tagging out
all energy sources leading into or out of the Confined Space.
Issuing the work permit.
Ensuring that all employees and subcontractors are familiar with this procedure.
Arranging training for personnel who work in or supervise a Confined Space.
Periodically monitoring work conditions in the Confined Space.
5.3

The Section Supervisor is responsible for the following: Ensuring


that the workforce is working to this procedure.
Checking that the workforce is carrying out work method safely.
Ensuring that all tests have been properly conducted and that procedures and
equipment are in place before endorsing the work permit and allowing entry. Planning
the work, as far as practicable, to include contingency plans and emergency
arrangements.

6.0

REFERENCES
ISO 9001:2008 Quality management systems - Requirements
ISO 14001:1996 Environmental management systems Specification with
guidance for use
OHSAS 18001:2007 Occupational health and safety management systems Specification

7.0

PROCEDURE

7.1

General

7.1.1

All work in a Confined Space shall be controlled by a Permit to Work Confined


Space Entry.

7.1.2

Prior to work commencing in the Confined Space, tests shall be carried out to
determine whether there is a hazardous atmosphere present that could endanger the
workforce carrying out the task.

7.1.3

The Competent Person, Gas Testing shall determine the composition of the atmosphere
and record the results on the form Vapour and Exposure Test Report. All deficiencies
must be corrected before entries can be authorised.

H- 3

7.1.4

No personnel shall enter a Confined Space without being made aware of the contents of
the work permit and the conditions attached to it. A copy of the work permit must be
positioned adjacent to the entry to the Confined Space.

7.1.5

All hinged or swinging access hatches, doors and covers shall be substantially blocked,
tied or otherwise affixed in the open position until the Confined Space is secured.

7.1.6

Guardrails, barricades or similar protection shall be provided around the Confined


Space access points to prevent persons from falling into openings or making
unauthorised entries.

7.1.7

Substances that are flammable and/or toxic shall not be used in a Confined Space
without appropriate personal protective equipment and respiratory protection and the
approval of the Site HSE Advisor.

7.1.8

Hoses supplying hazardous gases to areas within a Confined Space shall be equipped
with excess flow check valve devices and shall not contain patches or repairs
within the Confined Space or in the vicinity.

7.1.9

Dust generated within a Confined Space shall be controlled. Open flame work shall
be prohibited whenever a flammable atmosphere is present within a confined space.

7.1.10

The following equipment shall be available for use in a Confined Space. Employees will also
be trained in their proper use. The equipment includes but is not limited to:
Testing and monitoring equipment. Ventilating equipment.
Communication equipment (i.e. lifelines).
Personal protective equipment.

7.4.4

The Section Supervisor shall terminate and cancel the entry and return the permit to
work when one of the following conditions applies:
The work operations are complete.
When a condition that is not allowed under the work permit exists. A change in the use
or configuration of a Confined Space.

7.5

Planning the Entry

7.5.1

The Section Supervisor will establish the need for a Confined Space work permit based
on the job and conditions in the work area.

7.5.2

Ventilating the Space

7.5.2.1

The atmosphere of the Confined Space shall be purged of all toxins or combustibles.
Ventilation shall be provided in order to ensure that the atmosphere is safe. The exhaust
of the ventilating equipment shall be designed to protect workers from contamination of
the atmosphere. If the Confined Space is being ventilated prior to atmospheric
H- 4

sampling, a rule of thumb is to ventilate long enough to have seven complete volume
changes in the space.
7.5.2.2

When setting up the ventilation system, consideration should be given to the location of
fans order to provide the best airflow through the Confined Space.
Note: The air exhaust port shall be placed far enough away from the entrance in
order to prevent re-circulation of this air back into the Confined Space.

8.0

RECORDS

8.1

The forms Confined Space Entry Log shall be attached to the Permit to Work
Confined Space Entry to which they refer.

8.2

The work permit shall be the prime record and the document set shall be managed.

8.3

Documents generated by referenced procedures shall be managed in accordance


with the originating procedure.

H- 5

ANNEX K

REQUIREMENTS FOR
HOT WEATHER AND
HEAT STRESS

K-1

1.0

PURPOSE
To provide a safe working surrounding by establishing a procedure that addresses
temperature extremes and reduces exposure to the effects of heat related hazards.
To provide adequate access to drinking water and regimen for working in high heat
areas
To monitor workers and ensure they are consuming adequate amounts of water.

2.0

SCOPE

2.1

To inform all supervisors of their responsibilities to the workforce and regulate


exposure to heat situations.

3.0

REFERENCES
HSE Requirements as stipulated in Contract Documents.
All applicable Saudi Arabian Regulatory Authority requirements and regulations

4.0

DEFINITIONS, TERMS AND ABBREVIATIONS


HEAT STRESS is usually the result of work being performed at elevated
temperatures. Contributory factors may also include a decrease of natural body
ventilation by protective clothing e.g. chemical & impervious suits.
NOTE: If the bodys physiological processes fail to maintain a normal body
temperature because of excessive heat, a number of physical reactions can occur
ranging from mild (such as fatigue, irritability, anxiety, and decreased
concentration, dexterity , or movement) to fatal. Because heat stress is one of the
most common and potentially serious illnesses that construction workers
encounters, in areas where high temperatures are normally encountered, regular
monitoring and other preventative measures are vital.

5.0

RESPONSIBILITIES
It is the responsibility of each Manager. Department Head, Engineer, foreman,
charge-hand to ensure that their workers are informed of the physical hazards to
Heat Exposure.
Supervision shall actively monitor the work force for signs and symptoms of heat
stress.
The Site HSE Advisor / Doctor shall ensure that the requirements of this procedure
are communicated throughout the organization through education (toolbox talks)
and will liase with medical department in identifying and trends and concerns with
regard to cases of heat stress.
Medical personnel shall ensure the sufficient quantities of electrolyte and other
forms of treatment are available in the medical center for the handing of any
patients suffering from any heat related illness.
K-2

Project Management and supervision are responsible for ensuring that personnel
under their control are educated in recognizing and understanding the symptoms
and treatment for the various forms of heat stress.
6.0

PROCEDURE
There are several health hazards associated with excessive exposure to heat and sun.
Recognize the effects of the following heat exposures:
Heat Cramps
This is a result of the loss of salt in the working muscles, usually a part of heat
exhaustion.
Acclimatize yourself during hot weather and consume lots of water, juice, or a sport
drink before work. Other drinks like Coke, Tea and Coffee contain caffeine, which
if consumed in excess amounts, also accelerates fluid loss in the urine.
Heat Exhaustion
This is caused by the excessive loss of body fluids from sweating. The individual
sweat which causes dehydration and the symptoms are dizziness, become nauseated
or very tiered. Rest and plenty of water usually produce quick recovery to this
common heat ailment.
Heat Stroke
This is the most serious hot weather health problem. The individuals tolerance to
heat stops. The individual has hot, dry skin with a high core temperature, chills, and
mental confusion. If the individual is not cooled off quickly, the result can be brain
damage or even death. The individual with a medical history of heat stroke is more
likely to have a recurrence under the same conditions.
Ensure workers are acclimatized to the heat.
Provide shelters where workers can find shade and protection from direct sunrays.
Provide periodic water breaks where workers can drink before, during and after
work.
Establish a work regimen where workers can be rotated, allowing short rest periods
to prevent harmful effects due to Heat.
Categorize the work load as the type of work being performed.
Light supervising,
Medium regular work
Heavy digging, concrete work welding and grinding
Provide water access in strategic points that are accessible to the worker.
Establish access points to water for workers that are working at heights.
Supervisors must monitor their work force by looking for signs of dehydration,
especially in older persons or workers that have health problems.
If possible, regulate work hours where exposure to high heat will not be during
peak heat hours.

K-3

Preventative measures:
Employees shall have access to cool potable water at their place of work Water
coolers shall be provided for all crews.
Shaded areas shall be provided for rest periods and instructions given to workers
that resting adjacent to, or under plant and equipment is strictly prohibited.
First Aid equipment provided on site shall include treatment for dehydration e.g.
electrolytes.
General
All of the above conditions must be reported to the medical center and treated as
soon as possible. Medical staff or first aiders will send regular communiqus on the
subject of heat stress and inform management of any concerns. The contents of this
procedure will be communicated and emphasized to site supervision during training
sessions and at the contractors regular HSE meetings.

K-4

ANNEX L
REQUIREMENTS FOR
MEDICAL FACILITIES

L-1

LIST OF CONTENTS
1.0

Page
Purpose ...L - 3

2.0

Scope ....L - 3

3.0

Document Control .L - 3

4.0

Definitions, Terms and Abbreviations . L - 3

5.0

Responsibility . L - 3

6.0

References ...L - 4

7.0
7.1
7.2
7.3

Procedure
General . L - 4
Site Medical Facilities .. L - 5
Local Survey L - 6

8.0

Records .L -6

Table 7.1
Table 7.2

Equipment and General Supplies for the Clinic ..


Emergency Drugs for the Clinic ..

L-5
L-6

Guidelines for the Control of Heat Stress

L-2

1.0

PURPOSE

1.1

To define the minimum requirements for the establishment of appropriate medical


facilities to provide a reasonable standard of healthcare for the workforce.

2.0

SCOPE

2.1

This general procedure applies to all projects.

2.2

Guidance for the control of heat stress is provided in Appendix A.

3.0

DOCUMENT CONTROL

3.1

4.0

This Procedure will be a properly to this project. It is a controlled document means a document
that is registered and has its distribution controlled so that a holder has the correct issue of the
document at all times. All amendments, revision, will be subject to CM review and approval.
DEFINITIONS, TERMS AND ABBREVIATIONS

4.1

N/A

5.0

RESPONSIBILITY

5.1

The Project Manager has overall responsibility for the implementation of this general
procedure and shall ensure that:
Sufficient medical personnel are employed on the project to cater for the needs of the
workforce.
Early discussion with the Site HSE Advisor takes place to reach agreement on the
type and size of the medical facility required.

5.2

The HSE Advisor assigned to the project is responsible for:


Ensuring that all attendances to the medical centre are recorded by the medical
staff (see general procedure Emergency Planning and Accident Reporting). Ensuring
that suitably qualified medical personnel are employed.
The day-to-day administration of the medical personnel assigned to the project. Ensuring that
the medical facility is maintained to a satisfactory standard.

5.3

The Senior Medical Officer responsible for the medical facility shall:
Provide the Site HSE Advisor with status reports and advise on areas of concern
and identified trends.
Arrange for the medical facility to be maintained to the required standard.
Procure consumables to maintain stock levels.
Will arrange for all Prescriptions Only Medicines to be secured and shall hold an
inventory of all such drugs.

L-3

Liaise and make arrangements with local hospitals for support services (this
responsibility may be assumed by the Human Resources Department.)
Arrange through senior management emergency services for medical
evacuation.
Treat the workforce to a standard commensurate with the provided facilities.
Liaise with the Project Manager to determine the protocols to be adopted in the
event of death and to facilitate the repatriation of the body to its point of origin,
including certification and clearance requirements.
Be proactively involved in promoting good occupational health standards and
communicating such at site level.
5.4

The Site Nurse will:


Assist the Senior Medical Officer to administer medical treatment to patients.
Be proactively involved in promoting good occupational health standards and
communicating such at site level.

6.0

REFERENCES
ISO 9001:2008 Quality management systems - Requirements
OHSAS 18001:2007 Occupational health and safety management systems Specification

7.0

PROCEDURE

7.1

General

7.1.1 The Senior Medical Officer shall be either a doctor or a qualified medical assistant.
The choice depends upon a number of factors including the following:
The size of the workforce.
Whether or not a hospital or clinic is in the vicinity and attended by a doctor. Company senior
management.
7.1.2 The specification and equipment for the clinic reflect the site location and number of
persons involved.
7.2

Site Medical Facilities

7.2.1 A sufficient number of personnel will be provided and trained if necessary to meet the
requirements of the project for first aid cover.
7.2.2 The clinic shall be of a sufficient size to accommodate separate reception and
examination/treatment rooms and shall contain the general supplies and the equipment listed
in Table 7.1 and the emergency drugs listed in Table 7.2. Some supplies may be
unavailable in certain locations and the Senior Medical Officer shall finalise the emergency
drug list.

L-4

Table 7.1 Equipment and General Supplies for the Clinic


Office furniture - filing cabinets, desk
chairs etc
Examination couch
Fridge
Clinical waste bin
Sharps bin (small)
Blood pressure cuffs (mobile)
Examination light
Dressing trolley
Kidney bowls
Diagnostic set
Suturing kit (assorted)
Intubation kits
Eye magnet Stylet
Disinfectant
2x arm splint
2x leg splint
Finger splint
Flammazine cream
Multitrauma dressings
Syringes 1, 2, 5, 10, and 20ml
Tongue depressors
Cleaning solution (normasol or tisept)
Band aids
Steri-strips
Surgical masks
Oxygen cylinder with ambu bag, airway
and aspirator
Entonox kit
Cervical collars
Ventolin Spray

Oxygen cylinder complete with regulator,


flow meter, mask, nebuliser
Bandage scissors
Burn kit
Thermometer
Autoclave
1x box Examination gloves
Magnifying light
Polyfax ointment
Fucithalmic ointment
Antistin drops
Anesthetic eye drops
Eye pads
Alcohol solution
Lomotil or Loperamide (imodium)
Tubidressings A to L
Paracetamol (soluble)
E45 cream
Selection of adhesive tape
Cotton wool/buds
Needles 18, 20, 23, 25 G
Butadine
Triangular bandages
Lignocaine
Tetanus immunoglobuline
Stretcher (paraguard)
24x Saline solution
Ventolin Nebules (5 pack)
Magnesium trisilic ate
Kaolin Morphine

L-5

Table 7.2 Emergency Drugs for the Clinic


Name
Adenosine
Albuteral sol for nebulizer
Anactine
Atropine sulfate
Bretylium
Calcium chloride
Solumedrol
Dopamine pre-mixed
Dyphenhydramine
Epinephrine
Epinephrine
Glucagon
Lasix
Lidocaine
Metaproterenol
Morphine sulphate
Naloxine
Nitroglycerin spray

Quantity
6 mg
3cc
amp
1mg
100mg
20mg
70mg/125
mg IV
400mg
50mg
1/10000
1/1000
1mg
80mg
100mg
5%
10mg
2mg
0.4mg

Name
Nitroglycerine tablet
Procainamide
Sodium bicarbonate
Valium
Verapamil
Ventolin sol for nebulizer
Nifedipine
Demerol
Terbutaline
Theophylline
Rocephine
Dexamethazone
Mannitol
Glucose
Temgesic
Buscopan
Succinylcholine

Quantity
0.4mg
amp
100meg
TBA
5mg
TBA
10 by
10mg
100mg
SC
1m/IV
16r
4/8mg
10%
10%
TBA
IV
TBA

7.2.3 The medical centre will also have First Aid equipment that shall include treatment for
dehydration e.g. electrolytes and salt tablets for the treatment of heat stress. Guidelines for
the prevention, diagnosis, and treatment of heat-stress related conditions are given in
Appendix A.
7.3

Local Survey

7.3.1 A survey of the area near the project will be undertaken to determine the nature and
availability of local medical services. The result of the survey shall be discussed with the
Senior Medical Officer upon his appointment.
8.0

RECORDS

8.1

There are no records generated by this general procedure.

8.2

Records generated by referenced procedures shall be managed in accordance with the


originating procedure.

L-6

Guidelines for the Control of Heat Stress


Heat stress is defined as a medical condition ranging in severity from mild to fatal as a consequence
of working at elevated temperatures where the normal body temperature has increased to a level
requiring action.
Supervisors at any management level are responsible for ensuring that their workforce are not
subjected to heat stress by:
The provision of adequate supplies of drinking water. Ensuring that all personnel, including those of
subcontractors under their control, are not working in conditions that are likely to lead to the incidence
of heat stress. Monitoring their workforce during periods of high temperature, and at other
times such as Ramadan, for signs of heat stress and taking immediate action when necessary.
Heat stress is usually the result of work being performed at elevated temperatures. Contributory
factors may also include a decrease of natural body ventilation by heavy clothing or protective
personal equipment such as impervious suits.
If the body's physiological processes fail to maintain a normal body temperature because of
excessive heat, a number of physical reactions can occur ranging in degree from mild, such
as fatigue, irritability, anxiety and decreased concentration, dexterity, or movement, to fatal.
Heat stress is one of the most common and potentially serious illnesses that construction
workers encounter in areas where high temperatures normally occur and regular monitoring and
other preventative measures are vital.
All of the conditions described below must be reported to the clinic and treated as soon as possible.
Medical staff are to send regular communiqus on the subject of heat stress and inform
management of any concerns.
Supervisors are to ensure that their workforce is fully aware of the causes and symptoms of
heat stress and the measures that can be taken to prevent or reduce the effects.
Preventative Measures
Employees must have access to cool potable water at their place of work. Water and paper cups
are to be provided for all crews.
Shaded areas are to be provided for rest periods and instructions given to workers that
resting adjacent to or under plant and equipment is strictly prohibited. Fans may be required
to increase ventilation in such areas.
Heat Stroke
Heat stroke is an acute and dangerous reaction to heat stress caused by a failure of the heat
regulating mechanisms of the body, e.g. A breakdown of the employees temperature control

L-7

system that causes sweating. Body temperature rises so high that brain damage and death will
result if the person is not cooled quickly.
Typical symptoms are red, hot, dry skin, although the person may have been sweating earlier;
nausea; dizziness; confusion; extremely high blood pressure, rapid respiratory and pulse rate;
unconsciousness or in a coma.
The casualty must be cooled down and medical attention sought immediately, with the patient
transported to the clinic for treatment.
Heat Exhaustion
Heat exhaustion is a state of very definite weakness or exhaustion caused by the loss of
fluids from the body. This condition is much less dangerous than heat stroke, but must be
treated early on to prevent eventual deterioration to heat stroke.
Typical symptoms are pale, clammy, moist skin, profuse perspiration, and extreme weakness. Body
temperature is normal, pulse is weak and rapid, and breathing is shallow. The person may have
a headache, may vomit, and may be dizzy.
Remove the casualty from the heat, provide plenty of fluids to drink and allow rest.
Heat Cramps
Heat cramps are caused by perspiration that is not balanced by adequate fluid intake. Heat cramps
are often the first sign of a condition that can lead to heat stroke.
Typical symptoms are acute painful spasms of voluntary muscles; e.g. abdomen and extremities.
The casualty should drink plenty of water if the problem is too much salt due to sweat not
being replaced by drinking water. If the problem is a lack of salt (this is usually the case
when the person has been working for a long time in a heavy protective suit) a commercially
available carbohydrate-electrolyte replacement liquid should be given.
Heat Rash
Heat rash is caused by continuous exposure to heat and humid air and aggravated by chafing
clothes. The condition decreases the ability to tolerate heat.
Typical symptoms are a mild red rash, especially in areas of the body in contact with protective
clothing. Expose the affected skin to allow cooling and drying.

L-8

ANNEX M
PERMIT TO WORK
SCHEME

M-1

1.0

PURPOSE

1.1

To define a scheme for a safe system for working where control mechanisms are
considered necessary due to the nature of the work.

2.0

SCOPE

2.1

This technical procedure applies to all projects when the Client does not have a
comparable scheme in the Contract, and to the relevant activities in a workshop.

3.0

DOCUMENT CONTROL

3.1

This Procedure will be a properly to this project. It is a controlled document means a


document that is registered and has its distribution controlled so that a holder has the
correct issue of the document at all times. All amendments, revision, will be subject to CM
review and approval.

4.0

DEFINITIONS, TERMS AND ABBREVIATIONS

4.1

Permit Holder
The individual person responsible for supervising and controlling
the work requiring a permit.

4.2

Permit Authority

4.3

Competent Person, Permit to Work


managing a permit to work.

4.4

Competent Person, Electrical


A person assessed for his knowledge and
experience in electrical installations

4.5

Competent Person, Gas Testing


A person who has been assessed for
his knowledge and experience in the use of gas testing equipment.

4.6

Standby Man
A person who has been briefed and trained on the
procedures and equipment necessary for confined space entries.

A Competent Person, Permit to Work.


A person assessed for his experience in

emergency

M-2

4.7

Fire Watcher
A person assigned to the duties of fire suppression and
prevention necessitated by hot work activities.

4.8

Radiation Protection Supervisor


The person who is responsible for
supervising work with radiation sources (see general procedure Control of
Radiography).

5.0

RESPONSIBILITY

5.1

The overall responsibility for the implementation of this technical procedure is


with the Project Manager on a project.

5.2

The Permit Authority and the HSE Advisor have joint responsibility for the dayto-day operation of the permit to work scheme.

5.3

Members of the project management team, as applicable, have individual


responsibility for ensuring that the scheme is effective within their work area.

6.0

REFERENCES
ISO 9001:2000 Quality management systems - Requirements
ISO 14001:1996 Environmental management systems Specification with
guidance for use

7.0

PROCEDURE

7.1

Application for a Permit

7.1.1

This permit to work scheme operates on a project when there is no scheme run
by the Client under the Contract for the activities listed in section 7.1.2.

7.1.2

The Permit Holder shall make an application by completing the applicable form
Permit to Work (Permit). Individual forms are available for the following activities:
Extended Hours and Night Shift Working
Man Basket Operations
Confined Space Entry

7.1.3

The Permit shall be copied and distributed as follows after approval has been
signed:
Original
Copy
Copy
Copy

7.1.4

With the Permit Holder on the job site.


With the Permit Authority.
With the HSE Advisor
With the CM

Where the Permit covers more than one shift or working period, the Permit
Holder shall take the original to the Permit Authority for daily re-validation in
order that further work may proceed. Copies of the re-validated Permit shall be
distributed as for the initial approval.
M-3

7.1.5

The HSE Advisor shall maintain a register for permits to work and shall enter
the unique reference in section 1 of the Permit.

7.1.6

Unless otherwise noted on the individual Permit or elsewhere in this procedure


the Permit Holder shall complete all of the sections on the Permit up to the
approval section. He shall then present it to the Permit Authority for review and
approval.

7.1.7

The Permit is closed either when the work is complete or when it has become
invalid due to circumstances detailed on the permit.

7.2

Signatories to a Permit

7.2.1

Personnel such as the Project Manager, Construction Manager or HSE Advisor


can be assessed and registered as a Permit Authority depending on the nature of
the work to be carried out and the impact such work may have on adjacent
activities.

7.2.2

The Permit Holder may be a Section Engineer, Section Supervisor, appropriate


to the responsibilities of individual members of the management team and the nature
of the work.

7.3

Permit Authority Review


The Permit Authority shall review the Permit before signing approval to verify that
all the precautions and arrangements necessary to carry out the work safely
have been made and to ensure that all the requirements of the Permit are
satisfied.

7.4

Permit to Work: Extended Hours and Night Shift Working

7.4.1

Full details of permit management are given on the Permit.

7.4.2

Information on working at night is given in the general procedure Requirements


for Safe Working at Night.

7.5

Permit to Work: Man Basket Operations


Full details of permit management are given on the Permit.

7.6

Permit to Work: Confined Space Entry

7.6.1

Full details of permit management are given on the Permit.

7.6.2

The minimum requirements for confined space working are given in the procedure
Requirements for Safe Working in a Confined Space (ANNEX H) and are to
include adequate measures and responses to emergencies that cover all
personnel involved in the operations.

7.6.3

Entries will only take place after the HSE Advisor has checked the area. The
Permit Authority shall check entries where there is no HSE Advisor on the
M-4

project.
7.7

Gas Monitoring

7.7.1

The HSE Advisor shall decide the need for gas tests and the Competent Person,
Gas Testing shall conduct the testing when required. Results of the gas tests will
be entered prior to issuing the Permit.

7.7.2

The requirement for continuing testing will be specified on the Permit. The
Competent Person, Gas Testing is responsible for any further gas monitoring that
may be required.

7.8

Electrical Isolations

7.8.1

The Permit Holder shall notify the Competent Person, Electrical and the Tagging
Authority to carry out the necessary isolations. This work will be undertaken in
accordance with the clients system. Where this is not available the HSE Advisor
shall be consulted for advice.

7.9

Mechanical Isolations

7.9.1

The Permit Holder shall notify the Tagging Authority responsible for mechanical
isolations. This work will be undertaken in accordance with the clients system.
Where this is not available the HSE Advisor shall be consulted for advice.

7.9.2

The Tagging Authority shall co-ordinate with the Permit Authority, the Section
Supervisor and other personnel as necessary in the preparation of line diagrams
identifying spading and isolation points.

7.9.3

Consideration will be given to de-pressuring and draining down lines and equipment
in preparation for undertaking mechanical isolations.

7.10

Permit Holder Signing On

7.10.1

When the Permit Authority is satisfied that all conditions have been met in preparing
the area to be worked on, he shall discuss the measures taken and precautions
required to carry out the job safely with the Permit Holder.

7.10.2

When the Permit Holder is satisfied, he shall sign the approval section to indicate
acceptance of the terms and conditions set out in the Permit for doing the
work. The Permit Holder then accepts responsibility for the work.

7.10.3

The Permit Authority shall countersign to indicate the transfer of responsibility to the
Permit Holder.

7.11

Permit Holder Signing Off

7.11.1

When the Permit Holder is satisfied that the permitted work has been completed
or suspended for a sufficient length of time to warrant closure, he shall sign off
in the closure section of the Permit.
M-5

7.11.2

The Section Supervisor shall ensure on completing the work that:


Permit requirements have been cleared.
Materials have been cleared.
Personnel removed from the work area.
All necessary personnel have been informed.

7.12

Isolation Completion
The Competent Person, Electrical shall ensure that all isolations covered by the
permit have been removed, suspended or transferred. He shall then sign off the
Permit.

7.13

Permit Close Out


The Permit Authority shall check all closing signatures and confirm that the Permit can
be closed before countersigning the permit closure section.

8.0

RECORDS

8.1

A completed Permit is important document and may be used for claims, litigation or
for other purposes. The Project Manager or Workshop Manager shall ensure that
they are managed by the projects document control system.

8.2

The original of the completed Permit, where possible, or a copy, shall be retained
for a period of two years after completion of the project, following which period the
Corporate HSE Manager shall decide the disposition.

8.3

Documents generated by referenced procedures shall be managed in accordance


with the originating procedure.
-

M-6

STANDARD FORMS
Title
Permit to Work: Extended Hours and Night Shift
Working
Permit to Work: Man Basket Operations
Permit to Work: Confined Space Entry

Reference
[A]-SP-01-S16
[A]-SP-01-S17
[A]-SP-01-S18

Rev.

Pages

M-7

Permit to Work
Extended Hours and Night Shift Working

Project
1

Permit No.

Job Location

Work Activity

Number of Men on the Job

Name of Permit Holder

Name of Permit Authority

Job Checklist, to be completed by the Permit Holder


a)
b)
c)
d)
e)
f)
g)
h)
i)

Number of Workers

on date
on date

Number of Foremen

tick the appropriate response


The Permit Holder shall remain at the work site throughout the Permit validity period
PPE will be provided and its use shall be enforced by the Permit Holder
Adequate lighting has been provided at all work locations and access points
Adequate means of access have been provided
The Permit Holder shall notify the Duty HSE Supervisor of any accidents
The Duty HSE Supervisor shall notify the Clients Duty Officer of any accidents
The Duty HSE Supervisor is equipped with a radio or mobile telephone
The bus and driver will be located at the job location
Arrangements for late meals have been made

Yes

N/A

Approval of Permit

The work covered by the Permit may commence.

10

hrs
hrs

2 Permit Validity from


to

Signed

Permit Holder

Signed

Permit Authority

Permit Closure

The work covered by this Permit was completed at


The work site has been restored and the Permit is closed.

hrs

on

date

Signed

Permit Holder

Signed

Permit Authority

PERMIT MANAGEMENT
1
2
3
4
5
6
7

This Permit is valid only when Sections 1 to 9 inclusive are complete.


The original Permit shall be displayed at the work place and shall at all times remain under the responsibility of
the Permit Holder.
A separate copy of the completed Permit at both the approval and closure stages shall be given to the Permit
Authority, the HSE Department and the Client.
This Permit shall be taken on a daily basis for extended hours working.
This Permit shall be taken on a weekly basis for night shift working.
The Permit Holder shall apply for a Permit to the HSE Officer by 1500hrs on the applicable day.
Permit approval is to be completed by 1600hrs on the applicable day.

[A]-SP-01-S16

Permit to Work
Man Basket Operations

Project
1

Permit No.

hrs
hrs

2 Permit Validity from


to

Issued to

Job Location

Work Activity

Permit Holder

4 Issued by

7
8
9
10
11
12
13

tick the appropriate response


Lifejackets to be worn (only over water)
Tag lines required on the man basket
Safety harness required (only over land)
Safety harness will be tied off to crane hooks as required
Thorough Inspection Certificate for the man basket
Thorough Inspection Certificate for the crane
The Permit Holder will be in attendance

14

Approval of Permit

The work covered by the Permit may commence.


15

Permit Closure

on date
on date

Yes

Permit Authority

No

Remarks

Signed

Permit Holder

Signed

Permit Authority

Indicate either 15a or 15b. For 15b state the reason in the space provided.

15a

The work covered by the Permit was completed at

15b

This Permit is invalid because

hrs

on

date

Signed

Permit Holder

Signed

Permit Authority

PERMIT MANAGEMENT
1
2
3
4
5

This Permit is valid only when Sections 1 to 14 inclusive are complete.


The original Permit shall be displayed at the work place and shall at all times remain under the responsibility of
the Permit Holder.
A separate copy of the completed Permit at both the approval and closure stages shall be given to the Permit
Authority, the HSE Department and CM.
Any adverse change in circumstances shall cause this Permit to become immediately invalid. In this case, the
Permit Holder shall cease the work, withdraw the workforce and report to the Permit Authority.
This Permit may be given a validity period ranging from a single activity to two or more common activities over
a 7-day period.

[A]-SP-01-S17

Permit to Work

Confined Space Entry


Project
1

Permit No.

2 Permit Validity from


to

Issued to

Job Location

Work Activity

The confined space has been

Permit Holder

8 Gas testing required


Gases
Yes
No
Toxic
Flammable
Oxygen
9

10

Approval obtained for the use of

Yes

Permit Closure

12b

This Permit is invalid because

N/A

tick appropriate response

Explain any N/A response below

Coatings
Yes
N/A

Chemicals
Yes
N/A

Signed
Signed

Permit Holder
Permit Authority

Indicate either 12a or 12b. For 12b state the reason in the space provided.

The work covered by this Permit was completed at

Signed by Competent Person, Gas Testing

Isolated Mechanically
Yes
N/A

Solvents
Yes N/A

12a

1
2

tick appropriate response


N/A

Actual Readings

11 Approval of Permit
The work covered by this Permit may commence.
12

Yes

Isolated Electrically
Yes
N/A

HSE Checklist tick appropriate response


Method statement available
Pre-job toolbox talk conducted
All equipment and tools inspected and safe
Stand-by man available and in place
Life lines available
Adequate and safe lighting available
Adequate ventilation available
Manholes open and signs posted
Means of communication available
Fire fighting equipment available
All necessary PPE available
Means of access and egress available

Permit Authority

Flushed
N/A

Acceptable Readings
Zero
Zero
Between 19.5% and 21%

The confined space has been

on date
on date

4 Issued by

Vented
Yes

hrs
hrs

hrs

on

date

Signed

Permit Holder

Signed

Permit Authority

PERMIT MANAGEMENT
This Permit is valid only when Sections 1 to 11 inclusive are complete.
The original Permit shall be displayed at the work place and shall at all times remain under the responsibility of
the Permit Holder.
A separate copy of the completed Permit at both the approval and closure stages shall be given to the Permit
Authority, the HSE Department and the CM.
Any adverse change in circumstances shall cause this Permit to become immediately invalid. In this
case, the Permit Holder shall cease work, withdraw the workforce and report to the Permit Authority.

[A]-SP-01-S18

Permit to Work

Potrebbero piacerti anche