Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
PREPARED FOR:
CITY OF BURLINGTON
SUBMITTED BY:
180 Battery Street, Suite 350
Burlington, VT 05401
802.383.0118
www.rsginc.com
RSG
IN COOPERATION WITH:
HARTGEN ARCHEOLOGICAL ASSOCIATES, INC
POINT OF BEGINNING LAND SURVEYING
802.383.0118
www.rsginc.com
Scoping Study for Intersection of South Winooski Avenue, Howard Street, and Saint Paul
Street (Burlington STP BP15(17))
including at the study intersection of this proposal. Winooski Avenue as a corridor is a complex facility,
alternating between one-way and two-way vehicle traffic in several locations, with contra-flow bike lanes in
some locations or no bike lanes at all, with four lanes of traffic in the downtown to quieter neighborhood
streets to the north and the south. The scenarios investigated are equally diverse and complex, and demonstrate
the confidence that the City and RPC have in RSGs ability to make sense of such a constrained environment.
We look forward to applying our talents to this intersection in detail, working with the City and the residents to
investigate opportunities and uncover the constraints. We understand the goal of this project is to enhance the
safety, livability and comfort of residents and patrons, allowing for the neighborhood to foster this
prominent gateway between communities as an activity center, while allowing efficient vehicle travel.
The project will be managed by me, Jonathan Slason, PE. With years of related active transportation experience
on this continent and abroad, I will shepherd this project through the various stages of development with
support from David Grover, PE and Roxanne Meuse, EIT. Corey Mack, PE will assist with the development
of conceptual designs, alternatives and cost estimates, and provide technical review throughout the project.
RSG has also enlisted the support of Hartgen Archeological Associates, Inc. to provide historical and
archaeological survey support and Point of Beginning Land Surveying to provide site survey support.
We look forward to the opportunity to work with you and the City on this project. Our team is ready and eager
to provide the City, residents, and this emerging neighborhood a path forward to transportation equity.
Sincerely,
RSG
JONATHAN SLASON, PE
Senior Engineer
CONTENTS
1.0
2.0
PROJECT APPROACH.................................................................................................................... 7
2.1 | Scope of Work ............................................................................................................................... 7
TASK 1: Kickoff Meeting with the Steering Committee & Project Team .......................................... 7
TASK 2: Development and Maintenance of a Public Participation Plan.......................................... 7
TASK 3: Compile Base Map / Existing Conditions .......................................................................... 8
TASK 4: Identify Local Concerns, Purpose and Need Statement ................................................... 9
TASK 5: Develop Conceptual Alternatives ...................................................................................... 9
TASK 6: Alternatives Presentation ................................................................................................. 10
TASK 7: Preliminary Cost Estimates and Project Time Line ......................................................... 11
TASK 8: Report Production and Final Presentation ...................................................................... 11
2.2 | Estimated Labor Hours By Task .................................................................................................. 12
2.3 | Project Schedule ......................................................................................................................... 13
3.0
ii
4.0
RESUMES....................................................................................................................................... 21
5.0
1.0
RSG, in coordination with Hartgen Archaeological Associates, Inc. (Hartgen) and Point of Beginning
Land Surveying (POB Surveying) are pleased to submit this proposal to conduct the Scoping Study for
the intersection of South Winooski Avenue, Howard Street and Saint Paul Street. The goal of this
scoping study is to identify and evaluate alternative improvements to improve the safety for people
walking and bicycling, meet accessibility standards, and to foster the emerging neighborhood by
supporting enhancements to pedestrian, bicycling and motorist travel.
The intersection of Saint Paul Street with South Winooski Avenue and
Howard Street has long been a difficult junction to safely and efficiently
accommodate the variety of users who pass through. Several competing
factors highlight the challenges including:
-
activity center.
-
further east on the Hill to points west along Pine Street and the
waterfront. The intersection is a natural collector for school-aged children walking from the
Five Sisters neighborhood to Edmunds Elementary and Middle Schools. Furthermore, the
colorful crosswalk and proposed raised intersection at Pine and Howard may create higher
east-west pedestrian and bike flows.
FIGURE 1: VIEW OF THE INTERSECTION WEST FROM HOWARD STREET, WITH TOMGIRL
JUICE ON THE LEFT AND SHYGUY GELATO ON THE RIGHT.
City of Burlington
Scoping Study: South Winooski Ave, Howard
Street, and St. Paul St Intersection
TECHNICAL PROPOSAL
FIGURE 2: BURLINGTON
NEIGHBORHOODS.
The steep grade of Howard Street affects signal capacity for vehicles, and
can sometimes contribute to difficult winter conditions for all modes of
travel. In addition, the steep grade results in high velocity surface water
during storm events and increased risk of scour along the curb line.
SOURCE:
SEVEN DAYS,
DON EGGERT
ARTIST.
Five approaches to the intersection, built into a hillside, with acute angles, all contribute to
intersection complexity, resulting in long crossing distances and limited intersection sight
distance. Furthermore, the signal has not been upgraded to include pedestrian countdown
signals.
Commuting periods experience higher traffic flows between Shelburne Street to the south, St.
Paul Street and South Winooski to the north. The three busy legs meet at this intersection,
resulting in at least three signal phases, more unused all-red time, and increased congestion.
St. Paul Streets (north of the intersection) daily two-way traffic is approximately 9,500 vehicles
per day with the Winooski one-way southbound leg experiencing approximately 3,500 vehicles
per day. Howard is estimated to have an average daily traffic of less than 600 vehicles per day.
This study will require knowledge of the Burlington network, the
Impact
Worksheet
to
identify
to
communicate
the
project
continual
maintenance
of
this
plan
modes which people use to travel, and how the wider network
may be affected will be critical to the success of this study.
We know that input from the Neighborhood Planning Assembly,
local stakeholders, and public officials is critical to developing
alternatives that address real public needs in a feasible way, and we
will utilize multiple venues to receive public input. RSG will work
with the City to identify populations and stakeholder groups
which may otherwise be underrepresented by contacting housing
authorities, SSTA/Paratransit operators, and other organizations
City of Burlington
Scoping Study: South Winooski Ave, Howard
Street, and St. Paul St Intersection
TECHNICAL PROPOSAL
Development of the alternatives will begin with the initial public outreach. The first true public meeting
will coincide with a site access tour, where participants will be asked to walk, pedal, roll, ride, and wheel
through the project area. Afterwards, we will convene on site and describe how we experienced the
environment, at which point we will hand sketch possible improvements based on the feedback
received. The issues identified and the initial alternatives developed by the group at this public work
session will be documented for further evaluation.
Several initial alternative concepts have been explored:
Bulbout at northwest corner of St Paul and Howard
The large radius at the northwest corner of St Paul and
Howard Street is an obvious hindrance to pedestrian travel
through the intersection. Trucks could be prohibited from
turning southbound right, and a bulbout could be designed to
allow travel lanes and bicycle lanes with a reduced curb radius
(shown at 15-feet at right). A bulbout so designed could
reduce the pedestrian crossing distance to 50-feet; this
distance could be further reduced by realigning the crosswalk
to be perpendicular to the travel lanes.
The reclaimed asphalt surface could become public space like
a pocket park, or patio space for the adjacent retail and
restaurants.
Realignment of Winooski Avenue
By realigning South Winooski Avenue to intersect St Paul Street at a more perpendicular angle would
address several issues:
A pedestrian connection could be constructed more easily between the east and west sides of
South Winooski Avenue at the realigned intersection with St Paul Street.
The traffic signals could be carefully coordinated to reduce the number of signal phases,
improving vehicle congestion even with pedestrian phases.
There is approximately 8-feet of grade difference between St Paul Street and Winooski Avenue, and
additional preliminary planning and conceptual design would be required to evaluate the potential of
this alternative.
City of Burlington
Scoping Study: South Winooski Ave, Howard
Street, and St. Paul St Intersection
TECHNICAL PROPOSAL
We Know the Study Area. RSG staff live and work in the City of Burlington. We walk, ride,
roll, and cycle these streets. Our team has worked on numerous projects within Burlington for
the City and for the Chittenden County Regional Planning Commission, and are knowledgeable
of local concerns.
We Understand the Importance of Stakeholder Support. RSG staff appreciate that the
solution is only as good as how well it is understood. From the significant time spent in the
community for the Cliff Street sidewalk project to the extensive engagement and option
analysis for the Railyard Enterprise Project our team realizes this will be an important aspect
for this project. Our final deliverable will include a visually appealing, two-page fact sheet
that distills the entire project into an approachable and understandable summary, which can be
used by stakeholders moving forward.
RSG is a 100% employee-owned (ESOP) company and has been honored with several national
workplace excellence awards. RSG is headquartered in White River Junction, Vermont, and has
additional offices in Burlington, Vermont; Arlington, Virginia; Evansville, Indiana; Chicago, Illinois; Salt
Lake City, Utah; Portland, Oregon; St. Augustine, Florida; and San Diego, California.
2.0
PROJECT APPROACH
All of the tasks identified in the RFP scope of work issued August 5, 2016 are herein incorporated into
our proposed scope of work. The following task-based scope of work is intended to supplement the
RFP and illustrate a streamlined effort, combining activities when appropriate.
RSG reviewed the ECOS GIS data to better understand languages and other possible barriers for
communicating with the general public.
City of Burlington
Scoping Study: South Winooski Ave, Howard
Street, and St. Paul St Intersection
TECHNICAL PROPOSAL
these utilities, including the appropriate City Public Works staff will be contacted for the approximate
location of their infrastructure.
DELIVERABLES
Base maps of parcels, natural resources, land use, and pedestrian desire paths
Field conditions from topographic survey and turning movement count
Archaeological Resources Assessment / Historic Structures Review
City of Burlington
Scoping Study: South Winooski Ave, Howard
Street, and St. Paul St Intersection
TECHNICAL PROPOSAL
develop an Alternatives Matrix using the standard VTrans format, tailored to this specific site and City
and neighborhood issues. For each alternative, the matrix will contain information concerning the basic
facility information (e.g., length, typical width, etc.), impacts assessed (including ROW issues, utility
conflicts, and natural and cultural resource constraints), an estimated cost, and required permits.
DELIVERABLES
Maps showing general site features, proposed facilities, and constraints
Alternatives Matrix describing impacts, estimated cost, and required permits
10
11
City of Burlington
Scoping Study: South Winooski Ave, Howard
Street, and St. Paul St Intersection
TECHNICAL PROPOSAL
Cost/
Task
14
16
$1,708
$2,240
4
20
8
22
$777
$1,768
12
18
38
16
10
30
6
$1,652
$3,840
$1,191
$966
$3,080
$537
Project Engineer
Project Analyst
6
16
POB Surveying
Hours/
Task
Project Manager
Land Surveyor
4
2
2
2
16
6
6
6
8
6
24
16
$2,584
$1,716
Develop Alternatives
Identify Impacts
Develop Evaluation Matrix
2
2
2
8
6
2
20
12
4
30
20
8
$2,727
$1,892
$817
Public Meeting
Preferred Option
4
2
16
4
20
6
$1,751
$578
Comprehensive Costs
Implementation / Funding Sources / Time Line
2
2
12
12
14
22
$1,133
$2,253
8
2
4
2
2
2
20
8
$2,848
$1,115
$560
$668
78
52
188
30
12
4
6
Total Hrs
390
12
Hartgen
Historian /
Archaeologist
36
28
28
36
Aug
Sept
2016
Oct
Nov
Dec
Jan
Feb
Mar
2017
Apr
May
Jun
Jul
13
3.0
COREY MACK, PE, will serve as Senior Project Engineer for this project. Corey supports
RSGs traffic operations, transportation planning, and engineering design practices. Corey excels at
analyzing, designing, permitting, and constructing transportation facilities, from freeways and
highways to bike paths and sidewalks, and from project initiation and grant applications through final
design and construction administration. He previously managed and conducted the analysis of all
crosswalks within Stowes Village Center as part of a project that evaluated crosswalk locations for
safety and reasonableness within the overall pedestrian network. Corey enjoys working with
communities to identify their challenges, inform discussion, and develop tailored solutions through
public engagement. He is proficient in computer modeling, assembling conceptual plans, and
preparing construction documents, and he excels at guiding public conversations through the
transportation decision process.
ROXANNE MEUSE, EIT, will serve as Project Engineer for this project. Roxanne supports
RSGs traffic operations, transportation planning, and engineering design practices. She has designed
and drafted a new left-turn lane leading to the future Alchemist Brewery in Stowe, Vermont. Her skills
include drafting in AutoCAD and MicroStation; analyzing data using Excel and GIS; writing reports
and technical memos; and preparing cost estimates. She is particularly adept at bridging the gap
between engineering and public engagement, using written and visual forms of communication to
make technical principles and designs accessible to everyone.
15
City of Burlington
Scoping Study: South Winooski Ave,
Howard Street, and St. Paul St Intersection
TECHNICAL PROPOSAL
In addition to these local planning successes, RSG has extensive experience completing Intersection
Scoping and Bicycle and Pedestrian projects. We have included detailed summaries of a few projects
shown on the map below.
to arrive at publicly endorsed, bicycle use corridors prioritized across the state. Extensive public
comment has been collected during this phase, including three statewide meetings recorded and
broadcast to 13 locations and input from over 2,000 users of a crowd-sourced online map. Phase II
will identify critical gaps in the top-tier bicycle corridors. Phase III will identify specific improvements
(e.g., signage, striping, widening, etc.) to address the identified gaps in the top-tier bicycle corridors.
The scope and schedule of the second and third phases will be based on the findings and outcome of
Phase I.
REFERENCE
Sommer Bucossi, summer.bucossi@state.vt.us, (802) 828-3884
City of Burlington
Scoping Study: South Winooski Ave,
Howard Street, and St. Paul St Intersection
TECHNICAL PROPOSAL
intersection, and a preferred alternative was selected that weighed costs with Right-of-Way impacts,
safety concerns, traffic congestion, and community streetscape character. The Full Hourglass
Alternative with two realigned approaches to US-7 was selected and is moving forward into design
with contributions from the Vermont Agency of Transportation and Town of Milton.
REFERENCE
Jason Charest, jcharest@ccrpcvt.org, (802) 846-4490
18
With input from local, regional, state and federal stakeholders, RSG developed a transportation plan
based on reasonable and likely growth scenarios. These improvements included consideration for
expanded highway infrastructure, transit, and bicycle and pedestrian facilities. The resulting
recommendations required significant expansion to the Exit 16 diamond interchange, including
replacement of the existing bridge. In an
effort to minimize costs, an innovative
interchange design, the Double Crossover
Diamond (DCD), was presented for further
analysis. This alternative, which included
provisions for pedestrian and bicycle access
through the interchange, was selected as the
preferred alternative by the Town and State
stakeholders and is currently under design by
the Vermont Agency of Transportation.
REFERENCE
Eleni Churchill, echurchill@ccrpcvt.org, (802) 846-4490
19
City of Burlington
Scoping Study: South Winooski Ave,
Howard Street, and St. Paul St Intersection
TECHNICAL PROPOSAL
20
4.0
RESUMES
21
JONATHAN SLASON, PE
Senior Engineer
Jonathan Slason, PE, focuses on our connections with our built environment through the ways we plan for,
design, and continue to maintain and fund our infrastructure. Jonathans education in economics and civil
engineering combine to enable him to take the conceptual and translate that into tangible action. He
supports RSGs traffic operations, transportation planning, and engineering design practices bringing over
ten years of consulting experience analyzing, designing, permitting and constructing transportation facilities.
EXPERIENCE
10 years
EDUCATION
residential development in the north end of Burlington. The study reviews site access,
mobility within the site, parking needs, and assesses site impacts on the adjacent
street network. (2016)
New Lynn Transit Oriented Design, Auckland, NZ. Transportation engineer
responsible for roadway streetscape, sidewalk, signage, traffic signals, and overall
access to the major transit oriented redevelopment of the New Lynn around the
improved light rail and bus station. Work included weekly design meetings with project
team, complex array of construction related traffic management signals and temporary
configurations, and facilitating stakeholder engagement between the regional Traffic
SCOPE OF SKILLS
Management Unit (TMU), former Waitakere City Council, Auckland Transport, and the
Traffic Operations
I-89 Exit 20 Financing Plan, St. Albans, VT. Lead analyst for assessing the capacity
Traffic Design
Multi-Modal Planning
of St. Albans, Vermont. The innovative project assessed a range of revenue sources
Transportation Economics
Project tasks included: Growth projections and patterns for local property grand list;
Forecasts on growth rates based on longer-term historical trends; Sensitivity tests for
low and high projections; Assess implications of the statewide education taxes on local
financing ability; Develop revenue projections for Local Option Sales Tax, Tax
Incremental Financing Districts, Special Assessment Districts, and Revenue bonding
capacity. (2007)
Jonathan.Slason@rsginc.com
JONATHAN SLASON, PE
Senior Engineer
Severance Corners Transportation Plan, Colchester, VT. Managed and led a technical assistance
project assessing potential capacity improvements at the center of a proposed Statewide Growth Center
in Colchester, Vermont. The project included developing future intersection traffic demand for 2018 (10
year) and evaluated what capacity improvements would be necessary to maintain safe and efficient
transportation operations. Project tasks included: future growth projections; microsimulation and traffic
operational modeling; and establishing project priorities for inclusion into the towns capital improvement
plans. (2007-2008)
Biddeford Downtown Mill Redevelopment, Biddeford, Maine. Lead transportation planner and
engineer looking creatively at an entire downtown redevelopment and revitalization. Technical tasks
included safety assessments, existing vehicle, pedestrian, and biking demand, and future visioning with
planners on how and where development would occur. Transportation considerations included
formation of a transportation management association, parking demands, and access to the I-95
freeway corridor. (2007-2009)
Federal Street Corridor Study Update, St. Albans City, Vermont. Lead transportation engineer for
an assessment of traffic operations, safety, and mobility through the Federal Street corridor. The
analysis reviewed the entire length, with key considerations around the southern terminus, the Lake
Street intersection, and the northern extension. Central to the project was a development of future
potential and transportation access need for changes in zoning, land use, and multi-modal needs. The
project developed recommendations to change functional classification and street status to better align
with existing use and federal funding objectives. (2005-2006)
Khyber Pass Corridor Management Plan, Auckland Transport, Auckland, NZ. Lead transportation
engineer responsible for the transport analysis, planning, concept development, and presentation within
the corridor management plan within Auckland, New Zealand. The work included a review of existing
issues, future identified issues, and developing practical yet progressive solutions to management the
future growth and land use intensification along the corridor. Presented and facilitated workshops for a
technical stakeholder audience to develop a shared understanding of issues and opportunities; and
Develop concept layouts for the roadway configuration, intersection layouts, and bus priority measures
along the corridor. (2012)*
Albany Highway Scheme Assessment (2011-2012), Auckland, NZ. Transportation engineer
responsible for developing traffic and transport options for the Scheme Assessment of the 3.4km
section of the Albany Highway in Albany, Auckland, New Zealand. The scheme was focused on
developing a consistent and context sensitive design for the project corridor. The traffic and transport
assessment was included in the wider study assessing geotechnical, roadway geometrics, services,
and urban design. The objectives were to create a complete street, accommodate all modes, provide
bus priority measures, and allow for future growth in transport demands. (2011-2012)*
*Projects performed prior to joining RSG
COREY MACK, PE
Consultant
Corey Mack, PE, supports RSGs traffic operations, transportation planning, and engineering design
practices. Corey excels at analyzing, designing, permitting, and constructing transportation facilities, from
freeways and highways to bike paths and sidewalks, and from project initiation and grant applications
through final design and construction administration. He enjoys working with communities to identify their
challenges, inform discussion, and develop right-sized solutions through public engagement. While
proficient in computer modeling, assembling conceptual plans, and preparing construction documents,
Corey finds real excitement in guiding public conversations through the transportation decision process.
EXPERIENCE
PROJECT EXPERIENCE
10 years
EDUCATION
BEng, Civil, McGill University
(2005)
Corey.Mack@rsginc.com
COREY MACK, PE
Consultant
Construction to begin in the spring of 2014. (20132014)
Kennedy Pond Safe Routes to School Project (STP SRIN (16)), Vermont. Developed conceptual
and final design plans for the reconstruction of a sidewalk adjacent to the Kennedy Pond Recreation
Area in Windsor, Vermont. The preferred sidewalk alignment will impact the access drive to the
Kennedy Pond Recreation Area; the resulting project elements include realignment of the access drive,
a new vehicle control gate, guardrail, and a geosynthetic slope reinforcement system. The project was
constructed in the spring and fall of 2015. (20132015)
Market Street Gateway Project, Portsmouth, NH: Project Engineer for Roadway and Streetscape
Improvements from I-95 Exit 7 to Russell Street leading into the downtown of Portsmouth. The project
includes evaluating complete street elements, widening sidewalks adding bike lanes, enhanced bus
stops and pull-offs, improving drainage, and creating a gateway to the downtown. Integrated several
park enhancements along the Piscataqua River and coordinated design elements of the roadway and
streetscape corridor into the Sarah Long Bridge Reconstruction Project along US Route 1. Construction
is expected in Spring 2016. (2013-2015)
Transportation System Planning & Implementation, Mount Rainier Nation Park, WA: Project
Engineer for the planning, analysis, and design of changes to the National Parks parking and shuttle
transportation services. Designs included transit connections of regional bus and accommodation of
national tour busses, while being sensitive to the natural beauty and historical context of the site.
(2014)Burlington Wayfinding Improvements, Burlington, Vermont. Project Engineer for
improvements to city signing, wayfinding, and information display. Assisted with team memberLandworks. (2015)
Putney Village Sidewalk Design and Construction Support STP EH08(5), Vermont. Led the design,
permitting, and bidding services of a sidewalk redevelopment project in a village center setting. Project
included the coordination of a state Agency of Transportation paving project to realign the center of the
road to accommodate additional on-street parallel parking. Enhancements included improved
stormwater drainage, new granite curb, and nearly one-half mile of new concrete sidewalk. No utilities
were relocated, designing the sidewalk and curbing around the existing water, sewer, and storm
collection systems. Utilizing most of the available highway right-of-way, temporary construction
easements were sought and acquired from 10 adjacent landowners. Construction was completed in the
fall of 2012. (2010-2012)
Williston Road Complete Streets Pilot Study and Implementation Plan. Assisted with the analysis
of a road diet along US-2 / Williston Road, reducing the through travel lanes from two in each direction
to one. Coordinated striping plans as a change order to a Vermont Agency of Transportation paving
project underway along the corridor. Prepared final sign and striping plans, quantities, and estimated
costs in support of the construction change order. Striping was implemented as a temporary pilot study,
with final striping closely resembling the original intent. (2012)
Taylor Park Pervious Walkway (STP EH 09009), Saint Albans, Vermont. Managed the definition and
design of a linear segment of porous concrete sidewalk in a historic urban park in Saint Albans,
Vermont. Assisted community outreach, presented alternative pervious material designs at public
meetings, and supported the Categorical Exclusion environmental documentation. Project features
included underdrain infrastructure, crosswalk striping and signs, an accessible ramp, and a pervious
walkway medium. Construction was completed in the summer of 2011. (2011)
College Street Waterfront Access Project (STP 5000(17) C-3), Burlington, Vermont. Provided
construction engineering, inspection, and coordination services for this high-visibility streetscaping
enhancement and pedestrian mobility project in Burlington, Vermont. Project included steel sheet pile
walls, an information booth, public restrooms, a raingarden, pervious parking lot, intersection
improvements, and the replacement of two steel truss pedestrian bridges and the boathouse dock
decking. (20092010)
Jericho Sidewalk, Streetscape, and Traffic Calming Design (STP 030-1(19)), Jericho, Vermont.
Designed and coordinated streetscaping and sidewalk enhancements along VT Route 15, including
curbing, retaining walls, drainage improvements, lighting, crosswalks, and signage. Conducted speed
study to determine if additional traffic calming measures are warranted near Jericho Elementary School.
Final results included design plans, construction documents, and construction engineering services.
(20092010)
VT-30 Cornwall Pedestrian Shoulder Access Project (STP EH 08(13)), Cornwall, Vermont.
Designed the widening of a two-lane state highway rural arterial. Coordinated project goals with VTrans
and expanded from limited widening in contained areas to incorporation into a full-depth reclamation
project along the entire corridor at little additional cost to the municipality. Construction was completed
in the fall of 2010. (20092010)
Severance Corners Intersection Design, Colchester, Vermont. Designed and analyzed geometric
layouts for a congested intersection along US Route 7 in Colchester, Vermont. The designs included
signalized and roundabout alternatives, including approach geometries. Right-of-way constraints, a
high-crash-location designation, and heavy directional volumes increased the challenges associated
with this project. The result included preliminary engineering plans and cost estimate. (2009)
Transportation and Pedestrian Planning
Bicycle and Pedestrian Working Group Liaison, NYS Association of Metropolitan Planning
Organizations. Provided primary support to the statewide organization discussing bicycle and
pedestrian planning and design topics relating to federal, state, and local regulations. Regularly updated
the group regarding transportation funding bills, local and statewide legislation relating to bicycle and
pedestrian facilities including complete streets laws, MUTCD compliance, and the latest reports and
studies affecting active transportation. Coordinated efforts between regional planing groups and the
NYS Department of Transportation. (2013-ongoing)
Killington Road Walkway Scoping Report, Killington, Vermont. Managed and led the development
of a scoping report to identify the preferred alignment for a walkway to connect the existing town
walkway to the planned resort development, including coordination between the Town of Killington,
Killington Ski Resort, and a real estate company managing the site development. Walkway alignments
were complicated by steep mountainous terrain, adjacent wetlands, wildlife corridors, and an impaired
waterway. A preferred alignment was selected by the Town for future construction. (2014-2015)
COREY MACK, PE
Consultant
Milton US-7 / Middle Road / Railroad Street Intersection Scoping Report, Vermont. Managed and
led the development of a scoping report to address congestion and safety concerns at this complex
uncontrolled intersection in Milton, Vermont. After documenting the existing conditions along the
corridor and multiple nearby intersections, a set of intersection alternatives was developed that included
signalization, roundabout analysis, and the development of a grid network to help distribute traffic,
remove approach skew angles, and consolidate traffic intersections. The proposed alternatives were
analyzed for impacts, presented to the Selectboard and Agency of Transportation, and a final
alternative and recommendation was developed and accepted by the Town in 2013. (20122013)
Underhill Sidewalk Scoping Report Update, Vermont. Due to changing existing conditions and an
uncertain environment, the 2007 original Underhill Sidewalk Scoping Study was shelved for a later date.
Picking up from a previous consultants report, a scoping study with updated existing conditions and a
reanalysis of alternatives. The recommended preferred alternative was developed and approved by the
Selectboard, and the phased implementation plan was utilized by the Town to seek grant funding for
construction. The Town was awarded construction funding in the 2013 round of Agency of
Transportation Bicycle and Pedestrian Grant Program, with conceptual design expected to begin in
2014. (2013)
Old Hollow Road Traffic Calming Feasibility Study, Vermont. In cooperation with the Old Hollow
Neighborhood, the Town of Ferrisburgh and the Addison County Regional Planning Commission, the
existing traffic characteristics and development patterns were documented to analyze appropriate traffic
calming measures to implement along the corridor. The undesirable speed, noise, and safety concerns
of the community were documented and a set of immediately implementable, low impact, and context
sensitive solutions were presented to the Selectboard for consideration (2013).
Georgia South Village Bicycle and Pedestrian Feasibility Study, Georgia, Vermont. Developed
alternative sidewalk alignments along existing infrastructure and developed design standards for future
bicycle and pedestrian amenities in a rapidly growing village in Vermont. Evaluated existing conditions
and safety hazards, identified permitting requirements and impacts on environmental and cultural
resources, presented alternatives at public meetings, and identified a preferred alternative. (20112012)
Bristol to Rockydale Bicycle and Pedestrian Feasibility Study, Bristol, Vermont. Managed and
prepared a study of the existing bicycle and pedestrian facilities serving the corridor between Bristol
Village, Rockydale, and Bartlett Falls. The study area followed VT Route 17 along the New Haven River
through a steep mountain valley. Alternatives were developed that included on-road bicycle facilities,
sidewalks adjacent to the roadway, an off-road path that followed logging trails, and a new path through
the Bristol Cliffs Wilderness Area in the Green Mountain National Forest. The project also included
organization and presentation at several public meetings resulting in a final Feasibility Study with
documentation of the existing conditions, alternatives analysis, a preferred alternative, permitting
requirements, phasing plan, cost estimates, and implementation recommendations. (2011)
Stowe Crosswalk Evaluation, Stowe, Vermont. Managed and conducted the analysis of all
crosswalks within the Village Center of this vibrant community and busy tourist destination. Existing
crosswalk locations were evaluated for safety and reasonableness within the pedestrian network.
Various improvements to the location of the crosswalks were recommended and included a discussion
on the resulting impact to street parking. Results of the analysis were presented to the Stowe Vibrancy
Committee. Recommended improvements have been implemented at the School Street and Pleasant
Street intersection. (2010)
Exit 17 Growth Center Reanalysis, Vermont. Updated the Growth Center development traffic patterns
due to changes in the circulation network between Transportation Analysis Zones. The traffic model and
associated impacts were updated and revised, resulting in an updated traffic analysis on the State
Highway. (2010)
Roxanne Meuse, EIT, supports RSGs transportation planning, traffic operations, and engineering design
practices. Her skills include drafting in AutoCAD and MicroStation; analyzing data with Excel and GIS;
writing reports and technical memos; and creating visuals for reports and presentations. She is particularly
adept at bridging the gap between engineering and public engagement, using written and visual forms of
communication to make technical principles and designs accessible to everyone.
EXPERIENCE
PROJECT EXPERIENCE
1.5 years
EDUCATION
supporting citizen engagement to ensure all roadway projects account for local desire
for bicycle and pedestrian facilities. The guide is visually engaging and user-accessible.
It walks advocates through the planning and design process and explains basic
transportation designs and concepts to support particular active transportation needs.
(2015-2016)
Putney Village Sidewalk Landmark College Connection, Putney, VT. Prepared
right-of-way plans in MicroStation and prepared the cost estimate for this sidewalk
construction project. The sidewalk will connect the Village of Putney to Landmark
College. Enhancements included improved stormwater drainage, new granite curb, a
steep reinforced rock slope and new concrete headwall, and nearly one-half mile of new
concrete sidewalk. Construction is expected to begin in the summer of 2016. (2015-16)
Railroad Enterprise Project, Burlington, VT. Drafted seven alternatives for a new
network of Complete Streets in the South End of Burlington, Vermont. Determined each
alternatives impact to environmental resources and properties using GIS and AutoCAD.
Assisted with the creation and evolution of an evaluation matrix. Focused on making the
matrix and plots visually appealing and understandable for the public audience. This
project will create a route between Pine Street and Battery Street to bypass
neighborhoods that are currently congested with traffic traveling between these
locations. (2015-2016)
Essex Junction Station Scoping, VT. Designed and drafted alternatives for the
circulation and streetscaping around the Essex Junction train station, based on needs
Roxanne.Meuse@rsginc.com
Enhancements to EERPAT: Energy and Emissions Reductions Policy Analysis Tool. Researched
the EPAs recently approved Clean Power Plan and how it will affect EERPAT, a greenhouse gas policy
modeling tool created by RSG that is being piloted in several states. Wrote a technical memo
summarizing key findings and recommending a methodology for updating the model. (2015)
Worcester Energy Data and Marketing Internship, Worcester, MA. Assisted with the administration
of a rebate pilot program that the City offered residents for energy efficiency upgrades. Performed data
analysis and created simple visualizations of utility consumption and survey responses for use in the
Citys reporting and for marketing purposes. Contributed written content about the Citys sustainability
accomplishments for Worcester Energys website. (2015)*
*Work performed before joining RSG.
City of Burlington
Scoping Study: South Winooski Ave,
Howard Street, and St. Paul St Intersection
5.0
22
TECHNICAL PROPOSAL
Quechee Village
Prepared For:
55 Railroad Row
White River Junction, VT 05001
802-295-4999
www.rsginc.com
Town of Hartford
Submitted by:
Town of Hartford
Contents
1.0
1.1
1.2
Introduction 1
Methodology...................................................................1
Report Layout.................................................................2
2.0
2.1
2.2
2.3
2.4
2.5
2.6
2.7
Existing Conditions
5
Zoning Districts...............................................................7
Traffic Volumes & Roadway Context..............................9
Safety............................................................................14
Trail Network.................................................................16
Natural and Environmental Resources.......................... 17
Hazardous Materials Sites............................................20
Archeological Sites........................................................21
3.0
3.1
3.2
4.0
4.1
4.2
4.3
4.4
4.5
4.6
Alternatives 25
West Village...................................................................25
Central Village...............................................................32
East Village....................................................................41
US 4...............................................................................47
South Village.................................................................52
Impacts and Issues.......................................................55
4.7
4.8
5.0
5.1
5.2
5.3
5.4
Implementation 79
Phasing Strategy...........................................................79
Procedures....................................................................80
Cost Estimates..............................................................80
Funding Sources...........................................................80
iii
Note: Sections 1, 2, 3 and Appendices have been removed for insertion as a work sample.
Alternatives
Alternatives
To address the purpose and needs of the project area, the
following section describes the alternatives studied for each
of the five village segments in the project area. Each segment contains two action alternatives in addition to a no
build or no change option for comparison.
The division into five segments makes it easier to focus the
discussion on specific areas and ensures the possibility of
phasing and combining the ideas to create the most appropriate set of recommendations for the overall Quechee project area. The preferred package of solutions in the Quechee
Village study area may ultimately include a mix of elements
from several alternatives.
West Village
25
Alternative 1 seeks to make the interactions between motorists and non-motorized roadway users safer. Share the Road
plaques (MUTCD W16-1) placed below the standard bicycle
sign (MUTCD W11-1) are proposed at key points in the corridor to enhance the visibility of bicyclists.
Share the Road signage alerts passing motorists that bicyclists
are using the roadway, and reinforces the fact that bicyclists
have a legal right to use the public right-of-way (ROW). Signs
should be installed at least 50 feet, preferably further, prior to
the condition that warrants the additional alert to drivers. In
this focus area, two share the road signs should be installed,
one 50 feet to the west of the intersection of Quechee Main
Street and Quechee West Hartford Road, and the other 50
feet past the northernmost Quechee Clubhouse driveway (Figure 4.1).1 Existing bike route signs should also be removed.
Figure 4.1: Share the Road Sign
26
April 2015
Alternatives
Figure 4.4: West Village Alternative 1
27
28
April 2015
Alternatives
29
30
April 2015
Alternatives
31
Central Village
32
April 2015
Alternatives
Bicycle Facilities
The travel lanes would remain 11 feet, with two-foot shoulders where there are proposed granite curbed sidewalks. The
13 centerline to curb width allows for town snow plows to be
able to clear the travel lanes effectively. Catch basins would be
added to the new sidewalks and feed into the existing closed
drainage system along Main Street and Waterman Hill Road.
33
34
April 2015
Alternatives
35
36
April 2015
Alternatives
Across from the Parker Inn, the sidewalk would follow the
alignment of the existing path, widening to five feet west of
the pedestrian crossing to accommodate ADA accessibility. The existing walkway in front of the antique store would
remain, as would the three on-street parking spaces in front
of it. The plan proposes carrying the concrete sidewalk across
the churchs front lot, but allowing for the surface to be
mountable by cars.
Bicycle Facilities
Roadway
The travel lanes would remain 11 feet, with two-foot shoulders where there are proposed granite curbed sidewalks. Catch
basins would be added to the new sidewalks and feed into the
existing closed drainage system along Main Street and Waterman Hill Road.
37
38
April 2015
Alternatives
39
5
Alternative Considered and Dismissed
A third alternative that was considered was an off-road alignment through the public lands along the Ottauquechee River
and crossing through the Village Green, connecting from the
playground to the Quechee Library and the Post Office, as
well as extending on the river side to Simon Pearce. In meeting with representatives of Simon Pearce, the team learned
that the proposed path along the river would traverse land
40
April 2015
26
owned by multiple property owners, including the Parker Inn.
In addition, there are drainage and topographic issues in connecting between the Post Office and the Public Library. While
this off-road alternative may be revisited in a future phase, it
was dismissed from further analysis in this bike and pedestrian
scoping study due to the lack of substantial change to the
greater Quechee bike and pedestrian network, as well as challenges associated with necessary easement acquisition.
Alternatives
East Village
The Quechee East Village focus area extends from the Polo
fields to the west and to the covered bridge in Quechee Central Village to the east. The primary road running through the
focus area is Quechee Main Street, which connects points east
to Quechees Central Village. There are no sidewalks and only
intermittent sections of fog-line striping along the side of the
road. The roads posted speed limit is 35 mph. The Ottauquechee Trail extends through the study area from the polo
field/corn field in the east to the covered bridge to the west.
Improvements in this section are focused on improving the
trail and making stronger connections to the Central Village.
For this section, trail surface improvements are recommended
and enhanced signage and crossings are proposed, as well as
the creation of formalized trailheads. Alternative 1 can be
implemented in the short term, while Alternative 2 is a longer
range plan that will help to ensure safe interactions between
motorists and Ottauquechee trail users, and a more enjoyable
trail user experience.
East Village No Build
41
42
April 2015
Alternatives
to the Quechee Covered Bridge to help make a safer connection to the top of the hill. In the short term, it is acceptable if
the switch back remains a natural surface.
At the western terminus of the trail, a formalized trailhead
should be created, complete with motorist and bicycle parking, orientation map signage, trail maps, and trash receptacles.
43
44
April 2015
Alternatives
45
46
April 2015
Alternatives
US 4
US 4 No Build
The US 4 No Build Alternative would leave the road conditions as they are today, without any facilities for cyclists or
pedestrians. This corridor will continue to be difficult for nonmotorists to traverse through safely given the relatively high
speed of traffic, poor sight distances, and narrow shoulders to
the east of Waterman Hill Road.
47
8 to 9 parallel
parking spaces
Shared Use Path +
Landscaped Buffer
Connect to
existing sidewalk
8 to 9 parallel
parking spaces
8 to 9 parallel
parking spaces
200 400
800
Feet
Connect to
existing sidewalk
48
April 2015
200 400
800
Feet
Alternatives
Figure 4.19: US 4 Alternative 1 Typical Cross Section, Looking West
49
into a 10-foot shared use path that parallels the road alignment, with a 10-foot landscaped buffer between the roadway and the path. In this alternative, the centerline does not
change and the travel lanes remain at 12 feet throughout the
project corridor, with a minimum 3-foot shoulder on both
sides.
5 sidewalk +
10 landscape
d buffer
Maintain existing
parking spaces
50
April 2015
Connect to
existing sidewalk
Alternatives
51
South Village
The Quechee South Village focus area extends from West Gilson Avenue between Quechee/Hartland Road and US 4, and
includes Quechee/Hartland Road and Cross Street between
US 4 and West Gilson Avenue. West Gilson Avenue connects residential areas to US 4 and the Mid Vermont Christian
School. There are no sidewalks and fog-line striping exists
only at the very edge of the roadway on Quechee/Hartland
Road. Due to the rural residential character and relatively low
traffic volume, the two alternatives recommend enhancing the
pedestrian experience by adding a curbed sidewalk, and continuing to serve cyclists on-road in shared lanes. This allows
the roadway to remain narrow and for all improvements to
remain within the public ROW.
South Village No Build
52
April 2015
Alternatives
Figure 4.23: South Village Alternative 1
53
54
April 2015
Alternatives
Table 4.1 through Table 4.5 provide a comparison of the potential impacts and issues associated with each alternative proposed in each of the focus
areas.
Const.
Cost
No Build
Alternative 1
Alternative 2
$0
$16,000
$30,000
3/2/0/0
3 / 2 / 10 / 32
No
No
Street. However, not all cyclists would be Street. However, not all cyclists would be
comfortable sharing a lane with vehicles.
Yes, the presence of bicycle signage and
Traffic Calming
No
impacts
Agricultural Lands
No
No
No
Archaeological
No
No
No
Historic Structures/Sites
No
No
No
Floodplain
No
No
No
No
No
No
Public Lands
No
No
No
Utilities
No
No
No
Wetlands
No
No
No
55
permits
No Build
Alternative 1
Alternative 2
Act 250
No
No
No
No
No
No
No
No
No
Stream Alteration
No
No
No
No
No
No
No
No
No
Shoreland Encroachment
No
No
No
No
No
No
No
No
No
No
No
No
NEPA Category
No
No
No
No Build
Alternative 1
Alternative 2
$0
$1,397,000
$936,000
2,317 LF / 5 ft
2,177 LF / 5 ft
Surface
Bituminous Concrete
Bituminous Concrete
6 / 4 / 2 / 32
4 / 4 / 2 / 32
6/9
7/9
425 ft
180 ft
Construction
Cost
56
April 2015
Alternatives
No Build
No
Alternative 2
Yes - Pedestrians would have a de-
Street.
would be comfortable sharing a lane with would be comfortable sharing a lane with
Traffic Calming
impacts
No
Alternative 1
Yes - Pedestrians would have a delin-
No
vehicles.
vehicles.
vehicle speeds.
vehicle speeds.
Agricultural Lands
No
No
No
Archaeological
No
Potential
Potential
Historic Structures/Sites
No
Floodplain
No
No
No
proposed developments
proposed developments
No
Public Lands
No
No
No
Utilities
No
Yes 10 poles
Yes 2 poles
Wetlands
No
No
No
57
permits
No Build
Alternative 1
Alternative 2
Act 250
No
No
No
No
No
No
No
No
No
Stream Alteration
No
No
No
No
No
No
No
No
No
Shoreland Encroachment
No
No
No
No
No
No
No
No
No
No
NEPA Category
No
No
No
No Build
Alternative 1
Alternative 2
$0
$443,000
$1,279,000
Hardpack Surface
Boardwalk
230 ft
2/3
2/3
0 ft
390 ft
Construction
Cost
58
April 2015
Alternatives
Table 4.3: East Village Comparison Matrix, Continued
permits
impacts
No Build
No
Alternative 1
Alternative 2
and striped pedestrian crossing would be and striped pedestrian crossing would be
No
Traffic Calming
No
No
No
Agricultural Lands
No
No
No
Archaeological
No
Potential
Potential
Historic Structures/Sites
No
No
No
Floodplain
No
No
No
No
No
No
Public Lands
No
No
No
Utilities
No
No
No
Wetlands
No
No
No
Act 250
No
No
No
No
No
No
No
No
No
Stream Alteration
No
No
No
No
No
No
No
No
No
Shoreland Encroachment
No
No
No
No
No
No
No
No
No
No
No
No
NEPA Category
No
No
No
59
tion
Construc-
Cost
No Build
Alternative 1
Alternative 2
$0
$1,880,000
$710,000
650 ft
Surface
Asphalt
Asphalt
1 / 10
2 / 12
512 ft
0 ft
No
between Jakes Quechee Market and the needed at the intersection of Water-
Quechee Gorge.
No
Traffic Calming
60
April 2015
No
Alternatives
permits
impacts
No Build
Alternative 1
Alternative 2
Agricultural Lands
No
No
No
Archaeological
No
Historic Structures/Sites
No
Floodplain
No
No
No
No
No
No
Public Lands
No
No
No
Utilities
No
Wetlands
No
No
No
Act 250
No
No
No
No
No
No
No
No
No
Stream Alteration
No
No
No
No
No
No
No
surface added
surface added
Shoreland Encroachment
No
No
No
No
No
No
No
No
Potential
Potential
NEPA Category
No
No
No
61
tion
Construc-
Cost
No Build
Alternative 1
Alternative 2
$0
$218,000
$216,000
Surface
Bituminous Concrete
Bituminous Concrete
1/8
5/8
None
None
No
No
area.
area.
Yes The presence of a curbed sidewalk
Traffic Calming
No
62
April 2015
Alternatives
impacts
No Build
Alternative 1
Alternative 2
Agricultural Lands
No
No
No
Archaeological
No
No
No
Historic Structures/Sites
No
No
No
Floodplain
No
No
No
No
No
No
Public Lands
No
No
No
Utilities
No
permits
Wetlands
No
Act 250
No
No
No
No
No
No
No
No
No
Stream Alteration
No
No
No
No
No
No
No
No
No
Shoreland Encroachment
No
No
No
No
No
No
No
No
No
No
No
No
NEPA Category
No
No
No
63
64
April 2015
Table
4.6: Alternatives Cost Estimate
Date: 11/26/2014
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
Unit
LS
CY
CY
SY
CY
TON
LF
LF
SY
SY
LF
LF
LF
LF
LF
LF
EA
EA
LF
LF
SF
LF
LF
EA
EA
EA
LS
LS
LS
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
Price
VAR
10.00
15.00
2.50
35.00
135.00
35.00
20.00
70.00
80.00
100.00
300.00
30.00
15.00
15.00
15.00
3,000.00
2,000.00
45.00
15.00
50.00
100.00
1.00
250.00
3,500.00
1,000.00
VAR
8%
10%
WEST VILLAGE
Alternative 1
Alternative 2
Sign Package
Enhanced Signs & Striping
Quantity
Total
Quantity
Total
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
5
2
0
0
0
0
Subtotal
Contingency (25%)
Total Estimated Construction Cost
Engineering (15%)
Permitting (5%)
Resident Engineering + Inspection (10%)
Right of Way (var)
Total Cost for Design & Construction
0%
$
$
$
$
$
$
$
1,250
7,000
660
900
$
$
$
5000
15
2
0
0
0
0
CENTRAL VILLA
Alternative 1
South Side Sidewa
Quantity
Tota
0
$
870
$
8
948
$
14
0
$
383
$
13
188
$
25
1600
$
56
0
$
860
$
60
183
$
14
0
$
0
$
0
$
0
$
0
$
0
$
4
$
12
3
$
6
2250
$ 101
130
$
1
2400
$ 120
100
$
10
1600
$
1
10
$
2
0
$
0
$
5000
$
5
$
36
$
48
$
$
$
$
$
$
$
5,000
3,750
7,000
1,260
1,710
9,900
2,500
12,400
$
$
$
18,800
4,700
23,500
$
$
$
538
134
672
$
$
$
$
1,500
700
1,300
-
$
$
$
$
2,900
1,200
2,400
-
$
$
$
$
80
33
67
6
16,000
30,000
861
0%
1%
Alternatives
Alternative 2
anced Signs & Striping
antity
Total
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
-
000
15
2
0
0
0
0
0%
$
$
$
$
$
$
$
5,000
3,750
7,000
1,260
1,710
$
$
$
18,800
4,700
23,500
$
$
$
538,000
134,500
672,500
$
$
$
$
$
$
$
2,900
1,200
2,400
-
$
$
$
$
80,700
33,700
67,300
6,800
30,000
861,000
1%
2%
$
$
$
$
$
$
$
700
1,000
5,000
22,340
30,160
390,300
97,600
487,900
$
$
$
$
$
$
$
58,600
24,395
48,790
9,800
630,000
2%
700
4
0
0
5000
$
$
$
$
$
$
$
700
1,000
5,000
12,870
17,370
331,800
83,000
414,800
$
$
$
$
$
$
$
49,800
20,800
41,500
8,300
536,000
1%
EAST VILLAGE
Alternative 1
Alternative 2
Natural Trail + Signage
Enhanced Trail + Signage
Quantity
Total
Quantity
Total
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
355
$
35,550
0
$
286
$
85,666
1686
$ 505,675
0
$
2881
$
86,428
0
$
686
$
10,285
1701
$
25,519
204
$
3,065
5863
$
87,938
2269
$
34,033
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
1422
$
71,107
500
26
2
3
500
0
0
$
$
$
$
$
$
$
500
6,500
7,000
3,000
500
20,180
-
191,000
47,800
238,800
$
$
$
$
$
$
$
28,700
11,940
23,880
2,400
306,000
3%
250
29
2
3
500
0
0
$
$
$
$
$
$
$
250
7,250
7,000
3,000
500
58,290
-
272,400
68,100
340,500
$
$
$
786,900
196,800
983,700
$
$
$
$
40,900
17,100
34,100
10,300
$
$
$
$
118,100
49,200
98,400
29,600
443,000
3%
$ 1,279,000
65
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
Unit
LS
CY
CY
SY
CY
TON
LF
LF
SY
SY
LF
LF
LF
LF
LF
LF
EA
EA
LF
LF
SF
LF
LF
EA
EA
EA
LS
LS
LS
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
Price
VAR
10.00
15.00
2.50
35.00
135.00
35.00
20.00
70.00
80.00
100.00
300.00
30.00
15.00
15.00
15.00
3,000.00
2,000.00
45.00
15.00
50.00
100.00
1.00
250.00
3,500.00
1,000.00
VAR
8%
10%
Subtotal
Contingency (25%)
Total Estimated Construction Cost
Engineering (15%)
Permitting (5%)
Resident Engineering + Inspection (10%)
Right of Way (var)
Total Cost for Design & Construction
66
April 2015
0%
$
$
$
$
$
$
$
1,600
1,000
5,000
6,100
8,240
$
$
$
1000
4
0
0
5000
US 4 EA
Alternative
North Side Side
Quantity
0
$
2111
$
0
$
0
$
741
$
986
$
330
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
3
$
0
$
400
$
200
$
6200
$
$
$
$
$
$
$
$
1,000
1,000
5,000
10,100
13,640
90,600
22,700
113,300
$
$
$
150,000
37,500
187,500
$
$
$
$
$
$
$
13,600
5,700
11,400
-
$
$
$
$
22,500
9,375
18,750
-
$
$
$
$
144,000
239,000
0%
2000
4
0
0
10000
0%
$
$
$
$
$
$
$
$ 1
Alternatives
o Jakes)
ternative 2
de Shared Use Path
ty
Total
$
$
6,489
$
$
$
20,819
$
73,913
$
$
$
$
$
$
$
$
$
$
$
9,000
$
$
9,000
$
$
$
$
$
$
$
$
$
1,000
1,000
5,000
10,100
13,640
$
$
$
$
$
$
$
$
$
$
2,000
1,000
10,000
43,580
58,840
150,000
37,500
187,500
$
$
$
$
$
$
$
22,500
9,375
18,750
-
$
$
$
$
239,000
0%
$
$
$
$
$
$
$
2,000
1,000
10,000
24,000
32,400
647,200
161,800
809,000
$
$
$
97,100
40,500
80,900
-
$ 1,028,000
2000
4
0
0
10000
0%
SOUTH VILLAGE
Alternative 1
Alternative 2
North Side Sidewalk
South Side Sidewalk
Quantity
Total
Quantity
Total
0
$
0
$
1074
$
10,741
1074
$
10,741
0
$
0
$
0
$
0
$
537
$
18,796
537
$
18,796
544
$
73,406
544
$
73,406
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
200
$
3,000
150
$
2,250
0
$
0
$
500
4
0
0
5000
$
$
$
$
$
$
$
500
1,000
5,000
9,000
12,150
356,400
89,100
445,500
$
$
$
$
$
$
$
53,500
22,275
44,550
-
566,000
3%
500
4
0
0
5000
$
$
$
$
$
$
$
500
1,000
5,000
8,940
12,070
133,600
33,400
167,000
$
$
$
132,800
33,200
166,000
$
$
$
$
20,100
8,400
16,700
5,100
$
$
$
$
20,000
8,300
16,600
5,000
218,000
216,000
3%
67
Preferred Alternative
68
April 2015
West Village
Alternatives
Figure 4.25: West VillagePreferred Alternative
69
Central Village
A modified version of Alternative 1 is the preferred alternative for Central Village, with sidewalks along the south side of Quechee Main
Street and west side of Waterman Hill Road.
The sidewalk on the south side was preferable
over the north side because many community
members, as well as the steering committee
members, felt that the south side had more activities and that the north side was perceived to
have wider shoulders. The preferred alternative
also extends the sidewalk path to the Coldwell
Banker location to hold for future potential
connections to the Quechee Green Park. On
Waterman Hill Road, the sidewalk connects
from the existing path along the covered bridge
to the intersection with US 4. The preferred
alternative also proposes to remove the planted
island at River Street and instead, T the
intersection in order to create more landscaped
space on the corners and reduce the pedestrian crossing distance. To reduce the burden
of maintenance, the steering committee also
agreed to remove shared lane pavement markings in the preferred alternative.
70
April 2015
Alternatives
71
East Village
A modified version of Alternative 1 is the preferred alternative for East Village. Community
members, as well as the steering committee,
preferred to keep the trail simple and low cost,
while adding key amenities such as signage and
bicycle racks at trailhead locations. Many public
meeting participants and the steering committee members felt that the main priorities were
to widen the narrowest portions of the existing
trail and to add a boardwalk over the marsh
areas. The preferred alternative also proposes
shifting the crossing at Deweys Mills to the east
side of the road, reducing the number of road
crossings. Participants also felt that there was
no need to include flashing pedestrian crossing
lights in this location.
72
April 2015
Alternatives
73
US 4
74
April 2015
Alternatives
75
South Village
Alternative 1 is the preferred alternative for South Village, with a sidewalk proposed on the north side of West Gilson Road
and west side of Quechee-Hartland Road. While most residents who participated at the public meeting and online felt that this
segment was the lowest in priority, the recommendation for sidewalks is in place for potential development that may help the
Town direct future developers.
Figure 4.29: South VillagePreferred Alternative
76
April 2015
Alternatives
(Endnotes)
1 Additional guidance on Share the Road signage can be found in Chapter 8.3.1 of the VTrans Pedestrian and Bicycle Facility Planning and Design Manual
2 Additional guidance on Radar Speed Feedback Signs can be found in the VTrans publication Guidelines for the Use of Radar Speed Feedback Signs on the State Highway System
3 Federal Highway Administration. Publication Number: FHWA-RD-98-154, Synthesis of Safety Research Related to Speed and Speed Management. July 1998.
4 Reference for types of RSFSs allowed under the MUTCD: http://www.mutcd.fhwa.dot.gov/resources/interpretations/pdf/2_09_79.pdf
5 Additional guidance on Shared Lane Markings can be found in Section 9C.07 of the 2009 MUTCD
77
Implementation
Implementation
Phasing Strategy
Recognizing that that the Town will not undertake implementation of all the project segments at one time, the Selectboard
approved a prioritization strategy that was recommended by the Steering Committee, with input from the community participants, Town staff, and the consultant team. Central Village and US 4 were further subdivided to distinguish priorities within
those segments, and also to create sections that would be more feasible in applying for state and federal funding grants.
1. Central Village
a. Quechee Main Street: A sidewalk along the south side
of Quechee Main Street.
b. Waterman Hill Road: A sidewalk along the west side
of Waterman Hill Road, connecting from the existing
path on the covered bridge down to the intersection
with US 4.
2. West Village Add signage and a radar feedback sign
on Quechee Main Street between the Quechee Club and
Central Village.
3. US 4
a. Waterman Hill to Jakes Quechee Market: A sidewalk
with landscaped buffer connecting between Jakes
Quechee Market and the sidewalk on the west side of
Waterman Hill Road.
b. Waterman Hill to Quechee Gorge: A sidewalk and
landscaped buffer, with the exception of the parcel
at the northeast corner with Waterman Hill Road,
that connects from Waterman Hill Road to VINS and
ultimately connecting to the existing sidewalk at the
Quechee Gorge bridge.
4. East Village: Trail and signage improvements to the
existing Ottauquechee Trail alignment, as well as added
bicycle racks at key access points to the trail.
5. South Village: A sidewalk along the north side of West
Gilson Road and the west side of Quechee Hartland
Road, connecting to US 4.
79
Procedures
Cost Estimates
The construction cost estimate in Table 5.1 shows an overall order of magnitude estimate of the costs associated with
improvements throughout the project area. The estimate
contains realistic costs, as of 2014, for construction, surveying, engineering, and permitting services where applicable.
With the exception of the Ottaquechee Trail, the recom-
80
April 2015
Funding Sources
Funding for the recommendations may be secured from a variety of sources. Below is a list of various funding sources that
could be used to help with the implementation of the recommended preferred alternatives.
Transportation Alternatives Program (TA Funds): TA
funds can be used to increase bicycle and pedestrian mobility. These funds will cover a maximum of 80 percent of
the project, with a 20 percent match from the Town. TA
funds are distributed every year in Vermont through a
competitive grant program.
Bicycle and Pedestrian Program: These Vermont state
funds cover bicycle and pedestrian improvement projects
specifically and are provided via a competitive grant program. These funds will cover a maximum of 90 percent of
the project, with the remaining portion likely coming from
the project-sponsoring organization.
Town Capital Improvement Plan: The Town could opt to
use funds from its Capital Improvement Plan to undertake
one or several of the phases at once. There may be efficiencies by having a larger portion of a sidewalk constructed at one time.
Developer Mitigation or Impact Fees: As new development projects are built, the Town may impose a mitigation
or impact fee that will help finance capital improvements
needed as a result of added traffic or population growth.
Community Sponsorship or Private Fundraising: The
Town could work to raise private funds for the new
sidewalks or other pedestrian improvements, at least in
part, possibly with some memorial that acknowledges the
contributions.
Implementation
Table
5.1: Overall approximate cost estimate
Project: Quechee Bicycle and Pedestrian Scoping Study
Date: 11/26/2014
WEST VILLAGE
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
Unit
LS
CY
CY
SY
CY
TON
LF
LF
SY
SY
LF
LF
LF
LF
LF
LF
EA
EA
LF
LF
SF
LF
LF
EA
EA
EA
LS
LS
LS
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
Price
VAR
10.00
15.00
2.50
35.00
135.00
35.00
20.00
70.00
80.00
100.00
300.00
30.00
15.00
15.00
15.00
3,000.00
2,000.00
45.00
15.00
50.00
100.00
1.00
250.00
3,500.00
1,000.00
VAR
8%
10%
Sign Package
Quantity
Total
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
5
$
1,250
2
$
7,000
0
$
0
$
0
$
660
0
$
900
Subtotal
Contingency (25%)
Total Estimated Construction Cost
Engineering (15%)
Permitting (5%)
Resident Engineering + Inspection (10%)
Right of Way (var)
Total Cost for Design & Construction
0%
CENTRAL VILLAGE
(Waterman Hill Road)
West Side Sidewalk
Quantity
Total
0
$
870
$
8,696
710
$
10,650
0
$
353
$
12,367
162
$
21,870
710
$
24,850
0
$
361
$
25,278
17
$
1,333
0
$
0
$
0
$
0
$
0
$
0
$
2
$
6,000
1
$
2,000
700
$
31,500
200
$
3,000
2500
$ 125,000
0
$
700
$
700
4
$
1,000
0
$
0
$
5000
$
5,000
$
22,340
$
30,160
EAST VILLAGE
SOUTH VILLAGE
North Side Sidewalk
Quantity
Total
0
$
1074
$
10,741
0
$
0
$
537
$
18,796
544
$
73,406
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
0
$
200
$
3,000
0
$
0
$
500
$
500
4
$
1,000
0
$
0
$
5000
$
5,000
$
9,000
$
12,150
$
$
$
9,900
2,500
12,400
$
$
$
538,000
134,500
672,500
$
$
$
331,800
83,000
414,800
$
$
$
272,400
68,100
340,500
$
$
$
90,600
22,700
113,300
$
$
$
647,200
161,800
809,000
$
$
$
133,600
33,400
167,000
$
$
$
$
1,500
700
1,300
-
$
$
$
$
80,700
33,700
67,300
6,800
$
$
$
$
49,800
20,800
41,500
8,300
$
$
$
$
40,900
17,100
34,100
10,300
$
$
$
$
13,600
5,700
11,400
-
$
$
$
$
97,100
40,500
80,900
-
$
$
$
$
20,100
8,400
16,700
5,100
16,000
861,000
536,000
443,000
144,000
218,000
1%
2%
3%
0%
0%
$ 1,028,000
3%
81
ARLINGTON
VIRGINIA
BURLINGTON
VERMONT
CHICAGO
ILLINOIS
CONCORD
NEW HAMPSHIRE
EVANSVILLE
INDIANA
SAN DIEGO
CALIFORNIA