Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
http : //www.cigre.org
CIGRE 2016
SUMMARY
Online Partial discharge (PD) testing has been used for decades to help maintenance
personnel to detect problems in High voltage Systems. Most of the failures in todays extra
high voltage cable system is due to PD under AC voltage stress. Continuous or periodic
monitoring of this PD is a very vital activity to confirm the healthiness & early detection of
upcoming failures in extra high voltage systems. Condition based maintenance of power
cables required reliable significant diagnosis methods for the integrity of operation of cable
systems. Low PD magnitudes are very critical in extra high voltage cables & accessories.
Measuring such low magnitudes of sensitive PD is challenging and possible by an improved
Signal to Noise (S/N) ratio adopted measurement technique.
Ultra High Frequency (UHF) technique due to its ability to perform in MHz ranges will
enable us to establish periodic / continuous PD monitoring practice on critical assets. This
paper describes importance of PD measurements, case study based experience with PD
measurements as a part of periodic monitoring system and timely detection of an evolving PD
fault in a 220kV wet type cable sealing end at Gas Insulated Switchgear (GIS) side. This
cable is an interconnection between Generator step up transformer and GIS. Non conventional
PD measurement techniques like Ultra High Frequency (UHF) & High Frequency Current
Transformers (HFCT) are explained in this paper with some focus on practical problems and
challenges experienced in interpreting the PD measurement.
KEYWORDS
Partial Discharge, UHF Sensors, HFCT Sensors, Wet Type Cable Sealing end, PRPD.
1.0 Introduction
Partial Discharge is often defined as a localized electrical discharge that only partially bridges
the insulation between conductors and which can or cannot occur adjacent to a conductor [1].
PD is both the cause and symptom of a deteriorating insulation system. Internal to all
insulation systems exist some imperfections known as Voids. Causes for these Voids can be
numerous but these voids will act as a catalyst for the creation of PD.
Monitoring the partial discharge (PD) on site in cables accessories is now a more effective
method of cable tests. Meaningful PD measurement can obtain reliable information on the
condition of sealing ends and joints after installation or several years of operation.
Measuring frequencies of maximum 500 kHz are recommended as per IEC60270, however
such frequency ranges are not suitable for the site related PD measurements as the noise
signals dominate the signal strength. For an improved signal to noise ratio, measuring
frequency ranges need to be >500 kHz.
2.0 Ultra High Frequency method
The UHF (ultra high frequency) method is an effective PD detection method. It shows out the
superiority in measurement sensitivity and suppressing interference. It has been confirmed
that the frequency of the PD pulse generated in cables can reach up to GHz, while the
frequency of background noise usually lies below 400 MHz.
UHF based PD measurement due to its strong attenuation of PD pulses is highly applicable to
confirm the integrity of power cable accessories such as joints & terminations.
The UHF partial discharge measuring (PDM) system is consisting of the ultra-high frequency
measuring instrument the Pre-amplifier and the UHF partial discharge sensor (Figure 2 :
UHF-PD-coupler). [2]
Capacitive type
Sensor
CSE Type
Di electric Media inside CSE
Voltage Rating
Cable Size
Wet
Silicon oil
220 kV
400 mm
SF6 Media
As the fault location was not confirmed & the PD magnitude was also low periodic
monitoring of PD activity is planned to track the PD pulses and intensity. Below trend shows
the trend record of the PD activity.
In order to maintain the uniformity of ambient conditions with respect to critical frequency
its decided to keep the critical frequency value at 270 MHz & trend of PD pulse by time is
monitored almost close to every month to track the magnitude of the PD pulses & rate of
increase. Below graph clearly shows that by time there is not much increase in pulse
magnitude but more or less the value is maintained in the range of 400-600 V.
5.6 Visual Inspection of CSE
Even though the increase in PD magnitude is not significant but PD presence was detected in
almost all the measuring methods in view of the equipment criticality and associated risk in
the event of catastrophic failure it was planned to have a visual inspection to evaluate the
healthiness of the cable sealing end.
Dismantling of CSE connection chamber was done & the observations are explained below.
i. Drained oil level from the R-phase CSE chamber was less by 6 liters when compared
to the total chamber capacity.
ii. XLPE cable surface indicated surface tracking due to loss of dielectric media
(silicon oil). Figure-8 explains the surface tracking phenomena.
Silicon Oil
Silicon Oil
Seepage
BIBLIOGRAPHY
[1] IEC60270: High Voltage Test Techniques - Partial Discharge Measurements
[2] UHF PD Sensor manual- Doble-lemke Manual version 3
[3] High Frequency Current transformer HFCT-3000 user manual version 00
[4] Partial discharge diagnostics on GIS using UHF and Acoustic Method
AUTHORS BIOGRAPHY
Karthik Sriramakavacham, Graduate in Electrical Engineering & Lean Six Sigma certified
Green belt professional. He had total 12 years of experience in Condition monitoring of
electrical assets associated with power & process sector. Associated with numerous projects
related to fault finding, residual life assessment studies & preventive maintenance / diagnostic
testing of critical electrical assets. Worked for Alstom & ABB in India as a Testing engineer.
He is working in GCC last 8 years in the field of electrical condition monitoring & diagnostic
testing activities. Currently working as Head of Electrical Condition monitoring for Al Ezzel
Operation & Maintenance Company and based at Aldur Power & Water station, 1234 MW
combined cycle power plant with 49 MIGD water production plant based on Reverse Osmosis
technology at Kingdom Of Bahrain.
Shamalji Solanki, Graduate in Electrical Engineering and Master of business administration
(MBA) in Project Management. He had total 19 years of experience in power sector. He has
worked 9 years in Electrical maintenance department for Reliance Industries Ltd-India for
their 450MW Combined Cycle Captive Power Plant feeding power to the one of the largest
petroleum Refinery and Petrochemical complex. He is working in GCC last 9 years for
combined cycle power plant. Worked in Qatar for power plant maintenance and presently
working as Head of Electrical maintenance for 950MW Al Ezzel power plant, Al Ezzel O&M
Co. (GDF SUEZ)-Bahrain.