0 Tilling
5.1 Surface Preparation For Tilling
1) Check floor level from 1000 level line. If floor level is more than the finish floor
level, then chip that area.
2) Then chip the floor very clearly and remove all dusts.
3) Finally clean and wash the floor crystal clearly.
Fist check floor level and then put some level points. At that time we should reduce
the tile thickness.
When we putting level points we should consider what is the slopes and where should we
slope. (If it is bathroom or balcony)
Line of
Collimation
Staff
1011
Level point
Then put chemefix mixed with water to the floor. Here we put grouts to the floor.
Actually before drying grouts we should put mortar to the floor.
Mortar mixture is 1:3 or 1:4(cement: sand). Here we should remember to put suitable
amount of water to the mortar mixture.
Finally compact and level the tile bed.
Part 01
Z
Y
S
Tile marking
Part 02
L
L
Calculations: Assumptions;
a. Groove size is P
b. Tile dimension is O*R
For part 01(Linear System)
For horizontally;
No of full tile (Q) =X/ (O+P)
Then,
Z={X- (O+P)*Q}/2
For vertically;
No of full tile (Q) =Y/(R+P)
Then,
W= {Y- (R+P)*Q}/2