Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Abstract
This section covers the design concepts and criteria for external cathodic protection
of onshore well casings. Leak frequency, casing inspection, and system design are
discussed. An outline describes the steps involved from evaluating a candidate field
to making final adjustments to the cathodic protection installation.
Contents
Page
1510 Introduction
1500-3
1511 Background
1512 CP of Well Casings versus Pipelines
1513 Chevron Case Histories
1520 Limitations
1500-4
1500-6
1500-9
Chevron Corporation
1500-1
August 1999
1500-13
1551 Rules-of-Thumb
1552 Mathematical Modeling
1553 Suggested Well Casing Current Requirements
1554 Other Industry Practices
1555 Interference
1560 Anode Bed Design
1500-17
1500-19
August 1999
1500-21
1590 References
1500-22
1500-2
Chevron Corporation
1510 Introduction
This section discusses the use of CP (cathodic protection) for the cost effective
control of external well casing corrosion. CP is an important tool because maintaining casing integrity is essential to oil and gas production,water and gas injection, and gas storage fields.
When a leak develops, production (or injection) usually ceases until the leak is
repaired or a liner is installed. When corrosion is severe, the casing can collapse and
the well may have to be abandoned, which can result in lost reserves. CP can be
utilized in maintaining casing integrity caused by external corrosion, thereby
reducing operating costs and maximizing total production and profits.
1511 Background
Cathodic protection has been employed in the oil and gas industry for use on well
casings since the late forties. The use of CP on well casings is preceded by its application to pipelines. Because of its success and because it is the only technique that
can be used to mitigate corrosion after the well is in place, CP is now an accepted
procedure in the oil field.
2.
3.
Pipe-to-soil potential measurements can only be made at the end from which
the current is drained. Potentials cannot be directly measured along the outside
surface of the casing.
4.
Well casings are connected by threaded collars rather than welded connections,
which may increase the resistance of the metallic path.
5.
6.
7.
Long lengths of the production casing are shielded from CP by surface and
intermediate casing strings.
Chevron Corporation
1500-3
August 1999
Fig. 1500-1 Chevron Operated Oil Fields with Well Casing Cathodic Protection
Field Name
Location
Date Installed
# Anode Beds
# Wells
SACROC
TX
1979
750
1560
Elk Hills
CA
1963
650
2000
East Texas
TX
1970
132
225
Baxterville
MS
1960
125
270
Kettleman Hills
CA
1958
75
200
Pittsburg
TX
1988
36
45
Taft
CA
1965
30
30
Raleigh
MS
1961
26
26
Coalinga
CA
1965
25
60
Heidelberg
MS
1984
18
24
The number of wells that have been placed under CP is impressive, but includes
only a small fraction of the total number of wells operated by the company. The
majority of these systems were installed after well casing leaks became a significant problem.
1520 Limitations
While CP is a great tool for corrosion control of well casings, there are limitations
to its effectiveness. In some cases it simply may not be practical to get protection to
the bottom of deep well casings. This section will discuss those limitations.
August 1999
1500-4
Chevron Corporation
more even its current distribution. Figure 1500-3 is a plot of the equal potential lines
radiating out from a anode bed. It demonstrates that a well placed farther from an
anode bed will receive more uniform potentials and therefore more uniform
protection.
Fig. 1500-2 Typical Well Casing Completion Diagram
Figure 1500-4 illustrates how anode bed distance affects current density on a typical
well casing where X is the distance from the well to the anode bed.
Note Well logs are typically presented with the x-axis across the top showing
current density and the y-axis down the side showing depth from top to bottom. All
well casing plots are presented in this manner for consistency.
1524 Attenuation
Attenuation refers to the decrease in protection level with depth. The well head has
the most negative (best protected) potential at any point on the casing. Because
current is flowing up the casing within a resistive metal path, the casing potential
becomes more positive with depth, yielding a lower current density and less protection.
For very deep wells, attenuation may make it impractical to protect the casing to
total depth. However, in many cases, most leaks occur in a particular corrosive
zone, so that protection to bottom may not be necessary.
Chevron Corporation
1500-5
August 1999
1526 Temperature
The current requirement of steel increases with increasing temperature. To make
matters worse, attenuation in the well casing reduces the current density with depth
(i.e. the areas of the casing which receive the least protection need it the most).
1530 Justification
This section provides the reader with the background on how to identify candidate
wells for CP and how to justify installing a system. It also examines the logic for
applying CP.
August 1999
1.
At the time a well is drilled (as a matter of good operating practice or mandated
by governmental regulations).
2.
3.
1500-6
Chevron Corporation
Chevron Corporation
1500-7
August 1999
Extrapolations from the semi-log plot should not be made too far into the future
because an extremely high number of leaks would be predicted. It would be unreasonable to project more than two leaks for every well in the field. Success should
simply be judged by the amount of deviation from the original extrapolation that
occurred after installation of the CP system [2].
The data required for making a leak frequency plot usually requires many hours of
searching through all of the well files in the subject field. Data to be recorded
includes: when the leak developed, leak depth, and any indication as to the cause.
Notes should also be made of all casing strings including their size, weight, grade,
and total depth. Include only leaks caused by external corrosion when a distinction
can be made.
August 1999
1.
Availability of power.
2.
3.
4.
1500-8
Chevron Corporation
5.
Per well installation costs typically hover around the lower end of this scale because
of anode bed sharing. CP installation costs must be offset by a reduced number of
casing leak repairs which cost approximately $30,000 to $50,000.
2.
3.
Casing inspection logs are a vital part of a CP study because it would do little to
install a CP system on a field that had experienced only internal corrosion or corrosion behind a surface casing string. Significant space is devoted to well logs because
they are the only tools which reveals the present condition of the well.
All casing inspection logs require that the rods and tubing be removed from the
well. It is also good practice to make a bit and scraper run before any logs are run in
a well. The extra tubing trip will remove scale, paraffin, corrosion by-product, and
allow any accumulated fill to be washed out. It is important that the scraper tool
have sharp blades and strong springs.
Because of the cost of well preparation, the best opportunity to run a casing inspection log is during casing repair workovers. This approach not only provides data for
the CP project, but gives the production engineer an idea of where to look for the
leak with his squeeze packer. The inspection log may also indicate that the casing is
in such bad condition that repair by cement squeeze is futile and a liner is required.
Casing inspection tools utilize one of four technologies:
1.
Electromagnetic
2.
Mechanical
3.
Acoustic
4.
Optical
In addition, two other types of logs are important in well casing CP:
1.
Resistivity
2.
A well logging company representative will be quick to point out that each has its
advantages and to perform a thorough job more than one tool will be needed. While
this is true, it can be argued that a single log will provide enough information for the
CP project. If only one log is run, a combination DC induction (flux leakage/eddy
current) log should be selected. The flux leakage/eddy current log is most adept at
Chevron Corporation
1500-9
August 1999
identifying pitting corrosion and can discriminate between internal and external
defects.
AC Induction
The low frequency AC magnetic field tool measures the circumferential average
casing wall thickness. It also detects changes in the internal diameter. It is used to
detect internal pipe wear, casing splits, casing weight changes, bottoms of mixed
1.
Verilog, Magnalog, and Multi-finger Caliper are registered trademarks of Western Atlas International,
Atlas Wireline Services.
PAT, METT, and Mechanical Caliper are Registered Trademarks of Schlumberger.
Casing Caliper is a registered trademark of Kinley, Inc.
August 1999
1500-10
Chevron Corporation
strings, and casing parts. Because corrosion more often occurs as pits, this tool
should not be used alone in a casing inspection program.
Trade names:
Chevron Corporation
1500-11
August 1999
August 1999
1.
2.
The knife blade edges are coated allowing the tool to be run in any fluid,
including brine.
3.
1500-12
Chevron Corporation
4.
Because the knife contact spacing is two feet and readings are taken at stops every
two feet, Schlumberger sells the CPET tool as a continuous log that can identify
local corrosion cells. In reality there is simply too much noise or contact resistance
to use the log for that purpose. It is still the best tool available for taking long line
current flow measurements at 25 to 50 foot intervals. Rig time will be saved by
insisting on eliminating the extra measurements [7].
The conventional CPP tool and the CPET tool are presented in Figure 1500-6.
Note the extra set of contacts on the CPET that allow the casing resistance to be
measured directly.
The CPP log is interpreted by examining the sign and slope of the readings. A positive value indicates that current is traveling up the casing. A negative slope indicates that current is moving down the casing. Current density is obtained by
dividing the voltage measurement by the casing resistance. A positive slope
(increasing value with decreasing depth) indicates that current is being picked up. A
negative slope indicates that current is being discharged, and corrosion is occurring.
Figure 1500-7 presents the results of multiple CPP log runs from one well. The first
run was made immediately after CP was applied and the others were run after the
well had current applied and had been allowed to polarize [4].
It is useless to run a CPP log within multiple casing strings because there are
numerous incidental contacts where varying amounts of current jump from one
string to the other which makes interpretation of the data impossible. The shallow
areas of the casing are of least concern, because they receive a higher current
density than the bottom.
Chevron Corporation
1500-13
August 1999
Fig. 1500-6 Casing Profile Potential Logging (Courtesy of Schlumberger and Courtesy of
Western Atlas Logging Services, Div. of Western Atlas International)
1551 Rules-of-Thumb
There are two rules-of-thumb that circulate in the well casing CP community. The
first is a current density based on the surface area of the well casing. A value of
2 mA/ft2 is used to calculate the current required to protect all steel not covered by a
cement coating. A value of 0.1 mA/ft2 is used to estimate the amount of current to
protect steel covered by cement.
A second rule-of-thumb for estimating a current requirement assumes that the sizes
of well casings are roughly the same and that 1 amp of current should be adequate
for each 1000 feet of well depth.
August 1999
1500-14
Chevron Corporation
Both of these estimating tools break down in actual use because current is not
evenly applied to the well casing. In some cases current may never reach the deeper
sections of the casing. Use these rules-of-thumb for quick ballpark estimates, but do
not consider the answer to be final [8].
Fig. 1500-7 CPP Log Before and After Polarization (Courtesy of Western Atlas Logging Services, Div. of Western
Atlas International)
Chevron Corporation
1500-15
August 1999
required for input. Dabkowskis model allows the effects of many different resistivity layers to be evaluated. It also can evaluate interference effects of multiple
anode beds and wells.
The third technique is the BEM (boundary element model). This model is currently
in use to evaluate current requirements and potentials on complex structures, such as
offshore platforms. Because of difficulty in setting up input files with layered resistivities, convergence problems, and their CPU intensive nature, BEMs are not
commonly used to evaluate well casing CP [9].
Some computer models capable of running on an IBM or compatible are available
for specific applications. Contact the Corrosion Specialist at CRTC or CPTC to
obtain copies or to obtain assistance in running them.
Single Well
160 Acre
80 Acre
40 Acre
20 Acre
Current
(amps)
Current
(amps)
Current
(amps)
Current
(amps)
Current
(amps)
2,000 ft
1.0
1.5
2.0
2.5
3.0
4,000 ft
3.0
3.5
4.0
5.0
5.5
6,000 ft
5.5
6.0
7.0
10.0
13.0
8,000 ft
7.0
8.0
9.0
11.0
NR
10,000 ft
10.0
12.0
13.0
NR
NR
12,000 ft
12.0
13.0
NR
NR
NR
Well Depth
To facilitate complete CP coverage, an organic coating should be strongly considered for use on new well casings that are to be drilled to a depth over 10,000 ft. or
on wells that are tightly spaced. The greatest cost benefit can be achieved by coating
the OD of the surface casing, because the highest current density is near the surface.
August 1999
1500-16
Chevron Corporation
1555 Interference
Interference is in a non-uniform current density distribution on a structure. In some
cases this can lead to corrosion resulting from current flow through paths other than
the intended circuit. Interference can result from anode beds that are placed too
close to the wells being protected, or from tightly spaced wells, or congested surface
facilities which are near the anode beds. All anode beds contribute to interference,
including those for pipelines and facilities and those owned by other companies.
The solution is to limit the total current being discharged from the offending anode
bed, which limits the ability to protect wells at depth.
Chevron Corporation
1500-17
August 1999
2.
3.
4.
1562 Rectifiers
Of the two conventional types of rectifier stacks (silicon diode and selenium) the
silicon diode or bridge provides the best power conversion efficiency and least
expensive replacement. This units typically cost less than $1,000 for a pole mounted
air cooled model.
New high efficiency solid state switching type rectifiers are now available. Maintenance history should be examined to confirm unit reliability.
The technology that offers the most promise is the pulsed rectifier. Pulsed rectifiers
generate spikes of high current output many times per second. Chevron data shows
that polarization is actually slower, but the final polarized potential is much more
negative. Manufacturers claim that pulse technology uses four times less total
current output and allows the anode bed to be downsized by a comparable amount.
Pulsed rectifiers have been around for a number of years, but were not very cost
effective. Advanced electronic components have reduced the price from over $5,000
to under $2,500. A pulsed rectifier should be considered for deep or closely spaced
well casings or where reducing the anode bed size will provide a significant cost
savings.
August 1999
1.
Thermoelectric generators
2.
3.
1500-18
Chevron Corporation
4.
Solar systems
2.
3.
To minimize interference
Coating well casings that are to be drilled in closely spaced clusters, onshore or
offshore, may be the only method that will allow protection to depth.
Chevron Corporation
1500-19
August 1999
effective coating system. No leaks have been experienced in an area where leak
history with bare casings is significant [7].
During the early 1980s, Sun completed nine of its 11,500 foot wells with FBE
coated casing. Two of the casings were pulled due to non related operational problems and the coating was examined. Other than a few scuffs, the FBE coating was
found to be in excellent condition [2].
In 1981, two Aramco wells were installed with FBE coated surface and intermediate casing to a depth of 4300 feet. The current requirement was reduced over six
times that of similar wells with bare casing strings. Two additional wells in a
closely spaced drilling island were installed with coated surface casings to a depth
of 4,800 feet. Results from the study showed that the closely spaced wells were
protected with less than 10% of the current required for a similar bare steel casing
despite:
1.
2.
3.
External coating has not caught on as a standard operating practice in the oilfield,
but is no longer an experimental technique. These case histories have shown that an
externally coated well casing with a good epoxy system such as FBE makes good
operating sense, especially in congested areas, deep wells, or corrosive areas. In the
August 1999
1500-20
Chevron Corporation
last 20 years the standard industry practice has been to apply an external organic
coating to all new pipelines. At a cost of about $1.75/ft2 for FBE, well casings
should be externally coated, too.
2.
3.
4.
Chevron Corporation
b.
Record date and depth of leak (and other related well data).
c.
Use open hole logs to correlate leaks with specific geologic formations.
d.
e.
b.
c.
d.
b.
c.
d.
e.
b.
c.
Optionally run a CPP log to determine effects from the field wide system.
d.
1500-21
August 1999
1590 References
1.
2.
3.
4.
5.
6.
Davies, D.H., Niina, N., Sasaki, K., and Takeda, J. Diagnostic Surveys for
Well Casing Corrosion, Proceedings of the Second NACE International
Symposium, Milan, Italy, November 1989.
7.
Orton, M.D., Hamberg, A., and Smith, S.N. Cathodic Protection of Coated
Well Casing, Corrosion 87, Paper 66, San Francisco, CA.
8.
9.
August 1999
1500-22
Chevron Corporation