Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
FOR
Managing Director
Aurangabad Industrial Township Limited
Udyog Sarathi, MIDC office, Marol Industrial Area,
Andheri (East), Mumbai, Maharashtra 400093.
EPC Agreement
Table of Contents
S. No
Page No
PART I
Preliminary
10
12
1.1
Definitions
12
1.2
Interpretation
12
1.3
15
1.4
15
1.5
15
PART II
17
18
2.1
18
19
3.1
19
3.2
21
3.3
21
3.4
Contractors personnel
22
3.5
22
3.6
22
3.7
22
3.8
Unforeseeable difficulties
23
24
4.1
24
4.2
25
4.3
Environmental Clearances
25
27
5.1
27
5.2
28
5.3
Disclosure
29
Disclaimer
30
6.1
Disclaimer
30
PART III
31
Performance Security
32
7.1
Performance Security
32
7.2
32
7.3
33
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
EPC Agreement
7.4
33
7.5
Retention Money
33
Right of Way
35
8.1
The Site
35
8.2
35
8.3
36
8.4
37
8.5
37
8.6
38
8.7
38
8.8
38
39
9.1
39
9.2
39
9.3
New utilities
39
9.4
Felling of trees
41
10
42
10.1
42
10.2
44
10.3
46
10.4
47
10.5
47
10.6
Incomplete Works
49
10.7
Maintenance Manual
49
11
50
11.1
50
11.2
50
11.3
Methodology
50
11.4
51
11.5
51
11.6
51
11.7
51
11.8
Inspection
51
11.9
Samples
52
11.10
Tests
52
11.11
52
11.12
Rejection
53
11.13
Remedial work
53
11.14
54
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
EPC Agreement
11.15
54
11.16
Video recording
54
11.17
54
12
Completion Certificate
56
12.1
Tests on completion
56
12.2
Provisional Certificate
56
12.3
57
12.4
Completion Certificate
58
12.5
Rescheduling of Tests
58
13
Change of Scope
59
13.1
Change of Scope
59
13.2
59
13.3
61
13.4
61
13.5
61
14
Maintenance
62
14.1
62
14.2
Maintenance Requirements
63
14.3
Maintenance Programme
63
14.4
63
14.5
Lane closure
63
14.6
64
14.7
64
14.8
64
14.9
65
15
66
15.1
66
15.2
66
15.3
Tests
67
15.4
67
16
Traffic Regulation
68
16.1
68
17
Defects Liability
69
17.1
69
17.2
Remedying Defects
69
17.3
69
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
EPC Agreement
17.4
69
17.5
70
17.6
70
18
Employers Engineer
71
18.1
71
18.2
71
18.3
72
18.4
72
18.5
72
18.6
73
18.7
73
74
19
Payments
75
19.1
Contract Price
75
19.2
Advance Payment
75
19.3
76
19.4
77
19.5
77
19.6
78
19.7
78
19.8
Payment of Damages
79
19.9
79
19.10
80
19.11
81
19.12
81
19.13
81
19.14
Discharge
82
19.15
82
19.16
82
19.17
Change in law
83
19.18
83
19.19
Employers claims
83
19.20
84
20
Insurance
85
20.1
85
20.2
86
20.3
86
20.4
86
20.5
Waiver of subrogation
87
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
EPC Agreement
20.6
Contractors waiver
87
20.7
Cross liabilities
87
20.8
87
20.9
87
20.10
88
20.11
88
Part V
89
21
Force Majeure
90
21.1
Force Majeure
90
21.2
Non-Political Event
90
21.3
91
21.4
Political Event
91
21.5
92
21.6
93
21.7
93
21.8
94
21.9
Dispute resolution
94
21.10
94
22
95
22.1
95
22.2
95
22.3
Revocation of Suspension
95
22.4
Termination
96
23
Termination
97
23.1
97
23.2
99
23.3
100
23.4
100
23.5
100
23.6
Termination Payment
101
23.7
102
23.8
Survival of rights
103
104
24
105
24.1
105
24.2
105
25
106
25.1
General indemnity
106
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
EPC Agreement
25.2
106
25.3
107
25.4
Defence of claims
107
25.5
No consequential claims
108
25.6
Survival on Termination
108
26
Dispute Resolution
109
26.1
Dispute Resolution
109
26.2
Conciliation
109
26.3
Arbitration
109
26.4
110
27
Miscellaneous
111
27.1
111
27.2
Waiver of immunity
111
27.3
Delayed payments
111
27.4
Waiver
112
27.5
112
27.6
112
27.7
Survival
112
27.8
Entire Agreement
113
27.9
Severability
113
27.10
No partnership
113
27.11
Third Parties
113
27.12
114
27.13
Notices
114
27.14
Language
114
27.15
Counterparts
114
27.16
Confidentiality
114
27.17
115
27.18
Limitation of Liability
115
28
Definitions
116
28.1
Definitions
116
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
EPC Agreement
Schedules:
Schedule-A
Schedule-B
Schedule-C
Schedule-D
Schedule-E
Schedule-F
Schedule-G
Schedule-H
Schedule-I
Drawings.....292 - 295
Schedule-J
Schedule-K
Schedule-L
Schedule-M
Schedule-N
Schedule-O
Schedule-P
Insurance.....319 - 320
Schedule-Q
Schedule-R
Schedule-S
Schedule -T
Schedule U Reports.409
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
EPC Agreement
Part I
Preliminary
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
EPC Agreement
(A) A special purpose vehicle viz Aurangabad Industrial Township Limited (AITL),
is set up (the Employer) with the equity participation of Central and State
Governments for procurement and Construction of trunk infrastructure in
Shendra-Bidkin Industrial Area (SBIA), Aurangabad, Maharashtra.
(B)
Accordingly, the Employer has decided to undertake the Design and B uild
the Infrastructure Works for Roads, Drains, Culverts, Water Supply,
Sewerage, Power systems for Phase - I in Shendra-Bidkin Industrial Area,
Aurangabad, Maharashtra on EPC Basis (Package - I), (the Project),
through Engineering, Procurement & Construction (EPC) basis, in
accordance with the terms and conditions to be set forth in an Agreement to be
entered into.
(C)
(D) The E m pl oyer h a d presc ribe d the technical and commercial terms and
conditions, and invited bids (the Request for Proposals or RFP) from the
bidders shortlisted pursuant to the RFQ for undertaking the Project.
(E) After evaluation of the bids received, the Employer had accepted the Bid of the
selected bidder and issued its Letter of Acceptance No. .. dated
.. (hereinafter called the LOA) to the selected bidder Design and
Build the Infrastructure Works for Roads, Drains, Culverts, Water
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 10
EPC Agreement
Supply, Sewerage, Power systems Infrastructure for Phase - I in ShendraBidkin Industrial Area, Aurangabad, Maharashtra on EPC Basis
(Package - I) at the contract price specified hereinafter, requiring the selected
bidder to inter alia:
(a) deliver to the Employer a legal opinion from the legal counsel of the
selected bidder with respect to the authority of the selected bidder to
enter into this Agreement and the enforceability of the provisions
thereof, within 10 (ten) days of the date of issue of LOA; and
(b) execute this Agreement within 30 (Thirty) days of the date of issue of
LOA.
(F)
The Contractor has fulfilled the requirements specified in Recital (E) above;
NOW THEREFORE in consideration of the foregoing and the respective covenants and
Agreements set forth in this Agreement, the sufficiency and adequacy of which is hereby
acknowledged, the Employer hereby covenants to pay the Contractor, in consideration
of the obligations specified herein, the Contract Price or such other sum as may
become payable under the provisions of the Agreement at the times and in the manner
specified by the Agreement and intending to be legally bound hereby, the Parties agree as
follows:
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 11
EPC Agreement
ARTICLE 1
1. DEFINITIONS AND INTERPRETATION
1.1
Definitions
The words and expressions beginning with capital letters and defined in this
Agreement (including those in Article 28) shall, unless the context otherwise
requires, have the meaning ascribed thereto herein, and the words and
expressions defined in the Schedules and used therein shall have the
meaning ascribed thereto in the Schedules.
1.2
Interpretation
1.2.1
(b)
(c)
(d)
(e)
(f)
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 12
EPC Agreement
(h)
(i)
(j)
(k)
(l)
(m)
(n)
the words importing singular shall include plural and vice versa;
(o)
references to any gender shall include the other and the neutral
gender;
(p)
(q)
(r)
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 13
EPC Agreement
(s)
(t)
(u)
(v)
(w)
(x)
1.2.2
1.2.3
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 14
EPC Agreement
1.2.4
1.3
1.4
1.4.1
This Agreement, and all other Agreements and documents forming part of or
referred to in this Agreement are to be taken as mutually explanatory and,
unless otherwise expressly provided elsewhere in this Agreement, the
priority of this Agreement and other documents and Agreements forming
part hereof or referred to herein shall, in the event of any conflict between
them, be in the following order:
(a) this Agreement; and
(b) all other Agreements and documents forming part hereof or referred to
herein; i.e. this Agreement at (a) above shall prevail over the
Agreements and documents at (b).
1.4.2
1.5
1.5.1
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 15
EPC Agreement
Without prejudice to the joint and several liability of all the members of the
Consortium, the Lead Member shall represent all the members of
the Consortium and shall at all times be liable and responsible for
discharging the functions and obligations of the Contractor. The Contractor
shall ensure that each member of the Consortium shall be bound
by any decision, communication, notice, action or inaction of the Lead
Member on any matter related to this Agreement and the Employer shall be
entitled to rely upon any such action, decision or communication of the
Lead Member. The Employer shall have the right to release payments solely
to the Lead Member and shall not in any manner be responsible or liable
for the inter se allocation of payments among members of the
Consortium$.
$ This Clause 1.5 may be omitted if the Contractor is not a Corsortium. Even if the contractor is a
Consortium the Authority may,at its discretion,delete this provision
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 16
EPC Agreement
Part II
Scope of Project
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 17
EPC Agreement
ARTICLE 2
2. SCOPE OF THE PROJECT
2.1
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 18
EPC Agreement
ARTICLE 3
3. OBLIGATIONS OF THE CONTRACTOR
3.1
3.1.1
Subject to and on the terms and conditions of this Agreement, the Contractor
shall undertake the survey, investigation, design, engineering, procurement,
Construction, and Maintenance of the Project Roads and Services/utilities as
defined in Scope and observe, fulfill, comply with and perform all its
obligations set out in this Agreement or arising hereunder.
3.1.2
The Contractor shall comply with all Applicable Laws and Applicable
Permits (including renewals as required) in the performance of its obligations
under this Agreement.
3.1.3
Subject to the provisions of Clauses 3.1.1 and 3.1.2, the Contractor shall
discharge its obligations in accordance with Good Industry Practice.
3.1.4
The Contractor shall remedy any and all loss or damage to the Project
Roads and Services/utilities from the Appointed Date until the end of the
Construction Period at the Contractors cost, save and except to the extent
that any such loss or damage shall have arisen from any default or neglect of
the Employer.
3.1.5
The Contractor shall remedy any and all loss or damage to the Project Roads
and Services/utilities during the Defects Liability Period at the Contractors
cost to the extent that such loss or damage shall have arisen out of the
reasons specified in Clause 17.3.
3.1.6
The Contractor shall remedy any and all loss or damage to the Project Roads
and Services/utilities during the Maintenance Period at the Contractors cost,
including those stated in Clause 14.1.2, save and except to the extent that
any such loss or damage shall have arisen on account of any default or
neglect of the Employer or on account of a Force Majeure Event.
3.1.7
The Contractor shall, at its own cost and expense, in addition to and not in
derogation of its obligations elsewhere set out in this Agreement:
(a) make, or cause to be made, necessary applications to the relevant
Government Instrumentalities with such particulars and details as
may be required for obtaining Applicable Permits set forth in
Schedule-F and obtain and keep in force and effect such Applicable
Permits in conformity with the Applicable Laws;
(b) procure, as required, the appropriate proprietary rights, licenses,
Agreements and permissions for Materials, methods, processes and
systems used or incorporated into the Project Roads and Services;
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 19
EPC Agreement
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 20
EPC Agreement
3.2
3.2.1
The Contractor shall not sub-contract any Works in more than 50% (fifty per
cent) of the total contract amount of the Project and shall carry out
Works directly under its own supervision and through its own personnel in at
least 50% (fifty per cent) of the total contract amount of the Project.
Provided, however, that in respect of the Works carried out directly by the
Contractor, it may enter into contracts for the supply and installation of
Materials, Plant, equipment, road furniture, safety devices and labor, as the
case may be, for such Works. For the avoidance of doubt, the Parties agree
that the Contractor may sub-divide the aforesaid Works of 50% (fifty per
cent) in no more than 5 (five) sections of the Project Scope. The Parties
further agree that all obligations and liabilities under this Agreement for the
entire Project Works shall at all times remain with the Contractor. In case of
a Joint Venture, the Parties also agree that obligation of the Contractor to
carry out Works directly in at least 50% (fifty per cent) of the total contract
amount of the Project shall be discharged solely by the Lead Member.
3.2.2
3.2.3
3.2.4
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 21
3.3
EPC Agreement
3.4
Contractors personnel
3.4.1
3.4.2
3.4.3
3.5
3.6
3.7
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 22
3.8
EPC Agreement
Unforeseeable difficulties
Except as otherwise stated in the Agreement:
(a) The Contractor accepts complete responsibility for having foreseen all
difficulties and costs of successfully completing the Works;
(b) The Contract Price shall not be adjusted to take account of any
unforeseen difficulties or costs; and
(c) The Scheduled Completion Date shall not be adjusted to take account of
any unforeseen difficulties or costs.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 23
EPC Agreement
ARTICLE 4
4. OBLIGATIONS OF THE EMPLOYER
4.1
4.1.1
The Employer shall, at its own cost and expense, undertake, comply with and
perform all its obligations set out in this Agreement or arising hereunder.
To assist in due discharge of its obligation, the Employer has appointed
Programme Manager for New Cities, (PMNC). The role of the PMNC is
to perform activities necessary to plan, integrate, package, administer and
manage the implementation of SBIA Projects. Specifically, the PMNC will
be responsible for conceptualization of Projects and further, during the
design and Construction stage, overseeing the work of consultants and
contractors, including reviewing, monitoring, resolution of interface issues,
and reporting to the State nodal agency and AITL on the Programme
progress. All communications relating to contract management on this
Project shall be submitted to the PMNC for final approval of Employer.
4.1.2
The Employer shall be responsible for the correctness of the Scope of the
Project, Project Facilities, Specifications and Standards and the criteria for
testing of the completed Works.
4.1.3
4.1.4
Not used
4.1.5
4.1.6
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 24
EPC Agreement
(a) upon written request from the Contractor, and subject to the
Contractor complying with Applicable Laws, provide reasonable
support to the Contractor in procuring Applicable Permits required
from any Government Instrumentality for implementation of the
Project;
(b) upon written request from the Contractor, provide reasonable
assistance to the Contractor in obtaining access to all necessary
infrastructure facilities and utilities, including water and electricity at
rates and on terms no less favourable than those generally available to
commercial customers receiving substantially equivalent services;
(c) procure that no barriers that would have a Material Adverse Effect on
the Works are erected or placed on or about the Project Site by any
Government Instrumentality or persons claiming through or under it,
except for reasons of Emergency, national security, law and order or
collection of inter-state Taxes;
(d) not do or omit to do any act, deed or thing which may in any manner
be violative of any of the provisions of this Agreement;
(e) support, cooperate with and facilitate the Contractor in the
implementation of the Project in accordance with the provisions of
this Agreement; and
(f) upon written request from the Contractor and subject to
provisions of Clause 3.3, provide reasonable assistance to
Contractor and any expatriate personnel of the Contractor or
Subcontractors to obtain applicable visas and work permits for
purposes of discharge by the Contractor or its Sub-contractors
their obligations under this Agreement and the Agreements with
Subcontractors.
4.2
the
the
its
the
of
the
4.3
Environmental Clearances
The Employer represents and warrants that the environmental clearances
required for Construction of the Project are being procured by the Employer.
The Employer agrees and undertakes that the environmental clearances
shall be procured by the Employer no later than 60(sixty) days from the
Appointed Date. In the event of any delay beyond such 60(sixty) days, the
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 25
EPC Agreement
Contractor shall be entitled to Time Extension for the period of such delay in
accordance with the provision of Clause 10.5 of this Agreement and shall
also be entitled to Damages calculated as if the Right of Way for and in
respect of such sections of the Project Right of way has not been provided in
accordance with the provisions of Clause 8.2 and as a consequence
thereof, the Contractor shall be entitled to Damages under and in
accordance with the provisions of Clause 8.3. For the avoidance of doubt,
the present status of environmental clearances is specified in Schedule-A.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 26
EPC Agreement
ARTICLE 5
5. REPRESENTATIONS AND WARRANTIES
5.1
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 27
EPC Agreement
5.2
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 28
EPC Agreement
5.3
Disclosure
In the event that any occurrence or circumstance comes to the attention of
either Party that renders any of its aforesaid representations or warranties
untrue or incorrect, such Party shall immediately notify the other Party of the
same. Such notification shall not have the effect of remedying any breach of
the representation or warranty that has been found to be untrue or incorrect
nor shall it adversely affect or waive any obligation of either Party under this
Agreement.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 29
EPC Agreement
ARTICLE 6
6. DISCLAIMER
6.1
Disclaimer
6.1.1
6.1.2
6.1.3
6.1.4
The Parties agree that any mistake or error in or relating to any of the
matters set forth in Clause 6.1.1 above shall not vitiate this Agreement, or
render it voidable.
6.1.5
In the event that either Party becomes aware of any mistake or error relating
to any of the matters set forth in Clause 6.1.1 above, that Party shall
immediately notify the other Party, specifying the mistake or error.
6.1.6
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 30
EPC Agreement
Part III
Construction and Maintenance
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 31
EPC Agreement
ARTICLE 7
7. PERFORMANCE SECURITY
7.1
Performance Security
7.1.1
The Contractor shall, for the performance of its obligations hereunder during
the Construction Period, provide to the Employer, within 10 (ten) days of the
date of this Agreement, an irrevocable and unconditional guarantee from a
Bank in the form set forth in Schedule-G (the Performance Security) for
an amount equal to 7.5% (seven and half percent) of the Contract Price.
The Performance Security shall be valid until 60 (sixty) days after the
Defects Liability Period. Until such time the Performance Security is
provided by the Contractor pursuant hereto and the same comes into effect,
the Bid Security shall remain in force and effect, and upon such provision of
the Performance Security, the Employer shall release the Bid Security to the
Contractor. For the avoidance of doubt, the Parties expressly agree that the
Contractor shall provide, no later than 30 (thirty) days prior to the expiry of
the Performance Security for the Defects Liability Period specified in Clause
17.1.1, a Performance Security in respect of the extended Defects Liability
Period specified in Clause 17.1.2 for an amount equal to 5% (five per cent)
of the estimated cost of Structures and Major Bridges specified therein.
7.1.2
7.1.3
7.2
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 32
EPC Agreement
7.3
7.3.1
7.3.2
7.4
7.5
Retention Money
7.5.1
From every payment for Works due to the Contractor in accordance with
the provisions of Clause 19.5, the Employer shall deduct 6% (six per cent)
thereof as guarantee money for performance of the obligations of the
Contractor during the Construction Period (the Retention Money) subject
to the condition that the maximum amount of Retention Money shall not
exceed 5% (five per cent) of the Contract Price.
7.5.2
7.5.3
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 33
EPC Agreement
7.5.4
7.5.5
The Parties agree that in the event of Termination of this Agreement, the
Retention Money and the Bank guarantees specified in this Clause 7.5 shall
be treated as if they are Performance Security and shall be reckoned as
such for the purposes of Termination Payment under Clause 23.6.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 34
EPC Agreement
ARTICLE 8
8. RIGHT OF WAY
8.1
The Site
The Site of the Project Works (the Site) shall comprise the Site described
in Schedule-A in respect of which the Right of Way shall be provided by
the Employer to the Contractor. The Employer shall be responsible for:
(a) acquiring and providing Right of Way on the Site in accordance
with the alignment finalized by the Employer, free from all
encroachments and encumbrances, and free access thereto for the
execution of this Agreement; and
(b) obtaining licenses and permits for environment clearance for the
Project Works.
8.2
8.2.1
8.2.2
The Employer shall provide the Right of Way to the Contractor in respect
of all land included in the Appendix by the date specified in Schedule-A
for those parts of the Site referred to therein, or no later than 90 (ninety) days
of the Appointed Date for those parts of the Site which have not been
specified in Schedule-A, and in the event of delay for any reason other than
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 35
EPC Agreement
8.2.3
8.3
8.3.1
In the event the Right of Way to any part of the Site is not provided by the
Employer on or before the date(s) specified in Clause 8.2 for any reason
other than Force Majeure or breach of this Agreement by the Contractor,
the Employer shall pay Damages to the Contractor in a sum calculated in
accordance with the following formula for and in respect of those parts of
the Site to which the Right of Way has not been provided:
Amount of Damages in Rs. per day per meter = 0.05 x C x 1/L x 1/N
Where
C = the Contract Price;
L = length of the Project Right of Way in meters; and
N = Completion period in days (Appointed Date to Scheduled
Completion Date)
In the event that any Damages are due and payable to the Contractor under
the provisions of this Clause 8.3.1 for delay in providing the Right of Way,
the Contractor shall, subject to the provisions of Clause 10.5, be entitled to
Time Extension equal to the period for which the Damages have become due
and payable under this Clause 8.3.1, save and except that:
(a) if any delays involve time overlaps, the overlaps shall not be
additive; and
(b) such Time Extension shall be restricted only to the Works which
are affected by the delay in providing the Right of Way.
For the avoidance of doubt, the Parties expressly agree that the Damages
specified hereunder and the Time Extension specified in Clause 10.5 shall
be restricted only to failure of the Employer to provide the Right of Way
for and in respect of the width of the roadway, its embankment and a parallel
working strip at least 3 (three) metres wide
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 36
EPC Agreement
8.3.2
8.3.3
8.3.4
In the event of withdrawal of Works under Clause 8.3.3, the Contract Price
shall be reduced by an amount equal to 90 (ninety) per cent of the value of
the Works withdrawn and the Contractor shall not be entitled to any other
compensation or Damages for the withdrawal of Works, save and except
for Damages as provided under Clauses 8.3 and 9.2.
Provided that if any Works are withdrawn after commencement of the
Construction of such Works, the Employer shall pay to the Contractor
110% (one hundred and ten per cent) of the fair value of the work done, as
assessed by the Employers Engineer:
8.4
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 37
8.5
EPC Agreement
8.6
8.7
8.7.1
8.7.2
The Contractor shall ensure, subject to all relevant safety procedures, that the
Employer has un-restricted access to the Site during any emergency
situation, as decided by the Employers Engineer.
8.8
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 38
EPC Agreement
ARTICLE 9
9. UTILITIES AND TREES
9.1
9.2
9.3
New utilities
9.3.1
9.3.2
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 39
9.3.3
EPC Agreement
Contractor's acknowledgement
take all reasonable steps to co-ordinate and to integrate the design and
execution of the Works, including the work of Subcontractors, with
the activities of the Related Works Contractors; and
(b)
(c)
at all times refrain from carrying out any operation on the Site in a
manner which is likely to cause damage or inconvenience to the
execution of any Related Works; where such damage or
inconvenience is the unavoidable consequence of operations properly
to be carried out on the Site, the Contractor shall not carry out such
operations without first giving reasonable advance notice in writing
thereof to the Employer's Representative (with a copy to those
responsible for carrying out any Related Works reasonably likely to
be affected thereby) with a view to reaching an agreed procedure to
prevent or minimise any such damage or inconvenience. In particular,
the Contractor shall at all times prevent the discharge of surface water
across the Site except where the Employer's Representative gives its
prior written consent for such discharge; and
(d)
(e)
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 40
EPC Agreement
9.3.4
9.4
Felling of trees
9.4.1
The Employer shall assist the Contractor in obtaining the Applicable Permits
for felling of trees to be identified by the Employer for this purpose if and
only if such trees cause a Material Adverse Effect on the Construction or
Maintenance of the Project Works. The cost of such felling shall be borne
by the Employer and in the event of any delay in felling thereof for
reasons beyond the control of the Contractor; it shall be excused for failure to
perform any of its obligations hereunder if such failure is a direct
consequence of delay in the felling of trees. The Parties hereto agree that the
felled trees shall be deemed to be owned by the Employer and shall be
disposed in such manner and subject to such conditions as the Employer may
in its sole discretion deem appropriate. For the avoidance of doubt, the
Parties agree that if any felling of trees hereunder is in a forest area, the
Applicable Permit thereof shall be procured by the Employer within the
time specified in the Agreement.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 41
EPC Agreement
ARTICLE 10
10. DESIGN AND CONSTRUCTION OF THE PROJECT WORKS
10.1
10.1.1
10.1.2
The Employer shall, within 15 (fifteen) days of the date of this Agreement,
appoint an engineer (the Employers Engineer) to discharge the functions
and duties specified in this Agreement, and shall notify to the Contractor the
name, address and the date of appointment of the Employers Engineer
forthwith.
10.1.3
Within 30 (thirty) days of the Appointed Date, the Contractor shall submit to
the Employer and the Employers Engineer a Programme (the
Programme) for the Works, developed using networking techniques
giving the following details:
Part I-Contractors organization for the Project, the general methods and
arrangements for design and Construction, environmental management plan,
Quality Assurance Plan including design quality plan, traffic management
and safety plan covering safety of users and workers during Construction,
Contractors key personnel and equipment.
Part II- Programme for completion of all stages of Construction given in
Schedule-H and Project Milestones of the Works as specified in
Project
Completion Schedule set forth in Schedule-J. The Programme shall include:
(a) the order in which the Contractor intends to carry out the Works,
including the anticipated timing of design and stages of Works;
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 42
EPC Agreement
10.1.5
10.1.6
The safety audit pursuant to Clause 10.1.5 shall be carried out by the Safety
Consultant in respect of all such design details that have a bearing on safety
of Users as well as pedestrians and animals involved in or associated with
accidents. The recommendations of the Safety Consultant shall be
incorporated in the design of the Project Works and the Contractor shall
forward to the Employers Engineer a certificate to this effect together with
the recommendations of the Safety Consultant. In the event that any Works
required by the Safety Consultant shall fall beyond the scope of Schedule-B,
Schedule-C or Schedule-D, the Contractor shall make a report thereon and
seek the instructions of the Employer for Change in Scope. For the avoidance
of doubt, the Safety Consultant to be engaged by the Contractor shall be
independent of the design and implementation team of the Contractor.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 43
EPC Agreement
10.2
10.2.1
10.2.2
10.2.3
10.2.4
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 44
EPC Agreement
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 45
EPC Agreement
10.2.5
10.2.6
10.2.7
Within 90 (ninety) days of the Project Completion Date, the Contractor shall
furnish to the Employer and the Employers Engineer a complete set of as
built Drawings, in 2 (two) hard copies and in micro film form or in such
other medium as may be acceptable to the Employer, reflecting the Project
Works as actually designed, engineered and constructed, including an as
built survey illustrating the layout of the Project Works and setback lines, if
any, of the buildings and Structures forming part of Project Facilities.
10.3
10.3.1
10.3.2
The Contractor shall construct the Project Works in accordance with the
Project Completion Schedule set forth in Schedule-J. In the event that the
Contractor fails to achieve any Project Milestone or the Scheduled
Completion Date within a period of 30 (thirty) days from the date set
forth in Schedule-J, unless such failure has occurred due to Force Majeure
or for reasons solely attributable to the Employer, it shall pay Damages to
the Employer of a sum calculated at the rate of 0.05% (zero point zero five
percent) of the Contract Price for delay of each day reckoned from the date
specified in Schedule J and until such Project Milestone is achieved or the
Works are completed; provided that if the period for any or all Project
Milestones or the Scheduled Completion Date is extended in accordance
with the provisions of this Agreement, the dates set forth in Schedule-J shall
be deemed to be modified accordingly and the provisions of this Agreement
shall apply as if Schedule-J has been amended as above; provided further
that in the event the Works are completed within or before the Scheduled
Completion Date including any Time Extension, applicable for that work or
section, the Damages paid under this Clause 10.3.2 shall be refunded by the
Employer to the Contractor, but without any interest thereon. For the
avoidance of doubt, it is agreed that recovery of Damages under this Clause
10.3.2 shall be without prejudice to the rights of the Employer under this
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 46
EPC Agreement
The Employer shall notify the Contractor of its decision to impose Damages in
pursuance with the provisions of this Clause 10.3. Provided that no
deduction on account of Damages shall be effected by the Employer without
notifying the Contractor of its decision to impose the Damages, and taking
into consideration the representation, if any, made by the Contractor within
20 (twenty) days of such notice. The Parties expressly agree that the total
amount of Damages under Clause 10.3.2 shall not exceed 10% (ten percent)
of the Contract Price.
10.4
10.4.1
During the Construction Period, the Contractor shall maintain, at its cost, the
existing lane(s) of the Project roads so that the traffic worthiness and safety
thereof are at no time Material ly inferior as compared to their condition 10
(ten) days prior to the date of this Agreement, and shall undertake the
necessary repair and Maintenance Works for this purpose; provided that the
Contractor may, at its cost, interrupt and divert the flow of traffic if such
interruption and diversion is necessary for the efficient progress of Works
and conforms to Good Industry Practice; provided further that such
interruption and diversion shall be undertaken by the Contractor only with
the prior written approval of the Employers Engineer which approval shall
not be unreasonably withheld. For the avoidance of doubt, it is agreed that
the Contractor shall at all times be responsible for ensuring safe operation of
the Project roads.
10.5
10.5.1
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 47
10.5.2
EPC Agreement
The Contractor shall, no later than 15 (fifteen) business days from the
occurrence of an event or circumstance specified in Clause 10.5.1, inform
the Employers Engineer by notice in writing, with a copy to the Employer,
stating in reasonable detail with supporting particulars, the event or
circumstances giving rise to the claim for Time Extension in accordance
with the provisions of this Agreement. Provided that the period of 15
(fifteen) business days shall be calculated from the date on which the
Contractor became aware, or should have become aware, of the occurrence
of such an event or circumstance.
Provided further that notwithstanding anything to the contrary contained in
this Agreement, Time Extension shall be due and applicable only for the
Works which are affected by the aforesaid events or circumstances and shall
not in any manner affect the Project Completion Schedule for and in respect
of the Works which are not affected hereunder.
10.5.3
10.5.4
10.5.5
If the event or circumstance giving rise to the notice has a continuing effect:
(a) a fully detailed claim shall be considered as interim;
(b) the Contractor shall, no later than 10 (ten) days after the close of
each month, send further interim claims specifying the accumulated
delay, the extension of time claimed, and such further particulars as
the Employers Engineer may reasonably require; and
(c) the Contractor shall send a final claim within 30 (thirty) days after
the effect of the event or the circumstance ceases.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 48
EPC Agreement
Upon receipt of the claim hereunder, the Employers Engineer shall examine
the same in accordance with the provisions of Clause 10.5.4 within a period
of 60 (sixty) days of the receipt thereof.
10.6
Incomplete Works
In the event the Contractor fails to complete the Works in accordance with
the Project Completion Schedule, including any Time Extension granted
under this Agreement, the Contractor shall endeavor to complete the
balance work expeditiously and shall pay Damages to the Employer in
accordance with the provisions of Clause 10.3.2 for delay of each day until
the Works are completed in accordance with the provisions of this
Agreement. Recovery of Damages under this Clause shall be without
prejudice to the rights of the Employer under this Agreement including the
right to Termination under Clause 23.1.
10.7
Maintenance Manual
No later than 60 (sixty) days prior to the Project Completion Date, the
Contractor shall, in consultation with the Employers Engineer, evolve a
Maintenance Manual (the Maintenance Manual) for the regular and
preventive Maintenance of the Project Works in conformity with the
Specifications and Standards, safety requirements and Good Industry
Practice, and shall provide 5 (five) copies thereof to the Employers
Engineer. The Employers Engineer shall review the Maintenance Manual
within 15 (fifteen) days of its receipt and communicate its comments to the
Contractor for necessary modifications, if any.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 49
EPC Agreement
ARTICLE 11
11. QUALITY ASSURANCE, MONITORING AND SUPERVISION
11.1
11.2
11.2.1
11.2.2
The Contractor shall, within 30 (thirty) days of the Appointed Date, submit to
the Employers Engineer its Quality Assurance Plan which shall include the
following:
(a) organisation, duties and responsibilities, procedures, inspections
and Documentation;
(b) quality control mechanism including sampling and testing of
Materials, test frequencies, standards, acceptance criteria, testing
facilities, reporting, recording and interpretation of test results,
approvals, check list for Site activities, and proforma for testing and
calibration in accordance with the Specifications for Road and
Bridge Works issued by MORTH, relevant IRC specifications and
Good Industry Practice; and
(c) Internal quality audit system.
The Employers Engineer shall convey its comments to the Contractor within
a period of 21 (twenty-one) days of receipt of the QAP stating the
modifications, if any, required, and the Contractor shall incorporate those in
the QAP to the extent required for conforming with the provisions of this
Clause 11.2.
11.2.3
11.2.4
11.3
Methodology
The Contractor shall, at least 15 (fifteen) days prior to the commencement
of the Construction, submit to the Employers Engineer for review the
methodology proposed to be adopted for executing the Works, giving details
of equipment to be deployed, traffic management and measures for ensuring
safety. The Employers Engineer shall complete the review and convey its
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 50
EPC Agreement
11.4
11.5
11.6
11.7
11.8
Inspection
11.8.1
11.8.2
The Contractor shall give the Employers Engineer and its authorized
agents access, facilities and safety equipment for carrying out their
obligations under this Agreement.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 51
EPC Agreement
11.8.3
11.9
Samples
The Contractor shall submit the following samples of Materials and
relevant information to the Employers Engineer for pre-Construction
review:
(a) manufacturer test reports and standard samples of
Materials; and
manufactured
11.10
Tests
11.10.1
11.10.2
In the event that results of any Tests conducted under this Clause 11.10
establish any Defects or deficiencies in the Works, the Contractor shall
carry out remedial measures and furnish a report to the Employers
Engineer in this behalf. The Employers Engineer shall require the
Contractor to carry out or cause to be carried out Tests to determine that
such remedial measures have brought the Works into compliance with the
Specifications and Standards, and the procedure shall be repeated until such
Works conform to the Specifications and Standards. For the avoidance of
doubt, the cost of such Tests and remedial measures in pursuance thereof
shall be solely borne by the Contractor.
11.11
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 52
EPC Agreement
11.12
Rejection
If, as a result of an examination, inspection, measurement or testing, any
Plant, Materials, design or workmanship is found to be defective or
otherwise not in accordance with the provisions of this Agreement, the
Employers Engineer shall reject the Plant, Materials, design or
workmanship by giving notice to the Contractor,
with
reasons.
The
Contractor shall then promptly make good the Defect and ensure that the
rejected item complies with the requirements of this Agreement.
If the Employers Engineer requires the Plant, Materials, design or
workmanship to be retested, the Tests shall be repeated under the same
terms and conditions, as applicable in each case. If the rejection and
retesting cause the Employer to incur any additional costs, such cost shall
be recoverable by the Employer from the Contractor; and may be deducted
by the Employer from any monies due to be paid to the Contractor.
11.13
Remedial work
11.13.1
11.3.2
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 53
11.14
EPC Agreement
11.15
11.16
Video recording
During the Construction Period, the Contractor shall provide to the
Employer for every calendar quarter, a video recording, which will be
compiled into a 3 (three)-hour compact disc or digital video disc, as the
case may be, covering the status and progress of Works in that quarter. The
video recording shall be provided to the Employer no later than 15 (fifteen)
days after the close of each quarter after the Appointed Date.
11.17
11.17.1
11.17.2
The Contractor shall, pursuant to the notice under Clause 11.17.1, suspend
the Works or any part thereof for such time and in such manner as may be
specified by the Employer and thereupon carry out remedial measures to
secure the safety of suspended Works, the Users and pedestrians. The
Contractor may by notice require the Employers Engineer to inspect such
remedial measures forthwith and make a report to the Employer
recommending whether or not the Suspension hereunder may be revoked.
Upon receiving the recommendations of the Employers Engineer, the
Employer shall either revoke such Suspension or instruct the Contractor to
carry out such other and further remedial measures as may be necessary in
the reasonable opinion of the Employer, and the procedure set forth in this
Clause 11.17 shall be repeated until the Suspension hereunder is revoked.
11.17.3
Subject to the provisions of Clause 21.6, all reasonable costs incurred for
maintaining and protecting the Works or part thereof during the period of
Suspension (the Preservation Costs), shall be borne by the Contractor;
provided that if the Suspension has occurred as a result of any breach of this
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 54
EPC Agreement
11.18
The contractor shall take up the Aerial photography based on the details
provided in Schedule T
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 55
EPC Agreement
ARTICLE 12
12. COMPLETION CERTIFICATE
12.1
Tests on completion
12.1.1
12.1.2
12.2
Provisional Certificate
12.2.1
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 56
EPC Agreement
period thereof. For the avoidance of doubt, the Parties agree that the Punch
List shall include all Works for which Time Extension has been granted and
shall also include any minor outstanding items of work forming part of the
completed Sections if such Works do not Material ly affect the use of the
completed Sections for their intended purpose. The Parties further agree that
Provisional Certificate shall not be issued if the completed Works cannot be
safely and reliably placed in service of the Users thereof.
12.2.2
12.2.3
12.2.4
12.2.5
12.3
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 57
EPC Agreement
12.4
Completion Certificate
12.4.1
Upon completion of all Works, including the items specified in the Punch
List, and the Employers Engineer determining the Tests to be successful, it
shall forthwith issue to the Contractor and the Employer a certificate
substantially in the form set forth in Schedule-L (the Completion
Certificate).
12.4.2
Upon receiving the Completion Certificate, the Contractor shall remove its
equipment, Materials, debris and temporary Works from the Site within a
period of 30 (thirty) days thereof, failing which the Employer may remove or
cause to be removed, such equipment, Materials, debris and temporary
Works and recover from the Contractor an amount equal to 120% (one
hundred and twenty per cent) of the actual cost of removal incurred by the
Employer.
12.4.3
12.5
Rescheduling of Tests
If the Employers Engineer certifies to the Employer and the Contractor that
it is unable to issue the Completion Certificate or Provisional Certificate, as
the case may be, because of events or circumstances on account of which the
Tests could not be held or had to be suspended, the Contractor shall be
entitled to re-schedule the Tests and hold the same as soon as reasonably
practicable.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 58
EPC Agreement
ARTICLE 13
13. CHANGE OF SCOPE
13.1
Change of Scope
13.1.1
13.1.2
13.1.3
13.2
13.2.1
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 59
EPC Agreement
13.2.2
Upon receipt of a Change of Scope Notice, the Contractor shall, with due
diligence, provide to the Employer and the Employers Engineer such
information as is necessary, together with preliminary Documentation in
support of:
(a) the impact, if any, which the Change of Scope is likely to have on
the Project Completion Schedule if the Works or services are
required to be carried out during the Construction Period; and
(b) the options for implementing the proposed Change of Scope and the
effect, if any, each such option would have on the costs and time
thereof, including the following details:
(i)
(ii)
(iii)
For the avoidance of doubt, the Parties expressly agree that, subject to the
provisions of Clause 13.4.2, the Contract Price shall be increased or
decreased, as the case may be, on account of Change of Scope.
13.2.3
13.2.4
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 60
EPC Agreement
13.2.5
13.3
13.4
13.4.1
No Change of Scope shall be executed unless the Employer has issued the
Change of Scope Order save and except any Works necessary for meeting
any Emergency.
13.4.2
Unless the Parties mutually agree to the contrary, the total value of all
Change of Scope Orders shall not exceed 10 (ten) per cent of the Contract
Price.
13.4.3
13.5
13.5.1
In the event the Parties are unable to agree to the proposed Change of
Scope Orders in accordance with Clause 13.2, the Employer may, after
giving notice to the Contractor and considering its reply thereto, award
such Works or services to any person on the basis of open competitive
bidding from amongst bidders who are pre-qualified for undertaking the
additional work; provided that the Contractor shall have the option of
matching the first ranked Bid in terms of the selection criteria, subject to
payment of 2% (two per cent) of the B i d amount to the Employer,
and thereupon securing the award of such Works or services. For the
avoidance of doubt, it is agreed that the Contractor shall be entitled to
exercise such option only if it has participated in the bidding process and its
Bid does not exceed the first ranked Bid by more than 10% (ten percent)
thereof. It is also agreed that the Contractor shall provide assistance and
cooperation to the person who undertakes the Works or services hereunder,
but shall not be responsible for rectification of any Defects and/ or
Maintenance of Works carried out by other agencies.
13.5.2
The Works undertaken in accordance with this Clause 13.5 shall conform to
the Specifications and Standards and shall be carried out in a manner that
minimises the disruption in operation of the Project Works. The provisions
of this Agreement, insofar as they relate to Works and Tests, shall apply
mutatis mutandis to the Works carried out under this Clause 13.5.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 61
EPC Agreement
ARTICLE 14
14. MAINTENANCE
14.1
14.1.1
The Contractor shall maintain the Project Works for a period of [4 (four)
years] commencing from the date of the Provisional Certificate (the
Maintenance Period). For the performance of its Maintenance
obligations, the Contractor shall be paid a total amount equal to 0.4 % (zero
point four per cent) of the Contract Price for the first year of
Maintenance, and 0.5% (zero point five per cent) of the Contract Price for
the second, third and 0.6% (zero point six per cent) for the fourth year of
Maintenance, inclusive of all Taxes. The amount payable for Maintenance
shall be adjusted to reflect any increase or decrease arising out of variation
in WPI to be determined in accordance with the provisions of Clause 19.12.
For the avoidance of doubt, it is agreed that in the event no Provisional
Certificate is issued, the Maintenance Period shall commence from the date
of the Completion Certificate. It is further agreed that the Contract Price
hereunder shall be reckoned with reference to the amount specified in Clause
19.1.1, which shall be adjusted to the extent of Change of Scope and the
Works withdrawn under the provisions of Clause 8.3.3, but shall not include
any price adjustments in pursuance of Clause 19.10.
14.1.2
14.1.3
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 62
EPC Agreement
The Contractor shall remove promptly from the Project Roads any waste
Materials (including hazardous Materials and waste water), rubbish and
other debris (including, without limitation, accident debris) and keep the
Project Highway in a clean, tidy and orderly condition, and in conformity
with the Applicable Laws, Applicable Permits and Good Industry Practice.
14.2
Maintenance Requirements
The Contractor shall ensure and procure that at all times during the
Maintenance Period; the Project Works conforms to the Maintenance
requirements set forth in Schedule-E (the Maintenance Requirements).
14.3
Maintenance Programme
The Contractor shall prepare a monthly Maintenance Programme (the
Maintenance Programme) in consultation with the Employers Engineer
and submit the same to the Employers Engineer not later than 10 (ten) days
prior to the commencement of the month in which the Maintenance is to be
carried out. For this purpose a joint monthly inspection by the Contractor
and the Employers Engineer shall be undertaken. The Maintenance
Programme shall contain the following:
(a) The condition of the road in the format prescribed by the Employers
Engineer;
(b) the proposed Maintenance Works; and
(c) deployment of resources for Maintenance Works.
14.4
14.4.1
The Contractor shall ensure safe conditions for the Users, and in the event
of unsafe conditions, lane closures, diversions, vehicle breakdowns and
accidents, it shall follow the relevant operating procedures for removal of
obstruction and debris without delay. Such procedures shall conform to the
provisions of this Agreement, Applicable Laws, Applicable Permits and
Good Industry Practice.
14.4.2
The Contractor shall promptly remove any damaged vehicles and debris
from the Project Road to enable safe movement of traffic and shall report
all accidents to the police forthwith.
14.5
14.5.1
The Contractor shall not close any lane of the Project Road/ Utility line for
undertaking Maintenance Works except with the prior written approval of
the Employers Engineer. Such approval shall be sought by the Contractor
through a written request to be made at least 10 (ten) days before the
proposed closure of lane and shall be accompanied by particulars thereof.
Within 5 (five) business days of receiving such request, the Employers
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 63
EPC Agreement
14.5.2
Upon receiving the permission pursuant to Clause 14.5.1, the Contractor shall
be entitled to close the designated lane for the period specified therein, and in
the event of any delay in re-opening such lane, the Contractor shall, for
every stretch of 250 (two hundred and fifty) metres, or part thereof, pay
Damages to the Employer calculated at the rate of 0.1% (zero point one
percent) of the monthly Maintenance payment for each day of delay until
the lane has been re-opened for traffic/public use.
14.6
14.6.1
In the event that the Contractor fails to repair or rectify any Defect or
deficiency set forth in Schedule-E within the period specified therein, it
shall be deemed as failure of performance of Maintenance obligations by
the Contractor and the Employer shall be entitled to effect reduction in
monthly lump sum payment for Maintenance in accordance with Clause
19.7 and Schedule-M, without prejudice to the rights of the Employer under
this Agreement, including Termination thereof.
14.6.2
If the nature and extent of any Defect justifies more time for its repair or
rectification than the time specified in Schedule-E, the Contractor shall be
entitled to additional time in conformity with Good Industry Practice. Such
additional time shall be determined by the Employers Engineer and
conveyed to the Contractor and the Employer with reasons thereof.
14.7
14.8
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 64
EPC Agreement
14.9
14.9.1
14.9.2
In the event that the Contractor, upon notice under Clause 14.9.1, fails to
rectify or remove any hardship or danger within a reasonable period, the
Employer may exercise overriding powers under this Clause 14.9.2 and
take over the performance of any or all the obligations of the Contractor to
the extent deemed necessary by it for rectifying or removing such hardship
or danger; provided that the exercise of such overriding powers by the
Employer shall be of no greater scope and of no longer duration than is
reasonably required hereunder; provided further that any costs and expenses
incurred by the Employer in discharge of its obligations hereunder shall be
recovered by the Employer from the Contractor, and the Employer shall be
entitled to deduct any such costs and expenses incurred from the payments
due to the Contractor under Clause 19.7 for the performance of its
Maintenance obligations.
14.9.3
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 65
EPC Agreement
ARTICLE 15
15. SUPERVISION AND MONITORING DURING MAINTENANCE
15.1
15.1.1
15.1.2
15.2
15.2.1
The Employers Engineer may inspect the Project Works at any time, but
at least once every month, to ensure compliance with the Maintenance
Requirements. It shall make a report of such inspection (Maintenance
Inspection Report) stating in reasonable detail the Defects or
deficiencies, if any, with particular reference to the Maintenance
Requirements, the Maintenance Manual, and the Maintenance Programme,
and send a copy thereof to the Employer and the Contractor within 10 (ten)
days of such inspection.
15.2.2
15.2.3
15.2.4
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 66
15.3
EPC Agreement
Tests
For determining that the Project Works conforms to the Maintenance
Requirements, the Employers Engineer shall require the Contractor to
carry out, or cause to be carried out, Tests specified by it in accordance with
Good Industry Practice. The Contractor shall, with due diligence, carry out
or cause to be carried out all such Tests in accordance with the instructions
of the Employers Engineer and furnish the results of such Tests forthwith
to the Employers Engineer.
15.4
(b)
(c)
(d)
(e)
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 67
EPC Agreement
ARTICLE 16
16. TRAFFIC REGULATION
16.1
16.1.1
The Contractor shall take all the required measures and make arrangements
for the safety of Users during the Construction and Maintenance of the
Project Road or a Section thereof in accordance with the provisions of
MORTH Specifications. It shall provide, erect and maintain all such
barricades, signs, markings, flags, and lights as may be required by Good
Industry Practice for the safety of the traffic passing through the Section
under Construction or Maintenance.
16.1.2
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 68
EPC Agreement
ARTICLE 17
17. DEFECTS LIABILITY
17.1
17.1.1
The Contractor shall be responsible for all the Defects and deficiencies,
except usual wear and tear in the Project Works or any Section thereof, till
the expiry of a period of 4 (four) years commencing from the date of
Provisional Certificate (the Defects Liability Period).Provided that the
Defects Liability Period shall in no case be less than 18 (eighteen) months
from the date of Completion Certificate for and in respect of Works for
which Time Extension was granted. Provided further that in the event no
Provisional Certificate is issued, the Defects Liability Period shall commence
from the date of the Completion Certificate. For the avoidance of doubt,
any repairs or restoration on account of usual wear or tear in the Project
Works or any Section thereof shall form a part of the Maintenance
obligations of the Contractor as specified in Article 14.
17.1.2
17.2
Remedying Defects
Save and except as provided in Clause 14.1.2, the Contractor shall repair or
rectify all Defects and deficiencies observed by the Employers Engineer
during the Defects Liability Period within a period of 15 (fifteen) days
from the date of notice issued by the Employers Engineer in this behalf, or
within such reasonable period as may be determined by the Employers
Engineer at the request of the Contractor, in accordance with Good
Industry Practice.
17.3
17.4
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 69
EPC Agreement
by the Employer from the Contractor and may be deducted by the Employer
from any monies due to the Contractor.
17.5
17.5.1
The Employers Engineer may instruct the Contractor to examine the cause
of any Defect in the Works or part thereof before the expiry of the Defects
Liability Period.
17.5.2
In the event any Defect identified under Clause 17.5.1 is attributable to the
Contractor, the Contractor shall rectify such Defect within the period
specified by the Employers Engineer, and shall bear the cost of the
examination and rectification of such Defect.
17.5.3
17.6
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 70
EPC Agreement
ARTICLE 18
18. Employer S ENGINEER
18.1
18.1.1
18.1.2
18.1.3
18.2
18.2.1
The Employers Engineer shall perform the duties and exercise the
Authority in accordance with the provisions of this Agreement, and
substantially in accordance with the terms of reference (Terms of
Reference or TOR) set forth in Annex 1 of Schedule N, but subject to
obtaining prior written approval of the Employer before determining:
(a) any Time Extension;
(b) any additional cost to be paid by the Employer to the Contractor
(c) the Termination Payment; or
(d) any other matter which is not specified in (a), (b) or (c) above and
which creates an obligation or liability on either Party for a sum
exceeding Rs. 5,000,000 (Rs. fifty lakh).
18.2.2
18.2.3
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 71
EPC Agreement
18.3
18.3.1
18.3.2
18.3.3
18.4
18.4.1
18.4.2
18.4.3
In case the Contractor does not receive the confirmation of the oral
instruction within the time specified in Clause 18.4.2, the Contractor shall
seek the written confirmation of the oral instructions from the Employers
Engineer. The Contractor shall obtain acknowledgment from the
Employers Engineer of the communication seeking written confirmation. In
case of failure of the Employers Engineer or its delegated assistant to reply
to the Contractor within 2 (two) days of the receipt of the communication
from the Contractor, the Contractor may not carry out the instruction.
18.4.4
18.5
18.5.1
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 72
EPC Agreement
with this Agreement having due regard to all relevant circumstances. The
Employers Engineer shall give notice to both the Parties of each
Agreement or determination, with supporting particulars.
18.5.2
18.6
18.7
18.7.1
18.7.2
If the Contractor has reasons to believe that the Employers Engineer is not
discharging its duties and functions in accordance with the provisions of
this Agreement, it may make a written representation to the Employer and
seek Termination of the appointment of the Employers Engineer. Upon
receipt of such representation, the Employer shall hold a tripartite meeting
with the Contractor and Employers Engineer and make best efforts for an
amicable resolution of the representation. In the event that the appointment
of the Employers Engineer is terminated hereunder, the Employer shall
appoint forthwith another Employers Engineer in accordance with Clause
18.1.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 73
EPC Agreement
Part IV
Financial Covenants
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 74
EPC Agreement
ARTICLE 19
19. PAYMENTS
19.1
Contract Price
19.1.1
The Employer shall make payments to the Contractor for the Works on the
basis of the lump sum price accepted by the Employer in consideration of
the obligations specified in this Agreement for an amount of Rs...............
(Rupees..) (the Contract Price),
which shall be subject to adjustments in accordance with the provisions of
this Agreement. For the avoidance of doubt, the Parties expressly agree
that the Contract Price shall not include the cost of Maintenance which shall
be paid separately in accordance with the provisions of Clause 19.7. The
Parties further agree that save and except as provided in this Agreement,
the Contract Price shall be valid and effective until issue of Completion
Certificate.
19.1.2
The Contract Price includes all duties, Taxes, royalty, and fees that may be
levied in accordance with the laws and regulations in force as on the Base
Date on the Contractor's equipment, Plant, Materials and supplies acquired
for the purpose of this Agreement and on the services performed under
this Agreement. Nothing in this Agreement shall relieve the Contractor from
its responsibility to pay any tax including any tax that may be levied in India
on profits made by it in respect of this Agreement.
19.1.3
The Contract Price shall not be adjusted for any change in costs stated in
Clause 19.1.2 above, except as stated in Clauses 19.10 and 19.17.
19.1.4
The Contract Price shall not be adjusted to take account of any unforeseen
difficulties or costs, unless otherwise provided for in this Agreement.
19.1.5
Unless otherwise stated in this Agreement, the Contract Price covers all
the Contractors obligations for the Works under this Agreement and all
things necessary for the Construction and the remedying of any Defects in
the Project Works.
19.1.6
19.2
Advance Payment
19.2.1
The Employer shall make an interest bearing advance @ Bank Rate +5%
per annum (the Advance Payment), equal in amount to 10 (ten) percent of
the Contract Price, for mobilization expenses and for acquisition of
equipment. The Advance Payment shall be made in three installments. The
first installment shall be an amount equal to 2% (two percent) of the
Contract Price, the second installment shall be equal to 3% (three percent) of
the Contract Price, and the third installment shall be equal to 5% (five
percent) of the Contract Price.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 75
EPC Agreement
19.2.2
The Contractor may apply to the Employer for the first installment of the
Advance Payment at any time after the Appointed Date, along with an
irrevocable and unconditional guarantee from a Bank for an amount
equivalent to 110% (one hundred and ten per cent) of such installment,
substantially in the form provided at Annex-III of Schedule-G, to remain
effective till the complete and full repayment thereof.
19.2.3
At any time after 30 (thirty) days from the Appointed Date, the Contractor
may apply for the second installment of the Advance Payment along with an
irrevocable and unconditional guarantee from a Bank for an amount
equivalent to 110% (one hundred and ten per cent) of such installment,
substantially in the form provided at Annex-III of Schedule-G, to remain
effective till the complete and full repayment thereof along with proof of
satisfactory utilization of first installment of Advance Payment.
19.2.4
At any time, after 60 (sixty) days from the Appointed Date, the Contractor
may apply to the Employer for the third installment of the Advance Payment
along with an irrevocable and unconditional guarantee from a Bank for an
amount equivalent to 110% (one hundred and ten per cent) of such
installment, substantially in the form provided at Annex-III of Schedule-G,
to remain effective till the complete and full repayment thereof along
with proof of satisfactory utilization of second installment of the Advance
Payment. No advance shall be given after 40% of the original Contract
amount has been paid.
19.2.5
The first, second and the third installments shall be paid by the Employer to
the Contractor within 15 (fifteen) days of the receipt of its respective
requests in accordance with the provisions of this Clause 19.2.
19.2.6
The recovery of all Advances shall commence when 20% (twenty per
cent) of the original Contract Price of the work has been paid, or at ten
months after the Commencement Date of the Contract whichever is the
earlier, and it will be completed by the time 80% of the original contract
value has been paid or by the time of original Completion Date whichever is
earlier. The recovery of advances shall be limited to 30% (thirty per cent)
of an account bill.
19.2.7
If the Advance Payment has not been full repaid prior to Termination
under Clause 21.7 or Article 23, as the case may be, the whole of the balance
then outstanding including interest shall be immediately become due and
payable by the Contractor to the Employer.
19.3
19.3.1
19.3.2
The Contractor shall base its claim for interim payment for the stages
completed till the end of the month for which the payment is claimed, valued
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 76
EPC Agreement
Any reduction in the Contract Price arising out of Change of Scope or the
Works withdrawn under Clause 8.3 shall not affect the amounts payable
for the items or stage payments thereof which are not affected by such
Change of Scope or withdrawal. For avoidance of doubt and by way of
illustration, the Parties agree that if the amount assigned to Major Bridges is
reduced from Rs.100 crore to Rs. 80 crore owing to Change of Scope or
withdrawal of work, the reduction in payment shall be restricted to relevant
payments for Major Bridges only and the payment due in respect of all other
stage payments under the item Major Bridges shall not be affected in any
manner. The Parties further agree that the adjustments arising out of the
aforesaid modifications shall be carried out in a manner that the impact of
such modifications is restricted to the said Change of Scope or withdrawal,
as the case may be, and does not alter the payments due for and in respect
of items or stage payments which do not form part of such Change of Scope
or withdrawal.
19.4
19.5
19.5.1
19.5.2
19.5.3
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 77
19.5.4
EPC Agreement
19.5.5
19.6
19.6.1
19.6.2
The monthly lump sum amount payable for Maintenance shall be 1/12th
(one-twelfth) of the annual cost of Maintenance as specified in Clause
14.1.1.
19.7
19.7.1
19.7.2
19.7.3
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 78
EPC Agreement
19.7.4
The Employer shall pay to the Contractor every quarter any amount due
under a n y IPC under this Clause 19.7. The payment shall be made no
later than 30 (thirty) days from the date of submission of the last IPC for
the relevant quarter.
19.8
Payment of Damages
19.8.1
19.8.2
The Employers Engineer shall issue the IPC within 15 (fifteen) days of
the receipt of the claim under Clause 19.8.1, after making adjustments in
accordance with the provisions of this Agreement. The Employer shall pay to
the Contractor the amount due under any IPC within a period of 30 (thirty)
days from the date of the submission of the claim under this Clause 19.8. In
the event of the failure of the Employer to make payment to the Contractor
within the specified time, the Employer shall be liable to pay to the
Contractor interest thereon and the provisions of Clause 19.9 shall apply
mutatis mutandis thereto.
19.9
19.9.1
The Employer shall pay to the Contractor any amount due under any
payment certificate issued by the Employers Engineer in accordance with
the provisions of this Article 19, or in accordance with any other clause of
this Agreement as follows:
(a) payment shall be made no later than 30 (thirty) days from the date of
submission of the Stage Payment Statement by the Contractor to the
Employers Engineer for certification in accordance with the
provisions of Clause 19.4 for an IPC; provided that, in the event
the IPC is not issued by the Employers Engineer within the
aforesaid period of 30 (thirty) days, the Employer shall pay the
amount shown in the Contractors Stage Payment Statement and
any discrepancy therein shall be added to, or deducted from, the next
payment certificate issued to the Contractor; and
(b) payment shall be made no later than 30 (thirty) days from the date of
submission of the Final Payment Certificate for Works along with
the discharge submitted to the Employers Engineer in accordance
with the provisions of Clause 19.15 for certification.
19.9.2
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 79
EPC Agreement
19.10
19.10.1
19.10.2
19.10.3
To the extent that full compensation for any increase or decrease in costs to
the Contractor is not covered by the provisions of this or other Clauses in
this Agreement, the costs and prices payable under this Agreement shall be
deemed to include the amounts required to cover the contingency of such
other increase or decrease of costs and prices.
19.10.4
The Contract Price shall be adjusted for increase or decrease in rates and
price of labour, cement, steel, Plant, machinery and spares, bitumen, fuel and
lubricants, and other Material inputs in accordance with the principles,
procedures and formulae specified below:
(a) price adjustment shall be applied on completion of the specified stage
of the respective item of work in accordance with Schedule-H;
(b) The following expressions and meanings are assigned to the value of
the work done:
(c) Price adjustment for changes in cost shall be paid in accordance with
the following formula:
PV=0.85 R X (UI-UO)/UO
Where
R=
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 80
EPC Agreement
19.11
19.11.1
Price adjustment shall be due and payable only in respect of the stages of
Works for which the Stage Payment Statement has been submitted by the
Contractor no later than 30 (thirty) days from the date of the applicable
Project Milestone or the Scheduled Completion Date, as the case may be,
including any Time Extension granted therefor in accordance with the
provisions of this Agreement. For the avoidance of doubt, in the event of
submission of any Stage Payment Statement after the period specified
herein, price adjustment shall be applicable until the date of the respective
Project Milestone or the Scheduled Completion Date, as the case may be.
19.12
P X (WI-WO)/WO
V=
P=
19.13
19.13.1
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 81
EPC Agreement
19.14
Discharge
19.14.1
Upon submission of the Final Payment Statement for Works under Clause
19.13, the Contractor shall give to the Employer, with a copy to the
Employers Engineer, a written discharge confirming that the total of the
Final Payment Statement represents full and final settlement of all monies
due to the Contractor in respect of this Agreement for all the Works
arising out of this Agreement, except for any monies due to either Party on
account of any Defect. Provided that such discharge shall become effective
only after the payment due has been made in accordance with the Final
Payment Certificate issued pursuant to Clause 19.15.
19.15
19.15.1
Within 30 (thirty) days after receipt of the Final Payment Statement for
Works under Clause 19.13, and the written discharge under Clause 19.14,
and there being no Disputed items of claim, the Employers Engineer shall
deliver to the Employer, with a copy to the Contractor, a final payment
certificate (the Final Payment Certificate) stating the amount which, in
the opinion of the Employers Engineer, is finally due under this
Agreement or otherwise. For the avoidance of doubt, before issuing the
Final Payment Certificate, the Employers Engineer shall ascertain from
the Employer all amounts previously paid by the Employer and for all
sums to which the Employer is entitled, the balance, if any, due from the
Employer to the Contractor or from the Contractor to the Employer, as the
case may be.
19.15.2
The Employer shall, in accordance with the provisions of Clause 19.9, pay to
the Contractor the amount which is stated as being finally due in the Final
Payment Certificate.
19.16
19.16.1
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 82
EPC Agreement
documents showing the details set forth below in the form prescribed by
the Employers Engineer
(a) the total amount claimed in accordance with the monthly statement
for Maintenance of Project Works;
(b) the amount paid in accordance with the Interim Payment
Certificates; and
(c) any sums which the Contractor considers to be due to it, with
supporting documents.
19.16.2
19.16.3
If the Employers Engineer does not prescribe the form within 15 (fifteen)
days of the date of issue of the Completion Certificate, the Contractor shall
submit the statement in such form as it deems fit.
19.17
Change in laws
19.17.1
19.17.2
19.17.3
The Employers Engineer shall, within 15 (fifteen) days from the date of
receipt of the notice from the Contractor or the Employer, determine any
addition or reduction to the Contract Price, as the case may be, due to the
Change in Law.
19.18
19.19
Employers claims
If the Employer considers itself to be entitled to any payment from the
Contractor under any Clause of this Agreement, it shall give notice and
particulars to the Contractor 20 (twenty) days before making the recovery
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 83
EPC Agreement
from any amount due to the Contractor, and shall take into consideration
the representation, if any, made by the Contractor in this behalf, before
making such recovery.
19.20
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 84
EPC Agreement
ARTICLE 20
20. INSURANCE
20.1
20.1.1
The Contractor shall effect and maintain at its own cost the insurances
specified in Schedule-P and as per the requirements under the Applicable
Laws.
20.1.2
Subject to the provisions of Clause 21.6, the Employer and the Contractor
shall, in accordance with its obligations as provided for in this Agreement,
be liable to bear the cost of any loss or damage that does not fall within the
scope o f this Article 20 or cannot be recovered from the insurers.
20.1.3
20.1.4
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 85
EPC Agreement
20.1.5
20.1.6
20.2
20.3
20.3.1
20.3.2
The Contractor shall ensure the adequacy of the insurances at all times in
accordance with the provisions of this Agreement.
20.4
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 86
20.5
EPC Agreement
Waiver of subrogation
All insurance policies in respect of the insurance obtained by the Contractor
pursuant to this Article 20 shall include a waiver of any and all rights of
subrogation or recovery of the insurers thereunder against, inter alia, the
Employer, and its assigns, successors, undertakings and their subsidiaries,
Affiliates, employees, insurers and underwriters, and of any right of the
insurers to any set-off or counterclaim or any other deduction, whether by
attachment or otherwise, in respect of any liability of any such person
insured under any such policy or in any way connected with any loss,
liability or obligation covered by such policies of insurance.
20.6
Contractors waiver
The Contractor hereby further releases, assigns and waives any and all rights
of subrogation or recovery against, inter alia, the Employer and its assigns,
undertakings and their subsidiaries, Affiliates, employees, successors,
insurers and underwriters, which the Contractor may otherwise have or
acquire in or from or in any way connected with any loss, liability or
obligation covered by policies of insurance maintained or required to be
maintained by the Contractor pursuant to this Agreement (other than third
party liability insurance policies) or because of deductible clauses in or
inadequacy of limits of any such policies of insurance.
20.7
Cross liabilities
Any such insurance maintained or effected in pursuance of this Article 20
shall include a cross liability clause such that the insurance shall apply to the
Contractor and to the Employer as separately insured.
20.8
20.9
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 87
EPC Agreement
20.10
20.11
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 88
EPC Agreement
Part V
Force Majeure and Termination
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 89
EPC Agreement
ARTICLE 21
21. FORCE MAJEURE
21.1
Force Majeure
As used in this Agreement, the expression Force Majeure or Force
Majeure Event shall mean occurrence in India of any or all of Non- Political
Event, Indirect Political Event and Political Event, as defined in Clauses
21.2, 21.3 and 21.4 respectively, if it affects the performance by the Party
claiming the benefit of Force Majeure (the Affected Party) of its
obligations under this Agreement and which act or event (i) is beyond the
reasonable control of the Affected Party, and (ii) the Affected Party could
not have prevented or overcome by exercise of due diligence and following
Good Industry Practice, and (iii) has Material Adverse Effect on the Affected
Party.
21.2
Non-Political Event
A Non-Political Event shall mean one or more of the following acts or
events:
(a) act of God, epidemic, extremely adverse weather conditions,
lightning, earthquake, landslide, cyclone, flood, volcanic eruption,
chemical or radioactive contamination or ionising radiation, fire or
explosion (to the extent of contamination or radiation or fire or
explosion originating from a source external to the Site);
(b) strikes or boycotts (other than those involving the Contractor,
Subcontractors or their respective employees/representatives, or
attributable to any act or omission of any of them) interrupting
supplies and services to the Project Works for a continuous period
of 24 (twenty-four) hours and an aggregate period exceeding 10
(ten) days in an Accounting Year, and not being an Indirect
Political Event set forth in Clause 21.3;
(c) any failure or delay of a Sub-contractor but only to the extent
caused by another Non-Political Event;
(d) any judgment or order of any court of competent jurisdiction or
statutory Employer made against the Contractor in any
proceedings for reasons other than (i) failure of the Contractor to
comply with any Applicable Law or Applicable Permit, or (ii) on
account of breach of any Applicable Law or Applicable Permit or
of any contract, or (iii) enforcement of this Agreement, or (iv)
exercise of any of its rights under this Agreement by the Employer;
(e) the discovery of geological conditions, toxic contamination or
archaeological remains on the Site that could not reasonably have
been expected to be discovered through a Site inspection; or
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 90
21.3
EPC Agreement
21.4
Political Event
A Political Event shall mean one or more of the following acts or events by
or on account of any Government Instrumentality:
(a) Change in Law, only if consequences thereof cannot be dealt
with under and in accordance with the provisions of Clause 19.17;
(b) compulsory acquisition in national interest or expropriation of
any Project Assets or rights of the Contractor or of the SubContractors;
(c) unlawful or unauthorized or without jurisdiction revocation of, or
refusal to renew or grant without valid cause, any clearance,
license, permit, authorization, no objection certificate, consent,
approval or exemption required by the Contractor or any of the
Sub-contractors to perform their respective obligations under this
Agreement; provided that such delay, modification, denial, refusal
or revocation did not result from the Contractors or any Subcontractors inability or failure to comply with any condition
relating to grant, Maintenance or renewal of such clearance,
license, authorization, no objection certificate, exemption, consent,
approval or permit;
(d) any failure or delay of a Sub-contractor but only to the extent
caused by another Political Event;
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 91
EPC Agreement
21.5
21.5.1
21.5.2
The Affected Party shall not be entitled to any relief for or in respect of a
Force Majeure Event unless it shall have notified the other Party of the
occurrence of the Force Majeure Event as soon as reasonably practicable,
and in any event no later than 10 (ten) days after the Affected Party knew, or
ought reasonably to have known, of its occurrence, and shall have given
particulars of the probable Material effect that the Force Majeure Event is
likely to have on the performance of its obligations under this Agreement.
21.5.3
21.6
21.6.1
Upon the occurrence of any Force Majeure after the Appointed Date, the
costs incurred and attributable to such event and directly relating to this
Agreement (the Force Majeure costs) shall be allocated and paid as
follows:
(a) upon occurrence of a Non-Political Event, the Parties shall bear
their respective Force Majeure costs and neither Party shall be
required to pay to the other Party any costs thereof;
(b) upon occurrence of an Indirect Political Event, all Force Majeure
costs attributable to such Indirect Political Event, and not
exceeding the Insurance Cover for such Indirect Political Event,
shall be borne by the Contractor, and to the extent Force Majeure
costs exceed such Insurance Cover, one half of such excess amount
shall be reimbursed by the Employer to the Contractor for the
Force Majeure events; and
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 92
EPC Agreement
21.6.2
Save and except as expressly provided in this Article 21, neither Party shall
be liable in any manner whatsoever to the other Party in respect of any loss,
damage, cost, expense, claims, demands and proceedings relating to or
arising out of occurrence or existence of any Force Majeure Event or
exercise of any right pursuant hereto.
21.6.3
21.7
21.8
21.8.1
21.8.2
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 93
EPC Agreement
21.8.3
21.9
Dispute resolution
In the event that the Parties are unable to agree in good faith about the
occurrence or existence of a Force Majeure Event, such Dispute shall be
finally settled in accordance with the Dispute Resolution Procedure;
provided that the burden of proof as to the occurrence or existence of
such Force Majeure Event shall be upon the Party claiming relief and/or
excuse on account of such Force Majeure Event.
21.10
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 94
EPC Agreement
ARTICLE 22
22. SUSPENSION OF CONTRACTORS RIGHTS
22.1
22.2
22.3
Revocation of Suspension
22.3.1
In the event that the Employer shall have rectified or removed the cause of
Suspension within a period not exceeding 60 (sixty) days from the date of
Suspension, it shall revoke the Suspension forthwith and restore all rights of
the Contractor under this Agreement. For the avoidance of doubt, the Parties
expressly agree that the Employer may, in its discretion, revoke the
Suspension at any time, whether or not the cause of Suspension has been
rectified or removed hereunder.
22.3.2
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 95
22.4
22.4.1
22.4.2
EPC Agreement
Termination
At any time during the period of Suspension under this Article 22, the
Contractor may by notice require the Employer to revoke the Suspension and
issue a Termination Notice. The Employer shall, within 15 (fifteen) days of
receipt of such notice, terminate this Agreement under and in accordance
with Article 23.
Notwithstanding anything to the contrary contained in this Agreement, in
the event that Suspension is not revoked within 90 (ninety) days from the
date of Suspension hereunder, the Agreement shall, upon expiry of the
aforesaid period, be deemed to have been terminated by mutual
Agreement of the Parties and all the provisions of this Agreement shall
apply, mutatis mutandis, to such Termination as if a Termination Notice had
been issued by the Employer upon occurrence of a Contractor Default.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 96
EPC Agreement
ARTICLE 23
23. TERMINATION
23.1
23.1.1
Save as otherwise provided in this Agreement, in the event that any of the
defaults specified below shall have occurred, and the Contractor fails to cure
the default within the Cure Period set forth below, or where no Cure Period
is specified, then within a Cure Period of 60 (sixty) days, the Contractor shall
be deemed to be in default of this Agreement (the Contractor Default),
unless the default has occurred solely as a result of any breach of this
Agreement by the Employer or due to Force Majeure. The defaults
referred to herein shall include:
(a) the Contractor fails to provide, extend or replenish, as the case
may be, the Performance Security in accordance with this
Agreement;
(b) subsequent to the replenishment or furnishing of fresh Performance
Security in accordance with Clause 7.3, the Contractor fails to cure,
within a Cure Period of 30 (thirty) days, the Contractor Default for
which the whole or part of the Performance Security was
appropriated;
(c) the Contractor does not achieve the latest outstanding Project
Milestone due in accordance with the provisions of Schedule-J,
subject to any Time Extension, and continues to be in default for
45 (forty five) days;
(d) the Contractor abandons or manifests intention to abandon the
Construction or Maintenance of the Project Works without the
prior written consent of the Employer;
(e) the Contractor fails to proceed with the Works in accordance with
the provisions of Clause 10.1 or stops Works and/or the
Maintenance for 30 (thirty) days without reflecting the same in the
current Programme and such stoppage has not been authorized by
the Employers Engineer;
(f) the Project Completion Date does not occur within the period
specified in Schedule-J for the Scheduled Completion Date, or any
extension thereof;
(g) failure to complete the Punch List items within the periods
stipulated therefore in Clause 12.2.1;
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 97
EPC Agreement
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 98
EPC Agreement
23.1.2
23.1.3
23.2
23.2.1
In the event that any of the defaults specified below shall have occurred, and
the Employer fails to cure such default within a Cure Period of 90 (ninety)
days or such longer period as has been expressly provided in this
Agreement, the Employer shall be deemed to be in default of this Agreement
(the Employer Default) unless the default has occurred as a result of any
breach of this Agreement by the Contractor or due to Force Majeure. The
defaults referred to herein shall include:
(a) the Employer commits a Material default in complying with any of
the provisions of this Agreement and such default has a Material
Adverse Effect on the Contractor;
(b) the Employer has failed to make payment of any amount due and
payable to the Contractor within the period specified in this
Agreement;
(c) the Employer has failed to provide, within a period of 180 (one
hundred and eighty) days from the Appointed Date, the
environmental clearances required for Construction of the Project
Works;
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 99
EPC Agreement
Without prejudice to any other right or remedy which the Contractor may
have under this Agreement, upon occurrence of an Employer Default, the
Contractor shall be entitled to terminate this Agreement by issuing a
Termination Notice to the Employer; provided that before issuing the
Termination Notice, the Contractor shall by a notice inform the Employer of
its intention to issue the Termination Notice and grant 15 (fifteen) days to
the Employer to make a representation, and may after the expiry of such
15 (fifteen) days, whether or not it is in receipt of such representation, issue
the Termination Notice.
23.3
23.4
23.5
23.5.1
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 100
EPC Agreement
(a) value of the completed stage of the Works, less payments already
made;
(b) reasonable value of the partially completed stages of Works as on
the date of Termination, only if such Works conform with the
Specifications and Standards; and
(c) value of Maintenance, if any, for completed months, less payments
already made,
and shall adjust from the sum thereof (i) any other amounts payable or
recoverable, as the case may be, in accordance with the provisions of this
Agreement; and (ii) all Taxes due to be deducted at source.
23.5.2
23.6
Termination Payment
23.6.1
23.6.2
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 101
EPC Agreement
(ii)
and shall adjust from the sum thereof (i) any other amounts payable or
recoverable, as the case may be, in accordance with the provisions of this
Agreement, and (ii) all Taxes due to be deducted at source.
23.6.3
23.6.4
23.7
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 102
23.8
EPC Agreement
Survival of rights
Notwithstanding anything to the contrary contained in this Agreement any
Termination pursuant to the provisions of this Agreement shall be without
prejudice to the accrued rights of either Party including its right to claim and
recover money damages, insurance proceeds, security deposits, and other
rights and remedies, which it may have in law or Agreement. All rights and
obligations of either Party under this Agreement, including Termination
Payments, shall survive the Termination to the extent such survival is
necessary for giving effect to such rights and obligations.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 103
EPC Agreement
Part VI
Other Provisions
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 104
EPC Agreement
ARTICLE 24
24. ASSIGNMENT AND CHARGES
24.1
24.2
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 105
EPC Agreement
ARTICLE 25
25. LIABILITY AND INDEMNITY
25.1
General indemnity
The Contractor will indemnify, defend, save and hold harmless the Employer
and its officers, servants, agents, Government Instrumentality and
Government owned and/or controlled entities/enterprises, (the Employer
Indemnified Persons) against any and all suits, proceedings, actions,
demands and third party claims for any loss, damage, cost and expense of
whatever kind and nature, whether arising out of any breach by the
Contractor of any of its obligations under this Agreement or from any
negligence under the Agreement, including any errors or deficiencies in the
design documents, or
tort or on any other ground whatsoever, except
to the extent that any such suits, proceedings, actions, demands and
claims have arisen due to any negligent act or omission, or breach or default
of this Agreement on the part of the Employer Indemnified Persons.
25.2
25.2.1
Without limiting the generality of Clause 25.1, the Contractor shall fully
indemnify, hold harmless and defend the Employer and the Employer
Indemnified Persons from and against any and all loss and/or damages
arising out of or with respect to:
(a) failure of the Contractor to comply with Applicable Laws and
Applicable Permits;
(b) payment of Taxes required to be made by the Contractor in
respect of the income or other Taxes of the Sub-contractors,
suppliers and representatives; or
(c) non-payment of amounts due as a result of Materials or services
furnished to the Contractor or any of its Sub-contractors which
are payable by the Contractor or any of its Sub-contractors.
25.2.2
Without limiting the generality of the provisions of this Article 25, the
Contractor shall fully indemnify, hold harmless and defend the Employer
Indemnified Persons from and against any and all suits, proceedings,
actions, claims, demands, liabilities and damages which the Employer
Indemnified Persons may hereafter suffer, or pay by reason of any demands,
claims, suits or proceedings arising out of claims of infringement of any
domestic or foreign patent rights, copyrights or other Intellectual Propoerty,
proprietary or confidentiality rights with respect to any6 Materials,
information, design or process used by the Contractor or by the Subcontractors in performing the Contractors obligations or in any way
incorporated in or related to the Project. If in any such suit, action, claim or
proceedings, a temporary restraint order or preliminary injunction is
granted, the Contractor shall make every reasonable effort, by giving a
satisfactory bond or otherwise, to secure the revocation or Suspension of
the injunction or restraint order. If, in any such suit, action, claim or
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 106
EPC Agreement
25.3
25.4
Defence of claims
25.4.1
The Indemnified Party shall have the right, but not the obligation, to contest,
defend and litigate any claim, action, suit or proceeding by any third party
alleged or asserted against such Party in respect of, resulting from, related to
or arising out of any matter for which it is entitled to be indemnified
hereunder, and reasonable costs and expenses thereof shall be indemnified by
the Indemnifying Party. If the Indemnifying Party acknowledges in writing
its obligation to indemnify the Indemnified Party in respect of loss to the full
extent provided by this Article 25, the Indemnifying Party shall be entitled,
at its option, to assume and control the defence of such claim, action, suit or
proceeding, liabilities, payments and obligations at its expense and through
the counsel of its choice; provided it gives prompt notice of its intention to
do so to the Indemnified Party and reimburses the Indemnified Party for the
reasonable cost and expenses incurred by the Indemnified Party prior to the
assumption by the Indemnifying Party of such defence. The Indemnifying
Party shall not be entitled to settle or compromise any claim, demand,
action, suit or proceeding without the prior written consent of the
Indemnified Party, unless the Indemnifying Party provides such security to
the Indemnified Party as shall be reasonably required by the Indemnified
Party to secure the loss to be indemnified hereunder to the extent so
compromised or settled.
25.4.2
If the Indemnifying Party has exercised its rights under Clause 25.3, the
Indemnified Party shall not be entitled to settle or compromise any
claim, action, suit or proceeding without the prior written consent of the
Indemnifying Party (which consent shall not be unreasonably withheld or
delayed).
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 107
EPC Agreement
25.4.3
If the Indemnifying Party exercises its rights under Clause 25.3, the
Indemnified Party shall nevertheless have the right to employ its own
counsel, and such counsel may participate in such action, but the fees and
expenses of such counsel shall be at the expense of the Indemnified Party,
when and as incurred, unless:
(a) the employment of counsel by such party has been authorized in
writing by the Indemnifying Party; or
(b) the Indemnified Party shall have reasonably concluded that there
may be a conflict of interest between the Indemnifying Party and
the Indemnified Party in the conduct of the defence of such
action; or
(c) the Indemnifying Party shall not, in fact, have employed
independent counsel reasonably satisfactory to the Indemnified
Party, to assume the defence of such action and shall have been
so notified by the Indemnified Party; or
(d) the Indemnified Party shall have reasonably concluded and
specifically notified the Indemnifying Party either:
i.
ii.
Provided that if Sub-clauses (b), (c) or (d) of this Clause 25.4.3 shall be
applicable, the counsel for the Indemnified Party shall have the right to
direct the defence of such claim, demand, action, suit or proceeding on
behalf of the Indemnified Party, and the reasonable fees and disbursements
of such counsel shall constitute legal or other expenses hereunder.
25.5
No consequential claims
Notwithstanding anything to the contrary contained in this Article 25, the
indemnities herein provided shall not include any claim or recovery in
respect of any cost, expense, loss or damage of an indirect, incidental or
consequential nature, including loss of profit, except as expressly provided in
this Agreement.
25.6
Survival on Termination
The provisions of this Article 25 shall survive Termination.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 108
EPC Agreement
ARTICLE 26
26. DISPUTE RESOLUTION
26.1
Dispute Resolution
26.1.1
26.1.2
The Parties agree to use their best efforts for resolving all Disputes arising
under or in respect of this Agreement promptly, equitably and in good
faith, and further agree to provide each other with reasonable access during
normal business hours to all non-privileged records, information and data
pertaining to any Dispute.
26.2
Conciliation
In the event of any Dispute between the Parties, either Party may call upon
the Employers Engineer, or such other person as the Parties may mutually
agree upon (the Conciliator) to mediate and assist the Parties in arriving
at an amicable settlement thereof. Failing mediation by the Conciliator or
without the intervention of the Conciliator, either Party may require such
Dispute to be referred to the Managing Director of the Employer and the
Chairman of the Board of Directors of the Contractor for amicable
settlement, and upon such reference, the said persons shall meet no later than
7 (seven) business days from the date of reference to discuss and attempt to
amicably resolve the Dispute. If such meeting does not take place within
the 7 (seven) business day period or the Dispute is not amicably settled
within 15 (fifteen) days of the meeting or the Dispute is not resolved as
evidenced by the signing of written terms of settlement within 30 (thirty)
days of the notice in writing referred to in Clause 26.1.1 or such longer
period as may be mutually agreed by the Parties, either Party may refer the
Dispute to arbitration in accordance with the provisions of Clause 26.3.
26.3
26.3.1
Arbitration
Any Dispute which is not resolved amicably by conciliation, as provided in
Clause 26.2, shall be finally decided by reference to arbitration by a Board of
Arbitrators appointed in accordance with Clause 26.3.2. Such arbitration
shall be held in accordance with the Rules of Arbitration of the International
Centre for Alternative Dispute Resolution, New Delhi (the Rules), or such
other rules as may be mutually agreed by the Parties, and shall be subject to
the provisions of the Arbitration Act. The venue of such arbitration shall be
[Mumbai], and the language of arbitration proceedings shall be English.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 109
EPC Agreement
26.3.2
There shall be a Board of three arbitrators, of whom each Party shall select
one, and the third arbitrator shall be appointed by the two arbitrators so
selected and in the event of disAgreement between the two arbitrators, the
appointment shall be made in accordance with the Rules.
26.3.3
The arbitrators shall make a reasoned award (the Award). Any Award
made in any arbitration held pursuant to this Article 26 shall be final and
binding on the Parties as from the date it is made, and the Contractor and
the Employer agree and undertake to carry out such Award without delay.
26.3.4
The Contractor and the Employer agree that an Award may be enforced
against the Contractor and/or the Employer, as the case may be, and their
respective assets wherever situated.
26.3.5
This Agreement and the rights and obligations of the Parties shall remain in
full force and effect, pending the Award in any arbitration proceedings
hereunder.
26.3.6
In the event the Party against whom the Award has been granted challenges
the Award for any reason in a court of law, it shall make an interim
payment to the other Party for an amount equal to 75% (seventy five per
cent) of the Award, pending final settlement of the Dispute. The aforesaid
amount shall be paid forthwith upon furnishing an irrevocable Bank
Guarantee for a sum equal to 120 % (one hundred and twenty per cent) of the
aforesaid amount. Upon final settlement of the Dispute, the aforesaid interim
payment shall be adjusted and any balance amount due to be paid or
returned, as the case may be, shall be paid or returned with interest calculated
at the rate of 10% (ten per cent) per annum from the date of interim payment
to the date of final settlement of such balance.
26.4
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 110
EPC Agreement
ARTICLE 27
27. MISCELLANEOUS
27.1
27.2
Waiver of immunity
Each Party unconditionally and irrevocably:
a) agrees that the execution, delivery and performance by it of this
Agreement constitute commercial acts done and performed for
commercial purpose;
b) agrees that, should any proceedings be brought against it or its
assets, property or revenues in any jurisdiction in relation to this
Agreement or any transaction contemplated by this Agreement, no
immunity (whether by reason of sovereignty or otherwise) from
such proceedings shall be claimed by or on behalf of the Party with
respect to its assets;
c) waives any right of immunity which it or its assets, property or
revenues now has, may acquire in the future or which may be
attributed to it in any jurisdiction; and
d) consents generally in respect of the enforcement of any judgement
or award against it in any such proceedings to the giving of any
relief or the issue of any process in any jurisdiction in connection
with such proceedings (including the making, enforcement or
execution against it or in respect of any assets, property or revenues
whatsoever irrespective of their use or intended use of any order or
judgement that may be made or given in connection therewith).
27.3
Delayed payments
The Parties hereto agree that payments due from one Party to the other
Party under the provisions of this Agreement shall be made within the
period set forth therein, and if no such period is specified, within 30
(thirty) days of receiving a demand along with the necessary particulars. In
the event of delay beyond such period, the defaulting Party shall pay
interest for the period of delay calculated at a rate equal to Base Rate plus 2
(two) percent, calculated at quarterly rests, and recovery thereof shall be
without prejudice to the rights of the Parties under this Agreement
including Termination thereof.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 111
27.4
27.4.1
EPC Agreement
Waiver
Waiver, including partial or conditional waiver, by either Party of any
default by the other Party in the observance and performance of any
provision of or obligations under this Agreement:(a) shall not operate or be construed as a waiver of any other or
subsequent default hereof or of other provisions of or obligations
under this Agreement;
(b) shall not be effective unless it is in writing and executed by a duly
authorized representative of the Party; and
(c) shall not affect the validity or enforceability of this Agreement in
any manner.
27.4.2
Neither the failure by either Party to insist on any occasion upon the
performance of the terms, conditions and provisions of this Agreement or
any obligation thereunder nor time or other indulgence granted by a Party to
the other Party shall be treated or deemed as waiver of such breach or
acceptance of any variation or the relinquishment of any such right
hereunder.
27.5
27.6
27.7
Survival
27.7.1
Termination shall:
(a) not relieve the Contractor or the Employer, as the case may be, of any
obligations hereunder which expressly or by implication survive
Termination hereof; and
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 112
EPC Agreement
27.7.2
27.8
Entire Agreement
This Agreement and the Schedules together constitute a complete and
exclusive statement of the terms of the Agreement between the Parties on
the subject hereof, and no amendment or modification hereto shall be valid
and effective unless such modification or amendment is agreed to in
writing by the Parties and duly executed by persons especially empowered in
this behalf by the respective Parties. All prior written or oral understandings,
offers or other communications of every kind pertaining to this Agreement
are abrogated and withdrawn. For the avoidance of doubt, the Parties hereto
agree that any obligations of the Contractor arising from the Request for
Qualification or Request for Proposals, as the case may be, shall be deemed
to form part of this Agreement and treated as such.
27.9
Severability
If for any reason whatever, any provision of this Agreement is or becomes
invalid, illegal or unenforceable or is declared by any court of competent
jurisdiction or any other instrumentality to be invalid, illegal or
unenforceable, the validity, legality or enforceability of the remaining
provisions shall not be affected in any manner, and the Parties will
negotiate in good faith with a view to agreeing to one or more provisions
which may be substituted for such invalid, unenforceable or illegal
provisions, as nearly as is practicable to such invalid, illegal or
unenforceable provision. Failure to agree upon any such provisions shall
not be subject to the Dispute Resolution Procedure set forth under this
Agreement or otherwise.
27.10
No partnership
This Agreement shall not be interpreted or construed to create an association,
joint venture or partnership between the Parties, or to impose any partnership
obligation or liability upon either Party, and neither Party shall have any
right, power or Employer to enter into any Agreement or undertaking for, or
act on behalf of, or to act as or be an agent or representative of, or to
otherwise bind, the other Party.
27.11
Third Parties
This Agreement is intended solely for the benefit of the Parties, and their
respective successors and permitted assigns, and nothing in this Agreement
shall be construed to create any duty to, standard of care with reference to, or
any liability to, any person not a Party to this Agreement.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 113
27.12
EPC Agreement
27.13
Notices
Any notice or other communication to be given by any Party to the other
Party under or in connection with the matters contemplated by this
Agreement shall be in writing and shall:
(a) in the case of the Contractor, be given by facsimile or e-mail and by
letter delivered by hand to the address given and marked for attention of
the person set out below or to such other person as the Contractor may
from time to time designate by notice to the Employer; provided that
notices or other communications to be given to an address outside
[Aurangabad] may, if they are subsequently confirmed by sending a copy
thereof by registered acknowledgement due, air mail or by courier, be
sent by facsimile or e-mail to the person as the Contractor may from time
to time designate by notice to the Employer; [***]
(b) in the case of the Employer, be given by facsimile or e-mail and by letter
delivered by hand and be addressed to the [Managing Director] of the
Employer with a copy delivered to the Employer Representative or such
other person as the Employer may from time to time designate by notice
to the Contractor; provided that if the Contractor does not have an office
in [Aurangabad] it may send such notice by facsimile or email and by
registered acknowledgement due, air mail or by courier; and
(c) any notice or communication by a Party to the other Party, given in
accordance herewith, shall be deemed to have been delivered when in the
normal course of post it ought to have been delivered and in all other
cases, it shall be deemed to have been delivered on the actual date and
time of delivery; provided that in the case of facsimile or email, it shall
be deemed to have been delivered on the working day following the date
of its delivery.
27.14
Language
All notices required to be given by one Party to the other Party and all
other communications, Documentation and proceedings which are in any
way relevant to this Agreement shall be in writing and in English
language.
27.15
Counterparts
This Agreement may be executed in two counterparts, each of which,
when executed and delivered, shall constitute an original of this Agreement.
27.16
Confidentiality
The Parties shall treat the details of this Agreement as private and
confidential, except to the extent necessary to carry out obligations under it
or to comply with Applicable Laws. The Contractor shall not publish, permit
to be published, or disclose any particulars of the Works in any trade or
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 114
EPC Agreement
27.17
27.17.1
As between the Parties, the Contractor shall retain the copyright and other
Intellectual Propoerty rights in the Contractor's Documents and other design
documents made by (or on behalf of) the Contractor. The Contractor shall
be deemed (by signing this Agreement) to give to the Employer a
nonterminable transferable non-exclusive royalty-free licence to copy, use
and communicate the Contractor's Documents, including making and using
modifications of them. This licence shall:
(a) apply throughout the actual or intended working life (whichever is
longer) of the relevant parts of the Works,
(b) entitle any person in proper possession of the relevant part of the Works
to copy, use and communicate the Contractor's Documents for the
purposes of completing, operating, maintaining, altering, adjusting,
repairing and demolishing the Works, and
(c) in the case of Contractor's Documents which are in the form of computer
programs and other software, permit their use on any computer on the
Site and other places as envisaged by this Agreement, including
replacements of any computers supplied by the Contractor:
27.17.2
27.17.3
As between the Parties, the Employer shall retain the copyright and other
Intellectual Propoerty rights in this Agreement and other documents made
by (or on behalf of) the Employer. The Contractor may, at its cost, copy, use,
and obtain communication of these documents for the purposes of this
Agreement. They shall not, without the Employer's consent, be copied,
used or communicated to a third party by the Contractor, except as necessary
for the purposes of the contract.
27.18
Limitation of Liability
27.18.1
Neither Party shall be liable to the other Party for loss of use of any Works,
loss of profit, loss of any contract or for any indirect or consequential loss or
damage which may be suffered by the other Party in connection with this
Agreement, save and except as provided under Articles 23 and 25.
27.18.2
The total liability of one Party to the other Party under and in accordance
with the provisions of this Agreement, save and except as provided in
Articles 23 and 25, shall not exceed the Contract Price. For the avoidance
of doubt, this Clause shall not limit the liability in any case of fraud,
deliberate default or reckless misconduct by the defaulting Party.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 115
EPC Agreement
ARTICLE 28
28. DEFINITIONS
28.1
Definitions
In this Agreement, the following words and expressions shall, unless
repugnant to the context or meaning thereof, have the meaning hereinafter
respectively assigned to them:
Accounting Year means the financial year commencing from the first day
of April of any calendar year and ending on the thirty-first day of March of
the next calendar year;
Advance Payment shall have the meaning set forth in Clause 19.2;
Affected Party shall have the meaning set forth in Clause 21.1;
Affiliate means, in relation to either Party {and/or Members}, a person who
controls, is controlled by, or is under the common control with such Party {or
Member} (as used in this definition, the expression control means, with
respect to a person which is a company or corporation, the ownership, directly
or indirectly, of more than 50% (fifty per cent) of the voting shares of such
person, and with respect to a person which is not a company or corporation,
the power to direct the management and policies of such person, whether
by operation of law or by contract or otherwise);
Agreement means this Agreement, its Recitals, the Schedules hereto and
any amendments thereto made in accordance with the provisions contained in
this Agreement;
Applicable Laws means all laws, brought into force and effect by GOI
or the State Government including rules, regulations and notifications made
there under, and judgments, decrees, injunctions, writs and orders of any
court of record, applicable to this Agreement and the exercise, performance
and discharge of the respective rights and obligations of the Parties hereunder,
as may be in force and effect during the subsistence of this Agreement;
Applicable Permits means all clearances, licenses, permits, authorizations,
no objection certificates, consents, approvals and exemptions required to be
obtained or maintained under Applicable Laws in connection with the
Construction, operation and Maintenance of the Project Works during the
subsistence of this Agreement;
Appointed Date means that date which is later of the 15th day of the date of
this Agreement, the date on which the Contractor has delivered the
Performance Security in accordance with the provisions of Article 7 and the
date on which the Employer has provided the Right of Way on no less than
90% (Ninety per cent) of the total length of Project Right of Way;
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 116
EPC Agreement
Arbitration Act means the Arbitration and Conciliation Act, 1996 and shall
include modifications to or any re-enactment thereof, as in force from time to
time.
Bank means a Bank incorporated in India and having a minimum net worth
o f Rs. 1,000 crore (Rupees one thousand crore) or any other Bank acceptable
to the Employer;
Bank Rate means the Repo rate of interest announced by the Reserve Bank
of India for all its lending operations on the Base Date;
Base Date means the last date of that calendar month, which date precedes
the Bid Due Date by at least 28 (twenty eight) days;
Bid means the documents in their entirety comprised in the Bid submitted
by the [selected bidder/Consortium] in response to the Request for Proposals in
accordance with the provisions thereof;
Bid Security means the Bid security provided by the Contractor to the
Employer in accordance with the Request for Proposal, and which is to remain
in force until substituted by the Performance Security;
Change in Law means the occurrence of any of the following after the Base
Date:
(a)
(b)
(c)
(d)
(e)
Change of Scope shall have the meaning set forth in Article 13;
Change of Scope Notice shall have the meaning set forth in Clause
13.2.1;
Change of Scope Order shall have the meaning set forth in Clause
13.2.4;
Completion Certificate shall have the meaning set forth in Clause 12.4;
{Consortium means the consortium of entities which have formed a joint
venture for implementation of this Project ;}$
Construction shall have the meaning set forth in Clause 1.2.1 (f);
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 117
EPC Agreement
not relieve any Party from liability to pay Damages or compensation under
the provisions of this Agreement; and
(c) not in any way be extended by any period of Suspension under this
Agreement; provided that if the cure of any breach by the Contractor
requires any reasonable action by the Contractor that must be approved by
the Employer or the Employers Engineer hereunder, the applicable Cure
Period shall be extended by the period taken by the Employer or the
Employers Engineer to accord their approval;
$$ This definition may be omitted if the Contractor is not a Consortium.
Damages shall have the meaning set forth in paragraph (w) of Clause1.2.1;
Defect means any Defect or deficiency in Construction of the Works or any
part thereof, which does not conform with the Specifications and Standards,
and in the case of Maintenance, means any Defect or deficiency which is
specified in Schedule E;
Defects Liability Period shall have the meaning set forth in Clause17.1;
Dispute shall have the meaning set forth in Clause 26.1.1;
Dispute Resolution Procedure means the procedure for resolution of
Disputes set forth in Article 26;
Drawings means all of the Drawings, calculations and documents
pertaining to the Project Works as set forth in Schedule-I, and shall include as
built Drawings of the Project Works;
Document or Documentation means Documentation in printed or
written form, or in tapes, discs, Drawings, computer programmes, writings,
reports, photographs, films, cassettes, or expressed in any other written,
electronic, audio or visual form;
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 118
EPC Agreement
Page 119
EPC Agreement
Page 120
EPC Agreement
Maintenance Programme shall have the meaning set forth in Clause 14.3;
Maintenance Period shall have the meaning set forth in Clause 14.1.1;
Maintenance Requirements shall have the meaning set forth in Clause
14.2;
Major Bridge means a bridge having a total length of more than 60 (sixty)
meters between the inner faces of the dirt walls as specified in IRC:5-1998;
Manual shall mean the Manual of Standards and Specifications for Four
lane and Six lane Manuals i.e. IRC: SP-84, IRC: SP-87 as per the cross
section of road
Material Adverse Effect means a Material adverse effect of any act or
event on the ability of either Party to perform any of its obligations under and
in accordance with the provisions of this Agreement and which act or event
causes a Material financial burden or loss to either Party;
Materials are all the supplies used by the Contractor for incorporation in the
Works or for the Maintenance of the Project Works;
Monthly Maintenance Statement shall have the meaning set forth in
Clause 19.6.1;
MORTH means the Ministry of Road Transport and Highways or any
substitute thereof dealing with Highways;
Non-Political Event shall have the meaning set forth in Clause 21.2;
Parties means the parties to this Agreement collectively and Party shall
mean any of the parties to this Agreement individually;
Performance Security shall have the meaning set forth in Clause 7.1;
Plant means the apparatus and machinery intended to form or forming part
of the Works;
PMNC shall have the meaning set forth in Clause 4.1.1:
Political Event shall have the meaning set forth in Clause 21.4;
Programme shall have the meaning set forth in Clause 10.1.3;
Project means the Construction and Maintenance of the Project Works in
accordance with the provisions of this Agreement, and includes all Works,
services and equipment relating to or in respect of the Scope of the Project;
Project Assets means all physical and other assets relating to
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 121
EPC Agreement
(a) tangible assets such as civil Works and equipment including foundations,
embankments, pavements, road surface, interchanges, bridges, culverts, road
over-bridges, drainage Works, traffic signals, sign boards, kilometer-stones,
[toll plaza(s)], electrical systems, communication systems, rest areas, relief
centers, Maintenance depots and administrative offices; and
(b) Project Facilities situated on the Site;
Project Completion Date means the date on which the Provisional
Certificate is issued and in the event no Provisional Certificate is issued, the
date on which the Completion Certificate is issued;
Project Completion Schedule means the progressive Project Milestones set
forth in Schedule-J for completion of the Project Works on or before the
Scheduled Completion Date;
Project Facilities means all the amenities and facilities situated on the Site,
as described in Schedule-C;
Project Works means the Site comprising the existing road forming part of
Design and Build the Infrastructure Works for Roads, Drains, Culverts,
Water Supply, Sewerage, Power systems for Phase - I in Shendra-Bidkin
Industrial Area, Aurangabad, Maharashtra, on EPC Basis (Package-I)
Project and all Project Assets, and its subsequent development and
augmentation in accordance with this Agreement;
Project Milestone means the Project milestone set forth in Schedule-J;
Proof Consultant shall have the meaning set forth in Clause 10.2.2;
Provisional Certificate shall have the meaning set forth in Clause 12.2;
Punch List shall have the meaning set forth in Clause 12.2.1;
Quality Assurance Plan or QAP shall have the meaning set forth in
Clause 11.2;
Re., Rs. or Rupees or Indian Rupees means the lawful currency
of the Republic of India;
Request for Proposals or RFP shall have the meaning set forth in
Recital D;
Request for Qualification or RFQ shall have the meaning set forth in
Recital C;
Retention Money shall have the meaning set forth in Clause 7.5.1;
Right of Way means the constructive possession of the Site free from
encroachments and encumbrances, together with all way leaves, easements,
unrestricted access and other rights of way, howsoever described, necessary
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 122
EPC Agreement
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 123
EPC Agreement
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 124
EPC Agreement
DELIVERED
DELIVERED
(Signature)
(Name)
(Name)
(Designation)
(Designation)
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 125
EPC Agreement
SCHEDULES
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 126
EPC Agreement
Contents
Site of the Project............................................................................................................127
Annexure I - Site............................................................................................................ 129
Annexure II Land Details............................................................................................ 132
Annexure III - Development Plan........................................................................................ 134
Annexure IV Environment Clearance...........................................................................135
Appendix A-I - Index Maps and Location Maps..............................................................136
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 127
EPC Agreement
1.0
The Site
1.1
1.2
The dates of handing over the Land to the Contractor are specified in
Annexure-II of this Schedule-A.
1.3
1.4
1.5
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 128
EPC Agreement
Annexure - I
(Schedule-A)
1.0
SITE
The Phase-I Area lies within the Shendra-Bidkin Industrial Area (SBIA), spread
across an area of 8.45 sq.km. The area has an optimum mix of land use, with major
share as industrial.
The area has existing connectivity of Jalna-Aurangabad Railway line and MSH 6
on south side and existing Shendra-Bidkin Industrial Development area on west
side of the site. It has an optimum mix of land use comprising of industrial,
residential mixed use and recreation.
Topographically, proposed Shendra-Bidkin Development area occupies 628.900m
contour on the north side boundary to the 565.600 in the south-side boundary.
The Phase-I Area lies within the following Latitudes and Longitudes.
Table 1
Point
B1
B2
B3
B4
B5
B6
B7
B8
B9
B 10
B 11
B 12
B 13
B 14
B 15
B 16
B 17
B 18
B 19
B 20
B 21
B 22
UTM Coordinates
Easting
552781.069
552864.414
553625.134
554319.694
554187.410
554458.132
554712.496
555411.297
555296.164
555832.518
556513.328
556630.173
557645.688
558002.502
557722.013
558078.193
558072.770
556811.026
556879.988
556720.327
556693.706
556066.968
Northing
2196927.753
2197740.509
2199470.440
2199002.243
2198561.532
2198430.825
2198931.759
2198549.560
2199096.823
2198968.657
2198965.753
2199617.573
2199906.419
2199132.646
2198561.532
2198185.758
2197797.693
2197589.293
2197911.790
2197932.781
2197728.741
2197468.501
Index Maps and Location Maps of the Project are given at Appendix A-I.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 129
EPC Agreement
1.1
Seismicity
Shendra-Bidkin Industrial Area (SBIA) Phase I Region falls under the ZoneIII of the Seismic zoning map of India IS: 1893-2002.
AURA
Prop.Shendra
Industrial. area
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 130
EPC Agreement
2.0
2.1
2.1.1
The following utilities are identified near Perkins factory along existing road
and needs to be suitably rerouted/relocated. Additional Site surveys shall be
conducted with contractor to confirm and finalise relocation of utilities.
a. Underground HT Cable along the existing road.
b. DI water pipe line of 250mm dia.
c. Street lights along existing road
2.2
Religious Structures
There is one existing religious structure.
2.3
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 131
EPC Agreement
Annexure - II (Schedule-A)
Land Details
1.0 Existing Land
Total Project area of 845 Hectares is distributed as per the table mentioned below.
Land Use
1 Industrial
2 Light Industrial & PAP Area (15%)
Sub Total (Industries)
3 Logistic
4 Truck Terminus
Sub Total (Logistic)
5 Commercial
6 Residential Area
7 Public & Semi Public
8 Park & Open Space
9 Water bodies
Sub Total (Open Space)
10 Road Network
11 Basti
12 CBD
GRAND TOTAL
Area (Sq.m)
2,591,717.91
1,579,060.00
0.00
72,709.10
619,763.19
711,323.54
606,766.66
547,381.39
313,118.50
1,209,256.44
6,727.09
204,313.83
8,455,410.56
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Area
(ha)
259.17
157.91
417.08
0.00
7.27
7.27
61.98
71.13
60.68
54.74
31.31
86.05
120.93
0.67
20.43
845.54
Percentage
30.65%
18.68%
49.33%
0.00%
0.86%
0.86%
7.33%
8.41%
7.18%
6.47%
3.70%
10.18%
14.30%
0.08%
2.42%
100.00%
Page 132
EPC Agreement
3.0
A.
Table 3: Handing over of Site for Road and Other Infrastructures to Contractor
S. No.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
Road Name
A-1
A-2
A-3
A-3
A-4
A-5
A-6
B-1
B-2
B-3
B-4
C-1
C-2
C-3
C-4
C-5
C-6
C-6
PAP Internal Roads
10 km of other Internal
Roads not shown in the
Drawing are also part of
the scope
PROW
60
60
60
60
60
60
60
45
45
45
45
30
30
30
30
30
30
30
15
15
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 133
EPC Agreement
2.0
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 134
EPC Agreement
Annexure IV (Schedule-A)
Environment Clearances
1.0
As per MOM-147 with Expert Appraisal Committee (EAC) held on 23-24 April
2015, the overall Environment clearance for Shendra-Bidkin Industrial Area in
Phase-I has been granted by MOEF.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 135
EPC Agreement
Appendix A-I
INDEX MAPS AND LOCATION MAPS
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 136
EPC Agreement
AURANGABAD
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 137
EPC Agreement
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 138
EPC Agreement
Schedule B
Development of the Project Roads and Utilities/Services
(See Clause 2.1)
Contents
Development of the Project Roads and Utilities/Services................................................140
Appendix B I
Appendix B II
Appendix B III
Appendix B IV
Appendix B V
Appendix B VI
Appendix B VII
Appendix B VIII
Appendix B IX
Appendix B X
Appendix B XI
Appendix B XII
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 139
EPC Agreement
1.0
ii)
iii)
iv)
Geometric design and other features are given in Appendix B III (b)
v)
vi)
Embankment & Pavement design details are given in Appendix B III (d).
vii) Typical Cross Sections (TCS) Drawings are given in Appendix B IV.
viii) Potable Water Supply network details are given in Appendix B V.
ix)
x)
xi)
xii) Storm Water Drainage network details are given in Appendix B IX.
xiii) Details of Power supply network are given in Appendix B X.
xiv) Details of Culverts, Bridges and Outfall Structures for storm water drainage
are given in Appendix B IX.
xv) Network plans & Drawings are given in Appendix B XII.
2.0
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 140
EPC Agreement
Appendix B I
1.0
Plot No.
Area(ha)
22
Industrial
5.99
23
Industrial
11.89
24
PSP
2.97
76
Open
2.68
25
Commercial
0.47
PSP
2.55
75
Open
3.64
Industrial
2.99
Industrial
3.03
10
96
Open
2.14
11
Industrial
4.32
12
Industrial
4.09
13
Industrial
11.83
14
Industrial
4.77
15
Industrial
2.59
16
46
Industrial
4.3
17
Industrial
10.31
18
10
Industrial PAP
20.01
19
16
PSP
20
19
Residential
17.21
16369
21
20
Residential
22.61
21505
22
21
Residential
5.75
5469
23
15
Industrial PAP
6.33
24
13
Industrial PAP
7.96
25
63
industrial
14.34
26
64
Industrial
7.35
27
18
PSP
6.18
28
14
Industrial PAP
7.07
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Population
Page 141
EPC Agreement
Zone
Plot No.
Area(ha)
29
11
Industrial PAP
6.89
30
12
Industrial PAP
28.69
31
17
PSP
2.98
32
91
Open
4.96
33
69
Industrial PAP
5.75
34
68
Industrial PAP
16.03
35
67
Industrial PAP
15.25
36
84
Open
5.7
37
65
Industrial
17.79
38
66
Solid waste
3.62
39
98
Industrial
18.81
40
97
Industrial
17.91
41
62
Industrial
27.89
42
89
Truck Terminus
7.27
43
88
Industrial
2.96
44
95
Industrial
4.63
45
61
Commercial
3.7
46
87
Residential
5.01
47
59
Industrial
10.57
48
60
Industrial
10.41
49
58
Industrial
9.52
50
57
PSP
9.47
51
56
Industrial
39.33
52
52
Residential
14.55
53
51
Open
7.89
54
50
CETP
5.97
55
55
Industrial
13.69
56
53
Commercial
4.73
57
54
Commercial
4.58
58
86
Commercial
1.22
59
47 & 48
Industrial
13.17
60
45
Industrial
12.31
61
38
Commercial
6.5
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Population
4765
13839
Page 142
EPC Agreement
Zone
Plot No.
Area(ha)
62
39
PSP
2.8
63
49
PSP
3.26
64
43
Sub Station
4.18
65
44
Commercial
5.93
66
41
Industrial
10.45
67
40
Industrial
5.86
68
37
PSP
9.73
69
42
Residential
5.33
70
78
Open
4.53
71
36
CBD
20.43
72
77
Open
3.5
73
27
Commercial
4.1
74
26
Commercial
15.92
75
28 to 34
Commercial
14.81
76
35
PSP
1.94
Total
673
Population
5070
67017
Description
Industrial
Commercial
CBD
Other Uses
Residential
Total
Estimated Population
18769
24792
13628
4764
67657
129610
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 143
EPC Agreement
Appendix B II
1.0
S.No
Land Use
Area (Sq.m)
Area (ha)
Percentage
1 Industrial
2591717.91
259.17
30.65%
1579060.00
157.91
18.68%
417.08
49.33%
7.27
0.86%
7.27
0.86%
72709.10
Sub Total (Logistic)
4 Commercial
619763.19
61.98
7.33%
5 Residential Area
711323.54
71.13
8.41%
606766.66
60.68
7.18%
547381.39
54.74
6.47%
313118
31.31
3.70%
86.05
10.18%
8 Water bodies
Sub Total (Open Space)
9 Road Network
1209256
120.93
14.30%
10 Basti
6727.09
0.67
0.08%
11 CBD
204313.83
20.43
2.42%
8455410.56
845.54
100.00%
GRAND TOTAL
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 144
EPC Agreement
Appendix B III
1.0
1.1
1.2
Width of Carriageway
Width of carriageway is as given in typical cross sections Drawings in Appendix B
IV.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 145
EPC Agreement
Note -
S. No.
Road
Name
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
A-1
A-2
A-3
A-3
A-4
A-5
A-6
B-1
B-2
B-3
B-4
C-1
C-2
C-3
C-4
C-5
C-6
C-6
D
D
From
To
Applicable
Chainage Chainage
TCS
0+0
0+520
0+950
3+233
0+0
0+650
0+650
4+057
0+0
1+767
0+0
1+189
0+0
0+531
0+0
3+629
0+0
0+966
0+0
0+443
0+0
1+011
0+0
2+652
0+0
2+013
0+0
1+006
0+0
1+135
0+0
0+896
0+0
0+850
0+850
1+120
PAP Roads
10 km Internal roads
Type A1
Type A1
Type A2
Type A1
Type A1
Type A1
Type A1
Type B1
Type B1
Type B1
Type B1
Type C1
Type C1
Type C1
Type C1
Type C1
Type C2
Type C1
Type D
Type D
PROW
60
60
60
60
60
60
60
45
45
45
45
30
30
30
30
30
30
30
15
15
The actual length of roads may very as per detailed engineering design. Utilities shown in
typical cross sections provided in appendix B XII are indicative and the above schedules are
applicable for excluding utility services. For utility services respective schedule to be referred.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 146
EPC Agreement
1.1
General
Geometric design and other features of the Project Roads shall be in accordance
with the Standards and Specifications as per Schedule D.
1.2
Design speed
The Design Speeds for different category of roads are as given below in Table: 4
Table: 4
S. No.
Road
Name
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
A-1
A-2
A-3
A-3
A-4
A-5
A-6
B-1
B-2
B-3
B-4
C-1
C-2
C-3
C-4
C-5
C-6
C-6
D
From
Chainage
To
Chainage
0+0
0+520
0+950
2+283
0+0
0+650
0+650
4+057
0+0
1+767
0+0
1+189
0+0
0+531
0+0
3+629
0+0
0+966
0+0
0+443
0+0
1+011
0+0
2+652
0+0
2+013
0+0
1+006
0+0
1+135
0+0
0+896
0+0
0+850
0+850
1+120
PAP and Internal roads
Design Speed
(Km/h)
80
80
80
80
80
80
80
50
50
50
50
40
40
40
40
40
40
40
40
Service road
design Speed
(Km/h)
40
40
40
40
40
40
40
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 147
EPC Agreement
S. No.
Node
No.
Type
T Junction
60
30
30
X Junction
60
45
60
45
3
4
5
6
7
4
5
6
7
8
T Junction
X Junction
X Junction
T Junction
T Junction
60
60
60
60
60
60
60
60
30
60
60
60
60
60
60
45
45
-
T Junction
60
60
10
Roundabout
60
60
10
11
T Junction
30
30
11
12
T Junction
30
30
12
13
13
14
Roundabout
30
30
14
15
16
17
18
15
16
17
18
19
T Junction
X Junction
T Junction
X Junction
X Junction
60
45
30
45
60
60
30
30
45
45
19
20
Roundabout
30
20
21
22
23
21
22
23
24
T Junction
T Junction
X Junction
T Junction
30
45
60
30
45
45
45
30
24
25
25
26
27
26
27
28
T Junction
T Junction
T Junction
60
60
60
30
60
45
Remarks
Junction with
Service roads
No median
opening
Merging with
Existing Road
Existing Existing Merging with
Road
Road
Existing Road
Existing
Merging with
Road
Existing Road
30
End of 30m
ROW Road
Outer Radius of
30
Roundabout
45m
30
45
30
30
45
30
60
45
Outer Radius of
Round about 45m
30
45
60
30
30
Merging with
Existing Road
60
60
60
60
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 148
EPC Agreement
Node
S. No.
No.
28
29
29
30
Type
T Junction
T Junction
30
60
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Remarks
At grade
junction with
Service road
only
Page 149
EPC Agreement
Service Roads
Flexible
Cycle Track
Flexible
Flexible
60m
45m
30 m
Traffic (MSA)
25
10
10
Service Road
5
Cycle Track
2
Note: Granular layers shall be designed for minimum10MSA traffic for Cycle track
& service roads.
2.4 Footpath
Paver blocks are to be used for footpath/walkway and shall be in confirmation with
the technical specifications in Schedule-D.
Pattern/style/colour of paver block shall be got approved from the Employer or
Employer representative.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 150
EPC Agreement
Appendix B IV
1.0
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 151
EPC Agreement
Appendix B V
1.0
1.1
Background
The potable water for this Project area will be fed from the WTP of 72 MLD scheme
already under execution by MIDC. The Break Pressure Tank is proposed at
Khodegaon. The water source is Jayakwadi dam. Potable water will be fed from a
branch line in the existing gravity main (Tap off point shall be provided on the main
gravity line coming from Break Pressure Tank at Khodegaon, on service road parallel
to Jalna road near existing main entrance of Shendra-Bidkin Industrial area) to the
Underground Service Reservoir (UGSR) located at a distance of 3.10 km from the
main line within the Project area. Then the potable water is partly supplied by gravity
to a part of the Project area and partly pumped to the elevated service reservoir (ESR)
and thereon it is supplied under gravity to the other part of the Project area. The
schematic diagram of potable water supply scheme is provided in Appendix BXII.
1.1.1
The Project area is divided into different land uses as per Table 1 in Appendix B II.
The population or the number of employees under various land uses as provided in the
development plan are as under.
Table 1 Population as per Development Plan
S. No.
Description
No. of Employee
Industrial
11663
Industrial PAP
7106
Logistic/Warehousing
Residential
Utilities
Commercial
24792
CBD
13628
4066
388
10
Truck Terminal
109
11
Water Body
12
Road
Population
0
67657
200
TOTAL
61952
67657
Based on the above, the population for various land uses to be adopted for design is
provided in the following table.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 152
EPC Agreement
Description
Industrial
Commercial
CBD
Other Uses
Residential
Total
Estimated Population
18769
24792
13628
4764
67657
129610
The rate of water supply to be adopted for different land uses are as follows:
Domestic/Residential Water Supply
135 lpcd
45 lpcd
Commercial
45 lpcd
35 kl/ha/day
Logistic / Warehousing
5 kl/ha/day
Workforce
45 lpcd
15 lpcd
Hotel
Service Apartments
135 lpcd
For fire-fighting purpose, the water demand has been estimated in kiloliters per day
using the formula 100P where P is population in thousands as per CPHEEO Manual.
The horticultural/irrigation water demand to be adopted as follows:
Roadside trees: 28000 liters per km
Public parks and private gardens: 20 to 30 liters per 100 sq. meters
Based on the above parameters, the tentative water demands for different land uses
vis--vis the population are as described hereunder.
Table 3 Tentative Gross Water Demand
S. No.
1
2
3
4
DESCRIPTION
Drinking Water
Industrial
Horticulture
Fire Fighting
TOTAL
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 153
EPC Agreement
The total water demand has been further divided into potable and recycled water
demand based on the following:
Potable Water Demand - Drinking + Fire Fighting + 20% Industrial
Recycled Water Demand - 80% Industrial + Horticulture
The tentative breakup of total water demand is provided in the table below:
Table 4 Breakup of Tentative Gross Water Demand
S. No.
1
2
DESCRIPTION
Potable
Recycled
19.50
22.54
TOTAL
42.04
Peak Factor
The water supply is being done to a mixed land use which comprises of residential,
industrial and commercial developments. Due to uncertainty of the level of all these
developments, a weighted peak factor has been computed for the design of potable
and recycled water supply distribution network which is taken as 1.5.
1.2
1.3
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 154
EPC Agreement
The approximate length of the rising main is 110 m and working pressure in these
pipelines will vary between 30-60 m.
The scope for this item includes designing, providing, supplying, lowering, laying and
jointing of pipes & valves to be provided at appropriate spacing as per CPHEEO
guidelines for easy operation and Maintenance of distribution network, bulk flow
water meters including all specials, excavation, backfilling, bedding, Construction of
thrust blocks, level sensors, actuators for valves with provision for future SCADA
integration, valve chambers of appropriate sizes as per CPWD specification and bulk
water meter with chambers and other accessory structures. The scope of services
includes supply of water for hydraulic testing and carrying out hydraulic test for entire
water supply network. The anti-corrosion treatment of reinforcement shall be
provided and inner surface of OHSR shall be painted by food grade epoxy paints.
Also the water proofing of slab and Chequred tiles flooring shall be done on the top of
OHSR slab.
The tentative details of Potable water rising mains are as follows:
Table 5 Tentative Details Trunk Mains
S. No. Description
Value
Gravity main from Tap off Point to UGSR
1
Pipe Diameter
400mm - 600mm
2
Pipe Material above 250mm Dia
DI K-9
3
Total Length of Trunk Main
Refer the Drawings
Pumping main from UGSR to OHSR
1
Pipe Diameter
350 mm
2
Pipe Material
DI-K9
3
Total Length of Rising Main
Refer the Drawing
1.4
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 155
EPC Agreement
1000 KL
Staging Height*
25-30 m
*Exact staging height, diameter of OHSR etc. shall be as per the detailed design of the
Construction Contractor.
1.5
1.6
Description
Pipe Diameter
Pipe Material above 250mm Dia
Pipe Material below 250mm Dia
Total Length of Distribution network
Value
110 mm- 600 mm
DI K-7
HDPE
Refer the Drawings
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 156
EPC Agreement
The pumps shall be of vertical turbine type suitable to pump required amount of water
to the OHSR. The scope shall include all required appurtenances for completion of the
work and providing all PLC/ SCADA/Automation requirements for required
components. The minimum number of pumps to be provided shall be 4 (2W + 2S)
each for 50% of the flow, however actual capacity of the pumps has to be ascertained
by the contractor at the detailed design stage.
1.7
Property Connections
Service pipes should be laid up to plot boundaries in the Project area. The service pipe
details are as defined below:
Table 7 - Tentative Details of Property Connections
S. No.
1
2
3
Description
Value
Details of MDPE pipe house
As per the Drawings
service connection
Pipe Material
MDPE
Number of connections
221No.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 157
EPC Agreement
Appendix B VI
1.0
1.1
Background
The treated effluent from the STP and from CETP is conveyed to the recycled water
Underground service reservoir (UGSR) located in STP/CETP premises within the
Project area. Then recycled water is pumped from UGSR to Recycled Water Over
Head Service Reservoir catering to recycled water supply distribution network in the
Project area. The recycled water demand and peak factor shall be as per Appendix B
V, 1.1.1.
1.2
1.3
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 158
EPC Agreement
1.5
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 159
EPC Agreement
The implementation limit for this distribution system will be from the outlet of the
Overhead/Elevated service reservoir to the service connection points outside the plots
in the Project area.
The scope for this item includes Designing, providing, supplying, lowering, laying
and jointing of pipes & Valves to be provided at appropriate spacing as per CPHEEO
guidelines for easy operation and Maintenance of distribution network, Bulk flow
Water meters including all specials, excavation, backfilling, bedding, , Construction
of valve and water meter chambers of appropriate sizes as per CPWD specification
installation of valve, actuators for valves with provision for future SCADA
integration , and other accessory Structures and fixtures, all the electro-mechanical
installations and physical infrastructure of the distribution network shall be
PLC/SCADA compatible. The scope of services includes supply of water for
hydraulic testing and carrying out hydraulic test for distribution system.
The tentative details of recycled water distribution system are as defined below.
Table 2 Tentative Details of Recycled Water Distribution Network
S. No.
1
2
3
3
1.6
Description
Pipe Diameter
Pipe Material above 250mm Dia
Pipe Material below 250mm Dia
Total Length of Distribution network
Value
110 mm -600 mm
DI K-7
HDPE
Refer the Drawings
1.7
Property Connections
Service pipes should be laid up to plot boundaries in the Project area. The service pipe
details are as defined below:
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 160
EPC Agreement
Description
Pipe Diameter
Pipe Material
Number of property
connections
Number of connections for
Horticulture
Value
40 mm
MDPE
191 No.
700 No. tapping with valve.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 161
EPC Agreement
Appendix B VII
1.0
1.1
Background
The Sewerage network system is planned for the domestic sewage from residential as
well as commercial & institutional areas.
The STP is planned to be developed in modular basis and will be built under separate
package.
Description
Commercial
CBD/ City Center
Other Uses
Residential
TOTAL
Rate of Infiltration
Infiltration into the sewerage system occurs through defective sewers, manholes, etc.
The rate of infiltration into sewers also depends upon the ground water table and
permeability of the surrounding soil. Though strict quality control and good
workmanship would ensure minimum infiltration, however as the system condition
deteriorates with age, the possibility of infiltration increases. Manual on Sewerage and
Sewage Treatment, by CPHEEO, 2013 recommends the norms for adopting ground
water infiltration into sewers which shall be suitably adopted.
Peak Factor
The peak factor with respect to contributing population for sewage generation shall be
adopted as per CPHEEO Manual, 2013. For arriving at optimized sewer sizes while
designing, conduit wise progressively decreasing peak factor is to be applied based on
the contributory population on the individual conduit.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 162
EPC Agreement
1.2
Description
Sewer Pipe Diameter
Sewer Pipe Material along the Road
Sewer Pipe Material Crossing the
Road
Total Length of Sewerage network
Value
200 mm - 600 mm
RCC NP3
RCC NP4
Refer the Drawings
The scope for Manholes includes designing and constructing Sewer manholes, drop
manholes and scrapper manholes as per the type design in RCC M-30 (Batch Mix)
and outside plastering in C.M. 1:3, necessary coping in R.C.C. M-20 fixing PVC
encapsulated D.I / C.I Steps or Lugs, providing and fixing SFRC manhole frames and
covers over manholes etc. complete, including epoxy paint to be applied to both inner
and outer surface of RCC manholes, including all civil Works like excavation,
backfilling, RCC Works etc.
Table 4 Tentative Details of Manholes
Description
RCC Manholes
Distance
Depth of invert of manholes
Value
587 Nos.
@ 30 m c/c and at Junctions,
Bend, change of alignment etc.
1.1 m to 6.5 m
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 163
1.3
EPC Agreement
Property Connections
Service pipes for the property connections should be laid up to plot boundaries in the
Project area. The service pipe details are as defined below:
Table 5 - Tentative Details of Property Connections
S. No.
1
2
3
Description
Value
Pipe Diameter
160 mm
Pipe Material
HDPE /PE as per IS 14333
Total Number of Residential 108 No.
property connections
1.4
1.5
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 164
EPC Agreement
APPENDIX B VIII
1.0
1.1
Background
The industrial effluent collection network system is proposed primarily for the
collection of industrial effluent from the process units of the industries. This network
also collects the sewage generated from workers in the industries.
CETP is planned to develop in modular basis and shall be built under separate
package.
Description
Industrial Process
Industrial Workforce
TOTAL
Rate of Infiltration
Infiltration into the sewerage system occurs through defective sewers, manholes, etc.
The rate of infiltration into sewers also depends upon the ground water table and
permeability of the surrounding soil. Though strict quality control and good
workmanship would ensure minimum infiltration, however as the system condition
deteriorates with age, the possibility of infiltration increases. Manual on Sewerage and
Sewage Treatment, by CPHEEO, 2013 recommends the norms for adopting ground
water infiltration into sewers which shall be suitably adopted.
Peak Factor
Since the variability of flow in industrial sewers is not as high as domestic sewer, the
peak factor for these sewers is to be adopted as 1.5.
1.2
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 165
EPC Agreement
The pumping mains from the pumping stations will convey the effluent to the nearest
manhole and the scope includes designing of the intermediate pumping stations as
well as pumping mains line.
Contractor has to design the complete network system for the Project area.
The implementation limit of this network will be from the Property connection point
outside the Industrial plot boundaries in the Project area to the inlet points of the
terminal effluent pumping station in CETP premises (by gravity system). The Layout
Drawing for Industrial effluent collection system is given in Appendix BXII.
The scope for this item includes designing of the effluent collection system,
providing, supplying, lowering, laying and jointing of pipes including excavation,
backfilling, bedding for Industrial effluent collection. The scope of services includes
supply of water for hydraulic testing and carrying out hydraulic test for network and
manholes. The tentative details of the industrial effluent collection system shall be as
follows:
Table 2 Tentative Details of Industrial Effluent Collection Network
S. No.
1
2
Description
Sewer Pipe Diameter
Sewer Pipe Material along the Road
Value
200 mm - 700 mm
RCC NP3 with
HDPE lining
minimum 5 mm thick
RCC NP4 with
HDPE lining
minimum 5 mm thick
Refer the Drawing
The scope for Manholes includes designing and constructing of Sewer manholes, drop
manholes and scrapper manholes as per the type design in RCC M-30 (Batch Mix)
and outside plastering in C.M. 1:3, necessary coping in R.C.C. M-20 fixing PVC
encapsulated D.I / C.I Steps or Lugs, providing and SFRC manhole frames and covers
over manholes etc. complete, including epoxy paint to be applied to both inner and
outer surface of RCC manholes, including all civil Works like excavation, backfilling,
RCC Works etc.
Table 3 - Tentative Details of Manholes
Description
RCC Manholes
Material of Construction
Distance
Value
1215 Nos.
RCC with HDPE lining
minimum 5 mm thick
@ 30 m c/c and at Junctions,
Bend, change of alignment etc.
1.3 m to 6.5 m
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 166
EPC Agreement
1.3
Property Connections
Service pipes for the property connections should be laid up to plot boundaries in the
Project area. The service pipe details are as defined below:
Table 4 - Tentative Details of Property Connections
S. No.
1
2
3
1.4
Description
Value
Pipe Diameter
160 mm
Pipe Material
uPVC
Total number of industrial property connections 418 No.
1.5
Pumping Main
This item includes the design and Construction of pumping main from the outlet of
the common delivery pipe after the intermediate sewage pumping stations to the
nearest manhole in the network or to the collection chamber at CETP. The scope for
this item includes designing of the pumping main, providing, supplying, lowering,
laying and jointing of pumping main including all specials, excavation, backfilling,
bedding and other accessory Structures e.g. thrust blocks etc and providing all PLC/
SCADA/Automation requirements for required components for industrial
effluent/sewage collection.
The scope of services includes supply of water for hydraulic testing and carrying out
hydraulic test for pumping main.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 167
EPC Agreement
Description
Value
Number
of
intermediate
2 No.
Pumping station
Pumping main/ Pipe Diameter 400 and 450 mm
DI K-9 (Internal cement
mortar lining and outside
Pumping main/ Pipe Material
Zinc coating with finished
layer of bitumen coating)
Total approximate length of
Refer the Drawings
Pumping mains
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 168
EPC Agreement
Appendix B IX
1.0 Storm Water Drainage Network
Drainage system for the Project Area and adjacent areas shall be based on following
parameters.
Invert levels at the outfalls to primary drainage channels and the existing railway
drainage crossings will be considered for the design of secondary drainage system
Minimum cover shall be maintained below the finished ground level as per CPHEEO
2014 manual.
Once in 5 year event flows for secondary storm water drainage channels;
Once in 10 year event flows for minor culverts (5-year discharge < 10 m3/s);
Once in 25 year event flows for major culverts (5-year discharge > 10 m3/s); and
Type of Drain
Width (m)
Depth(m)
Type-B
RCC drains
1.5
2.5
Type-C
RCC drains
1.2
2.5
Type-C
RCC drains
3.5
2.2
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Length (m)
Refer the
Drawings
Page 169
EPC Agreement
Type of Drain
Diameter (mm)
RCC NP-3
1600
RCC NP-3
1400
RCC NP-3
1200
RCC NP-3
1000
RCC NP-3
900
CBD
RCC NP-3
900
Type-A
RCC NP-3
600
Type-D
RCC NP-3
450
Upstream UGD
Length (m)
Refer the
Drawings
Type of Drain
Width (m)
Depth(m)
Length (m)
Type-B
1.5
2.5
Type-C
1.2
2.5
Refer the
Drawings
Note: Width and depth mentioned in table above are including wall thicknesses. Typical property
connection arrangement Drawings are given in the Drawings Volume.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 170
EPC Agreement
Nos
12
75
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 171
EPC Agreement
Appendix B X
1.0
b)
Design, supply, installation, testing and commissioning of 33kV and 11kV VCB
based Switchgears inside 33/11kV substations including all cabling, laying in
trench, termination work etc. complete in all respect.
c)
d)
e)
f)
g)
h)
Note-: The detail of 33KV Capacitor banks as shown in the single line diagram in
tender Drawings for reference. The contractor shall design necessary capacitor
banks (as per the required value of P.F.) and install, test and commission in
accordance with Indian Standards, IEC and local electricity rules.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 172
EPC Agreement
i)
j)
k)
l)
m)
n)
o)
p)
All cabling, terminations, jointing and necessary Works as required to take the
power supply from 220/33kV MRSS substation and to connect this to each
33/11kV substation and to establish an interface between transmission and
distribution network battery limits.
q)
All Works w.r.t. existing Power Supply Infrastructure i.e., dismantling, shifting,
re-installation etc. shall be in contractors scope.
Page 173
EPC Agreement
It is proposed that all the consumer upto 3MVA power demand shall receive power
through 11kV Ring main units. However, all other consumers having maximum demand
above 3MVA and below 20MVA shall receive supply through 33kV Ring Main Units
(RMUs). The RMUs shall be provided at the proximity of each type of consumers.
For the space optimization and to reduce the cable sizes all 11kV and 33kV RMUs shall
be fed from nearby substations.
For the power supply arrangement of each RMU, the contractor shall ensure the
provision of necessary power supply feeders in respective substation. The quantity of
each type RMU is indicated in single line diagram.
All other auxiliary loads (lighting, small power) upto 200 kVA shall be using 415 V
supply. For this purpose, each substation shall be housing dedicated auxiliary
transformer to feed supply at 415 V AC.
To maintain the redundancy and reliability in the power supply distribution network, 11
kV and 33kV Ring main units shall be connected in a Ring. Each ring shall be
connected to separate sources through the feeders on the different buses (refer overall
single line diagram).
2.0
3.0
Design
The contractor shall design the power distribution system based on the following
criteria:
3.1 General
The electrical system shall be designed to provide:
a.
b.
Reliability of Service.
c.
d.
e.
f.
Electrical supply to equipment and machinery within the design operating limits.
g.
h.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 174
EPC Agreement
S. No.
Residential
57
Commercial
80
25
The maximum demand of the Shendra Project shall also be determined considering the
load density, load Factor, diversity factor (applicable for various types of consumers
present in Maharashtra) and future growth upto 30years.
3.5 Codes and Standards
The electrical equipment and accessories shall be designed as per the following codes,
standards and regulations.
Applicable Standards and Codes of Practices published by Bureau of Indian
Standards.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 175
EPC Agreement
2.
3.
4.
Description
Voltage level
control transformers)
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 176
EPC Agreement
S. No.
Description
Voltage level
5.
UPS
6.
Metering
7.
Illumination
8.
Description
Voltage
Permissible variation with rated performance For HT system:and control effectiveness maintained
Permissible voltage dip during starting of
motor
+/- 6%
+/- 10 %
All the power and distribution transformers shall be envisaged with Tap Changers with
voltage settings +5/-15% in the step of 1.25. However, all the electrical consumers shall
ensure to provide necessary equipment to limit the voltage variation in the network
within the specified values in this document.
3.8 Harmonics Suppression
All electrical consumers shall install necessary equipment to restrict the harmonics
generation less than 5% in the electrical network. Consumer shall install necessary
harmonic filters near to the loads generating harmonics.
3.9 Power Factor Correction
All electrical consumers i.e. Industrial, Commercial, Residential, CBD etc. shall install
necessary power factor correction equipment at their premises to bring the system
Power Factor at 0.99.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 177
EPC Agreement
Breaking Capacity
Making Capacity
31.5 kA
100 kA
Substation Design
The design of the all substations shall be in others scope. However, contractor shall be
responsible for necessary provisions and equipment as required for the interface
between the transmission and distribution netWorks.
5.0
HV Cables
The scope shall include the design, supply, laying, testing and commissioning of 33kV
and 11kV, XLPE, Armored cables.
The scope for this item also includes jointing and terminations (by methods prescribed
in Indian and International Standards).
6.0
Lighting
The scope shall include the design, supply, installation, testing and commissioning of
lighting system in substations, roads and open areas of Shendra Phase-1.
The lighting system shall be designed based on the various LUX levels as required for
various areas mentioned in Indian and International Standards. The design shall also
take care of all factors such as ambient conditions, utilization and electricity savings.
Successful bidder shall prepare the lighting layout based on the lighting study (using
lighting softwares) and energy saving evaluation charts.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 178
EPC Agreement
Appendix B XI
1.0 Structures: Culverts, Bridges and Outfalls Structures for Storm Water
Drainage
1.1 Bridges
All bridges and Structures shall be designed and constructed in accordance with the
Schedule D and shall conform to the cross-sectional features and other details
specified as per table given below;
A. Bridges
S. No.
Chainage
Road
Name
0+750
A3
0+740
B1
1+320
B1
0+090
B3
1+380
C1
1+200
C2
1+820
C2
Type of
Bridge
Minor
Bridge
Minor
Bridge
Minor
Bridge
Minor
Bridge
Minor
Bridge
Minor
Bridge
Minor
Bridge
Span
Arrangement
Length of
Bridge across
cross road (m)
1 x 6m
1 x 8m
1 x 8m
1 x 6m
Refer the
Drawings
1 x 10m
1 x 6m
1 x 6m
B. Culverts
1+800
Road
Name
A2
Type of
Culvert
Box Culvert
Span
Arrangement
1 x 3.6m
2+330
A2
Hume Pipe
1 x 1.2m
1+880
A3
Box Culvert
1 x 3.6m
1+600
A4
Hume Pipe
2 x 1.2m
3+140
B1
Box Culvert
1 x 3.6m
0+030
B2
Hume Pipe
1 x 1.2m
0+386
B4
Box Culvert
1 x 3.6m
0+030
C3
Hume Pipe
1 x 1.2m
S. No.
Chainage
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Width of the
Cross Road
Refer the
Drawings
Page 179
EPC Agreement
2.0
0+340
C3
Hume Pipe
1 x 1.2m
10
1+110
C4
Hume Pipe
1 x 1.2m
11
0+030
C5
Hume Pipe
1 x 1.2m
12
0+860
C6
Box Culvert
1 x 3.6m
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 180
EPC Agreement
Appendix B XII
1.0 Drawings (Refer Drawing Volume)
1.1 Roads
ROADS
S.NO.
DESCRIPTION
DWG NO.
SBIA/PH-1/PK-1/HW/TCS/01
SBIA/PH-1/PK-1/HW/TCS/02
SBIA/PH-1/PK-1/HW/TCS/03
LAYOUT PLAN
4
LAYOUT PLAN
SBIA/PH-1/PK-1/HW/01
SBIA/PH-1/PK-1/HW/02
SBIA/PH-1/PK-1/HW/03
7
8
SBIA/PH-1/PK-1/HW/04
SBIA/PH-1/PK-1/HW/05
SBIA/PH-1/PK-1/HW/06
SBIA/PH-1/PK-1/HW/JUN/01
A TYPE ROAD
11
12
13
14
SBIA/PH-I/PK-I/HW/PP/A1/1-2
SBIA/PH-I/PK-I/HW/PP/A1/2-2
SBIA/PH-I/PK-I/HW/PP/A2/1-4
SBIA/PH-I/PK-I/HW/PP/A2/2-4
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 181
EPC Agreement
15
SBIA/PH-I/PK-I/HW/PP/A2/3-4
SBIA/PH-I/PK-I/HW/PP/A2/4-4
SBIA/PH-I/PK-I/HW/PP/A3/1-4
SBIA/PH-I/PK-I/HW/PP/A3/2-4
SBIA/PH-I/PK-I/HW/PP/A3/3-4
SBIA/PH-I/PK-I/HW/PP/A3/4-4
SBIA/PH-I/PK-I/HW/PP/A4/1-2
SBIA/PH-I/PK-I/HW/PP/A4/2-2
SBIA/PH-I/PK-I/HW/PP/A5/1-1
SBIA/PH-I/PK-I/HW/PP/A6/1-1
SBIA/PH-I/PK-I/HW/PP/B1/1-4
SBIA/PH-I/PK-I/HW/PP/B1/2-4
SBIA/PH-I/PK-I/HW/PP/B1/3-4
SBIA/PH-I/PK-I/HW/PP/B1/4-4
SBIA/PH-I/PK-I/HW/PP/B2/1-1
SBIA/PH-I/PK-I/HW/PP/B3/1-1
SBIA/PH-I/PK-I/HW/PP/B4/1-1
SBIA/PH-I/PK-I/HW/PP/C1/1-3
SBIA/PH-I/PK-I/HW/PP/C1/2-3
SBIA/PH-I/PK-I/HW/PP/C1/3-3
SBIA/PH-I/PK-I/HW/PP/C2/1-2
SBIA/PH-I/PK-I/HW/PP/C2/2-2
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 182
EPC Agreement
37
SBIA/PH-I/PK-I/HW/PP/C3/1-1
SBIA/PH-I/PK-I/HW/PP/C4/1-1
SBIA/PH-I/PK-I/HW/PP/C5/1-1
SBIA/PH-I/PK-I/HW/PP/C6/1-1
41
SBIA/PH-I/PK-I/HW/MISC/01
42
SBIA/PH-I/PK-I/HW/MISC/02
43
SBIA/PH-I/PK-I/HW/MISC/03
44
SBIA/PH-I/PK-I/HW/MISC/04
STRUCTURES DRAWINGS
BOX
45
SBIA/PH-I/PK-I/HW/STR/BOX/A21800/1-2
SBIA/PH-I/PK-I/HW/STR/BOX/A21800/2-2
SBIA/PH-I/PK-I/HW/STR/BOX/A31800/1-2
SBIA/PH-I/PK-I/HW/STR/BOX/A31800/2-2
SBIA/PH-I/PK-I/HW/STR/BOX/B13140/01
SBIA/PH-I/PK-I/HW/STR/BOX/B40386/01
SBIA/PH-I/PK-I/HW/STR/BOX/C60860/01
SBIA/PH-I/PK-I/HW/STR/MIB/A30750/1-2
SBIA/PH-I/PK-I/HW/STR/MIB/A30750/2-2
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 183
EPC Agreement
54
55
56
57
58
59
60
61
62
SBIA/PH-I/PK-I/HW/STR/MIB/B10740/01
SBIA/PH-I/PK-I/HW/STR/MIB/B11320/01
SBIA/PH-I/PK-I/HW/STR/MIB/B30090/01
SBIA/PH-I/PK-I/HW/STR/MIB/C11380/1-2
SBIA/PH-I/PK-I/HW/STR/MIB/C11380/2-2
SBIA/PH-I/PK-I/HW/STR/MIB/C21200/1-2
SBIA/PH-I/PK-I/HW/STR/MIB/C21200/2-2
SBIA/PH-I/PK-I/HW/STR/MIB/C21820/1-2
SBIA/PH-I/PK-I/HW/STR/MIB/C21820/2-2
PIPE
63
64
65
66
67
68
69
SBIA/PH-I/PK-I/HW/STR/PIPE/A22330/01
SBIA/PH-I/PK-I/HW/STR/PIPE/A41600/01
SBIA/PH-I/PK-I/HW/STR/PIPE/B20030/01
SBIA/PH-I/PK-I/HW/STR/PIPE/C30030/01
SBIA/PH-I/PK-I/HW/STR/PIPE/C30340/01
SBIA/PH-I/PK-I/HW/STR/PIPE/C41110/01
SBIA/PH-I/PK-I/HW/STR/PIPE/C5030/01
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 184
EPC Agreement
DESCRIPTION
DWG NO.
NETWORK DRAWINGS
1
2
SBIA/PH-I/PK-I/RW/01
SBIA/PH-I/PK-I/FF/01
SBIA/PH-I/PK-I/PW/02
5
6
7
16
17
18
19
SBIA/PH-I/PK-I/PW/01
SBIA/PH-I/PK-I/PW-FF/01
SBIA/PH-I/PK-I/RW/02
SBIA/PH-I/PK-I/PW/SLD/01
SBIA/PH-I/PK-I/RW/SLD/02
SBIA/PH-I/PK-I/FF/SLD/01
SBIA/PH-I/PK-I/WS/ST/01
SBIA/PH-I/PK-I/WS/ST/02
SBIA/PH-I/PK-I/WS/ST/03
SBIA/PH-I/PK-I/PW/ST/01
SBIA/PH-I/PK-I/RW/ST/01
SBIA/PH-I/PK-I/PW-FF/ST/01
SBIA/PH-I/PK-I/RW/ST/02
SBIA/PH-I/PK-I/WS/MISC/01
SBIA/PH-I/PK-I/WS/MISC/02
SBIA/PH-I/PK-I/WS/MISC/03
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 185
EPC Agreement
DESCRIPTION
2
3
4
5
6
7
8
9
10
11
12
13
14
DWG NO.
SBIA/PH-I/PK-I/SWD/01
SBIA/PH-I/PK-I/SWD/02
SBIA/PH-I/PK-I/SWD/03
SBIA/PH-I/PK-I/SWD/04
SBIA/PH-I/PK-I/SWD/05
SBIA/PH-I/PK-I/SWD/06
SBIA/PH-I/PK-I/SWD/07
SBIA/PH-I/PK-I/SWD/08
SBIA/PH-I/PK-I/SWD/09
SBIA/PH-I/PK-I/SWD/10
SBIA/PH-I/PK-I/SWD/11
SBIA/PH-I/PK-I/SWD/12
SBIA/PH-I/PK-I/SWD/13
SBIA/PH-I/PK-I/SWD/14
DESCRIPTION
DWG NO.
NETWORK DRAWINGS
1
2
SBIA/PH-I/PK-I/IE/01
SBIA/PH-I/PK-I/IE/02
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 186
EPC Agreement
3
4
5
6
7
8
9
10
SBIA/PH-I/PK-I/IE/03
SBIA/PH-I/PK-I/IE/04
SBIA/PH-I/PK-I/IE/05
SBIA/PH-I/PK-I/FS/01
SBIA/PH-I/PK-I/FS/02
SBIA/PH-I/PK-I/FS/03
SBIA/PH-I/PK-I/FS/04
SBIA/PH-I/PK-I/FS/05
STANDARD DRAWINGS
11
12
13
14
15
16
17
18
19
20
1.5
SBIA/PH-I/PK-I/SEW/01
SBIA/PH-I/PK-I/SEW/02
SBIA/PH-I/PK-I/SEW/03
SBIA/PH-I/PK-I/SEW/04
SBIA/PH-I/PK-I/SEW/05
SBIA/PH-I/PK-I/SEW/06
SBIA/PH-I/PK-I/SEW/EL/01
SBIA/PH-I/PK-I/SEW/EL/02
SBIA/PH-I/PK-I/SEW/EL/03
SBIA/PH-I/PK-I/SEW/MISC/01
ELECTRICAL
ELECTRICAL
S.NO.
1
DESCRIPTION
SUBSTATION LOCATION AND CABLE
ROUTING DRAWING
DWG NO.
SBIA/PH-I/PK-I/EL/01
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 187
EPC Agreement
SBIA/PH-I/PK-I/EL/02
SBIA/PH-I/PK-I/EL/03
4
5
6
7
SBIA/PH-I/PK-I/EL/04
SBIA/PH-I/PK-I/EL/SL/01
SBIA/PH-I/PK-I/EL/HM/01
SBIA/PH-I/PK-I/EL/GAD/01
DESCRIPTION
CONTOUR MAP OF SHENDRA
INDUSTRIAL AREA
STAGING AND PHASING PLAN
DWG NO.
SBIA/PH-I/PK-I/GE/01
SBIA/PH-I/PK-I/GE/02
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 188
EPC Agreement
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 189
EPC Agreement
1.0
Project Facilities
The Contractor shall design and construct the Project Facilities in accordance with
the provisions of this Schedule C. Such Project Facilities shall include;
1.1
Project Facilities
Each of the Project Facility is briefly described below;
(a)
Road Side furniture and Road markings & signage shall be provided in accordance
with the provisions as per Schedule D.
The road side furniture shall include the provision of the:
i) Overhead Gantry signs: location and Nos. as given in table below;
Table 1
S. No.
Road ID
Junction No.
Total Nos.
1
2
3
A2
A3
A3
27
19
4
3
2
3
A3
Page 190
EPC Agreement
Street Lighting
Street lighting within the Right of Way shall be as per road plans in Drawings
volume. This work comprises of poles & fixtures, lighting cables, optical fibre
cables, controllers etc.
Table 2
S.No.
Element
Proposed Minimum
Illumination Level
(Lux)
In accordance with
the Standards and
specifications
Street lighting and High mast lighting shall be provided in accordance with
the Standards and Specifications as referred in Schedule-D.
(c)
Guard rails
Guard rails shall be confined to junctions at the traffic islands to retain the
landscape/plantation from animal menace, this shall be provided in accordance
with the Standards and Specifications as referred in Schedule-D.
(d)
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 191
EPC Agreement
Appendix C I
1.0
Typical Drawings
Typical Drawings given in Appendix C I (Refer B XII).
I. Miscellaneous Drawings (Refer B XII).
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 192
EPC Agreement
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 193
1.0
EPC Agreement
Construction
The Contractor shall comply with the Specifications and Standards set forth in
Annex- I of this Schedule-D for Construction of the Project Roads and Utilities/
Services.
2.0
Design Standards
The Project Roads and Utilities/ Services shall conform to design requirements
set forth in Annex-I of this Schedule-D.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 194
EPC Agreement
Annexure I
(Schedule-D)
The Codes, Standards and Technical Specifications applicable for the design
and Construction of Project components are:
i.
ii.
iii.
iv.
v.
vi.
Four lane and Six lane Manuals i.e. IRC: SP-84-2014, IRC: SP-87-2013 as
per the cross section of road
vii.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 195
1.2
EPC Agreement
II.
III.
Euro Codes
IV.
1.3
1.4
List of Standards
List of Standards are given in Table: 1, Table: 2, Table: 3 and Table: 4.
Latest revision of codes shall be referred.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 196
EPC Agreement
Table 1:
S. No.
Description
Code/Document
No.
IRC:11-1962
IRC:54-1974
IRC:65-I976
IRC:69-1977
IRC:70-1977
IRC:86-1983
IRC:92-1985
10
IRC: 103-2012
11
IRC: 106-1990
IRC:98-2011
IRC:99-1988
13
IRC:35-1997
14
IRC:67-2012
15
IRC:SP:31-1992
16
IRC:SP:23-1983
17
Guidelines for the design of curves for Highways & Design tables
(First Revision)
IRC:38-1988
18
Guidelines on Design of At-Grade Intersections in Rural & Urban Areas IRC:SP: 41-1994
19
IRC:SP: 44-1996
20
IRC:SP: 50-2013
12
21
22
23
24
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
IRC:SP: 12-1973
IRC: 32-1969
IRC:37 -2012
IRC:58 -2011
IRC:3-1983
Page 197
EPC Agreement
Table 2:
Element of
roads/services
Ground
improvement
Description
State-of-the-Art-Report: High Embankments on Soft
HRB SR No.14,1994 Ground, Part B Ground Improvement
State-of-the-Art-Report: Compaction of Earthwork and
Embankment filling HRB SR No.3,1999 Subgrades
IRC: 37- 2012
Pavement design
Road markings
IRC: 35-1997
Signage
IRC:67-2012
Landscaping
IRC:SP:21-2009
Pedestrian facilities
IRC:103-2012
Cycle tracks
IRC:11-1962
Safety features
IRC:SP: 44-1996
Traffic lights
Junctions / Median
openings
IRC: 93-1985
IRC:SP:41-1994
IRC : 112 -2011
IRC: 5-1998
Structures
IRC: 6-2014
IRC: 24-2010
IRC: 78-2014
IRC: 83-2002 (Part
III)-
Protection Works
IRC:89 - 1998
IRC:75-1979
Erosion control
IRC:56-2011
Slope stability
HRB SR.No.1,2000
IRC:86-1983
CPHEEO,
IRC SP-42 2014
IRC SP-50 2013
Retaining structure
High embankments
Drains
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 198
EPC Agreement
IS : 1255 1983
(Reaffirmed 1995)
IEC:60947
IEC : 60598 2 3
IUT (Institute of Urban Transport)
IS : 2309
IS : 3043
IEC : 61439
IEC:60947
IEC : 60598 2 3
IUT (Institute of Urban
Transport)
CIE (Industrial commission
of illumination)
IS : 2309
IS : 3043
IS : 1944
IS : 1367
BSEN ISO 1461
BS EN 10025-1:2004
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 199
EPC Agreement
1.0
1.1
Background
The potable water for this Project area will be fed from the WTP of 72 MLD scheme
already under execution by MIDC. The WTP is proposed at Khodegaon. The water
source is Jayakwadi dam. Potable water will be fed from a branch line in the existing
gravity main to the Underground Service Reservoir (UGSR) located at a distance of
3.1 km from the main gravity line within the Project area (Tap off point shall be
provided on the main gravity line coming from Break Pressure Tank at Khodegaon,
on service road parallel to Jalna road near existing main entrance of Shendra-Bidkin
industrial area.). Then the potable water shall be partly distributed by gravity from
UGSR to a part of the Project area and shall be partly pumped to the elevated service
reservoir (ESR) and thereon it is supplied under gravity to the balance Project area.
2.0
Population Details
Population for Potable water is as defined below.
Table 1: Population for Potable Water Supply
S. No
No. of
Employees
Description
Industrial
11663
Industrial PAP
7106
Logistics/Warehousing
Residential
Utilities
Commercial
24792
CBD
13628
4066
388
10
Truck Terminal
109
11
Water Body
12
Road
Population
67657
200
Total
61952
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
67657
Page 200
EPC Agreement
3.0
Sr. No.
Particulars
1.
135
lpcd
2.
45
lpcd
3.
45
lpcd
4.
Workforce
lpcd
5.
Convention Centre
Unit
15
lpcd
6.
Hotel
180
7.
Service Apartments
135
lpcd
5.0
6.0
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 201
EPC Agreement
water from UGSR to OHSR will be fed through a rising main of approximately 110
m in length. A pumping station is proposed with following recommendations:
The design parameters for the Potable water rising mains shall be as follows:
Table 3: Design Parameters for Potable Water Rising Main
S No
1
2
3
4
5
6
7
Design Parameters
Minimum Residual Pressure above FSL
of OHSR
Pumping hours
Design Velocity
Max. Unit head loss in the Pipe
Hazen- Williams coefficient
Pipe Material
Working pressure in the pipelines
Value
2.0 m
22
1.0 m/sec - 2.5 m/sec
10 m/Km.
140
DI K-9
30-60 m
The rising main should be designed based on economical size of rising main and
water hammer calculations with reference to CPHEEO Manual and IS codes.
6.1
Description
FOUNDATION
SUPER STRUCTURE
Specification
As per structural design based on soil
investigation.
2.1
Structure
3
3.1
4
5
FLOORING
Flooring in pump room
RAILING
FINISHING
5.1
External
5.2
Internal
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 202
EPC Agreement
7.0
S No.
1
Staging Height
25-30 m
Type
Foundation
The outside and inside finishes of the OHSR shall be as per the finishes mentioned
for civil Structures in Section 6.1 above.
8.0
Design Parameter
Value
10 m for Industries
5.0 m for high rise and bulk
consumers
1.5
Peak factor
Losses as Unaccounted for water (UFW)
10% losses
to be considered for designing
200 mm Moorum bedding for
Bedding
non-rocky stretches
Clear cover over pipe
1.0 m (minimum)
24x7 : gravity fed from UGSR
Basis of supply to consumers
and OHSR
Max. Unit head loss in the pipe
10m/KM
Hazen William Coefficient
140(DI); 145(HDPE)
HDPE(PE-100)
Pipe Material
DI-K7 & DI-K9
3
4
5
6
7
8
9
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 203
EPC Agreement
1.1
Background
The recycled water is pumped from Recycled water UGSR within the STP/CETP area
to the Recycled Water Overhead/ Elevated service reservoir within the Project area.
The OHSR is planned based on topography and coverage area of recycled water
supply in the Project area.
2.0
3.0
Description
Industrial
Horticultural
4.0
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 204
EPC Agreement
Design Parameters
Minimum Residual Pressure above FSL of OHSR
Pumping hours
Value
2.0 m
22
3
4
Design Velocity
Max. Unit head loss in the Pipe
Pipe Material
DI K-9
35-40 m
140
The rising main should be designed based on economical size of rising main and
water hammer calculations with reference to the CPHEEO Manual and IS codes.
A pumping station is proposed with following recommendations:
22 hours operation of pumping.
RCC Civil Works
1 working + 1 standby arrangements for single pumping operation
2 working + 1 standby arrangements for multiple pumping operations
4.1
Description
FOUNDATION
SUPER STRUCTURE
Specification
As per structural design based on soil
investigation.
2.1
Structure
3
3.1
4
5
FLOORING
Flooring in pump room
RAILING
FINISHING
5.1
External
5.2
Internal
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 205
EPC Agreement
5.0
Design Parameters
2
3
4
Staging Height
Type
Foundation
Value
2.1 ML of daily recycled water
demand
25-30 m
Circular & Intze type
Raft foundation / Pile Foundation
The outside and inside finishes of the OHSR shall be as per the finishes mentioned for
civil Structures in Section 4.1 above.
6.0
Design Parameter
Minimum residual pressure
Peak factor
Losses as Unaccounted for water
(UFW) to be considered for
designing
Bedding
5
6
7
8
Pipe Material
Value
10 m
1.5
10% losses
200 mm Moorum bedding for
non-rocky stretches
1.0 m (minimum)
24x7 : gravity fed from ESR
10m/KM
140(DI); 145(HDPE)
250 mm and below Dia:
HDPE (PE-100)
Above 250 mm Dia: DI-K7
Pumping Mains : DI-K9
List of Standards and Specifications for Potable and Recycled Water Supply
The design and Construction of potable water and recycled water supply pipelines
including the design and Construction of RCC elevated service reservoirs and other
water retaining Structures shall conform to design requirements and Construction
specifications set out in the following Indian and International Standards.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 206
EPC Agreement
Code or Standard
Manual for Water Supply &
Treatment
Manual on operation and
Maintenance on water supply
SP 7 (Part-9 Section-1) 1983
SP 35:1987
IS 2065:1983
Description
CPHEEO Manual for Water Supply & Treatment
1999-MoUD, GoI
CPHEEO Manual on Operation and Maintenance
of water supply systems, 2005 MoUD, GoI
National Building Code of India
Hand book on water supply & drainage
Code of practice for water supply in buildings
Code of Basic requirements for water supply,
IS 1172 :1993
drainage and sanitation
Code of practice for concrete structure for the
IS. 3370 part I to IV
storage of liquids
IS 456-2000
Code of Practice for plain and reinforced concrete
Criteria for earthquake resistant design of
IS 1893-2002 part I to V
structures
Detailing of reinforced concrete Structures
IS 13920-1993
subjected to seismic forces
Criteria for design of R.C.C. staging for overhead
IS. - 11682 / 1985
tanks
Code for exploration to find the safe bearing
IS 1992-1969 / IS 6403-1971
capacity
IS 2309-1969
Code for Lighting arrestors
Code of practice for design loads for building and
IS 875 part I to III,1987
structures
IS 7357
Code of practice for structural design of tanks
High strength deformed steel bars and wires for
IS 1786-1985
concrete reinforcement
Electrically welded steel pipes for water, gas and
IS 3589-2000
sewerage (150 to 2000 mm nominal size)
Code of practice for laying of welded steel pipes for
IS 5822
water supply
IS 1916-1989
Code for outside coatings for MS pipes
IS 7322-1989
Code for MS Specials
IS: 638
Specification for rubber and insertion jointing.
I.S. 1538 (Part I to XXII)
Specification for cast Iron fittings for pressure pipes
1976
for water, gas and sewage
IS: 3658-1981
Code of practice for liquid penetrant flaw detection
IS. 226-1975
Specification for Structural steel
High density polyethylene pipes for potable water
IS 4984/1995
supplies
Ductile iron fittings for pressure pipes for water, gas
IS: 9523
and sewerage
IS: 1500
Code for Hardness test for DI pipes
IS:909-1976
Code for C.I. Fire Hydrants
Code of practice for plastic pipework for potable
IS 7634 Part-2 (2012)
waterLaying and jointing of polyethylene pipes
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 207
EPC Agreement
S. No.
Code or Standard
30.
IS 8360 :2003
31.
IS 8008
32.
33.
IS 11606-1986
IS 1726 : 1991
34.
IS 3764-1966
35
IS 11906:1986
36
IS 5477
37
IS 9668:1980
38
IS 8062
39
40
41
42
IS 12288:1987
IS 779:1994
BIS IS 2104: 1981
IS2373:1981
43
44
IS 6784:1996
45
IS 14846:2000
46
IS 2906:1990
47
IS 2685:1971
48
IS 3950:1979
49
IS 5312
50
IS 9739:1981
51
IS 2692:1978
52
IS 10446:1983
53
IS 10500:2012
54
IS2951-1965
55
56
Description
Fabricated high Density polyethylene ( HDPE)
fittings for potable water supplies
Injection-molded HDPE fittings for potable water
supplies
Methods of sampling cast iron pipes and fittings
Cast iron manhole covers and frames -specification
Safety code of Excavation Works and related
Drilling Operations
Recommendations for cement mortar lining for cast
iron, Mild steel and Ductile Iron pipes and fittings
for transportation of water
Methods for fixing the capacities of reservoirs
Code of practice for provision and Maintenance of
water supply for fire fighting
Code of practice for cathodic protection for steel
structures
Code of practice for laying of ductile iron
Water meters (Domestic Type)
Water meter boxes (domestic type)
Water meter (bulk type)
Code of Practice for selection, installation and
Maintenance of domestic water meters
Method for performance testing of water meters
(domestic type)
Sluice valves for water Works purposes (50 to 1200
mm size)
Sluice valves for water Works purposes (350 to
1200 mm size)
Code of practice for selection, installation and
Maintenance of sluice valves
Surface boxes for sluice valves
Swing check type reflux (non-return) valves for
water Works purposes
Pressure reducing valves for domestic water supply
systems
Ferrules for water services
Glossary of terms relating to water supply and
sanitation
Drinking water quality
Recommendation for estimation of flow of liquids
in closed conduits.
A guideline note on
Guidelines for preparation of DPRs for water supply
continuous water supply
system by MoUD, 2013
(24X 7 supply)
Advisory note on
Guidelines for preparation of DPRs for water supply
improving Urban Water
system by MoUD, 2013
Supply & Sanitation Services
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 208
EPC Agreement
ISO: 2531-1991
ISO: 4179-1985
BS 3416
ISO: 8179-1995
ISO: 4633-1996
AWWA C600
BSEN -545
10
11
Description
Design method for ductile iron pipes
Ductile iron pipes, fittings and accessories for
pressure pipelines
Ductile iron pipes for pressure and non-pressureCentrifugal cement mortar lining General
requirements
Bitumen based coatings for cold application,
suitable for use in contact with Potable water
Ductile iron pipes-External coating-Part-1
Metallic Zinc with finishing layer
Rubber seals-Joint rings
Installation of ductile iron water mains and their
appurtenances
Code for Ductile Iron Flanges and Specials
Steel Pipe- A guide for design and Installation
(Fourth Edition)
Ductile Iron Pipe and Fittings (Third Edition)
PE Pipe- Design and Installation (First Edition)
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 209
EPC Agreement
1.1
Background
The firefighting water for this Project area will be fed from the UGSR for Potable
water. The provision for firefighting water demand is kept in this UGSR as a
separate enclosure within the Potable water supply UGSR. The system will comprise
of a pumping system along with necessary appurtenances and a Pump house near the
enclosure for firefighting storage. The pumps will be of Centrifugal type of required
horse power to provide 35m residual head at the farthest end of external fire hydrant
network.
The firefighting water demand is approximately 1.5MLD and suitable sized UGSR
enclosure is required so that the total water available for Potable use shall not be less
than 20 ML at any times and total firefighting water available shall be 1.5MLD at all
times.
A suitable network to carry the water to firefighting hydrants is also to be provided
along with the necessary appurtenances such as valves, fire hydrants etc.
The pipelines are of DI-K9 Material . Total network is as per Drawings.
1.2
1.3
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 210
EPC Agreement
1.4
S. No.
Type of Material
DI (K9)
150
As per Drawings
S. No.
Description
FOUNDATION
SUPER STRUCTURE
2.1
3
3.1
Structure
Specification
As per structural design based on soil
investigation.
R.C.C. framed Construction with brick
work or load bearing Construction
with intermediate columns as per
design.
FLOORING
Flooring in pump room
RAILING
FINISHING
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 211
EPC Agreement
S. No.
5.1
5.2
1.5
Description
External
Internal
Specification
Fire Hydrant
Suitable numbers of two-way external fire hydrants are to be provided at a maximum
distance of 45m centre to centre.
The relevant IS codes for firefighting are as follows:
S. No.
1
2
Code or Standard
Manual for Water
Supply & Treatment
SP 7 (Part-9 Section-1)
1983
IS 456-2000
IS 1893-2002 part I to V
IS 13920-1993
IS 7357
IS 1786-1985
10
IS 3589-2000
11
IS 5822
12
13
14
IS 1916-1989
IS 7322-1989
IS: 638
I.S. 1538 (Part I to
XXII) 1976
15
16
IS: 3658-1981
17
IS: 9523
18
IS: 1500
Description
CPHEEO Manual for Water Supply &
Treatment 1999-MoUD, GoI
National Building Code of India
Code of practice for concrete structure for the
storage of liquids
Code of Practice for plain and reinforced
concrete
Criteria for earthquake resistant design of
structures
Detailing of reinforced concrete Structures
subjected to seismic forces
Code of practice for structural design of tanks
High strength deformed steel bars and wires
for concrete reinforcement
Electrically welded steel pipes for water, gas
and sewerage (150 to 2000 mm nominal size)
Code of practice for laying of welded steel
pipes for water supply
Code for outside coatings for MS pipes
Code for MS Specials
Specification for rubber and insertion jointing.
Specification for cast Iron fittings for pressure
pipes for water, gas and sewage
Code of practice for liquid penetrant flaw
detection
Ductile iron fittings for pressure pipes for
water, gas and sewerage
Code for Hardness test for DI pipes
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 212
EPC Agreement
S. No.
Code or Standard
19
IS:909-1976
20
IS 11606-1986
21.
IS 1726 : 1991
22.
IS 3764-1966
23.
IS 11906:1986
24.
IS 5477
25.
IS 9668:1980
26.
IS 12288:1987
27.
IS 14846:2000
28.
IS 2906:1990
29.
IS 2685:1971
30.
IS 3950:1979
31.
IS 5312
32.
IS 9739:1981
33.
IS 2692:1978
34.
IS 10446:1983
35
IS2951-1965
36
IS 904-1983
37
IS 1641-1988
38
IS 2871 - 2012
39
IS 2469 - 1988
40
IS 13039 - 1991
41
IS 15301 - 2003
42
SP-7 : Part IV
Description
Code for C.I. Fire Hydrants
Methods of sampling cast iron pipes and
fittings
Cast iron manhole covers and frames
specification
Safety code of Excavation Works and related
Drilling Operations
Recommendations for cement mortar lining for
cast iron, Mild steel and Ductile Iron pipes and
fittings for transportation of water
Methods for fixing the capacities of reservoirs
Code of practice for provision and
Maintenance of water supply for fire fighting
Code of practice for laying of ductile iron
Sluice valves for water Works purposes (50 to
1200 mm size)
Sluice valves for water Works purposes (350 to
1200 mm size)
Code of practice for selection, installation and
Maintenance of sluice valves
Surface boxes for sluice valves
Swing check type reflux (non-return) valves for
water Works purposes
Pressure reducing valves for domestic water
supply systems
Ferrules for water services
Glossary of terms relating to water supply and
sanitation
Recommendation for estimation of flow of
liquids in closed conduits.
Specifications for two-way and three-way
suction collecting heads for firefighting
purposes
Code of practice for fire safety of building
(general) General principles of fire grading
and classification
Branch Pipe, Universal for firefighting purpose
- Specification
Specifications for pumps for firefighting
system
External Hydrant systems Provision and
Maintenance Code of Practice
Installation and Maintenance of firefighting
pumps Code of Practice
National Building Code
The above limit is not exhaustive and provisions of any other relevant IS code will
also be bound to be followed to provide an efficient firefighting network.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 213
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
EPC Agreement
Page 214
EPC Agreement
1.1
Background
The Sewerage network system would be designed for the expected domestic/industrial
sewage flows from residential as well as other sectors such as commercial &
institutional and Industrial. Sewage flow from a plot shall be primarily based on the
estimated population for the plot and per capita sewage generation rate as per the
CPHEEO manual/ National Building Code norms/ as per Development Plan.
STP/CETP is planned to develop in modular basis and built under separate package.
2.0
S. No.
1.
Design Parameters
Ground water infiltration
Value
375 ltr/day/manhole
Residential Peak factor:
Contributing Population Peak Factor
2.
Peak Factor
Up to 20,000
3.00
20,000 to 50,000
2.50
50,000 to 7,50,000
2.25
Above 7,50,000
2.00
Capacity of conduits
4.
Minimum velocity
5.
Depth of cover
6.
7.
Manholes Domestic
@ 30 m c/c distance
Manholes Industrial
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 215
EPC Agreement
S. No.
9
10
Design Parameters
Pipe Material for Domestic
sewage.
Pipe Material for Industrial
sewage
Value
RCC NP3 and RCC NP4 for Road crossing
RCC NP3 and RCC NP4 for Road crossing with
minimum 5 mm HDPE lining* with T ribs of
9.5mm height at 64 mmc/c.
* The HDPE Rib lining sheet is thermoplastic Material with Elongation factor of
200% having excellent weld ability which can be easily welded by wedge wielding
with high jointing strength.
3.0 Pumping Main for Sewage Collection
Sewage collected from the branch sewers will be conveyed through pumping main to
the nearest gravity manhole or the Sewage Treatment Plant for further treatment.
The design parameters for the pumping main for sewage collection shall be as
follows:
Table 2: Design Parameters for Pumping Main
S.No
4.0
Design Parameters
Value
1.
Velocity
2.
Pipe Material
D.I. K-9
Description
FOUNDATION
SUPER STRUCTURE
2.1
Structure
3
3.1
FLOORING
Flooring in pump room
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Specification
As per structural design
based on soil
investigation.
R.C.C. framed
Construction with brick
work or load bearing
Construction with
intermediate columns as
per design.
Vacuum dewatered
Page 216
EPC Agreement
S.No.
4
5
Description
RAILING
FINISHING
Specification
concrete.
GMS with Painting
Paint Weather Coat
paints.
5.1
External
5.2
Internal
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
10 year warranty
with chequered tiles
on slab top
Acrylic paint inside
the pump house.
Food grade epoxy,
chlorinated
rubberised paint
inside the reservoir.
Page 217
EPC Agreement
Code or Standard
Description
Manual for Water Supply & CPHEEO Manual for Water Supply & Treatment
Treatment
1999-MoUD, GoI
SP 35:1987
IS 1172 :1993
IS 456-2000
IS 1893-2002 part I to V
10
11
12
IS 7357
13
IS 1786-1985
14
IS: 638
15
IS. 226-1975
16
IS: 9523
17
IS: 1500
18
IS 3764-1966
19
IS 11906:1986
20
IS 8062
21
IS 12288:1987
22
IS 14846:2000
23
IS 2906:1990
24
IS 2685:1971
8
9
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 218
EPC Agreement
S.No
Code or Standard
Description
25
IS 3950:1979
26
IS 5312
27
IS 10446:1983
28
IS 2951-1965
31
Advisory note on
Guidelines for preparation of DPRs for water
improving Urban Water
supply system by MoUD, 2013
Supply & Sanitation Services
Indian Standard Code: Methods of Sampling Test
Is :4733-1972
Sewage Effluent
IS: 6908-1975
Indian Standard Code: Sewage and Drainage
32
33
IS:1538-(PT-XXIV)-1 982
34
IS 5600: 2002
35
IS 5611 :1987
36
IS: 5600-1970
37
IS : 4764-1973
38
IS 6279 :1971
39
IS 6280:1971
Sewage screens
40
IS 7232:1974
41
44
IS 7784: Part 1 & 2: Sec 1 to Indian Standard Code: Code of practice for design
5
of cross drainage work Part 1 General features
Code of practice for ancillary Structures in
IS 4111(Part 1):1986
sewerage system: Part I Manholes
Code of practice for ancillary Structures in
IS 4111(Part 4):1968
sewerage system: Part 4 Pumping stations and
pumping mains (rising mains)
IS 12251:1987
Code of practice for drainage of building
45
IS 12288:1987
46
SP 35(S&T): 1987
47
IS 458
48
IS 651
29
30
42
43
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 219
EPC Agreement
S.No
Code or Standard
Description
49
IS 783
50
IS 1729
51
IS 4885
52
53
IS-8112: 2013
54
IS-383: 1970
55
IS:3597 (1998)
56
IS: 783
57
IS:376
58
IS: 1077
59
IS:3102
60
IS: 395
61
IS: 2212
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 220
EPC Agreement
1.2
Once in 5 year event flows for secondary storm water drainage channels;
Once in 10 year event flows for minor culverts (5-year discharge < 10 m3/s);
Once in 25 year event flows for major culverts (5-year discharge > 10 m3/s); and
RAINFALL INTENSITY
Flood Estimation Report, Upper Godavari (Sub-Zone 3e) (FER) of the Central Water
Commission was used for design daily rainfall depth data for 25 and 50 year return
period events during the preliminary design stage. Intensity-Duration-Frequency
(IDF) rainfall data derived during the master plan stage was used for conversion ratios
for different return period events lower than 25 years and short duration high intensity
rainfall data for the required duration is derived using the Indian Meteorological
Department (IMD) formula. However at least 30 years of rainfall data from the
Aurangabad rain gauge station will be considered for formulating IDF curves during
the detailed design stage.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 221
EPC Agreement
S. No.
Design Parameter
Value
System
Gravity System
Time of Concentration
Coefficient of Runoff
Mannings n Value
< 0.3
0.10
0.3 to 0.9
0.15
0.9 to 1.5
0.30
>1.50
Depends on Discharge
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 222
EPC Agreement
2-year
(mm/hr)
96.80
48.40
32.27
24.20
19.36
16.13
13.83
12.10
10.76
9.68
8.80
8.07
6.05
4.84
4.03
5-year
(mm/hr)
115.80
57.90
38.60
28.95
23.16
19.30
16.54
14.48
12.87
11.58
10.53
9.65
7.24
5.79
4.83
10-year
(mm/hr)
136.80
68.40
45.60
34.20
27.36
22.80
19.54
17.10
15.20
13.68
12.44
11.40
8.55
6.84
5.70
25-year
(mm/hr)
168.40
84.20
56.13
42.10
33.68
28.07
24.06
21.05
18.71
16.84
15.31
14.03
10.53
8.42
7.02
50-year
(mm/hr)
189.40
94.70
63.13
47.35
37.88
31.57
27.06
23.68
21.04
18.94
17.22
15.78
11.84
9.47
7.89
IDF Curves
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 223
EPC Agreement
Description
Data
A.
General
Type
Service
Indoor
IP42
Voltage
36KV
Frequency
50Hz 3%
Phase
System ground
Earthed
10
Earthing bus
50 x 6 mm Copper (Min.)
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 224
EPC Agreement
S.No
Description
Data
11
As per requirement
12
Copper
13
90 deg C
100kA (min)
14
15
16
17
17.1
17.2
As required
31.5kA for 1 sec
18
Control voltage
110V DC
19
Paint
RAL 7032
20
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 225
EPC Agreement
S. No
Data
A.
General
Type
Service
Indoor
IP42
Voltage
12KV
Frequency
50Hz 3%
Phase
System ground
Earthed
10
Earthing bus
50 x 6 mm Copper (Min.)
11
As per requirement
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 226
EPC Agreement
S. No
Description
Data
12
Copper
13
90 deg C
105kA
14
15
16
17
17.1
17.2
As required
40kA for 1 sec
18
Control voltage
110V DC
19
Paint
RAL 7032
20
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 227
EPC Agreement
(I)TRANSFORMER
All Transformers upto 5MVA, shall be ONAN type however all Transformers above
5MVA shall be ONAF type.
The kVA rating and percentage impedance of each transformer will be selected to limit
the rated current and short circuit current to values which are within the current rating and
interrupting capacity of switchgear available.
The capacities of the transformer will be selected as per the following guidelines:
It will be ensured that when all the loads are in operation and the largest motor is started,
the voltage drop at the motor terminals should not be more than 10%.
It will be ensured that all transformers shall be designed to provide 99% efficiency at full
load. It is desirable to operate all transformers at 50-80% loading therefore these
transformers shall be designed with minimum 0.96 power factor and 98% efficiency at
half and 80% load.
Table 1: Transformer Data
Description
S. No
Data
ONAN, ONAF
Reference Standard
IS-2026/IS-11171/IS-1271/IEC-76
As per requirement
Type
Class of insulation
Service (Indoor/Outdoor)
Continuous rating
As required
Voltage Ratio
Type of Cooling
ONAN/ONAF
Number of phases
10
50
11
Connection Symbol
Dyn11
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 228
EPC Agreement
S. No
Description
12
13
Connection
14
System Grounding
Data
as applicable
HV Winding
As per SLD
LV Winding
As per SLD
HV - Side
Ungrounded
LV - Side
Solidly Grounded
15
Winding Material
16
Uni-directional
17
Tap Changer
18
Tapping
19
20
Range
Winding
80 C
80 C
Within safe limit of core & adjacent
Materials
21
Flux density
As required
22
As required
23
24
Creepage distance
25
26
3 Secs
At full load- 0.98 (min)
27
28
Enclosure protection
IP 42
29
Painting
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 229
EPC Agreement
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 230
EPC Agreement
floor standing type and shall have all necessary arrangement to interface with various
devices.
The MMI system shall also be capable for accepting the metering input on RS 485
Modbus protocol.
Data concentrator panel should be powered from the substation battery chargers. The
DC convertor should be the part of the data concentrator.
2.1 Remote IO Panels
All the metering and protection relays at remote locations shall be interfaced with
substation SCADA through Remote IO panels. These panels shall be strategically
located near the load centre RMUs.
Each IO panel shall have sufficient IO cards to accommodate all IOs coming from
RMUs and other field devices. RIO panel shall also be housing necessary Ethernet
switches and LIU cards to communicate with substation SCADA.
The substation SCADA system shall have independent Data concentrator panel which
shall have sufficient IO cards to accommodate all the IOs of substation equipment.
It is envisaged that 25% spare IO cards shall be provided in each IO panel to take care
of future requirement.
Below minimum inputs/outputs shall be taken in SCADA system 1. Power Transformers- Oil level low, Oil temp high, Winding Temp. High,
Buchholz relay, Ventilation Fan failure, Tap changers voltage settings (from
RTCC Panel)
2. Auxiliary Transformers- Oil & Winding Temp. High
3. HV Breakers- ON, OFF, TRIP, Trip Circuit Healthy, Breaker position i.e. Test,
Service and Maintenance mode etc.
4. Ring Main Units (RMUs) - Breaker ON, OFF & Trip status, all metering
parameters.
5. Numerical Relays- All protection parameters and relay status
6. All meters- All metering parameters
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 231
EPC Agreement
Beside above input/outputs, it is envisaged that 25% spare IO cards shall be provided
in each IO panel to take care of future requirement.
2.2 Communication
All protection relays in the substation shall be connected to SCADA system Ethernet
switches through Fibre Optic cables. All protection Numeric Relays shall have fiber
optic ports and shall communicate to Ethernet switch on star topology and shall be
connected to star coupler using fiber optic cables.
Communication from relays to Ethernet switch shall be through single communication
port. Communication from GIS switchboard Ethernet switch to data concentrator
panel shall be simultaneous on redundant ports. RS 485 to FO converters wherever
required shall be part of offered relay/other hardware.
All RMUs shall be made to communicate with substation SCADA system on Fibre
Optic cable. For this purpose remote IO Panel shall be provided near the RMU units
and each RIO panel shall communicate with SCADA system on Fibre Optic network.
The communication protocol shall be selected to transfer all information including
time stamp data from relay to data concentrator/substation MMI. The relay
communication shall be on latest IEC61850 protocol.
The maximum number of relays in one LAN shall be decided so as to achieve
maximum scan time as 600 ms. The above scan time does not include screen refresh
rate at MMI.
To maintain the reliability of Power system and to have better communication
between substations the SCADA system in each substation shall be connected
together. To achieve this purpose, each Data concentrator panel shall be connector
together in Fibre Optic network.
In order to have 100% redundancy in the communication system all five substations
shall be connected together in Fibre Optic Ring system. The successful bidder shall
incorporate all necessary requirements to achieve 100% redundancy in the SCADA
communication system.
The bidder should submit necessary certification for compliance of IEC61850
protocol. In case of proprietary protocol, the protocol converter shall be supplied as a
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 232
EPC Agreement
part of contract. Protocol converter, if provided, should not affect the speed of
communication.
2.3 Man Machine Interface (MMI)
The system should be interfaced with communicable protection & metering devices
and other equipments in the substation in such a way that operator can easily access
the essential information regarding the network and control the same so as to ensure
availability of electric network at its maximum efficiency giving highest utilization of
the installed primary equipments. MMI Software configuration to be carried out to
display the following data at the MMI and shall primarily but not limited to, provide
the following functions:-
Dynamic Single line diagram with bus bar colouring & with status of all
process objects like breaker, isolators etc.
Relay parameterisation.
Object control.
Classification and display of events in alarm class e.g. persisting and fleeting
alarms.
Time synchronization.
The name of the feeder from which the event has generated.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 233
EPC Agreement
System managing.
Engineering.
View only.
sychronised with data concentrator/HMI time clock. GPS unit shall provide in each
substation and shall be synchronised with other substation GPS by using GPS receiver
at substation.
The resolution of time synchronization shall be + 1 millisecond or better throughout
the entire system.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 234
EPC Agreement
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 235
EPC Agreement
FPI shall facilitate quick detection of faulty section of line. The fault indication may be
based on monitoring fault current flow through the device. The unit should be selfcontained requiring no auxiliary power supply. The FPI shall be integral part of RMU.
2.0 Earthing
The earthing system for 33/11kV substations and Ring Main Units (RMUs) shall be
designed as per the requirement of relevant latest editions of IEC, IEEE, Indian Standards
and Indian Electricity Rules.
It is proposed that earthing grid shall be provided in each 33/11kV substation. The
earthing grid shall be designed in accordance wih IEEE80 codes.
General requirements
Earth pit shall be plate type each with minimum 3mtrs. 85mm Dia GI Pipe, alternate
layers of salt and charcoal, LORES (ground enhancing Material ) and watering funnel.
Each equipment in the substation shall be earthed by appropriate size (as per IEEE80
guidelines) copper strip.
In any case the size of earthing strip shall not be less than the minimum size required
to carry the fault current.
Main earthing conductors shall be laid at the depth not less than 1000mm below the
ground.
All the equipments, structure etc shall be earthed by running main and duplicate
earthing conductor from the equipment base along structure to the main mat.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 236
EPC Agreement
Dedicated earthing pits shall be envisaged for each Transformer body and Neutral
earthing.
All the earthing pits shall be bonded together and connected with substation earthing
grid.
Cable trays and supports shall be connected to the earth mat at every 30m interval.
Whenever it passes through walls, floors etc., galvanized iron sleeves shall be
provided for the passage of the conductor. Both end of the sleeve shall be sealed to
prevent entrance of water.
Earthing conductor where ever crossing the road shall be buried at least 1000mm
below the ground level.
Metallic sheaths and Armour of all multi core power cables shall be earthed at both
equipment and switch gear end. Sheath and armour of single core cables shall be
earthed.
The body of all RMU units and HT Panels shall be connected to atleast two distinct
earth pits. For this two different rod earthing pits shall be envisaged near the RMU
units. The depth of the hot dip GI earthing rod shall be atleast 3000mm and diameter
shall not be less than 85mm. The body of each RMU shall be connected to these
earthing pits with two separate earthing strips of same size. The size of earthing strip
shall be determined based on the fault current and switchgear disconnection time.
3.0 Testing
All RMUs and HT Panels shall be tested in accordance with latest editions of the
IEC62271-200 ed1.0 (2003-11), IEC62271-1ed1.0 (2007-10), IEC60129, IEC60529,
IEC60265, IEC60420, IEC60185, IEC60186 & IEC60255.
The contractor shall submit the inspection plan and Quality Assurance Plan for the
consultant and Employers approval.
The contractor shall submit all necessary relevant type and routine test certificates for
consultant and Employers review and approval.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 237
EPC Agreement
IS-3043,
IEEE80,
IEC60364
During the course of the design wherever Indian codes are deemed to be
outdated or are no longer in-line with current international best practice,
internationally recognized standards shall be adopted.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 238
EPC Agreement
(L) CABLES
1.0 Design criteria
Size and type of cables for specific applications shall be selected giving due consideration
to following:
Voltage drop
Ambient conditions
The cross sectional area for HV power cables shall be minimum 95 Sqmm.
1.1 Type of Cable
HV Cables
The power cables for 33kV & 11kV distribution network shall be XLPE, Aluminium
Armored 3 core
grounded type.
All cables shall be heavy-duty type with compact circular stranded Aluminium conductor.
Each conductor shall be with extruded shielding of semi conducting Material , XLPE
insulation and with insulation shielding over individual cores.
Insulation shall be applied through extrusion process and chemically cross-linked in
continuous vulcanization process to comply with the requirements of the relevant
standards. The core insulation shall be with XLPE compound applied over the conductor
by extrusion and shall conform to the requirements of type A compound per IS 583.
The individual cores shall be stranded together with a holding tape provided with a
common covering of extruded inner FRLS sheath of type ST2 compound, galvanized
round steel wire armoured and FRLS PVC outer sheath of type ST2 compound as per IS :
7098 (Pt-II)-latest version.
To protect the cables against rodent and termite attack, suitable chemicals shall be added
into the PVC compound of the outer sheath.
The manufacturing of cables will be of dry curing type.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 239
EPC Agreement
The contractor shall mark it out on the Drawings and also on the Site and obtain the
approval of the engineer/consulting engineer before laying the cable.
Sharp bends shall be avoided; the minimum radius shall not be less than 15 D.
Wherever possible 25% larger radius than specified above shall be used.
The cable shall be clamped at every 600mm at the places where it is laid on a cable
tray.
Whenever cable passes through any floor or wall suitable cut outs shall be made. The
openings shall be sealed using suitable fire resisting Material to prevent fire spreading
and also to prevent entry of water.
Standard cable installation tools shall be utilized for cable pulling. Maximum pull
tension shall not exceed the manufacturers recommended value. Cable grips, reels or
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 240
EPC Agreement
pulleys used shall be properly lubricated. The lubricant shall not injury the overall
covering and shall not set up undesirable conditions of electrostatic stress.
Where groups of HV LV cables are to be laid along the same route, suitable barriers to
(physically) segregate them shall be provided and separated in accordance with
relevant IS code.
Where cable crosses cross roads, water, oil, gas or sewerage pipes, the cables shall be
laid in hume pipes/HDPE ducts. The size of the Hume pipe/HDPE pipe shall be at
least 2.5times the outer diameter (OD) of the cables.
For road crossing, the pipe of the cable shall be buried at not less than one meter
depth. Cables laid below rail track should be at a depth not less than 1500mm, unless
otherwise approved by the engineer. These cables shall be laid in MS pipe of 300mm
dia. Cable shall be protected at all times from mechanical injury and from absorption
of moisture.
Some extra length shall be kept in each cable run at a suitable point to enable one or
two straight through joints to be made at a later date if any fault occurs.
Metal sheath and the Armour of the cable shall be bonded with the earthing system of
the station.
Identification markings on draw pits to be made for HV/LV indications and pit no. to
be identified with the help of fluorescent road marking paint.
Anodized aluminium tag indicating cable number, cable size, feeder from-to, other
details etc at entry & exit of each draw pits to be installed inside the draw pits.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 241
EPC Agreement
A provision of space of appropriate (width) and depth for various sizes of cables and
number of circuits laid in cable trench has been made along the cable route as indicated in
the Typical Cross Section Drawing of road indicating utility corridor. However, in no
case the width and depth of these cable trenches shall not be more than 2mtrs.
The cable trench shall be provided at both sides of the roads. All type-A and type-B roads
shall be provided with 2mtrs width cable trench however, all other roads shall be provided
with 1.5mtrs width cable trench at both sides.
Note- It is proposed that a dedicated cable route shall be indentified for existing HV lines.
The successful bidder shall provide a dedicated cable trench for buried type underground
cables.
All EHV, HV, signal and control cables inside the cable trench shall be installed on the
dedicated cable trays. However, LV cables may be routed along the surface of the trench
wall. All cables shall be suitable supported and spaced by using cable-supporting ties.
Aluminium type engraved tags shall be envisaged at every 30mtrs distance for the
nomenclature and identification of each type of cables.
1.3 Termination Arrangement
Cable termination will be made with aluminium/ tinned copper crimped type solder less
lugs of approved make for all aluminium conductor and stud type terminals.
1.4 Cable Identification
Cable tags will be of 2 mm thick, 20 mm wide aluminium strap of suitable length to
contain cable number as per cable schedule.
1.5 Ferrules
Ferrules will be approved interlocked type & size to suit core size mentioned and will be
employed to designate the various cores of control cable by the terminal numbers to
which the cores are connected, for ease in identification and Maintenance.
1.6 Cable Glands
Cable glands to be supplied will be nickel plated brass double compression type. Glands
for classified hazardous areas will be of CMRS certified and approved by CCE.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 242
EPC Agreement
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 243
EPC Agreement
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 244
EPC Agreement
Particulars
1.
Main Roads
50 lux
0.4
2.
Pedestrian Crossing
50 lux
0.4
3.
1-10 lux
0.4
4.
Cycle Track
20 lux
0.4
5.
Substation rooms
200lux
0.4
6.
Substation Transformer
yard
20lux
0.4
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 245
EPC Agreement
strategically decided as per Site conditions. Each photocell shall be interlocked with
lighting feeder in main lighting distribution board.
Each feeder in main lighting distribution board shall be envisaged with Day/Night timer
(24 hrs), Power contactor, Auto/Manual selector switch, Energy meter etc. All energy
meters shall be communicable to substation SCADA system.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 246
EPC Agreement
A manual on/off override switch shall be provided at lighting distribution boards (LDBs)
to provide manual control of lighting luminaires.
Time clock and photo-cell control shall be provided to give automatic switch on during
darkness and/or low levels of light and off when lighting lux levels are achieved.
The location and installation of Photo cell (light sensors) shall be strategically decided as
per the layout and Site conditions.
The successful contractor shall submit lighting design, layout & calculations (generated
by reputed software like DIALUX) based on the lighting design standards and LUX
levels mentioned in the table 1.0 here in this Section for clients approval.
4.0 Standards and Codes
The illumination system shall be designed, installed and tested in accordance with the
latest editions of the standards - IS-2149, IS-3646, CIE129.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 247
EPC Agreement
N. DESIGN LIFE
Design Life
S.No.
Items
Design
Period in
years
Code Reference
Road layers
Bituminous layers
10
20
Drainage Structures
100
100
100
1
2
Misc Items
High mast - GS
25
CPWD Manual
Light poles - GS
25
CPWD Manual
Underground cabling
20
CPWD Manual
15
CPHEEO Manual
15
CPHEEO Manual
Electric Pump
15
CPHEEO Manual
Diesel Pump
10
CPWD Manual
Diesel Generator
12
CPWD Manual
Sewage Pump
15
CPHEEO Manual
Substation
Transformers
25
CPWD Manual
Switchgear LT/HT
20
CPWD Manual
Voltage Stabilizer
10
CPWD Manual
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Note
Page 248
EPC Agreement
Design Life
S.No.
Items
Design
Period in
years
Code Reference
Civil Structures
Storage by dams
50
CPHEEO Manual
30
CPHEEO Manual
a)
Civil Structures
30
CPHEEO Manual
b)
15
CPHEEO Manual
15
CPHEEO Manual
30
CPHEEO Manual
15
CPHEEO Manual
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Note
Page 249
EPC Agreement
ADDITIONAL SPECIFICATIONS
PART A - Standard Specifications
The Specifications and Standard as specified in Part A of this Schedule D comprise
"Specifications for Road and Bridge Works (Fifth Revision, April 2013), issued by
the Ministry of Road Transport & Highways (MoRT&H), Government of India and
published by the Indian Roads Congress at Sl. No. 1.1 iii apart from the other
Specifications and Standard. (Specification related to exposure condition shall be
adopted Very Severe).
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 250
EPC Agreement
Additional Specifications
The additional specifications shall comprise of specifications for particular items
of work not covered in Part A at Sl. No. 1.1 iii.
The following Appendices describing additional specifications have been added to the
Part A, Standard Specifications:
CLAUSE A-1
Utility ducts
CLAUSE A-2
In the absence of any definite provisions on any particular issue in the aforesaid
Specifications, reference may be made to the latest codes and specifications of IRC,
BIS, ASTM, AASHTO and BS in that order. Where even these are silent, the
Construction and completion of the Works shall conform to sound engineering
practice as approved by the Employers Engineer.
Construction of the Project Road & utility on the Site set forth in Schedule-A
and as specified in Schedule-B together with provision of Project Facilities as
specified in Schedule-C, and in conformity with the Specifications and
Standards set forth in Schedule-D.
b.
c.
Page 251
EPC Agreement
The Contractor shall identify quarries; borrow areas and other sources of Materials
required for the work. Contractor shall satisfy himself that the required Materials are
available in adequate quantities and complying with the requirements of
specifications. No claims shall be entertained on account of non-availability of
Materials and increase in leads etc.
It is the sole responsibility of the Contractor to arrange the quarries, borrow areas etc.,
on license / lease basis or otherwise, and study in detail before tendering, the scope of
taking the quarry on lease. Advance information must be collected by the contractor
regarding the procedure laid down and the consequent delay in arranging the quarries
on lease and must make alternative arrangement to procure the quarry products from
lease holders. No separate payment will be made for arranging such quarries, borrow
areas, etc.
1.5 Clause 110: Encumbrances in Construction Area, Including Trees and Utilities
Sub-Clause 110.7
Delete the Sub-clause 110.7 and shall be read as following:
The contractor may be required to carry out the removal or shifting of certain
services/utilities on specific orders from the Employers Engineer. However for
coordinating the work of cutting of trees and removal of encroachments etc. No
separate payment to the contractor will be made and these will be incidental to the
work.
1.6 Clause 113: General Rules for the Measurement of Works for Payment
Clause 113: shall be read as follows:
All payments and measurements shall be as per schedule H.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 252
EPC Agreement
SUB
BASES,
BASES
(NON
BITUMINOUS)
AND
3.1
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 253
EPC Agreement
mix properties. The laying of mix shall be done after approval of the Employers
Engineer.
In Table: 500-10, the following may be substituted:
Table : Road Grading
Grading
Layer Thickness
75mm to 100mm
50-75mm
Bitumen grade
VG-30
VG-30
Min.4%
Min.4.5%
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 254
EPC Agreement
Air voids at refusal density (300 blows at each end of Marshall Specimen at
Optimum Binder Content) 3% min.
Page 255
EPC Agreement
demonstrated on a suitable site, which is not part of the permanent Works. The rate
of application shall be checked and adjusted as necessary before application on a
large scale is commenced, and thereafter daily."
Sub-Clause 803.3: Ordinary Road Marking Paint
This Clause shall be deleted.
Sub-Clause 803.6: Application
Sub-Clause 803.6.4: Substitute 250gm by 350gms in the last line of this sub-clause
Page 256
EPC Agreement
welding on MS pipe 50mm dia. (NB-MW) and 500mm high or as shown in the
Drawings. All components of signs & supports shall be thoroughly descaled,
cleaned, primed and painted with two coats of epoxy paint. The sign backside
shall be with grey colour and post shall be white colour/ alternate white &
black bands. The post below ground shall be painted with three coats of red
lead.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 257
EPC Agreement
ADDITIONAL SPECIFICATIONS
1.0
1.1
Scope
The work shall consist of laying and jointing of R.C.C. Utility Ducts in accordance
with the requirements of these specifications.
1.2
Materials
Reinforced concrete pipes shall be of NP 4 type conforming to IS: 458 as shown in
the Drawings.
1.2.2 Jointing
The Pipes shall be jointed either by collar joint or flush joint. Caulking shall be
carried out as directed by the Employers Engineer. The provisions of clause 2906
of the specifications shall be followed to the extent applicable. The Employers
Engineer decision shall be final and binding.
2.0
2.1
General
Liquid membrane forming compound are sometimes permitted to be used by the
Employers Engineer for curing concrete for part or whole of the total curing period
as specified in sections dealing with concrete Construction. These membranes
reduce the loss of water from concrete during early hardening period and some type
of compounds also help in reducing the temperature-rise of concrete exposed to
the radiation from the sun. These specifications cover the type and use of such
compounds. However, the use of the same will need specific permission from the
Employers Engineer, who may require a number of Tests to be carried out
for establishing the conformity of the product to these specifications and to establish
that the curing compound and its method of use does not have any unacceptable
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 258
EPC Agreement
effect on the quality of concrete. The cost of the initial acceptance testing and
the quality control testing will be borne by the owner, if the method has been
specified as a requirement by the Employers Engineer. If on the other hand, it is
suggested by the contractor as an alternative to wet-curing, the full cost of testing
will be borne by him and deemed to be included in his rates for concreting. The cost
of curing in any case will be deemed to be part of the concrete rates and will not be
paid extra.
All equipment, Material etc., needed for curing and protection of concrete shall be
at hand and ready for installing before actual concreting begins. Detailed plans,
methods and procedures shall be firmly established, shall be settled and got approved
in writing from the Employers Engineer sufficiently in advance of the actual
concreting.
The equipment and method proposed to be utilized shall provide for adequate
control and avoid interruption or damage to the work of other agencies.
2.2
Curing Compound
The curing compound shall be conforming to ASTM-C-309-81, Type-2, white
pigmented compound. The solids dissolved in vehicle shall be either A (no
restrictions) or Class B (resin as defined in ASTM D-883) as approved by the
Employers Engineer.
White pigmented compound (Type-2) shall consist of finely divided white pigments
and vehicle solids, ready mixed for immediate use without alteration. The compound
shall present a uniform white appearance when applied uniformly to a fresh
concrete surface at a specified rate of application. It shall be of such consistency
that it can be readily applied by spraying to provide uniform coating at temperatures
40 degree centigrade. If two coats are to be applied then it should be applied at an
interval of approximately one hour. They shall adhere to freshly placed concrete
that has stiffened or sufficient resist marking during the application and to damp
hardened concrete and shall form a continuous film when applied at a rate of 5
m/liter. When dry, the covering shall be continuous flexible and without visible
breaks or pin holes and shall remain as unbroken film at least 28 days after
application. It shall not react deleteriously with the concrete.
The compound shall meet with the requirement of water retention test as per
ASTM designation C-156-80. The loss of water in this test shall be restricted to not
more than 0.55 kg/m of exposed surface in 72 hours.
The white pigmented compound (Type 2) when rested as specified in accordance
with method E-79 of ASTM shall exhibit a day light reflectance of not less than
60% of that of magnesium oxide.
It shall fulfill the requirement of drying time when tested in accordance with
ASTM- C-309-81. The compound applied shall be dry to touch in not more than 4
hours. After 12 hours it shall not be tacky or tack off (peel off) concrete when
walked upon nor it shall impart a slippery surface. The liquid compound should be
of a spray able consistency.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 259
3.3
EPC Agreement
3.4
Method of Application
The compound shall be sprayed using mechanical sprayer of approved design
to ensure uniform and continuous membrane on the concrete surface. The coverage
shall be at the rate specified by the manufacturer or at the rate of 4m per
liter or as specified by the manufacturer and approved by the Employers Engineer.
Field trials shall be conducted to decide effective coverage rate, which depends
upon surface finish. The Employers Engineer after verification of the field and
based on the actual experience shall order the rate of application as needed for
achieving the proper curing. With a view to ensure thorough and complete
coverage, approximately one half of the compound for a given area should be
applied by moving the spray gun back and forth in one direction and the remaining
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 260
EPC Agreement
half at right angles to this direction. In case the application is still not found
uniform, the contractor shall have to apply the second coat as and when directed by
the Employers Engineer. If a second coat is to be applied, it should be applied
approximately after an interval of one hour. The curing compound shall generally
be applied as soon as the bleeding water or shine disappears, leaving dull
appearance.
If surface treatment by roughing, hand brushing etc., is required (e.g. as in case
of road pavements) the curing compound should be applied immediately after the
same. Equipment for spraying curing compound shall be of pressure tank type
(5 to 7 kg/cm) with provision of continuous agitation. A curing jumbo with
multiple travelling spray fans shall be provided for effective spray. Spraying on
concrete lining shall be done in such a way that the green concrete is not disturbed
or damaged or any foot impression left. Necessary schemes of spraying by
mechanized means shall be got approved by the Employers Engineer. However, in
emergency (for very small areas/ patches) it can be applied with wire or bristled
brush.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 261
EPC Agreement
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 262
EPC Agreement
1.0
Maintenance Requirements
1.1
The Contractor shall, at all times maintain the Project Components (Roads &
Utilities/Services) in accordance with the provisions of this Agreement, Applicable
Laws and Applicable Permits.
1.2
The Contractor shall repair or rectify any Defect or deficiency set forth in Paragraph
2 of this Schedule-E within the time limit specified therein and any failure in this
behalf shall constitute non-fulfilment of the Maintenance obligations by the
Contractor. Upon occurrence of any breach hereunder, the Employer shall be
entitled to effect reduction in monthly lump sum payment as set forth in Clause 14.6
of this Agreement, without prejudice to the rights of the Employer under this
Agreement, including Termination thereof.
1.3
1.4
1.5
1.6
1.7
1.8
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 263
2.0
EPC Agreement
3.0
4.0
5.0
Emergency Repairs/Restoration
Notwithstanding anything to the contrary contained in this Schedule-E, if any
Defect, deficiency or deterioration in the Project Components (Roads &
Utilities/Services) poses a hazard to safety or risk of damage to property, the
Contractor shall promptly take all reasonable measures for eliminating or
minimizing such danger.
6.0
7.0
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 264
EPC Agreement
damages observed and proposed action to remedy the same shall be sent to the
Employers Engineer.
8.0
9.0
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 265
EPC Agreement
Appendix-E-I (Schedule-E)
REPAIR/RECTIFICATION OF DEFECTS AND DEFICIENCIES
The Contractor shall repair and rectify the Defects and deficiencies specified in
this Appendix E-I of Schedule-E within the time limit set forth in the table below.
Table 1
Nature Of Defect Or Deficiency
(a)
(i)
(iv)
(v)
(vi)
7 (seven) days
7 (seven) days
24 hours
7 (seven) days (Restore immediately if
(vii) Railing, parapets, crash barriers
causing safety hazard)
(c)
Road Side Furniture Including Road Sign And Pavement Marking
Damage to shape or position, poor visibility or loss of
(i)
48 hours
retro-reflectivity
(ii)
(iii)
(iv)
(d)
(i)
(ii)
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 266
EPC Agreement
(e)
(i)
(ii)
(iii)
(i)
(b)
(i)
(c)
(i)
(d)
Temporary measures
Permanent measures
Foundations
Scouring and/or cavitation
Piers, Abutments, Return Walls And Wing Walls
Cracks and damages including settlement and tilting,
spalling, scaling
Bearings (Metallic) of Bridges
15 (fifteen) days
4 (four) hours
4 (four) hours
within 48 hours
within 15 (fifteen) days or as
specified by the Employers
Engineer
15 (fifteen) days
30 (thirty) days
15 (fifteen) days
Greasing of metallic bearings once in a
Year
(i)
(e)
(i)
(f)
(i)
Joints
Malfunctioning of joints
15 (fifteen) days
Other Items
Deforming of pads in elastomeric bearings
7 (seven) days
Gathering of dirt in bearings and joints; or clogging of
3 (three) days
spouts, weep holes and vent-holes
3 (three) days
Damage or deterioration in kerbs, parapets, handrails (immediately within 24 hours if posing
and crash barriers
danger to safety)
Rain-cuts or erosion of banks of the side slopes of
7 (seven) days
approaches
Damage to wearing coat
15 (fifteen) days
Damage or deterioration in approach slabs, pitching,
30 (thirty) days
apron, toes, floor or guide bunds
(ii)
(iii)
(iv)
(v)
(vi)
(b)
Network pipelines
(i)
(ii)
Once in 6 months
(iii)
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 267
EPC Agreement
(d)
i)
ii)
(e)
i)
ii)
(i)
(ii)
(iii)
(iv)
(v)
(vi)
(vii)
(viii)
Battery voltage, battery charger, topping of distilled water, tightness of terminations etc.
Gland packing
Wear and tear of moving parts
Adoption of Electrical energy conservation methods and energy consumption
Electrical contacts
Motors
Meggering of electrical equipment
Watering of earthen pits
Page 268
EPC Agreement
Stuffing boxes should be repacked and the pump & motor should be realigned and reconnected
Overhauling requirement of all equipment
Improvement required if any in operation of plant
Testing and Calibration of all instruments
Transformer cleaning, checking silica gel, oil checking filtering/replacing
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 269
EPC Agreement
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 270
1.
EPC Agreement
Applicable Permits
1.1 The Contractor shall obtain, as required under the Applicable Laws, the following
Applicable Permits:
(a) Permission of the State Government for extraction of boulders from quarry;
(b) Permission of Village Panchayat and Pollution Control Board for installation
of crushers;
(c) License for use of explosives;
(d) Permission of the State Government for Drawing water from river/reservoir;
(e) License from inspector of factories or other competent authority for setting
up batching plant;
(f) Clearance of Pollution Control Board for setting up batching plant;
(g) Clearance of Village Panchayats and Pollution Control Board for setting
up asphalt plant;
(h) Permission of Village Panchayats and State Government for borrow earth; and
(i) Any other permits, clearances or approvals required under Applicable Laws.
1.2
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 271
EPC Agreement
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 272
EPC Agreement
Annex-I
(See Clause 7.1.1)
Performance Security
Employer
WHEREAS:
_______________________________ [name and address of contractor] (hereinafter
called as Contractor) and [name and address of the Employer ], (the
Employer ) have entered into an Agreement (the Agreement) for Design and
Build the Infrastructure Works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area,
Aurangabad, Maharashtra on EPC Basis (Package I) on Engineering, Procurement
and Construction (EPC) basis, subject to and in accordance with the provisions of
the Agreement.
(A)
(B)
The Agreement requires the Contractor to furnish a Performance Security for due and
faithful performance of its obligations, under and in accordance with the Agreement,
during the Construction Period and Defects Liability Period (as defined in the
Agreement) in a sum of Rs. . Crore (Rupees . Crore) (the Guarantee Amount).
(C)
NOW, THEREFORE, the Bank hereby, unconditionally and irrevocably, guarantees and
affirms as follows:
1. The Bank hereby unconditionally and irrevocably guarantees the due and faithful
performance of the Contractors obligations during and under and in accordance with
the Agreement, and agrees and undertakes to pay to the Employer, upon its mere first
written demand, and without any demur, reservation, recourse, contest or protest, and
without any reference to the Contractor, such sum or sums up to an aggregate sum of
the guarantee amount as the Employer shall claim, without the Employer being
required to prove or to show grounds or reasons for its demand and/or for the sum
specified therein.
2. A letter from the Employer , under the hand of an officer not below the rank of
[.of Employer ], that the Contractor has committed default in the due and
faithful performance of all or any of its obligations under and in accordance with the
Agreement shall be conclusive, final and binding on the Bank. The Bank further agrees
that the Employer shall be the sole judge as to whether the Contractor is in default in
due and faithful performance of its obligations during and under the Agreement and its
decision that the Contractor is in default shall be final, and binding on the
Bank, notwithstanding any difference between the Employer and the Contractor, or any
Dispute between them pending before any court, tribunal, arbitrators or any
other authority or body, or by the discharge of the Contractor for any reason whatsoever.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 273
EPC Agreement
3. In order to give effect to this Guarantee, the Employer shall be entitled to act as if the
Bank were the principal debtor and any change in the constitution of the
Contractor and/or the Bank, whether by their absorption with any other body or
corporation or otherwise, shall not in any way or manner affect the liability or
obligation of the Bank under this Guarantee.
4. It shall not be necessary, and the Bank hereby waives any necessity, for the Employer
to proceed against the Contractor before presenting to the Bank its demand under this
Guarantee.
5. The Employer shall have the liberty, without affecting in any manner the liability of
the Bank under this Guarantee, to vary at any time, the terms and conditions of the
Agreement or to extend the time or period for the compliance with, fulfillment and/or
performance of all or any of the obligations of the Contractor contained in the
Agreement or to postpone for any time, and from time to time, any of the rights
and powers exercisable by the Employer against the Contractor, and either to enforce
or forbear from enforcing any of the terms and conditions contained in the Agreement
and/or the securities available to the Employer , and the Bank shall not be released from
its liability and obligation under these presents by any exercise by the Employer of the
liberty with reference to the matters aforesaid or by reason of time being given to the
Contractor or any other forbearance, indulgence, act or omission on the part of
the Employer or of any other matter or thing whatsoever which under any law relating
to sureties and guarantors would but for this provision have the effect of releasing the
Bank from its liability and obligation under this Guarantee and the Bank hereby
waives all of its rights under any such law.
6. This Guarantee is in addition to and not in substitution of any other guarantee or
security now or which may hereafter be held by the Employer in respect of or relating
to the Agreement or for the fulfillment, compliance and/or performance of all or any of
the obligations of the Contractor under the Agreement.
7. Notwithstanding anything contained herein before, the liability of the Bank under
this Guarantee is restricted to the Guarantee amount and this Guarantee will remain in
force for the period specified in paragraph 8 below and unless a demand or claim in
writing is made by the Employer on the Bank under this Guarantee all rights of
the Employer under this Guarantee shall be forfeited and the Bank shall be relieved
from its liabilities hereunder.
8. The Performance Security shall cease to be in force and effect 90 (ninety) days after
the end of the Defects Liability Period as set forth in Clauses 7.1
9. The Bank undertakes not to revoke this Guarantee during its currency, except with
the previous express consent of the Employer in writing, and declares and warrants
that it has the power to issue this Guarantee and the undersigned has full powers to do
so on behalf of the Bank.
10. Any notice by way of request, demand or otherwise hereunder may be sent by
post addressed to the Bank at its above referred branch, which shall be deemed to have
been duly authorized to receive such notice and to effect payment thereof forthwith, and
if sent by post it shall be deemed to have been given at the time when it ought to have
been delivered in due course of post and in proving such notice, when given by post, it
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 274
EPC Agreement
shall be sufficient to prove that the envelope containing the notice was posted and a
certificate signed by an officer of the Employer that the envelope was so posted
shall be conclusive.
11. This Guarantee shall come into force with immediate effect and shall remain in force
and effect for up to the end **** month in the year ***** or until it is released earlier
by the Employer pursuant to the provisions of the Agreement.
Signed and sealed this .. day of . 20.. at
SIGNED, SEALED AND DELIVERED
For and on behalf of the Bank
by: (Signature)
(Name) (Designation)
(Code Number)
(Address) NOTES:
(i) The Bank guarantee should contain the name, designation and code number of
the officer(s) signing the guarantee.
(ii) The address, telephone number and other details of the head office of the Bank as well
as of issuing branch should be mentioned on the covering letter of issuing branch.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 275
EPC Agreement
Annex-II
(Schedule-G)
(See Clause 7.5.3)
Form for Guarantee for Withdrawal of Retention Money
..
.Employer ,
Mumbai
WHEREAS:
[Name and address of contractor] (hereinafter called the Contractor) has executed
an Agreement (hereinafter called the Agreement) with the [name and address of the
Employer ], (hereinafter called the Employer ) for the Design and Build the
Infrastructure Works for Roads, Drains, Culverts, Minor Bridges, Water Supply, Sewerage,
Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad, Maharashtra on
EPC Basis (Package - I) on Engineering, Procurement and Construction (the EPC) basis,
subject to and in accordance with the provisions of the Agreement.
a.
in accordance with the Clause 7.5.3 of the Agreement, whenever the amount of
the retention money
(hereinafter called Retention Money) held by the
Employer exceeds 1% (one per cent) of the Contract Price, the Contractor may,
at its option, withdraw the Retention Money after furnishing to the Employer a
Bank guarantee for an amount equal to the proposed withdrawal.
b.
Page 276
EPC Agreement
or any Dispute between them pending before any court, tribunal, arbitrators or any
other authority or body, or by the discharge of the Contractor for any reason whatsoever.
3. In order to give effect to this Guarantee, the Employer shall be entitled to act as if the
Bank were the principal debtor and any change in the constitution of the
Contractor and/or the Bank, whether by their absorption with any other body or
corporation or otherwise, shall not in any way or manner affect the liability or
obligation of the Bank under this Guarantee.
4. It shall not be necessary, and the Bank hereby waives any necessity, for the Employer
to proceed against the Contractor before presenting to the Bank its demand under this
Guarantee.
5. The Employer shall have the liberty, without affecting in any manner the liability of
the Bank under this Guarantee, to vary at any time, the terms and conditions of the
Retention Money and any of the rights and powers exercisable by the Employer
against the Contractor, and either to enforce or forbear from enforcing any of the
terms and conditions contained in the Agreement and/or the securities available to the
Employer , and the Bank shall not be released from its liability and obligation under
these presents by any exercise by the Employer of the liberty with reference to the
matters aforesaid or by reason of time being given to the Contractor or any other
forbearance, indulgence, act or omission on the part of the Employer or of any other
matter or thing whatsoever which under any law relating to sureties and guarantors
would but for this provision have the effect of releasing the Bank from its liability and
obligation under this Guarantee and the Bank hereby waives all of its rights under any
such law.
6. This Guarantee is in addition to and not in substitution of any other guarantee or
security now or which may hereafter be held by the Employer in respect of or relating
to the Retention Money.
7. Notwithstanding anything contained hereinbefore, the liability of the Bank under
this Guarantee is restricted to the Guarantee amount and this Guarantee will remain in
force for the period specified in paragraph 8 below and unless a demand or claim in
writing is made by the Employer on the Bank under this Guarantee all rights of
the Employer under this Guarantee shall be forfeited and the Bank shall be relieved
from its liabilities hereunder.
8. The guarantee shall cease to be in force and effect 90 (ninety) days after the end of
then Defects Liability Period specified in Clauses 17.1 of the Agreement.
9. The Bank undertakes not to revoke this Guarantee during its currency, except with
the previous express consent of the Employer in writing, and declares and warrants
that it has the power to issue this Guarantee and the undersigned has full powers to do
so on behalf of the Bank.
10. Any notice by way of request, demand or otherwise hereunder may be sent by
post addressed to the Bank at its above referred branch, which shall be deemed to
have been duly authorized to receive such notice and to effect payment thereof
forthwith, and if sent by post it shall be deemed to have been given at the time when it
ought to have been delivered in due course of post and in proving such notice, when
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 277
EPC Agreement
given by post, it shall be sufficient to prove that the envelope containing the notice was
posted and a certificate signed by an officer of the Employer that the envelope
was so posted shall be conclusive.
11. This Guarantee shall come into force with immediate effect and shall remain in force
and effect up to the end **** month in the year ***** or until it is released earlier by
the Employer pursuant to the provisions of the Agreement.
Signed and sealed this .. day of . 20.. at
SIGNED, SEALED AND DELIVERED
For and on behalf of the Bank
by: (Signature)
(Name) (Designation) (Code
Number) (Address) NOTES:
(i)
The Ba nk guarantee should contain the name, designation and code number of the
officer(s) signing the guarantee.
(ii)
The address, telephone number and other details of the head office of the Bank as
well as of issuing branch should be mentioned on the covering letter of issuing
branch.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 278
EPC Agreement
Annex-III
(Schedule-G)
(See Clause 19.2)
Form for Guarantee for Advance Payment
..,
.Employer ,
Mumbai
WHEREAS:
i.
[name and address of contractor] (hereinafter called the Contractor) has executed an
Agreement (hereinafter called the Agreement) with the [name and address of the
Employer ], (hereinafter called the Employer ) for the Design and Build the
Infrastructure Works for Roads, Drains, Culverts, Minor Bridges, Water Supply,
Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package - I) on Engineering, Procurement and
Construction (the EPC) basis, subject to and in accordance with the provisions of
the Agreement.
ii.
in accordance with the Clause 19.2 of the Agreement the Employer shall make to
the Contractor an interest bearing Advance Payment (hereinafter called
Advance Payment) equal to 10% (ten per cent) of the contract price for
mobilization expenses and acquisition of equipment; and that the Advance Payment
shall be made in three installments subject to the Contractor furnishing an irrevocable
and unconditional guarantee by a scheduled Bank for an amount equal to the 110%
amount of each installment to remain effective till the complete and full repayment of
the installment of the Advance Payment as security for compliance with its
obligations in accordance with the Agreement; and the amount of (first/second/third)
installment of the Advance Payment is Rs. **** cr. (Rupees ***** crore) (the
Guarantee Amount).
iii.
and irrevocably,
1. The Bank hereby unconditionally and irrevocably guarantees the due and
faithful repayment on time of the aforesaid installment of the Advance Payment under
and in accordance with the Agreement, and agrees and undertakes to pay to the
Employer , upon its mere first written demand, and without any demur, reservation,
recourse, contest or protest, and without any reference to the Contractor, such sum or
sums up to an aggregate sum of the guarantee amount as the Employer shall claim,
without the Employer being required to prove or to show grounds or reasons for its
demand and/or for the sum specified therein.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 279
EPC Agreement
2. A letter from the Employer , under the hand of an officer not below the rank of
[of Employer ], that the Contractor has committed default in the
due and faithful performance of all or any of its obligations for the repayment of the
installment of the Advance Payment under and in accordance with the Agreement shall
be conclusive, final and binding on the Bank. The Bank further agrees that the
Employer shall be the sole judge as to whether the Contractor is in default in due and
faithful performance of its obligations during and under the Agreement and its decision
that the Contractor is in default shall be final, and binding on the Bank, notwithstanding
any difference between the Employer and the Contractor, or any Dispute between
them pending before any court, tribunal, arbitrators or any other authority or body, or
by the discharge of the Contractor for any reason whatsoever.
3. In order to give effect to this Guarantee, the Employer shall be entitled to act as if the
Bank were the principal debtor and any change in the constitution of the
Contractor and/or the Bank, whether by their absorption with any other body or
corporation or otherwise, shall not in any way or manner affect the liability or
obligation of the Bank under this Guarantee.
4. It shall not be necessary, and the Bank hereby waives any necessity, for the Employer
to proceed against the Contractor before presenting to the Bank its demand under this
Guarantee.
5. The Employer shall have the liberty, without affecting in any manner the liability of
the Bank under this Guarantee, to vary at any time, the terms and conditions of the
Advance Payment or to extend the time or period of its repayment or to postpone for
any time, and from time to time, any of the rights and powers exercisable by the
Employer against the Contractor, and either to enforce or forbear from enforcing any
of the terms and conditions contained in the Agreement and/or the securities available
to the Employer , and the Bank shall not be released from its liability and obligation
under these presents by any exercise by the Employer of the liberty with reference to
the matters aforesaid or by reason of time being given to the Contractor or any other
forbearance, indulgence, act or omission on the part of the Employer or of any other
matter or thing whatsoever which under any law relating to sureties and guarantors
would but for this provision have the effect of releasing the Bank from its liability and
obligation under this Guarantee and the Bank hereby waives all of its rights under any
such law.
6. This Guarantee is in addition to and not in substitution of any other guarantee or
security now or which may hereafter be held by the Employer in respect of or relating
to the Advance Payment.
7. Notwithstanding anything contained hereinbefore, the liability of the Bank under
this Guarantee is restricted to the Guarantee amount and this Guarantee will remain in
force for the period specified in paragraph 8 below and unless a demand or claim in
writing is made by the Employer on the Bank under this Guarantee all rights of
the Employer under this Guarantee shall be forfeited and the Bank shall be relieved
from its liabilities hereunder.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 280
EPC Agreement
8. The guarantee shall cease to be in force and effect 90 (ninety) days after the end of
the one year from the date of payment of the installment of the Advance Payment, as set
forth in Clause 19.2 of the Agreement.
9. The Bank undertakes not to revoke this Guarantee during its currency, except with
the previous express consent of the Employer in writing, and declares and warrants
that it has the power to issue this Guarantee and the undersigned has full powers to do
so on behalf of the Bank.
10. Any notice by way of request, demand or otherwise hereunder may be sent by
post addressed to the Bank at its above referred branch, which shall be deemed to have
been duly authorized to receive such notice and to effect payment thereof forthwith, and
if sent by post it shall be deemed to have been given at the time when it ought to have
been delivered in due course of post and in proving such notice, when given by post, it
shall be sufficient to prove that the envelope containing the notice was posted and a
certificate signed by an officer of the Employer that the envelope was so posted
shall be conclusive.
11. This Guarantee shall come into force with immediate effect and shall remain in force
and effect for up to the end **** month in the year ***** or until it is released earlier
by the Employer pursuant to the provisions of the Agreement.
Signed and sealed this .. day of . 20.. at
SIGNED, SEALED AND DELIVERED
For and on behalf of the Bank
by: (Signature)
(Name) (Designation)
(Code Number)
(Address) NOTES:
(i) The B a n k guarantee should contain the name, designation and code number of the
officer(s) signing the guarantee.
(ii) The address, telephone number and other details of the head office of the Bank as well
as of issuing branch should be mentioned on the covering letter of issuing branch.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 281
EPC Agreement
2.0
3.0
4.0 Procedure for estimating the value of Storm water drain Works including out fall
Works done.............................................................................................................287
5.0
Procedure for estimating the value of Potable water supply network & elevated
service reservoirs Works done.................................................................................287
6.0
Procedure for estimating the value of Recycled water supply network & elevated
service
reservoirs
Works
done..................................................................................288
7.0
Procedure for estimating the value of Residential sewage collection network Works
done....288
8.0 Procedure for estimating the value of Industrial effluent collection network Works
done........................................................................................................................289
9.0
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 282
EPC Agreement
WEIGHTAGES
(See Clauses 10.1.4 and 19.3)
1.0
2.0
S No
Item
Road Works
Potable
Water
Recycled
water
% of
weightage
in the
contract
price
34%
4%
3%
% of
weightage
24
24
33
7
12
40
10
45
51
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 283
EPC Agreement
S No
Item
Fire fighting
Storm Water
Drainage
Industrial
Sewerage
% of
weightage
in the
contract
price
2%
13%
2%
% of
weightage
31
71
23
4
3
33
23
27
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
52
Page 284
EPC Agreement
S No
Item
% of
weightage
in the
contract
price
Residential
Sewerage
Power
Submission
and approval
of Data,
Drawings
and analysis
of Surveys &
Investigation
s and
Designs,
Drawings
and Reports
1%
40%
1%
% of
weightage
38
10
1
1
37
25
38
27
(b ) Cables
20
(c) Lighting
15
35
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
10
5
Page 285
EPC Agreement
S No
Item
% of
weightage
in the
contract
price
% of
weightage
5
5
10
10
15
10
5
10
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 286
EPC Agreement
3.0
3.1
% of
weightage
Payment procedure
Road Works
24
24
33
12
@ For example, if the total length of bituminous work to be done is L km, the cost per km
of bituminous work shall be determined as follows;
Cost per km of Bituminous work = P x weightage for road work x weightage for
bituminous work x (1/L)
=P x 34% x 33% x (1/L)
=
Where,
P= Contract Price
L = Total length of Bituminous work in km
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 287
EPC Agreement
4.0 Procedure for estimating the value of Storm water drain Works including out fall
Works done shall be as stated in Table: 3
Table 3: Storm Water Drain Works including out fall structures
Stage for Payment
% of
weightage
Payment procedure
5.0
33
52
Procedure for estimating the value of Potable water supply network & elevated
service reservoirs Works done shall be as stated in Table: 4
Table 4: Potable Water Supply Network & Elevated Service Reservoirs
Stage for Payment
% of
weightage
40
10
45
Payment procedure
Water supply
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 288
EPC Agreement
6.0
Procedure for estimating the value of Recycled water supply network & elevated
service reservoirs Works done shall be as stated in Table: 5
Table 5: Recycled Water Supply Network & Elevated Service Reservoirs
Stage for Payment
% of
weightage
Payment procedure
Recycled Water
51
31
7.0
% of
weightage
Payment procedure
37
25
38
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 289
EPC Agreement
8.0
% of
weightage
23
27
38
10
1
Payment procedure
Procedure for estimating the value of Power Works done shall be as stated in
Table: 8
Table 8: Power
Stage for Payment
% of
weightage
27
(b ) Cables
20
(c) Lighting
15
35
Payment procedure
Power
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 290
EPC Agreement
10.0
Procedure for estimating the value of Power Works done shall be as stated in
Table: 9
Table 9: Fire Fighting
% of
weightage
Fire fighting
a) Laying of the pipelines (DI K9) with specials
including earthwork for cutting, filling, disposal
of the surplus earth and also provision for
moorum bedding
71
23
11.0
Payment procedure
Table 10: Data, Drawings and analysis of surveys & investigations and Designs,
Drawings and Reports
Stage of Payment
Payment Procedure
Percentage
weightage
% Payment on
Complete
Submission
Submission and approval of Data,
Drawings and analysis of Surveys &
Investigations
and Designs,
and reports.
Data,
DrawingsDrawings
and analysis
of Surveys &
10%
Investigations
Designs, Drawings and reports of Potable
water supply network including Rising
Mains and property connections
Designs, Drawings and reports of Recycled
water supply network including Rising
Mains and property connections
Designs, Drawings and reports of Elevated
Service Reservoirs for recycled and potable
water supply
Designs, Drawings and reports of Domestic
sewage collection network including
pumping
mains
and
property
connections
% Payment on
Approval by
Engineer
6%
4%
5%
3%
2%
5%
3%
2%
5%
3%
2%
5%
3%
2%
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 291
EPC Agreement
5%
3%
2%
10%
6%
4%
10%
6%
4%
15%
9%
6%
10%
6%
4%
5%
3%
2%
As built Drawings
10%
6%
4%
5%
3%
2%
12.0
12.1
12.2
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 292
EPC Agreement
Schedule I - Drawings
(See Clauses 10.2.4)
Contents
1.0 - Drawings......................................................................................................................293
2.0 - Additional Drawings....................................................................................................293
Appendix I-I - List of Drawings............................................................................................294
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 293
1.0
EPC Agreement
Drawings
In compliance of the obligations set forth in Clause 10.2 of this Agreement, the
Contractor shall furnish to the Employers Engineer, free of cost, all Drawings listed in
Appendix I-I of this Schedule-I.
2.0
Additional Drawings
If the Employers Engineer determines that for discharging its duties and functions under
this Agreement, it requires any Drawings other than those listed in Appendix I- I, it may
by notice require the Contractor to prepare and furnish such Drawings forthwith.
Upon receiving a requisition to this effect, the Contractor shall promptly prepare and
furnish such Drawings to the Employers Engineer, as if such Drawings formed part of
Appendix I-I of this Schedule-I.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 294
EPC Agreement
Appendix I-I
(Schedule - I)
LIST OF DRAWINGS
All the Drawings that the Contractor is required to furnish under Clause 10.2 for the
Construction of Roads, Water Supply, Recycled Water, Firefighting Sewerage, Storm Water
Drains & Power systems are given in table below;
Table 1: List of Drawings
S.no
1
Description
Road Works
i
Drawings of horizontal alignment, vertical profile and cross sections
ii
Drawings for all Bridges
ii
Drawings of cross drainage Works
iii
Drawings of major junctions & minor junctions
Drawings of road furniture items including traffic signage, markings, safety barriers,
iv
etc.
i
ii
iii
iv
v
Network Drawings
Layout of water supply network with valves
Layout plan for recycled water
Schematic plan for Shendra Phase-I water supply scheme
Site plan of water supply Shendra Phase-I
Layout plan of fire fighting network
i
ii
iii
iv
v
vi
vii
viii
Standard Drawings
Masonry chambers
MDPE house service connection
Thrust blocks
Trench Excavation details
Underground reservoir - potable
Underground reservoir -recycled
Over head tank- potable
Over head tank- Recycled
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 295
vi
vii
viii
6
EPC Agreement
Power network
i
Substation location and cable routing Drawing
ii
Substation wise plan identification
iii
Cable trench sections
iv
Sections showing cable trench
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 296
EPC Agreement
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 297
1.0
EPC Agreement
2.0
Project Milestone-I
2.1
Project Milestone-I shall occur on the date falling on the 180th (One hundred and
Eightieth) day from the Appointed Date (the Project Milestone-I).
2.2
Prior to the occurrence of Project Milestone-I, the Contractor shall complete all the
designs for the entire Project work and shall have commenced Construction of the Project
components (roads and utilities / services) and submitted to the Employer duly and
validly prepared Stage Payment Statements for an amount not less than 10% (ten per
cent) of the Contract Price.
3.0
Project Milestone-II
3.1
Project Milestone-II shall occur on the date falling on the 36 5 t h . (Three hundred and
sixty fifth) day from the Appointed Date (the Project Milestone-II).
3.2
Prior to the occurrence of Project Milestone-II, the Contractor shall have continued
with Construction of the Project components (roads and utilities/services) and submitted
to the Employer duly and validly prepared Stage Payment Statements for an amount not
less than 20% (Twenty per cent) of the Contract Price.
4.0
Project Milestone-III
4.1
Project Milestone-III shall occur on the date falling on the 545th (Five hundred and
forty fifth) day from the Appointed Date (the Project Milestone-III).
4.2
Prior to the occurrence of Project Milestone-III, the Contractor shall have continued
with Construction of the Project components (roads and utilities/services) and submitted
to the Employer duly and validly prepared Stage Payment Statements for an amount not
less than 50% (Fifty per cent) of the Contract Price.
5.0
Project Milestone-IV
5.1
Project Milestone-IV shall occur on the date falling on the 730t h ( Seven hundred
and thirtieth) day from the Appointed Date (the Project Milestone-IV).
5.2
Prior to the occurrence of Project Milestone-IV, the Contractor shall have continued
with Construction of the Project components (roads and utilities/services) and submitted
to the Employer duly and validly prepared Stage Payment Statements for an amount not
less than 75% (Seventy Five per cent) of the Contract Price.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 298
EPC Agreement
6.0
6.1
The Scheduled Completion Date shall occur on the 930t h (Nine hundred and
thirtieth) day from the Appointed Date.
6.2
On or before the Scheduled Completion Date, the Contractor shall have completed
Construction in accordance with this Agreement.
7.0
Extension of Time
7.1
Upon extension of any or all of the aforesaid Project Milestones or the Scheduled
Completion Date, as the case may be, under and in accordance with the provisions of
this Agreement, the Project Completion Schedule shall be deemed to have been
amended accordingly.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 299
EPC Agreement
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 300
EPC Agreement
1.0
1.1
The Contractor shall, no later than 30 (thirty) days prior to the likely completion of
Construction, notify the Employers Engineer and the Employer of its intent to subject
the Project components (roads and utilities / services) to Tests, and no later than 10 (ten)
days prior to the actual date of Tests, furnish to the Employers Engineer and the
Employer detailed inventory and particulars of all Works and equipment forming part of
Works.
1.2
The Contractor shall notify the Employers Engineer of its readiness to subject the
Project components (roads and utilities / services) to Tests at any time after 10 (ten) days
from the date of such notice, and upon receipt of such notice, the Employers Engineer
shall, in consultation with the Contractor, determine the date and time for each Test and
notify the same to the Employer who may designate its representative to witness the
Tests. The Employers Engineer shall thereupon conduct the Tests itself or cause any of
the Tests to be conducted in accordance with Article 12 and this Schedule-K.
2.0
Tests
2.1
Visual and physical test: The Employers Engineer shall conduct a visual and physical
check of Construction to determine that all Works and equipment forming part thereof
conform to the provisions of this Agreement.
2.2
Riding quality test: Riding quality of each lane of the carriageway shall be checked
with the help of a calibrated bump integrator and the maximum permissible roughness for
purposes of this Test shall be 1800 (Eighteen Hundred) mm for each kilometer.
2.3
Tests for bridges: All major and minor bridges shall be subjected to the rebound
hammer and ultrasonic pulse velocity Tests, to be conducted in accordance with the
procedure described in Special Report No. 17: 1996 of the IRC Highway Research
Board on Non-destructive Testing Techniques, at two spots in every span, to be
chosen at random by the Employers Engineer. Bridges with a span of 15 (fifteen) meters
or more shall also be subjected to load testing.
2.4
Water Tightness test: All hydraulic structures, such as sewer lines network, industrial
network, joints, manholes etc. or any other liquid containers shall have to be tested for
water tightness. The water tightness test shall be conducted as specified in IS: 41271967.
2.5
Water Tightness test for Manhole: The entire height of the manhole shall be tested for
water tightness as per CPHEEO Manual, by closing both the incoming and outgoing ends
of the sewer and filling the manhole with water and the drop in water level not more than
50 mm per 24 hours shall be permitted.
2.6
Hydraulic Test: Fill the pipeline with water after it has been laid; bleed off any
trapped air. Subject the lowest element in the system to a test pressure that is 1.5 times the
design pressure, and check for any leakage. When, in the opinion of the engineer, local
conditions require that the trenches be backfilled immediately after the pipe has been
laid, apply the pressure test after backfilling has been completed but not sooner than a
time which will allow sufficient curing of any concrete that may have been used.
Typical minimum concrete curing times are 36 hours for early strengths and 7 days for
normal strengths.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 301
EPC Agreement
2.7
Water Tightness test for ESR: The contractor shall be fully responsible for the water
tightness of the tank, the tank shall be taken as water tight of the depression in water
level after filling the tank of full supply level not more than 12.20 mm in 24 Hrs. and no
leakages are observed.
2.8
Other Tests: The Employers Engineer may require the Contractor to carry out or
cause to be carried additional Tests, in accordance with Good Industry Practice, for
determining the compliance of the Project components (roads and utilities / services)
with Standards and Specifications.
2.9
Environmental audit: The Employers Engineer shall carry out a check to determine
conformity of the Project components (roads and utilities / services) with the
environmental requirements set forth in Applicable Laws and Applicable Permits.
2.10
Safety Audit: The Employers Engineer shall carry out, or cause to be carried out, a
safety audit to determine conformity of the Project components (roads and
utilities/services) with the safety requirements and Good Industry Practice.
2.11
Visual and physical test for Street lighting covering pole, luminaire, power supply,
grounding, communication between luminaire to control panel and central control
system.
2.12
2.13
All of the electrical equipment covered by this report shall be tested in accordance
with all relevant design and installation standards and codes of practices. Routine
and Type test reports shall be required as minimum. The contractor shall notify the
engineer, in writing, when each Section of work is complete and whole of the work
is completed. Each Section of the work and whole of the work shall be tested in
accordance with all relevant design and installation standards and codes of
practices.
3.0
3.1
All Tests set forth in this Schedule-K shall be conducted by the Employers Engineer or
such other agency or person as it may specify in consultation with the Employer.
4.0
Completion Certificate
4.1
Upon successful completion of Tests, the Employers Engineer shall issue the
Completion Certificate in accordance with the provisions of Article 12.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 302
EPC Agreement
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 303
EPC Agreement
Provisional Certificate
(See Clause 12.2)
1. I, .. (Name of the Employers Engineer), acting as Employers Engineer,
under and in accordance with the Agreement dated .. (the Agreement), for
Design and build the infrastructure Works for roads, Drains, Culverts, water supply, sewerage,
power systems, for phase-I in Shendra-Bidkin industrial area, Aurangabad, Maharashtra
through Engineering, Procurement & Construction
(EPC)
Basis
Contract
through. (Name of Contractor), hereby certify that the Tests in accordance
with Article 12 of the Agreement have been undertaken to determine compliance of the
Project.............................. with the provisions of the Agreement.
2. Construction Works that are incomplete on account of Time Extension have been
specified in the Punch List appended hereto, and the Contractor has agreed and accepted that
it shall complete all such Works in the time and manner set forth in the Agreement. In
addition, certain minor Works are incomplete and these are not likely to cause Material
inconvenience to the users of the Project .............................. or other their safety. The
contractor has agreed and accepted that as a condition of this Provisional Certificate, it shall
complete such minor Works within 30 (thirty) days hereof. These minor Works have also
been specified in the aforesaid Punch List.
3. In view of the foregoing, I am satisfied that that Project ............................................. can be
safely and reliably placed in service of the users thereof, and in terms of the
Agreement, the Project .............................. is hereby provisionally declared fit for entry into
operation on this the day of .20 ..
ACCEPTED, SIGNED, SEALED
AND DELIVERED
CONTRACTOR by
Employers Engineer by:
(Signature)
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
(Signature)
Page 304
EPC Agreement
Completion Certificate
(See Clause 12.4)
1. I, .. (Name o f the Employers Engineer), acting as Employers Engineer, under
and in accordance with the Agreement dated .. (the Agreement), for Design
and Build the Infrastructure Works for roads, Drains, Culverts, water supply, sewerage, power
systems, for Phase-I in Shendra-Bidkin Industrial area, Aurangabad, Maharashtra through
Engineering, Procurement & Construction (EPC) Basis through . (Name
of Contractor), hereby certify that the Tests in accordance with Article 12 of the Agreement
have been successfully undertaken to determine compliance of the Project
............................................. with the provisions of the Agreement, and I am satisfied that the
Project ............................................. can be safely and reliably placed in service of the Users
thereof.
2. It is certified that, in terms of the aforesaid Agreement, all Works forming part of Project
Works have been completed, and the Project Works is hereby declared fit for entry into
operation on this the ..day of ..20 ..
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 305
EPC Agreement
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 306
EPC Agreement
Monthly lump sum payments for Maintenance shall be reduced in the case of noncompliance with the Maintenance Requirements set forth in Schedule-E.
1.2
1.3
The Employers Engineer shall calculate the amount of payment reduction on the
basis of weightage in percentage assigned to non-conforming items as given in Paragraph
2.
2.0
2.1
Item/Defect/Deficiency
Percentage
71%
(a)
(i)
20%
(ii)
5%
(iii)
10%
(iv)
10%
(b)
10%
(i)
(ii)
(iii)
(c)
45%
5%
3%
2%
45%
(ii)
(iii)
10%
(iv)
10%
(i)
(v)
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
10%
5%
10%
Page 307
EPC Agreement
Table: 2
Percentage reductions for Storm Water Drain Works, Potable water supply network
& elevated service reservoirs Works, Recycled water supply network & elevated
service reservoirs Works, Domestic sewage collection network Works and
Industrial effluent collection network Works.
S. No.
Percentage
20%
(i)
50%
(ii)
50%
(i)
(i)
2
(i)
(ii)
3
(i)
(ii)
2.2
Item
2%
75%
25%
3%
75%
25%
2%
100%
2%
100%
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 308
EPC Agreement
L=
R=
The total amount of reduction shall be arrived at by summation of reductions for such
items/Defects/deficiency or noncompliance.
For any Defect in a part of one kilometer, the non-conforming length shall be taken as
one kilometer.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 309
EPC Agreement
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 310
1.
EPC Agreement
1.1
The provisions of the Model Request for Proposal for Selection of Technical
Consultants, issued by the Ministry of Finance in May 2009, or any substitute thereof
shall apply for selection of an experienced firm to discharge the functions and duties of
an Employers Engineer.
1.2
2.
Terms of Reference
The Terms of Reference for the Employers Engineer (the TOR) shall substantially
conform with Annex 1 to this Schedule N.
3.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 311
EPC Agreement
Annex I
(Schedule - N)
Terms of Reference for Employers Engineer
1.0 Scope
1.1
These Terms of Reference (the TOR) for the Employers Engineer are being specified
pursuant to the EPC Agreement dated........... (the Agreement), which has been entered
into between the .Name of Employer (the Employer ) and .......... (the
Contractor) for Design and Build the Infrastructure Works for Roads, Drains, Culverts,
Water Supply, Sewerage, Power Systems for Phase-I in Shendra-Bidkin industrial area,
Aurangabad, Maharashtra on Engineering, Procurement & Construction (EPC) Basis,
and a copy of which is annexed hereto and marked as Annex-A to form part of this
TOR.
1.2
The TOR shall apply to design, Construction and Maintenance of the Project Roads
and Services
The words and expressions beginning with or in capital letters and not defined herein but
defined in the Agreement shall have, unless repugnant to the context, the meaning
respectively assigned to them in the Agreement.
2.2
References to Articles, Clauses and Schedules in this TOR shall, except where the context
otherwise requires, be deemed to be references to the Articles, Clauses and Schedules of
the Agreement, and references to Paragraphs shall be deemed to be references to
Paragraphs of this TOR.
2.3
The rules of interpretation stated in Clauses 1.2, 1.3 and 1.4 of the Agreement shall
apply, mutatis mutandis, to this TOR.
3.0 General
3.1
The Employers Engineer shall discharge its duties in a fair, impartial and
efficient manner, consistent with the highest standards of professional integrity and
Good Industry Practice.
3.2
The Employers Engineer shall perform the duties and exercise the authority in
accordance with the provisions of this Agreement, but subject to obtaining prior
written approval of the Employer /PMNC before determining:
(a)
(b)
(c)
(d)
3.3
The Employers Engineer shall submit regular periodic reports, at least once every
month, to the Employer /PMNC in respect of its duties and functions under this
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 312
EPC Agreement
Agreement. Such reports shall be submitted by the Employers Engineer within 10 (ten)
days of the beginning of every month.
3.4
The Employers Engineer shall inform the Contractor of any delegation of its duties
and responsibilities to its suitably qualified and experienced personnel provided,
however, that it shall not delegate the authority to refer any matter for the Employers
prior approval in accordance with the provisions of Clause 18.2.
3.5
The Employers Engineer shall aid and advise the Employer on any proposal for
Change of Scope under Article 13.
3.6
In the event of any disAgreement between the Parties regarding the meaning, scope
and nature of Good Industry Practice, as set forth in any provision of the Agreement, the
Employers Engineer shall specify such meaning, scope and nature by issuing a
reasoned written statement relying on good industry practice and authentic
literature.
4 .0 Construction Period
4.1
During the Construction Period, the Employers Engineer shall review the Reports,
Designs and Drawings furnished by the Contractor along with supporting data, including
the geo-technical and hydrological investigations, characteristics of Materials from
borrow areas and quarry sites, topographical surveys, and the recommendations of the
Safety Consultant in accordance with the provisions of Clause 10.1.6. The Employers
Engineer shall complete such review and send its observations to the Employer / PMNC
and the Contractor within 15 (fifteen) days of receipt of such Reports, Designs and
Drawings; provided, however that in case of a Structure, the aforesaid period of 15
(fifteen) days may be extended up to 30 (thirty) days. In particular, such comments shall
specify the conformity or otherwise of such Drawings with the Scope of the Project and
Specifications and Standards.
4.2
The Employers Engineer shall review any revised Reports, Designs and Drawings sent
to it by the Contractor and furnish its comments within 10 (ten) days of receiving such
Reports, Designs and Drawings.
4.3
The Employers Engineer shall review the (a) Quality Assurance Plan (b) Health, Safety
and Environmental Management Plan submitted by the Contractor and shall convey its
comments to the Contractor within a period of 21 (twenty-one) days stating the
modifications, if any, required thereto. The Employers Engineer shall ensure the
Contractors Project Management requirements, BIM and CAD requirements
regularly on a monthly basis to the Employer/ PMNC.
4.4
The Employers Engineer shall complete the review of the methodology proposed to be
adopted by the Contractor for executing the Works, and convey its comments to the
Contractor within a period of 10 (ten) days from the date of receipt of the proposed
methodology from the Contractor.
4.5
Deleted.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 313
EPC Agreement
4.6
The Employers Engineer shall review the monthly progress report furnished by the
Contractor and send its comments thereon to the Employer / PMNC and the Contractor
within 7 (seven) days of receipt of such report.
4.7
The Employers Engineer shall inspect the Construction Works and the Project Roads
and shall submit a monthly Inspection Report bringing out the results of inspections and
the remedial action taken by the Contractor in respect of Defects or deficiencies. In
particular, the Employers Engineer shall include in its Inspection Report, the compliance
of the recommendations made by the Safety Consultant.
4.8
4.9
For determining that the Works conform to Specifications and Standards, the Employers
Engineer shall require the Contractor to carry out, or cause to be carried out, Tests at such
time and frequency and in such manner as specified in the Agreement and in accordance with
Good Industry Practice for quality assurance. For purposes of this Paragraph 4.9, the Tests
specified in the relevant Codes or any modification/substitution thereof and standards for
shall be deemed to be Tests conforming to Good Industry Practice for quality assurance.
4.10
The Employers Engineer shall test check at least 20 (twenty) percent of the quantity
or number of Tests prescribed for each category or type of test for quality control by the
Contractor.
4.11
The timing of Tests referred to in Paragraph 4.9, and the criteria for acceptance/
rejection of their results shall be determined by the Employers Engineer in accordance
with the Quality Control Manuals and/or the relevant Codes and Standards. The Tests
shall be undertaken on a random sample basis and shall be in addition to, and
independent of, the Tests that may be carried out by the Contractor for its own quality
assurance in accordance with Good Industry Practice.
4.12
In the event that results of any Tests conducted under Clause 11.10 establish any
Defects or deficiencies in the Works, the Employers Engineer shall require the
Contractor to carry out remedial measures.
4.13
The Employers Engineer may instruct the Contractor to execute any work which is
urgently required for the safety of the Project Works, whether because of an accident,
unforeseeable event or otherwise; provided that incase of any work required on account
of a Force Majeure Event, the provisions of Clause 21.6 shall apply.
4.14
In the event that the Contractor fails to achieve any of the Project Milestones, the
Employers Engineer shall undertake a review of the progress of Construction and
identify potential delays, if any. If the Employers Engineer shall determine that
completion of the Project Works is not feasible within the time specified in the
Agreement, it shall require the Contractor to indicate within 15 (fifteen) days the steps
proposed to be taken to expedite progress, and the period within which the Project
Completion Date shall be achieved. Upon receipt of a report from the Contractor, the
Employers Engineer shall review the same and send its comments to the Employer /
PMNC and the Contractor forthwith.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 314
EPC Agreement
4.15
The Employers Engineer shall obtain from the Contractor two copies of all the
Contractors quality control records and documents before the Completion Certificate is
issued pursuant to Clause 12.4.
4.16
4.17
In the event that the Contractor carries out any remedial measures to secure the safety of
suspended Works and Users, and requires the Employers Engineer to inspect such
Works, the Employers Engineer shall inspect the suspended Works within 3 (three) days
of receiving such notice, and make a report to the Employer / PMNC forthwith,
recommending whether or not such Suspension may be revoked by the Employer .
4.18
The Employers Engineer shall carry out, or cause to be carried out, all the Tests
specified in Schedule-K and issue a Completion Certificate or Provisional Certificate, as
the case may be. For carrying out its functions under this Paragraph 4.18 and all matters
incidental thereto, the Employers Engineer shall act under and in accordance with the
provisions of Article 12 and Schedule-K.
The Employers Engineer shall aid and advise the Contractor in the preparation of its
monthly Maintenance Programme and for this purpose carry out a joint monthly
inspection with the Contractor.
5.2
The Employers Engineer shall undertake regular inspections, at least once every month,
to evaluate compliance with the Maintenance Requirements and submit a
Maintenance Inspection Report to the Employer / PMNC and the Contractor.
5.3
The Employers Engineer shall specify the Tests, if any, that the Contractor shall carry
out, or cause to be carried out, for the purpose of determining that the Project Works is
in conformity with the Maintenance Requirements. It shall monitor and review the
results of such Tests and the remedial measures, if any, taken by the Contractor in
this behalf.
5.4
5.5
The Employers Engineer shall examine the request of the Contractor for closure of any
lane(s)/utilities lines of the Project Roads and/or Services for undertaking
Maintenance/repair thereof, and shall grant permission with such modifications, as it may
deem necessary, within 5 (five) days of receiving a request from the Contractor. Upon
expiry of the permitted period of closure, the Employers Engineer shall monitor the
reopening of such lane(s), and in case of delay, determine the Damages payable by the
Contractor to the Employer under Clause 14.5.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 315
EPC Agreement
The Employers Engineer shall determine the costs, and/or their reasonableness, that are
required to be determined by it under the Agreement.
6.2
The Employers Engineer shall determine the period of Time Extension that is required
to be determined by it under the Agreement.
6.3
The Employers Engineer shall consult each Party in every case of determination in
accordance with the provisions of Clause 18.5.
7.0 Payments
7.1
The Employers Engineer shall withhold payments for the affected Works for which the
Contractor fails to revise and resubmit the Drawings to the Employers Engineer in
accordance with the provisions of Clause 10.2.4 (d).
7.2
within 10 (ten) days of receipt of the Stage Payment Statement from the Contractor
pursuant to Clause 19.4, determine the amount due to the Contractor and
recommend the release of 90 (ninety) percent of the amount so determined as part
payment, pending issue of the Interim Payment Certificate; and
(b)
within 15 (fifteen) days of the receipt of the Stage Payment Statement referred to
in Clause 19.4, deliver to the Employer / PMNC and the Contractor an Interim
Payment Certificate certifying the amount due and payable to the Contractor, after
adjustments in accordance with the provisions of Clause19.10.
7.3
The Employers Engineer shall, within 15 (fifteen) days of receipt of the Monthly
Maintenance Statement from the Contractor pursuant to Clause19.6, verify the
Contractors monthly statement and certify the amount to be paid to the Contractor in
accordance with the provisions of the Agreement.
7.4
The Employers Engineer shall certify final payment within 30 (thirty) days of the receipt
of the final payment statement of Maintenance in accordance with the provisions of
Clause 19.16.
9. 0 Miscellaneous
9.1
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 316
EPC Agreement
9.2
The Employers Engineer shall retain at least one copy each of all Drawings and
Documents received by it, including 'as-built' Drawings, and keep them in its safe
custody.
9.3
Within 90 (ninety) days of the Project Completion Date, the Employers Engineer shall
obtain a complete set of as-built Drawings, in 2 (two) hard copies and in micro film
form or in such other medium as may be acceptable to the Employer , reflecting the
Project ............................................. as actually designed, engineered and constructed,
including an as-built survey illustrating the layout of the Project Works and setback lines,
if any, of the buildings and Structures forming part of Project Facilities; and shall hand
them over to the Employer against receipt thereof.
9.4
The Employers Engineer, if called upon by the Employer /PMNC or the Contractor or
both, shall mediate and assist the Parties in arriving at an amicable settlement of any
Dispute between the Parties.
9.5
The Employers Engineer shall inform the Employer /PMNC and the Contractor of any
event of Contractor's Default within one week of its occurrence.
9.6
The Employers Engineer, if called upon by the Employer/ PMNC, shall attend the
meetings on Project reviews, discussions to be held at Employer/ PMNC office with
required reports and presentations.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 317
EPC Agreement
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 318
1.
EPC Agreement
(g)
(h)
The estimated amount for the Works executed in accordance with Clause 19.3.1
subsequent to the last claim;
Amounts reflecting adjustments in price for the aforesaid claim;
The estimated amount of each Change of Scope Order executed subsequent to
the last claim;
Amounts reflecting adjustment in price, if any, for (c) above in accordance with
the provisions of Clause 13.2.3 (a);
Total of (a), (b), (c) and (d) above;
Deductions:
(i) Any amount to be deducted in accordance with the provisions of the
Agreement except Taxes;
(ii) Any amount towards deduction of Taxes; and
(iii) Total of (i) and (ii) above.
Net claim: (e) (f) (iii);
The amounts received by the Contractor up to the last claim:
(i)
For the Works executed (excluding Change of Scope orders);
(ii)
(ii)
(iii)
2.
3.
Note: The Contractor shall submit its claims in a form acceptable to the Employer / PMNC.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 319
EPC Agreement
Schedule P - Insurance
(See Clause 20.1)
Contents
1 - Insurance during Construction Period...............................................................................320
2 - Insurance for Contractors Defects Liability.....................................................................320
3 - Insurance against injury to persons and damage to property..............................................320
4 - Insurance to be in joint names...........................................................................................320
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 320
EPC Agreement
1.
1.1.
The Contractor shall effect and maintain at its own cost, from the Appointed Date till
the date of issue of the last Completion Certificate, the following insurances for any
loss or damage occurring on account of Non Political Event of Force Majeure,
malicious act, accidental damage, explosion, fire and terrorism:
(a) insurance of Works, Plant and Materials and an additional sum of [15 (fifteen)]
per cent of such replacement cost to cover any additional costs of and incidental to
the rectification of loss or damage including professional fees and the cost of
demolishing and removing any part of the Works and of removing debris of
whatsoever nature; and
(b) Insurance for the Contractors equipment and Documents brought onto the Site by
the Contractor, for a sum sufficient to provide for their replacement at the Site.
1.2
The insurance under paragraph 1.1 (a) and (b) above shall cover the Employer and the
Contractor against all loss or damage from whatsoever cause arising under paragraph
1.1 other than risks which are not insurable at commercial terms.
2.
3.
3.1
The Contractor shall insure against each Partys liability for any loss, damage, death
or bodily injury which may occur to any physical property (except things insured
under Paragraph l and 2 of this Schedule or to any person (except persons insured
under Clause 20.9), which may arise out of the Contractors performance of this
Agreement and occurring before the issue of the Performance Certificate. This
insurance shall be for a limit per occurrence of not less than the amount stated below
with no limit on the number of occurrences.
The Insurance Cover shall be not less than: Rs. 20 Lakhs.
3.2
The insurance shall be extended to cover liability for all loss and damage to the
Employers property arising out of the Contractors performance of this Agreement
excluding:
(a) the Employers right to have the Construction Works executed on, over, under, in
or through any land, and to occupy this land for the Works; and
(b) Damage which is and unavoidable result of the Contractors obligations to execute
the Works.
4.
Page 321
EPC Agreement
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 322
EPC Agreement
1. OBJECTIVE
The Employer mandates the use of advanced computer based dynamic 3D-model
driven approach for the detailed planning, design, engineering, Construction and
operation of the DMIC nodes to allow simulation, visualization and engineering
analysis of all transportation, utility, building, civil Works and geospatial
infrastructures.
This includes an aggregate dynamic 3D Building Information Model (BIM) for the
city infrastructure systems with 3D building models. 3D civil infrastructures, 3D
models for rail, roads and underground and above ground utilities systems
participating.
3D infrastructure modelling tools shall be used to develop and produce Project
models and simulations (e.g. in case of natural calamity etc.) as required for
submittals.
The 3D infrastructure Information Models are to be used throughout the design,
Construction and operational life-cycle of the asset, including but not limited to for
system collision detections, Materials quantification, Construction sequencing and
carbon impact analysis.
3D infrastructure models use shall be maximized for Project reviews, decision
support, design analysis, and quality assurance during all phases of this program.
2. GENERAL
2.1. Purpose
2.1.1.
2.1.2.
2.1.3.
BIM Project Execution Plan Overview Information: Document the reason for creating
the Project Execution Plan.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 323
EPC Agreement
Project Information: The Plan should include critical Project information such as
Project numbers, Project location, Project description, and critical schedule dates for
future reference.
Key Project Contacts: As part of the reference information, A BIM Plan should include
contact information for key Project personnel.
Project Goals / BIM Objectives: This Section should document the strategic value and
specific uses for BIM on the Project as defined by the Project team in the initial step of
the planning procedure.
Organizational Roles and Staffing: One of the primary tasks is to define the
coordinator(s) of the BIM planning and execution process throughout the various stages
of the Project. This is particularly important when identifying the organization(s) who
will initiate the development of the BIM Plan, as well as the required staff to
successfully implement the plan.
BIM Process Design: This Section should clearly illustrate the execution process
through the use of process maps which are developed in the second step of the planning
procedure.
BIM Information Exchanges: The model elements and level of detail required to
implement each BIM use should be clearly defined in the information exchanges
requirements.
BIM and Facility Data Requirements: The owners requirements for BIM must be
documented and understood.
Collaboration Procedures: The team should develop their electronic and collaboration
activity procedures. This includes the definition of model management procedures (e.g.,
file structures, and file permissions) as well as typical meeting schedules and agendas.
Model Quality Control Procedures: A procedure for ensuring that the Project
participants meet the defined requirements should be developed and monitored
throughout the Project.
Technology Infrastructure Needs: The hardware, software and network infrastructure
required to execute the plan should be defined.
Model Structure: The team should discuss and document items such as model structure,
file naming structure, coordinate system, and modeling standards.
Project Deliverables: The team should document deliverables required by the owner.
Delivery Strategy / Contracts: This Section should define the delivery strategy which
will be used on the Project.
2.2. Scope
2.2.1. This BIM requirement document outlines the roles and responsibilities that are
necessary for a successful collaborative 3D Building Information Modelling (BIM)
approach.
2.2.2. The Project Management Information System (PMIS) and Common Data
Environment (CDE) will be mandated for the structure and the controlled sharing of
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 324
EPC Agreement
Existing Conditions
Modelling
Site Analysis
Design Authoring
Design Visualization
Interference Detection
Description/Comments
This will require the gathering of existing conditions information
from a range of sources, and validating the quality, accuracy and
reliability of that information for use on the Project. The physical
extent of what is needed to be modelled is to be determined, based
on location, physical/spatial/visual relationship and potential
impact on the Project. Areas or elements identified as posing risk
to the Project should be communicated clearly to inform future
risk mitigation efforts. In the absence of anything better, a default
standard will be used to achieve this.
The Site context should be understood thoroughly and
acknowledged within the design, accounting for factors that may
impact on siting/position of proposed Construction Works, such as
interfaces with existing structure or services, vistas, nearby land
use, hydraulic analysis, geo tech and topographic conditions, Site
access/egress issues, traffic flows, other infrastructure and so on.
A process in which software is used to develop a Building
Information Model based on criteria important to the
communication of the building's design. Two types of software
applications are core to the BIM-based design process: design
authoring tools and audit and analysis tools. Authoring tools are
used to create models while audit and analysis tools draw from or
enhance the richness of information in a model. Most audit and
analysis tools can be used for Design Reviews and Engineering
Analysis BIM Uses. Design authoring tools are required in the
first instance, and employ a powerful database of properties,
quantities, means and methods, costs and schedules.
The BIM can be used to generate rendered images, animated flythroughs and read-only versions of the model as requested by the
Client (with due notice) to support effective communication of the
design intent of the building. This is critical for stakeholder
engagement at a number of levels and Project stages.
General coordination will take place during early design via visual
inspection and design coordination Workshops. In particular,
coordination efforts will be applied to key pinch points, such as
cores,
risers,
plenum
spaces,
and
Plant
areas.
Aggregation/intensity of interferences detected will further inform
priority zones and element types. Late in the design process, and
particularly for preConstruction planning (during early
Construction stage), interference severity criteria will be defined
and interference rules configured that will support element-level
coordination. Good interference rule definitions will be key to
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 325
Design Review
Planning of
Construction
Scheduling and
Sequencing
Record Modelling
EPC Agreement
2.4. Definitions
2.4.1. The following terms are specific to the BIM requirements:
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 326
EPC Agreement
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 327
EPC Agreement
2.5. Responsibility
The Design and Build Contractor shall provide: A structured BIM approach to the
production of all required design and as built data and information for these Works under
the Contract, modelled on BS1192 Collaborative production of architectural, engineering
and Construction information; Code of practice;
Evidence that an all discipline integration, coordination and resolution process has taken
place in a collaborative 3D object orientated CDE, the outputs of which meet or better
the Employers Requirements;
A uniform and interoperable software/hardware platform across the entire Work
Package, in that any software used shall be consistent with the principles of the sharing
of multi-disciplinary object data in a CDE; That data shall include geometry and object
attributes; Compatibility between software and hardware platforms, including processes
for any interfaces with other Work Packages, as to ensure seamless integration at all
areas of overlap;
An Engineering Content Management System (ECM) which shall be configured to the
CDE workflows consistent with those set out in BS1192 and integrate with Employers
PMIS
Access to the (ECM) for the Engineer;
Structured data sets:
Detailed Design Stage 1
Detailed Design Stage 2
As-Built Drawings
The data sets shall include all plot composition files and associated references, all
models and associated references, all associated object and attribute data in mandated
format; All renditions of the above (PDFs) all as listed in the Master Document Index
(MDI);
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 328
EPC Agreement
A copy of the database from the ECM system and its files store;
All data in a structured (Level/Layer/Filename) format consistent with UK
AEC Uniclass.
All As-Built data in a structured (format) consistent with the Construction
Operations Building Information Exchange (COBie) format;
Suitability trained personnel with the appropriate capabilities to execute the specific
roles and responsibilities as outlined this BIM requirements, CAD and GIS manuals
contained herein;
Produces a general BIM implementation plan for their specific Works package, together
with the Contractors Design Coordination Manager, containing:
Statements on how the work packages shall be zoned, the level of BIM resolution
required in what zones, the number of specific discipline models that will be
included what level of detail each of these models shall achieve for each stage for the
design and build workflow.
Statements on the level of program integration and Construction sequencing with the
BIM model.
Statements on how the interface with other Works packages shall be achieved and
managed.
Ensures the Contractors BIM systems are providing the tools, process is centred
on the delivery of structured, coordinated and accurate information.
Ensure that all CAD. GIS. BIM data is compatible consistent and accurate and all BIM
processes are compliant with BS 1192.
Ensures the Contractors BIM processes serves the engineering and business requirement
of managing multi-discipline collaborative workflows, CAD QA, Clash resolution,
program linkage and Construction sequencing.
Coordinates the Project needs for IT solutions.
Coordinates the agreed Project BEPs and updates to the BEPS.
Ensures compliance with those standards and methods.
Shall be responsible for resolution of all interdisciplinary/other contract work packages
and interface resolution.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 329
EPC Agreement
Provides the focal point for all file and document management issues in the Project
Ensures that all information is compliant with standards and that each model or file has
been signed off fit for purpose.
Ensure that all CAD models and Drawings are delivered to the SIA use agreed IT
solutions, and are according to the agreed Project requirements.
Ensure that all object attribute data is structured and is compliant with the Project SMPs
Ref BS1192. This role should be responsible to the Contractors BIM Manager.
Completion of a table of names assigned to the roles described above and submit it to
the client as a reference document.
Ensure that all Drawing production shall be in line with CAD Guidelines given in
Annexure I of this Schedule Q.
Page 330
EPC Agreement
Function
Version*
Autodesk Civil 3D
2014
SELECT Series 3
SELECT series 2
Autodesk Revit
AECOsim Building Designer
Autodesk Navis Works
Manage
2014
SELECT Series 3
Bentley Navigator
SELECT Series 5
2014
SELECT Series 3
Water Network
Modeling
SELECT Series 3
Sewer Network
Modeling
SELECT Series 4
Storm Network
Modeling
SELECT Series 3
Structural Analysis
STAAD Pro
SELECT Series 5
Drafting
AutoCAD
2014
SELECT Series 3
ArcMap
10
x 3D Infrastructure
Modeling
x 3D Rail Infrastructure
Modeling
x 3D BIM modeling for
Buildings
x Project Review and
coordination
5D Schedule
Simulation
x 3D BIM and GIS
integration/
coordinati on
GIS
2014
Publishing
Publish read only single
i-model Plug-ins
file containing
- For Revit
graphical and non- For Adobe (Reader)
graphical attribute
information for multi
discipline BIM models
Latest
3D/2D Models,
Drawings and Maps
Latest
Operating
System
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Windows 7
(64 Bit
Recommend
ed)
Page 331
EPC Agreement
Annex I
(Schedule - Q)
CAD Guideline
OVERVIEW
1.1 Purpose
Programme Manager for New Cities (CH2MHill) has initiated to manage a program
that will assist in standardizing the use of CAD across all departments. The primary
goal is to create an environment for seamless integration/collaboration between all
disciplines & business lines of all consultants/contractors regarding the use of CAD
for production of any Drawing. The document will achieve this through setting out the
Guideline for Drawing data production. This will then enable Drawing data to be
incorporated into the Aurangabad Industrial Township limited (AITL) GIS.
1.2 Application
This CAD standard shall be applied to all disciplines in all offices and design houses
working in this Project. The scope of this document is to provide guidelines and
procedures for adopting AutoCAD layering standards in preparing design and as-built
Drawings for automated transference to DMICDC GIS. This Guideline will address
the following:
i. Layer assignments,
ii. Standard symbols
iii. Layers and layer names,
iv. Attributes to each feature,
v. Templates,
vi. Colour usage associated with line widths for all Highways and Utility
Drawings.
The Guideline are to be applied for all Drawings from Concept through to As Built
handover stage.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 332
EPC Agreement
Page 333
EPC Agreement
Collaborative Working
Figure: 2 Application of code of practice BS 1192:2007 on Common Data Environment
(CDE)
i.
Within WIP folder each discipline can create a folder structure to suit its
needs.
ii.
Common resource files such as title sheets, mapping, surveys, imagery and
other shared CAD data must be available to all disciplines in the Shared area.
iii.
Once data has been checked, verified and approved, it must be copied to the
Shared area and other disciplines notified.
iv.
When models are revised or updated; other disciplines referencing the model
will be affected, so effective communication between disciplines is essential.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 334
EPC Agreement
2.7
v.
When data files have been authorised and verified for issue, it is copied to the
Published area, to maintain a local copy within the design organizations
server.
vi.
The previous version of the data in the Published area shall be moved to the
Archive area as a historical record and to maintain an audit trail.
Hard Copies
The print containing the original stamped, checked and approved signatures becomes
the hard-copy 'master plot' for the Drawing. See Section 3.3.13.
2.7.1 Drawings
The Project Implementation Plan (PIP) will define the area where the hard-copies for
Projects are to be filed.
The electronic version of the master plot of the Drawing shall be known as the
reference master. The reference master, if required, shall be utilised for the electronic
issue of the file.
Superseded master plots shall be retained and endorsed "superseded".
DRAWING DEVELOPMENT
3.1
Example
See
Reference
CH2MHILL
3.1.1
Project
Name
Discipline /
Drawing
Type code
SBIA
SWD
3.1.2
3.1.3
Document
code
DWG
3.1.4
Drawing
Number
1001
Sheet No
001
3.1.5
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 335
EPC Agreement
3.1.5
3.2
Example
D2
See
Reference
3.2.1
Originator
code
CH2MHILL -
3.1.2
Project
Name
SBIA
3.1.3
Discipline
code
Short Description
HW
Proposed _Centre_
line
3.1.4
3.2.5
2D Model
D2
3D Model
D3
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 336
EPC Agreement
3.3
The top line shall identify the specific area or Section within the contract, i.e.
HIGHWAYS, or it may be left blank where no such area or Section exists.
ii)
The second third and fourth lines shall identify the content or purpose of the
Drawing, i.e. TRAFFIC SIGNS AND ROAD MARKINGS
iii) Where several Drawings depict similar detail and no other qualifications are
available for distinguishing between them, the distinction shall be made by
labelling each Drawing consecutively with sheet numbers, such as SHEET
1
OF 10, SHEET 2 OF 10, etc.
Figure 3
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 337
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
EPC Agreement
Page 338
EPC Agreement
Table 5
Drawing Status
Concept Design
Preliminary Design
Detailed Design
Tender
Contract
As Built
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 339
EPC Agreement
The date shown in the revision history table shall be in the format DDMMMYY as
highlighted in Figure 9 below
Figure 9
Month
Abbreviation
Month
JAN
January
JUL
July
FEB
February
AUG
August
MAR
March
SEP
September
APR
April
OCT
October
MAY
May
NOV
November
JUN
June
DEC
December
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 340
EPC Agreement
The date of completion of the revision and the initials of the person effecting the
revision shall be stated.
The earliest revision descriptions shall be deleted when there is no space to include
the current revision within the revision column.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 341
EPC Agreement
Figure 13
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 342
EPC Agreement
3.3.11 Signatures
The revision history table shall contain the current issue revision number, date of
issue, Drafter/Author, Checker, Approver signatures or initials and description of
current revision.
Table 7
TITLE BLOCK
CAD
HARD COPY
PDF COPY
DRAWN BY
See 3.3.12
See 3.3.13
See 3.3.14
CHECKED BY
See 3.3.12
See 3.3.13
See 3.3.14
APPROVER BY
See 3.3.12
See 3.3.13
See 3.3.14
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 343
EPC Agreement
Original hand-signed copy is required for all Final Drawings submitted for: Concept
design, Preliminary design, Detailed design, Tender set, Contract set, GFC Drawings
(during Construction) and As Built.
Subsequent hard copies of the submitted original do not have to be hand signed.
Scanned copies of the hand signed Drawing are permitted as long as the clarity of the
Drawing is not compromised. Alternatively, copies may be printed directly from
CAD. It is acceptable for these not to contain a copy of the hand signature, but to bear
typed initials instead.
3.4
Units
All general Drawing work (e.g. Xrefs) are to be in model space and be produced in
meters to three decimal places.
Drawing borders to be in paper space and in
millimeters.
e.g.
54.000
78.720
0.325
Dimensions in meters and using whole numbers, can be expressed using the m
(meter) suffix as in the following
45.000m
The position of the decimal point shall be the same as a full stop and no space shall be
left between the number and its units, to ensure clarity, as in the following example:
5.800m
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 344
EPC Agreement
All other non-linear measurements, e.g. areas and volumes, shall be followed by the
unit symbol. The most common non-linear measurements are as follows
Square meter -
m2
Cubic meter
m3
All detail Drawing work (e.g. standard details) is to be in model space and be
produced in millimeters in whole numbers (i.e. no decimal places).
e.g.
10000
787
Dimensions in millimeters using whole numbers, can be expressed using the mm
(millimeter) suffix as in the following
250mm
Chainages shall be in meters and written as shown
0+100 (Chainages in whole numbers can be written without the decimal
accuracy)
15+255.345
Chainages are plan measurements taken along a setting out line, and provide a
horizontal distance not taking into account slope lengths.
3.5
Drawing Sizes
Drawing sizes shall conform to the International Standards Organisation (ISO).
Sizes (in mm) are as follows: A0 1189 x 841
A1 841 x 594
A2 594 x 420
A3 420 x 297
A4 297 x 210
In general, all Drawings shall be produced at the preferred A1 original size. The use of
A0 size Drawings shall be avoided wherever
possible.
Each group or set of Drawings shall use only one Drawing size unless situations
make this impractical.
3.6
Scales
Scales used on Drawings shall be selected as indicated in the table below. Only
standard metric scales shall be used. In all cases, the selected scale shall be large
enough to permit easy and clear interpretation of the information depicted.
Specific scale requirements of particular Drawings such as layouts will be as stated as
per RFP.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 345
EPC Agreement
Table 8
Permitted scales
1:1
1:2
1:10
1:100
1:1000
1:10,000
1:20
1:200
1:2000
1:20,000
1:25
1:250
1:2500
1:25,000
1:5
2:1
1:50
1:500
1:5000
1:50,000
5:1
10:1
20:1
50:1
In exceptional cases where for functional reasons the recommended scale cannot be
applied, intermediate scales may be chosen, provided that the required scale is of a
whole number, such as 1:125, 1:150, etc.
The following scale notes shall be considered:
i.
ii.
iii.
iv.
Where different scales exist, each scale shall be specified under the title of the
area of the Drawing to which it applies and noted in the Title Block field
as shown below:
Figure 16
v.
Where a single scale is used on a Drawing, it shall be specified within the title
block only. (See the object area and shall be large enough to below). The scales
selected shall depend on the object area and shall be large enough to permit easy
and clear interpretation of information and ensure clarity of prints on the
original as well as reduced copies i.e. A3 versions of A1 Drawings.
Figure 17
vi.
Where different scales are used for horizontal and vertical dimensions, such as
in profiles, each scale shall be clearly indicated on the Drawing as shown
below:
Figure 18
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 346
vii.
EPC Agreement
When the Drawing is not drawn to any scale, NTS (Not to Scale) shall be
placed in the title block as shown below:
Figure 19
Key Plan
Where layout plans are produced on a number of Drawings to cover the extent or
Section of the Project, a Key Plan shall be included on each sheet, clearly indicating
the Section of the Works under consideration. A dedicated box in the title frame is
provided for the Key Plan as shown below.
Figure 20
3.8
Drawing Notes
Notes are to be numbered and positioned appropriately and shall include the following
notes:
3.9
i.
ii.
All levels are in meters (Only on Drawings where this note is applicable)
iii.
General Notes
Where notes are extensive and apply on several Drawings, a General Notes
Drawing shall be provided which consolidates all notes. Deviation from these notes
on a particular Drawing may be permitted, provided this amendment is shown in
the
Notes section of the Drawing.
Where a General Notes Drawing is used, the first note on each applicable Drawing
shall contain the following statement: 1. FOR GENERAL NOTES, REFER TO DRAWING NO. XXX
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 347
EPC Agreement
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 348
3.11
EPC Agreement
3.12
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 349
EPC Agreement
Figure 22: Flow diagram showing overview of CAD Drawing checking procedure
INITIAL DRAFTING
AMEND DRAWING
NO ACTION REQUIRED
RAISE CHECK PRINT
ISSUE
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 350
EPC Agreement
3.12.5 Approval
Upon completion of the checking process, a clean print of the Drawing shall be
submitted to the relevant checkers for signature and to the designated authority for
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 351
EPC Agreement
approval. This then becomes the controlled Drawing for reference. The checkers and
approvers initials together with the relevant dates shall be entered in the appropriate
areas of the CAD file.
4.1
Drawing set up
i. All AutoCAD Drawings should be produced & saved in AutoCAD version not
lowers than 2009.
ii. Pre-defined Project Drawing templates will be used for setting the layers of
identifiable Drawings (e.g. drainage, roads).
iii. Units in AutoCAD shall be set to meters for Infrastructure layouts and profiles
and millimeters for detail Drawings such as standard details.
iv. The CAD files provided will be in the current version of AutoCAD file format
used on the Project.
v. Fonts and line types are to be followed as provided in this manual.
vi. Files shall be purged before issue only.
vii. Drawing features/entities must be in model space. Title frames must be in paper
space.
viii. The colour and line type of each entity is drawn on BYLAYER.
ix. All polygons shall be closed polylines.
x. Do not place entities on layer 0. This layer is for the creation of blocks only.
4.2
Line Work
ii.
iii.
iv.
The plotted appearance of line types shall be consistent across all Drawings.
v.
vi.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 352
EPC Agreement
Display
Screen Color
Plotted Line
Weight
(mm)
Plotted Colour
RED
0.18
Yellow
0.25
3
4
5
6
7
Green
0.35
Cyan
Blue
Magenta
White
0.50
0.70
0.35
0.25
SBIA_COL_
A1.CTB
BLACK
BLACK
BLACK
BLACK
BLACK
BLACK
BLACK
8
9
10
11-79 & 81-249
80
Dark Grey
Light Grey
Object Colour
Object Colour
Object Colour
0.20
0.15
0.6
0.35
0.6
Object Colour
Object Colour
Object Colour
Object Colour
Object Colour
250-255 (Greys)
Object Colour
0.15
Object Colour
4.3
Text
4.3.1
General
SBIA_BW
_A1.CTB
BLACK
BLACK
BLACK
BLACK
BLACK
BLACK
BLACK
BLACK
BLACK
BLACK
BLACK
BLACK
Object
Colour
i.
ii.
iii.
The objective shall be to make all lettering highly legible so that information can
be communicated with the minimal possibility of error in reading.
Lettering sizes shall be chosen such that it shall remain legible when Drawings
are reduced to A3 size.
iv.
Lettering shall be consistent, both in size and placement. Lettering sizes for
specific applications, such as notes or titles, shall not vary within the same
Drawing.
v.
Lettering shall be uniform, clear, sharp and distinct. The mixing of lettering
styles, sloping, italic, and elaborate fonts shall not be permitted.
vi.
All text shall be regularly spaced, upright and uppercase and not be
underlined. Deviation: Titles under plans, details etc. are to be underlined.
vii.
All text shall be left justified. Deviation: Titles shall be centre justified and
underlined.
viii.
Specific notations shall be carefully placed so they relate to the portion of the
Drawing or detail to which they apply.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 353
EPC Agreement
ix.
x.
4.3.2 Fonts
Permitted text fonts are as shown below:
Table 11
AutoCAD Style Name
CAD Usage
ISOCP
ISOCP.SHX
Technical/Engineering Drawings
ARIAL
ARIAL.TTF
Presentation Drawings
Width Factor
Plotted Line
weight
1.8
0.18
2.5
0.25
3.5
0.35
5.0
0.5
7.0
0.7
i.
Usage
General text, Dimensions, Notes used on A3 &
A4 only where Drawing is not plotted at a
reduced scale.
General text annotations, Dimensions, Notes
Special Notes
For more prominent notes or labels requiring
special emphasis.
Normal Titles, Drawing Numbers, Section titles,
Detail Titles
Major Titles
The preferred text height for general text and notes is 2.5mm.
ii. The text height adopted for a Project shall be consistent across all Drawings
unless situations make this impractical.
4.4 Dimensioning
Automated dimensioning commands within CAD software programs shall be used for
creation and editing of dimensions, as shown in table 16 below.
The editing of dimension values via basic text editing commands is not permitted.
Dimensions shall be associative and placed on their own unique layer.
Table 13
Dimension Text
Height
Extension
Line Offset
Extension Line
Extension
2.5mm
Dimexo = 2
Dimexe = 2
Stack Offset
Dimdli = 6.25
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Arrow Size
Centre Mark
Dimasz = 2.5
Dimcen = 1
Page 354
EPC Agreement
4.6 Hatching
Wherever possible, all hatching created shall be associative and placed on its own
unique layer. Exploding of hatches must be avoided.
4.7 Colours
In AutoCAD, entity colour shall be assigned By Layer. Deviation can be on
standard blocks, i.e. are Road signs blocks where specific standard colours are
assigned for each.
4.8 Layering
CAD Layering shall be in accordance with PMNC AutoCAD Layering Standards as
included in Appendix A of this document.
Additional layers may be required and the naming of such layers must be in the same
format in accordance with PMNC AutoCAD Layering Standards as shown in Section
4.8.1.
Department Designator
Status / Section Designator
Feature / Entity Designator
Page 355
EPC Agreement
Where CAD data is to be shared between Drawings the use of reference files is
to be adopted.
ii.
All reference files are to be inserted in model space with the UCS set to world.
All files are to be inserted at 0,0,0.
iii.
iv.
v.
vi.
Reference files shall be inserted on unique layer that does not conflict with the
general content of the Drawing. (i.e. layer Z_DREF in AutoCAD).
vii. Reference files shall be CLIPPED within the Active Drawing sheet file to
ensure that only the design data relevant to the Drawing is displayed.
viii. Reference files issued externally or shared between departments shall indicate
revised areas with a revision cloud and triangle. A revision history shall be
maintained within the reference file. In AutoCAD, the revision history log shall
be placed in paper space, see Figure 29 below.
ix.
4.10 Plotting
The following standard colour source files shall be used:
Table 14
Colour
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 356
EPC Agreement
Aarvee-SBIA--COL_A1.CTB
Aarvee-SBIA-BW_A1.CTB
This standard colour source file shall be flexible and can be adjusted to suit users
need during plotting. When Drawing files are required, CTB file used for the plotting
of the Drawing must also be submitted.
4.11.1 Submission
Refer to Programme Management Information System (PMIS) and Document.
Management
Drawing.
procedures
on
submission
of
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 357
EPC Agreement
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 358
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
EPC Agreement
Page 359
EPC Agreement
A.1
General Layers
CORE LAYERS NON DISCIPLINE
Layer Name
Screen
Colour
Line type
Plotted
Line
weight
Description
Z_18TEXT
red
Continuous
0.18
Z_25TEXT
white
Continuous
0.25
Z_35TEXT
green
Continuous
0.35
Z_50TEXT
cyan
Continuous
0.50
Z_70TEXT
blue
Continuous
0.70
Z_DIMS
red
Continuous
0.18
ALL DIMENSIONS
Z_DWG_GRID
251
Continuous
0.15
Z_DWG_SHT
white
Continuous
0.25
Z_NORTH
green
Continuous
0.35
NORTH POINT
Z_REV
yellow
Continuous
0.25
Z_SECMK
green
Continuous
0.35
Z_XREF
white
Continuous
0.25
GIS LAYERS
Layer Name
Screen
Colour
Line type
GIS_ACQ_BDRY
20
ACAD_ISO13W10
0
0.25
GIS_CADASTRAL
red
Continuous
0.18
CADASTRAL PLOT
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 360
EPC Agreement
GIS LAYERS
Layer Name
Screen
Colour
Line type
GIS_CNTRS
Continuous
0.15
CONTOURS
GIS_CNTRS_TEXT
red
Continuous
0.18
CONTOURS TEXT
GIS_CSTL
90
Continuous
0.35
COASTLINE
GIS_FLOWLINE
Continuous
0.20
FLOWLINES
GIS_PPLN
252
Continuous
0.15
POLICY PLAN
GIS_RD01
121
Continuous
0.35
MAJOR ROAD
GIS_RD02
151
Continuous
0.35
MINOR ROAD
GIS_RD03
181
Continuous
0.35
STREETS
GIS_ROW_BDRY
170
PHANTOM2
0.35
PROPOSED RIGHT
BOUNDARY
GIS_ZONE
13
Continuous
0.35
ZONE
A.2
Drainage layers
A.2.1
OF
WAY
Screen
Colour
Line type
Plotted
Line
weight
D_PR_SGW
80
SGW_PR
0.6
D_PR_SGW_ATT
white
0.25
PROPOSED
SGW
ATTRIBUTES
Diameter, Length, Material etc.)
Continuous
Description
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 361
(ID,
EPC Agreement
Screen
Colour
Line type
Plotted
Line
weight
Description
D_PR_SGW_DCH
90
Continuous
0.35
D_PR_SGW_DT
yellow
Continuous
0.25
D_PR_SGW_FCH
90
Continuous
0.35
D_PR_SGW_FLOW
white
Continuous
0.25
D_PR_SGW_FMC
90
Continuous
0.35
D_PR_SGW_GC
90
Continuous
0.35
D_PR_SGW_GL
90
Continuous
0.35
D_PR_SGW_ICH
90
Continuous
0.35
D_PR_SGW_ITCH
90
Continuous
0.35
D_PR_SGW_MH
90
Continuous
0.35
D_PR_SGW_MH_ATT
white
D_PR_SGW_OFCH
90
Continuous
0.35
D_PR_SGW_PS
90
Continuous
0.35
D_PR_SGW_RM
90
RM_PR
0.35
D_PR_SGW_VALV
90
Continuous
0.35
D_PR_SGW_VC
90
Continuous
0.35
D_PR_SGW_WCH
90
Continuous
0.35
Continuous
0.25
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 362
EPC Agreement
Screen
Colour
Line type
Plotted
Line
weight
Description
D_EX_SGW
96
SGW_EX
0.35
EXISTING
LINES
D_EX_SGW_ATT
white
Continuous
0.25
D_EX_SGW_DCH
96
Continuous
0.35
D_EX_SGW_DT
yellow
Continuous
0.25
D_EX_SGW_FCH
96
Continuous
0.35
D_EX_SGW_FLOW
white
Continuous
0.25
D_EX_SGW_FMC
96
Continuous
0.35
D_EX_SGW_GC
96
HIDDEN2
0.35
D_EX_SGW_GL
96
Continuous
0.35
D_EX_SGW_ICH
96
Continuous
0.35
D_EX_SGW_ITCH
96
Continuous
0.35
D_EX_SGW_MH
96
Continuous
0.35
D_EX_SGW_MH_ATT
96
Continuous
0.35
D_EX_SGW_OFCH
96
DASHED2
0.25
D_EX_SGW_PS
96
Continuous
0.35
D_EX_SGW_RM
96
RM_EX
0.35
D_EX_SGW_VALV
96
Continuous
0.35
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
SURFACE
GROUND
Page 363
WATER
EPC Agreement
Screen
Colour
Line type
Plotted
Line
weight
Description
D_EX_SGW_VC
96
Continuous
0.25
D_EX_SGW_WCH
96
Continuous
0.25
A.2.2
Layer Name
Screen
Colour
Line type
Plotted Line
weight
Description
SEW_DE_PSWR
242
SEW_PR
0.35
SEW_DE_MH
242
Continuous
0.25
242
Continuous
0.25
242
Continuous
0.25
DESIGN
SHAFT
Continuous
0.25
Continuous
0.25
Continuous
0.25
Continuous
0.25
SEW_DE_SWPS
SEW_DE_VSHFT
SEW_DE_SCONN
SEW_DE_MHFC
SEW_DE_STP
SEW_DE_PM
242
242
242
242
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
SEWER
FEATURE:
Page 364
VENT
EPC Agreement
A.2.3
Layer Name
Screen
Colour
Line type
Plotted
Line weight
white
Continuous
0.35
INEFF_DE_VSHFT
white
Continuous
0.25
INEFF_DE_IEPS
white
Continuous
0.25
INEFF_DE_SINLET
white
Continuous
0.25
INEFF_DE_TERTIARY
TREATMETN PLANT
white
Continuous
0.25
INEFF_DE_PINEF
A.2.4
Description
DESIGN
INDUSTRIAL
EFFLUENT
FEATURE:PROPOSED
INDUSTRIAL
EFFLUENT
DESIGN
INDUSTRIAL
EFFLUENT
FEATURE: VENT SHAFT
DESIGN
INDUSTRIAL
EFFLUENT
FEATURE:INDUSTRIAL
EFFLUENT
PUMPING STATION
DESIGN
INDUSTRIAL
EFFLUENT
FEATURE: SECTONDARY TREATMENT
PLANT INLET S
DESIGN
INDUSTRIAL
EFFLUENT
FEATURE: TERTIARY TREATMENT
PLANT
Potable Water
PROPOSED POTABLE WATER LINE
Layer Name
Screen
Colour
Line type
Plotted
weight
PW_DE_PWTM
Blue
Continuous
0.35
PW_DE_PWDIST
Blue
Continuous
0.25
PW_DE_PWPS
Blue
Continuous
PW_DE_VCH
Blue
Continuous
PW_DE_FH
Blue
Continuous
PW_DE_POTRES
Blue
Continuous
PW_DE_PWM
Blue
Continuous
PW_DE_PWFIT
Blue
Continuous
Line
Description
DESIGN POTABLE WATER FEATURE:
POTABLE
WATER
TRANSMISSION
MAIN
DESIGN POTABLE WATER FEATURE:
POTABLE WATER DISTRIBUTION
0.25
0.25
0.25
0.25
0.25
0.25
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 365
EPC Agreement
A.2.5
Recycled Water
PROPOSED RECYCLED WATER
Layer Name
Screen
Colour
Line type
Plotted
Line
weight
Description
RW_DE_RWPM
Green
Continuous
0.35
DESIGN
RECYCLED
WATER
FEATURE: RECYCLED WATER PUMPING
MAIN
RW_DE_RWDIST
Green
Continuous
0.025
DESIGN
RECYCLED
FEATURE:
RECYCLED
DISTRIBUTION
RW_DE_RWPS
Green
Continuous
RW_DE_RWRES
Green
Continuous
RW_DE_RWVCH
Green
Continuous
RW_DE_RWFIT
Green
Continuous
A.3
WATER
WATER
0.025
DESIGN
RECYCLED
WATER
FEATURE: RECYCLED WATER PUMPING
STATION
0.025
DESIGN
FEATURE:
RESERVOIR
0.025
DESIGN
FEATURE:
CHAMBER
0.025
DESIGN
RECYCLED
WATER
FEATURE: RECYCLED WATER FITTINGS
RECYCLED
RECYCLED
WATER
WATER
RECYCLED
WATER
RECYCLED WATER VALVE
ROAD LAYERS
Screen
Colour
Line type
Plotted
Line
weight
Description
RD_DE_AFNCE
22
FENCELINE1
0.35
RD_DE_BICYL
green
Continuous
0.35
BICYCLE LANE
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 366
EPC Agreement
PROPOSED ROAD
Layer Name
Screen
Colour
Line type
Plotted
Line
weight
Description
RD_DE_BRDG
yellow
Continuous
0.25
DESIGN ROAD
FLYOVER
RD_DE_CHNL
red
HIDDEN2
0.18
RD_DE_CILND
green
Continuous
0.35
DESIGN
ROAD
FEATURE:
ENTRAL/ROUNDABOUT ISLAND
RD_DE_CLMN
red
Continuous
0.18
RD_DE_CLVT
white
Continuous
0.25
RD_DE_CNRL
red
CENTER2
0.18
RD_DE_CSLPE
magenta
Continuous
0.35
CONCRETE
RD_DE_ECWAY
cyan
Continuous
0.5
EDGE OF
RD_DE_FNCE
green
FENCELINE2
0.35
RD_DE_FTPH
11
Continuous
0.35
RD_DE_GRAIL
white
Continuous
0.25
RD_DE_ILND
green
HIDDEN2
0.35
RD_DE_JILND
green
Continuous
0.35
RD_DE_KBDD
green
HIDDEN2
0.35
RD_DE_KBED
white
Continuous
0.25
RD_DE_KBFL
yellow
DASHED2
0.25
RD_DE_KBRD
cyan
Continuous
0.5
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
FEATURE:
BRIDGE
JUNCTION
Page 367
EPC Agreement
PROPOSED ROAD
Layer Name
Screen
Colour
Line type
Plotted
Line
weight
RD_DE_LOW
blue
DASHDOT2
0.7
LIMIT OF WORKS
RD_DE_EMBK
yellow
Continuous
0.25
green
Continuous
0.35
RD_DE_MEDIAN
Description
RD_DE_OTHR
red
Continuous
0.18
DESIGN
ROAD
INFORMATION
RD_DE_PBAY
green
Continuous
0.35
RD_DE_PDCR
Continuous
0.2
Continuous
0.35
RD_DE_PRAMP
green
DATA
OTHER
RD_DE_PRKG
white
Continuous
0.25
RD_DE_PTS
yellow
Continuous
0.25
RD_DE_PVMT
Continuous
0.2
RD_DE_RAILWAY
white
TRACKS
0.25
RD_DE_RAMP
yellow
Continuous
0.25
RD_DE_RLVL
white
Continuous
0.25
RD_DE_RNDA
white
Continuous
0.25
RD_DE_RSTL
white
Continuous
0.25
RD_DE_SHLDR
green
Continuous
0.35
RD_DE_SPTR
20
Continuous
0.35
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 368
EPC Agreement
PROPOSED ROAD
Layer Name
Screen
Colour
Line type
Plotted
Line
weight
Description
RD_DE_UPSS
yellow
Continuous
0.25
RD_DE_URAREA
40
DASHED2
0.35
DESIGN
ROAD
RESERVE AREA
FEATURE:
UTILITY
RD_DE_VBAR
magenta
Continuous
0.35
DESIGN ROAD
BARRIER
FEATURE:
VEHICLE
RD_DE_VERGE
yellow
Continuous
0.25
EXISTING ROAD
Layer Name
Screen
Colour
Line type
Plotted
Line
weight
Description
FENCELINE1
0.35
Continuous
0.35
BICYCLE LANE
Continuous
0.25
EXISTING
FLYOVER
red
HIDDEN2
0.18
RD_EX_CILND
green
Continuous
0.35
EXISTING
ROAD
FEATURE:
ENTRAL/ROUNDABOUT ISLAND
RD_EX_CLMN
red
0.18
EXISTING
COLUMN
RD_EX_CLVT
white
Continuous
0.25
RD_EX_CNRL
red
CENTER2
0.18
RD_EX_AFNCE
22
RD_EX_BICYL
green
RD_EX_BRDG
yellow
RD_EX_CHNL
Continuous
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
ROAD
ANIMAL
FEATURE:
ROAD
BRIDGE
FEATURE:
Page 369
EPC Agreement
EXISTING ROAD
Layer Name
Screen
Colour
Line type
Plotted
Line
weight
RD_EX_CSLPE
magenta
Continuous
0.35
CONCRETE
RD_EX_ECWAY
cyan
Continuous
0.5
EDGE OF
RD_EX_FNCE
green
FENCELINE2
0.35
RD_EX_FTPH
11
Continuous
0.35
RD_EX_GRAIL
white
Continuous
0.25
RD_EX_ILND
green
HIDDEN2
0.35
RD_EX_JILND
green
Continuous
0.35
RD_EX_KBDD
green
HIDDEN2
0.35
RD_EX_KBED
white
Continuous
0.25
RD_EX_KBFL
yellow
DASHED2
0.25
RD_EX_KBRD
cyan
Continuous
0.5
RD_EX_LOW
blue
DASHDOT2
0.7
LIMIT OF WORKS
RD_EX_EMBK
yellow
Continuous
0.25
EXISTING
EMBANKMENT
green
Continuous
0.35
RD_EX_MEDIAN
Description
JUNCTION
ROAD
FEATURE:
RD_EX_OTHR
red
Continuous
0.18
EXISTING
ROAD
INFORMATION
RD_EX_PBAY
green
Continuous
0.35
RD_EX_PDCR
Continuous
0.2
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
DATA
Page 370
OTHER
EPC Agreement
EXISTING ROAD
Layer Name
Screen
Colour
Line type
Plotted
Line
weight
green
Continuous
0.35
RD_EX_PRAMP
Description
RD_EX_PRKG
white
Continuous
0.25
RD_EX_PTS
yellow
Continuous
0.25
RD_EX_PVMT
Continuous
0.2
RD_EX_RAILWAY
white
TRACKS
0.25
RD_EX_RAMP
yellow
Continuous
0.25
RD_EX_RLVL
white
Continuous
0.25
RD_EX_RNDA
white
Continuous
0.25
EXISTING
ABOUT
RD_EX_RSTL
white
Continuous
0.25
RD_EX_SHLDR
green
Continuous
0.35
RD_EX_SPTR
20
Continuous
0.35
EXISTING
ROAD
SEPARATOR
RD_EX_UPSS
yellow
Continuous
0.25
RD_EX_URAREA
40
DASHED2
0.35
EXISTING ROAD
RESERVE AREA
FEATURE:
UTILITY
RD_EX_VBAR
magenta
Continuous
0.35
EXISTING
BARRIER
FEATURE:
VEHICLE
RD_EX_VERGE
yellow
Continuous
0.25
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
ROAD
ROAD
FEATURE:
ROUND
FEATURE:
Page 371
ROAD
EPC Agreement
Screen
Colour
Line type
Plotted
Line
weight
RD_DE_TS_BARL
green
Continuous
0.35
RD_DE_TS_CTRL-BOX
red
Continuous 0.18
RD_DE_TS_DET-LOOP
Continuous 0.2
RD_DE_TS_DUCT
30
Continuous 0.35
TRAFFIC : DUCT
RD_DE_TS_HMPL
Continuous
RD_DE_TS_INCH
12
Continuous 0.35
RD_DE_TS_MNHL
yellow
Continuous
0.25
TRAFFIC : MANHOLE
RD_DE_TS_OHLL
white
Continuous
0.25
RD_DE_TS_OTHR
yellow
Continuous
0.25
TRAFFIC : OTHER
RD_DE_TS_PBDG
31
Continuous
0.35
RD_DE_TS_PGR
40
Continuous
0.35
RD_DE_TS_PUP
13
Continuous
0.35
RD_DE_TS_RDSN
yellow
Continuous
0.25
RD_DE_TS_SIGN
white
Continuous
0.25
RD_DE_TS_SIGN-POST
white
Continuous
0.25
RD_DE_TS_SIGNAL
white
Continuous
0.25
TRAFFIC SIGNAL
0.2
Description
TRAFFIC:
BOLLARDS
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
BARRIERS,
RAILS
Page 372
&
EPC Agreement
RD_DE_TS_SIGNALPOST
white
Continuous
0.25
RD_DE_TS_STNM
green
Continuous
0.35
RD_DE_TS_STUDS
Continuous
0.2
TRAFFIC : STUDS
RD_DE_TS_TEXT
white
Continuous
0.25
TRAFFIC
:
/DESCRIPTIVE TEXT
RD_DE_TS_TPP
Continuous
0.2
RD_DE_TS_UGLL
yellow
Continuous
0.25
ANNOTATIONS
Screen
Colour
Line type
Plotted
Line
weight
Description
RD_DE_TS_BARL
green
Continuous
0.35
TRAFFIC:
BOLLARDS
RD_EX_TS_CTRL-BOX
red
Continuous
0.18
RD_EX_TS_DET-LOOP
Continuous
0.2
RD_EX_TS_DUCT
30
Continuous
0.35
TRAFFIC : DUCT
RD_EX_TS_HMPL
Continuous
0.2
RD_EX_TS_INCH
12
Continuous
0.35
RD_EX_TS_MNHL
yellow
Continuous
0.25
TRAFFIC : MANHOLE
RD_EX_TS_OHLL
white
Continuous
0.25
RD_EX_TS_OTHR
yellow
Continuous
0.25
TRAFFIC : OTHER
RD_EX_TS_PBDG
31
Continuous
0.35
RD_EX_TS_PGR
40
Continuous
0.35
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
BARRIERS,
RAILS
Page 373
&
EPC Agreement
Screen
Colour
Line type
Plotted
Line
weight
Description
RD_EX_TS_PUP
13
Continuous
0.35
RD_EX_TS_RDSN
yellow
Continuous
0.25
RD_EX_TS_SIGN
white
Continuous
0.25
RD_EX_TS_SIGN-POST
white
Continuous
0.25
RD_EX_TS_SIGNAL
white
Continuous
0.25
TRAFFIC SIGNAL
RD_EX_TS_SIGNALPOST
white
Continuous
0.25
RD_EX_TS_STNM
green
Continuous
0.35
RD_EX_TS_STUDS
Continuous
0.2
TRAFFIC : STUDS
RD_EX_TS_TEXT
white
Continuous
0.25
RD_EX_TS_TPP
Continuous
0.2
RD_EX_TS_UGLL
yellow
Continuous
0.25
Screen
Colour
Line type
Plotted
Line
weight
RD_DE_ST_CBLE
cyan
Continuous
0.5
Description
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 374
EPC Agreement
Screen
Colour
Line type
Plotted
Line
weight
Description
RD_DE_ST_DUCT
20
Continuous
0.35
RD_DE_ST_FDPL
magenta
Continuous
0.35
RD_DE_ST_POLE
yellow
Continuous
0.25
RD_DE_ST_SUBSTN
cyan
Continuous
0.5
RD_DE_ST_TEXT
white
Continuous
0.25
Screen
Colour
Line type
Plotted
Line
weight
Description
RD_EX_ST_CBLE
cyan
DASHED2
0.5
RD_EX_ST_DUCT
20
HIDDEN2
0.35
RD_EX_ST_FDPL
magenta
Continuous
0.35
RD_EX_ST_POLE
Continuous
0.25
RD_EX_ST_SUBSTN
cyan
Continuous
0.5
RD_EX_ST_TEXT
white
Continuous
0.25
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 375
EPC Agreement
Screen
Colour
RD_F_BNCH
yellow
RD_F_LGHT
white
RD_F_OTHR
Line type
Continuous
Plotted
Line
weight
Description
0.25
ROAD/STREET FURNITURE:
BENCH/SEAT
Continuous
0.25
white
Continuous
0.25
RD_F_POLE
yellow
Continuous
0.25
RD_F_TEXT
white
0.25
ROAD/STREET FURNITURE:
ANNOTATION/TEXT
Continuous
Screen
Colour
Line type
Plotted
Line
weight
Description
RD_C_25DASH
white
DASHED2
0.25
HIDDEN DETAILS
RD_C_25HID
white
HIDDEN2
0.25
HIDDEN DETAILS
RD_C_50OUT
cyan
Continuous
0.5
RD_C_50REBARS
cyan
Continuous
0.5
REINFORCEMENTDETAILS
RD_C_CHAIN_TEXT
white
Continuous
0.25
CHAINAGE TEXT
RD_C_CHAIN_TICK
yellow
Continuous
0.25
RD_C_CONT_MAJR
Continuous
0.2
MAJOR CONTOUR
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 376
EPC Agreement
Screen
Colour
Line type
Plotted
Line
weight
RD_C_CONT_MINR
Continuous
0.15
MINOR CONTOUR
RD_C_COORD_GRID
252
Continuous
0.15
COORDINATE GRID
RD_C_CTRLINE
red
CENTER2
0.18
CENTRE LINE
RD_C_HATCH
red
Continuous
0.18
HATCH
RD_C_MATCH_LINE
blue
PHANTOM
0.7
RD_C_PROF
cyan
DASHED2
0.5
PROFILES
RD_C_PROF-LINE
green
Continuous
0.35
PROFILE LINES
RD_C_PROF_GRID_MAJ
R
0.2
RD_C_PROF_GRID_MIN
OR
0.15
RD_C_SPT_HGT
yellow
Continuous
0.25
RD_C_SPT_NUM
yellow
Continuous
0.25
RD_C_TABLE
white
Continuous
0.25
TABLES
RD_C_TEXT
white
Continuous
0.25
COMMON TEXT
Continuous
Continuous
Description
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 377
EPC Agreement
Screen
Colour
Line type
Plotted
Line
weight
Description
BR_ABT
RED
Continuous
0.3
ABUTMENT
BR_BEARING
GREEN
Continuous
0.25
BEARING
BR_BH
11
Continuous
0.10
HATCH
BR_BR
160
Continuous
0.6
BOUNDARY
BR_CB
Continuous
0.25
CRASH BARRIER
BR_CEN
WHITE
Center
0.18
CENTER LINE
BR_DIM
MAGENTA
Continuous
0.18
DIMENSION
BR_DS
200
Continuous
0.18
DRAINAGE SPOUT
BR_GEN
YELLOW
Continuous
0.30
STRUCTURE
BR_HIDDEN
HIDDEN
0.15
BR_MAIN
RED
Continuous
0.35
HEADING TEXT
BR_MARK
CYAN
Continuous
0.15
HAUNCH LINES
BR_PIER
RED
Continuous
0.25
PIER
BR_REINF
BLUE
Continuous
0.35
REINFORCEMENT
BR_TEXT
GREEN
Continuous
0.3
BR_TITLE
WHITE
Continuous
0.35
TITLE BLOCK
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 378
EPC Agreement
A.4
UTILITIES LAYERS
A.4.1 Electricity
(ELECTRICITY)
Layer Name
Screen
Colour
Line type
Plotted
Line
weight
Description
SVE_11KV
240
ACAD_ISO04W
100
0.35
SVE_132K
240
ACAD_ISO04W
100
0.35
SVE_66KV
240
ACAD_ISO04W
100
0.35
SVE_ABDL
13
Continuous
0.35
SVE_DUCT
10
Continuous
0.35
SVE_ERTH_PIT
Continuous
0.2
SVE_FT_TEE
30
Continuous
0.35
SVE_LOWV
220
Continuous
0.35
SVE_MEDV
150
Continuous
0.35
SVE_MHLL
white
Continuous
0.25
SVE_MNHL
white
Continuous
0.25
SVE_MRKR
white
Continuous
0.25
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 379
EPC Agreement
Screen
Colour
ELECTRICITY
Line type
Plotted
Line
weight
SVE_OHLL
white
Continuous
0.25
SVE_OTHR
white
Continuous
0.25
SVE_POLE
white
Continuous
0.25
SVE_PYLN
white
Continuous
0.25
SVE_SBOX
white
Continuous
0.25
SVE_SJNT
green
Continuous
0.35
SVE_SSTL
yellow
Continuous
0.25
SVE_TEXT
white
Continuous
0.25
SERVICES FIXTURES
ANNOTATION / TEXT
SVE_TRANSF
cyan
Continuous
0.5
SVE_UGLL
white
Continuous
0.25
Layer Name
Description
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
(ELECTRICITY):
Page 380
EPC Agreement
A.4.2 Water
WATER
Layer Name
Screen
Colour
Line type
Plotted
Line
weight
Continuous
0.35
Description
SVW_ABDL
13
SVW_BNDL
130
Continuous
0.35
200
Continuous
0.35
200
Continuous
0.35
SERVICES FIXTURES
PROTECTION
130
Continuous
0.35
SVW_CLR_PT
SVW_CPRT
SVW_DRKL
(WATER)
CASING
WATER
Layer Name
Screen
Colour
Line type
Plotted
Line
weight
Description
AREA
SVW_DUCT
30
Continuous
0.35
150
Continuous
0.35
SERVICES
ADAPTER
SVW_FT_BEND
150
Continuous
0.35
SVW_FT_ENDCA
P
150
Continuous
0.35
SERVICES
ENDCAP
FIXTURES
(WATER)
FITTING
150
Continuous
0.35
SERVICES
REDUCER
FIXTURES
(WATER)
FITTING
150
Continuous
0.35
SVW_FT_ADPTR
SVW_FT_RDCR
SVW_FT_TEE
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
FIXTURES
(WATER)
Page 381
FITTING
EPC Agreement
200
Continuous
0.35
SERVICES
CHANNEL
SVW_GPIPE
200
Continuous
0.35
SVW_HYDR
200
Continuous
0.35
SVW_METER
200
Continuous
0.35
SVW_MNHL
170
Continuous
0.35
SVW_MRKR
130
Continuous
0.35
170
Continuous
0.35
SVW_PUMP
200
Continuous
0.35
SVW_SCSR
200
Continuous
0.35
SVW_SPIPE
200
Continuous
0.35
SVW_GCHNL
SVW_PIPE
FIXTURES
(WATER)
GRAVITY
WATER
Screen
Colour
Line type
Plotted
Line
weight
SVW_STRG_PT
200
Continuous
0.35
SVW_TANK
230
Continuous
0.35
SVW_TANK_FIL
_PT
200
Continuous
0.35
SERVICES FIXTURES
FILLING POINT
white
Continuous
0.25
Layer Name
SVW_TEXT
160
SVW_VALV
SVW_WELL
SVW_WFAC
Continuous
0.35
Description
(WATER)
TANKER
200
Continuous
0.35
200
Continuous
0.35
SERVICES
FACILITY
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
FIXTURES
(WATER)
Page 382
WATER
EPC Agreement
SVW_WMAIN
SVW_WSCON
170
DASHDOT2
0.35
200
Continuous
0.35
SERVICES FIXTURES
SERVICE CONENCTION
(WATER)
WATER
A.4.3 Commercial
COMMERCIAL
Layer
Name
Screen
Colour
Line type
Plotted
Line
weight
Description
SVC_TEXT
white
Continuous
0.25
SVC_SBDL
white
Continuous
0.25
COMMERCIAL
Layer
Name
Screen
Colour
Line type
SVC_POLE
white
Continuous
SVC_OTHR
white
Continuous
SVC_BBDL
30
Continuous
SVC_BANK
white
Continuous
Plotted
Line
weight
Description
0.25
0.25
0.25
0.25
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 383
OTHER
EPC Agreement
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 384
EPC Agreement
Zoom XP Scale
1
1 : 200
1 : 100
1 : 50
1 : 20
1 : 10
1:5
1:2
1:1
5
10
20
50
100
200
500
1000
0.8
0.4
0.2
0.1
0.04
0.02
2
Zoom XP Scale
0.002
1 : 200
1 : 100
1 : 50
1 : 20
1 : 10
1:5
1:2
1:1
0.005
0.01
0.02
0.05
0.1
0.2
0.5
1
Factor
(Multiply)
1 : 1000
1 : 1250
1 : 2500
1 : 5000
1 : 10000
1 : 25000
1.00
1.25
2.50
5
10
25
Text Height
0.25 Pen
2.5
3.125
6.25
12.5
25
62.5
0.35 Pen
3.5
4.375
8.75
17.5
35
87.5
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
0.5 Pen
5
6.25
12.5
25
50
125
Page 385
EPC Agreement
Scale of
Drawing
Factor
(Multiply)
1 : 50000
1 : 500
1 : 200
1 : 100
1 : 50
1 : 20
1 : 10
1:5
1:2
1:1
50
0.5
0.2
0.1
0.05
0.02
0.01
0.005
0.002
0.001
Text Height
0.25 Pen
125
1.25
0.5
0.25
0.125
0.05
0.025
0.0125
0.005
0.0025
0.35 Pen
175
1.75
0.7
0.35
0.175
0.07
0.035
0.0175
0.007
0.0035
0.5 Pen
250
2.5
1
0.5
0.25
0.1
0.05
0.025
0.01
0.005
Scale of
Drawing
Factor
(Multiply)
1 : 500
1 : 200
1 : 100
1 : 50
1 : 20
1 : 10
1:5
1:2
1:1
500
200
100
50
20
10
5
2
1
Text Height
0.25 Pen
500
200
100
50
20
10
5
2
1
0.35 Pen
1250
500
250
125
50
25
12.5
5
2.5
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
0.5 Pen
1750
700
350
175
70
35
17.5
7
3.5
Page 386
EPC Agreement
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 387
EPC Agreement
Project Codes
SBIA
Description
DRAWING
DRAWING LIST
SK Sketch Drawings
Title Series
Drawing No.
0000 - 0249
0250 - 0499
0500 - 0999
1000 -1499
1500 - 1999
2000 - 2499
2500 - 2999
3000 - 3999
4000 - 4999
5000 - 5499
5500 - 5999
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 388
Discipline/ Drawing
Type
GE - General
Title Series
Drawing No.
Foul Sewer
Treated Sewerage Effluent
Potable Water
Fire Water
Electricity
6000 - 6499
6500 - 6999
7000 - 7499
7500 - 7999
8000 - 8499
Drawing Lists
0001 - 0999
--0001 - 0999
HW - Highways
SC Site Clearance
0001 - 0999
0001 - 0999
SL - Street Lighting
---7000 - 7999
TR - Traffic/ Transport
EPC Agreement
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
1000 - 1999
2000 - 2999
3000 - 3999
4000 - 4999
5000 - 5999
6000 - 6999
7000 - 7999
8000 - 8999
2000 - 2999
--7000 - 7999
--0001 - 0999
1000 - 1999
2000 - 2999
3000 - 3999
4000 - 4999
5000 - 5999
--7000 - 7999
--0001 - 0999
Page 389
Discipline/ Drawing
Type
FE - Fencing
GR - Grading
Title Series
2000 - 2999
3000 - 3999
7000 - 7999
0001 - 0999
7000 - 7999
--0001 - 0999
UC - Utility Services
Corridor
PW - Potable Water
RW - Recycle Water
Drawing No.
ST - Structures
EPC Agreement
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
2000 - 2999
1000 - 1999
2000 - 2999
--7000 - 7999
--0001 - 0999
1000 - 1999
--7000 - 7999
--0001 - 0999
1000 - 1999
2000 - 2999
--7000 - 7999
--0001 - 0999
2000 - 2999
3000 - 3999
4000 - 4999
--7000 - 7999
8000 - 8999
0001 - 0999
1000 - 1999
2000 - 2999
Page 390
Discipline/ Drawing
Type
Title Series
Longitudinal Sections (Profiles)
Standard & Miscellaneous Details
FS - Foul Sewer/
Sewerage
SW - Surface Water
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
EPC Agreement
Drawing No.
3000 - 3999
--7000 - 7999
---0001 - 0999
1000 - 1999
2000 - 2999
3000 - 3999
--7000 - 7999
0001 - 0999
1000 - 1999
2000 - 2999
3000 - 3999
--7000 - 7999
---0001 - 0999
1000 - 1999
2000 - 2999
3000 - 3999
--7000 - 7999
---
Page 391
Discipline/ Drawing
Type
EL - Electricity
Title Series
General Notes, Abbreviations & Legends, Location
Plan, General Key Plan, Cluster layout, zoning etc.
Sub-station & network Layout, Single line diagram,
General Arrangement etc.
Extra High Voltage Electricity Supply Layout &
Keyplan
High Voltage Electricity Supply Layout & Keyplan
Medium Voltage Electricity Supply Layout & Keyplan
Low Voltage Electricity Supply Layout & Keyplan
Standard & Miscellaneous Details
EN - Environmental
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
EPC Agreement
Drawing No.
0001 - 0999
1000 - 1999
2000 - 2999
3000 - 3999
4000 - 4999
5000 - 5999
--7000 - 7999
--0001 - 0999
1000 - 1999
2000 - 2999
3000 - 3999
4000 - 4999
--7000 - 7999
---
Page 392
EPC Agreement
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 393
EPC Agreement
Contents
1.
2.
3.
4.
5.
6.
7.
8.
9.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 394
EPC Agreement
1.
HSE Standards
The contractor shall ensure that all personnel engaged (including sub-contractors) with the
Project shall be conversant with and at all times comply with the HSE standards for the
Project. The HSE standards shall include the relevant India HSE legislation, relevant IS
(Bureau of Indian Standards) & Project HSE documents.
2.
Legislation
The contractor shall ensure that as a minimum they will comply with all HSE requirements
imposed by India HSE legislation.
3.
4.
5.
6.
Environmental Management
The contractor shall specify in their HSE plan measures applied to avoid harm to the
environment.
7.
HSE PERSONNEL
The contractor shall ensure that adequate HSE personnel are appointed on the Project. No
HSE personnel on the Project shall be appointed without prior written permission from
PMNC. The Contractor shall ensure that all HSE personnel meet the requirements as
dictated by the Project HSE standards.
8.
Page 395
EPC Agreement
The contractor shall ensure that a Project HSE training matrix is produced. The training
matrix shall include the various positions on the Project and detail the HSE training that is
required for each position.
9.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 396
EPC Agreement
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 397
EPC Agreement
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 398
EPC Agreement
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 399
Titles of sections
Contractor must ensure that these sections are included in their Construction HSE plan.
The details in the sections are provided as guidance.
Section 1 - Project Details
Contractor to provide contact information for Key Contractor
personnel. Contact information to include Name, Mobile number,
email id. Key personnel include:
1.1
Project Specific
Details
1.2
Details of other
Consultants
1.3
Project Security
1.4
Welfare
Arrangements
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 400
Project
Organization
Chart
1.6
Arrangements for
communication
1.7
Project Goals
1.8
HSE Compliance
monitoring
1.9
Senior
Management HSE
monitoring
Inductions &
Trainings
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 401
3.1
Selection of
Contractors
3.2
Selection of Plant
4.1
First Aid
4.2
Fire and
Emergency
Procedures
Contractor to detail what are the fire safety arrangements that will
be available on site. For example:
Fire points How many, where will they be located
What kind of extinguishers will be available
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 402
Accident &
Incident reporting
5.1
Production of
Method
Statements
5.2
Risk Assessments
6.1
Environmental
Management
Strategy
6.2
Waste
Management
Planning
6.3
Environmental
Emergency plans
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 403
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 404
EPC Agreement
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 405
EPC Agreement
2. Participate in monthly Project status review meetings and present the Project progress
update in the meeting. The frequency of Project status review meetings may change based
on actual requirements.
3. Schedule: The Contractor shall submit a Level 3 schedule that covers the full scope of
Contractors work within 30 calendar days of date of appointment. This will be reviewed
within 15 calendar days by Employer/PMNC. The Contractor shall incorporate the
comments and resubmit the schedule no later than 15 calendar days after receiving the
comments from Employer/ PMNC. Upon approval the level 3 schedule will become the
baseline schedule for all the future monitoring and tracking.
The Contractor should keep to the following guidelines
i)
ii)
iii)
All schedules shall follow the Critical Path Method (CPM) of scheduling and
shall have meaningful and realistic logical ties and relationships between
activities.
iv)
The use of negative lags is not permitted in the baseline and all other versions of
the schedule.
v)
The schedule must contain all the long lead procurement items identified.
vi)
vii)
Upon approval, the copy of the Baseline schedule will become the first
Current Schedule.
viii)
The Current schedule shall be actively updated and maintained by the Contractor
every month.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 406
EPC Agreement
ix)
x)
xi)
The contractor should also submit a level 4 schedule within 60 calendar days
from approval of baseline level 3 schedules.
xii)
4. Cash Flow: Prepare Project cash flow at the start of the Project. Prepare monthly
statements to show the actual versus plan spending; update the cost periodically
5. Lessons Learned Database: The Contractor shall develop and actively maintain a
lessons learned database on a monthly basis (to be included in the monthly Project
report) and submit it to Employer/ PMNC at the end of the Project during closeout.
6. Risk Register: Maintain an active risk register addressing the risks and mitigation measures
(could be in excel format) that lists the Project risks related to their Scope of Work.
7. Inter-Project Links: Identify potential inter-Project links, inter-dependencies or conflicts/
interference to work or work areas and narrate them in the monthly progress report.
8. Monthly Progress Report: Prepare and submit a monthly progress report (standard
format and template will be provided by Employer /PMNC at a later date). Items 3 to 7
mentioned above shall be the minimum information that will need to be included in the
monthly progress report.
9. For better collaboration, Contractor shall use the Programme and Document Management
system that will be provided by Employer/PMNC at a later date and pay for the cost of
procuring licenses to use the system.
Monthly payments are subject to timely submission of monthly progress report and the
monthly updated electronic schedule file in the required and acceptable format.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 407
EPC Agreement
Note: The Phasing shown is indicative only. EPC contractor to develop Phasing
considering optimization of available Site access and prevailing Site conditions in
coordination with the Stake holders.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 408
EPC Agreement
1.
Aerial photography
1.1.
Aerial images need to be taken maintaining a GSD (Ground Sample Distance) GSD
of ~3cm to ~5cm per pixel or better. Necessary pre-marking or post marking of
ground control points are required for precise geo-referencing of the images. It is
required that each GCP (Ground Control Point) is clearly identifiable in the aerial
image after processing.
1.2.
1.3.
Identification and marking of GCP on the Site before processing the aerial
imageries. Minimum number of GCP should not be less than 20-25 for any
village settlement.
Existing fine resolution DEM data can be use or create the new DEM using
break lines and mass points is used along with camera the same data can be used
for undertaking ortho rectification of image data.
Ensure uniform pixel resolution across RGB and panchromatic bands if all
the bands are used in the data acquisition.
Perform precisely geo-referencing of image with 20-25 GCP in a village and 712 GCP outside village parcels.
Hardcopy of the ortho images are to be used for field verification of land
parcel and for further correction process as and when required by the client
within the contract period.
Record Visible and identifiable features like but not limited to Buildings,
other structures, including fence, building corners of the enclosed stack flare
station, former power Plant building, fence lines, tanks, major pieces of
stationary equipment, utility poles and visible utilities (manholes, etc.),
stockpiles, edge of roads, trails, paved areas, and gravel areas, grade
breaks/tops and bottoms of slopes and other major Site features.
Flight Frequency
Aerial photography (as described above) shall be perform every Six month or
as directed by the client.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 409
EPC Agreement
1.4.
Imagery Acquisition:
COMPONENTS
DESCRIPTION
Coverage Area
Pixel Size
Flight Height
Not more than 4000 ft. (Shall be consider as per the Site
conditions*)
Accuracy
Camera
Photographic
Conditions
Image Quality
Overlapping
*
1.5.
Height should be considered appropriately (for best result) as per best practices.
Delivery Schedule:
Flight Plans Within 10 days of contract
Orthophotos Within 30 days of acquisition
All Remaining Deliverables Within 60 days of acquisition
1.6.
Deliverables:
Part I - Ground Control Point (GCP) in ESRI GIS format.
Part II - Raw & processed Ariel imagery in GeoTIFF format.
Part III - Geo referencing images in GeoTIFF format.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 410
EPC Agreement
1.7.
Recording Objections:
A register shall be maintained by the consultant to record and track the objections.
The objections should also be flagged in the Digital Topographic Data Base
(DTDB) for better control and monitoring.
The consultant shall assist the Government officers in resolving the objections.
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 411
EPC Agreement
Schedule U Reports
INDEX
DISCLAIMER
1. Geotechnical Investigation Report.
2. Material Investigation Report.
3. Contour Plan of Shendra Industrial Area (Phase-I).
Design and Build the Infrastructure works for Roads, Drains, Culverts, Minor Bridges, Water
Supply, Sewerage, Power systems for Phase-I in Shendra-Bidkin Industrial Area, Aurangabad,
Maharashtra on EPC Basis (Package I)
Page 412