Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
CHAPTER 15
TESTING
100mmm
600mm
300 mm
Diameter =16 mm
Tamping rod
200 mm
Slump cone
First the cone placed on a steel plate. Then the cone is filed in three
layers of concrete and each layers tamped 25 terms by using slandered tamping
rod. After tamping, the cone is lifted carefully.
Slump is the difference between the height of the concrete cone and after
removal of the mould. In our site we used 120 mm slump for ready mix
concrete.
Tamping rod
H = Slump
Slump cone
Concrete mixture
Steel plate
Cube test is most commonly using method measuring strength hardened concrete.
The specimens are cast in steel or cast iron mould generally 150 mm cube; but mould should
be in cubical shape.
Before assembling mould in thin oil layer must be applied inside surface of the mould
to prevent the development of bond between the mould and concrete. And cube should be
clamped rigidly because the use of rigidly connected mould is essential for compaction
According to the stranded method the mould must have to filled in the three layers, and each
layer should compacted 25 times of the slandered tamping rod. The final layer should filed to
overflowing and after compaction excess concrete should removed and must be finished by
trowel smoothly. Then the cube should store undisturbed place for 24 hours, and the end of
the period the mould is removed and the cube is further cured in the water tank for 7 days
After that the specimen was crushed by using the crushing machine, and the find the
compressive strength of concrete
Diameter = 20mm
25 x 25mm
150mm
150mm
150mm
TEST CUBE
100mm
300mm
Weight of a tamping bar is 1.8 Kg
TAMPING BAR
A small hole is dug in the compacted material to be tested. The soil is removed and weighed,
then dried and weighed again to determine its moisture content. A soil's moisture is figured
as a percentage. The specific volume of the hole is determined by filling it with calibrated
dry sand from a jar and cone device. The dry weight of the soil removed is divided by the
volume of sand needed to fill the hole. This gives us the density of the compacted soil in lbs
per cubic foot. This density is compared to the maximum Proctor density obtained earlier,
which gives us the relative density of the soil that was just compacted.
15.3 TESTING OF AGGREGATES
Sieves
Preparation
In order to perform the test, a sample of the aggregate must be obtained from the
source. To prepare the sample, the aggregate should be mixed thoroughly and be
reduced to a suitable size for testing. The total weight of the sample is also
required.
Procedure
A suitable sieve size for the aggregate should be selected and placed in order of
decreasing size, from top to bottom, in a mechanical sieve shaker. A pan should
be placed underneath the nest of sieves to collect the aggregate that passes
through the smallest. The entire nest is then agitated, and the material whose
diameter is smaller than the mesh opening passes through the sieves. After the
aggregate reaches the pan, the amount of material retained in each sieve is then
weighed.
NATIONAL DIPLOMA IN ENGINEERING SCIENCES
INSTITUTE OF ENGINEERING TECHNOLOGY, KATUNAYAKE
Results
The results are presented in a graph of percent passing versus the sieve size. On
the graph the sieve size scale is logarithmic. To find the percent of aggregate
passing through each sieve, first find the percent retained in each sieve. To do
so, the following equation is used,
%Retained =
100%
Where WSieve is the weight of aggregate in the sieve and WTotal is the total
weight of the aggregate. The next step is to find the cumulative percent of
aggregate retained in each sieve. To do so, add up the total amount of aggregate
that is retained in each sieve and the amount in the previous sieves. The
cumulative percent passing of the aggregate is found by subtracting the percent
retained from 100%.
%Cumulative Passing = 100% - %Cumulative Retained.
The values are then plotted on a graph with cumulative percent passing on the y
axis and logarithmic sieve size on the x axis.
Engineering applications
Gradation is usually specified for each engineering application it is used for. For
example, foundations might only call for coarse aggregates, and therefore an open
gradation is needed. Gradation is primarily a concern in pavement mix
design. Concrete could call for both coarse and fine particles and a dense graded
aggregate would be needed.