Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
For
THE PROPOSED 4X300 MW COAL BASED THERMAL POWER PLANT
AT BINJKOT, DARRAMURA, BADEJAMPALI AND GINDOLA VILLAGES
IN KHARSIA TEHSIL OF RAIGARH DISTRICT, CHHATTISGARH
Sponsor :
Prepared by :
December, 2008
Table of Contents
_______________________________________________________________
Chapter
Title
Page
_______________________________________________________________
Table of Contents
List of Figures
List of Tables
1.0
Introduction
1.1
1.2
1.3
1.4
1.5
1.6
1.7
1.8
2.0
C1-1
C1-1
C1-2
C1-2
C1-7
C1-7
C1-8
C1-8
4.0
Project Description
2.1
2.2
2.3
2.4
2.5
2.6
2.7
2.8
3.0
TC-1
TC-IV
TC-V
Introduction
General Geology
Meteorology
Air Quality
Water Quality
Soil Characteristics
Noise Level Survey
Flora and Fauna Studies
Landuse Studies on Census
Demography and Socio-economics
C3-1
C3-1
C3-2
C3-14
C3-23
C3-30
C3-34
C3-39
C3-49
C3-55
Introduction
Impacts during Construction Phase
Impacts during Operational Phase
Environmental Management Plan during Construction
Environmental Management Plan during Operation
Greenbelt Development
Cost Provision for Environmental Measures
C4-1
C4-1
C4-4
C4-18
C4-19
C4-27
C4-32
TC-I
6.0
7.0
C6-5
C6-7
C6-7
Introduction
Approach of the Study
Hazard Identification
Hazard Assessment and Evaluation
Disaster Management Plan
Off-site Emergency Preparedness Plan
Occupational Health and Safety
C7-1
C7-1
C7-1
C7-3
C7-14
C7-24
C7-28
C8-1
C8-1
C8-1
C8-2
Administrative Aspects
9.1
10.0
C6-1
C6-1
C6-1
Project Benefits
8.1
8.2
8.3
8.4
9.0
Introduction
Environmental Monitoring and Reporting Procedure
Monitoring Schedule
Monitoring Methods and Data Analysis of
Environmental Monitoring
Reporting Schedules of the Monitoring Data
Infrastructure for Monitoring of Environmental
Protection Measures
8.0
Disclosure of Consultants
C9-1
C10-1
TC-II
AI-1
AII-2
AIII-1
AIV-1
AV-1
AVI-1
AVII-1
AVIII-1
AIX-1
AX-1
TC-III
List of Figures
_______________________________________________________________
Figure
Title
Page
_______________________________________________________________
1.1
1.2
2.1
2.2
2.3
3.3.1
3.3.2
3.3.3
3.3.4
3.3.5
3.3.6
3.4.1
3.5.1
3.6.1
3.7.1
3.8.1
3.9.1
3.9.2
4.1
4.2
4.3
4.4
4.5
4.6
5.1
7.1
7.2
7.3
9.1
C1-3
C1-4
C2-3
C2-7
C2-10
C3-7
C3-8
C3-9
C3-10
C3-11
C3-12
C3-15
C3-26
C3-32
C3-37
C3-43
C3-53
C3-54
C4-8
C4-9
C4-10
C4-17
C4-22
C4-28
C5-4
C7-10
C7-11
C7-23
C9-2
TC-IV
List of Tables
Tables
1.1
1.2
2.1
2.2
2.3
2.4
2.5
2.6
2.7
2.8
3.3.1
3.3.2
3.3.3
3.4.1
3.4.2
3.4.3
3.4.4
3.4.5
3.5.1
3.5.2
3.5.3
3.6.1
3.6.2
3.6.3
3.6.4
3.7.1
3.7.2
3.8.1
3.8.2
3.8.3
3.8.4
3.8.5
3.8.6
3.9.1
3.9.2
3.9.3
3.10.1
3.10.2
3.10.3
3.10.4
Title
Page
C1-5
C1-7
C2-2
C2-4
C2-5
C2-5
C2-6
C2-19
C2-19
C2-20
C3-2
C3-3
C3-6
C3-16
C3-16
C3-17
C3-17
C3-21
C3-24
C3-27
C3-28
C3-30
C3-31
C3-33
C3-34
C3-35
C3-38
C3-41
C3-42
C3-44
C3-45
C3-47
C3-48
C3-49
C3-50
C3-52
C3-55
C3-56
C3-56
C3-57
TC-V
4.1
4.2
4.3
4.4
4.5
4.6
4.7
4.8
4.9
4.10
4.11
4.12
4.13
4.14
6.1
6.2
7.1
7.2
7.3
7.4
7.5
7.6
7.7
7.8
7.9
7.10
7.11
7.12
7.13
7.14
7.15
7.16
Title
Page
C4-5
C4-6
C4-6
C4-6
C4-7
C4-12
C4-13
C4-14
C4-16
C4-16
C4-25
C4-27
C4-29
C4-33
C6-2
C6-4
C7-2
C7-2
C7-2
C7-3
C7-3
C7-3
C7-4
C7-5
C7-6
C7-7
C7-7
C7-7
C7-8
C7-12
C7-13
C7-27
TC-VI
1.0
INTRODUCTION
M/s. SKS Power Generation (Chhattisgarh) Limited (SKSPGCL) is a 100%
subsidiary of M/s. SKS Ispat and Power Ltd (SKSIPL) and is created as an Special
Purpose Vehicle (SPV) for setting up of 1200 MW coal based power plant.
The proposed 4X300 MW (1200 MW) coal based thermal power plant will be
located at Binjkot, Darramura, Badejampali and Gindola villages in Kharsia tehsil
of Raigarh district of Chhattisgarh state.
This chapter describes the purpose of the report, identification of the proposed
project and project proponent, brief description of nature, size and location of the
project and importance to the region and country. This chapter also describes the
scope of the study and details of regulatory scoping carried out as per Terms of
Reference (TOR) issued by Ministry of Environment and Forests (MoEF), New
Delhi.
1.1
1.2
C1-1
It is envisaged that coal for the power plant station would be from Fathepur coal
block and linked to SECL coal mines. Coal from SECL coal mines will be
transported by rail. Coal from Fatehpur coal block will be transported by road.
1.2.2 Project Proponent
The project is promoted by M/s. SKS Power Generation (Chhattisgarh) Limited, a
subsidiary of SKS ISPAT & Power Limited, which is one of the established and fast
growing industry of steel and power sectors.
1.3
1.3.1
Project Cost
The cost of the total project is about Rs.5100 crores, which includes Rs 450 crores
for environmental protection measures. The project will be commissioned within 45
months from the zero date.
1.3.2
1.3.3
1.4
The
the
The
and
C1-2
CHHATTISGARH
PLANT SITE
FIGURE-1.1
LOCATION MAP OF THE PROPOSED POWER PLANT
VIMTA Labs Limited, Hyderabad
C1-3
83 10'
83 15'
22
22
5'
5'
Dengurchua
A
Jhitipali
1
Benjkote
2
Nawagaon
Pamgarh
4 Gindola
Darramura
10 KM
22
22
0'
Chhote Dumarpali
C
Jampali
0'
Naharpali
Kharsiya
Kurubhata
Sendripali
Tilapali
Nawapara
21
21
55'
55'
83 10'
PLANT
83 15'
ASH POND
A : 22 01 40 N, 83 12 09 E
1 : 22 01 23 N, 83 12 36 E
B : 22 00 45 N, 83 11 39 E
2 : 22 01 17 N, 83 12 23 E
C : 21 59 58 N, 83 12 04 E
3 : 21 00 26 N, 83 12 58 E
D : 22 00 56 N, 83 13 15 E
4 : 22 00 32 N, 83 13 10 E
SCALE
1
2 KM
FIGURE-1.2
STUDY AREA MAP (10 KM RADIUS)
VIMTA Labs Limited, Hyderabad
C1-4
TABLE-1.1
ENVIRONMENTAL SETTING OF THE SITE
Sr. No.
1
Particulars
Plant location
Details
At Binjkot, Darramura, Badejampali and Gindola
villages in Kharsia tehsil of Raigarh district of
Chhattisgarh State
A : 22 0140N to 83 1209E
B : 22 0045N to 83 1139E
C : 21 5958N to 83 1204E
D : 22 0056N to 83 1315E
1 : 22 0123N to 83 1236E
2 : 22 0117N to 83 1223E
3 : 22 0026N to 83 1258E
4 : 22 0032N to 83 1310E
4
a)
b)
c)
d)
1602.3 mm
Maximum-41.0 minimum-20.0%
Pre-monsoon: NE and SE
Annual: NE and SW
From 1st March to 31st May 2008
a)
b)
c)
Temperature
Relative humidity
Predominant wind directions
5
6
7
8
9
10
11
12
13
14
15
16
17
C1-5
Sr. No.
18
Particulars
Wildlife sanctuaries, community
reserves
and
conservation
reserves)
Reserved / Protected Forests
Details
6)
7)
8)
9)
10)
11)
12)
Name of the
Forest block
Rabo RF
Taraimal RF
Lotan RF
Urdana RF
PF near
Bendajhariya
village
Burha pahar
RF
Bhalunara RF
PF (Daharidih
village)
Bargarh RF
Endu RF
Panikhet PF
Suhai RF
Distance(km)
Direction
0.8
8.2
6.6
9.2
4.1
NNE
ENE
NNW
E
SW
4.9
SW
5.4
9.3
W
NE
5.3
7.4
8.1
8.9
WNW
NW
NNE
NNE
19
20
21
Seismicity
Defence Installations
Major industries in 15-km radius
22
Socio-economic factors
Note: All distances mentioned are aerial distances; Source: EIA studies, Vimta Labs Limited, Hyderabad
The EIA report is prepared based on one season baseline environmental quality
data as per the guidelines and requirements of MoEF, Central Pollution Control
Board (CPCB) and Chhattisgarh Environment Conservation Board (CECB).
Environmental baseline monitoring has been carried out during pre-monsoon
season (1st March 2008 to 31st May 2008) and used to identify potential
significant impacts. Modelling exercises have been carried out to predict and
evaluate impacts due to proposed power plant. An Environment Management Plan
is included in this report.
The scope of the present study is inline with the TOR as recommended by MoEF
vide letter No. J-13012/164/2007-IA.II (T) dated 9th July 2008.
1.4.1 Study Area for EIA
The study area for the Environment Impact Assessment is 10-km radius area
around the periphery of proposed power plant, ash pond area and township. The
study area is shown in Figure-1.2.
1.4.2
C1-6
1.5
1.6
C1-7
TABLE-1.2
DETAILS OF MONITORING
Sr.
No.
1
1.7
Attribute
Parameters
Frequency of Monitoring
Meteorology
Wind
Speed, Direction,
Temperature,
Relative
Humidity,
Rainfall
&
duration and other non
instrumental observations
Water quality
Physical,
Chemical
and
Bacteriological Parameters
Ecology
Noise levels
Existing
terrestrial
and
aquatic flora and fauna
Noise levels in dB(A)
Soil characteristics
Land use
Socio-economic aspects
Geology
10
11
Risk
assessment,
Disaster
Management
Plan and Occupational
Health and Safety
Socio-economic
characteristics, labour force
characteristics
Geological history
Drainage area and pattern,
nature of streams, aquifer
characteristics,
recharge
and discharge areas
Identify
areas
where
disaster can occur and
identify
areas
of
occupational hazards.
Based on assessment
C1-8
1.8
C1-9
C1-10
2.0
PROJECT DESCRIPTION
This chapter deals with the technical details of the proposed power plant, details of
infrastructure, various sources of pollution and the measures proposed to control
pollution.
2.1
2.2
2.3
C2-1
Kharsia tehsil of Raigarh district, having major favourable features along with
good environmental features, has been identified for the proposed project.
The proposed site is about 15.0-km away from the nearest national highway, NH200. The state capital city Raipur is about 190-km away from the site. The
nearest airport at Raipur is about 190-km. The proposed plant layout is
presented in Figure-2.1 respectively.
Layout of the power plant has been optimised considering the space requirements
for all the equipment, systems, buildings, structures, coal storage area including
railway and marshalling yard, ash silos, raw water storage tank, water treatment
plant, cooling water pump house etc. Necessary plant drainage system would be
provided at the proposed power plant site. In laying out various facilities,
following general aspects have been taken into consideration:
Provision to install 4X300 MW;
Coal storage yard for 15 days requirement at site for 1200 MW;
Ash silos for fly ash;
Predominant wind directions as shown in the wind rose to minimise pollution,
fire risk etc;
Raw water supply and storage facilities; and
Availability of adequate space for fabrication / construction equipment.
All facilities of the plant area will be laid out in close proximity to each other to
the extent practicable so as to minimize the land requirement. The layout
facilitates movement of men and materials between the various facilities both
during construction and operation.
2.4
Features
Capacity
Configuration
Type of boilers
Power evacuation
Fuel
Source of Coal
Coal Requirement
Sulphur content
Ash Content in Coal
Ash generation
Bottom Ash
Fly Ash
ESP efficiency
Stack
Water Requirement
Description
1200MW
4X300
Pulverized coal fired sub-critical boilers
Power will be evacuated into PGCILs grid and CSEBs
grid through 400 KV level
Coal
Coal for the plant would be linked to SECL coal mines
6.02 MTPA
0.35%
41%
2.47 MTPA
0.49 MTPA
1.98 MTPA
99.99%
Two 275-m height multi- flue stacks
C2-2
Chapter-2
Project Description
FIGURE-2.1
PLANT LAYOUT SHOWING VARIOUS FACILITIES
VIMTA Labs Limited, Hyderabad
C2-3
About 960 acres of land had been considered for the project. Land requirement of
a power project as per the Norms of Central Electricity Authority (CEA) is 1 acre
per MW of power generation including 100 acres for Residential Township.
TABLE-2.2
BREAK-UP OF LANDUSE
Sr.No
Particulars
1
2
3
4
7
8
Misc Area
Greenbelt
9
10
2.4.2
Area
(Acres)
72
100
24
50
42.5
66
58
137.5
550
310
Basis / Workings
As per requirement
Water Storage for 7 days requirement
with water reservoir of 3m depth.
As per CEA Guidelines
As per CEA Guidelines
Coal Stock Storage for 30 days
requirement with Pile length of 650m.
For Considered 2 wagon Tipplers and
one Fuel oil unloading lines.
As per requirement.
Green Belt = 1/3 of
(1+2+3+4+5+6+7+8+9)
For considered, 25 years of Bottom
Ash & 3 years of Fly Ash storage.
100
960
C2-4
Parameter
Design Quality
Worst Quality
3850
41.0
22.5
25.5
11.0
25.5
2.6
4.9
0.35
3200
46.5
20.0
20.5
13.0
20.5
2.2
4.0
0.4
GCV, Kcal/kg
Ash, %
Volatile matter, %
Fixed carbon, %
Moisture, %
Carbon,%
Hydrogen,%
Nitrogen,%
Sulphur, %
TABLE-2.4
TYPICAL CHARACTERISTICS OF HEAVY FUEL OIL (HFO)
Sr. No.
1
2
3
4
5
6
Parameter
Total Sulphur content
Gross Calorific Value
Flash Point (Min)
Ash Content by weight (Max)
Pour Point (Max)
Specific heat (kCal/kg. oC)
Characteristics
(IS1953, Grade HV)
4.5% (Max)
About 11,000
66 Deg C
0.1%
24 oC (Max)
0.5
TABLE-2.4 (A)
TYPICAL CHARACTERISTICS OF LIGHT DIESEL OIL (LDO)
Sr. No.
1
2
3
4
5
6
Parameter
Pour point
Kinematic viscosity 38 oC
Water content, % by volume
Total sulfur by mass (max)
Ash (%by mass) Max
Flash point (min)
Characteristics
12oC & 18 oC for summer
and Winter
2.5 to 15.7
0.25
1.8
0.02
66 oC
C2-5
Units
1
2
3
4
Water
Requirement
3185
120
8
8
8
8
152+8=160
300
10
150
55
40
75
200
75
177
4427
41
4468
approximately
(4500 )
Mahanadi river is a perennial river with a huge catchment area. The state
government has already given permission to draw 35 Million Cubic Meters (35MCM) per annum of water to meet the requirement of 1200 MW from the
Mahanadi river. Adequate water is available throughout the year for the total
water requirement to meet the consumptive needs. Copy of Government order on
water allotment is enclosed as Annexure-III.
C2-6
MAHANADI RIVER
(2X100% SG FILL)
2X100% (TYP)
POTABLE WATER PUMPS 3X50% (TYP.FOR EACH UNIT)
H/W M/W UNIT#1
F.W OH
PLANT(20 Cu. M/Hr)
75m3
INTAKE PUMP HOUSE
4468
107240
PLANT MAKE-UP
WATER PUMPS
3 nos.(2W+1SB)
RAW WATER
STORAGE
RESERVIOR
1.0Milion Cu.m
60
D.M.F
3x50%
1000
160
3840
A.C.F
3x50%
D.M.W
S.T
2X1000m3
D.M.P
3x50%
TO REGENERATION
4427
106240
CLARIFIER
2 Nos.
2400 m3/Hr.
(EACH)
4250
SSF DRAINS
SP/THICKNER/
CENTRIFUGE
160
3840
462.5
11100
384
60
180
NEUTRALISING PIT
2 COMPARTMENTS
TOTAL:750 Cu.M
REF.NOT 4
470
11280
2X100%
EACH: 50 Cu.M/Hr.
3x50%
EACH:50 M3/Hr.
2X100%
4250
101990
180
470
11280
3x50%
SUPPLY PUMPS
GARDENING
SERVICE WATER,
GREEN BELT DEVELOPMENT
REF.NOT 2
TO ASH DISPOSAL AREA 2X100%
PUMPS
C.M.B
CAP:Min.2500 Cu.M
LEGEND
FROM UNIT # 4
E+D=654
E+D=654
E+D=654
REF.NOT 2
TO ASH DISPOSAL AREA
S.W PUMPS
FIRE FIGHTING SYSTEM
2X100%
EACH:200m3/Hr.
3165
76430
NDCT-4
NDCT-3
NDCT-2
NDCT-1
TO ASH
POND
S.G B/D FROM
2 UNITS
FROM UNIT # 1
B/D #1
126
CW M/U
B/D TANK
2X100%
SUPPLY PUMPS
COLLECTION
SUMP
38800
S.W
O.H
TANK
CAP:750m3
EXCESS
E+D=654
CHS
595
14280
AHS
PLANT WASH
IBD QUENCHING
150
3600
CCW PUMPS
2 X 100%
2700 m3/hr
PER UNIT
TOTAL 8 Nos.
TRANSFORMER
YARD DRAINS
CWPH
HVAC M/U
75
1800
CW FOR CLINKER
GRINDERS
55
1320
S.S.F
10X150m3/Hr
CONDENSER
38800
PLANT WASHING
& GRINDING
75
1800
1550
36100
CW PUMPS
2X50% PER UNIT
+
2X50% COMMON S/B
TOTAL 10 Nos.
UNIT #1
38800
FOR UNIT#2
38800
FOR UNIT#3
COAL PILE
RUN OFF
RECOVERED
ASH WATER
SG AUXILIARIES
TG AUXILIARIES
AIR COMPRESSORS
ASH HANDLING
STSTEM
FOR UNIT#4
UNIT #1
2700
200
4800
3 X50%
ACW BOOSTER PUMPS
FOR UNIT#2
OTHER SERVICES
BACKWASH WASTES TO
SLUDGE PIT
E.T.P
CLARIFIER
+
O.W.S
D.M
CLR
W.S.
D.M.F
F.W.O.H
A.C.F
D.M.P
D.M.W.S.T
C.S.T
TO
S.G
SLUDGE PIT H/W
M/U
SSF
ETP
S.P
S.W
O.H
C.W
NDCT
B/D
FPS
CHS
AHS
OWS
ACW
T.G
P.H.E
HAVE
BA
CEP DISCHARGE,
HOTWELL &
BFP PUMPS
PHE
2 X 50%
C.S.T
2 Nos.
CAP.EACH
1000 m3
ACW OHT
1 No.
CAP.,EACH:
15 m3
DE MINERALISED
CLARIFIER
WATER STORAGE TANK
DUAL MEDIA FILTER
FILTER WATER OVERHEAD TANK
ACTIVATED CARBON FILTER
DEMINERALISATION PLANT
DE MINERALISED WATER
STORAGE TANK
CONDENSATE STORAGE TANK
STEAM GENERATOR
HOT WELL
MAKE UP
SIDE STREAM FILTERATION
EFFLUENT TREATMENT PLANT
SLUDGE PIT
SERVICE WATER
OVER HEAD
CLARIFIED WATER
NATURAL DRAFT COOLING TOWER
BLOW DOWN
FIRE PROTECTION SYSTEM
COAL HANDLING SYSTEM
ASH HANDLING SYSTEM
OILY WATER SEPRERATOR
AUXILLARY COOLING WATER
TURBINE GENERATOR
PLATE HEAT EXCHANGER
HEATING VENTILATION & AIR
CONDITIONING
BOTTOM ASH
m3/hr
m3/day
NOTE
1.ALL FLOW CAPACITIES INDICATED ON FLOW LINES IN m3/hr.
2.THIS OPTION SHALL BE ADOPTED IN CASE QUALITY IS UNSUITABLE FOR REUSE.
3.CLARIFIED WATER TANK SHALL BE ABOVE GROUND,SO THAT CW MAKE-UP
FLOW IS BY GRAVITY.
4.ZERO DISCHARGE CONCEPT WITH SOLID WASTE MANAGEMENT SHALL BE ADOPTED.
FOR UNIT#3
FOR UNIT#4
TO C.M.B
FIGURE-2.2
WATER BALANCE DIAGRAM
VIMTA Labs Limited, Hyderabad
C2-7
2.4.4 Manpower
The proposed power plant will require 400 skilled and semi-skilled personnel
during operation, maintenance and administration of the proposed plant of 4X300
MW. People from neighbouring villages, if found suitable, shall be employed
during construction and operational phases. The total manpower of power plant
during operational period is estimated to be about 400 persons.
2.4.5 Township
It is estimated that about 70% of the total employees would be provided with
residential accommodation in the township of the station. It is therefore, proposed
to build residential quarters for a total of 400 employees. The township will
include the residential quarters (type A,B,C,D), one project hostel, guest house,
recreation facilities, health centre, shopping facilities, open air theatre, bank and
post office.
2.4.6 Transport Facilities
The nearest State Highway is at a distance of 1.7-km distance by road and the
nearest railway station (Robertson RS) is at about 2.4-km and Bhupdeopur
railway station is about 5.9-km from the site. Coal will be received at the site by
belt conveyor/dedicated railway line.
2.4.7 Health and Sanitation
To ensure optimum hygienic conditions in the plant area, proper drainage
network will be provided to avoid water logging and outflow. Adequate health
related measures and a well equipped safety and environment department will be
provided to ensure clean and healthy environment.
2.5
C2-8
Condenser
The supply would be complete with divided flow, double pass, horizontal, surface
type, water cooled condenser with closed cycle circulating clarified water system.
Condenser unit would be transverse mounted and would condense exhaust
steam by circulation of cooling water (inlet design temperature of 32 oC) in a
recirculating cooling water system using cooling towers. Necessary air evacuation
system will be provided. The condenser would be provided with 2 X 100%
capacity vacuum pumps or steam jet air ejectors to remove non-condensable
gases and maintain vacuum in the condenser at the desired level.
C2-9
C2-10
STACK
ID FAN
Compressed
Air
ELECTRICITY
BOILER
TURBINE
Coal
GENERATOR
COOLING
TOWER
CONDENSER
OIL
HP
HEATERS
AIR
HOT WELL
FD FAN
MAKEUP
WATER
CHEMICAL
DOSING
ACW SYSTEM
DEAERATOR
WATER
FROM
LP
HEATERS
WATER
TREATMENT
PLANT
FILTER
BACKWASH
FIGURE 2.3
TYPICAL PROCESS FLOW SCHEME FOR PROPOSED THERMAL POWER PLANT
VIMTA Labs Limited, Hyderabad
C2-11
C2-12
Building blocks;
Light weight aggregates;
Partial cement replacement;
Road sub-base;
Grouting material;
Filler in asphalt mix for roads;
Partial replacement of lime aggregate in concrete work;
Road embankment; and
Land filling material.
C2-13
Clarifier;
Pre-treatment plant (filtration plant); and
Demineralisation plant.
DM Plant Feed Pumps and Potable Water Supply Pumps will supply the water
through their respective pressure filtration system for further use. The potable
water will be pumped to the over head tanks and from these tanks potable water
will be distributed by gravity to the consumer points. Water will be chlorinated
before storing in the tanks.
2.6.3 Cooling System for Water
Natural draft cooling towers have been proposed for thermal power plant. The
towers shall be suitably located away from electrical installations and major
structures and are laid along prevailing wind direction to ensure minimum
recirculation and ingress of drift to other areas. The cooling water will have
multiple cells with film type fill material.
2.6.4
C2-14
water will pass through cation resin beds, demineralised water, anion resin beds
and mixed bed exchangers and the demineralised water will be stored in DM
water storage tanks. The acid and alkali handling system will be suitably provided
for the proposed new DM plant.
2.6.7 Chemical Feed System & Chemical Dosing system
Chemical feed system will be provided for feeding with tri sodium phosphate in
the boiler drum and neutralizing amines and/or hydrazine. In the condenser
pump discharge/ boiler feed suction line to maintain the chemical concentration in
the drum water and feed water within permissible limits for trouble-free operation
of the plant.
In circulating cooling water system shock chlorination alternatively sodium
hypochlorite dosing would be provided to contain algae growth. Dosing of proven
corrosion and scale inhibitor chemicals, acid dosing system shall also be provided
for cooling water treatment. Continuous chlorination will be required for the
potable water system.
The low pressure chemical dosing system will consist of:
C2-15
evaporative
cooling
has
been
2.6.10.2 ESP Control Building (Expect Control Room) & HP Control Room
For ventilation of these buildings, ambient air will be drawn through unitary air
filtration unit comprising fresh air intake louver, dry type filter and spry nozzle
and supplied to the space by means of centrifugal fans through ducting, grills etc.
2.6.10.3 Other Buildings
Other buildings like air compressor room, A/C plant room, CW pump house, coal
handling plant, DM plant etc will be ventilated by means of dry system comprising
axial flow fans, dry filter wherever required, cowls, ducting etc. Inside dry bulb
temperature is expected to be higher than ambient by about 50C. Fire dampers
will be provided as per code wherever there is electrical installation.
2.6.11 Fire Protection System
For protection of the plant against fire, all yards and plant will be protected by
any one or a combination of the following systems:
Hydrant System;
Automatic high velocity and medium velocity sprinkler system;
Water spray (emulsifier system);
Foam system;
Portable and mobile chemical extinguishers; and
Auto modular CO2 system.
C2-16
Back up operation and Indications are envisaged for essential trip operations
of the power and electrical system from control desk, which will be located on
one side of operators control desk. Direct indications such as Boiler Drum
C2-17
level etc. and any other emergency operation facility have been envisaged
from control desk.
2.7
Sources of Pollution
The various types of pollution from the proposed power plant are categorized
under the following types:
Air pollution;
Water pollution;
Solid waste; and
Noise pollution.
The major type of pollution from the power plant is gaseous emissions. In
addition, wastewater and solid waste will also be generated. The quantities and
the composition of the gaseous, liquid and solid waste that are likely to be
generated in the plant will be managed and treated such that their final disposal
into the environment meets all the statutory requirements and thus the
environmental impacts are minimized.
2.7.1 Air Emissions
The major pollutants emitted from the power plant stack will be SO2, NOx and
particulate matter. Proper control measures as described below will be installed to
minimize the stack emissions within the stipulated/permissible limits prescribed
by National Ambient Air Quality Standards.
Suspended Particulate Matter (SPM) is one of the important pollutants from the
proposed power plant. High efficiency (>99.9%) electrostatic precipitators are
proposed to be installed to limit the particulate matter emissions to below 50
mg/Nm3.
Sulphur dioxide
The sulphur content in coal is about 0.4%. Two stacks multi flue of 275-m height
will be provided, as per CPCB/MoEF Norms, to disperse the gaseous emissions.
Oxides of Nitrogen
To reduce the NOx emissions from the steam generator, all provisions in the
steam generator design and fuel firing system will be made. Necessary
confirmation from the boiler manufacturers regarding concentration from stack
will be less than 350 mg/Nm3 generation of NOx would be taken as a measure to
control production of this pollutant right at the source. The details of stacks and
emission rates are presented in Table-2.6. The emission rate calculations are
given in Annexure-IV.
C2-18
Thermal Pollution
Heat loss through the stack represents only about 8% to 10% of the total heat
input to the furnace. The quantum of heat so lost to the atmosphere is not
significant. It may further be noted that the area is subjected to moderate wind
speed and good rainfall.
The effect of tall chimneys, which are being installed primarily to take care of the
gaseous discharges, would also indirectly help in diffusing the thermal pollution.
Due to the high kinetic energy gained by the flue gases issuing from the stack,
the effective rise of the plume would ensure discharge of flue gas at a
considerably higher stratum ensuring dilution of the gas dispersed leaving the
local environment virtually unaffected.
TABLE-2.6
STACK DETAILS AND EMISSION RATES
Sr. No.
1
2
3
4
5
6
7
a
b
c
Parameters
Stack Height
No. of flues
Top diameter of each flue
Flue gas velocity in each flue
Flue gas temperature
Flow rate of gas in each flue
Coal Consumption
Sulphur dioxide (SO2) emission rate (Based
on 0.4 of Sulphur) in each flue
Particulate matter (SPM) emission rate in
each flue
Oxides of Nitrogen (NOx)
Units
m
No.
m.
m/s
o
K
Nm3/s
TPH
g/s/flue
Stack-I
275
2
7.0
25.0
413
694.3
760.1
422.3
Stack-II
275
2
7.0
25.0
413
694.3
760.1
422.3
mg/Nm3
g/s/flue
g/s/flue
mg/Nm3
50
34.7
243.0
350
50
34.7
243.0
350
C2-19
TABLE-2.7
WATER BALANCE OF THE PROPOSED POWER PLANT
Sr.
No
1
2
3
4
5
6
7
Units
Cooling tower makeup
Domestic consumption colony
Domestic consumption Plant
Service water/HVAC
Boiler make up
DM plant Regeneration
Contingency water
Loss in pre treatment /
evaporation
Total
Requirement
3185
280
20
16
190
160
10
405
218
150
120
0
350
41
40
40
10
55
177
4468
3780
688
The generated wastewater to a maximum extent will be used for ash handling
plant, coal handling plant and green belt and the remaining net treated
wastewater will be sent for disposal. The disposal water will meet the general
standards of wastewater discharge.
Adequate storm drains will be constructed along the boundary of the plant area
and within the plant area to drain off the storm water during monsoon period.
2.7.3 Solid Waste Generation in Power Plant
Ash is the main solid waste generated in the coal based thermal power plant. The
primary fuel for the proposed power project would be coal from SECL fields,
having an ash content of about 41%. Considering this, about 2.47 MTPA and 1.98
MTPA of fly ash and bottom ash will be generated.
Major portion of the ash will be utilized by supplying to potential users. Efforts will
be made to utilize 100% fly ash as per the Fly Ash Notification, 1999 and as
amended later.
The ash which is not lifted by the potential user will be disposed off in the ash
dyke using dry system of fly ash collection. The fleet of bulkers/trucks will dump
the ash in the ash dyke. Water sprinklers will be provided at the ash dyke to
sprinkle water for suppression of dust generated. We are also envisaging for fly
ash fine grinding system to fine grind it and send to oversees market- ready mix
to cement.
2.7.4 Noise Pollution
The noise levels expected from various noise generating sources in the proposed
plant are given in Table-2.8.
C2-20
TABLE-2.8
SOURCE NOISE LEVELS IN THE PROPOSED PLANT
Sr. No.
1
2
3
4
5
Unit
Turbine unit
Cooling tower
Air compressors
Transformer
Boilers
Noise Control
Acoustic enclosures will be provided wherever required to control the noise level
below 85 dB(A). Anywhere not possible technically to meet the required noise
levels, personal protection equipment will be provided to the workers. The wide
greenbelt around the plant will work as green mufflers to attenuate the noise
level dissemination outside the plant boundary.
2.8
2.8.2
2.8.3
C2-21
attenuate the noise levels and provision of earplugs to the workers working in high
noise level area is proposed.
2.8.4
C2-22
3.0
3.1
Introduction
A regional background to the baseline data is being presented at the very outset,
which will help in better appreciation of micro-level field data generated on
several environmental and ecological attributes of the study. The physical
environment consisting of geology, hydrogeology and water resources form the
first section of this baseline chapter. The second part contains micro-meteorology,
ambient air quality, water quality, soil quality and noise levels and field
investigations of aquatic and terrestrial ecology in the study area generated from
1st March to 31st May 2008 representing pre-monsoon season. The third section
is on land use pattern and socio-economic profile of the project site.
3.2
General Geology
The proposed power plant is located at Binjkot, Darramura, Badejampali and
Gindola villages in Kharsia tehsil of Raigarh district of Chhattisgarh state.
General topography of the area around the plant site is plain with a general
elevation of about 230-m aMSL.
The basin is an integral part of Gondwana super group (Mesozoic and Paleozoic)
and Archaean group. The geological succession is presented below:
GEOLOGICAL SUCCESSION
Age
Mesozoic
Paleozoic
Group Formation
Gondwana Super
Group
Alluvium/ Colluvium
Supra Barakars
Barakars
Talchir
C3-1
3.3
Meteorology
The meteorological data recorded during the study period is very useful for proper
interpretation of the baseline information regarding proposed plant area and
surrounding area for air quality dispersion. Historical data on meteorological
parameters will also play an important role in identifying the general
meteorological regime of the region.
The year may broadly be divided into four seasons:
Winter season
Pre-Monsoon season
Monsoon season
Post-Monsoon season
:
:
:
:
December to February
March to May
June to September
October to November
3.3.1 Methodology
The methodology adopted for monitoring surface observations is as per the
standard norms laid down by Bureau of Indian Standards (IS : 8829) and India
Meteorological Department (IMD). On-site monitoring was undertaken for various
meteorological variables in order to generate the site-specific data. Data was
collected every hour continuously from 1st March to 31st May 2008 representing
pre-monsoon season.
3.3.1.1Methodology of Data Generation
The Central Monitoring Station (CMS) equipped with continuous monitoring
equipment was installed on top of a residential building at a height of 3.0 m
above ground level to record wind speed, direction, relative humidity and
temperature. The meteorological monitoring station was located in such a way
that it is free from any obstructions and as per the guidelines specified under IS:
8829. Cloud cover was recorded by visual observation. Rainfall was monitored by
rain gauge.
The continuous recording meteorological instrument of Dynalab, Pune (Model
No.WDL1002) has been used for recording the met data. The sensitivity of the
equipment is given in Table-3.3.1.
TABLE-3.3.1
SENSITIVITY OF METEOROLOGY MONITORING EQUIPMENT
Sr. No.
1
2
3
Sensor
Wind Speed Sensor
Wind Direction Sensor
Temperature Sensor
Sensitivity
0.02 m/s
3 degrees
0.2oC
3.3.1.2Sources of Information
Secondary information on meteorological conditions has been collected from the
nearest IMD station at Raigarh. The available meteorological data of IMD, Raigarh
has been collected for the period 1986-2001 and analyzed.
VIMTA Labs Limited, Hyderabad
C3-2
IMD data from Raigarh has been collected for pressure, temperature, relative
humidity, rainfall, evaporation, wind speed and direction. The data at IMD is
usually measured twice a day viz., at 0830 and 1730 hr.
3.3.2 Presentation of Data
3.3.2.1Meteorological Data Recorded at IMD, Raigarh
The data collected from IMD includes wind speed, wind direction (recorded in
sixteen directions), temperature, relative humidity, atmospheric pressure; rainfall
and cloud cover over a period of 15 years from the year 1986-2001. The monthly
maximum, minimum and average values are collected for all the parameters
except wind speed and direction. All these parameters are recorded twice a day
viz at 0830 and 1730 hours. The collected data is tabulated in Table-3.3.2.
1] Temperature
The winter season starts from December and continues till the end of February.
December and January are the coolest month with the mean daily maximum
temperature in winter season is 31.60C (in the month of February) and the mean
daily minimum temperature at 13.20C (in the month of January). Both the night
and day temperatures increase rapidly during the onset of the pre-monsoon
season from March to May. During pre-monsoon season, the mean maximum
temperature (May) was observed to be 42.60C with the mean minimum
temperature (March) at 20.40C. The mean maximum temperature in the monsoon
season was observed to be 38.00C in the month of June whereas the mean
minimum temperature was observed to be 24.50C in the month of September. By
the end of August, the day temperatures increase slightly, with the mean
maximum temperature at 32.40C in the month of October and the night
temperature decreases with the mean minimum temperature at 17.10C in the
month of November. The monthly variations of temperature are presented in
Table-3.3.2.
2] Relative Humidity
The air is generally humid in this region during the monsoon season when the
relative humidity at 0830 hr was observed to be 86.0%. Similarly, at 1730 hr, the
relative humidity was observed to be of 78.0%. Generally, the weather during
other seasons was observed to be dry. The monthly variations in the relative
humidity are presented in Table-3.3.2.
TABLE-3.3.2
CLIMATOLOGICAL DATA
STATION: IMD, RAIGARH (1986-2001)
Month
January
February
March
Atmospheric
Pressure (mb)
8:30 hr
17:30 hr
991.6
987.6
989.6
985.5
987.3
982.7
Temperature
(0C)
Max
Min
28.3
13.2
31.6
16.0
36.0
20.4
Relative Humidity
(%)
8:30 hr 17:30 hr
61
40
53
30
41
23
Rainfall
(mm)
11.2
15.7
22.4
C3-3
Month
April
May
June
July
August
September
October
November
December
Atmospheric
Pressure (mb)
8:30 hr
17:30 hr
983.9
978.7
979.5
974.4
976.2
972.2
976.2
973.2
977.2
974.2
980.8
977.3
986.4
982.8
990.4
986.7
992.2
988.3
Temperature
(0C)
Max
Min
40.3
25.1
42.6
28.0
38.0
27.1
31.6
24.7
31.1
24.7
32.2
24.5
32.4
22.0
30.3
17.1
28.2
13.3
Relative Humidity
(%)
8:30 hr 17:30 hr
38
20
40
21
63
50
85
76
86
78
81
73
71
59
61
47
62
44
Total Rain fall
Rainfall
(mm)
13.8
17.5
199.0
453.8
494.5
287.2
49.1
3.7
4.1
1602.3
3] Atmospheric Pressure
The maximum pressure observed were 992.2 mb at 0830 hr and 988.3 mb at
1730 hr, with the maximum pressure occurring during the winter season, in the
month of December. The minimum pressure observed were 976.2 mb at 0830
and 972.2 mb at 1730, with the minimum pressure occurring during the month of
June and July in the monsoon season. The average pressure level was found to be
984.3 mb at 0830 hr and 980.3 mb at 1730 hr. It can be seen from the data that
not many variations are observed in the average atmospheric pressure levels. The
pressure levels are found to be fairly consistent over the region. The monthly
variations in the pressure levels are presented in Table-3.3.2.
4] Rainfall
The average annual rainfall based on the 15 year IMD data, was observed to be
1602.3 mm. The monsoon sets in the month of June and continues till September
and sometime extends up to mid October. The maximum amount of rainfall
(494.5mm) occurs in the month of August. The maximum number of rainy days
was observed in the month of July. Monthly variations in the rainfall are given in
Table-3.3.2.
5] Cloud Cover
During the winter and the pre-monsoon seasons, it was observed that the skies
were generally very clear. In the post-monsoon season, generally light clouds
were observed in the evenings, with clear mornings. During the monsoon season,
both in the mornings and evenings, the skies were found to be generally clouded.
6] Wind Speed/Direction
Generally, light to moderate winds prevail throughout the year. Winds were light
and moderate particularly during the morning hours, while during the afternoon
hours the winds were stronger. The season wise discussion of the respective wind
pattern is given as below:
C3-4
C3-5
1]
Temperature (0C)
Max
Min
37.6
21.3
40.2
24.1
42.0
28.5
Rainfall (mm)
Nil
Nil
Nil
Temperature
Relative Humidity
During the period of observation, the Relative Humidity recorded ranged from
20.3% to 41.3%. Maximum humidity was observed during the month of March.
3]
Rainfall
Cloud Cover
The clear skies were observed mostly during the study period.
5]
Wind Speed/Direction
The wind rose for the study period representing pre-monsoon season is shown in
Figure-3.3.6. A review of the wind rose diagram shows that predominant winds
are mostly from NE (20.6%) followed by SW (18.6%) and NW (17.4%) direction.
The winds in other directions are NNW (1.6%), N (1.8%), NNE (0.7%),ENE
(2.8%),E (5.1%),ESE (2.0%),SE (6.3%),SSE (1.7%),S (4.6%),SSW
(1.4%),WSW (2.9%),W (4.6%),WNW (1.7%) and
6.2% of the total time.
C3-6
FIGURE-3.3.1
WIND ROSE-PRE-MONSOON (IMD- RAIGARH)
VIMTA Labs Limited, Hyderabad
C3-7
FIGURE-3.3.2
WIND ROSE-MONSOON (IMD- RAIGARH)
VIMTA Labs Limited, Hyderabad
C3-8
FIGURE-3.3.3
WIND ROSE-POST-MONSOON (IMD- RAIGARH)
VIMTA Labs Limited, Hyderabad
C3-9
FIGURE-3.3.4
WIND ROSE-WINTER (IMD- RAIGARH)
VIMTA Labs Limited, Hyderabad
C3-10
FIGURE-3.3.5
WIND ROSE-ANNUAL (IMD- RAIGARH)
VIMTA Labs Limited, Hyderabad
C3-11
FIGURE-3.3.6
SITE SPECIFIC WIND ROSE (PRE-MONSOON SEASON, 2008)
VIMTA Labs Limited, Hyderabad
C3-12
3.3.2.3 Comments
The India Meteorological Department (IMD) records the data at two times a day viz.
0830 hr and 1730 hr while the site specific data has been recorded at an hourly
interval. On comparison of site specific data generated for study period vis--vis the
IMD data, slight variations were found. The following observations are brought out:
The temperature recorded on site when compared vis--vis the IMD data, slight
variations were found. The maximum and minimum temperatures recorded at
site during study period were 42.0oC and 21.3 oC, whereas the maximum and
minimum temperature recorded at IMD, Raigarh for the same season are 42.6oC
and 20.3oC respectively;
The relative humidity was observed to range from 20.3% to 41.3% during the
study period whereas according to IMD Raigarh data the relative humidity was
observed to range from 20.4% to 41%. The variation could be because of the
fact that the RH values considered for the site are actual values while the range
of IMD, Raigarh data represents the average values for 30 year period.
The data generated at continuous monitoring station at project site when compared
with the data recorded at IMD, it can be observed that the data generated at the
site is broadly compatible with regional meteorology, except minor variations as
descried above.
C3-13
3.4
Air Quality
The ambient air quality with respect to the study zone of 10-km radius around the
proposed plant site forms the baseline information. The various sources of air
pollution in the region are industrial, traffic, urban and rural activities. This will also
be useful for assessing the conformity to standards of the ambient air quality during
the plant operation. The study area represents mostly rural environment.
This section describes the selection of sampling locations, methodology adopted for
sampling, analytical techniques and frequency of sampling. The results of
monitoring carried out during study period are presented in Annexure-V.
3.4.1
Ambient Air Quality Monitoring (AAQM) stations were set-up at Twelve locations
with due consideration to the above mentioned points. Table-3.4.1 gives the
details of environmental setting around each monitoring station. The location of the
selected stations with reference to the plant boundary is given in the same table
and shown in Figure-3.4.1.
3.4.1.2 Frequency and Parameters for Sampling
Ambient air quality monitoring was carried out at a frequency of two days per
week at each location representing pre-monsoon season. The baseline data of air
environment was generated for the following parameters:
C3-14
FIGURE-3.4.1
AIR QUALITY SAMPLING LOCATIONS
VIMTA Labs Limited, Hyderabad
C3-15
TABLE-3.4.1
DETAILS OF AMBIENT AIR QUALITY MONITORING LOCATIONS
Station
Code
AAQ1
AAQ2
AAQ3
AAQ4
AAQ5
AAQ6
AAQ7
AAQ8
AAQ9
AAQ10
AAQ11
AAQ12
Plant site
Near forest boundary
(near Gindola village)
Gindola village
Naharpali village
Kurabhata village
Bade Jampali village
Daramurra village
Near Chotta
Dumarpali village
Pamgarh village
Jhintipalli village
Binjkot village
Dengurchua village
Distance
from Plant
Boundary
(km)
1.3
Direction
w.r.t. Plant
Boundary
Environmental
Setting
Remarks
NE
Residential
Residential
Up wind
0.9
2.2
1.9
0.7
0.4
2.6
E
SE
SSE
S
SW
SW
Residential
Residential
Residential
Residential
Residential
Residential
Cross
Down
Cross
Down
Down
Down
1.8
0.7
0.4
3.7
W
NW
N
NE
Residential
Residential
Residential
Residential
Cross wind
Up wind
Up wind
Up wind
wind
wind
wind
wind
wind
wind
Sampling Frequency
24 hourly sample twice a week for Three months
24 hourly sample twice a week for Three months
24 hourly samples twice a week for Three months
24 hourly samples twice a week for Three months
8 hourly samples for 24 hour twice a week for Three
months
24 hourly sample twice a week for Three months
C3-16
gaseous pollutants like SO2 and NOx. Pulse pump and mylar bags were used for
collection of carbon monoxide. Gas Chromatography techniques have been used for
the estimation of CO.
3.4.3
3.4.4
Instrument Name
Spectrophotometer
Electronic Balance
Gas Chromatograph
With FID, pFPD, ECD
Parameters
SO2, NOx, O3
TSPM, RPM
CO
Parameter
Technique
IS-5182 (Part-IV)
5.0
IS-5182 (Part-II)
4.0
4
5
Oxide of Nitrogen
Carbon Monoxide
IS-5182 (Part-IV)
Total Suspended
Particulate Matter
Respirable Particulate
Matter
Sulphur dioxide
Minimum
Detectable
Limit
(
g/m3)
5.0
IS-5182 (Part-VI)
IS-5182 (Part-X)
4.0
12.5
Ozone (O3)
ASTM-D 5011-92
1.0
3.4.5
Technical Protocol
C3-17
represents up wind to the plant site and residential and rural activities prevail in
the surroundings of monitoring location.
AAQ-3: Gindola Village
The sampler was placed on top of a residential building at a height of about 4.0 m
from the ground level and was free from any obstructions. This location falls in
down wind direction and represents rural and residential area.
AAQ-4: Naharpali Village
The sampler was placed on top of a residential building at a height of about 4.5 m
from the ground level and was free from any obstructions. This location falls in
the down wind direction to the plant site, the location also represents rural and
residential area.
AAQ-5: Kurabhata Village
The sampler was placed on top of a residential building at a height of about 3.0 m
from the ground level and was free from any obstructions, and the location falls in
the cross wind direction to the plant site and representing rural and residential
area.
AAQ-6: Bade Jampali Village
The sampler was placed on top of a residential building at a height of about 2.0 m
from the ground level and was free from any obstructions. This location is falls in
the down wind direction, residential activities were observed surrounding the
location.
AAQ-7: Daramurra Village
The sampler was placed on top of a residential building at a height of about 3.0 m
from the ground level and was free from any obstructions. This location
represents cross wind direction to the proposed plant site. Residential activities
prevail in the surrounding area.
AAQ-8: Near Chotta Dumarpali Village
The sampler was placed on top of a residential building at a height of about 4.0 m
from the ground level and was free from any obstructions. This location
represents down wind direction to the proposed plant site. Residential and rural
activities prevail in the surrounding area.
AAQ-9: Pamgarh Village
The sampler was placed on top of a residential building at a height of about 3.5 m
from the ground level and was free from any obstructions. This location
represents cross wind direction to the proposed plant site. Residential and rural
activities prevail in the surrounding area.
VIMTA Labs Limited, Hyderabad
C3-18
C3-19
C3-20
Environmental Impact Assessment for the Proposed 4x300 MW Coal Based Thermal Power Plant at Binjkot, Darramura, Badejampali
and Gindola Villages in Kharsia Tehsil of Raigarh District, Chhattisgarh State
Chapter-3
Baseline Environmental Status
TABLE-3.4.5
SUMMARY OF AMBIENT AIR QUALITY RESULTS PRE-MONSOON SEASON 2008
Sr.No
Location
TSPM
Max
AAQ1
Plant site
91.2
55.3
75.3
89.3
27.4
16.4
23.4
9.5
5.0
8.7
98%
tile
9.5
AAQ2
76.5
44.4
66.4
76.1
27.8
14.2
17.5
24.1
8.2
5.8
7.1
8.2
AAQ3
116.5
59.8
96.5
116.5
36.4
18.3
29.0
36.0
11.6
5.9
9.4
11.4
AAQ4
Naharpali village
129.8
75.6
106.1
129.2
42.3
35.6
38.4
41.8
12.2
8.6
10.2
12.2
AAQ5
Kurabhata village
139.6
81.4
111.9
134.4
48.6
21.3
29.0
40.7
13.4
6.5
8.5
13.0
AAQ6
126.3
60.2
96.6
125.0
38.8
18.5
29.5
37.7
10.9
5.3
7.8
10.5
AAQ7
Daramurra village
92.4
51.3
80.4
91.3
29.5
15.4
23.4
29.0
9.3
5.4
7.5
9.2
AAQ8
120.0
59.7
99.5
119.9
37.9
16.7
28.5
36.7
10.9
6.6
8.3
10.9
AAQ9
Near
Chotta
Dumarpali
village
Pamgarh village
113.5
72.6
95.4
112.0
33.3
20.1
27.5
32.8
9.3
5.2
7.8
9.3
AAQ10
Jhintipalli village
106.1
59.9
92.5
106.0
34.9
17.4
28.0
34.2
9.8
5.6
8.2
9.6
AAQ11
Binjkot village
105.6
54.5
83.5
103.8
33.6
17.7
25.3
32.0
8.1
5.8
7.3
8.1
AAQ12
Dengurchua village
103.5
60.4
83.4
99.4
29.8
16.6
22.9
28.1
8.9
5.1
6.4
8.6
Avg
44.4-139.6
98%tile
Max
Min
SO2
98%
tile
27.1
Min
RPM
Avg
14.2-42.3
Max
Min
Avg
5.0-13.4
C3-21
Environmental Impact Assessment for the Proposed 4x300 MW Coal Based Thermal Power Plant at Binjkot, Darramura, Badejampali
and Gindola Villages in Kharsia Tehsil of Raigarh District, Chhattisgarh State
Chapter-3
Baseline Environmental Status
TABLE-3.4.5 (A)
SUMMARY OF AMBIENT AIR QUALITY RESULTS PRE-MONSOON SEASON 2008
Sr. No.
AAQ1
AAQ2
AAQ3
AAQ4
AAQ5
AAQ6
AAQ7
AAQ8
AAQ9
AAQ10
AAQ11
AAQ12
Location
Plant site
Near forest boundary
(near Gindola village)
Gindola village
Naharpali village
Kurabhata village
Bade Jampali village
Daramurra village
Near Chotta Dumarpali
village
Pamgarh village
Jhintipalli village
Binjkot village
Dengurchua village
Study Area Range
Max
12.6
9.9
Min
6.1
6.4
NOx
Avg
11.0
8.7
98%tile
12.5
9.8
Max
319
255
Min
210
171
CO
Avg
290.7
186.1
14.9
14.3
15.6
13.8
11.3
12.5
7.2
9.9
8.7
6.9
7.6
6.6
12.0
12.4
11.1
9.8
9.8
9.6
14.7
14.3
15.1
13.2
11.3
12.4
302
375
395
345
322
330
263
288
314
275
262
243
282.9
324.2
350.3
305.3
293.9
279.2
298.5
358.2
392.9
337.8
320.6
313.2
10.6
12.4
10.8
11.2
6.5
6.5
7.2
7.4
9.0
9.6
9.2
9.0
6.1-15.6
10.5
12.0
10.6
10.9
314
332
310
310
249
215
233
224
267.8
261.7
271.2
276.3
171-395
399.1
322.4
308.9
309.5
98%tile
317.0
240.8
C3-22
3.5
Water Quality
Selected water quality parameters of surface and ground water resources within 10
km radius of the study area has been studied for assessing the water environment
and evaluate anticipated impact of the project. Understanding the water quality is
essential in preparation of Environmental Impact Assessment and to identify critical
issues with a view to suggest appropriate mitigation measures for implementation.
The purpose of this study is to:
The information required has been collected through primary surveys and
secondary sources.
3.5.1
Methodology
Reconnaissance survey was undertaken and monitoring locations were finalized
based on:
Drainage pattern;
Location of residential areas representing different activities/likely impact areas;
and
Likely areas, which can represent baseline conditions.
Three surface water and eight ground water sources covering 10-km radial
distance were examined for physico-chemical, heavy metals and bacteriological
parameters in order to assess the effect of industrial and other activities on surface
and ground water. The samples were analyzed as per the procedures specified in
'Standard Methods for the Examination of Water and Wastewater' published by
American Public Health Association (APHA).
Samples for chemical analysis were collected in polyethylene carboys. Samples
collected for metal content were acidified with 1 ml HNO3. Samples for
bacteriological analysis were collected in sterilized glass bottles. Selected physicochemical and bacteriological parameters have been analyzed for projecting the
existing water quality status in the study area. Parameters like temperature,
Dissolved Oxygen (DO) and pH were analyzed at the time of sample collection.
The methodology for sample collection and preservation techniques was followed as
per the Standard Operating Procedures (SOP) mentioned in Annexure-VI.
C3-23
3.5.2
Code
Surface Water
1
SW1
2
SW2
SW3
Ground Water
1
GW1
2
GW2
3
GW3
4
GW4
5
GW5
6
GW6
7
GW7
8
GW8
3.5.3
Location
Direction
w.r.t. Plant
Boundary
2.3
SSE
0.9
WNW
5.3
NNW
Kurubhata village
Sendripalee village
Jintipali village
Bade jampalee village
Gindola village
Nahardipa village
Darra murra village
Binjkot village
2.7
2.2
0.7
0.7
0.8
1.8
0.4
0.4
S
S
NNW
S
ESE
NW
SW
NE
Presentation of Results
The results of the water quality monitored during the study period representing premonsoon season are given in Table 3.5.2 to Table-3.5.3.
The analysis results indicate that the pH values in the range of 7.4 to 7.6, the
maximum value was observed at SW3, minimum value was observed at SW1
and which is well within the specified standard of 6.5 to 8.5.
The TDS was observed in the range of 105 mg/l to 115 mg/l, the maximum
TDS value was observed at SW1, and where as minimum value was observed
at SW3.
The chlorides and Sulphates were found to be in the range of 18.4 to 35.5 mg/l
and 4.3 to 4.8 mg/l respectively. It is observed that chlorides and Sulphates are
well within the permissible limits. It is evident from the above values that all the
parameters are found to comply with the requirements of IS: 2296 specification
of surface water. The surface water quality does not indicate any industrial
contamination.
C3-24
The analysis results indicate that the pH ranges in between 7.3 to 7.7, which is
well within the specified standard of 6.5 to 8.5. The maximum pH of 7.7 was
observed at GW6 and the minimum pH of 7.3 was observed at GW1 and GW8.
Total hardness was observed to be ranging from 163.3 to 364.8 mg/l. The
maximum hardness (364.8 mg/l) was recorded at GW5 and the minimum
(163.3 mg/l) was recorded at GW3. The hardness was found to be above the
prescribed limit of 300 mg/l at GW4 (327.7 mg/l), GW5 (364.8 mg/l) and GW7
(344.7 mg/l) respectively.
Chlorides were found to be in the range of 28.4 mg/l to 127.6 mg/l, the
maximum concentration of chlorides (127.6 mg/l) was observed at GW1, and
where as the minimum value of 28.4 mg/l was observed at GW3, respectively.
Sulphates were found to be in the range of 14.5 mg/l to 254.2 mg/l. The
maximum value observed at GW7 (254.2 mg/l) where as the minimum value
observed at GW3 (14.5 mg/l). The sulphates was found to be above the
prescribed limits of IS:10500 at GW4 (217.7 mg/l),GW5(274.1 mg/l) and GW7
(254.2)
The ground water quality in the study area does not indicate any industrial
contamination.
C3-25
FIGURE-3.5.1
WATER SAMPLING LOCATIONS
VIMTA Labs Limited, Hyderabad
C3-26
TABLE-3.5.2
SURFACE WATER QUALITY
Sr.
No
Parameters
Unit
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
IS: 2296
Class C
Limits
6.5 8.5
300
$
1500
4 min
3
$
$
$
$
$
600
$
$
400
1.5
50
$
$
$
0.05
0.005
0.1
0.01
0.2
1.5
0.1
50
0.05
0.05
15
$
$
Absent
1
pH
Colour
Hazen
Conductivity
S/cm
TDS
mg/l
DO
mg/l
BOD
mg/l
COD
mg/l
Total Hardness as CaCO3
mg/l
Total Alkalinity as CaCO3
mg/l
Calcium as Ca
mg/l
Magnesium as Mg
mg/l
Chlorides as Cl
mg/l
Residual free Chlorine
mg/l
Phosphates as PO4
mg/l
Sulphates as SO4
mg/l
Fluorides as F
mg/l
Nitrates as NO3
mg/l
Sodium as Na
mg/l
Potassium as K
mg/l
Total Boron as B
mg/l
Cyanides
mg/l
Phenolic Compounds
mg/l
Oil and Grease
mg/l
Cadmium as Cd
mg/l
Arsenic as As
mg/l
Copper as Cu
mg/l
Lead as Pb
mg/l
Iron as Fe
mg/l
Chromium as Cr+6
mg/l
Selenium as Se
mg/l
Zinc as Zn
mg/l
Aluminium as Al
mg/l
Mercury as Hg
mg/l
SAR
Insecticides
mg/l
Anionic detergents as
mg/l
MBAS
*Onsite results, $ Limits not specified, U O: Unobjectionable
SW1
SW2
SW3
7.5
14
163
115
5.2
<3
5
59.6
50
15.6
4.7
21.3
<0.1
0.01
4.3
0.2
0.8
8.0
4.1
0.04
<0.02
<0.001
<0.01
<0.01
<0.01
<0.01
<0.01
0.02
<0.05
<0.01
0.08
<0.01
<0.001
0.46
Absent
<0.2
7.4
11
160
110
5.6
<3
5
60.6
30
15.6
5.0
35.5
<0.1
0.01
4.8
0.2
0.7
8.3
4.2
0.05
<0.02
<0.001
<0.01
<0.01
<0.01
<0.01
<0.01
0.01
<0.05
<0.01
0.04
<0.01
<0.001
0.47
Absent
<0.2
7.6
16
170
105
5.8
<3
10
62
52
16.8
4.8
18.4
<0.1
0.02
4.5
0.2
0.3
9.8
3.9
0.03
<0.02
<0.001
<0.01
<0.01
<0.01
<0.01
<0.01
0.04
<0.05
<0.01
0.02
<0.01
<0.001
0.54
Absent
<0.2
C3-27
TABLE-3.5.3
GROUND WATER QUALITY
Sr.
No
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
Parameters
Units
pH
Colour
Taste
Odour
Hazen
-
IS: 10500
Limits
6.5 8.5
5 (25)
Agreeable
U.O
GW1
GW2
GW3
GW4
GW5
7.3
2
A
UO
7.4
1
A
UO
7.6
3
A
UO
7.4
2
A
UO
7.5
1
A
UO
Conductivity
Turbidity
TDS
Total Hardness
as CaCO3
Total Alkalnity
Calcium as Ca
Magnesium
as
Mg
Residual
Chlorine
Boron
Chlorides as Cl
Sulphates
as
SO4
Fluorides as F
Nitrates as NO3
Sodium as Na
Potassium as K
Phenolic
Compounds
Cyanides
Anionic
Detergents
Mineral Oil
Cadmium as Cd
Arsenic as As
Copper as Cu
Lead as Pb
Manganese
as
Mn
Iron as Fe
Chromium
as
Cr+6
Selenium as Se
Zinc as Zn
Aluminium as Al
Mercury asHg
Pesticides
E.Coli
Total Coliforms
S/cm
NTU
mg/l
mg/l
$
5 (10)
500 (2000)
300 (600)
767
3
623
299.1
520
2
411
190.5
393
4
276
163.3
885
3
713
327.7
1140
2
1010
364.8
mg/l
mg/l
mg/l
200 (600 )
75 (200)
30 (100)
125
84
20.5
120
63
7.6
128
44.8
11.8
136
92.3
22.3
160
110.8
20.2
mg/l
0.2 Min
<0.1
<0.1
<0.1
<0.1
<0.1
mg/l
mg/l
mg/l
1
250 (1000)
200 (400)
0.02
127.6
76.8
0.01
49.6
21.6
0.01
28.4
14.5
0.03
56.7
217.7
0.02
70.9
274.1
mg/l
mg/l
mg/l
mg/l
mg/l
1.0 (1.5)
45 (NR)
$
$
0.001 (0.002)
0.2
11.7
30.2
25
<0.001
0.1
31.0
21.5
0.2
<0.001
0.5
1.7
7.7
0.1
<0.001
0.3
1.1
42.5
4.5
<0.001
0.4
1.9
83.3
11.2
<0.001
mg/l
mg/l
0.05 (NR)
0.2 (0.1)
<0.02
<0.2
<0.02
<0.2
<0.02
<0.2
<0.02
<0.2
<0.02
<0.2
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
0.01 (0.03)
0.01(NR)
0.01(NR)
0.05(1.5)
0.05(NR)
0.1(0.3)
<0.01
<0.01
<0.01
<0.01
<0.01
0.21
<0.01
<0.01
<0.01
0.12
0.02
0.01
<0.01
<0.01
<0.01
0.06
0.01
0.02
<0.01
<0.01
<0.01
0.10
<0.01
<0.01
<0.01
<0.01
<0.01
0.10
<0.01
0.01
mg/l
mg/l
0.3(1.0)
0.05(NR)
0.01
<0.05
0.02
<0.05
0.08
<0.05
0.03
<0.05
0.03
<0.05
<0.01
0.03
0.01
<0.001
Absent
Absent
<2
<0.01
0.01
0.04
<0.001
Absent
Absent
<2
<0.01
0.03
0.08
<0.001
Absent
Absent
<2
mg/l
0.01(NR)
<0.01
<0.01
mg/l
5(15)
0.02
2.1
0.01
mg/l
0.03(0.2)
0.03
mg/l
0.001(NR)
<0.001
<0.001
mg/l
Absent
Absent
Absent
Absent
Absent
Absent
MPN/10
10
<2
<2
0 ml
*Onsite results, $ Limits not specified, U O: Unobjectionable
GW1-Kurubhata village (bore well)
GW2-Sendripalee village (bore well)
GW3-Jintipali village (bore well)
GW4-Bade jampali village (bore well)
C3-28
TABLE-3.5.3(A)
GROUND WATER QUALITY
Sr.
No
1
2
3
4
5
6
7
8
9
10
11
12
Parameters
Units
pH
Color
Taste
Odor
Conductivity
Turbidity
TDS
Total Hardness as CaCO3
Total Alkalinity
Calcium as Ca
Magnesium as Mg
Residual Chlorine
Hazen
S/cm
NTU
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
Boron
Chlorides as Cl
Sulphates as SO4
Fluorides as F
Nitrates as NO3
Sodium as Na
Potassium as K
Phenolic Compounds
Cyanides
Anionic Detergents
Mineral Oil
Cadmium as Cd
Arsenic as As
Copper as Cu
Lead as Pb
Manganese as Mn
Iron as Fe
Chromium as Cr+6
Selenium as Se
Zinc as Zn
Aluminium as Al
Mercury as Hg
Pesticides
E.Coli
Total Coli forms
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
MPN/10
0 ml
IS: 10500
Limits
6.5 8.5
5 (25)
Agreeable
U.O
$
5 (10)
500 (2000)
300 (600)
200 (600 )
75 (200)
30 (100)
0.2 Min
1
250 (1000)
200 (400)
1.0 (1.5)
45 (NR)
$
$
0.001 (0.002)
0.05 (NR)
0.2 (0.1)
0.01 (0.03)
0.01(NR)
0.01(NR)
0.05(1.5)
0.05(NR)
0.1(0.3)
0.3(1.0)
0.05(NR)
0.01(NR)
5(15)
0.03(0.2)
0.001(NR)
Absent
Absent
10
GW6
GW7
GW8
7.7
3
A
UO
770
4
601
289.3
130
88.6
15.6
7.6
2
A
UO
1028
3
926
344.7
130
93
25.8
7.3
2
A
UO
720
2
613
290.9
192
86.3
17.3
<0.1
<0.1
<0.1
0.02
85.1
97.1
0.3
5.3
42.1
0.6
<0.001
<0.02
<0.2
<0.01
<0.01
<0.01
<0.01
<0.01
0.01
0.03
<0.05
<0.01
0.02
<0.01
<0.001
Absent
Absent
<2
0.01
106.4
254.2
0.4
1.6
76
5.4
<0.001
<0.02
<0.2
<0.01
<0.01
<0.01
<0.01
<0.01
0.02
0.02
<0.05
<0.01
0.05
<0.01
<0.001
Absent
Absent
<2
0.03
56.7
88.3
0.4
0.3
45.3
0.07
<0.001
<0.02
<0.2
<0.01
<0.01
<0.01
<0.01
<0.01
0.01
0.01
<0.05
<0.01
0.01
<0.01
<0.001
Absent
Absent
<2
C3-29
3.6
Soil Characteristics
It is essential to determine the potential of soil in the area and identify the
current impacts of urbanization and industrialization on soil quality and also
predict impacts, which may arise due to the plant operations. Accordingly, a study
of assessment of the baseline soil quality has been carried out.
Eight locations within 10-km radius of the proposed plant boundary were
selected for soil sampling. At each location, soil samples were collected from three
different depths viz. 30 cm, 60 cm and 90 cm below the surface and are
homogenized. This is in line with IS: 2720 and Methods of Soil Analysis, Part-1,
2nd edition, 1986 of (American Society for Agronomy and Soil Science Society of
America). The homogenized samples were analyzed for physical and chemical
characteristics. The soil samples were collected during pre-monsoon season. The
samples have been analyzed as per the established scientific methods for
physico-chemical parameters. The heavy metals have been analyzed by using
Atomic Absorption Spectrophotometer and Inductive Coupled Plasma Analyzer.
The methodology adopted for each parameter is described in Table-3.6.1.
TABLE-3.6.1
ANALYTICAL TECHNIQUES FOR SOIL ANALYSIS
Parameter
Grain size distribution
Textural classification
Bulk density
Sodium absorption ratio
pH
Electrical conductivity
Nitrogen
Phosphorus
Potassium
Copper
Iron
Zinc
Boron
Chlorides
VIMTA Labs Limited, Hyderabad
The details of the sampling locations are given in Table-3.6.2 and are shown in
Figure-3.6.1. The soil quality at all the locations during the study period is
tabulated in Table-3.6.3. The results are compared with standard classification
given in Table-3.6.4.
TABLE-3.6.2
DETAILS OF SOIL SAMPLING LOCATIONS
Sr.
No.
S1
S2
S3
S4
S5
S6
S7
S8
Location
Sendripalee village
Jhintipali village
Gindola village
Plant site
Naharpali village
Kurubhata village
Bade jampale village
Darramurra village
Distance from
Plant Boundary
(km)
Barren Land
Barren Land
Agriculture Land
Barren Land
Agriculture Land
Agriculture Land
Agriculture Land
Barren Land
2.2
0.7
0.9
2.2
1.9
0.7
0.4
Direction w.r.t
Plant Boundary
S
NNW
E
SSE
SSE
S
SW
It has been observed that the pH of the soil in the study area ranged from 5.2
to 7.5 the maximum pH value of 7.5 was observed at Naharpali village (S5),
where as the minimum value of 5.2 was observed at Jintipali Village (S2).
The nitrogen values range between 49.3-191.4 kg/ha. The nitrogen content in
the study area falls in less to better category.
The phosphorus values range between 65.5 to 113.8 kg/ha, indicating that
the phosphorus content in the study area falls in average sufficient to more
than Sufficient.
The potassium values range between 164.4 386.8 kg/ha. The potassium
content in the study area falls in less to more than sufficient category.
The chlorides were found to be in the range of 105.6 174.4 mg/kg of soil.
C3-31
FIGURE-3.6.1
SOIL SAMPLING LOCATIONS
VIMTA Labs Limited, Hyderabad
C3-32
Environmental Impact Assessment for the Proposed 4x300 MW Coal Based Thermal Power Plant at Binjkot, Darramura, Badejampali
and Gindola Villages in Kharsia Tehsil of Raigarh District, Chhattisgarh State
Chapter-3
Baseline Environmental Status
TABLE-3.6.3
SOIL ANALYSIS RESULTS
Sr. No.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
Parameter
pH (1:5 Aq.Extract)
Condutivity (1:5Aq.Extract)
Texture
Sand
Silt
Clay
Bulk Density
Exchangeable Calcium as Ca
Exchangeable Magnesium as Mg
Exchangeable Sodium as Na
Available Potassium as K
Available Phosphorous as P
Available Nitrogen as N
Organic Matter
Organic Carbon
Water Soluble Chloride as Cl
Water Soluble Sulphate as SO4
Sodium Absorption Ratio
Aluminum
Total Iron
Manganese
Zinc
Boron
UOM
---S/cm
---%
%
%
mg/cc
mg/kg
mg/kg
mg/kg
Kg/ha
Kg/ha
Kg/ha
%
%
mg/kg
mg/kg
---%
%
mg/kg
mg/kg
mg/kg
S1
6.8
80
Sandy clay
54
11
35
1.1
2716
383
82.7
164.4
86.2
49.3
0.46
0.27
140.5
138.7
0.18
2.06
0.92
136.8
142.9
38.6
S2
5.2
90
Sandy clay
52
10
38
1.1
1781
376
88.1
276.3
94
60.5
0.57
0.33
137.4
101.9
0.22
1.84
0.75
142.6
116.4
49.4
S3
5.9
135
Clay
29
15
56
1.2
2433
167
54.9
335.8
106.0
186.7
1.61
0.93
174.4
53.6
0.13
1.92
1.02
128.4
102.6
36.8
S4
7.1
150
Clay
38
10
52
1.1
3473
288
79.9
226.3
65.5
163.0
1.53
0.89
141.0
57.7
0.16
1.70
0.69
119.6
112.6
44.9
S5
7.5
145
Clay
42
11
47
1.1
1435
542
105.7
325.8
88.5
154.5
1.45
0.84
141.3
112.2
0.27
1.78
0.88
162.4
126.8
52.8
S6
7.3
230
Sandy Clay
45
15
40
1.1
2632
119
71.7
386.8
81.6
123.7
1.16
0.67
138.9
206.6
0.17
1.68
0.75
192.8
121.6
48.6
S7
7.4
75
Clay
27
18
55
1.2
2283
526
93.0
238.8
113.8
191.4
1.65
0.95
105.6
166.5
0.21
1.49
1.02
146.3
142.8
39.4
S8
6.7
72
Sandy clay
51
14
35
1.1
2168
423
63.4
171.6
96.6
64.6
0.61
0.35
140.3
72.2
0.15
1.98
0.82
162.4
112.4
52.8
C3-33
TABLE-3.6.4
STANDARD SOIL CLASSIFICATION
Sr. No.
1
Soil Test
pH
Salinity
Electrical
(mmhos/cm)
(1ppm = 640 mmho/cm)
Nitrogen (Kg/ha)
Phosphorus (Kg/ha)
Potash (Kg/ha)
Conductivity
Classification
<4.5 Extremely acidic
4.51- 5.50 Very strongly acidic
5.51-6.00 moderately acidic
6.01-6.50 slightly acidic
6.51-7.30 Neutral
7.31-7.80 slightly alkaline
7.81-8.50 moderately alkaline
8.51-9.0 strongly alkaline
9.01 very strongly alkaline
Upto 1.00 Average
1.01-2.00 harmful to germination
2.01-3.00 harmful to crops (sensitive to
salts)
Upto 0.2: very less
0.21-0.4: less
0.41-0.5 medium,
0.51-0.8: on an average sufficient
0.81-1.00: sufficient
>1.0 more than sufficient
Upto 50 very less
51-100 less
101-150 good
151-300 Better
>300 sufficient
Upto 15 very less
16-30 less
31-50 medium,
51-65 on an average sufficient
66-80 sufficient
>80 more than sufficient
0 -120 very less
120-180 less
181-240 medium
241-300 average
301-360 better
>360 more than sufficient
The time of day at which noise occurs, for example high noise levels at night in
residential areas are not acceptable because of sleep disturbance; and
C3-34
The location of the noise source, with respect to noise sensitive land use, which
determines the loudness and period of exposure.
The environmental impact of noise can have several effects varying from Noise
Induced Hearing Loss (NIHL) to annoyance depending on loudness of noise. The
environmental impact assessment of noise from the plant operations and vehicular
traffic can be undertaken by taking into consideration various factors like potential
damage to hearing, physiological responses, and annoyance and general
community responses.
The main objective of noise monitoring in the study area is to establish the baseline
noise levels, and assess the impact of the total noise expected to be generated by
the construction and operation of the proposed plant facilities around it.
3.7.1
3.7.2
Method of Monitoring
Sound Pressure Level (SPL) measurements were measured at all locations. The
readings were taken for every hour for 24 hours. The day noise levels have been
monitored during 6 am to 10 pm and night levels during 10 pm to 6 am at all the
locations covered in 10-km radius of the study area.
TABLE- 3.7.1
DETAILS OF NOISE MONITORING LOCATIONS
Location
Code
N1
N2
N3
N4
N5
N6
N7
N8
N9
N10
Noise Sampling
Location
Distance from
Plant Boundary
(km)
Direction w.r.t.
Plant Boundary
Environmental
Setting
0.4
0.7
0.4
0.9
1.9
NE
S
SW
E
SSE
Residential
Residential
Residential
Residential
Residential
Nawapara village
Jhintipali village
Pamgarh village
Bhagoradih
village
2.2
0.7
1.8
0.5
SE
NNW
WSW
W
Commercial
Residential
Residential
Residential
C3-35
Leq = L50 +
( L10 _L90 ) 2
60
Lday is defined as the equivalent noise level measured over a period of time during
day (6 am to 10 pm).
Lnight is defined as the equivalent noise level measured over a period of time during
night (10 pm to 6 am).
A noise rating developed by E P A for specification of community noise from all the
sources is the Day-Night Sound Level, (Ldn).
C3-36
FIGURE-3.7.1
NOISE MONITORING LOCATIONS
VIMTA Labs Limited, Hyderabad
C3-37
Presentation of Results
The statistical analysis is done for measured noise levels at ten locations. The
parameters are analyzed for L10, L50, L90, Leq, Lday, Lnight, and Ldn. The statistical
analysis results are given in Table- 3.7.2.
3.7.5
Observations
Day time Noise Levels (Lday)
The day time noise levels at all the locations were ranged in between 42.3 to dB(A)
to 54.7. The maximum value (54.7 dB (A)) was recorded at Nawapara village (N7),
and the minimum value (42.3 dB (A)) was recorded at Plant site (N1).
Night time Noise Levels (Lnight)
The night time noise levels were ranged in between 38.5 dB (A) to 49.0 dB (A). The
maximum value (49.0 dB (A)) was recorded at Gindola village (N5) and the
minimum value (38.5 dB (A)) was recorded at Plant site (N1).
TABLE-3.7.2
NOISE LEVELS dB (A) IN THE STUDY AREA
Sr. No.
1
2
3
4
5
6
7
8
9
10
Location
Proposed plant site
Binjkot village
Bade Jampali village
Darramura village
Gindola village
Kurubhata village
Nawapara village
Jhintipali village
Pamgarh village
Bhagoradhi village
L10
44.1
48.2
49.1
47.8
55.5
49.8
56.2
46.6
50.4
47.6
L50
40.5
43.7
45.2
44.0
51.3
46.0
51.4
42.7
46.6
44.1
L90
36.7
40.3
41.5
40.2
47.4
42.2
47.8
38.8
43.4
40.6
Leq
41.4
44.7
46.2
45.0
52.4
47.0
52.6
43.7
47.4
44.9
Lday
42.3
46.7
47.0
46.2
53.4
48.6
54.7
44.6
48.8
45.8
Lnight
38.5
41.8
43.4
42.3
49.0
44.3
48.9
40.0
45.3
41.8
C3-38
Ldn
45.7
49.3
50.5
49.5
56.4
51.6
56.8
47.4
52.4
49.1
3.8
3.8.1 Introduction
An ecological survey of the study area was conducted particularly with reference
to the listing of species and assessment of the existing baseline ecological
(Terrestrial and Aquatic ecosystem) conditions in the study area.
3.8.2
3.8.3
To assess the nature and distribution of vegetation in and around the project
site;
To assess the distribution of animal life spectra; and
To ascertain migratory routes of fauna and possibility of breeding grounds.
Compilation of secondary data with respect to the study area from published
literature and Government agencies;
Generation of primary data by undertaking systematic ecological studies in the
area;
Discussion with local people so as to elicit information about local plants,
animals and their uses; and
Gathering data for ethno biology.
The present report gives the review of published secondary data and the results of
field sampling conducted during summer season-2008.
3.8.4
Floral structure
The Chhattisgarh Plains has long been cultivation and at present only small
patches of degraded tropical dry deciduous forests have been left, if at all. It is
rather more characterized by scattered stunted and crooked trees and shrubs of
Butea monosperma, Lagerstroemia parviflora, Albizia spp., Acacia leucophloea,
A.nilotica spp. Indica. Mangifera indica. Terminalia spp., Ficus racemosa.
F.benghalensis. F.religiosa, Azadirachta indica, Pithecellobium dulce, Syzygium
cumini, Mitragyna parvifolia, Aegle marmelos, diospyros melanoxylon, Bauhinia
spp., Calotropis spp., Caesalpinia bonduc, Ipomoea carnea and Mimosa
himalayana, with several climbers like ziziphus oenoplia, Celastrus patina,
Ipomoea spp., Atylosia scarabaeoides and Cissampelos pareira. Particular mention
may be made of the Mahua trees, Madhuca longifolia var. latifolia, which are
VIMTA Labs Limited, Hyderabad
C3-39
considered sacred and stay unlopped. In addition, Albizia spp., Dalbergia sissoo,
Delonix regia, Cassia fistula, Peltophorum pterocarpum, Pongamia pinnata,
Eucalyptus hybrids, and Pterocarpus marsupium are frequently planted on the
roadsides. The ground flora, during rainy and post rainy season, consists of
several annual or perennial species of grasses, sedges and other herbs and
creepers, but by the middle of winter it is completely grazed and presents a bare
desolate spectre. Mention may be made of two epiphytic orchids, Vanda tessellate
and V.testacea which grow freely on Mangifera Indica, Butea monosperma,
Madhuca longifolia var latifolia, Diospyros melanoxylon and Terminalia spp. The
former with large brown banded flowers immediately catches the eye.
A good development of these forests with a fair amount of sal can be observed in
the reserved forests around Chilpi, Rangakhar, Borai, sitanadi, Khallari and
Taurenga. It has tall trees of Shorea, robusta, Terminalia spp. Pterocarpus
marsupium, Dalbergia panigulata, Adina ccordifolia, Stereospermum chelonoides,
Schleichera oleosa, Garuga pinnata, Lannea coromandelica, Bombax ceiba,
Soymida febrifuga and Boswellia serrata, and smaller trees like Lagerstroemia
parviflora, Briedelia squamosa, Mallotus philippensis, Diospyros melonoxylon,
Anogeissus latifolia, Buchanania lanzan, Gmelina arborea, Antidesma
ghaesembilla, Ficus spp., Grewia tiliifolia and Cassia fistula and shursb like
Breynia vitisidaea, Embelia tsjeriam cottam, Chloroxylon swietenia, Holarrhena
antidysenterica, Casearia graveolens, helicteris isora, Semecarpus anacardium,
Ochna obtusata, Indigofera cassioides, Woodfordia fruticosa and species of Leela
and Desmodium. The common in Chhatisgarh bamboo, Dendrocalamum strictus,
forms dense thickets. The conspicuous climbers and ramblers in these forests are
Millettia extensa, Smilax zeylanica, Bauhinia vahlii, Olax scandens, combretum
roxburghii, Ventilago denticulate, Ichnocarpus frutescens, Dioscorea pentaphylla,
D.puber, D.oppositifolia and D.bulbifera.
The undergrowth in dense forests is often sparse, and not much varied. The
common species are Eranthemum purpurascens, Perilepta edgeworthiana,
Nelsonia canescens, Phoenix acaulis, Chlorophytum tuberosum, globba racemosa,
G.bulbifera, Curcuma spp., Zingiber spp., Tacca leontopetaloides, Carex speciosa,
and a few ground orchids like eulophia spp. Habenaria spp., Geodorum
densiflorum, and peristylus spp. The edges of the forests have a very luxurious
growth of numerous annual and perennial species of Cleome, Desmodium,
Alysicarpus, Tephrosia, Crotalaria, Blumea, Cynoglossum, Barleria, leucas,
Phyllanthus, Euphorbia, Pupalia, Aerva, Commelina, Cyanotis and sedges and
grasses. The species diversity and undergrowth in forests with high proportion of
Shorea robusta is comparatively poorer than in the mixed forests. Sal is generally
absent on hill slopes.
These are found in comparatively drier areas, genrally in and around the
Chhattisgarh Plains. Though not always conspicuously different from the moist
deciduous forests, since transitionary stages are not uncommon, dry deciduous
forests are dominated by Legerstroemia parviflora, Butea monosperma, Diospyros
melanoxylon, Albizia spp., Anogeissus latifolia, Terminalia spp., Aegle marmelos,
VIMTA Labs Limited, Hyderabad
C3-40
There are around 12 forest blocks which includes Protected, Reserved and Open
Mixed forest blocks in 10-km radius from project. The list of forest blocks and their
distances from plant site are presented in Table 3.8.1. The forest blocks mainly
consists of Salai, Tendu, Bija, Saja, Char Ganja, Dhauwra, Harra and Dhobin.
TABLE-3.8.1
LIST OF FOREST BLOCKS WITHIN 10 KM RADIUS
Sr.
No.
1
2
3
4
5
6
7
8
9
10
11
12
Forest Block
Rabo RF
Taraimal RF
Lotan RF
Urdana RF
PF near Bendajhariya village
Burha pahar RF
Bhalunara RF
PF (Daharidih village)
Bargarh RF
Endu RF
Panikhet PF
Suhai RF
Direction
NNE
ENE
NNW
E
SW
SW
W
NE
WNW
NW
NNE
NNE
C3-41
3.8.5
Distance
0.8
2.5
2.7
2.1
1.8
Direction
ESE
SE
S
SSW
SW
C3-42
FIGURE-3.8.1
ECOLOGICAL SAMPLING LOCATIONS
VIMTA Labs Limited, Hyderabad
C3-43
Floristic Richness
Cryptogamic Vegetation
The area shows many algae, fungi, bryophytes and ferns. Algae are present in
aquatic bodies or in marshy places. Fungi, particularly from ascomycetes and
basidiomycetes are located on ground or epiphytically. Lichens of crustose, foliose
and fruticose types are present on different substrates (Lichens, Ascomycetes and
Basidiomycetes could be observed near hilly terrain). Bryophytes occur in wet areas
and occasionally on barks of trees and old walls of houses. The commonly observed
bryophtes in this area are Funaria sp and Polypodium sp. Fern flora of the study
area is insignificant. The aquatic weeds Hydrilla sp, Chara sp, Salvinia, Nymphea
were predominant in small ponds in agricultural fields.
Life Form Spectrum
Raunkiaer defined life forms as the sum of adaptations of plants to climate. BraunBlanquet (1951), whose system is adapted in this study, modified the Raunkiaer's
system.
During field survey, maximum 251 plant species (except algae, fungi and
bryophytes) were recorded from the study area. Table-1 of Annexure-VII lists all
species recorded in the study area. Classwise distribution of lifeforms in the study
area is presented in Table-3.8.3.
TABLE-3.8.3
CLASS WISE DISTRIBUTION OF PLANT SPECIES IN THE STUDY AREA
Type of species
No
Study Period
%
Phanerophytes (P)
106
42.23
Therophytes (T)
Hydrophytes (H)
Hemicryptophytes (He)
Geophytes (G)
Epiphyte(E)
Total
95
04
35
09
02
251
37.85
1.60
13.94
3.58
0.80
100
C3-44
3.8.6
National Park/Sanctuary
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
Technical Name
Aves
Targos calvus
Milyus migrans
Corvus corvus
Corvus splendens
Turdoides striatus
Aegithina tiphia
Pycnonotus cafer
Pycnonotus jokokus
Saxicoloides fulicata
Gallus gallus
Columbus livibus
Bubo bubo
Copsychus saularis
Oriolus oriolus
Oriolus xanthornus
Temenuchus pagodarum
Acridotheres tristicus
Ploceus philippines
Uroloncha striata
English Name/
Local Name
King vulture*
Common Kite
Jungle crow
House crow
White headed babler
Iora*
Red vented bulbul
White browed Bulbul
Indian robin*
Red Jungle fowl
Rock Pigeon
Indian great horned Owl*
Magpie Robin
Indian Oriole
Black Headed Oriole
Brahmny Myna
Common myna
Weaver bird
Spotted munia
Conservation status
as per Wildlife
Protection Act(1972)
Sch-IV
Sch-IV
Sch-IV
Sch-V
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-IV
C3-45
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
Technical Name
Passer domisticus
Cinnyris lotensis
Cinnyris asiatica
Brachypternus bengalensis
Megalaima merulinus
Eudynamis scolopaceus
Centropus sinensis
Psittacula Krammeri
Coryllis vaeralis
Coracias benghalensis
Merops orinetalis
Merops leschenaulti
Alcedo atthis
Microfus affinis
Caprimulgus asiaticus
Tylo alba
Haliastur Indus
Milvus migrans
Anhinga melanogaster
Egretta garzetta
Bubulcus ibis
Ardeola grayii
Anas acuta
Aythya feroma
Pavo cristatus
Reptiles
Calotes versicolor
Chamaleon
zeylanicus
(Laurenti)
Varanus benegalensis
Lycodon spp.
Boiga spp.
Bangarus spp.
Naja naja
Vipera spp.
Butterflies
Pachliopta hector Lin.
Papilio demoleus Lin.
Junoria almana Lin.
Hypolimnas bolina Lin.
Euploea core Cramer
Neptis hylas Moore
Eurema hecabe Lin.
Catopsilia sp.
Leptosia nina (Fabricius)
Amphibians
Rana tigrina
Hyla goeldii
Bufo malanosticus
Mammals
Bandicota bengalensis
Rhinolopus spp.
Hipposiderus spp.
Axix axis
Herpestes edwardii
Rattus norvegicus
Lepus nigricollis
English Name/
Local Name
House Sparrow
Loten's sunbird
Purple Sunbird
Malabar Golden acked wood
Indian Cuckoo
Koel
Crow Pheasant
Rose ringed parakeet
Lorikeet
Indian Roller
Common Bee Eater
Chestnut headed Bee Eater
Common Kingfisher
House swift
Common Indian jar
Barn Owl
Brahmny kite
Pariah kite
Darter
Little Egret
Cattle Egret
Pond Heron
Common Teal
White eyed Pochard
Peacock
Common garden lizard
Indian chamaeleon
Monitor lizard
Wolf snake
Cat snake
Krait
Indian cobra
Viper*
Conservation status
as per Wildlife
Protection Act(1972)
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-V
Sch-IV
Sch-IV
Sch-V
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-V
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Part-III of Sch-I
Sch-IV
Sch-IV
Part-II of Sch-II
Part-II of Sch-II
Sch-IV
Sch-IV
Part-IV
Part-II of Sch-II
Crimson rose
Lime butterfly
Peacock pansy
Great eggfly
Common crow
Common sailor
Common grass yellow
Emigrant
Psyche
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Bull frog
Tree frog
Bufo
Sch-IV
Sch-IV
Sch-IV
Bandicoot
Bat
Bat
Cheetal
Common mongoose
Field mouse
Hare
Sch-IV
Sch-IV
Sch-IV
SCH-III
Part-II of Sch-II
Sch-V
Sch-IV
C3-46
72
73
74
75
76
77
78
79
80
81
82
*not
Technical Name
Rattus rattus
Hyaena hyaena
Canis auries
Presbytis entellus
Mucaca mulata
Rattus sp.
Funambulus spp.
Funambulus palmarum
Sus sucrofa
Felis chaus
Elephas maximus
English Name/
Local Name
House rat
Hyaena*
Jackal
Langur
Monkey
Rat
Squirrel
Squirrel
Wild pig*
Jungle cat*
Indian elephant*
Conservation status
as per Wildlife
Protection Act(1972)
Sch-V
Sch-III
Part-II of Sch-II
Part-I of sch-II
Part-I of Sch-II
Sch-V
Sch-IV
Sch-IV
Sch-III
Part-I of Sch-I
Part-I of Sch-I
On comparison of the check list given in the Schedule-I of the Act and the list of
wildlife recorded in the study area. 82 animal species were recorded/reported from
study area during study period, out of which 3 species belongs to Sch-I, 7 species
belong to Sch-II, 3 species belongs to Sch-III and rest of the species belongs to
Sch-IV and Sch-V as per Wildlife Protection Act, 1972.
3.8.7
Aquatic Ecosystems
Protecting the environment and making efficient use of natural resources are two of
the most pressing demands in the present stage of social development. The task of
preserving the purity of the atmosphere and water basins is of both national and
global significance since there are no boundaries to the propagation of
anthropogenic contaminants in the water. An essential pre requisite for the
successful solution to these problems is to evaluate ecological impacts from the
baseline information and undertake effective management plan. So the objective of
aquatic ecological study may be outlined as follows:
In order to get a clear picture and to assess the various parameters of water, two
sampling locations were identified for sampling. Samples were collected during
study period. The sampling locations are presented in Table-3.8.6 and shown in
Figure-3.8.1.
TABLE-3.8.6
DETAILS OF AQUATIC SAMPLING LOCATIONS
Sr. No. Code
1
AE-1
2
AE-2
Locations
Upstream of River Mand near sendripale
Downstream of River Mand near Kurubhata
Remarks
Fresh water
Fresh water
C3-47
Zooplankton
Arcella
Keratella sp
Asplancha sp
Brachionus sp
Daphnia sp
Cerodaphnia sp
Cyclops sp
Mesocyclops sp
Cypris sp
Summary
Ecological studies were conducted in and around existing industrial and assess to
know the biological resources. 251 plant species were identified which are mainly
composed of phanerophytes and therophytes, hemicryptophytes. Phytosociological
studies were conducted during study at various locations such as forest areas and
C3-48
3
4
3-7 km
124.0
558.0
124.0
3025.0
731.0
142.0
5497.0
2354.0
833.0
1570.0
4837.0
10121.0
Source: District Census Hand Book 2001
7-10 km
1021.0
0-10 km
% Area
1703.0
5.5
985.0
8988.0
1728.0
1251.0
17510
4813.0
4.0
56.1
15.4
3535.0
5938.0
19.0
16257.0
31215.0
100.0
C3-49
may either be fallows or covered with shrubs, which are not put to any use. The
study area comprises of 4813.0 ha cultivable wastelands, which works out to
about 16.4% of the total area. This percentage of land in this category indicates
that almost all the cultivable lands are used for cultivation as well as various
other purposes, while leaving a very less extent of land un-cultivated.
3.9.4 Land not available for Cultivation
All the lands not included in the above categories of land uses are considered in
the category of land not available for cultivation. This category of land use mainly
consists of the hilly and barren lands, human settlements, roads, water-bodies,
etc. About 5938.0 ha area working out to about 19.0% of the total study area
falls in this category.
3.9.5
Level-1
Built-up Land
Agriculture Land
Forest
Wastelands
Water Bodies
Others
Level-2
Town/cities
Villages
Institution/Industry/Godown etc
Plotted Area/Layout
Crop Land
Plantations
Fallow
Evergreen/Semi evergreen
Deciduous
Forest Plantation
Rocky/Stony Waste
Land with /without scrubs
Saline/sandy & Marshy/swampy
River/Stream
Lake/Reservoir/Tanks
Orchard/Other Plantation
Shifting cultivation
Salt Pans, Snow covered/Glacial
Barren/Vacant Land
C3-50
Both topo-sheets and imagery were taken for field verification and a transverse
plan using existing road network was made to cover as many representative
sample areas as possible to observe the broad land use features and to adjust the
sample areas according to field conditions. Detailed field observations and
investigations were carried out and noted the land use features on the imagery.
The base maps of the study area were prepared, with the help of Survey of India
Topo-sheets on 1:1,45,000 scale. Preliminary interpreted land use and the land
cover features boundaries from IRS-P6 False Colour Composite were modified in
light of field information and the final thematic details were transferred onto the
base maps. The final interpreted and classified thematic map was catrographed.
The cartographic map was colored with standard colour coding and detailed
description of feature with standard symbols. All the classes noted and marked by
the standard legend on the map.
3.9.5.5 Final Output
The final output would be the land use/land cover map on 1:1,45,000 scale,
numerals were given different colour code for each category as shown in map.
Area estimation of all features of Land use/Land cover categories was noted.
3.9.5.6 Observations
VIMTA Labs Limited, Hyderabad
C3-51
The following are the main interpreted land use/land cover classes of the study
area and their respective areas are given in hectares in Table-3.9.3 for the year
2007. The thematic map and land use pattern within 10-km radius based on IRSP6 for 27th December 2007 are shown in Figure-3.9.1 and 3.9.2 respectively.
TABLE-3.9.3
LANDUSE BREAKUP BASED ON IRS-P6 DATA 27th DECEMBER 2007
Sr.
No.
1
2
3
4
5
6
7
8
9
10
Land Use
Built-up Area
Industry/Institutional Area
Degraded/Reserved/Protected Forest
Dense/Mixed Jungle
Plantation
Double Crop/Irrigated Area
Other Agriculture Area
Land without Scrub
Stony/rocky/Barren Area
Water Body
Area
(sq.m)
8473300
1377555
83451595
25709259
881165
29475262
141818837
59361342
10541266
19293341
380382922
Area
(Hectares)
847.33
137.76
8345.16
2570.93
88.12
2947.53
14181.88
5936.13
1054.13
1929.33
38038.29
Area
(%)
2.2
0.4
21.9
6.8
0.2
7.7
37.3
15.6
2.8
5.1
100
Total
Source: IRS-P6:LISS3 data, 27th December 2007
C3-52
FIGURE-3.9.1
THEMATIC MAP OF STUDY AREA (IRS-P6:LISS3)
VIMTA Labs Limited, Hyderabad
C3-53
FIGURE-3.9.2
LAND USE PATTERN BASED ON SATELLITE DATA
VIMTA Labs Limited, Hyderabad
C3-54
3.10
Particulars
No. of Households
Male Population
Female Population
Total Population
Male Population (0-6 years)
Female
Population
(0-6
years)
Total Population (0-6 years)
Average Household Size
% of males to the total
population
% of females to the total
population
Sex Ratio (no of females per
1000 males)
Density of Population/Km2
0-3 km
2674
6487
6624
13111
1094
1081
3-7 km
5125
12193
12276
24469
2084
2018
7-10 km
12493
30630
30284
60914
4918
4560
0-10 km
20292
49310
49184
98494
8096
7749
2175
4.9
49.5
4102
4.8
49.8
9568
4.9
50.3
15845
4.9
50.1
50.5
50.2
49.7
49.9
1021.1
1006.8
988.7
997.4
271.2
241.8
374.7
315.5
The males and females constitute about 49.9% and 50.1% in the study area
respectively.
VIMTA Labs Limited, Hyderabad
C3-55
Particulars
Scheduled Castes
% to total population
Scheduled Tribes
% to total population
Total SC and ST
% to total population
Other castes
% to total population
Total Population
0-3 km
3-7 km
1164
8.9
3692
28.2
4856
37.0
8255
63.0
13111
2833
11.6
9396
38.4
12229
50.0
12240
50.0
24469
7-10
km
7809
12.8
13930
22.9
21739
35.7
39175
64.3
60914
0 10 km
11806
12.0
27018
27.4
38824
39.4
59670
60.6
98494
C3-56
TABLE- 3.10.3
DISTRIBUTION OF LITERATE AND LITERACY RATES
Sr.
No
1
Particulars
0-3 km
3-7 km
7-10 km
0-10 km
Total literates
8881
15276
38061
62218
67.7
62.4
62.5
63.2
Male literates
4890
8855
22225
35970
37.3
36.2
36.5
36.5
Total Male
6487
12193
30630
49310
55.1
58.0
58.4
57.8
3991
6421
15836
26248
Total Female
6624
12276
30284
49184
60.3
52.3
52.3
53.4
% Female Literates to
Total literates
Total Population
44.9
42.0
41.6
42.2
13111
24469
60914
98494
10
11
The male literacy i.e. the percentage of literate males to the total males of the
study area works out to be 36.5%.The female literacy rate, which is an important
indicator for social change, is observed to be 53.4% in the study area. This
indicates that there is a considerable need for sociological development in the
region.
3.10.5 Occupational Structure
The occupational structure of residents in the study area is studied with reference
to main workers, marginal workers and non-workers. The main workers include 4
categories of workers defined by the Census Department consisting of cultivators,
agricultural laborers, those engaged in manufacturing, processing and repairs in
household industry; and others including those engaged in household industry,
construction, trade and commerce, transport and communication and all other
services.
The marginal workers are those workers engaged in some work for a period of
less than six months during the reference year prior to the census survey. The
non-workers include those engaged in unpaid household duties, students, retired
persons, dependents, beggars, vagrants etc.; institutional inmates or all other
non-workers who do not fall under the above categories.
As per 2001 census records altogether the main workers works out to be 31.4%
of the total population. The marginal workers and non-workers constitute to
11.6% and 57.1% of the total population respectively. The distribution of workers
by occupation indicates that the non-workers are the predominant population.
The occupational structure of the study area is given in Table-3.10.4.
C3-57
TABLE-3.10.4
OCCUPATIONAL STRUCTURE
Sr. No
1
2
3
4
5
6
7
Occupation
Total Workers
Total Main Workers
Percentage to Total
Population (%)
Marginal Workers
Percentage to Total
Population (%)
Non-Workers
Percentage to Total
Population (%)
Total Population
0-3 km
6305
4198
32.0
3-7 km
11163
8631
35.3
7-10 km
24825
18052
29.6
0 -10 km
42293
30881
31.4
2107
16.1
2532
10.3
6773
11.1
11412
11.6
6806
51.9
13306
54.4
36089
59.2
56201
57.0
13111
24469
60914
98494
C3-58
4.0
4.1
Introduction
The chapter presents identification and appraisal of various impacts due to the
proposed power plant during construction and operational phases. The
environmental impacts are categorized as primary or secondary. Primary impacts
are those, which are attributed directly to the project and secondary impacts are
those, which are indirectly induced and typically include the associated
investment and changed pattern of social and economic activities by the proposed
action.
The mitigation measures proposed for minimizing the impacts have also been
discussed in this chapter. Environment Management Plan (EMP) is developed to
minimize adverse impacts and to ensure that the environment in and around the
project site is well protected. The EMP has been prepared for both construction
and operation phases of the proposed facilities.
The impacts have been assessed for the power plant assuming that the pollution
due to the existing activities has already been covered under baseline
environmental monitoring and continue to remain same till the operation of the
project.
The construction and operational phase of the proposed project comprises various
activities each of which may have an impact on some or other environmental
parameters. Various impacts during the construction and operation phase on the
environment have been studied to estimate the impacts on the environmental
attributes and are discussed in the subsequent sections.
4.2
4.2.1
C4-1
Construction of plant will lead to permanent change in land use pattern at the site
as a direct impact. The proposed project involves construction of large scale civil
works including levelling within project premises. The earthen material generated
during construction of large scale water storage reservoirs within the project
premises will be used for level rising of plant area.
The environmental pollution impacts during constructional phase would be
temporary and are expected to gradually stabilize by the time of commissioning
of proposed project.
The buffer zone of the proposed plant site is sparsely distributed villages. There
are no sensitive locations such as archaeological monuments, sanctuaries,
national parks, critical pollution zones etc within 10-km radial distance around the
proposed project site, except the reserved forest patches on hilltops. No major
changes in land use pattern of study area (region) will occur due to the project
activities.
Hence, no major impact is envisaged on land use pattern of the project site or
buffer zone.
4.2.2
Impact on Soil
All major construction activities tend to create certain changes in the soil of the
area. Excavation denudes the topsoil and makes it loose. Destruction of topsoil
leads to reduction of fertility and removal of vegetation cover with associated
hazards of the soil erosion.
During storms, some of the excavated soil and construction material such as sand
etc. would be blown up in the air and dispersed around the project site, some would
also tend to be driven into the soil and clog inter-granular spaces. However, in order
to minimise such impacts, appropriate soil conservation measures would be
undertaken. Vegetation cover would also be replaced by planting and turfing
wherever feasible. No adverse impacts on soil in the surrounding area are
anticipated.
4.2.3
Impact on Topography
The proposed project premise is a generally plain land with a general elevation of
about 230-m above MSL. Most of the buffer zone of the project is flat land.
It is proposed to level the project area and to use the earthen material excavated
from the proposed reservoir sites inside the premises. There will be no tall
structures except stacks. Also, the contours of natural drainage will not be
disturbed.
In view of the above, there will be no major adverse impact on topography of the
project site.
C4-2
4.2.6
4.2.7
C4-3
C4-4
Source Complex [ISC3] 1993 dispersion model, designed for multiple point
sources for short term and developed by United States Environmental Protection
Agency [USEPA] has been used for simulations from point sources.
The model simulations deal with dispersion of three major pollutants viz., Sulphur
Dioxide (SO2), Oxides of Nitrogen (NOx) and Suspended Particulate Matter (SPM)
emitted from the stacks.
4.3.2.1 Model Input Data
The air pollution modelling has been carried out representing the worst case
scenario. The stack details considered for model computations are summarized in
Table-4.1.
TABLE-4.1
PROPOSED STACK DETAILS
Sr. No.
1
2
3
4
5
6
7
a
b
c
Parameters
Stack Height
No. of flues
Top diameter of each flue
Flue gas velocity in each flue
Flue gas temperature
Flow rate of gas in each flue
Coal Consumption
Sulphur dioxide (SO2) emission rate (Based
on 0.4 of Sulphur) in each flue
Particulate matter (SPM) emission rate in
each flue
Oxides of Nitrogen (NOx)
Units
m
No.
m.
m/s
o
K
Nm3/s
TPH
g/s/flue
Stack-I
275
2
7.0
25.0
413
694.3
760.1
422.3
Stack-II
275
2
7.0
25.0
413
694.3
760.1
422.3
mg/Nm3
g/s/flue
g/s/flue
mg/Nm3
50
34.7
243.0
350
50
34.7
243.0
350
Meteorological Data
C4-5
TABLE-4.2
PREDICTED 24-HOURLY SHORT TERM INCREMENTAL CONCENTRATIONS
Season
Summer-season,
2008
Distance
(km)
Direction
2.8
SW
TABLE-4.3
RESULTANT CONCENTRATIONS DUE TO INCREMENTAL GLC's
(WORST CASE SCENARIO)
Pollutant
SPM
SO2
NOx
Maximum
Baseline
Concentration
g/m3)
(
139.6
13.4
15.6
Incremental
Concentrations
due to Proposed
Project (
g/m3)
2.3
31.5
23.9
Resultant
Concentration
(
g/m3)
141.9
44.9
39.5
TABLE-4.4
NAAQ/CPCB STANDARDS FOR AMBIENT AIR QUALITY
Pollutant
C4-6
It is also to be noted that the above concentrations are for worst case scenario of
operations only. For indigenous fuel consumption, the concentrations will be much
lower. Hence, it can be stated that the AAQ of the area will be within the
permissible limits of respective zones.
Air dispersion modeling studies have been carried to assess the impact on forest
blocks and sensitive location in study area. The details are presented in Table4.5.
TABLE-4.5
DETAILS OF INCREMENTAL CONCENTRATION OF POLLUTANTS
ON FOREST BLOCKS AND SENSITIVE LOCATIONS
Pollutant
Base
line
SPM
Rabo RF
Taraimal RF
Lotan RF
Urdana RF
PF near Bendajhariya village
Burha pahar RF
Bhalunara RF
PF (Daharidih village)
Bargarh RF
Endu RF
Panikhet PF
Suhai RF
SO2
Rabo RF
Taraimal RF
Lotan RF
Urdana RF
PF near Bendajhariya village
Burha pahar RF
Bhalunara RF
PF (Daharidih village)
Bargarh RF
Endu RF
Panikhet PF
Suhai RF
Nox
Rabo RF
Taraimal RF
Lotan RF
Urdana RF
PF near Bendajhariya village
Burha pahar RF
Bhalunara RF
PF (Daharidih village)
Bargarh RF
Endu RF
Panikhet PF
Suhai RF
Concentration (
g/m3)
Incremental
Resultant
Distance
Direction
72.0
48.7
62.9
71.2
87.5
82.1
87.5
80.1
80.2
71.2
73.7
72.0
0.2
<0.1
<0.1
<0.1
1.4
1.4
<0.1
<0.1
<0.1
<0.1
<0.1
<0.1
72.2
48.7
62.9
71.2
88.9
83.5
87.5
80.1
80.2
71.2
73.7
72.0
0.8
8.2
6.6
9.2
4.1
4.9
5.4
9.3
5.3
7.4
8.1
8.9
NNE
ENE
NNW
E
SW
SW
W
NE
WNW
NW
NNE
NNE
8.1
8.2
9.8
10.9
10.9
12.2
11.6
9.3
8.9
8.2
8.3
8.2
10.0
<0.1
<0.1
<0.1
6.0
10.0
<0.1
<0.1
<0.1
<0.1
<0.1
<0.1
18.1
8.2
9.8
10.9
16.9
22.2
11.6
9.3
8.9
8.2
8.3
8.2
10.8
9.9
12.4
13.8
12.5
14.3
14.9
11.3
12.6
9.9
12.4
11.2
8.0
<0.1
<0.1
<0.1
8.0
8.0
<0.1
<0.1
<0.1
<0.1
<0.1
<0.1
18.8
9.9
12.4
13.8
20.5
22.3
14.9
11.3
12.6
9.9
12.4
11.2
0.8
8.2
6.6
9.2
4.1
4.9
5.4
9.3
5.3
7.4
8.1
8.9
0.8
8.2
6.6
9.2
4.1
4.9
5.4
9.3
5.3
7.4
8.1
8.9
0.8
NNE
ENE
NNW
E
SW
SW
W
NE
WNW
NW
NNE
NNE
NNE
ENE
NNW
E
SW
SW
W
NE
WNW
NW
NNE
NNE
NNE
C4-7
FIGURE-4.1
SHORT TERM 24 HOURLY INCREMENTAL GLCs OF SPM
VIMTA Labs Limited, Hyderabad
C4-8
FIGURE-4.2
SHORT TERM 24 HOURLY INCREMENTAL GLCs of SO2
VIMTA Labs Limited, Hyderabad
C4-9
FIGURE-4.3
SHORT TERM 24 HOURLY INCREMENTAL GLCs of NOx
VIMTA Labs Limited, Hyderabad
C4-10
4.3.3
4.3.4
C4-11
will used for ash handling plant, coal handling plant and green belt.
Garland drains around the ash pond site will be provided for the collection of runoff water during monsoon season.
The storm water in the project area will be collected through storm water drains
and collected in the storm water tank, which is lined to prevent any
contamination of ground water. The stored storm water will be utilized in the
plant operation resulting in conservation of fresh water. Suitable rain water
harvesting pits will be provided along the storm water drain to recharge the
ground water table. In case the storm water tank starts overflowing, the same
will be discharged into nearby nalla.
Various types of wastewater to be generated in the proposed project with their
quantity, expected pollutants and treatment proposed are given in Table-4.6.
TABLE-4.6
TYPES OF WASTEWATER GENERATION AND TREATMENT DETAILS
All values are given in m3/hr
Sr.
No.
1
Type of Wastewater
Cooling tower blow down
Quantity
(m3/hr)
126
Expected
Pollutants
Higher TDS
40
Higher TDS
10
O&G,
TDS,
TSS, acidity
O&G, TSS
5
6
7
8
55
40
224
16
177
TSS,
TDS,
BOD, COD
TSS,
TDS,
BOD, COD
TSS,
TDS,
BOD, COD
Treatment Proposed
278 Sent
to
central
monitoring basin, CMB; 250consumed in AHP & CHP
Sent
to
CMB
after
neutralisation
Neutralization pit and sent to
CMB
Passed through Oil water
separator and sent to CMB
688
The expected quality of raw and treated wastewater from the power plant
including sewage water and discharge limits as specified by environment
protection rules is given in Table-4.7.
C4-12
TABLE-4.7
EXPECTED QUALITY OF WASTEWATER
Sr.
No.
Parameter
Unit
Raw
wastewater
Treated
Wastewater
1
2
3
4
pH
Suspended Solids
Oil & Grease
Total
Dissolved
Solids
BOD
COD
mg/l
mg/l
mg/l
5.5 to 9.0
100 to 500
10 to 200
500 to 10000
6.0 to 8.5
<100
<5
<1000
Permissible Limits as
per GSR 422 (E) for
On-land Discharge
(Irrigation)
5.5 to 9.0
200
10
--
mg/l
mg/l
250 to 350
450 to 600
<30
<100
100
-
5
6
4.3.6
Impact on Soil
Most of the impacts of power plant project on soils are restricted to the construction
phase, which will get stabilized during operational phase. The impact on the topsoil
will be confined to the proposed main plant area only. Further, the greenbelt
proposed will have a very positive impact on soil quality.
The probable sources of degradation of soil quality will be due to generation &
disposal of ash and fugitive dust emissions. However, the impacts due to disposal of
ash are covered under Section-4.3.8.
The airborne fugitive dust from the plant is likely to be deposited on the topsoil in
the immediate vicinity of the plant boundary. However, the fugitive emissions are
likely to be controlled to a great extent through proposed control measures like
water sprinkling and development of greenbelt development.
Hence, no major impact is envisaged on soil quality of the project site.
4.3.7
C4-13
plant. Coal consumption of 6.02 MTPA was considered for estimation of ash
generation. Ash will be generated as both forms viz. bottom ash and fly ash.
About 80% of the total ash generation will be fly ash and remaining 20% comes
as bottom ash. The fly ash is the important air pollutant, which emits to outside
environment through stacks attached to boilers. ESPs with >99.95% efficient
shall be provided to prevent ash dispersions into ambient air. The details of the
solid waste generation are given in Table-4.8.
TABLE-4.8
EXPECTED SOLID WASTE FROM POWER PLANT
Sr. No.
1
Plant
Ash
Bottom ash
Fly ash
Used Oil
Quantity of Generation
2.47 MTPA
0.49 MTPA
1.98 MTPA
8000 KLPA
1.75 Lakh kg/annum
1200 TPA
Mode of Disposal
Emphasis will be given for supply to
potential
users
in
dry
from.
Remaining ash will be disposed into
HDPE lined ash pond.
Will be supplied to authorized
recyclers
Sent to sludge drying beds and used
as manure
Organic portion will be dried,
composted and used as manure
It is proposed to collect fly ash from ESP hoppers in dry from and provide/supply
to potential ash users depending on the demand. The balance unutilized ash will
be disposed off using Lean Slurry Disposal technology. An area of about 310
acres has been identified for ash pond within the project premises. In view of the
proposed Lean Slurry ash disposal technology, the impact of ash pond
supernatant runoff would not be expected and the impacts on surrounding
environment would be insignificant. However, it is also proposed to provide the
ash pond with an impervious HDPE layers.
The sludge from sewage treatment plant will be dried, vermi-composted and used
as manure for greenbelt maintenance. Canteen/sanitary waste will be composted
and used as manure for greenbelt development.
With the implementation of above precautionary measures, the impacts due to
solid waste disposal will be minimum.
In ash disposal, Lean Slurry Disposal method will be adopted. The bottom ash
slurry and fly ash slurry from the both the units will be led to common slurry sump
of the combined ash slurry disposal pump house. In view of the proposed Lean
Slurry ash disposal technology, the impact of ash pond supernatant run off would
not be expected. Hence, the impact of the ash pond on the surface water will be
insignificant.
C4-14
the pond will be constructed with proper compaction at maximum dry density. The
co-efficient of permeability will be much less than the natural deposits to further
reduce the drainability. However, with the passage of time, more and more fly ash
particles will get deposited in the pore spaces of the top soil making it essentially
non-porous and impervious and in view of the above, contamination through
leaching is not envisaged. However, it is also proposed to provide the ash pond
with an impervious bottom HDPE layers.
In view of the above mitigative measures, no surface water or groundwater
pollution is anticipated from the ash disposal area. Similarly, as the other solid
wastes also used properly, no impact of solid waste is envisaged.
4.3.8 Impacts on Ecology
Detailed flora and fauna studies were carried out during study period and the
details are presented in Section-3.8 of Chapter-3. About 251 plant species were
identified and these are commonly growing plant species of the region. As per
records of forest department of Raigarh, literature survey and also from field
studies, there are no endangered, threatened and protected plants. 82 animal
species were recorded/reported from study area during study period, out of which 3
species belongs to Sch-I, 7 species belong to Sch-II, 3 species belongs to Sch-III
and rest of the species belongs to Sch-IV and Sch-V as per Wildlife Protection Act,
1972.
It is proposed to develop greenbelt with an average width of about 50-m to 100m around plant site and implementation of eco development along with local
people will enhance the greenery of the area. Hence, no significant adverse
negative impact is envisaged on terrestrial ecology.
The impacts on aquatic ecology due to proposed project would be negligible as the
treated effluents from the proposed power project will meet the prescribed
standards prior to final discharge.
Similarly, as the discharge water will not have much higher temperature than the
receiving body, no thermal effects on receiving body due to discharge are
envisaged.
Hence, minimal impact is envisaged on the ecology of the area.
4.3.9
C4-15
TABLE-4.9
MAJOR NOISE GENERATING SOURCES
Sr. No.
1
2
3
4
5
Sources
Turbine units
Cooling tower
Air compressors
Transformer
Boilers
Nature of Noise
Continuous
Continuous
Continuous
Continuous
Continuous
Direction
1
2
3
4
5
6
7
8
N
NE
E
SE
S
SW
W
NW
The predicted noise levels at the boundary due to various plant activities will be
ranging in between <30 to 32 dB (A). The incremental noise levels will be less
than 40 dB(A) at all the surrounding habitations. It is seen from the simulation
results that the incremental noise levels will be well within the CPCB standards.
4.3.9.2 Impact on Work Zone
Boilers and cooling towers are the high noise generating equipments in the
proposed power plant. However, impacts on the working personnel are not
expected to be significant on account of the high level of automation of the plant,
which means that workers will be exposed for short duration only and that too
intermittently.
The noise generation during operational phase would be at source itself through
different measures such as inspection, operation and maintenance at regular
intervals. The noise control measures as described in EMP will be fully followed.
The occupational noise exposure to the workers in the form of 8-hourly time
weighted average will be maintained well within the prescribed OSHA standards
(<90 dB(A)). Hence, the impact on occupational health of workers would be
insignificant.
VIMTA Labs Limited, Hyderabad
C4-16
-1000
1000
-800
-600
-400
-200
200
400
600
800
1000
1000.00
800
800.00
600
600.00
400
400.00
200
200.00
0.00
-200
-200.00
-400
-400.00
-600
-600.00
-800
-800.00
-1000
-1000.00
-800.00
-600.00
-400.00
-200.00
0.00
200.00
400.00
600.00
800.00
-1000.00
1000.00
FIGURE-4.4
PREDICTED NOISE DISPERSION CONTOURS
VIMTA Labs Limited, Hyderabad
C4-17
C4-18
The approach road to project site shall be appropriately widened and strengthened
to facilitate vehicular movement.
The greenbelt area shall be delineated before start-up of earthwork and tree
plantation shall be taken up during construction.
4.4.2 Air Quality Management
The activities like site development, grading and vehicular traffic contribute to
increase in SPM and NOx concentration. The mitigation measures recommended to
minimize the impacts are:
4.5
C4-19
Installation of ESP of efficiency more than 99.9% to limit the SPM concentrations
below 50 mg/Nm3;
Provision of bi-flue stack of 275-m height for wider dispersion of gaseous
emissions;
The plant raw water requirement shall be optimised. The COC in cooling system
shall be maximised (such as COC=6);
The effluent carrying oil spillage in the plant area shall be sent to oil-water
separator for removal of oil;
C4-20
Coal stock piles and ash ponds shall be provided with garland drains and water
shall be treated for suspended / floating solids;
Lining of effluent pond suitably to prevent any seepage into ground to avoid any
groundwater contamination;
Provision of separate storm water system to collect and store run-off water
during rainy season and utilization of the same in the process to reduce the
fresh water requirement;
Final disposal shall be through open channel with natural cascade aeration
arrangement to improve DO in treated effluent;
Treated effluents from all streams should be stored in CMB/Effluent Pond /Guard
Pond having 5 to 6 days detention time and the aquaculture may be practiced
with bioassay tests on regular basis;
in
toilet
flushing,
greenbelt
The wastewater from various units of the plant shall be appropriately treated and
disposed.
Type of Wastewater
Cooling tower blow down
Boiler blow down
DM plant regeneration waste
Service water
Effluents from fuel storage areas, floor washings,
runoff from Oil handling area
Sewage from township and plant
4.5.3
Treatment Proposed
Sent to central monitoring basin, CMB
Sent to CMB
Neutralization pit and sent to CMB
Treated in ETP (flocculator, settling tank)
and sent to CMB
Passed through Oil water separator and
sent to CMB
Treated in STP
C4-21
FIGURE-4.5
RAIN WATER HARVESTING STRUCTURE
VIMTA Labs Limited, Hyderabad
C4-22
The run-off from the paved surfaces of the proposed facility will be routed
through a carefully designed storm water drainage network and collected in storm
water collection sump and excess rainwater will be discharged to bore wells
constructed on these internal drains.
The run-off from the pervious area will be routed directly to the rainwater
harvesting structures constructed at suitable locations as per the contours.
For augmenting the ground water resources in the plant premises, number of
rainwater harvesting pits will be constructed and the internal drains where excess
rain water flowing in drain will be diverted to these pits. These structures will
facilitate percolation of water into the ground and thus augmenting the
groundwater sources. The roof top water will be routed to the storm drains. This
will result in increase in groundwater tables and to some extent the improvement
of ground water quality.
The size and the locations of rainwater harvesting pits will be decided during
detailed engineering of the project.
Run off from the proposed project site is calculated using rational formula:
Q=CxIXA
Q = Run-off in m3/hr
A = Catchment Area (ha)
C = Coefficient of Run-off
I = intensity of Rainfall in mm/hr
Total area
= 388.5-ha
Intensity of Rainfall (I) = 2.5 cm/hr (1 inch/hr)
Run-off co-efficient (C) = 0.7
Q = 0.7 x (2.5/100) m/hr x (388.5 x 10000) m2
= 67987.5m3/hr
4.5.3.2 Storm Water Management
The power plant water management system will be designed to minimize the
potential for storm water contamination occurring at the site. This will be
achieved by incorporating the following features into the storm water
management system:
VIMTA Labs Limited, Hyderabad
C4-23
Run-off from upstream areas will be diverted around the plant site;
The quantity of contaminated run-off generated will be minimized by diverting
run-off from areas external to the plant to storm water discharge points;
Hazardous material and fuel storage areas will be bunded and drains will be
provided to around these facilities to prevent entering of run-off water; and
Run-off from area external to process areas of the plant will be contained
within a storage system.
The excess ash will be disposed off using lean slurry disposal system to HDPE
lined ash pond;
The generated waste oil shall be explored to be used in boiler furnace with HFO
or shall be given to authorized recyclers;
The organic portion of solid waste generated in the Sewage Treatment Plant
(STP) will be used as manure in greenbelt development; and
Maintaining the data base on solid waste generation such as quantity, quality,
treatment/management.
C4-24
Ash Generation
1
2
3
4
5
6
7
8
9
MTPA
0.46
0.46
0.46
0.46
0.46
0.46
0.46
0.46
0.46
Ash Utilization
%
20
30
40
50
60
70
80
90
100
MTPA
0.0921
0.13815
0.1842
0.23025
0.2763
0.32235
0.3684
0.41445
0.4605
Ash Diverted to
Ash Storage Yard
MTPA
0.3684
0.32235
0.2763
0.23025
0.1842
0.13815
0.0921
0.04605
0
Cumulative
Total of
Disposal
MTPA
0.09
0.14
0.18
0.23
0.28
0.32
0.37
0.41
0.46
C4-25
In the proposed power plant, various avenues for ash utilization will be explored
as delineated in the above sections. In particular, supply of quality ash for
manufacture of cement will be taken as there are some cement units. Some of
the actions planned for the project are as given below:
SKS Power Generation (Chhattisgarh) Limited will encourage the use of water
treated fly ash as a soil ameliorator and as a source of micro-nutrients and
secondary nutrients for improving agricultural productivity.
4.5.5.4 Conclusion
All efforts will be made for maximum utilization of ash. However, after reviewing
various proposals of the ash utilization, 40-70% of ash utilization is possible at
the initial period and same will be improved over the period of time in future. SKS
Power Generation Limited is committed to explore possibilities for ash utilization
considering new technologies and avenues and try to achieve the target fixed by
MoEF in this regard.
SKS Power Generation Limited is committed to comply with the Fly Ash
Utilization Notification, 1999 and as amended thereof.
4.5.5.5 Fly Ash Disposal
The balance ash after utilisation shall be disposed in ash ponds. Ash disposal system
proposed is Lean Slurry Disposal. Treated wastewater will be used in ash handling
plant. The ash pond will be provided with HDPE liners. The area provided for ash
pond is about 310-acre.
The major advantages of the Lean Slurry Disposal method are:
C4-26
Both bottom ash and fly ash can be disposed together if needed; and
The trenches will be constructed along the periphery of the ash pond to collect
the run-off water during rainy days. The run-off water will be routed through
sedimentation tank before discharging into nalla.
The ash will be utilized in various construction materials to the maximum extent and
100% utilization will be achieved.
4.6
Greenbelt Development
With rapid industrialization and consequent deleterious impact of pollutants on
environment, values of environmental protection offered by trees are becoming
clear. Trees are very suitable for detecting, recognizing and reducing air pollution
effects. Monitoring of biological effects of air pollutant by the use of plants as
indicators has been applied on local, regional and national scale. Trees function as
sinks of air pollutants, besides their bio-esthetical values, owing to its large
surface area.
The greenbelt development not only functions as foreground and background
landscape features resulting in harmonizing and amalgamating the physical
structures of the plant with surrounding environment, but also acts as pollution
sink. Thus, implementation of afforestation program is of paramount importance.
It will also check soil erosion, make the ecosystem more complex and functionally
more stable and make the climate more conducive.
Greenbelt with a width of 50-m to 100-m will be developed around the plant site.
The total greenbelt around the power plant complex will be about (137.5-acre)
which works out to about 1/3rd of total project area including green belt in the
town ship.
In the proposed greenbelt about 343750 trees will be planted with a density of
2500 trees/acre. A capital cost of Rs. 1.0 Crore and an annual budget of Rs.2.0
Crore will be earmarked for this purpose. The plantation schedule will be
completed within five years from the construction period of the project. The
plantation schedule is given in Table-4.12.
TABLE-4.12
GREENBELT DEVELOPMENT SCHEDULE
Sr. No.
1
2
3
4
5
Total
Year
1st Year
2nd Year
3rd Year
4th Year
5th Year
Area (acre)
No. Saplings
27.5
27.5
27.5
27.5
27.5
68,750
68,750
68,750
68,750
68,750
137.5
343750
The layout plan of the greenbelt and tree cover in plant area is shown in Figure4.6.
C4-27
Chapter-4
Anticipated Environmental Impacts and Mitigation Measures
FIGURE-4.6
GREENBELT DEVELOPMENT PLAN
VIMTA Labs Limited, Hyderabad
C4-28
4.6.1
Providing shade.
Based on the above, the recommended species for greenbelt and plantation are
given in Table-4.13. Further, the already existing / native species will be given
preference.
TABLE-4.13
RECOMMENDED PLANTS FOR GREENBELT
Note: S: Small, M: Medium, L: Large
Sr.
No.
Hindi
Name
Size of Plant
Type and Suitable site
Acacia
auriculaeformis
(Mimosaceae)
Height: 5m
Adina cordifolia (Rubiaceae)
Height: 20m
Aegle marmelos( Rutaceae)
Height: 12m
Anogeissus latifolia
( Combretaceae)
Artabotrys
hexapetaius
(Annonaceae)
Height: 10m
Averrhoa carambola
(Averrhoaceae Oxalidaceae)
Height: 5m
Azadirachta India (Meliaceae)
Height: 20m
Vilaiti
Haldu
2
3
4
5
10
Bauhinia
(Caesalpiniaceae)
Height: 5m
Borassus flabellifer
Height: 20m
Boswellia serrata
(Burseraceae)
variegate
Bael
Dhaura
Hara
Champa
Kamrak
Nim
Kachanar
Tad
Kundur
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
Hindi
Name
Palas
Gulutora
Size of Plant
Type and Suitable site
Kumbi
Karaunda
Mari
Amaltas
Jungli
saru
Mahanim
Din-karaja
Garari
Nariyal
Shisham
Gul Mohar
Chalta
Aggai
Amla
Dauldhak
Dadap
Bargad
Pipal
Hindi
Name
42
Height: 20m
Gmelina arborea
(Verbenaceae)
Height: 3-5m
Grewia tiloifolia
(Tiliaceae)
Height:3- 5m
Hamelia patents
(Rubiaceae)
Height: 3m
Hardwickia binata
(Leguminosae)
Height: 3-5m
Hibiscus mutabilis
(Malvaceae)
Height: 3-5m
H. rosa sinensis
Height: 3m
Lxora arbprea
(Rubiaceae)
Height: 1-2m
Lxora coccinea
Height: 1-2m
Jasminum sbrahmanir (Oleaceae)
43
Pula
44
Lagerstroemia speciosa
(Lythraceae)
Height: 10m
Lannea coramandelica
(Anacardiaceae)
Height: 3-5m
Lawsonia alba (Lythraceae)
Height: 3-5m
Madhuca indica
(Sapotaceae)
Height: 5-8m
Mallotus philippensis
(Euphorbiaceae)
Height: 5-8m
Melia azedarach
(Meliaceae)
Height: 5-8m
Millingtonia hortensis
( Bignoniaceae)
Height: 3-5m
Mimusops elengi
(Sapotaceae)
Height: 10m
Moringa oleifera
(Moringaceae)
Height: 10m
Murava koenigii (Rutaceae)
Height: 3-5m
Jarul
34
35
36
37
38
39
40
41
45
46
47
48
49
50
51
52
53
54
Sewan
Dhamim
Anjan
Sthal
kamal
Jasut
Nevari
Rangan
Moghra
Size of Plant
Type and Suitable site
also as a single tree in isolated sites
M; deciduous , good in green belts
around flare sites
M; good in green belts for use as timber
Jhingan
Mehndi
Mahua
Sindur
Bakain
Akas Nim
Maulsari
Sainjna
Mitha
Neem
Royal
palm
Hindi
Name
55
Pandanus odoratissimus
(Pandanaceae)
Height: 1-2m
Peltophorum inerma
(Leguminosae, Caaesalpiniaceae)
Height: 3-5m
Pliumeria acuuminata
(Apocynaceae)
Height: 3-4m
Plumeria alba
(Apocynaceae)
Height: 3-4m
Plumeria rubra
Height: 3-4m
Pterocarpus
marsupium
(Leguminosae, Papilionaceae)
Height: 3-5m
Pogamia pinnata (Leguminosae,
Papilionaceae)
Height: 3-5m
Samalia malabarica (Bombaceae)
Height: 3-5m
Samanea saman (Leguminosae)
Height: 20m
Saraca
indica
(Leguminosae,
Caesalpinaceae)
Height: 5m
Spathodia campanulata
(Bignoniaceae)
Height: 12m
Syzygium cuminii (Myyrtaceae)
Height: 20m
Tabernamontana coronaria
(Apocynaceae)
Height: 2-3m
Tabebuia
pentaphylla
(Bignomiaceae)
Height: 20m
Tamarindus indica (Leguminosae,
caesalpiniaceae)
Height: 20m
Xylia
xyicarpa
(Leguminosae;Minosaceae)
Height: 2m
Zanthoxyium(Rutaceae)
Height: 2m
Kewada
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
Size of Plant
Type and Suitable site
S; a densely branched shrub; good in
gardens near sea shore
M; Semi evergreen, suitable on road
sides, in gardens & outside office buildings
Golainchi
Golaonchi
Bija
Karanj
Semul
Asok
Ruugtoora
Jaman
Chandni
Imli
Jambu
Badrang
C4-32
TABLE-4.14
COST PROVISION FOR ENVIRONMENTAL MEASURES
Sr. No.
1
2
3
4
5
6
7
Description of item
Fly ash control (ESP)
SO2 control (Stacks)
Water (ETP)
Solid waste (Ash handling plant)
Ash pond
Monitoring instruments
Green Belt
Total
C4-33
5.0
5.1
C5-1
Site#1 (Binjkot)
Site#2
(Pandapani/
Dumarpali)
Raigarh
Site#3
(Munund/
Barbaspur)
Dharamjaigarh
Site#4
(Jamgaon)
Nearest Town/
Tehsil
Kharsia
Connectivity
Water Source
Mahanadi River:
30-km
Mahanadi River:
75-km
Mahanadi River:
45-km
Coal Source
Fatehpur Coal
Block: 65-km
Fatehpur Coal
Block: 75-km
Fatehpur Coal
Block: 35-km
Fatehpur Coal
Block: 85-km
Power
Evacuation
Kotra substation :
15 km
Kotra substation :
10 km
Kotra substation :
85 km
Kotra substation :
45 km
Remarks
Non-availability of
sufficient land. Site
is surrounded by
forests.
Uranium reserves
were found and
land is not
advisable for
other industries
Raigarh
C5-2
After evaluation, a site near Binjkot village, Kharsia tehsil, Raigarh district, having
major favorable features along with good environmental features has been
identified for the proposed project.
The Binjkot site has the following advantages:
Rail connectivity is 1.0-km away from the proposed site and power
evacuation is near to the proposed site.
Road connectivity is less than 3-Kms.
Availability of the land.
Close to Fathepur coal block.
Close to PGCIL substation fpr power evacuation (about 15-kms)
Nearest national high way (NH-200) is at about 15-Kms from the selected
site and nearest state highway (Kharsia-Raigarh) is at 1.7-km from the
proposed site.
Nearest rail way station (Robertson RS) is at about 2.4-Km away from the
proposed site.
Selected site is mix of barren land (40%) & dry agricultural land (60%).
Water source from Mahanadi River at about 30-km from the selected site.
No forest land with in the project site.
No National Parks, Wildlife sanctuaries in 15-km radius;
Availability of required plain land.
There are no human settlements, habitations or forests in the project area;
and
Least R&R issues involved in the project;
Sufficient water is available from Mahanadi river , at a distance of 30-km
from the site;
The alternative sites considered for the proposed power plant are shown in
Figure-5.1.
C5-3
FIGURE-5.1
ALTERNATIVE SITES CONSIDERED FOR THE PROPOSED POWER PLANT
VIMTA Labs Limited, Hyderabad
C5-4
6.0
6.1
Introduction
Regular monitoring of environmental parameters is of immense importance to
assess the status of environment during project operation. With the knowledge of
baseline conditions, the monitoring programme will serve as an indicator for any
deterioration in environmental conditions due to operation of the project, to enable
taking up suitable mitigatory steps in time to safeguard the environment.
Monitoring is as important as that of control of pollution since the efficiency of
control measures can only be determined by monitoring.
Usually, as in the case of the study, an Impact Assessment study is carried over
short period of time and the data cannot bring out all variations induced by the
natural or human activities. Therefore, regular monitoring programme of the
environmental parameters is essential to take into account the changes in the
environmental quality.
6.2
6.3
Monitoring Schedule
Environmental monitoring schedules are prepared covering various phases of
project advancement, such as constructional phase and regular operational phase.
6.3.1
C6-1
Potential
Impact
Air Emissions
Noise
Action to be Followed
All
equipments
are
operated within specified
design parameters.
Vehicle
trips
to
be
minimized to the extent
possible
Maintenance of DG set
emissions
to
meet
stipulated standards
Ambient air quality within
the
premises
of
the
proposed
unit
to
be
monitored.
Gaseous emissions
(SO2, HC, CO, NOx)
Equipment
noise reading
Equipment
to
be
maintained in good working
order.
Night working is to be
minimized.
Generation
of
vehicular
noise
Noise to be monitored in
ambient air within the plant
premises.
Wastewater
Discharge
Soil Erosion
Drainage and
effluent
Management
Waste
Management
Parameters for
Monitoring
Random checks of
equipment
logs/
manuals
Vehicle logs
No untreated discharge to
be made to surface water,
groundwater or soil.
Protect topsoil stockpile
where possible at edge of
site.
Ensure drainage system
and
specific
design
measures
are
working
effectively.
The design to incorporate
existing drainage pattern
and avoid disturbing the
same.
Implement
waste
management
plan
that
The
ambient
air
quality will conform
to the standards for
SPM, RPM,SO2, NOx,
and CO
logs,
Working
hour
records
Maintenance
of
records of vehicles
Spot Noise recording
Frequency of
Monitoring
Periodic
Periodic
during
site clearance &
construction
activities
Periodic
emission
monitoring
As per CPCB/
SPCB
requirement or
on monthly basis
whichever
is
earlier
Regular
during
construction
activities
Daily records
Daily records
Visual inspection of
drainage
and
records thereof
As
per
CPCB/SPCB
requirement or
on
quarterly
basis whichever
is earlier
Periodic
during
construction
activities
Periodic
during
construction
activities
Periodic
during
construction
activities
Comprehensive
Waste Management
Periodic
during
No discharge hoses
shall be in vicinity of
watercourses.
Effective cover in
place.
check
C6-2
Sr.
No.
Potential
Impact
Action to be Followed
identifies and characterizes
every
waste
arising
associated with proposed
activities
and
which
identifies the procedures
for collection, handling &
disposal of each waste
arising.
Non-routine
events and
accidental
releases
Health
Environmental
Management
Cell/ Unit
10
6.3.2
Loss of flora
and fauna
Parameters for
Monitoring
Plan should be in
place and available
for inspection onsite.
Compliance
with
MSW Rules, 1998
and
Hazardous
Wastes
(Management
and
Handling
Rules),
2003
Mock
drills
and
records of the same
Frequency of
Monitoring
construction
activities
Periodic
during
construction
activities
All
relevant
parameters including
HIV
Responsibilities and
roles will be decided
before
the
commencement
of
work.
Regular
ups
No.
of
species
During
site
clearance Phase
plants,
check
During
construction
phase
on
the
C6-3
TABLE-6.2
ENVIRONMENTAL MONITORING DURING OPERATIONAL PHASE
Sr.
No.
1
Potential
Impact
Air Emissions
Action to be Followed
Stack emissions from power
boilers to be optimized and
monitored
Noise
Vehicle
trips
to
be
minimized to the extent
possible
Noise
generated
from
operation
of
power
boilers/cooing towers to be
optimized and monitored
Parameters for
Monitoring
Gaseous emissions
(SPM, SO2, CO,
NOx)
Gaseous emissions
HC,
CO,
(SO2,
NOx)
SPM, RPM, SO2,
NOx, CO and HC.
Frequency of
Monitoring
Continuous
monitoring using
on-line
equipment
during operation
phase
Periodic during
operation phase
As per CPCB/
SPCB
requirement or
on weakly basis
whichever
is
earlier
Vehicle logs to be
maintained
Wind
speed,
direction,
temp.,
relative humidity
and rainfall.
Vehicle logs
Continuous
monitoring using
on-line weather
station
during
operation phase
Daily records
Periodic during
operation phase
Maintain
records
of vehicles
Regular check ups
Periodic
operation
Periodic
operation
Discharge norms
for effluents
Periodic during
operation phase
pH,
Once in a week
Noise
generated
from
operation of DG set to be
optimized and monitored
DG sets to generate less
than 75 dB(A) Leq at 1-m
from the source
Wastewater
Discharge
TSS,
TDS,
during
phase
during
phase
C6-4
Sr.
No.
Potential
Impact
Action to be Followed
discharge to standards
Water Quality
and Water
Levels
Emergency
preparedness,
such as fire
fighting
Maintenance of
flora and fauna
Waste
Management
6.4
Drainage and
effluent
Management
10
Soil quality
11
Health
Compliance
of
treated
sewage to standards
Ensure drainage system and
specific design measures
are working effectively.
Design
to
incorporate
existing drainage pattern
and avoid disturbing the
same.
Monitoring
used
water
quality, groundwater quality
around
ash
pond
and
ground water levels
River
water
quality
downstream to discharge
Contaminants such as VOCs
to be reduced by providing
adequate ventilation
Parameters for
Monitoring
BOD,
COD
&
Temperature
Comprehensive as
per GSR 422(E)
Visual
inspection
of drainage and
records thereof
Frequency of
Monitoring
during operation
phase
Once
in
a
season
Periodic during
operation phase
Comprehensive
monitoring as per
IS 10500
Periodic during
operation phase
Groundwater level
in meters bgl
As per IS 2296
Monitoring
of
indoor
air
contaminants such
as CO, CO2 and
VOCs.
Mock drill records,
on site emergency
plan,
evacuation
plan
Once in a week
As per CPCB/
SPCB
requirement
Periodic during
operation phase
No.
of
plants,
species
Records of solid
waste generation,
treatment
and
disposal
Periodic
operation
Periodic
operation
during
phase
during
phase
Physico-chemical
parameters
and
metals.
All
relevant
parameters
including HIV
Periodical
monitoring
at
ash pond site
Regular
check
ups
C6-5
6.4.1
C6-6
documented and compared against the design values for any necessary corrective
action. This is checked on a daily basis and monthly reports are submitted to the
authorities concerned.
6.4.2.2 Monitoring of Groundwater
The monitoring of groundwater is the most important tool to test the efficiency of
ash pond performance. This is indispensable as it provides detection of the
presence of waste constituents in groundwater in case of leachate migration. In
this programme, water samples are taken at a predetermined interval and analysed
for specific pollutant expected to be in the leachate. For early detection of leachate
migration, if any, it is suggested to construct piezometers around the ash pond
site.
In addition to piezometers, monitoring wells should be installed to a depth of at
least 3-m below the maximum historic groundwater depth. Based on assumptions
and data about the characteristics of leachate to be generated, approximate
permeability of soils in the zone of aeration and direction and velocities of
groundwater flow, the maximum probable aerial extent of contaminant migration
can be estimated as a basis for establishing the position of monitoring wells.
A minimum of two ground monitoring wells should be typically installed at ash
disposal facility: one up-gradient well and one down-gradient well. It is suggested
to collect water samples and analyse. Records of analysis should be maintained.
All these observations are made on a daily & weekly basis and abnormalities are
controlled immediately.
6.4.3
Noise Levels
Noise levels in the work zone environment such as boiler house, cooling tower
area, DG house shall be monitored. The frequency shall be once in three months in
the work zone. Similarly, ambient noise levels near habitations shall also be
monitored once in three months. Audiometric tests should be conducted
periodically for the employees working close to the high noise sources. Periodic
checks and walk down checks are made on shift basis and any abnormality is
attended immediately.
6.5
C6-7
6.6
C6-8
7.0
7.1
Introduction
Hazard analysis involves the identification and quantification of the various
hazards (unsafe conditions) that exist in the proposed power plant operations. On
the other hand, risk analysis deals with the recognition and computation of risks,
the equipment in the plant and personnel are prone to, due to accidents resulting
from the hazards present in the plant.
Risk analysis follows an extensive hazard analysis. It involves the identification and
assessment of risks the neighboring populations are exposed to as a result of
hazards present. This requires a thorough knowledge of failure probability, credible
accident scenario, vulnerability of population etc. Much of this information is difficult
to get or generate. Consequently, the risk analysis is often confined to maximum
credible accident studies.
In the sections below, the identification of various hazards, probable risks in the
proposed power plant, maximum credible accident analysis, consequence analysis
are addressed which gives a broad identification of risks involved in the plant. The
Disaster Management Plan (DMP) has been presented.
7.2
7.3
Hazard Identification
Identification of hazards in the proposed power plant is of primary significance in the
analysis, quantification and cost effective control of accidents involving chemicals
and process. A classical definition of hazard states that hazard is in fact the
characteristic of system/plant/process that presents potential for an accident.
Hence, all the components of a system/plant/process need to be thoroughly
examined to assess their potential for initiating or propagating an unplanned
C7-1
7.3.1
Identification of hazardous units and segments of plants and storage units based
on relative ranking technique, viz. Fire-Explosion and Toxicity Index (FE&TI).
Hazardous Properties
UN 1203. Dangerous Goods class 3 Flammable Liquid
Dangerous Goods class 3 - Flammable Liquid
LDO
HFO
TABLE-7.2
CATEGORY WISE SCHEDULE OF STORAGE TANKS
Sr. No.
Material
1
2
LDO
HFO
No. of
Tanks
1
2
Design Capacity
(KL)
500 (each)
1000 (each)
Classification
Non-dangerous Petroleum
Non-dangerous Petroleum
TABLE-7.3
PROPERTIES OF FUELS USED IN THE PLANT
Chemical
HFO
LDO
TLV
MP
UEL
7.3.2
:
:
:
Codes/Label
Flammable
Flammable
TLV
5 mg/m3
5 mg/m3
FBP
350
400
FBP
FP
LEL
MP
c
-26
-
:
:
:
FP
UEL
LEL
%
66
98
6.0
7.5
0.5
0.6
C7-2
1989 in conjunction with Environment Protection Act, 1986. This is referred here as
GOI Rules 1989. For the purpose of identifying major hazard installations the rules
employ certain criteria based on toxic, flammable and explosive properties of
chemicals.
A systematic analysis of the fuels/chemicals and their quantities of storage has been
carried out, to determine threshold quantities as notified by GOI Rules, 1989 and
the applicable rules are identified. Applicability of storage rules are summarized in
Table-7.4.
TABLE-7.4
APPLICABILITY OF GOI RULES TO FUEL/CHEMICAL STORAGE
Sr.
No.
1
2
Chemical/ Fuel
LDO
HFO
Listed in
Schedule
3(1)
3 (1)
7.4
7.4.1
Methodology
Total
Quantity
(KL)
1X500
1X1000
Capacity (KL)
1X500
2X1000
Hazard Identified
Fire/Explosion
Fire/Explosion
TABLE-7.6
PRELIMINARY HAZARD ANALYSIS FOR THE WHOLE PLANT IN GENERAL
PHA
Category
Environmental
Description of
Plausible
Hazard
If there is any
leakage
and
Recommendation
Provision
--
PHA
Category
factors
Environmental
factors
7.4.3
Description of
Plausible
Hazard
eventuality
of
source
of
ignition.
Highly
inflammable
nature of the
liquid fuels may
cause fire hazard
in the storage
facility.
Recommendation
Provision
F&EI Range
0-60
61-96
97-127
128-158
159 and above
Degree of Hazard
Light
Moderate
Intermediate
Heavy
Severe
By comparing the indices F&EI and TI, the unit in question is classified into one of
the following three categories established for the purpose (Table-7.7).
TABLE-7.7
FIRE EXPLOSION AND TOXICITY INDEX
Category
I
II
III
Certain basic minimum preventive and protective measures are recommended for
the three hazard categories.
7.4.3.1 Results of FE and TI for Storage/Process Units
Based on the GOI Rules 1989, the hazardous fuels used by the proposed power
plant were identified. Fire and Explosion are the likely hazards, which may occur due
to the fuel storage. Hence, Fire and Explosion index has been calculated for in plant
storage. Estimates of FE&TI are given in Table-7.8.
VIMTA Labs Limited, Hyderabad
C7-4
TABLE-7.8
FIRE EXPLOSION AND TOXICITY INDEX
Sr. No.
1
2
7.4.4
Chemical/
Fuel
LDO
HFO
Total Capacity
(KL)
1X500
2X1000
F&EI
Category
TI
Category
2.6
4.1
Light
Light
Nil
Nil
Conclusion
Results of FE&TI analysis show that the storage of LDO and HFO falls into Light
category of fire and explosion index with a Nil toxicity index.
7.4.5
The results of consequence analysis are useful for getting information about all
known and unknown effects that are of importance when some failure scenario
occurs in the plant and also to get information as how to deal with the possible
catastrophic events. It also gives the workers in the plant and people living in the
vicinity of the area, an understanding of their personal situation.
The purpose of this listing (refer Table 7.11) is to examine consequences of such
failure individually or in combination. It will be seen from the list that a vast range
of failure cases have been identified. The frequency of occurrence of failure also
varies widely.
C7-5
Fire Damage
A flammable liquid in a pool will burn with a large turbulent diffusion flame. This
releases heat based on the heat of combustion and the burning rate of the liquid. A
part of the heat is radiated while the rest is convected away by rising hot air and
combustion products. The radiations can heat the contents of a nearby storage or
process unit to above its ignition temperature and thus result in a spread of fire.
The radiations can also cause severe burns or fatalities of workers or fire fighters
located within a certain distance. Hence, it will be important to know beforehand the
damage potential of a flammable liquid pool likely to be created due to leakage or
catastrophic failure of a storage or process vessel. This will help to decide the
location of other storage/process vessels, decide the type of protective clothing the
workers/fire fighters, the duration of time for which they can be in the zone, the fire
extinguishing measures needed and the protection methods needed for the nearby
storage/process vessels. The damage effect on equipment and people due to
thermal radiation intensity is given in Table-7.9. Similarly, the effect of incident
radiation intensity and exposure time on lethality is given in Table-7.10.
TABLE-7.9
DAMAGE DUE TO INCIDENT RADIATION INTENSITIES
Sr.
No.
1
Incident
Radiation
(kW/m2)
37.5
25.0
12.5
4.0
1.6
--
C7-6
TABLE-7.10
RADIATION EXPOSURE AND LETHALITY
All values are given in KW/m2
7.4.6
Radiation Intensity
(KW/m2)
1.6
Exposure Time
(seconds)
--
Lethality (%)
Degree of Burns
4.5
4.5
8.0
8.0
8.0
12.0
12.0
12.5
25.0
37.5
20
50
20
50
60
20
50
Inst
Inst
Inst
0
0
0
<1
<1
<1
8
10
50
100
No Discomfort even
after long exposure
1st
1st
1st
3rd
3rd
2nd
3rd
----
Fuel/Chemical
Failure of LDO tank
Failure of two HFO tanks
Total Quantity
Scenarios Considered
1X500
2X1000
Pool fire
Pool fire
TABLE-7.12
PROPERTIES OF FUELS CONSIDERED FOR MODELING
Sr.
No.
1
2
Fuel
LDO
HFO
Molecular weight
(kg/kg mol)
114.24
135.0
Boiling Point
(C)
400
350
Density
(kg/m3)
880
900
C7-7
7.4.7
7.4.8
The maximum capacity of storage of LDO in one tank will be 500 KL. The most
credible failure is the rupture of the largest pipe connecting to the storage tank.
As the worst case, it is assumed that the entire contents leak out into the dyke
forming a pool, which may catch fire on finding a source of ignition.
A perusal of the above table clearly indicates that 37.5 kW/m2 (100% lethality)
occurs within the radius of the pool which is computed at 12.1-m tank on pool
fire. This vulnerable zone will damage all fuel storage equipment falling within the
pool radius.
Similarly, the threshold limit for first degree burns is 1.6 kW/m2, this vulnerable
zone in which the thermal fluxes above the threshold limit for first degree is
restricted to 72.8-m in case tank on pool fire.
The maximum capacity of storage of HFO in each tank will be 1000 KL. The most
credible failure is the rupture of the largest pipe connecting to the storage tank.
As the worst case, it is assumed that the entire contents leak out into the dyke
forming a pool, which may catch fire on finding a source of ignition.
A perusal of the above table clearly indicates that 37.5 kW/m2 (100% lethality)
occurs within the radius of the pool which is computed at 48.1-m tank on pool
fire. This vulnerable zone will damage all fuel storage equipment falling within the
VIMTA Labs Limited, Hyderabad
C7-8
pool radius. Similarly, the threshold limit for first degree burns is 1.6 kW/m2, this
vulnerable zone in which the thermal fluxes above the threshold limit for first degree
is restricted to 290.5-m in case tank on pool fire.
7.4.9 Conclusions on MCA analysis
There will be one LDO storage tank each of 500 KL capacity will be provided in
the LDO tank farm. The results of MCA analysis indicate that the maximum
damage distances for 12.5-Kw/m2 thermal radiations extends upto 22.6-m in the
case of one full tank of 500-KL on fire during worst meteorological conditions. As
the fire resistant dyke walls will be created, no cumulative effect of one tank form
on fire to create fire on other tank farm is envisaged. The damage contours for
tank on fire of one LDO tank is shown in Figure-7.1.
The results of MCA analysis indicate that the maximum damage distances for
12.5-Kw/m2 thermal radiations extends upto 90.0-m in the case of two full tanks
on fire during worst meteorological conditions. As the fire resistant dyke walls will
be created, no cumulative effect of one tank farm on fire to create fire on other
tank farm is envisaged. The damage contours for tank on fire of two HFO tanks is
shown in Figure-7.2.
7.4.10 Coal Handling Plant - Dust Explosion
Coal dust when dispersed in air and ignited would explode. Crusher house and
conveyor systems are most susceptible to this hazard. To be explosive, the dust
mixture should have:
Particles dispersed in the air with minimum size (typical figure is 400
microns);
Dust concentrations must be reasonably uniform; and
Minimum explosive concentration for coal dust (33% volatiles) is 50 gm/m3.
C7-9
FIGURE-7.1
DAMAGE CONTOUR FOR ONE LDO TANK (1X500 KL) ON FIRE
VIMTA Labs Limited, Hyderabad
C7-10
FIGURE-7.2
DAMAGE CONTOUR FOR TWO HFO TANKS (2X1000 KL) ON FIRE
VIMTA Labs Limited, Hyderabad
C7-11
Stockpile areas shall be provided with automatic garden type sprinklers for dust
suppression as well as to reduce spontaneous ignition of the coal stockpiles.
Necessary water distribution network for drinking and service water with pumps,
piping, tanks, valves etc will be provided for distributing water at all transfer
points, crusher house, control rooms etc. for nozzle dust suppression at the zones
like in the crusher chute below breaker plate and the consequent transfer points
will be provided with interlock provision for coal flow.
A centralized control room with microprocessor based control system (PLC) has
been envisaged for operation of the coal handling plant. Except for locally
controlled equipment like traveling tripper, dust extraction/ dust suppression /
ventilation equipment, sump pumps, water distribution system etc, all other inline equipment will be controlled from the central control room but will have
provision for local control as well. All necessary interlocks, control panels, MCCs,
mimic diagrams etc will be provided for safe and reliable operation of the coal
handling plant.
7.4.10.1 Control Measures for Coal Yards
The total quantity of coal shall be stored in separate stockpiles, with proper drains
around to collect washouts during monsoon season.
Water sprinkling system shall be installed on stocks of coal in required scales to
prevent spontaneous combustion and consequent fire hazards. The stock
geometry shall be adopted to maintain minimum exposure of stock pile areas
towards predominant wind direction.
7.4.11 Identification of Hazards
The various hazards associated, with the plant process apart from fuel storage have
been identified and are outlined in Table-7.14.
TABLE-7.14
HAZARD ANALYSIS FOR PROCESS IN POWER PLANT
Sr. No.
1
2
3
4
Blocks/Areas
Coal storage in open yard
Coal Handling Plant including
Bunker area
Boilers
Steam Turbine Generator
Buildings
Hazards Identified
Fire, Spontaneous Combustion
Fire and/or Dust Explosions
Fire (mainly near oil burners), Steam Explosions,
Fuel Explosions
Fires in
a) Lube oil system
b) Cable galleries
c) Short circuits in:
i)Control rooms
ii) Switch-gears
5
6
Risk Rank
3
3
3
Electrocution
Consequences of Interest
Potential for single fatalities, onsite
only
Potential for single fatalities, onsite
only
Potential for single fatalities, onsite
only
Potential for single fatalities, onsite
only
Potential for multiple fatalities,
impact only
impact
impact
impact
impact
onsite
The hazardous event scenarios and risks in general at this facility can be
adequately managed to acceptable levels by performing the recommended
safety studies as part of detailed design, applying recommended control
strategies and implementing a Safety Management System. The equipment
are all provided with enough protection system to fail safe.
Buildings and plant structures shall be designed for cyclone floods and seismic
events to prevent structural collapse and integrity of weather (water) proofing
for storage of dangerous goods;
Provision for adequate water capacity to supply fire protection systems and
critical process water;
C7-13
Provision and integrity of process tanks, waste holding tanks and bunded
areas as per relevant standards;
7.5
7.5.1
Disasters
A disaster is a catastrophic situation in which suddenly, people are plunged into
helplessness and suffering and, as a result, need protection, clothing, shelter,
medical and social care and other necessities of life.
Disasters can be divided into two main groups. In the first, are disasters resulting
from natural phenomena like earthquakes, volcanic eruptions, storm surges,
cyclones, tropical storms, floods, avalanches, landslides, forest fires. The second
group includes disastrous events occasioned by man, or by man's impact upon the
environment. Examples are armed conflict, industrial accidents, radiation accidents,
factory fires, explosions and escape of toxic gases or chemical substances, river
pollution, mining or other structural collapses, air, sea, rail and road transport
accidents which can reach catastrophic dimensions in terms of human loss.
There can be no set criteria for assessing the gravity of a disaster in the abstract
since this depends to a large extent on the physical, economic and social
environment in which it occurs. What would be consider a major disaster in a
developing country, ill equipped to cope with the problems involved, may not mean
more than a temporary emergency elsewhere. However, all disasters bring in their
wake similar consequences that call for immediate action, whether at the local,
national or international level, for the rescue and relief of the victims. This includes
the search for the dead and injured, medical and social care, removal of the debris,
the provision of temporary shelter for the homeless, food, clothing and medical
supplies, and the rapid re-establishment of essential services.
7.5.2
C7-14
The Disaster Management Plan should reflect the probable consequential severalties
of the undesired event due to deteriorating conditions or through 'Knock on' effects.
Further the management should be able to demonstrate that their assessment of
the consequences uses good supporting evidence and is based on currently
available and reliable information, incident data from internal and external sources
and if necessary the reports of out side agencies.
To tackle the consequences of a major emergency inside the plant or in the
immediate vicinity of the plant, a Disaster Management Plan has to be formulated.
The objective of the Industrial Disaster Management Plan is to make use of the
combined resources of the plant and the outside services to achieve the following:
Emergencies
Fire consequences can be disastrous, since they involve huge quantities of fuel
either stored or in dynamic inventory in pipelines or in nearby areas. Preliminary
hazard analysis has provided a basis for consequence estimation. Estimation can be
VIMTA Labs Limited, Hyderabad
C7-15
made by using various pool fire, tank fire consequence calculations. During the
study of Risk Assessment, the nature of damages is worked out and probability of
occurrence of such hazards is also drawn up.
7.5.4
Emergency Organization
It is recommended to setup an Emergency Organization. A senior executive who has
control over the affairs of the plant should lead the Emergency Organization. He
shall be designated as Site Controller. General Manager [O & M] can be designated
as the Incident Controller. In the case of stores, utilities, open areas, which are not
under the control of the Production Heads, Senior Executive responsible for
maintenance of utilities would be designated as Incident Controller. All the Incident
Controllers would be reporting to the Site Controller. The actions are well defined as
to what action on the spot to be taken with what devotion in option to avert any
emergency situation.
Each Incident Controller, for himself, organizes a team responsible for controlling
the incidence with the personnel under his control. Shift-in-charge would be the
reporting officer, who would bring the incidence to the notice of the Incidence
Controller and Site Controller. All major equipment will have periodic checks in each
shift and the action are to be follow with respect to each observatory during walk
down check specific to each equipment.
Apart from prevention, The Emergency Co-ordinators would be appointed. Each
Incident Controller, for him self, organizes a team responsible for controlling the
incidence with the personnel under his control. Shift-in-charge would be the
reporting officer, who would bring the incidence to the notice of the Incidence
Controller and Site Controller. All major equipment will have periodic checks in each
shift and the action are to be follow with respect to each observatory during walk
down check specific to each equipment.
In each shift, electrical supervisor, electrical fitters, pump house in-charge, and
other maintenance staff would be drafted for emergency operations. In the event of
power or communication system failure, some of staff members in the office/plant
offices would be drafted and their services would be utilized as messengers for quick
passing of communications. All these personnel would be declared as essential
personnel.
All major equipments will have periodic checks in each shift and the to follow up
action during walk down check specific to each equipment.
C7-16
Emergency Responsibilities
The responsibilities of the key personnel are appended below:
Assesses the magnitude of the situation on the advice of Incident Controller and
decides;
Whether the effected area needs to be evacuated;
Whether personnel who are at assembly points need to be evacuated;
Declares Emergency and orders for operation of emergency siren;
Organizes announcement by public address system about location of
emergency;
Assesses which areas are likely to be affected, or need to be evacuated or are to
be alerted;
Maintains a continuous review of possible development and assesses the
situation in consultation with Incident Controller and other Key Personnel as to
whether shutting down the plant or any section of the plant is required and if
evacuation of persons is required;
Directs personnel for rescue, rehabilitation, transport, fire, brigade, medical and
other designated mutual support systems locally available, for meeting
emergencies;
Controls evacuation of affected areas, if the situation is likely to go out of control
or effects are likely to go beyond the premises of the factory, informs the District
Emergency Authority, Police, Hospital and seeks their intervention and help;
Informs Inspector of Factories, Deputy Chief Inspector of Factories, MSPCB and
other statutory authorities;
Gives a public statement, if necessary;
Keeps record of chronological events and prepares an investigation report and
preserves evidence; and
On completion of On Site Emergency and restoration of normalcy, declares all
clear and orders for all clear warning.
Keeping with the Union Government authorities to rend possible help in case
they are from the air force etc., as required.
C7-17
7.5.5.4
Mutual
Aid,
Rehabilitation,
Transport
and
In the event of failure of electric supply and thereby internal telephone, sets up
communication point and establishes contact with the ECC;
Organizes medical treatment to the injured and if necessary will shift the injured
to near by hospitals;
Mobilizes extra medical help from outside, if necessary;
Keeps a list of qualified first aid providers for the plant and seeks their
assistance;
Maintains first aid and medical emergency requirements;
Makes sure that all safety equipment is made available to the emergency team;
C7-18
C7-19
7.5.6
Emergency Facilities
Intercom, telephone;
P and T telephone;
Self contained breathing apparatus;
Fire suit/gas tight goggles/gloves/helmets;
Hand tools, wind direction/velocities indications;
Public address megaphone, hand bell, telephone directories (internal, P and T)
Plant layout, site plan;
Emergency lamp/torch light/batteries;
Plan indicating locations of hazard inventories, plant control room, sources of
safety equipment, work road plan, assembly points, rescue location vulnerable
zones, escape routes;
Hazard chart;
Emergency shut-down procedures;
Nominal roll of employees;
List of key personnel, list of essential employees, list of Emergency
Coordinators;
Duties of key personnel;
Address with telephone numbers and key personnel, emergency coordinator,
essential employees; and
Important address and telephone numbers including Government agencies,
neighboring industries and sources of help, outside experts, fuel fact sheets and
population details around the factory.
Closed circuit TV covering all the prime locations of the plant viewed at 3 to 4
strategic points in addition to unit control rooms will be available.
C7-20
Emergency Actions
Stop feed;
Dilute contents;
Remove heat;
Deluge with water; and
Transfer contents.
C7-21
General
C7-22
Site Controller
Safety Officer
Incident Controller
Emergency Control
Room
Emergency Coordinaror
(Rescue,Fire Fighting)
Emergency Coordinaror
(Medical,Mutual,Aid
Rehabilitation,Transport
and Communication)
Shift Incharge
Shift Incharge
Operator
Emergency Coordinaror
(Essential Services)
Electrician,
Pump Operator
First Aid,
Transport-Driver
Telephone-Operator
Electrician
Pump Operator
FIGURE-7.3
ON-SITE EMERGENCY ORGANIZATION CHART
VIMTA Labs Limited, Hyderabad
C7-23
7.6.1
Introduction
Off-site emergency plan would follow the on-site emergency plan. When the
consequences of an emergency situation go beyond the plant boundaries, it
becomes an off-site emergency. Off-site emergency is essentially the responsibility
of the public administration. However, the plant management will provide the public
administration with the technical information relating to the nature, quantum and
probable consequences on the neighboring population.
The off-site plan in detail will be based on those events, which are most likely to
occur, but other less likely events, which have severe consequence, will also be
considered. Incidents which have very severe consequences yet have a small
probability of occurrence would also be considered during the preparation of the
plan. However, the key feature of a good off-site emergency plan is flexibility in its
application to emergencies other than those specifically included in the formation of
the plan.
The roles of the various parties who will be involved in the implementation of an offsite plan are described below. Depending on local arrangements, the responsibility
for the off-site plan would either rest with the plant management or with the local
authority. Either way, the plan would identify an emergency coordinating officer,
who would take the overall command of the off-site activities. As with the on-site
C7-24
plan, an emergency control center would be setup within which the emergency
coordinating officer can operate.
An early decision will be required in many cases on the advice to be given to
people living "within range" of the accident - in particular whether they should be
evacuated or told to go indoors. In the latter case, the decision can regularly be
reviewed in the event of an escalation of the incident. Consideration of evacuation
may include the following factors:
In the case of a major fire but without explosion risk (e.g. an oil storage tank),
only houses close to the fire are likely to need evacuation, although a severe
smoke hazard may require this to be reviewed periodically; and
Although the plan will have sufficient flexibility built in to cover the consequences of
the range of accidents identified for the on-site plan, it will cover in some detail the
handling of the emergency to a particular distance from each major hazard works.
Power plant fire fighting system do have an extra fire fighting machine which will be
on the order of the shift in charge can proceed to any fire fighting work in a
neighborhood plant or any village or town etc.
7.6.2
Organization
Communications
Specialized Knowledge
Details of specialist bodies, firms and people upon whom it may be necessary to call
e.g. those with specialized fuel knowledge, laboratories.
Voluntary Organizations
C7-25
Fuel Information
Details of the hazardous substances stored and a summary of the risk associated
with them.
Meteorological Information
Humanitarian Arrangements
Public Information
Arrangements for (a) Dealing with the media press office; (b) Informing relatives,
etc
Assessment of Emergency Plan
Arrangements for:
(a) Collecting information on the causes of the emergency; and
(b) Reviewing the efficiency and effectiveness of all aspects of the emergency plan.
7.6.3
7.6.4
C7-26
7.6.5
Role of Police
Formal duties of the police during an emergency include protecting life and property
and controlling traffic movements.
Their functions should include controlling bystanders, evacuating the public,
identifying the dead and dealing with casualties, and informing relatives of death or
injury.
7.6.6
7.6.7
7.6.8
C7-27
TABLE-7.16
OFF-SITE ACTION PLAN
Sr.
No.
Responsible
Agencies for
taking action
Police
Department
Hospital and
public health
Pollution Control
Board
Municipal
corporation
Transport
department
Give
all
information
related
to
meteorological aspects for safe handling
of affected area for living beings
Forecast important weather changes, if
any
Meteorological
Department
Local Crises
Group
A 1
2
3
4
5
B
1
2
3
4
5
E
F1
2
3
G1
H1
Equipments/Material
facilities required at site
to mitigate Emergency
Self Breathing apparatus with
spare cylinder
Chemical gas
spare canister
mask
with
C7-28
I1
7.7
Responsible
Agencies for
taking action
Equipments/Material
facilities required at site
to mitigate Emergency
right
and
timely
media
release can be done
District Crisis
Group
All
necessary
facilities
available at district can be
made available at affected
zone
Control of
situation
law
and
order
7.7.1
Occupational Health
Occupational health needs attention both during construction and erection and
operation and maintenance phases. However, the problem varies both in magnitude
and variety in the above phases.
The occupational health problems envisaged at this stage can mainly be due to
constructional accident and noise. To overcome these hazards, in addition to
arrangements to reduce it within TLV's, necessary protective equipments shall be
supplied to workers.
Remote observations of all people into & going out of gate through CCTV.The
problem of occupational health, in the operation and maintenance phase is primarily
due to noise which could affect hearing. The necessary personal protective
equipments will be given to all the workers. The working personnel shall be given
the following appropriate personnel protective equipments.
C7-29
Full-fledged hospital facilities shall be available round the clock for attending
emergency arising out of accidents, if any. All working personnel shall be medically
examined at least once in every year and at the end of his term of employment.
This is in addition to the pre-employment medical examination.
7.7.2
Safety Plan
Safety of both men and materials during construction and operation phases is of
concern. Safety plan shall be prepared and implemented in the proposed power
plant. The preparedness of an industry for the occurrence of possible disasters is
known as emergency plan. The disaster in the plant is possible due to collapse of
structures and fire/explosion etc.
Keeping in view the safety requirement during construction, operation and
maintenance phases, the power plant would formulate safety policy with the
following regulations:
C7-30
7.7.3
employees in health and safety, first aid and to ensure that adequate publicity is
given to these matters;
To ensure proper implementation of fire prevention methods and an appropriate
fire fighting service together with training facilities for personnel involved in this
service;
To organize collection, analysis and presentation of data on accident, sickness
and incident involving people injury or injury to health with a view to taking
corrective, remedial and preventive action;
To promote through the established machinery, joint consultation in health and
safety matters to ensure effective participation by all employees;
To publish/notify regulations, instructions and notices in the common language
of employees;
To prepare separate safety rules for each type of occupation/processes involved
in a plant; and
To ensure regular safety inspection by a competent person at suitable intervals
of all buildings, equipments, work places and operations.
A book with fill fledged micro- details of all safety equipment system in the plant
will be available at all vital points of the plant. The same is duplicated in control
rooms; shift in charges room and the O & M head as well.
Safety Organization
Safety Circle
In order to fully develop the capabilities of the employees in identification of
hazardous processes and improving safety and health, safety circles would be
constituted in each area of work. The circle would consist of 5-6 employees from
that area. The circle normally shall meet for about an hour every week.
7.7.5
Safety Training
A full-fledged training center shall be set up at the plant. Safety training shall be
C7-31
provided by the Safety Officers with the assistance of faculty members called from
Professional Safety Institutions and Universities. In addition to regular employees,
limited contractor labors shall also be provided safety training. To create safety
awareness safety films shall be shown to workers and leaflets shall be distributed.
Some precautions and remedial measures proposed to be adopted to prevent fires
are:
7.7.6
Spread of fire in horizontal direction would be checked by providing fire stops for
cable shafts;
Reliable and dependable type of fire detection system with proper zoning and
interlocks for alarms are effective protection methods for conveyor galleries;
C7-32
8.0
PROJECT BENEFITS
Proposed power plant will result in considerable growth of stimulating the
industrial and commercial activities in the state. Small and medium scale
industries may be further developed as a consequence.
Proposed power plant would be beneficial in reducing the existing and ever
escalating demand of electricity in eastern part of the country.
In operation phase, the proposed plant would require significant workforce of
non-technical and technical persons. Migration of persons with better education
and professional experience will result in increase of population and literacy in the
surrounding villages.
8.1
8.2
8.3
Generation of employment: The project will create opportunities for direct and
indirect employment;
C8-1
8.4
Recruitment for the unskilled and semiskilled workers for the proposed project
will be from the nearby villages;
Overall the proposed project will change living standards of the people and
improve the socio-economic conditions of the area.
Employment Potential
The impact of the project on the economic aspects can be clearly observed. The
proposed project activities will provide employment to persons of different skills
and trades. The local population will be given preference to employment. The
employment potential will ameliorate economic conditions of these families
directly and provide employment to many other families indirectly who are
involved in business and service oriented activities.
The employment of local people in primary and secondary sectors of project shall
upgrade the prosperity of the region. This in-turn will improve the socio-economic
conditions of the area.
During construction phase of the project, this project will provide temporary
employment to many unskilled and semi-skilled laborers in nearby villages.
This project will also help in generation of indirect employment to those
people who render their services for the personnel directly working in the
project; and
The trend of out migration for employment, if any, is likely to be reduced due to
better economic opportunities available in the area.
About 2000 people will be deployed temporarily during construction of the project
and about 400 people will be employed during operational stage of the project.
C8-2
9.0
ADMINISTRATIVE ASPECTS
9.1
C9-1
GENERAL MANAGER
(SERVICES)
MANAGER
(ENVIRONMENT)
SAFETY OFFICER
ENVIRONMENT
ENGINEER
ECOLOGIST/
HORTICULTURIST
CHEMISTS
SUPPORT STAFF
FIGURE-9.1
ORGANIZATIONAL STRUCTURE OF ENVIRONMENT MANAGEMENT
VIMTA Labs Limited, Hyderabad
C9-2
10.0
DISCLOSURE OF CONSULTANTS
VIMTA LABS LIMITED is a leading multi-disciplinary testing and research
laboratory in India. VIMTA provides contract research and testing services in the
areas of clinical research, pre-clinical (animal) studies, clinical reference lab
services, environmental assessments and analytical testing of a wide variety of
products.
The Quality Policy:
C10-1
Services Offered:
Spread over the 70,000 Sq.ft lush green garden premises at Cherlapally,
Hyderabad (India), the scientifically designed and meticulously groomed
infrastructural facility of the Central laboratory of VIMTA has the most
sophisticated instruments backed by an excellent team of professionals. The
40,000 Sq.ft, three-storied, 120 roomed, centrally air conditioned state-of-the-art
Laboratory equipped with Rs.100 million worth analytical instruments and
computerized data management systems, all under one roof is perhaps the only
one of its kind in South Asia in the contract testing and research sector.
Vimta offers various services under the following divisions:
Environment
Analytical
Clinical Reference Lab
Clinical Research
The environment division of VIMTA Labs Limited (VLL) has its presence all over
India including a strong association with international consultants like Japan Bank
for International cooperation (JBIC), Kennametal Inc. - USA, BBL - UK, Rudal
Blanchard UK, E&E Solutions Japan, NEPESCO & KNPC Kuwait and others.
Vimta Laboratory has the following credentials:
Recognitions by BIS;
Recognitions by Ministry of Environment and Forests, Govt. of India;
Recognitions by State Pollution Control Boards;
Recognitions by Department of Science & Technology, Govt. of India (NABL) ;
Recognitions by Ministry of Defense, Govt. of India;
Recognitions by APEDA, Ministry of Commerce, Govt. of India;
Recognitions by Saudi Arabia Standard Organization (SASO), Saudi Arabia;
Accreditations by NCTCF;
Accreditations by GOSSTANDART;
Certification from Standard Australia;
Recognition from ANVISA Brazil;
Quality Assurance Services as per ISO/IEC 17025; and
Quality Assurance Services as per ICH Guidelines
C10-2
C10-3
Facilities
Quality Systems
The fact that Environment division and its supporting Site Laboratories are
accredited by NABL (IS0-17025) and Ministry of Environment and Forests and by
other international bodies such as Asian Development Bank (ADB) and World
Bank stands testimony to its emphasis on Quality Systems.
Achievements
Being the first laboratory to be recognized under Environment Protection (EP) Act
by GOI in 1986, Environment Division with its best mind power and industrial
knowledge competency that allows it to compare with the best in the business.
The Environment Division till date has executed about 350 Environmental
Impact Assessment (EIA) and Environment Management Studies with Risk
Assessment and Disaster Management Plans and obtained statutory
approvals.
C10-4
SHAR, ISRO and monitoring for offshore Oil & Gas exploration for deep-sea
water and sediment sampling.
The Environment division has also offered its services to major infrastructure
projects such as Ports, Oil & Gas Pipelines, Green field Air Ports, Roads and
Highways.
C10-5
Environmental Impact Assessment for the Proposed 4x300 MW Coal Based Thermal Power Plant at Binjkot, Darramura, Badejampali
and Gindola Villages in Kharsia Tehsil of Raigarh District, Chhattisgarh State
Chapter-10
Disclosure of Consultants
Name
Mr. M.Janardhan
Qualification
M.Tech (Env)
Position
Vice President
(Environment)
Contribution
Co-ordination
Project Manager
Dr.M.V.R.N.Acharyulu
Group Leader
Expert
M.Sc., Ph.D
(Ecology)
M.Tech (Env)
Env. Engineer
Expert
Mr. S. Karunakar
M.Tech (Env)
Env. Engineer
Expert
Mr. KV Suryanarayana
Scientist
Expert
M.Tech (Env)
Env. Engineer
Expert
M.Sc. (Env)
Scientist
Expert
Ms. P. Bhavna
M.Tech (Env)
Env. Engineer
Expert
10
M.Sc., Ph.D
Scientist
Expert
11
B.Com
Asst Manager
Secretarial
12
Mr. P.Krishna
I.T.I (Civil)
Draftsman
Cartography
13
I.T.I (Civil)
Draftsman
Cartography
14
15
Ms. Sireesha
Mr. Ram Kumar Kalyan
B.Sc.
Intermediate
Lab Assistant
Lab Assistant
Secretarial
Secretarial
Experience
About 15 years of experience in the field of air quality
impacts, environmental management and environmental
engineering
About 15 years of experience in the field of Water and
Wastewater Quality & Impacts, Environmental Chemistry
and Monitoring
About 16 years of experience in the field of Terrestrial,
Aquatic and Marine Ecology
About 7 years of experience in the field of Environmental
Impact Assessments, Risk Assessment and Wastewater
Management
About 2 years of experience in the field of Environmental
Impact Assessments, Risk Assessment and Wastewater
Management
About 3 years of experience in the field of Environmental
Chemical Analysis and Baseline Monitoring
About 3 years of experience in the field of Environmental
Impact Assessment studies
About 7 years of experience in the field of Environmental
Chemical Analysis
About 4 years of experience in the field of Environmental
Impact Assessment studies
About 6 years of experience in the field of Environmental
Teaching and Quality Control
About 18 years of experience in the field of Environmental
Monitoring and secretarial assistance
About 8 years experience in the field of Environmental
and Civil Drawings
About 7 years experience in the field of Environmental
and Civil Drawings
About 2 years of experience in Secretarial Assistance
About 4 years of experience in Secretarial Assistance
C10-6
ANNEXURE-I
TERMS OF REFERENCE
No. J-13012/164/2007-IA.II(T)
Government of India
Ministry of Environment & Forests
AI-1
ANNEXURE-I
TERMS OF REFERENCE
Paryavaran Bhavan,
C.G.O. Complex, Lodi Road,
New Delhi-110003.
Telefax.: 2436 2434
Dated the 9th July, 2008
To
M/s SKS Ispat and Power Ltd.
501 B, Elegant Business Park,
Andheri Kurla Road,
J.B. Nagar, Andheri (E),
Mumbai ? 400 059.
Sub:
The
undersigned
is
directed
to
refer
to
your
communication
no.SKSIPL/IPP/TOR/RGH/005 dated 6.5.2008 regarding the subject mentioned above.
2.
The proposal is for setting up of a 1200 MW (4x300 MW) coal based thermal power
project at village Binjkote, Darramura, badejampally, Gindola villages in Kharsia Tehsil,
District Raigarh, Chhattisgarh. The land requirement is 1200 acres. The coordinates of the
project area are 220 00? 06?N, 830 12? 10? E; 220 00? 26?N, 830 12 51? E ; 220 01? 32?N,
830 11? 23? E; 220 01? 52?N, 830 12? 03?E. The coal requirement is 6.02 Million TPA (90%
PLF), which will be obtained from SECL mine and transported through road/rail. Water
requirement is estimated as 4500 m3/hr and will be met from river Mahanadi. Closed circuit
cooling will be provided. Two bi-flue stack of height 275 m will be provided.
3.
(i)
Comparison of alternate sites considered and the reasons for selecting the
proposed site. Conformity of the site with the prescribed guidelines in
terms of distance HFL of the river, highways may also be shown.
AI-2
ANNEXURE-I
TERMS OF REFERENCE
(ii)
All the coordinates of the plant site as well as ash pond demarcated on the
toposheet (1:50000 Scale).
(iii)
Explore the possibility of having 2x600 MW/ 2x660 MW and examine the
adoption of super critical technology.
(iv)
The study area should cover an area of 10 km radius around the proposed
site.
(v)
Land use of the study area as well as the project area shall be given.
(vi)
(vii)
(viii)
Topography of the area should be given clearly indicating whether the site
requires any filling. If so, details of filling, quantity of fill material
required, its source, transportation etc. should be given.
(ix)
(x)
(xi)
(xii)
One complete season AAQ data (except monsoon) to be given along with
the dates of monitoring. The parameters to be covered shall include SPM,
RSPM, SO2 NOx and Ozone (ground level). The location of the
monitoring stations should be so decided so as to take into consideration
the pre-dominant downwind direction, population zone and sensitive
receptors including reserved forests. There should be at least one
monitoring station in the upwind direction.
(xiii) Impact of the project on the AAQ of the area. Details of the model used
and the input data used for modelling should also be provided. The air
quality contours may be plotted on a location map showing the location of
project site, habitation nearby, sensitive receptors, if any. The wind roses
AI-3
ANNEXURE-I
TERMS OF REFERENCE
should also be shown on this map. It may be kept in view that SPM
emissions are to be restricted to 50 mg/Nm3.
(xiv)
(xv)
(xvi)
(xvii) Details of rainwater harvesting and how it will be used in the plant.
(xviii) Examine the feasibility of zero discharge. In case of any proposed
discharge, its quantity, quality and point of discharge, users downstream
etc. should be provided.
(xix)
(xx)
(xxi)
Details of greenbelt i.e. land with not less than 1500 trees per ha giving
details of species, width of plantation, planning schedule etc. About 1/3rd
of the area should be covered under greenbelt.
(xxii)
ANNEXURE-I
TERMS OF REFERENCE
4.
Besides the above, the following general points will be followed:a) All documents to be properly referenced with index, page numbers and
continuous page numbering.
b) Where data is presented in the report especially in table, the period in which
the data was collected and the source should invariably be indicated.
c) Where the documents provided are in a language other than English, an
English translation should be provided.
d) The Questionnaire for environmental appraisal of thermal power projects as
devised earlier by the Ministry shall also be filled and submitted.
AI-5
ANNEXURE-I
TERMS OF REFERENCE
In addition to the above, information on the following may also be incorporated in the
EIA report.
1.
2. Notwithstanding 1(i) above, data on (d) & (e) above to be worked out and reported.
3. After preparing the draft EIA (as per the generic structure prescribed in Appendix-III
of the EIA Notification, 2006) covering the above mentioned issues, the proponent will
get the public hearing conducted and take further necessary action for obtaining
environmental clearance in accordance with the procedure prescribed under the EIA
Notification, 2006.
(Om Prakash)
Deputy Director
Copy to:1.
2.
3.
4.
(Om Prakash)
Deputy Director
Compliance
AI-6
ANNEXURE-I
TERMS OF REFERENCE
Sr.
Terms Of Reference given by MoEF
No
1. Comparison of alternate sites considered
and the reasons for selecting the
proposed site. Conformity of the site
with the prescribed guidelines in terms of
distance HFL of the river, highways may
also be shown.
Compliance
Four (4) probable locations
assessed for site selection:
were
Refer Chapter-1,Table-1.1,
Page no: C1-5
PLANT
A : 220140N to 831209E
B : 220045N to 831139E
C : 215958N to 831204E
D : 220056N to 831315E
ASH POND
1 : 220123N to 831236E
2 : 220117N to 831223E
3 : 220026N to 831258E
4 : 220032N to 831310E
The Latitudes/ Longitudes of the
extreme boundaries of plant site and
ash pond are given above.
The map showing the plant site, ash
pond and colony is given as figure-1.2
of Chapter -1, page- C1-4
AI-7
ANNEXURE-I
TERMS OF REFERENCE
Sr.
Terms Of Reference given by MoEF
No
3. Explore the possibility of having 2X600
MW and 2X660 MW and examine the
adoption of super critical technology
Compliance
After
exploration
of
various
technologies SKSPGCL finalized the
3X400 MW capacity sub critical boilers
based on the techno commercial
evaluation.
10 km radius study area considered for
the EIA study.
Land use studies has been carried out
in the study area, and are presented in
Annexure-VIII
No
National
Parks,
Sanctuaries,
Elephant / Tiger Reserve (existing as
well as proposed), migratory routes,
ecologically sensitive areas presented in
within 10 km of the project site.
The land requirement details are
presented in Chaper-2, Section-2.4.1
Break-up of land use is presented in
Table-2.2, page-C2-5
The proposed project premise is a
generally plain land with a general
elevation of about 230-m above MSL.
Most of the buffer zone of the project is
flat land.
It is proposed to level the project area
and to use the earthen material
excavated from the proposed reservoir
sites inside the premises. There will be
no tall structures except stacks. Also,
the contours of natural drainage will not
be disturbed.
AI-8
ANNEXURE-I
TERMS OF REFERENCE
Sr.
Terms Of Reference given by MoEF
No
10.Information regarding surface hydrology
and water regime and impact of the
same, if any due to the project.
Compliance
Mand River, is passing through 2.3-km
away from the proposed plant site.
Ground water is not using for the
project. No impact was envisaged.
AI-9
ANNEXURE-I
TERMS OF REFERENCE
Sr.
Terms Of Reference given by MoEF
No
15.Quantity of fuel required, its source and
transportation. A confirmed fuel linkage
should be provided.
Compliance
The quantity of coal required is 6.02
MTPA.
Coal for the plant would be linked to
SECL coal mines
Secondary fuels, LDO and HFO will be
brought to plant site by road/rail.
19.Optimization
of
COC
for
water
conservation. Other water conservation
measures proposed in the project should
also be given.
20.Details of water balance taking into
account reuse and re-circulation of
effluents.
AI-10
ANNEXURE-I
TERMS OF REFERENCE
Sr.
Terms Of Reference given by MoEF
No
23.Details of evacuation of ash.
24.Details
regarding
ash
pond
impermeability and whether it would be
lined, if so details of the lining etc.
25.Detailed
R&R
plan/compensation
package for the project affected people
shall be prepared taking into account the
socio economic status of the area,
homestead
oustees,
land
oustees,
landless laboureres.
26.Details of flora and fauna with list of
schedule of the wild life (Protection Act
1972) duly authenticated should be
provided.
In case of any scheduled
fauna, conservation plan should be
provided.
27.Details regarding infrastructure facilities
such as sanitation, fuel, restroom etc. to
be provided to the labour force during
construction as well as to the casual
workers including truck drivers during
operation phase.
Compliance
The total ash generated in the plant will
be 2.47 MTPA out of which 20% will be
bottom ash i.e. 0.49 MTPA and balance
will be fly ash of 1.98 MTPA
Details are presented chapter-4 under
section-4.5.5.5, page-C4-26
Details given in Annexure-IX
For
construction
force
temporary
sanitation facilities (septic tanks and
soak pits) will be set-up for disposal of
sanitary sewage generated by the work
force. Similarly, rest rooms and canteen
facilities will be provided for truck
drivers.
The construction water requirement will
be around 7 MLD. This water will be
supplied through storage reservoir and
distribution network. Water is available
at site or from near by area.
Public hearing yet to be conducted.
Details will be incorporated in final EIAReport.
AI-11
ANNEXURE-I
TERMS OF REFERENCE
Sr.
Terms Of Reference given by MoEF
No
32.EMP to mitigate the adverse impacts due
to the project along with item wise cost
of its implementation.
33.Risk assessment should be carried out. It
should take into account the maximum
inventory of storage at site at any point
in time. The risk contours should be
plotted on the plant layout map clearly
showing which of the proposed activities
would be affected in case of accident
taking
place.
Based
on
the
same,proposed
safeguard
measures
should be provided. Measures to guard
against fire hazards should also be
provided.
34.Details of industries existing and/or
proposed within 10 km radius of the
project
boundary
should
also
be
provided.
35.Any litigation pending against the project
and /or any direction /order passed by
any Court of Law against the project, if
so, details thereof.
Compliance
The Environmental Management plan is
detailed in chapter-4 under section-4.4,
page-C4-19 to 20
Risk
assessment
and
Disaster
management plan is detailed in
Chapter-7, section-7.0, page- C7-17
No
AI-12
ANNEXURE-II
ADMINISTRATIVE AND LEGISLATIVE BACKGROUND
The legal framework is covered under several legislations. Brief details of the
same are given below:
Legislative Framework
This section provides a brief summary of India's environmental legislation.
Ministry of Environment and Forests (MoEF) is the nodal agency for drafting the
new environmental legislations and giving the environmental clearance to the
new projects. State Pollution Control Boards (SPCB) are responsible for
implementing environmental legislation and issuing local Rules, Regulations and
Notifications.
Regulatory Control of the Project
The proposed project is covered under the Environmental Impact Assessment
(EIA) Notification, 1994 and amendments promulgated under Environment
(Protection) Act (EPA), 1986.
The key environmental legislations pertaining to the proposed operations include:
These key instruments and all subsequent and relevant amendments to them are
discussed in further details as below.
Specified activities in forest areas are controlled under the Forest (Conservation)
Act 1980 and clearances are required for such activities. The diversion of
forestland for non-forestry purposes is not encouraged and clearances for such
activities are difficult to obtain. Seismic surveys, are however, exempted from the
provisions of the Forest Act providing these activities are restricted to clearing of
undergrowth and lopping of tree branches and do not involve the felling of trees.
This Act introduced the State Pollution Control Boards to grant Consent For
Establishment (CFE) and Consent For Operation (CFO) to the industries. The
investor intending to set up an industry is required to apply to the SPCB to obtain
a CFE followed by CFO. While granting the consent, SPCB can stipulate conditions
pertaining to the effluents arising from the process. The consent to operate is
granted for a specific period (usually one year) after which conditions attached
are reviewed by the SPCB before renewal.
AII-1
ANNEXURE-II
ADMINISTRATIVE AND LEGISLATIVE BACKGROUND
This Act is very similar in scope to the Water Act, 1974. The Act stipulates the
establishment of State Boards for the Prevention and Control of Air Pollution. In
States where a water pollution board had already been established under the
earlier Water Act, the two boards were combined to form SPCBs. The
establishment or operation of any industry cannot be undertaken without the
prior consent of the SPCB. A decision on any application for consent must be
made by the SPCB within four months of receipt of the application.
o
o
ANNEXURE-II
ADMINISTRATIVE AND LEGISLATIVE BACKGROUND
These rules make the occupier and the occupier of a facility responsible for proper
collection, reception, treatment, storage and disposal of hazardous wastes listed
in schedule-1, 2, and 3.
This rule also recommends to obtain and renew the authorization to collection,
reception, treatment, storage and disposal of hazardous wastes from state
pollution control board (SPCB) by filing Form-1.
ANNEXURE-II
ADMINISTRATIVE AND LEGISLATIVE BACKGROUND
EMP and such other information as may be required by the Central Government.
There are few ecologically sensitive areas where mining has been prohibited
either by the court's order or by a MoEF Notification.
Under the Constitution of India, safety, welfare and health of workers employed
in mines are the concern of the Central Government (Entry 55 - Union List; Article
246). The objective is regulated by the Mines Act, 1952 and the rules and
regulations framed thereunder. These are administered by the Directorate
general of Mines Safety (DGMS), under the union Ministry of Labour. Apart from
administering the Mines Act and subordinate legislation thereunder, DGMS also
administers a few other allied legislation, including the Indian Electricity Act
The pieces of legislation administered by DGMS are,
o
o
o
o
o
o
o
Time Weighted
Average
Annual Average*
24 Hours**
Annual Average*
24 Hours**
Annual Average*
24 Hours**
Annual Average*
24 Hours**
Annual Average*
24 Hours**
8 Hours
0.75
1.0
2000
0.50
0.75
1000
AII-4
ANNEXURE-II
ADMINISTRATIVE AND LEGISLATIVE BACKGROUND
Pollutant
Ammonia
Time Weighted
Average
1 Hour**
Annual Average*
24 Hours**
Note:
*
Annual arithmetic mean of minimum 104 measurements in a year taken
twice a week 24 hourly at uniform interval.
**
24 hourly/8 hourly values should be met 98% of the time in a year.
However 2% of the time, it may exceed but not on two consecutive days.
Noise Limits and Guidelines for Diesel Generators
AII-5
ANNEXURE-II
ADMINISTRATIVE AND LEGISLATIVE BACKGROUND
TABLE-2
AMBIENT NOISE STANDARDS
Area Code
Category of Area
A
B
C
D
Industrial Area
Commercial Area
Residential Area
Silence Zone**
Note:
*
**
10
15
10
20
25
10
10
15
25
15
25
50
AII-6
ANNEXURE-II
ADMINISTRATIVE AND LEGISLATIVE BACKGROUND
Total Time of Exposure per Day in Hours
Sound Pressure Level in dB(A)
(Continuous or Short term Exposure)
2
100
3/2
102
1
105
107
110
115
Never
>115
Note:
No exposure in excess of 115 dB(A) is to be permitted.
For any period of exposure falling in between any figure and the next higher or lower figure as
indicated in column (1), the permissible level is to be determined by extrapolation on a
proportionate scale.
1.
2.
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
List of Parameters
Suspended Solids
Particle size of Suspended
Solids
pH value
Temperature
mg/l
--
mg/l
mg/l
10.0
Not Specified
Standard
(Surface Waters)
All efforts should be made to
remove colour and
unpleasant odour as far as
practicable.
100.0
Shall pass 850 micron IS
Sieve
5.5 to 9.0
Shall not exceed 5 oC above
the receiving water
temperature.
10.0
1.0
mg/l
Not Specified
50
mg/l
Not Specified
100
mg/l
Not Specified
mg/l
100.0
30.0
mg/l
Not Specified
250
mg/l
mg/l
mg/l
mg/l
mg/l
0.2
Not
Not
Not
Not
0.2
0.01
0.1
2.0
0.1
mg/l
Not Specified
mg/l
mg/l
mg/l
mg/l
Not
Not
Not
Not
Units
--
---
Standard
(On land Irrigation)
All efforts should be
made to remove colour
and unpleasant odour
as far as practicable.
200.0
Shall pass 850 micron
IS Sieve
5.5 to 9.0
Not Specified
Specified
Specified
Specified
Specified
Specified
Specified
Specified
Specified
2.0
3.0
5.0
0.05
3.0
AII-7
ANNEXURE-II
ADMINISTRATIVE AND LEGISLATIVE BACKGROUND
Sr.
No.
23
24
25
List of Parameters
Units
mg/l
mg/l
mg/l
mg/l
mg/l
Not Specified
Not Specified
28
A]
B]
29
Standard
(On land Irrigation)
0.2
Not Specified
Not Specified
30
31
32
33
26
27
C/ml
C/ml
--
mg/l
mg/l
mg/l
mg/l
10-7
10-7
90% survival of fish
after 96 hours in 100%
effluent.
Not Specified
Not Specified
Not Specified
Not Specified
Standard
(Surface Waters)
0.2
2.0
5.0
2.0
1.0
10-7
10-6
90% survival of fish after 96
hours in 100% effluent.
2.0
3.0
0.2
10.0
AII-8
ANNEXURE-III
COPY OF WATER ALLOCATION AND AVAILABILTY LETTER
AIII-1
ANNEXURE-III
COPY OF WATER ALLOCATION AND AVAILABILTY LETTER
AIII-2
ANNEXURE-III
COPY OF WATER ALLOCATION AND AVAILABILTY LETTER
AIII-3
ANNEXURE-IV
EMISSION CALCULATIONS
1.0
General Calculations
Area Calculations
Area(m2 ) =
3.142
Temperature Correction
273 + 25 0 C
Temperature Correction =
= 298/413=0.7215
273 + StackTemperature 0 C
Volumetric flow (
Nm 3
) = Area (m 2 ) x Exit Velocity (m / s ) x Temperature Correction
s
= 38.49 X 25 X 0.7215 = 694.3Nm/s
1.1
=
=
=
=
=
0.4%
(0.4/100) x (64/32) = 0.008
=
=
=
=
AIV-1
ANNEXURE-IV
EMISSION CALCULATIONS
2) NOx emission is calculated based on of 9 kg/tonne of coal burnt basis
= 760.1tone/hr X 9 kg/tonne
= 6840.9 kg/hr
= 1900.3 g/sec
= 475 g/sec /flue
AIV-2
ANNEXURE-IV
EMISSION CALCULATIONS
Time
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
Wind
Direction
47
45
225
45
48
315
46
315
215
50
47
225
315
45
45
55
45
50
225
225
228
315
325.5
319
Wind
Speed
1.5
1.6
1.7
1.6
1.4
0.7
1.8
1.9
1.2
1.1
0.9
1.8
2.6
2.4
1.5
1.9
1.2
1.5
1.4
0.3
1.2
0.4
0.2
1.1
Temp
304.3
303.9
303.4
303
303
303.3
304.3
305.8
307.3
308.5
309.6
310.8
312
313.4
312.9
311.9
310.6
309.3
307.8
306.8
306
305.3
304.7
304.5
Stability
Class
6
6
6
6
6
6
5
5
4
3
1
1
1
1
1
1
3
4
5
5
5
6
6
6
Mixing
Height
200
200
300
300
400
400
700
800
800
950
1100
1200
1800
1500
1500
1300
950
900
800
800
500
400
200
200
AIV-3
ANNEXURE-V
AMBIENT AIR QUALITY LEVELS
Sr. No.
Date
AAQ1
TSPM
Plant Site
RPM
SO2
NOX
Ozone (O3)
CO
03.03.2008
59.5
16.4
5.0
6.1
260
210
289
1.8
04.03.2008
75.6
25.2
8.9
10.2
299
304
266
1.5
10.03.2008
80.3
26.8
8.2
11.0
306
310
301
2.3
11.03.2008
72.1
27.4
9.5
10.3
290
319
261
2.9
17.03.2008
87.4
24.8
8.4
10.6
283
299
253
2.4
18.03.2008
91.2
25.6
8.9
12.3
310
293
302
2.7
24.03.2008
81.2
23.4
8.8
9.3
299
311
274
3.1
25.03.2008
64.0
19.8
9.1
10.2
294
299
279
31.03.2008
74.3
24.8
9.2
12.4
310
290
272
2.9
10
01.04.2008
55.3
26.3
5.2
12.3
291
279
299
2.4
11
07.04.2008
64.7
19.1
9.4
11.3
281
269
317
1.8
12
08.04.2008
79.8
23.8
9.0
10.9
299
302
311
1.7
13
14.04.2008
82.1
26
8.9
12.2
317
291
302
1.2
14
15.04.2008
68.0
20
9.0
9.8
287
308
282
1.6
15
21.04.2008
59.7
26.2
7.3
11.6
278
284
308
1.9
16
22.04.2008
76.4
25.4
7.4
9.8
273
292
297
2.2
17
28.04.2008
80.3
24
8.4
10.8
289
280
294
2.7
18
29.04.2008
63.0
19.2
9.2
12.2
311
311
2.9
19
05.05.2008
82.0
23.4
8.2
9.7
266
307
289
1.8
20
06.05.2008
85.4
26.4
8.8
12.6
262
277
280
1.5
21
12.05.2008
76.2
21.1
9.4
9.6
292
302
272
1.7
22
13.05.2008
82.6
24.7
9.5
10.7
313
283
298
2.3
23
19.05.2008
77.7
22.4
8.3
11.4
281
309
252
2.6
24
20.05.2008
84.4
24.6
9.1
12.0
288
303
264
2.8
25
26.05.2008
71.2
21.3
8.8
11.7
303
286
273
3.1
26
27.05.2008
83.4
55.3
21.3
16.4
8.5
5.0
11.6
6.1
308
300
210
291
2.6
1.2
Min
Max
91.2
27.4
9.5
12.6
319
3.1
Avg
75.3
89.3
23.4
27.1
8.5
9.5
10.9
12.5
290.1
317.0
2.3
3.1
98th
All units are in g/m3
AV-1
ANNEXURE-V
AMBIENT AIR QUALITY LEVELS
Sr. No.
Date
NOX
Ozone (O3)
CO
03.03.2008
53.4
14.5
6.3
7.9
179
183
173
1.6
04.03.2008
58.3
15.3
7.0
8.4
184
187
177
2.2
10.03.2008
57.6
16.5
8.0
9.3
181
184
175
2.6
11.03.2008
59.4
14.2
7.4
8.8
187
191
181
2.9
17.03.2008
54.3
15.0
6.7
8.0
185
188
179
2.6
18.03.2008
66.8
16.8
6.8
9.0
178
182
172
1.9
24.03.2008
73.4
19.7
8.2
9.9
176
179
171
1.8
25.03.2008
72.1
18.8
7.4
8.6
185
187
181
2.4
31.03.2008
64.0
17.0
6.1
7.9
179
184
174
2.7
10
01.04.2008
74.7
19.2
7.2
9.0
177
181
175
2.3
11
07.04.2008
68.1
17.3
7.9
9.7
183
188
181
1.8
12
08.04.2008
76.5
27.8
7.5
8.9
185
191
182
1.9
13
14.04.2008
65.4
15.7
5.8
7.7
182
189
178
2.1
14
15.04.2008
68.4
17.5
6.6
8.4
179
184
176
2.5
15
21.04.2008
74.3
19.1
6.9
9.4
181
187
179
2.2
16
22.04.2008
66.7
17.8
6.0
7.3
185
189
181
2.3
17
28.04.2008
75.6
20.3
7.6
8.4
233
255
250
1.6
18
29.04.2008
44.4
14.5
5.8
6.4
184
189
181
1.8
19
05.05.2008
60.1
15.0
6.4
8.6
195
205
189
1.9
20
06.05.2008
75.7
18.3
7.0
9.4
202
216
223
2.4
21
12.05.2008
65.4
18.3
7.7
9.0
183
185
176
2.7
22
13.05.2008
73.4
18.7
8.2
9.2
185
191
180
2.1
23
19.05.2008
63.4
17.4
7.8
9.0
179
183
175
2.3
24
20.05.2008
72.1
18.2
7.1
8.5
185
187
178
2.6
25
26.05.2008
74.0
16.8
7.6
8.9
184
190
180
2.7
26
27.05.2008
68.1
44.4
19.3
14.2
8.1
5.8
9.4
6.4
179
186
171
174
2.6
1.6
Min
Max
76.5
27.8
8.2
9.9
255
2.9
Avg
66.4
76.1
17.7
24.1
7.1
8.2
8.7
9.8
186.1
240.8
2.3
2.8
98th
All units are in g/m3
AV-2
ANNEXURE-V
AMBIENT AIR QUALITY LEVELS
Sr. No.
Date
AAQ3
TSPM
Gindola Village
RPM
SO2
NOX
Ozone (O3)
CO
03.03.2008
75.9
23.5
7.8
10.8
286
04.03.2008
89.2
25.9
8.2
11.3
292
288
285
3.0
10.03.2008
98.6
30.4
9.7
12.5
288
284
280
2.4
11.03.2008
110.2
36.4
10.1
13.8
282
276
268
1.6
17.03.2008
82.7
23.1
7.9
9.7
273
267
263
3.1
18.03.2008
104.3
30.2
10.2
13.2
280
273
269
2.9
24.03.2008
74.3
20.9
8.9
10.6
284
280
275
2.4
25.03.2008
116.5
32.8
10.1
14.5
288
284
278
2.2
31.03.2008
59.8
18.3
5.9
7.2
293
291
286
2.4
10
01.04.2008
112.4
35.4
9.9
13.8
298
295
288
3.0
11
07.04.2008
98.2
28.9
8.9
10.2
294
284
274
2.2
12
08.04.2008
110.5
31.5
10.8
12.4
298
292
289
2.1
13
14.04.2008
86.9
26.4
11.1
13.8
299
296
287
2.5
14
15.04.2008
98.5
28.4
9.6
10.7
295
289
284
2.3
15
21.04.2008
109.7
32.4
10.6
11.9
290
284
276
2.1
16
22.04.2008
115.4
35.6
8.9
14.9
280
275
270
1.7
17
28.04.2008
98.5
28.9
9.7
12.2
282
278
273
2.9
18
29.04.2008
86.4
26.7
8.3
11.1
282
274
266
2.6
19
05.05.2008
93.4
30.8
10.8
13.3
273
267
264
2.3
20
06.05.2008
78.6
23.5
7.6
9.8
282
275
273
2.1
21
12.05.2008
89.8
27.6
8.8
10.7
288
285
282
2.9
22
13.05.2008
107.8
32.2
11.6
12.6
302
294
290
2.1
23
19.05.2008
116.4
33.3
10.1
13.1
286
277
270
2.2
24
20.05.2008
99.7
29.8
10.1
12.8
296
290
285
2.4
25
26.05.2008
87.9
25.5
9.1
11.9
290
284
278
2.7
26
27.05.2008
34.6
18.3
9.8
5.9
13.7
7.2
297
292
286
Min
106.5
59.8
263
2.8
1.6
Max
116.5
36.4
11.6
14.9
302
3.1
Avg
96.5
116.5
29.0
36.0
9.4
11.4
12.0
14.7
282.9
298.5
2.4
3.1
98th
282
273
2.1
AV-3
ANNEXURE-V
AMBIENT AIR QUALITY LEVELS
Sr. No.
Date
SO2
NOX
9.6
10.6
303
296
312
Ozone (O3)
1.5
9.8
11.8
340
288
353
1.7
CO
03.03.2008
106.2
38.6
04.03.2008
95.2
35.6
10.03.2008
110.1
40.2
10.2
12.6
331
315
330
2.0
11.03.2008
88.6
42.3
10.4
13.2
319
326
321
2.5
17.03.2008
100.4
38.9
9.8
11.7
299
307
309
2.8
18.03.2008
96.5
38.2
10.2
12.8
325
309
299
3.3
110.6
129.8
39.2
9.8
13.6
335
355
295
1.6
41.2
10.2
12.6
319
349
290
3.1
24.03.2008
25.03.2008
31.03.2008
9.8
12.4
342
335
335
2.4
01.04.2008
115.9
98.4
36.6
10
36.2
9.7
11.5
326
349
331
2.7
11
07.04.2008
85.2
37.2
9.8
10.8
349
362
321
1.8
12
08.04.2008
95.6
37.7
9.6
11.6
323
341
329
2.2
13
14.04.2008
120.3
38.1
10.2
13.8
299
319
327
1.8
14
15.04.2008
75.6
37.9
12.2
14.2
342
331
318
1.6
15
21.04.2008
12.9
335
329
298
2.6
22.04.2008
38.4
39.2
10.9
16
128.5
116.2
9.8
11.3
307
300
347
2.9
17
28.04.2008
122.1
37.8
11.1
14.3
335
352
375
3.1
18
29.04.2008
86.5
38.6
8.6
9.9
317
339
293
2.0
19
05.05.2008
12.8
326
317
323
2.1
06.05.2008
37.8
37.8
10.0
20
120.2
95.4
11.6
13.9
314
326
334
2.5
21
12.05.2008
127.0
39.1
10.1
12.4
301
303
320
2.8
22
13.05.2008
105.2
37.6
12.2
13.2
327
307
315
2.3
23
19.05.2008
117.5
38.8
9.8
12.8
339
352
325
1.8
24
20.05.2008
125.2
36.2
11.5
13.8
307
335
331
2.0
25
26.05.2008
97.1
38.6
10.1
12.2
342
341
314
2.6
26
27.05.2008
89.6
39.8
333
292
75.6
35.6
10.8
9.9
330
Min
8.9
8.6
288
2.3
1.5
Max
129.8
42.3
12.2
14.3
375
3.3
Avg
106.1
129.2
38.4
41.8
10.2
12.2
12.4
14.3
324.2
358.2
2.3
3.2
98th
All units are in g/m3
AV-4
ANNEXURE-V
AMBIENT AIR QUALITY LEVELS
Sr. No.
Date
AAQ5
TSPM
Kurabhata village
RPM
SO2
NOX
Ozone (O3)
CO
03.03.2008
110.6
28.6
8.7
10.6
343
346
372
2.0
04.03.2008
81.4
21.3
6.5
8.7
324
314
338
2.3
10.03.2008
129.2
32.8
12.5
14.6
357
320
342
2.8
11.03.2008
120.4
30.8
7.7
10.4
318
321
351
2.6
17.03.2008
102.5
26.6
6.9
8.7
338
314
340
1.9
18.03.2008
113.8
29.2
7.3
9.9
334
348
337
2.8
24.03.2008
103.4
27.2
8.1
10.7
324
314
338
3.2
25.03.2008
128.2
31.7
10.4
12.3
357
320
342
1.7
31.03.2008
114.5
29.5
8.1
10.5
318
321
351
2.2
10
01.04.2008
107.2
27.1
7.7
9.4
338
314
340
2.4
11
07.04.2008
126.9
32.4
9.8
11.5
338
314
340
2.9
12
08.04.2008
96.9
25.2
6.8
10.2
378
386
346
3.1
13
14.04.2008
122.2
31.5
11.7
13.4
386
376
370
3.3
14
15.04.2008
125.2
32.2
10.6
11.2
360
366
374
2.1
15
21.04.2008
95.5
24.6
8.2
12.7
354
342
385
2.6
16
22.04.2008
106.1
26.7
7.5
10.8
373
369
395
2.4
17
28.04.2008
139.6
48.6
13.4
15.6
389
372
370
2.2
18
29.04.2008
117.8
29.4
7.8
10.9
353
394
392
3.3
19
05.05.2008
100.1
25.2
7.2
12.6
343
346
372
3.1
20
06.05.2008
110.3
28.2
7.3
11.0
337
321
359
3.4
21
12.05.2008
107.8
24.2
8.3
11.7
346
322
317
2.6
22
13.05.2008
101.4
26.6
6.7
8.8
335
316
339
3.1
23
19.05.2008
104.2
26.5
7.5
9.7
378
386
346
3.3
24
20.05.2008
113.1
29.3
8.2
10.8
360
366
374
1.9
25
26.05.2008
110.3
28.4
7.5
10.2
354
342
375
2.6
26
27.05.2008
31.1
21.3
7.8
6.5
11.3
8.7
373
369
314
389
Min
121.1
81.4
2.1
1.7
Max
139.6
48.6
13.4
15.6
395
3.4
Avg
111.9
134.4
29.0
40.7
8.5
13.0
11.1
15.1
350.3
392.9
2.6
3.4
98th
All units are in g/m3
AV-5
ANNEXURE-V
AMBIENT AIR QUALITY LEVELS
Sr. No.
Date
NOX
Ozone (O3)
CO
03.03.2008
60.2
18.5
5.3
7.2
296
04.03.2008
99.8
28.4
6.9
8.1
302
10.03.2008
112.5
32.6
7.5
10.6
308
315
296
2.3
11.03.2008
98.6
29.6
6.7
7.9
295
300
289
1.9
17.03.2008
110.2
32.4
7.1
8.3
302
307
295
3.0
18.03.2008
98.5
29.7
6.6
8.0
305
311
300
1.3
24.03.2008
87.5
27.1
5.8
6.9
308
318
302
2.0
25.03.2008
74.3
22.4
6.1
7.3
301
315
298
3.1
31.03.2008
89.7
26.7
6.5
8.2
296
305
292
2.7
10
01.04.2008
69.7
22.1
5.5
7.7
300
312
295
1.7
11
07.04.2008
123.7
35.4
7.6
8.7
305
313
297
3.4
12
08.04.2008
112.4
32.2
8.0
10.8
299
306
293
1.9
13
14.04.2008
126.3
36.5
10.9
12.5
303
316
290
2.8
14
15.04.2008
117.3
33.6
10.1
11.9
304
312
297
3.4
15
21.04.2008
87.6
24.7
8.8
10.4
310
322
305
2.5
16
22.04.2008
92.5
28.8
9.2
10.8
305
340
296
2.9
17
28.04.2008
78.8
26.1
7.2
9.5
290
315
281
3.4
18
29.04.2008
97.5
30.7
8.6
10.4
295
280
275
3.3
19
05.05.2008
100.5
32.4
8.9
11.1
300
336
292
2.6
20
06.05.2008
108.8
32.5
9.2
12.2
315
328
302
2.7
21
12.05.2008
95.5
28.7
8.1
11.3
299
310
293
1.7
22
13.05.2008
88.7
38.8
8.7
12.4
321
332
314
2.4
23
19.05.2008
118.6
35.4
9.2
13.8
300
306
292
1.8
24
20.05.2008
99.2
32.7
7.9
9.8
311
319
305
2.2
25
26.05.2008
86.5
25.4
8.5
10.5
324
331
310
2.3
26
27.05.2008
23.3
18.5
7.4
5.3
8.7
6.9
316
345
298
Min
75.6
60.2
275
2.9
1.3
Max
126.3
38.8
10.9
13.8
345
3.4
Avg
96.6
125.0
29.5
37.7
7.8
10.5
9.8
13.2
305.3
337.8
2.4
3.4
98th
303
290
1.7
311
301
1.6
AV-6
ANNEXURE-V
AMBIENT AIR QUALITY LEVELS
Sr. No.
Date
NOX
Ozone (O3)
CO
03.03.2008
75.6
20.6
6.6
9.5
305
314
321
04.03.2008
51.3
15.4
5.4
10.0
275
285
292
1.7
10.03.2008
79.8
24.3
6.9
9.7
304
310
316
2.8
11.03.2008
86.5
27.4
8.8
10.3
268
281
300
2.6
17.03.2008
86.0
24.1
8.4
11.2
274
287
294
2.2
18.03.2008
85.8
26.4
8.0
9.3
271
285
303
2.6
24.03.2008
66.5
19.4
5.6
9.8
273
292
309
2.9
25.03.2008
90.1
28.4
9.0
10.9
266
281
294
3.2
31.03.2008
76.1
20.5
6.1
8.9
262
272
278
2.5
10
01.04.2008
81.2
22.6
6.3
7.9
305
312
319
2.6
11
07.04.2008
89.2
25.4
7.8
10.9
262
276
293
2.3
12
08.04.2008
92.4
29.5
8.4
9.6
282
288
296
3.1
13
14.04.2008
90.1
27.6
9.3
10.8
298
307
316
2.7
14
15.04.2008
87.8
25.4
7.6
10.6
272
279
286
1.9
15
21.04.2008
68.7
18.5
6.9
9.3
293
299
307
2.1
16
22.04.2008
75.4
21.4
8.2
9.5
266
279
287
1.5
17
28.04.2008
79.7
23.4
8.9
10.5
280
291
297
2.3
18
29.04.2008
82.9
24.6
7.7
9.7
299
311
317
1.7
19
05.05.2008
89.9
25.6
8.1
11.3
280
291
297
3.1
20
06.05.2008
84.2
23.4
6.5
8.3
303
314
320
3.3
21
12.05.2008
68.9
18.6
5.9
7.6
299
309
322
2.6
22
13.05.2008
87.8
25.4
7.7
10.6
292
297
306
2.5
23
19.05.2008
75.1
20.3
6.9
9.8
273
282
296
1.8
24
20.05.2008
72.1
20.4
7.6
10.0
295
307
316
2.2
25
26.05.2008
86.8
24.5
8.2
10.5
295
303
310
2.1
26
27.05.2008
81.2
51.3
25.4
15.4
7.9
5.4
8.7
7.6
287
298
262
305
2.8
1.5
Min
1.9
Max
92.4
29.5
9.3
11.3
322
3.3
Avg
80.4
91.3
23.4
29.0
7.5
9.2
9.8
11.3
293.9
320.6
2.4
3.3
98th
All units are in g/m3
AV-7
ANNEXURE-V
AMBIENT AIR QUALITY LEVELS
Sr. No.
Date
Ozone (O3)
CO
03.03.2008
96.2
26.9
7.0
8.9
258
251
267
2.5
04.03.2008
91.5
25.4
6.6
7.8
295
243
308
1.7
10.03.2008
85.4
23.1
6.9
7.6
286
270
285
1.8
11.03.2008
105.9
33.4
8.1
9.2
274
281
276
2.4
17.03.2008
90.4
25.6
7.2
8.5
254
262
264
2.2
18.03.2008
94.5
26.5
8.3
9.4
280
264
254
2.8
98.6
119.8
28.9
7.2
8.6
290
310
250
1.7
33.6
8.7
9.9
274
304
245
1.5
24.03.2008
25.03.2008
31.03.2008
7.2
8.7
297
290
290
2.1
01.04.2008
87.6
110.4
24.5
10
29.7
7.1
8.5
281
304
286
2.6
11
07.04.2008
59.7
16.7
7.3
8.9
304
317
276
1.4
12
08.04.2008
85.6
24.4
7.7
6.6
278
296
284
1.5
13
14.04.2008
99.7
27.4
8.3
9.9
254
274
282
3.1
14
15.04.2008
115.6
37.9
9.6
10.2
297
286
273
3.3
15
21.04.2008
10.9
290
284
253
2.1
22.04.2008
28.4
30.1
8.9
16
96.5
106.2
9.8
11.8
262
255
302
2.6
17
28.04.2008
117.1
35.4
10.2
12.2
290
307
330
2.5
18
29.04.2008
114.4
32.2
9.7
10.9
272
294
248
2.1
19
05.05.2008
24.6
32.4
9.4
281
272
278
2.4
06.05.2008
86.5
120.0
7.4
20
10.9
12.5
269
281
289
2.7
21
12.05.2008
81.2
25.1
7.5
8.6
256
258
275
2.3
22
13.05.2008
114.8
32.6
9.8
10.7
282
262
270
2.9
23
19.05.2008
78.6
21.6
7.2
8.8
294
307
280
2.2
24
20.05.2008
115.2
33.4
8.9
9.9
262
290
286
2.3
25
26.05.2008
96.4
27.5
7.5
8.7
297
296
269
2.6
26
27.05.2008
118.1
34.6
288
247
59.7
16.7
11.6
6.6
285
Min
10.9
6.6
243
2.3
1.4
Max
120.0
37.9
10.9
12.5
330
3.3
Avg
99.5
119.9
28.5
36.7
8.3
10.9
9.6
12.4
279.2
313.2
2.3
3.2
98th
All units are in g/m3
AV-8
ANNEXURE-V
AMBIENT AIR QUALITY LEVELS
Sr. No.
Date
03.03.2008
90.6
04.03.2008
107.4
31.3
8.6
NOX
Ozone (O3)
CO
26.3
7.3
8.4
273
260
266
2.3
9.3
278
258
263
2.6
10.03.2008
87.1
25.2
6.6
7.4
276
259
264
2.1
11.03.2008
113.5
32.1
8.9
10.2
274
261
267
1.9
17.03.2008
93.9
26.9
7.6
8.6
272
263
269
2.3
18.03.2008
110
32.3
8.3
9.4
280
266
273
3.1
24.03.2008
90.4
26.5
7.4
8.7
272
259
265
2.4
25.03.2008
102.3
29.0
7.7
8.8
269
258
262
2.6
31.03.2008
94.6
28.7
8.5
9.2
274
258
268
2.4
10
01.04.2008
80.3
20.1
9.2
10.4
279
257
261
1.8
2.1
11
07.04.2008
88.2
26.0
6.9
8.7
272
260
259
12
08.04.2008
108.5
30.3
8.1
9.4
273
263
263
2.6
13
14.04.2008
86.6
25.4
6.7
8.2
276
259
267
2.5
14
15.04.2008
91.1
27.2
7.1
8.8
278
258
269
2.2
15
21.04.2008
100
29.0
9.2
274
256
266
2.6
16
22.04.2008
90.6
26.4
9.3
9.9
275
254
263
2.4
17
28.04.2008
96.3
29.7
7.8
9.0
284
258
273
2.6
18
29.04.2008
82.6
23.4
6.9
8.5
294
269
314
2.7
19
05.05.2008
103.4
26.4
9.4
273
257
272
2.9
20
06.05.2008
110.4
33.3
8.9
10.6
280
249
264
2.6
21
12.05.2008
90.7
26.4
8.4
274
255
258
2.6
22
13.05.2008
101
28.3
8.3
9.5
276
257
259
2.4
23
19.05.2008
72.6
20.6
5.2
6.5
273
258
264
2.2
2.6
24
20.05.2008
90.2
27.4
6.8
8.6
279
260
268
25
26.05.2008
103.5
30.0
8.5
9.6
277
263
305
2.7
26
27.05.2008
94.6
26.2
9.1
10.3
271
256
261
Min
72.6
20.1
5.2
6.5
249
2.9
1.8
Max
113.5
33.3
9.3
10.6
314
3.1
Avg
95.4
112.0
27.5
32.8
7.8
9.3
9.0
10.5
267.8
299.1
2.5
3.0
98th
All units are in g/m3
AV-9
ANNEXURE-V
AMBIENT AIR QUALITY LEVELS
Sr. No.
Date
NOX
CO
Ozone (O3)
03.03.2008
91.6
27.2
5.6
6.5
256
309
269
1.8
04.03.2008
97.4
32.2
6.1
8.3
233
246
256
2.1
10.03.2008
98.9
29.7
9.0
10.7
256
234
229
2.1
11.03.2008
106.1
33.4
8.7
10.2
218
263
246
2.9
17.03.2008
82.2
27.1
7.0
10.9
235
229
246
3.3
18.03.2008
105.0
30.8
7.2
7.1
226
298
321
3.4
24.03.2008
59.9
17.6
8.6
9.1
275
286
254
2.3
25.03.2008
72.4
23.9
9.0
9.5
240
298
263
2.1
31.03.2008
92.0
30.4
7.3
8.1
269
254
247
3.1
10
01.04.2008
103.9
28.7
9.8
12.4
300
309
240
3.3
11
07.04.2008
95.4
30.4
9.4
10.2
278
236
241
2.3
12
08.04.2008
101.9
28.5
8.6
9.7
230
215
240
2.5
13
14.04.2008
93.6
29.8
7.3
8.3
275
295
321
2.6
14
15.04.2008
80.5
26.6
9.0
9.7
286
252
263
2.9
15
21.04.2008
104.6
33.4
8.9
10.1
240
221
230
3.3
16
22.04.2008
87.6
23.9
9.4
11.1
256
324
275
2.6
17
28.04.2008
81.7
25.8
8.0
8.9
235
216
226
2.3
18
29.04.2008
102.7
29.1
8.4
9.5
240
256
275
2.1
19
05.05.2008
101.6
27.6
8.7
10.1
226
259
321
2.8
20
06.05.2008
97.9
28.4
8.1
8.6
240
252
286
2.4
21
12.05.2008
97.2
31.3
8.6
10.2
265
321
309
2.8
22
13.05.2008
102.0
30.6
7.4
9.4
254
296
284
3.4
23
19.05.2008
105.9
34.9
8.5
10.1
269
309
332
3.2
24
20.05.2008
92.7
25.6
9.4
11.6
26.05.2008
64.5
17.4
7.3
9.8
240
246
221
275
2.3
25
235
265
26
27.05.2008
23.4
17.4
8.2
5.6
10.7
6.5
254
249
267
Min
84.9
59.9
Max
106.1
34.9
9.8
Avg
92.5
106.0
28.0
34.2
8.2
9.6
98th
1.8
215
2.3
1.8
12.4
332
3.4
9.6
12.0
261.7
322.4
2.6
3.4
AV-10
ANNEXURE-V
AMBIENT AIR QUALITY LEVELS
Sr. No.
Date
AAQ11(Binjkot village)
TSPM
RPM
SO2
NOX
CO
Ozone (O3)
03.03.2008
18.9
7.6
9.1
04.03.2008
77.0
85.0
288
267
293
24.2
7.9
10.3
307
257
273
1.8
2.3
10.03.2008
66.4
24.6
7.1
8.8
261
256
259
2.3
11.03.2008
78.7
8.0
9.6
295
244
265
2.5
17.03.2008
80.7
19.4
20.5
7.5
9.8
273
274
277
1.4
18.03.2008
85.3
25.4
7.7
9.3
277
257
288
1.3
24.03.2008
89.3
27.4
7.4
9.9
263
277
273
1.9
25.03.2008
70.1
26.5
7.0
9.1
287
278
278
2.5
31.03.2008
83.9
22.2
6.8
9.2
268
298
243
1.6
10
01.04.2008
90.2
24.5
7.2
9.3
269
273
273
2.2
11
07.04.2008
87.2
7.6
9.0
265
267
260
1.8
12
08.04.2008
74.6
27.6
24.5
7.8
10.2
257
277
283
1.8
13
14.04.2008
24.6
8.0
9.7
272
270
283
1.9
14
15.04.2008
85.7
68.5
18.9
7.0
9.4
266
273
263
2.4
15
21.04.2008
64.6
17.7
6.6
8.4
267
279
261
1.8
16
22.04.2008
88.2
26.2
6.7
9.2
308
261
265
2.6
17
28.04.2008
105.6
27.2
6.8
7.8
276
267
310
2.2
18
29.04.2008
101.9
33.6
7.9
10.0
260
248
273
2.5
19
05.05.2008
99.4
30.4
6.7
9.4
242
293
265
2.1
20
06.05.2008
97.2
28.6
7.5
8.7
293
288
293
1.8
21
12.05.2008
29.5
5.8
7.2
277
257
233
2.9
22
13.05.2008
54.5
100.9
27.5
8.1
9.9
294
249
257
2.1
23
19.05.2008
96.2
26.5
7.6
10.8
248
310
293
2.9
24
20.05.2008
62.5
29.9
7.8
9.0
254
255
259
2.7
25
26.05.2008
86.7
26.2
8.1
7.9
273
269
243
1.7
26
27.05.2008
25.4
17.7
6.7
5.8
8.2
7.2
254
283
273
Min
93.8
54.5
233
1.7
1.3
Max
105.6
33.6
8.1
10.8
310
2.9
Avg
83.6
103.8
25.3
32.0
7.3
8.1
9.2
10.6
271.2
308.9
2.1
2.9
98th
All units are in g/m3
AV-11
ANNEXURE-V
AMBIENT AIR QUALITY LEVELS
Sr. No.
Date
AAQ12(Dengurchua village)
TSPM
RPM
SO2
NOX
CO
03.03.2008
64.1
16.9
6.3
9.9
286
04.03.2008
70.4
18.7
7.0
10.6
292
Ozone (O3)
270
254
1.9
260
269
1.7
10.03.2008
85.8
22.3
6.6
8.5
285
285
261
1.5
11.03.2008
9.2
280
289
260
1.7
17.03.2008
24.6
16.6
6.6
80.3
60.4
5.1
8.2
275
294
254
1.6
18.03.2008
63.8
17.2
5.4
7.6
264
296
246
1.4
24.03.2008
67.0
18.5
5.6
8.1
252
305
224
2.3
25.03.2008
70.4
19.1
5.8
8.6
248
310
226
3.6
31.03.2008
91.6
23.6
6.0
10.5
300
300
286
1.8
10
01.04.2008
92.8
25.5
7.3
11.2
292
290
280
1.5
11
07.04.2008
89.1
23.1
6.2
8.5
280
271
264
1.6
12
08.04.2008
90.3
24.1
6.4
7.4
275
304
262
1.5
13
14.04.2008
95.2
26.4
8.2
9.9
287
287
266
2.3
14
15.04.2008
93.9
24.3
6.5
7.6
277
283
254
1.9
15
21.04.2008
90.0
25.6
5.4
8.1
252
269
239
1.4
16
22.04.2008
103.5
29.8
8.9
10.2
246
291
300
2.5
17
28.04.2008
93.6
26.4
5.7
8.7
262
298
238
1.8
18
29.04.2008
74.4
20.4
6.9
9.4
261
305
236
1.3
19
05.05.2008
80.0
5.2
7.7
266
293
237
2.6
20
06.05.2008
82.7
22.5
23.4
6.8
8.4
246
281
238
1.9
21
12.05.2008
87.1
24.7
5.9
9.1
280
304
298
1.6
22
13.05.2008
92.6
26.4
7.5
9.8
310
292
295
1.3
23
19.05.2008
85.8
22.6
6.6
9.7
300
309
266
1.7
24
20.05.2008
80.0
5.7
8.7
290
303
260
1.3
25
26.05.2008
7.1
8.4
294
299
280
2.2
26
27.05.2008
90.8
93.7
20.8
25.5
6.3
5.1
10.6
7.4
300
302
270
16.6
224
2.3
1.3
26.4
Min
60.4
Max
103.5
29.8
8.9
11.2
310
3.6
Avg
83.4
99.4
22.9
28.1
6.4
8.6
9.0
10.9
276.3
309.5
1.9
3.1
98th
All units are in g/m3
AV-12
ANNEXURE-VI
METHODOLOGY FOR SAMPLING AND ANALYSIS
1.0
Meteorology
The methodology adopted for monitoring surface observations is as per the
standard norms laid down by Bureau of Indian Standards (IS : 8829) and India
Meteorological Department (IMD).
1.1
Sensor
Wind speed Sensor
Wind direction Sensor
Temperature Sensor
Sensitivity
0.02 m/s
3 degrees
0.2oC
Hourly maximum, minimum and average values of wind speed, direction and
temperature were recorded continuously with continuous monitoring equipment.
All the sensors were connected to filter and then logged on to datalogger. The
readings were recorded in a memory module, which was attached to datalogger.
The memory module was downloaded in computer through Dynalab software. The
storage capacity of memory module was 256 KB. Data was downloaded every
fortnight into the computer. The data was recorded continuously. The recovery of
data was about 98%. The rest of 2 % data gaps were filled by referring to IMD
data and daily weather reports in the local newspapers. However, Relative
Humidity and Rainfall were recorded manually.
1.2
1.2.1
Method of Analysis
The air samples were analyzed as per standard methods specified by Central
Pollution Control Board (CPCB), IS: 5184 and American Public Health Association
(APHA).
1.2.2
ANNEXURE-VI
METHODOLOGY FOR SAMPLING AND ANALYSIS
1.2.3
1.2.4
Sr.
No
1
Instrument Name
Make
Model
Spectrophotometer
HACH
Electronic Balance
Metler
Gas Chromatograph
With FID, pFPD,
ECD
GC-3,
VARIAN
Parameters
SO2, NOx, O3
TSPM, SPM,
RPM
CO
SPM (>10 ) and RPM (<10 ) present in ambient air is drawn through the
cyclone. Coarse and non-respirable dust (>10) is separated from the air stream
by centrifugal forces acting on the solid particles. These separated particulates fall
through the cyclone's conical hopper and collect in the sampling cup placed at the
bottom of the cyclone. The fine dust (<10 microns) forming the respirable
fraction passes the cyclone and is retained by the filter paper. The TSPM is
estimated by summing up the SPM and RPM fractions collected separately as
above.
A tapping is provided on the suction side of the blower to provide suction for
sampling air through a set of impingers. Samples of gases are drawn at a flow
rate of 0.2 Liters Per Minute (LPM).
TSPM and RPM have been estimated by Gravimetric method (IS: 5182, Part IV).
Modified West and Gaeke method (IS-5182 Part-II, 1969) has been adopted for
estimation of SO2. Jacobs-Hochheiser method (IS-5182 Part-VI, 1975) has been
adopted for the estimation of NOx.
Calibration:
Calibration charts have been prepared for all gaseous pollutants. The calibration is
carried out whenever new absorbing solutions are prepared. All the Resirable Dust
Samplers are calibrated as per ASTM D-4096. The rotameter is calibrated using
soap bubble meter.
2]
Carbon Monoxide
Charcoal filled glass tubes have been used for collecting the samples of Carbon
monoxide. The CO levels were analyzed through Gas Chromatography techniques.
The techniques used for ambient air quality monitoring and minimum detectable
level are given in Table-3.
AVI-2
ANNEXURE-VI
METHODOLOGY FOR SAMPLING AND ANALYSIS
TABLE-3
TECHNIQUES USED FOR AMBIENT AIR QUALITY MONITORING
Sr.
No.
Parameter
Technique
Total Suspended
Particulate Matter
Respirable
Particulate Matter
Sulphur dioxide
Oxide of Nitrogen
Carbon Monoxide
Gas Chromatography
Ozone (O3)
Technical
Protocol
IS-5182
(Part-IV)
IS-5182
(Part-IV)
IS-5182
(Part-II)
IS-5182
(Part-VI)
IS-5182
(Part-X)
ASTM-D
5011-92
Minimum
Detectable Limit
(
g/m3)
5.0
5.0
4.0
4.0
12.5
1.0
Water Analysis
Samples for chemical analysis were collected in polyethylene carboys. Samples
collected for metal content were acidified with 1 ml HNO3. Samples for
bacteriological analysis were collected in sterilized glass bottles. Selected physicochemical and bacteriological parameters have been analyzed for projecting the
existing water quality status in the study area. Parameters like temperature,
Dissolved Oxygen (DO) and pH were analyzed at the time of sample collection.
The methodology for sample collection and preservation techniques was followed as
per the Standard Operating Procedures (SOP) mentioned in Table-4.
TABLE-4
STANDARD OPERATING PROCEDURES (SOP)
FOR WATER AND WASTEWATER SAMPLING
Parameter
pH
Electrical
Conductivity
Total suspended
solids
Total
Dissolved
Solids
BOD
Hardness
Sample Collection
Grab sampling
Plastic /glass container
Grab sampling
Plastic /glass container
Grab sampling
Plastic /glass container
Grab sampling
Plastic /glass container
Grab sampling
Plastic /glass container
Grab sampling
Plastic /glass container
Sample Size
50 ml
Storage/ Preservation
On site analysis
50 ml
On site parameter
100 ml
Refrigeration,
can be stored for 7 days
Refrigeration,
can be stored for 7 days
Refrigeration, 48 hrs
100 ml
500 ml
100 ml
Add
HNO3
to
pH<2,
refrigeration; 6 months
AVI-3
ANNEXURE-VI
METHODOLOGY FOR SAMPLING AND ANALYSIS
Parameter
Chlorides
Sulphates
Sodium,
Potassium
Nitrates
Fluorides
Alkalinity
Ammonia
Sample Collection
Grab sampling
Plastic /glass container
Grab sampling
Plastic /glass container
Plastic container
Sample Size
50 ml
Storage/ Preservation
Not required; 28 days
100 ml
Refrigeration; 28 days
100 ml
Plastic containers
Plastic containers only
Plastic/ glass containers
Plastic/ glass containers
100
100
100
100
Refrigeration; 48 hrs
Not required; 28 days
Refrigeration; 14 days
Add
H2SO4
to
pH>2,
refrigeration, 28 days
Grab sample; refrigeration; 24
hrs
Filter, add HNO3 to pH>2;
Grab sample; 6 months
ml
ml
ml
ml
Hexavalent
Plastic/ Glass rinse with 1+1 100 ml
Chromium, Cr+6
HNO3
Heavy Metals (Hg, Plastic/ Glass rinse with 1+1 500 ml
Cd, Cr, Cu, Fe, HNO3
Zn, Pb etc.)
Source: Standard Methods for the Examination of Water and Wastewater, Published By APHA, AWWA,
WEF 19th Edition, 1995
1.3.1
Analytical Techniques
The analytical techniques used for water and wastewater analysis is given in the
Table-5.
TABLE-5
ANALYTICAL TECHNIQUES
FOR WATER AND WASTEWATER ANALYSIS
Parameter
pH
Colour
Odour
Temperature
Dissolved Oxygen
BOD
Electrical conductivity
Turbidity
Chlorides
Fluorides
Total dissolved solids
Total suspended solids
Total hardness
Sulphates
Arsenic
Calcium
Magnesium
Sodium
Potassium
APHA-4500-H+
APHA-2120 C
IS: 3025, Part-4
APHA-2550 B
APHA-4500 O
APHA-5210 B
APHA-2510 B
APHA-2130 B
APHA-4500 ClAPHA-4500 FAPHA-2540 C
APHA-2540 D
APHA-2340 C
APHA-4500 SO4-2
APHA-3120 B/ APHA-3114
APHA-3120 B/ APHA-3500
APHA-3120 B/ APHA-3500
APHA-3120 B/ APHA-3500
APHA-3120 B/ APHA-3500
Method
Manganese
Mercury
Selenium
Lead
Copper
Cadmium
Iron
Zinc
Boron
Coliform organisms
Alkalinity
APHA-3120
APHA-3112
APHA-3120
APHA-3120
APHA-3120
APHA-3120
APHA-3120
APHA-3120
APHA-4500
APHA-9215
APHA-2320
B/
B/
B/
B/
B/
B/
B/
B/
B
D
B
APHA-3500
APHA-3500
APHA-3114
APHA-3500
APHA-3500
APHA-3500
APHA-3500
APHA-3500
B/ APHA-3500 As
Ca
Mg
Na
K
Mn
Hg
B/ APHA-3500 Se
Pb
Cu
Cd
Fe
Zn
AVI-4
ANNEXURE-VI
METHODOLOGY FOR SAMPLING AND ANALYSIS
1.4
Soil Quality
At each location, soil samples were collected from three different depths viz. 30
cm, 60 cm and 90 cm below the surface and are homogenized. This is in line with
IS: 2720 & Methods of Soil Analysis, Part-1, 2nd edition, 1986 of (American
Society for Agronomy and Soil Science Society of America). The homogenized
samples were analyzed for physical and chemical characteristics. The soil samples
were collected and analyzed once in each season.
The samples have been analyzed as per the established scientific methods for
physico-chemical parameters. The heavy metals have been analyzed by using
Atomic Absorption Spectrophotometer and Inductive Coupled Plasma Analyzer.
The methodology adopted for each parameter is described in Table-6.
TABLE-6
ANALYTICAL TECHNIQUES FOR SOIL ANALYSIS
Parameter
Grain size distribution
Textural classification
Infiltration capacity
Bulk density
Porosity
Sodium absorption ratio
PH
Electrical conductivity
Nitrogen
Phosphorus
Potassium
Copper
Iron
Zinc
Boron
Chlorides
Fluorides
1.5
Noise Levels
ANNEXURE-VI
METHODOLOGY FOR SAMPLING AND ANALYSIS
Hourly Leq values have been computed by integrating sound level meter.
Lday: As per the CPCB guidelines the day time limit is between 07:00 hours to
22.00 hours as outlined in Ministry of Environment and Forest Notification S.O.
123 (E) dated 14/02/2000.
Lnight: As per the CPCB guidelines the night time limit is between 22:00 hours to
07.00 hours as outlined in Ministry of Environment and Forest Notification S.O.
123 (E) dated 14/02/2000.
[
Ldn = 10Log
i =1
10
(Leq i / 10)
10
(Leq i + 10 / 10)
i =1
24
AVI-6
ANNEXURE-VII
FLORA AND FAUNA
TABLE-1
PLANT SPECIES RECORDED IN STUDY AREA
Sr. No.
Technical Name
Family
I. Agricultural crops
II. Commercial crops
1.
Hordium vulgare
Poaceae
2.
Sorghum vulgare
Poaceae
3.
Triticum vulgare
Poaceae
4.
Zea mays
Poaceae
5.
Oryza sativa
Poaceae
6.
Pennisetum typhoideum
Poaceae
II
Commercial crops( including vegetables)
7.
Abelomoschus indicus
Malvaceae
8.
Allium cepa
Liliaceae
9.
Allium sativum
Liliaceae
10.
Annona squamosa
Annonaceae
11.
Arachis hypogia
Fabaceae
12.
Beta vulgaris
Chenopodiaceae
13.
Brassica oleracea var botrydis
Cruciferae
14.
Brassica oleracea var capitata
Cruciferae
15.
Cajanus cajan
Fabaceae
16.
Carica papaya
Caricaceae
17.
Catharanthes pusillus
Compositae
18.
Cicer arietinum
Fabaceae
19.
Citrus lemon
Ruataceae
20.
Colacasia esculenta
Areaceae
21.
Coreandrum sativum
Umbelliferae
22.
Daucus carota
Umbelliferae
23.
Lycopersicum esculentus
Solanaceae
24.
Mangifera indica
Anacardiaceae
25.
Memordia charantia
Cucurbitaceae
26.
Psidium guava
Myrtaceae
27.
Raphanus sativa
Cruciferae
28.
Solanum tuberosum
Solanaceae
III. Plantations
29.
Acacia nilotica
Mimosaceae
30.
Albizia lebbeck
Mimosaceae
31.
Albizia odorattissima
Mimosaceae
32.
Albizia procera
Mimosaceae
33.
Bauhinia variegata
Caesalpinaceae
34.
Bauhinia purpuria
Caesalpinaceae
35.
Bambusa arundanaceae
Poaceae
36.
Butea superba
Caesalpinaceae
37.
Eucalyptus sp
Myrtaceae
38.
Delonix regia
Caesalpinaceae
39.
Pongamia pinnata
Ceasalpinaceae
Natural Vegetation/Forest Tyepe
40.
Abutilon indicum
Malvaceae
41.
Acacia Arabica
Mimosaceae
42.
Acacia auriculiformis
Mimosaceae
43.
Acacia leucophloe
Mimosaceae
44.
Acanthospermum hispidum
Compositae
45.
Achras sapota
Sapotaceae
46.
Achyranthes aspera
Amaranthaceae
47.
Adina cordifolia
Rubiaceae
Life form
Hemicryptophyte
Hemicryptophyte
Hemicryptophyte
Hemicryptophyte
Hemicryptophyte
Hemicryptophyte
Therophyte
Geophyte
Geophyte
Phanerophyte
Geophyte
Geophyte
Therophyte
Therophyte
Therophyte
Therophyte
Therophyte
Hemicryptophyte
Therophyte
Geophyte
Hemicryptophyte
Geophyte
Therophyte
Phanerophyte
Therophyte
Phanerophyte
Geophyte
Geophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Therophyte
Phanerophyte
Therophyte
Phanerophyte
AVII-1
ANNEXURE-VII
FLORA AND FAUNA
Sr. No.
48.
49.
50.
51.
52.
53.
54.
55.
56.
57.
58.
59.
60.
61.
62.
63.
64.
65.
66.
67.
68.
69.
70.
71.
72.
73.
74.
75.
76.
77.
78.
79.
80.
81.
82.
83.
84.
85.
86.
87.
88.
89.
90.
91.
92.
93.
94.
95.
96.
97.
98.
99.
100.
101.
102.
Technical Name
Aegle marmelos
Agave wightii
Ageratum conyzoides
Ailanthes excela
Aloe barbedensis
Alstonia scholaris
Alysicarpus hamosus
Alysicarpus monilifer
Ammania baccafera
Antidesma diandrum
Argemone mexicana
Asparagaus racemosus
Atalantia monophylla
Azadirachta indica
Barleria prionoites
Bidens biternata
Blepharis asperima
Blepharis madaraspatens
Blumea lacera
Boerheavia chinensis
Boerheavia diffusa
Borreria hispida
Borreria stricta
Caesalpina pulcherima
Calotropis gigantia
Calotropis procera
Canna indicda
Cannabis sativa
Canthium diddynum
Careya arborea
Carissa carandus
Cassia absus
Cassia auriculata
Cassia obtuse
Cassia occidentalis
Cassia pumella
Cassia tora
Cayratia terifolia
Ceiba pentandra
Cestrum diurnum
Cestrum noctrunum
Chloris varigata
Chrysanthemum sp
Cissus quadrangularis
Citrus liminoites
Citrus media
Cleome gynandra
Cleome viscose
Clitoria ternate
Cocculus villosa
Combretum ovalifolium
Commelina benghalensis
Cordia dichotoma
Crotalaria medicagenia
Croton bonplandinum
Family
Rutaceae
Agavaceae
Compositae
Simaroubaceae
Agavaceae
Apocyanaceae
Fabaceae
Fabaceae
Lytharaceae
Euphorbiaceae
Papevaraceae
Liliaceae
Rutaceae
Meliaceae
Acanthaceae
Compositae
Acanthaceae
Acanthaceae
Compositae
Nycataginaceae
Nyctaginaceae
Rubiaceae
Rubiaceae
Caesalpinaceae
Asclepiadaceae
Asclipiadaceae
Cannaceae
Cannabinaceae
Rubiaceae
Palmae
Apocyanaceae
Caesalpinaceae
Caesalpinaceae
Caesalpinaceae
Caesalpinaceae
Caesalpinaceae
Caesalpinaceae
Vitaceae
Bombacaceae
Rubiaceae
Rubiaceae
Poaceae
Compositae
Vitaceae
Rutaceae
Rutaceae
Capparidaceae
Capparidaceae
Fabaceae
Cucurbiataceae
Rubiaceae
Commelinaceae
Rubiaceae
Fabaceae
Amaryllidaceae
Life form
Phanerophyte
Phanerophyte
Therophyte
Phanerophyte
Geophyte
Phanerophyte
Therophyte
Therophyte
Therophyte
Hemicryptophyte
Phanerophyte
Therophyte
Therophyte
Phanerophyte
Therophyte
Therophyte
Phanerophyte
Therophyte
Therophyte
Therophyte
Therophyte
Therophyte
Therophyte
Phanerophyte
Phanerophyte
Phanerophyte
Therophyte
Hemicryptophyte
Phanerophyte
Phanerophyte
Phanerophyte
Therophyte
Therophyte
Therophyte
Therophyte
Therophyte
Phanerophyte
Phanerophyte
Phanerophyte
Theophyte
Therophyte
Therophyte
Therophyte
Therophyte
Phanerophyte
Phanerophyte
Therophyte
Therophyte
Therophyte
Phanerophyte
Phanerophyte
Therophyte
Phanerophyte
Therophyte
Therophyte
AVII-2
ANNEXURE-VII
FLORA AND FAUNA
Sr. No.
103.
104.
105.
106.
107.
108.
109.
110.
111.
112.
113.
114.
115.
116.
117.
118.
119.
120.
121.
122.
123.
124.
125.
126.
127.
128.
129.
130.
131.
132.
133.
134.
135.
136.
137.
138.
139.
140.
141.
142.
143.
144.
145.
146.
147.
148.
149.
150.
151.
152.
153.
154.
155.
156.
157.
Technical Name
Cuscuta reflexa
Daemia extensa
Datura alba
Datura metal
Dendrophthe falcate
Desmodium triflorum
Eichhornia cressipes
Emblica officinale
Erythrina indica
Euphorbia geniculata
Euphorbia hirta
Euphorbia hyperocifolia
Euphorbia nerifolia
Euphorbia nivula
Euphorbia piluliflora
Euphorbia tricauli
Evolvulus alsinoides
Fagonia cretica
Feronia elephantum
Ficus benghalensis
Ficus carica
Ficus glomerata
Ficus hispida
Ficus racemosus
Ficus relisiosa
Ficus gibbosa
Flacourtia indica
Flacourtia Montana
Fumaria indica
Gardenia latifolia
Garuga pinnata
Gmelina arborea
Grewia abutifolia
Grewia subinaqualis
Haplanthus tentaculatus
Helictris isora
Heliotropium indicum
Hemidesmus indicus
Hibiscus gibbosa
Hibiscus micronthus
Hibiscus ovalifolia
Hibiscus rosa-cianensis
Hibsicus caesus
Hyptis suavalens
Ipomea aquatica
Ipomea carnea
Ixora parviflora
Ixora singapuriens
Jacarandra jacquimontii
Jasmimum arborens
Jatropha gossypifolia
Justia simplex
Jussiaea suffraticosa
Justia diffusa
Justicia diffusa
Family
Cuscutaceae
Fabaceae
Solanaceae
Solanaceae
Loranthaceae
Asclepiadaceae
Pontederiaceae
Euphorbiaceae
Papillionaceae
Euphorbiaceae
Euphorbiaceae
Euphorbiaceae
Euphorbiaceae
Euphorbiaceae
Euphorbiaceae
Euphorbiaceae
Convolvulaceae
Zygophyllaceae
Rutaceae
Moraceae
Moraceae
Moraceae
Moraceae
Moraceae
Moraceae
Moraceae
Flacourtiaceae
Flacourtiaceae
Papillionaceae
Rubiaceae
Burseraceae
Rubiaceae
Tiliaceae
Tiliaceae
Acanthaceae
Rubiaceae
Rubiaceae
Asclepiadaceae
Malvaceae
Malvaceae
Malvaceae
Malvaceae
Malvaceae
Labiatae
Convolvulaceae
Convolvulaceae
Rubiaceae
Rubiaceae
Bignoniaceae
Oleaceae
Euphorbiaceae
Acanthaceae
Onagraceae
Acanthaceae
Acanthaceae
Life form
Epiphyte
Therophyte
Therophyte
Therophyte
Hemicryptophyte
Therophyte
Hydrophyte
Phanerophyte
Phanerophyte
Therophyte
Therophyte
Therophyte
Phanerophyte
Therophyte
Hemicryptophyte
Hemicryptophyte
Therophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Hemicryptophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Therophyte
Phanerophyte
Hemicryptophyte
Phanerophyte
Therophyte
Therophyte
Therophyte
Therophyte
Hemicryptophyte
Therophyte
Hydrophyte
Phanerophyte
Phanerophyte
Phanerophyte
Therophyte
Phanerophyte
Therophyte
Therophyte
Hydrophyte
Therophyte
Therophyte
AVII-3
ANNEXURE-VII
FLORA AND FAUNA
Sr. No.
158.
159.
160.
161.
162.
163.
164.
165.
166.
167.
168.
169.
170.
171.
172.
173.
174.
175.
176.
177.
178.
179.
180.
181.
182.
183.
184.
185.
186.
187.
188.
189.
190.
191.
192.
193.
194.
195.
196.
197.
198.
199.
200.
201.
202.
203.
204.
205.
206.
207.
208.
209.
210.
211.
212.
Technical Name
Kyllinga trceps
Lannea grandis
Lantana camara
Lathyrus sativus
Lawsonia inermis
Lemna minor
Leucas aspera
Leucas longifolia
Leucas stelligera
Lycopersicum esculentus
Madhuca latifolia
Mallotus philippinus
Malvastrum coramandalicum
Marselia quadrifolia
Medicago aureus
Memordica diocea
Memycelon edule
Mentha piperata
Merremia emerginata
Mesua ferrea
Millingtonia hartensis
Mimosa hamata
Moringa olerifera
Murraya exotica
Murraya koenigii
Musa paradisica
Nelumbium nuciferum
Nerium indicum
Nicotiana plubigera
Nymphia sp
Ocimum americanum
Ocimum basillum
Ocimum sanctum
Oldenlandiua corymbosa
Opuntia dillinii
Oxalis corniculata
Panicum milliria
Panicum notatum
Parthenium hysterophorus
Passiflora foetida
Peltophorum ferrusinum
Peristrophe bicalculata
Phoenix aculis
Phyllanthes asperulatus
Phyllanthes emblica
Phyllanthes nirurii
Phyllanthes reticulates
Physalis minima
Pithocolobium dulce
Polyalthia longifolia
Polygala ererptera
Prosopis cineraria
Prosopis juliflora
Prosopis spicegera
Saccharum munja
Family
Cyperaceae
Anacardiaceae
Verbinacaee
Papillionaceae
Lythraceae
Lemnaceae
Labiatae
Labiatae
Labiatae
Solanaceae
Sapotaceae
Euphorbiaceae
Malvaceae
Marseliaceae
Papillionaceae
Cucurbitaceae
Melastonellaceae
Labiatae
Convolvulaceae
Guttiferae
Bignoniaceae
Mimosaceae
Moringaeae
Rutaceae
Rutaceae
Musaceae
Magnoliaceae
Apocyanaceae
Solanaceae
Magnoliaceae
Labiatae
Labiatae
Labiatae
Rubiaceae
Opuntiaceae
Oxalidaceae
Poaceae
Poaceae
Compositae
Passifloraceae
Caesalpinaceae
Acanthaceae
Palmae
Euphorbiaceae
Euphorbiaceae
Euphorbiaceae
Euphorbiaceae
Solanaceae
Mimosaceae
Annonaceae
Polygalaceae
Mimosaceae
Mimosaceae
Mimosaceae
Poaceae
Life form
Hemicryptophyte
Phanerophyte
Phanerophyte
Hemicryptophyte
Phanerophyte
Hydrophyte
Therophyte
Therophyte
Therophyte
Therophyte
Phanerophyte
Phanerophyte
Therophyte
Phanerophyte
Phanerophyte
Therophyte
Phanerophyte
Hemicryptophyte
Therophyte
Phanerophyte
Phanerophyte
Therophyte
Phanrophyte
Phanerophyte
Phanerophyte
Therophyte
Hydrophyte
Phanerophyte
Hemicryptophyte
Hydrophyte
Therophyte
Therophyte
Therophyte
Therophyte
Therophyte
Therophyte
Hemicryptophyte
Hemicryptophyte
Therophyte
Phanerophyte
Phanerophyte
Therophyte
Phanerophyte
Phanerophyte
Phanerophyte
Therophyte
Therophyte
Therophyte
Phanerophyte
Phanerophyte
Therophyte
Phanerophyte
Phanerophyte
Phanerophyte
Hemicryptophyte
AVII-4
ANNEXURE-VII
FLORA AND FAUNA
Sr. No.
213.
214.
215.
216.
217.
218.
219.
220.
221.
222.
223.
224.
225.
226.
227.
228.
229.
230.
231.
232.
233.
234.
235.
236.
237.
238.
239.
240.
241.
242.
243.
Technical Name
Salmalia malabarica
Sapindus emerginatus
Schleichera oleosa
Sesamum indicum
Shorea robusta
Sida cordifolia
Sida vernanifolia
Solanum nigrum
Solanum suratensis
Solanum xanthocarpum
Sterculia villosa
Sygygium cumini
Tamarindus indica
Tecomella undulate
Tectona grandis
Tephrosia purpuria
Thespesia populanea
Thespesia lampas
Tinospora cordifolia
Tragus biflorus
Trapa bispinosa
Trapa natans
Tridax procumbens
Trigonella cornuculata
Vicoa indica
Vitex negungo
Wrightia tomentosa
Yucca gloriosa
Zizyphus jujube
Zizyphus mauritiana
Zornia gobbosa
Family
Salmaliaceae
Sapindaceae
Sapindaceae
Pedaliaceae
Dipterocarpaceae
Malvaceae
Malvaceae
Solanaceae
Solanaceae
Solanaceae
Tiliaceae
Myrtaceae
Caesalpinaceae
Bignoniaceae
Verbinaceae
Fabaceae
Malvaceae
Malvaceae
Rhamnaceae
Poaceae
Trapaceae
Trapaceae
Compositae
Fabaceae
Compositae
Verbinaceae
Apocyanaceae
Agavaceae
Rhamnaceae
Rhamanaceae
Compositae
Life form
Phanerophyte
Phanerophyte
Phanerophyte
Hemicryptophyte
Phanerophyte
Phanerophyte
Hemicryptophyte
Therophyte
Phanerophyte
Therophyte
Therophyte
Phanerophyte
Phanerophyte
Therophyte
Phanreophyte
Therophyte
Phanrophyte
Phanerophyte
Therophyte
Hemicryptophyte
Hydrophyte
Hemicryptophyte
Therophyte
Hemicryptophyte
Phanerophyte
Therophyte
Phanerophyte
Therophyte
Phanerophyte
Phanrophyte
Therophyte
Grasslands
244.
245.
246.
247.
248.
249.
250.
251.
Cenchurus ciliaris
Apluda mutica
Chloris dolichosta
Cyanodactylon sp
Dichanthium annulatum
Cyperus aristatus
Eragrostis japonica
Themeda ciliata
Poaceae
Poaceae
Poaceae
Poaceae
Poaceae
Cyperaceae
Poaceae
Cyperaceae
Hemicryptophyte
Hemicryptophyte
Hemicryptophyte
Geophyte
Hemicryptophyte
Therophyte
Therophyte
Hemicryptophyte
Endangered plants
AVII-5
ANNEXURE-VIII
LANDUSE PATTREN
Village Name
Dist - Raigarh
0-3km Tehisil - KHARSIA
Pamgarh
Jabalpur
Chhote Dumarpali
Bade Dumarpali
Jhinti Pali
Darramuda
Gindola
Bade Jampali
Kurru Bhantha
Binjkot
Bhagoradih
Naharpali
Chaple
Sendripali
Tehsil-Gharghoda
Tharakpur
Darama
Sub Total
3-7Km Tehsil - UDAIPUR
Baheramuda
Adukala
Tehsil-Kharsia
Kukricholi
Gurda
Tendumudi
Adpathra
Chodha
Banipathar
Bhalunara
Bhelwadih
Nawagaon
Kunkuni
Kukri Jhariya
Rajghata
Ranisagar
Karranara Alias Naurangpur
Rasiyamuda
Bendo Jhariya
Temtema
Kanmura
Amapali
Khairpali
Singhanpur
Saliha Bhantha
Raksapali
Mura
Lodhajhar
Bilaspur
Rajpur
Ful Bandhiya
Pandripani
Tehsil- Gharghoda
Bagchaba
Amapali
Jamchunwa
Jevri
Bagbuda
Sub Total
Area
Forest
land
Total
Irrigation
Land
UnIrrigated
land
Cultivable
waste land
Area not
avilable for
cultivation
268
350
198
349
174
260
262
218
303
536
43
591
434
151
0
0
0
0
0
0
0
0
0
59
0
27
0
0
18
12
3
4
10
3
10
13
7
14
1
21
4
3
135
171
128
188
111
181
193
144
181
327
20
412
258
87
54
107
43
94
15
18
30
12
54
24
3
39
99
17
61
60
24
63
38
58
29
49
61
112
19
92
73
44
361
339
4837
19
19
124
1
0
124
260
229
3025
54
68
731
27
23
833
481
650
128
173
9
7
199
323
86
97
59
50
214
449
378
299
289
208
244
258
165
923
63
218
229
424
90
163
195
228
131
164
178
164
336
384
317
207
72
164
258
37
0
2
0
0
0
22
0
0
0
0
0
0
157
0
0
0
0
0
0
11
0
0
0
0
21
0
0
0
0
0
0
1
4
3
0
5
0
20
9
6
3
1
1
0
1
6
0
0
0
0
5
20
0
11
0
18
0
91
268
196
89
186
125
85
192
111
332
27
128
124
100
36
101
129
95
92
113
139
117
250
240
247
133
57
97
171
41
53
81
111
69
46
93
29
39
363
9
56
88
72
20
42
43
61
17
33
15
37
43
52
46
12
9
29
46
45
128
99
98
30
34
44
32
15
208
18
28
14
94
33
20
22
66
22
18
13
10
38
72
24
30
6
20
41
427
491
80
481
99
10121
0
7
0
0
0
558
4
6
1
1
0
142
200
244
49
324
87
5497
178
191
20
123
4
2354
45
43
10
33
8
1570
AVIII-1
ANNEXURE-VIII
LANDUSE PATTREN
10
3
50
2
163
73
5
4
20
3
24
32
45
131
122
41
34
13
50
23
21
10
24
27
13
15
24
33
49
30
15
31
24
10
39
35
61
47
2000
20
83
55
22
31
8
23
36
53
17
56
20
47
28
17
62
9
49
16
18
15
15
14
26
78
55
5
13
39
14
50
15
11
72
21
28
85
16
109
14
22
73
84
93
64
1728
4813
31
42
133
3535
5938
AVIII-2
ANNEXURE-IX
DEMOGRAPHIC DETAILS
NAME
No_HH
Dist - Raigarh
0-3km Tehsil - KHARSIA
Pamgarh
214
Chhote Dumarpali
136
Bade Dumarpali
228
Kurru Bhantha
130
Gindola
130
Jabalpur
135
Jhinti Pali
73
Darramuda
172
Bade Jampali
106
Binjkot
196
Bhagoradih
40
Naharpali
278
Chaple
468
Sendripali
109
Tehsil-Gharghoda
Tharakpur
99
Darama
160
Sub Total
2674
3-7Km Tehsil - UDAIPUR
Baheramuda
172
Adukala
184
Tehsil-Kharsia
Kukricholi
46
Gurda
158
Tendumudi
131
Adpathra
122
Chodha
181
Banipathar
324
Bhalunara
115
Bhelwadih
200
Nawagaon
132
Kunkuni
295
Kukri Jhariya
23
Rajghata
185
Ranisagar
147
Karranara Alias Naurangpur
83
Rasiyamuda
14
Bendo Jhariya
91
Temtema
101
Kanmura
84
Amapali
59
Khairpali
126
Singhanpur
107
Saliha Bhantha
115
Raksapali
202
Mura
298
Lodhajhar
209
Bilaspur
289
Rajpur
105
Ful Bandhiya
130
Pandripani
139
Tehsil- Gharghoda
Bagchaba
117
Amapali
180
Jamchunwa
32
Jevri
183
Bagbuda
46
Sub Total
5125
TOT_P
TOT_M TOT_F
P_06
M_06
F_06
P_SC
M_SC
F_SC
P_ST
M_ST
F_ST
P_LIT
M_LIT
F_LIT
MAIN
MARG
TOT_W MAINW WORK_ MAINW WORK_ MARGW MARGW NON_W
ORK_P ORK_P
M
ORK_F
P
ORK_M ORK_F ORK_P
1029
669
1176
710
651
588
326
857
534
1006
172
1195
2366
566
529
325
564
344
306
292
160
437
259
511
89
591
1188
276
500
344
612
366
345
296
166
420
275
495
83
604
1178
290
165
107
186
123
120
108
57
129
85
172
27
198
356
91
99
47
100
67
53
60
32
67
36
92
18
96
162
44
66
60
86
56
67
48
25
62
49
80
9
102
194
47
36
212
164
30
106
36
23
14
75
53
65
115
119
14
19
102
75
14
47
19
12
6
34
22
37
50
63
9
17
110
89
16
59
17
11
8
41
31
28
65
56
5
176
170
240
169
326
199
178
42
151
435
73
610
195
5
92
81
103
84
149
94
86
21
76
228
33
302
101
2
84
89
137
85
177
105
92
21
75
207
40
308
94
3
675
442
839
463
453
371
207
536
398
660
113
740
1790
420
387
250
425
249
230
209
113
318
213
374
60
432
994
218
288
192
414
214
223
162
94
218
185
286
53
308
796
202
570
249
425
271
398
312
143
382
260
519
81
667
982
280
443
215
376
23
296
257
62
261
189
445
40
404
549
143
253
149
255
20
166
146
53
213
142
268
37
251
463
122
190
66
121
3
130
111
9
48
47
177
3
153
86
21
127
34
49
248
102
55
81
121
71
74
41
263
433
137
40
22
25
159
19
17
38
21
15
18
7
79
187
30
87
12
24
89
83
38
43
100
56
56
34
184
246
107
459
420
751
439
253
276
183
475
274
487
91
528
1384
286
522
744
13111
253
363
6487
269
381
6624
106
145
2175
58
63
1094
48
82
1081
60
42
1164
30
25
564
30
17
600
203
520
3692
100
245
1797
103
275
1895
366
408
8881
181
237
4890
185
171
3991
316
450
6305
247
248
4198
133
224
2895
114
24
1303
69
202
2107
21
7
705
48
195
1402
206
294
6806
852
826
426
394
426
432
174
132
87
66
87
66
5
8
2
5
3
3
797
404
396
190
401
214
407
513
262
281
145
232
346
363
299
363
229
218
70
145
47
0
17
0
30
0
506
463
220
808
534
492
975
1453
540
1012
710
1593
136
898
755
395
71
411
494
440
247
632
545
560
949
1325
1176
1236
416
630
697
107
404
246
243
471
749
267
518
358
793
87
451
361
190
33
202
238
225
115
322
251
304
479
677
590
620
212
318
351
113
404
288
249
504
704
273
494
352
800
49
447
394
205
38
209
256
215
132
310
294
256
470
648
586
616
204
312
346
38
140
101
80
195
324
108
186
141
276
11
167
156
55
9
74
88
74
28
114
96
85
132
192
140
179
51
106
88
20
75
44
45
97
168
58
100
72
137
3
91
75
26
4
40
39
40
17
67
39
35
68
107
75
93
29
50
42
18
65
57
35
98
156
50
86
69
139
8
76
81
29
5
34
49
34
11
47
57
50
64
85
65
86
22
56
46
6
48
13
46
118
118
83
21
91
272
2
19
64
37
8
101
56
5
0
23
91
119
219
52
238
292
10
316
104
4
19
6
23
59
60
35
11
47
141
2
12
29
16
3
52
21
3
0
11
38
64
107
28
118
155
3
167
52
2
29
7
23
59
58
48
10
44
131
0
7
35
21
5
49
35
2
0
12
53
55
112
24
120
137
7
149
52
190
527
398
394
551
350
275
37
257
870
49
242
138
257
48
99
105
86
61
0
262
280
292
184
94
286
40
185
146
92
267
184
192
261
177
142
18
131
431
37
115
62
127
23
45
50
46
31
0
123
147
153
93
50
137
21
93
74
98
260
214
202
290
173
133
19
126
439
12
127
76
130
25
54
55
40
30
0
139
133
139
91
44
149
19
92
72
131
537
377
233
651
729
311
683
396
789
110
432
354
239
44
267
307
265
186
446
378
405
703
922
806
924
327
444
409
78
316
195
163
345
465
180
392
254
502
78
298
210
144
26
145
173
156
90
242
187
260
377
518
462
495
175
256
236
53
221
182
70
306
264
131
291
142
287
32
134
144
95
18
122
134
109
96
204
191
145
326
404
344
429
152
188
173
116
438
288
268
479
801
236
366
360
794
68
496
301
129
22
117
247
191
76
192
277
244
397
606
440
423
206
284
194
27
153
267
89
442
784
232
309
295
638
35
493
276
106
21
106
145
132
67
145
118
149
246
247
381
346
200
149
182
14
124
143
70
238
437
141
193
192
406
20
244
188
95
17
95
131
120
59
133
104
86
170
181
244
284
106
124
168
13
29
124
19
204
347
91
116
103
232
15
249
88
11
4
11
14
12
8
12
14
63
76
66
137
62
94
25
14
89
285
21
179
37
17
4
57
65
156
33
3
25
23
1
11
102
59
9
47
159
95
151
359
59
77
6
135
12
45
92
0
62
10
10
1
54
7
55
16
0
13
3
0
3
12
5
1
18
42
38
81
171
16
17
3
25
12
44
193
21
117
27
7
3
3
58
101
17
3
12
20
1
8
90
54
8
29
117
57
70
188
43
60
3
110
0
104
370
246
224
496
652
304
646
350
799
68
402
454
266
49
294
247
249
171
440
268
316
552
719
736
813
210
346
503
530
772
145
789
205
24469
255
380
76
391
89
12193
275
392
69
398
116
12276
85
117
18
114
28
4102
43
51
11
58
12
2084
42
66
7
56
16
2018
61
25
0
97
65
2833
30
12
0
43
31
1409
31
13
0
54
34
1424
368
555
145
416
8
9396
178
271
76
204
3
4640
190
284
69
212
5
4756
322
458
97
511
163
15276
187
287
56
291
73
8855
135
171
41
220
90
6421
291
464
89
433
121
11163
291
392
66
319
121
8631
152
202
41
195
54
5618
139
190
25
124
67
3013
0
72
23
114
0
2532
0
41
9
32
0
911
0
31
14
82
0
1621
239
308
56
356
84
13306
AIX-1
ANNEXURE-IX
DEMOGRAPHIC DETAILS
69
111
153
83
114
37
60
89
158
112
81
38
77
476
361
29
31
11
41
241
195
10
15
6
36
235
166
19
16
5
1268
41
72
70
48
144
66
205
60
205
38
50
53
164
126
26
120
49
35
57
84
34
51
26
61
115
37
1138
39
60
60
59
166
65
217
70
203
50
36
45
158
121
23
93
36
35
40
65
43
45
33
80
97
44
1806
9
149
39
29
279
231
601
43
585
14
48
110
170
76
78
174
84
75
57
232
62
43
60
192
189
56
890
0
71
19
12
121
124
309
19
301
7
24
58
90
40
34
86
39
38
27
114
27
22
33
101
95
30
916
9
78
20
17
158
107
292
24
284
7
24
52
80
36
44
88
45
37
30
118
35
21
27
91
94
26
33
80
28
51
120
42
51
145
45
70
23
62
122
24
58
109
55
54
99
113
110
99
44
251
26
28
48
52
58
48
18
124
195
90
211
4918
8096
181
99
198
4650
7749
163
135
210
7809
11806
90
62
115
3908
5881
432
49
684
1053
765
169
223
25
341
503
393
85
209
24
343
550
372
84
405
598
1059
589
490
285
235
343
668
366
322
171
170
255
391
223
168
114
346
234
506
529
615
241
136
232
405
367
439
148
108
198
390
285
276
121
28
34
15
82
163
27
210
2
101
162
176
93
82
2
69
64
21
11
128
0
32
98
155
82
327
675
1169
730
432
202
753
291
134
296
274
307
284
134
265
500
0
24
149
520
152
134
498
221
112
275
48
39
151
149
123
243
230
396
136
73
140
126
153
139
65
123
253
0
15
79
253
76
69
244
111
54
141
22
23
73
71
60
126
108
357
155
61
156
148
154
145
69
142
247
0
9
70
267
76
65
254
110
58
134
26
16
78
78
63
117
122
12234
242
516
387
249
1166
447
1367
455
1510
360
363
329
754
593
143
710
299
308
473
588
390
447
324
688
889
470
6919
116
275
247
131
685
240
856
236
904
199
207
214
500
379
93
438
174
181
280
329
221
254
200
395
465
261
5315
126
241
140
118
481
207
511
219
606
161
156
115
254
214
50
272
125
127
193
259
169
193
124
293
424
209
5512
177
252
396
230
687
213
992
313
827
286
274
284
755
594
153
747
226
330
341
258
250
361
195
272
533
221
5346
104
188
372
202
477
162
407
66
705
184
9
122
385
368
68
487
66
117
209
252
227
282
171
197
426
211
4477
61
137
207
115
398
140
312
61
577
122
6
114
300
292
43
268
56
113
161
221
144
172
131
179
254
146
869
43
51
165
87
79
22
95
5
128
62
3
8
85
76
25
219
10
4
48
31
83
110
40
18
172
65
166
73
64
24
28
210
51
585
247
122
102
265
162
370
226
85
260
160
213
132
6
23
79
24
75
107
10
79
27
28
9
0
116
19
297
115
41
31
125
30
88
20
36
107
77
55
38
5
15
16
10
46
79
6
46
36
15
28
94
32
288
132
81
71
140
132
282
206
49
153
83
158
94
1
8
63
14
29
28
4
29
26
51
61
52
51
26
127
250
196
165
188
534
0
136
429
123
100
80
96
252
0
70
220
127
96
85
92
282
0
66
209
372
746
232
458
1053
256
371
980
217
446
142
273
615
132
205
584
155
300
90
185
438
124
166
396
297
682
211
469
898
221
336
734
297
483
188
361
564
185
332
357
153
310
98
220
327
101
170
328
144
173
90
141
237
84
162
29
0
199
23
108
334
36
4
377
0
58
13
19
151
9
1
102
0
141
10
89
183
27
3
275
218
573
167
330
794
191
267
977
73
73
95
3901
5925
1173
200
1201
13930
27018
582
96
598
6916
13353
591
104
603
7014
13665
1122
619
1725
38061
62218
670
375
1062
22225
35970
452
244
663
15836
26248
955
565
1307
24825
42293
599
346
803
18052
30881
436
245
531
13504
22017
163
101
272
4548
8864
356
219
504
6773
11412
111
62
226
2516
4132
245
157
278
4257
7280
1104
575
1558
36089
56201
87
11876
167
462
345
209
1209
440
1641
423
1527
251
324
305
822
665
149
602
303
241
372
667
304
283
319
721
754
419
AIX-2
ANNEXURE-X
R&R PLAN
Government of Chhattisgarh
Ministry of Commerce & Industries
S.No. F11-1 / 2008 / 11 / (6)
Raipur, Dated
To:
Commissioner of Industries,
LIC Commercial Complex,
Pandari, Raipur.
Subject:
Reference:
The State Government hereby accords its in principal consent to M/S S.K.S. Ispat & Power
Limited for acquisition of 258.521 hectare personal land situated at Bade Jampani,
Darramuda & Binjkot villages (P.H.N. -14 Tehsil Kharasiya, Disrict Raigarh) for the
purpose of installation of 600 MW Power Plant under Land Acquisition Act, 1894.
The list of the account holders of the said land is attached in Appendix-1.
(S.K. Behar)
Secretary
Government of Chhattisgarh
Department of Commerce & Industries
S.No. F11-1 / 2008 / 11 / (6)
AX-1
Rehabilitation Scheme
Presented under Model Rehabilitation Scheme (as amended -2007) of Government of Chhattisgarh
For
Rehabilitation of displaced people affected due to land acquisition
For the proposed Power Plant at
INDEX
Chapter List as per points prescribed in Appendix Two of the
No.
Model Rehabilitation Scheme of the Government
1.
Introduction
2.
Short profile of the development project along with
purpose of the scheme, basic concept and time schedule
of implementation
3.
Drawing of the Project Area along with details of the
surroundings
4.
Details of direct and indirect benefits of the scheme
5.
Area and type of land (Whether Government, Forest,
Government Revenue, Service Land or Personal Land )
of the project as per land records
6.
Details of existing agricultural, business and other
economic activities in the area
7.
Details of the owner and lease holders of the proposed
land for acquisition
8.
Effect on Environment (Zoological as well as effect on
forest, water and atmosphere) due to implementation of
the project
9.
Action plan for implementation of Model Rehabilitation
Policy for providing employment to the people affected
due to land acquisition
a. Employment & other facilities
b. Compensation for proposed land, buildings, trees
& other movable & immovable assets
10.
Action plan for increasing proficiency of the people
eligible for employment due to land acquisition for the
project
11.
Details of the Social and Welfare activities to be
undertaken by the company in the area
12.
2.1 Clear Statement on necessity of Migration
2.2 Details of the migrated families
2.3 Action-plan for rehabilitation of the migrated people
13.
2.4 Details of such persons, for whom re-migration is
assessed along with clear statement for their migration
Page
No.
4
5
6
7
8
9
10
11
12-14
15-16
17-18
19
20
CHAPTER-1
INTRODUCTION
S.K.S. Ispat and Power Limited, Raipur is a well-established popular company of
the state. At present its area of function is our State. It is a well-known Public
Limited Company of the area engaged in steel production.
Looking into positive industrial policy of the Government of Chhattisgarh, the
peaceful and cordial and favorable industrial environment, the S.K.S. Ispat and
Power Limited, Raipur has decided to expand its function by installation of a
Power Plant. In this connection, the company has identified the site and executed
an MOU on 24.01.2007 with Government of Chhattisgarh for investment of
Rs.2400 Crore.
The existing plant of the company is situated at village Siltara in Raipur District.
The company has identified the proposed site for extension of their project and
installation of steel plant in Raigarh District. The proposed land at Badejanpali,
Darramuda and Binjkot villages is situated 1.20 K.M. away from the State
Highway-200. The company also proposes to install an integrated power plant in
near future. The company for requirement of land surrounding the plant area has
submitted this proposal. The project will contribute in industrial development of
the area as well as facilitate the local people to participate in the main stream of the
development and uplift the economic, educational and social status of their family.
S.K.S. Ispat and Power Limited, Raipur has identified the site with a view to
minimize the use of Government & Personal land and in terms of the Model
Rehabilitation Policy (As amended-2007) of the Government of Chhattisgarh.
The basic concept of the proposed Rehabilitation Scheme is to uplift the living
standard of the affected account holders and their dependents as per Government
policy. Special emphases have been given on optimum utilization of the land and
develop the land as per requirements of the project. To protect the area from
adverse effects on its zoology as well as atmosphere and to promote greenery, the
local resources will be utilized with best efforts and all requirements regarding
waste material management, residential accommodation, and water resources will
be fulfilled. S.K.S. Ispat and Power Limited, Raipur is committed to wholeheartedly cooperate in all social welfare activities as and when it requires.
CHAPTER-2
CHAPTER-3
CHAPTER-4
CHAPTER-5
CHAPTER-6
CHAPTER-7
S.K.S. Ispat and Power Limited Company, Raipur has undertaken a study on the
basis of Land Record, Poverty Line and Initial Regional Survey for
identification of the affected people due to installation of the project. The
details are given below:
S.No.
Bade Jampali,
Darramuda,
Binjkot
District- Raigarh
Proposed
area of land
acquisition
258.521
Hectare
Numbers of
affected
account
holders
Details of
account
holders and
their
dependents
238 account As attached
holders (310 in Appendixdependent
1
families)
10
CHAPTER-8
Effect on Environment
(Zoological as well as effect on forest, water and atmosphere) due
11
CHAPTER-9
ii.
4.
For trees
14
CHAPTER-10
16
CHAPTER-11
11.5
Self-help Groups of Women
Women are the backbone of their family and they must be motivated to earn
themselves and gain confidence. Making of Self-help groups for such
women may be proved to be an effective step in this direction. Company
17
will help in making of such groups and provide necessary assistance in such
a manner that they may be able to earn money through making of Papad and
Pickles, Tailoring, embroidery and other activities.
11.6
Agriculture Development
At present, most of the farmers of the affected area are engaged in traditional
single crop activities. It leads them to do outside work / job during
remaining 9 months of the year. The company will make arrangements for
tube well irrigation and sprinkle irrigation with the help of modern
technology to increase the output and enable the farmers to grow pulses, oil
seeds and other cash crops.
11.7
Adequate use of Pond Water
At present, the pond water is being used only during rainy season to grow
crops. Company will develop the water storage areas to facilitate irrigation
throughout the year. The same quantity of water may be utilized for more
then a single crop by using new technology. The Ground Water Level may
also be increased. Company will provide necessary training to the farmers in
this direction.
11.8
Medical Camp
The company will organize Medical Camps to provide artificial parts of the
body for physically handicapped persons, eye examination, diabetes test, etc.
18
CHAPTER-12
19
CHAPTER-13
20
Affidavit
S.K.S. Ispat and Power Limited Company, Raipur hereby declares that it will
fulfill all social obligations as enumerated in various provisions, paragraphs and
sections of the Model Rehabilitation Policy (as amended in 2007).
S.K.S. Ispat and Power Limited Company, Raipur will implement the scheme
regarding development of the living standard of the people located in and
around the area as well as account holders and their dependent families.
S.K.S. Ispat and Power Limited Company, Raipur will give special attention for
protection of biological entity of the affected area and promotion of the
greenery.
S.K.S. Ispat and Power Limited Company, Raipur will give special emphases on
optimum utilization of the land and develop the land as per requirements of the
project and in a manner to minimize its needs.
(K. Hariharan)
Authorized Representative
DECLARATION
I, K. Hariharan, authorized representative of S.K.S. Ispat and Power Limited
Company, Raipur hereby undertake in the presence of witness without any
pressure that the company will follow all paragraphs and sections of the Model
Rehabilitation Policy (as amended in 2007).
(K. Hariharan)
Authorized Representative
S.K.S. Ispat and Power Limited Company
21
22