Sei sulla pagina 1di 138

WESTERN LIBYA GAS

PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
COMPANY DOC. No:
CPECC DOC. No:

CPECC

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 0 OF 119

LIBYAN BRANCH

WESTERN LIBYA GAS PROJECT


ONSHORE PIPELINES
CONTRACT NO. 0142/WA/02

PIPELINE SYSTEM MAINTENANCE PROCEDURE

Company Doc. No.

C-70-C-G-0007-00

CPECC Doc. No.

WLGP-OG-M-CM-MU-0007

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
CPECC

A1
REV

COMPANY DOC. No:


CPECC DOC. No:

08 April 2004
DATE

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 1 OF 119

ISSUED FOR DESIGN


STATUS

Li Shugen

Liu Yan

Zhang Guohua

PREPARED

CHECKED

APPROVED

COMPANY

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES
C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0007

REV. No: A1

PAGE 2 OF119

INDEX
1

GENERAL..................................................................................................................

1.1

Scope...........................................................................................................................

1.2

Purpose of this document.........................................................................................

1.3

Reference....................................................................................................................

1.4

Abbreviations and definitions..................................................................................

1.5

Project description....................................................................................................

PREVENTIVE MAINTENANCE..............................................................................

2.1

Schedule based maintenance....................................................................................

2.2

Predictive maintenance.............................................................................................

MAIN EQUIPMENT INVENTORY..........................................................................

MAINTENANCE ROUTINES OF MECHANICAL EQUIPMENT.......................10

4.1

Maintenance of Tormene ball valve.......................................................................10

4.2

Maintenance of gate valve......................................................................................17

4.3

Maintenance of globe valve....................................................................................18

4.4

Maintenance of check valve...................................................................................19

4.5

Maintenance of safety relief valve.........................................................................20

4.6

Maintenance of launcher and receiver trap..........................................................22

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES
C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 3 OF 119

MAINTENANCE PROCEDURE OF ELECTRICAL EQUIPMENT.....................25

5.1

Maintenance of Electric ball valve........................................................................25

5.2

Solar power unit maintenance...............................................................................29

5.3

Maintenance of cathodic protection system..........................................................34

5.4

Maintenance of Diesel generator...........................................................................37

MAINTENANCE PROCEDURE OF INSTRUMENT EQUIPMENT....................42

6.1

Maintenance of gas over oil ball valve..................................................................42

6.2

Maintenance of liquid level transmitter................................................................49

6.3

Maintenance of liquid level switch........................................................................51

6.4

Maintenance of flow switch....................................................................................52

6.5

Maintenance of magnetic liquid level indicators..................................................53

6.6

Maintenance of fire alarm system.........................................................................54

6.7

Maintenance of burner system...............................................................................56

6.8

Maintenance of pressure transmitter....................................................................57

6.9

Maintenance of differential pressure transmitter................................................58

6.10

Maintenance of temperature transmitter.............................................................58

6.11

Maintenance of flow meter.....................................................................................58

6.12

Maintenance of differential pressure switch.........................................................58

6.13

Maintenance of control valve.................................................................................58

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES
C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 4 OF 119

6.14

Maintenance of RTU...............................................................................................67

MAINTENANCE AND CHECK-UP OF PIPELINE...............................................92

7.1

Maintenance of pipeline..........................................................................................92

7.2

Monitoring of pipeline from dispatching center..................................................93

7.3

Pipeline inspection...................................................................................................94

7.4

Check up and maintenance of pipeline systems...................................................94

SPARE PARTS..........................................................................................................96

8.1

Manual ball valve....................................................................................................96

8.2

Gate valves...............................................................................................................98

8.3

Globe valves.............................................................................................................98

8.4

Check valve..............................................................................................................98

8.5

Safety relief valves...................................................................................................99

8.6

Launcher and receiver..........................................................................................100

8.7

Electric actuator valves........................................................................................101

8.8

Solar panel system.................................................................................................102

8.9

Cathodic protection system..................................................................................103

8.10

Diesel generator.....................................................................................................106

8.11

Gas over oil actuator.............................................................................................107

8.12

Liquid level transmitter........................................................................................110

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES
C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 5 OF 119

8.13

Liquid level switch.................................................................................................110

8.14

Flow switch.............................................................................................................110

8.15

Liquid level indicator............................................................................................110

8.16

Fire alarm system..................................................................................................111

8.17

Burner system........................................................................................................112

8.18

Pressure transmitter..............................................................................................113

8.19

Differential pressure transmitter.........................................................................114

8.20

Temperature transmitter......................................................................................115

8.21

Flow meter.............................................................................................................116

8.22

Differential pressure switch..................................................................................116

8.23

Control valve..........................................................................................................116

8.24

RTU.........................................................................................................................116

8.25

Pipeline...................................................................................................................117

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
COMPANY DOC. No:
CPECC DOC. No:

CPECC

1.1

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 6 OF 119

GENERAL

Scope
This procedure provides the unit(s) maintenance strategy and the most cost effective
programmer in order to maintain the inherent safety and operational design properties for
Wafa - Millitah Onshore Pipelines (32 gas pipeline and 16 oil pipeline) Western Libya
Gas Project.

1.2

Purpose of this document


The purpose of this document is to enable AGIP GAS to have the pipeline and equipment
database, including preventive maintenance specifications and spare parts data and to
manage the maintenance activities of the pipeline under routinely conditions.

1.3

Reference
1.3.1

Company document

T-70-G-Z-000100-A2

Operating and Maintenance Philosophy Onshore

T-70-P-Z-000400-A1

Contents of Maintenance Manuals for Onshore Pipeline

T-70-S-Z-000200-A1

Pre-commissioning and Commissioning Guidelines

T-70-P-E-000200-A1

Contents of Pre-commissioning Manuals for Pipeline

T-70-P-Z-000300-A1

Contents of Operating and Safety Manuals for Onshore


Pipeline

LIBYAN BRANCH
COMPANY DOC. No:
CPECC DOC. No:

CPECC

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES
C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

1.3.2

1.4

REV. No: A2

PAGE 7 OF 119

Project documents

C-70-D-O-1016-01

Gas Pipeline WAFA C.P. Launching Pig Trap Process &


Instrument Diagram

C-70-D-O-1016-02

Gas Pipeline 1 Interm. Pig Trap Station Process &


Instrument Diagram

C-70-D-O-1016-03

Gas Pipeline 2 Interm. Pig Trap Station Process &


Instrument Diagram

C-70-D-O-1016-04

Gas Pipeline MELLITAH Receiving Pig Trap Process &


Instrument Diagram

C-70-D-O-1016-05

Gas Pipeline Typical for Line Valve Station Process &


Instrument Diagram

C-70-D-O-1017-01

Oil Pipeline WAFA C.P. Launching Pig Trap Process &


Instrument Diagram

C-70-D-O-1016-02

Oil Pipeline 1 Interm. Pig Trap Station Process &


Instrument Diagram

C-70-D-O-1016-03

Oil Pipeline 2 Interm. Pig Trap Station Process &


Instrument Diagram

C-70-D-O-1016-04

Oil Pipeline MELLITAH Receiving Pig Trap Process &


Instrument Diagram

C-70-D-O-1016-05

Oil Pipeline Typical for Line Valve Station Process &


Instrument Diagram

Abbreviations and definitions


1.4.1
BSCM/Y

Abbreviations
Billion of std. cubic meters per year

LIBYAN BRANCH
COMPANY DOC. No:
CPECC DOC. No:

CPECC

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

BPD

Barrels per day

ROW

Right of Way

MOV

Motorized Valve with Electrical Actuator

1.4.2

1.5

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES
PAGE 8 OF 119

Definitions

COMPANY:

is AGIP GAS BV or any third Parties assigned by


Company.

CONTRACTOR:

is CPECC, which carries out the Engineering


Procurement and Construction of the Project.

Project description
The Western Libya Gas Project (WLGP) entails developing two reservoirs, the former
(Wafa field) located in an onshore desert area 500 Km. from the Mediterranean coast, the
latter (NC-41 block) located offshore and covering an area between 30 and 350 Km. from
the Libyan coast in water depth ranging from 70 to 350 m.
Production from both fields will sum up to 11.1 BSCM/Y (inclusive 11% swing factor) of
sales gas, 60,600/39,000 SBPD of stabilized oil/condensate, 15,000 SBPD of liquid
propane, 13,000 SBPD of liquid butane and 530 t/day of liquid sulfur.
Due to the complexity of the installation as well as their geographic location, the Project
will be realized in various phases and assigned to first class Contractors for their
implementation.
At the completion of the overall Project, the facilities will represent a state-of-the-art design
encompassing high international standards for best technology, operation and
environmental protection.
Two pipelines, 32 gas and 16 liquid, are to be provided for the transportation of the
intermediate products from Wafa Desert Plant to Coastal Plant. The pipelines are buried
along the overall track, 527 Km. long.
The pipes are of API 5L x 65 with adequate thickness according to the adequate condition
and safety rules. The pipes are protected with polyethylene coating with thickness in
accordance with codes standards.

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES
C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 9 OF 119

Field joint will be coated using Heat shrinkable sleeve sheet suitable for the polyethylene
coating.
The pipeline has been divided in three sections, with intermediate scraper trap station, with
the scope to obtain easy pigging operations.
N 16 line valve station with line block valve on each line have been provided.
The valves are pneumatic activated, by the same gas transported in the 32 line, and
provided by remote control.
N10 Cathodic Protection Stations (1 at Wafa and 9 along the pipeline) have been provided
to protect the line against corrosion.
The Cathodic Protection stations along the pipelines are positioned in the same site of the
line valve or scraper trap stations. Telecommunication antennas masts shall be installed
along pipelines route.
Line valve stations, Cathodic Protection Statures and scraper traps station are electrical
powered by solar unit, excluding the stations located at the starting and ending points of the
pipeline.

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
COMPANY DOC. No:
CPECC DOC. No:

CPECC

2
2.1

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 10 OF 119

PREVENTIVE MAINTENANCE
Schedule based maintenance
A scheduled maintenance is required in which regular servicing of equipment is scheduled.
The criteria for this schedule are:
Statutory inspection requirements (i.e. pressure vessels, pressure safety valves, boilers,
lifting appliance, safety equipment);
Vendors recommendations;

Knowledge & experience of Maintenance and Production Staff.


2.2

Predictive maintenance
It needs a large number of measuring instruments for predictive maintenance. We dont
have such kind of measuring instruments. We cant do predictive maintenance. However
we can do some judgment from the readings of instruments on the DCS console. If we find
some errors of reading that deviate from normal reading we can correct it by modify the
curve of the instrument inside the computer database instead of calibrate the instrument.

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
COMPANY DOC. No:
CPECC DOC. No:

CPECC

REV. No: A2

PAGE 11 OF 119

MAIN EQUIPMENT INVENTORY


Description

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

Manual ball valve

Qt.
873

Location
A

EC

Period (months)

Vendor

TORMENE GAS
TECHNOLOGY
S.P.A.

Gate valve

73

Globe valve

101

Check valve

83

Safety relief valve

16

Launcher and receiver

12

EC

12

LVF

LVF

LVF

AST

12

GROUPE

EC

trap
7

Electric actuator ball

GENOVER
12

24

BIFFI

NAPS

valve
8

Solar power system

18

Cathodic protection

10

EC

EC

system
10

Diesel generator

EC

CATERPILLAR

11

Gas over oil actuator

73

EC

GROVE

ball valve
12

Liquid level

&LEDEEN
4

MAGNETROL

MAGNETROL

transmitter
13

Liquid level switch

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
CPECC

14

COMPANY DOC. No:


CPECC DOC. No:

Flow switch

Description

Qt.

15

Liquid level indicator

16

Fire alarm system

20

17

Burner system

18

Pressure transmitter

19

Differential pressure

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

C
Location

PAGE 12 OF 119

MAGNETROL

Period (months)

Vendor

MAGNETROL

12

CHUBB

SAMIA

46

EC

ROSEMOUNT

EC

ROSEMOUNT

EC

ROSEMOUNT

40

EC

transmitter
20

Temperature

44

transmitter
21

Flow meter

22

Differential pressure

28

6
B

switch
23

Control valve

SEVERN
GLOCON

24

RTU

20

25

Pipeline

Note: A: WAFA launching area


B: PTS1
C: PTS2
D: MELLITAH receiving area
EC: LVS with cathodic protection

EC

6
1

ABB

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES
C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

E: LVS without cathodic protection

REV. No: A2

PAGE 13 OF 119

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
COMPANY DOC. No:
CPECC DOC. No:

CPECC

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

MAINTENANCE ROUTINES OF MECHANICAL EQUIPMENT


Visual and aural checks;

Cleaning of equipment;

Leak checks and tightening up to prevent leaks;

Oil level checks, adding oil;

Checking cleanliness of filters.

PAGE 14 OF 108

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
COMPANY DOC. No:
CPECC DOC. No:

CPECC

4.1

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

Maintenance of Tormene ball valve

Fig 1.1TORMENE ball valve

REV. No: A2

PAGE 15 OF 119

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 16 OF 119

Fig 1.2 TORMENE ball valve


Good operation procedure requires periodic control to ensure the correct functioning of the
valve. The frequency of these controls has to be established in relation to the type of
service.
Two main points must be observed:
-

STEM LEAKAGE

Stem leakage could occur if O rings have been damaged.


On this type of valve, no repair is allowed with valve in pressure.

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 17 OF 119

SEAT LEAKAGE

In order to check the proper sealing action of the seat, put the valve in closed position and
bleed it through an appropriate connection downstream.
No leakage should occur after the body cavity pressure are stabilized. In case of leakage of
one of the seats, the valve will not seal properly in both directions.
When you discover that a seal fails, ensure you have the suitable spare parts in stock to
prevent any further damages.
4.1.1

Type TE valve

4.1.1.1 Disassembly
Before dissembling the valve, ensure you have the relevant spare parts available.
Observe carefully the instructions in the PRECAUTIONS section.
1) Remove the valve with its actuator from the pipeline then operate the valve to remove
all flow media in the cavity.
If the valve is in the open or closed position, use the vent/drain plug to depressurize
body cavity. Dont turn drain vent plug more than 1 turn until bleeding occurs through
the plughole.
2) Disassemble the actuator from the coupling flange following the instructions given by
the actuator manufacturer.
3) Leave the ball in full open position.
4) Remove top flange.
5) Remove the bonnet flange after un-tightening the bonnet bolts.
6) Lift the bonnet using lugs in threaded holes.
7) Remove all bonnet gaskets.
8) Using jacks according to dwg SK2.000 pull apart seat thrust ring from the seat

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 18 OF 119

9) Place the ball in the fully open position.


10) Pull the ball out of the body with the seats.
11) Release jacks.
12) Take seat thrust rings out of the body
After having inspected all items and replaced the fault ones, clean down all parts for
assembly. All O rings, must be replaced.
4.1.1.2 Assembly
A good lubricant should be applied on seats, ball and stem.
1) Insert spring holders with springs into each seat pocket.
2) Insert seat thrust ring into seat pocket after having fitted both gaskets in place.
3) Using jacks in accordance with dwg SK2.000 pull both seat thrust ring into seat pockets.
4) Place the seats around the ball bore and side them down in the direction of the lower
trunnion until they form an angle of 15/20 with the stem axis.
5) Push ball and stem into the body maintaining the ball in the open position until both ball
and seats are correctly installed.
6) Release the jacks and take them out of valve.
7) Install the bonnet with its gaskets.
8) Tighten the bonnet bolts using torque valves provided in table 1
TABLE 1
BOLT SIZE

TORQUE

Diam. mm

Nm

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

10

55

12

95

14

150

16

230

20

450

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 19 OF 119

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES
C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

4.1.2
from ball

REV. No: A2

PAGE 20 OF 119

Type TA valve with stem separate

Fig 2 TORMENE ball valve


4.1.2.1 Disassembly
Before dissembling the valve, ensure you have the relevant spare parts available.
Observe carefully the instructions in the PRECAUTIONS section.

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 21 OF 119

1) Remove the valve with its actuator from the pipeline then operate the valve to remove
all flow media in the cavity.
If the valve is in the open or closed position, use the vent/drain plug to depressurize
body cavity. Dont turn drain vent plug more than 1 turn until bleeding occurs through
the plug hole.
2) Disassemble the actuator from the coupling flange following the instructions given by
the actuator manufacturer.
3) Leave the ball in the closed position.
4) Remove top flange.
5) Remove the bonnet flange after un-tightening the bonnet bolts.
6) Lift the bonnet using lugs in threaded holes.
7) Remove all bonnet gaskets.
8) With the ball in the closed position insert the jacks (dwg SK1.000) into the set clamps. It
is necessary to reduce the width of the jacks to the minimum, insert them in the space
between the opening of the ball and the body and release them again to a length suitable
to clamp the seats.
9) After clamping the seats the jacks shall be tightened in order to pull the seats against the
ball.
10) Continue to pull seats against the ball until a gap of 1-2 mm is achieved between the
spring holder and the spacer chain
11) The spacer chain can be removed from around the seats pulling them out and lifting
each segment as it become free.
12) Turn the jacks vice-versa and push seats completely inwards inside the body
13) Install the seats clamp (dwg SK2.000)
14) Release the jacks until they can be removed from the seats clamps and taken out to the
valve body.

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES
C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 22 OF 119

15) Turn the ball into fully open position.


16) Lift the ball out of the body using the appropriate screw holes on the top trunnion.
While doing so avoid contact between the ball and the seats or the body as it lifted and
becomes free
17) Use the jacks to pull the seats out of the valve body with a similar operation used before.
18) When the seats are sufficiently pulled out the seats are no longer subject to the springs
force. When the seat O ring clears the body pocket the jacks can be disengaged,; when
provided, user the special equipment described in par. 8 (ref. ART 133/M) to extract the
seats from the body.
19) Lift each seat using the proper lifting tool (dwg SK 4.000)
After having inspected all items and replaced the fault ones, clean down all parts for
assembly. All O rings, must be replaced.
4.1.2.2 Assembly
A good lubricant should be applied on seats, ball and stem.
1) Insert each seat in the body pocket using the proper lifting tool (dwg SK 4.000) or the
special equipment described on par. 8 (ref. ART 133/M) when provided, until the seat
O rings start to engage into the body.
2) Using the jacks pull completely the seat into they pocket and install the seat clamp (dwg
SK 2.000)
3) Take the jacks out of the body
4) Insert the ball in the fully open position between the seats taking care not to scratch the
ball surface in doing so.
5) Turn the ball in the fully closed position
6) Insert the jacks on the seats and remove the seat clamps
7) Use the jacks to pull the seats against the ball.

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
COMPANY DOC. No:
CPECC DOC. No:

CPECC

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 23 OF 119

8) When a sufficient space of 1-2 mm between the spring holder and spacer chain is
achieved, insert the spacer chain in both seats.
9) Release the jacks and take them out of the valve.
10) Assemble the bonnet with the stem and the top flange.
11) Install the complete bonnet until on the valve body.
12) Tighten the bonnet bolts using torque valves provided in table 1

4.2

Maintenance of gate valve

Fig 3 Gate valve


1)
2)
3)
4)
5)

Clean all metallic parts using petrol or similar products;


Replace all the o-rings when valve is leaking;
Periodic filling grease to stem and gate;
Periodic maintenance of gear box, include greasing and cleaning;
Sealant when leaking;

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
COMPANY DOC. No:
CPECC DOC. No:

CPECC

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 24 OF 119

6) Periodic draining foul water.


4.3

Maintenance of globe valve

Fig 4 Globe valve


1)

2)

Dust, grease and medium residual trend to accumulate at the surface of body, stem
shall be cleaned frequently.
The sealing surfaces and packing shall be checked every three months.

3)

It is forbidden to open the bonnet or replace the bolt, nut or packing when the valve
contains pressure. After replacement of packing, gasket, bolt and nut, valve shall be
closure test prior to reuse.

4)

It is not recommended for reparation of valve pressure-containing part. User shall


replace the valve with a new one.

5)

Welding repair on valve online is forbidden.

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
COMPANY DOC. No:
CPECC DOC. No:

CPECC

4.4

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 25 OF 119

Maintenance of check valve

Fig 5 Check valve

Fig 6 Check valve


1) The sealing surfaces shall be checked every three months.
2) It is forbidden to open the bonnet or replace the bolt, nut or packing when the valve
contains pressure. After replacement of gasket, bolt and nut, valve shall be closure test
prior to reuse.
3) It is not recommended for reparation of valve pressure-containing part. User shall
replace the valve with a new one.

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES
C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

4) Welding repair on valve online is forbidden.

REV. No: A2

PAGE 26 OF 119

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
COMPANY DOC. No:
CPECC DOC. No:

CPECC

4.5

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

Maintenance of safety relief valve

Fig 7 Safety relief valve

REV. No: A2

PAGE 27 OF 119

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 28 OF 119

Check that the surfaces of contact between the seat and disc are perfectly mirror
polished. If there is any scratching or pitting, two surfaces should be re-machined on
lathe, and then lapped.
To disassemble the valve, proceed as follows:
1) Remove the cap (27).
2) Mark the adjusting screw (9) position corresponding to the lock nut (10) height so
that this position can be relocated.
3) Back off the adjusting screw lock nut (10).
4) Release the spring by backing-off the adjusting screw (9).
5) Remove the bonnet (2) from the valve body (1) after unscrewing the clamping nuts
(21).
6) Remove the upper spring seat and the lower spring seat (11) from the stem (8).
7) Remove the bottom guide (7) and disc holder (4) from the valve body (1).
8) Unscrew the bellows (25) from the disc (5) holder (4).
9) Remove the disc from the disc holder
10) Back off and remove the clamping screw (12) from the blow down ring.
11) Unscrew the blow down ring in the anti-clockwise direction counting the numbers
of turns.
12) Remove the nozzle (3) from the valve body.
Assembly
To reassemble the valve, carry out the same operations as for disassembly but in the
reverse order, paying attention:
1) To avoid scratching the lapped surfaces of the seat and disc.

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
COMPANY DOC. No:
CPECC DOC. No:

CPECC

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 29 OF 119

2) To carefully clean the valve trim


3) To smear with graphite grease the threaded sections.
4) To check the gaskets, replace them if necessary.

4.6

Maintenance of launcher and receiver trap


4.6.1
closures

Lubrication

for

quick

open

Piping technologies recommends a minimum periodicity of maintenance at least once a


year.
This maintenance will consist in one opening +closing operation.
The greasing operations will consist:
1) To grease the hinge axels.

Fig 8 Quick open closure

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 30 OF 119

2) To oil the flexible segment.

Fig 9 Quick open closure


3) To oil the rotating handle bleed screw (tapping + ORing)
4.6.2

Replacement of sealing ring

1) Clean carefully the sealing ring and the groove.


2) Grease lightly the complete gasket and its corresponding groove (use most preferably light
oil (engine car oil type)).

Fig 10 Sealing ring

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 31 OF 119

3) Install the gasket according to the attached drawing. The position shown is absolutely
necessary. The gasket is of self-energized type.

Fig 11 Sealing ring


4) Place the anti extrusion spring at the back of the sealing ring.

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
COMPANY DOC. No:
CPECC DOC. No:

CPECC

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 32 OF 119

MAINTENANCE PROCEDURE OF ELECTRICAL EQUIPMENT


Visual and aural checks;

Cleaning of equipment;

Oiling (bearings, etc.).


5.1

Maintenance of Electric ball valve


5.1.1

Standard maintenance

Visual inspection for oil leakage or external visible damages is recommended every two
years.
The following check will assure optimum performance:
1) If the stem is external, clean it and lubricate it to prevent damages to the threaded bush.
2) Lubricate the internal components of the coupling block by means of the spherical head
lubricator using suggested greases (see sect. 618/1 chap.D)

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 33 OF 119

Fig 12 Lubrication hole

Fig 13 Lubrication hole

3) Make sure there are no oil leaks from the actuator housing. The oil level should be
approx. 20 mm from the fill plug (see sect. 618/1 chap. D).
4) Check the external parts for possible damage and replace them immediately. If the
window glass is broken, the complete cover must be replaced.

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES
C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 34 OF 119

5) Repaint all area where paint is missing. Remove rust from surfaces and protect with a
rust preventative.
6) Check that all nuts and bolts securing the actuator to the valve are tight. Re-tighten them
if necessary.
7) If battery low warning appears on the display, replace the battery.

5.1.2

Special maintenance

In case actuator failure, please refer to section 618/3 chapter N of BIFFI manual for
possible causes. Spare parts can be required to BIFFI. Please refer to the item number in
section 618/4.
5.1.3

Alkaline battery change

1) Isolate the main power supply to the actuator and all other control voltages.
2) Open the terminal boards cover.

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

Fig 14 change battery


3) Disconnect two wires from the main board.
4) Bring the cover to a safe area.
5) Remove the label.

REV. No: A2

PAGE 35 OF 119

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 36 OF 119

6) Remove the battery cover.


7) Replace the battery.

Fig 15 Change battery


5.1.4

Lubrication for actuator

The actuator is fitted with oil plugs, so that for any assembly on the valve at least one oil

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 37 OF 119

plug is located on top of the housing and one on the bottom.


A spherical head lubricator is fitted on the coupling block for the proper greasing of the
inside thrust or sliding bearings.
The actuator is supplied filled with oil and greased where necessary.
In normal working conditions, the lubricating oil has practically an indefinite life-span. In
case it is necessary to top up to the max oil level, the same type of lubricant should be used.
The lubrication type and manufacture (ambient temperature from -30~85) shall be
shown as following:
Oil type:
1) ISO viscosity grade: VG 150
3) Viscosity: 135~ 165 cSt

Approved oil manufacture:


1) AGIP-BLASIA 150
2) ESSO-SPARTAN EP 150
3) MOBIL-MOBILGEAR 629
4) SHELL-OMALA OIL 150
5) TEXACO-MEROPA LUBRICANT 150
Grease type:
ISO viscosity grade-X1 (EP1)
Approved grease manufacture:
a) AGIP-GR MU/EP1
b) ESSO-BEACON EP1

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
COMPANY DOC. No:
CPECC DOC. No:

CPECC

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

5.1.5
valve

REV. No: A2

PAGE 38 OF 119

Maintenance of GROVE ball

See section 7.1.1


5.2

Solar power unit maintenance


5.2.1
instructions

Solar

array

maintenance

Inspect installation regularly to ensure that structure, modules, and wiring are sound, and
that all hardware is properly tightened.
Broken or otherwise faulty structure parts or modules should be replaced. A module with
broken glass may be an electrical hazard. Do not attempt to clean modules if any faulty
wiring or broken glass exists. Broken glass can also cause injury.
When cleaning modules, the amount of water used should be limited to avoid possibility of
electrical shock. For this reason, directing a solid stream of other cleaning solution at the
module is not recommended.
Inspect Panel Centers varistors regularly. If burnt varistors are found, they must be
replaced.
If you have any reason to suspect that one or more modules are not producing enough, carry
out the electrical tests on the sub-arrays procedure.
A voltmeter is highly recommended for verifying that the system is operating properly and
for checking system components, if necessary, A good quality expanded scale voltmeter
can be wired into the system. If a hand-held voltmeter is used, a digital readout type is
recommended.

5.2.1.1 Maintenance frequency


It is recommended that inspection be made at least annually or more frequently if required,
dependent on field experience.

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 39 OF 119

5.2.1.2 Maintenance procedures


1) Visually inspect the structure to ensure the alignment of all hardware is correct so that
stress or strain is not present on the modules. Adjust as required.
2) Check all mounting hardware for tightness at regular inspection period and correct as
required.
3) Modules may be cleaned with water. If severe soiling is present, also use soap. Cleaning
should be done utilizing non-abrasive methods. If terminals are exposed, water from
cleaning operation can contact them and cause an electrical hazard. Therefore, before
cleaning, inspect and correct any faulty wiring. If glass is broken, do not attempt any
cleaning. A broken or otherwise faulty module should be replaced. When cleaning in
direct sunlight, it is recommended that quantity of water used be limited.

5.2.2

Charge controller maintenance

Charge Controller does not normally need any service. However, it is good to check
regularly the controller function. Measure the battery voltage with the multimeter and
compare the value to the display. If the clamp amp-meter is available measure the currents
and compare the values to the display. If you discover possible controller malfunction
(faulty because of e.g. lightning stroke), the controller card must be changed. In case of the
Charge controller is not working properly, the reserve controller is taking care of charging
control.

5.2.2.1 When changing the card, proceed as follows:


1) Check the state-of-charge (SOC) value in the Service Menu.
2) Switch PV circuit breakers off.
3) Because the load disconnection is not allowed, open LI and MI relay drive
connectors. Load relay will remain closed during the operation.

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES
C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 40 OF 119

Fig 16 Change card of solar panel unit controller


4) Switch the circuit breaker F20 off.
5) Disconnect all other connectors and monitor cable from the controller.
6) Remove the screws (6pcs) holding the card.
7) Take the faulty card away.
8) Fix the new card in its place.
9) Put the correct EPROM (same serial number as in card) to the extractor and push to
the socket in the new card. To reduce danger of static electricity damage to the
EPROM we recommend avoiding clothes made of synthetic materials. Also before
touching the new EPROM you should touch a grounding post in the system to
remove any static electricity. Note the correct polarity of the EPROM.

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 41 OF 119

Fig 17 Change card of solar panel unit controller

10) Reconnect all other connectors except LI and MI relay drive connectors carefully to
their own places on the card.
11) Close the battery back-up jumper and the clock enable jumper.

Fig 18 Change card of solar panel unit controller

12) Switch F20 on.

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 42 OF 119

13) Check the parameters in the service menu. Correct SOC value and set time and
date.
14) Put the load relay drive connectors back on..
15) Turn PV circuit breakers on.

5.2.2.2 In normal operation to start-up controller the following procedure must be followed:
1) Close the fuses in the battery fuse box.
2) Close the battery main switches (S-1) in the controller cabinet.
3) Close the auxiliary circuit breaker (F10) in the controller cabinet.
4) Close the array circuit breakers in the controller cabinet. Check the position in the
main diagram.
5) Close the load circuit breakers in the controller cabinet. Check the position in the
main diagram.

5.2.2.3 When stopping controller, perform this sequence in order 4-3-2-1.


5.2.3

Battery maintenance

CAUTION! Lethal voltages exist permanently across the battery terminals. A battery may
release flammable and explosive gases.
To avoid leakage currents and the associated risk of fire keep the battery dry and cleaning
with clean water, no detergents, no solvents. Avoid electrostatic charges.
5.2.3.1 Measure and list every 6 months
1)

Battery voltage.

2)

Voltage of some cell/blocks (pilot cells).

LIBYAN BRANCH
COMPANY DOC. No:
CPECC DOC. No:

CPECC

3)

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES
C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 43 OF 119

Surface temperature of pilot cells and the room temperature.

5.2.3.2 Every 12 months:


1) Measure and list voltages and surface temperature of all cells/blocks.
2) Check connectors, racks and ventilation.

If the float charge of single cell deviates more than +0.2V or 0.1V from the average value
and if the surface temperature of different cells/blocks deviate more than 3K, you should
call customer service.
5.3

Maintenance of cathodic protection system


5.3.1
installations

Maintenance for sacrificial anode

a) At 3-monthly intervals, measure and record pipeline potentials at


representative measuring points, in particular where potentials are known to be
least negative.
b) At 12-monthly intervals, check and record pipeline potentials at all measuring
points and the current flow in each link.
Visually check all test facilitates for serviceability and damage and carry out
maintenance and repairs as necessary.
5.3.2
current installations

Maintenance

for

impressed

a) At 3-monthly intervals, check for satisfactory operation of T/R and DC-DC


converter, record output voltages and currents and measure pipeline potentials at
the point(s) of application of current, midway between the points of application of
the current, and the extremities of the pipeline being protected by the cathodic
protection system, noting any departures from normal.

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES
C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 44 OF 119

b) At 12-monthly intervals, measure pipeline potentials at all measuring points to


indicate that the required levels of protection are generally being obtained
throughout.
Visually check all test facilitates for serviceability and damage and carry out
maintenance and repairs as necessary.
c) At intervals of 5 years, give consideration to the carrying out a close interval
potential survey.

5.3.3
anode installations

Fault detection for sacrificial

If the potential has become insufficiently negative, an indication of the cause can be
obtained from a current measurement.
a) Current zero or low than expected
1) Wastage of anodes and possible need for replacement.
2) Deterioration of anode/cathode connection, breakage of anode or cables.
3) Drying out of soil around anode.
b) Current level increased:
1) Faulty isolation equipment.
2) Extension of the pipeline.

5.3.4
current installations

Fault detection for impressed

If abnormal values of potential and current are noted, comparison with expected or earlier values
will indicate the nature of the fault as follows.

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 45 OF 119

a) Pipeline potential become more positive as protection system is switch on: This indicates
reversed connections, which is the most serious fault and which could result in severe damage
to the pipeline in a relatively short period.
b)Applied voltage zero or very low, current zero:
1) Failure of power supply fuse or tripping of other protective device.
2) Failure of T/R or DC-DC converter.
c) Applied voltage normal, current low but not zero:
1) Deterioration of anodes or ground beds.
2) Drying out of soil around ground beds.
3) Accumulation of electrolytic produced gas around anodes.
4) Disconnection of some of the connections to individual anodes of a ground bed.
5) Disconnection of part of the pipeline.
d) Applied voltage normal, current zero.
1) Severance of anode or cathode cables.
2) Failure of power supply fuse or ammeter of T/R or DC-DC converter.
3) Complete failure of ground bed or anode system.
e) Applied voltage and current both low
1) Control on T/R or DC-DC converter unit set too low.
2) T/R or DC-DC converter failing
3) Electricity supply faulty.
f) Applied voltage and current both high: Control on T/R or DC-DC converter unit set too high.

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 46 OF 119

g) Applied voltage and current normal but pipeline/electrolyte potential insufficiently negative:
1) Break in continuity bond or increased resistance between point of connection and point
of test;
2) Greatly increased aeration of soil at or near point of test due to drought.
3) Alteration of environment causing rapid depolarization.
4) Faulty isolation equipment of an isolation joint.
5) Protected pipeline shielded by new structures.
6) Failure of cathodic protection system on another part of the same pipeline.
7) Deterioration of protective coatings.
8) Addition to buried pipeline.
9) Interaction from another cathodic protection system.
h) Applied voltage and current normal but pipeline/electrolyte potential abnormally negative:
1) Break in continuity bonding at position further from the point of application than the
point of test.
2) Decreased aeration of soil or electrolyte at point of test.
3) Reduction in rate of flow of electrolyte.
4) Effects of stray a. c. on the structure.
i)

Applied voltage and current normal but pipeline/electrolyte potential


fluctuates: The presence of stray earth current.

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
COMPANY DOC. No:
CPECC DOC. No:

CPECC

5.4

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 47 OF 119

Maintenance of Diesel generator


5.4.1
maintenance

Preparing Diesel generator for

1) On the Diesel generator, turn the RUN/OFF/AUTO switch to the OFF position.
2) Disconnect the battery cables.
5.4.2

Maintenance schedule

8 hours or
every day

250 hours
or
4
months

500 hours
or
12
months

Yes

Yes

Check the amount of water

Yes

Check the drive belt


Yes

Maintenance items

Renew the fuel filter element

Yes

Check the amount of lubricating oil in the sump

Yes

Check the lubricating oil pressure at the gauge


Yes

Renew the lubricating oil

Yes

Renew the canister of the lubricating oil filter

Yes

Empty the dust bowl of the air filter


Yes

Renew the air filter element.

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES
C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

5.4.3

REV. No: A2

PAGE 48 OF 119

How to drain the cooling system

Warning! Do not drain the coolant while the engine is still hot and the system is under pressure
because dangerous coolant can be discharged.
1) Remove the filler cap of the cooling system.

Fig 19.1 Diesel engine


2) Remove the drain plug (fig 19.1) from the side of cylinder block in order to drain the engine.
3) Open the drain plug under the bottom of the trailer.
4) Fit the drain plug and the filler cap.

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

5.4.4

PAGE 49 OF 119

How to adjust the belt tension

Fig 19.2 Diesel engine


1) Loosen the pivot fasteners of the alternator (Fig 19.2 B1) and the adjustment link fasteners
(Fig19.2 B2).
2) Change the position of the alternator to give the correct tension. Tighten the pivot fasteners of
the alternator and the adjustment link fasteners.
3) Check the belt tension again to ensure that it is still correct.

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

5.4.5
fuel filter

REV. No: A2

PAGE 50 OF 119

How to renew the element of the

Fig 19.3 Diesel engine


1) Clean the outside surface of the fuel filter assembly. The drain tap is fitted under the filter bowl.
Drain the fuel from the filter (Fig 19.3 A1).
2) Hold the bottom cover of the filter element and release the setscrew that is fitted through the
filter head above the center of the element (Fig 19.3 B1).
3) Lower the bottom cover of the filter (Fig19.3 B2).
4) Remove the element and discard it.
5) Clean the surfaces of the filter head and of the cover.
6) Renew the seals and lightly lubricate them with clean fuel.
7) Put the bottom cover under the new element and hold the element squarely to the filter head.
Ensure that the element is fitted in the center against the joint in the filter head. With the
assembly in this position, engage and tighten the setscrew.

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES
C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

5.4.6

REV. No: A2

PAGE 51 OF 119

How to renew the lubricating oil

1) Operate the engine until it is warm.


2) Stop the engine, open the sump drain valve and drain lubricating oil from the sump. Close the
sump drain valve.
3) Fill sump to the mark on the dipstick (Fig 19.4 B1) with new and clean oil filter 9API CD
20W50)

Fig 19.4 Diesel engine


5.4.7
lubricating oil filter

How to renew the canister of the

1) Put a tray under the filter to retain spit lubricating oil.


2) Remove the filter canister with a strap wrench. Ensure that the adaptor is secure in the filter
head. Then discard the canister.
3) Clean the filter head.
4) Add clean engine lubricating oil to the new canister. Allow the oil enough time to pass through
the filter element.

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 52 OF 119

5) Lubricate the top of the canister seal with clean engine lubricating oil.
6) Fit the new canister and tighten it by hand only. Do not use a strap wrench.

5.4.8

Air filter

Fig 19.5 Diesel engine


The air filter has an automatic dust valve (Fig 19.5 C1) through which dust is expelled from
the filter. The rubber dust valve must be kept clean. Ensure that the sides of the valves close
completely together and that they can separate freely.
A restriction indicator will indicate precisely when the air filter element needs service.
When the red warning indicator is seen through the clear panel after the engine has
stopped, the air filter element must be removed for service.
After a clean element has been fitted, press the button of the restriction indicator to reset
the red warning indicator.

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
COMPANY DOC. No:
CPECC DOC. No:

CPECC

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 53 OF 119

MAINTENANCE PROCEDURE OF INSTRUMENT EQUIPMENT


Visual and aural checks;

Cleaning of equipment;

Checking of measuring instruments, displays;

Oiling of the rods, screws, etc.;

Testing of display lights.


6.1

Maintenance of gas over oil ball valve


6.1.1

Maintenance of GROVE valve

CAUTION: The line pressure has been kept in the body cavity when closing the valve.
Attention must be paid to unscrewing the drain valve partially and slowly until the pressure
in the body cavity has been discharged.
6.1.2
pressure:
2) Close the valve completely.
3) Slowly unscrew the grease fitting (189).
4) Slowly open the drain connection (39).
WARNING

Drainage

procedure

under

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES
C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 54 OF 119

Open the drain valve slowly until the pressure in the body cavity has been
discharged
5) Remove the drain connection (39) and check its integrity while liquid medium
without residual is discharging. To expedite this operation, remove the drain plug
(39a).
6) Eliminate residual gas inside the valve body by opening the vent plug (172).
7) Mount again the drain connection (39) and (39a) and vent plug (172) after the
complete valve drainage.

Fig 20 Grease injection for GROVE valve


6.1.3

Grease injection procedure

The purpose of grease injection at the stem area is to lubricate and seal the stem. The
purpose of grease injection at the seat area is to isolate the pressure at valve upstream from

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES
C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 55 OF 119

the pressure at valve downstream when the valve is closed. Grease injection should be
performed periodically.
1) Inject lubricant grease on the stem area through the stem grease fitting (189). The stem
area is not subject to the line pressure because of the stem O-rings (134) so it is possible
to use standard grease gun. The grease fitting (189) has a head diameter of 22 mm.
2) The valve is provided with seat grease injection system, inject lubricant grease GROVE
N1 on the seat area through the seat grease fitting (45). The seat area is subject to the
line pressure, so provision should be made for a grease gun with button head fitting in
accordance with the line pressure. The grease fittings (45) have a head diameter of 22
mm. When greasing the seat area, the ball must be either in the fully open or fully
closed position.

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES
C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 56 OF 119

Fig 21 Grease injection for GROVE valve

3) It is temporarily possible to eliminate or reduce eventual leakage through the stem and
through the seat, if grease system is provided, by injecting sealant grease GROVE N2.
This temporary maintenance allows the substitution of any worn and damaged parts to
be postponed until the time of the next planned general maintenance.

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 57 OF 119

When the ball valve need to be disassembly and reassemble if it is necessary, please
following manufacturer maintenance manual.

Every maintenance operation on the actuator must be carried out only after having closed
the pressure taps to prevent undesired operation and enable the operating personnel to work
safely.
6.1.4

Fig 22 dehydrator filter

Start up operation

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES
C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 58 OF 119

1) Substitute the dehydrator filter and remove the condensation accumulated in the lower
part of the container.
2) Check the oil in the tank by means of the measuring rod and, if necessary, add a little oil
(see paragraph Oil tanks balancing). The oil level must correspond to that shown on the 3)
plate fixed to the frame. Excess oil can be drawn off through the drain plugs at the base of
the tanks.
3) Check the correct pneumatic and hydraulic piping seal.
4) Restore the paintwork of the components, which have been damaged during
transportation and assembling after having removed the rust.

6.1.5

Routine maintenance

1) Every 3 months:
a) Remove the accumulated condensation in the dehydrator filter cartridge through the
suitable draining plugs.

2) Every 6 months:
a) Substitute the dehydrator filter.
b) Check the correct valve position signaling on the control panel.
c) Check the status of the filter placed upstream the flow control valves.

3) Every year:
a) Check the lubrication of the scotch yoke and if necessary lubricate with RENOCAL
FN2O or equivalent grease.

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES
C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 59 OF 119

b) Check through the inspection windows that there is no leakage from the stem of the
cylinders.
c) Remove, if any, the condensation in the housing actuating the pressure relief valve
placed on the bottom of the housing.

6.1.6

Extraordinary maintenance

Fig 23 Flange of cylinder

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 60 OF 119

Fig 24 Piston of cylinder


a) In case of leakage from the hydraulic cylinder, disassemble, clean the o-ring grooves
and substitute the o-ring if damaged
b) If there is a leakage from the pneumatic or hydraulic piping, tighten the fitting nuts, or,
if necessary, change them if they are damaged.
c) In case of malfunction or leakage from the pneumatic or hydraulic valves, disassemble
and replace damaged components.
d) Oil tanks balancing

In case the oil contained in one tank is in excess and the oil in the other one is lower it is
possible to reset the right quantity proceeding as follows:
In order to transfer the oil from a gas-oil tank to the other, turn the pump distributor valve
on the by-pass position so to allow the oil passage from the high level oil tank to the other.
The eventual excess of oil can be removed by unscrewing the plug at the lower end of the
same tank

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES
C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

6.1.7
teflon seals

REV. No: A2

PAGE 61 OF 119

Instruction for replacement of

When the seals need to be replaced, it is necessary to check, before assembly, that their
seats are clean and lubricated.
In order to replace the sealing, proceed as follows:
a) Piston seals:
First of all mount the rubber o-ring on the piston, then cover the Teflon glider over the oring by enlarging it with the fingers. The elastic of the glider will recover its original
dimensions after a while.
b) Rod seals:
Insert the rubber o-ring into the groove of the flange first. Then collapse the teflon glider
and insert it inside the flange on the surface of rubber o-ring.

6.1.8
for valves with gas over oil actuators

Hydraulic actuator maintenance

After some time in operation all hydraulic components should be subject to a thorough
overhaul. Depending on the type of system and local conditions of operation the time
interval between such overhauls can vary between 1 and 5 years, but both shorter and longer
periods can be necessary.
The oil should be checked for possible deterioration and contamination and changed if
necessary. Dark-colored, cloudy oil with sediments most likely needs a change. Depending
on conditions, good hydraulic oil can be used between 5000 to 25000 hours. Clean air,
magnet fitters, also the tanks, pumps, pipes and valves. Take care that no dirt enters into the
system during the overhaul. Seals and damaged or worn parts should be replaced when
necessary. Inspect pipe hangers and fittings and replace if necessary.
Call for service assistance if necessary. Before service visit, owner must prepare follows:
system diagram, spars parts, special tools and clean cloths be at hand. Remove screens and
covers and clean the system thoroughly.

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
COMPANY DOC. No:
CPECC DOC. No:

CPECC

6.2

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 62 OF 119

Maintenance of liquid level transmitter


6.2.1

Replacing transmitter PC board

Refer to figure 27 during this procedure.

Fig 25 Liquid level transmitter

1) Remove power from the unit.


2) Remove transmitter-housing cover.
To remove old board:
3) Remove two screws that secure the PC board bracket to the housing base.
4) Remove two wires from TB1 on the PC board.

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 63 OF 119

5) Upplug the LVDT eight pin connector from the socket at J1 on the PC board.
6) Clip the plastic tie wraps which hold the cable to the PC board.
7) Remove the four screws that hold the PC board to the bracket.
8) Remove the c-ring from LVDT using snap ring pliers
9) Carefully remove the transmitter PC board from the transmitter housing.
10) Install new PC board by reversing above steps. Be certain that the red wire is attached
to the (+) terminal at TB1 and the black wire is attached to the (-) terminal at TB1.

6.2.2

Replacing LVDT

1) Remove power from the unit.


2) Remove the transmitter housing cover.
To remove old LVDT
3) Locate the black wire that runs from the top of the LVDT to the lower right hand corner
of the transmitter PC board. Remove the eight pins connector on this wire from J1 on
the PC board.
4) Remove the c-ring above the LVDT on the enclosing tube using a snap ring pliers.
5) Carefully slide the LVDT from the enclosing tube. If necessary, clip the plastic tie wrap
on the transmitter PC board.
6) Install new LVDT by reversing the above steps.
6.2.3
resistance
Refer to figure 26 during this procedure.

Checking

the

LVDT

winding

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES
C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 64 OF 119

Fig 26 Eight pins connector


1) Re move power from the unit.
2) Remove the transmitter housing cover.
3) Locate the black wire that runs from the top of the LVDT to the lower right hand corner
of the transmitter PC board. Remove the eight pins connector on this wire from J1 on
the PC board.
4) Using a multimeter, check the primary winding by verifying that pins 2 and 6 of the
eight pins connector have approximately 78 to 117 ohms resistance.
5) Check the secondary winding by verifying that pins 1and 5 or pins 4 and 8 of the eight
pin connector have approximately 72 to 109 ohms resistance.
6) If the winding resistance is out of range, replace LVDT.

LIBYAN BRANCH
COMPANY DOC. No:
CPECC DOC. No:

CPECC

6.3

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES
C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 65 OF 119

Maintenance of liquid level switch


6.3.1

Keep control clean

Be sure the switch housing cover is always in place on the control. This cover is designed
to keep dust and dirt from interfering with switch mechanism operation. In addition, it
protects against damaging moisture and acts as a safety feature by keeping bare wires and
terminals from being exposed. Should the housing cover or any seals become damaged or
misplaced, obtain a replacement immediately.
6.3.2
terminals, and connections monthly

Inspect

switch

mechanisms,

1) Dry contact switches should be inspected for excessive wear on actuating lever or
misalignment of adjustment screw at point of contact between screw and lever. Such
wear can cause false switch actuating levels. Adjusting switch to compensate (if
possible) or replace the switch.
2) DO NOT operate your control with defective or mal-adjusted switch mechanism (refer
to bulletin on switch mechanisms furnished for service instructions.)
3) Level controls may sometimes be exposed to excessive heat or moisture. Under such
conditions, insulation on electrical wiring may become brittle, eventually breaking or
pealing away. The resulting bare wires can cause short circuits.
Check wiring carefully and replace it at the first sign of brittle insulation.
4) Vibration may sometimes cause terminal screw to work loose. Check all terminal
connections to be certain that screws are tight.
Spare switches should be kept on hand at all times.
6.3.3

What to avoid

1) Never leave switch-housing cover off the control longer than necessary to make routine
inspections.
2) Never place a jumper wire across terminals to cut-out the control. If a jumper is
necessary for test purpose, be certain it is removed before placing control into service.

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
COMPANY DOC. No:
CPECC DOC. No:

CPECC

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 66 OF 119

3) Never attempt to make adjustments or replace switches without reading instructions


carefully. Certain adjustments provided for in level controls should not be attempted in
the field. When in doubt, consult the factory or your local representative.
4) Never use lubricants on pivots of switch mechanisms. A sufficient amount of lubricant
has been applied at the factory to ensure a lifetime of service. Further lubrication is
unnecessary, and will only tend to attract dust and dirt that can interfere with mechanism
operation.

6.4

Maintenance of flow switch


6.4.1

Keep control clean

Be sure the switch housing cover is always in place on the control. This cover is designed
to keep dust and dirt from interfering with switch mechanism operation. In addition, it
protects against damaging moisture and acts as a safety feature by keeping bare wires and
terminals from being exposed. Should the housing cover or any seals become damaged or
misplaced, obtain a replacement immediately.
6.4.2
terminals, and connections monthly

Inspect

switch

mechanisms,

1) Dry contact switches should be inspected for excessive wear on actuating lever or
misalignment of adjustment screw at point of contact between screw and lever. Such
wear can cause false switch actuating levels. Adjusting switch to compensate (if
possible) or replace the switch.
2) DO NOT operate your control with defective or mal-adjusted switch mechanism (refer
to bulletin on switch mechanisms furnished for service instructions.)
3) Controls may sometimes be exposed to excessive heat or moisture. Under such
conditions, insulation on electrical wiring may become brittle, eventually breaking or
pealing away. The resulting bare wires can cause short circuits.
Check wiring carefully and replace it at the first sign of brittle insulation.
4) Vibration may sometimes cause terminal screw to work loose. Check all terminal
connections to be certain that screws are tight.

LIBYAN BRANCH
COMPANY DOC. No:
CPECC DOC. No:

CPECC

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES
C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 67 OF 119

Spare switches should be kept on hand at all times.


6.4.3

What to avoid

1) Never leave switch-housing cover off the control longer than necessary to make routine
inspections.
2) Never place a jumper wire across terminals to cut-out the control. If a jumper is
necessary for test purpose, be certain it is removed before placing control into service.
3) Never attempt to make adjustments or replace switches without reading instructions
carefully. Certain adjustments provided for in flow switch should not be attempted in the
field. When in doubt, consult the factory or your local representative.
4) Never use lubricants on pivots of switch mechanisms. A sufficient amount of lubricant
has been applied at the factory to ensure a lifetime of service. Further lubrication is
unnecessary, and will only tend to attract dust and dirt that can interfere with mechanism
operation.
6.5

Maintenance of magnetic liquid level indicators


Periodic inspections are a necessary means to keep level indicator in good working order.
If the process liquid is clean (no solids or deposits), the MLI should require minimum
maintenance. If the process liquid is dirty (solid and deposits), it is recommended the
external cage be isolated from the process and flushed periodically. For complete cleaning,
after draining the unit, remove the bottom flange and float, inspect cage and float for build
up and clean if required.
Magnetic traps are available to prevent magnetic particulate travel from the vessel to the
chamber.

6.6

Maintenance of fire alarm system


6.6.1
LTD shall be tested every year

Maintenance of LTD

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES
C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 68 OF 119

1) Using a jump to apply a short across the end-of-line resistor to create an alarm.
2) The red LED of module PIM420 shall be illuminated.
3) Check whether FA panel and RTU receive the alarm signal.
4) Disconnect one wire of the detection loop to create a fault.
5) The yellow LED of module PIM420 shall be illuminated.
6) Check whether FA panel and RTU receive the fault.

6.6.2

Maintenance of smoke detector

Test series 60 optical smoke detector LTD every year


1) Using the aerosol dispenser test tool to test detectors and create an alarm.
2) The red LED of the detector shall be illuminated.
3) Check whether FA panel and RTU receive the alarm signal.
4) Disconnect one wire of the detection loop to create a fault.
5) Check whether FA panel and RTU receive the fault.
6.6.3
Test fire alarm panel every year

Maintenance of fire alarm panel

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES
C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 69 OF 119

Fig 27 Fire alarm panel


1) By pressing the reset and lump test switch, all indicators may be illuminated. The reset
and lump test switch will only become operative with the key switch in the enable
controls position.
2) Disconnect the main power, the system healthy indicator will extinguish.
3) Check whether battery start to power the system.
4) Check whether FA panel and RTU receive the fault.
5) Disconnect the battery. The system healthy indicator will extinguish.
6) Check whether FA panel and RTU receive the fault.
7) Disconnect one wire of any of detection loop to create a fault.
8) Check whether FA panel and RTU receive the fault.

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
COMPANY DOC. No:
CPECC DOC. No:

CPECC

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 70 OF 119

9) Test the LTD or detectors that be connected to detection loops.


10) Check whether FA panel and RTU receive the alarm signal.
6.7

Maintenance of burner system


6.7.1

Fig 28 Ignition control panel


Check regularly the working of the ignition equipment
a) Ignition transformer
b) Spark plug
c) Lamp
d) Temperature regulators
e) Twilight switch

Ignition control panel

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 71 OF 119

During maintenance operations pay attention to avoid both sand and water entrance inside
both the boxes and the pipes.
Pay attention in positioning the gasket of the Eex-d boxes inside its groove.
6.7.2

Burn pit

General check with particular emphasis in the following areas:

Fig 29 Burner tip


a) Pilot windshields
Check that top parts of pilots are not corroded or their geometry altered by
impingement of flame. If damaged, arrange for immediate replacement, as pilot flame
stability depends on this.
b) Retention ring
Check that flame retention ring and the whole extreme part of the tip are not damaged,
as this would cause blow-off. If damaged, arrange for immediate replacement.
c) Thermocouple
Check that thermocouple connection boxes are not misplaced or damaged. For the
thermocouple replacement, if necessary, the pilot must be dismantled.

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
COMPANY DOC. No:
CPECC DOC. No:

CPECC

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 72 OF 119

d) Piping and plate of burn pit


Check that all tips are not corroded or oxidized by flame temperature. If damaged,
specialized technicians shall be employed for inspection and possible subsequent repair or
replacement of parts that are defective.
6.8

Maintenance of pressure transmitter


If we find some errors of reading that deviate from normal reading we can correct it by
modify the curve of the instrument inside the computer database instead of calibrate the
instrument
See section 7.3 for periodic check.

6.9

Maintenance of differential pressure transmitter


If we find some errors of reading that deviate from normal reading we can correct it by
modify the curve of the instrument inside the computer database instead of calibrate the
instrument
See section 7.3 for periodic check.

6.10

Maintenance of temperature transmitter


If we find some errors of reading that deviate from normal reading we can correct it by
modify the curve of the instrument inside the computer database instead of calibrate the
instrument
See section 7.3 for periodic check.

6.11

Maintenance of flow meter


If we find some errors of reading that deviate from normal reading we can correct it by
modify the curve of the instrument inside the computer database instead of calibrate the
instrument
See section 7.3 for periodic check.

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
COMPANY DOC. No:
CPECC DOC. No:

CPECC

6.12

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 73 OF 119

Maintenance of differential pressure switch


See section 7.3 for periodic check.

6.13

Maintenance of control valve


Beta positioner maintenance
Every six months, check positioner for proper operation.

1. Maintain a clean air supply, free of dust, oil and water. It is recommended that an air filter
be used to ensure a clean air supply to positioner. Check and maintain air filter every
6months.
2. Make sure all arms and levers move freely.
3. Check for and tighten any loose parts.
4. Be sure there are no leaks in the air supply.
5. Check and maintain the coalescing filter element in the I/P module every 6months.

6.13.1

Repair of pilot valve

To repair the positioner pilot valve, refer to figure 16 and proceed as follows.
1. Loosen the zero adjustment locking knob (23) and zero adjusting knob (20). Disconnect the
feed back spring (34) from the zero screw (24). Remove the feedback spring from the
positioner assembly. Rotate the zero arm (22) out of the way before removing the snap ring
(8) holding the range adjustment arm (13) to the base assembly (7). Remove the range
adjustment arm.
2. Remove the two screws (53) holding the pilot valve to the base. Remove the pilot valve
from the positioner (be careful not to damage the pilot valve or balance beam). Slide the
pilot valve (40) from the spool valve body (52) and check it for dirt or sticking. The spool
should slide freely and fall through by its own weight when held vertically. Clean both the

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES
C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 74 OF 119

pilot valve spool and body with a degreasing solvent. When clean, insert the spool back
into the body and move it back and forth to ensure that it slides freely for proper operation.
If the spool doesnt slide freely, replace it.
Caution: Do not apply oil or grease to the spool.

6.13.2
assembly

Replace of instrument capsule

1. To replace the entire instrument capsule assembly, first remove the pilot valve as described
in steps 1 and 2 in the preceding section. Then remove the two screws fastening it to the
base. Make sure the new instrument capsule O-ring (48) is installed in the base of the
instrument capsule assembly. Install the two mounting screws (35) and tighten.
2. Replace the three pilot valve O-rings (54). Compress the leaf spring on the end of the
balance beam and carefully engage the notched end of spool with the beam spring. Slide
spool carefully until it is aligned with its mounting holes and fasten securely with two
screws (53).
3. Return the range arm to the base and secure with snap ring (8). Reinstall the feedback spring
with one end engaging the feedback screw and the other end engaging the zero screw.

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES
C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

Figure 30: Beta positioner-exploded view

REV. No: A2

PAGE 75 OF 119

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES
C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

6.13.3
6.13.3.1

REV. No: A2

PAGE 76 OF 119

I/P module maintenance

Service and replacement of I/P orifice


To service or replace the I/P module orifice, refer to Figure 17.

1. Disconnect air supply pressure to the positioner.


2. Remove the orifice screw (34) from the module housing (1). Examine the O-ring (32, 33) on
the orifice screw for wear. Replace if necessary.

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES
C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 77 OF 119

Fig 31 I/P module- exploded view

3. Examine the orifice for blockage. If blocked, dislodge the blockage by inserting a small
wire, less than 0.014-inch diameter, through the orifice. Be careful not to make the orifice

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES
C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 78 OF 119

larger during cleaning. Blow the orifice clean with air and then reassemble into housing. If
orifice is damaged it must be replaced.
4. Tightly replace cleaned or new orifice body into housing.
5. Reconnect the air supply pressure to the positioner.

6.13.3.2

Service and replacement of I/P filter

Check or replace filter element every six months.


1. Disconnect air supply pressure to the positioner.
2. Remove the filter cover screw (16) form the housing (1), being careful not to damage the Oring (17).
3. Remove the filter element (18) from the housing and examine it. If the filter is plugged or
dirty replace it with a new one.
4. Reinstall the filter after first cleaning the sealing surfaces. Install the filter in the housing,
and tightly fasten on the filter cover.
5. Reconnect the air supply pressure to the positioner.

6.13.3.3

Disassembly and reassembly of I/P pressure regulator

To disassembly and reassembly the I/P pressure regulator refer to Figure 17.
1. Disconnect air supply pressure to the positioner.
2. Remove the spring preload setscrew (30) from the pressure regulator cover (28)
Warning: The pressure regulator has an internal spring that is preloaded. Removing the
setscrew relieves this preload. This must be done before the pressure regulator cover is
removed; otherwise personal injury may occur.

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES
C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 79 OF 119

3. Remove the pressure gauge (31).


4. Remove the pressure regulator cover (28) by evenly removing its two mounting screws (29).
The pressure regulator preload will be further reduced as these screws are removed.
5. Remove the regulator spring button (27) and the regulator spring (26).
6. Remove the regulator piston (25), its O-ring (24), and the poppet seat (23) by gently pulling
on the raised lip of the piston with needle nose plier. Remove the poppet seat from the
piston. Do not pull on the protruding black stem.
7. Using a 7/16-inch socket wrench, remove the poppet guide (22), its O-ring (21), the
regulator poppet (20), and the poppet spring (19).
8. Before reassembly, clean the regulator cavity and check for galling and wear. Replace or
clean the necessary parts before reassembly.
9. To reassemble, place the poppet spring (19) into the housing cavity. Place the poppet guide
O-ring (21) on the poppet guide (22) and insert the regulator poppet (20) through the
bottom of the guide screw. Apply thread locking compound and thread the guide screw into
the housing using a 7/16-inch socket. Be careful not to over tighten the guide screw. Make
sure the poppet is free to move up and down and has spring load.
10. Assemble the poppet seat (23) into the regulator piston (25). Apply a small amount of Oring grease to the bore and wipe out all excess. Assemble the O-ring on the piston and
gently push the piston into the bore.
11. Place the regulator spring (26) on the piston, and place the spring button (27) on the spring.
Place a small amount of thread locking compound on the regulator cover screws (29) and
tightly secure the pressure regulator cover (28).
12. Place a small amount of thread locking compound on the threads of the pressure gauge (31)
and tightly thread it into the housing.
13. Reconnect the air supply to the positioner.

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

6.13.3.4

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 80 OF 119

Removal and replacement of I/P circuit board

To removal or replace the I/P circuit board refer to Figure 17.


1. Disconnect air supply pressure and input signal to the positioner.
2. Remove the I/P module housing cover (1).
3. Disconnect the input signal wires from the terminal block on the circuit board (4).
Disconnect the pressure modulator electrical connector from the circuit board.
4. Remove the three circuit board mounting screws (3) and carefully pull the circuit board
straight out. There is a pressure sensor attached to the underside of the circuit board that
fits in a port in the housing. Be careful not to damage the pressure sensor as the circuit
board is removed.
5. Install exiting, or replace with a new, circuit board by aligning the pressure sensor with the
port in the module housing and carefully pressing the board squarely in place. Do not
damage the pressure sensor O-ring. Reinstall the three circuit board mounting screws using
thread-locking compound.
6. Reconnect the pressure modulator electrical connector to the circuit board and the input
signal wires to the terminal block noting polarity.
7. Reinstall the housing cover. Reconnect the air supply pressure.

6.13.4
regulator

Maintenance of Bellofram filter

Clean the filter every 6 months.


1. To remove condensate, slowly open drain valve and bleed accumulated liquid.
2. To clean filter element:
1) Shut off air supply.
2) Drain condensate.

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
COMPANY DOC. No:
CPECC DOC. No:

CPECC

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

3) Remove large bolt from bottom of unit.


4) Remove bowl, filter and gasket.
5) Clean all parts thoroughly and reassemble in reverse order.

Fig 32 pressure regulator


1.

Sq. Hd. Adjusting Screw

2.

Nut, Locking

3.

Build Screw

PAGE 81 OF 119

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
COMPANY DOC. No:
CPECC DOC. No:

CPECC

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

4.

Bonnet

5.

Guide, Spring

6.

Spring, Range

7.

*Diaphragm Assembly

8.

Body

9.

*Gasket, Dripwell

REV. No: A2

10. *Filter
11. *Pintle, Valve
12. *Spring, Pintle
13. Screw, Pintle Spring
14. Housing, Dripwell
15. Petcock
16. Screw, Hex. Head
17. *Washer
All items marked with an asterisk (*) will be included in the repair kit.

PAGE 82 OF 119

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
COMPANY DOC. No:
CPECC DOC. No:

CPECC

6.14

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 83 OF 119

Maintenance of RTU
6.14.1

The hook-up drawing for LVS 1

6.14.2

The hook-up drawing for LVS 2

6.14.3

The hook-up drawing for LVS 3

6.14.4

The hook-up drawing for LVS 4

6.14.5

The hook-up drawing for LVS 5

6.14.6

The hook-up drawing for LVS 6

6.14.7

The hook-up drawing for LVS 7

6.14.8

The hook-up drawing for LVS 8

6.14.9

The hook-up drawing for LVS 9

6.14.10

The hook-up drawing for LVS 10

6.14.11

The hook-up drawing for LVS 11

6.14.12

The hook-up drawing for LVS 12

6.14.13

The hook-up drawing for LVS 13

6.14.14

The hook-up drawing for LVS 14

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

6.14.15
6.14.15.1

PAGE 84 OF 119

The hook-up drawing for LVS 15

Hook-up drawing for RTU DI

DEVICE NAME

TERMINAL

CABLE TAG

I/O LIST TAG

RTU TERMINAL(DI)

DOOR SWITCH

NC

3EZS029

3EZS029

DOOR SWITCH

COM

3EZS029

3EZS029

DOOR SWITCH

NC

3EZS030

3EZS030

DOOR SWITCH

COM

3EZS030

3EZS030

SOLAR CONT.CAB.

TB: 8 NO

3EE106

3EE106

SOLAR CONT.CAB.

TB: 21

3EE106

3EE106

I6

SOLAR CONT.CAB.

TB: 1 NO

3EE106

3EE107

SOLAR CONT.CAB.

TB: 14

3EE106

3EE107

SOLAR CONT.CAB.

TB: 2 NO

3EE106

3EE108

SOLAR CONT.CAB.

TB: 15

3EE106

3EE108

10

SOLAR CONT.CAB.

TB: 24

3EE106

3EE109

11

SOLAR CONT.CAB.

TB: 11

3EE106

3EE109

12

FIRE ALARM PANEL

15 NO

3EFAP015

3EFAPU015

13

FIRE ALARM PANEL

16

3EFAP015

3EFAPU015

14
15
16
17
18

FIRE ALARM PANEL

1 NO

3EFAP015

3ELTDA029

19

FIRE ALARM PANEL

3EFAP015

3ELTDA029

20

FIRE ALARM PANEL

3 NO

3EFAP015

3ELTDA030

21

FIRE ALARM PANEL

3EFAP015

3ELTDA030

22

FIRE ALARM PANEL

11 NO

3EFAP015

3ESODA071

23

FIRE ALARM PANEL

12

3EFAP015

3ESODA071

24

FIRE ALARM PANEL

13 NO

3EFAP015

3ESODA072

25

FIRE ALARM PANEL

14

3EFAP015

3ESODA072

26

FIRE ALARM PANEL

5 NO

3EFAP015

3ESODA073

27

FIRE ALARM PANEL

3EFAP015

3ESODA073

28

FIRE ALARM PANEL

7 NO

3EFAP015

3ESODA074

29

FIRE ALARM PANEL

3EFAP015

3ESODA074

30

FIRE ALARM PANEL

9 NO

3EFAP015

3ESODA075

31

FIRE ALARM PANEL

10

3EFAP015

3ESODA075

32

GAS BV VALVE

19 NO

3E160UV015S

3E160PSL015

33

GAS BV VALVE

20 COM

3E160UV015S

3E160PSL015

34

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 85 OF 119

GAS BV VALVE

25 NO

3E160UV015S

3E160UHS0154

35

GAS BV VALVE

24 COM

3E160UV015S

3E160UHS0154

36

GAS BV VALVE

10 NO

3E160UV015S

3E160UZSL015

37

GAS BV VALVE

9 COM

3E160UV015S

3E160UZSL015

38

GAS BV VALVE

4 NO

3E160UV015S

3E160UZSH015

39

GAS BV VALVE

3 COM

3E160UV015S

3E160UZSH015

40

OIL BV VALVE

19 NO

3E170UV015S

3E170PSL015

41

OIL BV VALVE

20 COM

3E170UV015S

3E170PSL015

42

OIL BV VALVE

25 NO

3E170UV015S

3E170UHS0154

43

OIL BV VALVE

24 COM

3E170UV015S

3E170UHS0154

44

OIL BV VALVE

10 NO

3E170UV015S

3E170UZSL015

45

OIL BV VALVE

9 COM

3E170UV015S

3E170UZSL015

46

OIL BV VALVE

4 NO

3E170UV015S

3E170UZSH015

47

OIL BV VALVE

3 COM

3E170UV015S

3E170UZSH015

48

CATODIC SOLAR CAB.

TB: 8 NO

3EE111

3EE111

49

CATODIC SOLAR CAB.

TB: 21

3EE111

3EE111

50

CATODIC SOLAR CAB.

TB: 1

3EE111

3EE112

51

CATODIC SOLAR CAB.

TB: 14

3EE111

3EE112

52

CATODIC SOLAR CAB.

TB: 2 NO

3EE111

3EE113

53

CATODIC SOLAR CAB.

TB: 15

3EE111

3EE113

54

CATODIC SOLAR CAB.

TB: 24

3EE111

3EE114

55

CATODIC SOLAR CAB.

TB: 11

3EE111

3EE114

56

CATODIC PRO. CAB.

X3.7

3ECPS029

3ECPS032

57

CATODIC PRO. CAB.

X3.9

3ECPS029

3ECPS032

58

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

6.14.15.2

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 86 OF 119

Hook-up drawing for RTU AI

DEVICE NAME

TERMINAL

CABLE TAG

I/O LIST TAG

RTU TERMINAL (AI)

OIL DIFF. PRESS. TRANS.

3E170PDT016

3E170PDT015

OIL DIFF. PRESS. TRANS.

3E170PDT016

3E170PDT015

GAS DIFF. PRESS. TRANS.

3E160PDT016

3E160PDT015

GAS DIFF. PRESS. TRANS.

3E160PDT016

3E160PDT015

EQUIP. BATT. VOLTAGE

U1: GND

3EE106

3EE110

EQUIP. BATT. VOLTAGE

U1:OUT

3EE106

3EE110

OIL PRESS. TRANS.

3E170PT015

3E170PT015

OIL PRESS. TRANS.

3E170PT015

3E170PT015

GAS PRESS. TRANS.

3E160PT015

3E160PT015

GAS PRESS. TRANS.

3E160PT015

3E160PT015

10

OIL TEMP. TRANS.

3E170TT015

3E170TT015

11

OIL TEMP. TRANS.

3E170TT015

3E170TT015

12

GAS TEMP. TRANS.

3E160TT015

3E160TT015

13

GAS TEMP. TRANS.

3E160TT015

3E160TT015

14

ROOM TEMP. TRANS.

3ETT015A

3ETT15A

15

ROOM TEMP. TRANS.

3ETT015A

3ETT15A

16

ROOM TEMP. TRANS.

3ETT015B

3ETT15B

17

ROOM TEMP. TRANS.

3ETT015B

3ETT15B

18

CATHODIC PRO. CAB. U

X3.3

3ECPS029

3ECPS029

19

CATHODIC PRO. CAB. U

X3.4

3ECPS029

3ECPS029

20

CATHODIC PRO. CAB. I

X3.1

3ECPS029

3ECPS030

21

CATHODIC PRO. CAB. I

X3.2

3ECPS029

3ECPS030

22

CATHODIC PRO. CAB. U

X3.5

3ECPS029

3ECPS031

23

CATHODIC PRO. CAB. U

X3.6

3ECPS029

3ECPS031

24

CATHODIC SOLAR U

U1:GND

3E111

3E115

25

CATHODIC SOLAR U

U1:IOUT

3E111

3E115

26

6.14.15.3

Hook-up drawing for RTU DO

DEVICE NAME

TERMINAL

CABLE TAG

I/O LIST TAG

RTU TERMINAL (DO)

GAS BV VALVE

17

3E160UV015C

3E160UYH0152

GAS BV VALVE

18

3E160UV015C

3E160UYH0152

GAS BV VALVE

15

3E160UV015C

3E160UYH0151

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 87 OF 119

GAS BV VALVE

16

3E160UV015C

3E160UYH0151

OIL BV VALVE

17

3E170UV015C

3E170UYH0152

OIL BV VALVE

18

3E170UV015C

3E170UYH0152

OIL BV VALVE

15

3E170UV015C

3E170UYH0151

OIL BV VALVE

16

3E170UV015C

3E170UYH0151

I/O LIST TAG

RTU TERMINAL

6.14.15.4

Hook-up drawing for RTU power supply

DEVICE NAME

TERMINAL

CABLE TAG

GAS BV VALVE

3E160UV015C

GAS BV VALVE

3E160UV015C

OIL BV VALVE

3E170UV015C

OIL BV VALVE

3E170UV015C

4
W1: 1
W1: 2
TB1: 1
TB1: 2
TB1: 3
TB1: 4
TB3: 1
TB3: 2

6.14.15.5

Hook-up drawing for input of fire alarm panel

DEVICE NAME

TERMINAL

CABLE TAG

I/O LIST TAG

FIRE ALARM TERM.

GAS LTD

3E160JB015

3E160JB015

17

GAS LTD

3E160JB015

3E160JB015

18

OIL LTD

3E170JB015

3E170JB015

19

OIL LTD

3E170JB015

3E170JB015

20

BATT. ROOM SOD

3ESOD071

3ESOD071

21

BATT. ROOM SOD

3ESOD071

3ESOD071

22

BATT. ROOM SOD

3ESOD072

3ESOD072

23

BATT. ROOM SOD

3ESOD072

3ESOD072

24

EQUIP. ROOM SOD

L1

3ESOD073

3ESOD073

25

EQUIP. ROOM SOD

L2

3ESOD073

3ESOD073

26

EQUIP. ROOM SOD

L1

3ESOD074

3ESOD074

27

EQUIP. ROOM SOD

L2

3ESOD074

3ESOD074

28

EQUIP. ROOM SOD

L1

3ESOD075

3ESOD075

29

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

EQUIP. ROOM SOD

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

L2

3ESOD075

REV. No: A2

3ESOD075

30

24VDC

24VDC

6.14.16
6.14.16.1

PAGE 88 OF 119

The hook-up drawing for LVS 16

Hook-up drawing for RTU DI

DEVICE NAME

TERMINAL

CABLE TAG

I/O LIST TAG

RTU TERMINAL (DI)

DOOR SWITCH

NC

3EZS031

3EZS031

DOOR SWITCH

COM

3EZS031

3EZS031

DOOR SWITCH

NC

3EZS032

3EZS032

DOOR SWITCH

COM

3EZS032

3EZS032

SOLAR CONT.CAB.

TB: 8 NO

3EE116

3EE116

SOLAR CONT.CAB.

TB: 21

3EE116

3EE116

SOLAR CONT.CAB.

TB: 1 NO

3EE116

3EE117

SOLAR CONT.CAB.

TB: 14

3EE116

3EE117

SOLAR CONT.CAB.

TB: 2 NO

3EE116

3EE118

SOLAR CONT.CAB.

TB: 15

3EE116

3EE118

10

SOLAR CONT.CAB.

TB: 24

3EE116

3EE119

11

SOLAR CONT.CAB.

TB: 11

3EE116

3EE119

12

FIRE ALARM PANEL

15 NO

3EFAP016

3EFAPU016

13

FIRE ALARM PANEL

16

3EFAP016

3EFAPU016

14
15
16
17
18

FIRE ALARM PANEL

1 NO

3EFAP016

3ELTDA031

19

FIRE ALARM PANEL

3EFAP016

3ELTDA031

20

FIRE ALARM PANEL

3 NO

3EFAP016

3ELTDA032

21

FIRE ALARM PANEL

3EFAP016

3ELTDA032

22

FIRE ALARM PANEL

11 NO

3EFAP016

3ESODA076

23

FIRE ALARM PANEL

12

3EFAP016

3ESODA076

24

FIRE ALARM PANEL

13 NO

3EFAP016

3ESODA077

25

FIRE ALARM PANEL

14

3EFAP016

3ESODA077

26

FIRE ALARM PANEL

5 NO

3EFAP016

3ESODA078

27

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 89 OF 119

FIRE ALARM PANEL

3EFAP016

3ESODA078

28

FIRE ALARM PANEL

7 NO

3EFAP016

3ESODA079

29

FIRE ALARM PANEL

3EFAP016

3ESODA079

30

FIRE ALARM PANEL

9 NO

3EFAP016

3ESODA080

31

FIRE ALARM PANEL

10

3EFAP016

3ESODA080

32

GAS BV VALVE

19 NO

3E160UV016S

3E160PSL016

33

GAS BV VALVE

20 COM

3E160UV016S

3E160PSL016

34

GAS BV VALVE

25 NO

3E160UV016S

3E160UHS0164

35

GAS BV VALVE

24 COM

3E160UV016S

3E160UHS0164

36

GAS BV VALVE

10 NO

3E160UV016S

3E160UZSL016

37

GAS BV VALVE

9 COM

3E160UV016S

3E160UZSL016

38

GAS BV VALVE

4 NO

3E160UV016S

3E160UZSH016

39

GAS BV VALVE

3 COM

3E160UV016S

3E160UZSH016

40

OIL BV VALVE

19 NO

3E170UV016S

3E170PSL016

41

OIL BV VALVE

20 COM

3E170UV016S

3E170PSL016

42

OIL BV VALVE

25 NO

3E170UV016S

3E170UHS0164

43

OIL BV VALVE

24 COM

3E170UV016S

3E170UHS0164

44

OIL BV VALVE

10 NO

3E170UV016S

3E170UZSL016

45

OIL BV VALVE

9 COM

3E170UV016S

3E170UZSL016

46

OIL BV VALVE

4 NO

3E170UV016S

3E170UZSH016

47

OIL BV VALVE

3 COM

3E170UV016S

3E170UZSH016

48

6.14.16.2

Hook-up drawing for RTU AI

DEVICE NAME

TERMINAL

CABLE TAG

I/O LIST TAG

RTU TERMINAL (AI)

OIL DIFF. PRESS. TRANS.

3E170PDT016

3E170PDT016

OIL DIFF. PRESS. TRANS.

3E170PDT016

3E170PDT016

GAS DIFF. PRESS. TRANS.

3E160PDT016

3E160PDT016

GAS DIFF. PRESS. TRANS.

3E160PDT016

3E160PDT016

EQUIP. BATT. VOLTAGE

U1: GND

3EE116

3EE120

EQUIP. BATT. VOLTAGE

U1:OUT

3EE116

3EE120

OIL PRESS. TRANS.

3E170PT016

3E170PT016

OIL PRESS. TRANS.

3E170PT016

3E170PT016

GAS PRESS. TRANS.

3E160PT016

3E160PT016

GAS PRESS. TRANS.

3E160PT016

3E160PT016

10

OIL TEMP. TRANS.

3E170TT016

3E170TT016

11

OIL TEMP. TRANS.

3E170TT016

3E170TT016

12

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 90 OF 119

GAS TEMP. TRANS.

3E160TT016

3E160TT016

13

GAS TEMP. TRANS.

3E160TT016

3E160TT016

14

ROOM TEMP. TRANS.

3ETT016A

3ETT016A

15

ROOM TEMP. TRANS.

3ETT016A

3ETT016A

16

ROOM TEMP. TRANS.

3ETT016B

3ETT016B

17

ROOM TEMP. TRANS.

3ETT016B

3ETT016B

18

6.14.16.3

Hook-up drawing for RTU DO

DEVICE NAME

TERMINAL

CABLE TAG

I/O LIST TAG

RTU TERMINAL (DO)

GAS BV VALVE

17

3E160UV016C

3E160UYH0162

GAS BV VALVE

18

3E160UV016C

3E160UYH0162

GAS BV VALVE

15

3E160UV016C

3E160UYH0161

GAS BV VALVE

16

3E160UV016C

3E160UYH0161

OIL BV VALVE

17

3E170UV016C

3E170UYH0162

OIL BV VALVE

18

3E170UV016C

3E170UYH0162

OIL BV VALVE

15

3E170UV016C

3E170UYH0161

OIL BV VALVE

16

3E170UV016C

3E170UYH0161

I/O LIST TAG

RTU TERMINAL

6.14.16.4

Hook-up drawing for RTU power supply

DEVICE NAME

TERMINAL

CABLE TAG

GAS BV VALVE

3E160UV016C

GAS BV VALVE

3E160UV016C

OIL BV VALVE

3E170UV016C

OIL BV VALVE

3E170UV016C

4
W1: 1
W1: 2
TB1: 1
TB1: 2
TB1: 3
TB1: 4
TB3: 1
TB3: 2

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

6.14.16.5

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 91 OF 119

Hook-up drawing for input of fire alarm panel

DEVICE NAME

TERMINAL

CABLE TAG

I/O LIST TAG

FIRE ALARM TERM.

GAS LTD

3E160JB016

3E160JB016

17

GAS LTD

3E160JB016

3E160JB016

18

OIL LTD

3E170JB016

3E170JB016

19

OIL LTD

3E170JB016

3E170JB016

20

BATT. ROOM SOD

3ESOD076

3ESOD076

21

BATT. ROOM SOD

3ESOD076

3ESOD076

22

BATT. ROOM SOD

3ESOD077

3ESOD077

23

BATT. ROOM SOD

3ESOD077

3ESOD077

24

EQUIP. ROOM SOD

L1

3ESOD078

3ESOD078

25

EQUIP. ROOM SOD

L2

3ESOD078

3ESOD078

26

EQUIP. ROOM SOD

L1

3ESOD079

3ESOD079

27

EQUIP. ROOM SOD

L2

3ESOD079

3ESOD079

28

EQUIP. ROOM SOD

L1

3ESOD080

3ESOD080

29

EQUIP. ROOM SOD

L2

3ESOD080

3ESOD080

30

24VDC

24VDC

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

6.14.17
pig trap station
6.14.17.1

REV. No: A2

PAGE 92 OF 119

The hook-up drawing for WAFA

Hook-up drawing for RTU DI

DEVICE NAME

TERMINAL

CABLE TAG

I/O LIST TAG

RTU TERMINAL (DI)

CATHODIC PRO. CAB

X3.7 NO

3ACPS001

3ACPS004

CATHODIC PRO. CAB

X3.8

3ACPS001

3ACPS004

2
3
4

FIRE ALARM CAB.

5 NO

3LAFU001

3LAFU001

FIRE ALARM CAB.

3LAFU001

3LAFU001

RECTIFIER1 FAILURE

3AES001

3AES001

RECTIFIER1 FAILURE

3AES001

3AES001

RECTIFIER2 FAILURE

3AES001

3AES002

RECTIFIER2 FAILURE

3AES001

3AES002

10

3A160MOV001

E3 N0

3A160MOV001

3A160MZSH001

11

3A160MOV001

E4 COM

3A160MOV001

3A160MZSH001

12

3A160MOV001

D2 NO

3A160MOV001

3A160MZSL001

13

3A160MOV001

D3 COM

3A160MOV001

3A160MZSL001

14

3A160MOV002

E3 N0

3A160MOV002

3A160MZSH002

15

3A160MOV002

E4 COM

3A160MOV002

3A160MZSH002

16

3A160MOV002

D2 NO

3A160MOV002

3A160MZSL002

17

3A160MOV002

D3 COM

3A160MOV002

3A160MZSL002

18

3A160MOV003

E3 N0

3A160MOV003

3A160MZSH003

19

3A160MOV003

E4 COM

3A160MOV003

3A160MZSH003

20

3A170MOV003

D2 NO

3A170MOV003

3A170MZSL003

21

3A170MOV003

D3 COM

3A170MOV003

3A170MZSL003

22

3A170MOV001

E3 N0

3A170MOV001

3A170MZSH001

23

3A170MOV001

E4 COM

3A170MOV001

3A170MZSH001

24

3A170MOV001

D2 NO

3A170MOV001

3A170MZSL001

25

3A170MOV001

D3 COM

3A170MOV001

3A170MZSL001

26

3A170MOV002

E3 N0

3A170MOV002

3A170MZSH002

27

3A170MOV002

E4 COM

3A170MOV002

3A170MZSH002

28

3A170MOV002

D2 NO

3A170MOV002

3A170MZSL002

29

3A170MOV002

D3 COM

3A170MOV002

3A170MZSL002

30

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 93 OF 119

3A170MOV003

E3 N0

3A170MOV003

3A170MZSH003

31

3A170MOV003

E4 COM

3A170MOV003

3A170MZSH003

32

3A170MOV003

D2 NO

3A170MOV003

3A170MZSL003

33

3A170MOV003

D3 COM

3A170MOV003

3A170MZSL003

34

FIRE ALARM CAB.

3 NO

3ALAFU001

3ALAFU002

35

FIRE ALARM CAB.

3ALAFU001

3ALAFU002

36

FIRE ALARM CAB.

1 NO

3ALAFU001

3ALTDA001

37

FIRE ALARM CAB.

3ALAFU001

3ALTDA001

38

3A170MOV001

E1 NO

3A170MOV001

3A170MUS0012

39

3A170MOV001

E2 COM

3A170MOV001

3A170MUS0012

40

3A160MOV002

E1 NO

3A160MOV002

3A160MUS0022

41

3A160MOV002

E2 COM

3A160MOV002

3A160MUS0022

42

3A160MOV001

E1 NO

3A160MOV001

3A160MUS0012

43

3A160MOV001

E2 COM

3A160MOV001

3A160MUS0012

44

3A160160PDSL001

NC

3A160PDSL001

3A160-PDSL001

45

3A160160PDSL001

COM

3A160PDSL001

3A160-PDSL001

46

3A160MOV003

E1 NO

3A160MOV003

3A160MUS0032

47

3A160MOV003

E2 COM

3A160MOV003

3A160MUS0032

48

3A160PDSL002

NC

3A160PDSL002

3A160-PDSL002

49

3A160PDSL002

COM

3A160PDSL002

3A160-PDSL002

50

3A 170MOV002

E1 NO

3A170MOV002

3A170MUS0022

51

3A 170MOV002

E2 COM

3A170MOV002

3A170MUS0022

52

3A 170PDSL001

NC

3A170PDSL001

3A170PDSL001

53

3A 170PDSL001

COM

3A170PDSL001

3A170PDSL001

54

3A 170MOV003

E1 NO

3A170MOV003

3A170MUS0032

55

3A 170MOV003

E2 COM

3A170MOV003

3A170MUS0032

56

3A 170-PDSL002

NC

3A170PDSL002

3A170PDSL002

57

3A 170-PDSL002

COM

3A170PDSL002

3A170PDSL002

58

3A 160PDSH003

NC

3A160PDSH003

3A160PDSH003

59

3A 160PDSH003

COM

3A160PDSH003

3A160PDSH003

60

3A 160SDV001

21 NO

3A160SDV001S

3A160PSL001

61

3A 160SDV001

22 COM

3A160SDV001S

3A160PSL001

62

3A 160SDV001

27 NO

3A160SDV001S

3A160SHS0014

63

3A 160SDV001

26 COM

3A160SDV001S

3A160SHS0014

64

3A 160SDV001

4 NO

3A160SDV001S

3A160SZSH001

65

3A 160SDV001

3 COM

3A160SDV001S

3A160SZSH001

66

3A 160SDV001

10 NO

3A160SDV001S

3A160SZSL001

67

3A 160SDV001

9 COM

3A160SDV001S

3A160SZSL001

68

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 94 OF 119

3A170PDSH003

NC

3A170PDSH003

3A170PDSH003

69

3A170PDSH003

COM

3A170PDSH003

3A170PDSH003

70

3A170SDV001

21 NO

3A170SDV001S

3A170PSL001

71

3A170SDV001

22 COM

3A170SDV001S

3A170PSL001

72

3A170SDV001

27 NC

3A170SDV001S

3A170SHS0014

73

3A170SDV001

26 COM

3A170SDV001S

3A170SHS0014

74

3A170SDV001

4 NO

3A170SDV001S

3A170SZSH001

75

3A170SDV001

3 COM

3A170SDV001S

3A170SZSH001

76

3A170SDV001

10 NO

3A170SDV001S

3A170SZSL001

77

3A170SDV001

9 COM

3A170SDV001S

3A170SZSH001

78

3A160SDV002

21 NO

3A160SDV002S

3A160PSL002

79

3A160SDV002

22 COM

3A160SDV002S

3A160PSL002

80

3A160SDV002

27 NC

3A160SDV002S

3A160SHS0024

81

3A160SDV002

26 COM

3A160SDV002S

3A160SHS0024

82

3A160SDV002

4 NO

3A160SDV002S

3A160SZSH002

83

3A160SDV002

3 COM

3A160SDV002S

3A160SZSH002

84

3A160SDV002

10 NO

3A160SDV002S

3A160SZSL002

85

3A160SDV002

9 COM

3A160SDV002S

3A160SZSL002

86

3A160SDV003

21 NO

3A160SDV003S

3A160PSL003

87

3A160SDV003

22 COM

3A160SDV003S

3A160PSL003

88

3A160SDV003

27 NC

3A160SDV003S

3A160SHS0034

89

3A160SDV003

26 COM

3A160SDV003S

3A160SHS0034

90

3A160SDV003

4 NO

3A160SDV003S

3A160SZSH003

91

3A160SDV003

3 COM

3A160SDV003S

3A160SZSH003

92

3A160SDV003

10 NO

3A160SDV003S

3A160SZSL003

93

3A160SDV003

9 COM

3A160SDV003S

3A160SZSL003

94

3A170SDV002

21 NO

3A170SDV002S

3A170PSL002

95

3A170SDV002

22 COM

3A170SDV002S

3A170PSL002

96

3A170SDV002

27 NC

3A170SDV002S

3A170SHS0024

97

3A170SDV002

26 COM

3A170SDV002S

3A170SHS0024

98

3A170SDV002

4 NO

3A170SDV002S

3A170SZSH002

99

3A170SDV002

3 COM

3A170SDV002S

3A170SZSH002

100

3A170SDV002

10 NO

3A170SDV002S

3A170SZSL002

101

3A170SDV002

9 COM

3A170SDV002S

3A170SZSL002

102

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

6.14.17.2

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 95 OF 119

Hook-up drawing for RTU AI

DEVICE NAME

TERMINAL

CABLE TAG

I/O LIST TAG

RTU TERMINAL (AI)

GAS TEMP. TRANS.

3A160TT001

3A160TT001

GAS TEMP. TRANS

3A160TT001

3A160TT001

GAS PRESS. TRANS.

3A160PT001

3A160PT001

GAS PRESS. TRANS.

3A160PT001

3A160PT001

CATHODIC PRO. CAB. U

X3.3

3ACPS001

3ACPS001

CATHODIC PRO. CAB. U

X3.4

3ACPS001

3ACPS001

CATHODIC PRO. CAB. I

X3.1

3ACPS001

3ACPS002

CATHODIC PRO. CAB. I

X3.2

3ACPS001

3ACPS002

CATHODIC PRO. CAB. U

X3.5

3ACPS001

3ACPS003

CATHODIC PRO. CAB. U

X3.6

3ACPS001

3ACPS003

10

GAS FLOW TRANS.

3A160FT001

3A160FT001

11

GAS FLOW TRANS.

3A160FT001

3A160FT001

12

6.14.17.3

Hook-up drawing for RTU DO

DEVICE NAME

TERMINAL

CABLE TAG

I/O LIST TAG

RTU TERMINAL (DO)

3A160SDV001

15

3A160SDV001C

3A160SYH011

3A160SDV001

16

3A160SDV001C

3A160SYH011

3A160SDV001

17

3A160SDV001C

3A160SYH012

3A160SDV001

18

3A160SDV001C

3A160SYH012

3A160SDV001

19

3A160SDV001C

3A160SYH013

3A160SDV001

20

3A160SDV001C

3A160SYH013

3A160SDV002

15

3A160SDV002C

3A160SYH0021

3A160SDV002

16

3A160SDV002C

3A160SYH0021

3A160SDV002

17

3A160SDV002C

3A160SYH0022

3A160SDV002

18

3A160SDV002C

3A160SYH0022

10

3A160SDV002

19

3A160SDV002C

3A160SYH0023

11

3A160SDV002

20

3A160SDV002C

3A160SYH0023

12

3A160SDV003

15

3A160SDV003C

3A160SYH0031

13

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 96 OF 119

3A160SDV003

16

3A160SDV003C

3A160SYH0031

14

3A160SDV003

17

3A160SDV003C

3A160SYH0032

15

3A160SDV003

18

3A160SDV003C

3A160SYH0032

16

3A170SDV001

19

3A160SDV003C

3A160SYH0033

17

3A170SDV001

20

3A160SDV003C

3A160SYH0033

18

3A170SDV001

15

3A170SDV001C

3A170SYH0011

19

3A170SDV001

16

3A170SDV001C

3A170SYH0011

20

3A170SDV001

17

3A170SDV001C

3A170SYH0012

21

3A170SDV001

18

3A170SDV001C

3A170SYH0012

22

3A170SDV001

19

3A170SDV001C

3A170SYH0013

23

3A170SDV001

20

3A170SDV001C

3A170SYH0013

24

3A170SDV002

15

3A170SDV002C

3A170SYH0021

25

3A170SDV002

16

3A170SDV002C

3A170SYH0021

26

3A170SDV002

17

3A170SDV002C

3A170SYH0022

27

3A170SDV002

18

3A170SDV002C

3A170SYH0022

28

3A170SDV002

19

3A170SDV002C

3A170SYH0023

29

3A170SDV002

20

3A170SDV002C

3A170SYH0023

30

6.14.17.4

Hook-up drawing for RTU AO

DEVICE NAME

TERMINAL

CABLE TAG

I/O LIST TAG

RTU TERMINAL (DO)

3A160PV001

3A160PIC001

3A160PY001

3A160PV001

3A160PIC001

3A160PY001

6.14.17.5

Hook-up drawing for RTU power supply

DEVICE NAME

TERMINA

CABLE TAG

I/O LIST TAG

RTU TERMINAL

L
3A160SDV001

3A160SDV001C

3A160SDV001

3A160SDV001C

3A160SDV002

3A160SDV002C

3A160SDV002

3A160SDV002C

3A170SDV001

3A170SDV001C

3A170SDV001

3A170SDV001C

3A170SDV002

3A170SDV002C

3A170SDV002

3A170SDV002C

3A160SDV003

3A160SDV001C

3A160SDV003

3A160SDV001C

10

24VDC FOR VALVE

W1: 1

24VDC FOR VALVE

W1: 2

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 97 OF 119

24VDC FOR RTU

TB1: 1

24VDC FOR RTU

TB1: 2

24VDC FOR RTU STAND-BY

TB1: 3

24VDC FOR RTU STAND-BY

TB1: 4

24VDC FOR INTERNAL

TB3: 1

24VDC FOR INTERNAL

TB3: 2

6.14.17.6

Hook-up drawing for input of fire alarm panel

DEVICE NAME

TERMINAL

CABLE TAG

I/O LIST TAG

FIRE ALARM TERM.

OIL LTD

3E170JB001

3E170JB001

OIL LTD

3E170JB001

3E170JB001

GAS LTD

3E160JB001

3E160JB001

GAS LTD

3E160JB001

3E160JB001

10

24VDC IN

3AFAP001

3AFAP001

+3

24VDC IN

3AFAP001

3AFAP001

6.14.17.7

Hook-up drawing for motor valve

DEVICE NAME

TERMINAL

CABLE TAG

I/O LIST TAG

MOTOR
TERMINAL

3A160PDSL001

NC

3A160PDSL001A

3A160PDSL001A

C3

3A160PDSL001

COM

3A160PDSL001A

3A160PDSL001A

C4

3A160PDSL002

NC

3A160PDSL002A

3A160PDSL002A

C3

3A160PDSL002

COM

3A160PDSL002A

3A160PDSL002A

C4

3A170PDSL001

NC

3A170PDSL001A

3A170PDSL001A

C3

3A170PDSL001

COM

3A170PDSL001A

3A170PDSL001A

C4

3A170PDSL002

NC

3A170PDSL002A

3A170PDSL002A

C3

3A170PDSL002

COM

3A170PDSL002A

3A170PDSL002A

C4

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

6.14.18
station 1

REV. No: A2

PAGE 98 OF 119

The hook-up drawing for pig trap

6.14.18.1 Hook-up drawing for RTU DI


DEVICE NAME

TERMINAL

CABLE TAG

I/O LIST TAG

RTU TERMINAL (DI)

3B170FSH001

NC

3B170FSH001

3B170FSH001

3B170FSH001

COM

3B170FSH001

3B170FSH001

3B170LSLL011

NC

3B170LSLL011

3B170LSLL011

3B170LSLL011

COM

3B170LSLL011

3B170LSLL011

3B170LSHH012

NC

3B170LSHH012

3B170LSHH012

3B170LSHH012

COM

3B170LSHH012

3B170LSHH012

SOLAR FAIL

TB: 8 NO

3BE001

3BE001

SOLAR FAIL

TB: 21

3BE001

3BE001

OVER VOLTAGE

TB: 1 NO

3BE001

3BE002

OVER VOLTAGE

TB: 14

3BE001

3BE002

10

UNDER VOLTAGE

TB: 2

3BE001

3BE003

11

UNDER VOLTAGE

TB: 15

3BE001

3BE003

12

OVER CURRENT

TB: 24

3BE001

3BE004

13

OVER CURRENT

TB: 11+12

3BE001

3BE004

14

SOLAR FAIL

TB: 8 NO

3BE006

3BE006

15

SOLAR FAIL

TB: 21

3BE006

3BE006

16

OVER VOLTAGE

TB: 1 NO

3BE006

3BE007

17

OVER VOLTAGE

TB: 14

3BE006

3BE007

18

UNDER VOLTAGE

TB: 2

3BE006

3BE008

19

UNDER VOLTAGE

TB: 15

3BE006

3BE008

20

OVER CURRENT

TB: 24

3BE006

3BE009

21

OVER CURRENT

TB: 11+12

3BE006

3BE009

22

CPS FAIL

X3.7 NO

3BCPS001

3BCPS004

23

CPS FAIL

X3.8

3BCPS001

3BCPS004

24

PILOT OFF

3B170XS501

3B170XS501

25

PILOT OFF

3B170XS501

3B170XS501

26

ROOM DOOR OPEN

NC

3BZS001

3BZS001

27

ROOM DOOR OPEN

COM

3BZS001

3BZS001

28

ROOM DOOR OPEN

NC

3BZS002

3BZS002

29

ROOM DOOR OPEN

COM

3BZS002

3BZS002

30

FIRE ALARM FAIL

21 NO

3BLAFU001

3BFAPU001

31

FIRE ALARM FAIL

22

3BLAFU001

3BFAPU001

32

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 99 OF 119

3B160UV002

4 NO

3B160UV002S

3B160UZSH002

33

3B160UV002

3 COM

3B160UV002S

3B160UZSH002

34

3B160UV002

10 NO

3B160UV002S

3B160UZSL002

35

3B160UV002

9 COM

3B160UV002S

3B160UZSL002

36

3B160UV003

4 NO

3B160UV003S

3B160UZSH003

37

3B160UV003

3 COM

3B160UV003S

3B160UZSH003

38

3B160UV003

10 NO

3B160UV003S

3B160UZSL003

39

3B160UV003

9 COM

3B160UV003S

3B160UZSL003

40

3B160UV0034

4 NO

3B160UV004S

3B160UZSH004

41

3B160UV004

3 COM

3B160UV004S

3B160UZSH004

42

3B160UV004

10 NO

3B160UV004S

3B160UZSL004

43

3B160UV004

9 COM

3B160UV004S

3B160UZSL004

44

3B160UV005

4 NO

3B160UV005S

3B160UZSH005

45

3B160UV005

3 COM

3B160UV005S

3B160UZSH005

46

3B160UV005

10 NO

3B160UV005S

3B160UZSL005

47

3B160UV005

9 COM

3B160UV005S

3B160UZSL005

48

3B160UV006

4 NO

3B160UV006S

3B160UZSH006

49

3B160UV006

3 COM

3B160UV006S

3B160UZSH006

50

3B160UV006

10 NO

3B160UV006S

3B160UZSL006

51

3B160UV006

9 COM

3B160UV006S

3B160UZSL006

52

3B160UV007

4 NO

3B160UV007S

3B160UZSH007

53

3B160UV007

3 COM

3B160UV007S

3B160UZSH007

54

3B160UV007

10 NO

3B160UV007S

3B160UZSL007

55

3B160UV007

9 COM

3B160UV007S

3B160UZSL007

56

3B170UV002

4 NO

3B170UV002S

3B160UZSH002

57

3B170UV002

3 COM

3B170UV002S

3B170UZSH002

58

3B170UV002

10 NO

3B170UV002S

3B170UZSL002

59

3B170UV002

9 COM

3B170UV002S

3B170UZSL002

60

3B170UV003

4 NO

3B170UV003S

3B170UZSH003

61

3B170UV003

3 COM

3B170UV003S

3B170UZSH003

62

3B170UV003

10 NO

3B170UV003S

3B170UZSL003

63

3B170UV003

9 COM

3B170UV003S

3B170UZSL003

64

3B170UV0034

4 NO

3B170UV004S

3B170UZSH004

65

3B170UV004

3 COM

3B170UV004S

3B170UZSH004

66

3B170UV004

10 NO

3B170UV004S

3B170UZSL004

67

3B170UV004

9 COM

3B170UV004S

3B170UZSL004

68

3B170UV005

4 NO

3B170UV005S

3B170UZSH005

69

3B170UV005

3 COM

3B170UV005S

3B170UZSH005

70

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 100 OF 119

3B170UV005

10 NO

3B170UV005S

3B170UZSL005

71

3B170UV005

9 COM

3B170UV005S

3B170UZSL005

72

3B170UV006

4 NO

3B170UV006S

3B170UZSH006

73

3B170UV006

3 COM

3B170UV006S

3B170UZSH006

74

3B170UV006

10 NO

3B170UV006S

3B170UZSL006

75

3B170UV006

9 COM

3B170UV006S

3B170UZSL006

76

3B170UV007

4 NO

3B170UV007S

3B170UZSH007

77

3B170UV007

3 COM

3B170UV007S

3B170UZSH007

78

3B170UV007

10 NO

3B170UV007S

3B170UZSL007

79

3B170UV007

9 COM

3B170UV007S

3B170UZSL007

80

3B170MOV011

E3 NO

3B170MOV011

3B170MZSH011

81

3B170MOV011

E4 COM

3B170MOV011

3B170MZSH011

82

3B170LSHH013

NC

3B170LSHH013

3B170LSHH013

83

3B170LSHH013

COM

3B170LSHH013

3B170LSHH013

84

3B170MOV011

E1 NO

3B170MOV011

3B170MUS0112

85

3B170MOV011

E2 COM

3B170MOV011

3B170MUS0112

86

3B170MOV011

D2 NO

3B170MOV011

3B170MZSL011

87

3B170MOV011

D3 COM

3B170MOV011

3B170MZSL011

88

3B170MOV011

D4 NO

3B170MOV011

3B170MHS0114

89

3B170MOV011

D5 COM

3B170MOV011

3B170MHS0114

90

3B160UV001

19 NO

3B160UV001S

3B160PSL001

91

3B160UV001

20 COM

3B160UV001S

3B160PSL001

92

3B160UV001

25 NC

3B160UV001S

3B160UHS0014

93

3B160UV001

24 COM

3B160UV001S

3B160UHS0014

94

3B160UV001

4 NO

3B160UV001S

3B160UZSH001

95

3B160UV001

3 COM

3B160UV001S

3B160UZSH001

96

3B160UV001

10 NO

3B160UV001S

3B160UZSL001

97

3B160UV001

9 COM

3B160UV001S

3B160UZSL001

98

3B160UV008

10 NO

3B160UV008S

3B160UZSL008

99

3B160UV008

9 COM

3B160UV008S

3B160UZSL008

100

3B160UV008

19 NO

3B160UV008S

3B160PSL008

101

3B160UV008

20 COM

3B160UV008S

3B160PSL008

102

3B160UV008

25 NC

3B160UV008S

3B160UHS0084

103

3B160UV008

24

3B160UV008S

3B160UHS0084

104

3B160UV008

4 NO

3B160UV008S

3B160UZSH008

105

3B160UV008

3COM

3B160UV008S

3B160UZSH008

106

3B170UV001

10 NO

3B170UV001S

3B170UZSL001

107

3B170UV001

9COM

3B170UV001S

3B170UZSL001

108

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 101 OF 119

3B170UV001

4 NO

3B170UV001S

3B170UZSH001

109

3B170UV001

3COM

3B170UV001S

3B170UZSH001

110

3B170UV001

19 NO

3B170UV001S

3B170PSL001

111

3B170UV001

20 COM

3B170UV001S

3B170PSL001

112

3B170UV001

25 NC

3B170UV001S

3B170UHS0014

113

3B170UV001

24 COM

3B170UV001S

3B170UHS0014

114

3B170UV008

10 NO

3B170UV008S

3B170UZSL008

115

3B170UV008

9COM

3B170UV008S

3B170UZSL008

116

3B170UV008

4 NO

3B170UV008S

3B170UZSH008

117

3B170UV008

3COM

3B170UV008S

3B170UZSH008

118

3B170UV008

25 NC

3B170UV008S

3B170UHS0084

119

3B170UV008

24 COM

3B170UV008S

3B170UHS0084

120

3B170UV008

19 NO

3B170UV008S

3B170PSL008

121

3B170UV008

20 COM

3B170UV008S

3B170PSL008

122

3B160PDSL001

NO

3B160PDSL001

3B160PDSL001

123

3B160PDSL001

COM

3B160PDSL001

3B160PDSL001

124

3B160UV002

19 NO

3B160UV002S

3B160PSL002

125

3B160UV002

20 COM

3B160UV002S

3B160PSL002

126

3B160UV004

19 NO

3B160UV004S

3B160PSL004

127

3B160UV004

20 COM

3B160UV004S

3B160PSL004

128

DEVICE NAME

TERMINAL

CABLE TAG

I/O LIST TAG

RTU TERMINAL (DI)

3B160PDSL002

NO

3B160PDSL002

3B160PDSL002

3B160PDSL002

COM

3B160PDSL002

3B160PDSL002

3B160PDSL003

NO

3B160PDSL003

3B160PDSL003

3B160PDSL003

COM

3B160PDSL003

3B160PDSL003

3B160UV005

19 NO

3B160UV005S

3B160PSL005

3B160UV005

20 COM

3B160UV005S

3B160PSL005

3B160UV007

19 NO

3B160UV007S

3B160PSL007

3B160UV007

20 COM

3B160UV007S

3B160PSL007

3B160PDSL004

NO

3B160PDSL004

3B160PDSL004

3B160PDSL002

COM

3B160PDSL004

3B160PDSL004

10

3B170UV003

19 NO

3B170UV003S

3B170PSL003

11

3B170UV003

20 COM

3B170UV003S

3B170PSL003

12

3B170PDSL001

NO

3B170PDSL001

3B170PDSL001

13

3B170PDSL001

COM

3B170PDSL001

3B170PDSL001

14

3B170PDSL002

NO

3B170PDSL002

3B170PDSL002

15

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 102 OF 119

3B170PDSL002

COM

3B170PDSL002

3B170PDSL002

16

3B170UV004

19 NO

3B170UV004S

3B170PSL004

17

3B170UV004

20 COM

3B170UV004S

3B170PSL004

18

3B170UV006

19 NO

3B170UV006S

3B170PSL006

19

3B170UV006

20 COM

3B170UV006S

3B170PSL006

20

3B170PDSL003

NO

3B170PDSL003

3B170PDSL003

21

3B170PDSL003

COM

3B170PDSL003

3B170PDSL003

22

3B170PDSL004

NO

3B170PDSL004

3B170PDSL004

23

3B170PDSL004

COM

3B170PDSL004

3B170PDSL004

24

3B170UV007

19 NO

3B170UV007S

3B170PSL007

25

3B170UV007

20 COM

3B170UV007S

3B170PSL007

26

3B170UV002

19 NO

3B170UV002S

3B170PSL002

27

3B170UV002

20 COM

3B170UV002S

3B170PSL002

28

3B160UV003

19 NO

3B160UV003S

3B160PSL003

29

3B160UV003

20 COM

3B160UV003S

3B160PSL003

30

3B170UV005

19 NO

3B170UV005S

3B170PSL005

31

3B170UV005

20 COM

3B170UV005S

3B170PSL005

32

3B160UV006

19 NO

3B160UV006S

3B160PSL006

33

3B160UV006

20 COM

3B160UV006S

3B160PSL006

34
35
36
37
38
39
40

3BFAP001

1 NO

3BLAFU001

3BLTDA001

41

3BFAP001

3BLAFU001

3BLTDA001

42

3BFAP001

3 NO

3BLAFU001

3BLTDA002

43

3BFAP001

3BLAFU001

3BLTDA002

44

3BFAP001

5 NO

3BLAFU001

3BLTDA003

45

3BFAP001

3BLAFU001

3BLTDA003

46

3BFAP001

7 NO

3BLAFU001

3BLTDA004

47

3BFAP001

3BLAFU001

3BLTDA004

48

3BFAP001

9 NO

3BLAFU001

3BLTDA005

49

3BFAP001

10

3BLAFU001

3BLTDA005

50

3BFAP001

11 NO

3BSODA001

3BSODA001

51

3BFAP001

12

3BSODA001

3BSODA001

52

3BFAP001

13 NO

3BSODA001

3BSODA002

53

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 103 OF 119

3BFAP001

14

3BSODA001

3BSODA002

54

3BFAP001

15 NO

3BSODA001

3BSODA003

55

3BFAP001

16

3BSODA001

3BSODA003

56

3BFAP001

17 NO

3BSODA001

3BSODA004

57

3BFAP001

18

3BSODA001

3BSODA004

58

3BFAP001

19 NO

3BSODA001

3BSODA005

59

3BFAP001

20

3BSODA001

3BSODA005

60
61
62
63
64

6.14.18.1

Hook-up drawing for RTU AI

DEVICE NAME

TERMINAL

CABLE TAG

I/O LIST TAG

RTU TERMINAL (AI)

3B160TT001

3B160TT001

3B160TT001

3B160TT001

3B160TT001

3B160TT001

3B160TT002

3B160TT002

3B160TT002

3B160TT002

3B160TT002

3B160TT002

3B160PT001

3B160PT001

3B160PT001

3B160PT001

3B160PT001

3B160PT001

3B160PT002

3B160PT002

3B160PT002

3B160PT002

3B160PT002

3B160PT002

3B160PDT001

3B160PDT001

3B160PDT001

3B160PDT001

3B160PDT001

3B160PDT001

10

3B160PDT002

3B160PDT002

3B160PDT002

11

3B160PDT002

3B160PDT002

3B160PDT002

12

3B170TT001

3B170TT001

3B170TT001

13

3B170TT001

3B170TT001

3B170TT001

14

3B170TT002

3B170TT002

3B170TT002

15

3B170TT002

3B170TT002

3B170TT002

16

3B170TT011

3B170TT011

3B170TT011

17

3B170TT011

3B170TT011

3B170TT011

18

3B170PT001

3B170PT001

3B170PT001

19

3B170PT001

3B170PT001

3B170PT001

20

3B170PT002

3B170PT002

3B170PT002

21

3B170PT002

3B170PT002

3B170PT002

22

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 104 OF 119

3B170PT0011

3B170PT0011

3B170PT0011

23

3B170PT0011

3B170PT0011

3B170PT0011

24

3B170PDT001

3B170PDT001

3B170PDT001

25

3B170PDT001

3B170PDT001

3B170PDT001

26

3B170PDT002

3B170PDT002

3B170PDT002

27

3B170PDT002

3B170PDT002

3B170PDT002

28

3B170PIT501

3B170PIT501

3B170PIT501

29

3B170PIT501

3B170PIT501

3B170PIT501

30

3B170PIT502

3B170PIT502

3B170PIT502

31

3B170PIT502

3B170PIT502

3B170PIT502

32
33
34

3BTT01A

3BTT01A

3BTT01A

35

3BTT01A

3BTT01A

3BTT01A

36

3BTT01B

3BTT01B

3BTT01B

37

3BTT01B

3BTT01B

3BTT01B

38

3B170LT011

3B170LT011

3B170LT011

39

3B170LT011

3B170LT011

3B170LT011

40

3B170LT012

3B170LT012

3B170LT012

41

3B170LT012

3B170LT012

3B170LT012

42

3BE001

U1: GND

3BE001

3BE005

43

3BE001

U1: OUT

3BE001

3BE005

44

3BE006

U1: GND

3BE006

3BE010

45

3BE006

U1: OUT

3BE006

3BE010

46

3BCPS001

X3.3

3BCPS001

3BCPS001

47

3BCPS001

X3.4

3BCPS001

3BCPS001

48

3BCPS001

X3.1

3BCPS001

3BCPS002

49

3BCPS001

X3.2

3BCPS001

3BCPS002

50

3BCPS001

X3.5

3BCPS001

3BCPS003

51

3BCPS001

X3.6

3BCPS001

3BCPS003

52

6.14.18.2

Hook-up drawing for RTU DO

DEVICE NAME

TERMINAL

CABLE TAG

I/O LIST TAG

RTU TERMINAL (DO)

3B160UV001

15

3B160UV001C

3B160UYH011

3B160UV001

16

3B160UV001C

3B160UYH011

3B160UV001

17

3B160UV001C

3B160UYH012

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 105 OF 119

3B160UV001

18

3B160UV001C

3B160UYH012

3B160UV008

15

3B160UV008C

3B160UYH0081

3B160UV008

16

3B160UV008C

3B160UYH0081

3B160UV008

17

3B160UV008C

3B160UYH0082

3B160UV008

18

3B160UV008C

3B160UYH0082

3B170MOV011

C2

3B170MOV011

3B170MYH0111

3B170MOV011

C7

3B170MOV011

3B170MYH0111

10

3B170MOV011

C2

3B170MOV011

3B170MYH0112

11

3B170MOV011

C6

3B170MOV011

3B170MYH0112

12

3B170MOV011

C2

3B170MOV011

3B170MYLL011

13

3B170MOV011

C5

3B170MOV011

3B170MYLL011

14

3B170UV001

15

3B170UV001C

3B170UYH0011

15

3B170UV001

16

3B170UV001C

3B170UYH0011

16

3B170UV001

17

3B170UV001C

3B170UYH0012

17

3B170UV001

18

3B170UV001C

3B170UYH0012

18

3B170UV008

15

3B170UV008C

3B170UYH0081

19

3B170UV008

16

3B170UV008C

3B170UYH0081

20

3B170UV008

17

3B170UV008C

3B170UYH0082

21

3B170UV008

18

3B170UV008C

3B170UYH0082

22

6.14.18.3

Hook-up drawing for RTU power supply

DEVICE NAME

TERMINAL

CABLE TAG

I/O LIST TAG

RTU TERMINAL

3B160UV001

3B160UV001C

3B160UV001

3B160UV001C

3B160UV002

3B160UV002C

3B160UV002

3B160UV002C

3B160UV003

3B160UV003C

3B160UV003

3B160UV003C

3B160UV004

3B160UV004C

3B160UV004

3B160UV004C

3B160UV005

3B160UV005C

3B160UV005

3B160UV005C

10

3B160UV006

3B160UV006C

11

3B160UV006

3B160UV006C

12

3B160UV007

3B160UV007C

13

3B160UV007

3B160UV007C

14

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 106 OF 119

3B160UV008

3B160UV008C

15

3B160UV008

3B160UV008C

16

3B170UV001

3B170UV001C

17

3B170UV001

3B170UV001C

18

3B170UV002

3B170UV002C

19

3B170UV002

3B170UV002C

20

3B170UV003

3B170UV003C

21

3B170UV003

3B170UV003C

22

3B170UV004

3B170UV004C

23

3B170UV004

3B170UV004C

24

3B170UV005

3B170UV005C

25

3B170UV005

3B170UV005C

26

3B170UV006

3B170UV006C

27

3B170UV006

28

3B170UV007

29

3B170UV007

30

3B170UV008

31

3B170UV008

32

6.14.18.4

24VDC FOR VALVES

W1:1

24VDC FOR VALVES

W2:2

24VDC FOR RTU

TB1:1

24VDC FOR RTU

TB1:2

24VDC FOR RTU STAND BY

TB1:3

24VDC FOR RTU STB

TB1:4

24VDC FOR INTERNAL

TB3:1

24VDC FOR INTERNAL

TB3:2

Hook-up drawing for input of fire alarm panel

DEVICE NAME

TERMINAL

CABLE TAG

I/O LIST TAG

FIRE ALARM TERM.

3B170JB003

3B170JB003

3B170JB003

23

3B170JB003

3B170JB003

3B170JB003

24

3B170JB001

3B170JB001

3B170JB001

25

3B170JB001

3B170JB001

3B170JB001

26

3B160JB001

3B160JB001

3B160JB001

27

3B160JB001

3B160JB001

3B160JB001

28

3B170JB002

3B170JB002

3B170JB002

29

3B170JB002

3B170JB002

3B170JB002

30

3B160JB002

3B160JB002

3B160JB002

31

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 107 OF 119

3B160JB002

3B160JB002

3B160JB002

32

3BSOD001

3BSOD001

3BSOD001

33

3BSOD001

3BSOD001

3BSOD001

34

3BSOD002

3BSOD002

3BSOD002

35

3BSOD002

3BSOD002

3BSOD002

36

3BSOD003

L1

3BSOD003

3BSOD003

37

3BSOD003

L2

3BSOD003

3BSOD003

38

3BSOD004

L1

3BSOD004

3BSOD004

39

3BSOD004

L2

3BSOD004

3BSOD004

40

3BSOD005

L1

3BSOD005

3BSOD005

41

3BSOD005

L2

3BSOD005

3BSOD005

42

3BFAP001

24V DC IN

43 +

3BFAP001

24V DC IN

51 -

6.14.18.5

Hook-up drawing for ON-OFF valve

DEVICE NAME

TERMINAL

CABLE TAG

I/O LIST TAG

TERMINAL

ON-OFF VALVE

3B160PDSL001

NC

3B160PDSL001A

3B160PDSL001

22

3B160UV002

3B160PDSL001

COM

3B160PDSL001A

3B160PDSL001

23

3B160UV002

3B160PDSL002

NC

3B160PDSL002A

3B160PDSL002

22

3B160UV004

3B160PDSL002

COM

3B160PDSL002A

3B160PDSL002

23

3B160UV004

3B160PDSL003

NC

3B160PDSL003A

3B160PDSL003

22

3B160UV005

3B160PDSL003

COM

3B160PDSL003A

3B160PDSL003

23

3B160UV005

3B160PDSL004

NC

3B160PDSL004A

3B160PDSL004

22

3B160UV007

3B160PDSL004

COM

3B160PDSL004A

3B160PDSL004

23

3B160UV007

3B170PDSL001

NC

3B170PDSL001A

3B170PDSL001

22

3B170UV003

3B170PDSL001

COM

3B170PDSL001A

3B170PDSL001

23

3B170UV003

3B170PDSL002

NC

3B170PDSL002A

3B170PDSL002

22

3B170UV004

3B170PDSL002

COM

3B170PDSL002A

3B170PDSL002

23

3B170UV004

3B170PDSL003

NC

3B170PDSL003A

3B170PDSL003

22

3B170UV006

3B170PDSL003

COM

3B170PDSL003A

3B170PDSL003

23

3B170UV006

3B170PDSL004

NC

3B170PDSL004A

3B170PDSL004

22

3B170UV007

3B170PDSL004

COM

3B170PDSL004A

3B170PDSL004

23

3B170UV007

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
COMPANY DOC. No:
CPECC DOC. No:

CPECC

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 108 OF 119

MAINTENANCE AND CHECK-UP OF PIPELINE


The maintenance and check-up necessary for buried pipelines shall be carried out both
through the continuous monitoring of specified parameters from the Dispatching Center
and specially through periodical and programmed inspections along the pipeline, to be
carried out by appointed personnel (line inspector) and in order that events in course, or
which may occur in future, may not cause damages to the pipeline.

7.1

Maintenance of pipeline
7.1.1

Inspection on foot

Two persons will carry out the inspection on foot along the whole pipeline monthly. A
motorize vehicle is provided for this inspection. Each person takes his turn in walking along
the route.
The scope of on foot inspection is to check:
a) Situations that are potentially dangerous for the pipeline;
b)

Product leakage;

c) Shrubs and undergrowth invading the area of the pipeline;


d) The conditions of the marker posts, replacing those which have been removed or
damaged;
e) Anomalous situation in correspondence of road, railway, river crossing;
f)

The condition of the pipeline protection works;

g) Works in progress or already carried out by third parties within the right of way.
The inspection personnel shall maintain good relationship with the owners of the
tenants of the land crossed by the pipeline. This will be helpful for getting information.
A written report is to be made by the inspection personnel after each on foot
inspection, whether or not anomalous situations were observed.

LIBYAN BRANCH
COMPANY DOC. No:
CPECC DOC. No:

CPECC

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES
C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

7.1.2

REV. No: A2

PAGE 109 OF 119

Analyze the possibility of leakage

Analyze the possibility of leakage from the pressure distribution on the console every day.
Get leakage information from computer software each day. Verify it by on foot
inspection.
7.1.3

Pipeline repairing

In case leakage or dents exceed a maximum depth of 6% of nominal pipe diameter, it is


necessary to cut out a cylindrical piece of pipe containing the defect and to replace it with
the same kind of pipe. The repairing procedure is as follows:
a) Shut down the blocking valves of upper stream and down stream of line valve station.
b) Discharge the pipeline pressure through the vent stack of upper stream of line valve
station.
c) Connect the pump to the by pass line of upper stream of line valve station. Pump out the
condensate from the pipeline or substitute the gas inside the pipeline with nitrogen.
d) Digging and substituting the section of defect pipe.

7.2

Monitoring of pipeline from dispatching center


The following parameters of an operating pipeline are to be continuously monitored:
-

Booster station delivery pressure

Intermediate station suction pressure or terminal back pressure

Pipeline flow rate

A leakage that is not macroscopic, however, can hardly be detected on the basis of the
parameters mentioned above, as their values keep changing according to the characteristics
of the product.

LIBYAN BRANCH
COMPANY DOC. No:
CPECC DOC. No:

CPECC

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES
C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 110 OF 119

It is clear that the check up is to be founded mainly on periodical inspections of the pipeline
route, to locate possible leakages or to prevent hazard.
A geometry pig pushed along the pipeline can spot the indentations caused by diggers of
other operating machines as well as ovalisations due to slow land sliding.
A corrosion pig pushed along the pipeline at periodic intervals provides information on
the condition of the internal wall and on the changes occurring with time. This particular
pig measures the reluctance of the magnetic circuit which, as the pig proceeds along the
pipeline, closes between the field poles of pig and tube.
The plotting of signals sent by the pig shows the sections or the areas where erosions or
deep pitting determine a reluctance value higher than that corresponding to a pipe with
smooth internal wall.

7.3

Pipeline inspection
The route inspection shall be done taking into account that no work which may
compromise the safety of the performance of the pipeline are to be carried out within the
ROW. Hence, the activities listed below are subjected to inspections and restrictions:
-

Diggings or earthworks which may reduce or however modify the thickness of the soil
covering the pipeline;

Erection of buildings of any kind;

Digging to open canals or to lay pipes (water, gas, etc.) parallel to or crossing the
pipeline (an authorization is required prior to starting these works).

The inspection of the ROW, to be carried out according to the schedule drawn by the
Maintenance Department, can be of two kinds:
-

Visual inspection, from locations easily accessible with motorized vehicle, from road of
access to the rout and according to an itinerary programmed on a 1:25,000 or
1:50,000scale map.

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
COMPANY DOC. No:
CPECC DOC. No:

CPECC

7.4

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 111 OF 119

Inspection carried out on foot along the whole pipeline route.

Check up and maintenance of pipeline systems


7.4.1

Block valves

As a rule, block valves are lodged in the valve pit, that is the whole of the construction and
fencing works erected above ground, around the operating devices, the branch points and
the auxiliary equipment (transformers, cathodic protection boxes, etc.).

The inspection of valve pits is to ensure that:


-

No leakage can be observed in flanges, plugs, valves or any other part;

The stuffing box of the branch point valves can be adjusted; in case small leakages are
observed, it shall be slightly tightened;

Constructions show no signs of cracks or subsiding;

The fence is intact and in good conditions;

Paints are not worn out before time.

The efficiency of the pipeline system shall be checked according to a program including the
following operations:
-

Valve operational test;

Adjustment of the stuffing box and greasing of the parts as provided for in the valve
maintenance manual;

Cleaning of rooms and equipment;

Cleaning and deweeding in the premises;

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
COMPANY DOC. No:
CPECC DOC. No:

CPECC

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

Retouching or repainting;

Measurements of the electric potential of the pipeline.

PAGE 112 OF 119

When the line valve is tested, needing to be closed and opened completely, a temporary
shutdown of the pipeline is to be agreed with the Dispatching Center. The Dispatching
Center is to be consulted and agreeable, even if the operation is partial, since the limit
switches can have special functions.
Should leakages be detected during the test, this is to be stopped immediately and the valve
is to be brought back to its original opening position. These troubles are to be reported
immediately to the Chief of Maintenance who shall plan for extraordinary measures.
7.4.2
personnel safety

Accident

prevention

and

When entering a valve pit or approaching operating devices or branch points, the person
carrying out the inspection shall comply with the following preventive measures:
-

He shall not smoke;

The pipeline shall be grounded as a protection against stray current surge;

He shall not make use of open flames of any kind;

He shall use explosion proof flash lights;

He shall use anti-spark equipment.

When inspecting pits, and prior to go down, he shall wait to make sure that fresh air has
entered the pit, and shall adopt all the necessary precautions against possible and persistent
toxic vapors. He shall never go down into a pit without having tied around himself a rope
held by a second person out of the pit.
8

SPARE PARTS

8.1

Manual ball valve


Description

Size/type

Quantity

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
COMPANY DOC. No:
CPECC DOC. No:

CPECC

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

Complete valve

Class 1500 1-1/2 reduce bore

Complete valve

Class 800 1-1/2 reduce bore

Complete valve

Class 800 1 full bore

Complete valve (AL330)

Class 800 1 full bore

Complete valve

Class 1500 3/4 full bore

Complete valve

Class 800 3/4 full bore

Complete valve (NPT)

Class 1500 3/4 reduce bore

Complete valve (NPT)

Class 800 3/4 reduce bore

Complete valve (NPT)

Class 800 1/2 reduce bore

10

Soft seal kit

Class 600 12 reduce bore

11

Soft seal kit

Class 600 6 reduce bore

12

Soft seal kit

Class 900 4 reduce bore

13

Soft seal kit

Class 600 4 reduce bore

14

Soft seal kit

Class 600 3 reduce bore

15

Soft seal kit

Class 1500 2 reduce bore

PAGE 113 OF 119

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
COMPANY DOC. No:
CPECC DOC. No:

CPECC

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

Description

Size/type

Quantity

16

Soft seal kit

Class 600 2 reduce bore

17

Soft seal kit

Class 150 2 reduce bore

18

Soft seal kit (AL330)

Class 150 2 reduce bore

19

Seat with insert

Class 600 12 reduce bore

20

Seat with insert

Class 600 6 reduce bore

21

Seat with insert

Class 900 4 reduce bore

22

Seat with insert

Class 600 4 reduce bore

23

Seat with insert

Class 600 3 reduce bore

24

Seat with insert

Class 1500 2 reduce bore

25

Seat with insert

Class 600 2 reduce bore

26

Seat with insert

Class 150 2 reduce bore

27

Special tools

Class 600 12 reduce bore

28

Special tools

Class 900 10 reduce bore

29

Grease

30

Lubricant
loader

PAGE 114 OF 119

1 (5kg each)
injection

LIBYAN BRANCH
COMPANY DOC. No:
CPECC DOC. No:

CPECC

8.2

Gate valves

8.3

Globe valves

8.4

Check valve

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES
C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 115 OF 119

LIBYAN BRANCH
COMPANY DOC. No:
CPECC DOC. No:

CPECC

8.5

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES
C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

Safety relief valves


Description

Drawing no

Quantity

Nozzle d

UN0711/D/SB

Disc d

UN0729/SB

Spring

SS-7/40F/17.2

Spring

SS-7/40/20

Spring

SS-7/40E/23.1

Spring

SS-7/40E/25.5

Spring

SS-7/40E/29.5

Set of gasket

UN0014/504/605/46

Nozzle n

70N026/SB

10

Disc n

70N052/SB

11

Spring

PH-7/150P/64.4

12

Set of gasket

UN0014/230/75

PAGE 116 OF 119

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
COMPANY DOC. No:
CPECC DOC. No:

CPECC

8.6

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

Launcher and receiver


Description

Size

Quantity

Gasket for Q.O.C

36600#

Gasket for Q.O.C

20600#

Gasket for Q.O.C

20900#

Gasket for pig alert

PAGE 117 OF 119

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
COMPANY DOC. No:
CPECC DOC. No:

CPECC

8.7

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

Electric actuator valves


Not require at present time.

REV. No: A2

PAGE 118 OF 119

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
COMPANY DOC. No:
CPECC DOC. No:

CPECC

8.8

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

Solar panel system


Description

Size

Quantity

Solar module

NR100G24

NSCI board + monitor

Fuse set + varistor

Rectifier module

PC-center board

Battery cell

Naps 160pzv2000, 2V cell

Battery cell

Naps 50pzv350, 2V cell

PAC 3200

1
4

PAGE 119 OF 119

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
COMPANY DOC. No:
CPECC DOC. No:

CPECC

8.9

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 120 OF 119

Cathodic protection system


8.9.1

Transformer rectifier

Description

Size
with

Quantity

Conversion
module
auxiliary and time relay

Complete circuit breaker

Spare part for circuit breaker

Complete contactor

Detachable terminal

Colored caps

Signal lamps

Signal lamps holder

Protection relay

10

Measuring instrument voltage

11

Measuring instrument current

12

Measuring instrument potential

13

Buttons

14

Fuse for auxiliary circuit

15

Lighting lamp &1 set fuses

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
COMPANY DOC. No:
CPECC DOC. No:

CPECC

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

8.9.2

REV. No: A2

CPVCM 24V

Description

Size
with

Quantity

Conversion
module
auxiliary and time relay

Complete circuit breaker

Spare part for circuit breaker

Complete contactor

Detachable terminal

Colored caps

Signal lamps

Signal lamps holder

Protection relay

10

Measuring instrument voltage

11

Measuring instrument current

12

Measuring instrument potential

13

Lighting lamp &1 set fuses

PAGE 121 OF 119

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
COMPANY DOC. No:
CPECC DOC. No:

CPECC

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

8.9.3

REV. No: A2

CPVCM 48V

Description

Size
with

Quantity

Conversion
module
auxiliary and time relay

Complete circuit breaker

Spare part for circuit breaker

Complete contactor

Detachable terminal

Colored caps

Signal lamps

Signal lamps holder

Protection relay

10

Measuring instrument voltage

11

Measuring instrument current

12

Measuring instrument potential

13

Lighting lamp &1 set fuses

PAGE 122 OF 119

LIBYAN BRANCH
COMPANY DOC. No:
CPECC DOC. No:

CPECC

8.10

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES
C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

Diesel generator
Description

Size

Quantity

Air filter

901-046

Fuel filter

901-202

Oil filter

901-104

PAGE 123 OF 119

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
COMPANY DOC. No:
CPECC DOC. No:

CPECC

8.11

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

Gas over oil actuator


Description

Size

Quantity

Soft seal kit for B4D

2x1.5 150

Soft seal kit for BT1

4x3 600

Soft seal kit for BT1

4x3 900

Soft seal kit for BT1

6x4 900

Soft seal kit for BT1

8x6 300

Soft seal kit for BT1

8 600

Soft seal kit for BT1

8 900

Soft seal kit for BT2

16x12 600

Soft seal kit for BT2

16x12 900

10

Soft seal kit for BT2

16 600

11

Soft seal kit for BT2

16 900

12

Soft seal kit for BT2

20x16 600

13

Soft seal kit for BT2

32x24 600

14

Soft seal kit for BT2

32 600

PAGE 124 OF 119

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
COMPANY DOC. No:
CPECC DOC. No:

CPECC

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

Description

Size

Quantity

15

Seat with insert for B4D

2x1.5

16

Seat with insert for BT1

4x3 600

17

Seat with insert for BT1

4x3 900

18

Seat with insert for BT1

6x4 900

19

Seat with insert for BT1

8x6 300

20

Seat with insert for BT1

8 600

21

Seat with insert for BT1

8 900

22

Special tool for BT1

8x6

23

Special tool for BT1

8 600#

24

Special tool for BT1

8 900#

25

Special tool for BT1

16x12 600

26

Special tool for BT1

16x12 900

27

Special tool for BT2

16 9 00

28

Special tool for BT2

32x24

29

Special tool for BT2

32

30

Grease

N1 (5kg)

31

Grease

N2 (25kg)

PAGE 125 OF 119

LIBYAN BRANCH
CPECC

COMPANY DOC. No:


CPECC DOC. No:

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES
C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 126 OF 119

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
COMPANY DOC. No:
CPECC DOC. No:

CPECC

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

Description

Size

Quantity

32

Injection loader

(NC)

33

Lubricant injection gun

(ND)

34

Honeywell limit switch

35

Solenoid valve seal kit

36

Frame cylinder, pump and distributor


seal kit or MT 175-I/200 GH

37

Frame cylinder, pump and distributor


seal kit or MT 175-I/70 GH

38

Frame cylinder, pump and distributor


seal kit or MT 100-I/70 GH

39

Frame cylinder, pump and distributor


seal kit or MT 175-I/160 GH

40

Frame cylinder, pump and distributor


seal kit or MT 200-I/200 GH

41

Frame cylinder, pump and distributor


seal kit or MT 120-I/130 GH

42

Frame cylinder, pump and distributor


seal kit or MT 135-I/130 GH

43

Frame cylinder, pump and distributor


seal kit or MT 120-I/100 GH

44

Frame cylinder, pump and distributor


seal kit or MT 160-I/130 GH

PAGE 127 OF 119

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
COMPANY DOC. No:
CPECC DOC. No:

CPECC

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

8.12

Liquid level transmitter

8.13

Liquid level switch

8.14

Flow switch

8.15

Liquid level indicator

REV. No: A2

PAGE 128 OF 119

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
COMPANY DOC. No:
CPECC DOC. No:

CPECC

8.16

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

Fire alarm system


Description

Size

Quantity

LTD

100m

Optical smoke detector

(Series 60)
3

Optical smoke detector Ex

(SLR-E-IS)
4

Interface module
(PIM-420)

PAGE 129 OF 119

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
COMPANY DOC. No:
CPECC DOC. No:

CPECC

8.17

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

Burner system
Description

Size/type

Quantity

Gasket

4150# spiral wound

Gasket

1150# spiral wound

Set fuses

Set of ignition & control


panel lamps

Pilot tip 3604

Thermocouple
k

HE igniter

HE feeder

CR/AL

PAGE 130 OF 119

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
COMPANY DOC. No:
CPECC DOC. No:

CPECC

8.18

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 131 OF 119

Pressure transmitter
Description

Size/type

Quantity

Pressure transmitter type A

Pressure transmitter type B

Pressure transmitter type C

Manifold M264

50

LIBYAN BRANCH
COMPANY DOC. No:
CPECC DOC. No:

CPECC

8.19

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES
C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 132 OF 119

Differential pressure transmitter


Description

Size/type

Quantity

Diff. pressure transmitter type A

Diff. pressure transmitter type B

Manifold M564

50

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
COMPANY DOC. No:
CPECC DOC. No:

CPECC

8.20

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

PAGE 133 OF 119

Temperature transmitter
Description

REV. No: A2

3144PD1A1E1B4M5T1Q4X1

Size/type

Quantity
1

0065N31J0080N2080X1

3144PD1A1E1B4M5T1Q4X1

0065N31J0080N1980X1

3144PD1A1E1B4M5T1Q4X1

0065N31J0080N2280X1

3144PD1A1E1B4M5T1Q4X1

0065N31J0080N2680X1

3144PD1A1E1B4M5T1Q4X1

0065N31J0080D0200F64
R07Q8X1E1

3144PD1A1E1B4M5T1Q4X1

0065N31J0080D0250F46 R16Q8X1E1

3144PD1A1E1B4M5T1Q4X1

0065N31J0080D0350F10 Q8X1E1

3144PD1A1E1B4M5T1Q4X1

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
COMPANY DOC. No:
CPECC DOC. No:

CPECC

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 134 OF 119

0065N31J0080D0330F46 R16Q8X1E1

664HEIJ6M5Q4X1
0065N31N0000N075X1E1

8.21

Flow meter

8.22

Differential pressure switch

8.23

Control valve

8.24

RTU

LIBYAN BRANCH
COMPANY DOC. No:
CPECC DOC. No:

CPECC

8.25

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES
C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

PAGE 135 OF 119

Pipeline
8.25.1

Spectacle blinds

Description

Size/type

Gasket

Octagonal ring 4 900# AISI 316

Gasket

Octagonal ring 16 900# AISI 316

Gasket

Octagonal ring 6 600# AISI 316

Gasket

Octagonal ring 32 600# AISI 316

Gasket

Octagonal ring 16 900# AISI 316

Gasket

Octagonal ring 6 600# AISI 316

Gasket

Octagonal ring 32 600# AISI 316

Gasket

Octagonal ring 4 600# AISI 316

Gasket

Octagonal ring 16 600# AISI 316

10

Gasket

Octagonal ring 8 600# AISI 316

11

Jackscrew

A193B7/A194Gr.2H 3/4X140

12

Jackscrew

A193B7/A194Gr.2H 1X255

13

Jackscrew

A193B7/A194Gr.2H 7/8X155

14

Jackscrew

A193B7/A194Gr.2H 7/8X155

15

Jackscrew

A193B7/A194Gr.2H 1 1/2X360

Quantity

LIBYAN BRANCH
COMPANY DOC. No:
CPECC DOC. No:

CPECC

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES
C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

Description

Size/type

16

Jackscrew

A193B7/A194Gr.2H 1 1/2X360

17

Jackscrew

A193B7/A194Gr.2H 3/4X130

18

Jackscrew

A193B7/A194Gr.2H 1 1/8X225

19

Jackscrew

A193B7/A194Gr.2H 1X170

PAGE 136 OF 119

Quantity

WESTERN LIBYA GAS


PROJECT--ONSHORE PIPELINES

LIBYAN BRANCH
COMPANY DOC. No:
CPECC DOC. No:

CPECC

C-70-C-G-0007-00
WLGP-OG-M-CM-MU-0003

REV. No: A2

8.25.2
and sacrificial anodes

PAGE 137 OF 119

Cathodic protection test points

Description

Size/type

Quantity

Terminal plate

Used for terminal box or test point


STP (type A)

Terminal plate

Used for terminal box or test point


STP (type B)

Magnesium trapezium
anode

8.25.3

Fire fighting equipment

Description

Size/type

Quantity

50kg extinguisher with cover (PTU50)

1000x600x650

12kg extinguisher (A12G)

16

8.25.4

Heat shrinkable sleeves

Description

Size/type

Quantity

HSS

16

25

HSS

32

25

Potrebbero piacerti anche