Doc Number
ABS.III.q/TC-008
01 - 02/01/2014
Prepared by
Approved by
Siti Margiastuti
(Act. Leader QC)
Teguh Sudrajat
(Deputy Tech. Manager)
Safety First
Action
1. Selection of Samples
2. Size of Samples
Details
Shall be sampled at the point of manufacture or storage, and at such time as to
allow the tests controlling acceptance or rejection.
liquid materials :
- For routine laboratory examination, 4 L
- From bulk storage, 4 L
- From drums, 1 L
3. Containers
- Shall be wide-mouth jars or bottles made of plastic with lined screw caps, or
plastic-lined triple-seal friction-top containers.D16
- Sample containers shall be new. They shall not be washed or rinsed, or wiped
with an oily cloth.
- Prevent contaminated. Immediately after filling, the container shall be tightly.
- shall be properly marked for identification after filling with a suitable marking on
the container, not on the lid. labels or tags also may be used for identification
Picture
Doc Number
ABS.III.q/TC-008
01 - 02/01/2014
Prepared by
Approved by
Siti Margiastuti
(Act. Leader QC)
Teguh Sudrajat
(Deputy Tech. Manager)
Safety First
Action
Details
The sample may be taken from the sample valve or tap if the tanks are
provided, before the sample is taken,
4 L shall be drawn from the sample valve and discarded.
Samples of liquid may be taken by the dip method using a clean wide-mouth or
friction-top can in a suitable holder as shown in picture, a clean container must be
used to take each sample, and the material sampled shall then be transferred to
another new and clean container for retention or testing sample.
A detachable fitting (similar the picture) may be inserted in the discharge line,
before the sample is taken 4 L shall be drawn from this sampling valve and
discarded
Picture
Doc Number
ABS.III.q/TC-008
01 - 02/01/2014
Prepared by
Approved by
Siti Margiastuti
(Act. Leader QC)
Teguh Sudrajat
(Deputy Tech. Manager)
Safety First
Action
Details
When sampling tankers and barges 4000 m3 or less, capacity, at least five 4-L
samples shall be taken at uniform intervals throughout the entire loading or
unloading, for larger, capacity requires at least ten 4-L samples
Picture