Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
User Guide
Contents
Purpose
Overview
USBGC Rationale
Application of EA Prereqs and Credits
CHP Guidance
Purpose
The USGBC created the District Energy
Systems (DES) Guidance document to
provide a framework to properly account
for the impact of district energy systems
within the LEED program. Primarily these
are cooling and heating utilities, but also
include electricity from a Combined Heat
and Power system.
Overview
The USGBC guidance document accounts
for DES under the Energy and
Atmosphere credit category of the rating
system.
USGBC Rationale
USGBC does not want to penalize a
project connected to a DES on the LEED
Program; therefore, the prerequisite
requirements for energy performance and
commissioning are independent of the
DES facilities (much like an electric
utility).
Exception
This philosophy does not, however, apply
to the prerequisite for non-CFC
refrigerants. The LEED Rating Systems
encourage the accelerated removal of
environmentally destructive products and
inefficient systems. Therefore, the
requirements of EA P3, Fundamental
Refrigerant Management must still be
met.
Prerequisite #1
Fundamental Commissioning of
the Building Energy Systems
Credit #3
Enhanced Commissioning
Credit #3 FAQs
What DES Systems must be commissioned? Only
applies to services used by the project building. (i.e.
Chilled Water)
To what level should new DES systems be
commissioned? Follow the same commissioning
requirements as the building.
What about existing DES systems: Follow the
commissioning requirements of LEED for existing
buildings.
Are their options to commissioning the plant? Yes,
Existing DE systems may meet this requirement by
showing proof of maintenance and efficiency
monitoring programs.
Prerequisite #2
Minimum Energy Performance
Goal Prereq #2
Minimum Energy Performance:
Goal: Verify the proposed buildings annual
energy use is below a maximum target.
For energy modeling, this is referred to as
Option1 - Building Stand-Alone Scenario.
Prereq #2 Definitions
Proposed
Building:
Baseline
Building:
The design of
the building
pursuing LEED
Certification.
Identical except
designed to
meet minimum
ASHRAE 90.1
guidelines.
Option1 Model
Inputs
Output
Other Utilities
($/year)
$ per year
for total
energy use
Proposed Building $
X
100 * 1
Baseline
Building
$
Result
Baseline
Building
$ per year
for total
energy use
LEED
Version
Target
2.2
14%
2009
10%
Buildings
DES Rate
Structure
Baseline &
Proposed
Building
Virtual
Utility Rate
Virtual DES
Rate
Apply
Formulas
on page 14
of the main
guide
Option1 FAQs
Does a modeler have to run an Option 1 model?
No, if you can meet the floor point requirements
under Option 2 (see slide # 28)
What info does a modeler need from the DES to
run an Option 1 model? Only the rate structure
charged to the building owner for the utility sold.
Can I meet the Pre-requisite Energy
Requirement with only an Option 1 Model? Yes
Can I earn points for optimizing energy with an
Option 1 Model? Yes, up to a certain cap. (see
slide # 28)
Credit #1
Optimize Energy Performance
Option 2 Model
Virtual DES-equivalent Plant
Proposed
Building
$ per year
for total
energy use
%
Improvement
Points Earned
12%
16%
20%
24%
28%
32%
11
36%
13
40%
15
44%
17
48%
19
$ per year
for total
energy use
Points Earned
10.5%
14%
17.5%
21%
24.5%
28%
31.5%
35%
38.5%
42%
10
Energy rates
based on
actual building
utility rates
Baseline
Building
$ per year
for total
energy use
Notes:
All energy equipment types (waterside and airside) are based on ASHRAE
90.1, Appendix G, Table 3.
Proposed
Building
$ per year
for total
energy use
Note:
All upstream DES equipment is included (chillers, towers, pumps,
boilers, etc).
Energy Input
(Gas, Oil,
Electric, etc.)
Energy Received
Virtual On-Site
Plant Efficiency
Proposed
Building
(Gas, Oil,
Electric,
etc.)
Energy Received
Natural Gas @
$7
1,000,000 BTUs
Boiler Efficiency
loss
15 %
Pump Energy
loss
1%
Distribution Heat
loss
8%
Natural Gas @
$8.78
1,000,000 BTUs
DES Option 1
points cap*
DES Option 2
points floor**
LEED-NC
10
LEED Schools
10
LEED CS
LEED v2.x
LEED CI
LEED v2009
LEED-NC
19
10
LEED-NC Retail
19
10
LEED Schools
19
10
21
12
24
12
LEED CS***
LEED
Healthcare****
LEED CI
LEED CI Retail
Option 2 FAQs
What if the DES uses a energy source, such as
fuel oil, in which the building does not have a
rate? In this case, use the DES rate for that
energy source.
What methods can be used for determining the
overall DES efficiency?
Measurement of actual system efficiency.
Computer Modeling of the System.
Default values provided by USGBC.
Prerequisite #3
Fundamental Refrigerant
Management
Goal: No CFCs
Application Options
1. Dont use CFC refrigerants anywhere in the
DES.
2. Phase out all existing CFC refrigerants
within a 5 year timeline.
3. Phase-out not required if not economically
feasible and leakage is controlled.
R-11
R-12
Credit #4
Enhanced Refrigerant
Management
Other EA Credits
Credit #2: On-site Renewable Energy
Credit #5: Measurement & Verification
Credit #6: Green Power
Credit #2
On-Site Renewable Energy
Biofuel-based electrical
Geothermal Htg. Systems
Low-impact hydroelectric
Wave & Tidal power
Landfill Gas
Credit 2 FAQs
Do I have to run an Option 2 model to use this
credit? Yes, Option 2 is required to determine
the buildings total energy use.
How do I account for the cost of renewable
energy as a fuel in modeling? All qualified
renewable energy is considered FREE in the
model.
What if the DES generates both chilled water
and steam from renewable sources? Run the
formula for each utility provided and sum the
results.
Credit #5
Measurement & Verification
Credit #6
Green Power
QFUEL
Turbine
Generator
WE
QTH
Reference: http://www.epa.gov/chp/basic/methods.html
QFUEL
Generator
WE
QTH
ELECTRIC
WE
=
Q FUEL
THERMAL
Q TH
=
QFUEL
TOTAL =
W E + Q TH
Q FUEL
WE
QTH
Proposed
Building
$ per year
for total
energy use.
QFUEL
Proposed
Building
Energy
Input
Useful Electrical
Energy Received, WE
Electrical Distribution
Virtual On-Site Plant
Thermal Efficiency = THERMAL* (1 - % Distribution Loss) =