Sr. no
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32

33
34
35
36
37
38
39
40
41
42

TDBFP Isolation &Normalisation


TDBFP Isolation
Check 11Kv Booster pump breaker is racked out from 11kv unit switchgear
check AC LO Pump 1 is stopped
check AC LO Pump 2 is stopped
Check DC LO Pump is stopped
Check OVEF 1 is stopped
Check OVEF 2 is stopped
Check Discharge Valve of LO Pump 1 is closed
Check Discharge Valve of LO Pump 2 is closed
Check Discharge Valve of DC LO Pump is closed
Check Inlet MIV of accumulators are closed
Check LO cooler water supply inlet MIV is closed
Check LO cooler water outlet MIV is closed
Isolate AC LO pump 1 from Emergency MCC
Isolate AC LO pump 2 from Emergency MCC
Isolate DC LO pump DC DB
Isolate OVEF 1 from Turbine MCC
Isolate OVEF2 from Turbine MCC
Check Extraction Inlet steam MOV is closed
Check Drain of Extraction Inlet steam MOV is opened
Check CRH to TDBFP Inlet steam MOV is closed
Check Drain of CRH to TDBFP Inlet steam MOV is opened
Check TDBFP Exhaust Steam MOV is Closed
Check Gland Steam Supply line MIVs are closed
Check Gland Steam supply line Drain is opened
Check Gland Steam Return Line MIVs is closed
Check Gland Steam Return line Drain is opened
Isolate CRH to TDBFP Inlet Steam MOV power from Turbine EER
Isolate Extraction Inlet Steam MOV power from Turbine EER
Isolate Exhaust Steam MOV power fromTurbine EER
Check Booster pump-A Inlet MOV is Closed
Check Booster pump-B Inlet MOV is Closed
Check BFP-A Discharge MOV is Closed
Check BFP-B Discharge MOV is Closed
check RH spray MOV closed
Check RH spray Drain opened
Check BFP-A minimum R/C MOV is closed
Check BFP -A minimum R/C CV is closed
Check BFP-A minimum R/C inlet MIV is closed
Check BFP-A minimum R/C MOV power supply is isolated
Check BFP-B minimum R/C MOV is closed
Check BFP -B minimum R/C CV is closed
Check BFP-B minimum R/C inlet MIV is closed

Check BFP-B minimum R/C MOV power supply is isolated


Isolate BP-A Inlet MOV power supply from Turbine EER
Isolate BP-B Inlet MOV power supply from Turbine EER
Isolate BFP-A Discharge MOV power supply from Turbine EER
Isolate BFP-B Discharge MOV power supply from Turbine EER
Isolate RH spray MOVs power supply from Turbine EER
Isolate BFP-A minimum R/C MOVpower supply from Turbine EER
Isolate BFP-B minimum R/C MOV power supply from Turbine EER
Check Seal water I/L MIV of BP-A is closed
Check Seal water I/L MIV of BP-B is closed
Check Seal water I/L valves of BFP-A are closed
Check Seal water O/L valves of BFP-A are closed
Check Seal water I/L valves of BFP-B are closed
Check Seal water O/L valves of BFP-B are closed
TDBFP Normalisation
Check Seal water I/L valves of BFP-B are opened
Check Seal water O/L valves of BFP-B are opened
Check Seal water I/L MIV of BP-A is opened
Check Seal water I/L MIV of BP-B is opened
Check Seal water I/L valves of BFP-A are opened
Check Seal water O/L valves of BFP-A are opened
Normalise BP-A Inlet MOV power supply from Turbine EER
Normalise BP-B Inlet MOV power supply from Turbine EER
Normalise BFP-A Discharge MOV power supply from Turbine EER
Normalise BFP-B Discharge MOV power supply from Turbine EER
Normalise RH spray MOV power supply from Turbine EER
Normalise BFP-A minimum R/C MOVpower supply from Turbine EER
Normalise BFP-B minimum R/C MOV power supply from Turbine EER
Check BFP-A minimum R/C inlet MIV is opened
Check BFP-A minimum R/C MOV power supply is normalised
Check BFP-B minimum R/C inlet MIV is opened
Check BFP-B minimum R/C MOV power supply is normalised
Check Booster pump-A Inlet MOV is opened
Check Booster pump-B Inlet MOV is opened
Check BFP-A Discharge MOV is opened
Check BFP-B Discharge MOV is opened
Check RH spray Drain is closed
Check Gland Steam Supply line MIVs are opened
Check Gland Steam supply line Drain is closed
Check Gland Steam Return Line MIVs is opened
Check Gland Steam Return line Drain is closed
Normalise CRH to TDBFP Inlet Steam MOV power from Turbine EER
Normalise Extraction Inlet Steam MOV power from Turbine EER
Normalise Exhaust Steam MOV power fromTurbine EER
Check Drain of Extraction Inlet steam MOV is closed
Check Drain of CRH to TDBFP Inlet steam MOV is closed
Check TDBFP Exhaust Steam MOV is opened

Check Discharge Valve of LO Pump 1 is opened


Check Discharge Valve of LO Pump 2 is opened
Check Inlet MIV of accumulators are opened
Check LO cooler water supply inlet MIV is opened
Check LO cooler water outlet MIV is opened
Normalise AC LO pump 1 from Emergency MCC
Normalise AC LO pump 2 from Emergency MCC
Normalise OVEF 1 from Turbine MCC
Normalise OVEF2 from Turbine MCC
Normalise power supply of Booster pump by racking in 11kv breaker