Sei sulla pagina 1di 8

Installation of Power Transformer

Power transformer is second most costly equipment installed in power


system. Hence, special care to be taken during installation of a new
power transformer in an electrical substation. During accessing the
interior of a power transformer, the worker should empty their pockets of
all loose articles so that there would not be any risk of falling anything
inside the transformer from their pocket. The tools used during the work,
should be securely tied with cotton tap so that they can be recovered if
accidentally fall into the transformer interior. Jute should not be used as
cleaning materials for a transformer. Loose fibers of the jute may be
remained even after completing the cleaning work, which may affect the
insulating properties of the equipment in future. Cleaning should be done
by clean cotton cloth without any suspended loose fibers. Generally,
many parts of a power transformer are transported from manufacturers
separately.
All the parts or components dispatched separately should be properly
cleaned from inside and outside before being fitted to the transformer
body. Special attention, to be given if, interior surface of the any
component is found rusty. Transformer oil is also dispatched in separate
sealed steel drums. This oil is highly inflammable hence no flame should
be brought nearer to the transformer oil. Transformer oil and the
cellulose-based insulating material used in transformer, both absorb
moisture easily hence, transformer oil and cellulose-based insulated
parts of the transformer should be handled very carefully. The main body
of power transformer can be supplied by the manufacturer without or
with insulating oil inside it. In both cases it is best practice to circulate
dry and warm oil through it until its temperature is 5C to 10C above
ambient. This should be done before allowing external access to the
interior of the tank. The warm and dry oil should be circulated in the
transformer during all the time the transformer remains open to
atmosphere. The oil pump and all joints in the oil pipe work should be
properly air tight otherwise air will enter in the transformer and get
lodged in the vulnerable places such as winding.

Locations and Site Preparation for Installation of a


Power Transformer
For installation of a power transformer, no special type of foundation
is required. The foundation should be strong enough to carry the heavy
load of transformer and it should be efficiently designed to prevent
accumulation of water below the transformer. It is essential to drain all
the oil coming out from transformer during any fire hazard and hence
special oil drainage facilities should be provided in the foundation design.
This last point is strongly recommended especially for large power
transformer. The foundation should be created in such a place where
easy accessibility can be provided to all indicating and protecting devises.
That means there should be sufficient place all around for proper viewing
of diaphragm plates, thermometers, valves, oil gauges, etc. Sufficient
and minimum standard electrical clearances of all live parts of the
transformer from earth and other live bodies are also to be provided. If
the transformer is of Oil Natural Air Natural (ONAN) type, there should be
sufficient space available all around the transformer for circulating the
air naturally. If the ONAN transformer is indoor type, the room must be
well ventilated. In this case the air inlets and outlets should be of
sufficient size and number. Air inlets of the room must be as nearer the
floor as possible and air outlets must be as high as the building will allow
and this arrangement will facilitate sufficient and efficient circulation of
air during natural cooling of transformer. Sometime in case of indoor
transformer, exhaust fans are used for forced circulation of air in the
room. Where wheels or rollers are not fitted on the base of the
transformer body, level concrete plinth with bearing plates of sufficient
size and strength can be adopted for outdoor transformer. To prevent
the formation of rust, it is essential to avoid presence of air and water in
the space between the plinth and the base of the transformer by use of
cretex or similar bituminous compounds. Where rollers are fitted on the
base, suitable rails or tracks should be fitted with the foundation to place
and lock the rollers on the rail. Locking of rollers on the rail is essential
because it prevents the accidental movement of transformer during
earth quakes or any similar hazard.

Preparation of Oil during Installation of Transformer

When transformer is dispatched without oil, required entire oil which is


supplied by the manufacturer in separate sealed steel drums. But when
the transformer is dispatched with oil in the main tank, the required oil
for conservator tank, radiators of transformer, and for other essential
parts is dispatched in separate sealed steel drums. Although the oil
supplied by the manufacturer are brand-new but still it is required to be
filtered, cleaned and dried before feeling in the transformer. Filtering
process must be continued until the transformer oil satisfies the

specifications indicated by manufacturer. The parameters of the oil, to be


checked during filter process are generally for electrical strength,
resistivity at 27C, resistivity at 90C, tan delta value at 90C, and
moisture content in ppm. Oil is easily contaminated hence it is important,
when sampling the oil and filling the tank, to keep the oil free from
contamination. All the components used for handling the transformer oil
should be cleaned and flushed with fresh transformer oil before use. For
collecting sample of the oil for the testing purpose, glass containers with
glass stopper is preferable over the metallic container. Cleanliness of the
container is essential because very small amount of moisture can affect
the test results. Never Use wax for sealing the oil sample containers. If
possible, glass stopper is covered by a pack of silica gel tied in a piece of
cloths. Flexible steel hose pipe is preferable for filtering and handling of
insulating oil. Some kind of a specially made synthetic rubber pipe or PVC
pipe can be used as hose but ordinary rubber hose pipe must not be used
in any case as the transformer oil dissolves the sulphur from rubber and
is thereby contaminated. The steel hose used for this purpose must also
be properly cleaned and free from moisture and loose rust.

Oil Filling in Transformer Tank during


Installation
The oil can only be filled in the transformer which satisfies the standard
specifications mentioned by the manufacturer of transformer. When the
transformer is supplied gas filled, the oil filling is done in the main tank
under vacuum. The large transformers are generally designed to
withstand the full vacuum for long periods. During oil filling in the main
tank of the transformer, it is preferable to connect the inlet hose pipe at
the bottom of the tank. After filling the oil up to the top of the
transformer core, maximum suitable vacuum is maintained above the oil
level in the tank to minimize the hazard of bubbles lodging in the
inaccessible corners of winding. It should be noted that condenser
bushing, diaphragm, Buchholz relay, tap changer board, conservator
tank, radiators units etc are not designed for withstanding vacuum hence
they should not be subjected to vacuum. That means vacuum processes
only to be done in main tank without connecting or with blocking all the
above-mentioned components of the transformer.

Drying out Power Transformer using Streamlined Filter


Machine

The most common process of drying out a power transformer is by using


a streamlined filter machine connected across the inlet and outlet oil
hose. The vacuum chamber and oil heater incorporated in the filter
machine are mainly utilised for this purpose. Before using the filter
machine it should be ensured that the oil previously filled in the machine,
must be drained out and the machine is refilled with the transformer oil

supplied by the manufacturer. This oil first circulated inside the machine
itself for several times and tested again and again for achieving required
result. If the required result is achieved then the machine should be
connected across inlets and outlet hose of the transformer and the entire
oil should be circulated through the transformer and filter machine
several times and the oil sample is to be tested during a specified interval
normally after each one hour. The vacuum pump of the filter machine
should have the capacity of creating vacuum as high as possible, but not
less than 710 mm of mercury. Where possible, an additional vacuum
pump can be connected at the top cover of the tank to keep the oil in the
tank under vacuum consistently. This additional vacuum pump may
accelerate the drying out process of the transformer. Although, the oil
was filled in the transformer under vacuum from the bottom of the tank,
but during drying out process oil is drawn out from the bottom and fed
into the top of the transformer tank. This helps to remove any settled
moisture/impurities remain in the oil. The oil circulation in that direction
must be continued about 8 to 12 hours and then the cycle is reversed i.e.
oil is drawn from the top and fed in the bottom of the tank. During this
process the oil must not be heated beyond 85C in the machine and the
temperature of the oil inside the transformer tank should not exceed
75C. If this maximum allowable temperature limit is not maintained,
the oil may be decomposed due to higher temperature operation. The
process of drying out is continued until the satisfactory insulation
resistance value is achieved. The insulation resistance or I R value of the
oil mainly depends upon its moisture content hence, by analyzing the I R
value, the moisture content in the oil can be predicted. The I R values of
the oil taken in a regular interval (at the interval of one hour) are plotted
against time. It should be observed from the graph that initially the I R
value drops down and this I R value will be low till the moisture is present
inside. Once the entire moisture is removed from the oil, as well as
interior of the transformer, the I R value again goes up and becomes
steady. Initially insulation resistance value came down because the
moisture contained in the core and winding of the transformer were
removing in the hot oil thereby moisture content of the oil was increased.
After, this moisture removed from the oil in the filter machine, the
insulation resistance value of the oil became again high and steady. The
I R values taken at regular intervals as should also be plotted against
temperature readings. In the beginning, I R values drop down as the
temperature goes up. The I R value will be low till the moisture is present
inside. Once the moisture is removed, the IR value will start rising and
then becomes steady. In addition to the drying out process by filter
machine, the transformer can also be heated up by short-circuiting the
LV winding and supplying a reduced voltage at the high voltage terminals.
The value of the applied voltage is so maintained that the current

through the short-circuited winding should be under 70% of the rated


current. It must also be of observed during heating up the transformer
winding by applying reduced voltage, the temperature of the oil must not
exceed 75C. At the same time temperature of the winding must not
exceed 90C.

Gaskets and Gasket Joints


Transformer gasket are neoprene bonded, cork gasket. The gaskets are
supplied loosely by the manufacturer without any bolt holes created on
them. The gaskets are usually cut to the size and shape and punched for
the holes at site. Joints in the gasket should be located away from the
corner and bold holes. Before using, the gasket must be checked for their
proper flexibility and free from local thickening. Neoprene solution is
used as adhesive for joints in the gasket. After fitting the gasket the bolts
are typed in sequence, a little every time so that uniform pressure is
exerted on the gasket until the gasket is compressed to about 2/3 of its
original thickness.

Fitting and Fixing Bushings of Transformer

Before fitting the bushings on the transformer, they should be checked


for any damage or crack. If they are all right, these should be cleaned by
dry cotton cloth. Bushings are normally delivered in complete assembled
form. When clamping the bushing to the tank, care should be taken to
ensure that an even pressure is obtained to the flange of the porcelain
and its gasket by tightening the diagonally opposite nuts alternatively.
The power connection at the stud of the bushing should be flexible
enough to absorb any vibration. If arcing horns are supplied with the
bushing they must be fitted and the gap between the horns must be
adjusted as per the drawing supplied with the transformer.

Installation of Conservator Tank

Conservator tank, where fitted should be assembled with its pipe work,
etc, making sure that SKATED joints are oil tight and the pipe work is
clean and free from moisture. The mechanism of the float type oil gauge
inside the conservator is locked to prevent damage during transit. After
placing the conservator in position, it should be released by turning the
locking bolt in the direction indicated on the plate. While feeling the
conservator with transformer oil, it should be ensured that the oil filled
up to the level indicated by the oil gauge on the conservator. On the oil
gauges dial there is an indication of temperature, this tells the
prescribed level of oil in the conservator at that temperature. For
example, if 30C is indicated in oil gauges dial, the oil should be filled in
conservator up to that level when oil temperature is 30C. But during
actual oil filling in conservator tank, we should commensurate with the
oil temperature at that time.

Fittings of Silica Gel Breather


Silica gel breather always comes as loose item. The plastic plug sealing
on the top of the breather should be removed and fitted to the associated
pipe work. The oil cup at the bottom of the breather should be removed,
filled with transformer oil to the level indicated on it and then re fitted to
the position. Thus the silica gel is prevented from absorbing moisture
from atmosphere.

Installation of Explosion Vent


Explosion vent is fitted with suitable gasket. Here care should be taken to
ensure that the top diaphragm with its gasket makes an air tight joint.
The explosion vent is sent blanket from works and the top blanking plate
should not be removed till the oil level inside the transformer comes up
of the tank cover. When a transformer is provided with a Buchholz device,
bottom paper diaphragm which acts as a deflector plate, is fitted at the
base of the explosion vent to ensure that any gases liberated in the
transformer, will pass through the Buchholz relay and not collect in the
vent. A hole in the side permits the oil to enter the vent and equalise the
pressure on either side of the deflector diaphragm. In transformers of
large rating the space above the oil in the vent is usually connected by a
pipe to the top of the conservator to equalise the pressure and vent it to
the atmosphere through the breather. For transformer supplied without
equalising pipe and air cock is fitted at the top which must be opened
when the tank is being filled with the oil and closed again.

Fitting of Buchholz Relay


Buchholz relay is connected across the pipe work between conservator
tank and main tank of the transformer. There is generally a Stop Valve
between Buchholz relay and conservator tank. The Buchholz relay should
be mounted on the pipe work only after the oil level inside the
transformer is above the tank cover. The Buchholz relay is provided with
an arrow marked on its housing and this arrow should always point
towards the conservator. If the gas release pipe is provided, it must be
fitted to the top pocket of the Buchholz relay. In this case the top pockets
of Buchholz relay should be opened and gas release pipes should be full
of oil during normal operation of transformer. When the gas is to be
collected through the gas release pipe, oil will flow out initially followed
by the gas. But when gas release pipe is not provided with Buchholz relay,
the top pockets are generally screwed tightly. During fittings of Buchholz
relay in the pipe work, the relay should be mechanically locked with the
locking screw provided in the relay. It prevents any mechanical damage
inside the relay due to transit. The alarm and trip contacts provided on
the relay should be properly identified from the control drawings of the
relay before connecting the control wires on those terminals of the relay.

The NO contacts for alarm and trip should be checked for their proper
functioning.

Installation of Temperature Indicator

Oil Temperature Indicator (OTI) and Winding Temperature Indicator


(WTI) are fitted in the Marshalling Kiosk. The thermometer bulbs are
enclosed in the pockets on the top cover of the transformer. The
thermometer pockets for OTI and WTI should be filled with transformer
oil during inserting the thermometer bulbs inside them. Both Oil
Temperature Indicator and Winding Temperature Indicator are provided
with maximum pointers and mercury switches. The steel capillary tubes
are normally quite flexible but it should not be bent sharply and
repeatedly and should be supported by clips to prevent unnecessary
sagging. Before installation, the instrument should be checked for proper
calibration by hot and cold oil bath. The mercury switches are adjusted to
make contact at the desired temperature depending upon the site
condition i.e. ambient temperature, loading condition, etc. The Current
Transformers connection of the WTI is made to the thermometer pocket
as per instructions given on the WTI terminal board.

Installation of Cooling Equipment


The radiator units are washed by clean dry oil before fittings to the main
body of the transformer. After fittings the radiators with proper gasket
work, are filled with transformer oil. The air should be released by
loosing air release pocket at the top of the header and also at each
radiator unit. When only the drying out process of main tank is
completed, the interconnecting valves between the tank and the radiator
unit are opened. This is because radiator unit should not be subjected to
the vacuum, applied in the main tank during drying out process. The
cooling fans and oil circulating pumps should also be fitted and proper
wiring should be done according to the cooler control drawings provided
with the transformer.

Fitting of On Load Tap Changer


The tap changer, if dispatched separately, it is to be fitted onto the tank,
The insulation resistance value of each tap changer lead should be
measured and the cause of low values, if any, investigated. The lead
from the tap changer should then be connected to their respective
position on the terminal board provided on the tank. The tightness of all
connections of the selector switch and terminal board should be ensured.
Sometimes it is difficult to get good insulation resistance values if there
is moisture in the tap changer board or on any of the parts of the selector
switch and diverter switch. Then it should be ensured that selector switch
and diverter switch are filled with clean dry processed oil. To remove the
moisture from the terminal board, it is preferable to circulate the

transformer oil in the selector switch tank and main transformer tank
simultaneously and at as high a temperature as permissible. If some
other special instructions are provided, the same should be followed.

Fitting of Off Load Tap Changer


If the transformer is supplied with off load tap changer, it is previously
assembled in the transformer itself. No extra connection to be done
unlike in the case of on load tap changer. In this case only precaution is
maintained and that transformer should be isolated from the system
during changing of tap from one position to other.

Earthing of Transformer
The main tank of the transformer should be effectively earthed at least
more than one point. This is to be noted that the earthing connection
should be of sufficient cross-section to carry the fault current for at least
30 seconds. The fans, oil pumps, neutrals, marshalling kiosk etc. should
also be properly earthed.

Completion of Erection Work for Installation of Power


Transformer

Any other work such as wiring of various alarm/trip contacts from


various accessories of the transformer to marshalling kiosk, settings of
relays, checking of protection scheme, etc. should be completed before
the transformer is cleared for commissioning.

Potrebbero piacerti anche