ISSUES ,KMRI

SL NO
1
2
3
4
5
6
7
8
9
10
11
12

DISCRIPTION
CT fan approch we need 3 ladder but supplied only 2 ladders
5M cube fines shortage
Disdribution pipes 3 damaged
Acw suction piping eccentric reducer 2 no's not send
Acw discharge piping concentric reducer 2 no's not send
Cooling water inlet and outlet for alternator not as per drawing
because alternator design not matching our drawing
Cooling water inlet and outlet for oil cooler as per our drawing pipi
size 4" but oil cooler inlet&outlet stups 3"
Acw recerculation line reducers 4" to 3" not supplied ( 3 no's)
Acw and mcw supply and return piping as per drawing undergroud but
we maked overground
Mcw suction line eccentric reducer not supplied
Mcw discharge line concentric reducer not supplied
Mcw return line connecting the cooling tower spool pipe not supplied
by paltech

13

CT makeup discharge line 2 nrv valves wrong supplied,We need 4'


NRV but supplied 6" nrv

14

CT makeup to cooling tower 3 butterfly valves wrong supplied,we


need 3" valve 3 no's but supplied 6" valves

15

CT makeup suction line strainer foundation not mentioned the civil


drawing

16

Raw water suction and discharge line to clarifier tank piping supports
details not available

18

WTP uf suction and return pipes and drain pipes (SS) and fittings are
not supplied
WTP pressure releif valve 2 no's not working

19

WTP uf supply line solinoid valve and air line 2 filtters are not supplied

20

WTP Edi plc panel not in line as per reschedule planing to take all
instruments from dcs

21

WTP Hp pumps 2 no's broken and one dosing pump missing

22

WTP all pipings and skids found damage condition ,Plc inside all
terminals found damage condition

17

23
24

Clarifier and clarifier storage tank & uf tank also no provisions gived
for level gauge and transmeter
Guardpond piping footvalves 2 no's not supplied by doosion

25
26

Total epc Air lines all pipes and fittings not supplied
Air receiver pressure releif valve missing

27

Instrument and service air piping routing drawing not available

28
29
30

Bucket elevator suppords not concider on drawing


Bucket elevator top conopy not provided the drawing
Bucket elevator sump pump with pipings not supplied

31

Submerged ash conveyor power cylinder solinoid valve not supplied

32

Piperack inbitween deaerator floor to tg building piperack modified


because fouling with roof of condrol room

34
35

All pressure pipes are modified including main steam line because the
piperack modified
DSH 2 and 3 not supplied
Auxilary steam header fouling with bfp suction line

36

Ejector approch platform not available ,Ejector elevation 3 mtr

37

Cep one pump wrong supply

33

REMARKS

Site fabrication
Site fabricated
Local purchased

we maked reducer 4 no's and


completed

Site fabricated
Site fabricated
Site fabricated
We Maked reducers and
completed
we used 3" valves from
firefighting system
we maked suit&site
Suit and site
localy purchased

localy purchased

One hp pump purchased in local


Rectified at site

localy purchased

localy purchased
localy purchased
Suit and site
we maked suit&site

Modified suit and site