Sei sulla pagina 1di 22

INCOMING MATERIAL INSPECTION REPORT FOR AAC BLOCKS

SITE :

1) Date Of Receipt :
2) Name of Supplier :
3) Challan No. :
4) Qty on Challan :
5) Ref. P. O. No. :
6) Size of Blocks :
7) Type of Blocks :

8) Check for Dimensions . Is it Acceptable ?


9) Check for Edges & Corners. Is it Acceptable ?
10) Are there any visible signs of efflorescences?
10) Check for Presence of Cracks or Any Flaws. Is it Acceptable ?
11) Check whether the block appears fully cured?
12) Is the Manufacturer's TEST CERTIFICATE for Blocks available ?
13) If the material is tested, mention results:
Compressive Strength Testing Results
Water Absorption Test Results

ACCEPTANCE OF THE MATERIAL BASED ON THE ABOVE INSPECTION REPORT.


If not accepted, then is the material / product suitable for any other works?
If suitable for any other works, then mention work activity & location:

Remarks (if any) :

SIGN. OF QA-QC MANAGER / ENGINEER :

SIGN. OF STORES IN-CHARGE :

ING MATERIAL INSPECTION REPORT FOR AAC BLOCKS


LOCATION :

DATE :

YES

NO

y Flaws. Is it Acceptable ?

CATE for Blocks available ?

ED ON THE ABOVE INSPECTION REPORT.

l / product suitable for any other works?

n mention work activity & location:

O.K.

YES

Not O.K.

NO

N.A.

INCOMING MATERIAL INSPECTION REPORT FOR FINE AGGREGAT


SITE :

1) Date Of Receipt :
2) Name of Supplier :
3) Challan No. :
4) Qty on Challan :
5) Ref. P. O. No. :

6) Check for Presence of Clay Lumps. Is it Acceptable ?


7) Check for Cleanliness of Fine Aggregates. Is it Acceptable ?
8) In case of crushed sand, is the shape of particles cubical?
8) If the material is tested, mention results:
Gradation
Silt Content/ fines content

ACCEPTANCE OF THE MATERIAL BASED ON THE ABOVE INSPECTION REPORT.


If not accepted, then is the material / product suitable for any other works?
If suitable for any other works, then mention work activity & location:

Remarks (if any) :

SIGN. OF QA-QC MANAGER / ENGINEER :

SIGN. OF STORES IN-CHARGE :

G MATERIAL INSPECTION REPORT FOR FINE AGGREGATES


LOCATION :

DATE :

YES

NO

it Acceptable ?

ates. Is it Acceptable ?

of particles cubical?

ED ON THE ABOVE INSPECTION REPORT.

l / product suitable for any other works?

n mention work activity & location:

O.K.

YES

Not O.K.

NO

N.A.

INCOMING MATERIAL INSPECTION REPORT FOR CONSTRUCTION CHE


SITE :

1) Date Of Receipt :
2) Name of Supplier :
3) Challan No. :
4) Qty on Challan :
5) As per P. O. No. :
6) Cateogory of the Chemical :
7) Make & Brand name of the Chemical :

8) Check for Manufacturing & Expiry dates. Is it Acceptable ?


9) Check for Physical damage to containers & Seal. Is it Acceptable ?
10) Check for Manufacturer's TEST CERTIFICATE / PRODUCT
11) Is the MSDS available?

ACCEPTANCE OF THE MATERIAL BASED ON THE ABOVE INSPECTION REPORT.


If not accepted, then is the material / product suitable for any other works?
If suitable for any other works, then mention work activity & location:

Remarks (if any) :

SIGN. OF QA-QC MANAGER / ENGINEER :

SIGN. OF STORES IN-CHARGE :

TERIAL INSPECTION REPORT FOR CONSTRUCTION CHEMICALS


LOCATION :

DATE :

YES

NO

YES

NO

tes. Is it Acceptable ?

ners & Seal. Is it Acceptable ?

TIFICATE / PRODUCT

ED ON THE ABOVE INSPECTION REPORT.

l / product suitable for any other works?

n mention work activity & location:

N.A.

INCOMING MATERIAL INSPECTION REPORT FOR PAINTS


SITE :

1) Date Of Receipt :
2) Name of Supplier :
3) Challan No. :
4) Qty on Challan :
5) As per P. O. No. :
6) Type of Paint :
7) Make of the Paint :

8) Check for Manufacturing & Expiry dates. Is it Acceptable ?


9) Check for Physical damage to containers & Seal. Is it Acceptable ?
10) Shade of Paint. Is it matching with the approved shade ?
11) Check for PRODUCT INFORMATION MANUALS. Is it Available ?
12) Is the Manufacturer Test Certificate available ?
13) Is the MSDS available?
ACCEPTANCE OF THE MATERIAL BASED ON THE ABOVE INSPECTION REPORT.
If not accepted, then is the material / product suitable for any other works?
If suitable for any other works, then mention work activity & location:

Remarks (if any) :

SIGN. OF QA-QC MANAGER / ENGINEER :

SIGN. OF STORES IN-CHARGE :

OMING MATERIAL INSPECTION REPORT FOR PAINTS


LOCATION :

DATE :

YES

NO

YES

NO

tes. Is it Acceptable ?

ners & Seal. Is it Acceptable ?

he approved shade ?

MANUALS. Is it Available ?

available ?

ED ON THE ABOVE INSPECTION REPORT.

l / product suitable for any other works?

n mention work activity & location:

N.A.

INCOMING MATERIAL INSPECTION REPORT FOR HARDWARE / IRONMO


SITE :

1) Date Of Receipt :
2) Name of Supplier :
3) Challan No. :
4) Qty on Challan :
5) As per P. O. No. :
6) Type of Item :
7) Make :

8) Is the item matching with the catalogue description / approved sample ?


9) Check for uniformity and free from any damage in finishes of the Iron Mongery. Is it Acceptable ?

ACCEPTANCE OF THE MATERIAL BASED ON THE ABOVE INSPECTION REPORT.


If not accepted, then is the material / product suitable for any other works?
If suitable for any other works, then mention work activity & location:

Remarks (if any) :

SIGN. OF QA-QC MANAGER / ENGINEER :

SIGN. OF STORES IN-CHARGE :

ERIAL INSPECTION REPORT FOR HARDWARE / IRONMONGERY


LOCATION :

DATE :

YES

NO

YES

NO

gue description / approved sample ?

ny damage in finishes of the Iron Mongery. Is it Acceptable ?

ED ON THE ABOVE INSPECTION REPORT.

l / product suitable for any other works?

n mention work activity & location:

N/A

INCOMING MATERIAL INSPECTION REPORT FOR WATER SUPPLY & SANIT


SITE :

1) Date Of Receipt :
2) Name of Supplier :
3) Challan No. :
4) Qty on Challan :
5) As per P. O. No. :
6) Type of Item :
7) Make :

8) Is the item matching with the catalogue description / approved sample ?


9) Is it free from any physical damage?
10) Check for Uniformity in Finishes. Is it Acceptable ?
11) Check for Class or Grade of the item. Is it Acceptable ?

ACCEPTANCE OF THE MATERIAL BASED ON THE ABOVE INSPECTION REPORT.


If not accepted, then is the material / product suitable for any other works?
If suitable for any other works, then mention work activity & location:

Remarks (if any) :

SIGN. OF QA-QC MANAGER / ENGINEER :

SIGN. OF STORES IN-CHARGE :

IAL INSPECTION REPORT FOR WATER SUPPLY & SANITARY ITEMS


LOCATION :

DATE :

YES

NO

YES

NO

gue description / approved sample ?

it Acceptable ?

m. Is it Acceptable ?

ED ON THE ABOVE INSPECTION REPORT.

l / product suitable for any other works?

n mention work activity & location:

N/A