Collins High School was constructed in 1976 and has undergone several renovation projects funded between 1997-2008 to address priorities like exterior repairs, mechanical and electrical upgrades, and interior renovations, however, there are still over $4 million in unfunded renovation needs remaining such as site improvements, kitchen upgrades, and student locker renovations. The document provides details on the history of funded and planned renovation projects at Collins High School along with their estimated costs.
Collins High School was constructed in 1976 and has undergone several renovation projects funded between 1997-2008 to address priorities like exterior repairs, mechanical and electrical upgrades, and interior renovations, however, there are still over $4 million in unfunded renovation needs remaining such as site improvements, kitchen upgrades, and student locker renovations. The document provides details on the history of funded and planned renovation projects at Collins High School along with their estimated costs.
Copyright:
Attribution Non-Commercial (BY-NC)
Formati disponibili
Scarica in formato PDF, TXT o leggi online su Scribd
Collins High School was constructed in 1976 and has undergone several renovation projects funded between 1997-2008 to address priorities like exterior repairs, mechanical and electrical upgrades, and interior renovations, however, there are still over $4 million in unfunded renovation needs remaining such as site improvements, kitchen upgrades, and student locker renovations. The document provides details on the history of funded and planned renovation projects at Collins High School along with their estimated costs.
Copyright:
Attribution Non-Commercial (BY-NC)
Formati disponibili
Scarica in formato PDF, TXT o leggi online su Scribd
2001 Power Distribution Funded Completed $211,000 2004 System Improvements Funded Completed $173,000 2007 Furniture Installation Funded Completed $51,000 Need Boiler/Mechanical System Renovation Planning $1,480,000 Need Bathroom/Plumbing System Renovation Planning $620,000 Need Lighting Renovation Planning $714,000
2007 Cabinets, Caulking, Counter tops, Doors, Faucets, Funded Completed $84,000 Kitchen, New Cullinary Arts classroom, New Stoves, New dishwasher, New power, Sinks, faucets 2007 New Small, Contract or Charter School Renovations Funded Completed $912,000 2007 Student Locker Renovation Funded Completed $207,000 Need Student Locker Renovation Planning $23,000 Need Interior Renovation Planning $1,249,000 Need Kitchen and Lunchroom Renovation Planning $132,000
Site Improvement (Priority 4) 49%
1997 Sitework Funded Completed $312,000
Chicago Public Schools
Capital Improvement Program Need Site Improvements Planning $328,000