CLERK OF WORKS PROJECT REPORT

Project:

Refurbishment meru County Hotel

Report. No.: 3..

Address:

Week ending: 7/9/2016

Project Manager

Pascal obale

Architect/CA:

symbion Kenya Ltd

Main Contractor:

jasir Contractors

Clerk of Works:

mwenda G. Mutua

Tel:

726590340

Contract start date: 26/08/2016


Contract completion date: 15/07/2017

Fax:

Progress against programme: 15%

TRADES (Man days)

Worker

Tues
11th

Wed
12th

Thur
13th

Fri
14th

Sat 15th

Site agent

Mo
n
1
10th

Foremen

G.Labourers

Note

Store keeper

Main Contractors and

Steel Fixers

Sub-Contractors Labour

Carpenters

Return may be substituted

Masons

Electricians

Plumbers

12

18

22

20

19

14

Sund
ay
16th

Operators
Safety officer
Chainman
Welders
Security
*Note: Additional trades

Drivers

may be added.
Total man days

WEATHER
REPORT

Day

AM

PM

Monday 31/10/2016

clear

clear

Man
hours
lost0

Tuesday 1/11/2016

clear

clear

Wednesday 2/11/2016

clear

clear

Thursday 3/11/2016

clear

clear

Friday 4/11/2016

clear

clear

Saturday 5/11/2016

clear

clear

Total man hours lost in week


TOTAL TO DATE

VISITORS TO
SITE
(including
statutory
inspectors)

1. Consultants
Member from MC/DC

GENERAL
a) Site Direction No:
Issued

Item
site instructions during the period were mainly towards good workmanship and to
strictly follow drawings, specifications and hills of quantities.

a) Site Direction
Issued

b) Delays
c)Pending
Information

1. Determination of boundary wall's positions by th surveyor

c) Defective
Work
d) Drawings/
Information

N/A

2. Approval of foundation base by the structural engineer

e)Plant/Material
s Removed from
site
f)Plants/MaterialsPlant
on Site

Number

conc mixer

pocker vibrater

Materials

Quantity

4" x 2" timber

500

g) Health and
Safety Matters

h)Working
Conditions On
Site

no satisfaction Working platforms and scaffolds at large need to be well secured

ELEMENT

T = % Target

100%

90%

100%

25%

100%

40%

100%

5%

Kitchen
Reception and lift

C = % Completedcore
Shear wall
1. Form work to
columns bases
2. Form work to
walls of lift core
3. Form work to
shear wall
4. Form work to
columns

REMARKS

feets

GENERAL
REPORT

1. Unusual strike by they site workers was experienced due to delayed payments by the contractor whereby the workers
took some the equipments on site and disappeared with them
2. The site lacks functional and well maintained sanitation block for workers.

Signed
Enclosures

Mwenda G.
Mutua

(Clerk of Works)

Date
Distribution

Main contractor's labour return

1.Project Manager

Site directions

2.Architect

Pictorial Report

3.Client /Representative
4.All consultants

#######################