Sei sulla pagina 1di 3

SPH - JV

GREEN LINE ELEVATED & AT-GRADE


Ref: M009-SPH-COM-LTR-00377
Date: 2nd September 2015
TO:

Qatar Railways Company


Contracts and Procurement
Qatar Rail Tower, 14th Floor
P.O. Box 29988
Doha, Qatar

For the attention of: The Engineers Assistant


Mr. Jean-Christophe Elis
Contract Title:

Design & Build Package: Green Line Elevated & At Grade

Contract No.:

RTC/082/2013

Subject:

Application for Engineers SONO for Payment Event Achievement


(Batch 02) - Interim Payment Application No.07.

Dear Sir,
With reference to the above, we herewith enclose Milestone Definition sheets together with
all the substantiation/backup documents for the following Payment Events in order to obtain
Engineers SONO for Payment Event Achievement (Batch 02) as a part of Interim Payment
Application No.07
Documen
t No.

12

13

Sectio
n No.

Payment
Event
Contract
Date

Feb-15

Aug-15

Payment
Event No.

Description

PLMS.19.02

Provision and Completion of


Contractor's Principal and Site Offices
including Civil Defence Certification at
the MLPA Site.

8,606,506.
00

PLMS.13.04

Provision of Site Services - including


access to Site, Site logistics, security,
including provisions of power supplies
and water, sewage disposal, fencing,
utilities connections - including
approval from all statutory authorities.

1,832,467.00

SBG-PORR-HBK JV
Phone: (+974) 44 57 0300

Mailing Address:

Fax: (+974) 44 57 0301 / 302

P.O.Box:207 471, Doha State of Qatar

Amount

Page 1 of 3

SPH - JV
GREEN LINE ELEVATED & AT-GRADE

14

May-15

PLMS.17.04

Provision of all IT requirements at the


Employer/Engineer's Principal Offices
including IT, telecommunication and
the like.
Provision of Employer/Engineer's
Principal Offices at the MLPA site
including all fixtures and furniture and
Civil Defence certification.
Engineers Confirmation of satisfactory
implementation of all Specified Plans,
at 3 months after PLMS.03

15

Feb-15

PLMS.17.03

16

May-15

PLMS.04

17

Aug-15

PLMS.05

Engineers Confirmation of satisfactory


implementation of all Specified Plans,
at 3 months after PLMS.04

18

Feb-15

STMS.08

Completion of all station piers, pier


caps and installation of bearings to the
satisfaction of the Engineer

STMS.09.06

Completion of Concrete support


beams beneath Platform slab level and
between Gridlines 1 - 5 including
formwork, rebar and concrete works to
the satisfaction of the Engineer.

19

Mar-15

1,829,227.
89

20

Apr-15

STMS.09.07

Completion of Concrete support


beams beneath Platform slab level and
between Gridlines 5 - 10 including
formwork, rebar and concrete works to
the satisfaction of the Engineer.

21

10

May-15

ELMS.012.05

Complete superstructure works up to


and including bearings between
chainages 12+932 - 13+100

3,778,582.
33
1,829,227.
89

1,829,228

1,213,171.
00

2,537,006.00

2,537,006.00

Yours faithfully
For and on behalf of SPH-JV,

Hussein El Saied
Project Director

Andrew Wood
Commercial Director

SBG-PORR-HBK JV
Phone: (+974) 44 57 0300

Mailing Address:

Page 2 of 3

Fax: (+974) 44 57 0301 / 302

P.O.Box:207 471, Doha State of Qatar

161,917.
00

SPH - JV
GREEN LINE ELEVATED & AT-GRADE

Received by:
Name:
Sign:
Date: