Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
drum from the top of the unit. There are many girders located within the main boiler support steel. Similar sized girders
are used for supporting the fuel silos and the airheater.
MAIN-GIRDER ERECTION
Main-girder erection is one of many rigging problems of the structural-steel erection process. The most accepted method
of lifting the heavier girders is as follows: Once the girder is raised above the column tops, bring the girder parallel to the
front of the boiler. The girder can then be connected to the upper ends of the columns. Once the girder is in place,
intermediate steel can be installed to tie all of the upper steel together. Coordinated radio communication, highly
experienced operating engineers and rigging supervisors, and first-class equipment are imperative for successful girder
erection.
CYCLONES
The recycle cyclones can be partially ground-assembled and then set in-place once the second tier of boiler structural
steel has been erected and bolted. The lower cone sections are ground assembled with the cones inverted, then set into
the structural support ring. This is followed by ground assembly of cyclone barrels and top.
The refractory lining system for the recycle cyclones will be installed after the cyclones have been erected, assembled
and fully welded.
Furnace Gas
Outlet Duct
Furnace Rear
Wall Tubes
Seal Pot
Solids Return
To Furnace
CYCLONE
CONE
RAISING A DRUM
The drum is raised parallel to the ground. Based on the lifting lugs welded on the drum in the shop, the location of the
support steel for the load blocks can be determined before construction is started. A set of "cat heads" (a temporary
support for the upper portion of the block-and-tackle arrangement which is used to raise the load) rests on top of the
support steel, through which the upper load block is pinned.
*The block can rotate according to the angle of the drum.
The steam drum is usually brought inside the furnace cavity, and off-loaded. The line-pull two-drum hoist that is used for
lifting is usually located on the ground with the two load lines following a column line up to the top blocks hanging in the
4
cat heads. Because of the inner dimensions of the structural steel and the location of the cat heads, an outhaul may be
used to keep the drum from drifting into the steel work. Proper location of all rigging is important because of the height of
the boiler and the lifting distance.
Steam drum
PRESSURE-PARTS SUPPORT-STEEL ERECTION
While the steam drum is being erected, the pressure-parts support steel can be installed. This steel, located at the top of
the unit, supports the weight of the boiler. Unlike conventional structures that are built from the ground up, most modern
boilers are built from the top down, with the furnace suspended by constant load springs (locked) and the backpass
suspended by rigid hanger rods all from the main girders. This permits the furnace to expand upward and the backpass to
expand downward during the start-up of the plant. The correct setting of the pressure-parts support steel is very important
because every part of the boiler is located with respect to this steel. It controls all elevations and is continually used as a
reference to align the different components as they are erected.
The refractory lining system of the sidewalls and floor of the FBHE should be installed after the platework has been
erected and fully welded but before the tube bundles are installed. The roof should be lined at grade in an inverted
position so that the refractory (castable) may be poured onto the roof panels.
Seal Pot
Fluidizing
Air Nozzle
Furnace
Fluid Bed
Heat Exchanger
Toggle
Expansion
Joint
FBHE Heat
Transfer Surface
Solids Return
to Furnace
FBACs which are used to cool the bottom ash before it is discharged to the bottom ash conveyor.
The FBAC is composed of platework and lined with refractory (both for insulation and erosion resistance). Erection of the
FBAC should take place after vertical erection access to the front of the boiler is no longer required.
The refractory lining system of the sidewalls and floor of the FBAC should be installed after the platework has been
erected and fully welded but before the tube bundles are installed. The roof should be lined at grade in an inverted
position so that the refractory castable may be poured onto the roof panels.
Typical Cooling Surface
(Feed Water or Cooling Water)
Cooling Surface or
Air Compartment
Rotary
Valve
Ash Inlet From
Furnace
1560 - 1650 F
850 - 900 C
Ash Discharge
400F / 200C
(Typical)
Fluidizing Air
From Blower
Refractory- Lined Box
12 in./ 300 mm thick
Oversized Ash
Discharge
Gravel Screw
Cooler
Water Cooled
Valve Shaft
Hydraulic
Actuator
Assembly
Plug
Valve Seat
Refractory Lined
Valve Body
SEAL POTS
Seat Pots, one- for each cyclone. Each seal pot directs hot solids to both the lower furnace and to its attendant FBHE.
Each seal pot is composed of platework and lined with refractory (both for insulation and erosion resistance). The seal
pots can be erected as the second tier of boiler structural steel is erected.
The refractory lining system of the Seal Pots should be installed after the platework has been erected and fully welded.
After the stainless steel refractory anchors have been installed, the back up lining System should be cast on all down
hand surfaces and gunned on walls and overhead surfaces. The service lining must be formed and cast.
FUEL
SILO
HOPPERS
SEAL POTS
BUCKSTAY ERECTION
The buckstays are structural shapes that restrain movement of the waterwalls caused by fluctuation in furnace pressure.
Buckstays should be temporarily set, prior to furnace and backpass wall erection, on the boiler steel elevation closest to
the buckstay's final location. After the furnace and backpass panels are aligned, buckstays can be installed.
Backpass
buckstays
Combustor
buckstays
SOOTBLOWER ERECTION
Cranes can be used to raise the retractable backpass sootblowers and set them on the grating nearest
their correct elevations. The type of fuel to be burned determines the number, type, and location of the
blowers. Mounted horizontally, they have a round tube or lance that is rotated, extended and retracted by
a driving motor(s).
These are long retractable blowers, 'Which can be inserted up to a distance of either full boiler width, or one half the
width of the boiler, depending upon available space and owner preference. These blowers are located in the backpass of
the boiler and extend between the sections of the superheater, reheater and economizer to clean the convection
heat-absorbing surfaces during steam generator operation. Retractable blowers are also used to clean the airheaters.
10
WATERWALL ERECTION
Once the sootblowers and buckstays have been laid on the grating temporarily, the waterwalls which form the sides of the
furnace can be erected. The water-walls are sections of tubes that are fin welded together into a gas-tight panel. They
conduct a mixture of steam and water upward as heat is applied from the furnace side. The walls extend from the base of
the boiler up to the steam-drum level.
Typically about 10 feet wide and 65 feet Iong, waterwall panels are brought into the furnace on a flatbed truck or its
equivalent. Because they are so Iong and flexible, the biggest problem with these panels is upending them. Two lines are
needed. The crane in the hole lifts the top line; a cherry picker, the other. Sometimes, a special lifting device distributes
the weight so the panel will not buckle. This requires that several slots be cut in the welded web between the tubes. A bar
welded to a small T-beam is inserted and pinned on the back. This device assists in keeping the panel straight along its
width during upending process. When the panel is vertical, it is lifted up to its final position.
Combustor Water Walls
COMBUSTOR ROOF PANEL ASSEMBLIES
LEFT SIDEWALL
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
RIGHT
SIDEWALL
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
LEFT SIDEWALL
RIGHT SIDEWALL
BACKPASS REAR WALL ASSEMBLIES
ECONOMIZER ERECTION
11
The economizer, located just above the air preheater, can be erected. This is a heat recovery device designed to transfer
heat from the exiting flue gases to the incoming, boiler feedwater. The economizer consists of an interconnected
horizontal bare tube array. The upper ends of each economizer assembly connect to the outlet header, which is already in
place above the roof tubes.
Economizer assemblies are raised into place from the around with a tugger rigged in the area of the outlet headers.
Banks of economizer elements can be pre-assembled in groups. Pins and rods usually support the assemblies directly to
lugs welded to the bottom of the intermediate headers. Because the economizer tubes are often fabricated in a staggered
pitch to increase heat transfer and minimize space requirements, fitting the last few elements sometimes presents a
rigging problem. It is difficult to pass hoisting falls through the staggered tubes. This often means that the already
installed elements must be spread apart and the side walls must be moved out.
Hanger Tubes
Flue Gas from Cyclone
Superheater
Steam Cooled
Wall Tubes
Reheater
Economizer
Fly Ash Hopper
12
ECONOMIZER
HOPPER
START-UP BURNER ERECTION
After the lower waterwall panels are in place, start-up burners can be attached to their respective seal boxes on both side
waterwalls.
13
FUEL AND LIMESTONE FEED SYSTEMS ERECTION
The fuel and limestone feeders should be placed at elevation during structural steel erection, if possible.
Early placement of this equipment minimizes handling and rigging.
FUEL SILO
FUEL
FEEDERS
14
DUCTWORK ERECTION
Ductwork erection can be completely integrated with boiler erection to avoid problems in fitting ductwork sections into the
structural steel framework.
The boiler ductwork consists of two main systems; the air-supply system, which includes the primary and secondary air
and the flue-gas system, which includes the backpass ash hopper and ductwork to the air preheater, precipitators,
induced-draft fans, and stack.
The primary and secondary hot-air ductwork from the airheaters to the furnace contains some of the biggest pieces of
equipment on the boiler. Because of the sizes involved, ductwork is generally assembled on the ground with sections
installed simultaneously with the structural steel. Hanger rods and expansion joints in the ductwork allow for thermal
expansion. Hangers and ductwork supports should be installed prior to erecting ductwork.
Secondary air
Primary air system
system
The gas-system ductwork extends from the bottom of the economizer to the exit side of the tubular airheaters. It also
includes the ductwork from the airheater to the precipitator, to the induced-draft fans, and to the stack. Most of this
ductwork is installed after the airheater is in place.
Economizer
outlet
Air Heater
To
Baghouse
15
Dampers to isolate equipment or regulate airflow or gas flow to and from the boiler are installed with the ductwork.
Depending on the material specification of the component and the diameter and thickness of the weld, post-weld heat
treating may be required to reduce the residual stresses induced by the welding. This stress-relieving process involves
the placement of electric elements or coils, or gas burners around the weld area of the component. A band around the
weld joint is brought up to a predetermined temperature, at a controlled rate, and is held there for a time period that is a
function of the weld thickness. Thermocouples attached at the outside of the heat band, or temperature indicating
crayons, are used to monitor the temperature. The component is then lowered to ambient temperature at a controlled
rate.
ADDITIONAL CONSTRUCTION WORK
When the lower headers have been set in place, the lower waterwall panels are brought in and raised into place, the
downtake system is installed. Additional work that can proceed simultaneously in other sections of the boiler is attaching
the buckstays to the waterwalls, bolting the sootblowers to the backpass walls, connecting the piping for the sootblowers,
and welding safety valves to the steam drum and outlet leads to the turbine. At this stage, a "punch list" of work that must
be completed before the hydrostatic test should be compiled, so that all responsible contractors can be aware of
unfinished items.
ERECTION OF STEAM GENERATOR AUXILIARY EQUIPMENT
Other equipment that is worked on during boiler erection are precipitators, fans and the stack. The precipitator is located
downstream of the steam generator proper and removes the solid particulate from the flue gases It rests on a
structural-steel frame which is also tied into the main support members for the precipitator. The hoppers are erected first
and lowered into the steel from above with a crane. The hoppers are usually sub-assembled on the ground and erected
as one piece. The main supports, sides and internal bracing are put up next along with the inlet and outlet ductwork. The
collecting and discharge electrodes, or other types of internals, are then erected. The inner roof, weather-roof, and
electrical components finish the main sections. Work on alignment, wiring and checkout is required before the unit is
complete.
On this unit, there are two primary air and secondary air fans that move combustion air through the tubular airheaters
and into the furnace through the watercooled grate and overfire air nozzles. Additionally, there are two fluidizing air
blowers that move combustion air through the tubular air heaters and into the seal pots, FBHE's, and FBACs through
fluidizing air nozzles and two induced-draft fans that pull the hot gases from the boiler and direct them to the stack.
17
Ash from Furnace
1560-1650F
850-900C
18
REFRACTORIES INSTALLATION
19
The recycle cyclones, ducts to/from cyclones, seal pots, FBHE's, FBACs and the ash return duct systems will be lined
with refractory. The purpose of the refractory lining is two-fold. First, it is used as an insulating medium and second, as an
erosion resistant liner. The various refractory lining materials are installed by casting, ramming, pneumatic gunning, and
by brick laying technique. Erector should insure that all craftsmen employed in this work are skilled in their respective
crafts.
ERECTION-COMMISSIONING INTERFACE
With most of the major work done on the boiler; refractory dryout, boilout and cleaning can be done. Chemicals are
circulated through the boiler for prescribed lengths of time and then drained from the boiler. These procedures remove
internal scale from water-bearing systems and assure free water passage in all tubes, headers and drums. Installation of
boiler-drum Internals may now be completed and access openings closed.
7
The contractual responsibility for the erection phase is usually complete at this point; however, support crafts for assisting
test and start-up engineers may be necessary to take care of items that require modification and/or replacement during
commissioning.
20