Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
OPERATING COMPANY
PROJECT
PHASE
EPC
18/03/13
Rev
Date
Description
PVE
EPC CONTRACTOR
(VSP-PVC-PTSC)
VSP
Approval
BPOC
Approval
CA
Approval
Document Number:
BB.G-VSP-PVE-ED-20-ME-DAS-004
Number of Pages: 5 (Including this page)
PROJECT
PHASE
EPC
18/03/13
Rev.
Date
Description
CAJ
Prepared Checked
by
by
JMS
NNT
EM
PM
Discipline
Sub-Contractor
Team
Leader
SPMB
EPC Contractor
EPC CONTRACTOR
(VSP-PVC-PTSC CONSORTIUM)
Document Number:
PV ENGINEERING J.S.C
BB.G-VSP-PVE-ED-20-ME-DAS-004
FOR FUEL/INSTRUMENT
SPMB
EPC Contractor
EPC CONTRACTOR
(VSP-PVC-PTSC CONSORTIUM)
BB.G-VSP-PVE-ED-20-ME-DAS-004
Rev
0 Sheet: 3 of 5
20-H-1000A/B
Plant Location:
Viet Nam, Landfall Station at Mui Tram
Natural Gas
Supplier:
BB.G-VSP-PVE-ED-20-PR-PID-005
Purchase Order No.:
BB.G-VSP-PVE-ED-20-PR-CAL-002
No. of Units:
2 x 100% (Note 8)
Heating for Instrument/Fuel Gas
OPERATING DATA
Contents
Cases
Natural Gas
Max. Duty (Note 6)
Design Temperature
Design Pressure
Operating Temperature
Operating Pressure
Pressure Drop
(Max./Min.)
Inlet
98
0.76
55.39
21.01
47.35
barg
85.69
85.39
66.05
65.75
0.3 / VTA
Sm3/h
11 Molecular Weight
108.3
10.2
12 Mass Density
13 Viscosity
Outlet
C
bar
10 Gas Flowrate
Inlet
80 / -29
barg
(Allow./Calc.)
Outlet
23.39
kg/m3
130.5
87.47
79.52
68.06
cP
0.0156
0.0159
0.0143
0.0149
14 Cp/Cv
2.147
1.569
1.659
1.52
15 Compressibility
0.6826
0.8458
0.8065
0.861
w/m2K
VTA
kw
kw
VTA
m2
VTA
W/cm2
VTA
21 Element Load
kw
VTA
22 Sheath Temperature
20 Heat Flux
DESIGN DATA
23
25 Service Class
27 Joint Efficiencies
28 Corrosion Allowance
29 Wind Speed
66
Heating Element
N/m2
950
67
67 / 89
32 Insulation
Required
33 Fireproofing
VTA
34 Painting
Note 23
CONSTRUCTION
36 Vessel Orientation
T3
mm
17.9 / 37
63 Temperature Class
64
35
0.0785
VTA
61
24 Design Code
26 ASME Code Stamping
SS316
70 Environmental Protection
IP65 (Min.)
71 Location
72
73
MATERIALS
Horizontal
74 Shell/Head/Pads
75 Tubesheet
ASME SA105
76 Nozzle Necks
mm
168 (VTC)
mm
3,081 (VTC)
mm
VTA
ASME SA105
mm
VTA
78 Elements
INCOLOY 800
79 Baffles/Tie Rods
316L SS
ASME SA36
41 Type of Heads
42 Type of Support
Saddle
N/A
Required
82
Required
46 Nameplate
Required
84 Gaskets
Note 15
VTA
316 SS
VTA
86 Lifting Lugs
316L SS
316L SS
(Note 18)
50
Active
mm
VTA
88 Element Couplings
51
Inactive
mm
VTA
89
52 Element Diameter
mm
VTA
90
53 Baffle Pitch
mm
VTA
VTA
kg
54 Baffle Cuts
VTA
VTA
kg
55 Baffle Thk
mm
VTA
93 During Operating
VTA
kg
mm
VTA
94 During Hydrotest
464 (VTC)
kg
VTA
95 Control Panel
VTA
kg
WEIGHTS
VTA
96
59
97
60
98
Rev
Sheet:
4 of 5
20-H-1000A/B
Plant Location:
Viet Nam, Landfall Station at Mui Tram
Natural Gas
Supplier:
BB.G-VSP-PVE-ED-20-PR-PID-005
Purchase Order No.:
BB.G-VSP-PVE-ED-20-PR-CAL-002
No. of Units:
2 x 100% (Note 8)
Heating for Instrument/Fuel Gas
FABRICATION AND INSPECTION
1
2
Inspection Authority
Required
Heat Treatment
Per code
Non-Destructive Testing
Radiography
Ultrasonic
Magnetic Particle
Dye Penetrant
Per Code
EN 10204 3.2
10 Impact Testing
Per Code
11 Hydrostatic Test
Per Code
Per Code
NOZZLES
13
14
Nozzle
NPS
15 Number
mm
16
N1
50
17
N2
18
Flange
Number
GAS COMPOSITION
28
Service
Remark
29
Composition
Mole%
30
Methane
71.55
Rating
Type
900# WN
RTJ
Inlet Gas
31
Ethane
2.81
50
900# WN
RTJ
32
Propane
1.47
N3
50 (VTC)
900# WN
RTJ
33
I-Butane
0.42
19
N4
50
900# WN
RTJ
Outlet Gas
34
N-Butane
0.33
20
N5
50
900# WN
RTJ
35
I-Pentane
0.16
21
VTA
VTA
Heater Element
36
N-Pentane
0.09
N-Hexane
0.09
N-Heptane
0.06
0.02
24
Supply shall be
37
with it's Terminal
Box, J-Box (Min. IP 38
56)
39
25
40
N-Octane
N2
26
41
CO2
20.00 (Note 4)
27
42
H2O
0.0147
22
23
2.99
VTA
VTA
VTA
Outlet
Inlet
H
N2
N1
N3
N4
Insulation
VTA
N5
Sliding Saddle
Fixing Saddle
NOTES
1.
2.
3.
4.
5.
6.
7.
8.
required duty of each heater is 50% of total required duty (0.157 kW).
Both Heater units shall be running normally in parallel and handle 50% of total required heat load. If one Heater trips, the
other shall automatically ramp up to handle 100% total required heat load.
Rev 0 Sheet:
of
20-H-1000A/B
Natural Gas
BB.G-VSP-PVE-ED-20-PR-PID-005
BB.G-VSP-PVE-ED-20-PR-CAL-002
Heating for Instrument/Fuel Gas
Plant Location:
Viet Nam, Landfall Station at Mui Tram
Supplier:
Purchase Order No.:
No. of Units:
2 x 100% (Note 8)
NOTES
9.
The Heater (elements, terminations etc) and all instrument / electrical equipment shall be certified for use in the applicable
hazardous area unless otherwise noted.
10.
11.
12.
13.
14.
15.
16.
17.
18.
The Heater shall be interface to SDS for shutdown and PCS for alarm via hardwire connection.
The Heater should be electrically checked and certified for insulation, flash, resistance check etc., during final acceptance.
Vendor to furnish general arrangement drawing in tender showing all leading dimensions and nozzle connections.
Vendor to verify that specified materials are suitable for the proposed service and design conditions.
Flange gasket contact face shall have ASME B16.5 standard finish of Ra 3.2 to 6.3 microns.
RTJ gaskets shall be solution heat-treated 316 stainless steel octagonal ring to ASME B16.20 Type R with max. 160 Brinell.
All stud bolts, nuts and washers shall be coated with Type II Class 8 chromated/cadmium plating.
All internal bolting shall be double-nutted or provided with "lock-tab" washers.
The provision of lifting lugs shall be for the whole unit (provided on Shell) and separately for the lifting and removal of the
elements c/w it's terminal box and junction box. The TCP also shall have it's lifting cleats etc. fitted. The lift lugs design shall be
tested and approved by the third party.
Vendor to advise details of impingement baffle (as required) at the inlet entrance of the shell side flow.
Deleted.
Vessel shall be provided with two support saddles, one shall be fixed and the other shall be sliding to allow for the expansion
of the shell.
Vendor to design and indicate the anchor bolt details (number, diameter, material specification, location, loading etc). Based on
Vendor's design and approvals, the anchor bolts will be provided by others.
The painting shall be as per "Specification for Onshore Painting" document no. BB.G-VSP-PVE-ED-60-CR-SPC-009.
19.
20.
21.
22.
23.