Sei sulla pagina 1di 3

Sweater Operation Breakdown

Breakdown is a listing of the content of a job by elements. A garment consists of some parts and
some group of operations. Breakdown means to writing down all parts and all process/operation
after one another lying with the complete garment according to process sequence.

Armhole Status Point


Jersey

Rib

1st Step: - Needle Selection from both needle bed.

2nd Step: - Needle setting for rib as per buyers requirement

Needle setting by needle selection device

3rd Step: - Prepare rib height by course (c/s) say 10 c/s (Based on WPI, CPI)

A1
18N

B1
Armhole Start Point

C1
Rib

4th Step: - Loop transfer from back needle bed to front needle bed

Needle loop transfer from back to front needle bed by transfer comb.

5th Step: - After transferring the loops knot up to armhole point by number of course.

6th Step: - Prepare armhole point by decreasing or increasing decreasing both demands on
styling.

Decreasing
Increase
Body Panel

7th Step: - Side by side prepare neck drop and finish up to neck line/ shoulder line.
8th Step: - Knit up to neck line/shoulder line
End of Production