Sei sulla pagina 1di 4

337087071.

xls

Service BOQ for ..


No

Item

Price Factor
1
Unit

QTY

Final Unit Price


exclusie VAT (PKR)

Baseline Unit Price


exclusie VAT (PKR)

SOW

reference

Materials
m

72 CELL MULTICRYSTALLINE MODULE 300 WATT SOLAR PANEL details reference


the specifications

pcs

YJV-0.6/1KV-2*10mm2

m
pcs

Junction Box IP55 or IP65 details to the specifications

9.1

Solar frame 3pcs,Material:Q235B/ASTM A36;.Reference the design drawing

pcs

9.2

Solar frame 9pcs,Material:Q235B/ASTM A36;.Reference the design drawing

pcs

1.27

PV Power Cable PFG1169-1*4 mm2 black and Red LSZH cable

1.28
1.31
1.33

11/15/2016

Top 5 brand globally,attach as specification

14

337087071.xls

Service BOQ for


No

Item

Unit

Final Unit Price


exclusie VAT (PKR)

QTY

Baseline Unit Price


exclusie VAT (PKR)

SOW

reference

Materials

1.4

Anchor Bolt,Materials:Q235B/ASTM A36include matching nuts and plate as design


drawing

KG

1.5

Steel Grade60

KG

1.6

5/8 inch steel rod with coated copper,Length 3meter

pcs

1.7

Concrete class A(1:1.5:3)

m3

1.8

Concrete class E(1:4:8)

m3

1.9

Outlet pit(inner size L*W*H:600*600*700mm):include Lean(1:4:8),bricks,CI/RCC


concrete cover of outlet pit:0.9m*0.9m;details according to design

set

1.10

HDPE pipe;out diameter 63mm/3.8mm

1.11

HDPE pipe;out diameter 40mm/3.5mm

1.12

Power cable:3*4mm2

1.13

Power cable:3*1.5mm2

1.14

Power cable:3*2.5mm2

1.15

Power cable(VMS):3*6mm2

m
m
m
m
m
m

1.16

STP 5e cable,waterproof

1.17

Ground cables,6mm2, Yellow&Green color

1.18

Ground cables,1.5mm2,Yellow&Green color

1.19

Flexiable GI pipe,out-diameter 40mm;

m
m
m

1.20

Anti-climb fence as per design

KG

1.21

Signal cableTraffic signalRVVP 4*1.5mm2;

1.22

Signal cable(Radar)RVVP 4*1mm2;

m
m

1.23

Supply of outdoor 2 core fiber,Single Mode( ITU-T G.652 D) optical fiber cable

1.24

Flexiable GI pipe out-diameter 20mm

1.25

Traffic Lights:300mm,High light LED,Anti-Sunshine cover One for each lamp,as per
specification.

pcs

1.26

Arrow Traffic Lights:300mm,High light LED,Anti-Sunshine cover One for each lamp,as
per specification.

pcs

1.29

Hoops for gantry

KG

1.32

RVVSP 5*0.5

Reference the
design drawings

Outlet Pit Design


Drawing
PTMS Site

1
1

IPNV Site

600/1000V,Newage/Fast

1
1
1

Nordan UK/3M

1
1

Lamp Central Light Intensity/View Angle:>=3000mcd/30;Lamp


Light Life>50000h;Rated Power (W/Single
Light)<15W;Working Temperature-40 ~ 80;Anti-Sunshine
cover One for each lamp.
Lamp Central Light Intensity/View Angle:>=3000mcd/30;Lamp
Light Life>50000h;Rated Power (W/Single
Light)<15W;Working Temperature-40 ~ 80;

Service
2

2.1

2.2

2.3

2.4

3.1

4.1

Foundation Construction

Service: Excavation and backfilling of Square type(including debris clean)

Service: Excavation of Pier type(including debris clean)

Service: Backfilling and reinstatement of road cut per site

Service: Pouring of concrete for foundation and OP(exclude material)

Details please refer to the detailed design drawings, the


following for your reference:
1.Before digging works, the site will be cleaned first, including
bushes, branches of trees, roots, rubbish and other obstacles.
2.Check site location is available ( no fiber, no power cable,
gas pipe.etc),joint visit and decision/solution will be required.
3.Before civil work,take proper safety messure(include warning
tape/Reflective vest/ Security isolation cones.etc )
4.Excavation the surface and dig the foundation(square type)
by necessary tools according to the design.
5.Backfilling and reinstatement of road surface.
6.Debris clean: After digging and installation, all the
construction rubbish should be carried away from field to the
places specified by local councils.

Details please refer to the detailed design drawings, the


following for your reference:
1.Before digging works, the site will be cleaned first, including
bushes, branches of trees, roots, rubbish and other obstacles.
2.Check site location is available ( no fiber, no power cable,
gas pipe.etc),joint visit and decision/solution will be required.
3.Before civil work,take proper safety messure(include warning
tape/Reflective vest/ Security isolation cones.etc )
4.Excavation the surface and dig the foundation(Pier type) by
necessary tools according to the design.
5.Backfilling and reinstatement of road surface.
6.Debris clean:After digging and installation, all the
construction rubbish should be carried away from field to the
places specified by local councils.

Details please refer to the detailed design drawings, the


following for your reference:
1.Take proper safety messure(include warning tape/Reflective
vest/ Security isolation cones.etc )and reinstatement solution
2.Backfilling and reinstatement of road surface in time and
meet the customer requirements.
3.Debris clean:After digging, all the construction rubbish
should be carried away from field to the places specified by
local councils.

Cum

Details please refer to the detailed design drawings, the


following for your reference:
1.Bury, rectification and fix steel cage & stiffener & anchor bolt
by necessary tools(For example level instrument); bury HDPE
pipe
2.Prepare concrete casting
3.Concrete pouring for foundation base
4.Concrete pouring, compaction,vibrator
5.If choice Pre-Production model, Need to provide the crane
and truck for transport the foundation from factory to site.
6.Watering and curing concrete within 24 hours after
pouring,use sack or plastic thin film to cover concrete
foundation for curing, foundation concrete should be watered
2~4 times per day, curing period not less than 7 day.

site

Details please refer to the detailed design drawings:


1.Construction of the grounding system resistance less than
10
2.Grounding cable should be fixed firmly and protected by
Flexiable GI pipe

Details please refer to the detailed design drawings,reference


as below:
1.Install the pole and the arm, routing cables(Provide all
necessary connectors) through the pole and all the
equipments in warehouse or on sites.
2.Label the cables at both ends with right standard.
3. Installation of the cabinet and awning on the pole. And
install all the necessary equipments(For example: router.etc )in
the cabinet.
4. Installation of the PTZ Camera/Box Camera/CPE/Fisher
eye camera on the arm.
5. Connect all cables include the power cable grounding cable
and network cable.
6.Transportation of IPNV pole (include all site materials,
supplier staffs and associated tools & machines)to the sites(in
lahore)with proper safety
7.Installation of Pole with crane( including Fuel ) on the
foundation and fixed firmly,make sure level and vertical
8.Installation of IPNV solar frame and solar panels
9.Installation of anti-climb fence
10.Power-On pre-commissioning and setting Parameters.

Cum

Cum

Site

Grounding

Service: Construction of grounding system(<10ohm) as per design(Excluding materials)

Transportation&Installation

Transportation&Installation of IPNV with both pole and equipment as per standard with
proper safety

11/15/2016

Site

24

337087071.xls

4.2

4.3

4.4

4.5

4.6

4.7

4.7

Transportation&Installation of IPNV with equipment (exclude pole)as per standard with


proper safety

Transportation&Installation of batteries

Transportation&Installation of RLMS with both pole and equipment as per standard with
proper safety

Transportation&Installation of VMS with both pole and equipment(include power


cabinet) as per standard with proper safety

Transportation&Installation of JTMS with both pole and equipment(include power


cabinet) as per standard with proper safety

Transportation&Installation of PTSC with both pole and equipment(include power


cabinet) as per standard with proper safety

Transportation&Installation of PTSC with equipment(exclude pole) as per standard with


proper safety

11/15/2016

Site

Site

Site

Site

Site

Site

site

Details please refer to the detailed design drawings,reference


as below:
1.Transportation of IPNV Equipments(exclude pole) (include
all site materials, supplier staffs and associated tools &
machines)to the sites(in lahore)with proper safety
2.Label the cables at both ends with right standard.
3.Installation of the cabinet and awning on the foundation. And
install all the necessary equipments(For example: router.etc )in
the cabinet.
4.Installation of the PTZ Camera/Box Camera/CPE/Fisher eye
camera on the wall/existing pole/ceiling.
5.Connect all cables include the power cable grounding cable
and network cable.
6.Installation of ICC30 cabinet and anti-climb fence
7.Power-On pre-commissioning and setting Parameters.

Details please refer to the detailed design drawings,reference


as below:
1.Transportation of batteries (include all site materials, supplier
staffs and associated tools & machines)to the sites(in
lahore)with proper safety
2.Insatllation of batteries in the power cabinet
3.Connect the cables and label cables at both ends with right
standard

Details please refer to the detailed design drawings,reference


as below:
1.Transportation of RLMS pole(include all site materials,
supplier staffs and associated tools & machines)to the sites(in
lahore)with proper safety
2.Install the pole and the arm, routing cables(Provide all
necessary connectors) through the pole and all the
equipments on sites.
3.Installation of Pole with crane(including Fuel) on the
foundation and fixed firmly,make sure level and vertical
4..Label the cables at both ends with right standard.
5. Installation of the pole cabinet and awning on the pole. And
install all the necessary equipments(For example: router.etc )in
the cabinet.
6. Installation of the/ANPR/LED/Box camera/PTZ camera/CPE
on the arm.
7. Installation of Power cabinet on the foundation.
8. Connect all cables include the power cable/grounding
cable /network cable/Fiber cable.
9. Power-On pre-commissioning and setting Parameters.

Details please refer to the detailed design drawings,reference


as below:
1.Transportation of VMS pole(include all site materials,
supplier staffs and associated tools & machines)to the sites(in
lahore)with proper safety
2.Install the pole and the arm, routing cables(Provide all
necessary connectors) through the pole and all the
equipments on sites.
3.Installation of Pole with crane(including Fuel) on the
foundation and fixed firmly,make sure level and vertical
4.Label the cables at both ends with right standard.
5.Installation of Power cabinet and all the necessary
equipments(For example: router.etc )in the cabinet.
6.Installation of the screen/Announcements device/camera on
the arm.
7.Connect all cables include the power cable/grounding
cable /network cable.
8.Installation of anti-climb fence
9.Power-On pre-commissioning and setting Parameters.

Details please refer to the detailed design drawings,reference


as below:
1.Transportation of JTMS pole(include all site materials,
supplier staffs and associated tools & machines)to the sites(in
lahore)with proper safety
2.Install the gantry pole and the arm, routing cables(Provide all
necessary connectors) through the pole and all the
equipments on sites.
3.Installation of Gantry with crane(including Fuel) on the
foundation and fixed firmly,make sure level and vertical
4.Label the cables at both ends with right standard.
5.Installation of Power cabinet and all the necessary
equipments(For example: router.etc )in the cabinet.
6.Installation of the ANPR/Radar/Flash lights/camera on the
arm.
7.Connect all cables include the power cable/grounding
cable /network cable.
8.Installation of anti-climb fence
9.Power-On pre-commissioning and setting Parameters.

Details please refer to the detailed design drawings,reference


as below:
1.Transportation of PTSC pole(include all site materials,
supplier staffs and associated tools & machines)to the sites(in
lahore)with proper safety
2.Install the pole and the arm, routing cables(Provide all
necessary connectors) through the pole and all the
equipments on sites.
3.Installation of Pole with crane(including Fuel)on the
foundation and fixed firmly,make sure level and vertical
4.Label the cables at both ends with right standard.
5.Installation of Power cabinet and all the necessary
equipments(For example: router.etc )in the cabinet.
6.Installation of the traffic lights on the new pole or existiong
pole.
7.Connect all cables include the power cable/grounding
cable /network cable.
8.Power-On pre-commissioning and setting Parameters.

Details please refer to the detailed design drawings,reference


as below:
1.Transportation of PTSC equipments(include all site
materials, supplier staffs and associated tools & machines)to
the sites(in lahore)with proper safety
2.Installation of traffic lights with crane(including Fuel)on the
foundation and fixed firmly,make sure level and vertical
3.Label the cables at both ends with right standard.
4.Installation of Power cabinet and all the necessary
equipments(For example: router.etc )in the cabinet.
5.Installation of the traffic lights on the new pole or existiong
pole.
6.Connect all cables include the power cable/grounding
cable /network cable.
7.Power-On pre-commissioning and setting Parameters.

34

337087071.xls

4.8

Transportation&Install the solar system with both support structure and solar panel as
per standard with proper safety.

5.1

6.1

Details please refer to the detailed design drawings,reference


as below:
1.Transportation of solar structure(include all site materials,
supplier staffs and associated tools & machines)to the sites(in
lahore)with proper safety
2.Assemble the solar structure, routing cables(Provide all
necessary connectors) and all the equipments on sites.
3.Installation of solar structure on the foundation and fixed
firmly,make sure level and vertical
4.Label the cables at both ends with right standard.
5.Installation of Power cabinet and all the necessary
equipments(For example: router.etc )in the cabinet.
6.Installation of the solar panels on the support structure.
7.Connect all cables include the power cable/grounding
cable /network cable.
8.Power-On pre-commissioning and setting Parameters.

Site

Details please refer to the detailed design drawings,reference


as below:
1.Laying power cable/ data cable/optical fiber cable in
duct/aerial (include provide overhead steel cable if
necessary)as per design
2.Remaining a Steel threading wire in the duct
3.Supply and make the necessary connector for cables
4.Connect all the cables firmly and protected as per design
5.Label the cables at both ends with right standard

Details please refer to the detailed design drawings,reference


as below:
1.Mark alignment,excavation,lay pipe,warning
tape,backfilling ,compaction,debris removal
2.SPECpipe depth 0.8M, warning tape depth 0.3M; if depth
can't reach requirement due to underground services ,joint visit
and decision/solution will be required
Details please refer to the detailed design drawings,reference
as below:
1.Mark alignment,excavation,lay pipe,warning
tape,backfilling ,compaction, surface reinstatement, debris
removal
2.SPECpipe depth 0.6M, warning tape depth 0.3M; if depth
can't reach requirement due to underground services ,joint visit
and decision/solution will be required

set

Wiring

Laying power cable/data cable/optical fiber cable in duct/aerial as per design

Trench civil work

Duct construction on naked soil surface/green belt as per Sow and spec.

6.2

Duct construction on tuff tiles/concrete/asphalt surface as per Sow and spec.

6.3

Supply and fix with inner dia 2 inch GI pipe protection

6.4

Supply and fix with inner dia 3 inch GI pipe protection

6.5

Maunal bore and fix pipe

6.6

HDD bore

Details please refer to the detailed design drawings,reference


as below:
1.Supply and fix with inner dia 2 inch GI pipe protection
2.For extra protection for HDPE pipe where have heavy traffic
Details please refer to the detailed design drawings,reference
load
as below:
1.Supply and fix with inner dia 3 inch GI pipe protection
2.For extra protection for HDPE pipe where have heavy traffic
load
1.Use maunal bore tools to bore through the road/ some area
not allow excavation. And fix required pipe into the bore hole
as per designed pipe type and qty.
1.Use HDD machine to bore through the road and pull
required HDPE pipe qty as per desgin required.

Commissioning

1.Adjusting of the camera angle view direction with Bucket


Crane and other necessary tools (for example:power
generator if necessary)until meet the requirement of customer
7.1

Commissioning of IPNV(include camera view and power cabinet)

site

7.2

Commissioning of solar system.

site

2.Configuration of the camera IP and OSD.etc parameter


3.Commissioning of the Power cabinet,make sure the power
system and network system work normally
4.Support for acceptance(including SAT, pre-commissioning
acceptance, User acceptance test, TOC)

1.Adjusting of the solar system with Bucket Crane and other


necessary tools until meet the requirement of customer

2.Commissioning of the Power cabinet,make sure the power


system and network system work normally
3.Support for acceptance(including SAT, pre-commissioning
acceptance, User acceptance test, TOC)

Dismantle existiong traffic light system and IPNV in Ashura

8.1

Dismantle existing traffic lights (exclude pole and foundation)include cables packaged
and transport to appoint place.

set

1.Dismantle existing traffic lights (exclude pole and


foundation)include cables packaged and transport to appoint
place(in lahore).
2.Clean the sites

8.2

Dismantle existing IPNV include cables packaged and transport to appoint place.
Ensure safety of dismantled IPNV equipments.

set

1.Dismantle existing IPNV equipments in Ashura include


cables packaged and transport to appoint place(in lahore).
Ensure safety of dismantled IPNV equipments.
2.Clean the sites

set/month

9
9.3

Frame Items
24X7 Bucket Crane Service for complete 30 days including Fuel

Remark:
1. All project management, business trip costs and acceptance cost
are included above.All equipments transportation cost from warehouse
to site are included above equipment installation service.
2. All cost of services required for execution the Contract are included
in the price as above.
3. All cost of materials, hardware,
software, license and etc required for execution the Contract are
included in the price as above, even though some item(bellows pipe)
and Qty are not indicated as above.

11/15/2016

44

Potrebbero piacerti anche