Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
GUIDELINES
FOR
SUPERVISION OF
INTERNATIONAL
CONSTRUCTION CONTRACTS
WITH PARTICULAR REFERENCE
TO FIDIC CONTRACTS
Originally issued: December 2005
Revision No.1: August 2011
Louis Berger
1250 23rd Street, NW
Washington, DC 20037,
USA Tel: +1 202 331-7775
Fax: +1 202 293-0787
August 2011
SUPERVISION OF INTERNATIONAL
CONSTRUCTION CONTRACTS
WITH PARTICULAR REFERENCE
TO FIDIC CONTRACTS
Introductory Note:
These Guidelines have been prepared by The Louis Berger Group, Inc. (LBG)
solely for the internal use of LBG and its authorized representatives.
The first edition of these Guidelines was dated December 2005, and posted on
LBGs internal website. A revision with minor amendments, dated January
2007, was liberally distributed in hard copy, but not posted on LBGs internal
website.
This edition of the Guidelines, as posted on LBGs internal website, supersedes
the previous edition and amendments.
It must be noted that FIDIC itself does not respond to requests for legal
interpretation of its various forms of contract.
Any comments upon or requests for clarification of these Guidelines, or for
interpretation of contract clauses, or concerning LBGs policies, should be
directed to:
Kent O. Lande, P.E., Vice President & Chief Engineer
2445 M Street NW, Suite 400, Washington, DC 20037, USA
Tel: +1 202 331-7775 Fax: +1 202 293-0787
Email: klande@louisberger.com
Acknowledgements
The Louis Berger Group, Inc. extends special thanks to the following authors
and publishers who gave their permission to quote some of their works to
support these Guidelines:
-
Table of Contents
TABLE OF CONTENTS
FOREWORD
Purpose & Scope of these Guidelines
Overview of FIDIC Contracts
START OF PROJECT
I-1.1
I-1.2
I-1.3
I-1.4
I-1.5
I-1.6
I-1.7
I-1.8
I-1.9
I-1.10
I-1.11
I-2.
I-2.1
I-2.2
I-2.3
I-2.4
I-2.5
I-2.6
I-2.7
I-2.8
+ CHECK LIST
The Louis Berger Group, Inc.
I-3.
I-3.1
I-3.2
I-3.3
I-3.4
I-3.5
I-3.6
I-3.7
I-3.8
I-3.9
I-3.10
I-3.11
I-3.12
I-3.13
Table of Contents
I-4.
END OF PROJECT
I-4.1
I.4.2
I-4.3
II-1.1
ii
II-1.2
II-1.3
II-1.4
II-1.5
II-1.6
II-1.7
II-1.8
II-2.
II-2.1
II-2.2
II-2.3
II-2.4
II-2.5
II-2.6
II-2.7
II-2.8
II-2.9
II-2.10
II-2.11
II-2.12
II-2.13
II-2.14
II-2.15
II-2.16
II-2.17
II-2.18
Table of Contents
iii
Table of Contents
II-3.1
II-3.2
II-3.3
II-3.4
II-3.5
II-3.6
iv
II-3.7
II-3.8
II-3.9
II-3.10
II-3.11
II-3.12
II-3.13
II-3.14
II-3.15
II-3.16
II-3.17
II-3.18
Table of Contents
Daywork
Measurement of Works
Valuation of Plant and Materials Intended for the Works
Contractors Interim Payment Statements
Interim Payment Certificates
- General Requirements
- Price Adjustments
- Repayment of Advance Payment
- Deductions for Retention Money
- Payment of Retention Money
- Security for Retention Money
Interim Payments
Delayed Payments
- Overview
- Interest (Financing Charges) on Late Payments
Records of Statements, Certifications & Payments
Estimates of Cost of Works to Completion
Work Quantities Management
- Bill of Quantities
- Quantity Take-offs
- Monitoring Quantity Trends
Monitoring & Reporting Works Progress
- Percentage of Progress
- Progress Charts
Contract Addenda & Amendments
+ CHECK LIST
II-4.
ONGOING SUPERVISION
II-4.1
II-4.2
II-4.3
Engineers Instructions
Regular Progress Meetings
Continuing Validity of Securities & Insurance
- Performance Security
- Advance Payment Security
- Insurance
Verification of Contractors Personnel & Equipment
Sampling & Testing of Materials, Workmanship & Plant
Works Inspection, Testing & Acceptance
Unacceptable Works, Defects Notification & Remedies
- Defects Notification
- Acceptance of Non-complying Works with Payment Deductions
- Remedies
II-4.4
II-4.5
II-4.6
II-4.7
II-4.8
II-4.9
II-4.10
II-4.11
II-4.12
II-4.13
II-4.14
II-4.15
Table of Contents
II-5.
II-5.1
II-5.2
vi
Table of Contents
II-5.3
II-5.4
II-5.5
II-6.
II-6.1
II-6.2
Substantial Completion
Taking-Over Certificate
- Taking-Over Certificate for the Whole of the Works
- Taking-Over Certificates for Sections and/or Parts of the Works
- Form of Taking-Over Certificate
Inspection at Completion & Snag List
Contractors Statement at Completion
Interim Payment Certificate at Completion
- Engineers IPC at Completion
- Supplementary Report to IPC at Completion
Interim Payment at Completion
+ CHECK LIST
II-6.3
II-6.4
II-6.5
II-6.6
II-7.
II-7.1
II-7.2
II-7.3
II-7.4
II-7.5
II-7.6
II-7.7
II-7.8
II-7.9
II-7.10
II-7.11
vii
Table of Contents
CONTRACT TERMINATION
II-8.1
II-8.2
II-8.3
II-8.4
viii
Table of Contents
APPENDICES
Examples for:
Section/Text References:
I-2.4
Inception Report
I-2.5
I-2.6
I-3.7
Method of Measurement
II-2.26
Variations
II-3.15
Taking-Over Certificate
II-6.2
Performance Certificate
II-7.9
Foreword
ix
Foreword
FOREWORD
Purpose & Scope of these Guidelines
These Guidelines have been prepared to assist Project Managers in their role
as LBGs senior construction site representative with direct responsibility for
administration and supervision of international construction contracts. The
official title for this role may depend on the complexity of the project which
could range from a single construction contract with one project/site office, to
several independent contracts each with its own site office and construction
supervision staff but administered from a separate, common project office.
Thus, alternative role titles might be Project Director, Project Manager, Team
Leader or Resident Engineer. The actual organization will generally follow the
provisions of the Clients Terms of Reference and/or LBGs Service Contract
that likely refers to LBGs Proposal for the Project.
These Guidelines, based upon FIDIC Conditions of Contract and good
practice, are intended to cover the main essentials of project management for
supervision of as-measured construction contracts or design/build contracts in
a foreign country.
These Guidelines are divided into two parts:
Part I: PROJECT ADMINISTRATION
- Procedures at start of Project, including requirements for briefing the
Project Manager.
- Management of LBGs Service Contract and, if applicable, LBGs Joint
Venture (or Consortium) and Sub-consultancy Agreements.
- Project Set-up and Execution.
- Procedures at end of Project.
Part II: WORKS CONTRACT SUPERVISION
- Start-up requirements.
- Financial control.
- Ongoing supervision.
- Taking Over the Works.
- Defects Notification Period and Contract Completion.
- Contract Termination.
The Service Contract, as discussed in these Guidelines, is the written
contract between The Louis Berger Group (LBG) and its Client, under which
LBG (referred to as the Engineer) is supervising one or more international
Works Contracts.
A Works Contract, as discussed herein, is a written contract between an
owner (referred to as the Employer) and a Contractor, under which the
August 2011
1 of 9
Foreword
August 2011
2 of 9
Foreword
August 2011
3 of 9
Foreword
old Red Book and wishing to identify equivalent clauses in the new 1999 Red
Book.
Due to these formatting differences, FIDIC clause numbers are generally not
referenced nor quoted in these Guidelines. The Project Manager must read
fully, understand and constantly refer to the detailed terms of the respective
contracts during his administration thereof.
These Guidelines, based on previous experience, identify typical important
requirements of Service Contracts and Works Contracts; and pitfalls to be
avoided by good management practices. The following convention is used:
means a required or recommended action of LBGs representatives
(usually the Project Manager).
o means something that should be taken into consideration by the Project
Manager.
August 2011
4 of 9
Foreword
August 2011
5 of 9
Foreword
The Red Book is intended primarily for the construction of works for which
detailed design is provided by the Employer to the Contractor, and the
Contractor is paid by the Employer based on measurement of the constructed
works and valuation in accordance with tendered unit rates and prices. Earlier
versions of the Red Book were drafted for use on civil engineering projects;
but the current edition drops those words from the title, signifying a move
away from only being applicable to civil engineering works.
FIDIC has recently published a Red Book - MDB Edition, commonly
referred to as the Harmonized version of the Red Book. This resulted from
requirements of the Multilateral Development Banks (MDBs) to modify certain
of FIDICs General Conditions of Contract to suit the MDBs commonly
agreed procurement practices. Prior to publication of this MDB Edition, an
MDBs requirements were incorporated into a Red Book contract by means of
added Part II Particular Conditions. In this recent MDB Edition the MDBs
requirements are incorporated into the Part I General Conditions. Changes
included in this MDB Edition include, the right of the funding bank to audit
the Contractors accounts, minor changes to the provisions for dispute
resolution, and limitations upon the Engineers authorities.
The MDBs that participated in the preparation of the Red Book - MDB
Edition are:
- African Development Bank
- Asian Development Bank
- Black Sea Trade & Development Bank
- Caribbean Development Bank
- European Bank for Reconstruction & Development
- Inter-American Bank
- International Bank for Reconstruction & Development (World Bank)
- Islamic Bank for Development
- Nordic Development Fund
Whereas the Red Book contracts allow some elements of a project to be
designed by the Contractor, they are not suitable when most of the works are
to be designed by the Contractor, and for such projects the Yellow or Silver
Book would be more appropriate.
The Yellow Book provides conditions of contract for construction works for
which the detailed design (to satisfy Employers Requirements embodied in
the contract documents) is performed by the Contractor, and the Contractor is
paid on a lump sum basis. Originally intended for contracts involving electrical
and mechanical works and the installation of plant manufactured off-site, the
reference is removed from the title of the current edition to reflect its suitability
to any combination of civil, mechanical, electrical and/or construction works
designed by the Contractor.
August 2011
6 of 9
Foreword
Both the Red and Yellow Books provide that the Contract shall be
administered and the Works supervised by the Engineer who is
appointed by the Employer and named in the contract documents. The
Engineer can be an individual but is more typically a firm of consulting
engineers.
Under the older forms of Red Book and Yellow Book contracts, the Engineer
(although hired by the Employer) is required to act independently, fairly and
unbiased in the performance of his duties which include issuing instructions,
certifying payments, verifying quality compliance and determining completion.
Under these older forms of contract, the Engineer has responsibility to render
determinations of any claims for time extension or additional payment arising
from variations of and/or delays to the Works. In the event of disagreement
with the Engineers determination, an Engineers Decision is sought; and only
if the Engineers Decision is disputed can the dispute be referred to
arbitration.
Under the current editions of the Red and Yellow Books, the Engineer is no
longer independent and he is defined as being part of the Employers
Personnel, but he is still required to perform his duties fairly in accordance
with the Contract. The older Engineers Decision is replaced by provision for
a Dispute Adjudication Board (DAB). That is, if any Engineers determination
is not agreed by either of the Parties, then the dispute shall be referred to the
DAB; and only if the DABs Decision is not accepted by either of the Parties
can the dispute be referred to arbitration.
The Turquoise Book, especially for Dredging & Reclamation Works, is the
only other form of FDIC contract administered by the Engineer. Before its
publication, there was little to choose from in the way of suitable standard
forms of contract. A common international practice was to adapt the Red
Book, with inherent difficulties of doing so.
Under all other forms of FIDIC contract (described below), there is no
reference to the Engineer; the Contract is administered directly by the
Employer (unless he appoints an Employers Representative).
The Green Book Short Form of Contract is recommended for engineering
and building work of relatively small capital value (say not greater than
US$500,000) and of relatively short construction period (say not greater than
6 months) without need of specialist sub-contracts. The usual arrangement
for this contract is that the Contractor constructs the Works in accordance
with design provided by the Employer. However, it may also be suitable for
contracts which include, or wholly comprise, the Contractors design. Prior to
this publication, some of the Multilateral Development Banks used their own
short forms of contract.
August 2011
7 of 9
Foreword
The Orange Book for Design-Build & Turnkey was published, in 1995, at a
time when the existing Red and Yellow Books were still aimed at procurement
of civil engineering and plant installation respectively. At the time, the Orange
Book offered a clear design-build and turnkey option to the then-available
suite of contracts, for use where the Contractor carries total liability for design
as well as construction. With publication in 1999 of the new suite of contracts
(and in subsequent publications), FIDIC has focused less on the type of
project and more on the implementation of different procurement strategies. It
is now likely that an Employer requiring a design-build or turnkey project
under a FIDIC contract would adopt either the recent Yellow Book for designbuild or the recent Silver Book for Turnkey. The Orange Book can be adapted
to provide for Contractor-financing. The contract may impose a requirement
for the Contractor to operate the Works, either for a few months
commissioning period, or for some years on a build-operate-transfer basis. In
the latter case, the recent Gold Book might be more appropriate.
The Silver Book, for EPC/Turnkey Projects, is intended for the provision on
a turnkey basis of a process or power plant, a factory or similar facility, or an
infrastructure project or other similar type of development, where (i) a higher
degree of certainty of final price and time is required, and (ii) the Contractor
takes total responsibility for the design and execution of the project, with little
involvement of the Employer. Under usual arrangements for turnkey projects,
the Contractor carries out all Engineering, Procurement and Construction
(EPC): providing a fully equipped facility, ready for operation (at the turn of
the key). The Employers higher degree of price/time certainty is achieved by
the Contractor accepting a higher level of risk (no doubt reflected in his
tendered price) than is typical under most other forms of FIDIC contract. For
example, the Silver Book transfers risk of ground conditions to the Contractor.
Similarly, the Contractor also assumes responsibility, subject to some
exceptions, for the accuracy of the Employers Requirements, which is a
major difference to usual design-build contracts. However, not all risk is
transferred to the Contractor, and the Employer still retains risks for war,
terrorism and force majeure. Under a Silver Book contract the Contractor has
freedom to perform the work in his chosen manner, provided that the end
result meets the performance criteria specified by the Employer as verified by
tests on completion. Given the high level of risk to be undertaken by the
Contractor, the Employer must allow sufficient time in its procurement
program for the Contractor to obtain and consider all relevant information.
The Silver Book can be adapted to provide for Contractor-financing.
The Gold Book, for Design, Build & Operate Projects, combines the need
for a contract having a design-build obligation with a long-term operation
requirement. This DBO contract adopts a green-field scenario with a 20-year
operation period and a single contract awarded to a single contracting entity
(which will almost certainly be a consortium or joint venture) to optimise
innovation, quality and performance, rather than award separate contracts for
The Louis Berger Group, Inc.
August 2011
8 of 9
Foreword
August 2011
9 of 9
PROJECT MANAGEMENT
GUIDELINES
FOR
SUPERVISION OF
INTERNATIONAL
CONSTRUCTION CONTRACTS
PART I
PROJECT ADMINISTRATION
I-1.
START OF PROJECT
This Chapter deals with:
o Appointment of a Head Office Supervisor who shall be available
throughout the Project to advise and support the Project Manager in the
execution of his duties.
o The necessary briefing of the Project Manager at the start of the Project,
to provide him/her with the information, documents, delegations of
authority and responsibility, and powers of attorney necessary to set up
and manage the Project.
I-1.1
I-1.2
August 2011
I-1 /1
I-1.3
I-1.4
Project Organization
The Project Manager should be provided with:
August 2011
I-1 /2
A chart (or charts) showing the project inter-relationship and reporting lines
between the Client / Contracting Authority / Employer, LBG (and its joint
venture or consortium partners, if relevant), and sub-consultants.
The chart should show names and titles of the persons in key positions.
The Client under LBGs Service Contract might be the same as or different
from the Contracting Authority under the Works Contracts. It is possible that
LBGs Service Contract might be directly with a Funding Institution.
Under the Works Contract, the Contracting Authority who signs the Works
Contract and will pay the Contractor (called the Employer under FIDIC forms
of contract) and the Beneficiary of the Works might be different entities.
The Project Organization charts should delineate these entities, as
appropriate, according to their functions.
I-1.5
I-1.6
LBG Representatives
The Project Manager should be provided with names, titles, functions,
addresses and contact particulars (tel./ fax / E-mail) for:
Vice President responsible.
Head Office Supervisor.
LBG contact person for medical problems and evacuations.
In-country representatives of LBG (e.g. who may have assisted LBG with
its Proposal and/or are available for advice and support). The basis of
such relationships and availability should be made clear.
August 2011
I-1 /3
I-1.7
Copies (sufficient for Project staff needs) of the latest pocket-book Berger
Group Directory (also down-loadable from LBG website).
I-1.8
I-1.9
August 2011
I-1 /4
August 2011
I-1 /5
I-1.10
The Project Manager should also check with the Client on the
acceptability of formats for Time Sheets and Invoices.
August 2011
I-1 /6
I-1.11
August 2011
I-1 /7
Formal written Powers of Attorney, for the Project Manager to act on behalf of
LBG, should be provided as necessary.
It must be noted that the duties, responsibilities and authorities delegated to
the Project Manager for his administration of LBGs Service Contract are quite
separate from duties, responsibilities and authorities delegated to him as the
Engineer, Engineers Representative or other designated member of the
Engineers staff under the Works Contract between the Employer and
Contractor. [See Sections II-2.1 & II-2.2 for further discussion.]
August 2011
I-1 /8
I-1.4
I-1.5
I-1.6
I-1.7
I-1.8
I-1.9
I-1.10
I-1.11
Requirement
Appointment of Head Office Supervisor
Provide to Project Manager at PROJECT BRIEFING:
Service Contract Documents:
Client's TOR & Request for Proposals
Pre-proposal clarifications & correspondence
LBG Proposal (Technical & Financial)
Pre-contract clarifications & correspondence
LBG Service Contract
Governing Funding Agreement
Standard Guidelines of Client and/or Funding Institution
Project Organization:
Organization chart(s)
Names/titles of Key Personnel
Client/Employer Contacts & coordinates:
Contracting Authority & Beneficiary for LBG Service Contract
Funding Institution for LBG Service Contract
Contracting Authority & Beneficiary for Works Contract(s)
Funding Institution(s) for Works Contract(s)
LBG Representatives (names/titles/coordinates):
VP responsible
Head Office Supervisor
Contact person for medical problems & evacuations
In-country representatives
Berger Group Directory
Staffing & Sub-consultancy Agreements:
Joint Venture or Consortium Agreement (if applicable)
Sub-consultancy Agreements
Project staffing arrangements
Procedures for staff mobilizations
Conditions of employment for LBG Project staff
Office, Living Accommodation & Transport:
LBG provisions & procedures
Project Manager's authority for procurement
LBG Financial Support & Accounting Procedures:
Project kick-off cash advance
Arrangements for Project banking
Power of Attorney for Project Manager for Project banking
Procedures for monthly Project cash advances
Person(s) to receive Project cash advance requests
Requirements for expenditure receipts
Procedures and format for submitting Project monthly accounts
Person to receive monthly reports of Project accounts
LBG Administration Procedures:
Project Numbers for Time Sheets & Expense Claims
Standard format & procedures for submitting Time Sheets
Person(s) to receive Time Sheets
Standard format & procedures for submitting Expense Claims
Person(s) to receive Expense Claims
Person to consult on employment conditions, benefits, problems
Access to LBG Website
Delegation of Responsibilities & Authority (to Project Manager):
Interface with Client & Funding Institution
Management & services under Service Contract
Preparing/signing Service Contract Addenda
Administration of Subcontract Agreements
Preparing/signing Subcontract Agreements/Addenda
Financial accountability & reporting
Administrative procedures
Quality assurance
Internal LBG reporting requirements
Check
Comment
August 2011
I-2.
I-2: Management of
Service Contract
I-2.1
August 2011
I-2 /1
I-2: Management of
Service Contract
I-2.2
August 2011
I-2 /2
I-2: Management of
Service Contract
Against this schedule the Project Manager should apply the budgeted time
(per Service Contract) of the intended Project staff in order to:
Establish intended mobilization and demobilization dates for Project staff
and sub-consultants.
Confirm the sufficiency of budgeted Project staff provisions.
The Project Manager should send a copy of this schedule (with comments
and recommendations) to the HO Supervisor and the responsible VP. In case
of conflicts with provisions of the Service Contract, the Project Manager and
HO Supervisor (and, if necessary, the responsible VP) will decide upon and
implement the manner of resolving such conflicts with the Client.
The above process should be completed before finalization of any Inception
Report to be submitted to the Client [see Section I-2.5].
I-2.3
August 2011
I-2 /3
I-2: Management of
Service Contract
Some Clients and/or Funding Institutions might decline payment for Project
staff services provided without or prior to the Clients written approval of
mobilization. Funding Institutions might not permit retroactive Client approvals
of staff mobilizations. Therefore it is important that such rules be established
or clarified (as necessary) in writing. Equally, so as to maintain an audit trail,
LBG applications (normally by the Project Manager) for staff changes and
mobilizations must be in writing, and staff mobilizations should not be effected
until the Clients written approval has been received.
I-2.4
August 2011
I-2 /4
I-2: Management of
Service Contract
staff are expected to work 5 or 6 days per week, as necessary to cover the
Contractors working schedule. Usually a standard 8-hour day is applied,
whatever hours are worked in that day (i.e. no overtime). Sundays, Saturdays
and Public Holidays might not be chargeable, even if worked, without prior
approval of the Client. Billable international travel time may be restricted.
Sometimes billable time has to be computed as the proportion of a month
engaged at the Project location (e.g. 18 calendar days on location within a
calendar month = 18/30 or 0.60 months). Alternatively, under different rules a
full month may be eligible if a total of 22 days have been worked in that
month; and a part month is computed from the eligible work-days worked
(e.g. 18 days worked on location = 18/22 or 0.82 months). The methods of
computing time charges might be different for long-term and short-term
Project staff; and these may need to be defined.
Also, it cannot be assumed that the same interpretation of time computation
rules of any one Funding Institution will be consistently applied from one
country to another. The rules may be interpreted differently from one incountry agency to another. The time computation rules need to be
established for each project.
In establishing these time computation rules, the Project Manager should
check that either they comply with or can be accommodated within the
requirements of any in-country legislation concerning the employment of local
staff, either directly or through sub-consultants.
An example of the clarification of rules, as agreed with the Client for a
previous project, is presented in Appendix A.
It may be expedient to submit for the Clients approval at the end of each
month the staff time sheets and, based thereon, a summary of the
computation of the Project staff time for that month. Thus, with the Clients
approval in hand, there should be no disagreement with LBGs subsequently
submitted invoices for services. This may be particularly advisable when
invoices will significantly post-date time sheets, such as when invoices are
due quarterly. An example of such client-approved Project staff time summary
is presented in Appendix D.
The same rules imposed by the Client for computation of Project staff time
should also be followed by the Project staff (including consortium partners
and sub-consultants) in their internal time sheets for salary payment purpose.
Living Allowances & Per Diems
Similarly, rules for charging (to the Client) per diems and monthly living
allowances are not consistent from project to project. A monthly Living
Allowance for long-term staff (sometimes referred to as Accommodation
The Louis Berger Group, Inc.
August 2011
I-2 /5
I-2: Management of
Service Contract
and/or Subsistence Allowance) may be chargeable only for the periods when
a consultant is engaged at the Project location (i.e. excluding while on
vacation); or alternatively the allowance may be chargeable for the whole
period of assignment including vacation time. Per diems might be chargeable
only if an overnight stay is involved. Amounts of allowances and per diems
may differ for different locations of a multi-contract project. These rules need
to be established with the Client for each project.
An example of the clarification of rules, based on a previous project, is
presented in Appendix A.
Unless otherwise established by LBG employment contracts or other
agreements, LBG employees should receive the amounts of allowances and
per diems that will be invoiced to the Client according to the computation
rules imposed by the Client.
On some projects, allowances and per diems are included in LBGs Service
Contract charge rates for the Project staff and are not, therefore, separately
chargeable to the Client. In this case, internal LBG rules must be established
for payment of allowances and per diems to Project staff (which should be
reflected in their respective employment contracts).
Travel / Mobilization Allowances or Expenditures
If billable under the Service Contract, but not clearly described therein, the
Project Manager should clarify with the Client the basis and rules for travel
and mobilization/demobilization expenditures, and confirm them in writing.
Either the allowances in LBGs Proposal or the actual costs (which may be
restricted to the maximum limit of the Proposal allowances) might be
chargeable.
The Project Manager should establish such particulars as:
Restrictions on air line carriers (e.g. US carriers only).
Restrictions on air travel class (usually economy only).
Home base limitations (e.g. travel cost might only be eligible from
countries of eligible citizenship).
Restrictions on train travel class.
Eligibility of other transport modes.
Requirements for air travel receipts and/or ticket stubs as back-up to
invoices (e.g. original boarding passes may be required).
August 2011
I-2 /6
I-2: Management of
Service Contract
Requirements to:
- first submit and obtain Client approval of procurement specifications;
- obtain a minimum number of quotations;
- submit an evaluation of the quotations and receive the Clients
approval before committing to the purchase.
Requirement to provide a Certificate of Origin as well as receipts for the
purchases.
In order that LBG will be reimbursed for such expenditures, the Project
Manager must obtain, in writing, any necessary clarification of procurement
rules and follow them rigidly.
I-2.5
Inception Report
An Inception Report is typically required by the Terms of Reference (TOR) to
be prepared and submitted to the Client within, say, one to three months after
commencement of the Consultants services. Any format and detail of the
Inception Report specified in the TOR must be complied with. Alternatively, if
not specified in the TOR, the Project Manager should ascertain if the Client
has a required format. A purpose of the Inception Report is to demonstrate
the Consultants understanding of the Project, by describing his start-up
actions and plans to fulfil the Project objectives. In general the Inception
Report should:
Summarize the Project background, objectives and status.
Summarize the background and purpose of LBGs Service Contract.
Provide a Project Organization showing reporting lines and interface
between the Funding Institution(s), Client, Consultant (LBG), Subconsultants, site offices and contractors.
Describe LBGs mobilizations of Project staff, facilities and equipment (to
date and projected to anticipated demobilization).
August 2011
I-2 /7
I-2: Management of
Service Contract
Describe LBGs activities (to date and projected) until the end of the
Service Contract.
Summarize the status of preparations for or execution of the Works
Contract(s).
Provide a Project schedule for the Works Contract(s) and LBGs activities.
I-2.6
August 2011
I-2 /8
I-2: Management of
Service Contract
August 2011
I-2 /9
I-2: Management of
Service Contract
I-2.7
August 2011
I-2 /10
I-2: Management of
Service Contract
proceed with provision of the additional services without the Clients written
undertaking that he will sign the necessary Addendum.
The Project Manager should be particularly careful when the Client is a dual
entity (e.g. Contracting Authority and Beneficiary). The Beneficiary, who is
technically orientated, might well request additional or different technical
services without considering Service Contract implications, and without
referring to the Contracting Authority whose signature would be required to
the necessary Addendum. The Project Manager must ensure by written
communications to/from the Contracting Authority (copied to the Beneficiary)
that the Contracting Authority agrees to the amended services and terms, and
will sign an Addendum. Approval might also be required of the Funding
Institution (if any), whose endorsement of an Addendum will be necessary.
The Project Manager should also be careful to comply fully with the Contract
Terms of Reference. Contracted services or deliverables cannot be changed
or omitted without a Contract Addendum. For example, omission of
contracted services or deliverables, based on the Beneficiarys informal
advice that he no longer requires them, might affect LBGs entitlement to
certain payments under the Service Contract unless an Addendum has been
effected.
The Project Manager must ensure that any of LBGs Consortium and/or Subconsultancy Agreements that are affected by amendments to the main
Service Contract are amended accordingly.
I-2.8
August 2011
I-2 /11
I-2: Management of
Service Contract
August 2011
I-2 /12
I-2: Management of
Service Contract
August 2011
I-2 /13
Check
Comment
August 2011
I-3.
I-3.1
Formal Communications
General Requirements
This Section, and Sections I-3.2, I-3.3 & I-3.4, deal with formal
communications for the Project Managers management of the Service
Contract, Sub-consultancy Agreements and Works Contract(s), which must
August 2011
I-3 /1
August 2011
I-3 /2
August 2011
August 2011
I-3 /4
August 2011
I-3 /5
written. Some clauses might require that such references be given. For
example:
In accordance with Clause(s)... of the Conditions of Contract, we
hereby give notice that ....
LBG communications to the Employer must be addressed to the person(s)
designated by name or title in the Works Contract, or formally appointed from
time to time by the Employer under the Works Contract, as the person(s)
authorized to act on behalf of the Employer.
LBG formal communications to the Employer need only be copied to the
Contractor if specifically required by any of the clauses of the Conditions of
Contract.
I-3.2
Letterhead
The Project Manager should prepare a standard LBG letterhead (for the
Project Office and each of the Site Offices, as appropriate) to be used for all
Project correspondence, including letters and faxes.
The letterhead should be in a digitized frame that can be pulled down for
computer-generated letters and faxes. In this electronic world, the use of preprinted letterheads is not economical. The Project Manager should ensure
that any coloured letterheads will photocopy in black-and-white without loss of
detail or definition.
Letterheads for each of the Project Office and Site Office(s) should include:
The Project name.
LBGs name (or, in the case that LBG is part of a Joint Venture or
Consortium, the name of the Joint Venture or the names of the
Consortium partners).
LBGs logo (if LBGs name is used in the letterhead).
The address, tel., fax and E-mail of the office.
The Project Manager should request the HO Supervisor to provide a digitized
file of LBGs logo.
I-3.3
Correspondence Identification
Outgoing Correspondence
All Outgoing Correspondence, to whomsoever, must bear a unique,
consecutive, reference number, such as:
August 2011
I-3 /6
August 2011
RECEIVED ON
Date
IN No....................
I-3 /7
FILE Nos.
A
I-3.4
Correspondence Registers
Correspondence registers, both in the Project Office and each Site Office,
should be kept; one for incoming correspondence, and one for outgoing.
While this can be achieved electronically, it is preferred also to have hard
copy registers into which the correspondence chronology and data is entered
manually. Since the registers will be in constant use for the duration of the
Project (perhaps for several years), they should preferable be bound in book
form with hard covers. They should be readily available for supervision staff to
consult.
Examples for such registers (in landscape format) follow:
August 2011
I-3 /8
Project Name
PROJECT OFFICE
OUTGOING CORRESPONDENCE
Start Date:
Finish Date:
Content Pages:
Ref.
No.
Date
To
Subject
Copies to
File
Numbers
Comment
e.g.In reply to
Contract Name
SITE OFFICE
INCOMING CORRESPONDENCE
Start Date:
Finish Date:
Content Pages:
IN
No.
Date
From
To
Letter Ref.No.
& Subject
File
Numbers
Comment
e.g.In reply to
I-3.5
Informal Communications
Other than formal communications (i.e. formal, signed letters delivered in hard
copy, although they may also have been transmitted electronically), informal
communications will likely pass by E-mail between project participants. These
E-mails must be restricted to informal matters. Approvals, consents,
agreements, certifications, determinations, decisions, notifications,
instructions and requests cannot be given by E-mail (unless permitted
under the respective contracts, which is unlikely).
Examples of such informal communications might be:
- passing drafts of proposed formal correspondence or documents for
review and comment;
- exchange of ideas or opinions;
- enquiries of availability for meetings;
- confirmation of travel plans.
It is suggested that informal E-mail communications need not follow the
recommended procedures for Correspondence Identification [Section I-3.3]
and Correspondence Registers [Section I-3.4] of formal communications.
August 2011
I-3 /9
I-3.6
Records of Meetings
All formal meetings (excluding day-to-day meetings for liaison) in respect of
the Service Contract, Sub-consultancy Agreements and Works Contracts
must be recorded as Minutes that are distributed to the designated
representatives of the parties who attended or were invited to attend the
meetings.
Agenda for formal meetings should be pre-distributed to invited participants at
least several days prior to a meeting (in order that participants can come
prepared).
It is recommended that such regular meetings as, say, Monthly Progress
Meetings have pre-established standard agenda, in which case predistribution of such agenda will be unnecessary.
The first item heading on standard agenda for such regular meetings should
be:
- Minutes of Previous Meeting whereunder participants are asked to
record their agreement or specific disagreement with those minutes of
previous meeting.
This is a more expeditious procedure than issuing draft minutes for comment
before finalization and/or trying to get minutes signed as accepted by the
participants.
Minutes of Meetings should include:
The Project name.
Service Contract name or Works Contract name (as appropriate).
A caption for the meeting.
Example: Monthly Progress Meeting No between Employer,
Engineer and Contractor
Example: Site Meeting No between Engineer and Contractor
Example: Meeting to discuss Schedule & Costs of Repairs to
Damaged Utilities
August 2011
I-3 /10
I-3.7
August 2011
I-3 /11
I-3.8
Project Reports
The various reports required by the Client to be prepared by LBG should be
listed in the Terms of Reference. They will likely include:
Inception Report [see Section I-2.5].
August 2011
I-3 /12
August 2011
I-3 /13
August 2011
I-3 /14
I-3.9
Sub-consultants
The Project Manager should have received at the Start of Mission, Project
Briefing [see Section I-1.2], copies of existing or proposed Sub-consultancy
Agreements.
Preparation of Sub-consultancy Agreements
In the event that Sub-consultancy Agreements are anticipated but not
prepared, the Project Manager should have been briefed regarding:
whether or not the Project Manager has responsibility and authority to
select sub-consultants, and to negotiate, prepare and sign Subconsultancy Agreements. And if he does not who does?
the extent to which the Project Manager is responsible for administering
the Sub-consultancy Agreements.
If the Project Manager has responsibility for preparing Sub-consultancy
Agreements, then he shall:
obtain, from LBGs HO Supervisor, LBGs standard or other form of Subconsultancy agreement to be adopted.
[FIDIC has as standard form of Sub-consultancy Agreement, but it may be
used only with the HO Supervisors pre-approval.]
Each Sub-consultancy Agreement should clearly and unequivocally state:
- the services to be provided;
- the location of services;
- the time duration of the Agreement (linked to the main Service
Contract);
- the General Conditions of Contract and Conditions of Particular
Application, including provisions for dispute resolution;
- the not-to-be-exceeded time budget for various categories of the subconsultants staff;
- rates and prices per day, per month, per service, as appropriate
(typically rates and prices should be stated as including any costs of
staff selection and mobilization, accommodations and/or living
allowances, non-work-related travel, vacations and statutory holidays,
statutory employment benefits, overtime which may be reasonably be
required and is consistent with the construction industry, professional
indemnity insurance, accident insurance, any other overheads and
incidentals none of which costs shall be paid separately or
additionally);
- any lump sum prices for services;
- the not-to-be-exceeded monetary budget for the sub-consultants
services;
August 2011
I-3 /15
August 2011
I-3 /16
I-3.10
August 2011
I-3 /17
All short-term experts must be advised, prior to their mobilization, that they
are required to bring with them laptops and any specialist software they
might require.
I-3.11
I-3.12
Confidentiality
The Project Manager must impress upon his supervision staff that all Project
documents are confidential to the parties of the Contracts, and shall not be
divulged to third parties.
August 2011
I-3 /18
I-3.13
August 2011
I-3 /19
Check
Comment
August 2011
I-4.
END OF PROJECT
This Chapter provides guidelines for:
o Supervision staff retention to complete services at Project completion.
o Hand-over (to the Client) and retention (by LBG) of documents and
equipment at the conclusion of project services.
I-4.1
August 2011
I-4 /1
Thus, it may not be possible to process the Final Payment Certificate until
up to 3 months after the end of the Defects Notification Period.
The Project Manager must:
Plan sufficient and appropriate staff to perform these periodic functions
until the Final Payment Certificate is issued for each Works Contract.
Consult with the Client to arrange the retention (or alternative
provision) of office accommodations, facilities and equipment adequate
for fulfilment of these remaining services.
I.4.2
August 2011
I-4 /2
August 2011
I-4 /3
I-4.3
August 2011
I-4 /4
I-4.2
I-4.3
Requirement
Staff Retention for Project Completion
Plan staff retention to complete services (after issuing TakingOver Certificate) of:
Further works inspections & measurement (if any)
Determination of outstanding claims & disputes (if any)
Interim Payment Certificate at Completion
Report at Completion of Works
Plan staff retention to complete services during & after Defects
Notification Period of:
Periodic inspections of Works & Notification of Defects
Measurement of works (if necessary)
Determination of outstanding claims & disputes (if any)
Performance Certificate (or Defects Liability Certificate)
Final Payment Certificate
Final Report at end of LBG Services (if required)
Hand-over & Retention of Documents
Plan hand-over of documents to Client:
Consult with Client to arrange
Implement hand-over
Retain copies of hand-over records
Plan retention of documents by LBG
Consult with LBG to arrange
Deliver or store documents
Hand-over & Retention of Equipment
Plan hand-over /ownership-transfer of equipment to Client:
Consult with Client to arrange
Implement hand-over/ownership-tranfer
Retain copies of hand-over /ownership-transfer records
Plan retention /delivery of LBG-owned equipment:
Consult with LBG to arrange
Deliver or store equipment
Check
Comment
August 2011
PROJECT MANAGEMENT
GUIDELINES
FOR
SUPERVISION OF
INTERNATIONAL
CONSTRUCTION CONTRACTS
PART II
WORKS CONTRACT SUPERVISION
II-1.
II-1.1
August 2011
II-1 /1
August 2011
II-1 /2
II-1.2
August 2011
II-1 /3
II-1.3
August 2011
II-1 /4
6.
7.
8.
9.
Specifications
Drawings
Priced Bill of Quantities (including Method of Measurement)
Schedules (proposals/undertakings) of the Contractors Tender
August 2011
II-1 /5
The MoM should clearly state what works are included under items or
categories of items of the BoQ. For example, does an item for excavation of
unsuitable material include haulage and disposal of that material off Site to an
approved deposition area? Does such excavated material become the
property of the Employer, or can the Contractor dispose of it to his own
financial advantage?
The MoM should clearly state how each measured quantity under line items
of the BoQ is to be measured. For example, is the volume of excavation for a
new underground concrete foundation measured to the neat vertical lines of
that foundation, or is an allowance permitted for subsequent working room to
construct the foundation? For example, is the area of asphalt paving
measured with or without consideration of the feathered edges of the
pavement?
Examples of typical item coverages of a Method of Measurement for items of
a Bill of Quantities are presented in Appendix I.
Contradiction or lack of clarity should not exist between the various Works
Contract documents. A dispute could arise, for example for asphalt works, if
the Specifications state that Tack Coat shall be applied between bituminous
bound courses and may only be omitted with the Engineers written consent,
the Bill of Quantities includes a payment item for Tack Coat, but the Method
of Measurement states that Tack Coat is included in the item coverage for
bituminous bound courses! Will the Tack Coat be separately measured and
paid or not?
Employer & Contracting Authority
It may be an intention that the Contracting Authority (who will sign the Works
Contract and make payments to the Contractor and is, therefore, the
Employer under the Works Contract) is a different arm of Government of the
Country from that intended as the Beneficiary of the Works. Hypothetically,
for example, the Contracting Authority may be a contracting agency of the
Ministry of Transport, and the Beneficiary is the National Roads
Administration.
To avoid confusion (and potential future contractual disputes) in such
circumstance, it is important to define in the Works Contract the roles to be
performed by the respective arms of the Employer. Under a FIDIC-based
Works Contract, for example, it would be advisable to include clauses in the
Particular Conditions that define the dual identity of the Employer, and identify
which of them (either one or the other or both) has jurisdiction for each of the
clauses of the Conditions of Contract (or other Contract documents) under
which the Employers actions are required.
August 2011
II-1 /6
II-1.4
August 2011
II-1 /7
II-1.5
August 2011
II-1 /8
II-1.6
August 2011
II-1 /9
II-1.7
August 2011
II-1 /10
II-1.8
August 2011
II-1 /11
o
o
o
o
o
o
o
o
The Project Manager (as, say, representing the Engineer under a Works
Contract) has no power of discretion in this matter. LBG is not a party to the
Works Contract. In their administration of the Works Contract:
the Project Manager and his supervision staff must adhere to the
provisions of those Contract documents.
Accordingly, for example, the Project Manager cannot agree with the
Contractor to change technical Specifications for the Works. He may
recommend such change to the Employer, but any change requires, before it
is effected, a written Agreement signed by the contracting Parties.
Similarly the Project Manager or any of his supervision staff do not have any
power of discretion to accept and certify payment for works that do not
comply with the Specifications. They cannot accept, for example, concrete
that is only marginally below the specified strength requirement. If any work
does not comply with the Specifications, it must be rejected - unless and until
the contracting Parties sign a written Agreement for acceptance of the
deficient work and the terms of acceptance (which might include, for example,
a price reduction and/or extended warranty period).
A development on externally funded Works Contracts is that some Funding
Institutions Guidelines for as-measured Works (if such Guidelines are
included in the Contract) might require that quantities of the Bill of Quantities
may only be exceeded by Contract Addenda. Under such requirement, the
Project Manager and Resident Engineer must be careful not to consent to the
Contractors execution of exceeding works quantities (except at the
Contractors risk) and not to certify payment for such exceeding quantities
until any necessary Addendum has been effected.
August 2011
II-1 /12
Check
Comment
August 2011
II-2.
II-2.1
August 2011
II-2 /1
II-2.2
August 2011
II-2 /2
August 2011
II-2 /3
August 2011
II-2 /4
Guidelines recommend that the provisions of the old Red Book contract be
followed on old Yellow Book contracts.
The Engineer, or the Engineers Representative (if he has been delegated
a general authority), must:
appoint by name and delegate duties/authorities to each of the
categories of the Engineers Representatives Assistants: Resident
Engineer, Deputy Resident Engineers, Section Engineers, Materials
Engineer, Inspectors, Geodetic Surveyor, Quantity Surveyor, etc.;
notify the Contractor in writing (copied to the Employer) of these
appointments and delegations.
These sub-delegations should be limited in extent. The Engineers
Representative should retain major contractual authorities such as issuing
Interim Payment Certificates and other certifications, instructing variations
and issuing Variation Orders, rendering Engineers determinations of the
Contractors claims, etc.
The notifications must state each of the clauses of the Conditions of
Contract under which duties/authorities are sub-delegated. This requires
painstaking review of all the Conditions of Contract.
For example:
Pursuant to Cl of the Conditions of Contract I hereby appoint
Mr as an Engineers Representatives Assistant for the (name of
Contract), and hereby delegate to him the duties and authority of the
Engineer in respect of the following Clauses of the Conditions of
Contract:
- receiving submissions under Cl.;
- issuing notices under Cl.;
- performing measurements under Cl.
If the Resident Engineer has been delegated the appropriate authority,
then he can notify to the Contractor the further sub-delegations in the
manner prescribed above.
Alternatively, and more efficiently, it is recommended that the subdelegations be effected by preparing a chart of delegations to all the
Engineers Representatives Assistants (identified by name and position),
related to specific clauses of the Conditions of Contract, which chart is
then formally copied to the Assistants themselves, the Contractor and the
Employer. [See Appendix Q for example of a delegations chart under
FIDICs old Red Book form of contract.]
Under Recent Forms of FIDIC Contract (from 1999)
August 2011
II-2 /5
August 2011
II-2 /6
II-2.3
Pre-commencement Meeting
Preferably prior to the Engineers issuing a Notice of the Commencement
Date [see Section II-2.5], it is recommended that the Parties and the
Engineer convene a meeting to discuss and record matters including:
The role and authority of each entity participating in the Contract.
Appointment of the Engineer and (if appropriate) the Engineers
Representative [see Section II-2.1 and Section II-2.2].
Appointment of the Contractors Representative [see Section II-2.4].
Where the Contract provides for delegating duties and authorities to
persons, these should be clearly established.
Status of availability for Access to and Possession of Site [see Section
II-2.13].
Requirement and procedures for obtaining Construction License [see
Section II-2.14].
Status of availability for Issuing Drawings [see Section II-2.15].
Status of Contractors Performance Security [see Section II-2.6] and
Advance Payment Security [see Section II-2.7].
Status of Contractors Insurance [see Section II-2.8].
Commencement Date [see Section II-2.5].
Requirements for Safety, Security and Protection of the Environment [see
Section II-2.25].
Requirements for Quality Assurance and Control [see Section II-2.12].
Status of the Works Programme, key dates for information and
submissions, periods for approval, long delivery periods and special
problems [see Section II-2.11].
Requirements for subcontractors named, nominated and yet to be
proposed by the Contractor [see Section II-2.19 Consent for
Subcontractors and Section II-2.20 Nominated Subcontractors].
Works or materials to be provided by the Employer.
Procedures for measurement, notices, instructions, submissions and
responses.
August 2011
II-2 /7
II-2.4
Contractors Representative
FIDIC Red and Yellow Book forms of contract require that the Contractor
shall appoint a Contractors Representative, and give him authority to act on
the Contractors behalf under the Contract. Further, the Contractors
Representative shall be full-time on Site, give his whole time to directing the
Contractors performance of the Contract, and shall, on behalf of the
Contractor, receive instructions and notices from the Engineer.
Unless the Contractors Representative is named in the Contract, the
Contractor is required to submit to the Engineer for consent or approval
the name and particulars of the person the Contractor proposes to appoint as
Contractors Representative. Recent forms of FIDIC contract use the term
consent; older forms of FIDIC contract use approval. The Engineer
should be careful to use the appropriate term.
Older forms of FIDIC contract do not specify any time limits for submission
and appointment of the Contractors Representative. Recent forms of FIDIC
contract require that the Contractor shall submit his proposal prior to the
Commencement Date [see Section II-2.5].
It is important that the Contractors Representative be appointed as soon as
possible after the Contract has come into force [see Section II-1.1 for
Contract Award], to enable the many communications necessary at the start
of the Contract.
The Engineer should, in writing:
Immediately after the Contract comes into force, prompt the Contractor to
submit his written proposal for appointment of the Contractors
Representative;
Promptly review the Contractors proposal and:
August 2011
II-2 /8
Recent forms of FIDIC contract provide that the Contractor shall not,
without the Engineers prior consent, revoke the appointment of the
Contractors Representative.
II-2.5
Commencement Date
The signing date of the Works Contract is not necessarily the date for
commencement of the Time for Completion of the Works. Most forms of
Works Contract (certainly FIDIC) require that the Engineer shall give to the
Contractor a Notice of Commencement Date.
The Commencement Date marks the start of the Time for Completion, and
therefore determines the date by which the Contractor shall substantially
complete the Works. Insofar as the Contract may provide for the Employers
August 2011
II-2 /9
August 2011
II-2 /10
provide that the Employer will not give Access to and Possession of Site
[see Section II-2.13] until he has received an acceptable Performance
Security from the Contractor [see Section II-2.6]. The Contractor cannot start
work on Site until those obligations have been fulfilled. Regardless of such
delays, however, the Commencement Date remains unchanged and the Time
for Completion continues to be counted from that date. If the delay is outside
the Contractors control, then the Contractor might be entitled to claim an
extension of the Time for Completion [see Section II-4.13 Delays, Extension
of Time for Completion & Associated Costs].
Under recent forms of FIDIC contract the Engineer should, as necessary:
at the time of giving notice of the Commencement Date, formally advise
the Contractor of his obligation to submit his proposal for appointment of
the Contractors Representative [see Section II-2.4].
II-2.6
Performance Security
The Contract will require that the Contractor shall obtain and provide to the
Employer, copied to the Engineer, a Performance Security (sometimes called
a Performance Bond). The Performance Security, from a bank or financial
institution acceptable to the Employer, entitles the Employer to monetary
compensation (to the limit of the amount of the security) in the event and to
the extent that the Contractor fails to execute the Contract satisfactorily. The
amount and currency of the Performance Security will be stated in the
Contract, usually in the Appendix to Tender.
There are many forms of performance security used in the construction
industry (including unconditional/on-demand forms and conditional forms).
The actual form to be provided will have been included in the Contract
documents.
The Performance Security is required to be valid until the Works have been
satisfactorily completed, the Defects Notification Period has expired, defects
have been rectified, and a Performance Certificate [see Section II-7.9] has
been issued.
[Note: Defects Notification Period and Performance Certificate are defined
terms of recent forms of FIDIC contract. Defects Liability Period and Defects
Liability Certificate are the equivalent terms in older forms of FIDIC contract.]
The Contract should, but might not, state the required period of validity of the
Performance Security. Sureties usually insist on a stated expiry date. If not
stated in the Contract, the required period of validity should be until the
anticipated date computed from Commencement Date + Time for Completion
+ Defects Notification Period + 28 days.
August 2011
II-2 /11
The Contract should state the period within which the Contractor shall provide
the Performance Security to the Employer. Old and recent forms of FIDIC
contract require that an acceptable Performance Security shall be provided
within 28 days after the Employers Letter of Acceptance.
Acceptance of the Performance Security is the Employers contractual
obligation, but the Employer might expect the Engineers assistance. The
Engineer should:
prompt the Contractor, as necessary and in writing, to deliver the
Performance Security on time.
if the Contractor does not submit the Performance Security on time, give
formal notice to the Contractor to remedy his default, failing which the
Employer may consider termination of the Contract.
check, word-by-word, that the Performance Security complies with the
Contract proforma and is in the correct amount and currencies, and advise
the Employer accordingly and in writing.
if the submitted Performance Security complies with Contract
requirements, advise the Employer that he should confirm acceptance in
writing to the Contractor, with a copy to the Engineer.
This last requirement is important. Both old and recent forms of FIDIC
contract stipulate that the Engineer shall not issue any Interim Payment
Certificates [see Section II-3.11 Interim Payment Certificates], including for
an Advance Payment [see Section II-2.7], until the Performance Security has
been received and approved by the Employer. FIDIC Conditions require that
all approvals shall be in writing, and the Engineer needs evidence of that
approval. Furthermore, the recent forms of FIDIC contract state that the
Employer may withhold Access to and Possession of Site [see Section II2.13] until the Performance Security is received.
A copy of the Performance Security should be retained by the Engineer; not
the original. The original must be retained safely by the Employer throughout
the Contract, and returned by him to the Contractor within the specified period
after the Performance Certificate has been issued.
During the Contract, the Engineer must:
monitor that the validity of the Performance Security is maintained in the
appropriate amount until the Performance Certificate (called the Defects
Liability Certificate under old forms of FIDIC contract) is issued.
[See Section II-4.3 Continuing Validity of Securities & Insurance]
II-2.7
August 2011
II-2 /12
and should include within the Contract Documents a proforma of the Advance
Payment Security (often called a Bank Guarantee for Advance Payment) to
be delivered by the Contractor to the Employer before the Advance Payment
can be authorized.
Both old and recent forms of FIDIC contract also require that the Advance
Payment cannot be authorized for payment until after the Employer has
received and approved the Contractors Performance Security [see Section
II-2.6].
The Advance Payment Security, from a bank or financial institution
acceptable to the Employer, entitles the Employer, in the event of the
Contractors Default under the Contract, to reimbursement from the surety of
that part of the Advance Payment remaining to be repaid to the Employer by
the Contractor. Therefore, the validity of the Advance Payment Security must
be maintained in an appropriate amount until the Advance Payment has been
completely repaid to the Employer [see Section II-3.11 IPCs: Repayment of
Advance Payment and Section II-4.3 Continuing Validity of Securities &
Insurance].
The Advance Payment Security should be provided directly to the Employer,
copied to the Engineer. Acceptance of the Advance Payment Security is the
Employers contractual obligation, but the Employer might expect the
Engineers assistance. The Engineer should:
check, word-by-word, that the Advance Payment Security complies with
the Contract proforma and is in the correct amount and currencies, and
advise the Employer accordingly and in writing.
A copy of the Advance Payment Security should be retained by the Engineer;
not the original. The original must be retained safely by the Employer, and
returned by him to the Contractor after the Advance Payment has been repaid
by the Contractor.
It is recommended (and recent forms of FIDIC contract require) that the
Engineer authorize payment of the Advance Payment in an Interim Payment
Certificate (usually the first). For this purpose the Engineer needs written
evidence from the Employer that he has received and accepted the Advance
Payment Security.
The Contract will contain provisions for repayment of the Advance Payment
through deductions in the Engineers Interim Payment Certificates [see
Section II-3.11 IPCs: Repayment of Advance Payment].
During the Contract, the Engineer must:
August 2011
II-2 /13
II-2.8
Insurance
General Conditions of Contract, including older and recent forms of FIDIC
contract, typically prescribe that insurances will be obtained by the
Contractor. Sometimes the Particular Conditions may provide for Employerprovided insurance. This Section deals with the usual requirement for
Contractor-provided insurance.
Older and recent forms of FIDIC contract require the following equivalent
insurances to be provided:
A
Insurance of
/against:
B
C
Evidence to be
provided:
Copies of Policies
to be provided:
Older FIDIC
Works & Contractors
Equipment
3rd Party Insurance (including
Employers Property)
Accident or Injury to Workmen
Prior to start of any work on
Site
Red Book: Within 84 days after
Commencement Date.
Yellow Book: When required by
the Employer.
Recent FIDIC
Works & Contractors Equipment
Injury to Persons & Damage to
Property
Contractors Personnel
Within period stated in Appendix
to Tender
Only for A &B: within period
stated in Appendix to Tender
If, under the Contract, the Contractor designs major parts of the Works, he
may also be required to effect professional indemnity insurance.
FIDIC forms of contract require that evidence and, subsequently, copies of
insurance policies be submitted by the Contractor directly to the Employer. In
the older forms of FIDIC contract it is required that the Contractor notify the
Engineer that he has done so. Such notification is not necessary under recent
forms of FIDIC contract where the Engineer is part of the Employers
Personnel.
Older forms of FIDIC contract require that all insurances shall be in terms
approved by the Employer. In recent forms of FIDIC contract there is no
provision for the Employers approval. However, it is implicit that the
The Louis Berger Group, Inc.
August 2011
II-2 /14
insurances shall comply with the Contract requirements, and the Employer is
entitled to insist on the Contractors compliance. The Employer should
formally notify the Engineer whether or not the Contractors insurance
submissions comply, so that:
in the event of compliance: the Engineer can allow the Works to proceed
and certify any payment entitlements under the Contract for insurance;
in the event of non-compliance: the Engineer can issue to the Contractor
notice of requirement to remedy this default within the time stipulated in
the Contract or, if none is stated, within a reasonable time.
If the Contractor fails to comply, there is provision that the Employer may (but
is not bound to) effect and maintain the prescribed insurances, and to recover
the premiums therefor from the Contractor (e.g. by deductions from certified
payments owing to the Contractor). This situation, however, would be risky at
the beginning of the Contract when no monies are owing to the Contractor.
FIDIC forms of contract do not address the consequences of prescribed
insurances not being effected by either Party, except that the Contractor, as
the defaulting Party, is liable for any monies which (following an insurable
event) should have been recoverable under the insurances that the
Contractor failed to effect. But would the Employer escape liability in the
event that the Contractor becomes bankrupt? It is likely that the Employer
does not wish to take such risk, and would prefer to terminate the Contract.
An Engineers notice to the Contractor, requiring remedy of the default, would
be a prerequisite to the Employer later serving a valid notice of termination of
the Contract.
Older forms of FIDIC contract require that the Contractor shall provide prior
to the start of work at the Site evidence that the insurances required under
the Contract have been effected. This does not mean just Permanent Works;
it means any work, including temporary site installations. The Project
Manager must ensure that this requirement is observed.
Recent forms of FIDIC contract contain no such provision. It can only be
hoped that the period stated in the Appendix to Tender, within which the
Contractor must provide evidence of insurances, is sufficiently short to
preclude the possibility of the Contractor starting work. In any event, the
Contractor cannot start works on the Site until the Employer gives him
Possession of Site, which the Employer should not do until he receives an
acceptable Performance Security from the Contractor. The Engineer should
not unilaterally suspend any work by reason that evidence of insurances has
not been provided, which action could give the Contractor justification to claim
delay. The Engineer should formally advise the Employer that work is starting
before evidence of insurance has been provided and that the Engineer has no
authority to prevent work starting. It will be up to the Employer to choose what
to do, if anything.
The Louis Berger Group, Inc.
August 2011
II-2 /15
August 2011
II-2 /16
II-2.9
August 2011
II-2 /17
Traditional definitions:
- Materials incorporated
into Permanent Works
- Plant incorporated
into Permanent Works
- Equipment
- Labour
- Temporary Works
- Other (explain)
Contractors Equipment
Labour
Temporary Works
Other (explain)
II-2.10
August 2011
II-2 /18
The Contractors Works Programme [see Section II-2.11] should take into
account the lead times necessary for procedures that are the Contractors
responsibility to obtain statutory approvals and permits.
Delays caused by the Employer in failing to perform actions for which he has
responsibility for obtaining statutory approvals and permits could give the
Contractor justification to claim extension of the Time for Completion and/or
additional costs. The Engineer should, as necessary and appropriate, formally
prompt the Employer in this regard.
II-2.11
August 2011
II-2 /19
basis on which the Employer/Engineer will plan their activities and obligations
including issuing Drawings, handing over possession of Site and, possibly,
mobilization of the Engineers supervision resources.
The Programme will also become a base reference for the Engineers
determination of any Contractors claims for extension of the Time for
Completion arising from alleged disruption or delay.
A comprehensive Programme would show:
The order in which the Contractor intends to execute the Works, including
timing for each stage of design (if any), Contractors Documents,
procurement, off-site manufacture and fabrication, delivery to Site,
construction, erection and testing.
The timing and sequencing of the Works, taking into account the lead time
of procedures for obtaining any necessary Statutory Approvals and
Permits for which the Contractor has responsibility [see Section II-2.10].
Similar detail of works to be performed by Nominated Subcontractors
[see Section II-2.20].
A general description of the methods the Contractor intends to adopt in
execution of each major stage of the Works.
A reasonable estimate, for each major stage of the Works, of the
number/class of Contractors Personnel and number/type of Contractors
Equipment to be mobilized.
The Programme must show the Works will be completed within the Time for
Completion.
A problem could arise if a programme submitted with the Contractors Tender
is included in the Contract documents and, thereby, is part of the Contract.
Tenderers are invariably required to submit an outline programme with their
tenders. The Employers acceptance of the Contractors tender may have
been influenced by his ability to release Possession of Site or issue Drawings
in accordance with requirements of the tender programme. If the Contractors
submits a detailed Programme so different from his tender programme that it
brings forward required release of Possession of Site or Drawings (with which
the Employer might not be able to comply), then the Engineer should not
(except with the Employers written no objection) accept such Programme.
However, in the event that the Contractors tender programme was not
practicable, it would be unwise for the Employer to impose unnecessary
compliance with the tender programme.
The Contract might require that the Programme be computer generated using
proprietary software (which might be specifically stated), showing the critical
path between activities.
August 2011
II-2 /20
August 2011
II-2 /21
a document upon which the Contractor could base claims for extension of
the Time for Completion due to delays arising from late issue of Drawings,
late Possession of Site, instructed Variations, etc.
The older standard forms of FIDIC contract have no provisions addressing
repercussions of the Engineers continuing objection to the Contractors
Programmes and the Contractors inability to obtain the Engineers
consent/approval. This would appear to be an omission considering that
Possession of Site may be required on the basis of the Programme [see
Section II-2.13]. The Contractors ability to substantiate later claims for
delay might be diminished without a Programme to which the Engineer, by
having objection thereto, withheld consent/approval. However, the
Engineer cannot unreasonably withhold consent.
Considering the contractual significance of the Programme, the Engineer
must:
ensure that the Programme is reviewed in detail to judge its adequacy
and, based on the Contractors proposed resources, its attainability.
As soon as practicable after receipt of the Programme, the Engineer must:
give to the Contractor in writing either his consent/approval (as
appropriate) or comment on its deficiencies and inconsistencies. In the
latter case he should require the Contractor to resubmit an improved
Programme to obtain the Engineers consent/approval.
Only when a Programme has received the Engineers consent/approval
(or deemed consent/approval if the Engineer failed to respond), could the
Contractor use it for validation of a claim for extension of the Time for
Completion.
Under older forms of FIDIC contract, after consent/approval has been
given to the initial Works Programme, the Contractor is contractually
obligated to submit Works Programme Revisions only if the Engineer so
requires [see Section II-4.8]. Unlike the initial Programme, the Engineers
consent or approval is not required for Works Programme Revisions.
Recent forms of FIDIC contract require that:
o The Contractor shall submit his Programme within 28 days after the
Commencement Date [see Section II-2.5]. But there is no provision for
the Employers or Engineers approval or consent.
o The Programme shall be prepared in such detail described at the
beginning of this Section II-2.11 Works Programme.
There is no provision for the Programme to be prepared in such form and
detail as the Engineer might require; only that the Programme shall
The Louis Berger Group, Inc.
August 2011
II-2 /22
conform to the Contract requirements. Thus, the Engineer can only give
notice to the Contractor of the extent to which his Programme does not
comply with the Contract. The Contract states that if the Engineer does
not give such notice within 21 days after receiving the Programme, then
the Contractor shall proceed in accordance with that Programme, subject
to his other obligations under the Contract.
The Engineer must:
review the Programme in detail and give notice to the Contractor,
within the prescribed time, of the extent to which the Programme does
not comply with the Contract.
If the Programme does comply with the Contract, then the Engineer
should just acknowledge receipt. For reasons given below, he should
definitely not give nor imply any consent or approval.
Recent forms of FIDIC contract have deliberately omitted provision for
consent or approval. By doing so:
- consent or approval cannot be unreasonably withheld;
- if the Contractor submits an over-optimistic Programme, there is no
approved Programme to be used thereafter for the unquestionable
validation of a claim for extension of the Time for Completion;
- therefore, neither Party can misuse the Programme to achieve an
unfair advantage over the other.
Under recent forms of FIDIC contract, the Contractor is contractually
obligated to submit Works Programme Revisions whenever his current
programme becomes inconsistent with his actual progress [see Section II4.8 for Works Programme Revisions].
Cash Flow Estimate
Older forms of FIDIC contract require the Contractors submission, within a
stated time after the Contract has come into force [see Section II-1.1
Contract Award], of a Cash Flow Estimate, in quarterly periods, of all
payments to which he will become entitled under the Contract
Recent forms of FIDIC contract require (unless the Contract includes a
Schedule of Payments in accordance with which the Contractor will be paid in
instalments) the Contractors submission, within 42 days after the
Commencement Date [see Section II-2.5], of an estimate, in quarterly
periods, of payments he expects to become due under the Contract.
Both are only for the Engineers/Employers information, and are the nonbinding Contractors estimates of the payments to which he will become
The Louis Berger Group, Inc.
August 2011
II-2 /23
entitled under the Contract during each quarterly period. Neither older nor
recent forms of FIDIC contract require that the estimates be based on the
Contractors Programme, but this can be reasonably inferred. The older forms
of FIDIC contract require the estimate to be detailed which, although
interpretable, does indicate more than a single estimated quarterly amount.
These estimates of future payment entitlements, based on the Programme,
are very useful information:
o for the Employer to ensure that funding will be in place to enable interim
payments to the Contractor;
o against which the Engineer can monitor progress of the Works.
It is recommended that the Engineer encourage the Contractor to submit
estimates:
based on monthly projections tied to the activities and production rates of
the Programme;
broken down to segregate the value of Works intended to be completed
from other payments and deductions including Advance Payment and
repayment, Retention Money and other adjustments.
The value of Works completed is the only reliable criterion for quantifying
and charting the overall % progress of the Works compared to the
Programme. The Engineer will be expected to provide such progress charts in
his Project Progress Reports [see Section I-3.8 Progress Reports]. Under
recent forms of FIDIC contract the Contractor is obligated to submit Monthly
Progress Reports including charts comparing actual and planned progress
[see Section II-2.17]. Cooperation between the Engineer and Contractor in
establishing the breakdown of estimates necessary to facilitate a common
basis for both of their progress reporting obligations would be mutually
beneficial.
Under older forms of FIDIC contract, the Contractor is required to submit
revised estimates at quarterly intervals only if the Engineer so requires.
Under recent forms of FIDIC contract, the Contractor is obligated to submit
revised estimates at quarterly intervals. [See Section II-4.8 Cash Flow
Revisions.]
II-2.12
August 2011
II-2 /24
Older forms of FIDIC contract refer neither to Quality Assurance nor Quality
Control, apart from the implicit requirement that Works shall comply with
Contract requirements.
Recent forms of FIDIC contract state only that the Contractor shall institute
a Quality Assurance System which the Engineer is entitled to audit, but
without any specific requirement that the Contractor shall submit his System
to the Engineer. However, the Contractor is required to submit details of all
procedures and compliance documents to the Engineer for information
before each stage of design or construction commences. Procedures and
compliance documentation could be construed to apply to Quality Assurance
and/or Quality Control.
Quality Assurance
It is common for Particular Conditions to require that the Contractor shall
submit, within a prescribed time at the beginning of the Contract, his Quality
Assurance System for the Engineers consent; and perhaps therein to
describe the required features of such System. It is a common requirement
that the Contractor shall designate an on-Site, full-time Quality Control
Manager.
In reviewing the Contractors Quality Assurance System, the Engineer should
be cognisant of the above definitions. The Contractors provision of an ISO
certification is not sufficient. Neither is the submission of a Quality Policy.
What is required is a Quality Assurance System directly referenced and
applicable to the Works Contract, and to the specific Works to be designed (if
applicable) and constructed by him thereunder. It should not just reiterate the
Specification clauses with which he must comply.
The Quality Assurance System must describe:
o The organization and procedures that the Contractor will implement to
ensure Quality Control specifically on the subject Works Contract. The
The Louis Berger Group, Inc.
August 2011
II-2 /25
o
o
o
o
August 2011
II-2 /26
Quality Control
As part of his Quality Assurance System the Contractor should submit, at the
beginning of the Contract, the standard forms he proposes to use as Quality
Control documents, including:
o Standard forms for recording results of the various materials tests
prescribed in the Contract.
o Standard forms for summarizing test results and, where required,
presenting statistical analyses of the test results.
o A format for regular submission of test reports to the Engineer.
o Standard forms for submission of samples of materials to be incorporated
into the Works;
o Standard forms whereby the Contractor will request the Engineers
inspection and (as appropriate) testing and/or measurement of completed
stages of the Permanent Works or Temporary Works:
- before works are covered up (e.g. layers of earthwork fill, base
formations, asphalt courses, below-ground foundations);
- before works are incorporated into further work stages (e.g. steel bar
reinforcement placements to be incorporated into concrete work);
- for Temporary Works that are critical to proper execution of Permanent
Works, before they are used for their function (e.g. formwork for
concrete);
- before natural materials that are intended to be incorporated into the
Works are transported to Site;
- before fabricated items are transported to Site (e.g. fabricated
steelwork, precast concrete);
- before manufactured Plant is packaged for storage or transport.
The Contractors motivation to provide comprehensive Quality Control
documentation should be to establish an unquestionable record
demonstrating his compliance with Contract requirements.
The Engineer must:
be satisfied with the Contractors Quality Control documentation, as it
affects acceptance of the Works and his certification of payments therefor.
It behoves the Engineer and the Contractor to cooperate in the development
of formats for the various standard Quality Control forms to their mutually
satisfaction.
Older forms of FIDIC contract do not require that the Engineer shall give
approval of or consent to test results or completed stages of Works, although
they do provide that the Engineer may reject such.
August 2011
II-2 /27
II-2.13
August 2011
II-2 /28
Older forms of FIDIC contract provide that, save insofar as the Contract
may prescribe otherwise, the Employer shall, from time to time, give access
to and possession of portions of the Site:
- as may be required to enable the Contractor to commence and
proceed, with due dispatch, with execution of the Works in accordance
with his Works Programme [see Section II-2.11];
- otherwise in accordance with such proposals as the Contractor shall
make by notice to the Employer copied to the Engineer.
Under such Contract provisions, the obligation for giving possession of Site in
a timely manner is the Employers; but the Engineers assistance should be
provided, since it is the Engineer who receives and reviews the Contractors
Programme.
Recent forms of FIDIC contract provide that the Employer shall give to the
Contractor right of access to and possession of all parts of the Site within the
time(s) stated in the Appendix to Tender. Except that, if no such times are
stated, the Employer shall give right of access to and possession of Site as
may be required to enable the Contractor to proceed in accordance with his
Programme. In this latter case the Engineer should act as recommended
above. Recent forms of FIDIC contract also provide that the Employer will not
give right of access to and possession of Site until the Contractor has
submitted an acceptable Performance Security [see Section II-2.6].
Thus, if specific time(s) within which the Employer shall give access to and
possession of Site are prescribed in the Contract, the Engineer should:
formally advise the Employer of this obligation, giving the actual dates as
derived from the Contract provisions.
If the Contract does not stipulate any such time(s), the Engineer should,
based on a review of the Contractors first submitted Programme, (whether or
not the Programme is acceptable as complying with Contract requirements):
interpret when the Contractor will require access to and possession of
either the whole of or successive portions of the Site, and obtain the
Contractors confirmation of that interpretation;
formally advise the Employer of the date(s) by which he should give
access to and possession of the whole of or successive portions of the
Site (as agreed by the Contractor based on his Programme), unless and
until he receives written requests otherwise from the Contractor.
August 2011
II-2 /29
II-2.14
Construction License
In many countries the local Law requires that the Contractor shall obtain a
construction license to execute construction works, and there may be
Contract requirements in this respect. Standard forms of FIDIC contract do
not address this issue, but they do require compliance with local Law. Any
such required license should be obtained/issued not later than when the
Employer gives to the Contractor Access to and Possession of Site [see
Section II-2.13].
Unless the Contract contains provisions therefor, the Engineer should:
consult with the Employer and Contractor to establish responsibilities of
the respective Parties and procedures for obtaining/issuing a construction
license;
thereafter monitor that the procedures are followed and obligations
performed.
II-2.15
Issuing Drawings
Drawings included in the Tender documents are for the purpose of tendering
only. Tender drawings do not constitute Contract Drawings.
Under contracts where design has been performed by or on behalf of the
Employer, it is typically stipulated (as in forms of FIDIC contract) that the
Engineer shall issue two copies of the Contract Drawings (and subsequent
Drawings) to the Contractor. If the Engineer has not been involved in the
design, then obviously the Engineer must first obtain the Drawings from the
Employer.
Delay in the issuing of any or all of the Drawings could provide the Contractor
with justification to claim extension of the Time for Completion and/or
additional costs. To avoid such circumstance arising, the Drawings should be
issued to the Contractor not later than the Commencement Date [see
Section II-2.5].
The Engineer should:
Before issuing a notice of Commencement Date, ascertain that:
- the Drawings have been prepared in the Contract language;
- the Drawings are suitably identified by title and reference number, and
stamped or labelled approved for construction;
- the Employer is able to hand over to the Engineer the requisite
numbers of Drawings.
Insist that the Employer transmits the Drawings to the Engineer in writing,
with every Drawing identified by title and reference number.
August 2011
II-2 /30
II-2.16
Upon receipt from the Employer, promptly issue to the Contractor the
requisite numbers of copies of the Drawings. The transmittal must be in
writing, with every Drawing identified by title and reference number.
Meteorological Records
Most forms of contract provide that the Contractor is:
o deemed to have obtained all available data on climatic conditions of the
Site and its surroundings, and based his tender, amongst other things,
thereon;
o entitled to extension of the Time for Completion in the event of
exceptionally adverse climatic conditions.
This does not mean that the Contractor is entitled to a time extension
whenever adverse weather conditions slow his progress. The climatic
conditions have to be exceptionally adverse.
It is hoped that the Contract provides a definition of exceptionally adverse
climatic conditions. If not, it will be necessary to adopt one. A reasonable
definition to be adopted by the Engineer, in rendering determinations, would
be that suggested in FIDICs guidelines on its recent (1999) forms of
contract:
o Exceptionally adverse climatic conditions are conditions having a
probability of occurrence, at or near the Site, less than five times the Time
for Completion.
For example, where the Time for Completion is 2 years and the Contractor in
his Programme has planned in November to perform asphalt works (which
cannot be performed when the temperature falls below 5oC) and the
maximum daily temperature is below 5oC on 10 days: If statistical records
show, over the past 10-year period, that maximum daily temperatures were
below 5oC for a maximum 7 days in November of any one year, then the
Contractor would be entitled to a 3-day extension of the Time for Completion
if this particular activity is defined on the Works Program as a critical-path
activity.
The importance of keeping detailed records of climatic conditions is obvious.
Contracts usually place responsibility upon the Contractor to obtain/record
and provide such data monthly to the Engineer, and the Engineer should
monitor that the Contractor fulfils such obligation from the Commencement
Date. The Engineer should require, if not already stipulated in the Contract,
that
August 2011
II-2 /31
II-2.17
Contractors Reports
Records of Contractors Personnel & Equipment
These records are essential to facilitate the evaluation of claims and
Variations. It is necessary to establish basic record-keeping from the
Commencement Date [see Section II-2.5].
Recent forms of FIDIC contract require that the Contractor shall submit for
each calendar month until a Taking-Over Certificate is issued for the whole of
the Works, in a form approved by the Engineer:
o Details showing the number of each class of the Contractors Personnel
and each type of the Contractors Equipment on Site.
General Conditions of older forms of FIDIC contract require this information
to be submitted only if required by the Engineer, at such intervals as he may
prescribe. The Engineer should:
at the beginning of the Contract, instruct the Contractor to submit this
information at least monthly.
By definition of recent FIDIC forms of contract:
August 2011
II-2 /32
August 2011
II-2 /33
August 2011
II-2 /34
Under any recent form of FIDIC contract the Engineer should, at the
beginning of the Contract, advise/remind the Contractor that:
Monthly Progress Reports are to be submitted for each calendar month
within 7 days after the last day of the month to which the reports relate.
The first Monthly Progress Report is to be submitted within 7 days after
the last day of the first full calendar month following the Commencement
Date. The period to which this first report relates shall be the period
commencing from the Commencement Date. (For example: if the
Commencement Date is 15 April, the first Report, covering the period 15
April to 31 May, is required to be submitted by 7 June.)
Interim Payment Certificates in respect of the Contractors Statements will,
in accordance with (state relevant clause of Contract) be withheld until
the Contractor has submitted a Monthly Progress Report for the period to
which a Contractors Statement relates.
Should the Engineer disagree with any facts of the Contractors Monthly
Reports, he must:
promptly notify such disagreement in writing to the Contractor (failing
which the Contractors information would be deemed as accurate), copied
to the Employer.
attempt to obtain the Contractors agreement to submit corrected records.
in the event that the Contractor fails to justify his submitted records and
disagrees to amend them, confirm the Engineers disagreement and the
Engineers records to the Contractor (copied to the Employer).
II-2.18
August 2011
II-2 /35
August 2011
II-2 /36
In the event that the Contractor does not complete the whole of the Works
within the Time for Completion, the adjustment multiplier for works executed
after the Time for Completion must be capped at its value applicable to the
month during which the Time for Completion expired [see Section II-3.11
IPCs: Price Adjustment]
In the event that the Contract excludes provision for price adjustment but an
extension of the Time for Completion is granted as a result of delay caused
by the Employer, the Contractor may be entitled to introduction of price
adjustment upon the value of works so delayed and performed after expiry of
the original Time for Completion [see Section II-4.13 Delays, Extension of
Time for Completion & Associated Costs].
II-2.19
August 2011
II-2 /37
August 2011
II-2 /38
August 2011
II-2 /39
latter circumstance the Engineer should, when giving consent, advise the
Contractor of his superintendence obligations.
Limit of Value of Works to be Subcontracted
Many contracts require that the Contractor shall not subcontract more than a
specified percentage of the Contract Price. Such requirement begs the
question What is a subcontract?
Older forms of FIDIC contract define a Subcontractor as:
any person named in the Contract as a Subcontractor for a part of the
Works or any person to whom a part of the Works has been subcontracted
with the consent of the Engineer
However, since these contracts state that the Contractor is not required to
obtain consent for the provision of labour or Materials, therefore suppliers of
labour or Materials do not fall within the definition of Subcontractor unless
named as such in the Contract. Nothing is said about suppliers of Equipment.
In so far as Nominated Subcontractors obviously have the consent of the
Engineer, therefore they must fall within the definition of Subcontractor.
Recent forms of FIDIC contract merely define a Subcontractor as:
any person named in the Contract as a subcontractor, or any person
appointed as a subcontractor, for part of the Works
without mentioning Engineers consent. Nominated Subcontractors obviously
fall within this definition. Since these contracts state (under a clause entitled
Subcontractors) that the Contractor is not required to obtain consent to
suppliers of Materials, it could be inferred that such suppliers are
nevertheless deemed as subcontractors. But what about suppliers of labour,
Plant or Equipment?
The Engineer should be careful not to jump to a determination of Contractors
breach of Contract for subcontracting works exceeding the specified limit. He
should fully discuss the matter with the Employer, hopefully to agree what
reasonably constitutes a subcontract for the purpose of assessing if this limit
has been exceeded. It should be remembered that the Contractor is himself
capable of applying his own interpretation of the Contract against which it
might be difficult to argue contractually and conclusively.
The following guidelines are suggested:
o The value of works undertaken by Nominated Subcontractors should be
included, but only to the limit of Provisional Sums provided in the original
Contract for works intended to be undertaken by Nominated
Subcontractors.
o The value of any subcontract for execution of Permanent and/or
Temporary Works, together with any supply of Materials, Plant, Equipment
The Louis Berger Group, Inc.
August 2011
II-2 /40
II-2.20
Nominated Subcontractors
Nominated Subcontractors are subcontractors nominated by the Employer or
imposed upon the Contractor not, as is sometimes misunderstood,
subcontractors nominated by the Contractor in his Tender.
Nominated Subcontractors, if required at all under the Contract, are typically
specified for specialist works which a general contractor is unable or not
permitted to perform. For example, an electrical utility owner might permit
relocation of a transmission line (required under the Contract) only to be
executed by a specialist contractor pre-approved by the utility owner to
perform such works. Provisional Sums may be included in the Contract to
cover such works, the primary cost of which is not under the Contractors
control.
The basic definition of a Nominated Subcontractor (as in recent forms of
FIDIC contract) is that of a Subcontractor who is stated in the Contract as a
Nominated Contractor, or who the Engineer instructs the Contractor to
employ to execute certain works under a Provisional Sum or as a Contract
variation. Older forms of FIDIC contract both extend and restrict the definition
to meaning any Subcontractor who is nominated, selected or approved by the
Employer or Engineer to perform works or services for which Provisional
Sums are included in the Contract.
Under FIDIC contracts the definition of a Provisional Sum is a sum
described as a Provisional Sum and included in the Contract for any part of
the Works, which may be used in whole or in part or not at all on the
instructions of the Engineer, but to which the Contractor has entitlement only
to payment for works so instructed by the Engineer. [See Section II-3.2
Provisional Sums.]
Thus, the Engineer must be careful to read the specific Contract clauses
relating to Nominated Subcontractors, in respect of:
definition;
provisions for the Contractors objection;
any required terms of the subcontract;
provisions for the Nominated Subcontractors indemnification of the
Contractor from and against:
August 2011
II-2 /41
August 2011
II-2 /42
II-2.21
August 2011
II-2 /43
If there is a Contract clause, as in forms of FIDIC contract, that the law of the
country shall apply to the Contract (according to which the Contract shall be
construed), then the Contract must be administered in accordance with that
law. The Engineer cannot insist that only the Contract provisions need prevail
for example, under a form of FIDIC contract, that documentation need only
be prepared in the Contract language, or that the Contracts Taking-Over
provisions prevail over local law requirements for Hand-Over of the Works on
completion.
Problems might arise where requirements of the applicable law contradict
prescribed provisions of the Contract. Under such circumstance, such
contradictions should be identified early in the Contract, in order that agreed
resolution or compromise may be established, formally agreed (between the
Employer, Contractor and Engineer) and recorded.
Otherwise, if provisions of the Contract and local law are not in conflict
(although they may be different), then provisions of both references should be
satisfied in tandem.
II-2.22
August 2011
II-2 /44
Origin for the various Materials and Plant. The Engineer may not be
permitted to accept (and, therefore, not to certify payments for) Materials
and Plant for which Certificates of Origin have not been provided.
o Ditto for equipment and vehicles that will become the property of the
Employer.
o The Contractors Personnel engaged in the Country of the Project must be
citizens of, and carry passports of, an eligible country.
The Engineer must, at the beginning of the Contract:
be conversant with any such rules;
remind the Contractor of these requirements;
establish procedures to demonstrate and record compliance;
and, during the Contract:
ensure that acceptable compliance documents are provided before works
are accepted and certified for payment.
II-2.23
August 2011
II-2 /45
is obliged to pay VAT, but will be reimbursed VAT within a certain period after
compliance with certain application procedures?
The Engineer should, at the beginning of the Contract, consult with the
Employer and Contractor to establish procedures to be followed respectively
by the Contractor, Employer and Engineer:
to achieve the Contractors exemption from VAT;
to facilitate, without unreasonable delays, cross-border imports of
Materials, Plant and Equipment for execution of the Works;
to achieve the Contractors exemption from import/excise duties, levies,
etc.
Export after Completion of Works
It must be remembered that Contractors Equipment imported, under Contract
provisions, free of import/excise duties, levies, etc., has been so imported
solely for executing works under the Contract. Such Equipment must not be
used for other purposes, and must be exported after the works for which it is
used are completed.
II-2.24
Contractors Mobilization
The beginning of the Contract is a period during which the Contractor and
Employer each have several obligations to fulfil including:
Contractor:
Employer:
Appointment of Contractors
Appointment of Engineer
Representative
Mobilization of Engineers Personnel
Submissions of/for
Provision of Drawings
- Performance Security
Acceptance of:
- Advance Payment Security
- Performance Security
- Insurances
- Advance Payment Security
- Breakdowns of Lump Sums
- Insurances
& Unit Rates
Giving Access to & Possession of Site
- Works Programme &
Issuing Construction License
Cash Flow
Statutory Approvals & Permits
- Quality Assurance System
(if relevant)
- Subcontractors
Establishment of Procedures for
Obtaining Statutory Approvals
Imports and Taxes
& Permits (if relevant)
General Mobilization
This early period is often invoked by the Contractor, in subsequent claims for
extension of the Time for Completion, for the Employer having not fulfilled an
obligation (e.g. late or problematic possession of Site). The Engineer, in
August 2011
II-2 /46
II-2.25
August 2011
II-2 /47
August 2011
II-2 /48
Hopefully the Contract includes provisions that the Contractor shall provide
safety apparel for the Engineers staff.
The Project Manager should:
Either ensure that the Contractor provides for the Engineers staff, or
procure from LBG petty cash:
- hard hats and reflective vests
- life jackets (as necessary)
- protective footwear, eyewear, earphones, gloves (as necessary)
Either ensure that the Contractor provides & maintains in each of the
Engineers offices, or procure/maintain from LBG petty cash:
- first aid kit
- fire extinguishers
Prepare and post memoranda conspicuously at each of the Engineers
offices instructing staff of:
- availability of hard hats, reflective vests and other protective
apparel;
- LBG requirement to wear hard hats (and, as appropriate, other
protective apparel) at all times during their supervision of Works;
- availability of first aid kit;
- contact numbers of the Contractors Safety Officer and other
emergency numbers (doctor, hospital, fire brigade, police);
- location and operation of fire extinguishers;
- emergency evacuation procedures.
II-2.26
August 2011
II-2 /49
Events Log
The Resident Engineer on each Works Contract (i.e. the most senior of the
Engineers on-Site representatives) should keep a running Events Log,
chronologically recording significant events from the beginning of and
throughout the execution of the Works. Such Events Log will be invaluable as
a readily available reference, when writing progress reports and reviewing the
Contractors claims, to the sequence of events and any delays.
On a multi-contract project, the Project Manager could request the Resident
Engineers to submit their Events Logs at the end of each month with their
draft Monthly Progress Reports [see Section I-3.8]; perhaps more regularly
at the beginning of the Works Contracts until the format and detail are
established. The Project Manager could then augment the Log with
submission events of which the Resident Engineer might be unfamiliar.
It is suggested that the Events Logs be in Excel spreadsheet format, in such
form as presented in Appendix K.
August 2011
II-2 /50
Check
Comment
August 2011
Guideline Requirement
II-2.14 Construction License:
Consult Employer /Contractor to establish requirement /responsibility
II-2.15 Issuing Drawings: (if design is Employer's responsibility)
Before notice of Commencement Date, ensure that Drawings available
Engineer obtain from Employer & issue to Contractor
II-2.16 Meteorological Records:
Instruct Contractor of required form & detail
Obtain from local Meteorological Station (if available & representative)
II-2.17 Contractor's Monthly Reports (incl. Labour /Equipment returns):
Instruct Contractor of required form /detail /frequency (if not in Contract)
Engineer's staff perform own regular counts of Labour /Equipment on Site
II-2.18 Price Adjustment Formula & Indices: (if applicable)
Check sources of indices are readily available & accessible
Check each index description is uniquely identifiable in source data
Obtain indices at Base Date
II-2.19 Consent for Subcontractors: (except those named in Works Contract)
Check Contract limit of value of Works that can be subcontracted
Check limit of Engineer's authority for consent without Employer approval
Instruct Contractor of form & detail required for Engineer's consent
Contractor's submissions for consent
Engineer's consent (with /without Employer approval as appropriate)
II-2.20 Nominated Subcontractors: (if applicable)
Read & follow Contract provisions for:
Definitions of Nominated Subcontractors & Provisional Sums
Contractor's objection
Nominated Subcontractors' indemnification of Contractor
Contractor's coordination of Nominated Subcontractor's work
Contractor's mark-up for overhead & profit
II-2.21 Compliance with Local Law:
Check requirements for:
Maintenance of 'Site Book' to record instructions & design changes
QC documents in local language as well as Contract language
Requirements for inspection by State Inspectorate
Documents required for 'Hand-Over' of Works
Requirements for statutory 'Commissions' for Hand-Over of Works
Hand-Over to different Regional Authorities (if Works span Regions)
II-2.22 Rules of Origin & Nationality: (if applicable)
Check & determine requirements /procedures for certification of:
Origin of Plant /Materials /equipment to become Employer's property
Nationality of Employer's Personnel
II-2.23 Imports & Taxes: (if applicable)
Check & determine Contract provisions /procedures for exemption from:
Value Added Tax
Import/excise duties on Materials /Plant
Construction consumables
Contractor's Equipment to be exported after use
Income taxation of expatriate personnel
II-2.24 Contractor's Mobilization:
Monitor & keep detailed records of:
Contractor's mobilization activities
Contractor's performance of obligations at start of Contract
Employer's performance of obligations at start of Contract
II-2.25 Safety, Security & Protection of the Environment:
Obtain applicable Laws of Country
& compare with Contract provisions to determine governing requirements
Check Contractor provides safety clothing, first aid facilities, emergency
& evacuation procedures
Safety of Engineer's Staff:
Provision of safety clothing & first aid facilities
Post instruction for safety compliance & emergency procedures
II-2.26 Diaries & Events Log:
All supervision staff to maintain daily diaries of Contractor's & own activities
Prepare standard diary forms for subordinate Site staff
Maintain Events Log starting at beginning of Contract
The Louis Berger Group, Inc.
Check
Comment
August 2011
II-3.
II-3.1
August 2011
II-3 /1
II-3.2
Provisional Sums
Definition & Payment Entitlement
Older forms of FIDIC contract define a Provisional Sum as:
a sum included in the Contract and so designated in the Bill of
Quantities for the execution of any part of the Works or for the supply of
goods, materials, plant or services, or for contingencies, which sum may
be used, in whole or in part, or not at all, on the instructions of the
Engineer, but to which the Contractor has entitlement only to payment for
works so instructed by the Engineer. The Contractor shall be entitled to
only such amounts to which the Provisional Sums relate as the Engineer
shall determine The Engineer shall notify the Contractor of any
determination , with a copy to the Employer.
Recent forms of FIDIC contract define a Provisional Sum as:
a sum (if any) specified in the Contract as a provisional sum, for the
execution of any part of the Works or for the supply of Plant, Materials or
services Each Provisional Sum shall be used, in whole or in part, in
August 2011
II-3 /2
accordance with the Engineers instructions The total sum paid to the
Contractor shall include only such amounts, for the work, supplies or
services to which the Provisional Sum relates, as the Engineer shall have
instructed.
All forms of FIDIC contract provide that for each Provisional Sum the
Engineer may instruct work to be executed, or for goods, materials, Plant or
services to be supplied:
o by the Contractor. In which case the Contractor is entitled to payment in
accordance with the Contract provisions for Variations [see Section II-3.4
Valuation of Variations].
o For Red Book contracts: by a Nominated Subcontractor [see Section II2.20 for definition and discussion of Nominated Subcontractors]. In this
case the Contractor is entitled to payment of the actual amount due to the
Nominated Subcontractor, plus a sum for the Contractors overhead and
profit calculated from the relevant percentage rate (if any) stated in the Bill
of Quantities.
o For Yellow Book contracts: the evidenced actual amounts paid by the
Contractor, plus a sum for the Contractors overhead and profit calculated
from the relevant percentage rate (if any) stated in the appropriate
Contract Schedule (recent FIDIC) or Preamble to the General Conditions
(old FIDIC). [Note: Yellow Book contracts have no provision for
Nominated Subcontractors.]
o Recent forms of FIDIC contract add that If there is no such rate, the
percentage stated in the Appendix to Tender shall be applied.
Under FIDIC forms of contract:
o Works to be performed by the Contractor under Provisional Sums are
dealt with as Variations.
For discussion of Daywork being considered as a Provisional Sum, see
Section II-3.7.
Differences between Older & Recent Forms of FIDIC Red Book Contract
regarding Payment for work performed by a Nominated Subcontractor:
Under older forms of FIDIC contract, in regard to work instructed to be
performed by a Nominated Subcontractor:
o The Contractor is entitled to a percentage mark-up for overhead and
profit only if there is provision in the Bill of Quantities against which the
Contractor placed a percentage in his accepted Tender regardless of
any provision in the Appendix to Tender.
But under the recent form of FIDIC Red Book contract:
August 2011
II-3 /3
II-3.3
Variations
General Requirements
In any construction project there will be a need to change the initial
requirements as construction proceeds on Site. This may be a matter of the
Employer changing his mind about some requirement, or the Engineer may
need to issue further information which involves changes to the initial
requirements, or it may be necessary to correct a mistake in the information
which has been issued to the Contractor.
It must be remembered, however, that the Engineer is only authorized to
instruct Variations under (pursuant to) the Contract. The Engineer is not
empowered to instruct a variation of the Contract. A variation of the Contract
can be made only by the Parties to the Contract who are the Employer and
Contractor, either by Contract Addendum or other written agreement.
The Contractor cannot make any variation to the Works without the
Employers or the Engineers instruction or consent. FIDIC Conditions of
August 2011
II-3 /4
Contract allow the Engineer, but not the Employer, to instruct a Works
Variation. In this context a Works Variation means:
o For an As-measured (FIDIC Red Book) Works Contract:
Any change to the Works described in the Specifications and
Drawings, or to the sequencing or timing of the Works.
o For a Design/Build (FIDIC Yellow Book) Works Contract:
Any change to the Works described in the Employers Requirements,
the Specifications and the Contractors Proposal, or to the sequencing
or timing of the Works.
As part of the Engineers instruction of a Variation the Engineer must:
Inform the Contractor of the basis of payment for the varied works.
This need only be a simple, but important, statement that the varied works will
be valued:
o at existing unit prices of the Bill of Quantities; and/or
o in accordance with Contract provisions (quote clause) for Valuation of
Variations [see Section II-3.4].
Alternatively the Engineer may instruct that some or all of the varied works be
performed:
o as Daywork [see Section II-3.7].
Permitted Variations
Most contracts (including standard forms of FIDIC contract) provide that the
Engineer may make any variation of the form, quantity or quality of the Works
that he considers necessary or appropriate, and that he has authority (subject
to any limitation of that authority specified in the Contract as requiring the
Employers pre-approval) to instruct the Contractor to:
a) Increase or decrease the quantity of any Works included in the Contract.
Caveats: ~ Except that such changes do not necessarily constitute a
Variation.
~ No instruction is required for any increase/decrease in
quantities that does not result from an instructed Variation,
unless:
- the Contract requires that any quantity increase of any item
of Works requires a formal Variation or Addendum;
- the Contract requires a formal Variation or Contract
Addendum if the sum of the values of quantity
increases/decreases would increase the Contract Price.
b) Omit any Works.
August 2011
II-3 /5
c)
d)
e)
f)
August 2011
II-3 /6
August 2011
II-3 /7
August 2011
II-3 /8
August 2011
II-3 /9
II-3.4
Valuation of Variations
General Principles of Valuation
Contract provisions for Valuation of Variations apply to all variations of:
o For construction-only contracts (FIDIC Red Book): unit rates & prices, or
lump sums, for changed or new items of work;
o For design/build contracts (FIDIC Yellow Book): the Contract Price.
All forms of contract should contain provisions for valuing Variations. All forms
of FIDIC contract do. The principles of evaluation in both the older and
recent forms of FIDIC Red Book contract are similarly expressed as:
o Variations shall be valued at the rates and prices set out in the Contract
(i.e. the Bill of Quantities & Unit Prices - BoQ) if, in the opinion of the
Engineer, the same shall be appropriate.
o If the Contract does not contain any rates and prices applicable to the
varied work, the rates and prices set out in the Contract shall be used as
the basis for valuation so far as may be reasonable.
o Failing which, after due consultation by the Engineer with the Employer
and the Contractor, suitable rates or prices shall be agreed upon between
the Engineer and the Contractor.
o In the event of disagreement the Engineer shall fix such rates and prices
as are, in his opinion, appropriate and shall notify the Contractor
accordingly, with a copy to the Employer.
o Until such time as rates or prices are agreed or fixed, the Engineer shall
determine provisional rates to enable the Engineers certification of onaccount payments to the Contractor.
o Provided that where an instruction to vary the Works is necessitated by
some default or breach of Contract by the Contractor or for which he is
responsible, any additional cost so attributable shall be borne by the
Contractor.
Breakdowns of Lump Sums & Unit Rates, submitted by the Contractor at the
beginning of the Contract [see Section II-2.9] should be used as a source for
establishing new rates and prices based on the rates and prices set out in the
Contract.
It should be noted that the above principles state the requirement for due
consultation by the Engineer with the Employer and the Contractor. Under
recent forms of FIDIC contract, the requirement for consultation is given in
Sub-clause 3.5 Determinations, which also states that in the case of failure
to reach agreement the Engineer shall make a fair determination in
accordance with the Contract, taking due regard of all relevant circumstances.
August 2011
II-3 /10
It should be further noted that under older forms of FIDIC contract, any
representative of the Engineer, if so formally delegated authority by the
Engineer [see Section II-2.2 Engineers Delegation of Duties & Authorities],
can determine new rates and prices, or other adjustments to the Contract
Price.
Under recent forms of FIDIC contract, however, the Engineer cannot
delegate authority to render determinations [also see Section II-2.2
Engineers Delegation of Duties & Authorities] and must render such
determinations himself. However, it is submitted that an Engineers
determination is required only if the Parties cannot agree. The establishment
by agreement of new rates and prices, or adjustments of the Contract Price,
does not constitute a determination and, therefore, the Engineer can
delegate authority to do so.
Additional Principles Sometimes Included
In addition to the above general principles, older forms of FIDIC Red Book
contract (but not the recent one) provide that:
if the nature or amount of any varied work relative to the nature or
amount of the whole of the Works or to any part thereof, is such that, in
the opinion of the Engineer, the rate or price contained in the Contract for
any item of the Works is, by reason of the varied work, rendered
inappropriate or inapplicable, then, after due consultation a suitable
rate or price shall be agreed In the event of disagreement the Engineer
shall fix such other rate or price, as is, in his opinion appropriate Until
such time as rates or prices are agreed or fixed, the Engineer shall
determine provisional rates or prices , and
Provided also that no varied work instructed to be done by the Engineer
shall be valued (accordingly) unless, within 14 days of the date of
such instruction and, other than in the case of omitted works, before the
commencement of the varied work, notice shall have been given either:
(a) by the Contractor to the Engineer of his intention to claim extra
payment or a varied rate or price, or
(b) by the Engineer to the Contractor of his intention to vary a rate or
price.
Such additional principles provide amplification to the general principle that:
o Variations shall be valued at the rates and prices set out in the Contract
(i.e. the Bill of Quantities & Unit Prices - BoQ) if, in the opinion of the
Engineer, the same shall be appropriate.
For example, if the Contract has provision in the BoQ for construction of one
manhole and the Engineer is instructing a Variation to construct, say, twenty
manholes of similar kind, then the Engineers opinion may be that the unit
The Louis Berger Group, Inc.
August 2011
II-3 /11
August 2011
II-3 /12
August 2011
II-3 /13
However, the onus will be upon the Engineer and Employer to substantiate
such case it will not be the Contractors obligation to substantiate otherwise.
Incorporating Variations into the Bill of Quantities by Establishing New
BoQ Items for New & Varied Rates
The following recommendations are offered for incorporating variations and
new and varied unit prices into the Bill of Quantities (BoQ) as the Works
proceed.
Existing unit prices of the BoQ should be considered as fixed in so far as
they each apply only to a unique BOQ Item number with its unique
Description of work.
Item No. ~ Unit ~ Quantity ~ Description ~ Unit Price ~ Amount
No one or any of the underlined item parameters should be changed.
If a new unit price for a work item is determined as warranted by some
changed circumstance (for example, in case of a Variation and/or significant
quantity change for which the Contract permits establishment of a new unit
price), then a new unique BoQ Item number should be established with its
own unique Description (describing the new circumstance) against which the
new Unit Price is applied.
Consequently any re-rated work item will have:
New
~ Unit ~ Estimated ~ New Unique ~ New
~ Amount
Item No.
Quantity
Description
Unit Price
Similarly, if by a Works Variation new works are introduced into the Contract,
then a new BoQ item must be established:
~ Unit ~ Estimated ~ Unique
~ Unit Price ~ Amount
New
Item No.
Quantity
Description
If any work item is, by Variation, omitted entirely from the Contract (by
Variation or Addendum), then the subject BoQ Item should be retained in the
BoQ (together with its Item No., Unit, Description and Unit Price) but with its
original Quantity demonstrably reduced (by Variation) to zero. The BoQ Item
Number should not be re-used for other works.
Recommendations for Incorporating Variations and New Unit Prices into
the Bill of Quantities, by use of the above principles, are presented in
Appendix L. Following these recommendations will facilitate:
o Immediate identification and estimated costs of each Variation;
o A summary of aggregate cost of all Variations;
August 2011
II-3 /14
August 2011
II-3 /15
If, on the issue of the Taking-Over Certificate for the whole of the Works,
it is found that as a result of:
a) all varied work valued under Cl, and
b) all adjustments upon measurements of the estimated quantities set out
in the Bill of Quantities, excluding Provisional Sums, dayworks and
adjustments of price made under Cl (rise or fall in the cost of labour
and/or materials by use of price adjustment indices),
but not from any other cause, there have been additions to or
deductions from the Contract Price which taken together are in excess
of 15% of the Effective Contract Price (which. shall mean the
Contract Price, excluding Provisional Sums and allowance for
dayworks, if any) then. (subject to any action already taken under
Cl...), after due consultation. there shall be added to or deducted
from the Contract Price such further sum as may be agreed. or
failing agreement, determined by the Engineer having regard to the
Contractors Site and general overhead costs of the Contract. Such
sum shall only be based on the amount by which such additions or
deductions shall be in excess of 15 per cent of the Effective Contract
Price.
c) Other settlements might include lump sum or time-related settlements of
Contractors claims.
Examples:
- Prolongation costs during extension of the Time for Completion to
cover the Contractors extension of overhead costs. Care should taken,
however, that the Contractor is not doubly benefiting through recovery
of some or all of such overhead costs from the unit prices of additional
works for which the Time extension was granted. [See Section II-4.13
Delays, Extension of Time for Completion & Associated Costs:
Prolongation Costs]
- Lump Sum settlements of Claims [see Section II-4.11], sometimes in
Amicable Settlement to avoid litigation or arbitration;
- Lump Sum settlements to compensate the Contractor for loss of
overhead recovery from omitted works.
II-3.5
Variation Orders
FIDIC Conditions of Contract provide that variations of the Works shall be
instructed and valued by the Engineer. Variation Orders, in the context of
formal contractual documents (other than the Engineers written instruction of
a Variation), are not required nor even mentioned in FIDIC Conditions of
Contract. Variations Orders (VOs) are, however, a commonly used
mechanism in the construction industry of formalizing and providing an audit
August 2011
II-3 /16
trail of Variations. Other forms of contract and some Employers may require
formalizations of Variations by VOs.
If VOs are to be issued, it is recommended that the agreed procedures for
submittal to the Employer (for approval) and issue to the Contractor be
summarized in an introduction to the presentation of VO summaries in the
Engineers Progress and Completion Reports. An example of such
explanatory introduction is presented in Appendix L.
At the time of instructing a Variation, the full cost implications of the Variation
may not be known. The quantities of the varied works may not have been
comprehensively estimated. New or varied unit rates/prices for additional or
changed works may not have been agreed or fixed. In the circumstance that
any delay to execution of the Variation could cause delay to the overall
progress of the Works, it would be wise for the Engineer to obtain
Employer/Contractor agreement to proceed with the varied works while they
are being quantified and evaluated.
The preparation and issuing of VOs, with provision for the Employers
signature of approval, is recommended. In this respect:
VOs of significant value should be prepared and submitted in writing to the
Employer for approval as soon as possible after an instruction for a
Variation has been issued to the Contractor.
Each VO must be identified by a consecutive, unique number (e.g. VO
No.14)
Each VO must clearly describe the varied works and the reasons for their
requirement.
A VO must reference the relevant clause(s) of the Conditions of Contract
pursuant to which each Variation was instructed.
Each VO should provide estimated quantities of the varied works.
The Variation must be valued at the unit rates and prices agreed or fixed
after due consultation by the Engineer with the Parties.
Copies of records of documents relevant to the VO must be referenced in
and appended to the VO including, as appropriate:
- Employers instruction; or
- Engineers recommendation and Employers approval; or
- Contractors proposal, Engineers review comments and
recommendations, and Employers approval.
- Records of Engineers consultations with the Employer and Contractor.
- Detailed analysis and calculations from which varied or new unit rates
and prices were derived.
August 2011
II-3 /17
II-3.6
Value Engineering
Recent forms of FIDIC contract include provisions for Value Engineering
whereby:
The Contractor may, at any time, submit to the Engineer a written
proposal that (in the Contractors opinion) will, if adopted:
i) accelerate completion;
August 2011
II-3 /18
August 2011
II-3 /19
II-3.7
Daywork
As stated in Section II-3.3 Variations, the Engineer can instruct varied works
to be executed on a daywork basis. This means payment will be made
according to rates and prices of the Daywork Schedule of the Contract,
based on daily records submitted by the Contractor of resources used in the
execution of the previous days work, including:
o Names, occupations and time of the Contractors Personnel;
o Types and times of Contractors Equipment and Temporary Works;
o Descriptions and quantities of Materials and Plant incorporated in the work
(supported by receipts or other vouchers).
Unless the Engineer conscientiously verifies the resources applied to
Daywork, the Contractor might be tempted to exaggerate those resources.
For this reason, emphasis is put on the verification of Materials used and on
provision of daily records of other resources applied. The Engineer must
ensure that:
Daywork and resources applied thereto are monitored closely by the
supervision staff.
Complete daily records are submitted by the Contractor of resources used
in the execution of the previous days work.
The daily records are signed daily by the Engineer as accepted.
Examples of standard forms that could be prepared and used for recording
and accepting daywork records are presented at the end of Appendix J.
If the Contract does not include a Daywork Schedule, then payment cannot
be made on a daywork basis. A Contract Addendum would be required to add
a Daywork Schedule to the Contract.
Generally the Engineer would instruct varied works that are minor and
incidental to be performed by Daywork when there are no appropriate workitem rates/prices in the Bill of Quantities (BoQ). Generally a contractor is
August 2011
II-3 /20
II-3.8
Measurement of Works
For as-measured (FIDIC Red Book) contracts, interim payments to the
Contractor are typically based upon monthly measurement of quantities of
work executed, applying the rates and prices from the Bill of Quantities (BoQ).
A Method of Measurement (MoM) should always accompany the BoQ.
Preambles to the Bill of Quantities should state that the MoM shall be read
in conjunction with the BoQ. An example of typical Preambles is presented
under Appendix H. Examples of typical item coverages of an MoM for items
of the BoQ are presented in Appendix I.
On some contracts the MoM might have been included in the contract
Specifications; either Specifications specially prepared for the Contract, or
referenced, published, Standard Specifications of the Employer. Alternatively,
it might be a published Standard Method of Measurement (e.g. *ICE CESMM,
or a Countrys own standard publication) which specifies principles of
measurement and is incorporated (by reference) into the BoQ Preambles.
August 2011
II-3 /21
August 2011
II-3 /22
II-3.9
August 2011
II-3 /23
August 2011
II-3 /24
form similar to, but not more onerous than, that required as security
against the Advance Payment, and be valid until the relevant Plant and
Materials are properly stored on Site and protected against loss, damage
or deterioration.
The Contractors intent should be to maintain sufficient working stocks of
Materials on Site, such that interrupted deliveries will not delay execution of
the Works. As Works execution progresses, stockpile quantities will fluctuate
as material is taken for incorporation into the Works, while new material is
delivered. Therefore delivery receipts and vouchers will not reflect stockpile
quantities after commencement of their use in the Works.
The Engineer must ensure that:
Stockpile quantities are measured by the Engineer on or about the cut-off
date to which an Interim Payment Certificate will apply.
The principles for Measurement of Works described under Section II-3.8
are followed regarding:
~ The Engineer must give reasonable notice to the Contractors
Representative who shall:
- promptly attend or send a qualified representative to assist the
Engineer in making the measurement, and
- supply any particulars requested by the Engineer.
~ Should the Contractor not attend, then the measurement made by the
Engineer shall be considered the correct measurement.
~ If the Engineer and Contractor cannot agree the estimated quantities,
the Engineers estimate shall prevail.
II-3.10
August 2011
II-3 /25
o Any other items in the BoQ for which there is provision for payment.
o Amount for the percentage of the invoice value of Plant and Materials
sent/delivered to Site for incorporation into the Works but not yet so
incorporated [see Section II-3.9 Valuation of Plant & Materials Intended
for the Works].
o Adjustments for changes in costs of labour, Materials or other inputs to the
Works [see Section II-3.11 IPCs: Price Adjustments: According to Price
Adjustment Formula].
o Any other amounts to which the Contractor may be entitled under the
Contract or otherwise, including, for example, in respect of:
- adjustments for costs arising from changes in legislation [see Section
II-3.11 IPCs: Price Adjustments: Arising from Change in Law];
- adjustment for aggregate value of Variations exceeding a stated
percentage of the Contract Price [see Section II-3.4 Valuation of
Variations: Adjustments of the Contract Price];
- other settlements - for example, prolongation costs during extension of
the Time for Completion, settlement of claims and disputes, and
settlement to cover omitted works.
o Amounts to be added or deducted for the Advance Payment and
repayments [see Sections II-2.7 Advance Payment Security & Section
II-3.11 IPCs: Repayment of Advance Payment].
o Amounts to be deducted or added for Retention Money and its partial or
full release [see Section II-3.11 IPCs: Deductions for Retention Money,
and Payment of Retention Money].
o Application of Value Added Tax (if applicable).
o Deduction of amounts certified in all previous Payment Certificates.
The Contractors IPS must be accompanied by supporting documents
necessary for the Engineer to verify amounts claimed, including:
o Invoices or vouchers to verify claims for Materials and Plant yet to be
incorporated into the Works.
o Invoices to substantiate costs claimed under Provisional Sums.
o Records of agreed measurements.
o Detailed estimates of the value of executed Works yet to be measured by
the Engineer, for which on-account payment is requested.
Recent standard forms of FIDIC contract also require that the supporting
documents to the Contractors IPS must include:
o The Contractors Monthly Progress Report for the period to which the IPS
corresponds [see Section II-2.17 Contractors Reports].
August 2011
II-3 /26
Contracts typically require that the Contractor shall submit IPSs in such form
approved by the Engineer or, alternatively, as the Engineer may prescribe. It
is important that the Engineer:
Establish, in consultation with the Contractor, a standard format for IPSs
that will match the format to be used by the Engineer in his Interim
Payment Certificates [see Section II-3.11].
Require the Contractor to provide with each IPS details of the bank
account(s) to which payment(s) are to be made.
A recommended format for as-measured contracts is discussed in Section II3.11 and presented in Appendix M.
It is recommended that the Engineer require that:
The Contractors IPSs are consecutively numbered.
The first IPS (if applicable) is submitted for the Advance Payment.
Design/Build contracts may require the Contractors IPS to follow the same
principles as for as-measured contracts except that:
o The value of Works executed will be based on estimates (often derived
from an estimated percentage of progress) of the value of those parts of
the Works for which the Contract contains prices into which the Contract
Price has been broken down. For example, design will invariably have
been priced separately from construction.
o The value of completed Variations and Daywork will be added.
Alternatively, Design/Build contracts may include a Schedule of Payments
specifying the instalments in which the Contractor will be paid. In this case:
o If the instalments are not defined by reference to actual progress, and if
the progress is less than that on which the Schedule of Payments was
based, then the Engineer may, after due consultation with the Employer
and Contractor, determine revised instalments taking account of the extent
to which progress is less than that on which the instalments were
previously based.
o Payments shall not be made for Material and Plant sent/delivered to Site
for incorporation into the Works but not yet so incorporated.
II-3.11
August 2011
II-3 /27
August 2011
II-3 /28
days notice to the Employer, suspend work (or reduce the rate of work) [see
Section II-4.10 Works Suspensions] unless and until he receives the IPC or
evidence of payment in respect thereof before expiry of the 21-day notice
period. Such action by the Contractor would probably incur additional cost
and/or delay that would likely precipitate a subsequent claim, costs of which
the Employer might have ability to subrogate to the Engineer. If the Engineer
fails to issue the IPC within 56 days after receipt of the IPS and supporting
documents, the Contractor would be entitled to terminate the Contract [see
Section II-8.2 Termination by Contractor arising from Employers Default].
The Engineer must ensure that:
IPCs are issued as soon as possible, and never later than the time limit
prescribed in the Contract.
A question often arises as to whether or not the Engineer should certify
payment for Works executed but not yet confirmed as complying with the
Contract or for unfinished or defective Works. For example, should executed
concrete works be certified for payment until strength test results show
compliance with Contract requirements? Should certification be withheld for
concrete whose formwork has not been removed or whose surface finish is
unacceptable? The following principles should apply:
o Certification for payment should not be withheld for executed works which
the Engineer has no reason to believe will not, after testing, satisfy
Contract requirements. If later tests show the works to be defective, then
appropriate corrections of certified amounts can be made in subsequent
IPCs until the defects are corrected
o In case of executed works that are unfinished or defective, the Engineer
should give consideration to:
- whether or not the defect can be remedied;
- if the defect cannot be remedied, then payment therefor cannot be
certified;
- if the defect is correctable, what is the estimated cost of remedial work;
- if the estimated cost of remedial work is close to or greater than the
contract value of the work, then payment should not be certified;
- if the estimated cost of remedial work is less than the contract value of
the work, then the contract value should be certified but with a
deduction of the estimated cost of remedial work (such deduction could
be effected by certifying a lesser quantity);
- if the work is unfinished, then its contract value should be certified with
a deduction of the estimated cost of the finishing works (such
deduction could be effected by certifying a lesser quantity);
Notwithstanding those principles, if the Contractors performance is such that
there is a record of many executed works having been defective, then the
August 2011
II-3 /29
August 2011
II-3 /30
as the date 28 days prior to the latest date for submission of Tenders. The
Engineer should only certify payment of such increased/decreased costs after
receiving and verifying particulars of a claim therefor. Since the Engineer is
not an expert on law (and should not be expected to be) it behoves the
Contractor to submit a claim for increased costs, and the Employer to submit
a claim for decreased costs. Invariably the Engineer would need the
Contractors breakdown of unit rates/prices to determine the effect of such
changes in Law upon those rates/prices (for example, to determine the effect
of an increased fuel tax on the various rates/prices of the Bill of Quantities).
The Engineers requirement for the Contractor to have submitted breakdowns
of his rates and prices at the beginning of the Contract [see Section II-2.9,
Breakdown of Lump Sums & Unit Rates] would greatly assist such
determination.
Price adjustment shall, in general, be inadmissible for changes in Law
occurring after the Time for Completion (including any granted extensions of
Time) has expired. Exceptions to this general rule would be in respect of
varied works instructed during the Defects Notification (Liability) Period, or
varied works instructed so late during the Time for Completion that they could
only practicably be executed or finished during the Defects Notification
Period.
In accordance with a Price Adjustment Formula:
The Contract may contain a Price Adjustment Formula whereby the amounts
payable to the Contractor shall be adjusted for the rise and fall of the costs of
labour, specified Materials or other inputs to the Works. Such formula [see
Section II-2.18, Price Adjustment Formula & Indices] is typically expressed
as:
Pn = a + b (Ln / Lo) + c (En / Eo) + d (Mn / Mo) + .
where:
Pn = adjustment multiplier applied to the estimated contract value,
in the relevant currency, of work carried out in period n, this
period being a month unless otherwise stated in the Appendix
to Tender.
a = fixed coefficient stated in table of adjustment data included in
the Appendix to Tender, representing the non-adjustable
portion of contractual payments.
b = coefficients representing the estimated portion of each cost
c
element related to execution of the Works, as stated in
d the table of adjustment data. For example b-unskilled
labour, c-cement, d-bitumen.
Ln = current cost indices or reference prices for the period n,
expressed in the relevant currency of payment, each of
En
August 2011
II-3 /31
August 2011
II-3 /32
August 2011
II-3 /33
August 2011
II-3 /34
II-3.12
Interim Payments
The Contract will specify the period within which the Employer is obligated to
pay the Contractor. Contract provisions vary:
o Older standard forms of FIDIC contract prescribe that payment shall be
made within 28 days after an Interim Payment Certificate has been
delivered by the Engineer to the Employer.
o Recent standard forms of FIDIC contract prescribe that payment shall
be made within 56 days after receipt by the Engineer of the Contractors
Application for Interim Payment (i.e. irrespective of the date when the
Engineer issues an Interim Payment Certificate).
o Both older and recent forms of FIDIC contract prescribe that payment
shall be made within 56 days after the Engineers Final Payment
Certificate has been delivered to the Employer.
Other forms of contract may have different provisions. Standard forms of
FIDIC contract may have been superseded by Particular Conditions. Such
Particular Conditions might even include provisions whereby amounts
August 2011
II-3 /35
II-3.13
Delayed Payments
Overview
Making payments to the Contractor in full and on time is the Employers
contractual obligation, in default of which Contract provisions may entitle the
Contractor to interest (called financing charges in recent forms of FIDIC
contract).
Also the Contractor may be entitled to take such actions as:
o In the event that payment is not made by due date, the Contractor may
give prescribed notice to the Employer (copied to the Engineer) of intent to
suspend work or reduce the rate of work, either of which could give the
Contractor valid grounds to claim extension of the Time for Completion
and/or additional costs. [See Section II-4.10 Works Suspensions:
Suspension of Works by Contractor.]
o Where the Contractor suspends work or reduces the rate of work, having
given the prescribed notice, and the Employer subsequently pays the
amount due, including interest (financing charges) to which the Contractor
is entitled, the Contractor shall resume normal working as soon as is
reasonably possible.
o In the event that the Employer fails to pay the Contractor the amount due
under any certificate within the stipulated period after the due date, the
Contractor may give prescribed notice to the Employer (copied to the
Engineer) of termination of his employment under the Contract [see
Section II-8.2 Termination by Contractor arising from Employers
Default]. It is important to note that even if the Employer subsequently
makes payment after the Contractor issues a notice of termination, the
Contractor is still entitled to terminate upon expiration of the notice period.
The Contractor may, however, withdraw his notice of termination in the
event that payment is made before expiration of the notice period. Also,
the Contractor could, at any time prior to expiration of the notice period,
extend the notice period for termination. Failing any action by the
August 2011
II-3 /36
August 2011
II-3 /37
Contracts invariably provide that the Employer shall pay interest on late
payments (i.e. payments made after the payment due date) at the rate
specified in the Appendix to Tender or elsewhere in the Contract. In recent
forms of FIDIC contract, and in contracts for Works in Islamic countries
influenced by the Shariah law (wherein payment of interest may be illegal),
this is called financing charges. In the following discussion interest also
means financing charges.
Most contracts stipulate interest as an entitlement to the Contractor, without
any requirement for formal notice by the Contractor or certification by the
Engineer. Interest charges are damages deemed to have been incurred as a
consequence of the Employers breach of Contract.
In respect of the Engineers certification of interest:
o The Contractor may, under Contract provisions relating to Interim Payment
Statements entitling him to claim any other amounts to which the
Contractor considers himself entitled under the Contract, include interest
in his Statements.
The Engineer should not certify payment of interest unless the Contractor
has claimed interest entitlement in his Interim Payment Statement.
However, this does not negate the Contractors entitlement or the
Employers obligation to pay.
If the Contractor has included interest in an Interim Payment Statement,
the Engineer is obliged to certify such valid and correct interest in his
corresponding Interim Payment Certificate.
Unless payment of interest is illegal or unenforceable under the Law of the
Contract, the Employers failure to pay such interest is a breach of Contract
subject to the same contractual repercussions (interest, slow-down or
suspension of Works, and Contract termination) as apply to late payment or
non-payment of any other amounts due under the Contract. Thus, if the
Contractor has submitted an Interim Payment Statement for or including
interest, in respect of which the Employer has not paid such interest by due
date, then a situation arises whereby the Employer has obligation to pay
interest on unpaid interest!
II-3.14
August 2011
II-3 /38
II-3.15
August 2011
II-3 /39
August 2011
II-3 /40
II-3.16
August 2011
II-3 /41
II-3.17
% Progress =
The Contract Value of Works should exclude any Provisional Sum for
Contingency and Value Added Tax that may have been included in the
Accepted Contract Amount (i.e. the Original Contract Price).
August 2011
II-3 /42
At the beginning of the Contract, before any Variations have been instructed
[see Section II-3.3]:
Contract Value of Works = Accepted Contract Amount (i.e. Original
Contract Price) less any amounts therein of
Provisional Sum for Contingency and Value
Added Tax.
As the Contract progresses, Variations will invariably be instructed and those
Variations incorporated into the BoQ [see Section II-3.3, Section II-3.4, &
Appendix L] as Revised Contract.
Contract Value of Works = BoQ value of Revised Contract, including
Variations incorporated therein.
Thus the Contract Value of Works is a moving target. It is not sufficient to
report progress only in relation to the Value of Works of Original Contract
(called the Accepted Contract Amount in recent forms of FIDIC contract, or
the Contract Price in older forms). It is not a reliable indication of progress to
completion.
It is recommended that the Engineer should report progress of the Works (in
his periodic Progress Reports to the Client/Employer) in 2 ways:
Progress = % of Value of Works of Original Contract
(achieved in X% of the Original Time for Completion)
Progress = % of Estimated Final Value of Works
(achieved in Y% of the Extended Time for Completion)
This data should be presented in the Executive Summary of Project Progress
Reports and the Project Synopsis [see Section I-3.8 Project Reports &
Appendix F].
August 2011
II-3 /43
II-3.18
August 2011
II-3 /44
August 2011
II-3 /45
Check
Comment
August 2001
Guideline
II-3.10
II-3.11
II-3.12
II-3.13
II-3.14
II-3.15
II-3.16
II-3.17
II-3.18
Requirement
Evidence & bank security for Plant/Materials sent to Site?
Same principles of 'Measurement of Works' applied to Material on Site
Contractor's Interim Payment Statements:
Establish with Contractor standard format for IPSs
(same as Engineer will use for IPCs)
Establish with Contractor the Engineer's requirements for support
documents (vouchers, records of agreed measurements, & other)
Advance Payment to be claimed by IPS (supported by copy of Security
& Employer's acceptance of Security)
IPSs consecutively numbered
Details provided of bank accounts to which payments to be made
Interim Payment Certificates:
Check/implement Contract provisions for IPCs:
IPCs not permitted until Performance Security submitted by
Contractor & approved by Employer
Period within which Engineer must prepare & submit
Advance Payment and deductions for repayment
% deduction for Retention & Limit of Retention Money
Partial payment of Retention Money at completion of parts of Works
for which a Taking-Over Certificate is issued
Bank security in lieu of Retention Money
IPCs consecutively numbered (corresponding to Contractor's IPSs)
Cover letter to IPC includes:
Payment due date
Details of Contractor's bank to which payment to be made
Amount to which Advance Payment Security can be reduced
Reasons for correction of Contractor's IPSs
Interim Payments:
Check Contract provisions for:
Period within which Employer must make payment
Request Employer to notify payment date & amount
Delayed Payments:
Check Contract provisions - Contractor's entitlements if payment delayed
If payment notification not within 10 days of due date, prompt Employer
If payment notification not within 7 days of due date, warn Employer
of Contractor entitlements if payment delayed
Records of Statements, Certifications & Payments:
Maintain records of:
Receipt date & amount of Contractor's IPSs
Due date, submission date & amount of Engineer's IPCs
Due date, payment date & amount of Employer's payments
Present records in Engineer's Progress Reports
Estimates of Cost of Works to Completion:
Check Service Contract requirements for submission of Estimates
Maintain Estimate continuously:
Update Estimate after Variation instruction or VO issue
Update Estimate after each IPC
Present latest Estimate in Engineer's Progress Reports
Work Quantities Management:
Perform quantity take-offs from drawings to verify BoQ quantities
Monitor quantity trends during construction
Early warning system to verify final estimated quantity when executed
quantity reaches 80% of BoQ quantity
Prepare VOs to reconcile significant quantity variations
Monitoring & Reporting Works Progress:
% Progress based on "Value of Works" completed
Prepare Progress Charts
Present Progress Charts in Engineer's Progress Reports
Contract Addenda & Amendments:
Establish with Employer (& Funding Institution if necessary) & implement
requirements & procedures for making changes to the Contract
Check
Comment
August 2001
II-4.
ONGOING SUPERVISION
This Chapter provides guidelines for ongoing supervision during execution of
a Works Contract, including:
o Engineers Instructions
o Regular Progress Meetings
o Continuing validity of the Contractors Performance Security,
Advance Payment Security, and Insurance
o Verification of the Contractors Personnel and Equipment
o Sampling & Testing of Materials, Workmanship and Plant
o Works Inspection, Testing and Acceptance
o Unacceptable Works, Defects Notification and Remedies
o Works Programme and Cash Flow Revisions
o Remedies for Contractors Slow Progress
o Works Suspensions
o Documentation, Determination & Evaluation of Claims
o Delays, Extension of Time for Completion and Associated Costs
o Liquidated Damages and Bonus for Early Completion
o Disputes and Dispute Resolution
II-4.1
Engineers Instructions
Without proper agreed procedures and consistency for issuance of
instructions, the effectiveness for monitoring of cost, schedule, progress and
delay will be diminished. Very often, the full effects of all instructions issued
during the execution of Works do not come to light until the final account is on
the table and the Contractor is reconstructing (with hindsight) the history of
events in order to support claims for extension of Time for Completion (to
avoid application of Liquidated Damages) and/or for additional costs. To
adequately assess such claims the Engineer should have records of all
instructions given.
Instructions given by the Engineer, or by his delegated assistants [see
Section II-2.2 Engineers Delegation of Duties & Authorities], to the
Contractor must be in writing. This can be achieved by letter, but it is
recommended that a standard-format Engineers Site Instruction be used,
which should be consecutively numbered, and to which (if appropriate) a
sketch or photograph should be attached. An example is presented in
Appendix J.
Verbal site instructions should be given in emergency only. Where verbal
instruction is given, the Engineer must:
August 2011
II-4 /1
follow up with a written instruction, also recording the date/time when the
verbal instruction was given by/to whom.
II-4.2
August 2011
II-4 /2
II-4.3
August 2011
II-4 /3
assist the Employer in drafting a letter whereby the Employer requires the
Contractor to provide from his surety the required validity extension of the
Performance Security.
August 2011
II-4 /4
II-4.4
August 2011
II-4 /5
II-4.5
August 2011
II-4 /6
The Engineer may instruct the Contractor to perform additional testing or vary
the locations or details of specified tests. But such instruction might constitute
a Variation for which the Contractor could be entitled to additional payment or
even an extension of the Time for Completion if the tests results show
compliance with the Contract.
In the event that test results show non-compliance with the Contract, the cost
of retesting is borne by the Contractor.
All forms of FIDIC contract require that:
the Contractor shall agree, with the Engineer, the time and place for the
specified testing of any Plant, Materials and other parts of the Works; and
the Engineer shall give the Contractor not less than 24 hours notice of his
intention to attend tests.
But, since it is the Contractors responsibility to perform the tests, it is
therefore incumbent upon him to have given prior notice of the tests, and
his readiness therefor, and obtained the Engineers agreement to the
timing and location of the tests.
If an authorized representative of the Engineer does not attend at the time
and place agreed, the Contractor may proceed with the tests, which shall be
deemed as having been performed in the presence of the Engineer.
The Contractor must promptly forward to the Engineer duly certified reports of
the tests. When the specified tests have been passed, the Engineer is
required to endorse the Contractors test certificate, or issue a certificate to
him. If the Engineer has not attended the tests, he shall be deemed to have
accepted the test results as accurate.
The Employer, should he so require, may witness any testing and countersign
test certificates. The beneficiary (if not the Employer) of parts of the Works
(e.g. utility owners in respect of utility relocations) may also require to witness
testing and countersign test certificates.
II-4.6
August 2011
II-4 /7
for Inspection), the Contractors agreement should have been obtained to the
standard forms to be used.
Where adopted standard forms for inspections provide for multiple and
sequential activities (for example: formwork & rebar fixing concrete
placement), a work item (concrete placement) must not be permitted to
commence before the preceding work items (formwork & rebar fixing) have
been inspected and accepted by the Engineer, as recorded on the inspection
forms. Similarly, paving of an asphalt wearing course is not permitted before
the underlying asphalt binder course has been inspected, tested and
accepted, and a tack coat acceptably applied.
All FIDIC forms of contract require the Contractor to give notice to the
Engineer whenever any part of the Works is ready, or about to be ready, and
before it is covered up or put out of sight; in order to afford the Engineer full
opportunity to examine, inspect, test and measure the work before it is
covered up.
The Engineer must perform such examination, inspection, testing and
measurement without unreasonable delay (or promptly give notice to the
Contractor that the Engineer does not require to do so).
Consequently the notice to be given by the Contractor must also be
reasonable according to the circumstances. Obviously the pressure testing of
a water main (prior to backfilling its trench) would require more time than, say,
simply inspecting a drainage pipe. In order to obviate claims for delay:
The Engineer and Contractor should, during the course of the Works
execution, pre-agree what will constitute adequate notice and response
time of the Engineer for the different types of work.
The above requirements apply also to the Contractors off-Site manufacture of
Plant, production of Materials, or fabrication of components of the Works. If
the Engineer does not provide full-time supervision at such off-Site locations,
then the Engineer and Contractor should pre-agree what will constitute
adequate notices of the Contractor and response times of the Engineer at
such locations, for the purposes of inspection and testing of works in progress
and before packaging and transportation to Site.
In the event that the Contractor covers up work without giving notice (or
without adequate notice for the purpose of inspection, testing and
measurement):
the Engineer is entitled to require the Contractor to uncover work to
facilitate inspection, testing and measurement, and thereafter to reinstate
and make good at the Contractors expense.
The Engineer may at any time require the Contractor to uncover any part of
the Works or make openings in or through the same. However, if the
The Louis Berger Group, Inc.
August 2011
II-4 /8
Contractor did comply with the Contract requirement to give adequate notice
before covering up, and if the uncovered work is found to have been executed
in accordance with the Contract, then the Contractor is entitled to his costs of
uncovering, making openings, reinstating and making good. If the uncovered
work is found not to be in accordance with Contract requirements, then the
Engineer shall issue a Defects Notice [see Section II-4.7 Unacceptable
Works, Defects Notification & Remedies] and instruct the Contractor to bring
the works within compliance at his own expense.
It is essential that the various assistants of the Engineer (Resident Engineer
and/or inspectors, surveyors, laboratory or other technicians) are authorized
in writing (copied to the Contractor) as having the delegated duties and
authorities to perform the inspections and/or testing and to accept such
inspected/tested works on behalf of the Engineer. [See Section II-2.2
Engineers Delegation of Duties & Authorities.]
II-4.7
August 2011
II-4 /9
The use of a standard form for Defects Notices will facilitate the Engineers
record-keeping during the construction period when compiling works to be
executed before and after the Works are deemed substantially completed and
formally handed over to the Employer, and during the Defects Notification
Period. Contract provisions typically provide that the Contract cannot be
concluded until all contractual obligations have been fulfilled, including the
correction of any and all defects.
Acceptance of Non-complying Works with Payment Deductions
Some contracts provide that works with minor defects can be accepted at
reduced payment rates or with payment deductions; formulae are sometimes
included in contracts to derive such reductions or deductions. In contracts
without such provision, there is still the possibility of acceptance with
negotiated payment deductions; but only if the Employer and Contractor
agree, which agreement must be in writing signed by both Parties. The
Engineer has no unilateral powers of discretion under the Contract in this
regard, although he could recommend such solution to the Parties. For
example, in road construction the Engineer might recommend that
acceptance, with payment deductions, of asphalt concrete wearing course
with some minor thickness deficiencies (that do not affect the integrity and life
of the road structure) is preferable to instructing the removal and replacement
of defective areas that would result in a patchwork quilt with poorer rideability. However, in the absence of Contract provisions therefor, acceptance
of defective works with price deductions should be resisted particularly early
in the Contract when emphasis should be upon the Contractors
establishment of effective quality control and quality assurance to prevent
defective works.
Remedies
The Contractor is required to comply with an instruction to correct defective
works within a reasonable time, which should be the time stated (if any) in the
instruction, or immediately if urgency is required.
The Louis Berger Group, Inc.
August 2011
II-4 /10
All forms of FIDIC contract provide that the Contractor is in default if he fails
to carry out the instruction within the time specified (or, if none, within a
reasonable time), and the Employer shall be entitled to employ and pay other
persons to perform the corrective actions or works. In such eventuality the
Contractor is entitled to payment for the works (per Contract provisions) but
the Employer is entitled to recover from the Contractor the Employers costs,
as verified by the Engineer in consultation with the Employer and Contractor,
of the remedial actions/works performed by others. A dispute could arise, in
such circumstance, from the lack of definition of reasonable time or if
urgency was necessitated. A dispute avoidance strategy would be to advise
the Employer not to take such action without first warning the Contractor in
writing (either directly or through the Engineer) that such action will be
implemented unless the Contractor fulfils his contractual obligations with due
diligence.
All forms of FIDIC contract also provide that the Employer is entitled to
terminate the Contract [see Section II-8.1 Termination by Employer arising
from Contractors Default] if the Contractor is in contractual default by failing
within 28 days to comply with a notice of rejection issued by the Engineer and
instructing remedial work. It is recommended, however, that the Engineer
should formally advise the Employer (if necessary) only to take such
precipitous action if the Contractor has, despite several written warnings,
been in continuous flagrant breach of Contract that demonstratively and
adversely affects the Employers or publics use of the works or safety.
II-4.8
August 2011
II-4 /11
August 2011
II-4 /12
II-4.9
August 2011
II-4 /13
There are slight differences between older and recent forms of FIDIC
contract, as described below. Where Time for Completion is mentioned, it
means including any Time extensions that have been awarded to the
Contractor.
Older forms of FIDIC contract provide that if, for any reason that does not
entitle the Contractor to a Time extension, the rate of progress of the Works is
at any time, in the Engineers opinion, too slow to complete the Works within
the Time for Completion:
the Engineer shall notify the Contractor who shall thereupon take such
steps as are necessary, subject to the consent of the Engineer, to
expedite progress so as to comply with the Time for Completion.
The Contractor shall not be entitled to any additional payment for taking
such steps (which, subject to the consent of the Engineer, may include
longer working hours, additional working shifts and/or working at night or
on locally recognized days of rest). If the steps taken by the Contractor
involve the Employer in additional supervision costs, such costs shall be
determined by the Engineer (after due consultation with the Parties) and
shall be recoverable from the Contractor by the Employer, and may be
deducted by the Employer from any monies due or to become due to the
Contractor, and the Engineer shall notify the Contractor accordingly.
Note, in respect of older forms of FIDIC contract, that:
The Engineer is required only to notify the Contractor of too-slow progress
in order to obligate the Contractor to expedite the Works.
Insofar as the Contractor is so obligated, the Engineers notice is
tantamount to an instruction. It is recommended that the Engineer make
clear in his notice that the Contractor is instructed to take such steps as
necessary to comply with the Time for Completion.
The Engineer is not required to request or the Contractor to submit a
revised Programme of Works. However, the Engineer should so request,
as he is entitled to do [see Section II-4.8 Works Programme & Cash Flow
Revisions], whereby the Contractor would be obligated to respond.
The steps to be taken by the Contractor are subject to the consent of the
Engineer.
The Engineer should make it clear in his notice that he requires the
Contractor to submit (together with the revised Programme), for the
Engineers consent, the Contractors written proposals of how he intends
to expedite the Works progress (which might not be clear from, say, a barchart revised Programme).
August 2011
II-4 /14
August 2011
II-4 /15
August 2011
II-4 /16
August 2011
II-4 /17
The use of payment deductions (from the Contractor) in order for the
Employer to pay the Engineer, may be conveniently implemented if the
financing sources for the Works Contract and LBGs Service Contract are the
same, except that pre-approval of the funding institutions would be required,
and an addendum may be required to the Service Contract.
Due to accounting mechanisms however, the Employer might not easily be
able to use payment deductions from the Contractor under one funding
source to pay the Engineer under a different funding source. A solution, if
acceptable, could be that:
- the Engineer submits invoices directly to the Employer (copied to
Contractor) for the additional supervision costs;
- the Employer submits invoices directly to the Contractor for the
additional supervision costs (per Engineers invoice to the Employer);
- on receipt of payment from the Contractor, the Employer promptly pays
the Engineer.
Again, however, either an addendum to LBGs Service Contract may be
required or even an additional Service Contract.
Under no circumstance should payment be made by the Contractor directly to
the Engineers staff; this would create a conflict of interest for the staff.
Payment should not be made directly by the Contractor to LBG a separate
contract would be required (since LBG is not a Party to the Works Contract)
but this would also create a conflict of interest. Payment of additional
supervision costs must be made directly by the Contractor to the Employer
under the Works Contract so that the force of the Works Contract can be
invoked in the event of non-compliance; and thereafter payment made by the
Employer to LBG, either under LBGs Service Contract or a separate contract.
In the case of occasional overtime working by the Contractor, an adequate
level of supervision may be possible by the Engineers staff working overtime
and/or in work shifts. However, it is recommended that the Engineers staff
not be requested (nor permitted) to work excessive overtime hours that could
cause lack of effectiveness (through tiredness) or potential burn-out. If the
Contractor proposes continuously to work excessively more than regular
hours, then it is recommended that an adequate supervision be achieved by a
combination of additional supervision staff mobilization and shift-working.
In any case of overtime working, the requirements of local Law should be
ascertained and adhered to both in respect of overtime premiums payable
and any rules for compensatory time-off.
A problem could arise if the Employer will not approve (and therefore not pay
for) overtime premiums and/or additional staff to provide an adequate level of
supervision; yet at the same time would object to (or not allow) limiting the
The Louis Berger Group, Inc.
August 2011
II-4 /18
II-4.10
Works Suspensions
Suspension of Works by the Engineer
Most contracts, including standard forms of FIDIC contract, provide that the
Engineer may at any time instruct the Contractor to suspend progress of part
or all of the Works and, during the suspension, to protect, store and secure
the suspended Works against any deterioration, loss or damage.
Curiously, FIDIC forms of contract do not require the Engineer to state, in his
instruction, the reason for or possible time extent of the suspension. However,
clearly it would be reasonable for the Engineer to do so; so that the
Contractor can decide how best to meet his obligation to protect, store and
secure the suspended Works.
FIDIC forms of contract give no guidance as to the circumstances under
which the Engineer can or should instruct a suspension of Works. Therefore,
unless the Contract limits the Engineers authority (for example, requiring the
Engineer to obtain prior approval of the Employer), the exercising of this
power is at the discretion of the Engineer. This is an onerous responsibility.
Insofar as suspensions may entitle the Contractor to additional costs and/or
extension of the Time for Completion (EoT), the Engineer should exercise this
power only when absolutely necessary and, except in emergency, preferably
with the Employers concurrence. Furthermore, the Engineers Delegation of
Authority [see Section II-2.2], for instructing suspensions should be limited to
the Engineers senior representative on the project.
Circumstances under which the Contractor could be entitled to additional
costs and/or EoT arising from the Engineers instruction of a Works
suspension, would include:
o Events prescribed in the Contract as constituting Force Majeure, such as:
- War, hostilities, invasion or act of foreign enemies;
- Rebellion, terrorism, revolution, insurrection, military or usurped power,
or civil war, within the country;
- Riot, commotion or disorder within the country (other than by
employees of the Contractor, his subcontractors or suppliers);
August 2011
II-4 /19
August 2011
II-4 /20
August 2011
II-4 /21
II-4.11
Claims
Contractors Claims
All contracts invariably prescribe procedures for submitting claims. Both older
and recent forms of FIDIC contract prescribe that:
o The Contractor shall give notice to the Engineer of his intention to submit
a claim within *28 days after the event or circumstance giving rise to the
claim has first arisen.
August 2011
II-4 /22
August 2011
II-4 /23
August 2011
II-4 /24
August 2011
II-4 /25
II-4.12
August 2011
II-4 /26
August 2011
II-4 /27
August 2011
II-4 /28
and the Contractor accepts), respond to the claim. The Engineer may
request further particulars, but shall nevertheless give response on the
principles of the claim within such time.
In respect of the Employers claims, no time limit is stipulated for the
Engineers response. However it would be a reasonable expectation for
the Engineer to respond within the same 42-day period as is applicable to
the Contractors claims.
Each Payment Certificate shall include such amounts for any claim as
have been reasonably substantiated. Unless and until the particulars
supplied are sufficient to substantiate the whole of a claim, the Contractor
shall be entitled to payment for such part of the claim as he has been able
to substantiate.
o Each party shall give effect to each agreement or determination unless
and until it is revised in the process of Dispute Resolution [see Section
II-4.15 Disputes & Dispute Resolution].
Principle & Quantum
The Engineers determination of a claim will be based on the particulars
submitted, but not necessarily confined thereto. Since the Engineer is
required to pay due regard to all relevant circumstances, he should take into
consideration events or circumstances of which he is aware and that are
known at large.
The particulars of claim must include:
- A description of the event or circumstance giving rise to the claim.
- The contractual basis for the claim, which should reference the specific
clauses of the Contract under which entitlement is claimed; hereinafter
called the Principle of claim.
- A detailed substantiation with, as necessary or appropriate, supporting
documentation of the amounts (of time extension or payment) that are
claimed; hereinafter called the Quantum of claim.
The Engineer might be wasting his time by focusing on the Quantum of a
claim before considering the contractual eligibility of the Principle of the claim.
If the Principle is ineligible, the Quantum need not be considered.
So, first the Engineer should:
determine if the Principle of claim is eligible. If, after due consultation with
the Parties, the Engineer considers it is not, then he should notify the
claiming party, copied to the other Party, accordingly.
If, after due consultation with the Parties, the Engineer considers the Principle
of claim is eligible (in whole or in part), then he may notify the claiming party,
copied to the other Party, accordingly. The Engineer might consider doing
The Louis Berger Group, Inc.
August 2011
II-4 /29
this, before assessing the Quantum of claim, in the event that he is running
out of any time prescribed for responding to a claim, and/or if he requires the
submission of more particulars to substantiate the Quantum.
Having established the contractual eligibility of the Principle of claim, only
then should the Engineer assess the Quantum of the claim. His assessment
should establish how much of the Quantum, if any, is justified by the
submitted particulars as are verifiable by contemporary records, and request
further particulars for any remaining part. In this respect it must be
remembered that the Engineer had opportunity, after notice of claim had been
submitted, to inspect contemporary records kept by the Contractor. Therefore
the Engineer cannot later argue that the contemporary records later submitted
(unless they are different from or supplementary to the records he was given
to inspect) are no longer verifiable.
Subject to any contractual requirement for the Employers approval, the
Engineer will render his determination of the claim. This determination must
be in writing, reasoned and with detailed comments. In the event that either
Party disputes the determination [see Section II-4.15 Disputes & Dispute
Resolution], a well-presented and well-reasoned determination is less likely
to be overturned in the next prescribed level of dispute resolution. The
determination should be structured to present/contain:
A description of the event and/or circumstance giving rise to the claim.
A summary of the Contractors (or Employers, as appropriate)
submissions of notice and particulars of claim in compliance (or not) with
Contract requirements.
A summary of correspondence (and minutes) pertaining to the claim.
A summary of the basis and amount of claim.
A summary of the Engineers consultation with the Parties prior to
rendering the determination, the effects of those consultations on the
determination, and/or agreements upon which the determination is based.
The Engineers determination of the contractual eligibility of the Principle of
claim, with reference to appropriate clauses of the Contract.
The Engineers determination of the Contractors (or Employers, as
appropriate) entitlement arising from the claim.
In appendix: copy of the claim and other significant correspondence and
records.
Due Consultation
In assessing a Contractors claim, FIDIC forms of contract require the
Engineer to consult with both the Contractor and the Employer, before
rendering a determination. However, under any other form of contract, it is
August 2011
II-4 /30
August 2011
II-4 /31
II-4.13
August 2011
II-4 /32
other default), the Contract still remains in force together with all obligations of
the Parties under the Contract. The Contractor remains obligated to complete
the Works, unless and until the Employer exercises prescribed contractual
entitlement to terminate the Contract [see Section II-8.1 Termination by
Employer arising from Contractors Default]; and the Employer remains
obligated to pay the Contractor for works executed.
In the event of delays occurring outside the Contractors control, the Contract
will provide that the Contractor is entitled to extensions of the Time for
Completion (EoT). Then:
It is the Engineers obligation, subject to the Contractors compliance with
prescribed claim procedures, to determine the amount of such extensions
to which the Contractor is entitled under the terms of the Contract.
EoT for the whole of the Works (or of milestones for completion of Sections of
the Works) automatically extends the date(s) after which the Employer would
be entitled to apply Liquidated Damages.
Care must be exercised when assessing and awarding EoT (including interim
EoT) once awarded, it cannot be subsequently diminished or withdrawn.
Grounds for Extension of Time
The Contractor will be entitled to extension of the Time for Completion (EoT)
to compensate for delays arising from:
- events described under the Contract as risks to be borne by the Employer;
- events of force majeure;
- the Employers failure to comply with his obligations under the Contract;
- neutral events such as exceptionally adverse climatic conditions.
Common grounds for EoT typically include:
o Instructed Variations to the Works (except as resulting from a default of
the Contractor).
o Additional quantities of Works.
o Delayed issuing of Drawings (except works for which the Contractor has
design responsibility).
o Delayed access to or possession of Site.
o Exceptionally adverse climatic conditions on Site.
o Adverse physical obstructions or physical conditions (other than climatic
conditions), which were unforeseeable by an experienced Contractor.
o Delay due to suspensions of the Works instructed by the Engineer (other
than provided for in the Contract or attributable to the Contractors
default).
August 2011
II-4 /33
o Delay due to suspensions of the Works by the Contractor (or his reduction
of the rate of works execution) in consequence of the Employers payment
default.
o Delays arising from discovery, protection or removal on Site of fossils,
articles of value or antiquity, structures and other remains of
archaeological interest.
o The Engineers instruction of tests, not provided for in the Contract, of
Materials, Plant and works.
o Unforeseeable shortages in the availability of personnel, materials plant or
temporary works caused by epidemic or governmental action.
o Delays or disruptions due to events or circumstances constituting Force
Majeure [see Section II-4.10 Works Suspensions].
o Delay, impediment or prevention caused by or attributable to the Employer
or the Engineer.
o Delays at ports of entry to the country, or delays not attributable to the
Contractor of customs clearance of Plant, Equipment, Materials or
supplies.
o Delays not attributable to the Contractor of processing visas and work
permits.
o Or as the Parties shall mutually agree.
Procedures for Extension of Time Claims
Under the provisions of most contracts, the Contractor is required to submit a
formal claim for an extension of the Time for Completion (EoT) of the Works
or for any Section or part thereof, failing which the Engineer (depending on
the terms of the Contract) either is not bound to make a determination of EoT
or cannot do so. [See Section II-4.11 Claims: Contractors Claims & Section
II-4.12 Documentation, Determination & Evaluation of Claims]
To establish entitlement to EoT, the mere citation of events and
circumstances causing delay or disruption to the Contractors work is
insufficient; the Contractor must demonstrate that the delays prevented
completion of the Works, with the resources stated in his Tender, within the
Time for Completion. This requires the Contractor to have mitigated delay or
disruption to the extent that was practicable and within his control, such as by
changing his planned sequencing of the Works (for which he may be entitled
to additional costs incurred by such mitigation).
EoT is determined by the Engineer from his assessment of particulars of
claim submitted by the Contractor, and from contemporary records. However,
Particular Conditions sometimes prescribe that the Engineer cannot award
EoT to the Contractor without the prior specific (i.e. written) approval of the
Employer.
The Louis Berger Group, Inc.
August 2011
II-4 /34
August 2011
II-4 /35
the event alleged to have caused delay, then less likely will be the Engineers
ability to verify the Contractors particulars and assess entitlement to EoT.
It must be particularly noted that recent forms of FIDIC contract
(whereunder the Engineer is part of the Employers Personnel) require that
the Engineer shall not determine any EoT (or costs associated therewith)
unless the Contractor has complied with the prescribed requirements for
submitting notice and particulars of claim. The Engineer cannot independently
exercise any discretion [see Section II-4.11 Claims: Contractors Claims for
discussion regarding time-barring claims for which notice of claim was not
given within prescribed time limitations]. Only if the Employer is sympathetic
to the Contractors non-complying claim and instructs the Engineer in writing
to make a determination, may the Engineer do so.
In assessing a Contractors claim for EoT, FIDIC forms of contract require
the Engineer to consult with both the Contractor and the Employer before
rendering a determination. However, under any other from of contract, it is
strongly recommended that the Engineer perform such consultation.
Consultation should be documented in written minutes, distributed to both
Parties, as a back-up and future reference to the eventual determination.
Recent forms of FIDIC contract state that the purpose of this consultation is
to attempt to obtain agreement of the Parties. Even if the purpose of obtaining
agreement is not so stated in the Contract, it is strongly recommended that
this should be a priority of the Engineers consultation. To avoid a later
dispute of his determination, the Engineer should always try to arrive at a
determination agreeable to both Parties, even if such determination would not
otherwise have been his own. However, if such agreement is obtained, the
Engineers determination must state, and provide records of, the agreement
signed by the Parties. In the event that an agreement is not obtained during
the process of consultation, then the Engineer must make a determination
that he considers fair and reasonable pursuant to the Contract, under which
circumstance records of the prior consultations should be retained in case
such determination is later disputed.
In the case that the Engineer experiences difficulties getting the Parties to
initiate the process of consultation, or to foreshorten the process when time is
of essence, the Engineer should, on the basis of his review of the
Contractors particulars, render (in writing) his assessment of the EoT claim
to both Parties and request (within a stated, reasonable period) their
respective agreement to or comments on such assessment; advising that this
procedure is intended as the process of due consultation. Depending on the
nature of the responses (or lack thereof), the Engineer can then convert his
assessment into a determination.
If the Conditions of Contract require that the Engineer must obtain the
Employers approval before rendering a determination of EoT, then the
The Louis Berger Group, Inc.
August 2011
II-4 /36
August 2011
II-4 /37
The costs to which the Contractor would be fairly entitled will be contingent on
the cause of delay giving rise to EoT entitlement. Types of cost may be
categorized as follows:
o Costs of standby of the Contractors Site resources affected by the delay
at the time of the delay. These are referred to herein as Direct Costs.
o Costs of prolongation, during the EoT period, of the Contractors Site
Overheads and Head Office Overheads. These are referred to herein as
Prolongation Costs.
o Costs of extended provision during the EoT period of General Items of the
Bill of Quantities (e.g. performance bond, insurances, provision &
maintenance of facilities for the Engineer) that are not included in the
Contractors overheads. These are referred to herein as Preliminary
Costs.
Responsibility for Delay affects Entitlement to Costs
When assessing a claim for extension of the Time for Completion (EoT), it is
vital to determine responsibility for the delay in respect of which the
Contractor is claiming EoT entitlement. This responsibility will determine the
Contractors entitlement to EoT, and also to types of permitted costs.
In general, cause of delay will fall into one of four categories:
a) Solely attributable to the Contractor with no fault attributable to the
Employer.
In this case the Contractor has no entitlement to EoT or to any costs.
b) Solely attributable to the Employer with no fault attributable to the
Contractor.
In this case the Contractor is entitled to EoT and to costs.
c) Concurrently attributable to the Contractor and the Employer i.e.
delays attributable to the Employer overlapping with delays attributable to
the Contractor.
In such case the Contractor is entitled to EoT, but his entitlement to costs
would be limited.
d) Exceptionally adverse climatic conditions (sometimes referred to as
Neutral Delay).
In this case the Contractor is entitled to EoT but not to any costs.
In case of a single claim arising from several events, the Engineers
determination should differentiate what parts of the total EoT entitlement are
within categories (b), (c) and (d). Such differentiation will assist the
assessment of costs to which the Contractor may be fairly entitled.
August 2011
II-4 /38
August 2011
II-4 /39
operations but are not statistically abnormal at the Site. [For more
discussion see Section II-2.16 Meteorological Records.]
Common Examples of Contractors Delay:
- Contractors delay in providing a Performance Security [see Section II2.6.]
- Contractors delay in providing Insurance [see Section II-2.8.]
- Failure to mobilize sufficient construction resources (as proposed in his
Tender and/or Programme of Works) to perform programmed works.
- Delay arising from his own failure to meet his programmed objectives.
Common Examples of Employers Delay:
- Employers delay in providing Possession of Site [see Section II-2.13]
- Employers delay in providing Drawings [see Section II-2.15.]
- Suspension of the Works, or parts thereof [see Section II-4.10.]
- Instructed Variations of the Works [see Section II-3.3 Variations]
affecting the critical path of the Contractors programme to complete the
Works on time (if the Variations did not result from the Contractors
default). Such cases would include additional works (additional to the
scope of Works tendered) and/or increased quantities of the tendered
scope of Works.
- Late instruction of works to be performed under Provisional Sums [see
Section II-3.2] included in the Contract. That is, instructions given so late
that they affected the Contractors ability to complete such works within
the Time for Completion.
Common Example of Concurrent Delay:
- Employers delay in providing possession of Site and/or working drawings,
overlapping with the Contractors delay in mobilizing to perform the
delayed works.
An Example of Differentiating between Causes of Delay:
Assume that:
- The Contractor had programmed to perform earthworks and paving works
but was prevented from so doing because possession of Site was
unavailable.
- The Contractor had completed his site office installations and obligations
to provide a Performance Security and Insurance.
- The Contractor was partially mobilized to perform some of the
programmed earthworks.
- The Contractor had also mobilized some asphalt equipment. However, in
his Tender the Contractor had proposed to install his own asphalt plant
August 2011
II-4 /40
but, during the delay period, had not done so and had made no alternative
commitment for asphalt supply.
During the delay period, no conditions occurred that would have prevented
earthworks. However, temperatures were below +5oC (the limit below
which paving operations would not have been permitted) for 3 days more
than the maximum 1-in-10 year occurrence (based on historical
meteorological records for the Site) for the delay period.
August 2011
II-4 /41
Prolongation Costs
Prolongation Costs are variously addressed in books on the subject of EoT as to whether they relate to the Contractors costs during the period of delay
or to his costs during the period of awarded extension of the Time for
Completion (EoT).
Prolongation Costs, as defined herein, are the Contractors Site Overhead
and Head Office Overhead costs during the period of EoT; to which the
Contractor would be entitled during that portion of the awarded EoT
determined as attributable to sole Employer delay (i.e. separate from the
Contractors concurrent delay).
Generally, Prolongation Costs should be limited to the lesser costs of the
actual resources provided by the Contractor or of those included in his
Tender.
The Contractors Tender provisions for % Site Overheads, % Head Office
Overheads, and % for Risk & Profit might be known either from:
o the Contractors Tender (if required to be stated by the Employers
Instructions to Tenderers) or
o the Contractors submission of Breakdowns of Lump Sums and Unit
Prices submitted (if required) at the beginning of the Contract [see
Section II-2.9.]
Thus, Prolongation Costs of Site and Head Office Overheads (if known as
aforesaid) could be computed as:
(% Site O/H + % H.O.O/H)
100
(Orig.Contract Sum)
(Orig.Time for Completion)
Where:
Site O/H = Site Overhead cost as % of direct cost of performing work.
H.O.O/H = Head Office overhead cost as % of direct cost of performing work.
Orig.Contract Sum = Accepted Contract Amount less Provisional Sums, Dayworks
and Contingencies.
[Accepted Contract Amount being the recent FIDIC definition
of the Contractors tendered amount (corrected as necessary)
accepted in the Employers Letter of Acceptance of the
Contractors tender. In older forms of FIDIC contract this was
call the Contract Price.]
Orig.Time for Completion = Original Time for Completion before time extensions.
August 2011
II-4 /42
All the above formulae have found favour, depending on the circumstances,
and been accepted by law courts in litigation disputes.
Loss of Profit
The principles of a claim by the Contractor for loss of profit, arising from an
extension of the Time for Completion (EoT), are similar to those applicable to
a claim for Overheads, and could be assessed based on the above-described
formulae but with % Profit replacing % Overhead.
However, before considering such claim the Engineer should check that:
there are no Contract provisions limiting the Contractors entitlement to
recovery of costs only, which would exclude alleged loss of profit;
there are no restrictions under the Law of the Contract to the Contractors
entitlement to recover lost profit.
August 2011
II-4 /43
X
Y
X-Y
August 2011
II-4 /44
The elements of Prolongation Costs included in (1) (for Site Overhead, Head
Office Overhead & Profit, and the percentages from which they are derived) must
identically be used in (2).
For more detailed discussion of such formula and its application see Section
II-2.18 Price Adjustment Formula & Indices and Section II-3.11 Interim
Payment Certificates: Price Adjustments.
As explained under Section II-2.18, the multiplier of such formula would be
capped at its value applicable when the Time for Completion (as may have
been extended) expires.
However, under a contract that does not include such Price Adjustment
provision for the rise and fall of the costs of labour and specified materials
(either by omission or, in FIDIC-based contracts the deletion by Particular
Conditions of the price adjustment provisions of the General Conditions), it is
not uncommon for the Contractor to claim entitlement to introduce such price
adjustment provision during the period of granted extension of the Time for
Completion - to commence upon expiry of the original Time for Completion.
The Contractors claim might be predicated upon:
- the fact that he had committed to execute the Works at his tendered rates
and prices (without price adjustment) only during the original Time for
Completion (and had made allowances in his tendered prices
accordingly).
- the Time for Completion was extended for reasons of delay attributed the
Employer, which the Contractor could not have anticipated when
preparing his Tender.
- he is at risk only for the rise and fall of prices during the original Time for
Completion.
August 2011
II-4 /45
and therefore he should be entitled to claim compensation for the rise and
fall of prices during extensions of the Time for Completion, by
establishment of a price adjustment formula to be applied after expiry of
the original Time for Completion.
II-4.14
Contract Cl.
reference
August 2011
Contract Cl.
reference
.% of *Contract Price.
August 2011
II-4 /47
August 2011
II-4 /48
August 2011
II-4 /49
II-4.15
August 2011
II-4 /50
August 2011
II-4 /51
which the decision was received (or by which it should have been
received), give notice to the other Party of his dissatisfaction. After giving
such notice of dissatisfaction either Party may, subject to requirements to
attempt amicable settlement, commence arbitration.
Neither Party is entitled to commence arbitration of a dispute unless he
has first given such notice of dissatisfaction within the prescribed time.
If no notice to commence arbitration was given within 28 days of receipt of
the DABs Decision (which therefore became binding) but one Party fails
to comply with the DABs Decision, the other Party may, without notice to
the other Party afterward refer the failure to arbitration.
The above provisions are summarised from standard forms of FIDIC contract,
but these may have been modified by the Contracts Particular Conditions.
For example, sometimes older forms of FIDIC-based contracts are modified
by replacement of the Engineers Decision with appointment of a DAB and
provision for a DABs Decision.
It should be emphasized that a matter cannot be referred to the Engineers or
DABs Decision (as appropriate to the Contract), unless it is a matter formally
in dispute.
Engineers Decision
Older forms of FIDIC contract provide that either Party may request an
Engineers Decision on any dispute of any kind that arises between the
Employer and the Contractor in connection with the Contract or the execution
of the Works (whether during the execution of the Works or after their
completion), including any dispute as to any opinion, instruction,
determination, certificate or evaluation of the Engineer.
In older forms of FIDIC contract, the Engineer is typically represented on
Site by the Engineers Representative [see Section II-2.2 Engineers
Delegation of Duties & Authorities]. The Engineers Representative, during
the course of the Contract, makes many determinations (including
instructions, certifications and valuations), any of which can be disputed by
the Contractor or Employer by requesting an Engineers Decision. In essence,
if the Contractor or Employer is dissatisfied with a determination of the
Engineers Representative, the request for an Engineers Decision is an
appeal to the Engineer to reconsider that determination before arbitration can
be commenced. It is for this reason that authority for rendering an Engineers
Decision should be retained by the person acting for the Engineer, and not
delegated to the Engineers Representative [see Section II-2.2].
Older forms of FIDIC contract do not prescribe that the Engineers Decision
shall be reasoned but it should be. If the Contractor or Employer disputes
August 2011
II-4 /52
August 2011
II-4 /53
August 2011
II-4 /54
Amicable Settlement
It is obviously desirable for the Employer and Contractor to resolve disputes
amicably without recourse to potentially expensive and time-consuming
arbitration. Unfortunately it often happens that the Parties have become so
entrenched that initiation of a process of amicable settlement is avoided for
fear that it might be perceived as a sign of weakness.
Although the Engineer may have no prescribed duties in regard to the
process of amicable settlement, it is recommended (and Funding Institutions
might expect) that the Engineer attempt to initiate and facilitate the process. It
is recommended that the Engineer:
Request the disputing Party to prepare a written summary of its dispute
and supporting argument, and request the other Party to provide a written
rejoinder. [They would have to do this in any case if the dispute were to
proceed to arbitration.] This will help focus the issue.
Convene a meeting to attempt to initiate an amicable settlement process.
Explain the process, rules and potential costs of arbitration.
Offer to act as a facilitator and/or mediator to an ongoing amicable
settlement process; although this might not be acceptable to the Party
disputing an Engineers Decision. Otherwise recommend that the Parties
engage the services of an independent mediator.
In the event that amicable settlement is unsuccessful, the Engineer should at
least have records to demonstrate that he had attempted to facilitate the
process.
If a settlement is successfully reached, the Engineer cannot certify payments
relating thereto under the Contract unless a written Settlement Agreement is
prepared and signed by authorized representatives of the Employer and
Contractor. The Settlement Agreement must state:
A full description of the matter of dispute;
The Settlement Agreement, clearly stating the agreed actions and
obligations of the Parties thereunder;
Any extension granted to the Time for Completion;
The amounts and details of any payments to be made in full settlement of
the dispute from one Party to the other, and the terms of payment (in
accordance with the Contract or otherwise).
The Engineer may offer to draft the Settlement Agreement, but, if he does
not, he should check that the Agreement is sufficiently clear and
comprehensive that he is able to administer the Contract in accordance with
August 2011
II-4 /55
its terms. If the Agreement is not clear, the Engineer should refer back to the
Parties for their written and joint clarification.
In the event that the Settlement Agreement involves payments from the
Employer to the Contractor intended to be paid from funds provided by an
external Funding Institution, it may be necessary that the Agreement be
submitted to the Funding Institution for prior approval and endorsement
signature before it can become effective.
In the event that the Contract is funded by an external Funding Institution, but
payments to be made from the Employer to the Contractor under the
Settlement Agreement are ineligible under the governing Funding Agreement,
then it will be necessary that the Settlement Agreement states the source of
funding for such payments. For example, the payments may be made by the
Employer from his internal financial resources. This consideration will affect
the Engineers form of certification of such payments.
Arbitration
If an arbitration clause is included in the Contract, it should prescribe:
o the court or forum of arbitration to which, and under whose rules, disputes
shall be referred and decided;
o the language of the arbitral proceedings;
o the number of arbitrators;
o the place of arbitration; and
o the law applicable to the arbitration.
Some contracts prescribe that arbitration shall be under the jurisdiction and
rules of the arbitration institute of the country in which the Works are
performed if the Employer and Contractor are both national entities of that
country; but that if the Contractor is foreign to that country, the arbitration
shall take place under the jurisdiction and rules of an international court of
arbitration.
All standard forms of FIDIC contract prescribe that disputes shall be finally
settled under the Rules of Conciliation and Arbitration of the International
Chamber of Commerce (ICC), which is based in Paris, France. The
following guidelines are related to the ICC Rules.
It is strongly recommended that the Project Manager become familiar with the
ICC rules, in order for the Engineer to be able to advise the Employer of the
process and costs of arbitration. ICC Rules of Arbitration are available from:
ICC Publishing
International Chamber of Commerce
August 2011
II-4 /56
August 2011
II-4 /57
The Parties are free to choose the arbitrators. The Parties may decide that
one or three arbitrators shall deal with their dispute. If there is to be one
arbitrator, and the Parties do not agree upon a person, the Court will make
the decision (appointing a person who is not a national of either of the Parties
countries). If there are to be three arbitrators (constituting an arbitral tribunal),
normally each Party will nominate one, and the third arbitrator (who will act as
chairman) is designated by the Court unless the Parties agree upon such
person or ask the co-arbitrators to do so. If the Contract does not stipulate
and/or the Parties have not agreed on the number of arbitrators, the Court will
appoint a sole arbitrator unless the amount in dispute or the complexity of the
case justifies appointment of three arbitrators.
After receipt of the Request (and Answer, if submitted by the defendant) from
the Secretariat, the Court fixes an Advance on costs, based on its estimate of
the arbitrators fees and expenses together with the ICCs administrative
costs in accordance with a Schedule of Costs based on the amount in
dispute. The amount in dispute is calculated on the basis of the total of the
principal claims and counterclaims submitted. The amount of the advance is
provisional and may always be adjusted before the end of the proceedings.
Each Party is required to pay 25% of the Advance to the Secretariat before
the file is transmitted to the arbitral tribunal. If one Party fails to pay the first
25% instalment of the Advance, the other Party (in order that arbitration
procedures may proceed) must pay in full the share due from the Party in
default.
Before commencing the arbitration procedures, the arbitrators first task is to
draw up a document entitled Terms of Reference that describe the Parties
claims to which he will confine his deliberations and awards. In order to avoid
late or abusive claims, no new claims whether counterclaims or otherwise
may be presented during the arbitration except by written joint agreement of
the Parties. Preparation of these Terms of Reference would preferably be
conducted by meetings, but could be effected by written dispositions. The
failure of a Party to participate does not prevent the Terms of Reference from
being drawn up. In such case, the arbitrator gives the Party concerned a final
time limit for submitting documents, failing which the arbitrator draws up the
Terms of Reference solely on the basis of the information submitted to him.
The arbitrator submits the Terms of Reference to the Parties (or their counsel)
for signature or comment. He may take into account any suggestions that
may be made and amend his draft accordingly. The arbitrator transmits the
Terms of Reference, signed by the Parties and himself, to the Court, which
takes note thereof. If a Party refuses to sign the Terms of Reference, the
arbitrator nonetheless submits them signed by the other Party and himself,
and the Court will approve them if satisfied that they have been prepared in
accordance with the Rules. The refusal by one Party to sign the Terms of
The Louis Berger Group, Inc.
August 2011
II-4 /58
Reference does not affect the validity of the proceedings; nor does it prevent
that Party from participating in the proceedings.
The Terms of Reference do not prejudge the case; they merely record the
Parties respective claims and describe the arbitrators mission. Similarly,
approval of the Court does not constitute approval of all the matters described
therein, but merely permits the arbitration to proceed.
The balance of the Advance (a further 25% from each Party) is due after
communication to the Court of the Terms of Reference for the dispute, and
the Terms of Reference come into force only after the Advance has been fully
paid.
If a defaulting Party persists in not paying its share of the Advance after
communication or approval of the Terms of Reference, the other Party may
either pay the remaining 50% or supply a bank guarantee therefor.
When, in addition to the principal claim, one or more counterclaims have been
submitted, the Court may fix separate advances for the principal claim and
counterclaim(s). In such case the Secretariat invites each Party to pay the full
amount of the separate Advance corresponding to its own claims. Thus, if a
request for an Advance is not complied with, the claim to which the delinquent
advance relates whether the principal claim or a counterclaim is deemed
to have been withdrawn and cannot be referred to the arbitrator for a
decision.
The arbitrator shall decide whether to hear the Parties and any witnesses.
However, if one Party so requests, the arbitrator shall hear the Parties
together in person. The arbitrator may only rule on the basis of documents
only if the Parties so agree.
The arbitrator may appoint expert witnesses, either at his own motion or at
the request of a Party. The arbitrator may request assistance of the ICC
International Centre for Expertise for this purpose. The arbitrator defines the
experts brief, but before expert witness can be provided it is up to the Parties
to advance such sums as may be required to cover the experts fees and
expenses in whatever proportions the arbitrator determines. Unless precluded
by provisions of the Works Contract, the Engineers staff may be called upon
to give evidence or opinion.
An arbitral award is rendered unanimously or by majority decision or, failing
either of these, by the chairman of an arbitral tribunal. The award must be in
writing and should be reasoned.
The final award must contain a decision on all matters referred to the
arbitrator as required by the Terms of Reference. If the Parties reach an
The Louis Berger Group, Inc.
August 2011
II-4 /59
amicable settlement during the arbitration proceedings, they may request the
arbitrator to record the terms of their agreement in an award made by consent
of the Parties.
The award must be submitted in draft form to the Court of Arbitration for
approval. The draft award is not communicated to the Parties. The Court
scrutinizes the draft award as regards both to form and substance. The Court
has the power solely to lay down modifications as to the form of the award,
but may also draw the arbitrators attention to substance without, however,
affecting the arbitrators liberty of decision. This scrutiny is intended to
enhance the awards enforceability and represents an additional guarantee of
the quality of the decision.
The award is deemed to be rendered at the place of arbitration and on the
date subsequent to approval by the Court when it is signed by the
arbitrator. The award is notified by the Court Secretariat to each of the Parties
only after all of the costs of arbitration have been fully paid by the Parties.
The award is final and binding on the Parties. If one Party refuses to carry out
the award voluntarily, the other Party may obtain its enforcement by instituting
enforcement proceedings before any court of competent jurisdiction.
The costs of ICC arbitration will be based on the aggregate amount of the
principal claims and counterclaims in dispute, but will also depend on the
number of arbitrators and the Courts assessment of the complexity of the
case. Separate arrangements between the Parties and the arbitrator are not
permitted under ICC Rules. The following tables indicate the ranges of costs
that might be expected, based on the ICCs Scales of Administrative
Expenses and Arbitrator Fees effective in May 2010. The ICC Scales are
always designated in US$. Arbitrators expenses (including travel,
accommodation & meals) and fees/expenses of experts would be additional
to these costs.
Amount in Dispute: A to B
(in US$)
Up to 50,000
50,000 to 100,000
100,000 to 200,000
200,000 to 500,000
500,000 to 1 million
1 million to 2 million
2 million to 5 million
5 million to 10 million
August 2011
II-4 /60
Amount in Dispute:
A to B
(in US$)
Minimum
Maximum
Up to 50,000
50,000 to 100,000
100,000 to 200,000
200,000 to 500,000
500,000 to 1 million
1 million to 2 million
2 million to 5 million
5 million to 10 million
10 million to 30 million
30 million to 50 million
50 million to 80 million
80 million to 100 million
100 million to 500 million
Over 500 million
3,000
(3,000) + (2.650% of B-A)
(4,325) + (1.431% of B-A)
(5,756) + (1.367% of B-A)
(9,857) + (0.954% of B-A)
(14,627) + (0.689% of B-A)
(21,517) + (0.375% of B-A)
(32,767) + (0.128% of B-A)
(39,167) + (0.064% of B-A)
(51,967) + (0.059% of B-A)
(63,767) + (0.033% of B-A)
(73,667) + (0.021% of B-A)
(77,867) + (0.011% of B-A)
(121,867) + (0.010% of B-A)
August 2011
II-4 /61
Comment
August 2011
Guideline Requirement
Check
II-4.10 Works Suspensions:
Suspension by the Engineer:
Restrict delegated authority to instruct suspension
Instruct suspension only when absolutely necessary
Get /record Employer's prior concurrence (except in emergency)
II-4.11 Claims:
Contractor's Claims: Contractor responsible to comply with Contract
provisions for submission of Notice & Particulars of Claim
(failing which Claim is inadmissible under recent FIDIC)
Employer's Claims (under recent FIDIC): Employer responsible to comply
with Contract provisions for submission of Notice & Particulars of Claim
II-4.12 Documentation, Determination & Evaluation of Claims:
Documentation:
Consecutively number claims when Notice given
Maintain separate file for each claim, including all correspondence,
contemporary records, particulars, consultation records,
notices of dispute, Engineer's (or DAB's) decisions
Limit of Engineer's Authority to render Determinations:
Check if Contract requires Engineer to obtain Employer approval to
increase Contract Price, award Extension of Time or other limitation
Procedures for Engineer's Determination:
Engineer must consult with Parties before rendering Determination
Base Determination on joint agreement (if any) of Parties
Otherwise Determination must be fair /reasonable pursuant to Contract
First check 'Principle' of Claim is valid pursuant to Contract
Check 'Quantum' of Claim only if Principle is valid
If Engineer's authority limited by Contract, submit 'Assessment' of
Claim for Employer approval before rendering Determination
II-4.13 Delays, Extension of Time for Completion & Associated Costs:
[Procedures same as for II-4.11 & II-4.12]
Engineer's Determination:
First check 'Principle' of Claim is valid pursuant to Contract
Consideration of 'Concurrent Delay' & 'Contractor's Float' in EoT claims
Establish responsibility for delay (Employer /concurrent /climatic)
which will affect Contractor entitlement to costs
Review costs claimed by Contractor (if any) are appropriate to
attributed responsibility for 'Concurrent Delay'
If Prolongation Costs claimed:
Consider standard formulae (Hudson, Emden, Eichleay)
And/or require Contractor to provide evidence /substantiate
Apply 'Overhead Recovery' if EoT granted for additional work
Engineer must consult with Parties before rendering Determination
Base Determination on joint agreement (if any) of Parties
Otherwise Determination must be fair /reasonable pursuant to Contract
If Engineer's authority limited by Contract, submit 'Assessment' of
Claim for Employer approval before rendering Determination
Consideration of 'Price Adjustment' after original Time for Completion
II-4.14 Liquidated Damages & Bonus:
Liquidated Damages (also called Delay Damages):
Read /understand Contract provisions for Liquidated Damages
Engineer cannot apply Liquidated Damages (Employer's prerogative)
Engineer only certifies Liquidated Damages in Interim Payment
Certificates if instructed in writing by Employer
Bonus for Early Completion
May affect entitlement to Extension of Time for Completion
II-4.15 Dispute & Dispute Resolution:
Read /understand /follow Contract procedures for Dispute Resolution:
Recent standard FIDIC
Older standard FIDIC (pre 1999)
Appointment of DAB
Engineer's Decision
DAB's Decision
Amicable Settlement
Amicable Settlement
Arbitration
Arbitration
Comment
August 2011
II-5.
II-5.1
August 2011
II-5 /1
[Older form of contract, 3rd Edition (1987) entitled Electrical and Mechanical
Works. Recent form of contract, 1st Edition (1999) entitled Plant and DesignBuild.]
The Yellow Book contract is intended for the provision of electrical and/or
mechanical plant, and for the design and execution of building or
engineering works. Under the usual arrangements for this type of contract,
the Contractor designs and provides, in accordance with the Employers
Requirements, plant and/or other works; which may include any
combination of civil, mechanical, electrical and/or construction works.
The Contractor has full design responsibility for the Works, including
the Permanent Works and any Temporary Works the Contractor requires
to construct the Permanent Works. This design responsibility is not
diminished by any reviews or approvals of the Engineer or the Employer.
No doubt the Contractor will wish to economise, in terms of his costs,
which may be at the expense of quality. It is expected, therefore, that the
Employer has (or procures) the necessary technical expertise to ensure
that his requirements (Employers Requirements) have been clearly
specified in the Contract documents, and that this expertise remains
available during the design/build contract to ensure that those
requirements are achieved in practice.
Any modification of the Employers Requirements during the Contract
would require a Variation to be instructed, pursuant to the Contract
provisions, by the Engineer. But since the Engineer has no unilateral
authority make any changes to the Contract provisions, the Employers
written agreement would be required to such Variation [see Section II-3.3
Variations]. A Variation of the Employers Requirements might also result
from a Value Engineering proposal submitted by the Contractor [see
Section II-3.6 Value Engineering].
FIDIC Red Book Construction Contract:
[Older form of contract, 4th Edition (1987) entitled Works of Civil Engineering
Construction. Recent form of contract, 1st Edition (1999) entitled
Construction for Building and Engineering Works.]
The Red Book contract is intended for building or engineering works
designed by the Employer. Under the usual arrangements for this type of
contract, the Contractor constructs the Permanent Works in accordance
with a design provided by the Employer.
The Contractor is responsible for designing any Temporary Works
required to construct the Permanent Works.
The Permanent Works design may have been performed by the Employer
himself or by a firm (or firms) engaged by the Employer. The designer may
have been LBG.
Customarily, the Drawings and Specifications comprising the Permanent
Works design are included in the contract documents for the construction
The Louis Berger Group, Inc.
August 2011
II-5 /2
II-5.2
August 2011
II-5 /3
(which) specifies the purpose, scope, and/or design and/or other technical
criteria, for the Works.
In other words: the criteria in accordance with which the Contractor is
required to prepare his design of the Works.
The General Conditions (Sub-Clause 5.2 Contractors Documents) state
that:
If the Employers Requirements describe the Contractors Documents
which are to be submitted to the Engineer for review and/or for approval,
they shall be submitted accordingly
and also that:
In the case of a Contractors Document which has (as specified) been
submitted for the Engineers approval the Engineer shall give notice to
the Contractor that the Contractors Document is approved, or that it fails
(to the extent stated) to comply with the Contract.
Clearly then, it is the Employers Requirements that should specify:
- which documents are to be supplied by the Contractor as Contractors
Documents;
- which (if any) of such Contractors Documents are to be submitted to the
Engineer for review, and/or for acceptance or approval.
The General Conditions also require that the Contractor shall include the
periods for reviews, consents and approvals (as specified in the Employers
Requirements) in his Works Programme [see Section II.2.11 Works
Programme & Cash Flow and Section II-4.8 Works Programme & Cash
Flow Revisions]. Unless otherwise stated in the Employers Requirements,
each review period shall not exceed 21 calendar days, calculated from the
date the Engineer receives a Contractors Document.
The Contractor is required to give written notice that each submitted
Contractors Document complies with the Contract and is considered ready
for review (and, if so specified in the Employers Requirements, for consent
or approval).
The General Conditions [Sub-Clause 5.2 Design: Contractors Documents] of
FIDICs recent Yellow Book state:
Any such approval or consent, or any review shall not relieve the
Contractor from any obligation or responsibility,
and FIDICs older Yellow Book [Sub-Clause 6.1 Contractors Drawings]
contains similar wording.
The General Conditions of FIDICs recent Yellow Book [Sub-Clause 3.1(c)
Engineers Duties and Authority] also state that:
The Louis Berger Group, Inc.
August 2011
II-5 /4
August 2011
II-5 /5
necessary for the Engineer, after his review, to give notice to the Contractor
(which notice must be in writing):
- that the Engineer has no objection to the relevant Contractors
Document(s); or
- the extent to which the Engineer considers that a Contractors Document
fails to comply with the Contract.
[Note: For minor non-compliances, the Engineer could require the
Contractors correction without a resubmission. For other than minor noncompliances, the Engineer should require the Contractor to revise and
resubmit.]
However, if the Employers Requirements do require the Engineers consent
or approval, then the Engineer cannot side-step this requirement (unless
provisions of his Service Contract contradict provisions of the Works
Contract). [See Section II-1.4 Contradictions between Works Contract and
LBGs Service Contract ]
Under the circumstance that the Engineer has no objection to the Contractors
submission but consent or approval is stated as being required, then it is
recommended that the Engineers written notice to the Contractor be
accompanied by such words as:
The basis of the review on which this approval [*] is given, has been to
ascertain the general suitability of the design and its general compliance
with the Contract. This approval [*] shall not be interpreted to imply the
Employers or Engineers approval of the Contractors design and shall not
relieve the Contractor of any responsibility for his design.
[* approval or consent, as appropriate]
It is recommended, when the Contractor has submitted an acceptably full
and complete Contractors Document, that:
The Engineer shall provide to the Employer a copy of the Contractors
submission, at the time or soon after it is submitted (for which purpose the
Engineer might request the Contractor to submit an additional copy of his
design submissions).
When providing a copy of the Contractors submission to the Employer:
the Engineer shall advise that he is proceeding to review the submission
for compliance with the Employers Requirements, but request that the
Employer also sufficiently review the proposed design to ensure his
satisfaction.
If the Engineer or Employer identify any non-compliance with the
Employers Requirements, or the Employer has any other objection to the
Contractors Document, they should meet during the review period to
discuss such problems and formulate a mutual response.
August 2011
II-5 /6
II-5.3
August 2011
II-5 /7
August 2011
II-5 /8
the Contractor shall be responsible for this part and it shall, when the
Works are completed, be fit for such purpose for which the part is
intended and specified in the Contract; and
prior to Tests on Completion, the Contractor shall submit to the
Engineer as-built documents and operation and maintenance manuals in
accordance with the Specifications of the Contract.
[* Contractors Documents are defined as meaning calculations,
computer programs, and other software, drawings, manuals, models and
other documents of a technical nature to be supplied by the Contractor
under the Contract, and therefore includes documents relating to the
Contractors design.]
It should be noted that the General Conditions of FIDICs recent Red Book
contract do not state what Contractors Documents must be submitted to the
Engineer, the procedures for submission, the purpose of submission
(Engineers and/or Employers review, consent or approval?), or time periods
allowed for the Engineers review and response. All these requirements
should have been specified elsewhere in the Contract, typically in the
Specifications and/or Particular Conditions; and may include (as in older
FIDIC) that submissions be made for the Engineers approval.
FIDICs recent Red Book contract (Sub-Clause 3.1(c) Engineers Duties and
Authority) also states that:
any approval, check, consent, examination, notice or similar act by
the Engineer (including absence of disapproval) shall not relieve the
Contractor from any responsibility he has under the Contract, including
responsibility for errors, omissions, discrepancies and non-compliances.
However, notwithstanding this provision (and the similar provision under older
FIDIC), it might be difficult under the governing law of the Contract (if a
dispute arises) for the Employer (or the Engineer acting on the Employers
behalf) to refute all liability for an approved submission. Even a deemed
approval (meaning a required approval deemed to have been given if the
Engineer fails to respond to the Contractors submission within the time
prescribed by the Contract) could give rise to such problem.
Clearly, LBG, as the Engineer, should not risk professional liability by giving
consent or approval, where neither is required under the Contract.
Under recent FIDIC, it would be in the Engineers best interest (regarding
professional liability) if the Contract omits any requirement for the Engineers
consent or approval. If, prior to contract procurement, LBG assists the
Employer in drafting the Contract documents (especially with anticipation of
later providing services as the Engineer), then LBG should attempt to omit
such a requirement.
The Louis Berger Group, Inc.
August 2011
II-5 /9
August 2011
II-5 /10
notification to the Contractor should state that the Employer has had
opportunity to review the Contractors design submission and the
Engineers response and has raised no objection thereto.
All submissions and responses must be in writing.
II-5.4
August 2011
II-5 /11
Clearly though, the layout and details of elements of the Permanent Works to
be designed by the Contractor might be affected by or affect the layout and
details of the design provided by the Employer (such as in the case of
electrical/mechanical plant designed by the Contractor to be incorporated
within civil engineering or building works for which design has been provided
by the Employer).
Recent FIDICs definition of Drawings is:
drawings of the Works as included in the Contract, including any
additional and modified drawings issued by (or on behalf of) the Employer
in accordance with the Contract.
Unless there is overriding provision elsewhere in the Contract, the Engineer
has no design-preparation duties under FIDIC Red Book General Conditions.
It is submitted, therefore, that the above Contract provision does not require
that the Engineer make any necessary additions or modifications to the
Drawings but only that the Engineer shall co-ordinate this activity. Any
modifications or additions to the Drawings should be provided by the
Employer, who provided the original Drawings included in the Contract.
It is likely that the original design and Drawings were prepared by designers
(hereinafter the original designer) contracted separately by the Employer for
that purpose prior to the procurement phase of the subject Works Contract.
The original designer may also have assisted the Employer in preparation
and compilation of the tender documents. Indeed, the original designer might
have been LBG.
Thus, unless the Contract contains contrary overriding procedural
provisions, it is recommended that the following procedure be adopted
(either under a recent or older FIDIC Red Book contract) in the event that the
Engineer considers that the Contractors design might necessitate
modifications or additions to the Drawings.
In his review of the Contractors design submission (Contractors
Documents under recent FIDIC), the Engineer should check that the
Contractor has provided sufficient information to identify the technical
and/or physical inter-relationship (if any) between the Contractors design
and the Employers original design.
If the Engineer considers or suspects that modifications or additions might
be necessary to the Drawings, he shall refer the Contractors design
submission to the Employer (in writing) for his no-objection; together with
a recommendation that the matter be referred by the Employer to his
original designer for any necessary detailed design checks and execution
of any necessary modifications or additions to the Drawings.
The Engineers notice of no-objection, consent or approval (as appropriate
in accordance with the Contract) should not be given to the Contractor
The Louis Berger Group, Inc.
August 2011
II-5 /12
until the Engineer has received the Employers written and clear noobjection to the Contractors design submission.
Responsibility for any necessary modifications or additions rests with the
Employer. If those modifications or additions to the Drawings are prepared
on the Employers behalf by the original designer, then they must be
transmitted by the original designer to the Employer, thenceforward by the
Employer to the Engineer, and finally (pursuant to the Contract) issued by
the Engineer to the Contractor. This formal sequence must be maintained
for reason of contractual authority. Unless specifically authorized under
the Works Contract, the original designer would have no authority to issue
Drawings directly to the Engineer and/or the Contractor.
Any new Drawings should be Approved for Construction. Any modified
Drawings should also bear a revision number, date and description of the
revision.
Even in the event that LBG, in addition to being the Engineer, was also the
original designer and has a contract to provide design-related services
during the Works Contract, it is recommended that these procedures still
be followed.
All submissions and responses must be in writing.
Problems could arise if the Employers contract with the original designer
(who was not LBG) had no provision for continuation of design-related
services during the Works Contract and has expired, or if the Employer is
unable or reluctant to re-engage his original designer for services during
construction, or if the original designer no longer exists. This would be the
Employers problem to resolve.
If LBG is the Engineer but was not the original designer (or if LBG was the
original designer but has no contract to provide design services during the
Works Contract), then:
the Engineers Site supervision staff must not succumb to entreaty or
pressure of the Employer for the Engineer to undertake any design
functions (and any consequential professional liability which could ensue
from effecting modifications or additions to the Drawings) unless a
contract is conformed between the Employer and LBG under which LBG
would provide such services with appropriately experienced technical
staff;
under such circumstance LBGs Project Manager should seek guidance
from his HO Supervisor [see Section I-1.1 Appointment of Head Office
Supervisor]
August 2011
II-5 /13
II-5.5
August 2011
II-5 /14
August 2011
II-5 /15
August 2011
II-5 /16
It is hoped that the Employer has retained his expertise and/or the services of
external design experts during the execution phase of the subject Contract
to answer any requests for correction or clarification of the Employers
requirements. If not, the Employer could have a problem, and might entreat or
pressurize the Engineer to undertake such design-related function. For
reason of avoiding professional liability for services not included in the Terms
of Reference of his Service Contract, the Engineer must resist. It may be
necessary for LBGs Project Manager to seek guidance from his HO
Supervisor [see Section I-1.1 Appointment of Head Office Supervisor].
The Engineers response to the Contractors notice or request might be a
contractually non-consequential clarification. Alternatively, it may necessitate
initiation of a Variation [see Section II-3.3 Variations], from which could arise
the Contractors entitlement under the Contract to an extension of the Time
for Completion and/or additional payment. Clearly, to minimize such adverse
repercussions, Contractors notices or requests concerning the Employers
requirements should be dealt with as expeditiously as possible.
II-5.6
August 2011
II-5 /17
August 2011
II-5 /18
II-5.7
August 2011
II-5 /19
II-5.8
August 2011
II-5 /20
Construction (FIDIC Red Book) contract for which the Contactor has design
responsibility, it is submitted that a Variation would be still need to be
instructed if a foreseeable physical condition was unforeseen and if that
unforeseen physical condition necessitates a modification of the Employers
requirements for the Contractors design.
If the Contractors notice of physical conditions also notifies that those
conditions necessitate a modification of the Employers requirements for the
Contractors design, or if the Engineer considers that such modification might
be required, then the Engineer should proceed in accordance with the
procedures recommended in Section II-5.6 [Modification of Employers
Requirements for Contractors Design].
Under a Construction (FIDIC Red Book) contract, for which the Employer
provides the design, it is submitted that a Variation would need to be
instructed if a foreseeable physical condition was unforeseen and if that
unforeseen physical condition necessitates a modification of the Employers
design. But whether or not the matter needs to be referred by the Engineer to
the Employer (and onward by the Employer to his original designer [*]) will
depend on the circumstance, for which the Engineers common sense and
discretion will be required.
[* It is likely that the original design and Drawings were prepared by
designers contracted separately by the Employer for that purpose prior to
the procurement phase of the subject Contract hereinafter called the
original designer. It is also possible that LBG was the original designer.]
The following examples may help:
- For a change in length of a drainage culvert (to suit ground terrain) whose
structural and hydraulic design is otherwise unaffected, it would not be
necessary to refer the matter to the Employer.
The Variation could be instructed by a simple Engineers instruction [see
Section II-4.1 Engineers Instructions] with an attached sketch. If no new
pay items of the Bill of Quantities (BoQ) are required and the change in
quantities of the modified works will not be significant, there would be no
necessity to valuate the Variation [see Section II-3.4 Valuation of
Variations] and issue a Variation Order [see Section II-3.5]. Work
quantities will be subject to measurement [see Section II-3.8
Measurement of the Works].
- But for a change in the cross-sectional dimensions or longitudinal gradient
of a culvert (to suit ground terrain), which modifications could affect the
culverts structural integrity or hydraulic performance, the Engineer must
refer the matter to the Employer (and onward to his original designer, as
appropriate) for resolution.
Depending on the criticality of the subject culvert works within the
Contractors Works Programme, the Engineer may need to suspend
The Louis Berger Group, Inc.
August 2011
II-5 /21
August 2011
II-5 /22
If LBG is the Engineer but was not the original designer (or if LBG was the
original designer but has no contract to provide design services during the
Works Contract), then:
the Engineers Site supervision staff must not succumb to entreaty or
pressure of the Employer for the Engineer to take responsibility for any
design functions (and any consequential professional liability which could
ensue from effecting design modifications) unless a contract is conformed
between the Employer and LBG under which LBG would provide such
services with appropriately experienced technical staff;
under such circumstance, LBGs Project Manager should seek guidance
from his Head Office Supervisor [see Section I-1.1 Appointment of Head
Office Supervisor].
Should the Employer so choose, an alternative exists to request the
Contractor to submit a design proposal to overcome the unforeseen physical
conditions. Under such circumstance, if the Contractors design is acceptable,
it will be reasonable for the Contractor to expect and be entitled to payment
for the design modification. It is recommended that review and co-ordination
of the Contractors design modification should be in accordance with
procedures outlined under Section II-5.3 [Review of Contractors Design
under Construction Contract] and Section II-5.4 [Co-ordination of
Employers and Contractors Design].
Having instructed a Variation arising from physical conditions, the Engineer
then has to determine, subject to the Contractors compliance with Contract
procedures for claims [see Section II-4.11 Contractors Claims], the
Contractors entitlement to an extension of the Time for Completion and/or
additional Cost. For this purpose, the criterion of unforeseeability is critical.
FIDIC provides that:
- If the Contractor suffers delay and/or increased Cost arising from adverse
physical conditions that the Engineer determines were not foreseeable by
an experienced contractor, then the Contractor shall be entitled to an
extension of the Time for Completion and/or additional Cost.
- FIDIC provides a caveat that the Engineer, in determining the Contractors
entitlement, may take into consideration other physical conditions in
similar parts of the Works (if any) that were more favourable than could
reasonably have been foreseen when the Contractor submitted his
Tender.
And the corollary of that provision is that:
- If the Engineer determines that the physical conditions, although
unforeseen by the Contractor, were foreseeable by an experienced
contractor, then the Contractor is not entitled to any extension of the Time
for Completion or additional Cost.
The Louis Berger Group, Inc.
August 2011
II-5 /23
II-5.9
Employers Design:
Contractors Notices of Faults or Requests for Clarification,
& Design Modifications arising therefrom
This Section applies to construction contracts (FIDIC Red Book) under which
design for all (or most of) the Permanent Works is provided by the Employer.
The Contractor has no design responsibility for Works for which the Employer
has provided the design (as contained in the Drawings and Specifications)
except in regard to preparation of any required Shop Drawings [see Section
II-5.11] necessary for pre-fabricated components to be incorporated into the
Permanent Works to meet requirements of the Employers design.
The Contractors only other design responsibility is for any Temporary Works
he requires to construct the Permanent Works.
The Contractor should, as soon as is practicable, give notice to the Engineer
of any errors, faults, defects, omissions, inconsistencies, or ambiguities he
discovers in the Drawings and Specifications, which could affect or are
affecting his execution of the Works. Although FIDIC does not place this as
an obligation upon the Contractor, the Engineers determination of any
August 2011
II-5 /24
August 2011
II-5 /25
If, as the Engineer, LBG receives from the Contractor a notice of any alleged
fault with the Employers design, or any request for clarification of or
additional information pertaining to that design:
It is recommended that the following procedure be adopted:
- if LBG has no contract with the Employer for services relating to the
Employers design during the Works Contract (even if LBG was the
Employers original designer under a previous but expired separate
contract):
The Engineer shall promptly forward the Contractors notice or request
to the Employer, together with the Engineers written request that the
Employer inform the Engineer what response the Employer wishes the
Engineer to convey to the Contractor.
The Engineers referral to the Employer should include advice as to
any potential contractual consequences of the Contractors
notice/request, or of delay in responding to that notice/request (e.g. a
necessary Variation, extension of the Time for Completion, or
additional Cost).
The Engineer shall respond to the Contractor only after receiving the
Employers direction.
It is recommended that the following procedure be adopted:
- if LBG was the Employers original designer and has a continuing
responsibility, specifically stated within his contract to provide
services of the Engineer, to resolve any questions regarding the
Employers design:
The Engineer shall promptly forward the Contractors notice/request to
the Employer, together with the Engineers written request to mobilize
the necessary technical staff (on-Site or off-Site as the case may be).
[The Engineers request to mobilize short-term technical staff (and the
Employers approval) may be a contractual pre-condition to LBGs
entitlement to payment for such services.]
If mobilization of LBGs technical review staff has been approved, LBG
shall (after its review of the Contractors notice/request), in its capacity
as the Engineer, convey to the Employer (in writing)
recommendations of a response to the Contractor (which response is
intended to be conveyed by the Engineer to the Contractor if the
Employer so consents).
The Engineers recommendations to the Employer should include
advice as to any potential contractual consequences of the
Contractors notice/request and the Engineers proposed response
(e.g. a necessary Variation, and/or extension of the Time for
Completion, and/or additional payment). There might be a matrix of
August 2011
II-5 /26
August 2011
II-5 /27
August 2011
II-5 /28
II-5.10
August 2011
II-5 /29
the Contractor shall be responsible for the part and it shall, when the
Works are completed, be fit for such purposes for which the part is
intended as are specified in the Contract; and
- prior to Test on Completion, the Contractor shall submit to the
Engineer the as-built documents and operation and maintenance
manuals in accordance with the Specification
[* Contractors Documents are defined as meaning calculations,
computer programs, and other software, drawings, manuals, models and
other documents of a technical nature to be supplied by the Contractor
under the Contract, and therefore includes documents relating to the
Contractors design.]
August 2011
II-5 /30
August 2011
II-5 /31
II-5.11
August 2011
II-5 /32
Under a Construction (FIDIC Red Book) contract, however, for which design
is provided by the Employer, the Contractors submission and Engineers
review of shop drawings would be required so that the Engineer can verify
(prior to fabrication or installation) that fabrication and/or installation details are
in accordance with the Employers Drawings and Specifications.
Shop drawings submissions must be adequately detailed to demonstrate
compliance with the Contract and jobsite conditions, including (as appropriate):
- Complete fabrication details.
- Design provision and instructions for transportation and handling (i.e.
operations for which design conditions will be different than those after final
incorporation into the Permanent Works).
- Dimensions to fit jobsite as-built details of works into which a fabricated
item is intended to be installed. For example: dimensions of a fabricated
bridge-deck expansion joint must fit the already constructed bridge deck
into which it is to be installed.
- Installation instructions, methodology and details. This may include
information on fasteners, adhesives and other necessary installation
materials, and any required Temporary Works.
- Manufacturers catalogues and specifications.
- Material samples, as may be required, say, for selection of colour or
texture finishes.
Review of the Contractors shop drawings must be performed by someone
who is thoroughly acquainted with the Contract Drawings and Specifications.
The Engineers on-Site supervision team may be able to review those
submissions which do not require a detailed knowledge and understanding of
the design. For example, bar bending schedules for concrete reinforcement
could be checked. So too might fabrication and installation details for a
proprietary expansion joint - if the Employers Drawings adequately specify
the required provision for expansion/contraction.
On the other hand, some shop drawing submissions will require a detailed
knowledge and understanding of the design on which the Contract Drawings
and Specifications were based. For example, shop drawings for structural
steelwork, including joint weld details. These submissions should be referred
to and reviewed by the Employers original designer.
It is recommended that the following procedure be adopted under a
Construction (FIDIC Red Book) contract:
The Engineer should require the Contractor to submit, for the Engineers
review, shop drawings for Permanent Works of items to be prefabricated
August 2011
II-5 /33
If LBG was the original designer (under a contract separate from that under
which LBG is providing services of the Engineer), it is nevertheless
recommended that the Engineer maintain an arms-length relationship with the
The Louis Berger Group, Inc.
August 2011
II-5 /34
II-5.12
August 2011
II-5 /35
Employer for that purpose prior to the procurement phase of the subject
Contract. And the Engineer has no authority to make changes to the design
(Employers Requirements, Drawings or Specifications) without preauthorization by the Employer, whose design it is and who carries
responsibility for it.
It is possible that the entity providing services of the Engineer during the
Works Contract was also the original designer. But FIDIC does not need to
accommodate such situation, because it is the Employers prerogative, during
the Works Contract, to prepare or agree to any design changes
recommended by his original designer and the Employer would then instruct
the Engineer, who would then instruct the Contractor accordingly.
Under standard forms of FIDIC contract, all instructions are given to the
Contractor through and by the Engineer. Thus, any instructions of design
change given by the Engineer to the Contractor could, unless procedural
safeguards are implemented, reasonably be deemed by the Contractor to be
valid instructions authorized by the Employer.
The Engineer must be careful to tightly control his delegation of
authorities (to the Engineers staff) to issue instructions of design
change Variations to the Contractor. [See Section II-2.2 Engineers
Delegation of Duties & Authorities]
It is recommended that:
Delegated authority to instruct design-change Variations should be
severely restriction (as suggested in Appendix Q) to the person
designated as acting on behalf of the Engineer (the Engineers
Representative under older FIDIC contracts). If the Engineers Site staff
includes another suitably experienced person (say, a person holding the
title of Contracts Engineer or Chief Quantity Surveyor), the authority
could be extended.
The Contractor must be informed in writing (copied to the Employer) of
this limited delegation, and that instructions of Variations (including those
relating to design modifications) shall be valid only if instructed in writing
signed by a duly authorized person. The notice should state that any
instruction, in writing or oral, given by any unauthorized member of the
Engineers staff, shall be null and void until and unless confirmed in
writing by and under the signature of a duly authorized person.
The Engineers decision, whether or not a design modification needs to be
referred by the Engineer to the Employer for resolution, shall be taken only
by a person delegated authority to instruct Variations.
Whether or not a design modification needs to be referred by the Engineer to
the Employer (and onward by the Employer to his original designer) for
The Louis Berger Group, Inc.
August 2011
II-5 /36
resolution, will depend on the circumstance, for which the Engineers common
sense and discretion will be required.
The following examples under a FIDIC Red Book contract [as also presented
in Section II-5.8 Design Modifications arising from Unforeseen Physical
Conditions] may help:
- For a change in length of a drainage culvert (to suit ground terrain) whose
structural and hydraulic design is otherwise unaffected, it would not be
necessary to refer the matter to the Employer.
The Variation could be instructed by a simple Engineers instruction [see
Section II-4.1 Engineers Instructions] with an attached sketch. If no new
pay items of the Bill of Quantities (BoQ) are required and the change in
quantities of the modified works will not be significant, there would be no
necessity to valuate the Variation [see Section II-3.4 Valuation of
Variations] and issue a Variation Order [see Section II-3.5]. Work
quantities will be subject to measurement [see Section II-3.8
Measurement of the Works].
- But for a change in the cross-sectional dimensions or longitudinal gradient
of a culvert (to suit ground terrain), which modifications could affect the
culverts structural integrity or hydraulic performance, the Engineer must
refer the matter to the Employer (and onward to his original designer, as
appropriate) for resolution.
Depending on the criticality of the subject culvert works within the
Contractors Works Programme, the Engineer may need to suspend
execution of those works [see Section II-4.10 Works Suspensions] until a
design solution is resolved. The design modification might necessitate
new or revised Drawings to be provided (through the Employer) by the
original designer, which the Engineer would issue as an attachment to his
instruction of the Variation.
If the design is so substantially modified that the works are not adequately
covered by existing BoQ items, new pay items may have to be negotiated
with the Contractor [see Section II-3.4 Valuation of Variations] and a
formal Variation Order will be advisable [see Section II-3.5].
The requirement for a Variation, either to the Employers Requirements of a
Design/Build (FIDIC Yellow Book) contract or to the Employers design of a
Construction (FIDIC Red Book) contract, will have arisen from:
a) an initiative of the Employer; or
b) a notification of need from the Contractor; or
c) a discovery of need by the Engineer.
In the case of (b), a notification from the Contractor, the recommended
procedures for referring that notification to the Employer are presented
under Sections:
August 2011
II-5 /37
In the case of (c), a discovery by the Engineer, the Engineer should follow
procedures similar to those recommended in Sections II-5.5,
II-5.6 and II-5.9.
August 2011
II-5 /38
II-5.2
II-5.3
II-5.4
II-5.5
II-5.6
II-5.7
Requirement
Check
Contractual Responsibility for Design:
Type of Contract:
FIDIC old (<1999) Yellow Book (Contractor's Design)? Or
FIDIC recent (1999) Yellow Book (Contractor's design)? Or
FIDIC old (<1999) Red Book (Employer's Design)? Or
FIDIC recent (1999) Red Book (Employer's design)? Or
Other?
Review of Contractor's Design under Design-Build Contract:
[FIDIC Yellow Book ]
'Employer's Requirements' included in Contract?
'Employer's Requirements' adequately specify 'Contractor's
Documents' to be submitted to Engineer for review?
'Employer's Requirements' require Engineer's "Approval" of any
'Contractor's Documents'?
Procedure established for review of design?
Procedure established for response to Contractor after review?
Need for Engineer to qualify "Approval" or "Consent" in response?
Review of Contractor's Design under Construction Contract:
[FIDIC Red Book with elements of Contractor's design - If applicable ]
Employer's requirements for Contractor's design included in
Contract Specifications/Drawings?
Employer's requirements adequately specify design documents
to be submitted to Engineer for review?
Employer's Requirements require Engineer's "Approval" of any
of Contractor's design submissions?
Procedure established for review of design?
Procedure established for response to Contractor after review?
Need for Engineer to qualify "Approval" or "Consent" in response?
Co-ordination of Employer's & Contractor's Designs:
[FIDIC Red Book with elements of Contractor's design - If applicable ]
Procedure established for review of compatibility of Employer's
and Contractor's designs?
Employer's design prepared by others (original designer)?
Conflict between Contractor's design and Employer's design?
Conflict not possible to resolve by Contractor?
Need for Employer to refer conflict to his original designer?
Need for modifications to Employer's design?
Procedure for conveying design modifications to Contractor?
Need for 'Variation'?
Employer's Requirements for Contractor's Design Contractor's Notices of Faults or Requests for Clarification:
[FIDIC Yellow Book, or FIDIC Red Book with elements of Contractor's
design ]
Who prepared Employer's requirements for Contractor's design?:
Employer himself?
LBG on behalf of Employer?
Other entity on behalf of Employer?
Does LBG or other entity have contract with Employer to resolve
and respond to Contractor's notices or requests?
Depending on above 'checks', procedures established for
responding to Contractor's notices or requests?
Need for 'Variation'?
Modification of Employer's Requirements for Contractor's Design:
[FIDIC Yellow Book, or FIDIC Red Book with elements of Contractor's
design ]
Depending on above 'checks' in II-5.5, procedures established for
making necessary modifications to Employer's requirements
for Contractor's design, and for instructing Contractor?
Need for 'Variation'?
Design by Nominated Subcontractors under Provisional Sums:
[FIDIC Red Book - if Nominated Subcontractor required, and if that
Nominated Subcontractor required to perform design ]
Employer's requirements for Nominated Subcontractor's design
included in Contract Specifications/Drawings?
Employer's requirements adequately specify design documents
to be submitted (by Contractor) to Engineer for review?
Employer's requirements require Engineer's "Approval" of any
design submissions?
Procedure established for review of design?
Procedure established for response to Contractor after review?
Need for Engineer to qualify "Approval" or "Consent" in response?
Comment
August 2011
Guideline
II-5.8
II-5.9
II-5.10
II-5.11
II-5.12
Requirement
Check
Design Modifications arising from Unforeseen Physical Conditions:
[FIDIC Yellow Book or Red Book ]
Has Contractor given notice of unforeseeable Site conditions that
require modification of the Employer's requirements for
Contractor's design, or of the Employer's design?
Engineer determines if unforeseen conditions were foreseeable by
an experienced contractor.
Variation may need to be instructed if unforeseen condition
necessitates modification of Employer's requirements for
Contractor's design or of Employer's design.
Should Employer refer to original designer to determine if
unforeseen condition requires modification of Employer's
requirements, or of Employer's design?
Contractor's entitlement to extension of Time for Completion and/or
additional payment depends on Engineer's determination of
whether unforeseen condition was unforeseeable.
Employer's Design: Contractor's Notices of Faults or Requests
for Clarification, & Design Modifications arising therefrom:
[FIDIC Red Book only]
Who prepared Employer's design?:
Employer himself?
LBG on behalf of Employer?
Other entity on behalf of Employer?
Does LBG or other entity have contract with Employer to resolve
and respond to Contractor's notices or requests?
Depending on above 'checks', procedures established for
responding to Contractor's notices or requests?
Need for 'Variation'?
Review of Contractor's Value Engineering Proposals:
[Recent (1999) FIDIC Red or Yellow Book - but could be applied to
old (<1999) FIDIC]
Value Engineering provisions included in Contract?
Red Book: Provision for Employer/Contractor shared benefit of
cost saving?
Yellow Book: No provision for shared benefit of cost savings.
Value Engineering conceptual proposal submitted by Contractor
for Engineer's "approval in principle"?
Value Engineering detailed proposal submitted by Contractor
for Engineer's "approval"?
Employer's "no objection" required before Engineer can
convey approval to Contractor.
Employer should refer Value Engineering proposal to his
original designer.
Engineer must qualify meaning of "Approval" in positive response
to Contractor.
Review of Contractor's Shop Drawings:
[FIDIC Red Book. Would apply to FIDIC Yellow Book only if
specifically required by 'Engineer's Requirements'] .
Contract contains provisions for Contractor's submission of
Shop Drawings?
Red Book: Shop Drawings, for any prefabricated components of
Permanent Works, required to be submitted to Engineer for
review, to ensure compliance with Employer's design.
Shop Drawings to be submitted by Contractor - not by his
subcontractors of suppliers.
Engineer can review Shop Drawings of works that do not require
detailed knowledge of Employer's design, to verify compliance
with Contract specifications and jobsite conditions.
Shop Drawings of works requiring detailed knowledge of the
Employer's design must be referred to Employer (for
onward referral to original designer, if appropriate).
Procedures established for review of Shop Drawings, including
adoption of review comments: (e.g. "Submit additional
information", "Revise & resubmit", "No objection")?
If Contract requires Engineer's "approval" or "consent" in response
to Shop Drawing submissions, provide disclaimer of those terms.
Engineer's Authority to Instruct Design Modifications:
[FIDIC Yellow Book or Red Book ]
Engineer has no authority, without the Employer's
pre-authorization, to modify Employer's Requirements for
Contractor's design, or to modify Employer's design.
However, if Engineer instructs the Contractor of such modification,
Employer's pre-authorization is deemed to have been given.
Engineer always obtains Employer's authorization to instruct
Variation to modify Employer's Requirements for Contractor's
design, or to modify Employer's design?
Engineer has tightly controlled delegation of authorities (to
Engineer's staff) to instruct design changes to Contractor?
Comment
August 2011
II-6.
II-6.1
Substantial Completion
Most contracts, including standard forms of FIDIC contract, provide that a
Taking-Over Certificate shall be issued when the whole of the Permanent
Works (or Sections or parts thereof) have been substantially completed.
The Contract must be read carefully. Some standard forms of contract might
have been modified (by Particular Conditions) to require that a Taking-Over
Certificate shall not be issued:
- until the whole of the Works have been completed;
- until the Works (or a Section or part thereof) have been fully completed
(perhaps simply by the removal of the word substantially);
- until statutory procedures and requirements for taking-over the Works (or
hand-over) have been satisfactorily performed [see Section II-2.21
Compliance with Local Law].
Even if the Contract permits the Works (or Sections or parts thereof) to be
taken over upon substantial completion, the Contract might impose specific
requirements to be met, such as:
- the Contractor shall have satisfactorily completed any Tests on
Completion prescribed by the Contract;
- the Contractors submission of As-built Drawings;
August 2011
II-6 /1
II-6.2
Taking-Over Certificate
All contracts will contain provisions for handing over the Works by the
Contractor to the Employer when the Works have been completed. In FIDIC
terminology the Works are Taken-Over by the Employer when the Engineer
issues a Taking-Over Certificate to the Contractor.
The General Conditions of FIDIC forms of contract state that when the whole
of the Permanent Works (or a Section or part thereof) has been substantially
completed the Contractor may give notice to the Engineer for a Taking-Over
Certificate. Thus, it is not a requirement for the Contractor to give notice. At
his discretion the Engineer can issue a Taking-Over Certificate without the
Contractors notice of request; but, it is recommended, should only do so with
August 2011
II-6 /2
August 2011
II-6 /3
August 2011
II-6 /4
o any part of the Permanent Works which has been completed to the
satisfaction of the Engineer (older forms of FIDIC contract require the
part to be a substantial part of the Works); or
o any part of the Permanent Works which the Employer has elected to
occupy or use prior to completion (where such prior occupation or use is
not provided for in the Contract or has not been agreed by the Contractor
as a temporary measure).
The procedures for Taking-Over a Section or part of the Works is the same as
those for the whole of the Works, except that:
o responsibility for care and maintenance of only the Section or part of
Works passes from the Contractor to the Employer;
o under recent forms of FIDIC Contract, the portion of retention money to be
paid to the Contractor (upon issue of the Taking-Over Certificate for a
Section or part of Works) is only 40% of the proportional value of the
works of the Section compared to the estimated value of the whole of the
Permanent Works.
[Under older forms of FIDIC contract, the portion is 50%.]
Insofar as the Contractor may be keen to reduce his responsibility and liability
by handing over parts of the Works as soon as possible, he might try to handover small, and possibly non-contiguous, parts of the Works as he completes
them. It is submitted that this would be unreasonable. For example,
completion of a single minor bridge or small intersection on a 50km road
construction contract should not be considered for Taking-Over as a part of
the Works; although a major interchange might. Before considering to issue a
Taking-Over Certificate for a part of the Works, the Engineer should:
consult with the Employer and Contractor to determine what parts of
Permanent Works will reasonably be taken-over.
The date on which a Taking-Over Certificate is issued for a Section or part of
the Works is the date from which:
o responsibility for care and maintenance of that Section or part of the
Works passes from the Contractor to the Employer;
o a portion (*) of the Retention Money, based on the value of the taken-over
works relative to the total estimated final value of the whole of the
Permanent Works, is paid by the Employer to the Contractor (*50% under
older forms of FIDIC contract, or *40% under recent forms of FIDIC
contract) [see Section II-3.11 IPCs: Payment of Retention Money].
The date of substantial completion stated in the Certificate is the date from
which:
o the Employers entitlement to per diem Delay Damages is reduced in the
proportion that the value of the part of works certified as completed bears
August 2011
II-6 /5
to the estimated final value of the Works, but this reduction of entitlement
to per diem damages does not affect the stipulated maximum amount of
damages [see Section II-4.14 Liquidated Damages];
o the Defects Notification Period starts to run for the Section or part of the
Works certified as completed.
Form of Taking-Over Certificate
The Taking-Over Certificate may be a simple letter of certification to the
Contractor. However, some Employers may have a standard format of
Certificate that they wish to be used. The Engineer should consult with the
Employer to determine the form of the Certificate to be used.
Examples of Taking-Over Certificates are presented in Appendix O.
In the event that remaining works and/or defects corrections are permitted to
be completed during the Defects Notification Period, a Snag List of such
works and defects should be referenced in the Taking-Over Certificate and
appended thereto.
II-6.3
August 2011
II-6 /6
those required works; following which the Engineer should give notice of the
date for a further inspection to confirm completion of those works.
The list of remaining works and defects corrections that the Contractor is
permitted to complete during the Defects Notification Period (commonly called
a Snag List or Punch List) should be prepared by the Engineer and
appended to the Taking-Over Certificate as a record of what the Contractor
has undertaken to finish with due expedition during the Defects Notification
Period.
II-6.4
August 2011
II-6 /7
August 2011
II-6 /8
II-6.5
August 2011
II-6 /9
August 2011
II-6 /10
II-6.6
August 2011
II-6 /11
Comment
August 2011
II-7.
II-7.1
August 2011
II-7 /1
II-7.2
II-7.3
August 2011
II-7 /2
August 2011
II-7 /3
defects that could jeopardize safety in winter weather can be rectified before
the onset of winter weather; just after winter, in order that the effects of winter
(which may manifest defects) can be observed; and at the height of summer
when defects might also be manifested.
II-7.4
August 2011
II-7 /4
II-7.5
August 2011
II-7 /5
II-7.6
II-7.7
Further Tests
The General Conditions of both older and recent forms of FIDIC contract
require that the issue of a Taking-Over Certificate is predicated on the
successful passing of any Tests on Completion (if any) prescribed by the
Contract.
The General Conditions of FIDICs recent Red/Yellow Book contracts and
older Yellow Book contract provide further that:
- if the work of rectifying any defects after performance of those Tests may
have affected the performance of the Works,
then the Engineer may require a repetition of any such Test so prescribed in
the Contract, and the Works may not be finally accepted until such repeated
Tests have been successfully performed. The cost of performing repeated
Tests shall be borne by the Party liable for the cost of rectifying the defects.
August 2011
II-7 /6
The General Conditions of FIDICs older Red Book contract have no such
provision, but the Engineer should check if added Conditions of Particular
Application do.
II-7.8
II-7.9
Performance Certificate
In these guidelines the following FIDIC terms are used synonymously:
- Defects Notification Period (recent FIDIC) and Defects Liability Period
(older FIDIC);
- Performance Certificate (recent FIDIC) and Defects Liability Certificate
(older FIDIC).
FIDIC contracts require the Engineer to issue a Performance Certificate:
within 28 days after expiry of the Defects Notification Period; or
if different Defects Notification Periods shall have become applicable to
different Sections or parts of the Works, within 28 days after expiry of the
latest such period; or
as soon thereafter as any works instructed by the Engineer (in respect of
rectifying defects) have been satisfactorily completed and tested, and the
Contractor has handed over all documents prescribed to be handed over
pursuant to the Contract.
The Certificate may be a simple letter such as the example presented in
Appendix P. The letter must state the date on which, in the Engineers
determination, the Contractor completed his obligations under the Contract.
August 2011
II-7 /7
II-7.10
Clearance of Site
General Conditions of recent FIDIC forms of contract state, and those of
older FIDIC forms of contract imply, that upon receiving the Performance
Certificate the Contractor shall:
o Remove from Site any remaining Contractors Equipment, surplus
material, wreckage, rubbish and Temporary Works.
General Conditions of recent forms of FIDIC contract further provide that:
o If these items are not removed from Site within 28 days after the Employer
receives a copy of the Performance Certificate, the Employer may sell or
otherwise dispose of any remaining items.
o The Employer shall be entitled to be paid (by the Contractor) the costs
incurred in connection with such sale or disposal, which cost is deductible
from moneys owing from the Employer to the Contractor.
II-7.11
August 2011
II-7 /8
August 2011
II-7 /9
II-7.12
Contractors Discharge
FIDICs recent Red/Yellow Books and older Red Book prescribe that at the
time of submitting the Final Statement, the Contractor is required to submit a
Discharge stating that the total of the Contractors Final Statement
represents full and final settlement of all moneys due to the Contractor.
Curiously, FIDICs older Yellow Book has no such provision.
However, there are differences in wording between the General Conditions of
FIDICs older Red Book and its recent Red/Yellow Book contracts.
Under older forms of FIDIC Red Book contract:
Upon submission of the Final Statement, the Contractor shall give to the
Employer, with a copy to the Engineer, a written discharge confirming that
the total of the Final Statement represents full and final settlement of all
moneys due to the Contractor arising out of or in respect of the Contract.
Provided that such discharge shall become effective only after payment
due under the Final Certificate has been made and the performance
security has been returned to the Contractor.
Note: The Discharge is to be provided directly to the Employer.
Under recent forms of FIDIC Red/Yellow Book contracts:
When submitting the Final Statement, the Contractor shall submit a
written discharge which confirms that the total of the Final Statement
represents full and final settlement of all moneys due to the Contractor
under or in connection with the Contract. This discharge may state that it
becomes effective when the Contractor has received the Performance
Security and the out-standing balance of this total in which the discharge
will be effective on such date.
Note: Since the Final Statement is to be submitted to the Engineer, the recent
FIDIC wording implies that the Discharge also is to be submitted to the
Engineer (who is a representative of the Employer). It is recommended,
however, that the Discharge be addressed directly to the Employer, and
copied to the Engineer.
Although there is no requirement for the Contractor to state in his Discharge
that it is predicated on the Employers payment and return of the Performance
Security, it would be wise for the Contractor to so state, as in the following
suggested example:
We, , hereby confirm, in terms of Sub-Clause of the Conditions of
Contract, that the total of the Final Statement, namely , represents full
and final settlement of all moneys due to us under or in connection with
the Contract. This discharge shall only become effective when we have
August 2011
II-7 /10
II-7.13
II-7.14
Final Payment
Standard forms of FIDIC contract require that the Employer shall make the
Final Payment to the Contractor within 56 days after the date of his receipt of
the Engineers Final Payment Certificate.
August 2011
II-7 /11
Comment
August 2011
Guideline Requirement
Check
II-7.13 Final Payment Certificate:
Prepare Final Payment Certificate including:
Total value of Works completed under the Contract
Payment of remaining portion of Retention Money
Other payment entitlements:
Price Adjustment for change in Law
Price Adjustment according to Price Adjustment Formula
Other adjustments of Contract Price if prescribed by Contract
Amounts in respect of Claim settlements /determinations
Interest (Financing Charges) if claimed by the Contractor
Deductions:
As agreed for acceptance of non-complying work
Liquidated Damages (if Employer instructs to be certified)
In respect of works completed and/or
defects rectified by the Employer
Submit Final Payment Certificate within time prescribed in Contract
II-7.14 Final Payment:
Advise Employer of time prescribed in Contract for payment
Comment
August 2011
II-8.
CONTRACT TERMINATION
This Chapter describes the contractual provisions under which a Works
Contract may be terminated:
o By the Employer, arising from Contractors Default.
o By the Contractor, arising from Employers Default.
o By either Party, arising from Force Majeure.
o By the Employer, for Convenience.
II-8.1
August 2011
II-8 /1
Older forms of FIDIC contract require that the Employer cannot terminate
the Contract for certain reasons (such as items 5 to 10 above) until the
Engineer has certified to the Employer that, in his opinion, the Contractor is in
default thereof. The Engineers Representative (if delegated this responsibility
by the Engineer) must read the Contract provisions carefully, and should so
certify only if there are adequate written records to substantiate the facts, and
only with the specific concurrence of the Engineer. Even so, the Engineer
should be careful to state that it is his opinion that the Contractor is in
default. The Employers subsequent action, if any, should be based on his
own opinion.
Recent forms of FIDIC contract (where the Engineer is part of the
Employers Personnel) do not require any certification by the Engineer.
In any of the above events, under both recent and older forms of FIDIC
contract, the Employer may give 14 days notice to the Contractor of
termination; except that recent forms of FIDIC contract state that immediate
notice may be given in the event of reasons (1), (2) and (3) above.
In any event, if the Employer believes that the Contractors failure of
performance is sufficiently serious to merit termination, he should take legal
advice before giving notice of termination. Under no circumstance should the
Engineer give such advice. A notice of termination that is subsequently
decided in arbitration to have been unjustified would constitute a breach of
Contract by the Employer. The Engineer should not offer nor agree to draft a
notice of termination for the Employer. The Employer would be well advised
to engage a legal advisor (which the Engineer is not) to prepare a notice of
termination.
There are differences of wording between older and recent forms of FIDIC
contract as to what is being terminated, but the intent is the same.
Older FIDIC states that the employment of the Contractor is terminated
without releasing the Contractor from any of his obligations or liabilities under
the Contract and without affecting the rights and authorities conferred on the
Employer or the Engineer by the Contract. The reference to the Contractors
continuing obligations is obviously not intended to be taken literally plainly
the Contractor is relieved of his obligation to execute and complete the Works
rather the words prevent the Contract being determined (in the legal sense
of being brought to an end).
Recent FIDIC states that the Contract is terminated, but the intent cannot
be that it will be determined (in the legal sense of being brought to an end)
since words are included that the Employers rights under the Contract shall
not be prejudiced and prescribe the Contractors continuing obligations.
August 2011
II-8 /2
If the Employer gives notice and then wishes or agrees to withdraw it, the
Parties may agree that the notice shall be of no effect and that the Contract is
not terminated. Alternatively it may be agreed that the notice be put on-hold
pending certain actions within an appropriate time frame. Obviously, though,
there would need to be a jointly signed agreement or confirmatory exchange
of correspondence to such effect.
What happens after expiry of the Employers notice of termination:
o The Employer may complete the Works himself or arrange for other
contractors to do so.
o The Employer, or his other contractors, may use any of the Contractors
Documents, Contractors Materials, Plant, Equipment, Temporary Works
or on-Site facilities or other documents as they deem fit [ref: Sub-Clause
15.2 of 1999 FIDIC Red and Yellow Books].
Invariably this will necessitate the Engineer instructing the Contractor not
to remove any facilities from Site without the Employers prior approval,
and it would behove the Employer to be able to enforce this requirement
(by official means) and, if necessary, obtain a court restraining order. The
facilities should be released to the Contractor only after his receipt from
the Employer of a notice to that effect, which might not be until the Works
have been completed (although contracts are usually silent as to any
requirement for the Employer to complete the Works diligently).
o Unless prohibited by law, the Employer is entitled to require the Contractor
to assign to him the benefit of any agreements or subcontracts that the
Contractor may have entered into for the supply of any goods, materials or
services for execution of any works under the Contract. [The Employer
should start considering, before notifying termination, whether he would
wish (after termination) to seek agreements to assignments, or to
renegotiate direct contracts with any previous Subcontractors. In either
case, it may be preferable to achieve agreement of the Subcontractor,
rather than relying on a term of the Contract to impose assignment on an
unwilling Subcontractor.]
o The Engineer shall, as soon as is practicable after due consultation with
the Parties, determine the value of the Works completed, Plant &
Materials (i.e. intended for incorporation into the Works) and Temporary
Works, or any other sums due to the Contractor for Works executed in
accordance with the Contract.
o The Employer is entitled to withhold any further payments to the
Contractor until the expiration of the Defects Notification Period and
thereafter until the costs of completing the Works and remedying any
defects attributable to the Contractor, damages for delay in completing the
Works (if any) and all other related expenses of the Employer have been
established.
August 2011
II-8 /3
[Note that older FIDIC requires the Engineer to certify these costs, which
would necessitate his continued close involvement with the Works
completion; but recent FIDIC does not.]
o Upon completion of the Works, the Contractor is entitled to receive the
amount (if any) to which the Contractor would have become entitled if he
had completed the Works himself (which older FIDIC requires to be
certified by the Engineer, but recent FIDIC does not), less the amount of
the Employers costs of completing the Works and his incurred delay
damages (if any). If the Employers costs and damages exceed the
Contractors entitlement, then the excess becomes a debt due by the
Contractor to the Employer.
II-8.2
August 2011
II-8 /4
8)
9)
In such of the above events, depending on the actual terms of the Contract,
the Contractor may give 14 days notice to the Employer of termination;
except that recent FIDIC entitles the Contractor to give notice of immediate
termination for reasons (3) and (4).
The Contractors election to terminate the Contract does not prejudice any
other rights of the Contractor under the Contract or otherwise.
If the Contractor gives notice and then wishes or agrees to withdraw it, the
Parties may agree that the notice shall be of no effect and that the Contract is
not terminated. Alternatively it may be agreed that the notice be put on-hold
pending certain actions within an appropriate time frame. Obviously, though,
there would need to be a jointly signed agreement or confirmatory exchange
of correspondence to such effect.
What happens after expiry of the Contractors notice of termination:
o The Contractor ceases all further work, except as may be instructed by the
Engineer for the safety of life, property and the Works.
o The Contractor hands over to the Employer any documents, Plant,
Materials and other work for which he has received payment.
o The Contractor removes from Site, with reasonable dispatch, all his
Equipment and facilities, and leaves the Site.
o The Employer must return the Contractors Performance Security.
o The Engineer shall determine and the Employer must pay to the
Contractor (less any deductions to which the Employer is entitled under
the Contract):
- amounts payable for works acceptably performed (including preliminary
items of the Bill of Quantities insofar as they have been provided);
- the cost of Plant and Materials delivered to the Contractor, or of which
the Contractor is liable to accept delivery (these become the property of
the Employer when paid for by the Employer);
- any other cost or liability which in the circumstances was reasonably
incurred by the Contractor in the expectation of completing the Works;
- the cost of removal of Temporary Works and Contractors Equipment
from Site and their return to the Contractors home base (or to other
destinations at no greater cost);
The Louis Berger Group, Inc.
August 2011
II-8 /5
II-8.3
August 2011
II-8 /6
Recent FIDIC provides that either Party may give notice of termination, but
that the notice shall be given within 14 days after the Party became aware, or
should have become aware, of the event constituting Force Majeure.
Fourteen days may seem a generous period within which to notify an
exceptional event, but it may not be immediately apparent that it will affect a
Partys performance. The notice must specify:
- the event which is considered to constitute Force Majeure;
- the effect by which it will prevent specific performance obligations under
the Contract.
Recent FIDIC appears not to permit a notice of termination given later than
the prescribed 14 days. It is a reasonable interpretation that, after 14 days,
termination would have to be by mutual consent.
What happens after notice of termination arising from Force Majeure:
o The Contractor ceases all further work, except as may be instructed by the
Engineer for the safety of life, property and the Works.
o The Contractor hands over to the Employer any documents, Plant,
Materials and other work for which he has received payment.
o The Contractor removes from Site, with reasonable dispatch, all his
Equipment and facilities, and leaves the Site.
o The Employer must return the Contractors Performance Security.
o The Engineer shall determine and the Employer must pay to the
Contractor (less any deductions to which the Employer is entitled under
the Contract):
- amounts payable for works acceptably performed (including preliminary
items of the Bill of Quantities insofar as they have been provided);
- the cost of Plant and Materials delivered to the Contractor, or of which
the Contractor is liable to accept delivery (these become the property of
the Employer when paid for by the Employer);
- any other cost or liability which in the circumstances was reasonably
incurred by the Contractor in the expectation of completing the Works;
- the cost of removal of Temporary Works and Contractors Equipment
from Site and their return to the Contractors home base (or to other
destinations at no greater cost);
- the cost of repatriation of the Contractors staff and labour employed
upon the Works at the date of termination.
August 2011
II-8 /7
II-8.4
August 2011
II-8 /8
Appendix A
COMPUTATION OF
TIME CHARGES,
ALLOWANCES &
REIMBURSABLE EXPENDITURES
Referenced in:
Section I-2.4: Rules for Time Charges & Reimbursable Expenditures
PROJECT TITLE
EXAMPLE
REFERENCES:
Terms of Reference (TOR) and LBG Proposal, both as embodied in the Service
Contract:
Article # Working Days of (Funding Institution) Manual, Annex # (copy attached).
Page # of TOR Comments to the Breakdown of Prices (copy attached).
LBG Financial Proposal, (Date):
Units of measurement for Consultants time:
Long-Term Consultants & Staff (> 6 months) designated as per Month.
Consultants & Staff designated as per Day.
Short-Term Experts and Part-Time Consultants designated as per Month.
2.
Appendix A
1 of 6
(Client) will sign LBGs bar chart submission as Accepted for Record Purposes and
provide copy to LBG.
Post-acceptance omissions may be corrected by mutual agreement which shall not be
unreasonably withheld (e.g. correction of an obvious mistake or revision for a latesubmitted timesheet).
Rules for computation of Consultants work time, allowances, per diems, and timerelated direct costs are described hereunder.
3.
3.1
3.2
Statutory Holidays:
Long-Term Staff (> 6 months):
Statutory Holidays shall count as Work Days (whether worked or not).
If a Statutory Holiday is worked, it shall only count as a single Work Day.
If (Client) officially moves a Statutory Holiday (i.e. to another day in lieu thereof) the
substitute day will be the Statutory Holiday for purpose of computing Consultants
time.
If (Client) closes its general staff operations for days other than Statutory Holidays or
days in lieu of Statutory Holidays, such days will be counted as Work Days only if
worked by the Consultants with prior (Client) approval.
Short-Term & Part-Time Staff (< 6 months):
Statutory Holidays and other days on which (Client) may close its general staff
operations shall not count as Work Days unless actually worked by the Consultants
with prior (Client) approval.
3.3
Appendix A
2 of 6
Computation Examples:
Example: December 1998
Work days available = 23 (including 3 Statutory Holidays)
Statutory Holidays = 3 days (not worked)
Other days worked by Consultant = 17 days
Therefore Proportion of Month = 20 / 22 = 0.91 month
Example: February 1999
Work days available = 20 (no Statutory Holidays)
Days worked by Consultant = 20 days
Therefore Proportion of Month = 20 / 20 = 1.00 month
Example: February 1999
Work days available = 20 (no Statutory Holidays)
Days worked by Consultant = 18 days
Therefore Proportion of Month = 18 / 20 = 0.90 month
Example: March 1999
Work days available = 23 (including 1 Statutory Holiday)
Statutory Holidays = 1 day (not worked)
Other days worked by Consultant = 21 days
Therefore Proportion of Month = 22 / 22 = 1.00 month
Example: March 1999
Work days available = 23 (including 1 Statutory Holiday)
Statutory Holidays = 1 day (on which Consultant worked)
Other days worked by Consultant = 26 days
Therefore Proportion of Month = 27 / 22 = 1.00 month
Short-Term Staff (< 6 months per assignment) / Payment Unit per Day:
Short-Term & Part-Time Staff (< 6 months per assignment) / Payment Unit per
Month:
Appendix A
3 of 6
If Consultants Work Days in a calendar month equal or exceed Work Days Available
In Month or 22 days (whichever is the least), then the Consultant is deemed to have
worked a full month. Days worked in excess of Work Days Available In Month or 22
days (whichever is the least) are not counted.
If Consultants Work Days are less than the Work Days Available In Month or 22
days (whichever is the least), then a part month is computed from the formula:
Proportion of Month = (Actual Work Days) / Work Days Available or 22
(whichever is least)
Computation Examples:
Example: December 1998
Work days available = 23 (including 3 Statutory Holidays)
Statutory Holidays = 3 days (not worked)
Other days worked by Consultant = 17 days
Therefore Proportion of Month = 17 / 22 = 0.77 month
Example: February 1999
Work days available = 20 (no Statutory Holidays)
Days worked by Consultant = 20 days
Therefore Proportion of Month = 20 / 20 = 1.00 month
Example: February 1999
Work days available = 20 (no Statutory Holidays)
Days worked by Consultant = 18 days
Therefore Proportion of Month = 18 / 20 = 0.90 month
Example: March 1999
Work days available = 23 (including 1 Statutory Holiday)
Statutory Holidays = 1 day (not worked)
Other days worked by Consultant = 21 days
Therefore Proportion of Month = 21 / 22 = 0.95 month
Example: March 1999
Work days available = 23 (including 1 Statutory Holiday)
Statutory Holidays = 1 day (on which Consultant worked)
Other days worked by Consultant = 26 days
Therefore Proportion of Month = 27 / 22 = 1.00 month
4.
Appendix A
4 of 6
Agreed by:
For Louis Berger ...
Project Management Guidelines
5 of 6
(Representatives Name/Title)
Date:
Date:
Appendix A
6 of 6
Appendix B
INCEPTION REPORT
Referenced in:
Section I-2.5: Inception Report
EXAMPLE
INCEPTION REPORT
TABLE OF CONTENTS
Letter of Transmittal
1.
PROJECT BACKGROUND
Purpose and history of Project. Client. Funding Institution. Scope of Project. Scope of services to
be provided.
2.
3.
4.
5.
PROJECT ORGANIZATION
Description. Present Organization chart in Appendix.
6.
PROJECT SCHEDULE
Present time bar chart in Appendix of main Project/Contract phases. Identify & discuss critical
activities for achievement.
7.
CONSULTANTS MOBILIZATION
Itemize mobilization of staff & facilities to date, and planned mobilizations. Present as time bar
chart.
8.
Appendices:
A
PROJECT ORGANIZATION
B
PROJECT SCHEDULE
C
CONSULTANTS MOBILIZATION
Project Management Guidelines
Appendix B
1 of 2
EXAMPLE
Year 2003
PROJECT SCHEDULE:
Month Mar Apr May Jun
Works Contract No.1
Compile Tender Documents
Tender Period
Tender Evaluation & Report
Funding Institution Approval
Compile Contract Documents & Contract Award
Time for Completion
Defects Notification Period
Final Payment Certificate & Discharge
Works Contract No.2 Ditto
Jul
Aug Sep
Oct
Nov Dec
2004
2005
Jan Feb Mar
Dec
2006
Jan Feb Mar.
Dec
2007
Jan Feb Mar
Intermittent
Intermittent
Appendix B
2 of 2
Appendix C
FORMAT FOR MONITORING
SERVICE CONTRACT BUDGET
Referenced in:
Section I-2.6: Management of Service Contract Budget
EXAMPLE
POSITION
A. FEES
A.1.1 Expatriate Staff:
The Engineer (part time)
Project Manager /Engineer's Representative
Resident Engineer (Contract 1)
Resident Engineer (Contract 2)
Materials Engineer
Short Term Experts
A.1.1 Local Staff
Project Engineer
Deputy Resident Engineers
Quantity Surveyors
Materials Engineer
Land Surveyors
Inspectors
A.1.1 Sub-Totals
A.1.2 ALLOWANCES:
Long-term Expatriate Staff:
Accommodation in (Main City )
Accommodation outside (Main City )
Per Diem away from Base in (Main City )
Per Diem away from Base outside (Main City )
Short-Term Expatriate Staff:
Per Diem in (Main City )
Per Diem outside (Main City )
Local Staff:
Per Diem away from Base in (Main City )
Per Diem away from Base outside (Main City )
A.1.2 Sub-Totals
A. Sub-Totals
B. DIRECT COSTS:
Financial Administrator
Bilingual Secretaries
Interpreters /Translators
Bilingual Office Clerks
Drivers
Vehicle Running Costs
Office Rent & Maintenance
Return Airfares (Expatriates)
Mobilization /Demobilization Allowance
Reports
B. Sub-Totals
Name
Unit
Unit
Rate
Contract
Quantity
month
month
month
month
month
day
20,000
20,000
16,000
16,000
14,000
1,000
4
24
24
24
24
12
month
month
month
month
month
month
2,500
2,000
1,500
1,500
1,300
1,000
27
54
54
50
50
120
0.83
month
month
day
day
1,200
700
120
70
60
54
30
60
0.83
day
day
120
70
240
240
day
day
50
30
30
90
month
1,500
month
1,250
month
1,000
month
750
month
500
month
250
month
1,000
No.
750
No.
2,000
LS 100,000
27
75
75
75
30
30
30
12
4
1
D1
E1
0.83
0.30
F 1 =C 1 -E 1
0.83
0.30
Quantity Total
Previous To Date
G 1 =H 0
H 1 =G 1 +F 1
0.83
0.30
D2
E2
1.00
F 2 =C 2 -E 2
1.00
1.00
1.00
Quantity Total
Previous To Date
G 2 =H 1
H 2 =G 2 +F 2
0.83
0.30
0.27
0.45
3.00
0.83
0.30
5.00
0.83
1.00
0.27
1.00
0.20
1.83
1.50
1,200.00
840.00
996.00
210.00
5.00
11.00
72,000.00
37,800.00
3,600.00
4,200.00
420.00
350.00
28,800.00
16,800.00
360.00
6.00
3.00
8.00
5.00
13.00
1.00
1.00
1.00
0.50
0.50
1.50
1.00
1.50
1.00
1.50
1.00
1.50
1.00
0.025
1.00
0.83
0.50
1.00
1.00
0.00
2.00
2.33
1.50
2.50
2.00
0.03
1.00
0.50
1.00
0.50
0.50
0.50
1.00
0.83
0.50
1.00
0.83
0.50
1.00
1.00
1.00
0.83
0.50
1.00
1.00
1.00
1.50
1.00
1.00
0.50
0.025
0.50
0.50
0.50
3.00
1,500.00
2,700.00
167,400.00
2,876,400.00
40,500.00
93,750.00
75,000.00
56,250.00
15,000.00
7,500.00
30,000.00
9,000.00
8,000.00
100,000.00
435,000.00
3,311,400.00
Appendix C
2,500.00 2,075.00
2,540.00
0.00
750.00
750.00
650.00
500.00
60,680.00 25,550.00
500.00
375.00
1,000.00
1,125.00
2,000.00
2,500.00
11,250.00
36,600.00
20,800.00
750.00
500.00
500.00
207.50
500.00
750.00
2,000.00
Quantity
Remains
=B-H 2
4.00
22.17
22.70
24.00
23.55
9.00
4,575.00
2,540.00
750.00
750.00
650.00
500.00
86,230.00
25.17
52.73
53.50
49.50
49.50
119.50
2,196.00
1,050.00
58.17
52.50
30.00
49.00
770.00
360.00
240.00
150.00
3,060.00 1,706.00
63,740.00 27,256.00
1,500.00
1,250.00
1,000.00
=K+L
6,300.00
3,000.00
0.83
0.30
3.00
0.50
6,300.00
3,000.00
1.00
1.20
6.00
0.50
20,000.00 16,600.00
16,000.00 4,800.00
67,500.00
108,000.00
81,000.00
75,000.00
65,000.00
120,000.00
2,709,000.00
5.00
0.50
L=G 2 *A
1.83
1.27
0.50
0.50
0.50
0.50
5.00
8.00
80,000.00
480,000.00
384,000.00
384,000.00
336,000.00
12,000.00
K=F 2 *A
0.83
1.00
5.00
=B*A
Amount
This Month Previous Total to Date
1.00
1.27
0.50
0.50
0.50
0.50
0.83
0.30
5.00
1.00
0.50
1.00
0.50
0.50
0.50
0.50
0.45
3.00
0.83
0.30
5.00
0.50
0.45
3.00
TOTALS
Notes:
1) All amounts & Rate in (currency).
1.83
1.30
Contract
390.00
4,766.00
90,996.00
2,250.00
1,250.00
1,500.00
5,207.50
1,000.00
582.50
1,500.00
1,875.00
4,000.00
2,500.00
16,457.50
74,990.00 32,463.50
107,453.50
237.00
240.00
0 00
0.00
30.00
77.00
25.50
74.00
73.50
75.00
28.00
27.67
28.50
9.50
2.00
0.98
1 of 1
Appendix D
FORMAT FOR
INVOICING CLIENT
Referenced in:
Section I-2.4: Rules for Time Charges & Reimbursable Expenditures
Section I-2.8: Invoicing for Services
Attention:
Name /Title
Reference:
Subject:
In accordance with Contract No. dated.., between The Louis Berger Group, Inc. and the Government
of, represented by The Ministry of, we request the following payment:
(currency: .)
a
b
c=a+b
d
Fees
Direct Costs
This
Previous
Total to
Contract
Amounts
Invoice
Invoices
Date
Amounts
Remaining
63,740.00
27,256.00
90,996.00 2,876,400.00 2,785,404.00
11,250.00
5,207.50
16,457.50
435,000.00
418,542.50
74,990.00
32,463.50 107,453.50 3,311,400.00 3,203,946.50
0.00 331,140.00 331,140.00
331,140.00
0.00
Advance
Payment
e
Repayment of
0.00
0.00
0.00 -331,140.00 -331,140.00
Advance
f=c+d+e Total (gross)
363,603.5 438,593.50 3,311,400.00 2,872,806.50
74,990.00
g=0.05*c Retention(5%)
1,623.18
5,372.68 If applicable
3,749.50
h=f-g
Total (net)
71,240.50 361,980.32 433,220.82
Fees and Direct Costs for the period ending 29 February 2004: Currency 71,240.50
(Currency seventy-one thousand, two hundred, forty and 50/100)
Payment should be made within 56 days (i.e. by 5 May 2004) to our account:
Name of Account Holder:
IBAN (International Identification):
Bank Name /Address
Bank Code:
Branch Code:
Account No.:
Control Key:
Swift:
.......
..
..
..
..
..
Yours faithfully,
Name
Project Manager
The Louis Berger Group, Inc.
cc: VP responsible
cc: Head Office Administrator
Project Management Guidelines
Attachments:
Contract financial status (no.of pages)
Summary Sheets (no.of pages)
Support documents (no.of pages)
Appendix D
1 of 2
EXAMPLE
OF BACK-UP TO
CLIENT INVOICE
Sat
1
A.1.1 Expatriate Staff:
Resident Engineer
Name
A.1.1 Local Staff
Deputy Resident Engineer
Name
Quantity Surveyor
Name
Materials Engineer
Name
Land Surveyor
Name
Inspectors
Name
A.1.2 ALLOWANCES:
Long-term Expatriate Staff:
Accommodation outside (Main City )
Name
B. DIRECT COSTS:
Bilingual Secretaries
Name
Sun Mon
Fri
Sat
Sun Mon
10
Fri
Sat
Sun Mon
Fri
Sat
Sun Mon
Fri
Sat
11
14
15
16
18
21
22
23
25
28
29
12
13
17
19
20
24
26
27
month
month
month
month
month
1
A.1.1 Expatriate Staff:
Resident Engineer
Name
A.1.1 Local Staff
Deputy Resident Engineer
Name
month
month
A.1.2 ALLOWANCES:
Long-term Expatriate Staff:
Accommodation outside (Main City )
Name
month
B. DIRECT COSTS:
Return Airfares (Expatriates)
Name
Mobilization /Demobilization Allowance
Name
Sun Mon
Fri
Sat
Sun Mon
10
Fri
Sat
Sun Mon
Fri
Sat
Sun Mon
Fri
Sat
11
14
15
16
18
21
22
23
25
28
29
12
13
17
19
20
24
26
27
No.
No.
Work Day
Air Flight IN
M
Mobilization
M
Demobilization
H
Public Holiday
R
Report Submitted
Name / Title
Date:
Date:
Appendix D
2 of 2
Appendix E
DOCUMENT CONTROL /
PROJECT FILING SYSTEM
Referenced in:
Section I-3.7: Document Control / Project Filing System
EXAMPLE
Content
FILE DESCRIPTION
1.1
1.2
OUTGOING
INCOMING
2.1
2.2
2.3
2.4
SUBJECTS:
2.4
LB PROPOSAL
2.5
CONTRACT DOCUMENTS:
2.5.1
Contract Documents
2.5.2
Contract Changes & Addenda
2.5.3
Contract Clarifications / Protocols
2.5.4
Funding Agreement
2.5.5
Funding Agency Guidelines
2.6
APPROVALS OF STAFF
2.7
2.7.1
2.7.2
27
2.7
2.8
2.8.1
2.9
2.9.1
2.9.2
2 10
2.10
2.12
BUDGET STATUS
2.13
2 13
COST ESTIMATES
2.14.1
2.14.2
2.14.3
2.14.4
2.15
2.15.1
2.15.2
2.15.3
2.15
2.16
2.16
Non-reimbursable Staff
2.11
2.14
g
Service Contract documents.
The original
APPROVALS OF SUB-CONSULTANTS:
Name
Name
(as necessary )
PROCUREMENT:
Vehicles
Office Equipment
Other Equipment
TIMESHEETS:
Reimbursable Staff
REIMBURSABLE EXPENDITURES:
Living Allowances
Per Diems
Air Travel
Other Travel
CLIENT INVOICES
2.10.1
2.10.2
2.10.3
2.10.4
PUBLICITY:
General
Brochures
Press Releases
Newspaper Articles
LBG REPORTS:
Inception Report
Progress Reports
Contract Completion Report
(Further sub-divisions for other reports )
REPORTS BY OTHERS
(Sub-divisions for such reports as precontract feasibility studies, environmental
assessment and monitoring, grotechnical
investigations, etc. )
3.1
3.2
OUTGOING CORRESPONDENCE
INCOMING CORRESPONDENCE
Appendix E
1 of 3
3.3
3.3.1
3.3.2
3.3.3
LB STAFF:
CVs
Employment Agreements
Staff Records for Emergency
Vacation Planning
POWERS OF ATTORNEY
PROJECT BANKING:
3.5.1
General
3.5.2
Bank Statements
LB MONEY TRANSFERS:
3.6.1
LB Head Office transfers to Project
(as required )
3.6.
MONTHLY ACCOUNTS:
3.7.1
Monthly Account Reports
3.7.2
Staff Allowances & Per Diems
3.7.3
Staff Expense Reports /Payments
3.7.4
Site Office No.1 Cash /Accounts
3.7.5
Site Office No.2 Cash /Accounts
3.3.4
3.4
3.5
3.6
3.7
SUBCONSULTANTS (CONFIDENTIAL)
4.1
SUB-CONSULTANT
S
CO S
No.1 (Name
(
)
):
Outgoing Correspondence
Incoming Correspondence
Subconsultancy Agreement & Addenda
CVs
Staff Interviews/Selection
Staff Approvals
4.1.1
4.1.2
4.1.3
4.1.4
4.1.5
4.1.6
4.1.7
4.1.8
4.2
4.3
Timesheets
Subconsultant's Invoices /Approvals
SUB-CONSULTANT No.2 (Name ):
(Sub-files as above )
4.2..
SUB-CONSULTANT No.3 (Name ):
(Sub-files as above )
4.3..
5.1
OUTGOING CORRESPONDENCE
5.2
INCOMING CORRESPONDENCE
5.3
5.3.1
5
31
5.3.2
5.3.3
SUBJECTS:
5.4
5.4.1
5.4.2
5.4.3
5.5
5.5.1
5.5.2
5.5.3
5.6
5.6.1
5.6.2
5.6.3
5.7
5.8
5.8.1
5.8.2
5.8.3
59
5.9
5.10
5.11
5.11.1
5.11.2
5.12
5.12.1
5.12.2
5.12.3
5.12.4
5.12.5
MINUTES OF MEETINGS
Monthly Progress Meetings
Regular Site Meetings
Subject Meetings
PRE-CONTRACT:
Tender Process
Tender Evaluation
Pre-Contract negotiations
WORKS CONTRACT DOCUMENTS:
General
Works Contract Addenda
Other Agreements & Protocols
SECURITIES:
Performance Bond
Guarantee for Advance Payment
Guarantee for Retention Money
INSURANCE
ENGINEER'S FACILITIES:
Project Office
Site Office
Vehicles
WORKS PROGRAMME & CASH FLOW
QUALITY ASSURANCE /QUALITY CONTROL
UNIT PRICES & LUMP SUMS:
Breakdowns of UPs & LSs
Rates /Prices for New Work Items
If relevant.
EMPLOYER RESPONSIBILITIES:
Tax & Customs Exemptions
Price Adjustment Indices
Applicable Law
Possession of Site
Construction License /Statutory Approvals
Appendix E
2 of 3
5.13
5.14
5.15
5.16
5.17
5.18
CONTRACTOR'S SUPERINTENDENCE:
5.13.1 Organization
5.13.2 Representative /Personnel
CONTRACTOR'S LABOUR & EQUIPMENT:
5.14 (Sub-divisions as necessary )
TECHNICAL INFORMATION /SUBMISSIONS:
5.15 (Sub-divisions as necessary )
CONTRACTOR'S REPORTS:
5.16.1
Monthly Progress Reports & Labour/Plant
Returns
5.16.2
Contractor's
Contractor
s Progress Photographs
5.16.3
Meteorological Records
HEALTH & SAFETY:
5.17.1 Safety & Accident Reports
5.17.2 Traffic Management
SUBCONTRACTORS
VARIATIONS:
Variation Instructed
Variation Orders Pending
Variation Orders Issued
5 20
5.20
SUSPENSIONS OF WORKS:
5.20.1
Suspensions by Contractor
5.20.2
Suspensions by Engineer/Employer
5.21
CONTRACTOR'S CLAIMS
File by month.
File by month.
File by month.
5.19
5.19.1
5.19.2
5.19.3
5.22
5.22.1
5.22.2
5.22.3
5 22 4
5.22.4
5.22.5
5.22.6
5.23
5.24
File by VO No.
Correspondence & detailed records. File by event.
File by Claim Number. Separate file for each Claim
including Notice of Claim, Particulars of Claim,
contemporary records, Engineer's assessment &
determination, notices of Dispute, Dispute Resolution.
PAYMENT CERTIFICATIONS:
Contractor's Interim Statements
Engineer's Interim Certificates
Contractor's Statement at Completion
E i
Engineer's
' Certificate
C ifi
at Completion
C
l i
Contractor's Final Statement
Engineer's Final Certificate
ENGINEER'S INSTRUCTIONS
DEFECTS NOTICES
IF PROJECT & SITE OFFICES SEPARATE, FOLLOWING FILES COULD BE KEPT AT SITE OFFICE ONLY:
5.25
5.26
5.27
5 28
5.28
5.28.1
5.28.2
5.28.3
5.28.4
5.28.5
5.28.6
5.28.7
5.28
5.29
5.29.1
5.29.2
5.29.3
5.29.4
5.29.5
5.29.6
5.29
5.30
5.31
Appendix E
3 of 3
Appendix F
PROJECT PROGRESS REPORTS
Referenced in:
Section I-3.8: Project Reports
Section II-3.5: Variation Orders
II-3.14: Records of Statements, Certifications & Payments
II-3.17: Monitoring & Reporting Works Progress
EXAMPLE
FOR PROGRESS
REPORTS
Name of Contractor
IPC No.
Period Ending
Date
Engineer's Certification
Date Issued
Amount
Date Due
Employer's Payment
Amount
Date Paid
1/1
1/2
1/3
Total
Name of Contractor
IPC No.
Period Ending
Date
Engineer's Certification
Date Issued
Amount
Date Due
Employer's Payment
Amount
Date Paid
2/1
2/2
2/3
Total
Construction Supervisor
Summary of Invoices
(Currency )
Name
Invoice
No.
XXX/1
XXX/2
XXX/3
Period Ending
Date
LB Invoice
Date Issued
Amount
Date Due
Client's Payment
Amount
Date Paid
Total
Supervision
Name
C
Total
A+B+C
Explanatory footnotes:
Appendix F
1 of 1
Appendix G
CONSTRUCTION COMPLETION
REPORT
Referenced in:
Section I-3.8: Progress Reports
Section II-6.5: Interim Payment Certificate at Completion
EXAMPLE
Bill
No.
Description
1
2
3
4
5
General Items
Site Clearance
Earthworks
10
Dayworks
Sub-total 1
Provisional Sum for Contingency
Retention
Return of Retention
Sub-total 2
Price Adjustment (Rise & Fall of Costs)
Price Adjustment (Change in Law)
Agreed Settlements, Claims, etc. (itemize)
Prolongation Costs during Extension of Time
Interest for Late Payments
Provisional Deductions
Final Deductions
Provision for outstanding Claims & Disputes
VAT
Contract Price / Estimated Final Cost
Contract
Amounts
N.A.
N.A.
N.A.
Contractor's
Statement
at Completion
Total
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
Appendix G
1 of 1
Appendix H
PREAMBLES TO
BILLS OF QUANTITIES
OF WORKS CONTRACT
Referenced in:
Section II-1.3: Works Contract Documents Sufficiency & Discrepancies
Section II-3.1: Bill of Quantities & Unit Prices
Section II-3.8: Measurement of Works
Measurement
EXAMPLE
(ii)
(iii)
(iv)
(v)
Temporary Works.
(vi)
(vii)
(viii)
(ix)
Waste.
(x)
(xi)
(xii)
Appendix H
1 of 7
Quantity of Items
The quantities set forth against the Items in each bill are an estimate of
the quantity of each kind of the work included in the Contract and are
given for the convenience of forming a common basis for bids. There is
no guarantee to the Contractor that he will be required to carry out the
quantities of work indicated under any one particular item in the Bill of
Quantities or that the quantities will not differ in magnitude from those
stated in the Bills.
The brief descriptions of items given in the Bill of Quantities are purely for
the purpose of identification and it shall in no way modify or supersede
the detailed description given in the Conditions of Contract or
Specifications. When pricing items, reference should be made to the
Conditions of Contract, Specifications and relevant Drawings for full
directions and descriptions of work and materials involved.
The quantities given in the Bill of Quantities are provisional, as estimated
on the basis of the Plans for Approval, which have been taken as a basis
for the Tender Documents and are given to provide a common basis for
Tendering. The Tenderers shall consider carefully all items and duties in
the Tender Documentation in order to prepare their tenders, being aware
of their responsibilities under the Contract. Accordingly, the quantities
entered against the various items shall be verified.
Comments, if any, concerning the quantities shall be made in the form of
an attachment, following the system of itemisation, quoting the codes and
brief descriptions, as in the present documents, including the rates and
prices.
Except where specifically and expressly otherwise stated in the Technical
Specification or in the Bill of Quantities, the Permanent Works only shall
be measured. The works shall be measured net to the dimensions
shown on the Drawings or ordered in writing by the Engineer, except
where otherwise specifically described or prescribed in the Contract.
In adjusting extras or variations on the Contract, the work shall be
measured on the same basis as that for which the quantities have been
prepared and all works not specifically mentioned in the Bill of Quantities
will be taken as included in the prices of various items valued. The
Contractor, if so directed by the Engineer, shall carry out the work at
daywork rates which shall be the rates shown in the Schedule of
Daywork. All completed Daywork Sheets must be signed by the
Engineer on or before the end of the week in which the work is executed.
No allowance will be made for loss of materials or volume thereof during
transport or compaction.
Units of
Measurement
The calculation units used are the same as specified and allowed in the
International System of Units (SI) and used in the Technical
Documentation herein. No other but the units used in the Technical
Documentation shall be used in measurements, pricing, detail drawings
etc. (Any units not used in the Technical Documentation shall also be
expressed in terms of the SI).
Appendix H
2 of 7
shall mean
shall mean
shall mean
shall mean
shall mean
shall mean
shall mean
shall mean
shall mean
shall mean
shall mean
shall mean
shall mean
shall mean
shall mean
shall mean
shall mean
millimetre
centimetre
metre
square millimetre
square centimetre
square metre
cubic metre
hectare
kilogram
metric tonne (1000 kg)
number
hour
week
calendar month
average
lump sum
provisional sum
Terms in Connection
with Payment
Each individual item shall have a rate or price entered against it. Rates
and prices shall be expressed in (currency) to two decimal places.
The rates and prices tendered in the priced Bill of Quantities shall be
quoted at the rates current prior to the date of submission, with due
consideration to the changes in price as anticipated up to the time of
completing the Works.
The rates shall be fixed, and shall not be subject to any change during the
contract period. The items in the priced Bill of Quantities shall cover the
total sum of compliance with the Contract. The prices for the items in
each Bill shall be summarised at the place designated for the purpose in
the Instructions to Tenderers. The price sums shall be stated and in the
Summary of the Priced Bill of Quantities.
The price for the Works shall be presented in compliance with those
stated in the Summary of the Priced Bill of Quantities.
Appendix H
3 of 7
The price for jobs not provided for in separate items shall be deemed to
be distributed among the rates and prices entered for the other items of
work. E.g., the price for the preparatory building, technological plant or
other temporary facilities, (such as offices, workers lodgings, amenities or
health service buildings, stores, workshops etc, including all internal
equipment, internal and external public utilities, heating, maintenance,
charges for the use of current, sewerage or water, and all other
expenses).
The Contractors costs of administration, planning, scheduling and coordination of works undertaken by others under Provision Sums will be
deemed to be distributed among the rates and prices entered for the
other items of work, and the Contractor will not be entitled to any mark-up
on the cost of works by others.
The rates and prices shall include, but not be limited to, labour, transport,
quality testing and inspection, materials, the provision, maintenance of all
temporary works of every description and the performance of all services
which may be required for the proper execution, completion and
contractual maintenance of the Works, including insurance, profit, and all
general risk, liabilities in full, completely in accordance with the provisions
of the Contract, and the undertaking of all obligations and responsibilities
therein defined.
The price for the Temporary Works shall be stated by considering that the
materials to be incorporated will fully revert to the Contractor.
The Bidder shall allow in his rates for all preliminary and general items
including temporary diversions and safe passage of traffic, traffic signs
and compliance with all other clauses of the Specifications and
Conditions of Contract which he may feel are not adequately covered
elsewhere in the Bill of Quantities.
Daywork
Labour
Rates entered in the Bill of Quantities for daywork rates labour shall
include all Contractors profit, supervision, insurances, overhead
expenses, transport to the Site of Works and all other costs incurred in
complying with the Contract.
The Contractor shall not be paid for any work at daywork rates unless the
written approval of the Engineer has been obtained prior to such work
being carried out.
Only time engaged in actual work will be allowed. All rates quoted for
daywork should bear reasonable relation to the rates given elsewhere in
the Bill of Quantities and will be considered in conjunction therewith.
Rates shall include for provisions of ordinary hand tools: shovels, brooms,
wheelbarrows, pickaxes, etc.
Appendix H
4 of 7
Use of Alternative
Specified Materials
or Designs
Appendix H
5 of 7
Privately and
Publicly Owned
Services or Supplies
Labour
Roadworks Overall
Requirements
The Contractor shall allow in his rates and prices for complying with
requirements in respect of Pavement Construction, Horizontal
Alignments, Surface Levels and Surface Regularity of Pavement
Courses, Cold Weather Working, Use of Surfaces by Traffic and
Construction Plant, and General Requirements for Sub-Bases and Road
Bases.
The Contractor shall allow in his rates and prices for taking measures
required to execute the work separately measured as being within and
below non-tidal open water or tidal water. For the measurement of work
affected by non-tidal open water or tidal water the datum stated in the
Contract shall be used irrespective of the actual level of water
encountered in the Works.
The Contractor shall allow in his rates and prices for taking measures to
deal with the existing flow of water, sewage and the like.
10
The Contractor shall allow in his rates and prices for complying with
any limitations and constraints on the use of the Site.
Equivalent Product
and Materials
11
Appendix H
6 of 7
Appendix H
7 of 7
Appendix I
METHOD OF MEASUREMENT
Referenced in:
Section II-1.3: Works Contract Documents Sufficiency & Discrepancies
Section II-3.1: Bill of Quantities & Unit Prices
Section II-3.8: Measurement of Works
EXAMPLES
METHOD OF MEASUREMENT
SECTION 1: GENERAL ITEMS
Temporary Facilities:
Units
The units of measurement shall be: Item, number, lump sum, month
or provisional sum (as noted in the Bill of Quantities).
Provision of
Temporary Offices and
Laboratories for the
Engineer
Item coverage
(i)
(ii)
(b)
(c)
preparation of sites;
(d)
(e)
(f)
(g)
(h)
(i)
Appendix I
1 of 20
(d)
Payment
Servicing and
Maintenance of
Temporary Offices and
Laboratories for the
Engineer
Item coverage
(b)
(i)
Mobilization and
Demobilization of
Temporary Site
facilities for Contractor
Item coverage
Payment
The item for mobilization and demobilization of site facilities for the
Contractor shall in accordance with the Preambles to Bill of
Quantities, General Directions, including:
(i)
(ii)
Appendix I
2 of 20
Item coverage
Equipment
(b)
(c)
Measurement
10
The items for vehicles for the Engineer shall in accordance with the
preamble to Bill of Quantities, General Directions, including:
(d)
equipment;
(e)
taxing for use on public highways and for the carriage of goods
and samples;
(f)
comprehensive insurance;
(g)
(h)
depreciation;
(i)
(j)
(k)
(l)
Appendix I
3 of 20
11
12
Cost of Telephone
Calls and
Communications of the
Engineer
Item coverage
(a)
13
Measurement
14
15
The items for operatives for the Engineer shall in accordance with
the preamble to Bill of Quantities, General Directions, including:
Item coverage
(a)
(b)
(c)
(d)
Publicity:
Units
16
Information Material
17
Item coverage
18
Appendix I
4 of 20
19
Item coverage
Maintenance of
Measures for or
Construction of
Temporary Diversion
for Traffic
20
Item coverage
Removal of Measures
for or Construction of
Temporary Diversion
for Traffic
21
Item coverage
(a)
(b)
(c)
(d)
(e)
preparation of site;
(f)
(g)
(a)
(b)
modifications.
(a)
breaking up diversion;
(b)
(c)
22
23
Appendix I
5 of 20
Item coverage
(a)
(b)
(c)
(d)
(e)
(f)
(g)
(h)
Etcetera
SECTION 3: EARTHWORKS
EXAMPLES
Earthworks Outline:
Definitions
(b)
(c)
(d)
(e)
Appendix I
6 of 20
In all cases of filter drains the Earthworks Outline shall be the top of
the filter material.
Measurement General
Sub-Soil Level is defined as the level of the ground after the removal
of topsoil required by the Contract.
10
For the purpose of this Section it shall be assumed that one cubic
metre of material excavated forms one cubic metre of compacted fill.
No allowance shall be made in the measurement for bulking and
shrinkage of any material.
11
12
Appendix I
7 of 20
(a)
(b)
In the case of landscape areas, noise bunds and other areas of fill
where settlement or penetration occurs the additional fill deposition
and compaction required shall not be measured.
Excavation:
Units
13
Measurement
14
(b)
or
(ii) under embankments, and other areas of fill - the volume of
the void formed under the excavation of material below
Existing Ground Level;
less in each case the volume of topsoil in the void included in
the measurement under Paragraph 14(a).
(c)
(d)
Appendix I
8 of 20
(i)
Excavation of
Acceptable Topsoil
Material
15
Item coverage
(f)
(g)
(b)
(c)
Appendix I
9 of 20
Excavation of
Acceptable Material
Excluding Topsoil
16
Item coverage
(d)
(e)
(f)
(b)
(c)
(d)
(e)
(f)
(g)
(h)
(i)
(j)
protection or sub-grade;
(k)
(l)
(n)
(o)
(p)
(q)
(r)
Appendix I
10 of 20
Excavation of
Unacceptable Material
17
Item coverage
(s)
(t)
(u)
(b)
18
Measurement
19
20
Item coverage
(a)
(b)
(c)
(d)
(e)
Deposition of Fill:
Units
21
Measurement
22
23
24
Deposition of Fill
Appendix I
11 of 20
Item coverage
(a)
(b)
haulage;
(c)
(d)
(e)
(f)
(g)
(h)
(i)
Disposal of Material:
Units
25
Measurement
26
27
28
Disposal of Material
Item coverage
(a)
(b)
(c)
Appendix I
12 of 20
(d)
Imported Fill:
Units
29
Measurement
30
Imported Fill
(a)
(b)
31
32
33
The items for imported fill shall in accordance with the Preambles to
Bill of Quantities, General Directions, including:
Item coverage
(a)
(b)
(c)
(d)
(e)
(f)
(g)
(h)
Appendix I
13 of 20
Compaction of Fill:
Units
34
Measurement
35
(b)
(c)
(i)
(ii)
37
fill to structures,
(b)
(c)
(d)
(e)
in each case, shall be the volume of the void filled to the outline
stated in the Contract less the volume of corrugated steel structures
and the like within that void.
Appendix I
14 of 20
Compaction of Fill
38
39
Item coverage
(a)
(b)
(c)
(d)
(e)
(f)
(g)
(h)
(i)
(j)
(k)
(l)
Etcetera
SECTION 4: PAVEMENTS
EXAMPLES
Sub-Base:
Units
Appendix I
15 of 20
Measurement
Sub-Base
Item coverage
(a)
(b)
(c)
(d)
(e)
(f)
(g)
(h)
(i)
edge support;
(j)
maintenance of surface;
(k)
(l)
taking measures to improve the sub-base to protect the subbase and sub-grade from damage due to the Contractors
method of construction and choice of constructional plant;
Pavement:
Units
Measurement
Appendix I
16 of 20
Note: The width of the top surface of the course or slab shall be
the width required by the Contract and shall exclude sloping sides or
edges.
No deductions shall be made for openings of 1 square metre or less.
Bituminous Base,
Binder Course,
Wearing Course
Item coverage
The items for bituminous base, binder course, wearing course shall
in accordance with the Preambles to Bill of Quantities, General
Directions, including:
(a)
(b)
(c)
(d)
(e)
designing mixes;
(f)
(g)
(h)
(i)
edge support;
(j)
(k)
surface texturing;
(l)
making joints;
(n)
(o)
(p)
(q)
maintenance of surface;
(r)
(s)
Appendix I
17 of 20
Measurement
(ii)
Bituminous and
Cement Bound
Profiling and Levelling
Courses
10
11
The items for bituminous and cement bound profiling and levelling
courses shall in accordance with the Preambles to Bill of Quantities,
General Directions, including:
Item coverage
(a)
(b)
(c)
Surface Treatment:
Units
12
Measurement
13
14
Appendix I
18 of 20
Surface Treatment
15
Item coverage
(b)
(c)
(d)
designing mixes;
(e)
(f)
(g)
making joints;
(h)
cleaning surfaces;
(i)
(j)
(k)
(l)
(o)
16
Measurement
17
Appendix I
19 of 20
18
Item coverage
The items for scarifying, planing (or milling) and burning off shall in
accordance with the Preambles to Bill of Quantities, General
Directions, including:
(a)
(b)
(c)
(d)
(e)
(f)
Etcetera
Appendix I
20 of 20
Appendix J
QUALITY CONTROL FORMS
Referenced in:
Section II-2.12: Quality Assurance & Control
Section II-3.7: Daywork
Section II-4.1: Engineers Instructions
Section II-4.6: Works Inspection, Testing & Acceptance
Section II-4.7: Unacceptable Works, Defects Notifications & Remedies
Contractor:
Engineer:
Contract:
Name
The Louis Berger Group, Inc.
Name
REQUEST FOR
SURVEYING OR TESTING
Submitted by Contractor (Signature)
EXAMPLE
Date
Time
Date
Time
Date
Time
Date
Time
(Name)
(Signature)
Received by Engineer
(Name)
Contractor's Request:
Engineer's Response:
ACCEPTED
Resident Engineer
(Signature)
(Name)
Comment:
NOT ACCEPTABLE
Resident Engineer
(Signature)
(Name)
Reasons:
Appendix J
1 of 8
Contractor: Name
Engineer: The Louis Berger Group, Inc.
Contract: Name
REQUEST FOR INSPECTION
EARTHWORKS AND ROAD SUBBASE
EXAMPLE
In accordance with Clause (State) of the Conditions of Contract, the Contractor gives notice that the
following work has been constructed in accordance with the Contract requirements and is available
for inspection:
Submitted by Contractor (Signature)
Date
Time
Received by Engineer
Date
Time
Location:
(Signature)
from km
to km
LHS
RHS
Type of Work
1. Road Sub-grade
2. Embankments
3. Excavation
4. Shoulders
5. Road Widening
6. Sub-base
7. Topsoil
8. Rockfill
9. Geotextile
2. Drawing No.
Comments
Signature
Inspection Points:
1. Inspector:
Compaction
Dimension
Layer thickness
Comments
2. Surveyor:
Signature
Alignment
Levels
Comments
3. Laboratory:
Signature
Sampling
Testing
Comments
ACCEPTED
RESIDENT ENGINEER
Slopes
Signature
NAME:
DATE:
NAME:
DATE:
NOT ACCEPTABLE
Reason
Action
RESIDENT ENGINEER
Project Management Guidelines
Appendix J
2 of 8
Contractor: Name
Engineer: The Louis Berger Group, Inc.
Contract: Name
EXAMPLE
STRUCTURES
In accordance with Clause (State) of the Conditions of Contract, the Contractor gives notice that the following
work has been constructed in accordance with the Contract requirements and is available for inspection:
Submitted by Contractor (Signature)
Date
Time
Received by Engineer
Date
Time
Structure:
Bridge
Location:
from km
Type of Work
(Signature)
Box Culvert
Arch Culvert
Retaining Wall
to km
LHS
I. Reconstruction
II. Repair
RHS
III. Demolition
1. Piles
2. Foundations
3. Abutments
4. Wing Walls
5. Piers
6. Cross Head
7. Bridge Bearings
8. Main Beams
9. Deck Slab
13. Waterproofing
14. Guardrails
2. Drawing No.
Signature
Inspection Points:
1. Inspector:
Formwork
Fixing
Dimensions
Stability
Reinforcement
Fixing
Dimensions
Concrete cover
Concrete Class
Placing
Compaction
Finish
Ironwork Fixing
Expansion Joints
Waterproofing
Comments
2. Surveyor:
Signature
Alignment
Levels
Comments
3. Laboratory:
Signature
Sampling
Comments
ACCEPTED
RESIDENT ENGINEER
Railings
Signature
NAME:
DATE:
NAME:
DATE:
NOT ACCEPTABLE
Reason
Action
RESIDENT ENGINEER
Appendix J
3 of 8
Contractor: Name
Engineer: The Louis Berger Group, Inc.
Contract: Name
EXAMPLE
ASPHALT PAVEMENT
In accordance with Clause (State) of the Conditions of Contract, the Contractor gives notice that the following
work has been constructed in accordance with the Contract requirements and is available for inspection:
Submitted by Contractor (Signature)
Date
Time
Received by Engineer
(Signature)
Date
Time
Asphalt Work
(Please Tick)
Levelling
Course
Location: from km
Binder
Course
to km
Type of Work
Wearing
Course
Position
Lane
3. Cutting of Joints
5. Setting Out
6. Cold milling
Comments:
mm ex
Plant
Signature
Inspection Points
1. Cleanliness of area to be paved
3. Condition of Cut Joints
5. Setting Out
Inspectors Remarks
6. Surveyor:
Signature
7. Laboratory:
Signature
levels
Comments:
Sampling
Comments:
ACCEPTED
RESIDENT ENGINEER
Signature
NAME:
DATE:
NAME:
DATE:
NOT ACCEPTABLE
Reason
Action
RESIDENT ENGINEER
Appendix J
4 of 8
Contractor: Name
Engineer: The Louis Berger Group, Inc.
Contract: Name
EXAMPLE
DRAINAGE
In accordance with Clause (State) of the Conditions of Contract, the Contractor gives notice that the following
work has been constructed in accordance with the Contract requirements and is available for inspection:
Submitted by Contractor (Signature)
Date
Time
Received by Engineer
Date
Time
Location:
(Signature)
form km
to km
LHS
RHS
2. Piped Culverts
3. Lined Ditch
5. Italian Chutes
6. Headwalls
Type of Work
2. Drawing No.
Comments
Signature
Inspection Points:
1. Inspector:
Formation
Concrete Foundation
Layer thickness
Reinforcement
Pipe laying
Precast Units
Ironwork Fixing
Backfilling
Signature
Comments
2. Surveyor:
Alignment
Levels
Comments
3. Laboratory:
Signature
Sampling
Testing
Comments
ACCEPTED
RESIDENT ENGINEER
Signature
NAME:
DATE:
NAME:
DATE:
NOT ACCEPTABLE
Reason
Action
RESIDENT ENGINEER
Appendix J
5 of 8
Contractor: Name
Engineer: The Louis Berger Group, Inc.
Contract: Name
EXAMPLE
Labour
Item
Name
Description
Unit
Rate
(Currency)
Quantity
Amount
(Currency)
SUBTOTAL:
Equipment
Item
Description
Unit
Rate
(Currency)
Quantity
Amount
(Currency)
SUBTOTAL:
Materials
Item
Description
Unit
Rate
(Currency)
Quantity
Amount
(Currency)
SUBTOTAL:
TOTAL:
Submitted by the Contractor:
..................................................
..
Name ........................Date Name Date .........
Project Manager
Resident Engineer
Appendix J
6 of 8
Contractor: Name
Engineer: The Louis Berger Group, Inc.
Contract: Name
DAYWORKS
APPROVALS OF MATERIALS / PRICES
(In accordance with Clause of the Conditions of Contract)
EXAMPLE
BoQ Item
(if any)
Quotation Ref.
Unit
Amount
(Currency)
.....................................
Name ........................Date
Project Manager
..
Name Date ..........
Resident Engineer
Appendix J
7 of 8
Contractor: Name
Engineer: The Louis Berger Group, Inc.
Contract: Name
EXAMPLE
LOCATION:
In accordance with Clause .. of the Conditions of the Contract, you are notified that the
following works have not been performed in accordance with Technical Specifications or
Drawings:
Description of Defective Plant, Materials or Works:
In accordance with Sub-Clause .. you are required to correct the above defects as
aforesaid, or to propose an alternative solution for which the Engineers prior
consent is necessary.
Time Constraints for remedial actions:
............................................
Signature
Date
.............................................
Signature
Date
Appendix J
8 of 8
Appendix K
DAILY DIARY FORMS
& EVENTS LOG
Referenced in:
Section II-2.26: Diaries & Events Log
Contract:
Name
Engineer: The Louis Berger Group, Inc.
Contractor: Name
EXAMPLE
Date: ..
Weather
Rainfall
Temp. [oC]
Effect on Programme
Slow-down [%]
Time
Fog
AM
MID
PM
Brief description of days operation
No.
Staff / Labour
Foreman
Skilled
Unskilled
Plant operator
Surveyor
Lab. technician
Location
Km + .. Km . + .
Km + .. Km . + .
Km + .. Km . + .
Km + .. Km . + .
Km + .. Km . + .
Work
Equipment
Quantity
Working hours
Signed ________________________
RE reviewed
Appendix K
______________________
1 of 2
Contractor:
Engineer:
Contract:
Name
The Louis Berger Group. Inc.
Name
EXAMPLE
Comment
ETC.
Appendix K
2 of 2
Appendix L
VARIATIONS
Referenced in:
Section II-3.4: Valuation of Variations
Section II-3.5: Variation Orders
Section II-3.16: Works Quantities Management
Section II-3.17: Monitoring & Reporting Works Progress
EXAMPLE 4
EXAMPLE 3
EXAMPLE 2
EXAMPLE 1
Item
3103
3104
Description
EARTHWORKS:
Topsoiling 150mm thick to surfaces
sloping 10o
Topsoiling 150mm thick to surfaces
sloping > 10o
PAVEMENT:
Profiling and levelling material, binder
grade, in carriageway and hardstrip
Profiling and levelling material, binder
grade, in carriageway and hardstrip 4511.1
> 110% of original quantity. Varied Rate
pursuant to Cl.
4511
DRAINAGE:
Manhole Type 1, finished depth to invert
not exceeding 2m.
Manhole Type 1, finished depth to invert
5104.1 not exceeding 2m. Varied Rate for
quantity increase pursuant to Cl.
5104
6202
6203
STRUCTURES
In-situ Class B25 concrete in walls and
columns
In-situ Class B35 concrete in walls and
columns
FENCING, SIGNS, MARKINGS
Pedestrian guard rails
ORIGINAL CONTRACT
Amount
(currency)
VARIATIONS
Estimated
Quantity
Amount
(currency)
REVISED CONTRACT
Estimated
Quantity
Amount
(currency)
EXAMPLES
Certified to Date
Amount
(currency)
Previously Certified
% of
Revised
Contract
Amount
(currency)
This Payment
Amount
(currency)
Unit
Rate
(currency)
m2
9.75
2,000
19,500.00
-1,000
-9,750.00
1,000
9,750.00
500
4,875.00
50%
300
2,925.00
200
1,950.00
m2
10.50
0.00
1,200
12,600.00
1,200
12,600.00
200
2,100.00
17%
0.00
200
2,100.00
30.00
50,000 1,500,000.00
5,000
150,000.00
55,000 1,650,000.00
55,000 1,650,000.00
100%
0.00
45.00
0.00
15,000
675,000.00
15,000
675,000.00
12,500
562,500.00
83%
83%
5,000
225,000.00
7,500
337,500.00
no
2,500.00
2,500.00
-1
-2,500.00
0.00
0.00
2,500.00
-1
-2,500.00
no
1,500.00
0.00
20
30,000.00
20
30,000.00
9,000.00
30%
0.00
9,000.00
m3
100.00
300
30,000.00
-100
-10,000.00
200
20,000.00
120
12,000.00
60%
80
8,000.00
40
4,000.00
m3
120.00
0.00
200
24,000.00
200
24,000.00
70
8,400.00
35%
0.00
70
8,400.00
12.00
500
6,000.00
500
6,000.00
420
5,040.00
84%
84%
300
3,600.00
120
1,440.00
Quantity
Quantity
Quantity
Quantity
55,000 1,650,000.00
EXAMPLE 1: Item 3103 is an original BoQ item for topsoiling slopes 10o. A requirement arises for topsoiling slopes > 10o for which there was no original BoQ provision. A Rate for the new work is negotiated based on the
o
original Rate of Item 3103 but with consideration of the increased difficulty of topsoiling slopes > 10 . A new BoQ Item 3104 with new 'Description', estimated 'Quantity' and new 'Rate' is established by Variation
for the additional works. The corresponding estimated quantity reduction of Item 3103 is included in the same Variation.
EXAMPLE 2: Item 4511 is an original BoQ item for profiling/levelling asphalt. There is no provision in the Contract for Price Adjustment arising from the rise or fall of Materials. There is Contract provision for price adjustment
arising from significant increase or decrease of executed quantities (>10% of original BoQ quantities). Market forces have driven up the cost of bitumen and, therefore, the cost of profiling/levelling asphalt. A
new Rate is negotiated based on the original Rate of Item 4511 but with consideration of the higher cost of bitumen prevailing from the time that 110% of the original BoQ quantity was exceeded. By Variation
the quantity of Item 4511 is raised by 10% (at the original BoQ rate), and a new Item 4511.1 with new Rate is established for quantity exceeding 110% of original BoQ Item 4511.
EXAMPLE 3: Item 5104 is an original BoQ item for a single Type 1 manhole. There arises a requirement for a total quantity of 20 Type 1 manholes, for which the Engineer considers that the original BoQ rate is
inappropriately high for the increased number now required. A new lower Rate is negotiated based on the original Rate of Item 5104 but with consideration of economy of significantly increased quantity. By
Variation the original Item 5104 is omitted and a new Item 5104.1 is established with the new Quantity and new Rate.
EXAMPLE 4: Item 6202 is an original BoQ item for B25 concrete. For technical reasons it is decided to increase the concrete strength (and therefore the cement content) to B35 for some parts of the Works, for which the
original BoQ has no provision. A rate is negotiated for B35 concrete, based on the rate for Item 6202 with consideration of the required additional cement content. By Variation a new Item 6203 is established
with estimated quantity and agreed rate. By the same Variation the Quantity of Item 6202 is reduced.
NOTES:
>80%
In accordance with the general 'Principles of Valuation of Variations' new or varied rates are to be based, whenever appropriate, on existing rates of the original BoQ. For this purpose the 'Breakdowns of
Lump Sums & Unit Rates' submitted at the beginning of the Contract are relevant.
Prompt for re-estimate of final quantity: When the executed quantity of any BoQ item reaches 80% of its estimated quantity of the Original or Revised Contract (as appropriate), a re-estimate should be
made of the anticipated final quantity for that item. If the re-estimated final quantity varies by more than, say, 5% of the Revised Contract quantity, a Variation should be issued for an adjustment of the Revised
Final Adjustment of Quantities: Upon completion of the Works, if so required by the Employer, a final Variation Order may be issued to reconcile executed quantities with the Revised Contract quantities.
Appendix L
1 of 8
EXAMPLE
Appendix L
2 of 8
(Resident Engineer)
Authorized by:
Issued by:
In this Appendix we present for each Works Contract a summary of Variation Orders
which records, for each VO, the dates of preparation by the Engineer, authorization by
the Employer, and subsequent issue by the Engineer to the Contractor.
The Accepted Contract Amount for each Works Contract contained a Provisional Sum
for Contingency. This Contingency was incorporated as an allowance for unanticipated
site conditions which could necessitate variations to the Works.
Appendix L
3 of 8
If the Works are to be completed within the Accepted Contract Amount, the total value of
all Variations should not exceed the allowance for Contingency. In effect, the value of
each Variation (if it increases the value of Works) depletes the amount of Contingency
available. In order to monitor this status, each Variation Order will record the amount of
Contingency remaining after issuing the subject VO and preceding VOs.
Regarding the Works Progress Synopsis presented in this Progress Report:
This Synopsis includes on two lines the value of:
-
Variation Orders Issued are not entered until they have been authorized by the
Employer and issued to the Contractor.
Variation Orders Pending includes:
The estimated value of other variations which the Engineer foresees but which
cannot yet be itemised or reliably quantified or valued. An example would be a
foreseen requirement for redesign of a part of the Works which will vary the nature
or scope of that work.
Appendix L
4 of 8
EXAMPLE
Name /Title
Reference:
Subject:
Ref.:
Date
po/OUT/205
..
Dear Sirs,
[NOTE: This is an example based on FIDIC Red Book (1999 Ed.) and assumed Particular
Conditions. Text changes needed to suit actual Contract provisions.]
The General Conditions of Contract permit the Engineer to:
- under Cl.13.1, make any Variation of the Works by instruction to the Contractor;
- under Cl.12.3, value Variations including, after due consultation, agreeing or fixing payment rates for
new work items.
Cl.3.1 of the Particular Conditions requires that the Engineer shall:
- obtain the specific approval of the Employer before issuing a Variation under Cl.13.1 of the General
Conditions, except if such variation would increase the *Original Value of Works by less than
(currency) 100,000, or the sum of it and all other approved variations would exceed the *Original
Value of Works by less than 10% [*Original Value of Works = Accepted Contract Amount less
Provisional Sum for Contingency].
- obtain the specific approval of the Employer before agreeing or fixing any rates and prices for varied
works under Cl.12.3 of the General Conditions.
It has been established that all Variations shall be confirmed by Variation Orders.
Given the joint requirements of Cl.3.1, 13.1 and 12.3, it has been established that all Variation Orders
shall be authorized by the Employer before they are issued to the Contractor by the Engineer.
Accordingly we submit herewith this Variation Order for your approval and authorization signature.
For your information, as shown in the attached summary list of Variation Orders:
- Accepted Contract Amount (including Provisional Sum for Contingency) =
- Provisional Sum for Contingency (incl. in Accepted Contract Amount) =
- Total estimated value of approved VOs previously issued =
- Total estimated value of previously issued VOs and this VO =
- Remaining Provisional Sum for Contingency (if any) =
- Estimated Contract Price following this VO =
We request that you sign and return the Variation Order to us; whereupon we will immediately issue it to
the Contractor.
Yours faithfully,
A.N.Other
For The Engineer
The Louis Berger Group, Inc.
Appendix L
5 of 8
EXAMPLE
Description
Example: Asphalt pavement wearing
course in bus lay-byes: Construct with
Dense Bitumen Asphalt, instead of
Splitt Mastic Asphalt specified on
drawings.
References
Contractors letter ref., dated
Engineers letter ref..., dated ,
recommendation to Employer.
Employers letter ref, dated , approval of
recommendation.
Contractors letter ref, dated , submission
of proposed unit payment rates.
Minutes of Meeting on , discussion/
agreement of unit payment rates.
Engineers Instruction No dated
Attachments hereto:
- References described in above table;
- Summary of estimated quantities and costs of Variations;
- (A) Unit payment rate breakdown for new BoQ Item for Dense Bitumen
Wearing Course;
- Explanatory notes and justification.
Prepared by:
Authorized by:
Issued by:
Name
Resident Engineer
Date:
Name
for the Employer
Date:
Name
for the Engineer
Date:
Appendix L
6 of 8
BoQ
Item
Description
Type C
Subtotal:
Unit
Rate
(Currency)
m2
m2
Variation Quantity
Add
Deduct
-()
Variation Cost
(Currency)
-()
+
-()
m
-()
+
TOTAL:
* denotes new BoQ Item and new Rate.
B: .......
Appendix L
7 of 8
EXAMPLE
VO No.
Description
Date of
Submission
by Engineer
Date of
Approval by
Employer
Date of
Issue to
Contractor
Original Value
Adjusted Value
Adjusted Value
Adjusted Value
1/001
1/002
1/003
* Note:
If the Accepted Contract Amount included a Provisional Sum for Contingency, this column would be helpful.
By adding/subtracting the Value of the VO, the remaining Contingency can be monitored.
Appendix L
8 of 8
Appendix M
INTERIM PAYMENT
STATEMENTS & CERTIFICATES
Referenced in:
Section II-3.10: Contractors Interim Payment Statements
Section II-3.11: Interim Payment Certificates
Section II-6.5: Interim Payment Certificate at Completion
EXAMPLE
Name /Title
Ref.:
Date
po/OUT/195
..
Reference:
Subject:
Dear Sirs,
In accordance with Cl. of the Conditions of Contract, we submit herewith the original
and copies of our Interim Payment Certificate No. for the Period ending 31 March
2005 in the amount state currencies & amounts.
In accordance with Cl. of the Conditions of Contract, payment should be made no
later than 25 April 2005.
Payment is to be made to the Contractors bank account(s) designated in the
Contractors Interim Payment Statement attached hereto.
Appended to the Interim Payment Certificate is the Contractors Interim Payment
Statement (or Application for Interim Payment Certificate, depending on Contract
terminology) No. , in the amount (state currency & amount) submitted under
cover of the Contractors letter ref. dated .
If certified amount is different from amount claimed by Contractor:
We have marked the Contractors Interim Payment Statement to show the Engineers
corrections and adjustments.
And either: The Engineers justifications for these corrections and adjustments are
appended to the Interim Payment Certificate.
Or:
The Engineers justifications for these corrections and adjustments will be
sent to you as soon as possible, under a separate letter.
And if applicable: Under this Interim Payment Certificate, a deduction has been made
for the Contractors partial repayment of the Advance Payment. Accordingly, please be
advised that the Contractors Advance Payment Security may now be reduced to
(state currency & amount).
Yours faithfully,
Name
For The Engineer
The Louis Berger Group, Inc.
cc *: Contractors Representative
cc *: Resident Engineer
cc: Head Office Supervisor
cc: Others as appropriate
* with attachments
Appendix M
1 of 2
EXAMPLE
Name /Title
Works Contract No. /Title
Contractor: Name
Interim Payment Certificate No for Period ending 31 March 2005
Revised
Contract
Total Certified
to Date
Payment Due
(Currency)
Total
Previously
Certified
(Currency)
(Currency)
N.A.
N.A.
N.A.
(Currency)
N.A.
N.A.
N.A.
Certified by:
...
Name
For The Engineer
The Louis Berger Group, Inc.
NOTE:
cc *: Contractors Representative
* with attachments
Appendix M
2 of 2
If applicable
If applicable
Amount
Amount
Quantity
(currency)
(currency)
Quantity
Amount
Amount
Quantity
(currency)
(currency)
Remaining
after (Date )
Quantity
Estimated Total
to Completion
Amount
Amount
Quantity
(currency)
(currency)
Amounts from individual
Bill summaries
If applicable
Quantity
Estimated Total
to Completion
Amount
(currency)
Remaining
after (Date )
Estimated
Quantity
This Payment
Amount
(currency)
% of
Amount
Amount
Amount
Quantity
Quantity
Quantity
Revised
(currency)
(currency)
(currency)
Contract
CONTRACTOR'S ESTIMATE
ENGINEER'S ESTIMATE
Previous Certified
Estimated
Quantity
Total Certified
to (Date )
Amount
(currency)
Quantity
Total to Date of
Taking-Over
Certificate
Rate
(currency)
Unit
REVISED CONTRACT
Description
GENERAL PROVISIONS
EARTHWORKS
DRAINAGE
STRUCTURES
PAVEMENT
ROADWAY FACILITIES
ENVIRONMENTAL WORKS
UTILITIES RELOCATION
DAYWORKS
VARIATIONS
1000
2000
3000
4000
5000
6000
7000
8000
9000
ORIGINAL CONTRACT
EXAMPLE
SUBTOTAL:
CONTINGENCY (REMAINING)
TOTAL:
As
appropriate
OTHER COSTS:
ADVANCE PAYMENT
ADVANCE REPAYMENT
RETENTION MONEY
PAYMENT OF RETENTION MONEY
PENDING VARIATIONS (Itemise)
PRICE ADJUSTMENTS FOR RISE/FALL OF PRICES
PRICE ADJUSTMENTS FOR LEGISLATION CHANGES
PRICE ADJUSTMENTS FOR WORK OMISSIONS
CONTRACTOR'S CLAIM SETTLEMENTS (Itemise)
PROLONGATION COSTS DURING EXTENSION OF TIME
TOTAL:
LS
LS
Month
TOTAL:
BILL 2000: EARTHWORKS:
TOTAL:
BILL 3000: DRAINAGE:
ETC.
Appendix M
5 of 5
Appendix N
COST ESTIMATES
TO COMPLETION
Referenced in:
Section II-3.15: Estimates of Cost of Works to Completion
Contract No. .
Contractor Name ..
Date of Estimate: ..
b1
Revised
Contract
a1+b1
c1
d1
c1+d1
Site Clearance
a2
b2
a2+b2
c2
d2
c2+d2
Earthworks
a3
b3
a3+b3
c3
d3
c3+d3
Etc.
a4
b4
a4+b4
c4
d4
c4+d4
a5
b5
a5+b5
c5
d5
c5+d5
a6
b6
a6+b6
c6
d6
c6+d6
an
bn
an+bn
cn
dn
cn+dn
N.A.
f1
f1
g1
h1
g1+h1
an
bn+fn
cn+gn
dn+hn
cn+dn+gn+hn
e1
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
i1
Original
Contract
a1
Bill
Description
No.
1 General Items
Etc.
Dayworks (if quantified in BoQ & incl.
in Accepted Contract Amount)
Subtotal:
Dayworks (if Schedule of DW Prices
included in Contract, but no amount
included in Accepted Contract Amount)
Subtotal:
VALUE OF WORKS
Provisional Sum for Contingency (if any)
ACCEPTED CONTRACT AMOUNT
Advance Payment
As appropriate
EXAMPLE
Total:
Variations
Certified to Date
Estimated Remaining
an+en
N.A.
an+bn+fn
"PS remaining"
(see Note 1)
N.A.
N.A.
N.A.
N.A.
N.A.
i1
Advance Repayment
N.A.
N.A.
N.A.
-( i2 )
N.A.
-( i1-i2 )
Retention
N.A.
N.A.
N.A.
j1
j2
N.A.
N.A.
k1
-( i1 )
j1+j2
-( j1+j2 )
Pending Variations
N.A.
N.A.
k1
N.A.
k2
k2
l1
m1
l1+m1
N.A.
k3
k3
l2
m2
l2+m2
N.A.
k4
k4
l3
m3
l3+m3
N.A.
k5
k5
l4
m4
l4+m4
N.A.
k6
k6
l5
m5
l5+m5
Subtotal
N.A.
kn
kn
in+jn+ln
in+jn+mn
in+jn+ln+mn
Total:
N.A.
fn+kn
en+fn+kn
k1
dn+hn+in+jn+kn+mn
cn+dn+gn+hn+kn+ln+mn
ESTIMATED COST TO COMPLETION cn+gn+in+jn+ln
Note:
Recommended Contingency for....(itemize)
n
1. If a PS for Contingency was included in the Accepted Contract Amount,
POTENTIAL COST TO COMPLETION cn+dn+gn+hn+kn+ln+mn+n
then in Revised Contract column enter a "PS remaining" as the lesser of
the following:
either: the amount by which Accepted Contract Amount (including PS) exceeds Revised Contract Price (excluding PS)
(whereby Revised Contract Price = Accepted Contract Amount, but with reduced PS)
or:
to zero if Revised Contract Price (excluding PS) exceeds Accepted Contract Amount (including PS).
2. If Contract payments in more than one currency, add columns as necessary. Also add Value Added Tax if relevant.
Appendix N
1 of 1
Appendix O
TAKING-OVER
CERTIFICATE
Referenced in:
Section II-6.2: Taking-Over Certificate
EXAMPLE
SIMPLE LETTER
FORMAT
Ref.:
Date
Reference:
Subject:
po/OUT/195
..
Dear Sirs,
We refer to your letter ref dated whereby you requested a Taking-Over Certificate
for a Section (or part) of the Works, and undertook to complete with due expedition any
outstanding work and to rectify defects during the Defects Notification Period.
Pursuant to Cl. of the Conditions of Contract we hereby certify that, in the Engineers
opinion, the following Section (or part) of the Works was substantially completed in
accordance with the Contract on (state date):
[Describe relevant section or part of Works]
Pursuant to Cl we hereby notify you that the attached list of outstanding works to be
executed and defects to be rectified are required to be completed by you expeditiously
during the Defects Notification Period.
The Defects Notification Period for this Section (or part) of the Works commenced on
[give date, same as date on which works hereby certified as having been substantially
completed] and will expire on [give date].
Yours faithfully,
Name
For The Engineer
The Louis Berger Group, Inc.
cc:
cc:
cc:
cc:
Appendix O
Employers Representative
Resident Engineer
Head Office Supervisor
Others as appropriate
1 of 7
EXAMPLE
SIMPLE LETTER
FORMAT
Ref.:
Date
Reference:
Subject:
po/OUT/295
..
Dear Sirs,
We refer to your letter ref dated whereby you requested a Taking-Over Certificate for the
whole of the Works, and undertook to complete with due expedition any outstanding work and to
rectify defects during the Defects Notification Period.
Pursuant to Cl. of the Conditions of Contract we hereby certify that, in the Engineers opinion,
the whole of the Works was substantially completed in accordance with the Contract on (state
date):
If relevant:
The following Taking-Over Certificates have previously been issued for Sections (or parts) of the
Works:
Description of Section
Effective date of Taking-Over Certificate
Description of Section
Effective date of Taking-Over Certificate
Pursuant to Cl we hereby notify you that the attached list of outstanding works to be executed
and defects to be rectified are required to be completed by you expeditiously during the Defects
Liability Period.
Attached list should show:
For each Section for which a Taking-Over Certificate was previously issued:
- Any works still remaining to be completed;
- Any defects notified with the Certificate but still remaining to be rectified;
- Any defects notified during the Defects Notification Period of the Works Section but still
remaining to be rectified.
For the remainder of Works now substantially completed:
- Any works remaining to be completed;
- Any defects to be rectified;\.
This final Defects Notification Period commenced on [give date, same as date on which works
hereby certified as having been completed] and will expire on [give date].
Yours faithfully,
Name
For The Engineer
The Louis Berger Group, Inc.
cc:
cc:
cc:
cc:
Appendix O
Employers Representative
Resident Engineer
Head Office Supervisor
Others as appropriate
2 of 7
NAME OF EMPLOYER
(The Employer)
AND:
NAME OF CONTRACTOR
(The Contractor)
TAKING-OVER CERTIFICATE
WITH RESPECT TO
THE WHOLE OF THE PERMANENT WORKS
ISSUED BY:
Appendix O
3 of 7
TAKING-OVER CERTIFICATE
WITH RESPECT TO THE
WHOLE OF THE PERMANENT WORKS
DISTRIBUTION:
Contractor: ..
Employer:
Engineer: The Louis Berger Group, Inc.
Funding Institution: ...........
PROJECT:
PROJECT TITLE
CONTRACT:
EMPLOYER:
NAME
CONTRACTOR:
NAME
ENGINEER:
Appendix O
4 of 7
RETENTION MONEY
In accordance with Clause of the Conditions of Contract the amount of Retention Money
retained by the Employer until expiration of the Defects Notification Period shall be % of the
Contract Price. Upon issue of this Taking-Over Certificate the amount of Retention Money
previously retained less % of the Contract Price shall be certified by the Engineer for payment
to the Contractor.
WORKS TO BE COMPLETED OR CORRECTED
DURING THE DEFECTS NOTIFICATION PERIOD
A LIST OF WORKS TO BE COMPLETED OR CORRECTED DURING THE Defects Notification
Period is appended hereto as Appendix 1 to the Taking-Over Certificate with respect to the
Whole of the Permanent Works. Omission from this list of any outstanding or defective works
shall not relieve the Contractor of responsibility to complete all Works in accordance with the
Contract.
To the intent that the Works shall be delivered to the Employer in the condition required by the
Contract, fair wear and tear excepted, the Contractor shall execute all work of amendment,
reconstruction, and remedying defects or other fault as the Engineer may as a result of
inspections made by or on behalf of the Engineer during the Defects Notification Period, instruct
the Contractor to execute. The Contractor shall execute such works in accordance with Clause
of the Conditions of Contract.
CERTIFICATION
Signed on behalf of
THE ENGINEER
The Louis Berger Group, Inc.
by:
Name
Title
Date: ....................
Appendix O
5 of 7
PROJECT:
PROJECT TITLE
CONTRACT:
APPENDIX No.1
TO TAKING-OVER CERTIFICATE
WITH RESPECT TO
THE WHOLE OF THE PERMANENT WORKS
DEFECTS TO BE RECTIFIED
DURING
DEFECTS NOTIFICATION PERIOD
Appendix O
6 of 7
PROJECT:
PROJECT TITLE
CONTRACT:
APPENDIX No.2
TO TAKING-OVER CERTIFICATE
WITH RESPECT TO
THE WHOLE OF THE PERMANENT WORKS
RELEVANT CORRESPONDENCE
Appendix O
7 of 7
Appendix P
PERFORMANCE
CERTIFICATE
Referenced in:
Section II-7.9: Performance Certificate
EXAMPLE
SIMPLE LETTER
FORMAT
Name /Title
Ref.:
Date
Reference:
Subject:
Performance Certificate
po/OUT/395
..
Dear Sirs,
Pursuant to Cl. of the Conditions of Contract we hereby certify that the date on which
the Contractor completed his obligations to execute and complete the Works and
remedy any defects therein to the Engineers satisfaction was [enter date, which
must be within 28 days after the end of the Defects Notification Period, or if sections
have been taken over the last such period, or when all remedial works were completed
to the Engineers satisfaction].
Yours faithfully,
Name
For The Engineer
The Louis Berger Group, Inc.
cc:
cc:
cc:
cc:
Appendix P
Contractors Representative
Resident Engineer
Head Office Supervisor
Others as appropriate
1 of 1
Appendix Q
ENGINEERS DELEGATION
OF DUTIES & AUTHORITIES
Referenced in:
Section II-2.2: Engineers Delegation of Duties & Authorities
Section II-5.12: Engineers Authority to Instruct Design Modifications
EXAMPLE
[ SIMILAR LETTER COULD BE ADOPTED FOR FIDIC OLDER 1987 RED BOOK]
Ref.:
Attention:
Attention:
Name
Contractors Representative
po/OUT/195
Date ..
Name
Employers Representative
.
Reference:
Subject:
Dear Sirs,
Pursuant to Sub-Clause 3.2 [Delegation by the Engineer] of the Conditions of Contract we hereby
notify that the Engineer appoints the following persons to assist him in the performance of the
Engineers duties under the Contract:
Position:
Asst. Resident
Engineer (Highways)
Asst. Resident
Engineer (Structures)
Contract Engineer
Quantity Surveyor
Section Engineers
Name:
Name
Position:
Sr. Materials Engineer
Materials Technicians
Name
Topographic Surveyors
Name
Name
Name
Name
Inspectors
Name:
Name
Name
Name
Name
Name
Name
Name
Name
The Engineer hereby delegates to these assistants duties and authorities as listed in the attached
Table entitled Engineer's Delegation of Duties & Authorities. The assistants shall have shall have
no authority, other than specifically noted in the Table, to issue any instructions to the Contractor
save in so far as such instructions may be necessary to enable them to carry out their duties and to
secure their acceptance of Materials, Plant or workmanship as being in accordance with the
Contract, and any instructions given by them for those purposes shall be deemed to have been
given by the Engineer".
Yours faithfully,
Name
Resident Engineer
for The Engineer
The Louis Berger Group, Inc.
Project Management Guidelines
cc:
cc:
cc:
Appendix Q
Employers Representative
Head Office Supervisor
Others as appropriate
1 of 13
EXAMPLE
ENGINEER'S DELEGATION OF DUTIES & AUTHORITIES
UNDER RECENT 1999 FIDIC RED BOOK CONDITIONS OF CONTRACT
The following delegations relate to the General Conditions of FIDICs 1999 Red Book Contract. Delegations relating to
Particular Conditions would need to be added.
The Engineer cannot delegate authority to determine claims pursuant to Sub-Clause 3.5.
1.
2.
3.
4.
5.
6.
Contract Engineer
Quantity Surveyor
Sr. Materials Engineer
7.
8.
9.
10.
1.9
1.12
2.1
2.5
3.1
3.2
3.3
3.5
X
X
Section Engineers
Materials Technicians
Topographic Surveyors
Inspectors
X
X
X
X
X
X
X
X
X
10
X
X
X
X
X
X
X
X
X
X
X
Appendix Q
2 of 13
4.
5.
6.
Contract Engineer
Quantity Surveyor
Sr. Materials Engineer
7.
8.
9.
10.
4.2
4.3
4.4
4.6
4.7
4.9
4.12
4.16
4.17
Section Engineers
Materials Technicians
Topographic Surveyors
Inspectors
10
X
X
X
X
X
X
X
X
X
X
X
Appendix Q
3 of 13
4.
5.
6.
Contract Engineer
Quantity Surveyor
Sr. Materials Engineer
7.
8.
9.
10.
4.21
X
X
X
X
X
X
X
4.24
5.1
5.2
5.3
5.4
6.5
6.9
6.10
7.2
7.3
7.4
Section Engineers
Materials Technicians
Topographic Surveyors
Inspectors
10
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
Appendix Q
X
X
4 of 13
4.
5.
6.
Contract Engineer
Quantity Surveyor
Sr. Materials Engineer
Section Engineers
Materials Technicians
Topographic Surveyors
Inspectors
7.
8.
9.
10.
7.6
8.1
8.3
8.4
8.6
8.8
8.9
8.11
8.12
9.1
10.1
10.2
10.3
11.1
11.4
11.6
11.9
12.1
X
X
X
X
X
10
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
Appendix Q
5 of 13
4.
5.
6.
Contract Engineer
Quantity Surveyor
Sr. Materials Engineer
Section Engineers
Materials Technicians
Topographic Surveyors
Inspectors
7.
8.
9.
10.
12.4
13.1
13.2
13.3
13.5
13.6
13.7
13.8
14.1
14.3
14.5
14.6
14.10
X
X
X
X
X
X
X
X
X
10
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
Appendix Q
6 of 13
4. Contract Engineer
5. Quantity Surveyor
6. Sr. Materials Engineer
7.
8.
9.
10.
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
Appendix Q
Section Engineers
Materials Technicians
Topographic Surveyors
Inspectors
10
X
X
7 of 13
EXAMPLE
ENGINEER'S DELEGATION OF DUTIES & AUTHORITIES
UNDER OLDER 1987 FIDIC RED BOOK CONDITIONS OF CONTRACT
The following delegations relate to the General Conditions of FIDICs 1987 Red Book Contract. Delegations relating to
Conditions of Particular Application would need to be added.
The Engineer should not delegate authority under Sub-Clauses 2.2, 2.3, 63.1 & 67.1.
1.
2.
3.
4.
5.
6.
7.
Contract Engineer
Quantity Surveyor
Sr. Materials Engineer
Materials Technicians
2.2
2.3
2.4
4.1
5.2
6.1
6.2
6.3
6.4
7.1
7.2
8.2
10.1
12.2
13.1
14.1
14.2
14.3
15.1
8. Section Engineers
9. Topographic Surveyors
10. Inspectors
10
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
Appendix Q
X
X
X
X
X
X
X
8 of 13
4.
5.
6.
7.
Contract Engineer
Quantity Surveyor
Sr. Materials Engineer
Materials Technicians
16.2
17.1
18.1
19.1
20.2
20.3
25.1
27.1
30.3
31.1
31.2
33.1
35.1
36.1
36.4
8. Section Engineers
9. Topographic Surveyors
10. Inspectors
X
X
X
X
X
X
X
X
Appendix Q
10
X
X
X
9 of 13
4.
5.
6.
7.
Contract Engineer
Quantity Surveyor
Sr. Materials Engineer
Materials Technicians
36.5
37.1
37.2
37.3
37.4
37.5
38.1
38.2
39.1
39.2
40.1
40.2
40.3
41.1
42.1
42.2
44.1
44.2
44.3
8. Section Engineers
9. Topographic Surveyors
10. Inspectors
X
X
X
X
X
X
Appendix Q
10
X
X
10 of 13
4.
5.
6.
7.
Contract Engineer
Quantity Surveyor
Sr. Materials Engineer
Materials Technicians
45.1
46.1
48.1
48.2
48.3
49.1
49.2
49.3
49.4
50.1
51.1
52.1
52.2
52.3
52.4
53.1
53.2
8. Section Engineers
9. Topographic Surveyors
10. Inspectors
X
X
X
X
X
X
X
X
X
X
X
X
Appendix Q
10
X
X
X
X
11 of 13
4.
5.
6.
7.
Contract Engineer
Quantity Surveyor
Sr. Materials Engineer
Materials Technicians
8. Section Engineers
9. Topographic Surveyors
10. Inspectors
53.3
X
X
X
X
X
X
X
X
53.5
54.1
56.1
57.2
58.1
58.2
58.3
59.1
59.2
59.5
60.1
60.2
Appendix Q
10
X
X
X
X
12 of 13
4.
5.
6.
7.
Contract Engineer
Quantity Surveyor
Sr. Materials Engineer
Materials Technicians
8. Section Engineers
9. Topographic Surveyors
10. Inspectors
60.5
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
60.6
60.7
60.8
62.1
63.1
63.2
63.3
63.4
64.1
65.3
65.5
65.8
67.1
68.3
69.1
69.4
70.2
Appendix Q
10
13 of 13
Appendix R
COMPARISON OF
SUB-CLAUSE NUMBERS
BETWEEN
1.1
1.2
1.2
1.2
1.3
2.1
2.2
2.3
2.4
2.5
2.6
3.1
3.2
3.2
3.2
3.3
3.1
3.1
4.1
4.2
1.7
4.4
4.5
5.1
5.2
6.1
6.2
6.3
6.4
6.5
7.1
7.2
7.3
Contract Documents
Language and Law
Priority of Contract Documents
Custody and Supply of Drawings and Documents
One Copy of Drawings to be Kept on Site
Disruption and Progress
Delays and Cost of Delay of Drawings
Failure by Contractor to Submit Drawings
Supplementary Drawings and Instructions
Permanent Works Designed by Contractor
Responsibility Unaffected by Approval
1.4
1.5
1.8
1.8
1.9
1.9
1.9
3.3
4.1
3.1
8.1
8.2
9.1
10.1
10.2
10.3
11.1
12.1
12.2
General Obligations
Contractors General Responsibilities
Site Operations and Methods of Construction
Contract Agreement
Performance Security
Period of Validity of Performance Security
Claims under Performance Security
Inspection of Site
Sufficiency of Tender
Not Foreseeable Physical Obstructions or Conditions
Appendix R
4.1
4.1
1.6
4.2
4.2
4.2
4.10
4.11
4.12
1 of 5
13.1
14.1
14.2
14.3
14.4
15.1
16.1
16.2
17.1
18.1
19.1
19.2
20.1
20.2
20.3
20.4
21.1
21.2
21.3
21.4
22.1
22.2
22.3
23.1
23.2
23.3
24.1
24.2
25.1
25.2
25.3
25.4
26.1
27.1
28.1
28.2
29.1
30.1
30.2
30.3
30.4
31.1
31.2
32.1
33.1
34.1
35.1
Labour
Engagement of Staff and Labour
Returns of Labour and Contractors Equipment
Appendix R
3.3, 19.7
8.3
8.3
14.4
3.1
4.3
6.9
6.9
4.7
13.1
4.8, 4.18, 4.22
2.3
17.2
17.2
17.4
17.3
18.2
18.2
18.1
18.2
17.1
17.1
17.1
18.3
18.3
18.3
18.4
18.4
18.1
18.1
18.1
17.1
1.13
4.24
17.5
7.8
4.14
4.15
4.13, 4.15
4.16
4.15
4.6
4.6
4.23
4.23
6.1
6.10
2 of 5
36.1
36.2
36.3
36.4
36.5
37.1
37.2
37.3
37.4
37.5
38.1
38.2
39.1
39.2
40.1
40.2
40.3
Suspension
Suspension of Work
Engineers Determination following Suspension
Suspension lasting more than 84 Days
41.1
42.1
42.2
42.3
43.11
44.1
44.2
44.3
45.1
46.1
47.1
47.2
48.1
48.2
48.3
48.4
8.1
2.1
2.1
4.13
8.2
8.4
8.4
8.4, 20.1
6.5
8.6
8.7
10.2
10.1
10.2
10.2
10.4
49.1
49.2
49.3
49.4
50.1
Defects Liability
Defects Liability Period
Completion of Outstanding Work and Remedying Defects
Cost of Remedying Defects
Contractors Failure to Carry Out Instructions
Contractor to Search
11.1
11.1
11.2
11.4
11
51.1
51.2
52.1
52.2
52.3
52.4
13.1
13.1
12.3
12.3
13
Appendix R
7.1
7.2
7.4
7.4
7.4
7.3
7.3
7.3
7.5
3.2
7.3
7.3
7.6
7.6
8.8
8.9
8.11
3 of 5
53.1
53.2
53.3
53.4
53.5
54.1
54.2
54.3
54.4
54.5
54.6
54.7
54.8
55.1
56.1
57.1
57.2
Measurement
Quantities
Works to be Measured
Method of Measurement
Breakdown of Lump Sums
14.1
12.1
12.2
14.1
58.1
58.2
58.3
Provisional Sums
Definition of Provisional Sum
Use of Provisional Sums
Production of Vouchers
13.5
13.5
13.5
59.1
59.2
59.3
59.4
59.5
Nominated Subcontractors
Definition of Nominated Subcontractors
Nominated Subcontractors: Objection to Nomination
Design Requirements to be Expressly Stated
Payments to Nominated Subcontractors
Certification of Payments to Nominated Subcontractors
60.1
60.2
60.3
60.4
60.5
60.6
60.7
60.8
60.9
60.10
61.1
62.1
62.2
63.1
63.2
63.3
63.4
64.1
Remedies
Default of Contractor
Valuation at Date of Termination
Payment after Termination
Assignment of Benefit of Agreement
Urgent Remedial Work
20.1
20.1
20.1
20.1
20
Appendix R
4.17
4.17, 17.2
2.2
2.2
4.4, 15.2
15.3
4.4
-
5.1
5.2
5.2
5.3
5.4
14.3
14.6
14.9
14.6
14.10
14.11
14.12
14.13
14.14
14.7
11.9
11.9
11.10
15.2
15.3
15.4
4.4, 15.2
7.6
4 of 5
65.1
65.2
65.3
65.4
65.5
65.6
65.7
65.8
Special Risks
No Liability for Special Risks
Special Risks
Damage to Works by Special Risks
Projectile, Missile
Increased Costs arising from Special Risks
Outbreak of War
Removal of Contractors Equipment on Termination
Payment if Contract Terminated
17.4
17.3
17.4
17.4
17.4
19.6
19.6
19.6
66.1
19.7
67.1
67.2
67.3
67.4
Settlement of Disputes
Engineers Decision
Amicable Settlement
Arbitration
Failure to Comply with Engineers Decision
20.1
20.5
20.6
20.7
68.1
68.2
68.3
Notices
Notice to Contractor
Notice to Employer and Engineer
Change of Address
69.1
69.2
69.3
69.4
69.5
Default of Employer
Default of Employer
Removal of Contractors Equipment
Payment on Termination
Contractors Entitlement to Suspend Work
Resumption of Work
16.2
16.3
16.4
16.1
16.1
70.1
70.2
13.8
13.7
71.2
72.1
72.2
72.3
1.3
1.3
1.3
Appendix R
14.15
14.15
14.15
5 of 5