Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
com
27th InternationalConferenceofthe
TOCPractitionersAlliance TOCPA
www.tocpractice.com
August1618,2016Johannesburg,SouthAfrica
Exploitationofthe
CriticalChain
Thuso Machaba, Babock, South Africa
17th 18th August, 2016
www.tocpractice.com
THUSO
Thuso Machaba was born on August
20, 1987 in Limpopo. He studied
Metallurgy Engineering at University
of Johannesburg. In 2011, he started
working at Crown Cast foundry, where
he was introduced to TOC. In the year
2013, he joined Rapid Allweiler pumps
where he worked as a Metallurgist. In
2014, he Joined Babcock as a Bill of
Material coordinator. He is currently
involved
with
boiler
shutdown
projects, where he is using CCPM
technology to run the sub-projects
assigned to him.
Placeforthephotoofthe
presenter
www.tocpractice.com
INTRODUCTION
Extended damage to boiler tubing was found during tube
thickness inspections in the primary reheater, resulting in
significant more work-scope than was predicted.
It extended the outage duration by one month.
The estimated cost ramification, due to the increase in time, for
the client, is in the order of R 70 000 000
Project:
Re-planned duration, catering for additional welding scope: 71
days
It forced the Primary reheater path to become the critical chain
of the project
27th InternationalConferenceoftheTOCPractitionersAlliance TOCPA
www.tocpractice.com
INTRODUCTION
TOC five focusing steps:
1. Identify the constraint
2. Exploit the constraint
3. Subordinate to the constraint
4. Elevate
5. Repeat / go back to step 1
20
25
30
www.tocpractice.com
Constraint 1
www.tocpractice.com
Constraint 2
Limited space to work in was identified as the second bottleneck, as
we had to wait for butt welds to be x-rayed, before we could gain
access to the next set of elements.
Four work areas pulled open, between the elements, were
considered optimal by the workforce, and they had done
calculations to support the claim.
Investigation revealed that more areas could be opened at times,
and the work areas were later increased to 7.
Average production per area was increased to: 49 (7 butts /welder X
7 areas)
www.tocpractice.com
Results
www.tocpractice.com
ButtWeldGraph
www.tocpractice.com
Constraint3
www.tocpractice.com
Results
By changing the construction methods we manage to pull back the path
so that it was no longer the critical chain of the project.
Project finished well before the project due date- more than a month
earlier than planned.
The client had no additional replacement cost, due to time overruns,
and saved in maintenance costs as the path was completed early.
All of which, can directly be contributed to the exploitation that was
done, very good ideas generated by the team and the team work that
was established in the area.
www.tocpractice.com
I THANK YOU!!!!