2 Cluster Acceptance
PAC will be based on cluster level comparison of OSS statistical and
Drive Test KPIs before and after swap.
Acceptance items and criteria of OSS statistical KPIs:
The following table shows the acceptance items of OSS statistical
KPIs for UMTS technology as per NPM contract.(suggest daily KPI
acceptance due to Ramadan )
UMTS acceptance OSS KPIs for Swap
S
N
1
2
3
4
5
6
KPI
RRC Setup Success Ratio (%)
RAB Setup Success Ratio (%)
CS Service Drop Ratio (%)
PS Call Drop Ratio (%)
Soft HO Success Ratio (%)
CS W2G Inter - RAT HO out Success Ratio (%)
KPI
HSDPA User Average Throughput (Kbps)
CS traffic
PS traffic
RTWP
UL CE utilization
HSDPA Users
HSUPA Users
TCP utilization
Before
Swap
After
Swap
Before
Swap
After
Swap
Page3, Total9
For OSS KPI acceptance, the network should be frozen for 30 days
before swap.
For OSS KPI comparison, the pre-Swap KPI value shall be the
average value of 14 days and the post-swap KPI should be the
average value of 7 days. A cluster shall be acceptable for CMpak
when the following OSS KPIs are equal to or better than that
before swap.
For UMTS monitor OSS KPIs need to be as monitor KPI instead
of acceptance KPI, if have large fluctuation we can clarify it by
observe GUL traffic together
Acceptance criteria for DT KPIs:
In general, a cluster performance after Swap would be considered
acceptable as long as there is no loss of coverage when compared
with pre swap drive test. For very few points degraded In post D.T,
although in total the D.T is better than before and these points
not degraded too much, it should not affect cluster acceptance
In order to compare the pre and post-drives, Cluster drive tests
will be conducted with same route, with the same equipment and
settings.
After cluster swap, we can organize post-DT at once.
As per CMPAK required use F1/F7 generate new dual-carriers
instead of old network frequency using, but DT test take free
mode (dont lock frequency), so the pre and post DT coverage will
have slight differentia, the phenomenon should be acceptance.
The others acceptance criteria statement
WO feedback within 1 day and acceptance report (cluster)
feedback within 3 days.
It is no limitation for parameter change in swap day due to some
urgent activities, after that we will make record and send them.
Huawei would not require any WO to take such corrective
measure.
Swap sites if belong to indoor site which just cover indoor area
supply fundamental service verification and IBS sites should
eliminate from cluster range due to implement and install hard
cant catch swap progress
2016-11-15
Page4, Total9
Comments
Used for Drive Test (3G)
Support 3G technology, CS service, 2 S4
GARMIN
Used to test PS Service
Destination no.( S4)
High performance FTP
2016-11-15
DT KPI
CS CSSR
CS AMR Call Drop Rate
CS Soft Handover Success Rate
PS RAB Assignment Success
Radio Network Design and Optimization
Department
Pre-test
KPI
Posttest KPI
Page5, Total9
rate
PS Drop rate
HSDPA Moving Throughput
Average RSCP ( Idle)
Average EC/IO ( Dedicated)
Items
Duration
Call number
Data Card
2
Mobile type
Laptop
HSDPA
File Size
4~6 Gb
15sec
Idle period
FTP Server
GPS
GPS
GPS
GPS
Items
180 sec
Idle period
Voice
Laptop
Mobile type
Common
Settings
Mobile
placement
Test type
Common Settings
Mobile
Placement
Test type
Software
Software
Post processing
Post processing
Page6, Total9
3G Swap Cluster
Acceptance Report.docx
2016-11-15
Functionality Test
Template.xls
Page7, Total9
4 Exclusion Criteria
Any degradation in performance due to below mentioned scenarios
shall be excluded from KPI calculation for OSS and DT KPIs
Since we are using F1/F7, the throughput results would be
different when compared to cells using F1/F2. Exclusion needs
to be given in such cases.
The hardware issues, software or parameter configuration of
other vender, core network issues (especially QOS, CGI, paging
issue ) or other issues related to end to end connectivity
The
period
where
major
network
activity/retuning/change/incident is performed should be
excluded from the KPI calculation with mutual agreement.
Change in traffic due to user behavior, special aggressive
promotional packages
High traffic Events adversely affecting performance.
LHR network almost dual-carries coverage but exist the two
carries discontinues coverage area. Once user long-term
random occupy discontinues frequency which will cause
difference in DT coverage and KPI between Pre-swap and Postswap. So once the phenomenon is appeared we just make a
clarification
The IUR strategy will be implemented during 3G network swap.
Since IUR parameter wrong configuration, no IUR deployment
or IUR parameters not configured even IUR compatibility issue
between Huawei and ZTE cause the marginal degradation on a
specific KPI such as SHO SR, traffic, CDR which should be
excluded; ZTE should be charge of corresponding IUR strategy
and parameter design even implement verification test for IUR
compatibility at ZTE side, if due to ZTE side IUR configuration
issue cause KPI degradation and complaint should be excluded;
External interference or Burst larger region interference should
be as clarify condition
ZTE have a large changed such RNC level parameters modified,
reframing, 3G power adjust, the second carries expanded,
upgrade action during swap or network freeze cause the KPI