Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Abstract: The lean construction concept has been introduced successfully into the construction industry to reduce construction wastes. While lean concepts require a rethinking of existing construction processes and practices, there is also a
need for new tools to implement lean thinking. In addition, while lean can improve project time and cost performance, it
may also have an impact on sustainability, which mainly focuses on reducing environmental impact of construction. This
paper describes the implementation of lean construction and its implication on environmental sustainability from a contractor perspective through a case study. The study observed waste in both project-level contractor coordination and operationlevel construction performance. A vertically-integrated scheduling system that features location-based look-ahead scheduling and graphic weekly work planning was developed to improve project-level contractor coordination. To implement
waste elimination solutions at the operation level, construction simulation and 3-D visualization were applied to facilitate
lean implementation. Meanwhile, the impact of lean on sustainability were observed and discussed.
Key words: lean construction, concrete construction, sustainability, scheduling, simulation, visualization.
Resume : Le concept de construction allegee a ete introduit avec succe`s dans lindustrie de la construction afin de reduire
les dechets de construction. Bien que les concepts alleges demandent de repenser les procedes et les pratiques de construction actuels, il existe un besoin de developper de nouveaux outils pour implanter la pensee allegee. De plus, la methode allegee peut ameliorer le temps consacre au projet et le rendement economique, elle peut aussi avoir un impact sur la
durabilite, qui porte principalement sur la reduction de limpact environnemental de la construction. Cet article decrit limplantation dune construction allegee et de son implication sur la durabilite environnementale du point de vue de lentrepreneur grace a` une etude de cas. Letude a examine les dechets du point de vue de coordination de lentrepreneur au
niveau du projet et le rendement operationnel de la construction au niveau de loperation. Un syste`me dordonnancement a`
integration verticale qui comporte un ordonnancement a` lecture anticipee base sur lemplacement et une planification graphique hebdomadaire a ete developpe afin dameliorer la coordination avec lentrepreneur au niveau du projet. Pour implanter les solutions delimination des dechets au niveau operationnel, une simulation de la construction et une
visualisation tridimensionnelle ont ete utilisees pour faciliter limplantation allegee. Entretemps, limpact de la methode allegee sur la durabilite a ete note et examine.
Mots-cles : construction allegee, construction en beton, durabilite, ordonnancement, simulation, visualisation.
[Traduit par la Redaction]
Introduction
Lean is a proven management strategy for achieving significant and continuous improvement through elimination of
all waste of time and other resources (Womack and Jones
2003). Lean construction has been used to improve planning
practice, construction operations, and the project delivery
Received 7 February 2010. Revision accepted 20 January 2011.
Published on the NRC Research Press Web site at cjce.nrc.ca on
15 February 2011.
L. Song.1 Department of Construction Management, University
of Houston, Houston, TX, USA.
D. Liang. Department of Construction Engineering &
Engineering Technology, Texas Tech University, Lubbock, TX,
USA.
Written discussion of this article is welcomed and will be
received by the Editor until 31 July 2011.
1Corresponding
doi:10.1139/L11-005
Field observations
The concrete construction company involved in this study
was new to lean and sustainability applications and the company intended to conduct a pilot study to better understand
the application of lean in concrete construction and its potential impact on sustainability. A typical project of the contractor was identified as a case study and the project
involves a mixed-use, 30-story, reinforced concrete residential building. Daily field observation of the concrete construction operation was made for three consecutive months.
In the context of lean construction, waste refers to any resources consumed by activities that do not add value to meet
the needs of a client. Traditionally, many productivity studies have been mainly focused on improving individual construction activities. Lean construction also focuses heavily
on the management of interactions among different trades
and the elimination of waste associated with coordination issues (Ballard 2000b). Therefore, in this case study, it was
351
decided that field observations would be made on both individual activities at the operation level and the coordination
of different trades or subcontractors at the project level. The
following two subsections describe waste identified as well
as lean-inspired solutions.
Waste at the project level
At the project level, close coordination of different trades
is crucial to project success. The concrete construction process consists of formwork erection, rebar and embedment installation, concrete placement and curing, and formwork
removal. In addition to the concrete contractor, several other
contractors were involved in the sample project, including
the general contractor and several subcontractors for rebar,
plumbing, insulation, and electrical systems. Coordination
issues among contractors were found to have caused schedule delays, and several observations that are of representative nature are briefly described below.
First, during weekly planning, there was inadequate review and analysis of constraints, which caused delays. For
example, the direction of post-tensioning cable runs was
changed by the contractor to ease concreting work, and this
change was implemented but without appropriate approval
from the engineer. The general contractor spotted this
change, halted the construction, and called for an engineering review to evaluate its impact. Although the change was
eventually approved, delay had been incurred. Had this issue
been identified and solved through more proactive lookahead scheduling, the delay would have been avoided. Second, delays due to unbalanced crew productivity rates and
space conflicts were not uncommon. For example, a slab
formwork crew had to slow down to avoid space conflict
with a crew working on a shear wall. In addition, when a
crew was rushed or several trades were stacked together,
safety and quality also became real concerns. Third, some
subcontractors took a very narrow view of weekly scheduling by focusing only on their own work. This resulted in coordination problems and contributed to the chaotic behavior
of the operation. From a sustainability perspective, these delays and idleness of crews and equipment can also cause unnecessary energy consumption and air emissions. In fact, the
power and fuel consumption represents about 1.2% of the
total cost of a building construction project (DOC 2005),
while construction activities produce approximately 1.7% of
total US greenhouse gas emissions (EPA 2009). Although
this impact appears to be small from an individual contractor standpoint, the cumulative impact on sustainability can
be significant considering the enormous size of the construction industry. In summary, these observed issues are directly
or indirectly related to the lack of effective team coordination and look-ahead scheduling practice. The last-planner
methodology was proposed for the look-ahead scheduling
process.
Last planner is a lean-production-based project-planning
methodology that integrates a multiple-level planning framework that includes master scheduling, look-ahead scheduling, and weekly work planning to improve the reliability of
work flow (Ballard 2000a). The master schedule identifies
work packages and the overall execution strategy of a project. The look-ahead schedule is a detail plan showing work
to be done within a look-ahead time window, such as six
Published by NRC Research Press
352
and Kim 2008). On the other hand, several proposals for reducing environmental impact were dropped by the contractor due to various cost and contracting reasons. As an
example, the concrete supplier was selected solely on the
cost basis regardless of transportation distance and associated environmental impact, since the project is a lump-sum
contract and the contractor has little incentive to address
sustainability issues. Other environmentally friendly solutions, such as self-consolidating concrete and concrete recycling, were not considered during design and contracting
stages and they would have been applicable if the contractor
had been involved in the design stage. In summary, the
value concept of lean must be aligned with that of sustainability to ensure a winwin of both lean and green.
Additionally, the traditional contracting method also needs
to be adjusted to emphasize the environmental aspect of
construction and promote contractors early involvement in
design to provide better sustainable design and construction
solutions.
While there are many forms of wastes identified through
the pilot study, two representative types of wastes that are
related to slab formwork installation and bulkhead installation and removal were presented in this pilot study. The objective was to demonstrate waste elimination, challenges
encountered, solutions developed, and the implication on
sustainability. These case studies are discussed in a latter
section titled Promoting changes at the operation level.
fortunately, the calendar format was found to be less effective in conveying scheduling information for the day-to-day
crew coordination. For example, the spatial interaction
among different crews, material layout, and access constraints are not explicitly shown in a calendar schedule, thus
discourage the crews to discover potential performance issues. Therefore, there is also a lack of an effective weekly
or daily scheduling method that can facilitate scheduling at
the crew operation level.
In summary, a better integrated scheduling method that
supports scheduling efforts at different organization levels
with different levels of details and time horizons is desired.
Proposed scheduling system
The proposed vertically-integrated scheduling system supports scheduling at three different levels: (1) project master
scheduling at the general contractor level, (2) 3 to 6 weeks
look-ahead scheduling at the subcontractor level, and
(3) weekly or daily work planning at the field operation
level. Moreover, these schedules of different resolutions
must also be integrated so that information can be shared
freely among them. A literature search was conducted with
an attempt to find a system that meets the above requirements. Chua et al. (2003) developed a look-ahead planning
tool, integrated production scheduler (IPS), based on last
planner and the theory of constraints. Also based on last
planner, Choo et al. (1999) developed a program, WorkPlan,
to guide foremen in doing constraint analysis and weekly
work planning. However, both programs are essentially
based on CPM and bar charts, or their variations, whose
drawbacks have been discussed previously. While CPM and
bar-charts remain as the methods used for master scheduling, it was concluded that a new system for look-ahead
scheduling and weekly or daily work planning were needed.
Location-based look-ahead scheduling
One of the primary goals of look-ahead scheduling is to
shape a continuous and smooth work flow by fine-tuning
work sequence and balancing the work-progress rate. Kenley
(2005) argued that construction projects involve activities
that are repeated in varying quantities in multiple locations
and that these activities should be viewed as a continuous
flow instead of as discrete activities, as they are in CPM.
Based on this definition, a location-based scheduling (LBS)
method, also called flow-line or linear scheduling, was suggested for look-ahead scheduling, and commercial software
packages, such as DYNAProject and Vico Control, were
used to show that lean principles are better supported using
LBS (Kenley and Seppanen 2009). For the same reason, in
this study, LBS was adopted as the underlying algorithm for
the look-ahead scheduling of repetitive concrete construction
work.
An example of an LBS chart for a concrete construction
operation is shown in Fig. 1. An activity such as formwork
installation is represented by a sloped line, called a flow
line, in a two-dimensional time-and-space coordinate system. Activities are represented by different flow-line colors
or styles. The horizontal axis represents time, and the vertical axis is the location of an activity e.g., a concrete pour
section. The slope of a flow line represents its productivity
rate, which can be affected by many factors, such as work
353
354
tem contains two software components, which are LBSbased look-ahead scheduling and graphic weekly or daily
work planning. These components were developed using
Microsoft Excel and Visual Basic for Application (VBA).
The system also interfaces with two popular CPM-based
scheduling tools, Microsoft Project and Primavera Project
Planner, with which schedules in the form of CPM and barcharts are developed. Integration of these three scheduling
methods simplifies the sharing of scheduling information
and eliminates almost entirely the need for data re-entry.
Discussion of the software development is beyond the scope
of this paper, but the main features of the developed system
are described below from an end-user perspective.
Look-ahead and weekly schedules are first developed in
Microsoft Project or Primavera Project Planner and then
they can be converted into the LBS format for look-ahead
scheduling. Before the conversion, the system allows users
to define and filter activities and to specify flow-line style,
the look-ahead time window, and the sequence of work locations. Screenshots of the user interface are shown in
Fig. 3. The look-ahead schedule in bar-chart format and the
converting options are shown in Fig. 3(a), and a converted
LBS chart is shown in Fig. 3(b), along with a dialog box
showing a tasks attributes.
The converted LBS schedule provides a base schedule
that allows users to add detailed tasks, shape work flow, adjust buffers, and balance productivity rates. For constraint
analysis, in addition to the time and space constraints shown
in LBS, other types of constraints can be traced as task attributes, such as those shown in Fig. 3(b). While some attributes can be transferred from CPM schedules, new data
can be added manually or even automatically from external
applications. For example, the system can pull weather forecasting information automatically from an online weather
forecast service (National Weather Service 2005), as shown
in Fig. 3(b). This function enables users to factor weather
conditions into scheduling. Easily accessible attribute data
and constraint information allow users to better analyze constraints and to track outstanding issues.
Published by NRC Research Press
355
Fig. 3. Bar chart and converted LBS chart. (a) Master schedule and exporting options; (b) LBS chart and task attributes.
In the weekly work-planning component, users can generate a base daily graphic schedule by transferring information
from a look-ahead schedule. To achieve this, users must first
define task locations in a construction layout diagram, which
can be prepared with the drawing tools embedded in Microsoft Excel or by importing a layout drawing from CAD programs. Based on these inputs, the system can automatically
generate daily graphic schedules for each working day
within a user-specified time frame, as shown in Fig. 4.
These schedule charts describe activities and their locations
on the site-layout diagram, and additional constraint information can be added graphically to the chart, and then
shared with others.
The use of this computerized program made the second
attempt of applying the proposed vertically-integrated scheduling method successful. The time required to manually prepare LBS and graphical schedules were eliminated and
schedulers spent more valuable time in analyzing, optimizing, and sharing information with other project participants.
As a result of this careful scheduling and closer coordination, several schedule delays related to unnecessary work
discontinuity and stack of activities were forecasted and
avoided later.
On the sustainability front, the new scheduling system
does not appear to immediately affect sustainability. However, effective scheduling improves work flow and minimizes conflicts, which reduce project duration and
unnecessary idling, thus making less of an environmental
impact. For example, the pull-driven approach of last planner effectively minimizes unnecessary floats attached to repeating activities and ensures a continuous work flow that
is more economically and environmentally efficient. Better
yet, there is no or little additional cost associated with better
management practices to achieve positive sustainability imPublished by NRC Research Press
356
357
Fig. 7. Productivity improvement against the crane demand.
sistent with the actual observations in the field. More importantly, the experiment results inspired discussions among
different crews regarding the impact of this change and the
need for collaboration. From a sustainability perspective, reducing waiting time of the formwork crew and unnecessary
movement of the crane represents a positive environmental
impact. For example, tower crane is often regarded as a top
energy guzzler on a building construction project and a large
amount of fuel and energy is needed to support its operation.
Although the overall spending on power and fuel represents
only about 1.2% of building construction costs (DOC 2005),
considering the enormous size of the construction industry,
even a small improvement can lead to substantial economic
and environmental savings.
Training on changed processes
Bulkhead installation and removal are presented here to
illustrate how process visualization has helped in communicating a changed process to the operation-level workforce. A
bulkhead is a temporary formwork strip that blocks fresh
concrete from a section of forms or closes the end of a
form at a construction joint. Holes are first drilled into the
strip to allow rebar, cables, and conduits to run through,
then the bulkhead is installed along the edges of a slab
formwork. This is followed by the placing of rebar, cables,
and conduits, and finally by concreting. After the concrete
has cured, the bulkhead is removed using prying tools. Carpenters normally install the bulkhead as one piece to save
time, but this makes bulkhead removal difficult and time
consuming because the bulkhead as a whole piece is blocked
by conduits, rebar, and cables running through the concrete
slab. Intense prying actions may also break the concrete slab
edge and cause quality problems. These problems can be
avoided by revising the installation process. The new procedure calls for an additional step of cutting the bulkhead horizontally into two pieces along the centerline, through which
most of the rebar and cables run. The bottom piece of the
bulkhead is installed first, followed by the routing of cables,
conduits, and rebar, and finally by the installation of the top
piece of the bulkhead.
Published by NRC Research Press
358
An issue in implementing this change is educating workers about the change. The majority of workers in the sample
project cannot communicate very well in English, and they
also relocate frequently from job to job. These issues made
the proposed change difficult to implement effectively and
consistently throughout the company. Therefore, effective
training was necessary, and the training format was expected
to be highly graphical and easy to understand without relying heavily on verbal or written instructions. Three-dimensional process visualization can easily illustrate the process
change, and the underlying model can be updated for future
continuous-improvement efforts. Therefore, process visualization of the bulkhead installation process was developed
using Autodesk 3ds Max. The viewing perspective is fixed,
and the scene, consisting of about 3000 frames, is then rendered. Figure 8 shows a screenshot of the process animation,
which proved to be very effective in explaining the changes.
With the new procedure, the time required for bulkhead installation is slightly increased, but bulkhead removal time is
significantly reduced, and damage to concrete is minimized.
Figure 9 shows a comparison of bulkheads removed with the
old procedure and the new procedure. These two pictures indicate that the new procedure allows the top and the bottom
pieces of a bulkhead to be removed easily without painstakingly shattering it into debris for removal, as is the case with
the old procedure. Some of the bulkheads can also be reused. The 3-D visualization was easily understood by the
crews and it was also used in several other job sites. From
the sustainability perspective, according to EPA (2009),
wastes from construction projects account for about 25% of
the total US solid waste volume and about 50% of these
construction wastes are disposed in a landfill. Although a
minor change, the revised bulkhead work process not only
improves time and quality performance but also brings positive environmental impact by reducing construction wastes
and promoting material re-use.
Fig. 9. Bulkhead removal with (a) the old procedure and (b) the
new procedure.
Conclusions
As shown in this case study, waste in construction can be
found in areas from contractor coordination to individual
work procedures, and much of this waste can be traced to a
lack of planning and to a resistance to changing the status
quo. At the project level, lack of coordination among contractors and crews was cited as the major factor contributing
to project delay. To improve the coordination, a verticallyintegrated scheduling system was developed and it features
an interface with CPM-based schedules, a location-based
look-ahead scheduling algorithm, and a graphic weekly
planning method. Although the immediate application of
this system is for repetitive concrete building construction,
day-to-day operations performed by many subcontractors
are essentially repetitive, and these contractors face scheduling problems similar to those that are addressed in this paper.
At the operation level, waste is pervasive, and many solutions are seemingly straightforward. However, their implementation may well be resisted by the operation personnel
for many reasons. Among them are a lack of understanding
of the benefits of change and inadequate training on the revised processes. Simulation was found to be very valuable
in identifying the need for changes and evaluating the benefits of lean thinking prior to field implementation. More importantly, it can inspire the talk among project members for
collaboration and continuous improvement. Furthermore, effective training is an important step for implementing
changes. Three-dimensional process visualization offers a
self-explanatory way to educate work-force on revised work
processes.
From a sustainability perspective, lean can result in environmental impacts of different natures (e.g., negative, positive, or neutral) and magnitudes (e.g., negligible or
Published by NRC Research Press
significant). A contractors narrower view of lean that focuses only on economical measures may actually result in a
negative impact on sustainability. Therefore, the value defined in lean must be aligned with that of sustainability to
achieve green-value while improving time and cost performance. Furthermore, at the project management level,
improving management practices using lean concepts incurs
little or no additional cost for achieving both lean and
green values. This free green approach provides a
unique and low-cost strategy in achieving sustainability. At
the field operation level, to promote effective waste-elimination that is of value to both lean and sustainability, innovative contracting methods should be applied to emphasize the
environmental aspect of construction and promote contractors early involvement in design to provide better sustainable design and construction solutions.
References
Bae, J., and Kim, Y. 2008. Sustainable value on construction projects and lean construction. Journal of Green Building, 3(1):
156167. doi:10.3992/jgb.3.1.156.
Ballard, G. 2000a. Last planner system of production control. Ph.D.
dissertation, University of Birmingham, Birmingham, UK.
Ballard, G. 2000b. Lean project delivery system. Lean Construction
Institute. Available from http://www.leanconstruction.org/lpds.
htm [Accessed on 29 July 2008].
Bovey, W.H., and Hede, A. 2001. Resistance to organizational
change: The role of defense mechanisms. Journal of Managerial
Psychology, 16(7): 534548. doi:10.1108/EUM0000000006166.
Choo, H.J. 2003. Distributed planning and coordination to support
lean construction. Ph.D. dissertation, University of California,
Berkeley, Calif.
Choo, H.J., Tommelein, I.D., Ballard, G., and Zabelle, T.R. 1999.
WorkPlan: Constraint-based database for work package scheduling. Journal of Construction Engineering and Management,
125(3):
151160.
doi:10.1061/(ASCE)0733-9364(1999)
125:3(151).
Chua, D.K.H., Shen, L.J., and Bok, S.H. 2003. Constraint-based
planning with integrated production scheduler over the Internet.
Journal of Construction Engineering and Management, 129(3):
293301. doi:10.1061/(ASCE)0733-9364(2003)129:3(293).
Davis, K.A., and Songer, A.D. 2009. Resistance to IT change in the
AEC industry: Are the stereotypes True. Journal of Construction
Engineering and Management, 135(12): 13241333. doi:10.
1061/(ASCE)CO.1943-7862.0000108.
Department of Commerce (DOC). 2005. 2002 economic census, industry summary: Construction. Subject series, EC0223SG-1,
Economics and Statistics Administration, U.S. Census Bureau,
Wash.
Environmental Protection Agency (EPA). 2009. Potential for reducing greenhouse gas emissions in the construction sector. Available from http://www.epa.gov/sectors/pdf/
construction-sector-report.pdf [Accessed on 8 December 2010].
Forsberg, A., and Saukkoriipi, L. 2007. Measurement of waste and
productivity in relation to lean thinking. In Proceedings of the
15th Annual Conference of the International Group for Lean
359
Construction, East Lansing, Mich., 1820 July 2007, International Group for Lean Construction (IGLC), pp. 6776.
Halpin, D.W., and Kueckmann, M. 2002. Lean construction and simulation. In Proceedings of the 2002 Winter Simulation Conference, San Diego, Calif., 811 December 2002. Edited by E.
Yucesan, C. Chen, J.L. Snowdon, and J.M. Charnes. WSC Foundation (WSCF), pp. 16971703.
Halpin, D.W., and Riggs, L.S. 1992. Planning and analysis of construction operation. Wiley, New York.
Harris, R.B., and Ioannou, P.G. 1998. Scheduling projects with repeating activities. Journal of Construction Engineering and Management,
124(4):
269278.
doi:10.1061/(ASCE)07339364(1998)124:4(269).
Hinze, J.W. 2008. Construction planning and scheduling, 3rd ed.,
Pearson Education, Upper Saddle Rive, NJ.
Howell, G.A., and Ballard, G. 1998. Implementing lean construction: Understanding and action. In Proceedings of the 6th Annual Conference of the International Group for Lean
Construction, Guaruja, Brazil, 1315 August 1998, International
Group for Lean Construction (IGLC), pp. 19.
Jongeling, R., and Olofsson, T. 2007. A method for planning of
work-flow by combined use of location-based scheduling and
4D CAD. Automation in Construction, 16(2): 189198. doi:10.
1016/j.autcon.2006.04.001.
Kenley, R. 2005. Dispelling the complexity myth: Founding lean
construction on location-based planning. In Proceedings of the
13th Annual Conference of the International Group for Lean
Construction, Sydney, Australia, 1921 July 2005, International
Group for Lean Construction (IGLC), pp. 245251.
Kenley, R., and Seppanen, O. 2009. Location-based management
for construction: Planning, scheduling and control. Spon Press,
London, UK.
Koskela, L. 1992. Application of the new production philosophy to
construction. Tech. Rep. 72. Center for Integrated Facilities Engineering, Department of Civil Engineering, Stanford University,
Stanford, Calif.
Lapinski, A.R., Horman, M.J., and Riley, D. 2006. Lean processes
for sustainable project delivery. Journal of Construction Engineering and Management, ASCE, 132(10): 10831091.
Mastroianni, R., and Abdelhamid, T. 2003. The challenge: the impetus for change to lean projet delivery. In Proceedings of the
11th Annual Conference of the International Group for Lean
Construction, Blacksburg, Va., 2224 July 2003, International
Group for Lean Construction (IGLC), pp. 112.
National Weather Service. 2005. National Digital Forecast Database (NDFD) Simple Object Access Protocol (SOAP) Web service. Available from http://www.weather.gov/xml/ [Accessed on
29 July 2008].
Salem, O., Solomon, J., Genaidy, A., and Luegring, M. 2005. Site
implementaiton and assessment of lean construction techniques.
Lean Construction Journal, 2(2): 121.
Tommelein, I.D. 1998. Pull-driven scheduling for pipe-spool installation: Simulation of lean construction technique. Journal of
Construction Engineering and Management, 124(4): 279288.
doi:10.1061/(ASCE)0733-9364(1998)124:4(279).
Womack, J.P., and Jones, D.T. 2003. Lean thinking: Banish waste
and create wealth in your organization. Free Press, Detroit,
Mich.
Copyright of Canadian Journal of Civil Engineering is the property of Canadian Science Publishing and its
content may not be copied or emailed to multiple sites or posted to a listserv without the copyright holder's
express written permission. However, users may print, download, or email articles for individual use.