Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Strip foundation
Pad foundation
Raft foundation
Pile foundation
In visiting site, building consist 32 floors. But, the subsoil does not have that much
bearing capacity. Geological soil report recommended pile foundation, therefore Pile
foundation was selected.
The setting out of the building has been done by establishing three permanent
Control Points. Total Station was used for the work. Initial setting out was done for
the pilling works. It was the initial stage of the foundation works.
Sub Contractor for Pilling Works: Walkers Piling (Pvt) Ltd
Commencement: Late 2009
NO. of finished piles: 104
Pile Type: 1500mm & 1800mm diameter end bearing piles drilled not
exceeding than 1m into the bedrock.
Setup the Total Station above the known control point(see the below level
slab in the small void on slab).
Entered the coordinates of two control points and oriented the instrument by
targeting the telescope to the prism.
Entered the required coordinates and marked the points on slab by directing
the prism along the slab.
Drawn the off lines by connecting the points on the slab by a marking chord.
Chapter 2
2.10 Formworks
A rigid structure or mould fixed temporarily which is retained size, shape and the
position of Structural elements (Column, Walls, Beam, and Slab) unfit set up fresh
concrete. Formwork is the single largest cost component in the concrete building. In
some situation cost of formwork is higher than steel and concrete. Selection of
suitable formwork mainly depends on project quality, time and cost of erecting and
removing, safety of formwork and direct and indirect costs. Formwork should be
easily fabricate, easily erect and remove and more times reusable. There are two
types of formwork solution, which are:
Conventional Formwork
Basic formwork solution which can design carpenters also. Normally used Plywood,
Lumbers (2x2, 2x4), GI pipes, thread bar, Form tics, P-Cone, Props and Chains.
SystemFormwork
Differentiate with conventional formwork which are prefabricated outside of the job.
It's made of steel or timber specific shapes and sizes. In the world there different
Brands of system formwork which PERI, Doka, MEVA etc.
In the Mehewara Piyasa Project, PERI Formwork solution is being used and
combined with Conventional system also. PERI is a professional Formwork solution
service provider in Germany. PERI Formwork product included self-climbing, panel
and many of different types of products. Mainly in site used MULTIPLEX Girder slab
formwork, LIWA panels and VARIO GT 24 Column and Wall formwork.
Shear wall consist of one long panel (outer panel), 04 L-shaped panels and one
straight panel. Initially outer long panel lift from crane and slowly cover the
reinforcement to correct position and lock temporary. Before shuttering the panel
marking is done to position of outer panel edges on the kicker for convenience.
Because outer panel heavier difficult to adjust after shuttering and panel ( Cross
section about 400mm at corners) inserting space insufficient due to 400mm from
external scaffolding to concrete finish. Thoroughly have to ensure that below external
scaffolding are anchored from wall supports. Other interior panels are shuttered
according to PERI drawings to correct position. Filler (a gap between panel) should
be uniform gap because outer L-shaped panel hasnt any support and that panel
plumb depends on filler adjustment. After closing all panels angle distance of
4300mm should have to check at the top and all other dimensions also checked.
Plumbing are done same as others and ensure that tie rods are tightened and gaps
are closed.
Formwork Panel
wall
the
kicker
height
from
pipes along Side form and two 2X2" runners are placed and locked with form ties
vertically across the GI pipes.
acrow jacks
ideal
solution
for
complicated
ground
plans,
slabs
with
offsets
Girder slab formwork consisting of main and cross beams for the form lining of
choice.
Tilt-resistant support of the cross beams on the main beams through the use
of Flex clips.
Time
24 hours
5 days
Props to Slab
11 days
Props to Beam
16 days
8 days
28 days
2.20 Reinforcement
A concrete member is reinforced with the prime intension of increasing its tensile
capacity though in certain instances the reinforcing is done to increase the
compression capacity. The main concrete reinforcing material being used in the
industry at present is steel. As civil engineers we are expected to carry out our work
at the minimum cost yet ensuring the safety aspects of building. Therefore, in the
process of reinforcing a structural element we should use the optimum quantity at
the correct places while ensuring the safety aspects expected. Hence the practical
exposure gained in this area would definitely be useful in the future.
The standard that governs the reinforcement work are BS 4466 and BS 8110. Bars
should be cut and bent correctly and accurately on an approved type of cutting and
bending apparatus, to the size and shape shown on the details Drawings or the
consultant approval.
Bar Type
Characteristic
Length of a
Strength (N/mm2)
bar (m)
Available sizes
Ribbed Tor
steel bars
460
6m
40mm(diameter)
9m
Plain Mild
steel bars
BRC
25mm. 32mm,
(diameter)
Bundles of
250
I 900kg
250
Fabric
Table 2.11 r/f bar details
BRC Fabric
Mild Steel
The strength of this steel is 250 N/mm2. This is a soft carbon steel and easy to work
with it. These bars are used in reinforced concrete slabs, beams, columns,
foundations etc. these are plain round bars and diameter varies from 6mm-32mm.
Tor Steel
The strength of this steel is 460 N/mm2. Diameter varies from l0mm-40mm. These
bars have helical ribs running along the surface of the bar.
The designs have been done taking the characteristic strength of the Tor steels bars
as 460N/mm2 and the value for Chinese bar is less than that. Therefore a safety
factor of 1.5 is applied and hence more bars are used accordingly.
T1 means the top most bar and T2 is below it. Likewise B1 is the bottom bar
closer to the bottom surface and B2 is above it.
SGD means Staggered. This was seen in the septic tank slab designs and in the
beams depth is more than 750mm. That way cracks can be controlled.
system provides easy alignment for engagement of the incoming rotating bar and
develop full strength when hand tightened.
Moment Barbreak Coupler consists of a High Tensile Carbon Steel Sleeve with
identical threads at opposing ends tapering towards the middle.
Bar ends shall be square cut and taper threaded accordingly for connection. Both
couplers and threaded bars are supplied with protective plastic caps.
Moment Barbreak Couplers are usually located in RC Structures such as long
columns, inclined columns, long beams, cantilevered structures where tensile
loadings are greater than for normal situation, etc where bars are free to turn.
2.20.3.2 Cranking
Cranking is also critical in fabrication of reinforcement. Most of the time, bars are
crank for the columns and beams. Cranking is needed to correct the align error
occurring after lapping two bars. Normal proportion of crank is 1:10 but the cranking
length is always given in the drawing. Cranking length should be included in the bar
schedule for bar bender to make it. Cranking reduces the strength of the bar about
40%of its actual strength.
from grease, oil, mud, mound oil or excessive rust. If not bond between
reinforcement and concrete will fail. Also corrosion of reinforcement is affected to the
bond between them. Because of that reinforcements should be stored properly.
The bars must be laid so that the correct type, size and length can be located
easily.
The bars should be stored in a raised platform to avoid dampness.
The bars must not get connected with materials like mud, oil and grease.
Long storage periods especially in high humidity conditions should be
avoided.
Steel reinforcements must be properly sheltered in a store room away from
rain and moisture.
If we could guide these lines, a better use of reinforcement can be expected in a site.
2.30 Concrete
Concrete consists of a mix of cement, sand, metal and pure water, and to be of the
right quality, the mix must be properly designed and the right amount of each
material correctly batched.
preferably batched by weight: this reduces the differences between one batch of
concrete and the next.
The concrete should possess the strength, durability, impermeability and resistance
to abrasion required for the proposed structure. It should be free of such defects as
cracking, honeycombing, palling of the surface, undue shrinkage etc. The concrete
should be of good quality and should be produced with careful control over the
batching of materials, water cement ratio etc. Necessary care and attention should
be given to the design and preparation of formwork.
In its fresh state, concrete should
Be well mixed
Be fully compacted
Quality of cement
Type of aggregate
Method of transportation
In this site designed concrete mixes have been designed as High Performance
Concrete (HPC). In grade 65 cement content is slightly reduced by adding Micro
Silica and Fly Ash. In grade 30 only Micro Silica is used with the cement. Industrial
byproducts such as Silica Fume (SF) and Fly Ash (FA) can be utilized to enhance
the
strength
and
water
permeability
characteristics of
High
Performance
Concrete (HPC) also improves compressive strength and flexural strength of the
concrete. The utilization of these industrial by products is becoming popular
throughout the world because of the minimization of their potential hazardous
effects on environment.
which
accelerate
the
corrosion
concrete.
Concrete with law slump contains more air voids therefore it should be
thoroughly compacted. For small-scale concrete hand tampering is enough but
for a large concrete vibrators are essential.
Surface Vibrators.
Bleeding
2.30.5.1 Bleeding
Bleeding is occurred when concrete contains more water than necessary. Due to this
aggregate particles settle down and the excess water comes up over the surface of
the compacted concrete. If there is a bleeding it can cause to make concrete porous
and hence leak and non-durable. Bleeding is preventing by controlling the water
content, using finely and cement and controlling compaction. So they just put the
porker vibrator and removed
2.30.5.2 Segregation
This is happening due to the separation of coarse aggregates from the mortar and
loosing uniformity and homogeneity of concrete. The differences in size of particles
an specific gravity are the reasons of segregation. To reduce the segregation,
concrete should be prepared by using well-graded particles. Then it holds the mortar
better. And also the incorrect handling during transportation and placing of concrete
and over compaction has affected the segregation. The final result should be the
honeycombs. This is a large issue for the structural elements. So if there are any
honeycombs that should be repaired or demolished and re-concreted.
Honeycombs occur for many reasons,
1 Inadequate poker vibrates.
2 Not concreting layer by layer.
3 Inadequate hammering.
4 Not providing proper formwork.
5 Not using adequate size poker.
6 Concrete grout leaking.
7 Not using skilled labors.
In mass concrete thermal expansions can be occur due to heat generated by the
Hydration reaction between cement and water. To avoid such situation in this site
chilled water/ crushed ice is used at the batching plant when mixing the concrete.
2.40.1.1 Advantages
1. Easy to install/dismantle, no need to spend more time hammering all those nails,
therefore you will be reducing the labor cost.
2. It is environment friendly! No need to cut more coconut trees for lumber.
3. Still reusable for other projects if you buy or you can just rent.
4. Safe to use as long as you meet the specs of your project.
Fig. 2.47 & 2.48 Frame scaffolding fixed at outer wall of the building with fixed steel
ladders for providing access to the upper floors
Cuplock
systems-
Versatile!
Cuplock systems- Timely tested and Proven design with safety accessories
Cuplock System has a proven performance history on an extensive number of
sites, meeting the requirements of the various statutory bodies.
Low maintenance.
Fig. 2.50 Cuplock Scaffoldings provided at the outer wall of the building
Chapter 3
3.10 Quality Control/Assurance Procedure
In the Site, Quality of works is the very important. Therefore many activities carried
out to maintain the quality.
1. Consultant Inspection
2. Quality control
3. Quality Assurance
manner possible. Within this broad context, quality assurance involves continued
evaluation of the activities of planning, design, development of plans and
specifications, advertising and awarding of contracts, construction, and maintenance,
and the interactions of these activities.
3.20 Safety
Occurrence of accidents is common in the construction industry and safety is a
critical issue compared to other industries. Economically it is important as it also lead
to delays in the construction process. The delays and total expenses following an
accident are usually much higher than the original cost of establishing and
maintaining safety standards. Therefore it is understood that the safety evaluation
and control save money. Site safety should be well maintained in good standards to
convince the industry without any risk on professional, institutional and social
perspective.
Accidents may happen in sites in many occasions such as
Falling objects from formwork, roof work or bricks form upper floors.
Health hazards may create from dust, liquid, gasses, & fumes.
There are some instructions that are displayed on a board that anyone who
enters to the site should follow these instructions.
Safety helmets Used against injuries from falling objects on to heads. Any
person who enters to the site should wear helmets. There were sufficient
helmets in the site.
Safety belts
height. It should be sufficiently strong to take the full weight of the person.In
our site sometimes workers didnt care to wear safety belts although they
were thoroughly warned.
Safety goggles - Goggles were used specially in welding and when bar
cutting.
Safety nets
that may happen to people and properties outside the building. It also
prevents movement of dust, outside the site.
Safety gloves - Safety gloves were provided when lifting or dealing with hard
materials.
(This topic (3.20) has been discussed with more details in the Assignment 2.)
3.30 Conclusion
In my Site visit I learned lot of site related activities and gained knowledge about lot
of specific Processes .The SP Sierra Joint Venture (Pvt) Ltd Is becoming one of
most prominent Construction Company in Sri lanka. They maintain their Quality very
well. In my visit I Observed some techniques used to done works easy and Quality
assuring way in Setting out process, Formworks, Reinforcement Arrangement, Super
structure works Etc.