Sei sulla pagina 1di 4

November 1, 2016

Page 1 of 4
Ref.: SO/QTN/040/16
M/s Al Hassan Engineering Co. S.A.O.G.
Tel.: +968 2481 0575
P.O. Box: 1948, PC: 112, Ruwi
Fax: +968 2481 3412
Muscat, Sultanate of Oman.
Attn.

: Mr. S. Rajesh Estimation Engineer

Subject

: Supply & Application of Cementitious Fire Proofing Works for

Structural Steel.

Project

: New IWPs Sharqiyah Project.

Your Ref.: Email, Dated: June 01, 2016.


Dear Sir,
With reference to your above referred mail for the subject job works as
desired, we are pleased to submit our offer for fireproofing works using
CAFCO Fendolite MII System (manufactured by Promat) for this project.
Our offer is detailed as under:JOB SPECIFICATION :1. Check the existing surface.
2. Supply and apply fireproofing material onto steel structures. The steel
sections up to and including 203mmX203mm shall be protected by solid fill
method and others shall be profile.
MATERIALS SPECIFICATION :1. CAFCO Fendolite MII
2. CAFCO PSK 101
3. CAFCO Plastic Coated Galvanised Mesh.
4. CAFCO Helical CD Weld Pin (Stainless Steel) for structures only.
5. CAFCO Top Coat 200.
6. Silicone Sealant Promaseal Mastic Sealant.

November 1, 2016
Page 2 of 4
Ref.: SO/QTN/040/16
7. SS316L Tie in wire.

OUR SCOPE OF WORK:1. We shall carryout the job as per above specification.
2. Provision of all Fireproofing materials, accessories, etc. required to carryout
the job.
3. We shall provide all the equipments, trained technicians, supervisors, etc.
required to carryout the job as per the above specifications.
4. We shall follow all the necessary QA/QC and safety procedures at site and
shall comply with the standard application procedures.

AHECS SCOPE :1. Touch ups paints for welding (CAFCO Helical CD Weld Pin) areas.
2. Provision of potable water in proper storage tanks, 3-phase electricity,
material storage, equipment handling facilities, disposal of wastage etc.
3. Provision of free accommodation, food, local transport and other
facilities at site.
4. Provision of erected scaffolding at free of cost.
5. Any touch-up / repair of fireproofing works damaged due to other trade
activity.
6. Any approvals required from the local authorities like Civil Defence to be
arranged and provided by the main contractor at no extra cost to M/s.
Swiss Intl LLC.

PRICE :Our offer to carry out fireproofing as mentioned above shall be as per the
attached

November 1, 2016
Page 3 of 4
Ref.: SO/QTN/040/16
Sl
No
.
1.

Materials

Thicknes
s

Fire
Rating
s

Area
[Sq.m]

Unit
Price
[OMR]

Total Price

Medium
density
CAFCO
Fendolite MII
System

46mm

3hrs

62,040.0
0

35.000

2,171,400.
000

PRICE VARIATION:1) The prices given in the above mentioned annexure I are for the said
quantities based on the bill of quantity provided by you and under
assumption of continuous hindrance free work front.
2) All areas shall be measured / re-measure after application.
TERMS OF PAYMENT :To be discussed and mutually agreed.
VALIDITY :Our offer is valid for 60 days from the date hereof.
COMMENCEMENT:To be mutually discussed and agreed upon after signing of contract.
JOB/CONTRACT ACCEPTANCE :It is mandatory to receive our official job acceptance for any contractual
obligations.

November 1, 2016
Page 4 of 4
Ref.: SO/QTN/040/16

FORCE MAJEURE CLAUSE :Standard Force Majeure Clause prevailing in Oman governs our offer.
INSURANCE :Our Employees are covered under Oman Workmen compensation policy
however our quotation for the subject job is based under the presumption that
you have already effected

the necessary / exclusive Insurance coverage to the Machines / Equipment /


Structures, etc., for the damage that might occur during the course of our job
execution.
We trust that you will find our proposal in line with your requirement. Kindly do
not hesitate to contact us in case you require any further information.

Yours truly,
For Swiss International L.L.C.

Jahangir Alam
Sales/Project Engineer
(GSM: 9936 0062)

Potrebbero piacerti anche