Sei sulla pagina 1di 4

DAY 1 (OCTOBER 25, 2016)

TIME
1:00 2:30
2:30 3:00
3:00 3:30
3:30
5:30
6:30
7:00
7:30

5:30
6:30
7:00
7:30
7:45

ACTIVITY
ASSEMBLY TIME
DISCUSSION OF THE PROJECTS OBJECTIVES
DISCUSSION OF THE APPLICATION OF THE PROJECT MATERIAL
RECOVERY PROGRAM
RESEARCH ON THE POSSIBLE DESIGN AND ITS MECHANISM
SKETCHING OF THE DESIGNED PARTS
LAYOUT THE PROCESS FLOWCHART
PLANNING OF THE GANTT CHART
SUMMARY AND DOCUMENTATION OF THE MEETING

On the first day. The members first discuss the projects objective, a conveyor
that separates metal and plastic. Its commonly used in the material recovery
program. After that, the group research for the possible sensors that can be used
the possible design of the conveyor and its proponents. Then the design has
been sketched, its a conveyor that uses a material alignment mechanism to hold
and align the metal or plastic that will be inserted and sorted in the conveyor. A
tentative flowchart has been generated and a gantt chart to follow for the next
weeks to come.
DAY 2 (OCTOBER 27, 2016)
TIME
1:00 2:30
2:30 3:00
3:00 3:30
3:30
5:30
6:30
6:45

5:30
6:30
6:45
6:55

ACTIVITY
ASSEMBLY TIME
CHANGING THE PROJECTS OBJECTIVES
DISCUSSION OF THE APPLICATION OF THE PROJECT LOGISTICS
INDUSTRY
RESEARCH ON THE MATERIALS
SKETCHING OF THE DESIGNED PARTS
LAYOUT THE PROCESS FLOWCHART
PLANNING OF THE GANTT CHART

6:55 7:00

SUMMARY AND DOCUMENTATION OF THE MEETING

On the second day, the group alter the objective of the project. From a material
recovery program to logistic industry, so that the previous project using an
ultrasonic sensor will still be applicable. The researchers just add a color sensor
to separate the different color of the boxes. Each color will represent the
destination of the packages. Designing two separate conveyors to accommodate
the two size of the parcel. The group decide to use the old conveyor as its main
conveyor, so that the expense will be lessen. The conveyor has been inspected
to see how will be the parts be layout. Afterwards, the members strategically
planned the activities within the given period of time.
DAY 3 (NOVEMBER 3, 2016)
TIME
1:00 2:30
2:30 4:00
4:00 5:30
5:30 6:30
6:30 6:45
6:45 6:55
6:55 7:00

ACTIVITY
ASSEMBLY TIME
ALTERING THE DESIGN
RESEARCH ON THE MATERIALS
SKETCHING OF THE DESIGNED PARTS AND POSSIBLE LAYOUT
LAYOUT THE PROCESS FLOWCHART
UPDATING THE GANTT CHART
SUMMARY AND DOCUMENTATION OF THE MEETING

The group decided to meet for the third time to continue


improving the project. The design of the conveyor was
altered once more for a more concrete design. The group plans to study more
about the color sensor since it's new to them before buying it. The materials
were gathered and tested and also the group's gantt chart has been updated.
The following are more accomplishments done by the group as of present: More
concrete idea of the process flow of the project. Tentative design of the conveyor.
Lengthen the conveyor to accommodate more processes to be done on it. Gather
the materials needed. (i.e., sensors, connecting wires and wood) Tested the
sensors and checked if it is still fit for usage. Planned the size and material to use
for the sample boxes that will go on the conveyor. Updated gantt chart of the
groups's plan.

Potrebbero piacerti anche