Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
com
http://electrical-engineering-portal.com/electrical-distribution-architecture-in-water-treatment-plants?
utm_source=Technical+Articles&utm_campaign=a03d102dedRSS_EMAIL_CAMPAIGN_MAILCHIMP&utm_medium=email&utm_term=0_ae069f0d91-a03d102ded319127325&mc_cid=a03d102ded&mc_eid=62e44fb4ff
Electrical Distribution Architecture In Water Treatment Plants (on photo: Makis 2 Water Treatment Plant in Belgrade; credit: icce.rs)
T1
T2
T3
T4
m 3/day
(drinking water or waste water)
1K-5K
5K-50K
50K-200K
200K-1000K
Inhabitants
1K-10K
10K-100K
100K-500K
500K-1000K
Power demand
25-125 kVA
125-1250 kVA
1.25-5 MVA
5-25 MVA
Electrical Distribution
Guidance is given for the selection of Electrical Distribution architecture in water treatment plants. This includes the
selection between different possible configurations of MV and LV circuits and the implementation of back-up power
sources.
The most relevant characteristics of the electrical installation are taken into account, such as
typology, power demand, sensitivity to power interruptions,
Metering, protection and disconnection devices, located in the delivery substations are not represented on the
following diagrams. They are often specific to each Utility company and do not have an influence on the choice of
installation architecture. For each connection, one single transformer is shown for simplification purposes, but in
practice, several transformers can be connected.
For the different possible configurations, the most probable and usual set of characteristics is given in the following
table:
Configurations
Characteristic
to consider
MV
MV
MV
MV
Single line
Ring main
Duplicate
supply
Autonomous water
treatment plant T1
Water treatment
plant T2
Remote
pumping station
P3
Water
treatment
plant T4
Desalination T4
Remote pumping
station P1, P2
Water
treatment
plant T3
Desalination
T2
Desalination
T3
Service
reliability
Minimum
Minimum
Standard
Standard
Enhanced
Power
demand
1.25-5 MVA
5-25 MVA
> 25 MVA
Site topology
LV
The connection configurations may differ from the above table due to particular constraints relative to water industry
plants spread-out configuration and suburban location.
Go back to Water Treatment Plants Topics
MV circuit configuration
The three main possible connection configurations are as follows:
1. Single feeder, one or several transformers,
2. Open ring, one MV substation,
3. Open ring, 2 MV substations.
The basic configuration is a radial single-feeder architecture, with one single transformer. In the case of using several
transformers, an open ring is commonly realized for improved power availability.
High power motors may be directly supplied at MV for reduction of cable size. The preferred basic configuration
comprises one single substation. However, a larger number of substations is possible in some circumstances:
A large site,
A site with several different process lines,
Single feeder
1 substation
1 transformer
Single feeder
1 substation
N transformers
Open ring
1 or 2 substations
N transformers
(different powers)
Plant topology
Small T2
Medium T3
Large T4
Power demand
1.25 5 MVA
> 5 MVA
Load distribution
Uniform
Intermediate
Maintainability
Minimum
Standard
Enhanced
Disturbance
sensitivity
Long interruptions
acceptable
Short interruption
acceptable
Short interruption
acceptable
Configuration of LV circuits
Here are the main possible configurations, to be selected according to the requested level of power
availability //
This is the reference configuration and the most simple. A load is connected to only one single source. This
configuration provides a minimum level of availability, since there is no redundancy in case of power source failure.
Two-pole configuration
The power supply is provided by 2 transformers, connected to the same MV
line. When the transformers are close, they are generally connected in parallel to
the same Main Low Voltage Switchboard (MLVS).
Interconnected switchboards
If transformers are physically not too far from one another, they
may be connected by a busbar trunking. A critical load can be
supplied by one or other of the transformers.
The availability of power is therefore improved, since the load
can always be supplied in the case of failure of one of the sources.
The redundancy can be //
Total: each transformer being capable of supplying the whole
installation,
Partial: each transformer only being able to supply part of the
installation. In this case, part of the load must be disconnected
(load- shedding) in the case of one of the transformers failing.
Two-pole configuration
Configuration combinations
An installation can be made up of several sub-assemblies with different configurations, according to requirements for
the availability of the different types of load. E.g.: generator unit and UPS , choice by sectors (some sectors supplied
by cables and others by busbar trunking).
Go back to Water Treatment Plants Topics
Back-up generators
The electrical power supplied by a back-up generator is produced
by an alternator, driven by a thermal engine. No power can be
produced until the generator has reached its rated speed. This
type of device is therefore not suitable for an uninterrupted power
supply.
The implementation of a back-up generator should take consideration of the sensitivity of circuits to power interruptions
and the availability of the public distribution network.
Interconnected switchboards
The back-up time of the batteries must be compatible with the maximum time for the generator to
start up and be brought on-line.
A UPS unit is also used for supplying power to loads that are sensitive to disturbances (generating a clean voltage
that is independent of the network).
Award-Winning APC Symmetra Line of Uninterruptible Power Supply Unit (UPS) photo credit: apcdistributors.com
References //
Wastewater treatment plants Recommended electrical network design for efficient plant and energy
operations by Schneider Electric
Water and Wastewater Power Solution Handbook by Schneider Electric