Radio Network Design and Optimization Department

Security Level: Confidential

CMPak Swap Project


Cluster Acceptance Procedure and
Criteria

2016-11-15

Radio Network Design and Optimization


Department

Page1, Total9

Radio Network Design and Optimization Department

Security Level: Confidential

Introduction & Objective............................................................................................................3

Cluster Acceptance.......................................................................................................................3

Reporting and Submission for Acceptance...............................................................................5

Exclusion Criteria........................................................................................................................7

2016-11-15

Radio Network Design and Optimization


Department

Page2, Total9

Radio Network Design and Optimization Department

Security Level: Confidential

1 Introduction & Objective


The objective of this document is to provide CMpak with the
procedures and criteria for Acceptance of CMpak Swap Project. This
would include comparison of cluster performance before and after the
swap.
It also addresses some exclusion criteria that would be applied in
order to filter out the cells that are performing poorly due to issues
out of the project scope.

2 Cluster Acceptance
PAC will be based on cluster level comparison of OSS statistical and
Drive Test KPIs before and after swap.
Acceptance items and criteria of OSS statistical KPIs:
The following table shows the acceptance items of OSS statistical
KPIs for UMTS technology as per NPM contract.(suggest daily KPI
acceptance due to Ramadan )
UMTS acceptance OSS KPIs for Swap
S
N
1
2
3
4
5
6

KPI
RRC Setup Success Ratio (%)
RAB Setup Success Ratio (%)
CS Service Drop Ratio (%)
PS Call Drop Ratio (%)
Soft HO Success Ratio (%)
CS W2G Inter - RAT HO out Success Ratio (%)

UMTS monitor OSS KPIs for Swap


S
N
1
2
3
4
5
6
7
8

KPI
HSDPA User Average Throughput (Kbps)
CS traffic
PS traffic
RTWP
UL CE utilization
HSDPA Users
HSUPA Users
TCP utilization

Before
Swap

After
Swap

Before
Swap

After
Swap

Table 1 UMTS OSS KPIs Acceptance items


2016-11-15

Radio Network Design and Optimization


Department

Page3, Total9

Radio Network Design and Optimization Department

Security Level: Confidential

For OSS KPI acceptance, the network should be frozen for 30 days
before swap.
For OSS KPI comparison, the pre-Swap KPI value shall be the
average value of 14 days and the post-swap KPI should be the
average value of 7 days. A cluster shall be acceptable for CMpak
when the following OSS KPIs are equal to or better than that
before swap.
For UMTS monitor OSS KPIs need to be as monitor KPI instead
of acceptance KPI, if have large fluctuation we can clarify it by
observe GUL traffic together
Acceptance criteria for DT KPIs:
In general, a cluster performance after Swap would be considered
acceptable as long as there is no loss of coverage when compared
with pre swap drive test. For very few points degraded In post D.T,
although in total the D.T is better than before and these points
not degraded too much, it should not affect cluster acceptance
In order to compare the pre and post-drives, Cluster drive tests
will be conducted with same route, with the same equipment and
settings.
After cluster swap, we can organize post-DT at once.
As per CMPAK required use F1/F7 generate new dual-carriers
instead of old network frequency using, but DT test take free
mode (dont lock frequency), so the pre and post DT coverage will
have slight differentia, the phenomenon should be acceptance.
The others acceptance criteria statement
WO feedback within 1 day and acceptance report (cluster)
feedback within 3 days.
It is no limitation for parameter change in swap day due to some
urgent activities, after that we will make record and send them.
Huawei would not require any WO to take such corrective
measure.
Swap sites if belong to indoor site which just cover indoor area
supply fundamental service verification and IBS sites should
eliminate from cluster range due to implement and install hard
cant catch swap progress
2016-11-15

Radio Network Design and Optimization


Department

Page4, Total9

Radio Network Design and Optimization Department

Security Level: Confidential

Some secretly region or specially region which cant accessed


since emergency like road blocked, protest activity, heavy rain
etc. which generate pre and post coverage have a different. For
those case just clarify it with photos, poster, event, news and
shouldnt affect swap cluster acceptance.
After cluster acceptance will automatically be handed over to
CMPak/NPM teams.
For user complain if happened after cluster swap and OSS KPI
under monitor period, Huawei is charge of complain handling.
RF acceptance shouldnt relate to hardware part, they cant be
conditional on to BSS or any other acceptances.
CMpak supply free SIM card and High performance FTP.
During swap if individual sites remained in swap cluster due to
proprietor blocking or permission issue and generate cross sites
between Huawei and ZTE, but over 85% sites had completed
swap, we can implement Post-test. Once the DT KPI and OSS KPI
affected by crossed sites we need to filter those cells to calculate
KPI but if still low than pre-KPI the cluster should be acceptance
according clarification.
Test methods and test tools description for each service
Test Tools description
Tools Description
TEMS 16
S4
GPS
Sierra wireless 3G watcher
Call test No.
FTP Server

Comments
Used for Drive Test (3G)
Support 3G technology, CS service, 2 S4
GARMIN
Used to test PS Service
Destination no.( S4)
High performance FTP

UMTS D.T KPI and coverage KPI as per NPM requirement


Cluster
NO.

2016-11-15

DT KPI
CS CSSR
CS AMR Call Drop Rate
CS Soft Handover Success Rate
PS RAB Assignment Success
Radio Network Design and Optimization
Department

Pre-test
KPI

Posttest KPI

Page5, Total9

Radio Network Design and Optimization Department

Security Level: Confidential

rate
PS Drop rate
HSDPA Moving Throughput
Average RSCP ( Idle)
Average EC/IO ( Dedicated)

Items

UE1/UE2(Lock3G but don't lock


frequency)

Duration
Call number

Data Card
2

Mobile type

Laptop
HSDPA

File Size

4~6 Gb

15sec

Idle period

FTP Server

GPS

GPS

GPS
GPS

Items

180 sec

Idle period

Voice

Laptop

Mobile type

Common
Settings
Mobile
placement
Test type

Common Settings
Mobile
Placement
Test type

Software

Drive test tool

Software

Drive test tool

Post processing

Post processing

3 Reporting and Submission for Acceptance


A cluster acceptance procedure will be initiated as soon as the sites
of that cluster have been swapped. The KPIs for acceptance will be
monitored on hourly basis and to verify the basic functionalities and
performance. A report on cluster level major KPIs will be sent to
CMpak within a day.
Afterwards, daily level stats monitoring and optimization will be done
to ensure that there is no degradation in performance compared to
pre swap KPIs. As soon as the KPIs are stable and all acceptance
criteria have been satisfied, the report for PAC will be submitted to
CMpak, the cluster will be considered provisionally accepted by
CMpak if no issues are fed back from CMpak in 3 working days. Please
refer to the below attachment Cluster Acceptance Report Template
for further details regarding the cluster acceptance report format for
each technology.
Single Site Verification template is also attached below for reference.
2016-11-15

Radio Network Design and Optimization


Department

Page6, Total9

Radio Network Design and Optimization Department

Security Level: Confidential

3G Swap Cluster
Acceptance Report.docx

2016-11-15

Functionality Test
Template.xls

Radio Network Design and Optimization


Department

Page7, Total9

Radio Network Design and Optimization Department

Security Level: Confidential

4 Exclusion Criteria
Any degradation in performance due to below mentioned scenarios
shall be excluded from KPI calculation for OSS and DT KPIs
Since we are using F1/F7, the throughput results would be
different when compared to cells using F1/F2. Exclusion needs
to be given in such cases.
The hardware issues, software or parameter configuration of
other vender, core network issues (especially QOS, CGI, paging
issue ) or other issues related to end to end connectivity
The
period
where
major
network
activity/retuning/change/incident is performed should be
excluded from the KPI calculation with mutual agreement.
Change in traffic due to user behavior, special aggressive
promotional packages
High traffic Events adversely affecting performance.
LHR network almost dual-carries coverage but exist the two
carries discontinues coverage area. Once user long-term
random occupy discontinues frequency which will cause
difference in DT coverage and KPI between Pre-swap and Postswap. So once the phenomenon is appeared we just make a
clarification
The IUR strategy will be implemented during 3G network swap.
Since IUR parameter wrong configuration, no IUR deployment
or IUR parameters not configured even IUR compatibility issue
between Huawei and ZTE cause the marginal degradation on a
specific KPI such as SHO SR, traffic, CDR which should be
excluded; ZTE should be charge of corresponding IUR strategy
and parameter design even implement verification test for IUR
compatibility at ZTE side, if due to ZTE side IUR configuration
issue cause KPI degradation and complaint should be excluded;
External interference or Burst larger region interference should
be as clarify condition
ZTE have a large changed such RNC level parameters modified,
reframing, 3G power adjust, the second carries expanded,
upgrade action during swap or network freeze cause the KPI
2016-11-15

Radio Network Design and Optimization


Department

Page8, Total9

Radio Network Design and Optimization Department

Security Level: Confidential

mapping result mismatching make KPI go down should be as


clarify condition
if KPI have a degradation due to transmission related issues
including but not limited TR alarms, TR QOS issue or bandwidth
limitations should be as clarify condition
During swap the paging rate maybe have a slight fluctuation
due to few sites swapped but received much paging message,
this case shouldnt be criticized
Some ZTE cell configured CPICH power over 8W, we need to
fellow accordingly. Whereas the dedication channel power will
reduced since product power is fixed so the KPI maybe have a
slight degradation. This case is objective problem should be as
conditional

2016-11-15

Radio Network Design and Optimization


Department

Page9, Total9