MWRI-MED Pumping Stations Rehabilitation Program

New Construction of Edku pumping station

Vol. II Technical Specifications


Chap 2 Description of Works

In principle, coating or painting shall be performed after the hydrostatic test, if applicable,
and assembling of the equipment. Coating or painting on those parts to be submerged in the
shop tests shall be finished prior to the test.
Dirt or rust preventive primers shall be applied immediately after surface treatment for
those parts to be grit blasted prior to fabrication. No lead primers are allowed.
Internal surfaces in contact with oil or grease shall be painted, if necessary, with epoxy
paint or as per manufacturer's standards.
The coating or painting schedule described hereinafter shall not applied to machined,
stainless parts, ferrous surfaces, non ferrous metal parts and galvanized parts.
Temporary rust preventive coatings shall be applied for ferrous machined surfaces for
protection during shipping.
Ferrous surfaces to be embedded in concrete shall be painted with zinc-primer to prevent
corrosion. Transition zones (water/concrete or air/concrete) of ferrous surfaces to be
partially embedded in concrete are to receive special treatment for avoiding crevice
corrosion. Bidders have to submit corresponding technical proposals.
Painting materials for touch-up at site shall be supplied in appropriate amount with the
equipment.
2.15.2

Surface Preparation
Ferrous surface of the equipment shall be prepared prior to coating or painting according to
the applicable standards, in either of two methods of treatment:
a)

Sand blast cleaning S 2 or equivalent.

b) Power sander cleaning or equivalent.


2.15.3

Color
The Main Contractor shall submit the color schedule for the different equipment, which
supports safety of operation and understanding of processes in the pumping station for
approval by MED within 4 weeks after Entering into Force of the Contract.

2.15.4 Coating or Painting Schedules


The following are the proposed coating or paintings. Bidders shall quote according to the
schedules given hereinafter or higher quality.
Schedule C:
Primer ................................................................... 2 coats
Epoxy resin enamel .............................................. 2 coats
Min. total dry film thickness ......................... 150 micron

10092014_Gen

Vol. II, chapter 2

Page 15 of 19

MWRI-MED Pumping Stations Rehabilitation Program


New Construction of Edku pumping station

Vol. II Technical Specifications


Chap 2 Description of Works

Schedule D:
Coal tar epoxy resin paint .................................... 3 coats
Min. total dry film thickness ......................... 240 micron
Schedule E:
Epoxy primer ....................................................... 2 coats
Epoxy resin enamel ............................................. 2 coats
Min. total dry film thickness ......................... 300 micron
Schedule F:
Epoxy lining
Design lining thickness ............................... 1000 micron
Schedule Z:
Manufacturer's Standard
Groups of elements to be treated for corrosion protection:
Group 1:
1) Main pumps.
2) Suction and discharge pipes.
3) Dewatering pumps
Applicable Surface

External Surface

Internal Surface

Surface preparation

Sand blasted S 2

Sand blasted S 2

Painting at works

Schd. C

Schd. D in general;
Schd. F for 1 and 2; see Notes

Painting at site
Touch up
Touch up as required
Notes: Painting of shafts of main pumps made of plain steels and not covered by protective
sleeves and shall be only for that portion which runs along with water.
Group 2:
1) Reduction gears (if offered).
2) Lubricating oil units.
3) Main motors
4) Overhead traveling crane
Applicable Surface
External Surface

Internal Surface

Surface preparation

Sand blasted S 2

Sand blasted S 2

Painting at works

Schd. C

Schd. Z

Painting at site

Touch up

---

Group 3:
1) Weed screen cleaning machine
2) Stop logs
Applicable Surface
10092014_Gen

External Surface

Vol. II, chapter 2

Internal Surface
Page 16 of 19

MWRI-MED Pumping Stations Rehabilitation Program


New Construction of Edku pumping station

Vol. II Technical Specifications


Chap 2 Description of Works

Surface preparation

Sand blasted S 2

Sand blasted S 2

Painting at works

Schd. E

Schd. Z

Painting at site

Touch up

---

Group 4:
1) M.V. Switchgear (if any)
2) L.V. Switchgear.
3) Battery and charger (if any)
4) Water level recorder panel.
5) Control panel.
Applicable Surface

Outer and Inner Surface

Surface preparation

Special treatment

Painting at works

Melamine resin dry backed 2 coats or better

Painting at site

Touch up to best standard

Group 5:
1) Weed screens
2) Elements for fixing Equipment to the concrete
3) Structural elements of screen cleaning installations and built-in elements
Applicable Surface

Outer and Inner Surface

Surface preparation

Special treatment

Coating at works

Hot dip galvanization

Repair of coating at site

Zinc paint after cleaning with wire brush

Additional coating after installation Schd D


Art . 2. 16 Calculation of Computational Fluid Dynamics Analysis ( CFD )
2- Tenders are requested to submit with the offers the study of Computational Fluid Dynamics
Analysis

( CFD ) of the pump sump to analyze the flow pattern in the sump . The required study

should include the analysis and the solution to improve the flow pattern in the sump , evidence
documents should be submitted .

10092014_Gen

Vol. II, chapter 2

Page 17 of 19