TITLE
INTRODUCTION
OBJECTIVE
WORK PROGRESS
TAKING OFF
BILL OF QUANTITY
CONCLUSION
APPENDICES
BUKU KADAR HARGA JKR
INTRODUCTION
Civil Engineering Quantities (ECM442) is one of the main subjects in civil
engineering courses. We need to look for architectural and engineering (detailing)
drawings for a single storey building. Therefore, we have chosen a single storey
terrace house in Perlis as our project plan. There are two main aspects need to be
prepared for this project, that is taking off and bill of quantities.
The works that need to be undertaken are excavation, filling, lean concrete,
concrete, reinforcement and formwork. Besides, we also must calculate the works
for basic structure of this project such as foundation, beam, slab and column.
Taking off must be prepared as measuring from drawings and recording all
dimensions in recognized form. After that, preparation bill of quantities need to be
prepared according to the items by stating the quantities and brief descriptions of
work to be carried out with it respective quantities and unit cost of the building.
Objectives of Bill of Quantities
The objectives of Bill of Quantities are to:
a)
performed to enable
bids to be prepared efficiently and accurately.
b)
c)
Works executed.
d)
additional works
instructed by the Clients.
e)
TASK
For this session, each group will discuss about:
Excavation
Filling
Lean concrete ( thickness of lean concrete at 50mm)
Concrete
Reinforcement
Formwork
You are required to calculate the works for basic structure of this
showroom such as:
Foundation
Beam
Slab
Column
The list of principal quantities being the main components of the works, with their
approximate estimated quantities, so that tenderers obtain an overall picture of the
general scale and character of the proposed works at the outset.
A list of principal quantities relating to a reservoir as follows:
NO.
1
TASK
GENERAL ITEMS
Provisional Sums
Prime Cost Items
FOUNDATION
Excavation
Concrete
Formwork
Steel Reinforcement
COLUMN
Concrete
Formwork
Steel Reinforcement
BEAM
Concrete
Formwork
Steel Reinforcement
SLAB
Concrete
Steel Reinforcement
COST
SECTION B: PREAMBLES
The preamble in a civil engineering bill of quantities is to indicate to tendering
contractors whether methods measurement other than the CESMM have been used
for any part of works and whether any modification have been made in applying the
CESMM to meet special needs where there are important practical reasons for
adopting a different procedure
a)
Taking Off
a list of materials with quantities and types (such as specific grades of steel) that are
required to build a designed structure or item. This list is generated by analysis of
a blueprint or other design document. The list of required material of construction is
sometimes referred to as the Material Take off List (MTOL).
b)
Bill of Quantities
Is a document used in tendering in the construction industry in which materials, parts,
and labour (and their costs) are itemized. It also (ideally) details the terms and conditions
of the construction or repair contract and itemises all work to enable a contractor to price
the work for which he or she is bidding.
c)
Foundation
The lowest and support layer of a structure. Foundations are generally divided into two
categories: shallow foundations and deep foundations
d)
Beam
A structural element that is capable of withstanding load primarily by resisting bending.
The bending force induced into the material of the beam as a result of the external loads,
own weight, span and external reactions to these loads is called a bending moment.
e)
Slab
A common structural element of modern buildings. Horizontal slabs of steel reinforced
concrete, typically between 100 and 500 millimeters thick, are most often used to
construct floors and ceilings, while thinner slabs are also used for exterior paving.
f)
Column
Is a structural element that transmits, through compression, the weight of the structure
above to other structural elements below. In other words, a column is a compression
member. The term column applies especially to a large round support with a capital and
base
g)
Excavation
Common excavation is the excavation of soil materials from within the
contract limits; however, this excavation is not limited to soil materials
and may include existing HMA pavement. This HMA pavement includes
HMA mixtures, crushed stone, bricks, cinders, etc. If the material is
indicated on the plans and is not a concrete pavement or another defined
excavation, then the material is considered common excavation.
h)
Concrete
Concrete is a composite material composed of coarse granular material
(the aggregate or filler) embedded in a hard matrix of material (the cement or binder)
that fills the space among the aggregate particles and glues them together.
i)
Lean Concrete
Lean concrete does not contain many of the high-density rock materials that regular
concrete does. Lean concrete often consists of reclaimed concrete materials, ash, and
discarded sand. It's a cheaper alternative to regular concrete.
j)
Formwork
Formwork is the term given to either temporary or permanent molds into which concrete or similar
materials are poured. In the context of concrete construction the falsework supports
NO
ELEMENT
UNIT
1.
Work
Excavation
Formwork
Concrete work
Reinforcement
Filling
Cost , Rate
m3
m2
m3
kg
m3
Ringgit Malaysia
Material
Cement
Aggregate
Water
Nails
Timber
Lean concrete
m3
m3
m3
kg
m2
m3
General
Density
Labour
Machinery
Site
Prime cost
Provisional sum
Kg/m3
No.
Per day
No.
Ringgit Malaysia
Ringgit Malaysia
2.
3.
UNIT OF MEASUREMENT
A list of the various classes of labor, material and plant for which daywork
rates or prices are to be inserted by the tenderer.
Provision for payment at the rates and prices and prices and percentage
variations contained in the current federation schedules of daywork.
The insertion of provisional sums in the bill of quantities for work executed on
a daywork basis comprising separate items for labor, materials, plants etc.
METHODOLOGY/PROCESS
ELEMENT
Foundations
Columns
Person in Charge
Mohd Fawwaz bin Md Isa
Muhammad Zulfaqur bin Abd
Beams
Manab
Muhammad Asyraf bin Roslan
Slabs
STANDARD
Authority Cooperated:
SCOPE OF WORKS
In this project, we only do the taking off and estimation cost for a single
house only. To accomplish this project, we have divided the works equally to the
team members so that the works can be done easily and efficiently without any
problems occurred. The team members and their division of works are :
Name
Muhammad Asyraf bin Roslan
Mohd Fawwaz bin Md Isa
Mohd Syafiq Firdaus bin Zolkefli
Muhammad Zulfaqur bin Abd Manab
Mohd Nor Aizat bin Nor Azizi
Scope of Work
Ground Beam & Estimation
Foundation and Estimation
Roof Beam and Estimation
Colum and Estimation
Slam and Estimation
Taking off
FOUNDATION
No.
Dimension
Quantit
Description
Unit
y
Footing 1 (F1)
EXCAVATION WORK
15
15
15
15
15
0.60
0.60
0.75
a) Footing excavation
thickness = 1200 450 = 750
4.05
0.3
0.95
3.90
0.6
0.6
5.4
0.6
0.6
0.25
0.25
0.25
0.8
M3
b) Backfilling of soil
( 0.6 x 0.6 ) (0.25 x 0.25) = 0.30m2
M2
d) Concrete
i) concrete to pad footing
1.35
+
ii) concrete to column stump
0.75
2.10
M3
Footing 2 (F2)
EXCAVATION WORK
0.90
0.90
0.75
0.72
0.90
a) Footing excavation
thickness = 1200 450 = 750
4.86
M3
b) Backfilling of soil
( 0.9 x 0.9 ) (0.3 x 0.3) = 0.72m2
5.18
M3
0.9
0.9
0.9
0.9
0.30
0.3
0.3
0.8
6.48
M2
d) Concrete
i) concrete to pad footing
1.94
+
ii) concrete to column stump
0.58
2.52
M3
15
0.6
0.6
5.4
0.9
0.9
6.48
M2
11.88
M2
0.6
0.6
0.75
4.05
0.9
0.9
0.75
1200
0.150 - topsoil
1.05
0.05 + hardcore
1.10
4.86
8.91
M3
15
0.6
0.6
0.45
2.43
0.9
0.9
0.45
2.92
5.34
M3
CONCRETE WORK
Concrete grade 1:1.5:3 (G30)
-20 mm aggregate for footings
0.6
0.6
0.25
1.35
0.9
0.9
0.3
1.94
M3
3.29
M3
Concrete grade 1:1.5:3(G30)
-20 mm aggregate for stumps
15
0.15
0.15
0.5
0.17
Footing 1 (F1)
1.200
0.450 ground beam
0.750
0.250 footing
0.500
Footing 2 (F2)
1.200
M3
0.3
0.3
0.45
M3
FORMWORK
Rough surface for footings
15/
4
0.6
0.25
8/4
0.9
0.3
8.64
17.64
M2
Rough surface formwork
for side of stump
15/
4
0.75
0.15
6.75
0.75
0.3
7.2
13.95
M2
8/4
REINFORCEMENT
Reinforcement For Footing
Footing 600 x 600 x 250
Length of one steel bar
0.600
0.100 cover
0.500
0.066 + bends 5.5d @ 5.5/0.012
0.566 ~ 0.57
0.57
42.75
15/
5
REINFORCEMENT
Reinforcement For Footing
Footing 900 x 900 x 300
Length of one steel bar
0.900
0.100 cover
0.800
0.066 + bends 5.5d @ 5.5/0.012
0.866 ~ 0.87
0.87
8/7
48.72
102
15/
4
35.7
MR of M6 link
15/
7
27.2
2/8
0.944
52.86
MR of M6 link
8/7
COLUMN
No.
Dimension
Quantit
y
Description
Unit
COLUMN
CONCRETE WORK
Concrete grade 1:1.5:3
5/
1.50
1.50
2.60
29.25
3.00
3.00
2.60
304.2
For column 225 x 225(C3)
6/
2.25
2.25
2.60
79.0
412.45 m3
M3
FORMWORK
Rough surface
Formwork for column 150 x 150
5/4
1.5
2.6
78.0
13/4
3.0
405.6
Rough surface
Formwork for column 150 x 150
Rough surface
Formwork for column 150 x 150
2.6
624 m2
6/4
2.25
2.60
104.4
M2
REINFORCEMENT FOR COLUMN
3.09
74.16
M
Mild steel link for column 225x225
Length of one link
0.175
0.076 - cover 2/0.038
0.099
4/0.099= 0.396
0.300 + hook 30d
0.696
0.696
129.5
3.07
61.4
0.304
105.4
MR of M6 link
GROUND BEAM
No.
Dimension
Quantit
y
Description
Unit
CONCRETE WORK
GB2
Length
add(+)column
add(+)column
1/
0.15/
0.45/
3.65/
0.246
1/
0.15/
0.45/
1.61/
0.109
1/
0.15/
0.45/
1.64/
0.15/
0.45/
3.2/
0.443
0.216
M3
=1830
=75
=112.5
1642.5
M3
= 1830
=75
=150
1605
1/
= 3350
=150
=150
3650
M3
= 3350
=75
=75
3125
M3
M3
GB19
Length
add(+)column
add(+)column
1/
1/
1/
1/
1/
1/
0.15/
0.45/
6.96/
0.15/
0.45/
6.10/
0.15/
0.45/
4.70/
0.15/
0.45/
3.09/
0.15/
0.45/
4.96/
0.15/
0.35/
0.47
0.412
0.209
0.335
M3
= 5180
=75
=150
4955
M3
= 3350
=150
=112.5
3087.5
GB14
Length
less(-)column
less(-)column
M3
= 4870
=75
=75
4720
GB10
Length
less(-)column
less(-)column
M3
= 5800
=150
=150
6100
GB6
Length
less(-)column
less(-)column
0.319
= 6700
=112.5
=150
6962.5
= 3350
=75
=150
3125
M3
1.64/
1/
1/
1/
0.15/
0.45/
13.41/
0.15/
0.45/
17.1/
0.15/
0.45/
1.97/
0.164
GB28
Length
add(+)column
less(-)column
0.906
1.15
=13410
=112.5
=112.5
13410
GB23
Length
less(-)column
less(-)column
M3
= 17400
=150
=150
17100
0.133
M3
M3
= 1820
=75
=75
1970
M3
FORMWORK
Vertical inner side:
Gb34, GB29
Side length
add(+)column
less(-)column
2/
0.45/
5.65/
5.09
= 5800
=75
=75
5800
5.09 m sawn timber
GB23
Side length
less(-)column
less(-)column
less(-)column
=17380
=75
=3/150
=75
M2
2/
0.45/
16.78
15.1
16780
15.1 m sawn timber
Side length
less(-)column
less(-)column
less(-)column
1/
0.45/
16.63/
7.48
=17380
=75
=4/150
=75
16630
7.48 m sawn timber
M2
M2
GB21
Side length
add(+)column
less(-)column
1/
0.45/
1.22/
0.55
= 1220
=75
=75
1220
0.55 m sawn timber
Side length
less(-)column
less(-)column
1/
0.45/
1.67/
0.75
= 1820
=75
=75
1670
0.75 m sawn timber
M2
M2
GB22
Side length
add(+)column
less(-)column
1/
0.45/
2.45/
1.10
= 2450
=75
=75
2450
1.10 m sawn timber
Side length
less(-)column
less(-)column
less(-)column
1/
0.45/
2.15/
0.97
= 2450
=75
=1/150
=75
2150
0.97 m sawn timber
M2
M2
GB28
Side length
less(-)column
less(-)column
less(-)column
2/
0.45/
12.36/
11.12
= 13410
=75
=4/225
=75
12360
11.12 m sawn timber
M2
vertical base:
GB23
Base length
less(-)column
less(-)column
less(-)column
1/
1/
0.15/
2.15/
0.15/
1.67/
0.32
= 2450
=75
=150
=75
2150
0.32 m sawn timber
M2
GB22
Base length
less(-)column
less(-)column
0.25
= 1820
=75
=75
1670
0.25 m sawn timber
M2
GB29
Base length
less(-)column
1/
1/
0.15/
12.06/
0.45/
1.68/
1.81
= 13410
=6/225
12060
1.81m sawn timber
M2
1.51
M2
8/
3/
Side length
less(-)column
less(-)column
0.45/
3.20/
12.6
0.45/
1.37/
1.85
=3350
=75
=75
3200
12.6 m sawn timber
GB6, inner GB19
Side length
= 1520
add(+)column
=75
less(-)column
=75
1370
M2
M2
1.85 m sawn timber
2/
8/
0.45/
3.16/
0.45/
1.64/
GB10
Side length
less(-)column
less(-)column
2.84
5.9
= 1820
=112.5
=75
3162.5
2.84 m sawn timber
7/GB4, inner GB19
Side length
= 1830
less(-)column
=112.5
less(-)column
=75
1642.5
5.9 m sawn timber
REINFORCEMENT
RB 2 (F-G)
Reinforcement bar:
Top
2T12
bottom
2T12
Length
= 3.35
M2
M2
Less(-) cover
2/0.038
Add (+)bend
2/5d
2/2
3.54
14.16
= 0.076
=0.12
3.54
14.16m T12
Stirrup:
150
450
Length
Less(-) cover
Width
Less(-) cover
=0.450
2/0.038
0.374
=0.15
2/0.038
0.074
Length = 0.374 + 0.074
= 0.45
Total length
=2/0.45
Add(+) anchor
24d
1.05
No of stirrup
Length
=3.35
Less(-)column =0.150
Total length
=3.225
(3.225/1.05)+ 1
=4 nos
1/4/
1.05
4.2
M
4.2m-R6
RB 6 (F-G)
Reinforcement bar:
Top
2T12
bottom
2T16
Length
= 3.35
Add (+)bend
2/5d
2
3.54
7.08
= 0.076
=0.12
3.54
=0.16
3.58
7.08m T12
Add (+) bend
2/5d
2
3.58
7.08
7.08m T16
Stirrup:
150
450
Length
Less(-) cover
=0.450
2/0.038
0.374
Width
Less(-) cover
=0.15
2/0.038
0.074
Length = 0.374 + 0.074
= 0.45
Total length
=2/0.45
Add(+) anchor
24d
1.05
No of stirrup
Length
=3.35
Less(-)column =0.150
Total length
=3.225
(3.225/1.05)+ 1
=4 nos
1/31
/
1.14
4.2
M
4.2m-R6
RB 9 (F-G)
Reinforcement bar:
Top
2T12
bottom
2T16
Length
= 3.35
= 0.076
2/5d
3.54
7.08
=0.12
3.54
=0.16
3.584
7.08m T12
Add (+) bend
2/5d
3.58
7.16
7.16m T16
Stirrup:
150
450
Length
Less(-) cover
=0.450
2/0.038
0.374
Width
Less(-) cover
=0.15
2/0.038
0.074
Length = 0.374 + 0.074
= 0.45
Total length
=2/0.45
Add(+) anchor
24d
1.05
No of stirrup
Length
=3.35
Less(-)column =0.150
Total length
=3.225
(3.225/1.05)+ 1
=4 nos
1.05
1/4/
4.2
M
4.2m-R6
RB 14(F-G)
Reinforcement bar:
Top
2T12
bottom
2T16
Length
= 3.35
7.08
=0.12
3.54
=0.16
3.584
7.08m T12
Add (+) bend
2/5d
3.58
= 0.076
7.16
7.16m T16
Stirrup:
150
450
Length
Less(-) cover
=0.450
2/0.038
0.374
Width
Less(-) cover
=0.15
2/0.038
0.074
Length = 0.374 + 0.074
= 0.45
Total length
=2/0.45
Add(+) anchor
24d
1.05
No of stirrup
Length
=3.35
Less(-)column =0.150
Total length
=3.225
(3.225/1.05)+ 1
=4 nos
1.05
1/4
4.2
M
4.2m-R6
RB 14 (G-H)
Reinforcement bar:
Top
2T12
bottom
2T16
Length
= 1.83
= 0.076
Add (+)bend
2/5d
=0.12
2.03
4.06
2.024
=0.16
2.184
4.06m T12
Add (+) bend
2/5d
2.18
4.36
4.36m T16
Stirrup:
150
450
Length
Less(-) cover
=0.450
2/0.038
0.374
Width
Less(-) cover
=0.15
2/0.038
0.074
Length = 0.374 + 0.074
= 0.45
Total length
=2/0.45
Add(+) anchor
24d
1.05
No of stirrup
Length
=1.83
Less(-)column =0.150
Total length
=1.68
(1.68/1.05)+ 1
=3 nos
1.05
1/3
3.2
M
3.2m-R6
RB 19(F-G)
Reinforcement bar:
Top
2T12
bottom
2T16
Length
= 3.35
14.16
= 0.076
=0.12
3.54
14.16m T12
Stirrup:
150
450
Length
Less(-) cover
Width
Less(-) cover
=0.450
2/0.038
0.374
=0.15
2/0.038
0.074
Length = 0.374 + 0.074
= 0.45
Total length
=2/0.45
Add(+) anchor
24d
1.05
No of stirrup
Length
=3.35
Less(-)column =0.150
Total length
=3.225
(3.225/1.05)+ 1
=4 nos
1.05
4.2
1/4
M
4.2m-R6
RB 33 (G-H)
Reinforcement bar:
Top
2T12
bottom
2T12
Length
= 1.83
8.12
= 0.076
=0.12
2.024
8.12m T12
Stirrup:
150
450
Length
=0.450
Less(-) cover
2/0.038
0.374
Width
Less(-) cover
=0.15
2/0.038
0.074
Length = 0.374 + 0.074
= 0.45
Total length
=2/0.45
Add(+) anchor
24d
1.05
No of stirrup
Length
=1.83
Less(-)column =0.150
Total length
=1.68
(1.68/1.05)+ 1
=3 nos
1.05
3.2
1/3
M
3.2m-R6
RB 23 (1-2)
Reinforcement bar:
Top
2T12/T20
bottom
2T20
TOP
Length
= 3.78
7.76
= 0.038
=0.06
3.877
7.76m T12
2.58
2T20
Length = 1.29 +1.29
= 2.58m
2.58m T20
Add (+) bend
2/5d
BOTTOM
Length
=0.16
2.184
= 4.57
8.9
= 0.076
=0.2
4.444
8.9m T20
Stirrup:
150
450
Length
Less(-) cover
=0.450
2/0.038
0.374
Width
Less(-) cover
=0.15
2/0.038
0.074
Length = 0.374 + 0.074
= 0.45
Total length
=2/0.45
Add(+) anchor
24d
1.05
No of stirrup
Length
=17.38
Less(-)column =0.150
Total length
=17.23
(17.23/1.05)+ 1
=18 nos
1.05
18.9
1/18
M
18.9m-R6
RB 23 (2-4A)
Reinforcement bar:
Top
2T12/T20
bottom
2T16
TOP
Length
3.30
= 3.30
6.60
M
6.60m T12
Length
2.58
= 2.58
5.16
M
5.16m T20
BOTTOM
Length
= 5.49
11.06
11.06m T16
= 0.038
=0.08
5.53
2.58
2T20
Length = 1.29 +1.29
= 2.58m
2.58m T20
Add (+) bend
2/5d
BOTTOM
Length
=0.16
2.184
= 4.57
8.9
= 0.076
=0.2
4.444
8.9m T20
Stirrup:
150
450
Length
Less(-) cover
Width
Less(-) cover
=0.450
2/0.038
0.374
=0.15
2/0.038
0.074
Length = 0.374 + 0.074
= 0.45
Total length
Add(+) anchor
=2/0.45
24d
1.05
No of stirrup
Length
=17.38
Less(-)column =0.150
Total length
=17.23
(17.23/1.05)+ 1
=18 nos
1.05
35.34
1/18
M
18.9m-R6
RB 23 (4A-4B)
Reinforcement bar:
Top
2T16
bottom
2T12
TOP
Length
1.675
= 1.675
3.35
M
3.35m T16
BOTTOM
Length
= 1.20
= 0.076
Add (+)bend
2/5d
1.394
2
2.79
=0.12
1.394
M
2.79m T12
Stirrup:
150
450
Length
Less(-) cover
=0.450
2/0.038
0.374
Width
Less(-) cover
=0.15
2/0.038
0.074
Length = 0.374 + 0.074
= 0.45
Total length
=2/0.45
Add(+) anchor
24d
1.05
No of stirrup
Length
=1.2
Less(-)column =0.15
Total length
=1.05
(1.68/1.05)+ 1
=2 nos
1.05
2.1
1/2
M
2.1m-R6
RB 23(4B-6)
Reinforcement bar:
Top
2T12/T20
bottom
2T12
TOP
Length
= 2.70
2.70
5.40
M
5.40m T12
Length
2.0
2
= 2.0
4.0
M
4.0m T20
BOTTOM
Length
= 3.70
7.80
= 0.076
=0.12
3.90
7.80m T12
Stirrup:
150
450
Length
Less(-) cover
=0.450
2/0.038
0.374
Width
=0.15
Less(-) cover
2/0.038
0.074
Length = 0.374 + 0.074
= 0.45
Total length
=2/0.45
Add(+) anchor
24d
1.05
No of stirrup
Length
=3.70
Less(-)column =0.150
Total length
=3.55
(3.55/1.05)+ 1
=5nos
1.05
1/5
5.25
M
5.25m-R6
RB 23 (6-7)
Reinforcement bar:
Top
2T12
bottom
2T12
TOP
Length
= 2.55
5.3
=0.06
2.647
5.30m T12
BOTTOM
Length
= 3.05
6.49
=0.12
3.244
6.49m T12
Stirrup:
150
450
Length
Less(-) cover
=0.450
2/0.038
0.374
Width
=0.15
Less(-) cover
2/0.038
0.074
Length = 0.374 + 0.074
= 0.45
Total length
=2/0.45
Add(+) anchor
24d
1.05
No of stirrup
Length
=3.05
Less(-)column =0.150
Total length
=2.90
(2.90/1.05)+ 1
=4nos
1.05
4.2
1/4
4.2m-R6
RB 23 (1-2)
Reinforcement bar:
Top
2T12/T20
bottom
2T20
TOP
Length
= 3.78
7.76
= 0.038
=0.06
3.877
7.76m T12
2.58
5.16
2T20
Length = 1.29 +1.29
= 2.58m
5.16m T20
Add (+) bend
2/5d
BOTTOM
Length
=0.16
2.184
= 4.57
8.9
= 0.076
=0.2
4.444
8.9m T20
Stirrup:
150
450
Length
Less(-) cover
Width
Less(-) cover
=0.450
2/0.038
0.374
=0.15
2/0.038
0.074
Length = 0.374 + 0.074
= 0.45
Total length
=2/0.45
Add(+) anchor
24d
1.05
No of stirrup
Length
=4.57
Less(-)column =0.150
Total length
=4.42
(4.42/1.05)+ 1
=6 nos
1.05
6.3
1/6
M
6.3m-R6
RB 23 (2-4)
Reinforcement bar:
Top
2T12
bottom
2T12
Length
= 4.88
Add (+)column
=0.15
Less(-) cover
= (2)0.038
Add (+)bend
2/5d
5.074
2/2
20.30
=0.12
5.074
20.30m T12
Stirrup:
150
450
Length
Less(-) cover
Width
Less(-) cover
=0.450
=2/0.038
0.374
=0.15
2/0.038
0.074
Length = 0.374 + 0.074
= 0.45
Total length
Add(+) anchor
=2/0.45
24d
1.05
No of stirrup
Length
=4.88
Less(-)column =0.150
Total length
=4.73
(4.73/1.05)+ 1
=6 nos
1.05
6.3
1/6
M
6.3m-R6
RB 23(4B-6)
Reinforcement bar:
Top
2T12/T20
bottom
2T12
TOP
Length
= 2.70
2.70
5.40
M
5.40m T12
Length
2.0
= 2.0
4.0
M
4.0m T20
BOTTOM
Length
= 3.70
7.80
= 0.076
=0.12
3.90
7.80m T12
Stirrup:
150
450
Length
Less(-) cover
=0.450
2/0.038
0.374
Width
Less(-) cover
=0.15
2/0.038
0.074
Length = 0.374 + 0.074
= 0.45
Total length
=2/0.45
Add(+) anchor
24d
1.05
No of stirrup
Length
=3.70
Less(-)column =0.150
Total length
=3.55
(3.55/1.05)+ 1
=5nos
1.05
5.25
1/5
M
5.25m-R6
RB 23 (6-7)
Reinforcement bar:
Top
2T12
bottom
2T12
TOP
Length
= 2.55
5.3
5.30m T12
=0.06
2.647
BOTTOM
Length
= 3.05
Add (+)bend
5d
3.244
2
6.49
=0.12
3.244
6.49m T12
Stirrup:
150
450
Length
Less(-) cover
=0.450
2/0.038
0.374
Width
=0.15
Less(-) cover
2/0.038
0.074
Length = 0.374 + 0.074
= 0.45
Total length
=2/0.45
Add(+) anchor
24d
1.05
No of stirrup
Length
=3.05
Less(-)column =0.150
Total length
=2.90
(2.90/1.05)+ 1
=4nos
1.05
4.2
1/4
M
4.2m-R6
SLAB
No.
Dimension
Quantit
y
Description
Unit
SLAB
CONCRETE WORK
Mass Concrete
1/
1/
5.80
1.83
0.125
6.06
3.35
0.100
4-6 / G-H
1.33
1.33 m
1-2 / F-G
2.03
2.03 m
1/
4.56
3.05
0.125
M3
M3
2-4B / F-G
1.74
M3
1.74 m
1/
1/
1/
3.70
3.35
0.125
3.05
3.35
0.125
1.52
1.22
0.125
4B-6 / F-G
1.55
1.55 m
1.28
6-7 / F-G
1.28 m
M3
M3
0.23
M3
2-3 / E1-F
0.23 m
1/
1.82
1.83
0.125
M3
1A-3 / E-E1
1/
3.64
3.35
0.125
0.42 m
1.52
M3
1/
5.50
3.35
0.125
3-4A / E-F
2.30
1.52 m
M3
1/
2.45
1.52
4A-6A / E-F
0.125
0.47
M3
2.30 m
1/
1.55
1.83
0.125
6A-7 / E1-F
0.35
M3
0.47 m
1/
0.90
1.83
0.125
6A-6B / E-E1
0.21
0.35 m
M3
6B-7 / E-E1
0.21m3
2/
2/
5.80
0.125
1.45
1.83
0.125
0.46
M2
FORMWORK
2/
2/
6.06
0.100
1.21
3.35
0.100
0.67
M2
2/
4.56
0.125
1.14
2/
3.05
0.125
0.76
2/
3.70
0.125
0.93
2/
3.35
0.125
0.84
2/
3.05
0.125
0.76
2/
3.35
0.125
1.91 m
M2
1.88 m2
M2
1.90 m
0.84
M2
1.77 m2
2/
2/
2/
2/
1.52
0.125
0.38
1.22
0.125
0.31
1.82
0.125
0.46
1.83
0.125
0.46
M2
1.60 m
M2
2/
2/
2/
2/
2/
2/
3.64
0.125
0.91
3.35
0.125
0.84
5.50
0.125
1.38
3.35
0.125
0.84
2.45
0.125
0.61
1.52
0.125
0.38
0.69 m
0.92 m
2/
1.55
0.125
0.39
1.83
0.125
0.46
2/
0.90
0.125
0.23
1.83
0.125
0.46
M2
2.22 m
2/
M2
M2
1.75 m
2/
M2
M2
1.00 m
10/
5.856
0.85 m
0.69 m
58.56
REINFORCEMENT
4-6 / G-H
y-direction
R8-200
29/
1.886
54.69
5.800
- 0.024 (- 2cover)
5.776
+ 0.080 (+ 2bends)
5.856
2/0.012
2/5d
2/0.012
+ 0.080 (+ 2bends)
1.886
2/5d
17/
6.116
103.97
1-2 / F-G
y-direction
R8-200
6.060
- 0.024 (- 2cover)
6.036
+ 0.080 (+ 2bends)
6.116
31/
3.406
105.59
No of steel
3326/200 = 16.63
17
103.97m R8
x-direction
R8-200
3.350
- 0.024 (- 2cover)
3.326
+ 0.080 (+ 2bends)
3.406
31/
4.616
73.86
2-4B / F-G
y-direction
R8-200
16/
3.106
71.44
4.560
- 0.024 (- 2cover)
4.536
+ 0.080 (+ 2bends)
4.616
Total length required steel
( 3050 -12 -12 ) = 3026
No of steel
3026/200 = 15.13
16
73.86m R8
x-direction
R8-200
3.050
- 0.024 (- 2cover)
3.026
+ 0.080 (+ 2bends)
3.106
17/
3.756
63.85
4B-6 / F-G
y-direction
R8-200
19/
3.386
64.33
3.700
- 0.024 (- 2cover)
3.676
+ 0.080 (+ 2bends)
3.756
x-direction
R6-200
3.350
- 0.024 (- 2cover)
3.326
+ 0.060 (+ 2bends)
3.386
16/
3.406
54.50
6-7 / F-G
y-direction
R8-200
17/
3.106
52.80
3.350
- 0.024 (- 2cover)
3.326
+ 0.080 (+ 2bends)
3.406
x-direction
R8-200
3.050
- 0.024 (- 2cover)
3.026
+ 0.080 (+ 2bends)
3.106
6/
1.556
9.34
2-3 / E1-F
y-direction
R8-200
1.500
- 0.024 (- 2cover)
8/
1.276
10.21
1.476
+ 0.080 (+ 2bends)
1.556
x-direction
R8-200
1.220
- 0.024 (- 2cover)
1.196
+ 0.080 (+ 2bends)
1.276
Total length required steel
( 1520 -12 -12 ) = 1496
No of steel
1496/200 = 7.48
8
10.21m R8
9/
1.886
16.97
1A-3 / E-E1
y-direction
R8-200
10/
1.876
18.76
1.830
- 0.024 (- 2cover)
1.806
+ 0.080 (+ 2bends)
1.886
x-direction
R8-200
1.820
- 0.024 (- 2cover)
1.796
+ 0.080 (+ 2bends)
1.876
0.57
17/
3.696
62.83
3-4A / E-F
y-direction
R8-200
3.640
- 0.024 (- 2cover)
19/
3.406
64.71
3.616
+ 0.080 (+ 2bends)
3.696
x-direction
R8-200
3.350
- 0.024 (- 2cover)
3.326
+ 0.080 (+ 2bends)
3.406
Total length required steel
( 3640 -12 -12 ) = 3616
No of steel
3616/200 = 18.08
19
64.71m R8
17/
5.556
94.45
4A-6A / E-F
y-direction
R8-200
28/
3.406
95.37
5.500
- 0.024 (- 2cover)
5.476
+ 0.080 (+ 2bends)
5.556
x-direction
R8-200
3.350
- 0.024 (- 2cover)
3.326
+ 0.080 (+ 2bends)
3.406
Total length required steel
( 5500 -12 -12 ) = 5476
No of steel
5476/200 = 27.38
28
95.37m R8
8/
2.506
20.05
6A-7 / E1-F
y-direction
R8-200
13/
1.576
20.49
2.450
- 0.024 (- 2cover)
2.426
+ 0.080 (+ 2bends)
2.506
x-direction
R8-200
1.520
- 0.024 (- 2cover)
1.496
+ 0.080 (+ 2bends)
1.576
Total length required steel
( 2450 -12 -12 ) = 2426
No of steel
2426/200 = 12.13
13
20.49m R8
8/
1.886
15.09
6A-6B / E-E1
y-direction
R8-200
10/
1.606
16.06
1.830
- 0.024 (- 2cover)
1.806
+ 0.080 (+ 2bends)
1.886
Total length required steel
( 1550 -12 -12 ) = 1526
No of steel
1526/200 = 7.63
8
15.09m R8
x-direction
R8-200
1.550
- 0.024 (- 2cover)
1.526
+ 0.080 (+ 2bends)
1.606
Total length required steel
( 1830 -12 -12 ) = 1806
No of steel
1806/200 = 9.03
10
16.06m R8
15/
4
1.700
8/4
15/
4
2.43
M
8/4
2.92
1.35
6A-6B / E-E1
y-direction
R8-200
1.94
0.17
15/
5
1.830
- 0.024 (- 2cover)
1.806
+ 0.080 (+ 2bends)
1.886
0.34
x-direction
R8-200
0.32
1.886
5/
9.43
1.550
- 0.024 (- 2cover)
1.526
+ 0.080 (+ 2bends)
1.606
Total length required steel
( 1830 -12 -12 ) = 1806
No of steel
1806/200 = 9.03
10
16.06m R8
6B-7 / E-E1
y-direction
R8-200
0.956
10/
9.56
1.830
- 0.024 (- 2cover)
1.806
+ 0.080 (+ 2bends)
1.886
Total length required steel
( 900 -12 -12 ) = 876
No of steel
876/200 = 4.38
5
9.43m R8
x-direction
R8-200
0.900
- 0.024 (- 2cover)
0.876
+ 0.080 (+ 2bends)
0.956
Total length required steel
( 1830 -12 -12 ) = 1806
No of steel
1806/200 = 9.03
10
9.56m R8
ROOF BEAM
No.
Dimension
Quantit
y
Description
Unit
CONCRETE WORK
RB15
Length
less(-)column
less(-)column
1/
0.15/
0.35/
4.96/
0.26
1/
0.23/
0.35/
13.41/
1.08
0.15/
0.35/
3.39/
0.178
1/
0.15/
0.35/
17.16/
0.901
M3
= 3350
=112.5
=75
3387.5
M3
= 13410
=112.5
=112.5
13410
1/
= 5180
=75
=150
4955
M3
= 17380
=75
=150
17155
M3
RB6
Length
less(-)column
less(-)column
1/
0.15/
0.35/
4.75/
0.248
RB20
Length
add(+)column
add(+)column
1/
0.15/
0.35/
6.96
0.37
4/
1/
0.15/
0.35/
3.65/
0.15/
0.35/
1.64/
0.15/
0.184
0.344
M3
= 1830
=75
=112.5
1642.5
M3
= 3350
=150
=150
3500
M3
= 6700
=112.5
=150
6962.5
RB2
Length
add(+)column
add(+)column
1/
= 4870
=75
=75
4720
= 3350
=75
=150
M3
0.35/
3.13/
1/
1/
0.15/
0.35/
1.97/
3125
0.164
RB22
Length
add(+)column
add(+)column
0.103
0.15/
0.35/
2.05/
1/
0.15/
0.35/
17.16/
0.15/
0.35/
6.1/
0.90
0.32
M3
= 5800
=150
=150
6100
RB10
Length
M3
= 17380
=75
=150
17155
RB34
Length
add(+)column
add(+)column
M3
=2050
=75
=75
2050
RB24
Length
less(-)column
less(-)column
M3
= 1820
=75
=75
1970
RB23
Length
add(+)column
less(-)column
0.11
1/
= 3350
M3
1/
1/
0.15/
0.35/
1.64/
0.15/
0.45/
1.97/
less(-)column
less(-)column
0.164
RB21
Length
add(+)column
add(+)column
0.133
=75
=150
3125
M3
= 1820
=75
=75
1970
M3
FORMWORK
1/
0.35/
2.45/
0.86
1/
0.35/
0.75/
0.26
= 900
=75
=75
750
0.26 m sawn timber
M2
Side length
less(-)column
less(-)column
1/
0.35/
1.44/
0.49
= 1550
=75
=75
1440
0.49 m sawn timber
M2
RB29
M2
Side length
add(+)column
less(-)column
1/
0.35/
1.22/
0.43
= 1220
=75
=75
1220
0.43 m sawn timber
Side length
add(+)column
less(-)column
1/
0.35/
1.82/
0.64
= 1820
=75
=75
1820
0.64 m sawn timber
M2
M2
RB29
Side length
less(-)column
less(-)column
1/
0.35/
1.6/
0.56
= 1820
=112.5
=112.5
1595
0.56 m sawn timber
Side length
less(-)column
less(-)column
1/
1/
0.35/
2.42/
0.85
= 3640
=112.5
=112.5
2415
0.85 m sawn timber
M2
Side length
less(-)column
less(-)column
0.35/
5.28/
1.85
= 5500
=112.5
=112.5
5275
1.85 m sawn timber
M2
Side length
less(-)column
less(-)column
1/
0.35/
1.33/
0.47
= 1500
=112.5
=112.5
1325
0.47 m sawn timber
M2
M2
Side length
less(-)column
less(-)column
1/
0.35/
0.68/
0.24
= 900
=112.5
=112.5
675
0.24 m sawn timber
M2
RB34,RB33
Side length
less(-)column
less(-)column
2/
0.35/
5.65/
3.96
= 5800
=75
=75
5650
3.96 m sawn timber
M2
RB34,RB33
Side length
less(-)column
less(-)column
2/
0.35/
2.90/
2.03
= 3050
=75
=75
2900
2.03 m sawn timber
Side length
less(-)column
less(-)column
2/
0.35/
3.55/
2.49
= 3700
=75
=75
3550
2.49 m sawn timber
M2
Side length
less(-)column
less(-)column
2/
0.35/
5.91/
4.14
= 6060
=75
=75
5910
4.14 m sawn timber
M2
Side length
less(-)column
less(-)column
2/
0.35/
4.35/
3.05
= 4570
=75
=150
4345
3.05 m sawn timber
M2
RB24
Side length
less(-)column
less(-)column
1/
0.45/
= 7050
=75
=75
7800
M2
3.65/
2.73
M2
RB24
Side length
less(-)column
less(-)column
1/
0.35/
4.71/
1.65
= 4860
=75
=75
4710
1.65 m sawn timber
M2
5/2/
3/2/
1/2/
0.35/
1.68/
0.35/
1.68/
0.35/
1.83/
11.48
M2
RB4
Side length
less(-)column
less(-)column
3.53
1.28
= 1830
=75
=75
1680
3.53 m sawn timber
Side length
add(+)column
=75
M2
= 1830
=75 less(-)column
M2
1830
1.28 m sawn timber
3/
0.35/
1.37/
1.44
RB6
Side length
less(-)column
less(-)column
= 152
=75
=75
1370
M2
2/
0.35
1.68/
1.18
RB9
Side length
less(-)column
less(-)column
= 1830
=75
=75
1680
1.18 m sawn timber
M2
Horizontal base:
1/
5/
2/
5/
0.15/
1.68/
0.15/
3.2/
0.15/
1.37/
0.15/
1.64/
0.25
2.4
RB9,RB15
Base length
less(-)column
less(-)column
= 1830
=75
=150
1680
0.25 m sawn timber
RB20,RB15,RB10,RB6,RB2
Base length
= 3350
less(-)column
=75
less(-)column
=75
3200
2.4 m sawn timber
0.41
RB20,RB6
Base length
less(-)column
less(-)column
1.23
RB20,4/RB4
Base length
less(-)column
less(-)column
= 1520
=75
=75
1370
0.41m sawn timber
= 1830
=112.5
=75
1642.5
1.23m sawn timber
M2
M2
M2
M2
1/
0.15/
3.16/
0.47
RB11
Base length
less(-)column
less(-)column
= 3350
=112.5
=75
3162.5
0.47m sawn timber
M2
vertical base:
1/
2/
2/
2/
0.15/
5.65/
0.15/
2.9/
0.15/
3.55/
0.15/
4.42/
0.85
RB35
Base length
less(-)column
less(-)column
0.87
RB33,RB24
Base length
less(-)column
less(-)column
1.07
Base length
less(-)column
less(-)column
M2
1.32
Base length
less(-)column
less(-)column
M2
= 5800
=75
=75
5650
0.85 m sawn timber
= 3050
=75
=75
2900
0.87 m sawn timber
= 3700
=75
=75
1370
1.07m sawn timber
= 4570
=75
=75
4420
1.32m sawn timber
RB33
Base length
= 3960
M2
M2
1/
1/
1/
1/
0.15/
3.81/
0.15/
1.95/
0.15/
1.05/
0.15/
4.71/
0.57
less(-)column
less(-)column
=75
=75
3810
0.57m sawn timber
M2
0.29
Base length
less(-)column
less(-)column
M2
0.16
RB24
Base length
less(-)column
less(-)column
M2
0.71
Base length
less(-)column
less(-)column
M2
= 2100
=75
=75
1950
0.29m sawn timber
= 1200
=75
=75
1050
0.16m sawn timber
= 4860
=75
=75
4710
0.71m sawn timber
Horizontal outer side:
4/
1/
0.35/
1.98/
0.35/
3.65/
2.77
RB9, RB15
Side length
add(+)column
M2
1.28
RB2
Side length
add(+)column
add(+)column
M2
= 1830
=150
1980
2.77 m sawn timber
= 3350
=150
=150
3650
1.28 m sawn timber
1/
1/
1/
0.35/
1.37/
0.35/
2.02/
0.35/
6.89/
0.48
0.71
2.41
RB6
Side length
less(-)column
less(-)column
M2
RB4
Side length
add(+)column
add(+)column
M2
RB20
Side length
add(+)column
add(+)column
M2
= 1520
=75
=75
1370
0.48 m sawn timber
= 1830
=75
=112.5
2017.5
0.71 m sawn timber
= 6700
=75
=112.5
6887.5
2.41 m sawn timber
1/
1/
1/
0.35/
5.95/
0.35/
3.05/
0.35/
8.53/
2.08
RB34
Side length
add(+)column
add(+)column
1.07
RB33
Side length
add(+)column
less(-)column
2.99
Side length
add(+)column
less(-)column
= 5800
=75
=75
5950
2.08 m sawn timber
= 3050
=75
=75
3050
1.07 m sawn timber
= 8530
=75
=75
M2
M2
M2
8530
2.99 m sawn timber
1/
0.35/
16.71/
5.85
RB29
Side length
add(+)column
less(-)column
add(+)column
= 17380
=112.5
=4/225
=112.5
2017.5
5.85 m sawn timber
M2
REINFORCEMENT
RB 23
Reinforcement bar:
Top
2T12
bottom
2T12
Length
= 2.450
2.67
10.68
= 0.05
=0.12
2.67
10.68m T12
Stirrup:
150
350
Length
=0.350
Less(-) cover
2/0.025
0.4
Width
Less(-) cover
=0.15
2/0.025
0.1
Total length
Add(+) anchor
No of stirrup
Length
Less(-)column
Less(-)column
1/12/
1.14
13.68
=2/0.5
24d
1.144
=2450
150
2/75
2150
(2150/200)+ 1
=11.7512nos
13.68m-R6
RB 20
Reinforcement bar:
Top
2T12
bottom
2T12
Length
= 6.70
7.0
28.0
28.0m T12
= 0.025
=0.12
6.995
Stirrup:
150
350
Length
Less(-) cover
=0.350
2/0.025
0.4
Width
Less(-) cover
=0.15
2/0.025
0.1
Total length
Add(+) anchor
No of stirrup
Length
Less(-)column
Less(-)column
Less(-)column
1/31/
1.14
35.34
=2/0.5
24d
1.144
=6700
2/150
112.5
150
6137.5
(6137.5/200)+ 1
=30.6831nos
35.34m-R6
RB 34
Reinforcement bar:
Top
bottom
2T12
2T12
Length
= 5.800
6.17
24.68
= 0.05
=0.12
6.17
24.68m T12
Stirrup:
150
350
Length
Less(-) cover
=0.350
2/0.025
0.4
Width
Less(-) cover
=0.15
2/0.025
0.1
Total length
Add(+) anchor
=2/0.5
24d
1.144
No of stirrup
Length
Less(-)column
1/29/
1.14
33.06
=5800
2/75
5500
(5500/200)+ 1
=28.529nos
33.06m-R6
RB 15
Reinforcement bar:
Top
2T12
bottom
2T12
Length
= 5.180
5.48
21.92
=0.12
5.48
21.92m T12
Stirrup:
150
350
Length
Less(-) cover
=0.350
2/0.025
0.4
Width
Less(-) cover
=0.15
2/0.025
0.1
Total length
Add(+) anchor
No of stirrup
Length
Less(-)column
Less(-)column
Less(-)column
1/25/
1.14
28.5
(4805/200)+ 1
=25.025nos
28.5m-R6
RB 11
=2/0.5
24d
1.144
=5180
75
150
150
4805
Reinforcement bar:
Top
2T12
bottom
2T12
Length
= 3.350
3.61
14.44
=0.12
3.61
14.44m T12
Stirrup:
150
350
Length
Less(-) cover
=0.350
2/0.025
0.4
Width
Less(-) cover
=0.15
2/0.025
0.1
Total length
Add(+) anchor
No of stirrup
=2/0.5
24d
1.144
Length
Less(-)column
Less(-)column
1/17/
1.14
19.38
=3350
112.5
75
3162.5
(3162.5/200)+ 1
=16.817nos
19.38m-R6
RB 6
Reinforcement bar:
Top
2T12
bottom
2T12
Length
= 4.870
=0.15
Less(-) cover
2/0.025
Add (+)bend
2/5d
2/2/
5.09
20.36
= 0.05
=0.12
5.09
20.36m T12
Stirrup:
150
350
Length
Less(-) cover
=0.350
2/0.025
0.4
Width
Less(-) cover
=0.15
2/0.025
0.1
Total length
Add(+) anchor
=2/0.5
24d
1.144
No of stirrup
Length
Less(-)column
1/25/
1.14
28.5
=4870
2/75
4805
(4870/200)+ 1
=24.625nos
28.5m-R6
RB 2
Reinforcement bar:
Top
2T12
bottom
2T12
Length
= 3.3500
3.75
14.88
= 0.05
=0.12
3.75
14.88m T12
Stirrup:
150
350
Length
Less(-) cover
=0.350
2/0.025
0.4
Width
Less(-) cover
=0.15
2/0.025
0.1
Total length
Add(+) anchor
No of stirrup
Length
Less(-)column
1/18/
1.14
20.52
(3345/200)+ 1
=17.718nos
20.52m-R6
=2/0.5
24d
1.144
=3350
2/75
3345
RB 4
Reinforcement bar:
Top
2T12
bottom
2T12
Length
= 1.83
2.023
32.32
= 0.025
=0.12
2.023
32.32m T12
Stirrup:
150
350
Length
Less(-) cover
=0.350
2/0.025
0.4
Width
Less(-) cover
=0.15
2/0.025
0.1
Total length
Add(+) anchor
No of stirrup
=2/0.5
24d
1.144
Length
Less(-)column
Less(-)column
1/9/
1.14
41.04
=1830
112.5
75
1643
(1643/200)+ 1
=9.219nos
M
41.40m-R6
RB 10
Reinforcement bar:
Top
2T12
bottom
2T12
Length
= 3.350
3.645
14.58
=0.12
3.645
14.58m T12
Stirrup:
150
350
Length
Less(-) cover
=0.350
2/0.025
0.4
Width
Less(-) cover
Total length
Add(+) anchor
No of stirrup
Length
Less(-)column
Less(-)column
1/13/
1.14
14.87
=0.15
2/0.025
0.1
=2/0.5
24d
1.144
=3350
150
75
2450
(2450/200)+ 1
=13.313nos
14.87m-R6
RB 22
Reinforcement bar:
Top
2T12
bottom
2T12
Length
= 1.820
=0.15
Less(-) cover
2/0.025
Add (+)bend
2/5d
2/2/
1.98
7.92
7.92m T12
Stirrup:
150
= 0.05
=0.12
1.98
350
Length
Less(-) cover
=0.350
2/0.025
0.4
Width
Less(-) cover
=0.15
2/0.025
0.1
Total length
Add(+) anchor
=2/0.5
24d
1.144
No of stirrup
Length
Less(-)column
1/25/
1.14
10.3
=18200
2/75
1670
(1670/200)+ 1
=9.359nos
10.3m-R6
RB 24
Reinforcement bar:
Top
2T12
Length (1-2)
less(-)t16
Add (+) col
Less(-) cover
= 4.57
=1.29
=0.15
= 0.025
1/2/
3.965
7.93
Add(+)lapping
Add (+)bend
= 0.5
=5d
3.965
7.93m-T12
1/2/
6.21
12.42
Length (2-4b)
= 7.0
Less(-) t12
=1.29
Add(+)lapping =0.5
6.21
12.42m T12
Length (7-4b)
Less(-) t12
Add(+)col
Less(-)cover
Add(+)lapping
Add(+)bend
1/2/
6.37
12.74
=6.76
=1.0
=0.075
=0.025
=0.5
=5d
6.37
12.74m-T12
1/2/
2.58
5.16
M
Length of T16 bar =2.58
5.16m-T16
bottom
1/2/
11.34
22.68
Length (1-4b)
Add(+)col
Less(-)cover
Add(+)lapping
Add(+)bend
2T12
=10.65
=0.15
=0.025
=0.5
=5d
11.34
22.68m-T12
Length (7-4b)
Less(-) t12
=6.76
=0.81
1/2/
6.06
12.12
Add(+)col
Less(-)cover
Add(+)bend
=0.075
=0.025
=5d
6.06
12.12m-T12
Stirrup:
150
350
Length
Less(-) cover
=0.350
2/0.025
0.4
Width
Less(-) cover
=0.15
2/0.025
0.1
Total length
Add(+) anchor
No of stirrup
Length
Less(-)column
4/150
Less(-)column
1/84
1.14
95.76
(16555/200)+ 1
=83.7784nos
95.75m-R6
=2/0.5
24d
1.144
=17380
150 Less(-)column
75
16555
RB 29
Reinforcement bar:
Top
1/2/
3.05
6.1
Length (1a-3)
Add (+) col
Less(-) cover
Add (+)bend
= 2.85
=0.113
= 0.025
=5d
3.05
6.1m-T12
1/2/
7.46
14.92
Length (4a-6a)
=3.5
Less(-) t16
=2/1.48
Add(+)lapping =2/0.5
7.46
14.92m T12
1/2/
1.55
3.1
1/2/
2.96
5.16
Length (7-6b)
Add(+)col
Less(-)cover
Add(+)lapping
Add(+)bend
=0.9
=0.113
=0.025
=0.5
=5d
1.55
3.1m-T12
4.8
9.6
Length of T16
Less(-)T12
Add(+)lapping
9.6m-T16
= 5.12
=1
=0.675
4.8
bottom
1/2/
9.61
19.22
Length (1a-6a)
Add(+)col
Less(-)cover
Add(+)lapping
Add(+)bend
2T12
=8.96
=0.113
=0.025
=0.5
=5d
9.61
19.22m-T12
1/2/
1.94
3.88
Length (7-6a)
Less(-) t12
Add(+)col
Less(-)cover
Add(+)bend
=2.45
=0.66
=0.113
=0.025
=5d
1.94
3.88m-T12
Stirrup:
225
350
Length
Less(-) cover
=0.350
2/0.025
0.4
Width
Less(-) cover
=0.225
2/0.025
0.175
Total length
Add(+) anchor
=2/0.575
24d
1.294
No of stirrup
Length
Less(-)column
Less(-)column
=17380
4/225
2/112.5
16255
1/13
1/
1.294
169.51
(16255/125)+ 1
=131.04131nos
169.51m-R6
RB 33
Reinforcement bar:
Top
4.04
8.08
Length (1a-2)
Add(+)col
Less(-)t16
Less(-)cover
Add(+)lapping
Add(+)bend
1/2/
=4.57
=0.15
=1.22
=0.025
=0.5
=5d
4.04
8.08m-T12
6.34
12.68
1/2/
Length (2-4b)
=7.06
Less(-) t16
=1.22
Add(+)lapping =0.5
6.34
12.68m T12
6.36
1/2/
12.72
Length (7-4b)
Add(+)col
Less(-)cover
Less(-)t12
Add(+)lapping
Add(+)bend
=6.75
=0.075
=0.025
=1.0
=0.5
=5d
6.36
2.44
4.88
12.72m-T12
1/2/
Length of T16 bar =2.4
4.88m-T16
bottom
12.01
24,02
1/2
Length (1a-4b)
Add(+)col
Less(-)cover
Add(+)lapping
Add(+)bend
=11.44
=0.15
=0.025
=0.5
=5d
12.01
24.02m-T12
6.05
1/2/
12.1
Length (7-4b)
Less(-) t12
Add(+)col
Less(-)cover
Add(+)bend
=6.75
=0.81
=0.075
=0.025
=5d
6.05
12.1m-T12
Stirrup:
150
350
Length
Less(-) cover
=0.350
2/0.025
0.4
Width
Less(-) cover
=0.15
2/0.025
0.1
Total length
Add(+) anchor
No of stirrup
Length
Less(-)column
4/150
Less(-)column
=2/0.5
24d
1.144
=17380
150 Less(-)column
75
16555
M
(16555/200)+ 1
=83.7784nos
96.75m-R6
BILLS OF QUANTITIES
Ite
m
no.
Description
Quanti
ty
Uni
t
Rat
e
RM
1.
2.
2.1
2.2
2.3
2.4
2.5
3.
4.
4.1
4.2
EXCAVATION WORK
Excavation of top soil , 150mm
Excavation of trench depth not exceeding 1.5m
Backfilling
Excavation for ground beam, (GB1, GB2, GB3,
GB4)
CONCRETE WORK
Footing
Concrete grade of C30 20mm aggregate for
footings
Concrete grade of C10- crusher run for lean
concrete
Concrete grade of C30 - 20mm aggregate for
stump
Column
Concrete grade of C30 for column
Ground Beam
Concrete grade of C30
Roof Beam
Concrete grade of C30
Slab
Concrete grade C30
FORMWORK
Rough surface
Rough surface
Rough surface
Rough surface
Rough surface
Rough surface
formwork
formwork
formwork
formwork
formwork
formwork
for
for
for
for
for
for
footing
stump
column
ground beam
roof beam
slab
REINFORCEMENT
Stump and Footing
Y12, 91.70
(3.142 x 0.0122 x 91.70 x 7850)
R6, 88.56
(3.142 x 0.0062 x 88.56 x 7850)
Column
11.88
8.91
9.08
10.149
m2
m3
m3
3.29
11.88
0.49
m3
m3
m3
412.45
m3
3.22
m3
7.05
m3
13.43
17.64
13.95
624
69.24
50.8
15.27
m2
m2
m2
m2
m2
m2
325.69
kg
78.56
kg
1468
kg
468.26
kg
4.5
35.6
0
17.5
0
326.
6
437.
5
326.
6
53.46
317.20
158.90
1074.5
5197.5
160.00
92801.
00
724.50
225.
0
5101.3
8
225.
0
3021.7
5
225.
0
225.
0
56.1
0
21.5
0
21.5
0
21.5
0
20.4
5
82.8
989.60
300.00
13416
1488.6
6
1038.8
6
1264.3
6
1270.2
0
0
306.40
1306
665.5
4.3
kg
5726.2
0
kg
Link,
R10, 529.5
(3.142 x 0.012 x 529.5 x 7850)
R16, 105.4
(3.142 x 0.0162 x 105.4 x 7850)
3.90
3.90
530
kg
3.90
4.4
4.5
Ground Beam
T12, 149.13 = 149.13m
(3.142 x 0.0122 x 149.13 x 7850)
T16, 40.17 = 40.17
(3.142 x 0.0162 x 40.17 x 7850)
T20, 50.18 = 50.18m
(3.142 x 0.0202 x 50.18 x 7850)
R6 for stirrups, 94.6 = 94.6m
(3.142 x 0.0042 x 954.8 x 7850)
Roof Beam
T12, = 374.49m
(3.142 x 0.0122 x 374.49 x 7850)
T16, = 24.8m
(3.142 x 0.0162 x 24.8 x 7850)
R6 for stirrups = 607.56m
(3.142 x 0.0082 x 607.56 x 7850)
Slab
R8 for y-direction, 582.9m
(3.142 x 0.0062 x 582.9 x 7850)
R8 for x-direction, 584.01m
(3.142 x 0.0052 x 584.0 x 7850)
1826.2
1
253.64
kg
495.06
kg
84
kg
5093.4
0
3.90
2595.5
0
3.90
1330
kg
156.6
kg
3.90
539.5
2012.7
0
kg
963.83
3.80
230
230
kg
3.80
1881.3
0
3.80
319.20
3.80
5054.3
0
kg
3.80
595.00
3.80
3.80
2050.0
0
3.80
874.00
3.80
874.00
ESTIMATING
LABOUR &EQUIPMENT COST
EXCAVATION BY MANUAL
(a)
1 1/3 hr
1 1/3 hr
2 2/3 hr
RM 9.17
RM 10.55
RM 422.20
EQUIPMENT COST
Cost Of Renting Excavator
Cost of excavator
RM
805.00
RM
80.50
Transportation to site
RM
40.23
RM
925.73
RM
0.57
- RM 805.00x [1/20]
Driver
RM 95.00
Unskilled labour
RM 55.00
36 liters of diesel - 2 x 36
RM 72.00
RM 90.00
RM 312.00
RM 39.00
RM 39.57
RM [39.57/8] x 1.15
=
=
RM 5.68
RM 227.31
Unskilled workers
Formwork
Concrete work
Reinforcement
Formwork
Concrete work
Reinforcement
Formwork
Concrete work
Reinforcement
Formwork
Concrete work
Reinforcement
Foundations
Columns
Beams
Slabs
= 451.81 x 0.0018
= 0.81m3
Cost of cement
= RM15451.90/ 451.81
= RM 34.20
Operating cost:
1. Workers;
a) Skilled workers
= 2 x RM85.00
= RM170.00
b) Unskilled workers
= 4 x RM 55.00
= RM 220.00
= 2 x rm85.00
= rm170.00
b) Unskilled workers
= 4 x rm 55.00
= rm 220.00
OPERATING COST
1. Workers;
a) Skilled workers
= 2 x rm85.00
= rm170.00
b) Unskilled workers
= 4 x rm 55.00
= rm 220.00
TOTAL COST
NO ITEMS
DESCRIPTION
TOTAL BILL
(RM)
EXCAVATION COST
1.
By manual (hand)
422.20
2.
By machine
227.31
MATERIALS COST
3.
4.
5.
5825.88
6.
1748.00
6429.00
92801.00
LABOUR COST
7.
Formwork
8.
Concrete work
126306.50
9.
Reinforcement
31442.24
15937.43
281,139.55
CONCLUSION
As a conclusion, the overall cost of the project is about RM 281139.55 for a single
unit of terrace house.
REFERENCES
1.
2.
3.
http://bceqjan2010.blogspot.com
4.
http://www.designingbuildings.co.uk/wiki/Bill_of_quantities
5.
http://web.worldbank.org/WBSITE/EXTERNAL/PROJECTS/PROCUREMENT/0,,contentM
DK:
APPENDICES