Sei sulla pagina 1di 2

Project Name: LNG.

Client: Petroleum Development Oman (PDO)


Contractor: Advanced Oil Field Field Technology
Work Scope: Supply & Application of Cementituos Fireproofing Materials for Steel Structures
Required PFP Thickness: 27mm (all Structures only) for 90min Fire Rating.
Job Status: Jobs in Hand
Location: Near Qarn Alam Area
Required Mobilizations: 01 Nos

Manpower Requirement per Team


Teams
Required Trade

Helper
Jet Wash & Cleaning
Operator
Masking & House Keeping

Helper

Tie/Key Coat

Painter
Helper

Pin Welding, Mesh Fixing & Primer Touch ups


Welder
Carpenter
Shuttering Works
Helper
Nozzleman
M/c Operator
Isoaltek Type MII Application
Masons
Helpers
Repair

Masons

Sealant Application

Helper

Top Coat Application (2 coats)

Painter
Total

Costing Factors & Summary:


Particulars
OHP

Values - Structures
0.25

Custom & Duty on Materials

0.05

Manhour rate per hour

21

Working Hours per day

10.00

Wastage

0.35

Production (Bags/day)

40

Theoretical Coverage at 25mm DFT [sqm/1000kgs]

66

Production (sqm/day)

35.91

Mob/Dmob & Consumable Cost [AED per Sqm]

5.00

Machine Cost [AED per Sqm]

5.00

Requird Fendolite MII Bags


Required No. of Trailer Trips for Mat Delivery
Materials Transport Cost [AED]

6,720.00
8
22,896.00

Total Area [sq.m]

6,000.00

Total Manhours

20,460.00

Total Labour Cost [AED]

429,660.00

Total Materials Cost [AED]

605,381.00

Custom & Duty on Materials

30,269.05

Total Mob/Demob (01 Nos) & Consumable Cost [AED]

30,000.00

Total Machine Cost [AED]

30,000.00

Cost for PDO Approved Pickup with driver [AED]


PDO Training & Medical (@ OMR225 per head) Cost [AED]
Staff Site Visit (OMR 150 per return trip) for 3 Trips [AED]
Total Cost [AED]
OHP [AED]
Total Price [AED]

38,637.00
4,293.00
1,191,136.05
297,784.01
1,488,920.06

Estimated Unit Rate [AED/sq.m]

248.15

Estimated Unit Rate [OMR/sq.m]

26.01

Estimated Unit Rate [OMR/CUM]

963.40

Offered Unit Rate [AED/sq.m]

Potrebbero piacerti anche