Client: PDO

Main Contractor: STS


Project: Production Station 76 at Amal
Scope: Supply and Application of PFP (Chartek 1709+HK-1 Mesh+ Chartek 1709+ Top Coat)
Method of Application: Plural Component Machine
Estimated Area [sq.m]

4000

Required DFT [mm]


Required Chartek 1709 [kg]

8
46,400.00

Required Mat
Chartek 1709 [50kg kits]

Lab Rate

20

Team Members

18

Production

25

Working Hours

10

Unit Cost

Amount - OMR

928

239

221,792.000

HK-1 Mesh [rolls]

32

662.508

21,200.256

Interthane 990 [20 litre pail]

45

19.2

864.000

1500

1,500.000

Materials Transport
PDO Medical (30*225)

5,250.000

Mob/Demob

3,000.000

Consumables

8,000.000

Staff Visit ( 10 times)

2,000.000

Required Days

162.000

Machine Cost

24,300.000

Labour Cost

61,132.075

Total Cost

349,200.331

35% OHP

122,220.116

Offer Price

471,420.447

Unit Price

117.86